VOL. 3

Arab Republic of Ministry of Electricity and Energy Egyptian Electricity Holding Company East Delta Electricity Production Company Public Disclosure Authorized

El-Ain Al-Sokhna 2x650 MWe GAS/OIL THERMAL POWER PROJECT

Public Disclosure Authorized Environmental and Social Impact Assessment

ANNEXES Consultation Activities & Other Annexes (Volume- Ill) Public Disclosure Authorized

August 2008 ECG File No. 1312

Prepared by:

Public Disclosure Authorized Engineering Consultants Group (ECG) Bldg. 2, Block 10, El-Safarat District Nasr City 11765, Cairo, Egypt. Arab Republic of Egypt Ministry of Electricity and Energy Egyptian Electricity Holding Company East Delta Electricity Production Company

EL-AIN AL-SOKHNA 2x650 MWe GASIOIL THERMAL POWER PROJECT

Environmental and Social Impact Assessment

ANNEXES Consultation Activities & Other Annexes (Volume- Ill)

August 2008

Prepared by:

Engineering Consultants Group (ECG) Bldg. 2, Block 10, El-Safarat District Nasr City 11765, Cairo, Egypt. P.O.Box: 1167. Cairo 1151 1, Egypt. El-Ain Al-Sokhna 2x650 MWe GASlOlL THERMAL POWER PROJECT

Environmental and Social lmpact Assessment

CONTENTS

EXECUTIVE TECHNICAL SUMMARY

1. INTRODUCTION 1.1 Background 1.2 Environmental Impact Assessment of the Project

2. POLICY, LEGAL AND ADMINIS'TRATIVE FRAMEWORK

2.1 Permits Required to Construct and Operate the Power Plant 2.2 Relevant Environmental Policy, Legal and Administrative Issues 2.3 Requirement for an EIA 2.4 Scope of the ESlA 2.5 Regional Development Planning 2.6 International and National Environmental Standards1 Guidelines

3. ANALYSIS OF ALTERNATIVES

3.1 Current Situation ("No Action" Option) 3.2 Alternative Technologies and Fuels 3.3 Alternative Designs of the Power Plant 3.4 Alternative Sites

4. DESCRIPTION OF THE PROPOSED PROJECT AND THE EXIS'I'ING FACILITY

Project Infrastructure Design of the El-Ain Al-Sokhna Power Plant Process Description Operational Releases to the Environment Operational Management and Staffing Operational Environmental Health and Safety Construction Activities and Program Description of the Existing Power Plant 5. DESCRIPTION OF THE ENVIRONMENT

General Setting of the Site Soils, Geology, Hydrogeology, Topography and Seismicity Climate and Meteorology Ambient Air Quality Aquatic Environment Aquatic Ecology Flora and Fauna Ambient Noise Land Use and Landscape Character Traffic and Transport Archaeological, Historic and Cultural Heritage Socio-Economic Environment

6. ENVIRONMENTAL IMPACT ASSESSMENT

6.1 Environmental Impact Process 6.2 Air Quality 6.3 Aquatic Environment 6.4 Noise and Vibration 6.5 Flora and Fauna 6.6 Land Use, Landscape and Visual Impact Soils, Geology and Hydrogeology Traffic Socio-Economic Effects Archaeological, Historic and Cultural Heritage Natural Disaster Risk Major Accident Hazards Solid and Hazardous Waste Management Public Health Occupational Health and Safety Issues Associated Infrastructure

7. MITIGA'I'ION OF ENVIRONMENTAL IMPACTS

7.1 Introduction 7.2 Mitigation Measures During Design and Construction 7.3 Mitigation Measures During Operation 7.4 Compensation For Affected Parties

8. ENVIRONMENTAL MITIGATION AND MONITORING: ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

8.1 Objectives of the Plan 8.2 Environmental Management 8.3 Schedule and Costs for Preparation and Implementation of EHS Plans 8.4 Baseline Monitoring of the Pre-Construction Environment 8.5 Monitoring of Impacts During Power Plant Operation 9. CONSULTATION AND DISCLOSURE

9.1 Introduction and General Approach 9.2 Consultation Methodology 9.3 Phase I Consultation 9.4 Phase II Consultation and Disclosure 9.5 Ongoing Facility For Public Consultation and Disclosure

REFERENCES

ANNEXES

Annex A: Record of Consultation Undertaken by ECG and EEHCIEDEPC Annex B: Scoping Meeting Annex C: Public & Stakeholder Involvement (Mini-Meetings) Annex D: Public Consultation and Disclosure Activities Annex E: Description of Atmospheric Dispersion Model Annex F: El-Ain Al-Sokhna Power Plant Air Quality Monitoring Program Annex G: Thermal Plume Modeling

ENGINEERING CONSULTANTS GROUP

Annex A

RECORDS OF CONSULTATIONS UNDERTAKEN BY ECG AND EDEPC / EEHC

- ESlA for El-Aln Al-Sokhna Thermal Power Pro~ectNo 1312 Annex-A - Page 1 of 5 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

RECORDS OF CONSULTATIONS

The following Table provides a record of consultations undertaken during March - August 2008, in conjunct~onwith project preparation and completion of environmental documentation for preparing the EIA study report and local permitting.

Organization Name

Egyptian Electricity Holding Company (EEHC) Chairman - Dr. Mohamed M. Awad Executive Board Member, Planning, - Dr. Kamel Yassin Studies and Engineering Sector Head, Steam Power Plant Projects - Eng. Ahmed Salah Sector Head, Gas Power Plant Projects - Eng. Mohamed Abdel Bary Sector Head, Environmental Management - Eng. Maher Aziz and Studies Sector Head, Design & Research - Dr. Eng. Fathi Tahoun Consultant, Power System Design - Dr. Eng. Ms. Nahed Haggi Sector Head, Network Studies - Eng. Abdel Rahim Ahmed Helmi Sector Head, Power Plant Studies - Eng.MuradBadie

East Delta Electricity Production Company (EDEPC) Chairman - Eng. Tarek Youssef Ali

Ex-Chairman - Eng. Mahmoud Soliman Balbaa Head of Oyoun Mousa Power - Eng. Mahmoud El-Nakib Plant Head of Sectors for Studies & - Eng. Abdel-Karim Abdel Wahab Ali Research Head of Sector, Ettaqa Power - Eng. Sayyed Farag Plant General Director for Technical - Eng. Said El-Sayyed Kotb Affairs General Director for Chemistry - Chemist. Adel Abdel-Moutagalli Director of Technical Affairs - Eng. Samouil Makar

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-A - Page 2 of 5 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Organization Name Canal Electricity Distribution Company (CEDC) Chairman - Eng. Mamdouh El-Nahhass

Deputy Chalrman for Networks - Eng. Daoud Badr El-Sayyed Executive Assistant for - Eng. Essam Ed-Din Shafik Technical Affairs Egyptian Environmental Affairs Agency (EEAA) Environmental Management - Dr. Fatma Abu-Shouk Sector - Dr. Hisham El-Agamawi - Eng. Mahmoud Shawki - Eng. Amany Salah EEAA- Regional Branch - Dr. Lila El-Khouli Suez Governorate Governor of Suez - Gen. Mohamed Seif Ed-Din Galal Secretary General of Suez Gov. - Mr. Alaa Baddour President of Local People's - Dr. Eng. Mohamed Saad Counc~lof Suez General Director for Civil for - Mr. Khaled Bahgat Defence General Director for - Eng. Nazih Bakhoum Occupational Health & Safety Director for Environmental - Eng. Hassan Abu Bakr Affairs Head of Environmental - Eng. Abu El-Wafa Bashir Commission of Suez Gov. Director of Environmental - Dr. Ms. Amal Mohamed Health Dept. El-Raie Information Center - Eng. Ms. Effat Baher Soliman Egyptian General Authority for Shore Protection Chairman - Eng. Yahya Halaby Head of General Department - Eng. Naguib Adly for Shore Protection Executive Director - Ms. Waffa Mohamed Hindawi Executive Director - Ms. Rahab Abdel-Aati Allaam Supporting Engineering - Eng. Mahmoud M. Rizk - Eng. Ahmed M. lbrahim - Eng. El-Sayyed Abdel Halim El-Tohamy Egyptian General Petroleum Corporation Director for Operations - Chem. Medhat Yousef Assistant Director for Refining - Chem. Ahmed Abdallah & Industrialization Chief Assistant Engineer for - Chem. Mohamed Abdel Quality Control Moneim

- ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-A - Page 3 of 5 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Organization Name

Egyptian Natural Gas Holding Company (EGAS) Head of Division, Planning and - Eng. lbrahim Ahmed Projects Head of Division, Operations - Eng. Abdel-Hamid El- Mokaddem

City Gas Company Planning and Assessment - Eng. Gamal Amer Supply Stations - Eng. Alaa Abdel Latif Operations Affairs - Eng. Mahmoud Sallam General Organization for Physical Planning Sector Head for Suez Region - Eng. Ms. Somayyah Abdel-Salam General Manager for Planning - Eng. Mohamed El- Husseiny Suez Gulf Development Organization (SGDO) Chairman I - Eng. Essam Badawi North Suez Gulf Reconstruction Organization (NSGRO) Chairman I - Mr. Essawi Ahmed Hydraulics Research lnstitute (HRI) Chairman - Eng. lbrahim El-Desouky Hydrothermal Modeling - Dr. Yasser Shawky Director, Hydrographic Survey - Eng. Ahmed El-Sayyed Egypt National lnstitute of Transport (ENlT) Executive Director - Prof. Dr. Abdallah Wahdan

Senior Transport Expert - Dr. Ms. Enas Bushra Nashed Technical Assistants - Eng. Mohamed Hussein - Eng. Nasser Mohamed National Research Center (NRC) Air Pollution Preclusion Unit - Prof. Dr.Kamal Tamer Hindy

- Eng. Adel Hassan Amer

Water Quality Unit - Prof. Dr. Osama Ahmed Ali - Prof. Dr. Mohamed lsmail Badawi - Dr. Mohamed Bakr M. lbrahim

ESIA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-A - Page 4 of 5 HB -10 August ZOOS ENGINEERING CONSULTANTS GROUP

Organization Name Ain Shams University, Faculty of Engineering Noise and Vibration Engineering - Prof. Dr. Mansour M. El-Bardisi

Institute of Environmental Studies and Research, Ain-Shams University Ecological Studies Department - Dr. Aly Nasser Hassan

Suez Local Population Local People's Council of Suez - Dr. Mohamed Saad Governorate - Mr. Abu El-Wafa Bashir Local Council of Ettaqa District - Mr. Ahmed Mansour - Mr. Ahmed Abboud

NGOs Representatives - Mr. Gharib Abdel-Mobdiee - Mr. Gamal Abdellah - Mr. Mohamed Rashed - Mr. Ramadan Abu El-Hassan - Ms. lntessar El-Hegazi

Suez Citizens - Eng. Ali Saber El-Khatib - Prof. Dr. Mohamed Mahmoud Sayyed - Chemist. Ms. Nadia Attallah - Eng. Hassan Kamel - Journalist. Yasser El-Buaidi - Dr. Tarek El-Sayyed

Al-Watany Political Party - Eng. Ahmed Abu Nazel

Fishermen - Abu El-Maati Hammoudah - Galal Desouki - Bahgat Ali Mohamed - Hassouna Zeid Ahmed - Bahloul El-Saadawi - El-Sweissi El-Bahari

-- - ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-A - Page 5 of 5 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

Annex B

SCOPING SESSION

-- - ESlA for El-Aln Al-Sokhna Thermal Power Pro~ectNo 1312 Annex-8 - Page 1 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

SCOPING SESSION

A scoping session was held in the Castellow Hall at the Social Club in Suez District, around 15 minutes driving from the end point of CairoISuez road to the Port Tawfic area, Suez Governorate. The main goal of conducting a scoping session is to assist the East Delta Electricity Production CompanyIEgyptian Electricity Holding Company in obtaining the views of concerned parties, local NGOs and affected groups, and keeping records of meetings and other activities, communications, and comments.

The scoping session is a TOR requisite. This is the first public consultation. A second public consultation will be conducted by the end of the stage of producing the Draft Final Report to present to the same stakeholders the results of the EIA report seeking their comments - if any - to include in the final report.

Records of meetings and other activities, communications and comments will be incorporated in the final report.

Appreciating the importance of the public consultation task, the Consultant moved fast and announced about the meeting in the media (see Appendix I) and held extensive meetings with all the interested and affected parties to explain the event and its importance. Some (173) of the stakeholders attended the session and actively participated in the Questions and Answers session following the project description presentation delivered by PGESCo's General Manager, Dr. Asem El-Gawhary (Project Engineer) and project scope presentation delivered by the ECG's Project Manager, Eng. Hassan El-Banna in cooperation with the EDEPC Power Plant Sector's Manager, Eng. Tarek Youssef Aly and the EEHC's Environmental Manager, Eng. Maher Aziz.

Accompanied by the Agenda of the meeting, a concised leaflet was delivered to the attendees on the registration desk. This leaflet and an Invitation Card were distributed also by ECG, EDEPC and EEHC to their members and many other concerned parties in Suez Governorate for inviting them to the meeting. Appendix II presents the invitation card and Appendix Ill provides with the Agenda and leaflet.

The Targets of the Scoping Session

The Consultant - was assigned to do the Environmental Assessment as an independent party, not biased to any preset ideas of the owner or the designer. The scoping session is a direct consultation of the public, collecting first hand information and reactions from those who might be affected by the construction of the project. Consequently, the session was organized to include the following activities:

- Presentation of the ESIA scope as per the TOR; - Breakdown of the activities to highlight the issues that the attendees might comment on;

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 2 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

- Explain the environmental issues and invite the participants to raise their concerns about possible negative impacts; - Conduct the discussions and invite the owner, local authorities and agencies to participate in the discussions; - Clearly identify the comments and recommendations of the attendees and write all the minutes of the meeting to be attached to the Interim Report.

Attendees

A wide selection of personnel from different orientations attended the scoping session as described hereinafter. A list of names and occupations is attached in Appendix IV.

- Egyptian Electricity Holding Company (EEHC); - West Delta Electricity Production Company (WDEPC); - Al-Sokhna Power Project; - Ettaqa Power Plant; - Oyoun Moussa Power Plant; - Suez Gulf BOOT Power Plant; - National Institute for Transport; - Many Interesting Companies (SEMADCo, Fertilizers Company, Arakas for Tourism Company; - Petroleum Companies (Nasr Petroleum Company, Petroleum Pipeline Company); - NGOs (Asdekaa Society, Art Society, Environmental Protection Society, El-Kheir Society, Society, Red Sea Society); - Institute of Oceanography Sciences; - Ministry of State for Scientific Research; - Ettaqa Indigenous Population; - Representatives of Suez Community; - Consultant team; - Project Engineer (PGESCo) team; and - EEAA branch in Suez.

Meeting Procedure

Introduction

The scoping session started 11.00am in the Castellow Hall at the Social Club adequately equipped to accommodate the attendees, the representatives of the main authorities and the ECG staff in charge of the presentation.

- ESIA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 3 of 52 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

EDEPC Chairman, Eug. Iblahmoud Soliman Balbaa inaugurated the session, welcoming all attendees and giving a short speech on the EEHC/EDEPC message and the significance of the Al-Sokhna power project.

Suez Governor, Mr. Mohmed Seif Ed-Din Galal gave a warm speech considering Al-Sokhna power project a landmark infrastructure urgently needed in the Suez area. ECG Project Manager, Eng. Hassan El-Banna opened the session, welcoming and thanking the attendees and briefing them about the role of the scoping session in the EIA study. He also emphasized the importance of their input of commenting, proposing and highlighting new ideas to enrich the study output.

Project Description

ECG Project Manager invited the General Director of the Project Engineering firm, PGESCo, Dr. Asem El-Gawhary to highlight the El-Ain Al-Sokhna Power Project. Dr. El-Gawhary started with warm welcome giving thanks for the attendees. He explained the purpose of the project and provided them with basic idea about main components of the proposed power plant at the Al- Sokhna site.

Project Scope

The Chairman of EDEPC, Eng. Mahmoud Balbaa invited the ECG's Project Manager, Eng. Hassan El-Banna to present the TOR of the EIA study emphasizing the components of the study as briefed herein after.

Proiect Obiectives

The study goals are to identify the environmental and social impacts of construction and operation of the project. A team of experts in various environmental disciplines will investigate the project area and study the possible impacts.

