______Bi-annual Environmental Monitoring Report

Project Number: 2 Loan Number 2562-ADB December 2012

REPUBLIC OF : WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSPORT CORRIDOR

(Financed by the Asian Development Bank and Government of Kazakhstan)

Prepared for MOTC, Committee for Roads ADB

This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.

Dohwa Consulting Engineers Co., Ltd

DOCUMENT CONTROL This Six Monthly Environmental Report is produced in accordance with the requirements of the Contract for the Provision of Construction Supervision Services to the Ministry of Transport and Communications, Committee for Roads of the Republic of Kazakhstan for the Western Europe- Western China Transport Corridor CAREC 1, Project Two under the Asian Development Bank Loan Number 2562.

The report covers six Construction Contracts between -Otar in Zhambyl Oblast, and the Construction Supervision of these Contracts by DOHWA Consulting Engineers Ltd.

The Contracts are:  Contract 004 “ KCC Engineering& Construction Co., Ltd km 310 +500 - km358 +600  Contract 005 Kazakhdorstroy km 358 + 600 - km389 +400  Contract No NCB-1 and NCB -2 (Aksioma Service Contract” LLP)  Contract No NCB-3 and NCB -4(““Construction Corporation Kulager” LLP)

This report reviews the actions that the Contractors have implemented in accordance with the Environmental Management and Monitoring Plan (EMMP) for the second half of 2012 (July to December).

Prepared By

Environmental Specialist DOHWA Engineering Co., Ltd Date:

Distribution

Recipient № Copies English № Copies Russian MOTC, Astana ( Committee for Road) 2 2 MOTC, Taraz ( Committee for Roads) 1 SAI Consulting Engineers Pvt.Ltd (PMC) 1 Dohwa Engineering Co.,Ltd 1 1

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 1

Dohwa Consulting Engineers Co., Ltd

BI- ANNUAL ENVIRONMENTAL MONITORING REPORT

(July 2012 to December 2012)

Table of Contents

LIST OF ABBREVIATIONS AND ACRONYMS

1 INTRODUCTION 6-25

1.1 Background 1.2 Project Area 1.3 Description of Contract Package 1.3.1 Contract- 004 (KCC E & C) 1.3.2 Contract – 005- Kazakhdorstroy (KDS) 1.3.3 Contract No NCB-1 (Aksioma Service Contract” LLP) 1.3.4 Contract No NCB-2 (“Aksioma Service Contract” LLP) 1.3.5 Contract No NCB-3 (“Construction Corporation Kulager” LLP) 1.3.6 Contract No NCB-4 (“Construction Corporation Kulager” LLP) 1.3.7 Construction Supervision Contract (DOHWA Consulting Engineer Co., Ltd.) 1.4 Construction Activities during This Period (July 2012- December 2012) 1.4.1 Contract 004-KCC Km 310.5 to Km 358.6 1.4.2 Contract 005- Kazakhdorstroy, Km 358.6 to Km 389.4 1.4.3 Contract No NCB-1 (Aksioma Service Contract” LLP) 1.4.4 Contract No NCB-2 (“Aksioma Service Contract” LLP) 1.4.5 Contract No NCB-3 (“Construction Corporation Kulager” LLP) 1.4.6 Contract No NCB-4 (“Construction Corporation Kulager” LLP) 1.5 Scope of Environmental Works 1.6 Project organization and Environmental Management Team 1.7 Relationship’s with Contractor’s, Owners, Lender etc.

2 ENVIRONMENTAL MONITORING 26-54

2.1 Previous Six months Construction and Environmental Monitoring Activities 2.2 Framework for Environmental Monitoring 2.3 Status of Performed Environmental Monitoring Activities 2.3.1 Contract 004-KCC Km 310.5 to Km 358.6 2.3.2 Contract 005- Kazakhdorstroy, Km 358.6 to Km 389.4 2.3.3 Contract No NCB-1 and NCB-2 - Aksioma Service Contract” LLP 2.3.4 Contract No NCB-3and NCB-4 - “Construction Corporation Kulager” LLP

3 ENVIRONMENTAL MANAGEMENT PLAN 57-65

3.1 Overview 3.2 Implementation of the EMMP 3.3 Site Inspection and Audits 3.4 Non-Compliance Notices/Letters International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 2

Dohwa Consulting Engineers Co., Ltd

3.5 Status of EMMP Implementation 3.5.1 KCC- Contract 004 3.5.2 Kazakhdorstroy - Contract 005

4 CONCLUSIONS 78

List of Tables

Table 1.1 Baseline Information for the Project Road during preconstruction Table 2.1: Previous Six Months Construction Progress Table 2.2: Relevant Laws, Policies and Regulation on Environmental Protection AsPer Government of Kazakhstan1 Table 2.3 Standards for Various quality Parameters as Per Government of Kazakhstan Table 2.4: Monitoring Schedule- KCC Table 2.5-1 Summary of Air Quality Results- (July to December 2012) - KCC Table 2.5-2 Summary of Water Quality Results- (July to December 2012) - KCC Table 2.5-3 Summary of Average Equivalent Sound Level (dB) and Corrected Variation Level Table 2.5-4 Household domestic wastewaters (worker’s settlement)-Sewage Pond № 1 Table 2.5-5 Household domestic wastewaters (worker’s settlement)-Sewage Pond № 2 Table 2.5-6 Household domestic wastewater (office)- Sewage Pond № 1 Table 2.6 Monitoring Schedule- KCC Table 2.6-1 Summary of Air Quality Results- (July to December 2012) - KDS Table 2.6-2 Summary of Water Quality Results (July to December 2012 Table 2.6-3 Summary of Average Equivalent Sound Level (dB) and Corrected Variation Level Table 2.6-4 Observation of Non-Compliance Issues/Aspects Table 2.7 Balance of the general water use and water drain at construction of RMD Table 2.8 Air Quality on border Sanitary Protection Zone for the 4th quarter 2012 Table 3.1 Summary of the Number and Type of Site Inspection Table 3.2: Non Compliance Notice (July- December 2012) Table 3.3: Calculation of compensation for vegetation clearing in connection with reconstruction of "Taraz-Korday" motor road in Merke rayon of Zhambyl oblast (km 379-360,8) Table 3.4: Status of the grievance under Environmental Issue (Km 331- 389) Table 3.5: Work performance for rehabilitation of temporary occupied land lots involved during the construction of the motor road

List of Figures

Figure 1.1 Project Location Map Figure 1.2: Contract 004– Km 310+500- km358+600 (Contractor- Korean Construction Company- KCC) Figure 1.3: Contract 005– km 358+600-km 389+400 (Contractor- Kazakhdorstroy LLP) Figure 1.4: Environmental Monitoring Work Coordination Set Up

1Kazakhstan: Multitranche Financing Facility for the CAREC Transport Corridor 1 (ZhambylOblastSection) Investment Program— Tranche 2 International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 3

Dohwa Consulting Engineers Co., Ltd

Figure 2.1: Environmental Monitoring Location Map- KCC Figure 2.2: Schematic drawing of sampling point Location- KDS Figure 3.1: Layout Plan of Camp- KDS Figure 3.2: Water Supply and Canalization Plan

List of Annexes

Annex 1: Environmental monitoring plan during construction Annex 2: Methods for conducting Environmental Quality Parameters Annex 3 Bi-annual Environmental Monitoring Reports of Contractors KCC E&C and «Kazakhdorstroy» LLP Annex 4 Environmental Permission obtained by the Contractors Annex 5 Location Maps of Loam Fields of KCC E&C Annex 6 Basic data on the construction camp Annex 7 Agreement for disposal of domestic wastes and wastewater on disposal facility of Merke Branch of «Central Asian Sugar Corporation» LLP and «Kazakhdorstroy» LLP Annex 8 Handover certificates of waste tires - KDS Annex 9 Handover certificate rehabilitated lands temporary occupied for quarry of loam «Land Lot #3» situated at the boundaries of Merke region in Zhambyl oblast Annex 10 Felling License for Vegetation Clearance Annex 11 Agreements with «Merke Disinfection» LLP and Central Hospital of Merke Region Public Health Department of Zhambyl oblast Akimat – KDS Annex 12 Handover certificates for rehabilitated lands used for temporary occupied for construction sites situated at the boundaries of Merke region in Zhambyl oblast

(AsofNovember 2012)

Currencyunit – KazakhstanTenge (KZT)

$1.00 = KZT 150

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 4

Dohwa Consulting Engineers Co., Ltd

ACRONYMS & ABBREVIATIONS

ADB Asian Development Bank BOD5 Biochemical Oxygen Demand CR Committee of Roads CSC Construction Supervision Consultants COD Chemical Oxygen Demand CAREC Regional Economic Cooperation dB Decibel EIA Environmental Impact Assessment EMP Environmental Management Plan EMMP Environmental Management and Monitoring Plan FIDIC Federation International Des IngenieursConseils(the French acronym for International Federation of Consulting Engineers) GRC Grievances Redress Committee IEE Initial Environmental Examination KCC Korean Construction Company KDS Kazakhdorstroy LLP Limited Liability Partnership MOTC Ministry of Transport and Communication MPC Maximum Permissible Concentration MPL Maximum Permissible Level PPE Personnel Protective Equipment PCRM Public Complaints Resolving Monitoring RK Republic of Kazakhstan ROW Right of Way RCM Road Construction Materials RMD Road Maintenance Depot SPS Safeguard Policy Statement TSL Top Soil Layer

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 5

Dohwa Consulting Engineers Co., Ltd

1.0 INTRODUCTION 1.1 Background The Republic of Kazakhstan is implementing the program of Rehabilitation and up gradation of road corridor from China to Russia through the cities of ,Taraz, Shymkent , Kyzylorda andAktobe (Western Europe-Western China Corridor) about 2787 km long route initiated by the Ministry of Transport and Communications (MoTC). The MoTC is the implementing and disbursing agency of this program through the Committee for Roads (CR). The project is a four lane/two Lane all weather road with divided carriage ways of concrete and bituminous pavement. It is being implemented in several contract packages. The environmental monitoring of construction contracts being the subject of this report includes reconstruction of road section km 310+500 – 389+400 is located in Merke region and in T.Ryskulov region, Zhambyl Oblast, Republic of Kazakhstan. Reconstruction of the road sectors from km 310 +500 to km 358+600 by the contractor KCC E & C and from km 358+600 to km 389+400 by the contractor Kazakhdorstroy. Hence this project consists of two independent contract packages. There are also four contract packages for Depot. DOHWA Engineering Company Ltd. with «TuranKurylys» Ltd." of Kazakhstan for Construction Supervision of the above contracts in Zhambyl Oblast, (detailed in Section 1.2) for a duration of 33 months from 15 November 2010 (date of signing the contract with CR). The objectives of Consulting Services are to provide high quality and execution of the Contracts in a timely manner within the budget, as well as execution of construction work in full compliance with the approved project documents, technical specifications, FIDIC and SNiP policies and guidelines, economic standards and GOST; including Environmental Management and Protection Plan.

This Bi-Annual Environmental Monitoring Report (period July to December 2012) is produced as an additional report to the requirements of the Contract for the provision of Construction Supervision Services to the Ministry of Transport and Communication, Committee for Roads of the Republic of Kazakhstan for the Western Europe- Western China international Transport Corridor CAREC 1(Zhambyl-Oblast Section)- Tranche 2 under the Asian Development Bank, Loan Number 2562. The project is implemented by MOTC through the Committee for Roads, Republic of Kazakhstan in accordance with ADB’s Safeguard Policy Statement (SPS) 2009 so as to ensure that all environmental mitigation measures is given in EIA and EMP incorporating all the Environmental concerns of the project. The principle objectives of the project with respect to Environment are

 To ensure environmentally compatible project implementation by avoiding and mitigation of negative impacts that are likely to arise from the project  To ensure that EMP recommendations are adequately followed and to meet the Environmental compliance of statutory requirements. As per the EIA report, the project has been classified as category “A” based on the cumulative Environmental and Social Impacts. The Environmental impacts of the project during implementation are assessed by measuring various performance indicators. The collection and collation of the baseline data for various environmental impacts for the project helped in assessing the impacts as per implementation schedule given in the contract.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 6

Dohwa Consulting Engineers Co., Ltd

This Bi-Annual monitoring report delineates Comprehensive Environmental Status for the period July 2012 to December 2012 at key construction locations in accordance with the contract requirements.

Commencement Completion Contract № Location Contractor Value (Tenge) Date Date

Contract – 310+500– September 17, June 03, 2013 KCC E&C 15,119,403,901.00 004 358+600 2010

Contract – 358+600– September 17, April 18, Kazakhdorstroy 9,067,194,627.37 005 389+400 2010 2013

CONTRACT PACKAGES for DEPOT

Commencement Completion Contract № Location Contractor Value (Tenge) Date Date

January 19, 2012 18 months Contract – DEPOT-34 417,766,362.00 from start NCB-1 in v.Korday Aksioma date Service Km 163 April13, 2012 18 months Contract – Contract turning to 331,705.191,00 from start NCB-2 Otar date

February 6, 2012 18 months Contract – v.Akyrtobe 337,479,769.20 from start NCB-3 Kulager date Construction September 15, 18 months Contract – v. Merke Corporation 425,000,000.32 2011 from start NCB-4 DEPOT-35 date

1.2 The Project Area The Project road is located in Merke Region of Zhambyl Oblast under Tranche-2 road section km 310+500-km 389+400 (Kulan-Merke and Merke-Blagoveschenka. The project road is divided into two parts such as km 310+500- 358+600 and km 358+600-km 389+400. The project road passes through the transient zone between the foothills and steppes of the Alatau Mountains that border Kazakhstan and . The road traverses vegetated drainage channels that flow intermittently during infrequent periods of heavy rainfall (isolated storms). Most of the road is bordered by flat / slightly undulating ground that has light to moderate grass cover or cropped land. Location of the Project road in terms of contracts is shown in Figure 1.1. Figure 1.2 andFigure 1.3 respectively.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 7

Dohwa Consulting Engineers Co., Ltd

The relief, basically plain, formed the merged cone of detritus of numerous and temporary water passage, dry narrows, developed in quaternary deposits, and tectonics-accumulative types are prevailing. Chu Channel has the general bias of northward, further from foothills and the relief more plainly.

Reporting Section

Figure 1.1: Project Location Map

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 8

Dohwa Consulting Engineers Co., Ltd

Figure 1.2: Contract 004– Km 310+500- km358+600 (Contractor- Korean Construction Company- KCC)

Kazakhstan Territory

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 9

Dohwa Consulting Engineers Co., Ltd

Figure 1.3: Contract 005– km 358+600-km 389+400 (Contractor- Kazakhdorstroy LLP)

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 10

Dohwa Consulting Engineers Co., Ltd

The surface of the project location is slightly hog-backed, complicated by numerous dry, narrow channels of temporary stream, depth of incision reaches 20-30m at root of a mountain and decreases inboard of a hollow, up to 1.5 m and less, in some areas, merge with the general surface. In narrows and in floodplains, grows fruit trees and miscellaneous herbs. There are water-logged sections.

Essentially soil covering is presented by pastures, arable lands, and also hay-makings. Practically along the whole length of a line, apart from rare intervals, are marked artificial plantation forests over a distance 10-40 m on both sides of road.

In the course of realization of archeological examination, it was revealed and investigated that there are 13 objects, recognized by monuments of history and culture. All 13 investigated monuments are located outside a buffer zone (about 200), on distance from 210 m to 2140 m from the designed axis of the motorway.

The climate in the project area is generally temperate and continental. Temperatures are hot in the summer, reaching past 30° Celsius (C); in winter, they fall well below freezing to as low as –25°C. Part of the corridor, close to the mountains, has unpredictable weather with severe rainstorms in the summer and blizzards in the winter, creating hazardous road conditions. Being at about 44° North latitude, the area has approximately 8 hours of daylight in the winter and 16 hours in full summer.

Springs are short and warm, with frequent cold spells and frost occurring until late May. The frost- free period lasts a minimum of 160 days, then autumn is dry and warm. The warmest months are July (with an average temperature of 23.8°C) and August (with an average temperature of 22.3°C), and the coldest month is January (with an average temperature of– 6.6°C). Absolute peak values recorded over the past two decades are a summer maximum of44°C and a winter minimum of – 40°C. The average annual precipitation ranges from 360 to 465millimeters (mm), whereby 187–252 mm falls during the warm period (April–September).Extended drought periods have been more frequent during recent years. At the end of winter, the soil freezes to depths of up to 1.3 m, strongly affecting local road conditions andmaintenance.

Air quality in the project area is not well documented. Modeling results from the preliminary EIA prepared by the MOTC indicate roadside levels of carbon monoxide, hydrocarbon, and soot within Kazakhstan norms, while nitrogen oxide and lead show levels that exceed them.

The road section crosses many small creeks and four rivers (Aspara, Kaindysai and Koltogan, Big Chu Channel).Groundwater aquifers occur at two levels. The shallow groundwater aquifer is 1–2 m below the surface and is affected by surface water contamination originating from storm water runoff and drain water from croplands. The deep groundwater aquifer, located 20–30 m below the surface, remains most likely unaffected by the planned road works.

The road corridor is part of a tectonic depression. According to seismic risk zoning of Kazakhstan, regional seismicity can reach magnitudes of up to 8 on the open Richter scale.

Ecological resources are not highly developed in the project area due to the geomorphologic uniformity. Steppe habitats are prevailing, with scattered (seasonal) wetlands developing in depressions and along roads. The area is occasionally used by migratory birds (flyway to Siberia). Natural forests are absent, but their ecological function has been resumed by extensive roadside plantations. Ash, elm, and poplar are the predominant trees.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 11

Dohwa Consulting Engineers Co., Ltd

Wildlife is typical for a Central Asian steppe and grassland biotopes, with few rare or endangered species. According to the environmental department in the city of Taraz, no suchspecies have been seen in the project area. The wetlands do have more enhanced biodiversity,mainly waterfowl and reed grasses. Local fish faunas seem well developed and are used inrecreational fishing activities. Some fish are migratory, whose populations peak in May. Nosensitive habitats or areas exist under criteria specified in the Ramsar Convention or asprotected areas within a 100 km distance of the road.

The baseline information gathered before the performance for construction of roads conducted (preconstruction stage) are as follows:

Table 1.1: Baseline Information for the project Road during preconstruction stage

Environmental Aspect Parameter Value for Chainage Value for Chainage Km Km 310+500 to Km 358+600 to Km 389+ 400 358+600 (KCC) (KDS) Surface Water Quality Aspara River pH 7.15 Biological Oxygen Demand 4.85 (BOD5) (mg/m3) Chemical Oxygen Demand 14.1 (COD) (mg/m3) Suspended Matter (mg/m3) Absent Chloride (mg/m3) 12.4 Lead (mg/m3) Absent Chromium (mg/m3) 0.013 Mineral Oil (mg/m3) Absent Kaindysai River pH 7.13 Biological Oxygen Demand 1.55 (BOD5) (mg/m3) Chemical Oxygen Demand 4.05 (COD) (mg/m3) Suspended Matter (mg/m3) Absent Chloride (mg/m3) 20.60 Lead (mg/m3) Absent Chromium (mg/m3) 0.022 Mineral Oil (mg/m3) 0.034 Koltogan pH 7.37 Biological Oxygen Demand 2.15 (mg/m3) Chemical Oxygen Demand 7.76 (mg/m3) Suspended Matter (mg/m3) Absent Chloride (mg/m3) 42.7 Lead (mg/m3) Absent Chromium (mg/m3) 0.016 Mineral Oil (mg/m3) 0.022 Big Chu Channel pH 7.13 Biological Oxygen Demand 1.55 (mg/m3) Chemical Oxygen Demand 4.05 (mg/m3) Suspended Matter (mg/m3) Absent Chloride (mg/m3) 20.6 Lead (mg/m3) Absent Chromium (mg/m3) 0.027 Mineral Oil (mg/m3) 0.034 Air Quality Site No. 1 (Km 357+ 808) Nitrogen Oxide (mg/m3) 0.000 Sulphur Oxide (mg/m3) 0.000

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 12

Dohwa Consulting Engineers Co., Ltd

Carbon Oxide (mg/m3) 0.000 Aldehydes (mg/m3) 0.000 Inorganic Dust (mg/m3) 0.000 Site No. 2 (Km 357+ 808) Nitrogen Oxide (mg/m3) 0.002 Sulphur Oxide (mg/m3) 0.000 Carbon Oxide (mg/m3) 0.000 Aldehydes (mg/m3) 0.000 Inorganic Dust (mg/m3) 0.000 Site No. 2 (Km 345 + 300) Nitrogen Oxide (mg/m3) 0.003 Sulphur Oxide (mg/m3) 0.080 Carbon Oxide (mg/m3) 0.000 Aldehydes (mg/m3) 0.000 Inorganic Dust (mg/m3) 0.000 Site No. 3 (Km 333 + 000) Nitrogen Oxide (mg/m3) 0.002 Sulphur Oxide (mg/m3) 0.005 Carbon Oxide (mg/m3) 0.009 Aldehydes (mg/m3) 0.000 Inorganic Dust (mg/m3) 0.000 Concrete batching Plant (km Nitrogen Oxide (mg/m3) 0.000 368) Sulphur Oxide (mg/m3) - Carbon Oxide (mg/m3) 0.046 Aldehydes (mg/m3) - Inorganic Dust (mg/m3) 0.000 Zhanaturmys village (km 377) Nitrogen Oxide (mg/m3) 0.000 Sulphur Oxide (mg/m3) - Carbon Oxide (mg/m3) 0.000 Aldehydes (mg/m3) - Inorganic Dust (mg/m3) 0.000 Noise Quality Km 334+300 Average Equivalent Sound 45 Km 310 + 500 level (dB) 54 Km 358 + 600 54 Road Interchange 65 Concrete batching Plant (km 55 368) Zhannaturmys village (km 56 377) Kazakh village (km 383) 76 Soil Quality Maximum Lead 20 23.5 Concentration (mg/kg)

Source: KCC and KDS, December 2012

1.3 Description of Contract Package 1.3.1 Contract- 004- (KCC E & C) This Contract comprises a new dual carriageway (each direction) cement / concrete road pavement. From Km 358+600 to km 337+000 ,part of the work will be on new alignment and part utilizing the existing old embankment. The Contractor will construct the new road first and then transfer traffic from the existing road to allow this to be reconstructed. There will be a realignment of the road from Km 310+500 to km331+000 as the road was shifted 100 – 300 meters off the existing alignment to provide a security zone between the Kazakhstan and Kyrgyzstan border.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 13

Dohwa Consulting Engineers Co., Ltd

Key Components:

Length of Road 48.1 km Culverts 49 Bridges 2 Interchange 1 Earthworks (embankment compaction) 3,350,040m3 Sub-base 715,660 m3 Base-course (cement treated) 241,534 m3 Asphalt wearing Course 1320 m3 Cement Concrete base-course (12.5cm) 126,360 m3

Cement Concrete wearing course (12.5cm) 116,640 m3

Maintenance of Merke-Shu-Korday detour 148 km road

1.3.2 Contract – 005- Kazakhdorstroy (KDS)

This Contract comprises a new dual carriageway (each direction) cement / concrete road pavement. Part of the work will be on new alignments and part utilizing the existing old embankment.

The Contractor will construct the new road first and then transfer traffic from the existing road toallow this to be reconstructed.

There will be a new alignment for the bridge at km 364+000 and also for the railway overpass atMerke.

Key Components: Length of Road 30.8 km Culverts 52 Bridges 2 (Big Chu Channel, Koltogan River) Interchange 1 & 1 railway overpass Earthworks (embankment compaction) 2,242,000 m3 Sub-base 499,231 m3

Base-course (cement treated) 184,480 m3

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 14

Dohwa Consulting Engineers Co., Ltd

Asphalt wearing course 1970 m3 Cement Concrete base-course (12.5cm) 81,070 m3

Cement Concrete wearing course (12.5cm) 81,070 m3

1.3.3 Contract No NCB-1 (Aksioma Service Contract” LLP)

Small works including Construction and repairs of buildings, Maintenance depots and facilities: Lot I: Thorough repair and construction of buildings and facilities of Maintenance DEPOT-34 in v.Korday concluded with “Aksioma Service Contract” LLP.

1.3.4 Contract No NCB-2 (“Aksioma Service Contract” LLP) Small works including Construction and repairs of buildings, Maintenance depots and facilities: Lot II: Complex of buildings and facilities for maintenance depots and on the km 163 Almaty-Korday- Blagoveschenka-Merke-Taskent-Termez (turning to Otar) concluded with “Aksioma Service Contract” LLP.

1.3.5Contract No NCB-3 (“Construction Corporation Kulager” LLP)

Small works including Construction and repairs of buildings, Maintenance depots and facilities: Lot III: Complex of buildings and facilities for maintenance depots and on the km 453 Almaty-Korday- Blagoveschenka-Merke-Taskent-Termez (in Akyrtobe) concluded with “Construction Corporation Kulager” LLP.

1.3.6Contract No NCB-4 (“Construction Corporation Kulager” LLP) Small works including Construction and repairs of buildings, Maintenance depots and facilities: Lot IV: Complex of buildings and facilities for maintenance depots and on the km 453 Almaty-Korday- Blagoveschenka-Merke-Taskent-Termez (in v. Merke) concluded with “Construction Corporation Kulager” LLP. 1.3.7 Construction Supervision Contract (DOHWA Consulting Engineer Co., Ltd.)

The DOHWA Consultant is responsible for the Construction Supervision of six Construction Contracts. Other duties include environmental and social monitoring in accordance with ADB requirements. 1.4 Construction Activities during This Period (July - December 2012) 1.4.1 Contract 004-KCC Km 310.5 to Km 358.6 (Tranche 2) Pursuant to Sub-Clause 8.1 of the General Conditions of Contract, the Notice for Commencement of Works was issued on 17th of September 2010 by the Engineer. The Contractor was already on the site and has established a temporary office. Address is Ahtamberdieva 34 str., v. Sarymoldaev, Merke region, Zhambyl oblast. The Contractor has also received the advance payment.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 15

Dohwa Consulting Engineers Co., Ltd

The cumulative work progress as of 31 December 2012 is approximately 95.71% while the corresponding planned progress based on the Revised Work Programme is 76.19%. The achieved progress in the month of December 2012 is 6.59% against the monthly planned progress of 0.00%.

