<<

Vs 70

h L UC L R C H EUROPEAN ORGANIZATION

FOR NUCLEAR RESEARCH

ANNUAL REPORT 1975

CERN The following Report is published in accordance with the provisions of article V, 2(f) of the Convention for the establishment of a European Organtation for Nuclear Research. It gives an account ofCERN's activities in 1975.

Twenty-first Annual Report of the European Organization for Nuclear Research, Geneva o Copyright 1976, CERN ISSN 0304-290I Foreword

The year 1975 has been an exciting and encouraging year for high-energy physics. Evidence is growing that the dream "charm" is not an empty one, and it is with im­ patience that we are waiting now for the experiments with the SPS to begin. Therefore, we are particularly glad that 1975, despite some temporary set-backs, has been another year of great progress for the 300 GeV Programme, and the new machine is nearing completion. But 1975 has been also a difficult year which, in a certain sense, marked a turning-point for CERN. Up to now our Member States have been able to acknowledge the successful work of CERN by approving rapidly growing budgets. 1975 put an end to this development Our Member States were, for the first time, forced to cut budgets and to ask the Directors-General to prepare long-term programmes consistent with budget reduc­ tions. The change from a positive to a negative'growth, to use the jargon of present day economists, raises many problems in a laboratory such as CERN. The spectrum of experimental possibilities and personnel expenditure will have to be reduced and this will unavoidably affect the chances of new discoveries. These reductions can only be accomplished without damaging CERN if the staff is willing to collaborate. I am confident that this will be the case and the responsible way in which the Staff Association reacted when faced with the budgetary problems this year seems to prove that I am right. This year was further marked by the end of Professor W. Jentschke's term as Director- General of CERN Laboratory I. Willibald Jentschke has been a Director-General full of enthusiasm for physics: during his term of office and with his active participation, CERN has experienced a particularly fruitful and fascinating time with the discovery of the neutral current interactions in the Gargamelle heavy liquid bubble chamber. . In deciding to appoint Dr J.B. Adams Executive Director-General and Professor 1_ Van Hove Research Director-General of a unified Laboratory, the Council entrusted the future of CERN to two personalities who are well known to all of us. I am convinced that they will steer CERN safely through the difficult times which lie ahead of us and that, during their joint directorship, CERN will be able to confirm its position as one of the leading high-energy physics laboratories.

P. LEVAUX President of the Council

3 Contents

Page

HISTORY 5

COUNCIL ORGANIGRAM 7

LABORATORY I: BASIC AND 1SR PROGRAMMES 9

INTERNAL ORGANIZATION OF LABORATORY I 10

INTRODUCTION BY THE DIRECTOR-GENERAL OF LABORATORY 1 11

PHYSICS 1 DEPARTMENT 33 Division (NP) 35 Synchro- Machine Division (MSC) 53

PHYSICS II DEPARTMENT 59 Track Chambers Division (TC) 61

THEORETICAL PHYSICS DEPARTMENT 81 Theoretical Studies Division (TH) 83

PROTON SYNCHROTRON DEPARTMENT 85 Proton Synchrotron Machine Division (MPS) 87

APPLIED PHYSICS DEPARTMENT 101 Data Handling Division (DD) 103

1SR DEPARTMENT 109 Intersecting Storage Rings Division(ISR) Ill

ADMINISTRATION DEPARTMENT 127 Finance Division (FI) 129 Personnel Division (PE) 140 TechnJ-al Services and Buildings Division (SB) 145 Health and Safety Division (HS) 152 Central Services (CS) 157

LABORATORY 11: 300 GeV ACCELERATOR PROGRAMME 159

INTERNAL ORGANIZATION OF LABORATORY II 161

INTRODUCTION BY THE DIRECTOR-GENERAL OF LABORATORY 11 162

300 GeV ACCELERATOR PROGRAMME 165 APPENDIX A: CERN publications 199 APPENDIX B: Lectures and seminars 227 APPENDIX C: Training programmes 231 APPENDIX D: Scientific conferences and schools 235

4 History

... The Organization shall provide for collaboration among European States in nuclear research of a pure scientific and fundamental character, anil in research essentially related thereto. The Organiza­ tion shall have no concern with work for military requirements und the results of its experimental ami theoretical work shall be pub­ lished... Extract from the Convention for the establishment of a European Organization for Nuclear Research. Article II — Purposes.

By the late 1940s, nuclear physicists in Europe had realized that further advances in pure research on a par with those taking place in the United States could only come through the construction of particle accelerators of a size and cost beyond the means of individual nations. Under the stimulus of a number of leading scientists, UNESCO sponsored an intergovernmental meeting in December 1951 to consider the practicability of a joint European nuclear laboratory. At a second meeting in February 1952, eleven "nations signed the Agreement which established an interim body which was to he known as the "Conseil européen pour la recherche nucléaire". So the acronym CERN came into being and has remained ever since the name by which the Organization is best known. Over the next twelve months, the structure and programme of the permanent organization was worked out, and between July and December 1953, the. Convention was signed by twelve States which established the European Organization for Nuclear Research. The founding States were Belgium, Denmark, France, the Federal Republic of , Greece, Italy, the Nether­ lands, Nonvay. Sweden, Switzerland, the United Kingdom and -Yugoslavia. With the entry into force of the Convention on 29 September 1954, the new CERN formally came into being. Subsequently, Austria joined the Organization in July 1959 but, at the end of 1961, Yugoslavia had to withdraw for financial reasons. Turkey became an observer State in June 1961 and was joined by Yugoslavia in 1962 and one year later by Poland. Spain entered the Organization in January 1961, but financial pressures forced her withdrawal from the end of 1968. As early as October 1952, the Council had agreed on Geneva as the centre for the Laboratory, which was then confirmed in the Convention. The foundation stone was laid on 10 June 1955 at Meyrin and the next day the Headquarters Agreement was signed with the Swiss Federal Council. At that time, the Laboratory comprised 40 hectares in the Canton of Geneva, upon which began construction of the two accelerators stipulated in the Convention—Article II, 3(a), viz. <•) a proton synchrotronfor energies abovetengigaelectronvolts (I0'°eV); (ii) a synchro-cyclotron capable of accelerating protons up to, approximately, 600 million elearonrolts (6* 10seV). Meanwhile, the design and construction of the 600 MeV Synchro-cyclotron went ahead and a first proton beam was produced on I August 1957. The Synchro-cyclotron has since supported a very vigorous programme of research in particle physics and

5 nuclear physics. A. major experimental facility for the study of short-lived nuclei (ISOLDE — Isotope Separator On-Line) was completed in 1967. The first circuits of the Synchrotron by a proton beam were made on 16 September 1959 and full energy was achieved on 24 November. Since then the Proton Synchrotron, operating at energies up to 28 GeV, has been the mainstay of the high-energy physics programme of Europe. The decision by the Council to build intersecting storage rings associated with the Proton Synchrotron for research with colliding beams,necessitated the'extension of the Laboratory and following approval by Council in June 1965, an Agreement was signed on 13 September with the Government of France, together with a Lease Agreement putting at the disposal of the Organization a further 40 hectares of land in the communes of Prévessin and St. Genis-Pouilly adjoining the existing site. On 27 January 1971 the first proton-proton collisions in the Intersecting Storage Rings were observed. A lively physics programme was immediately mounted at this machine which is unique in the world. _". ,': Collaboration with non-member States'has been actively pursued and an Agreement was signed on 4 July 1967 with the State Committee of the USSR for the Utilization of Atomic Energy for a joint scientific arid technical programme at the 76 GeV proton synchrotron at the Serpukhov Institute of High-Energy Physics. The Agreement was extended in 1975 by a Protocol which opened the possibility for Soviet teams to participate in experiments at CERN. The setting up of a new Laboratory to house a proton synchrotron of 300 GeV energy, first discussed by the Council in 1963, required.modifications to the original Convention. The Council, in December 1967, recommended to Member States the acceptance of the necessary amendments and on 17 January 1971 the amended Conven­ tion came into force. On 19 February 1971, ten European States (Austria, Belgium, France, the Federal Republic of Germany, Italy, the Netherlands, Norway, Sweden, Switzerland and the United Kingdom) decided to participate in the 300 GeV Programme. They were joined during 1972 by Denmark. It was agreed that the accelerator and the new experimental area in the north should be built by CERN Laboratory II on land adjoining the existing Laboratory designated Laboratory I. A total of 412 hectares in Franee and 68 hectares in Switzerland is being leased to the Organization and building restrictions have been imposed on a further 509 hectares in France and 63 hectares in Switzerland. The very large area involved and the open nature of the site—the accelerator is being built deep underground and only the few surface buildings will be enclosed—required that the Agreement covering the legal status of the Organization in France be revised. The amendments were agreed by Council in June 1972 and signed immediately after­ wards on 16 June. The Lease Agreement for the new land in France was signed on 9 December 1972 as well as amendments to the Lease Agreement signed in 1965 to bring the two into concordance with each other. The "Contrat de superficie" for the new land in Switzerland was signed oh 16 December 1974. The eight-year-long 300 GeV Programme is centred upon the construction of a proton synchrotron in a ring of 2.2 km major diameter. At the beginning of the Pro­ gramme, a number of options were left open as to the exact way in which the project should be completed. In June 1973 Council approved a proposal that the ring should be filled with iron-cored magnets and that the construction schedule should be adjusted to allow the accelerator to reach a full energy of 400 GeV during the sixth year of the Programme so that research could begin at the end ofthat same year in the West Area. Since then the 300 GeV Programme has progressed according to schedule. All the under­ ground work has been finished and at the end of 1975 the main magnet system was completed. In March 1975 the Council derided to reunite the two CERN Laboratories as from I January 1976. COUNCIL OF THE ORGANIZATION

STRUCTURE AND MEMBERSHIP (usai3! December 1975)

OFFICERS OF THE COUNCIL Pmùlein; Mr P. LEVAUX (Belgium) Via WVP.ÏIVI'HI.N: Prulessor Th. G. KorvorMZHLIS (Grcei Dr G.H. STAFFUKD (United Kingdom) I DELEGATIONS (two Dckjulcs from each Member Stale) HJNCIL OF THE ORGANIZATION STRUCTURE AND MEM! !-RSHIP OBSERVERS (usal31 December l»i~>i Poland President: Mr P. LEY ,' \ (Belgium) Turkey Vkc-rrvsitfatts: Professor Î ! Kuiviit MZlxis (Greece) Yugoslavia DrG-H. S- ; t nHt) (United Kingdom) ATIONS (two Delegates from . oh Member Suite)

PERCENTAGE CONTRIBUTIONS OF MEMBER STATES FOR THE FINANCIAL YEAR 1975

Member States Basic unit ISR MtGeV Programmes 1'wsramme Austria 2.22 2.22 Belgium 4.01 4.02 Denmark 2.28 2.29 France 21.47 21.49 Germany, Fed. Rep. of 25.00 25.40 Greece 0.46 — Italy 13.33 13.34 Netherlands 5.30 5.30 Norway 1.60 1.60 Sweden 4.55 4.55 Switzerland 3.38 3 38 United Kingdom 16.40 16.41

Nuclear Physics Division (NP) Leader: E. PICASSO Physics I SC Machine Division (MSÇ) " Department Leader: E.G. MICHAELIS " Director: P. FALK-VAIRANT

Track Ch imhers Dniston {TQ Leader R ARULNTÏRO«. Physics II Department Director: R. ARMENTERÔS

Co-ordinatororihe Theoretical Studie Division (TH) • Experimental Programme Leader: D:"AMATI = '"->, ' J.H. MLLYEY -Theoretical Physics .- Department - Director: S. Fumst

PS Machine Division (MPS) Leader: GX. MUNDAY Proton Synchrotron Director-General Department W. JUNTSCIIKI; Director: C-J. ZILVLRSCHOON

Data Hàhdlin^bivïsiontODy Leader: G. R. MACLEOD

Applied Physics Department*

Intersecting Storage Rings Division (ISRJÏ Leader:, F; FERGER _"'J; 1SR Department Director: W. SCHNELL

Financial Control Finance Division (Fl) - C. Tifoir Administration Leader: C. TIÈCHE Department Personnel Division (PE) Personnel Control Leader: G. ULLMANN G. L'IXMANV: (Central Services) Technical Services and Buildings Division (SB) I Leader: H. LAFORTE Budect Planning Director: G. H. HAMPTON Health and Safety Division (HS) Leader: A. HERZ . Introduction

by "W. Jentschke

As 1 take my leave as Director-General after five years, I should like to review.some of the outstanding discoveries from these eventful years for high-energy physics, in which European physicists using this great Laboratory have played a leading role. CERN came of age this year, A novel form of international collaboration, it was created about 21 years ago to investigate one of the oldest mysteries uf the physical world — the nature ofmatter. Having solved the secret of the , the basic component of the chemical elements which combine to give the physical world its essential character, we have turned in the second half of this century to probe the structure of thé particles, from which the atoms themselves are constructed. These'are the electron, the proton and the neutron. Along the path of discovery other particles have been found which do not themselves have a place in atoms. Three types of force determine the modes of interaction of the particles. The strong force is responsible for binding nucléons together to form nuclei. It is about 100 times stronger than the electromagnetic, force which is responsible for the behaviour of electric charges and thus ensures the existence of atoms and molecules. This force, in turn, is many orders of magnitude (1011) more powerful than the weak force which is responsible for the emission of electrons from certain radioactive nuclei and for many other particle decay processes. The force of gravity plays an insignificant role in this world of sub-atomic particles. The representation of the characteristics of the three forces in mathematical form has been achieved with complete success for the electromagnetic force, with only partial success for the weak force and with no success in the case of the strong force. Tests of quantum electrodynamics (the quantized form of Maxwell's electromagnetic equations) have so far always confirmed the validity of this theory over a range from about a million kilometres down to IO"13 cm (i.e. a range of 26 powers often!). Experiments on the electromagnetic properties of leptons such as electrons and mnons indicate no effects due to finite size, or structure. They behave as "points". In this connection the experiment performed at CERN measuring the magnetic moment of the muon has reached a remarkable level of precision. The electron and muon do not "feel" the strong interaction; the neutrino, which also behaves like a point particle, feels only the weak interaction. The situation is quite different for the hadrons, those particles (baryons like the proton and mesons like the pion) which can interact through the strong force. They have a finite size and probably a complex internal structure. Whereas, so far, only four lepton states are known (plus their antiparticles) the number of hadron states certainly exceeds the 200 or more which we have so far identified. As Professor Weisskopf remarked in 1965: "'There is no question that the existence of these states indicates an internal structure within the particles. A thorough study of these states is bound to lead towards a deeper understanding of this structure." CERN has played, and continues to play, a leading role in the important task of establishing the underlying pattern to this multitude of particle slates. Direct indications of size and structure have been obtained in a number of experiments, especially those in which the .'.'point-like" electron and neutrino have been used as tools to probe the inner constitution of the proton.

11 Experiments at CERN have, in these past five years, made fundamentally important contributions both to our present picture of the nucleon's composition and to our knowledge of the weak interaction (including the first experimental support for theories which might provide a unified theoretical framework for the weak and electromagnetic interaction). These results have been obtained at the Proton Synchrotron (PS) and at the Intersecting Storage Rings (1SR), amply justifying the wisdom and generosity of the Member States in providing these facilities at CERN for the use of their research physicis-

Proton size Two experiments at the ISR gave new information on the overall size of the proton as revealed in high-energy collisions of a type in which the protons interact "as a whole", or coherently, rather than in ways reflecting an internal structure. L One of the early discoveries at the ISR was that the total cross-section (measuring the probability that the two protons will interact), which had seemed to become constant at the highest energies previously accessible at the Serpukhov Laboratory, began to rise at still higher energies. This demonstrated that the overall effects of the strong interaction

Figure I — The total cross-section, ii'ftirfi determines the probability that panicles «ill interact, os measured for a variety of Imuran inter­ Figure 2 — Cross-section variation Kith angle in proton- actions. It was fount! at the Serpukhor Laboratory that at hUjh energies proton elastic scattering measured at two colliding beam the positive kaon-prolon. K 'p. cross-section began to rise with increasing energies. The shapes of the resulting curves are rypieal of eiwrijy q.'icr seeming constant. TIlis u-os dramatically demonstrated for optical diffraction indicating that, for the strong inter­ the protan-prvlon. pp. interaction tit die eery high collision energies (up action, the proton appears as a disc of less than I0~li cm 10 2600 CeVstationary target équivalent) arailable at the CERN ISR radius increasing in -size with energy. .The disc is not and then seen for several other hadron interactions to several hundred GeV completely opaque but allows protons sometimes to pass at the Fermilah. through one another without interacting. - s (GeVz) 0.1 10 20 50 100 200 500 1000 2000 li i | i i 1 i pp-pp 60 o Vs = 23 GeV v AGS - • Vs = 62GeV • SERPUKHOV 55 "~ » FNAL — 10" • ISR t - dtf _ dt 50 - * PP 10 45 #_ i nib ' • • AC J ^"^Zr - Iff V

- 7 25 - 7 10

50 100 500 1000 -6 2 PL(GeV/c) 10 2 (GeV ) 3 are still changing, albeit slowly, at energies up to 60 times greater than that associated with the proton mass. This rise of cross-sections at high energy was already observed for the positive kaon interaction with protons at Serpukhov, and has since been shown, at Fermilab, to be a feature common to other high-energy hadron collisions with the nucléon. Another characteristic of the proton-proton interaction which has been measured at the ISR is the probability ~f deflection at a given angle when two protons collide without producing new particle states (called elastic scattering). In this case, we observe a dependence of the probability on angle which is typical of the process of optical diffraction, with a sharp fall to, a low dip followed by a second maximum as the scattering angle increases. The position of the dip moves to smaller angles as the energy is increased. From these results, we can deduce that the proton is "seen" through the strong interaction as similar to a disc with a radius less than about ICH3 cm, which increases slowly with rising energy. Moreover it does not behave as a "black" disc;;two protons may sometimes pass through each other (like ghosts) without interacting. The overall size is similar to that inferred for the average: charge distribution from electron scattering experiments at the Stanford Linear Accelerator Center (SLAC). The finite size of the nucléon implies some form of internal structure and important clues as to the nature of this structure have been obtained from studies of the rich variety of hadron states (much as an inspection of a particular set of geometrical patterns might reveal the fact that they had been made up from a basic sub-set of Jhree-sided shapes rather than ones of four sides or more). I will discuss this approach and later describe the use of electrons and neutrinos as probes, before returning to the more complex phenome­ na of high-energy proton-proton collisions.

The search for order within the apparent chaos represented by the multitude of Hadron hadronic states was crowned with success by the work of Gell-Mann and Ne'eman in spectroscopy 1961. They found that the observed hadron states can be grouped into sets, or families, and quarks each containing states with the same spin and parity (parity being a quantum mechanical concept related to the properties of a particle under a transformation equivalent to reflection in a mirror). The mesons form families containing one state (a singlet) or eight states (octet); the baryons occur in singlets, octets and decuplets (ten states). Within each family there is a precise relationship between the values for each state of electric charge and strangeness (an attribute which is conserved in strong interactions but not in weak decay processes) and well satisfied relationships also between the masses of the states in each family. A large programme of systematic studies has established that the observed states all belong to such families; although not all members of the known families have yet been recognized, it is significant that no states have been found which do not find a place in this restricted collection of singlets, octets or decuplets. We can cite a few recent examples of this research. At CERN and through the work of a European collaboration at Serpukhov, a new meson state of spin 4 has been found, tiaJiighest meson spin yet established. An excellent-example of the bubble chamber technique is provided by results from the CERN 2 m bubble chamber on the existence of a meson named 8~, a state which had been tentatively seen in several earlier experiments but can now be considered firmly established. It is possibly the first member of a long- sought octet of zero spin and positive parity. The same 2 m bubble chamber experiment on the interactions of 4.2 GeV negative kaons in hydrogen in which about 3 million pictures have been taken, has also yielded new information on baryon states of strange­ ness equal to -2. >>'• u • f

? p. -Q

till I h°c}-

?V-d

*p.—. q \ / » \\ Bi970J  •§ * F igiirei — r/if fcnoirninisoii ! fa J ara/ fcurvom (hi fitting into the families predicted by the SU3 theory of Cell-Mann and Ne'eman. All the hadrons so far discovered fit into W Mich families, those particles which were discovered or whose properties were established a to*?) in experiments at CERN arc picked ont in colour.

3/2" 1/2 7/2"

Ö1 1/2 "

leeeöööe3/2" 5/2" 1/2" 5/21" 1/2* 9/2+ 1/2" e7/2"

sra* 7/2* 11/21- 1/2"

Tlie singlet, octet and dccuplet families can be readily understood by a very simple picture in which all hadrons are built up from just three types of "brick"; these have been given the name quarks. The three types are often labelled u for "up", d for "down" and s for "sideways" or strange. The quarks have a spin value of 'Ah (like the leptons) but their most unusual property is the possession of electric charge less_ than the electronic charge (hitherto believed to be the smallest unit of charge). In the quark model each meson contains a quark and an antiquark (for example the positive pion contains ud) while each baryon contains ihree quarks (for example, the proton contains uud). The elegant success of the quark model in accounting for the observed hadron states only needs the detection of free quarks to become one of the great breakthroughs in the

14 quest for ultimate components of matter. This last step Nature has stubbornly refused to yield, even at the highest energies so far available in the laboratory, in proton-proton collisions at the ISR. The reason may be that the mass of free quarks is too great. Alternatively, theories of "quark confinement" have been developed which deny the possibility of ever releasing individual quarks from their very strong bondage within the hadrons.

I want to describe next some results obtained in tvT> quite different types of ex­ Leptons periment which have proved to be very powerful methods of examining the internal as probes structure of the nucléon. Both use beams of high-energy leptons whose point-like nature of the makes them very suitable probes. High energy is also required to overcome the limits set nucléon by Heisenberg^ uncertainty principle and so resolve fine details of the internal structure. In the first experiments the nucléon was bombarded with electrons accelerated to high energy in the two-mile-long linear accelerator at SLAC. These experiments, which began in 19' S, probe the small-scale features of the electric charge distribution within the nucléon through the electromagnetic interaction. In the other experiments the nucléon was bombarded with intense beams of neutrinos to explore the spatial characteristics of the nucleonic matter responding to the weak interaction. These experiments were per­ formed first at CERN using the Gargamelle heavy liquid bubble chamber which came

Figure 4a — The linear increase of neutrino-nueleon tilul anwteutrino- nuclenn interaction cross-sections with energy as seen at CERN in the Gargumelle bubble chamber and til Fcnnihib. These linear relationships support the concept of the nucléon containing point-like constituents. The ratio of the rm> cross-sections suggests that the constituents have a spin value of '.'z.

Figure •ib — Estimates of the mean square charge of these point-like constituents can be made using data from elcctran-nmieon I SLAC) and netitrino-micleon (Gargumelle ami Fermilab) deep inelastic scattering experiments. These estimates are in Una with the quark model in which the quarks rarrv fractional electron charges ('A. '/i «»J -/ij. V

A Gargamelle A FNAL

_ Iniegral Unit Charges

*Q2=- _ Quark H-—\ "Charges

15 into operation in 1971. Some of the results have recently been confirmed at higher energies by electronic experiments at the Fermilab. The observations made in these two totally different approaches, taken together, provide an astonishingly detailed picture of the constitution of the nucléon. They can be interpreted in terms of a model in which the nucleon's response to both the weak and the electromagnetic interaction is located on point-like grains within the nucléon, of size less than 3/100 of the nucléon diameter. Moreover, the grains have the properties expected of quarks — spin Vx and fractional charges(%, 'A and 'A). Although subject to larger uncertainty, the neutrino results also indicate the presence of just three quarks in the nucléon, with small probability of there being any additional quark-antiquark pairs. One unexpected result, however, is the observation that only about half of the nucléon energy is carriedby the quark constituents. This has led to the speculation that the other half is carried by other components which participate in neither the weak nor the electromagnetic interactions. They have been termed "gluons"' and it is supposed that they are "carriers" of the very strong force which binds the quarks.so tightly within the nucléon that they cannot be freed.

Structure We have seen a remarkable consistency between the picture of nucléon structure revealed by obtained, on the one hand, from the systematics of hadron states, indicating'three quarks high-energy as basic "building blocks", and, on the other hand, from the high-energy scattering-of pp collisions electrons and neutrinos which seems to occur on point-like constituents whose charac­ teristics agree very well with those expected for quarks. If the picture is correct, we expect that high-energy collisions between protons will also reveal some aspects of this granular structure. However the extreme complexity of the strong interaction, which dominates the behaviour of two nucléon systems, and the finite range over which it extends (comparable with the nucléon size) do not allow

p+p-*n^+ anything

• \T=23.5 GeV 30.6 44.8 52.7 62.4

Figure S — The émission of naîtrai pions m a large angle to the line. of flight of the colliding protons in the 1SR {high transverse momentum particle). This [iltmanteiiim has been measured at various collision energies and has been found to occur 10000 times more frequently than was anticipated.

16 interpretations of these processes of a quality and detail anything like that which is possible for lepton scattering. We must be content, so far, with a much more crude and limited view. The violent encounters in which high-momentum transfers occur may reveal the secrets of internal structure. ISR experiments rewarded physicists with the surprise discovery that collisions leading to the emission of particles of high transverse momen­ tum, although very rare, occur nevertheless about 10000 times more frequently than „was expected. In these events particles are emitted sideways with high momentum, that is at a large angle to the line of flight of the colliding protons, in a manner reminiscent of the large-angle scattering observed by Rutherford early this century when he bombarded atoms with alpha particles. Just as Rutherford's observations led him to discover that the mass of the atom was concentrated in a very small nucleus about 10000 times smaller than the whole atom; so the presently favoured interpretation of the ISR results is that we are again seeing evidence for the existence of small-scale structure within the proton, this time via the strong interaction. In this picture the high transverse momentum particles are emitted on the rare occasions when a point-like constituent (called a parton) of one proton encounters one in the other proton.

Figure 6 — Dilta Irani an r.xperiincnl usiiuf the Split-Field Magnet dclcaiim system at the ISR indicate "jet structure" ill collisions where a high transverse momentum neutral pinn emeracs. The parameter Y. called "rapiiH'y". « a measure of correlations in anale and momentum. mi Juras a elmterint) in rapidity (u.-riimJ the J"=0 ralite) Jar panicles emitted on the ^ime vde a>> the IT": an ITCTI distribution is indicated by the dashed line: h ) show, a simitar clustering arauml the highest momentum particle for particles emitted mi the apposite side to the n°. In addition particles are found to be emitted close to the plane containiinj the incident priitons and the n°. All three of these features are expected if jets are formed.

Ni

rtF

I 1 I I 1 !_ j I i I i_L -2 -2 -1

P-» *-P P-* 4-P

PT (max) Py (max) Since these first observations, the study of such processes has been vigorously pursued at the ISR and at Fermilab. Although much remains to be learned, a lot of evidence supporting this explanation has been obtained. The parton-parton collision process is expected to give rise to two rather well defined clusters of particles, or jets, and an experiment yielding results which appear to confirm these expectations has recently been performed using the Split-Field Magnet at the ISR. The studies so far made of the jet structure are unable to convey much information on the actual nature of the partons. Future experiments will surely give some clues, especially those which study correlations betweei. the identity of the emitted particles. However, it seems reasonable to identify them with the quark-like constituents revealed by the high momentum transfer lepton scattering experiments. A comparison of the characteristics of hadron emission (at high transverse momentum) in the three different processes: p + p (ISR), e+p (SLAC) and e+e~ annihilation (SPEAR) supports this conjecture. Jet structure has been established at SPEAR in the annihilation of electron and positron to hadrons when the total hadron momentum has values comparable to those for the particles observed in high transverse momentum processes at the ISR.- To summarize, experiments at the ISR have discovered strong interaction processes which could be caused by the collision of point-like constituents within the proton. It is tempting to speculate that these could be the quarks which were invoked as the "building bricks" of hadron spectroscopy and which also present the simplest explanation to date of many details of lepton-nucleon scattering.

riaarc 7 — Schematic representation ot the jels arising in three types of particle inter­ action. Similar features are found in cvperimeiits studying jet formation in all three processes, leading 10 the suggestion, ihul llu* comjîinn n]t?c/iiinisi» is an tiltL'rui'nuu with the portons or quarks. uii Electron-positron collisions in the SPEAR storage ring tit SLAC with the possible intermediate formation of a guark-antiquark pair. i h ' Electron-proton •icancrimj at SLAC where the electron may scaner from un iiii/iritfiKif gitark. ' c, Proton-proton collisions in the CERX f5R where the scattering ntay centre on a auark in each panicle.

PROTON a)

NUCLEON/ (\

MESpNS~?0_

C)

MESONS

Figure iS — Prolan-prolan scattering invoicing the émission oj' particles from two processes — fragmentallait and emission from the central region. I a ) The eulliding protons seen as each containing three quarks. I It I Two excited nucléons emerge from the collision region leaving an excited 'glue scraped off behind them. (c) The nucléons dc-excite giving off mesons (fragmentation) and the glue disperses again gieing mesons (central region emission).

18 Before leaving the realm of high-energy proton-proton collisions at the ISR, I should Multiple like to show how some of these ideas could provide an explanation of the more typical production events. In a typical collision, two sources seem to contribute to the creation of an average of particles of about eighteen particles (mainly pions). These processes are fragmentation of the in high-energy protons, resulting in the emission of a cluster of pions accompanying one or both of the collisions emerging nucléons, and the emission of other clusters of pions in more or less random • directions from the central region of the collision. In a very simplified fashion, we might assume that the quarks of each incident proton fly through ihe interaction volume, carrying (as indicated by the lepton scattering experiments) about half the initial nucléon energy, and then "hear to form the outgoing nucléons, usually in an excited state, which then fragment, boiling oflf one or more pion clusters. Left behind, in the central region of the collision is a cloud of gluons which has been scraped ofTthe passing nucléons; the cloud breaks up into clusters decaying into the pions which are detected as emerging from the central region. This picture also carries the possible explanations of two characteristic features of such collisions — the outgoing nucléons have typically about half the initial proton energy and the total charge of the pion clusters centrally emitted is usually zero (as one would expect if their source was the gluon cloud since gluons have no electromagnetic interaction and hence no electric charge).

I will now turn to another major discovery made at CERN which has profound The neutral significance for our understanding of the basic forces in Nature, giving hope for a current form unification of the weak and electromagnetic interactions. At first sight this discovery does of the weak not seem to be related to hadron structure but, in fact, its ramifications may link with the interaction observation of new particle states with surprising properties. In their turn, the new states and charm give experimental support to theoretical ideas which seek to establish a relationship between the quarks and the leptons. The weak interaction was believed to have only the "charged current" form: a neutrino of the muon type (which carries no electric charge) would always change into a charged muon when interacting with matter. An experiment in Gargamelle has found neutrino interactions where no muon is created and the neutrino is presumed to leave the interaction unchanged. This form of interaction is called the "neutral current" weak interaction and its existence has been confirmed by experiments at Fermilab, Brookhaven and Araonne.

Figure 9 — The scattering of im anti- neutrino an an electron in the Gargamelle~ bubble cluimber. The anlincvlrino enleritu] from the right interacts with the electron and knacks it out of its atom to aire the typical electron track which seeins to start by itself. This is one of three such erems recorded in - the chamber iv/iir/i are eridence for the neutral current type of weak interaction. Two diffèrent processes due to neutral currents have been observed in Gargamelle. In the first, a neutrino is scattered by an electron. Three examples of this process have so far been round and the probability that these three events are due to a different mechanism is less than 1%. In the second process, the neutrino creates hadrons in its interaction with a nucléon, again without the production of a muon. The discovery is of profound significance. It immediately opened the door for theories which offer the prospect of a unification of the weak and the electromagnetic interactions but which awaited evidence for such a form of the weak interaction. However, with the discovery another puzzle arose. Why are neutral kaons not observed to decay into two leptons via the neutral current form of weak interactions? -' ", _ A' possible explanation was found by reviving an earlier version of the quark model in which it had been argued on symmetry grounds that there could exist a fourth "flavour" of quark, distinguished from the other three by the label "charm" (c). Until the discovery of neutral currents there was no obvious need for charmed quarks but now it could play a role, in partnership with the s-quark, in "cancelling-out" neutral kaqn decays to two leptons. The introduction of a fourth quark, an additional building block for hadrons, should lead to new families of hadrons and it was formerly the main objection to the idea of charm that such particles had not been observed. The situation now seems to have changed radically.

Recent High-mass stable particles discoveries At the beginning of November 1974, news came from Bropkhaven and SLAC of the discovery of a new particle. At Brookhaven the new particle was produced by 28 GeV protons hitting a beryllium target and was seen by its decay into an electron and a positron. Its mass was determined to be 3.1 GeV. At SLAC the same particle was found by the inverse process on the SPEAR storage ring — electron and positron annihilation at a total energy of 3.1 GeV to form hadrons. Within a short time, the particle was also observed at the Adone storage ring at Frascati and at the DORIS storage ring at DESY. A second similar particle with a mass of 3.7 GeV was found soon after at SPEAR and then at DORIS. One of the outstanding properties of these new particles is their lifetime which, at about 10-20 s, is about 1000 times longer than would be typical for hadronic states of 3 GeV mass. Several explanations were proposed and one of them connected the new particles with the existence of a charmed quark, c, such as was introduced to cancel strangeness-changing neutral currents. It is thought that the new particles are bound states of a charmed quark and a charmed antiquark (mesons with hidden charm). If we assume that the charmed quark is relatively heavy, then the long particle lifetimes find a possible explanation. The quark-antiquark state of a meson is a system similar to the electron-proton system in the hydrogen atom. In this analogy, a large number of possible energy levels is expected for charmonium, as cc states are called in general. Between these various levels transitions are possible (again in complete analogy with the hydrogen atom), when the proper quantum mechanical selection rules are observed. At the Conference on Lepton and Photon Interactions, held at SLAC in August 1975, the list of observed charmonium states had grown to seven, all fittingwel l into the predicted charmonium level scheme. It seems that the predictions of the charm model are verified one after the other with the exception so far of its most direct proof, namely the identification of particles pp -* ( J (3100) —»n»|f/«» e~* »Xj_Büaer et si t ( e++ e - ) 12, This experiment ( CCRS ) Nagy el al -32 (ir"-+ii-)/2x 10-«, BS Fit

10« •

1-33 - ^. u ja \t a.

|-34

Co O -1 \j

Aubertelal(BNL2BGeVI 1D-M Binon et al (PS 24 GeVt -35

-36 • 1 1 1 I 1 30 p" (GeV/c)

Figure U) — Measurements of the production i tow-section uf the Figure 11 — The direct production of single leptons as seen 3,1 del' panicle orer a wide range of energies, including those from emerging with transverse momentum between 1.5 GeV to 4 GcV experiment» on the bhpeetromvter at the CERN PS and from the Split* from proton-proton collisions at the ISR. Tile ratio of electron Fiehl \Iaanet um! two symmetric vt) speilruntetcrs at the ISR. ta pion production seems to be constant at about W~4 over a w'ult' ratine of energies. The origin of the phenomenon is- not known. carrying charm (that is, composed of normal quarks plus a single charmed quark). The search is intensive and many other quite new and unexpected effects have been observed but it is not yet certain that they are related to charm. Some of these new processes concern diiect production of leptons.

New lepton production processes Four discoveries concerning the production of leptons have recently been made. Explanations of these new processes are not yet established but they are surely of great importance. They may be related to chann or to the existence of a new form of lepton heavier than the muon or to some other as yet unpredicted phenomenon. The first concerns the direct production of electrons and muons in proton-proton collisions. At the ISR, the direct production of single electrons in proton collisions has been seen. A remarkable feature is that over most of the range of transverse momentum and up to quite high values, the ratio of electron to pion production appears to be constant at about 10-1. Experiments at the Fermilab have also observed the direct production of electrons and muons with the same yield relative to hadrons. As yet little is known about other characteristics of these interactions. The second concerns di-muon events. A neutrino experiment at Fermilab has detect­ ed the existence of neutrino-induced events in which two muons emerge rather than one. It is believed that one of the muons may be a decay product of a new and short-lived particle stale — perhaps a charmed hadron or heavy lepton. Again, little is known beyond the fact of the existence of such events. Figure i2 — An event seen in the Garaamelle bubble chamber which is a slrmuj candidate for the production of it charmed particle. The existence i.fti iniion (\i~) a positron (e*) anil a strange panicle (producing the characteristic V tracks ) is an expected signature for e charmed nariicle.

The third concerns di-lepton events seen in bubble chambers. A very interesting event was found in a neutrino experiment in the Gargamelle bubble chamber. It has since been confirmed by two further events in Gargamelle and by events in a Fermilab neutrino experiment in the 15 foot bubble chamber. In all these events a positron is emitted accompanied by a particle (lambda hyperon or neutral kaon) carrying one unit of strangeness. The particular interest of these events lies both in the emission of two leptons and the presence of a particle carrying strangeness. They have thus the charac­ teristics expected of charmed hadron production by neutrinos through the process: v„ + N-+u,~ + C+ + hadrons; followed by a fast decay of the charmed hadron, C:

+ + C -e +V° + vc where V° is a strange particle (lambda or neutral kaon, depending on whether C is a baryon or a meson). In this sequence both the presence of a positron (rather than an electron) and of a strange particle are the expected "signature" for a charmed particle semileptonic decay. The fourth concerns di-lepton events seen at SPEAR. The direct production of electron-muon pairs has also been observed in electron-positron annihilations on the SPEAR storage ring at SLAC. This process seems to have a threshold just below 4 GeV and is consistent with production of charmed-anticharmed particle pairs of mass about 2 GeV. It may also be indicative of the existence of new heavy leptons.

Great strides have been made in recent years in the study of the nature of matter and CERN has led the way with several essential discoveries. Perhaps the ultimate "elementary particles" of Nature are now coming into view — four leptons and four quarks. Shall we find more such states? After all, only two pairs (e. v,. and u, d) are needed to account for the physical world. We may have to assign a further attribute (given the name "colour") to the quarks in order to explain all aspects of their behaviour. Perhaps we shall eventually find an even deeper layer of structure, within the leptons and quarks. Great excitement exists in particle physics tod.-.y and I assure you that great discoveries, and surprises, are in store for those who pursue further this quest for knowledge. Figure IS — An experiment, originally designed for a precision measurement of 0.08 charge-purity violating effects in neutral kaon CHARGE ASYMMETRY IN THE DECAYS K° decays, has been taking data for three and a 0.06 half years on many ilifllieiH interactions. Usina the powerful technique of large multi- wire proportionul chambers in a matptetic 0.04 spectrometer, around 5 x Wv events have been recorded and analysed giving a substantial im­ : 0.02 provement in the precision of our knowledge of I'II" puzzlimj pfii'iionn'itii of ÇP violation. The figure shows the charge asymmetry of decays '. 0 fi 10 as a function of the decay time. At short times 1 the interference effects between the Ks und K° DECAY TIME T (10-'°sl Kî. components of the beam are prominent, at '. -0.02 later times the charge asymmetry of the Kt decay is observed. Other important results -0.04 from this experiment were a precise determina­ tion of the decay width of the shart-lircd kaon and the lambda, the first measurement of the -0.06 mean stpiare radius of the neutral liions, ifci' lifetime of the neutral sigma and the first -0.08 obserrations of its rtulhitivc decays.

Many other important experiments have been performed during .'ie past five years at CERN CERN and I now review some fields of physics where physicists using the CERN contributions facilities have made leading contributions. to other fields In the field of weak interactions there has been some very precise work on the decays of physics of the neutral kaon which has established the best values to date of the charge-parity violation parameters. The violation of time symmetry was established. The puzzle of the origin of these symmetry violations remains and the data are in agreement with the concept of the super-weak force. Another refined experiment on kaon decay concerned measurements on the decay of the positive kaon into a positron and a neutrino. The branching ratio compared to the decay into a positive muon and a neutrino is in agreement with the prediction of theory. In the field of electromagnetic interactions, the determination of the anomalous magnetic moment of the muon has long been a "forte" at CERN. It is one of the most refined tests of the theory of quantum electrodynamics (QED) and the most recent

16-59 usee (As scale on abscissa)

59-102 S 10' CO ci 102-146

Figure M — The g — 2 experiment is designed 146-169 to measure the anomalous g-factor of the nmon to a precision of the order of 10 ppm {parts per million ) by watching the decay of polarized 169-232 nntons in a 14 m diameter storage ring. The 3 v •",.'' •".. rotating muan spin modulates the counting rate £ 10 232- 275 of the electrons which emerge. The dato shown m giro a precision of 23 ppm and during 1975. 1,1. ,„ ' V», '„,1 ',, ,i' ', » ", ,l"" M this has been improved to 15 ppm which is in 275-316 agreement with i/iialirum electrodynamics up to 1 '' 'I.» .Il'l ...I 'l ,.' I'. .»"I J.III. I.'.. ' II. the sixth order in the electric charge and with the hadron racuum polarization contribution f 'in predicted to he at the level of 73+10 ppm. This is the first time that the hadronic vacuum polarization has been measured. 10' 10 20 30 40 50 60 TIME IN MICROSECONDS

23 experiment at CERN has carried the measurement of "g-2" to the point where it has been shown to be in agreement with QED to the sixth order in e. At this level the strong interaction (the hadronic vacuum polarization) begins to affect the measurement to the extent of 73 ± 10 parts per million. This is the first time the hadronic vacuum polarization has ever been measured. Another measurement in the field of QED is that of the energy difference between the 2P 3/i and the 2S % levels in helium ions where a nmon is in orbit around the nucleus. Assuming QED to be valid, this experiment has provided the best measurement of the charge radius of the helium nucleus. Twenty-five events of proton-antiptoton annihilation into electron and positron have been observed. They indicate that the branching ratio of this interaction compared to all proton-antiproton interactions is 5 * 10~7. This gives a value for the proton form factor in the timclike region. The field of nuclear physics .is investigated predominantly at the 600 MeV Synchro­ cyclotron. Here the ISOLDE on-line,isotope separator has been contributing new infor­ mation on nuclei far from the region of stability. A sudden decrease in radius in neutron- deficient mercury isotopes has been seen to occur at the atomic number (A) of 186. It looks as if there is a new region of deformed nuclei for A less than 186.- Delayed particle emission from unstable nuclei has also been seen at ISOLDE for the first time. All five of the known examples of beta-delayed alpha emission were found at CERN and ten bcta-dclaycd proton emitters have also been found. Experiments with muonic atoms were mentioned above. Other studies of "exotic" atoms have involved pionic, kaonic, antiprotonic and sigmic atoms. A wealth of infor­ mation has been drawn from the results, including precision measurements of the mass of the antiproton and the negative kaon and values for the magnetic moment of the antiproton and the sigma minus. Another variety of nuclear spectroscopy has been the study of nuclei where a lambda particle has replaced a neutron in the nucleus, creating a hypcrnucleus. This has revealed for the first time "strangeness analog states" when looking at the interaction between the negative kaon and such a hypernucleus.

Preparations Soon after the approval of the 300 GeV Programme by Council in 1971, an intense (or SPS activity was .started by physicists at CERN and in all the Member States to prepare for experiments exploitation of the machine. In 1972-1973 the SPS Committee started its work to prepare the physics programme and by the end of 1975, 15 counter experiments have been approved — 10 For the West Experimental Area and 5 for the North Experimental Area. Other proposals are being discussed. In the West Area there will be separated and unsepafated hadron beams from three extei nal targets which will be bombarded by 200 GeV protons. Special facilities will be : a tagged photon beam, a charged hyperon beam and a high-quality, widc-band/narrow- band neutrino beam (produced by 400 GeV protons). The neutrino beam can be used by the two bubble chambers, BEBC and Gargamellc, and by counter neutrino experiments mounted in a building behind BEBC. Great care, has been taken in the design of the neutrino beam to guarantee high intensity and a low background from decay muons. As a result, it should be possible to accumulate neutrino events about ten times faster in BEBC than at present in the 15 foot bubble chamber at Fermilab. The construction, of equipment for these experiments is well advanced and most of them will be able to start taking data when the first particles enter the West Area at the end of 1976. future /:> - fc.xpcrinictirs planned for the West Area of the SPS:

W'AI llitih-cncray ncutrinit interactions I1V16 Polari-ttlion in np and pp elastic scattering ut large pT

II'.-]- Leptonie decoys ofliypemir* WA7 Exclusive luulronic processes at lurac pr IV\ (.•> Quasi l\vo-bndv hadron reacliinn 1V.4W Rare mesons produced in Kp interactions WA4 Photonroduction ofhatlrons II'.'19 High precision study of Ref/imfin pp clastic mitterinu ÏV.-15 liacktvard Hvo-hody and tjliasi two-body reactions WAIÖ Quasi two-body reactions in Kp interactions

Experimentation in the North Area will start about 12 to 18 months after the West Area comes into operation. The experimental halls EHN1 and EHN2 arc under construc­ tion. In EHN2, two experiments will be set .up to investigate interactions of muons with hadrons up to the highest attainable energies. A very high quality muon beam with a design intensity some orders of magnitude higher than the intensity of the existing muon beam at Fcrmilab is being built for this purpose. The experimental hall EHN1 will initially have four hadron beams (one of them can be converted into an electron beam). The thr:e experiments already approved for this hall aim to investigate strong interaction phenomena. Equipment construction for these experiments also has begun. As well as providing the supporting facilities, including particle beams, CERN is providing a considerable part of the equipment, special magnets and detectors, needed for thei.'. experiments. Up to now about 90 million Swiss francs from the CERN budget

r Untre 16 E\pernnein^ planned for the North Area of the SPS: X -W Ct'ritparatirc study oflutttrtrn fratimenlalion .V \2 Test of scale invariance in uutan-nucleon scattering programme ofmuon jthysies

X A3 llodronie production afhiah pT leptons and hadrons XA4 Inclusive deep inelastic mnon scollerinsi ut hii/hcst enernics and Q:

\ .-15 Mahihotli final-stale tunlran reactions with a medium lliflh pT particle.

