<<

Procurement Plan National Community Driven Development Project Department of Rural Development Public Disclosure Authorized I. General

1. Bank’s approval Date of the procurement Plan: November 13, 2012 2. Procurement Plan Update Version: 8th Version 3. Date of General Procurement Notice: Nov 8, 2012 4. Period covered by this procurement plan: 12 months

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Public Disclosure Authorized Type of Procurement (US $ ) Works (Including turnkey supply and installation of plant and 2,000,000 equipment and PPP) ( 2 million) Goods, information technology and non-consulting services 1,000,000 ( 1million) Consultant firms 300,000 Consultant Individuals 200,000

Type of Market Approaches Thresholds Procurement (US $ in million) Public Disclosure Authorized International National- National Comments Open RFQ (Shopping) Works (Including 3 and above Less than 3 Less than 1 Recommended to turnkey supply and advertise for 7 days for installation of plant RFQ above 0.5 and equipment and PPP) Goods, information 1 and above Less than 1 Less than 0.5 Recommended to technology and non- advertise for 7 days for consulting services RFQ above 0.05 Consultants (Firms) 0.1 and above Less than 0.1 Not CQS method may be applicable used up to 0.5. Public Disclosure Authorized Use of full RFP mandatory for CQS above 0.3. Limits on market approaches do not July 9, 2010 apply to individual consultants.

2. Reference to (if any) Project Operational Manual (POM): is under preparation and to be acceptable to the World Bank.

3. Any Other Special Procurement Arrangements: N/A

4. Summary of the Procurement Packages (Goods, Works and Non-Consulting Services) planned for 12 months

1 2 3 4 5 6 7

Ref. Description Estimated Packa Domest Review Comments No. Cost ges ic by Bank US$ million Prefere (Prior / Post) nce (yes/no) 3 Summary of 3.5 25 No Prior and Shopping (Goods) Post 4 Summary of Direct 0.5 5 No Prior and Contracting Post (Goods) 6 Summary of 1 7 No Post Shopping (Works)

4. Summary of consultancy Assignments with Selection Methods and Time Schedule

1 2 3 4 5 6

Ref. Description of Estimate Packages Review Comments No. Assignment d by Bank Cost (Prior / US$ Post) million 1 Summary of number 4.4 4 Prior of contracts that will be let under QBS 2 Summary of number 3.4 20 Prior/Pos CQS and of contracts that will t Individual be let under other Consultant methods selection 3 Summary of number 13.2 12 Prior of contracts that will be amendment of existing contract/ Single Source Selection July 9, 2010 July 9, 2010 PROCUREMENT : Myanmar National Community Driven Development Project PLAN General Information

Country: Myanmar Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 Revised Plan Date(s): (comma delineated, leave blank if none)2020-09-02 Project ID: P132500 GPN Date: Project Name: Myanmar National Community Driven Development Project Loan / Credit No: IDA / H8140, IDA / 56870 Executing Agency(ies):Department of Rural Development

WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned

Under W3 / GARAGE for NEW Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 50,000.00 0.00 Implementat 2019-05-05 2019-06-30 2019-12-27 OFFICE BUILDING Quotations Envelope ion

Under W4 / WAREHOUSE for Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 100,000.00 0.00 Implementat 2019-05-28 2019-07-23 2020-01-19 NEW OFFICE BUILDING Quotations Envelope ion

W7 / REHABILITATION of Pending THE YANGON Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 120,000.00 0.00 Implementat 2019-05-05 2019-06-30 2019-12-27 WAREHOUSE COMPLEX 2 Quotations Envelope ion units

GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

G 45 / VEHICLES and MOTORCYCLES (HGC) for IDA / H8140 Community Block Grants Prior Direct Selection Direct 1,865,000.00 2,083,297.00 Signed 2016-07-28 TOWNSHIPS and

REGIONAL OFFICES

G53 / COMMUNICATION Request for Open - MATERIAL: VINYL IDA / H8140 Community Block Grants Prior 216,615.00 152,002.77 Canceled Quotations International POSTERS

G80 / TABLET Open - Single Stage - One COMPUTERS for 17 IDA / H8140 Community Block Grants Prior Request for Bids 669,375.00 700,875.00 Signed 2017-04-05 2017-05-09 International Envelope TOWNSHIPS (2017-2018)

G-59 / Communication Request for Open - IDA / H8140 Community Block Grants Prior 454,080.00 405,405.30 Signed 2017-05-19 Materials: T-shirts and Caps Quotations International

G16(a)(b), G17(b) / Motor Vehicle: Double cabs pickup, IDA / H8140 Community Block Grants Prior Direct Selection Direct 987,500.00 1,005,521.50 Signed 2015-09-10 land cruiser double cab,

Motorcycle 125 cc

G95 / ELECTRIC Request for Single Stage - One CURRENT STABILIZERS for IDA / H8140 Implementation Support Post Open - National 48,000.00 41,342.22 Completed 2017-12-10 2018-02-04 2018-04-11 2018-08-03 2018-08-03 Quotations Envelope 16 new townships

Page 1 G96 / DESKTOP and LAPTOP COMPUTERS and Request for Single Stage - One HARD DISK DRIVES for IDA / H8140 Implementation Support Post Open - National 371,700.00 299,708.92 Completed 2018-01-15 2018-03-12 2018-04-03 2018-09-08 2018-07-26 Quotations Envelope the UNION and 16 new townships

Pending G92B / 30 SEATER IDA / H8140 Implementation Support Post Direct Selection Direct 133,475.00 0.00 Implementati 2017-12-29 2018-01-03 2018-02-07 2018-08-06 BUSSES on

