Network Statement 2018 – Appendix 3.5A

Network statement 2018 – Appendix 3.5A 1

Appendix 3.5A

Contents Page

1 Introduction 1.1 About appendix 3.5A 3 1.2 Principles relating to infrastructure works and the capacity restrictions 3

2 Regional and main lines Overview of regional and main lines 5

ROUTE NO. 1 6 ROUTE NO. 2 & 4 7 ROUTE NO. 4 8 ROUTE NO. 5, 6, 10 & 11 9 ROUTE NO. 21 & 24 10 ROUTE NO. 24 & 25 11 ROUTE NO. 25, 32 & 34 12

3 S-train line Overview of S-train line 13

ROUTE NO. 810, 820, 830 & 840 14 ROUTE NO. 802, 840 & 860 15

4 Extra information Overview of miscellaneous possessions not covered by NS 16

Network statement 2018 – Appendix 3.5A 2

1 Introduction

1.1 About appendix 3.5A

The following is guideline of the infrastructure works and capacity restrictions known at the time of the publication of Network Statement 2018.

Upcomming infrastructure works and capacity restrictions in connection to the Signaling Program as mentioned below are temporary. The final determination hereof will be published from time to time.

Rail Net Denmark reserves the right to change or cancel planned infrastructure works and projects based on political dissensions. The following is based on the political determination to complete the Ringsted Femern project as well as upgrading of the coastal line.

Maintenance

There will be an ongoing demand for maintenance of all lines. Maintenance is carried out on the basis of the life circles of the lines. In order to meet demands, cancellations and rerouting after the publication of the K18 timetable is therefore to be expected.

To ensure punctuality, Rail Net Denmark works constantly to rationalize and develop systems and processes, so cancellations can be made as early as possible.

1.2 Principles in regards to infrastructure works and the capacity restrictions

Rail Net Denmark carries out infrastructure works and capacity reductions following major considerations:

The works are coordinated with the aim of ensuring best possible timetables for customers.

Signaling Program:  Mainly evening / night possessions (besides the early deployment lines)  One line at a time: East respectively West and S-train lines

Electrical Program:  Primary night possessions (up to nine hours) in connection to preparatory work related to replacing bridges possession can occur  One line at a time

Renewal projects:  Single track operations on double-track lines; possessions can occur in mainly weekends / holidays

Construction of facilities and 3rd party projects - including speed upgrades:  Coordinated in best possible solution with renewal projects

Coordination between S-train lines and main and regional lines

Network statement 2018 – Appendix 3.5A 3

 Infrastructure work on the S-train lines and main and regional lines are coordinated to ensure accessibility for customers. It ensures that either S- train lines or main and regional lines are always ready for traffic operations when one of them are closed at the coincident lines between the S-train lines and main and regional lines.

Network statement 2018 – Appendix 3.5A 4

Main and regional lines Network Statement 2018

København H Aalborg – Frederikshavn

København H Langå – Struer

Kværkeby – Ringsted – Fjenneslev Viborg

Roskilde/Ringsted/Slagelse Struer – Thisted

Næstved – Vordingborg

Orehoved – Rødby Færge

Roskilde – Køge – Næstved

Roskilde – Holbæk – Kalundborg

Vigerslev – København G

Hellerup – Helsingør

København G – Vigerslev

Odense – Svendborg

Langå – Aalborg

Network statement 2018 – Appendix 3.5A 5

# TIB Line Project name Description Expected Expected Expected dates Traffical consequences Building contractor duration period

1 1 København H Tietgensbroen Durability of bridge 8 x 14 days TBD Track 1-8 in possession for 14 days, Rail Net Denmark (Tietgens extended by approx. 40 one or two tracks at a time. (Construction Div.) Bridge) years Track 26 in possession for the entire period 2 1 København H Postterminalen Possession of track 20 at 10 weeks and TBD Reduced operations at Kh. In Project Nord (3rd party) Københavns 12 weekends conflict with 8 trains/hour Hovedbanegård indbound at track 1. ( Central Station) 3 1 Ringsted - Fjenneslev Kh-Rg, Rg Establishing the northern 3,5 months 24/6 - 15/10 Reduced traffic, and possession og Rail Net Denmark (High speed part of the bridge across track 1 og 2 spærret. Great line Copenhagen - Ringsted) Ringsted Å (Ringsted River) Southern over Little Southern