TDC2 TCC2 NA1 Beam NA3 NAB Beam P4

^Development line for proton beam

IMA 2 Beam M2 INA 4 EHN2 have been spent on the 15 approved experiments. A big effort is also being made to provide the computer support which is essential to meet the needs of these big ex­ periments. I am sure that all these investments will return a wealth of new results in one or two years. We seem to be at a threshold of a better understanding of our physical world and physics at the SPS will begin at an exciting moment when many discoveries seem to be at hand.

Theoretical In parallel'with the experimental physics, the work done in the Theoretical Studies physics Division at CERN is of world standing. Important contributions have been made to our understanding of the phenomena observed in the experiments and to the broad concepts of how Nature behaves. Among the original ideas, one of the most outstanding is the dual theory which has been developed with great success to explain the hadron interactions andThas recently been extended to explain quark characteristics in terms of relativistic strings. Another highlight is the introduction of supersymmetric field theories which hint at new unexpect­ ed connections between bosons and fermions. The possibility of the existence of a monopole in the framework of non-Abelian gauge field theories has created great interest eve; ywhere. ^n example of theoretical success is the completion of the sixth-order evaluation of radiative corrections, which is in perfect agreement with the latest very precise measure­ ment of the anomalous magnetic moment of the muon. Other important work directly connected with experimental findings concerns the interpretation of power levels in large p events in terms of elementary hadron constituents. The idea of an additional particle property and an additional type of quark (such as that now associated with the name "charm') was introduced originally at CERN in 1964 (as weh as by Glashow and Bjorken). It has since become very topical with the discovery of a new family of particles. The Theoretical Studies Division is enthusiastically partici­ pating in the genera! excitement following these recent developments.

Technical A large number of great successes in the field of technology have been achieved here developments at CERN over the past five years. The most outstanding was the extremely successful start up of the ISR at the beginning of the year 1971, four months ahead of schedule. The improvement programme at the PS (including a new RF system and a new type of injector, the Booster! and the reconstruction of the 600 MeV Synchro-cyclotron were completed with outstanding success. Two huge bubble chambers (Gargamelle and BEBC) came into operation, with Gargainelle rewarding us very quickly with the sensational discovery of neutral currents. Two oiher big facilities (the Split-Field Magnet at the ISR and the Omega spectrometer at the PS) were completed and used very efficiently in physics experiments. The 2 m hydrogen bubble chamber celebrated its tenth anniversary in 1974, taking more pictures per year than ever before. A number of interesting new detectors have been developed, such as drift chambers (which have become very important because of their high precision and relatively high data-taking rates) and a new type of Cerenkov counter (which will be necessary to identify efficiently particles in the high-energy beam lines at the SPS). CERN has maintained its leading position in building polarized targets — new developments were the frozen spin polarized target and a polarized neutron target. A meeting on "Technol­ og}- Arising from High-Energy Physics" held at CERN in April 1974 brought all this vork into the limelight and met a very positive response from European industry. 1 can briefly list some of the more important technical achievements of recent years in the domains of accelerators, main detectors and special instrumentation: The ISR have achieved luminosities of 2.1 * 10" per cm2 per s which is five times the design luminosity. Up to 4x I03' per cm2 per s has been reached in a low-beta insertion. Currents in the rings have reached 34.5 A. The average vacuum is 7 xlO-'2 torr, with the best value at one point of 4 * 10"13 torr. Beam lifetimes of about 40 hours are quite regular and beam decay is mainly due to the desired beam-beam interactions. Accelera­ tion to 31.5 GeV is possible while still retaining adequate luminosity. The improved PS had yielded up to 8 * 1012 protons per pulse for neutrino ex­ periments and 10" protons per pulse has been exceeded Tor some periods. The time that the machine is out of action owing to faults is only 5%. In readiness for the role of the PS as injector for the SPS, ihe continuous transfer system has been tested and has yielded 7 x 1012 ppp at 10 GeV operating with an efficiency of 90%. The improved Synchro-cyclotron has accelerated internal beam currents of over 4 uA and achieved extraction efficiencies of about 75% which has never been reached at other similar machines. The time available for physics is increasing rapidly — 488 hours in the first half of 1975 increased to 1402 hours in the second half.

Fit/lire 17 The imreüse in the reaml lumimniiy in the ISR from I'I7I In /'J75 «•• measured tluriini mi r-hyucs runs. ', h) machine ilerehinneiv runs tiiul le ] in the lew-belit insertion.

1971 1972 1973 1974 1975 The 3.7 m European bubble chamber, BEBÇ, has given a field of 36 tesla with its superconducting magnet. Nearly a million pictures have been taken and an accuracy of 200 to 300 urn for a point measurement is achieved, resulting in the most accurate momentum measurements so far reached in a bubble chamber. Almost 4 million pictures have been taken in the Gargamelle heavy liquid bubble chamber. Most of them have been taken with neutrino or antineutrino beams and propane or freon fillings. They have yielded the discovery öf neutral currents and the charm particle candidates. : The Omega spectrometer also has a superconducting magnet which is operating well. Ten experiments have been completed and the spectrometer is now being converted for use with beams from the SPS. The Split-Field Magnet at the LSR. has been used for twelve experiments. It has a detection system of multiwire proportional chambers involv­ ing 75 000 wires. Multiwire proportional chambers are one of the most important developments in detection techniques at CERN. Their use has now spread throughout the world and the first large-scale application was in the CERN experiment on charge-parity violation mentioned above. Even better spatial resolution (about 100 urn) is achieved: from a further product of the CERN work known as the drift chamber, which also has the advantage of lower cost for the associated electronics. Very high counting rates with good resolution (about 300 urn) are being pursued with detectors known as scintillating driA chambers. Transition radiation detectors have been shown to distinguish efficiently between electrons and pions at very high energies. They are in use at the-ISR, as are liquid argon/steel plate calo ïmeters which give good energy resolution with the possibility of reasonable spatial résolution and they have simple calibration. Other particle identifica­ tion instruments are DISC Cerenkov counters which have been developed to operate on beams at SPS energies.

T 1 1 1 T

50 iWT.-fi»!-.' Air chamber

•••••rgi7?l Egg shell s > 30 Figure 18 — An example of the application of drift dmmbers outside high-energy physics is in nuclear scattering radioscopy. Protons with energies in the 500 to 1000 Me V range can be used to obtain directly, wish only one exposure, a t hree-dimensiana} reconstruction of un 20 object. The nuclear scattering of the protons 'mside the object is measured by the drift chambers with a passible resolution of about J mnr — a mucli higher sensitivity than X-radhijraphy. Additional information on 10 relative chemical concentrations inside the object can be obtained and the radiation doses invoked are compatible with human tolerances. The figure shows a 2 mm thick cross-section of an incubated egg set perpendicular to the 20 40 prolan beam. X mm Polarized targets are another CERN speciality and further advances have been made in collaboration with the University of Helsinki. Very low temperatures (50 millidegrces) have been achieved. Proton targets usable in large-aperture magnets have been built which give about 90% polarization with a decay of polarization less than 1% after 30 hours of operation. Polarized neutron targets have also been developed. Instruments for measuring bubble chamber film include the spiral reader which has recently been retired from service, after having measured more than 1 million pictures. A new high-speed, semi-automatic scanning and measuring device, ERASME, will handle pictures from the BEBÇ bubble chamber. 1 The large volume of data emerging from the experiments requires correspondingly large computing facilities. The CERN computing-centre is operating a CDC 7600 computer, and over two hundred other computers arc in use on the site, including a powerful system linked to the Omega and Split-Field Magnet detection systems. Links between computers and experiments are working in' the FOCUS system and there is also an external data link operating to the Rutherford Laboratory.

Relationships with non-Member States have continued to develop. Many scientists Collaboration from the USA participate in the CERN research programme, particularly in experiments with other at the ISR, and European scientists participate in experiments at American laboratories. countries Close contacts with the Dubna Joint Institute for Nuclear Research and'with Soviet laboratories are maintained, in particular with the Institute for High-Energy Physics at Serpukhov. The collaboration with Serpukhov has involved the construction by CERN of a fast ejection system and a particle separator for use with the S'.rpukhov 76 GeV proton synchrotron. Five experiments by groups from the Soviet Union, the CERN Member States and CERN itself have been carried out at Serpukhov with great success. In July 1975, the Agreement "with Serpukhov was extended to accommodate further collabora­ tion between CERN and institutes of the USSR State Committee for.the Utilization of Atomic Energy and of the USSR Academy of Sciences, formalizing the participation of groups from the Soviet Union in SPS experiments. In 1973, a delegation of physicists from the People's Republic of China visited CERN and in September 1974 a CERN delegation paid a return visit to China. The CERN delegation was deeply impressed by the well informed discussions on recent experimental results and current theories in elementary particle physics and by the high standards reached in instrumentation. A number of discussions on the development of scientific contacts were held which may result in an extension of exchanges of information and physicists between China and CERN.

One way of showing the development of CERN during recent years is to study the Demographic statistics on the number of experiments in preparation or on the floor, the number of development CERN staiîin post, the number of visiting scientists (which represent by far the majority of CERN of experimental physicists) and the budget figures. The number of experiments increased when the ISR started operating and then stayed constant for a while. In 1975 the number of ISR and PS experiments began to decrease

29 FELLOWS AND ASSOCIATES 1971 ESTIMATE PAID BY CERN

CERN STAFF (EXPERIMENTAL PHYSICISTS! 1970 1971 1972 1973 1974 197S

1970 1972

Ficure 19 — The number of experiments on the flout ami in prepara­ Fiaure 20 — The number of scientists, reckoned in "man-years" tion during the years 1970 to 1975. In 1975 the numbers on the floor drawing their research material from CERN during the years 1966- tor tlw CERX machines were — Synci'ra-cyclotrmi 7. Proton 1975. The number on the permanent CERN staff has remained Synchrotron 1" t hiali-encray physics 14. nuclear structure 31. Inler- constant imd small while the total has risen by almost a factor of three. seeling Storage Kinas 12.

as effort turned to the preparation of SPS experiments. Although the number of ex­ periments seems to stay roughly constant, the effort increases because of the much bigger scale of the SPS experiments. The number of people on the CERN payroll has increased very little from 1970 onwards and is now decreasing but the number of visiting scientists has grown by a factor of two. Of the experimental research staff on the CERN payroll (which has averaged between 75 and 90 physicists) about half are permanent staff and the other half slay at CERN for periods of between three and six years. This latter category plays a particularly important role in.the European physics community since most of them come from and return to institutes in the Member States and thus help to ensure a close collaboration between CERN and its Member States. - After a period of rising budgets needed for (i) ISR construction, CD the improvement programme and (iii) construction of big detectors, we are now entering a period of decreasing budgets where only the preparation of SPS experiments shows some expan­ sion.

I began with a review or recent progress in this fundamental field of research. Discoveries have followed one other with great rapidity and I expect this to continue. As

30 BASIC AND ISR PROGRAMMES

£ JOO -

Figure 21 — The inulgels for the Basic and ISR Programmes tit CERN during the years 1966 to 1915. Only the proportion allocated to preparing for experi­ ments at the SPS fiiis grown in recent years.

always there will be a mixture of systematic gathering of data, leading to a gradual sharpening of our picture of Nature, and occasional single observations revealing unex­ pected new landscapes of knowledge. In any event, I am sure the physicists of Europe will continue to play a leading role because in Europe we are well placed — the ISR remains a unique instrument, the SPS will operate in a year's time ard the high-energy electron-positron storage ring, PETRA, at the DESY Laboratory will be in operation before the end of the decade. CERN was founded in order that European States could share the expense of providing the major tools required for this field of research and so that the physicists from their universities could collaborate in the search for new knowledge of the physical world. It has been a great source of satisfaction for me to see how very successful this enterprise has been. The scientific achievements reflect the excellent work of the staff of many nationalities at CERN and the cooperation between the groups from the Member States.-The spirit of the-Laboratory and among its users is excellent and is a great testimony to the wisdom of our founders. We must do more than congratulate ourselves on trie past; we must consider the future. Whether Europe is to continue to participate m the culture of this century — the advance of scientific knowledge —will depend upon plans laid in the next few years. It is here that I feel some concern for the future. I am deeply convinced, especially as we pass through times of economic difficulty, that we must not loose sight of long-term objectives and of the need to maintain a lively activity in the basic sciences. I also believe that we

31 must follow the lesson of CERN's successes and base our future plans on international collaboration, certainly within Europe or, perhaps, if conditions eventually permit, within a wider framework. It has been a great honour for me to be Director-General of this Laboratory for the past five years. 1 wish to thank all those whose efforts ensured that the research could be done and thus sustained the renown of CERN. They fully share all credit for the achievements. I should also like to express my regard for the Staff Association and its responsible and wise leadership. - ..'... • • '" ~ And, finally, I shouiù like to thank" the representatives of our Member States who have participated in the work of the CERN Council and its Committees. Their under­ standing of our problems, their encouragement and their basic faith in the worth of this great European Organization has been of invaluable support during my years as Director-General. ' ' '

Director-General CERN Laboratory I

Physics I Department

Nuclear Physics Division (NP) Synchro-cyclotron Machine Division (MSC)

During 1975 the activities of the Physics I Department were concentrated mainly in the following three fields: the setting-up of the experimental programme at the improved Synchro-cyclotron (SC2); full exploitation of the Intersecting Storage Rings and Proton Synchrotron accelerators; preparation of the firstexperiment s at the Super Proton Synchrotron. The first two subjects are dealt with in full in the following pages and the third subject, the experimental programme using electronic techniques at the SPS, as accepted by the Nuclear Physics Research Committee, is summed up in the list of approved experiments at the SPS to be found at the end of the Nuclear Physics Division report The first ten experiments, which will be set up in the West Area, are planned to start in the autumn of 1976. In the majority of cases preparation is well advanced. Physicists from the Nuclear Physics Division are taking part in five of the experiments. After the exciting discoveries of 1974 and 1975, several groups are revising their proposals, especially with regard to the use of the Omega spectrometer and also for several experiments planned for the North Area. The technical services of the Department provided important support in the design and construction of the experimental material for this new scientific programme: for instance, assistance was given in the construction of hyperon and neutrino beams, the construction of large magnets for spectrometers and also the development of wire chambers and electronic apparatus. ©c-

£^S&«

'p^ ^.^^^ 13

Fhfurv I — The speitraiueier used by the CERN-Max-riunck Insinue 'Miumh! Culliihoraiion in the n/> ' -* »7171 experiment'.

Nuclear Physics Division

More ilian two years have elapsed since the first observations, at the CERN Inter­ 1SR programme secting Storage Rings of large transverse momentum production al a level much higher than was commonly expected from naive extrapolation of low momentum spectra. This discovery triggered an intense activity around the 1SR because of the possibility of probing smaller distances than originally hoped for, and because of the interpretations of deep inelastic lepton scattering experiments in terms of parton models. It was hoped that large transverse momentum production could further the understanding of elementary inter­ actions between partons without suffering too much from the usual hadronic complica­ tions. Since then, knowledge of large transverse momentum production has made rapid progress, but no definitive picture has yet emerged, and a clear understanding of the dynamics of the process is lacking. Experiments have been performed in the past years using single-arm spectrometers, double-arm spectrometers, and large solid-angle detectors. The groups involved in this research were the Saclay-Strasbourg and the British-Scandinavian Collaborations using the single-arm spectrometer technique: the CERN-Columbia-Rockefeller, the CERN- Columbia-Rockefeller-Saclay. and the CERN-Saclay Collaborations using the double-arm

35 spectrometer technique; the Pisa-Stony Brook, the Aachen-CERN-Heidelberg-Munich, the CERN-CoIIège de France-Heidelberg-Karlsruhe, the Daresbury-Liverpool-Ruthecford Collaborations, and a CERN group using large solid-angle detectors and the Split-Field Magnet. The main results have been (i) single-particle inclusive production, where invariant cross-sections were observed to decrease very steeply with transverse momentum pT, like pfm, with a power law of m ranging between 8 and 12; and (ii) final states with a large transverse momentum product. Many experimental results are now available in the field of large transverse momentum hadronic production. Theoretical models to explain the phenomenon have evolved from what were rather naive ideas to much more elaborate concepts. Several of them are consistent with the experimental results. The favoured models are still the quark-parton models, because they have the merit of being the most suitable for the experimentalists to understand their difficult measurements. The single-particle inclusive cross-sections have been available for some time, and it seems they do not allow discrimination between the different models. Correlation studies and a detailed study of the structure of final states seem much better suited for understanding high transverse momentum phenomena. In spite of the fact that the structure of the final states appears to be complex, several of its properties Fitlltrf 3 — Fir.vr (i/iM'miriri/i »/;/lc lit'«1 piirtkh J/'!» f .*./,' _ I . ___ • •

M(e+(r)GeV/c2

have become clearer. An intelligible and clear presentation of hadronic collisions with a large transverse momentum product was given at the International Conference on High- Energy Physics, held in Palermo. Experiments have been performed on the two reactions p + p -+ lepton(s) + anything and p + p->e+ + e~, the first at the Intersecting Storage Rings and the second at the Proton Synchrotron. At the London Conference on High-Energy Physics (July 1974), three

experimental groups reported the observation of direct leptons at higher s/s values; one of these experiments was performed at the ISR. The CERN-Columbia-Rockefellcr-Saclay experiment observed electrons produced in proton-proton collisions at five different

ccntre-of-mass energies (N/s = 23.5,30.6,44.8,52.7, and 62.4 GeV). Electrons were detected

with 8^90° and transverse momenta pT greater than 1.0 GeV/c. The invariant cross-

section for single-electron production at each ,/s is a steeply falling function of pT, while the yields at différent centre-of-mass energies are seen to increase with\Js. Comparison with the behaviour of the charge-averaged pion cross-sections in the same px and ^/s ranges is made using the data of the British-Scandinavian Collaboration. Correlations between particles produced at 180° in

For all the data, summed over s/s, the ratios of pions to kaons to protons was 67:4:3 for tracks associated with electrons, and 720:50:53 Tor tracks associated with pions. A special case of correlation is the study of electrons produced in opposite detectors. A total of eleven such events were observed for an integrated luminosity of 1.79 x 1036 cm "2 , nine of which were attributed to the leptonic decay of the J/ty(3.1 GeV). Efforts will continue at the ISR to study the single electron and the electron-positron pairs produced in the proton-proton interaction. In particular, a superconducting solenoid with drift chambers and a lead-glass counter array is being built to explore high px electrons. Recently the CERN-Cclumbia-Rockcfeller-Saclay Collaboration has studied trans­ verse momentum distributions of A0 and K° in pp collisions at x=0. The K° yield is in + agreement with published K , K" results. The cross-section (da/dy)pp-,A is (0.43+0.05) mb for A0 and (0.97+0.04) mb for A0. The A°j:ross-section varies very little from PS energies 0 up to ISR energies. On the contrary, the A grows rapidly with s/s. It seems there is a striking similarity between the behaviour of the p and p cross-sections and the A0, A0 cross-sections. The reaction pp -» J/i|<(3.1) + X has been observed in the fragmentation region by the CERN--Orsay- Collaboration using the Split-Field Magnet (SFM) spectrometer. Sixteen ]i+]i~ pairs of invariant mass greater than 2.7 GeV/c- at N/s = 52 GeV have been observed. These events can be interpreted as originating from J/v|i(3.l) decay into u+u~- The mean transverse momentum of these events is =(1.0 + 0.2) GeV/c and the mean transverse kinetic energy

= -mj = (0.18+ 0.05) GeV. This shows that the J/v|z particle is produced with the same mean transverse kinetic energy as that or pions, kaons, and protons, suggesting that it is produced like a hudron. A comparison or the invariant cross-

section, at a mean rapidity of y = 1.6 and pT = 0.5 GeV/c, with that of pions, kaons, and 2 protons at the same value of the transverse energy ET = ^/pf + m shows close agreement, again supporting the conclusion that the J/\|i(3.1) particle is produced hadronically! A comparison with the cross-section for single-electron production suggests that the J/\|i production cannot fully account for single-lepton production. The search for charmed particles at the ISR is being pursued .with- high priority. As is well known, if the quark model is used as a guide, SU(4) symmetry implies a further kind of quark in addition to u, d, and s quarks. The new kind of quark, the c quark, would have the same charge and the same (zero) strangeness as the u quark, but with one unit of charm, whereas the u, d, and s have none. In the same way as the strange particles of lowest mass decay only weakly into other hadrons or hadron and lepton pairs, the lowest charm particles should decay only weakly. A new class of higher-mass particles should be Tound. Only the experimenters can establish ir such an attractive hypothesis is followed in Nature or not. The search for quarks is also being pursued at the ISR. As is well known, quarks have been introduced to explain the hadronic multitude produced in high-energy collisions. Combining the three quarks u, d, and s and making various selections among them, it is possible to reproduce the similarities and differences within a whole octet or decuplet of particles. In other words, a simple quark structure, with three different kinds of quarks with identical interaction; implies the observed SU(3) symmetry among particle states. At present, in high-energy physics, there is evidence to support a point-like (quarks) structure of the proton; in fact, in a very different kind of experiment, the proton behaves as an assembly of quarks acting independently of one another. But any effort to break the proton into its quark constituents has so far failed. A CERN-Bologna Collaboration took data in the Split-Field Magnet in the first half of the year to search for quarks and new particles.

Figure 4 — Special preaiuliom. such as an environment mill less than 2% humidity, an required in the construction of transition radiation detectors made from 0.05 film thick lithium foils. Assembled detectors, such as those used at an ISR intersection region to indicate the passage of ultrurelaticislie particles, consist of 500 layers of these Joih - spaced 0.3 mm apart and reach a sensitice cmss-sectiun areaofl in*. fCERN-Mli.2.751 Sonic other experiments ;it the Intersecting Storage Rings should be mentioned. A CERN-Rome Collaboration lias completed the analysis of the data on proton-proton total cross-sections measured at energies between 23 and 63 GeV in the centre-of-mass system. This experiment was performed in collaboration with Pisa and Stony Brook, and involved the measurement of the forward elastic scattering simultaneously with the total interaction rale. Total cross-sections have thus been obtained independently of luminosity measurements. The rise of the proton-proton total cross-section previously found has been confirmed by this experiment, the cross-section being determined with better precision (±0.8%).- " - "-;-.--- :-:'--.-: ;._ - . " ' "" " Measurements of proton-proton elastic scattering in the Coulomb region at 63 GeV c.m.s. energy have been made. An angular distribution extending over the range 10~3S|t|S4x 10"- GeV- has been obtained. A Brookhaven-Rome-Adelphi Collaboration is searching for particles decaying into photons. In view of the great interest generated by the discovery of the heavy-mass states decaying into lepton pairs, a measurement or the mass or heavy particles decaying into two photons will be carried out. Particular emphasis will be laid on a search for heavy particles decaying into photons emitted in tlie opposite direction around 90° with respect to the ISR beams, where the background of the low-enérgy photons is small, and where the energy of photons can be measured.

I ii/uiT > Ueprevnltilittti of some of llic results cmertjint} Irani ibe M'tf e\pe,-inieill where tile rn/t'i» tlota >,ltiraac M-\/rm i* useti. l'Ile experiment, locilletl til intcr<,ecli,m I-b of the ISR. is (( search for churmctl particles h\ it CURS~llarrurtl-\luiiicli-I<ùcrsitlc-\orlh\vc\tcrii Collaboration. Electrons are cailtlhl anil the relatetl portales InoU'il til lv MV wlielber iliey ctirrcspontl to tin1 special contlititms which are expected to prevail when ti t harmed panicle lui'- ht'i'n produced Tht- luiriztmtcil a.\e\ in the th/ttres pint the enejy.r ofill? particle /m measured in a leotl-ffhlii counter system) attains! the imiincntwit ot the punkte ias measured in a mannet spectrometer system), the vertical axis belnii the numlK-r of crem s. Piuurc a) JKIIVS thitii tor electrons lyinci arounil the 45" line, smce far relativistie electrons encray and nioiiicitiuiii ore proportional. Future b) ••htiwt tlie ir'ujtier open to pions oiso. For them eticray ami momentum are not proportional and they cluster olontj a particular, tptile low em-tyy value 01 the letlil-tllass counters while their moincnia are picket! up by the spectrometer. a) b) A Brookhaven-CERN-Syracuse-Yale University Collaboration, using novel techniques (see Annual Report 1974, page 40), is searching for single and double electrons by asking for a charged particle producing an electromagnetic shower. The experiment is designed to use a large variety of triggers which make it possible to study, for example, electron pairs with particular interest in the small mass region and in large mass states decaying into two or more photons. Finaliy.aCERN-Collège de France-Heidelberg-Karlsiuhe Collaboration has analysed data taken in the Split-Field Magnet spectrometer looking for particle production with high transverse momenta oft the 90° region at 0.15 < x <0.5 (y = 2) and in the 90D region at pr>25GeV/c. Extensive study on two-particle correlations shows a strong corrélation

between a high pT particle of positive charge and a negative additional particle' at the same rapidity and azimuthal angle. This correlation is due to the decay of A particles at

high pT. Though the triggering high py particle has a rapidity of y = 2, the compensating particles at opposite azimuthal angle are distributed symmetrically around y=0. New

high pT data with a trigger at y=l (9=45°) show that there exist strong correlations between the triggering high pr particles and additional particles at the same rapidity and azimuthal angle of the same and opposite charges. This result demonstrates that this cor­ relation is presumably not due to resonance decay. During 1975 the CERN-Harvard-Munich-Riverside-Northwestern Collaboration searched for "direct" electron emission at 30° in proton-proton collisions at the ISR.

Measurements were extended to very low transverse momenta (0.3

electron emission at larger values of pT. The results show the surprising behaviour of a rising e±/K± ratio, which is in contrast with the results at the ISR and Fermi National

Accelerator Laboratory at larger pT which, on the contrary, have shown a constant e±/n± ratio.

The exploration at small pT is of great interest, since a common feature of all models which seek to explain the single electrons as a decay product of a yet undiscovered family of particles is that the single-electron spectrum must fall off sharply for transverse momenta below the maximum momentum obtained by the electron in the rest frame of the decaying particle. For instance, the explanation of the effect in terms of decays of

known vector mesons (p. to. d>. J) cannot reproduce the fast rise at small pT. On the contrary, the decay of charmed objects could well reproduce the observations. The effect is being actively investigated. In particular a search is being made for ""bumps" in invariant mass and for muons in association with the anomalous electrons.

PS programme Only a few of the experiments being carried out at the Proton Synchrotron will be mentioned here but a complete list can be found at the end of this section and a brief description of both the aims of the experiments and the apparatus can be found in the book on "Experiments at CERN in 1975". Firstly, there is the experiment of the Basle-Karlsruhe-Stockholm Collaboration on (K, p) mesic atoms.-A powerful detection system for low-energy X-rays has been installed which consists of five Si detectors of extremely high-energy resolution, 200 eV at 6 keV. The aim of this experiment is to study the X- transitions in the K_p, pp system. The interest of this study cannot be easily summarized in a few words but a few r) Fimire 6 ^~A .set of binary-coded-scintillator-hoddscopes. To reduce the number of phoWimtltiplU'r lubes, a binary-coded liahl pipe system has been constructed. In tln\ way llteôU scintillator strips require only lb photomulliplier lubes. The hodoscopes arc used to meurtre the beam direttion in experiment SMS (Cleriiiont-Ferraiul-Lyan-Vppsalu- Uiirsuir Collahnnttiim ). (CERX-2I9.7.75I

Fiqurc 7 Mass speelruin lor the rc'V system produced in Ti /j-* TI'VH at JO GcV.c. The distribution is tor events Willi cos Oy..' sztl.5 and without any correction tor detection evident y. This result was obtained by the Karlsruhc-l'isa-ScrpiiUlur-liennu Collaboration in the fourth CERX-SerpliUun experiment.

arguments of general interest can be pointed out The first point is concerned with the variety of phenomena which are observable in spectra of hadronic X-rays in the mesic- nuclei systems. They range from observations of chemical and solid-state effects over clear, very detailed, nuclear physics information, to the accurate determination of properties of elementary particles and to the investigation of strong interactions between the captured hadrons and the nuclei. The second point of interest is the accuracy with which all this information can be gathered. The masses of the particles can be determined with a relative error approaching 10"', and the accuracy in the determination of strong interaction effects is sometimes as good as a few per cent The third point of interest is the simplicity of the system in that one is always dealing with a hydrogen-like system; this gives the hope that even in the field of chemistry and solid-state physics, valuable contributions can arise from the study or mesic X-ray data. A very clear and complete review of the physics of the muonic and hadronic atoms was given at the 1975 Summer School on Nuclear and Particle Physics at Intermediate Energies, in Victoria, Canada. A systematic study of electron pair and gamma-ray production in pp annihilation at rest is being done at the PS by a Mulhouse-Strasbourg-Turin Collaboration. This experi­ ment studies the reactions pp -> e+e~, pp -» JTV, where e'-» e+e", and pp -» Jt°jt°. The antiproton is slowed down at rest in a liquid hydrogen target. The first of these processes allows the investigation of the proton form factors at the threshold of the q2 time-like region. The second process will test the existence of the suggested resonance e' and its

41 decay into e+e" pairs; the third process would establish the presence of waves other than s-waves in pp annihilation at rest. Twenty-five collinear electron pairs have so far been observed. Since the background was proved to be very low {< 1%), these twenty-five events can be attributed to the first process. A branching ratio based on twelve Ce~ pairs was derived: npp-e+e-)- xlO" T(pp -* anything)i-(?f" ) The normalization is done relative to hadronic two-body processes it+it" and K+K". To complete the effort at the PS on the study of the pp system, an experiment will start soon to look for X-ray cascades of the final states of the pp atom (protonium). The cross-sections and energies of the transitions to the s- and p-states of the pp molecule will be measured. With regard to the effort to understand lepton production in proton-proton collisions, there has been a recent paper in which data on dilepton spectra in a forward cone have

been used to predict the p°, w°, and \(» production at 9cm = 90° and their contributions to the single-lepton spectra. The rc,(p 0+w0), and inclusive cross-sections are well fitted over the entire pr range by a simple expression. Combined contributions from p°, a>°,

^P production on and Nickel

13« 19 GeV/c a2« "«.dbrl (GeV/c)2

MjO = 1.192 GeV/c?

Figura S — The Primakoff production of J." hyperons is lisible us a peak in the differential cross-section at eery /oir q2 for data in the mass bin 1.192 ± 0.015 GcV/c-, and in the mass distribution of 2 1° Monte Ca'lo events A + 7 events for q* <0.001 (GeV/c) . The back- around is due to the decay of z? particles. The experiment was performed at the PS by a CERN- 1.30 Heidelberg Collaboration.

"AY (GeV/cZ) and \)f are found to account for about 30% of the observed lepton spectra. The simple model which describes the production of it, \|i, and vector mesons is given by

where f(y) is a single function of the centre-of-mass rapidity. A Heidelberg group is using a high-resolution magnetic spectrometer to investigate

hypernuclear levels via the strangeness exchange reaction K~ + A -* AA* + ÎT. Some, results on 'Be, '^C, and ^O have been obtained. In a preliminary test it was found that the spectrometer is an effective instrument for investigating the possible formation of narrow resonances in the p> system below 1 GeV/c p momentum. Very preliminary results seem to support the existence of a narrow resonance around 475 MeV/c, but more data are needed to confirm or disprove it. The strangeness exchange reaction (K ", jt") on nuclear targets has become an excellent tool for studying hypernuclei. Advantage has been taken of the fact that in this reaction the A particle can be produced without recoil. This favours the formation of hypernuclear states which are closely related to the target nucleus ground state. ; The (K~, T~) reactions have been studied in 'Be and '^C, where the states observed in these systems can be assigned to independent particle configurations where a neutron has been replaced by the A particle in either the Is or lp shell. In the 'jfO system the observed states cannot be described as unperturbed configura­ tions and some mixing has to be taken into account. It is in fact possible that in heavier nuclei the mixing configuration would be stronger and collective phenomena become dominant. Recently an experiment on 40Ga was performed at the PS. The number of configurations (Is, lp, 2s, Id) excited in the reaction should be big enough to give collective effects. The 40Ca spectrum is dominated by a single broad peak centred at a A bending energy of about—15 MeV. The qualitative features of this resonance are similar to those discussed by Lipkin. An IPN-IISN Collaboration has built a symmetric bispectrometer for a systematic search for heavy particles. The spectrometer offers a method for a high-sensitivity search

Figure y — One arm oftlie bispectromeler used in experiment SIS2. From left to right can be *een: four hodoseopes. two rertical and two horizontal: lour planes ofmjdtiwire proportional chambers for particle localization: two threshold Cerenkoc counters for e and p identification: two DISC counters mill liquid radiator for 1; and p identification: one more threshold Cerenkov counter for JC identification: limc-of-flight counter and the first office lead-glass . '--• vr c H iters CER.V-I_5.75 ) for charged two-body decays of heavy particles produced in a proton-nucleus interaction. The beam line and the two arms of the bispectrometer were installed during the long shutdown of the PS at the beginning of 1975. Evidence of the 3.1 GeV/c2 resonance has been found by analysing the e+e~ pairs produced in the collision between a 24 GeV/c proton on to a C target. The spectrometer is now ready to be used to search for new phenomena. , - The CERN-Max-Planck Institute, Munich Collaboration, whose activity at the PS has been so successful over the last few years, has taken data with a target containing polarized protons in order to study the reactions + + n~p-*nn 7i~,nK K~.npp,pA3"",pnrat. _ . The first reaction allows an almost complete determination of the quantum mechanical amplitudes describing the reaction. These are important because up till now this reaction has been the major source of information about the itTt interaction. Unfortunately its interpretation has been model-dependent, lacking a complete set of measurements. The combination of the polarization-dependent moments from this experiment with.the polarization-independent moments of previous experiments will allow a complete determination or the production amplitudes of this reaction, with the exception of one relative phase between two sets of amplitudes. The same group will measure the reaction K "p -> A (forward) + neutral meson. This reaction will permit the study of the production mechanisms of baryon-exchange processes and the value of the coupling constants to the nucléon of the t\, co, and t\' mesons. A CERN-ETH-Imperial College-Saclay experiment is designed to measure the P, A, and R parameters at 5 GeV/c in the reaction 7t~pî -> K°A. The group has found a rapid variation of the scattering amplitudes as a function of the momentum transfer for a value greater than 0.5 (GeV/c)2, which is not explained by Regge pole models and which may be connected with observations made in up backward elastic scattering. A Collège de France-Padua Collaboration is studying the reaction K°p -• KSJp(;t+7t~). This experiment measures do/dt in the incident momentum range 4-14 GeV/c and |t| range 0.1-2 (GeV/c)2. Data-taking is still in progress. A Geneva group is measuring strange boson production in the reactions K "p -• K°7i~p and K'p -> K°7t+p. The purpose of the experiment is to clarify the situation of the K*(1760), the expected strange member of the 3" triplet. Other reactions can also be recorded, as for example: K +p -• App, p + anything; pp -> K+p, prot, pKK, p + anything, etc.

Figure 10 — Liquid hydrogen tarnet (inside the horizontal black tube) withdrawn from the surrounding cylindrical y-ray-measuring scintillation counter Iwdoscope used in experiment SMO. (CERN-176.9.75) Figure II rolislliml the chromatic tocu>inii tinj corrcctimt mirror ifisaciateil irjf/i it dillcrcnlttil I'crcnkor counter. t KK.\-S.S_V5i

The Omega spectrometer stopped operating in the middle of 1975 in order to be converted for SPS physics. Data have been taken and analysis.is in progress. A search for charm has been made in Omega. The beam transport was modified to increase the beam momentum to 19 GeV/c, and to obtain a centre-of-mass energy of 6.0 GeV for ir~p inter­ actions. Three million triggers, which required a forward K- or p with transverse momentum greater than 0.5 GeV/c, were recorded; 300000 four-prong events and 100000 six-prong events were found. Subsequent kinematical analysis yielded 4500 events fitting the four-constraint four-prong reaction ir~p -+ K+K"ir~p, and 3000 events fitting the six-prong reaction n~p -* K.+K-ir+ir"ir~p. The aim or this study was to look Tor production or either charmed meson pairs (ir"p -* D~D°p, D°D°ir~p) or associated production of charmed mesons and baryons in the reaction jc"p -+ D~C+, D"C°. D masses i j GeV/c2 and C masses >2.0 GeV/c2 were searched for. No convincing accumulation of events was seen. Recently a group from the University of Aarhus, CERN and Strasbourg, using secondary beams ofp, jr+, it- of 1.35 GeV/c at the PS, established the channelling and blocking effects; the ionization loss spectra of several charged particles under channelling conditions were measured. When fast charged particles peneirate through a crystal lattice, their behaviour may depend strongly on the direction or motion because or correlation between deflections in successive collisions. Channelling means that a particle path near the centre of channels along a major axis in a crystal may have a certain stability. Particles moving along channels are subject to periodic forces, mainly focusing and, occasionally, defocusing. Blocking and channelling phenomena have been used in nuclear physics; in particular, blocking dips have been used to study nuclear lifetimes. A strong reduction in ionization loss of about a factor of three for p and ir+ has been observed. For jc~ no such clear-cut effect occurs. The results for positive charged particles are in agreement with qualitative arguments that attribute roughly one half of the stopping power of fast particles to close collision with large momentum transfers, and half to distant collision. For well channelled positive particles, the close collisions are suppressed owing to the low electron density along the particle trajectory. Finally, mention should be made of the recent muon (g—2) experiment done in the South-East Hall at the PS. This experiment is designed to measure the anomalous g-factor of the muon a = (g—2)/2 to a precision of the order of 10 ppm. Polarized muons from

45 pion decay are injected into a 14 m diameter weak-focusing storage ring. The magnetic field in the ring is uniform, and vertical, focusing is obtained by using a pulsed electro­ static quadrupole field. The momentum of stored muons is chosen to be at the so-called "magic" value where y2ß2a= 1, and the helicity precession of the muons depends only on the magnetic field. Decay electrons from stored muons are detected in twenty shower counters placed inside the ring. The asymmetrical decay distribution of-the electron relative to the rotating muon spin gives a modulation in the counting rate of energetic

electrons at the (g-^2) frequency: io„=a x (e/m0c) x B. A precise knowledge of the field B then enables a to be found. A first result of this experiment, with a precision of 23 ppm,: has already been published. Evidence was seen of the effects of hadron vacuum polariza­ tion in the space-like region. Data have been accumulated in 1975, and the precision now reached is at a level of about 15 ppra. The analysis of the data is still in progress. There have been runs with u+ and u~. The first published number is in agreement with quantum electrodynamics up to the sixth order in the electric charge, and with the hadron vacuum polarization contribution predicted to be at the level of 73 ppra. It is perhaps useful to summarize the results obtained recently in the analysis of an experiment which ended last year, carried out by a CERN-Heidelberg Collaboration in a K-neutral beam.in order to study the K°-Z° interactions:

the analysis of the Kc3 form factor has been completed; the mean square charge radius of the neutral kaons has been determined, < R2 >= (0.08+0.05) fin2; the analysis of the Äp total cross-section in the momentum range 4-14 GeV/c has been completed, CT=(49. 3 ± 3.8) mb; the lifetime of the 2° hyperon has been determined via the. Primakoff cross-section, TÏ° = (0.7±0.2)X10-I9S; the rare decays H° -» Ay and E -* £°y have been observed for the first time; the analysis of the respective branching ratios BR(E° -» Ay) = (1.4+0.4) x 10~3, BR(H° -• £°Y) = (2.2 + 1.2) x 10~3 have been completed, as well as the analysis of the decay asymmetry, a[E" -» Ay) = 0.22 ± 0.34; 10 the analysis of the lifetime of the A and E° hyperons, xA = (2.68 ±0.03) x 10~ s, is nearly completed; the analysis of the radiative decay K" -» Jiny has nearly been completed, BR(Kg - rory) = (2.59 + 0.02) x 10"3. Finally, a Heidelberg team has evaluated the branching ratio + + + + BR = T(K —e v)/T(K —u v). From 404±4 observed Ke2 decays a value of BR = (231 ±0.15) x 10~5 has been obtained. This result, combined with an earlier result of BR=(2.37±0.17) x HT5, yields the final number BR=(2.45±0.11) x HT5. The value expected from u-e universality and pure axial coupling is BR = 2.57 x 10"5.

A new result on the rate of the structure-dependent radiative Ke2 decay will also be obtained. The analysis of the K_& data is in the final stage. Results on the branching ratio in the lepton momentum region between 130 and 180 MeV/c are expected.

SC programme A CERN-Pisa-Saclay Collaboration has performed a very elegant experiment, 3 1 + measuring the energy of the 2p /2-2s /2 transition in the (u*He) ion. Negative muons from the Synchro-cyclotron u-channel are stopped in a gaseous helium target at 40 aim and 293°K, and about 5% of them form excited muonic helium atoms in the

46 t îîîîîrrrTïTO'

CAESIUM MASS NUMBER

Figure 12 Mass spectrum of radioactive caesium isotopes produced by bombarding lanthanum with 600 McV protons in the IS0LDE-2 on-line hotopc separator. The proton beiun of up to /J o.Afram the reconstructed SC in conjunction with the improved target and ion-source technique Iwve increased the production capacity of the facility. The resulting separated radioactive ion beams are now. in the most favourable cases, exceeding 6 nA or 10'° atoms per secoad. In the figure these beams are risualteed by means of the conventional charge-scanning technique, usually only applicable to the stable '**Cs. introduced for mass calibration purposes. The yield of the short-lived 124Cs (T», = 21 s) Jails below the general trend because of lasses by the radiative decay due to the delay between formation in the target and detection.

2s state. The lifetime of this metastable state is about 1.6 us. A pulsed electromagnetic radiation, produced by an infrared dye-laser excited by a Q-switched ruby laser, 4 is applied to the (n He)^s ion system. By varying the radiation wavelength, a search 1 3 3 for the resonance with the 2s /2-2p /2 transition is possible. The presence of the 2p /2 state 13 is identified by the detection of the 8.2 keV X-ray emitted promptly (x2p = 5 x 10~ s) p 1 3 in the 2p-ls decay. The energy difference S" = 2s /2-2p /2 is determined at that value of the wavelength X which corresponds to the maximum enhancement in the number of X-rays in coincidence with the radiation pulse. The measured value is I 3 Sf"'=(2s72-2p3/,)=(1527.4±8.7)x HT eV, to be compared with the theoretical value SÏ1 = (1525.1 +8.7) x 10 ~3 eV. The comparison with the theory is restricted by the uncertainty in the r.m.s. charge radius of 4He. The above theoretical value is obtained using a value k = (1.650 ±25) fm. In spite of such an uncertainty, this measure­ ment is an extremely good test of vacuum polarization effects in quantum electrodynamics. A Karlsruhe-Trieste Collaboration is studying pion absorption in complex nuclei, via the observation of the emitted reaction products. Information about pion-nucleus inter­ action, as well as about nuclear structure, is expected. Previously, nuclear de-excitation y-rays, emitted after the absorption of stopped pions,.were investigated in a series of nuclei between 9Be and 93Nb. The results showed the presence of a large variety of reaction channels which were, however, mostly of sequential character. The predominance of the initial pion interaction with two nucléons has been confirmed. The ISOLDE-2 facility, an electromagnetic isotope separator on-line at the Synchro­ cyclotron, has, during 1975, been operated with four different target-ion-source systems and has delivered beams of radioactive isotopes of the elements caesium (Z=55), mercury (Z=80), ytterbium (Z=70), and rubidium (Z=37). These products were chosen with a double purpose; they served to test the new installation, and at the same time they allowed a maximum number, of physics groups from the 15 laboratories in the collaboration to. begin testing ör data-taking. As the technology developed before the ISOLDE reconstruction is based on a total of 15 different target-ion-source systems, it is clear that many experiments cannot expect to get on the floor for quite some time to come. The tests of the installation have been satisfactory; in particular, the new beam- handling system (for the radioactive ions), which allows parallel operation of four experiments working on different separated masses, has greatly increased the utilization of the facility. Yet the basic difficulty still remains—to operate the different targets often enough to satisfy the needs of the physics programme. The intensities of the secondary beams are already very high; when the design current of 5 uA for the extracted proton beam is reached, the production yields at 1SOLDE-2 will be of the order of 300 times higher than with the old installation, or of the order of 5 x 1010atoms/s x mass number for the most favourable cases. Nowhere else in the world are such beams available. Most of the ISOLDE-2 physics experiments are still in an early stage of testing or data-taking, and a detailed discussion is hardly warranted. The main lines of research are as follows:

MAIN LINES OF RESEARCH AT ISOLDE-2

Beta-gamma spectroscopic studies of excited nuclear levels, associated problems in nuclear structure. Development of new experimental techniques, in particular target-ion-source systems. Atomic spectroscopy by optical pumping of radioactive atoms. Hyperfine spectroscopy by atomic-beam magnetic resonance techniques. Nuclear masses by high-resolution mass spectroscopy. Nuclear masses through the determination of Q-values in beta decay. Alpha decay of extremely neutron-deficient light nuclei. Electronic isotope shifts from crystal diffraction spectrometry. High-energy beta decay and delayed particle emission. Fine structure and fluctuations. Targets of radioactive nuclei for low-energy nuclear physics experiments. Ranges of ions in gases. Hyperfine interactions of radioactive atoms implanted in solids.

It should be pointed out that each of these usually comprises a considerable number of different experiments. A few of the early physics results are given below. In 1974, the firstan d only barely observable case of beta-delayed alpha emission from a highly neutron-deficient nucleus (181Hg) was reported. During 1975, two much more 118, 120 favourable cases were found, Csy which represent only a few hours of counting, with the proton beam still much below the SC2 design value: It is interesting to note that the high intensity in the U8Cs case probably arises to a large extent from quantum mechanical fluctuation phenomena of a type not previously observed in statistical physics.

