At

For

M/s. DSS BUILDTECH PVT. LTD.

June,2018 Schedule: 8 (b), Category: B Built Up Area: 1, 57,562.486 sqm

QCI Certificate no. NABET/EIA/1619/RA 0064

Prepared By GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD. (Accredited by QCI/NABET, Approved by MoEFCC, GoI, ISO 9001:2008 Certified Co.) F-374-375, Sector-63, Noida, U.P. Ph.: 0120- 4044630, Telefax: 0120- 2406519 Email: [email protected], [email protected] Website: http://www.grc-india.com GRC INDIA TRAINING & ANALYTICAL LABORATORY (Accredited by NABL, Recognized by MoEFCC, GoI) A unit of GRC India

TABLE OF CONTENT

Table No. Description Pagee No. CHAPTER 1 Introduction 1-9 1.1 Preamble 1 1.2 General Information 1-2 1.3 Environmental Clearance Process 2 1.4 Validity of Environmental Clearance 2-3 1.5 Post Environmental Clearance Monitoring 3 1.6 Transferability of Environmental Clearance 3 1.7 Generic Structure of Environment Impact Assessment 3-5 1.8 Profile of Project proponent 5 1.9 Brief Description of Project 5-6 1.10 Applicable Legal Framework 6 1.11 Need of the EIA Study 6 1.12 Scope of Study 7 1.13 Study Methodology 7-8 1.14 EIA Methodology 8-9 CHAPTER 2 Project Description 10-36 2.0 Introduction 10 2.1 Project location and Site Surroundings 10-11 2.2 Brief Project Details 11-12 2.3 Population Details 12-13 2.4 Power supply 13-14 2.5 Requirement of Natural Resources 14 2.6 Design Consideration 14 2.7 Parking Facilities 14-16 2.8 Water Requirement 16-20 2.9 Sullage Generation & Treatment 20-21 2.10 Sewage Treatment Plant 21-24 2.11 Rainwater Harvesting 24-27 2.12 Solid Waste Management 27-33 2.13 Landscape 33 2.14 Manpower Requirement 33-34 2.15 Fire Fighting System 34-35 2.16 Details of Construction Materials 35 2.17 List of Machinery used during Construction 35-36 CHAPTER 3 Description of the Environmeent 37-83 3.1 Introduction 37 3.2 Study periodo 37 3.3 Study area 37 3.4 Baseline monitoring of environmental component 37-83

CHAPTER 4 Anticipated Environmental Impacts &Mitigation 84-107 Measures

4.1 Introduction 84 4.2 Impact matrix 85-86 4.3 Pollution sources 87-88 4.4 Impact identification 89-90 4.5 Assessment of Environmental Impacts During Development and 90-100 Construction Phase 4.6 Assessment of the environmental impacts during operation phase 100-107 CHAPTER 5 Analysis of Alternative 108-115 5.1 Introduction 108 5.2 Building Materials 108-110 5.3 Natural Hazard Prone areas 111-113 5.4 Community issues 113 5.5 Energy conservation 114-115 5.6 Transportation 115 CHAPTER 6 Environmental Monitoring Prrogram 116-120 6.1 Introduction 116 6.2 Performance indictors 116-119 6.3 Data Management 120 6.4 Reporting Schedules 120 CHAPTER 7 Additional Studies 121-130 7.0 Introduction 121 7.1 Risk assessment And Disaster Management Plaan 121-125 7.2 Response In Case of earthquake 125-126 7.3 Response For LPG leakage 126 7.4 Response In case of fire 127-128 7.5 Resource conservation 1128-130 7.6 Resettlement And rehabilitation & Corporate Social Responsibility 130 CHAPTER 8 Project Benefits 131 8.1 General 131 8.2 Physical infrastructure 131 8.3 Social Infrastructure 131 8.4 Economic Benefits 131 CHAPTER 9 Environmental Management Plan 132-162 9.1 Introduction 132-133 9.2 Environmental Management Strategies 133-155 9.3 Overall Mitigation Measures and Environmental Management Plan 155-162 CHAPTER10 Summary And Conclusion 163-169 10.1 Project Background 163 10.2 Project Site and Salient Features 163-167

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM,

CHAPTER 1: INTRODUCTION

1.1 PREAMBLE EIA is a technical exercise to establish baseline environmental condition to predict environmental impact, assess their significance and provide recommendations for their mitigation. The impact assessment covers both construction and operation phase of the development. The report covers areas such as noise, air quality, ecology, water quality, hydrology, local architecture, landscape & visual character, sustainability and socio-economics. Early identification and characterization of critical environmental impacts allow the public and the Government to form a view about the environmental acceptability of a developmental project and what conditions should apply to mitigate or reduce those risks and impacts. The report describes how the project has been improved through the EIA process.

This report has been prepared as per the EIA Notification, 2006 and its amendments; ToR prescribed by SEAC, Haryana and Technical Guidance Manual for Building Construction, Townships and Area Development projects.

1.2 GENERAL INFORMATION ON PROJECT M/s DSS Buildtech Pvt. Ltd. has proposed Expansion of Group Housing Project “The Melia” at Village Mohammadpur Gujjar, Sector-35, Sohna, District- Gurugram, Haryana.

The existing part of the project was accorded Environmental Clearance by SEIAA, Haryana vide Letter no. SEIAA/HR/2016/807 dated 20/09/2016 for Plot area 70,455.77 m2 (or 17.41 acres) and Built-up area 1, 52,000 sqm (Tower A to I, S1, S2, EWS). A copy of the EC letter is enclosed as Annexure – I.

Consent to Establish (CTE) has also been obtained for existing part from HSPCB vide letter no. HSPCB/Consent/: 329962316GUSCTE3395524 dated 12.11.2016. Copy of the CTE is attached as Annexure - II.

M/S DSS BUILDTECH PVT. LTD. 1

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Earlier the project was proposed for 11 residential towers which are under construction phase but now the proponent wants to develop one more tower i.e Tower “J” therefore we have now proposed for Expansion of Group Housing Project, due to which the built-up area will increase to 1, 57,562.486 sqm but plot area will remain same for which EC is being sought.

1.3 ENVIRONMENTAL CLEARANCE PROCESS As per EIA Notification, 2006 and its amendments, all building construction and area development projects covering an area ≥ 50 ha / built up area greater than 1, 50,000 m2 i.e. 1,74,524 m2 are designated as 8(b) projects, Category B, are required to obtain prior environmental clearance from respective SEAC (Haryana). The application for environmental clearance comprises submission of Form 1, Form 1A, and Conceptual Plan. Following the appraisal of the project to the satisfaction of the SEAC (Haryana), environmental clearance will be granted. As per the EIA notification, M/s. DSS Buildtech Pvt Ltd. submitted an EC application to State Level Environment Impact Assessment Authority (SEIAA), Haryana which comprised of Form I, Form IA, Conceptual Plan and proposed Terms of Reference (ToR). Thereafter, the case was placed before State Expert Appraisal Committee (SEAC), Haryana during 158th meeting held on 27th Sept., 2017 wherein Terms of Reference was granted to the project. A copy of the ToR Letter (Memo No. SEIAA/HR/2017/828 dated 30.11.2017) is enclosed as Annexure-III. Point-wise compliance to the ToR conditions is enclosed as Annexure-IV.

As per EIA Notification, 2006 and its amendments, all building construction and area development projects covering an area ≥ 50 ha / built up area greater than 1, 50,000 m2 i.e. 1,57,562.486m2 are designated as 8(b) projects, Category B, and are required to obtain prior environmental clearance from respective SEAC (Haryana).

1.4 VALIDITY OF ENVIRONMENTAL CLEARANCE As per the provisions of the EIA Notification, 2006 & its amendments, the environmental clearance granted is for a period of seven years. This may be extended by a maximum of ten

M/S DSS BUILDTECH PVT. LTD. 2

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA years, provided an application is submitted to the regulatory authority within one month before validity period with updated Form 1, Form 1A and Conceptual Plan.

1.5 POST ENVIRONMENTAL CLEARANCE MONITORING On award of Environmental Clearance, M/s DSS Buildtech Pvt. Ltd., will require to advertise the receipt of EC in at least two local newspapers.

The project management will submit the half-yearly compliance report in respect of the stipulated prior environmental clearance terms and condition in hard and soft copies to the regulatory authorities concerned on 1st June and 1st December of each calendar year.

1.6 TRANSFERABILITY OF ENVIRONMENTAL CLEARANCE A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor or the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period.

1.7 GENERIC STRUCTURE OF ENVIRONMENT IMPACT ASSESSMENT The environmental impact assessment has been carried out to assess the impact of the project on various environmental components. The methodologies and findings of the study are detailed in this report along with other relevant information under the different chapters as under:

Introduction- provides background information about the project falls in the category as defined in EIA Notification 2006 and amendment thereof based on area statement and the developers along with the legal environmental requirements of the project. The scope and EIA methodology adopted in preparation of EIA report have also been described in this chapter.

Project Description– briefly discusses the project features while elaborating on components bearing environmental consequences.

M/S DSS BUILDTECH PVT. LTD. 3

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Description of the Environment– Discusses the baseline data of environmental attributes such as air, water, soil, noise and socioeconomic environment of the area based on primary and secondary data collection at the site. Study of existing environment at the site and in the study area comprising base-line and environmental quality after receive of new development during construction & operation of the project.

Anticipated Environmental Impacts & Mitigation Measures – Predicts the environmental impacts of the various components of the project during construction and operation phases to highlight concern areas requiring mitigation measures. Accordingly, it also suggests controls and mitigation measures to offset/ minimize the adverse impact while optimizing the positive benefits from the project.

Analysis of Alternatives – Explores the alternative sites and plans that have been considered for the project and evaluates the different scenarios in the environmental context.

Environmental Monitoring Programme – Outlines a monitoring programme for the different environmental components during the construction and operation phase for evaluation of the environmental status of the region against the project development.

Additional Studies – Discusses any study that has been carried out for the purpose of better understanding of the environmental impacts of the project. It also highlights any pertinent findings from the study that will aid decision-making.

Project Benefits – Brings out the positive impacts from the project.

Environmental Management Plan – Organizes the suggested mitigation measures to aid implementation through formulation of performance indicators, reporting structure and pronounced implementation period.

M/S DSS BUILDTECH PVT. LTD. 4

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Summary & Conclusion – Summarizes the important report findings and concludes on the environmental sustainability of the project.

Disclosure of Consultants engaged – gives the names of the technical team involved in the report preparation with accreditation of consultant from the Quality Council of India.

1.8 PROFILE OF PROJECT PROPONENT M/s DSS Buildtech Pvt. Ltd., has nominated Mr. Paras Kumar Jain as the authorized signatory to represent the company before SEIAA/SEAC for the Environmental Clearance of this Expansion of Group Housing Project “The Melia”.

The contact details of project proponent are as follows:

Registered Address: M/s DSS Buildtech Pvt. Ltd., 506, Time Square Building, B Block, Sushant Lok, Phase I, District-Gurugram, Haryana

Correspondence Address: M/s DSS Buildtech Pvt. Ltd., 506, Time Square Building, B Block, Sushant Lok, Phase I, District-Gurugram, Haryana M: 9810605575 [email protected]

1.9 BRIEF DESCRIPTION OF PROJECT 1.9.1 Project Background The project site is located at Village-Mohammadpur Gujjar, Sector-35, Sohna, District- Gurugram, Haryana on a land measuring 70,455.77 m2 (17.41 acres). The estimated built up area of the project (post expansion) will be 1,57,562.486 m2.

M/S DSS BUILDTECH PVT. LTD. 5

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The geographical coordinates of project site are 28 16 55.59 N and 77 03 26.64 E.

There is neither any litigation (s) pending against the project and / or any directions or order passed by any court of law/any statutory authority against the project.

1.9.2 Site Description The Nearest Highway is SH-8 which is 0.60 km (E) away from project site. The nearest Railway Station being Garhi Harsaru Railway Station is about 21.80km (NW) away from the project site. The nearest Airport is Indira Gandhi International Airport at 29 km (N) from project site.

1.10 APPLICABLE LEGAL FRAMEWORK The project falls under item 8(b), Category B, as per the notification 2006 and its amendments. The total estimated built-up area of the project (post expansion) is 1, 57,562.486m2. The project proponent is required to comply with the provisions of Environment Protection Act, 1986; Air (Prevention & Control of Pollution) Act 1981; Water (Prevention & Control of Pollution) Act 1974 and Hazardous Wastes (Management, and Handling) Rules, 1989 amendments thereto.

1.11 NEED OF THE EIA STUDY The project activities must co-exist in harmony with its surrounding environment, to reduce the environmental impact, which is likely to arise during various project activities. To safeguard the environment from adverse effects of developmental activities, the MoEFCC has issued guidelines to optimize the use of natural resources and protect environment for sustainable development. As per the MoEFCC notification dated 14.09.06, EIA study is required to be carried out for the projects having either plot area of 50 ha and or built up area greater than 1,50,000 m2. Since, the estimated built-up area of the project (post revision & expansion) is 1,57,562.486m2, an EIA/EMP report has been prepared and submitted herewith for Environmental Clearance for the project.

M/S DSS BUILDTECH PVT. LTD. 6

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

1.12 SCOPE OF STUDY The scope of the EIA study is:-  Compilation of baseline environmental and social scenario of the study area within a radius of 10 km around the project site based on field studies covering one season (March-May 2015 and October- November 2015), and secondary data collection;  Identification, prediction and evaluation of potential environmental impacts expected during the construction and operation phase of the project;  Preparation of mitigation measures, Environmental Management Plan (EMP) and Monitoring Programme for implementation of suggested mitigation measures.

1.13 STUDY METHODOLOGY The approach followed for conducting the EIA study is in accordance with the applicable regulatory framework. The main stages are described below:

Stage -I  Review of design and operational information of the project from various plans, drawing and identification of sources of major potential impacts. Stage -II  An initial review of the project site and status of the physical environment around the project site vicinity;  Understanding regarding project design and operation as well as macro environmental aspects. The major issues needed to be addressed with due care were identified and monitoring plan for the environmental baseline was prepared;  Baseline environmental assessment was conducted within the study area of 10 km radius around the project site;  Intense monitoring and primary field data collection of environmental components viz. Micro-Meteorological Condition, Ambient Air Quality, Water (Surface and Ground water) use and its Quality, Soil Quality, Noise Level, Traffic Volume etc.;  Survey study was carried out in the study area to assess the status of flora & fauna and socio- economic profile of the study area; and

M/S DSS BUILDTECH PVT. LTD. 7

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Information was also collected through Secondary sources like Department of Census, Local and City Offices, National Institutions (Survey of India, National Information Centre etc.), District Head Quarters and other Government Offices etc. as well relevant Published Literatures. Stage –III  Compilation of the Baseline Environmental Study of the Area.

Stage –IV  Assessment of Environmental Impact by predicting the scale and extent of changes associated with the project and their subsequent effects on the environment against the environmental baseline condition, and evaluating the significance of such impacts against accepted criteria. Stage -V  Identification and preparation of measures to mitigate significant impacts (evaluated from the impact prediction process) by proposing applicable alternatives and control measures; and  Finally, development of appropriate Environmental Management and Monitoring Plan to audit and ensure that the proposed mitigation measures are in place and effective.

1.14 EIA METHODOLOGY The project may have impact on environment attributes such as air, water, noise level, soil quality, hydrology and drainage pattern and meteorology of surrounding environment due to on- going project. In assessing the environmental impact, collection, collation and interpretation of baseline data is of prime importance. The objective of EIA is to predict and address potential environmental problems/concerns at an early stage of project planning and design as the infrastructure development has adverse impact on environment. EIA/EMP assists in the decision making process by identifying the key impacts/ issues as a results of the activities and formulating mitigation measures, leading to an improvement in environmental quality. In order to achieve these objectives, the following procedures have been adopted for the study:-  Collection, collation and analysis of regional and local environmental status for various environmental attributes (like topography, geology, ambient air quality, meteorology, water

M/S DSS BUILDTECH PVT. LTD. 8

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA quality, noise level, soil characteristics and land use, transport, settlement status and socio economic aspects etc.) to assess base-line status of the project.  Identification of environmental impacts leads to assessment of impact on the base-line status which will decide the feasibility of the project and suggests mitigation measures to control pollution with respect to standards applicable for the area.  Evaluation of impacts leading to preparation of environmental management and monitoring plan.  Addition study will cover disaster management plan during construction and operation phase of the project.  Environment Monitoring Plan and annual budget – one time and recurring cost of EMP will be discussed.

This report is based on scientific principles and professional judgment with resultant subjective interpretation. Professional judgments expressed herein are based on the available data and information.

M/S DSS BUILDTECH PVT. LTD. 9

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 2: PROJECT DESCRIPTION

2.0 INTRODUCTION M/s DSS Buildtech Pvt. Ltd has proposed Expansion of Group Housing Project “The Melia” at Village Mohammadpur Gujjar, Sector-35, Sohna, District- Gurugram, Haryana .The Group has made all efforts to create environment friendly project in line with the customer needs. Good Business Practices, Quality Practices, Quality Products, Integrity, Customer and Product Value guide our vision towards building a great institution.

The existing part of the project was accorded Environmental Clearance by SEIAA, Haryana vide Letter no. SEIAA/HR/2016/807 dated 20/09/2016 for Plot area 70,455.77 m2 (or 17.41 acres) and Built-up area 1, 52,000 sqm (Tower A to I, S1, S2, EWS). A copy of the EC letter is enclosed as Annexure – XXVII.

Consent to Establish (CTE) has also been obtained for existing part from HSPCB vide letter no. HSPCB/Consent/: 329962316GUSCTE3395524 dated 12.11.2016. Copy of the CTE is attached as Annexure – XXVIII.

Project Comprises of following facilities:  Residential Units (Main, EWS & Service units)  Schools  Commercial Facilities  Community Centre

2.1 PROJECT LOCATION AND SITE SURROUNDINGS 2.1.1 Location The project site is located at Village-Mohammadpur Gujjar, Sector-35, Sohna, District- Gurugram, Haryana. The geographical co-ordinates of project site are 28 16 55.59 N and 77 03 26.64 E.

M/S DSS BUILDTECH PVT. LTD. 10 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Google Earth map of 500 m radius and toposheet of 10+15 km around project site are attached as Annexure respectively. SoI Toposheet showing 10 km study area around the project site is attached as Annexure respectively.

2.1.2 Connectivity and Infrastructure The Nearest Highway is SH-8 which is 0.60 km (E) away from project site. The nearest Railway Station being Garhi Harsaru Railway Station is about 21.80km (NW) away from the project site. The nearest Airport is Indira Gandhi International Airport at 29 km (N) from project site.

2.2 BRIEF PROJECT DETAILS

The total area of project site is 70,455.77 m2 (17.41 acres). The detailed area statement along with brief details of the project is provided below in Table 2.1:

Table 2.1: Detailed Area Statement S. Particulars Existing (EC Expansion Total (Existing, EC No. Accorded) (m2) (m2) accorded +Expansion) (m2) 1. Total Plot Area 70,455.77 -- 70,455.77 Net Plot Area 67,915.15 -- 67,915.15 2. Permissible Ground Coverage 23,770.30 -- 23,770.30 (@ 35% of net plot (@ 35% of net plot area) area) 3. Proposed Ground Coverage 11278.45 527.76 11,806.21 (@16.6% of net (@17.4% of net plot plot area) area) 4. Total Permissible FAR 11,8851.51 -- 1,18,851.51 (@1.74 of net plot (@1.75 of net plot area) area) 6. Total Proposed FAR 1,13,522.75 5085.68 1,18,608.43 (@1.67 of net plot (@1.74 of net plot area) area) 7. Non FAR 38,477.21 476.846 38,954.056  Services (Balcony, Mumty & 1,680.756 423.874 2104.63

M/S DSS BUILDTECH PVT. LTD. 11 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Machine Room, etc.)  Stilt Area 2,882.664 52.972 2,935.636  Basement Area 33,913.79 ---- 33,913.79 8. Total Built Up Area (6+7) 1,52,000 5805.566 1,57,562.486 9. Green Area Proposed 18,882.14 1612.52 20,494.66 (@26.8% plot (@30.17%) area) 10. Maximum Height of the 44.9m -- 44.9m Building (meter)

Table 2.2: Built-up Area Details

S. Particulars Existing (EC Expansion Total (Existing, EC No. Accorded) (m2) (m2) accorded +Expansion) (m2) 1. Total Proposed FAR 1,13,522.75 5085.68 1,18,608.43 (@1.67 of net (@1.74 of net plot plot area) area) 2. Non FAR 38,477.21 476.846 38,954.056 Total Built Up Area 1,52,000 5805.566 1,57,562.486

2.3 POPULATION DETAILS The total population of proposed project is 8914 persons. The Comparative population as per the previous EC and after Expansion/Modification is shown in Table 2.3:

Table 2.3(a): Comparative Population Distribution (EC Accorded +Expansion) S. No. Particulars Value as per EC Accorded Expansion Total (EC Accorded + Expansion) 1 Dwelling units 917 78 995

Table 2.3(b): Comparative Population Distribution (EC Accorded +Expansion) S. No. Particulars Value as per EC Accorded Expansion Total (EC Accorded +Expansion) 1 Population 7,628 1286 8914

The detailed population breakup (Expansion) is given below in the following Table 2.4.

M/S DSS BUILDTECH PVT. LTD. 12 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Table 2.3(c ): Population Break-up (EC Accorded +Expansion)

S. No. Description DUs/FAR (sqm) PPU Total Population 1. Residential  Main Units 995 5 4975  EWS Units 176 5 880  Service Units 100 2 200 Total Residential Units 6055 2. Maintenance Staff 5% of Main unit 249 3. Visitors 10 % of total residential population 605 4. Primary School (1485.656 371 sqm) 5. Nursery School (195.1 49 sqm) 6. Commercial Population @3m2 / person 96 (289.065 sqm)  Staff 19  Visitors 77 7. Community Center 1 @1.5 m2 / person 937 (1406.82 sqm) 8. Community Center 2 @1.5 m2 / person 552 (827.93 sqm) Grand Total Population 8914

2.4 POWER SUPPLY 2.4.1 Source of Power Requirement The power supply will be supplied by Dakshin Haryana Bijli Vitran Nigam (DHBVN). The maximum load demand for the Expansion of Group Housing Project will be approx. 6063 kW.