Progress of Work for Major Work Items as on the end of December 2012:

Quantity Progress Work Description Unit Design Completed Rate

Removal of topsoil M3 441.430 441.430 100%

Compaction of Fill in M3 3.350.040 3.350.040 100% Embankment

Granular Sub-base M3 715.660 576.550 81%

Crushed Stone Road Base, Км 96,20 95,72 99,5% With 7% Cement

Cement Concrete Pavement Kм 96,20 80,13 83,3%

Bridge at Kayindysai № 1,00 0,99 99%

Bridge at Aspara № 1,00 0,99 99%

Interchange Bridge № 1,00 0,99 99%

Pipe Culvert м 1.158 1.158 100%

Box Culvert м 376 376 100%

1.4.2 Contract 005- Kazakhdorstroy, Km 358.6 to Km 389.4 (Tranche 2)

Pursuant to Sub-Clause 8.1 of the General Conditions of Contract, the Notice for Commencement of Works was issued on the 17th of September 2010 by the Engineer. The Contractor was already on Site and had established a temporary office in Merke. The Contractor has received the advance payment from ADB and Kazakhstan Government. The cumulative work progress as of 31 December 2012 is approximately 122,94% while the corresponding planned progress based on the Original Work Programme is 91,83%. The achieved progress in the month of December 2012 is 6,42% against the monthly planned progress of 0,00%.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 16

Dohwa Consulting Engineers Co., Ltd

Progress of Work for Major Work Items as on the end of December 2012:

Quantity Progress Work Description Unit Design Completed Rate

Removal of topsoil M3 152.970 152.970 100%

Compaction of Fill in M3 1.951.650 1.951.650 100% Embankment

Granular Sub-base M3 499.231 380,429 76%

Cement Concrete Pavement Kм 61,20 61,20 100%

Crushed Stone Road Base, Км 61,20 61,20 100% With 7% Cement

Bridge at Km. 366+667 № 1,00 1,00 100%

Bridge at Km. 367+124 № 1,00 1,00 100%

Bridge at Km. 364+748 № 1,00 1,00 100%

Interchange Bridge at Km. № 1,00 1,00 100% 370+200

Pipe Culvert м 1.289 1.289 100%

Box Culvert м 389 389 100%

Bus pavilions № 11 11 100%

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 17

Dohwa Consulting Engineers Co., Ltd

1.4.3 Contract No NCB-1 (Aksioma Service Contract” LLP)

The Original Commencement Date for the Works is 15 September 2011. Due to late issuance of Government’s Construction Permit, the Works officially commenced on 19 January 2012.

Progress of Work for each Structure as on the end of December 2012:

Progress SN Description Remarks To Date

1 Administrative Household Building 84%

2 Refueling Station 46%

3 WarmBox 10 units 15%

4 Repair workshop for road equipment 67%

5 BoilerHouse 42%

6 CoalStoreHouse 24%

Products and Material Storehouse 7 88% (Inventory Holdings)

8 SandandSaltStorehouse 56%

9 Shelter for large size equipment ‐‐

10 ToiletReservoirs ‐‐

11 FireReservoirs 5%

12 Cess Pool 25cum and 15 cum ‐‐

13 WaterSupplyandStorage ‐‐

14 CommunicationandAlarmSystem ‐‐

15 Landscaping and other finishing works 3%

16 Checkpoint 92%

17 Warm box (existing building) 67%

18 Bulk materials storage 77%

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 18

Dohwa Consulting Engineers Co., Ltd

1.4.4 Contract No NCB-2 (“Aksioma Service Contract” LLP) The Original Start Date for the Works is 15 September 2011. Due to shifting of location, the whole of the Works have to be redesigned. As of this reporting period, the revised design is yet to be issued by the Project Designer.

Progress of Work for each Structure as on the end of December 2012:

Progress SN Description Remarks To Date

1 Administrative Household Building 74%

2 Refueling Station 67%

3 WarmBox 10 units 50%

4 Repair workshop for road equipment 26%

5 BoilerHouse --

6 CoalStoreHouse --

Products and Material Storehouse 7 1% (Inventory Holdings)

8 SandandSaltStorehouse --

9 Shelter for large size equipment --

10 ToiletReservoirs --

11 FireReservoirs --

12 Cess Pool 25cum and 15 cum --

13 WaterSupplyandStorage --

14 CommunicationandAlarmSystem --

15 Landscaping and other finishing works --

16 HousingBuilding 81%

17 Checkpoint --

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 19

Dohwa Consulting Engineers Co., Ltd

1.4.5Контракт № NCB-3 (ТОО «Строительная корпорация Кулагер»)

The Original Commencement Date for the Works is 15 September 2011. Due to land acquisition issue, the whole of the Works have to be redesigned. The revised design was only issued by the Project Designer on 06 February 2012 which shall be considered as the revised Commencement Date.

The works have been suspended as the Contractor has encountered high water table. During the meeting held on 07 May 2012, the Employer is considering to relocate the Depot Site to a higher place.

Employer submitted the letter to Engineer and Contractor Ref. No23-13-1-4/1159 dated 16 August, 2012 in which informs about the acquisition of a new land plot (new location) for construction and maintenance of Depot from Km.453 to Km.451 (Lot III, Akyrtobe)

Progress of Work for each Structure as on the end of December 2012:

Progress SN Description Remarks To Date

1 Administrative Household Building 20%

2 Refueling Station 10%

3 WarmBox 10 units 80%

4 Repair workshop for road equipment 10%

5 HousingBuilding 70%

6 Checkpoint 50%

7 Coal Storage --

Products and Material Storehouse 8 15% (Inventory Holdings)

9 SandandSaltStorehouse 12%

10 Shelter for large size equipment --

11 ToiletReservoirs --

12 FireReservoirs --

13 Cess Pool 25cum and 15 cum --

14 WaterSupplyandStorage --

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 20

Dohwa Consulting Engineers Co., Ltd

Progress SN Description Remarks To Date

15 CommunicationandAlarmSystem --

16 Landscaping and other finishing works --

1.4.6 Contract No NCB-4 (“Construction Corporation Kulager” LLP) The Works for this Contract commenced on 15 September 2011 and is progressing satisfactorily. As of this reporting period, there is no major issue or constraint has been encountered that may affect the Intended Completion Date.

Progress of Work for each Structure as on the end of December 2012:

Прогресс на № Описание сегодняшний Заметки день

1 Administrative Household Building 100%

2 Checkpoint 95%

3 Storage of goods and materials 98%

4 Repair workshop for road equipment 100%

5 Warm Box (Project building) 55%

Warm box with storage of mechanical rubber 6 100% goods

7 Boiler House 75%

8 Sand and Salt Storehouse 100%

9 Household Building 100%

10 Petrol Station 95%

11 Repair Department of Furnishing Elements 99%

12 Coal Store House 100%

Shed. Storage of Cold Asphalt 13 100% (Previous Warm Box)

14 Loading and Offloading Area 10%

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 21

Dohwa Consulting Engineers Co., Ltd

Прогресс на № Описание сегодняшний Заметки день

15 Storage of Diesel Oil 100%

16 Pump Station 20%

17 Fire Tanks, capacity is 2x100 m3 45%

18 Cess Pool 25cum and 15 cum 46%

19 Two-holed Toilet 100%

20 Inside Area Communications 95%

21 Landscaping and other finishing works 10%

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 22

Dohwa Consulting Engineers Co., Ltd

1.5 Scope of Environmental Works The scope of works includes identification of environmental impacts during construction stage and implementation of environmental mitigation measures for various environmental components as given in technical specification in the contract. In addition, the supervision consultant has to undertake specific environmental safeguard measures during the execution of work.

The following activity are considered for effective Environmental Monitoring through periodic inspection and supervision during execution of works as per the General Requirement of the Technical Specification for construction of whole the work under clause 105 (Health and Safety) and clause 106 (Protection of the Environment).

 Loss of top soil  Soil erosion  Contamination of soil by fuel and lubricants  Quarry and hot mix plant operations  Siltation into water bodies  Alteration of drainage  Dust Control-haulage road and work sites  Pollution from crusher, hot mix plant and batching plant  Noise from plant and equipment  Safety and accidental risks  Traffic safety and control,

The EMMP signifies the environmental action to be undertaken under Taraz –Korday section in Zhambyl Oblast Project 2, delineating various mitigation measures/avoidance of negative impacts. The EMP also incorporates various environmental enhancement measures required for protecting the cultural properties in all contract packages.

1.6 Project organization and Environmental Management Team In general, as stipulated in the ToR for the Construction Supervision on the environmental aspect, the Consultant shall “Carry out the following duties related to environmental mitigation measures during construction (a) to ensure that all the environmental mitigation measures required to be implemented are incorporated in the contract documents; (b) supervise and monitor the implementation of environmental (management)/mitigation plan (EMP); and (c) in case of unexpected environmental impacts, coordinate with the Project Director and PMC to recommend necessary measures to the Committee of Roads and ADB for Implementation”.

Based on this the Environmental specialist shall establish coordinative work with relevant staffof the Consultant and the Contractor to ensure that environmental issues are recognized prior to or discovered during work implementation. The EMP for the project/s or component projects shall be the basis of the monitoring and accordingly, the Contractor should complete and submit their project EMP to the Engineer for approval as soon as possible. Coordinative communication channels shall be established according to the following work coordination chart:

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 23

Dohwa Consulting Engineers Co., Ltd

ADB MOTC

CommitteeforRoads PMC

ContractorSupervision DOHWA‐ TeamLeader

Construction Supervision (DOHWA) Contractor (KCC, KDS) ProjectManager Environmental Specialist Local Environmentalist

Contractor Environmental Officer Health & Safety Officer

Figure: 1.4 Environmental Monitoring Work Coordination Set Up

Project Management Consultant (PMC-ADB) through its environmental expert closely monitors the implementation of environmental management and monitoring plan for all the contract packages by conducting meetings with the environmental experts of the supervision consultant (CSC).

During this period (July to December 2012), the following International Environmental and Social Specialist has been deployed by DOHWA

Name Position Input Date

International Specialist

Abu NahidMunirUddin Environmental Specialist December 7 to December 26, 2012

Kh. KhairulMatin Social Development Specialist December 7 to December 26, 2012

Local Specialist

TalgatRomazannovichBaktiyarov Local Environmental Specialist July 9 to October 27, 2012 (Full time)

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 24

Dohwa Consulting Engineers Co., Ltd

KolbayBaurzman December 20 till date

All the contractors (KCC and KDS) have a full time Environmental Specialists on site.

As for the Contractor, the Environmental Management Plan will be an integral part of the contract agreement and he needs assurance to carryout all project activities in compliance with the EMP and the Kazakhstan standards. Both the Contractors (KCC and KDS) were appointed environmental specialist who is responsible for all precautionary and safeguard measures specified in the technical specification of the contract.

1.7 Relationship’s with Contractor’s, Owners, Lender etc. The relationships between Contractor, Engineer, Owner, and Lender are considered normal working relationships. At the working level, coordination of environmental issues has been good; the specialists mentioned in article 1.5 above are in frequent communication and consultation.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 25

Dohwa Consulting Engineers Co., Ltd

2. ENVIRONMENTAL MONITORING

2.1 Previous Six months Construction and Environmental Monitoring Activities The table below outlines the monthly progress of the Project Road in the previous six months.

Table2.1: previous six months Construction Progress N Month Construction Construction ConstructionActivities ConstructionActivities (Kulager) o. Activities (KCC Activities (Axsioma) EC) (Kazakhdorstroy) Contract No.004 Contract No. 005 Lot 1 Lot 2 Lot 3 Lot 4 KordayDepot OtarDepot AkyrtobeDepot MerkeDepot

1 July -Granular sub- -Miscellaneous - Repair -Petrol -Works were -Administrative 2012 base works at Bridges workshop Station suspended due Household -Embankment Big Chu Channel, -Boiler - to shifting of site Building Works Koltogan, and House Administrati -Materials -Lean concrete Railway overpass -Materials ve Storage pavement -Bridge railings Storage Household Building -Merke-Shu- and slope Building Building -WarmBox Korday Repair protection works -Warm Box - works at Interchange HouseholdBuil -Cement concrete Bridge ding pavement ,Km.370+200 -Bridges at -Embankment Kayindysay and works Aspara -Granular sub- -Interchange base Bridge,km.357+88 -Reinforced 7 Concrete Pipe culverts works -Lean concrete pavement -Cement concrete pavement 2 Aug.20 -Granular sub- -Big Chu Channel - -Petrol -Survey of the -Materials 12 base asphalt concrete Administrativ Station new site location Storage -Embankment overlay e Household - -Administrative Works -Koltogan Bridge Building Administrati Household -Lean concrete backfilling -Warm Box ve Building pavement -Railway -Repair Household -Repair -Merke -Shu- Overpass workshop Buildings workshop Korday Asphalt reinforced - -Warm Box -Sand and Salt patching works concrete girders MaterialsStor - Storage -Cement concrete -Interchange age RepairWork -Boiler House pavement bridge, setting of shop -Warm box -Bridges at approach slab building Kayindysay and -Granular sub- -Fire Tanks Aspara base -Interchange -Lean concrete Bridge,km.357+88 pavement 7 - Cementconcretep avement

3 Sep.20 -Granular sub- -Miscellaneous - - -Temporary - 12 base bridgeworks at Administrativ Administrati Fencing of the Shed/Storage -Lean concrete Koltogan, Big Chu e Household ve Building new site of Cold asphalt

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 26

Dohwa Consulting Engineers Co., Ltd

pavement Channel, and Building -Petrol -Filling of -Administrative -Merke-Shu- Railway overpass -Sand and Station embankment for household Korday DBST -Sidewalks and Salt Storage -Warm Box low areas building works spillway aprons at -Warm Box - -Repair -Cement concrete Interchange -Checkpoint RepairWork workshop pavement bridge -Materials shop -Warm box -Bridges at -Granular sub- Storage -Boiler house Kayindysay and base Building Aspara -Lean concrete -Embankment pavement works at -Cement concrete approaches of pavement Interchange -Road furniture Bridge,km.357+88 works 7 4 Oct.20 -Granular sub- -Minor works at - - -Soil filling -Administrative 12 base Bridges Koltogan, Administrativ Administrati works Household -Lean concrete Big Chu Channel, e Household ve Building -Foundation Buildings pavement and Railway Building -Petrol works for -Salt and Sand -Merke-Shu- Overpass -Warm Box Station various storage Korday DBST -Shoulder works -Repair -Warm Box buildings -Repair works -Top-soiling Workshop - Workshop -Cement concrete works - HousingBui -Household pavement -Guardrails MaterialsStor lding Building -Bridges at installation age -Diesel Kayindysay and - -BoilerHouse Storage Aspara Roadfurniturewor - -Embankment ks ElectricalWork works at -Roadjunctions s approaches of Interchange Bridge,km.357+88 7 5 Nov.20 -Granular sub- -Slope protection - - -Administrative -Administrative 12 base works for Administrativ Administrati Building building -Lean concrete structures e Building ve Building -Petrol Station -Checkpoint pavement -Road furniture -Petrol -Petrol -Warm box -Materials -Merke-Shu- works station station -Checkpoint Storage Korday DBST -Guardrails -Repair -Warm Box -Repair works installation Workshop - Workshop -Cement concrete -Top-soiling -Boiler HousingBui -Warm Box pavement works House lding -Sand and Salt -Minor works at -Auto pavilion and -Materials storage Kayindysay and toilets Storage Aspara bridges -Roadjunctions -Checkpoint

6 Dec.20 -Lean concrete -Road Furniture - - -Administrative -Administrative 12 pavement works Administrativ Administrati household Household -Cement concrete -Guardrails e Building ve Building building Building pavement installation -Petrol -Petrol -Warm Box -Checkpoint -Interchange -Sidewalks and station Station -Apartment -Materials Bridge,km.357+88 ramps -Warm Box -Repair house Storage 7 -Staff Workshop -Checkpoint -Repair -Guardrails Housing -Sand and Workshop installation building Salt -Boiler House -Repair Storage -Sand and Salt Workshop - Storage Checkpoint -Shed Storage -Warm box of Cold - Asphalt WaterRese -Fire Tanks,

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 27

Dohwa Consulting Engineers Co., Ltd

rvoir Cesspools

The Environmental issues of the project during the construction phase were monitored according to the Environmental Management Plan. The following key sectors were identified to monitor indicators of possible adverse environmental impacts

 Air quality- To minimize air pollution during the construction activities  Water Quality- To avoid contamination of water by construction and related activities such as accidental oil spills, disposal of solid waste, construction material and domestic waste water  Hydrology- To minimize hydrological and drainage effect such as temporary water logging and depletion of ground water  Ground Water Quality- To avoid ground water quality deterioration arising due to construction activities and post construction related activities  Noise and Ground Vibration- To minimize the noise emission due to construction activities and ground vibration  Exploitation, Handling, Transportation, and Storage of Construction Materials – To minimize the impacts  Social Impacts- To minimize indirect impact on dust, noise and vibration effects to the people close to the ROW

Environmental mitigation and monitoring Plan (EMMP) was submitted by each contractor, based on the Technical specifications (item 106) and sub item 4.18 of special conditions of the contract. As per the technical specification, the contractors were completed preconstruction monitoring to verify baseline conditions before commencement of construction works. They are now conducting the baseline monitoring of air quality, water quality, noise and vibrations etc. once per every month in each location and more frequently if determined necessary by the Engineer.

2.2 Framework for Environmental Monitoring The environmental monitoring and management activities for the project is based on the Environmental Impact Assessment (EIA) Reports drafted for the project road component namely the Environmental Impact Assessment Report. ADB Loan No. 2562-KAZ – Multitranche Financing Facility for the CAREC Transport Corridor 1 (Zhambyl Oblast Section) Investment Program – Tranche 2 (May 2009). This EIA report applies to the sections where construction is ongoing. Based on the General Requirement of the Technical Specification for construction of whole the work under clause 106 (Protection of the Environment); the environmental concerns which need to be monitored and managed are as follows:

 Siting of Construction Camps, Asphalt Plants and Related Facilities  Air Quality  Water Quality  Noise and Vibration  Community Relation  Earth works  Preservation of Antiquities  Environmental Enhancement In addition, the following laws, regulations and standards are also considered and used as guidelines related to road construction activities of the Contractor:

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 28

Dohwa Consulting Engineers Co., Ltd

Table 2.2: Relevant Laws, Policies and Regulation on Environmental ProtectionAs Per Government of Kazakhstan2

Name of Legislation Date and Number of registration Methodology for Determining Emissions Standards to Approved by the Order of the Minister of Environment (MEP), 21 the Environment May 2007, No. 158-p”. Regulations on Conducting State Ecological Expertise. Approved by the Order of the Minister of MEP, 28 June 2007, No. 207-p” The Amendments to the Order of the Minister of Approved by the Order of the Minister of MEP, 9 October 2007, Environment Protection of Republic of Kazakhstan on No. 296-p” Approval of Regulations on Conducting State Ecological Expertise Instructions on Negotiation and Permissions to Special Joint order of the Minister of Health of the Republic of Kazakhstan Water Use in the Republic of Kazakhstan dated 24 November 2004 № 824, Minister of Environment of the Republic of Kazakhstan of 1 December 2004 number 309-p, Acting Chairman of the Committee on Water Resources, Ministry of Agriculture of the Republic of Kazakhstan dated 11 November 2004 number 236- S, Chairman of the Committee of Geology and Mining Ministry of Energy and Mineral Resources of the Republic of Kazakhstan on 2 December 2004 number 161-p. Joined by the Ministry of Justice of the Republic of Kazakhstan 13 December, 2004 N 3263 The Rules for Licensing and Qualification Approved by the Order of the Government of Republic of Requirements to Work Implementation and Delivery of Kazakhstan, MEP, 5 June 2007, No. 457-p” Services in the Field of Environmental Protection Environmental Code of the Republic of Kazakhstan MEP, 9 January 2007, No. 212-p”. Law of the Republic of Kazakhstan «On Amendments MEP, 9 January 2007, No. 213-p” and Additions to Some Legislative Acts of Kazakhstan on Environmental Issues» Law of the Republic of Kazakhstan «On Ratification of MEP, 20 March 2007, No. 239-p” the Rotterdam Convention on the Prior Informed Consent Procedure for Certain Hazardous Chemicals and Pesticides in International Trade» Law of the Republic of Kazakhstan «On Ratification of 7 June 2007, No. 259-p” the Stockholm Convention on Persistent Organic Pollutants» The Concept of Transition to Sustainable Development The Order of the President of RK, 14 November 2006, No. 216-p” for 2007–2009 (Action Plan) The Concept of Environmental Security of the Republic The Order of the President of RK , 3 December 2003, No. 1241 of Kazakhstan for 2004–2015

Table 2.3: Standards for Various quality Parameters as Per Government of Kazakhstan

Monitoring Indicator Parameters Maximum Permissible Concentration (MPC) on ND, mg/m3 Ambient Air Quality Nitrogen dioxide 0.085 Nitrogen Oxide 0.4 Sulphur dioxide 0.5 Carbon Oxide 5.0 Aldehydes 0.035 Inorganic dust 0.3 Water Quality pH 6.5-8.5 Suspended Matter 0.21 Chemical Oxygen Demand 30 Biochemical Oxygen Demand 6.0 Mineral Oil 0.1 Lead 0.03 Arsenic 0.05 Chloride 350.0 Chromium 0.05 Noise Quality Maximum allowable limit in dB 75 Soil Quality Maximum Permissible 32 Concentration level for lead concentration (mg/kg)

2Kazakhstan: Multitranche Financing Facility for the CAREC Transport Corridor 1 (ZhambylOblastSection) Investment Program— Tranche 2 International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 29

Dohwa Consulting Engineers Co., Ltd

The monitoring program will include regular monitoring of construction activities for their compliance with the environmental requirements as per relevant standards, specifications and EMP; The purpose of such monitoring is to assess the performance of the undertaken mitigation measures and to immediately formulate additional mitigation measures and/or modify the existing ones aimed at meeting the environmental compliance as appropriate during construction which is mentioned in Environmental monitoring program of the EIA Report.(See Annex 1). During construction, environmental monitoring will ensure the protection of side slopes, and embankment from potential soil erosion, borrow pits restoration, quarry activities, sitting of work sites and material storages, sitting of batch, concrete and asphalt plants especially close to the nature reserve, preservation of religiously sensitive locations, community relations, and safety provisions.

2.3 Status of Performed Environmental Monitoring Activities The Engineer’s domestic environmentalist was performed environmental monitoring using checklist developed by Environmental Specialist of DOHWA which was given in the Bi-annual Environmental Monitoring Report (first half, 2012). The results of the monthly monitoring were incorporated in the Environmental Chapter of the monthly report of the Engineer. Primarily the environmental monitoring activities at various locations at the worksites focused on (i) the quality of atmospheric air; (ii) the quality of drinking water and river water; (iii) the condition of soil; (iv) flora and fauna; (v) the condition of construction equipment and transport; (vi) waste; and (vii) quarries. 2.3.1 Contract 004-KCC Km 310.5 to Km 358.6 Works for the conducting of the environmental monitoring observations in second half year of 2012 were conducted according to “Environmental mitigation and monitoring plan (EMMP)” and approved by the Shu-Talas Department of Ecology “Program for Industrial Ecological control till July 1, 2013. During the last 6 months, monitoring work provided and measured monthly on the basis of monitoring schedule.

Air quality monitoring was done before the performance for the construction of roads conducted in September 2010, on the concrete and crushing screening plant in April 2011 and for the storage and cement plant in July 2011. Instrumental laboratory measurements were carriedout in the month of July, August, September, October, and November 2012. The laboratory measurements for the month of December have not been performed yet due to heavy snow fall and bad weather condition. Air quality has been conducted in 7 places at 14 control points on 5 components on the border of sanitary protection zones.Concentration of pollutants on the control points which characterizing influence of sections on an environment, it have undergone express method by a gas analyzer «GАNК-4».

Water quality monitoring was carried out in river Kayindysay as per EMMP schedule on monthly basis. Preliminary Water quality was conducted for 22 parameters during preconstruction stage. Water quality was not performed in river Aspara due to non-availability of flow during this period.

Wastewater taken from household domestic sewage of worker’s settlement (during August and October from Septic tank 1 and August from Septic Tank 2) and from office (during the month of October from Septic tank 1) and laboratory analysis was performed as per request by the Engineer.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 30

Dohwa Consulting Engineers Co., Ltd

Measurements of baseline noise and vibration were conducted before the start of construction in September 2010. Noise and vibration data was collected in 4 places at 4 control point. Monitoring of noise and vibration was also conducted in the v. Kyzyl-Kystak near the school and near the mosque at the turn of road to crushing and screening plant.Noise and vibration measurements have undergone by instrument "Assistant". The specified instrument can be applied to measurement of the sound parameters, an infrasound and ultrasound, the general and local vibration on workplaces, in inhabited and public buildings, in territories.

All the monitoring works was carried out by the accredited laboratory named “KESON UTAN” (Accreditation certificate No KZ I.081065) registered in the register of accreditation from 14.12.2010 and valid till 14.12.2015.Annex 2 represents the methods for determining various environmental quality parameters (air, water, noise etc.)

The following Table shows the detail monitoring program and Figure 2.1 shows the Environmental monitoring map.

Table 2.4: Monitoring Schedule - KCC

Location of measurement, № of № ModeofTest Frequency KM, № of control point. 1 2 3 Not less than once per month The Test of air at the Site № 1. KM 357+808 or more often as required by 1 border of Sanitary Controlpoint № 1. the Engineer Protection Zone.

The Test of air at the Site № 1. KM 357+808 2 border of Sanitary Controlpoint № 2. Instrumental laboratory Protection Zone. measurements were carried The Test of air at the out in the month of July, Site № 2. v. Аspara KM 328+300 3 border of Sanitary August, September, October, Control point № 1. Protection Zone. and November, 2012. Due to bad weather condition, The Test of air at the laboratory measurements have Site № 2. v. Аspara KM 328+300 4 border of Sanitary not been done yet. Control point № 1. Protection Zone.

The Test of air at the Site № 3. Quarry (Aspara and 5 border of Sanitary Ryskulov) Control point № 1. Protection Zone.

The Test of air at the Site № 3. Quarry (Aspara and 6 border of Sanitary Ryskulov) Control point № 2. Protection Zone.

