<<

North-South Rail Link Feasibility Reassessment What is the North-South Rail Link?

Project Overview

The North South Rail Link is a concept to connect the north and south MBTA network through the construction of a rail tunnel under downtown .

Multiple benefits from the improved network connection could arise, including:

• Increase commuter rail capacity • Improve access to employment • Relieve crowding • Improve maintenance flexibility through easier access to facilities, • Reduce highway congestion and emissions • Create redevelopment opportunities by repurposing property no longer needed for rail layover

A potential concept for a connected MBTA network North-South Rail Link Feasibility Reassessment Alignments – Central Artery

CentralOption 1:Artery Central Four-Track Artery Four-Track CentralOption 2:Artery Central Four-Track Artery Two-Track

Key Features: Key Features: • Three stations; includes • Two stations Central Station • Cut-and-cover • Cut-and-cover construction in Fort construction in , mining Point Channel, mining around South Bay around South Bay interchange ramps interchange ramps • Alignment • Uses two 41-foot TBMs accommodated in a 38- to form two 38-foot foot internal diameter internal dimension tunnel built using a tunnels 41-foot-diamter TBM • Tunnels under the • Tunnels under the Orange Line, I-90 Orange Line, I-90 Ramps, the Red, Silver Ramps, the Red, Silver, and Blue Lines and Blue Lines • uses • Fairmount and Old the tunnel Colony Lines continue • to terminate at South continue to terminate at Station at grade at grade

Tracks Tunnel Diameter Stations Alignment Depth Tracks Tunnel Diameter Stations Alignment Depth 4 2 x 41ft 3 120-160ft 2 1 x 41ft 2 120-160ft North-South Rail Link Feasibility Reassessment Back Bay Portal

Back Bay Portal between Shawmut Avenue and Washington Street Back Bay Portal is utilized in all alternatives.

Location: • 2.75% grade means approach to portal must begin immediately east of , with portal located between Shawmut Avenue and Washington Street.

Method of Construction: • Constructed using boat sections and cut-and- cover.

Construction Impacts: • Limited single-tracking from Back Bay into South Station. • Temporary rerouting of some or all , Providence, Stoughton, and service Example Tunnel Portal (under construction) via the Fairmount Line into South Station (this requires electrification of the Fairmount line to allow electric Amtrak service into South Station during construction). • Termination of the Worcester Line and Amtrak Lakeshore Limited service west of Back Bay unless a viable rerouting (i.e. via the Grand Junction Line into ) is identified. North-South Rail Link Feasibility Reassessment Alignments – Congress Street

CentralOption 3:Artery South Four-Track / Congress Alignment CentralOption 4:Artery Pearl Four-Track / Congress Alignment

Key Features: Key Features: • Two stations • Two stations • Single 51-foot TBM • Mining around South bored tunnel with Bay interchange ramps stacked tracks and • Uses two 29-foot- platforms within the diameter TBM bored tunnel bore tunnels • Tunnels under Red, • Tunnels under Orange Blue, Orange and Line, I-90 Ramps, the Green Lines and the Red and Silver Lines, southbound lanes of I-93 northbound lanes, I-93 I-93, the Blue and • Fairmount and Old Green Lines Colony Lines continue • Fairmount and Old to terminate at South Colony Lines continue Station at grade to terminate at South Station at grade

Tracks Tunnel Diameter Stations Alignment Depth Tracks Tunnel Diameter Stations Alignment Depth 2 1 x 51ft 2 110-160ft 2 2 x 29ft 2 120-195ft North-South Rail Link Feasibility Reassessment Station Platforms

SouthSouth Station: Station Platform: Platform Location Alternatives Alternatives and Passenger Walk Times

The following maps show Approximate change in potential locations for the North Proposed South walking distance* (min) Station Platform Alignment Station Station and South Station (Pearl Congress) Option Depth (ft) Post Office platforms, and how each option Seaport Square affects pedestrian connectivity and access. Central Artery 135 ft +1 +4

South Congress 130 ft +6 -1 The accompanying tables Proposed South Proposed South Station Platform Station Platform estimate the change in walk (South Congress) Existing South (Central Artery) Pearl Congress times from the platforms to Station 130 ft +6 -1 (southbound) typical waking destinations from the existing stations. Pearl Congress 185 ft +7 -1 (northbound)

NorthNorth Station: Station Platform: Platform Location Alternatives Alternatives and Passenger Walk Times

= Indicates potential headhouse locations 1 Approximate change in Proposed North walking distance* (min) Station Platform Alignment Station (Central Artery) Option Depth (ft) State Street

Central Artery 140 ft +1

South Congress 140 ft -8

Pearl Congress 135 ft -8 Proposed (southbound) State/Haymarket Station (South Congress, Pearl Congress Pearl Congress) 195 ft -7 (northbound)

* Walking distance measurement taken from the center of the platform.

