City Region Development Project (RRP BAN 39298)

Resettlement Plan

Document Stage: Draft for Consultation Project Number: 39298 July 2010

BAN: City Region Development Project—Ashulia Industrial and Residential Clusters Subproject

Prepared By: Local Government Engineering Department (LGED), Government of

This Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. ABBREVIATIONS

ADB — Asian Development Bank ARIPO — Acquisition and Requisition of Immovable Property Ordinance CRDP — City Road Development Project DCC — City Corporation DOE — Department of Environment DPHE — Department of Public Health Engineering GRC — Grievance Redress Committee GRM — Grievance Redress Mechanism IRS — International Resettlement Specialist LGED — Local Government Engineering Department MDSC — Management, Design and Supervision Consultant MOL — Ministry of Land NRS — National Resettlement Specialist PIU — Project Implementation Unit PMCU — Project Management Coordination Unit ROW — right of way RSS — resettlement support staff SPS — Safeguard Policy Statement

TABLE OF CONTENTS

EXECUTIVE SUMMARY i

I. PROJECT DESCRIPTION 1 A. Overview 1 B. Subproject Components 1

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 3

III. SOCIOECONOMIC INFORMATION AND PROFILE 6

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 8 A. Public Consultation 8 B. Information Disclosure 9 C. Continued Consultation and Participation 9

V. GRIEVANCE REDRESS MECHANISMS 10

VI. LEGAL FRAMEWORK 11

VII. ENTITLEMENTS, ASSISTANCE AND BENEFITS 12 A. Eligibility 12 B. Entitlements 12 C. Assessment of Compensation Unit Values 12

VIII. INCOME RESTORATION AND REHABILITATION 15 A. Basic Provision for Relocation 15 B. Income and Livelihood Rehabilitiation 16

IX. RESETTLEMENT BUDGET AND FINANCING PLAN 17

X. INSTITUTIONAL ARRANGEMENTS 18 A. Project Management Coordination Unit 18 B. Project Implementation Unit 18 C. Management, Design and Supervision Consultants 18

XI. IMPLEMENTATION SCHEDULE 20

XII. MONITORING AND REPORTING 21

Appendixes 1. Census Questionnaire for Permanent Land Acquisition and Resettlement 23 2. Census Questionnaire Inventory of Temporary Loss 28 3. Summary of Public Consultation and Focus Group Discussions 30 4. Future Consultation and Disclosure Roles and Responsibilities 36 5. Monitoring Indicators and Sample for Status Report 37

EXECUTIVE SUMMARY

1. The City Region Development Project (CRDP, the Project) will be financed by the Asian Development Bank (ADB) and is being formulated as a project loan using the sector approach to be implemented over a six-year period (January 2011 to December 2016). This document is a draft Resettlement Plan prepared for the Ashulia Industrial and Residential Clusters subproject. It is based on a feasibility level study and preliminary engineering design and will be updated at the final detailed engineering stage. The Resettlement Plan is prepared in accordance with the ADB Safeguard Policy Statement, 2009 (SPS), Government of Bangladesh’s (the Government) policy, i.e., the Acquisition and Requisition of Immovable Property Ordinance, 1982 (ARIPO), and the Resettlement Framework adopted for CRDP. It is classified as Category B according to ADB’s SPS as minimal land acquisition and resettlement is required for this subproject.

2. The Ashulia subproject consists of three components including (i) water supply and sanitation (five production tube wells and 30 km distribution pipeline); (ii) improvement of two access roads (7.15 km); and (iii) road side drainage system (6 km). Design measures were adopted to minimize involuntary resettlement taking into consideration available Right of Way (ROW) for roads, drainage, and pipelines.

3. Summary of Resettlement Impacts. A total of 11 households are affected by the subproject. The five proposed production tube wells will be constructed on private land amounting to 182 square meters (sq.m.) and affecting 5 households with 11 fruit bearing mango trees. There are no buildings/structures affected. These five households are considered to be economically displaced households. A total of six hawkers and squatters will also be affected and the impacts are limited to temporary economic displacement and relocation. Of the 11 affected households, five are considered vulnerable as they earn incomes below the poverty line. The five vulnerable households are hawkers. The resettlement cost estimate includes eligible compensation, resettlement assistance, as outlined in the entitlement matrix, and support cost for Resettlement Plan implementation.

4. Public Consultations. Consultations were carried out during Resettlement Plan preparation and will continue throughout the subproject cycle. A grievance redress mechanism (GRM) will be made available as explained in this Resettlement Plan.

5. Implementation Arrangements. The subproject will be managed and implemented through a Project Implementation Unit (PIU) based in Savar Upazila Parishad with the overall support and guidance of the Project Management Coordination Unit (PMCU) based at the Local Government Engineering Department (LGED) Headquarters in Dhaka. The detailed design, preparation and implementation of the capital investments will be supported by (i) consultancy support (both international and national); and (ii) technical support from LGED and the Department of Public Health Engineering (DPHE). The PIU will implement the Resettlement Plan with support from the PMCU and consultants. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per the entitlement matrix within this Resettlement Plan. Income restoration assistance to the affected persons includes both short and medium term strategies. The Government will provide all funds for land and resettlement in a timely manner.

6. Resettlement Plan Implementation and Monitoring. All compensation is to be paid prior to displacement (both physical and economic) however, ongoing income rehabilitation activities will continue after construction begins. Written confirmation of full compensation to ii displaced persons must be made to ADB prior to commencement of civil works in sections ready for construction. The estimated total period of the implementation of the Resettlement Plan is 13 months. Monthly monitoring reports will be submitted by PIU to PMCU. PMCU will consolidate monthly reports into semi-annual monitoring reports or as part of the regular project reporting and will submit to ADB.

I. PROJECT DESCRIPTION

A. Overview

1. The City Region Development Project (CRDP, the Project) emphasizes economic growth in Dhaka and Khulna city regions of Bangladesh through (i) creation of an enabling environment towards improved governance and capacity building of the local governments; and (ii) prioritized investments in infrastructure sectors in the two regions. The objectives of CRDP are (i) to improve the regional economic and social context through long-term development plans and investment programs, set within an institutional and regulatory context that will ensure implementation and review; (ii) to improve the capacity and mandate of local government to govern and to invest in improved economic activity at local level; (iii) to improve the economic context for sustainable commercial and industrial growth; and (iv) to improve the economic and social needs of the urban population, as an inclusive aspect of the CRDP. The subprojects are largely built around ‘integrated area planning’ principles which enhance economic activity in the regional context and provide opportunities for investment. The vision of the Ashulia subproject is to optimize the economic potential of the Ashulia Industrial and Residential Cluster in a way that is sustainable and to the benefit of industrialists, traders, local businesses, residents and workers in the Clusters and the neighboring area.

B. Subproject Components

2. The subproject identifies targeted capital investments in the Ashulia Industrial and Residential Cluster located in Savar Upazila referred to here as the Ashulia Cluster. The Cluster consists of three urban centers formed from the Ashulia, Yearpur and Damsona Unions. Ashulia is located next to (a residential model town) within (DCC) boundary near Yearpur and Damsona. The subproject components aim at priority upgrading and expansion of urban services, including (i) water supply and sanitation; (ii) drainage and flood protection; and (iii) roads and highways. The proposals are entirely concerned with activities which address the most acute needs for better urban services.

1. Water Supply and Sanitation

3. Based on the results of preliminary design, it is proposed to install five production/tube wells as a priority, together with 30 km of distribution pipelines serving a population of approximately 80,000 persons, with the assumption that one production well will serve about 15,000 or more people. In selecting the sites for the five priority production wells, cluster communities with low-income residents living in sub-standard and informal housing were given highest priority. The five proposed productions tube wells are situated at Basaid Bazar (Ashulia), Khejur Bagan (Ashulia), Modhupur/Faruk Nagar (Dhamsona), Vadail (Dhamsona) and Montos (Yearpur). A brief description of the proposed five production tube wells are described below in Table 1.

2

Table 1: Proposed Production Tube Wells District No Component Site Name Moholla Name Mauza Location Name Close to the Market, Plot of Production 1 Ashulia Basaid Bazar Basaid Dhaka Hazi Md. Ranzan Tube Well-1 Ali, RS Dag no. 861 West side of Mosque, Plot of Production Boro 2 Ashulia Khejur Bagan Dhaka Mr. Nasiruddin Tube Well-2 Ashulia Gong, RS Dag no. 1169 Adjacent to Ismail Production Modhupur (Faruk Bepari school 3 Dhamsona Gonokbari Dhaka Tube Well-3 Nagar) beside Aziz Textile mill Road Beside the Road of Production Vadail Chawrasta 4 Dhamsona Vadail Gonokbari Dhaka Tube Well-4 to Mother Textile Road Plot of Md. Abdus Production Sattar Dewan, Son 5 Yearpur Yearpur Montos Dhaka Tube Well-5 of Mr. Abdur Rahman Dewan

2. Drainage

4. There are two interlinked priority areas for drainage and road investment as identified in Table 2. Nearly 6 km of drains will be constructed along the two identified roads which become inundated by the rainwater and industrial wastewater. Design of the drains will be prepared by the project consultant as part of the detailed design work.

3. Access Roads

5. A package of two roads is recommended for road and drainage improvements. These two roads make an important contribution to the economic development of the Clusters in the Ashulia area. Improvements include widening within ROW, strengthening, and resurfacing. Road safety measures will be integrated in the design to ensure safety to pedestrians. The two access roads are (i) Dhaka-Aricha (RHD) at 20 Mile-Jerabo Bazar Yearpur UP Road; and (ii) Nabinagar-Kaliakoir (RHD) Road at Sreepur-Kashimpur GC Road, as described further below.

6. Road 1: Dhaka-Aricha (RHD) at 20 Mile-Jerabo Bazar Yearpur UP Road. The road length is 5.65 km and existing width is 6 m and connects Dhaka-Aricha RHD National Highway at the 20 mile marker to Tongi-EPZ road at Jerabo Bazar. Large and medium industries like Incepta, DEKKO, Maskot Group and many others are located alongside the road. The condition in some parts of the road is poor and requires immediate improvement. Due to movement of heavy traffic, the road is proposed to be strengthened up to 40 mm bituminous carpeting with a 6 m double lane carriageway pavement. To protect the road from inundation by industrial waste water and rainwater, new drainage (4 km) alongside the road will be provided, which will include the length from Jirabo to Kondul Bag (1.5 km) and Koturia to Kondul Bag (2.5 km).

7. Road 2: Nabinagar-Kaliakoir (RHD) at Sreepur-Kashimpur GC Road. The total road length is 6 km and existing width is 4.9 m and connects Nabinagar-Kaliakoir RHD Road with 3

Kashimpur GC, and Norsinghapur - Konabari RHD Road. Many large and medium industries like Samsher Knit, Square Textile, Mother Textile and the Atomic Energy Commission are located along the roadside. Of the length, 1.5 km up to Biman Poultry is proposed for inclusion as part of the subproject. Due to heavy traffic the road is proposed to be strengthened up to 40 mm bituminous carpeting with the 6m double lane carriageway pavement. To protect the road from inundation by industrial waste water and rainwater, drainage (2 km) along the proposed section will be constructed.

Table 2: Proposed Interlinked Roads Improvement and Drainage SL. No Name of Road Union Proposed Condition Remarks/Drainage Length (Km) 1 Dhaka- Aricha (RHD) Ashulia & 5.65 Poor/width 4 km drainage at 20 Mile- Jirabo Yearpur 6m needed Bazar Yearpur UP 2 Nabinagor- Kaliakor Dhamsona 1.5 Poor/width 2 km drainage RHD at Sreepur- 4.9m needed Kashimpur GC road.

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

8. There are 11 households affected by the subproject activities – five landowners from proposed tube wells, and six hawkers/vendors within the ROW. A summary of impacts on land acquisition and resettlement are described below in Tables 3 and 4.

9. Tube Wells. Minimum land acquisition is required for the proposed production tube wells which have small land requirements. The five proposed production tube wells will be constructed on private land amounting to be a total of 182 sq.m. which will be required for permanent acquisition affecting five households, 11 fruit bearing mango trees and no buildings/structure. These five households are considered to be economically displaced households. The 30 km of distribution pipelines will not require land acquisition. The distribution pipe lines neither will have permanent nor temporary impact on land acquisition and resettlement. The distribution pipeline will be laid under the ground and will not have any impact on structures except some minor inconvenience during construction. Minor disturbance will be avoided by keeping the night time construction and works during off-peak hours. Further measures to avoid and minimize access disruptions to businesses will be implemented as per the subproject environmental management plans.1

10. Roads and Drainage. The proposed interlinked components of road improvement (7.15 km) and drainage improvement (6 km) will not require any permanent land acquisition and resettlement as all construction activities will be confined to the existing ROW. However, few hawkers and vendors will be affected though these are limited to temporary economic displacement. A total of six hawkers were identified in preliminary surveys. These hawkers are mostly small shop vendors having temporary structures (e.g., bamboo sheds and small wooden kiosks).

1 Environmental management plans form part of the civil works contracts are aim to provide continued access to local businesses to minimize impacts.

4

Table 3: Summary of Land Requirements Sl Name of the Impact on Land Temporary Remarks No Components Acquisition Impact 1. Water Supply and Sanitation a-1 Yes No 40.53 sq.m. of agricultural land to be Production acquired having 1 economically Tube Well-1 displaced households a-2 Production Yes No 40.53 sq.m. of agricultural land to be Tube Well-2 acquired having 1 economically displaced households a-3 Production Yes No 40.53 sq.m. of agricultural land to be Tube Well-3 acquired having 1 economically displaced households a-4 Production Yes No 40.53 sq.m. of agricultural land to be Tube Well-4 acquired having 1 economically displaced households a-5 Production Yes No 40.53 sq.m. of agricultural land to be Tube Well-5 acquired having 1 economically displaced households b 30 kms of No No The distribution pipeline will be distribution constructed underground having no pipelines permanent or temporary impact 2. Interlinked Roads and Drainage a-1 Dhaka- Aricha No No 6.65 kms of roads improvement and 4 (RHD) at 20 kms of drainage will not have any impact Mile- Jirabo on land acquisition and resettlement Bazar Yearpur either permanent or temporary as the UP Road. entire components will be constructed within the existing ROW a-2 Nabinagor- No Yes 1.50 kms of roads improvement and two Kaliakor RHD kms of drainage will have temporary at Sreepur- impact on 6 vendors/hawkers operating Kashimpur GC in the existing ROW. road. ROW = right of way.

Table 4: Land Acquisition Impacts Percentage Area to Total Area Percentage Area to of loss Total Land- Type Dag No/ be of the of Loss Name of the Name of the Ownership be compared holding NO of Cadastral Name of the Owner Acquired Affected compared Component Mohalla/Area of Land Acquired to the total (Affected + Land No (square plot to the total (katha) area of the Unaffected) meter) (katha) holding plot Production Agricult 1 Basaid Bazar Private 861 Mr. Hazi RamjanAli 0.56 40.53 1.50 37.33 8.00 7.00 Tube Well-1 ural Production Agricult 2 Khejur Bagan Private 1169 Mr. NasiruddinAhmed 0.28 20.27 2.00 14.00 10.00 2.80 Tube Well-2 ural Production Modhupur Agricult 3 Private NA Mr. FarukHosssain 0.56 40.53 3.00 18.67 14.00 4.00 Tube Well-3 (Faruk Nagar) ural Production Agricult 4 Vadail Private NA Mr. AmirHamza 0.56 40.53 1.80 31.11 20.00 2.80 Tube Well-4 ural Production Agricult Mr. Abdur Rahman 5 Yearpur Private NA 0.56 40.53 1.70 32.94 30.00 1.87 Tube Well-5 ural Dewan

5

6

III. SOCIOECONOMIC INFORMATION AND PROFILE

11. Structured census survey questionnaires (Appendixes 1 and 2) were used to collect detailed information on the impact of permanent land acquisition and temporary impacts hawkers and vendors in the subproject area. The surveys were conducted in June 2010.2

12. A total number of 11 households are being economically displaced by the subproject which consists of 5 households losing a small piece of agricultural land and 6 hawkers/vendors. Each is considered to be economically displaced as they will be losing some basic economic activities. The land owners are mostly occupied in agriculture, while hawkers in small business. Socioeconomic details of landowners are in Table 5. None of the displaced households belong to any Indigenous People or ethnic minority group as most of the displaced persons are Muslims. The census survey revealed that five hawkers fall under the vulnerable category as they earn income considered below the poverty line. Following section provides a socioeconomic profile of the displaced persons.

13. The total land required for proposed five production tube well is 2.52 katha (or 182 sq.m.). The land contains no structures and is characterized as agricultural and unirrigated. There are five landowners affected, each holding legal title. The requirement of land for each production well is minimal and no land owners will lose more than 10% of the productive asset and hence, none of the five households are significantly affected. There will be a total of 11 fruit bearing trees (mango) affected. There are no encroachers and squatters present in the affected land.

Table 5: Socioeconomic Details of Affected Land Owners HH size Main Vulnerability Monthly S. Name of the Occupation/ Income Women Physically N Owner Income a Total Male Female (Tk) Headed Disabled BPL Source Household Household Household 1 Mr. HaziRamjanAli 5 2 3 Business 18,000 No No No Mr. 2 NasiruddinAhmed 6 3 3 Business 30,000 No No No Government Mr. FarukHosssain 3 2 1 1 Service 15,000 No No No 4 Mr. AmirHamza 3 1 2 Agriculture 11,000 No No No Mr. Abdur 5 Rahman Dewan 8 4 4 Agriculture 13,000 No No No

a Below Poverty line (BPL) has been calculated on the basis of general formula which is 1$ per day per person. The average family size in the subproject area is 4.9 and the $1= Tk72. Therefore, the threshold for poverty line has been considered as Tk10,584 incomes per month per household. Source: Census Survey, June 2010.

14. Sex. The total number of displaced persons is 44 out of which 21 (38.89%) are male and 33 are female (61.11%). The average family size is 4.90.

2 The survey team was trained by the international resettlement specialist consultant and the survey was closely monitored on a regular basis. The census survey included various aspects including (i) assessment of land including quantity and typology; (ii) Inventory of physical assets; (iii) potential income loss; (iv) impact on trees; (v) household characteristics, including social, economic and demographic profile; and (vi) temporary impacts on the hawkers’ business activities. 7

15. Average Monthly Income of the displaced persons. A majority of households earn between Tk9,000 to Tk11,000 per month. Details of average monthly income are in Table 6 below.

Table 6: Average Monthly Income of the Displaced Households Sl. No. Monthly Income (Tk) Number of Households % Age 1 Less than Tk3,000 0 0.00 2 Tk3001 to Tk5,000 1 9.09 3 Tk5,001 to Tk7,000 3 27.27 4 Tk7,001 to Tk9,000 0 0.00 5 Tk9,001 to Tk11,000 6 54.55 6 Tk11,001 to Tk15,000 0 0.00 7 Tk15,001 to Tk20,000 0 0.00 8 Above Tk20,000 1 9.09 9 Total 11 100.00 Note: Average Monthly Income: 10,000 Tk [Minimum 5000, Maximum Tk25,000]. Source: Census Survey, June 2010.

16. Hawker Kiosks. The types of temporary structures are classified based on the type of construction, their usability and the age of the structure. There is no permanent foundation or construction materials being used except some bamboo pillars, tripol/plastic or thatched structures, and corrugated iron sheets. Details on the type of materials are given in Table 7. The total area of these temporary structures is 41 sq.m. and the average area has been calculated to be 7 sq. m. for each structure. Therefore, these can be easily shifted to other locations without much disruption. It is found that the age of most structures are below ten years old, with most being less than five. Out of the total surveyed hawkers/vendors, it is noted that five are fully affected and only one structure is partially affected.

Table 7: Type of Materials for Hawker Kiosks Sl. Number of Particulars % No. Properties Simple 1 (thatch/sack/bamboo/slats) 1 16.67 2 Brick 0 0.00 3 Concrete 0 0.00 4 Corrugated iron sheet 4 66.67 5 Asbestos sheet 0 0.00 6 Tripol/Plastic 1 16.67 7 Blank 0 0.00 Total 6 100.00 Source: Census Survey, June 2010.

17. The market prices of the hawker structures are indicated below in Table 8.

Table 8: Market Prices of Hawker Structures Number of Sl. No. Particulars % Properties 1 Up to Tk1,000 0 0.00 2 Tk1,000 to Tk2,000 0 0.00 3 Tk2,000 to Tk3,000 0 0.00 4 Tk3,000 to Tk4,000 2 33.33 5 Tk4,000 to Tk5,000 2 33.33

8

Number of Sl. No. Particulars % Properties 6 Tk5,000 to Tk6,000 0 0.00 7 Tk6,000 to Tk7,000 0 0.00 8 Tk7,000 to Tk8,000 1 16.67 9 Tk8,000 to Tk9,000 0 0.00 10 Tk9,000 to Tk10,000 0 0.00 11 Above Tk10,000 1 16.67 Total 6 100.00 Source: Census Survey, June 2010.

18. Gender. During disbursement of assistance and compensation, priority will be given to female headed households. Joint ownership in the name of husband and wife will be offered in case of non-female headed households where the asset was acquired during their marriage.

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

A. Public Consultation

19. During subproject preparation, consultations were held with the official representatives of the Savar Upazila, apart from the communities in the project area. The issues covered during these consultations included selection of subprojects and identification of key issues including addressing the current gaps in provision of basic services and improvement of urban environment conditions in the Savar urban area. These consultations (Table 9) provided an understanding of the needs and concerns of the project communities and the relevant stakeholders. Additionally, focus group discussions were also conducted with the local community especially with the displaced persons and the summary of these consultations is given in Appendix 3.

Table 9: Consultations with Stakeholders Incorporation into Number of Place Date Participants Issues Discussed Resettlement Plan and Project Participants Design Sawar May 6 Officials of Tourism Finalization of project Capacity building program, for Upazilla 10th Department, components, training on safeguards aspects 2010 Revenue environment and to the DPHE and other Department and social safeguard concerned engineers, as part of Forest Department. requirements. the project and proper institutional mechanism developed to implement the Resettlement Plan. Sreepur May 10 Communities along Need for improvement The proposed designs include 10th the road side. of the water supply measures to address the 2010 and drainage environmental and social conditions. Every year impacts. The drainage the roads are subject components have been added to to water logging, due the roads improvements to movement of heavy components and design has commercial vehicles been made to fit in all the Dust due to the subproject activities in to the operation of vehicles existing ROW except for the in the night. proposed production tube wells. 9

Incorporation into Number of Place Date Participants Issues Discussed Resettlement Plan and Project Participants Design Adequate compensation, assistance and advance notice to be given to these displaced persons and hawkers and the same provisions have been incorporated in the Resettlement Plan. This has also become an awareness exercise for the people regarding the project. Ashulia 21st 15 Officials of Sawar Discussion on project Potential lands for the production June Upazilla, elected components. Siting of tube wells site have been 2010 representatives/cou the project identified. Local people have ncillors, components to avoid been aware about the fact that Officials of DPHE, impacts on land they might have to give their land LGED acquisition and for the development purpose. clearance of trees etc, Concerned officials Need for management (DPHE/LGED) have been of pollution from advised to take advance action industrial clusters, on negotiation with land owners better sanitation and initiate further consultation facilities for the for smooth acquisition of the residents. required land. DPHE = Department of Public Health Engineering, LGED = Local Government Engineering Department, ROW = right of way.

B. Information Disclosure

20. Project information will be continually disseminated through disclosure of resettlement planning documents. Resettlement information leaflets containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Bangla) and the same will be distributed to DPs. The PIU Resettlement Support staff (RSS) will keep the displaced persons informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. The information will also be made available at a convenient place especially, the market place which will be easily accessible to the displaced persons. The summary of the Resettlement Plan and the entitlement matrix will be translated into the local language; disclosed to the displaced persons; and made available at PIU, local offices and libraries (or other pubic places, and at the LGED and DPHE offices. A copy of the Resettlement Plan will be disclosed on the LGED and ADB website.

C. Continued Consultation and Participation

21. For continued consultations, the following steps are to be taken:

(i) The PMCU and the PIU will organize public meetings and will apprise the communities about the progress in the implementation of resettlement, social and environmental activities. (ii) There will be a Grievance Redress Committees (GRC). The displaced persons will be associated with such committee along with their representatives. (iii) PMCU and PIU will organize public meetings to inform the community about the compensation and assistance to be paid. Regular update of the progress of the

10

resettlement component of the project will be placed for public display at the PCMU and PIU offices. (iv) All monitoring and evaluation reports of the resettlement components of the project will be disclosed in the same manner as that of the Resettlement Plan. (v) Key features of the entitlements will be displayed along the project corridor. (vi) The PMCU and PIU will conduct information dissemination sessions at major intersections and solicit the help of the local community leaders to encourage the participation of the displaced persons in Resettlement Plan implementation. (vii) Attempts will be made to ensure that vulnerable groups understand the process and to take their specific needs into account.

22. The details on consultation process and disclosure at various phases of project development including the responsible agency are described in Appendix 5.

V. GRIEVANCE REDRESS MECHANISMS

23. A grievance redress mechanism (GRM) will be established in Ashulia soon after project commencement. The first level and most accessible and immediate venue for the fastest resolve of grievances is the PIU, chiefly through the RSS and Project Manager, with assistance from the Resettlement Specialist (National and International-NRS and IRS) of the Management, Design and Supervision Consultant (MDSC). The contact phone number will be posted in the project areas. Grievances will be resolved through continuous interactions with affected persons and the PIU will answer queries and resolve grievances regarding various issues including land acquisition, structures acquisition, livelihood impacts, entitlements, and assistance. Corrective measures will be undertaken at the field-level itself within seven days. All grievances will be documented with full information of the person and issue.

24. Should the grievance remain unresolved, the PIU's Project Manager, will activate the second level of the GRM by referring the issue (with written documentation) to the local GRC of the Upazila, who will, based on review of the grievances, address them in consultation with the RSS of the PIU and PMCU, and affected persons. A hearing will be called, if necessary, where the affected person can present his/her concern/issues. The process will promote conflict resolution through mediation. The local GRC will consist of the following persons: (i) Chief Executive Officer of the Upazila (GRC Chair); (ii) representative of the head of the Upazila; (iii) representative of the affected persons; (iv) official of the land registry department; (v) official of the Department of Environment (DOE)’s divisional office; (vi) town planner of the Upazila; and (vii) Environmental Specialist/RSS of the PIU. The local GRC shall meet twice a month, unless the Project Director informs that there are no grievances to address, or they shall meet as needed as per the severity of the grievance. The local GRC will suggest corrective measures at the field level and assign responsibilities for implementing its decisions.

25. The functions of the local GRC are as follows: (i) provide support to displaced persons on problems arising from land acquisition (temporary or permanent); asset acquisition; and eligibility for entitlements, compensation and assistance; (ii) record grievances of displaced persons, categorize and prioritize them and provide solutions within a month; and (iii) report to the aggrieved parties about developments regarding their grievances and decisions of the GRC.

26. Should the grievance still remain unresolved, the PIU Project Manager, will activate the third level of the GRM by informing the PMCU Project Director who will, based on review of the local GRC minutes and consultation with the PIU Project Manager, activate the PMCU level GRC. This committee shall comprise the following representatives:(i) Project Director PMCU, (ii) 11

Environmental/Resettlement Officer of the PMCU; (iii) representative from Land Ministry; (iv) representative from DOE; (v) representative of the displaced persons; and (vi) Environmental / Social Safeguards officer of the PIU.

27. The GRC at the PMCU level shall meet based on the receipt of grievances, and the meeting shall be convened within 7 days of receipt of the grievance by the PMCU, and grievances redressed with 15 days. The Environmental/Resettlement Safeguards Officer of the PMCU will be responsible for processing and placing all papers before the PMCU GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out.

28. In the event that a grievance is not addressed by the PIU, local GRC, or the PMCU GRC, the displaced person can seek legal redress of the grievance in the appropriate Courts (the fourth level of the GRM). A grievance redress mechanism and procedure is depicted in Figure 1.

Figure 1: Grievance Redress Mechanism (GRM)

DSMC = Design Supervision Management Consultant, GRC = Grievance Redress Committee, GRM = Grievance Redress Mechanism, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

VI. LEGAL FRAMEWORK

29. This Resettlement Plan is prepared based on all applicable legal and policy frameworks of the Government (i.e., the Acquisition and Requisition of Immovable Property Ordinance 1982 [ARIPO]) and ADB's SPS. A summary of applicable acts and policies is presented provided in the Project's Resettlement Framework.

12

30. The Government's policy through ARIPO does not cover project-affected persons without titles or ownership record, such as informal settler/squatters, occupiers, and informal tenants and lease-holders (without document) and does not ensure replacement value of the property acquired. The ARIPO has no provision of resettlement assistance for restoration of livelihoods of affected persons except for the legal compensation. Gaps between national law and ADB policy are identified and bridging measures are included in the entitlement matrix for the project, described below. ADB will not finance the project if it does not comply with its SPS nor will it finance the project if it does not comply with its host country's social and environmental laws. Where discrepancy between the ADB and Government policies exist, the ADB policy will prevail. Moreover, the SPS applies to all ADB-financed and/or ADB-administered sovereign projects, and their components regardless of the source of financing, including investment projects funded by a loan; and/or a grant; and/or other means.

VII. ENTITLEMENTS, ASSISTANCE AND BENEFITS

A. Eligibility

31. All displaced persons who are identified in the project-impacted areas on the cut-off date3 will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their pre-project living standards, income-earning capacity and production levels. The project will recognize both licensed and non-licensed vendors. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the detailed census during the detailed design. Displaced persons who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice (60 days), requested to vacate premises and dismantle affected structures prior to project implementation.

B. Entitlements

32. The entitlement matrix in Table 10 summarizes the main types of losses and the corresponding entitlements in accordance with the Government and ADB policies.

C. Assessment of Compensation Unit Values

33. Land. All lands proposed to be acquired under CRDP will be compensated as per replacement cost consistent with both the Government and ADB’s SPS. The design consultants will prepare site plan overlays (based on detailed designs) on the cadastral map to define the area and parcels to be acquired. This is to form part of the application to the Ministry of Land (MOL).4 The MOL will then assign the task to the concerned Deputy Commissioner in the project areas. The Deputy Commissioner will then decide the cost of land through its property valuation advisory committee5 which will serve as the valuation committee.

3 The cut-off date for title holders is based according to the formal notification, and for non-titleholders the date of the census survey during the detailed design. Those who encroach into the subproject area after the cut-off date will not be entitled to compensation or any other assistance. The PIU will take video and photo documentation to ensure entitled persons on the cut-off date. 4 The application to MOL includes a detailed statement specifying whether the land mentioned in the application is needed for public or private purpose, the area of the land, sketch-map, purpose for which it could be used. 5 Under the Project, a representative from the displaced persons is required to be a member of the property valuation advisory committee to ensure compensation for assets is at replacement value.

Table 10: Entitlement Matrix Sl Type of Application Entitled Entitlement Implementation Responsible No Loss Person Issues Agency

1 Loss of Homestead Owner(s) with  Land-for-land option of equal productive capacity satisfactory to  If land-for-land is  PIU/PMCU land land, legal title owner if feasible and if alternate land is available. offered, title will be to  Deputy agricultural  Cash compensation equivalent to replacement cost.6 both husband and Commissioner land, or  Assistance in finding replacement land. wife, if feasible. vacant plot  Provision of stamp duty, land registration fee, capital gains tax,  Vulnerable and value added tax incurred for replacement land. households7 to be  Option to be compensated if remaining land is no longer viable. identified during  Access to equivalent common property resources previously census survey accessed conducted as part of  Additional compensation for vulnerable households. the Resettlement Plan.  Viability of land to be determined in consultation with land owner. 2 Loss of Standing Owner(s) with  60 days advance notice to harvest standing seasonal crops, if  Work schedule to  PIU/PMCU crops crops and legal title, harvest is not possible, cash compensation for crops (or share allow harvesting prior and trees trees tenant(s), of crops) equivalent to prevailing market price. to acquisition and leaseholder(s),  Cash compensation for perennial crops and fruit bearing trees avoid harvest season sharecropper(s based on annual net product market value multiplied by  Market value to be ), remaining productive years. determined in encroacher(s),  Cash compensation equivalent to prevailing market price of consultation with squatter(s) timber for non-fruit trees. divisional forest department. 3 Loss of Residential/ Encroacher(s)  Cash compensation equivalent to replacement value of  Vulnerable  PIU/PMCU structure commercial and squatter(s) structure (or part of structure) constructed by the displaced households to be structure person. identified during and other  Rights to salvage materials from structure. census surveys assets (e.g.  Provision of all taxes, registration costs, and other fees incurred conducted as part of fences, for replacement structure. the Resettlement gates,  Shifting allowance based on actual cost of moving (e.g., truck Plan. posts) hire, equipment, etc.). structure  Additional compensation for vulnerable households.  Assistance in finding alternate location.

6 The rate of compensation for acquired housing, land and other assets will be calculated at full replacement costs. The calculation of full replacement cost is described in Section B.V.c in this Resettlement Framework. Where market conditions are absent or in a formative stage, the borrower/client will consult with the displaced persons and host populations to obtain adequate information about recent land transactions, land value by types, land titles, land use, cropping patterns and crop production, availability of land in the project area and region, and other related information. The borrower/client will also collect baseline data on housing, house types, and construction materials. Qualified and experienced experts will undertake the valuation of acquired assets. In applying this method

of valuation, depreciation of structures and assets is not to be taken into account. 13 7 Vulnerable households/displaced persons may include female-headed households, disable-headed households, indigenous persons/ethnic minority-headed households and Below Poverty Line households

14

Sl Type of Application Entitled Entitlement Implementation Responsible No Loss Person Issues Agency

4 Loss of Livelihood/s Business  60 days advance notice.  Vulnerable  PIU/PMCU livelihood ource of owner(s),  Assistance in finding alternate location. households to be income tenant(s),  One time assistance for lost income based on three months lost identified during leaseholder(s), income (at replacement cost) or minimum wage rates census surveys employee(s), (whichever is higher). conducted as part of agricultural  Shifting allowance and cost of reestablishing business the Resettlement worker(s), elsewhere (cost of truck hire, equipment, etc.). Plan hawker(s)/  Training allowance in the form of cash equivalent to short term  Training allowance to vendors(s) training course. be paid directly to the  Additional compensation for vulnerable households. training institute  Consideration for project employment.

5 Impacts All impacts Vulnerable  Land-for-land option will be a guaranteed option for vulnerable  Vulnerable  PIU/PMCU on displaced displaced persons if available. If not available, assistance in households to be vulnerabl persons finding new land. identified during e  Additional allowance equivalent to Tk10,000/- for loss of land or census surveys displaced structure. conducted as part of persons  Preference in project employment. the Resettlement Plan

6 Any other Unanticipated involuntary impacts shall be documented and  PIU/PMCU loss not mitigated based on the principles provided in this Resettlement identified Framework and with compliance with the Government’s and ADB’s policy. PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. 15

34. The land valuation process will consist of two different values – (i) the sale deed record, and (ii) expected price. The PIU will be responsible for providing the recorded rate from the Local Land Registry Office (i.e., the sale deed record). The PIU will consult with willing buyers/sellers of the area to collect the expected price of land. The PIU will then submit the two rates to the valuation committee. Based on these rates the valuation committee will derive a price which will be called as the current market rate. Additionally, the cost for tax and stamp duties etc. will be added to the current marker as derived by the valuation committee which will finally be considered as the replacement cost.

35. Private Building and Structure. The compensation for houses, buildings and other immovable properties will be determined on the basis of replacement cost as on date without depreciation. The PIU with assistance from the Public Works Department (PWD) will determine the replacement cost of structures. PIU will engage experts form PWD and the experts will carry out on the field assessment of each property and will submit the report to the Deputy Commissioner office. PIU will ensure that the assessment is done keeping in consideration the market price and consultation with the owners by assessing sources, types and cost of materials, usage of the building and the cost related to labor and transportation etc.

36. Trees and Crops. The PIU will conduct the survey on unit prices of trees and crops affected by temporary or permanent land acquisition, in consultation with agriculture/horticulture experts. The compensation for crops will be calculated based the current market rate. The PIU will collect data on crops in the project area from the local department of agricultural extension. Subsequently, the unit/market rate for each crop will be determined in consultation with the department of agricultural extension. The unit prices for compensation of different species of fruit trees will be based on the market values of their fruits. For trees producing timber their unit prices will be based on species type, age, and quality. The cost for such trees will be collected after consultation with the divisional forest office.

37. Business or Sources of Income. The PIU will conduct a detailed census survey which is to include actual monthly income of the displaced persons followed by a verification of the income data based on the tax payment (for titled business owners). In the absence of the authentic income proof, the unit price will be collected from the displaced person during the survey.

VIII. INCOME RESTORATION AND REHABILITATION

A. Basic Provision for Relocation

38. The basic provision for loss of land has been taken as the cash compensation at market price which is equivalent to replacement cost. Advanced notice (60 days) will be provided for harvesting crops, or if harvesting is not possible, then the farmers will be compensated at replacement cost for such crops. Trees will be compensated at market value. All compensation is to be paid before displacement occurs. The land owners losing a small piece of land will not require any relocation as they will not be physically displaced nor they will be severely affected. The PIU will attempt to find suitable alternative locations for hawkers including creating potential formal market spaces where feasible. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per applicable according to the entitlement matrix. The PIU will compensate non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land, at full replacement cost. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. The preliminary number of displaced hawkers is quite

16 minimal (only six) in the subproject area and the consultation with these hawkers and vendors revealed that they will be willing to shift on their own provided they get some compensation. To help the hawkers losing structures in getting entitlements and relocating themselves, a relocation strategy will be adopted in the subproject including (i) all compensation will be paid and other resettlement entitlements will be before physical displacement; (ii) at least 60 days advance notice will be given; (iii) the PIU and RSS will assist displaced persons during verification of assets and will provide necessary counseling on payment of compensation and assistance; (iv) in close consultation with the displaced persons, the PIU RSS will fix the shifting dates agreed with the displaced persons in writing and the arrangements desired by the displaced persons with respect to their entitlements; and (v) in case of self relocation, the PIU will assist the displaced persons in finding alternative site within the area if so desired by the displaced persons.

B. Income and Livelihood Rehabilitation

39. Income restoration assistance to the displaced persons includes both short and medium term strategies. Short term income restoration strategies are for immediate assistance during relocation and include the following:

(i) Compensation for land, structures, crops, fruit bearing trees, and all other lost assets is paid in full before displacement occurs; (ii) Assistance in finding replacement land or alternate location for continuation of livelihood/living arrangements; (iii) Where provision of alternative sites is not feasible (for temporary impacts), compensation of lost income for period of disruption (if less than three months) or lump sum for three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (iv) Shifting allowance for reestablishing business elsewhere based on actual cost of moving/unloading; (v) 60 days’ advance notice to shift business or harvest standing seasonal crops (if harvest is not possible, compensation for share of standing crops at market rates); (vi) One time assistance for lost income based on three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (vii) Consideration for project employment; (viii) For vulnerable households, additional subsistence allowance equivalent to Tk10,000/HH for restoring or enhancing their livelihood. Vulnerable households will be prioritized in any project employment; (ix) Provision of temporary access where possible to continue business; and (x) Restoration of affected land, structure, utilities, common property resource for continuation of business after construction is completed.

40. Medium-term income restoration activities will include skill development training based on need. The PIU will identify suitable local training institutes and pay fees directly to the training institution and provide the names of entitled person(s).

41. Where necessary, training may include (i) capacity building, enterprise training, and facilitating economic activities to landowners; and (ii) training for self employment to agricultural laborers. Training for self-employment and skill development which may include but not limited to (i) plumbing; (ii) electrical; (iii) automobile repair; and (iv) electronic repair and service, etc. Training will be imparted to any willing displaced person losing income or livelihood.

17

42. During the construction stage the displaced persons, especially vulnerable displaced persons, will be given preference over others in being engaged in project activities suitable to their skills. In order to make the displaced persons employable, the PIU will identify the required skills for the construction activities prior to the commencement of the construction and provide the required training to the displaced persons.

IX. RESETTLEMENT BUDGET AND FINANCING PLAN

43. The resettlement cost estimate for the Ashulia subproject (Table 11) includes eligible compensation, resettlement assistance, as outlined in the entitlement matrix, and support cost for Resettlement Plan implementation. The Government will be responsible for releasing the funds for resettlement in a timely manner. The total resettlement cost for the subproject is Tk9.66 million. The cost items are outlined below:

(i) Compensation for land; (ii) Compensation for fruit bearing trees; (iii) Compensation for structures (hawkers/vendors) and other immovable assets at their replacement cost; (iv) Assistance for stamp duty etc for legal titleholders for land acquisition; (v) Assistance in lieu of the loss of income and livelihood; (vi) Assistance for shifting of the structures; (vii) Training allowance; and (viii) Special assistance to vulnerable groups for their livelihood restoration.