The Test of air at the Site № 4. Concrete Plant 7 border of Sanitary Control point № 1. Protection Zone.

The Test of air at the Site № 4. Concrete Plant 8 border of Sanitary Control point № 2. Protection Zone.

Site № 5. Crushing-Screening The Test of air at the 9 Plant border of Sanitary Control point № 1 Protection Zone.

Site № 5. Crushing-Screening The Test of air at the 10 Plant border of Sanitary Control point № 2 Protection Zone.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 31

Dohwa Consulting Engineers Co., Ltd

The Test of air at the Site № 6. Storage of cement. 11 border of Sanitary Control point № 1. Protection Zone.

The Test of air at the Site № 6. Storage of cement. 12 border of Sanitary Control point № 2. Protection Zone.

Site № 7. Garage of storage tank The Test of air at the 13 for diesel fuel border of Sanitary Control point № 1. Protection Zone. Site № 7. Garage of storage tank The Test of air at the 14 for diesel fuel border of Sanitary Control point № 2 Protection Zone. Not less than once per month or more often as required by the Engineer.

Bridge locations at water sites 15 Testofnaturalwaters There is no water in the river of (Aspara, Kayindysay)* Aspara from July to December. So, no water quality was monitored in the river Aspara during this period Not less than once per month Test for Noise and 16 ConcretePlant or more often as required by Vibration. the Engineer

The Mosque at the turn of Test for Noise and 17 Additional monitoring of noise Crushing and Screening Plant Vibration. and vibration near the school and mosque has been required v. Kyzyl-Kystak, school № 3 at Test for Noise and by the Engineer 18 the side of the road Vibration.

Test for Noise and 17 Crushing-ScreeningPlant. Vibration.

The summary of monitoring results on air, water and noise quality for this bi-annual period (July to December 2012) are shown in Table 2.2-1, Table 2.2-2, Table 2.2-3, Table 2.2-4, Table 2.2-5 and Table 2.2-6 respectively.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 32

Dohwa Consulting Engineers Co., Ltd

Figure 2.1: Environmental Monitoring Location Map, KCC

Table 2.5- 1: Summary of Air Quality Results- (July to December 2012)- KCC

№ Place of Paramet Maximu Average Average Average Average Average Average Averag measurement № ers m arithmeti arithmetic arithmet arithmetic arithmeti arithmetic e checkpoint Permiss c value Value of ic Value of c Value Value of arithmet ible of factual Value of factual of factual factual ic Concen factual concentra factual concentrat concentr concentrati Value of tration concentr tion, concent ion, ation, on, mg/m3, factual (MPC) ation, mg/m3, ration, mg/m3, mg/m3, November concent on ND, mg/m3 July mg/m3, Septembe October ration, mg/m3 baseline August r mg/m3, data* Decem ber 1 Control point №1 Nitrogen 0.085 0,000 0,011 0,026 0,002 0,045 0,009 0.008 Site№1 dioxide 357+808km. Sulfur 0.5 0,000 0,061 0,013 0,001 0,249 0,029 0.033 dioxide

Carbon 5.0 0,000 0,118 0,020 0,002 0,335 0,022 0.056 Oxide

Aldehyd 0.035 0,000 0,001 0,003 0,001 0,013 0,03 0.002 es

Inorgani 0.3 0,000 0,032 0,102 0,007 0,288 0,02 0.001 c dust

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 33

Dohwa Consulting Engineers Co., Ltd

№ Place of Paramet Maximu Average Average Average Average Average Average Averag measurement № ers m arithmeti arithmetic arithmet arithmetic arithmeti arithmetic e checkpoint Permiss c value Value of ic Value of c Value Value of arithmet ible of factual Value of factual of factual factual ic Concen factual concentra factual concentrat concentr concentrati Value of tration concentr tion, concent ion, ation, on, mg/m3, factual (MPC) ation, mg/m3, ration, mg/m3, mg/m3, November concent on ND, mg/m3 July mg/m3, Septembe October ration, mg/m3 baseline August r mg/m3, data* Decem ber 2 Control point №2 Nitrogen 0.085 0,002 0,027 0,075 0,009 0,018 0,027 0.014 Site №1 dioxide 357+808km. Sulfur 0.5 0,000 0,149 0,213 0,008 0,023 0,037 0.03 dioxide

Carbon 5.0 0,000 0,241 0,148 0,006 0,013 0,127 0.12 Oxide

Aldehyd 0.035 0,000 0,003 0,005 0,002 0,007 0,006 0.002 es

Inorgani 0.3 0,000 0,219 0,291 0,025 0,048 0,037 0.002 c dust

3 Control point №1 Nitrogen 0.085 0,015 0,023 0,004 0,049 0,012 0.013 Site№2 dioxide v. Aspara Sulfur 0.5 0,008 0,018 0,001 0,396 0,032 0.019 328+300 km. dioxide Carbon 5.0 0,013 0,016 0,011 0,228 0,052 0.04 Oxide Aldehyd 0.035 0,000 0,006 0,002 0,007 0,001 0.001 es Inorgani 0.3 0,092 0,142 0,005 0,281 0,002 0.001 c dust 4 Control point № 2. Nitrogen 0.085 0,030 0,075 0,008 0,011 0,011 0.014 Site № 2. dioxide v. Аspara KM Sulfur 0.5 0,058 0,229 0,005 0,031 0,049 0.019 328+300 dioxide Carbon 5.0 0,039 0,161 0,015 0,032 0,100 0.09 Oxide Aldehyd 0.035 0,000 0,009 0,005 0,003 0,003 0.002 es Inorgani 0.3 0,170 0,393 0,016 0,008 0,008 0.001 c dust 5 Control point № 1. Nitrogen 0.085 0,005 - - 0,045 - - Site № 3. dioxide Quarry (Aspara 1 Sulfur 0.5 0,007 - - 0,274 - - and Ryskulov) dioxide Carbon 5.0 0,011 - - 0,486 - - Oxide Aldehyd 0.035 0,000 - - 0,022 - - es Inorgani 0.3 0,216 - - 0,295 - - c dust 6 Control point № 2. Nitrogen 0.085 0,023 - - 0,012 - - Site № 3. dioxide Quarry (Aspara 1 Sulfur 0.5 0,006 - - 0,02 - - and Ryskulov) dioxide Carbon 5.0 0,031 - - 0,105 - - Oxide

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 34

Dohwa Consulting Engineers Co., Ltd

№ Place of Paramet Maximu Average Average Average Average Average Average Averag measurement № ers m arithmeti arithmetic arithmet arithmetic arithmeti arithmetic e checkpoint Permiss c value Value of ic Value of c Value Value of arithmet ible of factual Value of factual of factual factual ic Concen factual concentra factual concentrat concentr concentrati Value of tration concentr tion, concent ion, ation, on, mg/m3, factual (MPC) ation, mg/m3, ration, mg/m3, mg/m3, November concent on ND, mg/m3 July mg/m3, Septembe October ration, mg/m3 baseline August r mg/m3, data* Decem ber Aldehyd 0.035 0,000 - - 0,002 - - es Inorgani 0.3 0,254 - - 0,026 - - c dust 7 Control point №1 Nitrogen 0.085 0,034 0,013 0,002 0,017 0,008 0.014 Site№ 4 dioxide Concrete Plant Sulfur 0.5 0,061 0,020 0,002 0,032 0,026 0.015 dioxide Carbon 5.0 0,297 0,101 0,006 0,015 0,121 0.11 Oxide Aldehyd 0.035 0,001 0,000 0,000 0,002 0,001 0.002 es Inorgani 0.3 0,057 0,16 0,003 0,011 0,010 0.002 c dust 8 Control point №2 Nitrogen 0.085 0,075 0,061 0,005 0,034 0,011 0.014 Site№4 dioxide Concrete Plant Sulfur 0.5 0,201 0,107 0,005 0,408 0,083 0.023 dioxide Carbon 5.0 0,269 0,116 0,134 0,344 0,127 0.20 Oxide Aldehyd 0.035 0,000 0,007 0,002 0,019 0,003 0.003 es Inorgani 0.3 0,164 0,293 0,007 0,113 0,013 0.001 c dust 9 Control point №1 Nitrogen 0.085 0,014 0,012 0,002 0,009 0,014 0.013 Site № 5 dioxide Crushing and Sulfur 0.5 0,004 0,058 0,016 0,035 0,026 0.012 screening plant dioxide Carbon 5.0 0,012 0,050 0,208 0,107 0,064 0.07 Oxide Aldehyd 0.035 0,007 0,006 0,005 0,003 0,002 0.001 es Inorgani 0.3 0,057 0,104 0,013 0,030 0,004 0.001 c dust 1 Control point № 2 Nitrogen 0.085 0,047 0,079 0,006 0,022 0,015 0.015 0 Site № 5 dioxide Crushing and screening plant

Sulfur 0.5 0,066 0,300 0,029 0,115 0,186 0.018 dioxide

Carbon 5.0 0,046 0,163 0,279 0,414 0,015 0.12 Oxide

Aldehyd 0.035 0,000 0,010 0,007 0,011 0,003 0.002 es

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 35

Dohwa Consulting Engineers Co., Ltd

№ Place of Paramet Maximu Average Average Average Average Average Average Averag measurement № ers m arithmeti arithmetic arithmet arithmetic arithmeti arithmetic e checkpoint Permiss c value Value of ic Value of c Value Value of arithmet ible of factual Value of factual of factual factual ic Concen factual concentra factual concentrat concentr concentrati Value of tration concentr tion, concent ion, ation, on, mg/m3, factual (MPC) ation, mg/m3, ration, mg/m3, mg/m3, November concent on ND, mg/m3 July mg/m3, Septembe October ration, mg/m3 baseline August r mg/m3, data* Decem ber Inorgani 0.3 0,144 0,227 0,035 0,112 0,009 0.003 c dust

1 Control point №1 Inorgani 0,3 0,003 0,015 0,003 0,007 0,006 0.003 1 Site № 6 c dust Storage of cement

1 Control point №2 Inorgani 0.3 0.078 0.137 0.012 0.102 0.011 0.003 2 Site №6 c dust Storage of cement

1 Control point №1 Aldehyd 0.035 0,000 0,006 - - - - 3 Site № 7 es Garage of storage tank for diesel fuel

Sulphure 0.008 0,00003 0,00006 - - - - tted hydroge n

1 Control point №2 Aldehyd 0.035 0,000 0,010 - - - - 4 Site № 7 es Garage of storage tank for diesel fuel

Sulphure 0.008 0,000 0,0002 - - - - tted hydroge n

Source: Report for the monthly Monitoring Report on the environmental protection and environmental monitoring of the branch KCC,July to December – 2012- Blank indicates measurements were not carried out due to the lack of road construction work.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 36

Dohwa Consulting Engineers Co., Ltd

Table 2.5- 2: Summary of Water Quality Results- (July to December 2012) - KCC

№ Name of test Norm Baseline The test results of natural water r.Kayindysay parameters of monitoring Remark MPC (Preconstruction mg/м3 stage) July July August Septembe r October November December 1 pН 6,5-8,5 7,13 7,45 7,1 7,35 7,9 8,1 7.3 Not exceeded of the MPC 2 Sodium 200 55,1 56,1 102,4 77,12 75,62 68,3 44.8 -//- Potassium 3 Potassium - 10,0 2,2 2,8 2,72 2,31 2,8 1.8 -//- 4 Calcium 180 87,8 81,1 76,4 78,8 66,7 76,8 42.7 -//- 5 Magnesium 50 31,0 46,7 50,0 30,29 28,4 33,7 26.4 -//- 6 Cupper 1,0 abs. 0,007 0,008 0,007 0,005 0,01 0.005 -//- 7 Zinc 5,0 0,09 0,05 0,07 0,009 0,06 0,07 0.04 -//- 8 Lead 0,03 abs. abs. abs. abs. abs. abs. abs. -//- 9 Manganese 0,5 0,041 0,012 0,134 0,108 0,110 0,122 0.08 -//- 10 Arsenic 0,05 abs. abs. abs. abs. abs. abs. abs. -//- 11 Phosphate 5,0 22,1 2,43 4,8 4,12 4,77 3,8 1.1 -//- 12 Chromium 0,05 0,022 0,003 0,00 0,00 0,00 0,00 0.00 -//- 13 Iron 0,3 0,011 0,24 0,27 0,227 0,254 0,274 0.08 -//- 14 Chloride 350,0 20,6 12,12 16,8 15,35 17,22 13,4 10.9 -//- 15 Sulfate 500 23,6 75,7 68,4 74,5 88,6 70,6 81.3 -//- 16 Ammonium 2,0 abs. abs. 1,4 0,21 0,14 0,08 0.15 -//- nitrogen 17 Nitrate 45,0 6,4 abs. 1,2 0,1 0,09 abs. abs. -//- 18 Fluoride 1,2 0,25 0,86 0,91 1,23 1,16 0,88 0.68 -//- 19 Mineral oil 0,1 0,034 0,09 0,1 0,09 0,07 0,09 0.05 -//- 20 Suspender 0,21 abs. 0,15 0,20 0,45 0,38 0,32 0.22 -//- matter 21 Chemical 30 4,05 8,6 10,6 11,6 10,8 11,4 10.3 -//- oxygen demand 22 Biological 6,0 1,55 4,1 5,2 5,7 4,9 5,3 4.7 -//- oxygen demand

Source: Report for the half year Monitoring Report on the environmental protection and environmental monitoring of the branch KCC, July to December – 2012- There is no water in the river Aspara from July to December, so, no monitoring was conducted. Abs- denotes- absent.

Table 2.5‐ 3: Summary of Average Equivalent sound level (dB) and corrected variation level Location Point July August September October November December Allowable Remarks limit, dB

Concrete 62.5 51.5 56.7 65.7 44.5 44.5 75 All the value is batching plant ((according within to the order allowable limit Crushing and 56.9 55.7 55.6 68.8 60.7 56.0 of Ministry The noise Screening of Health of level depends Plant RK No. 841 not only dated workers of Transportation 49.7 38.03 39.7 42.13 41.5 41.4 03.12.2004- road- building of stone maximum technologies, materials near permissible but also School N0 3 level) depends on intensity of a

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 37

Dohwa Consulting Engineers Co., Ltd

at Kyzylkystak transport system. Vibration level on areas of carrying out of instrumental measurements which also not exceeds permissible value (SanPiN RK 3.01.032- 97)

.

Near the 56.3 46.3 44 52.06 44.44 43.7 mosque at the turning of Crushing and Screening Plant

Source: Report for the half year Monitoring Report on the environmental protection and environmental monitoring of the branch KCC, July to December, 2012.

Table 2.5- 4 Household domestic wastewaters (workers’ settlement) Sewage Pond № 1 № Name of test Norm Sewage Pond №1 parameters of Remark MPC mg/м 3 July July August Septembe r October November December 1 Suspender matter 3730 - 176,0 - 122 No exceeded the maximum permissible Concentration ( MPC) 2 Chloride 75 - 32,8 - 18,7 -//- 3 Sulfate 460 - 68,1 - 166,9 -//- 4 Mineral oil 4,5 - 2,0 - 2,04 -//- 5 Ammonium nitrogen 20,0 - 16 - 17,9 -//- 6 Phosphate 5,0 - 4 - 3,7 -//- 7 Iron 0,8 - 0,6 - 0,76 -//- 8 Anionic Surfactant 10,2 - 2,8 - 2,8 -//- 9 Nitrate 16,5 - 3,4 - 5,8 -//- 10 Nitrite 2,5 - 0,5 - 0,64 -//- 11 Fluoride 1,2 - 1,2 - 0,91 -//- 12 Chemical oxygen 1000 350 - 364 -//- demand 13 pH - 6,5 - 7,2 -//- Source: Report for the half year Monitoring Report on the environmental protection and environmental monitoring of the branch KCC, July to December

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 38

Dohwa Consulting Engineers Co., Ltd

Table 2.5-5 Household domestic wastewaters (workers’ settlement) Sewage Pond № 2 № Name of test Norm Sewage Pond № 2 parameters of Remark MPC mg/м 3 July July August Septembe r October November December 1 Suspender matter 3730 - 306,4 - No exceeded the maximum permissible Concentration ( MPC) 2 Chloride 75 - 44,1 - -//- 3 Sulfate 460 - 125,3 - -//- 4 Mineral oil 4,5 - 2,4 - -//- 5 Ammonium nitrogen 20,0 - 20,0 - -//- 6 Phosphate 5,0 - 5,2 - -//- 7 Iron 0,8 - 0,93 - -//- 8 Anionic Surfactant 10,2 - 3,4 - -//- 9 Nitrate 16,5 - 3,8 - -//- 10 Nitrite 2,5 - 0,8 - -//- 11 Fluoride 1,2 - 1,2 - -//- 12 Chemical oxygen 1000 620 - -//- demand 13 РН - 7,08 - -//- Source: Report for the half year Monitoring Report on the environmental protection and environmental monitoring of the branch KCC, July to December

Table 2.5-6 Household domestic wastewaters (office) Sewage Pond № 1 № Name of test Norm Sewage Pond №1 parameters of Remark MPC mg/м 3 July July August Septembe r October November December 1 Suspender matter 3730 - 106,5 95.7 No exceeded the maximum permissible Concentration ( MPC) 2 Chloride 75 - 30,4 26.9 -//- 3 Sulfate 460 - 155,3 147.2 -//- 4 Mineral oil 4,5 - 1,2 ‐ -//- 5 Ammonium nitrogen 20,0 - 15,7 12.77 -//- 6 Phosphate 5,0 - 4,3 4.9 -//- 7 Iron 0,8 - 0,77 0.66 -//- 8 Anionic Surfactant 10,2 - 2,3 3.0 -//- 9 Nitrate 16,5 - 5.0 6.2 -//- 10 Nitrite 2,5 - 0.45 0.52 -//- 11 Fluoride 1,2 - 0.97 0.88 -//- 12 Chemical oxygen 1000 483 307 -//- demand 13 pH - 6,9 7.6 -//- Source: Report for the half year Monitoring Report on the environmental protection and environmental monitoring of the branch KCC, July to December

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 39

Dohwa Consulting Engineers Co., Ltd

Findings: Air Quality The representative results indicates that, the contents of the controlled components (Inorganic dust, Nitrogen dioxide, Sulfur dioxide, Carbonmonoxide, Aldehydes) in the atmospheric air at the Sites do not exceed the maximum permissible concentration specified in the inventory of emissions of harmful substances into the air.

Water Quality

According to the results, the month characteristics at the River Kayindysay are within the permissible level according to the National standards.

Noise Quality

Indicators of noise and vibrations tests do not exceed permissible values , as the main quantity of the work is performed away from settlements.

Observation: Some of the non-compliance issues/aspects were observed in the past monitoring (July to December) as mentioned in the Environmental Chapter of the monthly progress report was as follows: Table 2.5-7Observation of Non-Compliance Issues/Aspects Location Observation Chainage 319 km The air pollution is due to dust from road and vehicular emission.Plentiful dust from road at chainage 319 km near Aspara village during transportation of materials as the subcontractors did not measures on dust suppression in a proper manner.

Cement Batching Plant  There is no fitted sanitation pits with the liquid for washing wheels of transport engaged in transporting materials  On the border territory of Batching Plant, there are some warehousing of defective concrete unusable for the road construction  A container for solid waste management is installed on the surface of the Earth and not surrounded with fence  Sewage thrown to the Earth’s surface, which can cause their rupture and water running to the surface of the Earth and it is not rational management of natural resources  From the transition well of water supply wells for No 1 ( 2011) water is leaking to the ground which is a violation of natural resource management

Concrete Batching Plant  There is no cover & fence protection on the tank for drain the wastewater  Violation of safety standards in respect of wearing protective equipment like dusk musk, safety helmet, protective shoes etc. during working hours Vehicle Maintenance Area – Garage  Oil products and droppings found in the territory of garage. Bottom of the earth are

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 40

Dohwa Consulting Engineers Co., Ltd

soaked with lubricating oil.  Garage area littered with household solid wastes and burnt the solid wastes within the compound  There is no device of the control of toxicity and smoke of exhaust gases from vehicles and did not control the toxicity standards  There are open storage barrels of petrol, oil and lubricants at the unequipped sites within the territory. Due to this, oil is leaking in the ground and filling the earth of the lower layers is soaked with fuel. Camp Site Violation of safety standards in respect of wearing protective equipment like dusk musk, safety helmet, protective shoes etc.

2.3.2 Contract 005- Kazakhdorstroy, Km 358.6 to Km 389.4 The Kazakhdorstroy completed their construction works before the schedule. They are now on process to hand over their sites to CR. They have started to dismantle camps, batching plant, crushing plant etc.

Environmental mitigation and monitoring plan (EMMP) was submitted in January 27, 2012, based on clause 106 of Technical specifications and sub-clause 4.18 of Special conditions of the Contract.The following Table shows the detail monitoring program and Figure 2.2 shows the Environmental monitoring map.

Table 2.6: Monitoring Schedule- KDS

Frequency of Monitoring № Description of the Activities Location i/o 1 2 3 4 Air Quality Monitoring Instrumental measurement of basic Source location of pollution Commencement of environmental indicators (Concrete-batching plant –km 368;v. construction 1.1. Zhanaturmys – km 377; v. Kazakh – km 383)

Routine instrumental measurements of Locationofpollutionsources Not less than once per air pollution (Concrete-batching plant - km 368 , month or more often as v. Aktogan – km 367, v. required by the Engineer Zhanaturmys - km 377; v. Kazakh - 1.2. km 383, quarry of loam site-3 – km 370+1000 m to the right from the road towards mountains ; crushing- stone plant Karakystak-2 - km 389,4+12 kmtowards the mountains) Water quality monitoring Conduct quality analysis of water Bridges locations at water sites Before civil works 2.1. (baseline data) (Koltogan river, Big Chu Channel) commencement

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 41

Dohwa Consulting Engineers Co., Ltd

Conduct water quality monitoring Not less than once a Bridges locations at water sites 2.2. month or often on (Koltogan river, Big Chu Channel) Engineer’s request Noise and Vibration Monitoring Instrumental measurement of basic In neighboring settlements located on Commencement of noise and vibration indicators the boundary with Sanitary Protected construction stage 3.1. Zone (Zhanaturmys v.; Kazakh v.; Altogan v.)

Routine instrumental measurements of In neighboring settlements located on Not less than once per noise and vibration the boundary with Sanitary Protected month or more often as 3.2. Zone (Zhanaturmys v.; Kazakh v.; required by the Engineer Altogan . v.)

Air quality monitoring was done before the performance for the construction of roads conducted in October 2010, on the concrete batching plant, Zhanaturmys village and Kazakh village. Routine instrumental measurements were carried out monthly by the accredited laboratory ZhB “KESO Otan” LLP under the Contract No. 67 of 05.03.2012.

Air quality monitoring was conducted in accordance with time program of control for compliance with standards related to maximum-permissible emissions included in Industrial Ecological Control program, which approved by Shu-Talas department of ecology. Concentration of pollutants on the control points characterizing the influence of object on environment has been undergone by express method with gas analyzer «GАNК-4».

Water Quality Monitoring of Koltogan river was conducted on following parameters: Sodium + Potassium; Potassium; Calcium; Magnesium; Copper; Zinc; Lead; Manganese; Arsenic; Phosphates; Chromium; Iron; Chlorides; Sulfates; Nitrogenammonium; nitrates; fluorides; mineral oil; Suspended matter; рН; Chemical oxygen demand (COD); Biochemical oxygen demand (BOD5). Domestic waste waters from construction camp were taken out by special motor transport on treatment plants under the contract, in this connection waste water monitoring was not conducted.

Noise and vibration measurements have been made with instrument - "Assistant". The given instrument can be applied for measurement of the sound parameters, infrasound, and ultrasound, general and local vibration on workplaces, inhabited and public buildings, and territories.