4 1 Ringsted Kh-Rg, Rg Mounting of bridge over 3,5 months 2/1 - 9/5 Possession of track 3 and 4. Local Rail Net Denmark (High speed Ringsted Å freight trains ind Rg towards/from line Copenhagen - Ringsted) western direction shunting to/from track 25 5 1 Fjenneslev - Ringsted Kh-Rg, Rg Safety works, new track 4,5 days 9/5 Possession of Fjenneslev – Ringsted Rail Net Denmark (High speed Ringsted – Kværkeby Fj-Rg, Gz-Rg, kl. 21.47 – and Ringsted – Kværkeby line Copenhagen - Ringsted) Rg-Ky, 14/5 Only 1 track in Rg kl. 05.30 Reduced traffic, Safety Construction Div. cancelled 6 1 Ringsted –Fjenneslev Kh-Rg, Rg Safety works. 4,5 days 14/5 Reduced traffic, Safety Rail Net Denmark (High speed Ringsted - Kværkeby New tracks/switches in Rg kl. 05.30 Construction Div. cancelled line Copenhagen - Ringsted) – 18/5 Possessions of Ringsted – kl. 21.47 Fjenneslev and Ringsted - Kværkeby spærret, only 1 track in Rg 7 1 Kværkeby – Ringsted Kh-Rg, Rg Safety usage 3,5 days 18/5 Safety Construction Div. cancelled Rail Net Denmark (High speed kl. 21.47 Total possession of Ringsted line Copenhagen - Ringsted) – 22/5 Station kl. 05.30 8 1 (Høje Tåstrup) – Signalling Roll-out 3 2 weekends 1st half TBD Total possession of Roskilde and Rail Net Denmark Roskilde - (Viby Sj.) Programme Installation, testing and 2018 therefore no operations possible (Signalling Programme) Fjernbane East Startup of switchdrive in between Roskilde and neighboring Roskilde stations. 9 1 (Kværkeby) – Ringsted Signalling Roll-out 3 2 weekends 1st half TBD Total possession of Ringsted and Rail Net Denmark – (Fjenneslev) Programme Installation, testing and 2018 therefore no operations possible (Signalling Programme) Fjernbane East Startup of switchdrive in between Ringsted and neighboring Ringsted stations.

Network statement 2018 – Appendix 3.5A 6

# TIB Line Project name Description Expected Expected Expected dates Traffical consequences Building contractor duration period

10 1 (Sorø) – Slagelse – Signalling Roll-out 3 1 weekend 1st half TBD Total possession of Slagelse and Rail Net Denmark (Forlev) Programme Installation, testing and 2018 therefore no operations possible (Signalling Programme) Fjernbane East Startup of switchdrive in between Ringsted and neighboring Slagelse stations. 11 1 Kværkeby – Ringsted Kh-Rg, Rg Safety usage. 3 days Week 42 15/10 -18/10 Reduced traffic Rail Net Denmark (High speed Track 1 and 2 westbound Great Southern over Little line Copenhagen - Ringsted) 2 (stage 3) Southern 12 2 Ringsted – Næstved Kg-Rg, Rg Connection of 12½ days 9/5 kl. 21.47 – Great Southern over Little Rail Net Denmark (High speed Næstved – Ringsted track/traction wire track 1 22/5 kl. 05.30 Southern line Copenhagen - Ringsted) with track Rg-Ky Safety usage 13 2 Næstved – Bropakke 3 og 4 Maintenance of bridge 5 weekends 5/1 - 8/1, Possession of all tracks between Rail Net Denmark (Ringsted- Vordingborg 12/1 - 15/1, Næstved and Vordingborg Femern) 10/8 - 13/8, 12/10 -15/10, 19/10 -22/10 14 2 Næstved – Construction Div works for 3 months 24/6 – 23/9 Reduced operations of following Rail Net Denmark (Ringsted- Vordingborg extension of dam, single lines: Næ-Lu, Lu-Vo Femern) track possessions Vo-Lu, Lu-Næ 15 2 Orehoved – Nykøbing Bropakke 2 Reisolation of bridges in 10 weeks 24/3 – 3/6 Possessions of all tracks between Rail Net Denmark (Ringsted- Falster Construction bropakke 2 Orehoved and Nykøbing Falster Femern) Div., track and station work in Ek. 16 2 Nykøbing Falster – Bropakke 2 Reisolation of bridges in 11 weeks 24/3 – 10/6 Possession of alle tracks between Rail Net Denmark (Ringsted- Rødby Færge bropakke 2 Nykøbing Falster and Rødby Færge Femern)

