<<

MARINE AND FOUNDATION Photo: Allan Klo TOGETHER, WEWILLTAKE YOUTHERE. how largeorsmall. to takeonthemostcomplexprojects anywhere intheworld–nomatter engineering combinedwithlocalpresence andexperience,weare ready afullsetofworld-class competencieswithinmarineandcoastal With operation phase,decommissioningorrehabilitation. the entire lifecycleofamarinestructure, from theinitialideas tothe our clients todeliverworld-classmarinestructures. Ourservicescover We are drivenbyinnovationandourambitiontoworkcloselywith technologies tostretch thelimitsofwhatispossible. position wehaveachievedbydiligentlypushingthedevelopmentofnew Today, weare aworldleader inmarineandcoastalengineering.Itisa protection, locksanddams. to equallychallengingcoolingwatersystems,offshore windfarms,flood challenging LNGterminals,containerportsandwaterfront developments projects worldwide.Theseprojects rangefrom largeandtechnically of marinedesignthrough ourinvolvementin more than3,300marine company wasfounded.Sincethen,COWIhaspushedtheboundaries COWI's historyincivilengineeringdatesbackto 1930 whenthe THINK FURTHER MARINE ANDFOUNDATION ENGINEERING 3 MARINE AND FOUNDATION ENGINEERING 5

AIN SUKHNA MARINE OIL TERMINAL - GORGON BARROW ISLAND LNG PLANT - AQABA LNG - SHTOKMAN LNG TERMINA - BATUMI TERMINAL - NEW PIER AND QUAY STOCKHOLM VÄRTAHAMNEN - HANSTHOLM - JEBEL ALI T3-Q10 CONTAINER TERMINAL - NEW YORK CITY CRUISE TERMINAL DREDGING - CALETA LA MISION PORT - NORVIKUDDEN CONTAINER AND RO-RO TERMINAL - DEVELOPMENT PLAN FOR KRONBORG CASTLE AND ELSINORE HARBOUR - LUSAIL DEVELOPMENT - MUSEUM OF ISLAMIC ART - AL ZORAH DEVELOPMENT - BEIRUT CENTRAL DISTRICT, MARINE WORKS - CASTING BASIN COSTA AZUL - QATAR - HONG KONG THREE RUNWAY SYSTEM - LONDON ARRAY - WIKINGER OFFSHORE WIND FARM - YANBU 2 POWER PLANT AND WATER PROJECT - RABIGH POWER PLANT NO 2 - NEW ORLEANS FLOOD PROTECTION BARRIER OLMSTED LOCKS AND DAM - UPPER ZAKUM ARTIFICIAL ISLANDS - AL RUWAIS PORT DEVELOPMENT - LNG LTD IMPORT TERMINAL AT MUNDRA - SHOAIBA NEW TANKER TERMINAL - LNG PROJECT, IDKU - RAS LAFFAN MARINE - RUWAIS THIRD NGL TRAIN JETTY - LARGE LIQUID TERMINAL NEW YORK – NORVIKUDDEN – FREDERIKSHAVN - SKAGEN - HVIDE SANDE - IRISH RAIL SEA - ISLAND 2 - PEARL-QATAR - ENERGINET - WIKINGER, TRANSFORMER - RØDSAND 2 - THORNTON BANK - DANTYSK - PEARL JUMEIRAH - KRIEGERS FLAK OSS - AIN SUKHNA MARINE OIL TERMINAL - GORGON BARROW ISLAND LNG PLANT - AQABA LNG - SHTOKMAN LNG TERMINAL - BATUMI TERMINAL - NEW PIER AND QUAY STOCKHOLMWHY VÄRTAHAMNEN - HANSTHOLM QATAR CHO - JEBEL ALI T3-Q10 CONTAINER TERMINALOSE - NEW YORK CITY CRUISE US? TERMINAL DREDGING - CALETA LA MISION PORT - NORVIKUDDEN CONTAINER AND RO-RO TERMINAL - DEVELOPMENT PLAN FOR KRONBORG CASTLE AND ELSINORE HARBOUR - LUSAIL DEVELOPMENT - MUSEUM OF ISLAMIC ART - AL ZORAH DEVELOPMENT - BEIRUT CENTRAL DISTRICT, MARINE WORKS - CASTING BASIN COSTA AZUL - QATAR - HONG KONG THREE RUNWAY - LONDON ARRAY - WIKINGER OFFSHORE WIND FARM - YANBU 2 POWER PLANT AND WATER PROJECT - RABIGH POWER PLANT NO 2 - NEW ORLEANS FLOOD PROTECTION BARRIER OLMSTED LOCKS AND DAM - UPPER ZAKUM ARTIFICIAL ISLANDS - AL RUWAIS PORT DEVELOPMENT - LNG LTD IMPORT TERMINAL AT MUNDRA - SHOAIBA NEW TANKER TERMINAL - LNG PROJECT, IDKU - RAS LAFFAN MARINE - RUWAIS THIRD NGL TRAIN JETTY - LARGE LIQUID TERMINAL NEW YORK – NORVIKUDDEN – FREDERIKSHAVN - SKAGEN - HVIDE SANDE - IRISH RAIL SEA - ISLAND 2 - PEARL-QATAR - ENERGINET - WIKINGER, TRANSFORMER - RØDSAND 2 - THORNTON BANK - DANTYSK - PEARL JUMEIRAH - KRIEGERS FLAK OSS - AIN SUKHNA MARINE OIL TERMINAL - GORGON BARROW ISLAND LNG PLANT - AQABA LNG - SHTOKMAN LNG TERMINAL - BATUMI TERMINAL - NEW PIER AND QUAY STOCKHOLM VÄRTAHAMNEN - HANSTHOLM QATAR - JEBEL ALI T3-Q10 CONTAINER TERMINAL - NEW YORK CITY CRUISE TERMINAL DREDGING - CALETA LA MISION PORT - NORVIKUDDEN CONTAINER AND RO-RO TERMINAL - DEVELOPMENT PLAN FOR KRONBORG CASTLE AND ELSINORE HARBOUR - LUSAIL DEVELOPMENT - MUSEUM OF I Photo: COWI illustration SERVICES Client Project period DATA with aspecificphaseforLPGtanksandberth. be completedinfivemaindevelopmentphases The entire project developmentisplannedto million tonnesperannumofvariousproducts. date future expansionstohandle upto24 The offshore facilityisintendedtoaccommo- carriers (VLCC),connectedviaaseapipeline. shore singlepointmooring forverylargecrude and otherauxiliaries.Thehubincludesanoff - (500-160,000 DWT)includingatopsidepipeline The offshore facilitycomprisesajettyandberths product storagetanksranges from 21to59m. the cityofSuez.Thediameterindividual and two50kmlongunidirectional pipelinesto tanks withatotalcapacityof2,125millionm³, onshore facilitycomprises 61 product storage hub includesonshore andoffshore facilities.The complex ontheRedSeaCoastinEgypt.The fully equippedproduct hubattheir AinSukhna Arab Petroleum PipelineCo.has establisheda AIN SUKHNAPRODUCTHUB, › › › › › › › › › › Preparation oftenderdocuments. Front endengineeringdesign(FEED) Plant layoutand3Dmodelling single baymooringandlandpipeline Concept designofmarineterminal,tankfarm, pipeline corridor Topographic surveyatfueltanksiteandland

Pipelines Co.(SUMED) Arab Petroleum 2012-2013

Photo: Saipem-Leighton Consortium › › SERVICES Client Saipem-Leigthon Project period DATA calculations. documents andperformingindependentdesign which includedcheckingmore than2,000 design verificationofthemarinefacility SLC engagedCOWItocarryouttheindependent off shore. caissons. Thejettyislocatedapproximately 2km of steeltrussesspanning70-80mbetween on gravelbeds.Aconnectingtrestle is made be prefabricated off site,towedinandplaced to 2009 basedonadesignconceptwithcaissons jetty andmarinestructure contactinNovember Leigthon Consortium(SLC)wasawarded the Gas andChubuElectricPower. TheSaipem- Corp, RoyalDutchShellPlc,OsakaGas,Tokyo Venture partnerswithChevron are ExxonMobil LNG projects inAustralia. It isthelargestofmore thanadozen planned gas fieldsoff Australia’s northwestcoast. stream athree-train 15mt/y, exploitingoffshore gas project onBarrow Islandwillbringon The Chevron-operated Gorgon liquefiednatural AUSTRALIA GORGON LNGPLANT, › › structural integrity. Independent calculationsforvalidation ofthe Independent designverification (IDV) MARINE ANDFOUNDATION ENGINEERING Consortium 2009-2014

7 MARINE AND FOUNDATION ENGINEERING 9

NEW CRUISE FERRY TERMINAL IN THE PORT OF STOCKHOLM, SWEDEN The new port facility consists of three new ferry berths and two upgraded ferry terminals. Each berth is configured with a 30 m wide movable steel ramp, submerged bulbous bow protection structures, and berth equipment.