Figure 2.2 shows the schematic layout of Environmental monitoring location.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 42

Dohwa Consulting Engineers Co., Ltd

Figure 2.2:Schematic drawing of Sampling point location- KDS Legend r.Koltogan № - Sampling locations Monitored parameters Distance to facilities Note 1 Storage areas for road- points construction materials 1 Koltogan river (km 364) Naturewater 20 m. from the road km 364

- Measurement 2 Large Shu Channel (km 366) Nature water 8 m. fromtheroad points Concrete batching plant (CBP) Air, physical parameters (noise, 1. Koltogan river 3 50 m. to the CBP 2. Big Chu Channel (km 368) vibration) Air, physical parameters (noise, 3. Concrete batching plant 4 Zhanaturmys village (km 377) 15 m. fromtheroad vibration) 4. Zhanaturmys village Air, physical parameters (noise, 5 Kazakhvillage (km 383) 20 m. fromtheroad 5. Kazakh village vibration) 6. Aktogan village Air, physical parameters (noise, 6 Aktoganvillage (km367) 20 m. fromtheroad vibration) Km 366 Air, physical parameters (noise, 10 m. from the construction 2 7 Constructionsite 7. – Lay out of the vibration) area, km 382 concrete batching plant and Quarry of loam "Land lot № 3" km Big Chu Channel of the construction camp. 8 370+1000 m (right towards the Air 10 m from the quarry mountains)

km 389,4

5 v.Kazakh v.Zhanaturmys

km 378 7 km 383 4 3 km 367

km 377 km370 km 368 6 v.Aktogan 8

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 43

Dohwa Consulting Engineers Co., Ltd

The summary of monitoring results on air, water and noise quality for this bi-annual period (January to June 2012) are shown in Table 2.4-1, Table 2.4- 2, Table 2.4-3 respectively. Table 2.6- 1: Summary of Air Quality Results- (July to December 2012) - KDS

№ Place of Parameters Maximum Average Average Average Average Average Average Average arithmetic measuremen Permissibl arithmetic arithmetic arithmetic arithmetic arithmetic arithmetic Value of factual t № e value of Value of Value of Value of Value of Value of factual concentration, mg/m3, checkpoint Concentrat factual factual factual factual factual concentration, December ion (MPC) concentrati concentrati concentration concentration concentration, mg/m3, on ND, on, mg/m3 on, mg/m3, , mg/m3, , mg/m3, mg/m3, November mg/m3 baseline July August September October data* 1 Site № 1 Nitrogenoxide 0.4 0.000 0.001 0.006 0.005 0.004 0,008 Samplings were not Sampling point conducted due to the end № 1 Carbon Oxide 5.0 0.046 0.001 0.062 0.011 0.012 0.007 of road construction works Concrete and precipitations in the Batching Plant (windward) Inorganic dust 0.3 0.000 0.003 0.003 0.003 0.001 0.001 form of snow

2 Site № 1 Nitrogenoxide 0.4 0.000 0.013 0.015 0.018 0.022 0.017 Sampling point № 2 Carbon Oxide 5.0 0.000 0.019 0.014 0.035 0.038 0.023 Concrete Batching Plant (Leeward) Inorganic dust 0.3 0.000 0.033 0.043 0.027 0.024 0.003

3 Site № 2 Inorganic dust 0.3 0.000 0.001 0.001 0.001 0.001 0.000 0.001 Sampling point № 1 v. Zhanaturmys (Windward) 4 Site № 2 Inorganic dust 0.3 0.000 0.003 0.005 0.006 0.001 0.001 0.004 Sampling point № 2 v. Zhanaturmys (Leeward) 5 Site № 3 Inorganic dust 0.3 0.000 0.001 0.003 0.002 0.000 0.000 0.001 Sampling point № 1 v. Kazakh (Windward)

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 44

Dohwa Consulting Engineers Co., Ltd

№ Place of Parameters Maximum Average Average Average Average Average Average Average arithmetic measuremen Permissibl arithmetic arithmetic arithmetic arithmetic arithmetic arithmetic Value of factual t № e value of Value of Value of Value of Value of Value of factual concentration, mg/m3, checkpoint Concentrat factual factual factual factual factual concentration, December ion (MPC) concentrati concentrati concentration concentration concentration, mg/m3, on ND, on, mg/m3 on, mg/m3, , mg/m3, , mg/m3, mg/m3, November mg/m3 baseline July August September October data* 6 Site № 3 Inorganic dust 0.3 0.000 0.003 0.021 0.005 0.002 0.001 0.002 Sampling point № 2 v.Kazakh(Leew ard) 7 Site № 4 Nitrogendioxide 0.085 Baseline 0.002 0.002 0.002 0.002 0.001 Samplings were not Sampling point sampling conducted due to the end № 1 was not of road construction works Construction Nitrogen Oxide 0.4 conducted 0.001 0.002 0.002 0.002 0.001 and precipitations in the site form of snow (Windward) Carbon black 0.15 0,000 0.000 0.000 0.000 0.000

Sulfur dioxide 0.5 0.001 0.002 0.001 0.001 0.000

Carbon Oxide 5.0 0.002 0.078 0.018 0.036 0.013

Alkanes 1.0 0.000 0.000 0,000 0.000 0.000

Inorganic dust 0.3 0.003 0.007 0.006 0.000 0.001

8 Site № 4 Nitrogendioxide 0.085 Baseline 0.044 0.014 0.031 0.018 0.013 Samplings were not Sampling point sampling conducted due to the end № 2 was not of road construction works Construction Nitrogen Oxide 0.4 conducted 0.027 0.010 0.014 0.014 0.014 and precipitations in the site form of snow (Leeward) Carbon Black 0.15 0.000 0.000 0.000 0.000 0.000

Sulfur dioxide 0.5 0.033 0.017 0.013 0.017 0.010

Carbon Oxide 5.0 0.286 0.315 0.057 0.075 0.031

Alkanes 1.0 0.000 0.000 0.000 0.000 0.000

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 45

Dohwa Consulting Engineers Co., Ltd

№ Place of Parameters Maximum Average Average Average Average Average Average Average arithmetic measuremen Permissibl arithmetic arithmetic arithmetic arithmetic arithmetic arithmetic Value of factual t № e value of Value of Value of Value of Value of Value of factual concentration, mg/m3, checkpoint Concentrat factual factual factual factual factual concentration, December ion (MPC) concentrati concentrati concentration concentration concentration, mg/m3, on ND, on, mg/m3 on, mg/m3, , mg/m3, , mg/m3, mg/m3, November mg/m3 baseline July August September October data* Inorganic dust 0.3 0.088 0.032 0.032 0.001 0.002

9 Site № 5 Inorganic dust 0,3 0.000 0.002 0.001 0.002 0.001 0.002 0.001 v. Aktogan Sampling point № 1 (Windward)

10 Site № 5 Inorganic dust 0.3 0.000 0.005 0.006 0.006 0.001 0.001 0.002 v. Aktogan Sampling point № 2 (Leeward)

11 Site №6 Nitrogen dioxide 0.085 0.000 Quarry of loam Site No. 3 Sampling point Carbon black 0.15 0.000 № 1 (Windward) Sulfur dioxide 0.5 0.000 Baseline sampling Samplings were not conducted in connection with the end of loam mining Carbon oxide 5.0 was not 0.001 conducted

Alkanes 1.0 0.000

Inorganic dust 0.3 0.005

12 Site №6 Nitrogen dioxide 0.085 0,024 Quarry of loam Site No. 3 Sampling point Carbon black 0.15 Baseline 0.000 Samplings were not conducted in connection with the end of loam mining № 2 (Leeward) sampling

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 46

Dohwa Consulting Engineers Co., Ltd

№ Place of Parameters Maximum Average Average Average Average Average Average Average arithmetic measuremen Permissibl arithmetic arithmetic arithmetic arithmetic arithmetic arithmetic Value of factual t № e value of Value of Value of Value of Value of Value of factual concentration, mg/m3, checkpoint Concentrat factual factual factual factual factual concentration, December ion (MPC) concentrati concentrati concentration concentration concentration, mg/m3, on ND, on, mg/m3 on, mg/m3, , mg/m3, , mg/m3, mg/m3, November mg/m3 baseline July August September October data* Sulfur dioxide 0.5 was not 0.044 conducted Carbon oxide 5.0 0.173

Alkanes 1.0 0.000

Inorganic dust 0.3 0.094

Source: Report for the half year on environmental protection and environmental monitoring ZhB “Kazakhdorstroy LLP, July to December – 2012- Blank indicates measurements were not carried out due to the lack of road construction work.

Table 2.6-2: Summary of Water Quality Results- (July to December 2012) - KDS

Sampling MAC Actual Actual Actual Actual Actual Actual location, № As per concentration, concentration, concentration, concentration, concentration, concentration, № of Indicators Baseline data i/o ND, mg/m3, mg/m3, mg/m3, mg/m3, mg/m3, mg/m3, sampling mg/m3 July August September October November December point

рН 6,5 - 8,5 7,37 8,11 7,4 7,01 7,7 7,8 Samplings Sodium+Potassium 200 48,3 52,5 were not 31,53 44,35 32,4 29,4 conducted due Potassium 20 2,3 2 2,44 1,93 1,88 to the end of Water, Calcium 180 138 120,2 road 1 Koltogan 164,13 150,9 80,22 77,3 construction channel Magnesium 50 28,8 25,4 24,75 29,09 20,55 22,4 works and Copper 1 Abs. Abs. 0,007 Abs. Abs. Abs. precipitations Zink 5 0,05 0,04 0,07 0,007 0,05 0,07 in the form of Lead 0,03 Abs. Abs. Abs. Abs. Abs. Abs. snow International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 47

Dohwa Consulting Engineers Co., Ltd

Manganese 0,1 0,064 0,017 0,08 0,023 0,04 0,06 Arsenic 0,05 Abs. Abs. Abs. Abs. Abs. Abs. Phosphates 5 39,2 2,52 5 4,99 3,88 4,2 Chrome 0,05 0,016 0,011 0 0 0 0 Iron 0,3 0,044 0,06 0,3 0,288 0,107 0,221 Chlorides 350 42,7 11,3 12,7 16,9 15,44 13,7 Sulfate 500 55,7 152,1 208,1 93 81,2 77,6 Ammonium nitrogen 20 Abs. Abs. 0,43 0,46 0,88 0,92 Nitrates 45 14,2 9,2 6,1 7,13 8,05 9,22 Fluoride 1,2 0,48 0,51 0,52 0,41 0,66 0,81 Oil products 0,1 0,022 0,06 0,1 0,08 0,05 0,07 Suspended 0,25 Abs. 0,11 substances 0,08 4,7 0,55 0,68 Chemical oxygen 30 7,76 12,5 demand 15,3 9,55 11,2 10,5 Biological oxygen 6 2,15 5,8 demand 6,5 4,8 5,3 4,8 рН 6,5 - 8,5 7,13 6,8 Sodium+Potassium 200 55,1 55,2 Potassium 10 1,5 Calcium 180 87,8 88,9 Magnesium 50 31 30,3 Copper 1 Abs. Abs. Samplings were not Zink 5 0,09 0,05 conducted due Water, Lead 0,03 Abs. Abs. to the end of Analysis of natural water was not conducted in connection with the 2 Big Chu Manganese 0,1 0,041 road absence of water 0,08 channel construction Arsenic 0,05 Abs. Abs. works and Phosphates 5 22,1 3,7 precipitations Chrome 0,05 0,027 0 in the form of Iron 0,3 0,011 0,122 snow Chlorides 350 20,6 15,8 Sulfate 500 23,6 55,3 Ammonium nitrogen 20 Abs. 0,77 Nitrates 45 6,4 6,5

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 48

Dohwa Consulting Engineers Co., Ltd

Fluoride 1,2 1,25 0,56 Oil products 0,1 0,034 0,05 Suspended 0,25 Abs. substances 0,74 Chemical oxygen 30 4,05 demand 9,22 Biological oxygen 6 1,55 demand 4,1

** Analysis of natural water in Koltogan River and in Big Chu channel for December 2012 was not conducted due to the end of road construction works and precipitations in the form of snow

*** Analysis of natural water in Big Chu Channel was conducted only in November 2012 because water is given under the certain schedule and in definite time period.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 49

Dohwa Consulting Engineers Co., Ltd

Table 2.6- 3: Summary of Average Equivalent sound level (dB) and corrected variation level

Location July August September October November December Allowable Remarks Point limit, dB

Concrete 63 55 56 62 61 - 75 ((according Measurements batching plant to the order of have not been Ministry of conducted due Village 43 44 42 41 41 41 Health of RK to the absence Zhanaturmys No. 841 dated of works in 03.12.2004- December for Village Kazakh 42 44 41 41 44 45 maximum concrete permissible batching plant. Village 43 43 43 42 56 54 level) The noise level Aktogan depends not only on workers of road- building technologies, but also depends on intensity of a transport system. Vibration level on areas of carrying out of instrumental measurements which also not exceeds permissible value (SanPiN RK 3.01.032-97)

Source: Report for the half year on environmental protection and environmental monitoring ZhB “Kazakhdorstroy LLP, July to December – 2012-

. Findings: Air Quality

Summary of the table presents (Table 2.4-1) a comparative analysis of: the actual concentration of basic indicators (baseline data), the measurement results for the reporting months–from July to December 2012 and maximum permissible concentrations of pollutants.

The results confirm that there have not been any measured excesses during the monitoring period. The results of monitoring show that the content of contaminators does not exceed MPC inaccordance with ecological requirements of Republic of Kazakhstan.

It is noted that emission concentrations will vary in accordance with meteorological conditions, (wind speed and direction and relative humidity), number and mechanical condition of construction machinery and volume, vehicle type, travel direction and mechanical condition of passing traffic.

Water Quality

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 50

Dohwa Consulting Engineers Co., Ltd

For the period from July to November water samplings were taken in Koltogan River. Due to the lack of water in Big Chu Channel (BCC), monitoring of nature water was carried out only in November. Analysis of natural water in December 2012 was not conducted both rivers due to the end of road construction works and precipitations in the form of snow.

From Table 2.4-2, No excesses were recorded by the monitoring. All results are below or within ranges specified by Kazakhstan regulations.

Noise Quality

According toSNiP12/11/77"Protection againstnoise"and in accordancewith the order ofActingMinisterof HealthonMarch 24, 2005№ 136maximumpermissible level (MPL), the noiseis 75dB. Measurements ofbaselinenoise and vibration levelswere carried out onthe border of sanitary- protective zone ofMortar-concrete plant,sitelocation of crushing and screening planton the depositKarakystak-2andhuman settlements(Aktoganv.,Zhanaturmysv.,, Kazakhv.). According to the resultsof measurementsof noise levelscan be seenthat the excessnoiseMPLis not fixed.The noise leveldepends not only onthe workingof road construction equipment, but also on the intensity oftraffic flow.Vibration levelsat the sitesof theinstrumental measurementsalsodo not exceed thepermissible values.

Observation: Some of the non-compliance issues/aspects were observed in the past monitoring (July to December) as mentioned in the Environmental Chapter of the monthly progress report was as follows: Table 2.6-4Observation of Non-Compliance Issues/Aspects

Location Observation Vehicle Maintenance Area – Garage  Oil products and droppings found in the territory of garage. Bottom of the earth are soaked with lubricating oil.  Garage area littered with household solid wastes and burnt the solid wastes within the compound  There is no device of the control of toxicity and smoke of exhaust gases from vehicles and did not control the toxicity standards  There are open storage barrels of petrol, oil and lubricants at the unequipped sites within the territory. Due to this, oil is leaking in the ground and filling the earth of the lower layers are soaked with fuel. Camp Site  Garage area littered with household solid wastes and burnt the solid wastes within the compound

 Violation of safety standards in respect of wearing protective equipment like dusk musk, safety helmet, protective shoes etc.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 51

Dohwa Consulting Engineers Co., Ltd

2.3.3 Contract No NCB-1 and NCB-2 - Aksioma Service Contract” LLP In pursuance of the requirements of “Technical Specifications” and Contract Terms during the reporting period the Contractor was produced Environment Mitigation Plan and Monitoring Programme. For implementation of Operational Environmental Monitoring, the Contractor has entered into a Contract with the accredited laboratory ZhB “KESO Otan” LLP under the Contract No. 79 ЖФ, however for the reporting period the Contractor was not submitted any analytical results of environmental quality parameters.

The building site is a ground of Road maintenance depot at the 163 km of the Almaty-Korday- Blagoveshchenka-Merke--Termez road (turning to Otar) in Zhambyl region.

The area of the plot of RMD makes 1,5 ha, including building area – 258,3 m2, landscaping area – 6269,1 m2, coverage area – 6972,6 m2

Atmospheric air

The main pollution sources at thorough repair of complex of buildings and facilities of RMD-34 are special construction engineering (excavator, bulldozer, crawler crane), motor transport, a mobile welding station, which have a negative effect on the community air.

The main polluting substances, those form at the building process: inorganic dust Sio 20-70%, benzapyrene, aldehydes, nitrogen dioxide, sulfur dioxide, soot, carbon oxide, hydrocarbons.

At a stage of construction works operation of motor transport and the construction special equipment, working on diesel fuel is expected. For assessment of the amount of harmful emissions, the Contractor used their specific value from РНД 211.1.03.01-96, Алматы, 1996and fuel consumption values for the whole construction period.

Construction period of the complex of buildings and facilities of RMD in the v. Otar. Zhambyl region will last 22 months, during this period a negative effect on the atmospheric air takes place (operation of machinery and units), water resources are used, and also formation of the wastes of production and consumption takes place, there was no negative effect on land and biological resources.

Pollution of the community air at the construction period of the complex of buildings and facilities of RMD is conditioned by operation of construction diesel engineering.

Water Resources

The source of water supply on the site – is an existing artesian well. For production needs and watering of green plantations in the territory the service water is used.

Norms for calculation of the volume of household water use for the needs of construction personnel are accepted at the rate of 30 l/day per person (Construction Rules and Regulations of the Republic of Kazakhstan 4.01-02-2001), and also for technological needs.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 52

Dohwa Consulting Engineers Co., Ltd

Table 2.7: Balance of the general water use and water drain at construction of RMD

Water consumption, m3 per season Water drain, m3 per season Service water Water For For For Irretrievable consumers household Total Service Household technical production losses purpose purpose purpose

Production - - 244 244 - 129.6 32.4 personnel

Technical needs 11 11 0.5 6.5

Total: 11 2447 255 0.5 129.6 37.9 Source: Environmental Report of Axiom‐Service‐Contract, 2012

Dumping of household drains, forming in the course of construction and further operation of the complex of buildings and facilities of RMD is carried out in the concrete cesspool and then on the grounds of the contract with the specialized organization it is removed to filtration fields.

In connection with small water consumption and the lack of industrial drains the negative effect of construction of the complex of buildings and facilities on superficial natural water bodies and ground waters is not expected.

Wastes

Expected impact on soil cover can be expressed in its pollution by construction materials, wastes of production and consumption, petroleum products when filling the equipment with fuels and lubricants. However for the construction period crushed stone, bitumen, cement etc. are used directly from “wheels” without construction of temporary grounds for construction materials, collection of domestic and construction wastes, their timely removal are provided. Storing or burial of toxic, radioactive wastes, solid domestic wastes are excluded by construction technology.

When carrying out construction works solid domestic waste (SDW), construction waste and stubs of welding electrodes are formed. Construction waste is formed during construction works, when carrying out plaster and face work. The structure of waste can include, for instance, cement remains – 10%, sand – 30%, breakage of ceramic tile – 5%, plaster – 55%. By accumulation it is removed from the territory to the rural landfill.

Stubs of welding electrodes are remains of electrodes after their use at welding works in the course of repair of main and auxiliary equipment. They are placed in containers on a waterproof surface.

The Contractor has entered into an Agreement with “Housing and communal services enterprise of the akimat, Korday region” for rendering services on removal of solid domestic waste for legal entities.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 53

Dohwa Consulting Engineers Co., Ltd

Observation: During site inspection, the following non- compliance issues were identified: 1. Construction area was found with Oil products and droppings 2. Due to the absence of garbage containers for solid waste disposal, the construction area littered with household solid wastes and burnt the solid wastes within the compound 3. The place for collection and temporary storage of used oil and oily rags was absent 4. Wastes (construction garbage) were disposed not in the proper place of construction area

2.3.4 Contract No NCB-3and NCB-4 - “Construction Corporation Kulager” LLP In pursuance of the requirements of “Technical Specifications” and Contract Terms duringthe reporting period, the Contractor was produced Environment Mitigation Plan and Monitoring Programme. During this reporting period, the Contractor was submitted analytical results of air quality of 4th quarter (October to December) for the year 2012 only.

Monitoring of Atmospheric air

According to the report, Kulager has one industrial site DEU-35 Merke village Merken district of Zhambyl region in which there are seven sources of emissions to the atmosphere, of which organized - 9, unorganized - 9 equipped PGUU - no.

Total estimated emissions for quarter 4 of the year 2012 (October to December) was 5.055 tons, including gas - 3.0671 tons and solid - 1.9877.

The Contractor has conducted on the sources of emissions on a quarterly basis, in accordance with the schedule of control, coordinated by the Department of Ecology in Zhambyl region. Thecontractor performed air quality monitoring through accredited laboratory named “KESON UTAN” under the contract number 71 dated April 16, 2012.

Table 2.8: Air Quality on border Sanitary Protection Zone for the 4th quarter 2012 Location Nitrogen di Oxide Carbon Smoke Black Hydrocarbons Inorganic Dust (actual Oxide (actual c12-c19 (actual concentration, (actual concentration, (actual concentration, mg/m3) concent mg/m3) concentration, mg/m3) ration, mg/m3) mg/m3)

Border of 0.0207 0.017 NR 0.0123 0.0253 Sanitary Protection Zone ( Point 1) Border of 0.0143 0.0253 NR 0.046 0.065 Sanitary Protection Zone ( Point 2)

NR- no substance identified in recording; Source: Environmental Report of Kulager for 4th Quarter, 2012

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 54

Dohwa Consulting Engineers Co., Ltd

The results of monitoring show that the content of contaminators does not exceed Maximum Allowable Concentration in accordance with ecological requirements of Republic of Kazakhstan.

Water Monitoring

Water source at the site is the existing borehole. Annual consumption of water at the site are to l be 4.481 thousand m3/year, including:

- Household needs - 0.642 thousand m3/year; - Production needs - 0.246 thousand m3/year

Water consumption limit for quarter 4 of 2012 composed in volume 1120.0 m3.

Sewage disposal is provided to the network with a sewer drain in pit concreted tank 15m3 and 50m3. Sump is buried in the ground ferro-concrete capacity in terms of rectangular shape with a brick superstructure with two compartments. Water drainage at the site is 3.841 thousand m3/year (farm domestic waste water).

As the filling sewage from the sump was pumped special auto-transport special-organization, contract.Monitoring of compliance with the established standards of sewage was not performed. Waste Monitoring Solid domestic waste is generated in the non-manufacturing sector of the staff, as well as janitorial and grounds. Waste at the site was collected in one metal container located in a special place on the tarmac (waterproof) surface, and the accumulation of leaves on the rural landfills under contract with the state of emergency "Dzhumasheva N.O." for number 01 0.05.2012.

Ogaryshi welding electrodes are the remnants of the electrodes after using them for welding in the repair of main and auxiliary equipment. Stirred containers on impervious surfaces, as experience was taken to rural landfills under contract with the state of emergency "Dzhumasheva N.O." for number 01 01.05.2012, but at least one every three months.

On all hazardous wastes are developed at the request of the passport of the Environmental Code of Kazakhstan.

About 1 ton solid waste was removed during October to December 2012 (quarter 4 of 2012). Observation: During site inspection, the following non-compliance issues were identified: 1. On the whole territory of Depot 35 in various places, construction materials were stored: wooden beams, elements of metal structures, bricks etc. leads to the lettering of the territory 2. Scrap metal was stored in places not intended and unequipped for storage of scrap metal 3. Construction area was found with Oil products and droppings 4. Due to the absence of garbage containers for solid waste disposal, the construction area was littered with household solid wastes and burnt the solid wastes within the compound 5. The place for collection and temporary storage of used oil and oily rags was absent

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 55

Dohwa Consulting Engineers Co., Ltd

6. There are some wells of sewage system that are out of repair and because of this water flows to the surface through the neck of the well and this is the violation of the Water Code of RK 7. Workers were not provided with the safety equipment, special clothes, special shoes etc. 8. A handmade boiler was installed in the checkpoint which causes emissions due to the burning of coal and wood without permission from relevant authority

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 56

Dohwa Consulting Engineers Co., Ltd

3.0 ENVIRONMENTAL MANAGEMENT PLAN 3.1 Overview

The Environmental Management Plan (EMP) was designed to avoid, reduce, or at least minimize the adverse environmental impacts that could result from the activities during the implementation and operation of the project. Accordingly, the EMP considered all phases of the Project cycle, namely the detailed design, construction and operational phases of the Project. It consists of various mitigation measures needed to be undertaken in the course of the Project cycle.

All potential environmental impacts identified in the Environment Impact Assessment Report for the said Road project are listed in the EMP. The description of the respective proposed protection or mitigation measures, their attributes and the responsible entities for their implementation were also presented vis-à-vis the impacts. This EMP was presented in a matrix form in the EIA Report and is being used as the basis of the periodic monitoring activities during the construction period of the Project road.

3.2 Implementation of the EMMP The Contractor is responsible for implementation of EMMP during construction works and Construction Supervision Consultant (CSC) is primarily responsible for supervision of monitoring of the implementation of the EMMP. The CR engaged PMC as an external monitoring consultant’ to monitor implementation and supervision of EMMP. As such, the PMC-ADB, CSC monitors and measures the progress of implementation of the EMP on behalf of the borrower/client.

Site inspections were conducted on various environmental aspects of the project and these were audited to form part of the Monthly Progress Report. Domestic environmentalist and International Environmental Specialist went to assess various sites along the Project Road as well as other locations that might pose some environmental concerns in the vicinity of the road such as the active quarry, Contractor’s campsite, batching plant, equipment maintenance sites, etc. During the inspection, a number of environmental and safety issues were observed and noted. These issues were subsequently brought to the attention of the personnel concerned on the CSC side as well as discussed with the Contractor’s side. The issues observed were generally concerning with the active quarry operations and rehabilitation, potential contamination in proposed material plants, noise and dust generation at soil hauling areas, and contractor’s work camp housekeeping. Following CSC’ direction and advice, the Contractors should implement these corrective actions and follow up on these actions to ensure their effectiveness.

3.3 Site Inspection and Audits According to the observations made during the site inspections by Supervision Consultant (CSC) further improvements were done at the sites. Joint weekly inspections of the CSC with the Contractor, Joint inspections, and monthly meetings have helped to sort out some of the problems at the site. The following Table 3.1 presents the summary of site visits.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 57

Dohwa Consulting Engineers Co., Ltd

Table 3.1: Summary of the Number and Type of Site Inspection

Date Contracts Remarks KCC KDS Kulager Axioma July 9,2012 © Meeting with Deputy Director, Zhmbal Road Department and site inspection of bypass road section ( 310 km to 328 km) to see air quality condition of the area July 23, 2012 © © Siteinspection September 4, 2012 © SiteInspectiontoDepot 35 September 4, 2012 October 15, 2012 © Site inspection to construction camp, CBP, disposal site October 20, 2012 © Site inspection December 20, 2012 © Site inspection to Equipment Vehicle Maintenance (Garage area) December 21, 2012 © Site inspection to CBP, Camp site, Equipment Vehicle Maintenance area December 21, 2012 © Site inspection to Quarry area , stock piling area December 24, 2012 © Site inspection to the territory of construction site December 28, 2012 © Site inspection to the territory of construction site Source: Compiled from Office record, July- December 2012

3.4 Non-Compliance Notices/Letters During the course of the construction supervision of the works, a number of Non-Compliance Notices were written by the Engineer to the Contractor. Among them are as follows.

Table 3.2: Non Compliance Notice (July- December 2012)

Date ReferenceNumber Subject Issues

July 03, 2012 KCC-MER 101 /2012 Environmental Issues on  There are no fitted Concrete Batching Plant, sanitization pits with Garage and Rotational the liquid for washing Camp for KCC wheels of transport engaged in transporting material for road construction  Sewage and solid waste management  Oil droppings within the territory of the garage  Fuel management within the territory of rotational camp area

August 29, 2012 MOTC 23/13-1-5/1224 Contractor’s Staff and Status of health protection, dated August 29 Labour for JSC working hours, accommodation Kazakhdorstroy, KCC , and welfare facilities as per RK Labour laws

September 04, 2012 KCC-MER-114/2012 Environmental Issue on  Health safety- Concrete Batching Plant

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 58

Dohwa Consulting Engineers Co., Ltd

Date ReferenceNumber Subject Issues

and Camp site for KCC Personnel Protective Equipment  There are no cover & fence protection on the tank for draining wastewater  Fire prevention box without necessary tools

September 04, 2012 KUL-MER-033/2012 Environmental issue on  Scrap material did not Reconstruction of Depot store properly 35 for Kulager LLP  There are no fixed containers for picking and temporarily storage of the household waste  There are no batching and sanitation facilities  Workers are not provided with safety equipment, special clothes, special shoes etc.