17 2 Ringsted – (Glumsø) Signalling Roll-out 3 2 weekends 1st half TBD Total possession of Ringsted and Rail Net Denmark Programme Installation, testing and 2018 therefore no operations possible (Signalling Programme) Fjernbane East usage of switchdrive in between Ringsted and neighboring Ringsted stations. 18 4 Roskilde - Køge Signalling EDL North 4 weekends Q1 TBD Possession of all tracks between Rail Net Denmark Programme Testdrive Roskilde and Køge (Signalling Programme) Fjernbane East 19 4 Lille Skensved - Signalling EDL Full 4 weekends 2nd half TBD Possession of alle tracks between Rail Net Denmark Næstved Programme Testdrive 2018 Lille Skensved and Næstved (Signalling Programme) Fjernbane East 20 4 Roskilde – Næstved Signalling EDL Full/EDL North/ R1 2 weeks TBD Possession of all tracks between Rail Net Denmark Programme Testdrive Roskilde and Næstved (Signalling Programme) Fjernbane East

Network statement 2018 – Appendix 3.5A 7

# TIB Line Project name Description Expected Expected Expected dates Traffical consequences Building contractor duration period

21 4 Køge N - Næstved Elektrification The line between Køge N og RESERVA- 2018 2018 Possession of the track, partially Rail Net Denmark Næstved is to be electrified TIONS: and total, on the entire line and (Electrification Programme) in 2018 I conjunction stations, inkl. Køge and Næstved The final timetable and with the EP therefore the detailed rollout the plConstruction Div.ning of follwing activities are not final, but possessions is is to be carried out as long expected:

nightpossessions, every day Long of the week – between nightpossessi 20.00 – 05.00. ons are expected, see ”Desricption”.

In addition: Up to 6 weekend- possessions on whole or half parts of the line (< 56 hours from Fridays kl. 22.00 to Mondays kl. 05.00)

And: Up to 2 week- possessions on parts of the line (223 hours from Fridays kl. 22.00 to the following Mondays kl. 05.00)

Network statement 2018 – Appendix 3.5A 8

# TIB Line Project name Description Expected Expected Expected dates Traffical consequences Building contractor duration period

22 5 Holbæk – Kalundborg Electrification: Railway sleepers, track 8 weeks Summer 14/7 – 09/9 Possession of all tracks between Rail Net Denmark Track-renewal renewal, lowering og tracks Holbæk and Kalundborg inkl. (Electrification Programme) and misc. and reisolation and Kalundborg Station, but without activities replacing of bridges, effecting Holbæk Station. distributed across the entire line 23 5 Roskilde – Lejre Electrification Preparation 8 weeks 2nd half TBD Possession of one track - reduced Rail Net Denmark 2018 operations (Electrification Programme) 24 5 Roskilde – Lejre Electrification Preparation 4 weeks 2nd half TBD In possession of both tracks Rail Net Denmark 2018 (simultaneous with #23) (Electrification Programme) 25 5 Tølløse – Holbæk Electrification Preparation 6 weeks 2nd half TBD Possession of both tracks Rail Net Denmark 2018 (Electrification Programme) 26 5 Roskilde – (Lejre) Signalling Roll-out 3 2 weekends 1st half TBD Total possession of Roskilde and Rail Net Denmark Programme Installation, testing and 2018 therefore no operations possible (Signalling Programme) Fjernbane East Startup of switchdrive in between Roskilde and neighboring Roskilde stations. 27 10 Hellerup - Helsingør Renovation and 6 weeks Summer School Possession of both tracks. Rail Net Denmark replacement of bridges and summer There will be periods, where switches break cannot turn in Snekkersten. 28 6 København Kh-Rg, Ig Safety usage. 4 days Easter 29/3 - 1/4 Possession of all tracks between Rail Net Denmark (High speed G/Kalvebod – Hvidovre Mounting of switches, København G and Vigerslev, line Copenhagen - Ringsted) 11 fjern spsk 21 and track towards Vigerslev and Hvidovre Fjern Kjn switch spsk 20, 19b Kalvebod – Vigerslev 1–2 hsp