Study area

The study area will include all aspects that might be affected by construction and operation of the project including the entire infrastructure serving the Power Plant.

Environmental Scope

The study will address all positive and negative as well as direct and indirect impacts and will conduct field measurements of baseline conditions and the contributing effects and compare with the International norms and limits as indicated hereinafter:

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 4 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Noise

Noise level will be measured in many locations within the possible affected areas. Using special software, anticipated values for the operational mode of the proposed project would be computed.

Air Pollution

Data will be collected to build a database followed by measuring the background air quality levels. The results will be analyzed and compared with the local and international limits. Additionally, a dispersion modeling exercise will be conducted for predicting maximum concentrations of pollutants and their locations during operation of the power project.

Water Quality

All available information on the available water sources will be collected in terms of quantities and quality. This database will be used for future water use.

Intake and Discharge Structures

A numerical and physical hydraulic modeling studies will be conducted for predicting thermal behaviour of cooling water after discharging to the Suez Gulf. In addition, the modeling studies will investigate best engineering design for intake and discharge structures.

Biological Life

Will study previous reports about all species living in the project area and will try to locate it on the area maps. Will also study the suitability of the environment to the seasonal species coming to the area. Study will cover terrestrial life and birds.

Solid and Hazardous Wastes

Will survey location of solid and hazardous wastes generation that might adversely affect the environment. Will propose the safe ways of its handling and locations of final disposal.

Traffic and Local Roads

Will study the road network, parking areas and pedestrian crossings in the Power Project area as well as the buses network servirlg the Power Plant. Will also study the capacity of these roads to accommodate the future projected expansions as well as the project peak traffic during construction phase.

For studying the impact of the project on the Socio-economic sectors, the Consultant will investigate the following:

------ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 5 of 52 HB -10 Augus12008 ENGINEERING CONSULTANTS GROUP

- Disturbance in social structure and development plans; - Impact on social health; - The infrastructure; - Increase in job opportunities and increase in the labor force; - Study land uses and project landscape.

All environmental alternatives will be studied to select the optimum solutions. Mitigation measures will be proposed to reduce the impact of the new activities on the environment.

Plan for Mitinatinq Proiect Neaative Impacts

Studying negative and positive impacts will lead to establishing a comprehensive management plan which will identify the mitigation measures to be implemented as part of the envisaged construction contracts and continuous operational conditions.

Institutional Su~portRequirements

The organization charts will be reviewed and modifications will be recommended. This will enable the electricity authorities to implement the environmental plan.

Develop the Environmental Monitorinn Plan

Prepare a detailed Monitoring Plan for both construction and operation phases, and continue measurements of air and water pollution during the operation phase.

The Final Public Consultation

After completing the EIA Draft Final Report, a public consultation session will be held in Suez area to present the findings of the study. Comments of the attending stakeholders will be incorporated in the Final Report.

Appendix V provides with "Presentation Slides"

Scoping Session Open Discussions

The items discussed covered most of the environmental impacts and demonstrated main concerns. 'The following are the main issues raised during the discussions.

Al-Sokhna Power Proiect

- A landscape area is proposed to be kept inside the Power Plant fence for improving the scenic impact.

ESlA for El-Aln Al-Sokhna Thermal Power Projecl No 13 12 Annex-B - Page 6 of 52 HB -10 August ZOOS ENGINEERING CONSULTANTS GROUP

- The Ettaqa District Council should review the current capacities of services as the number of workers will be increased during the construction of the new project.

Noise

- For model Predication, the condition of the worst case, not the average, should be adopted. - If the noise level is above the international standards, recommendations such as monitoring the noise level, any other mitigation measures should be adopted. - With respect to noise generated from ground traffic and equipment, the predication should be superimposed to all noise sources.

- The road network will be carefully studied. Recommendations for mitigating the direct and peak construction impacts will be prepared. - The traffic count points shall be selected very efficiently.

Power Supplv

- Electric power is available with ample capacity to meet the project requirements; - The Contractors assigned to build the Power Plant will provide emergency generating sets; - The generator's fuel will be recommended to be environment friendly.

Solid Waste

- The Power Plan should adopt practices (separation, reuse, ... etc.) of solid and hazardous wastes as per the solid waste integrated management philosophy. - Coordination between the Ettaqa District Council and the contractors for collection and disposal of solid wastes in anticipated sanitary landfill is recommended. - The ESlA study should adopt mitigation measures for hazardous wastes generated from the construction and operation of the Power Project.

Water SUPP~V

- Practices of water disinfection and tank cleaning should be adopted in order to improve drinking water quality.

Wastewater Services

- Wastewater from the new Al-Sokhna Power Plant will be disposed of through the plant sewer and the Ettaqa sanitary network in the near future.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 7 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

- The new Power Project should adopt Pre-treatment for industrial wastewaters produced from the Power Plant before discharging to the discharge facility.

Questions and Answers

The following is a paraphrasing of the questions with the questioner identified and the answer by a member of the presenters.

Mr. Ali Amin, President of Al-Wafd Committee and Member of Local People's Council of Suez Governorate.

Comment: Results from the Ettaqa air quality data has shown that background suspended particulate matters concentrations are higher than expected contribution of the proposed power plant emissions. Therefore, major air quality problems in the area are probably due to background concentrations rather than from the proposed power plant.

Question: What environmental limitations are there at El-Ain Al-Sokhna which could prevent building. 1300 MWe?

Answer: Any limitations to future power plant addition at El-Ain Al-Sokhna cannot be determined until the environmental assessment is completed.

Mr. Fawzv Ahmed Hosnev. Assistant Secretarv of El-Taaamoaa Party

Comment: Gaseous pollution presently in the area should be included in the air quality analysis.

Question: What criteria will be used for atmospheric considerations when selecting El-Ain Al-Sokhna as the site?

Answer: Previous predicting studies for similar units were used to evaluate potential pollutant levels. If additional information is needed about model used in these predictions, it can be provided.

Ms. lntessar El-Heaazy. Secretarv General of the Environment Protection (NGO)

Question: Will this project interfere with the existing environment?

Can cooling water used for the plant affect negatively the Suez Gulf?

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 8 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

Answer: The project will not have significant effect on the existing environment.

Utilization of sea water for power plant cooling is non-consumptive. Nevertheless, it is recognized that the power plant project will play an integral part in development of the east bank area and this effect will be addressed in the Environmental Assessment.

Ms. lnsaf Anwar, Member of El-Kheir Society (NGO)

Question: Did you study the effect of the power plant on shoreline and seabed in terms of erosion and sedimentation?

Answer: Complete modeling studies, numerically and physically, will be carried out by the Hydraulics Research lnstitute and their outcomes will be presented to you in the next public consultation meeting.

Dr. Tarek Sami of the Tebbin Institute for Metallurqical Studies (TIMS)

Question: The Al-Sokhna area is subject to flash flooding during specific times along the year. Did you take this into the design considerations and site selection studies?

Answer: Yes, there is a comprehensive study on geology, geomorphology and hydrogeology under implementation today, which will address all risks associated with the project, including flash floods.

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 9 of 52 HB -10 Augus~2008 ENGINEERING CONSULTANTS CROUP

Appendix I

Newspaper Advertisement for Scoping Session

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 10 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

- ESlA for El-Aln Al-Sokhna Thermal Power Pro~ectNo 1312 Annex-B - Page I I of 52 HE - I0 August 2008 ENGINEERING CONSULTANTS CROUP

Appendix II

Invitation Card to Scoping Session

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-0 - Page 12 of 52 HE - 10 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 I2 Annex-B - Page 13 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix Ill

Agenda and Leaflet

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Annex-B - Page 14 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

- ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Annex-B - Page 15 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 16 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS CROUP

JAJlsJJ+dl f-f

ESJA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 17 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 18 of 52 HB -10 August ZOO8 ENGINEERING CONSULTANTS GROUP

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 19 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix IV

List of lnvitees and List of Attendees

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 20 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

1. List of lnvitees

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 2 1 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

List ofthe Invitees Attending the Preliminary Session Held on Wednesday 2/7/08, 10 am at The Castello Hall Social Club Suez City

1. Gen/ ~ohamedSeif El Din Galal 2. DriMohamed Mosaad Ibrahim Suez Chief of the Local Council 3. Eng.1 Ahmed Abou Nazel Party General Secretary 4 Mr./ Ahmed Soubeh Shoura Council Member 5. Mr./Abd El Nasr Ahmed Peoples Assembly Member 6. Dr./Assem El Ghouhry Pegisco Consultant Oftice 1 7. Dr./Fatma Abou El Shouk Head of Central Dept. for Enviro. Assessment 8. Mr./Ramadan Abou El Hassan Head of Suez NGOs 9. Gen./Eissawi Ahmed Head of Habilitation Organization -Suez 10. Eng./Assem Badawi Head of Suez Gulf Development I I. DriMohamed Mahmoud Sayed Deputy Petroleum Eng. Faculty for environ. Head of Fire and Civil Defense , 13. Mr./ Abou El Wafaa Beshir Head of Environment Committee - People's

14. Mr./Gharib Abd el Moubdi Head of Environ. Society- El Arabeen 15. Eng./Aly Saber El Khatteeb Head of Quarry Dept. in the Governorate 16. DrJMohamed Mossad Head of People's Council in Suez 17. 1 Dr.lMohamed Tawfik Abou Ghattas ( Head of Medical Syndicate in the Governorate 18. 1 Cap./lbrahim El Kellani 1 Sports Club 19. 1 Eng. massan Abou Bakr I Environmental coordinate for Companies- Attaka 20. I Dr./Fahim Ahmed Khalifa I Deputy University Dean - Suez 2 1. 1 Mr./Ahmed Mansour I Head of Local People's Assembly-Attaka 22. 1 Dr./Amal M. El Raay I Head of Medical Precaution section

Development 44. Mr./Alaa El Din Bedour General Secretary 45. Mrsllntassar Hegazy Deputy Environment Society

- ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 22 of 52 HE - 10 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 23 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Local Council - Suez

Local Council - Suez

Local Council - Suez

Local Council - Suez

133. Abou El Wafaa Khalil Local Council - Suez 134. Ali El Sayed Local Council - Suez 1 135. Ibrahim Abd Allah Local Council - Suez 136. Talaat Fahim Local Council - Suez 137. Hussein El Sayed Local Council - Suez 138. Mohsen Ahmed Local Council - Suez 139. Zeinab El Behadi Local Council - Suez 140. Samir Abdeen Local Council - Suez 141. Ahmed El Asraa Local Council - Suez 142. Sayada Ahmed Local Council - Suez 143. Laila Moawad Local Council - Suez 144. Sobhy Mashalli Local Council - Suez 145. Ahmed Hussein Local Council - Suez 146. Khalil Salem Local Council - Suez 147. Gamal Samak Local Council - Suez

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 24 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Ser. Name Occupation 148. Talaat Orabi Local Council - Suez 149. Mostafa Aly Local Council - Suez 150. Salah Hussein Local Council - Suez 15 1. Ahmed Hussein Local Council - Suez 152. Farag Moharned Local Council - Suez 153. Shaat AbdAllah Local Council - Suez 154. Halirna El Gendy Local Council - Suez 155. Ahmed Abd El Latif Local Council - Suez 156. Ragab Abd El Nabi Local Council - Suez 157. Mansour Mohamed Local Council - Suez 158. lsmail Ahmed Local Council - Suez

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 25 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

2. List of Attendees

- - ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 26 of 52 HB -10 August2008 ENGINEERING CONSULTANTS GROUP

Scoping Session Environmental Assessment AI-Sokhna Power Project 2 x 650 MWe

Floor Attendees

Ser. Name Occupation 1. Gen/ Moharned Seif El Din Galal Suez Governor

2. DrIMoharned Saad Ibrahirn Suez Chief of the Local Council

1 3 I Mr./Mahrnoud Solirnan Balbaa 1 Head of Shark El Delta Company 1 1 1 Dr./ Laila El Khouly 1 Head of Environmental Organization -Suez I Pegisco Consultant Office 1 6. 1 Eng.1 Maher Aziz Environmental Head of Electricity Holding Company

I 7 Eng./Hassan El Banna I Project Manager- ECG

8 Eng.1 Iman Isrnail Project Engineer-ECG

9. Eng./Hassan Atta Technical Review Committee-ECG

10. Dr/Walid Hamdy Infrastructure Expert-ECG

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 27 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Scoping Session Environmental Assessment Al-Sokhna Power Project 2 x 650 MWe

Attendees List Date: 2ndof July 2008 Place: Castello Hall-Suez City

Serial Name Occupation CompanyIOthers Telephone 1 1. Ahmed Abd Allah Deputy Local Council Nasr Petroleum 3334388 2. Radwan Mohamed Environmental Affairs Suez Governorate 33 137 13 Dept. 3. Amal AbdEl Fatah Environmental Suez Governorate 33375 1 5 Inspector 4 1 Mariam Said Environmental Affairs Suez Governorate 0127059366 Dent. I 5. Fawzia Abd Allah Nasr Petroleum Nasr Petroleum 1 012312883 1 Manager 6. Environmental Affairs Environmental 0122763607 Dept.-Media Manager Affairs Dept 7. Mohamed Hafez Araks for Tourism Araks for Tourism - 0 12402658 1 Social Citizenship 8. Mohamed Abd El Lawyer City Council 0106586965 Halim Member 9. Ragab Hamed City Council City Council Member 10. Ayoub Abd El General Manager Local Moneim Peoples' Assembly 1 1. , Ahmed Khalifa Engineer City Council Member 12. Fateh Ahmed Consultant Eyoun Mousa 01271695521 Station 13. , Mohamed Scientific Consultant Engineering Faculty 0 124386743 1

15. / Motassem Abou El 1 Geologist I Suez Quarry 1 0124601 472

16. 1 Mohamed Basem I Geologist I Suez Quarry 1 0105796744 17. 1 Ezz El Din ( Photographer ( Channel (4) / 0111690029 / Mohamed 18. ( Mounir Shehata 1 Deputy Suez I Suez Governorate 1 0105545087 ~o;erkorate 1P 19. Magdi Ahmed Deputy Suez Suez Governorate 0 124942634

ember 2 1 . Essam Hassan Regional Union Board Suez 0101845143 Member 22. Ezz El Arab District Head Suez 0106027750 23. Nagat Aly Legal Consultant Suez University

------ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 28 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

1 Serial I Name I Occupation I Company/Others I Telephone 1 24. Ezzat Mohamed I Suez Quarry ) Suez Governorate 1 0 1046 14988 1 Hassan Zaki I Television Broadcast Channel 4 0123783546 1::: Aly Saber Quarry Manager Suez Governorate 0 122869848 27. Atta Saad El Din Professor Environment 1 01223622026 I I Institute 1 28. 1 Mohamed I Chief Engineer I Misr Electricity Co. 1 0168336801 1 1 I Mahmoud 1 29. Yehia Mohamed I Engineer I Suez Canal 1 0124849952

I ,I I I Organization- ~ ~~~-~- I I 30. Mohsen Mahmoud City Council Member City Council 0105267117 3 1. Mohamed Hussein City Council Member Suez University 01811465226 32. Mahmoud Riad Local People City Council 0123766489 Assemhlv 33. Abd El Halim Member of the Regional Federation 0 10 17 14 147 Mohamed Regional Federation 34. Mohamed Ahmed Member of the Regional Federation 7 Regional Federation 35. Hamed Hefney Member of the Regional Federation Regional Federation 36. 1 Mohsen Hussein I Deputy City Council I City Council 10101933463 37. Talaat Fahim ( Technical Petroleum I City Council )0124003447 Office 38. Hossam El Din City Council City Council-Suez 0123914072 Kamal Employee Canal 1 39. Awad Abou El City Council City Council-Suez 0 101 684222 1 Hassan I Employee 1 Petroleum 40. / Reda Radwan I Technical Head Suez 1 Suez Petroleum 10101987420 Petroleum ppp I 4 1. Hassan el Naggar ) Sector Head Electricity 1 Distribution Co. 42. ) Mohamed I Engineer I Delta Electricity 10161031393 Mahmoud Distribution Co. 43. Farag Soliman Public Relation Nasr Petroleum 10123226755 1 44. Aly Mansee / Journalist I Ahkbar El Yooum 1 0123376946 ( Newspaper 45. Intessar El Hegazi Secretary General Environment 0122958913 protection Society 1 46. Mohamed Tawfik , Medical Sydicate 0123730533 1 Head 47. Shadia Ahmed General Manager Educational Section 0 122290993 ppppp 48. Nadia Atta Manager Environment 0122654342 Section 49. Attia Mahmoud Secretary General Engineering Syndicate 50. Omar Attia Secretary Suez Society 0109231760 5 1. Mansour Gad City Council City Council 0107680150 Employee

