JIGAWA STATE GOVERNMENT

DUE PROCESS AND PROJECT MONITORING BUREAU OFFICE OF THE EXECUTIVE GOVERNOR

END OF YEAR PROJECTS REPORT

JANUARY TO DECEMBER, 2019

WEB: WWW.JIGAWADUEPROCESS.COM EMAIL: [email protected]

CONTENTS

SECTION (A) - EXECUTIVE SUMMARY SECTION (B) - CHARTS SECTION (C) - PRE-CONTRACTS EVALUATIONS JANUARY TO DECEMBER, 2019 SECTION (D) - CONTRACTS AWARDED JANUARY TO DECEMBER, 2019 SECTION (E) - COMPLETED PROJECTS SECTION (F) - ON-GOING PROJECTS - MINISTRY OF HEALTH - MINISTRY OF WATER RESOURCES - MINISTRY OF WORKS AND TRANSPORT - MINISTRY OF EDUCATION, SCIENCE & TECHNOLOGY - MINISTRY OF LAND AND HOUSING - MINISTRY OF COMMERCE - CAPITAL DEVELOPMENT AUTHORITY - CABINET OFFICE - MINISTRY OF INFORMATION - JIGAWA SATTE POLYTECHNIC, DUTSE - MINISTRY OF FINANCE AND ECONOMIC PLANNING - COLLEGE OF ISLAMIC & LEGAL STUDIES, - BINYAMINU USMAN POLYTECHNIC, - MINISTRY OF ENVIRONMENT - JIGAWA STATE INFORMATICS INSTITUTE, - GOVERNMENT HOUSE - DIRECTORATE OF EONOMIC EMPOWEERMENT - DEPUTY GOVERNOR’S OFFICE

EXECUTIVE SUMMARY. The 2019 Budget termed “Budget for Sustained Economic Growth and Social Transformation 11” was conceived to sustain the momentum of progress towards the attainment of medium-term objective of creating a self-sustaining local economy that fully leverages on productive potentials of the state. Also to continuously improve access to, and quality of, public service delivery particularly in the basic social services sectors including social protection.

In view of the above statement from year 2019 budget speech by His Excellency the Governor, the Bureau as an organ responsible for monitoring the implementation of capital projects hereby present its end of year report.

The end of year 2019 report consists of four sections only: Pre-contract Evaluations, Contracts Awarded, Completed Projects and Ongoing Projects report.

PRE-CONTRACT EVALUATIONS. As at the end of reporting period, projects worth N14,727,910,392.66 only were submitted for vetting out of which the Bureau recommended N14,520,849,570.67 only for execution thereby saving N207,060,821.99 only (1.4%) in favor of the government. This portrays a positive response by government agencies in terms of adequate costing of their projects in line with due process guidelines. Furthermore, this became possible as a result of timely production of the price list data book and compliance with its content by some government agencies accordingly. Though, training on use of procurement planning template has been conducted in the state by State Partnership for Accountability, Responsiveness and Capability (SPARC), however most MDAs are yet to put it to use adequately there by reducing the compliance level of the procurement exercise. It should be noted that this document is expected to be part of budget process requirement as well as procurement process respectively.

CONTRACTS AWARDED. A total of N73.970 billion was budgeted for capital expenditure, both for on-going projects and new ones, representing 47% of the total budget of N157.540 billion in the year 2019. Currently, contracts worth N13.231 billion only were awarded, representing 17.88% of the capital provision. Though it is the practice of the current administration to implement most of the capital intensive projects by means of “Open Tender” process, in 2019 only 71.88% were awarded through that process against the bench mark of 80% as per best practice. It is worth noting that the projects awarded by the open tender process, last year (2018), stand at 93% only. While projects awarded above threshold of N100million, by open competitive process, represent 58.69% only this year against 97% in the previous year 2018. This might not be unconnected with the additional works awarded on some mega ongoing projects in the state, to satisfy the aspirations of the communities in which the projects were sited. Namely it includes some roads projects in Hadejia township, Babura township, Jigawar Danalli, and two hospitals projects in Hadejia and .

Total Contracts Awarded in 2019; -Contracts Awarded by Open Competitive Bidding = N9,510,649,219.70 (71.88%) -Contracts Awarded by Selective Bidding Process = N2,942,639,760.80 (22.24%) - Contracts Awarded by Nominative Bidding Process = N 778,255,567.58 (5.88%) Total = N13,231,544,548.08 (100%)

Contracts Awarded Above Threshold of N100million in 2019; -Contracts Awarded above Threshold (N100 m), by Open Competition = N3,451,823,705.52 (58.69%) -Contracts Awarded above Threshold (N100m), by other method =N 2,429,581,418.90 (41.31%) Total =N 5,881,405,124.42 (100%).

POST CONTRACT EVALUATION. Projects with contract value of N123,576,349,031.75 billion were being reported under this section. Most of the projects, at various stages of completion, were being carried forward from the previous years. It is anticipated that about half of all the on-going projects will be completed by the end of this year if there is stability in capital receipt from the federation account. The only exception that will be carried to preceding years include, among others, Eastern bye pass road i.e western bye pass road i.e. -Galadi-Diginsa- Birniwa road, and others awarded at the end of previous year 2019. While Jigawa University project ,B/kudu new general Hospital, Guri, Garki, Gantsa General hospitals, and Hadejia and Kazaure Specialist Hospitals, will also spill to next year accordingly.

• COMPLETED PROJECTS; This section contains projects that are 100% completed worth N38,803,305,043.60 only, 30.89% of the N123.576 billion projects being reported on. It is worth noting that the percentage achieved is low despite the declaration by government that most of the projects will be completed within the year. This is mainly due to paucity of funds from the federation account. • ON-GOING PROJECTS; The value of on-going projects being reported under this section amounts to N84,773,043,988.15 only (69.11%) of the total under consideration. The figure is staggering and could not be provided for in next year’s budget (2020) to actualize the completion of all on-going projects but rather a percentage of it.

OBSERVATIONS.

It has been observed that there is a lot of improvement by government agencies, to date, in packaging their capital projects for vetting by the Bureau as highlighted in the pre -contract evaluation process whereby 7.3% was saved from vetting exercise within the period. This is largely due to adoption of the revised rates being produced regularly by the Bureau in conjunction with the MDAs of government. Despite this positive trend, absence of a comprehensive procurement plan by MDA’S, reduces the chances of optimum participation by contractors in all bidding process in terms of adequate preparation and also reduce the attainment of full compliance with the existing procurement law.

It was observed that only 72% of contracts awarded by government, this year, followed open competitive tender processes which need to improve in line with best practice, above 80%, to be abreast with donor agencies requirement.

The law provision which requires that for all contracts the value of which is above N10.00 million a performance bank guarantee must be presented is yet to take effect despite several reminders forwarded by the Bureau to government.

The use of Standard Bidding Document (SBD) by agencies during tender process is yet to be complied with in full despite extensive training conducted by SPARC and emphasis made by the Bureau, to achieve compliance with best practice as provided by law.

Many contracts awarded from the previous year are yet to make meaningful progress due to nonpayment of contractual obligations by government, caused by reduction in capital receipt from the federation account.

CONCLUSION/RECOMMENDATION. Government agencies are advice to prepare a comprehensive procurement plan for all the proposed capital projects, approved within the budget, and forward it to the budget department and the Bureau so as to achieve full compliance of the procurement law which will allow every contractor to get prepared for bidding in good time. The use of relevant tender processes, as prescribed by law, should always be considered for the award of contracts for works, goods and services, except in special circumstances where the government direct otherwise, such that the maximum benefit of the system could be harnessed.

The law provision which mandate the presentation of performance bank guarantee by prospective contractors should be activated in the council award letter so as to scare unserious contractors in participating in government business.

All contracts bidding process should be carried out as per Standard Bidding Documented (SBD) presented to each MDA in line with best practice as per law compliance.

Government should set up a Committee to advice on how to generate more revenue and reduce the dependency of capital receipt from the federation account so as to meet the state contractual obligations.

……………………………………… …………………………………… Alh. Garba Halilu Sara Ado Hussaini MON Special Adviser. Director General.

SECTION ( B )

CHARTS

JANUARY TO DECEMBER, 2019

PROJECTS BEING EXECUTED BY MINISTRIES/AGENCIES JANUARY-DECEMBER, 2019

ENVIRONMENT FINANCE JS POLY TECHNIC INFORMATION COMMERCE ECONOMIC EMPOWERMENT

PROJECTS BEING EXECUTED BY MINISTRIES/AGENCIES JANUARY-DECEMBER, 2019

68,210,461,519.59

20,100,894,380.81 15,008,150,836.44 9,653,818,005.82 4,587,643,851.15 2,926,246,754.80 966,545,560.70

WORKS & WATER DCDA EDUCATION HEALTH LAND & HOUSING CABINET OFFICE TRANSPORT RESOURCES

WORKS & TRANSPORT WATER RESOURCES DCDA EDUCATION

HEALTH LAND & HOUSING CABINET OFFICE

PROJECTS BEING EXECUTED BY MINISTRIES/AGENCIES JANUARY-DECEMBER, 2019

204,170,069.67 209,433,611.20 194,446,776.65

91,672,274.72

60,705,065.40

JSCI &LS Ringim Deputy Governor's Office BU Poly Hadejia Govt. House INFORMATIC Kazaure

ANALYSIS OF PROJECTS PERFORMANCE JANUARY-DECEMBER, 2019

Completed, 38,803,305,043.60 , 31%

On-going, 84,773,043,988.15 , 69%

Completed On-going

SECTION ( C )

PRE-CONTRACT EVALUATION

JANUARY TO DECEMBER, 2019

S/N PROJECT IN PROCESS QUOTED SUM DPPM RECOMMENDED SAVING/ REMARKS (N) COST (N) INCREASE

MINISTRY OF HEALTH Proposed Procurement of Beds, Mattresses and Classroom Arm Chairs and Grass Cutting Machines 1 for School 0f Nursing Hadejia. (Revised Scope) 5,328,125.00 5,145,656.25 182,468.75 Min of Health

2 Proposed Renovation works At JIMSO Regional Store Hadejia (Flooding) 11,178,829.58 10,890,818.56 288,011.02 Min of Health Proposed Construction of 1No Basic Health Clinic at Wurno (2019 Second Quarter Constituency 3 project) 17,484,899.82 17,484,899.82 - Min of Health Proposed Construction of Basic Health Center/ Health Clinic in 5No. Constituency Across the State 4 (2019 Constituency project) (bulangu, , Garki, Taura & Dutse) 47,584,342.74 48,333,671.42 (749,328.68) Min of Health Renovation of Male Students Hostel Block D & E old ICT and Security Wire at School of Health 5 Techonology 33,809,059.99 34,156,207.55 (347,147.56) Min of Health Proposed Renov. of Female Student Hostel Storey and New Hostel Block at School of Health 6 Technology Jahun. 5,921,107.22 5,921,078.84 28.38 Min of Health Proposed Constr. Of basic Health Center/Health Clinic in 3No constituency Across the State 7 (Constituency Project 2019) 80,958,192.71 84,318,515.87 (3,360,323.16) Min of Health

8 Propose constr. Of L-1 Maternity Ward 14,971,614.98 17,484,899.82 (2,513,284.84) Min of Health

9 Proposed Constr. Of New General Hospital Birnin Kudu (Variation/Additional work) 594,212,839.12 595,712,672.97 (1,499,833.85) Min of Health

10 Upgrading of Miga Primary Health Care to General Hospital 3,757,000.00 3,625,000.00 132,000.00 Min of Health

11 Proposed Ceiling Work, Standing A/C gate and Road Way at Dutse Central Store (JIMSO) 21,580,549.65 19,373,025.33 2,207,524.32 Min of Health

12 Proposed Upgrading of Primary Health care (PHC) to General Hospital 118,100,478.89 118,379,880.39 (279,401.50) Min of Health

13 Proposed Procurement of 500No. Mattresses to School of Health Technology Jahun 7,500,000.00 7,500,000.00 - Min of Health

14 Proposed Upgrading of maigatari Health Care (PHC) to General Hospital 107,151,264.74 107,252,313.59 (101,048.85) Min of Health Proposed renovation of Dr. Abbas house and Replacement of ridge Cap at GOPD Ward Maternity, 15 Pediatri, Postnatal wards at Dutse General Hospital 2,685,536.00 2,578,536.00 107,000.00 Min of Health Proposed Construction of 40 bed ward 183 meters length liking walk ways (59No. Total module 16 area) at Jahun General Hospital 47,666,736.17 48,440,728.62 (773,992.45) Min of Health Proposed Construction of BHC, 20Beds Ward and Health Post at , Fagam and Taura 17 Constituencies 18,278,424.15 19,425,717.13 (1,147,292.98) Min of Health

18 Proposed renovation/Improvement of PHC 96,052,991.24 91,032,017.12 5,020,974.12 Min of Health

19 Proposed upgrading of Kiyawa primary Health Centre to Cottage Hospital 97,753,082.68 96,214,947.77 1,538,134.91 Min of Health

20 Proposed Renovation / Improvement of kanya Babba PHC (Phase II) 99,872,710.10 94,483,309.50 5,389,400.60 Min of Health

21 Proposed Construction of Student Hostel at College of Nursing and Midwifery Birnin Kudu 83,799,369.99 90,089,863.85 (6,290,493.86) Min of Health

22 Proposed Renovation Construction Maintenance Works at Dutse General Hospital ( laboratory Unit) 8,343,703.18 8,919,296.62 (575,593.44) Min of Health

23 Proposed Upgrading of roni primary health centre to Cottage Hospital (Phase II) 96,202,050.59 96,202,050.59 - Min of Health 24 Proposed Construction and renovation works at Bulangu Cottage Hospital 96,939,259.09 98,846,893.09 (1,907,634.00) Min of Health

Upgrading of Primary Health Center to General Hospital ( Proposed Additional Work) 25 Extension of 407.12 Meters Wall Fencing (117 Modules) 22,164,224.24 23,257,704.02 (1,093,479.78) Min of Health

26 Proposed Renovation of GOPD, Isolation ward, Maternity & OPD at General Hospital 31,908,670.69 33,521,749.27 (1,613,078.58) Min of Health

27 Proposed Improvement of power supply at Ringim General hospital 7,043,482.66 6,883,022.25 160,460.41 Min of Health

28 Proposed Erecting of retaining wall for Erosion control at Rashid Shekoni Specialist Hospital Dutse 4,993,733.00 5,775,774.09 (782,041.09) Min of Health Renewal of contract for the provision of cleaning services (Admin Block and ITS Surroundings ) at 29 Rasheed Shekoni Specialist Hospital Dutse 2,446,742.00 2,446,742.00 - Min of Health

30 Proposed Laterite sand filling and Embankment at Hadin Newly Constructed Basic Health Clinic 3,812,852.00 3,521,326.57 291,525.43 Min of Health 31 Proposed Supply and Installation of Medical Equipment to the Newly Constructed 25No Basic Health Clinic Across the 95,423,350.00 State 95,423,350.00 - Min of Health 32 Proposed Construction of New General Hospital Birnin Kudu (additional works) 594,212,839.12 595,712,672.97 (1,499,833.85) Min of Health Proposed procurement of Beds, Mattresses and Dining Table & Chairs for Dr. Paul at Babura Gen 33 Hospital 1,072,000.00 1,072,000.00 - Min of Health Proposed Procurement of Beds, Mattresses Chairs and Grass Cutting Machine for School of Nursing 34 hadejia 6,070,000.00 5,300,000.00 770,000.00 Min of Health 35 Proposed External Works at Garki General Hospital (additional works) 5,377,542.45 5,377,542.45 - Min of Health 36 Proposed external works at Gantsa General Hospital (additional works) 8,947,304.07 8,947,304.07 - Min of Health

37 Proposed repairs and Services of Radiology Equipment at rasheed Shakoni Specialist Hospital Dutse 5,887,500.00 5,887,500.00 - Min of Health 38 Proposed Repairs Renovation of GOPD Ward and Maternity at Dutse General Hospital 7,807,170.11 8,525,676.79 (718,506.68) Min of Health - MINISTRY OF WATER RESOURCES - Proposed Upgrading and conversion of water schemes at Balago and Bakar Kuka in Dutse Zone and 39 Ringim Zone. 11,951,862.93 11,951,862.93 - STOWA 40 Propsed Rehabilitation of (88No.) Hand Pumps Borehole in 24No. Community of Babura LGA 3,534,825.00 3,364,729.00 170,096.00 RUWASA Proposed Improvement of Reticution and Conversion of 3No. Motorized Boreholes to Solar at Kafin 41 Gana in Birnin kudu LGA 20,515,697.42 20,714,129.42 (198,432.00) STOWA Proposed Rewinding of Flight Pump, High Lift Pump and procurement of Gen. set at Ringim, Kazaure, 42 Dutse and Hadejia Town 9,503,000.00 9,313,000.00 190,000.00 JS Water Board 43 Conversion of Motorized Pumps to Soler Power Schemes at Babura Town, Babura LGA 1,492,710.00 1,452,710.00 40,000.00 JS Water Board 44 Conversion of Motorized Pumps to Soler Power Schemes at LGA 49,928,704.96 49,136,641.39 792,063.57 JS Water Board Conversion of Motorised Pumps to Solar powered schemes at Babura town, Babura LGA (Additional 45 works) 2,551,000.00 2,438,500.00 112,500.00 JS Water Board 46 Proposeed Pipeline Reticulations (28.6KM) in Kazaure Town 537,951,025.00 530,771,054.78 7,179,970.22 Water Board 47 Proposed Construction of 50No. Handpump Across the state 36,897,000.00 36,897,000.00 - STOWA Proposed Construction of New Solar Power Schemes, Conversion and Improvement of motorized 48 Water Schemes in Dutse and its Environment (Revised) 254,346,007.74 249,431,025.31 4,914,982.43 Water Board Proposed Upgrading and Conversion of motorised water supply schemes to Solar Powered at Zareku 49 Town 11,920,254.81 10,905,152.57 1,015,102.24 Stowa 50 Proposed Rehabilitation of (3No) water Suppkly Schemes in Gumel Zone 4,644,281.25 4,644,281.25 - Stowa 51 Proposed Rehabilitation of (18no) water supply Schemes Across the Across the State 10,678,390.00 9,748,615.00 929,775.00 Stowa

52 Proposed Constr. Of 1No. Solar Powered water supply scheme at Kandi in Dutse LGA Zone 6,023,325.00 6,023,325.00 - Stowa Proposed Upgrading and Conversion of 7No Motorised Water Supply Schemes to Solar Powered at 53 Gumel and Birnin Kudu Zone 75,786,760.67 72,494,502.73 3,292,257.94 Stowa Proposed Uprading and Conversion of Motorised Water supply schemes to Solar powered at 54 Sugungun in Ringim Zone 14,002,788.55 12,582,658.31 1,420,130.24 Stowa Proposed Uprading and Conversion of Motorised Water supply schemes to Solar powered at Kadira 55 Small Town Guri LGA 25,794,513.36 22,443,547.29 3,350,966.07 Stowa Proposed for the Constr of New Solar Schemes at New Market Zai/Galadimawa and Improvement at 56 Main And Shuwarin Sabuwa Pump Station, Dutse 25,151,888.00 25,151,888.00 - Min of Water Resources Constr.of New Solar Schemes at New Market, Zai/Galadimawa and improvement at Main and 57 Shuwarin sabuwa Pump Station Dutse 4,967,123.70 4,295,024.00 672,099.70 Min of Water Resources Proposed Uprading and Conversion of Motorised Water supply schemes to Solar powered at Dutse 58 Zone 14,986,568.05 14,561,003.05 425,565.00 Stowa

59 Proposed Constr. Of 1No Solar Powered water supply Scheme at Daki Daka in Garki LGA Ringim Zone 6,023,325.00 6,023,325.00 - Stowa

60 Proposed Constr. Of 1No Solar Powered water supply Scheme at Kunyafa in Babura LGA Ringim Zone 6,023,325.00 6,023,325.00 - Stowa

61 Proposed Constr. Of 1No Solar Powered water supply Scheme at Damfa in Babura LGA Ringim Zone 6,023,325.00 6,023,325.00 - Stowa 62 Proposed Refurbishing of Some Vehicles 19,061,760.38 14,639,493.75 4,422,266.63 Min of Water Resources 63 Proposed Procurement of 12No Tyres tube and liners for the 2No Water Tanks in the Ministry 2,579,720.00 1,564,000.00 1,015,720.00 Min of Water Resources 64 Proposed Constr. Of (504No) of Facilities in Gagarawa LGA 10,899,200.00 10,322,000.00 577,200.00 Ruwasa 65 Proposed Constr. Of (1,641No) of Facilities in Kiyawa LGA (ODF) 36,734,100.00 33,462,843.75 3,271,256.25 Ruwasa 66 Proposed Constr. Of (956No) of Facilities in LGA (ODF) 21,595,600.00 19,527,375.00 2,068,225.00 Ruwasa Proposed constr of New Solar Schemes at New Market, Zai/Galadima and Improvement at main and 67 Shuwaring Sabuwa Pump Station, Dutse (Additional work) 2,515,888.00 2,515,888.00 - Min of Water Resources Upgrading & Conversion of (22No) water supply schemes to solar powered system Across the state 68 (Lot-1) 8,981,385.00 8,923,322.50 58,062.50 Stowa Proposed Upgrading & Conversion of Zaburan small town motorised water supply scheme to solar 69 powered 15,343,500.00 15,343,500.00 - Stowa 70 Proposed upgrading of existing water supply schemes at Gwiwa local Government Area 37,601,902.52 37,833,112.97 (231,210.45) JS Water Board 71 Upgrading and Conversion of 30No Small towns water supply scheme to solar Across the State 6,387,376.80 6,075,265.25 312,111.55 Stowa Proposed rehabilitation of water supply schemes at Babura, Kiri Kasamma & Hadejia in Ringim & 72 Hadejia Zone 7,621,950.00 7,543,200.00 78,750.00 Stowa

73 Proposed rehabilitation of water supply schemes at Auyo, kiri kasamma and Hadejia in Hadejia 7,818,300.00 7,660,800.00 157,500.00 Stowa 74 Proposed construction of (38No) Hand Pump Borehole Across the State 28,041,729.00 28,041,729.00 - Ruwasa 75 Proposed rehabilitation of water supply schemes in Ringim, Kazaure and Dutse Zone 6,555,150.00 6,413,400.00 141,750.00 Stowa Proposed rehabilitation of water supply schemes at Babura and Sule Tankarkar in Ringim and gumel 76 Zone 7,698,600.00 7,541,100.00 157,500.00 Stowa 77 Proposed Construction of (40No) Hand Pumps Borehole Across the state 29,517,600.00 29,517,600.00 - Ruwasa Proposed rehabilitation of water supply schemes at Hadejia, Malam Madori, , Birniwa, Guri 78 and Auyo in Jahun and hadejia Zone 8,070,300.00 7,660,800.00 409,500.00 Stowa Proposed upgrading and conversion of 2No motorized water supply scheme to solar powered at 79 gangara in babura LGA Ringim Zone 6,829,987.50 6,829,987.50 - Stowa 80 Construction of new solar powered water supply schemes at Babura tsallake 1,159,351.26 1,109,750.00 49,601.26 JS Water Board

81 Proposed rehabilitation of 2No Borehole at School of nursing Hadejia 1,373,163.75 1,354,145.63 19,018.12 JS Water Board Proposed Conversion of Motorized Water Schemes to Solar Powered Water Schemes and Some 82 Rehabilitation at College of Education, Gumel 30,197,849.17 29,287,259.96 910,589.21 JS Water Board Proposed Construction of 1No Solar powered water supply scheme at Yannmaulu Tsohuwa in 83 babura & Ringim Zone 6,023,325.00 6,023,325.00 - Stowa Proposed Upgarding and Conversion of motorised water supply schemes to Solar Powered at Ringim 84 Zone 19,228,758.15 18,459,647.97 769,110.18 Stowa 85 Proposed Conversion of Motorised pumps to Solar Powered Schemes at Sule Tankarkar LGA 2,771,126.93 2,797,219.43 (26,092.50) JS Water Board 86 Proposed Rehabilitation of (13No) water supply scheme in Ringim, Kazaure and Gumel 14,032,200.00 12,788,475.00 1,243,725.00 Stowa 87 Proposed Rehabilitation of (19No) Water Supply Schemes in Ringim Zone 20,400,450.00 17,361,750.00 3,038,700.00 Stowa Proposed upgarding and Conversion of motorised water supply schemes to Solar Powered 88 atMaizuwo in Sule Tankarkar Zone 6,829,987.50 6,829,987.50 - Stowa

89 Proposed Rehabilitation of Water supply schemes at Auyo, Kirikasamma and Hadejia in Hadejia zone. 6,555,150.00 6,413,400.00 141,750.00 Stowa Proposed Rehabilitation of 3no Small towns water supply schemes In Birnin Kudu, Ringim and 90 hadejia 7,951,440.00 8,014,597.50 (63,157.50) Stowa 91 Proposed Rehabilitation of 3no Small towns water supply schemes In Gumel and Jahun Zone 4,215,750.00 4,089,750.00 126,000.00 Stowa

92 Proposed Rehabilitation of 3no small Towns water supply schemes in Ringim and Birnin Kudu Zone 7,001,596.88 7,001,596.88 - Stowa Proposed Conctruction of 1no. Solar powered water Supply scheme at Nafara in Kiyawa LGA Dutse 93 Zone 6,023,325.00 6,023,325.00 - Stowa

94 Proposed Rehabilitation of 7no. Small towns water supply schemes in Hadejia, Gumel and jahun Zone 4,940,250.00 4,630,500.00 309,750.00 Stowa 95 Proposed Rehabilitation of 2No Small Towns water supply schemes in Dutse Zone 3,370,500.00 3,370,500.00 - Stowa 96 Proposed Rehabilitation of 2No Small Towns water supply schemes in Birnin Kudu Zone 2,908,500.00 2,887,500.00 21,000.00 Stowa 97 Proposed Procument of Generating set for Kazaure and Birnin Kudu Zone 28,615,253.66 28,619,712.07 (4,458.41) JS Water Board 98 Proposed Over Hauling of Generating sets across the state 9,781,910.00 9,171,892.50 610,017.50 JS Water Board 99 Proposed Rehabilitation of 6No Small towns water supply schemes in Hadejia, Gumel and Jahun Zone 5,362,035.00 5,047,035.00 315,000.00 Stowa 100 Rehabilitation of water supply schemes at town (Additional Works) 708,660.75 708,660.75 - JS Water Board Proposed Construction of New Solar Schemes ay Yalwawa, Malam Inuwa Dutse Housing Estate 101 (MIDEH) and & 744 Danmasara 99,856,958.51 98,158,678.54 1,698,279.97 Min of Water Resources 102 Proposed Procurement of Assorted submersible pumps across the state 19,479,796.87 19,479,796.87 - JS Water Board 103 Proposed rehabilitation of 2no Small Towns water supply Schemes in gumel Zone 1,155,000.00 1,018,500.00 136,500.00 Stowa Proposed Construction of 2no New Solar powered water supply scheme at Malarin Gamm in Malam 104 Madori LGA and Walawa in Birniwa Local Government Area 12,046,650.00 12,046,650.00 - Stowa 105 Proposed Rehabilitation of water supply scheme at Taura Town 10,723,753.67 10,526,670.91 197,082.76 JS Water Board Proposed Constructio of (148No) Laterines and (24,000) Tippy tap Across the Communities of 106 Gwiwa and Roni Local Government Area 2,990,400.00 2,990,400.00 - Ruwasa Proposed Construction of (22No) Hand Pump Borehole at 22 communities in Sule Tankarkar and 107 Maigatari Local government Area 16,234,680.00 16,234,680.00 - Ruwasa Proposed Construction of (15No.) hand Pump Borehole at 15 Communities in Sule Tankarkar Local 108 Government Area 11,069,100.00 11,069,100.00 - Ruwasa Proposed Construction of (12No) Hand pump borehole at 15 Communities in Sule Tankarkar Local 109 Government Are Gumel Zone 8,855,280.00 8,855,280.00 - Ruwasa

Proposed Constructionn of (6No.) Hand Pump Borehole at 6 Communities in Sule Tankarkar and 110 Kafin and Local Government Area 4,427,640.00 4,427,640.00 - Ruwasa Proposed rehabilitation of 5No Small Towns Water supply schemes in Birnin Kudu Dutse, jahun and 111 Kazaure Zone 6,127,170.00 6,105,109.50 22,060.50 STOWA Proposed Upgrading and Conversion of 1No Motorized Water supply Scheme to Solar Powered at 112 Jabo in Jahun Zone 23,596,060.01 23,567,109.24 28,950.77 Stowa Proposed Construction of 4No New Solar water powered supply scheme at Danmarke, Wada, 113 Kayarda and Garin baki in Babura LGA, Ringim Zone 24,093,300.00 24,093,300.00 - Stowa 114 Proposed Procurement of Assorted Submersible pumps Across the State 19,479,796.87 19,479,796.87 - JS Water Board 115 Procurement of assorted sumbersible pumps across the state (Additional works) 882,000.00 882,000.00 - JS Water Board Proposed rehabilitation of 2No Small Town water supply schemes at ruru and Budinga town in dutse 116 and gwaram LGs 882,000.00 882,000.00 - Stowa

117 Proposed Upgrading and Conversion of Doko water supply scheme in Garki Local Government Area 8,358,328.13 8,004,990.11 353,338.02 Stowa Proposed upgrading and Conversion of 1No Motorized water supply scheme to Solar Powerd at Uku 118 Da Sisi Sabuwa in Babura LGA, Ringim Zone 7,005,526.45 6,767,532.45 237,994.00 Stowa Proposed rehabilitation of 3no Small towns water supply schemes at Ruru, Budinga and Yabaza in 119 Dutse and Birnin Kudu Zone 2,100,000.00 2,100,000.00 - Stowa Proposed Rehabilitation of 2No Small town water supply schemes at Yan Damo and malam Baki in 120 Gumel zone 8,895,181.68 8,482,573.26 412,608.42 Stowa

121 Proposed Rehabilitation of 17No. Small Towns water supply schemes at Hadejia and Jahun Zone 5,161,739.63 5,161,739.63 - Stowa 122 Proposed rehabilitation of 1No Solar water supply schemes at Modoji in Sule Tankarkar 1,557,281.25 1,667,531.25 (110,250.00) Stowa 123 Proposed Construction of (40No) Hand Pump Boreholes Across the state 29,517,600.00 29,517,600.00 - Ruwasa 124 Proposed Rehablitation of (34No) Hand Pump Borehole at Babura LGA 1,953,600.00 1,478,400.00 475,200.00 Ruwasa Improvement of Gwaram Tsohuwa and gwaram Sabuwa Towns Water supply scheme (Additional 125 works) 34,045,356.30 29,520,524.45 4,524,831.85 JS Water Board Proposed Construction of 1No water Collection, 1No Complete Borehole in Hadejia Town and 1No 126 Hand pump Borehole at Babura LGA 2,898,139.00 2,813,984.25 84,154.75 Ruwasa Conversion and Upgrading of motorized Borehole to Solar Powered supply (7No.) at kanya Babba Main pump station, kanya babba water for all station, kanya babba LGA, Danzomo II Pump station, 127 Kudai Pump station and Waza pump station (Additional works) 3,534,038.03 3,534,038.03 - Stowa 128 Proposed constr of 50no. Hand pump borehole at 50 communities across the state 36,897,000.00 36,897,000.00 - Ruwasa

129 Proposed constr of 1no. Solar powered water supply scheme at Dorai in Garki LGA, Ringim zone 6,023,325.00 6,023,325.00 - Stowa

130 Proposed procurment of 200KVA Gen set as change of purpose in Kazaure Water supply project 12,977,439.30 12,977,439.30 - JS Water Board - MINISTRY OF EDUCATION - Proposed Procurement of Office Equipment for Permant Senate Building office 14,128,590.00 13,397,475.00 131 731,115.00 Sule Lamido University Proposed Renovation Works of Classroom Blocks (Each) at 5No Senior Secondary School Across the 22,404,592.38 22,487,382.75 132 State (82,790.37) Min of Education 133 Proposed Construction of Admin Block and 6-Seater pit Latrine 21,998,145.35 21,998,145.35 - IEB 134 Proposed Construction of 1No Block of Three Classrooms 11,202,005.64 11,202,005.64 - IEB 135 Proposed Construction of 4No Hand Pumps 2,410,000.00 2,410,000.00 - Bamaina Gifted Academy 136 Proposed Construction and Renovation works at Bamaina Academy 5,368,288.27 5,649,771.21 (281,482.94) Bamaina Gifted Academy

137 Proposed Construction of 1No Block of Three Classrooms 15,371,199.96 15,455,343.81 (84,143.85) COI&LS Ringim 138 Proposed Construction of one Block Two Laboratories at GGDSS Roni 28,487,680.00 33,552,607.41 (5,064,927.41) Min of Education Proposed Procurement and Distribution of 3-seater Students Desks and Benches, Principals and Staff 139 room Furniture for Senior Secondary school across the state 85,299,375.00 85,115,625.00 183,750.00 Min of Education 140 Proposed Procurement of 1No Brand New 350KVA sound proof perkins Generator 22,722,577.50 22,722,577.50 - Sule Lamido University 141 Proposed Renovation Works at Lautai Gumel LGA (GDSS) 57,457,387.79 60,686,506.55 (3,229,118.76) Min of Education 142 Proposed renovation of staff houses and hostels at College of Education Gumel 334,671,516.44 383,489,242.44 (48,817,726.00) Min of Education Proposed Procurement and Distribution of Instructional Materials for nomadic Primary Schools 143 Across the State 16,408,750.00 16,206,625.00 202,125.00 Nomadic Education Proposed Procurement and Distribution of (750No.) 3 Seater Desks and (4,000No) Sitting Mats for 144 Nomadic School Across the State 16,750,000.00 14,965,000.00 1,785,000.00 Nomadic Education Proposed fRenovation of Windstorm Damaged Structures (Phase II) at Science Secondary Secondary 145 School Lautai gumel (additional works) 3,168,882.15 3,168,882.15 - Scinece& Tech Board Proposed Constr. Of Gate House and Wall Fence at Jigawa College of Remidial and Advance Studies 146 Babura (JICORAS) 103,229,892.40 137,837,089.74 (34,607,197.34) Min of Education 147 Proposed Procurement of Chalk for Baic Schools Across the State 26,228,020.00 26,228,020.00 - Subeb Proposed Procurement of Science Laboratory Equipments for Distribution to 9No senior Secondary 148 Schools Upgraded to Science Centres of Excellence Core-2 81,068,353.92 81,068,353.92 - Min of Education 149 Proposed Renov of Storm Damaged structures at GSSS Taura, CGSSS Roni and GSTC Hadejia 49,576,548.66 50,071,865.14 (495,316.48) Science & Tech Board 150 Proposed Constr of new Mega School in Dutse 215,689,695.60 225,089,449.84 (9,399,754.24) Min of Education Constr of Female student's Hostel at Sule Lamido University Kafin Hausa (Proposed steel roof 151 members) 18,028,810.00 18,028,810.00 - Sule Lamido University Proposed Procurement of Office Materials and Renov/Conversion of Political Party Office to Admin 152 Block and Lecture classrooms at College of Remidial and Advance studies Babura 11,313,450.39 14,046,670.75 (2,733,220.36) Min of Education Proposed Registration with JAMB ABU Zaria and take-up grant of College of Remidial and Advance 153 studies Babura 2,350,000.00 2,350,000.00 - Min of Education

154 Proposed Procurement of 1no Isuzu Septic tank 23,820,000.00 22,878,228.51 941,771.49 Sule Lamido University Proposed procurement and Distribution of School uniforms, Sandals and Bags for Nomadic schools 155 across the state 29,980,000.00 27,880,000.00 2,100,000.00 Nomadic Education 156 Proposed constr of JICORAS at Babura (phase I) (revised Scope) 440,761,393.03 450,720,554.97 (9,959,161.94) Min of Education 157 Proposed departmental works and purchases for NBTE Requirements 5,310,020.00 5,310,020.00 - Bilyamu Usman Polytech 158 Proposed conduct of 2019 Musabaqar Ilimi 14,336,100.00 13,591,350.00 744,750.00 Islamic Education Bureau Proposed Procurement of Laboratory Equipments and Reagent , Food nutrition/catering craft practice and Animal Husbandary Items for waec and Neco Accreditation of Science secondary 159 schools 9,384,546.00 8,493,252.00 891,294.00 Science & Technical Board 160 Proposed Procurement of examination materials 1,420,000.00 1,420,000.00 - Bilyamu Usman Polytech Binyaminu Usman Proposed Construction of Library Phase II at New Campus, Binyaminu Usman Polytechnic Hadejia Polytechnic 161 44,992,746.03 42,334,242.16 2,658,503.87 Binyaminu Usman 162 Proposed Procurement of Academic Gowns 2,615,000.00 2,270,000.00 345,000.00 Polytechnic Proposed Procurement of Instructional / Enterpreneuship Materials, Jamb Scratch Cards and 5-Day 163 Training Workshop for FTDS Facilitator for the 3rd years scale up of FTDS 14,904,900.00 10,044,900.90 4,859,999.10 Ministry of Education Proposed Construction of (1No) Hostel Block for Jigawa State Institute of Information and 164 Technology Kazaure 49,994,477.82 47,989,101.98 2,005,375.84 JSIIT Kazaure Proposed Construction of 6 Classroom Blocks at the Proposed Boys and girls Junior Science 165 Secondary School Gumel (1st Quarter Constituency Project 2019) 30,520,842.46 29,997,708.62 523,133.84 SUBEB

Binyaminu Usman 166 Proposed Procurement of (250No) Student's Mattresses 1,925,000.00 1,925,000.00 - BinyaminuPolytechnic Usman 167 Procurement and Installation of a Brand New 100KVA Soundproof Perkins Generator (1100 Series) 5,334,960.00 5,334,960.00 - Polytechnic Proposed External Electrical power supply 33KV Dedicated feeder from Hadjia (Lot-1 of the phase II 168 Project 46,289,431.23 51,049,397.56 (4,759,966.33) Sule Lamido University Proposed External Electrical power supply 33KV Dedicated feeder from Hadjia (Lot-2 of the phase II 169 Project 39,137,223.31 42,158,908.89 (3,021,685.58) Sule Lamido University Proposed procurement of science laboratory equipments for senior secondary schools across the 170 state 33,630,751.71 33,630,751.71 - Ministry of Education Proposed procurement and distributions of (34,304No.) Science text books and teachers guide for 171 senior secondary across the state 49,949,800.00 49,949,800.00 - Ministry of Education 172 Proposed food order for 500 students per week in Boarding Schools 442,280.00 438,260.00 4,020.00 Ministry of Education Proposed external electrical power supply 33KV Dedicated feeder from Hadejia ( Lot-3 of the Phase I 173 Projects) 29,676,826.34 29,676,826.34 - Sule Lamido University Proposed NTBE Accreditation resources inspection and affiliation for 12No Programs in the Jigawa State 174 Polytechnic 9,225,000.00 8,976,000.00 249,000.00 Polytechnic 175 Proposed procurement of 1no Toyota Avensis (2018 Model) 28,934,000.00 28,934,000.00 - Sule Lamido University 176 Proposed procurement of 1No Toyota Corolla (2018 Model) 18,800,000.00 17,718,750.00 1,081,250.00 Sule Lamido University 177 Proposed Procurement of workshop materials and Consumables items in 4No Technical Colleges. 8,188,250.00 8,188,250.00 - Scinece& Tech Board 178 Proposed payment of facilitators for Litracy programme 30,630,000.00 30,630,000.00 - Mass Education 179 Proposed Staff Training and Development 3,638,622.00 3,638,622.00 - Bilyaminu Usman Poly 180 Proposed Renovation of 1No 3 Bedroom House 3,032,747.22 2,991,989.63 40,757.59 Bilyaminu Usman Poly State Polytechnic, 181 Proposed Procurement of (2No) Vehicles 27,950,000.00 27,950,000.00 - Dutse Proposed Production of (4,266 sets) of 3-seater students furniture from scraps at various schools 182 across the state 20,000,031.84 20,000,031.84 - Min of Education Proposed rennovation of classrooms and Admin Block at Sugungu Primary School Garki LGA and 183 GGJSS Gagarayaga Gwaram LGA 9,774,322.12 9,774,322.12 - Min of Education 184 Proposed External Electrical Power supply for permanent senate building Lot-2 27,171,584.37 24,691,772.46 2,479,811.91 Sule Lamido University Proposed External Electrical Power supply 33KV Dedicated feeder from Hadejia Lot-III of the Phase Ii 185 Project 49,183,473.65 47,439,656.28 1,743,817.37 Sule Lamido University Proposed renovation of classrooms blocks, Hostel, workshop, Library GJSS Aujara and re- 186 Construction of wall fence at Model Boarding Primary School Kila 42,117,899.50 45,009,447.40 (2,891,547.90) Min of Education 187 Proposed accreditation of 11No Pragrammes in the Polytechnic 3,110,900.00 3,110,900.00 - Bilyamin Usaini Poly Proposed printing of Examination papers with answer sheets by Jigawa State Printing press for 188 senior secondary schools across the state 8,110,096.50 8,247,851.33 (137,754.83) Min of Education Proposed printing of 2019 basic education certificate examination (BECE) Question papers with 189 answer sheets 16,724,512.00 15,260,680.05 1,463,831.95 Min of Education 190 Proposed repairs of 1No Monitoring Vehicle (Toyota Hilux) 2,228,500.00 2,005,200.00 223,300.00 Nomadic Education Proposed External electrical power supply for shopping complex,Clinic, Junior Staff Quarters and 191 VC's Lodge ( Lot-1) 46,004,312.20 42,497,088.81 3,507,223.39 Sule Lamido University 192 Proposed perimeter demarcation and Survey/Topographical and detail survey of the polytechnic 5,262,136.00 5,022,948.00 239,188.00 Bilyaminu Usman Poly 193 Proposed Renovation works at Jigawa State Research Institute Kazaure 9,775,628.66 9,713,139.27 62,489.39 Res earch Ins titute Kazaure Prposed procurement of new tractor (QLN-654, 65HP) and implement, Kazaure Research Institute 6,925,000.00 6,925,000.00 194 - Res earch Ins titute Kazaure Proposed production of 10HA each of millet & seame, 3HA groundnut and 3HA cowpea, Kazaure 4,763,300.00 4,778,300.00 195 Research Institute (15,000.00) Res earch Ins titute Kazaure

Proposed training on Artificial Insemination techniques and Insemination of (300) cows at Kazaure 5,923,015.00 5,923,015.00 196 Research Institute - Research Institute Kazaure 197 proposed procurement of vehicles at JICORAS Babura 47,250,000.00 47,250,000.00 - Min of Edcucation 198 Price of LAPTOP Lenovo BSO-10 Comuputer (variety) 807,500.00 807,500.00 - Scholarship Board 199 Proposed constr of Block of 3-classrooms at Ringim College of Islamic & legal Study. 15,371,199.96 15,455,343.81 (84,143.85) COI&LS Ringim 200 Proposed procurement of Examination material;s Ringim College of Islamic & legal Study. 4,600,000.00 4,600,000.00 - COI&LS Ringim Proposed supply and Installation of (52no) street light inntergrated Ringim College of Islamic & legal 201 Study. 32,215,050.00 32,215,050.00 - COI&LS Ringim

202 Proposed procurement of instructional materials for (81no) post literacy centre across the state. 3,239,670.00 3,191,790.00 47,880.00 Agency for Mass Educ. Action plan for Establishment of 81 Remidial and 36 Continuing Education centre facilitators monthly 203 allowance and Airtime programme 56,554,350.00 56,074,342.50 480,007.50 Agency for Mass Educ.

204 Proposed renovation of science Laboratories and ITC Room Each at 9No. Senior Secondary Schools 15,421,179.00 24,143,284.04 (8,722,105.04) Min of Education Proposed renovation of storm damages at GDASS Dantanoma, SAIS Hadejia, GDASS Zainab Kazaure, 205 GDASS Dabi, GDASS Birnin kudu, GDASS Gwaram and GDASS Danzomo 57,822,208.00 53,582,692.89 4,239,515.11 IEB 206 Proposed renovation of classrooms Blocks at MBPS Kudai in Dutse 4,450,715.27 4,971,711.32 (520,996.05) SUBEB

207 Proposed renovation of classrooms blocks at Kabewa and Samangara in Gwaram and Sule Tankarkar 7,213,644.52 5,824,507.21 1,389,137.31 SUBEB 208 Proposed re-construction of wall fence at GGUSS Garki and GGUSS Malam Madori 11,334,094.59 9,039,035.07 2,295,059.52 Min of Education 209 Proposed procurement of Double Decker Beds and Mattrasses 4,000,000.00 2,950,000.00 1,050,000.00 Bamaina Gifted Academy 210 Proposed procurement of Students uniform and Protective clothings 2,284,000.00 1,898,000.00 386,000.00 Bamaina Gifted Academy

211 Proposed Renovation of storm damaged structures at GSTC Karkarna SSS Kafin Hausa and GSSS Jahun 24,498,727.08 35,803,002.26 (11,304,275.18) SUBEB Proposed procurement of (30,000 sets) School Uniforms for Senior Secondary Schools Girls Across 212 the State 78,000,000.00 78,000,000.00 - Min of Education Proposed Construction of Admin Block, Students Hostel, Laboratory, 6 Seater Pit Latrine and 1 block 213 3 classroom 11,169,666.72 11,202,005.64 (32,338.92) Min of Education Proposed Procurement of Instructional materials for women funtional literacy and payment of 214 programme facilitators 5,859,500.00 5,667,800.00 191,700.00 Mass Education 215 Proposed Procurement of Instructional Materials 2,682,564.00 2,430,324.00 252,240.00 Bamaina Gifted Academy 216 Proposed procurement of sporting equipments 474,300.00 474,300.00 - Bamaina Gifted Academy Proposed Procurement of ICT Materials and Accessories for Distribution to 9No Senior Secondary 217 Schools upgraded to Science Center of Excellence 65,958,600.00 68,982,322.50 (3,023,722.50) Min of Education 218 Proposed Construction of A Prototype 480 Capacity Students Hostel 379,307,287.02 390,002,952.26 (10,695,665.24) Sule Lamido University 219 Proposed Conduct of 2019 Qur'anic Recitation competition 25,970,040.00 25,218,600.00 751,440.00 IEB 220 Proposed Renovation of Storm Damaged at 7No Schools Across the State 21,608,545.23 23,498,908.59 (1,890,363.36) Min of Education 221 Propose 2019 Capital Project 3,000,000.00 3,000,000.00 - JSIIT Kazaure 222 Proposed procurement of 1No Isuzu Septic Tank 23,820,000.00 18,425,462.35 5,394,537.65 Sule Lamido Uni Proposed Procurement of science laboratory equipments for distribution to 9No Senior Secondary 223 Schools Upgraded to science centres of Excellence core-2 81,068,353.92 81,068,353.92 - Min of Education Proposed Procurement of science laboratory equipments for distribution to senior secondary 224 schools across the state 29,491,628.31 29,491,628.31 - Min of Education 225 Proposed 2019 capital projects at JSCOE Gumel 20,004,592.06 19,702,558.36 302,033.70 Min of Education 226 Proposed renovation of Ringim divisional libarary 7,483,822.92 7,409,717.73 74,105.19 Library Board

227 Proposed Procurement of 150no. 3 Seater Student Desk 3,000,000.00 3,000,000.00 - Dutse Model School Proposed Procurement of ICT Materials and Accessories for Distribution to 9No Senior Secondary 228 Schools upgraded to Science Centres of Excellence 65,958,600.00 68,982,322.50 (3,023,722.50) MinAgency of Education for Mass 229 Proposed procument of Instructional materials for post Literacy centres across the state. 4,950,490.00 4,130,500.00 819,990.00 Education

MINISTRY OF WORKS - 230 Proposed Repairs of NYSC orientation Camp Generator 3,174,906.57 2,388,615.19 786,291.38 Ministry of Works

231 Construction of Jigawar Ali Township Road (2.10KM) by Messrs mothercat Nig LTD (additional) 224,213,450.06 203,412,195.00 20,801,255.06 Ministry of Works

232 Proposed Construction of 3KM Shoulder Along Gujungu - Gumel Road 18,301,342.50 20,172,442.50 (1,871,100.00) JIRMA

233 Proposed Stand Alone Solar Street Lighting Project at Babaldu Town in Birnin Kudu LGA 58,046,625.00 55,786,500.00 2,260,125.00 Ministry of Works Proposed Relocation of 1No Hand Pump Borehole Affected By Road construction at Hadejia Road10 234 Gandun Sarki 629,790.00 629,790.00 - Ministry of Works

235 Proposed Procurement of ICT Equipment and Training of Staff 5,000,000.00 4,558,000.00 442,000.00 Urban Dev Board

236 Proposed Maintenance of Birnin Kudu-Kiyawa road 14,644,282.17 14,644,282.17 - JIRMA

237 Constr of Babura township roads (10.28km) (Lot-8) (additional work) Consultancy 7,745,437.31 7,745,437.31 - Ministry of Works Stand Alone Solar Street Lighting Project at Garun-Gudiya (80) of Babura LGA and Garin - Gambo of 238 Gumel LGA 81,328,800.00 81,328,800.00 - Ministry of Works

239 Proposed Stand Alone Solar Street Lighting project at Marke town in Kaugama LGA (150no.) 81,328,850.00 82,797,750.00 (1,468,900.00) Ministry of Works

240 Proposed Supply and Installation of 800KVA Generator (Sound Proof) 46,446,759.80 46,263,912.00 182,847.80 REB

241 Proposed relocation of 12No Hand Pump Boreholes Affected by the township Roads Project in Gumel 8,855,280.00 8,855,280.00 - Ministry of Works

242 Relocation of water pipelines affected by the road Construction at Kaugama 5,429,983.61 5,387,600.40 42,383.21 Ministry of Works

243 Relocation of water supply facilities affected by the Road Construction at Kanya Babba Town 7,104,877.50 7,105,533.75 (656.25) Ministry of Works

244 Relocation of water supply facilities affected by the Road Construction at Jigawar Dan Ali Town 6,304,725.00 6,213,506.25 91,218.75 Ministry of Works

245 Relocation of Water supply facilities affected by the Road Construction at Chai-Chai Tsohuwa Town 2,391,637.50 2,391,637.50 - Ministry of Works Proposed Relocation of Urban Town Street Light Installation affected by the Project (Construction of 246 Gumel Township Roads) 27,797,663.25 27,077,730.75 719,932.50 Ministry of Works Proposed Relocation of Urban Town Street Light Installation affected by the Project ( Construction of 247 Zandam Nagogo Township Roads) 5,804,400.00 5,589,150.00 215,250.00 Ministry of Works Proposed Relocation of urban town solar street light installation affected by the project ( 248 Construction of jigawar dan Ali Township Roads) 1,139,250.00 1,055,000.00 84,250.00 Ministry of Works Proposed Relocation of urban town solar street light installation affected by the project ( 249 Construction of Kanya Babba township Roads) 1,438,500.00 1,370,000.00 68,500.00 Ministry of Works Proposed Relocation of Urban Town street light installation affected by the project ( Construction of 250 Kiyawa Township Roads) 7,029,750.00 7,080,255.00 (50,505.00) Ministry of Works Proposed Relocation of Urban Town street light installation affected by the project ( Construction of 251 MIga Township Roads) 8,583,750.00 8,715,262.50 (131,512.50) Ministry of Works

252 Proposed Construction of Hadejia Eastern Bye-Pass (Phase III) Water Damaged Section 58,964,002.00 58,607,439.60 356,562.40 JIRMA Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of 253 744 Yalwawa Township Roads) 6,997,000.00 6,082,000.00 915,000.00 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of 254 KanyaTownship Roads) 2,610,300.00 2,277,345.00 332,955.00 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of 255 Jigawar dan AliTownship Roads) 1,754,010.00 1,740,375.00 13,635.00 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of 256 Zandam Na GoGo Township Roads) 7,529,500.00 6,402,000.00 1,127,500.00 Ministry of Works

257 Relocation of Water supply facilities affected by the road Construction at Kazaure town 28,358,982.50 27,716,172.00 642,810.50 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of 258 Chai-Chai TsohuwaTownship Roads) 3,411,000.00 3,049,000.00 362,000.00 Ministry of Works

259 Construction of Hadejia Township Roads Project (additional works) 214,624,764.24 214,624,764.24 - Ministry of Works

260 Stand Alone Solar Street Lighting Project at Emir Palace Road, Dutse 17,419,500.00 17,391,937.50 27,562.50 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Road Project Construction of 261 kiyawa Township Roads 6,923,000.00 6,075,000.00 848,000.00 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Road Project Construction of 262 Miga Township Roads 3,237,500.00 2,712,500.00 525,000.00 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Road Project Construction of 263 Gumel Township Roads 9,162,195.00 9,235,595.00 (73,400.00) Ministry of Works

264 Proposed protection work at Premises of GGSS Garu Dutse 9,180,953.44 9,180,953.44 - JIRMA Proposed Relocation of Electrical Installations (Kedco) Affected by Roads Projects (Construction of 265 Gudunci-Aguyaka Road) 2,380,350.00 2,113,125.00 267,225.00 Ministry of Works

266 Proposed Repairs of Machines 4,682,000.00 4,682,000.00 - JIRMA Proposed Improving access between sugungu and kashin ganji Communities in Garki Local 267 Government Area 8,387,424.15 8,387,424.15 - JIRMA Proposed maintenance Rehabilitation of Some Failed Section along Kazaure Roni Asphaltic Concreter 268 surfaced Road 72,239,291.69 70,061,248.78 2,178,042.91 JIRMA Proposed Maintenance Pathole Patching of Some Failed Spot Along Unguwar Mani-Koreyal-Rorou 269 Surfaced dressed Road 31,775,900.21 29,959,647.20 1,816,253.01 JIRMA Proposed stand alone solar street lighting project at GGASS birniwa (42No) GGASS Kaugama (40No) 270 SOD Hadejia (30No) and JSS Guri (30No.) 77,002,800.00 77,002,800.00 - Ministry of Works 271 Proposed Maintenance of Maiganjara bridge along Jahun-Gujungu Road 6,586,482.00 6,588,449.70 (1,967.70) Ministry of Works 272 Proposed potholes patching along yarkirya-Dandi-Gada and Dandi-Achi lafiya roads 18,323,348.40 14,132,132.55 4,191,215.85 Ministry of Works Proposed recllamation of eroded road embenkment and construction of Drainage at Yalo Borrow-Pit- 273 Gujungu-Hadejia road 8,962,589.58 8,962,589.58 - Ministry of Works

274 Proposed rehabilitation of Gumel to Gagarawa ITC Line 2,963,468.39 2,963,468.39 - Ministry of Works

275 Construction of Gambara-Waza-Baranda with spur road to Yalwa (16.8km) (additional works) 993,666,672.04 909,144,691.47 84,521,980.57 Ministry of Works 276 Proposed relocation of Electrical installations of Kaugama township road (KEDCO) 2,673,085.00 2,318,400.00 354,685.00 Ministry of Works

277 Construction of Babura Township Roads (10k.28) Lot-8 (additional works) 587,368,516.84 510,841,607.48 76,526,909.36 Ministry of Works

278 Proposed relocation of electrical installations (KEDCO) affected by Roads Project (Phase III) (Gumel) 1,895,500.00 1,672,625.00 222,875.00 Ministry of Works

279 Proposed relocation of water supply facilities affected by the township roads project in Hadejia town 451,750.00 451,750.00 - Ministry of Works

Proposed relocation of 3no hand pump borehole affected by the township roads project in Kiyawa 280 town 1,889,370.00 1,196,370.00 693,000.00 Ministry of Works

281 Proposed rehabilitation of Gwaram - Basirka ITC Line 141,110,326.37 141,110,326.37 - REB

Proposed relocation of 3No Hand pump borehole affected by the township roads project in kanya 282 babba town 1,889,370.00 1,889,370.00 - Ministry of Works Proposed relocation of 1No Hand pump borehole affected by the township roads project in Jigawar 283 Dan Ali town 629,790.00 629,790.00 - Ministry of Works

Proposed relocation of 1No Hand pump borehole affected by the township roads project in Chai-Chai 284 Tsohuwa town 629,790.00 629,790.00 - Ministry of Works Proposed relocation of 1No Hand pump borehole affected by the township roads project in 744 285 yalwawa 629,790.00 629,790.00 - Ministry of Works Proposed relocation of 5no water collection points affected by the township roads project in Gumel 286 Town 6,264,993.00 6,264,993.00 - Ministry of Works Proposed relocation of 2No hand pump borehole affected by the township roads construction at 287 Zandam nagogo town 1,259,580.00 1,259,580.00 - Ministry of Works

288 Proposed relocationn of 2No hand pumps borehole affected by the township roads peoject in miga 1,259,580.00 1,259,580.00 - Ministry of Works

Proposed relocationn of 12No hand pumps borehole affected by the township roads peoject in Gumel 289 town 2,468,970.00 2,468,970.00 - Ministry of Works Proposed stand alone street lighting project at GGASS Danzomo (42No.) GGSS Sule Tankarkar (35No) 290 MBPS Gumel (30No.) and GGSSS Taura (32No.) 75,380,550.00 75,380,550.00 - Ministry of Works Road Maintenance 291 Proposed maintenance of Auyo Town retaining wall-River embankment 49,718,008.41 49,718,008.41 - Agency Road Maintenance 292 Proposedf reclamation and construction of a Retaining wall at Kwalam Borrow Pit Along Ringim-Hadejia Road 11,564,426.37 11,564,426.37 - Agency Proposed stand alone solar street lighting project at GGASS Danzomo (42No) GGSS Sule Tankarkar 293 (35no.) MBPS Gumel (30No) and GGSSS Taura (32No) 60,780,300.00 60,780,300.00 - Ministry of Works Proposed Stand Alone Street lighting project at GUSS Gwaram (45No.) GGASS Babura (38No.) and 294 GGSS Roni 60,780,300.00 60,780,300.00 - Ministry of Works

295 Proposed Relocation of water supply facilities affected by the Road Construction at Miga Town 9,044,352.75 8,653,117.55 391,235.20 Ministry of Works

296 Proposed Relocation of water supply facilities affected by the Road construction at Gumel Town 35,701,295.56 31,383,059.49 4,318,236.07 Ministry of Works Proposed Relocation of water supply facilities affected by the Road construction at Zandam Nagogo 297 Town 5,984,754.23 4,674,262.16 1,310,492.07 Ministry of Works 298 Constr. Of Taura-Garki Road 400,000.00 400,000.00 - Ministry of Works Proposed Relocation of water supply facilities affected by Kanya-Duzau-Goron Maje Feeder Road 299 Project 2,787,750.00 2,751,000.00 36,750.00 Ministry of Works

300 Proposed Repairs of Kwanar yalleman-Kaugama-Kwanar madana Road 54,230,613.60 35,906,265.73 18,324,347.87 Jirma 301 Proposed Rehabilitation of Takur Jaudi Feeder Road (2019 Flood) 9,442,085.63 6,451,728.00 2,990,357.63 Jirma

302 Proposed Construction of Reinforced block line and culvert at Sha'iskawa Takur Site 24,938,937.50 24,680,291.36 258,646.14 Jirma

303 Proposed Maintenance of Ayama Junction-Ayama Feeder Road 63,005,166.47 62,244,441.17 760,725.30 Jirma

304 Proposed Construction of Shagari Quarters-Burtilan-Three Star junction Road (2.0km) 300,097,007.94 294,311,528.94 5,785,479.00 Ministry of Works

305 Proposed Construction of Additional 3 Cell Box culvert along Hantsu Miga Dangyatum Road 43,364,604.94 43,364,604.94 - Jirma

306 Proposed reclamation and Construction of Drainage at IGGI town in Birnin Kudu LGA 25,790,264.43 25,790,264.43 - Jirma Proposed Maintenance and Rehabilitation of Multi Cell Box Culvert Along Karnaya-Chai Chai- Ringim 307 road at Sintilmawa 7,196,462.98 7,196,462.98 - Jirma Proposed Maintenance and Reconstruction of Section Damaged by 2018 Flood Along Kwalam-Gilima- 308 Kiri Road 197,729,725.73 199,672,807.59 (1,943,081.86) Jirma

309 Proposed Stand alone solar street lighting project at elleman town in Kaugama LGA 17,708,414.54 17,474,625.00 233,789.54 Ministry of Works Construction of Hadejia Township Roads Projects at Azare Road-Adua Mosque-New Motor Park 310 (Road 11) (additional works) 324,613,275.50 312,270,011.94 12,343,263.56 Ministry of Works

311 Construction of Hadejia Township Roads projects Additional Works (485M Road Network (road 10) 109,988,511.26 97,645,247.70 12,343,263.56 Ministry of Works Dutse International 312 Proposed Maintenance of Generating Set at Dutse International Airport 928,500.00 863,500.00 65,000.00 Airport 313 Proposed Relocation of Water supply facilities affected by the township roads poject in 744 Dutse 12,634,075.00 11,704,856.86 929,218.14 Ministry of Works 314 Proposed Relocation of Water supply facilities affected by the township roads project in kiyawa 12,739,349.00 12,043,954.33 695,394.67 Ministry of Works 315 Proposed Maintenance of Birnin Kudu-Kiyawa Road 14,644,282.17 14,644,282.17 - JIRMA 316 Proposed Maintenance of failed sections along Kazaure-Roni Asphaltic Concrete Road 113,701,901.25 98,528,040.30 15,173,860.95 JIRMA 317 Proposed Maintenance of Failed Spots and Potholes on Hadejia Gujungu Road 4,328,047.50 4,328,047.50 - JIRMA 318 Proposed Maintenance of Fail section of unguwar mani-Korayel Surface Dressiing Road 18,315,665.65 18,315,665.65 - JIRMA Proposed Reclamation of Reinforced concrete block drainage (2000M) Access Slabs and Culverts at 319 Gunka Along Sukullifi-Gunka Road Jahun 48,289,386.35 47,762,386.35 527,000.00 JIRMA 320 Proposed Repairs of NYSC Orientation Camp Generator, Dutse 3,174,906.57 1,977,397.29 1,197,509.28 Ministry of Works Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project ( Construction of 321 Birnin Kudu-KwanGwara-Zaziga Feeder Road 681,000.00 586,000.00 95,000.00 Ministry of Works 322 Proposed Repairs of 8No. Fire Fighting trucks 6,729,000.00 6,172,250.00 556,750.00 Fire Services 323 Proposed Drilling of 150MM PVC Borehole with reticulation of 90MM PVC of 2KM Distance 7,100,423.40 6,734,650.13 365,773.27 Fire Services 324 Proposed Procurement of Working Materials 3,485,920.00 3,300,500.00 185,420.00 DutseFire International Services 325 Proposed maintenance works of very high frequency OMINI Directional Radio (VOR) Shelter 1,059,148.50 1,059,148.50 - Airport Proposed reclamation of eroded road embankment, re-dressing of shoulder stone pitching and 326 construction of Chutes and Kerbs at Jangargari-babaldu-Sagu road 3,483,186.00 3,359,706.00 123,480.00 JIRMA Directorate of Economic Empowerment - 327 Proposed Upgrading of Babura Skills Acquisition and Training Center 8,596,891.21 11,263,571.41 (2,666,680.20) Directorate of Econ. Emp. 328 Proposed Procurement of (10No) Boxer Bajja Motorcycle 2,900,000.00 2,900,000.00 - Directorate of Econ. Emp.