M/S DSS BUILDTECH PVT. LTD. 13 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

2.4.2 Power back-up There is provision of 2 no. of DG sets of total capacity 1635 kVA (1 x 1010 kVA & 1 x 625 kVA) for power back up in the Expansion of Group Housing Project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion.

2.5 REQUIREMENT OF NATURAL RESOURCES It is proposed to use environment friendly construction material that is locally available to reduce concerns related to transportation of materials as well as achieve cost-effectiveness. It is proposed to use fly ash mixed cement, and bricks for the construction of the project. The use of timber will be minimal with the provision of aluminum frames for windows. Paints with low VOC and no ammonia are proposed to be used for all residential buildings.

2.6 DESIGN CONSIDERATION The project structures have been designed after due study of the local architecture. The project area is largely undeveloped and does not bear any significant architectural aspect. Likewise, the building has been planned with modern design and facilities with large stretches of open spaces. The following standards and bye-laws will be followed for designing the various units:  Building bye laws  Relevant IS Codes of Practice Published by Bureau of Indian standards  Manual on Sewerage and Water by Ministry of Urban Development  National Building Code, 2016

2.7 PARKING Adequate provision will be made for car/vehicle parking at the project site. Parking details are provided below: Table 2.7: Comparative Parking Distribution (EC Accorded +Expansion) S. No. Particulars Value as per EC Accorded Expansion Total Parking (EC Accorded

M/S DSS BUILDTECH PVT. LTD. 14 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA +Expansion) 1 Parking 1758 2 1760

Parking Required: As per MoEFCC norms For Residential facilities = 1 ECS/ 100 m2 FAR area = 1, 18,626.44/100 = 1186 ECS Total parking required as per MoEFCC norms = 1186 ECS

As per Haryana Bye laws: Required parking for residential = 1.5 ECS/ DU = 1.5 x 995 = 1492 ECS For EWS @ 5% of residential parking = 75 ECS

Total Required Parking = 1492+75 = 1567 ECS

PARKING PROPOSED (EC Accorded +Expansion): Area proposed for Stilt parking = 2040 Area proposed for 1 ECS of Stilt parking = 30 m² Parking proposed for Stilt parking = 68 ECS

Area proposed for Surface Parking = 9875 m2 Area proposed for 1 ECS of Surface Parking = 25 m² Parking proposed for Surface Parking = 395 ECS

Area proposed for Upper Basement Parking = 15067.17 m2 Area proposed for 1 ECS of Upper Basement Parking = 35 m² Parking proposed for Upper Basement Parking = 431 ECS

M/S DSS BUILDTECH PVT. LTD. 15 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Total Parking proposed for Upper Basement Parking = 431 ECS + 431(Mechanical Parking) = 862 ECS

Area proposed for Lower Basement Parking = 15,221.72 m2 Area proposed for 1 ECS of Lower Basement Parking = 35m² Parking proposed for Lower Basement Parking = 435 ECS

Total Basement Parking = 1297 ECS

TOTAL PARKING PROPOSED = 68 + 395 + 1297= 1760 ECS

2.8 WATER REQUIREMENT During operation phase, the source of water supply will be HUDA. The total water requirement is approx. 707 KLD, out of which total domestic water requirement is 563 KLD. The fresh water requirement is approx. 415 KLD and the one time fresh water requirement will be 707 KLD.

Comparative water calculation as per the previous EC and after Expansion is shown in Table 5. The daily water requirement calculation is given below in Table 2.8 (a)

Table 2.8 (a): Comparative water calculation (EC Accorded + Expansion) S. Particulars Value as per EC Expansion (KLD) Total (EC Accorded + Expansion) (KLD) No. Accorded (KLD) 1 Total water 863 -156 707 Requirement 2 Domestic Water 492 71 563

M/S DSS BUILDTECH PVT. LTD. 16 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA 3 Fresh Water 512 -97 415 4 Waste Water 643 -225 418 Generated 5 STP 800 -295 505

The daily water requirement calculation is given below in Table 2.8 (b): Table 2.8 (b): Calculations for Daily Water Demand (EC Accorded + Expansion) Total Water Requirement (EC S. Description Rate of water demand Accorded + Expansion) No. Occupancy (lpcd) A. Domestic Water Residents: Fresh Flushing Fresh Flushing Total  Main Units 4975 @ 65 lpcd @ 21 lpcd 323 105 428  EWS Units 880 @ 65 lpcd @ 21 lpcd 57 19 76  Service Units 200 @ 65 lpcd @ 21 lpcd 13 4 17  Staff 688 @15 lpcd @15 lpcd 10 10 20 (Maintenance, Schools, Commercial, facilities)  Visitors 2171 @ 5 lpcd @5 lpcd 11 11 22 (Community facilities etc) 414 KLD 149 KLD 563 KLD

Total Domestic Water = 563 KLD B. Horticulture 20,494.66 m2 7 l/sqm 143 KLD

C. Make up Water 1 KLD for Swimming (127 sqm) Pool Grand Total (A+B) = 707 KLD

TABLE 2.8 (c ): WASTE WATER CALCULATIONS (EC Accorded + Expansion)

M/S DSS BUILDTECH PVT. LTD. 17 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA DOMESTIC WATER REQUIREMENT 563 KLD  Fresh 414 KLD  Flushing 149 KLD Waste water generated [@80% fresh + 100% flushing] 331 + 87 = 418 KLD STP Capacity 875 KL

The water balance diagrams for different seasons are shown below:

FRESH WATER @ 80% @ 80% FRESH WATER (414 KLD) SULLAGE GENERATED = 33 KLD (414 +1 =415 KLD) (418 KLD +33 KLD) @ 100% STP CAPACITY =875 KL 149 KLD FLUSHING (149 KLD)

41 KLD WET SLUDGE

KLD (41 KLD) KLD 143 KLD HORTICULTURE* 42 (98% of total

(143 KLD) 376 untreated water)

KLD = = KLD

KLD = = KLD 418 418

418 418 EVAPORATED WATER 1 KLD 1 KLD

(1 KLD) @ 10% of of 10% @

SWIMMING POOL (2 % of total @ 90% of of 90% @ (1 KLD) untreated water)

84 KLD DISCHARGE TO EXTERNAL SEWER (84 KLD)

*Considering horticulture water demand @7l/sqm

Wastewater

Treated effluent Fresh water

M/S DSS BUILDTECH PVT. LTD. 18 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Figure 2.1: Water Balance Diagram (Summer Season)

@ 80% @ 80% FRESH WATER FRESH WATER (414 KLD) SULLAGE GENERATED = 33 KLD (414 +1 = 415 KLD) (418 KLD +33 KLD) @ 100% STP CAPACITY =875 KL 149 KLD FLUSHING (149 KLD)

41 KLD WET SLUDGE

(41 KLD) HORTICULTURE* 61 KLD (98% of total (61 KLD) untreated water)

EVAPORATED WATER (1 KLD) 1 KLD 1 KLD (2 % of total untreated

water)

SWIMMING POOL @10% of 418 KLD = 42 KLD

@90% of 418 KLD = 376 KLD (1 KLD)

166 KLD DISCHARGE TO EXTERNAL SEWER (166 KLD)

*Considering horticulture water demand @3 l/sqm

Wastewater

Treated effluent Fresh water

Figure 2.2: Water Balance Diagram (Monsoon Season)

M/S DSS BUILDTECH PVT. LTD. 19 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

@ 80% @ 80% FRESH WATER FRESH WATER (414 KLD) SULLAGE GENERATED = 33 KLD (414 +1 = 415 KLD) (418 KLD +33 KLD) @ 100% STP CAPACITY = 875 KL 149 KLD FLUSHING (149 KLD)

41 KLD WET SLUDGE

(41 KLD) HORTICULTURE* 82 KLD (98% of total (82 KLD) untreated water)

EVAPORATED WATER (1 KLD) 1 KLD 1 KLD (2 % of total untreated

water)

SWIMMING POOL @10% of 418 KLD = 42 KLD

@90% of 418 KLD = 376 KLD (1 KLD)

145 KLD DISCHARGE TO EXTERNAL SEWER (145 KLD)

*Considering horticulture water demand @4 l/sqm

Wastewater

Treated effluent Fresh water

Figure 2.3: Water Balance Diagram (Winter Season)

2.9 Sullage Generation & Treatment It is expected that the project will generate approx. 418 KLD of wastewater. The wastewater will be treated in onsite STP of 875 KL capacity. The treated effluent will be reused for flushing & horticulture. Surplus treated effluent will be discharged to external sewer.

M/S DSS BUILDTECH PVT. LTD. 20 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  10% of the waste water that is to be treated is removed from the STP in form of sludge as well as vapors.

 Out of this 10%, approx. 98% of the untreated waste water is removed as wet sludge, which is then dewatered by passing through a filter press and extracted water is added back to the collection chamber of the STP. Somewhat around 40% of the moisture of the sludge is retained, and the sludge thus generated is further processed by drying the same on a non- permeable bed, which upon drying can be used as manure in the green area provided within the project site. The wet sludge is generally removed during the processes of primary treatment, secondary treatment and tertiary treatment or scrubbed off of the collection tank.

 Remaining 2% of waste water is evaporated from the system during treatment process and thus cannot be converted into sewage.

2.10 SEWAGE TREATMENT TECHNOLOGY (MBBR TECHNOLOGY)

MBBR TECHNOLOGY An external sewage network shall collect the sewage from all units, and flow by gravity to the sewage treatment plant. Following are the benefits of providing the Sewage Treatment Plant in the present circumstances:  The process has long retention time and can absorb shock load situation.  Reduced net daily water requirements, source for Flushing and Horticultural purposes by utilization of the treated waste water.  Reduced dependence on the public utilities for water supply and sewerage systems.  The process produces a well-oxidized sludge in small quantities only, which can be removed and used as manure.

M/S DSS BUILDTECH PVT. LTD. 21 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA a. Wastewater Details (a) Daily load : 418 KLD (b) Duration of flow to STP : 24 hours (c) Temperature : Maximum 32oC (d) pH : 6.5-8.5 (e) Colour : Mild (f) T.S.S. (mg/l) : 250-400 mg/l

(g) BOD5 (mg/l) : 300-400 mg/l (h) COD (mg/l) : 600-700 mg/l b. Treated effluent (a) pH : 6.0 to 8.5 (b) B.O.D. : <20 mg/l (c) C.O.D. : <100 mg/l (d) Total Suspended Solids : <20mg/l c. Treatment Technology MBBR TECHNOLOGY

Moving bed biofilm reactor technology is based on the principle of attached growth process. Raw sewage will be collected under gravity into the equalization tank after allowing to pass through the bar screen. Screens will be provided in screen chambers and it will be manually cleaned by going down to a platform. The bar screen, by removing coarse solids from the sewage help in protecting the raw sewage pump. Fully submersible centrifugal non clog sewage handling pump will be provided in the collection cum equalization tank to pump the collected waste water to the next MBBR tanks. Automatic level controller will be provided in the tank to turn the pump off at the low water level in the tank and to start the pump when water level is high automatically. Air will be introduced in this tank to prevent any potential foul smell problem & to provide the mixing

M/S DSS BUILDTECH PVT. LTD. 22 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA of wastewater to avoid the sedimentation of solids in this tank. Air Grid used for aeration purpose shall be non-clog. The sewage collected in equalization tank is pumped the moving bed bioreactor. There shall be two nos. of bioreactors in series for the efficient working and removal of BODs for the required retention time. The process inside the moving bed bioreactors consists of adding small cylindrical-shaped polyethylene/polypropylene carrier elements in aerated basins to support biofilm growth. The small cylinders are provided with a cross inside the cylinder and longitudinal fins on the outside. The biofilm carriers are maintained in the reactor by the use of a perforated plate with appropriate slot at the tank outlet. Air agitation or mixers are applied in a manner to continuously circulate the packing. The packing may fill 25 to 50 percent of the tank volume. Specific surface area of the packing is about 450-500m2/m3 of bulk packing volume. The waste water from first bioreactor flows by gravity through the perforated plate/mesh to the next bioreactor kept in series. Inside the bioreactors, aerobic bacteria grow in an attached growth from around the moving plastic media inside the reactors. The bacteria have to reduce BOD & COD of waste water in the presence of oxygen provided through the air grids located at the bottom of the reactors. The Process does not require any return activated sludge flow or backwashing. From the bio-reactors, the effluent passes by gravity into the clarifier (Tube Settling Tank). Clarifier will be a hopper bottom sedimentation tank provided with appropriate size PVC tube deck media. The suspended solids will settle at the bottom of the tank & clear supernatant will overflow to filter feed tank through outlet launder. The collected sludge at bottom shall be transferred through pumps to sludge holding tank. The clear supernatant after clarifier will be collected in to filter feed tank. This tank will act as housing tank for filter feed pumps. The clarified & dis-infected water will be then fed to filtration unit.

Filtration unit consisting of Dual Media sand filter, activated carbon filter and ultra-filtration system (optional) will remove the residual impurities such as odor/color, suspended solids, BOD/COD. The treated water after the filtration unit will be collected in Irrigation cum

M/S DSS BUILDTECH PVT. LTD. 23 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Flushing water storage tank from where it is transferred to flushing water tank at terrace & Irrigation System. Excess sludge from the bottom of the settling tank will be removed and transferred to sludge holding tank. Air grid shall be provided in this tank to avoid conversion into anaerobic conditions, thickening of sludge and keep sludge in homogenous condition. The digested & thickened sludge shall be further thickened through Sludge Dewatering System (Filter press with screw pump) and disposed-off periodically through closed tanker or can be reused as manure.

Figure 2.4: Schematic Diagrams for STP Based on MBBR Technology

2.11 RAINWATER HARVESTING The storm water collection system for the premises shall be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area and the time required for such flow to reach the drains. The drains shall be located near the carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads shall flow towards the drains. Storm water from various plots/shall be connected to adjacent drain by a pipe through catch basins. Therefore, it has been calculated to provide 18 rainwater harvesting pits at selected locations, which will catch the maximum run- off from the site.

M/S DSS BUILDTECH PVT. LTD. 24 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA 1) Since the existing topography is congenial to surface disposal, a network of storm water pipe drains is planned adjacent to roads. All building roof water will be brought down through rain water pipes. 2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular intervals for rain water harvesting and ground water recharging. 3) For basement parking, the rainwater from ramps will be collected in the basement storm water storage tank. This water will be pumped out to the nearest external storm water drain. 4) The peak hourly rainfall of 45 mm/hr shall be considered for designing the storm water drainage system.

Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak hourly rainfall has been considered as 45 mm/hr. The recharge pit of 5 m diameter and 4 m depth is constructed for recharging the water. Inside the recharge pit, a recharge bore is constructed having adequate diameter and depth. The bottom of the recharge structure will be kept 5 m above this level. At the bottom of the recharge well, a filter media is provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan are as follows:  Catchments/roofs would be accessible for regular cleaning.  The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting has been avoided since most paints contain toxic substances and may peel off.  All gutter ends will be fitted with a wire mesh screen and a first flush device would be installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is flushed off.  No sewage or wastewater would be admitted into the system.  No wastewater from areas likely to have oil, grease, or other pollutants has been connected to the system.

M/S DSS BUILDTECH PVT. LTD. 25 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 2.11: Comparative Rain Water Harvesting Pits Distribution (EC Accorded +Expansion) S. No. Particulars Value as per EC Expansion Total (EC Accorded Accorded +Expansion) 1 Rain Water 17 1 18 Harvesting Pits

Calculations for storm water load:

Net Plot Area = 67,915.15m2

Roof-top area = Ground Coverage = 11,806.21m2 Green Area = 20,494.66 m2

Paved Area = Plot Area – (Roof-top Area + Green Area) = 67,915.15 – (11,806.21 + 20,494.66) = 67,915.15 – 32,300.87 = 35,614.28m2

Roof-top area = 67,915.15 × 0.045 × 0.90 = 2750.56 m3/hr

Green Area = 20,494.66 × 0.045 × 0.20 = 184.45m3/hr

Paved Area = 35,614.28 × 0.045 × 0.70 = 1121.84m3/hr

Total Runoff Load = 2750.56 + 184.45 + 1121.84 = 4056.85m3/hr

M/S DSS BUILDTECH PVT. LTD. 26 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Taking 20 minutes retention time, volume of storm water = 4056.85/3 = 1352.28 m3 Capacity of Recharge pit = π r2h = 3.14 × 2.5 × 2.5 × 4 = 78.5 m3

Hence No. of pits required = 1352.28/78.5 = 17.22 pits/18 pits

Total of 18 Rain Water Harvesting pits are proposed for artificial ground water recharge.

Figure 2.5: Rain Water Harvesting Pit Design

2.12 SOLID WASTE MANAGEMENT

M/S DSS BUILDTECH PVT. LTD. 27 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Solid waste would be generated both during the construction as well as operation phase. The solid waste expected to be generated during the construction phase will comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed to be followed for the management solid waste:  Garbage Bins are proposed for storage of construction materials.  The excavated material such as topsoil and stones will be stacked for reuse during later stages of construction  Excavated top soil will be stored in temporary constructed soil bank and will be reused for landscaping of the commercial project.  Remaining soil shall be utilized for refilling / road work / rising of site level at locations/ selling to outside agency for construction of roads etc.

Solid Waste

Construction Waste

Empty Construction waste, Excavated Cement Broken Bricks, Soil Bags Waste Plaster

Top soil conserved for Used in re-filling, Road making landscaping, balance used raising site level in re-filling

Figure 2.6: Solid Waste Management Scheme (Construction Phase)

During the operation phase, waste will comprise domestic as well as horticultural waste. The solid waste generated from the project shall be approx. 3,537.876 kg per day (@ 0.5 kg per

M/S DSS BUILDTECH PVT. LTD. 28 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA capita per day for residents, @ 0.15 kg per capita per day for the visitor, 0.25 kg per capita per day for the staff members and landscape waste @ 0.12 kg/acre/day). Following arrangements will be made at the site in accordance to Municipal Solid Waste (Management and Handling) Rules, 2000 and amended Rules, 2016. Solid waste calculations are given below in Table 2.12:

Table 2.12(a): Comparative Parking Distribution (EC Accorded +Expansion) S. No. Particulars Value as per EC Accorded Expansion Total Parking (EC Accorded +Expansion) 1 Solid Waste 3441 96.876 3,537.876

Table 2.12(b): Solid Waste Generation

S. No. Description Occupancy Waste Generated Waste Generated (kg/capita/day) (kg/day) 1. Domestic Solid Waste  Main Units 4975 0.5 2487.5  EWS Units 880 0.5 440  Service Units 200 0.5 100  Staff 688 0.25 172 (Maintenance, Schools, Commercial, facilities)  Visitors 2171 0.15 325.65 (Community facilities etc) 2. Horticultural @ 0.2 kg/acre/day 1.012 Waste (5.06 acre) 3. STP Sludge Sludge generated x 11.70 0 .35 x B.O.D difference/1000 Total Solid Waste Generation = 3,537.862 kg/day

(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment Engineering Organization, Ministry of Urban Development, (Government of India, May 2000)

M/S DSS BUILDTECH PVT. LTD. 29 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  Collection and Segregation of waste 1. Collection system will be provided for collection of solid waste in colored bins. 2. An authorized local vendor will be hired to provide separate colored bins for dry recyclable and Bio-Degradable waste. 3. For commercial waste collection, adequate number of colored bins (Green and Blue & dark grey bins– separate for Bio-degradable and Non Bio-degradable) are proposed to be provided at the strategic locations of the commercial area. 4. Litter bin will also be provided in open areas  Treatment of waste  Bio-Degradable waste 1. Bio-degradable waste will be subjected to organic waste converter and the compost will be used as manure. 2. STP sludge is proposed to be used for horticultural purposes as manure. 3. Horticultural Waste is proposed to be composted and will be used for gardening purposes.

 Recyclable waste i. Grass Recycling – The cropped grass will be spread on the green area. It will act as manure after decomposition. ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclers.  Disposal Disposal of waste will be done through an approved agency. Solid Waste Management Scheme is depicted in the following figure for the project.

M/S DSS BUILDTECH PVT. LTD. 30

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Figure 2.7: Solid Waste Management Scheme (Operation Phase)

Organic Waste Converter A waste converter is a machine used for the treatment and recycling of solid and liquid refuse material. A converter is a self-contained system capable of performing the following functions: pasteurization of organic waste; sterilization of pathogenic or biohazard waste; grinding and pulverization of refuse into unrecognizable output; trash compaction; dehydration

M/S DSS BUILDTECH PVT. LTD. 31 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Organic Waste Convertor Benefits of organic waste converter: 1. Large quantity of solid waste is converted to manure in a very short period 2. This manure can be sold as compost to farmers, or used for gardening 3. Machine requires less space and the efficiency is high 4. Manpower and maintenance is very less 5. This is one of the latest techniques of managing solid waste.

Operation cost of OWC: Organic Waste Converter - 300 (Dim. 3m × 4m) is proposed to be used for composting waste 120kg/batch or 3000 kg/day & it requires electricity of about 13.5 HP. No. of batches /day = 3000/120 = 25 No. of batches to convert 2123 kg/day = 2123 /120 = 17.69 say 18 batches

Operation Cost-monthly per capita: The operating cost of OWC - 300 = 1, 80,000 INR/month Cost/day = 1, 80,000/30

M/S DSS BUILDTECH PVT. LTD. 32 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA = 6000/- 1 batch/day cost = 6000/25 = 240 INR Cost for 18 batch/day = 18 × 240/- = 4320/- Monthly operating cost = 30 × 4320 = Rs. 1, 29,600 /- per month

E-waste management It will be disposed of through approved vendor of CPCB as per Electronic Wastes (Management and Handling) Rules, 2016

2.13 LANDSCAPE Total green area measures 20,494.66 m2 i.e. 30.17 % of the total plot area (Shelter belt, Avenue plantation and lawn).

