The Singareni Collieries Company Limited (A Government Company) 2 x 600 MW Singareni Thermal Power Plant Jaipur (V&M), Pin: 504 216, District, .

Ref: STPP/ENV/ 637/828 Date: 18.04.2018

To The Director (IA Division), Thermal Projects, Vayu Wing, Ministry of Environment, Forest and Climate Change, Indira Paryavaran Bhavan, Jor Bagh Road, Jor Bagh, New Delhi – 110 003.

Sir,

Sub: Point-wise reply for Essential Details Sought on Dt.12.04.2018 for the proposed expansion from 2x600 MW to 2000 MW (2x600 + 1x800MW) of Coal based Singareni Thermal Power Plant at Pegadapalli Village, Jaipur Mandal, in Telangana State by M/s Singareni Collieries Company Limited – Reg.

Ref.: Essential Details sought (EDS) for the above proposal on 12.04.2018 by e-mail. xxx

With reference to the above, EDS was raised based on the application made for issue of EC for the proposed expansion of STPP from 2x600 MW to 2000 MW (2x600 + 1x800MW Super Critical) coal based Singareni Thermal Power Plant vide e-mail dated 12.04.2018.

The point wise replies for EDS are prepared and uploaded in the website. SCCL intends to implement this project in a fast track mode and hence it is requested to consider the proposal for an early issue of Environmental Clearance for the proposed expansion.

Thanking You

Yours faithfully,

Director (E&M) Point wise replies for EDS pertaining to the Proposed Expansion of STPP (from 1200 MW to 2000 MW by adding 1x800 MW Super-Critical)

S. No. Essential details sought by Information by SCCL MS

i. Project Feasibility Report The Pre-Feasibility Report of the Project is attached as Annexure – E1.

ii. Sections of EIA report along Sections along with Page numbers in the EIA with page numbers to be report are furnished against each condition referred in each condition mentioned in the ToR compliance report and mentioned in the ToR revised ToR compliance is attached as compliance report. Annexure – E2.

iii. Upload ToR amendment The ToR amendment Dt.26.09.2017 along dated 26.9.2017 along with with main ToR issued on 27.05.2015 is the ToR. attached as Annexure – E3.

iv. Compliance to the EC The point wise compliance of additional amendment letter dated conditions given in EC Amendment dated 10.8.2016 shall be 10.08.2016 for existing 2x600 MW STPP is submitted. given as Annexure – E4.

v. Compliance status for All necessary measures have been taken to implementation of Revised follow revised emission standards and the emission standards dated Compliance status for implementation of 7.12.2015 for the existing revised emission standards Dt.07.12.2015 for power plant and proposed the existing and proposed power plant is project. enclosed as Annexure – E5.

vi. Submit the corrective action The corrective action plan report for non- taken report for non- compliance reported in the certified RO compliances reported by the compliance report on EC conditions vide certified RO compliance dated: 31.10.2017 is given as Annexure – report on EC conditions vide E6. dated 31.10.2017.

vii. Details of project affected Entire land (428.28 Ha.) has been acquired population with enumeration following due process during establishment of those losing of existing 2x600 MW STPP and for the houses/dwelling units, proposed expansion project no additional agricultural lands and land has been acquired. Hence, there are no project affected population losing landless laborers/artisans. houses/dwelling units, agricultural lands and landless laborers/artisans. viii. Baseline data of 104 Commercial operation of unit-1 & 2 of STPP readings a year for relevant are made on 25.09.2016 & 02.12.2016 parameters of Ambient Air respectively. The post project monitoring for Quality. STPP is being carried out twice in a week for AAQ from October 2017 onwards by awarding a fresh tender for PPEM exclusively for STPP.

But, from January 2017 to September,2017, the post project monitoring was carried out twice in a month for AAQ as per the then existing frequency till completion of the order which was awarded for post project monitoring work combinely along with coal mining projects in the area. i.e. up to September, 2017 only. As such the AAQ data from January 2017 to March, 2018 is given as Annexure – E7.

ix. Baseline data for Hg. As per baseline data collected during October 2017 to December 2017 the mercury content in ambient air quality locations was found to be below detectable limit. The mercury content was also found to be Below detectable limit in the coal samples of SCCL mines which are supplying coal to STPP. The coal analysis report is enclosed as Annexure – E8.

x. Status and progress of 10 Status of railway is from Srirampur CHP to km railway line from STPP is enclosed as Annexure – E9. Srirampur CHP

Director (E&M) SCCL PRE-FEASIBILITY REPORT For THE PROPOSED EXPANSION OF SINGARENI THERMAL POWER PLANT (From 1200 MW to 2000 MW by adding 1x800 MW) at Pegadapalli Village, Jaipur Mandal, Mancherial Dist, Telangana State

Submitted to Ministry of Environment, Forests & Climate Change (MoEF&CC), Government of , Indira Paryavaran Bhavan, Jorbagh, Jorbagh Road, New Delhi

Project Proponent

THE SINGARENI COLLIERIES COMPANY LIMITED

(A Government Company) P.O. Kothagudem Collieries - 507 101 District: Telangana State August 2017 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW) INDEX

S. No. Description Page No. 1 Executive Summary 1-4 2 Introduction of the Project / Background information 2.1 Identification of Project and Project Proponent 5 2.2 Brief description of nature of the project 6 2.3 Need for the Project and its Importance to the Country and or Region 6 2.4 Demand – Supply Gap 7 2.5 Imports Vs Indigenous Production 8 2.6 Employment Generation (Direct & Indirect) 8 3 Project Description Type of Project including interlinked and interdependent projects if 3.1 8 any Details of alternate sites considered and the basis of selecting the 3.2 proposed site, particularly the environmental considerations gone into 13 should be highlighted 3.3 Size or Magnitude of operation 13 3.4 Project Description with process details 13 Raw material required along with estimated quantity likely source, 3.5 marketing area of final products, mode of transport of raw material 14 and finished product Resource Optimization Recycling & Reuse envisaged in the project, if 3.6 15 any, should be briefly outlined) Availability of water its source, energy/power requirement and source 3.7 15 should be given 3.8 Energy / Power requirement and source 16 4 SITE ANALYSIS 4.1 Infrastructure 16 4.2 Connectivity 16 4.3 Land Details 17 Existing land use pattern, shortest distance from the periphery of the 4.4 17 project to periphery of the forests, water bodies 4.5 Soil Classification 18 4.6 Climatic Data from Secondary Sources 18 4.7 Social Infrastructure available 18 5 Planning Brief 5.1 Planning Concept 19 5.2 Population Projection 19 5.3 Land use planning 20 5.4 Assessment of Infrastructure Demand (Physical & Social) 20 5.5 Amenities / Facilities 20 6 Proposed Infrastructure 6.1 Industrial Area 20

THE SINGARENI COLLIERIES COMPANY LIMITED i Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW) 6.2 Residential Area 21 6.3 Green Belt 21 6.4 Social Infrastructure 21 6.5 Connectivity 21 6.6 Drinking Water Management 21 6.7 Sewage System 21 6.8 Industrial Waste Management 21 6.9 Solid Waste Management 22 6.10 Power Requirement & Supply 22 7 Rehabilitation & Resettlement Plan 22 8 Project Schedule & Cost Estimates 22 8.1 Likely date of start of construction and likely date of completion 22 Estimated Project cost along with analysis in terms of economic 8.2 22 viability of the project 9 Analysis of proposal 9.1 Project cost estimates and financial analysis 24 Financial and social benefits (With special emphasis on the benefit to 9.2 24 the local people including tribal population, if any, in the area) Location plan 25 Plates Topo Sheet 26 Plant layout 27

THE SINGARENI COLLIERIES COMPANY LIMITED ii

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

1. Executive Summary: Singareni Collieries Company Limited (SCCL) is proposing to set up a 1x800 MW (additional unit) besides the 2x600 MW units already in operation. The third unit of 1x800 MW will be constructed as an expansion project and will be located adjacent to already constructed and in operation of Stage-I (2x600 MW) units. The project site is located near Pegadapalli Village, Jaipur Mandal, and District Mancherial of Telangana. The proposed site is situated between 18°48’30” to 18°50’35” Northern latitude and between 79°34’00” to 79°35’30” Eastern longitude. The site is 14.6 km from nearest town Mancherial and 4.6 km from the Rajiv Rahadari and 500 meters from NH-63. The proposed project falls under the category ‘A’ of Project Activity 1(D) under the schedule as per EIA notification issued on 14th September, 2006 and hence the proposed expansion of the project requires Environmental Clearance from MoEF&CC, Govt. of India. The salient features of the proposal are as follows: Total Existing ToR issued Proposed (after expansion) S.No Description (a) (b) (c) (a+c) 1. Plant 2x600 MW 1x600 MW 1x800 MW 2000 MW Configuration (2x600+1x800) 2. Land requirement, 300.972 105.21 127.31 428.28 Ha 3. Forestland Nil Nil Nil Nil involved 4. R&R Involved Nil Nil Nil Nil

5. Water allocation 1.05 TMC per From From Pranahitha From Godavari annum during Godavari and River and Pranahitha lean period Pranahitha River from River River Godavari and 2.0 TMC from River Pranahitha as main source sanctioned by State Government 6. Coal Supply Naini coal Naini coal Naini coal block Naini coal block block was block was was allocated for was allocated for allocated for allocated for STPP. Expected STPP. Expected STPP. STPP. coal production is coal production Expected coal Expected coal 2020. MoC was is 2020. production is production is requested for Meanwhile MoC 2020. 2020. MoC grant of bridge has granted Meanwhile was requested linkage for use of bridge linkage MoC has for grant of coal from SCCL for its 2x600 granted bridge bridge linkage mines. MoC MW. SCCL linkage for use for use of coal during its meeting made a request of coal from from SCCL advised SCCL to MoC to SCCL mines mines that the issue will consider the be discussed in required coal for

THE SINGARENI COLLIERIES COMPANY LIMITED 1

Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Total Existing ToR issued Proposed (after expansion) S.No Description (a) (b) (c) (a+c) the next SLC 1x800 MW meeting. under bridge linkage from SCCL mines. 7. Coal Transport Through Through Rail Through Rail Through Rail Rail/Trucks 8. Man Power 700 100 450 1150 requirement 9. Capital Cost in Rs. 7573.51 3570.20 5879.62 13453.13 Crores 10. Power Evacuation Through 440 Through 440 Through 440 KV Through 440 KV KV system KV system system system 11. Boiler Boiler type Sub-critical Sub-critical The boiler shall - pulverized pulverized fuel, be Super-Critical, fuel, coal coal fired unit once through, fired unit to to produce water tube, direct produce sub- sub-critical pulverized coal critical steam steam fired, suitable for parameters parameters outdoor installation.

Capacity (TPH) 2050 2050 2690 2690 Main Steam 175 175 275 - Pressure (bar) Main Steam 540 540 603 - Temperature, ˚C Efficiency, % 87 86 During detailed - engineering 12. Turbine Heat Rate, 1935 1935 During detailed - K.Cal/KWH engineering Exhaust Pressure, 0.1047 0.1047 77 mm Hg (a) - ata Exhaust 40 40 During detailed - Temperature, 0C engineering Station Heat Rate, 2425 2351 2250 - KCal/KWh 13. Generator MW Capacity, MW 2x600 1x600 1x800 2000 (2x600+1x800) Generator 3 Nos. single phase Transformers - Transformer Type 3 x 1 Phase 3 x 1 Phase Power - Transformer (OFAF) MVA 260 260 315 - Voltage Ratio, KV 21.5/400 21.5/400 22/400 - Unit Transformer 2 nos. for 2 nos. 2 nos. - (UT) each unit MVA 31.5 31.5 63 -

THE SINGARENI COLLIERIES COMPANY LIMITED 2 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Total Existing ToR issued Proposed (after expansion) S.No Description (a) (b) (c) (a+c) Voltage Ratio, KV 400/21.5 400/21.5 22/11.5 - Station 2 Nos. 1 No. 2 nos. - Transformer MVA 100 each 50 130 - Voltage Ratio, KV 400 / 11 400 / 11 400 / 11 - 14. Coal Handling Plant Track hopper, MT 6000 No additional No additional 6000 requirement requirement Crusher 4 Nos. No additional Separate 8 (770 TPH) requirement Crusher House (4 nos )

Paddle feeders 4 Nos. No additional No additional 4 (1050 TPH) requirement requirement Vibrating screen 4 nos. No additional 4 nos. Separate 8 feeders (770 TPH) requirement Wagon tippler - 1 No. proposed 2 nos. proposed 2 All conveyors 1400 mm To be Provision for - wide extended interconnection (1400 TPH) between Stage-1 and Stage-2 Stacker Reclaimer 2 Nos. 1 No. of 1 No. - (1400 TPH) suitable (1750 TPH) capacity Coal requirement, 625 310 514 - TPH (Heat Rate – (Heat Rate – (Heat Rate – 1935 1935 2250 KCal/KWh, KCal/KWh, KCal/KWh, GCV of Coal - GCV of Coal GCV of Coal – 3500( KCal/Kg) – 4529 4529 ( KCal/Kg) ( KCal/Kg)

15. Fuel Oil Storage Capacity LDO, Cu.m. 2x500 No additional No additional 1000 requirement requirement HFO, Cu.m. 2x2000 No additional 1x2000 6000 requirement 16. Ash Handling System BA HP water 2 nos. 2 nos. 2 nos. 4 nos. pumps (W- (1W+1S) (1W+1S) (1W+1S) (2W+2S) working, S- Standby) Capacity, m3/hr 465 250 760 1225 BA LP water 3 Nos. 2 Nos. 2 Nos. 5 Nos. pumps (2W+1S) (1W+1S) (1W+1S) (3W+2S) Capacity, m3/hr 600 300 940 1540 Fly Ash main SILO 4 Nos. 2 Nos. During detailed - engineering

THE SINGARENI COLLIERIES COMPANY LIMITED 3 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Total Existing ToR issued Proposed (after expansion) S.No Description (a) (b) (c) (a+c) Capacity, MT 4 x 900 900 During detailed - engineering HCSD silo 3 Nos. No additional During detailed - requirement engineering Capacity, MT 500 Not applicable During detailed - engineering Ash dyke area, Ha 30 52.61 59.44 89.44 17. Water Pumps Details Raw water source from Rivers Godavari near Shetpalli village & Pranahitha near Devulawada Village, Mancherial Water allocation 1.05 TMC per No additional 2.00 TMC per 2 TMC per annum during requirement annum annum from lean period sanctioned by River Pranahitha from River State Godavari and Government 2.0 TMC from River Pranahitha as main source sanctioned by State Government No. of VT pumps, 2+1 No additional 3+1 3+1 W- working, S- (W+S) requirement (W+S) (W+S) standby Rating, KW 685 Nil 1050 1050 Flow, m3/hr 2916 - 2592 2592 Quantity of water 1.01 - 2.00 2.00 to be pumped, TMC Plant Reservoir 25 No additional 25 25 Capacity, L.Cu.m. (0.089 TMC) requirement (0.089 TMC) (0.089 TMC) 18. Date of Unit:1 – 39 50 months 50 months from 50 months from Commissioning Months from zero date zero date zero date (COD) done on 25.09.2016 Unit:2 – 43 Months (COD) done on 02.12.2016

THE SINGARENI COLLIERIES COMPANY LIMITED 4 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

2. INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION 2.1 Identification of Project and Project Proponent The Singareni Collieries Company Limited (SCCL) is a Government Company jointly owned by the Government of Telangana and Government of India on a 51:49 equity basis. The Singareni coal reserves stretch across 350 km of the Pranahita – Godavari valley of Telangana with a proven geological reserves aggregating to 8791 MT The studies of Geological Survey of India attribute as much as 22207 million tonnes of coal reserves in the Godavari valley coalfield. The inventory covers up to a depth of 1200 meters and it includes reserves proved, indicated as well as inferred. The SCCL has been exploiting coal for more than 127 years the Company had expanded its mining activities in Mancherial, Komaram Bheem Asifabad, Peddapalli, Jayashankar Bhoopalpalli, Bhadradri Kothagudem and Khammam districts of Telangana. The coal produced by SCCL in the Godavari valley coalfield in the year 2016-17 was 61.34 Million tonnes. The targeted production for the year 2017-18 is 66.06 Million tonnes.

SCCL also operating small captive power plants since 1960 and recently SCCL is foraying into large scale power generation. SCCL constructed Non pithead power station of 2x600 MW units located at Pegadapalli village, Jaipur Mandal in Mancherial district of Telangana which is commisioned in the year 2016.

The Environmental Clearance was accorded by Ministry of Environment, Forest and Climate Change vide Lr. No. J-13012/88/2008-IA.II (T), dated 27.12.2010 and Consent for Establishment (CFE) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by State Pollution Control Board vide Order No. 64/PCB/CFE/RO- NZB/HO/2010-818, dated 16.06.2011 and Consent For Operation (CFO) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by State Pollution Control Board vide Order No. TSPCB/CFO/NZBG/HO/2017-42,Dt.04.04.2017 and valid up to 30.04.2022 under Auto Renewal for the 2x600 MW Thermal Power Plant which is under Operation. In view of the power crisis in the newly formed state of Telangana, State Government vide letter dated 16.03.2017 accorded approval for setting up 1x800 MW as expansion and directed the SCCL to establish one more unit of 1x800 MW in addition to 2x600 MW Thermal Power Plant.((From 1200 MW to 2000 MW by adding 1x800 MW)

As SCCL is already constructed 2x600 MW units and are in operation, some of the BOP facilities of these units have spare capacities which can be utilized for the proposed 1X800 MW unit. The review of existing system reveals their adequacy for the proposed additional unit. The spare capacities of the existing system have been worked out after meeting the requirements for the 2x600 MW units in operation.

Infrastructure facilities such as land, water transport arrangements, railway line, roads etc. are available. The advantages of proposing the additional unit at same location are:  No new infrastructure facilities are required for expansion unit.  Total required land is available with SCCL.  No Re-settlement is involved.  Availability of adequate raw water from Pranahita River.  Water will be pumped through the existing pipe line and pump house.  There is no forest land involved for the project.  Since existing facilities are being used, cost of the power would be less.

