Environmental Monitoring Report July to September 2017

CAM: Medium Voltage Sub-Transmission Expansion Sector Project Loan 2979-CAM

Prepared by Electricite du Cambodge, for the Asian Development Bank.

This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website.

Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

KINGDOM OF CAMBODIA Nation Religion King

ELECTRICITÉ DU CAMBODGE Medium Voltage Sub-Transmission Expansion Sector Project, Package 1&2

ADB Loan N° 2979 CAM (SF)

UPDATED ENVIRONMENTAL MONITORING QUARTERLY REPORT No.4 (From July to September 2017)

October 2017

Korea Electric Power Corporation in association with Cheang Engineering Consultants Co.,Ltd

Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

CONTENTS

CONTENTS ...... i Environmental Monitoring ...... 1 1. Introduction ...... 1 2. Environmental Monitoring Program ...... 2 2.1 Scope of works ...... 2 2.2 Methodology ...... 2 3. Results of Environmental Monitoring ...... 3 3.1 Field monitoring ...... 4 3.1.1 Subproject Location ...... 4 3.2 Project implementation ...... 6 3.2.1 Progress up to June 2017 ...... 6 3.2.1.1 Package 1(Kalpataru) ...... 6 3.2.1.2 Package 2(Jong Ro) ...... 7 3.2.3 Progress up to September 2017 ...... 9 3.2.3.1 Package 1(Kalpataru) ...... 9 3.2.3.2 Package 2(Jong Ro) ...... 10 3.3 Summary of Inspection Activities ...... 19 3.4 Mitigation Compliance and Effectiveness ...... 21 3.5 Environmental Monitoring Result in the Reporting Period ...... 22 3.5.1 From April to June 2017 ...... 22 A. Physical Resource ...... 22 a.1 Air pollution ...... 22 a.2 Noise disturbance and Vibration ...... 22 a.3 Surface and Ground Water quality ...... 23 a.4 Soil erosion ...... 24 B. Natural resource ...... 26 C. Waste management ...... 26 c1. Solid waste ...... 26 c2. Liquid waste ...... 26

Monitoring Report #4 I Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

D. Social Resource ...... 26 d1. Cultural Heritage ...... 26 d2. Traffic...... 26 d3. Safety ...... 27 3.5.2 From July to Sept 2017...... 28 A. Physical Resource ...... 28 a.1 Air pollution ...... 28 a.2 Noise disturbance and Vibration ...... 28 a.3 Surface and Ground Water quality ...... 29 a.4 Soil erosion ...... 30 B. Natural resource ...... 31 C. Waste management ...... 32 c1. Solid waste ...... 32 c2. Liquid waste ...... 32 D. Social Resource ...... 32 d1. Cultural Heritage ...... 32 d2. Traffic...... 32 d3. Safety ...... 33 4. Conclusion and Recommendations ...... 34 4.1 Conclusion ...... 34 4.2 Recommendations ...... 34 ANNEX 1: Environmental Monitoring Matrix ...... 36

Monitoring Report #4 ii Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

List of Table

Table 3.3.1: Summary of Monitoring Program ...... 19 Table 3.4.1: Mitigation compliance and effectiveness ...... 21

Monitoring Report #4 III Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

List of Figure

Figure 3.1.1.1: Route Map with Work Progress in (P1) ...... 12 Figure 3.1.1.2: Route Map with Work Progress in Kampong Thom(P1) ...... 13 Figure 3.1.1.3: Route map in Siem Reap(P1) ...... 14 Figure 3.1.1.4: Route map in Banteay Meanchey(P2)...... 15 Figure 3.1.1.5: Route map in Siem Reap(P2) ...... 16 Figure 3.1.1.6: Route map in Kampong Thom (P2) ...... 17 Figure 3.1.1.7: Route map in Kandal(P2) ...... 18 Figure 3.5.1 (a1): MV system and Pole after installation ...... 22 Figure 3.5.1 (a2): Pole installation ...... 23 Figure 3.5.1 (a3): Condition of some MV Pole next to the canal ...... 24 Figure 3.5.1 (a4): Pole Condition after planted ...... 24 Figure 3.5.1 (b-1): Wood from cut trees for MV along the route ...... 25 Figure 3.5.1 (d2): Traffic and Road Condition next to the route line ...... 27 Figure 3.5.1 (d3-1): Safety Tool for worker during working ...... 27 Figure 3.5.2 (a1): MV system and Pole after installation ...... 28 Figure 3.5.2 (a2): Ear mug Protection from Noise ...... 29 Figure 3.5.2 (a3): Condition of some MV Pole next to the canal ...... 30 Figure 3.5.2 (a4): Pole Condition after planted ...... 30 Figure 3.5.2 (b-1): Wood from cut trees for MV along the route ...... 31 Figure 3.5.2 (d2): Traffic and Road Condition next to the route line ...... 33 Figure 3.5.2 (d3-1): Safety Uniform/Tool for worker during working ...... 33

Monitoring Report #4 iv Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

ENVIRONMENTAL MONITORING

1. Introduction

1. The environmental monitoring report is intended to follow-up the contractor’s implementation on environmental mitigation measures in construction stage as stated in EMP and other environmental safeguards provisions in construction contract documents. The main contents are as follows:

1) Project implementation progress;

2) Performance of compliance with ADB’s guideline and applicable government laws, regulations and requirements;

3) Environmental mitigation measures implemented;

4) Key issues identified and recommended corrective actions.

