Henry County Transportation Book June 2021

Prepared by the Henry County Department of Transportation Planning Legend

 ROW Right of Way  UTL Utility  CST Construction  PFPR Preliminary Field Plan Review- meeting to review  FFPR Final Field Plan Review- meeting to review final design construction plans  NTP Notice to Proceed  PTIP Project Team Initiation Process  PIOH Public Information Open House  FY Fiscal Year Georgia Department of Transportation Managed Projects I-75 from I-475 to SR 155 – Commercial GDOT # 0014203, ARC # AR-318

The project is in the project development phase to evaluate project limits, develop design standards, identify environmentally sensitive areas, study existing and future freight and passenger patterns, and identify potential access locations.

Next milestone: Federal environmental approval in 3rd quarter 2022 New on I-75 at Bethlehem Rd GDOT # 0017182, ARC # AR-955A

GDOT has undertaken scoping of the project. Additional funds have been allocated to this project which will be incorporated by ARC in TIP Amendment #3 in fall 2021.

Next milestone: Preliminary engineering in 2022 SR 42/US 23 from South of SR 138 to I-675 GDOT # 322050-

The project team is working towards FFPR submission which is anticipated in fall 2021. ROW acquisition is underway, and a public detour open house virtual website is anticipated to be live by late summer 2021.

Next milestone: FFPR submission Jonesboro from SR 3/US 41 to I-75 GDOT # 342970-

This project has been changed to a local let project.

Next milestone: Concept submission SR 155/Snapfinger Road at Panola Road GDOT # 0013686

This project was let to construction on March 19, 2021.

Next milestone: None SR 42/US 23 from Downtown McDonough to SR 138/North Henry GDOT # 0007855, ARC # HE-107

The project is awaiting NTP on the task order for preliminary design.

Next milestone: PFPR submission SR 155/North McDonough Road from I-75 to SR 42/US 23 GDOT # 0007856, ARC # HE-113

This project is behind schedule. Project team is working towards concept report submission in summer 2021. A PIOH is anticipated in late summer 2021.

Next milestone: Concept submission SR 20/Hampton-McDonough Road from I-75 to Phillips Drive GDOT # 0013531, ARC # 020A

The project team is working towards FFPR in fall 2021. ROW acquisition is underway.

Next milestone: FFPR submission SR 81 at Jackson Lake Rd/Snapping Shoals Rd GDOT # 0013697

The project team is working towards FFPR in summer 2021. ROW acquisition is underway.

Next milestone: FFPR submission on SR 42/US 23 over Norfolk Southern Rd GDOT # 0013995, ARC # HE-201

The project team is working towards FFPR in winter 2021. ROW plans were approved in March 2021 and ROW acquisition is anticipated to begin in spring of 2021. Project let to shelf date to late summer 2022.

Next milestone: FFPR submission Western Parallel Connector from Hudson Bridge Road to Jonesboro Road GDOT # 0014482, ARC # HE-179

The project is behind schedule. The alignment is being redesigned in the area of Mount Olive Road to eliminate impacts to a nearby cemetery. Redesign efforts are underway. ROW acquisition is underway. The project team is working towards FFPR in spring 2022.

Next milestone: FFPR submission SR 81 from East of Lemon to East of Bethany Road GDOT # 0015089, ARC # 005

Constructability Review held on 3/29/21. The project team is working toward PFPR in summer 2021.

Next milestone: PFPR submission Rock Quarry Road from Eagles Landing to SR 138/US 23 GDOT # 0015090, ARC # HE-161A

The project team is working towards having a FFPR in fall 2021. ROW acquisition is underway.

Next milestone: FFPR submission SR 81 at New Morn Drive GDOT # 0015689

The project team is working towards PFPR in winter 2021. Survey files were submitted to SUE office on 3/29/2021 and environmental resource identification activities are underway.

Next milestone: PFPR submission Panola Mountain Greenway – Phase II GDOT # 0015743, ARC # HE-198B

Henry County has approved new design plan for this project but will wait until phase 1 is complete. The project team has been transitioned to the TE program under Mark Lawing as of March 2021.

Next milestone: Concept submission SR 42/US 23 from Bill Gardner Parkway to Peeksville Road GDOT # 0015823, ARC # HE-202

The FFPR inspection is scheduled for 5/5/21. ROW acquisition is underway.

Next milestone: Final plan submission SR 20/North Zack Hilton Parkway at McGarity Road & Lawrenceville Street GDOT # 0015916

The project is behind schedule. The project team is working towards FFPR in summer 2021. PIOH anticipated in spring 2021. ROW plans being revised to municipal separate storm sewer system (MS4) requirements.

Next milestone: FFPR submission SR 42/US 23 from Martin Luther King Junior Boulevard to Marketplace Boulevard GDOT # 0017770

Scoping phase only. Procurement of the design consultant is underway.

Next milestone: Concept submission Bill Gardner Parkway from SR 155 to I-75 GDOT # 0017817, ARC # HE-126B

Scoping phase only. Project framework agreement is in development.

