India Natural Gas

‘Fuel for Growth’

India’s primary energy basket is on the threshold of witnessing a GAIL – BUY quantum jump in contribution from natural gas. While the demand for CMP: Rs451 Target: Rs525 gas has always been strong in the country, availability of transmission

– Doubling gas transmission infrastructure and regulatory issues has restricted supply matching up capacity in two years to the demand growth. However, the medium term outlook has – Exposure to city gas projects improved considerably with 1) increased availability of gas; both and E&P fields value accretive domestic and imports, 2) huge investments in gas pipeline – Huge expansion planned for infrastructure and 3) fast pace implementation of related reforms. the petrochemical segment – Subsidy an overhang, but 1) Improved domestic availability of natural gas: Recently, relatively better placed concerns have been raised with respect to sustenance of current level of gas production in the country given the declining trend of gas production from ’ KG-D6 field. However, we GSPL – BUY believe that in the near term, higher LNG imports will offset the CMP: Rs97 Target: Rs113 impact to some extent, while over the medium to longer term; – Expansion of transmission production at KG-D6 would revive. Furthermore, in the next three capacity to serve rising demand in Gujarat to five years, new fields such as GSPC’s Deendayal field, ONGC’s KG Basin field and Reliance Industries NEC-25 field are expected to – Three cross-country pipelines to add value commence production. Higher LNG import capacities with LNG – Tariffs to remain flattish post terminals of Petronet, Shell and Dabhol project will also add to the PNGRB authorization supply. As per GAIL, domestic production of gas will increase from about 145mmscmd in CY10 to about 215mmscmd by CY15.

2) Better pipeline infrastructure: Lack of adequate pipeline – BUY CMP: Rs370 Target: Rs409 infrastructure has always been a key hindrance in meeting the rising demand for natural gas, especially so in the southern and – Improving CNG economics and wider availability to drive eastern regions. Going ahead, GAIL, which transports more than demand in NCR region 70% of gas available in the country, has embarked upon an aggressive capacity expansion program to double its transmission – Under-penetration to propel demand for PNG capacity over the next three years from about 8,000kms currently.

– Pricing power to enable Companies such as GSPL and Reliance Gas Infrastructure are also margin sustenance adding material capacities in the near future.

3) Reforms have gathered pace: Realizing the importance of gas Petronet LNG – BUY sector, the Indian government has over the past five years, CMP: Rs141 Target: Rs162 implemented significant reforms such as i) raising APM gas prices – Near term LNG demand to and bringing them closer to market price, ii) regulating pipeline remain strong on lower tariffs, iii) streamlining processes for awarding CGD projects and production at KG-D6 field many more. Furthermore, the government is contemplating – Expanding capacities at implementation of gas price pooling, which would even out the opportune time prices for end consumers. – Regasification tariffs would

continue to rise Financial summary

Sales yoy OPM PAT yoy EPS P/E RoE

(Rs mn) (%) (%) (Rs mn) (%) (Rs) (x) (%) FY11E 325,365 30.2 17.0 35,611 13.4 28.1 16.1 19.8

GAIL FY12E 368,258 13.2 18.3 44,269 24.3 34.9 12.9 21.2

FY13E 395,401 7.4 19.2 45,828 3.5 36.1 12.5 18.8

FY11E 10,465 4.6 92.6 5,064 22.4 9.0 10.8 28.4 GSPL FY12E 11,680 11.6 93.3 5,699 12.5 10.1 9.6 25.2 FY13E 12,848 10.0 93.3 6,290 10.4 11.2 8.7 22.5 FY11E 17,505 62.4 28.5 2,598 20.5 18.6 19.9 28.4 IGL FY12E 23,431 33.9 24.8 2,938 13.1 21.0 17.6 26.6 FY13E 30,288 29.3 24.7 3,821 30.0 27.3 13.5 28.3 FY11E 131,973 23.9 9.2 6,196 53.2 8.3 17.1 25.2 Petronet FY12E 185,990 40.9 7.9 6,691 8.0 8.9 15.8 22.8 Research Analyst FY13E 237,469 27.7 7.3 7,600 13.6 10.1 13.9 21.9 Prayesh Jain Source: Company, India Infoline Research [email protected]

June 14, 2011 India Natural Gas

These developments, we believe, have created investment opportunities across the natural gas value chain. Pricing reforms are expected to be beneficial to both producers and LNG importers. While producers will gain from better realizations, LNG importers will benefit from correction in the pricing disparity (making LNG more affordable vis-à-vis domestic gas). Higher gas availability will lead to a jump in volumes for transmission companies. This coupled with stable tariffs would translate into better earnings visibility. City gas companies, which provide last mile connectivity for consumption by industries and vehicles, would also gain from increase in supplies and widening pipeline infrastructure of transmission companies.

We recommend investors to BUY GAIL, GSPL, Indraprastha Gas and Petronet LNG.

GAIL: GAIL, being the nodal gas transmission company in the country is all set to gain from the rising natural gas supplies in the country. The company is in the process of doubling its gas transmission capacity from current 8,000kms. It is also expanding its presence in the city gas business from 15 cities currently to about 50 cities in four years. E&P business will only add value as and when the discoveries are made. It also has aggressive expansion plans for its petrochemical segment. The subsidy overhang, we believe, has already been priced in. We expect FY11-13E revenue and PAT CAGR of 10% and 16% respectively.

GSPL: With Gujarat accounting for about 30% of the natural gas demand in the country and rapid growth in industrialization in the state, the demand for gas is expected to surge. Furthermore, supplies from Petronet LNG and E&P players are also increasing over the medium term. With GSPL widening its transmission network in Gujarat from about 1,900kms currently to 2,400kms, it will be well poised to leverage on this opportunity. New cross-country pipelines will establish it as a nation-wide player. Additionally, its exposure to city gas projects will increase value for the company. We expect FY11-13E revenue and PAT CAGR of 11% and 12% respectively.

Indraprastha Gas: Rising crude oil prices have improved the economic viability of CNG as an auto fuel. IGL, with a virtual monopoly in the NCR region is all set to gain from rising private vehicle conversions to CNG. Under penetration of PNG in both households and the industrial market will drive demand for the fuel. Its expansion beyond the Delhi region will add to its revenue and earnings growth over the medium term. We expect FY11-13E revenue and PAT CAGR of 32% and 21% respectively.

Petronet LNG: With demand-supply for natural gas likely to remain strained in the country, we expect the demand for LNG to continue on a strong trajectory. Petronet is expanding its regasification capacity at Dahej from current 10.5mtpa to 14mtpa by FY14 and its Kochi terminal with a capacity of 2.5mtpa (expandable to 5mtpa) will commence operations in FY13. With majority of the volume on long term contracts and limited risk to regasification charges, earnings visibility remains strong. We expect FY11-13E revenue and PAT CAGR of 34% and 11% respectively.

Sector Report 2 India Natural Gas

Contents Topics Page No Industry section India’s appetite for natural gas to remain strong 4 Robust growth in gas supplies 7 Huge investments in pipeline infrastructure 8 Regulations have gathered pace 8

Company Section GAIL 12 Investment rationale 13 Key concerns 17 Company background 19 Financials 20

GSPL 21 Investment rationale 22 Key concerns 26 Company background 27 Financials 28

Indraprastha Gas 29 Investment rationale 30 Key concerns 34 Company background 35 Financials 37

Petronet LNG 38 Investment rationale 39 Key concerns 42 Company background 43 Financials 44

Sector Report 3 India Natural Gas

India’s appetite for natural gas to remain strong

Primary energy mix to change in favour of natural gas

India’s primary energy consumption has witnessed a CAGR of 6.5% over the last decade as against 9.5% for China, 5.9% for Asia Pacific In India, natural gas accounts for only region and 2.7% for the entire world. Over the next three years, India 10.6% of the primary energy basket is expected to report the second fastest GDP growth in the world. This as compared to global average of 24% would translate into a strong demand for primary energy. The current

primary energy mix is dominated by coal and crude oil, which contributes about 53% and 30% respectively. Natural gas accounts for only 10.6% of the basket as compared to global average of 24%.

Primary energy mix World India China

Hy dro Hydro Renew - Hydro Renew - Nuc lear Renew - Nuc lear pow er pow er Nuc lear pow er ables ables ables Oil Energy 6% Ener gy Oil Energy Oil 5% 1% 7% 18% Natural 1% 1% 30% 1% 0% 5% 34% Gas 4% Coal 30% Coal Natural Natural 52% Gas Coal Gas 11% 70% 24%

Source: BP statistical review 2010, India Infoline Research

India currently consumes about 170mmscmd of gas. Power sector accounts for the maximum demand followed by fertilizers and industries. On the supply side, domestic production is about India currently consumes about 176mmscmd of gas. Power sector 154mmscmd, while remaining is through LNG imports. However, accounts for the maximum demand considering the advantages of natural gas over other fuels, the total followed by fertilizers and industries demand would actually be much higher than the current supply. The demand-supply gap today is estimated to be about 30mmscmd. We believe, this scenario is set to change considering improved supply situation and strengthening pipeline infrastructure in the country. Between 2008 and 2015, IEA expects natural gas demand and production in India to witness a CAGR of 9.8% and 11.1% respectively.

India gas demand growth

Pow er Fertilizer 300 City gas Industrial Petchem/ Refinieries Sponge iron/steel 250 mmscmd 200

150

100

50

0 FY08 FY09 FY10 FY11 FY12

Source: Infraline

Sector Report 4 India Natural Gas

Power deficit at unsustainable levels India’s per capita power consumption is at 700units as compared to While additional gas based capacities 11,000units for USA and 2,800units for China. Furthermore, the power are expected to come on stream over deficit in the country is at 10%. The current gas based power capacity the next few years, demand for gas will be huge even if the current plants in the country is about 17,700MW. For this capacity to operate at a are operated at above 80% PLF plant load factor of 90% more than 85mmscmd of natural gas supply is required, while the allocation currently is about 64mmscmd and the actual supply is even less. Leave apart additional gas-based capacities

that are expected to come on stream over the next few years (NTPC has plans to double its gas based capacity by 2017), demand for gas will be huge even if the current plants are operated at above 80% PLF.

Shortage of gas supply for the power sector

90 Gas req @90% PLF Gas alloted Gas supplied mmscmd 80

70 60

50 40

30 20

10 0 FY10 Apr-10 May-10 Jun-10

Source: Central Electricity Authority

Critical for curtailing fertilizer subsidies Fertilizer subsidy has been of the key factors of a huge fiscal deficit in India. With agriculture GDP expected to remain strong backed by government initiatives, the demand for fertilizers will continue to Higher gas availability to the fertilizer sector will mean lower subsidy burden remain strong. Significant portion of fertilizer production in the country for the government from the fertilizer uses naphtha as the feedstock, a far more expensive fuel relative to sector natural gas. Higher gas availability for the sector will not only improve financial performance of manufacturers, but will also lead to a reduction in subsidy burden for the government. Currently, about 25% of the India’s gas output is supplied to the fertilizer sector.

Trend in fertilizer subsidy burden 800 Rs bn 700 600 500 400 300 200

100 0

FY92 FY94 FY96 FY98 FY00 FY02 FY04 FY06 FY08 FY10 Source: Government of India

Sector Report 5 India Natural Gas

Refineries demand to gain traction India’s refining capacity is set to increase from 184mn tons in FY10 to India’s refining capacity is set to about 240mn tons over the next couple of years. Most refineries are increase from 184mn tons in FY10 to currently using fuel oil, which when replaced with natural gas could about 240mn tons over the next couple of years result in improvement in gross refining margins. RIL’s refineries have a combined demand of 9mmscmd of gas. With India having plans to emerge as a refining hub, usage of gas will allow refiners to be cost effective and improve their competitiveness.

Trend in India’s refining capacity

280

240 mtpa

200

160

120

80

40

0

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Current

FY12 End

Source: Ministry of Petroleum, Industry

City gas demand to witness multi-fold jump Currently, city gas projects are active in more than 25 cities in India. With rising economic advantages of compressed natural gas (CNG)

Rising advantage of CNG over other over petrol or diesel and that of piped natural gas (PNG) over liquefied liquid fuels, will keep demand strong petroleum gas (LPG) or other liquid fuels, the number of cities with for natural gas as a fuel CGD projects is likely to increase rapidly. This will be supported by improved pipeline infrastructure in the country. GAIL has plans to set up CGD projects in about 25 cities over the next couple of years. This would translate into strong demand growth for natural gas from this segment.

Advantage of CNG over petrol and diesel 80%

70%

60%

50%

40%

30%

20%

10%

0% Petrol Diesel

Source: India Infoline Research

Sector Report 6 India Natural Gas

The key impediments for the growth in natural gas consumption were: 1) lack of adequate supply

2) inadequate pipeline infrastructure

3) irrational pricing of natural gas

However, government initiatives along with increased investments in the sector could transform the scenario substantially over the medium term.

Robust growth in gas supplies India currently produces about 154mmscmd and imports about 30mmscmd. Adjusting for internal consumption and flaring, the net available supply is 170mmscmd. This has increased from about India currently produces about 100mmscmd in FY09. The growth was primarily on account of 154mmscmd and imports about commencement of production from RIL’s KG-D6 field, which is 30mmscmd. Adjusting for internal consumption and flaring, the net currently producing ~45mmscmd after reaching a peak of 60mmscmd. available supply is 170mmscmd With the company encountering technical glitches in the field, the production levels might remain flat over the next couple of years. Nevertheless, we believe increased imports of LNG and higher production from domestic fields will offset the impact to a greater extent.