2.14 MANPOWER REQUIREMENT During the construction phase, large number (800-850) of professionals and workers will be engaged. As a responsible corporate, the project proponent will comply with all applicable Acts related to employees’ service and their welfare like:  Minimum Wages Act, 1948  Contract Labour (Regulation & Abolition) Act, 1970  Inter-State Migrant Workmen (Regulation of Employment & Conditions of Services) Act,1979  The Building and other Construction Workers (Regulation and Employment of Service) Act, 1996  The Building and other Construction Workers Welfare Cess Act, 1996, etc.

M/S DSS BUILDTECH PVT. LTD. 33 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA All workers and technicians will be provided with clean drinking water, sheds for resting and sanitary facilities as mobile toilets/ toilets connected to septic tanks, etc. Camps will be organized for health check.

2.15 FIRE FIGHTING SYSTEM Following provisions will be made according to National Building Code, 2016. The firefighting system has been designed considering the following codes, manual and guidelines;  National Building Code of India (NBC);  Latest relevant NFPA codes, USA, in particular NFPA – 13, 14, 20 & 22;  IRI guidelines;  As per requirement of fire officer/local fire approving authorities; and  As per Indian Standard Code for Fire Protection (IS Codes)

Following items are envisaged for firefighting:  Fire-Water Connections;  Firewater inlet and outlet connections will be provided to the water storage tanks;  External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing will be provided. This external fire ring will be separated from the Sprinkler Main Systems;  All flow switches, test valves, drain pipes etc. will be provided as per NFPA guidelines on the sprinkler system;  All pump installation and arrangements will be in accordance with IRI guidelines and NFPA-20;  All pumps and accessories and electrical controllers will be as per UL/FM lists, tested, approved and certified; and  By-pass arrangements will to be provided (150 mm diameter nominal bore) with NRV and gate valve and bulk flow meter on the discharge header of each pump to check the duties of pumps.  Storage tanks are provided in the basement for the supply of water for the firefighting facility.

M/S DSS BUILDTECH PVT. LTD. 34 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  The fire extinguishers provided should be in conformance with Ozone Depleting Substances (Regulation and Control) Rules, 2000.

2.16 DETAILS OF CONSTRUCTION MATERIAL 1. Coarse sand 2. Fine sand 3. Stone aggregate 4. Stone for masonry work 5. Cement 6. Reinforcement steel 7. Pipe scaffolding (cup lock system) 8. Bricks 9. CLC fly ash blocks 10. Crazy (white marble) in grey cement 11. P.V.C. conduit 12. MDS, MCBs 13. 2 1/2'’ thick paver tiles 14. PPR (ISI marked) 15. PVC waste water lines 16. S.W. sewer line up to main sewer 17. PVC rain water down take 18. Stainless steel sink in kitchen 19. Joinery hardware- ISI marked

2.17 LIST OF MACHINERY USED DURING CONSTRUCTION (i) Dumper : Shall be used for mud and material handling (ii) Concrete mixer with hopper : For RCC work (iii) Excavator : Shall be used for digging and earth work (iv) Concrete Batching Plant : Will be used for concrete mixing (v) Cranes : For lifting and moving of materials.

M/S DSS BUILDTECH PVT. LTD. 35 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA (vi) Road roller : For compacting the earth (vii) Tower Cranes

M/S DSS BUILDTECH PVT. LTD. 36 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

CHAPTER 3: DESCRIPTION OF ENVIRONMENT

3.1 INTRODUCTION Information on the existing environmental status is essential for assessing the likely environmental impacts of the project. In order to get an idea about the existing state of the environment, various environmental attributes such as meteorology, air quality, water quality, soil quality, noise level, ecology and socio-economic environment have been studied/ monitored.

3.2 STUDY PERIOD Baseline environmental data generation for air, water, noise and soil quality monitoring around the project site was conducted from March to May, 2015 and October-November 2015. Apart from field monitoring, additional data was also collected from secondary sources like irrigation department, India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of India, State Ground Water Department, State Pollution Control Board, Census of India and Local Forest Department, Non - Governmental Agencies, etc.

3.3 STUDY AREA The present report covers baseline environmental data generated in the study area (10 Km radius around the project site for land use and the sample selection for air, water, soil and noise monitoring).

3.4 BASELINE MONITORING OF ENVIRONMENTAL COMPONENTS In order to get an idea about the existing state of the environment, various environmental attributes such as meteorology, air quality, water quality, soil quality, noise level, ecology and socio-economic environment have been studied/monitored.

METEOROLOGY Climate The district receives most of the rainfall during June to September. The district is characterized by a warm climate in March to June and later on there is a gradual decline in temperature from October onwards to December. December and January is the coolest months

M/S DSS BUILDTECH PVT. LTD. 37

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA of the year in Gurgaon. March, April and May are the hot and dry months of the district. During winter season the district records temperature between 5 to 21 °C while, during summer the temperature ranges from 30° to 44° C.

Meteorological data was generated during the March to May, 2015 and October-November 2015. The following parameters were recorded at hourly intervals continuously during monitoring period:  Air Temperature  Wind speed  Wind Direction Table - 3.1 gives summarized meteorological data for the monitoring period (March-May 2017). Figure - 3.1 gives the wind-rose diagram for the monitoring period.

Table 3.1: Meteorological Data for March– May, 2015 & October -November, 2015 Month Temperature in Relative Wind Speed Predominant Kelvin (K) Humidity (%) (km/h) Wind Direction Max Min Max Min Max Min March 33 10 100 20 34 3 WNW April 44 16 83 8 27 5 NW May 43 18 62 12 29 5 NW October 37 26 65 48 33 4 NWW November 32 23 82 47 32 5 NW

M/S DSS BUILDTECH PVT. LTD. 38

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Figure - 3.1: The wind-rose diagram based on the study period

AIR ENVIRONMENT The prime objective of the baseline study with respect to ambient air quality is to establish the present air quality and its conformity to National Ambient Air Quality Standards. This data has been further used during impact assessment to predict the final air quality. This section describes the sampling locations, frequency of sampling and methodology adopted for monitoring ambient air quality. To quantify the impact of the project on the ambient air quality, it is necessary at first to evaluate the existing ambient air quality of the area. The existing ambient air quality, in terms of Particulate Matter – 10 (PM10), Particulate Matter- 2.5 (PM2.5), Sulphur-dioxide (SO2),

Oxides of Nitrogen (NO2), and Carbon Monoxide (CO), has been measured through a planned field monitoring. To assess the ambient air quality level, 6 (six) monitoring stations were set up. Table - 3.2 gives location of the ambient air quality monitoring stations and a map showing the ambient air quality monitoring stations is attached as Annexure - XXVII. Table 3.2: Location of Ambient Air Quality Monitoring Stations Location Code Location Direction Distance (km) A1 Village Berka NE 3.02

M/S DSS BUILDTECH PVT. LTD. 39

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

A2 Village Khaika SE 3.70 A3 Sohna Town S 3.72 A4 Village Dhunela NE 1.30 A5 Village Samp ki SW 2.08 Nagli A6 Project Site -- ---

MONITORING SCHEDULE Ambient air quality monitoring was carried out twice a week with a frequency of 24 hours for 12 weeks.

METHODS OF SAMPLING AND ANALYSIS The brief methodology of the parameter analyzed is as follows: I. Particulate Matter (PM2.5): (CPCB Method) Particulate Matter (PM2.5) was analyzed by Fine particulate Sampler Enviro tech Model APM 550. PM 2.5 was collected on 47mm diameter filter paper. The mass concentration of (PM2.5) fine particles in ambient air was calculated as the total mass of collected particles divided by the volume of air sampled. II. Particulate Matter (PM10): Particulate Matter (PM10) was carried out by respirable dust sampler enviro tech Model APM 460 BL. The cyclone of this instrument is used for fractionating the dust into two fractions. PM 10 dust is accumulated on the filter paper (8ʺ×10ʺ size) while coarse dust is collected in a cup placed under the cyclone.PM 10 was calculated as per IS: 5182 (Part 23):2006. The mass of these particles was determined by the difference in filter weight prior to and after sampling. The concentration of PM 10 in the designated size range was calculated by dividing the weight gain of the filter by the volume of air sampled. III. Sulphur dioxide (SO2): SO2 was monitored with the help of APM 411 assembly attached with APM 460 BL using the impinge. It was absorbed by aspirating a measured air sample through a solution of Potassium tetrachloromercurate (TCM). This procedure resulted in the formation of a dichloro sulphite mercurate complex. The complex was made to react with pararosaniline and methylsulphonic acid. The absorbance of the solution was measured by means of spectrophotometer.

M/S DSS BUILDTECH PVT. LTD. 40

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

IV. Nitrogen Dioxides: NO2 was monitored with the help of APM 411 assembly attached with APM 460 BL using the impinge. It was collected by bubbling air through a solution of sodium hydroxide and sodium arsenite. The concentration of nitrite ion produced during sampling was determined colorimetrically by reacting with the nitrite ion with phosphoric acid, sulphanilamide and NEDA and absorbance of highly colored azo-dye was measured at 540nm. V. Carbon Monoxide: It is measured using CO Analyser. This analyser is used to measure CO in ambient air, in the range of 0-200 ppm (220 mg/m3) to a sensitivity of 0.05 ppm (55µg/m3). The Serinus 30 combines the benefits of Microprocess control with Non- Dispersive Infrared Spectrophotometry technology. CO concentration is automatically corrected for gas temperature and pressure changes. CO was monitored on hourly basis whereas other parameters were monitored on 24 hourly bases.

RESULTS AND DISCUSSIONS The results of AAQ are summarized in the tables below. The results when compared with National Ambient Air Quality Standards (NAAQS) of Central Pollution Control Board (CPCB) for "Industrial, Residential, Rural and Other Areas" show that the average values of ambient air quality parameters are well within the stipulated limit. The results of ambient air quality monitoring are summarized in the Tables 3.3 (a to u) below:

Table 3.3 (a) Ambient Air Quality with respect to PM2.5 (March 2015) 3 PM2.5 (µg/m ) LOCATION/ A 1 A2 A 3 A4 A5 A6 CONCENTRATION Min 39 40.42 40 40.25 40.66 41.24 Max 43.93 43.15 43.98 44.77 44.77 44.65 Average 41.26 41.65 41.76 41.95 42.69 42.52 NAAQS 60 60 60 60 60 60

The values of PM2.5 in study area for the month of March 2015 are presented in Table 3.3 (a). 3 The seasonal minimum, maximum, and average values of PM2.5 were observed 41.24µg/m , 44.65µg/m3 and 42.52µg/m3 respectively at the project site.

Table 3.3 (b) Ambient Air Quality with respect to PM2.5 (April 2015)

M/S DSS BUILDTECH PVT. LTD. 41

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of PM2.5 in study area for the month of April 2015 are presented in Table 3.3 (b). 3 The seasonal minimum, maximum, and average values of PM2.5 were observed 40.76µg/m , 45µg/m3 and 45.31µg/m3 respectively at the project site.

Table 3.3 (c) Ambient Air Quality with respect to PM2.5 (May 2015

The values of PM2.5 in study area for the month of May 2015 are presented in Table 3.3 (c). 3 The seasonal minimum, maximum, and average values of PM2.5 were observed 40.83µg/m , 44.4µg/m3 and 42.16µg/m3 respectively at the project site.

Table 3.3 (d) Ambient Air Quality with respect to PM2.5 (October 2015)

M/S DSS BUILDTECH PVT. LTD. 42

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of PM2.5 in study area for the month of October 2015 are presented in Table 3.3

(c). The seasonal minimum, maximum, and average values of PM2.5 were observed 44.15µg/m3, 47.85µg/m3 and 46.20µg/m3 respectively at the project site.

Table 3.3 (d) Ambient Air Quality with respect to PM2.5 (November 2015)

The values of PM2.5 in study area for the month of November 2015 are presented in Table 3.3

(d). The seasonal minimum, maximum, and average values of PM2.5 were observed 45.14µg/m3, 47.53µg/m3 and 46.31µg/m3 respectively at the project site.

Table 3.3 (e) Ambient Air Quality with respects to PM10 (March 2015)

M/S DSS BUILDTECH PVT. LTD. 43

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

A6 86.25 93.15 89.95 100

The values of PM10 in study area for the month of March 2015 are presented in Table 3.3 (c). 3 The seasonal minimum, maximum, and average values of PM10 were observed 86.25µg/m , 93.15 µg /m3 and 89.95µg/m3 respectively at the project site.

Table 3.3 (f) Ambient Air Quality with respects to PM10 (April 2015)

The values of PM10 in study area for the month of April 2015 are presented in Table 3.3 (f). 3 The seasonal minimum, maximum, and average values of PM10 were observed 91.59µg/m , 94.25 µg /m3 and 93.30µg/m3 respectively at the project site.

Table 3.3 (g) Ambient Air Quality with respects to PM10 (May 2015)

M/S DSS BUILDTECH PVT. LTD. 44

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of PM10 in study area for the month of May 2015 are presented in Table 3.3 (g). 3 The seasonal minimum, maximum, and average values of PM10 were observed 90.96µg/m , 94.98 µg /m3 and 93.56µg/m3 respectively at the project site.

Table 3.3 (h) Ambient Air Quality with respects to PM10 (October 2015)

The values of PM10 in study area for the month of October 2015 are presented in Table 3.3 (h). 3 The seasonal minimum, maximum, and average values of PM10 were observed 94.52µg/m , 97.94 µg /m3 and 96.15µg/m3 respectively at the project site.

Table 3.3 (i) Ambient Air Quality with respects to PM10 (November 2015)

The values of PM10 in study area for the month of November 2015 are presented in Table 3.3

(i). The seasonal minimum, maximum, and average values of PM10 were observed 95.94µg/m3, 98.12 µg /m3 and 96.98µg/m3 respectively at the project site.

M/S DSS BUILDTECH PVT. LTD. 45

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Mitigation Measures: It is proposed to provide adequate dust control systems in the form of installation of batch plants, and loose material handling in covered sheds. Dust suppression system is also to be provided where necessary. Provision for treatment of DG Flue Gas emissions in a scrubber will be considered. It is further proposed to cover scaffolding, hosing down road surfaces and cleaning of vehicles especially during the dry season. Avenue and curtain plantation on the internal roads and peripheral plantation around the site will also be developed.

Table 3.3 (j) Ambient Air Quality with respect to SO2 (March 2015) 3 SO2 (µg/m ) LOCATION/ A1 A2 A 3 A4 A 5 A6 CONCENTRATION Min 15.2 15.97 15.17 15.28 15.12 15.07 Max 17.63 17.57 17.69 16.83 17.51 16.77 Average 16.02 16.50 16.51 16.20 16.29 15.57 NAAQS 80 80 80 80 80 80

The values of SO2 in study area for the month of March 2015 are presented in Table 3.3 (j). 3 The seasonal minimum, maximum, and average values of SO2 were observed 15.07µg/m , 16.77µg/m3, and 15.57µg/m3 respectively at the project site.

Table 3.3 (k) Ambient Air Quality with respect to SO2 (April 2015)

The values of SO2 in study area for the month of April 2015 are presented in Table 3.3 (k). 3 The seasonal minimum, maximum, and average values of SO2 were observed 15.36µg/m , 18.36µg/m3, and 16.82µg/m3 respectively at the project site.

Table 3.3 (l) Ambient Air Quality with respect to SO2 (May 2015)

M/S DSS BUILDTECH PVT. LTD. 46

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of SO2 in study area for the month of May 2015 are presented in Table 3.3 (l). The 3 seasonal minimum, maximum, and average values of SO2 were observed 16.15µg/m , 18.94µg/m3, and 17.27µg/m3 respectively at the project site.

Table 3.3 (m) Ambient Air Quality with respect to SO2 (October 2015)

The values of SO2 in study area for the month of October 2015 are presented in Table 3.3 (m). 3 The seasonal minimum, maximum, and average values of SO2 were observed 5.89µg/m , 9.64µg/m3, and 7.68µg/m3 respectively at the project site.

Table 3.3 (n) Ambient Air Quality with respect to SO2 (November 2015)

M/S DSS BUILDTECH PVT. LTD. 47

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of SO2 in study area for the month of November, 2015 are presented in Table 3.3 3 (n). The seasonal minimum, maximum, and average values of SO2 were observed 6.04µg/m , 10.21µg/m3, and 8.08µg/m3 respectively at the project site.

Table 3.3 (o) Ambient Air Quality with respect to NO2 (March 2015)

The values of NO2 in study area for the month of March 2015 are presented in Table 3.3 (o). 3 The seasonal minimum, maximum, and average values of NO2 were observed 30.27µg/m , 32.36µg /m3, 31.44µg/m3 respectively at the project site.

Table 3.3 (p) Ambient Air Quality with respect to NO2 (April 2015)

The values of NO2 in study area for the month of April 2015 are presented in Table 3.3 (p). 3 The seasonal minimum, maximum, and average values of NO2 were observed 31.59µg/m , 34.56µg /m3, 32.93µg/m3 respectively at the project site.

Table 3.3 (q) Ambient Air Quality with respect to NO2 (May 2015)

M/S DSS BUILDTECH PVT. LTD. 48

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of NO2 in study area for the month of May 2015 are presented in Table 3.3 (q). 3 The seasonal minimum, maximum, and average values of NO2 were observed 32.70µg/m , 34.98µg /m3, 34.21µg/m3 respectively at the project site.

Table 3.3 (r) Ambient Air Quality with respect to NO2 (October 2015)

The values of NO2 in study area for the month of October 2015 are presented in Table 3.3 (r). 3 The seasonal minimum, maximum, and average values of NO2 were observed 17.62µg/m , 20.53µg /m3, 18.97µg/m3 respectively at the project site.

Table 3.3 (s) Ambient Air Quality with respect to NO2 (November 2015)

M/S DSS BUILDTECH PVT. LTD. 49

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

The values of NO2 in study area for the month of November 2015 are presented in Table 3.3 3 (s). The seasonal minimum, maximum, and average values of NO2 were observed 16.14µg/m , 21.52µg /m3, 18.56µg/m3 respectively at the project site.

Table 3.3 (t) Ambient Air Quality with respect to CO (March 2015)

Table 3.3 (u) Ambient Air Quality with respect to CO (April 2015)

Table 3.3 (v) Ambient Air Quality with respect to CO (May 2015)

M/S DSS BUILDTECH PVT. LTD. 50

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.3 (t) Ambient Air Quality with respect to CO (October 2015)

Table 3.3 (u) Ambient Air Quality with respect to CO (November 2015)

3.4.3 Noise Levels Noise is one of the most undesirable and unwanted by-products of our modern life style. It may not seem as insidious or harmful as air and water pollutants but it affects human health and well-being and can contribute to deterioration of human well-being in general and can

M/S DSS BUILDTECH PVT. LTD. 51

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA cause neurological disturbances and physiological damage to the hearing mechanism in particular. It is therefore, necessary to measure both the quality as well as the quantity of noise in and around the site.

3.4.3.1 Methodology The intensity of sound energy in the environment is measured in a logarithmic scale and is expressed in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an additional circuit (filters) is provided, which modifies the received signal in such a way that it replicates the sound signal as received by the human ear and the magnitude of sound level in this scale is denoted as dB (A). The sound levels are expressed in dB (A) scale for the purpose of comparison of noise levels, which is universally accepted by the international community. Noise levels were measured using an Integrating sound level meter manufactured by Pulsar Instruments Plc, Model NO. 91 (SL.No.B21625). It has an indicating mode of Lp and Leq. Keeping the mode in Lp for few minutes and setting the corresponding range and the weighting network in “A” weighting set the sound level meter was run for one hour time and Leq was measured at all locations. The day noise levels have been monitored during 6.00 am to 10.00 pm and night noise levels, during 10.00 pm to 6.00 am at all the 4 locations, which covers residential areas, and silence area within 6 km radius of the study area.

3.4.3.2 Sampling Locations A preliminary survey was undertaken to identify the major noise generating sources in the area. The noise survey was conducted to assess the background noise levels in different zones. Gazettes Notification (S.O. 123(E)) of MoEFCC dated December 14, 2000 on ambient air quality standards has different noise levels for different zones viz. project site, industrial, and residential zones. Four sampling locations were selected for the sampling of noise levels. The sampling locations are given in Table - 3.4 below. Map showing the noise monitoring stations is attached as Annexure - VIII Table 3.4 Noise Level Monitoring Stations in the Study Area

M/S DSS BUILDTECH PVT. LTD. 52

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Ministry of Environment, Forests and Climate Change (MoEFCC) has notified the noise standards vide gazette notification dated December 14, 2000 for different zones under the Environment Protection Act (1986). These standards are given in Table - 3.5. Table 3.5 Ambient Quality Standards in Respect of Noise Area Noise dB(A) Leq Category of Area Code Day time* Night time* A Residential Zone 55 45 B Silence zone 50 40 C Industrial Zone 75 70 D Commercial Zone 65 55 Note: 1. Daytime is from 6.00am to 10.00 pm and Night time is from 10.00 pm to 6.00 am. 2. Silence zone is defined as area up to 100 meters around premises of hospitals, educational institutions and courts. Use of vehicle hours, loud speakers and bursting of crackers are banned in these zones.