Address of the Project Proponent Director (E&M) The Singareni Collieries Company Limited Po:Kothagudem, PIN. Code: 507101 Dist: Bhadradri Kothagudem, Telangana State e-mail id: [email protected] Ph.No. 08744 – 245005; Fax No. 08744 – 241201

THE SINGARENI COLLIERIES COMPANY LIMITED 5 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Address of the Project In-charge/Occupier. Executive Director, Singareni Thermal Power Plant Pegadapalli Village, Jaipur Mandal, PIN Code: 504 216 Dist: Mancherial, Telangana State e-mail ID: [email protected] Ph. No. 08737-243243

2.2 Brief Description of the Nature of the Project

Singareni Collieries Company Limited (SCCL) is proposing to set up Singareni Thermal Power Plant by adding Stage-II 1x800 MW as expansion of 2x600 MW units already in operation, as per the directions of State Government in view of the acute power shortage in the state of Telangana. The third unit of Stage-II (1X800 MW) will be constructed as an extension project and will be located adjacent to the operating units. SCCL has obtained Environmental Clearance from MoEF&CC, New Delhi for establishing 2x600 MW coal based TPP of the Singareni Collieries Company Limited (SCCL) at Pegadapali Village, Jaipur Mandal, Mancherial District, Telangana State vide MoEF&CC lr. No. J- 13012/88/2008-IA.II (T), dated 27.12.2010 and amendment to EC was obtained vide MoEF&CC lr. No. J-13012/88/2008-IA.II(T), dated.10.08.2016. Consent for Establishment (CFE) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by State Pollution Control Board vide Order No. 64/PCB/CFE/RO-NZB/HO/2010-818, dated 16.06.2011 and Consent for Operation (CFO) under Air (Prevention & Control of Pollution) Act and Water (Prevention & Control of Pollution) Act by Telangana State Pollution Control Board vide Order No.TSPCB/CFO/NZBG/HO/2017- 42,dt.04.04.2017 and valid upto 30.04.2022. Presently, 2x600 MW TPP is in operation.

Present Proposal: Present proposal is amendment to ToR issued vide MoEF&CC lr. No. J-13012/08/2015-IA.I(T), dated.27.05.2015 for expansion of Singareni Thermal Power Plant (From 2x600 MW to 2000 MW by adding 1x800 MW) at Pegadapalli village, Jaipur Mandal, Mancherial District of Telangana State by M/s Singareni Collieries Company Limited.

2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR REGION POWER SCENARIO OF TELANGANA STATE - POWER SUPPLY SCENARIO As per the report “Power for All – Telangana State” A joint initiative of Govt. of India and Govt. of Telangana State, energy deficit in Telangana for last year’s was in the range of 4%-12%. Energy requirement in Telangana was 50,916 MU in FY 14-15, of which only 2,128 MU could not be met resulting in an energy deficit of nearly 4.2% with a maximum historic peak demand of 8,331 MW in 2014-15.

As can be seen from the table below, peak demand has increased by over 2,588 MW during the period FY 2008-09 till FY 2014-15 as against which peak met has increased by 1,345 MW.

THE SINGARENI COLLIERIES COMPANY LIMITED 6 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

2.4 Demand – Supply Gap

Historical Power Supply Position in Telangana State Period Peak Peak Peal Peak Energy Energy Energy Energy Deficit Deficit Dema Met Deficit Deficit/ Requir Availabili (MU) (-/+) Surplus (-/+) (MWnd ) (MW) / Surplus ement ty (MU) Surplu (%) (- (MU) s(MW) /+) ( -/+) 2008-09 5,743 5,303 -0.440 -8% 31,883 30,348 -1,535 -4.8% 2009-10 6,263 5,655 -0.608 -10% 34,808 32,752 -2,055 -5.9% 2010-11 6,600 6,239 -0.361 -5% 36,490 35,802 -0.688 -1.9% 2011-12 6,866 6,461 -0.405 -6% 47,987 45,312 -2,675 -5.6% 2012-13 6,741 6,317 -0.424 -6% 48,758 42,942 -5,816 -11.9% 2013-14 7,876 7,177 -0.699 -9% 47,428 44,946 -2,482 -5.2% 2014-15 8,331 6,648 -1.683 -20% 50,916 48,788 -2,128 -4.2% There was a 11% increase in the peak deficit in FY 2014-15 over FY 2013-14 attributable to the increased agricultural loads whereas the energy deficit has decreased by 1% attributable to the extensive short term market purchases which contributed to 21% of the total power purchased in FY 2014-15. Implementation of 24X7 supply across the State is likely to increase the electricity consumption substantially. Various factors that have been considered for future energy projections include:  Demand from Domestic segment  Agriculture supply from 7 hours to 9 hours in a day  Implementation of Lift Irrigation Schemes  Urban development in cities of Hyderabad, Warangal, Nizamabad and Karimnagar.  Upcoming major projects such as Hyderabad Metro Rail, Hyderabad ITIR region  Upcoming Bayyaram Steel Plant.  Existing Generation Capacity  Energy availability from existing sources as on FY 2014-15 was about 48,788 MU inclusive of market purchases and coal based power from long-term sources constituted nearly 66% of energy availability. PPAs due to expire in the next 5 years Some of the existing PPAs of TSDISCOMS with generators would expire during the next 10 years. Currently, Telangana is entitled to 53.89% of power from TSGENCO and APGENCO stations. Post expiry of PPA, no capacity would be available from APGENCO stations while 100% capacity of TSGENCO plants would be available to Telangana. This project (Singareni TPP Stage-II) has already been identified in the referred report while calculating the generation capacity and meeting the required supply of power against the demand to energize the power thirsty & development oriented newly formed Telangana State. Considering above facts & data, it is prudent to go for a coal based supercritical unit of 1X800MW utilizing the space available and the facilities of Stage-I.

2.5 Imports Vs Indigenous Production The entire saleable power from the project will be procured by TSTRANSCO independent consumers by utilizing the 400 kV power transmission grids being managed by TSTRANSCO. The saleable power from the additional unit will be of the order of 754 MW after accounting for

THE SINGARENI COLLIERIES COMPANY LIMITED 7 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

auxiliary power consumption of 5.75%.The total salable power from the entire 2X600 MW &1X800 MW will be 1885 MW to the TSTRANSCO.

Indigenous production of the power will be much cheaper, reliable and comfort than the import of the power from other states, The proponent is operating number of coal mines in the area of power plant there will not be any problem of supply of coal to the power plant.

2.6 Employment Generation (Direct & Indirect) due to the Project During the construction period the requirement of manpower will be about 2000 to 3000 persons on temporary basis. During Operational phase, direct employment for 1550 persons (1100 for 2x600 MW and 450 for additional 1X800 MW) will get and about 1000 persons will get indirect employment.

3 PROJECT DESCRIPTION: 3.1 Type of Project including interlinked and interdependent projects if any:

Expansion of 2x600 MW Coal Based Singareni Thermal Power Plant with 1x800 MW. Ultimate capacity of the station would be 2x600MW + 1x800MW i.e. 2000MW. a. Location: The present proposal is for setting up of one unit of 1X800 MW Thermal Power Plant besides the 2x600 MW units already in operation at Pegadapalli Village, Jaipur Mandal of Mancherial District in Telangana State. The plan showing plant location ,mines from which coal is proposed to supply and water source is enclosed as Annexure-I The details of the Location are as follows:

Location Details of the Project Village : Pegadapalli Tehsil : Jaipur District : Mancherial State : Telangana Latitudes : N 18° 48’ 30” and 18° 50’ 35” Longitudes : E 79° 34’ 00” and 79° 35’ 30” Survey of India Topo sheet No. : 56 N/9 Nearest Town : Mancherial (14.6 Km), NW Nearest City : Hyderabad (250 Km), SW District head quarters : Mancherial (14.6 Km), NW State capital : Hyderabad (250 Km), SW Mancherial Railway station at 14.6 Km (Nagpur- Nearest Railway Station : Kazipet main rail line of South-Central Railway) Rajiv Gandhi International Airport, Shamshabad, Nearest Airport : Hyderabad at a distance of 250 Km. Nearest Highway : Rajiv Rahadari State Highway (4.6 Km), W

THE SINGARENI COLLIERIES COMPANY LIMITED 8 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Co-ordinates of Main Plant and Ash Pond coordinates are as follows:

ID Latitude Longitude ID Latitude Longitude Existing 2x600 MW Plant Coordinates: A 180 48’57’’ 79034’10’’ J 180 50’22’’ 79035’14’’ B 180 49’12’’ 79034’09’’ K 180 50’10’’ 79035’10’’ C 180 49’15’’ 79034’21’’ L 180 50’00’’ 79034’58’’ D 180 49’45’’ 79034’21’’ M 180 49’20’’ 79034’56’’ E 180 49’45’’ 79034’53’’ N 180 49’09’’ 79034’56’’ F 180 49’57’’ 79034’53’’ O 180 49’06’’ 79035’14’’ G 180 49’57’’ 79034’40’’ P 180 48’42’’ 79035’14’’ H 180 50’21’’ 79034’39’’ Q 180 48’42’’ 79034’54’’ I 180 50’26’’ 79035’05’’ R 180 48’57’’ 79034’54’’ Existing 2x600 MW Ash Pond Coordinates: a 180 49’03’’ 79034’56’’ c 180 48’43’’ 79035’13’’ b 180 49’03’’ 79035’13’’ d 180 48’43’’ 79034’56’’ Proposed 1x600 MW Plant Coordinates: 1 180 48’57’’ 79034’54’’ 6 180 48’42’’ 79034’55’’ 2 180 48’52’’ 79034’54’’ 7 180 49’12’’ 79034’10’’ 3 180 48’42’’ 79034’15’’ 8 180 49’40’’ 79034’10’’ 4 180 48’57’’ 79034’15’’ 9 180 49’40’’ 79034’21’’ 5 180 48’57’’ 79034’55’’ 10 180 49’15’’ 79034’18’’ Proposed 1X600 MW Ash Pond Coordinates: 1 180 48’57’’ 79034’54’’ 3 180 48’42’’ 79034’15’’ 2 180 48’52’’ 79034’54’’ 4 180 48’57’’ 79034’15’’ Proposed 1x800 MW Plant coordinates: 1 180 48’57’’ 79034’54’’ 4 180 48’57’’ 79034’15’’ 2 180 48’52’’ 79034’54’’ 5 180 48’57’’ 79034’55’’ 3 180 48’42’’ 79034’15’’ 6 180 48’42’’ 79034’55’’

11 180 49’47’’ 79034’42’’ 13 180 49’48’’ 79034’70’’ 12 180 50’18’’ 79034’42’’ 14 180 50’17’’ 79034’71’’ Proposed 1X800 MW Ash Pond Coordinates: 1 180 48’57’’ 79034’54’’ 3 180 48’42’’ 79034’15’’ 2 180 48’52’’ 79034’54’’ 4 180 48’57’’ 79034’15’’

b. Land Requirement: Presently 2x600 MW Thermal Power Plant is in operation in Pegadapalli Village, Jaipur Mandal of Mancherial district of Telangana in an area of 280.40 Ha in addition to the railway line for coal transportation & water supply pipelines in an area of 20.572 Ha. The present proposal is for setting up of one more unit of 1x800 MW Thermal Power Plant besides the 2x600 MW units. Some of the facilities like Coal Handling arrangements, Raw Water Intake System, Raw Water Reservoir, Fuel oil unloading etc envisaged for 2x600 MW units can also be used for the proposed unit of 1x800 MW TPP. As such, an additional area required for 1x800 MW is 127.31 Ha. All the land required for plant under operation and proposed unit of 1x800 MW is available and under possession of Singareni Collieries Company Limited. No further land acquisition is envisaged in the present proposal.

THE SINGARENI COLLIERIES COMPANY LIMITED 11 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW) c. Water Requirement: The estimated water requirement for 2x600 MW plant under operation is 88,800 KLD (3700 m3/hr) and for additional unit of 1X800 MW is 48,000KLD (2000 m3/hr). Hence, Total Water required for 2000 MW (2x600 +1X800 MW) is 1, 36,800 KLD (5700 m3/hr). Total Existing ToR issued Proposed (after expansion) S. No Description 2x600 MW 1x600 MW 1x800 MW 2000 MW (c) (a+c) (a) (b)

1 Water 88,800 43,200 48,000 1,36,000 Requirement, KLD

2 Water 5700 1800 2000 Requirement, 3700 m3/hr State Government allocated vide G.O.Rt. No. 474, dated 19.07.2010 from River Pranahita 2.00 TMC near Devulawada Village, Mancherial District which will sufficient for total water requirement of 2000 MW. d. Fuel requirement:

Coal requirement: Total Existing ToR issued Proposed (after expansion) S.No Description 2x600 MW 1x600 MW 1x800 MW 2000 MW (c) (a+c) (a) (b)

1 Coal,MTPA 4.784 2.32 4.05 8.834 Annual coal requirement for the plant shall be 4.05 MTPA considering PLF of 90% and the same is proposed to be met from Naini Mines allocated to SCCL. LDO HFO/ requirement for startup and flame stabilization: The steam generator is designed primarily for coal firing. A fuel oil system will be used for boiler start up as well as for flame stabilization during low load. Light diesel oil will be used for furnace light up and boiler start up while HFO will be used for flame stabilization. The required HFO/LDO will be met from the nearest oil depots.

Total Existing ToR (after expansion) issued Proposed 2x600 MW 2000 MW S.No Description 1x800 MW 1x600 MW (a+c) (a) (c) (b)

1 LDO/HFO,KL/annum 8935 4437 3153 12088 e. Power Evacuation: The generation voltage is envisaged in the range of 22 to 27 kV. Evacuation of power from the proposed 800 MW extension unit will be done at 400 kV level. Two nos. 400 kV double circuit lines-3&4 to connect Nirmal substation are under construction. f. Project Cost & Tariff: The estimated Capital Cost, Capitalised Project Cost (including IDC) has been taken as Rs. 5879.62 Crs and Levelised cost of energy: 352 Paise/kWh.

THE SINGARENI COLLIERIES COMPANY LIMITED 12 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

3.2 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted

Sitting Guidelines Conformity

The project shall be at least 500 m River Godavari is existing 4 KM away from away from the HFL of the River the Project The project shall be at least 500 m NH-63 is at 500 m away from the project away from the High Way boundary. The project shall be at least 500 m The nearest railway line is Kazipet- away from the Railway Ballarsha section of South Central railway is at 14.6 Km from the project Location of TPS should be avoided No such areas are exists within 10 Km in the vicinity (10 Km) of places of from the Project. archaeological, historical, cultural, religious or tourist importance and defence installations No forestland should be utilized for No forest land is involved in the project.

setting up of TPS or for ash disposal

No alternate sites were considered as the present proposal is establishment of setting up of one additional unit of 1X800 MW Thermal Power Plant besides the 2x600 MW units already in operation at Pegadapalli Village, Jaipur Mandal of Mancherial District in Telangana State. Three alternate sites were examined before the establishment of 2x600 MW units. The location of the project meets guidelines issued by Ministry of Environment and Forests, Government of India.

3.3 Size or Magnitude of operation. Size of the Total Plant is 2000MW and is expansion of Singareni Thermal Power Plant (From 2x600 MW to 2000 MW by adding one additional unit 1x800MW) by M/s Singareni Thermal Power Plant.

Total Existing ToR issued Proposed (after expansion) S.No Description (a) (b) (c) (a+c)

1 Size of the 2x600 1x600 1x800 2000 Plant,MW 3.4 Project Description with process details

The proposed 1x800 MW Coal Based Thermal Power Plant of STPP, Stage-II is super- critical pulverised boiler technology. Coal received from the mines (expected bridge linkage from SCCL mines) at -200 mm size is crushed in the crusher house to -20mm size, which is subsequently pulverized in the coal mill. The powdered coal is burnt in the furnace to generate steam in the boiler. The steam generated in the boiler is expanded in the HP, IP & LP turbines and power is generated in the generator. The steam after expansion in the turbine is condensed in the condenser and the condensed steam is circulated back to the boiler. The hot gasses from the furnace after losing heat in different areas goes through the Electrostatic Precipitators, where ash is collected. The clean gas goes through the chimney. The bottom ash from boiler is collected in hydro-bins where water is separated and Ash in dry form is sent to underground mines of SCCL. The separated water will be reused / recirculated in the system.

THE SINGARENI COLLIERIES COMPANY LIMITED 13 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

3.5 Raw material required along with estimated quantity likely source, marketing area of final products, mode of transport of raw material and finished product. a. Coal requirement: Total Existing ToR issued Proposed (after expansion) S.No Description 2x600 MW 1x600 MW 1x800 MW 2000 MW (c) (a+c) (a) (b)

1 Coal,MTPA 4.784 2.32 4.05 8.834 The Annual coal requirement for the expansion unit at 4.05 million tonnes per annum at a plant load factor of 90%. Naini coal block was allotted for 3X600 MW STPP as end use plant. For 2X600 MW STPP Stage-I ,MoC has granted bridge linkage for the used coal from own mines of Singareni Collieries Company Limited namely SRP OC-I, SRP OC-II, RKP OC Phase-I, KK OCP and future mines like RKP Phase-II & SRP OC-III in Srirampur and Mandamarri areas at a distance of 6 to 15 Kms from the plant site. MoC will be approached to grant bridge linkage for this 1X800 MW stage-2.The coal handling Plant is designed to handle the maximum coal required for the project. b. HFO/LDO requirement for startup and flame stabilization: The steam generator is designed primarily for coal firing. A fuel oil system will be used for boiler start up as well as for flame stabilization during low load. Light diesel oil will be used for furnace light up and boiler start up while HFO will be used for flame stabilization. The required HFO/LDO will be met from the nearest oil depots.

Total Existing ToR (after expansion) issued Proposed 2x600 MW 2000 MW S.No Description 1x800 MW 1x600 MW (a+c) (a) (c) (b)

1 LDO/HFO,KL/annum 8935 4437 3153 12088

THE SINGARENI COLLIERIES COMPANY LIMITED 14 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW) c. Other Raw material:

Other Raw material like Cement (Estimated requirement: 90000 MT), Structural Steel (Estimated requirement: 45000 MT), Reinforcement Steel (Estimated requirement: 26000 MT), Sand (Estimated requirement: 1.10 L.Cu.m) and Stone/aggregate (Estimated requirement: 2.0 L.Cu.m) will be met from the local suppliers and transported through existing Rail/Road networks. d. Power evacuation:

Evacuation of power from the proposed plant will be done at 400 kV level, the generation voltage is envisaged as 22 KV. For evacuation of power, three nos. single phase 315 MVA, generator transformers for 1X800 MW unit will be connected to the 400 kV swithchyard of the 1x800 MW Power Plant which is to be constructed.

3.6 Resource Optimization Recycling & Reuse envisaged in the project, if any, should be briefly outlined) Estimated total water requirement for the 2000 MW is 136800 KLD (5700 m3/hr). It will be met from Pranahita River. Continuous efforts would be made to reduce the water consumption and thereby to reduce the wastewater generation. Flow meters would be installed for all major water inlet and the flow rates would be continuously monitored. Periodic water audits would be conducted to explore the possibilities for minimization of water consumption. Considering recirculation closed cooling water system with induced draught cooling tower, using river water for turbine condenser cooling, cycle make-up and other consumptive water requirements. The major quantity of this water will be essentially makeup water for the cooling towers, lost on account of evaporation, drift and blowdown.The filtered water shall be used for the cooling tower make-up, service water, potable water, DM plant, fire-fighting system etc.

3.7 Availability of water its source, energy/power requirement and source should be given a. Water requirement, source and mode of transport:

Estimated water requirement for 2x600 MW plant under construction is 88800 KLD (3700 m3/hr) and for additional 1X800 MW is 48000KLD (2000 m3/hr). Hence, Total Water required for 2x600 &1x800 MW is 136800 KLD (5700 m3/hr).