2. This report presents the project environmental monitoring progress including mitigation measures, environmental monitoring result, implementation roles and responsibilities, reporting, and capacity building.

3. The loan Project, Package 1, Medium-Voltage Sub-Transmission Expansion Sector Project, will finance the expansion the electricity sub-transmission infrastructure by constructing about 1,675 km of new three phase 22 kV overhead sub-transmission lines in province of Siem Reap Kampong Thom, and Kampong Cham. It also includes short lengths of 22 kV underground cables, installation of 22kV/0.4kV pole mounted distribution transformers, advanced electronic metering for all distribution transformers, auto reclosing circuit breakers and automatic voltage regulators to improve reliability and voltage performance. The following are the three subprojects under Package 1 of the project: - Subproject 1: 184 cct-km in - Subproject 2: 625 circuit-kilometer (cct-km) in - Subproject 3: 866 cct-km in

4. The loan Project, Package 2, will finance the expansion the electricity sub- transmission infrastructure by constructing about 483 km of new 22 kV overhead sub-transmission line in province of Banteay Meanchey, Siem Reap, Kampong Thom and Kandal.

Monitoring Report #4 1 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

2. Environmental Monitoring Program

2.1 Scope of works

5. The construction, operation, and maintenance of MV sub-transmission lines along rural roads in Cambodia will have an insignificant impact on the local environment. Environmental mitigation measures normally associated with internationally recognized good engineering practice will be implemented to ensure that potential environmental impacts of the Project are avoided or minimized to acceptable levels. Mitigation measures are presented: The major tasks for the environmental monitoring in construction stage include:

· Field monitoring on contractor’s environmental mitigation measure performance to avoid and minimize negative social and environmental impacts;

· Potential environmental impacts that could occur during each Project stage;

· Guidance to Contractor’s personnel on environmental monitoring aspect, in the field practice;

· Recommend to contractor to implement all EMP recommendation and other environmental safeguards in construction contract documents;

2.2 Methodology

6. In the construction stage, site observations are conducted for monitoring the implementation of environmental mitigation measures. Site monitoring is carried out using environmental monitoring matrix and public perception interview (directly asking the questions to the project workers and people living nearby the project sites). This EMP Monitoring Report presents overall assessment of the Project’s compliance with the EMP and also provides conclusion and recommendations going forward.

7. Environmental monitoring consisted of routine systematic checking to verify whether appropriate mitigation measures have been implemented effectively during each stage of the Project. The Environmental Safeguard Specialists of Project

Monitoring Report #4 2 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Implementation Consultant (PIC), with support from EDC’s Social, Environment and Public Relations Office (SEPRO) monitors the implementation status of the EMP, including identifying any non-compliance, proposing actions and a timeline for rectifying deficiencies and following up on the status of previous corrective actions.

8. Throughout the construction period, the PIC Environmental Specialists in consultation with SEPRO have prepared quarterly environmental monitoring reports to check the performance of compliance with ADB’s guideline and applicable government laws and supervise implementation of environmental mitigation measures carried out by contractor and the reports are submitted to EDC and ADB, The reports includes a summary of the results of site inspections and provides recommendations on key issues or concerns that need to be resolved.

9. The monitoring program will be done monthly in order to make the quarterly report. So, every 3 months will submit one report.

3. Results of Environmental Monitoring

10. The survey/investigations and assessment for environmental and social safeguard have been conducted and safeguard documents are prepared for not only the Package 1 project in the provinces of Kampong Cham, Kampong Thom and Siem Reap but also the Package 2 project in the provinces of Banteay Meanchey,Siem Reap, Kampong Thom and Kandal.

11. Contractor for Package 1 project submitted the Construction Environmental Management Plan (CEMP) dated on 14th March 2016 and approved by EDC dated on 22nd April 2016.

12. Contractor for Package 2 project submitted the Construction Environmental Management Plan (CEMP) dated on 4th November 2016 and approved by EDC dated on 29th November 2016.

13. The contractor has performed activities to minimize environmental issues according to the submitted CEMP and prepare monthly progressive report for submission to Consultant/EDC for reviewing and taken action to mitigate adverse environmental impact.