3.4.3.3 Results and Discussion The noise data compiled on noise levels during March –April 2015 and October-November 2015 are given in Table - 3.6 (a & b). Table 3.6 (a): Hourly Leq Noise Level in the study Area, (March –April 2015)

M/S DSS BUILDTECH PVT. LTD. 53

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.6 (b): Hourly Leq Noise Level in the study Area, (October, -November 2015) S.N Location ZONE LIMIT as per CPCB Observed value Leq, o. Guidelines Leq, dB(A) dB(A) DAY* NIGHT** DAY* NIGHT** 1 Village Residential Area 55 45 54.1 43.9 Berka 2 Khaika Residential Area 55 45 53.1 42.8 3 Sohna Residential Area 55 45 52.4 42.1 4 Village Residential Area 55 45 53.9 Dhunela 42.3 5 Vilalge Residential Area 55 45 52.6 Samp ki Nagli 41.6 6 Project Residential Area 55 45 53.2 42.8 Site

* Day time (6.00AM TO 10.00PM) ** Night time (10.00PM TO 6.00AM)

3.4.4 WATER ENVIRONMENT 3.4.4.1 Water Quality Water quality assessment is one of the essential components of EIA study. Such assessment helps in evaluating the existing health of water body and suggesting appropriate mitigation measures to minimize the potential impact from development projects. Water quality of ground water has been studied in order to assess proposed water-uses in construction, drinking, cooling and horticulture purpose. The water quality at the site and other locations within the 5 km impact zone was monitored during March-May, 2015 & October-November 2015. The locations of the monitoring sites are given in Table - 3.7.Results of the monitoring are given in Table 3.8 to 3.10. Table 3.7: Location of water sampling sites Location Code Location GW1 Village Berka GW2 Village Khaika GW3 Sohna Town GW4 Village Dhunela

M/S DSS BUILDTECH PVT. LTD. 54

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Location Code Location GW5 Village Samp Ki Nagli GW6 Project Site

3.4.4.2 Sampling Frequency and Sampling Techniques Samples were studied at monthly intervals in the study period. Quality of ground water was compared with IS: 10500: 1991 (Reaffirmed 1993 with Amendment No.3 July 2010) for drinking purposes. Surface water quality was analyzed for parameters as mentioned in the ‘Annexure IV of CPCB guidelines’ and it was rated according to the CPCB Water Quality Criteria (Designated Best Use). Water samples were collected in a 5 liter plastic jerry can and 500ml sterilized clean glass bottles for physio-chemical and bacteriological tests respectively. GW sampling was done after flushing out the source (minimum 10 minutes) to get the fresh ground water and grab sampling method was used. River water samples were collected about 10cm below the water surface. All sampling, preservative and sample handling techniques were in accordance with APHA for Examination of Water & Wastewater/ IS: 3025 (Part-1)/ IS: 1622. The samples were analyzed as per Indian standard /APHA latest edition. The water quality is compared with CPCB water quality criteria mentioned in Table 3.8. The water quality in the impact zone was assessed through physico-chemical and bacteriological analysis of ground samples. The results have been compared with the drinking water quality standards specified in IS: 10500.

Table 3.8: Water Quality Criteria as per Central Pollution Control Board Designated-best-use Class Criteria Drinking water source A Total Coliform Organism MPN/100ml will be 50 or less without conventional pH between 6.5 and 8.5 Dissolved Oxygen 6mg/l or treatment more but after disinfection Biochemical Oxygen Demand 5 days 20°C 2mg/l or less Outdoor bathing B Total Coliform Organism MPN/100ml will be 500 or (Organized) less pH between 6.5 and 8.5; Dissolved Oxygen 5mg/l or more Biochemical Oxygen Demand 5 days 20°C 3mg/l or less Drinking water source after C Total Coliform Organism MPN/100ml will be 5000 or conventional treatment and less disinfection pH between 6 to 9; Dissolved Oxygen 4mg/l or more Biochemical Oxygen Demand 5 days 20°C 3mg/l or less

M/S DSS BUILDTECH PVT. LTD. 55

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Propagation of Wild life and D pH between 6.5 to 8.5 Fisheries Dissolved Oxygen 4mg/l or more Free Ammonia (as N) 1.2 mg/l or less Irrigation, Industrial E pH between 6.0 to 8.5 Cooling, Controlled Waste Electrical Conductivity at 25°C micro mhos/cm disposal Max.2250 Sodium absorption Ratio Max. 26 Boron Max. 2mg/l Below- Not Meeting A, B, C, D & E Criteria E

M/S DSS BUILDTECH PVT. LTD. 56

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.9: Ground Water Quality in Study Area (March-May, 2015)

M/S DSS BUILDTECH PVT. LTD. 56

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 57

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 58

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 59

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.10: Ground Water Quality in Study Area (October-November, 2015)

M/S DSS BUILDTECH PVT. LTD. 60

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 61

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 62

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 63

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 64

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

3.4.5 DRAINAGE The drainage of the Gurgaon district is typical of the arid and semi-arid areas. It comprises of large depressions and streams. The drainage is peculiarly complex owing to most of the streams tending to converge towards inland depressions instead of flowing into . The important depressions in the level of the district in this region are Khalipur, Chandaini, Sangel-Ujina, Kotla Dahar Jheels and Lake. Sahibi and Indrani are two important seasonal streams of the district.

3.4.6 LAND ENVIRONMENT

M/S DSS BUILDTECH PVT. LTD. 65

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Soil Environment

M/S DSS BUILDTECH PVT. LTD. 66

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 67

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Methodology:

Soil Sampling Locations

M/S DSS BUILDTECH PVT. LTD. 68

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Soil Analysis Results and Discussions:

M/S DSS BUILDTECH PVT. LTD. 69

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 70

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 71

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

3.5 Biological Environment

3.5.0 Introduction

Biodiversity reflects the potential of a regional ecosystem. Biota of a particular area is considered as indicators of the environment as they quickly respond not only to one environmental factor but also an interactive group of factors. These communities influence and react sensitively to changes in the balance of environmental stresses.

Biological diversity comprises the variability of genus, species and ecosystems and is very crucial for maintaining the basic processes on which the life depends. On the basis of biological physiology biodiversity broadly can be divided into two category i.e. the floral diversity and faunal diversity. Conservation of the biodiversity is essential for the sustainable development as it not only provides the food, fodder and medicine, but also contributes to improvement of essential environmental attributes like air, water, soil, etc. Before starting any Environmental Impact Assessment study, it is necessary to identify the baseline of relevant environmental parameters which are likely to be affected as a result of the operation of the proposed project. A similar approach has been adopted for conducting the study on Biological Environment for this Project. Both terrestrial and aquatic ecosystems have been studied to understand the biological environment near the project site.

The study was conducted in the project area to assess all possible consequences on the biological environment. Flora and fauna surveys and data collection conducted for assessing the biological diversity and its status over a period of time that forms an integral part of Impact Assessment Techniques. The present study is highlighting the various issues pertaining to floristic diversity and the faunal wealth in the core area i.e. Expansion of Group Housing Project at Village –Mohammadpur Gujjar, Sector- 35, Sohna, Gurgaon, Haryana and buffer zone i.e. area within 10 km radius.

3.5.1 Ecological Flora

M/S DSS BUILDTECH PVT. LTD. 72

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.13 List of Plants in the area

AVENUE TREES & PROJECTION The common trees found in roadside of the study area are Azadirecta indica, Syzinium Cumini, Mangifera Indica, Delonix regia, Albezia Spp., Leucaenaleucocephala etc

M/S DSS BUILDTECH PVT. LTD. 73

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.14 List of fauna in Study area

M/S DSS BUILDTECH PVT. LTD. 74

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 75

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 76

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 3.16 List of villages within 5km of the project site

M/S DSS BUILDTECH PVT. LTD. 77

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 78

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 79

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 80

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 81

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 82

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 83

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 4: ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES

4.1 INTRODUCTION This chapter discusses identification and appraisal of various environmental impacts due to the proposed Project. Generally, the environmental impacts can be categorized as either primary or secondary. The development, construction and functional phase of the project comprise various activities, each of which may have some impact on environmental parameter. Various impacts during the development, construction and operation phase on the environmental parameters have been studied to estimate the impact on environment.

The project will be constructed and developed gradually in the time span of 3-4 years (approx.). For proper evaluation and assessment of the environmental impacts due to development, construction and functional phase of project understanding to the various activities associated with the project is essential. Various activities related to the project would be different, in terms of nature during the development, construction and operational phase.

The impact identification and prediction process aims to:  Identify potential source or cause of impact throughout life of the project.  Characterize the potential impacts affecting a target or receptor (physical, human and socio-economic).  Assess the potential of changing likely-hood of impact through Environmental Management Plan (EMP)  Prediction of the impacts due to the development, construction and functional activities encompass the developmental processes to be undertaken during construction and functional phases. For each category of environmental receptor (such as, ambient air quality, water quality, soils, land, etc.,) the potential impacts of activities during development, construction and functional phases have been identified. Pollution sources & its characteristics, potential impacts and magnitude of the impacts have been assessed and discussed in detail in following sub sections. In each case, cognizance has been taken to mitigation measures inherited in the development, construction and functional phase.

M/S DSS BUILDTECH PVT. LTD. 84

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

4.2 IMPACT MATRIX Various activities from the Project are likely to have some impact on the environmental constituents during its construction as well as operational phase. The impact assessment matrix given in Table 4.1 reveals the impact associated with each activity of the project on various environmental parameters during construction and function phase respectively before any mitigation measures are implanted. To assess the severity of the impacts, they are categorized as follows:

M/S DSS BUILDTECH PVT. LTD. 85

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Table 4.1: Impact Assessment Matrix

Environmental Nature of Potential Impacts during Construction and Operation Phases Parameters Local Regional Short Long Reversible Irreversible Adverse Beneficial No Impact Significant Insignificant Term Term Topography √ √ √ Drainage √ √ Soil √ √ √ Water Resources √ √ √ √ Water Quality √ √ Land Use √ Air Quality √ √ √ √ Noise √ √ √ √ Flora √ √ √ √ √ Fauna √ √ √ √ √ Employment √ √ √ √ √ Aesthetic √ √ √ √ √

M/S DSS BUILDTECH PVT. LTD. 86

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

4.3 POLLUTION SOURCES Pollutants generated from the development project during the construction and functional phases are solid, liquid and gaseous in nature. Also the generation of pollution could be continuous, periodic or accidental. Sources of pollution and their characteristics are given below in Table 4.2. Table 4.2: Pollution Sources S. No. Activity / Area Pollutant Sources Frequency CONSTRUCTION PHASE 1. Site Air emission- SO2, Dust from Temporary during preparation and & NO2. construction construction phase construction activities and only. activities excavation. Bulk of the Particulates matter, emissions is expected NO2 and CO from from ground work vehicle exhaust and leveling. Earth/Solid waste Solid waste from Periodic. construction activity and excavation. Hazardous waste From D.G. Sets and Periodic and generation such as painting of the temporary used oil and paints. buildings. Noise Noise generated Temporary lasting from construction the construction equipment and phase. machinery 2. Labour Camps Sewage Sewage generated Temporary-during from temporary labor the initial camps on site. construction phase Solid Waste Solid Waste Temporary- during generated from the initial temporary labor camps on site. phase OPERATIONAL PHASE 1. Vehicular Air emissions and Vehicle exhaust Continuous/ periodic movement noise emissions

2. Diesel Air emissions SO2, NO2, PM, CO Occasional- during generators from fuel burning power failure Noise Noise due to running Occasional - during of equipment power failure

M/S DSS BUILDTECH PVT. LTD. 87

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. No. Activity / Area Pollutant Sources Frequency Hazardous Waste Used Oil Generation Occasional- during oil changes 3. Maintenance / Sullage Floor washing Continuous House- Sewage keeping Solid waste Domestic and garden Continuous wastes 4. Vehicle Oil spills Minor oil leaks Continuous Parking Parking space 5. Storm water Rainwater Contamination During rainy season drains discharge from site- mainly suspended solids

4.4 IMPACT IDENTIFICATION The areas of environmental concerns for which the impacts and their predictions are taken into consideration are mainly:  Air Environment  Water Environment  Noise Environment  Land Environment  Biological Environment  Socio economic Environment  Aesthetics Environment The impacts can be further categorized as positive impacts and negative impacts depending upon their nature, potential and magnitude.

4.4.1 Environmental Aspects of Development, Construction & Operation  Generation, storage and disposal of construction waste;  Noise pollution due to plant, machinery, equipment and vehicle movement;  Air pollution due to plant, machinery, equipment and vehicle movement;  Generation and disposal of wastewater;  Impact on ecology;

M/S DSS BUILDTECH PVT. LTD. 88

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Consumption of resources such as water, electricity, and diesel.  Physical change in landscape due to earth work excavation and related activities.  Soil erosion caused due to loss of vegetation and other construction activities.

4.4.2 Environmental Aspects of Building Planning and Use Impacts identified during operation of the Revision & Expansion of Project and their use includes major concerns such as:  Disposal of domestic sewage generation  Disposal of solid wastes generated in the Revision & Expansion of Project from office, shops, restaurant and horticulture.  Increase in noise levels due to transport  Consumption of water and impact on water resources  Impact of traffic on the road  Storm water during rains  Management and maintenance project

Environmental aspects of the project are not just limited to impact of sources of pollution but also relate to energy conservation, water conservation and other issues, which are mentioned in Table 4.3. Table 4.3: Environment aspects of the Project S. No. Area Aspect I. Energy  Solar Heating, Day Lighting, Design Natural Ventilation, conservation Thermal Transfer value of Building Material, Energy Efficient Building Services and Equipment,  Public Area Lighting  Exterior Lighting II. Water  Reuse of Recycled Water from STP conservation  Rainwater Harvesting III. Internal Roads  Pedestrian Access Ramps for Disabled persons Road painting and Accesses and Signage Speed Breakers IV. Material Use  Construction Materials Selection  Paint Selection  Use of Recycled Materials

M/S DSS BUILDTECH PVT. LTD. 89

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Use of Timber V. Aesthetics  Playground for children during  Service Roads for walking functional Use  Standby Power Supply  Provision for Garden VI. Facilities for  Rest Rooms with toilets for Security Persons. Building complex servants

4.5 ASSESSMENT OF ENVIRONMENTAL IMPACTS DURING DEVELOPMENT AND CONSTRUCTION PHASE

4.5.1 Topography Impact: Topography around the project site is almost plain. Therefore, existing topography and physiography of the area will not be affected during construction and operation phase of the project.

Mitigation Measure: It is further proposed to maintain 20,494.66 m2 area as green through plantation of various local and aesthetic species to improve the vegetation covers of the area. It is however proposed that apart from the proposed plantation greens, turfing with local species will be carried out. Therefore, there is no significant impact on topography from the project.

4.5.2 Land Use Pattern Impact: No significant impact is expected from the project which will be constructed after obtaining all necessary permissions.

4.5.3 Land Environment Impact: Soil would be excavated at project site for laying foundation of building. During the disposal of redundant overburden, soil of filling area would be covered and lost permanently.

Mitigation: The soil is being excavating during construction and first temporarily stored in an area earmarked and then will be used to fill up low lying area in and around the project site and

M/S DSS BUILDTECH PVT. LTD. 90

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA rest of the soil will be transported by road to fill up low lying areas elsewhere. Proper drainage system will be provided to deal with the storm water in case of rain. The impact on soil during construction phase will be marginal and reversible in the nature. It is proposed to remove vegetative cover only from the specific site on which construction is to take place and allowing minimal disturbance to the vegetation in adjacent areas. Land clearing activities only confined to necessary areas. The top soil will be stripped from constructional areas and stockpiled for later reuse in landscaping. The number, frequency and area of movement of heavy machinery will also be restricted.

4.5.4 Water Environment 4.5.4.1 Surface Water Quality Impact: The primary concerns relating to surface water quality associated with construction activities are pointed out below:  Runoff related to unpaved and excavated areas during the rain.  Sediments transported to runoff from the construction site.  Run off related to area where lubricant, fuel other materials are stored, used and disposed, off. Surface water quality may be affected with the discharge of the runoff from the project site. The impact to the surface water bodies could arise from the increased soil erosion from excavated site only causing increase in the suspended particles and turbidity of runoff water from the site. However, this impact will be temporary in the nature and would be observed in first rain only and as soon as rain is over excavated soil at site would be stabilized. Therefore, the surface water quality during rains will be impacted marginally for very short duration.

Mitigation Measures: During the construction phase, surface water quality is likely to be affected due to soil erosion during first rain and generation of sullage mainly from construction labour camp. However, this phenomenon will be temporary and restricted to close vicinity of construction site. The impact on surface water quality can be minimized by adopting following measures;

M/S DSS BUILDTECH PVT. LTD. 91

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Excavation during dry season and proper management of excavated soils,  Clearing all debris from site as soon as construction is over.  By providing proper hutment and toilet facilities for construction labour,  Proper disposal of wastewater.

4.5.4.2 Ground water Quality Impact: No hazardous chemical and material will be used in the development and construction phase of the project. Debris and waste generated will be collected and disposed suitably. Therefore, possibility of contamination of ground water will be negligible. Hence, no impact is anticipated on the ground water quality during the construction phase.

Mitigation: A well planned solid waste management plan will be followed during the construction phase including timely collection, segregation and disposal as per legal requirements.

4.5.4.3 Surface and Ground Water Hydrology Surface Water Hydrology Impact: The project site is outside flood plain. Runoff during rain takes way to natural drain and in storm water drains laid in the area. During construction phase, there is no impact anticipated on the drainage pattern of the project area.

Mitigation Measures: Project proponent will ensure no interception on water runoff flow routes and drainage pattern of the area throughout the construction of the project by providing adequate water channel.

Ground Water Hydrology Impact: Water requirement during construction phase will be met from STP treated effluent of HUDA/private water tankers. Water will be required for site preparation activities dust settlement, consolidation, compaction and curing as well as building construction and drinking

M/S DSS BUILDTECH PVT. LTD. 92

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA water requirement. The requirement of construction water will not put sudden pressure on the available ground water resources of area. Therefore, impact on ground water resources will be insignificant during construction of the project.

Mitigation Measures: Although no significant impact is anticipated on the groundwater regime, it is proposed to carry out the following to further minimize the demand on freshwater resources:  Curing water will be sprayed on concrete structures and free flow of water not allowed.  After liberal curing on the first day, all concrete structures will be painted with curing chemical to save water to stop daily water curing hence save water.  Concrete structures will be covered with thick cloth/gunny bags and then water sprayed on them to avoid water rebound and ensure sustained and complete curing.  Ponds will be made using cement and sand mortar to avoid water flowing away from the flat surface while curing.  Water ponding will be done on all sunken slabs. This will also highlight the importance of having an impervious formwork.

4.5.5 Air Environment Emissions Source: The potential sources of air emissions during the construction and development phase of the project will be as follows:  Dust from earth works (during site clearance and preparation);  Emissions from power generator at site;  Emissions from the operation of construction equipment and machines;  Fugitive emissions from vehicles running to site;  Fugitive emissions during the unloading of material at the site;  Fugitive emissions during mixing of cement with other building materials during development and construction activities;  Air emissions other than dust arise from combustion of hydrocarbons. The pollutants of concerns are NO2, SO2, CO, particulate matter, etc.

M/S DSS BUILDTECH PVT. LTD. 93

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Potential Impacts: Ambient air quality effects are normally assessed in relation to their potential to cause;  Health deterioration and nuisance in local communities  Health deterioration amongst on-site workers

Assessment of the impacts from Dust Emissions: During the excavation of channels, foundations, unloading of construction material, cement bags and mixing of cement with other building materials such as brick and silica dust, wood dust, fugitive dust emissions may be emitted at construction site. During construction, curtaining floors from all sides will be done to prevent cement dust from becoming airborne. It may be noted that all the emissions will be in the form of coarse particulate matter and settle down ultimately in closed vicinity of construction site. Therefore, no significant impact is anticipated due to dust emission during development and construction phase.

Assessment of the impact from Diesel Generators: Emissions from D.G. Set during construction phase may cause some localized impact on ambient air quality for short duration, as it will be operated during power failure only. It may be noted that the D.G. Set power will be used to operate construction equipment only if required. Adequate height of stacks and acoustic erective will be provided to the D.G. Set as per guidelines of CPCB to facilitate the dispersion of flue gases into the atmosphere.

Mitigation Measures: It is proposed to provide adequate dust control systems in the form of installation of batch plants, and loose material handling in covered sheds. Dust suppression system is also to be provided where necessary. Provision for treatment of DG Flue Gas emissions in a scrubber will be considered. It is further proposed to cover scaffolding, hosing down road surfaces and cleaning of vehicles especially during the dry season. Avenue and curtain plantation on the internal roads and peripheral plantation around the site will also be developed.

M/S DSS BUILDTECH PVT. LTD. 94

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

4.5.6 Noise Environment During the construction phase of project, noise will be generated from the various sources. Some major sources of noise generation at project site are listed here under:  Generation of noise during movement of vehicles carrying materials, loading & unloading activities.  Generation of noise from excavation machines, concrete mixer and other construction machines,  Generation of noise during the operation of D.G. Set  Generation of noise during concreting, hammering, etc.

All the above-mentioned sources of development and construction activities at Project would be intermittent and experienced occasionally. It may also be noted that the most of the construction activities would be carried out only during the daytime. The expected noise levels from various activities are given hereunder: From vehicles bringing materials to the site 70 dB (A) D.G. Set 85 dB (A) Excavation 80 dB (A) Concrete Mixtures 80 dB (A) Hammering 85 dB (A)

Resultant Noise Level: The combined effect of above sources can be determined as per the following equation: (Lpl/10) (Lp2/10) (Lp3/10) Lp (total) = 10 log (10 + 10 + 10 +……..) ……. (1)

Where: Lp1, Lp2 and Lp3 are noise pressure level at a point due to different sources in dB (A). The resultant maximum noise level for the above sources as calculated using equation (1) is 89.3 dB (A). For an approximate estimation of dispersion of noise in the ambient air from the sources, a standard mathematical model for sound wave propagation is used. The sound level generated by noise source decrease with increasing distance from the source due to wave divergence. An

M/S DSS BUILDTECH PVT. LTD. 95

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA additional decrease in sound pressure level from the source is expected due to atmospheric effect or its interaction with objects in the transmission path. For hemispherical sound wave propagation through homogenous loss of free medium, noise levels at various locations can be calculated due to different sources using model based on the first principles as per the following, equation:

Lr2 = Lr1 - 20 log (r2) – 8 ………. ( 2 )

Also, Lr2 = Lr1 - 20 log (r2/ r1)

Where: Lr1 and Lr2 – Sound Pressure Level (SPLs) at points located at 1m from sources and at distance of r2 from the source respectively in dB (A). Assuming no environmental attenuation factors, noise modeling has been done, which shows that noise level will be mingle with baseline noise level within short distance. Baseline noise level at the project site has been given in Table 4.4. Table 4.4 (a): Noise Levels in the Study Area(March –April 2015)

Table 4.4 (b): Noise Levels in the Study Area (October, -November 2015) S.N Location ZONE LIMIT as per CPCB Observed value Leq, o. Guidelines Leq, dB(A) dB(A) DAY* NIGHT** DAY* NIGHT** 1 Village Residential Area 55 45 54.1 43.9 Berka 2 Khaika Residential Area 55 45 53.1 42.8 3 Sohna Residential Area 55 45 52.4 42.1 4 Village Residential Area 55 45 53.9 42.3

M/S DSS BUILDTECH PVT. LTD. 96

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Dhunela 5 Vilalge Residential Area 55 45 52.6 Samp ki Nagli 41.6 6 Project Residential Area 55 45 53.2 42.8 Site

* Day time (6.00AM TO 10.00PM) ** Night time (10.00PM TO 6.00AM)

The noise produced during development and construction phase will have temporary impacts on the existing, ambient noise levels at project site but restricted to limited distance and only during daytime. Therefore, the impact of noise levels on surrounding area will be insignificant during the development and construction phase.