Domestic E&P fields on east coast to drive supply surge India’s east coast, especially the fields in Krisha-Godavari basin are likely to translate into strong gas supply growth over the medium Apart from expected scale-up of RIL’s term. Apart from expected scale-up of RIL’s KG-D6 field (beyond KG-D6 field (beyond FY13), RIL’s D-3, FY13), RIL’s D-3, D-9 blocks, ONGC’s NDA field and GSPC’s Deendayal D-9 blocks, ONGC’s NDA field and field are expected to commence production of gas over the next three GSPC’s Deendayal field are expected to commence production of gas over to four years. Furthermore, RIL’s NEC-25 field is also slated to the next three to four years commence production in the next couple of years. CBM production is set grow multifold from about 0.2mmscmd currently to about 2.6mmsmcd in the next three years.

New LNG terminals and expansion of existing to propel supply Currently, two LNG terminals are in operation Petronet LNG’s Dahej terminal and Shell’s terminal. Together these two plants have a Over the next five years, GAIL’s capacity of 12.5mtpa. While Petronet LNG is increasing its capacity at Dabhol terminal (5mtpa), Petronet LNG’s Kochi terminal (5mtpa), GSPC- Dahej to 14mtpa by FY14, Shell’s Hazira terminal has infrastructure for Adani’s Mundra terminal (6.5mtpa) an additional 2.5mtpa. Over the next five years, GAIL’s Dabhol and IOC’s Ennore terminal (2.5mtpa) terminal (5mtpa), Petronet LNG’s Kochi terminal (5mtpa), GSPC- are expected to commence production Adani’s Mundra terminal (6.5mtpa) and IOC’s Ennore terminal (2.5mtpa) are expected to commence production.

Gas supply break-up 350 Pv t/JV ONGC OIL LNG 300 mmscmd 250

200

150

100

50

0 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 Source: Infraline Sector Report 7 India Natural Gas

Huge investments in pipeline infrastructure The present natural gas transportation infrastructure in the country is around 10,800kms with a capacity to move 270mmsmcd. Over the Over the next 2-3 years, another 7,450kms with a capacity of next 5 years, another 8,000-10,000kms pipeline is likely to be added. 248mmscmd is likely to be added Majority of this would be added to GAIL’s network. Recently, as per media reports, GSPL won bids for three inter-state pipelines totaling 4,000kms. The aim is to have a nation-wide gas transmission network

and add new markets for the fuel. This would widen the reach of gas suppliers and open new markets.

GAIL’s current and future pipeline network

Source: Company

Regulations have gathered pace Increased natural gas availability in the country along with widening PNGRB was set up in March 2006 transmission infrastructure across the country had prompted the government to set up a regulatory board in order to promote fair trade and ensure steady growth for the sector. Consequently, Petroleum and Natural Gas Regulatory Board (PNGRB) was set up in March 2006. The

key functions of PNGRB are as follows:

Protect the interest of consumers by The Board shall- fostering fair trade 1) protect the interest of consumers by fostering fair trade and competition amongst the entities;

2) register entities to-

a) market notified petroleum and petroleum products and, subject to the contractual obligations of the Central Government, natural gas; b) establish and operate liquefied natural gas terminals; c) establish storage facilities for petroleum, petroleum products or natural gas exceeding such capacity as may be specified by regulations; 3) authorise entities to- Authorise entities to build and operated pipelines and city gas a) lay, build, operate or expand a common carrier or contract projects carrier; b) lay, build, operate or expand city or local natural gas distribution network;

Sector Report 8 India Natural Gas

4) declare pipelines as common carrier or contract carrier; 5) regulate, by regulations,- a) access to common carrier or contract carrier so as to ensure fair Regulate tariffs charged by trade and competition amongst entities and for that purpose transmission companies specify pipeline access code;

b) transportation rates for common carrier or contract carrier;

c) access to city or local natural gas distribution network so as to ensure fair trade and competition amongst entities as per

pipeline access code;

6) in respect of notified petroleum, petroleum products and natural

gas-

Monitor prices and take corrective a) ensure adequate availability; measures to prevent restrictive trade b) ensure display of information about the maximum retail prices practice by the entities fixed by the entity for consumers at retail outlets; c) monitor prices and take corrective measures to prevent restrictive trade practice by the entities; d) secure equitable distribution for petroleum and petroleum products; e) provide, by regulations, and enforce, retail service obligations for retail outlets and marketing service obligations for entities; f) monitor transportation rates and take corrective action to prevent restrictive trade practice by the entities; 7) levy fees and other charges as determined by regulations; 8) maintain a data bank of information on activities relating to petroleum, petroleum products and natural gas; 9) lay down, by regulations, the technical standards and specifications including safety standards in activities relating to petroleum, petroleum products and natural gas, including the construction and operation of pipeline and infrastructure projects related to downstream petroleum and natural gas sector; 10)perform such other functions as may be entrusted to it by the Central Government to carry out the provisions of this Act.

Key highlights of the tariff regulations implemented by PNGRB – Post tax ROCE of 14% on capital employed by operators; however, the regulator will scrutinize capital costs – Tariff determination on DCF basis, where the regulator would ascertain operating costs on normative basis, to which ROCE would be added – Marketing exclusivity for the newly-appointed operator for three years and network exclusivity for a period of 25 years – Marketing margins on CNG and PNG to remain out of the regulatory purview

Sector Report 9 India Natural Gas

Key regulations for CGD operations

Geographic area

Based on the criteria of economic viability and contiguity License Period/ Pressure regime Exclusivity

7 barg and above Mktg. – 3yrs Infra – 25yrs from commencement

Reasonable Rate of Return @14% End-user prices Service obligations on Regulator no to look at it unless there’s a PNG domestic complaint Network tariff Allowable mktg. margins DCF CNG compression charges Actual Opex and LUAG

Source: Industry

Pricing of gas: moving towards market prices One of the key reasons discouraging national oil majors ONGC and Oil With increase in APM gas prices, India to increase their gas production was irrational APM gas pricing. government has taken a step towards However, in June 2010, government nearly doubled APM prices. This market determined pricing has made gas producing a positive cash flow business for ONGC and . Even for the private sector, the price decided for RIL’s KG-D6 field was derived as per a formula having linkage to crude prices. These moves have reduced the ambiguity on future pricing of the fuel, thus attracting new bidders to future rounds of NELP.

Domestic gas prices 10 9 US$/mmbtu 8 7 6 5 4 3 2 1 0 PMT Ravva Lakshmi KG-D6 PLNG PLNG Contract Spot

Source: Infraline

Sector Report 10

CCoommppaannyy SSeeccttiioonn

GAIL – BUY

‘Transmitting gains’

Sector: Oil & Gas Prime beneficiary of increased gas supplies Sensex: 18,309 GAIL, being the nodal gas transmission company in the country is all CMP (Rs): 451 set to gain from the rising natural gas supplies in the country. To Target price (Rs): 525 leverage upon the opportunity, the company has embarked upon an aggressive capacity expansion program whereby it plans to double its Upside (%): 16.5 natural gas transmission capacity from current more than 170mmscmd 52 Week h/l (Rs): 536 / 411 (8,000kms) over the next three years. New transmission tariffs have Market cap (Rscr) : 57,151 also been favorable clearing ambiguities on future earnings for the 6m Avg vol (‘000Nos): 1,174 company. No of o/s shares (mn): 1,268 FV (Rs): 10 CGD and E&P businesses to be value accretive GAIL is planning to set up city gas distribution projects in 20 cities Bloomberg code: GAIL IB over the next two years. Price hike of petrol and diesel will only Reuters code: GAIL.BO improve the economics of using CNG vis-à-vis auto fuels. We believe, BSE code: 532155 this venture would be margin accretive for GAIL. To further extend its NSE code: GAIL value chain, GAIL has increased its presence in exploration and Prices as on 14 Jun, 2011 production sector. It currently has 26 E&P and one CBM block. While nine discoveries have been made, it will take a couple of years before Shareholding pattern they achieve any scale. On a longer term perspective, this business March '11 (%) would be value accretive for GAIL. Promoters 57.3 Expansion in petrochemicals business to spur growth Institutions 38.6 GAIL is increasing the petrochemical manufacturing capacity at Pata, Non promoter corp hold 1.2 Uttar Pradesh from 410,000tpa to 500,000tpa. The company is Public & others 2.9 currently evaluating options to scale up the capacity to 800,000tpa. Furthermore, GAIL-led JV (70% stake), Brahmaputra Cracker and Performance rel. to sensex Polymer Limited (BCPL) is implementing the Rs54.6bn Assam Gas (%) 1m 3m 1yr Cracker Project to set up an integrated Petrochemical Complex at GAIL (1.2) (2.5) (7.9) Lepetkata, District Dibrugarh. It will have a capacity of about ONGC (10.6) (3.8) (13.6) 280,000tpa. GAIL also has a 19% stake in ONGC Petro Additions Ltd GSPL (5.9) (2.7) (4.2) (OPaL) which is setting up a 1.1mn tons dual feed cracker. Guj Gas 9.0 (0.9) 33.4 Subsidy an overhang, but relatively better placed In a recent move, the government raised the contribution of upstream Share price trend companies in the subsidy sharing pattern from 33% to 38%. However, GAIL Sensex amongst the upstream companies GAIL’s contribution reduced from 125 9.2% in FY10 to 7% in FY11. While the uncertainty would continue to persist on account of subsidy burden incidence, GAIL’s annuity like 110 business of transmission (50% of the EBIT) provides better relative earnings visibility when compared with other oil PSUs. We recommend 95 BUY with a price target of Rs525.

80 Financial summary Jun-10 Oct-10 Feb-11 Jun-11 Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Revenues 249,964 325,365 368,258 395,401

yoy growth (%) 5.1 30.2 13.2 7.4

Operating profit 46,688 55,324 67,547 75,942 OPM (%) 18.7 17.0 18.3 19.2 Pre-exceptional PAT 31,395 35,611 44,269 45,828 yoy growth (%) 12.0 13.4 24.3 3.5

EPS (Rs) 24.8 28.1 34.9 36.1 P/E (x) 18.2 16.1 12.9 12.5

Price/Book (x) 3.4 3.0 2.5 2.2

EV/EBITDA (x) 11.7 10.4 9.2 9.1

Debt/Equity (x) 0.1 0.1 0.2 0.5 RoE (%) 19.9 19.8 21.2 18.8 RoCE (%) 25.1 24.8 24.6 20.3 Source: Company, India Infoline Research

GAIL

Key beneficiary of the increased gas consumption GAIL, we believe, would be the biggest beneficiary of the rising consumption of gas in the country. The company has been the nodal For FY11, of the total gas availability of gas transmission company in the country. For FY11, of the total gas about 170mmscmd in the country, ~70% was transported via GAIL’s availability of about 170mmscmd in the country, ~70% was pipelines transported via GAIL’s pipelines and ~50% of the gas is marketed by GAIL. With the contribution of gas to India’s primary energy basket set to increase, GAIL would benefit substantially as it embarks upon an aggressive capacity expansion plan over the next few years.

Core business of transmission to see robust growth With RIL’s KG-D6 gas production failing to ramp up to the expected levels of 80mmscmd, concerns were raised on GAIL’s future growth in We expect GAIL to witness a 13% transmission volumes. However, we believe that LNG imports will growth in FY11 and 7% in FY12 in its offset the impact of lower KG-D6 gas production to some extent. We natural gas transmission volumes expect GAIL to witness a 6% growth in FY12 and 8% in FY13 in its natural gas transmission volumes.

Capacity expansion plans on track GAIL has plans to invest US$6bn in capacity expansion over the next three years. Of this, about two-thirds would be directed towards GAIL is doubling its natural gas doubling natural gas transmission capacity from current 170mmscmd. transmission capacity from current Amongst the latest pipeline to commence operation would be the 170mmscmd over the next three years phase II of DVPL pipelines whereby the capacity would increase from 24mmscmd to 78mmscmd (addition of 610kms) by June 2011. Apart from this, additional 6,000kms of pipeline is expected to be added in the next couple of years. The company is also investing close to Rs16bn towards developing spur lines.

GAIL’s pipeline projects Approved Capacity Length Pipeline projects cost (Rs bn) (mmscmd) (km) Status Mainline compressor commissioned at DVPL Pipelines – Phase II Incl. Jabhua and Vijaipur. Standby machine at compressor at Jhabua & Vijaipur 58.4 24 to 78 610 Jhabua by June 11 and Vijaipur Dec 11. VijaipurDadri Pipeline commissioned Vijaipur Dadri pipelines Incl. Compressor Compressor at Kailaras and Chainsa: at Kailaras & Chainsa 49.3 20 to 80 499 Commissioning by Dec 2011 Dadri Bawana Pipeline Commissioned. Bawana Nangal: Commissioning by Dec Dadribawana Nangal Pipeline 23.6 31 594 2011 Chainsa Sultanpur: Commissioned Chainsa-Jhajjar-Hissar Pipeline 13.2 35 349 Sultanpur Neemrana: Commissioned Being implemented in phased manner 2013- Jagdishpur - Haldia Pipeline 76.0 32 2,050 14 onwards

Dhabol Bangalore Pipeline 49.9 16 1,414 Phase I – Aug 2012, Phase II Dec 2012

Kochi-Koottanad-Mangalore / Bangalore 32.6 16 1,126 Phase I - Aug 2012, Phase II Dec 2012 Source: Company

Sector Report 13 GAIL

Revision in tariffs another important step In April 2010, PNGRB announced tariffs for GAIL’s HVJ-DVPL pipeline New tariffs higher than expectation network. While the tariff for the old pipeline was fixed at Rs960/scm, and have now set the tone for tariff determination of the three new cross- the tariff for the expanded pipeline was fixed at Rs2,014/scm. With country gas pipelines being laid by near doubling of the pipeline capacity by April 2011, the blended tariff GAIL works out to Rs1,385/scm, an increase of 45%. The new tariffs have set the tone for tariff determination of the three new cross-country gas pipelines being laid by GAIL.

