Railway Tender Conference 2019 Joint project and E16

• New station at Sundvollen • Complete reconstruction of Hønefoss station • 40 km double tracks • 15 km motorway • Railway: opening scheduled for 2029 • Road: opening scheduled for 2027 Project status

• State approval of zoning plan expected 4Q 2019 • Final Investment Decision Autumn 2020 • Prequalification for first main contract end 2020/beginning 2021 • Start-up for main preparatory works in 2021 (Prequal 3-4Q 2020) • Preparation of roads and traffic safety works • Access tunnels at Nordby and Avtjerna (190.000 solid m3) • Preparation of rig areas • Forest clearing • Noise prevention measures Ringerike Line and E16 Highway

ERTMS

TK07 Project summary – railway and highway

• 40 km new double track railway from to Hønefoss designed for a max speed of 250 km/h

• 15 km four lane highway from Høgkastet to Hønefoss/Ve, designed for max speed 110 km/h

• Complete rebuild of existing railway station at Hønefoss

• Estimated project value 34 billion NOK Project summary – tunnels and bridges

• 23 km double track railway tunnel with parallel escape and service tunnel from Sandvika to Sundvollen • 3 km double track railway tunnel at Vik • 2 x 3 km 2-lane highway tunnels at Vik • 770 m double track railway bridge across Kroksund • 640 m 4-lane highway bridge across Kroksund • Bridge crossing of the river and wetlands at Mælingen: • Alt 1: Two railway bridges (300 m + 900 m) plus three highway bridges (1 x 300 m + 2 x 900 m) with an embankment in-between • Alt 2: One railway bridge (1800 m) plus two highway bridges (2 x 1800 m) Requirements for model-based engineering

• The project will be fully model based and according to the Road and Rail Authorities' BIM-strategies

• Standardised requirements for model based engineering and building are now implemented across the contracts focusing on:

• Standardised formats per discipline • Standardised information per discipline • Model based reviews and interface checks Distribution and reuse of excavated materials

• 9,8 million m3 of excavated materials will be distributed and reused in the project

• 70% embankments, quality masses and concrete aggregates

• 30% landfill and preparation of land for future construction of homes Contract Structure

Ringerike Line and E16 Highway TK-01 Jong TK-02 Sollihøgda TK-03 Sundvollen TK-04 Vik TK-05 Mælingen TK-06 Hønefoss

Preparatory / Enabling works Several contracts (construction only)

Design substructure rail and road

TK-01 (EPC) TK-02 (EPC) TK-03 (EPC) TK-04 (EPC) TK-05 (EPC) TK-06 (ECI/EPC) Build substructure rail and road

Tracks, overhead contact line, TK-07 (EPC) high/low Railway Technique woltage, telecom Signal ERTMS Railway systems

Description Scope Contract type and Contract notice Commencem Completion strategy ent

Ringerike Line TK-06 Super structure, overhead Subcontract or JV 2021 2023 2029 railway systems contact line, HV/LV and to alliance Hønefoss. telecom. Combination of agreement newbuild and rebuild. Complete rebuild of existing railway station at Hønefoss during operation.

Ringerike Line TK-07 35 km double track, EPC 2023 2025 2029 Railway systems superstructure, overhead Jong-Styggedalen contact line, HV/LV and telecom. Project Values and Key Dates Ringerike Line and E16 Highway

• Total project value: 34 BILLION NOK • Railway in operation: 2029/30 • Highway in operation: 2028 Preliminary Dates for Prequalification

Prequal. 2021 Prequal. 2021 Prequal. 2021 Hønefoss EPC EPC EPC

TK-01 Jong TK-03 Sundvollen TK-05 Mælingen Sundvollen Tunnel Tunnel, station and Bridges bridges Civil Sandvika S works Prequal. 2020/21 Prequal. 2022 Prequal. 2021 Lysaker EPC EPC ECI / EPC TK-02 Sollihøgda TK-04 Vik TK-06 Hønefoss Tunnel Tunnels, bridges Civil works and and open railway systems landscape

Prequal. 2023

Railway EPC systems TK-07 Railway Systems excl. ERTMS and Hønefoss railway station area Ringerike Line and E16 Highway

For project information, please see: Bane NOR’s home page: www.banenor.no Project home page: www.banenor.no/prosjekter/prosjekter/RingeriksbanenogE16

Supplier contact: [email protected] Thank you for your attention