29 6 København Kh-Rg, Ig Mounting of switches, 2 + 2 days 10/2 - 11/2 Possession of both tracks between Rail Net Denmark (High speed G/Kalvebod – Hvidovre track 21 and 22 in 24/2 - 25/2 København G and Vigerslev, line Copenhagen - Ringsted) 11 fjern Vigerslev, moving safetyhut Vigerslev and Hvidovre Fjern # 8 Kalvebod – Vigerslev 1–2 hsp 30 6 København G – Kh-Rg, Ig Mounting of switches, track 19 days 9/3 - 28/3 Possession of Hvidovre fjern – Rail Net Denmark (High speed Hvidovre fjern 31, 32 Vigerslev and Vigerslev track 1, also line Copenhagen - Ringsted) 11 Partially removal of track 1 Vigerslev – Kalvebod 1 hsp

Network statement 2018 – Appendix 3.5A 9

# TIB Line Project name Description Expected Expected Expected dates Traffical consequenses Building contractor duration period 31 21 (Odense) - Svendborg Signalling Roll-out 10 Approx. 30 Q1, Q2 TBD Possession of all tracks at Rail Net Denmark Programme Replacement, testing and weekends and Q3 relevant workstations (Signalling Programme) Fjernbane East Startup of 30 junction. Construction Div. on Svendborgline, exchanging all switchdrives, testing and Startup 32 24 Langå - Hobro Electrification: Bridge 20998, km 168.68 3 weeks + 6 TBD TBD Possession of all tracks between Rail Net Denmark Preparational Viborgroad weeks Langå and Hobro for to periods (Electrification Programme) activities

33 24 Langå - Hobro Electrification: Bridge 21004, km 169,23 3 weeks TBD TBD Possession of all tracks between Rail Net Denmark Preparational Langå and Hobro. Lowering of (Electrification Programme) activities track over 480 meters

34 24 Langå – Aalborg Lg-Hb Replacement of 27 switces 1 weeks Summer Possession of all tracks between Rail Net Denmark (Track 77,3 km trackexchange Langå-Skørping West) 70,4 km sleeperexchange 91,1 km ballastcleaning New safetyConstruction Div. Rd Upgrade of ebilockConstruction Div. Rebuilding of 3 junctions Draining etc. 35 24 Langå – Aalborg Lg-Hb Replacement of 27 switces 4 weeks Summer Possession of all tracks between Rail Net Denmark (Track 77,3 km trackexchange (Before/af Langå-Hobro West) 70,4 km sleeperexchange ter 91,1 km ballastcleaning abovemen Platforms tioned – New safetyConstruction in total 4 Div. Rd weeks) Upgrade of ebilockConstruction Div. Rebuilding of 3 junctions Draining etc.