Realizations of transmission segment

1,000 Rs/'000scm 950 900 850 800

750

700

650 600

Q1FY07 Q2FY07 FY07 Q3 FY07 Q4 FY08 Q1 FY08 Q2 FY08 Q3 FY08 Q4 FY09 Q1 FY09 Q2 FY09 Q3 FY09 Q4 FY10 Q1 FY10 Q2 FY10 Q3 FY10 Q4 FY11 Q1 FY11 Q2 FY11 Q3 FY11 Q4 Source: Company, India Infoline Research

Rising crude oil prices: petchem gains, LPG loses GAIL is part of subsidy sharing mechanism, whereby it shares about 8- 10% of the upstream burden, which is close to one-third of the In a rising crude oil price scenario, industry-wide gross under recoveries. In a rising crude oil price while the petrochemical realizations scenario, the burden on GAIL increases which results in lower will rise, higher subsidy burden will impact LPG segment realizations for its LPG segment. However, the impact is offset by increase in realizations for its petrochemical segment, the prices of which move in tandem with crude oil prices. GAIL uses natural gas as the feedstock for producing petrochemicals, the prices for which remain constant. Hence, the impact of subsidy burden is offset by margin gains in the petrochemical segment.

Realizations of petrochemical segment 160 Crude price (LHS) 100 GAIL petchem realization (RHS) 140 90 US$/bbl Rs/'000 MT 80 120 70 100 60 80 50 60 40 30 40 20 20 10 - -

Q1 FY08 Q1 FY08 Q2 FY08 Q3 FY08 Q4 FY09 Q1 FY09 Q2 FY09 Q3 FY09 Q4 FY10 Q1 FY10 Q2 FY10 Q3 FY10 Q4 FY11 Q1 FY11 Q2 FY11 Q3 FY11 Q4 Source: Company, India Infoline Research

Sector Report 14 GAIL

Expanding presence in city gas business GAIL initiated its presence in the city gas business through forming joint ventures with BG Group ( Ltd) and BPCL GAIL has identified 230 cities for CGD (Indraprastha Gas Ltd). While MGL is present in Mumbai, IGL is projects. By FY14, the company dominant in Delhi and NCR region. Going ahead, GAIL has identified envisages presence in about 50 cities 230 cities for CGD projects. The company envisages presence in about 50 cities by FY14. With cost dynamics substantially in favor of natural gas as a fuel vis-à-vis liquid fuels, the demand is expected to remain strong in the near future. Considering the track record of IGL, we believe, these ventures would add significant value to GAIL.

PNG business locations State City Company Delhi Delhi Noida IGL UP Greater Noida Ghaziabad Mumbai Thane Maharastra Mira-Bhayandar MGL Navi Mumbai Pune Kanpur CUGL Bareilly Uttar Pradesh Lucknow GGL Agra Gujarat Vadodara GAIL Vijaywada Andhra Pradesh Hyderabad BGL Rajahmundery Tripura Agartala TNGCL Dewas GAIL Gas Madhya Pradesh Indore AGL Haryana Sonepat GAIL Gas Source: Company

CNG business locations State City Company Delhi Delhi Noida IGL UP Greater Noida Ghaziabad Mumbai Thane MGL Maharastra Mira-Bhayandar Navi Mumbai Pune MNGL Kanpur CUGL Uttar Pradesh Bareilly Tripura Agartala TNGCL Dewas GAIL Gas Madhya Pradesh Indore AGL Ujaain Haryana Sonepat Maharastra Panvel GAIL Gas Gujarat Vadodara Source: Company

Sector Report 15 GAIL

Presence in E&P segment to be value accretive over longer term GAIL has stakes in 26 oil and gas blocks and one CBM block. Out of the 26 conventional blocks, 8 are onshore blocks while 13 are deepwater and 5 are shallow water blocks. Hydrocarbon discoveries GAIL has stakes in 26 oil and gas have been made in 9 E&P blocks. The blocks are: MN-OSN-2000/2, blocks and one CBM block. CB-ONN-2000/1, Block A-1 and A-3, Myanmar, CY-OS/2, CY-ONN- Hydrocarbon discoveries have been made in 9 E&P blocks 2002/1, AA-ONN-2002/1, CB-ONN-2003/2 and Block-56, Oman. Currently, GAIL has only one block generating revenues, which the company expects to increase to five by FY15. Until March 2011, GAIL had invested Rs23bn across various blocks and the company plans to invest Rs20bn over the next three years.

GAIL’s E&P blocks Sl Block GAIL's PI Operator & PI Non Operating Partners No NELP- II Blocks 1 MN-OSN-2000/2 20% ONGC - 40% IOC - 20%; OIL - 20% 2 CB-ONN-2000/1 50% GSPC - 50% NELP- IV Blocks 3 AA-ONN-2002/1 80% JOGPL - 20% 4 CY-ONN-2002/1 50% JOGPL - 30% GSPC - 20% Farm-in Blocks (Domestic) 5 CY-OS/2 25% HEPI - 75% NELP- V Blocks 6 CB-ONN-2003/2 20% GSPC - 50% JCPL - 20%; GGR - 10% 7 AN-DWN-2003/2 15% Eni India - 40% ONGC - 45% 8 AA-ONN-2003/1 35% JOGPL - 10% GSPC - 20%; JSPL - 35% NELP- VI Blocks 9 CY-DWN-2004/1 10% ONGC - 70% GSPC - 10%; HPCL - 10% 10 CY-DWN-2004/2 10% ONGC - 70% GSPC - 10%; HPCL - 10% 11 CY-DWN-2004/3 10% ONGC - 70% GSPC - 10%; HPCL - 10% 12 CY-DWN-2004/4 10% ONGC - 70% GSPC - 10%; HPCL - 10% 13 CY-PR-DWN-2004/1 10% ONGC - 70% GSPC - 10%; HPCL - 10% 14 CY-PR-DWN-2004/2 10% ONGC - 70% GSPC - 10%; HPCL - 10% 15 KG-DWN-2004/1 10% ONGC - 70% GSPC - 10%; HPCL - 10% 16 KG-DWN-2004/2 10% ONGC - 60% GSPC - 10%; HPCL - 10%; BPRL - 10% 17 KG-DWN-2004/3 10% ONGC - 70% GSPC - 10%; HPCL - 10% 18 KG-DWN-2004/5 10% ONGC - 50% GSPC - 10%; HPCL - 10%; OIL - 10%; BPRL - 10% 19 KG-DWN-2004/6 10% ONGC - 60% GSPC - 10%; HPCL - 10%; OIL - 10% RJ-ONN-2004/1 GSPC (22.225%)- HPCL (22.22%)-Hallworthy (11.11%)-Nitin Fire (11.11%)- 20 22.23% GAIL (22.225%) BPRL (11.11%) 21 KG-ONN-2004/2 40% GSPC - 40% Petrogas - 20% 22 MB-OSN-2004/1 20% GSPC - 20% IOC - 20%; HPCL - 20%; Petrogas - 20% 23 MB-OSN-2004/2 20% Petrogas - 20% IOC - 20%; GSPC - 20%; HPCL - 20% NELP- VII Block 24 CY-ONN-2005/1 40% GAIL - 40% GSPC - 30%; Bengal Energy-30% Farm-in Blocks (Overseas) 25 A-1, Myanmar 8.50% Daewoo – 51% OVL - 17%; KoGas – 8.5%, MOGE – 15% 26 A-3, Myanmar 8.50% Daewoo – 51% OVL - 17%; KoGas – 8.5%, MOGE – 15% CBM Blocks 1 TR-CBM-2005/III 35% Dart Energy - 35% EIG - 15%, Tata Power - 15% Source: Company

Sector Report 16 GAIL

Expansion in petrochemicals… leading to further diversification GAIL currently operates a gas-based integrated plant at Pata, Uttar Current capacity at Pata being Pradesh, with a capacity of producing 410,000tpa of polymers – HDPE expanded to 500,00tpa and LLDPE. An additional gas cracker is being added which will take the total capacity to 500,000tpa. The company is currently evaluating options to further scale up the capacity to 800,000tpa by leveraging synergy of the existing facilities and augmenting these additional facilities.

Furthermore, GAIL-led JV (70% stake), Brahmaputra Cracker and Polymer Limited (BCPL) is implementing the Rs54.6bn Assam Gas GAIL-led JV, Brahmaputra Cracker and Polymer Limited is implementing the Cracker Project to set-up an integrated Petrochemical Complex at Rs54.6bn Assam Gas Cracker Project Lepetkata, District Dibrugarh. The project will be completed in 60 to set-up an integrated Petrochemical months from the date of approval. The petrochemical complex will Complex at Lepetkata having initial comprise a cracker unit, downstream polymer and integrated off- capacity of 280,000tpa site/utilities plants. The complex has been configured with a capacity of 220,000tpa of Ethylene and 60,000tpa of propylene with Natural Gas and Naphtha as feed stock. Recently, licensors for polyethylene and polypropylene technologies for the petrochemical plant have been finalized.

GAIL also has a 19% equity stake in GAIL also has a 19% equity stake in ONGC Petro Additions Ltd (OPaL) ONGC Petro Additions Ltd (OPaL) which is setting up a grass root Mega Petrochemical project in Dahej, which is setting up a grass root Mega Gujarat. The complex will have a 1.1mn ton dual feed cracker and will Petrochemical project in Dahej with a mainly produce HDPE (Swing and Dedicated lines), LLDPE, PP, capacity of 1.1mn tons Benzene, Butadiene, CBFS and Pygas. The plant is expected to commence production by December 2012.

Subsidy an overhang, but relatively better placed In a recent move, the government raised the contribution of upstream companies in the subsidy sharing pattern from 33% to 38%. However, amongst the upstream companies GAIL’s contribution reduced from 9.2% in FY10 to 7% in FY11. While the uncertainty would continue to persist on account of subsidy burden incidence, GAIL’s annuity like business of transmission (50% of the EBIT) provides better relative earnings visibility when compared with other oil PSUs. We recommend BUY with a price target of Rs525.

Key concerns – Higher than expected subsidy burden could dent our profit estimates – Delay in commencement production from new fields or operations at new LNG terminals could impact transmission volumes

Sector Report 17 GAIL

Steady growth in transmission volumes to spur revenue growth During FY11-13E, we expect GAIL to report a revenue CAGR of 10%. The growth will be driven by steady The growth will be driven by steady growth in natural gas transmission growth in natural gas transmission volumes from 106mmscmd in FY10 to about 135mmscmd in FY13E. volumes from 106mmscmd in FY10 to about 135mmscmd in FY13E After a flattish revenue growth for the petrochemical segment in FY11, we expect both volume and realizations growth to drive revenues for the segment. LPG segment revenues would be impacted by the subsidy burden.

Trend in revenue and revenue growth 450,000 Net s ales yoy grow th 35% 400,000 Rs mn 30% 350,000 25% 300,000 20% 250,000 200,000 15% 150,000 10% 100,000 50,000 5%

- 0%

FY07 FY08 FY09 FY10EFY11EFY12EFY13E

Source: Company, India Infoline Research

Margins to remain resilient despite subsidy burden

Robust growth in gas transmission and Natural gas transmission segment which accounts for about 11% of petchem business to keep margins revenues, contributes to about 52% of EBIT with EBIT margins of resilient ~70%. Petrochemicals segment which accounts for 6% of the revenues contributes about 15% of the EBIT with margins of ~35%. With robust revenue growth expected in both these segments, we expect margins to remain resilient.

Trend in EBIT and EBIT margins

80,000 EBIT EBIT Margin (%) 25% 70,000 Rs mn 20% 60,000

50,000 15% 40,000 30,000 10% 20,000 5% 10,000 - 0% FY07 FY08 FY09 FY10EFY11EFY12EFY13E

Source: Company, India Infoline Research

Balance sheet to remain strong in spite of aggressive capex GAIL has aggressive capital expenditure plan of Rs290bn over the next three years, with huge investments in increasing natural gas transmission capacity and petrochemical manufacturing capacity. This would require the company to raise about Rs110bn debt over the same period. In spite of this debt-equity for GAIL is expected to remain comfortable at 0.5x in FY13E.

Sector Report 18 GAIL

Company background

GAIL (India) Limited, is India's flagship Natural Gas company, integrating all aspects of the Natural Gas value chain (including Exploration & Production, Processing, Transmission, Distribution and Marketing) and its related services. In a rapidly changing scenario, the company is moving into a new era of clean fuel industrialisation, creating a quadrilateral of green energy corridors that connect major consumption centres in India with major gas fields, LNG terminals and other cross border gas sourcing points. GAIL is also expanding its business to become a player in the International Market.