Proposed Procurement of Consumable training materials of Mafita (DFID) Programme in 13No. Skills 329 Acquisition Center 21,014,450.00 20,378,263.50 636,186.50 Directorate of Econ. Emp. 330 Proposed Procurement of (14no.) 6 Water Pump and Solar Pump 6,640,000.00 6,640,000.00 - Directorate of Econ. Emp. - MINISTRY OF LAND & HOUSING - 331 Proposed procurement of furniture and at deputy governor's residence 44,790,300.00 34,868,641.50 9,921,658.50 Min of Land 332 Proposed renovation of deputy Governo'rs Residence 18,182,740.96 17,581,763.41 600,977.55 Min of Land Construction of 30No Boys Quarters External Electrification & Water supply to Individual 333 Legislators Quarters Dutse (generator house) 4,967,578.00 4,967,578.00 - Min of Land - CABINET OFFICE - Proposed Constr/Renovation of juma'at Prayer Mosques (First Quarter 2019 Constituency 334 Projects) 49,605,136.99 51,473,514.64 (1,868,377.65) Cabinet Office Proposed Constr. Of Juma'at Prayer Mosque at Oliya Sararin Rakuma Quarters Hadejia Constituency 335 First Quarter 2019 Constituency Projects) 5,804,760.56 5,940,460.38 (135,699.82) Cabinet Office 336 Proposed Constr. Of Juma'at Prayer Mosques (4no.) at Birniwa, Gagarawa and Buji) 41,773,970.56 42,013,131.72 (239,161.16) Cabinet Office Partial works (constr of main mosque lower level roof slab) at K/Hausa mosque 2018 2nd qtr 337 Constituemcy project (change of scope) 4,772,560.00 4,047,154.00 725,406.00 Religious Affairs 338 - Proposed Construction, Completion and Renoovation of juma'at and Daily Prayer Mosque for First 339 Quarter 2019 Constituency Project (13no) 69,483,551.42 68,104,946.96 1,378,604.46 Cabinet Office Proposed Construction / Completion and Renovation of Friday Prayer mosque / Five Daily Prayer 340 Mosque for First Quarter 2019 Constituency Projects (6no) at hadejia and K/kasamma 24,550,734.62 24,081,611.13 469,123.49 Cabinet Office 341 Proposed Construction of juma'at Prayer Mosques for first Quarter 2019 Constituency Projects at Maigatari 15,688,829.50 15,486,967.52 201,861.98 Cabinet Office Proposed Renovation/Upgrading of District Head House and Renovation of Juma'at Prayer Mosque 342 for First Quarter 2019 Constituency Projects at Babura and Yankwashi 33,666,807.87 29,625,345.03 4,041,462.84 Cabinet Office 343 Proposed repairs of (7No) Commands Operational Vehicles NSCD Corps Jigawa State Command 7,133,500.00 6,515,000.00 618,500.00 Special Services Proposed Construction of Borehole with Dwarf tank for Additional Works of Juma'at Prayer Mosque 344 (JIBWIS) at Garin Gabas in Malam Madori Constituency for third Quarter 2018 Remaining Works 700,000.00 700,000.00 - Cabinet Office 345 Proposed Construction of Female mosque at Federal university Dutse 41,271,654.26 57,137,963.58 (15,866,309.32) Cabinet Office 346 Proposed Renovation of Jigawa State hisbah command Office at Dutse 6,010,416.76 6,001,925.14 8,491.62 Special Services Proposed Additional works for the supply of carpet, generator Sound System and Mumbari at 347 Nasarawa Jibwis Moque Prayer in Gumel 681,712.50 671,215.50 10,497.00 Cabinet Office Proposed Additional works for the construction of imam zoffice on the construction of wall fencing 348 and interlocking at Nasarawa Jibwis Mosque in Gumel 678,005.00 669,186.00 8,819.00 Cabinet Office - MINISTRY OF INFORMATION - 349 Proposed Procurement of Electrical Equipments 23,699,999.00 18,049,500.00 5,650,499.00 JTB Dutse Proposed Construction of 1No Town Hall at Tsohuwar Gwaram LGA for First Quarter 2019 Ministry of 350 Constituency Projects 36,295,490.03 36,182,900.04 112,589.99 Information 351 Proposed Renovation works at Hadejia Township Stadium 5,291,054.31 5,589,226.28 (298,171.97) Sport Council 352 Proposed renovation of storm damage and Construction works at Dutse township Stadium 9,863,713.33 9,863,713.33 - Sport Council 353 Proposed Rehabilitation of Guyed wire and others at Andaza Mast 44,707,950.00 40,770,450.00 3,937,500.00 JTV GOVERNMENT HOUSE - 354 Supply of 2no. fairly used 2018 and 2016 Totota Landcruiser Jeeps 42,000,000.00 44,100,000.00 (2,100,000.00) Government House 355 Supply of 2no. fairly used 2015 and 2016 Totota Landcruiser Jeep 36,000,000.00 37,800,000.00 (1,800,000.00) Government House

356 Proposed Price of 2 No. GS 8 and 13no GS 4 vehicles or its equivelent 169,533,611.20 169,533,611.20 - Government House - MINISTRY FOR LOCAL GOVERNMENT - 357 Proposed Rehabilitation of 33KVA line from Sara-Gantsa Buji LGA 45,522,200.75 46,445,750.14 (923,549.39) Min for LG MINERAL RESOURCES - 358 Proposed conduct of Baseline Survey of Artisanal Miners/Acivities in 14 LGAS in the State 4,884,000.00 4,546,800.00 337,200.00 Mineral Resources Dev - OFFICE OF THE DEPUTY GOVERNOR - Proposed price of items to be distributed to N-Tech Trainees Under the N-Power Skills development Special Intervention 359 Across the State 23,500.00 23,500.00 - Program Proposed Price of Items to be Distributed to N-Tech Trainees Under the N-Power Skills Development 360 Across the State 6,322,000.00 8,154,562.50 (1,832,562.50) Deputy Govt Office Proposed Procurement of Furniture and Equipments at Deputy Governors Residence (additional 361 works) 9,897,500.00 8,750,175.00 1,147,325.00 Deputy Govt Office - MINISTRY OF ENVIRONMENT - 362 Proposed Construction of drainages across the state (2019 first qtr. Constituency) 57,845,636.72 57,340,033.63 505,603.09 Ministry of Environment Ministry of 363 Proposed for the Repairs of Gully Emptier (911 lorry truck) 1,250,000.00 1,095,000.00 155,000.00 Environment

Proposed Procurement of items to be distributed to the community organizations as Government Ministry of 364 support for the clearance of typha and other Aquatic weeds along the Riverine Areas (Revised Scope) 15,173,813.00 15,173,813.00 - Environment Ministry of 365 Proposed Construction of Drainage at Tsirma Town in Kiyawa Local government Area 44,880,680.25 44,880,680.25 - Environment Ministry of 366 Proposed Construction of Drainage at Fankan Fayau Pond in Taura LGA 66,232,100.77 65,917,579.77 314,521.00 Environment Ministry of 367 Proposed constr of Drainages across the state 47,326,454.83 47,218,265.69 108,189.14 Environment Proposed production of 2.5 million assorted seedling (supply of materials) Ministry of 368 14,568,775.00 17,927,142.19 (3,358,367.19) Environment Proposed Procurement of items to be Distributed to the community organizations as government Ministry of 369 support for the clearance of typha and other Aquatic weeds alone the reverine areas 6,338,925.00 6,338,925.00 - Environment Ministry of 370 Proposed construction of drainage and repairs of wall fencing of inuwa Dutse housing Estate 43,935,657.85 43,533,566.82 402,091.03 Environment - MINISTRY OF JUSTICE - Proposed Construction of (8No)New Sharia court at Gumel Kazaure Garki Chamo Baturiya Yalo 178,348,359.52 189,105,452.24 371 Hadejia and Garun Gudunya (10,757,092.72) Sharia Court of Appeal 372 Proprosed procurement of Equipment/Furnitures 2,000,000.00 1,980,000.00 20,000.00 Judicial Serv Commison 373 Proposed repairs of 3no Vehicles 412,000.00 412,000.00 - Justice Sector Proposed Renovation of Chief Magistrate Official Residence Kafin Hausa, Construction of Magistrate 374 Court at Ringim and Construction of 4 Bedroom Duplex at Highbrough Dutse 52,748,575.72 51,713,779.52 1,034,796.20 Ministry of Justice 375 Proposed construction of conference hall at Judicial Services Commission Secretariat Complex 17,403,651.04 17,963,823.37 (560,172.33) Judicial Serv Commison 376 Proposed Procurement of Vehicles 62,000,000.00 62,000,000.00 - State Judiciary 377 Proposed Renovation of 12No. Sharia court 81,685,950.61 78,783,875.00 2,902,075.61 State Judiciary

Judicial Service 378 Proposed Procurement of 2no Utility Vehicle 29,385,300.00 29,385,300.00 - Commission

379 Proposed procurement and supply of law books to Ministry of Justice 18,984,750.00 18,984,750.00 - Ministry of Justice Proposed Construction of Perimter wall fence at Proposed site for the Construction of Prison along 380 Limawa-warwade road-Dutse LGA 205,020,293.66 191,928,817.44 13,091,476.22 Ministry of Justice Proposed Procurement of Computer, Library Management System Software and Network 381 configuration to Ministry of Justice 2,965,000.00 2,798,250.00 166,750.00 Ministry of Justice

- MINISTRY OF AGRICULTURE - 382 Proposed Construction of Abattoir at Doko in garki Local government Area 9,935,055.96 10,219,945.22 (284,889.26) Min of Agriculture 383 Proposed renovation of JASCO Stores (12no.) 7,288,801.52 6,241,390.57 1,047,410.95 Min of Agriculture Proposed Procurement of Animal vaccines, vaccination inputs and accessories for 2019/2020 annual 384 vaccination exercise 7,396,000.00 7,217,000.00 179,000.00 Min of Agriculture 385 Proposed Renovation of JARDA Headquater, Dutse 9,966,385.80 9,822,858.22 143,527.58 JARDA Proposed Renovation and Alteration of office Block to Accommodate Staff of Islamic Development 386 Bank (IDB) Project at JARDA Premises 17,527,798.25 17,320,419.03 207,379.22 JARDA 387 Proposed Renovation of States Zonal Veterinary Clinics (3no.) at Ringim, Jahun and Gumel 15,740,457.72 20,256,382.14 (4,515,924.42) Min of Agriculture - HEAD OF SERVICE - Contributory Pension 388 Proposed Supply and Installation of 10KVA Inveter Solar Power 6,271,986.00 5,278,696.50 993,289.50 Scheme 389 Proposed procurement of brand new ATIZ Book Drive pro book scanner machine 6,800,000.00 6,800,000.00 - Library Board Contributory Pension 390 Proposed supply and Instalation of 10KVA inveter solar power 6,271,956.00 5,278,696.50 993,259.50 Scheme 391 Proposed Procurement of books 9,200,000.00 9,104,800.00 95,200.00 State Libry MINISTRY OF COMMERCE -

392 Proposed Procurement of tourism Promotional Equipment and Printing of Tourist Guide handBook 990,000.00 990,000.00 - Min of Commerce

393 Proposed Procurement of e-Registration facilities for business premises and Cooperative Societies 1,774,122.00 1,597,176.00 176,946.00 Min of Commerce 394 Proposed Procurement of ICT Equipment & Accessories 2,740,000.00 2,795,000.00 (55,000.00) Min of Commerces 395 Proposed Renovation of 8No Structures at export Processing Zone Maigatari 13,016,137.90 12,738,100.79 278,037.11 Min of Commerce Proposed Construction of 2no Parking Shades at Babura Motorpark and Achaba in Babura 396 Constituency for First Quarter 2019 Constituency Projects 2,104,005.85 2,097,097.03 6,908.82 Ministry of Commerce - MINISTRY OF FINANCE AND ECONOMIC PLANNING - Board of internal 397 Proposed procurement of ICT Equipments for Tax Payeers Registration office 1,339,000.00 1,185,000.00 154,000.00 Revenue 398 Proposed construction of Hisbah commandant General Residence at Dutse 8,602,278.14 8,646,067.31 (43,789.17) Min of Finance 399 Proposed price of some office equipments 2,282,500.00 2,205,500.00 77,000.00 Min of Finance

400 Proposed Minor Renovation at Kazaure Zonal Office for the Proposed Driving Lincence centre 580,000.00 566,278.55 13,721.45 Board of Int Rev MINISTRY OF WOMEN AFFAIRS - Proposed Supply & Installation of (10No) Integrated Stand Alone Solar at Dankwambo in Maigatari 401 LGA 4,668,004.84 4,378,500.00 289,504.84 Alternative Energy Fund

402 Proposed procurment of office equipments and furniture 2,448,000.00 2,369,000.00 79,000.00 Min of Women Affairs 403 Proposed procurement of office equipments and furnitures 2,448,000.00 2,369,000.00 79,000.00 Min of Women Affairs 404 Proposed repairs of 3No Vehicles 1,202,100.00 1,009,600.00 192,500.00 Min of Women Affairs

CIVIL SERVICE COMMISSION - Proposed renovation of office block and extension of existing conference hall at Jigawa State Civil Civil Service 405 Services Commission Office 8,782,384.13 7,980,091.30 802,292.83 Commission - TOTAL 14,727,910,392.66 14,520,849,570.67 207,060,821.99

SECTION ( D )

CONTRACTS AWARDED

JANUARY TO DECEMBER, 2019

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD works Construction for the construction of health post at Tashena Village in Malam Madori Local 1 31/01/2019 Government Area. FGPC/2/2019/VOL.I/7 DALARI CONSTRUCTION 7,543,976.80 Min of Health 8 Weeks Renovation works (2019 Phase I) Constittuency Project at Haya PHC and Gamji Health post in 2 31/01/2019 Fagam Constituency, Gwaram Local Government Area. FGPC/1/2019/VOL.I/7 GIDAN ADEDE GENERAL 12,468,995.04 Min of Health 8 Weeks Construction of 1No. Block of 4No. House of 2No. Bedroom Semi-Detach (Lot-3) at Birniwa 3 19/3/2019 Locl Government Area FGPC/15/2019/VOL.I/7 MWT Real Estate & General 10,424,245.65 Min of Land 14 Weeks Construction of 1No Block of health Post at Askandu Village in Kaugama Local Government 4 6/3/2019 Area FGPC/7/2019/VOL.I/6 Jawad Global Construction 7,543,976.80 Min of Health 12 Weeks 5 19/3/2019 Construction of New Special Hospital at Hadejia Phase I (Additional Works) FGPC/131/2017/VOL.I/22 Philko Limited 274,639,176.32 Min of Health 2 Month

6 14/1/2019 Construction of Health Post at Waza Viillage in Birnin Kudu Local Government Area FGPC/941/2018/VOL.I/4 Ngaloma Construction 7,543,976.80 Min of Health 12 weeks

7 5/3/2019 Construction of 50No Hand Pumps Boreholes at 50 Communities Across the State FGPC/5/2019/VOL.I/6 Sir Walter & Gen Serv 36,897,000.00 Min of Water Resources 16 weeks

8 20/06/2019 Construction of block line drain and Filling of Low Area in Majia Community of taura LGA JEC/37/2019/VOL.I/6 Ummukhulsum Invest 86,485,008.42 Ministry of Works 6 month

Construction of 2No. New Solar Powered Water supply Schemes at Malarin Gamm in Malam 9 31/05/2019 Madori Local Government Area and Walawa in Birniwa Local government Area Hadejia Zone FGPC/33/2019/VOL.I/6 BSY Industries Nig Ltd 12,046,650.00 Ministry of Water Resources 8 weeks

10 31/05/2019 Rehabilitation of 17no. Small towns water supply schemes at hadejia and jahun Zone FGPC/34/2019/VOL.I/6 BSY Industries Nig Ltd 5,161,739.63 Ministry of Water Resources 8 weeks Construction of 45No Hand Pumps Boreholes Water Supply to 45No Community at Babaduro, Gigar, Hazo, Unguwar Duna, Unguwar Naino Fulani, Wada, unguwar , Tudun Bayal, Janzomo, Kaikajo, Maizuwo, Yanmaulu, Mara, Kuldu A Malle, Matuntu, Gareji, Fulanin Kutumbi, Gandore, Fulanin Kandi, Shashatu, Cirimbin, Gumuzu,Arkel, Akula Quarters, Unguwar Sani, Yantuba, Waje Gari, Kandiren Fulani, Unguwar Mayau, Middle East, Karambanin Na Binni, Rahar Yusuf, Amsharawa Fulani, Gujguru Fulani, Burukun Fulani, Mudiri Fulani, Luggar Unguwar Turewa, Tirewa, Kurgun, Gagarawa, Sankarawa, Tasawa, Gangar Fulani, Bodawa G/Gurgu Danniya and Sayawa G/Mal, Ali Mai Rogo in Babura Local 11 7/3/2019 Govt Area FGPC/8/2019/VOL.I/6 Safah & Fresh Ltd. 33,207,300.00 Min of Water Resources 16 weeks Construction of 1No. Block of 4No. House of 2No. Bedroom Semi-Detach at Kazaure Local 12 19/3/2019 Government Area FGPC/13/2019/VOL.I/7 Al-Sabur Global Links 10,779,821.20 Min of Land 14 Weeks Construction of 1No. Block of 4No. House of 2No. Bedroom Smi-Detach at Gumel Locl 13 19/3/2019 Government Area FGPC/10/2019/VOL.I/7 Yalwa Oil & Gas Ltd 10,773,337.15 Min of Land 14 Weeks Construction of 1No. Block of 4No. House of 2No. Bedroom Smi-Detach at Ringim Locl 14 19/3/2019 Government Area FGPC/14/2019/VOL.I/7 Al-Sabur Global Links 10,779,821.20 Min of Land 14 Weeks Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach at Babura Local 15 19/3/2019 Government Area FGPC/9/2019/VOL.I/7 Yalwa Oil & Gas Ltd 10,773,337.15 Min of Land 14 Weeks Construction of 1no Block of 4No House of 2No Bedroom Semi-Detach (lot-2) at Birnin Kudu 16 19/3/2019 Local Government Area FGPC/16/2019/VOL.I/7 Babandoki General Enterprises 10,651,650.00 Min of Land 14 Weeks Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach (Lot-6) at Hadejia 17 19/3/2019 Local government Area FGPC/17/2019/VOL.I/7 Ngaloma Construction 10,719,537.18 Min of Land 14 Weeks

Bal.C/F 558,439,549.34 1

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRY COMP. PERIOD

BAL. B/F 558,439,549.34 Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach (Lot-9) at Malam 18 19/3/2019 Madori Local government Area FGPC/18//2019/VOL.I/7 Ngaloma Construction 10,719,854.25 Min of Land 14 Weeks Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach (Lot-4) at Dutse Local 19 19/3/2019 government Area FGPC/11/2019/VOL.I/7 Loyalty Properties Ltd 10,582,286.69 Min of Land 14 Weeks Construction of 1no Solar Powered water supply scheme at Nafara in Kiyawa LGA, Dutse 20 16/4/2019 Zone FGPC/26/4/2019/VOL.I/6 Sims Global Resources 6,023,325.00 Ministry of Water Res 8 weeks Construction of 4No. Solar Powered Water supply scheme at Danmarke, Wada,Kayarda and 21 16/4/2019 Garin Baki in Babura LGA Ringim Zone FGPC/25/2019/VOL.I/6 Sims Global Resources 24,093,300.00 Ministry of Water Res 12 Weeks

22 16/4/2019 Construction of 1No. Solar Powered Water Supply Scheme at Dora in Garki LGA Ringim Zone FGPC/27/2019/VOL.I/6 Sims Global Resources 6,023,325.00 Ministry of Water Res 8 Weeks Rehabilitation of 2No Small Towns water supply schemes at Yandamo and Malam Baki in 23 31/5/2019 Gumel Zone FGPC/35/2019/VOL.I/8 Forte Technical Services Ltd 8,482,573.26 Ministry of Water Res 8 weeks Construction of 6No Hand Pump Boreholes water supply scheme at Yandamo Kulle 2, umarni, Modoji Babba, Fulanin Riggade, Gidan Hardo Musa ( Fulanin Asayaya) in Sule 24 8/5/2019 Tankarkar Local Government Area and Tamburawa in Kafin Hausa LGA FGPC/30/2019/VOL.I/6 K-Manu Gen Construction 4,427,640.00 Ministry of Water Res 12 weeks

Construction of 12No Hand Pump Boreholes water supply schemes at Sule Fulanin Yandamo ( Gidan Mallam) Fulanin Kwalawa( Gidan Kato dan Goma), Fulanin dan Kiri ( Gidan Dan Bako) Garin Goto, Fulanin Kukule Gabas ( Gidan Isah Kato) Fulanin Malam Kadiri ( Gidan Sale), Fulanin Dantuwo ( Gidan Ingire), Dan Adama Gari, Fulanin Dan Adama ( Gidan ), Dankira, Sabon Garin Dankirya and Fulanin dan Kumbo ( Gidan Hardo Kan Doki) in Sule 25 8/5/2019 Tankarkar Local Government Area Gumel Zone. FGPC/29/2019/VOL.I/6 Al-Juraj Synergy Concept 8,855,280.00 Ministry of Water Res 12 weeks Construction of (1No.) Block of Twenty (20) Rooms Students Hostel at Jigawa State Intitute 26 28/06/2019 of Information Technology kazaure JEC/40/2019/VOL.I/7 Babandoki General Enter 47,989,101.98 Ministry of Education 16Weeks

27 21/06/2019 Renovation of Structures at Government Science Secondary School Lautai Gumel ( Phase II) JEC/39/2019/VOL.I/6 Gerawa Gobal Engr Ltd 98,014,279.51 Ministry of Education 6 month

Construction of 15No. Hand Pumps Boreholes water supply scheme at Sinti, Garin Goshi, Fulanin Masama ( Hardo Tamabya) Dantuwo Gari, Dantuwo Tsangaya, Tashar Bala S/Tankarkar, Balarabe Mai Gari, Fulanin Jalko( Gidan Rabiu) Hardo Dan Kawo ( Fulanin Kuka Maidire), Sabon Garin Dan Yarda, Fulanin Dan Banki ( Gidan Sha'aibu Jikan Hajja), Fulanin Tiriki ( Hardo Ilu), Fulanin Charko(Gidan Dabbi) and Ma'azu Gidan Salisu Tifa in Sule 28 8/5/2019 Tankarkar Local Government Area, Gumel Zone FGPC/28/2019/VOL.I/6 Al-Kawakeb Global Concept 11,069,100.00 Ministry of Water Res 12 weeks

Printing of 2019 Basic Education certificate examination (BECE) question papers with answer 29 13/6/2019 sheets for JSS Across the State JEC/52/2019/VOL.I/7 Clear Impressions Ltd 15,260,680.05 Ministry of Education 8 weeks

30 10/7/2019 Rehabilitation of ITC line from Kwanar Gawo to Hago in Kafin Hausa Local Government Area JEC/44/2019/VOL.I/5 Tasiu Muhammad Invest Ltd 8,333,050.69 Ministry of Works 8 weeks

Bal.C/F 818,313,345.77 2

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRY COMP. PERIOD

BAL. B/F 818,313,345.77

Construction of 22No Hand Pump Boreholes water supply schemes at Yandamo gari A, Yandamo Gari B, Garin Yasai, Hardo Jauro, Kargo, Fulanin Lula, Madoji Tsalle, Fulanin Barnawa Fulanin Bayan Eka STK, Fulanin Santarbi, Dangoho, Fulanin Mai Rago ( Yamma) Buntusu Fulani, Fulanin Hardo Musa S.Tankarkar Fulanin Kurguna, Fulanin Kaina unguwar Yamma ( Danzomo) in Sule Tankarkar LGA and Kwanar Tsuru, Garin Kwalandi, Garin Malam, 31 8/5/2019 Gabasawar Kwalandi and Fulanin Shabarawa ( Gidan Ibrahim Bidu) in Maigatari LGA FGPC/31/2019/VOL.I/6 Forte Technical Services Ltd 16,234,680.00 Ministry of Water Res 12 weeks Re-Construction of the damaged sections of Abunabo-Kadira-Guri Road (Phase-III of Eastern 32 15/07/2019 Bye Pass) JEC/45/2019/VOL.I/6 CGC Nig Ltd 50,000,000.00 Ministry of Works 10 weeks

33 6/9/2019 Renovation works at Deputy Governor's Official Residence, Dutse DGO/PRJ/003/V.I/17 Daniya Atiku Associate Ltd. 17,129,210.40 Cabinet Office 12 weeks

34 1/7/2019 Contract for the supply & Installation of Medical Equipment to Ringim General Hospital JEC/42/2019/VOL.I/7 Dagarai Integrated Srv 82,153,507.50 Min of Health 8 weeks Rehabilitation of Karshi-Gagarawar Karshi ITC Line and Extension of Farin Gida TDN in Ringim Local Government Area, Rehabilitation of Yandutse-Malamawar Yandutse ITC in 35 30/07/2019 Ringim LGA JEC/46/2019/VOL.I/6 Almajeed Constr Ltd 11,391,654.86 Min of Works 10 weeks

36 10/7/2019 Re-construction of fallen wall fence at GGUSS Garki and GUSS M/Madori JEC/54/2019/VOL.I/6 Pullad Global Consult 9,039,035.07 Ministry of Education 8 weeks

Constr of (38No) Hand Pumps at Makadi'B', Gangara waje, jiji'B' Unguwar Sama, Gidan Hardo Gawo, Gidan Beti dan Maigari, bodawa C, Unguwar Tsamiya B, GJASS Baura, GGADSS Babuura, Tsadura, Babura Arewa B, Kaute B, in babura LGA, Dutse Capital School in Dutse, unguwar Lawan in Jahun, tunubu town in Jahun, kuka in /S/Tankarkar, Gidan Danta Fulani, Kanawa Aume, dan Amale Fulani, Gage Yamma, Jelawa Damu, Kauyen Fulani HP in babura LGA, Shamuri HP in S/Tankarkar, Tinubu, Hayin Tara Yamma in Jahun, Burukum Fulani, Gidan Makeri, Minu, Unguwar Magaji, Batali, Malamawa, Bikawa Batali, Muni A, Gidan Dawa and 37 9/8/2019 Dan Makeri G/Nagawo in babura LGA JEC/53/2019/VOL.I/6 Bulangu Drilling 28,041,729.00 Min of Water Resources 14 weeks Renovation of Storm damages at 7no. Schools across the state : GGASS S/Tankarkar, GUSS maigatari, GDSS Shagari Qtrs. Hadejia, GSS Aujara, GDSS Buji, GGDSS Birnin Kudu and Dutse 38 15/8/2019 Model Int School. JEC/55/2019/VOL.I/9 AGM & Sons Nig 23,498,908.59 Mininstry of Education 8 weeks Renovation of storm damages at GDASS Dantanoma in Gumel LGA, School of Arabic and Islamic Studies (SAIS) Hadejia, GDASS Zainab Kazaure, GDASS Dabi in Ringim, GDASS 39 16/8/2019 Gwaram and GGASS Danzomo in Gagarawa LGA JEC/56/2019/VOL.I/10 Pullad Global Consult 53,582,692.89 Ministry of Education 16 weeks Upgrading and Conversion of 1No. Motorixzed water supply scheme to solar powered at 40 6/8/2019 Maizuwo in Sule tankarkar LGA FGPC/50/2019/VOL.I/6 Sims Global Resources 6,829,987.50 Min of Water Resources 4 weeks

Upgrading and Coversion of 1No. Motorized water supply scheme to solar powered to 41 6/8/2019 Gangara in Babura LGA FGPC/51/2019/VOL.I/6 Sims Global Resources 6,829,987.50 Min of Water Resources 4 weeks

Bal.C/F 1,123,044,739.08 3

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT EXECUTING MINISTRIES COMP. PERIOD (N) BAL. B/F 1,123,044,739.08 Works

42 2/10/2019 2019 Rural Electrification Project at Kulawa in Ringim LGA (Lot-9) JEC/71/2019/VOL.1/17 Ngloma Constr Nig Ltd 40,761,674.94 Min of Works 14 weeks

43 2/10/2019 2019 Rural Electrification Project at Kaigamari M/Awaso in K/Hausa LGA (Lot-7) JEC/72/2019/VOL.1/17 Babandoki Gen Entp. 56,156,069.34 Min of Works 14 weeks

44 2/10/2019 2019 Rural Electrification Project atTurbus in Maigatari LGA (Lot-8) JEC/73/2019/VOL.1/17 Babandoki Gen Entp. 51,909,858.00 Min of Works 14 weeks

45 2/10/2019 2019 Rural Electrification Project at Daurawa in Taura LGA (Lot-11) JEC/75/2019/VOL.1/17 Ngloma Constr Nig Ltd 39,499,187.75 Min of Works 14 weeks

46 2/10/2019 2019 Rural Electrification Project at Batali in Babura LGA (Lot-14) JEC/76/2019/VOL.1/17 Ngloma Constr Nig Ltd 87,414,189.61 Min of Works 14 weeks

47 2/10/2019 2019 Rural Electrification Project at Duwigi in Gwiwa LGA (Lot-13) JEC/74/2019/VOL.1/17 Babandoki Gen Entp. 45,418,689.70 Min of Works 14 weeks

48 2/10/2019 2019 Rural Electrification Project at Ringim in Yankwashi LGA (Lot-12) JEC/70/2019/VOL.1/17 Pullad Global Consultant 59,238,524.45 Min of Works 14 weeks

49 2/10/2019 2019 Rural Electrification Project at Batu in Birniwa LGA (Lot-5) JEC/66/2019/VOL.1/17 Masaka Global Concepts 42,505,703.10 Min of Works 14 weeks

50 2/10/2019 2019 Rural Electrification Project at Walawa in Hadejia LGA (Lot-4) JEC/65/2019/VOL.1/17 Ngloma Constr Nig Ltd 52,780,791.53 Min of Works 14 weeks

51 2/10/2019 2019 Rural Electrification Project at Kadira in Guri LGA (Lot-6) JEC/67/2019/VOL.1/17 Xtrax 99 integrated Services 101,346,796.79 Min of Works 14 weeks

52 2/10/2019 Electrification project (Lot-17) at Gangara Qtr. In Gumel LGA. JEC/78/2019/VOL.1/17 Ibrahim Yusuf Integ. 23,258,058.11 Min of Works 14 weeks

53 2/10/2019 Electrification project (Lot-15) at Masko villege in Babura LGA. JEC/77/2019/VOL.1/17 Nuhabib Nig. Ltd. 32,792,767.93 Min of Works 14 weeks

54 2/10/2019 Electrification project (Lot-2) at Gangawa village in Jahun LGA. JEC/63/2019/VOL.1/17 Yanduna Ventures 90,247,560.30 Min of Works 14 weeks Constr of 1no. Block of 3-classrooms each at GDSS Babura, GDSS Galagamma Gumel, GDSS 55 3/10/2019 babura and GDSS Ringim Areawa (2019 Capital projects) JEC/79/2019/VOL.1/8 Babandoki Gen Entp. 44,808,022.00 Min of Edcuation 12 weeks Constr of 1no. Block of 3-classrooms each at GDSS Dan Masara, GDSS Jahun, GDSS Shagari 56 3/10/2019 Qtrs Hadejia and GDSS M/madori (2019 Capital projects) JEC/80/2019/VOL.1/8 Math Global Invest. 44,808,022.00 Min of Edcuation 12 weeks

Renov of Science and ICT Labs. at 9no. Proposed Science Centres of Excellence core 2 (GGUSS M/madori, GDSS G/Gabas, GGSS Garki, GDSS Gwiwa, GUSS Aujara, GUSS Maigatari, 57 25/09/2019 GDSS T/Gwaram, GC Birnin Kudu and GUSS Basirka) JEC/61/2019/VOL.1/6 AGM & Sons Nig Ltd. 24,140,000.00 Min of Edcuation 12 weeks Constr of hadejia township roads (485m) road Network) Additional works) at Azare road- 58 2/10/2019 Adua Mosque-New Motor Park (Road II) JEC/71/2019/VOL.1/52 PAAche Constr Ltd. 312,270,011.92 Min of Works 16 weeks

59 2/10/2019 Constr of Babura township roads (10.28km) (Additional works) JEC/218/2018/VOL.1/31 Triacta Nig Ltd. 510,841,607.48 Min of Works 16 weeks Upgrading and Conversion of 1no. Motorised water supply scheme to Solar power at 60 27/9/2019 UKU da SISI Sabuwa in Babura LGA JEC/63/2019/VOL.I/7 Sims Nig. Ltd. 6,767,532.45 Min of Water 8 weeks 61 27/9/2019 Rehab. of 13no. Water supply scheme at Ringim, Kazaure and Gumel LGA JEC/64/2019/VOL.I/7 Sims Nig. Ltd. 12,788,475.00 Min of Water 8 weeks Constr of (1no.) New Solar powered water supply scheme at YAN Maulu Tsohowu in 62 27/9/2019 Babura LGA JEC/62/2019/VOL.I/7 Sims Nig. Ltd. 6,023,325.00 Min of Water 8 weeks

Bal.C/F 2,808,821,606.48

4

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 2,808,821,606.48

63 7/10/2019 Re-construction of B/kudu New General Hospital (Variations) JEC/20/2019/VOL.I/10 Datum Constr. Ltd. 395,712,672.97 Min of Health 16 weeks Constr of 1no. Block of 3-classrooms each at 8no. GDSS across the state (2019 Capital 64 28/10/2019 Projects) JEC/87/2019/VOL.I/9 Math Global Invest. Ltd. 90,089,432.00 Min of Education 14 weeks

Upgrading and Conversion of 1no. Motorised water supply scheme to Solar powered 65 11/10/2019 atJigawar Dan Ali, Garun Gudunya in Babura LGA and JEKE in S/Tankarkar LGA JEC/81/2019/VOL.I/13 Sims Nig. Ltd. 18,459,647.97 Min of Water 8 weeks

66 11/10/2019 Rehab. of 19no. Water supply scheme in Babura (Ringim zone) JEC/82/2019/VOL.I/13 Sims Nig. Ltd. 17,361,750.00 Min of Water 8 weeks Renovation of Staff Quarters at College of Education Gumel, Lot-7 (3rd & 4rd Quarter 2019 67 27/11/2019 Capital projects) JEC/117/2019/VOL.I/10 Babandoki General Entr 233,513,402.67 Min of Education 12 weeks Construction of 1No Block of 2 classroom Islamiyya School each, Lot-4 (First Quarter 2019 68 27/11/2019 Constituency Project) at Dodal (Nomadic and Jammaje Gafaffa in Gwiwa JEC/99/2019/VOL.I/11 Isah Halilu Nig Ltd 6,226,306.20 Min of Education 8 weeks Construction of classrooms Blocks at Jigawa College of Remedial and Advance 69 27/11/2019 Studies(JICORAS) Babura, Lot-4 (3rd & 4rd Quarter 2019 Capital Projects) JEC/115/2019/VOL.I/10 Babandoki General Entr 120,213,423.86 Min of Education 24 weeks Construction of 1No Block of 2 Classroom islamiyya School Lot-14B (First Quarter 2019 70 27/11/2019 Constituency Project) at Hassan Hadejia in Hadejia constituency JEC/106/2019/VOL.I/11 Muhal Global Concept Ltd 9,100,200.00 Min of Education 9 weeks Renovation of 13No Students Hostels at College of education Gumel, Lot-8 (3rd &b 4rd 71 27/11/2019 Quarter 2019 Capital Projects) JEC/118/2019/VOL.I/10 Babandoki General Entr 148,840,065.71 Min of Education 12 weeks Construction of Hostel Block at Jigawa College of remedial and Advance Studies (JICORAS) 72 27/11/2019 ConstructionLot-5 (3rd & 4th of 1No.Quarter 2 classroom 2019 Capital Islamiyya Projects) School each, Lot-6 (First Quarter 2019 JEC/116/2019/VOL.I/10 Ngaloma Constr Co Ltd 100,763,064.17 Min of Education 24 weeks Constituency Project at Abur, Margadu, Ahlal Sunnah Islamiyya, Musari and Wareri in Guri 73 27/11/2019 Constituency JEC/110/2019/VOL.I/11 Adam General Enter Ltd 15,576,795.40 Min of Education 8 weeks Construction of 2No Block of 2 Classroom Islamiyya ( 2018 Phase II Ongoing Constituency 74 18/11/2019 ConstructionProjects) Lot-10 of 1Noat danksoshe Block of 2 and Classroom Jatafinnamari Islamiyya in Buji School Constituency each Lot-12 (First Quarter 2019 JEC/92/2019/VOL.I/6 Mai-Mai Blocks Industry Ltd 6,231,539.60 Min of Education 8 weeks Constituency Project at Kan Hawa Roni, Santar Tsaye and Sabuwar Santa Tunas in Roni 75 27/11/2019 Constituency JEC/104/2019/VOL.I/11 Yanduna Ventures Ltd 9,339,248.04 Min of Education 10 weeks Construction of 3no Block of 2 classroom Islamiyya ( 2018 Phase III Ongoing Constituency 76 18/11/2019 Projects) Lot-12 at Garin Kwalandi and Kabara in Maigatari Constituency JEC/94/2019/VOL.I/6 NBS & Sons Constr Ltd 15,140,562.72 Min of Education 8 weeks Construction of Malam Makera Islamiyya School (Upstairs) 2018 III Ongoing Constituency 77 18/11/2019 project (Lot-1S) at Malam Abdullahi islamiyya Hadejia in Hadejia JEC/96/2019/VOL.I/6 Nabakwai General Entr 16,341,041.20 Min of Education 12 weeks Construction of 1No Block of 2 Classroom Islamiyya (2018 Phase II Ongoing Constituency 78 18/11/2019 Projects) Lot-7 at Guri in Guri Constituency JEC/91/2019/VOL.I/6 Nushe Business Resources 3,115,779.08 Min of Education 8 weeks

Bal.C/F 4,014,846,538.07

5

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 4,014,846,538.07 Construction of 2No Block of 2 Classroom Islamiyya (2018 Phase III Ongoing Constituency 79 18/11/2019 Projects ) Lot-7 at Garin Musa and Daneri in Birniwa Constituency JEC/93/2019/VOL.I/6 BDU Ventures Ltd 6,227,358.16 Min of Education 8 weeks Construction of 1No Block of Science Laboratory and Administrative Block (Lot-1) at GDSS 80 14/11/2019 Kukuma in Buji Constituency project 2019 JEC/88/2019/VOL.I/6 Yayarin Tukur Nig Ltd 22,937,034.15 Min of Education 8 weeks Construction of 1No Block of 2 classroom Islamiyya (2018 Phase III Ongoing Constituency 81 18//11/2019 ConstructionProjects) Lot-1B of 1Noat Maskangayu Block of 3 classrooms In Auyo Constituency each at GDASS Kiri Kasamma GDASS Bulangu JEC/90/2019/VOL.I/6 DDN Constr Nig Ltd 3,115,359.08 Min of Education 8 weeks GDASS Miga GDASS Kiri Kasamma GDASS Bulangu GDASS Miga, GDASS Marma, GDASS 82 14/11/2019 Limawa , GDASS Birniwa and GDASS Aujara JEC/89/2019/VOL.I/8 A.A. Maikatako Gen Entr 78,414,000.00 Min of Education 20 weeks Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 83 11l12l2019 Constituency projects) Lot-19B at Kunduwaje and Gagura in Gwaram Constituency, JEC/132/2019/VOL.1/7 Nushe Bus, Resources Nig Ltd 6,685,247.76 Min of Education 6 weeks Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-16 at Ramin kura, Juwan, Masaru and Nasarawa in Birnin Kudu 84 11/12/2019 Constituency, JEC/128/2019/VOL.1/7 Nushe Bus, Resources Nig Ltd 12,888,711.92 Min of Education 10 weeks

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First 85 11/12/2019 Quarter) Lot-1 at Fulanin Gamba, Fulanin Garu and Fulanin Kafur in Auyo Contituency. JEC/170/2019/VOL.1/20 AMM Manzo Nig Ltd 2,210,922.00 Min of Water Resources 8 weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-26 atKankanba, Dodorin Tudu, Hardo Magaji, Mataran, Dalarin Kwalta, Bultuwa Rigar Gabas, Dodorin Rigar Mal , Bultuwa Rigar Kauga, Ung. Jibrin Masallacin Mal. 86 11/12/2019 Kawu and Rigar Dado Gajere In Kaugama Contituency. JEC/184/2019/VOL.1/20 AMM Manzo Nig Ltd 7,377,510.00 Min of Water Resources 8 weeks Constr of Solar Powered Water Supply Schemes Constituency Project ( 2019 Phase 1) Lot-42 87 11/12/2019 at Kilawa in Fagam Contituency. JEC/163/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks Upgradingand Conversation of 1no. Motorised water Supply Scheme (2019 phase1 ) 88 11/12/2019 Constituency Project Lot-22 at Zauma in Gwiwa Constituency. JEC/167/2019/vOL.1/9 Jignaj Global Contr Ltd 8,685,075.00 Min of Water Resources 8 weeks Upgradingand Conversation of 1no. Motorised water Supply Scheme (2019 phase1 ) 89 11/12/2019 Constituency Project Lot-23 at Korayalin Gwiwa Constituency. JECl168/2019/VOL.1/9 Jignaj Global Contr Ltd 6,863,325.00 Min of Water Resources 8 weeks Renov of 2no. Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 90 11/12/2019 24 at Gidan Kudege and Kurneji in Gwiwa Constituency JEC/169/2019/VOL.1/9 Jignaj Global Contr Ltd 3,227,700.00 Min of Water Resources 8 weeks Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 41 91 11/12/2019 at tsallakawa in Fagam Constituency, Gwaram Local Government Area JEC/162/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 46 92 11/12/2019 at Garin Urema in Hadejia Constituency JEC/165/2019/VOL.1/9 A+Tech Integrated Nig. Ltd 6,021,855.00 Min of Water Resources 8 weeks Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 45 93 11/12/2019 at Gawon Dogari in Hadejia Constituency JEC/164/2019/VOL.1/9 Amia Integrated Service Nig Ltd 6,022,485.00 Min of Water Resources 8 weeks

Bal.C/F 4,197,569,561.14

6

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 4,197,569,561.14

Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 39 94 11/12/2019 atSabon Gari in Miga Constituency JEC/160/2019/VOL.1/9 Amia Integrated Service Nig Ltd 6,022,485.00 Min of Water Resources 8 weeks

Upgrading and Conversion of Zaburan, Small Town Motorised Water Supply Scheme to Solar 95 6/8/2019 Powered in Kaugama Local Government Area. FGPC/49/2019/VOL.1/7 Sims Global Resources Nig Ltd 16,917,862.50 Min of Water Resources 8 weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-9 at Askawa, Kulawa Babare, Achau Boro, Lugga Dashi, Tokai Arewa, Ung. M. Nagoggo, Damutawa, Gabashi, Rinde fulani, Bakin Kasuwa, Ung. Isah Yar Jigawa, Gwamfai 96 11/12/2019 Sabon Gari, Tsangaya, Kulluru Yammaci, Alikau, Sukullufi, Gidan Atiku, Makera, Gwamfai, JEC/177/2019/VOL.1/20 Danfatu & sons Nig Ltd 14,755,650.00 Min of Education 8 weeks Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-8 at Dansama , Gangara, M. Yaro and Garin Baki in Maigatari 97 27/11/2019 Constituency, JEC/101/2019/VOL1/11 Mai-Mai Block Ind. Ni g Ltd 9,310,318.35 Min of Education 9 weeks Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-1 at Girdo, Tasawa and Tsamiyar Kwance in Kanya Babba 98 27/11/2019 Constituency Babura Local Government Area JEC/97/2019/VOL.1/12 Dee- Tech Nig Ltd 9,347,337.24 Min of Education 13 weeks Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-7 at Jauga, Jankawa Yola, Karwai, Wailari and Budai in Ringim 99 27/11/2019 Constituency JEC/100/2019/VOL.1/11 Marb eng. & Multi service Nig Ltd 15,576,585.00 Min of Education 8 weeks Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 100 27/11/2019 Constituency projects) Lot-3A at Bukari and Aimas Kuka in Auyo Constituency JEC/98/2019/VOL.1/11 Mai-Mai Block Ind. Ni g Ltd 6,226,518.18 Min of Education 12 weeks Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-13 at Kiri Hawandu, Katarika and Kawari/Gujungu in Taura 101 27/11/2019 Constituency JEC/105/2019/VOL.1/11 Nushe Bus, Resources Nig Ltd 11,719,771.12 Min of Education 12 weeks Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 40 102 11/12/2019 at Gidan Barwa in Miga Constituency JEC/161/2019/VOL.1/9 A. Barde Global Concept Ltd 6,023,010.00 Min of Water Resources 8 weeks Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 4 at 103 11/12/2019 Juba Gandu in Auyo Constituency JEC/137/2019/VOL.1/9 Alh. Baban Doki Nig Ltd 6,004,715.00 Min of Water Resources 8 weeks Constr of Water Collection Point 2019 First Quarter Constituency Project (Lot-22) at Yofai, Tuyau, Gidan Kara, Dagasa, Jiyau, Fulani, Jiyau Babba, Tagwai, Kun Kurawa, Danbaje, Auramo Gabas Zangon Sallau, Dan Tsiru, Tsurutawa, Auramo Tudu, Gidan Sani, Zabara, Durno, Kuna, 104 11/12/2019 Dara Zai and Bangon Jani in Ringim Constituency. JEC/193/2019/VOL.1/20 Prestige Integ Serv. Nig Ltd 25,206,980.00 Min of Water Resources 8 weeks Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 39 105 11/12/2019 at Gabari in Malam Madori Constituency JEC/159/2019/VOL.1/9 Prestige Integ Serv. Nig Ltd 6,022,695.00 Min of Water Resources 8 weeks Constr of additional 1no. Block of 3- Classrooms each at GDSS Kazaure, GDSS Sabon Gida, GDSS Haruna (Hadejia), GDSS Fagoji, GDSS Galagamma Gumel and GDSS Famfo Goma 106 3/12/2019 Hadejia (2019 MOEST Capital project) JEC/120/2019/VOL.1/6 Al-sabur Global Links Nig Ltd 67,212,333.84 Min of Education 12 weeks

Bal.C/F 4,397,915,822.37

7

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 4,397,915,822.37 Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 3 at 107 23/12/2019 Sabuwar Auyo in Auyo Constituency JEC/278/2019/VOL.1/6 A.A Aljazeera Agro Processing Nig Ltd 6,010,515.00 Min of Water Resources 8 weeks Renov/Completion of 2no. Friday prayer mosques (2019 first Quarter constituency projects) 108 17/12/2019 Lot_91 at Danmakama and Dangwanki In Sule Tankarkar Constituency. JEC/267/2019/VOL.1/25 A.A Aljazeera Agro Processing Nig Ltd 7,331,978.53 Cabinet office 8 weeks

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-28 at Tashar Yellow, Fulani Cakindi, Turkushawa Gari, Gidan Amadu Inge, 109 11/12/2019 Fulanin Kaina, G. Idi Shiba, Fulanin Hammado, Gidan Dibbo in Sule Tankarkar Contituency. JEC/186/2019/VOL.1/20 A.A Aljazeera Agro Processing Nig Ltd 4,426,695.00 Min of Water Resources 8 weeks Renov/Completion of 1no. Friday prayer mosques (2019 first Quarter constituency projects) 110 17/12/2019 Lot_82 at Bango in Fagam Constituency. JEC/260/2019/VOL.1/25 A.A Aljazeera Agro Processing Nig Ltd 6,202,006.45 Cabinet office 8 weeks Constr of Water Collection Point 2019 First Quarter Constituency Project Lot- 19 at Kofar Kudu Basirka, kofar Yamma Basirka Dal and Kofar Tela Basirka in Fagam Constituency, 111 11/12/2019 Gwaram LGA JEC/190/2019/VOL.1/20 Jignaj Global Contr Ltd 4,876,422.00 Min of Water Resources 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 49 at 112 17/12/2019 Butiranawa Fulani, Buduru nad Fulanin Bayan Zarga in Taura Constituency. JEC/235/2019/VOL.1/25 Gamdu Multi Purpose Ltd 5,874,753.15 Cabinet office 8 weeks

Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 1 at 113 17/12/2019 Maro, Katangar Tsamiya, Guyu, and Tsurufawa in Auyo Constituency. JEC/197/2019/VOL.1/25 Gamdu Multi Purpose Ltd 7,833,028.20 Cabinet office 8 weeks Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 114 11/12/2019 Constituency projects) Lot-10B, at Bashuri in Dutse Constituency, JEC/135/2019/VOL.1/7 Al-kheeyad Nig Ltd 3,115,676.00 Min of Education 8 weeks Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 24 at 115 17/12/2019 Oliya Sararin Rakuma and Lungum Mutari Dankoli in Hadejia Constituency. JEC/217/2019/VOL.1/25 Alh. Umaru Baban Doki Nig Ltd 8,949,483.00 Cabinet office 8 weeks

Completion/Renov. 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 116 17/12/2019 57 at Kantin Waje, Tudun Wada, Unguwar NTA and Yankoli in Hadejia Constituency. JEC/243/2019/VOL.1/25 Alh. Umaru Baban Doki Nig Ltd 10,339,715.08 Cabinet office 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 30 at 117 17/12/2019 Jallomi Arewa, Manak and Kanjiwa in Kaugama Constituency. JEC/220/2019/VOL.1/25 Alh. Umaru Baban Doki Nig Ltd 5,870,866.05 Cabinet office 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 31 118 17/12/2019 atDaneri, Kanoke and Kota in Kaugama Constituency. JEC/221/2019/VOL.1/26 Alh. Umaru Baban Doki Nig Ltd 5,884,568.55 Cabinet office 8 weeks Renov of 2no. Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 119 11/12/2019 24 at Gidan Kudege and Kurneji in Gwiwa Constituency JEC/169/2019/VOL.1/9 Jignaj Global Contr Ltd 3,227,700.00 Min of Water Resources 8 weeks

Constr of Water Collection Point 2019 First aquarter Constituency Project Lot- 23 at Kauyen 120 11/12/2019 Zarga and Rigarsu Iro Akwai Allah In Taura Constituency JEC/194/2019/VOL.1/20 Nushe Bus, Resources Nig Ltd 2,519,647.20 Min of Water Resources 8 weeks

121 11/12/2019 Constr of Jigawar Dan Ali Township Road (2.10KM) (Additional Work) FGPC/887/2018/VOL.1/51 Mother Cat Nig Ltd 203,412,195.00 Min of Works 16 weeks Constr of Gwaram Tsohuwa and Gwaram Sabuwa Towns Water Supply Scheme (Additionsl 122 11/12/2019 Works) FGPC/897B/2018/VOL.1/13 Nushe Bus, Resources Nig Ltd 29,520,524.45 Min of Water Resources 12 weeks

Bal.C/F 4,713,311,596.03

8

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 4,713,311,596.03 Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Ringim Arewa, K/Babba, Gujungu, Sakwayya and G/Kuka (2019 Last Quarters MOEST Capital project 123 23/12/2019 Across the state (Lot-1ABCD&E) JEC/290/2019/VOL.1/9 Ngaloma Constr Nig Ltd 103,609,125.68 Min of Education 12 weeks

Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Bosuwa, 124 23/12/2019 Taura, and Gumel (2019 Last Quarters MOEST Capital project Across the state (Lot-3AB&C) JEC/292/2019/VOL.1/9 Babandoki Gen. Enterp Nig Ltd 104,213,888.67 Min of Education 12 weeks Constr of Classes, Laboratories at GDSS Kafin Hausa, Kadira, Shagari, Dakido, Kanti, Roni, Danmasara, Kudai, Birnin Kudu, Malamadori and Kiyawa (2019 Last Quarters MOEST Capital 125 27/12/2019 project Across the state (Lot-5ABC&D) JEC/315/2019/VOL.1/9 Sabon Garin yaya Nig Ltd 106,186,110.20 Min of Education 12 weeks Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Galadi, GDSS Marabusawa, GDSS Dakido (2019 Last Quarters MOEST Capital project Across the state 126 27/12/2019 (Lot-4AB&C) JEC/314/2019/VOL.1/9 Math Global Invt. Nig Ltd 104,338,846.77 Min of Education 12 weeks Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Danzomo, GDSS Abdulkadir, and GDSS Babaldu (2019 Last Quarters MOEST Capital project 127 27/12/2019 Across the state (Lot-7AB&C) JEC/317/2019/VOL.1/9 Pullad Global Consultant Nig Ltd 114,843,483.25 Min of Education 12 weeks Constr of Toilets, Admin Blocks, Laboratories and Wall Fence, 7no. JSQ Eamination Hall and additional course of Blocks Hand pumps at GDSS Kazaure, Dutse Capital, Bamaina Academy, Dutse Model and GDSS Jabo (2019 Last Quarters MOEST Capital project Across the state (Lot- 128 27/12/2019 6 ABCDE&F) JEC/316/2019/VOL.1/9 Pullad Global Consultant Nig Ltd 109,273,620.31 Min of Education 12 weeks Constr of Admin. Block, 21 Laboratories, Computer Lab. And 3-Blocks of 12 Classrooms at Mega School Dutse (2019 Last Quarter MOEST Capital projects) Across the State (Lot-8 ABC & 129 23/12/2019 D) JEC/297/2019/VOL.1/9 Babandoki Gen. Enterp Nig Ltd 224,397,873.13 Min of Education 12 weeks Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-65 at 130 17/12/2019 Yayarin Tukur Yamma In Buji Constituency JEC/246/2019/VOL.1/25 Yayarin Tukur Nig Ltd 10,318,579.38 Cabinet office 8 weeks Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 10 at 131 17/12/2019 Kabbe, J/mesa and Kore Bakwarga in Buji Constituency. JEC/204/2019/VOL.1/25 Yayarin Tukur Nig Ltd 3,920,345.07 Cabinet office 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 9 at 132 17/12/2019 U/Malam Amadu Damisa, Dambazaau Yamma and Kawaya Kudu in Buji Constituency. JEC/203/2019/VOL.1/25 Yayarin Tukur Nig Ltd 5,880,518.55 Cabinet office 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 21 at Yola 133 17/12/2019 Kauye, Unguwar Gandu and Shema in Gwiwa Constituency. JEC/214/2019/VOL/1/25 Jignaj Global Contr Ltd 5,884,566.00 Cabinet office 8 weeks Constr of 3no Modified Basic Health Clinics at Bagadaza, Larkan and Dukwana in Fagam 134 24/12/2019 Constituency (2019 Constituency projects) JEC/301/2019/VOL.1/7 Yayarin Tukur Nig Ltd 25,565,018.85 Min of Health 12 weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-12 at Sabuwar Jawo (sabaru ward), fulanin Ballami (Dandi ward), K/mal. Ali Headmaster (Gada ward), K/Alto Makeri (Gada ward) and Makabarat Gabas ( Gada ward) in 135 11/12/2019 Kazaure Contituency. JEC/179/2019/VOL.1/20 Yanduna Venture Nig Ltd 3,686,287.50 Min of Water Resources 8 weeks

Bal.C/F 5,635,429,859.39

9

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 5,635,429,859.39 Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 136 11/12/2019 Constituency projects) Lot-21 Dumbi, Yarchidau and Gurjiya in Yankwashi Constituency, JEC/133A/2019/VOL.1/7 Yanduna Venture Nig Ltd 9,339,771.12 Cabinet office 12 weeks Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-15 at Daba, Tsohuwar Jawo, Islamiyya Layin Emilalo and Bayan 137 11/12/2019 Lawan Yarima in Kazaure Constituency, JEC/127/2019/VOL.1/7 Yanduna Venture Nig Ltd 12,427,559.12 Cabinet office 10 weeks Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-8 at 138 11/12/2019 Tsohuwar Fitare in Kazaure Constituency JEC/141/2019/VOL.1/9 Yanduna Venture Nig Ltd 6,023,115.00 Min of Water Resources 8 weeks Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-7 at 139 11/12/2019 Wawan Rafi in Kazaure Constituency JEC/140/2019/VOL.1/9 Yanduna Venture Nig Ltd 6,023,115.00 Min of Water Resources 8 weeks Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 48 at 140 17/12/2019 Bandakado and Kuka in Sule Tankarkar Constituency. JEC/234/2019/VOL.1/25 HM Dagara Ldt 3,918,215.20 Cabinet office 8 weeks Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-79 at 141 17/12/2019 Komai Allah Yayi in Miga Constituency JEC/257/2019/VOL.1/25 Amia Integrated Service Nig Ltd 10,200,863.74 Cabinet office 8 weeks Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 40 at 142 17/12/2019 Tsohuwar Dalan, Dangoli, Yandadi and Mazama In Miga Constituency. JEC/227/2019/VOL.1/25 Barde Global Concept Nig Ltd 7,840,683.40 Cabinet office 8 weeks Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 23 at 143 17/12/2019 Faranunbunare and Borandage in Gwiwa Constituency. JEC/216/2019/VOL.1/25 Jignaj Global Contr Ltd 3,923,045.70 Cabinet office 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 22 at 144 17/12/2019 Ture kwando, Unguwar Yamma and Z/sainawa G/Dagachi in Gwiwa Constituency. JEC/215/2019/VOL.1/25 Jignaj Global Contr Ltd 5,884,568.55 Cabinet office 8 weeks Compl/Renov of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-90 145 17/12/2019 at Tasheguwa in Kirikasamma Constituency JEC/266/2019/VOL.1/25 Manhaf Global Constr Nig Ltd 7,442,582.78 Cabinet office 8 weeks Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 47 at 146 17/12/2019 Tagwayen Kuka, Santarbi and Chiromawa in Sule Tankarkar Constituency. JEC/233/2019/VOL.1/25 HM Dagara Ltd. 5,877,322.53 Cabinet office 8 weeks 147 6/12/2019 Constr of Basic Health Centre (BHC) at Masaya Village in Kiyawa Constituency (2nd quarter 2018 ConstituencyJEC/124/2019/VOL/1/6 project) Umar Aliyu & Sons Nig Ltd 11,853,799.02 Min of Health 12 weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-14 at Tuda, Zakirai, K/gidan Mal Mai unguwa, Gidan Dachi, Majiyawa, Gangare, Jigawar Kaba, Mazazzaga, Yammachi, Fake cikin Gari, Kabobi, Haddori, Jama'ar isah Yaldewa/Gumai, Malamawa, Zakoro, Tasha, Jama;ar Dawa Fulani, Unguwar Abdullahi Mati, 148 11/12/2019 Jigawar Tsaba and Makarantar Andaza in Kiyawa Contituency. JEC/181/2019/VOL.1/20 Tosarawa Global Nig Ltd 14,739,900.00 Min of Water Resources 12 weeks Constr of Water Collection Point 2019 First Quarter Constituency Project (Lot-21) at Fake Cikin Gari, Kalali, Katuka Cikin Gari, Garko Cikin Gari, Shuwarin Cikin Gari, Turho, Tsurma 149 11/12/2019 cikin Gari, Kadara Dankargo and Dangoli in Kiyawa Constituency. JEC/192/2019/VOL.1/20 Tosarawa Global Nig Ltd 12,603,490.00 Min of Water Resources 8 weeks Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-66 at 150 17/12/2019 Sabon Garin Rabadi in Fagam Constituency JEC/247/2019/VOL.1/25 NBS & Sons Nig Ltd 9,171,846.17 Cabinet office 8 weeks Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-2 at 151 11/12/2019 Kafeje in Auyo Constituency JEC/136/2019/VOL.1/9 AMM Manzo Nig Ltd 6,004,215.00 Min of Water Resources 8 weeks Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-19 at 152 11/12/2019 Ruwa yakaika in Gwiwa Constituency JEC/148/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks

Bal.C/F 5,774,727,171.72

10

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 5,774,727,171.72 Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-20 at 153 11/12/2019 yola Kauye in Gwiwa Constituency JEC/149/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks

Consrt of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-21 at 154 11/12/2019 tudunya in Gwiwa Constituency JEC/150/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First 155 11/12/2019 Quarter) Lot-17 at yankwashi fulani, rauda gabas and dumbule in yankwashi constituency. JEC/183/2019/VOL.1/20 Granitoids Engr Services 2,213,032.00 Min of Water Resources 8 weeks

Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-34 at 156 11/12/2019 addani in yankwashi Constituency JEC/158/2019/VOL.1/9 Granitoids Engr Services 6,022,590.00 Min of Water Resources 8 weeks

Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-33 at 157 11/12/2019 karkarna in yankwashi Constituency JEC/157/2019/VOL.1/9 Granitoids Engr Services 6,022,590.00 Min of Water Resources 8 weeks

Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lots - 16 at 158 11/12/2019 galamawa, G/Biredi, Sabalari, sakwaya and hausawa in Dutse Constituency. JEC/209/2019/VOL.1/9 Backbone global links ltd 7,836,430.04 Cabinet office 8 weeks

Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-35 at 159 23/12/2019 manomi in Malammadori Constituency JEC/285/2019/VOL.1/6 Step by Step Int. Ser. Ltd 6,022,905.00 Min of Water Resources 8 weeks

Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-37 at 160 23/12/2019 Surakin in Malammadori Constituency JEC/286/2019/VOL.1/6 Step by Step Int. Ser. Ltd 6,022,905.00 Min of Water Resources 8 weeks

Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-9 at 161 23/12/2019 munar yan biyu in Kanya Constituency, Babura LGA. JEC/279/2019/VOL.1/6 Deetech Nig. Ltd 6,010,935.00 Min of Water Resources 8 weeks

Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-30 162 23/12/2019 atkukule in Gagarawa Constituency JEC/283/2019/VOL.1/6 Farham Synergy Ltd 6,022,800.00 Min of Water Resources 8 weeks

Constr. of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II 163 11/12/2019 constituency projects) Lot-19 at B/kasuwa, Sakuwa and Ranbazau in Gwaram constituency JEC/131/2019/VOL.1/7 Farham Synergy Ltd 9,344,513.19 Min of Education 8 Weeks Constr. of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 164 23/12/2019 31 Mutumbi in Gagarawa Constituency JEC/284/2019/VOL.1/6 Farham Synergy Ltd 6,022,800.00 Min of Water Resources 8 weeks Consrt of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 165 23/12/2019 10 at Kanya cikin gari in Kanya Constituency, Babura LGA. JEC/280/2019/VOL.1/6 Deetech Nig. Ltd 6,010,935.00 Min of Water Resources 8 weeks

Completion/Renov. 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 166 17/12/2019 55 at Kundum, Jar kasa B/kasuwa Basirka and and bangon fulani in fagam Constituency. JEC/241/2019/VOL.1/25 Yayarin Tukur Nig Ltd 9,274,972.59 Cabinet office 8 weeks Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II constituency projects) Lot-10A at jidawa, rahama, duru gari, karnaya gari, abanderi, hara and 167 27/12/2019 tashar D/wake in Dutse constituency JEC/111/2019/VOL.1/11 Backbone global links ltd 21,724,075.66 Min of Education 18 Weeks

Bal.C/F 5,885,325,095.20

11

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 5,885,325,095.20

Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II 168 27/12/2019 constituency projects) Lot-11 at dahuwa kaku in kiri kasamma constituency JEC/103/2019/VOL.1/11 Nabakwai gen. entr. 3,103,439.45 Min of Education 8 Weeks

Drilling of borehole and construction of overhead tank at fire service directorate 169 18/12/2019 headquaters in Dutse (2019 capital project) JEC/273/2019/VOL.1/8 Al-juraj synergy concept Ltd 6,734,650.13 Min of Water Resources 8 weeks

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-10 at K/hausa gen. Hospital, bayan reformatory school, alakalawa A, alakalawa B, Makarantar allo kudu K/hausa, makarantar D/jalla, Makarantar M. sa'adu, makarantar turkawa, makarantar asharan chiroma, filin idi K/hausa, makarantar su shamsu, dawasa, yan darman shukura, fulanin toyara, kashe badi, chiroma kwakwata, kutungun, aguran kwari, usman kukoki, tagadawai, abewa, kazuba, karfa kama, rigar kanawa, kazalewa UNG, sule M. tubka, kununu, lafiya, katanga, rigar D/iya, kijinawa M. sa'adu, marwa abdullawa, zilawa abdullawa, aragada abdullawa, kanzan fulani (mai jama'a jingi), kargumaka (jema haruna), karori, fulanin baushe, mamajo, fulanin rumfa and baushe gari in 170 11/12/2019 K/Hausa constituency. JEC/178/2019/VOL.1/20 Mugin Inv. Nig. Ltd 29,509,200.00 Min of Water Resources 16 Weeks Rehabilitation of 3no. Water supply scheme at danzomo, maitsamiya, and dankumbo in sule 171 19/12/2019 tankarkar (gumel zone 2019) Lot-2 capital projects JEC/276/2019/VOL.1/8 LIMIS Brothers & Co 4,628,531.25 Min of Water Resources 4 weeks

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-4 at wuro bagga, gamawari, yola zairare, fulanin takaje, sabon gidan gabas, fulanin kufayi, hijabau, adamante, rugar abdul kogi, masharmo, makwasharga, waryam B, lautayi, Yambo, Jalingo G/kwalli, kawarin gari, yadda, gidan yauto (Z/kanya), gumurwa G.A 172 11/12/2019 Idi, Rimin kasuwa and shamakeri B/hanya in Bulangu constituency JEC/173/2019/VOL.1/20 Bulangu drilling serveices Ltd 15,491,227.50 Min of Water Resources 12 Weeks Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-27 at jalomin kudu, malari, zaburan, Ung/tsamiya, kundu, marke ung gabas, Dunbari, chuguliski, rigar ya'u karami, dolon malam and arbus ung. Mamman in kaugama 173 11/12/2019 constituency JEC/185/2019/VOL.1/20 Mufabamex concept nig. Ltd 7,376,800.00 Min of Water Resources 8 Weeks

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-30 at koluma, kodau, kata kata, kayoyi, turakan fulani, gidan jauro, jalingo S/sara, Baba ari, tsangayar gabas, malumawa, karalbali iguda, gobararin fulani, fulanin kira karama, rugar babayo, gamayin yamma, kayoyi jabo, tafa, jabo gabas, makerawa H/ali and 174 11/12/2019 rugar amadu babai in bulangu costituency JEC/188/2019/VOL.1/20 yusmatech inv. Nig. Ltd 14,754,800.00 Min of Water Resources 14 Weeks

Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II Constituency projects) Lot-14A at Abdulkadir Secondary School, Matasro Junior Secondary 175 11/12/2019 School and Unguwar Mai aye in Hadejia constituency JEC/126/2019/VOL.1/7 Step by Step Int. Ser. Ltd 9,334,463.01 Min of Education 10 weeks

Constr of 2no. Township Gate in Gumel Local Government Area 2019 third quarter 176 24/12/2019 Constituency projects GHS/A/130/VOL.111/705 Gare Invest Nig Ltd 9,099,121.73 Min of Environment 8 weeks

Constr of Drainage at Kamfala Town in Malam Madori LGA 2019 First Quarter Constituency 177 24/12/2019 Project GHS/A/130/VOL.111.694 Ramadan Constr Nig Ltd 12,261,288.37 Min of Environment 12 weeks Bal.C/F 5,997,618,616.64 12

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD BAL. B/F 5,997,618,616.64 178 24/12/2019 Constr of Drainage at Hammado in Gumel LGA 2019 Third Quarter Constituency Project GHS/A/130/VOL.111/698 farham synergy con. Ltd 6,497,962.62 Min of Environment 8 weeks Constr of Drainage at Marakumi Town in Malam Madori LGA 2019 First Quarter Constituency 179 24/12/2019 Project GHS/A/130/VOL.111./679 Meyadi Concept Nig Ltd 9,923,643.97 Min of Environment 12 weeks 180 24/12/2019 Constr of Drainage at Kargo Town in Garki LGA 2019 First Quarter Constituency Project GHS/A/130/VOL.111/684 Umar Aliyu & Sons Nig Ltd 12,899,602.80 Min of Environment 12 weeks 181 24/12/2019 Constr of Drainage at Kandahar in HadejiaLGA 2019 First Quarter Constituency Project GHS/A/130/VOL.111/690 Tasi'u Muhd Invt Nig Ltd 19,286,864.77 Min of Environment 12 weeks Constr of Drainage at Dantanoma Quarters in Gumei LGA 2019 Third Quarter Constituency 182 24/12/2019 Project GHS/A/130/VOL.3/687 JAG & H Intergreted Service 7,223,498.48 Min of Environment 12 weeks