Mitigation: To minimize impacts of noise generation from construction activities, the workers will be provided with ear muffs and other protection devices. D.G. Sets with proper acoustic enclosure for controlling noise would be installed.

4.5.7 Terrestrial Ecology Impact: There is no loss of forestland due to the construction of the project. No tree felling is involved, as the site is devoid of vegetation.

Birds and other domesticated biodiversity observed near the project site are common and already adapted to thrive in human - colonized habitats. The project will not have any major negative ecological impact. There is no forest near the project site and therefore there will be no effect on the ecology of the area.

Mitigation Measures: However, it is to develop extensive green areas in the project site to improve the aesthetics of the area which will also help in reduction of air pollution, noise pollution and provide suitable habitat for local birds and animal species.

M/S DSS BUILDTECH PVT. LTD. 97

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

4.5.8 Economic Impacts Impact: Relatively long-lived economic impacts of the development and construction phase are likely to be experienced in local area for the duration of construction phase of 3-4 years as workers make everyday purchases from local traders in nearby areas. This is likely to give a short-lived stimulus to the traders that may disappear as soon as the construction is complete. Noticeable, flow-on economic impacts will be experienced in other sectors of economy as a result of purchase of construction materials and the payment of wages and salaries to the personnel engaged in the development and construction of the project. Once the development and construction will complete, there will be some long-term positive impact on the economic structure of the area. People in the area will get direct and indirect employment opportunities and other benefits due to the project. Therefore, an overall positive impact is anticipated on economy of the area due to the proposed project.

4.5.9 Socio-Economic During the development and construction of Expansion of Group Housing Project “The Melia”, about 800-850 skilled and semiskilled and unskilled workers will get direct employment opportunity, which will have beneficial impact on the local people and improve socio-economic condition of the area.

4.5.10 Construction Camp Impact: During the development and construction phase, most of the laborers will be from local areas as the project will be developed gradually in the time span of about 3-4 years. Therefore, laborer camps will be constructed to accommodate the laborers at the project site. This may lead to sanitation problems in the absence of adequate facilities.

Mitigation: Suitable measures will be taken at the construction camps to mitigate anticipated impacts due to temporary accommodation of laborers such as provision of clean drinking water, adequate toilet facilities, water and solid waste disposal system.

M/S DSS BUILDTECH PVT. LTD. 98

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Other safety precautions to be maintained at work site including provision of PPEs, guarding of dangerous machine parts, maintenance of equipment as hoists and lifts etc., and adequate provision of different types of fire extinguishers will be made. All applicable rules and regulations pertaining to workplace health and welfare of workers will be adhered to.

4.5.11 Solid Waste Management Impact: The construction and demolition waste includes debris, concrete (often recycled and reused at the site), steel and other metals, pallets, packaging and paper products, fluorescent tubes, wood beams, joists, studs, baseboards, cabinets and cupboards, railings, brick, doors and casings, interior windows, bathroom fixtures, light fixtures, ceiling grid and tile, furnishings, replant trees, shrubs. All wastes generated during the construction phase will be collected and segregated for disposal as per the standard practice.

During the development and construction phase, some amount of debris, cuttings of construction materials may be observed at construction site. However, the quantity of these waste materials would be very small and limited up to the construction site only. There will be no contamination due to this waste as it will be collected time to time during construction phase and disposed accordingly.

Mitigation Measures: After due waste segregation, recyclable wastes will be sold off to scrap dealers and vendors, while inert wastes will be disposed-off in landfills. Hazardous wastes will be disposed-off as per the provisions of the Hazardous Wastes (Management & Handling) Rules, 2016.

4.5.12 Transport Linkage and Traffic Impact: During development and construction phase, construction labour and construction materials bringing vehicles will approach the project site. Expansion of Group Housing Project “The Melia” is well connected to neighborhood, where public transport facility, like, buses and minibuses are easily available in the area as transport linkage. During construction phase, some impact is anticipated on the transport linkage of the area, however increase in traffic will not

M/S DSS BUILDTECH PVT. LTD. 99

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA adversely affect the local traffic pattern since the site is well connected via wide roads and present traffic load on these road is not significant.

Mitigation: Through careful planning, the movement of the heavy vehicles will be scheduled to reduce load on existing traffic such that the peak hours are avoided. It will also be ensured that all the vehicles to the site will be provided with Parking space such that there is no waiting time along the access roads.

4.6 ASSESSMENT OF THE ENVIRONMENTAL IMPACTS DURING OPERATION PHASE 4.6.1 Land Environment Impact: During the operation phase of the project, the soil may get polluted/ contaminated from littering of various kinds of wastes generated within the site such as food items, paper, wood pieces, paints, pesticides, oil & grease etc. However, as a result of the proposed solid waste management plan, no significant impact is anticipated.

Mitigation Measures: To ensure against any chances of soil pollution, it is imperative to establish a well-planned solid waste collection system covering all areas of the project site apart from door to door for the residential units. An identified area will be designated for storage and segregation of the wastes which will be treated/ disposed as per their characteristics.

4.6.2 Water environment 4.6.2.1 Surface water hydrology Impact: During the operation phase, no water will be taken from surface water bodies in the area. Further, adequate drainage will be provided at the project site to channelize the storm water for rainwater harvesting.

The sewage effluents generated from the project will be collected through the sewer line network provided in the project site for treatment in the Sewage Treatment Plant (STP), and the treated

M/S DSS BUILDTECH PVT. LTD. 100

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA water reused within the site thereafter. Therefore, impact on the surface water hydrology will be insignificant during the operation phase.

Mitigation: It is proposed to provide rainwater harvesting across the project site. The roof tops of buildings will also be connected to the rainwater collection system. This will not only reduce the pressure of storm water management system of the city but also recharge groundwater.

4.6.2.2 Ground water hydrology Impact: During operation phase, the total water requirement of the Expansion of Group Housing Project “The Melia” is approx. 707 KLD out of which domestic water requirement is 563 KLD. The fresh water demand will be approx. 414KLD. The water requirement will be met from HUDA. Therefore, no impact is anticipated on ground water resources due to project.

To enhance the ground water level around the project site the rain water harvesting will be proposed. The rainwater harvesting will recharge groundwater aquifers from the open areas as well as roof top of the buildings. Treated water from the site will be recycled for landscaping, flushing and to water body.

Water meters conforming to ISO standards will be installed at the inlet point of water uptake and at the discharge point to monitor the daily water consumption. To further lower the water consumption, options of Low flow flushing systems, sensor based fixtures, waterless urinals, and tap aerators etc. will be explored.

4.6.2.3 Surface Water Quality Impact: The sewage effluents generated from the Expansion of Group Housing Project “The Melia” will be collected through the sewer line network provided in our Project, and treated in onsite STP of 1 onsite STP of total capacity 875 KL that will generate 376 KLD of treated effluent which will be reused for flushing and horticulture.

M/S DSS BUILDTECH PVT. LTD. 101

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

It is expected that the project after Expansion will generate approx. 418 KLD of sullage. Surplus treated effluent will be discharged to external sewer line.

Mitigation Measures: As no impact is anticipated on the surface water bodies of the region, no mitigation measures are suggested.

4.6.2.4 Ground Water Quality Impact: The storm water from the site will be collected for recharging groundwater resources after adequate treatment of the storm water through oil, grease traps and filtration. The wastewater from the site is proposed to be used for landscaping only after adequate treatment in Sewage Treatment plant. Hence, no adverse impact is anticipated on the groundwater quality form the project.

Mitigation Measures: The project site will be maintained well. Solid waste management practices will be adopted and followed to prevent groundwater pollution from rain water harvesting.

4.6.3 Air Environment Prediction of Impacts Vehicular emissions and DG sets emission will be major sources of air pollution from building construction projects. Ground Level Concentration of pollutants (as added by the project) will depend upon the following:  Emission of pollutants from additional traffic on the roads due to the project.  Meteorological conditions.  Emission sources from D.G. Sets.

PM, NO2, SO2 and CO will be the main pollutants of primary concern released from traffic movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the dispersion of vehicular emissions would be confined within limited distance from the road and concentration will decrease with the increase in distance from road. It was anticipated that the

M/S DSS BUILDTECH PVT. LTD. 102

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well within the stipulated National Ambient Air Quality Standards due to traffic movement and vehicles used inside the premises. DG sets will be main source of Air Pollution in the project. CPCB/ MoEF & CC approved USEPA dispersion model -ISCST3 was used for prediction of impacts caused by DG sets. Stack & emission data was used as per design value provided by standard make and stipulated standards. Other primary data used as input for model were hourly meteorological data of Wind speed, direction, temperature, cloud amount and mixing height. Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, ”. Hourly meteorological monitored at site during study period data was compared with long term data available from the nearest India Meteorological station or any other authorized source/Govt. agencies.

In this project, total 2 no. of D.G. set of total capacity 1635 kVA (1 x 1010 kVA & 1 x 625 kVA) have been proposed, for back up of electricity supply during power failure.

This will cause emission of PM, SO2, NO2 and CO in the Ambient Air Quality. In the project D.G. sets will be used only during power failure and low sulphur diesel will be used as fuel to minimize SO2 emission. Therefore, incremental load in the ambient air environment will be very low as given in the report. An adequate stack height of D.G. sets will be provided as per the stipulated guidelines of Central Pollution Control Board (CPCB)/ National Building Code Manual to facilitate proper dispersion of pollutants and to minimize the impact on Ambient Air Quality under the influence of local meteorology.

Meteorology – Hourly Meteorological data of wind speed & direction, temperature, cloud amount and rainfall were monitored at site for 5 month for the dispersion model. Wind rose (Figure - 4.1) was prepared in sixteen directions as per standards. It was observed that westerly and southwesterly was prevalent wind during the study period.

M/S DSS BUILDTECH PVT. LTD. 103

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Figure 4.1: The wind-rose diagram based on the study period

Model details and Frame work of Computation: The predictions for air quality during operation phase were carried using CPCB/MoEF & CC approved “USEPA, Industrial Source Complex (Version - ISCST3)” Dispersion model developed by the US Environmental Protection Agency (USEPA) for prediction of pollutants dispersion from single or multiple point sources using emission and hourly meteorological data of the study period. Assumption used in the model was as follows:

 The plume rise is limited to that of the mixing layer as published by IMD in the Catalogue of Atlas of Mixing Heights in India for the site  Stack down-wash is not considered.  Flat terrain is used for computations;  It is assumed that the pollutants do not undergo any Physico-chemical transformation.  Chemical and scavenging process occurred in the atmosphere in the pollutants released at the stack exit is not considered.

M/S DSS BUILDTECH PVT. LTD. 104

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Prediction is based on single/multiple point sources, pollution released at stack exit and dispersed on the ground under influence of local meteorological conditions during the season. ISCST3 dispersion model was used to predict GLC caused by a single point source at each receptor of 40 m x 40 m of grid network covering total area of 2000 m x 2000m around the proposed source with stack & emission values and 1-hourly meteorological data. It was observed that SO2, NO2, Co and PM were significant pollutants released from the fuel of the

D.G. sets. Emission of PM, CO and SO2 were found insignificant with low values compared to

NO2. In this project, NO2 was the worst affected pollutant released into the atmosphere (Table 4.5) with high emission value.

Mitigation Measures: The project proponent will develop a green belt inside the premises of the project site and along the internal road, which will work as barrier for the movement of pollutants and help in pollution control.

4.6.4 Noise Environment

Impact: The main sources of noise from the project are running of D.G. Sets and vehicular traffic. D.G. Sets will provide emergency electricity supply during power failure. This will be intermittent and for short durations. The vehicles playing within the site will be mainly of the residents and are hence not expected to cause unnecessary noise. Hence, during this phase, no major impact on noise environment is anticipated.

Mitigation Measures: D.G. Sets will be fitted in acoustic enclosures to control the noise generated within 25 dB (A) insertion loss or for meeting the ambient noise standard whichever is on higher side as per E (P) Act, GSR 371 (E) and its amendments. Adequate personnel protective equipment (PPE) will be provided. The traffic noise will diminish within a short distance from the source of origin. Honking within the site will be discouraged. Proposed green belt plantation will further restrict the noise.

M/S DSS BUILDTECH PVT. LTD. 105

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

4.6.5 Terrestrial Ecology Impact: The project proposes 20,494.66 m2 (30.17 % of plot area) of green area that will be planted with local species with aesthetic appeal that will attract local bird and insect species. As against the existing barren stretch of land, the project will add to the greenery and beauty of the region.

Mitigation Measures: Various kinds of plantation such as curtain, avenue, ornamental plantation and lawns will be started during the construction phase itself and maintained during the operation phase. Open space and Parks will be fenced through the grasses and ornamental plants. Local and low water demanding plants that will also be effective as sinks for various pollutants and attract birds will be grown in the site that will contribute in positive to the local ecology.

4.6.6 Socio-economic Impact Impact: During operational phase of the project, approx. 13000 persons will get employment opportunities. As an estimate, during operation phase, more than 300 persons will get marginal employment opportunities. This will help in improving the quality of life of economically weaker sections of the local area.

Mitigation Measures: To further improve the socio-economic conditions of the area, it may be proposed to employ mainly local people as workers. Much of the maintenance arrangements may also be made with local companies and purchase of new parts from the local market.

4.6.7 Transport Linkage and Traffic Impact: The vehicle from the project site will increase car and two wheeler traffic load along the road during peak hours. However, since present load is lean, increase in traffic load may not lead to traffic congestion problem.

M/S DSS BUILDTECH PVT. LTD. 106

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Mitigation Measures: As per the planning, entry and exit will occur through service road. Internal roads have been designed as per NBC and local regulations for smooth traffic circulation.

4.6.8 Energy Resources Impact: During the operation phase of the project, electric supply will be provided from D.G set and Dakshin Haryana Bijli Vitran Nigam.

Mitigation Measures: To promote energy conservation, it is proposed to provide the buildings with low energy consuming fixtures and maximize availability of natural light.

M/S DSS BUILDTECH PVT. LTD. 107

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 5: ANALYSIS OF ALTERNATIVES

5.1 INTRODUCTION This chapter discusses the assessment of various options that may be available for different components of the project in terms of environmental suitability. Lately, there are a number of options available for the use of building materials, means of energy conservation and methods of transportation. The various applicable options are thus evaluated for their suitability to project and environment.

5.2 BUILDING MATERIALS The choice of building materials plays an important role in terms of energy efficiency of the building. The manufacture of building materials should also be assessed to ensure the use of environment friendly and recycled/ recyclable construction material.

5.2.1 Wall Conventionally, sun burnt clay bricks are cemented in construction of walls. The strength of these construction materials cannot be compromised which will otherwise pose a threat to the life and property of the occupants. However, presently, materials with similar properties are easily available that are made of waste products, thereby reducing the waste burden and conserving natural resources. Thus, the project proposes the use of the following for walls:  Brick and block products with waste and recycled contents such as fly ash (15 to 35%), blast furnace slag (20 to 25%), sewage sludge, waste wood fibre etc.  Fly ash based lightweight aerated concrete blocks – flyash being a waste product of thermal power plant poses the challenge of disposal. Hazardous in powder form, it is rendered harmless when moulded as bricks. Fly ash-based lightweight aerated concrete blocks are manufactured for walling and roofing purposes by mixing fly ash, quick lime, or cement and gypsum with a foaming agent like aluminum powder  Fal-G products – are manufactured by use of two waste products being fly ash, calcined gypsum (a byproduct of phosphogypsum or natural gypsum) along with lime.  Perforated bricks

M/S DSS BUILDTECH PVT. LTD. 108

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  Materials proposed for use in the wall openings such as doors and windows include:  Precast thin lintels, use of Ferrocement-sunshade cum lintel etc.  Renewable timber  Steel manufactured from recycled content  Aluminum manufactured from verified recycled content  Saw dust based doors and window frames  Ferrocement shutters, PVC doors and windows, Rice husk boards, Natural fibre- reinforced  Polymer composite door panels  The finishing for the openings will be by the use of Fly ash, Ceramic tiles, Terrazzo floors.

5.2.2 Roof The conventional material used for roofing is RCC, as it is suitable for longer spans. The constituents of RCC, i.e. cement, sand, aggregate and steel are energy intensive materials and high embodied energy content. Alternately, it is proposed to use lightweight synthetic aggregates such as fly ash based aggregates, which is suitable for manufacture of brick, blocks, and is good substitute for clinker and natural aggregates. When pre-cast/aerated cellular concrete walling blocks and roofing slabs are used in multi- storied structures, they reduce the weight, resulting in a more economical design. They have high rating to fire resistance and provide better insulation and thus improved energy efficiency. These are manufactured by the aerated cellular concrete manufacturing process.

5.2.3 Superstructure Structural frame of building comprises of footing, columns, beams and lintels, over which the envelope of building is supported. A variety of metals are used in buildings. The major building material used structurally is steel. Steel has a high-embodied energy and recyclable content, as well as scrap value. Aluminum forms the second most common material used for roofing sheets, window frames, and cladding systems, which has the highest recyclable content. Hence, bulk of the metal needs for the building will be met by steel and aluminum.  Problem with RCC. The choice of cement will be:

M/S DSS BUILDTECH PVT. LTD. 109

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  Use of fly ash and/or blast furnace slag concrete: The amount of cement used in concrete can be reduced by replacing a portion of the cement with coal fly ash (waste material from coal burning power plants) and/or GGBF (ground granulated blast furnace) slag in conventional mixes.  Recycled aggregates: Recycled aggregates include crushed concrete, brick, glass, or other masonry waste can also be used in conventional mixes  Lightweight concrete: Aluminum powder when added to lime reacts and form hydrogen bubbles, and a lightweight cementation material is formed which could be used in conventional mixes.

5.2.4 Roads and open spaces Roads and open spaces consist of compound walls, grills, roads, sidewalks, parking lots, drains, curbs, landscaped areas, street furniture, tree covers, and flowerbeds. In line with environment friendly design it is proposed to provide:  Permeable paving- Permeable (porous) paving will be provided to control surface water runoff by allowing storm water to infiltrate the soil and return to the ground water. The traffic areas will however continue to be impermeable.  Gravel/crusher fines - Loose aggregate materials from masonry wastes will be used to cover pedestrian surfaces.  Use of grass pavers on the road, parking and pedestrian areas to reduce the heat island effect.  Use of steel in fencing, grills, tree covers, and benches and even in streetlights will be replaced by bamboo in the parks and green landscaped areas.

5.3 NATURAL HAZARD PRONE AREAS The project is located in high earthquake risk area (Seismic zone- IV). Special attention is thus given to the structural design of foundation, elements of masonry, timber, plain concrete, reinforced concrete, pre-stressed concrete, and structural steel. All applicable guidelines will also be followed in this regard to ensure safety of the building and its residents.

M/S DSS BUILDTECH PVT. LTD. 110

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA 5.4 GREEN BUILDING M/s DSS Buildtech Pvt. Ltd, proposes to design and construct the project in line with the requirements of Green Building. Without compromising on the safety and comfort of the occupants, care will be taken to achieve an energy efficient, water conscious project the benefits of which will be enjoyed in monetary terms by the residents and other intangible benefits will result for the society at large.

This will be achieved by: a. Minimal disturbance to landscapes and site condition The project aims to integrate the new development with the local existing surroundings. Efforts are made to minimize on-site tree cutting by careful and detailed layout planning. Tree felling will be undertaken only after receiving requisite permissions and under strict supervision. The original landscape of the site has also been integrated with the design of the project such that there is no alteration in the topography. b. Resource Conservation and Environmental Friendly Building Materials To reduce the ecological footprint of the development, use of recycled material for construction and conserving natural resources is of primary importance. In this light, the use of recyclable building materials has been proposed for various building materials. It is also proposed to reuse building components, minimization of construction waste, etc. The project proponent is also committed towards conservation of water. This includes use of treated water, rainwater harvesting, provision of low water flow fixtures and raising awareness on means of water conservation. c. Efficient use of Water and Water Recycling The need for water conservation in the face of impending water crisis cannot be overemphasized. The project will follow a three pronged management for water resource viz. water resource development, minimize use of water and recycle treated effluent within the site.

M/S DSS BUILDTECH PVT. LTD. 111

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Rainwater harvesting across the entire project area is proposed to recharge groundwater. A detailed storm water drainage system and water harvesting procedures are proposed to achieve this. The water demand is proposed to be brought down by the use of water efficient fixtures, implement best management practices for water conservation. An important means for achieving this is spreading awareness to the occupants for water conservation. To reduce the freshwater demand of the project, waste water from site will be treated in a STP and treated effluent will be reused for landscaping, flushing and DG cooling. d. Use of Energy Efficient design and Eco-Friendly Equipment The project will be designed such that there is optimal solar energy utilization, especially natural light availability. Shading will be provided on sides that will otherwise reduce the energy efficiency of the building. Energy conservation will be one of the focuses during the planning, development, construction and operation stages.