The water depth at the berth is 11 m and the total berth length is approx. 1200 m. The suspended deck consists of double spanned prefab reinforced concrete deck elements typically 8 m x 8 m supported on prefab pile caps and approximately 1,050 tubular driven steel piles (pile length varies from 30-55 m).

All prefab elements were cast in Poland and transported to the site, placed on the pile caps and then cast together with the other prefab elements.

Along the inner edge of the suspended pile deck a double anchored steel sheet pile wall was installed to retain the new fill above the existing sea bed. In areas with un-sorted existing rock fill, large anchored prefab concrete L-walls were installed instead.

Cement-limestone piles and jet grouting were used in the reclamation areas to improve soil conditions. Rock armour was placed to protect the existing slopes and the new retaining walls from propeller scour. COWI is the design consultant for all structural design.

DATA Project period 2013-2017 Client Per Aarsleff A/S

SERVICES ›› Tender and detailed design ›› Geotechnical design ›› Marine structural design ›› Design of pavement, drainage and utlities. Photo: Stockholm Hamn MARINE AND FOUNDATION ENGINEERING 11

FREDERIKSHAVN PORT EXPANSION, BROOKLYN NAVY YARD PIER C, DENMARK RECONSTRUCTION, NY, USA The Port of Frederikshavn is expanding the Pier C, within the Brooklyn Navy Yard, was port to improve business opportunities in cargo originally constructed in the early 1900’s and handling, maritime industry, and service and was in service throughout the century. In the maintenance of off-shore structures. The pro- early 2000’s Pier C was used to berth ferry ject is divided in three phases with construction vessels for the New York Harbour. Beginning of the first phase to be completed in 2018. in 2011, the pier suffered a series of partial collapses and required replacement. In 2016, Phase 1 comprises 2.6 km of main breakwa- NYCEDC proposed the new Pier C to become ters and 600 m new quay with a water depth the Home Port for ferry vessels for the new of 11 m, but allowing for future dredging to NYC Citywide Ferry System to begin servicing 14 m. A new port area of 330,000 m2 will be New York Harbour by 2017. reclaimed using material from dredging of the new port basin and enlargement of the ap- NYCEDC retained COWI to provide the struc- proach channel to allow access of Panamax tural design for the new pier to be constructed carriers. The project also comprises quay within the same footprint as the original pier. apron, roads, drainage, water and electricity, The new pier was designed to be approximate- waste water and lighting. The total expansion ly 690 feet long by 81 feet wide with a deck is planned to comprise 2,000 m of quays and capacity of 1,000 psf and included a Travel 1,200,000 m2 of new port areas. COWI is the Lift at the offshore edge of the pier in order to project management consultant (PMC) for the service ferry vessels on the pier’s deck. Twenty- entire project. one concrete floating docks are arranged along the pier to provide berths for the ferry vessels. DATA Project period 2012 - 2018 DATA Client Frederikshavn Havn A/S Project period 2017 Client NYCEDC SERVICES ››Master plan SERVICES ››Numerical modelling of waves, currents, ›› Marine structural design sediment transport and wave agitation ›› Site plan layout ››Geotechnical investigations ›› Design of utility systems. ››Navigation studies ››Concept design and construction budget ››Environmental impact assessment ››Design of all elements and phases of the port expansion ››Tendering and contracting as design & build contract ››Assistance during construction. MARINE AND FOUNDATION ENGINEERING 13

OSLO COPENHAGEN

LONDON

AT ANY GIVEN TIME, WE ARE INVOLVED VANCOUVER HAMBURG IN MORE THAN 200 MARINE PROJECTS WORLDWIDE OAKLAND NEW YORK SEOUL

QATAR

UAE DELHI HONG KONG WORLDWIDE REACH MANILA

CHENNAI In COWI, we take pride in our achievements. Since the 1970's, we have been at the forefront of marine engineering, setting the standard KUALA LUMPUR for tomorrow’s best practices. Together with our clients, we have been SINGAPORE involved in more than 3,300 marine projects all over the world – from Argentina to the far corners of Russia.

We can take your marine project further than you imagine. COWI's key marine and coastal engineering offices are shown here. With offices, around the globe, we are never far away. And regardless of the scope of your marine construction or problem, we deliver worldwide.

All other COWI offices are listed on www.cowi.com Photo: Winther airphoto › › › › › › SERVICES Client Project period DATA phase andthesuccessivecostcalculation. Risk assessmentwasintegratedintheplanning landscape architect JeppeAagaard Andersen. in closecollaborationwiththeClientand The multidisciplinaryproject was developed and parkingforbussescars. The project alsocomprises newaccessroads create thenewKing’s QuayandtheRavelin. Most ofthesoilwasreused inthe project to architectural interpretation oftheoriginalravelin. of vonScholten’s ravelin,acontemporary recreated orrestored includingtherecreation The fortificationsaround Kronborg havebeen and 1.1kmofbenches. mately 12,000m²ofgranitepaving,lighting, promenades alongthequay walls,approxi- harbour front withnewquaywalls, wooden developed intoarecreational area withanew UNESCO worldheritagelist.Thearea has been Elsinore andKronborg Castle,whichisonthe sive renewal ofthearea betweenthetownof Cultural HarbourKronborg isacomprehen - HARBOUR, DENMARK KRONBORG CASTLEANDELSINORE › › › › › › Supervision ofworks. Cost estimations Environmental andgeotechnicalinvestigations implementation oftheentire project Project managementconsultantforthe Preparation oftenderdocuments Overall planning MARINE ANDFOUNDATION Ministry oftheInterior, Elsinore Municipality ENGINEERING 2007-2014

15 Photo: COWI › › › › › › › › SERVICES Client Project period DATA marine works. Finally, COWI supervisedconstructionofall subsquently designedmarinasandbeaches. activities ofthemarineandearthworks COWI completedtheplanninganddesign entertainment district. with topclasshotels,twogolfcoursesandan and mixeduseareas aswellquality beaches The developmentincludesbusiness,corporate residential housingforabout 200,000inhabitants. The newdevelopmentincludeslowandhighrise new islands,accesschannelsandbeaches. line through dredging andreclamation, creating The project hastransformed thepresent shore- in NewYork. size astheentire Midtown and LowerManhattan about 21km²whichisapproximately thesame the shoreline northofDoha.Itcovers anarea of The waterfront developmentislocated along QATAR LUSAIL DEVELOPMENT, › › › › › › › › Construction supervision. phase Assistance inthetenderingand contracting Preparation oftenderdocuments Conceptual anddetaileddesign Environmental impactassessment Geotechnical investigations Bathymetric andtopographicsurveys Master planning Qatari Diar/BechtelOverseas Corporation 2004-2014