Today, GAIL's Business Portfolio includes: – 8,000kms of Natural Gas high pressure trunk pipeline with a capacity to carry 170mmscmd of natural gas across the country – 7 LPG Gas Processing Units to produce 1.2mmtpa of LPG and other liquid hydrocarbons – North India's only gas based integrated Petrochemical complex at Pata with a capacity of producing 410,000tons per annum of Polymers – 1,922 km of LPG Transmission pipeline network with a capacity to transport 3.8mmtpa of LPG – 26 oil and gas Exploration blocks and 1 Coal Bed Methane Blocks – 13,000kms of OFC network offering highly dependable bandwith for telecom service providers – Joint venture companies in Delhi, Mumbai, Hyderabad, Kanpur, Agra, Lucknow, Bhopal, Agartala and Pune, for supplying Piped Natural Gas (PNG) to households and commercial users, and Compressed Natural Gas (CNG) to the transport sector – Participating stake in the Dahej LNG Terminal and the upcoming Kochi LNG Terminal in Kerala – GAIL has been entrusted with the responsibility of reviving the LNG terminal at Dabhol as well as sourcing LNG – GAIL Gas Limited, a wholly owned subsidiary of GAIL (India) Limited, was incorporated on May 27, 2008 for the smooth implementation of City Gas Distribution (CGD) projects. GAIL Gas Limited is a limited company under the Companies Act, 1956. – Established presence in the CNG and City Gas sectors in Egypt through equity participation in three Egyptian companies: Fayum Gas Company SAE, Shell CNG SAE and National Gas Company SAE. – Stake in China Gas Holding to explore opportunities in the CNG sector in mainland China – A wholly-owned subsidiary company GAIL Global (Singapore) Pte Ltd in Singapore

Sector Report 19 GAIL

Financials

Income statement Key ratios Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Y/e 31 Mar FY10 FY11E FY12E FY13E Revenue 249,964 325,365 368,258 395,401 Growth matrix (%) Operating profit 46,688 55,324 67,547 75,942 Revenue growth 5.1 30.2 13.2 7.4 Depreciation (5,618) (6,503) (7,706) (10,406) Op profit growth 14.9 18.5 22.1 12.4 Interest expense (700) (829) (2,655) (6,155) EBIT growth 8.1 14.5 22.1 8.8 Other income 5,411 4,407 5,165 5,165 Net profit growth 12.0 13.4 24.3 3.5 Profit before tax 45,781 52,400 62,351 64,546 Taxes (14,386) (16,789) (18,082) (18,718) Profitability ratios (%) Net profit 31,395 35,611 44,269 45,828 OPM 18.7 17.0 18.3 19.2 EBIT margin 18.6 16.4 17.7 17.9 Balance sheet Net profit margin 12.6 10.9 12.0 11.6 Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E RoCE 25.1 24.8 24.6 20.3 Equity capital 12,685 12,685 12,685 12,685 RoNW 19.9 19.8 21.2 18.8 Reserves 155,305 179,849 213,177 248,065 RoA 11.3 11.5 12.4 10.2 Net worth 167,990 192,533 225,862 260,749 Debt 14,804 23,100 53,100 123,100 Per share ratios (Rs) Def tax liab (net) 13,896 16,332 16,832 17,332 EPS 24.8 28.1 34.9 36.1 Total liabilities 196,689 231,966 295,795 401,182 DPS 8.0 7.5 7.5 7.5 Cash EPS 29.2 33.2 41.0 44.3 Fixed assets 142,616 182,827 250,122 344,716 Book value per share 132.4 151.8 178.1 205.6 Investments 20,730 25,825 25,825 25,825 Net working cap (8,372) 2,000 18,807 29,282 Valuation ratios (x) Inventories 6,317 8,551 10,089 10,833 P/E 18.2 16.1 12.912.5 Sundry debtors 12,950 19,059 21,187 22,749 P/CEPS 15.5 13.6 11.010.2 Other curr assets 76,144 62,538 83,502 98,502 P/BV 3.4 3.0 2.52.2 Sundry creditors (20,318) (26,742) (30,268) (32,499) EV/EBIDTA 11.7 10.4 9.29.1 Other curr liabi (83,466) (61,406) (65,705) (70,304) Cash 41,715 21,314 1,041 1,359 Payout (%) Total assets 196,689 231,966 295,795 401,182 Dividend payout 37.4 30.7 24.7 23.9 Tax payout 31.4 32.0 29.0 29.0 Cash flow statement Y/e 31 Mar (Rs FY10 FY11E FY12E FY13E Liquidity ratios m) Debtor days 19 21 21 21 Profit before tax 45,781 52,400 62,351 64,546 Inventory days 9 10 10 10 Depreciation 5,618 6,503 7,706 10,406 Creditor days 30 30 30 30 Tax paid (14,386) (16,789) (18,082) (18,718)

Working capital ∆ 14,628 (10,372) (16,807) (10,475) Operating Leverage ratios 51,641 31,742 35,168 45,759 cashflow Interest coverage 66.4 64.2 24.5 11.5 Capital Net debt / equity (0.2) 0.0 0.2 0.5 (33,468) (46,714) (75,000) (105,000) expenditure Net debt / op. profit (0.6) 0.0 0.8 1.6 Free cash flow 18,174 (14,972) (39,832) (59,241) Equity raised 637 (127) - - Du-Pont Analysis Investments (3,358) (5,095) - - Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Debt 2,803 8,296 30,000 70,000 Tax burden (x) 0.69 0.68 0.71 0.71 raised/(repaid) Interest burden (x) 0.98 0.98 0.96 0.91 Dividends paid (11,738) (10,941) (10,941) (10,941) EBIT margin (x) 0.19 0.16 0.18 0.18 Other items 636 2,437 500 500 Asset turnover (x) 0.90 1.05 1.03 0.88 Net ∆ in cash 7,154 (20,402) (20,272) 318 Financial leverage (x) 1.76 1.72 1.70 1.84 RoE (%) 19.9 19.8 21.2 18.8

Sector Report 20 GSPL – BUY

‘Expanding boundaries’

Sector: Oil & Gas New sources to add to transmission volumes Sensex: 18,309 Gujarat State Petronet Ltd (GSPL) has a gas pipeline network of CMP (Rs): 97 1,900kms in the state of Gujarat. With Gujarat accounting for about Target price (Rs): 113 30% of the natural gas demand in the country and rapid growth in industrialization in the state, the demand for gas is expected to surge. Upside (%): 16.3 Furthermore, supplies from Petronet LNG and E&P players are also 52 Week h/l (Rs): 128 / 88 increasing over the medium term. This would translate into increased Market cap (Rscr) : 5,466 demand for transmission capacity. GSPL plans to invest about Rs12- 6m Avg vol (‘000Nos): 1,319 15bn during FY12E and FY13E to increase its reach in the state of No of o/s shares (mn): 563 Gujarat. The company aims to have a transmission grid spreading over FV (Rs): 10 2,400kms with an outreach to all 25 districts of Gujarat by end of Bloomberg code: GUJS IB FY12E. We expect GSPL to witness a volume CAGR of 9% during FY11- Reuters code: GSPT.BO 15E. BSE code: 532702 NSE code: GSPL Expansion beyond Gujarat to drive long term revenue growth In the recent past, a consortium led by GSPL (52% stake) won two Prices as on 14 Jun, 2011 bids for cross-country pipelines enabling it to expand its operations

beyond Gujarat. The two pipelines are 1) Mallavaram (Andhra Shareholding pattern Pradesh) to Bhilwara (Rajasthan) – 1,688kms and 2) Mehsana March '11 (%) (Gujarat) to Bhatinda (Punjab) – 1,611kms. Additionally, the company Promoters 37.7 has won the bid for the extension of Mehsana-Bhatinda pipeline up to Institutions 42.0 Srinagar (a stretch of 740kms). The overall investments required for Non promoter corp hold 5.5 the pipeline would be to the tune of Rs122bn. We believe the tenure Public & others 14.8 for laying the pipelines would be in the range of 30-36 months. Hence, these pipelines will contribute substantially to GSPL’s topline growth Performance rel. to sensex beyond FY14. (%) 1m 3m 1yr GSPL (5.9) (2.7) (4.2) Investment in CGD projects a positive GAIL (1.2) (2.5) (7.9) GSPL has 36% stake in GSPC Gas and 13% stake in Sabarmati Gas. IGL 10.5 22.4 49.7 Sabarmati Gas, a JV between BPCL and GSPC has a supply of Guj Gas 9.0 (0.9) 33.4 0.8mmscmd and operates primarily in Mehsana, Gandhinagar and Sabarkatha. GSPC Gas operates in Vapi, Valsad and Navsari with a Share price trend current supply of 3.8mmscmd. We believe that this investment in associate companies with combined sales of ~4.6mmscmd will enable GSPL Sensex GSPL to cash in on the strong growth in CGD. GSPL’s share in profits 140 of these two companies together was about Rs630mn or 12% of GSPL’s FY11 PAT. 120 Financial summary 100 Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E

80 Revenues 10,009 10,465 11,680 12,848 Jun-10 Oct-10 Feb-11 Jun-11 yoy growth (%) 105.3 4.6 11.6 10.0 Operating profit 9,414 9,694 10,896 11,985 OPM (%) 94.1 92.6 93.3 93.3

Pre-exceptional PAT 4,138 5,064 5,699 6,290

Reported PAT 4,138 5,064 5,699 6,290 yoy growth (%) 235.3 22.4 12.5 10.4

EPS (Rs) 7.4 9.0 10.1 11.2 P/E (x) 13.2 10.8 9.6 8.7 Price/Book (x) 3.5 2.7 2.2 1.8 EV/EBITDA (x) 6.9 6.9 6.1 5.6 Debt/Equity (x) 0.8 0.7 0.5 0.4

RoE (%) 29.8 28.4 25.2 22.5 RoCE (%) 26.5 25.6 24.5 24.3 Source: Company, India Infoline Research

GSPL

Increasing gas consumption in Gujarat to propel demand for transmission services With rapid industrialization and increasing gas-based power capacities,

It is estimated that demand for natural it is estimated that demand for natural gas in Gujarat will increase gas in the Gujarat will increase from from about 70mmscmd currently to about 146mmscmd in 2020, a about 70mmscmd currently to about CAGR of 6.9%. Supply is also catching up during the period with 146mmscmd in 2020 expansion of LNG terminals and monetization of new E&P finds. Total

supplies for the state of Gujarat are expected to increase from 47mmscmd currently to about 101mmscmd in 2020, a CAGR of 7.2%. GSPL, with its wide-spread network of 1,900kms in the state and planned expansion projects, is well poised to leverage on the increasing consumption of natural gas in the state.

Power and industrial sector driving demand growth The growth in demand for natural gas in Gujarat will be driven by continued increase in demand from industrial sector along with sharp jump in gas-based power generation capacities. City gas projects are It is expected that contribution of providing further fillip to demand. Currently about 3,411MW capacity power sector to demand for natural in Gujarat is purely based on Natural Gas, while another 810MW is gas in Gujarat will increase from 27% dual fuel (one of which is gas). Going ahead, over the next couple of in 2009 to 29% in 2020, while that of years, about 1,770MW of gas-based capacities are expected to arise in industry will increase from 49% to 50% the state. Additionally, with increasing number of natural gas applications, industrial demand is expected to remain robust. Contribution of power sector to demand for natural gas in Gujarat will increase from 27% in 2009 to 29% in 2020, while that of industry will increase from 49% to 50%.

Sectoral break up of gas demand in Gujarat Trend in gas demand in Gujarat 160 mms c md 2020 13% 140 Pow er 10% 29% 120 27% Fertilizer 100 Industry 2009 Distribution 80 60 49% 14% 8% 40 50% 20

0 2009 2012 2015 2020

Source: Crisil New sources of gas bridging the demand supply gap Post the commencement of natural gas production from Reliance Industries’ KG-D6 field, India’s domestic production has witnessed a Increased gas production and higher quantum leap. At peak production levels of 80mmscmd (if it reaches in LNG terminals capacity in Gujarat have FY14), KG-D6 would be contributing more than 50% to India’s widened supply base domestic production then. About 17mmscmd from 45mmscmd of current production is being supplied in Gujarat. Additionally, completions of expansion of Petronet LNG’s Dahej Terminal to 10mmtpa and Shell’s Hazira Terminal to 3.7mmtpa have further propelled supplies in Gujarat. Going ahead, as GSPC’s discovery in KG Basin and its LNG terminal commence operations, supply would increase further.

Sector Report 22 GSPL

GSPL expanding its presence in Gujarat GSPL currently supplies gas to places such as , Bharuch, Baroda, The company is currently in the Anand, Ahmedabad, Gandhinagar, Himmatnagar, Mehsana, Morbi, process of building additional pipelines Vapi and Jamnagar through its network of 1,900kms of pipeline (trunk in Gujarat, which include Darod- Jafrabad, Mehsana-Palanpur, Mundra and spur lines). The company is in the process of building additional spur lines and Satej Sanand pipelines in Gujarat, which include Darod-Jafrabad, Mehsana-Palanpur, Mundra spur lines and Satej Sanand. This would enable it to increase its transmission volumes until FY14. We expect GSPL to report

volumes of 40mmscmd in FY12E and 44mmscmd in FY13E.

