Environmental Monitoring Report

Project Number: 45030-002 June 2016

PRC: Sustainable Road Maintenance (Sector) Project

Prepared by the Yunnan Highway Administration Bureau for the People’s Republic of and the Asian Development Bank

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Asian Development Bank ii

PRC: Yunnan Sustainable Road Maintenance (Sector) Project(PRC-3074)

The 1st Quarterly Environmental Monitoring Report June 2016

For S211- to Songming Highway Maintenance Component

Prepared by the Yunnan Highway Administration Bureau for the Asian Development Bank

Table of Contents

TABLE OF CONTENTS I ACKNOWLEDGEMENT VI EXECUTIVE SUMMARY VII I. DESCRIPTION OF THE COMPONENT 1 II. DESCRIPTION OF THE ENVIRONMENT 2 A. Geology 2 B. Climate Condition 2 C. Hydrology 3 D. Natural Resource 3 III. REPORT PREPARATION 4 A. Policy, Legal, and Administrative Framework 4 B. Report Period 5 C. Scope of Environment Monitoring 5 D. Potential Environmental Impacts 6 IV. IMPLEMENTATION OF EMP 8 A. Detailed design drawings and bidding documents 8 B. Institutional Arrangements 8 C. Construction Supervisors 8 D. Implementation status of the mitigation measures 8 E. Analysis of Environmental Monitoring Results 11 F. Institutional Capacity Building and Training 17 V. PUBLIC CONSULTATION, INFORMATION DISCLOSURE AND GRIEVANCE REDRESS MECHANISM 19 A. Public Consultation, Information Disclosure 19 B. Grievance Redress Mechanism (GRM) 20 VI. CONCLUSIONS AND SUGGESTIONS 22 APPENDIX 1: SUMMARY OF POTENTIAL ENVIRONMENTAL IMPACTS AND THE MITIGATION MEASURES IMPLEMENTED 23 APPENDIX 2: SITE PHOTOS 40 ii

LIST OF PICTURES Picture A2- 1 Muddy Road Surface Before Construction 40 Picture A2- 2 Road Surface Before Construction 40 Picture A2- 3 Dusty Road Surface Before Construction 41 Picture A2- 4 Construction Announcement 41 Picture A2- 5 Detour notice 42 Picture A2- 6 GRM Signboard on Construction Site 42 Picture A2- 7 GRM Signboard at Construction Road Section 43 Picture A2- 8 Traffic Personnel Directing Traffic 43 Picture A2- 9 Construction Workers Wearing Safety Clothes 44 Picture A2- 10 Half-range construction, not affecting the traffic 44 Picture A2- 11 Construction workers excavating culvert, building retaining wall, with helmets 45 Picture A2- 12 Establishing Construction Safety Signs 45 Picture A2- 13 Set speed limit sign 46 Picture A2- 14 Set road safety cone 46 Picture A2- 15 Set speed and load limit signs at construction section 47 Picture A2- 16 Renting existing equipments and venues in asphalt mixing station 47 Picture A2- 17 The materials hauling vehicle covered with canvas. 48 Picture A2- 18 Sprinkler suppressing dust 48 Picture A2- 19 Recycling of construction waste 49 Picture A2- 20 Recycling of construction waste+ Dust control measures taken when loading 49 Picture A2- 21 Transporting Construction Waste 50 Picture A2- 22 Collecting lubricating oil from construction vehicle 50 Picture A2- 23 Sensitive point of environmental monitoring 51 Picture A2- 24 Sensitive point of environmental monitoring 51 Picture A2- 25 The staff collected water sample in the reservoir of Xizhelong village 52 Picture A2- 26 Environmental experts testing air quality on site 52 Picture A2- 27 Environmental experts testing noise on site 53 Picture A2- 28 ADB’s environmental experts and social experts conducted training on site 53 Picture A2- 29 Anti-AIDS training 54 Picture A2- 30 Anti-AIDS awareness education board 54 Picture A2- 31 Health Inspection 55 Picture A2- 32 Organizing regular physical examination for the staffs 55 Picture A2- 33 Female Employees 56 Picture A2- 34 Public Opinion Survey along construction road sections 56

iii

CURRENCY EQUIVALENTS (as of 21 June 2015)

Currency unit – Yuan (CNY) CNY1.00 = $0.1611 $1.00 = CNY6.2085

ABBREVIATIONS

ADB – Asian Development Bank ADB SPS – Asian Development Bank Safeguard Policy Statement 2009 CEWP – Construction Environmental Work Plan CIEE – Consolidated Initial Environmental Examination(i.e. many subprojects addressed in one IEE) dBA – A measure of audible (the ear) noise EARF – Environmental Assessment and Review Framework EIA – Environmental Impact Assessment EMP – Environmental Management Plan ESSU – Environment, Social and Safety Unit (established within YHAB) GRM – Grievance Redress Mechanism IEE – Initial Environmental Examination masl – metres above sea level PMO – Project Management Office PPTA – Project Preparation Technical Assistance PRC – People’s Republic of China RP – Resettlement Plan RoW – Right of Way SDAP – Social Development Action Plan SPS 2009 – ADB’s 2009 Safeguard Policy Statement subIDForm – Sub-identification form, provided in the project’s Operations Manual summarizing all features for a subproject vpd – Vehicles per day YEPD – Yunnan Environmental Protection Department YHAB – Yunnan Highway Administration Bureau YHDIC – Yunnan Highway Development and Investment Co. Ltd YPDOT – Yunnan Provincial Department of Transportation YSRI – Yunnan Science and Technology Research Institute of Highways YTPRDI – Yunnan Transport Planning Research and Design Institute

iv

WEIGHTS AND MEASURES

CO – Carbon monoxide kph – Kilometers per hour mu – Land measurement unit = 520m2

NO2 – Nitrate or Nitrogen Dioxide

SO2 – Sulphur dioxide TPM – Suspended particulate matter, with particles ≥ 10 microns in

size, and a danger to lungs. Also referred to as PM10

NOTE

In this report, "$" refers to US dollars.

v

Monitoring Indicators Water Quality SS – Suspended substance CODcr – Chemical oxygen demand pH – pH value DO – Dissolved oxygen NH3-N – Ammonia nitrogen Air Quality

PM10 – Inhalable particulate matter (particle size less than 10 microns, harmful to the lungs) NO2 – Nitrogen dioxide

SO2 – Sulfur dioxide

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of Asian Development Bank Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

vi

Acknowledgement We hereby want to show our great appreciations to all the following parties for their great guide and help on data collection and preparation of this report, including: Mr. Shen Haiping, the deputy director of YHAB, and Mr. Zhang Shijun and Miss. Wu Likun of YHAB; YSRI; Kunming General Section; and the leaders and staff members in S211 line project management office, have spent a large amount of time and efforts. The ADB project environmental specialist and project officer both participated in the completion of this report, and their inputs are acknowledged. The relevant design institutes, construction supervision companies and constructors, other relevant persons and experts participating in preparation of this component.

vii

Executive Summary

1. The Yunnan Sustainable Road Maintenance (Sector) Project (the Project) is located in Yunnan Province in the People’s Republic of China. The Yunnan Department of Transport (YPDOT) is the executing agency and the Yunnan Highway Administration Bureau (YHAB) the implementing agency. The latter manages non-tolled national highways, provincial roads and important county roads in the province. Condition of the network has been deteriorating resulting in a reduced level of service and safety, increased transport costs and environmental degradation. 2. The Project includes four outputs: maintenance of 866.8 km of national, provincial and county roads (Output 1); pilot of performance-based maintenance contracts (Output 2); development of a road asset management system (Output 3); and institutional development to enhance the performance and sustainability of YHAB road maintenance (Output 4). Maintenance activities will be implemented over five years in four Phases. 3. The Project was estimated to cost CNY 783.5283 million. The ADB loan will finance 68.7% or USD 80 million of the total project costs. YHAB’s Counterpart funds will be CNY 24544.83 or account for 31.3% of total investment. 4. The project management office of G211 line, the constructors and construction supervision companies performed their respective duties in accordance with the EMP. During implementation, environmental mitigation measures were carried out to reduce the impacts of construction on the surrounding environment and people’s health to the minimum as possible. They had minimized the pollution and improved local public transport.