Photo: London Array › › › › › › › SERVICES Client Project period DATA soil-structure interaction. geotechnical methodologyforcalculationsof Significant advanceswere introduced inthe projects tousetheconicalgrouted connection. The project isoneofthefirstoffshore wind IMS IngenieurgesellschaftmbH,COWI-IMSJV. engaged COWIasleadinajointventure with out thedetaileddesignofmonopiles,ABJV and installationofthesteelfoundations.To carry (ABJV) ascontractortoundertakefabrication missioned Aarsleff |Bilfinger BergerJoint Venture A consortiumofDONG,E.ONandMasdarcom- tonnes ayear. reduce harmfulCO ergy topowernearlyhalfamillionUKhomesand Its turbinesare capableof generating enoughen- tions are amongstthelargest everbuilt. lengthsupto85m,thesefounda- 25 m.With been installedatwaterdepthsbetween0mand Monopiles of4.7mand5.7diameterhave a peakratedpowerof630MWin2013. offshore windfarmistheworld’s largest, with Siemens 2.6MWturbines,theLondonArray 175monopiles,designedtocarrythe With WIND FARM, UK LONDON ARRAY OFFSHORE › › › › › › › Risk management. Scour assessment Cathodic protection analysisanddesign Driveability analyses Geotechnical design Structural design Hydraulic loadcalculations ² emissions by over 900,000 emissionsbyover900,000 MARINE ANDFOUNDATION Aarsleff /BilfingerBerger ENGINEERING Joint Venture 2009-2013

17 MARINE AND FOUNDATION ENGINEERING 19

WIKINGER OFFSHORE WIND FARM, GERMANY The joint venture of COWI and IMS Ingenie- urgesellschaft mbH, led by COWI, has been entrusted with the detailed design of the founda- tions and the basic design of the substation.

COWI was Iberdrola’s representative in the preliminary geophysical and geotechnical inves- tigations for the 1st German regulatory system's (BSH) release, and is finishing the detailed geo- technical investigations for the 2nd BSH release.

Before this, COWI carried out the feasibility study of the turbine foundation types, investigating concepts for monopiles, gravity based founda- tions and jacket foundations for depth variations up to 42 m. Based on our preliminary foundation design, we were awarded the basic design of the jacket foundations equipped with AREVA 5 MW turbine, for the application for the 2nd BSH release. The offshore wind farm is expected to deliver up to 400 MW.

For the offshore substation, COWI’s scope of work includes the mechanical and electrical design services in addition to the topside and jacket structure design.

DATA Project period 2010-2017 Client Iberdrola Renovables

SERVICES ›› Structural design of topside and jackets ›› Hydraulic design ›› Geotechnical design ›› Electrical and mechanical design ›› Low voltage design.

OWF App Photo: Hvide Sande Havn that extraexpertiseyouneed.Thechoiceisyours. at anygivenmomenttoprovide yourproject with We canhandletheentire project, orwecanstepin the timecomes. phase andrehabilitation –ordecommissioningwhen a marineproject from earlyideastotheoperational ourservices,wecovertheentire lifecycleof With OUR SERVICES MARINE ANDFOUNDATION ENGINEERING 21 MARINE AND FOUNDATION ENGINEERING 23 DIFFERENT PHASES SITE SUPERVISION We handle all disciplines relating to DIFFERENT SERVICES preconstruction and construction, project completion and subsequent defects liability INDEPENDENT DESIGN CHECK AND period and we deliver full project quality VALUE ENGINEERING documentation. Agility and expertise are the key to efficient marine and coastal engineering. We provide assistance to clients of complex We bring both to the table to make sure we provide you with the exact marine projects assessing if the project is RE-EVALUATION AND REHABILITATION service and expertise your project needs – regardless of where you are in reliable, safe, durable, constructable We cover all phases and every step of the the process. and optimal. inspections to ensure that technical evaluations are coherent – from visual inspections to special studies of load capacity and safety of structures.

CONSTRUCTION ENGINEERING We design rehabilitation works for existing The right selection and combination of structures for increased capacity and for construction methods is of crucial importance replacement of key structural elements. to any marine project. We handle erection schemes, logistics, temporary structures as well as the erection engineering itself. DESIGN OPERATION AND MANAGEMENT PROJECT IMPLEMENTATION We handle everything from development of Our asset management is based on worldwide We provide policy planning, advice and design basis to construction aspects as well practical experience with planning, budgeting management consulting for project decision as life-cycle design. We have state-of-the- and handling of short and long-term operation, and project implementation. art analysis tools which enable us to deliver competitive designs to tight schedules. With maintenance and rehabilitation works, as well our vast experience we can secure delivery of as implementation of management concepts. your project to quality, on time and budget. SITE STUDIES Understanding the environment in which the project is to be constructed requires knowledge obtained from various sources. The quality FEASIBILITY STUDIES CONSTRUCTION MANAGEMENT of the project depends on the accuracy and We have all the competencies to carry out We handle the contract, monitor the progress DECOMMISSIONING details of information obtained through these feasibility studies. And we take into account of the project in all details as well as cost To facilitate the choice between removal investigations. They include met-ocean data technical, environmental, social and economic control and take care of risk management. We options, we carry out quantitative, comparative gathering and assessment, seismic and aspects to establish the basis for the right also handle stakeholders and authorities and risk assessments of the various options and tsunami studies, collision/spill risk assessment decisions. perform technical follow-up. we take damaged structures, personnel and and mitigation, and navigation simulations. environmental risks into account. Photo: COWI › › › › › › › SERVICES Client Project period DATA construction ofthemarinefacilitiesbyArchirodon of technicaltenderdocumentstovendorsand design deliverablessuitabletosupporttheissue The scopeofworkincludespreparation of structures (extreme waves,currents, waterlevels). develop nearshore designconditions formarine seawater outfall.Hydraulicmodellingwasusedto facility andassociatedpumpingstationa The marinefacilitiesconsistofaseawaterintake the detaileddesign. for themarinefacilitieswithCOWIasconsultant Saudi Archirodon Ltd.wasselectedascontractor north ofJeddah. Kingdom ofSaudiArabia,approximately 280km The plantislocatedontheRedSeacoastof potable waterandseawatercooling. the increasing demandfor power, process and and waterplantforYanbu 2IndustrialCitytomeet developing anew850MW(nettothegrid)power The powerandwaterutilitycompanyMarafiqis YANBU 2POWERANDWATER PROJECT, › › › › › › › and culverts. Structural design ofpumpingstation,thrustblock structures Design ofdredging, reclamation and foundationof Design ofseawaterintakechannel andbreakwaters protection structure andGRPpipelinescovered byrock Layout anddesignofseawateroutfall transition seawater intakechannel Numerical flowmodellingforoptimisation of location ofseawaterintakeandoutfall Recirculation modellingfor confirmationofthe and hydrodynamics Met-ocean studyandnumericalmodellingofwaves MARINE ANDFOUNDATION Saudi Archirodon Ltd. ENGINEERING 2011-2016 25 Photo: COWI SERVICES Client Project period DATA services forthemarinesubcontract. COWI provided numericalmodellinganddesign ture andbreakwaters, andshore protection. pumping station,outfallchannel,struc- pipes, intakebasinsurrounded byrevetments, the powerplantanditcoversseawaterintake contract entailedaseawatercoolingsystemfor Doosan forthemarineworks.Thesub- Huta MarineWorks Ltd.wassub-contractor to Plant No.2. Company (SEC)todelivertheRabighPower procurement contract(EPC)bySaudiElectricity (Doosan) wasawarded theengineering Doosan HeavyIndustries&Construction of 700MWcapacityeachwere installed. additional fourpowergenerationunits programme forRabighPower Station,an of SaudiArabia.Asparttheexpansion Sea coast,northofJeddahintheKingdom The project islocatedinRabigh, ontheRed SAUDI ARABIA RABIGH POWERPLANTNO2, › › › › › › › › › › of marineworks. Electrical engineeringforthecathodic protection pipes Piping engineeringforintakeglass reinforced revetment, andoutfallstructure station, carriedoutinhydrauliclab,breakwater Management ofphysicalmodellingpumping Hydraulic engineeringandnumericalmodelling Huta MarineWorks Ltd. 2010-2013