= Indicates potential headhouse locations 2 North-South Rail Link Feasibility Reassessment Service Plans

MBTA Service Plan Service Plan Alternatives

No Build South Station Expansion NSRL Regular NSRL All-Day Peak These alternative MBTA Service Plans are All-Day Peak Service Service (2-Track) Service (2-Track and used to test the overall operations of the (No NSRL) 4-Track) rail network, and measure the impacts of changes in train frequency along each rail corridor. Each Service Plan has been Peak Current service Maximum achievable Maximum achievable Maximum achievable Level Service schedule service levels* service levels* service levels* calibrated to provide a high level of service for MBTA passengers while maintaining operational effectiveness. Off-Peak Level Current service Maximum achievable Maximum achievable Hourly Service Service Plan alternatives use a combination Service schedule service levels* service levels* of peak and off-peak strategies to deliver performance, and can be operated through any of the alignment alternatives, except as South Coast line South Coast line South Coast line South Coast South Coast line via via Stoughton via Stoughton via Stoughton noted. Rail Middleborough (fully electrified) (fully electrified) (fully electrified)

*A potential frequency of trains every 10-30 minutes depending on the line

Service Plan Assumptions • NSRL Tunnel can support 17 trains per hour (per track, • Quick passenger boarding and alighting using all • Significant infrastructure investments beyond the tunnel may be needed to per direction). train doors, similar to rapid transit operations. meet the above assumptions: • NSRL process held 2-3 slots per hour in each direction • Based on trains following precise schedule • Resignaling of 30 track miles supports increased service. for each tunnel options for Amtrak service. This allows operations that maintain a 17 trains/hour frequency. • Double Tracking at Worcester, Fitchburg, and Newburyport / Rockport (between flexibility for Amtrak to use tunnel capacity to serve • All trains operating through the tunnel are interlined McNall & Northey Point Junctions - between Swampscott and Salem stations). intercity needs. Significant infrastructure and rolling stock with another line on the other side of the system. • Additional Platforms at Fitchburg, Lowell, and Worcester. • Turnback Crossovers at Fitchburg, Franklin, and Fairmount. improvements (as part of the NEC Future process) may be • All trains serve North Station at new subsurface • Crossing and Passing Loops at Needham, Old Colony (passing loop between required. platforms Abington and Whitman Stations), and Haverhill. • Service Plans assume no constraints on station parking. North-South Rail Link Feasibility Reassessment Service Assumptions

NSRL Regular Service and NSRL All-Day Peak Service (2-track) NSRL All-Day Peak Service (4-track) North-South Rail Link Feasibility Reassessment Capital Cost Estimates

Cost Estimate Overview

SouthSouth StationStation CentralCentral Artery South Pearl / CentralCentral Artery ExpansionExpansion All-DayAll-Day South Congress Pearl / Congress Cost Estimate Methodology (22 -- Track)Track Congress Congress (44 -- Track)Track PeakPeak ServiceService • Escalation to midpoint of construction (2028): Tunneling N/ANA $8,629,000,000 $9,493,000,000 $10,701,000,000 $17,730,000,000 Standard practice for construction costs. Aims at simplifying the cost-loading strategy of a project by assuming that 50% of the project cost will be Vehicles $1,397,000,000 $2,380,000,000 $2,380,000,000 $2,380,000,000 $2,439,000,000 incurred in 50% of the project’s duration. • Every cost estimate is escalated by 3.5% for escalation per year. Upstream Investments to $833,000,000 $1,307,000,100 $1,307,000,100 $1,307,000,100 $1,321,000,000 Support Increased Service • Costs include: Alignment Lengths, tunnel types, station areas, trackwork, portals, and allowances • Allowances: underpinning works, roadway