3.5 Status of EMMP Implementation Environmental Impact Assessment (EIA) for the project was prepared and approved in May 2009. All the contractors (KCC and KDS) have submitted Environmental mitigation and monitoring plan and approved by the State Department “Zhambyl Oblast Department of Committee for Motor Roads. Environmental reports have been submitted by each contractor in every month, quarterly and semiannually. Previously, the reports were submitted for September to December in 2010, semiannual report for 2010 (second semiannual); Monthly report from January to June in 2011, July to December in 2011 and January to November in 2012 and semiannual report for 2012 (January to June- first half and July to December- second half. Semiannual environmental report for July to December 2012 on the environmental protection by each contractor is shown in Annex 3. Permission/License

As per Technical Specification, the contractor should obtained several permit/license for carry out the works. The contractors obtained necessary permission from relevant authority for setting up camps, quarry operation, concrete plants, crushing plant, and similar facilities. Annex 4 shows the details of permission so far obtained and provided to CSC.

Environmental mitigation measures adopted by the contractors as per technical specification are summarized in the following section.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 59

Dohwa Consulting Engineers Co., Ltd

3.5.1 KCC- Contract 004 Due to bad weather in winter civil construction of the project (at KCC E & C part) is going on slowly. They are scheduled to complete the tasks by June 03, 2013. General Contractor has employed expert (MitrofanovaEkaterine, Deputy Chief Engineer- in charge Environment) and appointed accredited testing laboratory for conducting environmental quality monitoring to ensure compliance with the terms of the project. Camps, Asphalt Plants, Cement Plants and Related Facilities Necessary plans were submitted to Engineer and obtained Engineer satisfaction. Activities have been undertaken following Engineer approval. Air Pollution Contractors have implemented the following actions:

 Effective water spraying during the delivery and loading of materials  Moistening of the stored materials  Storing of the reserved materials under the sheds or far away from the residential area on temporary areas  Covering of the bulk materials with clean tarpaulin with water spraying in the dry and windy weather  A Vehicle with an open body has the appropriate side and the rear side accessories for less dust formation  Prevention of the loading of bulk materials over the sides and rear sides  Prevention of the surface burning

Water Pollution

 Constructed local holding lagoon from reinforcement concrete to collect household sewage at the camp site and office; At Crushing plant, there is temporary unshielded holding lagoon to collect household sewage after washing the sand which located outside the site.  Stream sources and drains are at a great distance from the construction debris  There are agreement on the export of wastewater with the sugar factory in Merki Noise Pollution

The noise pollution is due to vehicle on road; generators, crushing plant, Batching plant etc.; Construction Equipment; Vibration from road vehicle. The concrete plant and crushing screening unit are located away from settlements. Working equipment is located far away from the community. The following measurements were taken to mitigate the problems:

 Vehicles regularly maintained and silencers checked  Speed limit enforced on project vehicles  Construction equipment maintained and silenced

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 60

Dohwa Consulting Engineers Co., Ltd

Drainage Water drainage pipes built in accordance with project. After the construction, drainage is carried out in the same existing channel. Wastes

 Household waste is removed by contract with private entrepreneur Dzhumasheva N.O.  All old tires and internal tubes will be removed on the automobile road after completion of construction works.  Development of the waste passports on used oils, accumulators, tires agreed with the Ecological department in Zhambyl Oblast.  Deliverable of the waste lamps to LLP “Energy Taraz” by contract. There are contracts for the use of used tires and oil Storage of fuels and chemicals

 The tank for the temporary storage of fuel is established at the Concrete plant with capacity of 49m3. Has received a new permission on emission №0001258 dated April 28, 2012 for cement unloading area and Concrete mixing plant including installed capacity which was 60 m3 in accordance with the project, received permission №0001458 dated November 01, 2012.  Fuel is stored in the garage area in the concrete plant in metal tanks with capacity of (49m3 and 60m3 which are installed in accordance with project  In accordance with the requirements, the refueling of transport carries out by fuel tank lorries and fuel filling column (2pieces). Top Soil The Contractor stores the top soil at designated disposal sites by excavating trenches along the boundary of the sites which will be used for re-cultivation. Currently 11 temporary sites are in operation (at chainage 358 km, 354 km, 350 km, 345 km, 340 km, 335 km, 329 km, 322 km, 320 km, 315 km , 311 km) while unsuitable material is temporarily stacked within the ROW and measures have been adopted to prevent wash off.

Quarry Site

Loam fields are located in Zhambyl oblast, Merki region which is about 3 km to the north-west direction of the village kenes. PresentlyKCC is extracting sand-gravel aggregate from the following loam fields.  Field “Asparinskyi 1” points №1-№4, area – 23,7ha  Field “Asparinskyi 2” points №1-№4, area – 20,6ha  Field “Kurozek” points №1-№3, area – 31,1ha  Field “Kuralas” points №1-№4, area – 15,2ha  Field “Ryskulovskyi” points №1-№4, area – 30,1ha

Geographical coordinates of the geological allotment center accordingly on sections:

 Field “Asparinskyi 1” – 43005'10.0" latitude 73042'30" longitude  Field “Asparinskyi 2” - 43003'48" latitude 73034'19" longitude  Field “Kurozek” - 42059'11" latitude 73027'17" longitude  Field “Kuralas” - 42058'14" latitude 73019'05" longitude  Field “Ryskulovskyi” - 42059'53.0" latitude 73015'07" longitude International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 61

Dohwa Consulting Engineers Co., Ltd

The required quarry area is 120.7 ha. The Contractor has obtained mining authorization vide contract No.- №Ю-09-1416dated 25.08.2011 for 89.6 ha area and №Ю-09-1412 dated 21.09.2011 for 31.1 ha.

Annex 5 shows the loam fields where the contractor is extracting raw materials.

By the Minute of the SK ICR №1635 dated August 18, 2011, approved reserves of raw materials in the 3 thousands m on the category C1 in the following amounts on sites: 1. Kuralas – 594,0 thousands m3 2. Asparinskyi-1 – 940,0 thousands m3 3. Asparinskyi-2 – 723,0 thousands m3 4. Ryskulovskyi – 907,0 thousands m3

By the Minute of the SK ICR №1655 dated September 15, 2011, approved reserves of raw materials in 3 3 the thousands m on the category C1 in the following amounts: Kurozek - 666,0 thousands m

Studied physical and mechanical properties of loam determine the stability of quarry walls for the period of field exploitation – 450;Field development is conducted by single bench, including “Asparinskyi №1” – 4,0m., “Asparinskyi №2” – 3,6m., “Kurozek” – 2,1m., “Kuralas” – 3,9m., “Ryskulovskyi” – 3,0m.Overburdens are presented by topsoil with average thickness 0,05m.

The Contractor has received the following exploitation license and documents of Quarry activities.

№ Name of document Issued by 1 Exploration contract of loam fields: “Asparinskyi №1”, “Asparinskyi Department of Natural Resources and №2”, “Kurozek”, “Kuralas”, “Ryskulovskyi” №527 dated June 20, Environmental Management of Zhambyl 2011. oblast 2 Geological allotment №Ю-09-2232 dated April 22, 2011. State Institution “South Kazakhstan International Department of Geology and Subsoil Use” 3 Conclusion of State environmental expertizes №3/Т-К-428 dated Department of Natural Resources and June 15, 2011. Environmental Management of Zhambyl oblast 4 Contract on subsoil use fields: “Asparinskyi №1”, “Asparinskyi Department of Natural Resources and №2”, “Kurozek”, “Kuralas”, “Ryskulovskyi” №542 dated Environmental Management of Zhambyl September 30, 2011. oblast 5 Project of industrial development of loam deposits “Asparinskyi LLP “DakeBarlau” №1”, “Asparinskyi №2”, “Kurozek”, “Kuralas”, “Ryskulovskyi” 6 Prospecting and evaluation works dated July 01, 2011 to the Committee for Geology and Subsoil of SA MD Contract №527 dated June 20, 2011Y. “Yuzhkaznedra”, LLP “Tau Oser”. 7 Mining allotment №Ю-09-1406 dated 25.08.2011. for the fields State Institution “South Kazakhstan “Asparinskyi №1”, “Asparinskyi №2”, “Kuralas”, “Ryskulovskyi”, International Department of Geology and and mining allotment №Ю-09-1412 dated 21.09.2011Y. for the Subsoil Use” field “Kurozek”. 8 Conclusion of expertize for industrial safety “Project of industrial LLP “Tau Oser”. development of loam deposits” in Merke region of Zhambyl oblast “Asparinskyi №1”, “Asparinskyi №2”, “Kurozek”, “Kuralas”, “Ryskulovskyi” 9 Sanitary and epidemiological conclusion №184 dated September DCSSEC of Ministry for Health of RK of 19, 2011. Zhambyl oblast (State authority of sanitary and epidemiological service). 10 Conclusion of State environmental expertizes №З/Т-К-829 dated Department of Natural Resources and September 21, 2011. Environmental Management of Zhambyl oblast 11 Minutes of meeting of the South Kazakhstan Department of State State Institution “South Kazakhstan Commission for reserves of mineral resources №1635 dated International Department of Geology and August 18, 2011Y., fields: “Asparinskyi №1”, “Asparinskyi №2”, Subsoil Use” “Kuralas”, “Ryskulovskyi”, №1655 dated September 15, 2011., field “Kurozek”,

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 62

Dohwa Consulting Engineers Co., Ltd

12 Permission on Environmental emissions №0000990 from Department of Natural Resources and 01.11.2011 to 31.12.2013. Environmental Management of Zhambyl oblast Source: KCC Engineering and Construction Co. Ltd., December 2012

There was no technical process of violation while visiting the quarry.The soil contamination by leaching of fuel and lubricants into the ground has not been detected as the vehicles are refueled directly from truck tankers;servicing and overall maintenance of road construction machinery is carried out procedurally.

The quarry re-cultivation plan is available. Permission on emission from the re-cultivation plan will be issued after endings of the quarry development loam, the liquidation project of soil will be ordered quarries in the future in accordance with the Government Decree of the RK No.634 dated 06.06.2011.

There-cultivation plan includestwostages of rehabilitation: technical and biological.

Technical stage re-cultivation includes the following works:

 Flattening of the pit wall at the angle wise 300  Rough grade of re-cultivation pit wall  Unloading of topsoil in the entire area of complete work on pit and its planning  Rolling surface on the pneumatic roller.

During re-cultivation works, bulldozer T-170 or analogous of China manufacture would be used.

Biological stage

Requirements to the land recultivation in the agriculture area should include:

- Formation areas of disturbed lands, suitable for use in relief, sizes and form, the surface layer which is compounded of soil that are to be used for biological re-cultivation. - Use of potentially topsoil with conduction of agrotechnical measures in absence or lacking of topsoil. - Repair works of re-cultivation areas; - The conduction of intensive ameliorative effects with growing of an annual, perennial of grasses and legumes cultures remediation and formation of root zone and its organic matter enrichment on application of special agrochemical, agricultural, agroforestry, engineering and anti-erosion measures; - Procurement of the agrochemical and sanitary-epidemiological services conclusion about the absence of danger removal plants, toxic to humans and animals.

Requirements to the land re-cultivation at the sanitary-hygienic area should include:

- Coordination of all activities on technical and biological re-cultivation in preservation of disturbed lands with the sanitary-epidemiological service; - The use of binder materials (fertilization) for fixation the surface of disturbed lands, which are not negative effect on the environment and have enough water stability and the stability of variation in temperature. - The application of screening layer of earth from potentially soil on the surface of compounded industrial waste dumps are unsuitable for biological re-cultivation substrate. - Executionofameliorativeworks; International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 63

Dohwa Consulting Engineers Co., Ltd

- Fixation of industrial waste dumps by technical, biological and chemical methods.

Three component mixture from grasses cultures (wheat grass) and legumes (Hungarian sainfoin) help forward fully sward the surface of recultivation site. Seeding rate of components in the grass mixture is wheat grass -30%, cropper -30%, hungariansainfoin -40%.

Liming or gypsum of soil conducts in a small areas in pH<6. Preparation of the area to the sowing is reduced to careful tillage. After planning of disturbed land at sites is conduct, as necessity, harrowing, disking, grubbing, soil compaction and sowing. Before pre-seeding treatment fertilize in the following doses: organic 20 – 30 t/hа, mineral 50 – 60kg/hа (nitrogen, phosphorus, potassium).

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 64

Dohwa Consulting Engineers Co., Ltd

Traffic and Occupational Safety

As per EMMP, the following measures has been taken by KCC

 Safety gears like helmets, safety boots jackets are in use.  Complied in the form of safety ribbons and hoardings signs.  Strict adherence to local traffic laws.

According to the field visit by the local Environmental Specialist, a violation was observed on using personal protective equipment (PPE) by the workers during working time. A letter was issued to KCC on September 04, 2012 by DOHWA to provide sufficient PPE to the workers and ensure using of these at work station. No further complaints have so far been received in this issue. According to the KCC, HIV/AIDS awareness program and regular health checkup of the workers and employees have been continuing.

 The KCC E & C confirmed by their letter no. 158/2012 dated September 10, 2012 that they are following general condition of the contract (GCC) clauses 6.4, 6.5, 6.6, 6.7, 6.12 & 6.14. In their letter they mentioned that the KCC complies with all the requirements of Labor Laws of the RK and laws of labor safety, health protection, etc. All of the staff members attended the medical inspection; employees are provided all of their rights such as right to rest, sick pay, vacation payments, providing special clothing, etc. The employees working in harmful conditions are provided with special food and dump truck drivers are provided lunch.  KCC also mentioned that they are complying with the norms of Kazakhstan regarding working hours of the employees. The employees are provided by accommodation and welfare facilities. The employees and workers are provided individual protection and safety measures. Foreign staff members are provided with visas and labor permits. Thestaffmembersareprovidedpotabledrinkingwater.

3.5.2 Kazakhdorstroy - Contract 005 The Kazakhdorstroy LLP has completed their civil works about 4 months ahead of the schedule (scheduled date was April 18, 2013) and planning to handover the site to the MOTC by December 2012. They have been dismantling structures and other establishments.Kazakhdorstroy has attended to compliance all environmental works before handed over their works to MOTC.

General Contractor has employed expert (ImanbayevaDinara, Environmental Engineer) to conduct environmental mitigation measures as per technical specification. They conducted environmental quality monitoring as per schedule through appointing accredited testing laboratory.

Camps, Asphalt Plants, Cement Plants and Related Facilities The Camp and production section arranged km 368 motor way Almaty- Taraz. Necessary plan for Sitting of housing facilities, labor camp, storage of equipment & vehicles, asphalt plants and similar facilities was submitted to the Engineer during September –October 2011 and oral approval was obtained by the

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 65

Dohwa Consulting Engineers Co., Ltd

Engineer. Figure 3.1 and 3.2 shows the layout plan of Camp and Water Supply and Canalization Plan. General data of the camp are presented in Annex 6. Camp closure plans are developed for dismantling and disposal of debris to the designated sites. The closure plan was submitted to the Engineer for their approval. Air Pollution

Contractors implemented the following actions:  Periodic water sprays on road surfaces/quarries  Covering stock piled materials  Vehicles regularly maintained  Equipment regularly maintained  Vehicles speeding checked by posting signs on roads, and awareness raising of staff and local communities  Prevention of the surface burning

Water Pollution All activities were designed during the execution of works preventing any adverse impact on water sources. These activities were included in EMMP.

Noise

Crushing plant, mortar concrete plant, soil-mixing plant conforms to the requirements of international standards. Noise reduction in crushing and screening plant was not performed. Noise level in working area within Crushing and Screening Plants compiled 85-90 dB(А). Workers used personal protection equipment (earplug) for acoustic protection. On border of a sanitary-protective zone the noise level was not exceed the installed sanitary-hygienic norms.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 66

Dohwa Consulting Engineers Co., Ltd

Figure 3.1: Layout Plan of Camp - KDS

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 67

Dohwa Consulting Engineers Co., Ltd

Figure 3.2: Water Supply and Canalization Plan

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 68

Dohwa Consulting Engineers Co., Ltd

Drainage

Drainage system from the carriage way realizes by means of longitudinal and transverse slopes. Discharge of water was carried out in ditch adjacent to the road which serves the evaporating basin thus pollutants accumulate within the reserve- technological band of the roadside area. Contractor was not discharged wastewater directly to surface waters.

Wastes

Wastes were not discharged. Household wastes generated from the activity of ZB of "Kazakhdorstroy" LLP are located on SDW landfill belonging to Oital rural district any domestic wastes were taken out with a special transport in special designated areas which is located on SDW landfill belonging to Oital rural district. Wastewaters were transported to wastewater treatment plants of Merke Branch “Central Asian Sugar Corporation” LLP (see Annex 7).

All old tires and internal tubes were removed from the sites and were done in accordance with land areas rehabilitation design. Handed over certificate of waste tiers are shown in Annex 8.

Storage of fuels and chemicals

Road-construction machineries are filled with special transport- petrol tanker. The storage of oil mineral is implemented at the petrol station territory of IE(Individual Entrepreneur) Nurseitov upon the Agreement (No. dated 01.01.2011).

Filling of vehicles was executed in accordance with safety and environmental requirements. In case of fuel spillage removal of polluted soil was conducted. For fire safety every fuel truck was provided with fire extinguishers.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 69

Dohwa Consulting Engineers Co., Ltd

Top Soil Topsoil was stored on specially designated sites before its use for re-cultivation of areas within construction site area, slopes and road shoulders protection, quarries etc.

Quarry Site

Administratively, the area of the mining lease is located on the territory of Merke region in Zhambyl oblast of the Republic of Kazakhstan in 3 km south-east from Merke village. Geographicalcoordinatesofthe "Landlot № 3" - 4205243 N., 4205243 W.

The depth of prospecting shaft and penetrated thickness of mineral resource makes 3,8м. to 4,8 м. Geological structure of the deposit with thickness from 4,0 м. to 5,0 м is studied. Thickness is up to 2,5м. The resources of loam (as of 01.07.2011) of C1 category in the volume of 658,4thous. м3 (record № 1631 dated 18.04.2011) were approved in the process of prospecting works on the deposit "Land lot № 3).

Development of site was conducted within the contours of mining allotment issued by MD "Yuzhkakaznedra №Ю-09-1407 dated 25.08 2011 on the territory of 13,7 ha.

Mining of loam in the volume of 266,0тыс. м3 was made for the contract period. Destructed territory - 39424 м2.

After the opencast mining in the quarry "Land lot 3", 266.0 thousand m3 were mined. Non- commercialreservesareabsent.

Studied physical and mechanical properties of rocks determine the stability of quarry walls with general angle of reclamation at the end of the development - 450;

- Mining of loam was conducted by single bench, height - up to 5,0 m; - Overburdens from all sites are presented by top soil later with average thickness 0.01 м; - TSL stripped from the sites has been stockpiled piles along the perimeter of the quarry, total volume - 5,913 thous. м3.

ZB of "Kazakhdorstroy" LLP obtained all legal documents for performance of prospecting, exploratory and mining works:

№ i/o Name of document Issued by 1 Agreement №525 dated 20.06.2011 for prospecting of Department of Natural Resources and loam on deposit "Land lot № 3" Environmental Management of Zhambyl oblast 2 Mining allotment № Ю-09-2230 dated April 21, 2011 State institution "South-Kazakhstan Interregional Department of Geology and Subsoil Use 3 Conclusion of state environmental expertise №З/Т-Ж-392 Department of Natural Resources and dated 09.06.2011 Environmental Management of Zhambyl oblast 4 Contract №541 dated September 30, 2011 for mining of Department of Natural Resources and loam on the deposit "Land lot № 3" Environmental Management of Zhambyl oblast 5 Project of industrial development of loam deposit on «DakeBarlau» LLP "Land lot № 3" in Merke rayon of Zhambyl oblast 6 Report on the results of prospecting and evaluation works Committee for Geology and Subsoil of SA MD at the deposit of loam "Land lot-3" with estimating of "Yuzhkaznedra", «Tau Oser» LLP reserves as of 01.07.2011 under the Contract reg. № 525

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 70

Dohwa Consulting Engineers Co., Ltd

dated 20.06.2011 7 Mining allotment №Ю-09-1407 dated August 25, 2011 State institution "South-Kazakhstan Interregional Department of Geology and Subsoil Use 8 Conclusion of expertise for industrial safety "Project for «Тau Oser» LLP industrial development of deposit-loam "Land lot № 3" 9 Sanitary and epidemiological conclusion №181 dated DCSSEC of Ministry for Health of RoK of September 13, 2011 Zhambyl oblast (State authority of sanitary and epidemiological service) 10 Conclusion of state environmental expertise №З/Т-С-807 Department of Natural Resources and dated 17.09.2011 Environmental Management 11 Minutes of meeting № 1631 of South Kazakhstan State institution "South-Kazakhstan department of State commission for reserves of mineral Interregional Department of Geology and resources dated 18.08.2011 Subsoil Use 12 Permission on environmental emissions № 0000988 from Department of Natural Resources and 01.11.2011 to 31.12.2012 Environmental Management

Source: KDS, December 2012

Re-cultivation of quarries has been done in accordance with the approval of Engineers. According to "Technical Specifications" clause 104, all works related to acquisition, rental payment for temporary land use, execution of authorization documents and agreements for work performance are entrusted to Contractor. KDS got handed over certificate and work acceptance certificate from relevant authority (see Annex 9). Mechanical and biological rehabilitation of temporary occupied land lots has been conducted without violations of normative, legal norms and handed over to the original land owners.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 71

Dohwa Consulting Engineers Co., Ltd

Protection of Flora and Fauna

A slight negative effect directly from the reconstruction on wildlife and plant life is possible only during the construction of random ramps of construction equipment outside the construction site.

All activities for reconstruction were conducted only within limits of the existing motor road and can't negatively affect on flora and fauna. Victims of moving vehicles on the road often become there presentatives of rodent, reptile, insect-eaters inhabiting in easement area.

Reflective metal fences were provided by project which acts as a device to scare the animals off the road. At night time when the car headlights hit the light barrier they reflect the bright frightening rays in the transverse direction from the road.

Reclamation project is provided for revegetation of disturbed lands, as well as pre-fertilization of land in order to increase the biological capacity of land after disturbance. In the case of the death of the grass stand the project provides for repeated cycle of works onsite preparation. A list and quantity of works on creating of the grass stand and care of them during the reclamation period (3 years) was submitted in the reclamation project.

The tree cutting was done in accordance with the procedures after getting the permission and relevant acts are drawn up. Felling License № 012269 dated 01.07.2010 - issued by Zhambyl oblast Department of Committee for roads was obtained for vegetation clearance (Annex10)

During construction period, total amount of KZT 18,14,881 (Tengi) was paid as compensation for various vegetation clearance. The following table shows the necessary calculation for compensation.

Table 3.3: Calculation of compensation for vegetation clearing in connection with reconstruction of "Taraz-Korday" motor road in Merke region of Zhambyl oblast (km 379-360,8)

species Quantity Diameter, Height, Volume, Rate VAT Compensation m. m. m3 KZT Elm 3231 0,16 5 324,651 0,42 1413 192667 (Ulmuscampestris) 1798 0,24 6 487,790 0,42 1413 289484 1070 0,32 7 602,076 0,6 1413 510440 431 0,32 8 277,164 0,6 1413 234980 Bush 54800 0,06 1 154,865 0,19 1413 41557 Total 61330 1846,546 1269148 with coefficients for 1,3 1649892 removal for relief 1,1 1814881 Total 1814881 Source: KDS, December 2012

Occupational, Health and Safety Issues Occupational health & safety is an integral part of the health management system. It is concerned with the interrelationship between work and health safety of contractor’s capacity to work.Further pursuant to the clause 6.4 of the GCC, “The Contractor shall comply with the relevant laws applicable to the Contractor’s

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 72

Dohwa Consulting Engineers Co., Ltd

Personnel, including Laws relating to their employment, health, safety, welfare, immigration and emigration and shall allow them all their legal rights”.

Medical station has been established since 2010 for rendering first medical aid on the territory of construction camp, where the permanent/shift work of two medical workers was organized.

Activities for daily morning and evening pre-trip medical examination with alcohol detecting device and tonometer for the employees: drivers, fitters, repairmen were carried out. The measures aimed on prevention of HIV infection in Zhambyl branch were performed on 22.02.2012 in ZB of "Kazahdorstroy" LLP in cooperation with the staff of the Regional Centre for the Prevention and Control of AIDS. At the end of the event the handout material was issued in 150 copies and booklets devoted to the given theme of 150 copies respectively, the condoms were given for all comers in amount of 500 pieces.

ZB of "KazakhDorStroy" LLP signed a contract with the "Central District Hospital of Merke rayon" of Department for health of Zhambyl oblast for a periodic medical examination and survey of workers engaged in heavy works or work under harmful (particularly harmful) and (or) hazardous working conditions. All employees underwent periodic medical examination. The Contract with "Nauryzbai" LLP for for the supply and provision of medicines for the company employees.

All facilities were provided with universal medicine kits and transport vehicles with car kits.All requirement of labor legislation were observed during conclusion of labor contract with the employees.

The employees engaged in heavy works, and worked in hazardous and dangerous conditions were provided with additional leaves and special food (kefir). Canteens where the employees were provided with three meals daily and during night shift were organized: 3 points of public catering in the form of cafe, where all the employees had sanitary books. There are conclusions from DSSEC of Merke rayon of water analysis for disinfection and disinfestation. Control for food quality with observation by the medical workers was conducted.

Also the workers were provided with special clothes for summer and winter periods respectively.

ZB of "Kazakhdorstroy" LLP concluded the agreement of compulsory social insurance for personal injury to life and health of the employee when performing of job duties. Agreement has been made with the branch of "Oil Insurance Company" JSC on September 24, 2011. (Annex 11)

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 73

Dohwa Consulting Engineers Co., Ltd

Accidents There were no accidents observed in this reporting period (July-December, 2012) in both the work packages though there were 4 accidents reported in May-June 2012 that causes deaths and injuries of the drivers and local people.