Photo: COWI › › › › › › › › SERVICES Client Project period DATA the taintergates. pass segmentsandsupportedthedesignof blocks andtheliftingframefornavigable the navigablepassprecast segments,paving COWI alsocompletedtheshelldesignfor anchors anddolphins. mating detailsfortheprecast shells,mooring cradle, steelframetremie mat templates,lifting/ tem bothaboveandbelowwater, precast shell skidway railincludingbeamandfoundationsys- and steelretaining walls,gantry cranebeams, The constructiondesignencompassedconcrete segments. rine skidwayforload-outofthepre-cast shell support oftheprecast yard includingthema- navigation damandalsoconstructiondesign COWI provided thedetaileddesign forthenew downstream scourprotection. sections, afixedweirsection,andupstream and a 1,400-footnavigablepass,twoboatabutment consist ofan800-foot-longtaintergatesection, the confluencewithMississippiRiver. Itwill under construction16milesupstream from The OlmstedDamontheOhioRiveriscurrently IL, USA OLMSTED LOCKSANDDAM, › › › › › › › › Cost estimation. Seismic analysis Mooring andberthing analysis Foundation design concrete elements Detailed designofallprecast andinsitucast Heavy liftsystems Dredging Casting yards/launch system

U.S. ArmyCorpsofEngineers, MARINE ANDFOUNDATION Louisville District ENGINEERING 2005-2020 27 Client › › SERVICES Project period DATA vulnerability. a naturalfunnelidentifiedasanarea ofcritical waterway andtheMississippiRiverGulfoutlet, near theconfluenceofGulfintracoastal The IHNCbarrierwascompletedbymid-2012 ing ofthecity. along theIHNCcontributedgreatly totheflood- storm surgeduringHurricaneKatrinain2005 canal. Failures offloodwalls overwhelmedby entering NewOrleans’innerharbournavigation tion ofastormsurgebarriertokeepsurgesfrom The federallyfundedcontractwasforconstruc- construction. example ofinnovativedesignandfast-track design honorin2014;andisanexcellent American SocietyofCivilEngineers'highest States ArmyCorpsofEngineers.Itwonthe design-build project everawarded bytheUnited This $1.3billionproject isthe largestcivilworks navigation canal(IHNC)inNewOrleans. flows, andstormsurgeintotheinnerharbour which willbeusedtoregulate navigation,tidal ture; andaconcrete swingbargegate;bothof and guidewalls,forthemainsectorgatestruc- of thefloodbarrierandmonolithfoundations COWI wasresponsible for the detaileddesign BARRIER, LA,USA NEW ORLEANSFLOODPROTECTION › › protection. structure, GIWW approach walls,and scour concrete by-passbargegate,MRGOberm gate monolith,batterpilefloodwall, reinforced Concept anddetaileddesignof the mainsector Numerical modelling 2008-2012 The U. S. Army CorpsofEngineers

MARINE ANDFOUNDATION ENGINEERING 29

Photo: Shaw E&I Photo: Claus Knuth to pushtheboundariesmaximisevalueforourclients. aspects ofmarineandcoastalengineering.Andwecontinue Today, ourteamsdeliver cutting-edgeknow-howinall in thefieldofmarinestructures. techniques, theuseofnewmaterialsandtechnologies participated intheresearch anddevelopmentofnew Since wedesignedourfirstmarineproject, wehaveactively OUR TEAMS MARINE ANDFOUNDATION ENGINEERING 31 MARINE AND FOUNDATION ENGINEERING 33

DIFFERENT ASSIGNMENTS DIFFERENT COMPETENCIES

Our large pool of and experts enables the project manager to set up a team with the right competencies to match your project.

THE CONSTRUCTION THE GEOTECHNICAL THE PROJECT THE STRUCTURAL THE SEISMIC THE HYDRAULIC AND > STRUCTURAL DESIGN > DREDGING DESIGN > COST ESTIMATION > REHABILITATION ENGINEERING > WAVE SPECIALIST EXPERT MANAGER EXPERT COASTAL EXPERT MODELLING > HYDRAULIC MODELLING > SOIL STRUCTURE INTERACTION > HYDRODYNAMIC FLOW MODELLING Our construction Our geotechnical Our project manager Our senior structural Based on information Our hydraulic expert specialist works to expert specifies is responsible for engineers are from the site, our is responsible for > CURRENT MODELLING > METOCEAN STUDIES > SERVICE LIFE DESIGN > LABORATORY TESTING > SEISMIC secure the balance the geotechnical managing the contract responsible for all seismic expert determining how between design and site investigations, with the client and for basic engineering establishes spectra the hydrodynamic ANALYSES > FATIGUE ASSESSMENTS > FINITE ELEMENT ANALYSES > LIFE CYCLE COSTS > SUSTAINABLE construction. analyses the results delivering the project aspects of the and time series to be processes influence ENGINEERING > MECHANICAL AND ELECTRICAL INSTALLATION DESIGN > OPERATIONAL RISK MANAGEMENT and establishes a on agreed time and project – drawings used in the design the design and geotechnical design budget. and verification, to process. functionality of any > CONSTRUCTION RISK MANAGEMENT > NAVIGATION SIMULATION > MASTER PLANNING > STRUCTURAL DYNAMICS basis for the project. secure practical structure. buildable structures. > SHIP COLLISION RISK > UTILITIES > BUILDING DESIGN > MODEL TEST VERIFICATIONS > SHIP IMPACT PROTECTION

> MOORING ANALYSES > HAZID/HAZOP > BIM

Photo: COWI › › › › › › › SERVICES Client Project period DATA surveying consultancyservicesforconstruction. general andsitesupervisionquantity COWI provided post-contract professional and landscapingincludingirrigation). drainage, LV, HVandELV, telecommunication ties (sewerage,potablewater, surfacewater In addition,there are serviceroads andallutili- and blockpaving. storage tanksanddispensers,gantrycranes port furniture, floatingpontoons,slipways,fuel navigation aids,rock revetments, utilitiesand reclamation, concrete blockquaywalls,fenders, The marineconstructionworkincludeddredging, and vegetables,livestockbuildingmaterials. traffic importinggeneralcargo includingfruit coastal tradingvesselsandpassenger/carferry with newfacilitiestoaccommodatedhows, the developmentofexistingfishingport 120 kmnorthofDoha.Theproject comprises Al RuwaisPortislocatedapproximately QATAR AL RUWAIS DEVELOPMENT, PORT › › › › › › › Site supervision. Post contractquantitysurveying Record documentation As-built drawingreview Quality assuranceprogram Redesign ofmarineworks Project management Public Works Authority(PWA) 2010-2014 Ashghal › › › › › SERVICES Client Project period DATA construction servicesincludingsitesupervision. COWI provides thepreconstruction and and outfall. form, shore protection works,seawaterintake with anapproach trestle of1.1km,flare plat- The marineconstructionworkincludesajetty carriers ofupto285,000m³capacity. The terminalisdesignedforhandlingLNG to thenaturalgasgrid. pressurization andvaporization, andconnection unloading, storagetanks,boil-off gashandling, and The terminalconsistsofLNGcarrierberthing Gujarat, India. fication terminalinMundraPorttheStateof 20 MTPA) LNGreceiving, storageandregasi- (GSPC) isdevelopinga5MTPA (expandableto The GujaratStatePetroleum Corporation INDIA GSPC LNGTERMINALAT MUNDRA, › › › › › Site supervision. Owner’s engineeringservices Request forproposals Cost estimation Front endengineeringdesign (FEED)review MARINE ANDFOUNDATION Whessoe Projects Ltd. ENGINEERING 2012-2017 35 MARINE AND FOUNDATION ENGINEERING 37

OUR EXPERTISE

Every marine project is unique. To meet this challenge, we have world-class engineers and experts working together to integrate seamlessly all aspects of marine engineering – from the marine construction itself to traffic planning, geo mapping and environmental impact assessment.