Use of Renewable Energy The electrical supply is largely dependent on thermal power plants that are largely responsible for accelerating the phenomenon of global warming and consumption of limited natural resources. It is of paramount importance to shift focus on other renewable sources of energy to achieve sustainable development in the energy sector. The area receives adequate hours and intensity of sunlight for effective solar energy generation. Taking full cognizance of the availability of natural sunlight and technology, the project proposes the use of solar energy to reduce the power demand of the project. Solar energy will be used for the purpose of heating of the water. e. Indoor Air Quality for Human Safety and Comfort To provide the occupants with a safe building is the primary responsibility of a developer. Indoor pollution source that release gases or particles into the air are the primary cause of indoor air quality problems in homes. Inadequate ventilation can increase indoor pollutant levels by not bringing in enough outdoor air to dilute emissions from indoor sources and by not carrying

M/S DSS BUILDTECH PVT. LTD. 112

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA indoor air pollutants out of the home. High temperature and humidity levels can also increase concentrations of some pollutants. Likewise, it is proposed to use all user safe building materials such as: i. The buildings will be painted with low VOC, ammonia free paints. ii. Asbestos will not be used. iii. Adequate ventilation will be provided in each residential unit and floor iv. Adequate openings for sunlight to enter the building, thereby reducing chances of microbial growth. v. All building maintenance and cleaning materials will be kept in an isolated and well ventilated room with restricted entry.

f. Effective Controls and Management Systems It is proposed to establish a Management System that will comprise modern equipment as well as an efficient team of maintenance staff. i. Each tower as well as common area will be provided with fire alarm as well as water sprinklers. All essential services such as lifts and water supply will be provided with power back up. ii. A security system for the entire project will be provided comprising intercom facility, closed circuit camera to the entrance and round-the-clock manning. iii. Separate entry and exits are proposed. The staffs’ vehicle will be provided with identification stickers while visitors’ vehicles will be monitored through security guards at the entrance/exit.

The project proponent further proposes extensive green areas as avenues, parks and roadside plantation. The plants serve to provide positive environmental impacts such as reduction in overall energy use in buildings.

5.5 COMMUNITY ISSUES All efforts will be made to ensure that the exiting neighborhood is not adversely affected by the project.

M/S DSS BUILDTECH PVT. LTD. 113

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

5.6 ENERGY CONSERVATION To achieve conservation of energy, appropriate design of a building is of paramount importance.

Accordingly, it is proposed to incorporate the guidelines of Energy Conservation Building Code, 2017 in the building structure.

The concept of passive solar design emphasizes architectural design that minimize building energy consumption by integrating conventional energy-efficient devices, such as mechanical and electrical pumps, fans, lighting fixtures, and other equipment, with passive design elements, such as building siting, an efficient envelope, appropriate amounts of fenestration, increased day lighting design, and thermal mass. The basic idea of passive solar design is to allow daylight, heat, and airflow into a building only when beneficial. The project layout has been finalized after careful citing consideration various components of Expansion of Group Housing Project “The Melia” to optimize availability of natural sunlight. Advanced Solar Passive Techniques are employed to achieve energy efficiency.  Glazed windows are proposed. To reduce heat losses during the night these windows are often double-glazed and have insulating curtains.  Thermal storage wall is placed between the glazing and habitable space to prevent solar radiation from directly entering the living space.  Passive cooling systems i.e. cooling directly from evaporation, convection radiation without using any intermediate electrical devices.  Provisions for use of desert cooler (Indirect evaporative cooling which comprises water, evaporative pads, a fan and a pump).

Effective measures have been incorporated to minimize the energy consumption in following manners: • Use of LED lamps instead of GLS lamps Expansion of Group Housing Project “The Melia”. • Use of LED instead of GLS lamps for Common area. • T5 lamps are used instead of Normal Fluorescent lamps in Basements

M/S DSS BUILDTECH PVT. LTD. 114

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA • Using electronic ballast for Discharge Lamps • Solar water heating systems will be provided as per HAREDA norms.

5.7 TRANSPORTATION A well planned road network is proposed within the project premises. Adequate parking will be provided during construction phase to ensure that all heavy vehicles visiting the site are provided parking space within the site. There will be no parking on the external roads. The movement of the vehicles will also be scheduled such that the peak hours are avoided.

In the operation phase, entry and exits will be from separate gates to minimize disturbance to the approach roads to project site Adequate parking is proposed within the project site. Wide internal roads are proposed as per norms. To achieve the speed limit, speed humps will be provided.

M/S DSS BUILDTECH PVT. LTD. 115

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 6: ENVIRONMENTAL MONITORING PROGRAM

6.1 INTRODUCTION The purpose of monitoring programme is to ensure that the specified mitigation measures defined in the EMP are complied with and leads to the desired benefits for the target area and its population. To ensure the effective implementation of the EMP and gauge the efficiency of the mitigation measures, monitoring will be undertaken both during the construction and operation period of the project.

6.2 PERFORMANCE INDICATORS (PIs) The physical, biological and social components are of particular significance to the project is as listed below:  Air quality  Water quality  Noise levels  Solid Waste Management  Replantation success/survival rate Of these, the following are selected as the Performance Indicators (PIs) and will be monitored, since these are well known and comparative data series exist:  Air Quality  Noise levels  Water Quality  Flora To ensure the effective implementation of the mitigation measures and environmental management during construction and operation phase of project road, it is essential that an effective Environmental Monitoring Plan be designed and followed as given in Table 6.1.

6.2.1 Ambient Air Quality (AAQ) Monitoring Ambient air quality parameters recommended for monitoring with regard to constructional activities are PM, CO, SO2, and NO2. Monitoring will be carried out twice a week for one month in each season during construction phase in accordance to National Ambient Air Quantity Standards. The locations with the pollution parameters to be monitored are detailed out in the Environmental Monitoring Plan (Table 6.1).

M/S DSS BUILDTECH PVT. LTD. 116

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

6.2.2 Noise Level Monitoring The measurement of noise levels will be carried out at all designated locations in accordance to the ambient Noise Standards formulated by MoEFCC as given. Noise level will be monitored on twenty-four hourly bases. Noise should be recorded at “A” weighted frequency using a slow time response mode of the measuring instrument. The measurement location, duration and the noise pollution parameters to be monitored are detailed in the Environmental Monitoring Plan (Table 6.1).

6.2.3 Survival of Plantation To ensure the proper maintenance and monitoring of the proposed plantation activities, a regular survey of survival rate of the planted trees is proposed from the start of operation of the project.

M/S DSS BUILDTECH PVT. LTD. 117

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 6.1: Environmental Monitoring Plan Environment Project stage Parameter Standards Location Duration / Frequency Component Ground Water Construction Drinking water Drinking water standards 5 locations including Half yearly Quality Stage parameters (IS 10500) project site

Operation Drinking water Drinking water standards Project site Once every year during the Phase parameters (IS 10500) dry season

Drinking water Construction Drinking water Drinking water standards Supply water Half yearly Stage parameters (IS 10500)

Operation Drinking water Drinking water standards Supply water Half yearly Phase parameters (IS 10500)

Treated Operation pH, BOD, COD, TDS , General Standards for Outlet of the Sewage Every three months during wastewater Phase TSS, DO, discharge of effluents Treatment Plant (s) the project life cycle Air Construction PM, SO2, NO2, CO National Ambient Air 1. Village Berka Continuos 24-hourly, Half Phase Quality Standards 2.Village Khaika Yearly 3. Sohna Town Village Dhunela 4. Village Samp ki Nagli 5. Project Site

Operation PM, SO2, NO2, CO, National Ambient Air Project Site Continuous 24-hourly, Phase Quality Standards HalfYearly

M/S DSS BUILDTECH PVT. LTD. 118

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Environment Project stage Parameter Standards Location Duration / Frequency Component Noise Construction Noise Level in dB (A) As per Ambient Noise Village Berka One day hourly Phase Standards Village Khaika measurement, Half Yearly Sohna Town Village Dhunela Village Samp ki Nagli Project Site Operation Noise Level in dB (A) As per Ambient Noise Project site One day hourly Phase Standards measurement, Half yearly Rainwater Operation Inspection of storm water Design parameters Project site Prior to monsoon harvesting Phase drains and rainwater harvesting pits

M/S DSS BUILDTECH PVT. LTD. 119

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

6.3 DATA MANAGEMENT The monitoring will be carried out through MoEFCC/ NABL approved laboratory. All results will be maintained and submitted to the Regulatory authorities as per norms..

6.4 REPORTING SCHEDULES The environment management cell will be responsible for timely conduct of the monitoring activities. The results of the analysis will be intimated to the project head. Any anomaly in test results will be investigated into and proper corrective actions will be undertaken. A complaint register will also be maintained to note any complaints from the staff and visitors in the project or any other stakeholder. Corrective actions taken against the complaints will also be noted.

M/S DSS BUILDTECH PVT. LTD. 120

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 7: ADDITIONAL STUDIES

7.0 INTRODUCTION This chapter broadly looks at various aspects related to disaster management, resource conservation and resettlement issues.

7.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN The project will encompass the lives of a large number of people. It will also involve installation of various structures and machineries that meet the comfort and needs of its residents but may also pose serious threat in case of an accident. It is thus considered necessary to carry out a risk assessment and disaster management plan for the project.

7.1.1 Risk Hazard & its control measures It is attempted to plan and construct the buildings following all safety norms. However, it is not always possible to totally eliminate such eventualities and random failures of equipment or human errors. An essential part of major hazard control has therefore, to be concerned with mitigating the effects of such emergency and restoration of normalcy at the earliest. A detailed table showing activities during construction and operation phase along with mitigation measures are given in Table 7.1.

Table 7.1: Activities during construction and operation along with mitigation measures HAZARDS ASSOCIATED WITH CONTROL/MITIGATION ACTIVITIES MEASURES (During Construction & Operation) Manual Handling - Strains and sprains due to incorrect lifting - Exercise/warm up - too heavy loads - get help when needed -Twisting - bending - repetitive movement - body - control loads vibration. - rest breaks/no exhaustion - no rapid movement /twisting/ bending / repetitive movement - Good housekeeping. Falls - Slips - Trips - Falls on same level - Good Housekeeping - falls to surfaces below - tidy workplace

M/S DSS BUILDTECH PVT. LTD. 121

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA - poor housekeeping - guardrails, handholds, harnesses, hole - slippery surfaces cover, hoarding, no slippery floors/trip - uneven surfaces hazards - poor access to work areas climbing on and off - clear/ safe access to work areas plant - egress from work areas - unloading materials into excavations wind - dust/water controlled - falling objects. - PP Fire - Flammable liquids/Gases like LPG, Diesel - Combustible/flammable materials Storage area and combustible building materials properly stored/used - poor housekeeping - good housekeeping - grinding sparks - fire extinguishers made available & Fire - Open flames, absence of Fire hydrant network. hydrant Network with reserve Fire water (As per NFPA Code) - Emergency Plan in case of Fire or collapse of structure. Absence of Personal Protective Equipment - Lack of adequate footwear - Head/face - head protection - footwear - hearing/eye protection - hearing/eye - respiratory protection - skin - gloves - respiratory protection provided -goggles. - training - maintenance Defective or wrong Hand Tools - Wrong tool - Right tool for the job - defective tool - proper use of tools - struck by flying debris - good condition/ maintenance guards - caught in or on - isolation/ proper demarcation of work - missing guards space - eye/face protection - flying debris controlled Electricity - Electrocution - Leads good condition and earthed - overhead/underground services - no temporary repairs - any leads damaged or poorly insulated - no exposed wires - temporary repairs - good insulation -no testing and tagging - no overloading - circuits overloaded - use of protective devices - non use of protective devices. - testing and tagging - no overhead/ underground services Scaffolding - Poor foundation - All scaffolds correctly braced and - lack of ladder access insufficient planking stabilized - lack of guardrails and toe boards - 3:1 height to base ratio

M/S DSS BUILDTECH PVT. LTD. 122

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA - insufficient ties or other means - firm foundation, plumb and level - all scaffolds incorrectly braced or stabilized - ladder access provided and used to prevent overturning. - proper platform (3 planks/675 mm) - planks secured - guardrails and toe boards - 900mm to 1100mm high, within 200mm of working face, mid-rail. Ladders - Carrying loads - Secured against movement or footed - not secured against dislodgement - ladders in good condition - defective ladders - regularly inspected - not sufficient length - extend 1m above platform - wrong positions - 4:1 angle - incorrectly placed (angles, in access ways, - out of access ways, vehicle vehicle movements. movements - not carrying loads - 3 points of contact - no higher than 3rd step down - use for access only, not working platforms Excavations - Trench collapse - Soil stability known - material falling in undetected underground - no water accumulation services - existing services known - falls - material 600mm from edge - hazardous atmosphere struck by traffic and - clear of suspended loads mobile plant. - hardhats/PPE - ladders - public protection – atmospheric testing - traffic controls - Emergency Plan. Gas Cutting and Welding - Fire - Welding flash and burns controlled - welding flash, burns, fumes, electrocution with PPE and shields in wet conditions - fumes controlled with ventilation - flashback in oxygen set, leaking cylinders, and PPE (in good condition and properly acetylene cylinders lying down positioned),Gas cylinders be kept upright & - poorly maintained leads. secured position (properly tied) - Combustible materials to be kept at secured place to avoid fire & Fire Extinguishers to be kept in fire prone area with training to people for its use. Noise - Unknown noise levels - Levels below 85 decibels

M/S DSS BUILDTECH PVT. LTD. 123

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA - known noise levels over 85 decibels - Proper protection. Falling Material - Fall during carrying/Lifting materials- Materials to be secured dislodged tools and materials from overhead work kept away from edge areas. toe boards Use of hard hats. Craneage& Lifts - Display of carrying capacity i.e. load (No. Of - Periodic testing by competent authority person), incorrectly slung, defective lifting - correctly slung/secured loads, lifting equipment, unsecured loads, craning in close equipment good condition proximity to building people and plant - use of proper hand signals - falls - falls while unloading controlled. - falling materials. Visitors Presence at site - Falls - Sufficient hoarding - struck by dropped materials - fencing and barricades - road accidents - safe pedestrian access past site - insufficient hoarding or fencing traffic management for loading and delivery - pedestrian access past site - construction separated from - mechanical plant movement on and off site. occupied areas of projects.

7.1.2 Emergency Response Plan (ERP) The overall objective of an Emergency Response Plan (ERP) is to make use of the combined resources at the site and outside services to achieve the following:

1. To localize the emergency and if possible eliminate it; 2. To minimize the effects of the accident on people and property; 3. Effect the rescue and medical treatment of casualties; 4. Safeguard other people; 5. Evacuate people to safe areas; 6. Informing and collaborating with statutory authorities; 7. Initially contain and ultimately bring the incident under control; 8. Preserve relevant records and equipment for the subsequent enquiry into the cause and circumstances of the emergency; 9. Investigating and taking steps to prevent reoccurrence The ERP is therefore related to identification of sources from which hazards can arise and the maximum credible loss scenario that can take place in the concerned area. The plan takes into

M/S DSS BUILDTECH PVT. LTD. 124

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA account the maximum credible loss scenario - actions that can successfully mitigate the effects of losses/ emergency need to be well planned so that they would require less effort and resources to control and terminate emergencies, should the same occur. Main hazards identified for the project include hazards pertaining to fires in buildings and fire in diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is described in the following section.

7.2 RESPONSE IN CASE OF EARTHQUAKE Response Procedures for Occupants If indoors: 1. Take cover under a piece of heavy furniture or against an inside wall and hold on. 2. Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try to leave the building because objects can fall on you.

If outdoors: Move into the open, away from buildings, streetlights, and utility wires. Once in the open, stay there until the shaking stops.

If in a moving vehicle: Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees, overpasses, or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps that might have been damaged by the quake.

After the earth quake 1. After the earthquake be prepared for aftershocks. 2. Although smaller than the main shock, aftershocks cause additional damage and may bring weakened structures down. Aftershocks can occur in the first hours, days, weeks, or even months after the quake.

Help injured or trapped persons.

M/S DSS BUILDTECH PVT. LTD. 125

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA 1. Give first aid where appropriate. Do not move seriously injured persons unless they are in immediate danger of further injury. Call for help. 2. Remember to help those who may require special assistance--infants, the elderly, and people with disabilities. 3. Stay out of damaged buildings. 4. Use the telephone only for emergency calls.

Response Procedure for Emergency Team 1. Formulate an Emergency Response Team for earthquake response. Using the public address system, inform residents of response procedures discussed above. 2. Inform the necessary authorities for aid. 3. Ensure no person is stuck beneath any debris, in case of a structural failure. 4. Ensure that all occupants standing outside near the buildings are taken to open areas. 5. Ensure that the first aid ambulance and fire tender vehicles are summoned if necessary. 6. Inform the nearby hospitals if there are any injuries. 7. Check the utilities and storage tanks for any damage.

7.3 RESPONSE FOR LPG LEAKAGE 1. The affected area should be evacuated and cordoned off immediately 2. Initiate an Emergency Response Team for LPG leakage. 3. Shut down the main valves in the gas bank. 4. Ensure that only concerned personnel are present in the affected area and all other personnel and visitors are moved to the nearest assembly points. 5. Rescue trapped personnel, also check if any personnel are unconscious in the area and immediately move them outside and provide first aid. Ambulance should be summoned to take injured personnel to the nearest hospital. 6. Personnel in the nearby buildings to close all doors and windows to prevent entry of the leaked gas. 7. Source of leakage to be traced and isolated from all the other areas. And if required use pedestal fans to bring down the gas concentration. 8. In case of a fire follow the instructions in case of fire.

M/S DSS BUILDTECH PVT. LTD. 126

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

7.4 RESPONSE IN CASE OF FIRE 1. Required response during in the event of a fire should be described in signs located in the lobby. 2. On sighting a fire, it should be immediately informed to the environment manager giving the exact location and type of fire in detail. 3. Initiate the Emergency Response Team for fires. 4. If the fire is small, engage in extinguishing the fire using the nearest fire extinguisher. 5. Guide the Emergency Response Team staff to the emergency assembly point. 6. The Emergency Response Team should immediately inform the nearest dispensary and security force. If required a fire tender should be summoned. 7. The response team should immediately move to the point of fire and take all necessary steps to stop the fire. If the fire is not controllable and spreads then the manager in charge should inform the district authorities and call for external help. 8. The Emergency Response Team will provide immediate relief to the injured residents at the scene of incident. Any injured persons should be evacuated on priority to the dispensary or one of the nearest hospitals based on their condition.

Instructions for occupants 1. Get out of buildings as quickly and as safely as possible. 2. Use the stairs to escape. When evacuating, stay low to the ground. 3. If possible, cover mouth with a cloth to avoid inhaling smoke and gases. 4. Close doors in each room after escaping to delay the spread of the fire. 5. If in a room with a closed door. 6. If smoke is pouring in around the bottom of the door or if it feels hot, keep the door closed. 7. Open a window to escape or for fresh air while awaiting rescue. 8. If there is no smoke at the bottom or top and the door is not hot, then open the door slowly. 9. If there is too much smoke or fire in the hall, slam the door shut. 10. Stay out of damaged buildings. 11. Check that all wiring and utilities are safe.

M/S DSS BUILDTECH PVT. LTD. 127

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA A state of the art firefighting system is proposed for the project to prevent and control fire outbreaks. The firefighting system will consist of portable fire extinguishers, hose reel, wet riser, yard hydrant, automatic sprinkler system, and manual fire alarm system. The Expansion of Group Housing Project “The Melia” buildings will also be provided with automatic fire detection and alarm system.

7.5 RESOURCE CONSERVATION The project will lead to utilization of various natural resources. As an environmentally responsible corporate, the developer will endeavor to conserve these resources by judicious management and recycling and strive to build up these resources where possible.

No withdrawal of groundwater: The water during operational phase will be sourced from HUDA. Reduced use of water: To further minimize the use of available freshwater, various low flow fixtures may be provided such as Low flow flushing systems, sensor based fixtures, waterless urinals, tap aerators. Awareness will also be spread amongst the residents on the following lines:  Timely detection and repair of all leakages;  Turning off tap while brushing teeth;  Avoiding use of running water while hand-washing;  Avoiding use of running water for releasing ice tray ahead of time from freezer;  Turning off the main valve of water while going outdoor;  Avoiding use of hose for washing floors; Use of broom may be preferred;  Watering of lawn or garden during the coolest part of the day (early morning or late evening, hours) when temperature and wind speed are lowest. This reduces losses due to evaporation.  Planting of native and/or drought tolerant grasses, ground covers, shrubs and trees. Once fully grown, they need not to be watered frequently.  Avoiding over watering of lawns. Good rains eliminate the need for watering for more than a week.  Setting sprinklers to water the lawn or garden only, not the street or sidewalk;

M/S DSS BUILDTECH PVT. LTD. 128

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  Avoiding installation or use of ornamental water features unless they recycle the water and avoiding running them during drought or hot weather;  Installation of high-pressure, low-volume nozzles on spray washers;  Replacement of high-volume hoses with high-pressure, low-volume cleaning systems;  Equipping spring loaded shutoff nozzles on hoses;  Installation of float-controlled valve on the make-up line, closing filling line during operation, provision of surge tanks for each system avoid overflow;  Washing vehicles less often, or using commercial car wash that recycles water.

Treatment and Recycling: The wastewater generated from the sites will be treated in on-site Sewage Treatment Plant. This will enable the treated wastewater to be used for flushing and landscaping thereby reducing the requirement of freshwater for these purposes.

Rainwater harvesting: The increased hard surface as a result of the project will increase the runoff as compared to an otherwise barren land. It is proposed to harvest this rainwater runoff that will recharge the groundwater resource while reducing the burden of storm water management of the city and eventually natural water bodies. Apart from the open spaces, it is proposed to harvest the roof top rainwater. The storm water will be treated through an oil and grease trap and allowed to flow through layers of sand and gravel for filtration prior to reaching the water table, to avoid any possibility of groundwater contamination.