Pending G93 / Seven BOATS for 16 Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 70,000.00 0.00 Implementati 2018-01-30 2018-03-27 2018-09-23 new townships Quotations Envelope on

G97 / PRINTERS and PHOTO COPIERS and FAX- Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 67,650.00 62,555.10 Completed 2017-12-26 2018-02-20 2018-06-26 2018-08-19 2018-08-09 SCANNERS for the UNION Quotations Envelope and 16 new townships

G98 / SUPPLY and INSTALLATION of a CCTV Pending Request for Single Stage - One SECURITY SYSTEM in the IDA / H8140 Implementation Support Post Open - National 30,000.00 0.00 Implementati 2018-02-23 2018-04-20 2018-10-17 Quotations Envelope YANGON and NAY PYI on TAW WAREHOUSES

G99 / PROJECTOR and Request for Single Stage - One SCREEN for 16 new IDA / H8140 Implementation Support Post Open - National 16,000.00 14,133.86 Completed 2017-12-26 2018-02-20 2018-03-05 2018-08-19 2018-03-22 Quotations Envelope townships

G100 / GSM PHONE Request for Single Stage - One HANDSET for 16 new IDA / H8140 Implementation Support Post Open - National 12,250.00 6,850.17 Completed 2017-12-06 2018-01-31 2018-02-07 2018-07-30 2018-02-22 Quotations Envelope townships

G101 / CAMERAS and Request for Single Stage - One VIDEO CAMERAS for 16 IDA / H8140 Implementation Support Post Open - National 32,600.00 29,527.33 Completed 2017-12-26 2018-02-20 2018-02-22 2018-08-19 2018-03-08 Quotations Envelope new townships

G102 / WATER COOLER Request for Single Stage - One and AIR CONDITIONERS IDA / H8140 Implementation Support Post Open - National 29,500.00 15,245.70 Completed 2017-12-09 2018-02-03 2018-02-28 2018-08-02 2018-03-06 Quotations Envelope for 16 new townships

G103 / OFFICE Request for Single Stage - One FURNITURE for 16 new IDA / H8140 Implementation Support Post Open - National 96,080.00 77,739.19 Completed 2017-12-09 2018-02-03 2018-02-09 2018-08-02 2018-02-16 Quotations Envelope townships

G104 / SAFETY EQUIPMENT MOTORCYCLE Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 97,920.00 92,811.80 Completed 2018-01-24 2018-03-21 2018-09-06 2018-09-17 2018-10-19 CRASH HELMETS for 16 Quotations Envelope new townships

G105 / SAFETY EQUIPMENT LIFE Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 60,000.00 35,202.24 Completed 2018-01-07 2018-03-04 2018-02-09 2018-08-31 2018-02-23 JACKETS for 16 new Quotations Envelope townships

G107 / CONSUMABLES and USAGE SPARE PARTS IDA / H8140 Implementation Support Post Direct Selection Direct 50,000.00 0.00 Canceled 2017-12-04 2017-12-09 2018-01-13 2018-07-12 for PHOTOCOPIERS and

PRINTERS

G108 / MOTORCYCLES Pending High Ground Clerance Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 171,478.00 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 including SPARE PART KIT Quotations Envelope on for 16 new townships

G110 / RAIN COATS with Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 60,900.00 24,865.47 Completed 2018-01-01 2018-02-26 2018-02-09 2018-08-25 2018-03-12 PROJECT LOGO Quotations Envelope

Page 2 G72 / WATER QUALITY Request for Single Stage - One TESTING KITS for 54 IDA / H8140 Implementation Support Post Open - National 270,000.00 316,797.69 Completed 2017-03-10 2017-05-05 2018-08-06 2017-11-01 2018-11-28 Quotations Envelope TOWNSHIPS

G111 / NCDDP VINYL Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 265,608.00 158,872.93 Completed 2018-03-12 2018-05-07 2018-07-17 2018-11-03 2018-09-18 POSTERS Quotations Envelope

G112 / TILES or PLAQUES or STONES with Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 73,346.00 63,869.01 Completed 2018-01-24 2018-03-21 2018-05-09 2018-09-17 2018-01-01 completed sub-project Quotations Envelope information

G113 / T SHIRTS with Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 445,728.00 302,985.14 Completed 2018-01-24 2018-03-21 2018-06-29 2018-09-17 2018-10-19 NCDD Project Logo Quotations Envelope

G114 / CAPS with NCDDP Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 166,800.00 145,434.53 Completed 2018-01-24 2018-03-21 2018-05-09 2018-09-17 2018-07-26 Logo Quotations Envelope

G118 / GENDER Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 43,500.00 23,673.40 Completed 2018-03-19 2018-05-14 2018-08-13 2018-11-10 2018-09-19 BOOKLETS Quotations Envelope

G119 / ENVIRONMENTAL Request for Single Stage - One CODE OF PRACTICES IDA / H8140 Implementation Support Post Open - National 4,750.00 6,905.37 Completed 2018-03-19 2018-05-14 2018-07-11 2018-11-10 2018-09-14 Quotations Envelope BOOKLETS

G120 / GRIEVANCE Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 63,195.00 55,272.06 Completed 2018-04-02 2018-05-28 2018-10-10 2018-11-24 2019-01-07 SUGGESTION BOXES Quotations Envelope

G121 / BROCHURES FOR Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 29,600.00 3,230.42 Completed 2018-03-19 2018-05-14 2018-07-17 2018-11-10 2018-08-31 UNION and TOWNSHIPS Quotations Envelope

G109 / SPARE PARTS and Pending REPAIR KITS for IDA / H8140 Implementation Support Post Direct Selection Direct 385,000.00 0.00 Implementati 2018-02-23 2018-02-28 2018-04-04 2018-10-01 MOTORCYCLES High on Ground Clerance