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-0 - Page 29 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

Serial Name Occupation CompanyIOthers Telephone 52. Hassan Ahmed Environment Expert Environment 0105229223 Society 53. Mahmoud Amin City Council Member City Council 01 04220972 -----54. AbouElWafaa City Council Member City Council 0122777196 55. lbrahim El Said General Manager Anaka :Electrical 0623360025 Station 56. Bosina Abd El Environment Manager Electrical Company 226 1653 1 Moneim 57. Hussein Hassan City Council Member Nasr Petroleum 0111313713 58. Hayam Mohamed Environment Manager Eyoon Mossa

59. 1 Ahmed Mohamed Deputy Manager 60. Hanaa Kamal Member in Engineering Society 0 1232935 1 8 Engineering Society 61. lnsaf Anwar Member in El Kheir :El Kheir Society 0128430112 Society 62. Tarek Mohamed Delta Co. Delta Co. 0182113868 63. Gad Amro Translator 0128084418 64. WafaaAbdEl Technical Manager Suez Station 0162800626 Razek 65. Mohamed El Kalawi Member Society Society 01033610909 Development Development 66. Essam Gharib Head of Asshab Social Affairs 0123882260 Society 67. 1 Mohamed Hussein Engineer Fertilizers Co. 0104155268 68. I Mohamed Mostafa Governor Office Governor Office 0124045271 69. Fahim Ahmed City Council Member City Council 0127486932 Member 70. Sobhy Said City Council Member City Council 0123762440 Member 71. Mohamed Counselor City Council Mahmoud Member 72. Seham Hassan Environment Manager Misr Electricity Co. 01 0 1 1301 96 73. Sayed Ahmed Technical Manager Ghanam Electricity 3363706 Station 74. Ahmed Mostafa City Council Member

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 30 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

1 Serial I Name 1 Occupation I Company/Others ( Telephone 1 86. 1 Mohamed Fahmi I Head Sector I Suez Fertilizers 1 87. Mohamed Ahmed I Safety Manager 1 Shark El Delta ~0109331018 1 Electricity Co. 88. lsmail shaaban City Council Member 0121981599 89. Rashad Helal Business Man 3340202 90. Amal Harb Coordinator 3340400 9 1 . Mohamed Araf General Manager Gasco Suez 3361 776 Maintenance Manager Gasco Suez Razak Maintenance Manager Gasco Suez Assistance 94. 1 Youssef Saad Marine Engineer 95. 1 Saad Ibrahim Manager Eyoun Mossa Electrical Station 96. Aly Mohsen Project Manager Suez 0105616221 97. Sayed Mahmoud Marine analyst Red Sea Society 33 16678 98. Iman Mohamed Public Relation Suez Governorate 99. Essam Fathy Manager Suez Governorate 100. Taha Abd El Aziz Electrical Engineer Suez Governorate 101. Magdi Abou El City Council Member Suez Governorate Hassan 102. Osama Mahmoud City Council Member Suez Governorate pppp 103. Karam Allah Shabba Society Suez Governorate 7 Mohamed 104. Kamal Haky General Manager Suez Co. 0103446077 105. Fayez Ahmed General Manager Nasr Petroleum 0124439953 106. Hassan Fouad Manager Suez Co 0121233260 107. Mahmoud Abd El Industrial Safety Attaka Electrical Oll35542l5 1 Fattah Manager Station 1 108. Mohamed Reda Chemist Suez Governorate 01084791 8 1 1 109. 1 Mansour Abou El 1 Dept. Manager 1 East Delta Co. 10107164829 1 Hassan 1 10. Gharib El Saied Studies Manager Suez Governorate 1 1 1. Hassan Mohamed Manager Suez Governorate 0125253483 ' 112. 1 Youssif El Sayed I Operational Manager I Suez Co. 1 0127818786 113. 1 Mohamed Radwan ) Telecommunication I Suez Marine 0100524878 1 Manager Authority 114. Ahmed Gamal City Council Member 10100928822 1 15. Hany Mohamed Dept. Manager Eyoon Mossa 3302809 116. Hesham Mohamed El Maarif 01091 1037 1 17. Fatma Mohamed Environment East Delta for 0104021049 Specialist Electricity 118. Hossam Abd Allah Media Manager Suez Governorate 0 123772749 1 19. Arabi El Taher Safety Manager Electrical Station 0 122285297 120. Awatef Abd El Hay Manager EOC 01006005400 121. Alia Farid Member of Women Women Council 0104363020 I Council

ESIA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 3 1 of 52 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

Serial I Name Occupation 122. ( Samah Aly General Org for eldest I education 123. 1 Wung Kah Sing 1 Manager EOC EOC 10122393872 124. 1 Mohamed Youssef 1 Expert I [ 125. 1 Mohamed Samir I Architect Asdekaa Society 10101935470 126 Taher Salah I Operation Manager Suez Gulf Station 0122393871 127. Mohamed Hassan ( Human Resources Suez Gulf Station 01 633 15566 mana er Misr lran Chemist Al El Seidi Go alarathenan Pro'ect Man er 132. Taha Abd El Aziz Mana er - 133. 1 Mahmoud Soliman ( Chairman East Delta Ismailia ( 01232701 15 134. ( Assem El Gohary I Egisco Co. 10122100522 ( 135. Mohktar Abd El I Production Manager East Delta 0 122440563 1 136. 1 ~oudaA~~EL 1 Manager East Delta Maksoud ' 137. Magdi Mostafa General Manager East Delta 0122428215 138. Adel Hamdi General Manager East Delta 0127687055 139. Amani Mohamed Engineer East Delta 140. Hatem Abd El Public relation Moniem 14 1. Ramadan Abou El Regional Society Suez 0123373714 Hassan Head Tarek Youssef ( Deputy Chairman East Delta 10623360620 1 kkMohamed Taha 1 Board Member East Delta 10123485151 1 1 144. Gamal Mohamed Deputy Chairman East Delta 1 0122424373 1 ) 145. Ragaa Monir Head of Central Egyptian Co. I laboratories Electricity Transfer 146. 1 Maher Aziz I Head of Studies Egyptian Holding I Sector Co. for Electricitv 147. 1 Nahed Shalabi 1 General Manager Egyptian Co. Central laboratories Electricity Transfer

Publication

Follow up manager Eyoun Mossa for 0125654027 Electrici 15 1. Dalia Noureldin Environmental Pgesco 26 185498 Specialist 152. Assem Morsi Public relation 1 153. Mohsen Mohamed Technical Affairs ( Responsible 154. 1 Abd El Rahman I Tagammo Secretary 1 I Ibrahim I - .

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 32 of 52 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

Serial Name Occupation CompanyIOthers Telephone 155. Fawzi Mohamed Tagammo Secretary 0107181185 General 156. Reda Aly Technical Affairs Attaka Station 0623363862 Manager 157. HusseinMohamed Chemist Attaka Station 0623363862 158. Ahmed Mohamed Technician Attaka Station 0623363862 159. Abd El Moneim Technician Art Society 0123707765 Gharib 160. Osama Aly El Din Department Manager City Council 0106056440 16 1. Tarek Khalil Department Manager Electricity Holding 0 10554605 1 Co. 162. Mohamed Soliman Information System Eyoun Mossa for 0122843932 Said Manager Electricity 163. Gad El Moula General Manager Attaka Station 0188920049 Mohamed

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 33 of 52 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix V

Presentation Slides 1. Project Description Slides 2. EIA Scoping Slides

-- - ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 34 of 52 HB -1 0 August 2008 ENGINEERING CONSULTANTS GROUP

1. Project Description Slides

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 35 of 52 HE -10 August 2008 ENGINEERING CONSULTANTS GROUP

2. EIA Scoping Slides

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Annex-B - Page 36 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix VI

SELECTED PHOTOS

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 I2 Annex-B - Page 37 of 52 HB -10 Augusl2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Annex-B - Page 38 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

- - ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 39 of 52 HB -10 August 2008 ENGINEERING CONSULTANTS CROUP

ESIA for El-Ain Al-Sokhna Thermal Power P~ojectNo 1312 Annex-B - Page 40 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

-- ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 41 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

ESLA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 42 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 43 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 44 of 52 HB - 10 August 2008

ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 45 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 I? Annex-B - Page 46 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 47 of 52 HB - 10 August 2008

ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 48 of 52 HB -10 Au yt2008

ENGINEERING CONSULTANTS GROLTP

-- ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B -Page 49 of 52 HB -10 August 2008

Eh'GlNEERlNG CONSULTANTS GROUP

ESIA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-B - Page 50 of 52 HB -10 August 2008

ENGINEERING CONSULTANTS GROUP

- - -- ESlA for El-Ain Al-Sokhna Thermal Power Projecr No 1312 Annex-B - Page 5 1 of 52 HB - 10 August 2008

ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-B - Page 52 of 52 HB - I0 August 2008

ENGINEERING CONSULTANTS GROUP

Annex C

PUBLIC & STAKEHOLDER INVOLVEMENT

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-C - Page I of 8 HB -10 Augusl2008 ENGINEERING CONSULTANTS GROUP

PUBLIC & STAKEHOLDERE INVOLVEMENT

Consultation with Affected Stakeholders

Given it's broad scope, an EIA study potentially involves a large number of stakeholders. The concerns and viewpoints of all parties interested in and affected by the project should be taken into account in reaching a decision on the project. Informed views of diverse segment of the affected population are critically important to the EA process because different groups use, and are familiar with, different parts of the environment and will be affected to different degrees by the project.

Public and stakeholder involvement is particularly important to developing an understanding of the nature and extent of potential socio-cultural impacts, and to assessing the suitability and acceptability of various measures that might be employed to prevent or mitigate impacts, or to compensate affected groups for unavoidable residual effects.

Classification of Stakeholders

Each stakeholder group will have a different interest in being involved in the EA process:

The developer or proponent needs to know where to site a project and how to minimize adverse environmental impacts; and what issues are likely to be of concern to regulators and the affected community.

An investor needs to know how the impacts will affect the viability of the project and what liabilities are incurred.

Regulatory authorities need to know the extent of impacts and whether they are acceptable; and they will use EA study results to decide on their response to specific permit applications.

Government policy makers will want to know the implications of the project for other projects/plans/programs they may wish to promote.

Regional planners need to know how the project might affect or interfere with adjacent developments and land uses.

The local community and its representatives will need to know how the project's impacts will affect their quality of life.

ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-C - Page 2 of 8 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Public interest groups (i.e., Non-government organizations or NGO's) may be interested in whether the project is consistent with sound environmental management practices.

Politicians need to know who is affected and in what way, and what issues should be of concern.

Purpose of Stakeholders Consultation

The purpose of taking these viewpoints into account is to improve project viability. The World Bank (1991) has found that where such views are seriously considered and incorporated in the EA process, projects are likely to be more successful. The Bank provides some useful guidance regarding the extent and level of stakeholder involvement in the EA process in its Sourcebooks (World Bank, 1991- Chapter 7).

The purpose of the consultation effort should be:

to inform interested groups and individuals about the proposed development, its potential impacts, and measures which will lessen impacts and protect the environment;

to provide opportunities for timely feedback, (i.e. for the public to voice concerns, comment on proposals and evaluate alternatives);

to identify problems, needs and values;

to minimize misunderstandings about the scope and impacts of the project and increase public confidence in the proposed development;

to ensure decisions have adequately considered the concerns and values of the stakeholders - particularly the affected community(ies);

to seek approaches to problem solving and hopefully resolve conflicts; and

to contribute to an increased awareness and understanding of project plans and activities.

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-C - Page 3 of 8 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

PUBLIC & STAKEHOLDERS INVOLVEMENT

To : File From : Assistant Project Manager Place Ettaqa Fishing Port in Suez -Date Tuesday, 27th~une 2008

Present for the Egyptian Electricity Holding Company (EEHC) Eng. Maher Aziz Bedrous

Present for ECG Eng. Hassan Atta

Present for Fishermen 1. Abu-El-Maati Hammoudah 2. Galal Desouki 3. Bahgat Ali Mohamed 4. Hassouna Zeid Ahmed 5. Bahloul El-Saadawi 6. El-Seweissi El-Bahari

Subiect Minutes of meeting with group of fishermen.

The principal points discussed in this meeting consisted the following:

1. Where are they fishing? 2. What are the areas of good fishing activity? 3. What about fishing at Al-Sokhna Port area?

Suez Gulf at Al-Sokhna port and the power plant site is not an area for good fishing activity.

No commercial or artisanal fishing is found in this area.

They fish in the northern part of the Suez Gulf and the deep water areas.

Fishing has long historic traditions in Suez area. It represents one of the most important features of the life customs of Suez people, irrespective of its economic value.

ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-C - Page 4 of 8 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

General Authority for Fishery Development is the main body responsible of fishing activities in Egypt. Red Sea Zone for Fish Wealth - a zonal division of the General Authority - is responsible of fishery works in Red Sea, Suez Gulf and South Sinai areas, which include water surfaces extend along about 1,460 km shoreline distances.

Fishing Units licensed by the "Suez Office for Fishery" to do fishing in the Suez Gulf totals 612. Fishing Units licensed by the same Office to do fishing out of the Suez Gulf totals 157 in Suez zone and 172 in the lakes area.

There are about 34 fishing farms in Suez Governorate at Shamandourah and Kabrieet on the lakes. There are, also, 2 fishing societies and one society for fish farming.

Moreover, there is a special port for fishing activities on Suez Gulf near Suez, called At-Ataka Fishing Port, which includes necessary facilities for providing fishing boats with supply materials and fishing tools. It serves, also, as a fish unloading and exporting facility, where fish is transported to many fish markets in the neighboring areas.

Fish yield in 2007 reached about 4,231.4 tons within Suez Gulf areas and about 1,127.8 tons at Al-Ataka port and Shamandourah.

Almost no fishing activities exist in the Suez Gulf waters fronting the Al-Sokhna port shoreline and the BOOT Suez Gulf power plant as well as the El-Ain Al-Sokhna power project site. Industrial and transport activities, including loading and unloading goods, make fishing a not common activity in such an area.

The number of fishermen on the Suez Gulf utilizing the area in question is estimated to about very few or engaged in fishing part time. Traditional practice has shown that the impacts of the warm water from a power plant are highly localized. At the point of discharge the water temperature is about 8 degrees above ambient. 20-50 meters from the discharge point the temperature is 5 degrees above ambient and at 100 meters 3 degrees higher. 300 meters downstream there is no longer any difference in temperature. The fishermen generally utilize a 5km stretch, roughly 2.5km in each direction from the point of discharge.

Most of the fisheries activities in Suez Governorate are concentrated at the northern part of the Suez Gulf and the deep Gulf waters. The effects on the fisheries of warmer water returned to the water body from similar power plants along the coastal zones of Egypt are well known. Experience from about eight other power plants - located on coastal areas of the Mediterranean seas

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-C - Page 5 of 8 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

and Suez Gulf - that have operated for a number of years indicate that the overall impacts on fisheries of slightly warmer water actually are positive, and consultations with the fishermen indicate that the catches in these areas have increased rather than decreased. Since this is part-time, small-scale fisheries no statistics are available, but after many years the warmer water around the various points of discharge, is clearly perceived by the fishermen to have positive effects.

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-C - Page 6 of 8 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

PUBLIC & STAKEHOLDERS INVOLVEMENT

To :File From : Project Manager Place Egyptian Environmental Affairs Agency, Suez Regional Branch Office Date Wednesday, ~une2008 Attended by Present for the Egyptian Electricity Holding Company (EEHC) Eng. Maher Aziz Bedrous

Present for Suez Regional Branch Office, EEAA Dr. Lila El-Kholi Mr. Hussam ed-Din Abdel-Alim Mr. Tamer Moustafa Ms. Halah es-Sayyed

Present for ECG Eng. Hassan El-Banna

Subiect Minutes of meeting with group of Environmentalists at the project area

The principal points discussed in this meeting consisted of the following:

1. NOx emissions of the power plant, under all operational regimes, should be kept within the standards. 2. Combined effect of the Al-Sokhna power project and the Suez Gulf BOOT power plant, in addition to all other industrial facilities in the area must not exceed the upper background air quality limit for the Al-Sokhna area. 3. Type of pollutants emitted to the atmosphere by the power plant shouldn't exceed, when superimposed to existing pollution loads, stipulated regulations.

- ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-C - Page 7 of 8 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

PUBLIC & STAKEHOLDERS INVOLVEMENT

To : File From : Project Manager Place Local People's Council Premises in Suez Date Saturday, 21" June 2008 Attended bv Present for the Egyptian Electricity Holding Company (EEHC) Eng. Maher Aziz

Present for Local People's Council Dr. Mohamed Saad (President) Mr. Gaber Hamzawi (Secretary for industrial affairs) Ms. Omaima Moustafa (Member)

Present for ECG Eng. Hassan El-Banna Eng. Hassan Atta Ms. lman lsmail

Subiect Minutes of meeting with Local People's Council representatives.

The principal points discussed in this meeting consisted of the following:

1. El-Ain Al-Sokhna Power Project is a big regional, as well as national, project and real benefit shall be earned to the local society as well as the whole nation. 2. Benefit from the project to the Local Community mainly includes new job opportunities for graduate youth. El-Ain Al-Sokhna society is an urban-labour featured. The problem is that the second generation seeks job opportunities and the power project will provide only some of them. 3. Necessary data on socio-economic setting in the project area, including NGOs information and data sheet, will be provided to EIA preparers within one week.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-C - Page 8 of 8 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Annex D

PUBLIC CONSULTATION AND DISCLOSURE ACTlVlTl ES

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-D - Page I of I HE -10 August 2008

Ministry of Electricity and Energy Egyptian Electricity Holding Company East Delta Electricity Production Company

El-Ain Al-Sokhna 2x650 MWe GASIOIL THERMAL POWER PROJECT

Environmental and Social Impact Assessment

Public Consultation Meeting Report (PCMR)

FINAL REPORT Annex- D

August 2008 ECC File No. 1312

Prepared by:

Engineering Consultants Croup (ECC) Bldg. 2, Block 10, El-Safarat District Nasr City 11765, Cairo, Egypt. P.O.Box: 1167. Cairo 1151 1, Egypt. ENGINEERING CONSULTANTS GROUP &ZdwdwdW

Public Consultation and Disclosure and Public Consultation Meeting Report

CONTENTS

Suez Public Consultation Meeting 6th~ugust 2008: Proceedings Appendix A : Advert

Appendix B : Invitation Card

Appendix C : Leaflet 1 Agenda

Appendix D : List of Invitees and List of Attendees

Appendix E : Non-Technical Summary

Appendix F : Presentation Slides: 1. Project Description Slides 2. ESIA - Study Slides

Appendix G : Selected Photos

ESIA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 2 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Suez Public Consultation Meeting 6thAugust 2008: Proceedings

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Annex-D - Page 3 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

INTRODUCTION

PUBLIC CONSULTATION

As part of the WB's and AfDB's public consultation and disclosure requirements, EEHC & EDEPC (or their consultants) must consult and involve primary and secondary stakeholders in the planning, development, construction and operation of the proposed power plant. This includes a requirement to hold a public consultation meeting to inform all interested parties of the proposals and provide an opportunity for representations to be made.

The public consultation meeting for the proposed El-Ain Al-Sokhna Power Plant was held in Suez on 6'h August 2008. This report details the proceedings of the meeting, including the presentations that were made and a record of the Question and Answer session Consultation and disclosure to date has included private meetings, individual and group interviews with stakeholders, advertisement of the proposed plant in a local newspaper and disclosure of the Draft Final ESlA report.

PUBLIC DISCLOSURE

According to the WB's and AfDB's Environmental Impact Assessment Regulations, an ESlA report prepared for the project must be a public document such that the report can be examined by all interested parties. Copies of the report and the non-technical summary, the latter in the native language, i.e. in Arabic, were made available for public inspection in the EEHC offices and its affiliate company, EDEPC in Suez. A notice, indicating disclosure of the ESlA report for public review was published in the Al-Ahram Newspaper in Arabic on Thursday 31'' July 2008 including notice of the public meeting was given (see Appendix A).

PUBLIC CONSULTATION MEETING

INTRODUCTION

The public consultation meeting was held in the Castellow Hall of the Social Club of Suez City.

Invitations in Arabic, along with an Arabic non-technical summary were sent or hand delivered to all primary and secondary stakeholders. The list of guests was gathered in several ways: namely, those who read the newspaper

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 4 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

announcement and contacted the offices in Cairo and Suez, EDEPC guests, and a list of primary and secondary stakeholders prepared during the scoping phase and ESIA. The list of invitees and attendees is given in Appendix D. Dr. Ms. Lila El-Kholi, Head of Suez Regional Branch of the EEAA, on behalf of Dr. Ms. Mawaheb Abu El-Azm, Chief Executive Officer of the EEAA attended the meeting with a delegation from the EIA Central Department of the EEAA.

-The Suez Social Club premises, located at Suez City, before the city Stadium, is well known to the residents of the Governorate of Suez and was easily accessible to all those wishing to attend the meeting.

The meeting commenced with the arrival of Dr. Ms. Lila El-Kholi and the Representative of Dr. Mohamed Saad, President of the Local People's Council of Suez, Mr. Abu El-Wafa Bashir, Head of Environmental Committee of the Local People's Council. The representative of the Governor of Suez, Mr. Alaa Baddour, Secretary General of Suez Governorate gave his apology at the last moment. The meeting was chaired by EDEPC.

The succession of presentations that took place were as follows:

Opening Address (Eng. Tarek Youssef Ali - Chairman, EDEPC). The EEAA Representative's speech (Dr. Ms. Lila El-Kholi). The Local People's Council Representative's speech (Mr. Abu El-Wafa Bashir). Technical description of the project by PGESCo (Dr. Asem El Gawhary - PGESCo's General Manager). Findings of the ESlA by Engineering Consultants Group (ECG) (Eng. Hassn El-Banna, Manager of El-Ain Al-Sokhna ESlA study project). Question & Answer session (Conducted by Eng. Maher Aziz Bedrous - Counsellor for Environmental Studies, Egyptian Electricity Holding Company). Coffee Break.

Each participant was given a leaflet on arrival which outlined the agenda of the meeting, along with some background on EDEPC Company and EEHC's commitment to environmental protection (see Appendix C). Additional copies of the non-technical summary were available as well as the ESlA Draft Report.

The presentations lasted approximately 80 minutes and the Question & Answer session for approximately one hour and was followed by soft drinks and cake. A brief outline of the presentations given by representatives of PGESCo and ECG is given below. 'The slides used in each presentation have been provided in Appendix F. The speeches given by EEAA representative, the Local People's Council Representative and Eng. Tarek Youssef Ali, Chairman of the EDEPC are transcribed below. A record of the proceedings of the Question & Answer session follows.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-D - Page 5 of 16 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

PRESENTATIONS

Eng. Tarek Youssef Ali (Conducted in Arabic)

Eng. Ali welcomed the audience to the meeting and conveyed greetings of Dr. Mohamed Awad, Chairman of the EEHC, who had an urgent meetiqg, which prevented him from attendance. He explained the role of the EDEPC Company, some key technical and managerial figures, key principles of EDEPC when running electricity generating projects and gave an indication of EDEPC's operation philosophy. He also explained the status of the El-Ain Al- Sokhna super-critical steam power project.

Eng. Ali, then gave the speech of Dr. Mohamed Awad, on behalf of him. He said:

"On behalf of the Ministry of Electricity and Energy, I welcome all of you. It is my pleasure to meet with you regarding the extension of our activities in Suez Governorate, and the execution of one of the most important projects in the southern part of Suez and in Egypt. The power station of El-Ain Al-Sokhna shall supply and cover the electricity needs for new projects in the area and in E~Ypt.

With good co-operation between Egypt and the international and regional banks, e.g. World Bank and the African Development Bank, this project has been decided to be executed through several international biddings.

I hope that today we will listen together to the PGESCo and ECG presentations and the good findings of their environmental study of the power plant which has been implemented in deep collaboration with EDEPC and EEHC.

The strategy of the EEHC is to put environmental considerations as the highest priority.

I wish EDEPC and our consultants all success and many thanks to the governor of Suez, Suez People's Counsel, Suez Community & NGOs and all of you".

Dr. Ms. Lila El-Kholi (Conducted in Arabic)

Dr. El-Kholi welcomed the attendees and introduced the EEAA Environmental Protection Strategy. She said that in the commencement of 19901s,the United Nations announced that Environment and Development are not contradicted. They can go hand in hand. Together they represent two faces of the same coin. She added that without conserving the environment and protecting it against deterioration, development will lack necessary background that receives its outcomes, and without development no progress mankind can achieve for supporting environment preservation. The issue, then, is not to decrease

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-D - Page 6 of 16 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

development for abating pollution, but to continue development in such ways that are effective, clean and sustainable.

Ms. El-Kholi Said: "The Environmental and Social Impact Assessment has become a necessity for incorporating environmental safeguard measures into design of the projects in early phases of implementation".

"Thank you for inviting EEAA. I am actually eager to listen to the outcomes of the ESlA of the El-Sokhna project and see how it considers all necessary aspects for preserving the environment".

2.2.3 Mr. Abu El- Wafa Bashir, Local People's Council's Speech (Conducted in Arabic)

"This meeting raises an important issue and a responsibility that we all must carry in order to balance sustainable development as well as the safeguarding of the environment.

With this important project that will enhance the Suez Region, including Ettaqa, with electricity supply in accordance with international standards, we provide a leading model in development, based on friendly environmental standards.

I would like to thank all of you for coming to this meeting and I am looking forward to seeing interaction between the project's owner, i.e. EDEPC and the audience".

Dr. Asem El-Gawhary (PGESCo) (Conducted in Arabic)

Dr. El-Gawhary outlined the technical specifications of the El-Ain Al-Sokhna super-critical steam power plant. This presentation included the site location and a description of the key features and main characteristics of the power project.

It, Also, included key dates, investment costs, employment opportunities, program, consents and commitments.

Eng. Hassan El-Banna (ECG) (Conducted in Arabic)

Eng. El-Banna presented the findings of the Environmental and Social Impact Assessment. The presentation included a description of the ESlA process, the key findings for each environmental aspect and a description of the Environmental and Social Management Plan.

Dr. Ahmed El-Sayyed, of the Hydraulics Research Institute was invited by Eng. El-Banna to present the preliminary results of the numerical hydraulic modeling study of the CWDS of the power plant project.

- ESlA for El-Ain Al-Sokhna Thermal Power Projecl No 1312 Annex-D - Page 7 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

QUESTION AND ANSWER SESSION

The Question and Answer session was conducted in Arabic by Eng. Maher Aziz Bedrous, EEHC's Counsellor for Environmental Management and Studies. The proceedings have been translated as accurately as possible. In order to demonstrate that the issues and concerns have been addressed, where applicable, a reference to the Environmental and Social Impact Assessment Report undertaken for the project has been given, in addition to further clarification, shown in italics.

QUESTION 1 :Mr. Ahmed Mohamed Atawi (Suez Citizen)

How and why did you choose this location for the El-Ain Al-Sokhna Plant?

Eng. Tarek Youssef (EDEPC)

The location for the power plant was selected at El-Ain Al-Sokhna on the same land allocated in 1999 for a Steam Power Generating Facilities near the Suez Gulf shoreline, because the plant uses up to 46 m3 per sec. i.e. 165,600 m3 per hour of water for cooling. Therefore, the farther we are from the water source and from this source of cooling, the more expensive it becomes to transport the water. Consequently, the price per kW would increase due to the need to pump the cooling water larger distances. When choosing the location, we abide by Egyptian laws and regulations, particularly to the guidelines of the Ministry of Water Resources and Irrigation, to those of the Egyptian Environmental Affairs Agency (EEAA), and finally to Environmental Law 411 994.

No need to mention that the location also has the advantage of being near the center of loads. We are certain and confident that there will be no environmental problems.

The site selection was predetermined by EEHC. The site is considered suitable for a number of reasons, including its direct access to the natural gas, the industrial nature of the area, existing infrastructure and proximity to the Suez Gulf. The findings of the ESlA show no significant impact given the implementation of the various mitigation measures. It is considered that the site selected for the power plant is appropriate.

Further details of the site selection process are available in Sections 3&4 of the ESIA.

QUESTION 2: Dr. Mohamed Tawfik Abu Ghattas (Representative of Physicians of Suez Governorate)

Can we use the Suez Gulf at the El-Ain Al-Sokhna project location for other purposes, such as fishing? and what about the cooling water recirculation as

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 8 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

the intakes and the discharges of both power plants are so close to each other?

Eng. Maher Aziz (EEHC)

The plant is located in an area reserved for power generation activities. It is also an industrial zone. Therefore, we shall not have any further impacts or influences on the usual activities linked with the Suez Gulf.

As for fishing activity, the area itself is not an area for commercial or artisanal fishing. But the warm mixing zone formed by warm cooling water discharged from the Suez Gulf BOOT power plant has created a good environment for fish growth, and about 6 boats are seen every evening for fishing in the mixing zone. This is a good proof of the positive impact of the power project on fish wealth in the area.

Concerning recirculation of cooling water, PGESCo has designed the intake and discharge of the new power project such as the warm water will be in between both of the power plants, while cool water will enter from the outer sides, which will enhance preventing recirculation.

QUES TlON 3: Dr. Sherif El-Gawhary (NGOs Federation of Suez Governorate)

Wastewater may cause bad effects. Is any regulatory body review the ESlA report?

Eng. Tarek Youssef Ali (EDEPC)

As for wastewater, we have undertaken the ESlA study which will be presented to the EEHC, the concerned competent authority and the Governorate of Suez, the Licensing authority who in turn will send it to the EEAA. The EEAA will review the report and return their comments to the EEHC. These comments will be reviewed by EEHC, EDEPC, ECG and PGESCo and amendments and modifications will be incorporated in the report. Once all this is done, the environmental permit will be issued.

QUESTION 4: Eng. El-Arabi El-Taher (Suez Gulf BOOT power plant)

What about the sewage from the plant?

Eng. Hassan El-Banna (ECG)

The sewage will be discharged to the plant sanitary wastewater treatment system. Treated wastewater will be directed to the plantation irrigation system and the sludge will be transported by licensed contractors to licensed dump

- - ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 9 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

sites. When the local sewer network of Ettaqa reachs the area in the future, sewage will be discharged to the local sewer system of the area, i.e. to the local sewer network at Ettaqa. Regarding EDEPC, this is a National Electricity Company, and they consider environmental protection on top of their highest priorities. See Section 8 of the ESIA.

QUESTION 5: Dr. Yousry Abdel Aziz (Suez Canal University)

Many details have been presented on the concentrations of emissions and how they are complying with the standards. It was better if the ESMP was presented in such details.

Eng. Maher Aziz (EEHC)

The outcomes of the ESIA study have been presented in a relatively long time and ESMP tables were also highlighted briefly. It would take much more time if these tables are presented in more details. But the whole volume of the ESIA study and the twelve baseline studies are available at the offices of EDEPC and EEHC for anybody to review.

QUESTION 6: Dr. Yousry Abdel Aziz (Suez Canal University)

If an environmental standard of the EEAA is more stringent than that of the World Bank, which one you will follow?

Eng. Maher Aziz (EEHC)

Certainly we must comply first with the national standards. Actually we comply with both of the EEAA and the World Bank standards whichever more stringent.

QUESTION 7: Eng. Taher Salah El-Shahawy (Egyptian Operating Co. S.A.E)

Don't you think that the stricter standards are much better for the sake of our environment? I believe that the more stringent the standards are the much better the situation is for our country.

Eng. Maher Aziz (EEHC)

It is not a matter of stringent standards. We are concerned about the soundness of the environment but stricter standards may obstacle development. We couldn't be stricter than the World Bank or the US-EPA because the WB and US-EPA with their current standards preserve the environment. We need development as well. We are a developing country and it is not wise to adopt stricter standards that prevent development and say we

ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-D - Page 10 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

preserve environment. I believe that the issue is to achieve the best reconciliation between environment, i.e. stringent standards and the development. We need development but in terms of sustainability.

QUESTION 8: Mr. Hassan Abu Bakr (Suez Citizen)

Why the new Al-Sokhna power project doesn't use closed circuit for cooling the condensers?