48 The atomic-beam magnetic resonance technique has been used to measure a sequence of spins in isotopes of gold (obtained as a daughter product from mercury) and from rubidium. The experiment permits the selection of nuclei according to their angular momentum; consequently, the joint set-up (spectrometer plus ISOLDE) acts as an instrument selecting one given set of values Z, A, and I. Two new alpha-emitting isotopes, li3Yb arid 177Hg, have been detected. The.latter, which has a half-life of 0.17 s, is approximately 23 neutrons removed(from beta-stable mercury and represents one of the most neutron-deficient nuclei ever observed. An experiment in cooperation with the Institut Laue-Larigevin in Grenoble is studying nuclear reactions induced by a thermal neutron beam in radioactive samples produced at ISOLDE. A first result has been the observation of protons arising from, the (n,p) reaction on a 0.01 microgram target of radioactive 84Rb with a half-life of 32 days. It is easy to see why it is the first time that such a reaction has been observed in heaviernüclei: only with a radioactive target does one obtain a sufficiently positive Q-value for the (n,p) reaction. The testing and development of new experimental techniques for the ISOLDE target and ion source are continuing. A new concept, a solid high-temperature (2200° C) powder target of tantalum, has been shown to give abundant and very clean beams of the rare- earth element ytterbium. An interesting feature in this type of target is the presence of a fast diffusion component, which enhances the yield of very short-lived products. This technique shows great promise for the future. The programme carried out at the PS by the Basel-Karlsruhe-Stocfcholm Collabora­ tion is complemented by the same group's activity at the Synchro-cyclotron. A careful evaluation of a high-precision measurement on muonic Ba and Pb X-ray lines has been done recently. The accuracy for the energies of these lines is ~2 x 10~5. The transition lines studied in the muonic Ba and muonic Pb atoms are very sensitive to QED effects (prevalently vacuum polarization) in large electric fields. These measurements provide a good test of the QED predictions. The muonic 3d-ls (3p-ls) Zn line, which should show an asymmetry of about 10 ~5, has been clearly seen in the X-ray spectra with a reasonable yield. This preliminary result is concerned with the problem of whether neutral currents (recently discovered in Gargamelle) are parity-violating or not The question may be solved by looking at the asymmetries of muonic X-rays relative to the muon spin, in particular in the 2s-ls Ml X-ray transition in fightelements . ISR EXPERIMENTS ON THE FLOOR IN 1975

Experiment Experiment Collaboration Number

i § min 1 Multiple gamma-ray production in pp collisions Brookhaven-Rome Study of high transverse momentum phenomena CERN-Columbia- Oxlbrd-Rockeleller Smalt- angle diffraction dissociation at ISR energies :CERN-Holland- , Manchester • Search for magnetic monopoles at the ISR Bologna-Fermilab Isobar production at ISR energies CERN-Hamburg- Orsay-Vienna Search for new particles at the ISR Bologna-CERN Study of general events and of events including a fast forward CERN-Collège de Franc'c- particle using the Split-Field Magnet facility at the ISR Heidelbcrg-Karlsruhe High transverse momentum events and central correlations at the Liverpool-MIT-Orsay- Split-Field Magnet Rutherford-Scandinavia Double diffraction dissociation at the ISR Pavia-Princeton A hunt for charmed particles at the CERN ISR CERN-Harvard-Muiiich- Rivcrside-North western Search for charmed particles and electron pairs at the ISR CERN-Suclay High-mass muon pairs and associated hadrons Frascati-Genoa-Harvard- MIT-Naples-Pisa Measurement of the ratio of the real to the imaginary part of the CERN-Rome proton-proton strong interaction forward scattering amplitude Study of large transverse momentum phenomena BNL-CERN- Syracuse-Yale

PS EXPERIMENTS ON THE FLOOR IN 1975

Experiment Kurnber Experiment Collaboration

S97 g-J CERN-Daresbury-Mainz SI 30 K°p -. K?p College de France-Padua S131 K^p -. KVp Geneva University S132 Bispectromcter IISN, Brussels-IPN, Orsay S134 n-pî -. K°A° CERN-ETH Zürich- Technical University, Helsinki-Imperial College, London-Southampton S135 pp -* c^c" Mulhouse-Strasbourg- Turin S136 n~pî -* n'n"n CERN-MPI, Munich S137 K*nî -. K°p (Testing) College de France- Padua-Freiburg SI 40 Kp-A,X° CERN-MPI, Munich S141 ppt (clastic) CERN-Orsay-Oxfbrd S144 K±p forward CERN S145 Exotic mesons. Omega n"d -* p,{ppn"iu~) CERN-Collège de Fruncc- Ecole Polytechnique-Orsay S146 Charm search at Omega at 19 GeV/c CERN-Orsay-Liverpool- Saclay-Ecole Polytechnique- Birmingham

S147 KLp -» Alt* Collège de France- Padua-Freiburg S148 ir"p -* K±K°n±n. Omega Aachen-CERN- ETH-Ziirich-Haifa

T230 vMe -* v^e neutral currents Aachen-Padua P7 K~p£" atoms CE RN-Basel-Karlsruhe- Stockholm

Pll Hypemuclear spectroscopy K"A -> AAn* Nucleus Heidelberg Group SC EXPERIMENTS ON THE FLOOR IN 1975

Ex/vririk'M Experiment Collaboration Number

ISOLDE ISOLDE programme ISOLDE Collaboration SC21 Measurement of the 2Sy,-2P^ energy difference in the (u4Hc)* CERN-Pisa muonic ton hy means ofa tunable dye laser SC50 Nuclear cross-sections of cosmic-ray interest Laboratoire Rene Bernas du CSNSM. Orsay SCSI Study of neutron-deficient nuclei between U(Z = 92) and Marburg-Gicsscn Ph(Z=82) using a helium jet transport technique SC52 Measurements of average energies, funvard momenta and aniso­ Chemistry Department, tropics of specific fission products from fission oHcad induced bv Oslo University 600 McV protons SC53 Study of products or binary fission in disintegrations of U, Pb, Lund-Oslo Pr, Ag, Sr and Cu by 600 McV protons SC54 Calibration of a neutron counter at the CERN Synchro-cyclotron Birmingham- Rutherford Laboratory- Tel Aviy-Wcstficld SC55 A study of particle emission induced in the absorption of Karlsruhe-Trieste stopped it" in 160 SC56 Test Tor experiment at SIN University of Geneva SC57-1 Hadron radiobiology: investigation of the survival of spermato­ CERN gonia type B in mice after exposure to the SC2 595 MeV neutron

SCS7-2 Hadron radiobiology: investigation of the inhibitation often days' CERN growth of Vicia Faba roots after exposure in the 595 McV neutron beam from SC2 SC5S Production of 24Na from U at intermediate and low proton Chemistry Department, energies Oslo University SC59 Precision measurement of the partial muon capture rate 6Li-6Hc Louvain SC60 Search for a new mode of capture in nuclei: ÏT~ + A -* B + 2y Lou vain SC6I Tests for experiment on weak neutral currents in u atoms CERN-Karlsruhe-Bascl SC63 Elastic scattering of up and ud muonic atoms against protons and 1NFN, Bologna dcuterons SC64 Tests for fast separations of nuclear reaction products Technische Hochschule, Darmstadt SC65 Local magnetic fields in ferromagnetics studied by positive muon Uppsala-CERN precession SC66 Various experiments with the Omicron spectrometer Turin-Oxford-Amstcrdam- Birmingham-Llubljana- CERN APPROVED SPS EXPERIMENTS

E.\pcrmwn{ Ev/ii'riiik-M Cnlliibimilitm S umher

WA1 High-energy neutrino interactions CERN-Dortmund- Hcidclbcrg-Saclay

WA2 Lcptonic decays of hypcrons Bristol:Heidelberg- Geneva-Orsay- Ruthcrford-SLrasbourg WA3 Exclusive np aud Kp interactions Amslcrdam-CERN-Cracow- Munich-Oxford-Ruthcrford WA4 rhotoproduction of hadrons Bonn-CERN-Daresbury- DESY-Ecole Polytechniquc- Glnsgow-Lancastcr- Manchcstcr-Orsay-Sherficld WAS Backward two-body reactions Indittna-Saclay WA6 Polarization in pp and np clastic scattering CERN-Triestc-Vicnnn WA7 Two-body reactions at large DT CERN-Gcnoa-Orsay- Oslo-University College, London WA8 Production of rare meson states in K^p collisions University of Birmingham WA9 High-precision study of elastic scattering in the Coulomb inter­ Clermont-Fcrrand- ference region Leningrad-Lyon-Uppsala WA 10 Study of K*p -> K§rtäp and reactions of similar topology with Geneva-Lausanne high statistics NAl Comparative study of hadron fragmentation Frascati-Milan- Pisa-Romc (FRAMM) NA2 Electromagnetic interactions of muons The European Muon Collaboration

NA3 High pT leptons and hadrons CERN-Collcge de France- Ecole Polytcchnique- Orsay-Saclay NA4 Inclusive deep inelastic muon scattering CERN-Dubna-Munich- Romc-Saclay NA5 Inelastic hadron reactious using a streamer chamber triggered by Max-Planck Institute, a single-arm spectrometer Munich Fl;/i/fi" I Drul i of a miuiW SC schedule far iliscusshm ni ('«' «vi'U.v schedule meelimi. Il shows same ol'llie tiliiin ami seeiuuliirv user* in Noreinher and Dceendwr 1V75. :(i:n\-:^.iijy,

Synchro-cyclotron Machine Division

The successful completion of the reconstruction of the Synchro-cyclotron in 1974 Introduction enabled the MSC Division in 1975 to tackle the task of rendering SC2 operational for physics research. This work had to be done under conditions of staffing and financial restrictions and of increasing radioactivity of the machine, and progress in 1975 was not uniformly smooth. However, all the facilities of the rebuilt accelerator have now been put into service and nineteen physics groups are performing research or tests at SC2. During the year the pulse repetition rale was increased by a factor five and the beam current by an order of magnitude, reaching a maximum of 4.! uA.

In 1975 machine time was distributed as follows: SC2 operation Hours Nuclear physics 2757 Prime users' time, single and sharing 3609 Parasitic users* lime 2187 Technical development 1402 Breakdowns 1545 Maintenance, cooling and beam changes 634 Shutdowns 1952 Official holidays 470 Total 8760 Figure 2 — The Isolde Experimental Area after its reconstruction during the shutdown for the SC improvement. The four hewn lines pmrided simultaneous beams of different isotopes to ten expérimental groups in 2975. - (CERN-149AJ5)

Operation for physics increased from 726 hours in the first half-year to 2030 hours in the second and the ratio of physics to unscheduled down-time was doubled. In addition, the completion of the Dee repanelling during the spring shutdown made it possible to raise the internal beam currant from about 0.4 uA to an average of 2 uA and to put the internal pipn production targets into service. These factors have permitted a great intensification of physics research with several groups sharing beams or targets for most of the available machine time. The commissioning of the long-burst devices further increased the effectiveness of operation for physics. In addition to the normal internal targets a fast-moving ("jumping") target and an external liquid deuterium target were put into operation. Losses of machine time were principally due to vacuum problems or component failure caused by increasing radio-frequency power dissipated in the rotary condenser and to difficulties experienced with internal targets. The latter gave rise to appreciable radiation doses to personnel in spite of the precautions taken in the design and handling of the targets. A simpler and more robust version has therefore been prepared for use with intense beams. During the year all experimental areas were put into service and five reconstructed secondary beam lines were commissioned for use by the physics research teams. These included not only fourteen groups engaged on SC experiments but also five who are preparing and testing equipment for research at the ISR and SPS.

Studies of the characteristics of the rebuilt accelerator and of its accessory elements were carried out throughout the year and led to a progressive improvement in their per­ formance. In addition, much effort was devoted to the task of increasing the reliability of operation. The intensity and the betatron amplitudes of the internal beam were measured under various conditions. Both radial and axial amplitudes were found to agree closely with the design values. The transfer and extraction efficiency between 40 cm orbit radius and the extracted proton beam was raised from 50% to more than 70% by the elimination of a beam-loss during acceleration. The designers of the extraction system thus had the double satisfaction of verifying their theoretical prediction of a 73% extraction efficiency and of establishing a world record for beam extraction from a synchro-cyclotron. The extracted proton beam was focused to a spot of less than 3x6 mm2 at the position of the pion production target ; 88% of the beam was transported over a distance of 60 m to a beam spot of 1.2 citf at the ISOLDE target. Optimized operation of the pulsed field coil yielded a distribution of extracted protons of uniform intensity and 2 ms duration per cycle. This distribution is free from radio- frequency structure. The secondary accelerating system using the peripheral Cee electrode was brought into service and produced beams of 15-20% duty cycle. By eliminating leaks in the ion-source housing, by modifications of the filament and by careful control of the operating parameters, filament lifetimes were increased from 25 to more than 100 hours and a multifilament unit, permitting four Clament changes by remote control, has operated during tests in the SC. The performance of the main radio-frequency (RF) system was constantly improved. The Dee voltage was raised from 20 kV to a maximum of 24 kV and the RF pulse repeti­ tion rate from 25 to 120 Hz, thereby increasing the internal beam current from 0.6 to 4,1 uA. At Dee voltages below 20 kY repetition rates of 180 Hz have been used. While improvements of the vacuum • of the rotary condenser were principally responsible for this result, many other elements in the condenser, the generator and the electronic control system had to be redesigned to achieve it. However, much remains to be done in the discovery and elimination of weak points in the system before operation at the full repetition rate of 450 Hz and with 30 kV on the Dee can be attempted. The present performance is limited by the power rating of certain components and by defects in the mechanical construction which can be eliminated only gradually. Rotco Speed 404 Hz

Dee Volts = 21 kV

23 (kV) 400 Dee Volts Rotco Speed (Hz) Fhjim- ? SC2 irtmsniiKsion timl extraction efficiency a.\ a function of Dee minute Mut i fraie ot freiiwncv modulation. Al tiiflh Dee ToHaije or /i»» trequenc\ inttjulotiun rule lite efficiency exceeds ^evenly per eeni.

The repanelling of the Dee may be cited as an example: even prior to installation in the SC, some cooling circuits in the roll-bond panels covering the Dee and Dee liner had developed leaks owing to bad brazing. All panels were therefore replaced by welded elements during a two-month shutdown in the spring of 1975, but ten months of prepara­ tion were needed to effect this change. In order to gain a better knowledge of.the characteristics of the accelerator, the computer-based data acquisition system, which at present furnishes an alarm protocol, is being extended to enable it to accept, store and analyse selected analog signals indicative of the state and performance of the SC. The planned modification of the SC for the acceleration of 3He+ + and, possibly, deuterons and alpha-particles had to be treated as a matter of lower priority but important progress was made by the demonstration that a large turbo-molecular pump providing the vacuum for the rotary condenser could be replaced by a cryopump of modest dimen­ sions. This not only simplifies the constructional problems posed by the extension of the resonator required for 3He++ but may ultimately provide a convenient pumping system for the condenser during proton acceleration.

Other The French "Groupe pour l'Accélérateur national à Ions lourds" (GANTL) obtained activities authority to test the design of the injector stage of a cascade accelerator system at the CERN micro-SC. The MSC Division provided some assistance in the modification of the micro-SC required for this purpose. -'---.' = The Division also participated in the preparation of the Omicron project. This involves the construction, for use at the SC, of a spectrometer consisting of a large-

gap, 180 ton magnet lent by the Rutherford Laboratory, and "a wirerchamber detection system. A drilling rig, built for drilling a 22 cm diameter axial hole in the poles and yoke of the SC, was lent to the Synchro-cyclotron Group of the Institut de Physique nucléaire de l'Université de Paris-Sud and MSC Division personnel took part in the drilling operations at Orsay. Members of the Division collaborated in the development of a new type of Hall-plate which has a surface area of 0.2x0.2 mm2 and a temperature coefficient of 5 x 10 ~5 per°C. The Engineering Group undertook a large share of the design, construction and mechanical installation work required for the SC. In addition it designed and constructed equipment for the SC, ISR and SPS physics programmes. Items: of particular interest were the design of target installations for ISOLDE and of the deuterium cryotarget for the SCj the modification of the Omicron magnet, the design of beams-ahd'sévefaï large detectors for.the SPS programme and the manufacture of a superconducting solenoid magnet for use at the ISR. Nineteen iron-core magnets and three iron-septum magnets were constructed for SPS experiments. --'•:•---___""._-. The Division took Tin active part inr the: preparation'of the Seventh-International Cyclotron Conference, held at Zurich from 19 tO;22 August 1975 and presented eight communications describing various aspects of the SC Improvement Project. l-iftiin f> t.avmn ti( Hie SC2 expvntm'lifii/ it 1'niitw liuom sc iinii Ileum h> ihh I-.MII are provided l>v inraets in ttie SC Hull imiituitvd >>\ the rlvtiv\i ftrnhiH Ih'iiin. I'aritslilc Ivritdltitiuns iisinti ttie spent | II beut» in the SC Hull art- »unle in zone 5. In mlilitim Zone ii reeeires neiithins fnan a Ihjiihl deuterium toruet ilm»n)b ''»' " nwitiut .it 0 . Irrtitlitillms afstimples in tin1 muehine mi tank un also undertaken. mu! luis liven used for lite ntlihrutitni of u lurue neutron deteerut te\i>erniiei SC 5-il, -/.um- 7 ivivivt's pion immi.s t>J HHI hi -Ulli Mv\' fur a piun etipture experiment i Si t fif)i,is viinrntly uwil Neutron Urn •f/sir ».s a source ul liiwi'm'i'uy |i ' proilittvtl hr pit m th'im \n I lt\iltt I'liese wiii, are UH'd fur .solid stale similes- (e\penwenis SC (S,1! uitd SCfiSI, Ihutitis tw litis ivinti urv provided (win Internal u/i-flft.i. Tlte Imv-eiH'ray ploit vltanttel ihHPCt supplies 711 MeV phtts tu a pioit capture experiment (SC 5$I lit :mw I. 'Anne 2 Is fi'il In- the Vtidernniund Aren I2Ü Me\' cltiinml mill currently supports wteral parasitic groups its well a\ a mihi user sttidylnil piuniv ttmlimtunlv X-iars in hydrogen f.S'C (>Vl:tliesame I2Ü MeV channel ahu supplies pions ut a •.ennui arm. zone 3. llnaltv the \t ctintinet Is used tu provide |i~ hetiim of 50 m 21H) AM: mut it Tin- lull pnnim Ufiint exiruetedjrom the SC l> win u> the iiiiilenpintnd nrvit, zuite fl. »here it is usai 1 to bombard various mi-gets of the ISOLD fi sepiirurw favilit y. Other gi mips, however, uhn use this etui supply "in oj mu itM'rs installed on opposite units it} ,i tmtuiiei In zone 4 (experiments SC 21. men (or the siudy «I (mum iliw tu proton Iwmbardinenl (experiments SC 51 and SC $}>. Lnmb-shljt in \i'tnvsie helium, und SC 67, plim abMirpliiiit nit nuclei). proton /pion/kaon j\

\ negative muon

BremsstrahlungN

'•\ 1/ strange particle ,-' y'"~\ \ \ U ^ \ X J< \ INCOMING NEUTRINO I

rThird charmed neutrino reaction observed ~m^M "Gargantclle: the event shows the'expected r- characteristics of the decay_ of a charmedjjM particle, a positron (e^j plus u strange par~]^

, tïcle (W'.K produced in the vM interaction in -

\ ':; addition to the usual negative muon. Physics II Department

Track Chambers Division (TC)

As in previous years this report is divided into two main sections: physics results and technical activities. The physics results are overshadowed by the observation in Gargamelle of neutrino events with a positron and a V° in the final state. This unexpected result could be a manifestation of a much sought new quantum number — charm. Amongst the technical activities the first substantial experiment performed with BEBC has to be underlined.

60 Figure I — The construction of the ERASME .scanning and measuring units was completed in 1975. The photograph .shows one of the operator tables with the projection of a BEBC picture, and, on the left-hand side, the newlv ilecclopetl TV displav svstein which is to he installed on all ERASME units. (CERN-l'79.1.76)

Track Chambers Division

PHYSICS

Observation of a new type of reaction in the search for charmed particles Neutrino experiments Charmed particles. C*, have been looked for in the production modes

+ vM + N->u~ + C + hadrons v„ + N-*u+ + C~ + hadrons with the charmed particle decaying into strange particles via either semileptonic or hadronic modes. An event which could be evidence for charm was observed in the first run with the heavy liquid bubble chamber Gaigamelle, filled with heavy freon and exposed to a wide­ band neutrino beam at the Proton Synchrotron. The observed event corresponded to the reaction

v„ + N->n~ +e+ +V° + 7t" +evaporation protons. The negative muon was clearly identified because it decayed at rest and the positron signed itself through its characteristic radiation loss. The V°, although clearly associated

61 with the interaction, had an ambiguous interpretation and could have been à K% or a A. The total visible energy was 3.1 GeV. A special neutrino run was done this year with an increased PS intensity obtained by operation of the Booster. The aim was to pursue the search for charm in the semileptonic mode, i.e. with the simultaneous observation of a positron and a V°. A part of this run performed in August provided a second event in the form v„ + N-*u~ +e+,+ V° + 7t+/P + evaporation protons. The probability that these two events are due to asymmetric Oalitz pairs or Y-rays or due to a vc contamination in the beam — these are the main sources of back­ ground — has been determined very carefully and found to be 6 x 10 ~*. Furthermore a very strong correlation is observed between e+ and V° production, since only four events have been observed with a u" and a positron and no visible V° decay in the final state; without correlation, 107 events were expected. The last part of the special run took place in December and in the scanning of the first photographs a third event was found: v,, + N -+ u~ + e+ + V° + 7t+ /p + evaporation protons. These observations, which have been confirmed by an experiment carried out at the Fermi Laboratory in the 1. foot bubble chamber, filled with, a light neon-hydrogen mixture exposed to a much higher energy neutrino beam than Gargamelle, indicate the existence of a new type of interaction which, according to current theoretical ideas, could be a manifestation of a new quantum number — charm (Aachen-Brussels-CERN-Ecole Polytechnique, Paris-Milan-Orsay-University College, London Collaboration).

Strange particle production Strange particle production has been measured in neutral current as well as in charged current events. Assuming associated production, AS = 0, this ratio is: S NC +0.17 =0.34 SCC -0.09 which may be compared with the ratio for events with no strange particle production: NC —=0.2ce 2 ±0.03 (Aachen-Brussels-CERN-Ecole Polytechnique, Paris-Milan-Orsay-University College, London Collaboration).

Scmileptonic neutral current interactions Single pion production has been studied in freon with neutrino and antineutrino beams in Gargamelle. For each beam two limits have been obtained for the ratio R:

R = CT(V+N->V+N' + H0)/CT(V+N->U-+N' + 7C°) R = CT(V+N-> v+N'+ 7t0)/a(v+N->u++ N'+ 7t°). The limits come from two different ways of estimating the background produced by

neutrons. An upper value of the ratio, RmM, is obtained from an estimate of the background in equilibrium with the events produced by neutrons. The lower limit, Rmi„, comes from a background estimate derived from events in which a it" is produced, such events being produced almost entirely by neutrons. The two limits are, respectively:

(Aachen-Brussels-CERN-Ecole Polytechnique, Paris-Milan-Örsay-University College, London Collaboration).

Lcptonic interactions Recently a third event has been found which could correspond to the reaction

Vj. + e-tVj. + e. The background has been re-evaluated. It comes from the reaction v+n-»e~ + p (0.22 ±0.14 events) and from very asymmetric decays of isolated gammas (0.24+0.15 events), giving a total of 0.46±0.20 events. The probability that the three observed events come from statistical fluctuation of the background is < 1% (Àactien- Brussels-CERN-Ecole Polytechnique, Paris-Milan-Orsay-University College, London Collaboration).

Stopping antiproton experiment Resonances With the discovery of the J/i|/ particles, several suggestions were made that related narrow resonances should be observable in pp reactions, and from a total cross-section measurement in Brookhaven the existence of one such resonance was reported. To search for such new particles and study them, an experiment was performed in which an anti- proton beam of 570 MeV/c and of low dispersion was passed into the 2 m chamber using a superconductor to screen the return field of the magnet. As all the antiprotons either stopped or interacted, the cross-section as ä function of pp mass could be accurately measured. No narrow resonance with a width T equal or smaller than the experimental mass resolution of 3 MeV was observed with a limit of Ter < 12 MeV/mb (90% confidence) in the mass range 1898-1946 MeV (the published result gave Tq= 160 MeV/mb).' However, structures are observed in the total and elastic pp cross-sections but their interpretation in terms of a simple resonance is difficult The structure observed in the pp total cross- section can be fitted with a Breit-Wigner„(M = 1936+1 MeV,T = 11.8±2.2 MeV) and corresponds to a cross-section over a smooth background of (10.8 ± 1.5) mb. The elasticity,

defined as x=rfi,/riDUd, is found to be x=0.44-o;?|. In the hypothesis of a single resonance, it leads to a spin value i = (0.07 ± 0.025). This hypothesis however meets Iwith. . • the difficulty that one does not observe the expected signal in the charge exchange reac­ tion pp-»nh. Several interpretations can be proposed to explain these observations (two resonances of different-isospin, interference effects with the background or even more complex situations). In these conditions, the mass, width, elasticity and spiii given above,, assuming a single resonance, do not apply (CERN-Democritus-Liverpool-Paduà-Rome- Saclay-Trieste Collaboration). - —I 1

60 - K-p-WVK+K-

1250 events

40

30

Figure 2 — The mass-squared distribution of the (MC~ I system in the reaction K~p -* AK*K~ at 42 GeVjc incident momentum. The distribution shows two statistic­ ally significant enhancements corresponding toS* produc­ tion; their masses and widths Have been tletermined to be: M=(]S25±2.5) MeV. T~(2]±4) MeV and M = (2]29±5) McV. r=(2]±S) MeV (Amsterdam- 2.0 5.0 6.0 CERN-Nijmegen-Oxford Collaboration). N|2(AK-) [GeV2]

4.2GeV/cK"p In the reaction K"p-»AKK7t at 42 GeV/c, two structures in the (KKTI) system decaying mainly into K*K have been observed. Although the mass of the first, 1429±4 MeV, is close to that of the E meson, its width, 21 + 11 MeV, and decay characteristics are significantly different The second structure, peaking near 1520 MeV,

may help to clarify the confused f, Fx region. In the study of E* resonances in K~p reactions at 4.2 GeV/c, the parameters of the H*(1820) have been determined. Indications of the E*(203O) have been found and a new narrow E* at (2129± 5) MeV has been observed; its width is T = 21 ± 8 MeV. In the same experiment it has been confirmed that in production experiments there exist two £(1660) states, whereas evidence for only one is seen in formation experiments (Amsterdam-CERN-Nijmegen-Oxford Collaboration).

Search for charm particles using the Omega spectrometer Using a beam of 19 GeV/c JI~ mesons on a hydrogen target, two experiments, each with —2000 events/ub, were performed to search for charm particles: (a) with a trigger on K~ mesons produced with a transverse momentum >0.5 GeV/c, (b) with a K+ trigger. No charm particles have been found indicating a production cross-section of < 50 nb (performed by all groups using the Omega spectrometer). Comparison of reactions:meso n + p-> 3 mesons +p Diffraction dissociation The technique of partial wave analysis (PWA) or mesonic systems produced in four- body finalstate s has given a number or important results on diffraction dissociation. This work hasbeen extended into a general study or the reactions meson+p-^3 mesons+p where the dissociations studied were ji-ntnrc, Jt-»JtKK,: K-*Kmc and K.->KKK at energies between 8 and 23 GeV. Several striking similarities and a few important differences are observed: (a) The reactions are consistent with the assumption that the three mesons decay entirely into a 0* meson and a 0+, I" or 2+ resonance, e.g. nf, JtK*.

(b) The three-meson mass spectra peak -250 MeV above the effective threshold Qerr of the dominant decay mode and then fall off approximately as (mass)"3.

(c) The average spin < J > rises with mass according to < J > =0.55+ I.I Qefr. (d) The average orbital angular momentum <•€> increases according to

<-e>=0.75Qcff. (e) The three-meson states are produced dominantly in unnatural spin-parity states in M agreement with Pinil = PnilllI ( - 1) . + (f) The only natural spin-parity states found are the well established 2 resonances A2 and K*(1420). They have similar properties to the non-resonant unnatural parity states except Tor a dip at t = 0 in the do/dt distributions (Aachen-Berlin-Bonn-CERN- Heidelberg-London-Vienna Collaboration).

n+p-*(n*it*îT)pat16GeV/ c

1 1 i 1 1 1 Mtf -

Figure 3 — // is found that the average spin of the stales produced diffraclivety increases approxi­ mately linearly with the mass of the system pro­ duced. This is slwwn here for tlic 3n system formed in die reaction x*p -- (n^n+xr )p~at !6 GeVjc. . Tile spin and parity of the various (3nJ stales were determined from a partial-wave analysis (Aaehen- 1 I I J L Berlin-Bonn-CERN-Hcidclberg Collaboration). 1.4 1.8 2.2 (TTVITI eff. mass, GeV

65 Studies of the Jp = 1+ states of K*n, Kp and Kco Partial wave analysis of the (Kmt) state produced in K"p-»(K~it+it")p and K~p -> (K07i~ir°)p at 10 and 16 GeV/c has shown that there are two types of production mechanism with different polarization properties. The l+(K*7t) state approximately conserves helicity in the t-channel while the l+(Kp) state conserves it in the s-channel. The statistics of this.channel were doubled by combining the 10 and 16 GeV/c data with those of the 14.3 GeV/c K~p Collaboration. The previous results were confirmed and some important new results were obtained. In the (KIEJI) mass distributions the (K~ 7t+n") channel gives a flat-topped enhancement while in the (K°n_!tu) channel two peaks are observed near 12] and 1.37 GeV. From the partial wave analysis, it was found that the 1 + S state decaying into K*jt has two peaks at these masses and, in addition, the 1+S (Kp) state has a peak near 1.3 GeV. The phase of the l+(Kp) state relative to the 1+ (K*IE) state rises to a maximum near 1.3 GeV and then falls. As both the Kp and Ka> states are 1+ and are produced in an s-channel helicity conservation mode, it is suggested that both the Kp and Kco peaks observed near threshold are decays of a 1+ resonance. The da/dt distributions for 0" states were found to be-steeper than for 1+ states (Aachen-Berlin-CERN-London-Vierina and Ecole Polytèchnique-Ruther- ford-Saclay Collaborations).

Study of crass-over in it±p -> it±(7i A+ +) at 16 GcV/c as a test of Deck model predictions To check predictions of the Deck model, da/dt' distributions are compared for the reactions iE+p-HE+(7t~A++) and Jt"p -HE~(IE~A++). at 16 GeV/c, for mass (it~A++)^ 1.9 GeV. No cross-over in do/dt' is observed for the total sample of events. When the data are divided into two subsets, according to whether the value of the + + azimuthal angle 05 of the A in the s-channel helicity system is greater than or less

than ir/2, then cross-over effects are observed for each subset. For |Os| >f the "normal" result is obtained that the slope b_ of the da/dt' distribution for negative beam particles

is greater than that b+ for positive beam particles, i.e. b_ > b+. For [t\ < f the opposite b+ > b_ is obtained, a situation observed here for the first time in high-energy reactions. These results are consistent with predictions by E.L. Berger based on a generalized Deck model (Aachen-Berlin-Bonn-CERN-Heidelberg Collaboration).

Churacierisiics The Split-Field Magnet (SFM) has been used to study the properties of pp collisions at

oj large pL centre-of-mass energy of 52.5 GeV when one of the charged tracks has large transverse

crews momentum. The triggering large px track was emitted around 20° in the centre of mass at the ISR and Cerenkov counters provided a separation of pions from heavier particles. The most important results were:

(a) Leading particles (defined as having |X| >0.5) are still present in large p± events, but they do not give a diffractive peak near |X| ~ 1.

(b) When triggering on a large px track, a broad enhancement is observed in the opposite (i.e. azimuthal) hemisphere. When this triggering track is at non-zero values of the rapidity, y (actually it is y ~ 2), the broad enhancement remains centred aty = 0. (c) For triggering tracks with pj. ~2.5 GeV/c, the ratio of jt+ to (K+ and proton) tracks emitted is constant over the X range 0<[X|<0.4 (CERN-Collège de France- Heidelberg-Karlsriihe.Collaboration)^

66 Positive correlations are observed for pion pairs of equal charge and similar Determination momentum vectors, produced in the reactions jcp-+p + 5ît and up-+p + 7JI at 4 to of fire-ball 25GeV/candK+p-»K+p2it+2Jt-at8.2GeV/c. . \ dimensions The results are consistent with being due to second-order interference effects expected for pairs of identical bosons andean be used to determine the average dimension ..'---_. of the "fire-ball" from which the pions are emitted. . _.' It is found for np reactions that the value of does not vary, within errors, in .._._ the energy range from 4 to 25 GeV/c and.the value averaged over this energy range is = 1.6 + 0.2 fin. For the K+p reaction ~ 0.8 fm.. Attempts are made to study the fire-ball shape by selecting pion pairs emitted in various polar and azimuthal directions. Indications are found that the fire-ball may. be contracted, rather than elongated, in the direction of the collision axis, i.e. < R,,x < Rj. > (Aachen-Berlin-Bonn-CERN-Cracow-Heidelberg-Warsaw and Mons- Brussels-CERN Collaborations). . .

Real part of the forward scattering amplitude Two-body reactions Using multiwire proportional chambers and hydrogen and deuterium targets, the ratios of the real to imaginary parts of the forward nuclear scattering amplitude have been measured in 7t±p, K*p, pp and K~d reactions at a variety of momenta between 0.6 and 2.6 GeV/c. In general the results are in good agreement with dispersion relation calculations, though the data for K±p reactions require the value of the KNA coupling

Figure 4 —: DJj/LTiHMiu/ cross-section for K^p elastic scattering til 10 CeV/c in the cer\> forward direction of the scattered A"\ The plot on the left shows on an eiihirtjeil scale the region where Ijie Couionil) ami nuclear forces interfere constructively. From tins interference the t aim of the forward nuclear amplitude is déterminai These and similar measurements at 4 and 7 Gel'/c for bath K*|i and K'p elastic scattering hare heal made at the PS ftv the CERN-Cuen Collaboration.

K+p lOGeV/c

11 I I I I .1 I I I I I I I ' ' ' I I I 1 1- I 0 0.002 0.004 0.006 0.008 0.010 0 0.02 0.04 0.06 0.08 0.10

Momentum transfer t {GeV2ï constant to be larger than those previously suggested. The new value, in agreement with SU(3) and SU(5), is 21 ±2. This work has now been extended to cover the 4 to 10 GeV/c range where 2 x 10* triggers were accumulated (CERN-Caen Collaboration).

K~ p elastic and charge exchange scattering at 4.2 GeV/c Elastic scattering K~p -> K~p and charge exchange K~p -• K°n at 4.2 GeV/c are found to have differential cross-sections da/dt with some striking differences and some similarities. In the charge exchange reaction there is a dip near t = 0 and the slope is much lower than that of elastic scattering. Near |t| of 0.6 to 0.8 GeV2 both da/dt distributions showstructure (dip, change of shaped Over the |t| range of IS to 5 GeV2, both distribu­ tions have the same slope and the elastic cross-section is; higher by only a factor of less than two (Amsterdam-CERN-Nijmegen-Oxford Collaboration).

The reactions K p-+hjpcron + meson at 4.2 GeV/c Studies of the reaction K~ p -• meson + hyperon have given a number of important results. Studies of the missing mass squared distribution for the mesonic states produced with backward and forward emitted lambdas show that different sets of mesonic resonances are produced in the two cases. Detailed investigations have been performed for three sets of final states: (1) 7t°A, T]A, TI'A; (2)A, loA, K~p -> pATDetailed tests of this prediction have been remarkably successfulTor both pairs and, in the latter case, a study of p—io interference has enabled the prediction of zero relative phase to be verified. '.''--_ Strong exchange degeneracy predicts zero polarization in pA and toA. The data liave been found in strong violation with this prediction, the dominating natural parity exchange contribution to the reactions exhibiting a polarization close to unity. The amplitude analysis has isolated this breaking to that pair of amplitudes with meson helicity Ï. The quark model provides strong predictions for the structure of the production amplitudes leading to finalstate s (3). Generally the data were found to be compatible with these predictions, although in the case of ir~£+(Ï385) a significant violation was observed for t'<0.25 GeV2. The final state ir+£-(1385) was also observed for t'<0.25 GeV1, a process corresponding to exotic meson exchange, and an interesting possibility exists that the two observations are somehow related (Amsterdam-CERN-Nijmegen-Oxford Collaboration). Study or the reaction it* p -» p«A++ (1236) at 16 GeV/c The reaction it+p-»p°A++(1236) at 16 GeV/c has been studied and cross-section, differential cross-section do/dt', single and joint spin-density matrix elements are determined. For small t'-value, unnatural spin-parity (pion) exchange dominates, the natural spin-parity contribution being only a few per cent of the total. However, above t' = 0.2 GeVVthis latter contribution becomes approximately as important Its the un­ natural exchange. Strong correlations between the p° and the A+ + decay distributions are observed (Aachen-Berlin-Bonn-CERN-Cracow-Heidelberg Collaboration).

Inclusive production or resonances Reaction Recently, there has been considerable interest in the inclusive production of resonances, for two reasons: (a) the evidence for cluster formation and short-range correlation effects may be wholly or p—tly accounted for by resonance formation; (b) the decay of vector mesons into leptons observed in hadronic interactions. In 7t+p collisions at 8. 16 and 23 GeV/c, p° and f production has been studied. The p° cross-section is found to increase with energy so that the p°/it~ production ratio remains constant at a value of about 20%. This large value of 20% indicates that when one takes into consideration other resonances, p~, p+, in, etc., a large fraction of pions comes from the decay of resonances. Studies of p° production as a function of the Feynman x-variable and of transverse momentum indicates that some p° are centrally produced, but there is also a pronounced forward peak. The cross-section for the production of p° mesons is too low to account for the relatively large lepton flux observed (Aachen-Berlin-Bonn-CERN-Cracow-Heidelberg-Warsaw Collaboration).

Triple Reggc analysis A triple Regge analysis has been made of the reaction K~ +p -» A + anything at 4.2 GeV/c in the target fragmentation and in the beam fragmentation regions. In the former case the effective trajectory derived lies between the K and K*(890) trajectories and in the beam fragmentation case it is consistent with the nucléon trajectory. Many features of the beam fragmentation show striking similarities with on-shell pp annihilations (Amsterdam-CERN-Nijmegen-Oxford Collaboration). The reaction K+ + p-!-A+ + + anything, studied at 8.2 and 16 GeV/c, has given an effective trajectory consistent with that of the p. except at small values of the four-momentum transfer where a contribution of jt-exchange is detected. Comparisons with previous results on the similar reaction with incident K~ show strong similarities, and give an interesting test of the dual properties of the Regge-Mueller formula (Birmingham-CERN-Mons-Serpukhov Collaboration).

Impact parameter analysis of multiparticle production in meson-proton interactions Lower bounds can be calculated for the root-mean-square impact parameter b, in any

exclusive reaction. These lower bounds, bL, have been calculated Tor nine exclusive 7t~p reactions at 16 GeV/c and for 24 exclusive K~p reactions at 10 and 16 GeV/c. It is

69 found that bL decreases with increasing multiplicity, but is larger at higherenergy. The-

values of bu are larger for diflractive than for non-diffractive channels of the same multiplicity (Aachen-Berlin-Bonn-CERN-Cracow-Heidelberg-London-Vienna-Warsaw Collaboration).

Comparison of K° production with inelastic electron-proton scattering The inclusive reaction K+p-» K°X. at 5, 8.2 and 16 GeV/c was compared to the reaction e~p -» e"X. Assuming p dominance and the validity of the Callan-Gross relation, the structure function for K° production is obtained and compared to the similar function for electron inelastic scattering. The two structure functions show a remarkably similar behaviour, particularly in the region of small values of "the Bjorken variable oi (Birmingham-Brussels-CERN-Mons-Serpukhov Collaboration).

Correlations in rapidity space and resonance production Correlations in rapidity space have beênusedlo investigate-the,prpduction of clusters in high-energy collisions. At 16 GeV/c, the reaction K+p -> K°JC+X produces abundantly the K*(890) resonance. Is it possible to detect this resonance, considered a cluster, by an analysis of the rapidity correlations?The results, after several checks, are negative, thus opening to criticism the usual method of analysis, at : least in this energy region (Birmingham-Brussels-CERN-Mons-Serpukhov Collaboration).

Inclusive reactions in 32 GeV/c K p collisions Interactions of 32 GeV/c K~ mesons have been studied in the 4.6 m Mirabelle bubble chamber at Serpukhov. Single-particle inclusive distributions have been obtained for several types of particles, K°, A, A, y, JC+, Jt~, u°, and slow protons. Also, they have been derived for resonance production £(1385), A++, and A0. Correlations between two- particle inclusive reactions have been studied. The data were compared with those obtained at lower energies (France-Soviet Union and CERN-Soviet Union Collabora­ tions).

70 BUBBLE CHAMBER RUNS 1975

No. of Experi­ photos Beam ment Chamber [units Laboratories -~ - ' _ Daies_ No. of 1000)

Us „- 4 GeV/C 227 HBC200 402 Bergen, College de France, __ August

Ecole Polytechnique, "" ~ _.v Madrid, Stockholm Birmingham, CERN, usK~ 8J3 GeV/c 209 HBC200 °2S , August + - Glasgow, LPNHE (Paris) - November- December

UBP 7J GeV/c 237 HBC200 395 Amsterdam, Athens October (University and Nuclear Research Centre Dcmocritos) Liverpool, Vienna

Stétata HBC200 1717

U7 It" 22 GcV/c 225 BEBC so Bonn, Hamburg, Munich, March Oxford. Pisa, Rutherford Laboratory U- IE~ 22 GeV/c 241 BEBC 5 CERN, Saclay March + May wire chambers u, p 12 GcV/c 243 BEBC 320 Brussels, CERN, April-June Imperial Collets (London). Mons, Orsay

.Vnfadf« / BEBC 405 1 1 Civ. \*1 propane 214 Garçamelle 570 Aachen, Bari, Bergen. February +• + Brussels. CERN. June-July j1 PS Booslcr Ecole Polytechnique, Milan. Orsay. Oxford. Padua, Strasbourg, Turin, University College(London)

<-'- M freon 245 Gargamelle 250 Aachen, Brussels. CERN. August + + Ecole Polytechnique, Milan. December 1 PS Booster Orsay, University College ! (London) i

' Suhwn 1 Guryumi'Ilc S2tt

c (v. v) H Spark Aachen. Padua February + chambers June + behind August Ga ream elle

SubunjI

Distribution: 1 S37000 pictures Tor laboratories outside CERN. 2065000 pictures for laboratories outside CERN and CERN.

HBC=li>dro"cn bubble chamber BEBC =BJ£ European huhblc chamber. TECHNICAL ACTIVITIES

Software Work has started on software to organize and process data from hybrid bubble development chamber systems (external muon identifiers with BEBC and Gargamelle, and the proposed European hybrid system). Considerable attention has been paid to the layout of data structures and it is expected that the one proposed is a valid starting point for all the: hybrid systems under consideration. A fruitful collaboration with the users of the NAL 30" hybrid bubble chamber enabled many ideas to be tested with real events. A rejuvenated version of the standard TC Division maintenance program PATCHY has been released. In addition to a number of new interesting facilities, "the "efficiency of the program has been improved considerably, and the new version is machine independent. Development started one "year ago on an interactive program for multidimensional data analysis and has brought into existence a satisfactory operational version. Examples of application to particular physical problems are the analysis of multibody pp reactions by a Paris group and of multibody K+D reactions by a Mons-Paris group.

Spiral During 1975 the two spiral readers (LSDs) measured 305000 events (580000 vertices) readers of an experiment in the 2 m bubble chamber (K~p at 4.2 GeV/c), for, which the record number of 1000000 measurements has already been reached. The production was about 10% higher than last year. This gain was due to a simplification of the measurement criteria made possible by improvements introduced in 1974, mainly on-line pre-filtering of information. The low percentage loss of running time (due to breakdowns, tests or other causes) is another reason for regarding the spiral readers as reliable and relatively economical instruments. Thus the mark of 1 million events and 2 million vertices has been passed this year, as forecast. For this performance, which makes the LSDs the principal producers of measurements of bubble chamber film, credit is due mainly to the team-work and competence of operators, technicians and programmers.

Figure 5 — When the parameters of a test are changed continuously, the contents of a histogram vary as shown by this still picture. It is a simple example of applica­ tions of the interactive multidimensional data analysis program.

72 The construction of the ERASME units was finishedthi s year. About 140000 events ERASME of an experiment with, stopping antiprotons in .the 1 m. chamber, at incident momentum 600 MeV/c, were completely scanned and measured with ERASME, The measurements were started in January and terminated in August. Another experiment — Jt+p in the 2 m chamber at 16 GeV/c — was taken over from the HPD which has been closed down. 40000 events were scanned and measured within the first ten months of the year. Since a geometrical reconstruction program was used to control the measurement quality on-line, none of these events needed subsequent rerheasurement .. •-. --.--t ._--•• ;_.--,._;•'----.•-.'-'.:. Three other experiments have been prepared and started on ERASME: (a) pp in BEBC at 12 GeV/c (b) K-p in Mirabelie at 32 GeV/c (c) KTp in the 2 m chamber at 8.25 GeV/c.

The Split-Field Magnet proportional chamber detector operated successfully during Split-Field the whole running time of the ISR. Four groups took data, either as single users or in Magnet (SFM) multi-user parallel operation, when the equipment and the triggering system permitted. Significant improvements were made to the detector, particularly in the refinement of trigger schemes and in on-line and off-line filteringprograms , aiming at the selection of rare events. The physics results are reported under the ISR research programme of the NP Division.