183 24/12/2019 Constr of Drainage at Dingaya Town In Gwaram LGA 2019 First Quarter Constituency Project GHS/A/130/VOL.III/701 Pullad Global Consultant Nig Ltd 16,180,030.57 Min of Environment 12 weeks 184 13/12/2019 Constr of Drainage at Fake in Kiyawa LGA 2019 2nd Quarter Constituency Project GHS/A/130/VOL.III/666 AGM & Sons Nig Ltd 14,830,841.81 Min of Environment 12 weeks

185 13/12/2019 Constr of Drainage at Makeral Kirnande in Miga LGA 2019 1st Quarter Constituency Project GHS/A/130/VOL.III/680 A. Barde Global Concopt Ltd 5,341,392.00 Min of Environment 8 weeks

186 13/12/2019 Constr of Drainage at Lungun Malamai in Hadejia LGA 2019 1st Quarter Constituency Project GHS/A/130/VOL.III/676 Amia Integrated Service Nig Ltd 4,118,002.53 Min of Environment 8 weeks Constr of Drainage and Culverts at Kukuma Town in Buji LGA 2019 1st Quarter Constituency 187 13/12/2019 Project GHS/A/130/VOL.III/670 Yayarin Tukur Nig Ltd 9,749,911.22 Min of Environment 12 weeks

188 12/12/2019 Laterite filling at Shuwarin Town in Kiyawa LGA under 3rd Quarter 2018 Constituency Project GHS/A/130/VOL.III/663 Khairushabah Nig Ltd 4,193,265.30 Min of Environment 8 weeks Constr of Additional 6no. Blocks of 1-block of 3-classrooms at GDSS Kondiko, GGDSS B/kudu, 189 24/12/2019 GDSS Kwarko, GDSS Kiyako, GDSS S/garin Takanebu and GDSS Galamawa GHS/A/4/VOL.IV/220 Babandoki Gen. Entp. 67,198,406.92 Min of Education 10 weeks

190 24/12/2019 Constr of 1-block of two Science Laboratories at GGDSS Roni GHS/A/4/VOL.IV/206 Manhaf Global Concept 33,552,607.41 Min of Education 16 weeks

191 23/12/2019 Construction of pipeline distribution network (28.6km) in Kazaure Town Lot-1 JEC/302/2019/VOL.1/8 CGC Ltd 529,952,482.00 Min of Water Resources 24 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 192 17/12/2019 97 at Basirka JIBWIS Jumu'at Mosque in fagam Constituency JEC/272/2019/VOL.1/25 Lines dimensions Nig Ltd 3,640,350.00 Min of Water Resources 8 weeks Installation of solar electrification (2019 first quarter constituency project) Lot-96 at Digijin 193 17/12/2019 and fagam central mosques in fagam constituency JEC/271/2019/VOL.1/25 Lines dimensions Nig Ltd 4,672,301.71 Cabinet office 8 weeks Installation of solar electrification (2019 first quarter constituency project) Lot-95 at galambi 194 17/12/2019 and basirka central mosques in fagam constituency JEC/270/2019/VOL.1/25 Lines dimensions Nig Ltd 4,478,167.05 Cabinet office 8 weeks Consr rof 1NO. Solar Powered Water Supply Scheme Lot-7 at Daki daka in Garki LGA (Ringim 195 19/12/2019 zone 2019)-capital project JEC/275/2019/VOL.1/8 LIMIS Brothers & Co 6,019,125.00 Min of Water Resources 8 weeks Constr of 1NO. Solar Powered Water Supply Scheme Lot-8 at Kunyafa in Babura LGA (Ringim 196 19/12/2019 zone 2019)-capital projects JEC/274/2019/VOL.1/8 LIMIS Brothers & Co 6,019,125.00 Min of Water Resources 8 weeks Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II 197 27/12/2019 Constituency projects) Lot-20 at garkon alli in kiyawa constituency JEC/112/2019/VOL.1/11 Yarkwari global serv Nig. Ltd 3,113,973.13 Min of Education 12 weeks Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II 198 27/11/2019 Constituency projects) Lot-3B at Zamini tagir in Auyo constituency JEC/108/2019/VOL.1/11 Yarkwari global serv Nig. Ltd 3,013,570.00 Min of Education 8 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 199 23/12/2019 1 at Kafardu in auyo Constituency JEC/277/2019/VOL.1/6 Faahm Integrated Ltd 6,018,915.00 Min of Water Resources 8 weeks

Bal.C/F 6,775,542,655.93

13

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 6,775,542,655.93

Construction of hand pump boreholes water supply schemes constituency projects (2019 200 11/12/2019 first quarter) Lot-5 at Maibarewa, Sabalari, K/Fulani and Kadusawa in Dutse constituency JEC/174/2019/VOL.1/20 Farham synergy con. Ltd 2,947,896.00 Min of Water Resources 8 weeks Construction of water collection points 2019 first querter constituency projects Lot-18 at 201 14/12/2019 kadiran, fagi, karanga and karde in birniwa constituency JEC/189/2019/VOL.1/20 Dabino integ serv Ltd 5,050,128.00 Min of Water Resources 12 weeks Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-3 at kazura, rugar taho, fulanin karanga, fulanin karanga gabas, fulanin fagi, rugar saga, fulanin diginsa, Gidan Mal Dahiru, Birniwa U/yamma, rugar idi kulla, rugar haberi, mara, diginsa, fulanin batu, Umaru mai goro, fulanin mai zariya, korewa, fulanin kachallari, dargazawa, fulanin kishinde, gidan amadu, fulanin kazadama and inkibulawa 202 14/12/2019 gabas in birniwa constituency JEC/172/2019/VOL.1/20 Dabino integ serv Ltd 15,492,109.50 Min of Water Resources 12 weeks Construction of classes and admin block at GDSS Kwalam, wurno, kyarama, and sankara 203 23/12/2019 across the state (2019 last quarter MOEST capital projects) lots-9ABCD$E JEC/298/2019/VOL.1/9 Allah Abin Godiya Nig Ltd 51,991,144.67 Min of Education 12 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 204 23/12/2019 44 at alkalawa in K/hausa Constituency JEC/289/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 205 23/12/2019 43 at Kore in K/hausa Constituency JEC/288/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 206 23/12/2019 38 at gari uku in malam madori Constituency JEC/287/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 207 23/12/2019 18 at garin tudu in maigatari Constituency JEC/282/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot- 208 23/12/2019 17 at kwaduge in maigatari Constituency JEC/281/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks 209 24/12/2191 Rehabilitation of 18No. Water supply Schemes Across the state. JEC/312/2019/VOL.1/13 LIMIS Brothers & Co 9,748,615.80 Min of Water Resources 8 weeks 210 27/12/2019 Constr. Of 1No. Basic Health Clinic at Hangu Village in Gwiwa Constituency project 2019 JEC/303/2019/VOL.1/7 Manhaf Global Constr Nig Ltd 19,663,090.37 Min of Health 16 Weeks Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 51 211 17/12/2019 at Dankama, Karkanai, Burji Fulani and Kuda in Yankwashi Constituency. JEC/237/2019/VOL.1/25 Granitoids Engr Services ltd 7,836,430.04 Cabinet office 8 weeks Constr, of 2No. Block of 2 Classroom islamiyya (2018 Phase iii on Going Constituency Projects) Lot-2 at Dadda Gari, Madoji Gari, Jeke Gari and Sarkin Gandu in Sule Tankarkar 212 18/11/2019 Constituency. JEC/95/2019/VOL.1/6 Danfatu & sons Nig Ltd 12,454,716.33 Min of Education 12 weeks Renovation of WindstormDamaged Structures at Government Science Technical college Karkarna, Science Secondary School Kafin Hausa and Girls Science Secondary School Jahun 213 24/12/2019 Across the state (2019 MOEST Capital Projects). JEC/313/2019/VOL.I/7 Allah Abin Dogaro Nig Ltd 35,803,002.26 Min of Education 8 weeks

Constr, of 2No. Block of 2 Classroom islamiyya Each (2018 first Quarter Phase II Constituency 214 11/12/2019 Projects) Lot-21 at Ung. Kalgo, Kuda walawa and Bade fulani yankwashi Constituency. JEC/133B /2019/VOL.I/7 Granitoids Engr Services ltd 9,339,771.12 Min of Education 12 weeks Constr of Soler Power supply Scheme Constituecy project (2019 Phase I) Lot-32 at 215 11/12/2019 Ganbabituwa in Kirikasamma Constituency. JEC/156/2019/VOL.I/9 Dabino integ serv Ltd 6,017,235.00 Min of Water Resources 8 weeks Constr of 1No. Friday Prayer Mosque (2019 First Quarter Constituency Projects) Lot-67 at 216 17/12/2019 Tsakuran in Fagam Constituency JEC/248/2019/VOL.I/25 Isa Halilu Nig. Ltd 9,315,820.89 Cabinet office 8 weeks Bal.C/F 6,991,287,215.91

14

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 6,991,287,215.91 Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-13 at Sawon Yamma, Gishingawa 2no., Rigar kaiwari, Iyo, Tage, Garin Wakili Gilakochini, Barmaguwa 2no. Fandun Fulani, Gayin Gane, Lofanga, Daladige, Babba Kamaji 218 11/12/2019 and Marawaji in Kirikasamma Constituency. JEC/180/2019/VOL.I/20 Dabino Integ Serv. Ltd 11,792,080.00 Min of Water Resources 12 weeks Construction of solar power water supply scheme constituncy project (2019 phase I) Lot-32 219 11/12/2019 at Ganbabituwa in kirikasamma constituency. JEC/156/2019/VOL.I/9 Dabino Integ Serv. Ltd 6,017,235.00 Min of Water Resources 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 5 220 17/12/2019 atYakuda, zazzaugawa and kwalele in Birnin kudu Constituency. JEC/200/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,881,568.50 Cabinet office 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 4 221 17/12/2019 at Kauyen Abuja, Lemo and Gidan Bello in Birnin kudu Constituency. JEC/199/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,883,340.05 Cabinet office 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 3 222 17/12/2019 at Fa'a, Chagu and Gudalai in Birnin kudu Constituency. JEC/198/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,879,148.00 Cabinet office 8 weeks

Construction of hand pump boreholes water supply schemes constituency projects (2019 223 11/12/2019 first quarter) Lot-15 at Sabon Sara, Jigalari, Lumu and Gidan Maza in Miga constituency JEC/182/2019/VOL.I/20 A. Barde Global Concopt Ltd 2,948,820.00 Min of Water Resources 8 weeks Construction of 2No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 50 224 17/12/2019 at Dkakawar Dinya and Kangal in Taura Constituency. JEC/236/2019/VOL.I/25 Dankwara M/jimina Inv. Nig. Ltd 3,916,502.10 Cabinet office 8 weeks Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 225 17/12/2019 63 at Dirimowa in Birniwa Constituency. JEC/244/2019/VOL.I/25 AMM Manzo Nig Ltd 10,518,579.33 Cabinet office 12 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 42 226 17/12/2019 at magamar uku miga, kikatawa miga and rugar rama in miga Constituency. JEC/229/2019/VOL.I/25 Amia Integrated Service Nig Ltd 5,880,512.85 Cabinet office 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 41 227 17/12/2019 at zangon jigawa gabas, garin gami and gidan kanya in miga Constituency. JEC/228/2019/VOL.I/25 Amia Integrated Service Nig Ltd 5,880,512.55 Cabinet office 8 weeks Costraction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 7 at 228 17/12/2019 arobade, mungolo and kwanar kangire in Birnin Kudu Constituency. JEC/202/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,874,753.15 Cabinet office 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 6 229 17/12/2019 at saboru, unguwar yamma and karfawa in Birnin Kudu Constituency. JEC/201/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,874,753.15 Cabinet office 8 weeKs Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 38 230 17/12/2019 at Garin Malam Ali in Malammadori Constituency. JEC/225/2019/VOL.I/25 Ramadan Constr Nig Ltd 1,961,522.85 Cabinet office 8 weeks

Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 17 at Kaho, K/Malam Yahya Basirka and Sabalari in Fagam Constituency, Gwaram Local 231 17/12/2019 Government Area. JEC/210/2019/VOL.I/25 Ramadan Constr Nig Ltd 5,877,322.53 Cabinet office 8 weeks

Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency 232 11/12/2019 Projects) Lot-18 at Aduwa in Kafin Hausa Constituency. JEC/130/2019/VOL.I/7 Mai Mai Blocks Ind. Nig. Ltd 3,111,654.55 Min of Education 9 weeks

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-2 at Kaute , Waje, Gurfai, Gangara, Kurta Fulani G. M/Jadi and Indurkuba Fulani 233 11/12/2019 Arewa in Babura Constituency JEC/171/2019/VOL.I/20 Mufabamex Concept Ltd 3,687,075.00 Min of Water Resources 12 weeks

Bal.C/F 7,082,272,595.52

15

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 7,082,272,595.52 Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency 234 17/12/2019 projects) Lot-53 at Sabon Layi K/kudu Iggi in B/kudu Constituency. JEC/239/2019/VOL.I/25 Modang Invest. Ltd. 1,954,613.85 Cabinet Office 8 weeks Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency 235 17/12/2019 projects) Lot-92 at Turkushawa in Sule Tankarkar Constituency. JEC/268/2019/VOL.I/25 Modang Invest. Ltd. 2,625,238.18 Cabinet Office 8 weeks Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 236 17/12/2019 68 at Malam Baki in Gagarawa Constituency. JEC/249/2019/VOL.I/25 AMM Manzo Nig Ltd 10,518,579.38 Cabinet office 12 weeks Completion/Renovation of 2No. Daily prayer Mosques (2019 first Quarter Constituncy projects) Lot-54 at Takur site Layin Yan Kosai and Masajid Matawalle Old Government House 237 17/12/2019 Dutse in Dutse Constituecy. JEC/240/2019/VOL.I/25 Modang Investment Limited 5,143,163.38 Cabinet office 8 weeks Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 238 17/12/2019 69 at Mai-Aduwa in Gagarawa Constituency. JEC/250/2019/VOL.I/25 Modang Investment Limited 10,518,579.38 Cabinet office 8 weeks Contr. of Wall Fence (2019 first quarter Constituecy projects) Lot- 81 at Dagacheri Juma'at 239 17/12/2019 Prayer Mosque in Birniwa Constituecy. JEC/259/2019/VOL.I/25 AMM Manzo Nig Ltd 3,429,961.13 Cabinet office 8 weeks Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 18 240 17/12/2019 at Zango in Gumel Constituency. JEC/211/2019/VOL.I/25 farham synergy con. Ltd 1,958,251.05 Cabinet office 4 weeks

Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 36 241 17/12/2019 at Fake Cikin Gari, Shuwarin Gari and Miyawo Tudu in Kiyawa Constituency. JEC/223/2019/VOL.I/25 Muhal Global Concept Ltd 5,880,518.55 Cabinet office 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 37 242 17/12/2019 at Majiya, Danfusan and Kiyawa cikin Gari in Kiyawa Constituency. JEC/224/2019/VOL.I/25 Muhal Global Concept Ltd 5,880,518.55 Cabinet office 8 weeks

Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency 243 27/12/2019 Projects) Lot-5 at Hayatul Islam and Kabal in Jahun Constituency. JEC/109/2019/VOL.I/11 Sasco Multi Serv Nig Ltd 6,218,498.70 Cabinet office 9 weeks

Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 19 244 17/12/2019 at Jugwa A, Z/Nagogo G/sarkin aska, Z/Ta Gabas and Girawa in Gwaram Constituency. JEC/212/2019/VOL.I/25 JAG & H Intergreted Service 7,846,091.40 Cabinet office 8 weeks

Completion/Renovation of 1No.Friday prayer Mosques (2019 first Quarter Constituncy 245 17/12/2019 projects) Lot-89 at Tashar Dankwmbo in Kanya Constituency in Babura LGA JEC/264/2019/VOL.I/25 Deetech Nig. Ltd 2,131,685.87 Cabinet office 8 weeks

Min of Works 246 15/12/2019 Electrification projects at tashena village and shagaryo town in malam madori LGA. JEC/84/2019/VOL.I/8 A.H.F. Global Nig Ltd 49,293,924.94 16 weeks

Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at Cabinet office 247 17/12/2019 Ladin kani in mai gatari Constituency. JEC/253/2019/VOL.I/25 Khairushabah Nig Ltd 7,609,184.60 8 Weeks

Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 78 at Cabinet office 248 17/12/2019 Jobi in maigatari Constituency. JEC/256/2019/VOL.I/25 Marb Eng. & Multi serv. Ltd 7,720,042.25 8 Weeks

Bal.C/F 7,211,001,446.73

16

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 7,211,001,446.73 Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 45 249 17/12/2019 at Debe kai, Tinti and Daneji Ringim Constituency. JEC/231/2019/VOL.I/25 Marb eng. & Multi Service Ltd 5,884,568.55 Cabinet office 8 weeks

Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 35 250 17/12/2019 at Kulluru, Harbon Mai Unguwa, katuka cikin Gari and Abarewa in Kiyawa Constituency. JEC/222/2019/VOL.I/25 Muhal Global Concept Ltd 7,834,461.60 Cabinet office 8 weeks Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 31 251 11/12/2019 at Daneri, Kanoke and Kota in Kaugama Constituency. JEC/221/2019/VOL.I/25 Danfatu & sons Nig Ltd 5,884,568.55 Cabinet office 8 weeks

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-6 at Kwalam Fulani, Maidu Tsokai, Makwai Fulani, Gidan Haruna Dan Daga, Sarkin Dare Kofar Shafi'I, Sarkin Dare Fulani, M. Na'annabi Fulani, Garin Dutse Fulani Tale, 252 11/12/2019 Wadi Fulani and Gidan Alasan Nadidi in Gagarawa Constituency JEC/175/2019/VOL.I/21 JAG&H integrated services ltd 7,379,940.00 Min of Water Resources 8 weeks Constr.of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-29 at 253 11/12/2019 Wadda in Gagarawa Constituency JEC/155/2019/VOL.I/9 Farham Synergy con. Ltd 6,022,800.00 Min of Water Resources 8 weeks Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-15 254 11/12/2019 At Dawar Gada in Maigatari Constituency JEC/146/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 Min of Water Resources 8 weeks Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-14 255 11/12/2019 At Zuba Barkono in Guri Constituency JEC/145/2019/VOL.I/9 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks Constr.of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-12 256 11/12/2019 At Madamuwa in Guri Constituency JEC/143/2019/VOL.I/9 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 257 17/12/2019 76 at Dankumbo in Maigatari Constituency. JEC/254/2019/VOL.I/25 Allah Abin Dogaro Nig Ltd 14,500,005.00 Cabinet office 12 Weeks

258 12/12/2019 Mainatinance and Rehabilitation of some Failed Sections along Kazaure - Roni Road JEC/197/2019/VOL.I/8 Retercha Cmp. Nig Ltd 98,528,040.30 Min of Works 16 weeks Constr. Of JSS Science each (2019 first quarter phase II constituency projects) LOT-17 at 259 11/12/2019 Gumel and Garin Barka in Gumel constituency. JEC/129/2019/VOL.I/7 Farham Synergy con. Ltd 29,908,200.00 Cabinet office 18 Weeks Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-44 at 260 17/12/2019 Kwai Kwayu, Kagadama and Gagarawa in Ringim constituency. JEC/230/2019/VOL.I/25 Marb eng. & Multi Service Ltd 5,884,568.55 Cabinet office 8 Weeks Constr of Wall fence at Jigawa College of Remedial and Advance Studies (JICORAS) Babura, 261 27/11/2019 Lot-2 (3rd & 4th Qtr. 2019 Capital Projects) JEC/113B/2019/VOL.I/10 Ngaloma Constr. Co. Ltd. 131,969,392.51 Min of Education 24 weeks Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-11 at 262 11/12/2019 Unguwar Gabas in Guri Constituency. JEC/142/2019/VOL.I/10 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-5 263 11/12/2019 atGeneral Hospital in Birniwa Constituency. JEC/138/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 Min of Water Resources 8 weeks Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-6 at 264 11/12/2019 Kazura in Birniwa Constituency. JEC/139/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 Min of Water Resources 8 weeks

Bal.C/F 7,560,889,431.79

17

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD BAL. B/F 7,560,889,431.79 Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-13 at 265 11/12/2019 Bodala in Guri Constituency. JEC/144/2019/VOL.I/9 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks Constr of 1no. Friday prayer mosques (2019 first quarter constituency projects) Lot-77 at Lallashi in Cabinet office 266 17/12/2019 Maigatari Constituency. JEC/255/2019/VOL.I/25 Marb Eng & Multi Serv. Ltd. 7,833,599.56 8 Weeks Conversion of Motorized Water Supply Scheme to Solar Powered and Rehabilitation of 267 6/12/2019 Existing Solar Schemes at College of Education Gumel JEC/122/2019/VOL.I/6 SIMS Global Resources 29,243,441.00 Min of Water Resources 8 weeks Constr of Admin Block at Jigawa College of Remedial and Advance Studies (JICORAS) 268 27/11/2019 Babura, Lot-1 (3rd & 4th Qtr. 2019 Capital Projects) JEC/113A/2019/VOL.I/10 Ngaloma Constr. Co. Ltd. 83,365,963.69 Min of Education 24 weeks

Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at Cabinet office 269 7/12/2019 Ladin Kani in Maigatari Constituency. JEC/253/2019/VOL.I/26 Nadada Venture Nig. Ltd 7,609,184.60 8 Weeks

Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 78 at Cabinet office 270 17/12/2019 Jobi in Maigatari Constituency. JEC/256/2019/VOL.I/26 Nadada Venture Nig. Ltd 7,720,042.25 8 Weeks

Constr. Of Gate House and Toilet at Jigawa Colege od Remedial and advance Studies Min. of Education 271 27/11/2019 (JICORAS) Babura, Lot- 3 (3rd and 4th Quarter 2019 Capital Project) JEC/114/2019/VOL.I/10 Al-sabur Global Nig. Ltd 39,190,677.39 24 Weeks

Costr.of 2No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 88 at Cabinet office 272 17/12/2019 Duzau and Danyayi in Kanya Constituency. JEC/265/2019/VOL.I/25 Deetech Nig. Ltd 7,029,877.90 8 Weeks

Constr. Of 4no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-29 at Cabinet office 273 17/12/2019 Karfawa, Kanawa, Adigul and Balladar Kanya constituency in Babura LGA. JEC/219/2019/VOL.I/25 Deetech Nig. Ltd 7,824,104.04 8 Weeks

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-16 Cabinet office 274 11/12/2019 At Dangwabro in Maigatari Constituency JEC/147/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 8 Weeks

Constr. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-39 at Cabinet office 275 17/12/2019 Kkama and Kwanar Duniya in Maigatari constituency JEC/226/2019/VOL.I/25 Marb eng. & Multi service Nig Ltd 3,908,555.70 8 Weeks

Constr. Of 1No. Block of 2-Laboratories at GGDSS Roni (2nd Quarter 2019 Constituency min. of education 276 24/12/2019 Project) Lot-1 JEC/295/2019/VOL.I/8 Manhaf Global Constr Nig Ltd 33,552,607.41 12 weeks

Construction of additional block of 3 classrooms each at kondiko, GGASS Binin kudu, GDSS min. of education 277 24/12/2019 kwarko, GDSS kiyako, GDSS sabon gari takanebu and GDSS galamawa across the state JEC/294/2019/VOL.I/7 Babandoki Gen. Enterp Nig Ltd 67,198,406.92 12 weeks

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-47 Min. of Water Resouces 278 11/12/2019 At maruta in gwaram Constituency JEC/166/2019/VOL.I/9 farham synergy con. Ltd 6,022,800.00 8 Weeks

Constr. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-46 at Cabinet office 279 17/12/2019 ruwan garai and dansure tasha in roni constituency JEC/232/2019/VOL.I/25 Na'ayi Resources Nig Ltd 3,919,811.70 8 Weeks

Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-12 at Cabinet office 280 17/12/2019 gabari, machiba and shagawa in bulangu constituency JEC/206/2019/VOL.I/25 Kawu Nigeria Ltd 5,567,369.55 8 Weeks

Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 80 at Cabinet office 281 17/12/2019 Kaki mai wando in Roni Constituency. JEC/258/2019/VOL.I/25 Na'ayi Resources Nig Ltd 9,527,340.25 8 Weeks

Bal.C/F 7,892,433,693.75 18

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 7,892,433,693.75

Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-14 at Cabinet office 282 17/12/2019 kwarin bulama, S/garin bulangu, mandamari sabuwa in bulangu constituency JEC/208/2019/VOL.I/25 Kawu Nigeria Ltd 5,842,273.05 8 Weeks

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-25 Min. of Water Resouces 283 11/12/2019 At Fagoji in Dutse Constituency JEC/151/2019/VOL.I/9 JAG & H Interg. Service 6,021,015.00 8 Weeks

Constr. Of watar collection point 2019 first quarter constituency project Lot 20 at zazzana, Min of Water resource 284 11/12/2019 mida, and lafiya in gwaram constutuency JEC/191/2019/VOL.I/20 farham synergy con. Ltd 3,758,997.00 8 weeks

Renov. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-84 at Cabinet office 285 17/12/2019 buro and fadi gurje in fagam constituency JEC/262/2019/VOL.I/25 Pullad Global Consultant Ltd 2,503,688.50 8 Weeks

Constr, of 2No. Block of 2 Classroom islamiyya Each (2019 first Quarter Constituency Min. of Education 286 27/11/2019 Projects) Lot-14c at harazimiyya islamiyya in hadejia Constituency. JEC/107/2019/VOL.I/11 Alh. Umaru Babandoki Nig Ltd 8,055,821.00 8 weeks

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-26 Min of Water resource 287 11/12/2019 At Kulasa in Dutse Constituency JEC/152/2019/VOL.I/9 JAG & H Interg. Service 6,021,015.00 8 Weeks

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-27 Min of Water resource 288 11/12/2019 At Kwaimawa in Dutse Constituency JEC/153/2019/VOL.I/9 JAG & H Intergreted Service 6,021,015.00 8 Weeks

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-28 Min of Water resource 289 11/12/2019 At Tabobo in Dutse Constituency JEC/154/2019/VOL.I/9 JAG & H Intergreted Service 6,021,015.00 8 Weeks

Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-11 at Cabinet office 290 17/12/2019 turaka, gandu and K/bulama Waek in bulangu constituency JEC/205/2019/VOL.I/25 Kawu Nigeria Ltd 5,865,605.55 8 Weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First

Quarter) Lot-29 at gangawa, sabara, ruwan dawa, kulleran, ganwa fulani, fanisau, tazara Min. of Water Resouces sabon gida, tula, majiga, harbo, dina, kamai gitsira, dogawa gabashi, bayan kotun cikin gari, 291 11/12/2019 gundin sabon gida and yamma in jahun Constituency JEC/187/2019/VOL.I/20 Sasco Multi Serv Nig Ltd 11,791,752.00 14 Weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-12 at sabuwar jawo (sabaru ward), fulanin ballami (dandi ward), K/Mal. Ali Min. of Water Resouces 292 11/11/2019 headmaster (gada ward), K/alta makeri (gada ward) and makabarta gabas (gada ward) in JEC/179/2019/VOL.I/20 Yanduna Venture Nig Ltd 3,686,287.50 8 Weeks

Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Constituency Min. of Education 293 27/12/2019 Projects) Lot-5 at hayatul islam and kabal in Jahun Constituency. JEC/109/2019/VOL.I/11 Sasco Multi Serv Nig Ltd 6,218,492.70 8 weeks

Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Min. of Education 294 11/12/2019 Projects) Lot-2 at rukumi in malam madori Constituency. JEC/134/2019/VOL.I/7 Mai Mai Blocks Ind. Nig. Ltd 3,473,316.00 8 weeks

Constr. Of 1No. Block of science Laboratory at GDSS Dan sure in roni LGA (2019 MOEST Min. of Education 295 6/12/2019 capital Project) Lot-1 JEC/123/2019/VOL.I/6 Na'ayi Resources Nig Ltd 9,561,049.80 8 weeks

Completion /Renovation of 2no. Friday prayer mosques (2019 first qtrs. Constituency Cabinet Office 296 17/12/2020 projects) Lot-84 at Buro and Fadi Gurje in Fagam Constituency. JEC/262/2019/VOL.I/25 Pullad Global Consultant 2,503,688.50 8 weeks

Completion /Renovation of 2no. Friday prayer mosques (2019 first qtrs. Constituency Cabinet Office 297 17/12/2020 projects) Lot-83 at JIBWIS Fagam and Dangulan in Fagam Constituency. JEC/261/2019/VOL.I/25 Pullad Global Consultant 4,668,587.70 8 weeks

Bal.C/F 7,984,447,313.05 19

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD BAL. B/F 7,984,447,313.05

Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 74 at gwalerima in Cabinet office 298 17/12/2019 kaugama Constituency. JEC/251/2019/VOL.I/25 Danfatu & sons Nig Ltd 8,200,007.27 12 weeks

Completion./Renovation Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT- Cabinet office 299 17/12/2019 56 at magarya, sabuwar unguwa and GGSS Garki in Garki constituency JEC/242/2019/VOL.I/25 MMZ Garki Gen contractor 4,814,329.08 8 Weeks Completion./Renovation Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT- Cabinet office 300 17/12/2019 52 at argina and yartsaka in auyo constituency JEC/238/2019/VOL.I/25 MMZ Garki Gen contractor 7,293,833.85 8 Weeks Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 74 at Ubba in Cabinet office 301 17/12/2019 kaugama Constituency. JEC/252/2019/VOL.I/25 Danfatu & sons Nig Ltd 8,200,007.27 12 weeks Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-13 at bujaye, Cabinet office 302 17/12/2019 makera mashawai in bulangu constituency JEC/207/2019/VOL.I/25 Kawu Nigeria Ltd 5,784,568.58 8 Weeks Constr. Administrative block at jigawa college of remedial and advance studies (JICORAS) Babura, Lot-1 Min. of Education 303 27/12/2019 (3rd & 4th quarter 2019 capital projects) JEC/113A/2019/VOL.I/10 Ngaloma Constr Nig Ltd 83,365,963.69 24 Weeks Constr. Of 4no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-51 at dankama, Cabinet office 304 17/12/2019 karkanai, burji fulani and kuda in yankwashi constituency JEC/237/2019/VOL.I/25 Granitoids Engr Services ltd 7,836,430.04 8 Weeks Constr of 5No. Hand Pumps Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-25 at kanya abbba, dan yayin daurawa, kagadama, walawa and shantake in kanya babba Min. of Water Resouces 305 11/12/2019 Constituency JEC/196/2019/VOL.I/20 Deetech Nig. Ltd 5,100,375.00 8 weeks

Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Projects) Min. of Education 306 11/12/2019 Lot-21 at Ung. Kalgo, Kuda Walawa and Bade Fulani in Yankwashi Constituency. JEC/133/2019/VOL.I/7 Granitoids Engr Services ltd 9,339,771.12 8 weeks Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-8 at mai dashi, Idi gwamna, unguwar malam, rigar lamido, adiyani islamiyya, dagana Nato, daba, dirba, Min. of Water Resouces rigar malam wuri, yalwa tsangaya, goni garin una, askandi arinjasko, rigar wakilin dajjo lafiya, rigar 307 11/12/2019 babare, and rigar duka maza in guri Constituency JEC/176/2019/VOL.I/20 AYH Intg. Serv. Ltd 10,331,489.00 8 weeks

Ren. of Windstorm Damaged Structures at GSTC Karkarna, SSS K/Hausa and GSSS Jahun across the state Min. of Education 308 24/12/2019 (2019 MOEST Capital Projects) JEC/313/2019/VOL.I/7 Allah Abin Godiya Nig Ltd 35,803,002.26 8 weeks

Constr of 4no. Daily prayer mosques (2019 first quarter constituency projects) Lot-19 at Jugwa A., Cabinet office 309 17/12/2019 Z/nagogo G/Sarkin Aska, Z/Ta gabas and Girawa in Gwaram Constituency. JEC/212/2019/VOL.I/25 JAG&H Integ. Services Ltd 7,846,091.40 8 weeks

Constr. of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-20 at abena, Cabinet office 310 17/12/2019 babban gidan nahuce and tsangwanwa in gwaram constituency JEC/213/2019/VOL.I/25 JAG & H Intergreted Service 5,880,512.55 8 Weeks

Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr. 2019 constituency project) Min of Education 311 27/11/2020 at Babura k/Arewa and Garin Baki in Babura Constituency. JEC/102/2019/VOL.I/11 Mufabamex Concept Ltd. 6,391,877.10 7 weeks Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr. Phase II 2019 constituency Min of Education 312 11/12/2020 project) at Ung. Kalgo, Kuda Walawa and Bade Fulani in Yankwashi Constituency. JEC/133/2019/VOL.I/7 Granitoids Eng Serv. Ltd. 9,339,771.12 12 weeks Completion /Renovation of 3no. Daily prayer mosques (2019 first qtrs. Constituency projects) Lot-56 at Cabinet Office 313 17/12/2020 Magarya, Sabuwar Unguwa and GGSS Garki in Garki Constituency. JEC/242/2019/VOL.I/25 MMZ Garki Gen.Constr Ltd. 4,814,329.08 8 weeks Constr of 2no. Daily prayer mosques (2019 first qtrs. Constituency projects) Lot-46 at Ruwan Garai and Cabinet Office 314 17/12/2020 Dansure Tasha in Roni Constituency. JEC/232/2019/VOL.I/25 Na'ayi Resources Ltd. 3,919,811.70 8 weeks

Bal.C/F 8,208,709,483.16 20

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 8,208,709,483.16 GOODS

315 16/4/2019 Procurement of Assorted Submersible pumps Across the State FGPC/28/2019/VOL.I/8 Umar Aliyu & Sons Nig Ltd 19,479,796.87 Ministry of Water Res 8 Weeks Supply of Alternative Solar Power Energy and Solar Street light at Jigawa State Institute of 316 28/06/2019 Information Technology Kazaure JEC/41/2019/VOL.I/12 Ngaloma Construction 62,121,465.00 Ministry of Education 12 weeks

317 20/06/2019 Purchase of 2No. Fairly used vechicle JEC/38/2019/VOL.I/4 Modang investment Ltd 39,900,000.00 Government House 2 weeks

318 16/4/2019 Procurement of 2No. 200KVA Perkins Generating Set for Kazaure and Birnin Kudu Zone FGPC/29/2019/VOL.I/8 Limis Brothers & Co 28,619,712.07 Ministry of Water Res 8 Weeks Supply and Installation of inytegrated standalone Solar Powered Streetlight at buji (150 Units), Basirka/Digijin (120 Units), Kudai (100 Units), balanngu-Sarawa (100 Units) Garin 319 16/4/2019 Gabas (160 Units) and Biriwa Tasha (100 units) Total 710 units (Lot-1) FGPC/24/2019/VOL.I/8 Arrayan Ventures Global 403,649,600.00 Ministry of Works 14 weeks

Supply and Installation of inytegrated standalone Solar Powered Streetlight atGada (150 320 12/2/2019 units) Dandi (100 unit) Amaryawa (100 units) and Yankwashi (80 unit) total 430 units (lot-3) FGPC/4/2019/VOL.I/28 Ngaloma Construction 256,684,050.00 Min of Works & Transport 14 weeks Supply and Installation of 52No. Standalone Solar Integrated Streetlight (Phase-II) 321 3/5/2019 at the Jigawa State College of Islamic & Legal Studies Ringim JEC/48/2019/VOL.I/7 Sims Global Resources 32,215,050.00 Ministry of Education 4 weeks Supply and Distribution of Science text Books and Teachers Guide for Senior Secondary 322 11/7/2019 Schools Across the State JEC/43/2019/VOL.I/6 Learn Africa Plc 49,949,800.00 Ministry of Education 6 weeeks

323 31/7/2019 Supply & Installation of Solar streetlight at Emir's Drive, Dutse JEC/47/2019/VOL.I/7 Arrayyan Global Vent 17,319,500.00 Min of Works 8 weeks Supply & Installation of Stand alone solar powered streetlight at Government Girls Arabic Secondary School Babura, Government Girls Unity Secondary School Gwaram & Computer 324 31/7/2019 Girls Secondary School Roni. JEC/48/2019/VOL.I/8 Sims Global Res 60,780,300.00 Min of Works 12 weeks Procurement and Installation of Furniture at the Official Residence of His Excellency, the 325 19/9/2019 Deputy Governor at Dutse JEC/60/2019/VOL.I/6 Aimim Consult Nig. Ltd. 34,825,680.00 Cabinet Office 8 weeks Procurement and Sewing of 30,000 sets of School Uniforms to Senir Secondary Schools acros 326 3/9/2019 the state JEC/59/2019/VOL.I/6 313 Textile Nig Ltd. 79,980,000.00 Min of Education 12 weeks Supply and Installations of Integrated Standalone Solar Powered Streetlights at GGASS Sule 327 11/9/2019 Tankarkar, GGSSS Taura and Model Boarding Primary School, Gumel JEC/58/2019/VOL.I/8 SIMS Nigeria Limited 75,380,550.00 Min of Works & Transport 12 weeks

Supply and Installations of Integrated Standalone Solar Powered Streetlight at Hammado- Gagarawa (200 Unit) Bosuwa (100 Unit) iri (100 Units) Manga-Takwasa (120 Unit) and 328 12/2/2019 Unguwar Gawo-Batali-Kuzunzumi-Balarabe (200 unit) Total 720 Units (Lot 2) FGPC/3/2019/VOL.I/28 SIMS NIGERIA LTD 430,360,875.00 Min of Works & Transport 14 Weeks Feeding of 597 Boarding School students at MBPS/JSS Kazaure & 35 students at Intel 329 23/12/2020 Disability Kazaure in Kazaure LGA (2019 MOEST Capital Projects) Lot-40. JEC/3514/2019/VOL.I/7 Umar Aliyu & Sons 23,888,538.40 Min of Education 40 weeks

Bal.C/F 9,823,864,400.50

21

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 9,823,864,400.50 GOODS Procurment of Medical Drugs, ICT and Sicbay Equipment for Jigawa Academy for the Gifted, 330 16/10/2019 Bamaina JEC/86/2019/VOL.I/6 IMAM Ahmed Nig Ltd. 4,639,345.25 Min of Education 2 weeks

331 9/12/2019 Purchase of 15no. Vehicles JEC/125/2019/VOL.1/3 CIG motor Company Nig Ltd 169,533,611.20 Govt House 2 weeks Supply and installation of medical equipment to the 25No. Newly constructed basic health 332 11/12/2019 clinic across the state. JEC/304/2019/VOL.1/7 Dangata mem. inv. Ltd 95,423,350.00 Min of Health 8 weeks Supply and installations of 100-units integrated standalone solar powered streetlight at 333 24/12/2019 babaldu town in Birnin Kudu LGA JEC/299/2019/VOL.1/7 Ar-rayyan ventures global ltd 55,786,500.00 Min of Works 12 weeks Supply and installations of 150-units integrated standalone solar powered streetlight at 334 24/12/2019 Garun gudunya and garin gambo towns in babura and gumel LGAs JEC/300/2019/VOL.1/7 SIMS Nig. Ltd 81,328,800.00 Min of Works 12 weeks Feeding of 1,003 Boarding school students at GGSSS Taura in Taura LGA (2019 MOEST Capital 335 23/12/2019 projects) Lot-26 JEC/337/2019/VOL.I/17 Dankwara Maijimina Gen. Entp. 37,911,714.80 Min of Education 40 weeks

Procurement and installation of Furniture at the official Residence of His Excellency Deputy 336 18/12/2019 Governor Jigawa state in Dutse (2019 Capital Projects) Additional works JEC/60/2019/VOL.1/18 AIMM Consult Nig Ltd 8,750,175.00 Deputy Governor Office 4 weeks Feeding of 433 Boarding school students at GJSSS Guri in Guri LGA (2019 MOEST Capital 337 23/12/2019 projects) Lot-28 JEC/339/2019/VOL.I/17 Baradugum Gen. Entp. 16,366,540.00 Min of Education 40 weeks Supply and Installations of Integrated stadalone Solar Powered Streetlight at GGASS 338 15/10/2019 Birniwa, GGASS Kaugama, Science of Deef Hadejia and JSSS Guri JEC/85/2019/VOL.1/18 SIMS Global Resources 77,002,800.00 Min of Works 12 weeks

Supply and installation of 150-units integrated stand alone powered streetlights at marke Min of Works 339 3/12/2019 town in kaugama LGA JEC/121/2019/VOL.I/7 Sims Global Resources Nig Ltd 82,797,750.00 12 weeks

Supply of Science Laboratories Equipment for Distribution to Senior Sec School Across the Cabinet office 340 24/12/2019 state (2019 MOEST capital project) JEC/318/2019/VOL.I/9 Aldan Project Ltd 29,491,628.72 8 weeks Procurement of science laboratory equipments for distribution to 9No. Senior secondary

schols upgraded to science centre of exlence core-2 at GGUSS Malammadori, GDSS G/Gabas, Min. of Education GGSS garki, GDSS gwuiwa, GUSS aujara, GUSS maigatari, GUSS tsohuwar gwaram, GC birnin 341 24/12/2019 Kudu, and GUSS basirka accross the state JEC/293/2019/VOL.I/9 Quest Ventures Ltd 81,037,103.92 8 weeks Feeding of 970 Boarding school students at GGSS S/tankarkar in S/tankarkar LGA (2019 342 23/12/2019 MOEST Capital projects) Lot-24 JEC/335/2019/VOL.I/17 Hassan Habu T. Gen. Entp. 39,182,001.60 Min of Education 40 weeks Feeding of 790 Boarding school students at GSTC Hadejia in Hadejia LGA (2019 MOEST 343 23/12/2019 Capital projects) Lot-12 JEC/323/2019/VOL.I/17 A.H.M. Global Ventures 29,860,672.80 Min of Education 40 weeks

Bal.C/F 10,632,976,393.79

22

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 10,632,976,393.79 GOODS Feeding of 287 Boarding School students at bamaina academy in birnin kudu LGA (2019 min. of education 344 23/12/2019 MOEST Capital Projects)LOT-39 JEC/350/2019/VOL.I/17 Kabiru na Malam Nig Ltd 40,204,006.00 40 weeks Feeding of 1031 Boarding school students at GGASS Danzomo in Sule tankarkar Local 345 23/12/2019 Government Area (2019 MOEST Capital project) Lot-25 JEC/336/2019/VOL.I/17 Salisu & Isah Gen. Entp. 38,969,984.00 Min of Education 40 weeks Feeding of 1,762 Boarding school students at GUSS Maigatari in Maigatari Local Government 346 23/12/2019 Area (2019 MOEST Capital project) Lot-20 JEC/331/2019/VOL.I/17 Shabarawa Gen. Enterpr 66,600,638.40 Min of Education 40 weeks Feeding of 426 Boarding school students at Science secondary school kanya Babba in Babura 347 23/12/2019 Local Government Area (2019 MOEST Capital project) Lot-41. JEC/352/2019/VOL.I/17 H.A.U. Gen. enterp. 16,102,084.40 Min of Education 40 weeks Feeding of 635 Boarding school students at MBPS/JSS Ringim in Ringim Local Government 348 23/12/2019 Area (2019 MOEST Capital project) Lot-35 JEC/346/2019/VOL.I/17 H.A.U. Gen. enterp. 23,875,921.20 Min of Education 40 weeks Feeding of 3378 Boarding school students at GUSS Ringim in Ringim Local Government Area 349 23/12/2019 (2019 MOEST Capital project) Lot-21. JEC/332/2019/VOL.I/17 H.A.U. Gen. enterp. 127,667,604.80 Min of Education 40 weeks Feeding of 761 Boarding school students at SSS Lautai in Gumel Local Government Area 350 23/12/2019 (2019 MOEST Capital project) Lot-8. JEC/319/2019/VOL.I/17 Bakar Kasa Gen. Enter. 28,764,521.60 Min of Education 40 weeks Feeding of 1,030 Boarding school students at SAIS Hadejia Local Government Area (2019 351 23/12/2019 MOEST Capital project) Lot-13 JEC/324/2019/VOL.I/17 MS Amar & son enterp 38,932,269.60 Min of Education 40 weeks Feeding of 753 Boarding school students at GGCSS Roni in Roni Local Government Area (2019 352 23/12/2019 MOEST Capital project) Lot-23 JEC/334/2019/VOL.I/17 Talba Gen. Enterp 28,462,134.80 Min of Education 40 weeks

Feeding of 1319 Boarding school students at GUSS Roni and 170 tsangaya school students at 353 23/12/2019 Gwiwa in Roni and Gwiwa Local Government Area (2019 MOEST Capital projects) Lot-22 JEC/333/2019/VOL.I/17 Adon Sale Bandu 57,699,603.60 Min of Education 40 weeks

Feeding of 1572 Boarding school students at GUSS Fantai and 279 students at school for deaf 354 23/12/2019 in hadejia Local Government Area (2019 MOEST Capital project) Lot-11 JEC/322/2019/VOL.I/17 Alh. Muhammad Kwalli Gen. 69,924,690.40 Min of Education 40 weeks Feeding of 1703 Boarding school students at GUSS Malammadori in Malammadori Local 355 23/12/2019 Government Area (2019 MOEST Capital project) Lot-37 JEC/348/2019/VOL.I/17 AG Isyaku Gen Ent 64,366,351.60 Min of Education 40 weeks Feeding of 445 Boarding school students at GSTC Karkarna in Yankwashi Local Government 356 23/12/2019 Area (2019 MOEST Capital project) Lot-27 JEC/338/2019/VOL.I/17 Malabai Gen Ent 16,820,252.40 Min of Education 40 weeks Feeding of 580 Boarding school students at GJSSS Karkarna in Yankwashi Local Government 357 23/12/2019 Area (2019 MOEST Capital project) Lot-29 JEC/340/2019/VOL.I/17 Malabai Gen Ent 21,923,025.60 Min of Education 40 weeks

Feeding of 635 Boarding school students at MBP/JSS Gumel and 60 Tsangaya school students 358 23/12/2019 at Mai Aduwa in Gumel Local Government Area (2019 MOEST Capital project) Lot-32 JEC/343/2019/VOL.I/17 Wangara Agent Gen Ent. 26,406,169.60 Min of Education 40 weeks

Bal.C/F 11,299,695,651.79

23

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 11,299,695,651.79 GOODS Feeding of 453 Boarding school students at GSTC Ringim in Ringim Local Government Area 359 23/12/2019 (2019 MOEST Capital project) Lot-36 JEC/347/2019/VOL.I/17 Maidala Gen. Ent. 17,122,640.00 Min of Education 40 weeks Feeding of 2,254 Boarding school students at GGUSS Gwaram in Gwaram Local Government 360 23/12/2019 Area (2019 MOEST Capital project) Lot-9 JEC/320/2019/VOL.I/17 Gobirawa kwari Gen. Ent. 84,333,796.80 Min of Education 40 weeks Feeding of 1231 Boarding school students at GGASS birniwa in birniwa Local Government 361 23/12/2019 Area (2019 MOEST Capital project) Lot-4 JEC/308/2019/VOL.I/17 A.I. Maiso Gen. Ent. 46,529,720.00 Min of Education 40 weeks Feeding of 728 Boarding school students at GGJSSS Miga in Miga Local Government Area 362 23/12/2019 (2019 MOEST Capital project) Lot-31 JEC/342/2019/VOL.I/17 Yusif Garba Miga Gen. Ent. 27,511,020.00 Min of Education 40 weeks Feeding of 1,380 Boarding School students at GUSS Malam Madori LG (MOEST Capital 363 23/12/2019 Projects)LOT-19 JEC/330/2019/VOL.I/17 SawIra gen enterprises 52,161,681.60 Min of Education 40 weeks

Feeding of 1,122 Boarding School students at GSS Aujara in Jahun LG (MOEST Capital Adamu Ibrahim Aujara Gen. 364 23/12/2019 Projects)LOT-15 JEC/326/2019/VOL.I/17 Entp. 42,687,419.20 Min of Education 40 weeks

Feeding of 621 Boarding School students at SAIS Fatara in Dutse LG (MOEST Capital 365 23/12/2019 Projects)LOT-6 JEC/310/2019/VOL.I/17 Baita Daushanga Gen. Entp. 23,394,510.80 Min of Education 40 weeks

Feeding of 1,233 Boarding School students at MBPS/JSS KILA Gwaram LG (MOEST Capital 366 23/12/2019 Projects)LOT-42 JEC/353/2019/VOL.I/17 Baita Daushanga Gen. Entp. 46,605,328.40 Min of Education 40 weeks

Feeding of 882 Boarding School students at GUSS Basirka Gwaram LG (MOEST Capital 367 23/12/2019 Projects)LOT-10 JEC/321/2019/VOL.I/17 Baita Daushanga Gen. Entp. 33,333,159.20 Min of Education 40 weeks Feeding of 554 Boarding School students at MBP/JSS Guri, 58 Tsangaya School students at Tarabu and 60 Tsangaya School students at Birniwa in Guri and Birniwa LG (2019 MOEST 368 23/12/2019 Capital Projects)LOT-34 JEC/345/2019/VOL.I/17 GMA Kadira Gen. Entep 25,893,694.00 Min of Education 40 weeks Feeding of 940 Boarding School students at science secondary school (SSS) Kafin Hausa in 369 23/12/2019 Kafin Hausa LG (MOEST Capital Projects)LOT-16 JEC/327/2019/VOL.I/17 Zango Gen. Entp. 35,530,420.80 Min of Education 40 weeks

Feeding of 467 Boarding School students at GSTC Birnin kudu in Birnin kudu LG (MOEST 370 23/12/2019 Capital Projects)LOT-3 JEC/307/2019/VOL.I/17 Baita Daushanga Gen. Entp. 17,651,815.60 Min of Education 40 weeks

Feeding of 1,077 Boarding School students at GGASS Kaugama in Kaugama LG (MOEST 371 23/12/2019 Capital Projects)LOT-17 JEC/328/2019/VOL.I/17 Danbiri Global Ventures 40,709,000.80 Min of Education 40 weeks

Bal.C/F 11,793,159,858.99

24

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 11,793,159,858.99 GOODS

Feeding of 639 Boarding School students at MBPS/JSS Bulangu in Kafin Hausa LG (MOEST Hussaini Ahmed bookshop Gen 373 23/12/2019 Capital Projects)LOT-33 JEC/344/2019/VOL.I/17 Entp. 24,027,126.40 Min of Education 40 weeks

Feeding of 920 Boarding School students at GGUSS Kazaure in Kazure LG (MOEST Capital 374 23/12/2019 Projects)LOT-18 JEC/329/2019/VOL.I/17 Haru jika Gen. Entp. 34,767,096.00 Min of Education 40 weeks

Feeding of 2309 Boarding School students at GGSS Garki in Garki LGA (MOEST Capital 375 23/12/2019 Projects)LOT-7 JEC/311/2019/VOL.I/17 MMZ Garki Gen Const 87,276,300.00 Min of Education 40 weeks

Feeding of 674 Boarding School students at MBPS/JSS Kudai in Dutse LGA (MOEST Capital 376 23/12/2019 Projects)LOT-43 JEC/354/2019/VOL.I/17 Sabuwar Kuka Gen Enterp 25,476,067.60 Min of Education 40 weeks

Feeding of 788 Boarding School students at GJSSS Aujara in Jahun LGA (2019 MOEST Capital 377 23/12/2019 Projects)LOT-30 JEC/341/2019/VOL.I/17 Na'ima and Fati Gen. Entp. 29,785,076.00 Min of Education 40 weeks

Feeding of 209 Boarding school students at Tsangaya school gantsa in bujiLocal Government Min. of Education 378 23/12/2019 Area (2019 MOEST Capital project) Lot-38 JEC/349/2019/VOL.I/17 Zai General Ent. 8,762,692.80 40 weeks

Feeding of 2,416 Boarding school students at GUCSS Dutse in Dutse Local Government Area Min. of Education 379 23/12/2019 (2019 MOEST Capital project) Lot-35 JEC/309/2019/VOL.I/17 Zai General Ent. 91,320,405.20 40 weeks

Feeding of 1,696 Boarding school students at GUC Birnin kudu in birnin kudu Local Min. of Education 380 23/12/2019 Government Area (2019 MOEST Capital project) Lot-2 JEC/306/2019/VOL.I/17 Muduka General Ent. 64,105,950.80 40 weeks

Feeding of 1,407 Boarding School students at GGASS Babura in Babura LGA (2019 MOEST Min of Education 381 23/12/2020 Capital Projects) Lot-1. JEC/305/2019/VOL.I/7 JALGO Integ. Services Ltd. 53,186,214.40 40 weeks

Bal.C/F 12,211,866,788.19

25

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD

BAL. B/F 12,211,866,788.19 SERVICES

Commissioning as consultant for the Supervision of the Construction of Kiyawa Township 382 20/3/2019 Roads Phase II (4km) FGPC/140/2012/VOL.I/111 Sadiq Engineering 13,679,571.15 Min of Works 6 months

Commissioning as consultant for the Supervision of the Construction of Chai Chai Tsohuwa 383 20/3/2019 township Roads FGPC/20/2019/VOL.I/4 UGS Consultants 3,949,973.17 Min of Works 6 weeks

Commissioning as Consultant for the Supervision of the construction of Kanya Babba 384 20/3/2019 Township Roads (2.8km) FGPC/59/2017/VOL.I/60 Curves & Straight design 6,056,229.07 Min of Works 6 months

Commissioning as Consultant for the Supervision of the Construction of Kazaure-Fanda- 385 20/3/2019 Sabaru-Gallu-Karkarna Feeder Road (16km) FGPC/138/2012/VOL.I/228 UKM Civil Engineering 9,226,965.83 Min of Works 6 months

Commissioning as Consultant for the Supervision of the Construction of Hammado- 386 20/3/2019 Dafarantama-Mele-Baikarya-Garin Baki-Kokinami-Liman Mado feeder Roads (32.76km) FGPC/22/2011/VOL.I/179 Hag Engineering 15,959,738.87 Min of Works 6 months

Commissioning as consultant for the supervision of the Construction of Zandam Nagogo 387 20/3/2019 township Roads (2.38km) FGPC/6/2012/VOL.I/III Land Base Engineering 7,629,535.56 Min of Works 6 months

Commissioning as Consultant for the supervision of the Construction of Kaugama - Malam 388 20/3/2019 Madori Feeder Road (19.31km) FGPC/411/2018/VOL.I/21 SIIS Engineering Consult 9,112,024.27 Min of Works 6 months

Commissioning as consultant for the Supervision of the Construction of Guduncin-Aguyaka 389 20/3/2019 Road (4.30km) FGPC/59/2017/VOL.I/56 Curves & Straight design 17,024,414.69 Min of Works 10 months

Commissioning as Consultant for the Supervision of the Construction of Kwanar Medi- 390 20/3/2019 Danzomo-Garki Road (29.51km) FGPC/59/2017/VOL.I/54 Curves & Straight design 62,714,754.77 Min of Works 20 months Commissioning as consultant for the Supervision of the Supply and Installation of Intergrated Standalone Solar Powered Streetlights at Buji 150 units, Basirka/Digijin 120 391 26/3/2019 Units, Kudai 100 Units, Bulangu-Sarawa 100 units, garin Gabbas 160 units and birniwa Tasha FGPC/21/2019/VOL.I/10 ARDUGAL Engineering Ltd 7,606,368.00 Min of Works 4 months Commissioning as Consultant for the Supervision of the Supply and Installation of Integrated Standalone Solar Powered Streetlights at Hammado-Maituruniya-Duhuwa- Gangar 200 Units, Bosuwa 100 units, Kiri 100 units, Manga-Takwasa 12 units and unguwar 392 26/3/2019 Gawo-Bataki-Kuzunzumi-Balarabe 200 units (Total 720 units) FGPC/22/2019/VOL.I/10 Secwave Nigeria Limited 7,531,315.31 Min of Works 4 months

Commissioning as consultant for the supervision of the construction of sada-Kanawa- 393 10/4/2019 Dankari-Nasarawa-Kuda Feeder Road (11.2km) FGPC/138/2012/VOL.I/248 UKM Engineering Consult 6,889,699.73 Ministry of Works 6 Months

BAL. C/F 12,379,247,378.61

26

S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRY COMP. PERIOD

BAL. B/F 12,379,247,378.61 Commissioning as Consultant for the Training and Technical Support of 250No Senior Secondary School Teachers on K-Yan Machine for the Facilitation of E-Learning at Senior 394 24/5/2019 Secondary Schools Across the State FGPC/32/2019/VOL.I/8 C-Stemp Construction Skills 36,227,761.00 Ministry of Education 6 Month Commissioning as Consultant for the Supervision of the Construction of Birnin Kudu-Zazia- KwanGwara-Nafadan Warji-Nafadan Kanawa-Marmara-Kadangare-Hirin-Kwatai Nafara 395 20/3/2019 Feeder Road (33 Km) FGPC/29/2011/VOL.I/77 Himma Tech Service & Co 19,415,172.13 Min of Works 10 months

Commissioning as Consultant for the Supervision of the Construction of Gumel Township 396 20/3/2019 Roads (Phase III) 4.7Km FGPC/29/2011/VOL.I/75 Himma Tech Service & Co 17,440,289.13 Min of Works 6 months

Commissioning as Consultant for the Supervision of the Re-Construction of Taura-Garki 397 20/3/2019 Road (26.68Km) FGPC/29/2011/VOL.I/73 Himma Tech Service & Co 51,197,948.77 Min of Works 16 months

Commisiioning as Consultant for the Supervision of the Construction of Miga Township 398 20/3/2019 Roads (Phase II) 3.1Km) FGPC/223/2018/VOL.I/32 Apex Design & Associate 13,091,926.38 Min of Works 6 months

Commissioning as Consultant for the Supervision of the Construction of Balago-Kadowawa- 399 20/3/2019 Dumadumin Ky-Dumadumin Toka-Auno Road (41.2km) FGPC/223/2018/VOL.I/30 Apex Design & Associate 93,126,261.93 Min of Works 24 months

Commissioning as Consultant for the Supervision of the Construction of Jigawar Dan Ali Akram Engineering & 400 20/3/2019 Township Roads (2.1km) FGPC/97/2013/VOL.I/36 Management 7,484,294.27 Min of Works 6 monthd

Commissioning as Consultant for the Supervision of the Construction of Access Roads to 401 20/3/2019 744, Sabuwar Takur and Yalwawa township roads (8.1km) FGPC/59/2017/VOL.I/58 Curves & Straight design 27,603,997.03 Min of Works 10 months Engagement/Commissioning as Consultant for the reconciliation and recovery of unremitted pay as you earn (PAYE) of Staff of Federal Government Agencies Residing in 402 26/6/2019 Jigawa State for the period off 2002-2018(8% of N 6,383,001,715.57) JEC/57/2019/VOL.I/6 Henry Young And Co. 563,172,144.01 Min of Finance 6 weeks

Supervision of the construction works at jigawa college of remedials and advance studies Min. of Education 403 27/11/2019 (JICORAS) babura, Lot-6 (3rd and 4th quarters 2019 capital projects) JEC/223/2018/VOL.I/67 Apex Design & Associates 23,537,374.82 6 months

TOTAL 13,231,544,548.08

27

SECTION ( E )

COMPLETED PROJECTS

JANUARY TO DECEMBER, 2019

Ministry of Health

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

1 General Renov ation/Improv ement w orks at Dutse General Hospital Ummu Khulsum Global Dutse 56,668,862.45 56,668,862.45 56,666,735.62 30/12/2016 16 w eeks 100 Completed Supply and Installation of Solar Powered Lightening System at 2 Dutse Gen. Hospital SIMS Global Resources Dutse 27,835,303.13 27,835,303.13 27,835,303.13 2/11/2017 8 Weeks 100 Completed

Supply and installation of Solar Powered lightening System in 3 Babura General Hospital. Sims Global Resources Babura 20,984,971.88 20,984,971.88 20,984,971.87 20/12/2017 8 Weeks 100 Completed

Supply and installation of Solar Powered lightening System in 4 GumelGeneral Hospital. Sims Global Resources Gumel 30,263,168.13 30,263,168.13 30,262,168.12 20/12/2017 8 weeks 100 Completed

General Renov./Improvement of Auyo Model Primary Health 5 Care at Auyo town, Auyo LGA. Math Global Investment Auyo 87,354,794.85 87,354,794.85 86,269,610.43 3/9/2018 24 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-3) at 6 Kale in Jahun Local Government Area. Baban-Doki General Entp. Jahun 19,816,590.02 19,816,590.02 18,497,752.60 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-4) at 7 Harbo Sabuwa in Jahun Local Government Area. Ngloma Constr. Comp. Ltd Jahun 20,061,603.77 20,061,603.77 20,052,221.17 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-16) at 8 Gora in Roni Local Government Area. Khanadi Global Links Roni 20,260,338.21 20,260,338.21 20,136,492.07 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-19) at 9 Zauma in Gwiwa Local Government Area. Ngloma Constr. Comp. Ltd Gwiwa 20,129,282.23 20,129,282.23 19,170,744.98 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-21) at 10 Yola in Gwiwa Local Government Area. Baban-Doki General Entp. Gwiwa 19,899,400.66 19,899,400.66 19,489,949.48 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-8) at 11 Hadin in Kaugama Local Government Area. Dangata Memorial Invest. Kaugama 19,495,565.93 19,495,565.93 18,197,951.22 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-23) at 12 Dabawa in Babura Local Government Area. Ngloma Constr. Comp. Ltd Babura 19,035,497.45 19,035,497.45 18,038,513.27 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-1) at 13 Dundubus in Dutse Local Government Area. ALLAH Abin dogara Nig. Ltd. Dutse 19,725,041.09 19,725,041.09 19,626,682.66 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-13) at 14 Chakwaikwaiwa in Taura Local Government Area. Baban-Doki General Entp. Taura 19,683,109.98 19,683,109.98 19,670,756.17 14/11/2018 12 weeks 100 Completed Balance C/F 401,213,529.78 401,213,529.78

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 401,213,529.78 401,213,529.78

Construction of Prototype Basic Health Care Clinic (Lot-17) at 15 Sankau in Roni Local Government Area. Al-Sabur Global Links Ltd. Roni 19,555,834.00 19,555,834.00 19,534,098.87 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-18) at 16 Takurdawa in Roni Local Government Area. Al-Sabur Global Links Ltd. Roni 19,416,248.88 19,416,248.88 19,394,181.48 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-20) at 17 Firjin Yola in Gwiwa Local Government Area. Pullad Global Consultant Nig Gwiwa 19,663,657.62 19,663,657.62 19,577,089.86 14/11/2018 12 weeks 100 Completed

Construction of Prototype Basic Health Care Clinic (Lot-7) at 18 Ubba in Kaugama Local Government Area. Nushe Business Resources Kaugama 20,025,983.09 20,025,983.09 19,997,296.20 14/11/2018 12 weeks 100 Completed

Construction of Prototype basic Health Care Clinic (Lot-6) at 19 Mezan in Kafin Hausa L.G.A. Asaka Construction Nig. Ltd. K/Hausa 19,315,830.95 19,315,830.95 18,285,824.55 14/11/2018 12 weeks 100 Completed

Construction of Prototype basic Health Care Clinic (Lot-2) at 20 Lafiya in Birnin kudu L.G.A. Imam Ahmad Nig. Ltd. B/kudu 19,956,897.66 19,956,897.66 19,840,781.07 14/11/2018 12 weeks 100 Completed

Construction of Prototype basic Health Care Clinic (Lot-11) at 21 Gagarawa Gari in Gagarawa L.G.A. Math Global Investment Ltd Gagarawa 20,290,282.93 20,290,282.93 20,157,450.85 14/11/2018 12 weeks 100 Completed

Construction of Prototype basic Health Care Clinic (Lot-15) at 22 Siyori in Garki L.G.A. Sabon Garin 'Yaya Garki 20,293,808.95 20,293,808.95 20,159,968.97 14/11/2018 12 weeks 100 Completed

Construction of Prototype basic Health Care Clinic (Lot-12) at 23 Jeke in Sule Tankarkar L.G.A. Sir Welter Drilling & General S/Tankarkar 20,887,831.00 20,887,831.00 20,734,104.26 14/11/2018 12 weeks 100 Completed

Construction of Prototype basic Health Care Clinic (Lot-9) at 24 Saleri in Kirikasamma L.G.A. Nushe Business Resources Kiri Kasamma 19,816,590.01 19,816,590.01 19,708,414.74 14/11/2018 12 weeks 100 Completed

Co ns tructio n o f pro to type bes ic Health Care Clinic (Lo t-5) Gafaya in 25 Kafin haus a L.G.A. Yusmatech Investment Nig. Ltd K/Haus a 20,637,816.30 20,637,816.30 20,489,694.12 14/11/2018 12 weeks 100 Completed

26 Co ns tr o f One blo ck o f Health po s t at Kwandiga village in Kaugama LGA. Sambu Synergy Concept Ltd. Kaugama 2,865,048.91 2,865,048.91 2,854,621.41 31/12/2018 8 weeks 100 Completed

27 Co ns tr o f o ne blo ck o f health po s t at Karko village in Gwaram LGA. Ngaloma Constr. Co. Ltd. Gwaram 7,543,976.80 7,543,976.80 7,520,739.77 31/12/2018 12 weeks 100 Completed

Balance C/F 631,483,336.88 631,483,336.88 1b

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 631,483,336.88 631,483,336.88 Co ns tr o f P ro to type Bas ic Health Care Clinic (Lo t-10) at Birniwa Tas ha in 28 Birniwa LGA. Wajabs Building and Constr Birniwa 19,756,195.59 19,756,195.59 19,656,319.72 14/11/2018 12 weeks 100 Completed Supply and Istallation of Hospital Equipments to Kafin hausa General 29 Ho s pital Dagari Integrated Services K/Haus a 83,543,417.50 83,543,417.50 83,543,417.50 28/12/2018 8 weeks 100 Completed