For every project, from a small coastal protection project to a major LNG terminal, we establish a specific team to ensure that we deliver the best solution for you. Photo: COWI MARINE AND FOUNDATION ENGINEERING 39

DIFFERENT CHALLENGES DIFFERENT EXPERTISE

We combine our expertise and competencies to deliver the optimal solution to your challenge.

DESIGN PROCUREMENT ››Marine foundation design ››Procurement strategies ››Offshore wind turbine foundations ››Tender documents LIFE CYCLE CONSIDERATIONS ››Marine terminals ››Scheduling ››Operation and emergency planning ››Ports ››Contracting ››Inspection and maintenance systems ››Coastal engineering ››Life cycle cost optimization CONSTRUCTION ››Waterfront developments ››Sustainability ››Construction management ››Man-made islands ››Site supervision CONCEPT DEVELOPMENT ››Breakwaters ››Marine structures ››Electrical and mechanical design SITE INVESTIGATIONS ››Renderings and animations of installations ››Design basis development ››Geological, wind and hydraulic IMPACT ASSESSMENT investigations ››Environmental impact ››Operational risk and safety ››Hydraulic modelling concepts ››Social impact ››Metocean conditions ››Planning impact ››Cost impact MARINE AND FOUNDATION ENGINEERING 41

THE PEARL-QATAR The Pearl-Qatar project involved detailed design of the reclamation works for the 400 hectare new island requiring approximately 13.5 million m³ of fill and the associated sea defence structures for the 40 km of new shoreline.

The development included private beaches along most of the perimeter, which adds to the aesthetics and exclusiveness of the develop- ment. Various concepts were developed to create a variety of beach environments that are optimised to suit the local conditions and requirements.

Numerical hydrodynamic model studies were carried out to determine the metocean design basis.

COWI has, in addition to the island design, rendered technical assistance during construc- tion and the design of the marinas.

DATA Project period 2003-2008 Client United Development Company (UDC)

SERVICES ›› Bathymetric survey ›› Design of marinas ›› Design of culverts ›› Design basis ›› Conceptual design ›› Detailed design ›› Preparation of tender and contract documents. MARINE AND FOUNDATION ENGINEERING 43

UPPER ZAKUM ARTIFICIAL ISLAND PMC, HONG KONG THREE-RUNWAY SYSTEM ABU DHABI, UAE DEEP CEMENT MIXING, CHINA The Zakum Development Company (ZADOC) needed The Hong Kong Three Runway System project to construct additional facilities in order to increase oil is a 650 ha extension of the existing airport at production from the Upper Zakum Field. Chek Lap Kok planned to meet future demands. Based on site conditions and production/facility The marine elements of the project comprise requirements, XADOC elected to construct four six packages where package 1 through artificial islands to meet this need. 5 cover deep cement mixing (DCM) of contaminat- ed mud pits. Package 6 covers the main reclama- Each island was proposed to be approximately 35 hectares except for the central "m" island, which was tion of all 650 ha including 12 km new seawall and proposed to be approximately 70 hectares. about 6 km existing seawall to be either removed To manage the construction of these islands, ZADOC/ or changed. ADNOC issued tenders for a project management consultant (PMC) and a design-build contractor. This project covers part of the seawall and part of COWI was selected as the PMC and the National the loading platform zone with about 25,000 DCM Marine Dredging Company (NMDC) as the design- clusters (one cluster consists of four overlapping build contractor. DCM columns) or a volume of about 2.6 Mm³. The lengths of the clusters are up to 45 m and COWI's primary scope of work was to manage the installed through a sand blanket into contaminated project to ensure that the islands were designed mud or soft clay and terminated in a competent according to the specifications within the agreed schedule and budget. Our specific tasks included: stratum of alluvium. establishing project objectives and requirements; preparing scope of services; contract tendering; Each DCM column has a diameter of 1 meter and evaluation and award; technical support; liaising with a design strength between 800 and 1.000 kPa. authorities; design checking and review; coordination, management, administration and quality control; DATA monitoring; auditing; reporting; close-out and Project period 2016-2018 commissioning. Client Sambo

DATA SERVICES Project period 2010-2013 ›› Detailed evaluation of the top of competent stratum Client Abu Dhari National Oil Company ›› Required embedment depth of deep cement (ADNOC) columns ›› 3D ground model SERVICES ›› Quantities for DCM clusters ››Design checking and review ›› Technical assessment of possible non-compliant ››Project management and construction supervision DCM works. ››Administration ››Control ››Review ››Follow-up ››Commissioning ››Quantities for DCM clusters ››Technical assessment of possible non-compliant works. MARINE AND FOUNDATION ENGINEERING 45

WHAT IS NEEDED?

Protection against high tides and rain or an economic analysis of consequences or intervention. We are ready to take on whatever is needed on requests from the municipalities or the citizens. MARINE AND FOUNDATION ENGINEERING 47 MARINE TERMINALS PORTS AND HARBOURS

BAHRAIN LNG IMPORT PORT OF REDWOOD CITY, KNPC NORTH AND SOUTH PIER RUWAIS GASPORT, AL ZOUR LNG IMPORT, PORT OF ANCHORAGE, PLANNING FOR CRUISE SHIP CHHARA PORT, CARGO TERMINAL, PORT OF SONAREF REFINERY MARINE TERMINAL CALIFORNIA, USA SURVEY, UAE KUWAIT ALASKA, USA FACILITY, GREENLAND INDIA OWENDO, GABON, WEST TERMINAL, ANGOLA