Total Existing ToR issued Proposed (after expansion) S. No Description 2x600 MW 1x600 MW 1x800 MW 2000 MW (c) (a+c) (a) (b)

1 Water 88,800 43,200 48,000 1,36,000 Requirement, KLD

2 Water 5700 1800 2000 Requirement, 3700 m3/hr

The required water will be met from River Pranahita. 2.0 TMC of water per annum through infiltration galleries from Pranahitha River near Devulawada Village, Mancherial District was allocated by State Government vide G.O.Rt. No. 474, dated 19.07.2010. The quantity allocated water will be sufficient for entire 2x600 &1X800 MW. The water from the Pranahita River will be transported through pipeline.

THE SINGARENI COLLIERIES COMPANY LIMITED 15 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

The details of water pumping are as follows:

B Raw water source from River Pranahitha near Devulawada Village, Mancherial District. 1 Water allocation 2.00 TMC per annum Same will be used sanctioned by State Government 2 No. of VT pumps 3+1 (three working & one standby) 3 Rating 1050 kW 4 Flow 2592 m3/hr 5 Quantity of water to be 2.00 TMC pumped C Plant Reservoir capacity 25 L.Cu.m. (0.089 Existing will be used TMC)- 47.92 Ha

3.8 Energy / Power requirement and source: Construction power for the proposed expansion of 800 MW shall be availed from the existing source of TSTRANSCO / Nearest 33 KV substation.

4 SITE ANALYSIS

4.1 Infrastructure The present proposal is expansion of 2x600 MW Thermal Power Plant in operation with addition of 1x800 MW in view of the availability of the land, coal, water, transportation facilities, etc. The infrastructure facilities envisaged for 2x600 MW TPP like Coal Handling Arrangements, Raw Water Reservoir, Coal transportation facilities (Railway line), Administrative building, etc can be used for proposed 1x800 MW additional unit also. The additional land required for the present proposal is 127.31 Ha is also available adjacent to the plant under construction and also under possession of SCCL. The additional coal required for the project can be met from the SCCL mines under operation and future mines of SCCL in the area. The township is also planned outside the main plant area for operational and maintenance staff and sufficient area is also available for additional accommodation of additional staff envisaged for the proposed 1x800 MW Plant.

4.2 Connectivity The proposed project site is situated at a distance of around 500 m from the National Highway, (NH – 63 which connects Nizamabad town in Telangana and Jagdalpur town in Chhattisgarh). The access roads connecting to the National Highway have already been built for existing units; however, internal roads within the proposed extension unit area would have to be built. The project area is also well connected with rail network. Mancherial Railway station situated at a distance of 14.6 Km (Nagpur-Kazipet main rail line of South-Central Railway). Railway siding is available up to Srirampur CHP belongs to SCCL which is at a distance of 10 Km. It is proposed to extend the Railway line from the Srirampur CHP to the proposed Power Pant via Srirampur Opencast project for coal transportation. The nearest air port is Rajiv Gandhi International Airport, Shamshabad, and Hyderabad at a distance of 250 Km.

4.3 Land Details The land requirement for the 2x600 MW TPP in operation along with proposed additional unit of 1X800 MW is furnished in the following table. All the land required for the proposal is under the possession of Singareni Collieries Company Limited. No additional land is required to be acquired for the present proposal.

THE SINGARENI COLLIERIES COMPANY LIMITED 16 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Area in Ha Total S. No Particulars 2x600MW 1x600MW 1X800MW 2000MW (a) (b) (c) (a+c) 1 Main Plant & Equipment 110.00 26.60 47.632 177.932 2 Coal Handling Plant 20.30 3 Raw Water Reservoir 47.92 Nil Nil 47.92 4 Ash Dyke 30.00 52.61 59.44 89.44 5 Greenbelt 72.18 26.30 20.24 92.42 Land for Main Plant 280.40 105.21 127.31 407.71 6 Land required for transportation 15.245 Nil Nil 15.245 of coal by rail system 7 Land required for water pipeline 5.327 Nil Nil 5.327 Total land requirement 300.972 105.21 127.31 428.28

Details of Survey No.s of existing 2x600 MW Coal Based Thermal Power Plant is as follows: Pegadapalli Village, Jaipur Mandal: Sy. Nos: 147(P) 471/2 (P), 472, 473/2, 474, 477 to 480, 481(P), 482(P), 483 to 485, 525 to 533, 534(P) to 539(P), 540(P) to 548, 592 to 605(P), 608(P), 609(P), 610(P), 613(P), 614, 615(P), 616(P), 759(P), 760(P), 761(P), 762(P), 766(P), 767(P), 768 to 953, 955 to 963(P), 964(P), 966(P), 967, 968, Vagu (P). Gangipalli Village, Jaipur Mandal: SY.Nos.: 36(P), 37 to 39, 40(P), 44(P), 45(P), 46 to 53, 54(P), 55(P), 56(P), 316, 317, 322, 324, 336, 365, 366, 367, 378, 379. Elakanti Village, Jaipur Mandal: Sy. Nos: 63(P),64(P), 67(P), 69(P), 70, 71, 72/1, 72/2, 73(P), 74, 75, 76/2, 76/3, 357(P), 358(P), 382(P), 383(P), 385(P), 386(P), 387(P), 388 to 394, 395/1, 395/2(P), 395/3(P), 396/1, 396/2, 397, 398, 399, 400(P), 401(P), 402(P) VAGU(P). Shetpalli Village, Jaipur Mandal: Sy.Nos:148(P), 150(P), 152(P), 153(P), 166(P), 167(P), 168(P), 181 (P), 188(P), 194(P), 195(P), 196(P), 200(P), 201(P), 202(P), 239(P), 245(P), 249(P), 253(P), 255(P), 256(P), 264(P), 265(P), 268(P), 269(P), 436(P), 477(P), 478(P), 479(P), 486(P), 488(P), 489(P), 491 (P), 537(P), 546(P), 549(P), 599(P). Tekumatla Village, Jaipur Mandal: Sy.Nos: 79(P), 80(P), 102(P), 103(P), 104(P), 110(P), 111(P), 113(P), 115(P), 359(P), 381(P), 720(P), 721(P), 722(P), 724(P), 737(P). Indaram Village, Jaipur Mandal: Sy.Nos: 26(P), 27(P), 37(P), 38(P), 39(P), 40(P), 46(P), 47(P), 116(P), 126(P), 128(P), 129(P), 134(P), 284/1(P), 284/3(P), 1184(P), 1196(P), Road(P). Ramaraopet Village, Jaipur Mandal: Sy.Nos: 282(P), 290(P), 295(P), 296(P), 384(P), 385(P), 386(P), 388(P), 395(P), 399(P), 402(P), 404(P).

Note: P=Part List of Survey No.s of the additional land required for setting 1x800 MW as follows:

Pegadapalli Village, Jaipur Mandal: Sy. Nos: 534(P), 539(P), 615(P), 616(P), 617(P), 618(P), 619(P), 620(P).

Elakanti Village, Jaipur Mandal: Sy.Nos: 59(P), 60(P), 61, 62, 63(P), 64(P), 65, 66, 67(P), 68(P), 338(P), 339, 340, 341(P), 342(P), 345(P), 349(P), 350 to 356, 364(P), 365 to 367, 368(P), 381(P), 382(P), 383(P), 384, 385(P), 386(P), 387(P), 400(P), 401(P), 402(P), 403 to 409, 410(P), 413(P), 414(P), 415 to 417, 418(P), 482(P).

4.4 Existing land use pattern, shortest distance from the periphery of the project to periphery of the forests, water bodies Total land requirement for the 2000 MW will be 428.20 Ha. An extent of 127.31 Ha of the land mainly open barren land under possession of SCCL is required for additional 1X800 MW in addition to the 2x600 MW plant in operation in an area of 300.972 Ha. No structures or forestland exists in the proposed land area.

THE SINGARENI COLLIERIES COMPANY LIMITED 17 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

Description Name and Distance Jaipur - 1Km (W), Pegadapalli – 1.0 Km (E), Nearest major Villages Gangipalli -1Km (S), Rasulapalli - 2.5 Km (NW). Indaram reserve forest– 1.85 Kms (NW) Nearest Forest Kundaram reserve forest – 2.1 Kms (E) Nearest Wildlife No Sanctuary/National Park Nearest River Godavari river (4 Km) No archeologically important places exist within 10 Nearest Historical Places Km of the project

4.5 Soil Classification Red loamy soils are the main soils, which are derived from country rocks. The other soils are black cotton soils mainly derived from basalt rock. In sedimentary formations the soils are deep up to 5 m and in other formations up to 1.5 m.

4.6 Climatic Data from Secondary Sources Meteorological data for the site is shown below: IMD Station: Ramagundam Lat.180 46’ Long. 790 26’ Mean Sea Level. 156 m Temperature º C Humidity % Rainfall Mean Pre-dominant No of Wind wind Month Mean Mean Highe 8.30 17.30 Month Lowest rainy speed direction Min Max st Hrs Hrs ly mm days KMPH 1st 2nd Jan 30.7 15.6 33.4 10.5 74 45 11.5 0.7 2.6 S NE Feb 33.5 18.5 36.5 13.3 65 38 9.7 0.7 3.3 S SE Mar 37.5 21.8 40.7 16.5 57 30 9.2 0.7 3.5 S SE Apr 40.5 25.7 43.7 21.2 55 29 13.7 1.1 4.6 S SW May 42.1 28.3 45.3 23.4 49 29 34.7 2.4 4.5 S SW Jun 37.4 26.8 43.8 22.6 65 49 180.1 8.7 4.9 W NW Jul 32.6 24.8 36.6 22.2 79 68 328.2 14.5 3.6 W NW Aug 31.4 24.5 34.8 22.6 82 72 285.8 13.1 2.9 W NW Sep 33.1 24.3 35.7 22.1 80 69 166.9 8.2 2.0 W NW Oct 33.3 22.1 35.8 17.7 76 61 102.5 4.7 1.6 NE NW Nov 31.5 18.0 34.1 13.4 71 54 24.0 1.7 1.5 NE E Dec 30.0 14.4 32.4 10.4 72 49 6.5 0.6 1.7 NE E

Source: GOI, Ministry of Earth Sciences, IMD, Climatological Tables - 1971-2000

4.7 Social Infrastructure available

Employment is expected during construction period as well as operation phase, in trade, garbage lifting, sanitation, afforestation works and other ancillary services. Employment in these sectors will be primarily temporary or contractual and involvement of unskilled labour will be more. A major part of this labour force will be mainly from local villagers who are expected to engage themselves both in agriculture and project activities. This will enhance their income and lead to overall economic growth of the area.

THE SINGARENI COLLIERIES COMPANY LIMITED 18 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

The following changes in socio-economic status are expected to take place with this project. The project is going to have positive impact on consumption behaviour by way of raising average consumption and income through multiplier effect. a) The project is going to bring about changes in the pattern of demand from food to non- food items and sufficient income is generated. b) The treated water supply from this proposed plant to nearby tanks can be used for agricultural purpose by the villagers which results in the economic growth of them. c) Better indirect employment opportunities due to proposed project. d) Due to the corporate social responsibility activities of M/s SCCL, the socio economic condition of the people will be improved. e) People perceive that the project will help in the development of social infrastructures/such as.  Education facilities  Banking facilities  Post offices and Communication facilities  Medical facilities  Recreation facilities  Business establishments  Plantation and parks  Community facilities

Industrial development and consequent economic development should lead to improvement of environment through better living and greater social awareness. On the other hand, the proposed project is likely to have several benefits like improvement in indirect employment generation and economic growth of the area, by way of improved infrastructure facilities and better socio-economic conditions.

5 Planning Brief

5.1 Planning Concept As SCCL is already constructed 2x600 MW units and in operation, existing infrastructure facilities such as land, water transport arrangements, railway line, roads etc. will be used.  No new infrastructure facilities are required for expansion unit.  Total required land is under possession of SCCL, No R&R is involved.  Availability of adequate raw water will be met from Pranahita River.  Water will be pumped through the existing pipe line and pump house.  There is no forest land involved for the project.  Since existing facilities are being used, cost of the power would be less.

5.2 Population Projection Around 450 people would be required to operate and maintain the 1X800 MW in addition to 1100 People required for 2x600 MW power plant under construction. During the construction stage about 2000 to 3000 people required for various works of construction. It is expected that a fair percentage of skilled and unskilled personnel would be available from the nearby areas for operation and maintenance. In addition to the operational, maintenance and construction personnel, there will be indirect employment creation in the area through service sectors, material supply, establishment of ancillary units, transport, etc.

THE SINGARENI COLLIERIES COMPANY LIMITED 19 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

5.3 Land use planning (Breakup along with green belt etc.) Land use planning of proposed expansion of 2x600 MW to 2000 MW by expansion of another 1X800 MW is as follows:

Area in Ha Total S. No Particulars 2x600MW 1x600MW 1X800MW 2000MW (a) (b) (c) (a+c) 1 Main Plant & Equipment 110.00 26.60 47.632 177.932 2 Coal Handling Plant 20.30 3 Raw Water Reservoir 47.92 Nil Nil 47.92 4 Ash Dyke 30.00 52.61 59.44 89.44 5 Greenbelt 72.18 26.30 20.24 92.42 Land for Main Plant 280.40 105.21 127.31 407.71 6 Land required for transportation 15.245 Nil Nil 15.245 of coal by rail system 7 Land required for water pipeline 5.327 Nil Nil 5.327 Total land requirement 300.972 105.21 127.31 428.28

5.4 Assessment of Infrastructure Demand (Physical & Social) Power is an essential requirement for all facets of our life and has been recognized as a basic human need. It is the critical infrastructure on which the socio-economic development of the country depends. India faces formidable challenges in meeting its energy needs and providing adequate energy of desired quality forms to various users in a sustainable manner and at reasonable cost. The gap between availability of power and the demand is not likely to be met in the foreseeable future either in southern region or in state of Telangana. To meet the deficit power in newly formed Telangana state, the Singareni Collieries Company Limited (SCCL) (Which is a Government Coal Mining company jointly owned by the Government of Telangana and Government of India) has proposed to install one unit of 800MW at their existing 2x600 MW STPP at Jaipur Mandal, Mancherial District. Accordingly, the proposal of Singareni Collieries Company Limited, for expansion of unit of 800 MW will further help in meeting the shortfall in generating capacity in the Telangana State.

5.5 Amenities/ Facilities The main approach roads to the plant have already been constructed for the operating units. The approach roads for the proposed expansion unit have to be constructed and the drainage system for the proposed unit shall be constructed separately. The route of the existing Nallah has to be diverted which is currently passing though the BTG area of the proposed unit. Necessary approval from competent authority has already been obtained for diversion of existing Nallah. Additional quarters shall be constructed in existing township area to accommodate the plant personnel of proposed unit.

6 Proposed Infrastructure The proposed infrastructure are main plant building, boiler, transformer bay, switchyard, chimney, coal handling system, water system, Induced draught cooling towers, miscellaneous building like control room, diesel generator building, water treatment plant etc

6.1. Industrial Area (Processing Area) The plant layout of the proposed thermal power plant is enclosed.

6.2 Residential Area Additional quarters shall be constructed in existing township area to accommodate the plant personnel of proposed unit.

THE SINGARENI COLLIERIES COMPANY LIMITED 20 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

6.3 Green Belt Landscaping shall be done for the entire plant and township area. A green belt of shall be provided as stipulated by the MoEF&CC. Green belt envisaged for 2x600 MW is 72.18 Ha and proposed additional unit area for 1X800 MW is 20.24 Ha.

6.4 Social Infrastructure The access roads connecting to the National Highway have already been built for existing units; however, internal roads within the proposed expansion unit area would have to be built.

For existing 2x600MW During construction phase of the project, the project proponent earmarked approximately Rs.22.10 Cr as one time capital cost for CSR activities. Further during the operation phase of the project, Rs 4.40 Cr per annum will be earmarked as recurring expenditure for CSR activities.

 Rs.11.71 Crores was spent for infrastructural facilities like roads, drains, community Halls in the surrounding villages against allocated 15.5 Crs. Balance 3.79 is allocated for the year 2017-18 infrastructural developments towards CSR activities.  Rs.6.6 Crs Funds were allocated for Training programmes for the local Youth, medical camps, Environment works, support to agriculture/Social forestry

For proposed additional 1x800MW During construction phase of the project, the project proponent earmarked approximately Rs.15.0 Crores as one time capital cost for CSR activities. Further during the operation phase of the project, CSR cost will be as per the relevant directives in this regard.

6.5 Connectivity The proposed project site is situated at a distance of around 500 meters from the National Highway, NH–63, which connects Nizamabad town in Telangana and Jagdalpur town in Chhattisgarh. It passes through the states of Telangana, Maharashtra and Chhattisgarh.

6.6 Drinking Water Management Drinking water required during the construction will be met from the existing facility of 2x600 MW units.

6.7 Sewerage System The Effluent Treatment System and Sewage Treatment Plants are proposed to treat all liquid effluent generated so as to meet the standards as per the MOEF/TSPCB standards. The Effluent treatment plant comprises of CMB, Clarifier, oil separator and settling ponds, R.O plant, solar evaporation pond etc. Domestic effluents from plant will be treated in the STP. The treated water will be utilized for cooling water make up, bottom ash sluicing, green belt development, dust suppression, dust extraction, floor washing etc.

6.8 Industrial Waste Management The sludge from the raw water pre-treatment plant shall be treated in a sludge handling plant to convert the sludge into solid form and disposed off for land fill. There shall be a central monitoring basin (CMB) to which waste water from treatment plant and cooling tower blow down shall be led. Effluents from boiler blow down and plant area drains (after separation of oil) shall flow, also to CMB where they shall be treated to comply with pH levels to meet pollution control norms. The treated effluents shall be used for green belt development and plantation works. As such, any appreciable impact on the quality of surface water and ground water is not anticipated during the operation phase of the plant.

THE SINGARENI COLLIERIES COMPANY LIMITED 21 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

6.9 Solid Waste Management During the process of power generation, about 3316.02 TPD of Fly ash and 1421.15 TPD will be generated in 2x600 MW Plant. In addition to these, 3950 TPD of fly ash and 987 TPD of bottom ash will be generated in the present proposal of 1X800 MW TPP. Fly ash and bottom ash would be collected in dry form and stored in the silos and hydro bins respectively. Fly ash will be utilized for manufacturing cement and bricks. There is a demand for fly ash from cement and brick industries. The entire fly ash generated from the proposed power plant will be utilized for manufacturing cement, bricks and other end users. In case of exigency, the fly ash will be stored in ash pond area provided in the plant premises. Bottom ash will be used for stowing or void filling in the SCCL mines in the area.

Total Existing ToR issued Proposed (after expansion) S. No Description 2x600 MW 1x600 MW 1x800 MW 2000 MW (c) (a+c) (a) (b)

1 Fly Ash, TPD 3316.02 1854 3950 7266.02 2 Bottom Ash, 1451.15 463 987 2438.15 TPD

6.10 Power Requirement & Supply The Electricity required during construction will be met from existing source / nearest 33 KV sub-station.