1

I. Description of the Component 1. S211(Songming- line) is the important economic links from Xundian county to , Yiliang County in Kunming city, finally to Yuxi City. The ADB funded pavement restoration component mainly involves repairing the road pavement damage and subgrade gap, safety facilities and collapse, and restoring the original function of road. 2. The phase 1 of S211 line pavement restoration component, starts at the section K51+972, and ends up at the section of K125+086. It is divided into three parts. The first part, K51+972~K60+400, has the length of 8.428km, with the original grade four highway. The second part, K102+514~K105+114, has the length of 2.6km with the original secondary highway. The third part, K105+114~K125+086, has the length of 19.972km with the original grade four highway. The three parts have the total length of 31km. The route runs from Xiapingdi village, through Longiiezi Village, Dabeidang Village in Xundian County, to Zhangguanying Village and Xiaoshidong Villagein Songming County, to Liziqing village finally ends Xiaomuxi Village in Yiliang County. 3. This component commenced on December 12, 2014 and will be completed on December, 2015, lasting for 1 year.

2

II. Description of the Environment A. Geology 4. Songming County is located in the middle of Yunnan Province, and the northeast of Kunming City. It is an outskirt county of Kunming city. The county downtown seats 43 km away from Kunming City. Songming County is located in the east longitude 102°41′~103°21′, north latitude 25°05′~25°28′. Yiliang County is in its east and Guandu of Kunming City is in its south. is adjacent to its southwest. Its northwest and north are close to Xundian County, northeast connected with Malone County. Its total land area is 870 km2 including 4 towns, 75 villages committees including 446 villages. 5. Xundian County is located in the northeast of Yunnan Province, is the hub of Northeast Yunnan, in the east longitude 102°41′~103°33′ and north latitude 25°20′~26°01′, across the Jinsha River and Nanpan River Basin. The county's total area is 3,598 km2, with mountainous and alpine areas accounting for 87.5%. It has 6 towns, 10 townships,and 173 village committees. 6. Yiliang County, in the southeast of Kunming city, in the east longitude 102°58′~103°28′ and north latitude 24°30′~25°17′. Its east is and Shilin County, the south Mile County and Huaning County, the West , Chenggong Counties and , the north Songming and Malong Counties connected. Its total area is 1,886 km2, including basin and valley areas accounting for 11%, mountains areas accounting for 88%, and the water areas of about 1%.

B. Climate Condition 7. Songming has mild climate and good ecological condition. Throughout the county, the climate is mixed type climate with typical temperate zone, warm temperate zone and north subtropical. Its annually average temperature is 14 °C , rainfall of 993 mm, frost free period of 222 days, and sunshine 2,073 hours. 8. Xundian area is subtropical monsoon climate. Its average annual rainfall days are 134.6 days, with relative average humidity of 73%, evaporation from 1,870 to 2,120mm, annual average sunshine of 2,448.7 hours, and sunshine rate of 65%. Its dominant wind direction in many years is west-southwest. 9. The climate in Yiliang is mild. Belonging to north subtropical monsoon climate, its summer is not hot, and it has no cold winter. The annual average temperature is 16.3°C, with annual extreme maximum temperature 33.9°C, minimum temperature of - 6.2°C; average annual sunshine of 2,177.3 hours; the average annual rainfall of 912.2 mm; annual average relative humidity of 75%, and frost free period of 260 days.

3

C. Hydrology 10. Songming river system belongs to the Yangtze River and Pearl River Basins. Its surface water resource is very rich with volume of 510million cubic meters. It is the water resources of Panlongjiang and Niulanjiang rivers. 11. Xundian has about 20 rivers, mainly including Niulanjiang River, Keduhe River, Niujie River, Sijia River, and Xiangshuihe River, etc.. The longest one, Niulanjiang River, is the major tributaries of the Jinsha River, originally from Guoma Town in the county, flows through Jialize town in Songming County then back into Tangzi, Rende, Qixing, and Hekou townships (towns) in the county with the length of 75 km , finally to . 12. Yiliang County has Nanpanjiang River and its tributary of Maitian River, Zhangziba River, Jialong River, Baiyi River, Bajiang River. These rivers’ runoff areas are greater than 100 km2. Its mainly natural lakes have include Yangzonghai lake and Caodian sea. These rivers and lakes belong to the Pearl River water system. D. Natural Resource 13. Since ancient times, Songming has the reputation of ’Yunnan granary ‘ and ‘land of plenty’. It is a national commodity grain base county, key county of flue-cured tobacco production, commodity pig base county in Yunnan Province, and fresh-cut flower as well dried flower production county. Its forest belongs to eastern plateau warm broadleaf forest and warm coniferous forest sub region, rich in species with around 1153 plant populations, mainly including four types vegetation of coniferous forest, broad-leaved forest, shrub forest and bamboo. It has three rare and endangered plants. 14. Xundian is rich in mineral resources, mainly including three major resources of coal, phosphorus, and silicon, which reserves are large and high grade. There are more than 3million mu of natural grassland, 0.18 million mu of artificial grassland and magic spectacular Baishiyan Cave Group, the beautiful landscape of Fenglong Bay, Qingshuihai (‘Plateau pearl’), Nangu Springs in Tangzizhen, Zhonglingshan National Forest Park. It is also the world's southernmost wintering ground for black necked cranes, the world's rare species. 15. Yiliang County metal mineral resources mainly include iron, copper, lead, zinc and cobalt. Of which iron ore is in the first place, with reserves of 3.64million tons and grade of 51.07%. Nonmetal minerals include coal, phosphorus, barite, limestone, building sand, and clay. Among which, coal and limestone reserves are the most. Yiliang County has more than one hundred common wild animals, more than 1300 kinds of common wild plant, of which there are more than 100 species of common tree species, mainly including timber forest, economic forest, and firewood forest.

4

III. Report Preparation A. Policy, Legal, and Administrative Framework 16. PRC’s EIA legal system is applicable to only commercial or industrial development planning and construction projects. For the proposed road maintenance and rehabilitation works associated with this project, PRC’s Environmental Assessment Law does not apply; however, the following legislation does: (i) The Environmental Protection Law of PRC (1989), fundamental law; (ii) Management Directory of EIA Classification for Construction Project (MEP, 2008), (iii) Regulations on Review and Approval of EIAs for Construction Project (MEP, 2009), (iv) Regulation on Hierarchical Review and Approval of EIAs for Construction Project in Yunnan Province (2010), covering management of the whole EIA process; (v) Environmental Protection Management Ordinance for Construction Project (1998), (vi) Environmental Protection Management Regulation for Transport Construction Project (MOT, 2003), (vii) Environmental Protection Ordinance of Yunnan Province (2004), (viii) Notice on Enforcement of Environmental Supervision in Transport Construction Project (MOT, 2004), covering environmental management for the life cycle of the transport construction project; (ix) Water Pollution Prevention Law of PRC (2008) and relevant regulations, mandatory requirements for water pollution prevention and mitigation; (x) Air Pollution Prevention Law of PRC (2000) and relevant regulations, mandatory requirements for air pollution prevention and mitigation; (xi) Environmental Noise Pollution Control Law of PRC (1996) and relevant regulations, mandatory requirements for noise pollution prevention and mitigation; (xii) Solid Waste Pollution Control Law of PRC (2005) and relevant regulations, mandatory requirements for solid wastes pollution control and recycling; (xiii) Water and Soil Conservation Law of PRC (2010) and relevant regulations, mandatory requirements for soil erosion control; (xiv) Land Management Law of PRC (2004), (xv) Highway Safety Ordinance of PRC (2011), (xvi) Quota for Land Use of Highway Construction Project (Ministry of