DATA DATA DATA DATA DATA DATA DATA DATA DATA DATA ›› Project Period: 2015-2019 ›› Project Period: 2011-2013 ›› Project Period: 2012-2014 ›› Project period: 2015 ›› Project Period: 2016-2018 ›› Project period: 2017 ›› Project period: 2013 ›› Project period: 2017-2018 ›› Project period: 2016 ›› Project period: 2013-2014 ›› Client: Whessoe Engineering Limited ›› Client: Port of Redwood City ›› Client: Kuwait National Petroleum ›› Client: Excelerate Energy Limited ›› Client: Hyundai Engineering and ›› Client: Port of Anchorage ›› Client: Qaasuitsup Kommunia ›› Client: Simar Port Pvt Ltd ›› Client: AFCONS Overseas Project ›› Client: Odebrecht Angola Projectos e ›› (main PMC consultant), Nogaholding Company and Integral Services Co. Partnership Construction Company Deepwater access for bulk, neo-bulk, and Gabon SARL Serviços Lda ›› Onshore receiving facility and pipeline W.L.L. (ISCO) The Port of Anchorage is undertaking a Updating and clarifying current and future The greenfield port at Chhara 50 km liquid cargos. Existing Wharves 1 and 2, Abu Dhabi Gas Industries Ltd. (GASCO) New liquefied natural gas regasification (4.1 km, buried) modernization program to upgrade the cruise ship operations at the Ilulissat Ice- to the west of Diu Airport will build a Gabon Special Economic Zone (GSEZ) Sonangol is planning to build a refinery built in the 1930’s and 1940’s, are used Terminal for gas import and export of intends to develop a gas port at the plant to supply natural gas to Kuwait ›› pipeline (4.3 km, 10-15 m water port’s facilities and provide new structures fiord in Qaasuitsup Kommunia in northern breakwater with a total length of 4.2 km Ports S.A. builds a new general cargo in Lobito including a marine terminal to for offloading aggregate, primarily from crude oil and refined products, for vessels existing sulphur terminal in Ruwais, Abu national gas grid. depth) that can survive extreme seismic events Greenland. comprising of 3.3 km section to protect terminal comprising a 420 m long berth receive Angolan crude oils, which will be Panamax vessels. COWI was retained to of up to 300,000 DWT. Dhabi to provide a natural gas supply ›› Breakwater (600 m long, 15 m water SERVICES and Cook Inlet’s harsh marine environment, the liquefied natural gas berths, container including quay, storage and service crane processed into refined liquid products lead a modernization project for Wharves through a floating storage and regasifica- SERVICES depth) SERVICES COWI will provide detailed design of the which includes extreme tidal fluctuations and multipurpose berths and coal jetties. for general cargo and container vessels, along with solid byproducts. The new 1 and 2. tion unit (FSRU). Excelerate provides the ›› Review of current cruise ship traffic to ›› Regasification platform with jacket ›› Sub- and superstructure inspections following units: and winter ice impacts. The new resilient COWI has been awarded the services dredged to -14.0m CD, for import of marine terminal will consist of two berths, 138.000 m³ FSRU and upgrades the jetty Ilulissat town in terms of opportunities substructure and regas. module SERVICES including underwater inspection of piles ›› Jetty I and II: OP, BD, MDs and IB, structures will have a 75-year design life. related to the detailed design of the general cargo such as grain, re-bars and one capable of loading liquid products topside HP loading arms and associated and challenges ›› Berthing jetty for FSU (175,000 m³) ›› Coordination of site investigations ›› Non-destructive testing and gauging Trestle: main trestle, arm 1 and arm 2, breakwater. hydrocarbons, and export of palm oil and and solid products and for loading liquid nearshore ancillary facilities, including a SERVICES ›› Meetings and interviews with and LNG carriers up to QMax size. including a geotechnical exploration, with ultrasound equipment Approach channel and flare platform containers. AFCONS Gabon SRL is the products and for loading liquid products 24" pipeline linking to the local gas grid. ›› Structural design stakeholder groups to identify local SERVICES hydrographic survey, topographic ›› Structural calculations of typical ›› Intake tower, pipelines and pump contractor for design and construction of and unloading heavy crude oil as well as Bahrain LNG W.L.L. is establishing an ›› Geotechnical engineering concerns and preferences ›› Data collection and review of existing survey, and hazardous material surveys sections in North and South Piers SERVICES station the works. AFCONS has appointed RH- a materials offloading facility. LNG import and regasification facility with ›› Coastal engineering. ›› Field trips by foot and by boat along the data ›› Marine structural design ›› Finite element modelling and structural ›› Berth layout and mooring study ›› Outfall diffuser, pipelines and chamber DHV as its Lead Design Consultant COWI peak send-out capacity of 800 MMSCFD, wilderness coast north of the Icefiord to ›› Establishment of design conditions SERVICES ›› Production of bridging documents for assessments ›› Desktop navigation simulation ›› Land reclamation and rock revetment. is the independent engineer. approximately 4 km off the coast near the identify suitable locations with potential ›› Concept design and detailed design for ›› Independent design verification (IDV) the design-build team ›› Survey and re-assessment study for the ›› Basic and detailed marine and structural Mina Salman port. for development of new marine facilities selected concept SERVICES of marine facilities (blockworks, ›› Permitting North Pier engineering ›› Summary report with proposed next ›› Design basis for hydraulic design ›› Independent design verification of revetments, reclamation) SERVICES ›› Review and approval of the design-build ›› Re-assessment calculations and ›› for the onshore steps. ›› Geotechnical design ›› Technical assistance on dynamic ›› PMC sub-consultant for the marine works teams' 75%, 95% and final designs rehabilitation strategy study. building and pipe racks. marine and onshore facilities, including ›› Specification and supervision for 2D and compaction trial tests ›› Technical advisor to the National Oil ›› Quality assurance during construction. civil infrastructure and MEP works 3D physical modelling tests. ›› Alternative design of revetment and and Gas Holding Company for certain ›› Independent modelling of structures. heavy duty pavement. interface-related activities. MARINE AND FOUNDATION ENGINEERING 49 COASTAL ENGINEERING AND WATERFRONT OFFSHORE WIND FARMS DEVELOPMENTS

BREAKWATER FOR VIZHINJAM HANSTHOLM PORT EXPANSION, SALWA RESORT HOTEL, MARINE MONACO URBANISATION EN SHENZHONG LINK, RENTEL OFFSHORE WIND FARM, MERKUR OFFSHORE WIND THORNTON BANK OFFSHORE FORMOSA 1 OFFSHORE HORNS REV C, KRIEGERS PORT, INDIA DENMARK WORKS, QATAR MER PHASE PRO/EXE CHINA BELGIUM FARM, GERMANY WIND FARM - PHASE 1, WIND FARM FOUNDATIONS, FLAK A AND B, TRANSFORMER BELGIUM TAIWAN PLATFORMS, DENMARK DATA DATA DATA DATA DATA DATA DATA ›› Project period: 2017-2018 ›› Project period: 2017-2018 ›› Project period: 2014-2015 ›› Project period: 2015-2013 ›› Project period: 2016-2017 ›› Project period: 2014-2017 ›› Project period: 2015-2017 DATA DATA DATA ›› Client: HOWE Engineering projects ›› Client: Per Aarsleff A/S ›› Client: Tashgeel & Besix JV ›› Client: SAM L'Anse du Portier ›› Client: Shenzhong Link Management ›› Client: Rentel NV ›› Client: DEME GeoSea NV ›› Project period: 2006-2008 ›› Project period: 2014-2015 ›› Project period: 2013-2015 (India) pvt Limited Center ›› Total: 550 MW ›› WTG: Alstom Haliade 150, 6 MW Hanstholm is a major fishery harbour Private Engineering Office develops a The Principality has contracted for a ›› Client: Dredging International n.v. ›› Client: Formosa Wind Power Co. ›› Client: Energinet.dk ›› Water depth: 22-32 m ›› Foundation no.: 66 Belgium ›› Total: 144 MW COWI carried out the detailed design of on the Danish North Sea coast. It has major high end resort. It includes a marina 60,000-sqm extension of the city of The 24 km link will connect the cities of Concept and basic design of two trans- ›› Foundations no: 42 ›› Water depth: 27-33 m ›› WTG: REpower 5.0 MW ›› Water depth: 15-30 m the 3.1 km long rubble mound break- launched a design-build tender for an in the middle and man-made beaches at Monaco into the sea. SOCOTEC and Shenzhen and Zhongshan across the former platforms for the 600 MW Kriegers ›› Foundation type: Monopile ›› Foundation type: Monopile ›› Water depth: 30 m ›› Foundations no.: 36 water. expansion with new outer breakwater- both sides. The harbour has an almost COWI carry out the independent verifica- Pearl River Delta. The link comprises Flak offshore wind farms. Futhermore, ›› Foundation no.: 6 ›› Foundation type: Monopile/Jacket sand quay wall. The eastern breakwater is ellipsoidal shape in order to protect the tion of the detailed design. The project two approach bridges, two bridges, the Rentel NV is developing an offshore wind MERKUR Offshore Wind builds Merkur COWI develops cthe oncept and detailed SERVICES ›› Foundation type: Gravity based 1 km long, the main western breakwater basin from waves from W and NW. The comprises 17 perimeter caissons, a world’s widest immersed tunnel and two farm in Belgian territorial waters with in the German part of the North Sea. The An offshore wind farm in East Asia on the design of Horns Rev C 400 MW trans- ›› Numerical modelling for establishing is 400 m long, both exposed to severe beaches are constructed as a basin leisure boat marina and land reclamation artificial islands. The islands are designed sand dunes of 5 m in height. Rentel has approval process for the development Detailed design of foundations. In western coast of Taiwan, consisting of former platform. design waves waves from the North Sea, with significant dredged along the coast. The beaches for the construction of underground park- to minimize the blocking effect in the appointed Dredging International NV as complies with the requirements of the 2003-04 we carried out a concept study, 36 turbines in total, is planned to be ›› Detailed design with Accropode® II as SERVICES wave heights in the order of 7-8 m. are stabilised with beach islands with a ing spaces as well as roads, utilities and environmentally sensitive river delta and EPCI contractor, and COWI (in joint ven- German Federal Maritime and Hydro- including the innovative conical shell installed in 2018. primary units. COWI carried out the tender design of very special layout. high-rise housing. the loads from typhoon waves and associ- ture with Technum-Tractebel) is Dredging graphic Agency (BSH). The construction structure, eventually adopted by the ›› Design of foundations ›› Detailed geotechnical design SERVICES breakwaters and revetments based on ated water levels. Both islands will be International’s design consultant for the is contracted to GeoSea for which COWI, project owner. In 2006-2008 we carried ›› Basic and detailed design of 2x400 MW ›› Technical specs for physical model tests SERVICES SERVICES the port expansion layout provided by the reclaimed from sand dredged in the river detailed design of the monopole founda- with IPU as sub-consultant, carries out out the detailed design. ›› Front end engineering design and and 200 MW platforms including and visit to lab ›› Marina layout confirmation ›› Independent verification of the detailed port, and after the award of the design- and protected by revetments with armour tions and transition pieces for 42 Siemens the detailed design of the foundations, detailed design of foundation for eight mechanical and electrical design. ›› Detailed structural design of wave wall ›› Review of existing data and design design of the caissons and their SERVICES build contract to Aarsleff, the detailed of rocks and concrete blocks. The services Gamesa SWT-7.0-154 turbines. viz. design of primary and secondary steel positions ›› Technical specifications for breakwater ›› Basis of design foundations as well as the marina and include independent design checks of the and transition pieces, bolted connection ›› Structural design of foundations ›› Front end engineering design of the design. SERVICES ›› Interface with concrete armour licensor ›› Geotechnical interpretative report associated structures two islands. between monopole and transition piece, ›› Geotechnical design entire wind farm. ›› Workshop on construction methodology SERVICES ›› Detailed design of marina outer ›› Independent modelling of the wave ›› Design of foundations geotechnical design, hydrodynamic load ›› Numerical and physical hydraulic SERVICES ›› Bill of quantities and issue of good-for- ›› Tender design of breakwaters and breakwater and beaches agitation inside the marina and ›› Geotechnical design calculation, scour protection, corrosion modelling of installation stages, construction drawings. revetments ›› Review of quay wall settlement analysis numerical calculation models of the ›› Dredging ›› Scour and corrosion protection protection, low voltage design, and ship including dynamic loads and scour ›› Detailed design. ›› Technical specifications. caisson structures in order to verify the ›› Reclamation and ground improvement ›› Designer's risk assessment collision friendliness analysis. ›› Appurtenances design, including boat designer’s numerical modelling ›› Initial perimeter of large steel cylinders ›› Risk management. landing and J-tubes ›› Assistance to marine environmental ›› Protecting perimeter structures SERVICES ›› Project follow-up in construction stage. monitoring of construction activities. ›› Rescue harbours. ›› Detailed design and FEM analysis ›› Concrete and grout structures. OWF App MARINE AND FOUNDATION ENGINEERING 51 INDUSTRIAL SEAWATER SYSTEMS LOCKS, DAMS AND BARRIERS