Pending G122 / VEHICLE SPARE IDA / H8140 Implementation Support Post Direct Selection Direct 121,380.00 0.00 Implementati 2018-02-28 2018-03-05 2018-04-09 2018-10-06 PARTS on

G91B / 13 PICKUPS Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 468,000.00 0.00 Canceled 2018-01-03 2018-02-28 2018-08-27 DOUBLE CAB Quotations Envelope

G 92A / G 92A Nine Request for Single Stage - One Pickup Double Cabs for IDA / H8140 Implementation Support Post Open - National 378,000.00 311,319.00 Completed 2018-11-21 2019-01-16 2019-01-07 2019-07-15 2019-03-29 Quotations Envelope NCDDP

G123 / SUPPLY and INSTALLATION of a CCTV Request for Single Stage - One SECURITY SYSTEM in IDA / H8140 Implementation Support Post Open - National 50,000.00 16,802.67 Completed 2019-03-06 2019-05-01 2019-10-10 2019-10-28 2020-01-30 Quotations Envelope NEW BUILDING OF DRD HEAD OFFICE

Pending Request for Single Stage - One G124 / Office Furniture IDA / H8140 Implementation Support Post Open - National 104,600.00 0.00 Implementati 2019-07-15 2019-09-09 2020-03-07 Quotations Envelope on

G125 / 3HP Stand Air Pending Request for Single Stage - One Conditioner for New Project IDA / H8140 Implementation Support Post Open - National 5,000.00 0.00 Implementati 2019-07-15 2019-09-09 2020-03-07 Quotations Envelope Office and Training Hall on

G126 / Photo Copieer for Request for Single Stage - One replacement and additional IDA / H8140 Implementation Support Post Open - National 105,000.00 104,040.23 Completed 2019-03-13 2019-05-08 2019-06-26 2019-11-04 2019-09-03 Quotations Envelope needs for existing townships

Page 3 G127 / Projector with Request for Single Stage - One screen for replacement in IDA / H8140 Implementation Support Post Open - National 25,000.00 22,519.53 Completed 2019-03-13 2019-04-22 2019-05-08 2019-06-03 2019-11-04 2019-08-16 Quotations Envelope Township and Union

G128 / Still Camera for Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 7,500.00 7,588.10 Completed 2019-03-13 2019-05-14 2019-05-08 2019-07-11 2019-11-04 2019-09-20 Regional Office Quotations Envelope

Pending G131 / Rehabilitation of Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 130,000.00 0.00 Implementati 2019-03-24 2019-05-19 2019-11-15 Project Vehicles Quotations Envelope on

G132 / Life Jackets for Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 13,500.00 0.00 Canceled 2019-04-07 2019-06-02 2019-11-29 replacement Quotations Envelope

G133 / Printing Grievance Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 33,000.00 7,106.05 Completed 2019-05-14 2019-07-09 2019-08-07 2020-01-05 2019-09-20 Envelop Quotations Envelope

G134 / Tshirts with project Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 333,000.00 172,385.38 Completed 2019-05-14 2019-07-09 2019-08-30 2020-01-05 2019-08-30 logo Quotations Envelope

G135 / Caps with project Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 171,000.00 59,994.26 Completed 2019-05-14 2019-07-09 2019-09-05 2020-01-05 2019-09-05 logo Quotations Envelope

G136 / Project Information Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 210,000.00 205,546.95 Completed 2019-03-05 2019-04-22 2019-04-30 2019-05-31 2019-10-27 2019-09-03 Board with Project Logo Quotations Envelope

G137 / Backpack for 16 new project townships and Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 40,000.00 18,792.86 Completed 2019-03-05 2019-04-22 2019-04-30 2019-06-11 2019-10-27 2019-08-15 additional needs for other Quotations Envelope townships

G138 / Operation and Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 52,000.00 18,484.86 Completed 2019-03-10 2019-05-05 2019-09-30 2019-11-01 2019-09-30 Maintenance Vinyl Poster Quotations Envelope

G139 / Printing Operation Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 13,500.00 8,728.15 Completed 2019-03-10 2019-05-05 2019-09-23 2019-11-01 2019-09-23 and Maintenance Books Quotations Envelope

G140 / Printing Communication Guide Book Pending Request for Single Stage - One and Printing Community IDA / H8140 Implementation Support Post Open - National 7,500.00 0.00 Implementati 2019-07-07 2019-09-01 2020-02-28 Quotations Envelope Driven Development Booklet on support by World Bank

G141 / Printing Gender Manual Book and Check Request for Single Stage - One List Review and Revised IDA / H8140 Implementation Support Post Open - National 9,350.00 5,126.52 Completed 2019-07-07 2019-09-01 2019-09-23 2020-02-28 2019-09-23 Quotations Envelope Book and Printing Gender Success Stories Booklet

G142 / NCDDP Sticker(Grievance Suggestion Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 65,900.00 12,999.16 Completed 2019-03-10 2019-04-22 2019-05-05 2019-06-12 2019-11-01 2019-09-05 Boxes,Motorcycles and Fie Quotations Envelope

Cover)

Pending G143 / Video Conference Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 45,000.00 0.00 Implementati 2019-06-09 2019-08-04 2020-01-31 for Union Quotations Envelope on

G144 / Highspeed Scanner Request for Single Stage - One for Union Regional and IDA / H8140 Implementation Support Post Open - National 35,000.00 49,703.98 Completed 2019-06-09 2019-08-04 2019-08-13 2020-01-31 2019-09-23 Quotations Envelope Township

Pending G145 / Printing Operation Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 189,663.00 0.00 Implementati 2019-05-14 2019-07-09 2020-01-05 Manual in 2018 Quotations Envelope on