Table 11: Resettlement Budget Sl. No. Item Unit Rate Quantity Amount (Tk) A Compensation A-1 Land sq.m. 18,275 182 3,326,050 A-2 Compensation for Trees Numbers 20,000 11 220,000 A-3 Compensation for Temporary Numbers 7,000 6 42,000 Structure Sub Total (A) 3,588,050 B. Assistance B-1 Shifting Assistance Numbers 5,000 6 30,000 B-2 Training Assistance Numbers 12,000 11 132,000 B-3 Loss of Income Numbers 30,000 11 330,000 B-4 Assistance to Vulnerable Households Numbers 10,000 5 50,000 B-5 Assistance for Documentation (Stamp Numbers 10,000 5 50,000 Duty) for titleholders Sub Total (B) 592,000 C Resettlement Plan Implementation Support Cost C-1 Hiring of Resettlement Support Staff Person Month 100,000 36 3,600,000 at DCC/PIU C-2 Administrative Cost Lump Sum 1,000,000 Subtotal C 4,600,000 Total (A+B+C) 8,780,050 Contingency (10%) 878,005 GRAND TOTAL 9,658,055 GRAND TOTAL (Million Tk) 9.66 GRAND TOTAL (Million USD) 0.13 DCC = Dhaka City Corporation, PIU = Project Implementation Unit.

18

X. INSTITUTIONAL ARRANGEMENTS

A. Project Management Coordination Unit

44. The LGED will be the executing agency responsible for overall guidance and project implementation. A PMCU headed by a Project Director will implement the project investments and will be responsible for overall planning, management, coordination, supervision and progress monitoring of the CRDP in the two regions. The PMCU will ensure compliance with assurances, including safeguards and preparing and submitting reports, resettlement plan monitoring updates. To ensure effective implementation of the land acquisition and resettlement aspects, two full time PMCU resettlement safeguard officers will be recruited, including one Resettlement Compliance Officer primarily responsible for compliance with legal requirements of the Government, and one Resettlement Surveyor responsible for overseeing PIU preparation of the Resettlement Plan for subprojects and data collection. The MDSC will recruit one international and one national resettlement specialist to assist the PMCU in this regard. The PMCU will review monthly reports submitted by PIUs and will consolidate them into quarterly reports to ADB. Corrective actions to be taken when necessary based on close monitoring and results of grievance redress process.

B. Project Implementation Unit

45. The subproject will be managed and implemented through the PIU based in Savar Upazila Parishad The PIU will be responsible for carrying out the detailed design of the subprojects and updating Resettlement Plans for the sample subprojects and prepare new Resettlement Plans for future subprojects under the sector approach The PIU will ensure compliance with safeguards requirements of the Government and ADB. The PIU will be responsible for day-to-day monitoring of the project progress, including the implementation of the resettlement provisions in the project.

46. The capacity to implement safeguards planning and implementation at the PIU level is not currently adequate. Therefore, it is proposed that resettlement support staff (or facilitators) at the PIU level will be recruited. The number of resettlement support staff at each PIU will be commensurate to the scale of involuntary resettlement impacts (e.g., the greater the impact, the greater number of support staff needed). All PIU and PMCU safeguards staff will undergo training conducted by the consultant team’s resettlement specialists. Each PIU will prepare monitoring reports on all aspects concerning to resettlement planning and implementation of the land acquisition and resettlement issues and report to the PMCU on a monthly basis.

C. Management, Design and Supervision Consultants

47. The MDSC will hire one IRS and one NRS. They will be responsible for updating/finalizing the Resettlement Plans of sample subprojects in accordance with this Resettlement Framework and based on the detailed engineering design. These specialists will also prepare new Resettlement Plans for future subprojects under the sector approach consistent with this Resettlement Framework. This will be done in close coordination with PIU resettlement support staff and PMCU resettlement officers. The IRS and the NRS will assist in the overall supervision of the projects and ensure all plans are implemented in a smooth and timely manner in accordance with the provisions of the Resettlement Plan. They will also prepare and implement training and capacity development programs for resettlement planning for the PIU and PMCU safeguards staff (see section below on Training and Capacity Building), and will closely work with the PMCU and PIUs to ensure displaced persons are compensated before displacement occurs, including ongoing rehabilitation measures. Further details on 19 agencies responsible for Resettlement Plan activities are in Table 12 and the organization chart for Resettlement Plan implementation is depicted in Figure 2.

Table 12: Institutional Roles and Responsibilities Activity Responsible Agency A. Subproject Initiation Stage and Institutional Setup Formation of PMCU. LGED Formation of PIU. LGED Finalization of sites for subprojects. PMCU/PIU/MDSC Disclosure of proposed land acquisition and subproject details PIU/PMCU by issuing Public Notice. Meetings at community/household level with displaced persons. PIU Capacity Building training. MDSC/IRS B. Resettlement Plan Preparation/Updating Stage Resettlement screening and categorization form and submission PIU/PMCU to ADB for each subproject. ADB to confirm resettlement categorization. ADB Census of 100% displaced persons and socioeconomic survey. PIU/PMCU Screening of vulnerable displaced persons. PIU/PMCU Survey on unit prices for computing replacement costs. PIU/PMCU Calculation of compensation and entitlements. PIU/PMCU Update of sample subproject Resettlement Plans and preparing PIU/PMCU new Resettlement Plans in accordance with Resettlement Framework. Consultations with displaced persons on entitlements. PIU/PMCU Compliance with disclosure requirements. Finalize Resettlement Plans and submit to ADB. All draft PIU/PMCU Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Incorporate all comments and suggestions to Resettlement PIU/PMCU Plans. Web disclosure ADB/PMCU C. Resettlement Plan Implementation Stage Issuance of identification cards to displaced persons PIU/PMCU Detailed schedule for compensation PIU/PMCU Distribution of relocation notices to displaced persons PIU/PMCU Award of checks for land compensation PIU/PMCU Award of Checks for other compensation and assistance/ PIU/PMCU rehabilitation Confirm with ADB in writing when payment of entitled PMCU/PIU compensation to Displaced persons has been completed. Permission to contractor to begin works once compensation to displaced persons is confirmed (note: other income rehabilitation to continue after civil works commence). Notice to proceed for civil works is issued on sections where PIU/PMCU compensation is paid. Demolishing/ relocation of affected structures/assets PIU/PMCU Income restoration program and training PIU/PMCU Grievances redress mechanism PIU/PMCU/GRC Internal monitoring PIU/PMCU Review of Resettlement Plan implementation by external expert External Expert through a compliance report for projects with significant impacts ADB = Asian Development Bank, IRS = International Resettlement Specialist, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

20

Figure 2: Organization Chart for Resettlement Plan Implementation

LGED ADB

PMCU

1 Resettlement Compliance Officer, 1 Resettlement Surveyor

MDSC 1 International Resettlement Specialist, 1 National Resettlement Specialist

PIU Resettlement Support staff

DISPLACED PERSONS

ADB = Asian Development Bank, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

XI. IMPLEMENTATION SCHEDULE

48. Land acquisition, compensation and relocation of displaced persons cannot commence until the Resettlement Plan has been cleared by ADB. All entitlements are to be paid prior to displacement. Written confirmation is required by the PMCU to ADB stating that all compensation has been paid to displaced persons. Only then can construction works begin on sections where compensation has been paid. The project will be implemented over six years (January 2011 to December 2016). The implementation of the Resettlement Plan will include: (i) identification of cut-off date and notification; (ii) verification of losses and extent of impacts; (iii) finalization of entitlements and distribution of identity cards (iv) consultations with displaced persons on their needs and priorities; and (v) resettlement, provision of compensation and assistance, and income restoration for displaced persons. The expected implementation schedule for a subproject is given in Table 13.

Table 13: Implementation Schedule Activity Months

1 234567891 1 1 1 1 1 1 1 1 0 1 2 3 4 5 6 7 8 Establishment of PMCU and PIU.  Appointment of safeguards staff in  PMCU and PIUs. Appointment of international and  national resettlement specialists on consultant team. 21

Activity Months

Formation of GRC at PIU and PMCU  level. Census surveys (issuance of     identification cards). Send screening and categorization  form for subprojects to ADB. Consultations and disclosure.                  Confirmation of government land to   be used and transfer from other departments. Resettlement Plan preparation.      Resettlement Plan review and  approval (PMCU and ADB). All draft Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Issue notice to displaced persons.  Compensation prior to displacement    and income rehabilitation ongoing. Written confirmation from PMCU to  ADB that all compensation paid in sections ready for construction. Permission to contractor to begin works once compensation to displaced persons is confirmed. Relocation as required    Takeover possession of acquired    property Handover land to contractors  Start of civil works  Skills training as required for income       restoration Grievance Redress Mechanism Internal monitoring               

Monthly monitoring reports (PIU to                PMCU) Quarterly monitoring reports (PMCU                to ADB) Rehabilitation of temporarily Immediately occupied lands after construction ADB = Asian Development Bank, GRC = Grievance Redress Committee, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. Note: The Resettlement Plan will be updated based on final detailed design and displaced person census and surveys. Endorsement and disclosure of finalized Resettlement Plans consistent with the Resettlement Framework to be undertaken.

XII. MONITORING AND REPORTING

49. The extent of monitoring activities will be commensurate with the project’s risks and impacts. Monthly monitoring reports to be submitted by PIU to PMCU. PMCU to consolidate monthly reports into quarterly monitoring reports to ADB. These reports should form a part of the project progress reports submitted by PMCU to ADB.

22

50. The objectives of monitoring are to: (i) ensure that the standard of living of displaced persons are restored or improved; (ii) ascertain whether activities are progressing as per schedule and the timelines are being met; (iii) assess if compensation, rehabilitation measures are sufficient; (iv) identify problems or potential issues; and (v) identify methods to rapidly to mitigate problems. The above information will be collected by executing and implementing agencies through its PMCU and respective PIU which is responsible for monitoring the day-to- day resettlement activities of the project through the following instruments:

(i) Review of census information for all displaced persons; (ii) Consultation and informal interviews with displaced persons; (iii) In-depth case studies; (iv) Sample survey of displaced persons; (v) Key informant interviews; and (vi) Community public meetings.

51. Internal Monitoring. The internal monitoring by PMCU/PIU will include (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socio-economic monitoring during and after the relocation process to ensure that people are settled and recovering. This will utilize the baseline information established by the socio-economic survey of displaced persons undertaken during subproject preparation; and (iii) overall monitoring whether recovery has taken place successfully and on time. Monitoring will also include the following:

(i) Communication with and documentation of reactions from displaced persons. (ii) Information from displaced persons on entitlements, options, alternative developments, etc. (iii) Valuation of properties. (iv) Usages of grievance redress mechanism. (v) Disbursement of compensation amounts and all assistance. (vi) Physical progress of the Resettlement Plan implementation which will include relocation of displaced persons and affected community properties.

52. The indicators for achievement of objectives during Resettlement Plan implementation are of two kinds such as (i) Process Indicators (Indicating project inputs, expenditure, staff deployment, etc.); and (ii) Output Indicators: Indicating results in terms of numbers of displaced persons compensated, area of temporarily occupied lands restored with topsoil (and other pre- project features), number of displaced persons provided with skills training, etc. Input and output indicators related to physical progress of the work will include items such as:

(i) Training of executing and implementing agencies and other staff completed. (ii) Census, assets inventories, assessments and socio-economic studies completed. (iii) Grievance redress procedures in-place and functionality. (iv) Compensation payments disbursed. (v) Relocation of displaced persons completed. (vi) Project employment provided to displaced persons. (vii) Infrastructure rehabilitated or constructed. (viii) Income restoration activities initiated. (ix) Skills training of displaced persons initiated. (x) Number of households displaced and resettled. (xi) Monitoring and evaluation reports submitted.

Appendix 1 23

CENSUS QUESTIONNAIRE FOR PERMANENT LAND ACQUISITION AND RESETTLEMENT

1. Questionnaire No: ______Date: ...... 2. Name of the Project Component /Site:

3. Name of the Mohallah:

4. Name of the Street:

5. Name of the Ward:

6. Name of the Pourashava:

7. Name of the Upazila:

8. Name of the Zilla/District:

9. Name of the Province:

10. Plot No. ------.

11. Ownership of the Land

1. Private 2. Government 3. Religious 4. Community 5. Khas 6. Others 12. Legal Status of Land/Owner

1. Legal/Title Holder 2. Encroacher 3. Squatter

13. Type of Land 1. Agricultural 2. Residential 3. Commercial 4. Fallow 5. Forest

14. Total Area of the Land/ Plot (Incase a portion of the land/ plot to be acquired/affected) (in Bigha) ......

15. Area to be Acquired / Affected Land (in Katha) ......

16. Total Land you possess (Total possession: affected + unaffected) (in Katha) Total......

24 Appendix 1

17. Rate of the Land (Per Katha) 1. Market Rate (Tk./Rs.)...... ……2. Government Rate (Tk.)...... 18. Name of the Land Holder ......

19. Father’s Name ...... 20. Any of the following person associated with the Land

A. Agricultural Labour 1. Yes 2. No

B. Tenant 1. Yes 2. No

C. Share-Croppers 1. Yes 2. No

D. Lease Holder 1. Yes 2. No

21. If yes, their Numbers A. Agricultural Labour…………………….. B. Tenant……………………………………. C. Share-Croppers ………………………… D. Lease Holder…………………………… 22. Number of trees within the affected area

1. Total………………2. Fruit Bearing………3. Non-fruit Bearing………… 3. Timber…………………….

23. Any Building/structure in the Affected Land 1. Yes...... 2. No...... 24. Use of Structure

1 House 2 Boundary Walls/Fences 3 Residential-cum Commercial 4 Industry 5 Shops 6 Hotel/Restaurant 7 Small Eatery 8 Kiosks and Vendors 9 Mobile Vendors 10 Farm house 11 Gas Station 12 Private Clinic 13 Workshops 14 Govt. Offices 15 School / College 16 Hand pump 17 Hospitals 18 Water /Gas Pipe Line 19 Bus Stop 20 Transmission Lines 21 Mosque 22 Church 23 Mazar 24 Cemetery 25 Temple 26 Community centre 27 Cattle shed 28 Storage 29 Others

Appendix 1 25

25. Total area of the structure (in Square Meter) …………………..

26. Area of the affected structure (in Square Meter) …………………..

27. Type of Structure

1. Temporary 2. Semi-Permanent 3. Permanent

28. Age of the structure (Years)…………………….

29. Type of Construction Structure

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

30. Is the house/structure have the following?

A. Tenant 1. Yes 2. No

B. Employee in Commercial Structure 1. Yes 2. No

31. If yes, their Numbers A. Tenant…………………….. B. Employee…………………

32. Is the building/structure constructed by Tenant? 1. Yes 2. No

33. How much monthly rent you pay?......

34. Market Value of the Structure (in Tk.)......

35. Number of family members. Total………… Male …… Female……….

26 Appendix 1

36. Number of family members above 18 years

Total………… Male …… Female……….

37. Is it a woman headed household? 1. Yes 2. No

38. Is it a household owned by physically handicapped? 1. Yes 2. No.

39. Main Occupation of the Head of the Household (Main Source of Income)

1. Agriculture 2. Commercial /business 3. Service Holder. 4. Others (Specify)……

40. Total Monthly income of the family (Tk.)………….

41. Willing to shift

1. Voluntarily 2. Need Resettlement

42. Compensation Option

1. Land for land loss 2. Cash for Land loss 3. House/Shop for House/ Shop loss 4. Cash for House/ Shop loss

43. Desire Assistance and other help

1. Shifting Allowance 2. Employment Opportunities in Construction work 3. Assistance/ Loan from other ongoing development scheme 4. Training for Vocational activities 5. Others (specify ...... )

44. Is there alternate site available for relocation? 1. Yes 2. No. 45. If Yes, How far and the name of the place……………………………. Appendix 1 27

DETAILS OF THE AFFECTED PEOPLE

Sl. No Name of the Family Member Age Sex Occupation Marital status Education In 1. Male 1. Service 1. Married 1.Illiterate Years 2. Female 2. Business 2. unmarried 2.Literate 3. Agriculture 3. Widow 3.Up to Secondary 4. Study 4.Widower 4.Higher Secondary 5. Housewife 5. Others 5.Graduate 6. Labour 6. NA 6.Masters 7. Unemployed 7.Ph-D 8. Professional 8. NA 9. NA

1 2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

28 Appendix 2

CENSUS QUESTIONNAIRE: INVENTORY OF TEMPORARY LOSS

1. Questionnaire No: ______Date: ...... 2. Name of the Project Component /Site:

3. Name of the Mohallah:

4. Name of the Street:

5. Name of the Ward:

6. Name of the Pourashava:

7. Name of the Upazila:

8. Name of the Zilla/District:

9. Name of the Province:

10. Property No. ------

11. Location 1. Left 2. Right

12. Status of the Property 1. Squatters 2. Encroachers

13. Name of the Owner ......

14. Father’s Name ......

15. Use of Structure 1 House 2 Huts 3 Sheds 4 Shops 5 Kiosks and Vendors 6 Mobile Vendors 7 Small Eatery/Teas Stall 8 Cattle shed 9 Boundary Walls/Fences

16. Area of the affected structure (in Square Meter) …………………..

17. Type of Structure 1. Temporary 2. Semi-Permanent

18. Age of the structure (Years)…………………….

Appendix 2 29

19. Type of Construction Structure

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

20. Market Value of the Structure (in Tk.)......

21. Number of family members. Total………… Male …… Female……….

22. Is it a woman headed household?

1. Yes 2. No

23. Is it a household owned by physically handicapped? 1. Yes 2. No.

24. Total Monthly income of the family (Tk.)………….

25. Willing to shift

1. Voluntarily 2. Need Resettlement

26. Compensation Option

1. Alternate structure 2. Cash for structure loss

27. Desire Assistance and other help 1. Shifting Allowance 2. Employment Opportunities in Construction work 4. License to resume the current activities 5. Others (specify ...... )

28. Is there alternate site available for relocation? 1. Yes 2. No. 29. If Yes, How far and the name of the place…………………………….

30 Appendix 3

SUMMARY OF PUBLIC CONSULTATION AND FOCUS GROUP DISCUSSIONS

Date of Consultations: 04.07.2010 Number of Consultations: 03 numbers Place of Consultations: Amtola, Kath gora, Jamgora, Gonak Bari (road and pump house location) Ashulia Number of Participants: 30

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 1 Have you heard about CRDP Most of the participants have heard or informed about the CRDP (City Region Development Project. But many of them think development of roads is necessary. In Project)? some location it is essential due to industrialization and roads are being used for different purposes. Besides some walk ways are needed for a number of workers of the industries as because everyday thousands of female and male workers also use same roads. Beside, in some area people claimed for the development of drainage system. Also some community people also want water supply at home. 2 If yes, where from They have heard from the local leaders and officials. Many participants guessed that there must some road development which would come in the up coming future and also desired for the development of Ashulia as a growth centre and a new prospecting city 3 General perception about the All most all participants have appreciated the project activities. They project and the awareness about thought the project will bring a tremendous development for the locality. the proposed project. The entire Ashulia economic activities are based on production of the industries. Majority people of the community are migrated from different districts and working in those industries. Therefore community people have demanded redevelopment of the road and drainage system for the betterment of the community as well as economic development of the country. 4 Do others in this locality support According to the participants opinion the project will bring positive result this project? for people and there is no doubt about people’s cordial support to this project. Even some of them said that they will help the implementing agencies by any terms of condition. Only a very few people said they will ask proper compensation if their land or structure get affected due to the impact of the project. 5 Any critical issue or concern by No, there are no critical issues related to this project. In general the the local people regarding the entire roads in Ashulia are very wide and there is no need for project? acquisition. Only few trees and a very small number of structures will be temporarily affected during construction. Besides, for the construction of production tube wells/ pump house the private lands will be required and community people are eagerly like to provide those lands for bundling water pump. 6 Any criteria you would like to Some participants have requested to serve water to every house hold see considered during project and in some extent to the poor community in law rate. Also asked for design, construction and some water point in the road sides for the vulnerable people who would operation stage? not be able to pay change for water.

7 Employment Potential in the There are huge employment opportunities of the construction of the project which is of benefit to project such as increase in petty shop business and employment of village local labor. Appendix 3 31

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 8 Ethnic Minorities /Indigenous No peoples composition (If there are Indigenous People, please mention about the names of the IP and number of households) 9 Numbers of Industrial Units in Huge industries are d in Ashulia, these are various types of industries the Mohallah/town and and also Export Processing Zone located in the area. surrounding area

10 Is the Area Electrified Yes, the major proportion of the area has electrical connection provided by Pauroshava but still there is some area has no street light. 11 Source of drinking water Tube-well water is the main drinking water sources of the community. In the Ashulia area. But most of the household owners installed own tube-well and provided connection to the tenants’. After industrialization of the area, local people constructed one room house for the migrant labor (at least built 10 rooms in each house). In summer, most of these water pumps can not provide sufficient water due to underground water scarcity. Most of these tube wells are 150-200 meters in depth. So there is always water scarcity in summer season. 12 Loss of residential/commercial There will be few permanent loss of land due to the project especially structures, if any due to the construction of water pump. But there will be very few losses of trees project and temporary structure for wading road only one location. 13 Loss of community life like any There will be no loss of community life or market place as such except Market Places or community few scattered vendors and squatters who need to be sifted. activities to be affected 14 Poverty Level: Is the village poor Almost 80% people migrant labor and work in the different impurities. or very poor or well off Local people are mostly involved in land buying and selling business and the most common income earning sources is rental house /room for the migrant labor. Besides some shops, transport business has been increased due to highly increasing tendency of industrialization. 15 Education Status: Literate, Less then 50% of community people are educated but have no higher illiterate etc level of education(very few have), Majority children go to school but could not continue higher education instead after finishing primary or secondary education they go for job. Participants said outsiders are more educated then local community. 16 Employment Status: Percentage All of the migrant people of the community work in the industries. About of employment/ unemployment/ Three lac people are working in the area are migrant labor. Local underemployment people are mostly depending on the income of rental room. Majority of the local people now engaged in room rental business. Still there is very few which is about 10% of the people are still unemployed. 17 Migration Pattern (If any), inward Yes, the area has high tendency of in migration. Most of the people of or outward the locality have been migrated form the whole country. Community people very less in terms of its quantity. 18 Are you satisfied with the Most of the people are satisfied service provided by Pauroshava. The present infrastructure facility in original roads were constructed by CARE and roads are very wide the town and locality compare to any region. This has also given scope for investment .They also suggested for more services such as adequate street light, public toilet for male female both and solid waste management in a planed way. 19 Do you face any problem Yes, lack of drainage system is a serious problem. In the rainy season regarding the exiting water many of the roads go down under water. And another problem is water supply/solid waste scarcity during the dry season. Some participant said if the roads and management/river drainage the drain problems get solve the land pries will be high and

32 Appendix 3

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions port/Drainage/Traffic system? more development prospect will be addressed from government and private sector.

20 If there is any problems related Yes, waste management is very necessary for the community to these services, do you think that any upgradation is necessary? 21 For this upgradation the Yes very much, due to drainage problem and poor road quality the road/street/path /drainage may community as well the business getting suffered. The existing roads are get affected- what do you think already used by huge number of transport and public which caused about that- is it desirable? more trouble. Development water management and road will bring better opportunity for the economic growth of the community as well as the nation. 22 How can this affect your present The economic condition of Ahsulia focused on huge industries and living or activity labor forces and production. The price of the land of the area is also increasing day by day. Construction of better road and drainage system will bring a prospective situation of the Ashulia people. 23 The project may need shifting of There is little temporary structure which needs to be shifted. However, some encroachments and some help in the form of compensation and assistance will be desirable squatters .Would you like to shift and people will be able to shift voluntarily if they get compensation. from here on your own? 24 Where will you like to shift They have some plan for shifting, or if even they get sufficient time during this period? before construction they will find place for shifting. But despite all every body want the development. 25 If requested to shift, would you It is up to the situation. May be the owner do not allow them to come like to return here? back. Most of the shop owner thinks, after road construction the importance will be changed. Some said that there might not be possible to come back in same location after the implementation of the project. 26 Is there available alternate place Yes, it is within half kilometer area. for relocation? If yes, how far and the name of the place 27 Perceived losses from the Temporary loss of the business. Project- 28 If losses are perceived, what is Cash Compensation for the land owners and d squatters and if possible the expected compensation you then license for reopening their business. The Pourashava may issue would desire license to the affected vendors and squatters.

29 Perceived benefits from the Drainage and road construction in proper way. Better traffic, water Project- supply and drainage system.

30 Do you think that the local Yes, cooperation from the local people will be there during the project residents would like to implementation provided peoples vies are taken in to consideration by participate in this work the Government Implementing agency such as DPHE and LGED in Upazila 31 Do you think that the local Yes , local people should be informed people would like to get regular information regarding this Project? Appendix 3 33

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 32 Will it be through informal or Yes, it is very important to have or will have consultation with the formal consultation community before the implementation. Both formal and informal consultation is desired through the help of ward councilor. 33 Will the project cause landslides No or soil erosion in the locality 34 Will the project cause No widespread imbalance by cutting fruit and commercial trees in the locality. 35 Will the project cause health and No safety issues in the area. 36 Resettlement and Land Minimum land acquisition is foreseen for the construction of production acquisition (if foreseen due to tube well. They have not been experienced with any previous land project components especially acquisition and resettlement activities. on private land). Has there been land acquisition before? If yes, what was the process of land acquisition and compensation package? 37 Protected areas (national park, No protected forest, religiously sensitive sites, historical or archaeological sites), if any 38 Health status, Availability of Some government hospitals are there but most of the people prefer to Hospitals and over all go Dhaka for treatment and diagnosis. People are aware about the environmental condition. Is there HIV/AIDS any chronic disease prevalent in this area and are you aware about HIV/AIDS and STP? 39 Will the project siting adversely No change migration pattern of animals that would destroy fields, habitats 40 What other organizations of a Some organizations provides loan to the community. BRAC ASHA and social nature (NGOs/CBOs/ Civil few local credit based organization are working in the locality. Society) active in the area? Name of these organizations 41 Will there be likely involvement Yes of local people in the implementation of the project? 42 Please indicate what kind of Women from better income group work in Bank, office and NGO. economic/ non-economic Majority women of the poor income group who has migrated are activities female members of working in Garments and other industries. In the poor section of the your family are engaged in community all women are involved in different income generating activities. All the household activities are done by the women. 43 Does your female member have To some extent they can take some decision, not completely. Decisions any say, in decision making of at family level are taken as sharing basis especially in better off or household matters middle types of family income group. But in the poor section and the family where women work are more involved in household decision making process. Most of the income earner women has some voice and mobility them the local women of the community.

34 Appendix 3

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 44 How safe do you regard the Women of the community are safe but not every where. The area mobility of women in where street light is not available and little remote women worker neighborhood/village always faces different kind of incident such as scathing money bag, tease or physical abuse. In general the area where enough street lights available, women enjoy safe mobility but with in sufficient light women suffer in regular way. 45 Do the women of your Yes, Most of the women of the community go freely for any purposes. household can freely go outside Women mobility is very high and they can go out for any purposes at to work, for marketing, or day and night time. accessing hospitals, educational institutes, etc? 46 How often women of your All most all of the family has some drinking water source but still some household go outside the house But for the women member of the poor family, they fetch water from to fetch water in a week? outsides. Poor people fetch water from some water points and tube well of the other people twice a day. 47 Do you have a toilet at your Yes, most of the people have toilet, poor people have ring latrine or household? sharing Latrine or community latrine 48 Do you have adequate street Yes, there are some street lights, however, these are not enough lighting during the night?

49 Any Other Issues you may feel As we already mentioned that we need better arrangement of road and to share: drainage system. More over water is also one of the problems of the locality. So these three issues are most concerned issues for the people of the Ashulia and we want very definite solution form the government. 50 Is this consultation useful? Yes, very useful, it gives us freedom to speak our opinion on the Comments coming project and also we think government will conceder the situation and take active steps on that. .

CBO = community-based organization, CRDP = City Region Development Project, DPHE = Department of Public Health Engineering, LGED = Local Government Engineering Department, NGO = nongovernmental organization, STP = sewerage treatment plant.

LIST OF PARTICIPANTS S.No. Name Occupation Sex (M/F) Age (Years) 1 Jamir Sharkear Service Male 46 2 Hossain Ali Carpenter Male 45 3 Anwar Hussain Service Male 28 4 Badal Rickshaw puller Male 34 5 Amir Hussain Owner of tea shop Male 40 6 Bashir Working in Tea Male 40 7 Rezaul karim Studentll Male 22 8 Sagar Truck helper Male 18 9 Narayan Chandra dash Constructor Male 45 10 Masud Driver Male 22 11 Hazi Rahaman Agriculture Male 58 12 Abdul Khalek Day labor Male 42 13 Fazul Haque Agriculture Male 43 14 Goljar Service Male 35 15 Somirudding Carpenter Male 50 Appendix 3 35

S.No. Name Occupation Sex (M/F) Age (Years) 16 Razzak Van puller Male 39 17 Hamayet shek Business Male 53 18 Joli Student Female 16 19 Khodeja Service Female 39 20 Hasan Service Male 24 21 Monjurl Agriculture Mael 50 22 Jalil Service Mael 20 23 Shanty Service Female 38 24 Hasina Service Female 40 25 Nosimon Survive Female 25 26 Khodeja House wife Female 28 27 Saiful Driver Male 16 28 Mamun Helper Male 19 29 Saddam Driver Male 21 30 Juel Mechanic Male 28

36 Appendix 4

FUTURE CONSULTATION AND DISCLOSURE ROLES AND RESPONSIBILITIES Responsible Project Phase Activities Details Agency - Subproject information dissemination on various components. -Leaflets posted/distributed - Disclosure of preliminary plans for containing information on the proposed land acquisition. Project Initiation subproject in subproject area. - Preliminary Information sharing PIU/PMCU Stage -Public notice issued in public places about the tentative alignment/sites including newspapers and direct with the DPs in case of temporary consultation with displaced persons. impact on business, income and livelihood. -Further consultations with displaced persons and households, titled and non-titled. -Summary Resettlement Framework Stakeholder consultations. PIU/PMCU made available to all displaced persons at the convenient place which is easily accessible and should be in local language. Disclosure of final entitlements and Resettlement Resettlement Plans disclosed to all rehabilitation packages and disclosure PIU/PMCU Plan displaced persons in local language of draft Resettlement Plan. Preparation -Review and approval of Phase Resettlement Plan by executing agency. -Review and clearance of Resettlement Plan by ADB (prior to Finalization of Resettlement Plan. PIU/PMCU award of contract). -Web disclosure of the Resettlement Plan. -Disclosure of the Final Resettlement Plan to displaced persons -Continued discussions and information disclosure to displaced persons; -Payment of entitlements (all compensation must be paid before displacement occurs. - Grievance Redress Mechanism activated. -Written notification from PMCU to Resettlement Ongoing consultation with displaced ADB that all compensation paid Plan persons during Resettlement Plan before displacement occurs. PIU/PMCU/GRC Implementation implementation. Construction can begin on sections Stage where compensation is paid and community notified of start date of civil works. Displaced persons with unresolved grievances or disputes over land ownership, compensation amounts, etc. are notified of any compensation payments set aside by PIU in separate escrow accounts to be paid when disputes are resolved. ADB = Asian Development Bank, GRC = Grievance Redress Committee, PIU = Project Implementation Unit, PMCU= Project Management Cordination Unit.

Appendix 5 37

MONITORING INDICATORS AND SAMPLE FOR STATUS REPORT S. N. R&R Activities Progress Remarks Pre Construction Activities and R&R Activities 1 Assessment of Resettlement impacts due to changes in project design (If required) 2 Preparation/updating of Resettlement Plan based on changes in project design 3 Approval of updated Resettlement Plan from ADB 4 Disclosure of updated Resettlement Plan 5 Establishment of Grievance Redress Committee 6 Capacity building of PIU Verification of displaced persons Census list; assessment on compensation and assistance, and readjustment 7 Land Acquisition Resettlement Plan Implementation 1 Payment of Compensation as per replacement value of land & assets to displaced persons 2 Disbursement of assistance to title holders 3 Disbursement of assistance to non-title holders 4 Disbursement of special assistance to Vulnerable groups 5 Replacement/ shifting of community property resources 6 Reinstallation of public utilities 7 Records of Grievance Redressal 8 Temporary Relocation of Hawkers and Vendors 9 Income Restoration Measures through training Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or use of children as labour 2 Prohibition of Forced or Compulsory Labour 3 Ensure equal pay for equal work to both men and women 4 Implementation of all statutory provisions on labour like health, safety, welfare, sanitation, and working conditions 5 Maintenance of employment records of workers ADB = Asian Development Bank, PIU = Project Implementation Unit, R&R = Resettlement & Rehabilitation.

City Region Development Project (RRP BAN 39298)

Resettlement Plan

Document Stage: Draft for Consultation Project Number: 39298 July 2010

BAN: City Region Development Project—Banani Integrated Traffic Management Subproject

Prepared By: Local Government Engineering Department (LGED), Government of Bangladesh

The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. ABBREVIATIONS

ADB — Asian Development Bank ARIPO — Acquisition and Requisition of Immovable Property Ordinance CRDP — City Road Development Project DCC — Dhaka City Corporation DOE — Department of Environment GRC — Grievance Redress Committee GRM — Grievance Redress Mechanism IRS — International Resettlement Specialist LGED — Local Government Engineering Department MDSC — Management, Design and Supervision Consultant NRS — National Resettlement Specialist PMCU — Project Management Coordination Unit PIU — Project Implementation Unit ROW — right of way RSS — Resettlement Support Staff SPS — Safeguard Policy Statement

TABLE OF CONTENTS

EXECUTIVE SUMMARY i

I. PROJECT DESCRIPTION 1 A. Overview 1 B. Subproject Components 1

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 3

III. SOCIOECONOMIC INFORMATION AND PROFILE 3 A. Census survey 3

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 6 A. Public Consultation 6 B. Information Disclosure 7 C. Continued Consultation and Participation 7

V. GRIEVANCE REDRESS MECHANISMS 8

VI. LEGAL FRAMEWORK 9

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS 10 A. Eligibility 10 B. Entitlements 10 C. Assessment of Compensation Unit Values 12

VIII. INCOME RESTORATION AND REHABILITATION 12 A. Basic Provision for Relocation 12 B. Income and Livelihood Rehabilitiation 12

IX. RESETTLEMENT BUDGET AND FINANCING PLAN 13

X. INSTITUTIONAL ARRANGEMENTS 14 A. Project Management Coordination Unit 14 B. Project Implementation Unit 14 C. Management, Design and Supervision Consultants 15

XI. IMPLEMENTATION SCHEDULE 17

XII. MONITORING AND REPORTING 18

Appendixes 1. Description of Road Network in Banani 20 2. Inventory of Temporary Loss on Right of Way 21 3. Summary of Consultations 23 4. Consultation and Disclosure Roles and Responsibilities 29 5. Monitoring Indicators and Sample for Status Report 30

EXECUTIVE SUMMARY

1. The City Region Development Project (CRDP, the Project) will be financed by the Asian Development Bank (ADB) and is being formulated as a project loan using the sector approach to be implemented over a six-year period (January 2011 to December 2016). This document is a draft Resettlement Plan prepared for the Banani integrated traffic management subproject. It is based on a feasibility level study and preliminary engineering design and will be updated at the final detailed engineering stage. The Resettlement Plan is prepared in accordance with the ADB Safeguard Policy Statement, 2009 (SPS), Government of Bangladesh’s (the Government) policy, i.e., the Acquisition and Requisition of Immovable Property Ordinance, 1982 (ARIPO), and the Resettlement Framework adopted for CRDP. It is classified as Category B according to ADB’s SPS as minimal land acquisition and resettlement is required for this subproject.

2. The Banani subproject envisages integrated traffic management to achieve a major upgrade of the public realm and achieve an improved quality of life for residents and businesses.

3. Summary of Resettlement Impacts. There is no land acquisition required for this subproject. The subproject will impact 225 mobile street hawkers and shop vendors who operate kiosks informally within the right of way (ROW). No residential displacement is envisioned. The hawker structures are considered temporary and therefore these businesses will experience temporary economic displacement. The impacts are further detailed and mitigation measures and entitlements are provided in the Resettlement Plan.

4. Public Consultations. Consultations were carried out during Resettlement Plan preparation and will continue throughout the subproject cycle. A grievance redress mechanism (GRM) will be made available as explained in this Resettlement Plan.

5. Implementation Arrangements. The subproject will be managed and implemented through a Project Implementation Unit (PIU) based in Dhaka City Corporation Banani office with the overall support and guidance of the Project Management Coordination Unit (PMCU) based at the Local Government Engineering Department (LGED) Headquarters in Dhaka. The detailed design, preparation and implementation of the capital investments will be supported by: (i) consultancy support (both international and national); and (ii) technical support from LGED. The PIU will implement the Resettlement Plan with support from the PMCU and consultants. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per the entitlement matrix within this Resettlement Plan. Income restoration assistance to the affected persons includes both short and medium term strategies. The Government will provide all funds for resettlement in a timely manner.

6. Resettlement Plan Implementation and Monitoring. All compensation is to be paid prior to displacement however, ongoing income rehabilitation activities will continue after construction begins. Written confirmation of full compensation to displaced persons must be made to ADB prior to commencement of civil works in sections ready for construction. The estimated total period of the implementation of the Resettlement Plan is 13 months. Monthly monitoring reports will be submitted by PIU to PMCU. PMCU will consolidate monthly reports into semi-annual monitoring reports or as part of the regular project reporting and will submit to ADB.

I. PROJECT DESCRIPTION

A. Overview

1. The City Region Development Project (CRDP, the Project) emphasizes economic growth in Dhaka and Khulna city regions of Bangladesh through (i) creation of an enabling environment towards improved governance and capacity building of the local governments; and (ii) prioritized investments in infrastructure sectors in the two regions. The objectives of CRDP are (i) to improve the regional economic and social context through long-term development plans and investment programs, set within an institutional and regulatory context that will ensure implementation and review; (ii) to improve the capacity and mandate of local government to govern and to invest in improved economic activity at local level; (iii) to improve the economic context for sustainable commercial and industrial growth; and (iv) to improve the economic and social needs of the urban population, as an inclusive aspect of the CRDP. The subprojects are largely built around ‘integrated area planning’ principles which enhance economic activity in the regional context and provide opportunities for investment. The Banani subproject envisages integrated traffic management to achieve a major upgrade of the public realm and achieve an improved quality of life for residents and businesses.

2. This is a Resettlement Plan prepared for the Banani Integrated Traffic Management component (the subproject) which is in accordance with the ADB’s SPS, the Government’s policy, namely the ARIPO, and the Resettlement Framework1 adopted for the CRDP.

B. Subproject Components

3. Banani is a primarily residential area with mixed commercial activity located in north Dhaka, within Gulshan Thana area. The Subproject area covers 32 ha and contains 8.76 km of roads (including the bordering roads of Kamal Ataturk Avenue and Road 11). Several north- south roads serve as local distributors, even though the available carriageway widths are quite inadequate for the task. All east-west roads (other than Kamal Ataturk Avenue and Road 11) are local access roads: some are very narrow and several lack metalled surfaces. The basic characteristics of the existing road network are outlined in Appendix 1.

4. Preliminary Traffic Management Plan. The preliminary proposed District Traffic Management scheme for central Banani is specified in Tables 1 and 2. It may be noted that all but two of the major and minor roads are proposed into one-way streets. All but three of the local distributors are proposed one-way, with the exceptions being Roads 8, 10 and 11. However, Road 11 has a one-way eastbound section towards its western end to discourage through traffic, in combination with the prohibition of the right-turn northbound from New Airport Road. Vehicular access has been maintained in Road 11 for the benefit of frontage traders. It is proposed to wholly pedestrianize Road 17, which serves university premises and which is heavily thronged with pedestrians at most times. The internal one-way system has been proposed because it will make the roads safer for vehicles and pedestrians and it will also lengthen journey times within the subproject area, thereby discouraging drivers seeking short- cuts. Careful attention has been given to road and footway widths. Bearing such considerations in mind, the width requirements shown in Table 1 were developed for guidance purposes.