SSX* $2,466,000,000 N/ANA N/ANA N/ANA N/ANA reconstruction, and utility relocations. • Total Design Build Costs = Direct Costs + Indirects + Contractor’s Overhead / Profit + Design Engineering Total $4,696,000,000 $12,317,000,000 $13,181,000,000 $14,388,000,000 $21,491,000,000 • Total Project Costs = Total Design Build Costs + Owner’s Soft Costs + Project Risk Contingency + * Includes only project elements from MassDOT’s South Station Expansion Federal Environmental Filing Escalation to Midpoint of Construction *2018 dollars Cost Estimate Assumptions: • Each alternative has 2 stations except for the Central Artery 4-track which has 3 stations • 2028 Midpoint of Construction USD • Additional Vehicles costs are part of increased service in all alternatives North-South Rail Link Feasibility Reassessment Operating Cost Estimates

Operating Cost Estimates Operating Cost Inputs Operating costs have been estimated for the No Build, South Station The chart below shows train miles and hours per Service Plan alternatives. Expansion All-Day Peak Service, and NSRL Regular Service options.

No Build South Station Expansion NSRL Regular Weekday Daily Totals All-Day Peak Service Service

Vehicle Revenue Service Non-revenue Non-revenue 16,420 41,550 51,470 Revenue Miles Revenue Hours Miles / Day Alternative Miles Hours

Operating $400M $775M $929M Expenses / Year No Build 16,420 530 800 30

South Station *2018 dollars Expansion 41,550 1,370 1,630 60 All-Day Peak Operating Cost Methodology Service

• Train miles and hours provide the basis • The calculations do not allow for non- NSRL Regular 28,290 950 2,300 60 for the estimation of operating costs, revenue moves between lines during Service (2-Track) including maintenance operating hours or any additional

• Distances are derived from the current movements required for rolling stock NSRL All-Day MBTA Commuter Rail track network maintenance or refueling. Peak Service 51,470 1,690 2,800 80 • Journey times are based on current • Mileage and hours are based on the (2-Track) schedule timings whole consist rather than per coach. • Non-revenue mileage and train hours NSRL All-Day Peak Service 55,230 1,780 2,800 90 are based on assumed trainyard (4-Track) locations. (A high-level assessment of yard capacity has been undertaken) North-South Rail Link Feasibility Reassessment Other Factors Affecting Cost

Dual Mode Locomotives and Coaches Electrification Proposal

Dual-mode locomotives are proposed for the NSRL tunnel alternatives as they are Newburyport able to travel on both the electrified and non-electrified portions of the commuter rail Wachusett Haverhill system, switching between diesel and electric operations as appropriate. The chart Lowell Rockport below shows how the MBTA’s fleet would change under each alternative to provide significant capacity across the network.

West Medford Rail Fleet Breakdown Malden Center Chelsea Porter Square SSX All-Day Peak NSRL 2-Track NSRL 4-Track North Station No Build (No NSRL) Tunnel Tunnel South Station Back Bay JFK/UMass 42 Diesel 32 Diesel

Newmarket

Locomotive Type

Needham Heights 90 Diesel 145 Diesel 120 Dual-mode 130 Dual-mode

Worcester

Total 90 145 162 162

Forge Park/495 Greenbush

Coaches Wickford Junction

Middleboro/ Lakeville Kingston Plymouth

Total 397 583 600 600 Battleship Cove

Whale’s Tooth *2018 dollars 250,000

Peak Hour Project Capacity

North-South Rail Link Feasibility Reassessment80,000 67,000 200,000

Ridership and Capacity 60,000 59,000 55,000 48,000 Electrification Proposal All-Day Boardings Peak Hour44,000 Project Capacity 40,000 250,000 250,000 80,000 35,000 38,000 43,000 47,000 51,000 67,000 AM Peak Hour Project 225,000 20,000 Capacity 150,000 60,000 59,000 55,000 48,000 AM Peak 200,000 195,000 195,000 44,000 51,000 Hour Forecast 47,000 0 43,000 Ridership 150,000 195,000 195,000 225,000 250,000 40,000 No Build South Station NSRL Regular NSRL All-Day NSRL All-Day 38,000 35,000 Expansion All-Day Service Peak Service Peak Service Peak Service (2-Track) (2-Track) (4-Track) 20,000 (No NSRL) 150,000 150,000 AM Peak Hour Forecast Ridership 100,000 AM Peak0 Hour Project Capacity No Build South Station NSRL Regular NSRL All-Day NSRL All-Day Expansion All-Day Service Peak Service Peak Service Peak Service (2-Track) (2-Track) (4-Track) (No NSRL) 100,000

*NSRL All-Day Peak Service capacity is slightly above NSRL Regular Service capacity due to slight differences in the proposed timetables for these two Service Plan alternatives.