Page 4 Pending G41 / GRADIENT Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 18,900.00 0.00 Implementati 2019-07-22 2019-09-16 2020-03-14 MEASUREMENT DEVICES Quotations Envelope on

G117 / 60001 kits SUPPLY Request for Single Stage - One of MEDICAL KITS for the IDA / H8140 Implementation Support Post Open - National 187,870.00 0.00 Canceled 2019-04-07 2019-04-22 2019-06-02 2019-11-29 Quotations Envelope PROJECT STAFF

G 130 / Maintenance and Under Request for Single Stage - One Repair Service for the IDA / 56870 Implementation Support Post Open - National 365,635.00 0.00 Implementati 2019-10-22 2019-12-17 2020-06-14 Quotations Envelope NCDDP Fleet of Motorbikes on

G146 / Life Jackets for Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 13,500.00 11,492.79 Completed 2019-10-29 2019-12-24 2020-01-03 2020-06-21 2020-01-03 replacement Quotations Envelope

G 147 / Supply of Medical Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 187,870.00 110,761.25 Completed 2019-10-29 2019-12-24 2020-01-30 2020-06-21 2020-01-30 Kits Quotations Envelope

Pending G148 / Spare parts for UN Agencies IDA / 56870 Implementation Support Post Direct 110,000.00 0.00 Implementati 2019-11-06 2019-11-11 2019-12-16 2020-06-13 vehicles (Direct) on

G162 / Protective Items For Pending Emergency Contingency COVID-19 Response for IDA / 56870 Post Direct Selection Direct 35,000.00 0.00 Implementati 2020-04-06 2020-04-11 2020-04-28 2020-05-12 Response project staff on

G145 PRINTING OPERATION MANUAL 2020 Under / Printing of the Operation Request for Single Stage - One IDA / 56870 Knowledge and Learning Post Open - National 49,350.00 0.00 Implementati 2020-06-28 2020-08-23 2021-02-19 Manual Update Version 2020 Quotations Envelope on for Union, State, Regional, Townships.

G148 SPARE PARTS FOR MOTOR VEHICLES / Spare Under parts for Motor Vehicles in IDA / 56870 Implementation Support Post Direct Selection Direct 110,000.00 0.00 Implementati 2020-06-23 2020-06-28 2020-08-02 2021-01-29 State, Regional, union, on Townships

G161 REPLACEMENT BATTERIES FOR TABLETS / REPLACEMENT Pending Request for Single Stage - One BATTERIES for SAMSUNG IDA / 56870 Implementation Support Post Open - National 24,000.00 0.00 Implementati 2020-07-04 2020-08-29 2021-02-25 Quotations Envelope and HUAWEI TABLET on COMPUTERS in Union, State, Regional, Towships.

G164 / Reagents for the Pending Water Quality Testing Kits IDA / 56870 Implementation Support Post Direct Selection Direct 145,000.00 0.00 Implementati 2020-06-23 2020-06-28 2020-08-02 2021-01-29 in the Current Townships. on

G 176 / Video Conferencing Pending Request for Single Stage - One Equipment for the State and IDA / 56870 Implementation Support Post Open - National 85,000.00 0.00 Implementati 2020-07-01 2020-08-26 2021-02-22 Quotations Envelope Regional Offices on

Under G 158 / PHONE Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 6,500.00 0.00 Implementati 2020-07-08 2020-09-02 2021-03-01 HANDSETS Quotations Envelope on

G 156 / OFFICE EQUIPMENT; COLOR Pending Request for Single Stage - One PRINTER, BLACK and IDA / 56870 Implementation Support Post Open - National 17,700.00 0.00 Implementati 2020-07-07 2020-09-01 2021-02-28 Quotations Envelope WHITE PRINTER, ALL-IN- on ONE PRINTER

Page 5 G 157 / OFFICE Pending EQUIPMENT;HIGH-SPEED Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 13,800.00 0.00 Implementati 2020-07-01 2020-08-26 2021-02-22 SCANNER and HARD DISK Quotations Envelope on DRIVE

G 159 / Pending COMMUNICATION Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 20,350.00 0.00 Implementati 2020-07-08 2020-09-02 2021-03-01 MATERIAL; CAMERA and Quotations Envelope on VIDEO CAMERA

G166 INFORMATION BOARD / INFORMATION Pending Request for Single Stage - One BOARDS for CURRENT IDA / 56870 Implementation Support Post Open - National 155,100.00 0.00 Implementati 2020-09-02 2020-10-28 2021-04-26 Quotations Envelope TOWNSHIPS and 13 NEW on TOWNSHIPS

G 152 / FURNITURE for Pending Request for Single Stage - One Union and 13 new IDA / 56870 Implementation Support Post Open - National 91,650.00 0.00 Implementati 2020-07-01 2020-08-26 2021-02-22 Quotations Envelope townships on

G 153 / AIR- Pending CONDITIONERS , WATER Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 23,000.00 0.00 Implementati 2020-07-07 2020-09-01 2021-02-28 COOLERS AND Quotations Envelope on REFRIGERATOR

G168 VINYL POSTERS (9) ITEM / Vinyl Posters (9) Pending Request for Single Stage - One Item for Union, Regional IDA / 56870 Implementation Support Post Open - National 112,733.00 0.00 Implementati 2020-09-04 2020-10-30 2021-04-28 Quotations Envelope Office, 12 Old TSPs and 13 on new TSPs

NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

G89 / SUPPLY and INSTALLATION and Pending CONFIGURATION of a IDA / H8140 Implementation Support Prior Direct Selection Direct 10,000.00 0.00 Implementati 2018-03-12 2018-03-17 2018-04-21 2018-10-18 SERVER for the NEW on FINANCE SOFTWARE