7 Rehabilitation and Resettlement Plan No R & R involved in the project.

8 Project Schedule & Cost Estimates.

8.1. Likely date of start of construction and likely date of completion Likely date of start is from the date of Environmental Clearance obtained. The total time period is estimated to be 50 months for the proposed 1x800 MW unit (Stage-2) from “zero date” up to date of commercial operation. Zero date is the date of letter of award for the project. IDC will be provided up to the date of commercial operation.

8.2. Estimated Project cost along with analysis in terms of economic viability of the project The estimated Capital Cost of proposed additional unit of 1x800MW, Capitalized Project Cost (including IDC) has been taken as Rs. 5879.62 Crores.

The project cost and analysis of proposed additional unit of 1x800MW are given in Table below. Cost of Generation

S. Particulars Existing ToR issued Proposed Total No amendment (after to ToR expansion) 1 Plant Capacity, MW 2x600 1x600 1x800 2000 (2x600+1x800) 2 Auxiliary Energy 6.50 5.50 5.75 12.25 Consumption, % 3 Station Heat rate (kcal 2425 2351 2250 /kg) 4 Depreciation 5.28% for 5.28% for 5.28% for first -

THE SINGARENI COLLIERIES COMPANY LIMITED 22 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

first 12 years first 12 12 years and and 2.04% years and 1.78% for for balance 1.78% for balance period period of 13 balance of 13 years years period of 13 years 5 O&M 2.07% 3.08% 3.08% - escalated escalated escalated @5.72% per @6.29% @6.29% per annum per annum annum 6 Loan Repayment 12 12 12 - Period, years 7 Interest on Loan, % 12 12 9.5 - 8 Loan repayment 48 equal 48 equal 48 equal - quarterly quarterly quarterly installments installments installments with 6 with 6 with 6 months months months moratorium moratorium moratorium 9 GCV of coal (Design), 4529 4529 3500 - kcal/kg 10 Present day coal price Rs.2266/- Rs.2650/- Rs.2850/- - tonne on tonne on tonne (Mar- delivered delivered 2017) on basis with basis with delivered basis 6.62% 6.29% with 6.29% annual annual annual escalation escalation escalation 11 GCV of support Fuel 10000 10000 10000 - (LDO), kcal/kg 12 Support fuel price Rs.45,000/- Rs.60,762/- Rs.44,607/- tonne tonne tonne for LDO LDO/HFO LDO/HFO and Rs.32394/- tonne for HFO (May-2017) 13 Plant Load Factor, % 85 85 90 14 Return on Equity 15.5 15.5 16 (RoE), % 15 Completion Schedule Unit:1 – 39 50 Months 50 Months Months (COD) done on 25.09.2016 Unit:2 –43 Months (COD) done on 02.12.2016 16 Economic life of plant 25 years 25 years 25 years

THE SINGARENI COLLIERIES COMPANY LIMITED 23 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW)

9 Analysis of proposal (Final Recommendations)

9.1 Project cost estimates and financial analysis

For additional 1x800MW

The objective of this section is to estimate and analyze the project cost, cost of generation and Levelised tariff for the proposed project in order to assess overall financial viability of the project.

Basis of cost estimates The project cost estimate for the proposed power plant has been worked out on the following basis; i. Unit size considered is 800 MW for financial analysis. Commissioning of the project is considered as 50 months from zero date. ii. Various items of packages covered in the cost estimates are based on most of the packages are based on the awarded rates for various ongoing projects of NTPC and suitably updated to current price level. iii. The cost of Balance of Plant (BoP) and other equipment has been estimated based on preliminary design and on the benchmark cost of the similar projects. iv. The project is financed through domestic funding. Taxes and duties on supply of equipment, civil works, contract and erection and commissioning have been worked out as per the prevalent rates. The economic plant life has been taken as 25 years for depreciation calculation as per CERC norms.

As per the above report, the overall peak demand shortage during 2014-15 in the newly formed state Telangana is 4.2%.

Conclusion As seen from the above, the gap between availability of power and the demand is not likely to be met in the foreseeable future either in Southern region or in Telangana. All out efforts are called for to add capacity considering the fuel availability and evacuation system.

Accordingly, the proposal of Singareni Collieries Company Limited, for extension of unit of 800 MW will further help in meeting the shortfall in generating capacity in the Telangana State.

9.2 Financial and social benefits (With special emphasis on the benefit to the local people including tribal population, if any, in the area)

Financial

For proposed additional 1x800MW During construction phase of the project, the project proponent shall incur approximately Rs. 15.0 Crores on CSR activities. Further during the operation phase of the project, the CSR will be as per the relevant directives in this regard.

Social benefits The project will improve the socio-economic status of the society in the region by generating direct and indirect employment opportunities The project will contribute additional revenue to the State & Central exchequers in the form of taxes and cess etc.

The anticipated impacts of the project are explained below: Human settlement is expected to increase after this project gets operational. In the long term, the project will have impact on the population growth due to migration of people from outside area. Indirect employment opportunities will also add to this. The literacy level of the project area is

THE SINGARENI COLLIERIES COMPANY LIMITED 24 Pre-Feasibility Report for expansion of Singareni TPP (From 1200 MW to 2000 MW by adding 1x800 MW) likely to increase as there will be influx of many educated people taking up jobs in the project, which is likely to result in establishment of better educational facilities.

The project related construction activities will benefit the local populace in a number of ways such as supply of construction laborers – skilled, semi-skilled and un-skilled, tertiary sector employment and provision of goods and services for daily needs including transport. The proposed project will provide employment to the skilled as well as un-skilled persons. The local population will be given preference depending upon their suitability to the job requirement.

Besides direct employment, indirect employment opportunities will also open up. The project will have positive impact in the region. Quality of life of the people will improve, which in-turn will improve the socio-economic conditions of the area.

THE SINGARENI COLLIERIES COMPANY LIMITED 25 EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

Terms of Reference Compliance ToR for increase in capacity from 1x600 MW (Sub-critical technology) to 1x800 MW (Super-critical Technology) with additional ToR S.No ToR Compliance Additional ToR issued on 26.09.2017 i. Separate land shall be identified preferably The land required for the proposed expansion nearby power plant achieving greenbelt (1x800 MW) is 127.31Ha, which is identified development in 33% of the total project area. separately just adjacent to the existing (2x600 MW) plant. An area of 92.42 Ha within the project site is already identified and under the progress of green belt development. Further, an additional 50 Ha of SCCL owned vacant land will be identified and developed for green belt in order to meet 33% criteria notified by MoEF&CC. Chapter 2, Table 2.4, Pg No. 240 ii. Impact assessment on downstream users, Pranahitha is a perennial River. As per the 20 agriculture and fisheries/ aquatic life due to years discharge data of River Pranahitha water withdrawal from Godavari/ Pranahitha monitored at Tekra, in the monsoon season, the Rivers shall be carried out. Minimum e-flow flow varies from a maximum of 76,657MCM shall be maintained for sustenance of ecology to a minimum of 11,155 MCM. The non- and environment in the downstream. monsoon season flow varies from a minimum of 342.6MCM to a maximum of 4737MCM. The annual flow varies from a minimum of 12,241MCM to a maximum of 78,741MCM. Permission granted for the total water withdrawal for the project is 56.63MCM per annum (2 TMC) which is 0.463% of the minimum flow of river. Hence there are no impacts envisaged for downstream users and ecology. Chapter 3, Section 3.10.10, Pg No 330 iii. Details of Water allocation of the reservoir The required 2.0 TMC of water per annum will shall be submitted. be met from River Pranahitha through infiltration galleries near Devulawada Village, Mancherial District which was allocated by the State Government vide G.O. Rt. No. 474, dated 19.07.2010. The quantity of allocated water will be sufficient for the entire 2x600 MW as well as 1x800 MW. The water from River Pranahitha will be transported through pipeline. Water allocation permission letter is enclosed as Annexure T1. Pg. No 51.

Ramky Enviro Services Private Limited ToRC. 1

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

The existing reservoir (capacity is 25 L. Cu. m (0.089 TMC)) at the site will be used for 1x800 MW also. The water in the reservoir will be sufficient for the entire plant operations. iv. Noise barriers/ reduction measures shall be  To dampen the noise levels at CHP, impact proposed. rollers are provided at transfer points.  Height of dust fall at coal handling area/hydro bins/fly ash silos will be minimized by providing internal lining of bins and chutes.  A three tier green belt will be developed all around the plant boundary to dampen the noise.  In the high noise intensity working areas / zones earmuffs or earplugs will be provided to the workmen.  Noise level monitoring will be done periodically for taking corrective action, wherever required.  Proper maintenance and tuning of machinery will be done regularly.  Proper maintenance of plant and machinery as well as improvement on the design of machines will be carried out.  Acoustically designed cabins for heavy noise generating boilers, turbines, generators and other equipments will be provided. Chapter 4, Section 4.6.3, Pg No 393 All the conditions specified in the ToR letter dated 27.5.2015 shall remain the same. i Shall explore the feasibility of switching to As suggested, it is proposed to explore the Super Critical Technology. If sub-critical is feasibility of Super Critical Technology for proposed, prior approval of MoP shall be 1x800 MW by switching to it. The EIA/EMP submitted. Accordingly, the EIA/EMP shall report will be prepared accordingly. be prepared. Chapter 2, Table 2.1, Pg No 237 ii Transportation plan including impact of The extended railway line from Srirampur road transportation, in case of delay of rail CHP to the proposed power plant for coal transportation shall be included in the transportation will be commenced much before EIA/EMP. the proposed 1x800 MW is established. Chapter 2, Section 2.8.3.2, Pg No 250 iii The PP shall obtain amendment in existing Temporary permission for transportation of

Ramky Enviro Services Private Limited ToRC. 2

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

EC for change of source of coal, mode of coal by road for a period of two years (for transportation etc. existing 2x600 MW) was granted vide EC dated 10.08.2016. A copy of the amended EC is enclosed as Annexure T2. Pg. No. 52-53. iv Details of using Bottom Ash for the Central Institute of Mining and Fuel Research existing and new units shall be provided. (CIMFR), Dhanbad, carried out field and laboratory investigations on the bulk utilization of bottom ash as a stowing material for SRP 3 & 3A incline mine. The detailed project report of CIMFR (No. CNP/3923/14-15, February, 2015) is enclosed as Annexure T3. Pg. No. 54-77. v The proposed project shall be given a For better identification purpose, the proposed unique name in consonance with the name project has been given a unique name of submitted to other Government “Expansion of Singareni Thermal Power Departments etc. for its better identification Plant (from 2x600 MW to 2000 MW by and reference. adding 1x800 MW)”. Cover page, Pg No 2 vi Vision document specifying prospective A vision document has been prepared and long term plan of the project shall be enclosed as Annexure T4. Pg. No. 75-82. formulated and submitted. vii Latest compliance report duly certified by Certified compliance report issued by the Regional Office of MoEF for the MoEF&CC regional office (South Eastern conditions stipulated in the environmental Zone), F. No. EP/12.1/841/AP/58 dated & CRZ clearances of the previous phase(s) 10.03.2015 is enclosed as Annexure T5. Pg. for the expansion projects shall be No. 83-100. submitted. viii The Project proponent needs to identify Three alternate sites were examined before minimum three potential sites based on setting up of 2x600 MW units and the location environmental, ecological and economic of the project meets the guidelines issued by considerations and choose one appropriate MoEF&CC, GoI. site having minimum impacts on ecology and environment. A detailed comparison of The proposed project is expansion of the the sites in this regard shall be submitted. existing power plant. Moreover, enough land is available just adjacent to the existing plant and some of the existing infrastructure/ facilities will be utilized for the proposed unit. Hence “No alternate sites” were considered. Chapter 5, Section 5.1, Pg No 400 ix Executive summary of the project Separate Executive summary of the project indicating relevant details along with recent indicating relevant details is given in Page No. photographs of the proposed site(s) shall be 213-219. Recent photographs of the proposed

Ramky Enviro Services Private Limited ToRC. 3

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

provided. Response to the issues raised site are given in Figure 1.4, Chapter 1. Pg. during Public hearing and the written No. 227. representations (if any), along with a time bound Action Plan and budgetary Public Hearing was conducted on 07.03.2018 allocations to address the same, shall be 11:00 AM at project site. The issues raised by provided in a tabular form, against each public during PH, a time bound action plan for action proposed. the fulfillment of demands raised by the public along with Public Hearing minutes are given in Chapter 7, Section 7.11. Pg. No. 452-480. x Harnessing solar power within the premises A proposal is being made for installation of of the plant particularly at available roof roof top Solar PV lights and panels on stand- tops and other available areas shall be alone buildings. It is proposed to install up to formulated and for expansion projects, 10 MW of solar PV power plant within the status of implementation shall also be premises of STPP in an area of 50 acres. submitted. Chapter 9, Section 9.7, Pg No 516-517 xi The geographical coordinates (WGS 84) of The geographical coordinates (WGS 84) of the the proposed site (plant boundary), proposed site (plant boundary), including including location of ash pond along with location of ash pond along with topo sheet topo sheet (1:50,000 scale) and IRS satellite (1:50,000 scale) and IRS satellite map of the map of the area, shall be submitted. area is given in Chapter 2, Table 2.2; Pg. No. Elevation of plant site and ash pond with 238 & Chapter 3, Figure 3.8, Pg. No. 299. respect to HFL of water body/nallah/River and high tide level from the sea shall be The elevation of the plant site is 144-149 m specified, if the site is located in proximity above the mean sea level. The site is far away to them. from nearby water bodies, river and sea. Chapter 1, Table 1.3, Pg 222 xii Layout plan indicating break-up of plant The layout plan showing various facilities of area, ash pond, green belt, infrastructure, the existing as well as proposed plant is shown roads etc. shall be provided. in Figure 2.1. Pg. No. 239. The breakup of plant area with particulars such as ash pond, infrastructure and roads, green belt etc., are given in Table 2.4, Chapter 2. Pg. No. 240. xiii Land requirement for the project shall be Land requirement for the expansion project has optimized and in any case not more than been optimized. The land required for the what has been specified by CEA from time proposed project is 127.31 ha (314.59 Acres). to time. Item wise break up of land After expansion, the total land for the project requirement shall be provided. will become 428.282 ha. (1058.3 Acres) which is 0.53 acres/MW. This is less than the existing CEA norms of 0.61acres/MW for 800 MW unit station using 100% indigenous coal.

The land use will change from open barren land to mixed use development, as the land will

Ramky Enviro Services Private Limited ToRC. 4

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

be occupied by the proposed thermal power plant. The breakup of land requirement is given in Chapter 2. Table 2.4, Pg. No. 240. xiv Present land use (including land class/kism) Present land use as per the revenue records and as per the revenue records and State Govt. state Govt. records and the particulars of land records of the proposed site shall be utilization for proposed 1x800MW (letter furnished. Information on land to be issued by Tahsildar, Jaipur Mandal, Mancherial acquired including coal transportation Dist. Letter dated 04.12.2017) is enclosed as system, laying of pipeline, ROW, Annexure T6. Pg. No. 101. transmission lines etc. shall be specifically submitted. Status of land acquisition and litigation, if any, should be provided. xv If the project involves forest land, details of There is no forest land involved for the project. application, including date of application, Chapter 5, Section 5.3, Pg No 402 area applied for, and application registration number, for diversion under FCA and its status should be provided along with copies of relevant documents. xvi The land acquisition and R&R scheme with The proposed unit will be set up within the a time bound Action Plan should be existing land of SCCL. Hence, it is envisaged formulated and addressed in the EIA report. that there is no R&R involved. Chapter 5, Section 5.3, Pg No 402 xvii Satellite imagery and authenticated topo Satellite imagery and authenticated topo maps sheet indicating drainage, cropping pattern, indicating the environment setting representing water bodies (wetland, river system, stream, 10 Km radius of study area is given in Chapter nallahs, ponds etc.), location of nearest 3, Figure 3.8, Pg. No. 299. habitations (villages), creeks, mangroves, The drainage pattern of the study area is shown rivers, reservoirs etc. in the study area shall in Chapter 3, Figure 3.13, Pg. No. 328. be provided. xviii Location of any National Park, Sanctuary, The office of the Divisional Forest officer, Elephant/Tiger Reserve (existing as well as Mancherial Forest department, certified vide proposed), migratory routes / wildlife letter Rc. No. 1234/2008-S2B; dated: corridor, if any, within 10 km of the project 22.06.2010 issued and confirmed that there are site shall be specified and marked on the no National park, Sanctuary, Elephant/Tiger map duly authenticated by the Chief Reserve (Existing as well as Proposed), and Wildlife Warden of the State or an officer migratory routes/wildlife corridor within 10 authorized by him. Km radius of the STPP site. A copy of the letter is enclosed as Annexure T7. Pg. No. 102. xix Topography of the study area supported by The site is well developed and no land filling is topo sheet on 1:50,000 scale of Survey of required.

Ramky Enviro Services Private Limited ToRC. 5

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

India, along with a large scale map The topographical features of the proposed preferably of 1:25,000 scale and the project site and study area are shown in specific information whether the site Chapter 1, Figure 1.2, Pg. No. 225. requires any filling shall be provided. In that case, details of filling, quantity of required fill material; its source, transportation etc. shall be submitted. xx A detailed study on land use pattern in the The land use details based on census records study area shall be carried out including are given in Chapter 3, Section 3.7, Pg. No. identification of common property 296. resources (such as grazing and community land, water resources etc.) available and The land use land cover classification of the Action Plan for its protection and study area is given in Chapter 3, Table 3.18, management shall be formulated. If Pg. No. 298, and the same is furnished in acquisition of grazing land is involved, it Chapter 3, Figure 3.9, Pg. No. 300. shall be ensured that an equal area of grazing land be acquired and developed and detailed plan submitted. xxi A mineralogical map of the proposed site A certified letter is issued by the Dept. of (including soil type) and information (if Geology & Mines, Govt. of Telangana State, available) that the site is not located on stating that the site is not located on potentially potentially mineable mineral deposit shall mineable minerals deposit in the study area. be submitted. The letter along with mineralogical map is enclosed as Annexure T8. Pg. No. 103. xxii Details of fly ash utilization plan as per the Ash utilization/Management shall be done as latest fly ash Utilization Notification of per MoEF&CC gazette notification on GOI along with firm agreements / MoU utilization of ash dated 03.11.2015. with contracting parties including other  Ash utilization plan will be implemented usages etc. shall be submitted. The plan for 100% extraction and utilization of dry shall also include disposal method / fly ash along with suitable collection, mechanism of bottom ash. storage, segregation, loading, transportation and disposal etc. facilities.  Ash in dry form is pneumatically transported to fly ash silos.  Fly ash shall be taken to high concentration slurry disposal system (HCSDS) and bottom ash through wet slurry disposal system for ultimate disposal.  The technical as well as utilization details are explained in Chapter 2, Section 2.10.4, Pg. No. 258 and Chapter 9,

Ramky Enviro Services Private Limited ToRC. 6

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

Section 9.6, Pg. No. 513.  Details of ash from STPP, SCCL with action plan for utilization of 100% fly ash enclosed as Annexure T9. Pg. No. 105. xxiii The water requirement shall be optimized The water requirement for the proposed project (by adopting measures such as dry fly ash is 48000 KLD (2000 m3/hr) which shall be and dry bottom ash disposal system, air optimized. The concept of zero discharge will cooled condenser, concept of zero be adopted. Further, the plant shall have two discharge) and in any case not more than different systems for ash disposal – that stipulated by CEA from time to time, conventional wet bottom ash slurry disposal to be submitted along with details of source system with dewatering bin to utilize bottom of water and water balance diagram. Details ash and High Concentration Slurry Disposal of water balance calculated shall take into for fly ash which will require less quantity of account reuse and re-circulation of water and therefore there will be no effluent effluents. from the fly ash disposal site.