5

Construction combined with Ministry of Land and Resources,1999), regulatory requirements for land acquisition of the highways; (xvii) Nature Reserve Ordinance of PRC (1994), Ordinance for Scenic Resorts and Historic Sites of PRC (2006), (xviii) Ordinance for Management of Nature Reserves in Yunnan Province (1998), mandatory requirements for conservation of the protected areas. (xix) Ordinance for Redress of Public Complaints (the State Council, 2005), Interim Procedures for Public Consultation in EIA (SEPA, 2006), and Environmental Complaints Management Regulation (SEPA, 2006), requirements for EIA public consultation and environmental grievance redress; (xx) Notice on Strengthening EIA Management to Control Environmental Risks (SEPA, 2003) (xxi) Interim Management Regulation for Contingency Plan of Environmental Incidents (MEP, 2010), management requirements for environmental risks control, preparation and implementation of environmental contingency plan; (xxii) Environmental standards and guidelines, including environmental quality standards for surface water, air, and ambient noise; emission standards for polluting sources of wastewater, air pollutants, and noise; as well as EIA guidelines such as Technical Guideline on EIA published by MEP. (xxiii) PRC guideline HJ/T169-2004, National Inventory of Hazardous Goods & MEP Dec.1, 2008. 17. Yunnan has a large number of international, national, provincial and local protected areas. For each Phase, determination of the location of any designated sites in relation to the roads to be maintained will be necessary.

B. Report Period 18. This report, the 1st quarter EMR of 2015, focuses on atmosphere, water and acoustic environmental impacts during the construction and various indicators before and during construction are compared.

C. Scope of Environment Monitoring 19. (1) atmosphere environment: within 200m on the two sides of the road center; (2) noise: Within 200m on the two sides of the road center, those nearest to the road, such as residential areas, buildings, schools, parks, hospitals and other sensitive points; (3) surface water: water quality of Xilongzhe Village, nearest to the road; (4) ground water: solid waste piling sites and sewage discharge points; (5) ecological environment:

6

the affected land, vegetation, animals and plants along the road.

D. Potential Environmental Impacts

20. The total mileage of S211 highway maintenance component reaches 31 km and it passes through 3 counties: Xundian, Songming and Yiliang. Through field survey along the road, the sensitive receptors involve at each section are listed in the following Table 1.

Table- 1 List of Environmental Sensitive Receptors Alongside S211 Line

Relative distance to the center line of the road Influence No. sensitive receptors Categories distance factors direction (m) Xiapingdi Village, Xundian noise, 1 residential area east 10 County dust

Longjiezi Village, Xundian noise, 2 residential area west 8 County dust

Dabeidang Village, Xundian noise, 3 residential area east 5 County dust

Dashuying Village of Yanglin noise, 4 residential area west 5 Town, Songming County dust

Health center of Laoyutun noise, 5 village committee in Yanglin hospital east 5 dust Town, Songming County

Nanchong Village, Yanglin noise, 6 residential area east 5 Town, Songming County dust

Xiaoshidong Village, Yanglin noise, 7 residential area both sides 5 Town, Songming County dust

Public garden of Xiaoshidong, noise, 8 activity center both sides 5 Yanglin Town, Songming County dust Xia Lizijing Village, Tangchi noise, 9 residential area west 10 Town, Yiliang County dust

7

Note: identification of sensitive area: a. Acoustic environment: concentrated residential areas, schools, hospitals, elderly care centers; b. Atmospheric environment: concentrated residential areas, schools, hospitals, elderly care centers; c. Water environment: drinking water source protection area, water intake; d. Influencing factors: surface water, groundwater environment, atmospheric environment, noise; e. The nature of the category: water source, residential area, school, hospital.

8

IV. Implementation of EMP A. Detailed design drawings and bidding documents 21. The detailed design drawings include environment management, and EMP is also included in the bidding documents.

B. Institutional Arrangements 22. Yunnan Highway Administration Bureau (YHAB), the implementing agency(IA), is responsible for organizing, coordinating and supervising the implementation of this component. The project management office of G211 line had been set up in Kunming General Section.

C. Construction Supervisors 23. Yunnan Yunlu Engineering Supervision Consulting Co., Ltd, with Class A construction supervision qualification, is the supervisor of S211 component. With good testing equipment and strong technical capacities of construction supervision, this CSC has undertaken all types (I,II,III) of highway project supervision.

D. Implementation status of the mitigation measures 24. Implementation status of the mitigation measures during this reporting period are summarized in the Appendix 1. The implementation status of the mitigation measures are summarized in the last columns of the tables for comparison with the designed mitigation measures stated in the EMP. In summary, the mitigation measures have to date been implemented effectively. 25. In accordance with clauses and technical specifications in the construction contracts and the EMP, corresponding mitigation measures are adopted during construction management. Specific measures are shown as follows (The site photos pls. see the Appendix 2): 26. Water: There is a small reservoir within the component area- Xizhelong reservoir, which mainly serves for local agricultural water. In the maintenance section of S211 line, about 50m will be constructed along the reservoir. Main measures are shown as below: a. No soil borrowing or spoil was required,therefore, it does not have construction wastewater. During the construction period, a small amount of construction dust flew into the water, but had little impact. b. Equipment maintenance and refueling were undertaken in the fixed places, rather than on the construction sites, which did not permeate into the water body.

9

c. The equipments and vehicles were cleaned up in the vicinity of nearby car washing shops, so the maintenance section did not generate vehicle washing wastewater. d. The maintenance component involves pavement gradation, cement stability layer and asphalt directly on the original road, excluding few parts needed to be replaced, did not generate construction wastewater. e. The constructors leased the existing asphalt mixing station, which was set in the abandoned quarries, without any water body or resident nearby. The asphalt spill was also collected and processed in the container. The groundwater was not affected by surface runoff. f. On construction sites, no new barrack was built. The S211 line project management office, the supervisors and the contractors rented house of local villagers as workplace, with toilet and septic tank. Domestic wastewater and catering wastewater was not directly discharged. 27. Air: The impact of the air quality is mainly from smoke, dust and exhaust of construction machinery and vehicle, etc..Main mitigation measures are shown as below: g. The constructor was equipped with 6 sprinklers, 2 times a day, and increased to 4 times at construction section near the villages. h. Hauling trucks in bulk materials were covered by canvas as much as possible to reduce the dust during transport. i. Material mixing stations were built on the abandoned quarry, without any resident nearby, therefore, the generated dust little effect to the public. 28. Noise: Noise pollution at construction stage is mainly caused by the construction machinery and vehicle hauling activities. The constructor worked from 8:00-18:00 time during daytime, and at night without construction. If at construction section near the villages, construction stopped during 12:00-14:00 to avoid disturbance with the villagers. 29. Solid waste: During construction period, the earth materials, asphalt, gravel were piled in the slope less than 5% in the fixed places. 30. Soil erosion. Soil erosion of the component was mainly caused by solid waste, construction waste, leaking oil in case of rain runoff. Main mitigation measures are shown as below: j. Only a small amount of pavement material was used to repair the pavement, so did not need to dispose of solid waste. k. Before daily construction, firstly checking the construction vehicles

10

and machinery status. If any problem, the vehicle was sent to the nearest vehicle repair shop for maintenance. Vehicle was refueled in the refueling station in the vicinity. l. On the construction sites, there was no vehicle maintenance and refueling. m. Renting nearby village houses as a living area and office area, so the garbage generated by the construction workers was collected by the community sanitation department. n. The constructors leased the existing asphalt mixing station, which was set in the abandoned quarries, without any water body or resident nearby. The asphalt spill was also collected and processed in the container. The groundwater was not affected by surface runoff.