NC82 / RENTAL of VEHICLES for UNION DRD Pending Request for Single Stage - One EVENTS and CROSS IDA / H8140 Implementation Support Post Open - National 60,000.00 0.00 Implementati 2018-01-23 2018-03-20 2018-09-16 Quotations Envelope EXCHANGE VISITS between on townships

Pending NC85 / PHOTOCOPY AND Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 9,230.00 0.00 Implementati 2017-12-17 2018-02-11 2018-08-10 PRINTING SERVICES Quotations Envelope on

G129 / Rehabilitation of Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 20,000.00 0.00 Canceled 2019-03-24 2019-05-19 2019-11-15 Nissan SUV Quotations Envelope

G130 / Rehabilitation of Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 232,600.00 0.00 Canceled 2019-03-24 2019-05-19 2019-11-15 Project Motorbikes Quotations Envelope

G131 REPAIR SERVICE FOR PROJECT VEHICLES / Under Repair Service for the IDA / 56870 Implementation Support Post Direct Selection Direct 30,000.00 0.00 Implementati 2020-06-18 2020-05-19 2020-06-23 2020-05-29 2020-07-28 2021-01-24 rehabilitation of the project on vehicles (15 Toyota and 1 Nissan)

Page 6 G149 REPAIR SERVICE FOR THE MOTORBIKES / Under Repair service for the IDA / 56870 Implementation Support Post Direct Selection Direct 150,000.00 0.00 Implementati 2020-06-23 2020-04-01 2020-06-28 2020-08-02 2021-01-29 Rehabilitation of the on Motorbikes

G150 SPARE PARTS FOR Under HONDA MOTORCYCLES / IDA / 56870 Implementation Support Post Direct Selection Direct 100,000.00 0.00 Implementati 2020-06-23 2020-04-01 2020-06-28 2020-08-02 2021-08-02 Spare Parts for Honda on Motorcycles

G-151 SPARE PARTS FOR TVS MOTORCYCLES / Under Spare Parts (TVS IDA / 56870 Implementation Support Post Direct Selection Direct 200,000.00 0.00 Implementati 2020-06-18 2020-04-01 2020-06-23 2020-07-28 2021-07-28 Motorcycles) for Union, on Regional, and Townships.

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

C.4.16 / TTA Y3 Cluster 7: Quality Based Open - IDA / H8140 Community Block Grants Prior 3,000,000.00 1,817,882.14 Signed 2015-11-12 2015-11-27 Selection International

C4.13 / TTA Y3 Cluster 4: Quality Based Open - IDA / H8140 Community Block Grants Prior 3,000,000.00 2,605,225.09 Signed 2015-11-23 2015-11-27 Magway-Chin Selection International

C4.12 / TTA Y3 Cluster 3: Quality Based Open - IDA / H8140 Community Block Grants Prior 3,000,000.00 1,766,947.30 Signed 2015-12-11 2015-12-16 Kayah Selection International

C4.14 / TTA Y3 Cluster 5: Quality Based Open - IDA / H8140 Community Block Grants Prior 6,000,000.00 2,932,594.57 Signed 2015-12-17 2015-12-22 Mon-Kayin-Tanintharyi Selection International

C4.10 / TTA Y3 Cluster 1: Quality Based Open - IDA / H8140 Community Block Grants Prior 3,000,000.00 2,800,626.17 Signed 2015-12-16 2015-11-06 Ayeyawaddy Selection International

C4.15 / TTA Y3 Cluster 6: Quality Based Open - IDA / H8140 Community Block Grants Prior 4,500,000.00 3,156,957.00 Signed 2015-12-16 2015-12-21 Naypyitaw-Mandalay Selection International

C.4.11 / TTA Y3 Cluster 2: Quality Based Open - IDA / H8140 Community Block Grants Prior 4,500,000.00 2,748,468.14 Signed 2016-01-15 2016-01-15 Bago-Yangon Selection International

C72 / FINANCE - NEW Consultant Open - SOFTWARE PACKAGE and IDA / H8140 Community Block Grants Prior Qualification 100,000.00 78,660.00 Canceled 2017-04-05 International CUSTOMIZATION Selection

C4.18 / Y4 TTA Quality Based Open - CONSULTANT FIRM for IDA / H8140 Community Block Grants Prior 1,200,000.00 1,008,471.75 Signed 2017-01-11 2016-12-21 Selection International KACHIN STATE

C4.19 / Y4 TTA Quality Based Open - CONSULTANT FIRM for IDA / H8140 Community Block Grants Prior 1,200,000.00 1,196,495.48 Signed 2017-01-23 2017-01-23 Selection International

C 4.3/ 2014 / TTA Quality And Cost- Open - Sidoktaya Township, Magway IDA / H8140 Community Block Grants Prior 425,000.00 662,209.93 Signed 2014-12-22 2015-01-07 Based Selection International Region

C 4.2/2014 / Township Level Technical Assistance Quality Based Open - IDA / H8140 Community Block Grants Prior 900,000.00 746,557.83 Signed 2014-12-29 2015-01-05 for Township of Selection International

Page 7 C 4.5/ 2014 / TTA Quality Based Open - Laymyethnor Township IDA / H8140 Community Block Grants Prior 425,000.00 883,753.00 Signed 2015-01-02 2015-01-15 Selection International Ayarwaddy Region

Consultant C-10/2014 / Technical Open - IDA / H8140 Community Block Grants Prior Qualification 0.00 8,300.00 Signed 2015-02-17 2015-02-27 Auditor International Selection

C 4.1/2014 / TTA Nay Pyi Quality Based Open - IDA / H8140 Community Block Grants Prior 425,000.00 1,163,384.20 Canceled 2015-10-08 2015-05-15 Taw Selection International