Figure 6 — Event observed in the Split-Field Magnet. One A -*• n~p, one Kti -*• TCTC and 8 charged particles have been reconstructed front

a pp collision at v"s = 52ô GeV. The hits m the inultiwire proportional counters are indicated by circle*. The tracks given by the reconstruction program are shown as continuous lines. The dashed lint's indicate the path of the A and K° before decay ICERN-Collège de France- Heidelberg-Karlsruhe Collaboration ).

pp -> A+ K° -*- 8 charged tracks at Ys~ 52.5 GeV

o hit in MWPC

73 T beam tracks track residuals in BEBC

camera 2 22GeV/c TI" 12GeV/cPp 2 +10- '„'Àï', ,..l 5h.i^œ». ur.l»!!..!.'.1!!!?!'!'."!. i : : Q s-S»'•»;•'".,-|;rÄ™ -»;•;•;••• i- in 1-10. camera 3 400 is , «•10- * 1 • U 11 1 U 350' " ' • sä •' V-îfef «-SK^K.» Ü,--!U!-S5!? ft JJ.'SKfJiiS» - 0- ^^-^«äfr—w "SS -10- 300 --SS."

camera 4 250 1 ÏSS5

+10- i =i : •. .Li • » Ï !,: Î ! SCrib? •!. .'noss»? 200 ~ |§cS- 0- yc": :i " i'*jTif,'""1".i®!i!s£!Ka?r -10- . ' '• ISO camera 5 100 • *10- !!!:':'!:.= .' AssJ's.n-lffijiU'Jj'BiJäAj? 50 S"::5555 . !"; l'\ «Wan" '•' ! "•VA'»"' i'TVi-V," ' SÜSSSSCKSN -10- » . '

2 3 4 10 15 20 25 30 ï) track length (mj b) residua is [um]

figiin- 7 - Figure a) iftoiri the scattering of measured points alang 3.7 m long '•earn tracks (22Gel~!cn j trmvrsinj; BEBC. Tlie measurements plotted in the film plane of BEBC camera?, were dune uir/r ERASME and the rtns-scattcrs ohtaineil correspond to a setting ernir on points of 250 urn in chamber space. Figure b) slums a histogram aj residuals on tracks \rith momenta above 1 CeV/c in BEBC as obtained from ERASM E measurements and aeonietrical event reconstruction m the 12 Cel'.'c pp experiment T243. The peak value of the distribution at 5 um corresponds to < 3(11) um selling error on points in BEBC space. The sample comuins all tracks nu/i track leniilh rarylnu from a few cm up to3 in.

BEBC The end of 1974 was marked by the restart of the BEBC magnet, which could be run at its nominal field of 3.5 T without any difficulty. AH efforts then concentrated on the chamber in order to prepare a long physics run. The magnet was cooled down at the end of February. After a short technical run, 425000 photographs were taken: 100000 pictures with ir" at 22 GeV/c, 300000 with antiprotons at 12 GeV/c (search forcharme d particles) and 25000 for technical trials, with wire chambers in front of and behind the chamber. These trials were undertaken to gain some experience for the future external muon identifier where the measurements made in the chamber must be linked with those of the wire chambers. The quality of the photographs was, in general, good. Only rarely could distortions be seen with the naked eye. The standard deviation of the points measured around a well fitted trajectory is 250-300 um. This should make it possible to measure the momenta of particles to ah even higher degree of precision than that obtained in the 2 m chamber. The magnet was operated at its maximum field of 3.5 tesla throughout the run. The operation of a metallic piston caused no difficulties due to eddy currents in spite of the high magnetic field. In view of this satisfactory result, a final version of the piston, made either of stainless steel or titanium, can now be designed.

74 Figure S — Hydraulic expansion system: hl_' the ventre can he seen the tower end of the ? hydraulic jack to which the cold piston is coupled 'not risible). The big rectangular^ blocks arc very powerful servoralres (capacity"- 500 -£,>;, which are controlled hv smaller^ .wrrijid/to. risible in their magnetic shielding. ~ Each servorahe has two accumulators, aperat-;, inn »it n niiixmiuiii pre.siiire of 210 bar. The • piston performs the full cycle of expansion and *~: recompres\ion of the chamber in SO ms with a stroke of 120 mm. (CERN-S6SJ.75)

As a result of some modifications to the piston joint, there was very little wear, and very little dust was seen in the chamber after 800000 expansions. Two minor breakdowns occurred during the run, each one stopping the operation for two weeks. One breakdown was caused by a leak in the water coolers, the other one by a crack of a welding seam on the piston. Apart from these incidents, the reliability of the whole rather complex set-up (chamber, magnet, refrigerator, hydraulic system, cameras, etc.) was good throughout the four months of continuous running.

Future M-iif Overall new of the BEBC storage area. Three horizontal tUnvars of 50000 tttrvh each store the fitfiiiik (neon, hydrogen and deuterium) to be used for SPS e\ périment s. A \ounh dewar to which the chamber is connected is to be found further to the left, but h not rhible in the photograph. The vertical cylinders take the various

t/ti.M'% '.Vf. II2. D: K waiting for relique/action. To the right, in the background, a trailer with high-pressure aas bottles filled with neon can be seen. CERN takes delivery of 1.2 um* »»/ neon every three weeks. {CER.\-232J.?6 ) Figure 9(b) — Dermis of the front view of lite neon dewar with its controls. The transfer liivs, visible to the right, are Inter­ changeable and allow unv dewar required-to be connected to the chember dewar. (CERN-2303.76) -.-.--.- From 2 July, it was not possible to continue the 25 GeV physics in the West Area, which is being prepared for SPS physics. For BEBC this involves preparations to

use H2/Ne mixtures and a track-sensitive target. A first technical run is scheduled for early in 1976. The installations required for the use of neon are nearly finished. Eleven tons of

liquid neon are already in stock, enough to fill BEBC with a H2/Ne mixture of medium density. The neon stock is increasing regularly at the rate of 1.5 tons per month. The preparations for future use of deuterium continue also. The electrolyser for heavy water has been delivered and commissioned. It is now being run with ordinary water in order to gain experience with long-term operation of the plant before switching to heavy water.

Gargattwiie The runs during this year showed that some components of the chamber were deteriorating, jnainly due to aging. This concerns mainly the optics and the coating on the inside of the chamber body. Solutions to improve these parts of the chamber have been found and the necessary changes will be made during the time available for the reinstallation of Gargamellc in the West Area, where it will operate with beams from the SPS. The planning for this move and for the reinstallation has started. The chamber ran for 1120 hours and produced 920000 photographs. i

2 m chamber The chamber was moved 13 m towards the North to permit a more efficient use of the East Hall for counter experiments. On this occasion a big overhaul of the expansion system, cameras, refrigerator and compressors of the chamber was undertaken. The refrigeration system was modified; the safety sphere, 520 m3 in volume, is now incorporated as buffer volume into the refrigeration circuit at the inlet of the compressor. Therefore only metallic surfaces are in contact with the hydrogen while the gasholder with its non-metallic membrane is only used for gas recuperation. A major modification of the data box was prepared. It allows a shorter exposure time, 40 to 60 ms, to mark the data on film. During" the dismantling operations the chamber window on the camera side was slightly damaged; it was replaced by a spare window. The optical quality of the pictures taken with this new window is good, although its fiducial marks are not seen by all cameras. The precision of the measurements made since then on the spiral reader and ERASME does not seem to suffer from this shortcoming. The chamber started to operate on 27 June with JU" af 4 GeV/c. The run was interrupted for three weeks when a hydrogen leak had to be repaired. Afterwards the run continued and another experiment, K~ at 8.25 GeV/c, was started. Operation had to cease on 29 August, because of the fire which broke out at the PS, and could not start again before the end of October. This interruption was used for technical runs to check the feasibility of multiple expansions. These trials showed that the chamber can be made sensitive for each of 5-6 expansions separated from each other by 150 ms with a repetition rate of this multi-expansion cycle of 2.5 s. Parasitic bubbles, created at the inflatable gaskets, appeared in the visible region after the fourth expansion. Track distortions could not be checked

76 since this required ;i particle beam. The refrigeration capacity can cope with this cycle but the design of the inflatable gaskets would have to be changed if the chamber were to operate in such a mode. Furthermore, some changes to the system, cameras and data box would also be necessary. The 2 m chamber was stopped for the annual shutdown on 18 December having produced 1718000 pictures in three months of operation. The breakdown of pictures taken is as follows: experiment T227 it" 4 GeV/c 402312 pictures experiment T237 p 7.3 GeV/c 395 338 pictures experiment T209 K ' 8.25 GeV/c 921 157 pictures.

This service has three development machines of large capacity at its disposal which Film can work with all the various types of emulsion. A fourth machine has been installed development which has a smaller capacity but more flexibility for various purposes and can also do installation reversal development. A small computer to control this installation has been put into service. It is used to control the development operation and to check its quality. Some 2800 km of film have been developed in 1975 using 165000 litres of developer and fixer. The most important "customers" were: 2mHBC 1200 km Gargamelle 800 km BEBC 200 km Spark chamber (Aachen-Padua) 180 km EMI 50 km PS M14 20 km.

After the last year's results in obtaining high-quality tracks in a small hydrogen Gas discharge streamer test chamber, the construction and testing of a large chamber with a sensitive and multiwire volume of 55 x 35 x 20 cm3 was completed this year. This chamber consists of two cells, chambers separated by a central "high-voltage plane" made of a fine mesh with 50 um stainless steel wires coated with urethane painting. A new conical oil-insulated Blumlein line of 25 £1 feeds into the chamber high-voltage pulses of a duration of 3 ns at half width with a rise-time of 1.3 ns and an amplitude up to 700 kV. Trials of the chamber showed good quality tracks of cosmic rays in hydrogen and deuterium gas up to atmospheric pressure,

with an additive of ~ 0.5% CH4; the quality of the pictures obtained using an image intensifier is similar to He-Ne streamer chamber pictures but with 2 to 2.5 streamers/cm.

The development work on the H2 streamer chamber is now completed. A projection chamber, of 0.2 m3 useful volume, consisting of thick wires (the total mass of these thick wires is 200 kg) and its photographic readout, has been designed, built and tested. It is composed of a set of electrically independent modules that are arranged in such a way that the whole chamber is transparent along the "crystal planes". The double role of the thick wires as spark electrodes and conversion matter yields good spatial resolution. The high efficiency for many particles traversing the chamber at the same time, and its mass, make it well suited to be a detector for neutral particles and y-rays. This

11 Figure 10 — A xhonvr of mmiv hatirom front an inchkiu fast neutron in a vus tîiscîntrgi' chumher.

has been shown by a test run on the attenuation and shape of the hadronic cascade in iron from incident protons at 25 GeV/c. A project proposed for a system of multiwire proportional chambers has been studied and prepared. It is a system of multiwire proportional chambers intended as the central detecting apparatus, vertex detector, in a spectrometer for the study, for example, of

high pT interactions at the SPS. All construction details have been worked out after an exhaustive study of the geometrical and experimental conditions. An important aspect of the design is its optimization for track identification and reconstruction, particularly for large multiplicity events. There will be a total of 35000 wires. The design of this vertex detector has been finalized, the construction of one module as a prototype has been completed and tests have been carried out.

Beams 1 m chamber During the PS shutdown a new RF beam was constructed. The RF separator is composed of the elements of the dismantled separator that was used in 1974 for a 2 m chamber beam and in the first half of this year for the BEBC beam. This new beam has been operational since June. It separates K* up to 15 GeV/c and antiprotons up to 12 GeV/c.

SPS Neutrino beams Construction of the various components continues. The first quadrupole magnets of the narrow-band beam have been delivered. The equipment to measure the magnetic field has been assembled and tested, and it works as expected. The first power supply has been tested in connection with a capacitor bank of 100 kj and a discharge unit.

78 Future 11 — Construction of tin RF separ­ ator in the TC hull. ICERN-SUUO.75)

External muon identifier The manufacturing method for the chambers has been defined and production has started. The firstchambe r has been tested and found to work satisfactorily. The electronic circuits have also been completely defined and the corresponding purchasing orders are being placed.

S3 beam Two deflectors, which are 6 m long, have been constructed. They passed the high- power tests satisfactorily and the third one is now being assembled. The year has mainly been used to construct and assemble the various components of the separator. One of the three stations is completely assembled and undergoing long- duration tests in the laboratory. A temperature-stabilized RF line between the two RF "bulges" in tunnel TT60 has been installed as planned. A superconducting magnet combination is planned for the last horizontal deflection of this beam. The progress of the work on these magnets is described in the following section.

Two superconducting bending magnets are planned for the projected s3 beam from Low-temperature the SPS to BEBC These magnets are now being constructed. Designed for particle beams laboratory of up to 120 GeV/c the required deflecting power is 10.5 tesla metres per unit, to be

79 Figure t2 — One of the siipcmmductlmj bendimi tmifinctsfor the BEBC beam, reodv to he »mimed into /f.i helium cryotfut. Euch mannet will provide u heiulinii power of 10.5 teshi mart' ot a central field of 4.6 leda. ICERN-I5H.I.76)

obtained at a central inductance of 4.6 T in a "cold" bore of 74 mm diameter. In October the first unit was tested successfully in a vertical cryostat.

Liquéfier Addition of an expansion engine to replace the Joule-Thomson throttling valve of the central helium liquéfier increased the elTective output by about 25%. Liquefaction rates in excess of 80 -£/h arc now possible. During the year 1975 the following quantities of cryogenic liquids were distributed: 3570000 litres of liquid nitrogen 20 800 litres of liquid hydrogen 133000 litres of liquid helium.

St»

Theoretical Physics Department

Theoretical Studies Division (TH)

The scientific activity of the Theoretical Studies Division covers a very wide spectrum of topics which range from the investigation of the first principles of quantum field theories 10 the phenomenological study of the most recent experimental findings. In the field of research of a more fundamental nature, the study of scattering by massless particles and some important investigations in constructive quantum field theory should be mentioned. At the same time very interesting activity has been dedicated to general properties of scattering in non-reiativistic Schroedinger theory. Research in quantum electrodynamics has been very lively and has led to the study of eighth-order radiative correction of the renormalization group and of mesic atoms. The dual theories have found a renewed interest through the introduction of supersymmetric fields. A completely new family of models has recently been proposed. flic iivrcluriai of the Theoretical Sttaiies Division (CEIt^-313.3.76} '

Theoretical Studies Division

Tne experimental discovery of the narrow resonances (j — i(i) has strongly influenced the Division during the period in question. Theoreticians have tried to understand the unexpected phenomenon in terms of present theoretical ideas and to get from them inspiration towards future developments. These new phenomena still escape a simple interpretation; however, here at CERN — as in several other places — several schemes have been propose»! and a lot of interesting study has been dedicated to the consequences of charm, colour, intermediate boson, etc. The activity in this field has evolved into a collective enterprise (CERN Theory Boson Workshop) which has been an »citing experience in itself. The output of these discussions was a common report which was considered a valuable summary of the exciting situation. In addition to this, specific models to classify and ui.Jemand these new phenomena have been proposed. In particular, the charm and colour interpretations have been at the root of very interesting phenomenology. The quark-antiquark models have been investigated for all bosons on the basis of a specific interaction potential. The spectrum obtained in this way is satisfactory. The quark picture of elementary particles has been further applied to scattering piocesses and current-induced reactions. Quark confinement has been the object or much attention. In particular, the bag mechanism, and more recently the extended non-perturbative solutions (solitons. monopoles) of non-linear Lagrangians. have been studied.

83 An interesting approach to high-energy production processes which follows a topo­ logical expansion has been proposed. This leads, in particular, to the well known cutting rules in the Gribov calculus. This last approach has been consistently explored in the critical situation of the unity Rcggc intercept. Critical parameters have been calculated using techniques of statistical mechanics. A Pomeron with intercept larger than one was also explored and showed typical non- perturbativc effects such as spontaneously broken symmetry. A lan»e effort was dedicated to various aspects of hadron phenomenology, in two- body and quasi-two-body exclusive processes as well as in properties of multiparticle distributions. Special attention has been devoted to hard collisions. . The activities of the nuclear physics group have also been rewarding, especially in problems of hadron nucleus interaction. Also very interesting are the investigations on electromagnetic properties of particles and nuclei. m

ii •> • m v m m p p • » M

^•tfaSS

ftïSill

^1 F/* î/rj/çî up «i'm* nf thr i'ijuîpmaii aumtnu- îiavJfrr ifiL' i ublt'-iiawcl *m: 7/I-JV, il is ht im> îiin/it*;/ ilonn nnk hm wtilcr njtcr chanuat -J/valH.VHI I*J rt7iï»ïf corromv -.KiLiiîfK After- ii i;r,/v. /,* ni!! ÎM-1- îUrmuih iïjt;hi! ncuiTiiiizim} Proton Synchrotron Department

Proton Synchrotron Machine Division (MPS)

Although I975 had more than its share of the unexpected, it was also a year in which considerable progress was made towards the goals set by the research programme and the approaching completion of the SPS. For the first time, accelerated beam intensity appeared on the schedule as a programmed variable. The flexibility conferred by Booster injection has made this possible, opening the way to a significantly more efficient use of PS protons. Since the East Hall ejected beams have now been adapted for "inter­ mediate-intensity" operation, the Booster operated for more than three times the number of hours worked in 1974. During runs for the neutrino experiments, maximum intensity was sought, and generally 8 x 10': protons per pulse were successfully accelerated — with an appreciable amount of running time over the "magic" figure of 1013. Considerable effort has been devoted to providing the right kind of beam for injection to the SPS early in 1976, and this has so fai been accomplished without loss to the "25 GeV" research programme. Towards the end of the year, a beam of 7 x 1012 protons was iransporied as far as SPS territory. A careful examination of the limitations on future PS performance is being made, with due regard Tor the present economic climate. The fire which occurred in the cable tunnels in August completely stopped PS opera­ tion for four weeks, and seriously restricted it for many more. Apart from the direct it caused, a large quantity of electrical and electronic equipment was severely contaminated by smoke and fumes, and this presented a formidable cleaning problem. Staff of every description cooperated in the common task, and help came readily from other Divisions. Without all these willing hands speeding up the work, further deteriora­ tion would have been inevitable and more equipment would have been lost. The insurance companies* representatives were somewhat surprised to find salvage taking precedence over cash claims, and the sight of so much industrious alchemy temporarily supplanting physics was a memorable one to see. West Hall experimental physics with BEBC, the big European hydrogen bubble chamber, qnd the Omega magnetic spectrometer ended in July, so that preparations for experiments with beams from the SPS could begin. The work of the Experimental Areas Group towards SPS physics is dealt with in the part of this report devoted to Laboratorv II. kslisüe: J*~t*-£~

Fiijme 1 — .1 niurhlc monument w lost protons — the mitmml appearance of the uw internal dump taraet in tlw l'S, Marble i\ useil ta shield tili' radioactive Itilïji'l because the element\ <>! u/iidi if i* vompttseii ilo twt become so cirrivt' m heavier ones wuler high- enertfv honihardment. Mvrcorer, il can vastly he shaped to Jit aveitvaiely araiuttl lite t acmun chamber and the drive Mechanism i see h'iaure 6). The whole unit is mutinied on it trotlev which runs on the trucks visible in the picture for removal or installation. C'EK.V-Cy./ll.^'.

Proton Synchrotron Machine Division

THE PHYSICS PROGRAMME

After ihc long annual shutdown (Christmas to 19 February), the Linac, Booster PS operation and PS ail came back into action on schedule, and an ejected beam was ready for the for pliysics neutrino experiment fourteen hours in advance of the promised programme. The Booster has been used as injector to the PS for most of the year, and in consequence it has been possible for the first time to operate al a predetermined intensity in accordance with the vary ing experimental requirements. The additional decree of flexibility is doubly welcome, since an important part of operational policy is keeping down proton wastage, which, through radiation damage and induced radioactivity, can be costly in both money and manpower. The basic operational pattern for most of this year was simultaneous sharing between one of the two South Hall targets and slow extraction to either East or West Halls, with a few bunches used 10 supply the 2 m hydrogen bubble chamber and the g— 2 experiment.

87 A scheduled intensity of between 3 and 4 Tp per pulse (Tp=1012 protons) was accelerated, depending upon particular requirements of the run, and when supplying the 1SR the intensity of their alternate pulse was appropriately adjusted. Some periods used direct injection at 50 MeV partially or wholly, giving about 2 Tp, and Booster machine studies using the interleaved Linac pulse went on concurrently. During runs for the neutrino experiments the highest attainable intensity was sought; generally, this was. in. the region of 8 Tp, but it could be pushed up to 10 Tp under good conditions..Eighteen of the twenty bunches went to the neutrino ejected beam line, and the other two were used for the hydrogen bubble chamber and Tor slow extraction to cither East or West. Statistics or the year's performance are shown in Figure 2. Time lost owing to faults was slightly better than average, except for two major breakdowns. In May, forty-five hours of running time were lost owing to trouble with the power supplies of the focusing quadrupoles in the Linac, and in August, a fire in the South Hall Extension caused the loss of some five hundred hours. Besides the direct effects of the fire itself, widespread damage was caused by the fumes of hydrochloric acid arising from burning PVC insulation. Power supplies for the auxiliary magnet system.

Fitli"v _ Fmk-n'iuiii/ i/iriwoii of iht: PS \sar i24 himrs ;»'r (/crj iiml u Miinimirv of THE YEAR [&1£>0 k\ ili.'w.iiiwii-N«/-i.p.T,«iHiiiïi I97.ï.

STATISTICS OF OPERATION

{p.ulU : finaation 0(j percentage. iduduZnd beam intanhtty rmiv ving 1 opeAation Tp/pu&ie ) time, lo&t EXPERHENTAL THVS1CS : 84% 13.1Ï 2) (3.47)

3 -luiife S00 Metf injection ! 62% 76.35 2> 4.03 >

-ui-Ltli SO Mai/ in/ecüon zn 4% 1.93

(.(ACHIME DEVELOPMENT 16%

Tp = Teraprocon = 10,z protons mainly due to cable-tunnel fire; other faults ^ 5% (y 300 h) intensity programmed at "intermediate" level for most of the year. poleface windings and injection corrections, the hydraulics of the plunging fast kicker magnet, an electricity substation, timing circuits, numerous smaller items of equipment and even the fabric of the building itself were all affected to a greater or smaller extent depending upon their distance from the seat of the fire. Thanks to great efforts and a good deal of willing assistance from elsewhere (especially the SB and ISR Divisions) it was possible to restart within a month, at first with a drastically simplified programme. By December, operation was virtually normal, but everything will not be put back into order before the early part of 1976.

The slow-ejected beam complex in the East Hall was completely rebuilt between Experimental October 1974 and April 1975. The three primary beam branches are now housed in areas shielding tunnels adequate for "intermediate-intensity" operation, and six secondary beams are derived from the four targets employed. Intensities in the primary branches may differ by a factor of ten or more; the total is between 2 and 3 x 1012 protons per pulse depending upon experimental requirements. In the course of reconstruction, major improvements were made to the facilities available. A new building houses twenty-one rectifiers for beam transport equipment, transferred from other areas, and cables have been laid from two large generators housed in the South Area. The cooling water system was extended and its capacity increased from 360 to 510 m3/h. The construction of the beam lines themselves was also improved. More refined beam optics reduced losses at the splitting magnets, and provided an additional degree of flexibility in meeting experimental requirements for beam size and intensity at target position;. The vacuum equipment of all primary branches has been adapted for the use of metallic joints throughout. Prototypes of two kinds of quick-alignment support, for beam transport elements and instrumentation, were built and tested; they have now been installed in the vicinity of targets. For the whole reconstruction project, six target stations and eighteen exchangers for TV screens were installed, exhausting the stock in reserve. The tungsten targets used are protected from oxidation by a quartz coating, this being the best method found up to the present.

Two experiments have already been completed, and in November beams pI4 and pJ6 were modified for the installation of two new experiments, (K." p -» A°X) and (K+ n -» K.°p). The 2 m hydrogen bubble chamber started work in its new position in June, using an RF- separaled beam derived from a target employing fast extraction from straight-section 58. The West Hall beams ceased operation in July (after a short extension for "charm" searches with the Omega magnetic spectrometer) so that preparations for SPS experiments could begin. In the Soulh-East Area, the g-2 experiment alternated with Gargamelle neutrino physics, and, by transferring power supplies from the South Area, it was possible to run g-2 at the same lime as the East Hall beams. In the South Hall, three beams were in use for experiments and six zones for apparatus tests. In spite of fast turnover the test zones were crowded, and additional facilities arc planned for 1976. Of the nine electronics experiment beams available in the South and. East Halls, three are low-energy p or K using electrostatic separators. Separator equipment and beam transport elements have been prepared to furnish a low-energy K beam at ITEP (Moscow) for an experiment in the Xenon chamber (ITEP-Padua Collaboration). Six hydrogen targets and two polarized targets are in use in current experimental layouts. Special hydrogen targets are being constructed for SPS experiments. The well-known "CPS User's Handbook" has been replaced by a new and up-to-date version in a handier formal, entitled — to avoid confusion — the "CERN PS Experi­ menters' Handbook".

89 SCHEMATIC DIAGRAM OF PS EXTERNAL BEAMS AND EXPERIMENTAL COMPLEXES IN 1975

I;.../.-..' h,',im tn n/iiMfm./ li"in ^ir.iuihl-M'ilii»! U\ üiut irutïihiiti m unwell (i> slw Iti'vf Ihtll ulier,' u is

du uwJ mw nui hnunlh'*. .'n rivitw -./.m t'/i't lion, tnhl1';. uûtw W-l I'lu-liiin.

li »Hi ;, li'Hiil M\.t M'. .'iiil.ii \ hi\mr- Pt r »r Jo IS {n'l" i' Ivy Otm'tui nuiiiiwuc *fv./n»mi'h'j ; I. fr-f /,,.mi /

    J ni/ri r;J ftir^iT, cfii- uY-i'i./'iin /v.irji. u- HI-^piiiiUi-tl lltri-c iiinliL-\ . k~ up !o I(> t-icl t unit mihi- powibihllt'*: suppUnui the livilnnli-n huhhlc , J1.11.1/1.T HEM

    SOi'l II II I I.I.

    r.ir*h I HI Uu /uiiniv ,11e (/tTH t'J tr

    i.....'L M^ in,: N\mi* ,11; ,ltiu<-J ln>in ihr. hiuli'l '• . /MI.'I.Ü'M ^!<,:,„',Jp k' up ,'ii l; V (V'l t lllL/mli l,ir sloppi'il k'< s„ sfh'r!rtiim'Hr * • . - k W„ I ,

    CIRRE.NT TECHNICAL DEVELOPMENT

    Linac Since the performance of the Linac in 1974 was satisfactory, the available effort in 1975 was largely concentrated on careful maintenance, completing the planned improvements to the RF system, and making a few modifications, mostly concerning observation and diagnosis of beam behaviour. After a successful test with a borrowed turbomolecular pump, a set was ordered to replace the present trichlorethylene-cooled mercury diffusion pump system. Beam at 50 MeV has been satisfactory at the 50 mA level which was hitherto the norm. This year, using the buncher, 80 to 90 mA has usually been available, generally of similar quality. Operation was reliable, with the exception of a two-day breakdown of the quadrupole focusing system in the first tank.

    Vtl *\k20

    2m HBC

    GARGfiMELLE

    SPARK CHAMBERS

    / d31

    q12

    S'/i'u nivin'ii Iriitii tinmilil-wltiin t>.. ihf pnm.uy Iwam i1,,, t\ itirhU'tl inlti l/irtr brunche*-. i-nch iWr/l u fm-c/t'ï. lii'in uliuli Mv M t mithin /'itim\ ure i/rrnvj" p,„ it' K" • CI.VI' . ,

    iJ Miil/.-ii'J/triimm prnln;r> til rii"i (MM rm-rtjy: ' W"p pt'r pul->c. h., IK-Iirr./S ,11 5j nirtld pitidii, lull] illlil/i ' !tir K" "./.'(iJIi'S I • ,',. .- m> i» /" dVi i.- *•- il,iiihU>-liiainh v,,( li'tinicltr uiitilyiiiiti li\'ti-bihl\ ifi'ni w I,., I-IVIUÏHMII. tllll vptirtin-d K" . ji «MI..S (îi'l ."'.

    / iM I'inn.tfj /nun \jr,itt//ij-u\ nun 5*. r/mv /'I»MMI' Mri/i-l pc)-.i'lif)Fiv mu' il (/lime u/ rVii»i.-i /fir r/ii' _ in Intlfijtii ImhhL i fumfii'i j/s J\h—t-ptii\ilcd lluw (IJI iffcs < K' »p f<< /ft (u-l L dud ullifr pnwibilnw*.

    l >un m IIM' m Z1'"

    vu 7'/; i: l.sv ML l

    \L-imiu<- t'\;ii'riiiitii(. viprliL-il •»ii/i /TiniLin /it iim t'ft i hi /i/s/ cieiliiitt livm ^tiiiuflll-st'clitm 74. uml iisintf llw îit'urv liquid bubble i /uiui/vr "(iurtici'it-ik'" uml ti sptu k ihtiiuln'r tiswnkh: lfri'i'iiif:rr/i- i/ - J r\/>tTiiiji'ur »s/ui/1; sa i>iular\ bi\uu uj ,t m - 3 Gi'Wc denied Jroiv a turyi't in i\*.

    To meet the demands of the experimental programme, the Booster operated for most Booster of the physics running time in 1975. After a first run with record reliability (836 hours synchrotron with only about 2% down time) the accelerator continued to perform very steadily (average fault rate 3.6%), successfully meeting the varying requirements of the programme.

    91 Figure é — Q-diagram "f ''"' Booster, .showing the mast important slap-hands {nan-linear betatron resonances) causing cmiiumce blow-up. ami the programmed mtmmenl of the working paint durum acceleration. The large space-clmrge- imlttced incoherent Q-shift at injection was formerly accommodated by adjusting the lune to point A. just below the .systematic resonance JQi- = 16. IKift decreasing space- charge effects, the Q-ealues can he mured nmiy flam this resonance (A m Cj. The new extra windings »n the quadrtipnles now cnabie the starting paint to be placed al posi­ tion It — within the .shaded area which was previously mialtninalile heatuse of the thre­ shold currents of the main Q-tuniini supplies. This has a beneficial effect on horizontal emitlance blow-up at the highest intensities.

    During "intermediate-intensity" operation, pulse-to-pulse intensity modulation was provided whenever the ISR needed lower beam levels, and Tor the "neutrino" runs a steady 1.2 x 1013 protons per pulse were delivered to the PS. The responsibility for operation was transferred from the Booster Ring Group to the Operations Group in April, although Booster Ring machine specialists continued to act as Booster supervisors. This performance reflects the progress made in machine studies and improvements. The major problems have been omittance biow-up and longitudinal instabilities. The first is due to stop-bands combined with strong space-charge forces, and is avoided by a proper choice of Q-values. The range of possible Q-values has been extended since the beginning of the year by energizing extra windings in the main quadrupoles, which also allows the eight betatron frequencies to be individually tuned as functions of time. Whilst it somewhat complicates operation, this facility makes injection possible near to the difference line Qv~Qii= 1, a form of "skew" (or coupled) injection which can give some 15% improvement at high intensities. Better means of displaying the eight Q values and measuring beam omittance arc under development. The technique of "shaking" the bunches, to render them more stable longitudinally, continued to be used successfully in operation. However, at the highest intensities it is not sufficiently effective and leads to losses. After many theoretical and experimental studies, an active feedback method has been developed which damps the troublesome coupled dipole, quadrupole and sextupole modes. It does this by operating through the RF system on appropriate sidebands of the sixth and seventh harmonics of the revolution frequency. At the same time the search continues for the parasitic coupling impedances causing this instability. Another phenomenon which sometimes also occurs at the highest intensities is transverse instability; experiments are being made with an active damping system. The faster 50 MeV beam distributor was installed, together with its high-performance power supply, and successfully tested with beam. The last of the ninety-six additional Fiütirc 5 - 7iwt of tin- fire J5 n/im pu/.u'-~ liirmintj m'/uorA.s /i»r l/tf »t'U' I'LTIIVU/ distributor tliviilvui 5U Mfi' /ICWII /ft*invt'/i (hi- /i»jjr /itiii.sfcr rimt*. TV MM A vttmnil pulsi's pntthiccil /itiiv a particularly (itiml risï-timï j.s'lt Jiv) uni/ ßmiwss (with­ in ±0.5"^} />»' l/u-jr lauith of 100 p,s\ iC"ER,\"-2W./Jft)

    multipolc lenses, was delivered in October, and most or the installation work was completed by the end of the year; first tests with beam in November gave encouraging results. The vacuum system behaved exceptionally well, with an average pressure of 2 x 10 "s torr. Some improvements were made in the interests of higher reliability and quicker pump-down lime; for example, increased radiation resistance lor the turbo- molecular pumps, more precision in pressure measurements, and the installation of titanium sublimation pumps at critical points, such as tanks containing ferrite. When the SPS comes into operation, it will be the Booster's task to modulate, by substantial factors and in a closely-controlled way, the beam intensity and, possibly, the beam emitlance. The method favoured at present is to change the number of turns over which Linac beam is injected, and the necessary modifications and additions to the timing and programming systems are ncaring completion. The electronics for extending the dynamic range or the radial loop or the beam control system by an order of magnitude is being made and corresponding circuits for the phase loop arc under development. In order to be able to check the quality of the recombined Booster beam during operation, and to allow use of intermediate pulses for machine studies and performance development, the magnet deflecting the beam to the 800 MeV measurement line will be replaced by a unit that can be switched between pulses. The magnet design is finished, and the power supply is being ordered. Throughout the year steady improvement continued on the beam observation equip­ ment, the 800 McV transpDrt and measurement lines, and the Booster control equipment in the Main Control Room.

    93 Main Prtntm Studies of 800 MeV injection and matching continued. Thanks to a reduction in Synchrotron Booster transverse omittance, progress was made in improving the injection efficiency. More refined methods of analysis of measurement results, and more elaborate computer programs for quadrupole tuning in the transfer line, are being developed in order to increase reproducibility and improve matching. Modifications to the 800 MeV injection kicker substantially reduced beam losses, and work is in progress to widen its operational margins. ~ : ~. -.•-'•' Careful control of the configuration of the PS magnetic field is an essential pre-" requisite to obtaining accelerated beams of the quality required by the ISR and the SPS. Time-dependent compensation of second- and third-order stop-bands before transition has been progressively introduced; the working point is programmed at low energy so that it remains in a favourable location of the tune diagram during the space-charge- dominated period and is also suitably placed for transition. This resulted in suppression of the emitUince blow-up occurring before transition. In order to be able to control both the working point and the chromaticity after transition, new bipolar power supplies are being provided for the machine quadrupoles, and, of rather more importance, (he decision was made to adopt a new scheme for powering the polefacc windings. • The introduction of the new poleface winding (PFW) circuits will take place in two stages. In the first stage (1976), separate programmable power supplies will feed the PFW in the focusing ("F') and defocusing ("D") halves of the magnet units, and an.additional winding, using a third supply, will be installed in figure-of-eight form-around the two halves of each unit. The final configuration will only be achieved after replacement of all the present poleface windings by new ones, in which provision is made for splitting each of the "F" and "D" circuits into two. This will provide a total of five independent para­ meters, in addition to the main power supply, for control of the magnetic field. Work is in hand at present on all aspects of the first stage. As for the second stage, an order has been placed for the PFW sheets themselves, and the final configuration of the power supply and control systems is being studied. The new PFW sheets are compatible with the old ones, so that installation can take place in stages (scheduled for 1978 and 1979). A contract has been negotiated for the supply of ten spare excitation coils for the PS magnet Two spare bus-bar connections have been made at CERN, so that replacements are now available for all except four locations (where flexible cables would be used in case of failure). Power supplies have been ordered for the various elements being added to the auxiliary magnet system, and a building to house them, adjacent to the PS ring on the north side, has been completed. The electronics for the "supercycle" programmer of the main magnet power supply have been installed, and have passed initial tests (see "Further development and future plans"). Improvements to the RF system in the interests of.operational efficiency include installation of an additional accelerating cavity, better fault indication in the Control Room, and, nearing completion, a beam control system with a wide dynamic range. During the annual long shutdown, a major task was the installation of enlarged vacuum chambers in eight magnet units to accommodate the particle orbit deformations required for the "continuous transfer" ejection system. In the adjoining straight-sections, modified or specially built components, such as lenses, pick-up electrodes, etc., with suitably enlarged apertures, were installed. Most of the old sextupoles were removed,, in preparation for the installation of new compact units in the course of the year. Since the performance of the vacuum system has been satisfactory, with an average working pressure lower than 2 x 10~7 torr and an almost negligible failure rate, improve­ ments are only made when the opportunity oecurs in connection with new installations, and are generally directed towards facilitating maintenance in order to economize on both the time spent and the radiation dose received by the staff responsible. Whenever a magnet vacuum chamber is dismounted, a new one-piece pump manifold is fitted, and l>4 the whole assembly is rigidly fixed to the magnet unit. Alignment of straight-section equipment is thus simplified, and single-bolt quick-connect vacuum couplings can be employed. The number of vacuum seals is reduced, the delicate and poorly accessible C-rings eliminated and more space is made available Tor the modified poleface winding installations. The new internal high-intensity dump target (see below) has all these features, and. in addition, the vacuum couplings can be remotely manipulated in order to keep radiation exposure as low as possible.

    Above a certain interacting beam intensity, internal targets overheat, and this limit Targets could easily be reached unintentionally, when, for instance, another beam-consuming and ejection operation suddenly stops. An overload protection system has therefore been built which measures the energy received and withdraws the target when a pre-set limit is reached. For rapid beam dumping, a fast-operating target using a mechanical resonance system has been built and installed. It is mounted on a trolley and provided with its own shielding, in order to simplify maintenance and reduce ambient radioactivity levels. The first operational tests were successful. Two projects in the field of ejection are nearing completion; the extension of the full-aperture kicker, to provide an adequate margin of power, and the computer- controlled fast-ejection timing. The major components for the new slow-ejection septum extraction magnet for the East Hall beams have been ordered.

    Figure A The m*n- turret unit far me n/u'/l if i:* m.'ti'SMirj- to tlmnp PS burnt insUle the iieeelerutur. Quiek-ionneei nitiunii fltmifes anil the miter eatilititf /u/v.s can he seen: the ntpiti-.icltmi résiliant tlrite tn.Tlumism is enclosed tit the rear. When installed, it is shrouded in marble shielding tu ralucv jnJiwni radioactivity levels during PS maaihiuaut-piTimh '..we Figure J). (CEHX-275.10.75}

    95 Computer The IBM 1800 computer and its satellites have continued their limited but reliable control and services in control or the whole or the Booster and parts or the PS and Linac. Although instrumentation the IBM is now more than fall and reacts sluggishly, a Tew small but urgent tasks must still be given to it; the core memory has therefore been increased by a block or 16K (obtained within CERN at no cost). One of these new tasks is pulse-to-pulse beam modulation; the setting of parameters before each Booster cycle strongly emphasizes the on-line aspect of the IBM 1800, and, consequently, access to the computer will have to be restricted. : - .- - . i.., The computer-controlled low-energy magnetic correction system is being adapted to cope with pulse-to-pulse intensity modulation; hardware based on the use of autonomous function generators has been installed for this purpose. Equipment for controlling auxiliary magnet power supplies is being built, and requirements for the first stage of the poleface- winding project are being examined. The digital data acquisition system constructed for the beam position monitors in the Booster-PS transfer line has worked successfully. The new beam-loss monitors in the accelerator ring, using the aluminium cathode electron multiplier developed in collaboration with industry, have been successfully brought into operation with the analogue acquisition system, giving a pictorial display of beam losses. The digital part of the acquisition system has been developed and built, but its eventual operation will have to wait until the future framework for the control system has been decided. A monitor for use in slow-ejected proton beams of 107 to 109 particles per second is now functioning satisfactorily, and the digital data acquisition for it is being constructed. Two ionization beam scanners, built here for the Brookhaven National Laboratory, are now operating in the Alternating Gradient Synchrotron. Studies on vacuum-compatible radiation-resistant fluorescent screens have continued and the most successful (alumina activated with chromium or cobalt) are being used in a number of applications at CERN and other laboratories.

    FURTHER DEVELOPMENT AND FUTURE PLANS

    New Linac The project has made good progress during this year, although a shortage of staff in certain areas and deliveries which were either late or failed to meet specifications prevented it from reaching all the anticipated milestones. The contractors have handed ovsr the building, and installation of supplies and services is well ahead. All components or the 750 keV pre-acce!erator have been assembled, and commission­ ing is in progress. The design of the beam transport and matching system leading to the first Linac tank has been optimized, and prototypes of some components have been tested. A study programme using the experimental 500 keV beam installation has now been completed; besides providing valuable experience with measuring equipment, electronics and computer software, it yielded interesting information on the properties of the beam from the ion source. Specifications for the Linac accelerating structure were finalizedafte r checking against farther beam dynamics computations and model measurements, and alignment procedures have been defined. The tanks, and also a pilot batch of drift-tubes to test manufacturing techniques, have been ordered. Nearly half of the order for quadrupole lenses has been delivered, as well as a first consignment of their power supplies. Development and construction of the RF system is well advanced and a prototype of the power output stage is under test Tendering for the production of the drive

    96 Figur? ~ - The 750 Acl7 prc-aceelerator lor the new Lmac. In the picture, the "hoi'' end at the hah iciwnn rij/iuije-mit/np/viiH/ rectifier is >\'ipg earthed for sajety during mainlenaiue. Tlie larije lank in the back­ ground contain!* electronics for the ion M'lirce. which is iusi out ttj nViv on the right. >CERX-l23.4-75)

    amplifier is in progress, and all the other component parts are either at the final prototype stage or already in production. The vacuum system specification is complete. AH pumps have been ordered and a substantial proportion already delivered. The vacuum control and interlock system is being manufactured. There has also been good progress in the development of the control system. Production orders for more than half the required electronic modules have been placed and the two control computers have been installed in their final position. The first section of the control console and the central part of the CAMAC-based data transfer system have been commissioned. Development of systems software is well advanced, and applications programming is beginning.

    Preparations for ejecting a beam to supply the SPS — the "continuous transfer" scheme — are reaching their final stages. After passing satisfactorily the programme of measurements and life tests, the magnets of the "fast bumper" system have been placed in their working position. With the installation of a 2 m electrostatic septum, and a pair of large-aperture dipöles for the requisite orbit deformation, the equipment in the.PS ring is virtually complete. The fast bumper "staircase" wave-form generator built for the first trials of the system lias been renovated, and is being used for the current development programme. Installation of the final "staircase" and "pedestal" generators is well advanced; and first tests of the latter have already been made. Some concern had been felt for the durability of the thyratron switches, since similar models used for SPS equipment had suffered early failure; however, the generator successfully passed its life tests. The prototype of the large-aperture extraction (septum) magnet also came successfully through life-testing. Unfortunately, there is some delay in the delivery of laminations for the final model, which may therefore not be ready in time for installation during the long shutdown of early 1976. However, the unit at present-installed is satisfactory up to "intermediate" intensities, and its modified power supply has been tried out at various energies in a multipulsing mode. The final version of the power.supply is undergoing laboratory tests. Hardware and software problems in the control computer have caused some delay. Pirns have therefore been simplified, and features which can be classed only as "desirable" havj been given low priority. The whole ejection system has been tried out at low intensities with the equipment in its final positions, and no major problems have been found. Combined operation of the ISR and the SPS will require ejection at different energies in alternate cycles; this mode has also been successfully tested, including use of the beam transfer line, in collaboration with the ISR Division. The instrumentation for beam observation in the transfer tunnel has been installed and partially tested; equipment and interconnections for radiation safety, inter­ communications, program control, etc., which will be required for beam transfer, have been fully specified, and their construction is proceeding according to schedule. Extensive studies have also been carried out to determine the best method of changing the longitudinal structure of the beam, which is bunched in the PS at 9.5 MHz, whereas the SPS accelerating frequency is 200 MHz. Attempts to debunch in the PS at the transfer momentum of 10 GeV/c produce strong instabilities at.gigahertz frequencies, probably due to interaction between the beam and vacuum chamber discontinuities, resulting in a large increase in emittance. Effort was therefore directed towards trying to combine controlled blow-up of the bunches with increase of the r\ factor, using quadru- poles already employed when crossing transition (q = 1/Y,2, — 1/y2; 7 = E/E„). In the meantime, simulation studies on the PS before transition, and at the FNAL accelerator (Batavia), showed that debunching may well be easier to do in the SPS itself than in the PS before transfer; this will be tried out when SPS operation begins. The necessary modifications to the PS radio-frequency accelerating system have been made; beam control has been adapted to allow the voltage reduction and phase-shift required for debunching. A 200 MHz cavity has been installed to modulate the PS beam prior to transfer, and the behaviour of the pin-diodes (used to short-circuit this cavity during acceleration) in a radiation environment has been investigated.

    Operation When the SPS starts operating, the PS will function in a repetitive sequence of different cycles, each cycle producing accelerated beam with characteristics suited to the particular user. This sequence is called a "supercycle", and was illustrated in last year's Annual Report Its development is closely linked to the work on pulse-to-pulse intensity

    9S modulation, which is already partially operational. The next stage will require, besides a new timing system and sequence programmer, automatic switching of parameters for various elements, for example, the sensitivity of pick-up electrodes. The actual change of intensity can largely be obtained by altering the number of turns injected into the Booster, which is currently the means used to reduce intensity for the ISR; other methods, such as the use of a "sieve", are being developed as a second priority. ; _, Tests of "supercycle" operation as it is planned for 1976 were carried out towards the end of the year. Positive results were obtained, but it was evident that a considerable amount of further work on the operational aspects would be required. The static absorber, which forms part of the reliable high-intensity dumping scheme for the ISR/SPS beam line, has been installed, and design of the remaining components is proceeding.