Network statement 2018 – Appendix 3.5A 10

# TIB Line Project name Description Expected Expected Expected dates Traffical consequenses Building contractor duration period 36 24 Langå – Aalborg Lg-Hb 77,3 km trackexchange 27 weeks Before/aft Single track operation on parts of Rail Net Denmark (Track 70,4 km sleeperexchange er the line between Langå og Hobro. West) 91,1 km ballastcleaning abovemen LA80 in neighboring track when Platforms tiod work in progress New safetyConstruction Div. Rd Upgrade of ebilockConstruction Div. Rebuilding of 3 junctions Draining etc. 37 24 Langå -Randers NFBR0379 Replacement of 10 days Summer TBD Possession of all tracks between Rail Net Denmark (Bridges) trackcarrying bridge across Langå and Randers. In the same stream period as #39 38 24 Langå -Randers NFBR0379 Reisolation and 21 days Summer TBD Possession of all tracks between Rail Net Denmark (Bridges) replacement of railing on Langå and Randers trackcarrying bridge 39 24 (Hobro) – Skørping Signalling EDL West 1 weekend 2nd half TBD Possession of all tracks between Rail Net Denmark (Signalling Programme Startup 2018 Hobro and Skørping Programme) Fjernbane West 40 24 Skørping – Lindholm Signalling EDL West 1 weekend 2nd half TBD Possession of all tracks between Rail Net Denmark (Signalling Programme Startup 2018 Skørping and Lindholm Programme) Fjernbane West 41 24 Hobro – Lindholm Signalling EDL West 3 weekends TBD Possession of all tracks between Rail Net Denmark (Signalling Programme Trial Run Hobro and Lindholm Programme) Fjernbane West 42 24 Skørping Signalling EDL West 5 days 2nd half TBD Due to the transition to the new Rail Net Denmark (Signalling Programme Startup 2018 signalling system, turnarounds in Programme) Fjernbane West Skørping will be unavailable for 5 days 43 25 (Hjørring) - (Strandby) Signalling EDL West 6 weekends Q1-Q2 TBD Possession of all tracks between Rail Net Denmark Programme Trial Run Sindal and Frederikshavn, no (Signalling Programme) Fjernbane West operations available 44 25 Vrå - Lindholm Signalling EDL West 4 weekends Q1-Q3 TBD Possession of all tracks between Rail Net Denmark Programme Trial Run Lindholm and Vrå, no operations (Signalling Programme) Fjernbane West possible 45 25 Aalborg - Lindholm Signalling EDL West 5 weekends TBD TBD Possession of all tracks between Rail Net Denmark Programme Startup Aalborg and Lindholm, no (Signalling Programme) Fjernbane West operations possible. (To be carried out simultaneously with Skørping – Aalborg) 46 25 Skagen – Signalling EDL West 14 days Q2-Q3 TBD Up to 14 days with closed circuit Rail Net Denmark (Signalling Frederikshavn Programme Startup to/from Skagen before Programme) Fjernbane West startupweekend

Network statement 2018 – Appendix 3.5A 11

# TIB Line Project name Description Expected Expected Expected dates Traffical consequenses Building contractor duration period 47 25 (Strandby) – Vrå Signalling EDL West 5 days Q2-Q3 TBD Possession of track between Fh Rail Net Denmark (Signalling Hjørring – (Tornby) Programme Startup and Vr. Both stations incl. Programme) Fjernbane West 48 25 Vrå -Lindholm Signalling EDL West 4 days Q2-Q3 TBD Possession of track between Vrå Rail Net Denmark (Signalling Programme Startup and Lindholm. Both stations incl. Programme) Fjernbane West 49 32 Langå - Struer Signalling Roll-out 05 West 3 weekends 2nd half TBD Possession of all tracks between Rail Net Denmark Programme Installation, testing 2018 Langå and Struer (Langå exc), no (Signalling Programme) Fjernbane West operations possible 50 32 Viborg Ny Hærvejsbro New bridge across tracks. 5 days Q2 Apr/may Possession of both tracks Viborg Municipality (3rd (perhaps 7 party) days) 51 32 Viborg Ny Hærvejsbro New bridge across tracks 3 days Q3 Aug/sept. Possession of both tracks Viborg Municipality (3rd party) 52 32 Viborg Ny Hærvejsbro New bridge across tracks Night / May- Ad hoc Possession of one track ,crossing Viborg Municipality (3rd Weekends november not possible party) 53 34 Struer - Thisted Signalling Roll-out 08 West 6 weekends 2nd half TBD Possession of all tracks between Rail Net Denmark Programme Installation, testing and 2018 Struer and Thisted (Struer excl) (Signalling Programme) Fjernbane West Startup no operations possible