C4.4/2014 / TTA Ann Quality Based Open - IDA / H8140 Community Block Grants Prior 425,000.00 824,816.00 Signed 2015-02-02 2015-02-18 Township Selection International

Quality Based Open - C4.6/2014 / TTA Yangon IDA / H8140 Community Block Grants Prior 425,000.00 812,762.00 Signed 2015-02-02 2015-02-18 Selection International

C4.17 / TTA Y3 Cluster 8: Quality Based Open - IDA / H8140 Community Block Grants Prior 1,500,000.00 1,088,927.30 Signed 2015-11-23 2015-11-27 Kayin Selection International

C5-03 / TOWNSHIP TECHNICAL ASSISTANCE Quality Based Open - IDA / 56870 Community Block Grants Prior 2,200,000.00 1,196,400.71 Signed 2017-11-22 2017-12-08 2017-12-06 2018-01-03 2017-12-23 2018-02-20 2018-01-22 2018-02-05 2018-06-20 2018-03-22 2018-08-17 2018-04-09 2018-09-13 2022-04-08 (2017-2018) in RAKHINE Selection International (Ponnagyun, Gwa)

C5-05 / TOWNSHIP TECHNICAL ASSISTANCE Quality Based Open - IDA / 56870 Community Block Grants Prior 1,100,000.00 532,680.81 Signed 2017-11-22 2017-12-08 2017-12-13 2018-01-03 2018-01-26 2018-02-20 2018-02-23 2018-03-26 2018-03-25 2018-05-14 2018-04-24 2018-06-29 2018-05-29 2018-07-04 2019-05-29 (2017-2018) in SHAN Selection International (Mongkhet)

C 5-08 / TOWNSHIP TECHNICAL ASSISTANCE Quality Based Open - IDA / 56870 Community Block Grants Prior 1,100,000.00 764,088.05 Signed 2017-11-22 2017-12-08 2017-12-06 2018-01-03 2017-12-23 2018-02-20 2018-01-22 2018-03-26 2018-02-05 2018-05-12 2018-03-22 2018-06-29 2018-04-09 2018-07-04 2022-04-08 (2017-2018) in BAGO Selection International (Thegon)

C100 / PROCUREMENT and LOGISTICS Consultant Pending SPECIALIZED TRAINING IDA / H8140 Implementation Support Post Qualification Open - National 30,000.00 0.00 2019-03-25 2019-04-15 2019-05-29 2019-06-28 2019-08-02 2020-01-29 Implementation INSTITUTE for SHORT Selection TERM TRAININGS

C6.03 / Township Level Facilitation and Capacity Quality Based Technical Assistance in Chin IDA / 56870 Prior Open 1,090,000.00 0.00 Under Review 2020-05-04 2020-07-19 2020-05-25 2020-07-31 2020-06-29 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Development Selection State(Mindat Township)

C6.06 / Township Level Facilitation and Capacity Quality Based Technical Assistance in Shan IDA / 56870 Prior Open 2,030,000.00 0.00 Under Review 2020-05-04 2020-07-19 2020-05-25 2020-07-27 2020-06-29 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Development Selection State(Tangyan Township)

C6.08 / Township Level Technical Assistance in Facilitation and Capacity Quality Based IDA / 56870 Prior Open 1,000,000.00 0.00 Under Review 2020-05-04 2020-07-31 2020-05-25 2020-06-29 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Tanintharyi Region(Palaw Development Selection

Township)

C6.09 / Township Level Facilitation and Capacity Quality Based Technical Assistance in Bago IDA / 56870 Prior Open 1,200,000.00 0.00 Under Review 2020-05-04 2020-07-19 2020-05-25 2020-07-27 2020-06-29 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Development Selection Region(Oakpho Township)

C6.11 / Township Level Technical Assistance in Facilitation and Capacity Quality Based IDA / 56870 Prior Open 1,200,000.00 0.00 Under Review 2020-05-04 2020-07-31 2020-05-25 2020-06-29 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Mandalay Region (Taungtha Development Selection

Township)

C6.12 / Township Level Technical Assistance in Facilitation and Capacity Quality Based IDA / 56870 Prior Open 1,020,000.00 0.00 Under Review 2020-05-04 2020-07-27 2020-05-25 2020-08-13 2020-06-29 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Yangon Region (Kayan Development Selection

Township)

Page 8 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

C42/ 2015 / National IDA / H8140 Community Block Grants Prior Direct Selection Direct 50,000.00 50,407.75 Signed 2016-01-01 Developer for MIS 2.0 (firm)

Individual C12 / Finance Assistant IDA / H8140 Community Block Grants Prior Consultant Open 0.00 29,644.99 Signed 2014-07-17 2014-08-10 Selection

Individual C 22/ 2014 / International IDA / H8140 Community Block Grants Prior Consultant Open 47,280.00 47,280.00 Signed 2014-09-15 2014-09-22 Procurement Specialist Selection

C28 / Peachtree Financial Accounting Software, Refresher Training and IDA / H8140 Community Block Grants Prior Direct Selection Direct 6,000.00 4,980.00 Signed 2015-02-26 additional customization April

Individual C 22.1/ 2014 / National IDA / H8140 Community Block Grants Prior Consultant Open 27,600.00 25,321.07 Signed 2015-05-25 2015-05-01 Senior Finance Assistant Selection

C 5-01 / TOWNSHIP TECHNICAL ASSISTANCE (2017-2018) in KACHIN IDA / 56870 Community Block Grants Prior Direct Selection Direct 3,300,000.00 1,171,361.03 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (Putao, Shwegu, Mabeing (Shan))

C 5-04 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 1,100,000.00 436,282.83 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-05-04 2022-02-09 (2017-2018) in SHAN