    The various plans to ensure that the PS will perform efficiently its threefold future Development function have resulted in a sudden increase in the demand for controls, besides implicitly of the control including the use of several control computers. A number of isolated computer systems system exist at present, and the approaching use of the PS as injector to the SPS urgently demands the development of further applications, such as the control of complex programme sequences {as described in the preceding section) and the continuous transfer system, to which must be added the new linear accelerator. Conversion to complete and integrated computer control of the accelerator complex, comprising Linac, Booster and the PS itself, therefore raises a number of problems. Apart from the differing ages of various components, ranging up to nearly twenty years, and the need to keep the machines in almost constant operation, an integrated system must be capable of coping with some of the variants of historical origin without being unduly constrained by them, and must be able to accept step-by-step integration of the various subsystems. The year has been spent on an analysis of present and future needs; in a joint effort with all the groups concerned a catalogue of control functions has been produced, as well as a study of operational aspects, and a design philosophy is being worked out. Further studies concerned interfacing, communication between computers, modalities of transition between old and new system." and relative merits of different layouts. Since these studies are essentially iterative processes, they have proceeded at a somewhat slower pace than originally hoped. Renewed collaboration with the DD Division has brought two scientific programmers to join the PS effort, and a project proposal for an integrated control system is expected in 1976.

    The efficiency of the whole accelerating process through the Linac, the Booster and Limitations the PS has been the subject of a study analysing physical limitations on an increase of on beam beam intensity. It turns out that the various systems and components are quite well intensity matched, and there is no single major bottleneck, but a number of different effects converge to about the same limiting value. The study showed what would be necessary

    99 to enable the accelerator complex to realise its present full potential, which proves to be relatively inexpensive and may well result in an increase or intensity by a Factor of between 1.5 and 2 over the present maximum.

    Acceleration With the availability of the present Linac for experimental use when the new one of other comes into service, and the planned future mode of operation in which interleaved PS particles cycles serve different users, it becomes feasible to consider the acceleration of other kinds of particles. A preliminary study, embracing polarized protons and light ions, has been undertaken. As far as polarized protons were concerned, the study comprised collaboration with the Argonne National Laboratory on polarimetry and depolarization phenomena in synchrotrons, and the development of a higher-intensity source. The study is being wound up, owing to the redefinition of priorities consequent upon the present economic situation. Deuterons were first accelerated in the Linac in 1964. New tests this year yielded an output current of 8 mA, and in a further trial with fully stripped helium nuclei 0.5 mA was obtained. Extension to the PS (and, in the event, to the ISR and SPS) is largely a radio-frequency problem; it requires acceleration in two steps with a change of harmonic number in between. The technique has been tried out on protons with success. For other ions lighter than neon, information is being sought from laboratories with experience of suitable ion sources, and a prototype electron beam source, capable of producing fully stripped light ions which could be directly accelerated by the present Linac, is being studied.

    100 applied Fiiysicä

    ••P^/^V^,

    Wfifft'- '•*• • ' • * vî 1 £>£ *.. î,* v -v* ,; ^^Hp ^.•A ----•* -^ ^> HM^^'* ^Kft"'-V* &ÊÊmp''ï WÈÊÊ*,

    •22 *2*2#22#2 •••52 2 ••22 Applied Physics Department

    Data Handling Division (DD)

    Introduction Considerable effort this year has been put into planning the development programme of the Laboratory's computing facilities for the next four years. The development pro­ gramme, approved by the Scientific Policy Committee in May, calls for: (a) a doubling of" installed processing capacity to meet the needs of the start-up of the SPS physics programme in 1977/1978; (b) construction of a data communications network on the CERN site with high-speed links to the central computers for data sampling from experiments and with medium- speed links for file transfers between computers on site and also to laboratories in Member States through normal post office lines; (c) installation of a new computing facility, from a manufacturer other than Control Data, with a mass storage system and high-density magnetic tape units and capable of providing data sampling facilities via the network to selected experiments from 1978 onwards. In June, the Finance Committee approved the purchase of a second CDC 7600 computer for (a) above, and the purchase of Modular Computer Systems and Norsk Data small computers for (b). At the same time, a request for information concerning (c) was sent to manufacturers. Following the June Council session, when the Directors-General were requested to propose a long-term programme for 1976-1979 consistent with an overall budget reduction of 3% per year, the computer development programme was re-examined as part of the general review of the scientific programme. It was proposed to retain the three elements of the development programme, but to implement each part with a reduced configuration and with a slower and more selective build-up of services than previously foreseen. The Scientific Policy Committee at its November meeting approved this revised programme. However, at the end of the year no contracts for the supply of computers for any part of the development programme for improvements to the Laboratory's computing facilities had been signed, in view of the decisions made at the December Council session concerning the Laboratory's budgets for the years 1976-1979. During 1975, the central computer service on the CDC 7600 unproved over the acceptable level achieved last year, both in the amount of central processor time available and stability. Two major software introductions were successfully completed, one on Figure 1 —- The upcraton' rinr of the CDC /ÎH7 anil 669 lape unit*. '(CEns-330A.ur,)

    Data Handling Division

    the CDC 7600, the other on the CDC 6500. The most important improvement in the services has been the successful build-up of the INTERCOM terminal service which is now being extensively used in the Laboratory. The Data Handling Division has continued to give support to the experimental physics Divisions with the ERASME, Omega and Split-Field Magnet (SFM) data handling facilities, with support for specific experiments, and by the development of new data handling methods. The Scientific Information Service continues to provide the central and branch library services and the document reproduction services for the Laboratory.

    The computer centre Central computing The computing service provided by the interlinked CDC 7600, 6500 and 6400 com­ facilities puters has continued at an acceptable and improved level under an increased workload. The mean time between deadstarts in the combined CDC 7600/6500 system averages nine hours compared with seven hours in 1974 and the workload averages about 15000 jobs per week compared with 13000 in 1974. New record weekly levels have been achieved for the mean time between deadstarts (25 hours), achieved production (151 hours), 7600 central processor time used (118 hours), and the number of tapes processed on the 7600 (3230).

    103 Tape processing with the new CDC 669 and 667 tape units has continued with a fourfold reduction in the incidence of parity errors, compared to last year when the 659 and 607 units were in service. A special "closed shop" service for tapes only used internally m the computer centre has been established and is providing a further fourfold reduction in parity errors. The on-line, computing service provided by FOCUS on the CDC 6600/3200 has achieved an availability of 98.5% during PS/ISB runs to date. As the CERNSCOPE service was terminated at the end of this year, FOCUS access to the CDC 6400 and 6500. and hence the 7600, had already been implemented, in order to provide a smooth transition for the on-line users. The CDC 6600 was withdrawn from service at the end of the year as part of a programme of rationalization of the services offered by the computer centre, and to effect a reduction in current operating expenditure. The machine had been in operation for eleven years, for most of which it carried the major part of CERN's computing load, and, apart from the difficult first two years, had provided good service. The CERN-developed SUPERMUX concentrator, introduced last year to provide high-speed terminal access to the file editing, job-submittal and interactive computing facilities of INTERCOM, has been expanded to some 35 fully backed-up terminals. In the course of the year, INTERCOM has been consolidated into a major service of the computer centre. The number of users has grown linearly to one third of the total number of users of the 7600/6000 computers, the number of logged-in sessions has doubled in six months and use of the central processor has trebled in the same period. The spectrum of applications which regularly use the service is very broad. As a result of the high demand for resources the service was switched from the 6400 to the 6500 computer. The development of the SIGMA interactive graphic system for applied mathematics is now completed. SIGMA, running under INTERCOM, is used extensively within CERN and has also now been installed on ten other sites on computers from several different manufacturers.

    Figure 2 — Suinc of the high-spcetl terminals connected to the SUPERMUX amienlratur. ICERS-2S2A.1J6I

    104 New versions or the CDC standard software for both the 7600 (SCOPE 2.1.2) and the 6500 (SCOPE 3.4.3), together with all associated CERN modifications, have been prepared, tested, and successfully introduced. These systems allow for the interconnection of up to four CDC computers and provide support for new CDC peripheral equipment. Collaboration-with other_CnC_users, in Europe in particular, has proved mutually adv;intageous.:The CERN modifications to CDC SCOPE to provide 7600 job-scheduling are in' use at other 7U)0 European installations, including the University of Bologna, the UriiVersityVof London; and-Saclay. A CERN utility for file copying on theGDC 6000 - machines has been sent to users in Holland, Spain, and the USA. In addition, a,very useful facility for debugging FORTRAN programs has been obtained from the University of Manchester and installed at CERN. A system of user registration and control has been successfully introduced; and a scheme for budgetary control of the computer usage is being introduced. Performance analysis of the CDC 7600 system has continued, and.a cross-compiler for the BCPL high- level language between the CDC 7600 and Norsk Data series mini-computers has been completed.

    Applied mathematics The development of user programs for the CERN program library has continued. Machine-code inner product routines, optimized for the CDC 7600, have been written. The function approximation routines have been revised and several programs for approximation over discrete sets of data points have been added to the library. Several of the Harwell routines for function minimization have been adapted for the CERN library. Statistical routines for the standard test procedures, for regression analysis, and for the generation of random numbers from the most commonly used distributions have been written. Consultancy work has included collaboration with the NP Division on the problem of detector acceptance corrections, with the TC Division on pressure calculations for BEBC, using the full Navier-Stokes equations, and with the MPS Division on the determination of measurement precision for current distribution in the Proton Synchrotron beam. Other activities have included studies in the fields of multidimensional integration and multidimensional data analysis.

    Data processing for bubble chamber film The joint DD Division/TC Division project ERASME is reported on by the TC Division. Collaboration with the TC Division is continuing on the proposal for a rapid cycling bubble chamber for SPS experiments.

    Data processing Tor electronics experiments Omega and Split-Field Magnet data handling system The data-link software on the CII 10070 has been improved to support more data links and remote compilers. The Omega analysis programs have been modified to recognize 6-prong events from the charm search experiment The on-line system continued to support Omega until the West Hall was shut down in July. Further improvements to the system hardware and software, to handle the new detectors and the higher data rate requirements or Omega at the SPS, are under way. A detailed study of the data handling requirements of the European Muon Collabora­ tion SPS experiment in the North Area has been made with the experimental groups concerned, and the design of the on-line computer system required has been completed. For the Split-Field Magnet (SFM) facility, the on-line data handling system now

    allows simultaneous operation of several experiments. After the shutdown of the West ; Area, the EMR 6130-used-for~Omega was moved to the SFM, which now has, two EMR 6130s and two HP 2100 computers being used by experimental groups. During 1975, a RDP-11/20 was added to the system as u central control and data distribution facility and this is connected to each or the experimental computers via a CAMAC-CAMAC data link. There are now two methods of on-line support used by the SFM groups, the Hewlett Packard computers being linked to FOCUS on the central CDC 6600, and the PDP-11 and the EMR computers to the CII 10070, shared with Omega. In the course or the year, large-scale data analysis continued and the computing for the Split-Field Magnet used 25% of the total CDC 7600 central processor time. Consequently a major effort has been made not only in the development of new methods but in the establishment of a fast, and operationally convenient, program chain for the data analysis. An automatic production scheme, of generalise, which keeps.track of a large number of jobs and tapes, and which automatically re-runs jobs which fail because of a system error, has been developed. In addition to several improvements in the overall track finding, a new facility has been introduced for the detection of neutral decays. The SFM programs have also been modified to allow a search for secondary vertices, and to handle muons traversing lead absorbers.

    General

    A comprehensive histogramming and plotting package HBOOK lias been completed and added to the CERN program library; it has also been distributed to many laboratories and institutes throughout the world and is being used on a variety of computers. The development of analysis programs for several SPS experiments is under way. The development of special hardware processors for a variety of applications is continuing. Processors for track finding and coplanarity checking (to improve trigger efficiency) are being built, and the processor for the 1SR spectrometer has been brought into use after it had been verified by its output being compared with results obtained by processing the same data using a conventional computer program.

    The TABLOID data base management system has reached a most satisfactory level of reliability. Effort has been directed towards consolidation and extension of the wide variety of applications which now regularly use TABLOID in production. New and improved versions of the GD3 graphics package and of the PERT network analysis program have been added to the CERN program library. In collaboration with the MPS Division, programming assistance has been given to the PS pole-face windings project and to the revised PS computer control system. Work continued this year on the general problem of gamma-ray imaging. Fast, two- dimensional proportional chamber readout was successfully demonstrated, and, in collaboration with the University of Geneva, two 10 x 10 cm2 chambers for the positron annihilation project were constructed and are now in operation. Extensive studies have A . . '" Figure 4 — .'I scini~mtttnmitic iiiiu-liine fur wirc-nrapping. Umltr numerical control hy a punched paper tape, a "fork" guttling the \rire-\rrtippiiig tool h positioned in .front of the phis in their sapience af ciimicijuhi. The wires needed are prc-cut: the tithe front which lite Kite /n/r la he taken i.s indictiled hy a liglti. iCERS-i4ft.2.761

    Figured One a] the two high-demur drift >fiuinhei-\ nine tu UM' til Geneva t'niverxity lor the ik'tection of gumma ray1, midline flom positron annihilation. The rhanther »tiiv aw-trm ted at Cl:l(,\ in du­ ll est Workshop. ;Ch:RS-27S.lll ~>.'

    been made to analyse the feasibility of constructing detectors for low-energy gamma-rays and for neutrons. The chamber and readout experience gained to date is now being applied to the problem of detection of very high energy photons (GeV) for the European Muon Collaboration. A precision refractometer to be used in connection with Cerenkov counters at the SPS has been completed. Studie* of the optics and data handling requirements of the Cerenkov effect spot focusing counter have also been made for the NP Division. In the field of computer-aided design and manufacture of printed circuit boards, a CERN working group has made recommendations and. after an analysis of tenders from industry, selected equipment. A semi-automatic wire-wrap machine has been installed and the programs necessary for the production or standardized cards and crates have been written.

    Library Scientific Information The programs needed for the library mechanization project have now been completed Service and are being used for some specific applications, such as various lists of periodicals and lists of institutions and address's. The integration of these programs to form a system Tor interactive cataloguing is in process. The organizational details of computerization of the book order and acquisition procedures are also being worked out. The system is being used to provide paper tape of bibliographic records and abstracts of CERN reports for input to the International Nuclear Information System (INIS).

    107 Figure 5 — Part of the rim printing production Une in Building SKI. ( CERi\-X?.l.7(i i

    Independently, the existing data base of bibliographie descriptions of preprints and reports together with the DESY High-Energy Physics Index lias been made available on the central computer system for information retrieval using the ÏNFOL 1 language.

    Exchange or publications Twenty CERN reports were issued, and reprints of 312 publications by CERN authors in scientific periodicals were distributed. Publications are now being exchanged with 734 institutions and libraries in 60 countries.

    Document reproduction Approximately 54000 pages of typescript were reproduced in offset, making a total of about 32 million printed pages, and 17000 slides were provided. The functional regrouping of the production line of the printing services, made possible by the move to Building 510. has resulted in greater efficiency in the operations of the section.

    10S

    ISR Department

    Intersecting Storage Rings Division (ISR)

    Introduction Because of the great interest in searches for new particles and studies of lepton produc­ tif«/ summitry tion at the Intersecting Storage Rings, high luminosities at high energies have been demanded for most of the physics programme this year. About 70% of the physics time has been at 26 GeV, with luminosities up to 2.1 x 103' cm"- s~'. The total integrated luminosity for all physics runs during the year was 5.3 x 1037 cm-2 compared with 1.9 x 1037 cm"2 for 1974. Operation at these high intensities, with low backgrounds, has been achieved by the development of a series of complex techniques that are described later. Of the total operating time for the year of 3175 hours, somewhat more than three quarters was spent on filling and colliding-beam physics and less than one quarter for setting up the machine and studies on its performance and behaviour. Fourteen colliding-beam physics experiments have been taking data during the year at six intersections; five of these experiments have been completed. At intersection 1-7, a newly installed experiment has benefitted from the operation ' there of the low-beta insertion (described in the 1974 Annual Report) which has provided luminosities up to about 4 x 1031 cm-2 s_1. Extensive preparations are in progress for the installation next year of two new large-scale ISR experiments. Studies on the design and performance of large storage rings have continued by a few of the stalf and by some limited part-time effort in the Department, elsewhere at CERN, and at other laboratories. Both proton-proton and electron-proton collisions are being explored and some attention has been given to proton-antiproton collisions. Several members of the Department have participated during the year in study groups that have been evaluating projects for storage rings at other laboratories.

    110 cnrf2sec~1

    1971 1972 1973 1974 1975

    Figure I Record luminosities in the 1SR.

    Intersecting Storage Rings Division

    Observations on beam behaviour Performance of the ISR The methods that were introduced towards the end of last year for increasing the luminosity of the ISR and reducing background radiation have been consolidated for alJ general operating conditions and, although there have been no spectacular gains, there has been steady improvement in performance during the year. At 26 GeV, luminosity for physics runs has increased to 2.1 x 1031 cm'1 s_1 and maximum stored currents have reached 36.7 A. Improvements at other energies have also been made; with the beams accelerated to 31 GeV, luminosities of 3.4 x 1030 cm-2 s-1 have been attained. Under­ standing of the behaviour of ISR beams has progressed and three effects, described below, have received particular attention. Observations of the top parr of a stack, which is close to an integral resonance, have shown a transverse blow-up while beam is being injected into the other or into the same ring. This has been found to be due to an overlap of the frequency spectrum of the bunches on the injection orbit with the betatron frequencies in the stack. The fields created by the bunches interact through some coupling impedances with the stack in the same ring; they also interact in the intersection regions with the stack in the other ring. In the

    111 ISR, the spectrum of these fieldsoverlap s with the betatron frequencies present in the top part of the stack, RF knock-out occurs and blows up the stack. This effect can be reduced considerably by increasing the bunch length and, thereby, reducing the high- frequency content of the bunch spectrum. A reduction of longitudinal phase-space density is observed during the stacking of beams. Extensive measurements ,of:this;eJTect and observation^ high-frequency signals indicate the presence of an internal high-frequency instability in the ISR similar" to the one observedjn.the_PS.jThe stability criterioji normally applied tojunbunched beams can also be relevant for bunched'beams if the instabilityoccurs atyery.high frequencies-ana if its growth is fast compared with a phase-oscillation period. The'local values ofbeam current and energy spread then determine the threshold of the instability. The presence of a stack of particles surrounding the bunches increases the stability and this effect, together with an optimum choice of RF parameters, can be helpful in obtaining high densities in a stack. From observations of this instability, the longitudinal wall impedance at high frequencies was estimated to be |Z/n| ss 20 ohms. This number is not inconsistent with the measured inductive impedance at lower frequencies and with the transverse impedance obtained from observations of the "head-tail" instability. With the improved vacuum system and the resultant low average pressure, the produc­ tion of electrons by ionization is so low that the loss of these electrons by collisions with protons contributes substantially to clearing and electron-proton instabilities are rarely observed. The electrons trapped in the beam produce observable noise on the pick-up monitors that can give information about the rate of this clearing. However, the electrons sometimes produce local spots of neutralization of the beam and, thus, a local change in the space-charge Q-shift. This change in focusing has a low superperiodicity and can widen stop-bands. When this effect occurs, high-order resonances can be observed on the Schottky-scan monitors.

    Limitations to performance, remedies and anticipated improvements The performance of the ISR is still subject to three basic types of limitation that have been known for several years. The first one is the beam-induced pressure rise in the vacuum system. Indicative of recent progress is the present stability of beams of over 30 A. achieved by increasing the pumping speed and by glow-discharge cleaning of a greater number of sections of vacuum chamber. The second problem concerns transverse coherent instability and the fact that the stabilizing tune-spread is limited by low-order non-linear resonances. A working line close to the integral resonances, known as ELSA and introduced towards the end of last year, has been used successfully throughout this year. Based on theoretical relationships between the required correction and beam parameters, the continual compensation of the space-charge tune shift during stacking is now made by the computer, on-line, using the beams' actual density distribution as obtained by the computer from the Schottky-scan monitors. However, use of this working Une has brought a new problem called overlap knock-out that has been described in the previous section. As a remedy, certain correction procedures, mentioned in the previous and the next sections, are being tried and a special high-frequency feedback system is under consideration. For general transverse stabiliza­ tion, the feedback system of 50 MHz bandwidth (mentioned in the 1974 Annual Report) has been tried successfully but it is not yet in general operation. It could permit the use of another working line where the overlap knock-out is negligible or, if the overlap problem can be overcome, could result in higher stacked currents with the ELSA line. A third limitation is due to the finite particle density in the longitudinal phase-plane. Dilution of this density occurs immediately after injection of beam into the ISR and is almost certainly due to the longitudinal instability at very high frequencies mentioned above. Because contributions to this instability arise from the electromagnetic properties of every variation in cross-section of the vacuum chamber around the ring, a radical cure is not possible short of a complete rebuilding of the vacuum envelope. However, considerable progress has been made by optimizing the RF programme during the stacking cycle and local densities compatible „with beam currents well above 40 A have been obtained. The actual maximum current reached so far is 36.7 A. To make use of the full increase in density of beams from the PS when it is operated with its Booster, compensation is needed for the additional beam loading on the RF system of the ISR. A system for providing this compensation was described in the 1974 report. Good progress has been made this year: modified upper halves for all RF cavities have been installed in Ring 1 and other components are being delivered and assembled on schedule. The low-beta insertion, consisting of a system of steel-copper quadrupoles installed in intersection 1-7 last year, produces a local decrease in the effective beam height and, hence, an increase in the luminosity at this one intersection by a factor of 2.3. The system works well and is currently in use for a physics experiment at that location. However, this increase represents the limit obtainable with conventional quadrupoles. A similar local improvement in luminosity by a further factor of about three is possible with super­ conducting quadrupoles. Plans for such a project have been drafted but the implementa­ tion has not yet been decided.

    Working lues, resonances and coupling effects The working line ELSA, which gave improved luminosity and reduced backgrounds at 26 GeV at the end of last year, has been developed for other standard ISR energies, both with and without the operation of the low-beta insertion. The problems related to the

    proximity of the integral resonances QH,Qv = 9 have been studied and special procedures have been developed to correct orbit distortions which are amplified at the top of the stack. The beam blow-up, due to the overlap knock-out previously mentioned, is considerably reduced by the use of special RF parameters and by a shift of the working

    line of AQH = AQv= —0.015 during stacking. These effects are particularly important when the low-beta insertion, which breaks the symmetry of the machine, is in operation. A similar but longer working line ELVA, with the stacking region extended across seventh-order resonances, has been used for reaching maximum currents during machine studies. The working line that is used for acceleration to 31 GeV has been modified to incorporate the technique of dynamic compensation of space-charge detuning. Further investigations of special working lines and adjustments to working lines are continuing. The general technique for compensating space-charge detuning during the stacking process has been improved. In the past, it was based on pre-calculated corrections applied at successive intensity levels. Now, the rune corrections are calculated on-line and applied by the computer; they are based on data, also obtained by the computer, from the longitudinal Schottky scans. The current density is determined for each 5 mm bin across the aperture and all structure in the stack, such as holes and tails, is taken into account. This approach provides the flexibility needed for the very wide range of ISR operating conditions and is more accurate than attempts to match a pre-calculated theoretical modeL The main magnet's poleface winding system provides the means for adjustments in the tune of the machine and it is now being used to its maximum capacity. In order to Figure 2 Coherent r»w iîlatums oj ISR huant in Ihe presence of coupling A/HI» n aller a kick lui.\ been ghen to the beam. Measurement* (if the eoiiplme coelhcient can lie ohlalnctl from luch truce-: Upper Irate oscilhl[wii\ in the plane perpemlh alal­ ia the k iek. /.(HUT trace o\cillation\ in the plane parallel to the kick.

    increase both the capability and flexibility for tuning procedures, a project to provide additional quadrupoles has been approved; the required quadrupoles and their power supplies have been ordered. For a physics experiment to be installed next year, a solenoidal magnet will surround intersection 1-1 and its axial field {the first in the ISR) may introduce serious coupling effects. Theoretical studies on linear coupling have shown that skew quadrupoles can compensate effects of axial fields;th e theory was extended to cover all resonances excited by three-dimensional fields. The influence on luminosity and machine performance has been examined, and schemes for measuring and compensating linear coupling have been developed. Some measurements of the coupling now present in the ISR have been performed for certain critical resonances. For these measurements, a kick is given to the beam and the modulus of the linear coupling coefficient is obtained from a simple relationship between the period and magnitude of the resultant modulation of the coherent oscillations in the plane parallel to the kick.

    Developments in the vacuum and electron-clearing systems Efforts to raise the vacuum stability limits in the ISR have continued, chiefly by methods used in the past. Still more sublimation pumps have been installed and critical regions in the vacuum chamber have been treated by 350°C bake-outs and by cleaning chamber surfaces by argon glow-discharge. The result has been an increase this year in maximum currents with stable vacuum to about 30 A in Ring 1 and 32 A in Ring 2. The average pressure in both rings is about 7 x 10"12 torr (nitrogen equivalent) and no individual gauge, of the 250 in operation, indicates a pressure higher than 3 x 10"lI torr. The lowest pressure in the whole machine is 4 x 10~13 torr in the upstream arms of intersection 1-8 where four liquid helium cryopumps have been in operation since April. Experiments have also continued for increasing the understanding of the basic phenomena involved in vacuum instabilities. Surfaces of materials for vacuum chambers, which have been given various preparatory treatments, have been subject to extensive

    114 analysis both in the laboratory and in test sections installed in the ISR. Analyses, more sophisticated then hitherto, have been made of the residual gas in the chambers in the presence of high-intensity beams. The large amount of information that has been collected is still under study. The clearing-electrode system has, as its primary purpose, the removal of electrons produced by the proton beam's ionization of the residual gas but the system's usefulness has been extended to the measurement of very low pressures during the operation of the ISR. The clearing current is proportional to the ionization rate and, even though this is now very low, a measurement of the sum of these currents in a sector of the vacuum chamber can give a good value for the pressure in the 10~12 torr range where most gauges are unreliable. A system for refining these measurements by monitoring the electron current from individual clearing electrodes is under study.

    Statistics of operation After the usual long shutdown at the beginning of the vear, th"? ISR started operation smoothly on 4 March. The operating schedule this yeir lias been characterized by very intensive running periods alternating with shutdown^, about four weeks long, in April, June and August, that were required for installations of new physics experiments. The shutdown in August had to be extended by about four weeks because of two consecutive accidents. The first was the collapse of a new titanium vacuum chamber at inter­ section 1-7 and somewhat more than a week was needed to replace it by a stainless steel chamber (already made as an alternate) and to replace, clean and repair adjacent damaged components. The second was the fiie at the PS. Part of the lost time for physics was recovered by the end of the year. Total operating time for the ISR this year has been 3175 hours, of which 2425 hours were for filling and physics runs, and 750 hours for setting up the machine and for studies of its performance and of beam behaviour. About 10% additional time was scheduled but was lost because of equipment failures, lack of beam from the PS, or external causes such as perturbations in the 18 kV power line. The distribution of time for colliding-beam physics at the various beam momenta, and the values for beam currents and luminosities, are shown in the following table.

    Mtimt-nlunj Kumtini; Beam current himmosiiy timû ruruje maxima average'! r,-r.- per ct'iu amperes tlll'Vni !i '

    11.8 0.8 4- 5 0.4 0.35 15.4 13 8-15 3 2.2 22_S 3.4 22-25 13.2 10 26.5 69.S 13-31 21 10 3Î.4 9.8 8-14 3.4 2 Different in each ring 3-2 special runs at low luminosity

    ISR staff also operated the beam line from the PS to the West Hall for 2056 hours until this line was disconnected on 2 July. Figure J — Logarithmic display in the ISR control room of hack-ground measurements taken downstream of each of the eight ISR intersection points.

    Running conditions for physics This year the ISR physics programme has been strongly influenced by the recent discoveries of new particles. The ISR experiments concerned with searches for new particles and with the investigation of lepton production have required the maximum luminosities compatible with acceptable backgrounds, which may differ from one experiment to another. The relatively numerous long shutdowns scheduled this year for new installations have not been conducive to good performance since the complexities of operation now required need very careful and lengthy procedures. In spite of this, many good physics runs have taken place. As a result of the developments in working lines described in other sections of this report, and of now standard procedures for centring the beams within the vacuum chamber, typical currents for physics runs have been around 25 A with luminosities up to 2x 10" cm-2 s"1 and beam-decay rates of a few parts per million per minute. Occasional cleaning of the beams with scrapers has maintained good conditions in all intersections for 48 hours or more. With such long runs, some problems were experienced in the middle of the year with accidental beam losses due to power fluctuations and occasional equipment failures. The monitoring of interaction rates and background by scintillation counters that have been installed at each intersection has allowed rapid optimization of conditions at the start of a physics run. Some control of the distribution of particle loss has become possible with the installation of vertical collimators. By the help of such techniques, experiments at the Split-Field Magnet facility have been able to use luminosities some­ what above 10" cm-2 s"1 but at these intensities the appreciable percentage of double events starts to become a problem. Towards the end of the year, vertical separation of the beams was used successfully to limit the luminosity in the Split-Field Magnet while keeping it high elsewhere. Increased luminosities at 31.4 GeV/c have been of advantage to many experiments. The low-beta insertion at intersection 1-7 has been made operational during the year and the new experiment installed there (R 702) has been able to benefit from luminosities up to about 4 x 1031 cm-2 s_1, the effect at the other intersections being small. For an experiment measuring elastic scattering at very small angles (R 805), special beam conditions have been set up. An interaction diamond only 25 mm long was provided by the combined use of radial shaving at injection and the operation of the Terwilliger focusing scheme. Information on the interaction diamond, obtained with proportional chambers of the experiment, was transmitted to the ISR's control computer via the Data Link. The use of dump blocks and collimators to absorb the beam halo has allowed this experiment to bring its scintillator-counter hodoscopes to distances as small as 7 mm from the centre of the circulating beam. During the special runs for this experiment, scraping procedures were repeated at about ten-minute intervals to maintain the required beam quality with little disturbance to other experiments taking data.

    Operational improvements and equipment behaviour Methods of controlling and monitoring ISR components and special observational equipment by the Argus computer have been greatly extended to the point of overloading its capacity for access and storage of information. The performance of the computer has been impaired by this overloading, sometimes to the extent of impeding operation of the ISR. To alleviate this situation, a project has been defined and approved for adding iome computers to perform certain specific large-scale functions now handled by the Argus, such as the handling of the data library and the monitoring and control of the vacuum system and the numerous magnet power supplies. The system for damping vertical errors at injection has been modified to increase reliability and ease of operation. To overcome the disadvantages of the moving aluminium screens that protect stacked beams from the pulsed stray field of the injection magnet, a static screen is being developed and one of the inflector tanks will be equipped with these new screens for assessment under operating conditions. For orbit measurements inside stacked beams, the system for monitoring beam position has been modified and its electronics are being improved. Several improvements and modifications have been introduced in the RF system which have increased reliability. These include a new program generator, and modifications to the amplitude control and closed-loop matching systems. Minicomputers are now used on-line with the RF system for performing calibrations and tests. The bunch-to-bunch feedback system is operational in both rings. The reliability of the very-high-stability magnet power supplies and their remote controls has been fairly satisfactory but systematic effort continues in order to eliminate weak spots. During the year, improvements were made on tile medium-power rectifiers and a similar programme for the low-power rectifiers for the main ring is in preparation. Following the fire at the PS. a spare pulsed power supply (of the TT2 line) was modified to feed the PS poleface windings. Without this supply, it would probably not have been possible for the ISR to be fed with 26 GeV beams before the end of the year. During the June shutdown, the 0.5 Q. 60 kA beam-dumping system was installed in Ring 2 and has operated reliably from the start. The system for Ring 1 has been assembled in the laboratory and is being tested. Remeasurement of the survey-pillar system was completed so that the evolution of the pillars' position over the years can be followed. The necessary measurements and realign­ ments of the ISR magnet system were completed.

    Experimental areas in 1975 Experimental Fourteen physics experiments have been taking data during the year at six inter- „ tha IS att the ISR sections of the ISR and five of them have been completed. As a result of the loss of scheduled running lime for ISR physics, owing to the PS fire, several experiments that were expected to be finished this year must continue into next year.

    117 1-7 PRODUCTION OF SINGLE ELECTRONS 1-6 AND ELECTRON PAIRS (R 7021 SEARCH FOR CHARMED PARTICLE PRODUCTION (R 6051 1-8 VERY SMALL ANGLE ELASTIC SCATTERING (R806I ELECTRON AND PHOTON DETECTION WITH ARGON CALORIMETERS IR80BT)

    -1-1 SEARCH FOR MULTIGAMMA EVENTS (R 107) 1-4 ISOBAR PRODUCTION (R101) SFM DETECTOR IR-103T) SEARCH FOR NEW PARTICLES |R 406) *\I-2 STUDY OF EVENTS WITH A LARGE PARTICLE PRODUCTION • COINCIDENCE PT PARTICLE IN THE FORWARD BETWEEN SMA' '. ANGLE AND WIDE DIRECTION (R407/R40B) / ANGLE SPECTROMETERS IR206/R 2061 CORRELATIONS WITH A LARGE 1-3 DIFFRACTION DISSOCIATION AND TRANSVERSE MOMENTUM FORMATION AT SMALL MOMENTUM SEARCH FOR MAGNETIC TRIGGER AT 90° (R410/R413) TRANSFERS (R207) MONOPOLES IR 3011

    /•''»»I'i'J ISIt e\periiiienn in /''".

    At intersection 1-1, experiment R107 (search for multigamma events) with a large array of lead-glass counters, multiwire proportional chambers and hodoscopes, was fully installed at the beginning of the year and has been taking data with various geometrical configurations of its detectors. These detectors are retractable, by remote control, to reduce damage from radiation during periods of beam stacking or machine studies.

    Ft^ure S E\perimenl It 1117 itt^itil/eil til tiller- ••ctltori 1-1. The titrée urrtiv oj tteleiuir\ on emit side ol the inler\eelitm * slum n /uirllv relrttt ledt lire removed by renmre i nnlitil Hi retint e diniltttn' /nini radiiiliaii during perinth til henni shitkiin; antl niiijiiiie slttdies : CI.I\X-276.J.7:~,

    US htitlin wilii tin- \/m lininrh-i ut I'V/XTÎ- m,/)/ /v-r'/.i ;n>r„'U;h>u lilt- rfi,'A; 11/ W M lilt- WIITU'I ?;/;t! hctiiil* and flu- mtn\ihlc t t'.tinhi'ii jtid /mt/mi i»/H\ a! I'lPiTtiKcnl A'-//" m ..//,W on lh< cw/t" wr/t' nj the \-ihl-l i-l.l \l.i«ncl i I «N-/r«."'.

    At intersection 1-2, experiments R205 (wide-angle spectrometer) and R206 (small-angle spectrometer) continued their joint correlation studies until the middle of the year. Then, the equipment of R205 was removed and that of R206 was modified and rearranged to create two small-angle spectrometers, one on each side of the intersection, for experiment R207 (diffraction dissociation at small momentum transfer). A new thin-walled vacuum chamber was installed at the centre of the intersection to fit inside the barrel-shaped hodoscope. At intersection 1-3, a ferromagnetic, passive detector has been fitted around the inter­ section's vacuum chamber for experiment R301 (search for magnetic monopoles). At intersection 1-4, experiment R406 (search for new particles) was fully installed at the beginning of the year with a massive array of some 300 large counters around the Split-Field Magnet facility and this experiment took data at high luminosity until the end of July. In the spring, the last of the central, close-packed, detector chambers were installed inside the Split-Field Magnet, thus completing the facility's full multiwire pro­ portional chamber detector system and it has been in operation for the rest of the year. In June, the wide-angle spectrometer, which had been used for experiment R205, was moved to 1-4 for experiment R413 (selective large pj trigger for the Split-Field Magnet). For experiment R410 (study of particle correlations at large angles), large-angle movable hodoscopes and proportional chambers were also set up in midsummer and this experi­ ment has been taking data in conjunction with R413. New improved versions of the atmospheric-pressure Cerenkov counters for experiment R 407/408 (two-particle correla­ tions in the fragmentation region) were installed at the Split-Field Magnet for use in the second half of the year. Experiment R401 (isobar production) has also taken further data at the Split-Field Magnet. At intersection 1-6. experiment R605 (search for charmed particles) continued from 1974 with an improved configuration of its electron arm at 30° that consists of a magnetic spectrometer, drift chambers, lead-glass and threshold Cerenkov counters. The main magnetic spectrometer, equipped with muon filters, is in the forward region of the inter­ section and there is another muon-detector arm at 55e on the side opposite the electron arm. At intersection 1-7, where the low-beta insertion is located, experiment R702 (search for charmed particles and electron pairs), with twin magnetic spectrometers at 90°, threshold Cerenkov counters, drift and proportional chambers, hodoscopes and lead-glass counters, has been set up in steps and data have been obtained with partial installation of the Figure ' Klectton-spectrometei ai ms of experiment K?U2. installai at W on each stile it! the inter \ei ting (warns at inter­ section 1-7. Each arm consists of drift ehamhers. analysing magnet with a Cerenkar counter inside its gap, und an array of lead- glass counters thai require heavy shielding against radiation. In the ccntw foreground can he .seen some a/ the tputdrupalc.s of the hm-heta insertion installed at this intersection. ICFJIS-77.I ?rti

    equipment. Special magnetic shielding has been added at the intersection to prevent disturbance to the circulating beams. At intersection 1-8, there arc two experiments: experiment R805 (ratio of real to imaginary part of forward scattering amplitude) and R806T (large transverse momentum phenomena with transition radiation detectors and calorimeters). For R805. the new

    Tigun- ,S' The iithium transition-radiation detectors and the large liquid organ athiri- niL'ters of experiment RS06 T are shau n above and helow the intersection at l-S. At W to the intersecting beams, shown port tally withdrawn, are the monitor ma, proportional ihamhers of experiment Rc.,)5. special re-entrant vacuum pots (described in the 1974 report) were installed to allow detectors to be brought very close to 1SR beams, cryopumps have been placed at the intersection to provide very low pressures, and collimators were inserted into the 1SR to reduce background coming from the beam-dump area. For R806T, a large system for feeding liquid nitrogen and circulating liquid argon was designed and installed. Much mechanical design and construction work was carried out for the calorimeters and supporting structures. Two complete modules, installed opposite each other, are now in place and are operating successfully and reliably. The heavy load of installation work for experiments this year has received considerable technical help from the laboratories of the experimental teams, in particular from the Orsay and Rutherford Laboratories and the Universities of Liverpool, Manchester, Munich and Rome, in addition to the usual helpful collaboration from, other Divisions at CERN.

    Preparations for future experiments Preparations began last year and have intensified this year for two large-scale experi­ ments that will be installed next year: experiment R108 (search for e*, e+e~, multipion correlations) and experiment R804 (search for neutral boson, muon pair production and associated hadron correlations). For experiment R108, a large superconducting solenoid magnet (being built elsewhere at CERN) will surround the intersection and, to correct the effects of its field on the circulating beams, compensating magnets have been designed and ordered along with their power supplies. A building for the helium compressor has been designed and its construction completed. Designs and construction are well under way for a new special thin-walled vacuum chamber, for the transport and alignment of the solenoid magnet, for supporting structures, a new counting room, signal cabling, etc. It is planned to move the low-beta insertion, now at 1-7, to intersection 1-1 and the necessary preparations are in progress. The experiment will be installed in two stages: the detectors in the spring of 1976 and the solenoid in the middle of the year. For experiment R804, considerable mechanical design has been carried out for the magnetized iron sections that will be fitted around one side of the intersection and for all the supporting structures. The coils and power supplies for the magnet are being provided by the Department; half of the steel yokes have arrived from the United States. The pre-assembly and testing of the magnet will start in the spring of 1976. Tests of the large drift chambers and of the central detector will also start next year and will continue until the full installation of the experiment At that lime, the new, shallow, thin-walled vacuum chamber will also be installed. Other preparations have included the design of a set of copper coils for generating a toroidal field in the electron-spectrometer arm of experiment R606 (search for muon- electron coincidences and hadronic states) that will also be installed next year. In addition considerable design and analytical work has been done to evaluate and study the feasibility of proposed experiments prior to discussions on their approval.

    Intersection vacuum chambers Each new experiment at the ISR usually requires a newly designed vacuum chamber or extensive modifications to designs previously used. For experiment R207, the chamber is of an entirely new type that may also be useful for other experiments. It is a stainless steel cylinder, of 375 mm diameter, with undulating Figure y The thin-waited '0.3 mm) titanium vacuum ehamhc shown after its im­ plosion at intersection 1-7. i CKliA'-107.H .751

    walls only 0.3 mm thick. It is equipped with a new design of large clearing electrodes made from very thin titanium foil. For experiment R702, because of the urgency of its installation at the beginning of the year, an improvised chamber of stainless steel, with walls 1 mm thick, was designed and speedily constructed. During the year, a titanium chamber, with walls 0.3 mm thick, was designed and prepared. It would have been the most "transparent" chamber yet installed at the ISR but, unfortunately, it collapsed after its installation when baked at

    Figure 10 - An undulating vacuum chamber for downstream arms of ISR intersections is shown undergoing mechanical tests. Made of Jnco'ief, it lias inner dimensions of 150 mm hy 50 mm and a wall thickness of 0.3 mm. The deflection under vacuum is- measured hy mechanical dial gauges- and the strain hy electrical strain causes.

    122 Figure 11 Tue ipcriiit raannn ehamber (made by the Central llarl.\lioli\l far experiment RS04 that i\ to he installed in 1U76. The ehnmber i\ made from srain/e\i sree/ vAiv/, 0.4 tant thiek. and if/// be impended bv \lamlc\s WW ribbon* (shown ahme and below ) between the palelace\ of an analysing magnet against u compre.witnt laree of 1.2 tans. CKR\-:?l.W.?Sl

    300 °C. As a result, nearby regions were heavily contaminated with dust and debris, especially from the mineral wool that had been used for thermal insulation. Analysis of the failure showed that the fault was most probably in the welds. To minimize the loss of operating time for the ISR. an extensive work programme was carried out for cleaning and repairing the section, installing spare chambers, pumps, valves, etc., and an alternate stainless steel intersection chamber, also with walls 03 mm thick, was put in place. In spite or this accident, it is still believed that titanium chambers Tor intersection regions can be made successfully and preparations are under way for manufacturing two new chambers of titanium for use at intersections 1-4 (with the Split-Field Magnet facility) and 1-7.

    Preliminary studies, begun last year, on possible designs for 400 GeV proton-proton Long-term storage rings have shown that such large storage rings with normal, copper-steel magnets development could actually be built to achieve good performance with a luminosity of 1033 cm-2 s_I. Drawback-*, to such a project would be the uncomfortably large circumference and the very high power consumption. Storage rings with superconducting magnets could over­ come these drawbacks, might have potentialities for somewhat higher performance, and might perhaps be lower in cost although little is known as yet about costs. Therefore, the studies are now concentrating entirely on designs with superconducting magnets and a tentative list of parameters has been drawn up. The machine's circumference is made up of the normal lattice and insertions for colliding-beam physics and for such other functions as injection and beam dumping. Studies of these individual parts are in progress and of the problems of matching them together, a condition which must be achieved for all particle momenta in the stacked beam and for all required operating conditions. For a given energy and stacked current, the maximum design luminosity in an interaction region is governed by several, sometimes conflicting, factors, such as the non­ linear electromagnetic beam-beam interaction, the maximum acceptable values of betatron function in the neighbouring quadrupoles, acceptable source length, etc., and compromises must be made. For proton-proton physics, three types of interaction region have been considered so far, each for a particular class of physics experiments: a high-luminosity, low-beta region; a general-purpose region with plenty of unencumbered space; and a high- beta region with special optics for measurements at very small scattering angles. For 400 GeV proton-proton collisions, with circulating beams of 7 A in each ring, the respective luminosities in these regions would be 1 x 1033,2 x 1031, and 5 x 1030 cm"2 s"1. Because or its economic consequences, the size of the aperture and its influence on the machine's performance is being carefully studied. From an extrapolation to higher energies of the observed behaviour of beams in the ISR, and estimates of achievable tolerances, it may be possible to keep the radius of the vacuum chamber as small as 25 mm. Closely linked to these studies on 400 GeV proton-proton storage rings, the possibilities for electron-proton collisions have been examined. Preliminary evaluations indicate that it should be feasible to incorporate an electron ring in the facility to obtain a luminosity for electron-proton interactions of 1032 cm-2 s"1 with electron energies up to about 20 GeV, and about one third of this luminosity at 25 GeV. With the assumption of an unbunched proton beam, and with physics experiments on inelastic electron scattering and weak interaction events particularly in mind, values for ring parameters and requirements for interaction regions have been outlined. In order to reach the quoted luminosity with a 400 GeV proton beam of 7 A and an RF-power limited electron beam of 250 mA at 20 GeV, very small crossing angles (of the order of 1 mr) are necessary. A configuration is being studied in which the magnetic fields close to the interaction region are used to bring the beams into coincidence at this small angle. To cover adequately the solid angle around the interaction volume, the detector arrangement is closely integrated into the beam-optical layout Although the synchrotron radiation produced in the magnetic fields of this configi ration gives rise to some serious problems of machine design and background, the studies indicate that these difficulties can probably be overcome. This electron-proton interaction region's layout is also quite well adapted to the use of longitudinally polarized electrons, of interest for the study of parity-violating effects. Recently, some very preliminary evaluations have started of possible electron-positron facilities for centre-of-mass energy ranges considerably above any of the projects now being planned elsewhere. Other areas in the design and performance or large storage rings that are being given some attention include the injection systems, dumping systems, minimization of beam losses (particularly important with superconducting magnets), RF problems, and possible layout geometries. The crucial role of the vacuum system has been emphasized by experience with the ISR, and gas-desorption effects continue to be studied for both proton and electron rings. The relative merits of various materials for vacuum chambers (stainless steel titanium, aluminium) and of methods of pumping, such as cryopumping or distributed pumping through titanium sputtering, are being explored. Possibilities for in situ cleaning of vacuum chambers by glow-discharge are being investigated. The studies of superconducting magnets for beam handling in storage rings have continued. Although design criteria for a possible dipole for large storage rings have been examined and a preliminary set of dimensions has resulted, the major emphasis has been on the design of a full-scale model superconducting quadrupole that would meet the requirements of a high-luminosity insertion for the ISR. The design has been completed for such a model quadrupole that would provide a gradient of 40 T/m, 1.25 m in length, in a horizontal cryostat with a warm bore of i70 mm. Particular effort has been put into the definition of the superconductor and of its insulation, into the structural design or a coil-core system having high stability at the operating temperature, and into the establishment of a streamlined and reproducible coil making process. All necessary materials and components for the quadrupole have been ordered from industry. Part or the superconducting wire lias been received and insulated. The vertical test cryostat, the helium recovery system, the current leads and the power supply have been delivered and installed. Manufacture of all other components is in progress. After successful tests of a prototype coil, two of the final coils for the model quadrupole were wound and one or them was tested in December inside a special magnetic mirror. It reached the design field of 5.1 T at the second quench and then trained up to 6 T in 20 quenches. Special electronic instrumentation was set up to monitor, control and protect the magnet and the cryogenic system during the tests, with the result that instructive analysis and reconstruction of the quench phenomena could be made. Another area or study has been an exploration of the possibilities for proton-anti- proton collisions. For collisions at 400 GeV, it may be possible to reach proton-antiproton luminosities of I0'8 to 1029 cm~2 s"1 after a rilling time of about two days, but opera­ tional considerations might lower these values by an order of magnitude. An up-dated review of possibilities for proton-antiproton collisions in the ISR resulted in a discouraging value for the luminosity of only 5 x 10" cm-2 s~'. This luminosity could be increased at one intersection by the addition or a high-luminosity insertion. The possibility of increasing the overall luminosity through stochastic cooling is being examined.