Monitoring Report #4 3 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.1 Field monitoring

3.1.1 Subproject Location

3.1.1.1 Project in Kampong Cham province(P1)

14. The subproject is located in 3 districts in Kampong Cham, namely Chamkar Leu, Kampong Siem and . This subproject consists of overhead MV totaling 184 cct-km. According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 217 km - Underground distribution line: 3 km

3.1.1.2 Project in Kampong Thom province(P1)

15. The subproject is located in 7 districts in Kampong Thom province, namely Baray, Kampong Svay, PrasatBalang, PrasatSambo, Santuk, Steung Saen and Stoung. This sub-project in this province consists of overhead MV totaling 625 (cct-km). According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 736 km - Underground distribution line: 11km

3.1.1.3 In Siem Reap province(P1)

16. The subproject is located in 8 districts in Siem Reap province, namely Angkor Chum, Chikreng, Kralanh, Pouk, Prasat Bakong, Siem Reap, Sotr Nikum and Varin. The sub-project in this province consists of overhead MV totaling 866 (cct-km). According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 933 km - Underground distribution line: 22 km

3.1.1.4 In Banteay Meanchey (P2)

Monitoring Report #4 4 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

17. The subproject is located in 5 districts in Banteay Meanchey province, namely Thma Phouk, Phnom Srok, Svay Chek, Mongkul Borey, Malai. The sub-project in this province consists of overhead MV totaling 112 (cct-km). According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 346 km

3.1.1.5 In Siem Reap(P2)

18. The subproject is located in 4 districts in Siem Reap province, namely Angkor Chum, Svay Leu, Srei Snam, Kralanh. The sub-project in this province consists of overhead MV totaling 129 (cct-km). According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 399 km

3.1.1.6 In Kampong Thom (P2)

19. The subproject is located in 2 district in Kampong Thom province, namely Prasat Sambour, Sandan. The sub-project in this province consists of overhead MV totaling 192 (cct-km). According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 593 km

3.1.1.7 In Kandal (P2)

20. The subproject is located in 1 district in , namely S’Ang. The sub- project in this province consists of overhead MV totaling 50 (cct-km). According to the price schedule in the contract document, the distance of each type of distribution line is below:

- Overhead distribution line: 148 km - Underground distribution line: 7.87 km

Monitoring Report #4 5 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.2 Project implementation

3.2.1 Progress up to June 2017

3.2.1.1 Package 1(Kalpataru)

21. According to the Contractor monthly progress report N° 018 dated March 2017, the civil works progress of the 3 provinces is as follows:

SIEM REAP province

a) Concrete Pole installation - Concrete pole in the contract 13,648 - Concrete pole installed (progress of work) 11,777 (86%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 933 - Distribution line stringing cct-km (progress of work) 777.47 (83%) c) Underground cable installation - Cable in the contract (m) 22,000 - Cable installation (progress of work) 8,452 (38%) d) Transformer installation - Transformer in the contract 306 - Transformer installation (progress of work) 0 (0%) KAMPONG THOM province

a) Concrete Pole installation - Concrete pole in the contract 10,310 - Concrete pole installed (progress of work) 7,353(71%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 736 - Distribution line stringing cct-km (progress of work) 304 (41%) c) Underground cable installation - Cable in the contract (m) 11,000 - Cable installation (progress of work) 0 (0%) d) Transformer installation - Transformer in the contract 257 - Transformer installation (progress of work) 0 (0%)

Monitoring Report #4 6 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

KAMPONG CHAM province

a) Concrete Pole installation - Concrete pole in the contract 3,490 - Concrete pole installed (progress of work) 190 (5%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 217 - Distribution line stringing cct-km (progress of work) 9 (4%) c) Underground cable installation - Cable in the contract (m) 3,000 - Cable installation (m) (progress of work) 0 (0%) d) Transformer installation - Transformer in the contract 50 - Transformer installation (progress of work) 0 (0%)

3.2.1.2 Package 2(Jong Ro)

22. According to the Contractor monthly progress report N° 05 dated June 2017, the civil works progress of the 4 provinces is as follows:

Banteay Meanchey province a) Concrete Pole installation - Concrete pole in the contract 1,578 - Concrete pole installed (progress of work) 1,532 (97%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 346 - Distribution line stringing cct-km (progress of work) 117 (33.9%) c) Transformer installation - Transformer in the contract 19 - Transformer installation (progress of work) 0 (0%)

Siem Reap province a) Concrete Pole installation - Concrete pole in the contract 1,632 - Concrete pole installed (progress of work) 1,081 (66.2%) b) Concrete Pole stringing

Monitoring Report #4 7 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

- Distribution line in the contract (cct-km) 399 - Distribution line stringing cct-km (progress of work) 0 (0%) c) Transformer installation - Transformer in the contract 40 - Transformer installation (progress of work) 0 (0%)

Kampong Thom province a) Concrete Pole installation - Concrete pole in the contract 2,460 - Concrete pole installed (progress of work) 1,997 (81.2%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 593 - Distribution line stringing cct-km (progress of work) 0 (0%) c) Transformer installation - Transformer in the contract 58 - Transformer installation (progress of work) 0 (0%)