The detailed water balance calculations and water balance diagram are given in Chapter 4, Table 4.10, Pg. No. 383 and Figure 4.9 respectively, Chapter 4. Pg. No. 384. xxiv Water body / Nallah (if any) passing across A nallah is currently passing through the the site should not be disturbed as far as proposed project site BTG area. In this regard, possible. In case any Nallah / drain is permission is accorded to divert existing nallah proposed to be diverted, it shall be ensured within the plant area to meet Rasulpalli vagu, that the diversion does not disturb the subject to conditions without causing natural drainage pattern of the area. Details obstruction to natural flow of water. of proposed diversion shall be furnished duly approved by the concerned The permission granted by Dept. Executive Department of the State. Engineer, I.B. Sub-division, Chennur Lr. No. EE/IBD/MNCL/DB/D3/2016-17/236/M; dated: 02.06.2017 is enclosed as Annexure T10. Pg. No. 107. xxv It shall also be ensured that a minimum of River Godavari is 4 Km away from the project 500 m distance of plant boundary is kept site. NH-63 is 500 m away from the main plant from the HFL of river system / streams etc. boundary. Chapter 1, Table 1.3, Pg No 222 and the boundary of site should also be A dedicated railway line is under extension located 500 m away from railway track and from Srirampur CHP to the proposed power National Highways. plant for coal and ash transportation. Chapter 2, Section 2.8.3.2, Pg No 250 xxvi Hydro-geological study of the area shall be Hydro-geological study was carried out by carried out through an institute / Exploration division of Singareni Collieries organization of repute to assess the impact Company Limited, to know the quality of

Ramky Enviro Services Private Limited ToRC. 7

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

on ground and surface water regimes. water in the neighbouring villages around the Specific mitigation measures shall be spelt project site. 04 surface and 05 ground water, out and time bound Action Plan for its samples were collected for evaluating the basic implementation shall be submitted. nutrient demand and toxic parameters. The parameters of prime importance were selected and analyzed under physical, chemical, organic and heavy metal groups. The monitoring was carried out periodically and report submitted to statutory authorities regularly. The Hydrogeological Report of the same enclosed as Annexure T11. Pg. No. 109-153. xxvii Detailed Studies on the impacts of the The ecological studies have been carried out ecology including fisheries of the during the study period and the observations River/Estuary/Sea due to the proposed representing the flora and fauna of the study withdrawal of water / discharge of treated area are presented in Section 3.8, Chapter 3. wastewater into the River/ Sea etc. shall be Pg. No. 301. carried out and submitted along with the EIA Report. In case of requirement of There is no marine water intake or outfall. marine impact assessment study, the location of intake and outfall shall be clearly specified along with depth of water drawl and discharge into open sea. xxviii Source of water and its sustainability even The water required (2000 m3/hr) for the 1x800 in lean season shall be provided along with MW project will be met from Pranahitha River details of ecological impacts arising out of located 43.5 Km away from the project site withdrawal of water and taking into account before confluence of Godavari River at inter-state shares (if any). Devulawada village. Information on other competing sources downstream of the proposed project and commitment regarding availability of requisite quantity of water from the Competent Authority shall be provided along with letter/document stating firm allocation of water.

As per the 20 years discharge data of River Pranahitha monitored at Tekra, in the monsoon season, the flow varies from a maximum of 76,657MCM to a minimum of 11,155 MCM. The non-monsoon season flow varies from a minimum of 342.6MCM to a maximum of 4737MCM. The annual flow varies from a minimum of 12,241MCM to a maximum of 78,741MCM. Permission granted for the total water withdrawal for the project is 56.63MCM per annum (2 TMC) which is 16.5% of the minimum flow of river. Hence there are no impacts envisaged for downstream users and ecology. Chapter 2, Section 2.8.2 & Table 2.6, Pg No

Ramky Enviro Services Private Limited ToRC. 8

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

241 xxix Detailed plan for rainwater harvesting and Rainwater harvesting is done by the its proposed utilization in the plant shall be construction of harvesting pits all along the furnished. storm water drainage network at a definite pitch. Artificial recharge measures like rainwater harvesting helps in reducing the surface run-off, decrease pollution of groundwater and improve the groundwater table, which augments the yield of wells. Necessary advice will be taken in this regard.

Recharge trenches will be built all along the outer land boundary which acts as rainwater harvesting pits. Chapter 4, Section 4.5, Table 391 - 392 xxx Feasibility of near zero discharge concept The feasibility of zero discharge is examined shall be critically examined and its details and based on reduce, reuse and recycle of submitted. effluents the quantities of water requirement and effluent generation has been optimized to the extent feasible. For SCCL-STPP the following scheme have been envisaged. - Closed cycle cooling system with cooling towers with CoC5 - Use of cooling tower’s blow down for  Ash Handling  Coal dust suppression  Service water system  Firefighting - Ash water recirculation system - Treatment and recirculation of CHP effluents and source water effluents. - Recirculation of filter backwash to clarifier inlet an effluent management scheme, consisting of collection, treatment, recirculation and disposal of effluents. Chapter 4, Section 4.4.3.2, Pg No 386 xxxi Optimization of Cycles of Concentration Water requirement for the project shall be (CoC) along with other water conservation optimized with designed CoC5 for measures in the project shall be specified. conservation of water. Chapter 4, Section 4.4.2, Pg No 385 xxxii Plan for recirculation of ash pond water & Ash pond water is recirculated for existing

Ramky Enviro Services Private Limited ToRC. 9

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

its implementation shall be submitted. unit. Additional pipeline will be laid for expansion unit to drain ash pond water.

Quantity of makeup water required for 1x800 MW would be about 2000 Cum/hr with ash water recirculation system and 2650 Cum/hr with once through ash water system. Chapter 2, Section 2.8.2, Pg No 241 xxxiii Detailed plan for conducting monitoring of Seven (7) piezometric wells were constructed water quality regularly with proper around ash pond for regular monitoring of maintenance of records shall be formulated. ground water levels and ground water samples Details of methodology and identification will be collected from these wells and analyzed of monitoring points (between the plant and for heavy metals. drainage in the direction of flow of Water samples from these piezometric wells surface/ground water) shall be submitted. It will be collected and analysed for prescribed shall be ensured that parameter to be heavy metals for establishing the base line monitored also include heavy metals. A data, before commencement of the plant and provision for long-term monitoring of continued periodical analysis to monitor the ground water table using Piezometer shall changes in quality of water. be incorporated in EIA, particularly from The locations for surface water samples will be the study area. identified in monsoon season and samples will be collected and analysed periodically. Chapter 6, Table 6.2, Pg No 410; Table 6.3 Pg No 412 – 416 xxxiv Socio-economic study of the study area Socio-economic study was carried out around comprising of 10 km from the plant site 10 Km radius of the study area. Detailed shall be carried out through a reputed impact assessment survey was carried out and institute / agency which shall consist of mitigation measures are proposed. The details detail assessment of the impact on of demography and the prevailing socio- livelihood of the local communities. economic conditions are given in Section 3.12, Chapter 3. Pg. No. 334. xxxv Action Plan for identification of local Action plan is in place for local employable employable youth for training in skills, youth to develop skills through special training. relevant to the project, for eventual A provision is made for training as part of CSR employment in the project itself shall be plan. Budgetary provision has been made for formulated and numbers specified during the proposed project to impart training/skill construction & operation phases of the development programmes to make them self- Project. employable. This budget will be utilized during construction phase and it will be continued during plant operation stage through CSR. Chapter 8, Section 8.4.1 Pg 483 - 492 xxxvi If the area has tribal population it shall be Tribal issues have been studied and necessary ensured that the rights of tribals are well provisions are made in the action plan to

Ramky Enviro Services Private Limited ToRC. 10

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

protected. The project proponent shall upgrade the skill and improve socio-economic accordingly identify tribal issues under conditions. various provisions of the law of the land. Chapter 8, Section 8.4.1 Pg 483 – 492 xxxvii A detailed CSR plan along with activities During construction phase of the project, the wise break up of financial commitment project proponent earmarked approximately. shall be prepared. CSR component shall be Rs. 15 crores as one time capital cost for CSR identified considering need based activities. Further, during the operation phase assessment study and Public Hearing of the project, CSR budget will be as per the issues. Sustainable income generating relevant directives. measures which can help in up-liftment of affected section of society, which is A detailed plan of CSR activities and action consistent with the traditional skills of the plan are mentioned along with the breakup of people, shall be identified. Separate budget financial commitment. The on-going CSR for community development activities and activities and expenditure are given in the income generating programmes shall be Chapter 8, Section 8.4. Pg. No. 482. specified. xxxviii While formulating CSR schemes it shall be An in-built monitoring mechanism for ensured that an in-built monitoring conducting social audit exists at SCCL. mechanism for the schemes identified are in place and mechanism for conducting annual A detailed plan of CSR activities and action social audit from the nearest government plan are mentioned along with the breakup of institute of repute in the region shall be financial commitment. The on-going CSR prepared. The project proponent shall also activities and expenditure are given in the provide Action Plan for the status of Section 8.4, Chapter 8. Pg. No. 482. implementation of the scheme from time to time and dovetail the same with any Govt. scheme(s). CSR details done in the past should be clearly spelt out in case of expansion projects. xxxix R&R plan, as applicable, shall be The proposed unit will be set up within the formulated wherein mechanism for existing land of SCCL. Hence, it is envisaged protecting the rights and livelihood of the that there is no R&R. people in the region who are likely to be Chapter 5, Section 5.3, Pg 402 impacted, is taken into consideration. R&R plan shall be formulated after a detailed census of population based on socio economic surveys that were dependent on land falling in the project, as well as, population who were dependent on land not owned by them. xl Assessment of occupational health and There is no specific endemic disease in the endemic diseases of environmental origin area. General sanitation and hygiene shall be in the study area shall be carried out and maintained in the labour camp.

Ramky Enviro Services Private Limited ToRC. 11

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

Action Plan to mitigate the same shall be Chapter 3, Section 3.12.3, Pg No 335 - 344 prepared. xli Occupational health and safety measures Basic health care facilities like First-aid and for the workers including identification of ambulance facility will be made available to work related health hazards shall be the workers during the construction period. formulated. The company shall engage full Contractors will be responsible for all the basic time qualified doctors who are trained in amenities during construction other than occupational health. Health monitoring of sanitation, firewood and basic health care. the workers shall be conducted at periodic intervals and health records maintained. Company will engage highly qualified doctors Awareness programme for workers due to and conduct health camps for the workers. likely adverse impact on their health due to Required treatment and medicines will be working in non-conducive environment provided free of cost under CSR activity. shall be carried out and precautionary Workers will not be allowed to work without measures like use of personal equipments personal protective equipments like safety etc. shall be provided. Review of impact of jackets, safety shows, helmets etc. various health measures undertaken at intervals of two to three years shall be Chapter 8, Section 8.4, Page 482 conducted with an excellent follow up plan of action wherever required. xlii One complete season site specific The ambient air quality monitoring was carried meteorological and AAQ data (except out during Post-Monsoon season from October monsoon season) as per latest MoEF&CC to December, 2017 covering predominant wind Notification shall be collected and the dates directions and population zones. Villages in the of monitoring shall be recorded. The vicinity are considered. The details are given in parameters to be covered for AAQ shall Chapter 3, Section 3.3. Pg. No. 276.

include PM10, PM2.5, SO2, NOx, CO and Hg. The location of the monitoring stations should be so decided so as to take into consideration the upwind direction, pre- dominant downwind direction, other dominant directions, habitation and sensitive receptors. There should be at least one monitoring station each in the upwind and in the pre – dominant downwind direction at a location where maximum ground level concentration is likely to occur. xliii In case of expansion project, air quality Yes. The project proposed is expansion from monitoring data of 104 observations a year existing 2x600 MW to 2000 MW (by adding for relevant parameters at air quality 1x800MW) coal based TPP. The air quality monitoring stations as identified/ stipulated monitoring data for existing project from shall be submitted to assess for compliance January to December 2017, for relevant

Ramky Enviro Services Private Limited ToRC. 12

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

of AAQ Standards (annual average as well parameters at air quality monitoring stations as 24 hrs.). are enclosed as Annexure T12. Pg. No.154- 158. xliv A list of industries existing and proposed in 1. SCCL existing 2x600 MW STPP the study area shall be furnished. 2. Sri Chennakesava Ceramics -2.2Km NW 3. Sri Venkateswara Agro Industries -2.3Km W 4. ML ceramics - 2.5 Km NW 5. Balaji Agro Industries - 2.6Km W 6. Om Industries - 2.8Km W 7. Jayalaxmi Rice Mill – 2.9Km W 8. Balaji Cotton Ginning Mill – 3.7Km W 9. Shivasai Industries Rice Mill – 4.1Km W 10. Sri Laxmi Industries Rice Mill – 4.2Km SW 11. Venkata Sailaxmi ceramics-4.2Km SW 12. SCCL RKNT Open Cast Mine – 4.5Km NW 13. Varalaxmi Agro Industries – 5.2Km SW 14. SCCL SRP Open Cast Mines – 6.0Km W 15. SCCL RKP Open Cast Mines -10.5Km NW 16. Ramagundam NTPC TPPs - 12Km SW Chapter 1, Table 1.3, Pg No 223 xlv Cumulative impacts of all sources of The modeling input details for the cumulative emissions including handling and impacts of AERMOD (version 7.0.3) software transportation of existing and proposed model used for predicting the incremental air projects on the environment of the area quality levels in the study area due to the shall be assessed in detail. Details of the proposed project. Model used and the input data used for modeling shall also be provided. The air Cumulative impacts of all sources of emissions quality contours should be plotted on a including handling and transportation of location map showing the location of existing and proposed projects on the predicted project site, habitation nearby, sensitive maximum GLC of 24 hours average of PM10, receptors, if any. The wind rose and PM2.5, SO2, & NOx concentrations isopleths should also be shown on the considering mean meteorological data of the location map. The cumulative study should study season are superimposed on the also include impacts on water, soil and maximum baseline concentrations obtained socio-economics. during the study period to estimate the post project scenario, which would prevail at the post operational phase. The air quality contour maps of overall post project scenario of 2000 MW are given in Chapter 4, Section 4.3.4. Pg. No. 367. xlvi Radio activity & heavy metal contents of The analysis report examining Radio Activity coal to be sourced shall be examined and and heavy metal content in coal are their submitted along with laboratory reports. laboratory reports are enclosed as Annexure

Ramky Enviro Services Private Limited ToRC. 13

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

T13. Pg. No. 159-163. xlvii Fuel analysis shall be provided. Details of The details of auxiliary fuel, quantity and their auxiliary fuel, if any, including its quantity, storage furnished in Section 2.8.3.4 Chapter quality, storage etc. should also be 2. Pg. No. 250. The auxiliary fuel analysis furnished. details are enclosed as Annexure T14. Pg. No. 164-167. xlviii Quantity of fuel required, its source and The estimated coal requirement for the characteristics and documentary evidence proposed project is 514 TPH (4.05 MTPA-90% to substantiate confirmed fuel linkage shall PLF). Naini coal block (expected production in be furnished. The Ministry's Notification 2020-21) the coal characteristics and the dated 02.01.2014 regarding ash content in documentary evidences were enclosed as coal shall be complied. For the expansion Annexure T15. Pg. No. 168-173. projects, the compliance of the existing The certified compliance of the existing unit is units to the said Notification shall also be enclosed as Annexure T5, Pg 83 – 100 submitted. xlix Details of transportation of fuel from the The project area is well connected with railway source (including port handling) to the network. Mancherial railway station is situated proposed plant and its impact on ambient at a distance of 14.6 Km. Presently, railway AAQ shall be suitably assessed and siding is available up to Srirampur CHP that submitted. If transportation entails a long belongs to SCCL which is at a distance of distance it shall be ensured that rail 10Km. it is proposed to extend the railway line transportation to the site shall be first from Srirampur CHP to the existing and assessed. Wagon loading at source shall proposed power plant for coal and ash preferably be through silo/ conveyor belt. transportation. Chapter 2, Section 2.8.3.2, Pg 250 l For proposals based on imported coal, 100% domestic coal will be used for the inland transportation and port handling and proposed power plant. Permission granted for rail movement shall be examined and the extension of railway line and the key plan details furnished. The approval of the Port is enclosed as Annexure T16. Pg. No. 174. and Rail Authorities shall be submitted. li Details regarding infrastructure facilities Basic health care facilities i.e. first-aid and such as sanitation, fuel, restrooms, medical ambulance facilities will be made available to facilities, safety during construction phase the workers during the construction period. etc. to be provided to the labour force Temporary sanitary facilities i.e. septic tanks during construction as well as to the casual will be provided. workers including truck drivers during operation phase should be adequately Contractors will be responsible for all the basic catered for and details furnished. amenities during construction other than sanitation, firewood and basic health care. Necessary conditions will be imposed in the work order of contractors. Chapter 4, Section 4.2, Pg No 357 - 362