SEAWATER INTAKE RE-GASIFI- QURAYYAH INDEPENDENT GASCO 4TH NGL TRAIN, RAS AL KHAIR, FOLSOM DAM SPILLWAY CHARLEROI LOCKS AND RAS LAFFAN NEW SHIP REPAIR BRADDOCK DAM LOCK 2, CATION TERMINAL 2, MALAYSIA POWER PLANT, SAUDI ARABIA SAUDI ARABIA CA, USA DAM - LOCK #4, PA, USA YARD, QATAR MONONGAHELA RIVER, PA, USA

DATA DATA DATA DATA SERVICES DATA DATA DATA DATA ›› Project period: 2015-2016 ›› Project period: 2012-2013 ›› Project period: 2010-2012 ›› Project period: 2010-2011 ›› Design of seawater intake channel ›› Project period: 2008-2016 ›› Project period: 2003-2013 ›› Project period: 2006-2011 ›› Project period: 1997-2008 The challenges presented: developing ›› Client: Petronas CLIETAmec Foster ›› Client: Hula Marine Works Ltd. ›› Client: Target Eng. Cons Co. ›› Client: Archirodon Ltd. consisting of two approximately 1.4 km ›› Client: URS Corporation, USACE- ›› Client: USACE - Pittsburgh District ›› Client: QP/Nakilat ›› Client: U.S. Army Corps of Engineers a cast and launch facility for two, Wheeler long straight breakwaters orientated Sacramento District Pittsburgh District 11,000-ton dam segments; developing a New gas-fired combined-cycle gas The seawater cooling system of the 4th The Saline Water Conversion Corpora- Design of a new river wall and upper The marine part of the project consists perpendicularly to the coast 102 m long precast dam segment float-in Samsung C&T carries out the construction turbine power plant of net power capacity NGL train is a once-through cooling water tion (SWCC) developed a combined Design of a new spillway and six new guardwall at Charleroi Locks and Dam. of two graving docks to accommodate COWI was retained by the USACE ›› Design of scour protection of outfall and set-down sequence shell with suf- and the commissioning of the liquefied 3,927 MW. system comprising offshore intakes, cycle power and desalination plant in Ras gates to allow release of more water in COWI designed the upper guardwall. QMax and QFlex LNG vessels as well as Pittsburgh District to design and assist structures consisting in eight buried ficient strength for launch, transport, and natural gas regasification facility project offshore supply pipes, pumping station, Al-Khair formerly known as Ras Az Zawr advance of major storms, taking earlier The guardwall consists of six piers and VLCC's, one floating dock of panamax with construction supervision of the New SERVICES discharge pipes and an outfall structure immersion while maintaining a 3.1 m in Pengerang. The project includes the manifold, discharge pipes, discharge (RAZ) Power and Desalination Plant. advantage of the river’s capacity. a sheetpile nose cell, which supports size, six wet berths with a total length of Braddock Dam. As the Engineer-of-Re- with diffusers maximum draft; and developing a transport, installation of facilities for receipt, storage ›› Hydraulic design of intake and outfall structure, sealing weir structure and seven precast posttensioned concrete 2,400 m and a minimum depth of 11 m, cord for all final structural design draw- The plant has a capacity of: 2,400 MW ›› Design of shoreline protection SERVICES positioning, immersion, and dam comple- and regasification of LNG in order to supply pipeline system outfall structure. box beams, with flow skirts, that form the a heavy lift berth and extensive lay-down ings, we designed the float-in precast net power output and 1,025 Tm³/d water revetments tion plan that would safely accommodate a natural gas to RAPID, PCP and existing ›› Design basis including met-ocean ›› guard wall. and fabrication areas. dam segments and developed in-the-wet SERVICES production. ›› Design of transition between onshore 500-year flood at any time with 48-hour PGU system. Foster Wheeler E&C Sdn verification ›› Geotechnical engineering construction methods and procedures. ›› Geotechnical interpretative report ›› Marine and coastal design The Ras Al-Khair power and desalination structures and the eight discharge ›› Coastal engineering SERVICES SERVICES notice. Bhd (AmecFW), designing the facility, has The Braddock Dam was constructed us- ›› Design of intake risers – velocity cap ›› Structural design plant project was divided into two EPC pipes with the diffuser structure. ›› Quantities and cost estimation ›› Detailed design ›› Optimisation studies appointed COWI to manage the detailed ing a new and innovative float-in method, SERVICES type structures ›› Geotechnical design contracts covering power production ›› . ›› River navigation structures ›› Design of finger piers and mass design services of marine elements. a first within the USACE. The application ›› Detailed design ›› Design of dredging and reclamation ›› Hydraulic studies and design facilities and desalination plant. ›› Precast concrete construction concrete block quay walls for vessel of this innovative in-the-wet approach ›› River navigation structures SERVICES ›› Design of diffuser structures ›› Mechanical design ›› Construction sequencing and fitting-out, including substations is a landmark event, and one that could ›› Construction sequencing and ›› for intake pipes, ›› Review of details from manufacturer of ›› Piping design scheduling ›› Design of load-out quay for heavy lifts revolutionize the future construction of scheduling for bay/pump station and discharge outfall glass fibre reinforced pipe for the outfall ›› Electrical and instrumentation systems ›› Construction engineering. ›› Design of a lay-down and fabrication area navigation projects. We successfully ›› Construction means and methods ›› Sizing of pump station and piping ›› Review of construction methodology ›› Smart plant design (3D modelling). ›› Preparation of tender documents completed a major portion of the detailed ›› Tremie concrete mix design engineering for intake pipes ›› Design of lifting arrangments. ›› Supervision of construction. design following an aggressive seven ›› Construction engineering. ›› Geotechnical engineering month schedule. ›› Structural engineering for concrete head structure and manholes ›› Design of shore protection structures ›› 3D physical modelling for the pump station. MARINE AND FOUNDATION ENGINEERING 53 GROUND ENGINEERING AND RECLAMATION ENVIRONMENT AND CLIMATE ADAPTATION