Eng. Maher Aziz (EEHC)

There is a huge resource of water near the plant site, the Red Sea. Cooling water required for the condensers is a large quantity of water, almost 165,600m3/hr, but represents only a very small incremental volume of the Red Sea flow at the Al-Sokhna segment. If this quantity of water provided for a closed circuit system, there will be significant impacts, either environmentally or economically.

Also, there is an important consideration for the efficiency of the plant. Closed circuit cooling system decreases the efficiency of the plant with about 4% loss. This considerably affects the fuel consumption, emissions to the air and economics of operation.

Finally, the question is: why you go to use closed circuit whilst you have plentiful water supply and all you do you only bypass this water through the plant and discharge it again to the water body with almost no effect?

QUESTION 9: Dr. Fikry Ashour Mourad (National Institute for Oceanographic Studies & Fishery)

The impact of the power plant on sea organisms, as Eng. Hassan El-Banna has presented, will be very minor or even nothing. I totally contradict with this conclusion. 'The impact of the power plant is very significant on marine organisms and the area should have a biodiversity of organisms in contrary to what has been presented to us.

Also, the power plant is designed and operated in conformance with industrial country's cold waters, but not adapted to national circumstances. Accordingly, the chlorine dosage for destroying algae deposition on the intake screens is not specified to our sea waters' circumstances. This should be reviewed and more-controlled.

Eng. Maher Aziz (EEHC)

The impact of the power plant on marine organisms may be significant in a very localized scale. Thermal plume is discharged from the outlet of the Circulating Water Dischrge System of the power plant at 9.6 OC at the point of discharge, but it is decreased to about 5 OC within a distance 100-150 m and

- - ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 1 1 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

continue to fall down to about 3 OC within another 100 m distance, where organisms highly welcome this warm water environment.

Thus, if there is a severe marine environmental conditions against organisms within first 100-150 m, these conditions become favorite afterwards, and this is very limited and very localized effect, provided that huge volumes of water are available for normal organisms life beyond the severe short distance from the plant outlet.

As for chlorine dosage for cleaning the intake screen from algae deposition, we very much thank you for your instructive comments and a recommendation is forwarded to PGESCo, the project engineer, for checking chlorine dosage with regard to the warm water characteristics of the localized environment.

QUESTION 10: Dr. Mohamed Tawfik Abu Ghattas (Representative of Physicians of Suez Governorate)

I have two questions:

First, During commissioning period of the Al-Sokhna power plant, there will be intermittent high noise impacts. What are your plans for abating those impacts?

Second, Concerning noise impacts, will the monitoring program include noise measurements during the operation of the plant, e.g. every certain period of time?

Eng. Tarek Youssef Ali (EDEPC)

First, Usually we use noise silencers during power plant commissioning. These silencers will be used for the commissioning of Al-Sokhna power project. Also, there will be an awareness program for the neighboring facilities to take into their consideration noise impacts associated with commissioning.

Second, Monitoring program during construction and operation includes periodic measurements for noise impacts.

QUESTION 11: Mr. Abdel- Hamid Kamal (Writer in Sawasia and El-Ahaly Journals)

There are already many industrial facilities in the area of Al-Sokhna district. The new Al-Sokhna power plant is considered a significant industrial addition in the area. Would this addition have a negative effect on the place? What about wastewater?

As a Suez citizen, I see that all these plants have a negative impact as they emit pollutants to the atmosphere.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 12 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Eng. Tarek Youssef Ali (EDEPC)

Having many industrial facilities in this area is not a problem. The criteria always is that their combined impact shouldn't exceed permissible limits. For example in Cairo North, there are three plants close to each other, and they are not the cause of pollution in north of Cairo. On the contrary, this power plant is essential to the area, as well as Egypt, because of the increasing electricity demand. New developments are growing, therefore importing electricity would be far more expensive for Egypt.

Furthermore, Suez will benefit from the plant because the surplus of electricity can be exported to Jordan or Libya. Please note that when EEHC (previously EEA) built the old Suez power plant there were no comprehensive environmental standards. Today, we are controlled by these standards. Additionally, at EEHC, we refuse investments that do not respect the environment. As for electricity produced by gas firing, it is not a polluting industry like cement or petrochemicals.

Let me insure something concerning wastewater discharge: for the permanent type of wastewater discharge, we have a complete treatment scheme. The EEHC and EDEPC very keen on implementing the same standards in all the new plants, as in the Unified System plants such as Oyoun Moussa, Sidi Krir, Cairo North and Ettaqa.

Finally, this is a very good location for the power plant because there are reasonable infrastructures and the use of Suez Gulf for cooling renders it economically efficient.

QUESTION 12: Mr. Hassan Abu Bakr (Suez Citizen)

I think the project will benefit the area from an infrastructure point of view. I have a number of questions however:

First, will the 9.6 "C temperature difference be at the discharge point, or in the mixing zone?

Second, did you study the water flow and the Suez Gulf currents in the area? Third, by increasing the temperature of the water by few degrees centigrades, will there be an impact on the fauna?

Eng. Hassan El-Banna (ECG)

First, the power plant will be built according to the standards of the Egyptian Environmental Laws. Law 4 of 1994 issued for the protection of the environment states that, the temperature of the water that goes out in the sea should not exceed that of the surface water by 10°C and the maximum surface temperature should not exceed 38°C.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 13 of 16 HB - 10 August 2008 ENGINEERING CONSULTANTS GROUP

In the mixing zone the temperature of the water will have decreased to 5OC at 100-150 m from the discharge point. We are therefore within the limits of Law 4 of 1994.

The discharged cooling water will be around 9.6OC above the ambient temperature at the point of discharge.

Thermal modeling was undertaken to determine the excess temperature above ambient conditions. This modeling included water flows and Al-Sokhna Suez Gulf segment currents.

A temperature increase will lead to localized impacts on the aquatic fauna and flora, but impacts are not considered significant. See also Section 6.3.3 of the ESlA Report.

QUESTION 13: Mr. Abdel- Hamid Kamal (Writer in Sawasia and El-Ahaly Journals)

It is mentioned that There are no impacts on fisheries, the study states, could you tell us where ECG did the ESlA study? Did they co-operate with the General Authority for Fishery Development (GAFD)?

What about the job opportunities available for the citizens of Suez Governorate, particulary Ettaqa District?

Eng. Maher Aziz (EEHC)

With respect to the fisheries, there will be no significant impacts however, the warm water in the mixing zone may attract fish and provide good conditions for fish growth. This is experienced in Shoubrah El-Kheima and Ettaqa and almost all EEHC's power plants.

Furthermore, the ESlA has conducted a number of studies in the Al-Sokhna location, involving the National Research Center.

Consultations have also been undertaken with GAFD and representatives of fishermen in the area.

Regarding job opportunities, it is true that there will be about 2000-2500 jobs available during the construction phase. There will also be services such as transportation for the workers. Most of the people employed in the plant- as the Chairman of EDEPC said- will be from Suez Governorate.

The GAFD were consulted as part of the public consultation process. Fisheries are discussed in Section 6.3.3 of the ESlA Report.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 14 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS CROUP

QUESTION 74: Dr. Sherif El-Gawhary (NGOs Federation of Suez Governorate)

I am very pleased with this civilized discussion about the impacts of such a development on the environment. It is a large improvement that the stakeholders take part in this consultation. However, I have some additional comments and questions:

First, the questions asked here should have been written down in advance.

Second, it seems to me that the ESlA does not include anything about seismic issues or earthquakes.

Third, I believe that the plant should have its own fuel combating equipment against spills to protect the water intake.

Fourth, I noticed this is a sensitive environment, in recovery from previous and present pollution due to industrial growth. This is why we need to protect the aquatic life and fisheries and we must set standards for the recovery of these.

Fifth, you said there is almost no aquatic life in the place of the power plant. Is this statement true and confirmed and are there studies?

Eng. Maher Aziz (EEHC)

The plant will have an Emergency Action Plan. This plan identifies all the risks that may occur and how to mitigate them. It is only used in case of emergency and there are precautionary measures, routinely implemented for normal operations.

About earthquakes, CSC Consulting Firm, in collaboration with the National Research Institute of Astronomy and Geophysics, did a simulation study on the intensity and occurrence of earthquakes in the area and presented us with their conclusions. The ESlA takes them into consideration, translates them into codes for planning, designing and constructing buildings. These are called building codes for earthquakes.

The study of the plant also shows a continuous monitoring program for water and air quality at all stages. This is clear from Tables 3 through 6 in the Executive Summary, which show the emission levels during construction and operation and the management of these.

At all stages, I believe that it is a very rigorous plan. About the air quality, the ESlA is based on a sophisticated mathematical dispersion model. The power plant is operated continuously with natural gas and in case of emergency, it will use mazout. However, this nearly never occurs (only about 2% of the time all over the year) and if it does, it will only be for a few hours. This explains the tolerance of pollutants if mazout is used. In addition, in case of continuous operations using natural gas, the emissions will not exceed the Egyptian Standards which are respected as national standards by the World Bank and the African Development Bank.

-- - ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Annex-D - Page 15 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

About seismicity, it is evident that different sites have different risks. The Consultant studied those risks and the EEHC took the decision of building the power plant given full knowledge of these risks.

See Section 6.3.3 of the ESlA for details of the Suez Gulf water / aquatic studies that were undertaken for the project.

Eng. Tarek Youssef Ali (EDEPC)

As you know, the area around the power plant site is an industrial area. This shows there are environmental impacts to development, but also economic considerations in the sense that one has to balance the needs for electricity and the protection of the environment.

Mr. Abdel- Hamid Kamal (Writer in Sawasia and El-Ahaly Journals)

We would like to thank you for protecting the environment and complying with Law 411994 standards and guidelines. We all know that the industrial establishments have all contributed to the pollution of Egypt's environment. I hope the Governorate of Suez will impose regulations to treat the different industrial effluents before discharging into the Red Sea. Finally, the people of Suez are supporting the project.

Eng. Tarek Youssef Ali (EDEPC)

If you would like to raise any clarifications on today's discussions, please contact the East Delta Electricity Production Company and PGESCo as the developer of the project and their consultants. Finally, we would like to thank you for attending this public consultation.

THE PUBLIC CONSULTATION MEETING FINISHED AT 2:OOp m.

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Annex-D - Page 16 of 16 HE - 10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix A

Advert

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 I2 Appendix-A - Page I of 2 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Appendix-A - Page 2 of 2 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix B

Invitation Card

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Appendix-B - Page 1 of 2 HE - I0 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Appendix-B - Page 2 of 2 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix C

Leaflet I Agenda

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix-C - Page I of I H B - I0 August 2008

ENGINEERING CONSULTANTS GROUP

Appendix D

List of lnvitees and List of Attendees

- ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Append~x-D- Page I of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

I. List of lnvitees

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Appendix-D - Page 2 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

List ofthe In vitees Invited to the Consultation Meeting Held on Wednesday 6 August 2008, I0 am at The Castellow Hall, Social Club, Suez City

Ser. Name Occupation 1. Dr. Ms. Mawaheb Abu El-Azm Chief Executive Officer, EEAA I 1 2. / Dr. Ms. Fatma Abu Shouk 1 Head of EIA Division (EEAA) 1 3 ( Dr. Hirham El-Agamawi General Director of Power Projects, EIA Department, EEAA Eng. Mahmoud Shawki General Director for Industrial Projects, EIA ".T - 5. Dr. Eng. Hafez Salmawi Managing Director, Egyptian Electrical Utility and Consumer Protection Regulatory Agency 1 6. 1 Eng. Hassan Nagm Chairman of Egyptian Electricity Transmission 1 Company (EETC)

1 7. 1 Dr. Eng.- Mohamed Awad I Chairman, EEHC 8. Dr. Eng. Kamel Yassin Executive Board Member for Planning, Research and Service Companies Affairs, EEHC 9. Eng. Ms. Fawziyya Abu-Neima Executive Board Member for Affiliate Companies, EEHC 10. Acc. Salah Awad Executive Board Member for Economic, Financial & Administrative Affairs, EEHC 1 I. Dr. Eng. Amal Khashab Sector Head, Information Department, EEHC - -- 12. Dr. Ms. Nahed Haggi Consultant, Research & Testing, EEHC Head of Sector for Environmental Management 13. 1 Ena.w Maher Aziz Bedrous Studies 14. Eng. Ahmed Salah Sector Head for Steam Power Projects, EEHC ( 15. 1 Eng. Mohamed Abdel Bary I Sector Head for Gas Power Projects, EEHC I

16. Eng. Ahmed Hassan General Director for Civil Works, EEHC -

18. Ena. Mourad Badie ( 19. 1 Eng. Mohamed Et-Tablawi I Power Plants Studies, EEHC 1 - - 1 20. 1 Eng. Ms. Dalia Nour Ed-Din / Environmentalist, PGESCo 1 -- I 2 1. Eng. Anob Condo 22. Eng. Sherif Shetta Assistant Eng., PGESCo 23. Eng. Gasser Saber Project Eng., PGESCo 24. Eng. Ashraf El-Far Executive Assistant, PGESCo I 25. I Mr. Gobal I Talkha Project Manager, PGESCo I 26. Eng. Ashraf Nassar General Director of Power Projects, PGESCo

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 I? Appendix-D - Page 3 of 14 HE -10 August 2008 ENGINEERING CONSULTANTS GROUP

Ser. Name Occupation 27. Mr. Serage Eddin El-Sayyed Environmental Quality Sector, EGPC 28. Ms. Amani Selim Environmental Quality Sector, EGPC 29. 1 Eng. Abdel Rehim Salah I Egyptian General Petroleum Corporation 1 30. 1 Chem. Hassan Akl I Egyptian General Petroleum Corporation I 3 1. Dr. Hamed Korkor Technical Expert, EGAS 32. Ene. Sherif Ismail Chairman, EGAS " I 33. 1 Eng. Ibrahim Ahmed I Deputy Chairman, EGAS 1 34. 1 Eng. Abdel-Hamid El-Mokaddem I Deputy Chairman, EGAS I 35. Mr. Hemdan Abdel-Sattar Deputy Chairman, General Authority for Fishery Development (GAFD) 36. Dr. Al-Sayed Tawfik Moustafa Department of Fish Resources (GAFD) 37. Dr. Magdi Abbass Saleh Aqua-culture Specialist (GAFD) 38. Eng. Farag Mahmoud Yamani Chairman, Egyptian General Authority for Shore Protection 1 39. 1 Eng. Attia Ibrahim Omar Sector Head, Studies & Research, I Egyptian General Authority for Shore Protection 40. 1 Dr. Ali Abdel-Azim Toailab Chairman, National Research Institute of Astronomy & Geophysics (NRIAG) 41. Dr. Salah El-Hadidi Ali Associate Professor, NRIAG i 42. 1 Dr. Ahmed Badawi I Associate Professor, NRlAG I 43. Eng. Ibrahim A. El Desouky Deputy Director, Hydraulics Research Institute 44. Prof. Dr. Kamal Tamer Hindi Air Protection from Pollution Unit, National Research Center 45. Prof Dr. Aleyya Abdel Shakour Air Protection from Pollution Unit, National Research Center 46. Chem. Yasser Hassan Ibrahim Air Protection from Pollution Unit, National Research Center 47. Eng. Adel Hassan Amer Air Protection from Pollution Unit, National Research Center Water Quality Unit, National Research Center

-- ~~~ Water Quality Unit, National Research Center --49. Prof Dr. Mohamed Anwar El-Dib 50. Prof Dr. Mohamed M. Al Abdi 5 1. Prof Dr. Osama Ahmed Ali Water Quality Unit, National Research Center 52. Prof Dr. Mohamed Ismail Badawi Water Quality Unit, National Research Center 53. Dr. Mohamed Bakr M. Ibrahim Water Quality Unit, National Research Center 54. Prof Dr. Mansour M. El Bardisi Noise Engineering, Faculty ofEngineering, Ain Shams University 55. Prof Dr. Abdallah Wahdan Director, Egypt National Institute of Transport (EN IT) 56. Dr. M. Mahmoud Bassvoni Senior Transport Expert, ENIT