Ramky Enviro Services Private Limited ToRC. 14

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

lii EMP to mitigate the adverse impacts due to EMP to mitigate adverse impacts due to the the project along with item - wise cost of its proposed project and EMP cost towards implementation in a time bound manner pollution control measures are given in Table shall be specified. 9.9, Chapter 9. Pg. No. 518. liii A Disaster Management Plan (DMP) along SCCL has a dedicated team of professionals with risk assessment study including fire who are involved in the emergency operations. and explosion issues due to storage and use For effective control and management of an of fuel should be carried out. It should take emergency, on-site emergency plan has been into account the maximum inventory of prepared. storage at site at any point of time. The risk contours should be plotted on the plant Details of Disaster Management Plan (DMP) layout map clearly showing which of the along with risk assessment study including fire proposed activities would be affected in and explosion issues due to storage and use of case of an accident taking place. Based on fuel is given in Chapter 7. the same, proposed safeguard measures DMP is given in Section 7.10, Pg. No. 449. should be provided. Measures to guard Onsite emergency plan given in Section 7.8, against fire hazards should also be Pg. No. 444. Hazardous Assessment and invariably provided. Mock drills shall be Evaluation Section 7.4 of Chapter 7. Pg. No. suitably carried out from time to time to 427. check the efficiency of the plans drawn. liv The DMP so formulated shall include Details of DMP and risk assessment study are measures against likely Fires/Tsunami/ provided in Section 7.10, Chapter 7. Pg. No. Cyclones /Storm Surges/ Earthquakes etc., 449. as applicable. It shall be ensured that DMP Onsite emergency plan given in Section 7.8 consists of both On-site and Off-site plans, Pg. No. 444, and Off-site emergency Plan in complete with details of containing likely Section 7.9, Chapter 7. Pg. No. 447. disaster and shall specifically mention personnel identified for the task. Smaller The proposed plant site is not prone zone of version of the plan for different possible Tsunami/cyclones/storm surges/Earthquakes disasters shall be prepared both in English etc. Chapter 1, Table 1.3, Pg 223 and local languages and circulated widely. lv Detailed scheme for raising green belt of The survival rate is also monitored by native species of appropriate width (50 to periodical enumeration of new plantation. 100 m) and consisting of at least 3 tiers around plant boundary with tree density of The details of existing plantation, proposed 2000 to 2500 trees per ha with a good plantation along with area and no. of plants are survival rate of around 80% shall be given in Table 9.4, Chapter 9. Pg. No. 502. submitted. Photographic evidence must be created and submitted periodically including NRSC reports in case of expansion projects. A shrub layer beneath tree layer would serve as an effective sieve

for dust and sink for CO2 and other gaseous

Ramky Enviro Services Private Limited ToRC. 15

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

pollutants and hence a stratified green belt should be developed. lvi Over and above the green belt, as carbon In consultation with the District Forest sink, plan for additional plantation shall be Department, additional plantation will be done drawn by identifying blocks of degraded within the identified blocks of degraded forest. forests, in close consultation with the District Forests Department. In pursuance The details of existing plantation location wise to this the project proponent shall formulate are enclosed as Annexure T17. Pg. No. 175 & time bound Action Plans along with 176. financial allocation and shall submit status of implementation to the Ministry every six months. lvii. Corporate Environment Policy i Does the company have a well laid down Yes. The company has a well laid Environment Policy approved by its Board Environmental Policy approved by its Board of of Directors? If so, it may be detailed in the Directors. The same incorporated in Chapter EIA report. 9, Section 9.3, Pg. No. 500, Figure 9.1, Pg. No. 501 ii Does the Environment Policy prescribe for Yes. Relevant clauses in Environment & Forest standard operating process / procedures to laws & legal consequences in case of violation bring into focus any infringement / of the sections are given in the “Procedures and deviation / violation of the environmental Frame Works for SCCL” document. or forest norms / conditions? If so, it may Chapter 9, Section 9.3, Pg. No. 500, Figure be detailed in the EIA. 9.1, Pg. No. 501 iii What is the hierarchical system or The hierarchical system/ administrative setup Administrative order of the company to of the company to deal the environmental deal with the environmental issues and for related issues for ensuring compliances with ensuring compliance with the the environmental clearance conditions is given environmental clearance conditions? in Figure 6.1, Chapter 6 of Pg. No. 420, and Details of this system may be given. compliance of conditions of environmental clearance given in Page No. 36 of Annexure T11. Pg. No. 148-150. iv Does the company has compliance Yes. General manager (Environment) will management system in place wherein monitor the compliance of Environmental compliance status along with compliances / norms in all the areas of SCCL. Chief GM violations of environmental norms are (Corporate Planning & Projects) will be reported to the CMD and the Board of reviewing the environmental issues for Directors of the company and / or ensuring compliance for norms/ conditions. shareholders or stakeholders at large? This Director (E&M), Director (Planning & reporting mechanism should be detailed in Projects) & Director (Operations), who are the the EIA report. All the above details should board of Directors, SCCL, will review the be adequately brought out in the EIA report overall compliance of statutory norms in the

Ramky Enviro Services Private Limited ToRC. 16

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

and in the presentation to the Committee. organization. Chapter 6, Section 6.4, Pg 419, Figure 6.1 Pg No 420 lviii Details of litigation pending or otherwise No Litigation/complaints are pending against with respect to project in any Court, the existing as well as proposed project. Tribunal etc. shall invariably be furnished. 4. Besides the above, the following general points shall be followed a. All documents to be properly referenced Noted. And all the documents have been with index, page numbers and continuous properly referenced with index, page numbers page numbering. and continuous page numbering. b. Where data is presented in the report Noted and complied especially in table, the period in which the data was collected and the source should invariably be indicated. c. Where the documents provided are in a All the documents are provided in English language other than English, an English only. translation should be provided. d. The Questionnaire for environmental Questionnaire for environmental appraisal of appraisal of thermal power projects as TPP has been filled and enclosed as Annexure devised earlier by the Ministry shall also be T18. Pg. No. 177-190 and its Annexures from filled and submitted. Pg. No. 191-212. e. The consultants involved in the preparation The QCI/NABET accreditation Certificate of of EIA/EMP report after accreditation with consultant involved in preparation of EIA/EMP Quality Council of India (QCI) / National report given in Page 15 of EIA report. Accreditation Board of Education and Training (NABET) would need to include a certificate in this regard in the EIA/ EMP reports prepared by them and data provided by other organization / Laboratories including their status of approvals etc. In this regard circular no. F.No. J- 11013/77/2004-IA-II (I) dated 2nd December, 2009 is posted on the Ministry's website http://www.moef.nic.in may be referred. Additional information to be incorporated in the EIA report

1. Is the project intended to have CDM- The Gross specific CO2 emissions of the intent? proposed 1x800 MW shall be 0.78 tons of

(i) If not, then why? CO2/MWh. As per CO2 baseline database for (ii) If yes, then the Indian Power sector, Version 10 of 2014, a. Has PIN (Project Idea Note) {or PCN published by CEA, the weighted average (Project Concept Note)} submitted to emission factor for Southern Grid in India is

Ramky Enviro Services Private Limited ToRC. 17

EIA of Proposed 800 MW Coal Based Thermal Power Plant at Mancherial District, Telangana

the? NCA? (National CDM Authority) 0.82 tons of CO2/MWh. Details are presented in the MoEF? in EIA report Section 9.9, Chapter 9. Pg. No. b. If not, then by when is that expected? 518. c. Has PDD (Project Design Document) been prepared? d. What is the Carbon intensity? from your electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH) e. Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA?s web-site (www.cea.nic.in) 2. Notwithstanding 1(i) above, data on (d) & (e) above shall be worked out and reported. 5 The Environmental Clearance shall be Noted and complied. applied only after fuel and water linkage are firmed up. 6 After preparing the Draft EIA (as per the Draft EIA was prepared in January 2018 and generic structure prescribed in Appendix III submitted to TSPCB for conducting public of the EIA Notification, 2006) covering the hearing. above mentioned issues, the same shall be submitted to the SPCB for conducting the The TSPCB given environmental public public Hearing as per procedure of hearing paper notification in local Telugu daily EIA/EMP report. The final EIA/EMP report newspaper of Andhra Jyothi and English daily along with public hearing report and the newspaper of Deccan Chronicle on 02 requisite documents (including written February, 2018 and subsequent telugu objections, if any) shall be submitted to the corrections was published on 03 February, Ministry for appraisal by the Expert 2018. Appraisal Committee for Environmental Impact Assessment notification dated The Public hearing was conducted on September 14, 2006. 07.03.2018, 11:00 AM at project site. All the issues raised by public and written representations, time bound action plan along with budget provision are incorporated in the final EIA/EMP report Chapter 7; Section 7.11. Pg. No. 452. 7 The ToRs prescribed shall be valid for Noted and complied. period of three years for submission of EIA/EMP reports, after Public Consultation.

Ramky Enviro Services Private Limited ToRC. 18

Annexure E4 Compliance to the EC amendment letter dated 10.8.2016 i) Prior requisite approvals from the concerned State Authorities, especially the PWD, shall be obtained.

The required approvals from the concerned state authorities have been obtained to widen and strengthen roads from SCCL mines to SCCL TPP, and same are attached as Annexure E4a. ii) The transportation by road shall be through mechanically covered trucks to the extent feasible, else through trucks covered by tarpaulin.

For transportation of coal from SCCL mines to SCCL TPP trucks covered by tarpaulin are used. iii) Periodic maintenance of the road shall be done by the project proponent at its own expenses and shall also facilitate the traffic control on the road in consultation with the State Govt. Adequate road safety measures shall be provided for pedestrians.

As instructed the periodic maintenance works are carried out by the SCCL management and adequate safety measures are provided to pedestrians (foot path, road crossing signals, etc.) iv) Avenue plantation of 2/3 rows along the road shall be carried out by the project proponent at its own expenses in consultation with the State Government.

Avenue plantation of 2/3 rows along the road have been carried out at places where there is no plan of immediate widening of the roads, and further plantation will be carried out after proposed widening works are completed. v) The PP shall advertise in the local leading newspapers and upload on the website, the above amendment of EC so accorded by the Ministry, for public information.

The SCCL has advertised about amendment of EC accorded by the Ministry in local leading newspapers (i) Deccan Chronicle (English) Dt.20.08.2016and (ii) Eenadu (Telugu), Dt.20.08.2016 and the same attached as Annexure E4b. vi) The standard stipulated by the Ministry vide Notification dated 07.12.2015 (as amended from time to time) for Thermal Power Plants shall be duly complied.

SCCL TPP is complying the standards stipulated by the Ministry vide Notification dated 07.12.2015.

The water consumption for existing 2x600MW TPP is 3700 m3/MWh (all existing CT based plants reduce specific water consumption upto maximum of 3.5m3/MWh within a period of two years from the date of publication of this notification). Meeting the stack emission 3 3 3 3 standards of PM 50mg/Nm ; SO2 200mg/Nm ; NOx 300mg/Nm ; and Mercury 0.03mg/Nm .

Director (E&M) SCCL Annexure E4a Permissions from Concerned Authorities for widening the roads

Annexure E4b Advertisement of issue of Amendment to EC (10.08.2016) in Local Newspapers

Annexure E5 Compliance status for implementation of revised emission standards Dated: 7.12.2015 for the existing power plant & proposed project

Existing Power Plant (2x600MW) SCCL TPP (2x600MW) is complying the standards stipulated by the Ministry vide Notification dated 07.12.2015.

The water consumption for existing 2x600MW TPP is 3700 m3/Hour. The specific water consumption is coming to 3.08Cu.m/MWh.(all existing CT based plants reduce specific water consumption upto maximum of 3.5m3/MWh within a period of two years from the date of publication of this notification).

3 3 3 Meeting the stack emission standards of PM 50mg/Nm ; SO2 200mg/Nm ; NOx 300mg/Nm ; and Mercury 0.03mg/Nm3.

For meeting particulate matter emission standard high efficiency Electro Static Precipitator (ESP) has already been provided with microprocessor based programmable type rapper control system and ESP management system to ensure safe and optimum operation of ESP.

For meeting SO2emission standards low sulphur content coal is being used and for meeting NOx emission standard low NOx burners are used. STPP is processing the installation of FGD plant for further reduction of SO2 Emission.

Proposed Power Plant ( 1 x 800 MW) – TPPs to installed from 1st January 2017 Proposed SCCL TPP (1x800MW) will comply the standards stipulated by the Ministry vide Notification dated 07.12.2015.

The water consumption for proposed 1x800MW TPP is 2000 m3/hr (New plants to be installed after 1st January 2017 shall have to meet specific water consumption upto maximum of 2.5m3/MWh and achieve zero waste water discharged) with zero discharge by utilization after treatment within plant for horticulture, ash handling and dust suppression.

3 3 3 Meeting the stack emission standards of PM 30mg/Nm ; SO2 100mg/Nm ; NOx 100mg/Nm ; and Mercury 0.03mg/Nm3 following control measures are provided.

For meeting particulate matter emission standard high efficiency Electro Static Precipitator (ESP) is proposed. The ESP will be provided with microprocessor based programmable type rapper control system and ESP management system to ensure safe and optimum operation of ESP.

For meeting SO2 emission standards Wet Limestone Flue Gas Desulphurizing (FGD) system shall be installed. The FGD system shall have an independent absorber limestone milling systems and gypsum dewatering system. The SO2 removal efficiency will be >/= to 90%.

For meeting NOx emission standards flue gas Selective Catalytic Reduction (SCR) DeNOx system will be installed. The SCR system shall be planned designed to perform and demonstrate to meet the environmental norms of MOEFCC.

Mercury exists in three forms in coal fired thermal power plants flue gas: (i) Elemental Hg (O) (ii) Oxidized Hg (2+) (iii) Particle bound Hg (P). The Hg(P) fraction is typically removed by ESP, particulate control device. The Hg(2+) portion is water soluble and therefore a relatively high percentage can be captured by wet flue gas desulphurization (FGD) system. The Hg(O) fraction is generally not captured by proposed air pollution control device. However, the proposed SCR for controlling NOx emissions will promote oxidation of Hg(O) to Hg(2+) and enhance Hg capture in downstream FGD.

Director (E&M) SCCL Annexure E6 Corrective action taken report for non-compliances reported by the certified RO compliance report on EC conditions vide lr.Dt.31.10.2017

S.No Observed non-compliance Status of compliance 1 Presently, project authority has SCCL has made a request to MOC for long term linkage obtained only “In principle” to 2X600MW STPP on 07.12.2013, 25.06.2014, approval from Ministry of coal 04.07.2014 & 24.02.2015 to Ministry of power and CEA for grant of “Bridge linkage” on 30.03. 2015. (tapering Linkage) to the power MOC vide file No.23014/2/2016-CPD, Dt.22.04.16 has plant. It appears in this regard, approved the recommendations of Standing Linkage final concurrence yet to be Committee (Long Term). obtained from MoC- specification No. (i). Copy of letter enclosed in Annexure-1 2 Though the continuous online The continuous online stock monitoring equipment has stack monitoring equipment has been installed for the monitoring of gaseous emission & been installed for the particular matter from stack and data being monitored monitoring of gaseous emission continuously. & particulate matter from stack, Now the steps are being taken up for linking the data with the same has not been linked the website of CPCB & TSPCB by collecting quotations with the website of CPCB and for online instrument with data connectivity from the state PCB – Specification eligible firms. Condition No.(vi) 3 Report on hydro – geological “Hydro-geological study of the area for the year – 2017” in study of the area has not been respect of 2X600 MW STPP has been carried out and the submitted to the Ministry and its report is recently submitted to MoEF& CC vide Regional office – Specification Lr.No.STPP/ENV/637/157, Dt:24.01.2018. (The copy of Condition No.(ix) the covering letter enclosed here with). 4 Inadequate greenbelt As a part of development of green belt, Plantation is being development. Green belt developed within the premises of power plant at various consisting of three tiers of locations in a phased manner and it is at different stages plantations of native species in growth. around plant has not been The details of Block plantation and avenue plantation made as stipulated - taken up so far are given in the Annexure-II. Specification Condition No. (xxi). Steps are also being taken up to further development of green belt include providing 3 tier plantation with native species. 5 Details of the amount spent Various works and activities are being taken up by SCCL yearly from capital cost and under CSR programme. The details of year wise/ phase-

recurring cost of CSR allocated wise expenditure spent from capital cost so far are and the activities undertaken furnished as Annexure-III. are not made available. Also , Further, various training programmes have also been details are not made available given to the unemployed local youth on traditional skills to regarding implementation of take up the self-employment and the details are furnished income generating projects as Annexure-IV. consistent with the traditional skills of the people to take up self – employment and job -– Specification Condition No.(xxiv) and (xxv). 6 Neither carried out annual Steps will be taken to carry out social audit by identifying social audit by the nearest suitable government institute of repute in the region and government institute of repute report will be submitted. in the region nor submitted the status of implementation of the scheme from time to time - S.No Observed non-compliance Status of compliance Specification Condition No.(xxvi). 7 ETP & STP have not been ETP: Construction of ETP is completed and installed – general condition commissioned. No.(i) & (ii). STP: Civil works for construction of STP is completed. But, erection of Mechanical equipment is under progress. It will be completed by the end of May,2018 and the allocation of residential quarters to the employees of STPP will also be completed in the month of May, 2018. 8 Rain water harvesting 5 No’s of Rain Water harvesting structures (RWHS) are measures have not been proposed to be taken up. The STPP premises are of black implemented - general cotton soil and the water table at most of the locations is condition No.(iv). at shallow depth ranging only from 0.58m to 4.18m in various seasons. Hence, CGWB authorities were consulted for design of RWHS. The Deputy Director, CGWB, South zone, HYD has inspected in and around the STPP and the design report is awaited. Soon after receipt of design, RWHS will be constructed accordingly. 9 Ground water quality has not Fresh post project monitoring work is awarded and been monitored. The commenced from Oct’2017. The monitoring of Ground monitoring of heavy metals water quality at 13 locations in and around the project site, around the ash pond area has Ash pond effluents at 2 locations and water quality around not been carried out. The Ash pond area through piezo metric wells has been details of the monitored data carried out in the season Post-Monsoon, 2017 and the compared with baseline status data is enclosed as Annexure –V, VI and VII have not been submitted to respectively. Regional Office, MoEF&CC at

Chennai- general condition No.(vi)&(vii). 10 Frequency of AAQ monitoring The fresh post project monitoring work is awarded and and its parameters are not commenced from October, 2017. Now, the AAQ conformed to the latest protocol monitoring is being carried out twice in a week (for the of CPCB - general condition parameters such as PM10, PM2.5, SO2, NOx and Hg) No.(x). duly obtaining approval from Environmental Engineer, Regional office, TSPCB, Nizambad. 11 Project authority has not Recently, a separate environmental cell has been established separate established by posting two executives (one Dy.GM (Civil) environmental cell with qualified and one Addl. Manager, exclusively to look after personnel at the project site - environmental related issues at the project site. general condition No.(xiv). 12 The monitored AAQ data and Fresh post project monitoring work is commenced from Stack emission have not been October, 2017. Monitoring of AAQ and stack emissions displayed at a convenient are being monitored regularly and being displayed location near the main gate of manually on the notice boards provided near the Main the company on the public Gate of STPP. domain as stipulated.PA should Steps are also being taken up to install electronic display. install electronic display- general condition No.(xv) & (xviii).

Director (E&M) SCCL

Annexure-1 MOC vide file No.23014/2/2016-CPD, Dt.22.04.16 has approved the recommendations of Standing Linkage Committee (Long Term)

ANNEXURE – II PLANTATION DETAILS OF 2X600MW STPP Total plantation taken up in STPP S.No Total No. of Location Year Block Avenue plants planted plantation in Ha plantation in Km 1. Block plantations at 2012 40.00 41,361 STPP 2. Avenue plantation along 2012 3.80Kms 1,243 internal roads 3. Block plantations at 2013 20.00 22255 STPP 4. Avenue plantation along 2013 4.0kms 1450 internal roads 5. Block plantations at 2014 10.00 2501 STPP 6. Avenue plantation along 2015 3.00 Km 1200 internal roads 7. Block plantations at 2016 1.00 620 STPP (Near Pylon) 8. Block plantation near 2017 4.00 Plantation weigh bridge by the side under progress of coal road 9. Block plantation near 2017 3.00 Plantation weigh bridge by the side under progress of fly ash road Total 78.00 Ha 10.80 Kms Expenditure incurred on plantation so far : Rs.69,05,712.00 Total Avenue Plantation Taken up so far : 10.80 Km. Block plantation taken up so far : 78.00 ha. Block plantation existing since the time of land acquisition : 8.26 ha.