Kandal province a) Concrete Pole installation - Concrete pole in the contract 806 - Concrete pole installed (progress of work) 0 (0%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 933 - Distribution line stringing cct-km (progress of work) 0 (0%) c) Underground cable installation - Cable in the contract (m) 7,875 - Cable installation (progress of work): 0 (0%) d) Transformer installation - Transformer in the contract 40 - Transformer installation (progress of work) 0 (0%)

Monitoring Report #4 8 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.2.2 Progress up to September 2017

3.2.3.1 Package 1(Kalpataru)

23. According to the Contractor monthly progress report N° 021 dated October 2017, the civil works progress of the 3 provinces is as follows:

SIEM REAP province a) Concrete Pole installation - Concrete pole in the contract 13,648 - Concrete pole installed (progress of work) 12,289 (90%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 933 - Distribution line stringing cct-km (progress of work) 836 (89%) c) Underground cable installation - Cable in the contract (m) 22,000 - Cable installation (progress of work): 8,452 (38%) d) Transformer installation - Transformer in the contract 306 - Transformer installation (progress of work) 7(5%)

KAMPONG THOM province a) Concrete Pole installation - Concrete pole in the contract 10,310 - Concrete pole installed (progress of work) 8,683 (84%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 736 - Distribution line stringing cct-km (progress of work) 446 (60%) c) Underground cable installation - Cable in the contract (m) 11,000 - Cable installation (progress of work) 0 (0%) d) Transformer installation - Transformer in the contract: 257 - Transformer installation (progress of work): 0 (0%)

Monitoring Report #4 9 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

KAMPONG CHAM province a) Concrete Pole installation - Concrete pole in the contract 3,490 - Concrete pole installed (progress of work) 1,002 (28%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 217 - Distribution line stringing cct-km (progress of work) 20 (9%) c) Underground cable installation - Cable in the contract (m) 3,000 - Cable installation (m) (progress of work) 0 (0%) d) Transformer installation - Transformer in the contract 50 - Transformer installation (progress of work) 0 (0%)

3.2.3.2 Package 2(Jong Ro)

24. According to the Contractor monthly progress report N° 08 dated October 2017, the civil works progress of the 4 provinces is as follows:

Banteay Meanchey province a) Concrete Pole installation - Concrete pole in the contract 1,578 - Concrete pole installed (progress of work) 1,542 (99%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 346 - Distribution line stringing cct-km (progress of work) 306 (88%) c) Transformer installation - Transformer in the contract 19 - Transformer installation (progress of work) 0 (0%)

Siem Reap province a) Concrete Pole installation - Concrete pole in the contract 1,632 - Concrete pole installed (progress of work) 1,369 (84%)

Monitoring Report #4 10 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

b) Concrete Pole stringing - Distribution line in the contract (cct-km) 399 - Distribution line stringing cct-km (progress of work) 257 (64%) c) Transformer installation - Transformer in the contract 40 - Transformer installation (progress of work) 0 (0%)

Kampong Thom province a) Concrete Pole installation - Concrete pole in the contract 2,460 - Concrete pole installed (progress of work) 2,349 (95%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 593 - Distribution line stringing cct-km (progress of work) 201 (34%) c) Transformer installation - Transformer in the contract 58 - Transformer installation (progress of work) 0 (0%)

Kandal province a) Concrete Pole installation - Concrete pole in the contract 806 - Concrete pole installed (progress of work) 0 (0%) b) Concrete Pole stringing - Distribution line in the contract (cct-km) 933 - Distribution line stringing cct-km (progress of work) 0 (0%) c) Underground cable installation - Cable in the contract (m) 7,875 - Cable installation (progress of work): 0 (0%) d) Transformer installation - Transformer in the contract 40 - Transformer installation (progress of work) 0 (0%)

Monitoring Report #4 11 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.1: Route Map with Work Progress in Kampong Cham(P1)

Monitoring Report #4 12 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.2: Route Map with Work Progress in Kampong Thom(P1)

Monitoring Report #4 13 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.3: Route map in Siem Reap(P1)

Monitoring Report #4 14 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.4: Route map in Banteay Meanchey(P2)

Monitoring Report #4 15 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.5: Route map in Siem Reap(P2)

Monitoring Report #4 16 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.6: Route map in Kampong Thom (P2)

Monitoring Report #4 17 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.1.1.7: Route map in Kandal(P2)

Monitoring Report #4 18 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.3 Summary of Inspection Activities

25. The EDC-SEPRO/PIC personnel for environmental and technical supervision regularly visit the construction sites and monitor the safeguard compliance of the contractor. The monitoring activities were as followings:

· Assess their performance of environmental safeguards implementation on site; · Examine, request, and supervise the Contractor in its implementation of traffic management methods within the site and at the road crossings; · Instruct and supervise the Contractor to carry out the environmental and social management plans in accordance with the mitigation measures listed in the EMP; · Monitor and document dust and noise mitigation measures, solid waste management and site clean-up carried out by the Contractor.