Construction materials: The project will require various kinds of natural construction minerals such as sand, gravel etc. It is proposed for prior estimation of required quantities of these materials and procurement only as per requirement. This will also result in cost-efficiency. Excavated soil from the project site will be used within the site to the extent feasible. Excess soil will be made available to the nearby construction sites, as per demand or sold to local vendors. Energy: To conserve the energy resources, good practices will be followed during the construction phase such as turning off lights and equipments when not in use, ensuring fuel efficiency of motors and vehicles through proper maintenance and minimal work at night. The principles of energy conservation will also be embedded in the buildings through use of energy

M/S DSS BUILDTECH PVT. LTD. 129

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA efficient fixtures, maximum availability of natural light and use of solar energy for street lighting.

7.6 RESETTLEMENT AND REHABILITATION The project will not result in displacement of local population and hence does not require a resettlement and rehabilitation study.

7.7 CORPORATE SOCIAL RESPONSIBILITY M/s DSS Buildtech Pvt. Ltd., continues to create world-class infrastructure and realizes its responsibilities as a responsible Corporate and a change agent for accelerating the pace of social and economic transformation across various segments to complement the efforts of government.

M/S DSS BUILDTECH PVT. LTD. 130

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 8: PROJECT BENEFITS

8.1. GENERAL

The Expansion of Group Housing Project “The Melia” is located at Village Mohammadpur Gujjar, Sector-35, Sohna, District- Gurugram, Haryana on land measuring 17.41 acre.

The project offers environment friendly condominiums with amenities such as power backup, food court, convenient shopping, including for economically weaker sections of the society and service units.

8.2. PHYSICAL INFRASTRUCTURE

The project will help in meeting the growing commercial demand for people. It provides state- of-the-art offices and modern terms of comfort and safety of its occupants. Care has been taken to provide the occupants and visitors with necessary facilities as power, water supply, parking spaces, and landscaping, wide internal roads that are safe and secure.

8.3. SOCIAL INFRASTRUCTURE

The project will result in an overall development of the region with construction/maintenance of new/existing roads, power supply and water supply.

8.4. ECONOMIC BENEFITS

The project will have positive impact on the local economy. The construction phase will engage a large number of construction workers including skilled, semi-skilled or unskilled. During Operation phase too, several direct and indirect opportunities will be created which will further stimulating the local economy. Public transport facilities are also likely to improve with the development of the area.

M/S DSS BUILDTECH PVT. LTD. 131

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER 9: ENVIRONMENTAL MANAGEMENT PLAN

9.1 INTRODUCTION Identification and prediction of impacts further needs to suggest the mitigation measures which would play a vital role in prevention of environmental degradation during construction and operational phase of the project. This leads to preparation of Environmental Management Plan (EMP), therefore EMP forms an imperative part of EIA process.

The Environmental Management plan is a site specific plan developed to ensure that the project is implemented in an environmentally sustainable manner where all contractors and subcontractors, including consultants if any, understand the potential environmental risks arising from the project and take appropriate actions to minimize those risks. EMP also ensures that the project implementation is carried out in accordance with the planned design and by taking appropriate mitigates actions to reduce adverse environmental impacts during project’s life cycle. The project is being created certain inevitable impacts, mainly during construction phase, although within permissible limits as mentioned in Chapter 4 and can be reduced significantly with the help of effective implementation of a well-designed EMP. The potential environmental impacts, which need to be regulated, are as mentioned below:

 Air pollution due to the emission of particulate matter and gaseous pollutants from operation of D.G. Sets during power failure and vehicular movement;  Noise pollution due to various noise generating equipment as well as vehicular movement;  Water resource management to ensure continuous water supply.  Wastewater generation from sanitary/domestic activities; and  Generation of municipal solid wastes from residences, maintenance of roads, parks, common areas including constructional, electrical and plumbing wastes.  Energy conservation methods  Maintenance of Building Management Systems and emergency aids.

M/S DSS BUILDTECH PVT. LTD. 132 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA To ensure better environment in & around the project site, effective EMP needs to be developed separately for construction and operational phase.

9.2 ENVIRONMENTAL MANAGEMENT STRATEGIES Strategy for environmental management in construction work is based on three-pronged approach comprising of:  Pollution prevention.  Pollution control.  Protection of pollution recipients.

9.2.1 Topography and Physiography During the development, construction and operation phase of the project, no significant impact is anticipated on local or regional topography and Physiography, hence exhaustive management plan is not required.

9.2.2 Soil Development & Construction Phase During the construction phase, various kinds of wastes are generated that is being disposed in varied ways. The following measures are being taken to prevent soil contamination at site and ensure waste management:

Vegetation and top soil management:  Remove vegetative cover only from the specific area on which construction is being take place.  Plantation as proposed will be started at the earliest.  The top soil has been stripped from constructional areas and stockpiled for later reuse in landscaping.  Promote use of organic fertilizers.  Construction of erosion prevention troughs, as deemed necessary.

M/S DSS BUILDTECH PVT. LTD. 133 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  To prevent the erosion of excavated loose soil produced as a result of excavation, site preparation activities and excavation work would be undertaken during dry season after monsoon is over.

Construction Debris:  Fuel and oil is being stored in cement lined storage yard and handled carefully to prevent soil contamination through leakage or spillage.  All metal, paper, plastic wastes, debris and cuttings have been collected from site as soon as particular construction activity is over.  During construction of flexible pavement, bitumen wastes is being collected (if any) and disposed in environmentally sound manner.  The number, frequency and area of movement of heavy machinery are also restricted.  Recycling of construction wastes into aggregates for use in the project site.  Used oil from DG Sets is being stored in HDPE drums in isolated covered facility and disposed-off as per the Hazardous Wastes (Management & Handling) Rules, and its amendments 2016.  Wastes from the labour camps will be collected and disposed as per the existing practices in the site.

Operation Phase To prevent soil contamination at site, the most important aspect is to manage the solid wastes that will be generated during the operation phase. The Environmental Management Plan for solid waste focuses on three major components during the life cycle of the waste management system i.e. collection, transportation, and treatment or disposal.

Collection and segregation of wastes  Solid waste generated from project would be collected door to door and segregated into decomposable, recyclable and inert wastes.  Decomposable wastes will be decomposed and converted to manure to be used for horticulture.

M/S DSS BUILDTECH PVT. LTD. 134 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA  Recyclable waste would be sold to vendors.  Inert waste which comprises a very small amount of the total solid waste generated would be temporarily stored within the project premises.  Waste bins would be placed at the strategic locations such as inter section of internal roads, parks, common places, etc.  To minimize littering and odors, waste will be stored in well-designed containers/ bins that will be located at strategic locations to minimize disturbance in traffic flow.  Care would be taken such that the collection vehicles are well maintained and generate minimum noise and emissions. During transportation of the waste, vehicle will be covered to avoid littering.

Disposal Non-recyclable and non-biodegradable waste will be disposed through local approved agency. The biodegradable waste will be converted to manure through Organic Waste Converter. SWM Plan for Operation phase is shown below:

Solid Waste

Biodegradable Non-Biodegradable Waste Waste Recyclable Non- Recyclable

Green Blue Bins Dark grey Bins Bins Organic waste Converter Final disposal through a Final disposal through Govt. approved Govt. approved Manure agency to agency

M/S DSS BUILDTECH PVT. LTD. 135 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Figure 9.1 Solid Waste Management Flow Diagram (Operation Phase)

A local vendor will be hired for solid waste management during Operation Phase.

9.2.3 Hydrology Ground Water Development & Construction Phase The water requirement during the construction phase will met from recycled water from STP of HUDA. The following are also proposed to further reduce the demand of water:  Curing water will be sprayed on concrete structures and free flow of water not allowed.  After liberal curing on the first day, all concrete structures will be painted with curing chemical to save water to stop daily water curing hence save water.  Concrete structures are being covered with thick cloth/gunny bags and then water sprayed on them to avoid water rebound and ensure sustained and complete curing.  Pools have been made using cement and sand mortar to avoid water flowing away from the flat surface while curing.  Water ponding has been done on all sunken slabs. This has also highlighted the importance of having an impervious formwork.

Post Construction Phase It is proposed to conserve groundwater resources through the combined means of water resource development, minimized water consumption and reuse of treated sullage to reduce freshwater demand.

Water Resource Development

The storm water collection system for the premises shall be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area

M/S DSS BUILDTECH PVT. LTD. 136 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA and the time required for such flow to reach the drains. The drains shall be located near the carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads shall flow towards the drains. Storm water from various plots/shall be connected to adjacent drain by a pipe through catch basins. Therefore, it has been calculated to provide 18 rainwater harvesting pits at selected locations, which will catch the maximum run- off from the site. 1) Since the existing topography is congenial to surface disposal, a network of storm water pipe drains is planned adjacent to roads. All building roof water will be brought down through rain water pipes. 2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular intervals for rain water harvesting and ground water recharging. 3) For basement parking, the rainwater from ramps will be collected in the basement storm water storage tank. This water will be pumped out to the nearest external storm water drain. 4) The peak hourly rainfall of 45 mm/hr shall be considered for designing the storm water drainage system.

Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak hourly rainfall has been considered as 45 mm/hr. The recharge pit of 5 m diameter and 4 m depth is constructed for recharging the water. Inside the recharge pit, a recharge bore is constructed having adequate diameter and depth. The bottom of the recharge structure will be kept 5 m above this level. At the bottom of the recharge well, a filter media is provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan are as follows:  Catchments/roofs would be accessible for regular cleaning.  The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting has been avoided since most paints contain toxic substances and may peel off.  All gutter ends will be fitted with a wire mesh screen and a first flush device would be installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent

M/S DSS BUILDTECH PVT. LTD. 137 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is flushed off.  No sewage or wastewater would be admitted into the system.  No wastewater from areas likely to have oil, grease, or other pollutants has been connected to the system.

Comparative Rain Water Harvesting Pits Distribution (EC Accorded +Expansion) S. No. Particulars Value as per EC Expansion Total (EC Accorded Accorded +Expansion) 1 Rain Water 17 1 18 Harvesting Pits

Calculations for storm water load:

Net Plot Area = 67,915.15m2

Roof-top area = Ground Coverage = 11,806.21m2 Green Area = 20,494.66 m2

Paved Area = Plot Area – (Roof-top Area + Green Area) = 67,915.15 – (11,806.21 + 20,494.66) = 67,915.15 – 32,300.87 = 35,614.28m2

Roof-top area = 67,915.15 × 0.045 × 0.90 = 2750.56 m3/hr

Green Area = 20,494.66 × 0.045 × 0.20 = 184.45m3/hr

M/S DSS BUILDTECH PVT. LTD. 138 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA Paved Area = 35,614.28 × 0.045 × 0.70 = 1121.84m3/hr

Total Runoff Load = 2750.56 + 184.45 + 1121.84 = 4056.85m3/hr

Taking 20 minutes retention time, volume of storm water = 4056.85/3 = 1352.28 m3 Capacity of Recharge pit = π r2h = 3.14 × 2.5 × 2.5 × 4 = 78.5 m3

Hence No. of pits required = 1352.28/78.5 = 17.22 pits/18 pits

Total of 18 Rain Water Harvesting pits are proposed for artificial ground water recharge.

M/S DSS BUILDTECH PVT. LTD. 139 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Figure 9.2: Rain Water Harvesting Pit Design

M/S DSS BUILDTECH PVT. LTD. 140 EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Storm water management system Since the storm water on site will be harvested for ground water recharge, proper management of this resource is necessary to prevent contamination. Hence, regular inspection and cleaning of storm drains will be carried out. Use of fertilizers and pesticides will be avoided prior to and during monsoons. Clarifiers or oil/ water separators will also be installed.

Minimal Water Consumption To reduce the water consumption, awareness along the following lines will be spread amongst the management and maintenance team:  Installation of water meters conforming to ISO standards at inlet and outlet point of water supply.  To further lower the water consumption, options of Low flow flushing systems, sensor based fixtures, and tap aerators etc. will be explored.  Leak detection  Drip irrigation for shrubs and trees  Use of low-volume, low-angle sprinklers for lawn areas The message of water conservation will be spread amongst the residents through awareness campaigns and pamphlets. Following tips will be provided to the residents for conserving water.  Timely detection and repair of all leakages;  Turning off tap while brushing teeth;  Use of mug rather than running water for shaving;  Avoiding/minimizing use of shower/bath tub in bathroom;  Turning off faucets while soaping and rinsing clothes;  Using automatic washing machine only when it is fully loaded;  Avoiding use of running water while hand-washing;  Avoiding use of running water for releasing ice tray ahead of time from freezer;  Turning off the main valve of water while going outdoor;  Avoiding use of hose for washing floors; Use of broom may be preferred;  Watering of lawn or garden during the coolest part of the day (early morning or late evening, hours) when temperature and wind speed are lowest. This reduces losses due to evaporation.

M/S DSS BUILDTECH PVT. LTD. 145

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Planting of native and/or drought tolerant grasses, ground covers, shrubs and trees. Once fully grown, they need not to be watered frequently.  Avoiding over watering of lawns. Good rains eliminate the need for watering for more than a week.  Setting sprinklers to water the lawn or garden only, not the street or sidewalk;  Avoiding installation or use of ornamental water features unless they recycle the water and avoiding running them during drought or hot weather;  Installation of high-pressure, low-volume nozzles on spray washers;  Replacement of high-volume hoses with high-pressure, low-volume cleaning systems;  Equipping spring loaded shutoff nozzles on hoses;  Installation of float-controlled valve on the make-up line, closing filling line during operation, provision of surge tanks for each system avoid overflow;  Washing vehicles less often, or using commercial car wash that recycles water.

Re-use of treated effluent It is expected that the project will generate approx. 418 KLD of wastewater. The wastewater will be treated in onsite STP of 505 KL capacity. The treated effluent will be reused for flushing & horticulture. Surplus treated effluent will be discharged to external sewer.

 10% of the waste water that is to be treated is removed from the STP in form of sludge as well as vapors.

 Out of this 10%, approx. 98% of the untreated waste water is removed as wet sludge, which is then dewatered by passing through a filter press and extracted water is added back to the collection chamber of the STP. Somewhat around 40% of the moisture of the sludge is retained, and the sludge thus generated is further processed by drying the same on a non- permeable bed, which upon drying can be used as manure in the green area provided within the project site. The wet sludge is generally removed during the processes of primary treatment, secondary treatment and tertiary treatment or scrubbed off of the collection tank.

M/S DSS BUILDTECH PVT. LTD. 146

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

 Remaining 2% of waste water is evaporated from the system during treatment process and thus cannot be converted into sewage.

Ground water Quality Development and Construction Phase To ensure against any groundwater pollution through leaching of soil, solid waste management plan ensuring timely collection of wastes is being followed. The collected wastes is being stored at designated area and disposed as per the standard procedures in line with the statutory requirement.

Post Construction Phase The ground water pollution can arise from improper waste handling or by recharge of groundwater through contaminated storm water. A well planned solid waste management as discussed in Chapter 2 is proposed for the operation phase that will ensure against any chances of soil or groundwater pollution on this account. Storm water collects dirt and garbage along its flow. Contamination of this water with spilled oil/ grease is especially of concern when recharging is proposed. Hence, preliminary treatment for oil and grease and filtration through layers of sand and gravel is proposed prior to recharge of the groundwater. Landscaping water enters the soil and finally the groundwater. It is thus of utmost importance that only clean water is used for horticulture purposes. The water from the households will contain significant amounts of detergent and soap that is undesirable for plants, soil and in groundwater. Hence, it is proposed to treat the waste water from the site up to tertiary level, and be used for flushing, landscaping, etc. Regular monitoring of treated effluent will be carried out to ensure that all parameters are within acceptable limit.

9.2.4 Air Quality Development and Construction Phase The construction phase of the project will last for about 3-4 years, causing marginal impact on ambient air quality from constructional activities, unloading of construction materials, cement, soil and vehicular movement etc. The main pollutant of concern is

M/S DSS BUILDTECH PVT. LTD. 147

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

PM 2.5 & PM10 (dust). Likewise, following mitigation measures is being adopted during this phase to mitigate the impacts on ambient air:  Installation of batch plant at isolated place and providing cover shed around plants.  Loading and unloading of cement and other material in covered shed.  Providing dust suppression system in unloading area (as per requirement).  Developing avenue and curtain plantation on the internal roads and peripheral plantation around the site to protect the movement of dust and other pollutants.  Cover scaffolding, hosing down road surfaces and cleaning of vehicles.  On-Road- Inspection for black smoke generating machinery.  Vehicles having pollution under control certificate is allowed to ply.  Use of covering sheets for trucks to prevent dust dispersion from the trucks.  Reducing the speed of a vehicle to 20 km/hr to reduce emissions on site.  All material storages is adequately covered and contained.  Training to the workers to reduce idling time of machines that otherwise tends to produce hydrocarbons and carbon monoxide.  Best practices for maintenance and repair of all machineries and equipment. Operation Phase During the operation phase, following measures will be adopted for air pollution control:  Adequate stack height for DG sets  Low sulphur diesel based DG sets  Traffic management to avoid congestion  Green belt plantation

DG Set: The running of DG sets will result in emission of various pollutants. To achieve adequate natural dispersion, adequate stack height will be provided as per guidelines of Central Pollution Control Board (CPCB).

Traffic management: Internal roads would be maintained in good conditions to control the dust emissions and adequate width will be provided to avoid traffic congestion.

M/S DSS BUILDTECH PVT. LTD. 148

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Plantation development: Plantation is an effective means for controlling air pollution due to its dual action of acting as a barrier between the source of emission and receptors and also as a sink for various pollutants. It is proposed to develop the green area species effective in absorption of expected pollutants at site, along the internal roads and on the periphery of the project. Suggested species for plantation are:  Cassia fistula (Amaltas)  Delonixregia (Gulmohar)  Bauhinia variegata(Kachnar)  Thevetiaperuviana (Kaner)  Dalbergiasissoo(Shisham)

9.2.5 Noise Levels Development and Construction Phase During the construction phase, some noise is being generated through the operation of construction machines, excavators, DG set, etc. Following measures would be taken; into consideration to mitigate the noise at construction site:  Use of well-maintained equipment fitted with silencers and providing noise shields near the heavy construction operations  Acoustic enclosures would be provide to DG sets at the construction site,  Earmuff and other protection devices will be provided to laborers working in high noise generating machines.  High noise activities will be carried out during daytime. Operation Phase The main sources of noise during this phase are the intermittent use of DG Sets and traffic. The principles of noise emission control and screening are proposed for the two different scenarios of noise generation.

Noise emission control All the D.G. Sets will be provided with acoustic enclosures ensuring 25 dB (A) insertion loss or for meeting the ambient noise standards whichever is higher as per CPCB norms. It will be

M/S DSS BUILDTECH PVT. LTD. 149

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA ensured that the manufacturer provides acoustic enclosures as an integral part with Diesel Generator Sets.

Barriers Trees having thick and fleshy leaves with flexible petioles having capacity to withstand vibration are suitable. Heavier branches and trunk of the trees also deflect or refract the sound waves. The following species are proposed to be used in a greenbelt especially surrounding plotted colony and along the periphery of the project.  Antocephalouscadamba (Kadam)  Polyathialongifolia (Ashok)  Terminaliaarjuna (Arjun)

9.2.6 Biological Environment

Development and construction phase During the development, construction and operation phase, no tree has been cut and therefore no impact is anticipated on terrestrial ecology. Site clearing has been carried out strictly as per plan. Workers have advised against cutting, uprooting, coppicing of trees or small trees present in and around the project site for cooking. Workers have also been discouraged from wandering in nearby areas with plantation or dense vegetation.

Further, green belt has been developed on the periphery and along the internal roads of project site during the construction phase itself that will act as a curtain to restrict the movement of pollutants from either side of the project and improve site aesthetics.

Operation phase During the operation phase, green belt will be developed and maintained. Ornamental plant species and grasses will be planted in open space within the premises. 20,494.66 m2 i.e. 30.17% is proposed to be maintained as green within the project site.

M/S DSS BUILDTECH PVT. LTD. 150

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

9.2.7 Demographic and Socio-Economic Environment Development and Construction Phase During the development and construction phase of the project, more than 800-850skilled, semiskilled and unskilled workers got direct and indirect employment opportunities which have beneficial impact on the socio-economic condition of the area.

Following suggestions are given to strengthen the beneficial impacts on the socio-economic environment.

 All the applicable guidelines under relevant acts and rules related to labor welfare and safety is being implemented during the construction work activities.  Proper sanitary and drinking water facilities have been provided to workers living in the construction camps within the project premises.  Workers have been provided with appropriate PPEs during work.  Guarding of dangerous machine parts, maintenance of equipment’s as hoists and lifts is being ensured  Adequate provision of different types of fire extinguishers has been made.  Construction Camps has been provided with clean and safe drinking water and toilet facilities. Domestic refuse generated at the construction camps is being disposed off on a regular basis. First Aid Medical facilities have been proposed for the construction workers.

Operation Phase The project envisages addressing the wider goal of environmental protection through a social investment strategy for the communities around the project. The project seeks to increase the benefits to the local population and contribute towards meeting community’s expectation of benefits from the project.

Some of the concerns raised by local people relate directly to the project. Concerns and aspirations not directly related to the project were also solicited so as to identify areas that could be addressed through socially responsible initiatives and interventions. These were: a) Demand for employment opportunities.

M/S DSS BUILDTECH PVT. LTD. 151

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA b) Infrastructure development The proposed strategy envisages addressing the wider goal of sharing benefits with the local community. The following activities would be undertaken.

Income Generation Opportunity for local community The local people will be given preference, although they will be recruited on their individual merit. Tender specification for operation services will include favorable employment opportunities towards the local population. The main principles of employment are outlined below:  Employment strategy will provide for preferential employment during operation phase.  General recruitment procedures will be transparent, public and open to all.  Recruitment procedures will be publicized at locally prominent locations in advance.  There will be no discrimination on basis of gender, caste or other factors.  Contractors would be required to abide by the Indian labour laws regarding standards on employee working conditions, minimum wages for workers, safety and welfare measures. Following the appointment of the contractor, information on employment will be available to the local community at the Panchayat office or other prominent places like the school, frequently visited spots in the village etc. Information on the following aspects would be provided- scale and duration of employment, type of available work and demand projection.

Improved working conditions The project would provide safe working conditions for the labor and other workers employed at the facility during construction and operation phase. Conditions of employment would address issues like minimum wages, medical care, etc.