1 As per ADB’s Safeguards Requirement-4 (SR-4) of the SPS-2009, the sector approach requires preparation of Resettlement Framework to guide subproject selection, screening and categorization, social and resettlement assessment, and preparation and implementation of Resettlement Plans of subprojects and to facilitate compliance with the requirements specified in Safeguard Requirements 1–3. The Resettlement Framework is prepared in accordance with the Government and ADB policy related to land acquisition and resettlement. 2

Table 1: Proposed Road and Footway Plan Road Classification Width Remarks Local distributor (two-way) 8.5 m May be reduced to 7.0 m if wide vehicles or rickshaws are prohibited. Local distributor (one-way) 4.5 m May be reduced to 4.0 m where frontage constraints apply. Major access road (two-way) 7.0 m Scope for reduction not recommended. Major access road (one-way) 4.0 m May be reduced to 3.5 m in extreme situations. Possible scope for reduction to 6.0 m in Minor access road (two-way) 7.0 m constrained situations. Minor access road (one-way) 3.5 m May be reduced to 3.0 m in extreme situations. Sidewalk (commercial and 3.0 m May be expanded to 4.0 m or more where other high-activity streets) each side activity levels are high or where frontage positions allow. May be reduced to 1.5 m where necessary, or a 2.0 m Sidewalk (other streets) single 3.0 m sidewalk may be provided on one each side side of the road only. Car parking bay (parallel to May be reduced to 2.5 m in constrained 3.0 m the carriageway) situations. Depending on space available, may be considered on north-south local distributor or Rickshaw ‘station’ 3.0 m major access roads at junction approaches with KAA and Road 11.

5. Table 2 presents traffic management proposals for Banani. Most local access roads in the subproject area would be narrower than they are now. A narrower, safer road with proper sidewalks, planned on-street parking would greatly improve the character and operations in the subproject area. Redundant space could be properly landscaped, rather than becoming a dump for refuse and construction materials. It will be important to enlist the cooperation of residents and business tenants to ensure that standards are maintained.

Table 2: Proposed Traffic Management Improvements Road Length (m) Width (m) Remarks KAA 933 2 x (12/14) Rebuilt sidewalks 4 322 4.5/7.5 Minor access road, one-way northbound. Sidewalk to one side only. 6(0) 322 4.5/8.5 Local distributor, one-way southbound. 6(1) 144 4.0/7.5 Major access road, one-way westbound. 6(12) 122 3.0/7.5 Minor access road, one-way northbound. 6(2) 144 4.0/7.5 Major access road, one-way eastbound. 6(21) 122 3.0/7.5 Minor access road, one-way southbound. Local distributor, two-way, signals at junction with Road 11. 8 233 8.5/14.5 Parallel parking can be permitted in bays 2.5 m wide. Local distributor, two-way, signals at junction with Road 11 10 322 8.5/14.5 and KAA. Parallel parking can be permitted in bays 2.5 m wide. Local distributor, two-way, signals at junctions with Roads 8 11 1172 8.5/14.5 and 10 and New Airport Road. One-way eastbound between Roads 6 and 10. Local distributor, one-way, signals at junction with KAA, no 12 322 4.5/10.5 right turn from Road 11 westbound. Parallel parking can be permitted in bays 2.5 m wide. 13(0) 389 4.5/9 Major access road, one-way eastbound. 13(1) 194 3.5/7.5 Minor access road, one-way westbound. 13(2) 128 3.5/7.5 Minor access road, one-way westbound. 13(3) 161 3.5/7.5 Minor access road, one-way eastbound. 3

Road Length (m) Width (m) Remarks 13(4) 100 3.5/7.5 Minor access road, one-way southbound. 13/A(1) 266 3.5/7.5 Minor access road, one-way westbound. 13/A(2) 128 3.5/7.5 Minor access road, one-way northbound. 13/A(3) 67 3.5/7.5 Minor access road, one-way southbound. 13/B 194 3.5/7.5 Minor access road, one-way eastbound. 13/C(1) 200 3.5/7.5 Minor access road, one-way westbound. 13/C(2) 122 3.5/7.5 Minor access road, one-way westbound. 13/C(3) 61 3.5/7.5 Minor access road, one-way northbound. 15(1) 266 3.5/7.5 Minor access road, one-way eastbound. 15(2) 233 3.5/7.5 Minor access road, one-way southbound. Pedestrian street, shared surface type with block or sett 17(1) 144 15/15 surface dressing, residents’ access only. 17(2) 305 4.0/24 Major access road, one-way eastbound, parallel parking can be permitted in bays 2.5 m wide. Remaining width to be pedestrianised. 17(3) 389 4.0/20 Major access road, one-way westbound, parallel parking can be permitted in bays 2.5 m wide. Remaining width to be pedestrianised. 17(4) 200 4.0/8.0 Major access road, one-way westbound. 17(5) 111 4.5/17 Minor access road, one-way westbound. 17/A(1) 194 7.5/18 Minor access road, one-way eastbound. 17/A(2) 117 3.5/7.5 Minor access road, one-way eastbound. 19/A 339 4.0/8.0 Major access road, one-way southbound, no right turn at Road 11. UNR(1) 83 7.0/13.0 Major access road, two-way. UNR(2) 111 4.0/7.5 Major access road, one-way eastbound. UNR(3) 56 7.0/13.0 Major access road, two-way. UNR(4) 44 3.5/7.5 Minor access road, one-way southbound. KAA = Kamal Ataturk Avenue; UNR = un-named road (at least no name is given on the source map). Note: In the width column the first width is that of the carriageway and the second is the aggregate road plus sidewalk width (combined sidewalk widths for each side of the road). All recommended widths fit within frontage-to-frontage widths. Extra width left over after rebuilding the roads and footways can be used for landscaping or parallel parking bays.

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

6. There is no land acquisition required for this subproject and specific design measures are adopted to minimize involuntary resettlement by keeping within the ROW. Impacts are limited to temporary economic displacement and relocation of 225 mobile hawkers and vendors in the subproject area who operate within the ROW. No residential displacement is envisioned. The impacts are further detailed below and mitigation measures and entitlements are provided in the following sections.

III. SOCIOECONOMIC INFORMATION AND PROFILE

A. Census Survey

7. Structured census survey questionnaires (Appendix 2) were used to collect detailed information on the impact of temporary impacts hawkers and vendors in the subproject area who are considered economically displaced.2 The survey was conducted in June 2010.3

2 As the Resettlement Plan will be updated at the detailed design stage, and the hawkers defined at the time of the census survey (the cut off date for receiving entitlements) the actual number of hawkers may be subject to change and will be reconfirmed.

4

8. Street Hawkers and Vendors. The subproject will impact 225 mobile hawkers and street vendors who operate within the ROW. The hawker structures are considered temporary and therefore they will experience temporary economic displacement. The socioeconomic findings of the census are described below.

9. The socioeconomic profile of the displaced persons is homogenous nature. These households are mostly engaged in small-scale business activities such as small shops, vegetable stands, and eateries. None of the households belong to Indigenous People or ethnic minority group as most of the displaced persons are Muslims. The major source of income of these vendors and hawkers households are the small business activities.

10. Average Monthly Income of the Displaced Persons. The average income of the displaced households vary. A majority of the hawkers (125) earn an average monthly income in the range of Tk5,000 to Tk10,000. Around 64 hawkers reported their income level per month is less than Tk5,000. These persons are considered to be vulnerable and considered as poor and are entitled to additional entitlement measures under the project. The total average income of the affected hawkers is Tk8,262. Details are given in Table 3.

Table 3: Average Monthly Income Monthly Income Sl. No. Number of Households % Age (Tk) 1 Less than 5,000 64 28.44 2 500-10,000 125 55.56 3 10,000-15,000 28 12.44 4 More than 15,000 8 3.56 5 Total 225 100.00 Source: Census Survey, June-2010.

11. Vulnerable Households. Vulnerable households are defined as (i) women headed, (ii) physically handicapped, and (iii) those below the below poverty line. Details of vulnerable hawkers are given in Table 4.

Table 4: Vulnerable Households Sl. No. Vulnerable DHs Numbers 1 Women Headed Households 14 2 Physically Handicapped Households 5 3 Below Poverty Line Households 64 Total 83 Source: Census Survey, June-2010.

12. To understand the relocation options, only 11 (4.89%) hawkers opted for self relocation or voluntary relocation. The choice of hawkers is further supported by their compensation option where 41.33% opted for cash compensation against loss of their structure. Details of relocation and compensation option are given in Table 5.

3 The survey team was trained by the international resettlement specialist consultant and the survey was closely monitored on a regular basis. The census survey included various aspects including (i) assessment of land including quantity and typology; (ii) Inventory of physical assets; (iii) potential income loss; (iv) impact on trees; (v) household characteristics, including social, economic and demographic profile; and (vi) temporary impacts on the hawkers’ business activities. 5

Table 5: Relocation Option by Displaced Persons Number of Households Sl. No. Option Percent Response 1 Voluntarily Relocation 11 4.89 2 Need Resettlement 214 95.11 3 Alternate structure as Relocation 132 58.67 Cash for structure loss as 93 4 Relocation 41.33 5 Shifting Allowance for Relocation 132 58.67 Employment Opportunities in 15 6 Construction work 6.67 License to resume the current 53 7 activities 23.56

13. Structures. The use of hawker structures is mostly for the roadside small business activities. As per the census survey, 74 of the structures were for vegetable/fruit vendors, followed by 73 small shops, 46 small eatery/tea stall, 31 mobile vendors and one kiosk. Details are given in Table 6.

Table 6: Use of the Structure Number of Sl. Type of Properties % Age No. Properties/Structures and Households 1 Small Shops 73 32.4 2 Kiosks 1 0.4 3 Mobile Vendors 31 13.8 4 Small Eatery/Teas Stall 46 20.4 5 Vegetable/Fruit Vendor 74 32.9 Total 225 100 Source: Census Survey, June 2010.

14. The type of structures is classified based on the type of construction materials, their usability and the age of the structure. The average age of the structures is 5 years. Most of the structures are temporary meaning they do not have a permanent foundation and characterized by construction materials such as bamboo pillars, tripol/plastic or thatched structures. Most of the structures cover a very small area with most reporting to cover less than 5 square meters. Details are given in Table 7.

Table 7: Average Area of Structures Number of Properties Sl. No. Area of the Structure %Age and Households 1 Less than 5 Sq.m. 189 84.00 2 5 to 10 Sq.m. 31 13.78 3 10 to 15 Sq.m. 5 2.22 Total 225 100 Source: Census Survey, June 2010.

15. The average market price as viewed by the hawkers for majority of the structures (134) is less than Tk5,000. The overall average market price of the structures along the subproject area is Tk6,606. Details are given in Table 8.

6

Table 8: Average Market Price of the Structure Number of Average Market Price Properties Sl. No. % Age (Tk) and Households 1 Less than 5,000 134 59.6 2 5,001 to10,000 58 25.8 3 10,001 to15,001 20 8.9 4 More than 15,000 13 5.8 Total 225 100 Source: Census Survey, June 2010.

16. Gender. During disbursement of assistance and compensation, priority will be given to female headed households. Joint ownership in the name of husband and wife will be offered in case of non-female headed households where the asset was acquired during their marriage.

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

A. Public Consultation

17. During subproject preparation, consultations were held with the official representatives of Banani and Dkaha City Corporation, apart from the communities in the subproject area. The issues covered during these consultations included selection of subprojects and identification of key issues including addressing the current gaps in provision of basic services and improvement of urban environment conditions in the Banani area. These consultations (Table 9) provide an understanding of the needs and concerns of the project communities and the relevant stakeholders. Additionally, focus group discussions were also conducted with the local community especially with the displaced persons and the summary of these consultations is given in Appendix 3.

Table 9: Summary of Public Consultations Incorporation into Number of S.No. Place Date Participants Issues discussed Resettlement Plan participants and Project design A Banani 12th 20 Residents of Understanding of All the subproject June Banani, the current issues activities have been 2010 shopkeepers, pertaining to traffic confined to the and road and environmental existing Right of users conditions, including Way in the project road safety, design. Hence, no drainage issues etc land acquisition is within the project needed. area Compensation and Environmental and assistance provision social issues have been made to including the shifting all the likely affected of vendors and and displaced squatters and hawkers and minimization of vendors irrespective resettlement of their legal title. B Banani 1s 3 Executive Overview of the Suitable DCC office July engineer – Safeguards policies organization 2010 DCC, Town and capacity structure with 7

Incorporation into Number of S.No. Place Date Participants Issues discussed Resettlement Plan participants and Project design planner DCC, assessment of DCC adequate Zonal officials on the safeguards Executive implementation of specialist have been officer (DCC) the subproject added in the overall – Banani. organization structure and executing agency and implementing agency level. These provisions have been made in the Resettlement Plan and provision for budget have been made to meet these requirements DCC = Dhaka City Corporation.

B. Information Disclosure

18. Project information will be continually disseminated through disclosure of resettlement planning documents. Resettlement information leaflets containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Bangla) and the same will be distributed to displaced persons. The PIU the Resettlement Support staff (RSS) will keep the displaced persons informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. The information will also be made available at a convenient place especially, the market place which will be easily accessible to the displaced persons. The summary of the Resettlement Plan and the entitlement matrix will be translated into the local language; disclosed to the displaced persons; and made available at PIU, local offices and libraries (or other pubic places, and at the LGED offices. A copy of the Resettlement Plan will be disclosed on the LGED and ADB website.

C. Continued Consultation and Participation

19. For continued consultations, the following steps are to be taken:

(i) The PMCU and the PIU will organize public meetings and will apprise the communities about the progress in the implementation of resettlement, social and environmental activities. (ii) There will be a Grievance Redress Committees (GRC). The displaced persons will be associated with such committee along with their representatives. (iii) PMCU and PIU will organize public meetings to inform the community about the compensation and assistance to be paid. Regular update of the progress of the resettlement component of the project will be placed for public display at the PCMU and PIU offices. (iv) All monitoring and evaluation reports of the resettlement components of the project will be disclosed in the same manner as that of the Resettlement Plan. (v) Key features of the entitlements will be displayed along the project corridor. (vi) The PMCU and PIU will conduct information dissemination sessions at major intersections and solicit the help of the local community leaders to encourage the participation of the displaced persons in Resettlement Plan implementation.

8

(vii) Attempts will be made to ensure that vulnerable groups understand the process and to take their specific needs into account.

20. The details on consultation process and disclosure at various phases of project development including the responsible agency are described in Appendix 5.

V. GRIEVANCE REDRESS MECHANISMS

21. A grievance redress mechanism (GRM) shall be set up in the Dhaka City Corporation PIU office in Banani to register grievances of the people regarding technical, social and environmental aspects. The process will designed to be transparent, gender responsive, culturally appropriate and commensurate to the risks and adverse impacts of the project, as well as readily accessible to all segments of the affected people. The project GRM will not supersede any legal government grievance procedures. Affected people are to be informed about the mechanism through media and public outlets. This participatory process shall ensure that all views of the people are adequately reviewed and suitably incorporated in the design and implementation process. The GRM will be implemented in three levels.

22. The first level and most accessible and immediate venue for the fastest resolve of grievances is the PIU, chiefly through the resettlement safeguards officer and Project Manager, with assistance from the Resettlement Specialist(s) of the Management, Design and Supervision Consultant (MDSC). The contact phone number will be posted in the project areas. Grievances will be resolved through continuous interactions with affected persons and the PIU will answer queries and resolve grievances regarding various issues including Environmental Management Plan implementation, land acquisition, structures acquisition, livelihood impacts, entitlements, and assistance. Corrective measures will be undertaken at the field-level itself within seven days. All grievances will be documented with full information of the person and issue.

23. Should the grievance remain unresolved, the PIU's Project Manager, will activate the second level of the GRM by referring the issue (with written documentation) to the local GRC of the City Corporation, who will, based on review of the grievances, address them in consultation with the Safeguards Officer of the PIU and PMCU, and affected persons. A hearing will be called, if necessary, where the affected person can present his/her concern/issues. The process will promote conflict resolution through mediation. The local GRC will consist of the following persons: (i) Chief Executive Officer of the City Corporation (GRC Chair); (ii) representative of the mayor of the City Corporation; (iii) representative of the affected persons; (iv) official of the land registry department; (v) official of the DOE divisional office; (vi) town planner of the City Corporation; and (vii) Environmental/Social safeguards Officer of the PIU. The local GRC shall meet twice a month, unless the Project Director of the PIU informs that there are no grievances to address, or they shall meet as needed as per the severity of the grievance. The local GRC will suggest corrective measures at the field level and assign responsibilities for implementing its decisions.

24. The functions of the local GRC are as follows: (i) provide support to affected persons on problems arising from land acquisition (temporary or permanent); asset acquisition; and eligibility for entitlements, compensation and assistance; (ii) record grievances of affected persons, categorize and prioritize them and provide solutions within a month; and (iii) report to the aggrieved parties about developments regarding their grievances and decisions of the GRC.

25. Should the grievance still remain unresolved, the PIU Project Manager, will activate the third level of the GRM by informing the PMCU Project Director who will, based on review of the 9 local GRC minutes and consultation with the PIU Project Manager, activate the PMCU level GRC. This committee shall comprise the following representatives: (i) Project Director PMCU, (ii) Environmental/Resettlement Safeguards Officer of the PMCU; (iii) representative from Land Ministry, (iv) representative from DOE; (v) representative of the affected persons; and (vi) Environmental/Social Safeguards officer of the PIU.

26. The GRC at the PMCU level shall meet based on the receipt of grievances, and the meeting shall be convened within 7 days of receipt of the grievance by the PMCU, and grievances redressed with 15 days. The Environmental / Resettlement Safeguards Officer of the PMCU will be responsible for processing and placing all papers before the PMCU GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out.

27. In the event that a grievance is not addressed by the PIU, local GRC, or the PMCU GRC, the AP can seek legal redress of the grievance in the appropriate courts (fourth level of GRM). Figure 1 illustrates the GRM.

Figure 1: Grievance Redress Mechanism (GRM)

DSMC = Design Supervision Management Consultant, GRC = Grievance Redress Committee, GRM = Grievance Redress Mechanism, PMCU = Project Management Coordination Unit, PIU = Project Implementation Unit.

VI. LEGAL FRAMEWORK

28. This Resettlement Plan is prepared based on all applicable legal and policy frameworks of the Government (i.e., ARIPO) and ADB's SPS. A summary of applicable acts and policies is presented provided in the Project's Resettlement Framework.

10

29. The Government's policy through ARIPO does not cover project-affected persons without titles or ownership record, such as informal settler/squatters, occupiers, and informal tenants and lease-holders (without document) and does not ensure replacement value of the property acquired. The ARIPO has no provision of resettlement assistance for restoration of livelihoods of affected persons except for the legal compensation. Gaps between national law and ADB policy are identified and bridging measures are included in the entitlement matrix for the project, described below. ADB will not finance the project if it does not comply with its SPS nor will it finance the project if it does not comply with its host country's social and environmental laws. Where discrepancy between the ADB and Government policies exist, the ADB policy will prevail. Moreover, the SPS applies to all ADB-financed and/or ADB-administered sovereign projects, and their components regardless of the source of financing, including investment projects funded by a loan; and/or a grant; and/or other means.

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS

A. Eligibility

30. All displaced persons who are identified in the project-impacted areas on the cut-off date4 will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their pre-project living standards, income-earning capacity and production levels. The project will recognize both licensed and non-licensed vendors. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the detailed census during the detailed design. Displaced persons who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice (60 days), requested to vacate premises and dismantle affected structures prior to project implementation.

B. Entitlements

31. The entitlement matrix in Table 10 summarizes the main types of losses and the corresponding entitlements in accordance with the Government and ADB policies.

4The cut-off date for title holders is based according to the formal notification, and for non-titleholders the date of the census survey during the detailed design. Those who encroach into the subproject area after the cut-off date will not be entitled to compensation or any other assistance. The PIU will take video and photo documentation to ensure entitled persons on the cut-off date.

Table 10: Entitlement Matrix Sl Type of Application Entitled Person Entitlement Implementation Issues Responsible No Loss Agency

1 Loss of Residential/ Encroacher(s)  Cash compensation equivalent to replacement value of structure (or  Vulnerable households  PIU/PMCU structure commercial and squatter(s) part of structure) constructed by the DP. to be identified during structure  Rights to salvage materials from structure. census surveys and other  Provision of all taxes, registration costs, and other fees incurred for conducted as part of assets (e.g. replacement structure. the Resettlement Plan fences,  Shifting allowance based on actual cost of moving (e.g., truck hire, gates, posts) equipment, etc.). structure  Additional compensation for vulnerable households.  Assistance in finding alternate location. 2 Loss of Livelihood/s Hawkers  60 days advance notice.  Vulnerable households  PIU/PMCU livelihood ource of  Assistance in finding alternate location. to be identified during income  One time assistance for lost income based on three months lost census surveys income (at replacement cost) or minimum wage rates (whichever is conducted as part of higher). the Resettlement Plan  Shifting allowance and cost of reestablishing business elsewhere (cost  Training allowance to of truck hire, equipment, etc.). be paid directly to the  Training allowance in the form of cash equivalent to short term training training institute course.  Additional compensation for vulnerable households.  Consideration for project employment. 3 Temporary Temporary Hawkers  60 days advance notice.  PIU/PMCU loss of loss of  Provision of temporary access where possible. livelihood livelihood/so  Provision of alternative sites for continued economic activity where urce of possible. income  Where provision of alternative sites is not feasible, a one time assistance for lost income for period of disruption (if less than three months) or lump sum for three months lost income (at replacement cost) or minimum wage rates (whichever is higher).  Compensation for agricultural losses.  Restoration of affected land, structure, utilities, common property resource. 4 Impacts on All impacts Vulnerable  Land-for-land option will be a guaranteed option for vulnerable  Vulnerable households  PIU/PMCU vulnerable displaced displaced persons if available. If not available, assistance in finding to be identified during displaced persons new land. census surveys persons  Additional allowance equivalent to Tk10,000/- for loss of land or conducted as part of structure. the Resettlement Plan  Preference in project employment. 5 Any other Unanticipated involuntary impacts shall be documented and mitigated  PIU/PMCU loss not based on the principles provided in this Resettlement Framework and identified with compliance with the policy of the Government and ADB. ADB = Asian Development Bank, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

11 12

C. Assessment of Compensation Unit Values

32. Private Building and Structure. The compensation for structures will be determined on the basis of replacement cost as on date without depreciation. The PIU with assistance from the Public Works Department (PWD) will determine the replacement cost of structures. PIU will engage experts form PWD and the experts will carry out on the field assessment of each property and will submit the report to the Deputy Commissioner office. PIU will ensure that the assessment is done keeping in consideration the market price and consultation with the owners by assessing sources, types and cost of materials, usage of the building and the cost related to labor and transportation etc.

33. Business or Sources of Income. The PIU will conduct a detailed census survey which is to include actual monthly income of the displaced persons followed by a verification of the income data based on the tax payment (for titled business owners). In the absence of the authentic income proof, the unit price will be collected from the displaced person during the survey. See income restoration and rehabilitation measures below.

34. Temporary Source of Income. The compensation for temporary impacts will be decided based on the average daily income which will be derived from the census survey. The unit cost for temporary loss of income for mobile vendors has been derived based on the minimum wage for the entire period of disruption. The disruption period has been considered as 15 days and the minimum wage has been considered to be Tk200 per day. Therefore, the unit cost for temporary loss has been calculated to be Tk3,000 per household. See income restoration and rehabilitation measures below.

VIII. INCOME RESTORATION AND REHABILITATION

A. Basic Provision for Relocation

35. The PIU will attempt to find suitable alternative locations for hawkers including creating potential formal market spaces where feasible. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per applicable according to the entitlement matrix. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. To help hawkers losing structures in getting entitlements and relocating themselves, a relocation strategy will be adopted in the subproject including (i) all compensation will be paid and other resettlement entitlements will be before physical displacement; (ii) at least 60 days advance notice will be given; (iii) the PIU and Resettlement Support Staff will assist displaced persons during verification of assets and will provide necessary counseling on payment of compensation and assistance; (iv) in close consultation with the displaced persons, the PIU Resettlement Support Staff will fix the shifting dates agreed with the displaced persons in writing and the arrangements desired by the displaced persons with respect to their entitlements; and (v) in case of self relocation, the PIU will assist the displaced persons in finding alternative site within the area if so desired by the displaced persons.

B. Income and Livelihood Rehabilitation

36. Income restoration assistance to the displaced persons includes both short and medium term strategies. Short term income restoration strategies are for immediate assistance during relocation and include the following: (i) Compensation for structure paid in full before displacement occurs; 13

(ii) Assistance in finding alternate location for continuation of livelihood/living arrangements; (iii) Where provision of alternative sites is not feasible (for temporary impacts), compensation of lost income for period of disruption (if less than three months) or lump sum for three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (iv) Shifting allowance for reestablishing business elsewhere based on actual cost of moving/unloading; (v) 60 days’ advance notice to shift business; (vi) One time assistance for lost income based on three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (vii) Consideration for project employment; (viii) For vulnerable households, additional subsistence allowance equivalent to Tk10,000/household for restoring or enhancing their livelihood. Vulnerable households will be prioritized in any project employment; (ix) Provision of temporary access where possible to continue business; and (x) Restoration of affected land, structure, utilities, common property resource for continuation of business after construction is completed.

37. Medium-term income restoration activities will include skill development training based on need. The PIU will identify suitable local training institutes and pay fees directly to the training institution and provide the names of entitled person(s).

38. Where necessary, training may include (i) capacity building, enterprise training, and facilitating economic activities to landowners; and (ii) training for self employment to agricultural laborers. Training for self-employment and skill development which may include but not limited to (i) plumbing; (ii) electrical; (iii) automobile repair; and (iv) electronic repair and service, etc. Training will be imparted to any willing displaced person losing income or livelihood.

39. During the construction stage the displaced persons, especially vulnerable displaced persons, will be given preference over others in being engaged in project activities suitable to their skills. In order to make the displaced persons employable, the PIU will identify the required skills for the construction activities prior to the commencement of the construction and provide the required training to the displaced persons.

IX. RESETTLEMENT BUDGET AND FINANCING PLAN

40. The resettlement cost estimate for the Banani subproject (Table 11) includes eligible compensation, resettlement assistance, as outlined in the entitlement matrix, and support cost for Resettlement Plan implementation. The Government of Bangladesh will release funds to the PMCU and the PMCU will release funds to the PIU in a timely manner. The PIU in Dhaka City Corporation (DCC) will then release funds for resettlement to the entitled displaced persons. The total resettlement cost for the subproject is estimated at Tk20.85 million. The cost items of this Resettlement Plan are outlined below:

(i) Compensation for structures (Hawkers/Vendors) and other immovable assets at their replacement cost; (ii) Assistance in lieu of the loss of income and livelihood; (iii) Assistance for shifting of the structures; (iv) Training allowance; and (v) Special assistance to vulnerable groups for their livelihood restoration.

14

Table 11: Resettlement Budget Sl. No. Item Unit Unit Rate Quantity Amount (Tk) A Compensation A-1 Compensation for Temporary Structure Numbers 6,000 223 1,338,000 Compensation for Semi Permanent Numbers 8,000 2 16,000 Structure Sub Total (A) 1,354,000 B. Assistance B-1 Shifting Assistance Numbers 5,000 225 1,125,000 B-2 Training Assistance Numbers 12,000 225 2,700,000 B-3 Loss of Income Numbers 24,000 194 4,656,000 B-4 Temporary Loss of Income Numbers 3,000 31 93,000 B-5 Assistance to Vulnerable Households Numbers 10,000 83 830,000 Sub Total (B) 9,404,000 C Resettlement Plan Implementation Support Cost C-1 Hiring of Resettlement Support Staff at Person 100,000 72 7,200,000 DCC/PIU Month C-2 Administrative Cost Lump Sum 1,000,000 Subtotal C 8,200,000 Total (A+B+C) 18,958,000 Contingency (10%) 1,895,800 GRAND TOTAL 20,853,800 GRAND TOTAL (Million Tk) 20.85 GRAND TOTAL (Million USD) 0.29 DCC = Dhaka City Corporation, PIU = Project Implementation Unit.

X. INSTITUTIONAL ARRANGEMENTS

A. Project Management Coordination Unit

41. The LGED will be the executing agency responsible for overall guidance and project implementation. A PMCU headed by a Project Director will implement the project investments and will be responsible for overall planning, management, coordination, supervision and progress monitoring of the CRDP in the two regions. The PMCU will ensure compliance with assurances, including safeguards and preparing and submitting reports, resettlement plan monitoring updates. To ensure effective implementation of the land acquisition and resettlement aspects, two full time PMCU resettlement safeguard officers will be recruited, including one Resettlement Compliance Officer primarily responsible for compliance with legal requirements of the Government, and one Resettlement Surveyor responsible for overseeing PIU preparation of the Resettlement Plan for subprojects and data collection. The MDSC will recruit one international and one national resettlement specialist to assist the PMCU in this regard. The PMCU will review monthly reports submitted by PIUs and will consolidate them into quarterly reports to ADB. Corrective actions to be taken when necessary based on close monitoring and results of grievance redress process.

B. Project Implementation Unit

42. The subproject will be managed and implemented through the PIU based in the Dhaka City Corporation office in Banani. The PIU will be responsible for carrying out the detailed design of the subprojects and updating Resettlement Plans for the sample subprojects and prepare new Resettlement Plans for future subprojects under the sector approach The PIU will ensure compliance with safeguards requirements of the Government and ADB. The PIU will be 15 responsible for day-to-day monitoring of the project progress, including the implementation of the resettlement provisions in the project.

43. The capacity to implement safeguards planning and implementation at the PIU level is not currently adequate. Therefore, it is proposed that resettlement support staff (or facilitators) at the PIU level will be recruited. The number of resettlement support staff at each PIU will be commensurate to the scale of involuntary resettlement impacts (e.g., the greater the impact, the greater number of support staff needed). All PIU and PMCU safeguards staff will undergo training conducted by the consultant team’s resettlement specialists. Each PIU will prepare monitoring reports on all aspects concerning to resettlement planning and implementation of the land acquisition and resettlement issues and report to the PMCU on a monthly basis.

C. Management, Design and Supervision Consultants

44. The MDSC will hire one International Resettlement Specialist (IRS) and one National Resettlement Specialist (NRS). They will be responsible for updating/finalizing the Resettlement Plans of sample subprojects in accordance with this Resettlement Framework and based on the detailed engineering design. These specialists will also prepare new Resettlement Plans for future subprojects under the sector approach consistent with this Resettlement Framework. This will be done in close coordination with PIU resettlement support staff and PMCU resettlement officers. The IRS and the NRS will assist in the overall supervision of the projects and ensure all plans are implemented in a smooth and timely manner in accordance with the provisions of the Resettlement Plan. They will also prepare and implement training and capacity development programs for resettlement planning for the PIU and PMCU safeguards staff (see section below on Training and Capacity Building), and will closely work with the PMCU and PIUs to ensure displaced persons are compensated before displacement occurs, including ongoing rehabilitation measures. Further details on agencies responsible for Resettlement Plan activities are in Table 12 and the organization chart for Resettlement Plan implementation is depicted in Figure 2.

Table 12: Institutional Roles and Responsibilities Activity Responsible Agency A. Subproject Initiation Stage and Institutional Setup Formation of PMCU. LGED Formation of PIU. LGED Finalization of sites for subprojects. PMCU/PIU/MDSC Disclosure of proposed land acquisition and subproject details by issuing Public PIU/PMCU Notice. Meetings at community/household level with displaced persons. PIU Capacity Building training. MDSC/IRS B. Resettlement Plan Preparation/Updating Stage Resettlement screening and categorization form and submission to ADB for PIU/PMCU each subproject. ADB to confirm resettlement categorization. ADB Census of 100% displaced persons and socioeconomic survey. PIU/PMCU Screening of vulnerable displaced persons. PIU/PMCU Survey on unit prices for computing replacement costs. PIU/PMCU Calculation of compensation and entitlements. PIU/PMCU Update of sample subproject Resettlement Plans and preparing new PIU/PMCU Resettlement Plans in accordance with Resettlement Framework. Consultations with displaced persons on entitlements. Compliance with PIU/PMCU disclosure requirements. Finalize Resettlement Plans and submit to ADB. All draft Resettlement Plans PIU/PMCU must be submitted to ADB for clearance prior to award of contracts.

16

Activity Responsible Agency Incorporate all comments and suggestions to Resettlement Plans. PIU/PMCU Web disclosure ADB/PMCU C. Resettlement Plan Implementation Stage Issuance of identification Cards to displaced persons PIU/PMCU Detailed schedule for compensation PIU/PMCU Distribution of relocation notices to displaced persons PIU/PMCU Award of checks for land compensation PIU/PMCU Award of Checks for other compensation and assistance/ rehabilitation PIU/PMCU Confirm with ADB in writing when payment of entitled compensation to PMCU/PIU displaced persons has been completed. Permission to contractor to begin works once compensation to displaced persons is confirmed (note: other income rehabilitation to continue after civil works commence). Notice to proceed for civil works is issued on sections where compensation is PIU/PMCU paid. Demolishing/ relocation of affected structures/assets PIU/PMCU Income restoration program and training PIU/PMCU Grievances redress mechanism PIU/PMCU/GRC Internal monitoring PIU/PMCU Review of Resettlement Plan implementation by external expert through a External Expert compliance report for projects with significant impacts ADB = Asian Development Bank, GRC = Grievance Redress Committee, IRS = International Resettlement Specialist, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

Figure 2: Organization Chart for Resettlement Plan Implementation

LGED ADB

PMCU

1 Resettlement Compliance Officer, 1 Resettlement Surveyor

MDSC 1 International Resettlement Specialist, 1 National Resettlement Specialist

PIU Resettlement Support staff

DISPLACED PERSONS

ADB = Asian Development Bank, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

17

XI. IMPLEMENTATION SCHEDULE

45. Land acquisition, compensation and relocation of displaced persons cannot commence until the Resettlement Plan has been cleared by ADB. All compensation is to be paid prior to displacement although income rehabilitation measures will continue after construction begins. Written confirmation is required by the PMCU to ADB stating that all compensation has been paid to displaced persons. Only then can construction works begin on sections where compensation has been paid. The project will be implemented over six years (January 2011 to December 2016). The implementation of the Resettlement Plan will include: (i) identification of cut-off date and notification; (ii) verification of losses and extent of impacts; (iii) finalization of entitlements and distribution of identity cards; (iv) consultations with displaced persons on their needs and priorities; and (v) resettlement, provision of compensation and assistance, and income restoration for displaced persons. The expected implementation schedule for a subproject is given in Table 13.

Table 13: Implementation Schedule Activity Months

1 2 345678910 1112 13 14 15 16 1718 Establishment of PMCU and PIU.  Appointment of safeguards staff in  PMCU and PIUs. Appointment of international and  national resettlement specialists on consultant team. Formation of GRC at PIU and PMCU  level. Census surveys (issuance of     identification cards). Send screening and categorization  form for subprojects to ADB. Consultations and disclosure.                  Confirmation of government land to   be used and transfer from other departments. Resettlement Plan preparation.      Resettlement Plan review and  approval (PMCU and ADB). All draft Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Issue notice to displaced persons.  Compensation prior to displacement    and income rehabilitation ongoing. Written confirmation from PMCU to  ADB that all compensation paid in sections ready for construction. Permission to contractor to begin works once compensation to displaced persons is confirmed. Relocation as required    Takeover possession of acquired    property Handover land to contractors 

18

Activity Months

Start of civil works  Skills training as required for income       restoration Grievance Redress Mechanism Internal monitoring                Monthly monitoring reports (PIU to                PMCU) Quarterly monitoring reports (PMCU                to ADB) Rehabilitation of temporarily Immediately after occupied lands construction ADB = Asian Development Bank, GRC = Grievance Redress Committee, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. Note: The Resettlement Plan will be updated based on final detailed design and displaced person census and surveys. Endorsement and disclosure of finalized Resettlement Plans consistent with the Resettlement Framework to be undertaken.

XII. MONITORING AND REPORTING

46. The extent of monitoring activities will be commensurate with the project’s risks and impacts. Monthly monitoring reports to be submitted by PIU to PMCU. PMCU to consolidate monthly reports into semi-annual monitoring reports to ADB. These reports should form a part of the project progress reports submitted by PMCU to ADB.

47. The objectives of monitoring are to (i) ensure that the standard of living of displaced persons are restored or improved; (ii) ascertain whether activities are progressing as per schedule and the timelines are being met; (iii) assess if compensation, rehabilitation measures are sufficient; (iv) identify problems or potential issues; and (v) identify methods to rapidly to mitigate problems. The above information will be collected by executing and implementing agency through its PMCU and respective PIU which is responsible for monitoring the day-to-day resettlement activities of the project through the following instruments:

(i) Review of census information for all displaced persons; (ii) Consultation and informal interviews with displaced persons; (iii) In-depth case studies; (iv) Sample survey of displaced persons; (v) Key informant interviews; and (vi) Community public meetings.

48. Internal Monitoring. The internal monitoring by PMCU/PIU will include (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socio-economic monitoring during and after the relocation process to ensure that people are settled and recovering. This will utilize the baseline information established by the socio-economic survey of displaced persons undertaken during subproject preparation; and (iii) overall monitoring whether recovery has taken place successfully and on time. Monitoring will also include the following:

(i) Communication with and documentation of reactions from displaced persons. (ii) Information from displaced persons on entitlements, options, alternative developments, etc. (iii) Valuation of properties. (iv) Usages of grievance redress mechanism. 19

(v) Disbursement of compensation amounts and all assistance. (vi) Physical progress of the Resettlement Plan implementation which will include relocation of displaced persons and affected community properties.

49. The indicators for achievement of objectives during Resettlement Plan implementation are of two kinds such as (i) Process Indicators (Indicating project inputs, expenditure, staff deployment, etc.); and (ii) Output Indicators: Indicating results in terms of numbers of displaced persons compensated, area of temporarily occupied lands restored with topsoil (and other pre- project features), number of displaced persons provided with skills training, etc. Input and output indicators related to physical progress of the work will include items such as:

(i) Training of executing and implementing agencies and other staff completed. (ii) Census, assets inventories, assessments and socio-economic studies completed. (iii) Grievance redress procedures in-place and functionality. (iv) Compensation payments disbursed. (v) Relocation of displaced persons completed. (vi) Project employment provided to displaced persons. (vii) Infrastructure rehabilitated or constructed. (viii) Income restoration activities initiated. (ix) Skills training of displaced persons initiated. (x) Number of households displaced and resettled. (xi) Monitoring and evaluation reports submitted.

20 Appendix 1

DESCRIPTION OF ROAD NETWORK IN BANANI Road Length Width Remarks (m) (m) KAA 933 2 x District distributor, dual carriageway, commercial frontages. (12/14) 4 322 4.5/7.5 Narrow road used as N-S local distributor, commercial frontages. Some katcha surface. 6(0) 322 6/15 Relatively narrow road used as N-S local distributor. Some katcha surface. 6(1) 144 6/12 Residential E-W access road. 6(12) 122 5.5/7.5 Residential minor N-S access road, residential. 6(2) 144 5.5/8.5 Residential E-W access road. 6(21) 122 5.5/7.5 Residential minor N-S access road, residential. Some katcha surface. 8 233 7.5/15 N-S local distributor, commercial frontages. 10 322 6/15 N-S local distributor, mixed (shop house) frontages. Katcha surface at southern end. 11 1172 9/21 E-W local distributor used as district distributor. Worst pedestrian and traffic conditions of any road in Banani. 12 322 6/18 N-S local distributor, commercial frontages. 13(0) 389 4.5/9 Residential E-W access road, narrow usable carriageway. 13(1) 194 4.5/7.5 Residential E-W access road, narrow usable carriageway. 13(2) 128 5.5/12 Residential E-W access road, narrow usable carriageway. 13(3) 161 5.5/14 Residential N-S access road, narrow usable carriageway. 13(4) 100 5.5/14 Residential N-S access road, narrow usable carriageway. 13/A(1) 266 4.5/10.5 Residential E-W access road, narrow usable carriageway. Some katcha surface. 13/A(2) 128 4.5/7.5 Residential N-S access road, narrow usable carriageway. 13/A(3) 67 7.5/10.5 Residential N-S access road, reasonably wide carriageway. 13/B 194 4.5/12 Residential E-W access road, narrow usable carriageway, semi- pacca and katcha surface. 13/C(1) 200 6/20 Residential E-W access road, reasonably wide carriageway. 13/C(2) 122 5.5/12 Residential E-W access road, reasonably wide carriageway. 13/C(3) 61 3.5/10.5 Residential N-S access road, very narrow usable carriageway. 15(1) 266 7.5/18 Residential E-W access road, reasonably wide carriageway. 15(2) 233 9/18 Residential N-S access road, wide carriageway. 17(1) 144 10.5/17 E-W access road, educational activity, many pedestrians, wide carriageway. 17(2) 305 12/24.5 E-W access road, canyon-like street between tall buildings (commercial, educational, hotel). Seriously degraded street. 17(3) 389 7.5/21 E-W access road, tall buildings to north (commercial, educational, hotel). Seriously degraded street: just over a third of its width is available for traffic. 17(4) 200 7.5/15 E-W access road, mainly commercial to north side. 17(5) 111 4.5/17 Residential E-W access road, narrow usable carriageway. 17/A(1) 194 7.5/18 Residential E-W access road, reasonably wide carriageway. 17/A(2) 117 3/7.5 Residential E-W access road, very narrow carriageway. 19/A 339 6/14 Residential N-S access road, narrow usable carriageway. Blockaded during site visit because of construction works. UNR(1) 83 15/24.5 Short, relatively wide N-S commercial connector. UNR(2) 111 12/17 Shopping street with tall frontages to both sides; heavily trafficked. UNR(3) 56 12/17 Very wide N-S connector alongside open air car park. UNR(4) 44 7.5/9 Short, relatively wide N-S residential connector. Notes: KAA = Kamal Ataturk Avenue. UNR = un-named road (at least no name is given on the source map). N-S = north-south, E-W = east-west. In the width column the first width is that of the carriageway and the second is the frontage-to-frontage width.