26. The contractual agreement between EDC and the contractor indicates that the contractor shall undertake mitigation measures to avoid and minimize negative social and environmental impacts. The Environment Management Plan was therefore enclosed in the contractual agreement of civil works.

27. The Bidding Documents and the Contractual Agreement include provisions of safeguard requirements to ensure that EMP and the Environmental Protection Commitment (EPC) are being adhered to during the design and construction stage as following monitoring programs:

Table 3.3.1: Summary of Monitoring Program Monitoring Frequency Environmental Monitoring Activities EDC-SEPRO, issues Location Contractor PIC Clearing of ROW and Monitor tree cutting Weekly Monthly vegetation transportation (July-Sept, routes 2017) Erosion and Pole foundation Inspection of excavation Weekly Monthly sedimentation area works, silt arising from (July-Sept, exposed soil surface, 2017) condition of erosion Monitoring Report #4 19 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Monitoring Frequency Environmental Monitoring Activities EDC-SEPRO, issues Location Contractor PIC control measures Dust generation · Along access · Monitor and inspect Weekly Monthly road, dust condition around (July-Sept, · Surrounding construction area and 2017) residential transportation routes, areas · Consult with local · Construction people on dust site problem during construction.

Noise Surrounding · Monitor noise during Weekly Monthly residential areas materials delivery and (July-Sept, operation of 2017) construction equipment, · Consult with local people on noise caused by construction activities Waste Workers’ camp · Inspection of worker Weekly Monthly Management sites camp site condition, (July-Sept, · Check proper solid 2017) waste disposal Health and Safety Sub-transmission Review contractor’s Weekly Monthly line construction construction workers (July-Sept, health and safety plan 2017) and training activities on health and safety Damage/nuisance · ROW and · Monitor and inspect Weekly Monthly around the impact on (July-Sept, project area, community’s 2017) · Along the infrastructure, lake, roads river, irrigation and drainage facilities, · Monitor and inspect public road conditions

Monitoring Report #4 20 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.4 Mitigation Compliance and Effectiveness

28. Mitigation compliance and effectiveness are described in qualitative terms and are evaluated based on a ranking system. Table 3.4.1 shows the effectiveness of the mitigation measures undertaken.

Table 3.4.1: Mitigation compliance and effectiveness Mitigation Measures Compliance Effectiveness Environmental safeguards compliance at construction site

Permanent land acquisition 2 2

Temporary land acquisition 2 2 Biodiversity and natural resources 2 2 Air quality 2 2 Noise and Vibration 2 2 Waste management 2 2 Water quality 2 2 Erosion, sedimentation and flood 2 2

Community Health and Safety(CHS) Construction Health and Safety 3 3 Public Safety Risk Management 2 2 Note: 1. VeryGood 2. Good 3. Fair 4. Poor 5. VeryPoor

Monitoring Report #4 21 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.5 Environmental Monitoring Result in the Reporting Period

3.5.1 From April to June 2017

A. Physical Resource

a.1 Air pollution

29. The condition of the air in the project site was not affected by the project activities. Air pollution is not identified in the project location according to the field observation, there is no significant from dust and smoke generation from construction activities.

Figure 3.5.1 (a1): MV system and Pole after installation (on April 2017 in Siem Reap province

a.2 Noise disturbance and Vibration

30. According the filed observation, the impacts by noise or vibration were not identified. However, in case PIC uses machinery for cable wire installation, it shall have the ear protected tools due to the noise level over 70 dB(A). Also, contractor shall consider to find the machineries with noise and vibration protection and provide the noise protected tool to workers who work close to this.

Monitoring Report #4 22 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.5.1 (a2): Pole installation (April 2017 in Kampong Thom)

a.3 Surface and Ground Water quality

31. In reality, due to field observation, no significant water bodies were found along the ROW of overhead and underground MV. No impact on surface and groundwater quality occurred as most earthworks were carried out during the dry season.

32. According to project nature, it may not affect to the surface and ground water quality, but it may consider to avoid dredging on place next to canal during raining because it may cause of the erosion to pollute the water next to these activities.

Monitoring Report #4 23 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.5.1 (a3): Condition of some MV Pole next to the canal (on May 2017 in Kampong Thom)

a.4 Soil erosion

33. Soil erosion may not have much concerned due to planting of poles seems very small spot on ground, also it was completed compress after worked. After works, contractor did the good job to compress well to avoid any eroding by wind and rain as above figure. Contractor properly reinstated the sites by backfilling and compacting the foundation of poles and underground cable trenches.

Figure 3.5.1 (a4): Pole Condition after planted (on May 2017 in Kampong Thom)

Monitoring Report #4 24 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

B. Natural resource

34. According to the site observation, there were not forest area identified along the project route line, excepting some place of underground cable in area of APSARA authority. To minimize the impact on existing physical cultural resource in the Angkor Protected Landscape where trees are not allowed to be cut or trimmed and no machineries are to be used. Some trees that are located in ROW in front of residential properties were trimmed and cut to obtain minimum safety clearance with consent from owners who signed voluntary contribution forms.