Next milestone: Concept submission SR 920/Jonesboro Road from Clayton County Line to Mount Olive Road GDOT # 0017818, ARC # HE-920M

The email FFPR held on 4/16/21. ROW is certified. Project is working towards a summer 2021 let.

Next milestone: Let to construction Henry County SPLOST Department Managed Projects McDonough Parkway - Construction

Paving, striping, and signage from Henry Parkway to State Route 20/81

Status Update: Binder & topping still to be completed; road to be opened once GDOT completes 20/81 widening & South Ola Road Extension

Intersection Improvement project; realignment from South Ola Road to intersection at State Route 81 & North Ola Road

Status Update: Pre-Construction meeting held with Pittman Construction on 4/12/2021 Lester Mill Road at Bill Gardner Parkway

Intersection improvement project (design only)

Status Update: Traffic study received the week of 12/9/2020. Racetrack Road at Iris Lake

Intersection improvement project

Status Update: Notice to Proceed, for design, issued to American Engineering on 12/14/2020. Traffic study received as of 1/19/2021. Peeksville Rd (Bridge to Old Jackson Rd)

Dirt road project - from Old Jackson Road to Tussahaw Bridge (1.6 miles)

Status Update: Titles and data book ordered for proposed R/W and easement acquisitions. Plans for utility relocations requested as of 4/1/2021. Burg Rd (County Line to Peeksville Rd)

Dirt road project - from County Line to Peeksville Road

Status Update: Field work complete; survey database in progress as of 2/1/2021. Ellistown Road (Peeksville Road to Moccasin Gap Road)

Dirt road project - from Peeksville Road to Moccasin Gap Road (1.06 miles)

Status Update: Notice to Proceed issued to Croy Engineering for design as of 12/14/2020. Sandy Ridge Road (Keys Ferry Road to Stallsworth Road)

Widening project - from Keys Ferry Road to Stallsworth Road (design only), 0.65 mile

Status Update: Survey letters sent to property owners. Survey to begin on 2/15/21 as of 2/1/2021. Flippen Road Extension

Dirt road project - widening & paving from EOP to Jonesboro Road (1.35 miles)

Status Update: Survey to begin on 2/15/2021; letters have been sent to property owners as of 2/1/2021. SR 155 at Greenwood Industrial Parkway

Intersection improvement project

Status Update: Bid award, for construction, went before the Henry County Board of Commissioners on 5/18/2021. Dutchtown Road

Dirt road project - widening & paving from EOP to Jonesboro Road (1.35 miles)

Status Update: Survey complete as of 1/25/2021. Mill Road Improvements

Sidewalk improvement project - from Mt. Carmel Road to Jonesboro Road

Status Update: Working on design RFP as of 10/19/2020. East Lake Road Widening

Widening from SR 155 to SR 20 (design only), 3.7 miles

Status Update: Board of Commissioners awarded the design bid to Croy Engineering as of 12/1/2020. McDonough Parkway (SR 42 to SR 155)- Construction

New Construction from EOP to Turner Church Road, includes a bridge over SR 155 (1 mile)

Status Update: ROW completed in SPLOST IV. Airline Road Extension

New construction from Rodgers Road to intersection of SR 81 & Old Jackson Road (design Only), 0.25 mile

Status Update: Notice to Proceed, for design, issued to EXP US Services; work to begin on 2/8/2021. Snapping Shoals Road

Widening and paving from North Ola Road to River Road (design only), 5 miles

Status Update: Surveying in progress as of 2/2/2021. East Lake Road at Elliott Road

Intersection improvement project (design only)

Status Update: Board of Commissioners awarded design bid to Croy Engineering. East Lake Road at Airline Road

Intersection improvement project (design only)

Status Update: Board of Commissioners awarded design bid to Croy Engineering. East Lake Road at Rowan Drive

Intersection improvement project (design only)

Status Update: Board of Commissioners awarded design bid to Croy Engineering. Road at Willow

Intersection improvement project

Status Update: Surveying for design began as of 11/16/2020. SR 20 at Turner Church Road

Intersection improvement project

Status Update: Bid award, for construction, is scheduled to go before the Henry County Board of Commissioners for approval as of 5/18/2021. North Ola Road at Snapping Shoals Road

Intersection improvement project (design only)

Status Update: Survey work began as of 1/25/2021. Upchurch Road at SR 81

Intersection improvement project (design only)

Status Update: Notice to Proceed has been issued to American Engineering for design. Airline Road at McGarity Road

Intersection improvement project (design only)

Status Update: Notice to Proceed has been issued to American Engineering for design. Survey work has begun. Fairview Road Widening

Widening from Home Depot to Hearn Road, 2.2 miles

Status Update: Notice to proceed issued to Kimley-Horn Engineering for design. Surveying began the week of 2/15/2021. West Village Parkway - Construction

Paving, striping, and signage from Panola Road to County Line

Status Update: Memorandum of Understanding, for construction, approved by both Clayton & Henry Counties. Fairview

From Village Park to DeKalb County Line

Status Update: The Henry County Board of Commissioners awarded the design to Kimley-Horn Engineering.