()

C 5-06 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 2,200,000.00 1,560,848.42 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in KAYIN

(Hlaingbwe, Kawkareik)

C 5-07 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 2,200,000.00 833,562.02 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in SAGAING

(, Kani)

C 5-09 / TOWNSHIP TECHNICAL ASSISTANCE Direct - IDA / 56870 Community Block Grants Prior Direct Selection 1,100,000.00 408,483.00 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in BAGO International (Shwegyin)

C 5-10 / TOWNSHIP TECHNICAL ASSISTANCE (2017-2018) in IDA / 56870 Community Block Grants Prior Direct Selection Direct 2,200,000.00 2,186,439.81 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-05-04 2022-02-09 AYEYARWADDY (Danubyu, Ingapu)

C 5-02 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 1,100,000.00 564,232.00 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in CHIN

(Tonzang)

C67 / National Technical Under IDA / 56870 Implementation Support Post Direct Selection Direct 60,000.00 0.00 2018-01-18 2017-12-27 2018-01-24 2018-01-08 2018-02-13 2018-08-12 Auditors- 5 Experts Implementation

Page 9 C68 / IT CONSULTANTS Individual Facilitation and Capacity Pending for UNION and IDA / 56870 Post Consultant Open 40,800.00 0.00 2018-01-31 2018-02-26 2018-02-28 2018-03-09 2020-03-08 Development Implementation TOWNSHIPS Selection

C69 / IT CONSULTANTS Individual Facilitation and Capacity Under for UNION and IDA / 56870 Post Consultant Open 86,400.00 0.00 2018-01-31 2018-01-25 2018-02-26 2018-04-20 2018-03-01 2018-05-02 2018-03-10 2020-03-09 Development Implementation TOWNSHIPS Selection

C92 / National Consultant Individual Facilitation and Capacity Under for the development of the IDA / H8140 Post Consultant Open 3,200.00 0.00 2018-01-31 2018-01-25 2018-02-16 2018-02-21 2018-03-01 2018-04-10 Development Implementation PRA MANUAL Selection

Individual C84 / GRIEVANCE Facilitation and Capacity Pending IDA / 56870 Post Consultant Open 35,585.00 0.00 2018-05-18 2018-06-12 2018-06-17 2018-06-22 2019-06-22 ASSISTANT Development Implementation Selection

Individual C81 / VEHICLE FLEET Facilitation and Capacity Pending IDA / 56870 Post Consultant Open 36,000.00 0.00 2018-05-17 2018-06-12 2018-06-17 2018-06-22 2020-06-21 MANAGER Development Implementation Selection

Individual C65 / NATIONAL Under IDA / H8140 Implementation Support Post Consultant Open 86,400.00 0.00 2019-03-25 2019-04-12 2019-05-13 2019-06-03 2019-07-08 2020-01-04 TRAINING EXPERT Implementation Selection

C93 / GENDER Individual ASSISTANT replacing Pending IDA / H8140 Implementation Support Post Consultant Open 18,000.00 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2020-01-04 JUNIOR CONSULTANTS for Implementation Selection GRIEVANCE

Individual C95 / NATIONAL GENDER Under IDA / H8140 Implementation Support Post Consultant Open 18,580.00 0.00 2019-03-18 2019-06-26 2019-05-06 2019-05-27 2019-07-01 2019-12-28 CONSULTANT Implementation Selection

C96 / COMMUNICATIONS Individual Under CONSULTANT including IDA / H8140 Implementation Support Post Consultant Open 18,210.00 0.00 2019-02-25 2019-06-26 2019-04-15 2019-05-06 2019-06-10 2019-12-07 Implementation website mgt. & advocacy Selection

C97 / FINANCE Individual ASSISTANT for CHECKING Under IDA / H8140 Implementation Support Post Consultant Open 18,000.00 0.00 2019-03-18 2019-06-26 2019-05-06 2019-05-27 2019-07-01 2019-12-28 TOWNSHIP FINANCIAL Implementation Selection MANAGEMENT

Individual C99 / NATIONAL Pending IDA / H8140 Implementation Support Post Consultant Open 28,800.00 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2020-01-04 TRAINING COORDINATOR Implementation Selection

C102 / PROJECT Individual Pending SECRETARY AT UNION IDA / H8140 Implementation Support Post Consultant Open 14,400.00 0.00 2019-03-18 2019-05-06 2019-05-27 2019-07-01 2019-12-28 Implementation LEVEL Selection

C90 / NATIONAL Individual Facilitation and Capacity Under GRIEVANCE HANDLING IDA / H8140 Post Consultant Open 19,200.00 0.00 2019-03-18 2019-06-26 2019-04-21 2019-04-26 2019-05-09 2020-05-08 Development Implementation EXPERT Selection

C101 / COMMUNITY Individual Under PROCUREMENT IDA / H8140 Implementation Support Post Consultant Open 21,600.00 0.00 2019-03-18 2019-05-13 2019-04-16 2019-06-12 2019-04-26 2019-06-17 2019-05-06 2020-10-27 Implementation RESOURCE OFFICER Selection

C98 / (20) PROCUREMENT Individual Under ASSISTANT for the (20) IDA / H8140 Implementation Support Post Consultant Open 198,000.00 0.00 2019-03-25 2019-05-21 2019-04-28 2019-05-05 2019-05-20 2020-11-10 Implementation TOWNSHIPS Selection

Individual C53 / (15) REGIONAL Under IDA / H8140 Implementation Support Prior Consultant Open 576,000.00 0.00 2019-03-18 2019-08-02 2019-04-16 2019-09-27 2019-04-21 2019-05-04 2020-10-25 OFFICE CONSULTANTS Implementation Selection