Construction for the construction of health post at Tashena Village in 30 M alam M adori Local Government Area. DALARI CONSTRUCTION M /madori 7,543,976.80 7,543,976.80 7,519,281.10 31/01/2019 8 Weeks 100 Completed Renovation works (2019 Phase I) Constittuency Project at Haya PHC and Gamji Health post in Fagam Constituency, Gwaram Local 31 Government Area. GIDAN ADEDE GENERAL Gwaram 12,468,995.04 12,468,995.04 12,421,231.26 31/01/2019 8 Weeks 100 Completed Construction of Health Post at Redo Viillage inGwaram Local 32 Government Area Ramadan Gwaram 7,543,976.80 7,543,976.80 7,184,739.76 14/01/2019 8 weeks 100 Completed Construction of Health Post at Sarkin Baka Village in Babura Local 33 Government Area Babandoki Babura 7,543,976.10 7,543,976.80 7,504,149.76 10/6/2019 8 weeks 100 Completed Construction of Health Post at Waza Viillage in Birnin Kudu Local 34 Government Area Ngaloma Construction B/kudu 7,543,976.80 7,543,976.80 7,520,739.76 14/1/2019 8 weeks 100 Completed Construction of Health Post at Karko Viillage inGwaram Local 35 Government Area Ngaloma Construction Gwaram 7,543,976.80 7,543,976.80 7,520,739.76 14/1/2019 8 weeks 100 Completed

36 Constr of Health Post at Shiyo in Auyo DDN Constr Co. Auyo 2,865,048.91 2,865,048.91 2,854,621.41 31/12/2018 8 weeks 100 Completed Contract for the supply & Installation of M edical Equipment to Ringim 37 General Hospital Dagarai Integrated Srv Ringim 82,153,507.50 82,153,507.50 82,153,507.50 1/7/2019 8 weeks 100 Completed 38 Constr of Health post of Sharkawa in Kaugama M aikatako & Sons Kaugama 7,543,976.80 7,543,976.80 7,184,739.76 31/12/2018 8 weeks 100 Completed M aintenance of toilets and reconstruction of soakway at female hostels 39 School of Nursing Hadejia GIDAN ADEDE GENERAL Hadejia 2,467,026.00 2,467,026.00 2,467,026.00 27/06/2019 8 weeks 100 Completed

Total 880,001,387.52 880,001,388.22

1c

Ministry of Water

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Improv ement of Kazaure tow n Water Supply Marb Eng. & Multy Serv ices Kazaure 131,208,239.13 163,939,534.76 156,132,890.23 7/28/2016 7 w eeks 100 Completed 2 Improv ement of Ringim tow n w ater supply Marb Eng. & Multy Serv ices Ringim 137,576,766.21 213,146,514.63 213,145,467.79 11/23/2016 20 w eeks 100 Completed

Constr. Of Hand Pumps Water Supply Schemes as Constituency Projects at Falkin Jalo Nasaraw a, Fulanin Kuka Uku, Fulanin Liman Mado, Fulanin Gangara and 3 Fulanin Dan'ama Gabas in Gumel Constituency . JAG & H Int. Serv ices Gumel 2,742,600.00 2,742,600.00 2,735,743.50 29/8/2017 8 w eeks 100 Completed Constr. Of Solar Pow ered Water Supply Schemes (Phase I) as Constituency Project at Mary e in Birniw a 4 Constituency ADZ GLOBAL SERV LTD Birniw a 6,968,010.00 6,968,010.00 6,950,589.98 7/8/2017 8 Weeks 100 Completed Constr. Of Hand Pumps Supply Schemes (Phase I-2017) as Constituency Project at Kofar Gabas Gw aram, Barebari Makabarta Sabuw a, Auy akaw a Gidan Dutse Gw aram, Tambo Gw aram and Sumangara in Gw aram 5 Constituency AZZIDS NIG LTD Gw aram 7,076,160.00 7,076,160.00 7,076,160.00 28/8/2017 8 Weeks 100 Completed Upgarding and Conv ersion of 7No Motorized Water Supply Schemes to Solar Pow ered Water Supply Schemes at Dundubus, Kafin Gana, Danmakama, 6 Marma, Bulangu, Dansure and Jigaw a Tow n. SIM S GLOBAL RESOURCE State 90,265,107.03 90,265,107.03 90,038,444.26 25/08/2017 16 weeks 100 Completed

Rehabilitation of Solar Pow ered Water supply schemes across the State at Birnin kudu, Dutse, Hadejia,Ringim, 7 Gumel, Jahun and Kazaure zone (Stow a) Sims Global Resources Across the state 166,689,700.28 166,689,700.28 166,272,976.03 18/12/2017 12 w eeks 100 Completed Constr of (10No.) Hand Pumps Water Suppy Schemes 2017 Constituency Phase II Projects (Lot-5) at Kw akw ado Fulani, Kabaw a, Danbagaje Fulani,Rigar Dumu Dakau, Fulanin Fankami, Gana , Gw allaw a Unguw ar Kole, Jama'ar Dan Maigari and Ribinji in Garki 8 Constituency Loy alty Properties Garki 7,980,000.00 7,980,000.00 7,980,000.00 1/24/2018 8 w eeks 100 Completed Constr. Of (1no.) Solar [pow ered w ater supply scheme 2017 constituency phase II project (LOT-29) at Kadamu 9 tudu tashena in M/madori Constituency . Limis Brothers & Co. M/madori 6,968,430.00 6,968,430.00 6,951,008.93 24/1/2018 8 w eeks 100 Completed Construction of (1No.) Solar Pow ered Water supply scheme 2017 Constituency phase III Projects (Lot-39) at 10 Jama'ar Suga in Kirikasamma Constituency . Bulangu Drilling Serv ices K/kasamma 6,968,430.00 6,968,430.00 6,968,430.00 6/2/2018 8 w eeks 100 Completed Construction of Hand Pumps Water Supply Scheme 2017 Constituency Phase III Projects (Lot-10) at Unguw ar Faru 11 in Kazaure Consituency . Na'ay i Resouces Ltd. Kazaure 797,580.00 797,580.00 797,580.00 6/2/2018 8 w eeks 100 Completed Balance C/F 565,241,022.65 673,542,066.70

2a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 565,241,022.65 673,542,066.70

Construction of (6No.) Hand Pumps Water supply scheme 2017 Constituency phase II Projects (Lot-10) at Faskarau, Ubba, Fulanin Askandu, Turmi, Kanjuw a and 12 Bay in Kw ari in Kaugama Constituency . ADZ Global Serv ices Ltd. Kaugama 4,803,750.00 4,803,750.00 4,791,740.65 22/2/2018 8 Weeks 100 Completed Upgrading and Conversion of Motorised Boreholes to Solar Powered at 7no. Towns water supply schemes (Kanya Babba in Babaura LGA, Danzomo in S/tankarkar LGA, Kudai in Dutse LGA and Waza 13 in B/kudu LGA) SIMS GlobalResources State 82,495,606.57 82,495,606.57 78,710,101.05 10/4/2018 16 weeks 100 Completed Constr of Hand pump Boreholes as constituency projects (2018 phase II) Lot-7 at Zunburu, Tange, S/garin Matsango, Bagiya, Ligada, Kuyungu (2no.), Rigar Beti Digijin and Tudun Wada Fagam in Fagam 14 Constituency. Loyalty Properties Nig. Ltd. Gwaram 6,603,660.00 6,603,660.00 6,603,660.00 18/12/2018 8 weeks 100 Completed Constr of Hand pump Boreholes as constituency projects (2018 phase II) Lot-10 at Fulanin Dan Ama, Dantanoma Sarkin Gora, Jarumai Abuja Quarters, Nasarawa M/Juma'a, Fulanin Kanjau, Haruna Kuka Uku, Fulanin Danfarantama, Garin Ginsau, Prison Qtrs. and Gidan maigari in Gumel 15 Constituency. Farham Synergy Concept Gumel 7,374,150.00 7,374,150.00 7,374,150.00 18/12/2018 6 weeks 100 Completed Conversion of 2no. Motorized boreholes to Solar powered water supply schemes at Main pump station Sule Tankarkar and Oliya pump station in 16 Sule Tankarkar LGA. SIMS Global Resources S/Tankarkar 42,243,266.00 42,243,266.00 42,243,265.99 31/12/2018 12 weeks 100 Completed Constr of Hand pump Boreholes as constituency projects (2018 phase II) Lot-2 at Guruma and 17 Mungula B/Kudu Constituency. Umar Aliyu & Sons Nig. Ltd. B/kudu 1,475,560.00 1,475,560.00 1,475,560.00 18/12/2018 4 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 18 9 at Zareku Miga Constituency. AMIA Integ. Services Miga 6,022,275.00 6,022,275.00 6,008,141.00 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 19 27 at U/Shuri in Babura Constituency. Mufabamex Consept Babura 6,020,700.00 6,020,700.00 6,008,057.21 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 47 at Danzomo Gari in Sule Tankarkar 20 Constituency. Lautai General Invest. S/tankarkar 6,023,115.00 6,023,115.00 6,008,057.21 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 21 28 at Kantudu in Roni Constituency. HIKIMA Synergy Gen. Roni 6,023,115.00 6,023,115.00 6,008,057.21 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 22 33 at Matsarida in Maigatari Constituency. A+Tech Integ. Nig Ltd. Maigatari 6,022,275.00 6,022,275.00 6,007,219.31 17/10/2018 8 weeks 100 Completed Balance C/F 740,348,495.22 848,649,539.27

2b

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 740,348,495.22 848,649,539.27 Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 40 at Farin Dutse in Fagam Constituency, Gwaram 25 LGA. A+Tech Integ. Nig Ltd. Gwaram 6,022,275.00 6,022,275.00 6,005,648.25 17/10/2018 8 weeks 100 Completed

Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 26 37 at Mai'adua in Gagarawa Constituency. LIMIS Brothers & Co. Gagarawa 6,020,700.00 6,020,700.00 5,985,000.00 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 27 31 at Takur in Dutse Constituency. Talaku Ingrated Services Dutse 6,000,000.00 6,000,000.00 5,985,000.00 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 28 32 at Rungumau in Dutse Constituency. Talaku Ingrated Services Dutse 6,000,000.00 6,000,000.00 5,985,000.00 17/10/2018 8 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 29 20 at Zabaran in Gumel Constituency. Muhal Global Concept Gumel 6,020,700.00 6,020,700.00 6,020,700.00 17/10/2018 8 weeks 100 Completed Constr of (10no.) Hand pumps Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 8 at Fulanin Akwalawa, Garin Kailu, Harbo sabo, Fulanin Mele, Dagerawa, Danfarantama, F/Mijin Gini, Lautai Science, Boarding Girls Pri. & JSS and 30 Kuka Uku Fulani in Gumel Constituency. Muhal Global Concept Gumel 7,347,380.00 7,347,380.00 7,347,379.99 17/10/2018 12 weeks 100 Completed Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 31 6 at Anturu in Birniwa Constituency. Synclime Nig. Ltd. Birniwa 6,023,115.00 6,023,115.00 6,008,057.21 17/10/2018 8 weeks 100 Completed

Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 32 5 at GGSS Birniwa in Birniwa Constituency. Synclime Nig. Ltd. Birniwa 6,022,276.00 6,022,276.00 6,007,220.31 17/10/2018 8 weeks 100 Completed

Constr of (7no.) Hand Pumps Water Supply Scheme Constituency Projects (2018 phase 1) Lot-2 at Bagudu, Dugujaba, Gangara Nabunu, Wada Tsohuwa Tudu, Jan Zomo, Babbar Riga and 33 Yarkirya in babura Constituency. Mufabamex Concept Babura 5,100,676.00 5,100,676.00 5,100,676.00 17/10/2018 8 weeks 100 Completed

Constr of (5no.) Hand Pumps Water Supply Scheme Constituency Projects (2018 phase 1) Lot-3 at Kauyen Boka, Dukari, Kyaurawa, fagoje U/Iya and 34 Mungulo in Birnin Kudu Constituency. Nushe Business Resources B/kudu 3,656,467.50 3,656,467.50 3,647,326.34 17/10/2018 8 weeks 100 Completed

Balance C/F 798,562,084.72 906,863,128.77

2c

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 798,562,084.72 906,863,128.77

Constr of (6no.) Hand Pumps Water Supply Scheme Constituency Projects (2018 phase 1) Lot-10 at Rahaina, Takalafiya, Jangwam Fulani, Tasgan Gabas, Madamuwa and Garmaguwa Yamma in Guri 35 Constituency. A.Y.H. Investment Co. Guri 4,415,040.00 4,415,040.00 4,404,002.40 17/10/2018 8 weeks 100 Completed

Construction of (28NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 13 at Gidan Danko, Bayan Gidan Wanka, Likindi, Damutawa Kazage, Kukawa Fulani, Afasha, Lilon Dan Baki, Tsalliyawa Kunguyun, Mahauta, Jabarna Kauye, Fantagwal, Zagau Makera, Abirikyau T. Gabas, Tsibiri, Masallacin M. Madibo, Gidan Tila, Gangaren Kwalta, Yalleman K. Gabar. Gidan Atiku, Kwanyoli, Gidan Hakimi, Jabarna, Darai Madobi, Bayan Katarin, Yalayin Kolrori, Kandahar and 36 Sabon Kaye in Jahun Constituency. Jawad Global Resources Jahun 20,572,664.00 20,572,664.00 20,572,663.99 17/10/2018 8 weeks 100 Completed

Construction of (10NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 16 at Yan Auta, Miyawa, Yalwan Fulani, Sabuwar Unguwa, Nafara Alh. Uba, Sabuwar Raba, Yolal, Jigawar Kiyawa, Ung. Dahiru Mai Gyada and 37 Mandela in Kiyawa Constituency. Demastbo Ventures Ltd. Jahun 7,377,825.00 7,377,825.00 7,377,825.00 17/10/2018 12 weeks 100 Completed

Construction of (25NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 4 at Laraba, Zangon Farin Dutse, Kwanar Fado, Kakibare, Sayasaya Sabuwar Yalwa, Gayawa Zai, Kalusa, Gidan Kuka mainari, Dutsin Duru Ungullo Kagara, Taju, Ruwan Baure, Lemunawa, Hora Arewa, Dabawa Zango, Gidan Gawo, Kundi, Tsangayar Jan Shuri, Kargo Mahauta Manhada and 38 Dilake in Dutse Constituency. Talaku Integrated Services Dutse 18,361,875.00 18,361,875.00 18,315,970.31 17/10/2018 12 weeks 100 Completed

Balance C/F 849,289,488.72 957,590,532.77

2d

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 849,289,488.72 957,590,532.77

Construction of (10NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 19 at Dan kawu Hardo Take, Tubus Hardo Gatag M. Amadu, Gidan Dogo Hardo Ruwa, Abdullahi Balga Hardo Dawa, Barmanawa Gari, Kunkurai Gari, Akwai ALLAH Gari, Sabo mai Kalanda Hardo Juli, Saidi Dogo Fulanin Gwata Gidan Rabo Fulani and 40 Zokoto in Sule Tankarkar Constituency. Lautai Genaral Investment S/tankarkar 7,377,825.00 7,377,825.00 7,377,825.00 17/10/2018 12 weeks 100 Completed

Construction of (15NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 7 at Muku, Tsalle, Balashe, Fankami, Tsagwaye, Jirima, Magatarin B/ALLAH, Doguwar Kuka, Kwadage Dan karofi, Gwallawa, Kabawa, Kwana,Zaidawa, Karangi and Koguran Tsohuwa in 41 Garki Constituency. A.D.Z. Global Services Ltd. Garki 18,884,580.00 18,884,580.00 18,884,580.00 17/10/2018 8 weeks 100 Completed Construction of (1NO.) Water Collection Point Constituency projects (2018 Phase I) Lot 9 at Rigar 42 Kangal in Taura Constituency. Nushe Business Resources Taura 1,199,677.50 1,199,677.50 1,196,678.31 17/10/2018 4 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-30) at Yan Duna in Miga 43 Constituency. Amia Integ. Service Nig Ltd. Miga 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 44 Projects (Lot-27) at Muduga in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 6,201,720.00 6,201,720.00 6,201,720.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-37) at Botsotsuwa in Babura 45 Constituency. Mafabamex Concept Nig. Ltd. Babura 6,023,199.00 6,023,199.00 6,008,141.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-34) at Maradawa in Kazaure 46 Constituency. Yanduna Ventures Ltd. Kazaure 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-33) at Kanti Gabas in Kazaure 47 Constituency. Yanduna Ventures Ltd. Kazaure 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Balance C/F 907,045,919.22 1,015,346,963.27

2e

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 907,045,919.22 1,015,346,963.27 Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-38) at Achiya in Babura 48 Constituency. Mufabamex Concept Ltd. Babura 6,023,199.00 6,023,199.00 6,008,141.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-4) at Lawandi in Birniwa 49 Constituency. Limis Brother & Co., Birniwa 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed Construction of (3NO.) Water Collection Point Constituency Projects (2018 Phase 1) Lot-12 at Walawa (2NO.) and Kofar Tukura (1NO.) in Hadejia 50 Constituency. Step by Step Integrated Hadejia 3,600,002.70 3,600,002.70 3,591,002.69 23/10/2018 6 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 51 Projects (Lot-5) at Kukuma in Buji Constituency. Limis Brother & Co., Buji 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-17) at Kirilla in Maigatari 52 Constituency. Limis Brother & Co., Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-43) at Gayawa Tudu in Gagarawa 53 Constituency. Limis Brother & Co., Gagarawa 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-44) at San Amarya in Gagarawa 54 Constituency. Limis Brother & Co., Gagarawa 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-36) at Matsa in Malam Madori 55 Constituency. Hambiscon Nig. Ltd. M/Madori 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-11) at Kila Kofar Arewa in Gwaram 56 Constituency. Jag & H Intgrated Serv. Ltd. Gwaram 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 57 Projects (Lot-31) at Burji in Miga Constituency. A. Barde Global Concept Miga 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 58 Projects (Lot-28) at Dabaka in Miga Constituency. A. Barde Global Concept Miga 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed

Balance C/F 970,877,134.92 1,079,178,178.97

2f

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 970,877,134.92 1,079,178,178.97

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 59 Projects (Lot-15) at Guri in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 60 Projects (Lot-16) at Arin in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 61 Projects (Lot-13) at Dawa in Guri Constituency. A. y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-14) at ArinJasko in Guri 62 Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III 63 Projects (Lot-12) at Musari in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-9) at Juma'ar Yunusa in Kafin Hausa 64 Constituency. Tosarawa Global Nig. Ltd. K/Hausa 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-8) at Autako in Kafin Hausa 65 Constituency. Mugin Investment Nig. Ltd. K/Hausa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-6) at Majefarin Yamma in Kafin Hausa 66 Constituency. Mugin Investment Nig. Ltd. K/Hausa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-7) at Ansaya in Kafin Hausa 67 Constituency. Mungin Investment Nig. Ltd. K/Hausa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-41) at Babbar Riga in Malam Madori 68 Constituency. Step By Step intgrated Servic M/madori 6,023,125.00 6,023,125.00 6,008,067.18 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-32) at Bagade Gari in Sule Tankarkar 69 Constituency. Danfatu & Sons Nig. Ltd. S/tankarkar 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Balance C/F 1,037,131,094.92 1,145,432,138.97

2g

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,037,131,094.92 1,145,432,138.97 Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-24) at Burdawa S/Gabas in Gwiwa 70 Constituency. Jignaj Global Constructions Gwiwa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-25) at Buntusun Abuja in Gwiwa 71 Constituency. Jignaj Global Constructions Gwiwa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-39) at Sankara in Ringim 72 Constituency. Marb Engr. Multi-Services Ringim 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed Supply of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects + (3no. Saflex pumps) (Lot-40) at Karshi, Fachama 73 and Gamoji in Ringim Constituency. Marb Engr. Multi-Services Ringim 10,872,138.69 10,872,138.69 10,872,138.69 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-35) at Andaza Kudu in Kiyawa 74 Constituency. Farham Intgratred Resources Kiyawa 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-2) at Kaigamari in Auyo 75 Constituency. Madanta Global Nig. Ltd. Auyo 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-19) at Bakawa in Maigatari 76 Constituency. Alkawakeb Global Concept Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Upgrading of 1no.) motorized Water Supply Schemes 2018 Constituency Phase III Projects (Lot- 77 22) at Digijin in Fagam Constituency. Pullad Global Consultant Gwaram 10,872,138.69 10,872,138.69 10,872,138.69 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes (2018 Phase III) Constituency 78 Projects at Shiyo in Auyo Constituency. Alaska Genral Enterprises Auyo 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes (2018 Phase III) Constituency 79 Projects at Garin Jama'u in Gagarawa Constituency. Altima Intgrated Services Gagarawa 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 80 Phase II) Lot-10 at Takalafiya in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed Balance C/F 1,113,083,680.30 1,221,384,724.35

2h

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,113,083,680.30 1,221,384,724.35 Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 81 Phase II) Lot-9 at Garbo in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-47 at Gidan Gona in Kazaure 82 Constituency. Lautai Genaral Investment Kazaur e 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-41 at Maguwa in Kirikasamma 83 Constituency. Talaku Intgrated Services K/Kasamma 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-35 at Kakudi Babba in Suletankarkar 84 Constituency. Talaku Intgrated Services Sule tankarkar 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-39 at Solari in Kirikasamma 85 Constituency. Loyalty Properties Ltd. Kirikasamma 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-27 at Babura Yamma in Babura 86 Constituency. Mufabamex Concept Ltd. Babura 6,014,355.00 6,014,355.00 5,999,319.11 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 87 Phase II) Lot-50 at Gizo in Kazaure Constituency. Yanduna Ventures Ltd. Kazaure 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-49 at Yar'Unguwa in Kazaure 88 Constituency. Yanduna Ventures Ltd. Kazaure 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-3 at Jam'ar Ayan in Auyo 89 Constituency. Khairussabah Nig. Ltd. Auyo 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-36 at Shadamai in Yankwashi 90 Constituency. Granitoids Engr. Services Ltd Yankwashi 6,023,220.00 6,023,220.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-37 at Karkarna in Yankwashi 91 Constituency. Granitoids Engr. Services Ltd Yankwashi 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 92 Phase II) Lot-1 at Anauya in Auyo Constituency. Farham Intgratred Resources Auyo 6,023,220.00 6,023,220.00 6,007,952.47 23/11/2018 8 weeks 100 Completed

Balance C/F 1,185,352,720.30 1,293,653,764.35

2i

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,185,352,720.30 1,293,653,764.35 Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 P ha se II) Lot- 44 a t Kuzunzumi in Ka nya Ba bba 93 Constitue nc y. Limis Brother & Co., Babura 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed

Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 94 P ha se II) Lot- 24 a t Ka ma in Ma iga ta ri Constitue nc y. Limis Brother & Co., Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed

Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 95 P ha se II) Lot- 25 a t Dira ni in Ma iga ta ri Constitue nc y. Limis Brother & Co., Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed

Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 96 P ha se II) Lot- 23 a t Ma ifa ri in Ma ga ta ri Constitue nc y. Limis Brother & Co., Magatari 6,023,010.00 6,023,010.00 6,007,952.48 23/11/2018 8 weeks 100 Completed Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 P ha se II) Lot- 40 a t Ila lla h in Kirika sa mma 97 Constitue nc y. Sahal Bin Nig. Ltd. Kirikasamma 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 P ha se II) Lot- 38 a t Kira misa u in Kirika sa mma 98 Constitue nc y. Sahal Bin Nig. Ltd. Kirikasamma 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 P ha se II) Lot- 16 a t Rora n Ma la ma i in Gwiwa 99 Constitue nc y. Jignaj Global Constructions Gwiwa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 100 P ha se II) Lot- 44 a t Da ushe in Ringim Constitue nc y. Marb Engr. Multi-Services Ringim 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed

Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 101 P ha se II) Lot- 46 a t Ma ra wa in Ringim Constitue nc y. Marb Engr. Multi-Services Ringim 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 102 P ha se II) Lot- 7 a t Ba kwa rga in Buji Constitue nc y. Limis Brother & Co., Buji 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed

Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 103 P ha se II) Lot- 8 a t Gwa ngwa n in Buji Constitue nc y. Limis Brother & Co., Buji 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Construc tion of the (1 No.) S ola r P owe re d Wa te r Supply Schemes Constituency Projects (2018 104 P ha se II) Lot- 22 a t Ga rba ga l in Guri Constitue nc y. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed

Balance C/F 1,257,630,310.30 1,365,931,354.35

2j

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,257,630,310.30 1,365,931,354.35 Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-31 at Maijiruwa in Gagarawa 105 Constituency. Danfatu & Sons Nig. Ltd. Gagarawa 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 106 Phase II) Lot-2 at Kwazumo in Auyo Constituency. Danfatu & Sons Nig. Ltd. Auyo 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 107 Phase II) Lot-21 at Abunabo in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 108 Phase II) Lot-20 at Zugo in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-19 at Garmaguwa Yamma in Guri 109 Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.48 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-18 at Garmaguwa Gabas in Guri 110 Constituency. A. Y. H. Invest. Co. Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 111 Phase II) Lot-17 at Zugobiya in Guri Constituency. A. Y. H. Invest. Co. Guri 6,075,720.00 6,075,720.00 6,060,530.70 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-28 at Unguwar Dinya in Roni 112 Constituency. Hikima Synergy Gen. Entp. Roni 6,023,199.00 6,023,199.00 6,008,141.00 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-30 at Amaryawa in Roni 113 Constituency. Hikima Synergy Gen. Entp. Roni 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-29 at Unguwar Mani in Roni 114 Constituency. Hikima Synergy Gen. Entp. Roni 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed

Balance C/F 1,311,890,719.30 1,420,191,763.35 2k

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,311,890,719.30 1,420,191,763.35

Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 115 Phase II) at Kabala Jahun in Jahun Constituency. Dalari Constr Co. Jahun 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed

Construction of (5 No.) Hand Pump Water Supply Schemes Constituency Projects (2018 Phase I) Lot- 21 at Gidan Nokia Fulani, Karkarna C/Gari, S/Fulani Gurjiya, Karkarna Islamiyya and Ringim in 116 Yankwashi Constituency. Granitoids Engr. Services Ltd Yankwashi 3,644,025.00 3,644,025.00 3,634,914.93 17/10/2018 8 weeks 100 Completed Construction of (4No.) Solar Powered Water Supply Schemes at Garin ganau, Kwadage, Chika- koshi and Kankaren Nagona in Babura L. G. A. 117 (Ringim Zone). Sims Global Resources Nig. Babura 24,093,300.00 24,093,300.00 24,093,300.00 12/12/2018 12 weeks 100 Completed Construction of (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-48 at Gwabbare in Kazaure 118 Constituency. Yanduna Ventures Ltd. Kazaure 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed Construction of (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-47 at Gidan Gona in Kazaure 119 Constituency. Yanduna Ventures Ltd. Kazaure 6,023,122.00 6,023,122.00 6,008,161.95 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes (2018 Phase III) Constituency Projects (Lot-42) at Matara Galadima in 120 Kirikasamma Constituency. Bulangu Drilling Services K/kasamma 6,023,010.00 6,023,010.00 6,023,010.00 31/12/18 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes (2018 Phase III) Constituency Projects (Lot-29) at Garin Abdalla in Miga 121 Constituency. Xtrax 99 Integrated Services Miga 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Solar Powered Water Supply Schemes (2018 Phase II) Constituency Projects (Lot-43) at Kanya Arewa in Kanya Babba 122 Constituency. Limis Brother & Co., Babura 6,023,010.00 6,023,010.00 6,007,952.48 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency (Phase III) Projects (Lot-10) at Be-bayi in Kafin Hausa 123 Constituency. Tosarawa Global Nig. Ltd. K/Hausa 6,023,010.00 6,023,010.00 6,023,010.00 12/12/2018 8 weeks 100 Completed Construction of Water Collection Point as Constituency Projects (2018 Phase III) Lot-24 at Tsohuwar Gwaram, Guduma, Katsinawa and 124 Dutsen Gandu in Gwaram Constituency. Farham Synergy Concept Ltd. Gwaram 5,011,996.00 5,011,996.00 5,011,995.96 18/12/2018 8 weeks 100 Completed Balance C/F 1,380,778,632.30 1,489,079,676.35

2L

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,380,778,632.30 1,489,079,676.35

Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase III) Lot-7 at Gidan Nakuka, Makwai Fulani, Dandidi (4 No.), Gidan Kato Furya, Gidan Badawai, Fulanin mai 126 Adu'a and Kukule in Gagarawa Constituencyi Farham Synergy Concept Ltd. Gagarawa 7,374,150.00 7,374,150.00 7,374,150.00 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase III) Lot-12 at Limawa, Afaru, Giwaran, Kununu Zaki, Kuzan Iliya and Kwazalewa Gidan Mafi in Kafin Hausa 127 Constituencyi Faahm Intgratred Resources K/Hausa 4,425,750.00 4,425,750.00 4,425,750.00 18/12/2018 6 weeks 100 Completed Construction of Water Collection Point as Constituency Projects (2018 Phase III) Lot-28 at Ajaura (Pipe Line Extention) and Gidan 128 (W.C.Point) in Taura Constituency. Nushe Business Resources Taura 4,874,063.25 4,874,063.25 4,861,878.09 18/12/2018 8 weeks 100 Completed

Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase III) Lot-18 at 129 Majiya Secondary School in Taura Constituencyi Nushe Business Resources Taura 737,520.00 737,520.00 737,520.00 18/12/2018 4 weeks 100 Completed

Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase III) Lot-15 at Kabobo Chaichai, 'Yanduna kawai, Dandalin Wailari, Takwasha, Chaichai Makabarta and Amaguwa in 130 Ringim Constituencyi Marb Engr. Multi-Services Ringim 4,426,680.00 4,426,680.00 4,415,413.30 18/12/2018 8 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-5 at Akurya, Limawa, Gumussawa, Gabari, Yola Musa, Mawa, Bujaje, Jigawar Gabas, Rigar Jauro Mato, Rigar Buba Salewa, Gulungulun, Karsha, Suwameri, ALLAH kayi, Tumba gidan Baba Sarki, Aduna Dikko, Shagewa, Yammarin A. Mato, Shagen Yamma Danlalan Fulanin Village, Gamajan, Kuloma, Sadingo Garin Mati, Babbar Jigawa, Alhajerin Chiromari, Chakwasan, Guduwari Gidan Gaiya, Mangari, Mawalan Tumunjira and Rigar 131 Buba Habbo in Bulangu Constituencyi Bulangu Drilling Services K/Hausa 25,036,410.00 25,036,410.00 24,973,818.97 18/12/2018 12 weeks 100 Completed

Balance C/F 1,423,226,525.55 1,531,527,569.60

2m

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,423,226,525.55 1,531,527,569.60 Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-19 at Alagarno Gari Haru, Tarawa Fulani, Haro Yale, Babbar Dinya, Balarabe, Harso Sale, Gidan Nomau and Gidan M/manu in Maigatari 132 Constituency. Nadada Ventures Nig. Ltd. Maigatari 5,869,920.00 5,869,920.00 5,869,920.00 18/12/2018 8 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-23 at Girgi Gari, Tsangaya, Jemau,Sabon Layi Unguwar Barde Banaga, Sakataren Muyatti ALLAH, Hardo Yahaya Balkindo, Hardo Lauwali Fulanin Girgi Yamma, Zanguna, Jumawa Gari, Nazau Gari, Fulanin Walawa Gidan Haruna Babe, Dungundun Gari and Gidan Shuaibu 133 Ajiya HardoIla in Sule Tankarkar Constituency. Nushe Business Resources S/tankarkar 8,844,192.00 8,844,192.00 8,822,081.52 18/12/2018 8 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-18 at Tsotsawa Fulani and Bakata 134 Cikin Gari in Kiyawa Constituency. Faahm Intgratred Resources Kiyawa 1,467,730.00 1,467,730.00 1,467,730.00 18/12/2018 4 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-16 at Rangina, Kantamari, Gangara, Motso, Karumi, Mai Kunama, Rugar Kota Buhun Karangiya, Meleri Marke, Masama Karama, Fulanin Kagori, Kaugama Yamma, Kanwar Gamawa, Manda Mai Gawo and Anguwar Habulle in Kaugama 135 Constituency. Faahm Intgratred Resources Kaugama 14,569,232.00 14,569,232.00 14,569,232.00 18/12/2018 10 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-8 at Firya, Garin Inu, Zaro, Dan Daga 136 Arewa and Habatsai in Gagarawa Constituency. Farham Synergy Concept Ltd. Gagarawa 3,687,075.00 3,687,075.00 3,687,075.00 18/12/2018 6 weeks 100 Completed

Balance C/F 1,457,664,674.55 1,565,965,718.60

2n

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,457,664,674.55 1,565,965,718.60

Construction of Water Collection Point as Constituency Projects (2018 Phase II) Lot-29 at Unguwar Kanya T/Gwaram, Shiwo Sara, Sakuwa Sara, Lukutu, Innakawa, Maruta cikin Gari, Yaddare Kila, Unguwar kudu Z/nagogo, Gogurawa Yamma Z/Nagogo, Lafiya Tsangarwa Shabewa Tsangarwa,Fasa Ganga T/Gwaram, Sakwaya Maruta Tsahira T/Gwaram GGUSS Gwaram and 137 Salmande in Gwaram Constituency. Jag & H Intgrated Services Ltd. Gwaram 22,686,282.00 22,686,282.00 22,686,281.10 18/12/2018 12 weeks 100 Completed

Construction of Water Collection Point as Constituency Projects (2018 Phase II) Lot-28 at Tsamiyar Osi, Ahabab Rasulillahi Ado Tela Gana, Layin Babar Sardauna, Tudun Alhazai, College of Education, Kofar Danmakwayo, Dantanoma S/Kwalta, Layin GidanGalaba, Layin Gidan Dallatu, Dantanoma L/Mari Audu, Gidan Gawo, Egoni Sabon Layi, Famfom Gawo, Masallacin J/Gabas and 138 Masallacin Yarabawa in Gumel Constituency. Farham Synergy Concept Ltd. Gumel 20,165,584.00 20,165,584.00 20,165,583.99 18/12/2018 12 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-3 at Dagolori, Fulanin Mariye, Buhunni, Fulanin Nguwa, Fajiginari, Medori, Birniwa Unguwar Mangawa, Birniwa T/kudu, Kadairi, Goruban Tingiri and Gidan usaini wanzam 139 in Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 8,833,860.00 8,833,860.00 8,811,775.35 18/12/2018 6 weeks 100 Completed Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase II) Lot-15 at Rabo Fulani (4No), Kankaren Jemawa, Jolowa Fulani, Sansami, Toge, Halladu, Kwadabe Fulanin Shuaibu, Dan Maakeri, Fulanin Tsamiyar Kwance, Fulanin Yamma, Kwanar Kuzunzumi and Dorawar 140 Waje in Kanya Babba Constituency. Deetech Nig. Ltd. Babura 11,072,250.00 11,072,250.00 11,072,250.00 18/12/2018 10 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-3 at Kupsa, Fulanin Karda, Barbura, Baltori, Zigidimi, Marge and Busugu Abdu in 141 Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 5,330,906.00 5,330,906.00 5,317,578.73 31/12/18 8 weeks 100 Completed Balance C/F 1,525,753,556.55 1,634,054,600.60

2O

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,457,664,674.55 1,565,965,718.60

Construction of Water Collection Point as Constituency Projects (2018 Phase II) Lot-29 at Unguwar Kanya T/Gwaram, Shiwo Sara, Sakuwa Sara, Lukutu, Innakawa, Maruta cikin Gari, Yaddare Kila, Unguwar kudu Z/nagogo, Gogurawa Yamma Z/Nagogo, Lafiya Tsangarwa Shabewa Tsangarwa,Fasa Ganga T/Gwaram, Sakwaya Maruta Tsahira T/Gwaram GGUSS Gwaram and 137 Salmande in Gwaram Constituency. Jag & H Intgrated Services Ltd. Gwaram 22,686,282.00 22,686,282.00 22,686,281.10 18/12/2018 12 weeks 100 Completed

Construction of Water Collection Point as Constituency Projects (2018 Phase II) Lot-28 at Tsamiyar Osi, Ahabab Rasulillahi Ado Tela Gana, Layin Babar Sardauna, Tudun Alhazai, College of Education, Kofar Danmakwayo, Dantanoma S/Kwalta, Layin GidanGalaba, Layin Gidan Dallatu, Dantanoma L/Mari Audu, Gidan Gawo, Egoni Sabon Layi, Famfom Gawo, Masallacin J/Gabas and 138 Masallacin Yarabawa in Gumel Constituency. Farham Synergy Concept Ltd. Gumel 20,165,584.00 20,165,584.00 20,165,583.99 18/12/2018 12 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-3 at Dagolori, Fulanin Mariye, Buhunni, Fulanin Nguwa, Fajiginari, Medori, Birniwa Unguwar Mangawa, Birniwa T/kudu, Kadairi, Goruban Tingiri and Gidan usaini wanzam 139 in Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 8,833,860.00 8,833,860.00 8,811,775.35 18/12/2018 6 weeks 100 Completed Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase II) Lot-15 at Rabo Fulani (4No), Kankaren Jemawa, Jolowa Fulani, Sansami, Toge, Halladu, Kwadabe Fulanin Shuaibu, Dan Maakeri, Fulanin Tsamiyar Kwance, Fulanin Yamma, Kwanar Kuzunzumi and Dorawar 140 Waje in Kanya Babba Constituency. Deetech Nig. Ltd. Babura 11,072,250.00 11,072,250.00 11,072,250.00 18/12/2018 10 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-3 at Kupsa, Fulanin Karda, Barbura, Baltori, Zigidimi, Marge and Busugu Abdu in 141 Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 5,330,906.00 5,330,906.00 5,317,578.73 31/12/18 8 weeks 100 Completed Balance C/F 1,525,753,556.55 1,634,054,600.60

2O

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,525,753,556.55 1,634,054,600.60 Construction of Water Collection Points Constituency Projects (2018 Phase II) Lot-26 at Gomburawa, Kachallari and Gajarma in Birniwa 142 Constituency. Kafiyama Gen. Enterprises Birniwa 3,778,327.26 3,778,327.26 3,768,881.43 18/11/2018 8 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-9 at Rigar Lamido Gandu Una, Rigar Wuro Jigga, Gaduwa, Rigar Gapta, Maiyiri, Rigar 143 Lamido Nairi and Rigar Zuzu in Guri Constituency. A.Y.H. Investment Ltd. Guri 8,054,970.00 8,054,970.00 8,034,832.57 18/11/2018 10 weeks 100 Completed Construction of Water Collection Points Constituency Projects (2018 Phase II) Lot-34 aFilin Aya, Veterinary, Tsohuwar Quarters Yamma da Tsamiya, Unguwar M. Danmodoji, Mains Goma Shabiyu, Sule kudu Pri. Sch., Tsangayar M. Liman,Kofar gidan Rabiu Hassan, Tsangayar M. Haruna K/Arewa Gari, Gaban Gidan Najib Councilor K/Gabas,Masallacin M. SaleDan Birib K/Yamma and Kofar Gidan Aminu Ado Kofa in Sule 144 Tankarkar Constituency. Pullad Global Consultant S/tankarkar 14,716,363.00 14,716,363.00 14,678,572.09 18/12/2018 8 weeks 100 Completed

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-14 at Rigar Wakiliya'a, Zubafinji and 145 Jarmari in Malam madori Constituency. Express Innovation Concept M/madori 2,213,340.00 2,213,340.00 2,207,806.65 18/12/2018 6 weeks 100 Completed

Renovation of (1No) Solar Powered Water supply Scheme Constituency Projects (2018 Phase II) Lot- 146 26 at Jingino in Gwaram Constituency. Bakawa Multi Services Ltd. Gwaram 6,023,115.00 6,023,115.00 6,008,057.21 23/12/2018 8 weeks 100 Completed

Upgrading and Conversion of Wurma Town Water Supply Schemes to Solar Powered Water supply 147 Scheme in Dutse L. G. A. Sims Global Resources Dutse 16,451,241.45 16,451,241.45 15,667,848.99 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-6 at Kiroro Duru Ward, Irwa Limawa Ward, Laraba Kudai Ward, Zai cikin gari Kachi Ward, Dutsawa J/Tsada Ward and Gadadin Kachi 148 Ward in Dutse Constituency Loyalty Properties Nig. Ltd. Dutse 4,402,440.00 4,402,440.00 4,402,440.00 18/12/2018 6 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-6 at Yalwan Gabas, Rigar kaba, Bakawa, Damagyal, Dabawa, Shiti, Ije, Tsungur, 149 Kwanar Fado and Junawo in Dutse Constituency Loyalty Properties Nig. Ltd. Dutse 7,337,800.00 7,337,800.00 7,337,799.99 18/12/2018 8 weeks 100 Completed

Balance C/F 1,572,279,911.81 1,680,580,955.86

2p

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,572,279,911.81 1,680,580,955.86 Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-1 at Gamba kaban, Ayama K/bulama, 150 Aguza and Jejin Garo in Auyo Constituency Khairussabah Nig. Ltd. Auyo 2,947,560.00 2,947,560.00 2,947,560.00 18/12/2018 6 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) at Fulanin Fateka, Fulanin Garin Malam Makarantar Yamma and fulanin marma in Malam 151 madori Constituency. Limis Brothers & Co. M/madori 5,164,110.00 5,164,110.00 5,151,199.72 18/12/2018 6 weeks 100 Completed

Co ns tructio n o f Hand P ump Bo reho les Water Supply Schemes Constituency P rojects (2018 P hase II) Lot-9 at Unguwar Saidu, Fulanin Madachi, Unguwar s hege Unguwar kale,Ufala Fulanin Farjak, Gunzara, Zankawa, Gidan Wada Daurawa, Gas atanni Garki, Fulanin Rairai, Tafin Sale, Kita, Yarkures he, Unguwar Gayya, Fulanin Dandarai, Kargo Sabuwar Unguwa, Gidan Baki, Barmawa Gari, Abdawa muku Ward, Rigar Hardo Ibrahim Ko re, Rigar Us man Mai Bare, Ko re Sabuwar Unguwa, Gwadayawa, Kukar mekiya, Garin Makera, Rigar Malam Adamu kugi, Ko far Gidan Na'abi Garki, Ko far Gidan Liman Garki and Ko far Gidan 152 Cici Garki in Garki Co ns tituency. ALLAH Abin Dogara Nig. Ltd. Garki 22,121,190.00 22,121,190.00 22,121,190.00 18/12/2018 12 weeks 100 Completed Construction of Water Collection Point as Constituency Projects (2018 Phase II) Lot-27 at Umboro, Aujara, Kwanar Garki, Siyore Cikin Gari, Magarya Garki and Sabuwar Unguwa in Garki 153 Constituency. ALLAH Abin Dogara Nig. Ltd. Garki 7,562,094.00 7,562,094.00 7,562,094.00 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-11 at Rigar Wakili Ya'a, Zubafinji, Jarmari, Kwanar mai Labbo, Garin Malam S/Guga 154 and Tasgan Yamma in Guri Constituency. Limis Brothers & Co. Guri 4,426,380.00 4,426,380.00 4,415,314.05 18/12/2018 6 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 155 Phase III) Lot-4 at Bulangori in Buji Constituency. Limis Brothers & Co. Buji 737,625.00 737,625.00 735,780.93 18/12/2018 4 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot-4 at Gogel Kukuma, Rigar Shehu Kado Kukuma, Dakawa Danbazau and Galadima Bebeji in 156 Buji Constituency. Limis Brothers & Co. Buji 2,950,920.00 2,950,920.00 2,943,542.70 18/12/2018 6 weeks 100 Completed

Balance C/F 1,618,189,790.81 1,726,490,834.86

2q

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,618,189,790.81 1,726,490,834.86 Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase II) Lot-17 at 157 Farar Dutsanya and Gizo in Kazaure Constituency. Yanduna Ventures Ltd. Kazaure 1,472,730.00 1,472,730.00 1,472,730.00 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) at Takwardawa, Roni Gabas, Kalage Gabas, Kwanar Ganji, Dage Baderi and Bahe Elde 158 in Roni Constituency. Hikima Synergy Gen. Enterp. Roni 4,422,096.00 4,422,096.00 4,411,040.76 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-16 at Roni Mission, Ruwan Dutse, Jahoko, Rahamawa A. Roni and Marke in Roni 159 Constituency. Hikima Synergy Gen. Enterp. Roni 3,687,600.00 3,687,600.00 3,678,381.00 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-1 at Fulanin Tudun Yola, Jammutum Arewa, Fulanin Aunaka, Koko and Rubunji in 160 Babura Constituency. Mufabamex Concept Nig. Ltd. Babura 3,688,650.00 3,688,650.00 3,679,428.38 18/12/2018 8 weeks 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-7 at Gidan Nakuka, Makawai Fulani, Fulanin Dandidi (4No.), Gidan Kato Furya, Gidan badawai, Fulanin Mai adu'a and Kukule in 161 Gagarawa Constituency. Farham Synergy Concept Ltd. Gagarawa 7,374,150.00 7,374,150.00 7,374,150.00 22/12/2018 8 weeks 100 Completed Upgrading and Conversion of Motorized Boreholes to Solar Powered Water supply Scheme at Mairakumi Town in Malam madori L. G. A. (Hadejia 162 Zone). Sims Global Resources Ltd M/madori 14,518,546.88 14,518,546.88 13,827,187.50 31/12/2018 8 weeks 100 Completed

Conversion of Motorized Pumps to Solar Powered Water supply Scheme at Jama'are pump station in 163 K/hausa L.G.A. Sims Global Resources Ltd K/Hausa 14,998,281.46 14,998,281.46 14,284,077.58 31/12/2018 8 weeks 100 Completed

Conversion of Motorized Pumps to Solar Powered Water supply Scheme at Unguwar kudu in Auyo 164 L.G.A. Sims Global Resources Ltd Auyo 16,809,055.11 16,809,055.11 16,008,623.91 31/12/2018 8 weeks 100 Completed

Construction of (1No.) Solar Powered Water supply Schemes (2018 Phase III) Lot-42 at Medu Town in 165 Gagarawa Constituency. Dantatu Gen. Constr. Eng. Gagarawa 6,023,010.00 6,023,010.00 6,023,010.00 31/12/2018 8 weeks 100 Completed Balance C/F 1,691,183,910.26 1,799,484,954.31 2r

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,691,183,910.26 1,799,484,954.31 Construction of (1No.) Solar Powered Water supply Schemes (2018 Phase III) Constituency Projects Lot- 166 46 at Magaji Kufai in Gagarawa Constituency. A.A. Aljazeera Agro Proc. Gagarawa 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed Construction of new Solar Powered Pump Water supply Schemes at Babura Tsallake in Babura 167 ConstructionL.G.A. of Water Collection Points Water Sims Global Resources Ltd Babura 25,563,695.34 25,563,695.34 24,346,376.25 31/12/2018 8 weeks 100 Completed supply Schemes Constituency Projects (2018 Phase II) Lot- 25 at Giginya, Achiya, Babura Tsallake, Garin Ganau, Marken Biki, Gurfai, Yammaulu, Botsotsuwa and Kwando in Babura 168 Constituency. Mufabamex Concept Ltd. Babura 11,037,269.25 11,037,269.25 11,009,679.08 18/12/2018 10 weeks 100 Completed Construction of Water Collection Points Constituency Projects (2018 Phase III) Lot- 20 at Babura Islamiyya, Gangara Hanware, Baskwar and 169 Chirimbi in Babura Constituency. Mufabamex Concept Ltd. Babura 4,905,453.00 4,905,453.00 4,893,189.32 18/12/2018 8 weeks 100 Completed Construction of Water Collection Points as Constituency Projects (2018 Phase II) Lot- 30 at Unguwar Sankira, Kandahar, Kofar Abdullahi Ranbo, Unguwar Aminu Yusuf and garejin musan 'O' 170 in Hadejia Constituency. Alh. Umaru Babandoki Ltd. Hadejia 6,131,816.25 6,131,816.25 6,116,486.71 18/12/2018 8 weeks 100 Completed

Construction of Water Collection Points as Constituency Projects (2018 Phase II) Lot-33 at 171 Gumuma in Roni Constituency. Hikima Synergy Gen. Enterp. Roni 1,226,363.25 1,226,363.25 1,223,297.34 18/12/2018 6 weeks 100 Completed

Construction of (30No). Hand Pumps at Tsakuware, Gidan Hanau (Madatta), Timbau, Bekawa, Sabon Gari, Kandiren Wailare, Zanguna, Damfar Jigawa, Tsallake, Rugagen Melefe, Kafin Dan Yayi, Jaunare, Unguwar Duhuwa, Gidan Gide, Gidan Maja, Danzago, Naino Sabon Garin Jigawa, Tsugunau, Garin Baki, Chirimbi Malamai, Rugar Hardo Hassan, Ribinjin Manzo, Gurfan Batali, Jan Mutum, Lambar Lululu, Rahar Hanau, Nabai, Kaya Harimi 172 and Kankaren Nagona in Babura L.G.A. Limis Brothers & Co. Babura 22,138,200.00 22,138,200.00 22,082,854.50 28/12/2018 15 weeks 100 Completed

Upgrading and Conversion of (2No.) Motorized Boreholes to Solar Powered Water supply Scheme at Gurfai in Babura L.G.A. of Ringim Zone, Garkon Alli in Kiyawa L.G.A. of Dutse Zone, and Construction of 1No. New Solar Water Supply Schemes at Luddaga in Birnin kudu L.G.A. of Birnin 173 kudu Zone. Sims Global Resources Ltd State 31,275,783.95 31,275,783.95 29,786,460.90 31/12/2018 12 weeks 100 Completed

Balance C/F 1,777,347,301.30 1,885,648,345.35

2s

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,777,347,301.30 1,885,648,345.35

Construction of (22No). Hand Pumps at Jankoli, Unguwar Malam, Doguwar Dorawa, Gidan Kwano, Bodawa, Digawar Kwando, Babajiya, Gidan Gitti, Shafa, Kyara, Gage, Yantuba, Kaliya Jemawa, Karkafawa, Fulanin Danmarke, Adugul Fulani, Danmakera, Waje, Fulanin Masko and Aunaka Gari 174 in Babura L.G.A. Sir Welter Drilling & Gen. Serv Babura 16,234,680.00 16,234,680.00 16,194,093.30 28/12/2018 12 weeks 100 Completed

Construction of 50No Hand Pumps Boreholes at 50 175 Communities Across the State Sir Walter & Gen Serv State 36,897,000.00 36,897,000.00 36,897,000.00 5/3/2019 16 week 100 Completed Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase II) Lot- 24 at Kawaye, Karkarna Bakin Titi, Rauda durbe, Gwarta Karama and rauda Asibitin 176 Yankwashi Constituency. Granitoids Engr. Services Ltd. Yankwashi 3,685,082.10 3,685,082.10 3,675,869.39 18/12/2018 6 weeks 100 Completed S upply a nd instla tion of (1nN0.) 30KVA Ge ne ra tor set 2018 Constituency projects (Lots -40) at 177 Dabuwaran in Kaugama constiuency Madanta Global nig. Ltd Kaugama 3,740,625.00 3,740,625.00 3,740,625.00 23/11/2018 8 weeks 100 Completed Constr of 11no. Hand pumps water supply constituency project phase III 2018 (Lot- 7) at Wallere, S/Gari, Redo, Shinfida, Daragi, Tsamiya, Kafa Doya, Kundiga, Daurawa, Fara Fulani and 178 Sabuwar Yola in Gwiwa Jignaj Global Gwiwa 8,113,297.50 8,113,297.50 8,093,014.26 18/12/2018 12 weeks 100% Completed Rehab of Some water supply scheme at Maidabaru 179 and Nazau in S/tankarkar L.G.A. Centuary Trade Ltd. S/Tankarkar 2,956,078.13 2,956,078.13 2,948,687.93 31/12/2018 8 weeks 100% Completed Rehab and Maintenance of 5no. Water supply scheme at Limawa A,B,C, Galamawa and Karnaya 180 in Dutse L.G.A. Limis Brothers & Co Dutse 3,585,192.19 3,585,192.19 3,414,468.75 31/12/2018 4 weeks 100% Completed

Rehab of 2no. Water supply Scheme at Dansure, 181 Roni and Gafaya town in K/Hausa L.G.A. Limis Brothers & Co Roni+K/Hausa 1,584,843.57 1,584,834.51 1,509,375.00 31/12/2018 4 weeks 100% Completed Rehab of 4no. Water supply Scheme at Arbus, Karoro, Dodorin Malan Audu, and Ronjin in 182 Kaugama L.G.A. Limis Brothers & Co Kaugama 3,611,204.57 3,611,204.57 3,439,242.45 31/12/2018 4 weeks 100% Completed Rehab of 4no. Small towns water supply schemes at Albasu main station, Albasu Hospital, Katangar Lafiya and Chediyar Kuda in Gumel, Dutse and 183 Kazaure zones. Limis Brothers & Co State 4,932,998.44 4,932,998.44 4,698,093.75 31/12/2018 8 weeks 100 Completed

Construction of Water Collection Points as Constituency Projects (2018 Phase Ii) Lot-32 at Maigatari, Balarabe, Matoya, Bosuwa, Galadi, 184 Madana and Jajeri in Maigatari Constituency JAG & H Integrated Maigatari 8,822,443.00 8,822,444.00 8,822,444.00 14/1/2019 8 Weeks 100 Completed

Balance C/F 1,871,510,745.80 1,979,811,781.79

2t

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,871,510,745.80 1,979,811,781.79 Construction of 1no Solar Powered water supply 185 scheme at Nafara in Kiyawa LGA, Dutse Zone Sims Global Resources Kiyawa 6,023,325.00 6,023,325.00 6,023,325.00 16/4/2019 8 weeks 100 Completed

Construction of 4No. Solar Powered Water supply scheme at Danmarke, Wada,Kayarda and Garin 186 Baki in Babura LGA Ringim Zone Sims Global Resources Ringim 24,093,300.00 24,093,300.00 24,093,300.00 16/4/2019 12 Weeks 100 Completed

Rehabilitation of 2No Small Towns water supply schemes at Yandamo and Malam Baki in Gumel 187 Zone Forte Technical Services Ltd Gumel 8,482,573.26 8,482,573.26 8,078,641.20 31/5/2019 8 weeks 100 Completed

Construction of 12No Hand Pump Boreholes water supply schemes at Sule Fulanin Yandamo ( Gidan Mallam) Fulanin Kwalawa( Gidan Kato dan Goma), Fulanin dan Kiri ( Gidan Dan Bako) Garin Goto, Fulanin Kukule Gabas ( Gidan Isah Kato) Fulanin Malam Kadiri ( Gidan Sale), Fulanin Dantuwo ( Gidan Ingire), Dan Adama Gari, Fulanin Dan Adama ( Gidan Abdullahi), Dankira, Sabon Garin Dankirya and Fulanin dan Kumbo ( Gidan Hardo Kan Doki) in Sule Tankarkar Local Government Area Gumel 188 Zone. Al-Juraj Synergy Concept S/tankarkar 8,855,280.00 8,855,280.00 8,855,280.00 8/5/2019 12 weeks 100 Completed

Construction of 15No. Hand Pumps Boreholes water supply scheme at Sinti, Garin Goshi, Fulanin Masama ( Hardo Tamabya) Dantuwo Gari, Dantuwo Tsangaya, Tashar Bala S/Tankarkar, Balarabe Mai Gari, Fulanin Jalko( Gidan Rabiu) Hardo Dan Kawo ( Fulanin Kuka Maidire), Sabon Garin Dan Yarda, Fulanin Dan Banki ( Gidan Sha'aibu Jikan Hajja), Fulanin Tiriki ( Hardo Ilu), Fulanin Charko(Gidan Dabbi) and Ma'azu Gidan Salisu Tifa in Sule Tankarkar Local Government 189 Area, Gumel Zone Al-Kawakeb Global Concept S/Tankarkar 11,069,100.00 11,069,100.00 11,069,100.00 8/5/2019 12 weeks 100 Completed

Balance C/F 1,921,551,750.80 2,029,852,786.79

2u

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,921,551,750.80 2,029,852,786.79

Construction of 22No Hand Pump Boreholes water supply schemes at Yandamo gari A, Yandamo Gari B, Garin Yasai, Hardo Jauro, Kargo, Fulanin Lula, Madoji Tsalle, Fulanin Barnawa Fulanin Bayan Eka STK, Fulanin Santarbi, Dangoho, Fulanin Mai Rago ( Yamma) Buntusu Fulani, Fulanin Hardo Musa S.Tankarkar Fulanin Kurguna, Fulanin Kaina unguwar Yamma ( Danzomo) in Sule Tankarkar LGA and Kwanar Tsuru, Garin Kwalandi, Garin Malam, Gabasawar Kwalandi and Fulanin Shabarawa ( 190 Gidan Ibrahim Bidu) in Maigatari LGA Forte Technical Services Ltd Maigatari 16,234,680.00 16,234,680.00 16,194,093.30 8/5/2019 12 weeks 100 Completed

Construction of 2No. New Solar Powered Water supply Schemes at Malarin Gamm in Malam Madori Local Government Area and Walawa in 191 Birniwa Local government Area Hadejia Zone BSY Industries Nig Ltd M/madori + Birniwa 12,046,650.00 12,046,650.00 12,016,533.37 31/05/2019 8 weeks 100 Completed Rehabilitation of 17no. Small towns water supply 192 schemes at hadejia and Jahun Zone BSY Industries Nig Ltd Hadejia + Jahun 5,161,739.63 5,161,739.63 4,915,942.50 31/05/2019 8 weeks 100 Completed Procurement of Assorted Submersible pumps 193 Across the State Umar Aliyu & Sons Nig Ltd Across the state 19,479,796.87 19,479,796.87 18,552,187.50 16/4/2019 8 Weeks 100 Completed Procurement of 2No. 200KVA Perkins Generating 194 Set for Kazaure and Birnin Kudu Zone Limis Brothers & Co B/Kudu 28,619,712.07 28,619,712.07 28,619,712.07 16/4/2019 8 Weeks 100 Completed Extension of Pipe borne water supply line (Lot-27) phase III-2018 Constituency project at Achauya 195 village in S/Tankarkar . Pullad S/Tankarkar 3,647,700.00 3,647,700.00 3,647,700.00 31/12/2018 8 weeks 100 Completed Constr of Solar Water Scheme at Hammadi in 196 Babura Constituency Mufabamax Nigeria Ltd. Babura 6,020,700.00 6,020,700.00 6,005,648.25 17/10/2018 8 weeks 100 Completed Constr of 6no. Hand pumps boreholes (2018 phase III) Constituency projects at Gidantawa, Ganzayi A, Gidan Chaya, K/Hausa basen Asibiti, Kanzan Masarafa and Yam Darma Element in K/Hausa 197 Constituency. Dantatu Nigeria Ltd. K/Hausa 4,426,380.00 4,426,380.00 4,415,314.05 18/12/2018 8 weeks 100 Completed Constr of Solar water Scheme at Ando in Babura 198 Constituency Mufabamax Nigeria Ltd. Babura 6,020,700.00 6,020,700.00 6,005,648.25 17/10/2018 8 weeks 100 Completed

199 Constr of 45no. Hand pumps Boreholes at Babura Safah & Fresh Int. Babura 33,207,300.00 33,207,300.00 33,207,300.00 7/3/2019 16 weeks 100 Completed Balance C/F 2,027,797,397.30 2,136,098,433.29

2v

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 2,027,797,397.30 2,136,098,433.29 Constr of Solar water scheme at Madari in Kanya 200 Babba Constituency Mufabamax Nigeria Ltd. Babura 6,023,115.00 6,023,115.00 6,008,057.21 21/12/2018 8 weeks 100 Completed Constr of Solar water supply scheme at Gayana 201 Tudu in Gagarawa L.G.A. Limis Brothers & Co Gagarawa 6,023,005.00 6,023,115.00 6,008,057.21 20/5/2019 8 weeks 100 Completed 202 Constr 2no Bore holes at Hadejia LGA Limis Brothers & Co Hadejia 1,254,519.00 1,254,519.00 1,251,382.70 28/12/2018 4 weeks 100 Completed Rehab of Water Scheme at Dadda in Stankarkar 203 LGA Guidence Agency for Excellence S/Tankarkar 1,447,031.25 1,447,031.25 1,443,413.67 8/1/2019 4 weeks 100 Completed Constr of 3no. Hand pumps water supply (Lot-14) phase III 2018 Constituency projects at Sabuwar Kwalta, Rugar Zargu, and Dakuna town in 204 M/madori Constituency. Express Innovation Co. Ltd. M/madori 2,213,340.00 2,213,340.00 2,207,806.65 14/01/2019 8 weeks 100 Completed Rehab of Madoji solar water Scheme at Abanderi 205 in S/Tankarkar LGA Giant Tech Ltd. S/Tankarkar 1,667,531.25 1,667,531.25 1,588,125.00 3/6/2019 4 weeks 100 Completed Constr of solar water Scheme at Abanderi in Dutse 206 LGA Limis Brothers & Co Dutse 4,598,493.32 4,598,493.32 4,379,517.45 31/12/2018 8 weeks 100 Completed Co ns tr o f (38No ) Hand P umps at Makadi'B', Gangara waje, jiji'B' Unguwar Sama, Gidan Hardo Gawo , Gidan Beti dan Maigari, bo dawa C, Unguwar Ts amiya B, GJ ASS Baura, GGADSS Babuura, Ts adura, Babura Arewa B, Kaute B, in babura LGA, Duts e Capital Scho o l in Duts e, unguwar Lawan in J ahun, tunubu to wn in J ahun, kuka in /S/Tankarkar, Gidan Danta Fulani, Kanawa Aume, dan Amale Fulani, Gage Yamma, J elawa Damu, Kauyen Fulani HP in babura LGA, Shamuri HP in S/Tankarkar, Tinubu, Hayin Tara Yamma in J ahun, Burukum Fulani, Gidan Makeri, Minu, Unguwar Magaji, Batali, Malamawa, Bikawa Batali, Muni A, Gidan Dawa and Dan Makeri G/Nagawo in 207 Babura LGA Bulangu Drilling Babura 28,041,729.00 28,041,729.00 28,041,720.00 9/8/2019 14 weeks 100 Completed

Upgrading and Co nvers io n o f 1No . Mo to rixzed water s upply s cheme to s o lar po wered at Maizuwo in Sule 208 tankarkar LGA Sims Global Resources S/Tankarkar 6,829,987.50 6,829,987.50 6,504,750.00 6/8/2019 4 weeks 100 Completed

Upgrading and Co vers io n o f 1No . Mo to rized water s upply 209 s cheme to s o lar po wered t Gangara in Babura LGA Sims Global Resources Babura 6,829,987.50 6,829,987.50 6,504,750.00 6/8/2019 4 weeks 100 Completed

Rehabilitation of 6no water scheme in Hadejia, 210 Gimel and Jahun, Zones Limis Brothers & Co State 5,047,035.00 5,047,035.00 5,047,035.00 23/11/2018 6 weeks 100 Completed Rehab of 3no water schemes in Gumel and Jahun 211 zones Limis Brothers & Co Gumel+Jahun 4,089,750.00 4,089,750.00 4,089,750.00 20/08/2019 6 weeks 100 Completed Rehab of 4no water schemes in Ringim and 212 Hadejia zones Sims Global RingimAuyo + Hadejia + 7,543,200.00 7,543,200.00 7,543,200.00 20/02/2019 6 weeks 100 Completed Rehab of 6no water schemes in Auyo, K/kasamma K/kasamma 213 & hadejia Sims Global +Hadejia 7,660,800.00 7,660,800.00 7,660,800.00 20/8/2019 6 weeks 100 Completed Rehab of 10no water schemes in Hadejia, 214 M/madori, Kaugama, Birniwa, Guri & Auyo Sims Global State 7,660,800.00 7,660,800.00 7,660,800.00 20/8/2019 6 weeks 100 Completed Rehab of 10no water schemes in Ringim and 215 Gumel zones Sims Global Ringim + Gumel 7,541,100.00 7,541,100.00 7,541,100.00 20/8/2019 6 weeks 100 Completed Balance C/F 2,132,268,821.12 2,240,569,967.11

2w

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 2,132,268,821.12 2,240,569,967.11

Rehab of 9no water schemes in Ringim, Kazaure 216 and Dutse zones Sims Global State 6,413,400.00 6,413,400.00 6,413,400.00 20/8/2019 6 weeks 100 Completed

Constr of 1no Solar water supply schemes at 217 Achau in Jahun LGA Loyalty Properties Ltd. Jahun 6,023,325.00 6,023,325.00 6,023,325.00 15/01/2019 8 weeks 100 Completed

Maintenance of Generators in Gumel from Dec, 218 2017 to Dec, 2018 Marbs Eng. Ltd. Gumel 2,607,937.50 2,607,937.50 2,607,937.50 20/12/2017 24 months 100 Completed

Maintenance of 2no. Generators in Babura town 219 from Dec, 2017 to Dec, 2018 Marbs Eng. Ltd. Babura 582,750.00 582,750.00 582,750.00 1/12/2017 24 months 100 Completed

Maintenance of 4no.Generators in Ringim town 220 from Dec, 2017 to Dec, 2018 Marbs Eng. Ltd. Ringim 2,945,908.25 2,945,908.25 2,945,908.25 3/11/2018 24 months 100 Completed Maintenance of 3no.Generators in Ringim town 221 from Dec, 2016 to Dec, 2017 Marbs Eng. Ltd. Ringim 2,802,187.50 2,802,187.50 2,802,187.50 21/12/2016 24 months 100 Completed

Maintenance of Generators inBabura town from 222 Dec, 2017 to Dec, 2018 Prestige Integ. Services Babura 582,750.00 582,750.00 582,750.00 1/12/2017 12 months 100 Completed

Constr of 22no Hand pumps in K/kasamma 223 constituency (phase III 2018) Lot-13 Dabino Internation Ltd. K/kasamma 16,230,060.00 16,230,060.00 16,230,060.00 31/12/2018 12 weeks 100 Completed