1. However, there are some planted trees needing to cut with the good negotiation between PIC/EDC and owner. According to some interview with owner of the planted trees, they said that they agreed to cut because they need wood for their cook, and said that some trees are too tall that need to cut. Contractor tries to avoid any clearing trees on the transmission route, some trees were cut only its branches for good environment as the below figure.

Figure 3.5.1 (b-1): Wood from cut trees for MV along the route (on May 2017 in Kampong Cham)C. Waste management

Monitoring Report #4 25 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

C. Waste management

c1. Solid waste

35. According to the site monitor, there was no rubbish from project activities identified for this quarter (April, May, and June). Construction debris were found at some sites, however site cleanup was done soon after works completed.

c2. Liquid waste

36. No liquid wasted is generated from both underground and overhead construction activities.

D. Social Resource

d1. Cultural Heritage

37. As the previous, experienced site manager is staffed by Electricity of Siem Reap to supervise the construction of underground cable in Siem Reap. No chance find was encountered during the reporting period. Extra efforts have been made by EDC to avoid impact on physical cultural resources within Angkor Protected Landscape. So, EDC, PIC and Contractor is working very closed for all of dredging works and other works in the location of ASARA area.

d2. Traffic

38. Also, during site visit, no traffic congestion and accidents were caused by construction activities. However, inadequate warning by placing traffic diversion signs were noted especially around crane truck during offloading concrete poles along the roads at some sites. On-coming traffic was affected and created risks of accidents. Therefore, PIC recommended contractor to put appropriate warning signs such as construction cones around work sites and warning light at dusk to prevent any accident. PIC has good practiced according to the some discussion with some local people.

Monitoring Report #4 26 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.5.1 (d2): Traffic and Road Condition next to the route line (on June 2017 in Kampong Cham)

d3. Safety

39. Contractor carried out the good job after PIC advised for Personal Protective Equipment (PPE). Health and Safety was observed at most sites where workers were found properly wearing Personal Protective Equipment (PPE) such as hard hats, reflective vests. However, this measure still needs to be enforced at some sites. PIC will continuously check the use of safety equipment and improve compliance to Health and Safety at all sites. Site inspector from EDC was working much closed with contractor for patrolling on the PPE too.

Figure 3.5.1(d3-1): Safety Tool for worker during working (on April 2017 in Kampong Thom)

Monitoring Report #4 27 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

3.5.2 From July to September 2017

A. Physical Resource

a.1 Air pollution

40. As the previous observation, the condition of the air quality in the project site was not affected by the project activities. Also, local people did not complain during our discussion during monitoring. Thus, Air pollution is not identified in the project location according to the field observation, dust or smoke generation from construction activities were not identified.

Figure 3.5.2 (a1): MV system and Pole after installation (on 2017 in Siem Reap province)

a.2 Noise disturbance and Vibration

41. According the filed observation, the impacts by noise or vibration were not identified. However, in case PIC uses machinery for cable wire installation, it shall have the ear protected tools due to the noise level over 70 dB(A). Also, contractor shall consider to find the machineries with noise and vibration protection and provide the noise protected tool to workers who working close to this.

Monitoring Report #4 28 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.5.2 (a2): Ear mug Protection from Noise (on August 2017 in Siem Reap)

42. Moreover, PIC improved their works’ safety that all workers shall wear the safety tool/equipment to protect their health during working. As above picture, worker was wearing mug during they are operating the machinery to install cable wire.

a.3 Surface and Ground Water quality

43. According to project nature, it may not affect to the surface and ground water quality, but it may consider to avoid dredging on place next to canal during raining because it may cause of the erosion to pollute the water next to these activities.

44. Most works of foundation for pole planting were completed in dry season. So, no impact on surface and groundwater quality occurred due to most earthworks were carried out during the dry season. Monitoring Report #4 29 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Figure 3.5.2 (a3): Condition of some MV Pole next to the canal (on August 2017 in Kampong Thom)

a.4 Soil erosion

45. All footing of the pole were well compressing after work to avoid the soil erosion by rain. Soil erosion may not have much concerned due to planting of poles seems very small spot on ground, also it was completed compress after worked. As the below pictures, contractor did the good job to compress well. Contractor properly reinstated the sites by backfilling and compacting the foundation of poles and underground cable trenches.

Figure 3.5.2 (a4): Pole Condition after planted (on August 2017 in Kampong Thom)

Monitoring Report #4 30 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

B. Natural resource

46. Some trees that are located in ROW in front of residential properties were trimmed and cut to obtain minimum safety clearance with consent from owners who signed voluntary contribution forms. However, there are some planted trees needing to cut with the good negotiation between PIC/EDC and owner. According to some interview with owner of the planted trees, they said that they agreed to cut because they need wood for their cook, and said that some trees are too tall that need to cut. Contractor tries to avoid any clearing trees on the transmission route, some trees were cut only its branches for good environment as the below figure. Local people always suggested contractor not to remove those cutting trees away, because they need these for wood.