31. Flora and Fauna: Within the scope of construction area, no ancient tree has been found. The construction sites was limited on the original road, without expansion or no excavation and blasting operations, therefore, it did not affect the roadside farmland and trees. 32. Health and Safety. Health and safety education is the important content during construction period. Most construction workers are local villagers. If any illness, they went to local community hospitals for medical treatment. In order to ensure the construction safety and quality, before construction, the constructors conducted safety and skills training for all the staff. Main mitigation measures are shown as below: o. Worker personal protection. Before construction, all construction workers are trained on use of personal protection equipments. p. At the construction sections, the bulletin boards were erected. q. All workers were provided with protective masks, gloves, safety vest, helmet and protective shoes, etc..On-site construction workers were wearing eye-catching safety vest. r. Renting local village houses as office space, equipped with drinking water, life necessities, and clean public toilets. s. Daily supervision and inspection of the construction workers whether safety protection measures were completed, the construction equipments were under normal operation according to standard procedures. Daily or weekly logs of supervision were kept. t. Irregular maintenance on the vehicles and construction machinery. u. Regularly inspecting the cable lines in the construction area to

11

eliminate the safety hazard. 33. Landscape: S211 line is not within the scope of the scenic area, so the natural landscape will not be significantly impacted. The construction equipment and material was only temporarily stored, will be recovered after completion. Main mitigation measures are shown as below: v. The village houses were rented as office space and for living. Construction sheds were built along the sides of the road, so the landscape was not affected. w. Rented houses were equipped with garbage pool. The community sanitation management department regularly collected then transported to the landfill for disposal. x. Trucks with bulk materials were covered with canvas in order to keep the vehicle clean and tidy as possible. y. No new path was built to avoid the destruction of land or vegetation. z. Mixing station and material yard were leased with local existing equipment and facilities, and will be recovered after completion.

E. Analysis of Environmental Monitoring Results 34. Water quality monitoring: Xizhelong Village reservoir mainly functions for agricultural irrigation. The SS should meet the The Water Quality Standards For Irrigation (Ministry of agriculture, see Table 2), and other indicators should meet Class III standard of Environmental Quality Standards For Surface Water (GB3838-2002, see Table 3). YSRI conducted on-site sampling and monitoring on Xizhelong Village reservoir. The monitoring results are indicated as follows (see Table 4).

Table- 2 Standards for irrigation water quality(GB5084-2005) Unit:mg/L No. Item Type of Crops Standard Limit

1 SS Aquatic Crop <=80

Table- 3 Environmental quality standards for surface water(GB3838-2002) Unit:mg/L No. Item Class I Class II Class III Class IV

1 CODCr 15 15 20 30

2 pH 6-9 6-9 6-9 6-9

3 DO 7.5 6 5 3

12

4 NH3-N 0.15 0.5 1.0 1.5

Table- 4 Water Quality Monitoring Results of the reservoir in Xizhelong Village Unit:mg/L

Monitoring CODCr pH DO NH3-N SS Point

Construction 3 8.25 8.49 0.00 3 Period(10 Mar.2015) The Complied reservoir Compliance Status Class I Class I Class I Class I with in Xizhelong Prior to Construction 4 8.45 8.77 0.00 2 Village (24 Dec.2014)

Complied Compliance Status Class I Class I Class I Class I with

35. Evaluation of water quality monitoring results. The monitoring results of Xizhelong Village reservoir show little change in water quality between pre-construction and construction period, and water quality have both reached the class I of Surface Water Environmental Quality Standards (GB3838-2002). It is relatively dry in winter in Yunnan, with less rainfall or surface runoff. At the same time, it also shows that the construction of the component did not cause water pollution by. 36. Air quality monitoring. The main pollutants in the construction period are dust and asphalt. Along the road, the Class II standard in the Ambient Air Quality Standard "(GB3095 - 2012) should be complied with, as shown in table 7. YSRI undertook on-site air quality monitoring. The results are as follows (see Table 6).

Table- 5 Ambient air quality standard(GB3095-1996) Unit:mg/ m3 Class I, Standard Class II, Standard Item Sampling Period Limit Limit

PM10 Daily Average 0.05 0.15

NO2 Daily Average 0.08 0.12

SO2 Daily Average 0.05 0.15

13

Table- 6 Air Quality Monitoring Results Nearby S211 Unit: mg/m3

Monitoring Indictor PM10 NO2 SO2 Applicable Standards Point 0.15 0.12 0.15 (Class II) Construction Period(10 0.021 0.073 0.046 Mar.2015) Compliance Status Complied with Complied with Complied with Along S211 Prior to Construction (24 0.017 0.069 0.052 Dec.2014) Compliance Status Complied with Complied with Complied with

37. Evaluation of air quality monitoring results. From the above data, the air monitoring indicators, PM10, NO2 and SO2, before construction and construction period, had little change and both were better than Class II standard in the Ambient Air Quality Standard "(GB3095 - 2012). It shows that the construction activity has no serious influence on the surrounding air quality. 38. Noise monitoring: The construction noise has a certain effect on the sound environment quality, which is mainly caused by the construction machinery and vehicles. 39. For S211 line, the Class 4a standard in the Standards for Acoustic Environmental Quality (GB3096-2008) (see Table 7) should be complied with. During construction phase, Emission Standard of Environment Noise for Boundary Of Construction Site (GB12523-2011(see table 8) is applicable. The main noise source during the construction period sees Table 9, and the noise monitoring results are shown in Table 10. Table- 7 Environmental quality standard for noise (GB3096-2008) Unit:dB (A)

Noise Limit LAeq(dB) Acoustic environment functional area Daytime Nighttime

Class 4a 70 55 1

Table- 8 Emission standard of environment noise for boundary of construction site(GB12523-2011)

Daytime(LAeq(dB)) Nighttime(LAeq(dB))

14

70 55

Table- 9 Major Noise Source

Noise Limit LAeq(dB) Period Major Noise Source Daytime Nighttime

Construction All kinds of vehicles 70 55

Period All kinds of vehicles, concrete mixer, etc. 70 55

Bulldozer, excavator, paver 75 55

After All kinds of vehicles 70 55 completion

Table- 10 Noise Monitoring Results of Contract Package No.1 ( Section) Unit: dB (A)

Distance LAeq(dB) Environmental to the Compliance Period Time Sensitive road Standard MonitoringValue Status Receptors center limit line(m) Xiapingdi Village, Complied 10 53 70 Xundian County with Longjiezi Village, Complied 8 49 70 Xundian County with Dabeidang Village, Complied 5 57 70 Xundian County with Dashuying Village Pre- 9:00-17:00, Complied of Yanglin Town, 5 53 70 construction 24 Dec. with Songming County 2014, Daytime Health center of Laoyutun village Complied committee in 8 58 70 with Yanglin Town, Songming County Nanchong Village, Complied 5 65 70 Yanglin Town, with

15

Songming County

Xiaoshidong Village, Yanglin Complied 5 55 70 Town, Songming with County Public garden of Xiaoshidong, Complied 5 59 70 Yanglin Town, with Songming County Xia Lizijing Village, Complied Tangchi Town, 10 48 70 with Yiliang County Xiapingdi Village, Complied 10 47 55 Xundian County with Longjiezi Village, Complied 8 47 55 Xundian County with Dabeidang Village, Complied 5 45 55 Xundian County with Dashuying Village Complied of Yanglin Town, 5 50 55 with Songming County Health center of Laoyutun village Complied committee in 8 51 55 with 22:00- 5:00 Yanglin Town, 24 Dec. Songming County Nanchong Village, 2014, Complied Yanglin Town, 5 46 55 Nighttime with Songming County Xiaoshidong Village, Yanglin Complied 5 48 55 Town, Songming with County Public garden of Xiaoshidong, Complied 5 44 55 Yanglin Town, with Songming County Xia Lizijing Village, Complied Tangchi Town, 10 47 55 with Yiliang County Constructi Xiapingdi Village, Complied 9:00-17:00, 10 56 70 on Xundian County with 10 Mar. 2014, Longjiezi Village, 8 60 70 Complied