Appendix 2 21

INVENTORY OF TEMPORARY LOSS ON RIGHT OF WAY

1. Questionnaire No: ______Date: ...... 2. Name of the Project Component /Site:

3. Name of the Mohallah:

4. Name of the Street:

5. Name of the Ward:

6. Name of the Pourashava:

7. Name of the Upazila:

8. Name of the Zilla/District:

9. Name of the Province:

10. Property No. ------

11. Location 1. Left 2. Right

12. Status of the Property 1. Squatters 2. Encroachers

13. Name of the Owner ......

14. Father’s Name ......

15. Use of Structure 1 House 2 Huts 3 Sheds 4 Shops 5 Kiosks and Vendors 6 Mobile Vendors 7 Small Eatery/Teas Stall 8 Cattle shed 9 Boundary Walls/Fences

16. Area of the affected structure (in Square Meter) …………………..

17. Type of Structure 1. Temporary 2. Semi-Permanent

18. Age of the structure (Years)…………………….

22 Appendix 2

19. Type of Construction Structure

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

20. Market Value of the Structure (in Tk.)......

21. Number of family members. Total………… Male …… Female……….

22. Is it a woman headed household?

1. Yes 2. No

23. Is it a household owned by physically handicapped? 1. Yes 2. No.

24. Total Monthly income of the family (Tk.)………….

25. Willing to shift

1. Voluntarily 2. Need Resettlement

26. Compensation Option

1. Alternate structure 2. Cash for structure loss

27. Desire Assistance and other help 1. Shifting Allowance 2. Employment Opportunities in Construction work 4. License to resume the current activities 5. Others (specify ...... )

28. Is there alternate site available for relocation? 1. Yes 2. No. 29. If Yes, How far and the name of the place……………………………. Appendix 3 23

SUMMARY OF CONSULTATIONS

Date of Consultations: 15-06,2010, 16-05-2010 and 17-06-2010 Number of Consultations: 05 numbers Place of Consultations: (i) Ward: 2 & 3 , (ii) Ward: 7 & 8, (iii) Ward: 9 & 10, (iv) Ward: 5 & 6 and (v) Ward: 3. Number of Participants: 25

Q. Issues Participants’ Opinion, Comments and Suggestions No Have you heard about CRDP (City Yes, people have partially heard about City Region 1 Region Development Project) Development Project (CRDP) 2 If yes, where from From the DCC officials and other engineers General perception about the project People are generally in favor of the project especially and the awareness about the proposed the local residents. However, the hawkers and vendors 3 project. are skeptical about their relocation and shifting. They still perceive that project will take some time to take off and they can still operate till the project starts. Do others in this locality support this Yes, especially the residents in this locality surely 4 support this. Any critical issue or concern by the Displacement of the large numbers of hawkers and local people regarding the project? vendors who are working on the street may cause some 5 concern and need proper compensation and arrangements for relocation prior to the start of the project. Any criteria you would like to see Proper compensation and assistance including some 6 considered during project design, support for their relocation. construction and operation stage?

Employment Potential in the project Yes, there will be huge scope of employment for the which is of benefit to village squatter people and the plot owners will get barrier free 7 way out. However, hawkers/vendors foresee some temporary disruption in their business activities. Number of Households in the The total number of Households is relatively high. Mohallah/Town/District People who are living in Banani land varying from 8 10,125 to 15,000 persons at day time. But at night it becomes poor around 500 people. Ethnic Minorities /Indigenous peoples’ There is no indigenous person or ethnic minority who composition (If there are Indigenous are living there. 9 People, please mention about the names of the indigenous people and number of households). Number of Shops/ Commercial In the market side, there are some shops and large establishments in the Mohallah/town. numbers of commercial establishments in this Mohallah 10 Market places. On road side land, there are many shops which are approximately 250 numbers of hawkers and vendors Numbers of Industrial Units in the There are some garment industry and private luxury 11 Mohallah/town and surrounding area. offices and several private Universities and other

24 Appendix 3

Q. Issues Participants’ Opinion, Comments and Suggestions No business canters.

General socio-economic standing: Land and house owners are having good socio- What are the economic activities? economic condition while squatters are in moderate 12 Land use, cropping pattern (Seasonal), economic condition that is solely dependent on the daily types of crops, value of the crops, business. Average land holding size etc. Is the land Irrigated and what are the Not Applicable as the land is residential and commercial 13 sources of Irrigation? Access to the forest land and the use No access to the forest land. No forest land found there. 14 of the forest land (if any) 15 Is the area electrified Yes it is an electrified area. Source of drinking water DWASA Supplied Water, Bottled purified Water & HTWs 16 are the sources of drinking water. Loss of residential/commercial Mostly squatters who are doing their small business on structures, if any due to the project the street and are mostly smaller shops, tea-shops, 17 floating hotels, grocery shops, Cloth shops, and etc. structures are found there. Loss of community life like any Market Not at all. 18 Places or community activities to be affected Poverty Level: Is the village poor or Poverty level is there. Local Mohallah poor people= 15 19 very poor or well off families, Very poor= 10 families and well off= 45 families & medium families are 30%. 20 Education Status: Literate, illiterate etc Literate=85%, illiterate=35%. Employment Status: Percentage of Employed= 68%, unemployment= 10% and 21 employment/ unemployment/ underemployment= rest underemployment Migration Pattern (If any), inward or Inward migration= 93% 22 outward Outward migration= 7% What is the major occupational The major occupational structure of the local people is 23 structure of the local people commercial activities. Are you satisfied with the present Yes, we are satisfied with the present infrastructure infrastructure facility in the town and facility in the town and locality. But some over Bridges 24 locality are essential at Dhaka City to manage traffic. Also, the congestion on Banani streets need to be solved das it is a business centre. Do you face any problem regarding the We do not face existing water supply/solid waste exiting water supply/solid waste management and Drainage systems. But, traffic become 25 management/river some problem, since there is only one lay-bay for the port/Drainage/Traffic system? traffic at Banani. If there is any problems related to Up-gradation is necessary for Traffic system 26 these services, do you think that any management at Dhaka City, upgradation is necessary? 27 Do you have any idea regarding the Government should take action. To be cleaned and de- process of upgradation? marketed properly, shifting of some the available Appendix 3 25

Q. Issues Participants’ Opinion, Comments and Suggestions No unauthorized vendors/hawkers structures from the right of way and several well paved approach roads are required. 28 For this upgradation the For up-gradation the road/street/path /drainage may get road/street/path/drainage may get affected to some extent. However, it is desirable. affected- what do you think about that- is it desirable? 29 How can this affect your present living This will not affect the present living or activity of the or activity people except the fact these unauthorized hawkers and vendors may suffer in their business on a temporary basis. 30 Who else could be affected due to this Only some shop keepers and squatters are likely to be upgradation affected due to this upgradation. General pedestrians who work over there likely to be affected there. 31 How intense could be the effect The impact on these hawkers and squatters are significant when we take in to account the all the streets in banana. 32 Do you think the affect will be of Some of them may be permanent but mostly the impact permanent nature? will be temporary in nature. 33 The project may need shifting of some The project may need shifting of some encroachments encroachments and squatters. Would and squatters from the right of way i.e., from Banani you like to shift from here on your own land. However, we prefer project assistance and compensation so that we can shift on our own. 34 Where will you like to shift during this No idea where to shift. Most possibly on some residual period? land if land is available. 35 Is there available alternate place for There is no available alternate place for relocation for relocation? If yes, how far and the the affected people. . name of the place 36 Perceived losses from the Project- Many small shops and vendors/ hawkers Banani Road land are the perceived losses from the Project. 37 If losses are perceived, what is the People believe some compensation from any sources. expected compensation you would desire 38 Perceived benefits from the Project- Perceived benefits from the Project would be a permanent way out and in for the people; not only for some limited traders. It would be for everyone’s business centre. 39 Do you think that the local residents Yes we hope so. would like to participate in this work 40 Any suggestion/opinion, etc. 1. Well Paved road at Banani 2. Best Communication networks. 41 Do you think that the local people Yes, it would be possible to get regular information would like to get regular information regarding this Project. regarding this Project?

42 Will it be through informal or formal Yes, it may be both. consultation

26 Appendix 3

Q. Issues Participants’ Opinion, Comments and Suggestions No 43 Will the project cause landslides or soil There will be no cause of landslides or soil erosion in erosion in the locality. the locality. .

44 Will the project cause widespread No, the project will not cause any imbalance by cutting imbalance by cutting fruit and fruit and commercial trees in the locality; Infact, there commercial trees in the locality. are no cases of big trees found in the project area as it is a hub of urban centre 45 Will the project cause health and safety The project will not cause any health and safety issues issues in the area. in the area. However, during the construction, the contractor should sprinkle water and should take adequate measures for noise and dust pollution. 46 Resettlement and Land acquisition (if No, there had been no land acquisition before at Banani, foreseen due to project components Dhaka, if land acquisition is being done by the especially on private land). Has there concerned Deputy Commissioner of the been land acquisition before? If yes, and compensation may be paid by Deputy what was the process of land Commissioner following Government LA Ordinances acquisition and compensation and its subsequent amendments therein. When there is package? ADB fund in this project, the affected people will get compensation following ADB guidelines. Deputy Commissioner pays compensation to legal plot owners only. We expect transparent compensation procedure in this project 47 Protected areas (national park, No such cases found in Banani. protected forest, religiously sensitive sites, historical or archaeological sites), if any 48 Health status, Availability of Hospitals There may be any chronic disease prevalent in this area and over all environmental condition. Is and people are aware about HIV/AIDS and STP. there any chronic disease prevalent in The health statuses, is availability of Hospitals and over this area and are you aware about all environmental condition are there; since it is a main HIV/AIDS and STP? part of Dhaka City. 49 Will the project siting adversely change No, the project setting will not adversely change migration pattern of animals that would migration pattern of habitats destroy fields, habitats 50 Will the project sitting adversely impact The project sitting will not adversely impact the water or the water or soil resource in the locality soil resource in the locality. 51 What other organizations of a social BRAC, , Proshika, Padakhep and other nature (NGOs/CBOs/ Civil Society) NGOs are active in Dhaka Banani area active in the area? Name of these organizations 52 Will there be likely involvement of local There will be likely involvement of local people in the people in the implementation of the implementation of the project as professional worker project? and other occupation. 53 Kindly indicate what kind of economic/ The female members of families could engage in both in non-economic activities female economic/ non-economic activities at Dhaka City. members of your family are engaged in Appendix 3 27

Q. Issues Participants’ Opinion, Comments and Suggestions No 54 If, engaged in economic activities how The female are engaged in economic activities and much they contribute to total family contribute to total family income of the year. Normally income of the year the females are involved household activities and in small scale manual work in wage earning and running small shops. 55 Does your female member have any Normally, a male is a head in decision making of say, in decision making of household household matters. In some special cases, female are matters involved in. 56 Do the women of your household can Yes, the women of the household can freely go outside freely go outside to work, for to work, for marketing, or accessing hospitals, marketing, or accessing hospitals, educational institutes, etc. educational institutes, etc? 57 Does the woman have easy access to Yes, the woman has easy access to get water from get water from outside? outside. 58 Do you have a toilet at your Yes, all members have a toilet at household as when household? they need the toilet. 59 Can a woman access public toilets and Most of the women have access to public toilets and bathing facilities in the evening easily? bathing facilities in the evening if any guardian with her at Banani. 60 Do you have adequate street lighting Yes the people of Banani have adequate street lighting during the night? during the night since it is a part of main part of Banani town. 61 Any other issues you may feel to Other Issues at Banani may feel to share is the share: establishment are the internal and external communication network with local people and people in other districts and abroad. Also, they need full cooperation from the DCC in the process of payment of compensation, assistance and relocation. Sufficient advance notice should be given to all these hawkers and squatters operating in the banana Street. Possible attempts should be made by the DCC to find some alternate market place for those who will be permanently shifted due to the project. 62 Is this consultation useful? Comments Yes, the consultation is useful to almost everybody. Consultation helps much the people to know one another the internal information what we need and the other people’s requirements. Consultation also mitigates information gaps of the people at Banani. ADB = Asian Development Bank, CBO = community-based organization, CRDP = City Region Development Project, DCC = Dhaka City Corporation, DWASA = Dhaka Water Supply and Sewerage Authority, NGO = nongovernmental organization.

28 Appendix 3

LIST OF PARTICIPANTS

SL. Name Occupation Sex (M / F) Age (Years)

1 Mr. Shorab Hossaim Godown Worker M 45

2 Mr. Habibur Rahman Godown Worker M 32

3 Mr. Kalam Bapari Shop keeper M 35

4 Mr. Hannan Mollah Helper in a market M 20 5 Mr. Kabir Ali Tea-stall owner M 40 6 Mr. Kh. Hasan Mia Shop keeper M 34 7 Mr. Latif Talukder Fuel Sealer M 45 8 Mr. Keramot Ali Worker in a market M 30 9 Mr. Jay Miah Food Sealer M 22 10 Mr. Jamal Uddin Hotel Worker M 24 11 Mr. Karim Hossain Pan-Biri Sealer M 58 12 Mr. Zahir Mollah Passer by M 55 13 Mrs. Shanjida Nurse Of the Hospital F 34 14 Mr. Shubir Kumar Buyer in a shop M 47 15 Mr. Arun Kumar Pal Workman M 26 16 Mrs. Kalima Khatun Hotel Worker F 36 17 Mr. Hasmot Mollah Hotel worker M 25 18 Mrs. Shabiha Begum Seals Lady F 17 19 Mr. Hori Pado Ghosh Passer by M 23 20 Mrs. Jaitan Nessa Tea-lady F35 21 Mr. Adbul Karim Pedestrian M 46 22 Mr. A. Gani Worker in a farm M 34 23 Mr. A Kadair Van Puller M 36 24 Mr. Kafil mahmud Rickshaw Driver M 40 25 Mr. Akbar Hossain Van Puller M 47

Appendix 4 29

CONSULTATION AND DISCLOSURE ROLES AND RESPONSIBILITIES

Responsible Project Phase Activities Details Agency Subproject information dissemination on various components -Leaflets containing

information on the Project Disclosure of Preliminary and subprojectarea to be proposed for required land prepared) acquisition to displaced Project PIU/PMCU persons Initiation Stage -Public notice issued in (DCC/LGED)

public places including Preliminary Information newspapers and direct Sharing about the tentative consultation with displaced alignment/ sites with the persons displaced persons in case of temporary impact on business, income and livelihood -Further consultations with PIU/PMCU displaced persons and (DCC/LGED) households, titled and non- titled.

-Summary Resettlement Stakeholder consultations Framework made available to all displaced persons at the convenient place which is easily accessible and should be in local language (Bengali) Resettlement Disclosure of final entitlements Resettlement Plans PIU/PMCU Plan and rehabilitation packages disclosed to all displaced (DCC/LGED) Preparation and disclosure of draft persons in local language Phase Resettlement Plan (Bengali) -Review and approval of PIU/PMCU Resettlement Plan by (DCC/LGED) executing agency. -Review and approval of Resettlement Plan by ADB Finalization of Resettlement (prior to award of contract). Plan -Web disclosure of the Resettlement Plan. -Disclosure of the Final Resettlement Plan to displaced persons -Consultations with PIU/PMCU displaced persons; (DCC/LGED) Resettlement Consultation with displaced -Payment of entitlements; Plan persons during Resettlement -Written notification from Implementation Plan implementation PMCU to ADB that all Stage compensation paid before displacement occurs ADB = Asian Development Bank, DCC = Dhaka City Corporation, LGED = Local Government Engineering Department, PIU = Project Implementation Unit, PMCU = Project Management Cordination Unit,.

30 Appendix 4

MONITORING INDICATORS AND SAMPLE FOR STATUS REPORT

S. N. R&R Activities Progress Remarks Pre Construction Activities and R&R Activities 1 Assessment of Resettlement impacts due to changes in project design (If required) 2 Preparation/ updating of Resettlement Plan based on changes in project design 3 Approval of updated Resettlement Plan from ADB 4 Disclosure of updated Resettlement Plan 5 Establishment of Grievance Redressal Committee 6 Capacity building of PIU Verification of displaced persons Census list; assessment on compensation and assistance, and readjustment 7 Land Acquisition Resettlement Plan Implementation 1 Payment of Compensation as per replacement value of land & assets to displaced persons 2 Disbursement of assistance to title holders 3 Disbursement of assistance to non-title holders 4 Disbursement of special assistance to Vulnerable groups 5 Replacement/ shifting of community property resources 6 Reinstallation of public utilities 7 Records of Grievance Redressal 8 Temporary Relocation of Hawkers and Vendors 9 Income Restoration Measures through training Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or use of children as labour 2 Prohibition of Forced or Compulsory Labour 3 Ensure equal pay for equal work to both men and women 4 Implementation of all statutory provisions on labour like health, safety, welfare, sanitation, and working conditions 5 Maintenance of employment records of workers ADB = Asian Development Bank, PIU = Project Implementation Unit, R&R = Resettlement & Rehabilitation.

City Region Development Project (RRP BAN 39298)

Resettlement Plan

Document Stage: Draft for Consultation Project Number: 39298 July 2010

BAN: City Region Development Project—Gazipur Water Supply and Sanitation Subproject

Prepared By: Local Government Engineering Department (LGED), Government of Bangladesh

The Resettlement Plan is a document of the Borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

ABBREVIATIONS

ADB — Asian Development Bank ARIPO — Acquisition and Requisition of Immovable Property Ordinance CRDP — City Road Development Project DOE — Department of Environment DPHE — Department of Public Health Engineering GRC — Grievance Redress Committee GRM — Grievance Redress Mechanism IRS — International Resettlement Specialist LGED — Local Government Engineering Department MDSC — Management, Design and Supervision Consultant NRS — National Resettlement Specialist PMCU — Project Management Coordination Unit PIU — Project Implementation Unit ROW — right of way RSS — Resettlement Support Staff SPS — Safeguard Policy Statement

TABLE OF CONTENTS

EXECUTIVE SUMMARY i

I. PROJECT DESCRIPTION 1 A. Overview 1 B. Subproject Components 1

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 3

III. SOCIOECONOMIC INFORMATION AND PROFILE 6

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 6 A. Public Consultation 6 B. Information Disclosure 7 C. Continued Consultation and Participation 8

V. GRIEVANCE REDRESS MECHANISMS 8

VI. LEGAL FRAMEWORK 10

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS 11 A. Eligibility 11 B. Entitlements 11 C. Assessment of Compensation Unit Values 14

VIII. INCOME RESTORATION AND REHABILITATION 14 A. Basic Provision for Relocation 14 B. Income and Livelihood Rehabilitiation 15

IX. RESETTLEMENT BUDGET AND FINANCING PLAN 16 A. Project Management Coordination Unit 17 B. Project Implementation Unit 17 C. Management, Design and Supervision Consultants 17

X. IMPLEMENTATION SCHEDULE 19

XI. MONITORING AND REPORTING 21

Appendixes 1. Census Questionnaire for Permanent Land Acquisition and Resettlement 23 2. Census Questionnaire Inventory of Temporary Loss 28 3. Details of Public Consultation and Focus Group Discussions 30 4. Future Consultation and Disclosure Roles and Responsibilities 35 5. Monitoring Indicators and Sample for Status Report 36

EXECUTIVE SUMMARY

1. The City Region Development Project (CRDP, the Project) will be financed by the Asian Development Bank (ADB) and is being formulated as a project loan using the sector approach to be implemented over a six-year period (January 2011 to December 2016). This document is a draft Resettlement Plan prepared for the Gazipur Water Supply and Sanitation subproject. It is based on a feasibility level study and preliminary engineering design and will be updated at the final detailed engineering stage. The Resettlement Plan is prepared in accordance with the ADB Safeguard Policy Statement, 2009 (SPS), Government of Bangladesh’s (the Government) policy, i.e., the Acquisition and Requisition of Immovable Property Ordinance, 1982 (ARIPO), and the Resettlement Framework adopted for the Project. It is classified as Category B according to ADB’s SPS as minimal land acquisition and resettlement is required.

2. Summary of Resettlement Impacts. A total of 16 households will be affected consisting of five households (39 affected persons) losing a small piece of land for four proposed tube wells and one public toilet; and 11 street hawkers/mobile vendors who will experience temporary economic impacts. Four proposed tube wells will be constructed on private land amounting to a total of 425 sq.m. and one public toilet amounting to 144 sq.m. A total of 18 fruit bearing trees were identified on these lands. No buildings or structures will be affected and there are no encroachers and squatters present. The 50 km. of distribution extension pipelines will be within the public right of way (ROW) and will temporarily affect the identified street hawkers and mobile vendors who will experience temporary economic displacement. Each hawker operates a small shop within temporary bamboo or wooden structures/kiosks which can be easily shifted with minimal disturbance. There are a total of 13 vulnerable households as they earn income considered below the poverty line.

3. Public consultations. Consultations were carried out during Resettlement Plan preparation and will continue throughout the subproject cycle. A grievance redress mechanism (GRM) will be made available as explained in this Resettlement Plan.

4. Implementation Arrangements. The subproject will be managed and implemented through a Project Implementation Unit (PIU) based in Gazipur Pourashava with the overall support and guidance of the Project Management Coordination Unit (PMCU) based at the Local Government Engineering Department (LGED) Headquarters in Dhaka. The detailed design, preparation and implementation of the capital investments will be supported by (i) consultancy support (both international and national); and (ii) technical support from LGED and the Department of Public Health Engineering (DPHE). The PIU will implement the Resettlement Plan with support from the PMCU and consultants. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per the entitlement matrix within this Resettlement Plan. Income restoration assistance to the affected persons includes both short and medium term strategies. The Government will provide all funds for land and resettlement in a timely manner.

5. Resettlement Plan Implementation and Monitoring. All compensation is to be paid prior to displacement (both physical and economic) however, ongoing income rehabilitation activities will continue after construction begins. Written confirmation of full compensation to displaced persons must be made to ADB prior to commencement of civil works in sections ready for construction. The estimated total period of the implementation of the Resettlement Plan is 13 months. Monthly monitoring reports will be submitted by PIU to PMCU. PMCU will ii consolidate monthly reports into semi-annual monitoring reports or as part of the regular project reporting and will submit to ADB.

I. PROJECT DESCRIPTION

A. Overview

1. The City Region Development Project (CRDP, the Project) emphasizes economic growth in Dhaka and Khulna city regions of Bangladesh through (i) creation of an enabling environment towards improved governance and capacity building of the local governments; and (ii) prioritized investments in infrastructure sectors in the two regions. The objectives of CRDP are (i) to improve the regional economic and social context through long-term development plans and investment programs, set within an institutional and regulatory context that will ensure implementation and review; (ii) to improve the capacity and mandate of local government to govern and to invest in improved economic activity at local level; (iii) to improve the economic context for sustainable commercial and industrial growth; and (iv) to improve the economic and social needs of the urban population, as an inclusive aspect of the CRDP. The subprojects are largely built around ‘integrated area planning’ principles which enhance economic activity in the regional context and provide opportunities for investment. This draft Resettlement Plan is based on a feasibility level study and preliminary engineering design and will be updated at the final detailed engineering stage.

2. The Gazipur water supply/sanitation subproject focuses on providing a sustainable framework in which water supply and sanitation (WSS) improvements may be delivered more effectively by incorporating and optimizing existing systems. At the same time, the subproject seeks to mitigate as far as practicable, the current depletion of groundwater resources by substantially reducing wastage in water delivery and use. A key aim of the subproject is for water to be produced and delivered more effectively and to improve energy efficiency and reduce power consumption.

3. The specific objectives of this subproject are to (i) rehabilitate the existing water supply sources, including the production tube wells and the distribution system in the core area of Gazipur; (ii) expand the sources of water supply within the core and fringe areas, including the construction of new production wells; (iii) improve the institutional structure of the Pourashava to more effectively deliver water and sanitation services; (iv) improve overall health and sanitary conditions; and (v) improve the financial standing of WSS services through the introduction of modern accounting, billing and revenue collection to full cost recovery.

B. Subproject Components

4. The details of each subcomponent under the subproject is described in the sections below.

1. Water Supply

5. Rehabilitation of existing production tube wells. The subproject includes rehabilitation of eight existing tube wells. Rehabilitation will include the following works: (i) collection of bore hole data and design; (ii) inspection by closed-circuit television (CCTV); (iii) unclogging tubewell silt deposits; (iv) removal of silt and debris; (v) borehole disinfection; and (vi) conducting step-drawdown test. Actual requirements will be based on the findings of the hydrogeological study. The locations of the tube wells are in Table 1.

2

Table 1: List of Existing Production Tube Wells Sl No Location and Area of the Production Ward No Tube Well (PTW) PTW-01 Rajbari Water Works Compound 04 PTW-02 Boruda 04 PTW-03 Madhov bari Water Works Compound 04 PTW-04 Bazar Water Works Compund 03 PTW-05 North Bilashpur 03 PTW-06 Laxmipura Water Works Compound 07 PTW-07 East Chandana near graveyard 07 PTW-08 Laxmipura Talukdar para 07 PTW = production tube well.

6. Refurbishment of existing water supply network. The existing water supply network in Gazipur Pourashava consists of 28 km of mainly PVC pipelines of 100 to 200 mm diameter. Activities under this component include (i) removing and replacing broken or leaking pipes; (ii) installing washout valves; (iii) flushing pipes for silt removal; and (iv) replacing illegal connections with new metered service. The work will be carried out to the existing distribution systems.

7. Interconnections of existing networks. A system of interconnection will be designed as part of the network analysis carried out in Phase 1 of this subproject. It is envisaged that significant operational efficiencies may be realized by the interlinking of the networks especially in regard to proposed network extensions and the provision a continuous 24 hrs supply.

8. Expansion of distribution network. It is aimed to increase the piped supply coverage from 34–65% of the Gazipur population. New supply areas will be determined during detailed design taking into account the findings of population surveys. Installation of water meters at consumer premises and production wells are also proposed. Allowance has been made for the installation of 1,000 new meters with valved service connections. Current estimates for new pipeline lengths are given in Table 2.

Table 2: Proposed Pipeline Network Extensions Existing pipeline Proposed Extension Length Pipe Diameter (km) (km) 200 mm 1.75 20 150 mm 12.75 15 100 mm 13.75 15 Total 28.25 50

9. New production tube wells. Activities are to include the drilling of 12 new production tube wells to provide additional water corresponding with the expansion of the water supply network. It is envisaged that 8 new production wells will be drilled with an additional 4 to be drilled as replacement of existing wells. The details on the location of the proposed production tube wells are described in Table 3.

Table 3: List of Proposed Production Tube Wells Sl No Location and Area of the Proposed Ward No Production Tube Well (PTW) PTW-01 East Bhurulia near primary school 01 PTW-02 West Bhurulia near mazir khola 01 PTW-03 West Bhurulia (Chayatoru) 01 3

Sl No Location and Area of the Proposed Ward No Production Tube Well (PTW) PTW-04 West Bhurulia near nandita hall 01 PTW-05 Near mariali school 03 PTW-06 West side of Niamot sharak 03 PTW-07 Sahapara 04 PTW-08 Sashan 04 PTW-09 Harinal 05 PTW-10 Bangalgach 06 PTW-11 East Chandana 07&08 PTW-12 Near Tin Sharak 07 PTW = production tube well.

10. Water supply to informal housing areas. The subproject will provide new production wells, hand pumps and drainage facilities in areas where gaps in provision have been identified under feasibility studies during the detailed design stage, including informal housing areas and in rural development clusters.

2. Sanitation Facilities

11. Public Toilets. Public toilets are very limited in the core area and this component includes for the construction of 10 new public toilets and wash facilities. Facilities are to be provided with piped water supply and drainage system with suitably designed soakways. The details on the names and locations of the proposed public toilets are described in Table 4.

Table 4: List of Proposed Public Toilet Sl No Location and Area of the Proposed Ward No Production Tube Well (PTW) PT-01 Near Duet 01 PT-02 Near BIDC Bazar 01 PT-03 Near Mazirkhola 01 PT-04 South Corner of Rajbari Field 04 PT-05 Raj Dhiigir Par 04 PT-06 Joor Pukhur par 04 PT-07 Kanya bazaar 06 PT-08 Niler Para near market 06 PT-09 Near Laxmipura jave councilor office 07 PT-10 Dirashram bazaar 08 PTW = production tube well.

12. Pit Latrines. The subproject also aims to construct 2,000 new pit latrines in the core and fringe areas, matching the priority needs identified during the course of discussions between the consultant team and representatives of the pourashava. 13. Sludge Management. Towards improved operation and maintenance (O&M) of the existing septic tanks within Gazipur, the subproject will provide new septage collection equipment and vehicles. Sludge drying beds are proposed to be developed at the existing solid waste dumping ground at Gazipur.

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

14. A total of 16 households will be affected consisting of five households losing a small piece of land for four proposed tube wells and one public toilet; and 11 street hawkers/mobile

4 vendors who will experience temporary economic impacts. Four proposed tube wells will be constructed on private land amounting to a total of 425 sq.m. and one public toilet amounting to 144 sq.m. A total of 18 fruit bearing trees were identified on these lands. No buildings or structures will be affected and there are no encroachers and squatters present. The 50 km of distribution extension pipelines will be within the public ROW and will temporarily affect 11 identified street hawkers and mobile vendors who will experience temporary economic displacement. Each hawker operates a small shop within a temporary bamboo or wooden structures/kiosks which can be easily shifted with minimal disturbance. A summary of land acquisition and resettlement impacts are described in Tables 5 and 6.

Table 5: Summary of Land Acquisition and Resettlement Impacts SI No. Name of the Impact on Temporary Remarks Components Land Impact Acquisition 1. Water Supply 1 Rehabilitation of No No Rehabilitation of 8 existing Existing Production production tube wells will not require Tube Wells any land acquisition. 2 Refurbishment of No No 28 km of mainly PVC pipelines of Existing Water Supply 100 to 200 mm diameter. Land Network acquisition not required. Works to occur at night to avoid and minimize disturbance to local businesses. 3 Interconnection of No No Land acquisition not required. Existing Networks 4 Extension of No Yes 50 kilometers of pipelines extension Distribution Network will temporarily affect 11 hawkers. Land acquisition not required. 5 Development of New Yes No Out of 12 proposed tubewells, 4 Production (Tube) require acquisition of private land Wells amounting to 281 sq.m. 6 Water Provision in No No Land acquisition not required. Informal Housing Areas 2. Sanitation 1 Construction public No Yes Out of the proposed 10 public toilets toilets only one will require land acquisition amounting to 144 sq.m. of private land. 2 Sanitation – Core Area No No Additional land acquisition not and Fringe Areas required. 3 Improved sludge No No Land acquisition not required. management system

Table 6: Details of Private Land Acquisition % loss Total Total Area to vs. % loss Cadastr Area to be area of Landholding Land be total vs. No. Component Location al Map Owner Acquired affected (Affected + Use acquired area of total No. (katha) plot Unaffected) (sq.m.) the holding (katha) (katha) plot Dirashram Mr. 1 Public Toilet Agric. – 2.00 144 2.00 100.00 83 2.41 Bazar Aftabuddin East Bhurulia Agric Mr. Habibur Pump House- 2 near primary – Rahman 2.07 149 3.44 60.17 96 2.16 01 school Talukder West Bhurulia Agric Pump House- Md. Anisur 3 near Mazir 273 0.50 36 2.00 25.00 52 0.96 02 Rahman khola Pump House- Near Mariali Agric Md. Mosarraf 4 – 0.50 36 5.00 10.00 89 0.56 05 School Hossain Mir Pump House- Agric Mr. Abdur 5 Saha Para – 0.83 60 4.00 20.75 78 1.06 07 Rahim Khan

Table 7: Socioeconomic Details of the Displaced Persons Experiencing Permanent Land Acquisition Household Size Vulnerability Main Monthly Income Below S.N Name of the Owner Occupation/Income Total Male Female (Tk) Women Physically Poverty Source Headed Handicapped Line Household Household Household* 1 Aftabuddin 5 2 3 Business 10,000 No No Yes 2 Habibur Rahman Talukder 12 7 5 Agriculture 8,500 No No Yes 3 Md. Anisur Rahman 10 3 7 Business 30,000 No No No 4 Md. Mosarraf Hossain Mir 7 3 4 Business 20,000 No No No 5 Abdur Rahim Khan 5 2 3 Business 12,000 No No No Note: Below Poverty line has been calculated on the basis of general formula which is $1 per day per person. The average family size in the subproject area is 5.3 and the $1= Tk72. Therefore, the threshold for poverty line has been considered as Tk11,475 income per month per household. 5 6

III. SOCIOECONOMIC INFORMATION AND PROFILE

15. Structured census survey questionnaires (Appendixes 1 and 2) were used to collect detailed information on the five affected households losing land. The survey was conducted in June 2010.1 A summary of socioeconomic data of affected persons is included below.

16. Land Owners. There are a total of five separate landowners losing small pieces of land as a result of the subproject. The total number of affected persons is 39. Total monthly income ranges between Tk10,000-20,000. Two of these households are considered vulnerable as they earn income below the poverty line. The land owners are mostly occupied in agriculture, service and doing small business.

17. Street Hawkers and Mobile Vendors. The subproject will impact 11 identified street hawkers and mobile vendors who are operating within or encroaching onto the ROW. Each operate within temporary structures. The uses of these structures are mostly for roadside small business activities. Out of the 11 affected street hawkers and mobile vendors, 2 are partially affected (structures encroaching onto the ROW) while the remaining 9 will be fully impacted as they are located entirely within the ROW. The types of structures are classified based on the type of construction, their usability and the age of the structure. All the structures are temporary as they have no permanent foundation and are between 1 to 10 years old. Each consists of bamboo pillars, Tripol/Plastic or thatched structures with iron corrugated sheets. The total area for each structure is approximately 12 sq.m. Therefore, each can be easily shifted to other locations without much disturbance. The average market price for replacing the structures ranges between Tk9,000 to Tk10,000. Therefore each of street hawkers and mobile vendors are considered vulnerable households as they earn below the poverty line.

18. Gender. During disbursement of assistance and compensation, priority will be given to female headed households. Joint ownership in the name of husband and wife will be offered in case of non-female headed households where the asset was acquired during their marriage.

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

A. Public Consultation

19. During subproject preparation, consultations were held with the official representatives of the Gazipur Pourashava, apart from the communities in the project area. The issues covered during these consultations included selection of subprojects and identification of key issues including addressing the current gaps in provision of basic services and improvement of urban environment conditions in the Gazipur urban area. These consultations (Table 8) provided an understanding of the needs and concerns of the project communities and the relevant stakeholders. Additionally, focus group discussions were also conducted with the local community especially with the DPs and the summary of these consultations is given in Appendix 3.

1 The survey team was trained by the international resettlement specialist consultant and the survey was closely monitored on a regular basis. The census survey included various aspects including (i) assessment of land including quantity and typology; (ii) Inventory of physical assets; (iii) potential income loss; (iv) impact on trees; (v) household characteristics, including social, economic and demographic profile; and (vi) temporary impacts on the hawkers’ business activities. 7

Table 8: Summary Consultation Findings Incorporation into Number of S.No. Place Date Participants Issues discussed Resettlement Plan participants and Project Design A Gazipur 12th 8 Executive Assessment of the Capacity building May engineer, CEO, environment and program, for training 2010 acting Mayor of social safeguard on environmental and Gazipur capacities of the social/involuntary Pourashava, Pourashava, resettlement aspects and other staff understanding of the to the Pourashava of Pourashava externally funded engineers, as part of projects implemented the project. Training till date, key issues on ADB’s safeguard pertaining to Policy Statement environmental requirement management, including land acquisition and resettlement B Gazipur 22nd 20 Mayor, CEO, Discussion and Joint site visits with June Executive finalization of the the elected 2010 engineer, subproject representatives to elected components identify lands which representatives, Siting of the project result in minimum staff of components to avoid land acquisition Pourashava impacts on land impacts acquisition C Gazipur 21st 15 Elected Siting of the project Site visits June representatives components to avoid undertaken, and 2010 and impacts on land consultations with communities, at acquisition and owners of the land locations of clearance of trees parcels where the distribution etc, production tubewells, networks, There was no toilets are proposed locations of objection to the to be sited. Assets on production construction activities land, including tubewells, and that may occur when structures, trees community the water network is evaluated, and toilets. laid, as these would compensation be temporary and provided for in the would result in long resettlement plan for term benefits to the the subproject. city residents. ADB = Asian Development Bank, CEO = Chief Executive Officer.

B. Information Disclosure

20. Project information will be continually disseminated through disclosure of resettlement planning documents. Resettlement information leaflets containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Bangla) and the same will be distributed to displaced persons. The PIU Resettlement Support staff (RSS) will keep the displaced persons informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. The information will also be made available at a convenient place especially, the market place which will be easily accessible to the displaced persons. The summary of the Resettlement Plan

8 and the entitlement matrix will be translated into the local language; disclosed to the displaced persons; and made available at PIU, local offices and libraries (or other pubic places), and at the LGED and DPHE offices. A copy of the Resettlement Plan will be disclosed on the LGED and ADB website.

C. Continued Consultation and Participation

21. For continued consultations, the following steps are to be taken:

(i) The PMCU and the PIU will organize public meetings and will apprise the communities about the progress in the implementation of resettlement, social and environmental activities; (ii) There will be a Grievance Redress Committees (GRC). The displaced persons will be associated with such committee along with their representatives; (iii) PMCU and PIU will organize public meetings to inform the community about the compensation and assistance to be paid. Regular update of the progress of the resettlement component of the project will be placed for public display at the PCMU and PIU offices; (iv) All monitoring and evaluation reports of the resettlement components of the project will be disclosed in the same manner as that of the Resettlement Plan; (v) Key features of the entitlements will be displayed along the project corridor; (vi) The PMCU and PIU will conduct information dissemination sessions at major intersections and solicit the help of the local community leaders to encourage the participation of the displaced persons in Resettlement Plan implementation; and (vii) Attempts will be made to ensure that vulnerable groups understand the process and to take their specific needs into account.

V. GRIEVANCE REDRESS MECHANISMS

22. A grievance redress mechanism (GRM) shall be set up in the Gazipur Pourashava PIU office to register grievances of the people regarding technical, social and environmental aspects. The process will designed to be transparent, gender responsive, culturally appropriate and commensurate to the risks and adverse impacts of the project, as well as readily accessible to all segments of the affected people. The project GRM will not supersede any legal government grievance procedures. Affected people are to be informed about the mechanism through media and public outlets. This participatory process shall ensure that all views of the people are adequately reviewed and suitably incorporated in the design and implementation process. The GRM will be implemented in three levels.

23. The first level and most accessible and immediate venue for the fastest resolve of grievances is the PIU, chiefly through the resettlement safeguards officer and Project Manager, with assistance from the Resettlement Specialist(s) of the Management Design Supervision Consultant (MDSC). The contact phone number will be posted in the project areas. Grievances will be resolved through continuous interactions with affected persons and the PIU will answer queries and resolve grievances regarding various issues including Environmental Management Plan implementation, land acquisition, structures acquisition, livelihood impacts, entitlements, and assistance. Corrective measures will be undertaken at the field-level itself within seven days. All grievances will be documented with full information of the person and issue.

24. Should the grievance remain unresolved, the PIU's Project Manager, will activate the second level of the GRM by referring the issue (with written documentation) to the local GRC of 9 the City Corporation, who will, based on review of the grievances, address them in consultation with the Safeguards Officer of the PIU and PMCU, and affected persons. A hearing will be called, if necessary, where the affected person can present his/her concern/issues. The process will promote conflict resolution through mediation. The local GRC will consist of the following persons: (i) Chief Executive Officer of the City Corporation (GRC Chair); (ii) representative of the mayor of the City Corporation; (iii) representative of the affected persons; (iv) official of the land registry department; (v) official of the Department of Environment (DOE) divisional office; (vi) town planner of the City Corporation; and (vii) Environmental/Social safeguards Officer of the PIU. The local GRC shall meet twice a month, unless the Project Director of the PIU informs that there are no grievances to address, or they shall meet as needed as per the severity of the grievance. The local GRC will suggest corrective measures at the field level and assign responsibilities for implementing its decisions.