Daily Ridership Forecast Daily Ridership Forecast 50,000 50,000 Daily Northside 55,000 +27% +48% +75% +100% Daily Boardings Northside Boardings

0

No Build South Station NSRL Regular NSRL All-Day NSRL All-Day Daily Expansion All-Day Service Peak Service Peak Service Daily Southside Southside Peak Service (2-Track) (2-Track) (4-Track) 95,000 +36% +23% +36% +50% Boardings (No NSRL) Boardings No Build South Station NSRL Regular NSRL All-Day NSRL All-Day 0 No Build SouthExpansion Station All-Day NSRLService Regular NSRLPeak All-Day Service NSRLPeak All-DayService Peak Service (2-Track) (2-Track) (4-Track) No Build South Station NSRL Regular NSRL All-Day NSRL All-Day Expansion(No NSRL) All-Day Service Peak Service Peak Service Peak Service (2-Track) (2-Track) (4-Track) Expansion All-Day Service Peak Service Peak Service (No NSRL) Peak Service (2-Track) (2-Track) (4-Track) (No NSRL) Frequencies (peak direction)

Service Midday PM Peak Evening Late Night Lines/Line Pairings AM Peak Alternative (9:00- (16:00- (19:00- (21:00- (6:00-9:00) 16:00) 19:00) 21:00) 1:00)

Newburyport/Rockport to North Station 15 60 20 30 60 Haverhill to North Station 30 60 30 60 120 Lowell to North Station 20 60 30 60 120 Fitchburg to North Station 30 60 30 60 120 Worcester to South Station 15 120 20 60 60 Needham to South Station 30 60 30 60 120 No Build 2040 Franklin to South Station 30 60 30 60 60 Providence/Stoughton to South Station 15 60 20 60 60 Fairmount to South Station 30 60 60 60 120 Middleborough/SCR to South Station 30 120 60 120 240 Kingston/Plymouth to South Station 30 120 60 120 120 Greenbush to South Station 30 120 30 120 240 Newburyport/Rockport to North Station 15 15 15 15 30 Haverhill to North Station 20 20 20 20 30 Lowell to North Station 20 20 20 20 30 Fitchburg to North Station 20 20 20 20 30 Worcester to South Station 10 10 10 10 20 South Station Needham to South Station 30 30 30 30 60 Expansion All Day Peak (No NSRL) Franklin to South Station 30 30 30 30 60 Providence/Stoughton to South Station 15 15 15 15 30 Fairmount to South Station 15 15 15 15 30 Middleborough/SCR to South Station 30 60 30 60 120 Kingston/Plymouth to South Station 30 60 30 60 120 Greenbush to South Station 30 60 30 60 120

Fairmount to South Station 15 60 15 60 60 Middleborough to South Station 30 120 30 120 180 Kingston/Plymouth to South Station 30 120 30 120 180 Greenbush to South Station 30 120 30 120 180 NSRL Regular Worcester to Newburyport/Rockport Service 15 60 15 60 60 Needham to Fitchburg 30 90 30 60 120 Franklin to Fitchburg 25 90 25 90 120 Providence/SCR to Lowell 20 60 20 60 60 Providence/SCR to Haverhill 20 60 20 60 60

Fairmount to South Station 15 15 15 15 30 Middleborough to South Station 30 60 30 60 120 Kingston/Plymouth to South Station 30 60 30 60 120 Greenbush to South Station 30 60 30 60 120 NSRL All-Day Peak Worcester to Newburyport/Rockport Service (2-track) 15 15 15 15 30 Needham to Fitchburg 30 30 30 30 60 Franklin to Fitchburg 15 15 15 15 30 Providence/SCR to Lowell 15 15 15 15 30 Providence/SCR to Haverhill 20 20 20 20 30

Dedham to South Station 30 30 30 30 60 Middleborough to South Station 30 60 30 60 60 Kingston/Plymouth to South Station 30 60 30 60 60 Greenbush to South Station 30 60 30 60 60 Worcester to Newburyport/Rockport 30 30 30 30 60 NSRL All-Day Peak Worcester to Fitchburg Service (4-track) 15 15 15 15 30 Needham to Haverhill 30 30 30 30 60 Franklin to Haverhill 30 30 30 30 60 Providence/SCR to Lowell 10 10 10 10 30 Fairmount to Newburyport/Rockport 30 30 30 30 60 Fairmount to Fitchburg 30 30 30 30 60