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Appendix-D - Page 4 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Ser. Name Occupation I 57. Dr. Khaled Nabil Helaly Transportation & Traffic Planning, Faculty of I Engineering, Cairo University I 58. 1 Prof. Dr. Mohamed Yousry / Transportation & Traffic Planning, Faculty of I Engineering, Al-Azhar University 1 I 59. 1 Dr. Alv Nasser Hassan 1 Ecological Studies Department, Ain Shams I University 1 60. Dr. Fathi Bekhit Shenodah ) Head of Acoustics Department, National Institute for Standards 6 1. Dr. Khalifa Soliman Central Dept. of Projects, the Egyptian Geological Survey and Mining Authority 62, Genl Mohamed Seif El Din Gala1 Suez Governor 63. DrIMohamed Mosaad Ibrahim Suez Chief of the Local Council 64. Eng.1 Ahmed Abou Nazel Party General Secretary 65. Mr./ Ahmed Soubeh Shoura Council Member 66 Mr.1Abd El Nasr Ahmed Peoples Assembly Member / 67. 1 Dr.1Assem El Ghouhry / Pegisco Consultant Office I 1 68. 1 Dr./Fatma ~bouEI ~houk I Head of Central Dept. for Enviro. Assessment / 1 69. 1 Mr./Ramadan Abou El Hassan I Head of Suez NGOs I 70. Gen.1Eissawi Ahmed Head of Habilitation Organization -Suez 7 1 . Eng./Assem Badawi Head of Suez Gulf Development 72, DrIMohamed Mahmoud Sayed Deputy Petroleum Eng. Faculty for environ. I I 1 73. ) Col./Khaled Bahgat ( Head of Fire and Civil Defense 74. Mr./ Abou El Wafaa Beshir Head of Environment Committee - People's Assembly 1 - - T5. ~r./GharibAbdel~oubdi Head of Environ. Society- El Arabeen

1 77. Dr./Mohamed Mossad Head of People's Council in Suez 78. Dr./Mohamed Tawfik Abou Ghattas Head of Medical Syndicate in the Governorate ) 79. / Cap./lbrahim El Kellani / Sports Club I 80. Eng. massan Abou Bakr Environmental coordinate for Companies- ~ttak; 8 1. Dr./Fahim Ahmed Khalifa Deputy University Dean - Suez 82. Mr./Ahmed Mansour Head of Local People's Assembly-Attaka 83. Dr./Amal M. El Raay Head of Medical Precaution section 84. Chem.1 Nadia Attallah Head of Environmental Section , 85. , Eng./Hassan Kamel Head of Housing and Utilities 1 86. 1 Eng./Nazih Bahom I Head of Safety 1 87. Dr./Mamdouh Fahmy Head of Marine Institute 88, Chem.1 Leila el Khouly Head of Suez Environmental office 1 89. 1 Mr./Gamal Abd Allah I Bendar Society I

- ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Appendix-D - Page 5 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Am Al-Sokhna Thermal Power Project No 13 12 Appendix-D - Page 6 of 14 HB -1 0 August 2008 ENGINEERING CONSULTANTS GROUP

Occupation 1 123. ( Eng./Sayed El Hagaan General Manager of Civil Engineering - Red Sea Ports Org.

125, Gen./ Ahmed Abd El Aziz Head of Eng. Dept.- Red Sea Ports Org. 126, Mr./Mohamed Farah 1 127, Mohamed Hamed 17 R Mostafa El Eissawy Organization Head- Attaka district ( r29. ( Eng./Mohamed Agami ( Environmental Affairs 1 130. ama ad an Abd El Rehim Arbeen Society 13 1. Mohsen Ahmed Ans Ibn Malek Society 132. Gharib Awad

--134. Aly Soliman 1 35. Ahmed El Gamaal Member of Egyptian Red Crescent 136, Insaaf Abd El Rahman -1 137. Mohamed Abd El Megid Member of El Lowaa for Development ( 138. ( Mohamed Salam ( Member of Youth Development Society 1 T397 ~ehia~omaa Member of Society Development 140. Mohamed Marzouk Member of Assiut Society 14 1. Ragab El Shaat Member of Society Development-Shaloofa 142. Mostafa Abd El Fattah Member of El Hussein Society 143. Essam Abd El Azeim Member of Aswan Society 144, Abd El Halim Herigi Member of El Iman Society 1 145. 1 Samir Michele 1 Member of Orthodox Society 1 146. Ragab El Shaat Member of Development Society- Shaloofa 147. Ramadan Abou El Hassan Union Federation 1 48, Mrsmanaa Resaala Society RehlatySociety149. Mr. Arabi ( 150. 1 Ahmed Abd El Aleem 1 Environment Society I 1 15 1. Sayed Ghoneim / Suez Youth Society 1 / 152. / Farag AbelGhany I Local Society 1 1 153. Osama A~Y I Local Council - Suez 1 154. Bakry Hassan Local Council - Suez 155. Mohamed El Bohariy Local Council - Suez 1 156. 1 Adel El Sayed 1 Local Council - Suez 1 I 157. / Osama Ismail / Local Council - Suez

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix-D - Page 7 of 14 HE -10 August ZOO8 ENGINEERING CONSULTANTS GROUP

187. Moharned Saleh Local Council - Suez 1 188. Alia El Nahas Local Council - Suez 189. Gamal Attia Local Council - Suez 190. Mohamed Ibrahirn Local Council - Suez 19 1. Mohamed Gaber Local Council - Suez 192. Mohamed Agamy Local Council - Suez 193. Hossam Mohamed Local Council - Suez

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Appendix-D - Page 8 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

--Ser. Name Occupation 1 194. Abou El Wafaa Khalil Local Council - Suez 195. Ali El Sayed Local Council - Suez

197. Talaat Fahim Local Council - Suez I 198. 1 Hussein El Sayed / Local Council - Suez - 199. Mohsen Ahmed Local Council - Suez 200, Zeinab El Behadi Local Council - Suez 20 1. Samir Abdeen Local Council - Suez 202. Ahmed El Asraa Local Council - Suez 203. Sayada Ahmed Local Council - Suez I 1 204, 1 Laila Moawad I Local Council - Suez I 205. 1 Sobhy Mashalli I Local Council - Suez ) 206. Ahmed Hussein I Local Council - Suez 1 -207.~hx~alem Local Council - Suez 208. Gamal Samak Local Council - Suez 209. Talaat Orabi Local Council - Suez I I 2 10. I Mostafa Aly / Local Council - Suez 1 21 1, ( Salah Hussein I Local Council - Suez 2 12. 1 Ahmed Hussein ( Local Council - Suez

214. Shaat AbdAllah Local Council - Suez 215. Halima El Gendy Local Council - Suez 216. Ahmed Abd El Latif Local Council - Suez 2 17. Ragab Abd El Nabi Local Council - Suez 1 2 18. Mansour Mohamed 1 Local Council - Suez 1 1 219. 1 Ismail Ahmed I Local Council - Suez I

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Append~x-D- Page 9 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

2. List of Attendees

ESlA for El-Ain Al-SokhnaThermal Power Project No 1312 Appendix-D - Page 10 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

List ofthe Attendees Attending the Consultation Meeting Held on Wednesday 6 August 2008, 10 am at The Castellow Hall, Social Club, Suez City

19. Taha Abd El Aziz Electrical Engineer Suez Governorate 20. Aziza Aly Suez Co. 21. Wafaa Abd El Razak Suez Co. 22. Ezz El Arab District Head Suez 01 06027750 23. Mohamed El Shaat Delta Co. 24. Tag Ahmed Delta Co. 0104614988 25. Mohamed Abou El Medical Syndicate Head G hattas 26. Aly Saber Quarry Manager Suez Governorate 01 22869848 27. Atta Saad El Din Professor Environment 01223622026 Institute 28. Mohamed Mahmoud Chief Engineer Misr Electricity 0168336801 Co.

-- - ESlA for El-Ain Al-Sokhna Thermal Power Projecr No 13 I2 Appendix-D - Page I l of 14 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

Serial Name Occupation CornpanylOthers Telephone 29. Yehia Mohamed Engineer Suez Canal 0124849952 Organization 30. Mohsen Mahmoud City Council Member City Council 0105267117 3 1. Mohamed Hussein City Council Member Suez University 0 18 1 1465226 32. Mahmoud Riad Local People Assembly City Council 0 123766489 33. Abd El Halim Mohamed Member of the Regional Regional 0101714147 Federation Federation 34. Mohamed Ahmed Member of the Regional Regional Federation Federation 35. Hamed Hefney Member of the Regional Regional Federation Federation 36. Mohsen Hussein Deputy City Council I City Council 10101933463 37. Talaat Fahim Technical Petroleum City Council Office 38. Hossam El Din Kamal City Council Employee City Council-Suez Canal 39. Awad Abou El Hassan City Council Employee City Council-Suez Petroleum 40. Reda Radwan Technical Head Suez Suez Petroleum Petroleum 4 1. Hassan el Naggar Sector Head Electricity Distribution Co. 42. Mohamed Mahmoud Engineer Delta Electricity Distribution Co. 43. Farag Soliman Public Relation I Nasr Petroleum 44. Aly Mansee Journalist Ahkbar El Yooum Newspaper 45. Intessar El Hegazi Secretary General Environment protection Society 46. Moharned Tawfik Medical Syndicate Head 47. Shadia Ahmed General Manager Educational Section 48. Nadia Atta Manager Environment Section 49. Attia Mahmoud Secretary General Engineering Syndicate 50. Omar Attia Secretary Suez Society 5 1. Mansour Gad City Council Employee City Council 52. Hassan Ahmed Environment Expert Environment Society 53. Mahmoud Amin City Council Member City Council 54. Abou El Wafaa City Council Member City Council 55. Ibrahim El Said General Manager Attaka Electrical Station

ESIA for El-Aln Al-Sokhna Thermal Power Project No 13 I2 Appendix-D - Page 12 of 14 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

Serial Name Occupation CompanyIOthers Telephone 56. Bosina Abd El Moneim Environment Manager Electrical Company 57. Hussein Hassan City Council Member Nasr Petroleum 58. Hayam Mohamed Environment Manager Eyoon Mossa Electrical Station 59. Ahmed Mohamed Deputy Manager Transport Co. 60, Hanaa Kamal Member in Engineering Engineering Society Society 61. lnsaf Anwar Member in El Kheir El Kheir Society Society 62. Tarek Mohamed Delta Co. Delta Co. 63. Gad Amro Translator 64. Wafaa Abd El Razek Technical Manager Suez Station 65. Mohamed El Kalawi Member Society Society I Development Development 66. Essam Gharib Head of Asshab Society Social Affairs 67. Sayed Ahmed Technical Manager 68, Ahmed Mostafa City Council Member 69. Aly Mohamed City Council Member 70. Fekry Rashwan Researcher 7 1. Sayed Ahmed Technical Manager 72. Arabi Mohamed Pegisco Co. 73. Abd El Aziz Amar Deputy City Council 74. Maisa abd El Kadar Central lab chemist 75. Farag Nyazi 76. Youssry Abd El Aziz Social Researcher 77. Yossry Abd El Aziz Researcher Sea Science 012454 1295 78. Ahmed Odaa Pegisco Co. 79. Magdi Abou El Hassan City Council Member Suez Governorate 80. Osama Mahmoud City Council Member Suez Governorate 8 1. Karam Allah Mohamed Shabba Society Suez Governorate - 82. Kamal Haky General Manager ~uezCo. 83. Magdi Abou El Hassan City Council Member Suez Governorate 84. Osama Mahmoud City Council Member Suez Governorate 85. Magd El Seidi Pegisco 86, Amro Attia Suez Society 87. Asen Ely Pegisco 88. Mohamed Ahmed Kandil Chemist

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Appendix-D - Page 13 of' 14 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

Serial Name Occupation Company/Others Telephone 89. Hatem abd el Moneim Public Relations 90. Omar Sadek Abd El Public Relations Karim 9 1. Khaled Helmy Public Relations 92. Ahmed El Nemar General Manager Electricity Station 93. Mahmoud abd El Fattah Industrial Safety 94. Mahmoud Hassan EOC 95. Hossam Ibrahim KSB 96. Reda Hussein EEHC 97. Seham Ehamad EEHC 98. Abd El Hamid Journalist EL Ahaly 99. Kamal Hefney City Council 100. Magdi Mariee General Manager East Delta 101. Mohamed Abedel Hakim Security 102. Lobna El Khouly Manager Environmental Manager 103. Maher Aziz Head of Studies Sector Egyptian Holding 0 123689795 Co, for Electricity 104. Hassan Elbanna Project Manager for the Engineering 0101716679 study Consultants Group 105. Fatma Helaly Socialist specialist Engineering 02-22744740 Consultants Group

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Append~x-D- Page 14 of 14 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

Appendix E

Non-Technical Summary

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Appendix-E - Page 1 of 1 HE -10 August 2008

ENGINEERING CONSULTANTS GROUP

' 7 ...... Wl~1\&1;J! + .f \ Y ...... &I\ ir~~b~ + > i)dJU\\-t Y ...... U &$I LI&I + gk Y-t \ Y ...... &$I &!dl & T-t

\, t ...... &GI9 +s;Ul +Id\ f-t

\ t ...... &&.all &+I &$I 0-t

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S - Page 2 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESTA for El-Ain Al-Sokhna Thermal Power.Project No 13 12 N.T.S - Page 3 of 28 HB -28/7/2008 ENGINEERING CONSULTANTS GROUP &/"iWdWA>b

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S. - Page 4 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N.T.S. - Page 5 of 28 HB -28/7/2008 ENGINEERING CONSULTANTS GROUP &ZJ~~WA~

&llP it. di)95;j super-critical Gj+l Gib tjl; ijs2 &I; LJJ ~9 3s; L a

&A\ 93b&l>b,Lo yo* x Y bjl& ,?A~lhyl & GJ1G &j& &$ ;~L+j+l;lr!hdl &udFg . ~bgall&dl ~~~&ilI c(?! & -19GI-> rjI+YI relL j(ir>jLdl) &ill J9$I J~$I &I jLlL -12 ij-L &I;) ib & ib>&I ~JJL &L JX & bjL LJUI &I jLll

ESlA for El-Ain Al-Sokhna Thermal Power Projecl No 13 12 N.T.S.- Page 6 of 28 HE -281712008 ENGINEERING CONSULTANTS GROUP

&j~Lk I+ (Y) & L+ ' +dl $41 (Y) ' (\) h3 .&-I .&-I Ul @go

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S - Page 7 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

-- -- ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N.T.S.-Page 8 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

- ESlA for El-Aln Al-Sokhna Thermal Power Pro~ectNo 1312 N T.S - Page 9 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

------ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S. - Page 10 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S.- Page I l of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N T.S - Page 12 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S. -Page 13 of 28 HB -2817!2008 ENGINEERING CONSULTANTS GROUP

~~lg&i4jU1 f-t

" &yg \ 9 9 La\. - t dk 2 " ij$u &.!s 'G$u\g WI

&!I LL&~x~9 '(Y a a 0) LUI+ * UIoh+i ++ &A+ dg(\ 770) SJ~I~IabI>YI &K OJIL! & tg>l dg '&jvl wl Gg>>dl :t9@& i&LIQII Wl ijli q1;Il SGJl f

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N.T.S. - Page 14 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S - Page 15 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N.T.S.-Page 16 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

updl &lj,s$l Ol,& i;iJI@eJ&+ %'-'I 4i;n dud Jd\ WI 441 yUYIl*ihu, Lrvn k"J &Ad\ &iUI 'k - j%\.' & J Yo\.. 3Y)

0) rr/ +r. a rr / e I-7 - r?/ ,> pox) &,gl +~i r?/e-y... r,=/?y".. F ,> ryl (SOz) -+I dijl; rdF O.> I-?/? O. r?/~ (PM) QJJI JI+I

&&Ad\ cjL!i\ (%\.. ;,jL.- %\.. &) (&+dl '&.%I1 'j.JI 'j. YoY &. &Y) 0) r? / +- r r,=/ e r*.> . . (NOx) &,Sl +Ki ey... r?/ F yo.. r?/ey...> (SO2) -41di ~l; I-?/ F O' r?/ ?+ r?/F Oe> (PM) JI+\