    Modification of beam-transfer line TT2 Other The project for modifying the beam-transfer line TT2, in order to alternate the injec­ activities tion of beams from the PS into the ISR and the SPS, has been described in previous Reports. This project was completed by the end of the year.

    Figure 12 -- Sume ni ihr um pim'er supplies Uir rhc ntuditiej bfam-lrun^cr line TT2. •CERX-II.1.76, Figure 13 - One ni the induct ive-hnp betmt-pmititm tmmitor\ for the tnatltfteil heum-lmnsfer line TT2. {CERN-63M75I

    At the beginning of the year, the previously used d.c. power supplies for this transfei line were removed from the Y Building and replaced by the 19 new pulsed power supplies which were installed, connected to their loads and to the mains, and through CAMAC to the satellite computer that controls operation of this modified transfer line. After thorough testing, the complete system was smoothly put into operation in the d.c. mode at the end of February and has operated well since that time. Meanwhile, considerable effort has gone into the beam-observation systems and into the completion of the software for the control programs. As soon as the PS could eject protons al different energies on alternate machine cycles, the TT2 line was tested with beam in the pulsed mode. These tests were carried out for the firsttim e in mid October and were immediately successful. Administration

    Hie signature, an 10 July, of the Protocol » Inch extends the collaboration between CERN and high-ejicrgy physics untres in the Soviet Union. Deputy chairman I.G. Marozar (left) signed far the USSR Stute Committee for the Utilization of Atomic Energy and the Director-General of CERN Laboratory I, IV.K. Jentschke, signed for CERX. (CERN-116.7.75/ Administration Department

    Finance Division (FI) Personnel Division (PE) Technical Services and Buildings Division (SB) Health and Safety Division (HS)

    Central Services (CS)

    A new interpretation of the Organization's financial, personnel and other rules and regulations was adopted by Council following their earlier decisions concerning the management structure which will become effective on 1 January 1976. The health and safety services, brought together as a unit in 1974, were given the status of a Division by decision of Council in June, thus completing the organizational steps necessary for the full coordination of these services. 1975 marked another step in the development of scientific collaboration between CERN and the Soviet Union when, in July, a new protocol was signed which extended this collaboration to include experiments at the CERN accelerators and, in the Soviet Union, collaboration with all the institutes of the State Committee for the Utilization of Atomic Energy and of the Soviet Academy of Sciences. This enlarged cooperation will be channelled through a joint scientific committee. ^\ \JPV

    u

    Figure I — Approximately 70000 inrimes are cheeked eaeh year. ICF.RN-3I6^J(>)

    Finance Division

    Exchange rates were once again quite unstable in 1975. The exchange equalization Financial account showed a debit balance of some 1.7 million Swiss francs at the end of 1974. This situation was quickly made good during the first six months of 1975 and subsequent transactions led to a credit balance of 0.37 million Swiss francs at the end of the financial year. The average interest rate for short-term investments (one to three months) in Swiss francs and various other currencies was approximately 4.5% in 1975, compared with 10% in 1974. In addition to this drop in interest rates, the Member States paid their contributions more siowiy, and accordingly much less interest was earned in 1975 than in 1974. Income from bank interest for the two Laboratories was estimated at 6.05 million Swiss francs in the 1975 budget. The amount actually earned was 5.56 million Swiss francs, nearly half a million Swiss francs less than expected.

    In December 1974. the Council decided to block 25 posts and three million Swiss Accounts for francs of the 1975 budget for the Basic and ISR Programmes, and it confirmed this the financial decision in June 1975. A sum of three million Swiss francs was therefore transferred to the year Special Reserve in order to reduce the Member States' contributions in 1976.

    129 The decisions taken by the Finance Committee in November 1975 concerning the 1976 budget had repercussions on expenditure in 1975. Owing to the reductions in the budgets Tor 1976-1978. the Management had to begin revising the programmes at the end or 1975. Accordingly, expenditure amounting to some ten million Swiss francs, relating mainly to the purchase of a new computer, had to be postponed. The accounts of the Organization may be summarized as follows:

    Expenditure Budgets Accounts millions of Swiss francs Basic and !SR Programmes 429.40 \ Savings imposed by the Council - 3.00* I 300 GeV Programme 237.90 237.97 664.30 668.73

    The overspending of 4.43 million Swiss francs concerns expenditure for which no provision could be made in the budgets (taxes, services rendered to third parties, etc.). and is covered by compensatory income.

    Fwure 2 - Dcu'lvpinciu ut the expenditure til the Orsumzuuim.

    "- 450- Expendiîure at curent prices

    • Expenditure at 1970 prices

    1960 1961 1962 1963 1964 1965 1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 ' (Budget) • including 1.77 million Swiss francs under the "Personnel" heading and 1.23 million Swiss francs under the "Materials" headmes.

    130 Income Budgets Accounts millions of Swiss francs Contributions from Member States 626.85 626.85* Bank interest 6.02 5.56 Brought forward from previous financial year 15.03 15.03 Contribution from the 3G0 GeV Programme to the Basic and ISR Programmer 16.30 16.30 Contribution from ESO 0.60 0.76 Miscellaneous income 2.50 8.27 Savings imposed —3.00 664.30 672.77

    The excess of income amounts to 8.47 million Swiss francs. A total of 4.04 million Swiss francs will be reimbursed to the Member States (bank interest —0.461 million, unused reserves 1.47 million, miscellaneous 0.03 million, sav.ngs 3.00 million); the balance of 4.43 million Swiss francs is compensator}' income.

    Budget for the Basic and ISR Programmes In June 1975 the Council invited the Directors-General, in consultation with the Scientific Policy Committee, to prepare a programme which would ensure a reduction of 3% per annum in the total CERN budget This programme was described in document CERN/CC/1198/Rev. (CERN/SPC/380/Rev., CERN/FC/1879/Rev.). The 1976 budget for the Basic and ISR Programmes amounted to 407 million Swiss francs. It was presented in 1975 prices because no decision had been taken on the cost variation index for 1976. It was, therefore, not possible to submit a final budget document to the Council at its session in December 1975. Nevertheless, the Council did at that time approve a total budget of 407 million Swiss francs at 1975 prices, a cost variation index of 5.96%. and a reduced salary index of 2%. The net budget thus amounted to 431.24 million Swiss francs to which should be added the 34.19 million Swiss francs detailed below.

    millions of Swiss francs (a) 1976 prices)

    The gross budget amounts to 465.43 from which must be deducted: — the cost of services paid for by Laboratory II . . . 17.40 — the overheads covered by ESO 0.52 — the income from work carried out and charged for by the workshops 2.57 — a transfer from the Special Fund 13.70 34.19 giving a net budget of 431.24 from wLich must be deducted: — the savings imposed in 1975 3.00 — a transfer from the Special Fund 13.00 — miscellaneous income 1.90 17.90 Contributions payable by the Member States 413.34

    * including 567-52 million Swiss francs paid by 31 December 1975 and 59.33 million Swiss francs lo be paid at the beginning of 1976. /

    Budget for the 300 GeV Programme The total budget for the 300 GeV Programme, approved by the Council at its Forty- fifth Session (CERN/958/Rev.), is 1150 million Swiss francs, at 1970 costs and fixed prices. The ani;uul budgetary profile was adopted by the Finance Committee at its Hundred- and-sixteenth Meeting (CERN/FC/1408) and was approved by the Council(CERN/1050). At its June 1975 session, the Council asked the Directors-General to prepare a long- term programme auù budgets for the years 1976-1979 inclusive for the unified CERN Laboratory. The revised proposal presented by the Directors-General in document CERN/CC/119S/Rev. (CERN/SPC/380/Rev., CERN/FC/1879/Rev.) includes a modified budgetary profile for the 300 GeV Programme. This profile, with no change in the total cost of the programme, is based on a shift of 40.7 million Swiss francs from the years 1976-1978 into the year 1979, to meet payments expected to be made in that year. The following table shows the two budgetary profiles (at 1975 prices):

    1976 '.977 1978 1979 Total (millions of Swiss francs)

    Previously agreed profile (CERN/1050) . . 223.9 223.9 223.9 36.5 708.2 Revised proposal (CERN/CC/1198/Rev.) . . 218.6 213.1 199.3 77.2 708.2

    The budget for 1976 is based on the new profile, and is (at 1975 costs) 218.6 million Swiss francs. At its Fifty-sixth Session, in December 1975, the Council approved a cost variation index of 5.96% including a 2% salary index. Consequently, the 1976 budget for the 300 GeV Programme amounts to 231.62 million Swiss francs, including a contribution of 17.40 million Swiss francs to the Basic Programme.

    millions of Swiss francs (al 1976 prices)

    The budget for 1976 amounts to 231.62 from which should be deducted: — Probable bank interest 2.60 * — Other income 0.15 2.75 Contributions payable by the Member States 228.87

    The total budget for the three programmes thus amounts to:

    millions of Swiss francs

    Basic and ISR Programmes 300 GeV Programme Total

    From »vhich must be deducted: — the true income (including the transfer of 13 million Swiss francs from the Special Fund) 20.65 Net contributions payable by the Member States 642.21

    ' IncludingÜJ9 million Swiss franc:,urnc d forward from 197?. The monetary situation was again a source of concern throughout the year, with Financial regard to both short-term investments and the purchase of currencies to provide partial and Accounting cover for our commitments in 1975. Services Another cause for concern was the growing number of firms going bankrupt or into liquidation. These cases lead to very awkward and often very protracted negotiations. The number of visiting teams increased again, this time by 20%, giving rise to a considerable increase in the workload. Despite this extra work, the Financial and Accounting Services had to do without the services of nine persons (temporary labour). Some activities have had to be discontinued, and there may be some delay in balancing the books at the end of the financial year.

    Modifications are continually being made to existing upplications in order to keep up Administrative with the changing needs and procedures of the service Divisions. The stock system is at Data Processing present undergoing major development. Service In order to deal with the constant increase in demand, performance was (' "hir improved by extending the central memory and by adding more peripherals (fa« units and printer); this means that the present IBM 360/30 computer is being ed almost to its technological limits. The decisions concerning the future structure of the Organization will have a great impact on the present administrative data processing system. Preliminary work is under way with a view to making the necessary changes to the applications, basic software and equipment. The concept of a data base has been introduced and is already being used to develop the present applications.

    Purchasing Supply For the Supply Services 1975 was another year dominated by the economic crisis and its repercussions. The price of standardized equipment continued to rise by between 5% and 15% approximately, depending on the items concerned. Very great care had to be exercised in dealing with all problems relating to supply. However, CERN was able to make some savings owing to the fall in the price of some electronic components and equipment. In view of the uncertain economic situation, the Supply Services intensified their market surveys by carefully studying the information published in the technical press and by issuing a large number of price enquiries for major contracts over as wide an area as possible. In 1975,1963 price enquiries were made compared with 1785 in 1974. With regard to major contracts, business eased somewhat owing to the budget restric­ tions and the completion of the SPS accelerator. Only 112 calls for tenders were sent out in 1975, compared with 132 in 1974. Although fewer large contracts were awarded, the Supply Services were kept just as busy because the economic situation led suppliers, together with their professional bodies, associations and agents, to intensify their sales campaigns in an attempt to secure contracts with the Organization. In view of the budget cuts, temporary labour cannot be called in to ease the workload in the Purchasing Service, where the stafT are overworked. Although the hourly rate for

    133 temporary labour increased in 1975, the total expenditure under this heading dropped from 180049.95 Swiss francs in 1974 to 122427.50 Swiss francs in 1975. The Service was able to carry on as a result of the cooperation of the staff but the problem is still a pressing one. Whereas it seemed likely at the beginning of 1975 that the number of orders would decline, by 31 December 1975 the number had risen to 39884, compared with 38996 in 1974. On the other hand, in the Invoice Office there was no change and the number of invoices handled remained the same (70000). This figure does not reflect the very heavy workload of the staff in this office. Suppliers are anxious to be paid more and more promptly in order to be able to settle their own bills on time. Furthermore, since prices are so unstable, most contractors now stipulate price revision clauses, which was not the case a few years ago. With regard to purchasing, an important event took place which will increase the efficiency of the Service without pushing the workload beyond the present limits. The Finance Committee approved the new General Conditions of CERN Contracts. Not only will this document provide the Organization with an up-to-date legal instrument well suited to its needs, but it will also relieve the staff of administrative tasks which they were obliged to carry out in the past because the previous texts were becoming obsolete. A major contribution has thus been made to the efficient running of the Organization, especially since the texts approved by the Finance Committee have formed the basis for the drafting and publication of instructions in which methods, procedures, documents etc.. are standardized to a very high degree. Having been freed from these thankless tasks, the staff are now in a position to devote more of their time to market surveys and to the protection of the Organization's interests.

    Stores In 1975. as in 1974. activity in all sections of the Service increased considerably. In some areas the rate of increase was even greater. The following trends were observed (compared with the same period in 1974): the total value of standardized items drawn from stores rose by 3%; deliveries of equipment for the Organization as a whole increased by 2%; despatches of equipment outside increased by 24%. The number of standardized items out of stock dropped by 28% (on average) compared with 1974. On the other hand, since it was difficult to predict the general trend of demand, stock levels remained fairly high during the year. Effective action (a reduction of reserve stocks, an overall adjustment of lead times, the elimination of obsolete items etc.) was taken to bring the stock level nearer to the authorized limit. In order to deal with the large volume of in/out traffic, the despatch office was moved from Goods Reception to a temporary hut. Building 133 was reassembled in the new storage area for equipment belonging to the Divisions, and power racks were installed to double the storage capacity. A new computer-controlled system for managing stores of this type was also introduced. The storage of chemical products was studied with a view to concentrating the bulk of these items in one place properly designed to meet the safety requirements. Instructions to suppliers concerning the routing of goods and proposals aimed at clarifying the commercial terms used in orders were drafted in conjunction with the Purchasing Service. More than 200 specifications written by the Technical Section and covering 5000 standardized items are now at the disposal of the Purchasing Service. Contracts concerning the various types of stainless steel which meet the Organization's special

    134 Personnel

    1970 1971 1972 1973 1974 1975 fiçtin 3 Diwlopiiwu! ut sunk mou'mviUs .sma' 19/(1.

    requirements have been awarded on the basis of specifications written in close collaboration with the users. During 1975: the total value of issues of standardized items was 35.3 million Swiss francs, represeniing an increase of 3% in relation to 1974; the value of items issued in Laboratory II amounted to 8.9 million Swiss francs (25% of the total value of items issued); the self-service system accounted for 4.7% of total issues; the annual rate of stock turnover was 2.3; the average stock level was found to be 13%-24% higher than the authorized stock limit of 12.7 million Swiss francs;

    135 53162 deliveries and 12995 despatches were recorded for the Organization as a whole; 12031 delivery requests and orders for standardized material were drawn up; the Standardization Groups (130 members) took 2864 decisions (to introduce or eliminate items in stock). As a result of these decisions, 992 new items were introduced into the stores and 1142 items, worth 204600 Swiss francs, were removed and handed over to the Salvage Service. The latter sold items outside the Organization worth about 667000 Swiss francs (including 265 tons of paper and 700 tons of metal waste).

    Insurance The Service was still concerned in late 1975 with the settlement or the claims concern- Service ing flood damage in 1973 and a number of other claims which are long drawn-out affairs, the most important being that of BEBC (February 1974). In 1975, the fire in the PS area caused a great deal of extra work, as the nature or the damage was such that liaison between the Divisions and the insurers was necessary at every stage of repair and replacement. The Organization's third-party insurance has been brought up to date, and a new accident insurance contract was negotiated covering summer students. The Service collaborated in particular with the Legal Service and with the Social Affairs Service in 1975 on questions of reintegration into national insurance schemes and insurance for family members. The administration of the Staff Insurance Scheme has been heavily committed during 1975 with investment portfolio mana2~ment, the running of the Staff Insurance Scheme and, with new Rules apparently imminent, an increasing number of enquiries from staff. The Service has provided the secretariat and administration for the Finance Committee Working Group on CERN's Pension Policy during the last three years.

    Auditors The financialyea r 1974 was the second for which the audit was carried out by the report Bundesrechnungshof (Federal Court of Audit) of the Federal Republic of Germany. At its Fifty-fifth Session, in June 1975, the Council approved the Accounts for the financialyea r 1974.

    136 1975 EXPENDITURE LABORATORY I

    (liasic and ISH Programmes) (in lliousiiiuls of Swiss fruiics)

    Departments 1975 Ilrciikdowil Dircclonilc- Budget Differences Gencrnl Theoretical Proton Applied Physics I Physics II Physics Synchrotron Physics ISH

    GUAM) TOTAL 429,400.0 + 1,356.(1 18,293.9 67,885.1 f.3,194.4 3.196.0 74.214.1 36,450.8 44,568.4 Workshop jobs (o be charged -7.HU0.0 + 371.5 Sub-lcilal 437,2011.» + 984.5 18,293.9 67,885,1 63,194.4 3,196.0 74,214.1 36.450,8 44,568.4 1. Personnel 227,20(1.» -2,341.7 17,012.5 32,457.4 35,903.7 2,885.8 34,6114.5 18,685.« 22,277.4 10) Stuff members 204.565.0 -2.592.8 4.927.4 30.200.2 30.788.H 2.657.0 33.921.7 17.443.1 22,146.4 12 Laboratory flliiiï 5,975.0 + 21.8 1.064.3 4,085.7 6.1 588.1 14 Fellows 6.700.0 + 709.8 6,629.3 145.9 235,3 287.3 72.5 12.7 15) Consultants and associates 9.960.0 - 480.5 5.455 8 1.047.0 793.9 228.8 389.4 581.3 118.3 2. Operation 86,210,0 -3,346.6 1,265.8 10,076.2 8,477.7 307.8 4,956.9 10,043.4 2,241.9 201 Site and buildings 15.240.0 -1,111.9 3.1 723.6 279.5 1.2 134.7 218.4 239.4 21) Service equipment 11,185.0 + 944,6 214.4 820.1 1.938.6 3.8 384.1 894.2 804.5 22) Accelerators 5.525.0 -1,718.2 688.3 2.709.2 409.3 231 Equipment for experiments 8,9)5.0 + 231.5 106.1 4,918.4 3.802.4 61.7 5.1 103.0 24) Beams 3.045.0 -1.400.5 406.3 552.1 671.7 25 Dntlt handling 11,870.0 -1,036.3 874.8 863.9 23,2 8,414.6 160.2 27 Power, water 18,200.0 - 689.5 28) Administration 12.230.0 +1.433.7 942.2 1,644.7 1,041.2 302.8 972.3 511,1 525.5 3. Capital outlays 123,790.0 + 6,672.8 15.6 25,351.5 18,813.0 2.4 34,652.7 7,722,4 20,049.1 30) Site und buildings 14,805.0 + 6,432.2 1991 151.9 468,3 155.7 31 Service equipment 10,920.0 -2,189.7 9.4 I.128.J 983.6 2.4 646.4 1.706.4 32) Accelerators . 30,885.0 + 1,735.4 233.3 16,623.5 873.2 13.733.4 33) Equipment for experiments 28,585.0 - 218.0 6.2 15,961.2 9,370.4 3.029.2 341 Beams 23,425.0 +4,343.7 4.167.9 6,809.2 16.791.6 35) Dutu hnndling 15,170.0 -3,430.8 1,691.8 1,497.9 122.9 1.424.4 6,849.2

    ~J BUDGET 1976 BASIC AND ISK PROGRAMMES (in thousands of Swiss francs)

    Dirce- Divisions Breakdown TOTAL lorute- Gcnenil Til UP DD PS l.,R SPS SB Fl HS

    GUAM) TOTAL 465.430 18,485 .3,260 72,780 54,840 53,255 67,770 47,545 22.160 86,005 16,300 11.160 11,770 Workshop jobs to be charged to Divisions. - 7.520 -7,520 Sub-totnl 472,950 18,485 3,260 72,780 54,840 53,255 67,770 47,545 22,160 93,515 16,300 11,260 11,770

    1. J'LTMMmcl 229,140 17,110 2,941) 35,980 27,760 19,590 311,840 22,700 2,160 33,980 11,200 7,580 930 101 Slnff members . , 206,730 4,900 2.680 29,230 27.500 18,500 38.200 22,600 2,160 33.760 11,200 7,100 8,900 12) Laboratory stair . 6.080 5,220 610 250 14)Fellows. ... 6,670 6,670 15) Associates . . 9,660 5,540 260 1,530 260 480 640 100 220 480 150 2. Operation 98,700 1,270 310 9,270 9,610 12,555 8,325 2,685 410 45,160 4,330 3,520 1,255 201 Site and buildings . 17,140 85 20 785 860 1,155 330 360 40 13.325 95 30 55 21) Service equipment . 11,610 160 1.060 1,700 615 555 745 20 5,330 535 30 860 22) Accelerators .... 6,675 5.935 740 231 Eqtlipmrni for experimen 9,600 55 4.725 4,525 25 165 10 95 241 Beams 1,855 785 835 235 25 Data handling . . . 12,830 1.165 880 10.140 1(1 195 430 10 27) Power, wilier . . . 25,590 25,590 28) Administration . . 13,400 970 290 1,535 860 645 635 480 105 915 3,270 3,460 235

    3, Capital Outlays 145,110 105 10 27,530 17,470 21,110 20,605 22,160 19,590 14,385 770 160 1,215 30) Site and buildings .... 14,425 75 750 535 590 55 12,275 115 30 31) Service equipment . . . . 10,580 30 1,455 1,400 850 2,175 195 2,110 440 160 1.110 32) Accelerators 32,060 645 17.655 14,405 331 Equipment for experiments 30,675 16,070 11,120 3,440 45 34) Beams 32,630 8,280 3,445 1,565 19,340 35) Data bundling 24,740 975 1,505 1.550 215 30 20,465 TH = Theoretical Physics PS = Proton Synchrotron FI = Finance EP = Experimental Physics ISR = Intersecting Storage Rings PE = Personnel EF = Experimental Physics Facilities SPS = Super Proton Synchrotron HS = Health and Safety DD = Data Handling SD = Technical Services and Buildings 1975 EXPENDITURE AND 1976 BUDGET 300 GeV PROGRAMME tin thousands of Swiss francs)

    Financial year 1975 Breakdown Budget Expenditure

    TOTAL 237,900.0 237,968.9 1. Personnel 29,770.0 28,054.1 III) Staff members 28.770.0 26.964.9 15) Fellows 1.0C0.0 1.0S9.2 2, Operation 35,300.0 30,276.5 20) Site and buildings 4.200.0 ZS50.I 2!) Service equipment 3.800.0 3.551.4 22) Accelerators 2.000.0 1.922.7 25) Equipment for experiments ISS.7 24) Beams 189.5 25) Data handling 1.000.0 491.2 27) Power, water 5.70O.0 Z947.4 28) Administration 2J00.0 1.835.5 — Contribution to general overheads of Laboratory 1 16.300.0 16.300.0

    X Capital outlays 172,830.0 179,638.3 511) S:te and building 78.600.0 91,946.9 31) Service equipment 12.930.0 7.241.7 32) Accelerators 65.300.0 57.985.1 33) Equipment for experiments 16S.7 34) Beams 16.000.0 21.286J 35) Data handling 9.6 — Stock in stores 1.000.0

    I.W Figure 1 — Sortine in the mail office, for lite four tlnilr dciivcrv and collection services. (CERN-32U.76)

    Personnel Division

    The main functions of the Division were described in a document submitted to the new Directors-General. To meet the foreseeable consequences for the personnel of the budgetary restrictions imposed, the work of the Personnel Division is now being directed towards action within the Organization, such as increased mobility of staff, investigation of possible savings to avoid the need for dismissals, and additional rationalization measures. As soon as the first budgetary restrictions for the coming years were known, external recruitment was stopped, and efforts were increased to fill the essential vacancies by internal transfers. The use of personnel provided by firms supplying temporary labour was examined during the first half of the year. The effect of the proposals put forward, which were approved by the Directors-General and the Finance Committee, was to redefine policy and procedures in this field, and their immediate implementation led to a substantial reduction in numbers. Steps are being taken, in cooperation with the French authorities, to minimize the human and social consequences of these decisions. The negotiations for the reintegration of Swiss members of the personnel into the "Assurance Vieillesse et Survivants" (AVS) resulted in an agreement allowing optional and partially retroactive reintegration. Renegotiation of the Agreement on Social Security TOTAL NUMBER OF PERSONS AT CERN ON 31.12.1975

    LABORATORY 1 Ashociules siiiir Lnhnnitory CERN Members Stuff FelloWH Member Non-Member Department» Divisions States States Dlrectorulc-Clcniirul Total 2ft 2 28

    Physics 1 l'öllll 436 35 32 8.12 121 1456

    NP 3IH 35 31 H2I 120 1325

    MSC 117 1 II 1 130

    Physics Jl Total 428 12') 20 69 23 669

    TC 426 129 20 69 23 667

    Thcurelicul Physics Total 25 26 19 15 85

    Til 24 26 19 15 84

    Proton Synchrotron Tolul 497 15 8 2 522

    EA 28 28

    MI'S 466 15 8 2 491

    Applied Physics Tolul 268 22 9 10 6 315

    DD 268 22 9 10 6 315

    ISR TuUil 356 4 1 1 362

    ISR 355 4 1 1 361

    Administration Tolul 1127 6 3 16 9 1161

    Dl + PJO + TM 42 J 43

    IIS 13» 6 2 2 2 151

    Fl 209 209

    PE 129 11 4 144

    | SB 608 1 | 2 3 614

    TOTAL LABORATORY 1 3163 192 109 957 | 177 4598

    TOTAL LABORATORY II 433 — 4 7 1 445

    TOTAL CERN 359

    NP = Nuclear Physics EA = Experimental Areas Croup Dl = Directorate FI = Finance MSC = Synchro-cyclotron Muchine MPS = Proton Synchrotron Machine PIO = Public Information Oflice PE = Personnel TC = Track Chambers DD = Data Handling TM = Translation and Minutes Service SB = Technical Services and Buildings TH = Theoretical Studies ISR = Intersecting Storage Rings US = Health and Safety 3600

    3500

    Dec 70 Dec 71 Dec 72

    / entire T Flut malum* m lite number-* oj Mull member', ami uu\'ifitirie\ m IV7!. 1V7J. IV'J IV~4 ami /"J~5 77/.' up/nl line represent* ihe CERS ••hilt Intal Tile ,umali mil iLp:irmre\ .•«. hale . huime\ m tnnrrut mal *itim\ iempi>rar\ beiuniiiig Mut I member. tnr i \unipL

    concluded with France in 1970 is proceeding with a view to securing improvements, in particular on unemployment insurance. Discussions on reintegration are also continuing with Germany and Belgium. The enquiry into salaries carried out in 1974 as part of the five-yearly review of CERN salaries was to some extent updated during 1975 by visits to certain European

    Fienre J Turnover nf \lnll member* dilti uintliune* between il /JV/V7-/ und JI.IJ.IV75.

    14: Some personnel statistics at 31-12-75 staff members * auxiliaries LBboratorv 1 laboratory II CERN

    Sex Men 88% 92% 89%

    Women 12% 8% 11%

    Family Persons receiving the family allowance 85% 85% 85%

    Average number of children 1.5 1.6 1.5

    Average age of children 9.9 years

    Breakdown according to occupational category and average age % age % age % age

    Physicists and scientific programmers 12% 39.3 10% 38.2 12% 392

    Engineers 9% 41.1 16% 39.3 10% 40.7

    Technicians 24% 39.8 36% 35.4 26% 39.0

    Draughtsmen 6% 36.9 10% 36.0 6% 36.6

    Manual workers 19% 41.5 18% 34.0 19% 40.6

    Operators 6% 37.8 1% 31.6 5% 37.6

    Administrative staff 7% 41.3 2% 39.9 6% 41.3

    Office staff 9% 36.3 6% 35.5 9% 38.3

    Auxiliary service staff 8% 41 £ 1% 43.3 7% 41.8

    100% 100% 100% TOTAL 39.9 36.3 39.4

    h'i«mc4 HrciiAi/iHinn/ CKR\ \ialtiminhrr\aii3i.l? /uo. firms. The information obtained showed a slackening in the rate of increase of salaries, although there was an average increase, in real terms, of about 5% in the salaries for 140 jobs in 30 of the firms which participated in the 1974 survey. In the course of the annual job evaluation survey, certain professional groups were the subject of particular study: Laboratory II technicians, secretaries, quantity surveyors.

    I4UU 1393|1366

    1300 - 1289

    1215 1200 1156] 1134| ,1,9 1133 _ 9 llS2l 1100 ; il2 lj |l082 1082

    |10121006

    1000 981 |975

    9g, 9711 930| 900 868 8631

    800

    Figure ~ Mi'HInll IiilaU ill U'llim \ tL*»it-nin'\ illltl f *m

    143 photo-cngrnvers, firemen, construction inspectors and computer operators. A new job catalogue, comprising about 200 standard descriptions, is being prepared and will be gradually brought into use. The object is to reduce the number or individual descriptions. The CERN fellows and associates programme was the subject of a report to the Council, describing the development or the_ programme in the period 1971-1975 and proposing that it should continue at its 1975 level for the period 1976-1980. This was accepted by the Council. The academic training, general education, technical training and language courses are listed in Appendix C, together with the courses organized Tor the summer students. In addition, the firemen and certain operator groups were given intensive language courses designed to meet their professional needs. The School of Physics and other events organized by the Scientific Conference Secretariat are listed in Appendix D. The Division assisted in the work of the Rehabilitation Board for handicapped persons, which has been able to find or confirm satisfactory solutions for all the cases so far referred to iL With the aid of the Restaurant Supervisory Committee, new conditions of contract were worked out for the CERN restaurants, with a view to facilitating closer control over prices and price changes.

    144 T§^

    M

    /•n,'»/v / • OiUtbiT l't75: ImiLhnt; of llw hull anil the basv. uppri:\inuitclv ft in Wij/i. "» ir/iiifi ilw Gtngiiniïlk Inihhlc cluimbvr i\ to Iv Imcd. in ihv IIVn Ann. iCER.X-}~.ll>.75>

    Technical Services and Buildings Division

    In spite of the increased workload of the Division, especially with respect to Iniroiluciiim maintenance and the 300 GeV Programme, the number of staff members was substantially reduced. There were 602 at the end of 1975, with four posts blocked for personnel attached to ESO as part of the collaboration between that organization and CERN, while one person left the Division to join ESO. The Division consists of a central management and six groups, whose activities are described below. They are: new works (Laboratories I and 11), alteration and structural maintenance of buildings, maintenance and operation of technical installations, mechanical engineering and specialized workshops, transport, equipment handling and cleaning. The budget for the Division amounted to 92.4 million Swiss francs in 1975, including 33.4 million for personnel. The budget may be broken down as follows: Millions »/ Swiss francs Construction 24.4 Power, water 17.5 Maintenance, operation, alterations 25.3 Workshops 15.4 Transport 7.0 Management ^2.8 92.4

    145 This amount included neither the cost of altérations to installations and workshop jobs put out to contract, which is charged to the budgets of other Divisions, nor the cost of the work for Laboratory II in which personnel from the SB Division took part. The estimated number of staff from the Division working for the 300 GeV Programme was 112 in 1975,40 of whom were engaged in construction work. The policy change with respect to temporary (contract) labour, decided on during the first half of the year, resulted in a reduction of this class of personnel from 140 to only ten, while most of the work previously done by them was covered by service or maintenance contracts.

    Vi'i\' wi)rl

    Fieun- J1 Sriihiither IV! • insiiillnlum til llh- 7! tun invrlti'utl /imW/j/iy twin' lor tin1 m-ulriiit' hall in tin- II r\; AITII. tCF.It\-::4M7f:

    146 during the second half of the year, with the minimum disturbance to the rest of the building. The Division is carrying out design studies on behalf of the Site Installation Group or Laboratory 11, for civil engineering work and general technical installations. The very large construction programme in the North Experimental Area continues to make heavy calls on the Division's design resources, particularly in the civil engineering field. As part of the collaboration between CERN and ESO, the Division's engineers and designers continued to help in the work on the essential services for the Observatory at La Silla in Chile.

    The Maintenance and Operation Group was reorganized so as to rationalize the Maintenance distribution of maintenance work carried out by contractors and that done by the and opération Group's own personnel for reasons of safety and quality of workmanship. At the same time, the measures aimed at reducing certain maintenance costs are beginning to take effect especially the reduction in the frequency of the work, which has meant accepting the concomitant reliability and safety risks. Although the staff and financial resources or the Group remained virtually constant, it assumed responsibility for a large number of new installations and buildings, including the new Linac and the new printing shop, and, Tor the SPS, six auxiliary buildings, the fire detection system and the discharge station, and also many different technical installations on both sites. The quality or the water supply to Laboratory 1 continued to raise considerable problems throughout 1975. A pilot filler station was installed and monitored, and the good results obtained show that a solution is likely to be found. As a result of cases of pollution or local rivers, a close watch was kept on the waste water, and a design study for the installation of monitoring stations is in hand. A large number of improvements aimed at achieving greater savings continued to be made, including supplying the fire-fighting system with recirculated water. Studies are going ahead on the selectivity of the stand-by electric powei network and the emergency electricity supply using flywheel generator sets, and also design studies relating to the modernization or the central heating plant. A great deal of work was put into repairing the PS installations after the fire which broke out on 29 August. On that occasion, the Maintenance Group set up an emergency IS kV power supply for the affected area and brought up and installed the mobile 1 MVA motor-generator set to power the air-conditioning plant and the essential installations in the ring. This helped to minimize the effects of the accident on the physics programme. The annual variation in the consumption of power, water, fuel oil and gas from 1970 to 1975 is aiven in the followina table.

    1V71 1<)74

    Active power consumption (units ofone thousand KWh) grid supph | loom 192 184 203242 222 719 242660 230 CSD - sland-bv generators . . . ! 8481 174.14 21 665 20 751 18063 J 8711 Total \ 174 592 209 61« 224 907 243 470 260 723 248 791 Maximum instantaneous pouer(kW) . | 36 SOU 47 200 530U() 55 000 58 500 57KOO Cooling water! lUUUm3) j 6712 8(163 8665 8 364 7493 6 877

    J Drinking water (m ) . . . . | 472036 545 197 482443 319417 464040 484074 Heav\ fuel oil (tons) | 10181 12 989 14076 15818 11 902 11951 Gd<(m3| , 120256 113 118 100 588 115 328 112618 47767 -L i

    147 Alterations The number of requests for re-fitling and making alterations to buildings amounted to building.': to 1838 for the year, 30% fewer than in 1974, involving a total amount of some 7.5 mil- aiid instil/lotions lion Swiss francs, which is also considerably lower than the figure for 1974 (12.5 million Swiss francs). Nevertheless, the Group handled :i number of major jobs, including the rc-inslallalion of the large storage shed (building 133), the extension of the PS control room, and the installation of the ISR chemical cleaning shop. The maintenance of roads and buildings, which is essential to keep the CERN site in good order, cost about 1.5 million Swiss francs, which is still very low considering the amount of the investments concerned.

    Central The Central Workshops Group was reorganized, and some activities were regrouped Workshops (sheet metalwork. welding, hjat treatment and special processes). The amount of work done for the Divisions remained substantially the same (9.45 million Swiss francs), but in fact fewer hours were worked because of the reduction in the number of temporary staff. Work put out to contract, on the other hand, increased considerably (4 million Swiss francs as against 2.5 million in 1974). The equipment available was supplemented in 1975 by a large numerically controlled boring and milling machine for milling complex shapes, a gas-chromatography analyser and a large vacuum tank for electron beam weldine.

    i //t'»rc t rillmz llw »i'n vaanim r,wk lur ihr iii'ilrun beam Kctilnin miuluiK. iCERN-V4.HJi)

    Hgurc 4 - Tilt' ltiri,i' vacuum lank lor ch'cmm hi'iim netting .VcVH open, hi lllc Jim-çrmiml l.ï tin' huillilt! ruinuw (CERN-93.Il.75)

    148 Figun' 5 — Muchining a trapezohhl cross-section vacuum uink on the large. mtmericalk-conlwllvil Hulling machine. _ ICERX-5.I1.7S)

    Figure ft Tlw h\ itrofonueil "Flat Fi.\h" intersection chamber. X> made ol tl.J nmi gauge \ltimlcv> \lccl sheet, \eith itx susncn\ian system. • CKR\:?2.I0 75 ,

    Quality Control Section There was a general increase in the workload with 600 work orders. This was particularly the case in the Metrology Section, mainly owing to work for Laboratory II, which accounted for about 9000 out of the total of 23 000 hours, and in the Metallurgy Section for the inspection of materials bought by the Stores.

    Main Workshop and Sheet Metaluork Section The workload remained heavy. A great deal of interesting work was done, including in particular two aluminium alloy, trapezoidal-section vacuum tanks for the R 806 T-Q calorimeter experiment, eight diamond-machined aluminium alloy cathodes, 3.2 metres long, a liquid metal target for an isotope separator with a tantalum tank, a hydroformed "Flat Fish" intersection chamber made of 0.4 mm stainless steel sheet, and a 1.6 metre long intersection chamber made of 0.7 mm titanium alloy sheet

    West Workshop and Special Techniques The ""Plexiglas" and "Araldite" sections had a great deal of work. A new installation for casting scintillators had to be built, and new Araldite mixes for the manufacture of parabolic mirrors by centrifuging were developed, as were new materials for radiation- resistant "encoders". The new high-precision centrifuge for parabolic mirrors was commissioned, with highly satisfactory results. The processes and equipment needed for vacuum-coating are being studied. Wirb Chamber Manufacture Workshop The extension of this workshop has made an area of 170 m2 available to physics groups for chamber assembly. Eight "driff-type wire chambers were completed, with the wires aligned and parallel to within +5 u., while a major effort was put into the manufacture of detectors for 300 GeV physics experiments.

    Surface Treatment Workshop This shop had a great deal or work, especially of the routine type. There were also some very difficult tasks, such as the oxidation or aluminium-alloy separator cathodes, the silvering of cryogenic pumps and RF cavities and high-grade polishing of titanium components for the new linear accelerator. The new chemical cleaning shop for ultrahigh vacuum components was commissioned in collaboration with the ISR Division.

    Printed Circuit Section The demand Tor very large printed circuits with very close tolerances increased considerably, making it necessary to install a new production line. A coordinatograph Tor tracing drawings very accurately was commissioned in order to reach the required degree of precision.

    Thermal Treatment Section The essential work or this Section related to the outgassing of ultrahigh vacuum components and the vacuum brazing of RF structures, drift tubes and hollow conductors. There is an increasing demand Tor the heat treatment or alloys with special magnetic properties and light alloys.

    figure T Clicckmx the nri«iiutl ilrimmç tar it 12011 mm /e»» primal circuit tin llic i»oriitmiliiitnipli. t CKR.\-~.2.~6 •

    150 / •.", L ^ t.i[inpiHi in Ihinjlmc u7 lin hur- U'ltl

    CERN possesses a fleet of 393 vehicles, including passenger cars, utility vehicles, Transport, lorries, tractors, trailers, cranes, etc all of which are maintained by the Transport Section. equipment While continuing to carry out its everyday duties (moving furniture and effects, handling transporting passengers for conferences, visits, site maintenance, refuse collection, etc.), and cleaning the Section also took part in major operations such as the whole of the removals for the large West Hall and the re-installation of the 300 GeV shielding and beams (about 50000 tons had to be moved), the installation of the 422 fifteen-ton discs in the neutrino tunnel and that of the SPS machine components in the tunnel. The policy of transferring as much of the cleaning as possible to outside contractors «as continued. Four contracts for cleaning the buildings were awarded, and the responsibilitv for the upkeep of working clothes was handed over to an outside firm.

    151 A il 1 • '

    •S?',

    Figure I—The Health PhymsCraiip instrument ailihratioii litharatory. (CERN-24,1.76 )

    Health and Safety Division

    At ils Fifty-fifth Session ihe Council approved the establishment of the Health and Safety Division (HS) as from I July 1975. The new Division consists of the following Groups: Health Physics Group General Safety Group Medical Service General Services.

    It thus contains all the services which areconcerned v.ïth the maintenance, protection and promotion of health and with the safety of people and equipment. In particular, its activities comprise radiation protection (including research in radiation dosimetry and radiobiology). control of radioactive materials and disposal of radioactive waste, industrial safety, control of hazardous chemicals, occupational medicine (including routine medical supervision of workers exposed to radiations and hazardous substances), emergency medical assistance, the fire brigade and general emergency, rescue and ambulance services, and training and information in the field of safety and health at work. As CERN is an international organization, its activities and facilities are not subject to supervision and inspection by the Swiss and French authorities; equivalent surveillance is therefore provided by the HS Division.

    Health Physics Radiation survey and control Group Two problems were studied in detail at the Proton Synchrotron, namely the measure­ ment of stray radiation and the control of induced radioactivity. A comparison between various instruments for measuring dose equivalents showed a very good agreement of the results in different radiation fields, and it can be concluded that stray-radiation measure­ ments with our measurement technique and the understanding of the results have reached a very high level, and further improvement in the framework of the present recommenda­ tions of the International Commission on Radiological Units (ICRÜ) and the Inter­ national Commission on Radiological Protection (ICRP) could only be on the technical side. Major problems in radiation protection around the PS arise from the increasing levels of induced radioactivity. The control of this hazard was improved with the installation of a monitoring system for measuring the dose rate from induced radioactivity during the transformation of the East Hall into a multiple-target region. Furthermore, monitors were installed for the control of radioactive material at the sntrances to the machine and the target regions. Experiments were carried out to understand better the relation between beam losses and induced radioactivity (reports DI/HP/185 and HP-75-148). The secondary-particle distributions around various target materials at 50 MeV were studied to help in predicting radiation problems in the future Linac. The level of long-lived induced radioactivity kept the dose rates within the ISR tunnel below 2.5 mrem/h except for the beam dumps, where permanent access barriers had to be installed. Unusually large beam losses were observed during the last period of West Hall opera­ tion by the installed tissue-equivalent monitoring system. The unpredictable character of these losses required the classification of the whole E3 Hall as a restricted radiation area. From the beginning of July, all beam lines in the West Hall and of the transfer tunnels TT2a, TT4. and TT5 were dismantled, which required control and checking for induced radioactivity of all the equipment, such as magnets, vacuum chambers, shielding blocks, etc. In Septemher, an IS MeV betatron was installed and put into operation in the West HalL The evaluation of the associated radiation hazard was made and the necessary protective measures taken. The start-up of the Synchro-cyclotron following the completion of its improvement programme required frequent interventions. Careful planning of this work helped to keep the exposure of the personnel low. Only 37 man-rem were registered during 1975, which is low compared to doses received during the reconstruction period. Fifty-three containers of low-level radioactive waste were prepared and dispatched to the Swiss authorities; 173 new radioactive sources were introduced in the radioactive source inventory register, which now totals 896 sources with 75% out on loan. Dose rates to areas outside radiation areas on the CERN site and to regions outside the CERN boundaries, as well as released radioactivity in the air and effluent water, were found to be within the permissible limits.

    Personnel monitoring The number of film badges distributed every month stayed constant despite an increased turnover in personnel- A new filing system for personnel exposures (microfiche) is being developed in order to reduce filing space. Research into personnel monitors based on the observation of tracks in plastic continued.

    Instrument calibration and maintenance

    The calibration and maintenance services have been integrated and over 300 health physics instruments were maintained and calibrated or repaired during the year. A special effort was devoted to establishing routine servicing procedures. The calibration procedures were considerably improved with the installation of a specially designed facility in the new calibration hall.

    Development and instrumentation A forty-channel data logger for the site monitoring system was constructed and put into operation, and 20 rem counters were rebuilt for low-level counting of the stray neutron radiation on the site. Identity-card holders, to be attached to the film-badge holder, were manufactured. Studies were carried out in order to evaluate new possibilities for measurements.

    Research Dosimetry and radiobiology experiments with hadrons continued, using 600 MeV neutrons at the SC2 and pions at SIN (Swiss Institute for Nuclear Research).