Constr of Solar Powered Water Supply Schemes Constituency Project ( 2019 Phase 1) Lot-42 at 224 Kilawa in Fagam Contituency. Jignaj Global Contr Ltd Gwaram 6,023,220.00 6,023,220.00 6,023,220.00 11/12/2019 8 weeks 100 Completed

Upgradingand Conversation of 1no. Motorised water Supply Scheme (2019 phase1 ) Constituency 225 Project Lot-22 at Zauma in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 8,685,075.00 8,685,075.00 8,685,075.00 11/12/2019 8 weeks 100 Completed

Upgradingand Conversation of 1no. Motorised water Supply Scheme (2019 phase1 ) Constituency 226 Project Lot-23 at Korayalin Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 6,863,325.00 6,863,325.00 6,863,325.00 11/12/2019 8 weeks 100 Completed Renov of 2no. Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 24 at Gidan Kudege and Kurneji in Gwiwa 227 Constituency Jignaj Global Contr Ltd Gwiwa 3,227,700.00 3,227,700.00 3,227,700.00 11/12/2019 8 weeks 100 Completed Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 41 at tsallakawa in Fagam Constituency, Gwaram Local 228 Government Area Jignaj Global Contr Ltd Gwaram 6,023,220.00 6,023,220.00 6,023,220.00 11/12/2019 8 weeks 100 Completed

Balance C/F 2,201,279,679.37 2,309,580,825.36

2x

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 2,201,279,679.37 2,309,580,825.36

Upgrading and Conversion of Zaburan, Small Town Motorised Water Supply Scheme to Solar Powered 229 in Kaugama Local Government Area. Sims Global Resources Nig Ltd Kaugama 16,917,862.50 16,917,862.50 16,112,775.00 6/8/2019 8 weeks 100 Completed

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-4 at wuro bagga, gamawari, yola zairare, fulanin takaje, sabon gidan gabas, fulanin kufayi, hijabau, adamante, rugar abdul kogi, masharmo, makwasharga, waryam B, lautayi, Yambo, Jalingo G/kwalli, kawarin gari, yadda, gidan yauto (Z/kanya), gumurwa G.A Idi, Rimin kasuwa and shamakeri B/hanya in Bulangu 230 constituency Bulangu drilling serveices LtdK/Hausa 15,491,227.50 15,491,227.50 15,491,227.50 11/12/2019 12 Weeks 100 Completed

TOTAL 2,233,688,769.37 2,341,989,915.36 2y

Ministry of Works

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Constr. of Internal Road Netw ork and Drainage at College of Agriculture YamidiAmirco Univ ersal Concept Hadejia 114,852,386.25 499,296,564.31 499,296,564.31 6/10/2011 20 w eeks 100 Completed

2 Reconstr. Of Asphaltic concrete ov erlay of Kijaw al-Dabi road (4.5km) Triacta Nig. Ltd. Ringim 453,412,679.27 526,840,847.35 526,837,028.02 18/3/2013 3 months 100 Completed 3 Urban Tow ns Streetlight Projects at Karkarna Tow n Stratrade Nig. LTD Yankw ashi 234,338,917.73 234,338,917.73 230,270,845.40 11/11/2013 6 Months 100 Completed Commissioning as Consultant for the Superv ision of the Constr. of Gumel- 4 G/Gambo, feeder roads, M/madori-Dakido, Shafar-G/sani OPIQ Consultant LTD. Gumel 16,024,856.75 16,024,856.75 16,024,856.75 3/3/2014 6month 100 Completed 5 Constr. of feeder road at gumel-Garin Gambo in Gumel L.G.A. Omega Stars Nig. Ltd. Gumel 149,763,131.44 149,763,131.44 149,763,131.44 13/02/2014 6 months 100 Completed 6 Consulltancy serv ices for the Constr. Of Kiy ako-Zarenaw a feeder road UKM Civ il Eng. Consultant B/kudu 16,187,482.45 16,187,482.45 16,187,482.00 2/2/2014 8 months 100 Completed Commissioning as consultant for the superv ision of Kazaure tow nship roads 7 (15KM) Wuro Associate Kazaure 92,141,988.97 92,141,988.97 85,842,229.66 5/9/2013 8 months 100 Completed Commissioning as Consultant for the Constr. of Sule Tankarkar Tow nship 8 roads Thamar Eng. Ltd. S/tankarkar 64,638,503.00 64,638,503.00 58,339,028.04 13/02/2014 12 months 100 Completed 9 Re-Constr. of Sule Tankarkar Tow nship road (5.16km) Afdin Constr. Co. Ltd. S/tankarkar 727,649,360.56 909,561,700.70 857,941,087.50 4/4/2016 8 months 100 Completed

10 Cons. of Handpumps Across the State (RUWASA) Muhabib Nig. Ltd State 28,000,000.00 28,000,000.00 26,000,013.06 3/1/2014 4month 100 Completed Supervision of the construction of Maigatari-Galadi-Girbobo- 11 Diginsa-Birniwa Road (Phase II) (37.1KM) HIMMA TECH SERV. Birniwa 74,761,966.60 74,761,966.60 74,760,523.27 18/05/2017 13 months 100 Completed Supply and installation s of 150 Units Integrated stand alone Solar 12 Powered Streetlight at Aujara in Jahun Local Govt Area Sims Nig. Ltd. Jahun 95,192,680.94 95,192,680.94 90,659,703.75 14/12/2017 12 weeks 100 Completed Constr of Dutse-Madobi-Katanga-Dangoli with Spur from Madobi to 13 Baranda road (35.7km) Lot -1 Gerawa Global Eng Ltd. Dutse 4,643,482,872.42 4,643,482,872.42 4,640,482,872.21 27/4/2018 12 months 100 Completed Rehab/Asphalt Overlay of Babura-Yarkirya-Kuzunzumi road 14 (49.4km) lot -5 Gerawa Global Eng Ltd. Babura 4,944,415,159.06 4,944,415,159.06 4,941,128,617.95 27/4/2018 8 months 100 Completed Constr of Access road from Harbo Sabuwa to Harbo Tsohuwa 15 (1.52km) lot-9 Retercha Co. Ltd. Jahun 241,058,058.35 241,058,058.35 240,921,302.79 27/4/2018 4 months 100 Completed Constr of Bariki-Munzarau-Tawakkalta-Turabu road (16.8km) lot- 16 6 CGC Nig. Ltd. Hadejia 2,919,955,823.72 2,919,955,823.72 2,919,634,562.05 4/5/2018 12 months 100 Completed Electrification project at Katurje in Kafin Hausa Constituency, Kafin 17 Hausa LGA. Kawu Nig. Ltd. K/Hausa 10,916,014.48 10,916,014.48 10,023,514.47 10/5/2018 16 weeks 100 Completed Commissioning as Consultant for the Supervision of the Constr. of 18 Babura township roads (10.28km) UKM Civil Eng. Babura 45,933,233.82 45,933,233.82 45,933,237.82 7/6/2018 10 months 100 Completed Commissioning as Consultant for the Supervision of the Rehab./Asphalt Concrete Overlay of Babura-Yarkirya -Kuzunzumi 19 road (49.4km) HAG Eng Consultants Babura 86,527,265.28 86,527,265.28 86,212,265.27 7/6/2018 8 months 100 Completed

Supply and Installations of Integrated Standalone Solar Powered 20 Streetlight at Yalleman Town in Kaugama LGA SIMS Nig. Ltd. Kaugama 85,276,275.00 85,276,275.00 82,792,500.00 25/9/2018 3 months 100 Completed

21 Constr of Gadadin-Jigawar Sarki road (600m) in Dutse LGA. Retercha Company Ltd Dutse 64,554,624.07 64,554,624.07 64,554,624.07 20/12/2018 3 months 100 Completed

22 Constr. Of Kaugama-Mallam Madori Feeder Road (19.31km) Lot-15 IGEE Eng. Ltd. M/madori 520,687,101.38 520,687,101.38 520,082,820.60 21/12/2018 6 months 100 Completed Construction of Hammado-Danfarantama-mele-Balkarya-Kokinami- 23 Limanmado-Barikin faka-Gumel Feeder Road (33.0KM) Lot 17. Babandoki Gen. Enterp. Gumel 911,985,078.38 911,985,078.38 911,971,052.16 21/12/2018 6 months 100 Completed

Balance C/F 16,541,755,459.92 17,181,540,146.20 3a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 16,541,755,459.92 17,181,540,146.20 Construction of Kazaure - Gallu Babba - Karkarna Feeder Road 24 (16.0KM) Lot 13. China Zhanghao Nig. Ltd.Kazaure/Yankwashi 527,255,190.00 527,255,190.00 527,223,814.03 27/12/2018 6 months 100 Completed

Construction of Kanya Babba - Kankare - Ballada - Duzau - Dan 25 Halili - Kyambo - Mundu - Goran Maje Feeder Road (19.KM) Lot 18.A.Y.A. Logistics & Constrt Ltd. Babura 512,115,693.47 512,115,693.47 511,568,526.00 24/12/2018 6 months 100 Completed

26 Construction of Kanya Babba Township Road (2.0KM) Lot 10. Mother Cat Nig. Ltd. Babura 346,070,232.61 346,070,232.61 343,974,392.46 24/12/2018 6 months 100 Completed Rehabilitation of Hadejia - Aguyaka - Gudincin Road (4.30KM) Lot 27 13. Centralead Nig. Ltd. Hadejia 972,823,696.47 972,823,696.47 923,431,810.86 24/12/2018 8 months 100 Completed 28 Electrification Project at Masanawa in Kiyawa L.G.A. Nabakwai Gen. Enterprises Kiyawa 19,149,196.14 19,149,196.14 18,810,572.61 24/12/2018 12 weeks 100 Completed 29 Electrification Project at Hambarawa in Ringim L.G.A. Al-Majeed Constr. Nig. Ltd Ringim 14,261,545.68 14,261,545.68 14,236,065.78 24/12/2018 12 weeks 100 Completed 30 Electrification Project at Gidan Garke in Ringim L.G.A. Al-Majeed Constr. Nig. Ltd Ringim 13,314,314.45 13,314,314.45 13,290,203.07 24/12/2018 12 weeks 100 Completed 31 Electrification Project at Guntai in Gwiwa L.G.A. H & N Engr. Consultancy Gwiwa 38,057,153.66 38,057,153.66 38,055,053.50 24/12/2018 16 weeks 100 Completed Maintenance of Failed Section of Auyo - Kafin hausa Road (100) 32 Section 'B' Retercha Company Ltd Auyo 51,175,143.02 51,175,143.02 51,083,760.00 31/12/2018 12 weeks 100 Completed 33 Electrification Project at Kanya Babba - Muna in Babura L.G.A. Deetech Nig. Ltd. Babura 29,981,471.52 29,981,471.52 27,374,387.04 24/12/2018 16 weeks 100 Completed Maintenance of Failed Section of Auyo - Kafin hausa Road (150) 34 Section 'A' Retercha Company Ltd K/hausa 69,533,544.12 69,533,544.12 69,392,935.50 31/12/2018 12 weeks 100 Completed 35 Electrification Project at NTA Hadejia in Hadejia L.G.A. Xtra X-99 Integ. Services Hadejia 19,427,729.87 19,427,729.87 19,419,923.62 31/12/2018 12 weeks 100 Completed

36 Electrification Project at Sambo Primary School Hadejia in Hadejia L.G.A. A+Techn. Integ. Services Hadejia 14,876,542.55 14,876,542.55 14,087,057.64 31/12/2018 12 weeks 100 Completed Construction of Block Line Drainages (738M ) at Basirka Town in Gwaram 37 L.G.A. Pullad Global Consultant Gwaram 22,726,861.79 22,726,861.79 22,726,861.79 24/12/2018 12 weeks 100 Completed Supply and Installations of 130 Units Integrated Standalone Solar Powered 38 Streelight at Danzomo in Sule Tankarkar L.G.A Sims Nigeria Limited S/Tankarkar 82,515,030.00 82,515,030.00 74,843,565.00 1/17/2018 16 weeks 100 Completed Supply and instlation of standalone solar power streetlight at Bekarya, mele 39 and Danmanomi towns in Gumel LGA Sims glo bal res . Nig ltd Gumel 91,008,225.00 91,008,225.00 88,200,000.00 22/11/2018 16 weeks 100 Completed

40 Co ns tr o f ro ad Netwo rk at Co llege o f Educatio n, Gumel (3.3km) lo t-4 H & M Nig. Ltd. Gumel 674,198,072.42 674,198,072.42 672,895,458.69 30/4/2018 6 mo nths 100 Completed 41 SupplyCo ns tr ando f Gadadin-J Installations igawar of Integrated Sarki ro ad, Standalone Duts e (600m) Solar Powered Streetlight Retercha Co . Ltd Duts e 64,554,624.07 64,554,624.07 64,146,465.81 20/12/2018 3 mo nths 100 Completed at Hammado-Gagarawa (200 Unit) Bosuwa (100 Unit) iri (100 Units) M anga- Takwasa (120 Unit) and Unguwar Gawo-Batali-Kuzunzumi-Balarabe (200 unit) 42 Total 720 Units (Lot 2) SIM S NIGERIA LTD Gagarawa 430,360,875.00 430,360,876.00 430,349,174.12 12/2/2019 14 Weeks 100 Completed Construction of block line drain and Filling of Low Area in M ajia Community 43 of Taura LGA Ummukhulsum Invest Taura 86,485,008.42 86,485,008.42 86,470,998.89 20/06/2019 6 month 100 Completed Supply and Installation of inytegrated standalone Solar Powered Streetlight at buji (150 Units), Basirka/Digijin (120 Units), Kudai (100 Units), balanngu- Sarawa (100 Units) Garin Gabas (160 Units) and Birniwa Tasha (100 units) 44 Total 710 units (Lot-1) Arrayan Ventures Global State 403,649,600.00 403,649,600.00 392,133,000.00 16/4/2019 14 weeks 100 Completed Commissioning as Consultant for the Supervision of the Construction of Yankwashi 45 Kazaure-Fanda-Sabaru-Gallu-Karkarna Feeder Road (16km) UKM Civil Engineering +Kazaure 9,226,965.83 9,226,965.83 9,226,965.82 20/3/2019 6 weeks 100 Completed

Balance C/F 21,034,522,176.01 21,674,306,863.29 3b

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

BAL. B/F 21,034,522,176.01 21,674,306,863.29

Commissioning as consultant for the Supervision of the Supply and Installation of Intergrated Standalone Solar Powered Streetlights at Buji 150 units, Basirka/Digijin 120 Units, Kudai 100 Units, Bulangu-Sarawa 100 units, 46 Commissioninggarin Gabbas 160 as units Consultant and birniwa for Tashathe Supervision 100 Units (totalof the 710 Supply Units) and ARDUGAL Engineering Ltd State 7,606,368.00 7,606,368.00 6,606,368.00 26/3/2019 4 months 100 Completed Installation of Integrated Standalone Solar Powered Streetlights at Hammado-M aituruniya-Duhuwa-Gangar 200 Units, Bosuwa 100 units, Kiri 100 units, M anga-Takwasa 12 units and unguwar Gawo-Bataki-Kuzunzumi- 47 Balarabe 200 units (Total 720 units) Secwave Nigeria Limited State 7,531,315.31 7,531,315.31 7,531,315.31 26/3/2019 4 months 100 Completed

Commissioning as consultant for the supervision of the construction of 48 sada-Kanawa-Dankari-Nasarawa-Kuda Feeder Road (11.2km) UKM Engineering Consult Yankwashi 6,889,699.73 6,889,699.73 6,337,767.06 10/4/2019 6 M onths 100 Completed Rehabilitation of ITC line from Kwanar Gawo to Hago in Kafin Hausa Local 49 Government Area Tasiu M uhammad Invest Ltd K/Hausa 8,333,050.69 8,333,050.69 8,333,050.56 10/7/2019 8 weeks 100 Completed Re-Construction of the damaged sections of Abunabo-Kadira-Guri Road 50 (Phase-III of Eastern Bye Pass) CGC Nig Ltd Guri 50,000,000.00 50,000,000.00 7,936,238.63 15/07/2019 10 weeks 100 Completed Rehabilitation of Karshi-Gagarawar Karshi ITC Line and Extension of Farin Gida TDN in Ringim Local Government Area, Rehabilitation of Yandutse- 51 M alamawar Yandutse ITC in Ringim LGA Almajeed Constr Ltd Ringim 11,391,654.86 11,391,654.86 11,391,654.01 30/07/2019 10 weeks 100 Completed

52 Supply & Installation of Solar streetlight at Emir's Drive, Dutse Arrayyan Global Vent Dutse 17,319,500.00 17,319,500.00 16,563,750.00 31/7/2019 8 weeks 100 Completed

Supply & Installation of Stand alone solar powered streetlight at Government Girls Arabic Secondary School Babura, Government Girls Unity Secondary 53 School Gwaram & Computer Girls Secondary School Roni. Sims Global Res State 60,780,300.00 60,780,300.00 60,767,338.01 31/7/2019 12 weeks 100 Completed Supply and Installations of Integrated Standalone Solar P owered Streetlights at GGASS Sule Tankarkar, GGSSS Taura and Mo del Bo arding P rimary 54 School, Gumel SIMS Nigeria Limited State 75,380,550.00 75,380,550.00 73,185,000.00 11/9/2019 12 weeks 100 Completed

55 Supervis io n o f Gumel to wns hip ro ads Himma Tech. Services Gumel 17,440,289.13 17,440,289.13 17,044,289.12 20/3/2019 8 weeks 100 Completed

56 Supervis io n o f J igawar Dan Ali to wns hip ro ads Akram Eng. Babura 7,484,294.27 7,484,294.27 7,484,294.26 20/3/2019 6 mo nths 100 Completed

57 Co ns t o f Gumel to wns hip ro ads (4.73km) Triacta Nig. Ltd. Gumel 996,587,950.46 996,587,950.46 996,577,850.89 24/12/2018 8 mo nths 100 Completed

Supply and Installations of Integrated stadalone Solar Powered Streetlight at GGASS Birniwa, GGASS Kaugama, Science of Deef 58 Hadejia and JSSS Guri SIMS Global Resources Across the state 77,002,800.00 77,002,800.00 77,002,800.00 15/10/2019 12 weeks 100 Completed

59 Eletrification project of Gwarzon-Garki Alsabur Global Nig Garki 63,635,819.61 63,635,819.61 62,733,544.82 2/10/2019 12 weeks 100 Completed TOTAL 22,441,905,768.07 23,081,690,455.35

Ministry of Education

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

1 Constr. of 1no. Block of w orkshop w ith Standard w ork benchs at GSTC Ringim Marb Eng. & Multi-serv ices Ringim 18,564,893.17 18,564,893.17 18,564,893.17 30/12/2016 6 w eeks 100 Completed

2 Constr. of 1no. Block of tw o (2) Science Laboratories at GSTC Ringim Marb Eng. & Multi-serv ices Ringim 28,487,680.00 28,487,680.00 28,487,680.00 30/12/2016 6 w eeks 100 Completed Construction of Block of 2No. Classroom Islamiya (1No.) 3rd Phase 2017 3 Constituency Projects (Lot-16) at Lautai in Garki Constituency. Jag & H Integ. Serv. Ltd. Garki 3,273,426.45 3,273,426.45 3,115,926.45 6/3/2018 6 weeks 100 Completed Construction of Block of 2No. Classroom Islamiya (3No.) 3rd Phase 2017 Constituency Projects (Lot-7) at Yalwa and Gandum Bundigoma in Malam 4 madori Constituency. Ramadan Constr. Ltd. M/madori 9,180,832.35 9,180,832.35 8,708,332.34 6/3/2018 9 weeks 100 Completed Construction of 1No. Block of 2No. Classroom Islamiya School (1No.) 2nd Phase 2017 Constituency Projects (Lot-11) at Gora maikasuwa in Roni 5 Constituency. Na'ayi Resources Nig. Ltd. Roni 3,272,810.10 3,272,810.10 3,115,310.10 19/3/2018 3 weeks 100 Completed Construction of 1no. Block of 2No. Classroom Islamiya School (1No.) 2nd Phase 2017 Constituency Projects (Lot-16) at GAJSS Jeke Gari in Sule 6 Tankarkar Constituency. Khairussabah Nig. Ltd. S/Tankarkar 3,224,219.90 3,224,219.90 3,078,219.90 6/3/2018 6 weeks 100 Completed Construction of 1no. Block of 6No. Classroom Islamiya School (Upstairs 1No.) 2nd Phase 2017 Constituency Projects (Lot-9) at Tsakuwawa in Miga 7 Constituency. A.G.A. Kilawa Nig. Ltd. Miga 20,735,725.17 20,735,725.17 20,079,272.01 6/3/2018 18 weeks 100 Completed

Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS 8 Amaryawa, Roni LGA (1st phase 2018 projects) (Lot-8) Sabon Garin Yaya Roni 11,734,589.64 11,734,589.64 11649994.83 12/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS 9 Yankwashi (1st phase 2018 projects) (Lot-9) Sabon Garin Yaya Yankwashi 11,734,589.64 11,734,589.64 11,649,994.83 12/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS 10 Sakwaya in Dutse LGA. (Lot-10) Steb by Step Integ. Dutse 11,734,589.64 11,734,589.64 11,618,430.78 16/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS 11 Kwalam in Taura LGA. (Lot-12) Steb by Step Integ. Taura 11,734,589.64 11,734,589.64 11,598,398.71 16/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS 12 Garki (1st phase 2018 projects) Lot-6 Yusma Tech Invest. Garki 11,745,517.16 11,745,517.16 11,660,425.90 12/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms, 1no. Admin. Block at GDSS Doko, GDSS 13 Gunka and GDSS Shuwarin (Lot-13) SUB Gen. Ventures State 70,030,373.82 70,030,373.82 69,711,120.60 16/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms each at at GDSSTsohuwar Gwaram, 14 Birniwa, Maigatari, Guri and Auyo LGA (1st phase 2018 projects) (Lot-14) Sabon Garin Yaya State 46,968,477.85 46,968,477.85 45,989,109.54 12/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS 15 Beguwa, Ringim LGA (1st phase 2018 projects) (Lot-15) Imam Ahmed Nig. Ltd. Ringim 14,089,454.89 14,089,454.89 13,899,800.51 12/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS 16 Gerawa, Ringim LGA (1st phase 2018 projects) (Lot-16) Imam Ahmed Nig. Ltd. Ringim 14,133,338.07 14,133,338.07 13,888,831.16 12/7/2018 6 months 100 Completed

Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS 17 Babaldu in Birnin Kudu LGA (Lot-17) Math Global Ltd. B/Kudu 14,099,561.50 14,099,561.50 13,428,153.82 16/7/2018 6 months 100 Completed BAL. C/F 304,744,668.99 304,744,668.99 4a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 304,744,668.99 304,744,668.99 Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS 18 Takanebu, Miga LGA (1st phase 2018 projects) (Lot-18) Sabon Garin Yaya Miga 14,089,454.89 14,089,454.89 13,936,878.82 12/7/2018 6 months 100 Completed Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS 19 Kwarko in Gwaram LGA (Lot-19) SUB Gen. Ventures Gwaram 14,080,760.93 14,080,760.93 13,859,245.31 16/7/2018 6 months 100 Completed Renov of classrooms blocks, Hostels, Admin block, School Clinic, Toilet, and Constr of wall fence and Gate, Additional 3 courses blocks to Existing wall, Renov of Zonal office and Reticulation of Water at GDSS Kazaure (1st phase 20 2018 projects) (Lot-27) Abdulcom Projects Kazaure 49,732,107.32 49,732,107.32 49,223,609.70 12/7/2018 6 months 100 Completed Development and Improvement on the Grave of the Late Emir of Hadejia, 21 Mallam Muhammadu Sambo at Mairakumi Village of Malam Madori LGA. AGM & Sons Nig. M/Madori 14,426,123.10 14,426,123.10 13,734,855.30 19/7/2018 9 weeks 100 Completed Renov of ICT and Science Laboratories at 4no. Centre of Excellence across the state (Dutse Model Internation School, GUSS Fantai, GUSS Ringim and 22 SSS Lautai). Abdulcom Projects Ringim 32,979,423.69 32,979,423.69 32,001,226.78 21/9/2018 10 weeks 100 Completed Constr. Of 2no. Bore-hole and Pipeline route of Water Supply from 23 Matanfada pump station to (GSS) Roni in Roni. NE Global Eng. Roni 12,400,890.80 16,875,276.80 16,867,411.57 14/9/2017 8 Weeks 100 Completed Construction for the Rehabilitation of Windstorm Damaged Structuresat 24 Science School Lautai in Gumel L.G.A. (phase I) Gerawa Global Engr. Ltd. Gumel 94,507,858.91 94,507,858.91 93,884,336.41 16/10/2018 16 weeks 100 Completed Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-6 at Tashena 25 and Tagwaro in Malam madori Constituency Express Innovation Nig. M/Madori 6,208,148.10 6,208,148.10 5,998,152.30 1/11/2018 6 Weeks 100 Completed Construction of Block of 2-Classroom Islamiyya (5NO.) Lot-18 at Samamiya, Zanga, Waza, Warwade and Rungumawa in Birnin kudu 26 Constituency. Nushe Business Resources B/Kudu 15,574,595.66 15,574,595.66 15,051,170.66 1/11/2018 16 Weeks 100 Completed Construction of Block of 2-Classroom Islamiyya (1NO.) Lot-12 at Unguwar 27 mani in Roni Constituency. Yanduna Ventures Ltd. Roni 3,100,220.00 3,100,220.00 2,995,220.45 1/11/2018 4 Weeks 100 Completed Construction of Block of 2-Classroom Islamiyya (4NO.) Lot-17 at Guru, 28 Wawan rafi, Lokon Rijiya and Hayen Gabas in Kazaure Constituency. Yanduna Ventures Ltd. Kazaure 12,427,116.32 12,427,116.32 12,005,316.33 1/11/2018 15 Weeks 100 Completed Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-15 at Karkarna 29 Town and Magami Fulani in Yankwashi Constituency. Granitoids Engr. Service Ltd. Yankwashi 6,230,701.36 6,230,701.36 6,011,944.91 1/11/2018 6 weeks 100 Completed Construction of (3N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -9) at chilaro, munkawo and kakori 30 sabuwa in Birniwa constituency. Amm Manzo Nig. Ltd Birniwa 9,334,202.22 9,334,202.22 9,019,202.22 23/11/2018 8 weeks 100 Completed Construction of (2N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -15) at Tagwayen fage and Kargo in 31 Garki constituency. MMZ Garki contr. Nig Ltd Garki 6,230,718.16 6,230,718.16 6,020,881.65 23/11/2018 8 weeks 100 Completed Construction of (8N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -4) at Dangan tsaure, Galadanchi, maranjuwa, kargo mahauta, abaya cikin gari mainomi opp. Government 32 House, Gwdige and sabuwar Abuja in Dutse constituency. Backbone global links Dutse 24,921,192.62 24,921,192.62 23,735,124.26 23/11/2018 18 weeks 100 Completed Construction of (8N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -3) at hago, Inkaibo, Hardo Ali, Mezan, 33 kirin Kwatalo, sabon sara and kurunbudi in Bulangu constituency. Kawu Nig Ltd K/Hausa 21,772,100.00 21,772,100.00 21,712,598.35 23/11/2018 16 weeks 100 Completed Construction of (3N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -5) at Sabuwar Gwaram, Unguwar Kudu 34 Jibwis kila and unguwar Gamji in Gwaram constituency. Nushe Bus. Resou. Nig Ltd Gwaram 9,346,064.24 9,346,064.24 8,947,064.23 23/11/2018 10 weeks 100 Completed

BAL. C/F 652,106,347.31 656,580,733.31 4b

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 652,106,347.31 656,580,733.31

Construction of (1N0.) Blocks of 2-classroom Islamiyya school typed 2018 35 phase II constituency projects (Lot -21) at Bila in Taura constituency. Nushe Bus. Resou. Nig Ltd Taura 3,113,183.85 3,113,183.85 3,008,183.85 23/11/2018 8 weeks 100 Completed Construction of (6N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -22) at Gidan Gona Ringim, 36 Karshi,Shangal, Jankawa Yola, and Gasakoli in Ringim constituency. Marb Eng. Multi-serv. Nig. Ltd Ringim 18,662,710.50 18,662,710.50 18,029,888.10 23/11/2018 18 weeks 100 Completed Construction of (6N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -24) at Tsadoji, Filin Danshawai, Gidan shallau, Lokon Dallatu, Gada yamma and Ganguli islamiyya in Kazaure 37 constituency. Yanduna Venture Nig Ltd Kazaure 18,629,958.00 18,629,958.00 17,999,963.10 23/11/2018 18 weeks 100 Completed Construction of (1N0.) Blocks of 2-classroom Islamiyya school typed 2018 38 phase II constituency projects (Lot -6) at Kwatsatsa in Roni constituency. Na'ayi Resources Ltd Roni 3,115,354.00 3,115,354.00 3,006,399.90 23/11/2018 10 weeks 100 Completed Construction of (2N0.) Blocks of 2-classroom Islamiyya sschool typed 2018 phase II constituency projects (Lot -19) at Karkarna in Yankwasi 39 constituency. Granitoids Eng. Nig. Ltd Yankwashi 6,224,045.10 6,224,045.10 6,020,298.10 5/12/2018 8 weeks 100 Completed Construction of (5N0.) Blocks of 2-classroom Islamiyya school atDakwaro, 3No. 2-classroom block at govt. day arabic secondary school basirka and 1No.2-classroom block at digijin (Lot-8) in fagam constituency in gwaram 40 LGA G.M Sara & sons Nig Ltd Gwaram 15,485,650.64 15,485,650.64 14,960,646.75 1/11/2018 4 weeks 100 Completed Construction of (3N0.) Blocks of 2-classroom Islamiyya sschool typed 2018 phase II constituency projects (Lot -13) at chukutu, malumawar 41 taura and gidan ganji in Taura constituency. Nushe Bus. Resou. Nig Ltd Taura 9,347,337.24 9,347,337.24 9,032,337.24 1/11/2018 10 weeks 100 Completed Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-15) at Kwaido, Tsagam, 42 Almajirawa and Majiyawa in Ringim Constituency. Marb Engr. Multi-Services Ringim 12,454,716.33 12,454,716.33 12,034,716.33 18/12/2018 12 weeks 100 Completed Construction of (3 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-8) at Majirga Yanduna, Jamaga and 43 Ganuwa in Miga Constituency. Nabakwai Gen. Enterp. Nig. Ltd. Miga 9,334,202.22 9,334,202.22 9,027,175.50 5/12/2018 8 weeks 100 Completed Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-11A) at Malori and Kuka Dabo in 44 Kirikasamma Constituency. Tosarawa Global Nig. Ltd. Kirikasamma 6,231,558.16 6,231,558.16 6,021,558.16 18/12/2018 10 weeks 100 Completed Construction of (1 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-23) at Kawari in Kiyawa 45 Constituency. Demastbo Ventures Ltd. Kiyawa 3,104,993.80 3,104,993.80 2,999,099.25 17/12/2018 8 weeks 100 Completed Construction of (9 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-25) at Masaya, Zaraina, Tsangaya, Badingu, Dokoki, Ramin kura, Samamiya, Zarainawa and Kura in Birnin 46 kudu Constituency. Nushe Business Resources B/kudu 27,909,116.39 27,909,116.39 26,964,115.92 5/12/2018 20 weeks 100 Completed Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-II) at Diya and Unguwar Malawa 47 in Gwiwa Constituency. Dankaka Intgrated Services Gwiwa 6,225,216.00 6,225,216.00 6,015,219.00 5/12/2018 8 weeks 100 Completed Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-18) at Maitsamiya and 48 Burmanwa in Sule Tankarkar Constituency. Pullad Global Consultant S/tankarkar 6,223,218.34 6,223,218.34 6,014,218.35 5/12/2018 8 weeks 100 Completed BAL. C/F 798,167,607.88 802,641,993.88 4c

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 798,167,607.88 802,641,993.88 Construction of (1 No.) Blocks of 3-Classroom, 1No. 6-Seater Pit Latrine, and Supply of 17No. 3-Seater Desks at GDASS G/Gabas, 1No. Block of 3- Classroom, 1No. 6-Seater Pit Latrine, and 23No. 3-Seater Desks at GDASS 49 Bulangu. Masaka Global Concept Ltd. Various 24,539,884.16 24,539,884.16 24,430,607.74 12/12/2018 8 weeks 100 Completed Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-2) at Majingini and Babban 50 Kambari in Gumel Constituency. Jag & H Intgrated Services Ltd. Gumel 6,230,703.46 6,230,703.46 6,020,716.06 5/12/2018 8 weeks 100 Completed

Construction of (1 No.) Blocks of 3-Classroom, 1No. 6-Seater Pit Latrine, Supply of (38No.) 3-Seater Desks at GDASS Aujara, 1No. Block of 3- Classroom, Construction 1No. 6-Seater Pit Latrine, Supply of 34No. 3-Seater Desks at GDASS Kwalam, Construction of (1No.) Block of 6-Seater Pit Latrine Renovation of 2-Classroom and Supply of (29No.) 3-Seater Desks at GDASS Gwaram, Construction of (1No.) Block of 3-Classroom, 1No. 6-Seater 51 Pit Latrine and Supply of (38No.) 3-Seater Desks at GDASS Marma. Yusmatech Investment Nig. Ltd Across the state 45,687,338.25 45,687,338.25 43,815,809.25 12/12/2018 8 weeks 100 Completed Construction of (1 No.) Blocks of Students Hostel and Supply and 52 Distribution of 100No, Double Bunks Beds at GSTC Birnin kudu. Math Global Investment Ltd. B/kudu 29,140,079.84 29,140,079.84 29,092,645.67 12/12/2018 8 weeks 100 Completed Construction of (1 No.) Blocks of Students Hostel and Supply and Distribution of 100No, Double Bunks Beds at GSSS Kanya Babba, Babura 53 LGA. Sabon Garin 'Yaya Nig. Ltd. Babura 29,140,079.84 29,140,079.84 29,092,645.63 12/12/2018 8 weeks 100 Completed Construction of Teacher Lodge Hostel 2018 Phase II Constituency 54 Projects (Lot-26) at Madachi in Kirikasamma Constituency. K-Manu Gen. Constr & Engr. Kirikasamma 22,461,011.45 22,461,011.45 21,391,439.17 5/12/2018 16 weeks 100 Completed Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed and 2-Classroom Blocks with Head Master Office Subeb Typed (2No) 2018 Phase II Constituency Projects (Lot-14) at Dawar Gada, Malam Aba, 55 Gangara and Dan Barno in Maigatari Constituency. ALLAH Abin Dogara Nig. Ltd. Maigatari 18,855,242.08 18,855,242.08 18,291,543.71 5/12/2018 14 weeks 100 Completed Construction of (3 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-4) at Kwaita, Unguwar Dinya and 56 Computer Girls School Roni in Roni Constituency. Yanduna Ventures Ltd. Roni 23,016,302.00 23,016,302.00 22,149,857.43 18/10/18 10 weeks 100 Completed Construction of (1No.) Blocks of Teacher Lodge 2018 Phase III 57 Constituency Projects (Lot-8B) at Buji in Buji Constituency. Yayarin Tukur Nig. Ltd. Buji 12,701,000.00 12,701,000.00 12,688,611.14 18/10/2018 12 weeks 100 Completed Construction of (1 No.) Blocks of 3-Classroom, and 1No. 6-Seater Pit Latrine each at GDSS Jahun, GDASS Malam madori, GDASS Gagarayaga, GDASS 58 Kondiko, GDASS Roni and GDASS Danmasara Babandoki General Enterprises Across the state 71,225,652.48 71,225,652.48 71,216,726.88 12/12/2018 8 weeks 100 Completed Construction of (3 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-20) at Galadimawa Maje ward, 59 Tunannan Kiyawa ward and Zakwaro Tsirma in Kiyawa Constituency. Step by Step Intergrated Serv Kiyawa 9,346,077.24 9,346,077.24 9,026,037.24 24/12/2018 10 weeks 100 Completed

Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-18) at Dantanoma, Abuja, Garin 60 Barka and Gangara Village in gumel Constituency. Jag & H Integrated Serv. Ltd. Gumel 12,454,716.33 12,454,716.33 12,034,716.33 18/12/2018 12 weeks 100 Completed

BAL. C/F 1,102,965,695.01 1,107,440,081.01 4d

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,102,965,695.01 1,107,440,081.01 Construction of (5 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-8A) at Gantsa kudu, Foto, 61 Gwadayi, Sagu and Y/Chakari in Buji Constituency. Mai-mai Blocks Industry Nig. Buji 15,578,895.41 15,578,895.41 14,935,576.16 18/12/2018 12 weeks 100 Completed Construction of (8 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-4) at Sumangara, Tsahiro, Kafit Gwaram, Innakawa, Tsangaya Sara, Sara kudu, Isawa Maruta and Tsangayar 62 kofar kudu in gwaram Constituency. Nushe Business Resources Gwaram 24,909,432.66 24,909,432.66 24,069,432.66 18/12/2018 15 weeks 100 Completed Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-17) at Kari Tsalle and Majiya 63 Tasha in Taura Constituency. Nushe Business Resources Taura 9,662,035.24 9,662,035.24 9,470,443.73 18/12/2018 10 weeks 100 Completed Construction of (8No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-21) at Dangoli, Yarma, Andazawa, Rungumawa, Zarainawa A., Chandan, Nahuce and Bammowa in 64 Birnin kudu Constituency. NUshe Business Resources B/kudu 24,922,872.66 24,922,872.66 24,090,432.66 18/12/2018 15 weeks 100 Completed Construction of (1No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-6) at Malam Isa Unguwa in 65 Kaugama Constituency. Mai-mai Blocks Industry Nig. Kaugama 3,113,679.08 3,113,679.08 3,010,779.08 18/12/2018 10 weeks 100 Completed Construction of (2No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-1A) at Arawa and Tigima in 66 Auyo Constituency. Mai-mai Blocks Industry Nig. Auyo 6,231,558.16 6,231,558.16 6,021,558.16 18/12/2018 10 weeks 100 Completed Construction of (1No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-9) at Waluwa in Kafin Hausa 67 Constituency. Mai-mai Blocks Industry Nig. K/Hausa 3,117,879.08 3,117,879.08 3,010,779.08 18/12/2018 8 weeks 100 Completed Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-22) at Kilawa, Martaba, Sumiyau 68 and Galambi in Fagam Constituency. Pullad Global Consultant Gwaram 14,367,439.93 14,367,439.93 13,711,431.33 18/12/2018 10 weeks 100 Completed Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-11C) at Diladige and Malorin 69 Baturiya in Kirikasamma Constituency. Nabakwai Gen. Enterprises Kirikasamma 6,230,718.16 6,230,718.16 6,020,718.16 10/12/2018 8 weeks 100 Completed Construction of (1 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-11B) at Madachi in Kirikasamma 70 Constituency. Mai-mai Blocks Industry Nig. Kirikasamma 3,115,354.08 3,115,354.08 3,010,779.08 18/12/2018 8 weeks 100 Completed Construction of (1No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-14) at Yoruba Islamiyya School Hadejia 71 Quarters in Hadejia Constituency. Step by Step Interg. Serv Hadejia 3,115,779.08 3,115,779.08 3,010,779.08 18/12/2018 8 weeks 100 Completed Construction of (4No.) 1-Blocks of 3-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-23) at Karkarna 'A', Karkarna 'B', 72 Karkarna 'C' and Karkarna 'D' in Yankwashi Constituency. Granitoids Engr. Services Yankwashi 34,364,888.00 34,364,888.00 32,923,529.10 18/12/2018 18 weeks 100 Completed Construction of 1-Blocks of 3-Classroom, 1-Block of 6-Seater VIP Pit Latrine 73 and Hand Pump at Tsohuwar Gwaram (Lot-2). Babandoki Gen. Enterp. Gwaram 12,528,665.77 12,528,665.77 12,289,355.25 28/12/2018 3 months 100 Completed Construction of (3No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-16) at Dan Abzin, Tinkishi and Waila 74 Karai in Gwiwa Constituency. Jignaj Global Constr. Ltd. Gwiwa 9,341,037.24 9,341,037.24 9,026,037.24 18/12/2018 10 weeks 100 Completed Construction of 1-Blocks of 3-Classroom, 1-Block of 6-Seater VIP Pit Latrine 75 and Hand Pump at GDSS Kirikasamma (Lot-3). Babandoki Gen. Enterp. Kirikasamma 12,467,040.04 12,467,040.04 12,112,508.77 28/12/2018 3 months 100 Completed BAL. C/F 1,286,032,969.60 1,290,507,355.60 4e

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,286,032,969.60 1,290,507,355.60 Renovation of 2No. Students Hostel, Block of 3-Classes and Computer 76 Laboratory at GSTC Birnin kudu (Lot-9). Masaka Global Concept B/kudu 14,023,833.17 14,023,833.17 13,375,079.21 28/12/2018 3 months 100 Completed 77 Renovation of Classrooms and Hostels at GSS Aujara (Lot-5). Ngaloma Constr. Co. Jahun 79,506,892.39 79,506,892.39 78,002,265.33 28/12/2018 6 months 100 Completed Development of Permanent Site of GGDSS Gagarayaga and GDSS Gawuna 78 (Lot-4). Ngaloma Constr. Co. Gwaram+Hadejia 95,540,000.00 95,540,000.00 93,407,896.69 28/12/2018 6 months 100 Completed Construction of Additional Block of 3-Classrooms each at GDSS Kanti 79 Kazaure and GDSS Bosuwa (Lot-3) Pullad Global Consultant Kazaure+Gagarawa 19,004,045.22 19,004,045.22 18,695,950.58 28/12/2018 3 months 100 Completed Supply and Installation of (63 Units) of Solar Powered System at Various 80 Schools (Lot-2) Sims Nig. Ltd. Across the state 48,238,101.45 48,238,101.45 47,471,547.50 1/11/2018 3 Month 100 Completed Procurement and Renovation of Classes at Jigawa State Academy for the 81 Gifted, Bamaina (Lot-8) Ngaloma Constr. Co. B/Kudu 47,319,728.73 47,319,728.73 45,688,101.46 28/12/2018 3 months 100 Completed Procurement of Science Laboratory equipment and consumables at 82 Dutse Model Int. school (Lot-7) Al-hamsad Invest. Ltd. Dutse 4,587,837.70 4,587,837.70 4,587,837.70 28/12/2018 4 month 100 Completed Procurement and Distribution of 2.520 3-Seater Students Desks to various 83 Senior Secondary Schools across the State (Lot-6) Furni-Elect Global Ventures Across the state 50,373,237.60 50,373,237.60 50,373,237.60 28/12/2018 5 months 100 Completed Supply and Distribution of 640No. 3-Seater Students Desks and Benchs at GDSS Jahun, GGDSS Malam madori, GDSS Gagarayaga, GDSS Kondiko, GGDSS 84 Roni and GDSS Danmasara Furni-Elect Global Ventures Across the state 12,796,800.00 12,796,800.00 12,796,800.00 12/12/2018 8 weeks 100 Completed Procurment of 224 boxer motorcycles for school supervision effectiveness 85 across the state. Babandoki Gen. Entp. Across the state 75,000,000.00 75,000,000.00 75,000,000.00 28/12/2018 8 weeks 100 Completed 86 General Renov of School Structures at GGASS Kaugama (Lot-4) Al-hamsad Invest. Ltd. Kaugama 153,516,678.32 153,516,678.32 153,278,954.44 28/12/2018 8 months 100 Completed Procurement of ICT materials/Equipments for 3-centres of excellence (Lot- 87 6) Al-hamsad Invest. Ltd. Across the state 41,452,175.00 41,452,175.00 41,452,175.00 28/12/2018 3 months 100 Completed 88 Procurement of School uniforms, Sendels and Bags to Nomadic Schools. Muhib Global State 29,880,000.00 29,880,000.00 29,880,000.00 19/12/18 12 weeks 100 Completed Procurement of instructional materials to Schools at basic levels across 89 the state. Babandoki Gen. Entp. State 62,319,731.25 62,319,731.25 62,319,731.25 28/12/18 12 weeks 100 Completed Constr of Upstars Classroom Islamiyya type (1no.) Block of 2classrooms Alh. Umaru Babandoki Nig. 90 (2018 phase II) constituency project (Lot-17) at Harazimiyya in Hadejia Ltd. Hadejia 15,011,567.54 15,011,567.54 14,889,338.36 5/12/2018 14 weeks 100 Completed P rinting of 2019 Basic Education certificate examination (BECE) question papers with 91 ans wer s heets fo r J SS Acro s s the State Clear Impres s io ns Ltd State 15,260,680.05 15,260,680.05 15,260,680.05 13/6/2019 8 weeks 100 Completed 92 Re-co ns tructio n o f fallen wall fence at GGUSS Garki and GUSS M/Mado ri P ullad Glo bal Co ns ult State 9,039,035.07 9,039,035.07 8,908,113.11 10/7/22019 8 weeks 100 Completed Renovation of Storm damages at 7no. Schools across the state : GGASS S/Tankarkar, GUSS maigatari, GDSS Shagari Qtrs . Hadejia, GSS Aujara, GDSS Buji, 93 GGDSS Birnin Kudu and Dutse Model Int School. AGM & So ns Nig State 23,498,908.59 23,498,908.59 23,490,970.35 15/8/2019 8 weeks 100 Completed Renovation of storm damages at GDASS Dantanoma in Gumel LGA, School of Arabic and Islamic Studies (SAIS) Hadejia, GDASS Zainab Kazaure, GDASS Dabi in 94 Ringim, GDASS Gwaram and GGASS Danzomo in Gagarawa LGA P ullad Glo bal Co ns ult State 53,582,692.89 53,582,692.89 53,299,656.22 16/8/2019 16 weeks 100 Completed Supply and Installation of 52No. Standalone Solar Integrated Streetlight (P hase-II) at 95 the J igawa State Co llege o f Islamic & Legal Studies Ringim Sims Global Resources Ringim 32,215,050.00 32,215,050.00 3/5/2019 4 weeks Supply and Distribution of Science text Books and Teachers Guide for Senior 96 Secondary Schools Across the State Learn Africa Plc State 49,949,800.00 49,949,800.00 49,949,800.00 11/7/2019 6 weeeks 100 Completed

Procurement and Sewing of 30,000 sets of School Uniforms to Senir Secondary 97 Schools acros the state 313 Textile Nig Ltd. State 79,980,000.00 79,980,000.00 79,980,000.00 3/9/2019 12 weeks 100 Completed

98 Renov of Dining Hall at GGASS Babura Sabon garin Yaya Ltd. Babura 20,866,366.64 20,866,366.64 20,859,565.28 28/12/2018 8 weeks 100 Completed BAL. C/F 2,318,996,131.21 2,323,470,517.21 4f

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 2,318,996,131.21 2,323,470,517.21 Constr of 3no. Blocks of 2classroom Islamiyya School type (2018 phase III) 99 constituency project (Lot 19) at Fulanin Kurfi, Kuka kofar gari, Kantudu in Yanduna Ventures Kazaure 9,346,077.24 9,346,077.24 9,346,077.24 18/12/2018 12 weeks 100 Completed Constr of additional 3classrooms block each at GDSS Ringim Areawa, GDSS 100 Baura (Lot-1) Pullad Global Consult Ringim + Babura 19,004,045.22 19,004,045.22 17,305,017.20 28/12/2018 3 months 100 Completed Constr of 1no. Block of 3-classrooms each at GDSS Babura, GDSS Galagamma Gumel, GDSS babaldu and GDSS Ringim Areawa (2019 Capital 101 projects) Babandoki Gen Entp. state 44,808,022.00 44,808,022.00 44,225,690.58 3/10/2019 12 weeks 100 Completed Renov of Science and ICT Labs. at 9no. Proposed Science Centres of Excellence core 2 (GGUSS M/madori, GDSS G/Gabas, GGSS Garki, GDSS Gwiwa, GUSS Aujara, GUSS Maigatari, GDSS T/Gwaram, GC Birnin Kudu and 102 GUSS Basirka) AGM & Sons Nig Ltd. state 24,140,000.00 24,140,000.00 24,034,905.66 25/09/2019 12 weeks 100 Completed Constr of 1no. Block of 3-classrooms each at 8no. GDSS across the state 103 (2019 Capital Projects) Math Global Invest. Ltd. Across the state 90,089,432.00 90,089,432.00 87,675,689.47 28/10/2019 12 weeks 100 Completed Construction of 1No Block of 3 classrooms each at GDASS Kiri Kasamma GDASS Bulangu GDASS Miga GDASS Kiri Kasamma GDASS Bulangu GDASS 104 Miga, GDASS Marma, GDASS Limawa , GDASS Birniwa and GDASS Aujara A.A. Maikatako Gen Entr Aujara 78,414,000.00 78,414,000.00 74,680,037.57 14/11/2019 20 weeks 100 Completed Procurment of Medical Drugs, ICT and Sicbay Equipment for Jigawa 105 Academy for the Gifted, Bamaina IMAM Ahmed Nig Ltd. B/kudu 4,639,345.25 4,639,345.25 4,639,345.25 16/10/2019 2 weeks 100 Completed Construction of Additional Block of 3-Classrooms each at GDSS Galagamma 106 Gumel and GGDSS Hadejia (Lot-2) Pullad Global Consultant Gumel + Hadejia 19,004,045.22 19,004,045.22 18,695,950.58 28/12/2018 3 months 100 Completed Construction of (4No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-12) at Batali, Insharuwa, Bakar Kuka 107 and Masko in Babura Constituency. Mufabamex Concept Nig. Ltd. Babura 12,444,222.00 12,444,222.00 12,024,222.00 5/12/2018 12 weeks 100 Completed Procurement of 7.500No Furniture Sets to Primary Schools 4-6 Pupil (1st & 2nd Quarter 2018 UBEC/SUBEB Intervention Project) Lot-32 across the 108 State. Furni-Elect Global Ventures Across the state 119,749,935.00 119,749,935.00 119,749,935.00 18/12/2018 16 weeks 100 Completed TOTAL 2,740,635,255.14 2,745,109,641.14 4g

Ministry of Land

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT (N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Construction of 1No. Block of 4No. House of 2No. Bedroom 1 Semi-Detach at Kazaure Local Government Area Al-Sabur Global Links Kazaure 10,779,821.20 10,779,821.20 10,289,698.65 19/3/2019 14 Weeks 100 Completed

Construction of 1No Block of 4No House of 2No Bedroom Semi- 2 Detach (Lot-6) at Hadejia Local government Area Ngaloma Construction Hadejia 10,719,537.18 10,719,537.18 10,673,330.85 19/3/2019 14 Weeks 100 Completed

Construction of 1No Block of 4No House of 2No Bedroom Semi- 3 Detach (Lot-9) at Malam Madori Local government Area Ngaloma Construction M/Madori 10,719,854.25 10,719,854.25 10,673,330.85 19/3/2019 14 Weeks 100 Completed

Constr of 1no. Block of 4no. House of 2no. Bedrooms semi detached 4 (Lot-3) at Birniw a LGA MWT Real Estate & Gen Entp. Birniw a 10,424,245.65 10,424,245.65 10,420,295.55 19/3/2019 14 Weeks 100 Completed

Constr of 1no. Block of 4no. House of 2no. Bedrooms semi detached at 5 Jahun LGA Nushe Business Jahun 10,691,491.65 10,691,491.65 10,606,901.55 19/3/2019 14 Weeks 100 Completed TOTAL 53,334,949.93 53,334,949.93

Ministry of Commerce

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS (N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

1 Renov of 4no. Structures at EPZ Maigatari AMIA Int. Ltd. Maigatari 12,738,100.79 12,758,100.79 12,738,095.56 28/10/2019 2 months 100 Completed

Total 12,738,100.79 12,758,100.79

Dutse Capital Development Athority

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 ProvConstr. ision of &New Installation High Brow of Streetlights lay out in Dutse at the 3 Arms zone, Ibrahim Aliy u Dantata & Sawoe Dutse 3,822,690,275.89 5,073,417,718.02 4,577,814,987.09 14/10/2011 48 w eeks 83 Completed Eastern By e-pass and Old Police Hqrs. To Gadadin-Fanisau Link road, 2 Dutse. Dantata & Sawoe Dutse 1,064,545,077.91 1,267,613,083.02 1,058,862,394.59 8/11/2012 12 w eeks 100 Completed Consultant for the Constr. Of 30N0. Houses for Jigawa State members of 3 the House of Assembly at Disina HAG Eng. Nig. Limited Dutse 131,922,214.60 147,301,384.74 147,146,095.43 11/7/2012 14 months 100 Completed 4 Cconstr of Wall Fence & land Scaping to 30no. Houses Afdin Constr. Ltd. Dutse 315,291,242.77 315,291,242.77 291,248,714.33 7/5/2015 6 months 100 Completed

TOTAL 5,334,448,811.17 6,803,623,428.55

Cabinet Office

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

A M OUN T (N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Constr. of Juma'at Prayer Mosque at Galambi, fagam 1 Constituency in Gwaram LGA. Ramadan Constr. Nig. Ltd. Gwaram 26,396,975.14 26,396,975.14 25,831,669.29 24/01/2017 16 weeks 100 Completed Constr. of five (5) Daily prayer Mosques at Gidan Mutari Fulanin Harbo, Danmodi Gari and Hammado in Sule 2 Tankarkar Constituency. Manhaf Global Ventures S/Tankarkar 6,543,114.75 6,543,114.75 6,352,538.59 16/10/2017 6 weeks 100 Completed Constr. of Friday prayer mosque at Gada yamma and 3no. Daily prayer mosques at Gada Rumawa, Sabaru Fanda and 3 Gada Gabas in Kazaure Constituency. Yanduna Ventures Kazaure 53,061,271.36 53,061,271.36 52,346,684.20 25/10/2017 12 Weeks 100 Completed Interlocking Tiles and External Works of (1No.) Friday Prayer M osque ( 2018 Phase II) Constituency Projects (Lot-44) at Garki Central 4 M osque in Garki Constituency M M Z Garki Construction Garki 7,642,374.33 7,642,374.33 7,280,614.74 31/12/2018 8 weeks 100 Completed Constr. of Friday Prayer Mosques at Nasarawa in Gumel 5 Constituency. JAG & H Integrated Serv. Ltd. Gumel 15,046,340.35 15,046,340.35 15,001,060.45 16/10/2017 12 weeks 100 Completed Construction of Five (5) daily Prayer Mosques at Wutsadaand 6 Kankare Fulani in Gagarawa Constituency. Al-Nasibi Gen. Intp. Gagarawa 4,129,061.98 4,129,061.98 3,932,439.98 18/12/2017 4 Weeks 100 Completed Constr of (3no.) Five Daily prayer mosques (2018 phase III) Constituency projects (Lot-11) at Wasari, Yanusori and Goyi 7 in Bulangu Constituency Kawu Nig Ltd. K/Hausa 5,868,833.55 5,868,833.55 5,780,776.24 23/11/2018 12 Weeks 100 Completed Construction of Five (5) daily Prayer Mosques at Garbagar Gari (Garbagai Ward), Wareri (Guri Ward), Zoriyo (Adiyani Ward), Jauron Kadira (Kadira Ward) and Dolewa (Kadira 8 Ward) in Guri Constituency. Alh Umar Baban Doki Nig Ltd Guri 10,322,654.95 10,322,654.95 10,322,654.94 18/12/2017 8 Weeks 100 Completed Construction of Five (5) daily Prayer Mosques at mazazzaga (Garko Ward) and Balago Town Balago Ward) in Kiyawa 9 Constituency. Demastbo Ventures Ltd. Kiyawa 4,129,061.98 4,129,061.98 3,932,439.98 18/12/2017 6 Weeks 100 Completed Construction of (3No. Friday Prayer Mosques (2018 Phase II) Constituency Projects ( Lot-40) at Zangin Kanya, Waloyi 10 Sabuwa and Tsangaiwa in Bulangu Constituency Kawu Nigeria Ltd Kafin Hausa 16,888,035.21 16,888,035.21 16,797,853.54 23/11/2018 12 Weeks 100 Completed Completion/renovation of Juma'at Prayer Mosques at Jibwis 11 Garki in Garki Constituency. Jag & H Intgrt Services Ltd Garki 23,736,083.26 23,736,083.26 23,423,788.50 18/12/2017 12 Weeks 100 Completed Construction of (3No) Five Daily Prayer Mosques at Kukuma Kudu (Kumuma Ward), Dakori (Gantsa Ward) and Falgeri 12 Arewa ( Falgeri Ward) in Buji Constituency A+-TECH INTEG Buji 6,193,592.97 6,193,592.97 5,898,659.98 1/19/2018 8 weeks 100 Completed Constr of 2no. Five daily prayer mosques 2017 constituency projects phase III remaining works (lot-3) at Mahudi 13 Tsangaya and Jingino in Fagam Constituency, Gwaram LGA. G.M. Sara & Sons Ltd. Gwaram 4,129,061.98 4,129,061.98 3,932,439.98 16/4/2018 6 weeks 100 Completed Balance C/F 184,086,461.81 184,086,461.81 8a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 184,086,461.81 184,086,461.81 Constr of Juma'at Prayer mosques 2017 constituency projects phase III remaining works (Lot-7) at Kiri-kasamma Gari in 14 Kirikasamma Constituency. Alh Umaru Babandoki K/Kasamma 17,176,291.17 17,176,291.17 17,130,145.55 16/4/2018 12 weeks 100 Completed Constr /Renovation/Completion of prayer mosques 2017 Constituency projects phase III Remaining works (Lot-4) at 15 Galambi Central mosque in Fagam Constituency, Gwaram LGA. Ramadan Constr Ltd. Gwaram 16,011,630.21 16,011,630.21 15,249,171.63 16/4/2018 12 weeks 100 Completed Renovation/Completion of Juma'at prayer mosques 2017 Constituency projects phase III Remaining works (Lot-8) at 16 Maje in Taura Constituency. Nushe Business Resources Taura 9,001,562.13 11,793,398.14 10,940,373.12 16/4/2018 12 weeks 100 Completed Constr of (6no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-5) at Nera, Lauya, Shantake, Kurtulla, Haladawa 17 and G/Ganji in Kanya Babba Constituency, Babura LGA. Deetech Nig. Ltd. Babura 11,455,254.00 11,455,254.00 10,784,277.06 10/10/2018 6 weeks 100 Completed Constr of (2no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-15) at Gadewa and Bayan Lambu in Jahun 18 Constituency. Yanduna Ventures Jahun 3,788,985.90 3,788,985.90 3,746,645.70 10/10/2018 6 weeks 100 Completed Constr of (5no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-22) at Bodayal, Belas, K/chiroma, Todariya and 19 Tsedau in Kazaure Constituency. Yanduna Ventures Kazaure 9,745,359.75 9,745,359.75 9,269,646.75 10/10/2018 6 weeks 100 Completed

Constr of (1no.) five Daily Prayer Mosques 2018 Constituency 20 Projects (Lot-2) at Mata kuwa in Auyo Constituency. Step by Step Integ. Auyo 1,952,627.20 1,952,627.20 1,870,570.63 10/10/2018 6 weeks 100 Completed

Constr of (1no.) five Daily Prayer Mosques 2018 Constituency 21 Projects (Lot-28) at Bula Sure in Roni Constituency. Na'ayi Resources Ltd. Roni 1,943,923.00 1,943,923.00 1,853,929.35 10/10/2018 6 weeks 100 Completed Constr of (5no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-6) at Bulunkuce, Kangire, Kantoga T., Gorrawa 22 and Tosoro in B/kudu Constituency. Nushe Bus. Resources B/kudu 9,559,735.50 9,559,735.50 9,139,735.50 10/10/2018 6 weeks 100 Completed Constr of (5no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-7) at Dukana, U/Galadima, Shungurun, Iggi and 23 Gogoriya in Birnin Kudu Constituency. Nushe Bus. Resources B/Kudu 9,795,123.50 9,795,123.50 9,375,123.50 10/10/2018 6 weeks 100 Completed Constr of (4no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-24) at Talaku, Janiskifeta, Janiskitagwaro and 24 Kashin Dila in Malam Madori Constituency. Express Innovation Concept M/Madori 7,732,082.04 7,732,082.04 7,363,887.63 10/10/2018 6 weeks 100 Completed Constr of (3no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-19) at Nasarawa, Dubantu and Walawa Matsaro 25 in Hadejia Constituency. Alh. Umaru Babandoki Hadejia 5,735,858.70 5,735,858.70 10/10/2018 6 weeks On-going Balance C/F 287,984,894.91 290,776,730.92 8b

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 287,984,894.91 290,776,730.92 Constr of (3no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-23B) at G/Hadau, D/Talle and D/Takore in 26 Maigatari Constituency. Modang Investment Ltd. Maigatari 5,756,502.15 5,756,502.15 5,754,438.69 10/10/2018 6 weeks 100 Completed Construction of (1NO.) five Daily Prayer Mosques 2018 Constituency Projects at Laya in Fagam Constituency, 27 Gwaram Local Government Area. Ramadan Constrt. Nig. Ltd. Gwaram 7,307,084.41 7,307,084.41 6,959,128.00 14/11/2018 8 weeks 100 Completed Construction of (3NO.) five Daily Prayer Mosques (2018 Phase II) Constituency Projects (Lot-12) at Gonga Yamma, Kakibare 28 and Jingi Town in Dutse Constituency. Al-Kassam Jannah Nig. Ltd. Dutse 5,881,500.02 5,881,500.02 5,846,768.55 23/11/2018 8 weeks 100 Completed Construction of (3NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-8) at Tsangayar Kuka, Dagaceri 29 Kukawa and Goguwa Kandawa in Birniwa Constituency. Amm Manzo Nig. Ltd. Birniwa 5,830,306.65 5,830,306.65 5,578,306.65 14/11/2018 8 weeks 100 Completed Construction of (1NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-1) at Kajilmaran in Auyo 30 Constituency. Amm Manzo Nig. Ltd. Auyo 1,943,435.55 1,943,435.55 1,859,435.55 14/11/2018 8 weeks 100 Completed Construction of Five (5) daily Prayer Mosques at Sabuawar Kaura, Kiyako, Birnin kudu, Samamiya and Bigidan in Birnin 31 Kudu Constituency. Nushe Business Resources B/kudu 10,322,654.95 10,322,654.95 9,831,099.96 18/12/2017 8 Weeks 100 Completed Construction of Juma'at Prayer Mosques at Garin Mado in 32 Gagarawa Constituency. Modang Investment Ltd. Gagarawa 9,527,340.25 9,527,340.25 6,914,922.90 18/12/2017 12 Weeks 100 Completed Construction of (3NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-31) at Rauda L/Dutse, Karkarna 33 "A" and new Achilafiya in Yankwashi Constituency. Granitoids Engr. Service Ltd. Yankwashi 5,834,168.55 5,834,168.55 5,582,168.55 14/11/2018 8 weeks 100 Completed Construction of (4NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-10) at Basirka Taya, Basirka S/Fawa, Ruwa Kari and Basirka Karofi in Fagam Constituency, 34 Gwaram Local Government Area. Ramadan Constrt. Nig. Ltd. Gwaram 7,754,111.40 7,754,111.40 7,418,111.40 14/11/2018 8 weeks 100 Completed Completion/Renovation of (1NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-4) at Faru M/Taya in Babura 35 Constituency. Danfatu & Sons Nig. Ltd. Babura 1,931,522.85 1,931,522.85 1,815,157.71 26/12/2018 8 weeks 100 Completed

Construction of (1NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-3) at Gandun Kadir in Auyo 36 Constituency. Wajedu Nig. Ltd. Auyo 1,951,976.50 1,951,976.50 1,867,976.50 14/11/2018 8 weeks 100 Completed

Balance C/F 352,025,498.19 354,817,334.20 8c

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 352,025,498.19 354,817,334.20 Construction of (2NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-21) at Maragwado and Jama'ar 37 Jiyan in Kirikasamma Constituency. Naila Multiservices Venture K/kasamma 3,922,645.70 3,922,645.70 3,910,445.70 14/11/2018 8 weeks 100 Completed Construction of (3NO.) five Daily Prayer Mosques 2018 Constituency Projects at Kaugama S/Gari, Taura Jarkasa and 38 Daurawa in Taura Constituency. Nushe Business Resources Taura 5,853,062.00 5,853,062.00 5,632,568.55 14/11/2018 6 weeks 100 Completed Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects at Gusau Quarters in Gumel 39 Constituency. Jag&H Integrated Services Ltd Gumel 4,875,157.22 4,875,157.22 4,643,096.85 14/11/2018 8 weeks 100 Completed Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-40) at Mele in Gumel 40 Constituency. Jag&H Integrated Services Ltd Gumel 11,823,386.40 11,823,386.40 11,658,501.75 14/11/2018 8 weeks 100 Completed Completion/Renovation of (2NO.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-41) at Dantawuya 41 and Maja B/Jeji Towns in Dutse Constituency. Al-kasam Jannah Nig. Ltd. Dutse 20,177,486.34 20,177,486.34 20,221,586.34 23/11/2018 8 weeks 100 Completed Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-66) at Tsangaiwa in Miga 42 Constituency. Amia Integ. Service Nig Ltd. Miga 11,869,289.26 11,869,289.26 11,845,989.25 14/11/2018 8 weeks 100 Completed Construction of Five (5) daily Prayer Mosques at mazazzaga (Garko Ward) and Balago Town Balago Ward) in Kiyawa 43 Constituency. Demastbo Ventures Ltd. Kiyawa 4,129,061.98 4,129,061.98 3,932,439.98 18/12/2017 6 Weeks 100 Completed Construction of Five (5) daily Prayer Mosques at Jemawa, Sansami, Muna fadi and Construction of Juma'at Prayer Mosque at Kanya Town in Kanya Babba Constituency of 44 Babura Local Govt Area. Deetech Nig. Ltd. Babura 16,304,386.14 16,304,386.14 16,009,453.15 18/12/2017 12 Weeks 100 Completed Construction of Five (5) daily Prayer Mosques at Mirgina, Danbuwayi, Zuge, UnguwarKiwo, Dan Goriba and Construction of Juma'at Prayer Mosque at Danbanki in Sule 45 Tankarkar Constituency. Bulangu Drilling Services S/tankarkar 22,536,624.84 22,536,624.84 21,463,452.24 18/12/2017 12 Weeks 100 Completed Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 46 Constituency Projects (Lot-54) at UZA in Auyo Constituency. Muhal Global Concept Ltd. Auyo 2,276,676.25 2,276,676.25 2,168,263.10 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-35) at Yalwa Dawai Village in 47 Birnin kudu Constituency. Nushe Business Resources B/kudu 7,300,090.20 7,300,090.20 7,037,590.20 14/11/2018 12 weeks 100 Completed