25. The functions of the local GRC are as follows: (i) provide support to affected persons on problems arising from land acquisition (temporary or permanent); asset acquisition; and eligibility for entitlements, compensation and assistance; (ii) record grievances of affected persons, categorize and prioritize them and provide solutions within a month; and (iii) report to the aggrieved parties about developments regarding their grievances and decisions of the GRC.

26. Should the grievance still remain unresolved, the PIU Project Manager, will activate the third level of the GRM by informing the PMCU Project Director who will, based on review of the local GRC minutes and consultation with the PIU Project Manager, activate the PMCU level GRC. This committee shall comprise the following representatives:(i) Project Director PMCU; (ii) Environmental/Resettlement Safeguards Officer of the PMCU; (iii) representative from Land Ministry; (iv) representative from DOE; (v) representative of the affected persons; and (vi) Environmental/Social Safeguards officer of the PIU.

27. The GRC at the PMCU level shall meet based on the receipt of grievances, and the meeting shall be convened within 7 days of receipt of the grievance by the PMCU, and grievances redressed with 15 days. The Environmental / Resettlement Safeguards Officer of the PMCU will be responsible for processing and placing all papers before the PMCU GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out.

28. In the event that a grievance is not addressed by the PIU, local GRC, or the PMCU GRC, the affected person can seek legal redress of the grievance in the appropriate Courts (fourth level of GRM). Figure 1 illustrates the GRM.

10

Figure 1: Grievance Redress Mechanism (GRM)

DSMC = Design Supervision Management Consultant, GRC = Grievance Redress Committee, PIU = Project ImplementationUnit, PMCU = Project Management Coordination Unit.

VI. LEGAL FRAMEWORK

29. This Resettlement Plan is prepared based on all applicable legal and policy frameworks of the Government (i.e., the ARIPO) and ADB's SPS. A summary of applicable acts and policies is presented provided in the Project's Resettlement Framework.

30. The Government's policy through ARIPO does not cover project-affected persons without titles or ownership record, such as informal settler/squatters, occupiers, and informal tenants and lease-holders (without document) and does not ensure replacement value of the property acquired. The ARIPO has no provision of resettlement assistance for restoration of livelihoods of affected persons except for the legal compensation. Gaps between national law and ADB policy are identified and bridging measures are included in the Entitlement Matrix for the project, described below. ADB will not finance the project if it does not comply with its SPS nor will it finance the project if it does not comply with its host country's social and environmental laws. Where discrepancy between the ADB and Government policies exist, the ADB policy will prevail. Moreover, the SPS applies to all ADB-financed and/or ADB-administered sovereign projects, and their components regardless of the source of financing, including investment projects funded by a loan; and/or a grant; and/or other means.

11

VII. ENTITLEMENTS, ASSISTANCE AND BENEFITS

A. Eligibility

31. All displaced persons who are identified in the project-impacted areas on the cut-off date2 will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their pre-project living standards, income-earning capacity and production levels. The project will recognize both licensed and non-licensed vendors. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the detailed census during the detailed design. Displaced persons who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice (60 days), requested to vacate premises and dismantle affected structures prior to project implementation.

B. Entitlements

32. The entitlement matrix in Table 9 summarizes the main types of losses and the corresponding entitlements in accordance with the Government and ADB policies.

2 The cut-off date for title holders is based according to the formal notification, and for non-titleholders the date of the census survey during the detailed design. Those who encroach into the subproject area after the cut-off date will not be entitled to compensation or any other assistance. The PIU will take video and photo documentation to ensure entitled persons on the cut-off date.

12

Table 9: Entitlement Matrix Sl Type of Applicatio Entitled Entitlement Implementation Responsible No Loss n Person Issues Agency

1 Loss of Homestead Owner(s) with (i) Land-for-land option of equal productive capacity satisfactory  If land-for-land is  PIU/PMCU land land, legal title to owner if feasible and if alternate land is available. offered, title will be to  Deputy agricultural (ii) Cash compensation equivalent to replacement cost.3 both husband and Commissioner land, or (iii) Assistance in finding replacement land. wife, if feasible. vacant plot (iv) Provision of stamp duty, land registration fee, capital gains  Vulnerable tax, and value added tax incurred for replacement land. households4 to be (v) Option to be compensated if remaining land is no longer identified during viable. census survey (vi) Access to equivalent common property resources previously conducted as part of accessed the Resettlement (vii) Additional compensation for vulnerable households. Plan.  Viability of land to be determined in consultation with land owner. 2 Loss of Standing Owner(s) with (i) 60 days advance notice to harvest standing seasonal crops, if  Work schedule to PIU/PMCU crops crops and legal title, harvest is not possible, cash compensation for crops (or share allow harvesting prior and trees trees tenant(s), of crops) equivalent to prevailing market price. to acquisition and leaseholder(s), (ii) Cash compensation for perennial crops and fruit bearing trees avoid harvest season sharecropper(s based on annual net product market value multiplied by  Market value to be ), remaining productive years. determined in encroacher(s), (iii) Cash compensation equivalent to prevailing market price of consultation with squatter(s) timber for non-fruit trees. divisional forest department. 3 Loss of Residential Encroacher(s) (i) Cash compensation equivalent to replacement value of  Vulnerable PIU/PMCU structure / and squatter(s) structure (or part of structure) constructed by the displaced households to be commercial person. identified during structure (ii) Rights to salvage materials from structure. census surveys and other (iii) Provision of all taxes, registration costs, and other fees conducted as part of assets (e.g. incurred for replacement structure. the Resettlement fences, (iv) Shifting allowance based on actual cost of moving (e.g., truck Plan gates, hire, equipment, etc.). posts) (v) Additional compensation for vulnerable households. structure (vi) Assistance in finding alternate location.

3 The rate of compensation for acquired housing, land and other assets will be calculated at full replacement costs. The calculation of full replacement cost is described in Section B.V.c in this Resettlement Framework. Where market conditions are absent or in a formative stage, the borrower/client will consult with the displaced persons and host populations to obtain adequate information about recent land transactions, land value by types, land titles, land use, cropping patterns and crop production, availability of land in the project area and region, and other related information. The borrower/client will also collect baseline data on housing, house types, and construction materials. Qualified and experienced experts will undertake the valuation of acquired assets. In applying this method of valuation, depreciation of structures and assets is not to be taken into account. 4 Vulnerable households/displaced persons may include female-headed households, disable-headed households, indigenous persons/ethnic minority-headed households and Below Poverty Line households

Sl Type of Applicatio Entitled Entitlement Implementation Responsible No Loss n Person Issues Agency

4 Loss of Livelihood/ Business (i) 60 days advance notice.  Vulnerable PIU/PMCU livelihood source of owner (s), (ii) Assistance in finding alternate location. households to be income tenant (s), (iii) One time assistance for lost income based on three months identified during leaseholder(s), lost income (at replacement cost) or minimum wage rates census surveys employee(s), (whichever is higher). conducted as part of agricultural (iv) Shifting allowance and cost of reestablishing business the Resettlement worker(s), elsewhere (cost of truck hire, equipment, etc.). Plan hawker(s)/ (v) Training allowance in the form of cash equivalent to short term  Training allowance to vendors(s) training course. be paid directly to the (vi) Additional compensation for vulnerable households. training institute (vii) Consideration for project employment.

5 Impacts All impacts Vulnerable (i) Land-for-land option will be a guaranteed option for vulnerable  Vulnerable PIU/PMCU on displaced displaced persons if available. If not available, assistance in households to be vulnerabl persons finding new land. identified during e (ii) Additional allowance equivalent to Tk10,000/- for loss of land census surveys displaced or structure. conducted as part of persons (iii) Preference in project employment. the Resettlement Plan

6 Any other Unanticipated involuntary impacts shall be documented and PIU/PMCU loss not mitigated based on the principles provided in this resettlement identified framework and with compliance with the Government’s and ADB’s policy. ADB = Asian Development Bank, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

13

14

C. Assessment of Compensation Unit Values

33. Land. The land valuation process will consist of two different values – (i) the sale deed record, and (ii) expected price. The PIU will be responsible for providing the recorded rate from the Local Land Registry Office (LLRO) (i.e., the sale deed record). The PIU will consult with willing buyers/sellers of the area to collect the expected price of land. The PIU will then submit the two rates to the valuation committee. Based on these rates the valuation committee will derive a price which will be called as the current market rate. Additionally, the cost for tax and stamp duties etc will be added to the current marker as derived by the valuation committee which will finally be considered as the replacement cost.

34. Private Building and Structure. The compensation for houses, buildings and other immovable properties will be determined on the basis of replacement cost as on date without depreciation. The PIU with assistance from the Public Works Department (PWD) will determine the replacement cost of structures. PIU will engage experts form PWD and the experts will carry out on the field assessment of each property and will submit the report to the Deputy Commissioner office. PIU will ensure that the assessment is done keeping in consideration the market price and consultation with the owners by assessing sources, types and cost of materials, usage of the building and the cost related to labor and transportation etc.

35. Trees and Crops. The PIU will conduct the survey on unit prices of trees and crops affected by temporary or permanent land acquisition, in consultation with agriculture/horticulture experts. The compensation for crops will be calculated based the current market rate. The PIU will collect data on crops in the project area from the local department of agricultural extension. Subsequently, the unit/market rate for each crop will be determined in consultation with the department of agricultural extension. The unit prices for compensation of different species of fruit trees will be based on the market values of their fruits. For trees producing timber their unit prices will be based on species type, age, and quality. The cost for such trees will be collected after consultation with the divisional forest office.

36. Business or Sources of Income. The PIU will conduct a detailed census survey which is to include actual monthly income of the displaced persons followed by a verification of the income data based on the tax payment (for titled business owners). In the absence of the authentic income proof, the unit price will be collected from the displaced person during the survey. The average income in the project area as collected during the census is approximately 6,000 and therefore, the unit cost for one time for each household losing the income is Tk18,000.

VIII. INCOME RESTORATION AND REHABILITATION

A. Basic Provision for Relocation

37. The basic provision for loss of land has been taken as the cash compensation at market price which is equivalent to replacement cost. Advanced notice (60 days) will be provided for harvesting crops, or if harvesting is not possible, then the farmers will be compensated at replacement cost for such crops. Trees will be compensated at market value. All compensation is to be paid before displacement occurs. The land owners losing a small piece of land will not require any relocation as they will not be physically displaced nor they will be severely affected. The PIU will attempt to find suitable alternative locations for hawkers including creating potential formal market spaces where feasible. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation 15 for partially damaged structures, and relocation assistance, as per applicable according to the entitlement matrix. The PIU will compensate non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land, at full replacement cost. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. The preliminary number of displaced hawkers is quite minimal (only 11) in the subproject area and the consultation with these hawkers and vendors revealed that they will be willing to shift on their own provided they get some compensation. To help the hawkers losing structures in getting entitlements and relocating themselves, a relocation strategy will be adopted in the subproject including (i) all compensation will be paid and other resettlement entitlements will be before physical displacement; (ii) at least 60 days advance notice will be given; (iii) the PIU and Resettlement Support Staff will assist displaced persons during verification of assets and will provide necessary counseling on payment of compensation and assistance; (iv) in close consultation with the displaced persons, the PIU Resettlement Support Staff will fix the shifting dates agreed with the displaced persons in writing and the arrangements desired by the displaced persons with respect to their entitlements; and (v) in case of self relocation, the PIU will assist the displaced persons in finding alternative site within the area if so desired by the displaced persons.

B. Income and Livelihood Rehabilitation

38. Income restoration assistance to the displaced persons includes both short and medium term strategies. Short term income restoration strategies are for immediate assistance during relocation and include the following:

(i) Compensation for land, structures, crops, fruit bearing trees, and all other lost assets is paid in full before displacement occurs; (ii) Assistance in finding replacement land or alternate location for continuation of livelihood/living arrangements; (iii) Where provision of alternative sites is not feasible (for temporary impacts), compensation of lost income for period of disruption (if less than three months) or lump sum for three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (iv) Shifting allowance for reestablishing business elsewhere based on actual cost of moving/unloading; (v) 60 days’ advance notice to shift business or harvest standing seasonal crops (if harvest is not possible, compensation for share of standing crops at market rates); (vi) One time assistance for lost income based on three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (vii) Consideration for project employment; (viii) For vulnerable households, additional subsistence allowance equivalent to Tk10,000/household for restoring or enhancing their livelihood. Vulnerable households will be prioritized in any project employment; (ix) Provision of temporary access where possible to continue business; and (x) Restoration of affected land, structure, utilities, common property resource for continuation of business after construction is completed.

39. Medium-term income restoration activities will include skill development training based on need. The PIU will identify suitable local training institutes and pay fees directly to the training institution and provide the names of entitled person(s).

16

40. Where necessary, training may include (i) capacity building, enterprise training, and facilitating economic activities to landowners; and (ii) training for self employment to agricultural laborers. Training for self-employment and skill development which may include but not limited to (i) plumbing; (ii) electrical; (iii) automobile repair; and (iv) electronic repair and service, etc. Training will be imparted to any willing displaced person losing income or livelihood.

41. During the construction stage the displaced persons, especially vulnerable displaced persons, will be given preference over others in being engaged in project activities suitable to their skills. In order to make the displaced persons employable, the PIU will identify the required skills for the construction activities prior to the commencement of the construction and provide the required training to the displaced persons.

IX. RESETTLEMENT BUDGET AND FINANCING PLAN

42. The resettlement cost estimate for the Gazipur subproject (Table 10) includes eligible compensation, resettlement assistance, as outlined in the entitlement matrix, and support cost for Resettlement Plan implementation. The Government will be responsible for releasing the funds for resettlement in a timely manner. The total resettlement cost for the subproject is Tk17.15 million. The cost items are outlined below:

(i) Compensation for land; (ii) Compensation for trees (fruit bearing and timber trees); (iii) Compensation for structures (hawkers/vendors) and other immovable assets at their replacement cost; (iv) Assistance for stamp duty etc for legal titleholders for land acquisition; (v) Assistance in lieu of the loss of income and livelihood; (vi) Assistance for shifting of the structures; (vii) Training allowance; and (viii) Special assistance to vulnerable groups for their livelihood restoration.

Table 10: Resettlement Budget Sl. Item Unit Rate Quantity Amount No. (Tk) A Compensation A-1 Land sq.m. 23,225 425 9,870,625 A-2 Compensation for Fruit bearing Trees Numbers 20,000 11 220,000 A-3 Compensation for Non-fruit bearing Numbers 15,000 7 105,000 Trees A-4 Compensation for Temporary Structure Numbers 7,500 11 82,500 Sub Total (A) 10,278,125 B. Assistance B-1 Shifting Assistance Numbers 5,000 11 55,000 B-2 Training Assistance Numbers 12,000 16 192,000 B-3 Loss of Income Numbers 18,000 16 288,000 B-4 Assistance to Vulnerable Households Numbers 10,000 13 130,000 B-5 Assistance for Documentation (Stamp Numbers 10,000 5 50,000 Duty) for titleholders Sub Total (B) 715,000 C RP Implementation Support Cost C-1 Hiring of Resettlement Support Staff at Person 100,000 36 3,600,000 DCC/PIU Month 17

Sl. Item Unit Rate Quantity Amount No. (Tk) C-2 Administrative Cost Lump Sum 1,000,000 Subtotal C 4,600,000 Total (A+B+C) 15,593,125 Contingency (10%) 1,559,313 GRAND TOTAL 17,152,438 GRAND TOTAL (Million Tk) 17.15 GRAND TOTAL (Million USD) 0.24

A. Project Management Coordination Unit

43. The LGED will be the executing agency responsible for overall guidance and project implementation. A PMCU headed by a Project Director will implement the project investments and will be responsible for overall planning, management, coordination, supervision and progress monitoring of the CRDP in the two regions. The PMCU will ensure compliance with assurances, including safeguards and preparing and submitting reports, resettlement plan monitoring updates. To ensure effective implementation of the land acquisition and resettlement aspects, two full time PMCU resettlement safeguard officers will be recruited, including one Resettlement Compliance Officer primarily responsible for compliance with legal requirements of the Government, and one Resettlement Surveyor responsible for overseeing PIU preparation of the Resettlement Plan for subprojects and data collection. The MDSC will recruit one international and one national resettlement specialist to assist the PMCU in this regard. The PMCU will review monthly reports submitted by PIUs and will consolidate them into quarterly reports to ADB. Corrective actions to be taken when necessary based on close monitoring and results of grievance redress process.

B. Project Implementation Unit

44. The subproject will be managed and implemented through the PIU based in Gazipur Pourashava. The PIU will be responsible for carrying out the detailed design of the subprojects and updating Resettlement Plans for the sample subprojects and prepare new Resettlement Plans for future subprojects under the sector approach The PIU will ensure compliance with safeguards requirements of the Government and ADB. The PIU will be responsible for day-to- day monitoring of the project progress, including the implementation of the resettlement provisions in the project.

45. The capacity to implement safeguards planning and implementation at the PIU level is not currently adequate. Therefore, it is proposed that resettlement support staff (or facilitators) at the PIU level will be recruited. The number of resettlement support staff at each PIU will be commensurate to the scale of involuntary resettlement impacts (e.g., the greater the impact, the greater number of support staff needed). All PIU and PMCU safeguards staff will undergo training conducted by the consultant team’s resettlement specialists. Each PIU will prepare monitoring reports on all aspects concerning to resettlement planning and implementation of the land acquisition and resettlement issues and report to the PMCU on a monthly basis.

C. Management, Design and Supervision Consultants

46. The MDSC will hire one International Resettlement Specialist (IRS) and one National Resettlement Specialist (NRS). They will be responsible for updating/finalizing the Resettlement Plans of sample subprojects in accordance with this Resettlement Framework and based on the

18 detailed engineering design. These specialists will also prepare new Resettlement Plans for future subprojects under the sector approach consistent with this Resettlement Framework. This will be done in close coordination with PIU resettlement support staff and PMCU resettlement officers. The IRS and the NRS will assist in the overall supervision of the projects and ensure all plans are implemented in a smooth and timely manner in accordance with the provisions of the Resettlement Plan. They will also prepare and implement training and capacity development programs for resettlement planning for the PIU and PMCU safeguards staff (see section below on Training and Capacity Building), and will closely work with the PMCU and PIUs to ensure displaced persons are compensated before displacement occurs, including ongoing rehabilitation measures. The Terms of Reference (TORs) along with the specific tasks are attached in Appendix 5. Further details on agencies responsible for RP activities are in Table 11 and the organization chart for Resettlement Plan implementation is depicted in Figure 2.

Table 11: Institutional Roles and Responsibilities Activity Responsible Agency A. Subproject Initiation Stage and Institutional Setup Formation of PMCU. LGED Formation of PIU. LGED Finalization of sites for subprojects. PMCU/PIU/MDSC Disclosure of proposed land acquisition and subproject details by issuing PIU/PMCU Public Notice. Meetings at community/household level with displaced persons. PIU Capacity Building training. MDSC/IRS B. Resettlement Plan Preparation/Updating Stage Resettlement screening and categorization form and submission to ADB PIU/PMCU for each subproject. ADB to confirm resettlement categorization. ADB Census of 100% displaced persons and socioeconomic survey. PIU/PMCU Screening of vulnerable displaced persons. PIU/PMCU Survey on unit prices for computing replacement costs. PIU/PMCU Calculation of compensation and entitlements.. PIU/PMCU Update of sample subproject Resettlement Plans and preparing new PIU/PMCU Resettlement Plans in accordance with Resettlement Framework. Consultations with displaced persons on entitlements. Compliance with PIU/PMCU disclosure requirements. Finalize Resettlement Plans and submit to ADB. All draft Resettlement PIU/PMCU Plans must be submitted to ADB for clearance prior to award of contracts. Incorporate all comments and suggestions to Resettlement Plans. PIU/PMCU Web disclosure ADB/PMCU C. Resettlement Plan Implementation Stage Issuance of identification cards to displaced persons PIU/PMCU Detailed schedule for compensation PIU/PMCU Distribution of relocation notices to displaced persons PIU/PMCU Award of checks for land compensation PIU/PMCU Award of checks for other compensation and assistance/rehabilitation PIU/PMCU Confirm with ADB in writing when payment of entitled compensation to PMCU/PIU displaced persons has been completed. Permission to contractor to begin works once compensation to displaced persons is confirmed (note: other income rehabilitation to continue after civil works commence). Notice to proceed for civil works is issued on sections where PIU/PMCU compensation is paid. Demolishing/ relocation of affected structures/assets PIU/PMCU 19

Activity Responsible Agency Income restoration program and training PIU/PMCU Grievances redress mechanism PIU/PMCU/GRC Internal monitoring PIU/PMCU Review of Resettlement Plan implementation by external expert through External Expert a compliance report for projects with significant impacts ADB = Asian Development Bank, GRC = Grievance Redress Committee, IRS = International Resettlement Specialist, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

Figure 2: Organization Chart for Resettlement Plan Implementation

LGED ADB

PMCU

1 Resettlement Compliance Officer, 1 Resettlement Surveyor

MDSC 1 International Resettlement Specialist, 1 National Resettlement Specialist

PIU Resettlement Support staff

DISPLACED PERSONS

ADB = Asian Development Bank, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

X. IMPLEMENTATION SCHEDULE

47. Land acquisition, compensation and relocation of displaced persons cannot commence until the Resettlement Plan has been cleared by ADB. All entitlements are to be paid prior to displacement. Written confirmation is required by the PMCU to ADB stating that all compensation has been paid to displaced persons. Only then can construction works begin on sections where compensation has been paid. The project will be implemented over six years (January 2011 to December 2016). The implementation of the Resettlement Plan will include: (i) identification of cut-off date and notification; (ii) verification of losses and extent of impacts; (iii) finalization of entitlements and distribution of identity cards; (iv) consultations with displaced persons on their needs and priorities; and (v) resettlement, provision of compensation and assistance, and income restoration for displaced persons. The expected implementation schedule for a subproject is given in Table 12.

20

Table 12: Implementation Schedule Activity Months 1 2 3 45678910 11 12 13 14 15 16 17 18 Establishment of PMCU and PIU.  Appointment of safeguards staff in  PMCU and PIUs. Appointment of international and  national resettlement specialists on consultant team. Formation of GRC at PIU and PMCU  level. Census surveys (issuance of     identification cards). Send screening and categorization  form for subprojects to ADB. Consultations and disclosure.                  Confirmation of government land to   be used and transfer from other departments. Resettlement Plan preparation.      Resettlement Plan review and  approval (PMCU and ADB). All draft Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Issue notice to displaced persons.  Compensation prior to displacement    and income rehabilitation ongoing. Written confirmation from PMCU to  ADB that all compensation paid in sections ready for construction. Permission to contractor to begin works once compensation to displaced persons is confirmed. Relocation as required    Takeover possession of acquired    property Handover land to contractors  Start of civil works  Skills training as required for income       restoration Grievance Redress Mechanism Internal monitoring                Monthly monitoring reports (PIU to                PMCU) Quarterly monitoring reports (PMCU                to ADB) Rehabilitation of temporarily Immediately after occupied lands construction ADB = Asian Development Bank, GRC = Grievance Redress Committee, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. Note: The Resettlement Plan will be updated based on final detailed design and displaced person census and surveys. Endorsement and disclosure of finalized Resettlement Plans consistent with the Resettlement Framework to be undertaken.

21

XI. MONITORING AND REPORTING

48. The extent of monitoring activities will be commensurate with the project’s risks and impacts. Monthly monitoring reports to be submitted by PIU to PMCU. PMCU to consolidate monthly reports into quarterly monitoring reports to ADB. These reports should form a part of the project progress reports submitted by PMCU to ADB.

49. The objectives of monitoring are to (i) ensure that the standard of living of displaced persons are restored or improved; (ii) ascertain whether activities are progressing as per schedule and the timelines are being met; (iii) assess if compensation, rehabilitation measures are sufficient; (iv) identify problems or potential issues; and (v) identify methods to rapidly to mitigate problems. The above information will be collected by executing and implementing agencies through its PMCU and respective PIU which is responsible for monitoring the day-to- day resettlement activities of the project through the following instruments:

(i) Review of census information for all displaced persons; (ii) Consultation and informal interviews with displaced persons; (iii) In-depth case studies; (iv) Sample survey of displaced persons; (v) Key informant interviews; and (vi) Community public meetings.

50. Internal Monitoring. The internal monitoring by PMCU/PIU will include (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; and (ii) socio-economic monitoring during and after the relocation process to ensure that people are settled and recovering. This will utilize the baseline information established by the socio-economic survey of displaced persons undertaken during subproject preparation; and (iii) overall monitoring whether recovery has taken place successfully and on time. Monitoring will also include the following:

(i) Communication with and documentation of reactions from displaced persons. (ii) Information from displaced persons on entitlements, options, alternative developments, etc. (iii) Valuation of properties. (iv) Usages of grievance redress mechanism. (v) Disbursement of compensation amounts and all assistance. (vi) Physical progress of the Resettlement Plan implementation which will include relocation of displaced persons and affected community properties.

51. The indicators for achievement of objectives during Resettlement Plan implementation are of two kinds such as (i) Process Indicators (Indicating project inputs, expenditure, staff deployment, etc.); and (ii) Output Indicators: Indicating results in terms of numbers of displaced persons compensated, area of temporarily occupied lands restored with topsoil (and other pre- project features), number of displaced persons provided with skills training, etc. Input and output indicators related to physical progress of the work will include items such as:

(i) Training of executing and implementing agencies and other staff completed. (ii) Census, assets inventories, assessments and socio-economic studies completed. (iii) Grievance redress procedures in-place and functionality. (iv) Compensation payments disbursed.

22

(v) Relocation of displaced persons completed. (vi) Project employment provided to displaced persons. (vii) Infrastructure rehabilitated or constructed. (viii) Income restoration activities initiated. (ix) Skills training of displaced persons initiated. (x) Number of households displaced and resettled. (xi) Monitoring and evaluation reports submitted.

Appendix 1 23

CENSUS QUESTIONNAIRE FOR PERMANENT LAND ACQUISITION AND RESETTLEMENT

1. Questionnaire No: ______Date: ...... 2. Name of the Project Component /Site:

3. Name of the Mohallah:

4. Name of the Street:

5. Name of the Ward:

6. Name of the Pourashava:

7. Name of the Upazila:

8. Name of the Zilla/District:

9. Name of the Province:

10. Plot No. ------.

11. Ownership of the Land

1. Private 2. Government 3. Religious 4. Community 5. Khas 6. Others 12. Legal Status of Land/Owner

1. Legal/Title Holder 2. Encroacher 3. Squatter

13. Type of Land 1. Agricultural 2. Residential 3. Commercial 4. Fallow 5. Forest

14. Total Area of the Land/ Plot (Incase a portion of the land/ plot to be acquired/affected) (in Bigha) ......

15. Area to be Acquired / Affected Land (in Katha) ......

16. Total Land you possess (Total possession: affected + unaffected) (in Katha) Total......

17. Rate of the Land (Per Katha) 24 Appendix 1

1. Market Rate (Tk./Rs.)...... ……2. Government Rate (Tk.)......

18. Name of the Land Holder ......

19. Father’s Name ...... 20. Any of the following person associated with the Land

A. Agricultural Labour 1. Yes 2. No

B. Tenant 1. Yes 2. No

C. Share-Croppers 1. Yes 2. No

D. Lease Holder 1. Yes 2. No

21. If yes, their Numbers A. Agricultural Labour…………………….. B. Tenant……………………………………. C. Share-Croppers ………………………… D. Lease Holder…………………………… 22. Number of trees within the affected area

1. Total………………2. Fruit Bearing………3. Non-fruit Bearing………… 3. Timber…………………….

23. Any Building/structure in the Affected Land 1. Yes...... 2. No...... 24. Use of Structure

1 House 2 Boundary Walls/Fences 3 Residential-cum Commercial 4 Industry 5 Shops 6 Hotel/Restaurant 7 Small Eatery 8 Kiosks and Vendors 9 Mobile Vendors 10 Farm house 11 Gas Station 12 Private Clinic 13 Workshops 14 Govt. Offices 15 School / College 16 Hand pump 17 Hospitals 18 Water /Gas Pipe Line 19 Bus Stop 20 Transmission Lines 21 Mosque 22 Church 23 Mazar 24 Cemetery 25 Temple 26 Community centre 27 Cattle shed 28 Storage 29 Others

Appendix 1 25

25. Total area of the structure (in Square Meter) …………………..

26. Area of the affected structure (in Square Meter) …………………..

27. Type of Structure

1. Temporary 2. Semi-Permanent 3. Permanent

28. Age of the structure (Years)…………………….

29. Type of Construction Structure

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

30. Is the house/structure have the following?

A. Tenant 1. Yes 2. No

B. Employee in Commercial Structure 1. Yes 2. No

31. If yes, their Numbers A. Tenant…………………….. B. Employee…………………

32. Is the building/structure constructed by Tenant? 1. Yes 2. No

33. How much monthly rent you pay?......

34. Market Value of the Structure (in Tk.)......

35. Number of family members. Total………… Male …… Female……….

26 Appendix 1

36. Number of family members above 18 years

Total………… Male …… Female……….

37. Is it a woman headed household? 1. Yes 2. No

38. Is it a household owned by physically handicapped? 1. Yes 2. No.

39. Main Occupation of the Head of the Household (Main Source of Income)

1. Agriculture 2. Commercial /business 3. Service Holder. 4. Others (Specify)……

40. Total Monthly income of the family (Tk.)………….

41. Willing to shift

1. Voluntarily 2. Need Resettlement

42. Compensation Option

1. Land for land loss 2. Cash for Land loss 3. House/Shop for House/ Shop loss 4. Cash for House/ Shop loss

43. Desire Assistance and other help

1. Shifting Allowance 2. Employment Opportunities in Construction work 3. Assistance/ Loan from other ongoing development scheme 4. Training for Vocational activities 5. Others (specify ...... )

44. Is there alternate site available for relocation? 1. Yes 2. No. 45. If Yes, How far and the name of the place……………………………. Appendix 1 27

DETAILS OF THE AFFECTED PEOPLE

Sl. No Name of the Family Member Age Sex Occupation Marital status Education In 1. Male 1. Service 1. Married 1.Illiterate Years 2. Female 2. Business 2. unmarried 2.Literate 3. Agriculture 3. Widow 3.Up to Secondary 4. Study 4.Widower 4.Higher Secondary 5. Housewife 5. Others 5.Graduate 6. Labour 6. NA 6.Masters 7. Unemployed 7.Ph-D 8. Professional 8. NA 9. NA

Appendix 2 28

CENSUS QUESTIONNAIRE: INVENTORY OF TEMPORARY LOSS

1. Questionnaire No: ______Date: ...... 2. Name of the Project Component /Site:

3. Name of the Mohallah:

4. Name of the Street:

5. Name of the Ward:

6. Name of the Pourashava:

7. Name of the Upazila:

8. Name of the Zilla/District:

9. Name of the Province:

10. Property No. ------

11. Location 1. Left 2. Right

12. Status of the Property 1. Squatters 2. Encroachers

13. Name of the Owner ......

14. Father’s Name ......

15. Use of Structure 1 House 2 Huts 3 Sheds 4 Shops 5 Kiosks and Vendors 6 Mobile Vendors 7 Small Eatery/Teas Stall 8 Cattle shed 9 Boundary Walls/Fences

16. Area of the affected structure (in Square Meter) …………………..

17. Type of Structure 1. Temporary 2. Semi-Permanent

18. Age of the structure (Years)…………………….

Appendix 2 29

19. Type of Construction Structure

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

20. Market Value of the Structure (in Tk.)......

21. Number of family members. Total………… Male …… Female……….

22. Is it a woman headed household?

1. Yes 2. No

23. Is it a household owned by physically handicapped? 1. Yes 2. No.

24. Total Monthly income of the family (Tk.)………….

25. Willing to shift

1. Voluntarily 2. Need Resettlement

26. Compensation Option

1. Alternate structure 2. Cash for structure loss

27. Desire Assistance and other help 1. Shifting Allowance 2. Employment Opportunities in Construction work 4. License to resume the current activities 5. Others (specify ...... )

28. Is there alternate site available for relocation? 1. Yes 2. No. 29. If Yes, How far and the name of the place…………………………….

Appendix 3 30

DETAILS OF PUBLIC CONSULTATION AND FOCUS GROUP DISCUSSIONS

Date of Consultations: 22.06.2010 Number of Consultations: 03 numbers Place of Consultations: Gazipur: Laksmipur Mazir Khola, Sashan and Jore pokor per Number of Participants: 15

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 1 Have you heard about CRDP Most of the participants are aware about the project activities (City Region Development especially production well, public toilet and pipe water supply Project)? for the community. Most of the participants have welcomed CRDP project because they think these are essential for the community. 2 If yes, where from Many of the participants admitted that they heard about the project from councilors of Pourashava responsible for the specific ward of the Union. 3 General perception about the Most of the participants think that water and sanitation program project and the awareness about is very essential for this area. Many of the houses have no or the proposed project. very few water supply connection and in most of the cases houses do not have access of safe water. On the other hand Gazipur area is getting crowded day by day due to the increasing number of industries and workforce. Therefore all the project components are very significant for the locality. 4 Do others in this locality support According to the participant’s, water supply at household level this project? and public toilets in market are for people of the locality is very much essential. The whole population of this locality fell the need and benefits of the project. 5 Any critical issue or concern by No such critical issue was reported by the participants except the local people regarding the their worry about forceful evacuations of vendors during the project? construction time. The want fair compensation for people losing their land or structures to the project. 6 Any criteria you would like to see Public toilet should be in a crowded place and close to the considered during project design, market area. The construction works should be done by the construction and operation stage? local authority.

7 Employment Potential in the There is some employment potential there. Some working project which is of benefit to people will be benefited. village 8 Ethnic Minorities /Indigenous No indigenous people are residing in the project area and the peoples composition (If there are census survey also did not identify any such community. Indigenous People, please mention about the names of the indigenous people and number of households) 9 Numbers of Industrial Units in the There is about 28 industries the units, hundreds of shop in Mohallah/town and surrounding different types in the town. area 10 Is the area electrified Yes, the entire area is electrified but there are some roads without electric light. 11 Source of drinking water Tube-wells and some pipelines drinking water sources of the community of Paurashava. Most of the supply water systems are not operating successfully. Installation of each tube-well charged Tk50-60,000 and poor people of the community do not have ability of installation such kind of tube well. Appendix 3 31

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 12 Loss of residential/commercial There will be no permanent loss of land or structures/buildings structures, if any due to the due to the project except few temporary impacts on hawkers project and vendors.

13 Loss of community life like any There will be no loss of community life or market place as such Market Places or community except few squatters who need to be sifted. activities to be affected

14 Poverty Level: Is the village poor Being an urban community, majority of people working as or very poor or well off businessmen, shop owner, service holders. Poor sections of people belong to only laborers mostly migrated from countryside. 15 Education Status: Literate, About 80% of people are educated in Gazipur. Many educated illiterate etc people from this area as well as other district are also working in government and autonomous institutions (Bank, training centre, NGO) in Gazipur. Migrant labors of the industries are less educated. Almost all families send their children to school including the low income group. 16 Employment Status: Percentage A large number of people are employed in formal and informal of employment/ unemployment/ service/ activities. There is very few unemployed persons are in underemployment town. Increasing number of institutions and industries has created excellent working scopes for male female both in Gazipur. 17 Migration Pattern (If any), inward Yes, the area has highly significant for migration as a large or outward number of people migrated to this area to find work. Besides, there is also tendency of out migration is identified. Few members of some house have gone to , South Africa other countries and their families are depending on the remittance. 18 Are you satisfied with the present People are not fully satisfied with service being provided by the infrastructure facility in the town Pauroshava. Gazipur needs development of road, street and locality electricity and water supply for its growing population 19 Do you face any problem Yes, water supply is one of the major problems in Gazipur; the regarding the exiting water existing water supply is not providing enough water to the supply/solid waste people. Besides some public toilets are also needed management/river immediately for the increasing number of the population. port/Drainage/Traffic system? 20 If there is any problems related to Yes, very much necessary. these services, do you think that any upgradation is necessary?

21 For this upgradation the No, there is a plenty of area is available which is belongs to road/street/path /drainage may government land. get affected- what do you think about that- is it desirable? 22 How can this affect your present In broader aspect no negative impact will come through this living or activity project, only for few temporary settlements will be affected which has already been taken under consideration. 23 The project may need shifting of There are little temporary structures which need to be shifted. some encroachments and However, some help in the form of compensation and squatters .Would you like to shift assistance will be desirable and people will be able to shift from here on your own? voluntarily if they get compensation. 24 Where will you like to shift during They will find another government land for shifting and want this period? compensation for shifting.

32 Appendix 3

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 25 If requested to shift, would you It is up to the Pourashava. These shops are mostly squatters like to return here? and occupying the government land. But majority of them still want to shift government land because they have no other option and land is available too. 26 Is there available alternate place Yes, it is within one and half kilometer area. for relocation? If yes, how far and the name of the place

27 Perceived losses from the Temporary loss of the business only. Project- 28 If losses are perceived, what is Cash Compensation for the vendors and squatters and if the expected compensation you possible then license for reopening their business. The would desire Pourashava may issue license to the affected squatters.

29 Perceived benefits from the Safe water at home and public toilet in the market and crowded Project- locations. 30 Do you think that the local Yes, cooperation from the local people will be there during the residents would like to participate project implementation provided people’s views are taken in to in this work consideration by the Pourashava. 31 Do you think that the local people Yes, local people should be informed would like to get regular information regarding this Project? 32 Will it be through informal or Yes, it is very important to have consultation with the formal consultation community before the implementation. Both formal and informal consultation is desired through the help of ward councilor. 33 Will the project cause landslides No or soil erosion in the locality 34 Will the project cause widespread No imbalance by cutting fruit and commercial trees in the locality. 35 Will the project cause health and Only the water body where public toilet site was proposed safety issues in the area. would create health problem if proper safety measures are not taken. 36 Resettlement and Land 3-4 private lands (30’*30’) for proposed pump hose will be acquisition (if foreseen due to taken under Land acquisition program followed by ADB project components especially on resettlement frame work. private land). Has there been land acquisition before? If yes, what was the process of land acquisition and compensation package? 37 Protected areas (national park, No protected forest, religiously sensitive sites, historical or archaeological sites), if any 38 Health status, Availability of One hospital and few private hospitals are in Gazipur, but Hospitals and over all people prefer to go to the doctors/hospitals at Dhaka. The most environmental condition. Is there prevalent disease is diarrhea and fever during the rainy season. any chronic disease prevalent in People are aware about the HIV/AIDS this area and are you aware about HIV/AIDS and STP? Appendix 3 33

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 39 Will the project siting adversely No change migration pattern of animals that would destroy fields, habitats 40 What other organizations of a Some organizations provides loan to the community. BRAC social nature (NGOs/CBOs/ Civil ASHA and few local credit based organization are working in Society) active in the area? Name the locality. of these organizations 41 Will there be likely involvement of Yes local people in the implementation of the project?

42 Please indicate what kind of Women in the area are engaged in both primary and secondary economic/ non-economic sectors including agriculture, employed in government and activities female members of your private industries. family are engaged in 43 Does your female member have Decisions at family level are taken as sharing basis especially any say, in decision making of in better off or middle income group. household matters

44 How safe do you regard the Women of the community are not safe in all location. Some mobility of women in participants said the area close to Pourashava are safer than neighborhood / village the isolated area. 45 Do the women of your household Yes, Most of the women of the community travel freely can freely go outside to work, for specifically in day time. marketing, or accessing hospitals, educational institutes, etc? 46 How often women of your Women of poor family often fetch water from the neighboring household go outside the house household and road side water point. In summer most of the to fetch water in a week? shallow tube wells run out of water and community share other’s water sources. 47 Do you have a toilet at your Yes, most of the people have their own toilet. Some people household? have ring latrine or sharing latrine with community. 48 Do you have adequate street Yes, there are some street lights, however, these are not lighting during the night? enough, in the industrial area where women work and move frequently need more street lights for their safety. 49 Any Other Issues you may feel to No share: 50 Is this consultation useful? The consultation is very useful because, with this consultation Comments the exact situation of us (local people) came in light and it gives us freedom to speak our opinion on the coming project and also we think government will consider our views and take proper steps in this regard. ADB = Asian Development Bank, CBO = community-based organization, CRDP = City Region Development Project, NGO = nongovernment organization, STP = sewage treatment plant.