Figure 3.5.2 (b-1): Wood from cut trees for MV along the route (on July and August 2017 in Kampong Cham)

Monitoring Report #4 31 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

C. Waste management

c1. Solid waste

47. According to the site monitor, there was no rubbish from project activities identified for this quarter (July, August, and September). Construction debris were found at some sites, however site cleanup was done soon after works completed. But, most people needed woods from these cutting trees, so they don’t want contractor to remove those away.

c2. Liquid waste

48. No liquid wasted is generated from both underground and overhead construction activities.

D. Social Resource

d1. Cultural Heritage

49. As the previous, experienced site manager is staffed by Electricity of Siem Reap to supervise the construction of underground cable in Siem Reap. No chance find was encountered during the reporting period. Extra efforts have been made by EDC to avoid impact on physical cultural resources within Angkor Protected Landscape. So, EDC, PIC and Contractor is working very closed for all of dredging works and other works in the location of ASARA area.

50. For the overhead MV, contractor also worked very close with local authorities and EDC for some information of cultural heritage in advance before starting work, even those route lines are not in the APSARA area.

d2. Traffic

51. Also, during site visit, no traffic congestion and accidents were caused by construction activities. However, inadequate warning by placing traffic diversion signs were noted especially around crane truck during offloading concrete poles along the roads at some sites. On-coming traffic was affected and created risks of accidents. Therefore, PIC recommended contractor to put appropriate warning signs such as construction cones

Monitoring Report #4 32 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

around work sites and warning light at dusk to prevent any accident. PIC has good practiced according to the some discussion with some local people.

Figure 3.5.2 (d2): Traffic and Road Condition next to the route line (on July 2017 in Manteay Mean Chey)

d3. Safety

52. Contractor carried out the good job after PIC advised for Personal Protective Equipment (PPE). Health and Safety was observed at most sites where workers were found properly wearing Personal Protective Equipment (PPE) such as hard hats, reflective vests. However, this measure still needs to be enforced at some sites. PIC will continuously check the use of safety equipment and improve compliance to Health and Safety at all sites. Site inspector from EDC was working much closed with contractor for patrolling on the PPE too.

Figure 3.5.2 (d3-1): Safety Uniform/Tool for worker during working (on Sept 2017 in Kampong Thom) Monitoring Report #4 33 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

4. Conclusion and Recommendations

4.1 Conclusion

53. Contractor was working on the good practice for most implementation work for this Package. However, all of changes and updated route lines and types of wires shall inform to PIC and EDC to avoid any late to implement the work.

54. It is not much different for this quarterly; contractor was working on the good practice for most implementation work for this Package 1 & 2. However, all of changes and updated route lines and types of wires shall inform to PIC and EDC to avoid any late to implement the work.

4.2 Recommendations

55. As the results of site inspection on environmental issues based on the Environmental Monitoring Matrix, the environmental safeguard specialist recommends in following points to the contractor to take action for the next month:

1. The contractor should practice a simple, common-sense traffic management plan. This should include: 1) placing traffic/warning signs i.e. “Construction in Progress” and creating temporary fences or enclosures by placing traffic cones, also called pylons around parked construction vehicles providing visibility to on- coming motorists; 2) employ traffic control persons to direct traffic during offloading of poles, especially in areas of Angkor Protected Landscape (APL).

2. all of the safety tools must immediately provide to all project workers/staffs in the working to ensure all the workers are properly use ( as safety hats, safety boots, gloves…) during working time.

3. Contractor should adequately provide PPEs to workers; and enforce the H&S guidelines as specified in the EMP. Foreman/Site Manager to regularly give toolbox talk on H&S, site cleanup to workers before works begin.

4. Contractor should follow and regularly implement a simple Waste Management Plan. This should include: 1) site clean-up soon after works are finished; 2) regular toolbox talk which includes site cleanup and chance find Monitoring Report #4 34 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

procedure to be followed at underground cable sites in APL; 3) upon completion of construction works, ROWs should be restored to its original or better condition.

5. Contractor shall work very closed with EDC before and after energize the electricity to the project for testing or any to avoid any accentual matter from this.

6. Contractor and EDC shall work closely with Mr. Resettlement to meet people whenever there are some planted trees needing to cut under the route line.

7. Well informing to local people about project and purpose of this project shall be done before and during project implementing the contraction.