16

Daytime Xundian County with

Dabeidang Village, Complied 5 51 70 Xundian County with Dashuying Village Complied of Yanglin Town, 5 64 70 with Songming County Health center of Laoyutun village Complied committee in 8 57 70 with Yanglin Town, Songming County Nanchong Village, Complied Yanglin Town, 5 55 70 with Songming County Xiaoshidong Village, Yanglin Complied 5 57 70 Town, Songming with County Public garden of Xiaoshidong, Complied 5 59 70 Yanglin Town, with Songming County Xia Lizijing Village, Complied Tangchi Town, 10 57 70 with Yiliang County Xiapingdi Village, Complied 10 43 55 Xundian County with Longjiezi Village, Complied 8 46 55 Xundian County with Dabeidang Village, Complied 5 35 55 Xundian County with Dashuying Village Complied of Yanglin Town, 5 45 55 22:00- 5:00 with 10 Mar. Songming County 2014, Health center of Laoyutun village Nighttime Complied committee in 8 39 55 with Yanglin Town, Songming County Nanchong Village, Complied Yanglin Town, 5 43 55 with Songming County

Xiaoshidong 5 42 55 Complied

17

Village, Yanglin with Town, Songming County Public garden of Xiaoshidong, Complied 5 44 55 Yanglin Town, with Songming County Xia Lizijing Village, Complied Tangchi Town, 10 41 55 with Yiliang County

40. Evaluation of noise monitoring results. 9 representative monitoring points was set along the S211 line. The main noise source during construction period is social traffic noise and construction machinery noise. Because construction is prohibited at night, construction machinery noise has little effect on the surrounding residents. All the monitoring result meets national standards. F. Institutional Capacity Building and Training 41. YHAB strengthened the implementation of the component, and facilitated with environment, social, safety and other aspects of experts. 42. The PMO, S211 line project management office, CSC, and the constructors assigned EHS staffs. Please see Table 11. Table- 11 List of EHS Staffs

Name of EHS Staffs Dept. Name Gender Position Phone. No. ADB Project Management Wang Xin M EHS specialist 18687194563 Office in YHAB Project Management Zhou Kaili M Chief Engineer 13700645862 Office of S211 Project Management Liu Caiying F Traffic Directing Specialist 15911605941 Office of S211 CSC Ji Zhiguo M Construction Supervisor 15987139831

Constructor Mao Yun M Safety Engineer 13987411689

Constructor Han Tao M Safety Engineer 13698770407

Constructor Yu Yacai M Constructor 13888660396

43. In order for implement the mitigation measures and environmental monitoring, before entering construction sites, ADB's environmental

18

experts provided training related to environmental protection to the CSCs and constructors. The training was mainly focused on implement the mitigation measures and environmental monitoring. Training activities were held in the S211 line project management office meeting room. Training activities include the following aspects: a. Understanding and application of internationally accepted environmental management practices. b. Compliance monitoring method, required equipment and methods. c. Compliance monitoring information analysis. d. Environmental safeguards enforcement methods and measures. e. Training contents include case studies and field trips.

19

V. Public Consultation, Information Disclosure and Grievance Redress Mechanism A. Public Consultation, Information Disclosure 44. On March 10th of 2015, YSRI carried out a public opinion survey to the public along S211 line. The below questions asked are as follows: (I) Do you think there is any impact of the noise and dust generated during construction on your production and life? (ii) During the construction period, is there any influence on your trip due to traffic control? (iii) Any impact on your farmland and crops during the construction period? (iv) How do you think the constructors to take measures to mitigate environmental pollution? (v) Should overloading vehicles be controlled? 45. During consultation, some villagers said during construction period there was a small amount of environmental impact, but the impact period was short, the constructors took mitigation measures, such as regular watering, stopping construction at noon time, and covering haulage vehicles with canvas, etc..These measures reduced dust a lot. After the completion of the component, these impacts will be reduced or disappear. Respondents said they supported the road maintenance component. Table- 12 List of Persons Consulted With

No. Name Gender Minorities Profession Name of Village Wang Xiaoshidong Village, Yanglin 1 M Han Villager Zhengchuan Town, Songming County Huang Mafang Village, Yanglin Town, 2 F Han Driver Zhizhen Songming County Xiaoshidong Village, Yanglin 3 Wang Shoujiu M Han Villager Town, Songming County Xiaoshidong Village, Yanglin 4 Li Jufen F Han Villager Town, Songming County Xiaoshidong Village, Yanglin 5 Xia Hongshun M Han Villager Town, Songming County Migrant Xiaoshidong Village, Yanglin 6 Ding Xiuying F Han Worker Town, Songming County 7 Zhao Lianbao M Han Villager Xiaoshidong Village, Yanglin

20

Town, Songming County

Zeng Nanchong Village, Yanglin Town, 8 M Han Villager Zhaoming Songming County Zhao Xiaoshidong Village, Yanglin 9 M Han Villager Shenghua Town, Songming County Diantou Village, Yanglin Town, 10 Zhang Lixian F Han Villager Songming County Dashuying Village of Yanglin 11 Tao Xiufen F Han Driver Town, Songming County Migrant Nanchong Village, Yanglin Town, 12 Zeng Chao F Han Worker Songming County

B. Grievance Redress Mechanism (GRM) 47. YHAB established environmental GRM, and publicized the relevant information, such as phones numbers, etc. 48. During construction, the constructors and the relevant village committees have not received any complaint. 49. The procedures of GRM is shown as below.

PERSON WITH GRIEVANCE STEP 1 Resolve issue with contractor or village 5 days committee

STEP 2 ESSU to Resolve issue with YHAB facilitate and Maintenance or General 2 weeks track Section resolution and report to ADB STEP 3 Resolve issue with 2 weeks Prefecture Government

Figure- 1 Procudures of Project GRM

21

46. The basic grievance redress steps are described below and shown in Figure 4. The ESSU will be responsible for facilitating, tracking and reporting grievance resolution at each step: Step 1: The affected person should first try to resolve the issue of concern directly with the contractor and the local village committee. A solution must be presented within five days. If successful, no further follow-up is required. Step 2: If there is no resolution the person can file the grievance with the county office of YHAB, the Maintenance Section or the Prefecture level Office the General Section. A resolution must be reached within two weeks Step 3: If no resolution is found the complainant can take the next step and contact the county or prefecture government offices where resolution will be required within two weeks.

22

VI. Conclusions and Suggestions 47. During construction, the S211 line project management office, the constructors and CSCs had taken the corresponding environmental impact mitigation measures in the EMP. The construction noise, dust and wastewater, and other impacts on the surrounding environment were reduced to a minimum. 48. Through field inspection, according to relevant national environmental protection laws and regulations, ADB's SPS (2009) and the EMP, the constructors strengthened environmental protection, water conservation, safety and other aspects. The environmental impacts of the component during the construction period were limited, and the construction period was short. With the completion of the component, the pollution will be eliminated in time, and the environment will revert to the state better than the original. From the point of view of the whole process of construction, the constructors strictly abided by the provisions, actively took mitigation measures to reduce pollution. So it obtained the strong support of the local community and the village. During this period, no any pollution complaint did occur. 49. Suggestions: (i) Local villagers were hired, and their mobility was frequent. To address their potential safety issue, it is recommended to provide safety education and training before hire local villagers in a timely manner. (ii) Some road safety signs were not obvious or missing, so should be promptly installed or repaired. And (iii) Safety and environmental protection awareness education should be carried out to improve safety and environmental awareness of the villagers and construction workers then to reduce environmental pollution and ecological damage.