Cross-country pipelines to add substantial value In the recent past, a consortium led by GSPL (52% stake) won two A consortium led by GSPL (52% stake) won two bids for cross-country bids for cross-country pipelines enabling it to expand its operations pipelines Mallavaram to Bhilwara and beyond Gujarat. The two pipelines are 1) Mallavaram (Andhra Mehsana to Bhatinda Pradesh) to Bhilwara (Rajasthan) – 1,688kms and 2) Mehsana (Gujarat) to Bhatinda (Punjab) – 1,611kms. Additionally, the company

has won the bid for the extension of Mehsana-Bhatinda pipeline up to Srinagar (a stretch of 740kms). The overall investments required for the pipeline would be to the tune of Rs122bn. We believe the tenure for laying the pipelines would be in the range of 30-36 months. Hence,

these pipelines will contribute substantially to GSPL’s topline growth beyond FY14.

Mallavaram–Bhilwara Pipeline

The Mallavaram-Bhilwara pipeline will transport gas from the eastern Mallavaram–Bhilwara Pipeline will coast of India to the central region. KG Offshore basin, which accounts connect east coast where bulk of new for more than one-third of the gas production in the country houses production is likely to arise few of India’s largest gas finds. This includes RIL’s KG-D6 field, GSPC’s Deendayal block and ONGC’s KG-DWN-98/2 block. The pipeline will transport gas from the KG basin to the gas-consuming market along the HVJ pipeline in North India and likely to Gujarat. Considering a capacity of 52mmscmd, life of 25 years, tariff of Rs1,150/scm and capital expenditure of Rs65bn we estimate a NPV of Rs24bn. For GSPL’s 52% stake in the consortium, the value works out to Rs22/share. With high element of risks such as delay in executions, increase in capital costs, availability of gas, demand from customers, we assign a 50% discount and add Rs11/share to GSPL’s valuation.

Mehsana-Bhatinda Pipeline Mehsana-Bhatinda pipeline to arise from Gujarat, where LNG imports are As discussed earlier, Gujarat has been the landfall point for imported set to increase at a rapid pace LNG into the country and also Mumbai Offshore, a dominant gas production block in the country is in its vicinity. The Mehsana-Bhatinda pipeline of GSPL will transmit this gas to the northern region of the country. Considering a capacity of 45mmscmd, life of 25 years, tariff of Rs1,250/scm and capital expenditure of Rs45bn we estimate a NPV of Rs24bn. For GSPL’s 52% stake in the consortium, the value works out to Rs22/share. For the aforementioned risks, we assign a 50% discount and add Rs11/share to GSPL’s valuation.

Sector Report 23 GSPL

GSPL Pipelines expansion in Gujarat

Source: Company

GSPL’s cross country pipelines

Source: Company

Sector Report 24 GSPL

Company guides for flat tariffs post authorization from PNGRB As per the PNGRB regulations, natural gas pipeline tariffs will be As per the management, post the calculated by considering a reasonable rate of return on normative implementation of PNGRB regulations level of capital employed plus a normative level of operating expenses tariffs can, at most, decline to Rs0.75/scm in the natural gas pipeline. PNGRB has fixed regulated post-tax RoCE at 12% and pre-tax RoCE at 18% (based on current tax structure). GSPL has submitted the authorization requirements and is awaiting an approval from PNGRB. During FY11, average tariffs were Rs0.8/scm.

As per the management, post the implementation of PNGRB regulations tariffs will continue to remain at the current level.

Take-or-pay nature of agreements secures cash flows

GSPL’s agreements with RIL and have built-in take-or- pay clauses. This means that if the second party to the contract fails to meet its commitment to transmit gas as per the agreement, GSPL can claim capacity charge from it. On an average, capacity charge forms nearly 90% of the tariffs.

Stake in CGD projects through group companies GSPL has picked up strategic stakes in group companies—GSPC Gas, Sabarmati Gas and Krishna Godavari Gas Network Ltd—which are Stakes in city gas projects of GSPC setting up city gas businesses in Gujarat and Andhra Pradesh. City gas Gas Company, Sabarmati Gas, Krishna Godavari Gas to be value accretive as distribution, which includes supply of compressed natural gas for they sell more than 5mmscmd automobiles, will be a natural diversification for GSPL from its transportation business. As in the cases of Indraprastha Gas Ltd and Ltd, the CGD projects are likely to contribute significantly to profit growth for GSPL. We have not factored any upsides in profits or valuations in our model

GSPC Gas Company Ltd – This company marked the foray of GSPC into CGD business. It has a mandate to set up CGD projects in 18 cities across Gujarat, with an investment of Rs15bn. The company is supplying Piped Natural Gas (PNG) to nearly 172,111 domestic households, 734 commercial establishments, 907 industrial customers and operating 71 CNG Stations. The daily gas sales volume is in tune of 3.29mmscmd. The Company plans to setup total 300 CNG Stations by year 2013 in phased manner all across Gujarat.

Sabarmati Gas Ltd, a JV between BPCL and GSPC, was incorporated in June 2006 to set up CGD projects in Gandhinagar, Mehsana and Sabarkantha districts of Gujarat. It has chalked out a business development plan involving a capex of Rs4.1bn.

Krishna Godavari Gas Network Ltd – The company has been set up by INCAP, GSPC and IDFC Private Equity to develop an intra-state transportation grid in Andhra Pradesh.

Sector Report 25 GSPL

FY11-13E revenue CAGR of 8% and PAT CAGR of 13.5% We estimate 8% revenue CAGR during Conservatively, we estimate 8% revenue CAGR during FY11-13E. This FY11-13E. This will be driven by 11% will be driven by 11% volume CAGR. We expect tariffs to remain flat at volume CAGR Rs0.8/scm in FY12E and FY13E. Margins are expected to remain strong as better utilization translates into benefits of operating leverage. As a change of result in depreciation rate in Q3 FY11 and Q4 FY11 depreciation expense declined 45% in FY11. This would translate into earnings CAGR of 11.5% during FY11-13E.

Trend in revenues and yoy growth

14,000 Revenue yoy grow th 120%

12,000 Rs mn 100% 10,000 80% 8,000 60% 6,000 40% 4,000

2,000 20%

- 0% FY07 FY08 FY09 FY10 FY11EFY12EFY13E

Source: Company, India Infoline Research

DCF valuation of Rs113/share, recommend BUY With annuity like cash flows for GSPL, we prefer to value the company on DCF basis. We value its extant pipelines at Rs88/share considering a stable transmission tariff of Rs0.8/scm. Increase in transmission tariffs would result in higher valuations. Further, we value its 52% stake in the three cross-country pipelines at Rs25/share taking the total valuations to Rs113/share. Recommend BUY.

Key concerns – Delay in decision or adverse decision on the pipeline authorization could significantly impact our NPV valuations. – Higher than expected decline in tariffs could dent our earning estimates

Sector Report 26 GSPL

Company background

GSPL, a GSPC Group company, is a pioneer in developing energy transportation infrastructure and connecting natural gas supply basins and LNG terminals to growing markets. GSPL is constantly expanding its pipeline network in Gujarat to reach demand centres by laying a gas pipeline network. The company has developed the requisite expertise and confidence with proven project management competencies.

GSPL is the first pipeline company in India operating on open-access basis and is a pure transmission network. The company’s transmission network envisages development of systematic and seamless pipeline network across Gujarat connecting various suppliers and users. The suppliers of natural gas include traders, producers and LNG terminals. The users comprise industries such as power, fertilizer, steel, chemical plants and local distribution companies.

Key operational milestones for GSPL Year Event FY01 GSPL first Pipeline section Hazira - Mora was commissioned. The section was 36” x 14 kms long. FY02 Commissioning of 24” x 45 kms Amboli - Dahej pipeline. The total length increased to 59 kms.

FY03 Commissioning of 66 kms of gas pipeline, which included 12” X 25 Kms Mora - Utran, 24” x 6.0 Kms Cairn - Mora and 24” x 26 Kms Bhadhut - Paguthan pipelines, and 12” x 5.0 Kms GNFC, 12” x 1.0 Km Videocon and 12” x 3.0 Kms Mora - Kribhco spur lines. The total length increased to 125 kms.

FY04 Commissioning of 24” x 64 Kms Paguthan - Baroda pipeline. The total length increased to 209 kms.

FY05 Commissioning of Baroda – Ahmedabad - Kalol pipeline, GACL - Petronet pipeline, Mora - Sajod pipeline and the Kalol - Santej pipeline. The total grid length increased to 433 kms. Completion of construction of the Gandhinagar spur line, which was 15 kms in length. The total grid length increased to 448 kms.

FY06 Commissioned Anklav Dhuvaran, GFL spurline, NTPC kawas Pipeline projects. The EPC and engineering contracts for Mora - Vapi, Anand - Rajkot, Kalol-Himmatnagar, Kalol - Mehsana and Aanklav - Dhuvaran pipelines are awarded and under execution.

FY07 Commissioning of Mora Vapi, Anand Rajkot Pipeline, Kalol Mehsana Pipeline, Kalol Himmatnagar Pipeline Project.

FY08 Commissioned Torrent connectivity at Surat, Padamla-Halol Pipeline, Petronet LNG connectivity.

FY09 Rajkot - Jamnagar Pipeline on 25.03.2009. FY10 Commissioned Olpad- Utran Pipeline at Surat on 29.10.2009. FY11 Ajanta Spurlines and Jamnagar Spurlines. Morbi Mundra Pipeline, Gana Hadala Pipeline, Euro Spur line. Ajanta Spurline Project. Sumangalam Glass Spurline and Euro-Metrade Spurline Source: Company

Sector Report 27 GSPL

Financials

Income statement Key ratios Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Y/e 31 Mar FY10 FY11E FY12E FY13E Revenue 10,009 10,465 11,680 12,848 Growth matrix (%) Operating profit 9,414 9,694 10,896 11,985 Revenue growth 105.3 4.6 11.6 10.0 Depreciation (2,365) (1,299) (1,631) (1,853) Op profit growth 121.7 3.0 12.4 10.0 Interest expense (938) (961) (880) (880) EBIT growth 158.9 19.5 10.2 9.4 Other income 159 216 225 250 Net profit growth 235.3 22.4 12.5 10.4 Profit before tax 6,269 7,650 8,610 9,502 Taxes (2,131) (2,586) (2,911) (3,212) Profitability ratios (%) Net profit 4,138 5,064 5,699 6,290 OPM 94.1 92.6 93.3 93.3 EBIT margin 72.0 82.3 81.2 80.8 Balance sheet Net profit margin 41.3 48.4 48.8 49.0 Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E RoCE 26.5 25.6 24.5 24.3 Equity capital 5,624 5,626 5,626 5,626 RoNW 29.8 28.4 25.2 22.5 Reserves 10,014 14,440 19,495 25,141 RoA 12.2 12.2 12.2 12.2 Net worth 15,638 20,066 25,121 30,767 Debt 12,595 14,835 13,585 13,585 Per share ratios Def tax liab (net) 1,405 2,641 1,200 1,200 EPS 7.4 9.0 10.1 11.2 Total liabilities 29,639 37,541 39,906 45,552 Dividend per share 0.7 1.0 1.0 1.0 Cash EPS 11.6 11.3 13.0 14.5 Fixed assets 29,754 35,363 38,829 44,840 Book value per share 27.8 35.7 44.7 54.7 Investments 666 766 766 766 Net working cap (2,527) (980) (1,093) (1,203) Valuation ratios (x) Inventories 1,327 623 695 764 P/E 13.2 10.8 9.6 8.7 Sundry debtors 752 698 779 857 P/CEPS 8.4 8.6 7.4 6.7 Other curr assets 3,728 5,286 5,900 6,490 P/B 3.5 2.7 2.2 1.8 Sundry creditors (4,848) (2,894) (3,230) (3,553) EV/EBIDTA 6.9 6.9 6.1 5.6 Other curr liabilities (3,486) (4,692) (5,237) (5,760) Cash 1,746 2,393 1,404 1,149 Payout (%) Total assets 29,639 37,541 39,906 45,552 Dividend payout 10.9 12.7 11.3 10.2 Tax payout 34.0 33.8 33.8 33.8 Cash flow statement Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Liquidity ratios Profit before tax 6,269 7,650 8,610 9,502 Debtor days 27 24 24 24 Depreciation 2,365 1,299 1,631 1,853 Inventory days 48 22 22 22 Tax paid (2,131) (2,586) (2,911) (3,212) Creditor days 177 101 101 101 Working capital ∆ 1,837 (1,547) 114 109 Operating cashflow 8,339 4,816 7,444 8,252 Leverage ratios Capital expenditure (7,987) (6,907) (5,098) (7,863) Interest coverage 7.7 9.0 10.8 11.8 Free cash flow 352 (2,092) 2,346 389 Net debt / equity 0.7 0.6 0.5 0.4 Equity raised (202) 8 - - Net debt / op. profit 1.2 1.3 1.1 1.0 Investments (310) (100) - - Debt raised/repaid 1,086 2,239 (1,250) - Du-Pont Analysis Dividends paid (449) (644) (644) (644) Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Other items 261 1,235 (1,441) - Tax burden (x) 0.66 0.66 0.66 0.66 Net ∆ in cash 738 647 (988) (255) Interest burden (x) 0.87 0.89 0.91 0.92 EBIT margin (x) 0.72 0.82 0.81 0.81 Asset turnover (x) 0.29 0.25 0.25 0.25 Financial leverage (x) 2.45 2.33 2.07 1.85 RoE (%) 29.8 28.4 25.2 22.5