Monitoring Report #4 35 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

ANNEX 1: ENVIRONMENTAL MONITORING MATRIX

Monitoring Report #4 36 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Project: Medium Voltage Sub-Transmission Expansion Sector Project Package 1&2 (ADB Loan No. 2979 CAM(SF)) Monitor(s) Names: Chheang You Sour Contractor Name: KALPATARU Power Transmission Limited / Jong Ro Electric Monitoring Period: Jan ~ March 2017 Weather Conditions: dry season Table 4.1: Environmental Monitoring Matrix

Environmental Mitigation Measures Specific Compliant Remarks Follow-Up Impact/issue Date Item Actions Yes No Contract/EMP Monitored Needed

1). Before · Careful construction practices to avoid damage to July-Sept, cutting all

existing facilities. 2017 trees under · The contractor will be required to select a line the overhead route and location for poles that as much as possible MV, EDC and minimizes the need for tree cutting. contractor · Where cutting or trimming of trees is necessary, need Damage to private property √ trimming will be minimized in accordance with EDC’s discussing minimum clearance requirements. with local · Full reinstatement of land to pre-construction (or residents first. better) condition after construction completion 2). Some · Provide compensation for temporary loss of rubber trees in production in accordance with RP. Kampong Cham · Careful construction practices to avoid damage to existing facilities. July-Sept, · The contractor will be required to select a line 2017 route and location for poles that as much as possible minimizes the need for tree cutting. Damage to private property · Where cutting or trimming of trees is necessary, that may affect to Loss or √ trimming will be minimized in accordance with EDC’s damage to valuable assets minimum clearance requirements. · Full reinstatement of land to pre-construction (or better) condition after construction completion Provide compensation for temporary loss of production in accordance with RP.

37 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Environmental Mitigation Measures Specific Compliant Remarks Follow-Up Impact/issue Date Item Actions Yes No Contract/EMP Monitored Needed

Interference with traffic and · Properly planned and executed traffic blockage of access ways/ management measures supported by good site July-Sept, √ Disruption of services and supervision. 2017 livelihood activities But for short Dust and noise nuisance to · Good construction practice to minimize dust and July-Sept, time in some nearby properties noise nuisance supported by good site supervision. 2017 location only PPEs were July-Sept, provided 2017 adequately to The Contractor workers as shall Human health impacts, boots, gloves, adequately · Construction will be limited to the dry season pollution during working √ ear protected provide PPEs (approximately early November to mid-March) during wet season tools…etc;; also to workers warning signs during working were not well hours installed at the construction site · No temporary or permanent Project facilities shall be established within the APL. Such facilities include July-Sept, but are not limited to, vehicle and maintenance areas, 2017 storage areas for poles, conductors, transformers, It was well pole boring equipment etc. implementation; · Workers will be required to confirm with all APL contractor and rules and requirements. EDC site Encroachment into APL/ · A Chance Find Procedure will be put in place: inspector did the Loss of historical/cultural - If physical cultural resources are √ good monuments/values encountered during the construction phase, all works cooperation with at the find site should be immediately halted. APSARA - The find should be assessed by a authority before competent APSARA Authority expert, and procedures and during to avoid, minimize or mitigate impacts to the physical working. cultural resources should be developed. - Work should not begin until the procedures to avoid, minimize or mitigate impacts to the physical

Monitoring Report #4 38 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Environmental Mitigation Measures Specific Compliant Remarks Follow-Up Impact/issue Date Item Actions Yes No Contract/EMP Monitored Needed

cultural resources have been implemented. - Where avoidance is not feasible, no alternatives to removal exist, and the Project benefits outweigh the anticipated cultural heritage loss from removal, the physical cultural resource should be removed and preserved according to the best available technique. - Any removal should be conducted in accordance with relevant provisions of heritage protection decrees and laws. - Records should be maintained of all finds, including chain of custody instructions for movable finds. - All Project workers and staff should be made aware of the chance-find procedure. As the previous 1). Before July-Sept, time, trees cutting all 2017 under the trees under · The contractor will be required to select a line overhead MV the overhead route and location for poles that as much as possible that have height MV, EDC and minimizes the need for tree cutting. over 3 meters contractor · Where cutting or trimming of trees is necessary, been cut; but it need Tree Removal and Pruning √ trimming will be minimized in accordance with EDC does not have discussing minimum clearance requirements. any complaint with local · Compensation to local residents for loss of trees from local residents first. will be provided in accordance with the RP. residents 2). Some because they rubber trees in also need wood Kampong for cook. Cham It is good July-Sept, practice to use · Contractor to prepare and implement a workers’ PPE during health and safety plan in compliance with Electrical 2017 Health and safety √ work. But it Power Standards of the Kingdom of Cambodia and needs to EDC requirements. adequately provide and

Monitoring Report #4 39 Medium Voltage Sub-Transmission ELECTRICITÉ DU CAMBODGE Expansion Sector Project, Package 1&2

Environmental Mitigation Measures Specific Compliant Remarks Follow-Up Impact/issue Date Item Actions Yes No Contract/EMP Monitored Needed

advise workers more during working hours Contractor should formulate and implement a Waste Management Plan in the worksite as the following: July-Sept, 1). Garbage containers in the construction place at 2017 Waste management work site; √

2). Educate all staffs for proper management of solid waste generated from their works; 3). Clean the worksite after worked;

Monitoring Report #4 40