34 Appendix 3

LIST OF PARTICIPANTS S.No. Name Occupation Sex (M/F) Age (Years)

1 Sabina Housewife F 35 Noman, 2 Student M 18

Akhter Hossain 3 Business M 40

4 Selim Gazi Service M 40

5 Afaj Uddin Business M 40

6 Najmul Hasan Student M 18

7 Iqbal Hossain Student M 17

8 Md. Zobaer Business M 22

9 Shajahan Mir Business M 45

10 Samsuddin Pathan Pump Operator M 50

11 Mubarak Service M 37

12 Abdur Rashid Mollah Business M 50

13 Kajuli Begam Housewife F 50

14 Rahela Housewife F 30

15 Babul Halder Service M 38 35 Appendix 4

FUTURE CONSULTATION AND DISCLOSURE ROLES AND RESPONSIBILITIES

Project Phase Activities Details Responsible Agency

Subproject information dissemination on various components

-Leaflets containing Disclosure of Preliminary information on the Project and proposed for required land subproject area to be acquisition to displaced prepared) PIU(Gazipur Project persons Pourashava)/PMCU Initiation Stage -Public notice issued in public (LGED) Preliminary Information places including newspapers Sharing about the tentative and direct consultation with alignment/ sites with the displaced persons displaced persons in case of temporary impact on business, income and livelihood -Further consultations with PIU(Gazipur DPs/DPs and households, Pourashava)/PMCU titled and non-titled. (LGED)

-Summary Resettlement Stakeholder consultations Framework made available to all displaced persons at the convenient place which is easily accessible and should be in local language (Bengali) Disclosure of final PIU(Gazipur Resettlement entitlements and Resettlement Plans disclosed Pourashava)/PMCU Plan rehabilitation packages and to all displaced persons in (LGED) Preparation disclosure of draft local language (Bengali) Phase Resettlement Plan -Review and approval of PIU(Gazipur Resettlement Plan by Pourashava)/PMCU executing agency. (LGED) -Review and approval of Resettlement Plan by ADB Finalization of Resettlement (prior to award of contract). Plan -Web disclosure of the Resettlement Plan. -Disclosure of the Final Resettlement Plan to displaced persons -Consultations with displaced PIU(Gazipur persons; Pourashava)/PMCU Resettlement Consultation with displaced -Payment of entitlements; (LGED) Plan persons during Resettlement -Written notification from Implementation Plan implementation PMCU to ADB that all Stage compensation paid before displacement occurs ADB = Asian Development Bank, LGED = Local Government Engineering Department, PIU = Project Implementation Unit, PMCU= Project Management Cordination Unit. Appendix 5 36

MONITORING INDICATORS AND SAMPLE FOR STATUS REPORT

S. N. R&R Activities Progress Remarks Pre Construction Activities and R&R Activities 1 Assessment of Resettlement impacts due to changes in project design (If required) 2 Preparation/ updating of Resettlement Plan based on changes in project design 3 Approval of updated Resettlement Plan from ADB 4 Disclosure of updated Resettlement Plan 5 Establishment of Grievance Redress Committee 6 Capacity building of PIU Verification of displaced persons Census list; assessment on compensation and assistance, and readjustment 7 Land Acquisition Resettlement Plan Implementation 1 Payment of Compensation as per replacement value of land & assets to displaced persons 2 Disbursement of assistance to title holders 3 Disbursement of assistance to non-title holders 4 Disbursement of special assistance to vulnerable groups 5 Replacement/ shifting of community property resources 6 Reinstallation of public utilities 7 Records of Grievance Redress 8 Temporary Relocation of Hawkers and Vendors 9 Income Restoration Measures through training Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or use of children as labour 2 Prohibition of Forced or Compulsory Labour 3 Ensure equal pay for equal work to both men and women 4 Implementation of all statutory provisions on labour like health, safety, welfare, sanitation, and working conditions 5 Maintenance of employment records of workers ADB = Asian Development Bank, PIU = Project Implementation Unit, R&R = Resettlement & Rehabilitation.

City Region Development Project (RRP BAN 39298)

Resettlement Plan

Document Stage: Draft for Consultation Project Number: 39298 July 2010

BAN: City Region Development Project— Narayanganj Solid Waste Management Subproject

Prepared By: Local Government Engineering Department (LGED), Government of Bangladesh

The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

ABBREVIATIONS

ADB — Asian Development Bank ARIPO — Acquisition and Requisition of Immovable Property Ordinance CRDP — City Road Development Project DOE — Department of Environment GRC — Grievance Redress Committee GRM — Grievance Redress Mechanism IRS — International Resettlement Specialist LGED — Local Government Engineering Department MDSC — Management, Design and Supervision Consultant NRS — National Resettlement Specialist PMCU — Project Management Coordination Unit PIU — Project Implementation Unit ROW — right of way RSS — Resettlement Support Staff SPS — Safeguard Policy Statement SWM — solid waste management

TABLE OF CONTENTS

EXECUTIVE SUMMARY i

I. PROJECT DESCRIPTION 1 A. Overview 1 B. Subproject Components 1

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 2

III. SOCIOECONOMIC INFORMATION AND PROFILE 3

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 5 A. Public Consultation 5 B. Information Disclosure 7 C. Continued Consultation and Participation 7

V. GRIEVANCE REDRESS MECHANISMS 8

VI. LEGAL FRAMEWORK 9

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS 10 A. Eligibility 10 B. Entitlements 10 C. Assessment of Compensation Unit Values 12

VIII. INCOME RESTORATION AND REHABILITATION 12 A. Basic Provision for Relocation 12 B. Income and Livelihood Rehabilitiation 12

IX. RESETTLEMENT BUDGET AND FINANCING PLAN 13

X. INSTITUTIONAL ARRANGEMENTS 14 A. Project Management Coordination Unit 14 B. Project Implementation Unit 14 C. Management, Design and Supervision Consultants 15

XI. IMPLEMENTATION SCHEDULE 16

XII. MONITORING AND REPORTING 17

Appendixes 1. Details on Land Acquisition and Resettlement (Components Wise) 19 2. Census Questionnaire: Inventory of Temporary Loss 20 3. Summary of Consultations and FGDs 22

EXECUTIVE SUMMARY

1. The City Region Development Project (CRDP, the Project) will be financed by the Asian Development Bank (ADB) and is being formulated as a project loan using the sector approach to be implemented over a six-year period (January 2011 to December 2016). This document is a draft Resettlement Plan prepared for the Narayanganj Solid Waste Management subproject. It is based on a feasibility level study and preliminary engineering design and will be updated at the final detailed engineering stage. The Resettlement Plan is prepared in accordance with the ADB Safeguard Policy Statement, 2009 (SPS), Government of Bangladesh’s (the Government) policy, i.e., the Acquisition and Requisition of Immovable Property Ordinance, 1982 (ARIPO), and the Resettlement Framework adopted for CRDP. It is classified as Category B according to ADB’s SPS as minimal land acquisition and resettlement is required for this subproject.

2. The Narayanganj subproject consists of two components namely (i) eight solid waste transfer stations (50X30 square feet each), and (ii) one sanitary landfill site (2 acres). Design measures were adopted to minimize involuntary resettlement taking into consideration available Right of Way (ROW) for transfer stations and available government land for the landfill site.

3. Summary of Resettlement Impacts. The subproject will affect 17 households who are considered to be temporarily displaced and are taken as economically displaced households. These are hawkers and vendors operating small shops on government land. The structures are temporary in nature. Of the 17 displaced households, 11 are considered vulnerable (e.g., one woman-headed, and 10 below the poverty line). Vulnerable households are entitled to additional assistance under this resettlement plan.

4. Public Consultations. Consultations were carried out during Resettlement Plan preparation and will continue throughout the subproject cycle. A grievance redress mechanism (GRM) will be made available as explained in this Resettlement Plan.

5. Implementation Arrangements. The subproject will be managed and implemented through a Project Implementation Unit (PIU) based in Narayanganj Pourashava with the overall support and guidance of the Project Management Coordination Unit (PMCU) based at the Local Government Engineering Department (LGED) Headquarters in Dhaka. The detailed design, preparation and implementation of the capital investments will be supported by (i) consultancy support (both international and national); and (ii) technical support from LGED. The PIU will implement the Resettlement Plan with support from the PMCU and consultants. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per the entitlement matrix within this Resettlement Plan. Income restoration assistance to the affected persons includes both short and medium term strategies. The Government will provide all funds for resettlement in a timely manner.

6. Resettlement Plan Implementation and Monitoring. All compensation is to be paid prior to displacement however, ongoing income rehabilitation activities will continue after construction begins. Written confirmation of full compensation to displaced persons must be made to ADB prior to commencement of civil works in sections ready for construction. The estimated total period of the implementation of the Resettlement Plan is 13 months. Monthly monitoring reports will be submitted by PIU to PMCU. PMCU will consolidate monthly reports into semi-annual monitoring reports or as part of the regular project reporting and will submit to ADB. I. PROJECT DESCRIPTION

A. Overview

1. The City Region Development Project (CRDP, the Project) emphasizes economic growth in Dhaka and Khulna city regions of Bangladesh through (i) creation of an enabling environment towards improved governance and capacity building of the local governments, and (ii) prioritized investments in infrastructure sectors in the two regions. The objectives of CRDP are (i) to improve the regional economic and social context through long-term development plans and investment programs, set within an institutional and regulatory context that will ensure implementation and review; (ii) to improve the capacity and mandate of local government to govern and to invest in improved economic activity at local level; (iii) to improve the economic context for sustainable commercial and industrial growth; and (iv) to improve the economic and social needs of the urban population, as an inclusive aspect of the CRDP. The subprojects are largely built around ‘integrated area planning’ principles which enhance economic activity in the regional context and provide opportunities for investment. The primary purpose of the Narayanganj subproject is to improve public health and the urban environment through integrated solid waste management (SWM). The proposed subproject is to ensure that the collection and disposal of solid waste is sustainable, protects public health, and results in improved environmental conditions and practices. This is a Resettlement Plan to address involuntary resettlement impacts to affected persons in the subproject area.

B. Subproject Components

2. The Narayanganj subproject consists of two components namely (i) eight solid waste transfer stations (50X30 square feet each), and (ii) one sanitary landfill site (2 acres). Design measures were adopted to minimize involuntary resettlement taking into consideration available ROW for transfer stations and available government land for the landfill site. Further explanation of the subproject design is provided below.

1. Primary Collection

3. House-to-house primary collection will be implemented in Narayanganj Pourashava, geared towards collecting up to 55 tons of domestic waste per day from all households, using a simple segregation at source approach. Private sector operators, licensed by the Pourashava will collect waste from houses using tricycle vans. An additional 150 vans would be required to cover the solid waste generated in Narayanganj. The household service will be extended to the whole of Pourashava including the markets and other commercial and community facilities. No involuntary resettlement impacts are expected from primary collection activities.

2. Solid Waste Transfer Stations

4. Primary collectors will bring segregated solid waste to eight transfer stations where the waste will be transferred from the tricycles vans to conventional trucks, after which the trucks will transfer the waste to the proposed sanitary landfill site. This will provide the means to achieve the transfer efficiently and without significant environmental impact. Each transfer station will require a dedicated land area of around 50X30 square feet (size of transfer station will depend on site specific dimensions which is to be decided at detailed design). As the sites are within government owned land, no land acquisition is required. However, involuntary resettlement impacts will include impacts to hawkers/street vendors.

2

3. Sanitary Landfill

5. During Phase 1 of this subproject (this Resettlement Plan addresses Phase 1 only)1 the subproject will rehabilitate the existing dump site in Narayanganj into a sanitary landfill site and resource recovery facility (e.g., composting), therefore providing significant environmental and economic benefits to the community. The dumpsite for Narayanganj Pourashava, known as Ponchoboti, is located nearly 2.5 km from the town centre. The existing area is 2 acres. It is estimated that Narayanganj Pourashava is generating 55 tons of waste/day, where 48 tons of waste is organic. As per the estimate, about 4 tons will be filled every day, such that the landfill site can be used for up to 1,663 days or around 4.5 years at existing use rates. By this time, Phase 2 of the project will be implemented. As the location of the landfill site is government owned, no land acquisition is required, however, there are some hawkers operating small shops on the edge of the property which will require relocation.

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

6. There will be 17 total households affected by the project (8 at the transfer stations, and 7 at the landfill site), all of them being hawkers operating small shops on government land on a temporary basis.2 These small shops/kiosks are within temporary structures (e.g., bamboo sheds, small wooden or small tin shed structures). There is no land acquisition required for this subproject and its components. The land requirements for the landfill and transfer stations are minimal and hence limited impacts will occur. Specific design measures have been adopted to minimize involuntary resettlement by taking in to consideration existing available government land for the proposed landfill site. The impacts are limited to temporary economic displacement and relocation of hawkers. A summary of resettlement impacts are described Table 1. A detailed description of each proposed transfer station location and the landfill site along with its resettlement impacts are given in Appendix 1.

Table 1: Summary of Land Acquisition and Resettlement Impacts Sl Name of the Land Acquisition Involuntary Resettlement Remarks No Components 1 Primary Not required None This does not require Collection any physical construction. 2 Solid Waste Not required Temporary Impacts to 8 Out of the proposed 8 Transfer hawkers/vendors/squatters transfer stations only 2 Stations (8 Nos) stations have hawkers who are operating small shops. 3 Landfill at Not required Temporary Impacts to 9 The land belongs to the Narayanganj hawkers government/pourashava. These 9 hawkers are squatters and they run their small temporary shops on government land.

1 Phase 2 will develop a regional landfill site which is to include Narayanganj and other surrounding Pourashavas who are actively searching for land to implement Phase 2. This plan will serve the longer term needs of the pourashavas. A separate Resettlement Plan will be prepared for Phase 2 when it is ready. 2 As the Resettlement Plan will be updated at the detailed design stage, and the hawkers defined at the time of the census survey (the cut off date for receiving entitlements) the number of hawkers may be subject to change. 3

III. SOCIOECONOMIC INFORMATION AND PROFILE

7. Structured census survey questionnaires (Appendix 2) were used to collect detailed information on the impact of temporary impacts hawkers and vendors in the subproject area who are considered economically displaced. The survey was conducted in June 2010.3

8. Street Hawkers and Vendors. The subproject will impact street 17 households who are considered hawkers and vendors operating on government land. These structures are temporary in nature. The socioeconomic findings of the census are described below.

9. The socioeconomic profile of the displaced persons is homogenous nature. In addition to the inventory of assets the census survey recorded basic demographic data. These households are mostly engaged in small-scale business activities such as small shops, eatery, beetle shops, shoe maker and small repair shop. None of the households belong to Indigenous People or ethnic minority group as most of the displaced persons are Muslims. The major source of income of these vendors and hawkers households are the small business activities. The census survey revealed that some of the displaced persons have incomes below the poverty line are therefore considered vulnerable.

10. Average Monthly Income of displaced persons. The average income of the displaced households varies from each other. A majority of the households (7 displaced households) earn average monthly income in the range of Tk5,000 to 10,000. Around 11 displaced households reported that their income level per month between Tk11,000 to 15,000. Details are given in Table 2.

Table 2: Average Monthly Income of the Displaced Households Sl. No. Monthly Income (Tk) Number of Households % Age 1 Less than Tk3,000 1 6.25 2 Tk3001 to Tk5,000 2 12.50 3 Tk5,001 to Tk7,000 7 43.75 4 Tk7,001 to Tk9,000 0 0.00 5 Tk9,001 to Tk11,000 1 6.25 6 Tk11,001 to Tk15,000 5 31.25 7 Tk15,001 to Tk20,000 0 0.00 8 Above Tk20,000 0 0.00 9 Total 16 100.00 Average Monthly Income: Tk8,500 [Minimum 3000, Maximum Tk15,000]. Source: Census Survey, June 2010.

11. Vulnerable Households. Vulnerable households are defined as (i) women-headed displaced households, and (ii) physically handicapped displaced household and displaced households below poverty line.4 The total numbers of vulnerable displaced households are 11

3 The survey team was trained by the international resettlement specialist consultant and the survey was closely monitored on a regular basis. The census survey included various aspects including (i) assessment of land including quantity and typology (ii) Inventory of physical assets; (iii) potential income loss; (iv) impact on trees; (v) household characteristics, including social, economic and demographic profile; and (vi) temporary impacts on the hawkers’ business activities. 4 Below Poverty line has been calculated on the basis of general formula which is $1 per day per person. The average family size in the subproject area is 4.5 and the $1= Tk72. Therefore, the threshold for poverty line has been considered as Tk9,720 income per month per household.

4 out of which 1 displaced household is women headed and 10 displaced households fall below the poverty line. Details are given in Table 3.

Table 3: Vulnerable Households Sl. No. Vulnerable Displaced Households Numbers 1 Women Headed Households 1 2 Below Poverty Line Households 10 Total 11 Source: Census Survey, June 2010.

12. Structures. The use of the hawker’s structures is mostly for the road side small business activities. As per the census survey, 8 of the structures are of small shops, followed by 5 small eatery/tea stall shops, 2 kiosk, 1 shoe maker and one repair shop. Details are given in Table 4.

Table 4: Types of Hawkers Sl. Type of Number of Properties Percentage No. Properties/Structures and Households 1 Shops 8 47.06 2 Kiosks and Vendors 2 11.76 3 Mobile Vendors 0 0.00 4 Small Eatery/Teas Stall 5 29.41 5 Shoe maker 1 5.88 6 Repair Shop 15.88 Total 17 100.00 Source: Census Survey, June 2010.

13. The type of structures is classified based on the type of construction material, their usability and the age of the structure. All the structures are temporary meaning they do not have a permanent foundation and are characterized as having bamboo pillars, tripol/plastic/thatched structures covering small areas. Therefore, these can be easily shifted to another place without much disruption.

14. It was found that 10 structures were reported to be 1 year old, 5 structures between 1 and 5 years old and 2 structures between 5 to 10 years of old. Details on the age of structures are given in Table 5.

Table 5: Age of the Structures/Properties Sl. Number of Properties and Particulars Percentage No. Households 1 Below and up to 1year 10 58.82 2 Between 1 year to 5 year 5 29.41 3 Between 5 year to 10 year 2 11.76 Total 17 100.00 Source: Census Survey, June 2010.

15. A majority of the structures are made of iron sheet. Details on the type of construction of the structures are given in Table 6.

5

Table 6: Type of Construction Structure-Roof Sl. No. Particulars Number of Properties Percentage 1 Simple (thatch/sack/bamboo/slats) 6 35.29 2 Corrugated Iron sheet 11 64.71 Total 17 100.00 Source: Census Survey, June 2010.

16. The average market price as viewed by the displaced persons for the structures is up to Tk15,000. Details are given in Table 7.

Table 7: Average Market Price of the Structure Number of Properties Sl. No. Average Market Price (Tk) % Age and Households 1 Up to 5,000 9 52.94 2 5,000 to 10,000 5 29.41 3 10,000 to 15000 3 17.65 4 Above 15,000 0 0.00 Total 17 100.00 Source: Census Survey, June 2010.

17. Gender. During disbursement of assistance and compensation, priority will be given to female headed households. Joint ownership in the name of husband and wife will be offered in case of non-female headed households where the asset was acquired during their marriage.

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

A. Public Consultation

18. During subproject preparation, consultations were held with the official representatives of the Narayanganj Pourashava, apart from the communities in the subproject area. The issues covered during these consultations included selection of subprojects and identification of key issues including addressing the current gaps in provision of basic services and improvement of urban environment conditions in the Narayanganj Pourashava area. These consultations (Table 8) provided an understanding of the needs and concerns of the project communities and the relevant stakeholders. Additionally, focus group discussions were also conducted with the local community especially with the displaced persons and the summary of these consultations is given in Appendix 3.

Table 8: Consultations with Stakeholders Incorporation into Number of Resettlement Plan S.No. Place Date Participants Issues Discussed participants and Project Design A Narayanganj 12th 8 Executive Assessment of the Capacity building May engineer, environment and program, for 2010 Narayanganj social safeguard training on Pourashava, capacities of the safeguards aspects and other staff Pourashava, to the Pourashava of Pourashava. understanding of engineers, as part the externally of the project and funded projects proper institutional

6

Incorporation into Number of Resettlement Plan S.No. Place Date Participants Issues Discussed participants and Project Design implemented till mechanism date, key issues developed to pertaining to implement the environmental and Resettlement Plan. social management especially the land acquisition and resettlement and the temporary relocation of the illegal vendors and squatters. B Narayanganj 12th 12 Communities in Environmental The proposed June the vicinity of issues due to the designs include 2010 the existing ongoing solid measures to solid waste waste disposal, address the dumping site including smoke, environmental (Ponchoboti). smell etc. and impacts. The shifting of the 9 measures to hawkers who have address these been doing their impacts during the small business on operation of the the government landfill facility are land. integrated in the environmental management plan of the Project. Adequate assistance and advance notice to be given to these hawkers and the same provisions have been incorporated in the Resettlement Plan. This has also become an awareness exercise for the people regarding the project. C Narayanganj 23rd 15 Mayor, Need for the A potential land for June Narayanganj development of a the regional landfill 2010 Pourashava, regional landfill site identified. Local elected site, identification people have been representatives, of a suitable site, aware about the Mayors of 5 that can be utilized fact that they might adjoining as a regional have to give their Pourashavas. landfill site, land for the Need for development 7

Incorporation into Number of Resettlement Plan S.No. Place Date Participants Issues Discussed participants and Project Design introduction of purpose. better waste Pourashava people management have been advised practices in all the to take advance LGUs. action on negotiation with land owners and initiate further consultation for smooth acquisition of the required land for the phase-II landfill site. LGU = Local Government Unit.

B. Information Disclosure

19. Project information will be continually disseminated through disclosure of resettlement planning documents. Resettlement information leaflets containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Bangla) and the same will be distributed to displaced persons. The PIU Resettlement Support staff (RSS) will keep the displaced persons informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. The information will also be made available at a convenient place especially, the market place which will be easily accessible to the displaced persons. The summary of the Resettlement Plan and the entitlement matrix will be translated into the local language; disclosed to the displaced persons; and made available at PIU, local offices and libraries (or other pubic places, and at the LGED office. A copy of the Resettlement Plan will be disclosed on the LGED and ADB website.

C. Continued Consultation and Participation

20. For continued consultations, the following steps are to be taken:

(i) The PMCU and the PIU will organize public meetings and will apprise the communities about the progress in the implementation of resettlement, social and environmental activities. (ii) There will be a Grievance Redress Committees (GRC). The displaced persons will be associated with such committee along with their representatives. (iii) PMCU and PIU will organize public meetings to inform the community about the compensation and assistance to be paid. Regular update of the progress of the resettlement component of the project will be placed for public display at the PCMU and PIU offices. (iv) All monitoring and evaluation reports of the resettlement components of the project will be disclosed in the same manner as that of the Resettlement Plan. (v) Key features of the entitlements will be displayed along the project corridor. (vi) The PMCU and PIU will conduct information dissemination sessions at major intersections and solicit the help of the local community leaders to encourage the participation of the displaced persons in Resettlement Plan implementation.

8

(vii) Attempts will be made to ensure that vulnerable groups understand the process and to take their specific needs into account.

21. The details on consultation process and disclosure at various phases of project development including the responsible agency are described in Appendix 5.

V. GRIEVANCE REDRESS MECHANISMS

22. A grievance redress mechanism (GRM) will be established in Narayanganj soon after project commencement. The first level and most accessible and immediate venue for the fastest resolve of grievances is the PIU, chiefly through the RSS and Project Manager, with assistance from the Resettlement Specialist (National and International-NRS and IRS) of the Management, Design and Supervision Consultant (MDSC). The contact phone number will be posted in the project areas. Grievances will be resolved through continuous interactions with affected persons and the PIU will answer queries and resolve grievances regarding various issues including land acquisition, structures acquisition, livelihood impacts, entitlements, and assistance. Corrective measures will be undertaken at the field-level itself within seven days. All grievances will be documented with full information of the person and issue.

23. Should the grievance remain unresolved, the PIU's Project Manager, will activate the second level of the GRM by referring the issue (with written documentation) to the local GRC of the Pourashava, who will, based on review of the grievances, address them in consultation with the RSS of the PIU and PMCU, and affected persons. A hearing will be called, if necessary, where the affected person can present his/her concern/issues. The process will promote conflict resolution through mediation. The local GRC will consist of the following persons: (i) Chief Executive Officer of the Pourashava (GRC Chair); (ii) representative of the head of the Pourashava; (iii) representative of the affected persons; (iv) official of the land registry department; (v) official of the Department of Environment (DOE)’s divisional office; (vi) town planner of the Pourashava; and (vii) Environmental Specialist/RSS of the PIU. The local GRC shall meet twice a month, unless the Project Director informs that there are no grievances to address, or they shall meet as needed as per the severity of the grievance. The local GRC will suggest corrective measures at the field level and assign responsibilities for implementing its decisions.

24. The functions of the local GRC are as follows: (i) provide support to displaced persons on problems arising from land acquisition (temporary or permanent); asset acquisition; and eligibility for entitlements, compensation and assistance; (ii) record grievances of displaced persons, categorize and prioritize them and provide solutions within a month; and (iii) report to the aggrieved parties about developments regarding their grievances and decisions of the GRC.

25. Should the grievance still remain unresolved, the PIU Project Manager, will activate the third level of the GRM by informing the PMCU Project Director who will, based on review of the local GRC minutes and consultation with the PIU Project Manager, activate the PMCU level GRC. This committee shall comprise the following representatives:(i) Project Director PMCU; (ii) Environmental/Resettlement Officer of the PMCU; (iii) representative from Land Ministry; (iv) representative from DOE; (v) representative of the displaced persons; and (vi) Environmental/Social Safeguards officer of the PIU.

26. The GRC at the PMCU level shall meet based on the receipt of grievances, and the meeting shall be convened within 7 days of receipt of the grievance by the PMCU, and grievances redressed with 15 days. The Environmental / Resettlement Safeguards Officer of the 9

PMCU will be responsible for processing and placing all papers before the PMCU GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out.

27. In the event that a grievance is not addressed by the PIU, local GRC, or the PMCU GRC, the displaced person can seek legal redress of the grievance in the appropriate Courts (the fourth level of the GRM). A grievance redress mechanism and procedure is depicted in Figure 1.

Figure 1: Grievance Redress Mechanism (GRM)

DSMC = Design Supervision Management Consultant, GRC = Grievance Redress Committee, GRM = Grievance Redress Mechanism, PMCU = Project Management Coordination Unit, PIU = Project Implementation Unit.

VI. LEGAL FRAMEWORK

28. This Resettlement Plan is prepared based on all applicable legal and policy frameworks of the Government (i.e., ARIPO) and ADB's SPS. A summary of applicable acts and policies is presented provided in the Project's Resettlement Framework.

29. The Government's policy through ARIPO does not cover project-affected persons without titles or ownership record, such as informal settler/squatters, occupiers, and informal tenants and lease-holders (without document) and does not ensure replacement value of the property acquired. The ARIPO has no provision of resettlement assistance for restoration of livelihoods of affected persons except for the legal compensation. Gaps between national law and ADB policy are identified and bridging measures are included in the Entitlement Matrix for the project, described below. ADB will not finance the project if it does not comply with its SPS nor will it finance the project if it does not comply with its host country's social and environmental laws. Where discrepancy between the ADB and Government policies exist, the ADB policy will prevail. Moreover, the SPS applies to all ADB-financed and/or ADB-administered sovereign projects, and their components regardless of the source of financing, including investment projects funded by a loan; and/or a grant; and/or other means.

10

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS

A. Eligibility

30. All displaced persons who are identified in the project-impacted areas on the cut-off date5 will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their pre-project living standards, income-earning capacity and production levels. The project will recognize both licensed and non-licensed vendors. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the detailed census during the detailed design. Displaced persons who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice (60 days), requested to vacate premises and dismantle affected structures prior to project implementation.

B. Entitlements

31. The entitlement matrix in Table 9 summarizes the main types of losses and the corresponding entitlements in accordance with the Government and ADB policies.

5 The cut-off date for title holders is based according to the formal notification, and for non-titleholders the date of the census survey during the detailed design. Those who encroach into the subproject area after the cut-off date will not be entitled to compensation or any other assistance. The PIU will take video and photo documentation to ensure entitled persons on the cut-off date.

Table 9: Entitlement Matrix Sl Type of Applicatio Entitled Entitlement Implementation Responsible No Loss n Person Issues Agency

1 Loss of Residential Encroacher(s)  Cash compensation equivalent to replacement value of  Vulnerable  PIU/PMCU structure / and squatter(s) structure (or part of structure) constructed by the displaced households to be commercial person. identified during structure  Rights to salvage materials from structure. census surveys and other  Provision of all taxes, registration costs, and other fees incurred conducted as part of assets (e.g. for replacement structure. the Resettlement fences,  Shifting allowance based on actual cost of moving (e.g., truck Plan gates, hire, equipment, etc.). posts)  Additional compensation for vulnerable households. structure  Assistance in finding alternate location. 2 Loss of Livelihood/ Business  60 days advance notice.  Vulnerable  PIU/PMCU livelihood source of owner (s),  Assistance in finding alternate location. households to be income tenant (s),  One time assistance for lost income based on three months lost identified during leaseholder(s), income (at replacement cost) or minimum wage rates census surveys employee(s), (whichever is higher). conducted as part of agricultural  Shifting allowance and cost of reestablishing business the Resettlement worker(s), elsewhere (cost of truck hire, equipment, etc.). Plan hawker(s)/  Training allowance in the form of cash equivalent to short term  Training allowance to vendors(s) training course. be paid directly to the  Additional compensation for vulnerable households. training institute  Consideration for project employment.

3 Impacts All impacts Vulnerable  Land-for-land option will be a guaranteed option for vulnerable  Vulnerable  PIU/PMCU on displaced displaced persons if available. If not available, assistance in households to be vulnerabl persons finding new land. identified during e  Additional allowance equivalent to Tk10,000/- for loss of land or census surveys displaced structure. conducted as part of persons  Preference in project employment. the Resettlement Plan

4 Any other Unanticipated involuntary impacts shall be documented and  PIU/PMCU loss not mitigated based on the principles provided in this Resettlement identified Framework and with compliance with the Government’s and ADB’s policy. ADB = Asian Development Bank, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. 11

12

C. Assessment of Compensation Unit Values

32. Private Building and Structure. The compensation for structures will be determined on the basis of replacement cost as on date without depreciation. The PIU with assistance from the Public Works Department (PWD) will determine the replacement cost of structures. PIU will engage experts form PWD and the experts will carry out on the field assessment of each property and will submit the report to the Deputy Commissioner’s office. PIU will ensure that the assessment is done keeping in consideration the market price and consultation with the owners by assessing sources, types and cost of materials, usage of the building and the cost related to labor and transportation etc.

33. Business or Sources of Income. The PIU will conduct a detailed census survey which is to include actual monthly income of the displaced persons followed by a verification of the income data based on the tax payment (for titled business owners). In the absence of the authentic income proof, the unit price will be collected from the displaced person during the survey.

VIII. INCOME RESTORATION AND REHABILITATION

A. Basic Provision for Relocation

34. The PIU will attempt to find suitable alternative locations for hawkers including creating potential formal market spaces where feasible. The PIU will provide adequate and appropriate replacement structures or cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per applicable according to the entitlement matrix. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. To help hawkers losing structures in getting entitlements and relocating themselves, a relocation strategy will be adopted in the subproject including (i) all compensation will be paid and other resettlement entitlements will be before physical displacement; (ii) at least 60 days advance notice will be given; (iii) the PIU and Resettlement Support Staff will assist displaced persons during verification of assets and will provide necessary counseling on payment of compensation and assistance; (iv) in close consultation with the displaced persons, the PIU Resettlement Support Staff will fix the shifting dates agreed with the displaced persons in writing and the arrangements desired by the displaced persons with respect to their entitlements; and (v) in case of self relocation, the PIU will assist the displaced persons in finding alternative site within the area if so desired by the displaced persons.

B. Income and Livelihood Rehabilitation

35. Income restoration assistance to the displaced persons includes both short and medium term strategies. Short term income restoration strategies are for immediate assistance during relocation and include the following:

(i) Compensation for structure paid in full before displacement occurs; (ii) Assistance in finding alternate location for continuation of livelihood/living arrangements; (iii) Where provision of alternative sites is not feasible (for temporary impacts), compensation of lost income for period of disruption (if less than three months) or lump sum for three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (iv) Shifting allowance for reestablishing business elsewhere based on actual cost of moving/unloading; (v) 60 days’ advance notice to shift business; (vi) One time assistance for lost income based on three months lost income (at replacement cost) or minimum wage rates (whichever is higher); 13

(vii) Consideration for project employment; (viii) For vulnerable households, additional subsistence allowance equivalent to Tk10,000/household for restoring or enhancing their livelihood. Vulnerable households will be prioritized in any project employment; (ix) Provision of temporary access where possible to continue business; and (x) Restoration of affected land, structure, utilities, common property resource for continuation of business after construction is completed.

36. Medium-term income restoration activities will include skill development training based on need. The PIU will identify suitable local training institutes and pay fees directly to the training institution and provide the names of entitled person(s).

37. Where necessary, training may include (i) capacity building, enterprise training, and facilitating economic activities to landowners; and (ii) training for self employment to agricultural laborers. Training for self-employment and skill development which may include but not limited to (i) plumbing; (ii) electrical; (iii) automobile repair; and (iv) electronic repair and service, etc. Training will be imparted to any willing displaced person losing income or livelihood.

38. During the construction stage the displaced persons, especially vulnerable displaced persons, will be given preference over others in being engaged in project activities suitable to their skills. In order to make the displaced persons employable, the PIU will identify the required skills for the construction activities prior to the commencement of the construction and provide the required training to the displaced persons.

IX. RESETTLEMENT BUDGET AND FINANCING PLAN

39. The resettlement cost estimate for the Narayanganj solid waste management subproject (Table 10) includes eligible compensation, resettlement assistance, as outlined in the entitlement matrix, and support cost for Resettlement Plan implementation. The Government of Bangladesh will release funds to the PMCU and the PMCU will release funds to the PIU in a timely manner. The PIU in Narayanganj Pourashava will then release funds for resettlement. The total resettlement cost for the subproject is Tk4.22 million. The cost items of this Resettlement Plan are outlined below:

(i) Compensation for structures (hawkers/vendors) and other immovable assets at their replacement cost; (ii) Assistance in lieu of the loss of income and livelihood; (iii) Assistance for shifting of the structures; (iv) Training allowance; and (v) Special assistance to vulnerable groups for their livelihood restoration.

Table 10: Resettlement Budget Sl. Item Unit Rate Quantity Amount No. (Tk) A Compensation A-1 Compensation for Temporary Structure Numbers 6.0 17 102,000 Sub Total (A) 102,000 B. Assistance B-1 Shifting Assistance Numbers 5.0 17 85,000 B-2 Training Assistance Numbers 12.0 17 204,000 B-3 Loss of Income Numbers 25.5 17 433,500 B-4 Assistance to Vulnerable Households Numbers 10.0 11 110,000 Sub Total (B) 832,500 C Resettlement Plan Implementation Support Cost

14

Sl. Item Unit Rate Quantity Amount No. (Tk) C-1 Hiring of Resettlement Support Staff at Person Month 100000 24 2,400,000 Narayanganj Pourashava/PIU C-2 Administrative Cost Lump Sum 500,000 Subtotal C 2,900,000 Total (A+B+C) 3,834,500 Contingency (10%) 383,450 GRAND TOTAL 4,217,950 GRAND TOTAL (Million Tk) 4.22 GRAND TOTAL (Million USD) 0.06

X. INSTITUTIONAL ARRANGEMENTS

A. Project Management Coordination Unit

40. The LGED will be the executing agency responsible for overall guidance and project implementation. A PMCU headed by a Project Director will implement the project investments and will be responsible for overall planning, management, coordination, supervision and progress monitoring of the CRDP in the two regions. The PMCU will ensure compliance with assurances, including safeguards and preparing and submitting reports, resettlement plan monitoring updates. To ensure effective implementation of the land acquisition and resettlement aspects, two full time PMCU resettlement safeguard officers will be recruited, including one Resettlement Compliance Officer primarily responsible for compliance with legal requirements of the Government, and one Resettlement Surveyor responsible for overseeing PIU preparation of the RP for subprojects and data collection. The MDSC will recruit one international and one national resettlement specialist to assist the PMCU in this regard. The PMCU will review monthly reports submitted by PIUs and will consolidate them into quarterly reports to ADB. Corrective actions to be taken when necessary based on close monitoring and results of grievance redress process.

B. Project Implementation Unit

41. The subproject will be managed and implemented through the PIU based in Narayanganj Pourashava. The PIU will be responsible for carrying out the detailed design of the subprojects and updating Resettlement Plans for the sample subprojects and prepare new Resettlement Plans for future subprojects under the sector approach The PIU will ensure compliance with safeguards requirements of the Government and ADB. The PIU will be responsible for day-to-day monitoring of the project progress, including the implementation of the resettlement provisions in the project.

42. The capacity to implement safeguards planning and implementation at the PIU level is not currently adequate. Therefore, it is proposed that resettlement support staff (or facilitators) at the PIU level will be recruited. The number of resettlement support staff at each PIU will be commensurate to the scale of involuntary resettlement impacts (e.g., the greater the impact, the greater number of support staff needed). All PIU and PMCU safeguards staff will undergo training conducted by the consultant team’s resettlement specialists. Each PIU will prepare monitoring reports on all aspects concerning to resettlement planning and implementation of the land acquisition and resettlement issues and report to the PMCU on a monthly basis.

15

C. Management, Design and Supervision Consultants

43. The MDSC will hire one International Resettlement Specialist (IRS) and one National Resettlement Specialist (NRS). They will be responsible for updating/finalizing6 the Resettlement Plans of sample subprojects in accordance with this Resettlement Framework and based on the detailed engineering design. These specialists will also prepare new RPs for future subprojects under the sector approach consistent with this Resettlement Framework. This will be done in close coordination with PIU resettlement support staff and PMCU resettlement officers. The IRS and the NRS will assist in the overall supervision of the projects and ensure all plans are implemented in a smooth and timely manner in accordance with the provisions of the Resettlement Plan. They will also prepare and implement training and capacity development programs for resettlement planning for the PIU and PMCU safeguards staff (see section below on Training and Capacity Building), and will closely work with the PMCU and PIUs to ensure displaced persons are compensated before displacement occurs, including ongoing rehabilitation measures. Further details on agencies responsible for Resettlement Plan activities are in Table 11 and the organization chart for RP implementation is depicted in Figure 2.

Table 11: Institutional Roles and Responsibilities Activity Responsible Agency A. Subproject Initiation Stage and Institutional Setup Formation of PMCU. LGED Formation of PIU. LGED Finalization of sites for subprojects. PMCU/PIU/MDSC Disclosure of proposed land acquisition and subproject details PIU/PMCU by issuing Public Notice. Meetings at community/household level with displaced persons. PIU Capacity Building training. MDSC/IRS B. RP Preparation/Updating Stage Resettlement screening and categorization form and submission PIU/PMCU to ADB for each subproject. ADB to confirm resettlement categorization. ADB Census of 100% displaced persons and socioeconomic survey. PIU/PMCU Screening of vulnerable displaced persons. PIU/PMCU Survey on unit prices for computing replacement costs. PIU/PMCU Calculation of compensation and entitlements.. PIU/PMCU Update of sample subproject Resettlement Plans and preparing PIU/PMCU new Resettlement Plans in accordance with Resettlement Framework. Consultations with displaced persons on entitlements. PIU/PMCU Compliance with disclosure requirements. Finalize Resettlement Plans and submit to ADB. All draft PIU/PMCU Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Incorporate all comments and suggestions to Resettlement PIU/PMCU Plans. Web disclosure ADB/PMCU C. RP Implementation Stage Issuance of identification Cards to displaced persons PIU/PMCU Detailed schedule for compensation PIU/PMCU Distribution of relocation notices to displaced persons PIU/PMCU Award of checks for land compensation PIU/PMCU Award of Checks for other compensation and assistance/ PIU/PMCU rehabilitation Confirm with ADB in writing when payment of entitled PMCU/PIU compensation to displaced persons has been completed. Permission to contractor to begin works once compensation to displaced persons is confirmed (note: other income

6 All resettlement plans are to be updated based on detailed designs.

16

Activity Responsible Agency rehabilitation to continue after civil works commence). Notice to proceed for civil works is issued on sections where PIU/PMCU compensation is paid. Demolishing/ relocation of affected structures/assets PIU/PMCU Income restoration program and training PIU/PMCU Grievances redress mechanism PIU/PMCU/GRC Internal monitoring PIU/PMCU Review of Resettlement Plan implementation by external expert External Expert through a compliance report for projects with significant impacts ADB = Asian Development Bank, GRC = Grievance Redress Committee, IRS = International Resettlement Specialist, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

Figure 2: Organization Chart for Resettlement Plan Implementation

LGED ADB

PMCU

1 Resettlement Compliance Officer, 1 Resettlement Surveyor

MDSC 1 International Resettlement Specialist, 1 National Resettlement Specialist

PIU Resettlement Support staff

DISPLACED PERSONS

ADB = Asian Development Bank, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

XI. IMPLEMENTATION SCHEDULE

44. Land acquisition, compensation and relocation of displaced persons cannot commence until the Resettlement Plan has been cleared by ADB. All entitlements are to be paid prior to displacement. Written confirmation is required by the PMCU to ADB stating that all compensation has been paid to displaced persons. Only then can construction works begin on sections where compensation has been paid. The project will be implemented over six years (January 2011 to December 2016). The implementation of the Resettlement Plan will include: (i) identification of cut-off date and notification; (ii) verification of losses and extent of impacts; (iii) finalization of entitlements and distribution of identity cards; (iv) consultations with displaced persons on their needs and priorities; and (v) resettlement, provision of compensation and assistance, and income restoration for displaced persons. The expected implementation schedule for a subproject is given in Table 12.