Sector Report 28 Indraprastha Gas – BUY

‘Stepping on the gas’

Sector: Oil & Gas Demand for CNG to remain strong Sensex: 18,309 Over the past one decade, IGL has reported a CNG volume CAGR of CMP (Rs): 370 46% led by 1) mandatory conversion of all public transport vehicles to Target price (Rs): 409 CNG, 2) growing conversion of private vehicles, 3) increased number of stations and higher compressing capacity at stations and 4) Upside (%): 10.5 improving availability of fuel across the NCR region. While demand 52 Week h/l (Rs): 376 / 234 from mandatory conversions might not witness substantial growth, Market cap (Rscr) : 5,181 momentum in private vehicle conversions would continue on the back 6m Avg vol (‘000Nos): 275 of increasing cost advantage of CNG as an auto fuel. We expect IGL to No of o/s shares (mn): 140 witness a 16% CNG volume CAGR during FY11-13E. FV (Rs): 10 Bloomberg code: IGL IB PNG volume growth momentum to continue Reuters code: IGAS.BO IGL currently supplies PNG to about 0.17mn households compared to BSE code: 532514 total of 4.3mn households using LPG. We believe with rising awareness NSE code: IGL about advantages of PNG over LPG (safety and convenience) the acceptance of the fuel will increase at a robust pace. Industrial Prices as on 14 Jun, 2011 segment, which has accounted for significant portion of IGL's PNG

sales will also witness strong growth as cost effectiveness of PNG can Shareholding pattern improve profitability for these players. Compared to Gujarat, where March '11 (%) PNG has a wide acceptance for co-generation, Delhi has been under Promoters 45.0 penetrated. This would keep PNG volume growth strong for IGL. We Institutions 39.4 expect a 30% CAGR in IGL's PNG volumes during FY11-13E. Non promoter corp hold 7.5 Public & others 8.1 Expanding beyond Delhi IGL is now extending its reach beyond Delhi to tap markets of Noida, Performance rel. to sensex Greater Noida and Ghaziabad. PNG would be the key growth segment (%) 1m 3m 1yr in these areas considering fast development of small and medium IGL 10.5 22.4 49.7 industrial units. In Noida and Greater Noida combine, IGL has 11 CNG GAIL (1.2) (2.5) (7.9) stations and more than 3,500 PNG customers. In Ghaziabad the GSPL (5.9) (2.7) (4.2) operations are at a nascent stage with only three CNG stations and a Guj Gas 9.0 (0.9) 33.4 very small number of PNG customers. All three regions have a strong potential and we reckon over the next two to three years these Share price trend markets can contribute about 15-20% of IGL's total volumes.

IGL Sensex Strong earnings visibility, recommend BUY 160 We believe IGL has strong earnings visibility considering rapid 140 conversions of private vehicles to CNG and increasing usage of gas in industries. Superior pricing power will enable them to sustain margins 120 and strong return ratios. Recommend BUY with a 9-month price target 100 of Rs409 (P/E of 15x FY13E EPS).

80 Jun-10 Oct-10 Feb-11 Jun-11 Financial summary Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Revenues 10,781 17,505 23,431 30,288 yoy growth (%) 26.4 62.4 33.9 29.3 Operating profit 3,808 4,987 5,812 7,486

OPM (%) 35.3 28.5 24.8 24.7

Reported PAT 2,155 2,598 2,938 3,821 yoy growth (%) 24.9 20.5 13.1 30.0

EPS (Rs) 15.4 18.6 21.0 27.3 P/E (x) 24.0 19.9 17.6 13.5 Price/Book (x) 6.3 5.1 4.3 3.5 EV/EBITDA (x) 13.2 10.4 8.9 6.8 Debt/Equity (x) 0.0 0.2 0.2 0.1 RoE (%) 28.6 28.4 26.6 28.3

RoCE (%) 41.8 38.1 34.0 37.1 Source: Company, India Infoline Research

Indraprastha Gas

CNG volume growth to remain strong Over the past one decade IGL has reported a CNG volume CAGR of 46% led by 1) mandatory conversion of all public transport vehicles to While demand from mandatory CNG, 2) growing conversion of private vehicles, 3) increased number conversions might not witness substantial growth, momentum in of stations and higher compressing capacity at stations and 4) private vehicle conversions would improving availability of fuel across the NCR region. While demand continue on the back of increasing cost from mandatory conversions might not witness substantial growth, advantage of CNG as a fuel momentum in private vehicle conversions would continue on the back

of increasing cost advantage of CNG as a fuel.

CNG sales volume of IGL Per km cost comparison of diesel vs CNG car 1.6 2.5 mn kgs/day CNG Diesel 1.4 Rs /km 2.0 1.2 1.0 1.5

0.8 1.0 0.6 0.4 0.5

0.2 - -

FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY05 Q1 FY05 Q3 FY06 Q1 FY06 Q3 FY07 Q1 FY07 Q3 FY08 Q1 FY08 Q3 FY09 Q1 FY09 Q3 FY10 Q1 FY10 Q3 FY11 Q1 FY11 Q3 Source: Company Source: Company, IOC

Going ahead, we expect the pace of private car conversion to gather The number of private car conversions momentum as petrol prices have been deregulated and government is has increased from 2,000 per month in also contemplating decontrol of diesel prices. In a rising crude oil price FY08 to about 4,000 per month in FY10 scenario, viability of CNG as an auto fuel will only improve. Furthermore, the penetration of CNG vehicles is substantially lower despite being 10 years into existence. At the end of FY10, compared to a total vehicular population of 4mn only 0.35mn vehicles operated on CNG. As per the management, the number of private car conversions has increased from 2,500 per month previous year to about 5,000 per month in FY11.

In the recent past, OEMs such as Maruti and Hyundai have launched CNG variants of many small cars. Furthermore, radio taxi concept has OEMs such as Maruti and Hyundai gathered substantial momentum in the recent past in the city. Post the have launched CNG variants of many Commonwealth Games, the number of DTC buses have also risen small cars considerably. All these factors will provide additional fillip to IGL's CNG volumes. We expect a 16% CAGR in CNG sales volumes over the next couple of years.

OEM Models on CNG FY11 Total passenger car sales – 1,979,996 Maruti mkt share 49% Hyundai mkt share 18%

Model with CNG % of Maruti Model with CNG % of Hyundai variant vol variant vol Alto 35% i10 45% Wagon R 17% Santro 23% Estilo 5% Accent 4% SX4 2% Source: Crisil, India Infoline Research

Sector Report 30 Indraprastha Gas

Strong CNG infrastructure built up by IGL One of the key hindrances for a quantum jump in private vehicle conversions to CNG has been lack of adequate infrastructure (number of stations or capacity at the stations) in the initial stage. This led to long queues at various stations causing a sentimental impact to the demand. However, over the past few years IGL has adopted three- pronged strategy to widen its infrastructure network.

1) FY2000 to FY04: During this phase, IGL focused on establishing a presence in New Delhi by capturing the prime locations for stations. IGL over the years has built in a wide It increased the number of stations from 30 in FY2000 to 120 in and efficient CNG network across the FY04, while the average compressing capacity per station increased capital from close to 1,000 kgs/day to 13,000 kgs/day. 2) FY05 to FY08: During this period, IGL widened its network by adding new locations (43 stations). The average capacity per station during the period remained in the range of 12,500-13,500 kgs/day. 3) FY09 to FY11: During FY09, the company not only added 18 new stations but also increased the average compression capacity per station to 14,700 kgs/day. In FY10 and FY11, the company added 100 stations and also increased its average compression capacity per station to 18,200 kgs/day.

No of IGL CNG stations Compression capacity of IGL 300 5.5 Nos mn kgs /day 5.0 250 4.5 4.0 200 3.5 3.0 150 2.5 100 2.0 1.5 50 1.0 0.5 - -

FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 Source: Company

Average per station compression capacity Ratio of CNG sales to compression capacity 20.0 0.50 '000 kgs/day x 18.0 16.0 0.45 14.0 0.40 12.0 10.0 0.35 8.0 6.0 0.30 4.0 2.0 0.25 - 0.20 FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11

FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11

Source: Company

Sector Report 31 Indraprastha Gas

PNG volume growth momentum to continue IGL currently supplies PNG to about 0.24mn households compared to total of 4.3mn households using LPG. We believe with rising awareness Under-penetration and rising about advantages of PNG over LPG (safety and convenience) the awareness of PNG’s advantage would acceptance of the fuel will increase at a robust pace. Industrial drive the demand PNG segment, which has accounted for significant portion of IGL's PNG sales will also witness strong growth as cost effectiveness of PNG can improve profitability for these players. Compared to Gujarat, where PNG has a wide acceptance for co-generation, Delhi has been under-

penetrated. This would keep PNG volume growth strong for IGL. We expect a 30% CAGR in IGL's PNG volumes during FY11-13E.

Trend in number of domestic customers for PNG

275,000 Nos 250,000

225,000

200,000 175,000 150,000 125,000

100,000 75,000 50,000 25,000

-

FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11

Source: Company

Strong foothold in Delhi market to continue IGL has been enjoying a virtual monopoly status in Delhi since its inception. However, this was under threat when PNGRB decided to

regulate the sector with a perspective of regulating tariffs and bring in competition. As per the regulations, IGL will continue to have Competition would find difficult to hurt monopoly in marketing till January 2012 and network exclusivity till IGL considering relatively high capital 2025. Post 2012, new players although will be allowed to market the costs and already a wide reach of IGL gas but will have to use IGL's network for transmission. For these services, IGL will receive a fixed charge. We believe competition would be difficult to arise considering IGL's substantially low capital costs and widespread network (2,300kms across Delhi). Going ahead, IGL plans

to further strengthen its network by expanding into areas where it has no presence currently. Furthermore, IGL has tied up long term contracts with DTC, which accounts for 25% of IGL’s CNG volumes and is looking to enter into similar contracts with oil marketing companies.

Expanding beyond Delhi IGL is now extending its reach beyond Delhi to tap markets of Noida, Greater Noida and Ghaziabad. PNG would be the key growth segment

Noida, Greater Noida and Ghaziabad in these areas considering fast development of small and medium have a strong potential and we reckon industrial units. In Noida and Greater Noida together IGL has 11 CNG over the next two to three years these stations and more than 3,500 PNG customers. In Ghaziabad the markets can contribute about 15-20% operations are at a nascent stage with only three CNG stations and a of IGL's total volumes very small number of PNG customers. All three regions have a strong potential and we reckon over the next two to three years these markets can contribute about 15-20% of IGL's total volumes.

Sector Report 32 Indraprastha Gas

IGL CNG penetration in Delhi

Source: Company

IGL’s PNG penetration in Delhi

Source: Company

Sector Report 33 Indraprastha Gas

Financials

30% PNG volume and 16% CNG Strong volume growth to result in 30% revenue CAGR volume CAGR to drive 31% revenue We expect IGL to report a strong volume CAGR of 19% during FY11- CAGR during FY11-13E 13E driven by 16% CNG volume CAGR and 30% PNG volume CAGR. This would translate into a revenue CAGR of 31% during the same period.

Trend in revenues and yoy growth 35,000 70% Net s ales yoy grow th

30,000 60% 25,000 Rs mn 50%

20,000 40% 15,000 30%

10,000 20% 5,000 10%

- 0% FY07 FY08 FY09 FY10 FY11E FY12E FY13E

Source: Company, India Infoline Research

Gross margins to be sustained During FY08-10, IGL has witnessed raw material cost pressures as the government has raised gas prices. Additionally, with IGL current volumes much above its contracted APM (2.2mmscmd) and KG-D6 Pricing power to enable passing of high (0.15mmscmd) gas, contribution of LNG has increased substantially price of R-LNG leading to sustenance and will rise further. With the cost advantage of CNG over petrol and of gross margins diesel, IGL has been able to pass on the hike and maintain its gross margin per unit sold. In the PNG segment, the pricing power is relatively less considering only 5% discount of PNG over domestic LPG. In a rising crude oil price scenario though, IGL will be able to pass on the impact to industrial customers. We expect IGL to report earnings CAGR of 22% during FY11-FY13E.

Strong earnings visibility, recommend BUY We believe IGL has strong earnings visibility considering rapid conversions of private vehicles to CNG and increasing usage of gas in industries. Superior pricing power will enable them to sustain margins and strong return ratios. Recommend BUY with a 9-month price target of Rs409 (P/E of 15x FY13E EPS).

Concerns – Slower than expected roll out of CNG outlets and PNG network in the new territories

– Higher than anticipated increase in cost of natural gas

– Delay in diesel price hike or de-regulation

Sector Report 34 Indraprastha Gas

Company background

IGL was incorporated in 1998, with the prime objective of taking over the City Gas Distribution project from GAIL (India) Ltd. The initial participants in the project were BPCL, GAIL and Government of NCT of Delhi. The objective of the project was to set up infrastructure for CNG and PNG distribution in the NCT of Delhi. With Delhi appearing in the list of the most polluted cities in the world, the Government required to implement the usage of CNG at a rapid pace. IGL has done so quite remarkably and has seen all DTC buses, auto rickshaws and Taxis getting converted to CNG. Latest additions to the list have been LCVs and private cars. IGL has also increased the usage of PNG in the NCT of Delhi. The pace of expansion, however for PNG, has been slower as compared to that of CNG. Nevertheless, the scope of penetration for both the segments continues to remain high.