Page 10 C103 / International Facilitation and Capacity Under IDA / H8140 Post Direct Selection Direct 196,040.00 0.00 2019-05-29 2019-09-05 2019-06-14 2019-07-09 2021-07-08 Procurement Consultant Development Implementation

C104 / International M&E Facilitation and Capacity Under IDA / H8140 Post Direct Selection Direct 198,220.00 0.00 2019-05-29 2019-06-05 2019-06-14 2019-07-09 2021-07-08 Consultant Development Implementation

C105 / International Facilitation and Capacity Under IDA / H8140 Post Direct Selection Direct 196,040.00 0.00 2019-05-29 2019-09-05 2019-06-14 2019-07-09 2021-07-08 Finance Consultant Development Implementation

Individual C106 / Senior Procurement Under IDA / 56870 Implementation Support Post Consultant Open 21,600.00 0.00 2019-09-27 2019-10-17 2019-11-15 2019-12-06 2020-01-10 2021-12-30 Assistant (National) Implementation Selection

C4.18 EXT 01 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity IDA / H8140 Prior Direct Selection Direct 750,000.00 750,170.02 Signed 2020-01-22 2020-02-04 2020-02-13 2020-02-03 2020-02-22 2020-02-23 2022-02-21 ASSISTANCE (Putao, Development

Shwegu, )

C4.10 EXT 03 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity Under IDA / H8140 Prior Direct Selection Direct 700,000.00 0.00 2020-03-20 2020-04-08 2020-04-20 2020-04-08 2020-04-27 2022-04-27 ASSISTANCE (Danubyu, Development Implementation

Ingapu)

C4.19 EXT 01 / Ext. of the Facilitation and Capacity Under TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 0.00 2020-03-20 2020-04-08 2020-04-20 2020-04-08 2020-04-27 2022-04-27 Development Implementation ASSISTANCE (Mawkmai)

C4.12 EXT 03 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity Under IDA / H8140 Prior Direct Selection Direct 600,000.00 0.00 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2022-02-21 ASSISTANCE (Hlaingbwe, Development Implementation

Kawkareik)

C4.13 EXT 03 / Ext. of the Facilitation and Capacity TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 383,348.92 Signed 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2020-02-23 2022-02-21 Development ASSISTANCE (Tonzan)

C4.14 EXT 02 / Ext. of the Facilitation and Capacity TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 222,990.00 Signed 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2020-02-23 2022-02-21 Development ASSISTANCE (Shwegyin)

C4.16 EXT 03 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity Under IDA / H8140 Prior Direct Selection Direct 500,000.00 0.00 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2022-02-21 ASSISTANCE (Kyunhla, Development Implementation

Kani)

C5.03 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity IDA / H8140 Prior Direct Selection Direct 850,000.00 0.00 Under Review 2020-07-27 2020-08-05 2020-08-18 2020-08-27 2022-08-27 ASSISTANCE (Ponnagyun, Development

Gwa)

C5.08 / Ext. of the Facilitation and Capacity Under TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 600,000.00 0.00 2020-05-22 2020-05-18 2020-06-13 2020-06-22 2022-06-22 Development Implementation ASSISTANCE (Thegon)

C5.05 / Ext. of the Facilitation and Capacity Under TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 0.00 2020-05-22 2020-05-18 2020-06-13 2020-06-23 2022-06-23 Development Implementation ASSISTANCE (Mongkhet)

C89 EXT-01 / MIS Under SUPPORT & IDA / H8140 Knowledge and Learning Post Direct Selection Direct 35,000.00 0.00 2020-02-25 2020-03-10 2020-03-03 2020-03-12 2022-03-12 Implementation DEVELOPMENT for Year 5

Page 11 C107 / (2) Legal Advisors for Developing of Regulations Under IDA / 56870 Knowledge and Learning Post Direct Selection Direct 30,000.00 0.00 2020-04-06 2020-06-23 2020-04-09 2020-04-26 2020-05-11 and Follow Up Guidelines of Implementation the Rural Development Law

C6.02 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,800,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Kayin State(Hpa An Development Implementation

Township)

C6.07 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-31 2020-09-20 2024-09-19 Sagaing Region(Hkamti Development Implementation

Township)

C6.10 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Magway Region(Ngape Development Implementation

Township)

C6.01 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-31 2020-09-20 2024-09-19 Kachin State (Waingmaw Development Implementation

Township)

C6.13 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,540,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Ayeyarwaddy Region (Dedaye Development Implementation

Township)

C6.04 / Township Level Facilitation and Capacity Under Technical Assistance in Mon IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-31 2020-09-20 2024-09-19 Development Implementation State(Kyaikmaraw Township)

C6.05 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Rakhine State(Munaung Development Implementation

Township)

C108 / Individual Individual Consultant for Ponnagyun Facilitation and Capacity Pending IDA / H8140 Post Consultant Open 32,400.00 0.00 2020-08-14 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Townsip (Team Leader, Lead Development Implementation Selection CDD and Training Expert)

C109 / Individual Individual Facilitation and Capacity Pending Consultant for Ponnagyun IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Development Implementation Townsip (Finance Officer) Selection

C110 / Individual Individual Consultant for Ponnagyun Facilitation and Capacity Pending IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Townsip (Procurement Development Implementation Selection Officer)

C111 / Individual Individual Facilitation and Capacity Pending Consultant for Ponnagyun IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Development Implementation Townsip (M&E, MIS Officer) Selection

C112 / Individual Consultant for Ponnagyun Individual Facilitation and Capacity Pending Townsip (Communication, IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-09-19 2020-09-26 2020-10-15 2021-04-13 Development Implementation Social Accountability & Selection Gender)

Page 12