PEARL JUMEIRAH, BUSAN-GEOJE FIXED LINK, AL ZORAH DEVELOPMENT, HONG KONG THREE-RUNWAY LIVING BREAKWATERS, NEW DOHA PORT, GREAT BELT TUNNEL, CLIMATE LEMVIG FLOOD BARRIER, STORM DAMAGE ASSESSMENT, UAE SOUTH KOREA UAE MAIN RECLAMATION, CHINA NY, USA QATAR CHANGE EVALUATION, DENMARK DENMARK DENMARK

DATA DATA DATA DATA SERVICES DATA DATA DATA DATA DATA ›› Project period: 2009-2014 ›› Project period: 2003-2011 ›› Project period: 2008-2012 ›› Project period: 2017 ›› Verification of land based DCM design ›› Project period: 2017 ›› Project period: 2009-2019 ›› Project period: 2017 ›› Project period: 2010 ›› Project period: 2013-2014 ›› Client: Meraas Development LLC ›› Client: Daewoo Engineering & ›› Client: SOLIDERE ›› Client: Jan De Nul / Chun Wo JV ›› Settlement estimate for both natural and ›› Client: SCAPE/Landscape Architecture ›› Client: The Government of Qatar ›› Client: Sund & Bælt ›› Client: Municipality of Lemvig ›› Client: Danish municipalities Construction Co. Ltd. improved ground conditions PLLC An offshore development area, constructed Technical support and construction Hong Kong Airport is currently operating The port will be built in phases with the 18 km long fixed road and rail link across Floods have through many years been The storm Bodil in December 2013 ›› Stone columns: Verification and from sourced reclaimed sand and The Busan-Geoje Fixed Link connects the supervision for dredging and reclamation, at near full capacity. In order to secure the Staten Island and Raritan Bay were hard first phase having a capacity of two million the Great Belt comprising a low bridge, a threat to Lemvig, a low-lying town in coincided with very high water levels in development of alternative optimised locally sourced rock. The sand is retained island of Geoje with the large city Busan rock work, ground improvement, settle- airport for future expansion it has been hit by Super Storm Sandy in 2012 and TEU (twenty-foot equivalent unit) per year a suspension bridge and a tunnel, COWI Northern Jutland near the North Sea. In Danish waters and caused much material design for land based stone columns along the perimeter of the development in the southern part of South Korea, ment monitoring etc. A 12 sq km parcel decided to build a third runway and asso- much of the shore of Staten Island is and by 2030, when fully operational, the was contracted by the owner Sund & 2010, the Municipality initiated a project damage. It gave impetus to many climate ›› PVD & surcharging: Verification and with rockwork slopes that are designed to improving access from the city to the of land was developed along the coast ciated airside facilities. The current airport being eroded as a result of creation of port will be able to handle six million TEU Bælt to perform a climate assessment to counter the threat of climate change adaptation acitvies. development of alternative design provide shoreline stability and a seaward industrial and recreational areas on Geoje of Ajman by Al Zorah Development. One is placed on an artificial island off Lantau shipping channels, heavy fishing of the of container capacity per year. A total of of the tunnel ramps. The study included and created new qualities and develop- for combined PVD and surcharging SERVICES defence of the upland areas. Island. The link comprises three major of the features of the development is a Island. The airport expansion covers shellfish resources and exposure to wave five import/export terminals will be built an assessment of the effects of climate ment opportunities for the city. The mangrove area. The mixed-use develop- design, providing reduced surcharge elements; one of the world's deepest and 6.5 million m², and will require reclama- action and coastal erosion. This project on the 20 sq km area which will serve as change based on newer statistical data solution was an eastethically pleasing ›› Inspection SERVICES ment will stretch along 3 km of coastline requirements longest immersed tunnels and two long- tion of an additional 75 million m³ of fill. is one of ten projects selected by the the port of entry for cargo, containers, as well as the potential impact of climate high-water barrier in the harbour. ›› Surveys and include commercial, residential, ›› Vibro-compaction of reclamation fill: ›› Assessment of subsurface conditions span cable-stayed bridges. The project site is characterised by very Department of Housing and Urban Develop- livestock, vehicles, bulk grain and other change in relation to the original design ›› Design and permitting of coastal recreational, educational and healthcare Review of compaction requirements. SERVICES ›› Concept, preliminary and detailed difficult ground conditions with up to 15 m ment (HUD) across the Sandy-affected goods. Additionally, the port will include a criteria. structures following damage by the SERVICES facilities as well as a golf course, marinas Preparation of alternative solution using design of marine, geotechnical and of soft clay and dumped mud pits where region to be pursued in the final stage cruise terminal, a base for offshore industry ›› Project management consultant for the storm Bodil. and hotels. resonance vibratory plate compaction SERVICES hydraulic services ›› Preliminary design, detailed design and contaminated material from other projects of the Rebuild By Design competition to supply vessels and coastguard vessels. high water barrier and renewal of urban ›› Geotechnical interpretation: Preparation create innovative solutions for resiliency. ›› Specification of surcharging and technical support during construction SERVICES has been placed and capped. The excavation, including an 11 km long ›› Risk analysis space, including relocation of utlities of geological and geotechnical model COWI was selected to provide coastal settlement monitoring of rock structures ›› Sand compaction piles (SCP) for sub-sea ›› Design of dredging and reclamation navigation channel dredged into the sea, ›› Analysis of the robustness of the and new street furniture. In order to accommodate the ground for reclamation area engineering and marine biology expertise. ›› Hydrodynamic numerical modelling. embankment ›› Marina design and design of marine required 95 million cubic metres of materi- surface water systems conditions, while complying with strict ›› Sloping and vertical seawalls: The proposed strategy, living, growing ›› Deep cement mixing (DCM) for tunnel structures als to be removed in the first phase. ›› Update of the operational risk analysis environmental regulations, extensive verification of tender design breakwaters, will combine offshore break- trench ›› Beach stability ›› cost estimate. ground improvement is utilised. The ›› Preliminary Environmental Monitoring waters with creation/restoration of finfish ›› Advanced numerical modelling for ›› Numerical modelling of waves, currents SERVICES employer's ground improvement methods Plan (EMP) and shellfish habitats to enhance ecologi- verification and water levels ›› Environmental impact assessment include: Deep Cement Mixing (DCM), ›› Physical hydraulic model testingTrial ›› Environmental impact assessment ›› 4D BIM model based on Contractor's cal benefits of the structure. studies (EIA) Stone Columns, Prefabricated. programme testing for SCP and DCM. ›› Power station impact study SERVICES ›› Advice and monitoring during ›› Cost estimate ›› Review of Contractor's Method construction. ›› Feasibility study ›› Construction supervision. Statements for reclamation and ground improvement. ›› Evaluation ›› Cost estimate. MARINE AND FOUNDATION ENGINEERING 55

TOGETHER WITH OUR CUSTOMERS, WE CREATE COHERENCE IN TOMORROW'S SUSTAINABLE SOCIETIES THROUGH OUR UNIQUE 360° APPROACH. 021-1700-023e-18h Cover photo: Thierry Dosogne EXPLORE USMOREAT: www.cowi.com