CNG CNG is a natural gas that is compressed to a pressure of 200- 250kg/cm2(g) (due to its low density) to enhance the vehicle on-board storage capacity. Thus, this compressed form of natural gas is used as a fuel for transportation purposes. With pollution levels reaching alarming levels in Delhi, the Supreme Court issued several directives, which had a major influence on IGL’s operations. Following directives were issued by the apex court: – No 8-year old buses to ply except on CNG or other clean fuels by April 1, 2000. – The entire city bus fleet (DTC and private) to be steadily converted to single fuel mode on CNG by March 31, 2001. Subsequently, the time period for compliance with these directives was extended from time to time by the Supreme Court. – Replacement of all pre-1990 autos and taxis with new vehicles on clean fuels.

Further, on April 5, 2002, the Supreme Court passed an order stating that, among other things, the Union of India and all governmental authorities including IGL shall allocate and make available 16.1 lakh kgs per day (2 MMSCMD) of CNG in the NCT of Delhi by June 30, 2002 for use by the transport sector.

Advantages of using CNG

Green fuel Commonly referred to as the green fuel because of its lead-free and sulphur-free character, CNG reduces harmful emissions. Being non- corrosive, it enhances the longevity of spark plugs. Due to the absence of any lead or benzene content in CNG, the lead fouling of spark plugs, and lead or benzene pollution are eliminated.

Increased life of oils Another practical advantage observed is the increased life of lubricating oils, as CNG does not contaminate and dilute the crankcase oil.

Sector Report 35 Indraprastha Gas

Safety CNG is less likely to auto-ignite on hot surfaces, since it has a high auto-ignition temperature (540 degrees centigrade) and a narrow range (5%-15%) of inflammability. It means that if CNG concentration in the air is below 5% or above 15%, it will not burn. This high ignition temperature and limited flammability range makes accidental ignition or combustion very unlikely.

Low operational cost The operational cost of vehicles running on CNG, as compared to those running on other fuels, is significantly low. At the prevailing price of fuel in Delhi, operational cost of CNG vehicles is 60% lower than petrol and 40% lower than diesel.

PNG PNG is nothing but piped natural gas ie processed natural gas piped to the homes and establishments for the kitchen and home heating like geysers etc. PNG installation inside the premises contains only a limited quantity of natural gas at low pressure around 21 milibar and is much safer compared to LPG which is stored in a liquefied form in a cylinder.

Advantages of PNG

Versatile: Natural Gas is being used predominantly as a versatile fuel for domestic and commercial applications such as cooking, water heating, space heating and air conditioning.

Environment-friendly: Natural Gas is one of the cleanest burning fossil fuels. Its combustion results in virtually no atmospheric emissions of sulphur dioxide (SO2), and far lower emissions of carbon monoxide (CO), reactive hydrocarbons and carbon dioxide, than combustion of other fossil fuels. In fact, when Natural Gas burns completely, it gives out carbon dioxide and water vapour, the same components that human beings exhale while breathing.

Uninterrupted supply: PNG offers the convenience of ensuring continuous and adequate supply at all times, without any problems of storing in cylinders.

Convenient to use: The domestic consumers of LPG are required to order a cylinder refill periodically and wait for its delivery. Switching to PNG renders this entire exercise unnecessary. PNG also eliminates the tedious routine of checking LPG cylinders for any suspected leakage, or it being underweight, at the time of delivery. Moreover, the user is spared the inconvenience of connecting and disconnecting the LPG cylinder when out of gas. Space occupied by LPG cylinders is also saved.

Safe: The combustible mixture of Natural Gas and air does not ignite if the mixture is leaner than 5% and richer than 15% of the fuel:air ratio required for ignition. This narrow inflammability range puts PNG amongst the safest fuels. Natural Gas is lighter than air, therefore, in case of a leak, it rises and disperses into air, given adequate ventilation.

Sector Report 36 Indraprastha Gas

Financials

Income statement Key ratios Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Y/e 31 Mar FY10 FY11E FY12E FY13E Revenue 10,781 17,505 23,431 30,288 Growth matrix (%) Operating profit 3,808 4,987 5,812 7,486 Revenue growth 26.4 62.4 33.9 29.3 Depreciation (775) (1,029) (1,509) (1,859) Op profit growth 26.9 31.0 16.6 28.8 Interest expense 0 (132) (168) (168) EBIT growth 25.3 22.9 14.7 28.9 Other income 211 31 270 270 Net profit growth 24.9 20.5 13.1 30.0 Profit before tax 3,244 3,857 4,405 5,729 Taxes (1,089) (1,259) (1,467) (1,908) Profitability ratios (%) Net profit 2,155 2,598 2,938 3,821 OPM 35.3 28.5 24.8 24.7 EBIT margin 30.1 22.8 19.5 19.5 Balance sheet Net profit margin 20.0 14.8 12.5 12.6 Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E RoCE 41.8 38.1 34.0 37.1 Equity capital 1,400 1,400 1,400 1,400 RoNW 28.6 28.4 26.6 28.3 Reserves 6,854 8,636 10,676 13,518 RoA 21.6 19.1 16.6 17.8 Net worth 8,254 10,036 12,076 14,918 Debt 0 2,098 2,098 2,098 Per share ratios Def tax liab (net) 238 290 290 290 EPS 15.4 18.6 21.0 27.3 Total liabilities 8,493 12,424 14,465 17,307 Dividend per share 4.5 5.0 5.5 6.0 Cash EPS 20.9 25.9 31.8 40.6 Fixed assets 8,340 12,485 15,077 18,218 Book value per share 59.0 71.7 86.3 106.6 Investments 170 170 170 170 Net working cap (1,230) (1,906) (2,754) (3,735) Valuation ratios (x) Inventories 278 480 642 830 P/E 24.0 19.9 17.6 13.5 Sundry debtors 335 671 899 1,162 P/CEPS 17.6 14.2 11.6 9.1 Other curr assets 747 600 600 600 P/B 6.3 5.1 4.3 3.5 Sundry creditors (1,217) (1,679) (2,247) (2,904) EV/EBIDTA 13.2 10.4 8.9 6.8 Other curr liab (1,373) (1,978) (2,648) (3,423) Cash 1,213 1,674 1,972 2,654 Payout (%) Total assets 8,493 12,424 14,465 17,307 Dividend payout 34.1 31.4 30.6 25.6 Tax payout 33.6 32.7 33.3 33.3 Cash flow statement Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Liquidity ratios Profit before tax 3,244 3,857 4,405 5,729 Debtor days 11 14 14 14 Depreciation 775 1,029 1,509 1,859 Inventory days 9 10 10 10 Tax paid (1,089) (1,259) (1,467) (1,908) Creditor days 41 35 35 35 Working capital ∆ 559 675 848 981 Operating cashflow 3,488 4,302 5,295 6,662 Leverage ratios Capital expenditure (3,904) (5,174) (4,100) (5,000) Interest coverage - 30.3 27.2 35.1 Free cash flow (415) (872) 1,195 1,662 Net debt / equity (0.1) 0.0 0.0 (0.0) Equity raised (0) - - - Net debt / op. profit (0.3) 0.1 0.0 (0.1) Investments 872 - - - Debt raised/repaid - 2,098 - - Du-Pont Analysis Dividends paid (735) (816) (898) (980) Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Other items 29 52 - - Tax burden (x) 0.66 0.67 0.67 0.67 Net ∆ in cash (249) 462 298 682 Interest burden (x) 1.00 0.97 0.96 0.97 EBIT margin (x) 0.30 0.23 0.20 0.19 Asset turnover (x) 1.08 1.29 1.32 1.41 Financial leverage (x) 1.32 1.49 1.60 1.59 RoE (%) 28.6 28.4 26.6 28.3

Sector Report 37 Petronet LNG – BUY

‘Opportune player’

Sector: Oil & Gas Gas demand-supply balance favours Petronet Sensex: 18,309 The demand-supply balance for natural gas in the country is expected CMP (Rs): 141 to be stretched over the next few years as 1) demand growth is likely Target price (Rs): 162 to remain strong with newer applications across industries, 2) peak production from RIL’s KG-D6 field delayed and 3) no other major gas Upside (%): 14.9 field going into production in the near term. These factors, we believe 52 Week h/l (Rs): 144 / 77 would translate into strong demand for LNG in the near term. With Market cap (Rscr) : 10,579 Petronet having tied up 7.5mtpa for Dahej and 1.5mtpa for Kochi, it is 6m Avg vol (‘000Nos): 1,964 well poised to gain on the increasing gas deficit. No of o/s shares (mn): 750 FV (Rs): 10 Expanding capacities at opportune time Bloomberg code: PLNG IB Petronet has more than doubled its re-gasification capacity at the Reuters code: PLNG.BO Dahej terminal from 5mtpa in FY08 to 10.5mtpa in FY10. While the re- BSE code: 532522 gasification capacity is much higher, lack of marine facilities will NSE code: PETRONET prevent Petronet from operating beyond 10.5mtpa. Hence, the company is setting up a new jetty, which will allow the company to Prices as on 14 Jun, 2011 scale up its capacity to 14mtpa by FY14. To gain on the rising demand

of gas in southern India, Petronet is setting up a terminal at Kochi Shareholding pattern having an initial capacity of 2.5mtpa is expected to commence March '11 (%) operations in FY13E. The capacity can be further scaled up to 5mtpa. Promoters 50.0 Institutions 21.3 Port and power projects to aid growth Non promoter corp hold 2.3 Petronet is currently setting up a solid cargo port through a JV Public & others 26.4 company; Adani Petronet (Dahej) port, where it has a 26% stake. The project commenced operations in H2 CY10 and involved an investment Performance rel. to sensex of US$270mn (Petronet’s equity share of US$26mn). The company (%) 1m 3m 1yr also plans to set up a 1,200MW gas based power plant at Dahej. The Petronet 5.1 20.4 66.9 construction of the project is likely to commence in CY11. These GAIL (1.2) (2.5) (7.9) projects, we believe, would be earnings and value accretive over the GSPL (5.9) (2.7) (4.2) medium term. Guj Gas 9.0 (0.9) 33.4 Strong earnings visibility Share price trend Petronet has long term sale and purchase agreement for 7.5mtpa of LNG with Rasgas of Qatar. On the customer side, it has offtake Petronet Sensex agreement with GAIL, IOC and BPCL. This provides a strong revenue 180 visibility for Petronet over the longer term. Further, with limited threat 160 to re-gasification margins, earnings visibility is also robust. Over FY11- 140 13E we expect revenue CAGR of 34% and PAT CAGR of 11%. 120 100 Financial summary Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E 80 Jun-10 Oct-10 Feb-11 Jun-11 Revenues 106,491 131,973 185,990 237,469 yoy growth (%) 26.3 23.9 40.9 27.7 Operating profit 8,465 12,163 14,634 17,431 OPM (%) 7.9 9.2 7.9 7.3

Reported PAT 4,045 6,196 6,691 7,600

yoy growth (%) (22.0) 53.2 8.0 13.6

EPS (Rs) 5.4 8.3 8.9 10.1 P/E (x) 26.1 17.1 15.8 13.9 Price/Book (x) 4.7 3.9 3.3 2.8 EV/EBITDA (x) 15.0 11.2 10.4 8.8 Debt/Equity (x) 1.1 1.2 1.5 1.3 RoE (%) 19.2 25.2 22.8 21.9 RoCE (%) 16.3 19.5 18.1 17.0 Source: Company, India Infoline Research

Petronet LNG

Global LNG scenario to keep prices soft over medium term We believe that the global gas scenario is likely to witness substantial changes following sharp increase in production of shale gas in the US.

Against an expected increase in imports of LNG in the US, there are Increased shale gas production in US expectations that the country might start exporting LNG. With a 5% and higher liquefaction capacity in CAGR in shale production over the next decade, gas imports in the US Qatar will keep LNG prices soft over (inclusive of pipeline imports from Canada and LNG imports) are the medium term estimated to account for only 8% of the total consumption as compared to about 11% in 2010. Apart from US, Qatar the largest

exporter of LNG has also scaled up its capacity from nil to 77mtpa over the last 14 years. With supply growth substantially outpacing demand growth, we expect LNG prices to remain soft in the medium term.

Revision in LNG import forecasts for US Gas production and consumption in Qatar 140

120 bcm Production Consumption

100

80

60

40

20

0

CY90 CY92 CY94 CY96 CY98 CY00 CY02 CY04 CY06 CY08 CY10 Source: LNG Journal Source: BP Statistical Review

Domestic demand for LNG to remain strong LNG imports accounted for 20% of natural gas consumption in the With peak production at KG-D6 field country. While the demand for natural gas continues to remain strong, not expected to reach over the near domestic production has not been on expected lines. This is primarily term, LNG demand would offset the supply source on account of delay in peak production from RIL’s KG-D6 field and dawdling on commencement of production from other important deep water blocks. We believe this would translate into strong demand for LNG in the domestic markets.

Expected trend in LNG supplies 90 80 mmscmd

70

60 50 40 30 20 10 0

FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 Source: Infraline

Sector Report 39 Petronet LNG

Expanding domestic gas transmission network to increase market reach for Petronet One of the key reasons restricting the demand growth for LNG has been the lack of gas transmission pipeline capacity along with an Increased transmission network will uneven spatial distribution. Majority of the pipelines are in the western result in access to new markets for and northern India. Southern and Eastern parts of the country are Petronet lagging behind. The current operational LNG terminals are also located mainly in the western India. With GAIL embarking on an aggressive capacity expansion program whereby it plans to double its transmission capacity over the next three years, we believe the demand will get a boost from newer markets within the country.