9.2.8 Vehicle Parking and Traffic Management Adequate provision will be made for car/vehicle parking at the project site. There will also be adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement at the site.

M/S DSS BUILDTECH PVT. LTD. 152

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

9.2.9 Energy Conservation The Project will be designed in such a way that natural light is maximized indoor. The project will be energy efficient through use of low energy consuming fixtures. Energy conservation will be achieved through various means as given below.

Site Plan and building design  Maximum utilization of solar light will be done  Public areas will be cooled by natural ventilation as opposed to air-conditioning  Maximize the use of natural lighting through design  The orientation of the buildings will be done in such a way that maximum daylight is available  The water bodies and green areas will be spaced, so that a significant reduction in the temperature can take place.

Energy saving  Energy efficient lamps will be provided within the complex.  Constant monitoring of energy consumption and defining targets for energy conservation  Adjusting the settings and illumination levels to ensure minimum energy used for desired comfort levels Awareness  Promoting resident awareness on energy conservation  Training staff on methods of energy conservation and to be vigilant to such opportunities

9.2.10 Management and Maintenance System Management and maintenance is an important issue for the project. During the construction phase the project proponent will take care of the implementation of environmental management plan. They will review the effectiveness of implemented mitigation measures adopted by contractors and sub-contractors from time to time. The buildings will be provided with water sprinklers and fire alarms and there will be provision of adequate number of fire extinguishers

M/S DSS BUILDTECH PVT. LTD. 153

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA as per NBC norms. Power back up service will be provided for all emergency equipment and machineries. Operation, management and maintenance of the internal services laid inside the project will be done by the project proponent.

Institutional Capacity Building a. Reporting: For effective implementation of any system/ plan, a systematic reporting system is essential. An Environmental Management Cell will be set up for implementation of the proposed Management Plan. Reporting of the results of all the management and monitoring plan will be submitted to the designated Project Head. The reports will be reviewed and parameters exceeding their limits should be identified and the reason for the same investigated. Any requisite mitigation plan will be taken up accordingly. The Environment Management Cell will be a permanent organizational set up charged with the task of ensuring its effective implementation of mitigation measures and conduct environmental monitoring. The major duties and responsibilities of Environmental Management Cell will be as given below:  To implement the environmental management plan  To assure regulatory compliance with all relevant rules and regulations  To ensure regular operation and maintenance of pollution control devices  To minimize environmental impact of operations as by strict adherence to the EMP  To initiate environmental monitoring as per approved schedule b. Review and interpretation of monitored results and corrective measures in case monitored results are above the specified limit. c. Maintain documentation of good environmental practices and applicable environmental laws for a ready reference d. Maintain environmental related record e. Coordination with regulatory agencies, external consultants, laboratories, etc.

M/S DSS BUILDTECH PVT. LTD. 154

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA f. Maintenance of log of public complaints and the action taken.

Hierarchical Structure of Environmental Management Cell EMP cell would be supervised by the Project Head.

Awareness and Training Training and human resource development is an important link to achieve sustainable operation of the facility and environment management. For successful functioning of the project, relevant EMP would be communicated to residents and contractors.

Occupants must be made aware of the importance of waste segregation and disposal, water and energy conservation. The awareness can be provided by periodic Integrated Society meetings. They would be informed of their duties.

9.3 OVERALL MITIGATION MEASURES AND ENVIRONMENTAL MANAGEMENT PLAN Overall impact assessment of anticipated environmental impacts and mitigation measures & environmental management plan to mitigate the potential impacts during the development & construction and operation phase are summarized in Table 9.1.

M/S DSS BUILDTECH PVT. LTD. 155

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Table 9.1: Environmental Management Plan during Construction and Operation phase of the Project

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures 1. Groundwater Ground water Construction Phase Quality contamination . Wastewater 1. Mobile type toilets No significant generated from Labor will be provided impact as majority tents. of laborers would be locally deployed. Operation Phase . Wastewater  Waste water will be No significant In an unlikely event treatment, sludge treated in onsite negative impact on of soil and ground disposal on land. Sewage Treatment ground water water Plant. Sludge will be quality envisaged. contamination, used for horticultural remediation purpose as manure. measures will be implemented. 2. Groundwater Ground Water Construction Phase Quantity Depletion . Ground water will  Not Applicable Not Applicable not be used for construction activity.

M/S DSS BUILDTECH PVT. LTD. 156

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures Operation Phase . Water will be  Recycling of treated No significant supplied by HUDA. effluent from STP to impact on ground reduce freshwater water quantity requirement envisaged.  Storm water collection for Water Harvesting.  Awareness Campaign for reduced water use by occupants. 4. Air Quality Dust Construction Phase Emissions . All heavy  Dust suppression Not significant construction through water because dust activities. sprinkling using water generation will be trucks, handheld sprays temporary and will and automatic sprinkler settle fast due to systems. dust suppression  Vehicles techniques used. transporting loose construction material should be covered.  Contractors will be advised to provide dust masks for the employed labor.

M/S DSS BUILDTECH PVT. LTD. 157

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures Emissions of Construction Phase PM, SO2, NO2 . Operation of  Rapid on site Not significant Regular monitoring and CO construction construction of emissions and equipment and  Improved control measures to vehicles during site maintenance of reduce the emission development. equipment. levels.

Operation Phase . Power back-up  Use of low Sulphur Not significant as through D.G. Set diesel. D.G. Set would be  Stack will be used for power provided with adequate back-up only. height as per CPCB guideline. . Emissions from vehicular traffic. . Green belt to be provided with specified species to help reduce PM level.

M/S DSS BUILDTECH PVT. LTD. 158

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures 5. Noise Noise Construction Phase  Equipment should be Environment emissions fitted with silencers, . Operation of where applicable and construction maintained well. equipment and  Providing noise vehicles during site shields near heavy development. construction operations.  Construction activity will be limited mostly to daytime hours only.  Use of Personal Protective Equipment (PPE) like earmuffs and earplugs during construction activities. Operation Phase . Noise from  Peripheral Not significant vehicular movement. plantations.

. Noise from D.G.  Providing Acoustic Short-term sets operation. Enclosures on D.G. exposure within Sets. permissible limit.

M/S DSS BUILDTECH PVT. LTD. 159

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures 6. Land Soil Construction Phase Environment contamination . Disposal of  Construction debris Impact will be construction debris. will be collected and local, as any waste suitably used on site as generated will be per construction waste reused for management plan. construction activities. Not significant. Operation Phase  Solid waste from site . Dumping of will be collected on a Not Significant municipal solid waste daily basis and on land. disposed as municipal . Dumping of wastes. The hazardous solid waste segregation, on land. transportation and disposal of waste will . Handling of used be handled by a local Negligible impact oil from D.G. Sets. approved vendor.  Used oil generated will be managed through authorized recyclers.

7. Biological Removal of Construction Phase Environment Flora and . Site development  The site comprises No negative impact -- (Flora and Fauna on site. during construction. of fallow land.

M/S DSS BUILDTECH PVT. LTD. 160

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures Fauna) Operation Phase . Plantation along  Plantation of species Beneficial impact Increase of the periphery of the that is native to the Green Cover project. area, fast growing and with good canopy cover. 8. Socio -Economic Population Construction Phase Environment displacement . No relocation is  Employment No negative impact -- and economic involved. opportunities. impact Beneficial impact . Constructional activities Operation Phase -- . Site operation.  Project will provide Beneficial impact employment opportunities.  Boost to local market for increased demand in goods of daily need.

M/S DSS BUILDTECH PVT. LTD. 161

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

S. Environmental Potential Potential source of Controls through Impact Evaluation Remedial No. Components Impacts Impact EMP & Design Measures 9. Traffic Pattern Increase of Construction Phase Vehicular . Heavy vehicular  Heavy vehicular No negative impact traffic movement during movement will be construction. restricted to daytime only and adequate parking facility will be provided. Operation Phase . Increased traffic  Vehicular movement No significant from the project. will be regulated inside impact the project site

 Adequate parking space provided within the complex.

M/S DSS BUILDTECH PVT. LTD. 162

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

CHAPTER 10: SUMMARY AND CONCLUSION

10.1 PROJECT BACKGROUND Expansion of Group Housing Project “The Melia” is spread over an area of 70,455.77 m2 (17.41 acres). The estimated Built-up area (post expansion) is 1, 57,562.486 sqm. Total green area measures 20,494.66 m2 (25%).

As per EIA Notification, 2006 and amendments thereto, all building and construction projects covering an area of 50 ha and/ or built up area greater than 1, 50,000 m2 are designated as 8(b) and are required to obtain prior environmental clearance from respective State Environmental Impact Assessment Authority (SEIAA).

The EIA/EMP report for the project has been prepared based on ToR conditions conveyed by the State Environment Impact Assessment Authority, Haryana vide letter no. SEIAA/HR/2016/807 dated 20/09/2016.

The EIA is conducted to establish the baseline environmental setting in the study area, assessment of potential impacts on different environmental components, design of mitigation measures so as to keep impacts within acceptable limits and strengthen the positive impacts.

The summary highlights the baseline environmental status, key environmental issues and their likely impacts and also lists the major recommended mitigation measures to attenuate the impacts. It describes the findings of the EIA study to aid in decision making and provides project related information and environmental impacts.

10.2 PROJECT SITE AND SALIENT FEATURES

The area has good infrastructure facilities. The Nearest Highway is SH-8 which is 0.60 km (E) away from project site. The nearest Railway Station being Garhi Harsaru Railway Station is

M/S DSS BUILDTECH PVT. LTD. 163

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA about 21.80km (NW) away from the project site. The nearest Airport is Indira Gandhi International Airport at 29 km (N) from project site.

Table 5.1: Salient Features of the Project

Feature Detail Project name Expansion of Group Housing Project “The Melia” Location Village Mohammadpur Gujjar, Sector-35, Sohna, District- Gurugram, Haryana Type of project 8 (b), Category B Plot area Plot Area = 70,455.77m2 Built-up area 1,57,562.486m2 Ground coverage 11,806.21m2 Parking facilities 1760 ECS Power requirement 6063 KW from Dakshin Haryana Bijli Vitaran Nigam & source (DHBVN) Power backup 2 no. of D.G sets of total capacity 1635 kVA kVA (1 x 1010 kVA & 1 x 625 kVA) Water requirement Fresh water: 415 KLD (from HUDA) & source Waste water generated : 418 KLD Total water requirement:707 KLD Sewage treatment & Sewage treatment facility: 1onsite STPs of 505 KLD each. disposal Solid wastes 3,537.876 kg/day generation Estimated 8914 population Green-area 20,494.66 m2 (25% of plot area)

M/S DSS BUILDTECH PVT. LTD. 164

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

10.20 ENVIRONMENTAL SETTING OF THE STUDY AREA The baseline environmental status was assessed based on primary and secondary data collected either through in-site field observation or obtained from agencies such as Irrigation Department, India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of India, State Ground Water Department, State Pollution Control Board, Census of India and Local Forest Department, Non -Governmental Agencies. The baseline status established from analysis of secondary and primary data and predicted impacts and management plan are discussed below.

10.2.1 Land Environment The site falls under residential land use as per the development plan by Gurgaon Master Plan, 2031. The construction phase of a project may pose threat of soil contamination and soil erosion. Inadequate solid waste management may also cause soil contamination during operation phase.

During construction phase, excavation related work avoided during the monsoons and site clearing is being carried out for specific areas being developed. Recyclable and non-recyclable wastes are disposed through a local approved agency. Municipal Solid Waste Management is proposed as per Municipal Solid Wastes (Management and Handling) Rules, 2016.

10.2.2 Water environment The water requirement during construction phase will be met from STP treated water of HUDA. A combination of efficient water management to reduce water consumption, reuse of treated wastewater to reduce freshwater demand and rainwater harvesting to replenish groundwater is proposed to have a positive bearing on the water environment of the region.

The wastewater will be treated in 1 onsite STPs of Total 875 KL capacity generating 376 KLD of treated effluent for reuse in flushing, horticulture and HVAC cooling.

M/S DSS BUILDTECH PVT. LTD. 165

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

10.2.3 Air Environment During construction phase, the major air pollutant is particulate matter as impacts of other emissions such as SO2, NO2, and CO is not be significant.

Monitored average PM2.5, PM10 level not exceeded NAAQS at all the ten locations. The levels of

PM2.5, PM10, NO2, SO2 and CO at all the five locations were within the standards prescribed by NAAQS at all the five locations. Thus dust emissions from construction activities will require comprehensive mitigation measures and best construction practices. Adequate stack heights have been proposed for D.G. sets i.e. 6 m above the rooftop to provide sufficient dispersion of pollutants. Water sprinklers will be used to suppress dust during construction. During the operation phase, green belt is proposed to restrict and absorb air pollutants.

10.2.4 Noise Environment Noise levels were observed at four locations within the study area. Levels of background noise monitored in exceed the limit at 55 dB (A) and 45 dB (A) for daytime and night time respectively. The noise emitted from heavy-duty construction equipment’s during construction period being high will require occupational preventive measures and temporary noise barriers for noise attenuation. The construction period being about three to four year duration, will require significant mitigation measures such as restricted loud noise activities to daytime and provision of PPEs In the operation phase, noise pollution will be checked through acoustic enclosures of DG Sets and green belt plantation.

10.2.5 Biological environment The landscape area will be developed with native species that will attract local birds and insects, reduce pollution and improve aesthetics and micro-climate of the region. Total green area measures 20,494.66 m2 (30.17 % of plot area) which include area under tree plantation and lawn.

M/S DSS BUILDTECH PVT. LTD. 166

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Evergreen tall and ornamental trees like Acacia auriculiformis, Acacia delbata, Aegle marmelos, Adina cordifolia and ornamental shrubs like Bambusa arundinacia, Bambusa vulgaris have been proposed to be planted inside the premises.

10.2.6 Socio-economic environment The Expansion of Group Housing Project “The Melia” does not call for change in the existing land use pattern. The project will generate employment opportunities for both skilled and unskilled workers which will have a multiplying positive effect on the life and economy of the local population. Thus from socio-economic point of view the project is beneficial to the people.

10.2.7 Energy efficiency Please refer Environment Management Plan for details.

10.2.8 Other Resource Conservation: A concerted effort is made towards resource conservation by way of using recycled building materials, fly-ash bricks, reduced water consumption and improving energy efficiency of the building.

Indoor Air Quality: Special attention is being given to maintaining indoor air quality through use of low VOC paints, provision of adequate ventilation, proper storage of chemical and cleaning materials.

Safety: A network of manned security gates, security men, closed circuit TV and intercom facilities are proposed to ensure safety of the occupant. The buildings will also be provided with adequate fire tenders, fire alarms and water sprinklers as per norms.

M/S DSS BUILDTECH PVT. LTD. 167

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

10.3 ENVIRONMENTAL MANAGEMENT PLAN Adequate environmental management measures will be incorporated during the entire planning, construction and operating stages of the project to minimize any adverse environmental impact and assure sustainable development of the area.

For the effective and consistent functioning of the campus, an Environmental Management System (EMS) will be established at the site including an Environmental Management cell for implementation of the EMP and monitoring plan, training and awareness, audits and maintenance of records. The total estimated cost of Expansion of Group Housing Project “The Melia” is INR 430 Crore which includes the cost of land as well as development.

Based on the environmental assessment, the associated potential adverse environmental impacts can be mitigated to an acceptable level by adequate implementation of the measures as stated in the EIA and the EMP. Some of the environment friendly features of the project are:  Use of solar energy for street lighting  Provision of green walls and green terraces  Use of CLC blocks (containing approx. 33% fly ash)  Use of steel manufactured from recycled content.  Provide permeable paving to control surface water runoff  Rainwater harvesting  Meet all requirements for buildings in moderate earthquake prone areas.  Provision of fire alarms and water sprinklers.  Provision of welfare schemes to workers.  Extending educational and healthcare facilities to the local people.  Commitment to engaging local population for job opportunities.

M/S DSS BUILDTECH PVT. LTD. 168

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

Hence, it may be concluded that the project will have significant positive socio-economic impact on the local community apart from meeting the housing needs of the society, without bearing any significant adverse environmental impact.

M/S DSS BUILDTECH PVT. LTD. 169

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER-11 DISCLOSURE OF CONSULTANTS ENGAGED

Project Name: Expansion of Group Housing Project “The Melia” Name and address of GRC India (P) Ltd. ISO 9001:2008 Certified, the Consultant F-374,375, Sector: 63, QCI-NABET Accredited. Noida, India Technical Members Ms. Kavita Chopra(FAA) Involved Mr. Saurabh Gola (Member) Base line data GRC India Training and Recognized by MoEF&CC, GoI & Analytical Laboratory Accredited by NABL. F- 375, Sector: 63, A unit of GRC India (P) Ltd. Noida, India

Under the guidance of following EIA Coordinator & Functional Area Experts: EIA Coordinator Mr. Rajesh Bhaskaran FAE- AP Dr. Dhiraj Kr. Singh FAE- WP Dr. Dhiraj Kr. Singh FAE- SHW Dr. Dhiraj Kr. Singh FAE- SE Mr. B N Chaudhari FAE - LU Mr. B N Chaudhari FAE- EB Dr. Dhiraj Kr. Singh FAE- AQ Ms. Mudita Tomar Singh FAE- GEO Prof. Tapan Majumder/Shahbaz Malik FAE- HG Prof. Tapan Majumder FAE - NV Mr. Sanjay Singh FAE- RH Dr. Ravindra Kode

M/S DSS BUILDTECH PVT. LTD. 170

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

11.1 ACCREDITION/ FROM QUALITY COUNCIL OF INDIA, QCI AND LIST OF COORDINATORS Grass Roots Research & Creation India (P) Ltd., Noida is an EIA Consultant organization accredited by Quality Council of India, NABET. GRC India is accredited vide NABET Certificate No. – NABET/EIA/1619/RA 0064 and validity of accreditation is till Dec., 12. 2019. Certificate of Accreditation is attached for reference.

M/S DSS BUILDTECH PVT. LTD. 171

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

As per the recently published QCI NABET ‘List of Accredited Consultant Organizations/Rev. 67/July 09, 2018’, listed in as accredited consultant, Category ‘A’ Sl. No. 77. The list of accredited consultants is published on QCI NABET and MoEF&CC websites as well.

For reference, a snapshot of the list where GRC India’s name is listed is pasted below:

M/S DSS BUILDTECH PVT. LTD. 172

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

M/S DSS BUILDTECH PVT. LTD. 173

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA CHAPTER-12 CORPORATE ENVIRONMENTAL RESPONSIBILITY

12.1 PROCEDURE FOR ENVIRONMENTAL COMPLIANCE M/s DSS Buildtech Pvt. Ltd has a standard operating procedure to identify and bring into focus any infringement/ deviation/ violation of the environmental/ forest norms and conditions to its management. The applicable regulations are given in the Table 12.1 below:

Table 12.1 Applicable regulatory Framework

S. No. Environmental Acts & Rules Compliance 1 The Environment (Protection)  Obtaining Environmental Clearance (EC) Act, 1986 and EIA Notification from State Environment Impact dated 14.09.2006 Assessment Authority (SEIAA), Haryana for modification of the project.  Submission of Six-monthly Report of Compliance of Stipulated EC Conditions to Regional office of MoEFCC/SEIAA/other authority as mentioned in EC order- Twice a year: 1st June and 1st December.  Submission of Environmental Statement (ES) in Form-V to State Pollution Control Board (SPCB) - Once in a year by 30th September. 2 The Environment (Protection)  Monitoring of stack emission and Rules, 1986 compliance to Emission Limits for DG sets  Monitoring of STP effluent and compliance to Standards for Discharge of Effluents  Monitoring of air quality and compliance to National Ambient Air Quality Standards  Monitoring of DG noise level and compliance to Noise limits for DG sets 3 The Water (Prevention &  Obtaining Consent to Establish (NOC) Control of Pollution) Act, 1974, from HSPCB before establishing the and The Air (Prevention & project Control of Pollution) Act, 1981  Obtaining Consent to Operate (CTO) from HSPCB and its periodic renewal.

M/S DSS BUILDTECH PVT. LTD. 174

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA S. No. Environmental Acts & Rules Compliance 4 Noise Pollution (Regulation  Monitoring of ambient noise quality and and Control) Rules, 2000 compliance to Ambient Noise Standards 5 Hazardous Wastes  Obtaining Authorization for storage & (Management, Handling & disposal of hazardous waste (in Form-1) Transboundary Movement) from SPCB and its periodic renewal Rules, 2008 and its amendment  Submission of Annual Return for hazardous waste (in Form-4) to HSPCB- Once in a year by 30th June  Disposal of hazardous waste to authorized recycler (once in every three months)  Maintaining records of disposal and transportation 6 Water (Prevention and Control  Submission Monthly Returns for Water of Pollution) Cess Act, 1977 Cess (Form-1) to HSPCB for extraction and Water (Prevention and of groundwater- Once a month before 5th Control of Pollution) Cess of current calendar month Rules, 1978  Payment of Cess- when claimed by SPCB 7 Municipal Solid Wastes  Segregation of solid waste into (Management and Handling) biodegradable and non-biodegradable and Rules, 2016 storage into separate color bins.  Disposal of waste through authorized local vendors.

12.2 Proposed Organizational Structure for Environmental Compliance

M/s DSS Buildtech Pvt Ltd. has an an in-house team for ensuring compliance with the conditions of Environmental Clearance letter. The proposed organization structure for Environmental Compliance is shown in following chart at Figure 12.1:

M/S DSS BUILDTECH PVT. LTD. 175

EXPANSION OF GROUP HOUSING PROJECT “THE MELIA” AT VILLAGE MOHAMMADPUR GUJJAR, SECTOR-35, EIA/EMP REPORT SOHNA, DISTRICT GURUGRAM, HARYANA

MD

Executive Director Executive Director

General Manager

Finance Head Legal Advisor IT Head Project Manager

Customer Care Head

Figure 12.1: Proposed Organizational Structure for Environmental Compliance

M/S DSS BUILDTECH PVT. LTD. 176