&J~I&Ls.w • a &\ .49 - wljUl GP ~k) pox) +,SI +Ki - 'r/& f r,=/,=lJ+~& rrt,~4 LL \ L+ rd?l~~&\ o (')r,=/pl~J& \ O* r,=/plJ+~&\ rv,f 4 LLYfL+ - r?/rlJ+~& 1 a . ~,=/?IJ+J& t 08Ay J+A+ (SO*) Q+I +i ~l; - r?/?!J+,&(l'\ysty r?/?\J+,&ro. LL \ L+ rdrl~~&(')vsr~ '?/c'wJ& \o* r?/fl~,& \ 0 LLYtL+ rd+~,& (') s ,q 7 rrIrb+~J4.A rdpl~,& 7 . J+ibY+ (PM 10)

r?/?'3J& \ r?/?l*~& r?/?l>,& (y) f 1Y kLyfL+ - rd?lJ+,& o. y?/rlJ+,& "' 17 3 1f is+ Lj; awl cjlrjal 9-1 9-1 9 -1 (pH) &,>I, *Wl J+L - $I? 1. $/? la> (BOD) 41641 dii1 $1~eVo J/e\ jJ/? a ,o> r~9 , #O> A+- avo $I? ' 8 Jqe ,pWI A- \ JIJ/y\ lo J/F \ > +A \ $1~ A/? \> LLJI A? \ . A? )O A/? \ *> ,=$I> LN-?~ jJ/eo. A? 1. jJ/eo.> (TSS) i;lw~ 4\41 (r'J/e ,Y - - A/? * ,y> .-;;I' &'I ai. GL Jk ?Or ?O\' > ihi; Jk P9,1> - (OC) JIdl GJ-l> LJ&>I (1) MI "41UZ ~k &C Po, "41 a&) I+ \o. (+ r. .-Ul

ESIA for El-Ain Al-Sokhna Thermal Power.Project No 1312 N.T.S. - Page 17 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP &dwdwA&b

u,dn GI>> &I,,& &.A &Ie,;. & JJAI L?L;n 2h &&M~I uu"lwh, 4ii11‘jbi 4ull

("1 ,&&J\

&J Ve ILYYU-IV- ILYYU-I Oh,l > ( +>I dl ) &i

&+J V. &J 1. ILYYU-I oh,\ > ( +>I dl) MI &i

. NO, &,+I +Si jGLhJ+ .L NOx &,&I1 +KY $+I *Wl()) ct;j; L ~i'7. .A ;,dl d,il~$41 LL&I G, L$I4 &+I air LI~J~;, g t& 41.ir (Y) . 5%J& Y 4 @ air + ibvll U.+ iJj- jJ9i)?j&lI UL. riL+ ?lGlJL 6 ( j iLnL ;)& 6 ' dj3yI i-" (r) j+ vsrY d c j?;L ;U &j jJ/? Y d &,All iLjllj . Ul&&+A i+l LCI~I .(jJ/rY.,Yi)+-jl~kL\IiLJ;IJ)kLYi&L jip+$Y -I GL L= 21 5 j3G~~IAI bj~j i~&j ;, ++I 2 4 +$I b~+ &ji +-~i -+ (i) J,dl Ul aL +*GF > -1 bb j& L&, 4 -1, L& bk!diiYl@ . Gul air Jx; j iL ij;L LzJ+J + dli~j@i' L&c c &+&I Lii & + ! iiL jI+ Udtlki +Li, " &,J,' -1 cL,A.I L_).DJl auifr;JL "qcd&L - +Lw l&.* )!I & (0) . J,d1 &I *W WL "+j&

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N T.S. - Page 18 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Aln AI-Sokhna Thermal Power Project No 13 12 N.T.S.-Page 19 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 N.T.S.- Page 20 of 28 HB -281712008 ENGINEERING CONSULTANTS CROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N.T.S. - Page 21 01'28 HB -281712008 ENGINEERING CONSULTANTS GROUP

i&>k G* i~+41AUI JS dg +IA 2~~-ALQ L +;YI 'ji +> "u &+s L Gliu. LL~&hid\ 31 j&Yl 2 ljiii Ij! 3y3 iL+ G* u&&I &Id1 'jg &I+ ib~;L 'jUl lie j $&dl jl+I 3r614 .&IA kL 'j&

?L +I i3jcui i+ i$JX A+ di @+ J3>~ &I$! JUI $I3 L~qpi~-3 ?LJjY\ JLI +.% hi ePi3. T b \ T -T &lcL b3'@I igJL i$JX Lii ;1; LjF &l>kl\ hie 'ji +3 AhdJ cjlclH! 'ji & ,155\j & &I Sp3 j3plI & 4LdlJSJI $kll 'j$'i3,11I .&+I1 &l&Il j& JLI J&liig! ~j* $fill lie

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 N.T.S. - Page 22 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N.T.S. -Page 23 of 28 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 131 2 N.T.S.- Page 24 of 28 HB -28/7/2008 ENGINEERING CONSULTANTS GROUP

/& j *i .&.A o . ++ ~$1 +Ill 2141 MI & &+I &dl &LA tjr UJ! ((P q*xy cj+/ Je) 1s Jlilq* UJ~POJJJ&J~JIL~J Ob* 2+.3~> +Ji &&IkJI Jl+l di +!L3.Ul &I GI& L t3+

i$\d\c3J+1 d-1 2141 Mk & i-y dlp J& .d.d yy * ++ -&&m\&J*- bw$l/&dl&A& .d.d yy* * .d.dY Y . +LAY1 &Y- L i)a +S$ L+ switching station AS; & iddl &$I @J& +u $1 .&.&I0 * * * $l&l L$d M&J * JkaJ di3 .d.d YY. /o* * ++&&I1 UJ!L&l Ul&I L

/ +UI i$ldl c3~+7 JU\2141 -I$ & AS &JI &LA JAS3

u- &! (+ i .XI &i 'c3+ / J+J) I+ ~lili. J& OJLI~ &+I -1 .switching station &dl

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 NT.S - Page 25 of 28 HB -281712008

ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 HB -281712008 ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 N T.S. - Page 28 of 28 HI3 -281712008 ENGINEERING CONSULTANTS GROUP

Appendix F

Presentation Slides 1. Project Description Slides 2. EIA Scoping Slides

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix-F - Page I of 3 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

1. Project Description Slides

ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Appendix-F - Page 2 of 3 HB -10 August 2008 MINISTRY OF ELECTRICITY AND ENERGY EGYPTIAN ELECTRICITY HOLDING COMPANY (EEHC) EAST DELTA ELECTRICITY PRODUCTION COMPANY (EDEPC)

Associated Environmental Impact Hearing

EL AIN EL SOKHNA 2x650 MW

THERMAL SUPERCRITICAL POWER PLANT PROJECT

August 06,2008

Power Generation Engineering and Services Company

Egyptian Electricity Holding Company

Chairman Dr. Mohamed Awad

Director Director Director for Financial for Studies, for Regulated and Economical Projects and Services Companies Affairs Companies Affairs Affairs Mr. Saiah Awad Dr. Kamel Eng. Fawzia Abou Neama IDistribution Companies , Generation Companies I I North Cairo Eng. Mohamed Ashour Chairman Cairo Eng. Ahmed Emam Chairman South Cairo Eng. Mahmoud Sami Sultan Egyptian Electricity Chairman East Delta Eng. Tarek Youssef Transmission Co. Chairman Chairman I Eng. Ibrahiem Mady Eng. Hassan Negm Chairman West Delta Eng. Mahmoud Baibaa Vice Chairman El Behiera Eng. Ahmed Khalil Chairman I Eng. Galal Halawa Chairman. Vice Chairman Middle Delta Eng. Awad Mohamed Fathy Eng. Ismail Teleb North Delta Eng. Mohamed Bakr Chairman tan

Upper Egypt Eng. Shaaban Khalaf South El Delta Eng. Fawzy El Serby I Chairman Canal Eng. Mamdouh El Nahas Hydro Plants Eng. Mohamed Mohamed Faragallah Chairman Chairman Middle Egypt Eng. AM El Sattar Abou Ras I Chairman Upper Egypt Eng. Mohamed Hassan El Ezzklany Chairman EEHC Generation Expansion Plan ( 2002 12012 )

Estimated Award (x) and Operation Dates with plant size, MW Location Type 01103 06104 OA105 05/06 06/07 07/08 08/09 09/10 1W1 11112 12/13 Zafarana Wind Farm 0 30 47 43 42 80 90 440 500 500 500 Suez Gulf (l&2) Steam Turblnes 682 3,636 MW Port Said East (1&2) Steam Turbines 682 Cairo North I Comb~nedCycle 250 150 250 Nubaria I Combined Cycle 250 250 250 Nubaria II Combined Cycle 500 250 4,500 MW Cairo North I1 Combined Cycle 500 150 Talkha Combined Cycle 500 1.50

El Kuriemat I1 Combined Cycle 500 ?

Location Type 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 2U22 22/23 23Pt4 24/25 25t26 26/27

Zafarana Wind Farm 580 600 600 600 600 600 600 600 600 100 100 100 100 100 100 5,980 MW

Mini &Small H~droLnik Hydro Power plank 32 32 MW El Kureimat Solar I Thermal

Abu Qir Steam Turbines 650 1,950 MW ' El Ain El Sokhna * Steam Turbines 650 650

Thermal Power Plank 650 MW 1 x 650 2 x 650 2 x 651 2 x 650 2x650 3x 650 3 x 650 2 x 650 1x 650 3 x 650 3 x 650 3 x 650 34,250 MW Combined Cycle Plank 750 MW 4x250 4x250 3x250 3x250 3x250 5x250 4x250 3x250 5x250 4x250 5x250 6x250 4x250 5x250 1x250

Nuclear 1 1,000 1,000 1,000 1,000 5,000 MW

'I'obd 3330 2@0 2,682 2,654 2,650 2,850 2900 3,300 2,850 3,050 3,650 4,200 4,050 3,300 3,300 47,212MW

Plant Cooling System Once Through Cooling System design Considerations

Design Considerations el300 MW

Water Flow Requirement, m3ls e45 Preliminary

Temperature Rise Across the el0 Max Condenser, o C

ENGINEERING CONSULTANTS GROUP

2. ESIA-Study Slides

ESlA for El-Aln Al-Sokhna Thermal Power Project No 1312 Appendtx-F - Page 3 of 3 HB -10 August 2008

El-Ain Al-Sokhna Site Plan and the Selected Monitoring Locations

rn m m-m IT1 5.-m - -.9) 5 V) F 8 (D (D %(D 9) 9) Cn h PI- s - O 7 9) 9) a -I N -.9) 5 (D 2 I 3 0 N V) 0 u 3 Fi: CD -9)

a a " A 03 P ru V, cn A A 03 CD CD 0 0 P P iu in in in

A A 4 P P 4 P==A "A01 03 h) 0OIP 4 NO 4 5P 3 B < CD 3 h) " " 01 A P P C13 01 4 ru " " 0 -I% 0 A 03 P 4 CD " 'II -

a " ru P " CD cn 01 4 P 0 a s 0 03 A " 01 03 " s Stack Emissions for Firing with Natural Gas, mg/Nm3 [Ceiling Values of both the Egyptian & the W.B. Standards]

Emission Concentration

Emission Type Egyptian Estimate Value World Bank Guideline Requirement

NOx -< 300 mglNm3 300 mglm3 -c 320 mglNm3 so2 Negligible Not Specified Not Specified

"MI o < 50 mglNm3 - -

Particulate Matter mg/Nm3 200 mglm3 50 mglNm3 (all size): TSP -< Stack Emissions for Firing with Heavy Fuel Oil, mg/Nm3 [Ceiling Values of both the Egyptian & the W.B. Standards]

Emission Concentration Emission Type Egyptian Estimate Value World Bank Guideline (2)9(3) Requirement

NOx -< 300 mg/Nm3 300 mg/m3 -< 460 mg/Nm3

2000 mg/Nm3 2.0 t/d /MWe for the first 500 MWe < 2000 mg/Nm3 3600 mg/m3 So* - Plus 0.1 t/d /MWe additional over 500 MWe

PM1O < 50 mgINm3

Particulate Matter 200 mglNm3 200 mg/m3 50 mg/Nm3 (all size): TSP -, Localization Map Used for Dispersion Modeling

Receptor Map Used in Air Quality Modeling (MM5 Nested Areas) [The modeling domain covers the area between Longitudes 230-400 E and Latitudes 220-350 N] Estimated Maximum Average Concentrations of Nitrogen Dioxide, pg/m3 [Two Al-Sokhna Units (2x650 MWe) Burning Natural Gas and Running as of BAU Scenario] [Stack Height = 150ml

I-hr 24-hrs Annual

Max. Hourly Ave. Max. 24-Hours Ave. Max. Annual Ave.

NO2 Dis. x Y NO2 Dis. x Y NO2 Dis. x Y

1 266.5 779.7 628.7 461.2 130.0 482.4 -141.5 461.2 38.8 669.4 -141.5 -658.8

2 265.1 669.9 628.7 231.4 125.5 896.5 118.6 -888.6 32.2 896.5 118.6 -888.6

3 256.9 691.6 118.6 681.3 124.5 1001.0 888.4 461.2 28.8 454.4 888.4 -438.7

4 255.8 695.8 -141.5 681.3 122.3 915.0 888.4 -218.8 25.3 1115.1 888.4 -1108.7

5 251.4 806.4 -661.5 461.2 1 18.5 918.1 888.4 231.4 23.1 962.0 888.4 -888.6

6 247.4 918.1 888.4 231.4 1 17.5 461.O -141.5 -438.7 21.6 754.9 -141.5 -658.8

7 . 246.4 482.4 .-141.5 461.2 1.13.4 962.0 368.5 -888.6 20.4 1 168.4 368.5 -1108.7

8 246.1 888.5 888.4 11.3 1 12.8 888.5 888.4 11.3 19.7 899.8 888.4 -888.6

9 243.7 896.5 118.6 -888.6 109.2 766.6 628.7 -438.7 19.6 1344.0 628.7 - 1338.8

10 243.3 61 1.6 -401.7 461.2 107.0 1171.7 1148.6 231.4 19.2 673.8 1 148.6 -658.8 Estimated Maximum Average Concentrations of Nitrogen Dioxide, pglm3 [Two Al-Sokhna Units (2x650 MWe) and Two Suez Gulf Units (2~340.25MWe) Burning Natural Gas and Running as of BAU Scenario] (tack Height = 15Om)

Max. Hourly Ave. Max. 24-Hours Ave. Max. Annual Ave.

NO2 Dis. x Y NO2 Dis. x Y NO2 Dis. x Y

1 322.1 482.4 -141.5 461.2 130.0 271.2 -141.5 231.4 44.8 669.4 -141.5 -658.8

2 316.6 896.5 118.6 -888.6 127.6 888.5 888.4 11.3 43.7 896.5 888.4 -888.6

3 312.0 611.6 -401.7 461.2 125.5 910.6 628.7 -658.8 34.7 1115.1 628.7 -1 108.7

4 31 1.2 695.8 -141.5 681.3 122.9 673.8 -141.5 -658.8 30.2 962.0 -141.5 -888.6

5 295.7 779.7 628.7 461.2 122.4 766.6 628.7 -438.7 28.0 454.4 628.7 -438.7

6 288.1 975.2 -401.7 -888.6 121.7 918.1 888.4 231.4 27.9 1168.4 888.4 -1 108.7

7 288.1 899.8 -141.5 -888.6 120.8 1088.5 628.7 -888.6 27.2 1344.0 628.7 -1 338.8

8 284.9 1115.1 118.6 -1 108.7 119.4 1171.7 1148.6 231.4 24.5 754.9 1148.6 -658.8

9 282.1 669.4 118.6 -658.8 115.9 1344.0 1 18.6 -1338.8 23.8 1388.6 118.6 -1338.8

10 279.3 806.4 -661.5 461.2 115.6 1388.6 368.5 -1338.8 23.2 899.8 368.5 -888.6 Commulative Effect of the Proposed ACSokhna Gas-Fired Power Project and the Existing Suez Gulf Gas-Fired Power Plant (Air Dispersion Modeling Results), in addition to the Background levels in the Background Atmosphere (Stack Height = 750 m)

Pollutant NO2 NO2 NO2

Averaging Period, pg/m3 1 hr 24-hr Annual

322.1 130 44.8 First Maximum, pg/m3 (-141.5m, 461.2113) (-141.5m, 231.4m) (-141.5m, -658.8m)

Background Level 12.69 7.49 1.02 (measured by NRC)

Total, pg/m3 334.79 137.49 45.82

Egyptian Limit, pg/m3 400 150 NIA

World Bank Guideline, pg/m3 No Limit 150 100 NO,-Maximum Annual Combined Mean Concentrations in pg/m3 [Two Al-Sokhna Units (2x650 MWe) and Two Suez Gulf Units (2~340.25MWe) Burning Natural Gas and Running as of BAU Scenario)