Social Impacts Owners of the lands acquired for the construction of the highway have been duly compensated. However people living in the close proximity to the ROW get affected due to various construction activities.

Pubic complaints received are directed to contractor for necessary remedial actions. Status of public complaints is periodically discussed through Public Complaints Resolving Monitoring (PCRM) meetings held at CSC’s’s Office, once a month. Representatives from MOTC, PMC, Engineer, and Contractor Participate in the above meeting. Apart from this, regular Joint field Investigation Visits are also conducted for nightly, to investigate the status of complaints. Further representatives of engineer and contractor participate in Grievances Redress Committee (GRC), meetings convened by local Akim.

About 14 grievances have been received from the local people/community during the reporting report (as of December 25, 2012). The status of environmental related complaints is listed below. All other complaints have stated in the social monitoring report.

Table 3.4:Status of the grievance under Environmental Issue (Km 331- 389)

Date of receiving Approxi Description of Status Nameofco Contactinf No the mate complaints (What actions have mplainant ormation complain Location (Problematic issues) been taken) ts 1 30 Zhanatur UsenovaGul 8 705 24 A toilet constructed very A letter was written to the Novemb mys zatZhazhorb 1 04 28 close to her café (AkJol), Contractor to conduct er, 2012 ayevna (mob) (15 meters) but according survey. Contractor on 22 5 29 24 to Sanitary Norms of RK December infomred (home) the distance between DOHWA by letter No. 543 projected toilet and café that the distance in should be at least 50 between Café and toilet is meters, so she asks to shift 10 meter. This this toilet to another place. corresponds the norms of Kazakhstan. The issue is to be finalized after decision of the RD. 2 29 UsenovaGul 8 705 24 She needs ramp to her Same person as sl. No. 1. Novemb zatZhazhorb 1 04 28 café (AkJol). The contractor er, 2012 ayevna (mob) constructed toilet without 5 29 24 keeping pedestrian way to (home) Cafe. Decision to be required from the Employer. 3 19 Aktogan AlimbayevK Kunanba 1) To date walls of 1) According to our Novemb v. yrgyzbai yev St., his house have big investigation the house er, 2012 1, cracks because of the is not affected by the Aktogan equipment of Project because it is village Kazakhdorstroy passing located 60 meters away 3-54-14 their street. from the constructed (home) 2) He suffers in road and house is spring and autumn classified as an old because of the very big house that is the reason water flow from for cracks. Anyhow as a mountains. Before there help Contractor (KDS

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 74

Dohwa Consulting Engineers Co., Ltd

Date of receiving Approxi Description of Status Nameofco Contactinf No the mate complaints (What actions have mplainant ormation complain Location (Problematic issues) been taken) ts was a little culvert and LLP) provided this they diverted the flow of complainant with two the water to fields. Now bags of cement for due to construction of the repairing of the cracks. road this culvert was 2) KDS LLP removed and nothing is surveyors made a survey there instead of this of that section and culvert. submitted the survey results to DOHWA. It`s possible to construct there a drainage/channel for water flow but because of the Beeline cable passing there it can be constructed only if it will cross the private land. (Land plot of neighbors located opposite to the house of complainant). The claimer was asked to make an agreement with land owners about this. .

There were no complaints and social problems received from depot contractors (Aksioma and Kulagar) as of December 2012.

Public Relations KCC and KDS have held a series of information sessions for local communities to keep them informedabout construction progress and upcoming activities.

Construction works are located in rural areas that have limited access to electronic media suchas the internet. Local communities are informed at meetings with KCC and KDS staff and by localauthorities (village akimats) who are briefed directly by Contractor’s management. In addition, thecontractors have produced a series of posters, public notification and provided information tolocal newspaper for distribution to local communities before commencement of construction works. .

Rehabilitation of Lands

The complex of technological processes connecting with arrangement of earth bed brings the most harmful effect on environment. First of all soil contamination usually is observed on temporary occupied sites for quarry, construction sites, reconstructing motor road. Soil contamination occurs mostly by fallout of finely dispersed, solid, pulverous particles from the atmosphere on surface brought by the wheels of cars from the roads and driveways with the unimproved pavement because of partial loss of transported bulk materials, products of tires and coatings abrasion and toxic components of exhaust gases from automobiles.

Soil erosion as a result of the reconstruction of the road in the roadside is of low-probability, because the main operations were carried on the existing road with protection work in the drainage system. Some soil

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 75

Dohwa Consulting Engineers Co., Ltd erosion may occur in areas of construction,material mining, but this erosion has limited area time, and low-impact because the sites are located lands which have low value for agricultural purposes. The most important stage of capital repair of the motor road section is rehabilitation of lands destructed in the process of road construction work performance. Project for rehabilitation of lands was developed in accordance with the requirements of current legal documents of RoK: 1) guidance on the development of projects for reclamation of disturbed lands in Kazakhstan GosNPTszem, 1993, and 2) general requirements for land reclamation, GOST 17.5.3.04-83 3) "Instruction on the development of projects for rehabilitation", Astana, 2009 4) the decree of the Government of the Republic of Kazakhstan dated October 8, 2003 № 1037 "on approval of standards for compensation of losses of agricultural and forestry lands, caused by the withdrawal of agricultural and forest land as to be used for purposes not related to agriculture and forestry", 5) rules for compensation of losses concerning agricultural production with setting off the sums spent on land's rehabilitation.

Rehabilitationoflandstemporaryoccupiedforoverhaulrepair of the motor road was performed for the following objects:

- rehabilitation of temporary occupied lands for construction site of the Contractor; - rehabilitation of other temporary sites for various purposes; - reclamation of temporary access roads to the objects of construction; - rehabilitation of lands earlier (before flattening) occupied by existing motor road.

Complex of works for rehabilitation of lands destructed in the process of overhaul repair of the motor road consists of 2 stages: the first stage – technical rehabilitation including activities for stripping and storage of top soil, vertical leveling of land surface after development, flattening of slopes, return of top soil layer on designed surface, treatment of soil surface by blade cultivator; the second stage – biological rehabilitation including activities for fertility restoration of disturbed lands after the first stage, pre-planting cultivation of soil, planting of perennial grasses and post-seeding rolling.

Table 3.5: Work performance for rehabilitation of temporary occupied land lots involved during the construction of the motor road "Almaty-Korday-Blagoveshenka-Merke- Tashkent-Termez" km 358,6-389,4 on the territory of Merke rayon in Zhambyl oblast

Target Cleani Levelli Levllin Name of Cadastral Area of Method of № purpose ng ng g of land lot № lands(ha) rehabilitation TSL km 358,6-km 389,4 (for stockpiling of Land lot №1 TSL, RCM 06-092- Technical, 1 км 372+600 3,01 and access 100% 100% 100% 092-015 Biological right 60 м. road maintenance )

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 76

Dohwa Consulting Engineers Co., Ltd

(for stockpiling of Land lot №2 TSL, RCM 06-092- Technical, 2 км 362 right 3,01 and access 100% 100% 100% 017-092 Biological 170 м. road maintenance ) (for stockpiling of Land lot №3 TSL, RCM 06-092- Technical, 3 км 369+600 3,1 and access 100% 100% 100% 022-295 Biological left 60 м. road maintenance ) (for stockpiling of Land lot №4 TSL, RCM 06-092- Technical, 4 км364 left 30 3,006 and access 100% 100% 100% 022-296 Biological м. road maintenance ) (for stockpiling of Land lot №1 TSL, RCM 06-091- Technical, 5 км353+300 3,01 and access 100% 100% 100% 088-319 Biological right 25 м. road maintenance ) (for stockpiling of Land lot №2 TSL, RCM 06-091- 6 км 377+800 3 and access technical 100% 100% 100% 093-550 left 50 м. road maintenance ) Area of land acquisition for mining of loam on 06-092- Technical, 7 Land lot №3 13,97 deposit 100% 100% 100% 020-116 Biological "Land lot № 3" and access road maintenance Source: KDS, December 2012 Works on rehabilitation of lands which was occupied for road construction (section km 358.6- 389.4) were executed by KDS LLP in compliance with normative, legislative norms and rules. The commission considers that rehabilitated lands are suitable for subsequent agricultural use in the context of the previous lands. (See Annex 12).

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 77

Dohwa Consulting Engineers Co., Ltd

4. CONCLUSION The second biannual environmental monitoring report of 2012 relates to the progress of implementation of the EMMP during the last six months (July to December) of 2012 in respect of various work components of Contracts (contract 004 and 005) and Depot contractors (Contract No. NCB 1, NCB 2, NCB 3 abd NCB 4(under Tranche 2 (Zhambyl Oblast Section). This report is being developed by Environmental Specialist of CSC based on the feedback from and inconsultation with Supervision Engineers, review of pertinent environmental documents (EIA and EMP of the project, EMMP report prepared by the contractors, required permit and licenses); site visits,incorporating the results of the required sampling, laboratory analysis and measurements. Physical work in km 358-389 (Kazakhdorstroy LLP) has been finished about 4 months ahead of the schedule and the site has been handed over to the MOTC in December, 2012. Physical works in km 310- 358 (KCC E & C) is scheduled to be completed by June 2013.

During the reporting period from July to December 2012, the contractor of KCC E & C (contract No. 004) has conducted monitoring of ambient air, noise and water samples. The monitoring results of all the parameters are within the standard of Republic of Kazakhstan.

Kazakhdorstroy (KDS) has performed environmental quality (air, water, noise) monitoring works as per their schedule. Indicators of air tests for the second half of the year did not exceed the maximum permissible concentrations. Indicators of natural water test in Koltogan River did not exceed the maximum permissible concentrations. Monitoring of water in Big Chu Channel was conducted only in November, because there was no water in the river during the previous months. Indicators of noise and vibration tests did not exceed permissible values , since the bulk of the work was performed away from settlements.

The status of various activities undertaken by the Contractors right from the Contract signing to setting up site offices and construction camps, mobilization of equipment and manpower site clearing, cut and fill activities, earth works, operation of quarries, movement of vehicles and construction materials were provided in the EMMP matrix and as per Technical Specification.

The quarry operation is being undertaken by the contractor within the purview of the rules and regulations in Force and according to Environmental management plan developed by them. All the Contractors (KCC and KDS) have obtained the necessary approvals and licenses from the relevant Authorities for quarry operations and subsequent operations are to be in accordance with the requirements of these Authorities.

Sitting and operation of Cement and Concrete Batching Plants have been undertaken in accordance with all current rules and regulations for protection of environment.

Both of the campsites were observed pollution of household wastes. There is rubbish and debris scattered at camp territory, the toilets are usually dirty with trash; drains are filled up with garbage and ultimately clog to flow the waste water. The CSC has requested to the Contractor to often implement housekeeping work to keep these areas in cleanliness and sanitary condition.

Both Contractors took reasonable precautions to maintain the health and safety of the Contractor’sPersonnel and to provide a safe work environment.

At the direction of the Engineer, both the Contractors provided dust suppression measures, watering of the works and roads, and other areas immediately adjacent to the Construction Works.

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 78

Dohwa Consulting Engineers Co., Ltd

Both Contractors prepared necessary plan and executed the work so as to minimize the possibility of pollution of areas adjoining the construction work sites or any area utilized by the Contractors for the project, from contaminants such as petroleum products, trade waste, garbage and other noxious substances.

The tree cutting is carried out in accordance with the procedures after getting the permission and relevant acts are drawn up.

Works on rehabilitation of lands which was occupied for road construction were executed by KDS LLP in compliance with normative, legislative norms and rules. KCC will be conducted land rehabilitation process through technical and biological process after completion of all construction works.

Environmental report of all 4 depot contractors was submitted. The reports and inspections indicated that depot contractors are being trying to implement the requirements of the EMMP. They did not conduct monthly monitoring of air, water and noise and vibration on the construction site.

During the reporting period, some non-compliances issues were identified and they have been instructed to measure corrective action as per technical specification.

Decision was made that the contractors shall respond to the issues, while the domestic environmentalist shall actively monitor the compliance and report them to the International Environmental Specialist. It is important that the domestic environmentalist should follow through with the Contractor on the items that were not yet acted upon, as well as those in progress. A consistent follow through inspection is necessary in order to improve the environmental performance of the project to the satisfaction of the MOTC (Employer) and ADB (Financier).

International Transport Corridor CAREC 1, Taraz-Korday in Zhambyl oblast (Project Two) Loan 2562-Kaz Bi-Annual Environmental Monitoring Report Page 79

ANNEX 1

Environmental Monitoring Plan during Construction

ANNEX I-Environmental Monitoring Plan during Construction 1

Mitigation Measures Parameters to be monitored Schedule of Executing Unit Reporting Frequency Responsibility

1Kazakhstan: MultitrancheFinanciang Facility for the CAREC Transport Corridor 1 (Zhambyl Oblast Section) Investment Program – Tranche 2, EIA Report. May 2009

ANNEX 2

Methods for conducting environmental quality parameters

ANNEX -2

Methods for conducting environmental quality parameters

Air of sanitary protection zone № i/o Showings Method of conducting Measuring means

1 Suspended particles of dust GOST 17.2.6.02-85 Gas analyzer GANK -4 2 Nitrogen dioxide GOST17.2.6.02-85 Gas analyzer GANK -4 3 Sulfur dioxide GOST17.2.6.02-85 Gas analyzer GANK -4 4 Carbon monoxide GOST17.2.6.02-85 Gas analyzer GANK -4 5 Aldegidy GOST17.2.6.02-85 Gas analyzer GANK -4 Physical characteristics 6 Noise GOST12.1.050-86 Noise and vibration analyzer GOST23337-78 «Assistant» 7 Vibration Government Order of Noise and vibration analyzer Ministry of health «Assistant» 3.12.2004 № 841 Natural, drinking and waste water 9 pHvalue Tech. regulation рН – 150 М № 456 of 13.05.2008 10 Potassium PND F 14.1:0:4.167-2000 Capillary electrophoresis system «Kapel-104 Т» 11 Sodium PND F14.1:0:4.167-2000 Capillary electrophoresis system «Kapel-104 Т» 12 Calcium PND F14.1:0:4.167-2000 Capillary electrophoresis system «Kapel-104 Т» 13 Magnesium PND F 14.1:0:4.167-2000 Capillary electrophoresis system «Kapel-104 Т» 14 Lead М 01-02-2010 Liquid analyzer «Fluorat-02-3М» 15 Zink PND F14:1:2:4.183-02 Liquid analyzer «Fluorat-02-3М» 17 Manganese PND F14.1:2:4.188-02 Liquid analyzer «Fluorat-02-3М» 18 Phosphate PND F14.1:2:4.157-99 Capillary electrophoresis system «Kapel-104 Т» 19 Chlorides PND F14.1:2:4.157-99 Capillary electrophoresis system «Kapel-104 Т» 20 Sulfates PND F14.1:2:4.157-99 Capillary electrophoresis system «Kapel-104 Т» 21 Ammonium nitrogen PND F14.1:0:4.167-2000 Capillary electrophoresis system «Kapel-104 Т» 22 Nitrates PND F14.1:2:4.157-99 Capillary electrophoresis system «Kapel-104 Т» 23 Fluorides PND F14.1:2:4.157-99 Capillary electrophoresis system «Kapel-104 Т» 24 Mineral oils PND F14.1:2:4.128-98 Liquid analyzer «Fluorat-02-3М» 25 Suspended substances GOST 26449.1-85 Gravimetric method 26 Chemical oxygen demand PND F14.1:2:4.190-03 Liquid analyzer «Fluorat-02-3М» 27 Biochemical oxygen demand RD 52.24.420-2006 light-and-dark-bottle method

28 Iron PND F14.1:2:4.29-95 Liquid analyzer «Fluorat-02-3М» 29 sodium dodecyl sulfate PND F14.1:2.158-2000 Liquid analyzer «Fluorat-02-3М» 30 Nitrites PND F14.1:2:4.157-99 Capillary electrophoresis system «Kapel-104 Т»

ANNEX 3

Bi-annual Monitoring Report of Contractors

КСС E&C and «Kazakhdorstroy» LLP

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

ANNEX 3-1

Half-year Monitoring Report

(Period July 1, 2012Y. – December 31, 2012Y.)

CAREC Investment Project Two (Trance 2) – Zhambyl Oblast Section

Contract №004 АDВ/CWI

Reporter Name: Mitrofanova E.V.

Contractor Name: KCC «Engineering and Construction Co., Ltd.» in Zhambyl oblast Date: December II half-year period 2012Y. Half-year report.

Month: December (Half-year monitoring report) Year: II half-year period 2012Y. Signature:

Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No General 1. Contractor shall provide environmental 1.1 Plan submitted V Monitoring Plan submitted. There are Programs of industrial mitigation and monitoring plan (EMMP) in ecological control the permission for emission from the road connection with the submission of the construction till July 01, 2013Y. by the concrete batching Program based in the Technical plant and cement-receiving area, by the work of the Specifications crushing-screening plant and from the work of quarries. Instrumental laboratory measurements were carried out in December 14, 2012Y.: to air on the borders of Sanitary protection zones in 5 places at 11 control points on 5 components; - to natural water in 1 place at 1 control point on 22 components; chemical water test from the well of

Half year Environmental Management and Monitoring Plan Report Final Page 1

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

Concrete plant. 2. Contractor shall nominate senior staff 2.1 Appointed person V 16.02.2012Y. Ecologist fired in accordance with retirement. person to be responsible for follow-up of The duties of ecologist performs to deputy chief engineer implementation of EMMP and guidance of Mitrofanova E.V. the Contractor staff and reporting to Engineer 2.2 Briefing held with the V According the written instructions, by order responsible subcontractors subcontractors appointed the responsible on environment. 2.3 Reports have prepared for V December 2012Y. is according to the half-yearly report. Engineer 3. EMMP shall be provided as a part of the 3.1 EMMP provided with method V EMMP is the part of the construction of the road section. method statement statement Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Siting of Camps, Concrete-batching Plants, cement Plants and Related Facilities

4. Inspection of construction sites and 4.1 Plans are submitted to V Received: Ecological conclusion to the section of the EIA environmental restoration of facilities for Engineer (Environmental Impact assessment) sites for storage of housing of construction staff, storage of cement and concrete batching unit under No.Z/T-K-49 dated equipment & vehicles, labour camps, April 19, 2011Y. Received new permission on emission into 4.2 Received the approval of the concrete plants, crushing screening plant the environment on site for storage of cement and concrete and similar facilities must be planned to the Engineer batching unit under №0001258 dated 28.04.2012Y. in satisfaction of the Engineer. connection with the installation of tanks for temporary storage of diesel fuel. Received permission for special water use №Shu-T/170 T/R dated 01.07.2011Y. to use water well. Received: Ecological conclusion on the project OVOS of work on crushing - screening plant Z/T – K-589 dated 21.07.2011Y., - Permission on the emission in the Environment at Crushing Screening Plant №0000913 dated 01.09.2011Y., Environmental report and permission for the emission of quarry work No.0000990 dated November 01, 2011Y. The project EIA recultivation of quarries has developed. Developed working project EIA for the II construction stage of the concrete plant and for the installation of II capacity for the temporary storage of fuel. Half year Environmental Management and Monitoring Plan Report Final Page 2

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

Received sanitary conclusion on EIA project and working project of II construction stage of the Concrete plant No.124 dated 09.08.2012Y. Received: Ecological conclusion No.ZT-N-722 dated 02.09.2012Y. to the EIA project of II construction stage of the Concrete plant. The application handed over to Nature and natural resources in October 10, 2012Y. for receiving the permission on emission. Received permission on emission of II construction stage of the Concrete plant No.0001458 dated 01.11.2012Y. Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Air Quality Monitoring 5. EMMP shall specify proposed pre- 5.1 Pre-construction AQ V Air quality monitoring before the performance of work for construction monitoring to verify baseline monitoring included in the construction of roads conducted in September 2010Y., conditions as advised by Engineer EMMP on the concrete plant in November 06, 2011Y., storage of cement 13.07.2011Y. and crushing screening plant in April 06, 2011Y. 5.2 Recommendation from an V There were no recommendations. Engineer 6. Pre-construction TSP monitoring at not less 6.1 Monitoring points identified V Check items are defined and available on the scheme. than 2 points depending on proposed location of pollution sources 7. EMMP shall specify locations and 7.1 Locations of measurement in V In EMMP indicated location and frequency of monitoring frequency of routine instrumented the process of carrying out air quality. monitoring of AQ monitoring defined 8. AQ monitoring required not less than once 8.1 AQ monitoring is available V AQ Monitoring is conducted monthly. per month monthly 9. Additional event-related monitoring may be 9.1 An additional monitoring is V Engineer required carrying out an additional monitoring at required by Engineer require the cement storage. Analyze of inorganic dust at the border of the Sanitary-protection zone. 10. Monitoring undertaken by third party 10.1 Received the approval of the V Monitoring is undertaking by accredit testing laboratory in

Half year Environmental Management and Monitoring Plan Report Final Page 3

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

organisations acceptable to Engineer Engineer branch Zhambyl oblast, Ltd. «KESO OTAN», №KZ.I.081065 from 14.12.2010Y. 11. Following AQ provisions apply to crushing 11.1 The excess of Maximum permissible concentration in the air and screening plant, concrete mixing plant didn’t reveal on the borders of the Sanitary protection zone. a. Open burning prohibited a is executing V Responsible for Crushing and screening Unit and Concrete mixing plant given the written orders about prohibition of open burning. We are constantly control for its performance. b. Solvents & materials used to Engineer’s b the materials are use with V Testing laboratory of the branch of JSC KCC receives an satisfaction approval of the engineer approval for the use of fluids and materials . c. Blasting limited to small charges c Blasting works are not V Blasting works are not allowed. conducted d. Dust generating items conveyed under d Construction materials are V Storage areas are located far from residential areas. cover not covered in storage Construction materials are not covered in storage. e. Road surfaces, excavations & e Suppress dust by spraying V Issued written orders which are executing non completely. construction sites water sprayed for dust of water control f. Trucks carrying earth, sand or stone f Trucks covered with tarps V Issued written orders which are executing non completely. covered with tarps to avoid spilling. Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Water Quality Monitoring 12. EMMP shall include pre-construction 12.1 Pre-construction monitoring V r.Aspara and r.Kayindysay. Monitoring of water quality monitoring to verify baseline conditions at of WQ included in EMMP of these rivers is included in the plan EMMP. Monitoring is locations as advised by Engineer performed monthly. There isn’t water in the river Aspara in December. 12.2 There weren’t V There weren’t additional recommendations of the Engineer. recommendations of Engineer 13. Pre-construction WQ monitoring to include 13.1 Required parameters included V suspended solids (SS), biological oxygen in pre-construction WQ Preliminary WQ monitoring is conducted in all parameters demand (BOD) and dissolved oxygen (DO), (22 parameters). Preliminary WQ monitoring is conducted Half year Environmental Management and Monitoring Plan Report Final Page 4

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

conductivity, faecal coliforms and oil & monitoring in the r.Aspara in April 2011Y., and r.Kayindysay dated grease October 06, 2010Y. 14. Additional baseline monitoring may be 14.1 Additional baseline V required by location of major sources of monitoring undertaken Additional monitoring of natural waters didn’t carry out in potential water pollution (construction December 2012Y. Additional pollution sources of natural camps & other sources of significant run-off waters are absent. & liquid waste generation) 15. Plan shall specify procedures for routine 15.1 Procedures specified in V Monitoring of domestic waste is not conducted. Household instrumented monitoring of WQ & run-off EMMP waste is removing by contract with private entrepreneur from construction camps, parking areas Dzhumasheva N.O. (equipment and transport) and labour camps, at least 1 time per month 16. Monitoring consists of analyses: suspended 16.1 Monitoring includes required V Waste water monitoring was not carry out in December. matter SS, BOD, DO, conductivity, faecal parameters coliform, oil & grease. 17. Additional event-related monitoring may be 17.1 Additional event-related V Engineer didn’t require an additional monitoring. requested by Engineer monitoring wasn’t request by Engineer 18. Monitoring undertaken by third party 18.1 Engineer acceptance received V Monitoring is carried out by the testing laboratory Ltd. organisations acceptable to Engineer «KESO OTAN». Accreditation certificate №KZ.I.081065. Registered in the register of accreditation from 14.12.2010Y. and valid until 14.12.2015Y.

Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Noise & Vibration Monitoring 19. Pre-construction baseline monitoring of 19.1 Pre-construction monitoring V Measurements of noise and vibrations were conducted noise and vibration required at minimum of executed before the start of construction in September 2010. The 2 sites including major settlements protocol is provided in the monthly report for September 2010. from the construction of the road from Crusher plant works in September 2011Y.