23

Appendix 1: Summary of Potential Environmental Impacts And The Mitigation Measures Implemented (As of June 2015)

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action

1. PRECONSTRUCTION PERIOD

Complied with. 1.1 Lack of environmental technical 1.1 YHAB will establish a unit, the ESSU, to manage environmental, capacity within YHAB and its General and social and safety aspects of maintenance projects. The ESSU will be ESSU was established prior to loan effectiveness. Maintenance Sections in environmental staffed by 3 full-time suitably qualified people. ADB will support assessment and design, management, international and national environmental consultancy services to YHAB training was completed during detailed supervision and reporting. develop and deliver a 5-day environmental assessment and design and prior to bidding. management training workshop for YHAB staff and a 2-day workshop

for first year Contractors. Contractor training was on appointment. Complied with or to be complied with. 1.2 1.2 ESSU will provide the design team with translated copies of IEE,

EMP and templates and check relevant clauses have been included. Translation of IEE, EMP, contract clauses Translated during detailed design stage and and other templates for use by General and YHAB/ESSU will provide the successful contractor with translated provided instructions prior to contractor field Maintenance Sections, copies of IEE/EMP and assist contractor to prepare the Construction mobilization. Environmental Work Plan (CEWP).

General Section will provide the Maintenance Section site engineer As part of 1.1, workshop was held in General with the IEE, EMP and other templates for use in their inspection Sections . process. Given the uncertainty of inspection qualifications , the workshops as defined above will be held at the six General Section

24

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action offices

Complied with. 1.3 1.3 ESSU will check that design and bid documents are responsive

to key environmental, social and safety considerations. Consideration of IEE/EMP in preparation of Before the bid documents for Section 3 and 6, the NA the detailed design and bid documents. contracts were completed

Complied with. 1.4 1.4 During detailed design YHAB will incorporate mitigation measures

defined in the IEE as follows:: Optimise design and planning of works to minimise impacts 1. minimize the removal of mature trees from roadsides;

2. optimise traffic management to minimise access restrictions

3. provide step-by-step guidance on environmentally acceptable bridge and culvert replacement methods

Complied with. 1.5 1.5 Four weeks before work begins announce the project on roadside

sign(s), at a location(s) easily accessible by the public. Signs should be Announcement of subproject with road At both ends (boundaries) of the project. presented in a language that can be understood by affected people, in signs Yunnan, there may be a need to provide signs in multiple languages. 3-4 weeks before the start of work At the same time, provide information on the construction activity via the Maintenance Section

2. CONSTRUCTION PERIOD

2.1 Preparation of Environmental Documentation

25

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action Complied with. 2.1.1 2.1.1 Contractor team will include a specialist with environmental

assessment experience to prepare the CEWP and obtain all relevant Technical environmental capacity of Prior to the start of the construction work. permits. The contractor will not be permitted to mobilize the workers Contractor to prepare the CEWP and to without an approved CEWP and the appropriate permits in place. implement all mitigation and monitoring measures

2.2 Soils, Earthworks & Erosion

Complied with. 2.2.1 2.2.1 Large volumes of crushed quarry rock, aggregate and sand may

be transported to and/or stored in the work site. These operations and Management of earthworks transport and Construction roads were enclosed with colored storage areas will be constantly exposed to the elements and will Storage procedures, including cleaning; fence. create primarily dust during the frequent windy conditions, and some leading to dust and air pollution Hauling vehicles were not overloaded, and silty runoff. covered with waterproof canvas. Dust will be managed by daily use of watering trucks, subject to The constructors sprayed water with sprinklers at availability of water. 2 times a day. In the vicinity of the villages and the All topsoil needs to be collected, stored and reused to schools, the frequencies of watering were rehabilitate/revegetate the areas disturbed. This is applicable only to increased. projects with IEEs

Complied with. 2.2.2 2.2.2 Contractor will be required to know the subsoil materials that are

being cut into and excavated and have ready appropriate plans to stop Erosion control and slope stabilization, risk Based on an analysis of soil conditions by land slippage and erosion,. At water crossings where structures are to of land slip and chronic erosion at cuts and contractor and consultation with the General be upgraded, careful replacement and use of gabions with culverts and water crossings. Sections hydrology and geotechnical expertise. bioengineering methods for rapid revegetation and slope stabilization Construction activities were limited on the original

26

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action will be used. Bioengineering approaches to be explored as described road, without building a new road. in Annex D.

Not applicable. 2.2.3 Slope slippage and landslide zones 2.2.3 In any road sections where maintenance takes place and where left unaddressed there is a history of landslides and slope slippage, the contractor will be required to report any such conditions (if not already known) to the Maintenance Section and propose a costed remedial action, then undertake this work to stabilize the road and reduce risk of failure; including bioengineering solutions, metal netting and other proven methods.

Not applicable. 2.2.4 2.2.4 Any need for borrow material outside of the RoW will be subject

to local environmental approvals and procedures and should also be Risk of erosion, landslide and destruction of No borrow pit is required. carried out in consultation with ADB. Bioengineering approaches landscape from side borrow operations should be considered.

Complied with. 2.2.5 2.2.5 Side casting of waste earthen materials is not permitted where

slope is more than 5% and a side cast waste materials cannot be Side casting of waste by Contractor No waste dumping. easily stabilized and prevented from eroding during a rain event, or degrading down-slope area and blocking/ extend outside the road RoW. contaminating water body

Complied with. 2.2.6 2.2.6 When encountering contaminated materials or it is a construction

waste, contractors will follow PRC national and provincial Handling of contaminated construction requirements, consulting with EPBs if needed waste materials

27

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action Complied with. 2.2.7 Inappropriate disposal of spoil from 2.2.7 Contractors will be required to a) attempt to recycle all clean No soil dumping. construction work leading to contamination spoils material where possible and b) consider composting or b) dispose of all other material at sites approved by the local EPB.

2.3 Poor Contractor Operating Procedures

Complied with. 2.3.1 2.3.1 Contractors will adhere to standard good housekeeping practices

as defined in the contract Terms & Conditions and Contract Failure to adhere to construction related Solid waste was collected in certain places and Specifications. Special considerations will be given to good housekeeping practices, including transported regularly. solid and sanitary waste management 1. management of construction waste and water 2. equipment lubricants and fuel, including management and Renting nearby farmers’ houses. collection of waste oils and fuel particularly related to Septic tank was equipped with. refuelling depots, maintenance areas and diesel generator Fecal sewage and catering wastewater were sets discharged separately. Not affecting surface water. 3. Sewage will require latrines or chemical toilets with complete clean up after the construction is complete.

4. Garbage will be collected and properly disposed of after recycling and sorting,

This work will be completed in accordance with PRC, regulations and standards which the contractor will be expected to know. Also, the contractor shall orient all construction workers in basic sanitation and health care issues, and on the specific hazards of their work and will need to certify to that effect at the start of the construction period.

28

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action 5. Once the site is no longer needed the contractor must fully decommission it, with special emphasis on waste removal and clean up of any spills or hazardous materials plus any necessary revegetation.

Complied with. 2.3.2 2.3.2

Management of bitumen storage, asphalt, YHAB has indicated that no new facilities will be needed, but for sealcoat and concrete production facilities smaller jobs bitumen will be stored at the worksites. Under these to avoid leakage, dust and air pollution for conditions, the contractor will be required to provide secure locations community in vicinity for storage, handing and safe disposal of any worksite bitumen supplies. PRC’s hazardous materials handling regulations ( as defined in IEE, Section II) will be adhered to.