NO,-Maximum 7 Hr (Hourly) Combined Mean Concentrations in pg/m3 [Two Al-Sokhna Units (2x650 MWe) and Two Suez Gulf Units (2~340.25MWe) Burning Natural Gas and Running as of BAU Scenario)

k4

$4

ben vr

'L4

$4 6- "k- t;' h 3

Bathymetry in the Northern Gulf of Suez (Source: Sedimentological Expertise Study" Completed on behalf of EDF, Using SHOM Map No. 6878 Scale 111 75000, Suez Gulf Power SAE studies, 2000)

Selected Current Measurements Carried out at Location of Point No. 1 (E: 43751 2.8443, N: 3275232.627)

Point Temperature Conductivity Pressure Direction Velocity Date & Time Depth r 1 Degree C I mmholcm 1 kglcm2 I Degree 1 cmlsec I m Tidal Heights at Suez and Al-Sokhna

Location HHWL MHWL MSL MLWL LLWL

Suez (all year) 2.00 1.53 1.04 0.52 -0.10

Suez (July) 1.60 1.38 0.81 0.36 0.00

Suez (February to March) 2.00 1.63 1.12 0.60 020

Al-Sokhna measured levels (July 1998) 1.55 1.12 0.70 0.25 -0.08

Al-Sokhna measured levels excluding meteorological 2.05 1.30 0.45 set-up (February-March 1999)

Al-Sokhna SUMED Jetty (October-November 1998 2.21 1.79 1.I4 -0.48 -0.09 Current Speed and Direction Adjacent to the Project Site

Location Site Date Maximum Speed (cmls) Minimum Speed Oyoun Moussa A (2.5km from shore) 3017195 14.7 2.3 B (1.5km from shore) 13.6 2.7 A 12/8/95 23.8 0 B 16.8 0 West Suez Gulf Power A (At mid-depth, approximalely 81-17) 211 1198 8.0 1.8 Plant 6 (Approximatelyl0.5m) 9.4 2.2

C (At mid-depth, approximately 10m) 10.1 2.3 A 1011 1198 8.3 3.1 B 9.5 3.6

C 11.7 4.4 West Suez Gulf Power A (vertical profile) 211 1/98 15.0 2.9 Plant 6 (vertical profile) 18.3 2.9

C (vertical profile) 24.9 6.8 A (vertical profile) 1011 1198 16.2 3.5 B (vertical profile) 22.3 5.4

C (vertical profile) 22.3 7.4 Location of Sampling Points for Sea Water Quality Analysis Water Quality at the Project Location Physico-chemical Analysis of Water Samples at the Project Location (Samples Delivery Date: 29 june 2008)

Concentration Parameters Unit Site Site Site Site Site (1) (2) (3) (4) (5) PH - 8.0 7.9 8.0 8.0 7.8 Water Temperature OC 23 24.5 25 24 26 Electrical Conductivity pmholcm 61 150 59800 62000 59200 60500 Transparency cm 90 90 90 90 90 Total Dissolved Solids mgll 39503 39557 38795 38889 39084 Suspended Solids mgll 8.6 9.5 10.6 10 8.9 Total Solids mgll 3951 1.6 39566.5 38791.6 38899 39092.9 Total Alkalinity (as CaCO,) mgll 120 122 124 128 116 Chloride(C1-) mgll 25000 25000 25000 25000 24000 Sulfate (SO,--) mgll 421 . 41 2 439 432 438 Nitrate (NO,-N) mgll 0.02 0.01 0.01 0.01 0.01 Sodium (Na+) mgll 1 1 502 10842 1091 2 10987 10223 Potassium (K+) mgll 753 731 692 684 613 Manganese ~gll Nil 0.02 0.27 0.65 0.1 1 Calcium (Ca+) mgll 56 1 641 56 1 56 1 601 Magnesium (Mg++) mgll 1703 1654 1605 1654 1581 Water Quality at the Project Location Organic Analysis of Water Samples at the Project Location (Samples Delivery Date: 29 June 2008)

Concentration

Parameters Unit Site Site Site Site Site (1 (2) (3) (4) (5)

COD mg0211 32 28 32 28 30

BOD mgO,/l 16.2 16.5 18 7.8 24.9

Oil& Grease mgll 14.8 15.1 15.3 16.5 16.0

Phenol mgll N/D(2) NID N/D NID NID

Polycyclic Aromatic Hydrocarbons 0.041 0.039 0.037 0.038 0.0375

Total Hydrocarbons ~911 78.6 79.2 81.6 85.7 84.3

Chlorinated Hydrocarbons ~gll 0.034 0.049 0.053 0.047 0.062

Polychlorinated Biphenyles (PCBs) P~II 0.67 0.87 0.85 0.76 0.68 Heavy Metals Analysis of Water Samples (Samples Delivery Date: 29 June 2008)

Concentration Detection Parameters Unit Limits Site Site Site Site Site (1) (2) (3) (4) (5)

Zinc mg/l N/Do N/D N/D N/D N/D 0.005

Cadmium mg/l 0.162 0.1 58 0.151 0.142 0.14 0.002

Chromium mg/l 0.096 0.089 0.091 0.092 0.093 0.02

Lead mg/l 1.063 1.034 1.048 1.052 1.051 0.05

Nickel mg/l 0.676 0.669 0.668 0.672 0.674 0.02 2 '-go" 5 2 $0 q 1a -rn n 0 as cn ms 0 a 3 m am

Organic Analysis of Sediment Samples (Samples Delivery Date: 29 June 2008)

Concentration Parameters Unit Site Site Site Site Site (1 (2) (3) (4) (5) Oil & Grease mg/kg 312.4 278.3 291.02 282.42 287.6 Polycylic Aromatic 12.51 15.13 16.83 13.5 15.7 Hydrocarbons

Total Hydrocarbons ~g/kg 423.8 386.4 403.12 537.6 568.7 Chlorinated Hydrocarbons ~g/kg 3.02 3.68 4.01 4.38 4.46

Polychlorinated Biphenyles . ~glkg 17.02 20.01 21.54 24.31 23.96 (PCBs) . Heavy Metals Analysis of Sediment Samples (Samples Delivery Date: 29 June 2008)

Concentration Detection Parameters Unit Site Site Site Site Site Limits@) (1 (2) (3) (4) (5)

Zinc mglkg 8.52 8.42 8.43 8.72 8.75 -

Cadmium mg/kg 2.8 2.79 2.78 2.83 2.84 0.002

Chromium mg/kg 7.3 7.2 7. I 7.4 7.5 -

Lead mg/kg 0.5 0.48 0.47 0.46 0.45 -

Nickel mg/kg 4 3.8 3.9 3.7 3.8 - - Concentration of Process Chemicals in Combined Effluent Discharged to Mediterranean Sea

Predicted Egyptian World Bank Pollutant Concentrations Standards Guidelines (msl-l) (ms 1-I1 (msr) Biological Oxygen Demand (BOD) Chlorine (Free) lron Oil and Grease Suspended Solids (Total) Zinc pH

By: Dr. Ahmed Sayed Mohamed Ahmed Associate Professor Hydraulics Research Institute National Water Research Center Ministry of Water Resources and Irrigation

Current Speed (cm/s)

el- Current Direction ON f POP?'+ 0PgO$OOOO O\h)WPOO\- -NU W 00~0000~0 0 0 0 0 0 0 0O:O 800Zl6Zl£ I 1 1 1 1 -.--- L J

0O:O 800Zl I£I£ - am. 0O:O 8OOZIZIP -

0O:O 8OOZlPlP - i

$ 0010 8OOZl9lP - i R (P ei 3 0O:O 800Z/81P - (P

0O:O 8OOZ/O I/P -

0O:O 8OOZ/ZI/P - me

0O:O 8OOZ/PI/P -

00:O 800Z19 IIP

Data Analysis and Model Result

Spectrum Graph of Values of Sound Levels for Each Third Octave Band (Locations 1, 10, 15 & 20)

.,, .,,,,, ,.,,

lrrs Iwr Iwvl" 16 313 61 18 20 m lm) HD rm A L Wz -M>HI ~q.~sm-~m unr~rmsm IUq IUFY- ILVYn C- HZ w-477m umprmem LVY,PSZ~ Location 1 Location 10

Location 15 Location 20

Individual Point Sources of a Significant Amount of Noise in the Power Plant [Main Sources Inside the Power Plant (2D view)] Predicted Operational Noise Levels

Egyptian Standard World Bank Guideline (dB(A)) (dB(A)) Predicted Receptor Level (dB(A)) Day-time Night-time Day-time Night-time

Fence of the Power Plant at the Suez Gulf BOOT power plant 70 60 70 70 58.1 Northern Edge

100 m away from the Fence of the 70 60 70 70 < 55 Power Plant . Noise Fiiied Contours for El-Ain A/-Sokhna Power Plant in L,, Noise Filled Contours for El-Ain Al-Sokhna Power Plant at Night

l 34 'I, An Example of Salt Marshes within the Study Area Typical Vegetated Coastal Desert Plain of the Study Area Parts of the Site Showing no Plant Growth (A), while Others Support Patchy Vegetation (B)

Geographical Distribution of Fishermen in the Red Sea

Fishermen Gulf of Suez Hurghada El-Qusseyr El-Tour

Number 13,376 2,022 1,227 831

Yo 75 11 7 5 Clean Sandy Beach along the Whole Study Area

Main Access Roads to the Power Plant Site Average Annual Daily Traffic (AADT) for Suez /Zaafrana Road during Period (2000 - 2007)

Year 1 Traffic Volume (Veh.lday) I Locations of Traffic Count Points Fronting Al-Sokhna Power Plant Site 00 DO V, 0 IV, ;II (D 9) (D 9) PC 0 9) cn =' F =' cn x =. r E 5 E 5: g E (P3k n V, 9) T % D 9) I E C 2 n (0 T iT n 3 9) N )< I

-i 0 d 0 220 E -I -. 0 4-120 3 o-4 I0 5 D 0 D 0 u, 0 "C c E. c @. 0E.0% c P " 3 =.o R axaxa x3 a a, R 3 3 a a, a,

rz 10 10 0 0 P P 0 W 10 10 ? S 0,

10 10 10 P P P 0 0 3 a 0 0 P hgsn 3 3 3 3 3 3 z Y 5 3

0 0 0 9) oooooo < < o 0 00 0 0 0 0 b b 00 00 00 00 0 0 28 a n n n n n 0 0 8 8 e,-* 3 a a S n

V, a 5 10 10 10 P\) r\> h, 0 333333 Y Y r, 9 n h 9 h h h h h n h " u 3 Q C BQ55889 < < c 9 ca, c9) (D < B (D (D (D (D 5 5 (D (D a a 2 n w wa wa wFi wa wa w a a w w 2 5

49)3 CO a a a a -4 COW 8 0, cn 0 0 cn 2 zx cn 0 E $ g Iua f: f: a CO 25 f

Volume-to-Capacity Ratios for Suez/Hurghada Road

Volume-to- Peak Hour Road Capacity (C) Capacity Ratio Volume (V) (VIC)

Coming From Hurghada to Suez 292 1100 0.27

Coming From Suez to Hurghada 199 1100 0.18 Traffic Volume for Suez/Hurghada Road with and without the New Power Plant (in Vehicledhr)

1. Expected traffic volume in year 2009

Morning Peak Hour Evening Peak Hour

Without During Without During Power Plant Construction Power Plant Construction To Suez 240 293 493 51 5 To Hurgada 307 354 346 368

2. Expected traffic Volume in year 2010

~ornin~Peak Hour ' Evening Peak Hour

Without During Without During Power Plant Construction Power Plant Construction

To Suez 271 318 543 565

To Hurgada 338 385 381 403 Traffic Volume for Suez/Hurghada Road with and without the New Power Plant (in Vehicledhr)

3. Expected traffic Volume in year 201 1 Morning Peak Hour Evening Peak Hour Without During Without During Power Plant Construction Power Plant Construction To Suez 299 346 598 620 To Hurgada 372 419 420 442 4. Expected traffic Volume in year 2012 Morning Peak Hour Evening Peak Hour Without During Without During Operation Power Plant Operation Power Plant To Suez 329 376 658 680

To Hurgada 410. 457 - 462 484 5. Expected traffic Volume in year 201 3 Morning Peak Hour Evening Peak Hour Without During Without During Operation Power Plant Operation Power Plant To Suez 362 406 724 768 To Hurgada 451 495 509 553

Traffic Volumes for Related Regional Roads with and without the New Power Plant (in vehicle/hour/direction)

2009 2010 2011 2012 2013 Road Section Without During Without During Without During Without During Without Post Const Const Const. Const. Const. Const. Const. Const. Const. Const.

Cairol Alex. 32969 Desert Highway 33063 35428 35522 38069 38 163 40907 41001 43956 44043

Cairol Alex. Agr. 133244 133338 148834 185792 207425 2075 12 Highway 148928 166247 166341 185698

CairolSuez Desert 9606 19700 20983 24032 257 19 25806 Highway 21077 22456 22550 24126

CairolAin Sokhna 8064 8158 9032 9126 10210 11330 12689 12776 Freeway 10116 1 1424 Summary of Generated Operational Traffic

Type Vehicle Peak Period Daily

HGV 6 12

CarILGV 81 162

Total 87 174 4 1 t7 3

d

'a,'3 od '"5 $3 4 ~3 'Ir, t9% 7;9 .qu C ==5a S rn

Spatial Locations of Major Basic Economic Activities in Suez Governorate (Source: EEAA, DANIDA, GOS: The Environmental Profile of the Governorate of Sues, 2004)

'a, 3 % 9 > % 43 3 CU

C5 r), C%I

,as3 '1 C1 4' 9 9

~3 'a,

Seismicity Map of Egypt and Surrounding Areas in the Period :1900 - 1996 (Compiled from Different Authors)

CA YUM

Google Spot Image Showing the Location of the Existing 7 Dams Constructed alongwith the Main Tributaries of Wadi Ghweibba Drainage System

E

":. ":.

k L

m c c st"4

4n 4

"a,\

3;4

-9 @r &~l&I iJA4 khJ + dl CSI&~~~I ~9 Jb

Wdi_??lw &+ gi L~~IAI o+l UljLkijw . p~ $~WI &.+I UjLtd4~idl (COD mLl ow LTSSml iSSfl-l rl+13 (discharge plume) &~dls~e.+Jls ~HJIJ

uP;.1! &dl~91s L+J~ L-l wl twAI3 (BOD . DO ~9lg(TOC . &$91 csI:&dlJ iJ&l (j'kdl

f@4) @JC && &A fq &I&?( uu\ (I)&&! LA& jfl &~IIoli . dl +!dl3Gyl &vul -Jl 2 9Jkj Li.pj ((3j~l U + 6 2 oJJ LjJdill

4& &'t J&J alj! 9~91 (2) &-dl &&+I bd .9&Jl& hidl 9y: "!G

ENGINEERING CONSULTANTS GROUP

Appendix G

SELECTED PHOTOS

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix -G- Page 1 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

~~~~~ ------ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Appendix -G- Page 2 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix -G- Page 3 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

A for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix -C- Page 4 of 16 -10 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain At-Sokhna Thermal Power Project No 13 12 Appendix -G- Page 5 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 I2 Append~x-G- Page 6 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP &JL~J,~~WA&~

ESIA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Appendix -G- Page 7 of 16 HB -10 Augus; 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Append~x-G- Page 8 of 16 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix -G- Page 9 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP &~wdLs-/dhb

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix -G- Page 10 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP

- - ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Append~x-G- Page 1 1 of 16 HB - I0 August 2008 :NGINEERING CONSULTANTS GROUP &J!& k&

p~ ESIA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendix -G- Page 12 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP &dwdwah'Le

- -- - - ESlA for El-Aln Al-Sokhna rhermal Power Pro~eciNo 1312 Append~x-G- Page 1 3 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS GROUP &dwdts-/Abb

ESlA for El-Ain Al-Sokhna Thermal Power Project No 13 12 Appendix -G- Page 14 of 16 HB -10 August 2008 ENGINEERING CONSULTANTS CROUP

ESlA for El-Ain Al-Sokhna Thermal Power Project No 1312 Appendlx -G- Page 15 of 16 HB - I0 August 2008 ENGINEERING CONSULTANTS GROUP &JW&~&&V

------ESlA for El-Aln Al-Sokhna Thermal Power Project No 13 12 Appendlx -C- Page 16 of 16 HB - I0 August 2008 Annex E

THERMAL PLUME MODELING The Study of the Hydraulics Research Institute will Follow