Balance C/F 463,093,364.52 465,885,200.53 8d

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 463,093,364.52 465,885,200.53 Completion/Renovation of (3NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-59) at Yarfi, Sharifori and Digijin 48 Village in Fagam Constituency, Gwaram L.G.A. G.M. Sara & Sons Ltd. Gwaram 5,203,805.88 5,203,805.88 5,003,624.64 14/11/2018 8 weeks 100 Completed

Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-47B) at Likori in Kirikasamma 49 Constituency. Tosarawa Global Nig. Ltd. Kirikasamma 5,005,071.05 5,005,071.05 5,005,071.05 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-51) at Jibwis Sule Tankarkar in 50 Completion/RenovationSule Tankarkar Constituency. of (1NO.) Friday Prayer Mosque 2018 Lautai Genaral Investment S/Tankarkar 7,960,852.75 7,960,852.75 7,610,355.95 14/11/2018 8 weeks 100 Completed Constituency Projects at K/Fada in Sule Tankarkar 51 Constituency. Lautai Genaral Investment S/Tankarkar 6,506,264.97 6,506,264.97 6,414,745.17 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 52 Constituency Projects at Bebeji in Buji Constituency. Yayarin Tukur Nig. Ltd. Buji 8,267,235.04 8,267,235.04 7,873,557.18 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-45) at Wiwi in Kafin Hausa 53 Constituency. Danfatu & Sons Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 3,996,672.01 14/11/2018 8 weeks 100 Completed Completion/Renovation of (3NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-67) at Nisan Marke, Shafar and 54 Gidan K/H Ari in Ringim Constituency. Madanta Global Nig. Ltd. Ringim 16,816,456.06 16,816,456.06 16,709,406.06 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects at Sarkin Dare in Gagarawa 55 Constituency. Amm Manzo Nig. Ltd. Gagarawa 10,561,294.91 10,561,294.91 10,058,376.11 14/11/2018 8 weeks 100 Completed Completion/Renovation of (5NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-63) at Majerinzan Goma, Matakur, 56 Kutugum, Aduwa and D/Kyaure in Kafin Hausa Constituency. Amm Manzo Nig. Ltd. K/Hausa 16,853,819.38 16,853,819.38 13,140,583.66 14/11/2018 8 weeks 100 Completed

Construction of (1NO.) Friday Prayer Mosque 2018 57 Constituency Projects at Jikas in Gwaram Constituency. Amm Manzo Nig. Ltd. Gwaram 14,523,958.83 14,523,958.83 14,463,706.74 14/11/2018 8 weeks 100 Completed

Construction of (1NO.) Friday Prayer Mosque 2018 58 Constituency Projects at Girbobo in Kaugama Constituency. Amm Manzo Nig. Ltd. Kaugama 10,069,325.22 10,069,325.22 10,069,325.21 14/11/2018 8 weeks 100 Completed

Completion/Renovation of (5NO.) Friday Prayer Mosque 2018 Constituency Projects at Takwasa, Batali, Babura Central, 59 Jigawar Dan Ali and Babura Jibwis in Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 11,560,530.17 11,560,530.17 11,010,028.73 19/11/2018 8 weeks 100 Completed

Balance C/F 580,418,650.80 583,210,486.81 8e

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 580,418,650.80 583,210,486.81 Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-65) at Askandu in Kaugama 60 Constituency. Amm Manzo Nig. Ltd. Kaugama 6,219,763.56 6,219,763.56 6,020,579.08 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-53) at Sabuwa Village in 61 Yankwashi Constituency. Granitoids Engr. Service Ltd. Yankwashi 12,195,580.26 12,195,580.26 12,164,242.52 14/11/2018 12 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-32) at Gamsarka in Auyo 62 Constituency. Muhal Global Concept Ltd. Auyo 7,026,996.02 7,026,996.02 6,692,377.15 24/12/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects at K/Fada Sara in Gwaram 63 Constituency. Alh. Umaru Baban Doki Gwaram 15,941,139.39 15,941,139.39 15,925,657.32 31/12/2018 8 weeks 100 Completed Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-99) at Yan Makada in Kazaure 64 Constituency. Karami Constr. Co. Kazaure 18,118,618.22 18,118,618.22 17,255,827.82 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-37) at Nasarawan Kigudu in Fagam 65 Constituency Gwaram L.G.A. Sukudai Construction Nig. Ltd. Gwaram 7,274,348.35 7,274,348.35 7,259,747.80 14/11/2018 8 weeks 100 Completed Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-64) at Kaugama Town in Kaugama 66 Constituency. Nabakwai General Entp. Kaugama 17,890,045.00 17,890,045.00 17,780,488.09 14/11/2018 8 weeks 100 Completed

Completion/Renovation of (3NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-58) at Jibwis Kondiko, Dangulani 67 and Kijin Village in Fagam Constituency, Gwaram L.G.A. G.M. Sara & Sons Ltd. Gwaram 8,371,896.23 8,371,896.23 8,021,154.15 14/11/2018 8 weeks 100 Completed Construction of (1NO.) Friday Prayer Mosque 2018 Constituency Projects at Makerabu Village in Gagarawa 68 Constituency. Modang Investment Ltd. Gagarawa 10,561,294.91 10,561,294.91 10,058,376.10 14/11/2018 8 weeks 100 Completed Fencing of Kafin Hausa Jibwis Friday Prayer Mosque 2018 69 Constituency Projects (Lot-62) in Kafin Hausa Constituency. Faahm Intgrated Resources K/Hausa 2,403,328.04 2,403,328.04 1,998,822.04 14/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-57) at Dansure in Roni 70 Constituency. Na'ayi Resources Nig. Ltd. Roni 4,550,100.85 4,550,100.85 4,550,100.85 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-...) at Kadama in Roni 71 Constituency. Na'ayi Resources Nig. Ltd. Roni 9,527,340.25 9,527,340.25 9,317,340.24 23/11/2018 8 weeks 100 Completed Balance C/F 700,499,101.88 703,290,937.89 8f

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 700,499,101.88 703,290,937.89 Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-...) at Kwanar Yarshara in Roni 72 Constituency. Na'ayi Resources Nig. Ltd. Roni 9,527,340.25 9,527,340.25 9,317,340.24 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-69) at Bashe and Amaryawa 73 Towns in Roni Constituency. Na'ayi Resources Nig. Ltd. Roni 13,161,630.65 13,161,630.65 12,534,886.32 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-47) at Dinya Wayakawoka in 74 Jahun Constituency. Khairussabah Nig. Ltd. Jahun 4,411,465.20 4,411,465.20 4,201,395.42 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-45) at Kulawa mai Kasuwa 75 Gauza in Jahun Constituency. Khairussabah Nig. Ltd. Jahun 9,942,198.00 9,942,198.00 9,937,789.05 24/12/18 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-71) at Sabon Garin Yaya in 76 Taura Constituency. ALLAH Abin Dogara Nig. Ltd. Taura 19,681,939.15 19,681,939.15 19,622,234.31 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-43A) at Nasarawa Jibwis in 77 Gumel Constituency. Farham Synergy Concept Ltd. Gumel 15,210,520.70 15,210,520.70 15,155,375.19 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-50) at Gareru in Kaugama 78 Constituency. Danfatu & Sons Nig. Ltd. Kaugama 8,120,321.42 8,120,321.42 7,733,639.44 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-68) at Garun Gabas in Malam 79 madori Constituency. Step By Step intgrated Servic M/madori 15,819,389.40 15,819,389.40 15,766,085.13 23/11/2018 8 weeks 100 Completed Completion/Renov. Of (2 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-66) at Yalo and 80 Yanleman/Dakayyawa in Kaugama Constituency. Danfatu & Sons Nig. Ltd. Kaugama 12,471,560.90 12,471,560.90 11,949,935.26 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-54) at Garin Makera in Ringim 81 Constituency. Marb Engr. Multi-Services Ringim 8,142,760.20 8,142,760.20 8,121,760.19 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-53) at Yanduna in Ringim 82 Constituency. Marb Engr. Multi-Services Ringim 8,157,650.70 8,157,650.70 8,135,226.36 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-44) at Kundiga in Gwiwa 83 Constituency. Jignaj Global Constructions Gwiwa 14,802,529.09 14,802,529.09 14,765,972.55 23/11/2018 8 weeks 100 Completed Balance C/F 839,948,407.54 842,740,243.55 8g

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 839,948,407.54 842,740,243.55 Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-...) at Yelwa in Buji 84 Constituency. Yayarin Tukur Nig. Ltd. Buji 12,518,061.42 12,518,061.42 11,921,962.85 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-38) at Dagilfani in Birniwa 85 Constituency. AMM Manzo Nig. Ltd. Birniwa 10,900,793.17 10,900,793.17 10,133,120.74 29/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-51) at Ubba in Kaugama 86 Constituency. Danfatu & Sons Nig. Ltd. Kaugama 8,110,126.52 8,110,126.52 7,723,931.07 23/11/2018 8 weeks 100 Completed Construction of the (2No.) Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-31) at Gajin Gebi and 87 Margawa in Ringim Constituency. Marb Engr. Multi-Services Ringim 3,923,039.40 3,923,039.40 3,755,039.40 23/11/2018 6 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-53) at Yandutse in Ringim 88 Constituency. Marb Engr. Multi-Services Ringim 8,157,650.70 8,157,650.70 8,135,226.36 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects at Kwantamawa in Kafin Hausa 89 Constituency. Mugin Investment Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 3,989,065.98 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects at G/Kanya in Kafin Hausa 90 Constituency. Mugin Investment Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 3,989,065.98 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase 91 III) Constituency Projects at Zarga in Taura Constituency. Dankwara Maijimina Invest. Taura 8,373,590.40 8,373,590.40 8,373,590.40 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects at Wurma Town in Dutse 92 Constituency. H.M. Dangara Ltd. Dutse 2,401,479.28 2,401,479.28 2,316,649.70 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects at Matara Babba in Birniwa 93 Constituency. AMM Manzo Nig. Ltd. Birniwa 10,100,873.67 10,100,873.67 10,060,866.90 29/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase 94 III) Constituency Projects at Rabadi in Fagam Constituency. Ramadan Construction Ltd. Gwaram 8,167,025.88 8,167,025.88 7,778,119.88 23/11/2018 8 weeks 100 Completed

Construction of the (1 No.) Friday Prayer Mosque (2018 Phase 95 III) Constituency Projects at Ganji in Fagam Constituency. Ahmad Maidoya & Sons Gwaram 4,001,112.00 4,001,112.00 3,810,582.85 23/11/2018 8 weeks 100 Completed

Balance C/F 924,595,504.02 927,387,340.03 8h

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 924,595,504.02 927,387,340.03 Completion/Renovation of (3 No.) Friday Prayer Mosques 2018 Constituency Projects (Lot-67) at Nisan Marke, Shafar 96 and Gidan K/H Ari in Ringim Constituency. Madanta Global Nig. Ltd. Ringim 16,816,456.06 16,816,456.06 16,709,406.06 14/11/2018 8 weeks 100 Completed Completion/Renovation of (6 No.) Friday Prayer Mosques 2018 Constituency Projects at Sugungun, Kanya, Gwarzo, 97 Zaidawa, G/Maza and Kargo in Garki Constituency. MMZ Garki Construction Nig. Garki 27,784,329.15 27,784,329.15 26,734,547.76 14/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-49) at Romawa village in Miga 98 Constituency. Amia Integ. Service Nig Ltd. Miga 10,169,831.21 10,169,831.21 10,162,921.57 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-52) at Akasan in Taura 99 Constituency. Dankwara Maijimina Invest. Taura 8,219,582.90 8,219,582.90 8,177,082.90 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-57) at Meden Laban in 100 Gagarawa Constituency. Essence World Wide Service Gagarawa 8,229,020.55 8,229,020.55 8,171,044.38 23/11/2018 8 weeks 100 Completed Construction of the (3 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-62) at Kiri Town 101 Gujungu/Civil Defence and Nomi in Taura Constituency. Essence World Wide Service Taura 21,345,568.24 21,345,568.24 19,823,715.94 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects at Danyayi in Kanya Babba 102 Constituency. Deetech Nig. Ltd. Babura 6,907,388.25 6,907,388.25 6,907,388.26 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-42B) at Kafin Tugga in Fagam 103 Constituency. Yayarin Tukur Nig. Ltd. Gwaram 5,391,347.85 5,391,347.85 5,056,374.80 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-38) at Digawar Kwando in 104 Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 4,797,719.10 4,797,719.10 4,566,453.35 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-58) at Malam Anas Madachi in 105 Kirikasamma Constituency. Wajedu Nig. Ltd. K/kasamma 13,008,460.55 13,008,460.55 12,413,468.55 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-48) at Chanchanda in Malam 106 Madori Constituency. Wajedu Nig. Ltd. M/madori 10,102,692.86 10,102,692.86 9,931,523.67 23/11/2018 10 weeks 100 Completed Construction of the (2 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-53) at Addani and Ringim in 107 Yankwashi Constituency. Granitoids Engr. Services Ltd Yankwashi 24,386,180.20 24,386,180.20 24,328,485.04 23/11/2018 8 weeks 100 Completed Balance C/F 1,081,754,080.94 1,084,545,916.95 8i

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,081,754,080.94 1,084,545,916.95 Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-39) at Lafiya Madabe in Buji 108 Constituency. Yayarin Tukur Nig. Ltd. Buji 12,518,061.42 12,518,061.42 11,921,963.25 23/11/2018 8 weeks 100 Completed Construction of the (2 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-51) at Dandi and Nisan Marke 109 Towns in Ringim Constituency. Marb Engr. Multi-Services Ringim 4,272,234.94 4,272,234.94 4,068,795.17 23/11/2018 8 weeks 100 Completed Construction of the (3 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-50) at K/Bashe, Tsabare and 110 G/Sani in Ringim Constituency. Marb Engr. Multi-Services Ringim 6,170,717.41 6,170,717.41 5,876,873.10 23/11/2018 8 weeks 100 Completed Construction of the (4 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-61) at Kwalam, Wayu, Bardu 111 and Yangayami in Taura Constituency. Baban Doki General Enterp Taura 22,075,259.57 22,075,259.57 21,024,056.73 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-59) at Kargo mai Makaranta in 112 Malam Madori Constituency. Ramadan Construction Nig. Ltd. M/Madori 14,081,577.61 14,081,577.61 14,072,137.80 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-37) at Ganuwar Kuka in Auyo 113 Constituency. AMM Manzo Nig. Ltd. Auyo 10,604,774.94 10,604,774.94 10,597,464.93 23/11/2018 8 weeks 100 Completed Construction of the (1 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-43) at Bula Sabuwa in 114 Gagarawa Constituency. A.G.M. & Sons Nig. Ltd. Gagarawa 9,245,690.00 9,245,690.00 9,245,690.00 23/11/2018 8 weeks 100 Completed Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-20) at Tudun Alhazaiand 115 Maigazari in Gumel Constituency. Lautai Genaral Investment Gumel 3,831,916.20 3,831,916.20 3,746,645.70 23/11/2018 6 weeks 100 Completed Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-19) at G/Dawa Kabawa, 116 Dahabu and Malaman Doko in Garki Constituency. MMz Garki Construction Nig. Garki 5,846,768.55 5,846,768.55 5,614,950.00 23/11/2018 6 weeks 100 Completed Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects at Bayan GSS Wunti and Unguwar 117 Danjani in Hadejia Constituency. Jiffa Enterprises Hadejia 3,912,545.07 3,912,545.07 3,532,839.03 23/11/2018 6 weeks 100 Completed Construction of (4 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects at Kagadama, Sarkin Gabas, Madaka 118 and Gamji in Gagarawa Constituency. Essence World Wide Service Gagarawa 7,835,700.60 7,835,700.60 7,807,061.39 23/11/2018 6 weeks 100 Completed Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-36) at Rafin kanya and Garin 119 Kuttu in Taura Constituency. Nushe Business Resources Taura 3,918,404.70 3,918,404.70 3,743,300.00 23/11/2018 8 weeks 100 Completed Balance C/F 1,186,067,731.95 1,188,859,567.96 8j

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,186,067,731.95 1,188,859,567.96 Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects at Kubuna, Dolen Kwana and 120 Karanga in Birniwa Constituency. AMM Manzo Nig. Ltd. Birniwa 5,878,268.25 5,878,268.25 5,783,768.23 23/11/2018 6 weeks 100 Completed Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-29) at Barbawa in Kaugama 121 Constituency. Danfatu & Sons Nig. Ltd. Kaugama 1,952,522.85 1,952,522.85 1,930,022.85 23/11/2018 6 weeks 100 Completed Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-3) at Yammaulu Insharuwa 122 ward Karade in Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 3,918,845.70 3,918,845.70 3,755,045.70 23/11/2018 6 weeks 100 Completed Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects at Kankaren Shatima in Maigatari 123 Constituency. ALLAH Abin Dogara Nig. Ltd. Maigatari 1,959,107.85 1,959,107.85 1,877,522.85 23/11/2018 6 weeks 100 Completed Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects at Kankaren Bakin Ruwa, 124 Kankaren Madawa and Idari in Maigatari Constituency. NBS & Sons Construction Nig. Maigatari 5,878,268.50 5,878,268.50 5,632,568.55 23/11/2018 6 weeks 100 Completed

Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-6) at Malamawar G/Kwalli, 125 Azare Sabuwa and Kalgeri in Bulangu Constituency. Kawu Nig. Ltd. K/Hausa 5,881,121.97 5,881,121.97 5,795,089.17 23/11/2018 6 weeks 100 Completed Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-5) at Sabon Gidan Jabo, 126 Fadawa Karama and Dokori in Bulangu Constituency. Kawu Nig. Ltd. K/Hausa 5,869,568.55 5,869,568.55 5,645,892.31 23/11/2018 6 weeks 100 Completed Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-21) at Sabaru Gabas, Gada 127 Yamma and Kanti Gabas in Kazaure Constituency. Yanduna Ventures Nig. Ltd. Kazaure 5,881,418.50 5,881,418.50 5,632,568.55 23/11/2018 6 weeks 100 Completed Construction of (4 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects at Dan Karaye, Bindaye, Lafiya and 128 Kokochi in Taura Constituency. Sambu Synergy Concept Ltd. Taura 7,830,026.40 7,830,026.40 7,486,599.96 23/11/2018 6 weeks 100 Completed Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-25) at Malam Abba and 129 Alagarno in Maigatari Constituency. Nadada Ventures Nig. Ltd. Maigatari 3,919,263.76 3,919,263.76 3,721,445.70 23/11/2018 6 weeks 100 Completed Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects at Baramusa in Malam Madori 130 Constituency. Step By Step intgrated Servic M/Madori 10,100,798.17 10,100,798.17 9,621,612.18 23/11/2018 8 weeks 100 Completed

Balance C/F 1,245,136,942.45 1,247,928,778.46

8k

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,245,136,942.45 1,247,928,778.46 Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-...) at Dallare, Barebari 131 Sankara and Digawar Kurmi in Ringim Constituency. Marb Engr. Multi-Services Ringim 5,884,568.55 5,884,568.55 5,632,568.55 23/11/2018 6 weeks 100 Completed Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-30) at Kaki Kankare, 132 Larabawa and Daunawa in Ringim Constituency. Marb Engr. Multi-Services Ringim 5,882,678.50 5,882,678.50 5,630,678.48 23/11/2018 6 weeks 100 Completed Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-3) at Yayarin Tukur Town in 133 Buji Constituency. Yayarin Tukur Nig. Ltd. Buji 1,961,519.70 1,961,519.70 1,877,522.80 23/11/2018 6 weeks 100 Completed Construction of (2 No.) Two Daily Prayer Mosque 2018 Constituency Projects at Masheme and Tangari Tsagaya in 134 Garki Constituency. MMZ Garki Constr. Nig. Garki 3,915,162.00 3,915,162.00 3,743,809.45 14/11/2018 8 weeks 100 Completed Construction of wall fencing and Grave yard (2018 phase II) constituency projects (lot -64B) at B/Zango in Gwaram 135 Constituncy. Yayarin Tukur Nig Ltd Gwaram 10,524,058.65 10,524,058.65 10,022,912.99 23/11/2018 8 weeks 100 Completed Construction of wall fencing and Grave yard (1No.) (2018 phase II) constituency projects (lot -65) at Dakayyawa town 136 in Kaugama Constituncy. Nabakwai Gen. Enterp Ltd Kaugama 10,175,937.42 10,175,937.42 10,161,792.63 23/11/2018 10 weeks 100 Completed Completion/Renov. Of (1no.)Friday Prayer Mosque (2018 phase III) Constituency Projects (Lot-67 ) at Gada yamma in 137 kazaure Constituency. Yanduna Venture Nig Ltd kazaure 3,268,000.00 3,268,000.00 3,112,380.94 23/11/2018 8 weeks 100 Completed Construction of (5No) five daily prayer mosques (2018 phase II) constituency project (Lots -32) at agufa Gabas, markawa, 138 kadirawa,sarawiya and maiganjara in miga constituency Amia interg. Serv.Nig. Ltd Miga 9,781,364.25 9,781,364.25 9,361,364.25 23/11/2018 6 weeks 100 Completed Construction of wall fencing, External works and Solar Electricity Supply (2018 phase III) constituency projects at 139 JIBWIS Juma'at Mosque Basirka in Fagam Constituncy. Lines and Dimension Nig. Ltd Gwaram 12,484,914.10 12,484,914.10 11,890,363.80 31/12/18 8 weeks 100 Completed Construction of wall fencing and Grave yard (2018 phase II) 140 constituency projects (lot -) at Kukuma in Buji Constituncy. Yayarin Tukur Nig Ltd Buji 8,320,638.93 8,320,638.93 7,954,570.48 23/11/2018 8 weeks 100 Completed Renov. Of District Head house (2018 phase III) Constituency 141 Projects (Lot-26 ) at Auyo in Auyo Constituency. Na-bakwai Enterp. Ltd Auyo 6,127,766.75 6,127,766.75 5,835,963.33 23/11/2018 8 weeks 100 Completed Balance C/F 1,323,463,551.30 1,326,255,387.31

8L

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,323,463,551.30 1,326,255,387.31 Construction of wall fencing and Grave yard (2018 phase II) constituency projects (lot -) at Kiyawa Gabas kiyawa 142 Constituncy. AGM & Sons Nig. Ltd kiyawa 11,146,344.60 11,146,344.60 11,024,014.57 23/11/2018 8 weeks 100 Completed Construction of wall fencing and Grave yard (2018 phase II) constituency projects (lot -) at Gagara Yaga town in Gwaram 143 LGA AS Gaza inter. Serv. Nig ltd Gwaram 13,260,534.00 13,260,534.00 13,200,390.77 27/11/2018 8 weeks 100 Completed Completion/Renov. Of (1no.)Friday Prayer Mosque (2018 phase III) Constituency Projects (Lot-65 ) at Yoruba Juma'at 144 mosque in Hadejia Constituency. Muhal Global concept Hadejia 4,013,760.20 4,013,760.20 3,822,702.10 23/11/2018 8 weeks 100 Completed Completion/Renov. Of (2no.)Friday Prayer Mosque (2018 phase III) Constituency Projects (Lot- 62) at Shamakeri in 145 Bulangu Constituency. Kawu Nig. Ltd. K/Hausa 11,250,950.40 11,250,950.40 10,714,848.00 27/12/18 8 weeks 100 Completed Completion/Renov. Of (2no.) Friday Prayer Mosque (2018 phase III) Constituency Projects (Lot-60) at Waloyi sabuwa, 146 JIBWIS Juma'at mosque in Bulangu Constituency. Kawu Nig Ltd K/Hausa 12,674,985.00 12,674,985.00 12,674,985.00 23/11/2018 8 weeks 100 Completed Construction of (3No.) Friday prayer Mosque (2018 phase II) Constituency project (lot -40) at Zangon kanya, waloyi 147 sabuwa and Tsangaiwa in Bulangu Constituency Kawu Nig Ltd K/Hausa 16,888,035.21 16,888,035.21 16,797,853.60 23/11/2018 8 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-30) at sabaru, Batatsaba and 148 Tudun wayo in kazaure Constituency. Yanduna Venture Nig Ltd kazaure 7,833,491.40 7,833,491.40 7,285,022.85 23/11/2018 6 weeks 100 Completed Construction Of (2no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at kofar yamma anad rukutu 149 in Sule Tankarkar Constituency. Na'ayi Resources Ltd S/tankarkar 5,375,297.80 5,375,297.80 5,112,128.79 23/11/2018 8 weeks 100 Completed Construction Of (5no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-7) at kuntukulu, yarma, 150 chiliga, Nafada and giwa in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/kudu 9,799,739.25 9,799,739.25 9,379,739.25 23/11/2018 8 weeks 100 Completed Construction Of (2no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-) at kadira and tukuikui town 151 in guri Constituency. Jiffa enterprises Guri 3,912,545.07 3,912,545.07 3,606,083.67 23/11/2018 6 weeks 100 Completed

Balance C/F 1,419,619,234.23 1,422,411,070.24

8m

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Balance B/F 1,419,619,234.23 1,422,411,070.24 Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-) at Riga yoka, kubulu and abir 152 in guri Constituency. Jiffa enterprises Guri 5,881,418.55 5,881,418.55 5,629,418.55 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-23) at Dadin duniya, kargo and 153 maje gari in kiyawa Constituency. FAAHM Intreg. Resour. Ltd kiyawa 5,872,358.50 5,872,358.50 5,489,381.48 23/11/2018 6 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-19) at U/malam, kununrogo, 154 kankare and timbau in kanya babba Constituency. Deetech Nig Ltd Babura 7,846,091.40 7,846,091.40 7,510,091.40 23/11/2018 6 weeks 100 Completed Construction Of (6no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-5) at Barwa, K/boka, Bulliti, 156 Dokaro, Lafiya and Jingargari in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/kudu 11,733,404.10 11,733,404.10 11,229,404.13 23/11/2018 8 weeks 100 Completed Construction Of (5no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-4) at Chandam, Daurawa, Ajawa 157 bkd, Juwan Tudu and Ludduga in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/kudu 9,782,614.25 9,782,614.25 9,362,614.27 23/11/2018 8 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Masama, Malumawa, 158 Jinnako and Kintiri in Kirikasamma Constituency. Dabino interg.serv. Ltd Kirikasamma 7,085,135.75 7,085,135.75 6,865,270.06 23/11/2018 6 weeks 100 Completed Construction Of (1no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Kirikasamma police 159 station in Kirikasamma Constituency. Dabino interg.serv. Ltd Kirikasamma 1,196,120.45 1,196,120.45 1,194,714.15 23/11/2018 8 weeks 100 Completed Construction Of (1no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Garin Kosau in Maigatari 160 Constituency. Nadada Venture Nig Ltd Maigatari 1,952,627.20 1,952,627.20 1,913,222.85 23/11/2018 8 weeks 100 Completed Construction Of (2no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-17) at Jabarna and Jahun Gabas 161 in Jahun Constituency. Khairussabah Nig ltd Jahun 3,918,645.50 3,918,645.50 3,746,645.70 23/11/2018 6 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-27) at Makera, Malikawa, Da'a 162 and Atafiyawar Gyatami in Miga Constituency. Khairussabah Nig ltd Miga 7,842,091.36 7,842,091.36 7,821,452.56 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-28) atDunnaka, koramawa and 163 Gidan Yaya in Miga Constituency. Khairussabah Nig ltd Miga 5,880,473.55 5,880,473.55 5,864,986.05 23/11/2018 6 weeks 100 Completed Balance C/F 1,488,610,214.84 1,491,402,050.85 8n

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,488,610,214.84 1,491,402,050.85 Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Gaduwa, Tsangaya Yamma 164 and U/buluburum in Guri Constituency. AMIM Consult Nig Ltd Guri 5,877,322.55 5,877,322.55 5,617,993.50 23/11/2018 6 weeks 100 Completed Construction Of (1no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Tasgen yamma in Guri 165 Constituency. AMIM Consult Nig Ltd Guri 1,959,420.85 1,959,420.85 1,877,522.85 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Guri, Galadimari and 166 Majanguwa in Guri Constituency. Jiffa enterprises Guri 5,882,678.05 5,882,678.05 5,630,678.04 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-10) at U/Gamji, Wale wale and 167 M/tahir in Garki Constituency. Mugin Inv. Nig ltd Garki 5,878,007.61 5,878,007.61 5,626,007.60 23/11/2018 6 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-) at Kurgunguma, babande, 168 koguran sabuwa and wauta in Garki Constituency. MMZ Garki contr. Nig Ltd Garki 7,841,169.36 7,841,169.36 7,510,091.40 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-16) at Dandaga, Kangarwa and 169 Dogon dawa in Gagarawa Constituency. Essence world wide serv. Nig ltd Gagarawa 5,876,775.45 5,876,775.45 5,854,621.16 23/11/2018 6 weeks 100 Completed Construction Of (5no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-6) at Damukashi, Lura, Asayaya 170 and Sundumina, Nafara in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/Kudu 9,807,614.25 9,807,614.25 9,387,614.25 23/11/2018 8 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-35) at Titi Town, Danmakama 171 and Adama in Sule Tankarkar Constituency. Nushe Bus. Resou. Nig Ltd S/Tankarkar 5,877,323.55 5,877,323.55 5,859,968.55 23/11/2018 8 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-16) at Dakila, Tauraruwa, 172 ankun Yamma and Matsaro in Hadejia Constituency. Xtrax 99 Interg. Serv. Nig Ltd Hadejia 7,844,831.40 7,844,831.40 7,192,088.07 23/11/2018 6 weeks 100 Completed Construction Of (1no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-54) at Uza in Auyo 173 Constituency. Muhal Global concept Auyo 2,276,676.25 2,276,676.25 2,276,676.00 23/11/2018 8 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Jidawa, Kwannawa and 174 G/Darmara in Dutse Constituency. H.M Dangara ltd Dutse 5,879,843.00 5,879,843.00 5,628,473.55 23/11/2018 6 weeks 100 Completed Balance C/F 1,553,611,877.16 1,556,403,713.17 8O

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,553,611,877.16 1,556,403,713.17 Construction Of (4no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-14) at Innakawa, Uduwa, 175 Lambuna and sabon garin ila in Gwaram Constituency. Yayarin Tukur Nig Ltd Gwaram 7,846,076.80 7,846,076.80 7,510,076.78 23/11/2018 6 weeks 100 Completed Construction Of (6no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-17) at Kira Malumawar jabo, satari, malumawar Jigawa,Alagarno and Lugga towns in 176 Bulangu K/Hausa Constituency, K/Hausa LGA. Kawu Nig Ltd K/Hausa 11,733,900.00 11,733,900.00 11,701,539.00 23/11/2018 8 weeks 100 Completed Construction Of (4no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-10) at U/maina, Yara dankoshe, 178 karanjau and musa d/hajiya kukuma in Buji Constituency. Yayarin Tukur Nig Ltd Buji 7,825,091.40 7,825,091.40 7,469,528.43 23/11/2018 6 weeks 100 Completed Construction Of (1no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-56) at Sara Kudu in Gwaram 179 Constituency. Yayarin Tukur Nig Ltd Gwaram 1,956,272.85 1,956,272.85 1,872,272.85 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-24) at Kawal Gana, Bye pass 180 Gwaram and Maruta in Gwaram Constituency. Yayarin Tukur Nig Ltd Gwaram 5,868,818.55 5,868,818.55 5,616,818.55 23/11/2018 6 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-13) at Basirka A, Ali Kondigo 181 and madachi in Fagam Constituency. G.M Sara & sons Nig Ltd Gwaram 5,881,568.55 5,881,568.55 5,635,339.62 23/11/2018 8 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-15) at Yarfi, Gadama and 182 Dingaya in Fagam Constituency. G.M Sara & sons Nig Ltd Gwaram 5,875,118.55 5,875,118.55 5,628,905.75 23/11/2018 8 weeks 100 Completed Construction Of (3no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-14) at Basirka Tsangaya, 183 S/Ruwa Digijin and chediya in Fagam Constituency. G.M Sara & sons Nig Ltd Gwaram 5,880,586.95 5,880,586.95 5,634,360.48 23/11/2018 8 weeks 100 Completed Construction Of (2no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Gugurum and Wargale in 184 Birniwa Constituency. B.D.U Vent. Nig Ltd Birniwa 3,907,045.70 3,907,045.70 3,738,247.48 23/11/2018 6 weeks 100 Completed Construction Of (1no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-26) at Inaruwanku in Malam 185 madori Constituency. Wajedu Nig Ltd M/madori 1,961,519.70 1,961,519.70 1,871,650.00 23/11/2018 6 weeks 100 Completed Construction of (2No.) Friday Prayer Mosques 2018 Constituency Projects at Mamudawa and U/Kaya in Roni 186 Constituency. Na'ayi Resources Ltd. Roni 18,967,013.14 18,967,013.14 18,063,822.04 14/11/2018 8 weeks 100 Completed Balance C/F 1,631,314,889.35 1,634,106,725.36 8p

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,631,314,889.35 1,634,106,725.36 Completion/Renovation of (2 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects at Farin Dutse and 187 Chediya Towns in Fagam Constituency. A.A. Maikatako Gen. Enterp. Gwaram 13,213,177.10 13,213,177.10 12,583,978.18 23/11/2018 8 weeks 100 Completed Construction of (2 No.) Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-1) at Zigon Fulani and Kataudi in 188 Auyo Constituency. Wajedu Nig. Ltd. Auyo 3,923,039.45 3,923,039.45 3,755,045.70 23/11/2018 6 weeks 100 Completed Construction of (1 No.) Daily Prayer Mosque (2018 Phase III) Constituency Projects at Ashura Madaki in Kafin Hausa 189 Constituency. Mugin Investment Nig. Ltd. K/Hausa 1,959,335.00 1,959,335.00 1,877,522.85 11/12/2018 8 weeks 100 Completed Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-56) at Unguwar Kanya in 190 Gwaram Constituency. Yayarin Tukur Nig. Ltd. Gwaram 1,959,790.35 1,959,790.35 1,875,790.35 14/12/2018 8 weeks 100 Completed Construction of (3No.) Five Daily Prayer Mosques (2018 Phase II) Constituency Projects (Lot-1) at Maje Hausawa, 191 Jama'ar Alkali and Muran in Auyo Constituency. Ahmed Maidoya & Sons Auyo 5,821,382.70 5,821,382.70 5,569,382.70 23/12/2018 6 weeks 100 Completed Construction of (1No.) Friday Prayer Mosques (2018 Phase III) Constituency Projects at Baramusa in Malam madori 192 Constituency. Step by Step Interg. Serv M/madori 10,100,798.17 10,100,798.17 9,621,612.18 31/12/2018 8 weeks 100 Completed Construction of (3No.) Five Daily Prayer Mosques (2018 Phase II) Constituency Projects (Lot-2) at Dogon Marke Tudu, 193 Takwasa and Akula Quarters Babura in Babura Constituency. Express Innovation Concept Babura 5,787,583.55 5,787,583.55 5,452,528.54 23/11/2018 6 weeks 100 Completed Completion/Renovation of (1No.) Friday Prayer Mosques 2018 Constituency Projects (Lot-68) at Zugai in Roni 194 Constituency. Yanduna Ventures Ltd. Roni 4,231,861.26 4,231,861.26 4,030,352.45 14/11/2018 8 weeks 100 Completed Construction of (1No.) Friday Prayer Mosques 2018 195 Constituency Projects at Kargo in Jahun Constituency. Yanduna Ventures Ltd. Jahun 3,674,875.89 3,674,875.89 3,596,966.88 14/11/2018 8 weeks 100 Completed Renovation of (1No.) Juma'at Prayer Mosques (2018 Phase III) Constituency Projects (Lot-59A) at Gatafa in Auyo 196 Constituency. A.G.M. & Sons Nig. Ltd. Auyo 9,331,213.96 9,331,213.96 9,327,464.19 24/12/2018 8 weeks 100 Completed Construction of (3No.) Daily Prayer Mosques (2018 Phase III) Constituency Projects Karofin Tsamiya, Maje and Ruwan Dutse and completion of (1No.) Daily Prayer Mosques at Roni 197 Unguwar Sani Kwati in Roni Constituency. Na'ayi Resources Ltd. Roni 7,821,847.00 7,821,847.00 7,372,828.41 17/12/2018 6 weeks 100 Completed Construction of (2No.) Daily Prayer Mosques (2018 Phase III) Constituency Projects (Lot-2) at Aunaka and Katirje Fulani in 198 Babura Constituency. A.A. Aljazeera Agro Proc. Babura 3,919,049.70 3,919,049.70 3,755,045.70 23/11/2018 6 weeks 100 Completed Balance C/F 1,703,058,843.48 1,705,850,679.49 8q

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 1,703,058,843.48 1,705,850,679.49 Completion/Renovation of (1No.) Friday Prayer Mosques (2018 Phase III) Constituency Projects at Danyarda Gari in 199 Sule Tankarkar Constituency. A.A. Aljazeera Agro Proc. S/Tankarkar 2,820,120.00 2,820,120.00 2,565,078.56 23/11/2018 8 weeks 100 Completed Construction of (4No.) Five Daily Prayer Mosques (2018 Phase III) Constituency Projects at Darare, Gwanda Gwaro, Udawaki 200 and Ma'azu in Sule Tankarkar Constituency. A.A. Aljazeera Agro Proc. S/Tankarkar 7,841,891.40 7,841,891.40 7,510,091.40 23/11/2018 6 weeks 100 Completed Constr of (1no) Friday mosque at Kuda in Yankwashi (2018 201 phase III) constituency project Deetech Nig Ltd. Ynakwashi 15,576,291.17 15,576,291.17 15,417,313.02 17/12/2018 12 Weeks 100 Completed Renov of Jumaat Mosque (2018 phase III) consultancy project 202 (Lot-35) at Masko in Babura Muhabib Nig Ltd Babura 4,545,883.87 4,545,883.87 4,534,163.18 25/11/2018 8 weeks 100 Completed Constr of Juma'at Prayer mosques 2017 constituency projects phase III remaining works (Lot-5) at Sunkuye and Suga in 203 Kirikasamma Constituency. Alh Umaru Babandoki K/Kasamma 16,539,295.58 16,539,295.58 16,215,864.03 16/4/2018 12 weeks 100 On-going

TOTAL 1,750,382,325.50 1,753,174,161.51 8r

Ministry of Information

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

(N ) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

1 Procurement of Electrical Equipments (phase 1) Zurfat Investment Nig. Ltd Dutse 18,049,500.00 18,049,500.00 16,371,428.57 30/04/2019 4 weeks 100 Completed 2 Renov of Gumel township stadium Farham Synergy Gumel 34,986,981.93 34,986,981.93 34,981,927.27 10/1/2019 6 weeks 100 Completed 3 Renov of Hadejia township stadium Kawu Nig. Ltd. Hadejia 5,588,405.03 5,588,405.03 5,326,332.60 17/10/2019 4 weeks 100 Completed 4 Renov of Dutse Sports Complex Gare Invest. Nig. Ltd. Dutse 18,192,343.02 18,192,343.02 18,192,337.17 10/1/2019 12 weeks 100 Completed 5 Renov of Dutse township stadium M aikatako & Sons Dutse 9,749,837.85 9,749,837.85 8,446,140.81 12/11/2019 4 weeks 100 Completed

6 Renov of Dutse township stadium (additional works) Pullad Global Dutse 8,621,123.75 8,621,123.75 8,420,632.05 20/02/20 4 weeks 100 Completed

Total 95,188,191.58 95,188,191.58

Jigawa State Polytechnic

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS (N) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

1 Constr of Wall fence Loyalty Property Dutse 16,404,601.62 16,404,601.62 16,386,322.31 28/01/19 12 weeks 100 Completed

Total 16,404,601.62 16,404,601.62

Binyaminu Polytechnic Hadejia

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

(N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Fabrication of (300no.) Detached classroom Desk K-Manu Eng. Ltd. Hadejia 9,090,000.00 9,090,000.00 9,089,999.99 22/10/2018 12 w eeks 100 Completed

1

TOTAL 9,090,000.00 9,090,000.00

Ministry of Environment

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 100 1 Constr. of Drainage at K/fada basirka (phase II) Dazal Nig. Ltd. Gwaram 8,236,789.42 8,236,789.42 8,127,129.15 18/09/2017 8 weeks Completed Construction of Drainages at makwalla (A) and 100 Unguwar sarkin Busa Quarters in Hadejia Local 2 Govt area Muhal Global concept Hadejia 41,936,999.19 41,936,999.19 41,936,999.19 23/11/2018 16 weeks Completed

Total 50,173,788.61 50,173,788.61

Informatics Institute Kazaure

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Renov ation of 40 rooms male hostel Talaku Int. Serv ices Ltd. Kazaure 17,023,989.64 17,023,989.64 17,023,870.97 29/11/2017 8 w eeks 100 Completed

2 Renov ation of Female Hostel Talaku Int. Serv ices Ltd. Kazaure 12,718,116.36 12,718,116.36 12,183,694.37 29/11/2017 8 w eeks 100 Completed

3 Renov . Of 2no. Lecture Theatre and 4no. Staff Qtrs. M.S. Danzomo Nig. Ltd. Kazaure 2,491,474.26 2,491,474.26 2,491,474.23 20/12/2018 8 w eeks 100 Completed

4 Renov . Of 4no. Houses M.S. Danzomo Nig. Ltd. Kazaure 1,896,058.29 1,896,058.29 1,896,058.29 20/12/2018 8 w eeks 100 Completed

5 Supply of Books Ngloma Consr. Co. Kazaure 9,371,485.34 9,371,485.34 9,371,485.34 18/04/2019 8 w eeks 100 Completed 6 Supply & Installation of Solar sy stem and street light Ngloma Consr. Co. Kazaure 62,121,465.00 62,121,465.00 60,901,296.75 28/6/2019 8 w eeks 100 Completed 7 Constr 1no student Hostel on ex isting foundation Talaku Int. Serv ices Ltd. Kazaure 40,835,085.78 40,835,085.78 37,630,857.88 19/11/2018 12 w eeks 100 Completed

TOTAL 146,457,674.67 146,457,674.67

Government House

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS (N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

1 Purchase of 2No. Fairly used vechicle Modang investment Ltd in the state 39,900,000.00 39,900,000.00 39,900,000.00 20/06/2019 2 weeks 100 Completed 2 Purchase of 15no. Vehicles CIG motor Company Nig Ltd in the state 169,533,611.20 169,533,611.20 169,533,611.20 9/12/2019 2 weeks 100 Completed

Total 209,433,611.20 209,433,611.20

Directorate of Economic Empowerment

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Approval for the release of Three Hundred and Fourty Thousand Naira (N340,000,000.00) only for the Procurement of Fifty (50no.) tractors from JASCO for 1 Distribution as Empowerment loans to Farmers. JASCO Across the state 340,000,000.00 340,000,000.00 24/12/2018 3 months 100 Completed

Total 340,000,000.00 340,000,000.00

Deputy Governor Office

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS A M OUN T (N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Renovation works at Deputy Governor's Daniy a Atiku 1 Official Residence, Dutse Associate Ltd. Dutse 1 7 ,1 29,21 0.40 1 7 ,1 29,21 0.40 17121001.76 6/9/201 9 1 2 weeks 100 Completed Procurement and Installation of Furniture at the Official Residence of His Excellency, the Deputy 2 Governor at Dutse Aimim Consult Nig. Ltd. Dutse 34,825,680.00 43,575,855.00 43575855 19/9/2019 8 weeks 100 Completed

Total 51,954,890.40 60,705,065.40

Jigawa State College of Islamic and Legal Studies Ringim

POST CONTRACT PROJECT EVALUATION

S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Constr. of Library Complex (phase 1) at College of Islamic R & Partners Ltd. Ringim 70,000,000.00 70,000,000.00 69,998,914.36 20/10/2016 24 w eeks 100 Completed and Legal Studies, Ringim 2 Constr of Liabrary Complex (phase II) R & Partners Ltd. Ringim 47,930,224.47 47,930,224.47 47,902,467.25 27/11/2017 20 w eeks 100 Completed 3 Constr of Liabrary Complex (phase III) Back bone Global Ringim 54,024,795.20 54,024,795.20 53,963,448.21 28/12/2018 16 w eeks 100 Completed 4 Supply and Installation of 52no. Standalone street light Sims Global Ringim 32,215,050.00 32,215,050.00 32,215,050.00 15/5/2019 8 w eeks 100 Completed

Total 204,170,069.67 204,170,069.67

SECTION ( F )

ON-GOING PROJECTS

JANUARY TO DECEMBER, 2019

Ministry of Health

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Constr. of New Gen. Hospital at B/Kudu Datum Constr. Limited B/kudu 1,498,970,413.02 1,894,683,085.99 1,145,153,325.12 19/5/2014 8 months 60 On-going

Commissioning/engagement as consultants for the supervision of construction of new general 2 hospital at Birnin kudu Design Plus B/Kudu 74,010,950.99 74,010,950.99 67,484,513.49 27/5/2014 10 month 91 On-going Renovation of X-Ray Block and Others at Hadejia Spring Global Service Hadejia 10,771,117.36 10,771,117.36 4,502,571.15 4/2/2014 2month 43 Terminated 3 General Hospital

Conversion of Catering Rest House to School of 4 Nursing, Hadejia Business Gold Ltd. Hadejia 67,757,628.62 67,757,628.62 38,524,250.94 3/22/2016 3 months 57 Revoked General Renov. /Improvement works at Fagam 5 Primary Health Care Ngaloma Const. Co. Ltd. Gwaram 64,869,057.07 71,417,939.66 64,370,619.95 30/12/2016 12 weeks 86 On-going Constr. Of New 250 Bed Specialist Hospital in 6 Hadejia PHILKO LIMITED Hadejia 1,593,314,294.25 1,867,953,470.57 1,201,703,551.71 11/10/2017 18 months 64 On-going

Engagment as Consultant for the supervision of the 7 Constr. of New Specialist Hospital, Hadejia HAG Eng. Nig. Ltd. Hadejia 67,363,041.01 67,363,041.01 45,503,239.00 19/10/2017 16 months 67 On-going

Constr of New General Hospital at Gantsa in Buji 8 LGA Ngaloma Constr Ltd. Buji 465,983,075.70 465,983,075.70 383,967,848.25 12/7/2018 9 months 82 On-going

9 Constr of New General Hospital at Garki Babandoki Gen. Entp. Garki 493,805,327.06 493,805,327.06 392,405,349.52 12/7/2018 12 months 79 On-going

Constr of New General Hospital at Guri town, 10 Headquarters of Guri LGA Retro Constr Ltd. Guri 538,386,262.75 538,386,262.75 367,653,903.85 12/7/2018 12 months 68 On-going

Constr of New School of Nursing and Midwifery at 11 Babura, Headquarters of Babura LGA Gridarch Nig. Ltd. Babura 591,562,261.76 591,562,261.76 453,962,997.41 12/7/2018 12 months 77 On-going

Upgrading of Miga PHC to General Hospital at Miga 12 town, Miga LGA. Sabongarin Yaya Miga 98,226,184.67 98,226,184.67 93,527,265.11 3/9/2018 24 weeks 91 On-going

Engagement as Consultant for the Supervision of 13 the Constr. of New General Hospital, Guri AADC Limited Guri 34,870,673.74 34,870,673.74 21,968,524.45 30/8/2018 12 months 63 On-going

Engagement as Consultant for the Supervision of 14 the Constr. of New Specialist Hospital, Kazaure HAG Eng. Consultants Kazaure 78,006,110.10 78,006,110.10 51,531,977.61 10/8/2018 16 months 66 On-going

Engagement as Consultant for the Supervision of 15 the Constr. of New General Hospital, Gantsa Blue Urban Transnational Buji 33,925,256.47 33,925,256.47 20,593,195.17 10/8/2018 9 months 60 On-going

Engagement as Consultant for the Supervision of 16 the Constr. of New General Hospital, Garki Zeebro Global Resources Garki 34,321,462.71 34,321,462.71 20,670,835.53 10/8/2018 12 months 58 On-going

17 Constr. of New Specialist Hospital at Kazaure Afdin Constr Co. Ltd. Kazaure 1,893,240,056.40 1,893,240,056.40 1,003,430,526.00 5/7/2018 16 months 53 On-going Supply and Installation of Medical equipments to 18 the newly constructed 31no. BHC across the state. Mashasha Investment Ltd.Across the state 98,065,965.00 98,065,965.00 25/4/2018 20 weeks On-going

Balance C/F 7,737,449,138.68 8,414,349,870.56

1a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 7,737,449,138.68 8,414,349,870.56

Co ns ultant fo r the s upervis io n o f the co ns tructio n o f new s cho o l o f Nurs ing and Midwifery at Babura 19 Supply and Ins tallatio n o f Medical equipments to the newly INTERGRAP H CONSULT Babura 50,318,699.92 50,318,699.92 35,992,089.38 24/12/2018 12 mo nths 72 On-going 20 constructed 31no. BHC across the state. G.M. Sara & So ns Ltd. Acro s s the s tate 4,129,061.98 4,129,061.98 16/4/2018 6 weeks

Supply and Ins tallatio n o f Medical equipments to the newly 21 constructed 31no. BHC across the state. Mashasha Investment Ltd. Acro s s the s tate 98,065,965.00 98,065,965.00 25/4/2018 20 weeks On-going

Co ns ultant fo r the s upervis io n o f the co ns tructio n o f new 22 s cho o l o f Nurs ing and Midwifery at Babura INTERGRAP H CONSULT Babura 50,318,699.92 50,318,699.92 35,992,089.38 24/12/2018 12 mo nths 72 On-going

Supply and Ins tallatio n o f Medical equipments to the newly 23 constructed 31no. BHC across the state. G.M. Sara & So ns Ltd. Acro s s the s tate 4,129,061.98 4,129,061.98 16/4/2018 6 weeks On-going

Constr of 3no M odified Basic Health Clinics at Bagadaza, Larkan and Dukwana in Fagam Constituency (2019 24 Constituency projects) Yayarin Tukur Nig Ltd Gwaram 25,565,018.85 25,565,018.85 24/12/2019 12 weeks On-going

25 Constr of Basic Health Centre (BHC) at M asaya Village in KiyawaUmar Constituency Aliyu & Sons (2nd Nig quarterLtd 2018Kiyawa Constituency project) 11,853,799.02 11,853,799.02 6/12/2019 12 weeks On-going Constr. Of 1No. Basic Health Clinic at Hangu Village in 26 Gwiwa Constituency project 2019 M anhaf Global Constr Nig Ltd Gwiwa 19,663,090.37 19,663,090.37 27/12/2019 16 Weeks On-going

Supply and installation of medical equipment to the 25No. 27 Newly constructed basic health clinic across the state. Dangata mem. inv. Ltd Across the state 95,423,350.00 95,423,350.00 11/12/2019 8 weeks On-going

Total 8,096,915,885.72 8,773,816,617.60

1b

Ministry of Water

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Rehab. of Water Supply Schemes across the state 1 at Gwaram Zone (Water Board) Interworld I & E Gwaram 27,207,315.85 27,207,315.85 25,403,004.38 9/21/2015 12 weeks 89 On-going

2 Constr. Of 40no. Hand pumps AGM & Sons Ltd. State 28,000,000.00 28,000,000.00 18,000,009.00 3/24/2014 6 months 65 Terminated

Constr. of Hand Pumps Water Supply Schemes (phase II) as Constituency projects at Yosaro, Dilima/Zaramba and Mungulo in B/Kudu 3 Constituency. A.A. Aljazeera Agro Properties B/Kudu 1,657,215.00 1,657,215.00 29/3/2017 8 weeks Stalled

Constsruction of Hand pumps Water supply schemes (phase II) as constituency project at Yola, Masanawa, Larabar Gulai, Katanga Kudu, 4 Dan koli and Dubal in Kiyawa Constituency. DE-MASTBO Kiyawa 3,331,430.00 3,331,430.00 29/03/2017 8 weeks Stalled

Construction of Solar Powered Water supply schemes (Phase II) as constituency Projects at Sabuwar Rafa (Andaza ward ) in Dutse 5 constituency DE-MASTBO Dutse 6,270,000.00 6,270,000.00 29/03/2017 8 weeks Stalled

Constr. Of 4no. Hand pumps Water supply schemes (phase II) as Constituency projects at Kofar Gidan Liman, Bayan Gidan Sarkin Bai, Zankuwa fulani and Sabuwar SSS in Garki 6 Constituency. Taqib Ventures Nig. Ltd. Garki 2,340,000.00 2,340,000.00 21/6/2017 8 weeks Stalled Constr. Of Solar Powered Water Supply Schemes (Phase I) as Constituency Project at Marma in 7 Kirikasamma Constituency LOYALTY PROPERTIES LTD K/Kasamma 6,943,387.00 6,943,387.00 7/8/2017 8 Weeks Stalled Construction of (1No.) Hand pump water supply Schemes 2017 Constituency Project Phase II (Lot- 8 3) at Tsattiya in Dutse Constituency Loyalty Properties Ltd Dutse 798,000.00 798,000.00 1/24/2018 8 weeks On-going

Construction of 91No.) Solar Powered water supply scheme 2017 constituency Phase II Project 9 (Lot-16) at Gambawa in Miga Constituency Loyalty Properties Miga 6,968,430.00 6,968,430.00 1/24/2018 8 weeks On-going Constr. Of (1no.) Solar [powered water supply scheme 2017 constituency phase II project (LOT- 10 27) at Gacharam in Guri Constituency. Limis Brothers & Co. Guri 6,968,430.00 6,968,430.00 24/1/2018 8 weeks On-going Conversion of Motorizied Boreholes to Solar Powered Water supply at Garki main Station in 11 Garki Local Govt Area. Sims Global Resources Garki 34,070,557.50 34,070,557.50 18,327,487.50 7/2/2018 12 Weeks 52 On-going BAL. C/F 124,554,765.35 124,554,765.35 2a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 124,554,765.35 124,554,765.35

Constr of (1no.) Solar Powered water supply schemes 2017 constituency phase III projects (Lot- 12 13) at Kangarwa in Maigatari Constituency Jignaj Global Constr Ltd. Maigatari 6,968,430.00 6,968,430.00 21/3/2018 8 weeks On-going Construction of (9No.) Hand Pumps Water supply scheme 2017 Constituency phase II Projects (Lot- 8) at Gidan Iliyasu, Mai Goro, Falari Burburwa, Zulkiya Kila, Kila by pass, Sara cikin gari, Kuka manoma, Kafin torto and Fiji in Gwaram 13 Constituency. A.A. Aljazeera Agro Proc. Gwaram 7,202,791.35 7,202,791.35 5,588,165.61 24/1/2018 8 Weeks 74 On-going Constr of (1no.) Solar Powered Water Supply Scheme Constituency Projects (2018 phase 1) Lot- 14 7 at Constituency. Jignaj Global Ltd. 6,023,115.00 6,023,115.00 17/10/2018 8 weeks On-going

Constr of Hand pump Boreholes as constituency projects (2018 phase III) Lot-8 at Nasarawa, Saunawa Fulani, Kashin Ganji, Kirya, Galma, Wailare, Rafin Kaba, Chakurawa, Timbi, Joganai, Matsari, Fulanin Maikanbu, Buta, Makera, U/tudu, Fulanin Dakata, G/Gashi, Malamawa Dankabo, Danyaka fulani, JSS Garki, Sabuwar U/Arewa, Daurawa Yamma, Gurarraji and Kuttu in Garki 15 Constituency. Mugin Invest. Nig. Ltd. Garki 17,703,000.00 17,703,000.00 18/12/2018 12 weeks On-going Constr of Water Collection points constituency projects (2018 phase III) Lot-22 at Gangara, Yarbarewa, JSS Doko, Barebari, Dan Kargo, Mahoni, Jangari, Dunguzu, Masare and Koyama in Garki 16 Constituency. Mugin Invest. Nig. Ltd. Garki 12,588,450.00 12,588,450.00 18/12/2018 10 weeks On-going

Constr of Hand pump Boreholes as constituency projects (2018 phase II) Lot-14 at Kanzon Kokori, D/Kyaure Yamma, Gafaya B., G.Baba Gagare D/Toca, Aguran Mazana, Dangoli Gabas and Gafaya in Kafin 17 Hausa Constituency. Alkawakeb Global Concept K/Hausa 5,164,110.00 5,164,110.00 18/12/2018 8 weeks On-going

Constr. Of (4no.) Hand pumps water supply Scheme Consultancy projects (2018 phase) Lot 20 18 at Fulanin G. Dunfu in Taura Constituency. Faahm Integrated Resource Taura 2,942,100.00 2,942,100.00 17/10/2018 6 weeks On-going

Construction of (1NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 19 18 at Ban-iyaka in Roni Constituency. HikimaSynergy Gen Entp Nig Roni 733,918.50 733,918.50 17/10/2018 4 weeks On-going

BAL. C/F 183,880,680.20 183,880,680.20

2b

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

BAL. B/F 183,880,680.20 183,880,680.20

Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-21) at Fagam in Fagam Constituency 20 Gwaram LGA. Loyalty Properties Ltd. Gwaram 6,023,010.00 6,023,010.00 23/11/2018 8 weeks On-going Construction of Block of 2-Classroom Islamiyya (1NO.) Lot-11 at Jibori in Kirikasamma 21 Constituency. Tosarawa Global Ltd. Kirikasamma 3,097,448.45 3,097,448.45 1/11/2018 4 Weeks On-going

Construction of (8NO.) Hand Pumps Water supply scheme Constituency projects (2018 Phase I) Lot 14 at Muna, Mundu, Kwagga, Fulanin Hauwa, Jakai Fulani, Dangaigai, Inguwar Goje and Kadagawa in Kanya Babba Constituency. Babura Local 22 Government Area. DeeTech Nig Ltd. Babura 5,905,200.00 5,905,200.00 15/10/2018 8 weeks On-going Construction of the (1 No.) Solar Powered Water Supply Schemes 2018 Constituency Phase III Projects (Lot-18) at Kaya Jamu in Maigatari 23 Constituency. Alkawakeb Global Concept Maigatari 6,023,115.00 6,023,115.00 23/11/2018 8 weeks On-going

Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-32 at Yalwa in Gagarawa 24 Constituency. Farham Intgratred Resources Gagarawa 6,023,115.00 6,023,115.00 23/11/2018 8 weeks On-going Construction of the (1 No.) Solar Powered Water Supply Schemes Constituency Projects (2018 Phase II) Lot-33 at Medin Saleh in Gagarawa 25 Constituency. Farham Intgratred Resources Gagarawa 6,022,275.00 6,022,275.00 23/11/2018 8 weeks On-going

Upgrading and Conversion of (30 No.) Water Supply Schemes to Solar Powered System Across 26 the State (Lot-1). Sims Global Resouces Nig. across the State 240,169,437.35 240,169,437.35 184,805,303.97 14/11/2018 3 Months 77 On-going Conversion of 2no. Motorized boreholes to Solar powered water supply schemes at Babura town in 27 Babura LGA. SIMS Global Resources Babura 56,502,805.27 56,502,805.27 31/12/2018 12 weeks On-going

Construction of Water Collection Point as Constituency Projects (2018 Phase II) Lot-32 at Maigatari (2No.) Maloya, Bosuwa, Galadi, Madana 28 and Jajeri in Maigatari Constituency. Jag & H Intgrated Services Ltd. Maigatari 7,358,173.38 7,358,173.38 18/12/2018 8 weeks On-going

BAL. C/F 521,005,259.65 521,005,259.65 2c

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 521,005,259.65 521,005,259.65

Constr of Hand pump Boreholes as constituency projects (2018 phase II) Lot-14 at Kanzo kokori, D/kyaure yamma, Gafaya B, Baba Gagare D/Toca, Aguran mazana, Dangoli Gabas and Gafaya in 29 K/Hausa Constituency. Alkawakeb Global Concept K/Hausa 5,164,110.00 5,164,110.00 18/12/2018 8 weeks On-going

Improvement of Gwaram Tsohuwa and Gwaram 30 Sabuwa Towns Water Supply Schemes Nushe Business Resources Gwaram 122,870,123.46 122,870,123.46 59,837,762.25 28/11/2018 6 weeks 48 On-going

Upgrading and Conversion of 22No. Small Towns Water Supply Schemes to Solar Powered Water supply Scheme (Lot-1) at Maitsamiya in Sule Tankarkar, Sarkin gandu in Sule Tankarkar, Medu in Gagarawa, Dankumbo in Maigatari, Giginya in Babura,Dorawa in Babura Tasawa in Babura, Samamiyya in Birninkudu, Bamaina in Birnin kudu, Kantoga in Birnin kudu, Kila kudu, in Gwaram Kila Orchad in Gwaram, Jidawa in Dutse, Aujara A. B. & C in Jahun, Girbobo in Kaugama, Margadu in Birniwa, Batatsaba in Guri, Tuntube in Kazaure and Sada in 31 Roni. Sims Global Resources State 204,765,713.15 204,765,713.15 167,257,096.65 24/12/2018 4 month 82 On-going

Construction of Hand Pump Boreholes Water Supply Schemes Constituency Projects (2018 Phase III) Lot-11 at Katsiro Gidan Jaka, Mai Yadiya, Kwarin Sanka, Gama Fulani, Unguwar Dani Fulani, Gyauraji Alhazai, Torankayi, Makaranta Gabas ZangonKaigamari, Kanwayi, Tsalliyawa katagum, dangewaye, kwanjamawa, albirakyau, gidan sansani, shafatu, gauzagidandorawa, narba kauye, komai ALLAH yayi, ringimawa fulani, jikin kotu, gargabo, fanfam liba, zagau fulani, gidan dan wanka, harbo tsohuwa, harbo sabuwa, zarga, nahuce harbo, tazara gidan gabas, gaskawa, turubu, kurfai fulani, koya tsangayar tsoho, bagamarusabon gari, dogawa bankin titi and jahun police station in jahun 32 Constituency Loyalty Properties Nig. Ltd. Jahun 28,035,640.00 28,035,640.00 18/12/2018 15 weeks On-going

BAL. C/F 881,840,846.26 881,840,846.26 2d

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 881,840,846.26 881,840,846.26

Construction of Hand Pump Boreholes as Constituency Projects (2018 Phase II) Lot-13 at Shamsul Duhu Islamiyya, Achau Makaranta, Gwanfai Yamma, Afun funa, Akena Fulani, Gwanfai Malamai Magama, Birjawa Fulani, AskawaGidan makera, Alkalawa, makanin makera, kamaiAujara gidan kaya fulani, achau barnoji, rindai dina, unguwar tile, juniorarabicaujara, kauyen makama, unguwar yakubu tubabe, buki tsurutawa, garawai, sabuwar abujagabashi, yantsuru, kwarin malam,dashi yar jigawa, kwaru nula, kadoma kagul, kargo, fagen ganji, gurji, Alhazai bakin kasuwa jahun, rigar larabargambadungu, lungun mai katako 33 and sabuwar unguwa jahun in jahun Constituency. Loyalty Properties Nig. Ltd. Jahun 27,882,120.00 27,882,120.00 18/12/2018 14 weeks On-going Constr of Solar powered water supply schemes at new market, Zai/Galadimawa and Improvement works at Shuwarin Sabuwa and Shuwarin main 34 pump stations, Dutse zone. China Zhanghao Nig. Ltd. Dutse 95,232,647.00 95,232,647.00 81,979,563.75 31/12/2018 16 weeks 86 On-going

Upgrading and Conversion of Motorized Boreholes to Solar Powered Water supply Scheme Sabon 35 Garin Takanebu Town in Miga L.G.A. of Jahun Zone. Sims Global Resources Ltd Miga 17,238,621.65 17,238,621.65 12,608,859.90 31/12/2018 8 weeks 73 On-going

Conversion of (15No.) Hand Pumps to Solar Powered Water supply Schemes at Babura Yamma, Yangadi, Zuru, Gadi, Dan Barage, Hayin Buzu, Kuka, Gasakoli, Duzau, Yada, Kaki Zago, Gatuta Sansami, Kankare tukurkusa and Lamba in 36 Babura L.G.A. Sims Global Resources Ltd Babura 15,301,125.00 15,301,125.00 31/12/2018 10 weeks On-going

Conversion of (12No.) Hand Pumps to Solar Powered Water supply Schemes at Dan Amale, Walawa, Yanmaulu, Unguwar Ma'aruf, Batali, Kanya Gari, Dankarda, Babura Gabas, Malamawa, 37 Figi, Dunkumi and Duwala in Babura L.G.A. Sims Global Resources Ltd Babura 12,240,900.00 12,240,900.00 31/12/2018 10 weeks On-going

BAL. C/F 1,049,736,259.91 1,049,736,259.91 2e

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

BAL. B/F 1,049,736,259.91 1,049,736,259.91

Construction of Water Collection Points as Constituency Projects (2018 Phase III) Lot-26 at Kwanar Duniya, Kogon Bara and Jobi in Maigatari 38 Constituency. Danbanki Gen. Enterprises Maigatari 3,679,089.75 3,679,089.75 18/12/2018 8 weeks On-going