Not complied with. 2.3.3 2.3.3 Contractor will be required to have the following spill prevention The

measures in place at all work sites: construct Management of petroleum products such Asphalt overflow was found in an asphalt or should as fuel, lubricants and bitumen to avoid spill 1. all fuelling to be done on a concrete surface provided with mixing station. Neither container is used to provide and contamination. spill catch surfaces that can be cleaned and all spilled fuel collect the overflow asphalt, nor does it take container recovered and recycled based on discussions with fuel pavement measures around the overflow to collect supplier. outlet. the 2. All repair and maintenance work must either be done on a overflow concrete surface with oil spill catch basin or oil catch pans asphalt, must be provided at all service areas and training provided to and take all ‘mechanics’. pavement 3. All fuel use areas where spills and leakage is possible, e.g. measures

29

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action the generator, must have drip basins installed to prevent any around leakage. These recovered materials must be recycled. the overflow 4. A fuelling areas must be equipped with proper non-drip fuel outlet nozzles immediate 5. All fuel tanks must have means for containment of accidental ly. spills.

6. All bitumen handling must not permit any material from leaking to the ground, including transfer areas and any areas where bitumen is transported in drums.

7. Bitumen drums must be stored in a dry covered secure place where no leakage to water or ground is possible. Drums must be recycled at least once a year.

8. Any spills must be cleaned up and contaminated soils and water treated according to PRC regulations and standards within 24 hours of the occurrence.

Complied with. 2.3.4 2.3.4 The tonnage of material hauled must not exceed the road

capacity. If the material mobilization causes damage of the road, Overloading of construction vehicles No overloading in all materials hauling roads. then contractor must repair it immediately. leading to damage to existing roads

Complied with. 2.3.5 2.3.5 The contractor will need to demonstrate that an attempt has

been made to reuse, recycle, convert by composting construction No or inadequate consideration for wastes such as asphalt, wooden materials, plant materials and other recycling and reuse of construction

30

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action ‘wastes’ by the contractor benign organic matter

Complied with. 2.3.6 2.3.6 Contractors will be encouraged to complete the work as quickly All

as possible, consulting with local communities on best timing and constructio Work Duration agreeing to such a timetable n sites

2.4 Surface Water, Drainage and Water Pollution

Complied with. 2.4.1 2.4.1 When modifying or interfering with surface drainage of any sort

the contract will have to undertake the following: Modification of surface drainage during No bridge or culvert involved. culvert and bridge replacement and/or 1. All culverts must be sized at or larger than the one being raising of horizontal road alignment replaced and with care about slope and erosion protection at Drainage ditch built. inflow and outflow. All construction materials at the entrance Well maintenance to keep smooth. of culverts must be removed so as not to provide any obstruction. Culvert removal and replacement will be done when there are low flows or no water in the channel and during the dry months of the year. Confirm culverts are clear of debris on completion.

2. Bridges will be repaired and widened and as such there will be machinery at least at the water edge. Maximum care is needed to avoid degradation of the river, stream shore and to undertake excessive excavation at the shore and in the water (at least not when there is water in the stream). Demolition must be done in a way that prevents large chunks of material from falling into the river. Stabilization of disturbed crossing

31

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action banks must take place as part of the construction work and include filter fabric, gabions and preferably bioengineering techniques.

3. Where horizontal alignments are raised to reduce flooding, extra care is needed to ensure that all drainage channels convey water properly. The contractor must undertake a surface drainage inventory of the future raised road sections, identifying where there will be new culverts or where existing culverts need to be replaced or relocated. This inventory needs to be submitted to the supervising engineer.

4. When modifying the existing drainage system through culvert replacement, the contractor must minimize flood risk by carefully confirming that all works to be undertaken will not flood roadside properties due to improper design or construction practices. The contractor will be required to fully rehabilitate property damaged due to flooding.

Complied with. 2.4.2 2.4.2 Where drainage from a construction site involves more than 20

linear meters of roadway, a drainage channel into a grassed area of Management of contaminated construction some detention area allowing an suspended sediment and minor wastewater contaminants to settle, must be prepared by the contractor(s).

Complied with. 2.4.3 Fuel storage for generators powering 2.4.3 All fuel storage sites must be checked daily for leaks and held in Had taken measures to prevent oil spills. the asphalt plant, aggregate preparation an impervious site where spilled/leaking material can be collected. Without refueling facilities, equipment onsite and plant, and for vehicles and avoidance of

32

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action leakage of hazardous materials into surface vehicle cleaning is not in the construction site, but and groundwater. in the car wash area outside construction site.

Complied with. 2.4.4 2.4.4 TPM, SO2 and NO2 will be monitored once a month. Two

samples will be taken (one during the morning traffic peak, and one Air pollution PM10, SO2 and NO2 were monitored. when construction has stopped for the day) at each of six stations

along the road.

2.5 Air and Noise Pollution

Complied with. 2.5.1 2.5.1 Emissions will be kept to a minimum by:

Construction-period air pollution 1. ensuring that the contractor’s fleet of vehicles are properly maintained according to manufacturers specifications; and 2. use acceptable fuel and haul loads within specified limits.

3. Vehicle idling time limits to no more than 2 minutes and

4. equipment maintenance specifications will be imposed through construction inspection and regular reporting,

5. Dust control at the construction site will be particularly stringently controlled by watering, setting strict speed limits of no more than 30kph in or near settled areas, and sweeping of paved haul roads.

6. Equipment such as the diesel generator will be included in the

33

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action emission control program and will be and regularly tuned to prevent excessive TPM pollution.

Complied with. 2.5.2 2.5.2 Due to respirable silica dust from cutter heads, contractor needs

to have water spray nozzles on milling machine a) directed at the point Dust and noise from road milling machine of cutting and the drum, one nozzle every 30-40 cm and b) nozzles along the conveyor on both sides every ½ meter. Avg. water flow should be around 24L/min. Alternative is to provide dust masks to all operators and workers supporting the milling operation

Complied with. 2.5.3 2..5.3 Mitigation will involve

Managing dust, noise and drainage 1. enforcing a speed limit of 30 kph within 500m of any village associated with earthworks and haul roads. and the use of chemical dust suppressants at least on road for 500m on either side of a village, Same approach is to be taken if the other site is used.

2. restricting operating hours through roadside villages and settlements to between hours of 0800 and 1800.

Complied with. 2.5.4 2.5.4 At the same locations and times that surface water quality is

tested, noise measurements will be completed, but with site Excessive Noise variations focused on sensitive receptors such as schools, residential areas and health care facilities. Measurement frequency will be the same as for air quality

2.6 Flora and Fauna

34

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action

2.6.1 2.6.1 For each section of the road, contractors are required to develop a sketch map of the location number and species of trees Protection of roadside trees and shelter belt along the roadside that are located within the area likely to be cleared. planting along roadsides In areas where there are large trees creating a treed/shaded corridor, Complied with. designers will be contacted and alternative designs, such as narrowing

the carriageway and transforming this area into a roadside rest area should be discussed and an option found that requires the minimum tree loss. Any tree removed will be replaced by replanting several (>2) young trees of the same species.

Complied with. 2.6.2 2.6.2 Specify native species of local provenance that are appropriate

for the local setting for any new areas of landscaping. Selection of landscape species and management of arisings Ensure that any invasive species cleared during landscape works are managed in accordance with PRC regulations and standards.

Consider opportunities for establishing composting facilities at General and Maintenance Sections, to enable recycling of green waste.

2.7 Cultural Sites and Local Communities

Not applicable so far. 2.7.1 2.7.1 Since all the work is within existing RoWs and in previously

disturbed soil, the risk of loss of historical or cultural relics is highly Loss of physical cultural resources unlikely. However when widening roads in villages and towns, contractors will have to meet with local mayor to consult about any possible past relics or foundations of old buildings along the road. Contractor will also need to consult the database on archaeological

35

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action sites in Yunnan, retained with the Provincial Cultural Relics Department as well as the County Cultural Relics Bureau. Any finds during works must be reported to the Maintenance Section Head and all construction work stopped until authorities have inspected the site.