Annexure-III Status of CSR works by STPP as on 13-02-2018 Expenditure including No. of Sl.No Description material cost Remarks works (Rs.in lakhs) PHASE-I A 111.22 5 (Year: 2010-11) Works completed PHASE-II B 327.36 16 (Year: 2011-12) Awarded works - 18Nos. 590.71 (17 works completed & 01 is in PHASE-III C 18 progress) (Year: 2014-15) Expenditure to be booked on 11.09 finalisation of bills BY SCCL: Expenditure – Rs.37 Lakhs (No. of works- 7) 81.12 PHASE-IV By Govt: Expenditure – Rs.44.12 D 16 (Year: 2017-18) Lakhs (No. of works-9) Expenditure to be booked on 742.08 completion of works Total Expenditure 1110.41 55

ANNEXURE – IV LOCAL EMPLOYABLE YOUTH ON TRAINING SKILLS RELEVANT TO THE PROJECT– 2X600MW COAL BASED THERMAL POWER PLANT. (I) 224 candidates have been provided outsourcing jobs in unskilled category who are the land oustees and nearby local unemployed youth in STPP and attached to Power Mech Agency. (II) 43 candidates belonging to neighbouring villages of STPP undergone training in Electrical house wiring course at National Academy of constructions, Hyderabad in the year 2009. (III) 21 candidates have been provided training in Police and Army recruitment programmes during the year 2009. (IV) 75 Candidates have been provided training in Candle making. (V) 42 candidates have been imparted training in Motor vehicle driving. (VI) 31 candidates have been provided training in Saree rolling and tailoring. (VII) 19 persons have been provided training in Beautician course. (VIII) 4 persons have been provided training in Photography. (IX) 19 members have been provided training in Welding course at NAC, Hyderabad. (X) 40 candidates have been given training in Plumbing and Sanitation at NAC, Hyderabad. (XI) 34 candidates have been providing training in Fitter & Welder course at Khadi Gramodyog Maha Vidyalaya (KGMV), Hyderabad. Annexure-V Physico-Chemical, Bacteriological Characteristics of Groundwater Collected within the Study Area (Oct 2017 - Dec 2017)

S. Test IS: 10500 IS: 10500 RESULT Parameters Unit No Method Desirable Limits Permissible Limits GW-1 GW-2 GW-3 GW-4 GW-5 GW-6 GW-7 1 pH - 4500-H+B 6.5 to 8.5 No relaxation 7.8 7.9 7.6 7.9 7.8 7.7 7.7 2 Temperature ºC 2550. B -- -- 25.0 25.0 25.1 25.0 24.8 25.0 25.0 3 Turbidity NTU 2130. B 1 5 0.7 0.6 0.4 0.9 1.0 0.6 0.7 4 TDS at 180o C mg/L 2540.C 500 2000 700 730 430 1250 1120 950 940

5 Total Alkalinity as CaCO3 mg/L 2320. B 200 600 499 473 347 530 641 462 473

6 Total Hardness as CaCO3 mg/L 2340. C 300 600 425 450 330 505 610 440 450 7 Chloride (as Cl) mg/L 4500-Cl-.B 250 1000 80 72 20 307 192 202 195

2- 8 Sulphates (as SO4) mg/L 4500-SO4 .E 200 400 40 114 10 94 90 69 64

- 9 Nitrates (as NO3) mg/L 4500-NO3 .B 45 No relaxation 1.80 1.70 10 1.2 1.4 1.0 6.3 10 Fluoride (as F) mg/L 4500-F=.C 1.0 1.5 0.761 0.797 0.831 1.07 0.823 1.01 0.941 11 Calcium as Ca mg/L 3500-Ca.B 75 200 82 90 70 114 134 84 92 12 Magnesium as Mg mg/L 3500-Mg.B 30 100 53 55 38 53 67 56 53

13 Phenolic compounds as C6H5OH mg/L 5530-D 0.001 0.002 BDL BDL BDL BDL BDL BDL BDL 14 Cyanide as CN- mg/L 4500-CN-.F 0.05 No relaxation BDL BDL BDL BDL BDL BDL BDL

15 Hexavalent Chromium as Cr+6 mg/L 3500-Cr+6.B 0.05 No relaxation BDL BDL BDL BDL BDL BDL BDL

16 Colour Pt-co- 2120. B 5 15 <5 <5 <5 <5 <5 <5 <5

No odour No odour No odour No odour No odour No odour No odour 17 Odour TON 2150. B Agreeable Agreeable observed observed observed observed observed observed observed No flavor No flavor No flavor No flavor No flavor No flavor No flavor 18 Taste FTN 2160. B Agreeable Agreeable observed observed observed observed observed observed observed Anionic Detergents 19 mg/L IS:13428:2005K 0.2 1.0 <0.2 <0.2 <0.2 <0.2 <0.2 <0.2 <0.2 (as MBAS) IS:3025 20 Mineral Oil mg/L 0.5 No relaxation Absent Absent Absent Absent Absent Absent Absent (part 39) 21 Residual free chlorine mg/L 4500-Cl-.B 0.2 1.0 BDL BDL BDL BDL BDL BDL BDL

22 Mercury as Hg µg/L 3500-Hg.B 0.001 No relaxation BDL BDL BDL BDL BDL BDL BDL

23 Sulfide as S2- mg/L 4500. S2- G - - BDL BDL BDL BDL BDL BDL BDL S. Test IS: 10500 IS: 10500 RESULT Parameters Unit No Method Desirable Limits Permissible Limits GW-1 GW-2 GW-3 GW-4 GW-5 GW-6 GW-7

24 Aluminium as Al mg/L 3120-B 0.03 0.2 BDL BDL BDL BDL BDL BDL BDL

25 Barium as Ba mg/L 3120. B 0.7 No relaxation 0.20 0.22 0.28 0.15 0.41 0.42 0.14

26 Boron as B mg/L 3120-B 0.5 1.0 0.16 0.12 0.05 0.09 0.07 0.10 0.07

27 Copper as Cu mg/L 3120-B 0.05 1.5 0.06 0.10 0.07 0.09 BDL 0.07 BDL

28 Iron as Fe mg/L 3120-B 0.3 No relaxation 0.46 2.95 0.41 0.50 1.15 2.1 0.24

29 Manganese as Mn mg/L 3120-B 0.1 0.3 0.06 0.13 BDL BDL BDL 0.07 BDL

30 Selenium as Se mg/L 3120-B 0.01 No relaxation BDL BDL BDL BDL BDL BDL BDL

31 Silver as Ag mg/L 3120. B 0.1 No relaxation BDL BDL BDL BDL BDL BDL BDL

32 Zinc as Zn mg/L 3120-B 5 15 0.13 0.28 0.09 0.08 0.08 0.10 0.15

33 Cadmium as Cd mg/L 3120-B 0.003 No relaxation BDL BDL BDL BDL BDL BDL BDL

34 Lead as Pb mg/L 3120-B 0.01 No relaxation BDL BDL BDL BDL BDL BDL BDL

35 Molybdenum as Mo mg/L 3120. B 0.07 No relaxation BDL BDL BDL BDL BDL BDL BDL

36 Nickel as Ni mg/L 3120-B 0.02 No relaxation BDL BDL BDL BDL BDL BDL BDL

37 Total Arsenic as As mg/L 3120-B 0.01 0.05 BDL BDL BDL BDL BDL BDL BDL

38 Total Chromium as Cr mg/L 3120-B 0.05 No relaxation BDL BDL BDL BDL BDL BDL BDL

IS: 10500 IS: 10500 RESULT S.No Parameters Unit Test Method Desirable Limits Permissible Limits GW-8 GW-9 GW-10 GW-11 GW-12 GW-13 1 pH - 4500-H+B 6.5 to 8.5 No relaxation 7.2 7.0 7.6 7.1 7.1 7.0 2 Temperature ºC 2550. B -- -- 25.1 25.0 25.1 25.0 25.0 25.0 3 Turbidity NTU 2130. B 1 5 0.4 0.8 0.6 0.6 0.5 0.7 4 TDS at 180o C mg/L 2540.C 500 2000 400 1080 540 730 810 1620

5 Total Alkalinity as CaCO3 mg/L 2320. B 200 600 278 551 452 452 431 462

6 Total Hardness as CaCO3 mg/L 2340. C 300 600 265 525 430 425 410 440 7 Chloride (as Cl) mg/L 4500-Cl-.B 250 1000 50 132 30 82 115 492

2- 8 Sulphates (as SO4) mg/L 4500-SO4 .E 200 400 13 229 13 52 58 149

- 9 Nitrates (as NO3) mg/L 4500-NO3 .B 45 No relaxation 1.0 32 7.7 50 73 89 10 Fluoride (as F) mg/L 4500-F=.C 1.0 1.5 0.586 0.872 0.592 0.894 0.921 1.1 11 Calcium as Ca mg/L 3500-Ca.B 75 200 54 124 102 104 106 112 12 Magnesium as Mg mg/L 3500-Mg.B 30 100 32 52 42 40 35 39

13 Phenolic compounds as C6H5OH mg/L 5530-D 0.001 0.002 BDL BDL BDL BDL BDL BDL 14 Cyanide as CN- mg/L 4500-CN-.F 0.05 No relaxation BDL BDL BDL BDL BDL BDL 15 Hexavalent Chromium as Cr+6 mg/L 3500-Cr+6.B 0.05 No relaxation BDL BDL BDL BDL BDL BDL 16 Colour Pt-co- 2120. B 5 15 <5 <5 <5 <5 <5 <5 No odour No odour No odour No odour No odour No odour 17 Odour TON 2150. B Agreeable Agreeable observed observed observed observed observed observed No flavor No flavor No flavor No flavor No flavor No flavor 18 Taste FTN 2160. B Agreeable Agreeable observed observed observed observed observed observed Anionic Detergents 19 mg/L IS:13428:2005K 0.2 1.0 <0.2 <0.2 <0.2 <0.2 <0.2 <0.2 (as MBAS) IS:3025 20 Mineral Oil mg/L 0.5 No relaxation Absent Absent Absent Absent Absent Absent (part 39)

- 21 Residual free chlorine mg/L 4500-Cl .B 0.2 1.0 BDL BDL BDL BDL BDL BDL

22 Mercury as Hg µg/L 3500-Hg.B 0.001 No relaxation BDL BDL BDL BDL BDL BDL 2- 2 23 Sulfide as S mg/L 4500. S - G - - BDL BDL BDL BDL BDL BDL 24 Aluminium as Al mg/L 3120-B 0.03 0.2 BDL BDL BDL BDL BDL BDL

25 Barium as Ba mg/L 3120. B 0.7 No relaxation 0.07 0.6 0.48 0.44 0.57 0.32 IS: 10500 IS: 10500 RESULT S.No Parameters Unit Test Method Desirable Limits Permissible Limits GW-8 GW-9 GW-10 GW-11 GW-12 GW-13

26 Boron as B mg/L 3120-B 0.5 1.0 0.09 0.20 0.11 0.18 0.18 0.26

27 Copper as Cu mg/L 3120-B 0.05 1.5 BDL 0.06 0.07 0.07 0.08 0.06 28 Iron as Fe mg/L 3120-B 0.3 No relaxation 1.78 0.94 0.50 0.51 0.73 1.17 29 Manganese as Mn mg/L 3120-B 0.1 0.3 BDL 0.09 0.06 BDL BDL BDL 30 Selenium as Se mg/L 3120-B 0.01 No relaxation BDL BDL BDL BDL BDL BDL 31 Silver as Ag mg/L 3120. B 0.1 No relaxation BDL BDL BDL BDL BDL BDL 32 Zinc as Zn mg/L 3120-B 5 15 0.13 0.18 0.06 0.16 0.26 0.11 33 Cadmium as Cd mg/L 3120-B 0.003 No relaxation BDL BDL BDL BDL BDL BDL 34 Lead as Pb mg/L 3120-B 0.01 No relaxation BDL BDL BDL BDL BDL BDL 35 Molybdenum as Mo mg/L 3120. B 0.07 No relaxation BDL BDL BDL BDL BDL BDL 36 Nickel as Ni mg/L 3120-B 0.02 No relaxation BDL BDL BDL BDL BDL BDL 37 Total Arsenic as As mg/L 3120-B 0.01 0.05 BDL BDL BDL BDL BDL BDL 38 Total Chromium as Cr mg/L 3120-B 0.05 No relaxation BDL BDL BDL BDL BDL BDL NTU – Nephelometric Turbidity Unit; BDL – Below Detection Limit

Annexure-VI Characteristics of Ash Pond Effluent Sample

Season: Post-monsoon Date of Sampling: 12.12.2017

Test RESULT S No. Parameters Unit method HMAPD-1 HMAPD-2 1 pH - 4500H+ B 8.8 8.9 mg/L 2 TSS 2540-D 22 24 mg/L 3 O & G 5520-B <1 <1 4 Arsenic as As mg/L 3120. B BDL BDL 5 Mercury as Hg mg/L 3120-B BDL BDL 6 Chromium as Cr mg/L 3120. B 0.12 BDL 7 Lead as Pb mg/L 3120-B BDL BDL HMAPD- Heavy Metals in Ash Pond

Annexure-VII Physico-Chemical Characteristics of Piezometric Wells samples at Selected Locations in the Study Area (Oct 2017-Dec 2017)

IS: 10500 IS: 10500 RESULT S.No Parameters Unit Test Method Desirable Limits Permissible Limits PW-1 PW-2 PW-3 1 pH - 4500-H+B 6.5 to 8.5 No relaxation 7.5 7.8 8.3 2 Temperature ºC 2550. B -- -- 25.1 25.2 25.2 3 Turbidity NTU 2130. B 1 5 0.7 4.9 0.9 4 TDS at 180o C mg/L 2540.C 500 2000 620 420 400

5 Total Alkalinity as CaCO3 mg/L 2320. B 200 600 431 425 506

6 Total Hardness as CaCO3 mg/L 2340. C 300 600 135 180 80 7 Chloride (as Cl) mg/L 4500-Cl-.B 250 1000 107 35 22

2- 8 Sulphates (as SO4) mg/L 4500-SO4 .E 200 400 78 7 1

- 9 Nitrates (as NO3) mg/L 4500-NO3 .B 45 No relaxation 8 1 1 10 Fluoride (as F) mg/L 4500-F=.C 1.0 1.5 0.982 1.25 0.99 11 Calcium as Ca mg/L 3500-Ca.B 75 200 20 40 16 12 Magnesium as Mg mg/L 3500-Mg.B 30 100 21 19 10 Phenolic compounds as 13 mg/L 5530-D 0.001 0.002 BDL BDL BDL C6H5OH 14 Cyanide as CN- mg/L 4500-CN-.F 0.05 No relaxation BDL BDL BDL Hexavalent Chromium as 15 mg/L 3500-Cr+6.B 0.05 No relaxation BDL BDL BDL Cr+6 16 Colour Pt-co- 2120. B 5 15 10 15 5 No odour No odour No odour 17 Odour TON 2150. B Agreeable Agreeable observed observed observed No flavor No flavor No flavor 18 Taste FTN 2160. B Agreeable Agreeable observed observed observed Anionic Detergents 19 mg/L IS:13428:2005K 0.2 1.0 <0.2 <0.2 <0.2 (as MBAS) IS:3025 20 Mineral Oil mg/L 0.5 No relaxation Absent Absent Absent (part 39)

- 21 Residual free chlorine mg/L 4500-Cl .B 0.2 1.0 BDL BDL BDL

22 Mercury as Hg µg/L 3500-Hg.B 0.001 No relaxation BDL BDL BDL 2- 2 23 Sulfide as S mg/L 4500. S - G - - BDL BDL BDL 24 Aluminium as Al mg/L 3120-B 0.03 0.2 BDL BDL BDL IS: 10500 IS: 10500 RESULT S.No Parameters Unit Test Method Desirable Limits Permissible Limits PW-1 PW-2 PW-3

25 Barium as Ba mg/L 3120. B 0.7 No relaxation 0.08 0.04 0.06 26 Boron as B mg/L 3120-B 0.5 1.0 0.24 0.05 0.11 27 Copper as Cu mg/L 3120-B 0.05 1.5 BDL BDL BDL 28 Iron as Fe mg/L 3120-B 0.3 No relaxation 3.2 5.4 1.5 29 Manganese as Mn mg/L 3120-B 0.1 0.3 0.18 0.07 BDL 30 Selenium as Se mg/L 3120-B 0.01 No relaxation BDL BDL BDL 31 Silver as Ag mg/L 3120. B 0.1 No relaxation BDL BDL BDL 32 Zinc as Zn mg/L 3120-B 5 15 0.36 0.11 0.07 33 Cadmium as Cd mg/L 3120-B 0.003 No relaxation BDL BDL BDL 34 Lead as Pb mg/L 3120-B 0.01 No relaxation BDL BDL BDL 35 Molybdenum as Mo mg/L 3120. B 0.07 No relaxation BDL BDL BDL 36 Nickel as Ni mg/L 3120-B 0.02 No relaxation BDL BDL BDL 37 Total Arsenic as As mg/L 3120-B 0.01 0.05 BDL BDL BDL 38 Total Chromium as Cr mg/L 3120-B 0.05 No relaxation 0.03 BDL BDL NTU – Nephelometric Turbidity Unit; BDL – Below Detection Limit. AAQ data from January 2017 to March 2018