    The principal activity continued to be the systematic inspection of installations and equipment to identify potential hazards, and prescribe precautionary measures, improved methods of work and the use of safety equipment. A number of meetings were held with Divisional Safety Officers and Monitors with whom close liaison was maintained. Talks on safety were given to workshop personnel and six Safety Bulletins were issued. Two serious electrical accidents occurred durinp the year, in one of which a contractor's employee was killed. Improved procedures and means to avoid such accidents are being introduced. The Safely Code for Experimental Pressure Vessels was published during the year. It was prepared in collaboration with the Nuclear Physics Division and contains rules on the construction and operation of all kinds of experimental apparatus operated under pressure. Included, in particular, are wire chambers, proportional and Cerenkov counters, and particular attention is being paid ta the use of inflammable gases and vapours. Members of the Group have participated in investigations of potential sources of environmental pollution and are taking part in a CERN-wide effort to improve the handling or liquid waste. Among the major projects in which the Croup was involved was the evaluation of safety problems associated with the experimental installations being set up for SPS physics. In particular, detailed studies and analyses were made of the proposals for the West Experimental Area and for the very large set of liquid-hydrogen targets to be placed in the North Experimental Hall No. 2 (EHN2). Other tasks were concerned with details of the developments involving Gargamelle, the "neutrino ramp", the 35 mi liquid- hydrogen counter and BEBC. In addition, a special study was made of the safety of barracks used as control rooms for experiments, and a set of safety specifications was drawn up which barracks will have to satisfy. A start was made on drawing up emergency plans in collaboration with the Fire Brigade and the Divisions involved, and evacuation exercises were held in the Central Computer Building (513) and Laboratory 5. The inventory of mechanical items requiring periodic inspections increased again. In addition, a wide variety of components for the SPS and other installations were inspected by radiography. Figure 2 Preparation m the under- ground test hunkvr for the pressure test- nig und taking of sin»* measurements. hy means of \train gauges, of a Q-nwJu!c tunk wfiti'tt uiff he usai in the ISR e\penment R S06T. tCF.RN-35.12.75}

    ACCIDENT STATISTICS

    Period covered: I November 1974 to 31 October 1975 (accidents lo contractors' personnel not included)

    ' Lahuratarx • Laboratory 11 Toial

    236 20 256

    Number of disabling accidents* 5a 2 60

    Number of losl norkinc davs 1005 22 1027

    Disabling accidents* per lO* man-hours** 0.56 ±0.07 0.10 ±0.14 0.53 ±0.07

    9.7 22 9.0

    ' A disabling accident is an accident causing an absence from work of muic than one day. ' This quantity is known also as the "frequency rate"; in many publications the unit used is "per 10h man- hours". 10s man-hours corresponds approximately to a working life of 50 years. * This quantity is also knouii as the "severity rate".

    In addition to ilie routine medical examinations (pre-employment or in cases of Medical resignation or awards of indefinite contracts, or following requests by the patient or the Service Staff Insurance Scheme), particular attention was given to selected groups which have a special need for medical surveillance. These were: (i) Personnel in occupations in which failing health can endanger not only themselves but also others — firemen,drivers , crane drivers and electricians. One hundred and eighty-nine members of these groups were examined in 1975, and appropriate complementary tests were carried out. Suitable action, hi particular referral to a medical practitioner, was taken if required. (ii) Apprentices: these were supervised medically in conformity with the regulations of the Canton of Geneva.

    155 (iii) Personnel exposed to special occupational health hazards (workers in the surface- treatment shops, workers engaged in soldering electronic circuits). An enquiry was carried out. in collaboration with the Safety Group, into the risk of lead poisoning associated with soldering; special ventilation was recommended and installed in some shops, and u significant decrease in urinary lead content was found. (iv) Personnel or the NP Division. This group was examined in its entirety, many or them being radiation workers or exposed to other, less evident, occupational hazards. (v) Personnel more than 50 years or age. These examinations were carried out in order to obtain better information about the problems of this group, in particular with regard to their adjustment to their work and. Tor the oldest, preparation Tor retirement.

    Close collaboration with the radiation-protection services was maintained, and a combined filing system was set up containing data on contractors' personnel. It is intended to extend this joint record keeping to cover all personnel working at CERN. The Medical Service continued to provide first aid and emergency medical advice during working hours. Its doctors also acted as consultants on medico-social afTairs to the CERN social services (Personnel Division) and to the CERN Pension Fund. As in the past, first-aid courses for volunteers were organized and given jointly with the Fire Brigade. In addition, specialized brief courses were given, also in collaboration with the Fire Brigade, at the request of the Divisions.

    General The General Services include the Site Security Service (which acts as the fire brigade, Serrhes provides first aid outside working hours and carries out guard duties), the conference room technicians and the gardening staff. The workload of these three sections, which is closely bound up with the general level 0Î activity at CERN, increased considerably as compared to previous years. For the Site Security Service, the progress made with the construction of Labor­ atory I! resulted in more guard and patrol duties, and more calls for action of all kinds. This made it necessary to continue to employ contract labour. Special mention should be made of the activities of the Site Security Service in the field of personnel training. The Head of the Service and his deputy have periodically given the following courses in collaboration with firemen holding the Brevet National Francais de Secourisme: a first-aid course for volunteer members of the personnel who are being trained as first-aid assistants: an advanced course for first-aid assistants; a special course on treatment of electric shock; a course on lire extinguishers and how to use them; a course dealing with the evacuation of buildings in the event of an emergency. By being aware of possible hazards and knowing how to deal with them and prevent them. CERN personnel can make a positive contribution to their own safety. The conference room technicians, as usual, gave their services at various conferences, seminars, courses and colloquia. of which there were twice as many as in 1974. In addition to carrying out improvements to the existing installations, they assisted in fitting up a new conference room at the top of the Administration Building. The gardening staff, apart from their routine work, improved the floral decorations around the Laboratory I buildings and continued their task or landscaping the large green expanses of the Laboratory 11 site. Dcmoimnithij' the iw>r£imr of the SPS control system to a group ol Italian ioltmaltsls. iCERS-l73.llt.75)

    Central Services

    Plans tor the development of the CERN COURIER, aimed at identifying more Public closely the activities of the laboratories in the Membet States with the diffusion of Information information on high-energy physics, have gone ahead smoothly and the new system of Office information collection and copy distribution is to be put into effect from the beginning of 1976. Local editors have been appointed in eighteen laboratories around the world, who will collect material for transmission to the central editorial office at CERN where, as in the past, the issues will be prepared. In Europe, distribution will be made in bulk to a number of national centres which will then organize the circulation in their own countries whilst other countries will continue to receive copies directly from CERN. In the United States, the journal will be reprinted from proofs supplied by CERN and distribution will be organized there from the Fermi Laboratory. In addition to the regular contacts maintained with the press and television, a special visit to CERN of the Italian press was organized in October. Altogether some twenty-one scientific journalists were received and heard talks from senior members of the staff as well as seeing the installations of the Organization. The experiment was made of taking a member of a national delegation (Sweden) into the PIO as an associate for one month, during which time he participated in the work of the office and brought up to date documentation destined for his own country. The success of this initiative was later evident from the renewal of press interest in Sweden in the activities of CERN.- The number of visitors to CERN again exceeded 10000 in 1975 with a high proportion of educational groups. A prototype slide/commentary unit has been designed which will provide the necessary experience for equipping the site with informational units placed at strategic points. A new model of the CERN high-energy machines has been designed by one of the regular CERN guides, largely on a voluntary basis. The first section is being built to check out the presentation. A series of talks to the guides by senior staff has been instituted to explain new equipment on the site and to provide a forum for the discussion of CERN's information policy.

    157 The demand for visual information in the form of Alms, slides and photographs continues and better facilities are now needed for storage and viewing. Copies of the film on BEBC are now available in English and German as well as French and the revised version of "Inside CERN" including the latest views of the SPS will be available in English, French, German and Italian early in 1976. The technical series on the SPS now comprises "Travaux souterrains" and. "Géodésie et Métrologie" (both in French only) and "The SPS Magnet System" (in English and in French). The film on the beam transfer system will be available shortly in English. The standard documentation has been kept up to date but the technical series has suffered from the lack of effort available in both the PIO and the relevant technical Divisions. It is hoped that studies now in hand will show how this situation can be rectified. For the past eighteen months one member of the PIO has been detached to prepare data on the history of CERN. A number of discussions have been held with senior people concerned with the creation of CERN and with early experimenters. Information is being collected on the construction of the PS ready for the historian to begin work.

    Translation During 1975 the volume of work increased by about 10%. As in 1974. the Service and Minutes provided minute-writers for the Working Group on Pension Policy. The Council gave its approval to the Programme for the Construction and Bringing into Operation of the CERN 300 GeV Laboratory at its Forty-fifth Session held on 19 February. 1971. Eleven of the twelve Member States of CERN participate in the Programme viz. Austria. Belgium, Denmark. France. Federal Republic of Germany. Italy. Netherlands, Norway. Sweden. Switzerland. United Kingdom. It has been agreed that the cost of the Programme should not exceed 1150 million Swiss francs at 1970 costs and constant prices and the duration of the Programme should not exceed eight years. The Council appointed Dr J.B. Adams Director-General of CERN Laboratory II. •fïfiSS R. BILLING!! 1

    p/VRadio-Frcqucncy (RF) t C. Zt-ITLER

    " BeamiJransfcrjBT)" ü. I>E RÄAD

    Power Supplies (PS) S. VAS DER MUER

    Controls (CO) M.C. CKim'Lirv-MiLi-iNü '

    Director-General J.B. An\Ms | Survey (SU) " J. GERVAIS!: Deputy to the Director-General " II.O.WCMLK

    Radialion (RA) -"K.J. GOEHEL

    Experimental Areas (EA^ ^ - - G. BRIANTI

    Mechanical Design (ME) '"• H. HoKlsm RGliK

    Parameters (Dl. PA) E.J.N. WILSON

    Planning and Budget-1 DI PL) B. MIL\ÙN -Site Installation (SI) R: LÉVY-MANDEL Contracts and Purchasing (DI CP) R- FLORENT

    Personnel N.F. BLACKBLTIXE (detached from Laboratory' I) - Administration Service (SA) -"" - ":.A. K LEIN' -> Introduction

    The year 1975 was a very eventful year for the 300 GeV Programme. In January, the depressing discovery was made that a cleaning fluid, used in the manufacture of the coils of one type of the irain bending magnets of the Super Proton Synchrotron, had destroyed the ground insulation of about 30 coils and probably would ultimately ruin the remain­ ing 250. In the autumn came the news of budget cuts and staff reductions, and in November, there was a strike of the workforce of the main contractor, which brought all the work on the North Experimental Area to a standstill. During the whole year the economic difficulties in Europe affected the firms supplying equipment for the SPS, causing in some cases delays in deliveries,- and in a few instances no deliveries at all owing to the firm going bankrupt. Managing the 300 GeV Programme during the course of the year therefore required considerable flexibility in planning and called for much improvisation and ingenuity. It was with a certain feeling of relief that we reached the end of the year with the Programme schedule intact. Indeed, looking back at the year's work, it is remarkable how well we have done in the circumstances. In particular, it is worth noting the splendid efforts made by the members of Magnet Group, who had to take apart and rebuild 280 magnets to restore their insulation, and who nevertheless managed to install the last magnet in the tunnel exactly on schedule. Concerning the progress made during the year with the other parts of the SPS machine, reference is best made to the individual chapters of this report. Very briefly, the civil engineering for the accelerator and its beam lines to the West Experimental Area is now finished, the main electricity and water distribution system for the machine is complete, the magnet system is in place and partially tested and its power supplies installed. The high-power RF system for accelerating the protons is installed in the machine and tested, the beam extraction elements for the North Area beams are installed and those for the West Area are being put into place. The injection system from the PS to the SPS is mostly installed, the vacuum system for the machine is nearly complete and seems to work very well. All the control computers are installed and most are in use. The radiation monitors are being installed, and, finally, a recent survey shows that the elements of the accelerator are reasonably well positioned so that a final survey and alignment in 1976 should put them into their final position with the required precision. Indeed, the main threat now to getting proton beams to the West Area at the end of 1976 seems to be the very late delivery of the quadrupole magnets for the beam transfer lines, and we can do very little to improve this situation apart from encouraging the firm to do better. However, on a big project such as this, one is always conscious that next week or next month something could turn up which could easily upset today's confidence. Therefore we hope for the best and try to anticipate the worst.

    162 Since this turns out to be the last year of Laboratory II, although not, of course, the last year or the 300 GeV Programme, it is perhaps the appropriate occasion to say something about the staff of the Laboratory. I suppose it is obvious to everyone that the quality of the SPS machine depends on the quality of the project staff and its construc­ tion schedule reflects their enthusiasm. It is one of the attractions of a big project that it briugs together all kinds of people and gives them, for the duration of the construction, a common purpose and a single goal. The disadvantage is that the project comes to an end one day when the purpose is achieved and the goal is reached, and what has held the project team together during all the years of construction melts away. We have now reached the time in the 300 GeV Programme when our first goal is in sight and the staff are wondering and worrying about the future. Of course, all projects reach this stage at some time, and the change-over from construction to operation is never easy. It is more than usually difficult in this case owing to the quite fortuitous coincidence of the economic recession in Europe and the need to reduce budgets and staff at CERN, and the reorganization going on at CERN associated with uniting the two Laboratories under a new management. All this adds to the worries of the staff and their uncertainties about the future, and one of the big problems in 1976 will be to carry out the transition from the construction phase to the operating phase of the SPS in such a way as to maintain the enthusiasm and spirit of the staff who are now working so hard to finish the machine.

    «Jdw/v\ CLVHQ

    JOHN B. ADAMS Director-General CERN Laboratory II i-ï-,——~ . t.: lou^a

    es*- ^-"^

    'mi OT Jfcl«

    £*ö^ The 300 GeV Accelerator Programme

    Underground work Site Installation During the course of the year all the underground work, including the SPS tunnel, Group the transfer and the neutrino tunnels, was completed. The delays m the work which occurred in 1974 were partially absorbed by the firm this year and the work programme in the main tunnel was two months in advance of the schedule established in 1973. This made it possible to speed up the installation of machine components in the tunnel. During the year, the following underground works were completed and made avail­ able for installation work. The superstructure of access shaft PP1 was finished in March and the lift was put into service in August. The superstructure of shaft PP4 was completed in June and the lift was put into service in October. In access shaft PA6, the superstructure was finished in March and the lifts were in operation by July. The top of shaft PGC was sealed in October. The long straight-section LSS4 and the half-sextant of tunnel TS4 + were completed in February, TS5 — in March, and tunnels LSS5, TS5 + and TS6 — were ready in April. In May, tunnel TS6 + was completed, and LSS6 and TS1 — were finished in June. Tunnel LSS1 was ready in July. In the transfer tunnel TT10, the junction with TT2 was completed in February and the junction between tunnels PGC and LSS1 was finished in July. In June, the transfer tunnel TT60 was completed and the junction with TT4 was finished at the end of the year. The shaft superstructure of the neutrino tunnel PA7 was finished in October and the lift was in operation at the end of the year. The decay tunnel and the neutrino cave were completed in June and July respectively. At the end of the year, the measurement shafts were finished to ground level. The 425 iron blocks, each weighing ten tons, for the muon shield were installed bv the end of November.

    rtaure I Tin' ir.in>ft-r hiniu'f.s running lo\\ürtI\ the Xarth Experimental Aren: in tar tareijrnund is the end

    Auxiliary buildings Building BA7 was the last of the auxiliary buildings to be finished. Construction started in March and was completed at the end of the year.

    Electrical power installations The contract for the supply of electrical power to the Laboratory II site was con­ cluded with Electricité de France in September, after long and detailed negotiations. The 380 kV grid line to the site, which was put into service in November 1974, suffered considerable voltage interruptions during the summer owing to storms. These interruptions were of short duration — 20% voltage reduction for 20 to 150 ms — but long enough to disturb the control computer system of the SPS. Consequently, an order will be placed early in 1976 for no-break power supplies for the computers which will make them independent of the voltage drops on the 380 kV line. The system for measuring the pulsed and mean power levels on site and the power consumption was put into service in February. Since October there has been com­ puterized surveillance of the power consumption during peak periods and certain equip­ ment is disconnected if the prescribed maxima are exceeded. During the year, the remaining auxiliary buildings, BA4, BA5, BA6 and BA7, were successively connected to the 18 kV distribution system. At the end of the year, the 14 groups of IS kV cells, together with the 19 trans­ formers (18 kV/380 V), were installed and put into service.

    Cooling water installations The general lines of a contract for the supply of cooling water to the site were presented to and accepted by the Finance Committee in October. The pumping and water treatment station at Le Vengeron, financed by FIPOI, was first tested in July, as a result of which some modifications had to be made. These were carried out in September and October during which time CERN Laboratory II was supplied with water from La Planta. In July the same tests were carried out at the pumping station at CERN and at the cooling towers through which the water passes before being discharged into.the Nant d'Avril. The tests showed that the system was generally satisfactory but that some elements, such as the regulation of the main discharge valves, needed modification. These modifications will be completed by February 1976, but in the meantime, the system can be used.

    166 Infrastructure equipment for the SPS The ventilation and air conditioning equipment for the tunnels was installed and put into service in PA6 in July, and in PA1 and PA5 in August. During the last two months or the year the equipment temporarily installed in PA3 was moved to PA4, and PA3 was equipped with its final plant. At the end or the year all conditioning equipment was in service, except for the local heat exchangers needed in the long straight-sections and the transfer tunnels. Progress with the water cooling equipment in the auxiliary buildings was as follows: auxiliary building BA1 was finished in November 1974 and building BA3 was in service in the same month. In February 1975 building BA5 was completed, BA2 was in service by August and BA6 was completed in September. Auxiliary building BA4 was completed in December. The water treatment plant to supply the whole SPS with demincralized water was put into service in BA4 in October. Work on this contract was practically finished by the end or the year — only the plant in BA7 is yet to be installed. The piping work for deminera- lized water, compressed air and raw water distribution progressed satisfactorily, and the work in the tunnels and auxiliary buildings was completed and tested by the end or the year, with the exception of some final testing. Of the 17 groups of low-tension electric cubicles, 15 are now installed and in service. The remaining two for BA7 will be installed at the beginning of next year. The electrical distribution system in the tunnels and auxiliary buildings was completed except for installations in the neutrino area and the TT60/TT4 junction. An enormous effort was made this year to follow closely the completion of civil engineering work with the installation of the service equipment and this helped consid­ erably to advance the SPS Programme. About 70 km or piping were installed and about 250 km or electrical power cabling were laid in a period or about 18 months. Finally, a contract was placed for a special crane, which is entirely automatic and programmable, for the highly radioactive areas or the neutrino cave and target halls.

    North Experimental Area

    Infrastructure The infrastructure work for the North Area, including the road system, technical galleries, and raw water distribution, which was started in July 1974, was finished in July 1975 in spite or delays caused by heavy rain.

    Civil engineering work The civil engineering work started in March with the extensive excavations required in the North Area and the schedule was respected despite very bad weather. By the end of the year the slate of the work was as follows: tunnel TDC2 concreted to 75% Hall TCC2 concreted to 40% HallEHNl concreted to 75% steel work to 50% tunnel TT83 concreted to 45% tunnel TDC8 concreted to 80% tunnel TT85 concreted.to 90% Hall EHN2 concreted to 20%. A strike or the workforce delayed this work by several weeks. .j^^^^L^^m^&sss^SÊm

    r'niim- 2 \tnih l.\j\rtmcntiü Aren m tliï /luvi/mnin/ tun Iv MVH the lauinhiliini^ at Hall l.ll \ I mi'i/Min/ii/ .ill • Mill in- CER.\-là.lll'f,

    Some problems arose with the short underground galleries from BASO to TCC2 owing to the problems caused by the moraine in this region. Modifications were made to the programme to avoid delays since this work is on the critical path. The execution plans for the civil engineering work of the North Area, made by an external office, are complete. A contract was placed for all the painting work in this Area.

    Service equipment A contract was placed in July for the electrical power equipment in the surface buildings of the North Area and a contract for the IS kV distribution cables was placed in June.

    Future 3 -- Hull Ê//.V/• the

    16S A request for tenders was sent out in October for the electrical power equipment for the underground tunnels and. at the same time, another was sent out for the 18 kV equipment. A contract was placed in September for the water piping system in the technical galleries and another was placed in October for the piping in the tunnels. A request for tenders was sent out in December for the piping and drains in the surface buildings. A request for tenders for the air conditioning systems for the tunnels was sent out in September and for the air conduits in November. A contract was placed in December for the five travelling cranes required for the auxiliary buildings of the North Area. Finally, studies were made for a central cryogenic plant for the North Area, consist­ ing of a local liquéfier, compressors and purification plant for liquid helium, gas and liquid storage tanks, a building for all this plant and a distribution system for liquid helium and the recovery of gaseous helium. This central plant is intended for all users in the North Area and will be ordered according to the future development of this Area.

    The year 1975 saw the completion of deliveries of the components of the SPS magnet Magnet Croup system and their assembly, testing and installation in the ring tunnel. The last ring magnets were installed in December, thus meeting the original schedule in spite of the problems caused by the acid-contaminated coils. During the first half of 1975. full-power tests began on installed sextants of the magnet system. These continued in parallel with the missive re-building programme which comprised the disassembly, re-insulation of the coils and re-assembly of 280 MBA type dipoies. As completion of the main magnet system approached, it was possible to reduce progressively both the space occupied in the Assembly Hall and the workforce. The temporary labour force was reduced from 29 during the period of peak activity to 11 at the end of the year. In addition, ten members of the staff were assigned or transferred to assist in the work of other SPS groups and it is expected that only a small nucleus

    /-i(/'"v 4 A/ui/m-ls imttillal tint! nmmvrfj m tlw UUUIL-L FitturL'5—A iwrmiltiiml an cnhryvtl quadrupoie n-atlvjur illslulhliun. CERX-U23.75) (CERN-331J)JJ) Figure fi — Sating alignment references un a thrum athitr scxtupok: Fiqnre 7 — .4 Laiulatt tlampimj antipole prior to installation. ' CEP.S-2SS.W.751 I CF.RK-232.IU.751

    of staff will be needed as a magnet team to complete the assembly and testing of MBB type dipoles required for the extracted proton beam lines. The main activity of the Group is now directed towards completing the documenta­ tion of the whole magnet system, and several staff are taking an active part in the préparations for the running-in of the SPS during 1976. In conclusion, it is worth noting that during the four years since the first few staff arrived, the main magnet system has been designed, manufactured, precisely measured and installed in the tunnel. It has been possible to improve on the specified field tolerances in all respects. Also, the considerable effort expended on optimal economic design of the components has allowed the machine to be equipped for a peak energy of 400 GeV within the original cost estimate for a 300 GeV magnet system.

    Powt'r The assembly of the main power supplies for the dipoles and quadrupoles is finished Supply Group and power tests have been performed on about one half of the rectifier stations. First tests were made with one of the stations in conjunction with the power supply computer. The latter evaluates the results of field measurements during each pulse and applies corrections to the excitation profile for the subsequent pulse. Preliminary results showed that the required precision will be obtained by this method. The control software for the definition and adjustment of magnet cycle parameters has been written and tested.

    7» The reactive power compensator has been installed and tested. Although application of the full pulsed power is not yet possible, tests at constant power indicate that both the stabilizer and the harmonics filter will perform as expected. About two thirds of the more than 200 auxiliary rectifiers have now been delivered and installed. The associated low-level electronics modules have been ordered and their delivery is progressing in step with the testing of the rectifiers.

    The two large RF cavities, which will be used to accelerate protons in the SPS Radio-Frequency machine, were completed this year and installed in the tunnel. The tuning of each cavity Group section was carried out by first measuring the resonant frequency of the section with a set of drift tubes used especially for this purpose, and then adjusting the distance between the supports of the final drill tube assemblies before brazing at CERN. In March the first two sections were assembled together and equipped with input and output couplers, in order to adjust the matching of the latter. These two sections of the first cavity were installed in the tunnel in April, thus enabling high-power tests to be performed for the first time. The first cavity, comprising five sections, was completed and installed in the tunnel in July. By August all components for the second accelerating cavity had been delivered to CERN. The first section of this cavity was installed in the tunnel in October, and the complete cavity installed in December. The commissioning and the acceptance of the power amplifier plant was also finished this year, including all auxiliary equipment such as high-power feeder lines, loads, etc. All three power amplifier chains work satisfactorily, in pari-cular with regard to parasitic modes which were completely suppressed. The first batch of power tubes showed a rather high failure rate but after some modification of the tube design the failure rales are now normal.

    M-iirt .S' Belli SI'S u tïlfraimç Lti\i- uc\ mMttllvJ in llic tuiuiti ,mil ready lit [turpi ills RF pmuT /nr tomlilHuimg. CI:K.\-IV?.J :A,

    171 Fiiiure y The SPS lif pmver amplifiers durimi tfWHm'w'imiili/ where the aeet'h'ratiiui ftnilifi arcreplineil hy adianmvhad n-M'.v- fur llefl Meat pielure, lCERN-196J.76)

    In the autumn, continuous operation of one complete power chain, i.e. amplifier and cavity, was started under practically the final working conditions except for a slightly reduced accelerating voltage. By the end of the year, both power chains were ready and test operation under full power had begun. Most of the units of the beam control system are now installed in the Faraday cage (i.e. RF control room) and have been used in the above-mentioned tests on the cavities and power amplifiers. All the important components of the low-level system were successfully tested in the PS machine under real operating conditions with a proton beam, in particular the frequency program, which is derived from the magnetic field of the machine. All the modules for the radial and the phase loops are completed and the system for controlling the equivalent RF voltage, which is more complicated than with conventional standing wave cavities, is approaching completion. As far as instrumentation is concerned, the various wide-band pick-up stations built by the RF Group are either installed in the tunnel or are under construction. The very fast electronic circuitry which is used in conjunction with these stations has been built and tested. Complex measuring devices for the RF equivalent voltage and the instan­ taneous frequency have been constructed. Practically ail of the installed equipment can now be controlled by the computer system, though many of the application programs remain to be expanded and refined. The first prcbunching cavity for the PS machine was tested under RF power in March. This cavity, complete with damping lines, was installed in the PS ring early in May. The power amplifiers for this cavity (25 kW, 200 MHz) were also built by the SPS RF Group. This first cavity is now operational and has proved to be very efficient in providing a modulation on the PS beam before it is injected into the SPS machine. It will, in addition, permit longitudinal instability studies at high intensity. The low-level circuitry for this cavity was also tested with the proton beam in the PS. Further studies on beam dynamics were carried out in the PS, to study the longitudinal transfer scheme, and a simulation experiment performed at the NAL machine brought confirmation of the existing theory.

    172 Concerning the interaction between the SPS equipment and the circulating proton beam, all the large tanks used in the SPS ring for beam dumping, injection, extraction and beam monitoring were measured this year, in urder to determine their longitudinal coupling impedance, and, where necessary, they were fitted with damping resistors.

    Injection transfer line Beam Transfer Group The installation of the TT10 transfer line which brings the PS beam to the SPS has been completed and system tests are beginning.

    Fast kicker magnets for injection, extraction and beam dumping The assembly and laboratory tests of all fast kicker magnets have been completed. The injection kicker magnets, the kickers for Q-mcasurcments and the vertically deflecting kickers and the horizontal sweeping magnets for beam dumping have been installed. The kickers for extraction will be installed early in 1976. In order to obtain the desired pulse shape, each kicker magnet is connected to a number of matching boxes which contain capacitors or resistors. Some of these required extensive development work and life tests, such as, for instance, the terminating resistors for the beam dumping kickers, each of which has to withstand a peak power of 300 MW. Nevertheless, all 120 matching boxes have now been completed and their installation has started. The high-voltage cables which connect each magnet in the SPS tunnel to its pulse generator in the auxiliary buildings have been delivered and installed. The manufacture and assembly of the 400 connectors for these cables is progressing according to schedule. The HV pulse generator of each kicker magnet consists of a pulse-forming network (PFN) and a set of HV switches. The components have been standardized for all systems

    Future /(I — The vacuum tanks eontain- inii the pulset! mat/nets at the haemal beam dumpmti system at the SPS.

    173 l-'iaiirc II The pulst' tlem'rtilors m llw cqitipinvnt buiL'inn IIA4 for llw ewllallon of llw fusi pulsed Hltiiiiwl-, at lite beam liumpuu/ M'Mi'iii C£K.\'-?J 2Jfi :

    and two production lines have been set up. one for assembling and adjusting the 14 PFNs. the other for the production of the 26 HV switch assemblies of the "thyragni- tron" type in their coaxial housings. Each PFN and the corresponding switches are then tested together at the nominal working voltage of 60 kV, before being installed in the auxiliary building. Only the pulse generators for the fast extraction system remain to be assembled and tested. The 70 kV d.c. power supplies for recharging the PFNs of the injection and beam dumping kickers have been delivered. The assembly of the resonant charging power supplies for the fast extraction kickers and Q-measuring system is progressing according to schedule. In parallel with the construction and installation of the final equipment, much effort has been devoted to the computer control of the kicker systems. The software related to

    Figure 12 A \liorl ••trttiilhl-scctiail at the SPS wilh. Imm k'H to nain, il ll.ttn in loua ilipok maçitiel Itir mitkilltj tt liariziOllul clasctl-orhil hump, u ilipok tin- clast'il- orbil an'ri'clion ul iilicctiun. a niiliatioil ilelvclar ami un ckclra'iîauv phk-up far llic nwttMiri'mvM of tin' tia\al-arhu ptHition. ICERN-5I2.V.1}!

    174 the interface between computers and hardware is now complete and application pro­ grams are being written and tested on the prototype kicker system, which is kept operating for this purpose.

    Extraction system The extraction system in LSS2 for the North Area has been completely installed and has been tested with its power supplies, using the satellite computer for extraction. The components of the extraction system in LSS6 for the West Area are now being assembled. Although the West Area will come into operation first, this order of installation was dictated by the order in which the different parts of the SPS tunnel were completed. The first tests of the installed extraction system in LSS2 gave satisfactory results. The electrostatic septum is made up of four separate wire septa with a combined total length of 4x3=12 m and has a design electric field of 100 kV/cm. In the tests it was possible to maintain a voltage of 200 kV across a 17.5 mm gap (corresponding to an electric field of 115 kV/cm) with a sparking rate of less than two sparks per hour. The pressure in the four electrostatic septum tanks in LSS2 is now 10"8 torr. It is hoped that the combined effects of the low pressure and of the ion collection electrode:), which have been installed to remove the ions created by the circulating beam, will give adequate voltage holding characteristics in the presence of an accelerated beam. The wires of the installed septa are made of tungsten and have a thickness of 0.12 mm. It is intended to install in LSS6 one septum section with 0.08 mm thick wires made of tungsten-rhenium alloy. Each three-metre-long wire septum is straight to within 0.05 mm. A special system using a stretched wire and inductive position detectors is being installed for accurate alignment of the four wire septa in line with each other.

    Future M Otu' t>f nw nu) in\tuiit-ii fvrthlwn ihiinncl'. U>r tlic transir til the < ir. ukitliiit prtiutn hcum ttt llw iwum Irwis/I'r iuw\ itn\tinl\ tlw t'\pt'rimt-mal iirvtf> Tlw thiintn-1 nuis/us .smu'.swre/i til four elt'ctrtt- \lttltt M'p/ij. ititii ptitr-, tij thin t.t'[

    175 The Tour vacuum tanks with their thin septum magnets and the five tanks with their thick septum magnets in LSS2 were tested with their power supplies at 7500 A and 24000 A respectively, and with their water cooling system which operates at a pressure of 25 atm. One septum coil which developed a leak was replaced, and the pressure in the entire extraction region is now close to the SPS design pressure of 3 x 10"7 torr. All the 73 auxiliary magnets required Tor extraction, comprising dipolcs, quadrupoles, sextupoles and octupoles. have been delivered, measured and installed.

    Beam monitors Praciically all components for the three standard types of monitors which were originally foreseen for the beam transfer lines, that is the secondary emission monitors for beam intensity, beam position and beam profile measurements, the miniscanners and the luminescent screens, have been delivered. Their assembly, alignment, testing and installation are proceeding as planned. A fourth type of standard monitor lias now been designed. It consists of a split-foil measuring head mounted on a miniscanner mechanism. This type of beam monitor enables the position of a proton beam which is displaced with respect to the centre of the vacuum chamber to be measured and will be used for angular steering of the protons incident on the targets in the West and North Areas. A number of beam monitors with measuring heads of different shapes, for beam observation in front of the injection septum magnets, beam dumps, splitters and targets, have been ordered and their delivery has started.

    Extracted proton beams to the West and North Experimental Areas Long delays have occurred in the delivery of the 135 beam transfer quadrupoles of 1.5 m and 3.0 m lengths, which will be used for all extracted proton beam lines, mainly because the contractor had underestimated the manufacturing facilities needed for this

    / untre 14 /*;<-..,M'»JMI H/ n \/i/jm-r mannet tar an internal pralon beam lnn\ Thh mannet '.plilt, tbe rcrlicall) cnlartictt beam into Fiaure 15 — .-1 radiation-resistant uni Jar a '.plitter magnet, wound three branch:'* antl lUjk'its the central branch laterally, prior to their from mineral-insulated cable. This eable con\i\l\ of a water-cooled tranter to three target .-.luttons for lite lVc.\t Experimental Area. copper conductor ivltieh is electricully insulated Irani its wraundina ICERX-224.1.76I rectangular capper tube by niuunesiuiu o\ide. (Cllli!\'-2Z2.I.76 )

    176 contract. At the end of the year about 30% of the quadrupoles had been delivered and the delivery rale was about 75" « of the contract mil delivery rate. This is sufficient to permii the completion of the TT60 beam line to the West Area on schedule in the autumn of 1976. but the quadrupoles for the TT20 beam line to the North Area will not be installed until 1°77. About half the beam transfer steering dipoles and about two thirds of the C-magnels for the beam switches in the underground switchyard of TT00. which direct the protons to the neutrino targets, have been delivered. The deliveries of both these components have been made in time for the installation schedules to be respected. The first of the coils fur the steel septum splitter magnets, which are made of square, hollow, water-cooled, mineral-insulated cables, was delivered in October. The production of the cores for these magnets, which arc about 5 m long, necessitates very precise machining but it is progressing well at the manufacturer's works. The first core was delivered in December and conforms entirely to the CERN specification. The assembly of lhcse magnets and their vacuum enclosures will be done at CERN.

    Beam dumps and targets All collimators and dumps needed for injection, and the collimators downstream of the electrostatic septa for extraction, have been installed. Prototypes of the scraping targets upstream of the dump blocks in LSS4 were tested successfully and the final scraping targets are now being assembled. The design of the absorber blocks for the internal beam dumping system has been completed. Their water-cooled cores, which are made of aluminium and copper alloys, are under construction. The water-cooled cast iron shields, which surround the cores, have been delivered. Movable beam-dump absorber blocks will also be installed at the upstream ends of the TT20 and Ti 60 beam lines for the disposal of the proton beam during extraction

    / i-urt ]!. 0:u utile nv n>lliml..<>r>. tor the miecmm beam transfer r'iaure II Awembly of a water-nnded nlunrber block tor the '""• TTln 1: /vriiui. the colhmalion o) 'he beam intss-yecinm thrtmuh internal beam i/umpin;/ synem «/ the SI'S, Its mir iimv\l\ of an the -.c!c< tian at a Jumncl hv a lateral déplacement of the circular hlnek. aluminium cylinder Jotlmved by a copper cylinder and it i\ snmnmded • LBRS-2US.I.7A1 h\ two cast iron half cylinders of 0.96 m diameter. tCURN-274.2.7b)

    111 Fhfitrv IS -tu afaorbi-r I'loik ot 22 tons jtir hfum iliimpiml I» tin' I'Wi'ni«/ /vimi

    studies. Their water-cooled copper cores and their cast iron shields have been manufac­ tured. The remotely controlled supports for all the dumps are under construction. Copper collimators in front of the splitter magnets, upstream of the targets, will shield the steel septa against the incident proton beam. The design of these collimators and their vacuum tanks is complete and all components have been ordered. Six different target stations will be needed for the generation of secondary particle beams for the West Area. Their target boxes will each contain several targets which can be selected for irradia'ion by the incident proton bean. These target boxes and related monitors will be supported by a common movable frame and completely surrounded by cast iron shielding blocks. The design of the target boxes and their supporting mechanisms has been completed and the ordering or their components has been started. The shielding bloekb are bein« manufactured.

    Elïïlïonits The Electronics Section is building about one hundred racks with electronic equip­ ment which will be located in eight different auxiliary buildings. About half of this equipment h;is already been installed and is now being used in the various system tests w hich are in progress.

    Cuiuml-, Group Computers

    During the year, control computers were installed in the main control room and in the auxiliary buildings according to schedule. Eighteen of them are now in place and connected to the message transfer system. Because of the extensive use of the computers rs I unm IV I lu ^mlml mum lur llw SI'S I In tin.; liltlllhtli (uti'Lriiiiir • •I h, an: lint * tin Imnlfi tuiiuili' is ttir I.,!-.,.««.i.n,...,,.«.,.; < i.R\-iriii~f

    for testing electronic equipment and the overlap of the requirements lor testing with those for installation of the computers, it was decided to order another computer to be used for equipment testing, as this requirement will continue even after the accelerator is running, for maintenance and minor development. The reliability of the computer hardware is improving but has not yet reached the level required, the mean time before failure being about 2000 hours. This includes the failure of a number of power supplies owing to rapid variation of the mains supply, and steps are being taken to provide a more stable supply for the computers. Other sources of faults arc being traced and eliminated progressively, and it is expected that the reliability will improve substantially when this work has been completed. All the remaining equipment for the message transfer system was delivered in February, and passed the acceptance tes;s. which involved the transmis­ sion of strings of messages between up to ten computers at the maximum rate. Since then, all eighteen installed computers have been joined into the system and experience with running the multicomputer system has been gained. However, there is still a continuing demand to operate mam of the satellite computers in a "stand-alone" mode.

    I hiiif!' -'<' I'm "I llic n'liin'l o'»ls<'/t's. CM lli'iwpi * f.-r ii,n.--fiTf(i i/i-./'/,ii .in'on

    llh Id; Ulli! llh alarm M rt;n ml im' ntilll. /Jrî.miî !ht-tn ai, the iiiti'r.iilitt- Mn\-n\ n^tl m the "nt'ritfjM/i "t ill,- m, ckratiir. i /K\.;-YI jo--

    179 Fiqurt' 21 Siinlc ot ihc

    disconnected from the system, for testing equipment in (lie tunnel and auxiliary build­ ings, so the configuration of the system changes from day to day and this will continue until earlv in 1976.

    Interface equipment There have been some delays in the deliveries ofCAMAC crates and modules from the manufacturers, which has required some re-scheduling of the order of installation, but nearrt all of the 800 units have now been received and the 550 units due for installation b> the end of the year are in place and tested. As other groups completed their designs during the year, it was found that the original estimates of their requirements for the multiplex system had been too low. and it was necessary to order an extra 1200 modules and crates. So far. 3600 modules out of a total order of 4000 have been accepted and over 2200 of these have been installed and commissioned in the auxiliary buildings, in accordance with the planning. A long-distance version of the multiplex system is needed for communication with the PS, etc. and the design of the controllers and drivers for this is complete and prototypes are under test. The first of the special high-precision systems Tor d.c. measurement has been installed and the contract for the assembly of the 120 modules for pulse-height measurement has been awarded. The latter is behind schedule owing to the failure of the manufacturer to meet the contract delivery date for analogue to digital converters, but sufficient have been built inside CERN to avoid delays to the programme. The requirements for timing modules, which plug into the multiplex crates, has increased to over 600. More than 400 have been delivered and accepted, and most of these arc installed. The design has been completed of the central timing system to replace the temporary arrangements which already pro\ ide sufficient facilities for the initial commissioning of the equipment. The design of the function generators for controlling the current wave shapes in various correcting and extraction elements has been completed and a number of units were made for evaluation and testing with the power supplies. A contract was placed for the assembly of 250 units and about a third of these have been delivered. Software On the software side, it was necessary to add some facilities to the real-time operating system SYNTRON. to include the message transfer software, to provide dynamic buffer management and resource allocation and to add a file handling system. The new operating system, called SYNTRON II, has been in operation sufficiently long to become stable, and in future only minor changes are expected. This, together with the NODAL interpreter, gives (lie facilities for running a main program in one computer, executing parts of it in other computers, using files retrieved from the mass storage on another computer, and displaying the results on devices driven from yet another comput­ er. The parts of the handlers for the distributed data base, called data modules and equipment functions, particular to the various types of equipment, are being written and nearly sixty out of the seventy-three that will be required have been completed and tested with the hardware. One of the reasons for the provision of the interpretive language NODAL was that it enables the equipment groups to write their own applications programs. A "tree" structure for linking and calling these programs has been defined and. although slow to start, this work is gathering momentum, and programs are now available for many systems, both for testing and commissioning the equipment in a "stand-alone" satellite computer and for operation from the main control room. After a long period when one of the control consoles was used for development of display programs in a simulated system, and another became available for use with the message transfer system, by the end of the year, all three consoles were connected to the system and available for applications program development and control of apparatus in the auxiliary buildings. A system has been developed for the alarm computer, which can

    hniurt- 22 The nmipun-r-tunlmUciï

    "tdï-btitid itdt-o ilinl niiillfillu- \\illf-it Ci.R\-i4l.lU~?

    181 accept messages from surveillance programs and display the appropriate text. The operating system SINTRAN III is being used in the service computer where additional facilities are required, and a special version of the message handling part of SYN- TRON II has been added to it, so that the service computer can be addressed by the system in the same way as any other computer.

    Communications The large video switching matrix is complete and in operation, and the similar system for switching nearly 1500 analogue wave-form signals to the oscilloscopes on the con­ soles is being installed. The programs for switching between signals, using a special touch button panel, have been written. All the television cameras and amplifiers have been delivered, and installation is proceeding according to schedule. The public address and intercommunication system has been installed in six auxiliary buildings and the associated tunnel sections. The access control system, using punched plastic identity cards, has been used to control the access to sections of the tunnel where tests of the magnets and power supplies have been taking place. The access control console in the main control room has been equipped with temporary panels for these tests, and the final panels are now being manufactured. The principles for control of access to experimental areas have been laid down, and the first batch of doors has been delivered.

    Beam monitoring Turning to the instrumentation, all the standard ring beam-position pick-up units ha\e been delivered and five out of the six tunnel sectors have been equipped. About half of the special electronic equipment for these has been delivered and installed. A new type of position monitor has been developed for installation where a wider than normal aperture is needed and the prototype has been tested successfully in the PS. Parts have been ordered and sufficient have been delivered to assemble six of the eleven pick-ups required of this type, and they are being installed. All the power supplies for the orbit correction dipoles have been delivered and installed. More than half of the power supplies for the special stop-band correction inultipolcs have also been delivered and installed. The other beam monitors in the ring, beam current transformers, ionization beam scanners and the electronics for the Q-measuring equipment, have been installed and tested, using the computer system and the special programs needed for the fast acquisi­ tion of the data. A damper system has been designed to correct vertical and horizontal transverse instabilities of the beam, consisting of two sets of wide-band position monitors, ampli­ fiers and electrostatic deflectors. Any coherent instability will be detected, the signal amplified and fed to the deflectors in such a phase as to damp the instability. The two deflector tanks are ready for installation in tunnel scctoi 3, and the amplifiers and special electronics will be available in mid 1976. Electronics services AU the special electronics for the control of the various types of beam monitors in the beam lines has been delivered, and is being installed as required by the schedule. The majority of the control cables between equipment in the tunnel and the auxiliary buildings were installed during the year. This involved the specification, ordering, instal­ lation and testing of more than 10000 different cables, totalling over 1000 kilometres in length. In addition, several thousand junction and distribution boxes were manufactured and installed. The activity in the electronics workshop and drawing offices continued at a high level, resulting in the production of about 500 chassis and modules of various types, and the subcontracting of a further 2000 to outside firms. In addition to producing all the necessary drawings, printed circuit masters, etc. this section is also responsible for supplying thousands of modular power supplies, ventilation units and chassis for other users. The instrument maintenance workshop is responsible for all instruments in Labo­ ratory II. which now total 1900 units, mainly oscilloscopes, multimeters and pulse generators, with a total inventory value of over 6 million Swiss francs. About 200 of them needed repair during the year.

    Mechanical engineering and design office Mechanical The detailed design of components for the accelerator and beam transfer lines is practically finished. The available effort has been partially shifted towards the follow-up of orders with industry, the participation in tests and installation of equipment and the updating of drawings. An increasing effort is being required for the design, specification and ordering of target stations, different types of collimators for secondary beam lines and some experimental equipment for the North Area. One of the magnet handling vehicles was modified and equipped with two hydraulic tractors, suitable for the safe installation of 20-ton magnets in the beam transfer lines which have slopes of up to 12%. The special carriage designed for the remote handling of heavy radioactive components in the underground tunnels, such as beam dumps, splitter magnets, etc. was successfully tested. A special crane attachment was also built crane uttavhuwnt for remote UomUimj of nunint'i \ MI a raJttituiu c eimroiimcnt. tCl-:iiS-4t>ll.7?i

    and tested for the placing and removing of radioactive elements, without human inter­ vention on the floor, in larget hulls equipped willi cranes. The outside contracting of design and drawing office work has been further devel­ oped to compensate, at least partially, for the considerable reduction in temporary labour.

    Workshop The workload in the various workshop sections (mechanical, sheet metal and weld­ ing, chemical cleaning and the free access workshop! continued to be very high. A total volume of work equivalent to 20 man-years has been subcontracted to about •40 different local firms, mainly for classical mechanical jobs, whereas difficult prototype work, rapid interventions and delicate work on vacuum components is carried out by the CERN workshops. Other activities include the fabrication of coils for the extraction septum magnets, the assembly of pick-up stations. RF cavities. Ccrenkov counters, short straight-sections of the accelerator and the supervision of the free access workshop.