Half year Environmental Management and Monitoring Plan Report Final Page 5

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

20. Additional baseline monitoring may be 20.1 An additional monitoring is V Engineer required an additional monitoring of noise and required by Engineer require vibration near the mosque at the turn of road to Crushing Screening Plant and near the school in Kyzyl-Kishlak, which carry out since June2011Y. monthly. 21. Routine instrumented required at minimum 21.1 Routine monitoring V Requires are executed, in accordance with the engineer- 2 locations including baseline monitoring undertaken ecologist DOHWA. sites 22. It is necessary to carry out Monitoring 1 22.1 Monitoring is carried out 1 V Requirements are executed. Monitoring is carried out time per month time per month monthly. 23. Additional monitoring may be required 23.1 Additional monitoring V Noise and vibration monitoring is conducted since June during pile driving and blasting and undertaken 2011Y. Measurements carried out in the v.Kyzyl-Kyshlak otherwise as requested by Engineer near the school and near the mosque at the turn of road to Crushing Screening Plant. 24. Monitoring undertaken by third party 24.1 Engineer acceptance received V Monitoring is carried out by the testing laboratory Ltd. organisations acceptable to Engineer «KESO OTAN». Accreditation certificate №KZ.I.081065. Registered in the register of accreditation from 14.12.2010Y. and valid until 14.12.2015Y. There is no excess of Maximum permissible concentration. Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Community Relations

25. EMMP shall specify proposed public 25.1 Program included in the plan V Advertisement is given to the newspaper «Magnolia» №31 information programs in advance of EMMP from August 01, 2012Y. for the project II construction stage construction, notification procedures (mass of the Concrete plant. media and signage) etc. Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Fuel and Chemical Storage

26. The basis for the storage of fuel & 26.1 Impervious bund and fencing V The tank for the temporary storage of fuel is established at chemicals must be waterproof and the the Concrete plant with capacity of 49m3. In accordance Half year Environmental Management and Monitoring Plan Report Final Page 6

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

storage must be enclosed by a fence provided with the working project, we received a new permission on emission №0001258 dated 28.04.2012Y. for cement unloading area and Concrete mixing plant including installed capacity. Capacity V-60m3 installed in accordance with the project, received permission №0001458 dated November 01, 2012Y. 27. Storage located away from watercourse and 27.1 Appropriately located V Fuel storage is provided in the garage of the Concrete plant. wetlands 28. Bund base and walls impermeable 28.1 Impermeability satisfactory V Fuel is stored in the garage area in the concrete plant in metal tanks. 29. Capacity of bunded 110% of the volume of 29.1 Pre-construction monitoring V Fuel is stored in the garage area in the concrete plant in tanks within bund undertaken metal tanks 49m3 and 60m3 which are installed in accordance with project, there is a calibration of capacity and passports. 30. Filling and refuelling strictly controlled & 30.1 Procedures developed and V In accordance with the requirements the refueling of subject to formal procedures implemented transport carries out by fuel tank lorries in accordance with requirements and fuel filling column (2pieces). 31. Valves & trigger guns shall be resistant to 31.1 Valves and trigger guns V Valves and trigger guns comply with requirements. unauthorised interference and vandalism comply with requirements. and be turned off and securely locked when not in use 32. Contents of any tank or drum shall be 32.1 Contents clearing marked V Developed the project of installation tankages for temporary clearly marked of fuel storage at the Kyzyl-Say and Kenes, developed the project of EIA (Environmental Impact Assessment). The projects of EIA have sanitary and ecological conclusion, we received permission on emission №0001258 from 28.04.2012Y. for installation of II capacity V60m3, developed working project and EIA project. Received Sanitary and ecological conclusion on the worker project and EIA project of II capacity No.124 dated 09.08.2012Y. and ZT-N-722 dated 12.09.2012Y. The application on emission is executed in October 10, 2012Y. Received permission on emission No.0001458 dated

Half year Environmental Management and Monitoring Plan Report Final Page 7

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

November 01, 2012Y.

33. Measures shall be taken to ensure that no 33.1 Measures implemented V Fuel material is refuels by petrol truck and fuel dispensers, contaminated discharges enter any drain or no fuel leakage, the fuel does not fall into the sewage waters watercourses and and water reservoirs. Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Water Quality 34. Contractor shall prevent any interference 34.1 Any unintended influence on V There is not influence on water sources and underground with supply or abstraction from supply or the sources water. pollution of water resources including 34.2 Any pollutions surface or groundwater groundwater 35. All water and other liquid waste products 35.1 All liquid & other wastes V Constructed local holding lagoon from reinforcement arising on sites shall be collected on or off collected concrete to collect household sewage at the workers town the sites and in a manner that shall not cause 35.2 Manner of collection not and office, at the Crushing screening unit has got a nuisance or pollution causing pollution temporary unshielded holding lagoon to collect household sewage after washing the sand which located outside the site. 36. Contractor shall not discharge or deposit 36.1 Requirements are in progress V There are agreements on the export of wastewater with any matter arising from execution of the the sugar factory in Merke. Works into any water except with permission of Engineer and regulatory

authority 37. Contractor shall at all times ensure that all 37.1 Stream courses and drains are V Stream sources and drains are at a great distance from the existing stream courses and drains within on site or adjacent to it are at a construction debris. and adjacent to the Site are kept free from great distance from the debris any debris and materials arising from the Works 38. Contractor shall protect all watercourses, 38.1 All waterways protected V At the concrete plant was built well, has permission on waterways, ditches, canals, drains, lakes and special water use, head well enclosed within the sanitary

Half year Environmental Management and Monitoring Plan Report Final Page 8

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

the like from pollution, silting, flooding or protection zone, pavilion has installed above the headwall. erosion as a result of the execution of the Works 39. Contractor shall submit details of his 39.1 Detailed information V Constructed local concreted holding lagoon to collect temporary drainage system (including all submitted to Engineer before household sewage at the workers town which located near surface channels, sediments traps, washing construction start the concrete plant and office where it will flow waste water basins and discharge pits) to the Engineer from showers, sanitary conveniences, and canteen. At the for approval prior to commencing work on Crushing screening unit has got a temporary unshielded its construction. holding lagoon to collect household sewage after washing the sand which located outside the site. Waste water is removed by the contract to the filtration fields of sugar factory. Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Air Quality 40. Open burning prohibited 40.1 Requirements are performed V Subcontractors received a letter about prohibition burning in the open air. 41. Contractor shall utilise effective water 41.1 Water sprays utilized V Work is carried out at a great distance from the housing sprays during delivery and handling of community, kindergartens, and hospitals. Permanently we materials when dust likely to be created and water the roads which transport the materials. to dampen stored materials during dry and windy weather 42. Stockpiles of materials shall be sited in 42.1 Material stockpiles sited in V Storage of dusty materials is at a great distance from sheltered areas or within hoarding, away remote areas from the housing community, material stockpiles are not wetted from sensitive areas. Stockpiles of friable environmentally sensitive areas till moving because they are far from environmentally material shall be covered with clean 42.2 Material stockpiles are not sensitive areas. tarpaulins, with application of sprayed water wetted till movement. during dry and windy weather. Stockpiles of material shall be dampened prior to their movement, except where this is contrary to the Specification 43. Any vehicle with an open load-carrying area 43.1 Tailgate of automotive V Requirements are observed. used for transporting potentially dust Half year Environmental Management and Monitoring Plan Report Final Page 9

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

producing material shall have properly transport provided. fitting side and tail boards 44. Materials having potential to produce dust 44.1 Loads comply with loading V Procedure is not fully observed. shall not be loaded to a level higher than the requirement side and tail boards and shall be covered 44.2 Tarpaulins secured as per with a clean tarpaulin in good condition. specification Tarpaulin shall be properly secured and extend at least 300mm over the edges of the side and tail boards 45. In periods of high wind, dust generating 45.1 Operations comply with V Works carried out at a great distance from housing operations shall not be permitted within specification community, schools and hospitals. 200m of residential areas having regards to the prevailing direction of the wind 46. Construction vehicles & machinery shall be 46.1 Vehicles & Machinery V Permanent work is conducted in this direction, explanatory kept in good working order and engines kept in good working order work, controlled by the security services and safety turned off when not in use. 46.2 Engines turned off when not engineers. in use. 47. Appropriate measures shall be taken to limit 47.1 Measures taken to limit V Measures are acceptable. exhaust emissions from construction exhaust emissions vehicles emissions from construction vehicles, machinery & plant & contractor shall include details in EMMP

48. In residential or other sensitive areas such 48.1 Details included in EMMP V Road under construction is located far away from housing as nurseries and hospitals etc, advance 48.2 Assistance with mitigation estates. warning shall be given to potentially measures provided to project affected persons, so that measures can be affected people (PAP) taken by them before commencement of works

Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No

Half year Environmental Management and Monitoring Plan Report Final Page 10

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

Noise 49. Contractor shall consider noise as an 49.1 Noise considered as V Monthly monitoring of noise is conducted at the borders of environmental constraint in the planning environmental constraint Sanitary protection zone. and execution of the Works 50. Contractor shall use plant and equipment 50.1 Plant and Equipment V Equipment for the production of concrete and stone conforming to international standards and conforms with international materials is requirement standards. directives on noise and vibration emissions standards 51. EMMP shall include details for abating 51.1 EMMP includes required V Measures are accepted. noise at source as per sub-item 4.18 of details Conditions of Contract 52. Contractor shall take all necessary measures 52.1 All necessary measures are V See point 50.1 to ensure that the operations of all accepted The dislocation concrete plant and concrete crushing - mechanical equipment and construction 52.2 Noise levels in accordance screening unit are located away from settlements. Monthly processes on and off-site shall not cause with applicable environmental measurements of noise and vibration are carried out at the unnecessary or excessive noise, taking into account applicable environmental requirements. borders of the sanitary protection zone. The exceeding of requirements. MPC is not observed in December 2012Y. 53. The Contractor shall use all necessary 53.1 All necessary measures taken V Measures are accepted, under construction route is far measures and maintain all plant and 53.2 Silencing equipment away from settlements. silencing equipment in good condition so as maintained in good condition to minimise noise during Works 54. When operating close to sensitive receptors 54.1 Construction near the V Working equipment is located far away from housing such as residential, nursery, or medical sensitive areas limited community facilities, the Contractor’s hours of working shall be limited Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Earthworks

Half year Environmental Management and Monitoring Plan Report Final Page 11

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

55. Surplus excavation of topsoil shall 55.1 Surplus excavation and V At the present time, the soil fertile topsoil stored on the wherever possible be used to reinstate topsoil will be temporarily reserved land and will be used for re-cultivation. borrow pits and quarries or other areas as used to restore quarries. The contract for the extraction of loam obtained from the may be approved by the Engineer 55.2 The quarries restored in Environmental Management №542 from 30.09.2011Y. The accordance with the approval project of reclamation quarries is developed, now developed the EIA project by contract with KESO OTAN in the of the Engineer. process of work on reclamation of soil quarries. At the present time the project EIA is undergone the sanitary and the ecological expertise, complete application for receiving of permission for emission in the process of work on recultivation of quarries is executed, the permission will be obtained after the end of loam quarry mining. 56. Such materials shall be spread in such a 56.1 These materials are V The measures are observable. manner as to limit subsequent erosion and distributed to prevent erosion shall be conducted measures for re- cultivation Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Yes Part No Preservation of Antiquities

57. Contractor shall take all necessary measures 57.1 All necessary measures taken V There are no historical structures and archaeological finds to protect any antiquities or archaeological on the reconstructed area. finds as required by item 4.24 of Conditions of Contract 58. Where antiquities are shown on the 58.1 Identified antiquities protected V There are no historic structures. drawings or otherwise identified during the course of the Works, and protected by means of suitable fencing and barriers to the satisfaction of the Engineer. 59. The Contractor shall provide and maintain 59.1 Access maintained as required V There are no monuments on the reconstructed road at the access at all times for persons wishing to site. stop and pay their respects Specification Requirement Implementation Activity Implementation Comment / Verification / Proposed Action Half year Environmental Management and Monitoring Plan Report Final Page 12

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

Yes Part No Environmental Enhancement

60. The Contractor shall remove all old tyres 60.1 All removed from within V Will be executed after completion of all construction works and internal tubes from within the Limits of Limits of site. on the automobile road. Developed the waste passports on Site, and subject to the agreement of 60.2 Landholder agreement used oils, accumulators, tires agreed with the Ecological adjacent landholders, from an additional department in Zhambyl oblast. We deliver the waste lamps area 75m either side of the road centre line obtained to LLP “Energy Taraz” by contract. There are contracts for 60.3 Tyres removed in accordance the use of used tires and oil. with landholder agreements. 61. Contractor shall dispose of all materials in a 61.1 Materials disposed of as V Will be executed after completion of all construction works manner approved by the Engineer approved by Engineer on the automobile road. 62. When directed by the Engineer, the 62.1 Directive relating to land V Will be executed after completion of all construction works. Contractor shall improve and reinstate the reinstatement received from land on which informal roadside service Engineer areas have been established by removing all debris and contaminated soils regrading to 62.2 Debris removed and land natural ground levels, and re-establishing reinstated as directed by the natural vegetation. Engineer 63. All debris and contaminated materials shall 63.1 Disposal as approved by V Will be executed after completion of all construction works. be disposed off site as approved by the Engineer Engineer. 63.2 Management of lead contaminated soil.

Prepared by:. Department Head:

Tel: Tel:

Half year Environmental Management and Monitoring Plan Report Final Page 13

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

ANNEX 3-2 CAREC Investment project 2 (Tranche 2) Road section in Zhambyl Oblast

Contractors Monthly Environmental Reporting Format

Contractor: ZB of "Kazakhdorstroy" LLP» Name: Imanbaeva D.Y.

Month: December Date: 24

Year: 2012 Signature: ______

Specification Requirement Implementation Activity Implementation Comments / Verifications / Proposed Actions Yes Part No General 64. Contractor shall provide environmental 1.1. The plan has been submitted. V Environmental mitigation and monitoring plan (EMMP) approved mitigation and monitoring plan (EMMP) in by ZhB «Kazakhdorstroy» LLP from 27th of January, 2012, connection with the submission of the accepted by the Engineer and approved by the State Department Program based in the Technical “Zhambyl Oblast Department of Committee for Motor Roads” in Specifications January 2012-. 65. Contractor shall nominate senior staff 2.1. The person has been appointed. V The responsible person was appointed. A curriculum vita was person to be responsible for follow-up of introduced in the report for March 26, 2012 with ref. num. №43. implementation of EMMP and guidance of 2.2. The instruction was provided with V The personnel of the Contractor were acquainted with ecological the Contractor staff and reporting to Engineer the staff of the Contractor. requirements which execution was a mandatory condition at realization of construction. Instructing with the personnel has undergone before starting of construction. 2.3. Reports prepared for the Engineer V Environmental report is provided monthly. Previously, the reports were submitted for September- December 2010, half-yearly report for 2010 (second half-year); January to July – 2011, July – December of 2011, half yearly report for 2012 ( January –June), Monthly report from January to November 2012 half-yearly report for the first half-and second half for 2012. Half year Environmental Management and Monitoring Plan Report Final Page 14

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

66. EMMP shall be provided as a part of 3.1. EMMP provided with method V EMMP is the part of Method Statement the method statement statement Specification Requirement Implementation Activity Implementation Comments / Verifications / Proposed Actions Yes Part No Expectation of Camps, Asphalt Plants, cement Plants and Related Facilities

67. Siting construction and environmental 4.1 Plans submitted to the Engineer V Project of Camp and Production section (2 of Mortar Concrete restoration of facilities for housing Plant, Soil-mixing plants, Crushing and screening plants) were construction staff, storage of equipment & submitted in report for September-October. The Camp and vehicles, labour camps, asphalt plants and production section arranged km 368 motor way Almaty – Taraz similar facilities must be planned to the satisfaction of the Engineer 4.2 Engineer satisfaction obtained V The oral approval of Engineer was obtained.

Air Quality Monitoring (AQM) 68. EMMP shall specify proposed pre- 5.1 Pre-construction Air Quality V Air Quality monitoring had been conducted before the construction monitoring to verify baseline monitoring included in EMMP commencement of works. Protocols of the air analyses results (for conditions as advised by Engineer September) were submitted in the second half of 2010. 5.2 Engineer recommendations V There were no recommendations.

69. Pre-construction TSP monitoring at not less 6.1 Monitoring points identified V Measurements of the base indicators have been performed: at the than 2 points depending on proposed location of the projected road interchange ( before the village location of pollution sources Merke), Mortar-concrete plant, Zhanaturmys v., Kazakh v. 6.2 Additional baseline monitoring V An additional monitoring was not required. required by Engineer 70. EMMP shall specify locations and 7.1 Locations specified V Air Quality monitoring is performed at the location of pollutant frequency of routine instrumented sources. (Mortar-concrete plant (km 368) Aktogan v. (km367), monitoring of Air Quality Zhanaturmys v. (km 377) Kazakh v. (km 383) not less than once a month. 71. Air Quality monitoring required not less 8.1 Air quality monitoring is submitted V Air Quality monitoring has been performed. The protocols of than once per month monthly. measurement results are submitted in the Annex 2. 72. Additional event-related monitoring may be 9.1 An additional monitoring is V An additional monitoring was not required. Half year Environmental Management and Monitoring Plan Report Final Page 15

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

required by Engineer required. 73. Monitoring undertaken by third party 10.1 Engineer acceptance has been V Testing laboratory for the instrumental measurements has been organisations acceptable to Engineer received approved. (ref. No.KAZ-MER 026/2011 dated 30/04/2011) 74. The following quality requirements for the 11 The following requirements are applied for Concrete Batching Plant air are applied to the Plant for production of asphalt and mixing plant. a. Open burning prohibited a Prohibition implemented V Open burning is not produced b. Use of Solutions and Materials are b Material use satisfactory. V Engineer’s approval of required solutions and materials is given to approved by the Engineer the testing laboratory. c. Blasting operations shall be carried out c Carried out V Blasting operations are not stipulated. using a small number of charges. d. Dust-raising items are covered with a d Carried out V Stored dust generating materials are not covered as located far from tarpaulin. (cover) settlements and have no impact to environment e. The construction sections and roads are e Carried out V This point is in the process. Pictures are attached in the Annex 3. watered to prevent the dust-raising. f. The trucks that transport soil, sand or f Trucks have been covered with V Trucks are covered with tarpaulins during the transportation of inert rock shall be covered with a tarpaulin to tarpaulins. materials. Photographs are attached in the Annex 3. prevent spilling. Water quality monitoring 75. EMMP shall include pre-construction 12.1 The pre-construction monitoring is V There are two water objects in the construction zone: Koltogan river monitoring to verify initial conditions at included in EMMP – 364 km, Big Chu Channel -366 km. The quality monitoring of locations as been advised by Engineer these object was included in the EMMP. Pictures are attached in Annex 4

12.2 Engineer recommendations V There were no recommendations.

Specification Requirement Implementation Activity Implementation Comments / Verifications / Proposed Actions Yes Part No

Half year Environmental Management and Monitoring Plan Report Final Page 16

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

76. Pre-construction water quality monitoring 13.1 Required parameters are indicated V shall include analysis for: suspended solids, in the pre-construction water quality Pre-construction monitoring for water quality has been performed. biological oxygen demand (BOD) and monitoring. Protocols of the analysis results for the natural water were submitted dissolved oxygen (DO), electrical in the report for the second half of 2010. conductivity, colon bacillus, oil and grease.

77. Additional baseline monitoring may be 14.1 Additional baseline monitoring V Additional monitoring has not been conducted. required by location of major sources of undertaken potential water pollution (construction camps & other sources of significant run- off & liquid waste generation)

78. Under the procedure plan for the 15.1 Procedures are listed in the EMMP. V Monitoring for the waste water quality of the camp has not been monitoring of water quality and wastes of conducted, the construction camps, parking lots (of becausethewastewaterisremovedbythefilteredfieldsunderthecontract. machineries and transports), shall be held once a month.

79. Pre-construction water quality monitoring 16.1 Monitoring includes the required V See the item 13.1 includes analysis for: suspended solids, parameters. biological oxygen demand (BOD) and dissolved oxygen (DO), electrical conductivity, colon bacillus, oil and grease. 80. The Engineer may demand to conduct an 17.1 The Engineer demanded to conduct V An additional monitoring was not demanded. additional monitoring. an additional monitoring.

81. Monitoring conducted by a third party, 18.1 Received the approval of Engineer V Monitoring is carried out by the accredited test laboratory ZhB which received permission of the Engineer «КESO-Оtan» LLP in accordance with the agreement № 67 dated March 5, 2012 Specification Requirement Implementation Activity Implementation Comments / Verifications / Proposed Actions Yes Part No Noise and vibration monitoring

Half year Environmental Management and Monitoring Plan Report Final Page 17

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

82. Pre-construction baseline monitoring of 19.1 Implemented V Noise and vibration measurements were conducted before the noise and vibration required at minimum of commencement of construction. The protocols were submitted in 2 sites including major settlements the report for the second half of 2010. 83. An additional monitoring may be requested 20.1Engineer requested an additional V An additional monitoring was not conducted. monitoring. 84. Regular monitoring shall be conducted at 2 21.1 Implemented V Measurements were conducted close or directly in the settlements, site minimum. according to the measurement rules. Noise and vibration monitoring are conducted at the following points: Sanitary protection zone of the Motor-concrete plant, Zhanaturmys v., Kazakh v., Aktogan v.

85. Monitoring shall be conducted once a 22.1 Implemented V Noise and vibration monitoring is conducted monthly. month. 86. Additionalmonitoring may be requested 23.1 Additional monitoring V Additional monitoring was not conducted. during pile sinking and blasting operations and also on Engineer’s request. 87. Monitoring carried out by the 3rd party, 24.1 Engineer acceptance is obtained. V Testing laboratory is approved by the Engineer. acceptable by the Engineer.

Public relations 88. EMMP shall specify proposed public 25.1 The program is included in EMMP V Notification of public is conducted before the commencement of information programs in advance of construction construction, notification procedures etc 25.2 Request regarding to the According to the official statistics, there are 2968 residents in settlements amount in Aktogan v. Aktogan v. 25.3 Request regarding to the settlements According to the official statistics, there are 2535 residents in amount in Zhanaturmys v. Zhanaturmys v. 25.4 Request regarding to the settlements According to the official statistics, there are 901 residents in Kazakh amount in Kazakh v. v. Specification Requirement Implementation Activity Implementation Comments / Verifications / Proposed Actions Yes Part No Storage of fuels and chemicals

Half year Environmental Management and Monitoring Plan Report Final Page 18

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

89. The foundation of the Fuel and Chemical 26.1 The waterproof foundation and V Road-construction machineries are filled with special transport- Storage shall be waterproof; the storage fencing is provided. petrol tanker. The storage of oil mineral is implemented at the petrol shall be fenced around. station territory of IE(Individual Enterpreneur) Nurseitov upon the Agreement (No. dated 01.01.2011. 90. Storage located away from watercourse and 27.1 Appropriately located V There is no owned fuel storages Territory of petrol station is located wetlands away from watercourse and wetlands. 91. Foundation and walls are waterproof 28.1 Level of Waterproof level is V Placement of tanks for the fuel storage meets all the sanitary and satisfactory environment standards. 92. Capacity of bunded 110% of the volume of 29.1 Implemented V See the item 28.1 tanks within bund 93. Filling and refuelling strictly controlled 30.1 Procedures developed and V Filling of vehicles is executed in accordance with safety and implemented environmental requirements. In case of fuel spillage removal of polluted soil is conducted. For fire safety every fuel truck is provided with fire extinguishers. 94. Valves & trigger guns shall be resistant to 31.1 Valves and trigger guns comply V unauthorised interference and vandalism with requirements and be turned off and securely locked when SeeItem26.1 not in use

95. Contents of any tank or drum shall be 32.1 Contents clearly marked in Russian V See Items 26.1, 28.1 clearly marked language 96. Measures shall be taken to ensure that no 33.1 Measures implemented V See Items 26.1, 12.1 contaminated discharges enter any drain or 33.2 Any contaminated discharges V Ingress of pollutants in water sites is not possible as there were no watercourses entering drain or water course surface water sites found on the road construction site, the fuel storage meets all the sanitary, environment and safety requirements. Water quality 97. Contractor shall prevent any interference 34.1 Any interference with supply V Activities are designed during the execution of works preventing with supply or abstraction from supply or any adverse impact on water sources. These activities are included pollution of water resources including in EMMP. groundwater 34.2 Any pollution of surface or V See item 34.1 groundwater Half year Environmental Management and Monitoring Plan Report Final Page 19

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

98. All water and other liquid waste products 35.1 All liquid & other wastes collected V The liquid formation is not provided in the area of construction arising on sites shall be collected on or off works. the sites and in a manner that shall not cause nuisance or pollution 35.2 Manner of collection not causing V See item 35.1 pollution 99. Contractor shall not discharge or deposit 36.1 Requirement implemented V Wastes are not discharged; any domestic wastes are taken out with a any matter arising from execution of the special transport in special designated areas. Wastewaters is Works into any water except with transported to wastewater treatment plants of Merke Branch permission of Engineer and regulatory “Centralnoaziatsikaya Sakharnaya Korporaciya” LLP . Annex 16 authority 36.2 If discharges, prior Engineer V See item 36.1 approval obtained 100. Contractor shall at all times ensure that 37.1 Stream courses and drains kept free V Wastes are formed during the construction works, if formed they are all existing stream courses and drains within of debris and materials arising from taken out to a special designated place. (see item 36.1) and adjacent to the Site are kept free from the Works any debris and materials arising from the Works 101. Contractor shall protect all 38.1 All waterways protected V Measurements for waterways protection are implemented watercourses, waterways, ditches, canals, drains, lakes and the like from pollution, silting, flooding or erosion as a result of the execution of the Works 102. Contractor shall submit details of his 39.1 Details submitted to Engineer prior V Water supply and sewage system project of the construction camp temporary drainage system (including all to construction and concrete batching plant are included in report for the second surface channels, sediments traps, washing half of 2011. basins and discharge pits) to the Engineer 39.2 Samplings of water for chemical Water analysis (bacteriological and chemical) of well in for approval prior to commencing work on and bacteriological analysis are construction camp has been conducted. The results of sanitary- its construction. taken from well in Aktogan village microbiological resting of water №3, №2 dated 25.04.2012, issued by ORSBE "Center of sanitary and epidemiological expertise of Zhambyl oblast" Air quality 103. Open burning is prohibited 40.1 In accordance with the specification V No open burning conducted.

Half year Environmental Management and Monitoring Plan Report Final Page 20

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

104. Contractor shall utilise effective 41.1 Water sprays utilised V Dust suppression is conducted twice a day in hot and dry weather water sprays during delivery and handling of materials when dust likely to be created and to dampen stored materials during dry and windy weather 105. Stockpiles of materials shall be sited 42.1 Material stockpiles sited in sheltered V Storage locations are not fenced as located far from settlements in sheltered areas or within hoarding, areas or within hoarding away from sensitive areas. Stockpiles of 42.2 Stockpiles of friable material V SeeItem42.1 friable material shall be covered with covered with clean tarpaulins and clean tarpaulins, with application of sprayed water during dry and windy sprayed with water weather. Stockpiles of material shall be 42.3 Stockpiles dampened prior to V SeeItem42.1 dampened prior to their movement, except movement where this is contrary to the Specification 106. Any vehicle with an open load- 43.1 Properly fitting side and tail boards V All trucks equipped with side limiters and flaps carrying area used for transporting provided potentially dust producing material shall have properly fitting side and tail boards

107. Any vehicle with an open load- 43.1 Properly fitting side and tail boards V All trucks equipped with side limiters and flaps carrying area used for transporting provided potentially dust producing material shall 44.1 Loads comply with loading V Being executed have properly fitting side and tail boards requirement Materials having potential to produce dust shall not be loaded to a level higher than the 44.2 Tarpaulins clean and good condition V Being executed side and tail boards and shall be covered with a clean tarpaulin in good condition. Tarpaulin shall be properly secured and extend at least 300mm over the edges of the side and tail boards. 108. In periods of high wind, dust 45.1 Operations comply with V Being executed generating operations shall not be specification permitted within 200m of residential areas having regards to the prevailing direction Half year Environmental Management and Monitoring Plan Report Final Page 21

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

of the wind 109. Construction vehicles & machinery 46.1 Vehicles & machinery kept in good V Repairing works of transports are executed by internal services, in shall be kept in good working order and working order the workshop “TilemisBatyr” LLP upon the agreement, the engines turned off when not in use. agreement was submitted in the report for October of 2010.