Complied with. 2.7.2: 2.7.2 Contractor shall provide safe and convenient passage for Before construction, a notice had been issued. vehicles and pedestrians to and from side roads and properties Loss of access for roadside residents During the period of limiting access, traffic control connecting the project road/area, whether public or private. Work that personnel was responsible for directing traffic. affects the use of side roads and existing access shall not be On construction sites, public signs was undertaken without provision of adequate alternate routes; to the prior established to provide phone numbers and other satisfaction of the Engineer and affected persons. information of the IA, supervisor, constructor. 2.7.3 2.7.3 Temporary bypasses will be constructed with the approval of Complied with. Traffic/access diversions and road dust the Engineer and in consultation with affected persons. management The temporary traffic detours shall be kept free of dust by frequent sweeping or application of water. Complied with. 2.7.4 2.7.4 Contractors will be required to conduct rigorous inspections of

the work sites to be sure that there are no stagnant waters. This will Spread of Vector-Born Diseases include removal of items such as old tires, drums and other receptacles where water can collect. These are all breeding grounds for malaria, encephalitis and dengue fever mosquitoes.

2.7.5 2.7.5 In order to protect the safety of communities on the construction Complied with. Community safety zone contractors will need to provide appropriate traffic management, lighting, management of excavations and making communities aware of any particular hazards.

36

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action 2.7.6 2.7.6 Contractors will be encouraged to hire at least unskilled labour Complied with. Hiring locally locally 2.7.7 2.7.7 Construction activities may, in rare instances, be necessary Not applicable Work outside the RoW outside the RoW. Where this becomes necessary, the use of land outside the RoW must be planned and agreed with owners of the affected land and properties prior to the start of the construction

2.8 Occupational Health And Safety

2.8.1 2.8.1 Contractor to implement adequate traffic management Complied with. Protecting the workforce and maintaining a measures, including safety cones, marking and use of traffic control safe working environment personnel to maintain a safe environment for workforce and Providing workers with health knowledge. community. Contractor must provide safety vests, hard hats and protective Setting traffic signs on construction site. footwear for all workers handling heavy materials, and working with caustic and hazardous materials such as concrete, asphalt, paints, Community hospitals providing health counseling cleaning agents, herbicides and pesticides. and disease prevention knowledge to the Contractor must provide protective masks to milling machine villagers. operators, and anyone working in the area of the milling machine dust- with masks of a micron size, capable of capturing dust down to 2 Providing safety equipment for construction microns. workers. Contractor must provide high-visibility clothing for workers at sites that have active traffic. Any works at night should be adequately lit and Traffic control personnel responsible for directing high visibility clothing worn. traffic. The contractor should provide basic training on use of protective clothing and equipment

37

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action 2.8.2 2.8.2 Contractor must have first aid services available to all staff and Complied with. Medical facilities and assistance workers at all times; Contractor must have at least one emergency treatment specialist on call at all times and available for emergency treatment as required. 2.8.3 2.8.3 Complied with. Storage, handing and use of toxic and/or Handling of all caustic, petroleum based materials, and other hazardous materials hazardous materials, such as pesticides/herbicides and cleaning agents, must be done, wearing protective footwear and clothing and application on steep slopes avoided Storage of such materials must be protected from the weather, clearly marked and safe from potential tampering and theft. Transport of such materials will be made according to PRC regulations and standards including pre-notification of shipment to local EPB 2.8.4 2.8.4Contractor must provide sanitary toilet for all full-time workers on Complied with. Provision of sanitary toilet facilities the construction site and make sure it is serviced daily. 2.8.5 2.8.5 Ensure large vehicles have safety equipment such as reverse Complied with. Control of movement of large equipment alarms and assistants are available to provide traffic control and and handling of construction items direction when large equipment is moved on the construction site. Demarcate work areas and use traffic cones as needed. 2.8.6 2.8.6 No Children (less than 16 year of age ) can work on any contract Complied with. Child Labour 2.8.7 2.8.7 The Contractor shall maintain such records and make such Complied with. Records of Safety and Health reports concerning safety, health, and welfare of persons and damage to property available for inspection as the Engineer may from time to time prescribe

38

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action 2.8.8 2.8.8 The Contractor shall report to the Engineer details of any accident Not applicable. Reporting of Accidents as soon as possible after its occurrence. In the case of any fatality or serious accident, the Contractor shall, in addition, notify the Engineer immediately by the quickest available means 2.8.9; 2.8.9 The contractor shall provide potable water to all staff working on Complied with. Provision of Potable Water the worksite and at all times 2..8.10 2.8.10 Generally contractors will be restricted to work only during the Complied with. Working into the night and disturbing daylight hours. However consultation and agreement with local communities ( see also 2.2.5) communities will allow for modifications. Contractor consultation with No construction at night. subproject corridor communities will be important

3. OPERATING PERIOD

3.1 3.1 The project includes a road and community safety programme, Not yet due. Increased risk of pedestrian accidents due which will include various mitigation measures to control traffic speed, to improved roads, faster speeds and reduce hazards and to increase awareness of local communities. greater traffic volume Post-maintenance consultation with local communities is proposed to check that provisions are adequate. 3.2 3.2 A number of the subprojects parallel toll road and it has been Not yet due. Diverted traffic damaging roads and observed that under these conditions, improvements to non tolled endangering communities roads results in truck traffic shifting to avoid tolls. To prevent that YHAB will install height barriers at both entrances to the affected roads 3.3 3.3 YHAB will support financial incentives for transport entities to Not yet due. Social and community-based re-establish public transport services along subproject roads and will enhancements in support of positive monitor roads to assess changes in the provision of public

39

Environmental Issue Mitigation Measures Compliance Status Proposed Corrective Action impacts transportation.

40

Appendix 2: Site Photos

Picture A2- 1 Muddy Road Surface Before Construction

Picture A2- 2 Road Surface Before Construction

41

Picture A2- 3 Dusty Road Surface Before Construction

Picture A2- 4 Construction Announcement

42

Picture A2- 5 Detour notice

Picture A2- 6 GRM Signboard on Construction Site

43

Picture A2- 7 GRM Signboard at Construction Road Section

Picture A2- 8 Traffic Personnel Directing Traffic

44

Picture A2- 9 Construction Workers Wearing Safety Clothes

Picture A2- 10 Half-range construction, not affecting the traffic

45

Picture A2- 11 Construction workers excavating culvert, building retaining wall, with helmets

Picture A2- 12 Establishing Construction Safety Signs

46

Picture A2- 13 Set speed limit sign

Picture A2- 14 Set road safety cone

47

Picture A2- 15 Set speed and load limit signs at construction section

Picture A2- 16 Renting existing equipments and venues in asphalt mixing station

48

Picture A2- 17 The materials hauling vehicle covered with canvas.

Picture A2- 18 Sprinkler suppressing dust

49

Picture A2- 19 Recycling of construction waste

Picture A2- 20 Recycling of construction waste+ Dust control measures taken when loading

50

Picture A2- 21 Transporting Construction Waste

Picture A2- 22 Collecting lubricating oil from construction vehicle

51

Picture A2- 23 Sensitive point of environmental monitoring

Picture A2- 24 Sensitive point of environmental monitoring

52

Picture A2- 25 The staff collected water sample in the reservoir of Xizhelong village

Picture A2- 26 Environmental experts testing air quality on site

53

Picture A2- 27 Environmental experts testing noise on site

Picture A2- 28 ADB’s environmental experts and social experts conducted training on site

54

Picture A2- 29 Anti-AIDS training

Picture A2- 30 Anti-AIDS awareness education board

55

Picture A2- 31 Health Inspection

Picture A2- 32 Organizing regular physical examination for the staffs

56

Picture A2- 33 Female Employees

Picture A2- 34 Public Opinion Survey along construction road sections