17

Table 12: Implementation Schedule Activity Months 1 2 345678910 11 12 13 14 15 16 17 18 Establishment of PMCU and PIU.  Appointment of safeguards staff in  PMCU and PIUs. Appointment of international and  national resettlement specialists on consultant team. Formation of GRC at PIU and PMCU  level. Census surveys (issuance of     identification cards). Send screening and categorization  form for subprojects to ADB. Consultations and disclosure.                  Confirmation of government land to   be used and transfer from other departments. Resettlement Plan preparation.      Resettlement Plan review and  approval (PMCU and ADB). All draft Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Issue notice to displaced persons.  Compensation prior to displacement    and income rehabilitation ongoing. Written confirmation from PMCU to  ADB that all compensation paid in sections ready for construction. Permission to contractor to begin works once compensation to displaced persons is confirmed. Relocation as required    Takeover possession of acquired    property Handover land to contractors  Start of civil works  Skills training as required for income       restoration Grievance Redress Mechanism Internal monitoring                Monthly monitoring reports (PIU to                PMCU) Quarterly monitoring reports (PMCU                to ADB) Rehabilitation of temporarily Immediately after occupied lands construction ADB = Asian Development Bank, GRC = Grievance Redress Committee, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. Note: The resettlement plan will be updated based on final detailed design and displaced person census and surveys. Endorsement and disclosure of finalized resettlement plans consistent with the resettlement framework to be undertaken.

XII. MONITORING AND REPORTING

45. The extent of monitoring activities will be commensurate with the project’s risks and impacts. Monthly monitoring reports to be submitted by PIU to PMCU. PMCU to consolidate monthly reports into semi-annual monitoring reports to ADB. These reports should form a part of the project progress reports submitted by PMCU to ADB.

18

46. The objectives of monitoring are to (i) ensure that the standard of living of displaced persons are restored or improved; (ii) ascertain whether activities are progressing as per schedule and the timelines are being met; (iii) assess if compensation, rehabilitation measures are sufficient; (iv) identify problems or potential issues; and (v) identify methods to rapidly to mitigate problems. The above information will be collected by executing and implementing agencies through its PMCU and respective PIU which is responsible for monitoring the day-to-day resettlement activities of the project through the following instruments:

(i) Review of census information for all displaced persons; (ii) Consultation and informal interviews with displaced persons; (iii) In-depth case studies; (iv) Sample survey of displaced persons; (v) Key informant interviews; and (vi) Community public meetings.

47. Internal Monitoring. The internal monitoring by PMCU/PIU will include (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; and (ii) socio-economic monitoring during and after the relocation process to ensure that people are settled and recovering. This will utilize the baseline information established by the socio-economic survey of displaced persons undertaken during subproject preparation; and (iii) overall monitoring whether recovery has taken place successfully and on time. Monitoring will also include the following:

(i) Communication with and documentation of reactions from displaced persons. (ii) Information from displaced persons on entitlements, options, alternative developments, etc. (iii) Valuation of properties. (iv) Usages of grievance redress mechanism. (v) Disbursement of compensation amounts and all assistance. (vi) Physical progress of the Resettlement Plan implementation which will include relocation of displaced persons and affected community properties.

48. The indicators for achievement of objectives during Resettlement Plan implementation are of two kinds such as (i) Process Indicators (Indicating project inputs, expenditure, staff deployment, etc.); and (ii) Output Indicators: Indicating results in terms of numbers of displaced persons compensated, area of temporarily occupied lands restored with topsoil (and other pre-project features), number of displaced persons provided with skills training, etc. Input and output indicators related to physical progress of the work will include items such as:

(i) Training of executing and implementing agencies and other staff completed. (ii) Census, assets inventories, assessments and socio-economic studies completed. (iii) Grievance redress procedures in-place and functionality. (iv) Compensation payments disbursed. (v) Relocation of displaced persons completed. (vi) Project employment provided to displaced persons. (vii) Infrastructure rehabilitated or constructed. (viii) Income restoration activities initiated. (ix) Skills training of displaced persons initiated. (x) Number of households displaced and resettled. (xi) Monitoring and evaluation reports submitted.

DETAILS ON LAND ACQUISITION AND RESETTLEMENT (COMPONENTS WISE) Sl Name of the Name of the Name of the Name of Ownership of Land Acquisition and Location of the site No Components Mohalla Street the Ward Land Resettlement Impacts Solid Waste Transfer Stations 1 Transfer Stations-01 Ukilpara Bangabandhu 5 Pourashava Just Opposite to Digubabu Nil (Ukilpara Moar) Road Market (At Ukilpara Moar) & on the BB Road 2 Transfer Stations-02 Gulshan Hall Moar Bangabandhu 8 Pourashava Adjacent to Gulzar Nil (Gulshan Hall Moar) Road Confectionary and on BB road (Gulshan Moar). 3 Transfer Stations-03 Balur Math Bangabandhu 4 Pourashava Just adjacent to Family Nil (Press Club Area) Road Planning Office, opposite to Narayanganj Press Club and on BB road. 4 Transfer Stations-04 Missionpara Nawab 4 Pourashava On Nawab Salimullah Road Nil (Hokar's Market) Salimullah Facing Hoker's Market Road (Opposite to Central Diagonestic Center) 5 Transfer Stations-05 Haziganj Isa Khan Road 2 Pourashava Adjacent to Haziganj Fort [At Nil (M Circus Moar) the intersection of Fort Road and Isa Khan Road]. Near Rocky Textile and Capital Packaging Industry. 6 Transfer Stations-06 Khanpur Hospital Road 4 Pourashava Opposite to the gate no. 2 of Nil (Khanpur Hospital) Narayanganj Hospital 7 Transfer Stations-07 Jollarpar Paikpara 7 Pourashava Near Pourashava office No permanent land (Jollapur) Road/Shahsuja acquisition required. A total of Road 5 Hawkers will be displaced 8 Transfer Stations-08 ACI Gate ACI Panirkal 1 Pourashava Near Water Intake point No permanent land (ACI Gate) Road acquisition required. A total of 3 Hawkers will be displaced Landfill Site

9 Ponchoboti Landfill Sashongaon Enayat Nagar 1 Pourashava Near existing landfill site No permanent land 19 Appendix 1 Site acquisition required. A total of 9 Hawkers will be displaced

20 Appendix 2

CENSUS QUESTIONNAIRE: INVENTORY OF TEMPORARY LOSS

1. Questionnaire No: ______Date: ...... 2. Name of the Project Component /Site:

3. Name of the Mohallah:

4. Name of the Street:

5. Name of the Ward:

6. Name of the Pourashava:

7. Name of the Upazila:

8. Name of the Zilla/District:

9. Name of the Province:

10. Property No. ------

11. Location 1. Left 2. Right

12. Status of the Property 1. Squatters 2. Encroachers

13. Name of the Owner ......

14. Father’s Name ......

15. Use of Structure 1 House 2 Huts 3 Sheds 4 Shops 5 Kiosks and Vendors 6 Mobile Vendors 7 Small Eatery/Teas Stall 8 Cattle shed 9 Boundary Walls/Fences

16. Area of the affected structure (in Square Meter) …………………..

17. Type of Structure 1. Temporary 2. Semi-Permanent

18. Age of the structure (Years)…………………….

19. Type of Construction Structure

Appendix 2 21

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

20. Market Value of the Structure (in Tk.)......

21. Number of family members. Total………… Male …… Female……….

22. Is it a woman headed household?

1. Yes 2. No

23. Is it a household owned by physically handicapped? 1. Yes 2. No.

24. Total Monthly income of the family (Tk.)………….

25. Willing to shift

1. Voluntarily 2. Need Resettlement

26. Compensation Option

1. Alternate structure 2. Cash for structure loss

27. Desire Assistance and other help 1. Shifting Allowance 2. Employment Opportunities in Construction work 4. License to resume the current activities 5. Others (specify ...... )

28. Is there alternate site available for relocation? 1. Yes 2. No. 29. If Yes, How far and the name of the place…………………………….

22 Appendix 3

SUMMARY OF CONSULTATIONS AND FGDs

Date of Consultations: 28-06-2010 Number of Consultations: 03 numbers Place of Consultations: Ponchaboti, Ukil Para (Gulshan Cinema hall) and Jollahar Para Number of Participants: 34

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 1 Have you heard about CRDP Most of the participants have heard about the project but they don’t (City Region Development have any specific information about Solid Waste Management. Project)? However many of them are concerned about the waste management of the Market especially whose shop owners who is close to the piles of garbage dumping place. 2 If yes, where from They just have heard from the neighbours and local officials as there has been some discussion on the proposed landfill site etc. 3 General perception about the They are very much concerned about the project. Some of the project and the awareness about participants think that solid waste management is very important the proposed project. because now most of the waste is throwing in a place exact on the main road sides and there is no proper management of waste disposal 4 Do others in this locality support According to the participants, most of the people of this market will be this project? agreed to have an organizing way of waste management. Now all of those waste piles are thrown openly which needs to keep in a covered drum even before it takes to other places, using this place as secondary basis needs to do in proper way. Another few participants even did not like the place where piles of solid waste are thrown. They think this kind of waste should be thrown to an isolated or corner of some area. 5 Any critical issue or concern by The place is congested and the landfill site is proposed to be in the the local people regarding the market area. Hence, adequate engineering solution should be adopted project? by the Pourashava to have a hygienic waste management system including the landfill. 6 Any criteria you would like to Community people requested for bigger landfill site in the future which see considered during project should be away from the city design, construction and operation stage? 7 Employment Potential in the There could be some employment opportunities during the construction project which is of benefit to of the project such as increase in petty shop business and employment village of local labor. 8 Ethnic Minorities /Indigenous None of the Indigenous People or ethnic minority population found in peoples composition (If there the project area. are Indigenous People, please mention about the names of the IP and number of households) 9 Numbers of Industrial Units in No industry in the area, there are only shop and some workshop for the Mohallah/town and fixing cycle and rickshaw surrounding area 10 Is the Area Electrified Yes, the entire area has electrical connection provided by Pauroshava. 11 Source of drinking water Tube-well and pipe water are the main drinking water sources of the community. In the Paurashava area, but most of the participants said they do not drink Pauroshava water source because the quality of water is not good enough for drinking, it smells very bad. So many of the community people installed deep tube-well for their own use. Installation of each tube-well charged Tk50-60,000. Supply water from Pauroshava is available but due to the bad water quality many people do not like to drink water from the source. 12 Loss of residential/commercial There will be no permanent loss of land or structures/buildings due to structures, if any due to the the project except few temporary impacts on hawkers and vendors. project Appendix 3 23

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 13 Loss of community life like any There will be no loss of community life or market place as such except Market Places or community few scattered vendors and squatters who need to be sifted. activities to be affected 14 Poverty Level: Is the village poor Almost 80% people are better off or middle type of income earning or very poor or well off sources. Most of community people are working as businessmen, Shop owner and worker of different industry and workshop, and some are service holders. 15 Education Status: Literate, About 75% of community people are educated but have no higher level illiterate etc of education( very few have), Majority children go to school but could not continue higher education instead after finishing primary or secondary education they go for job. 16 Employment Status: Percentage The employment status is poor among the youth. According to the of employment/ unemployment/ participants, 40% of the people are still unemployed. underemployment 17 Migration Pattern (If any), inward Yes, the area has high tendency of migration. Almost each and every or outward house has some migrated member .They have gone to Middle East, Italy and other countries and their families are depending on the remittance. 18 Are you satisfied with the Most of the people are satisfied service provided by Pauroshava, present infrastructure facility in Especially the Mayor who is very proactive and developed roads and the town and locality other necessary infrastructures. They also suggested for more services such as adequate street light, public toilet for male female both and solid waste management in a planed way. 19 Do you face any problem Yes, water supply from Pauroshava is not good enough for drinking regarding the exiting water purpose, Solid waste management is also creating sufficient trouble for supply/solid waste the community and many of the community peoples said that management/river Pauroshava should initiate more advanced way of managing the solid port/Drainage/Traffic system? waste collection and disposal. 20 If there is any problems related Yes, waste management is very necessary for the community to these services, do you think that any upgradation is necessary? 21 For this upgradation the Yes very much, due to improper solid waste management people of the road/street/path /drainage may market community is suffering. The bad waste management has been get affected- what do you think creating unhygienic situation in the area. Flies and bad smells are about that- is it desirable? spreading all over the area now. They think better waste management will give relief to the people of the community. 22 How can this affect your present This Solid Waste Management project affects community in terms of living or activity their health and environment. People who lives or do works close to the dumping place have difficulties to breath. The garbage dumping space is closer to the participants shop owners and they are suffering more than others. Therefore better waste management will bring good result for then as well as the market community. 23 The project may need shifting of There are few temporary structure which need to be shifted. However, some encroachments and some help in the form of compensation and assistance will be desirable squatters .Would you like to shift and people will be able to shift voluntarily if they get compensation. from here on your own? 24 Where will you like to shift May be some of them have other place some do not and they will during this period? manage somewhere near to existing location where they are working now. 25 If requested to shift, would you It is up to the pourashava. These shops are mostly vendors and like to return here? squatters and illegally occupying the government land, therefore, they would like to shift some other nearby stable place. 26 Is there available alternate place Yes, it is within half kilometer area. for relocation? If yes, how far and the name of the place

24 Appendix 3

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 27 Perceived losses from the Temporary loss of the business and some health issues during the Project- shifting of the present garbage. 28 If losses are perceived, what is Cash Compensation for the vendors and squatters and if possible then the expected compensation you license for reopening their business. The pourashava may issue license would desire to the affected vendors and squatters.

29 Perceived benefits from the Solid waste management in appropriate way (dumping in a covered Project- drum would be preferred ) 30 Do you think that the local Yes, cooperation from the local people will be there during the project residents would like to implementation provided peoples vies are taken in to consideration by participate in this work the pourashava. 31 Do you think that the local Yes, local people should be informed people would like to get regular information regarding this Project? 32 Will it be through informal or Yes, it is very important to have or will have consultation with the formal consultation community before the implementation. Both formal and informal consultation is desired through the help of ward councilor. 33 Will the project cause landslides No or soil erosion in the locality 34 Will the project cause No widespread imbalance by cutting fruit and commercial trees in the locality. 35 Will the project cause health and Only temporary in nature during the shifting of the garbage in the safety issues in the area. landfill and during the construction time. 36 Resettlement and Land This is a Narayangang Pauroshava Land and no need for land acquisition (if foreseen due to acquisition. According to the participants, they don’t have any prior project components especially experience on land acquisition as their land has never been acquired on private land). Has there been before. land acquisition before? If yes, what was the process of land acquisition and compensation package? 37 Protected areas (national park, No protected forest, religiously sensitive sites, historical or archaeological sites), if any 38 Health status, Availability of One hospital is close with insufficient service. The most prevalent Hospitals and over all disease is diarrhea and fever during the rainy season. People are environmental condition. Is there aware about the HIV/AIDS any chronic disease prevalent in this area and are you aware about HIV/AIDS and STP? 39 Will the project siting adversely No change migration pattern of animals that would destroy fields, habitats 40 What other organizations of a Some organizations provides loan to the community. BRAC ASHA and social nature (NGOs/CBOs/ Civil few local credit based organization are working in the locality. Society) active in the area? Name of these organizations 41 Will there be likely involvement Yes of local people in the implementation of the project? Appendix 3 25

Q. No. Issues Raised Participants’ Opinion, Comments and Suggestions 42 Please indicate what kind of Women from better income group do not do job; few educated women economic/ non-economic of the locality work in NGO and Bank. Majority women of the poor activities female members of income group who live in are working in Garments Industry. In the your family are engaged in poor section of the community all women are involved in different income generating activities. All the household activities are done by the women. 43 Does your female member have To some extent they can take some decision, not completely. Decisions any say, in decision making of at family level are taken as sharing basis especially in better off or household matters middle types of family income group. But in the poor section and the family where women work are more involved in household decision making process. 44 How safe do you regard the Women of the community are safe. Many of the women who work mobility of women in outside and go for personal purposes have sufficient safety in the neighborhood / village locality. Women mobility is quite safe in the locality. 45 Do the women of your Yes, Most of the women of the community go freely for any purposes. household can freely go outside Women mobility is very high and they can go out for any purposes at to work, for marketing, or day and night time. accessing hospitals, educational institutes, etc? 46 How often women of your People who have access of water at home they do not need to fetch household go outside the house water from outside. But for the women member of the poor family, they to fetch water in a week? fetch water from outsides. Poor people fetch water from some water points and tube well of the other people twice a day. 47 Do you have a toilet at your Yes , most of the people have toilet, poor people have ring latrine or household? sharing Latrine or community latrine 48 Do you have adequate street Yes, there are some street lights, however, these are not enough lighting during the night? 49 Any Other Issues you may feel Yes, we think proposed for SWM should be very carefully planned to share: without harming the public health or else it should be shifted to some isolated place. Besides, those people who are involved in this waste management work needs proper safeguards as they are currently working very unhygienic way, using their own hands and have no shoes or gloves which is also not good for health. 50 Is this consultation useful? Yes, very useful, it gives us freedom to speak our opinion on the Comments coming project and also we think government will conceder the situation and take active steps on that. . CBO = community-based organization, CRDP = City Region Development Project, NGO = nongovernment organization, STP = sewage treatment plant, SWM = solid waste management.

City Region Development Project (RRP BAN 39298)

Resettlement Plan

Document Stage: Draft for Consultation Project Number: 39298 July 2010

BAN: City Region Development Project—Shakhari Bazaar Urban Renewal Subproject

Prepared By: Local Government Engineering Department (LGED), Government of Bangladesh

The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

ABBREVIATIONS

ADB — Asian Development Bank ARIPO — Acquisition and Requisition of Immovable Property Ordinance CRDP — City Road Development Project DCC — Dhaka City Corporation GRC — Grievance Redress Committee GRM — Grievance Redress Mechanism IRS — International Resettlement Specialist LGED — Local Government Engineering Department MDSC — Management, Design and Supervision Consultant PMCU — Project Management Coordination Unit PIU — Project Implementation Unit ROW — right of way RSS — Resettlement Support Staff SPS — Safeguard Policy Statement

TABLE OF CONTENTS

EXECUTIVE SUMMARY i

I. PROJECT DESCRIPTION 1 A. Overview 1 B. Subproject Description 1

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 4

III. SOCIOECONOMIC INFORMATION AND PROFILE 4

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 8 A. Public Consultation 8 B. Information Disclosure 8 C. Continued Consultation and Participation 9

V. GRIEVANCE REDRESS MECHANISMS 10

VI. LEGAL FRAMEWORK 12

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS 12 A. Eligibility 12 B. Entitlements 12 C. Assessment of Compensation Unit Values 14

VIII. INCOME RESTORATION AND REHABILITATION 14 A. Basic Provision for Relocation 14 B. Income and Livelihood Rehabilitation 15

IX. RESETTLEMENT BUDGET AND FINANCING PLAN 16

X. INSTITUTIONAL ARRANGEMENTS 17 A. Project Management Coordination Unit 17 B. Project Implementation Unit 17 C. Management, Design and Supervision Consultants 17

XI. IMPLEMENTATION SCHEDULE 19

XII. MONITORING AND REPORTING 21

Appendixes 1. Details on Public Consultation (FGDs) 23 2. Future Consultation and Disclosure Roles and Responsibilities 29 5. Monitoring Indicators and Sample for Status Report 30

EXECUTIVE SUMMARY

1. The City Region Development Project (CRDP, the Project) will be financed by the Asian Development Bank (ADB) and is being formulated as a project loan using the sector approach to be implemented over a six-year period (January 2011 to December 2016). This document is a draft Resettlement Plan prepared for the Shakhari Bazaar urban renewal Subproject (the subproject). It is based on a feasibility level study and preliminary engineering design and will be updated at the final detailed engineering stage. The Resettlement Plan is prepared in accordance with the ADB Safeguard Policy Statement, 2009 (SPS), Government of Bangladesh’s (the Government) policy, i.e., the Acquisition and Requisition of Immovable Property Ordinance, 1982 (ARIPO), and the Resettlement Framework adopted for the Project. It is classified as Category B according to ADB’s SPS as minimal land acquisition and resettlement is required. The scope of this Resettlement Plan is based on improvements to the public realm (e.g., utility relocation, paving, and traffic management) and restoration improvements to two identified buildings (Nos. 53 and 70) taken up as pilot buildings.

2. Summary of Resettlement Impacts. There is no land acquisition envisaged. The restoration of two pilot buildings will result in temporary impacts to building tenants through short-term relocation. There will be a total of 18 households temporarily relocated by the subproject. Of affected households, 13 are considered to be residential owners followed by 2 commercial owners, 2 residential tenants and 1 commercial tenant. Each will be ensured a guaranteed return to their original residence after works are completed through agreements between the owners/tenants and the Dhaka City Corporation (DCC). There are a total 15 vulnerable households they earn incomes below the poverty line. Improvements to the public realm will cause minimal temporary disturbance to local shops and street vendors during construction. These are to be mitigated through good construction practices (e.g., night works, maintaining access, etc.) to minimize disturbance. Entitlements for all impacts are outlined in the Resettlement Plan.

3. Public Consultations. Consultations were carried out during Resettlement Plan preparation and will continue throughout the subproject cycle. A grievance redress mechanism will be made available as explained in this Resettlement Plan.

4. Implementation Arrangements. The subproject will be managed and implemented through a Project Implementation Unit (PIU) based in Dhaka City Corporation office with the overall support and guidance of the Project Management Coordination Unit (PMCU) based at Local Government Engineering Department (LGED) Headquarters in Dhaka. The detailed design, preparation, and implementation of the capital investments will be supported by: (i) consultancy support (both international and national); and (ii) technical support from LGED. The PIU will implement the Resettlement Plan with support from the PMCU and resettlement specialists engaged by LGED. The PIU will provide adequate and appropriate relocation options (temporary), shifting allowance, cash compensation at full replacement cost, and adequate compensation for partially damaged structures as per the entitlement matrix within this Resettlement Plan. Income restoration assistance to the affected persons includes both short and medium term strategies. The Government will provide all funds for resettlement in a timely manner.

5. Resettlement Plan Implementation and Monitoring. All temporary relocation, compensation, and entitlements will be paid prior to displacement however, ongoing income rehabilitation activities where relevant, will continue after construction begins. Written confirmation of full relocation and compensation to displaced persons must be made to ADB prior to displacement in sections ready for construction, including the two buildings where works will occur. The estimated total period of the implementation of the Resettlement Plan is 13

ii months. Monthly monitoring reports will be submitted by PIU to PMCU. PMCU will consolidate monthly reports into semi-annual monitoring reports or as part of the regular project reporting and will submit to ADB.

I. PROJECT DESCRIPTION

A. Overview

1. The City Region Development Project (CRDP, the Project) emphasizes economic growth in Dhaka and Khulna city regions of Bangladesh through (i) creation of an enabling environment towards improved governance and capacity building of the local governments, and (ii) prioritized investments in infrastructure sectors in the two regions. The objectives of CRDP are (i) to improve the regional economic and social context through long-term development plans and investment programs, set within an institutional and regulatory context that will ensure implementation and review; (ii) to improve the capacity and mandate of local government to govern and to invest in improved economic activity at local level; (iii) to improve the economic context for sustainable commercial and industrial growth; and (iv) to improve the economic and social needs of the urban population, as an inclusive aspect of the CRDP. The subprojects are largely built around ‘integrated area planning’ principles which enhance economic activity in the regional context and provide opportunities for investment.

2. This is a Resettlement Plan prepared for the Shakhari Bazaar Urban Renewal Subproject which is in accordance with the ADB Safeguard Policy Statement, 2009 (SPS), Government of Bangladesh’s (the Government) policy, namely the Acquisition and Requisition of Immovable Property Ordinance 1982 (ARIPO) and the Resettlement Framework1 adopted for the CRDP. The scope of this Resettlement Plan is based on improvements to the public realm (e.g., utility relocation, paving, and traffic management) and restoration improvements to two identified buildings (Nos. 53 and 70) taken up as pilot buildings.

B. Subproject Description

3. Shakhari Bazaar comprises a street over 1,000 feet (300 meters) in length, lined by shop houses, many of which are still occupied by traditional craft workshops. The traditional buildings are typically two or three stories tall, mostly around 100 to 200 years old, with a few even older. Many of the ground floors are older, between 200 to 300 years and were built in the Mughal period. The inner parts of the ground and upper floors are mainly residential, although in some buildings the rear parts of the ground floors are also used for craftwork. Typically, the traditional houses are long and narrow and may contain courtyards opening onto open top-floors. The original Mughal architecture is often embellished by surface decorations and carvings. There are over 100 buildings (covering 142 building lots), including several vacant lots where buildings have been demolished. Lots are typically long and narrow, with widths mainly between three and four meters. Storey heights vary between two and six stories, but with most between three and four stories (72%). Some 79% of the buildings were built before 1900 and very few buildings have been completed in recent years. Over time the traditional Mughal architecture was influenced by colonial architecture, usually extensions built in British-style colonial style architecture and construction, plus other European influences, all of which add to the unique character of the area.

4. Unfortunately the environment has deteriorated dramatically in recent years, and it is now blighted by a high degree of building obsolescence (some structurally unsound) and

1 As per the ADB’s Safeguards Requirement-4 (SR-4) of the SPS-2009, the sector approach requires preparation of Resettlement Framework to guide subproject selection, screening and categorization, social and resettlement assessment, and preparation and implementation of Resettlement Plans of subprojects and to facilitate compliance with the requirements specified in Safeguard Requirements 1–3. The Resettlement Framework is prepared in accordance with the Government and ADB policy related to land acquisition and resettlement.

2 disruption in the public realm. The majority of the remaining buildings of architectural and historic interest are at risk through neglect. In spite of this Shakhari Bazaar (and the adjoining streets) remains remarkably vibrant. Shakhari Bazaar is not yet a major tourist attraction but within the context of current tourist numbers to Bangladesh, the area regularly attracts visitors. The area is identified as an attraction in many of the international tourism publications about Bangladesh. Therefore, the conservation and restoration of Shakhari Bazaar would enhance visitor potential, as borne out by overseas experience.

5. Key Issues and Project Need. From discussions and a site visit with representatives of DCC and the Urban Study Group, the following are key issues confronting Shakhari Bazaar:

(i) The loss of buildings of architectural and historic importance to redevelopment, which is incompatible in nature, scale, detailing and use of materials with the original vernacular architecture and the public realm in general. In this regard the desire of extended families to remain in Shakhari Bazaar has increased the pressure for buildings of six stories more (often illegal), which is out of keeping with the traditional two- to three-storey form of the original buildings; (ii) A lack of building maintenance by both the Government and the private sector, leading to buildings of architectural and historic significance being in a poor state of repair, and which to varying degrees may be structurally unsound. To this extent there have been previous surveys of structural condition, the most recent of which identified some 12 buildings in Shakhari Bazaar as structurally unsound; (iii) Buildings of architectural and historic significance where the original exteriors, internal layout and decoration have been badly affected by poorly designed and constructed extensions; (iv) Complex ownership situations2 acting as a constraint to public and private investment in revitalising the area; (v) The lack of basic services, including public water supply and effective sewerage, in many of the properties. It is understood this is at least partly due to a lack of clarity regarding ownership issues; (vi) The potentially attractive appearance of the public realm (street) is damaged by a multitude of power cables and telecommunications wires attached to the buildings, solid waste dumped at the street edge and unattractive street surfacing; and (vii) The vitality and potential attraction of a predominantly pedestrian environment is damaged by the excessive penetration by rickshaws and motorcycles, the majority of which do not appear to have an origin or destination in Shakhari Bazaar.

6. Vision and Objectives. The vision of the Shakhari Bazaar urban renewal subproject is to ensure its long-term sustainability, its culture and its history through a range of actions to upgrade its buildings and spaces, optimizing the potential for the partnership(s) between

2 The ownership situation in Shakhari Bazaar is complex, and there are three main types: (i) Vested Properties – these are properties in the ownership of absentee landlords, whilst their ongoing administration is exercised by the Government, which has let the buildings by various leasehold and rental formulae. There may be several leases and tenancies within each building: it is understood that the vested properties make up around 60% of the buildings in Shakhari Bazaar. It is also understood that the Government is now reviewing the status of the vested properties, with the possibility of returning them to the original owners; (ii) Endowed Properties – these properties are properties given over by Hindu religious interests for individual/family occupancy; and (iii) Private Ownership – private ownership properties are typically occupied by various family interests, such that they may be divided up amongst an extended family and ownership may extend across more than one building. 3

Government, the community and the private sector. To achieve this vision the following four objectives are proposed to ensure:

(i) The retention of the area’s historically-important buildings and to improve the appearance of adjacent buildings (which do not blend well with the nature and scale of traditional architectural forms); (ii) Improvements to the visual appearance and pedestrian environment of the street/public realm for the enjoyment of visitors and the local community; (iii) The needs and aspirations of the community affected by the subproject should be incorporated into the proposed revitalisation of Shakhari Bazaar; and (iv) That the economic value of Shakhari Bazaar should be optimized as an attractive environment for private sector investment in the area’s conservation.

7. The following are the proposed components of the Shakhari Bazaar subproject:

8. Component 1- Relocation of utilities. This activity will include opening the surface of the public realm in Shakhari Bazaar for the placement of new utilities services and (where required) the removal of the existing utilities services. The work will include the provision of connections to the adjoining properties. It will also include the underground re-location within impermeable conduits of all the overhead power and telecommunication equipment currently situated in the public realm.

9. Component 2 – Resurfacing the street and parking area immediately east of Shakhari Bazaar. On completing the reconstruction and re-location of the utilities services the street will need to be re-surfaced in materials appropriate to the environment of the Heritage Area, along with any additional hard and soft street furniture and lighting. Here the parking area immediately to the east of Shakhari Bazaar lends itself to the use of soft landscaping to frame the entrance to the Heritage Area. The new surfacing should be to standards capable of accommodating emergency vehicles.

10. Component 3 – Traffic Management. Access controls on motorized vehicles and rickshaws at specified periods of the day would be enforced by adjustable traffic barriers and blocks, to be installed during the re-surfacing activity.

11. Component 4 - Restoration of buildings with heritage status. Two buildings (nos. 53 and 70) are identified for conservation and restoration as part of the first phase, as a sample demonstration project. Restoration works will vary in accordance with the conditions of those buildings with Heritage Status and through agreement with owners and occupiers. In most cases the internal layouts will remain intact and the restoration works will respect this. However, where the structural condition is particularly bad, the building frontage will be restored but the interiors will be re-built and alternative internal layouts can be considered. Restoration may include (i) structural improvements; (ii) provision of basic amenities such as toilets; (iii) restoration of significant features (such internal courtyards, building façades and detailing); and (iv) other cosmetic improvements, such as new internal plastering.

12. Component 5 - Upgrading the design and provision of utilities to other buildings. For buildings which do not have heritage status the emphasis will be on providing technical guidance and incentives to secure (i) improvements to building façades such that they are more in keeping with the traditional architecture of Shakhari Bazaar; and (ii) provision of basic amenities, such as toilets. The proposed Design Guidelines and Restoration Advice (see above)

4 will serve as a context for action in the restoration of all buildings in Shakhari Bazaar, and in particular for action to improve and/or redevelop private property.

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

13. There is no land acquisition envisaged for interventions proposed in the first phase as the improvements to the public realm are within the available right of way (ROW). The restoration of two pilot buildings (Nos 53 and 70) will temporarily relocate the occupants of these building. A total of 18 households will be temporarily relocated. None of these buildings will be permanently affected or displaced.

14. Ownership. Out of the 18 households 15 of them are owners and 3 households are tenant. Additionally, one private temple will be restored.

III. SOCIOECONOMIC INFORMATION AND PROFILE

15. Structured census survey questionnaires (Appendix 2) were used to collect detailed information on the impact to all 18 households in the subproject area who are considered temporarily displaced. The survey was conducted in July 2010.3 Some of the important issues covered during the surveys are (i) type of ownership, (ii) duration of stay, (iii) legal status and ownership, (iv) usage pattern of the buildings, (v) number of tenants, (vi) number of family members, and (vii) their socio-economic details.

16. The two pilot buildings (House Nos. 70 and 53) have 15 owners and 3 tenants. Details are given in Table 1.

Table1: Type of Impacts Number of Number of Total Number Building Households Households of Number (Owners) (Tenants) Households House No. 70 8 1 9 House No. 53 7 2 9 Total 15 3 18 Source: Census Survey, July 2010.

17. Most of the households are residential owners. There are 13 households considered to be residential owners followed by two commercial owners, two residential tenants and one commercial tenant. Additionally, there will be a small religious structure (temple) which will also be affected. Details are given in Table 2.

3 The survey team was trained by the international resettlement specialist consultant and the survey was closely monitored on a regular basis. The census survey included various aspects including (i) assessment of land including quantity and typology; (ii) Inventory of physical assets; (iii) potential income loss; (iv) impact on trees; (v) household characteristics, including social, economic and demographic profile; and (vi) temporary impacts on the hawkers’ business activities. 5

Table 2: Uses of the Structures Building Residential Commercial Residential Commercial Total Religious Number Households Households Tenants Tenants Households (Temple) House # 70 6 2 0 19 0 House # 53 7 0 2 09 1 Total 13 2 2 1 18 1 Source: Census Survey, July 2010.

18. Most of the owners are long-time residents of these buildings. It is assessed that 11 households (61.11%) have been living in the buildings for almost 50 years. Only 2 households have been reported to be present for less than 10 years. Details are given in Table 3.

Table 3: Duration of Stay Duration Number of Percentage Sl No Households 1 Less than 10 Years 2 11.11 2 11 Years to 20 Years 1 5.56 3 21 Years to 30 Years 1 5.56 4 31 Years to 40 Years 2 11.11 5 41 Years to 50 Years 1 5.56 6 More than 50 Years 11 61.11 Total 18 100.00 Source: Census Survey, July 2010.

19. The maximum number of rooms per household is three and the minimum is one. The survey revealed that 10 (55.56%) households have only one room each and 6 households have been found to have two rooms set and only two households are staying in a three-room set. Details are given in Table 4.

Table 4: Availability of Rooms per Household Number of Sl No Number of Rooms Percentage Households 1 One 10 55.56 2 Two 6 33.33 3 Three 2 11.11 Total 18 100.00 Source: Census Survey, July 2010.

20. The living areas are considered small. There are six households who reported living in less than 5 sq.m. of area. Eight households are living within 5 to 15 sq.m. areas, three households are 15 to 25 sq.m. of area, and only one household is having 25 to 35 sq.m. of area. Details are given in Table 5.

6

Table 5: Area of the Structure Area/Space per Number of Percentage Sl No household (Square Households meters) 1 Less than 5 6 33.33 2 5.01 to 15.00 8 44.44 3 15.01 to 25.00 3 16.67 4 25.01 to 35.00 1 5.56 Total 18 100.00 Source: Census Survey, July 2010.

21. The main source of income for most of the households (total 11) is service related. Six households have reported that business is their main source of income. Only one household has been reported to have daily wage as the main source of income. Details are given in Table 6.

Table 6: Main Source of Income Main Source of Number of Percentage Sl No Income Households 1 Business 6 33.33 2 Service Holder 11 61.11 3 Daily Wage 1 5.56 Total 18 100 Source: Census Survey, July-2010.

22. The total numbers of vulnerable displaced households are 15 as they fall below the poverty line.4

23. Gender. During disbursement of assistance and compensation, priority will be given to female headed households.

24. Summary Socioeconomic Profile. There will be a total of 18 households who will be temporarily displaced by the sub project. The total numbers of vulnerable households are 15 which are below poverty line. There are a total of 14 residential owners, 2 commercial owners and 1 commercial tenants residing in these two pilot buildings. The summary socio-economic details are given in Table 7.

4 Below Poverty line has been calculated on the basis of general formula which is $1 per day per person. The average family size in the subproject area is 5.3 and the $1= Tk72. Therefore, the threshold for poverty line has been considered as Tk11,475 incomes per month per household.

Table 7: Socio-Economic Details of the Households HH size Main Vulnerable Monthly S.N Name of the Owner Type of Ownership Occupation/Inco Household Income (Tk) Total Male Female me Source s

1 Mr. Joy Ghosh Residential Owner 4 2 2 Service Holder 6,000 BPL 2 Mr. Kalachan Dutta Residential Owner 4 3 1 Service Holder 5,000 BPL 3 Mr. Nila Rani Dutta Residential Owner 6 5 1 Service Holder 4,000 BPL 4 Mr.Dilip Sarkar Commercial Owner 2 1 1 Business 5,000 BPL 5 Mr. Kishor Kumar Bashu Residential Owner 5 3 2 Business 50,000 – 6 Mr. Bina Rani Dash Residential Owner 5 3 2 Service Holder 3,500 BPL 7 Mr. Amorendro Bashu Roy Chowdhury Residential Owner 3 2 1 Service Holder 6,000 BPL 8 Mr. Ujjal Kumar Dutta Commercial Owner 3 2 1 Service Holder 2,500 BPL 9 Mr. Ronjit Dash Commercial Tenant 5 3 2 Service Holder 5,000 BPL 10 Mr. Khokon Dhar Residential Owner 3 2 1 Business 3,000 BPL 11 Mr. Mala Mondol Residential Tenant 3 2 1 Service Holder 2,000 BPL 12 Mr. Maloti Residential Owner 5 4 1 Business 6,000 BPL 13 Mr. Ananda Mohisur Residential Owner 10 6 4 Service Holder 12,000 – 14 Mr. Ashtami Rani Dhar Residential Owner 3 1 2 Daily Wage 2,000 BPL 15 Mr. Jibon Residential Tenant 1 1 0 Service Holder 6,000 BPL 16 Mr. Ranjit Sur Residential Owner 4 3 1 Business 30,000 – 17 Mr. Polash Dhar Residential Owner 4 1 3 Service Holder 3,000 BPL 18 Mr. Uma Sangkar Residential Owner 3 1 2 Business 10,000 BPL Total Displaced Persons 73 45 28 Total Vulnerable Households=15

7

8

IV. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

A. Public Consultation

25. During subproject preparation, consultations were held with the official representatives of DCC, apart from the communities in the subproject area. The issues covered during these consultations included selection of subprojects and identification of key issues including addressing the current gaps in provision of basic services and improvement of urban environment conditions in the Shakhari Bazaar area. These consultations (Table 8) provide an understanding of the needs and concerns of the project communities and the relevant stakeholders. Additionally, focus group discussions were also conducted with the local community especially with the displaced persons and the summary of these consultations is given in Appendix 3.

Table 8: Summary of Consultations Incorporation into Number of Issues S.No. Place Date Participants Resettlement Plan and participants discussed Project design A 12th 15 Residents of Understanding June Shakhari of the heritage A detailed design of the 2010 Bazaar, status of the project area shall be Members of area, profile of prepared, in consultation the Shakhari the with the communities, and Bazaar communities shall include plans for Panchayat inhabiting the infrastructure improvement. committee, Shakhari shopkeepers, Bazaar, All utilities and services and Access to currently within the ROW residents. infrastructure shall be accommodated services, key within the ducts on the road issues surface, to improve the pertaining to visual appeal of the area environment – Support to DCC in framing including lack up the guidelines for heritage of sanitation management facilities, waste collection Enforcement mechanisms by mechanisms the DCC to avoid any and flooding adverse impacts including during rains unplanned development in Willingness of heritage areas and communities to protection of the ROW participate in restoration of the area, including buildings conservation and the way to temporarily shift to the other location during the restoration period

9

Incorporation into Number of Issues S.No. Place Date Participants Resettlement Plan and participants discussed Project design B Banani, 1s 3 Executive Overview of the Written agreements DCC July engineer – Safeguards between residents and office 2010 DCC, Town policies DCC will ensure that all planner DCC, Environmental owners and tenants Zonal impacts due to residing in the buildings at Executive project, the time of the cut-off date officer (DCC) - including are entitled to return to their Banani selection of original location after the buildings for subproject or sections of restoration, the buildings (deemed as enforcement of safe by contractors, DCC, development and certified engineers) are controls in completed. Adequate heritage areas. compensation for temporary relocation such as shifting allowances, business loss allowances, vulnerable households allowances and rental allowances etc. DCC = Dhaka City Corporation, ROW = right of way.