46.2 Engines turned off when not in use V Being executed

110. Appropriate measures shall be taken 47.1 Measures taken to limit exhaust V Part of road construction machinery is equipped with exhaust filters to limit exhaust emissions from emissions from vehicles & plant construction vehicles emissions from construction vehicles, machinery & plant & contractor shall include details in EMMP 111. In residential or other sensitive areas 48.1 Preliminary warning of people, V Settlements areas population timely notified before the start of such as nurseries and hospitals etc, working in the environmental construction works. advance warning shall be given to sensitive areas. potentially affected persons, so that measures can be taken by them before 48.2 Assistance with mitigation measures V Dust suppression works are executed (water sprinkling, cover with provided to project affected people tarpaulin), works are on-going from 8.00 to 22.00. commencement of works (PAP) Specification Requirement Implementation Activity Implementation Comments / Verifications / Proposed Actions Yes Part No Noise 112. Contractor shall consider noise as 112.1 Noise considered by Contractor as V Noise level monitoring is conducted monthly. Protocols are an environmental constraint in the environmental constraint attached in report planning and execution of the Works 113. Contractor shall use plant and equipment 50.1 Plant and equipment conforms with V Crushing plant, mortar concrete plant,soil-mixing plant conforms to conforming to international standards international standards for noise and the requirements of international standards. (Euro 3) and directives on noise and vibration vibration emissions 114. EMMP shall include details for 51.1 EMMP includes required details for V Noise reduction in crushing and screening plant is not performed. abating noise at source as per sub-item abating noise at source Noise level in working area Crushing and Screening Plants 4.18 of Conditions of Contract compiled 85-90 dB(А). Workers use personal protection equipment

Half year Environmental Management and Monitoring Plan Report Final Page 22

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

(earplug) for acoustic protection. On border of a sanitary-protective zone the noise level does not exceed the installed sanitary-hygienic norms 115. Contractor shall take all necessary 52.1 All necessary measures taken V See item 50.1 measures to ensure that the operations of all mechanical equipment and construction processes on and off-site shall not cause unnecessary or excessive 52.2 Noise levels in accordance with V See item 8.1. noise, taking into account applicable applicable environmental environmental requirements. requirements 116. The Contractor shall use all 53.1 All necessary measures taken V See item 50.1 necessary measures and maintain all plant and silencing equipment in good condition so as to minimise noise during Works 53.2 Silencing equipment maintained in V See item 50.1 good condition

117. When operating close to sensitive 54.1 Construction is not executed until V Control is conducted at nearby villages and residential sections. receptors such as residential, nursery, or 08:00 and after 18:00 medical facilities, the Contractor’s hours of working shall be limited to 0800 to 1800

Earthworks 118. Surplus excavation and topsoil shall 55.1 Surplus excavation and topsoil used V Topsoil is stored on specially provided sites before its use for re- wherever possible be used to reinstate to reinstate borrow pits and quarries cultivation of areas within construction site area, slopes and road borrow pits and quarries or other areas as shoulders protection, quarries etc. may be approved by the Engineer 55.2 2 Re-cultivation of quarries in V Projects of rehabilitation of quarries after development and accordance with the approval of the agreement with authorized bodies has been presented Engineer

Half year Environmental Management and Monitoring Plan Report Final Page 23

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

119. Surplus excavation and topsoil shall 56.1 Surplus excavation and topsoil used V Rehabilitation was executed in connection with completion of wherever possible be used to reinstate to reinstate borrow pits and quarries works. borrow pits and quarries or other areas as may be approved by the Engineer 56.2 Re-cultivation of quarries in V Mechanical re-cultivation was executed in connection of accordance with the approval of the completion of works Engineer Preservation of Antiquities 120. Contractor shall take all necessary 57.1 All necessary measures taken V In the area of the reconstructed section of road ( 260-383 km ) measures to protect any antiquities or There are 13 historic buildings and archaeological finds are located archaeological finds as required by item outside the buffer zone ( 20 m )According to the legislation of RK, 4.24 of Conditions of Contract in case of archeological or historical value, is reported to the competent authorities 121. Where antiquities are shown on the 58.1 Identified antiquities protected by V See item 57.1 drawings or otherwise identified during means of suitable fencing and the course of the Works, and protected by barriers to satisfaction of the means of suitable fencing and barriers to Engineer the satisfaction of the Engineer. 122. The Contractor shall provide and 59.1 Access maintained as required V See item 57.1 maintain access at all times for persons wishing to stop and pay their respects Environmental Enhancement 123. On completion of the Works the 60.1 Site Rehabilitation Plan prepared to V Project for rehabilitation of land lots provided for temporary land Contractor shall reinstate all areas with the satisfaction of the Engineer usage was developed and presented natural vegetation to the satisfaction of 60.2 Areas reinstated with natural V Has been performed in accordance with land areas rehabilitation the Engineer revegetation in accordance with SRP design 61. . The Contractor shall remove all old 61.1 All old tyres and internal tubes V Old tyres are hauled out of the sites tyres and internal tubes from within removed from within Limits of Site the Limits of Site, and subject to the 61.2 Landholder agreement obtained for V Has been performed in accordance with land areas rehabilitation agreement of adjacent landholders, removal of tyres within 75m of either design. from an additional area 75m either side of the road centre line side of centreline 61.3 Tyres removed in accordance with V Has been performed in accordance with land areas rehabilitation landholder agreements design Half year Environmental Management and Monitoring Plan Report Final Page 24

Dohwa Engineering CAREC Project Two – Zhambyl Oblast Section Contract Location: km 310+500-km 358+600

62. Contractor shall dispose of all 62.1 Materials disposed of as approved V Has been performed in accordance with land areas rehabilitation materials in a manner approved by the by Engineer design Engineer 63. When directed by the Engineer, the 63.1 Directive relating to land V Has been performed in accordance with land areas rehabilitation Contractor shall improve and reinstate the reinstatement received from Engineer design land on which informal roadside service areas have been established by removing 63.2 Debris removed and land reinstated V Has been performed in accordance with land areas rehabilitation all debris and contaminated soils as directed by Engineer in design regrading to natural ground levels, and re- accordance with SRP (see above) establishing the natural vegetation. 64. Debris and contaminated materials 64.1Disposed with a permission of the V Has been performed in accordance with land areas rehabilitation shall be disposed off site as approved by Engineer. design the Engineer. 123.1 Management of lead-contaminated V The analysis of soilwas undertaken for lead contamination before soil the construction works and submitted in the the previous monthly report .

Prepared by: D.Y. Imanbaeva. Department Head: M.V. Kim tel.: +77057891178 tel: +77771105229

Half year Environmental Management and Monitoring Plan Report Final Page 25

ANNEX 4

Environmental Permission obtained by the Contractors ANNEX 4

Compliance Status for getting permission/licenses/approvalfrom concerned authority- KCC No. Activity KCC “Engineering and Construction Co., Ltd.” 1 Vegetation clearance Tree-cutting permit №12270 incoming №60 dated August 27,2010Y. 2 Sitting and Location of Office: Str. Ahtamberdiev 34, village Sarymoldaev, Camp Sites Merke region, Zhambyl oblast, Republic of Kazakhstan on Rental contract. Rotational camp (worker’s settlement) is located on the rural district Kenes, act on the land №955832, cadastral number of the site №06- 092-066-682 dated December 01,2010Y. 3 Quarry Site 1) Permission on emission №0000990 dated November 01, 2011Y. 2) The act of state registration of the contract on subsoil operations between the Natural resources and environmental management of the Akimat (local administration) in Zhambyl oblast and branch of KCC “Engineering and Construction Co., Ltd.” dated September 30, 2011Y. registration No.542 4 Crusher Plant Permission on emission №0000913 dated September 01, 2011Y. 5 Concrete Plant and 1) Permission on emission №0001459 dated November 01, 2012Y. Cement unloading area instead of Permission on emission №0001258 dated September 28, 2011Y. and №0000827 dated July 01, 2011Y. 2) Permission on special water useNo.Shu-T/170 Т.Р. dated July 01, 2011Y. 6 Traffic Safety Fencing scheme of work places and arrangement of road signs issues management Plan Department in Zhambyl oblast Automobile Road Committee of the MOTC of the RK and sign (confirm)by the SAI RPD DIA (State Automobile Inspection of Road Police Department, Department of Internal Affairs) from September 01, 2010Y. No.31-55 7 Waste disposal plan Contract with IE “Dzhumasheva N.O.” export of household waste dated and site December 16, 2010Y., there are developed passports of hazardous wastes on an old used tires registered in Shu-Talas Ecological Department №H-08-2069 dated February 27, 2012Y., used mercury- containing lamps №H-08-1959 dated January 17, 2012Y., contract on demercurization with “EnerjiTaraz”, household waste №H-08-1962 dated January 17, 2012Y., waste batteries №H-08-1960 dated January 17, 2012Y., used oils №H-08-1958 dated January 17, 2012Y., contract on export of used oils dated December 22, 2011Y. with IE “Kokumov”. 8 Extraction of ground Extraction of ground water of project for construction of roads developed water KazNI&PI “Dortrans”. 9 Road Construction Permission on emission №0000607 dated November 01, 2010Y.

Compliance Status for getting permission/licenses/approval from concerned authority- KDS SI No Activity KDS 1 Vegetation clearance Felling License № 012269 dated 01.07.2010 - issued by Zhambyl oblast Department of Committee for motor roads 2 Sitting and Location of Official Act for Land Lot № 955755, Sanitary and Camp sites epidemiological conclusion № 258 dated 13.10.2010 – issued by Department of state sanitary and epidemiological control, Conclusion of state environmental expertise №З/Т-924 dated 11.11.201 – issued by Department for Ecology of Zhambyl oblast, Emission Permit №0000637 dated 31.12.2010 – issued by Department for Ecology of Zhambyl oblast 3 Quarry site Detailed in report 4 Crusher Plant There is no Crushing Plant 5 Concrete Plant and Cement Official Act for Land Lot № 955755, Sanitary and Unloading Area epidemiological conclusion № 258 dated 13.10.2010 – issued by Department of state sanitary and epidemiological control, Conclusion of state environmental expertise №З/Т-924 dated 11.11.201 – issued by Department for Ecology of Zhambyl oblast, Emission Permit №0000637 dated 31.12.2010 – issued by Department for Ecology of Zhambyl oblast 6 Traffic Safety Management Environmental protection Department doesn't obtain Plan such kind of information 7 Waste Disposal plan and Solid Domestic Wastes and Liquid Domestic Wastes are site removed when they accumulate in accordance with the contract specified in the report 8 Extraction of Ground water There is no extraction of Ground water 9 Road Construction Emission permit № 0000614 dated 11.2010 - issued by Department of Natural Resources and Land Use Management of Zhambyl oblast Akimat

ANNEX 5

Location Map of Loam Field – KCC E & C

ANNEX6

Basic data on the construction camp ANNEX 6 General data of the Camp

Contd. Annex 6

ANNEX 7

Agreement for disposal of domestic wastes and wastewater on

disposal facility of Merke branch of “Central Asian Sugar

Corporation” LLP - «Kazakhdorstroy» LLP

ANNEX8

Handover Certificatesof Waste tires

ANNEX 8

Handover Certificate 1- Waste tires

Dated: October 24, 2012

We the undersigned "YKSM" limited liability partnership - hereinafter referred to as – “Customer”, represented by the director, Chensou, on the one part and Zhambyl branch of “KAZAKHDORSTROY” limited liability partnership, hereinafter referred to as - “Executor”, represented by the project manager - T.K. Tayzhanov, on the other part made this certificate for the following actions: The Customer accepted in a proper way, and the Executor delivered waste tires of Road Construction machinery in the amount of 17 (seventeen) pieces.

“Executor” “Customer” Zhambyl Branch of "UKSM" LLP “Kazakhdorstroy” LLP

Project Manager Director ______T.K. Tayzhanov ______Chensou

Handover Certificate 2- Waste tires

Dated: August 24, 2012

We the undersigned Military unit 03811 - hereinafter referred to as – “Customer”, represented by the capitan, Y.A. Baybosynov, on the one part and Zhambyl branch of “KAZAKHDORSTROY” limited liability partnership, hereinafter referred to as - “Executor”, represented by the project manager - T.K. Tayzhanov, on the other part made this certificate for the following actions: The Customer accepted in a proper way, and the Executor delivered waste tires in the amount of 109 (one hundred and nine) pieces.

Attendee: Head of coordination department ______M.V. Kim

“Executor” “Customer” Zhambyl Branch of Military Unit 03811 “Kazakhdorstroy” LLP

Project Manager Capitan ______T.K. Tayzhanov ______Y.A. Baybosynov

Handover Certificate 3- Waste tires

Dated: August 4, 2012

We the undersigned representative office of republican non-governmental association "OTAN" in T.Ryskulov rayon - hereinafter referred to as – “Customer”, represented by the chairman, R.A. Turebekov on the one part and Zhambyl branch of “KAZAKHDORSTROY” limited liability partnership, hereinafter referred to as - “Executor”, represented by the project manager - T.K. Tayzhanov, on the other part made this certificate for the following actions: The Customer accepted in a proper way, and the Executor delivered waste tires of Road Construction machinery in the amount of 59 (fifty nine) pieces.

“Executor” “Customer” Zhambyl Branch of Republican non-governmental Kazakhdorstroy” LLP association "Otan"

Project Manager Chairman ______T.K. Tayzhanov ______R.A. Turebekov

Handover Certificate 4- Waste tires

We the undersigned representative office of republican non-governmental association "OTAN" in T.Ryskulov rayon - hereinafter referred to as – “Customer”, represented by the chairman, R.A. Turebekov on the one part and Zhambyl branch of “KAZAKHDORSTROY” limited liability partnership, hereinafter referred to as - “Executor”, represented by the project manager - T.K. Tayzhanov, on the other part made this certificate for the following actions: The Customer accepted in a proper way, and the Executor delivered waste tires of Road Construction machinery in the amount of 32 (thirty three) pieces.

“Executor” “Customer” Zhambyl Branch of Republican non-governmental Kazakhdorstroy” LLP association "Otan"

Project Manager Chairman ______T.K. Tayzhanov ______R.A. Turebekov

ANNEX9

Handover certificate rehabilitated lands temporary occupied for quarry of loam "Land lot №3" situated at the boundaries of Merke rayon in Zhambyl oblast ANNEX 9

Handover certificate

rehabilitated lands temporary occupied for quarry of loam "Land lot №3" situated at the boundaries of Merke rayon in Zhambyl oblast connected with reconstruction of the motor road "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" (road section km 358,6- 389,4)

Merke rayon November 21,2012

Commission represented by: Merke rayon Akimat Head of Land Relations Department R. Ospankulov

Department for ecology of Zmabyl oblast Regional inspector T. Smagulov

Zhambyl rural district Akim M. Kokrekbaev

PF "Abdukarimov" A. Abdukarimova

ZB of "Kazakhdorstroy" LLP Project Manager M.N. Kadyrov

conducted the survey of land lot for mining of loam, deposit "Land lot № 3" with total area 13,3 ha. and site of access road to the quarry with total area 2,67 ha. provided for temporary short- time land use by the order of Akim of Merke rayon of Zhambyl oblast № 529 dated 11.11.2011, resolution of Zhambyl rural district Akimat of Merke rayon of Zhambyl oblast № 106 dated 28.11.2011 and order of Zhambyl oblast Akimat № 122 dated 26.04.2012. For location of: -quarry of deposit "Land lot №3" with total area 13,3 ha.; - access road with total area 2,67 ha.;

The commission made this certificate on the following: 1. ZB of "Kazakhdorstroy" LLP has performed works for rehabilitation of destructed lands for above-mentioned sites provided for temporary short-time land use in order to return the lands to their previous owners consisting of the original grounds: 1. plough land - 13,3 ha.; 2. pasture - 2,67 ha.;

2. The following documents were submitted: - Order of Akim of Merke rayon of Zhambyl oblast № 529 dated 11.11.2011; - Resolution of Zhambyl rural district Akimat of Merke rayon of Zhambyl oblast № 106 dated 28.11.2011; - order ofZhambyl oblast Akimat № 122 dated 26.04.2012; - Identification documents for land lots; - Work acceptance Certificate for land rehabilitation; № i/o Cadastral № Area, ha 1 06-092-020-116 13,97 2 06-092-022-311 2,0

3. There were no deviations from norms during the process of rehabilitation. 4. Conclusion of commission: Works on rehabilitation of lands temporary occupied for quarry of loam "Land lot №3" and access road situated at the boundaries of Zhambyl rural district of Merke rayon in Zhambyl oblast connected with reconstruction of "Almaty-Korday-Blagoveshenka-Merke-Tashkent- Termez" motor road (road section km 358,6-389,4) were executed in compliance with normative, legislative norms and rules.

The commission considers that rehabilitated lands are suitable for subsequent agricultural use in the content of the previous lands. Rehabilitated lands are handed over to the previous land users of Merke rayon.

R. Ospankulov

T. Smagulov

M. Kokrekbaev

A. Abdukarimova

M.N. Kadyrov

Contd. Annex 9

Work acceptance certificate rehabilitated lands temporary occupied for quarry of loam "Land lot №3" situated at the boundaries of Merke rayon in Zhambyl oblast connected with reconstruction of the motor road "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" (road section km 358,6- 389,4)

Merke rayon November 21,2012

Commission represented by: Merke rayon Akimat Head of Land Relations Department R. Ospankulov

Department for ecology of Zmabyl oblast Regional inspector T. Smagulov

Zhambyl rural district Akim M. Kokrekbaev

PF "Abdukarimov" A. Abdukarimova

ZB of "Kazakhdorstroy" LLP Project Manager M.N. Kadyrov observed the works performance for rehabilitation of lands temporary occupied for location of quarry of loam deposit "Land lot №3 and access road situated at the boundaries of Zhambyl rural district of Merke rayon in Zhambyl oblast connected with reconstruction of "Almaty-Korday- Blagoveshenka-Merke-Tashkent-Termez" motor road (road section km 358,6-389,4)

1. Mechanical and biological rehabilitation of temporary occupied land lots has been conducted without violations of normative, legal norms and requirements. 2. Temporary occupied land lots can be handed over to the original land owners.

R. Ospankulov

T. Smagulov

M. Kokrekbaev

A. Abdukarimova

M.N. Kadyrov

ANNEX 11

Agreementswith «MerkeDisinfection» LLPandCentralHospitalofMerkeRegionPublic Health Department of Zhambyl oblast Akimat

ANNEX12

Handover certificate of rehabilitated lands temporary occupied for construction sites situated at the boundaries of Merke region in Zhambyl oblast

ANNEX 12

Handover certificate of rehabilitated lands temporary occupied for construction sites situated at the boundaries of Merke rayon in Zhambyl oblast connected with reconstruction of the motor road "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" (road section km 358,6-389,4)

Merke rayon November 21,2012

Commission represented by: Merke rayon Akimat Head of Land Relations Department R. Ospankulov Department for ecology of Zmabyl oblast Regional inspector T. Smagulov T. Ryskulov rural district Akim S. Yessenov PF "TylemysBatyr" B. Zheksembiev PF "Kuan and D" D. Moldagulova PF "Nart" K. Nartova PF "Kerymbai" K. Beksultan PF" Moldyr G" A. Abdukarimov PF "Toleget-Dat" Zh. Seitov "Arna" LLP K. Burkitbaev

ZB of "Kazakhdorstroy" LLP Project Manager M.N. Kadyrov

conducted the survey of land lots with total area 14,775 ha provided for temporary short-time land use by the order of Akim of Merke rayon of Zhambyl oblast № 363 dated 27.08.2010 for location of -sites for accumulation in amount of 5 pcs with total area - 14,776 ha The commission made this certificate on the following: 1. ZB of "Kazakhdorstroy" LLP has performed works for rehabilitation of destructed lands for above-mentioned sites provided for temporary short-time land use in order to return the lands to their previous owners consisting of the original grounds: 1. plough land - 9,96 ha; 2. pasture - 4,816 ha;

2. The following documents were submitted: - acts for right of temporary short-term land use for above mentioned sites (copies) according to the specified list; - Completion Certificate for land rehabilitation; № i/o Cadastral № Area, ha 1 06-092-092-015 3,01 2 06-092-017-092 3,01 3 06-092-022-295 3,1 4 06-092-022-296 3,006 5 06-092-027-235 2,65 TOTAL: 14,776

3. There were no deviations from norms during the process of rehabilitation. 4. Conclusion of commission: Works on rehabilitation of lands temporary occupied for construction objects of "Almaty- Korday-Blagoveshenka-Merke-Tashkent-Termez" motor road (road section km 358,6-389,4) at the boundaries of Merke rayon in Zhambyl oblast were executed in compliance with normative, legislative norms and rules. The commission considers that rehabilitated lands are suitable for subsequent agricultural use in the content of the previous lands. Rehabilitated lands are handed over to the previous land users of Merke rayon. R. Ospankulov

T. Smagulov

S. Yessenov

B. Zheksembiev

D. Moldagulova

K. Nartova

K. Beksultan

A. Abdukarimov

Zh. Seitov

K. Burkitbaev

M.N. Kadyrov

Work acceptance certificate rehabilitated lands temporary occupied for construction sites situated at the boundaries of Merke rayon in Zhambyl oblast connected with reconstruction of the motor road "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" (road section km 358,6-389,4)

Merke rayon November 21,2012

Commission represented by: Merke rayon Akimat Head of Land Relations Department R. Ospankulov Department for ecology of Zmabyl oblast Regional inspector T. Smagulov T. Ryskulov rural district Akim S. Yessenov PF "TylemysBatyr" B. Zheksembiev PF "Kuan and D" D. Moldagulova PF "Nart" K. Nartova PF "Kerymbai" K. Beksultan PF" Moldyr G" A. Abdukarimov PF "Toleget-Dat" Zh. Seitov "Arna" LLP K. Burkitbaev ZB of "Kazakhdorstroy" LLP Project Manager M.N. Kadyrov observed the works performance for rehabilitation of lands temporary occupied for location of storage sites for reconstruction of "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" motor road (road section km 358,5-389,4) at the boundaries of Merke rayon in Zhambyl oblast. 1. Mechanical and biological rehabilitation of temporary occupied land lots has been conducted without violations of normative, legal norms and requirements. 2. Temporary occupied land lots can be handed over to the original land owners after expiration of lease terms. R. Ospankulov

T. Smagulov

S. Yessenov

B. Zheksembiev

D. Moldagulova

K. Nartova

K. Beksultan

A. Abdukarimov

Zh. Seitov

K. Burkitbaev

M.N. Kadyrov

Handover certificate rehabilitated lands temporary occupied for construction sites situated at the boundaries of T. Ryskulov rayon in Zhambyl oblast connected with reconstruction of the motor road "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" (road section km 358,6-389,4)

T. Ryskulov rayon November 21,2012

Commission represented by: T. Ryskulov rayon Akimat Head of Land Relations Department B. Bashanov Department for ecology of Zhambyl oblast Regional inspector Zh. Mambetaliev PF "Dulat" O. Niyazkulov PF "Nurdaulet" N. Mustafaev

ZB of "Kazakhdorstroy" LLP Project Manager M.N. Kadyrov

conducted the survey of land lots with total area 6,01 ha. provided for temporary short-time land use by the order of Akim of T. Ryskulov rayon of Zhambyl oblast № 373 dated 27.08.2010 for location of -sites for stockpiling in amount of 5 pcs with total area - 6,01 ha

The commission made this certificate on the following: 1. ZB of "Kazakhdorstroy" LLP has performed the works for rehabilitation of destructed lands for above-mentioned sites provided for temporary short-time land use in order to return the lands to their previous owners consisting of the original grounds: 1. plough land - 3,0 ha; 2. pasture - 3,01 ha;

2. The following documents were submitted: - acts for right of temporary short-term land use for above mentioned sites (copies) according to the specified list; - Work acceptance Certificate for land rehabilitation; № i/o Cadastral № Area, ha 1 06-091-088-319 3,01 2 06-091-093-550 3,0 TOTAL: 3,01

3. There were no deviations from norms during the process of rehabilitation. 4. Conclusion of commission: Works on rehabilitation of lands temporary occupied for construction objects of "Almaty- Korday-Blagoveshenka-Merke-Tashkent-Termez" motor road (road section km 358,6-389,4) at the boundaries of T. Ryskulov rayon in Zhambyl oblast were executed in compliance with normative, legislative norms and rules. The commission considers that rehabilitated lands are suitable for subsequent agricultural use in the content of the previous lands.

Rehabilitated lands are handed over to the previous land users of T. Ryskulov rayon. B. Bashanov

Zh. Mambetaliev

O. Niyazkulov

N. Mustafaev

M.N. Kadyrov

Work acceptance certificate rehabilitated lands temporary occupied for construction sites situated at the boundaries of T. Ryskulov rayon in Zhambyl oblast connected with reconstruction of the motor road "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" (road section km 358,6-389,4)

T. Ryskulov rayon November 21,2012

Commission represented by: T. Ryskulov rayon Akimat Head of Land Relations Department B. Bashanov Department for ecology of Zhambyl oblast Regional inspector Zh. Mambetaliev PF "Dulat" O. Niyazkulov PF "Nurdaulet" N. Mustafaev

ZB of "Kazakhdorstroy" LLP Project Manager M.N. Kadyrov observed the works performance for rehabilitation of lands temporary occupied for location of storage sites for reconstruction of "Almaty-Korday-Blagoveshenka-Merke-Tashkent-Termez" motor road (road section km 358,5-389,4) at the boundaries of t. Ryskulov rayon in Zhambyl oblast. 1. Mechanical and biological rehabilitation of temporary occupied land lots has been conducted without violations of normative, legal norms and requirements. 2. Temporary occupied land lots can be handed over to the original land owners after expiration of lease terms.

B. Bashanov

Zh. Mambetaliev

O. Niyazkulov

N. Mustafaev

M.N. Kadyrov