<<

1 12 FEBRUARY 2018 James Pickard

Vauxhall Station Roundabout 2

Background • is a complex multiple lane roundabout, linking the A5201 Old Street and the A501 .

• The roundabout is located within the Borough of , however the area immediately to the east falls within the London Borough of Hackney.

• The Old Street area as a whole suffers from a lack of open green space, as identified in the London Borough of Islington’s Opportunity Area Planning Framework. 3

Background • The proposed layout will contribute towards significant economic opportunities and the Gateway to ‘Tech City’ and supporting economic growth in the area.

• The scheme will help deliver the Mayor’s Transport Strategy commitment of providing Healthy Streets by helping to encourage Londoners to walk, cycle and use public transport.

• Our Principal Contractor, Morgan Sindall will carry out the works with close supervision from TfL. 4

Public Consultation

• We consulted on the scheme in early 2015.

• 87 per cent of respondents felt the proposed changes would improve conditions for pedestrians and cyclists.

• 63 per cent of respondents felt the scheme would improve conditions for bus and tube passengers.

• There were a wide a range of written comments, including a number of different suggestions for what use we might make of a new peninsula space that would be created. 5 Transformation 6 Proposed Scheme

• Remove the existing roundabout and close the northwest arm to create a new public space.

• Switch road traffic movements to two-way operation.

• Improve facilities for cyclists travelling through the junction with segregated cycle lanes and safe traffic signal controlled crossings at surface level. 7 Proposed Scheme

• Build a new main entrance and a new lift to connecting to the retail concourse below, both accessible from the new public space.

• Close three of the four existing station subway entrances. The existing stepped entrance on the north- west side of the junction will be retained and the south-east subway will be modified to create a new stepped access in Cowper Street.

• Install urban realm improvements in the new public space. Plans to be finalised and agreed with the Islington Council. 8 Existing Junction 9 New Main Station Entrance, Lift & Public Space 10 New Cowper Street Station Entrance 11 What is happening and when

• Phase A – Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street. o Required to facilitate construction of new stepped entrance. o Working hours: Mon – Fri, 8am to 5pm.

• Phase B – Advanced Works (Mar 2019 to Apr 2019) o Removal of traffic islands on all arms of the roundabout and relocation of existing bus stops. o Required to facilitate safe movement of traffic when main works commence. o Proposed Working hours: Mon to Sun, 8.30pm to 5.30am. Night works required to minimise traffic impact during the day. 12 Phase B – Advanced Works (Mar 2019 to Apr

TM Phase 1 – Old street East island TM Phase 2 – City road South island 2019) removal removal

TM Phase 4 – City road North island TM Phase 3 – Old street West island removal removal 13 What is happening and when

• Phase C – Main works (May 2019 to Nov 2019)

o Closure of the south eastern arm of the roundabout to traffic. Two-way traffic flow o Creation of dedicated cycle and pedestrian routes through the works site o Required to build the new station entrance at Cowper Street and subway works o Proposed Working hours: Mon – Sat, 7am to 7pm o Some night time works between 8.30pm and 5.30am due to LU operations 14

Phase C – Main Works (May 2019 to Nov 2019) TM Phase 5 – Traffic Switch to two way operation 15 What is happening and when

• Phase D – Main works (Nov 2019 to Oct 2020)

o Closure of the north western arm of the roundabout to traffic. Two way traffic flow o Required to build the new main station entrance o Required to build the new station lift o Required to transform the roundabout into a new public space o Required to close Subways 1 and 3 permanently o Proposed Working hours: Mon – Sat, 7am to 7pm o Some night time works between 8.30pm and 5.30am due to LU operations 16

Phase D – Main Works (Nov 2019 to Oct 2020) TM Phase 7A – Traffic Switch to two way operation (permanent)

TM Phase 7B – Subway 1 closed & filled

TM Phase 8 – Subway 3 closed & filled 17

Programme

Milestone Date

Start Phase A Enabling Works Nov 2018 Start Detailed Design Jan 2019 Start Phase B Advanced Works (traffic island removals) Mar 2019 Start Phase C Main Works (new station entrance at Cowper Street) May 2019 Start Phase D Main Works (new main station entrance, lift, open space) Nov 2019 New Cowper Street entrance opened Feb 2020 Subway 1 closed Mar 2020 New main station entrance opened Jul 2020 Subway 3 closed Aug 2020 New lift operational Sep 2020 Construction completed Oct 2020 18 During construction

• Our main priority is the health and safety of all road and station users throughout the works.

• We will continue to maintain safe pedestrian access to Old Street Station throughout the works.

• We will continue to provide safe cycle and pedestrian provision throughout the works.

• We will minimise disruption keep traffic moving by monitoring the road network via our 24/7 traffic control centre, balancing queues protecting buses.

• We will keep noise and dust levels to a minimum. • 19 Local Impacts during construction • Phase B – Night works and noisy works (Mar to Apr 2019)

• Traffic and pedestrian management: o Changes to your usual walking and cycling routes o Changes to your subway/station access routes o Advance signage will be in place

• Bus stop relocations on Old Street: o On the western arm of the roundabout the eastbound bus stop is being relocated 30m towards the west o On the eastern arm of the roundabout the westbound bus stop moving 65m towards the east

• Relocation of cycle hire station, capacity will be maintained. 20 Communications & Engagement • We will keep the public and stakeholders up to date throughout the project.

• We are working closely with the London Boroughs of Islington and Hackney to make sure we inform as many affected people as possible of the upcoming works.

• Our Communications teams will look at how we can minimise disruption for the travelling public as well as local residents and businesses.

• We will be helping customers to understand the changes before, during and after construction and helping them to plan their journeys in advance and by knowing their travel options. 21 Communications & Engagement • A host of channels will be used to publicise the works in advance of each stage.

• TfL website - tfl.gov.uk/travel- information/improvements-and-projects/old-street- roundabout • Social media and press announcements • Station and bus stop posters and leaflets • Drop in sessions • Customer emails - including our weekly information in the weekly multi-modal email • Metro and other press articles • Regular letters drops to the local community – 2 wks in advance • Use of temporary and permanent VMS signage • Attendance at Ward Partnership and Residents Forums 22

Who to contact?

• PLO: David Kingston ([email protected] - 07811 200919) – Available on Tuesdays and Thursdays (this will be enhanced as works progress). The PLO will be based in a surface level office for public to ask questions.

• TfL Contact Centre : 0343 222 1234

• TfL Local Communities and Partnerships team: [email protected] 23 Questions