Construction of Water Collection Points as Constituency Projects (2018 Phase II) Lot-31 at Yelleman (2No.) Dakayyawa (2No.) and Yellaman 39 Tijjanai (2No.) in Kaugama Constituency. Alkawakeb Global Concept Ltd Kaugama 7,358,173.38 7,358,173.38 18/12/2018 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-8 at mai dashi, Idi gwamna, unguwar malam, rigar lamido, adiyani islamiyya, dagana Nato, daba, dirba, rigar malam wuri, yalwa tsangaya, goni garin una, askandi arinjasko, rigar wakilin dajjo lafiya, rigar babare, and rigar duka 40 maza in Guri Constituency AYH Intg. Serv. Ltd Guri 10,331,489.00 10,331,489.00 11/12/2019 8 weeks On-going Conversion of 10No hand Pump Boreholes to Solar in at Uku da Sisi, Ajjah, Mudirin gadi, Mundu, unguwar Ganji, Kafin Danyayi, Unguwar gawo, Dabawa, Katirje and Tsadarwa in Babura Local 41 Government Area Sims Global Res Babura 10,276,880.00 10,276,880.00 8,221,500.00 11/7/2018 8 weeks 76% On-Going

Construction of 1No. Solar Powered Water Supply 42 Scheme at Dora in Garki LGA Ringim Zone Sims Global Resources Ringim 6,023,325.00 6,023,325.00 16/4/2019 8 Weeks On-going Construction of 6No Hand Pump Boreholes water supply scheme at Yandamo Kulle 2, umarni, Modoji Babba, Fulanin Riggade, Gidan Hardo Musa ( Fulanin Asayaya) in Sule Tankarkar Local Government Area and Tamburawa in Kafin Hausa S/tankarkar + 43 LGA K-Manu Gen Construction K/Hausa 4,427,640.00 4,427,640.00 3,680,475.75 8/5/2019 12 weeks 83 On-going

Upgrading and Conversion of 1no. Motorised water supply scheme to Solar power at UKU da SISI 44 Sabuwa in Babura LGA Sims Nig. Ltd. Babura 6,767,532.45 6,767,532.45 27/9/2019 8 weeks On-going

Rehab. of 13no. Water supply scheme at Ringim, 45 Kazaure and Gumel LGA Sims Nig. Ltd. Gumel 12,788,475.00 12,788,475.00 27/9/2019 8 weeks On-going BAL. C/F 1,111,388,864.49 1,111,388,864.49 2f

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,111,388,864.49 1,111,388,864.49

Constr of (1no.) New Solar powered water supply 46 scheme at YAN Maulu Tsohuwa in Babura LGA Sims Nig. Ltd. Babura 6,023,325.00 6,023,325.00 27/9/2019 8 weeks On-going

Upgrading and Conversion of 1no. Motorised water supply scheme to Solar powered atJigawar Dan Ali, Garun Gudunya in Babura LGA and JEKE in 47 S/Tankarkar LGA Sims Nig. Ltd. S/Tankarkar 18,459,647.97 18,459,647.97 11/10/2019 8 weeks On-going

48 Rehab. Of 19no. Water supply schemein Ringim Sims Nig. Ltd. Ringim 17,361,750.00 17,361,750.00 11/10/2019 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-1 at Fulanin Gamba, Fulanin Garu and 49 Fulanin Kafur in Auyo Contituency. AMM Manzo Nig Ltd Auyo 2,210,922.00 2,210,922.00 11/12/2019 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-26 atKankanba, Dodorin Tudu, Hardo Magaji, Mataran, Dalarin Kwalta, Bultuwa Rigar Gabas, Dodorin Rigar Mal Yakubu, Bultuwa Rigar Kauga, Ung. Jibrin Masallacin Mal. Kawu and Rigar 50 Dado Gajere In Kaugama Contituency. AMM Manzo Nig Ltd Kaugama 7,377,510.00 7,377,510.00 - 11/12/2019 8 weeks On-going

Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 46 at 51 Garin Urema in Hadejia Constituency A+Tech Integrated Nig. Ltd Hadejia 6,021,855.00 6,021,855.00 11/12/2019 8 weeks On-going Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 45 at 52 Gawon Dogari in Hadejia Constituency Amia Integrated Service Nig Ltd Hadejia 6,022,485.00 6,022,485.00 11/12/2019 8 weeks On-going Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 39 53 atSabon Gari in Miga Constituency Amia Integrated Service Nig Ltd Miga 6,022,485.00 6,022,485.00 11/12/2019 8 weeks On-going Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 40 at 54 Gidan Barwa in Miga Constituency A. Barde Global Concept Ltd Miga 6,023,010.00 6,023,010.00 11/12/2019 8 weeks On-going

Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 4 at Juba 55 Gandu in Auyo Constituency Alh. Umaru Baban Doki Nig Ltd Auyo 6,004,715.00 6,004,715.00 11/12/2019 8 weeks On-going

BAL. C/F 1,192,916,569.46 1,192,916,569.46 2g

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,192,916,569.46 1,192,916,569.46

Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 39 at 56 Gabari in Malam Madori Constituency Prestige Integ Serv. Nig Ltd M/Madori 6,022,695.00 6,022,695.00 11/12/2019 8 weeks On-going Constr of Water Collection Point 2019 First Quarter Constituency Project (Lot-..) at Yofai, Tuyau, Gidan Kara, Dagasa, Jiyau, Fulani, Jiyau Babba, Tagwai, Kun Kurawa, Danbaje, Auramo Gabas Zangon Sallau, Dan Tsiru, Tsurutawa, Auramo Tudu, Gidan Sani, Zabara, Durno, Kuna, 57 Dara Zai and Bangon Jani in Ringim Constituency. Prestige Integ Serv. Nig Ltd Ringim 25,206,980.00 25,206,980.00 11/12/2019 8 weeks On-going

Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 3 at 58 Sabuwar Auyo in Auyo Constituency A.A Aljazeera Agro Processing Nig Ltd Auyo 6,010,515.00 6,010,515.00 23/12/2019 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-28 at Tashar Yellow, Fulani Cakindi, Turkushawa Gari, Gidan Amadu Inge, Fulanin Kaina, G. Idi Shiba, Fulanin Hammado, Gidan 59 Dibbo in Sule Tankarkar Contituency. A.A Aljazeera Agro Processing Nig LtdS/Tankarkar 4,426,695.00 4,426,695.00 11/12/2019 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-29 at Gangawa, Sabara, Ruwan Dawa, Kulleran, Gangawa Fulani, Fanisau, Tazara Sabon Gida, Tula, Majiga Harbo, Dina, Kamai Gitsiri, Dogawa, Gabashi, Bayan Kotun cikin Gari, Gundin Sabon Gida and Yammawa in Jahun 60 Contituency. Sasco Multi Serv Nig Ltd Jahun 11,791,752.00 11,791,752.00 11/12/2019 14 weeks On-going

Constr of Water Collection Point 2019 First Quarter Constituency Project Lot- 19 at Kofar Kudu Basirka, kofar Yamma Basirka Dal and Kofar 61 Tela Basirka in Fagam Constituency, Gwaram LGA Jignaj Global Contr Ltd Gwaram 4,876,422.00 4,876,422.00 11/12/2019 8 weeks On-going

Renov of 2no. Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 24 at Gidan Kudege and Kurneji in Gwiwa 62 Constituency Jignaj Global Contr Ltd Gwiwa 3,227,700.00 3,227,700.00 11/12/2019 8 weeks On-going

Constr of Water Collection Point 2019 First aquarter Constituency Project Lot- 23 at Kauyen Zarga and Rigarsu Iro Akwai Allah In Taura 63 Constituency Nushe Bus, Resources Nig Ltd Taura 2,519,647.20 2,519,647.20 11/12/2019 8 weeks On-going

BAL. C/F 1,256,998,975.66 1,256,998,975.66 2h

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,256,998,975.66 1,256,998,975.66

Constr of Gwaram Tsohuwa and Gwaram Sabuwa 64 Towns Water Supply Scheme (Additionsl Works) Nushe Bus, Resources Nig Ltd Gwaram 29,520,524.45 29,520,524.45 11/12/2019 12 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-12 at Sabuwar Jawo (sabaru ward), fulanin Ballami (Dandi ward), K/mal. Ali Headmaster (Gada ward), K/Alto Makeri (Gada ward) and Makabarat Gabas ( Gada ward) in 65 Kazaure Contituency. Yanduna Venture Nig Ltd Kazaure 3,686,287.50 3,686,287.50 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-8 at 66 Tsohuwar Fitare in Kazaure Constituency Yanduna Venture Nig Ltd Kazaure 6,023,115.00 6,023,115.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-7 at 67 Wawan Rafi in Kazaure Constituency Yanduna Venture Nig Ltd Kazaure 6,023,115.00 6,023,115.00 11/12/2019 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-14 at Tuda, Zakirai, K/gidan Mal Mai unguwa, Gidan Dachi, Majiyawa, Gangare, Jigawar Kaba, Mazazzaga, Yammachi, Fake cikin Gari, Kabobi, Haddori, Jama'ar isah Yaldewa/Gumai, Malamawa, Zakoro, Tasha, Jama;ar Dawa Fulani, Unguwar Abdullahi Mati, Jigawar Tsaba and 68 Makarantar Andaza in Kiyawa Contituency. Tosarawa Global Nig Ltd 14,739,900.00 14,739,900.00 11/12/2019 12 weeks On-going Constr of Water Collection Point 2019 First Quarter Constituency Project (Lot-21) at Fake Cikin Gari, Kalali, Katuka Cikin Gari, Garko Cikin Gari, Shuwarin Cikin Gari, Turho, Tsurma cikin Gari, Kadara Dankargo and Dangoli in Kiyawa 69 Constituency. Tosarawa Global Nig Ltd Kiyawa 12,603,490.00 12,603,490.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-2 at Kafeje 70 in Auyo Constituency AMM Manzo Nig Ltd Auyo 6,004,215.00 6,004,215.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-19 at Ruwa 71 yakaika in Gwiwa Constituency Jignaj Global Contr Ltd Gwiwa 6,023,220.00 6,023,220.00 11/12/2019 8 weeks On-going BAL. C/F 1,341,622,842.61 1,341,622,842.61 2i

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,341,622,842.61 1,341,622,842.61 Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-20 at yola 72 Kauye in Gwiwa Constituency Jignaj Global Contr Ltd Gwiwa 6,023,220.00 6,023,220.00 11/12/2019 8 weeks On-going Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-17 at yankwashi fulani, rauda gabas 73 and dumbule in yankwashi constituency. Granitoids Engr Services YanKwashi 2,213,032.00 2,213,032.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-34 at 74 addani in yankwashi Constituency Granitoids Engr Services YanKwashi 6,022,590.00 6,022,590.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-33 at 75 karkarna in yankwashi Constituency Granitoids Engr Services YanKwashi 6,022,590.00 6,022,590.00 11/12/2019 8 weeks On-going Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-35 at 76 manomi in Malammadori Constituency Step by Step Int. Ser. Ltd M/madori 6,022,905.00 6,022,905.00 23/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-37 at 77 Surakin in Malammadori Constituency Step by Step Int. Ser. Ltd M/Madori 6,022,905.00 6,022,905.00 23/12/2019 8 weeks On-going

Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-9 at munar 78 yan biyu in Kanya Constituency, Babura LGA. Deetech Nig. Ltd Babura 6,010,935.00 6,010,935.00 23/12/2019 8 weeks On-going Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-30 79 atkukule in Gagarawa Constituency Farham Synergy Ltd Gagarawa 6,022,800.00 6,022,800.00 23/12/2019 8 weeks On-going

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-10 at K/hausa gen. Hospital, bayan reformatory school, alakalawa A, alakalawa B, Makarantar allo kudu K/hausa, makarantar D/jalla, Makarantar M. sa'adu, makarantar turkawa, makarantar asharan chiroma, filin idi K/hausa, makarantar su shamsu, dawasa, yan darman shukura, fulanin toyara, kashe badi, chiroma kwakwata, kutungun, aguran kwari, usman kukoki, tagadawai, abewa, kazuba, karfa kama, rigar kanawa, kazalewa UNG, sule M. tubka, kununu, lafiya, katanga, rigar D/iya, kijinawa M. sa'adu, marwa abdullawa, zilawa abdullawa, aragada abdullawa, kanzan fulani (mai jama'a jingi), kargumaka (jema haruna), karori, fulanin baushe, mamajo, fulanin rumfa and baushe gari in 80 K/Hausa constituency. Mugin Inv. Nig. Ltd K/Hausa 29,509,200.00 29,509,200.00 11/12/2019 16 Weeks On-going BAL. C/F 1,415,493,019.61 1,415,493,019.61 2j

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

BAL. B/F 1,415,493,019.61 1,415,493,019.61 Constr. of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-31 81 ConsrtMutumbi of 1NO.in Gagarawa Solar Powered Constituency Water Supply Farham Synergy Ltd Gagarawa 6,022,800.00 6,022,800.00 23/12/2019 8 weeks On-going Scheme Constituecy project (2019 Phase 1) Lot-10 at Kanya cikin gari in Kanya Constituency, Babura 82 LGA. Deetech Nig. Ltd Babura 6,010,935.00 6,010,935.00 23/12/2019 8 weeks On-going Drilling of borehole and construction of overhead tank at fire service directorate headquaters in 83 Dutse (2019 capital project) Al-juraj synergy concept Ltd Dutse 6,734,650.13 6,734,650.13 18/12/2019 8 weeks On-going

Rehabilitation of 3no. Water supply scheme at danzomo, maitsamiya, and dankumbo in sule 84 tankarkar (gumel zone 2019) Lot-2 capital projects LIMIS Brothers & Co S/Tankarkar 4,628,531.25 4,628,531.25 19/12/2019 4 weeks On-going

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-27 at jalomin kudu, malari, zaburan, Ung/tsamiya, kundu, marke ung gabas, Dunbari, chuguliski, rigar ya'u karami, dolon malam and 85 arbus ung. Mamman in kaugama constituency Mufabamex Concept Ltd Kaugama 7,376,800.00 7,376,800.00 11/12/2019 8 Weeks On-going

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-30 at koluma, kodau, kata kata, kayoyi, turakan fulani, gidan jauro, jalingo S/sara, Baba ari, tsangayar gabas, malumawa, karalbali iguda, gobararin fulani, fulanin kira karama, rugar babayo, gamayin yamma, kayoyi jabo, tafa, jabo gabas, makerawa H/ali and rugar amadu babai in 86 bulangu costituency yusmatech inv. Nig. Ltd K/Hausa 14,754,800.00 14,754,800.00 11/12/2019 14 Weeks On-going Construction of pipeline distribution network 87 (28.6km) in Kazaure Town Lot-1 CGC Nigeria Ltd Kazaure 529,952,482.00 529,952,482.00 23/12/2019 24 weeks On-going

Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-97 at Basirka JIBWIS Jumu'at Mosque in fagam 88 Constituency Lines dimensions Nig Ltd Gwaram 3,640,350.00 3,640,350.00 17/12/2019 8 weeks On-going

Consr rof 1NO. Solar Powered Water Supply Scheme Lot-7 at Daki daka in Garki LGA (Ringim 89 zone 2019)-capital project LIMIS Brothers & Co Ringim 6,019,125.00 6,019,125.00 19/12/2019 8 weeks On-going

BAL. C/F 2,000,633,492.99 2,000,633,492.99 2k

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 2,000,633,492.99 2,000,633,492.99 Constr of 1NO. Solar Powered Water Supply Scheme Lot-8 at Kunyafa in Babura LGA (Ringim 90 zone 2019)-capital projects LIMIS Brothers & Co Ringim 6,019,125.00 6,019,125.00 19/12/2019 8 weeks On-going Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-1 91 at Kafardu in auyo Constituency Faahm Integrated Ltd Auyo 6,018,915.00 6,018,915.00 23/12/2019 8 weeks On-going Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-5 at Maibarewa, Sabalari, K/Fulani 92 and Kadusawa in Dutse constituency Farham synergy con. Ltd Dutse 2,947,896.00 2,947,896.00 11/12/2019 8 weeks On-going

Construction of water collection points 2019 first querter constituency projects Lot-18 at kadiran, 93 fagi, karanga and karde in birniwa constituency Dabino integ serv Ltd Birniwa 5,050,128.00 5,050,128.00 14/12/2019 12 weeks On-going

Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-44 94 at alkalawa in K/hausa Constituency Hambiscons Nig Ltd K/hausa 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-43 95 at Kore in K/hausa Constituency Hambiscons Nig Ltd K/Hausa 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going

Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-3 at kazura, rugar taho, fulanin karanga, fulanin karanga gabas, fulanin fagi, rugar saga, fulanin diginsa, Gidan Mal Dahiru, Birniwa U/yamma, rugar idi kulla, rugar haberi, mara, diginsa, fulanin batu, Umaru mai goro, fulanin mai zariya, korewa, fulanin kachallari, dargazawa, fulanin kishinde, gidan amadu, fulanin kazadama 96 and inkibulawa gabas in birniwa constituency Dabino integ serv Ltd Kaugama 15,492,109.50 15,492,109.50 14/12/2019 12 weeks On-going Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-38 97 at gari uku in malam madori Constituency Hambiscons Nig Ltd M/madori 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-18 98 at garin tudu in maigatari Constituency Hambiscons Nig Ltd Maigatari 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-17 99 at kwaduge in maigatari Constituency Hambiscons Nig Ltd Maigatari 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going

Rehabilitation of 18No. Water supply Schemes 100 Across the state. LIMIS Brothers & Co Across the state 9,748,615.80 9,748,615.80 24/12/2191 8 weeks On-going BAL. C/F 2,075,994,882.29 2,075,994,882.29 2l

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 2,075,994,882.29 2,075,994,882.29 Constr of Soler Power supply Scheme Constituecy project (2019 Phase I) Lot-32 at Ganbabituwa in 101 Kirikasamma Constituency. Dabino integ serv Ltd K/Kasamma 6,017,235.00 6,017,235.00 11/12/2019 8 weeks On-going Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-13 at Sawon Yamma, Gishingawa 2no., Rigar kaiwari, Iyo, Tage, Garin Wakili Gilakochini, Barmaguwa 2no. Fandun Fulani, Gayin Gane, Lofanga, Daladige, Babba Kamaji and 102 Marawaji in Kirikasamma Constituency Dabino Integ Serv. Ltd K/Kasamma 11,792,080.00 11,792,080.00 11/12/2019 12 weeks On-going

Construction of solar power water supply scheme constituncy project (2019 phase I) Lot-32 at 103 Ganbabituwa in kirikasamma constituency. Dabino Integ Serv. Ltd K/Kasamma 6,017,235.00 6,017,235.00 11/12/2019 8 weeks On-going Construction of hand pump boreholes water supply schemes constituency projects (2019 first quarter) Lot-15 at Sabon Sara, Jigalari, Lumu and 104 Gidan Maza in Miga constituency A. Barde Global Concopt Ltd Miga 2,948,820.00 2,948,820.00 11/12/2019 8 weeks On-going Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-2 at Kaute , Waje, Gurfai, Gangara, Kurta Fulani G. M/Jadi and Indurkuba Fulani Arewa 105 in Babura Constituency Mufabamex Concept Ltd Babura 3,687,075.00 3,687,075.00 11/12/2019 12 weeks On-going Constr.of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-29 at 106 Wadda in Gagarawa Constituency Farham Synergy con. Ltd Gagarawa 6,022,800.00 6,022,800.00 11/12/2019 8 weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-6 at Kwalam Fulani, Maidu Tsokai, Makwai Fulani, Gidan Haruna Dan Daga, Sarkin Dare Kofar Shafi'I, Sarkin Dare Fulani, M. Na'annabi Fulani, Garin Dutse Fulani Tale, Wadi Fulani and 107 Gidan Alasan Nadidi in Gagarawa Constituency JAG&H integrated services ltd Gagarawa 7,379,940.00 7,379,940.00 11/12/2019 8 weeks On-going

Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-15 At 108 Dawar Gada in Maigatari Constituency A.S.Maifata Gen. EntP. Ltd Maigatari 6,015,765.00 6,015,765.00 11/12/2019 8 weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-14 At 109 Zuba Barkono in Guri Constituency A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going Constr.of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-12 At 110 Madamuwa in Guri Constituency A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going BAL. C/F 2,137,905,262.29 2,137,905,262.29

2m

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 2,137,905,262.29 2,137,905,262.29 Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-11 at 111 Unguwar Gabas in Guri Constituency. A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-5 112 atGeneral Hospital in Birniwa Constituency. A.S.Maifata Gen. EntP. Ltd Birniwa 6,015,765.00 6,015,765.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-6 at 113 Kazura in Birniwa Constituency. A.S.Maifata Gen. EntP. Ltd Guri 6,015,765.00 6,015,765.00 11/12/2019 8 weeks On-going Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-13 at 114 Bodala in Guri Constituency. A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going Conversion of Motorized Water Supply Scheme to Solar Powered and Rehabilitation of Existing Solar 115 Schemes at College of Education Gumel SIMS Global Resources Gumel 29,243,441.00 29,243,441.00 6/12/2019 8 weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-47 At 116 maruta in Gwaram Constituency farham synergy con. Ltd Gwaram 6,022,800.00 6,022,801.00 11/12/2019 8 Weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-25 At 117 Fagoji in Dutse Constituency JAG & H Interg. Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going Constr. Of watar collection point 2019 first quarter constituency project Lot 20 at zazzana, mida, and 118 lafiya in gwaram constutuency farham synergy con. Ltd Gwaram 3,758,997.00 3,758,997.00 11/12/2019 8 weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-26 At 119 Kulasa in Dutse Constituency JAG & H Interg. Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-27 At 120 Kwaimawa in Dutse Constituency JAG & H Intergreted Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-28 At 121 Tabobo in Dutse Constituency JAG & H Intergreted Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going

Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-29 at gangawa, sabara, ruwan dawa, kulleran, ganwa fulani, fanisau, tazara sabon gida, tula, majiga, harbo, dina, kamai gitsira, dogawa gabashi, bayan kotun cikin gari, gundin sabon gida 122 and yamma in Jahun Constituency Sasco Multi Serv Nig Ltd Jahun 11,791,752.00 11,791,752.00 11/12/2019 14 Weeks On-going BAL. C/F 2,236,867,272.29 2,236,867,273.29 2n

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 2,236,867,272.29 2,236,867,273.29 Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-12 at sabuwar jawo (sabaru ward), fulanin ballami (dandi ward), K/Mal. Ali headmaster (gada ward), K/alta makeri (gada ward) and makabarta gabas (gada ward) in 123 kazaure Constituency Yanduna Venture Nig Ltd Kazaure 3,686,287.50 3,686,287.50 11/11/2019 8 Weeks On-going

Constr of 5No. Hand Pumps Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-25 at kanya abbba, dan yayin daurawa, kagadama, walawa and shantake in 124 kanya babba Constituency Deetech Nig. Ltd Babura 5,100,375.00 5,100,375.00 11/12/2019 8 weeks On-going

TOTAL 2,245,653,934.79 2,245,653,935.79

Ministry of Works

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Consultancy serv ices for the Constr. of Limaw a-Warw ade-Jidaw a- 1 Sakw ay a-Dutse road KAP Civ il Eng. Consultants Dutse 57,547,589.11 57,547,589.11 51,132,963.56 11/15/2012 16 months 94 Stalled

2 Constr. of Limaw a-Warw ade-Jidaw a-Sakw ay a-Dutse road (33.40km) Boroni Prono & Co. Ltd. Dutse 2,968,551,896.02 2,968,551,896.02 2,611,339,802.95 2/11/2012 14 months 88 Stalled Commissioning as Consultant on the superv ision of the Urban Tow n 3 Streetlight Project at Garki, Karkarna, Bamaina and 3no. Gen. Hosp. MBS Eng. Nig. Ltd. Garki 29,431,500.00 29,431,500.00 27,371,295.00 23/4/2014 93 stalled 4 Consultancy serv ices for the constr. Of T/kance-jamus feeder road UKM Civ il Eng. Consultant Babura 21,657,808.87 21,657,808.87 21,657,808.87 2/8/2014 8 Months 60 On-going Commisioning as consultant on the superv ision of the construction of 6No. 5 New feeder road projects across the state OPIQ Consultant Ringim 22,400,354.68 22,600,354.68 21,242,736.09 28/5/2014 8 months 95 On-going

6 Consultancy Superv ision for the Constr. of Gw iw a tow nship roads (4.0km) Sadiq Eng. Serv ices Gw iw a 34,489,165.99 34,489,165.99 31,495,251.31 12/17/2012 6 months 95 Stalled

7 Construction of Tow nship at kaugama Urban Centre (6.30KM) Rocad Contr. LTD Kaugama 940,127,208.47 940,127,208.47 263,578,988.93 13/12/2013 8 Months 28 Rev oked

8 Constr. of Tow nship Roads at Hadejia Urban Centre (12.80KM) Paache Const. Nig. LTD Hadejia 2,507,773,876.62 2,997,892,256.00 2,596,781,916.87 12/31/2013 12 months 87 On-going 9 Constr. of Tow nship Roads at Maigatari Urban Centre (6.95KM) H&M Nig. LTD Maigatari 1,037,700,121.50 1,037,700,121.50 866,698,245.00 17/12/2013 8 Months 83 On-going 10 Constr. of Tow nship Roads at Guri Urban Centre (6.15KM) SKY Tech.& Contr.LTD Guri 1,362,774,826.33 1,362,774,826.33 1,266,547,203.54 17/12/2013 8 Months 93 On-going Commissioning as Consultant on the Superv ision of the Constr. of Maigatari 11 Tow nship Road (6.95KM) Sadiq Eng Ser. LTD Maigatari 64,472,315.43 64,472,315.43 58,918,158.83 19/12/2013 8 Months 90 On-going Commissioning as Consultant on the Superv ision of the Constr. of M/Madori 12 tow nship Road (6.40KM) U.K.M Civ il Eng. LTD M/madori 59,544,758.06 59,544,758.06 58,052,780.58 12/31/2013 8 Months 100 On-going Commissioning as Consultant on the Constr. Of Roni tow nship roads 13 (5.00KM) EMACS Eng. Consultants Roni 61,195,703.35 61,195,703.35 57,626,153.48 12/31/2013 8 Months 94 On-going

14 Commissioning as Consultant for the Constr. of Hadejia Tow nship roads Global Ecological Hadejia 101,482,637.11 101,482,637.11 89,435,668.10 12/31/2013 16 months 88 On-going

15 Commissioning as Consultant for the Constr. of Kaugama Tow nship roads Interactiv e Consultants Kaugama 66,347,751.06 66,347,751.06 38,946,478.35 12/31/2013 12 months 58 Revoked

16 Commissioning as Consultant for the Constr. of Guri Tow nship roads Madapad Eng. Ltd. Guri 66,500,604.95 66,500,604.95 58,742,130.61 12/3/2013 12 months 88 On-going Fabrication and Erection of roads directional signs (Gantry ) and street 17 naming w ithin DutseMunicipality Durability Eng. Serv ices Dutse 90,081,840.00 90,081,840.00 77,618,236.51 18/3/2014 12 w eeks 87 Stalled

18 Construction of Gw iw a tow nship roads (4.0km) H & M Nig. Ltd. Gw iw a 509,414,865.75 509,414,865.75 412,393,839.50 29/11/2012 6 months 88 Stalled

19 Re-Constr. of Roni Tow nship road (5.00km) Alren Constr. Co. Ltd. Roni 645,608,565.02 645,608,565.02 645,579,156.97 4/4/2016 8 months 100 On-going

Balance C/F 10,647,103,388.32 11,137,421,767.70 3a

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Balance B/F 10,647,103,388.32 11,137,421,767.70 20 Re-Constr. of Kazaure Tow nship road (14.643km) Soject Nig. Ltd. Kazaure 2,090,736,236.34 2,090,736,236.34 2,090,610,656.20 4/4/2016 8 months 100 On-going Constr. of Jigaw ar Dan Ali-Maitsamiy a-S/tankarkar-Dangw anki-Dankumbo 21 Feeder road w ith Sur from Dankumbo to Matsatsagi (45km) H & M Nig. Ltd. S/tankarkar 639,156,955.50 1,003,554,571.95 943,572,613.20 28/12/2016 9 months 95 On-going Constr. of Majingini-Maimazari-Dantuw o -Hannun Giw a-Dankumbo feeder 22 road (11.5km) H & M Nig. Ltd. S/tankarkar 188,786,408.33 188,786,408.33 174,762,675.02 28/12/2016 6 months 75 On-going

Consultant for valuation of the State Govt.'s Investment in Electricity 23 Distribution network (PHCN) Emirate Consulting Ltd. State 125,000,000.00 125,000,000.00 62,500,000.00 19/6/2013 12 months 50 Stalled 24 Electrification of Shakoto-Bulangu (REB) Aima Strong Store Ltd. K/hausa 36,199,059.19 36,199,059.19 29,923,001.66 2/19/2014 6 months 89 On-going Supervision of the construction of JigawarDan-ali-Maitsamiya- Suletankarkar-Dangwanki-Dankumbo to Matsatsagi (45KM) and construction of Kudai-Ruru-Dantawuya-Sakwaya Feeder Road S/tankarkar + 25 (15KM) UKM Civil Eng. Dutse 14,172,571.35 14,172,571.35 10,066,755.99 11/4/2017 12 months 71 On-going 26 Constr of Darai-Gilima road (9.5km) lot-2 Alren Const. Co. Ltd. Jahun/Taura 2,492,310,165.97 2,492,310,165.97 2,114,436,744.00 27/4/2018 8 months 84 On-going Constr of Gambara-Waza-Baranda with Spur to yalwa (16.8km) lot- 27 3 Alren Const. Co. Ltd. B/kudu 3,194,083,855.93 3,194,083,855.93 3,119,614,701.90 27/4/2018 10 months 96 On-going

28 Constr of Kaugama township road (6.3km) lot-7 Afdin Constr Co. Ltd. Kaugama 1,333,357,771.41 1,333,357,771.41 651,161,382.57 30/4/2018 12 months 49 On-going 29 Constr of Babura Township road (10.28km) lot-8 Triacta Nig. Ltd. Babura 2,624,756,218.01 3,135,597,825.49 2,907,493,341.18 2/5/2018 10 months 93 On-going Commissioning as Consultant for the Supervision of the Constr. of 30 Road Network at College of Education, Gumel (3.3km) EMACS Eng. Consultants Gumel 11,798,466.27 11,798,466.27 9,038,773.02 7/6/2018 6 months 72 On-going Commissioning as Consultant for the Supervision of the Constr. of Dutse-Madobi-Katanga-Dangoli with a SPUR from Madobi to 31 Baranda (35.7km) CURVES and Straight Dutse 81,260,950.27 81,260,950.27 74,966,379.21 7/6/2018 12months 91 On-going Commissioning as Consultant for the Supervision of the Constr. Of Bariki-Munzarau-Tawakkalta-Turabu-Gidan Mutum Daya road 32 (16.8km) Himma Technical Services Hadejia 51,099,226.92 51,099,226.92 43,434,342.88 7/6/2018 12 months 85 On-going Commissioning as Consultant for the Supervision of the Constr of 33 Darai-Gilima road (9.5km) APEX Design & Associates Jahun + Taura 43,615,427.90 43,615,427.90 37,315,427.89 8/6/2018 8 months 85 On-going Commission as Consultant for the Supervision of the Construction 34 of Gambara-Waza-Baranda with a Spur to Yalwa Wuro Associates Eng. Dutse 55,896,467.48 55,896,467.48 49,188,896.92 7/6/2018 10 months 88 On-going

Commission as Consultant for the Supervision of the Construction 35 of Access road from Harbo Sabuwa to Harbon Tsohuwa (1.52km) Powermatrix Eng Jahun 4,218,516.02 4,218,516.02 3,796,664.41 13/6/2018 4 months 90 On-going

Rehabilitation of the electrification project at Marke- yalo ITC line 36 in Kaugama LGA AG Global serv. Nig ltd Kaugama 40,151,533.53 40,151,533.53 36,276,617.55 6/12/2018 12 weeks 90 On-going Constr of Balago-Dubeni-Kodowawa-Dumadumin Kyaure-Auno 37 road (41.2km) Lot-3 Gerawa Global Engr. Ltd. Kiyawa 5,321,500,681.77 5,321,500,681.77 4,549,464,150.00 21/12/2018 24 months 85 On-going Construction of 744 - Sabuwar Takur - Yalwawa Road (8.10KM) Lot 38 7. Retercha Company Ltd Dutse 1,577,371,259.00 1,577,371,259.00 1,154,812,255.80 21/12/2018 10 months 73 On-going

Balance C/F 30,572,575,159.51 31,938,132,762.82 3b

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 30,572,575,159.51 31,938,132,762.82 39 Construction of Taura - Garki Road (26.68KM) Lot 2. Alren Constr. Comp. Ltd. Taura + Garki 2,925,979,072.38 2,925,979,072.38 2,650,909,720.05 21/12/2018 16 months 91 On-going Construction of Kwanar Medi - Danzomo - Garki Road (29.51KM) 40 Lot 1. Triacta Nig. Ltd. Gagarawa + Garki 3,583,700,255.94 3,583,700,255.94 1,939,080,265.43 27/12/2018 20 months 54 On-going Construction of Birnin kudu - Zazika - Kwangara Nafadan - Kadangare - Shirin - Malamawa - Kwatai - Nafara Feeder Road 41 (33.0KM) Lot 16. Ganan Constr. Co. B/Kudu 1,109,438,407.32 1,109,438,407.32 659,736,236.25 24/12/2018 10 months 60 On-going

42 Construction of Zandam Nagogo Township Road (2.38KM) Lot 12. Ganan Constr. Co. Gwaram 435,973,460.83 435,973,460.83 190,412,659.50 24/12/2018 6 months 44 On-going Construction of Sada - Kanawa - Dankari - Nasarawa - Kudu Feeder 43 Road (11.2KM) Lot 14. SDY Engr. & Const.. Co. Ltd. Yankwashi 393,697,127.25 393,697,127.25 373,748,968.15 24/12/2018 6 months 94 On-going Construction of Chai-chai Tsohuwa Township Road (1.23KM) Lot 44 11. Belgrade Engr. & Const. Ltd. Dutse 225,712,752.30 225,712,752.30 44,221,066.37 24/12/2018 6 months 20 On-going

45 Construction of Jigawar Dan Ali Township Road (2.10KM) Lot 9. Mother Cat Nig. Ltd. Babura 427,673,958.29 427,673,958.29 415,503,284.62 24/12/2018 6 months 97 On-going 46 Construction of Miga Township Road (3.1KM) Lot 5. CGC Nig. Ltd. Miga 748,110,079.06 748,110,079.06 59,852,246.48 24/12/2018 8 months 8 On-going 47 Construction of Kiyawa Township Road (Phase II) (4.0KM) Lot 8. CGC Nig. Ltd. Kiyawa 781,689,780.01 781,689,780.01 446,685,490.77 24/12/2018 7 months 57 On-going 48 Electrification Project at Askandu in Kaugama L.G.A. Nabakwai Gen. Enterp. Kaugama 20,298,933.03 20,298,933.03 18,533,808.41 24/12/2018 12 weeks 90 On-going Consultancy services for the Dualization of Fanisau road to Unity 49 Pentagon round about in Dutse (11.4km) A.G. & Partners Ltd. Dutse 83,028,671.25 83,028,671.25 44,446,452.75 14/7/2017 50 On-going 50 Electrification Project at Alaye in Kirikasamma L.G.A. Dabino Integ. Serv. Ltd. K/kasamma 24,380,538.09 24,380,538.09 17,785,248.08 24/12/2018 12 weeks 87 On-going Co mmis s io ning as Co ns ultant fo r the Supervis io n o f the Co ns tr o f 51 Kaugama To wns hip ro ads (6.3km) SIIS Eng. Consultants Ltd. Kaugama 23,333,761.00 23,333,761.00 10,966,867.67 1/11/2018 12 m,o nths 47 On-going Commissioning as consultant for the Supervision of the Construction of 52 Chai Chai Tsohuwa township Roads UGS Consultants Dutse 3,949,973.17 3,949,973.17 1,224,290.42 20/3/2019 6 weeks 30 On-going Commissioning as consultant for the Supervision of the Construction of 53 Kiyawa Township Roads Phase II (4km) Sadiq Engineering Kiyawa 13,679,571.15 13,679,571.15 9,492,515.76 20/3/2019 6 weeks 69 On-going Commissioning as Consultant for the Supervision of the construction of 54 Kanya Babba Township Roads (2.8km) Curves & Straight design Babura 6,056,229.07 6,056,229.07 4,236,211.35 20/3/2019 6 weeks 70 On-going Commissioning as Consultant for the Supervision of the Construction of Hammado-Dafarantama-M ele-Baikarya-Garin Baki-Kokinami-Liman M ado 55 feeder Roads (32.76km) Hag Engineering Gumel 15,959,738.87 15,959,738.87 6,383,855.55 20/3/2019 6 weeks 38 On-going

Commissioning as consultant for the supervision of the Construction of 56 Zandam Nagogo township Roads (2.38km) Land Base Engineering Gwaram 7,629,535.56 7,629,535.56 2,288,860.67 20/3/2019 6 weeks 29 On-going

Commissioning as Consultant for the supervision of the Construction of 57 Kaugama - M alam M adori Feeder Road (19.31km) SIIS Engineering Consult M /M adori 9,112,024.27 9,112,024.27 20/3/2019 6 weeks On-going

Balance C/F 41,411,979,028.35 42,777,536,631.66 3c

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

BAL. B/F 41,411,979,028.35 42,777,536,631.66

Commissioning as consultant for the Supervision of the Construction of 58 Guduncin-Aguyaka Road (4.30km) Curves & Straight design Hadejia 17,024,414.69 17,024,414.69 3,404,881.97 20/3/2019 6 months 19 On-going

Commissioning as Consultant for the Supervision of the Construction of 59 Kwanar M edi-Danzomo-Garki Road (29.51km) Curves & Straight design Garki 62,714,754.77 62,714,754.77 12,542,910.95 20/3/2019 20 months 19 On-going

60 Supervis io n o f Balago -Auno ro ads Apex Design Kiyawa + K/hausa 93,126,261.93 93,126,261.93 46,266,287.51 20/3/2019 24 mo nths 50 On-going

61 2019 Rural Electrification Project at Kulawa in Ringim LGA (Lot-9) Ngloma Constr Nig Ltd Ringim 40,761,674.94 40,761,674.94 2/10/2019 14 weeks On-going

2019 Rural Electrification Project at Kaigamari M/Awaso in 62 K/Hausa LGA (Lot-7) Babandoki Gen Entp. K/Hausa 56,156,069.34 56,156,069.34 2/10/2019 14 weeks On-going

63 2019 Rural Electrification Project atTurbus in Maigatari LGA (Lot-8) Babandoki Gen Entp. Maigatari 51,909,858.00 51,909,858.00 2/10/2019 14 weeks On-going

64 2019 Rural Electrification Project at Daurawa in Taura LGA (Lot-11) Ngloma Constr Nig Ltd Taura 39,499,187.75 39,499,187.75 2/10/2019 14 weeks On-going

65 2019 Rural Electrification Project at Batali in Babura LGA (Lot-14) Ngloma Constr Nig Ltd Babura 87,414,189.61 87,414,189.61 2/10/2019 14 weeks On-going

66 2019 Rural Electrification Project at Duwigi in Gwiwa LGA (Lot-13) Babandoki Gen Entp. Gwiwa 45,418,689.70 45,418,689.70 2/10/2019 14 weeks On-going

2019 Rural Electrification Project at Ringim in Yankwashi LGA (Lot- 67 12) Pullad Global Consultant Yankwashi 59,238,524.45 59,238,524.45 2/10/2019 14 weeks On-going

68 2019 Rural Electrification Project at Batu in Birniwa LGA (Lot-5) Masaka Global Concepts Birniwa 42,505,703.10 42,505,703.10 37,994,663.70 2/10/2019 14 weeks 89 On-going

69 2019 Rural Electrification Project at Walawa in Hadejia LGA (Lot-4) Ngloma Constr Nig Ltd Hadejia 52,780,791.53 52,780,791.53 2/10/2019 14 weeks On-going

70 2019 Rural Electrification Project at Kadira in Guri LGA (Lot-6) Xtrax 99 integrated Services Guri 101,346,796.79 101,346,796.79 2/10/2019 14 weeks On-going

71 Electrification project (Lot-17) at Gangara Qtr. In Gumel LGA. Ibrahim Yusuf Integ. Gumel 23,258,058.11 23,258,058.11 2/10/2019 14 weeks On-going

72 Electrification project (Lot-15) at Masko villege in Babura LGA. Nuhabib Nig. Ltd. Babura 32,792,767.93 32,792,767.93 29,136,338.54 2/10/2019 14 weeks 88 On-going

Balance C/F 42,217,926,770.99 43,583,484,374.30 3d

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

BAL. B/F 42,217,926,770.99 43,583,484,374.30

73 Electrification project (Lot-2) at Gangawa village in Jahun LGA. Yanduna Ventures Jahun 90,247,560.30 90,247,560.30 2/10/2019 14 weeks On-going Constr of hadejia township roads (485m) road Network) Additional 74 works) at Azare road-Adua Mosque-New Motor Park (Road II) PAAche Constr Ltd. Hadejia 312,270,011.92 312,270,011.92 2/10/2019 16 weeks On-going

75 Constr of Babura township roads (10.28km) (Additional works) Triacta Nig Ltd. Babura 510,841,607.48 510,841,607.48 2/10/2019 16 weeks On-going Supply and Istallation of Stand Alone Solar powered streetlights at 76 Government Girls Arabic School Babura, Goverbment Girls Unity Sims Global Resources Gwaram 60,780,300.00 60,780,300.00 4/11/2019 8 weeks On-going

Constr of Jigawar Dan Ali Township Road (2.10KM) (Additional 77 Work) Mother Cat Nig Ltd Babura 203,412,195.00 203,412,195.00 11/12/2019 16 weeks On-going

Installation of 100-units of Integrated Standalone Solar Powered 78 Streetlight at Babaldu town, Birnin Kudu LGA. Ar-Rayyan Ventures Global Birnin Kudu 55,786,500.00 55,786,500.00 24/12/2019 4 weeks On-going

Mainatinance and Rehabilitation of some Failed Sections along 79 Kazaure - Roni Road Retercha Cmp. Nig Ltd Kazaure+Roni 98,528,040.30 98,528,040.30 12/12/2019 16 weeks On-going

Electrification projects at Tashena Village and Shagaryo town in 80 Mallam Madori LGA AHF Global Nig Ltd. M/madori 49,293,924.94 49,293,924.94 41,642,186.99 15/10/2019 16 weeks 95 On-going Supply and installations of 150-units integrated standalone solar powered streetlight at Garun gudunya and garin gambo towns in 81 babura and gumel LGAs SIMS Nig. Ltd Babura+Gumel 81,328,800.00 81,328,800.00 24/12/2019 12 weeks On-going

Supply and installation of 150-units integrated stand alone 82 powered streetlights at marke town in kaugama LGA Sims Global Resources Nig Ltd Kaugama 82,797,750.00 82,797,750.00 3/12/2019 12 weeks On-going

TOTAL 43,763,213,460.93 45,128,771,064.24 3e

Ministry of Education

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Procurement of 2-sets of Sporting facilities at Bamaina Talented & Gifted School, 1 B/kudu L.G.A. BM Inv est. Nig. Ltd. B/kudu 36,030,000.00 36,030,000.00 31,987,558.79 16/8/2012 12 w eeks 85 Stalled 2 Supply of Classrooms, Staff Houses & Office Equip. to JICORAS A. Barde Global Concept. K/hausa 33,143,878.07 33,143,878.07 24,952,793.85 13/12/2012 3 w eeks 75 Stalled 3 Supply of Library books to JICORAS Al-kassam Jannah K/Hausa 30,785,750.00 30,785,750.00 28,526,075.95 2/5/2013 8 w eeks 92 Stalled 4 Constr. w orks at JICORAS (phase II) Datum Constr. Co. K/Hausa 1,677,895,165.73 1,708,557,551.33 1,608,258,817.26 30/8/13 18 w eeks 94 On-going Constr. of 1No. Block of Sabbatical Lodge, 5No Principal Officers Quarters 3No Blocks 240 Capacity Students Hostels and Construction of Road Netw ork Culv ert 5 and Drainages at Jigaw a State Univ ersity Kafin Hausa (Phase III) Datum Const. Nig. LTD K/Hausa 2,574,587,179.00 2,782,409,740.68 873,397,813.68 28/11/2013 6 Months 34 On-going 6 Construction of Senate Building at Jigaw a State Univ ersity , K/hausa A.G Ferrero K/Hausa 1,698,949,299.60 1,961,397,871.17 1,759,415,903.28 24/7/2014 10 months 90 On-going

7 Supply and Installation of 5HP Pumps at BEC Camp For the use of State Univ ersity Modang Inv estment Nig. Ltd Auy o 2,436,750.00 2,436,750.00 623,000.00 13/2/2014 8 w eeks 23 Stalled Commissioning as Consultant for the Designing and Superv ision of (phase II) for the 8 constr.of Jigaw a State Univ ersity , K/Hausa Design Plus + K/Hausa 158,703,031.78 158,703,031.78 117,453,599.98 12/18/2014 18months 74 On-going Procurement of 1000no. College Tablets, CAMP 1000 students for the period of (5) 9 w eeks E-learning Programme Activ ities Echo Infotech Solutions H/qtrs. 34,311,150.00 34,311,150.00 28,508,507.50 12/3/2015 2 months 83 Stalled Constr of 1no. Block of 2no. Classroom Islamiyya school (3no.) 2nd phase 2017 constituency projects (Lot-5) at Karkarna, Sada and Yalawa in 10 Yankwashi Constituency. Granitoids Eng Services Yankwashi 9,820,818.00 9,820,818.00 9/5/2018 13 weeks On-going Constr of 1no. Block of 2-classroom Islamiyya at Bakwarga in Buji 11 Constituency 2017 (phase III) Yayarin Tukur Nig Ltd. Buji 3,269,819.70 3,269,819.70 28/5/2018 8 weeks On-going Constr of Block of 2no. Classroom Islamiyya and Constr of 1no. Block of 3- classroom and 2no. Block of classroom with office (SUBEB Type) 3rd phase 2017 Constituency project (Lot-9) at K/Arewa, Izala Islamiyya and 12 Makarantar Malam Daura in Ringim Local Govt. Nushe Business Resources Ringim 9,819,350.10 9,819,350.10 5/7/2018 10 weeks On-going Constr of Drainage at Kuburu-Mabuga (Anku) Titin Yahai Qtrs (907m) 13 Hadejia town, 1st Qtrs. 2018 Constituency project Tasi'u Mohammed Hadejia 28,264,601.73 28,264,601.73 17/8/2018 3 months On-going Installation of TDN Line, Substation and 40KVA Gen. at GS&TC Ringim (1st 14 phase 2018 projects) (Lot-30) Yusma Tech Invest. Ringim 11,119,230.57 11,119,230.57 6,006,971.25 12/7/2018 6 months 55 On-going Installation of TDN Line, Substation and 20KVA Gen. at GS&TC B/kudu and 15 Installation of TDN line at SSS K/Babba (Lot-31) Math Global Concept B/Kudu + Babura 12,717,747.66 12,717,747.66 8,916,752.51 16/7/2018 6 months 67 On-going

Construction of Senate Building along with the provition of parking Lots 16 and walk ways at Sule Lamido University, Kafin Hausa (additional Works). A.G Ferrero Building K/Hausa 262,448,571.57 262,448,571.57 23/10/2018 24 weeks On-going Construction of Block of 2-Classroom Islamiyya (3NO.) Lot-19 at Jigawar 17 Maroka, Kiyawa K/fada and Tuje in Kiyawa Constituency Demastbo Ventures Ltd. Kiyawa 9,342,612.24 9,342,612.24 1/11/2018 10 Weeks On-going

BAL. C/F 6,593,644,955.75 7,094,578,474.60 4a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 6,593,644,955.75 7,094,578,474.60 Feeding of 597 Boarding School students at MBPS/JSS Kazaure & 35 students at Intel Disability Kazaure in Kazaure LGA (2019 MOEST Capital 18 Projects) Lot-40. Umar Aliyu & Sons Kazaure 23,888,538.40 23,888,538.40 23/12/2020 40 weeks On-going Construction of Block of 2-Classroom Islamiyya (1NO.) Lot-20 at Dunnaka 19 in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 3,115,779.08 3,115,779.08 1/11/2018 4 Weeks On-going Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-2 at Rakumin 20 Rafa and Kasabur in Birniwa Constituency. Amm Manzo Nig. Ltd. Birniwa 6,224,550.80 6,224,550.80 1/11/2018 10 weeks On-going Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-2 at Rakumin 21 Rafa Constituency. Bulangu Drilling Services 6,968,430.00 6,968,430.00 1/11/2018 10 Weeks On-going Construction of Block of 2-Classroom Islamiyya (7NO.) Lot-10 at Sabalari, kishingawa, Limawa Gabar, Dan masara, Chamo Gari, Yalwawa and Buju in 22 Dutse Constituency. Al-kasam Jannah Nig. Ltd. Dutse 21,687,679.15 21,687,679.15 5/11/2018 20 Weeks On-going Construction of Block of 2-Classroom Islamiyya (1NO.) 2nd Phaes 2017 Constituency Projects (Lot-16) at Government Arabic Secondry School 23 (G.A.S.S.) in Sule Tankarkar Constituency. Kairussabah Nig. Ltd. S/tankarkar 3,224,219.90 3,224,219.90 1/11/2018 3 Weeks On-going Construction of Block of 2-Classroom Islamiyya (2Nos.) at Kankare & Raha and (1NO.) Block of 3-Classroom Subeb Type at Tsardawa in Kanya Babba 24 Constituency, (Lot-1) Babura Local Government Area. DeeTech Nig Ltd. Babura 13,885,760.58 13,885,760.58 15/10/2018 10 weeks On-going Construction of (1N0.) Blocks of 2-classroom Islamiyya school SUBEB typed 2018 phase II constituency projects (Lot -7) atDanmakeri in Ringim 25 constituency. Mai-Mai Blocks ind. Nig. Ltd Ringim 4,940,040.00 4,940,040.00 1/11/2018 6 weeks On-going Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-19) at Karkarna and Ruruma in 26 Yankwashi Constituency. Granitoids Engr. Services Ltd Yankwashi 6,224,045.10 6,224,045.10 18/12/2018 8 weeks On-going Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase II Constituency Projects (Lot-2) at Majingini and Babban 27 Kambari in Gumel Constituency. Jag & H Intgrated Services Ltd. Gumel 6,230,703.46 6,230,703.46 3,010,358.03 5/12/2018 8 weeks 48 On-going Constr of (3no.) block of 2-classroom Islamiyya School typed 2018 phase II constituency projects (Lot-13) atHussaindeen Babangida Jahun, Atuman 28 Harbo Sabuwa and Ruwan Dawa in Jahun Constituency. AGA Kilawa Nig. Ltd Jahun 9,311,022.00 9,311,022.00 5,209,942.50 5/12/2018 10 weeks 55 On-going Construction of (1 No.) Blocks of 3-Classroom, 1-Block of 6-Seater VIP Pit Latrine and Hand Pump at Govt. Day Arabic Secondary School Birniwa (Lot- 29 1). MWT Real Estate & Gen. Mer. Birniwa 12,639,228.22 12,639,228.22 28/12/2018 3 months On-going Construction of 1-Blocks of 6-Classroom (1st & 2nd Quarter 2018 UBEC/SUBEB Intervention Project) Lot-5 G/Sarki and Construction of 2- Classrooms with Office, Staff Room, Meeting Room and Toilet at Ruhogo in 30 Hadejia L.G.A. Step by Step Intergrated Serv Hadejia 31,639,463.50 31,639,463.50 18/11/2018 16 weeks On-going

Construction of Blocks of 2-Classroom Islamiyya Typed (2No.) Lot-6 at 31 Tashena and Kargon Gabas in Malam madori Constituency. Express Innovation Concept M/madori 6,208,148.10 6,208,148.10 27/12/2018 6 weeks On-going Construction of (1No.) Blocks of Teachers Lodge 2018 Phase III 32 Constituency Projects (Lot-25) at Kanya Babba in Kanya Constituency. Deetech Nig. Ltd. Gwaram 12,701,001.00 12,701,001.00 18/12/2018 12 weeks On-going Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-24) at Garun Gabas in Malam 33 madori Constituency. Nabakwai Gen. Enterprises M/madori 3,115,351.08 3,115,351.08 18/12/2018 8 weeks On-going

BAL. C/F 6,765,648,916.12 7,266,582,434.97 4b

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 6,765,648,916.12 7,266,582,434.97 Constr of (3no.) blocks of 2-classroom Islamiyya school typed 2018 phase III constituency projects (Lot-13) at Ajura, Kekau and Garki in Garki 34 Constituency. Mugin Investment Nig. Ltd. Garki 9,341,037.24 9,341,037.24 18/12/18 10 weeks On-going Constr of (10no.) block of 2-classroom Islamiyya School typed 2018 phase III constituency projects (Lot-3) at Gida Dubu, Kargo Yamma, Kudai Yamma, Zobiya, Tofa, Galadimawa, Katangare, Irwa, Gandun Mazare and 35 Baranda in Dutse Constituency. Mugin Investment Nig. Ltd. Dutse 31,136,790.83 31,136,790.83 12,836,962.26 24/12/2018 15 weeks 39 On-going Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-1 at Girdo, Tasawa and Tsamiyar Kwance in Kanya Babba Constituency Babura Local Government 36 Area Dee- Tech Nig Ltd Babura 9,347,337.24 9,347,337.24 27/11/2019 13 weeks On-going Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-7 at Jauga, Jankawa Yola, 37 Karwai, Wailari and Budai in Ringim Constituency Marb eng. & Multi service Nig Ltd Ringim 15,576,585.00 15,576,585.00 27/11/2019 8 weeks On-going Construction of (3No.) Blocks of 2-Classroom Islamiyya School Typed 2018 Phase III Constituency Projects (Lot-10) at Dan Barage, Tela Rabiu 38 Residence Babura Kofar kudu and Jigawa Yamma in Babura Constituency. Mufabamex Concept Nig. Ltd. Babura 9,341,037.24 9,341,037.24 18/12/2018 10 weeks On-going Procurement and Distribution of Instructional Materials Basic Levels 39 across the State. Ngaloma Constr. Co. Across the state 62,319,731.25 62,319,731.25 28/12/2018 12 weeks On-going Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr. Phase II 2019 constituency project) at Ung. Kalgo, Kuda Walawa and Bade 40 Fulani in Yankwashi Constituency. Granitoids Eng Serv. Ltd. Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 12 weeks On-going Renovation of Structures at Government Science Secondary School Lautai 41 Gumel ( Phase II) Gerawa Gobal Engr Ltd Gumel 98,014,279.51 98,014,279.51 50,616,896.92 21/06/2019 6 month 52 On-Going Feeding of 1,407 Boarding School students at GGASS Babura in Babura LGA 42 (2019 MOEST Capital Projects) Lot-1. JALGO Integ. Services Ltd. Babura 53,186,214.40 53,186,214.40 23/12/2019 40 weeks On-going Commissioning as Consultant for the Training and Technical Support of 250No Senior Secondary School Teachers on K-Yan Machine for the 43 Facilitation of E-Learning at Senior Secondary Schools Across the State C-Stemp Construction Skills Across the state 36,227,761.00 36,227,761.00 32,604,984.89 24/5/2019 6 Month 90 On-going Constr of 1no. Block of 3-classrooms each at GDSS Babura, GDSS Galagamma Gumel, GDSS babura and GDSS Ringim Areawa (2019 Capital 44 projects) Babandoki Gen Entp. Ringim 44,808,022.00 44,808,022.00 3/10/2019 12 weeks On-going Constr of 1no. Block of 3-classrooms each at GDSS Dan Masara, GDSS Jahun, GDSS Shagari Qtrs Hadejia and GDSS M/madori (2019 Capital 45 projects) Math Global Invest. M/madori 44,808,022.00 44,808,022.00 3/10/2019 12 weeks On-going Renovation of Staff Quarters at College of Education Gumel, Lot-7 (3rd & 46 4rd Quarter 2019 Capital projects) Babandoki General Entr Gumel 233,513,402.67 233,513,402.67 27/11/2019 12 weeks On-going Construction of 1No Block of 2 classroom Islamiyya School each, Lot-4 (First Quarter 2019 Constituency Project) at Dodal (Nomadic and Jammaje 47 Gafaffa in Gwiwa Isah Halilu Nig Ltd Gwiwa 6,226,306.20 6,226,306.20 2 7 /1 1 /2 01 9 8 weeks On-going Construction of classrooms Blocks at Jigawa College of Remedial and Advance Studies(JICORAS) Babura, Lot-4 (3rd & 4rd Quarter 2019 Capital 48 Projects) Babandoki General Entr Babura 120,213,423.86 120,213,423.86 2 7 /1 1 /2 01 9 24 weeks On-going BAL. C/F 7,549,048,637.68 8,049,982,156.53 4c

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 7,549,048,637.68 8,049,982,156.53 Construction of 1No Block of 2 Classroom islamiyya School Lot-14B (First Quarter 2019 Constituency Project) at Hassan Hadejia in Hadejia 49 constituency Muhal Global Concept Ltd Hadejia 9,100,200.00 9,100,200.00 2 7 /1 1 /2 01 9 9 weeks On-going Renovation of 13No Students Hostels at College of education Gumel, Lot-8 50 (3rd &b 4rd Quarter 2019 Capital Projects) Babandoki General Entr Gumel 148,840,065.71 148,840,065.71 2 7 /1 1 /2 01 9 12 weeks On-going Construction of Hostel Block at Jigawa College of remedial and Advance 51 Studies (JICORAS) Lot-5 (3rd & 4th Quarter 2019 Capital Projects) Ngaloma Constr Co Ltd K/Hausa 100,763,064.17 100,763,064.17 2 7 /1 1 /2 01 9 24 weeks On-going Construction of 1No. 2 classroom Islamiyya School each, Lot-6 (First Quarter 2019 Constituency Project at Abur, Margadu, Ahlal Sunnah 52 Islamiyya, Musari and Wareri in Guri Constituency Adam General Enter Ltd Guri 15,576,795.40 15,576,795.40 2 7 /1 1 /2 01 9 8 weeks On-going Construction of 2No Block of 2 Classroom Islamiyya ( 2018 Phase II Ongoing Constituency Projects) Lot-10 at danksoshe and Jatafinnamari in 53 Buji Constituency Mai-Mai Blocks Industry Ltd Buji 6,231,539.60 6,231,539.60 18/11/2019 8 weeks On-going Construction of 1No Block of 2 Classroom Islamiyya School each Lot-12 (First Quarter 2019 Constituency Project at Kan Hawa Roni, Santar Tsaye 54 and Sabuwar Santa Tunas in Roni Constituency Yanduna Ventures Ltd Roni 9,339,248.04 9,339,248.04 27/11/2019 10 weeks On-going Construction of 3no Block of 2 classroom Islamiyya ( 2018 Phase III Ongoing Constituency Projects) Lot-12 at Garin Kwalandi and Kabara in Maigatari 55 Constituency NBS & Sons Constr Ltd Maigatari 15,140,562.72 15,140,562.72 18/11/2019 12 weeks On-going Construction of Malam Makera Islamiyya School (Upstairs) 2018 III Ongoing Constituency project (Lot-1S) at Malam Abdullahi islamiyya 56 Hadejia in Hadejia Nabakwai General Entr Hadejia 16,341,041.20 16,341,041.20 18/11/2019 12 weeks On-going Construction of 1No Block of 2 Classroom Islamiyya (2018 Phase II Ongoing 57 Constituency Projects) Lot-7 at Guri in Guri Constituency Nushe Business Resources Guri 3,115,779.08 3,115,779.08 18/11/2019 8 weeks On-going Construction of 2No Block of 2 Classroom Islamiyya (2018 Phase III Ongoing Constituency Projects ) Lot-7 at Garin Musa and Daneri in Birniwa 58 Constituency BDU Ventures Ltd Birniwa 6,227,358.16 6,227,358.16 18/11/2019 8 weeks On-going Construction of 1No Block of Science Laboratory and Administrative Block 59 (Lot-1) at GDSS Kukuma in Buji Constituency project 2019 Yayarin Tukur Nig Ltd Buji 22,937,034.15 22,937,034.15 14/11/2019 8 weeks On-going Construction of 1No Block of 2 classroom Islamiyya (2018 Phase III Ongoing 60 Constituency Projects) Lot-1B at Maskangayu In Auyo Constituency DDN Constr Nig Ltd Auyo 3,115,359.08 3,115,359.08 18//11/2019 8 weeks On-going Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-19B at Kunduwaje and Gagura 61 in Gwaram Constituency, Nushe Bus, Resources Nig Ltd Gwaram 6,685,247.76 6,685,247.76 11l12l2019 6 weeks On-going Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-16 at Ramin kura, Juwan, 62 Masaru and Nasarawa in Birnin Kudu Constituency, Nushe Bus, Resources Nig Ltd B/kudu 12,888,711.92 12,888,711.92 11/12/2019 10 weeks On-going Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-9 at Askawa, Kulawa Babare, Achau Boro, Lugga Dashi, Tokai Arewa, Ung. M. Nagoggo, Damutawa, Gabashi, Rinde fulani, Bakin Kasuwa, Ung. Isah Yar Jigawa, Gwamfai Sabon Gari, Tsangaya, Kulluru Yammaci, Alikau, Sukullufi, Gidan Atiku, Makera, Gwamfai, Achau 63 Auyakayi and Likindin Gabashi in Jahun Contituency. Danfatu & sons Nig Ltd Jahun 14,755,650.00 14,755,650.00 11/12/2019 8 weeks On-going BAL. C/F 7,940,106,294.67 8,441,039,813.52 4d

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 7,940,106,294.67 8,441,039,813.52 Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-13 at Kiri Hawandu, Katarika 64 and Kawari/Gujungu in Taura Constituency Nushe Bus, Resources Nig Ltd Taura 11,719,771.12 11,719,771.12 27/11/2019 12 weeks On-going

Constr of additional 1no. Block of 3- Classrooms each at GDSS Kazaure, GDSS Sabon Gida, GDSS Haruna (Hadejia), GDSS Fagoji, GDSS Galagamma 65 Gumel and GDSS Famfo Goma Hadejia (2019 MOEST Capital project) Al-sabur Global Links Nig Ltd State 67,212,333.84 67,212,333.84 3/12/2019 12 weeks On-going Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-10B, at Bashuri in Dutse 66 Constituency, Al-kheeyad Nig Ltd Dutse 3,115,676.00 3,115,676.00 11/12/2019 8 weeks On-going Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Ringim Arewa, K/Babba, Gujungu, Sakwayya and G/Kuka 67 (2019 Last Quarters MOEST Capital project Across the state (Lot-1ABCD&E) Ngaloma Constr Nig Ltd Ringim 103,609,125.68 103,609,125.68 23/12/2019 12 weeks On-going Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Bosuwa, Taura, and Gumel (2019 Last Quarters MOEST 68 Capital project Across the state (Lot-3AB&C) Babandoki Gen. Enterp Nig Ltd Gumel 104,213,888.67 104,213,888.67 23/12/2019 12 weeks On-going Constr of Classes, Laboratories at GDSS Kafin Hausa, Kadira, Shagari, Dakido, Kanti, Roni, Danmasara, Kudai, Birnin Kudu, Malamadori and Kiyawa (2019 Last Quarters MOEST Capital project Across the state (Lot- 69 5ABC&D) Sabon Garin yaya Nig Ltd Kiyawa 106,186,110.20 106,186,110.20 27/12/2019 12 weeks On-going Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Galadi, GDSS Marabusawa, GDSS Dakido (2019 Last 70 Quarters MOEST Capital project Across the state (Lot-4AB&C) Math Global Invt. Nig Ltd Across the state 104,338,846.77 104,338,846.77 27/12/2019 12 weeks On-going Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Danzomo, GDSS Abdulkadir, and GDSS Babaldu (2019 Last 71 Quarters MOEST Capital project Across the state (Lot-7AB&C) Pullad Global Consultant Nig LtdAcross the state 114,843,483.25 114,843,483.25 27/12/2019 12 weeks On-going Constr of Toilets, Admin Blocks, Laboratories and Wall Fence, 7no. JSQ Eamination Hall and additional course of Blocks Hand pumps at GDSS Kazaure, Dutse Capital, Bamaina Academy, Dutse Model and GDSS Jabo (2019 Last Quarters MOEST Capital project Across the state (Lot-6 72 ABCDE&F) Pullad Global Consultant Nig LtdAcross the state 109,273,620.31 109,273,620.31 27/12/2019 12 weeks On-going Constr of Admin. Block, 21 Laboratories, Computer Lab. And 3-Blocks of 12 Classrooms at Mega School Dutse (2019 Last Quarter MOEST Capital 73 projects) Across the State (Lot-8 ABC & D) Babandoki Gen. Enterp Nig Ltd Across the state 224,397,873.13 224,397,873.13 23/12/2019 12 weeks On-going Constr. of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II constituency projects) Lot-19 at B/kasuwa, Sakuwa and 74 Ranbazau in Gwaram constituency Farham Synergy Ltd Gwaram 9,344,513.19 9,344,513.19 11/12/2019 8 Weeks On-going

Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II constituency projects) Lot-10A at jidawa, rahama, duru gari, 75 karnaya gari, abanderi, hara and tashar D/wake in Dutse constituency Backbone global links ltd Dutse 21,724,075.66 21,724,075.66 27/12/2019 18 Weeks On-going BAL. C/F 8,920,085,612.49 9,421,019,131.34 4e