Petronet expanding capacities at opportune time Petronet has doubled its re-gasification capacity at the Dahej terminal While capacity at Dahej is being from 5mtpa in FY08 to 10.5mtpa in FY10. While the re-gasification expanded from 10.5mtpa to 14mtpa capacity is much higher, lack of marine facilities will not allow Petronet by FY14, Kochi terminal will commence to operate beyond 10.5mtpa. Hence, the company is setting up a new operations with 2.5mtpa capacity and jetty, which will allow the company to scale up its capacity to 14mtpa will be further expanded to 5mtpa by FY14. To gain on the rising demand of gas in the southern India, PLG is setting up a terminal at Kochi having an initial capacity of 2.5mtpa is expected to commence operations in FY13E. The capacity can be further scaled up to 5mtpa.

Petronet capacity expansion trend 20 Dahej Kochi 18 mtpa 16 14 12

10

8

6 4 2 0 FY09 FY10 FY11E FY12E FY13E FY14E FY15E

Source: Company, India Infoline Research

Substantial portion of Petronet volumes on long term contracts For its Dahej plant, Petronet has a long term contract with Rasgas, Qatar for 7.5mn tons. Additionally, the company has tied up 1.1mn tons for FY12 and FY13 while GAIL and GSPC have reserved 0.8mtpa With majority of the volumes on contracts, Petronet’s business is capacity taking the total long term contracts to about 9.4mtpa. This safeguarded from gyrations in means the company would have 1.1mtpa at Dahej for re-gasifying international LNG markets spot cargos, whereby it earns US$0.3/mmbtu marketing margins over and above its re-gasification charges.

For Kochi, Petronet has tied up 1.4mtpa from Exxon Mobil’s Gorgon project in Australia. The company is scouting for other longer term contracts as well.

Sector Report 40 Petronet LNG

Re-gasification charges would continue to rise Petronet’s re-gasification charges for its Dahej terminal were fixed at Rs23.7/mmbtu for CY04 with a 5% escalation per annum. Considering that the current tariffs are at Rs33.35/mmbtu. The original formula With a strained demand supply was based on the capacity of 5mtpa and initial project costs of Rs25bn scenario Petronet will be well placed to to enable the company earn equity IRR of 16%. However, Petronet has take an annual 5% increase in its re- gasification charges increased the capacity since then through de-bottlenecking and new expansion which has brought the per ton capital cost of the project much below the initial estimates. This has enabled the company to earn RoE of more than 20% for the past few years. Market participants have been skeptic of sustenance of such high RoE and are expecting that further increase in re-gas charges would be difficult to come by for the company. However, we believe that strong demand for LNG would allow the company to implement the 5% hike per annum.

Petronet re-gasification charges trend 40.0

35.0 Rs /mmbtu 30.0 25.0 20.0

15.0 10.0 5.0

-

CY04 CY05 CY06 CY07 CY08 CY09 CY10 CY11 CY12 CY13 Source: Company, India Infoline Research

Implementation of gas pooling could be a big positive

Power sector would continue to be the largest consumer of gas in the

Pooling of high-priced LNG with low- country. However, with LNG contracts being expensive than domestic priced domestic gas will ensure that supplies, the power plants would be able to dispatch power only during high-priced LNG is absorbed in the peak requirements. Hence the viability of LNG-based power plants for market base load is impacted. In order to improve dynamics for such plants. the Ministry of Petroleum and Natural Gas has been contemplating pooling of volumes from various domestic fields and LNG terminals. This would make gas more affordable to priority sectors such as power and fertilizer. The mixing of high-priced LNG with low-priced domestic gas will ensure that high-priced LNG is absorbed in the market. Thus, capacities at existing and planned re-gasification terminals would be better utilized leading to direct benefits for players like Petronet.

Port and power projects to aid growth Petronet is currently setting up a solid cargo port through a JV company; Adani Petronet (Dahej) port, where it has a 26% stake. The project has recently commenced operations. It involved an investment of US$270mn (Petronet’s equity share of US$26mn). Petronet also plans to set up a 1,200MW gas based power plant at Dahej. The construction of the project is likely to commence in CY11. These projects, we believe, would be earnings and value accretive over the medium term.

Sector Report 41 Petronet LNG

Strong topline growth led by increased volumes During FY11-13E, we expect Petronet to report a revenue CAGR of 34%. The growth would be primarily driven by increase in volumes Volume growth to drive topline CAGR from 7.5mn tons in FY10 to about 11mn tons in FY13. While we expect of 34% during FY11-13E volumes from Dahej to be at 10mn tons in FY13 from 7.5mn tons in FY10, Kochi terminal is estimated to process 1.2mn tons in its first year of commercial operations. 5% per annum increase in re-gas charges would add to realizations.

Petronet revenue growth

250,000 Total sales yoy grow th 35% 30% 200,000 Rs mn 25%

150,000 20%

100,000 15% 10% 50,000 5%

- 0% FY08 FY09 FY10 FY11E FY12E FY13E

Source: Company, India Infoline Research

Free cash flow positive by FY13 We expect the company to generate robust operating cash flows over the next three years based on strong volume growth. However, capital expenditure related to Kochi terminal will keep the company free cash flow negative until FY13.

Recommend BUY with a target price of Rs162 Considering strong earnings growth expectations in the near term, we prefer to value Petronet on PE basis. We assign a P/E of 16x to FY13E EPS of Rss10.1, arriving at a target price Rs162. We recommend BUY.

Concerns – Spike in LNG prices could lower the demand for spot LNG – Delays in capacity expansion at Dahej and commencement of Kochi terminal could impact our estimates – Steep fall in crude prices could impact the economic viability of LNG vis-à-vis liquid fuels

Sector Report 42 Petronet LNG

Company background

Petronet LNG, incorporated in 1998, was formed as a JV by the Government of India to import LNG and set up LNG terminals in the country. Its promoters are GAIL, ONGC, Limited (IOCL) and Corporation Limited (BPCL). It currently has one terminal at Dahej and is in the process of constructing another at Kochi.

LNG chain

Source: Company, India Infoline Research

Dahej LNG Terminal – Located at West coast, Gujarat (India) in the Gulf of Cambay. – Commenced operations in 2004 with nameplate capacity of 5mtpa. – Capacity expanded to 10mtpa in July, 2009. – Terminal comprising : ƒ 2.5 KM long Jetty with unloading facilities ƒ Four LNG storage tanks (of 148000 CBM each) ƒ Re-gas facilities ƒ Truck loading facilities for onland sales. – 7.5mtpa sourced through Long Term Contract with RasGas, Qatar with back to back sales arrangement with GAIL, IOCL & BPCL. – Additional LNG being sourced through Spot /Short Term Contracts & sold to Offtakers/ Bulk Buyers. – Connected to major trunk pipelines HBJ & DUPL of GAIL and Gujarat’s GSPL Network.

Kochi Terminal – LNG Terminal part of newly created Special Economic Zone & Petronet one of the Codevelopers. – Capacity - 2.5mtpa, being expanded to 5mtpa. – Tied up 1.44mtpa LNG from Exxon Mobil’s Gorgon Venture in Australia. – Work for building two LNG Storage Tanks awarded to IHI, Japan. – Work related to Re-gasification Facilities awarded to CTCI, Taiwan. – Work related to Marine Facilities awarded to Afcons Infrastructure Limited. – Progress on schedule, overall completion 71%, Scheduled Commissioning in Q3 CY12.

Sector Report 43 Petronet LNG

Financials

Income statement Key ratios Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Y/e 31 Mar FY10 FY11E FY12E FY13E Revenue 106,491 131,973 185,990 237,469 Growth matrix (%) Operating profit 8,465 12,163 14,634 17,431 Revenue growth 26.3 23.9 40.9 27.7 Depreciation (1,609) (1,847) (2,182) (3,622) Op profit growth (6.1) 43.7 20.3 19.1 Interest expense (1,839) (1,931) (3,065) (3,065) EBIT growth (10.5) 40.4 18.7 10.4 Other income 978 680 600 600 Net profit growth (22.0) 53.2 8.0 13.6 Profit before tax 5,995 9,064 9,986 11,343 Taxes (1,950) (2,868) (3,295) (3,743) Profitability ratios (%) Net profit 4,045 6,196 6,691 7,600 OPM 7.9 9.2 7.9 7.3 EBIT margin 7.4 8.3 7.0 6.1 Balance sheet Net profit margin 3.8 4.7 3.6 3.2 Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E RoCE 16.3 19.5 18.1 17.0 Equity capital 7,500 7,500 7,500 7,500 RoNW 19.2 25.2 22.8 21.9 Reserves 14,849 19,302 24,267 30,142 RoA 7.1 9.2 7.7 7.3 Net worth 22,349 26,802 31,767 37,642 Debt 24,998 32,161 47,161 47,161 Per share ratios Def tax liab (net) 3,262 3,480 2,692 2,692 EPS 5.4 8.3 8.9 10.1 Total liabilities 50,609 62,443 81,621 87,495 Dividend per share 1.8 2.0 2.0 2.0 Cash EPS 7.5 10.7 11.8 15.0 Fixed assets 42,012 49,053 68,829 74,829 Book value per share 29.8 35.7 42.4 50.2 Investments 5,386 11,649 11,649 11,649 Net working cap (194) 201 582 730 Valuation ratios Inventories 2,223 2,480 3,519 4,493 P/E 26.1 17.1 15.8 13.9 Sundry debtors 5,035 8,472 12,023 15,350 P/CEPS 18.7 13.1 11.9 9.4 Other curr assets 1,554 1,383 1,645 1,965 P/B 4.7 3.9 3.3 2.8 Sundry creditors (6,043) (8,500) (12,063) (15,402) EV/EBIDTA 15.0 11.2 10.4 8.8 Other curr liab (2,963) (3,634) (4,542) (5,678) Cash 3,405 1,540 561 288 Payout (%) Total assets 50,609 62,443 81,621 87,495 Dividend payout 38.0 27.8 25.8 22.7 Tax payout 32.5 31.6 33.0 33.0 Cash flow statement Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Liquidity ratios Profit before tax 5,995 9,064 9,986 11,343 Debtor days 17 23 24 24 Depreciation 1,609 1,847 2,182 3,622 Inventory days 8 7 7 7 Tax paid (1,950) (2,868) (3,295) (3,743) Creditor days 21 24 24 24 Working capital ∆ 2,791 (395) (381) (148) Operating cashflow 8,445 7,648 8,492 11,074 Leverage ratios Capital expenditure (10,465) (8,888) (21,958) (9,622) Net debt / equity 1.0 1.1 1.5 1.2 Free cash flow (2,020) (1,240) (13,466) 1,452 Net debt / op. profit 2.6 2.5 3.2 2.7 Equity raised 5 (18) - - Investments (2,344) (6,263) - - Du-Pont Analysis Debt raised/repaid 2,181 7,163 15,000 - Y/e 31 Mar (Rs m) FY10 FY11E FY12E FY13E Dividends paid (1,536) (1,725) (1,725) (1,725) Tax burden (x) 0.67 0.68 0.67 0.67 Other items 540 218 (788) - Interest burden (x) 0.77 0.82 0.77 0.79 Net ∆ in cash (3,173) (1,865) (979) (273) EBIT margin (x) 0.07 0.08 0.07 0.06 Asset turnover (x) 1.87 1.97 2.15 2.30 Financial leverage (x) 2.70 2.73 2.95 2.98 RoE (%) 19.2 25.2 22.8 21.9

Sector Report 44

Recommendation parameters for fundamental reports: Buy – Absolute return of over +10% Market Performer – Absolute return between -10% to +10% Sell – Absolute return below -10%

Published in 2011. © India Infoline Ltd 2011

This report is for the personal information of the authorised recipient and is not for public distribution and should not be reproduced or redistributed without prior permission.

The information provided in the document is from publicly available data and other sources, which we believe, are reliable. Efforts are made to try and ensure accuracy of data however, India Infoline and/or any of its affiliates and/or employees shall not be liable for loss or damage that may arise from use of this document. India Infoline and/or any of its affiliates and/or employees may or may not hold positions in any of the securities mentioned in the document.

The report also includes analysis and views expressed by our research team. The report is purely for information purposes and does not construe to be investment recommendation/advice or an offer or solicitation of an offer to buy/sell any securities. The opinions expressed are our current opinions as of the date appearing in the material and may be subject to change from time to time without notice.

Investors should not solely rely on the information contained in this document and must make investment decisions based on their own investment objectives, risk profile and financial position. The recipients of this material should take their own professional advice before acting on this information.

India Infoline and/or its affiliate companies may deal in the securities mentioned herein as a broker or for any other transaction as a Market Maker, Investment Advisor, etc. to the issuer company or its connected persons.

This report is published by IIFL ‘India Private Clients’ research desk. IIFL has other business units with independent research teams separated by 'Chinese walls' catering to different sets of customers having varying objectives, risk profiles, investment horizon, etc and therefore, may at times have, different and contrary views on stocks, sectors and markets.

IIFL, IIFL Centre, Kamala City, Senapati Bapat Marg, Lower Parel (W), Mumbai 400 013.

For Research related queries, write to: Amar Ambani, Head of Research at [email protected] or [email protected] For Sales and Account related information, write to customer care: [email protected] or call on 91-44 4007 1000