Network statement 2018 – Appendix 3.5A 12

S-train line Network Statement 2018

København H

Lyngby

Østerport –

Gentofte – Lyngby

Valby – Frederikssund

Buddinge

Dyssegård – Buddinge

Svanemøllen – Klampenborg/Hillerød

Nordhavn – Farum

Network statement 2018 – Appendix 3.5A 13

# TIB Line Project name Description Expected Expected Expected dates Traffical consequenses Building contractor duration period 54 810 København Tietgensbroen Durability of bridge extended 2 x 14 days TBD Only 3 available tracks at Rail Net Denmark (Tietgens Bridge) by approx. 40 years (One track at København H (Copenhagen (Construction Div.) track 9+10 a time) Central Station) 55 820 Lyngby Light Rail at Ring 3 Establishing new tunnel for the Track 1 and 2 June- TBD Trains to Holte and Hillerød Greater Copenhagen Light Rail under Nordbanen blocked for 90 August will use track 3 in both Light Rail (3rd party) (part 1) - new platformtunnel days directions. Track 1 and 2 can (top-down spunstunnel) on be used to turn around from the new trains from København lightrailplatform on Lyngby St. 56 820 Lyngby Light Rail at Ring 3 Establishing new tunnel for the Track 3 Septem- TBD Only traffic in track 1 and 2 Greater Copenhagen Light Rail under Nordbanen blocked in ber - for 100 days Light Rail (3rd party) (part 2) 100 days December 57 820 Østerport – Holte Traction Renewel of tractioncurrent 2 weekends 2018 TBD Possession of both tracks Rail Net Denmark Østerport – Holte Construction Div. both tracks and reduced traffic on (Construction Div.) blocked + 10 Nordbanen plus alle weekends neighboring lines to Hellerup reduced traffic 58 820 Gentofte – Lyngby Bridges at Reparing, enforcement and 1 weekend + Spring/su 18/5-21/5, 1 weekend; possession of Rail Net Denmark Ermelundsvej og surfacetreatment etc. 21 days + 10 mmer 11/6-1/7, both lines + single track (Construction Div.) Lyngby Hovedgade Replacement of overhead lines days + 14 2/7-11/7, operations for 21 days, days 12/7-25/7 possession of both tracks in 10 days, 14 days of single track operations 59 830 Valby – Frederikssund Trackrenewal, - Trackrenewal Easter + 2018 28/3-3/4, Possession of both tracks Rail Net Denmark Frederikssunds- - Bridge maintenance Whitsunday + 26/4-30/4, (excl. 42) (Construction Div.) banen - Vinge St. 12 May + 9/5-14/5, Vinge Station Ascension Day 18/5-22/5 + 12 weeks + 1/6-30/8 Week 42 12/10-22/10 60 840 Buddinge Light Rail at Ring 3 Establishing new Track 2 2018 TBD H Line cancelled between Greater Copenhagen pedestriantunnel under possession for Østerport and Farum. 20 Light Rail (3rd party) Farumbanen 15 days min-operation north of Kildebakken Station 61 840 Buddinge Light Rail at Ring 3 Establishing new Track 1 2018 TBD H Line cancelled between Greater Copenhagen pedestriantunnel under possession for Østerport and Farum. 20 Light Rail (3rd party) Farumbanen 15 days min-operation north of Kildebakken Station 62 840 Dyssegård – Buddinge Gentofte-renden Establishing new sewerage 6½ days Easter Possession of both tracks Nordvand A/S (3rd party) pipelines under Farumbanen

Network statement 2018 – Appendix 3.5A 14

# TIB Line Project name Description Expected Expected Expected dates Traffical consequenses Building contractor duration period 63 820 Hillerød – Svanemøllen Signalling Startup af RO2 1 weekend Q2 TBD Possession of both tracks. Rail Net Denmark Klampenborg - Programme Currently examing if 860 Svanemøllen possession between Jægersborg-Hillerød can be avoided, fully or partially 64 840 Farum – Nordhavn Signalling Test of RO3.1 2 weekends One in TBD Possession of both tracks Rail Net Denmark Programme Q2, one TBD

Network statement 2018 – Appendix 3.5A 15

Misc. possessions not covered by the NS *

TIB Line Project name Description Expected Expected Expected dates Trafical consequenses Building contractor duration period 6 København G – Hvidovre Kh-Rg, Ig Rebuilding overhead lines 33 nights 15/1-8/3 Systempossession at Rail Net Denmark (High fjern Vigerslev speed line Copenhagen - Ringsted) 6 København G/Kalvebod Kh-Rg, Ig 1/4 – 31/12 Only 1 track open for Rail Net Denmark (High – Hvidovre fjern thoroughfare at Vigerslev speed line Copenhagen - 11 Ringsted) 6 København G/Kalvebod Kh-Rg, Ig Removal of bridge over 8 hours ( 27. or 28/4 Possession of track 2 Rail Net Denmark (High – Hvidovre fjern Vigerslev Alle 29.) speed line Copenhagen - 11 Ringsted) 32 Langå – Struer Ny Hærvejsbro New bridge across the tracks Night/Weeke May-nov. Ad hoc Possession of one track, Viborg Municipality (3rd Viborg St km 40,4 nd Crossing not possible party)

* known at the date of publishing

Network statement 2018 – Appendix 3.5A 16