Summary of AAQ PM10 Results – (March 1st - 31st, 2018) Core zone Buffer zone Days Civil Weigh Bridge Labour Stacker Rasul Dubbapalli Jaipur Pegadapalli Tekumatla Office near main gate Camp Reclaimer palli Day1 87 93 87 95 75 82 80 81 73 Day2 91 89 91 108 88 85 86 94 78 Day3 86 94 104 91 77 79 90 88 84 Day4 82 90 90 104 73 81 73 93 85 Day5 93 91 92 96 89 84 91 91 73 Day6 90 87 89 90 85 78 77 82 83 Day7 86 92 91 106 86 73 82 90 80 Day8 94 86 86 92 78 76 83 87 89 PM 2.5 (ug/m3) Day1 43 52.1 43.5 45.9 32 42.3 41.7 37.2 32.4 Day2 49.2 53.2 51.7 47.7 41.9 43.0 43.8 53.5 32.4 Day3 51.3 54.4 38.8 52.0 39.0 35.8 46.0 46.4 42.5 Day4 44.5 46.8 45.4 50.9 36.6 38.3 34.3 51.2 43.0 Day5 46.5 46.5 52.8 57.5 43.3 39.3 47.4 44.3 36.5 Day6 48.7 42.7 45.6 45.7 31.4 38.9 34.4 42.5 41.2 Day7 44.7 53.5 44.2 39.9 39.3 31.7 40.3 43.7 43.4 Day8 53.5 42.2 45.4 50.1 40.7 32.7 43.7 45.7 45.5 SO2(ug/m3) Day1 17.3 20 11.6 11.6 13.0 17.8 32.6 33.3 11.3 Day2 14.2 17.2 12.5 14 7.8 9.2 30.1 26.5 19.4 Day3 10 11.8 16.3 13.1 18.7 10.2 28.3 31.2 22.3 Day4 12.6 21.2 15.2 18.4 14.1 11.7 25.6 29.8 15.4 Day5 11.2 18.4 17 21 10.2 13.6 33.5 34.5 16.1 Day6 9.3 15.8 11.5 18.2 11.3 9.5 27.7 28.8 24.6 Day7 12.6 16.1 10.1 16.6 12.6 10.8 25.3 35.6 13.5 Day8 13.2 15.5 18.4 19.2 17.4 11.7 24.1 37.5 18.1 NOx(ug/m3) Day1 24.6 23.5 15.0 15.5 17.5 22.9 35.9 37.2 16.2 Day2 18.6 21.9 16.8 17.9 10.8 13.6 38.3 36.3 25.7 Day3 14.6 16.9 19 16.3 28.1 14.6 37.5 38.1 28.1 Day4 17.3 27 18.3 25.8 17.3 12.9 36 39.5 18.6 Day5 16.5 23.3 21.4 28.6 18.3 14.4 42.3 40.6 20.3 Day6 18 19.4 16.1 21.6 15.6 18.1 40.5 35.7 29.3 Day7 16.8 21 14.3 21.7 15.3 15.1 43.3 42.8 19.2 Day8 15.2 18.2 22.5 23.7 21.8 14.6 35.4 45.5 23.8 All locations are Hg Values in BDL Summary of AAQ PM10 Results – (February, 1st - 28st, 2018) Core zone Buffer zone Days Civil Weigh Labour Stacker Rasul Office Bridge near Camp Reclaimer Dubbapalli Jaipur Pegadapalli Tekumatla palli main gate Day1 88 88 91 94 87 82 92 95 71 Day2 94 93 94 96 91 75 88 97 82 Day3 82 90 92 115 75 88 73 96 88 Day4 93 91 110 98 90 90 91 90 74 Day5 95 96 93 93 76 84 86 89 91 Day6 92 80 86 104 88 89 90 92 84 Day7 89 91 87 92 85 83 88 78 83 Day8 90 92 93 97 83 78 85 90 89 PM 2.5 (ug/m3) Day1 52 52.8 52.8 50.7 37 36.5 46.1 45.9 37.1 Day2 53.9 55.2 54.5 53.2 46.1 41.1 45.1 55.6 36.2 Day3 48.2 54.5 53.7 51.6 36.6 45.5 37.2 52.3 49.2 Day4 47.7 53.5 49.6 55.8 45.2 45.7 42.1 49.6 36.6 Day5 55.2 56.2 53.1 53.7 35.9 40.7 45.4 49.2 53.6 Day6 47.0 40.2 49.8 54.0 33.7 44.5 43.3 54.9 46.6 Day7 53.1 53.7 52.2 54.9 40.1 37.2 35.8 39.4 35.2 Day8 52.7 52.0 51.6 55.3 32.6 36.6 42.6 52.8 40.0 SO2(ug/m3) Day1 16.8 23.5 13.5 21.3 11.8 12.6 31.2 28 9.4 Day2 15.2 19.2 12.4 23.7 14.3 13.2 36.5 25.6 21.7 Day3 12.4 21.3 14.2 20.4 16.8 9.8 41.3 30.5 20.5 Day4 16.5 28.4 18.5 19.6 15.4 8.5 33.4 34.3 10.2 Day5 13.6 18.4 21.5 13.2 10.3 14.6 29.3 31.6 14.3 Day6 18.1 19.6 16.2 24.5 12 16.2 26.8 29.4 11.2 Day7 14.8 17.8 15.3 19.3 9.1 14.1 27.9 32.8 10.9 Day8 17.2 21.3 16.2 24 13.2 10.6 25.1 27.2 15.8 NOx(ug/m3) Day1 21.3 28.4 17.2 26.6 19.8 15.8 37.7 32.7 18.2 Day2 18.2 24.7 14.6 29 16.5 16.4 42.1 41 31.9 Day3 19.4 31.1 18.1 26.4 16.8 14.3 44.4 39.1 32.8 Day4 21.2 33.6 23.3 27.8 15.4 13.1 38.7 38.2 14.5 Day5 17.1 25.3 26.2 22.0 14.0 17.5 35.3 35.8 16.9 Day6 21.5 24.2 21.7 30.4 18.3 21.3 30.8 33.7 17.7 Day7 23.2 22.5 18.5 25.0 17.3 18 31.5 37.8 15.8 Day8 24.3 26.8 23.6 28.1 16.7 14.7 33 31.4 24.5 All locations are Hg Values in BDL Summary of AAQ PM10 Results – (January, 1st - 31st, 2018) Core zone Buffer zone Days Civil Weigh Labour Stacker Rasulpal Office Bridge near Camp Reclaime Dubbapalli Jaipur Pegadapalli Tekumatla li main gate r Day1 92 88 90 90 77 72 81 90 74 Day2 89 83 79 105 72 77 83 84 69 Day3 90 74 77 92 73 74 78 95 76 Day4 96 91 88 95 67 78 73 98 79 Day5 86 92 75 91 74 78 81 93 76 Day6 93 77 80 94 60 73 77 81 71 Day7 84 85 91 110 71 83 81 96 77 Day8 91 87 105 92 76 72 84 86 78 PM 2.5 (ug/m3) Day1 52 53.7 46.8 53.5 49 49.2 46.8 48.0 39.4 Day2 46.9 51.3 47.7 51.7 34.1 34.1 45.3 49.0 36.5 Day3 54.5 50.4 50.9 52.5 47.4 49.5 47.0 50.1 42.7 Day4 55.2 40.3 49.4 54.0 43.7 47.8 44.9 54.9 44.6 Day5 52.8 54.5 53.8 53.8 42.0 49.8 43.2 53.5 43.9 Day6 54.3 50.2 40.4 52.8 40.7 47.1 44.1 50.5 40.9 Day7 53.4 47.7 55.4 51.7 39.3 50.4 41.8 43.4 44.5 Day8 54.7 46.1 44.9 51.9 41.2 40.3 47.3 54.5 42.7 SO2(ug/m3) Day1 14.2 18.6 9.7 16.1 14.6 11.3 29.3 26.1 9.4 Day2 12.6 21.0 10.3 17.1 13.0 10.5 31.2 29.5 21.7 Day3 13.5 14.8 11.0 16.8 15.3 12.6 26.4 28.5 20.5 Day4 11.2 18.7 11.9 20.2 11.3 13.6 19.6 33.2 10.2 Day5 9.0 19.4 9.8 14.8 12.3 14.8 26.4 29.2 14.3 Day6 12.3 17.3 10.6 19.1 14.7 12.2 27.1 31.2 11.2 Day7 11.8 19.2 8.9 20.3 13.5 11.7 26.7 27.7 10.9 Day8 9.2 20.9 10.7 21.2 14.7 14.4 21.1 29.5 15.8 NOx(ug/m3) Day1 18.7 25.5 14.0 22.5 19.8 16.6 38.9 38.2 18.2 Day2 18.6 26.9 13.9 23.9 16.5 19.5 39.2 39.3 31.9 Day3 15.5 22.0 15.8 231 16.8 20.0 34.9 40.1 32.8 Day4 16.9 25.5 17.1 26.0 15.4 20.5 28.7 43.2 14.5 Day5 15.3 25.5 13.9 22.0 14.0 21.8 35.1 36.8 16.9 Day6 16.5 22.2 14.1 25.9 18.3 18.4 34.6 41.3 17.7 Day7 14.0 26.3 15.0 26.7 17.3 19.1 37.4 35.6 15.8 Day8 12.2 27.9 17.3 27.2 18.0 21.7 30.0 35.6 24.5 All locations are Hg Values in BDL

Summary of AAQ PM10 Results – (Jan – Dec, 2017) 17-Jan PM 10 (ug/m3) Days Ramaraopet pet Shettipalli Tekumatla Jaipur Rasulpalli Pegadapalli Day1 91 91 94 87 91 97 Day2 89 92 84 92 78 94 17-Feb Day1 93 79 86 92 84 97 Day2 84 86 92 89 94 87 17-Mar Day1 86 92 79 86 72 97 Day2 82 96 88 92 87 98 17-Apr Day1 81 96 89 92 84 95 Day2 92 90 82 89 72 95 17-May Day1 87 96 76 92 87 94 Day2 88 79 67 83 74 94 17-Jun Day1 73 82 97 92 84 97 Day2 79 74 85 87 78 94 17-Jul Day1 82 89 72 82 76 94 Day2 79 84 96 92 87 93 17-Aug Day1 79 94 72 95 92 85 Day2 67 91 88 82 76 97 17-Sep Day1 76 97 93 Day2 91 87 91 17-Oct Day1 76 81 73 80 Day2 60 84 82 78 Day3 70 86 69 82

Day4 86 62 70 75 Day5 79 80 68 80 Day6 82 86 74 68 17-Nov Day1 75 75 83 72 Day2 82 78 82 70 Day3 64 76 71 86 Day4 77 82 75 82 Day5 72 85 84 88 Day6 73 68 66 71 Day7 68 71 72 76 Day8 63 85 75 81 17-Dec Day1 82 70 82 75 Day2 68 78 67 85 Day3 74 72 77 70 Day4 85 84 80 73 Day5 76 80 76 78 Day6 84 85 68 67 Day7 65 64 63 83 Day8 82 62 78 78 Summary of AAQ PM2.5 Results – (Jan – Dec, 2017) 17-Jan PM 2.5 (ug/m3) Days Ramaraopet pet Shettipalli Tekumatla Jaipur Rasulpalli Pegadapalli Day1 53.4 56.2 52.5 48.7 57.4 58.2 Day2 49.7 54.8 46.8 52.2 46.9 57.4 17-Feb Day1 57.2 41.2 46.2 59.7 45.6 51.2 Day2 46.2 42.5 53.4 50.3 51.3 48.9 17-Mar Day1 42.8 51.3 40.8 52.4 43.1 56.8 Day2 46.4 52.8 49.5 56.8 42.9 58.7 17-Apr Day1 47.9 59.3 54.9 54.3 49.8 56.4 Day2 55.4 56.4 47.8 51.8 42.2 56.4 17-May Day1 46.1 56.8 41 52.6 49.7 56.9 Day2 49 43.6 41.4 46.3 45.8 56.5 17-Jun

Day1 41.9 46.8 52.1 52.3 51.7 58.9 Day2 43.8 46.1 47.8 47.1 45.2 56.1 17-Jul Day1 40.6 45.1 39.4 43.8 38.7 46.7 Day2 41.4 48.2 55.6 51.7 49.2 52.6 17-Aug Day1 43.8 51.6 39.7 56.4 52.8 50.1 Day2 38.4 53.4 49.1 47.9 43.2 51.4 Day1 39.7 51.6 48.4 Day2 53.8 47.6 50.8 17-Oct Day1 47.6 33.2 36.4 35.1 Day2 42.6 35.2 48.2 30.3 Day3 30.2 30.2 40.1 38.6 Day4 32 40.2 46.2 32.3

Day5 40.4 48.3 42.9 37.7 Day6 30.3 49.2 42.8 38.4 17-Nov Day1 47.6 33.2 46.4 35.1 Day2 32.4 32.8 40.5 30.4 Day3 31.2 38.2 42.8 31.1 Day4 42.6 35.6 48.4 34.5 Day5 42.7 32.4 42.5 30.8 Day6 46.5 40.8 43.5 38.9 Day7 40.2 31.6 48.1 32.4 Day8 38.7 39.2 36.9 34.5 17-Dec Day1 33.3 37.9 40.8 30.5 Day2 37.7 25.5 38 33.9 Day3 36.2 31.4 35.9 38.2 Day4 48.2 27.1 31.7 36.2 Day5 36.4 31.7 35 32.2 Day6 26.3 32.3 47.9 23 Day7 34.5 37.9 42 33.5 Day8 27.5 33.9 45.4 35.2

Summary of AAQ SO2 Results – (Jan – Dec, 2017) 17-Jan SO (ug/m3) Days 2 Ramaraopet pet Shettipalli Tekumatla Jaipur Rasulpalli Pegadapalli Day1 8 11.5 8.8 10.1 8.3 8.2 Day2 10.6 13.8 10.9 10.1 9.8 11.5 17-Feb Day1 8.9 9.2 9.1 9.2 7.7 11.1 Day2 11.5 12.3 11.9 14.8 10.6 11.2 17-Mar Day1 13.5 14.3 10.5 12.5 11.3 15.4 Day2 10.5 14.6 11.3 12.6 11.2 10.5 17-Apr Day1 9.2 10.2 9.4 12.1 10.4 8 Day2 14.8 16.8 14.8 11.2 13.9 8 17-May Day1 10.9 10.5 8.9 10 9.2 8.3 Day2 9.6 10 7.2 10.6 9.6 8 17-Jun Day1 10.2 15.2 12.4 8.3 9.4 13.2 Day2 14.9 11.9 10.2 11.5 12.2 11.6 17-Jul Day1 9.9 8.2 8.9 8.6 8.6 12.8 Day2 11.7 15.4 12.6 10.8 13.2 14.6 17-Aug Day1 10.6 12.3 8.2 12.8 11.3 13.6 Day2 12.1 11.6 10.6 8.9 7.6 14.2 17-Sep Day1 10.6 13.6 14.1 Day2 11.3 11.2 12.1 17-Oct Day1 10.2 11.8 10.8 9.7 Day2 12.4 12.4 13.4 12.2 Day3 13.9 16.6 13.9 13.2 Day4 11.6 13.2 11.3 11

Day5 10.3 14.1 12 9.8 Day6 13.2 15.4 14.4 12.6 17-Nov Day1 16.1 10.5 12.9 15.3 Day2 14 15 14.1 13.3 Day3 13.9 13.1 14.8 14.1 Day4 12.3 15.6 11.3 10.8 Day5 10.1 17.6 12.3 11.7 Day6 14.2 14.5 14.7 14 Day7 13.6 12.9 13.5 12.9 Day8 16.1 14.5 14.7 14 17-Dec Day1 11.4 10 11.2 12.8 Day2 13.9 12.2 12.5 12.2 Day3 15.6 14.1 11.8 13.3 Day4 13 11.2 11.6 15 Day5 11.5 12 10.2 12.3 Day6 14.8 13.1 12.2 11 Day7 18 17.4 11 12.3

Day8 15.7 12.8 12 12.8

Summary of AAQ NOx Results – (Jan – Dec, 2017) 17-Jan NOx (ug/m3) Days Ramaraopet pet Shettipalli Tekumatla Jaipur Rasulpalli Pegadapalli Day1 10.7 13.5 10.6 12.6 12.6 12.4 Day2 13 16.9 13.9 13.2 14.4 13.9 17-Feb Day1 16.3 11.6 13.5 14.1 10.8 14.6 Day2 18.6 18.6 15.3 21.2 16.2 15.2 17-Mar Day1 18.1 19.4 15.7 15.4 16.2 20.3 Day2 17.4 21.2 16.2 17.4 16.2 17 17-Apr Day1 14.3 15.8 17.1 15 15.8 15.6 Day2 21.3 21.3 18.7 19.5 21.2 15.6 17-May Day1 16.7 15.4 13.8 17.8 15.8 16.8 Day2 14.2 14.3 10.8 18.5 16.7 18.7 17-Jun

Day1 15.2 19.4 16.8 16.4 15.5 21.4 Day2 18.3 15.1 13.4 13.4 14.8 15.6 17-Jul Day1 14.9 11.2 18.4 17 14.8 18.9 Day2 16.2 21.3 18.4 18.1 16.7 22.1 17-Aug Day1 14.2 14.2 15.4 15.7 18.4 19.1 Day2 18.9 16 15.4 14.3 13.5 18.2 17-Sep Day1 15.1 17.5 19.6 Day2 17.8 18.2 17.4 17-Oct Day1 14.4 16.6 18.9 15.7 Day2 18.6 18.6 19.9 20.3 Day3 16 19.3 16 17.5 Day4 17.7 17.4 17.2 19.3 Day5 13.7 20.2 14.4 15 Day6 18.7 21.7 18.5 20.4 17-Nov Day1 21.2 26.3 17 18.2 Day2 20.5 22.3 18.5 22.4 Day3 16 21.7 16.6 18.1 Day4 18.8 23.1 15.4 16.8 Day5 17.2 20.1 14 15.3 Day6 18.6 22 18.3 20 Day7 16.7 21.1 17.3 18.9 Day8 20.7 18.2 18 19.7 17-Dec Day1 16.6 15.8 18 18.2 Day2 21.4 17.7 18.9 20.6 Day3 18.4 18.3 15.2 17.9 Day4 20.4 16.5 16.3 19.1 Day5 15.8 19.2 13.7 20.9 Day6 21.5 20.6 17.6 17 Day7 24.4 18 16.2 17.3 Day8 15.6 21.2 17.6 18.2

Annexure-E8 Characteristics of Coal (December 2017)

Result Test S No. Parameters Unit method HMC-1 HMC-2 HMC-3 HMC-4 1 Chromium as Cr mg/Kg SW846-6010B 15 28 24 12 2 Cadmium as Cd mg/Kg SW846-6010B BDL BDL BDL BDL 3 Lead as Pb mg/Kg SW846-6010B BDL BDL BDL BDL 4 Zinc as Zn mg/Kg SW846-6010B 19 123 96 31 5 Iron as Fe mg/Kg SW846-6010B 652 11023 10082 8340 6 Cobalt as Co mg/Kg SW846-6010B BDL BDL BDL BDL 7 Manganese as Mn mg/Kg SW846-6010B 230 309 234 309 8 Copper as Cu mg/Kg SW846-6010B 16 18 14 18 9 Molybdenum as Mo mg/Kg SW846-6010B BDL BDL BDL BDL 10 Nickel as Ni mg/Kg SW846-6010B 10 16 11 12 11 Vanadium as V mg/Kg SW846-6010B 8 6 12 14 12 Silver as Ag mg/Kg SW846-6010B BDL BDL BDL BDL 13 Aluminium as Al mg/Kg SW846-6010B 1375 1450 1325 1705 14 Arsenic as As mg/Kg SW846-6010B BDL BDL BDL BDL 15 Selenium as Se mg/Kg SW846-6010B BDL BDL BDL BDL 16 Mercury as Hg µg/Kg SW-7471A BDL BDL BDL BDL As per CHNS 17 Sulphur content % instrument 0.48 0.54 0.56 0.56 manual 18 Ash content % ISO-1171:2010 53.2 54.6 54.1 49.6

Annexure – E9 Status and progress of 10 km railway line from Srirampur CHP

Out of total 21 Km length of railway track from Srirampur CHP to STPP, 20.50 Km length of track is in advance stage of execution and total track line is expected for completion / commissioning by end of May, 2018.

The latest photos taken at various locations are furnished hereunder for your ready reference.

Director (E&M) SCCL Photographs of Railway line from Srirampur CHP to STPP