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 8,920,085,612.49 9,421,019,131.34 Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II constituency projects) Lot-11 at dahuwa kaku in kiri kasamma 76 constituency Nabakwai gen. entr. K/kasamma 3,103,439.45 3,103,439.45 27/12/2019 8 Weeks On-going Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II Constituency projects) Lot-14A at Abdulkadir Secondary School, Matasro Junior Secondary School and Unguwar Mai aye in Hadejia 77 constituency Step by Step Int. Ser. Ltd Hadejia 9,334,463.01 9,334,463.01 11/12/2019 10 weeks On-going Constr of Additional 6no. Blocks of 1-block of 3-classrooms at GDSS Kondiko, GGDSS B/kudu, GDSS Kwarko, GDSS Kiyako, GDSS S/garin Takanebu 78 and GDSS Galamawa Babandoki Gen. Entp. B/kudu 67,198,406.92 67,198,406.92 24/12/2019 10 weeks On-going 79 Constr of 1-block of two Science Laboratories at GGDSS Roni Manhaf Global Concept Roni 33,552,607.41 33,552,607.41 24/12/2019 16 weeks On-going Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter 80 Phase II Constituency projects) Lot-20 at garkon alli in kiyawa constituency Yarkwari global serv Nig. Ltd Kiyawa 3,113,973.13 3,113,973.13 27/12/2019 12 weeks On-going Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter 81 Phase II Constituency projects) Lot-3B at Zamini tagir in Auyo constituency Yarkwari global serv Nig. Ltd Auyo 3,013,570.00 3,013,570.00 27/11/2019 8 weeks On-going Construction of classes and admin block at GDSS Kwalam, wurno, kyarama, and sankara across the state (2019 last quarter MOEST capital 82 projects) lots-9ABCD$E Allah Abin Godiya Nig Ltd Across the state 51,991,144.67 51,991,144.67 23/12/2019 12 weeks On-going Constr, of 2No. Block of 2 Classroom islamiyya (2018 Phase iii on Going Constituency Projects) Lot-2 at Dadda Gari, Madoji Gari, Jeke Gari and 83 Sarkin Gandu in Sule Tankarkar Constituency. Danfatu & sons Nig Ltd S/tankarkar 12,454,716.33 12,454,716.33 18/11/2019 12 weeks On-going Renovation of WindstormDamaged Structures at Government Science Technical college Karkarna, Science Secondary School Kafin Hausa and Girls Science Secondary School Jahun Across the state (2019 MOEST 84 Capital Projects). Allah Abin Dogaro Nig Ltd Across the state 35,803,002.26 35,803,002.26 24/12/2019 8 weeks On-going Feeding of 2309 Boarding school Students at GGSS Garki in Garki local Govt 85 (2019 MOEST Capital projects) Lot-7 MMZ Garki Gen Constructors Garki 87,276,300.00 87,276,300.00 23/12/2019 40 weeks On-going Constr, of 2No. Block of 2 Classroom islamiyya Each (2018 first Quarter Phase II Constituency Projects) Lot-21 at Ung. Kalgo, Kuda walawa and 86 Bade fulani yankwashi Constituency. Granitoids Engr Services ltd Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 12 weeks On-going Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Projects) Lot-18 at Aduwa in Kafin Hausa 87 Constituency. Mai Mai Blocks Ind. Nig. Ltd K/Hausa 3,111,654.55 3,111,654.55 11/12/2019 9 weeks On-going Feeding of 1,003 Boarding school students at GGSSS Taura in Taura LGA 88 (2019 MOEST Capital projects) Lot-26 Dankwara Maijimina Gen. Entp. Across the state 37,911,714.80 37,911,714.80 23/12/2019 40 weeks On-going Feeding of 433 Boarding school students at GJSSS Guri in Guri LGA (2019 89 MOEST Capital projects) Lot-28 Baradugum Gen. Entp. Guri 16,366,540.00 16,366,540.00 23/12/2019 40 weeks On-going Feeding of 970 Boarding school students at GGSS S/tankarkar in 90 S/tankarkar LGA (2019 MOEST Capital projects) Lot-24 Hassan Habu T. Gen. Entp. S/tankarkar 39,182,001.60 39,182,001.60 23/12/2019 40 weeks On-going Feeding of 790 Boarding school students at GSTC Hadejia in Hadejia LGA 91 (2019 MOEST Capital projects) Lot-12 A.H.M. Global Ventures Hadejia 29,860,672.80 29,860,672.80 23/12/2019 40 weeks On-going BAL. C/F 9,362,699,590.54 9,863,633,109.39 4f

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 9,362,699,590.54 9,863,633,109.39 Constr of Wall fence at Jigawa College of Remedial and Advance Studies 92 (JICORAS) Babura, Lot-2 (3rd & 4th Qtr. 2019 Capital Projects) Ngaloma Constr. Co. Ltd. Babura 131,969,392.51 131,969,392.51 27/11/2019 24 weeks On-going Constr of Admin Block at Jigawa College of Remedial and Advance Studies 93 (JICORAS) Babura, Lot-1 (3rd & 4th Qtr. 2019 Capital Projects) Ngaloma Constr. Co. Ltd. Babura 83,365,963.69 83,365,963.69 27/11/2019 24 weeks On-going Supply of Science Laboratories Equipment for Distribution to Senior Sec 94 School Across the state Aldan Project Ltd Across the state 29,491,628.72 29,491,628.72 24/12/2019 8 weeks On-going Procurement of Science Laboratory equipment for distribution to 9no 95 Science Centre of Excellence Core-2 Quest Ventures Ltd. Across the state 81,037,103.92 81,037,103.92 24/12/2019 3 weeks On-going Feeding of 1031 Boarding school students at GGASS Danzomo in Sule 96 tankarkar Local Government Area (2019 MOEST Capital project) Lot-25 Salisu & Isah Gen. Entp. Danzomo 38,969,984.00 38,969,984.00 23/12/2019 40 weeks On-going Feeding of 1,762 Boarding school students at GUSS Maigatari in Maigatari 97 Local Government Area (2019 MOEST Capital project) Lot-20 Shabarawa Gen. Enterpr Babura 66,600,638.40 66,600,638.40 23/12/2019 40 weeks On-going Feeding of 426 Boarding school students at Science secondary school kanya Babba in Babura Local Government Area (2019 MOEST Capital 98 project) Lot-41. H.A.U. Gen. enterp. Babura 16,102,084.40 16,102,084.40 23/12/2019 40 weeks On-going Feeding of 635 Boarding school students at MBPS/JSS Ringim in Ringim 99 Local Government Area (2019 MOEST Capital project) Lot-35 H.A.U. Gen. enterp. Ringim 23,875,921.20 23,875,921.20 23/12/2019 40 weeks On-going Feeding of 3378 Boarding school students at GUSS Ringim in Ringim Local 100 Government Area (2019 MOEST Capital project) Lot-21. H.A.U. Gen. enterp. Ringim 127,667,604.80 127,667,604.80 23/12/2019 40 weeks On-going Feeding of 761 Boarding school students at SSS Lautai in Gumel Local 101 Government Area (2019 MOEST Capital project) Lot-8. Bakar Kasa Gen. Enter. Gumel 28,764,521.60 28,764,521.60 23/12/2019 40 weeks On-going Feeding of 1,030 Boarding school students at SAIS Hadejia Local 102 Government Area (2019 MOEST Capital project) Lot-13 MS Amar & son enterp Hadejia 38,932,269.60 38,932,269.60 23/12/2019 40 weeks On-going Feeding of 753 Boarding school students at GGCSS Roni in Roni Local 103 Government Area (2019 MOEST Capital project) Lot-23 Talba Gen. Enterp Roni 28,462,134.80 28,462,134.80 23/12/2019 40 weeks On-going Feeding of 1319 Boarding school students at GUSS Roni and 170 tsangaya school students at Gwiwa in Roni and Gwiwa Local Government Area 104 (2019 MOEST Capital projects) Lot-22 Adon Sale Bandu Across the state 57,699,603.60 57,699,603.60 23/12/2019 40 weeks On-going Feeding of 1572 Boarding school students at GUSS Fantai and 279 students at school for deaf in hadejia Local Government Area (2019 MOEST Capital 105 project) Lot-11 Alh. Muhammad Kwalli Gen. Hadejia 69,924,690.40 69,924,690.40 23/12/2019 40 weeks On-going

Feeding of 1703 Boarding school students at GUSS Malammadori in 106 Malammadori Local Government Area (2019 MOEST Capital project) Lot-37 AG Isyaku Gen Ent M/madori 64,366,351.60 64,366,351.60 23/12/2019 40 weeks On-going Feeding of 445 Boarding school students at GSTC Karkarna in Yankwashi 107 Local Government Area (2019 MOEST Capital project) Lot-27 Malabai Gen Ent Yankwashi 16,820,252.40 16,820,252.40 23/12/2019 40 weeks On-going Feeding of 580 Boarding school students at GJSSS Karkarna in Yankwashi 108 Local Government Area (2019 MOEST Capital project) Lot-29 Malabai Gen Ent Yankwashi 21,923,025.60 21,923,025.60 23/12/2019 40 weeks On-going Feeding of 635 Boarding school students at MBP/JSS Gumel and 60 Tsangaya school students at Mai Aduwa in Gumel Local Government Area 109 (2019 MOEST Capital project) Lot-32 Wangara Agent Gen Ent. Gumel 26,406,169.60 26,406,169.60 23/12/2019 40 weeks On-going BAL. C/F 10,315,078,931.38 10,816,012,450.23 4g

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 10,315,078,931.38 10,816,012,450.23 Feeding of 453 Boarding school students at GSTC Ringim in Ringim Local 110 Government Area (2019 MOEST Capital project) Lot-36 Maidala Gen. Ent. Ringim 17,122,640.00 17,122,640.00 23/12/2019 40 weeks On-going Feeding of 2,254 Boarding school students at GGUSS Gwaram in Gwaram 111 Local Government Area (2019 MOEST Capital project) Lot-9 Gobirawa kwari Gen. Ent. Gwaram 84,333,796.80 84,333,796.80 23/12/2019 40 weeks On-going Feeding of 1231 Boarding school students at GGASS birniwa in birniwa 112 Local Government Area (2019 MOEST Capital project) Lot-4 A.I. Maiso Gen. Ent. Birniwa 46,529,720.00 46,529,720.00 23/12/2019 40 weeks On-going Feeding of 728 Boarding school students at GGJSSS Miga in Miga Local 113 Government Area (2019 MOEST Capital project) Lot-31 Yusif Garba Miga Gen. Ent. Miga 27,511,020.00 27,511,020.00 23/12/2019 40 weeks On-going Feeding of 1,380 Boarding School students at GUSS Malam Madori LG 114 (MOEST Capital Projects)LOT-19 SawIra gen enterprises M/madori 52,161,681.60 52,161,681.60 23/12/2019 40 weeks On-going Feeding of 1,122 Boarding School students at GSS Aujara in Jahun LG Adamu Ibrahim Aujara Gen. 115 (MOEST Capital Projects)LOT-15 Entp. Jahun 42,687,419.20 42,687,419.20 23/12/2019 40 weeks On-going Feeding of 621 Boarding School students at SAIS Fatara in Dutse LG (MOEST 116 Capital Projects)LOT-6 Baita Daushanga Gen. Entp. Dutse 23,394,510.80 23,394,510.80 23/12/2019 40 weeks On-going Feeding of 1,233 Boarding School students at MBPS/JSS KILA Gwaram LG 117 (MOEST Capital Projects)LOT-42 Baita Daushanga Gen. Entp. Gwaram 46,605,328.40 46,605,328.40 23/12/2019 40 weeks On-going Feeding of 882 Boarding School students at GUSS Basirka Gwaram LG 118 (MOEST Capital Projects)LOT-10 Baita Daushanga Gen. Entp. Gwaram 33,333,159.20 33,333,159.20 23/12/2019 40 weeks On-going Feeding of 554 Boarding School students at MBP/JSS Guri, 58 Tsangaya School students at Tarabu and 60 Tsangaya School students at Birniwa in 119 Guri and Birniwa LG (2019 MOEST Capital Projects)LOT-34 GMA Kadira gen. enterprises Guri+Birniwa 25,893,694.00 25,893,694.00 23/12/2019 40 weeks On-going Feeding of 940 Boarding School students at science secondary school (SSS) 120 Kafin Hausa in Kafin Hausa LG (MOEST Capital Projects)LOT-16 Zango Gen. enterprises K/Hausa 35,530,420.80 35,530,420.80 23/12/2019 40 weeks On-going Feeding of 467 Boarding School students at GSTC Birnin kudu in Birnin kudu 121 LG (MOEST Capital Projects)LOT-3 Baita Daushanga Gen. Entp. B/kudu 17,651,815.60 17,651,815.60 23/12/2019 40 weeks On-going Feeding of 1,077 Boarding School students at GGASS Kaugama in Kaugama 122 LG (MOEST Capital Projects)LOT-17 Danbiri Global Ventures Kaugama 40,709,000.80 40,709,000.80 23/12/2019 40 weeks On-going Feeding of 639 Boarding School students at MBPS/JSS Bulangu in Kafin Hussaini Ahmed bookshop 123 Hausa LG (MOEST Capital Projects)LOT-33 Gen Entp. K/Hausa 24,027,126.40 24,027,126.40 23/12/2019 40 weeks On-going Feeding of 920 Boarding School students at GGUSS Kazaure in Kazure LG 124 (MOEST Capital Projects)LOT-18 Haru jika Gen. Entp. Kazaure 34,767,096.00 34,767,096.00 23/12/2019 40 weeks On-going Feeding of 2309 Boarding School students at GGSS Garki in Garki LGA 125 (MOEST Capital Projects)LOT-7 MMZ Garki Gen Const Garki 87,276,300.00 87,276,300.00 23/12/2019 40 weeks On-going Feeding of 674 Boarding School students at MBPS/JSS Kudai in Dutse LGA 126 (MOEST Capital Projects)LOT-43 Sabuwar Kuka Gen Enterp Dutse 25,476,067.60 25,476,067.60 23/12/2019 40 weeks On-going Feeding of 788 Boarding School students at GJSSS Aujara in Jahun LGA 127 (2019 MOEST Capital Projects)LOT-30 Na'ima and Fati Gen. Entp. Jahun 29,785,076.00 29,785,076.00 23/12/2019 40 weeks On-going Constr. Of Gate House and Toilet at Jigawa Colege od Remedial and advance Studies (JICORAS) Babura, Lot- 3 (3rd and 4th Quarter 2019 Capital 128 Project) Al-sabur Global Nig. Ltd Babura 39,190,677.39 39,190,677.39 27/11/2019 24 Weeks On-going Constr. Of 1No. Block of 2-Laboratories at GGDSS Roni (2nd Quarter 2019 129 Constituency Project) Lot-1 Manhaf Global Constr Nig Ltd Roni 33,552,607.41 33,552,607.41 24/12/2019 12 weeks On-going BAL. C/F 11,082,618,089.38 11,583,551,608.23 4h

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 11,082,618,089.38 11,583,551,608.23 Construction of additional block of 3 classrooms each at kondiko, GGASS Binin kudu, GDSS kwarko, GDSS kiyako, GDSS sabon gari takanebu and GDSS 130 galamawa across the state Babandoki Gen. Enterp Nig Ltd Across the state 67,198,406.92 67,198,406.92 24/12/2019 12 weeks On-going Feeding of 287 Boarding School students at bamaina academy in birnin 131 kudu LGA (2019 MOEST Capital Projects)LOT-39 Kabiru na Malam Nig Ltd B/kudu 40,204,006.00 40,204,006.00 23/12/2019 40 weeks On-going Procurement of science laboratory equipments for distribution to 9No. Senior secondary schols upgraded to science centre of exlence core-2 at GGUSS Malammadori, GDSS G/Gabas, GGSS garki, GDSS gwuiwa, GUSS aujara, GUSS maigatari, GUSS tsohuwar gwaram, GC birnin Kudu, and GUSS 132 basirka accross the state Quest Ventures Ltd Across the state 81,037,103.92 81,037,103.92 24/12/2019 8 weeks On-going Supervision of the construction works at jigawa college of remedials and advance studies (JICORAS) babura, Lot-6 (3rd and 4th quarters 2019 133 capital projects) Apex Design & Associates Babura 23,537,374.82 23,537,374.82 27/11/2019 24 Weeks On-going Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Constituency Projects) Lot-14c at harazimiyya islamiyya in hadejia 134 Constituency. Alh. Umaru Babandoki Nig Ltd Hadejia 8,055,821.00 8,055,821.00 27/11/2019 8 weeks On-going Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Constituency Projects) Lot-5 at hayatul islam and kabal in Jahun 135 Constituency. Sasco Multi Serv Nig Ltd Jahun 6,218,492.70 6,218,492.70 27/11/2019 8 weeks On-going Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Projects) Lot-2 at rukumi in malam madori 136 Constituency. Mai Mai Blocks Ind. Nig. Ltd M/madori 3,473,316.00 3,473,316.00 11/12/2019 8 weeks On-going Constr. Of 1No. Block of science Laboratory at GDSS Dan sure in roni LGA 137 (2019 MOEST capital Project) Lot-1 Na'ayi Resources Nig Ltd Roni 9,561,049.80 9,561,049.80 6/12/2019 8 weeks On-going Constr. Administrative block at jigawa college of remedial and advance 138 studies (JICORAS) Babura, Lot-1 (3rd & 4th quarter 2019 capital projects) Ngaloma Constr Nig Ltd Babura 83,365,963.69 83,365,963.69 27/11/2019 24 Weeks On-going Constr. Of wall fencing at jigawa college of remedial and advance studies 139 (JICORAS) Babura, Lot-2 (3rd & 4th quarter 2019 capital projects) Ngaloma Constr Nig Ltd Babura 131,969,392.51 131,969,392.51 27/11/2019 24 Weeks On-going Feeding of 209 Boarding school students at Tsangaya school gantsa in 140 bujiLocal Government Area (2019 MOEST Capital project) Lot-38 Zai General Ent. Buji 8,762,692.80 8,762,692.80 23/12/2019 40 weeks On-going Feeding of 2,416 Boarding school students at GUCSS Dutse in Dutse Local 141 Government Area (2019 MOEST Capital project) Lot-35 Zai General Ent. Dutse 91,320,405.20 91,320,405.20 23/12/2019 40 weeks On-going Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Projects) Lot-21 at Ung. Kalgo, Kuda Walawa and 142 Bade Fulani in Yankwashi Constituency. Granitoids Engr Services ltd Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 8 weeks On-going Feeding of 1,696 Boarding school students at GUC Birnin kudu in birnin 143 kudu Local Government Area (2019 MOEST Capital project) Lot-2 Muduka General Ent. B/kudu 64,105,950.80 64,105,950.80 23/12/2019 40 weeks On-going Ren. Of Windstorm Damaged Structures at GSTC Karkarna, SSS K/Hausa 144 and GSSS Jahun across the state (2019 MOEST Capital Projects) Allah Abin Godiya Nig Ltd Across the state 35,803,002.26 35,803,003.26 24/12/2019 8 weeks On-going Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr. 2019 constituency project) at Babura k/Arewa and Garin Baki in Babura 145 Constituency. Mufabamex Concept Ltd. Babura 6,391,877.10 6,391,877.10 27/11/2019 7 weeks On-going TOTAL 11,746,570,838.92 12,247,504,358.77 4i

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 11,746,570,838.92 12,247,504,358.77 constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-8 at Dansama , Gangara, M. 146 Yaro and Garin Baki in Maigatari Constituency, Mai-Mai Block Ind. Ni g Ltd Maigatari 9,310,318.35 9,310,318.35 27/11/2019 9 weeks On-going Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-3A at Bukari and Aimas Kuka in 147 Auyo Constituency Mai-Mai Block Ind. Ni g Ltd Auyo 6,226,518.18 6,226,518.18 27/11/2019 12 weeks On-going

TOTAL 11,762,107,675.45 12,263,041,195.30 4j

Ministry of Land

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT (N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Construction of (30NO.) Boys Quarters, External Electrification and Water supply to individual Legislator's Quarters at Disina 1 in Dutse L.G.A. Gerawa Global Engr. Dutse 812,600,502.00 812,600,502.00 723,720,196.50 17/10/2018 32 weeks 89 On-going Consultancy services for the supervision of the construction of 30no. Boys Qtrs., Ext. Electrification and Water Supply at 2 Legislative Qtrs., Dutse HAG Eng. Ltd. Dutse 47,049,676.58 47,049,676.58 42,948,768.82 9/1/2019 32 w eeks 91 On-going

Construction of 1No. Block of 4No. House of 2No. Bedroom Smi- 3 Detach at Gumel Locl Government Area Yalwa Oil & Gas Ltd Gumel 10,773,337.15 10,773,337.15 9,787,707.10 19/3/2019 14 Weeks 92 On-going

Construction of 1No. Block of 4No. House of 2No. Bedroom Smi- 4 Detach at Ringim Locl Government Area Al-Sabur Global Links Ringim 10,779,821.20 10,779,821.20 8,737,582.35 19/3/2019 14 Weeks 82 On-going

Construction of 1No Block of 4No House of 2No Bedroom Semi- 5 Detach at Babura Local Government Area Yalwa Oil & Gas Ltd Babura 10,773,337.15 10,773,337.15 9,987,707.10 19/3/2019 14 Weeks 92 On-going Construction of 1no Block of 4No House of 2No Bedroom Semi- Babandoki General 6 Detach (lot-2) at Birnin Kudu Local Government Area Enterprises B/Kudu 10,651,650.00 10,651,650.00 19/3/2019 14 Weeks On-going Construction of 1No Block of 4No House of 2No Bedroom Semi- 7 Detach (Lot-4) at Dutse Local government Area Loyalty Properties Ltd Dutse 10,582,286.69 10,582,286.69 5,677,764.75 19/3/2019 14 Weeks 54 On-going TOTAL 913,210,610.77 913,210,610.77

Ministry of Commerce

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS (N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

1 Constr. of (3.5km) Culverts & Drainage at Sara Market Beefar Constr. Nig. Ltd. Gwaram 76,329,801.45 76,329,801.45 59,864,067.40 22/11/2012 3 months 78 Stalled

2 Extension of road works at Maigatari Border Free Zone Beefar Constr. Nig. Ltd. Maigatari 37,677,600.00 37,677,600.00 11,259,724.00 11/12/2012 20 weeks 30 Stalled Consultancy services for the Constr. of Drainages at Sara, 3 Maigatari + Gujungu markets Stirling Dev. Ltd. State 19,140,670.57 19,140,670.57 16,621,973.19 14/10/12 6 months 90 Stalled

Total 133,148,072.02 133,148,072.02

Dutse Capital Development Authority

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Constr. of Dutse township road (15 & 20) Dantata & Sawoe Dutse 760,653,932.06 760,653,932.06 540,282,932.70 20/12/12 16 w eeks 73 Stalled 2 Rehab. Of Dutse Township road phase II (10.110km) CGC Nig. Ltd. Dutse 2,129,872,584.00 3,173,304,408.80 2,688,981,022.36 8/11/2012 14 months 82 Stalled 3 Rehab. Of Dutse Township road phase I (1.250km) CGC Nig. Ltd. Dutse 487,164,968.00 972,442,157.57 812,016,426.23 8/11/2012 14 months 83 Stalled 4 Re-dualisation of Old Police H/qtrs-Gadadin road (2.55km) Dantata & Sawoe Dutse 1,487,873,351.19 1,487,873,351.19 922,979,632.16 11/4/2013 6 months 62 On-going 5 Dualisation of Ibrahim Aliy u road (Dutse Eastern By e-pass) (5.65km) Dantata & Sawoe Dutse 2,861,812,037.79 3,160,794,816.68 2,512,869,594.04 11/4/2013 9 months 83 On-going

Constr. Of Streetlights on Dutse township roads (17.576KM) phase I 6 & II CGC Nig. Limited Dutse 666,041,660.55 666,041,660.55 543,723,853.77 9/9/2013 16 weeks 85 Stalled

Constr. Of Access road (1.92KM) at the New House of Assembly 7 Members Qtrs. Disina, Dutse CGC Nig. Limited Dutse 419,305,302.03 419,305,302.03 303,493,140.29 19/9/2013 5 months 73 Stalled 8 Constr. Of River Re- Alignment project at Dutse, phase 1 (2KM) Dantata & Sawoe Dutse 1,999,219,676.02 1,999,219,676.02 803,044,623.06 26/9/2013 6 months 40 On-going Landscaping and External works at new Jigawa State 9 Broadcasting Complex Dantata & Sawoe Dutse 657,635,647.36 657,635,647.36 457,989,460.07 31/3/2014 6 months 66 Stalled

TOTAL 11,469,579,159.00 13,297,270,952.26

Cabinet Office

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

A M OUN T (N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

1 Upgrading and Renov ation of Jigawa State Gov ernor's Lodge Anhas Nig. LTD Kano 123,614,216.81 123,614,216.81 97,062,788.87 5/11/2013 9 Months 78 On-going Commissioning as Consultant on the Superv ision of the Upgrading 2 and Renov . of Gov ernor's Lodge Kano Design+ Consultant LTD Kano 10,097,505.90 10,097,505.90 6,555,808.21 19/11/2013 9 Months 75 On-going Constr. of Juma'at Prayer Mosque at Kukuma yamma and 3 Gubabiya in Buji Constituency. Loyalty Properties Nig. Ldt. Buji 5,613,871.72 5,613,871.72 24/01/2017 6 weeks Stalled Constr. of Five (5) Daily Prayer Mosques at Dawan gawo and 4 Karkarna in Yankwashi Constituency. Granitoids Eng. Services Yankwashi 6,148,095.00 6,148,095.00 3,267,402.13 16/10/2017 6 weeks 53 On-going Construction of Five (5) daily Prayer Mosques at Makwarawa(Tofa Ward) and Dabi (Dabi ward) in Ringim 5 Constituency. Prestige Intgrt. Serv. Ringim 4,129,061.98 4,129,061.98 18/12/2017 6 Weeks Stalled Renov/Completion of 1no. Juma'at prayer mosque 2017 constituency projects phase III Remaining works (Lot-1) at 6 Garki Jibwis in Garki Constituency. JAG & H Integrated Garki 10,088,567.00 10,088,567.00 16/4/218 12 weeks On-going Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency projects) Lot-92 at Turkushawa in 7 Sule Tankarkar Constituency. Modang Invest. Ltd. S/tankarkar 2,625,238.18 2,625,238.18 17/12/2019 8 weeks On-going Constr of (3no.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-19) at Nasarawa, Dubantu and Walawa Matsaro 8 in Hadejia Constituency. Alh. Umaru Babandoki Hadejia 5,735,858.70 5,735,858.70 10/10/2018 6 weeks On-going Construction of (1NO.) Five Daily Prayer Mosque 2018 Constituency Projects (Lot-12) at Gusau in Gumel 9 Constituency. Jag&H Intgrated Services Gumel 1,882,927.00 1,882,927.00 10/10/2018 6 weeks On-going Construction of (3NO.) Five Daily Prayer Mosque 2018 Constituency Projects (Lot-29) at Santerbi Gari, Chakindi Gari 10 and Sule Bakin Titi in Sule Tankarkar Constituency. Lautai Genaral Investment S/Tankarkar 5,763,123.45 5,763,123.45 3,746,645.70 10/10/2018 6 weeks 60 On-going Construction of District Head Residence 2018 Constituency projects (Lot 1) at Tsohuwar Gwaram in Gwaraam 11 Constituency A.G.A. Kilawa Nig. Ltd. Gwaraam 55,264,747.00 55,264,747.00 18,777,191.37 10/10/2018 6 weeks 34 On-going Construction of (4NO.) five Daily Prayer Mosques 2018 Constituency Projects (Lot-18) at Zangon Kanya, Alagarno, Luggai and Tsagaiwal in Bulangu Constituency, Kafin Hausa 12 Local Government Area. Kawu Nig. Ltd. K/Hausa 7,843,906.50 7,843,906.50 14/11/2018 8 weeks On-going BAL. C/F 238,807,119.24 238,807,119.24 8a

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 238,807,119.24 238,807,119.24 Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-55) at Marken Biki in Babura 13 Constituency. Danfatu & Sons Nig. Ltd. Babura 1,577,938.00 1,577,938.00 14/11/2018 8 weeks On-going Completion/Renovation of (1NO.) Friday Prayer Mosque 2018 Constituency Projects at Suga Town in Kirikasamma 14 Constituency. Murat Construction Company K/kasamma 8,439,582.90 8,439,582.90 7,559,671.35 14/11/2018 8 weeks 85 On-going Construction of (2NO.) Friday Prayer Mosque 2018 Constituency Projects (Lot-33) at Dagilibani and Matara 15 Babba in Birniwa Constituency. Amm Manzo Nig. Ltd. Birniwa 10,008,223.63 10,008,223.63 14/11/2018 12 weeks On-going Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-67) at Gada Yamma in Kazaure 16 Constituency. Yanduna Ventures Nig. Ltd. Kazaure 3,268,000.00 3,268,000.00 23/11/2018 8 weeks On-going Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-36) at Jansa in Babura 17 Constituency. Mufabamex Concept Ltd. Babura 1,910,001.00 1,910,001.00 23/11/2018 6 weeks On-going Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-35) at Masko in Babura 18 Constituency. Mufabamex Concept Ltd. Babura 3,002,226.00 3,002,226.00 23/11/2018 6 weeks On-going Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-46) at Tsigi in Jahun 19 Constituency. Khairussabah Nig. Ltd. Jahun 3,102,667.92 3,102,667.92 23/11/2018 8 weeks On-going Construction of the (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-59) at Gatafa and Shinge in 20 Auyo Constituency. Nushe Business Resources Auyo 10,520,922.00 10,520,922.00 23/11/2018 8 weeks On-going

Construction of the (1 No.) Friday Prayer Mosque (2018 Phase 21 III) Constituency Projects at Kalagari in Kiyawa Constituency. Demastbo Ventures Ltd. Kiyawa 10,620,617.35 10,620,617.35 23/11/2018 8 weeks On-going Completion/Renovation of (1 No.) Friday Prayer Mosques 2018 Constituency Projects (Lot-57) at Ganji in Fagam 22 Constituency. Kawu Nig. Ltd. Gwaram 11,000,088.92 11,000,088.92 14/11/2018 8 weeks On-going Completion/Renovation of (1 No.) Friday Prayer Mosques 2018 Constituency Projects (Lot-55) at Marken Biki in 23 Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 3,577,938.00 3,577,938.00 14/11/2018 8 weeks On-going

BAL. C/F 305,835,324.96 305,835,324.96 8b

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 305,835,324.96 305,835,324.96

Construction of Interloking tiles and External Works at Garki Central Mosque (2018 Phase II) Constituency Projects (Lot- 24 44) at Garki Central Mosque in Garki Constituency. MMZ Garki Construction Nig. Garki 7,642,374.33 7,642,374.33 23/11/2018 8 weeks On-going Construction of the (2 No.) Friday Prayer Mosque (2018 Phase II) Constituency Projects (Lot-...) at Buro and Fadi Burgi 25 Towns in Fagam Constituency. G.M. Sara & Sons Ltd. Gwaram 10,700,387.08 10,700,387.08 23/11/2018 8 weeks On-going Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-27) at Gemu H/Tsohuwa, 26 Fantagwai and Gangawa in Jahun Constituency. A.G.A. Kilawa Nig. Ltd. Jahun 5,883,803.10 5,883,803.10 2,278,253.25 23/11/2018 6 weeks 39 On-going Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-11) atTudun Wada in Hadejia 27 Constituency. Muhal Global Concept Ltd. Hadejia 2,276,676.25 2,276,676.25 23/11/2018 8 weeks On-going Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects (Lot-9) at Lafiyan Kondiko in 28 Fagam Constituency. Ahmed Maidoya & Sons Nig Gwaram 1,960,892.42 1,960,892.42 23/11/2018 6 weeks On-going Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase III) Constituency Projects at Ashura Madaki in Jahun 29 Constituency. Mugin Investment Nig. Ltd. Jahun 1,959,335.00 1,959,335.00 23/11/2018 8 weeks On-going Constr of 2no. Daily prayer mosques (2019 first qtrs. Constituency projects) Lot-46 at Ruwan Garai and Dansure 30 Tasha in Roni Constituency. Na'ayi Resources Ltd. Roni 3,919,811.70 3,919,811.70 17/12/2020 8 weeks On-going Construction of (2N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -16) at 31 kalasu and Kukawa in Fagam constituency. Amm Manzo Nig. Ltd Gwaram 6,222,111.00 6,222,111.00 23/11/2018 8 weeks On-going Construction of (3N0.) Blocks of 2-classroom Islamiyya school typed and renovation of teachers lodge 2018 phase II constituency projects (Lot -20) at sayawa, danbando and 32 kuzunzumi/tsardawa in kanya babba constituency. Deetech Nig Ltd Babura 14,739,389.96 14,739,389.96 23/11/2018 15 weeks On-going Construction of (1N0.) Blocks of 2-classroom Islamiyya school typed 2018 phase II constituency projects (Lot -6) at 33 Kwatsatsa in Roni constituency. Na'ayi Resources Ltd Roni 3,115,354.00 3,115,354.00 23/11/2018 10 weeks On-going Construction of wall fencing and Grave yard (2018 phase III) constituency projects at U/Tudu A. in Kanya Babba 34 Constituncy. Deetech Nig Ltd Babura 15,576,291.17 15,576,291.17 23/11/2018 8 weeks On-going

BAL. C/F 379,831,750.97 379,831,750.97 8c

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 379,831,750.97 379,831,750.97 Construction of N.D.L.E.A office (2018 phase II) constituency 35 projects (lot -74) at Gumel in Gumel Constituncy. Na-bakwai Enterp. Ltd Gumel 14,701,871.63 14,701,871.63 23/11/2018 8 weeks On-going Construction of wall fencing and Grave yard (2018 phase III) constituency projects (lot -72) at kofar arewa Babura in 36 Babura Constituncy. mufabamex concept nig ltd Babura 12,752,272.00 12,752,272.00 23/11/2018 8 weeks On-going Completion/Renov. Of (1no.)Friday Prayer Mosque (2018 phase III) Constituency Projects (Lot- ) at Batatsaba in 37 Kazaure Constituency. Na'ayi Resources Ltd Kazaure 7,821,847.00 7,821,847.00 23/11/2018 6 weeks On-going Construction Of (1no.) five daily Prayer Mosques (2018 phase II) Constituency Projects (Lot-34) at Gidan Yakubu in 38 Roni Constituency. Na'ayi Resources Ltd Roni 1,959,212.85 1,959,212.85 23/11/2018 6 weeks On-going Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-31) at Rauda Y/Dutse, Karkarna "A" and Jama'ar Gabas Fulani in Yankwashi 39 Constituency. Granitoids Eng. Nig. Ltd Yankwashi 5,834,168.55 5,834,168.55 23/11/2018 8 weeks On-going Construction Of (2no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Nasakari and Danbako in 40 Garki Constituency. Mugin Inv. Nig ltd Garki 3,918,671.70 3,918,671.70 1,875,335.85 23/11/2018 6 weeks 46 On-going Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-29) at G/karfi, Limamai and 41 shinkafi in Miga Constituency. Tosarawa Global Nig Ltd Miga 5,884,568.55 5,884,568.55 3,755,045.70 23/11/2018 8 weeks 63 On-going Construction Of (3no.) five daily Prayer Mosques (2018 phase III) Constituency Projects (Lot-) at Takur Aduwa, Sabuwar 42 Tasha and Gidan Dugur in Dutse Constituency. H.M Dangara ltd Dutse 5,879,213.55 5,879,213.55 23/11/2018 6 weeks On-going Completion of Magahsala/Janazah Preparation Block, Fencing, Gate, Landscaping of Vicinity, Installation of Overhead Tanks and Supply of Ghusal Table and Trolley at Dutse General 43 Mosque. Equishare Nig. Ltd Dutse 12,332,148.96 12,332,148.96 2,113,524.61 10/12/2018 8 weeks 16 On-going Completion/Renovation of (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-41) at Sagi in 44 Fagam Constituency. A.G.A. Kilawa Nig. Ltd. Gwaram 5,391,347.85 5,391,347.85 4,668,776.01 23/11/2018 8 weeks On-going Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase II) Constituency Projects (Lot-28) at Gangawa Yankunama 45 and H/tsohuwa in Jahun Constituency. A.G.A. Kilawa Nig. Ltd. Jahun 3,920,735.70 3,920,735.70 1,587,633.60 23/11/2018 6 weeks 40 On-going Completion/Renovation of (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects (Lot-42) at Mana in 46 Fagam Constituency. A.G.A. Kilawa Nig. Ltd. Gwaram 5,391,347.85 5,391,347.85 23/11/2018 8 weeks On-going BAL. C/F 465,619,157.16 465,619,157.16 8d

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 465,619,157.16 465,619,157.16 Construction of (1 No.) Friday Prayer Mosque (2018 Phase III) Constituency Projects at Kwatamma in Kafin Hausa 47 Constituency. Mugin Investment Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 11/12/2018 8 weeks On-going

Wall Fencing of (1No.) Juma'at Prayer Mosque (2018 Phase III) 48 Constituency Projects at Wurma Town in Dutse Constituency. H.M. Dangara Ltd. Dutse 2,401,479.28 2,401,479.28 13/12/2018 8 weeks On-going Construction of (3No.) Five Daily Prayer Mosques (2018 Phase III) Constituency Projects at Shabarun Jere, Mailefe Gari and 49 Kakindi Tsuru in Sule Tankarkar Constituency. A.A. Aljazeera Agro Proc. S/tankarkar 5,884,568.55 5,884,568.55 23/11/2018 6 weeks On-going Completion/Renovation of (1No.) Friday Prayer Mosques (2018 Phase II) Constituency Projects (Lot-64) at Sabon Garin 50 Dingaya in Fagam Constituency. A.A. Aljazeera Agro Proc. Gwaram 5,729,567.56 5,729,567.56 27/12/2018 8 weeks On-going

Construction of (1No.) Friday Prayer Mosques (2018 Phase III) 51 Constituency Projects at Chakara in Fagam Constituency. A.A. Aljazeera Agro Proc. Gwaram 5,279,873.00 5,279,873.00 23/12/2018 8 weeks On-going Supply and Installation of Medical equipments to the newly 52 constructed 31no. BHC across the state. G.M. Sara & Sons Ltd. Across the state 4,129,061.98 4,129,061.98 16/4/2018 6 weeks On-going Partial works (Constr of Main mosque Lower Level Roof Slab) at K/Hausa Juma'at mosque 2018 2nd Qtr. Constituency 53 project. Shelterdom Nig. Ltd. K/Hausa 24,584,666.85 24,584,666.85 21,637,096.46 14/9/18 24 w eeks 98 On-going Completion /Renovation of (4No) Friday prayer M osques (2018 Phase II Constituency Projects (lot-61) at Kwalam Wayu, Bardu and 54 Yangayami in Taura Constituency Babandoki Gen Entr Taura 22,075,259.57 22,075,259.57 16/1/2019 8 weeks On-going Completion/Renovation of Juma'at Prayer M osques 2017 Constituency Projects Phase III Remaining Works (Lot-8) at M aje In 55 Taura constituency Nushe Business Resouces Taura 11,793,398.14 11,793,398.14 22/1/2019 12 Weeks On-going

Construction for the Construction of (1No) Daily Prayer M osque (2018 Phase III) Constituency Projects (Lot-46) at Sabon Gari ta Daya and 56 Renovation of Jabarna juma'at M osque in Jahun Constituency Khairussabah Nig Ltd Jahun 3,102,667.92 3,102,667.92 22/1/2019 8 weeks On-going Renov/Completion of 2no. Friday prayer mosques (2019 first Quarter constituency projects) Lot_91 at Danmakama and 57 Dangwanki In Sule Tankarkar Constituency. A.A Aljazeera Agro Proc. Ltd S/tankarkar 7,331,978.53 7,331,978.53 17/12/2019 8 weeks On-going Renov/Completion of 1no. Friday prayer mosques (2019 first Quarter constituency projects) Lot_82 at Bango in Fagam 58 Constituency. A.A Aljazeera Agro Proc. Ltd Gwaram 6,202,006.45 6,202,006.45 17/12/2019 8 weeks On-going BAL. C/F 568,130,357.01 568,130,357.01 8e

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 568,130,357.01 568,130,357.01 Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 49 at Butiranawa Fulani, Buduru 59 nad Fulanin Bayan Zarga in Taura Constituency. Gamdu Multi Purpose Ltd Taura 5,874,753.15 5,874,753.15 17/12/2019 8 weeks On-going Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 1 at Maro, Katangar Tsamiya, 60 Guyu, and Tsurufawa in Auyo Constituency. Gamdu Multi Purpose Ltd Auyo 7,833,028.20 7,833,028.20 17/12/2019 8 weeks On-going Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 24 at Oliya Sararin Rakuma and 61 Lungum Mutari Dankoli in Hadejia Constituency. Alh. Umaru Baban Doki Nig Ltd Hadejia 8,949,483.00 8,949,483.00 17/12/2019 8 weeks On-going

Completion/Renov. 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 57 at Kantin Waje, Tudun 62 Wada, Unguwar NTA and Yankoli in Hadejia Constituency. Alh. Umaru Baban Doki Nig Ltd Hadejia 10,339,715.08 10,339,715.08 17/12/2019 8 weeks On-going Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 30 at Jallomi Arewa, Manak and 63 Kanjiwa in Kaugama Constituency. Alh. Umaru Baban Doki Nig Ltd Kaugama 5,870,866.05 5,870,866.05 17/12/2019 8 weeks On-going Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 31 atDaneri, Kanoke and Kota in 64 Kaugama Constituency. Alh. Umaru Baban Doki Nig Ltd Kaugama 5,884,568.55 5,884,568.55 17/12/2019 8 weeks On-going Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-65 at Yayarin Tukur Yamma In Buji 65 Constituency Yayarin Tukur Nig Ltd Buji 10,318,579.38 10,318,579.38 17/12/2019 8 weeks On-going Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 10 at Kabbe, J/mesa and Kore 66 Bakwarga in Buji Constituency. Yayarin Tukur Nig Ltd Buji 3,920,345.07 3,920,345.07 17/12/2019 8 weeks On-going Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 9 at U/Malam Amadu Damisa, 67 Dambazaau Yamma and Kawaya Kudu in Buji Constituency. Yayarin Tukur Nig Ltd Buji 5,880,518.55 5,880,518.55 17/12/2019 8 weeks On-going Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 21 at Yola Kauye, Unguwar Gandu 68 and Shema in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 5,884,566.00 5,884,566.00 17/12/2019 8 weeks On-going Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-21 69 Dumbi, Yarchidau and Gurjiya in Yankwashi Constituency, Yanduna Venture Nig Ltd Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 12 weeks On-going BAL. C/F 648,226,551.16 648,226,551.16 8f

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 648,226,551.16 648,226,551.16 Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2 Constituency projects) Lot-15 at Daba, Tsohuwar Jawo, Islamiyya Layin Emilalo and Bayan 70 Lawan Yarima in Kazaure Constituency, Yanduna Venture Nig Ltd Kazaure 12,427,559.12 12,427,559.12 11/12/2019 10 weeks On-going Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 48 at Bandakado and Kuka in Sule 71 Tankarkar Constituency. HM Dagara Ldt S/tankarkar 3,918,215.20 3,918,215.20 17/12/2019 8 weeks On-going Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-79 at Komai Allah Yayi in Miga 72 Constituency Amia Integrated Service Nig Ltd Miga 10,200,863.74 10,200,863.74 17/12/2019 8 weeks On-going Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 40 at Tsohuwar Dalan, Dangoli, 73 Yandadi and Mazama In Miga Constituency. Barde Global Concept Nig Ltd Miga 7,840,683.40 7,840,683.40 17/12/2019 8 weeks On-going Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 23 at Faranunbunare and 74 Borandage in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 3,923,045.70 3,923,045.70 17/12/2019 8 weeks On-going Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 22 at Ture kwando, Unguwar 75 Yamma and Z/sainawa G/Dagachi in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 5,884,568.55 5,884,568.55 17/12/2019 8 weeks On-going Compl/Renov of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-90 at Tasheguwa in 76 Kirikasamma Constituency Manhaf Global Constr Nig Ltd K/kasamma 7,442,582.78 7,442,582.78 17/12/2019 8 weeks On-going Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 47 at Tagwayen Kuka, Santarbi and 77 Chiromawa in Sule Tankarkar Constituency. HM Dagara Ltd. Stankarkar 5,877,322.53 5,877,322.53 17/12/2019 8 weeks On-going Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-66 at Sabon Garin Rabadi in Fagam 78 Constituency NBS & Sons Nig Ltd Gwaram 9,171,846.17 9,171,846.17 17/12/2019 8 weeks On-going Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lots - 16 at galamawa, G/Biredi, 79 Sabalari, sakwaya and hausawa in Dutse Constituency. Backbone global links ltd Dutse 7,836,430.04 7,836,430.04 11/12/2019 8 weeks On-going Completion/Renov. 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 55 at Kundum, Jar kasa B/kasuwa Basirka and and bangon fulani in fagam 80 Constituency. Yayarin Tukur Nig Ltd Gwaram 9,274,972.59 9,274,972.59 17/12/2019 8 weeks On-going BAL. C/F 732,024,640.98 732,024,640.98 8g

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 732,024,640.98 732,024,640.98 Installation of solar electrification (2019 first quarter constituency project) Lot-96 at Digijin and fagam central 81 mosques in fagam constituency Lines dimensions Nig Ltd Gwaram 4,672,301.71 4,672,301.71 17/12/2019 8 weeks On-going Installation of solar electrification (2019 first quarter constituency project) Lot-95 at galambi and basirka central 82 mosques in fagam constituency Lines dimensions Nig Ltd Gwaram 4,478,167.05 4,478,167.05 17/12/2019 8 weeks On-going Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 51 at Dankama, Karkanai, 83 Burji Fulani and Kuda in Yankwashi Constituency. Granitoids Engr Services ltd Yankwashi 7,836,430.04 7,836,430.04 17/12/2019 8 weeks On-going Constr of 1No. Friday Prayer Mosque (2019 First Quarter Constituency Projects) Lot-67 at Tsakuran in Fagam 84 Constituency Isa Halilu Nig. Ltd Gwaram 9,315,820.89 9,315,820.89 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 5 atYakuda, zazzaugawa 85 and kwalele in Birnin kudu Constituency. Nushe Bus, Resources Ltd B/kudu 5,881,568.50 5,881,568.50 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 4 at Kauyen Abuja, Lemo 86 and Gidan Bello in Birnin kudu Constituency. Nushe Bus, Resources Ltd B/kudu 5,883,340.05 5,883,340.05 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 3 at Fa'a, Chagu and 87 Gudalai in Birnin kudu Constituency. Nushe Bus, Resources Ltd B/kudu 5,879,148.00 5,879,148.00 17/12/2019 8 weeks On-going Construction of 2No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 50 at Dkakawar Dinya 88 and Kangal in Taura Constituency. Dankwara M/jimina Inv. Ltd Taura 3,926,502.10 3,926,502.10 17/12/2019 8 weeks On-going Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 63 at Dirimowa in 89 Birniwa Constituency. AMM Manzo Nig Ltd Birniwa 10,518,579.33 10,518,579.33 17/12/2019 12 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 42 at magamar uku miga, 90 kikatawa miga and rugar rama in miga Constituency. Amia Integ. Serv. Ltd miga 5,880,512.85 5,880,512.85 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 41 at zangon jigawa 91 gabas, garin gami and gidan kanya in miga Constituency. Amia Integ. Serv. Ltd miga 5,880,512.55 5,880,512.55 17/12/2019 8 weeks On-going Costraction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 7 at arobade, mungolo and 92 kwanar kangire in Birnin Kudu Constituency. Nushe Bus, Resources Ltd B/Kudu 5,874,753.15 5,874,753.15 17/12/2019 8 weeks On-going BAL. C/F 808,052,277.20 808,052,277.20 8h

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 808,052,277.20 808,052,277.20 Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 6 at saboru, unguwar 93 yamma and karfawa in Birnin Kudu Constituency. Nushe Bus, Resources Ltd B/Kudu 5,874,753.15 5,874,753.15 17/12/2019 8 weeKs On-going Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 38 at Garin Malam Ali in 94 Malammadori Constituency. Ramadan Constr Nig Ltd M/madori 1,961,522.85 1,961,522.85 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 17 at Kaho, K/Malam Yahya Basirka and Sabalari in Fagam Constituency, Gwaram 95 Local Government Area. Ramadan Constr Nig Ltd Gwaram 5,877,322.53 5,877,322.53 17/12/2019 8 weeks On-going Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency projects) Lot-53 at Sabon Layi 96 K/kudu Iggi in B/kudu Constituency. Modang Invest. Ltd. B/kudu 1,954,613.85 1,954,613.85 17/12/2019 8 weeks On-going Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency projects) Lot-92 at Turkushawa in 97 Sule Tankarkar Constituency. Modang Invest. Ltd. S/tankarkar 2,625,238.18 2,625,238.18 17/12/2019 8 weeks On-going Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 68 at Malam Baki in 98 Gagarawa Constituency. AMM Manzo Nig Ltd Gagarawa 10,518,579.38 10,518,579.38 17/12/2019 12 weeks On-going Completion/Renovation of 2No. Daily prayer Mosques (2019 first Quarter Constituncy projects) Lot-54 at Takur site Layin Yan Kosai and Masajid Matawalle Old Government House 99 Dutse in Dutse Constituecy. Modang Invest. Ltd Dutse 5,143,163.38 5,143,163.38 17/12/2019 8 weeks On-going Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 69 at Mai-Aduwa in 100 Gagarawa Constituency. Modang Invest. Ltd Gagarawa 10,518,579.38 10,518,579.38 17/12/2019 8 weeks On-going Contr. of Wall Fence (2019 first quarter Constituecy projects) Lot- 81 at Dagacheri Juma'at Prayer Mosque in Birniwa 101 Constituecy. AMM Manzo Nig Ltd Birniwa 3,429,961.13 3,429,961.13 17/12/2019 8 weeks On-going Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 18 at Zango in Gumel 102 Constituency. farham synergy con. Ltd Gumel 1,958,251.05 1,958,251.05 17/12/2019 4 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 36 at Fake Cikin Gari, 103 Shuwarin Gari and Miyawo Tudu in Kiyawa Constituency. Muhal Global Concept Ltd Kiyawa 5,880,518.55 5,880,518.55 17/12/2019 8 weeks On-going BAL. C/F 863,794,780.63 863,794,780.63 8i

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 863,794,780.63 863,794,780.63 Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 37 at Majiya, Danfusan 104 and Kiyawa cikin Gari in Kiyawa Constituency. Muhal Global Concept Ltd Kiyawa 5,880,518.55 5,880,518.55 17/12/2019 8 weeks On-going Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Projects) Lot-5 at Hayatul 105 Islam and Kabal in Jahun Constituency. Sasco Multi Serv Nig Ltd Jahun 6,218,498.70 6,218,498.70 27/12/2019 9 weeks On-going Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 19 at Jugwa A, Z/Nagogo G/sarkin aska, Z/Ta Gabas and Girawa in Gwaram 106 Constituency. JAG & H Intergreted Service Gwaram 7,846,091.40 7,846,091.40 17/12/2019 8 weeks On-going Completion/Renovation of 1No.Friday prayer Mosques (2019 first Quarter Constituncy projects) Lot-89 at Tashar 107 Dankwmbo in Kanya Constituency in Babura LGA Deetech Nig. Ltd Babura 2,131,685.87 2,131,685.87 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 45 at Debe kai, Tinti and 108 Daneji Ringim Constituency. Marb eng. & Multi Serv. Ltd Ringim 5,884,568.55 5,884,568.55 17/12/2019 8 weeks On-going Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 35 at Kulluru, Harbon Mai Unguwa, katuka cikin Gari and Abarewa in Kiyawa 109 Constituency. Muhal Global Concept Ltd Kiyawa 7,834,461.60 7,834,461.60 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 31 at Daneri, Kanoke and 110 Kota in Kaugama Constituency. Danfatu & sons Nig Ltd Kaugama 5,884,568.55 5,884,568.55 11/12/2019 8 weeks On-going Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at Dankumbo in 111 Maigatari Constituency. Allah Abin Dogaro Nig Ltd Maigatari 14,500,005.00 14,500,005.00 17/12/2019 12 Weeks On-going Constr. Of JSS Science each (2019 first quarter phase II constituency projects) LOT-17 at Gumel and Garin Barka in 112 Gumel constituency. Farham Synergy con. Ltd Gumel 29,908,200.00 29,908,200.00 11/12/2019 18 Weeks On-going Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-44 at Kwai Kwayu, Kagadama and 113 Gagarawa in Ringim constituency. Marb eng. & Multi Serv. Ltd Ringim 5,884,568.55 5,884,568.55 17/12/2019 8 Weeks On-going Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at Ladin Kani in Maigatari 114 Constituency. Nadada Venture Nig. Ltd Maigatari 7,609,184.60 7,609,184.60 7/12/2019 8 Weeks On-going BAL. C/F 963,377,132.00 963,377,132.00 8j

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 963,377,132.00 963,377,132.00 Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 78 at Jobi in Maigatari 115 Constituency. Nadada Venture Nig. Ltd Maigatari 7,720,042.25 7,720,042.25 17/12/2019 8 Weeks On-going Costr.of 2No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 88 at Duzau and Danyayi in Kanya 116 Constituency. Deetech Nig. Ltd Babura 7,029,877.90 7,029,877.90 17/12/2019 8 Weeks On-going Constr. Of 4no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-29 at Karfawa, Kanawa, Adigul 117 and Balladar Kanya constituency in Babura LGA. Deetech Nig. Ltd Babura 7,824,104.04 7,824,104.04 17/12/2019 8 Weeks On-going Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-16 At Dangwabro in Maigatari 118 Constituency A.S.Maifata Gen. EntP. Ltd Maigatari 6,015,765.00 6,015,765.00 11/12/2019 8 Weeks On-going Constr. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-39 at Kkama and Kwanar Duniya 119 in Maigatari constituency Marb eng. & Multi service Nig LtdMaigatari 3,908,555.70 3,908,555.70 17/12/2019 8 Weeks On-going Constr. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-46 at ruwan garai and dansure 120 tasha in Roni constituency Na'ayi Resources Nig Ltd Roni 3,919,811.70 3,919,811.70 17/12/2019 8 Weeks On-going Supply of Science Laboratories Equipment for Distribution to Senior Sec School Across the state (2019 MOEST capital 121 project) Aldan Project Ltd Across the state 29,491,628.72 29,491,628.72 24/12/2019 8 weeks On-going Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-12 at gabari, machiba and 122 shagawa in bulangu constituency Kawu Nigeria Ltd K/Hausa 5,567,369.55 5,567,369.55 17/12/2019 8 Weeks On-going Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-20 at abena, babban gidan 123 nahuce and tsangwanwa in gwaram constituency JAG & H Intergreted Service Gwaram 5,880,512.55 5,880,512.55 17/12/2019 8 Weeks On-going Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 80 at Kaki mai wando in Roni 124 Constituency. Na'ayi Resources Nig Ltd Roni 9,527,340.25 9,527,340.25 17/12/2019 8 Weeks On-going Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-14 at kwarin bulama, S/garin 125 bulangu, mandamari sabuwa in bulangu constituency Kawu Nigeria Ltd K/Hausa 5,842,273.05 5,842,273.05 17/12/2019 8 Weeks On-going Renov. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-84 at buro and fadi gurje in fagam 126 constituency Pullad Global Consultant Ltd Gwaram 2,503,688.50 2,503,688.50 17/12/2019 8 Weeks On-going BAL. C/F 1,058,608,101.21 1,058,608,101.21 8k

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,058,608,101.21 1,058,608,101.21 Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-11 at turaka, gandu and K/bulama 127 Waek in bulangu constituency Kawu Nigeria Ltd K/Hausa 5,865,605.55 5,865,605.55 17/12/2019 8 Weeks On-going Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at Ladin kani in mai gatari 128 Constituency. Khairushabah Nig Ltd Maigatari 7,609,184.60 7,609,184.60 17/12/2019 8 Weeks On-going Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 78 at Jobi in maigatari 129 Constituency. Marb Eng. & Multi serv. Ltd Maigatari 7,720,042.25 7,720,042.25 17/12/2019 8 Weeks On-going Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 74 at gwalerima in kaugama 130 Constituency. Danfatu & sons Nig Ltd Kaugama 8,200,007.27 8,200,007.27 17/12/2019 12 weeks On-going Completion./Renovation Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-56 at magarya, 131 sabuwar unguwa and GGSS Garki in Garki constituency MMZ Garki Gen contractor Garki 4,814,329.08 4,814,329.08 17/12/2019 8 Weeks On-going Completion./Renovation Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-56 at magarya, 132 sabuwar unguwa and GGSS Garki in Garki constituency MMZ Garki Gen contractor Garki 4,814,329.08 4,814,329.08 17/12/2019 8 Weeks On-going Completion./Renovation Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-52 at argina and 133 yartsaka in Auyo constituency MMZ Garki Gen contractor Auyo 7,293,833.85 7,293,833.85 17/12/2019 8 Weeks On-going Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 74 at Ubba in kaugama 134 Constituency. Danfatu & sons Nig Ltd Kaugama 8,200,007.27 8,200,007.27 17/12/2019 12 weeks On-going Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-13 at bujaye, makera mashawai in 135 bulangu constituency Kawu Nigeria Ltd K/Hausa 5,784,568.58 5,784,568.58 17/12/2019 8 Weeks On-going Constr. Of 4no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-51 at dankama, karkanai, burji 136 fulani and kuda in yankwashi constituency Granitoids Engr Services ltd Yankwashi 7,836,430.04 7,836,430.04 17/12/2019 8 Weeks On-going

Constr of 4no. Daily prayer mosques (2019 first quarter constituency projects) Lot-19 at Jugwa A., Z/nagogo G/Sarkin 137 Aska, Z/Ta gabas and Girawa in Gwaram Constituency. JAG&H Integ. Services Ltd Gwaram 7,846,091.40 7,846,091.40 17/12/2019 8 weeks On-going TOTAL 1,134,592,530.18 1,134,592,530.18

8L

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % BAL. B/F 1,134,592,530.18 1,134,592,530.18 Constr of 1no. Friday prayer mosque (first qtr. 2019 constituency project) Lot-74 at Ubba in Kaugama 138 Constituency. Danfatu & Sons Nig. Ltd. Kaugama 8,200,007.27 8,200,007.27 17/12/2020 12 weeks On-going Completion /Renovation of 2no. Friday prayer mosques (2019 first qtrs. Constituency projects) Lot-84 at Buro and Fadi 139 Gurje in Fagam Constituency. Pullad Global Consultant Gwaram 2,503,688.50 2,503,688.50 17/12/2020 8 weeks On-going Completion /Renovation of 2no. Friday prayer mosques (2019 first qtrs. Constituency projects) Lot-83 at JIBWIS Fagam and 140 Dangulan in Fagam Constituency. Pullad Global Consultant Gwaram 4,668,587.70 4,668,587.70 17/12/2020 8 weeks On-going Completion /Renovation of 3no. Daily prayer mosques (2019 first qtrs. Constituency projects) Lot-56 at Magarya, Sabuwar 141 Unguwa and GGSS Garki in Garki Constituency. MMZ Garki Gen.Constr Ltd. Garki 4,814,329.08 4,814,329.08 17/12/2020 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 6 at saboru, unguwar 142 yamma and karfawa in Birnin Kudu Constituency. Nushe Bus, Resources Ltd B/Kudu 5,874,753.15 5,874,753.15 17/12/2019 8 weeKs On-going Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 38 at Garin Malam Ali in 143 Malammadori Constituency. Ramadan Constr Nig Ltd M/madori 1,961,522.85 1,961,522.85 17/12/2019 8 weeks On-going Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 17 at Kaho, K/Malam Yahya Basirka and Sabalari in Fagam Constituency, Gwaram 144 Local Government Area. Ramadan Constr Nig Ltd Gwaram 5,877,322.53 5,877,322.53 17/12/2019 8 weeks On-going Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency projects) Lot-53 at Sabon Layi 145 K/kudu Iggi in B/kudu Constituency. Modang Invest. Ltd. B/kudu 1,954,613.85 1,954,613.85 17/12/2019 8 weeks On-going Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency projects) Lot-92 at Turkushawa in 146 Sule Tankarkar Constituency. Modang Invest. Ltd. S/tankarkar 2,625,238.18 2,625,238.18 17/12/2019 8 weeks On-going

TOTAL 1,173,072,593.29 1,173,072,593.29 8m

Ministry of Information

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

(N ) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -

Ministry of Agriculture

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

(N ) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -

State Universal Basic Education Board

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

(N ) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -

Jigawa State Polytechnic

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

(N ) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -

Ministry of Justice

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS

(N ) CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -

Ministry of Finance

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS (N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Commission/Engagement as Consultant for the Technical consultants on Softw are Dev . Consulting in the state and 1 MDAs. (IPSAS) Sparklesoft Solutions Ltd. Dutse 19,710,000.00 19,710,000.00 16,753,528.35 10/28/2016 6 months 85 On-going

Engagement as Consultant to Recover all excess and Cot charges covering the period of April, 2013 to 2 December, 2015 (at 5% commission). Yolight Limited In the state 14/8/2018 3 months Stalled

Consultancy services fees to deliver World class 3 payment and collection on I.G.R. Ercas Solution Limited In the state 70,016,433.40 24/12/2018 On-going Engagement/Commissioning as Consultant for the reconciliation and recovery of unremitted pay as you earn (PAYE) of Staff of Federal Gov ernment Agencies Residing in Jigawa State for the period off 2002-2018(8% of N Henry Young 4 6,383,001,715.57) A n d Co. In the state 563,172,144.01 563,172,144.01 2 6 /6 /2 01 9 6 w eeks Termiated

Total 582,882,144.01 582,882,144.01

Agency for Nomadic Education

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL.STATUS REMARKS (N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Total - -

Jigawa State College of Islamic and Legal Studies

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATIONCONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENTCOMPL.STATUS REMARKS (N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Total - -

Binyaminu Usman Polytecnic Hadejia

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

(N ) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN %

Constr. of Classrooms and Laboratories complex at Binyaminu Usman Polytechnic, 1 Hadejia. DAD A.E. Nig. Ltd. Hadejia 82,582,274.72 82,582,274.72 43,106,485.97 5/1/2017 24 weeks 50 Stalled

TOTAL 82,582,274.72 82,582,274.72

Ministry of Environment

POST CONTRACT PROJECT EVALUATION S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % Constr of 2no. Township Gate in Gumel Local Government Area 2019 third quarter Constituency 1 projects Gare Invest Nig Ltd Gumel 9,099,121.73 9,099,121.73 24/12/2019 8 weeks On-going Constr of Drainage at Kamfala Town in Malam Madori LGA 2019 First Quarter Constituency 2 Project Ramadan Constr Nig Ltd M/madori 12,261,288.37 12,261,288.37 24/12/2019 12 weeks On-going Constr of Drainage at Hammado in Gumel LGA 3 2019 Third Quarter Constituency Project farham synergy con. Ltd Gumel 6,497,962.62 6,497,962.62 24/12/2019 8 weeks On-going Constr of Drainage at Marakumi Town in Malam Madori LGA 2019 First Quarter Constituency 4 Project Meyadi Concept Nig Ltd M/madori 9,923,643.97 9,923,643.97 24/12/2019 12 weeks On-going Constr of Drainage at Kargo Town in Garki LGA 5 2019 First Quarter Constituency Project Umar Aliyu & Sons Nig Ltd Garki 12,899,602.80 12,899,602.80 24/12/2019 12 weeks On-going Constr of Drainage at Kandahar in HadejiaLGA 6 2019 First Quarter Constituency Project Tasi'u Muhd Invt Nig Ltd Hadejia 19,286,864.77 19,286,864.77 24/12/2019 12 weeks On-going Constr of Drainage at Dantanoma Quarters in 7 Gumei LGA 2019 Third Quarter Constituency JAG & H Intergreted Service Gumel 7,223,498.48 7,223,498.48 24/12/2019 12 weeks On-going Constr of Drainage at Dingaya Town In Gwaram 8 LGA 2019 First Quarter Constituency Project Pullad Global Consultant Nig Ltd Gwaram 16,180,030.57 16,180,030.57 24/12/2019 12 weeks On-going Constr of Drainage at Fake in Kiyawa LGA 2019 2nd 9 Quarter Constituency Project AGM & Sons Nig Ltd Kiyawa 14,830,841.81 14,830,841.81 13/12/2019 12 weeks On-going Constr of Drainage at Makeral Kirnande in Miga 10 LGA 2019 1st Quarter Constituency Project A. Barde Global Concopt Ltd Miga 5,341,392.00 5,341,392.00 13/12/2019 8 weeks On-going Constr of Drainage at Lungun Malamai in Hadejia 11 LGA 2019 1st Quarter Constituency Project Amia Integrated Service Nig Ltd Hadejia 4,118,002.53 4,118,002.53 13/12/2019 8 weeks On-going Constr of Drainage and Culverts at Kukuma Town 12 in Buji LGA 2019 1st Quarter Constituency Project Yayarin Tukur Nig Ltd Buji 9,749,911.22 9,749,911.22 13/12/2019 12 weeks On-going Laterite filling at Shuwarin Town in Kiyawa LGA 13 under 3rd Quarter 2018 Constituency Project Khairushabah Nig Ltd Kiyawa 4,193,265.30 4,193,265.30 12/12/2019 8 weeks On-going

Total 131,605,426.17 131,605,426.17

Jigawa College of Education Gumel

POST CONTRACT PROJECT EVALUATION

S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT(N) CONTRACT SUM (N)CERTIFIED WORK (N) DATE PERIOD IN %

Total - -

Informatics Institute Kazaure

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N) CERTIFIED WORK DATE PERIOD IN % 1 Constr of 1no block of hostel (20 rooms) Babandoki Gen. Entp. Kazaure 47,989,101.98 47,989,101.98 43,155,113.32 28/6/2019 12 w eeks 86 On-going

TOTAL 47,989,101.98 47,989,101.98

Head of Service Office

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION C ON T R A C T REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

,

TOTAL - -

Government House

POST CONTRACT PROJECT EVALUATION S/N. PROJECT EXECUTOR LOCATION C ON T R A C T REVISED VA LUE OF COMMENCEMENTCOMPL. STATUS REMARKS AMOUNT CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

,

TOTAL - -

Directorate of Economic Empowerment

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -

Deputy Governor Office

POST CONTRACT PROJECT EVALUATION

S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS

AMOUNT CONTRACT SUM (N)CERTIFIED WORK DATE PERIOD IN %

Total - -