B. Information Disclosure

26. Project information will be continually disseminated through disclosure of resettlement planning documents. Resettlement information leaflets containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Bangla) and the same will be distributed to displaced persons. The PIU the Resettlement Support staff (RSS) will keep the displaced persons informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. The information will also be made available at a convenient place especially, the market place which will be easily accessible to the displaced persons. The summary of the Resettlement Plan and the entitlement matrix will be translated into the local language; disclosed to the displaced persons; and made available at PIU, local offices and libraries (or other pubic places, and at the LGED offices. A copy of the Resettlement Plan will be disclosed on the LGED and ADB website.

C. Continued Consultation and Participation

27. For continued consultations, the following steps are to be taken:

(i) The PMCU and the PIU will organize public meetings and will apprise the communities about the progress in the implementation of resettlement, social and environmental activities. (ii) There will be a Grievance Redress Committees (GRC). The displaced persons will be associated with such committee along with their representatives. (iii) PMCU and PIU will organize public meetings to inform the community about the compensation and assistance to be paid. Regular update of the progress of the resettlement component of the project will be placed for public display at the PCMU and PIU offices.

10

(iv) All monitoring and evaluation reports of the resettlement components of the project will be disclosed in the same manner as that of the Resettlement Plan. (v) Key features of the entitlements will be displayed along the project corridor. (vi) The PMCU and PIU will conduct information dissemination sessions at major intersections and solicit the help of the local community leaders to encourage the participation of the displaced persons in Resettlement Plan implementation. (vii) Attempts will be made to ensure that vulnerable groups understand the process and to take their specific needs into account.

28. The details on consultation process and disclosure at various phases of project development including the responsible agency are described in Appendix 5.

V. GRIEVANCE REDRESS MECHANISMS

29. A grievance redress mechanism (GRM) shall be set up in the Dhaka City Corporation PIU office to register grievances of the people regarding technical, social and environmental aspects. The process will designed to be transparent, gender responsive, culturally appropriate and commensurate to the risks and adverse impacts of the project, as well as readily accessible to all segments of the affected people. The project GRM will not supersede any legal government grievance procedures. Affected people are to be informed about the mechanism through media and public outlets. This participatory process shall ensure that all views of the people are adequately reviewed and suitably incorporated in the design and implementation process. The GRM will be implemented in three levels.

30. The first level and most accessible and immediate venue for the fastest resolve of grievances is the PIU, chiefly through the resettlement safeguards officer and Project Manager, with assistance from the Resettlement Specialist(s) of the Management Design Supervision Consultant (MDSC). The contact phone number will be posted in the project areas. Grievances will be resolved through continuous interactions with affected persons and the PIU will answer queries and resolve grievances regarding various issues including Environmental Management Plan implementation, land acquisition, structures acquisition, livelihood impacts, entitlements, and assistance. Corrective measures will be undertaken at the field-level itself within seven days. All grievances will be documented with full information of the person and issue.

31. Should the grievance remain unresolved, the PIU's Project Manager, will activate the second level of the GRM by referring the issue (with written documentation) to the local GRC of the City Corporation, who will, based on review of the grievances, address them in consultation with the Safeguards Officer of the PIU and PMCU, and affected persons. A hearing will be called, if necessary, where the affected person can present his/her concern/issues. The process will promote conflict resolution through mediation. The local GRC will consist of the following persons: (i) Chief Executive Officer of the City Corporation (GRC Chair); (ii) representative of the mayor of the City Corporation; (iii) representative of the affected persons; (iv) official of the land registry department; (v) official of the Department of Environment (DOE) divisional office; (vi) town planner of the City Corporation; and (vii) Environmental/Social safeguards Officer of the PIU. The local GRC shall meet twice a month, unless the Project Director of the PIU informs that there are no grievances to address, or they shall meet as needed as per the severity of the grievance. The local GRC will suggest corrective measures at the field level and assign responsibilities for implementing its decisions.

32. The functions of the local GRC are as follows: (i) provide support to affected persons on problems arising from land acquisition (temporary or permanent); asset acquisition; and 11 eligibility for entitlements, compensation and assistance; (ii) record grievances of affected persons, categorize and prioritize them and provide solutions within a month; and (iii) report to the aggrieved parties about developments regarding their grievances and decisions of the GRC.

33. Should the grievance still remain unresolved, the PIU Project Manager, will activate the third level of the GRM by informing the PMCU Project Director who will, based on review of the local GRC minutes and consultation with the PIU Project Manager, activate the PMCU level GRC. This committee shall comprise the following representatives: (i) Project Director PMCU; (ii) Environmental/Resettlement Safeguards Officer of the PMCU; (iii) representative from Land Ministry; (iv) representative from DOE; (v) Representative of the affected persons; and (vi) Environmental/Social Safeguards officer of the PIU.

34. The GRC at the PMCU level shall meet based on the receipt of grievances, and the meeting shall be convened within 7 days of receipt of the grievance by the PMCU, and grievances redressed with 15 days. The Environmental/Resettlement Safeguards Officer of the PMCU will be responsible for processing and placing all papers before the PMCU GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out.

35. In the event that a grievance is not addressed by the PIU, local GRC, or the PMCU GRC, the affected person can seek legal redress of the grievance in the appropriate Courts (fourth level of GRM). Figure 1 illustrates the GRM.

Figure 1: Grievance Redress Mechanism (GRM)

GRC = Grievance Redress Committee, DSMC = Design Supervision Management Consultant, PMCU = Project Management Coordination Unit, PIU = Project Implementation Unit.

12

VI. LEGAL FRAMEWORK

36. This Resettlement Plan is prepared based on all applicable legal and policy frameworks of the Government (i.e., the ARIPO) and ADB's SPS. A summary of applicable acts and policies is presented provided in the Project's Resettlement Framework.

37. The Government's policy through ARIPO does not cover project-affected persons without titles or ownership record, such as informal settler/squatters, occupiers, and informal tenants and lease-holders (without document) and does not ensure replacement value of the property acquired. The ARIPO has no provision of resettlement assistance for restoration of livelihoods of affected persons except for the legal compensation. Gaps between national law and ADB policy are identified and bridging measures are included in the Entitlement Matrix for the project, described below. ADB will not finance the project if it does not comply with its SPS nor will it finance the project if it does not comply with its host country's social and environmental laws. Where discrepancy between the ADB and Government policies exist, the ADB policy will prevail. Moreover, the SPS applies to all ADB-financed and/or ADB-administered sovereign projects, and their components regardless of the source of financing, including investment projects funded by a loan; and/or a grant; and/or other means.

VII. ENTITLEMENTS, ASSISTANCE, AND BENEFITS

A. Eligibility

38. All displaced persons who are identified in the project-impacted areas on the cut-off date5 will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their pre-project living standards, income-earning capacity and production levels. The project will recognize both licensed and non-licensed vendors. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the detailed census during the detailed design. Displaced persons who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice (60 days), requested to vacate premises and dismantle affected structures prior to project implementation.

B. Entitlements

39. The entitlement matrix in Table 9 summarizes the main types of losses and the corresponding entitlements in accordance with the Government and ADB policies.

5 The cut-off date for title holders is based according to the formal notification, and for non-titleholders the date of the census survey during the detailed design. Those who encroach into the subproject area after the cut-off date will not be entitled to compensation or any other assistance. The PIU will take video and photo documentation to ensure entitled persons on the cut-off date.

Table 9: Entitlement Matrix Sl Type of Loss Applicatio Entitled Entitlement Implementation Issues Responsible No n Person Agency

1. Temporary loss of Temporary Owner(s) with  60 days advance notice. All the buildings will be identified PIU/PMCU access loss of legal title,  Provision of temporary access and in advance and a relocation Contractor to access to tenant(s), relocation. strategy will be made in advance restore access land, leaseholder(s),  Restoration/enhancement of affected in consultation with the displaced structure, sharecropper(s land, structure, utilities, common persons. The PIU will help find utilities, ), property resource. suitable alternative locations for common encroacher(s), displaced persons and ensure all property squatter(s) persons have an equally similar resource location (with equal or better quality and access to services including water, sanitation, electricity, transport, education, etc.) to reside prior to physical displacement. DCC will have a signed agreement that all the displaced persons guaranteeing their return back to their original place after the restoration. 2. Temporary loss of Temporary Street  60 days advance notice. DCC through the PIU will identify PIU/PMCU livelihood loss of Hawkers,  Provision of temporary access where the nature of each business of the livelihood/s mobile vendors possible. displaced persons and ource of  Provision of alternative sites for accordingly all the displaced income continued economic activity where persons losing income/livelihood possible. in temporarily will be paid in the  Where provision of alternative sites is form of compensation for the not feasible, a one time assistance for entire duration of the business lost income for period of disruption (if loss. DCC will attempt to find less than three months) or lump sum for alternate site for these people who three months lost income (at will be losing their business in a replacement cost) or minimum wage temporary basis. DCC will ensure rates (whichever is higher). that the displaced persons restart  Compensation for agricultural losses. their business activities after the  Restoration of affected land, structure, restoration activities are done utilities, common property resource. 3. Impacts on All impacts Vulnerable  Land-for-land option will be a  Vulnerable households to be  PIU/PMCU vulnerable displaced guaranteed option for vulnerable identified during census surveys displaced persons persons displaced persons if available. If not conducted as part of the available, assistance in finding new Resettlement Plan land.  Additional allowance equivalent to Tk10,000/- for loss of land or structure.  Preference in project employment. 4. Any other loss not Unanticipated involuntary impacts shall be  PIU/PMCU identified documented and mitigated based on the principles provided in this Resettlement Framework and with compliance with the Government’s and ADB’s policy. ADB = Asian Development Bank, DCC = Dhaka City Corporation, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. 13

14

C. Assessment of Compensation Unit Values

40. Shifting Allowance. Shifting allowances have been considered to be Tk10,000 per household to help the displaced person shift all their personal belongings. The rental allowances have been considered to be Rs.5,000/- per household for a period of one year which becomes Tk60,000 per household.

41. Business or Sources of Income. The PIU will conduct a detailed census survey which is to include actual monthly income of the displaced persons followed by a verification of the income data based on the tax payment (for titled business owners). In the absence of the authentic income proof, the unit price will be collected from the displaced person during the survey. See income restoration and rehabilitation measures below.

42. Temporary Source of Income. The compensation for temporary impacts will be decided based on the average daily income which will be derived from the census survey. The unit cost for temporary loss of income for mobile vendors has been derived based on the minimum wage for the entire period of disruption. The average income in the project area as collected during the census is approximately 9,000 and therefore, the unit cost for one time assistance equivalent to one year loss of income is Tk108,000 per household.

VIII. INCOME RESTORATION AND REHABILITATION

A. Basic Provision for Relocation

43. Relocation in this sub project will be of temporary in nature. None of the households will be permanently displaced and will be guaranteed return through written agreement between themselves and the DCC.6 The agreements are to be legally enforceable and agreeable to the displaced persons. All agreements are to be confirmed through an independent third party.7 The objective of the subproject is to restore the heritage building and to bring back its original owners and occupants after the restoration process is done. Therefore, resettlement is characterized as a temporary shifting of affected households until the buildings are declared safe and ready for residence. Buildings were agreed to be worked on one at a time to minimize impacts. The Implementing Agency, DCC in this case, will provide adequate and appropriate replacement structures and cash compensation in the form of rental allowances for the entire period of relocation. The DCC will facilitate displaced persons in finding alternate residences agreeable to the displaced persons. All displaced persons are to be relocated and all entitlements provided before displacement occurs. The entitlement also includes shifting allowances. DCC will ensure that all temporary displaced persons are settled in a new place and DCC will be responsible to bring them back to their original place (through signed agreements) of stay once the restoration activities are complete. The implementing agency will compensate non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land, at full replacement cost. The entitlements to the non- titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date.

6 The PIU will help find suitable alternative locations for displaced persons and ensure all persons have an equally similar location (with equal or better quality and access to services including water, sanitation, electricity, transport, education, etc.) to reside prior to physical displacement. The PIU will provide adequate and appropriate replacement structures, cash compensation at full replacement cost, adequate compensation for partially damaged structures, and relocation assistance, as per applicable according to the entitlement matrix. 7 Draft agreements should be sent to ADB for review.

15

44. To help affected persons receive entitlements and relocating themselves, a relocation strategy will be adopted in the subproject including (i) all compensation will be paid and other resettlement entitlements will be before physical displacement; (ii) at least 60 days advance notice will be given; (iii) the PIU and Resettlement Support Staff will assist displaced persons during verification of assets and will provide necessary counseling on payment of compensation and assistance; (iv) in close consultation with the displaced persons, the PIU Resettlement Support Staff will fix the shifting dates agreed with the displaced persons in writing and the arrangements desired by the displaced persons with respect to their entitlements; and (v) in case of self relocation, the PIU will assist the displaced persons in finding alternative site within the area if so desired by the displaced persons.

B. Income and Livelihood Rehabilitation

45. Income restoration assistance to the displaced persons includes both short and medium term strategies. Short term income restoration strategies are for immediate assistance during relocation and include the following:

(i) Compensation for structure paid in full before displacement occurs; (ii) Assistance in finding alternate location for continuation of livelihood/living arrangements; (iii) Where provision of alternative sites is not feasible (for temporary impacts), compensation of lost income for period of disruption (if less than three months) or lump sum for three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (iv) Shifting allowance for reestablishing business elsewhere based on actual cost of moving/unloading; (v) 60 days’ advance notice to shift business; (vi) One time assistance for lost income based on three months lost income (at replacement cost) or minimum wage rates (whichever is higher); (vii) Consideration for project employment; (viii) For vulnerable households, additional subsistence allowance equivalent to Tk10,000/household for restoring or enhancing their livelihood. Vulnerable households will be prioritized in any project employment; (ix) Provision of temporary access where possible to continue business; and (x) Restoration of affected land, structure, utilities, common property resource for continuation of business after construction is completed.

46. Medium-term income restoration activities will include skill development training based on need. The PIU will identify suitable local training institutes and pay fees directly to the training institution and provide the names of entitled person(s).

47. Where necessary, training may include (i) capacity building, enterprise training, and facilitating economic activities to landowners; and (ii) training for self employment to agricultural laborers. Training for self-employment and skill development which may include but not limited to (i) plumbing; (ii) electrical; (iii) automobile repair; and (iv) electronic repair and service, etc. Training will be imparted to any willing displaced person losing income or livelihood.

48. During the construction stage the displaced persons, especially vulnerable displaced persons, will be given preference over others in being engaged in project activities suitable to their skills. In order to make the displaced persons employable, the PIU will identify the required

16 skills for the construction activities prior to the commencement of the construction and provide the required training to the displaced persons.

IX. RESETTLEMENT BUDGET AND FINANCING PLAN

49. The resettlement cost estimate for the Shakhari Bazaar subproject (Table 10) includes eligible compensation, resettlement assistance, as outlined in the entitlement matrix, and support cost for Resettlement Plan implementation. The Government of Bangladesh will release funds to the PMCU and the PMCU will release funds to the PIU in a timely manner. The PIU in DCC will then release funds for resettlement to the entitled displaced persons. The total estimated resettlement cost for the subproject is Tk0.07 million. The costs are outlined below:

(i) Compensation in the form of rental allowances for the temporary displaced households; (ii) Assistance in lieu of the loss of income and livelihood ; (iii) Assistance for shifting of personal items and structures; (iv) Training allowance; and (v) Special assistance to vulnerable groups for their livelihood restoration.

Table 10: Resettlement Budget Sl. No. Item Unit Rate Quantity Amount (Tk) A Compensation A-1 Rental Fees Numbers 60,000 18 1,080,000 Sub Total (A) 1,080,000 B. Assistance B-1 Shifting Assistance Numbers 10,000 18 180,000 B-2 Training Assistance Numbers 12,000 3 36,000 B-3 Loss of Income Numbers 108,000 3 324,000 B-4 Assistance to Vulnerable Numbers 10,000 15 150,000 Households Sub Total (B) 690,000 C RP Implementation Support Cost C-1 Hiring of Resettlement Support Person 100,000 24 2,400,000 Staff at DCC/PIU Month C-2 Administrative Cost Lump 500,000 Sum Subtotal C 2,900,000 Total (A+B+C) 4,670,000 Contingency (10%) 467,000 GRAND TOTAL 5,137,000 GRAND TOTAL (Million Tk) 5.14 GRAND TOTAL (Million USD) 0.07 DCC = Dhaka City Corporation, PIU = Project Implementation Unit.

17

X. INSTITUTIONAL ARRANGEMENTS

A. Project Management Coordination Unit

50. The Local Government Engineering Department (LGED) will be the executing agency responsible for overall guidance and project implementation. A PMCU headed by a Project Director will implement the project investments and will be responsible for overall planning, management, coordination, supervision and progress monitoring of the CRDP in the two regions. The PMCU will ensure compliance with assurances, including safeguards and preparing and submitting reports, resettlement plan monitoring updates. To ensure effective implementation of the land acquisition and resettlement aspects, two full time PMCU resettlement safeguard officers will be recruited, including one Resettlement Compliance Officer primarily responsible for compliance with legal requirements of the Government, and one Resettlement Surveyor responsible for overseeing PIU preparation of the Resettlement Plan for subprojects and data collection. The MDSC will recruit one international and one national resettlement specialist to assist the PMCU in this regard. The PMCU will review monthly reports submitted by PIUs and will consolidate them into quarterly reports to ADB. Corrective actions to be taken when necessary based on close monitoring and results of grievance redress process.

B. Project Implementation Unit

51. The subproject will be managed and implemented through the PIU based in the Dhaka City Corporation office. The PIU will be responsible for carrying out the detailed design of the subprojects and updating RPs for the sample subprojects and prepare new RPs for future subprojects under the sector approach The PIU will ensure compliance with safeguards requirements of the Government and ADB. The PIU will be responsible for day-to-day monitoring of the project progress, including the implementation of the resettlement provisions in the project.

52. The capacity to implement safeguards planning and implementation at the PIU level is not currently adequate. Therefore, it is proposed that resettlement support staff (or facilitators) at the PIU level will be recruited. The number of resettlement support staff at each PIU will be commensurate to the scale of involuntary resettlement impacts (e.g., the greater the impact, the greater number of support staff needed). All PIU and PMCU safeguards staff will undergo training conducted by the consultant team’s resettlement specialists. Each PIU will prepare monitoring reports on all aspects concerning to resettlement planning and implementation of the land acquisition and resettlement issues and report to the PMCU on a monthly basis.

C. Management, Design and Supervision Consultants

53. The MDSC will hire one International Resettlement Specialist (IRS) and one National Resettlement Specialist (NRS). They will be responsible for updating/finalizing the Resettlement Plans of sample subprojects in accordance with this Resettlement Framework and based on the detailed engineering design. These specialists will also prepare new Resettlement Plans for future subprojects under the sector approach consistent with this Resettlement Framework. This will be done in close coordination with PIU resettlement support staff and PMCU resettlement officers. The IRS and the NRS will assist in the overall supervision of the projects and ensure all plans are implemented in a smooth and timely manner in accordance with the provisions of the Resettlement Plan. They will also prepare and implement training and capacity development programs for resettlement planning for the PIU and PMCU safeguards staff (see section below on Training and Capacity Building), and will closely work with the PMCU and PIUs to ensure

18 displaced persons are compensated before displacement occurs, including ongoing rehabilitation measures. Further details on agencies responsible for Resettlement Plan activities are in Table 11 and the organization chart for Resettlement Plan implementation is depicted in Figure 2.

Table 11: Institutional Roles and Responsibilities Activity Responsible Agency A. Subproject Initiation Stage and Institutional Setup Formation of PMCU. LGED Formation of PIU. LGED Finalization of sites for subprojects. PMCU/PIU/MDSC Disclosure of proposed land acquisition and subproject details by PIU/PMCU issuing Public Notice. Meetings at community/household level with displaced persons. PIU Capacity Building training. MDSC/IRS B. Resettlement Plan Preparation/Updating Stage Resettlement screening and categorization form and submission to ADB PIU/PMCU for each subproject. ADB to confirm resettlement categorization. ADB Census of 100% displaced persons and socioeconomic survey. PIU/PMCU Screening of vulnerable displaced persons. PIU/PMCU Survey on unit prices for computing replacement costs. PIU/PMCU Calculation of compensation and entitlements.. PIU/PMCU Update of sample subproject Resettlement Plans and preparing new PIU/PMCU Resettlement Plans in accordance with Resettlement Framework. Consultations with displaced persons on entitlements. Compliance with PIU/PMCU disclosure requirements. Finalize Resettlement Plans and submit to ADB. All draft Resettlement PIU/PMCU Plans must be submitted to ADB for clearance prior to award of contracts. Incorporate all comments and suggestions to Resettlement Plans. PIU/PMCU Web disclosure ADB/PMCU C. Resettlement Plan Implementation Stage Issuance of identification Cards to displaced persons PIU/PMCU Detailed schedule for compensation PIU/PMCU Distribution of relocation notices to displaced persons PIU/PMCU Award of checks for land compensation PIU/PMCU Award of checks for other compensation and assistance/ rehabilitation PIU/PMCU Confirm with ADB in writing when payment of entitled compensation to PMCU/PIU displaced persons and relocation has been completed. Permission to contractor to begin works once compensation to displaced persons is confirmed (note: other income rehabilitation to continue after civil works commence). Notice to proceed for civil works is issued on sections where compensation PIU/PMCU is paid. Demolishing/ relocation of affected structures/assets PIU/PMCU Income restoration program and training PIU/PMCU Grievances redress mechanism PIU/PMCU/GRC Internal monitoring PIU/PMCU Review of Resettlement Plan implementation by external expert through a External Expert compliance report for projects with significant impacts ADB = Asian Development Bank, GRC = Grievance Redress Committee, IRS = International Resettlement Specialist, LGED = Local Government Engineering Department, MDSC = Management, Design and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. 19

Figure 2: Organization Chart for Resettlement Plan Implementation

LGED ADB

PMCU

1 Resettlement Compliance Officer, 1 Resettlement Surveyor

MDSC 1 International Resettlement Specialist, 1 National Resettlement Specialist

PIU Resettlement Support staff

DISPLACED PERSONS

ADB = Asian Development Bank, LGED = Local Government Engineering Department, MDSC = Management, Design, and Supervision Consultant, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit.

XI. IMPLEMENTATION SCHEDULE

54. Compensation and relocation of displaced persons cannot commence until the Resettlement Plan has been cleared by ADB. All compensation and relocation activities is to be paid prior to displacement although income rehabilitation measures will continue after construction begins. Written confirmation is required by the PMCU to ADB stating that all compensation has been paid to displaced persons and relocation is accomplished. Only then can construction works begin on sections where compensation has been paid. The project will be implemented over six years (January 2011 to December 2016). The implementation of the Resettlement Plan will include: (i) identification of cut-off date and notification; (ii) verification of losses and extent of impacts; (iii) finalization of entitlements and distribution of identity cards ; (iv) consultations with displaced persons on their needs and priorities; and (v) resettlement, provision of compensation and assistance, and income restoration for displaced persons. The expected implementation schedule for a subproject is given in Table 12.

20

Table 12: Implementation Schedule Activity Months 1 2 3 45678910 11 12 13 14 15 16 17 18 Establishment of PMCU and PIU.  Appointment of safeguards staff in  PMCU and PIUs. Appointment of international and  national resettlement specialists on consultant team. Formation of GRC at PIU and PMCU  level. Census surveys (issuance of     identification cards). Send screening and categorization  form for subprojects to ADB. Consultations and disclosure.                  Confirmation of government land to   be used and transfer from other departments. Resettlement Plan preparation.      Resettlement Plan review and  approval (PMCU and ADB). All draft Resettlement Plans must be submitted to ADB for clearance prior to award of contracts. Issue notice to displaced persons.  Compensation prior to displacement    and income rehabilitation ongoing. Written confirmation from PMCU to  ADB that all compensation paid in sections ready for construction. Permission to contractor to begin works once compensation to displaced persons is confirmed. Relocation as required    Takeover possession of acquired    property Handover land to contractors  Start of civil works  Skills training as required for income       restoration Grievance Redress Mechanism Internal monitoring                Monthly monitoring reports (PIU to                PMCU) Quarterly monitoring reports (PMCU                to ADB) Rehabilitation of temporarily Immediately after occupied lands construction ADB = Asian Development Bank, GRC = Grievance Redress Committee, PIU = Project Implementation Unit, PMCU = Project Management Coordination Unit. Note: The Resettlement Plan will be updated based on final detailed design and displaced person census and surveys. Endorsement and disclosure of finalized Resettlement Plans consistent with the Resettlement Framework to be undertaken.

21

XII. MONITORING AND REPORTING

55. The extent of monitoring activities will be commensurate with the project’s risks and impacts. Monthly monitoring reports to be submitted by PIU to PMCU. PMCU to consolidate monthly reports into semi-annual monitoring reports to ADB. These reports should form a part of the project progress reports submitted by PMCU to ADB.

56. The objectives of monitoring are to (i) ensure that the standard of living of displaced persons are restored or improved; (ii) ascertain whether activities are progressing as per schedule and the timelines are being met; (iii) assess if compensation, rehabilitation measures are sufficient; (iv) identify problems or potential issues; and (v) identify methods to rapidly to mitigate problems. The above information will be collected by executing and implementing agencies through its PMCU and respective PIU which is responsible for monitoring the day-to- day resettlement activities of the project through the following instruments:

(i) Review of census information for all displaced persons; (ii) Consultation and informal interviews with displaced persons; (iii) In-depth case studies; (iv) Sample survey of displaced persons; (v) Key informant interviews; and (vi) Community public meetings.

57. Internal Monitoring. The internal monitoring by PMCU/PIU will include (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socio-economic monitoring during and after the relocation process to ensure that people are settled and recovering. This will utilize the baseline information established by the socio-economic survey of displaced persons undertaken during subproject preparation; and (iii) overall monitoring whether recovery has taken place successfully and on time. Monitoring will also include the following:

(i) Communication with and documentation of reactions from displaced persons. (ii) Information from displaced persons on entitlements, options, alternative developments, etc. (iii) Valuation of properties. (iv) Usages of grievance redress mechanism. (v) Disbursement of compensation amounts and all assistance. (vi) Physical progress of the Resettlement Plan implementation which will include relocation of displaced persons and affected community properties.

58. The indicators for achievement of objectives during Resettlement Plan implementation are of two kinds such as (i) Process Indicators (Indicating project inputs, expenditure, staff deployment, etc.); and (ii) Output Indicators: Indicating results in terms of numbers of displaced persons compensated, area of temporarily occupied lands restored with topsoil (and other pre- project features), number of displaced persons provided with skills training, etc. Input and output indicators related to physical progress of the work will include items such as:

(i) Training of executing and implementing agencies and other staff completed. (ii) Census, assets inventories, assessments and socio-economic studies completed. (iii) Grievance redress procedures in-place and functionality.

22

(iv) Compensation payments disbursed. (v) Relocation of displaced persons completed. (vi) Project employment provided to displaced persons. (vii) Infrastructure rehabilitated or constructed. (viii) Income restoration activities initiated. (ix) Skills training of displaced persons initiated. (x) Number of households displaced and resettled. (xi) Monitoring and evaluation reports submitted. Appendix 1 23

DETAILS ON PUBLIC CONSULTATION (FGDs)

Name of the Project Component /Site: Renovation houses –Shakhari Bazar

Name of the Mohallah: Shakharibazar

Name of the Street: Shakharibazar road

Name of the Ward: 70

Name of the Zilla/District: Dhaka

Number of Participants: 14 ( fourteen )

Date: July 7, 2010

Time: 12.30 P.M

Q. No. Issues Participants’ Opinion, Comments and Suggestions 1 Have you heard about CRDP Project components like renovation of houses and construction of (City Region Development roads are very familiar to the participants’. Some of them said Project) ‘Members of Ponchaiet committee of Shankari Bazaar’ is more informed about project due to their involvement with city corporation and other organizations than general ‘moholla members. On the other hand few people said they have participated in the discussion meeting with city corporation who also discussed them about the project. Most of women of the household have never been informed about any activities of the project and they are not aware of any activities of the project. 2 If yes, where from They have heard about the project component from local Ward member, staff of Dhaka City corporation who has been trying to motivate people for participating in renovation for long time. 3 General perception about the Many of them think renovation of the buildings is a great project and the awareness opportunity for the people who live in here. They also think that about the proposed project. the project is getting delayed for the last few years which have created little confusion. 4 Do others in this locality support Participants said that almost all people of the locality will support this this support. . 5 Any critical issue or concern by The most concerning issues is about the entitlement of the the local people regarding the house/room. Most of the people do not like to shift the place project? without their authentic ownership. Although community people inherited the house/room from their forefather. But the area is declared as “Vested property “ after the partition in 1947. All most all owners are very much defensive toward the law of government and this makes them concerned of the renovation of the building because if they lose their property. 6 Any criteria you would like to The local poor people should be incorporated in the see considered during project construction/renovation work. Besides owners of the households design, construction and must know schedule of work and budget in transparently. operation stage?

24 Appendix 1

Q. No. Issues Participants’ Opinion, Comments and Suggestions 7 Employment Potential in the Some labor force could be included from the community. project which is of benefit to village 8 Number of Households in the There are around 145 houses in the Mohallah. Mohallah/Town/District 9 Ethnic Minorities /Indigenous Most of the people are from Hindu religion live in the locality. A peoples composition (If there very few Muslims are also live in this area. However, these Hindu are Indigenous People, please groups are not indigenous peoples. mention about the names of the indigenous people and number of households) 10 Number of Shops/ Commercial There are around 2000 shops in the area. establishments in the Mohallah/town 11 Numbers of Industrial Units in The area is very popular for “Shankari cottage industry and most the Mohallah/town and of the people are doing same business. So people have show surrounding area room and industry (small scale) in the same place. 12 General socio-economic Most of the people are middle income earner. The local people standing: What are the (Old Dhaka –‘Dhakkai’, 25% of local residence) are lower in economic activities? Land use, number and they are comparatively well off. They are now only cropping pattern (Seasonal), representatives of ‘shakhari’ and this is their prime business. types of crops, value of the Besides this trading of daily necessaries, groceries are principal crops, Average land holding economic activities. size etc. 13 Is the Area Electrified Yes 14 Source of drinking water The main drinking water source is supply line from WASA. But most of the house share water from one source or road side point. Some also have tube well and dug well. 15 Loss of residential/commercial There may be very little loss of residential/commercial structures structures, if any due to the due to the project which will be temporary in nature project 16 Loss of community life like any When any house will take under construction shops under house Market Places or community will be affected. However it may not affect at the same time. activities to be affected 17 Poverty Level: Is the village The mohallah is belonging to middle income group. poor or very poor or well off 18 Education Status: Literate, Older people are less educated compare to the new generation. illiterate etc Now all most all children of the family member go to school and some also for higher education. Some girl children are also studying in higher class. 19 Employment Status: Most of the people are working, there is no highly unemployed Percentage of employment/ are in the area. A few people do not work due to drug addiction unemployment/ and sickness. underemployment 20 Migration Pattern (If any), Not applicable inward or outward 21 What is the major occupational Most of the local people are ‘shakhari’( shanka maker/bangles). structure of the local people There are numbers of retailers work in groceries and likewise shops. Appendix 1 25

Q. No. Issues Participants’ Opinion, Comments and Suggestions 22 Is there any vulnerable group No. like Ethnic Minority or Adivasis people living in the surrounding area and if yes then how far and the name of the groups 23 Are you satisfied with the They are not satisfied because this locality is mostly out of present infrastructure facility in services provided by DCC. They are neglected. the town and locality 24 Do you face any problem Water problem is severe, drainage problem is also bad. Besides regarding the exiting water huge electrical wires surrounded outside of the building is also a supply/solid waste big threat for people. management/river port/Drainage/Traffic system? 25 If there is any problems related Yes, some house do not have sufficient water supply. Some of to these services, do you think them use roadside water points which are low cost. The entire that any upgradation is building has one connection. Water supply and cooking gas is necessary? needed to upgrade. 26 For this upgradation the Yes it is desirable. road/street/path /drainage may get affected- what do you think about that- is it desirable? 27 How can this affect your Shifting may cause problem in many ways, it will cause loss of present living or activity work and children’s education. 28 Who else could be affected due People who work in the locality, children who study in the same to this up gradation area , if they will shifted to separate place will cause problem in this regards. 29 How intense could be the effect It can affect very seriously in terms of changing their working condition and lifestyle. 30 Do you think the affect will be of The impact will be temporary in nature permanent nature? 31 The project may need shifting Shifting will be possible with proper compensation and of some encroachments and assurances from DCC to get back their old place after the squatters .Would you like to restoration work is complete. shift from here on your own 32 Where will you like to shift yes during this period? 33 If requested to shift, would you Yes, we like to return here with legal assurance and the most like to return here? vital issue for inhabitants of the area. 34 Is there available alternate Some said yes and they will share with other relatives and place for relocation? If yes, how neighbors. Some said they have no place or known people for far and the name of the place getting support. 35 Perceived losses from the Temporary loss of the business, job loss. Project- 36 If losses are perceived, what is Money for rental house the expected compensation you Transfer cost would desire Interest free loan from the bank Compensation for income loss 37 Perceived benefits from the (i) Cottage Shankari business will be sustained; Project- (ii) People life will be more safe for safe home; and (iii) Better environment situation will be created.

26 Appendix 1

Q. No. Issues Participants’ Opinion, Comments and Suggestions 38 Do you think that the local Yes, they are eagerly like to participate in the work; they also residents would like to interested to participate of beginning of the proposal and during participate in this work the work.

39 Any suggestion/opinion, etc. Yes, they all want our house renovation and also want to know process of renovation. We want detailed about that

40 Do you think that the local They all want to know regularly about the upgrading situation of people would like to get regular project. Some of them showed their doubt about the project if or information regarding this not really coming to improve the situation. Project? 41 Will it be through informal or Yes, it is very important to have consultation with the community formal consultation before the implementation. Both formal and informal consultation is desired. 42 Will the project cause health Probably not and safety issues in the area. 43 Resettlement and Land No. acquisition (if foreseen due to project components especially on private land). Has there been land acquisition before? If yes, what was the process of land acquisition and compensation package? 44 Protected areas (national park, Few said ‘Some historical heritage sites within the community protected forest, religiously should be protected. sensitive sites, historical or archaeological sites), if any 45 Health status, Availability of Entire environment is not suitable, total area is congested, open Hospitals and over all drains create unhygienic condition of the area. From the building environmental condition. Is #53 at least four people died from the diseases like tuberculosis, there any chronic disease jaundice ,liver problem prevalent in this area and are you aware about HIV/AIDS and STP? 46 What other organizations of a Grammen Bank, ASA, BRAC etc social nature (NGOs/CBOs/ Civil Society) active in the area? Name of these organizations 47 Will there be likely involvement Yes, they like to monitor the process of the renovation. of local people in the implementation of the project? 48 Kindly indicate what kind of Among the households, most of the women are involved in the economic/ non-economic jobs like sewing , prepare and selling paper packet, supply food activities female members of to office , work in medicine industry and homeopathy. Few also your family are engaged in work at household. Only one says; her husband does not allow her to go outside for work or any reason. 49 If, engaged in economic Most of the women who are working outside said they contribute activities how much they equally as their husband do. Some women who have no male contribute to total family income income earner contribute entirely. of the year Appendix 1 27

Q. No. Issues Participants’ Opinion, Comments and Suggestions 50 Does your female member have Most of the women said they can participate in the household any say, in decision making of decision making process with their male members. Women who household matters are the main of the household take all the decisions. 51 How safe do you regard the The houses are protective and area is electrified and crowed neighborhood / village for therefore there is negligible chance any unsafe events. . women and children during the day time? 52 How safe do you regard the The area has harmony in terms of religion background and neighborhood/village for women occupation. There is no large economic difference between and children during the night people to people in the community. So no harm for women and time? children as they are also have huge mobility in the area. 53 Do the women of your Yes, it is a commercial place and generally women go household can freely go outside everywhere. The children in all level go to school and college. to work, for marketing, or Some youth also go for higher education. accessing hospitals, educational institutes, etc? 54 How often women of your Women fetch water from the road side source regularly. Because household go outside the house many of those household have no individual connection. Some to fetch water in a week? male family members also collect water. 55 Do you have a toilet at your Many of the households sharing one or two toilets household? 56 Do you have adequate street Yes lighting during the night? 57 Is this consultation useful? Yes, much desired consultation, we are delighted to know the Comments project work and appreciated. One woman said; we do not know much about the project activities, but there may be some people come and say so many things. We are not sure about what support exactly is coming to us. Since we are living here nothing good has happened to us from government or any institution. Therefore, this type of consultation is always useful CBO = community-based organization, CRDP = City Region Development Project, DCC = Dhaka City Corporation, NGO = nongovernment organization, STP = sewage treatment plant.

28 Appendix 1

LIST OF PARTICIPANTS Sex Age S.No. Name Occupation (M/F) (Years)

1 Biddut Kumar Nag Service holder M 35

2 Nilkanto Dutta Business M 51

3 Dipak Kumar Dutta Owner of grocery shop M 35

4 Mohesh Chandra Das Service holder M 30

5 Samar Chandra Sur Business M 38

7 Sharati Ghosh Housewife F 25 Prepare paper packet( 8 Nilarani datta F 50 thonga ) 9 Jaideb Lal Dash Vender M 55

10 Suman Lal Das Collage student ( MA) M 24

11 Mala mondal Food supply in office F 40

12 Sapan Kumar sur Gold shop M 45

13 Anandamohi Sur Older person M 70

14 Astomi Ranidhaor Older person F 85

15

16

17

18

19

20

Appendix 2 29

FUTURE CONSULTATION AND DISCLOSURE ROLES AND RESPONSIBILITIES Project Phase Activities Details Responsible Agency Subproject information dissemination on various components

-Leaflets containing Disclosure of Preliminary information on the Project and proposed for required land subproject area to be acquisition to displaced prepared) PIU(Gazipur Project persons Pourashava)/PMCU Initiation Stage -Public notice issued in public (LGED) Preliminary Information places including newspapers Sharing about the tentative and direct consultation with alignment/ sites with the displaced persons displaced persons in case of temporary impact on business, income and livelihood -Further consultations with PIU(Gazipur displaced persons and Pourashava)/PMCU households, titled and non- (LGED) titled.

Stakeholder consultations -Summary Resettlement Framework made available to all displaced persons at the convenient place which is easily accessible and should be in local language (Bengali) Disclosure of final PIU(Gazipur Resettlement Resettlement Persons entitlements and Pourashava)/PMCU Plan disclosed to all displaced rehabilitation packages and (LGED) Preparation persons in local language disclosure of draft Phase (Bengali) Resettlement Plan -Review and approval of PIU(Gazipur Resettlement Plan by Pourashava)/PMCU executing agency. (LGED) -Review and approval of Resettlement Plan by ADB Finalization of Resettlement (prior to award of contract). Plan -Web disclosure of the Resettlement Plan. -Disclosure of the Final Resettlement Plan to displaced persons -Consultations with displaced PIU(Gazipur persons; Pourashava)/PMCU Resettlement Consultation with displaced -Payment of entitlements; (LGED) Plan persons during Resettlement -Written notification from Implementation Plan implementation PMCU to ADB that all Stage compensation paid before displacement occurs ADB = Asian Development Bank, LGED = Local Government Engineering Department, PIU = Project Implementation Unit, PMCU= Project Management Cordination Unit.

30 Appendix 3

MONITORING INDICATORS AND SAMPLE FOR STATUS REPORT S. N. R&R Activities Progress Remarks Pre Construction Activities and R&R Activities 1 Assessment of Resettlement impacts due to changes in project design (If required) 2 Preparation/ updating of Resettlement Plan based on changes in project design 3 Approval of updated Resettlement Plan from ADB 4 Disclosure of updated Resettlement Plan 5 Establishment of Grievance Redress Committee 6 Capacity building of PIU Verification of displaced persons Census list; assessment on compensation and assistance, and readjustment 7 Land Acquisition Resettlement Plan Implementation 1 Payment of Compensation as per replacement value of land & assets to displaced persons 2 Disbursement of assistance to title holders 3 Disbursement of assistance to non-title holders 4 Disbursement of special assistance to vulnerable groups 5 Replacement/ shifting of community property resources 6 Reinstallation of public utilities 7 Records of Grievance Redress 8 Temporary Relocation of Hawkers and Vendors 9 Income Restoration Measures through training Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or use of children as labour 2 Prohibition of Forced or Compulsory Labour 3 Ensure equal pay for equal work to both men and women 4 Implementation of all statutory provisions on labour like health, safety, welfare, sanitation, and working conditions 5 Maintenance of employment records of workers ADB = Asian Development Bank, PIU = Project Implementation Unit, R&R = Resettlement & Rehabilitation.