    Vacuum The Vacuum Section has received virtually all components for the SPS vacuum system up to the targets in the extraction lines. Series deliveries of standard vacuum chamber components for use in the experimental areas are far advanced. Assembly and leak testing of the vacuum system in the normal periods of the ring is 75"« complete. In five out of the six long straight-sections, as well as in the transfer line for injection, nearly all the vacuum equipment is installed. Pre-assembly has started of vacuum chambers for the West extraction line. High vacuum was produced in 50% of the normal periods. The design pressure was normally readied after less than 24 hours of pumping in the first pump-down. After

    1S4 { unite 2* IvM'juMi c/ i in mim /'i/'i-v in llli mii.th'ii /mini-/ »Mm/ ml inblltll m-lillilil imnlum {IR\A('i'<

    short subsequent interventions, the design pressure could be restored in a working day. In the long straight-sections, high vacuum was produced in the accelerating cavities, in the tanks of the extraction septa for the North Area and in some of the fast pulsed magnet systems. All the completed parts of the vacuum system can be operated via the local comput­ ers in the auxiliary buildings. Monitoring of vacuum systems from the main control room «as tested. The special application programs needsd for operation of the vacuum system from the main control room were delined and partly written.

    Installation Sectiun

    At the beginning of 1473 it was estimated that the installation of machine elements in the ring would be finished by the end of February 1976. provided the installation of general services started by mid June 1974 and all operations proceeded at an average rate of 32 m per day. The actual starting date was 8 July 1974 and. until now, the average installation speed of 32 m day has been maintained, in spite of many unforeseen difficul­ ties. The installation of the general services, e.g. cooling water and electricity supplies, was finished in October this year. With the exception of the West extraction system in LSS6 and the beam dump blocks in LSS4. the complete magnet system and all ether major beam elements were installed before the end of 1975. There is every reason to believe, therefore, that the original end-date for the installation of main ring elements can be kept. The injection line TT1Ü is practically complete, three months ahead of schedule. This was made possible by taking advantage of every shutdown of the PS and by making partial installations as soon as a portion of the tunnel was finished by the civil engineer­ ing firm. In the West extraction tunnel TT60 the piping and electrical distribution systems are almost finished. The installation of the beam elements themselves will start earlv in 1976. In the North extraction tunnel TT20 the infrastructure (water and electricity) is complete over the first portion of the tunnel, which brings the beam up to near the surface. The installation of power supplies, cooling equipment and control systems is nearly finished in the six equipment buildings around the ring and has started in the neutrino building. The dispatching of all material needed for the installation is organized using a computer program, which has proved to be very useful. Peak loads of up to 150 tons of material per day were transported to the underground areas. As the distances have increased, the fleet of transport vehicles has had to be increased and it now totals some 300 vehicles of all kinds. The general layout and installation drawings are finished and are being updated remilarlv.

    Radiation During 1975. the completion of the hardware for the radiation protection system in GGroup the 300 GeV accelerator and West Experimental Area was the prime objective of the Radiation Group. Work aiso continued on the development of the computer programs for estimating radiation parameters and on the control of radiation and radioactivity for the SPS site. Nearly all the site monitors installed outside the shielded enclosures and at some distance from the accelerator have been brought into operation and are measuring the radiation background on the SPS site. The program for monitoring the release of radioactivity was started and measurements are being made, using the ventilation and aerosol monitors. In addition, samples of water, soil, mud and vegetation are taken regularly from the surrounding areas and analysed in the laboratory. Half of the neutron monitors situated in the access ways are installed. All the alarm monitors to be installed in transfer tunnels and secondary beam areas will be delivered by January 1976: their installation has already started in the transfer tunnels. The

    I'ttlurc 2ft Imhilliittt'ii nl urn' o\ llw la^l vi/i- tmmmtr* im !iw SI'S \iU Hip

    i;I >iu f.W JHIIHC» iimund ihf SPS site. .'/n> Mjiiip/iiJi; pntiu (i \mnUiil nc\i to tin' ,'U hihUh- (itr.^-, f/n- /.i.»11 nier (ii'iir ti> tlh- \i»r//i / x/vnin.w.i/ //tj/f Vu /.

    moniior system for the West Experimental Area has been finalized, following the detailed shielding layout and access conditions which were defined in collaboration with the Experimental Areas Group. The ionization chambers and head amplifiers of the beam loss moniior system have been installed in ring sectors 2 and 3: the system will lie completed by March 1976. Monitors for checking radioactive material being removed from the accelerator areas (lift monitors and monitors installed near access gates) are nearing completion, and the radiation survey vehicle for the ring will be ready for operation in May. Provision for the software of the radiation monitor system required considerable effort. Programs for transmitting the information from the monitors lo the main control room, for display and logging, are well advanced.

    r^. ^

    I liiur, :.\ KiUl.iliiUJ flH- i nsmi/ tlw itxyacn imhx m imirai parameu-r. (CERN-7UJ4 '

    Routine radiation surveys and control ofradioaclive materials and sources on the site and during tests of neu accelerator components continued. A series of instruction lectures were gi\cn to SPS Mlal'f. covering the basic knowledge of radiation protection. The delivery of the first batches of different types of portable radiation survey instruments loi the accelerator and the West Area will be completed early in 1976. Prototypes of the personal alarm monitors have been received and tested, these monitors and their associated equipment will be delivered early next year. Shielding calculations using the muon transport codes continued and estimates were made of the muon levels in and behind experimental areas, particularly for the two North Areas. The Monte Carlo nucleon-meson cascade codes were further developed by introducing a new sampling technique (KASPRO) and more versatile routines for the cascade geometry (CYLKAZ and KAPRYZ). Estimates of dose and remanent radiation levels in the ring and the primary beam areas and calculations of neutron transmission through the ducts and access ways were completed. These calculations and the program development were supported by contributions made by visitors and consultants from different European universities. Selection lests l'or a large variety of different materials to be used in areas with high radiation levels continued. Tests were also made of the fire resistance of various cable- insulating materials. Recently work has concentrated on the materials and components to be used in the transfer tunnels and in the target and experimental areas. The prepara­ tion of long-duration exposure tests in the SPS of materials taken from the production line or identical *.o the materials used in critical accelerator components has started. The Group is collaborating with the Mechanical Engineering Group in developing special devices for handling radioactive beam line elements. The vear ]S>75 marked llic end of the preliminary alignmcnl of I ho quadrupoles and dipoles in lho SPS lunnel. and Ihc beginning ol" ihe final alignnienl work in the ring. Whilst these two activities, together with the field survey work in the North Area, are the most spectacular aspects of the Group's work, all of the sections, in addition to their own specialized fields, have made an additional effort in helping the Metrology Section with the alignments in the SPS tunnel. As in previous years, the Survey Group's activities have included Held survey and metrology work in both CERN Laboratories.

    Field survey The Field Survey Section has continued to furnish assistance for the civil engineering work. h\ providing the layout for the North Area. At present, the work site in the Area CMCIUIS over 2 km. As it is characterized by relatively deep open-cut excavations, the survoNors have constantly been obliged to repeat the measurements of the local triangu­ lation network to ensure that, as the civil engineering work progresses, the coordinates of the geodetic points located at the edge of the excavations are kept up to date, since the »lability of these points is not guaranteed even for short periods of time. More than half of the staff of the Field Survey Section have been engaged in this work. The other aspect of this Section's work is the assistance given to the groups respon­ sible for site maintenance: surveying and mapping for preliminary projects and follow-up of the survey during the construction period, and publication of maps at different scales for use by the CERN Divisions. This year, the work also included helping the official surveyors in locating the existing survey marks and siting new ones on the perimeter of the Laboratory II site. The Section had to install markers for the exact identification of the underground SPS supply sys:ems, after the contractor had been unable to carry out hi> own part of the survey work. In addition to these activities, which are of general importance to the site, the Section had to cope with more than 160 work requests Tor Laboratory 11 and 60 for Laboratory I. The duration of these operations ranged from one day to more than one month in certain cases.

    Metrolugy The measurements relating to the installation of the dipoles and quadrupoles in the tunnel were made by the Metrology Section. These measurements were performed as and when the various components were brought into the tunnel. This work was fitted into the time-table of other activities. Preliminary measurements were carried out separately for each sextant, using provi­ sional reference points obtained from the surface geodetic network. After the brackets had been installed around the entire periphery of the ring at the end of June 1975, measurements were made on the last sextant and a least-squares adjustment carried out on the complete set of SPS sextants. A preliminary alignment of the magnets was then possible. The final geodetic monuments located on the top of the auxiliary buildings were made available as the civil engineering work progressed. On 3 November, measurements Parted on the linal surface geodetic network. By the same dale, it had been possible to complete the final metrology of the brackets in the ring. The overall underground network had been adjusted by ihe least-squares method as soon as the surface network was complete and computed: it was then possible to make the adjustment, between six fixed terminals, of the long chain of braced quadrilaterals which had proved to be too flexible lo be computed with only a single fixed point and one bearing. On the basis of these results, the final positioning of the quadrupoles and dipoles started at the end of the year. The provisional measurements made in July showed thai the radial deviations did not exceed 6 mm and were concentrated in specific areas. Several precision levellings were made on the brackets in preparation for magnet positioning. After 7 km of levelling traverses, the average closure deviation was as little as 0.5 mm. As a check, a large levelling loop connecting LSS6 to LSS1, passing through TT60, TT2a and TT10, and the whole ring, was measured. This represents more than 18 km of precision levelling measurements. Transfer tunnel TT 10, which links. viaTT2, the PS and SPS, was aligned and levelled. The survey work in TT60 ^nd the neutrino tunnel is in course of completion, and the coordinates of the markets used for pre-alignnicnt have been calculated. The beam trajectory in TT60 Ims already been marked out on the floor. The geodetic measurements in TT20 have also been completed and the beam trajectory marked out on the floor in preparation for magnet installation. As is the case every year, the Section has participated in the measurement, alignment and levelling of the other CERN ai .clcrutors. namely the PS, Booster. ISR, and the new Linac. in close collaboration with the ISR Metrology Section, which, from the work standpoint, forms part of the Survey Group. Preparations for the installation of experiments in the West Area started on 1 July. The local network of this area was repeated to allow measurement and calculation of the coor limites of the grid which had already been used for 25 GeV physics. Using these reference points, from the target'area up to the physics installations, the bending magnet centres were marked out on the floor.

    Electronic and mechanical work The Group's Electronics and Mechanics Section actively participated in the installa­ tion measurements in the ring. For the final alignment of the quadrupolcs, a laser beam offset measurement device was developed to duplicate the present offset device, which employs a taut nylon wire as reference. Owing to the ventilation system adopted, a

    Fitjuff 3Ï - Auutmiilk' offsi't mcasw\'- im'tlt by /rt.scT ih'ritr in the SPS hthj. (CERN-305.2.76)

    190 systematic error might affect the nylon wire measurements, and this is why a sophisticat­ ed system has been developed using a laser beam as a reference. For the last three years, the invar wires used for distance measurements have been standardized with a laser interferometer, calibrated against a four-metre rule taken as the primary standard for all length measurements made at CERN. A new, simpler type of interferometer is being adapted so that the distances can be measured between the brackets and quadrupoles during final alignment work in the ring. Special hydrostatic levels are being developed so that small variations in altitude can be detected and transferred from points where direct measurements are impossible, for example inside the shielding of the beams in the experimental areas. The automatic clinometers used for measuring magnet tilts can now be operated by remote control. This is already being tried out in the PS, and results show the measurements to be reliable. All of this equipment is ready to be used for the fine-alignment measurements of the SPS quadrupolcs and the components in the transfer tunnels. It has been designed for subsequent use iu the experimental areas where remote-controlled measurements are being increasingly called for by the physicists. This equipment has been developed for connection to a computer in real time and can, if necessary, supply accurate geometric parameters whilst the physics experiments are in progress.

    Geology The geological reports for the shafts, main tunnel and transfer tunnels have now been completed and published. The drawing office has also supplied all the drawings required for the official documents between CERN and the host countries.

    During the year the first experiments to be carried out in the North Experimental Experimental Area received final approval, namely two experiments concerned with muon and three Areas Group with hadron physics. Consequently the total number of SPS experiments approved so far is 15, involving 14 independent counter set-ups. In addition, there are the two bubble chambers, BEBC and Gargamelle. the experimental programmes of which are under active review for neutrino and hadron physics. Obviously the process leading to the approval of such a vast complex of experiments has involved the Group in a number of studies, ranging from matching the beams to the particular requirements of experiments, to the design of hydiogen targets and various services. As reported elsewhere, the civil engineering work for the North Area has made good progress and the design of practically all halls and buildings has been finalized. The neutrino tunnel in the West Area having been completed, the shield, consisting of 425 large iron disks, was put in position and sealed by light concrete in order to prevent leaking particles from reaching the detectors. The decay tunnel, in which a vacuum of a few torr has to be realized, was completed by the two windows, one of which is made of titanium and vacuum tests started. The West Area was shut down for 25 GeV physics at (he beginning of July and its conversion to SPS physics began. After the removal of all existing beams and experimen­ tal equipment, the two major items, namely the joining of the transfer tunnel TT60 to the existing tunnel TT4 and the installation of beams, shielding and services for the SPS

    1< l-iijitrr 32 I "slim" iiiiiulntpttU'. otic ol tin1 2tl nnii\ In hi' «w'J in llw lir\i thin of sei miliars hi'(iin\. It /•. (/ tfiii/ilni/ioli1 of ivn cnmpihi i/t's/i/ii >32 i IM width for ti hair iliiniiclcr of III i in l nli'u li allow* lliv ilcrii ti~ nun of li\o lit ihrrr ln-itni\ Iftini i-tii h liirijrl ici:RX-24.i.:rt,i

    experiments, were tuck led vigorously. To date, the joining of the transfer tunnel is almost complete, while all the beams have been traced on the floor by (he surveyors and some sections of the shielding installed, together with auxiliary equipment and services. A number of magnets and quadrupoles. not necessary for the future programme, were recuperated from the transfer line between the PS and the West Hall, and reconditioned in view- of their re-utili/alion for the new secondary beams. Magnet supports are being installed in their final position. The bulk of the activity during this year was directed towards the complex new hardware to be acquired. In the field of magnets, the deliveries concerning three eon- tracts. 22 coils of 1000 A to equip MBB iron cores. 25 C-shaped magnets and 21 slim quadrupoles. were completed. For a fourth contract, concerned with 40 normal quadru- polcs. only about half of them were delivered owing to a slow rale of production in the firm, but this improved towards the end of the year. Work is in progress in the firms for other types of magnets, namely the MTN dipoles for target stations (the first magnet is being completed), the 80 M BN dipoles and the 120 QNL quadrupoles (for the North Area), and two types of correcting elements, dipoles and sextupoles. It is worth noting that the secondary beams for both experimental areas require a total of 600 magnetic elements. The power supplies and associated electronics for all these elements are also under construction in industry. The prototypes of the main units were successfully tested at CERN and agreement given for the serial production. The first differential Ccrenkov counter with chromatic correction (called CEDAR). which will be used for particle identification in all hadron beams, was successfully tested at the PS in July. The performance was found to be very close to computed values and all the various items, including computer control, worked very satisfactorily. The orders for the first six counters to be used in the West Area were placed and some elements received. For other monitors, such as filament beam scanners and multiwire proportional chambers to be used in beam spectrometers, production has started. A number of orders for the electronics of the monitors were also placed and some equipment received. Two contracts, for 40 normal and 20 double collimators, respectively, were placed on the basis of successful prototypes built at CERN. All these activities were paralleled by an equally intense effort on the software of the computerized control system. A number of orders for other components, such as vacuum chambers, "quick" electrical and water connections, and supports of various kinds were placed and delivery started.

    192

    f It n: 1 : 1 ' !" " ''—' . 1. .-;

    0 5 « 15 20 25 30

    f-i.i'inv 3.1 Phm ol the II <-\i Expertnu-niot Arat iSephtnher 1975). PHPSiiri^ I-innre J4 T/ii1 /irs; Clil)Alt coioncr which was icslctl in a heam Fiaure .1) • Fractional view of the diaphragm which can /arm at tin' I'S in Jnlw Some ni the eiahi phoioiniihipliers can he seen: annahm o) 2110 nan diameter, I). I mm »penhui with only ± (1.0 / ihci ICI cue i he liiihi rclleued hack ihrouah the annular diaphraitm de/iat'iitrc Iront ait ideal circle. s MV i'iaurc J* '

    A contract for the realization of two superconducting dipoles to be used in the North Area was placed with CEA-Saclay, as a result of the collaboration established with them. The manufacture of several components started at the end of the year. The Group is also involved in the design of some experimental equipment for the North Area. The design of a 400 ton assembly of magnetized iron, to be used as muon analyser in an experiment, has been completed and tenders sent out. Finally, the effort to extend and improve the computer programs used to predict the features of the secondary beams and the associated background in the experimental areas has been pursued. The most recent achievements concern the introduction of the produc­ tion of neutral particles and their derivatives (pand e) in the ray-tracing programme TURTLE and of polarization parameters in the muon programme HALO.

    The activities of the Service during the past year can be divided into two types; those Administration related to the installation of the Laboratory on its new site, and those related to the Service operation of the Laboratory. Included in the first type of activity was the completion of the road network on the French part of the site, which permitted the closure of the public road crossing the North Area, and considerably improved the access to the Laboratory II installations. Also, the- new hostel for people working for the Organization is now ready. Concerning the second type of activity, excellent relations with the local authorities were maintained and developed during the year. The management of those areas of the site which are to be left as farm land continued satisfactorily and the new areas, required for the development of the North Area, were made available. The activities in the customs and taxes service continued to expand. &mrM «fi »*RÄ* i m m s

    l-'hjiin' .M 77»' hosH'l m Si-Cn'ni^-Potalh. Cl'.li \-y\..i ~t)

    Preparatory measures have been taken to adapt the activities of the Service to the new structure of the Organization planned for 1976.

    Planning The main problem that had to be faced in the planning of the programme in 1975 was am' due to the discovery, early in the year, that the main magnet coils had deteriorated, BiukjCis owing to the use by one of the manufacturers of a cleaning fluid containing phosphoric Section acid, and had to be rebuilt. As a result, the order of the installation of components in the ring tunnel had to be completely rescheduled. The new schedule had to take into account not only the delivery rates of new magnets, but also the rebuilding of the faulty magnets. Also, it was essential to cause the minimum of interference with all the other activities, notably with all the work proceeding in the auxiliary buildings. The new schedule has now been sucessfully implemented and the complete magnet system was in place in the ring tunnel by the end of the year. The installation of tho equipment in the auxiliary buildings proceeded according to the planned schedule. All systems ^re now going through the testing and commissioning process, as described in detail in each Group's report. As previously mentioned, it is expected that a proton beam from the PS will be transferred to the SPS injection system in the first half of 1976 and that the accelerated proton beam will reach the West Experimental Area before the end of that year. Budget reviews were carried out at regular intervals. The accounts for the year 1974 were analysed and recalculated in terms of 1970 costs and fixed prices by introducing the real cost variation indices as published in the official national statistics. The results of these calculations were published in document CERN/FC/1825 and show that the purchasing power available to the Programme over the first four years was less than the agreed amount by 14.8 million Swiss francs (at 1970 costs). After the June session of the Council the required budgets for the years 1976-1979 were again carefully analysed. The result«- showed that it was possible to reprofile the annual budgets as proposed in document CERN/FC/1879/Rev. During 1975 several large contracts were placed for the construction of the buildings Contracts in the North Experimental Area and the supply of bending magnets for the secondary and beams. Purchasing Thirty-seven calls for tenders were sent out for contracts in excess of 200000 Swiss Section francs, and also 340 price inquiries relating lo orders worth more than 50000 Swiss francs. With regard to purchasing, progress with the construction of the SPS machine was reflected in a marked increase in low and medium-value orders. The total number of contracts and orders placed was 6900 (5400 in 1974) representing a total of 148 million Swiss francs (134 in 1974). The information relating to all contracts and orders in excess of 100000 Swiss francs was processed by computer, the results of which are used by the Planning and Budgets Section. This system makes it possible, in particular, to keep constant track of the breakdown of contracts among the Member States participating in the 300 GeV Pro­ gramme. The procedures used by Laboratory II for purchasing and contracts were improved and simplified. Implementation of these procedures, together with the use of magnetic data-storage -ystems, considerably reduced the time spent in drawing up administrative and commercial documents. In addition, a central card index system was installed to store information on all European firms which have participated or are likely to participate in the 300 GeV Programme. This index, which is processed by computer, should give a more systematic picture of the industrial potential in Europe which can be used for CERN contracts. Finally, the Section cooperated with the Services of Laboratory 1 in drawing up the new General Conditions of Contracts.

    During the year, as more and more of the SPS dipole and quadrupole magnets were Parameter assembled and measured by the Magnet Group, the Parameter Section was able lo form Section an almost complete picture of the small imperfections in field to be expected in the ring. This compares well with the design aims of the machine, and both linear and non-linear imperfections prove to be comfortably within the range which the harmonic correction magnets around the circumference are capable of compensating when peak performance is required. The Parameter Section, in partnership with the Magnet Group, has launched the production of these harmonic multipole magnet lenses, specified to cope with some of the effects which had proved troublesome at the Fermi Laboratory machine. Prototypes haw been received and tested and installation is planned to be complete before injection studies start next year. Each of the correcting magnets is lo be individually powered, via a digitally con­ trolled wave-form generator, to superimpose a changing azimuthal pattern of Fourier harmonics in the ring. Programming the control system to enable the operator to set up this pattern empirically has been a joint venture with members of the Controls Group. It has proved to be among the most ambitious uses of the computer system envisaged and members of the Section have been able to pass on to other Groups useful experience in integrating together hardware, di'ta modules, applications programs and the various TV screens, knobs and touch buttons which the operator will use. Among the software facilities which have been developed with the Controls Group is a tree structure which exploits the touch screens. This will allow swift access to the various manipulations the operator will have to perform. Another task was to write the software necessary to channel the many hundreds of analogue signals which measure the

    197 performance of the accelerator to oscilloscopes in the control room. The Section also developed a standard program for filing and recalling blocks of operational data or trial settings for different sets of hardware. Early in the yeur it became cl^ar that, of the alternative schemes for changing from the 9.5 MHz RF bunch slructun. of the PS to the 200 MHz structure matched to the SPS. the one which involved making the change in the PS proved difficult to implement at high intensity. An unexpected microwave instability appeared which blew up the beam beyond the acceptance of the SPS. This instability is only partly understood even now. To be sure that the alternative scheme of making the frequency change in the SPS would not be beset with similar difficulties, the Section and the Radio-Frequency Group mounted an experimental test at FNAL. Batavia and verified that the frequency change and subsequent RF capture would indeed be possible with parameters which closely simu­ lated SPS conditions. A beam of 8 x 10'2 protons was debunched. recaptured and accelerated to 400 GeV. Near the end of the year a Running-ln Committee (RIC) was set up to plan the machine experiments which will bring the SPS up to its design performance during the running-in phase, and provide the software necessary to perform these experiments. The Parameter Section has integrated its preparations for running-in within the framework of this now committee and intends to provide coordination and machine theory support for the various hardware teams which form the RIC.

    During the 1975 annual staff review, a complete survey was made of the technician category, the largest in Laboratory II. The work of interviewing almost all technicians as well as certain other staff presented a particularly heavy load during the first half of the year. and. in all. just over 44% of the personnel were seen. Since the beginning of 1975 the Personnel Section has controlled the numbers of temporary labour personnel working throughout the Laboratory and a specially devel­ oped program has enabled the Section to provide the Laboratory management with regular information and statistics on the use of temporary labour. The Section has co­ operated closely with the Temporary Labour Office, particularly concerning the changes resulting from the contract decisions taken by the Finance Committee in June 1975. Special efforts were made to reduce to a minimum the disruption to the work of the Laboratory caused by the need to replace many temporary labour personnel during a short period of time. A total of 718 personnel (staff, fellows, associates and temporary labour) were working directly for the 300 GeV Programme at the end of the year. APPENDIX A CERN PUBLICATIONS

    CERN REPORTS

    CERN 75-1 FRY. W.F., HAIDT. D. Calculation of the neutron-induced background in the Gar- gamelle neutral current search. CERN 75-2 AMAT1. D.. FUBINI. S. Power laws in particle physics. CERN 75-3 SCHÖNBACHER. H., VAN DE VOORDE, M.H. Radiation and rire resistance of cable-insulating materials used in accelerator engineering. CERN 75-4 LAMBERT. K.P.. SCHÖNBACHER. H., VAN DE VOORDE, M. A comparison of the radiation damage of electronic components irradiated in different radiation fields. CERN 75-5 SCHMIED. H. A study of economic utility resulting from CERN contracts. CERN 75-6 SCHMIED. H. Etude de Futilité économique des contrats du CERN. CERN 75-7 LOCK. W.O. A history of the collaboration between the European Organization for Nuclear Research (CERN) and the Joint Institute for Nuclear Research (JINR), and with Soviet research institutes in the USSR 1955-1970. CERN 75-8 THIRRING. W. Problems of classical dynamical systems. Lectures given in the Academic Training Programme of CERN 1974-1975. CERN 75-9 WILLIS. VVJ. A new collective-field acceleration mechanism using a powerful laser. CERN 75-10 BAILLON, P.. BRICMAN. C. PERRO-LUZZI, M., JENNI, P., PERREAU. J.M.. TRIPP. R.D.. YPSILANTIS, T., DECLAIS, Y.. SEGUINOT, J. Measurement of the real part of the forward scattering amplitude by means of the Coulomb- nuclear interference in n±p and K*p elastic scattering at incident momenta below 3GeVc. CERN 75-11 BELL. J.S. Polarized particles for accelerator physicists. CERN 75-12 BERSET. J.C.. DEI.AVALLADE, G.. LINDSAY, J. A 256-channe! puke-height analyser. CERN 75-13 KEIL. E.. MARTI. Y.. MONTAGUE, B.W., SUDB0. A., AGS - the ISR computer program for synchrotron design, orbit analysis and the insertion matching. CERN 75-14 VOGT. HG. Monte Carlo calculations of the neutron transmission through the access ways of the CERN Super Proton Synchrotron. CERN 75-15 VAN PRAAG. A. Terminals fov the interactive input and editing of bibliographic records on the PDP-11 computer in the CERN Library. CERN 75-16 McGRATH, B.. SCHÖNBACHFR, H., VAN DE VOORDE, M. Effects of nuclear radiation on th«; optical properties of cerium-doped glass. CERN 75-17 HOLMES A.J.T. Calculation and optimization of stra) fields of septum dipole magnets. CERN 75-18 BATTISTI. S, BOSSART, R., SCHÖNBACHER, H.. VAN DE VOORDE, M. Radiation damage to electronic components. CERN 75-19 LI PPS. H. Instruction timing for the CDC 7600 computer. CERN 75-20 CROWLEY-MILLING, M.C. The design of the control system for the SPS. PAPERS PUBLISHED IN SCIENTIFIC PERIODICALS, BOOKS AND CONFERENCE PROCEEDINGS

    CTS Staff. The CPS improvements. 1965-1973 - an assessment. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522. p. 524-528. ADAMS, J.B. Introduction. Journée d'étude sur la topométnc souterraine. CERN, Geneva. 5-6 March 1974. Proceedings, Lyon. Inst. Nat. Sei. Appl.. 1974. p. 1-4. ADAMS, J.B. What makes an engineer in Europe. Wiys. Bull.. 17-20. 1975. ADER, J.P. Backward meson-baryon scattering and geometrical properties of baryonic exchanges. Nucl. Phys. B9S. 154-172. 1975. ADER. J.P.. HUMBLE. S.. PESCHANSK1, R., LACAZE, R.. Impact parameter description of the charge exchange process n*p -» it^it^p). Phys. Lett. WB, 71-76. 1975. ADER. J.P., PESCHANSKI. R„ LACAZE. R.. COHEN-TANNOUDJ1. G.. GRAIN. C. Reggco- metry Nuovo Cim. 27. 385-411. 1975. ADERHOLZ, M.. LAZEYRAS, P.. LEHRAUS. !.. MATTHEWSON, R., TEJESSY. W. External particle identifier (EP1) for the Big European Bubble Chamber (BEBC). Nucl. lustrum. Meth. 123. 237-254. 1975. ADERHOLZ, M.. LEHRAUS, I.. MATTHEWSON. R. Reduction of the ionization loss distribu­ tion width of several simultaneous relut i vistic particles traversing a scintillation counter. Nucl. Instrum. Meth. 123. 45-50. 1975. AEBISCHER, D.. FAVIER, B.. GREENIAUS. G.. HESS. R., JUNOD, A., LECHANOINE, C, NIKLES. J.C., RAPIN. D. WERREN, D. Measurement of p-C analyzing power with a small angle scattering system. Nucl. Instrum. Meth. 124. 49-60. 1975. AHMED, M.A., ROSS, G.G. Deep inelastic photon-photon scattering in an asymptotically free gauge theory. Phys. Lett. 59B. 369-376. 1975. AHMED, M.A., ROSS, G.G. Radiative decays as a test for right-handed currents. Phys. Lett. MB. 293-298. 1975. AHMED. M.A., ROSS, G.G. Spin-dependent deep inelastic electron scattering in an asymptotically free gauge theory. Phys". Lett. 56B. 385-390. 1975. ALBRIGHT. C.H.. JARLSKOG. C. TJIA, M.O. Implications of gauge theories for heavy leptons. Nucl. Phys. B«6, 535-547. 1975. ALBRIGHT, C.H., .IARLSKOG, C. Neutrino production of MT and E* heavy leptons. I. Nucl. Phys. B84, 467-492. 1975. ALBRIGHT, C.H., JARLSKOG, C, WOLFENSTEIN. L. Neutrino production of M' and E4 heavy leptons, 2. Nucl. Phys. BS4. 493-502. 1975. ALBROW, M.G., BARBER, D.P.. BENZ. P., BOSNJAKOVIC, B„ BROOKS, j.R., CHANG, C.Y., CLEGG. A.B., ERNE, F.C.. KOOIJMAN, P., LOEBINGER. F.K., McCUBBIN, N.A., MURPHY, PC... RUDGE. A., SENS, J.C.. SESSOMS. A.L.. SINGH. J., TIMMER. J. (CHLM Collabora­ tion). Search for stable particles of charge s 1 and mass > deuteron mass. Nucl. Phys. B97.189-200, 1975. ALESSANDRINI. V., AMAT1. D.. LE BELLAC, M.. OLIVE, D. The operator approach to dual multiparticle theory. Dual theory, ed. by Jacob. M.. Physics Reports Reprint Series v.l. Amsterdam, North-Holland, 1974, p. 51-127. Also Publ. in Phys. Reports 6. 269-346, 1971.

    200 ALLARDYCE, B.W., GASE, K. Use of a secondary emission monitor in the extraction channel of the CERN synchro-cyclotron. Seventh international conference on cyclotrons and their applications, Zurich, 19-22 August 1975. Proceedings, ed. by Joho, W., Basel, Birkhäuser Verlag, 1975, p. 355-357. ALLARDYCE, B.W., GIANN1NI, R., HEDIN, B., LINDBÄCK, S., SUSINI, A., MANDRILLON, P., VOGT-NILSEN, N. The extraction system of the improved CERN synchro-cyclotron. Seventh international conference on cyclotrons and their applications, Zurich, 19-22 August 1975. Proceedings, ed. by Joho, W., Basel, Birkhäuser Verlag, 1975, p. 287-291. ALLES-BORELLI. V., BERNARDINI, M., BOLLINI, D., BRUNINI, P.L., FIORENT1NO, E., G1UST1, P., MASSAM, T., MONARI, L., PALMONARI, F., RIMONDI, F., VALENTINI, G., ZICH1CH1, A. A study of the possible existence of p'and p". Nuovo Cim. 30A. 136-143, 1975. ALLES-BORELLI, V., BERNARDINI, M., BOLLINI, D., GUISTI, P., MASSAM, T., MONARI, L., PALMONARI, F., VALENTI, G„ ZICHICHI, A. Measurements of afe+e"-^^) in the energy range 1.2-3.0 GeV. Phys. Lett. 59B, 201-204, 1975. ALPER, B„ B0GG1I.D, H„ BOOTH. P., BULOS, F., CARROLL, L.J., DAMGAARD, O. VON DARDEl, G„ DUFF, B., HANSEN, K.H., HEYMANN, F., JACKSON, J.N., JARLSKOG, G., JÖNSSON. L., KLOVNING, A., LEISTAM, L., LILl.ETHUN, E., LOHSE, E.. LYNCH, G.. MANNING, G., POTTER, K„ PRENTICE, M., SHARP, P., SHARROCK, S., ÖLGAARD-NIELSEN. S., QUARRIE, D„ WEISS, J.M. (British-Scandinavian Collaboration) Production spectra of it1, K*, p* at large angles in proton-proton collisions in the CERN Intersecting Storage Rings. Nucl. Phys. BIOO. 237-290, 1975. ALPER. B.. B0GGILD. H., BOOTH, P., CARROLL, L.J., VON DARDEL. G., DAM­ GAARD, G., DUFF, B.. JACKSON, J.N., JARLSKOG, G., JÖNSSON, L, KLOVNING, A.. LEISTAM. L.. L1LLETHUN, E., 0LGAARD-NIELSEN, S., PRENTICE, M., WEISS. J. (British-Scandinavian Collaboration). The production of charged particles with high transverse momentum in proton-proton collisions at the CERN ISR. Nucl. Phys. B87, 19-40. 1975. A LVAR EZ-ESTR A DA, R.F. Convergent perturbation expansions and analyticily properties in static field-theoretic models. Nuovo Cim. 27, 37-59, 1975. AMALD1. U.. BARTEL, W., COCCONI, G., DIDDENS, A.N., DIMCOVSKI, Z., DOBINSON, R.W., DUINKER, P., THORNDIKE. A.M., WETHERELL, A.M., BELLETTINI, G., BRACCINI, P.L.. CASTALD1, R.. DEL PRETE, T., LAURELLI, P., SANGUINETTI, G., VALDATA, M., BARONCELLI. A.. MATTHIAE, G., GRANN1S, P., JÖSTLEIN, H., KEPHART, R., LLOYD- OWEN, D., THUN, R. Correlations of secondaries in events with a forward negative hadron at the ISR. Phys. Lett. 58B. 206-212, 1975. AM ALDI. U., BARTEL, W.. COCCONI, G., DIDDENS, A.N., DIMCOVSKI, Z., DOBINSON, R.W.. DUINKER. P., THORNDIKE, A., WETHERELL, A.M., FLAUGER, W., MÖNNIG, F., BELLETTINI, G., BRACCINI, P.L., CASTALDI, R., CAVASINNI, V„ DEL PRETE, T., LAURELLI. P.. PATERNOSTER. G., ROMANO, M.. SANGUINETTI, G., VALDATA, M., BARONCLLLI, A., MATTHIAE, G.. GRANNIS, P., JÖSTLEIN, H., KEPHART, R., LLOYD- OWEN, D., THUN. R. Correlations of secondaries in events with a forward neutron at the ISR. Phys. Lett. SSB, 213-218, 1975. AMALDI. U.. B1ANCASTELLI, R., BOSIO, C, MATTHIAE, G., ALLABY, J.V., DIDDENS, A.N.. DOBINSON, R.W., KLOVNING. A., LITT, J., ROCHESTER. L.S., SCHLÜPMANN, K., WETHERELL, A.M. Momentum spectra of secondary particles produced in proton-proton colli­ sions at 14.2. 19.2 and 24.0 GeV/c. Nucl. Phys. B86. 403-440, 1975. AMATI. D„ ELLIS, S.D., WEIS, J.H. Electrcproduction and annihilation scaling laws in a dual model. Nucl. Phys. B84. 141-177, 1975. AMATI. D.. JENGO, R. The origin of a high-energy scale in the Pomeron calculus. Phys Lett. 56B. 465-469. 1975. ANDERSSON. B. Finite-energy corrections and multiplicity fluctuations according to the Gottfried model of hadron-nucleus interactions. Nucl. Phys. B95. 237-248,1975. ANTIPOV, Vu.M., ASCOLI. G., BUSNELLO, R., KIENZLE-FOCACCI, M.N., KIENZLE, W„ KLANNER, R., LANDSBERG, L.G., LEBEDEV, A.A., LECOMTE, P., MARTIN, M., ROIN1SHVILI, V.N., SARD, R.D., WEITSCH, A., YOTCH, F.A. (ŒRN-IHEP Boson Spectro­ meter). Analysis of the reaction K~p -» K~7r"rt+pat40GeV/c. Nucl. Phys. B86. 381-402, 1975. AMONIOU, N.G.. KOUR1S, C.B., PAPAIOANNOU, G.M. On the factorization of the Pome- ranchuk singularity in the Mueller-Regge diagrams. Phys. Lett. 52B, 207-209. 1974. ARTRU, X., YODH, G.B., MENNESS1ER, G. Practical theory of the multiiayered transition radiation detector. Phys. Rev. D12, 1289-1306. 1975. ASTBURY, P., GALL1VAN, J., JAFAR, J., LETHEREN, M., STEINER, V., WILSON, J.A., BEUSCH, W., BORGH1NI, M., WEßSDALE, D., FLURI, L., FREUDENREICH, K., GENTIT, F.X., WETZEL, W., LE DU, P., GUISAN, O. Measurement of the differential cross section and the spin-correlation parameters P, A and R in the backward peak of 7t"p-»K°A at 5 GeV/c. Nucl. Phvs. B99, 30-52, 1975. ATHERTON, H., BAR-NIR, I., FRENCH, B.R. Strange-particle production in pp collisions at 5.7 GeV/c. NuovoCim. 25/1, 1-15, 1975. AXELSSON, O. High-order methods for parabolic problems. J. Comput. Appl. Math. /, 5-16, 1975. AXELSSON, O. On the efficiency of a cla; if A-stable methods. BIT 14. 279-287, 1974. BAARLI. J., SULLIVAN. A.H. Dosimetry problems of negative ir-mesons. Radiology - thirteenth international congress of radiology, Madrid, 15-20 October 1973. Proceedings, Amsterdam, Excerpta Medica, 1974, v.2, p. 426-431. BACKENSTOSS, G. Particular properties of hadronic (exotic) atoms. Atomic physics 4, ed. by zu Putlitz. G., Weber, E.W. and Winnacker, A., New York, Plenum Publ. Corp., 1975, p. 163-190. BACKENSTOSS, G.. BUNACIU, T., EGGER, J., KOCH. H.. SCHWJTTER, A., TAUSCHER, L. Intensity measurements on I-hyperonic and kaonic atoms. Z. Phys. A273. 137-156. 1975. BAGL1N, C, BRIANDET, P.. FLEURY, P., DE ROSNY. G„ CARLSON, P.J., JOHANSSON, K.E.. D'ALMAGNE, B., LEHMANN, P., RICHARD. F„ TREILLE, D., EIDE, A., LUNDBY. A., NAVARRO-SAVOY, A., STAURSET, L, GRACCO, V. Elastic scattering of 10 GeV/c n+ and K + mesons and of 9 GeV/c protons on protons. Nucl. Phys. 89«, 365-400, 1975. BAILEY, J.. BORER, K.. COMBLEY. F.. DRUMM, R, ECK. C, FARLEY, F.J.M.. FIELD, J.H.. FLEGEL, W., HATTERSLEY. P.M., KR1ENEN. F.. LANGE. F.. PETRUCCI, G., PICASSO. E., PIZER. H.I.. RUNOLFSSON. O.. WILLIAMS. R.W., WOJC1CKI, S. (CERN Muon Storage Ring Collaboration) New measurement of (g - 2) of the muon. Phys. Lett. 55B. 420-424, 1975. BAILLON, P. DECLA1S, Y.. FERRO-LUZZ1, M., FRENCH, B., JENNI. P.. PERREAU, J.M., SEGUINOT, J., YPSILANT1S, T. Ultraviolet Cerenkov light detector. Nucl. Instrum. Meth. 126, 13-23, 1975. BAILLON, P., LITCHFIELD, P.J. Energy-independent partial-wave analysis of KN->Att between 1540 and 2150 MeV. Nucl. Phys. B94. 39-66, 1975. BAKER, P.A., BARNHAM, K.W.J., BUSCHBECK, B„ CARNEY, J.N., COLLEY, D.C., DUNWOOD1E, W., GENSCH, U„ GINESTET. J.. GOLDSCHMIDT-CLERMONT, Y., GRANT, A., GRARD, F.. HERQUET, P., HENRI, V., HONECKER, R., JAMES, M., JONES, G.T.. KARIMÄKI, V., KELLNER, G., KIRK, H., KLABUHN, J., KUHN, D., MARKYTAN, M„ MANESSE. D.. MORRISON, D.R.O.. ROWE, P., SAARIKKO, H., SCHMID, P., SEKERA, Z., SENE, M., SHERRATT, D„ STERGIOU, A., STROYNOWSKI, R., TUOMINIEMI, J., VERBEURE, F., VIGNAUD, D., WAHL. H., WINDMOLDERS, R. (Aachen-Berlin-CERN- London-Vienna Collaboration) (Birmingham-Brussels-CERN-Mons-Paris-Saclay Collaboration). Approach to scaling in proton fragmentation studied in the reactions K*p -» n±X and K~p -» ir±X. Nucl. Phys. B8V. 189-200, 1975.

    202 BAKSAY. L.. BÖHM, A.. FOETH, H., STAUDE, A., LOCKMAN, W„ MEDINN1S, M., "lEYER, T.. RANDER, J., SCHLEIN, P., TRIPPE, T., WEBB, R., ELLIS, R„ NAROSKA, B., STROL IN, P. Observation of diffraction excitation in pp — (pjr+jr") + X at the CERN-ISR and tests of limiting fragmentation. Phys. Lett. 53B, 484-488. 1975. BAKSAY, L.. BÖHM, A., FOETH, H., STAUDE, A., LOCKMAN, W., MF.DINNIS, M., MEYER. T., RENDER, J., SCHLEIN. P., WEBB, R„ ELLIS. R., NAROSKA. B., STROLIN, P. Evidence : r douole diffractive excitation in pp -> (pr:+Jt") + X at the CERN ISR and test of factorization. Phys. Lett. 55B, 491-494, 1975. BALUNI, V., BROADHURST, D.J. Scale dimension of chiral symmetry breaking and rigorous constraints on 1C& decay. Nucl. Phys. B84, 178-200. 1975. BARBIERI, R. Vacuum polarization phenomenology; the u tnesic atom x-ray discrepancy and the 2Pi,-2Si, separation in the (u^He)* system. Phys. Lett. 56B. 266-270, 1975. BARBIERI, R., ERICSON, T.E.O. Evidence against the existence of a low mass scalar boson from neutron-nucleus scattering. Phys. Lett. 57B, 270-272, 1975. BARBIERI, R.. REMIDDI. E. Effective coupling constant expansion of the muon anomalous magnetic moment. Phys. Lett. 57B, 27.1-276. 1975. BARBIERI. R., REMIDDI. E. Electron and muon '/i(g-2) from vacuum polarization insertions. Nucl. Phys. fly», 233-266. 1975. BARGMANN. H.W., MURATORI. G. Comments on 'Quartz-window design for gas-pressurized photomultiplier-tube installations'. Nucl. Instrum. Meth. 12V, 307-308, 1975. BAR1BAUD, G., BENINCASA, G., DANEELS. A.. HEYMANS. P.. METZGER, C, PEDERSEN. F., RABANY, M., SCHINDL, K., STARK, J. User's assessment of the computer controls system of the CERN PS Booster. Ninth international conference on high energy accelerators, Stanford. 2-7 May 1974. Proceedings. Springiicld. Nat. Tech. Inf. Serv., 1974, CONF 740522. p. 490-494. BAYARD. O.. FOX, J. Connexion de l'alimentation puisée de l'accélérateur de 400 GeV du CERN au réseau E.D.F., pt. 1 : caractéristiques de la charge puisée et du stabilisateur de tension. Rev. Gen. Elec. St, 160-164. 1975.

    BECK. F. The ope: ator interface of the 300-Ge V accelerator. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings, Springfield. Nat. Tech. Inf. Serv.. 1974, CONF 740522, p. 499-502. BEGER. H.. CUSACK. R.. FIEBIG, A„ SCHROOT. H. The data acquisition system (DAS) for the improved CERN SC. Seventh international conference on cyclotrons and their applications, Zurich, 19-22 August 1975. Proceedings, ed. by Joho. W.. Basel, Birkhäuser Verlag, 1975, p. 549-552. BEGER. H.. BLYTHF., F.. LE DALLIC. G„ LUSTIG, H., MICHAELIS, E.G.. VOGT-NILSEN, N. Report on the CERN SC improvement programme. Seventh international conference on cyclotrons and their applications, Zurich, 19-22 August 1975. Proceedings, cd. by Joho, W.. Basel, Birkhäuser Verlag. 1975, p. 49-55. BEGER. H., FIEBIG. A.. HILL. C.E.. HOHBACH, R., NITSCH. F.. TALAS. S. Design, cons­ truction and operation of the new CERN SC RF system. Seventh international conference on cyclotrons and their applications, Zurich. 19-22 August 1975. Proceedings, ed. by Joho. W.. Basel, Birkhäuser Verlag, 1975, p. 146-149. BEILL1ÈRE. P.. COCHET, C. DUMONT. J.J., MILLER, D.B., FACCINI, M.L., FENJUK, A.B., GENSCH. U., HENRI, V.P., JOHNSTAD, H., KAUFMANN. H.H., KOZLOVSKY, E.A., LAURENT. J.. MEYER. A., MOISEEV. A.M., MOSCA, L., NIKOLAENKO, V.l.. NOWAK, H., SMADJA. G.. TARASEVICH. S.V., TRIANTIS, F.A., WINDMOLDERS. K._ (France-Soviet Union Collaboration) (CERN-Soviet Union Collaboration). Neutral K, A and A production in K p and K *p interactions at 32 GeV/c. Nucl. Phys. BW, 20-34. 1975. BEILLIÈRE, P., COCHET, C, DUJARDIN, C, FACCINI. M., FENJUK, A.B., GYSEN, M., K1RK, H., KLUGOW, J., KOZLOVSKY, E.A., KUHN, D., MEYER, A., MOISEEV, A.M., MOSCA, L., N1KOLAENKO, V.l., NOWAK, H., PORTH, P., SCHLESINGER, J., SKURA, J., SMADJA, G., TRIANTIS, F.A.. VOGT, H. (France-Soviet Union Collaboration) (CERN-Soviet Union Collaboration). Production of y-rays in K "p and K +p interactions at 32 GeV/c. Nucl.Phys.B9/, 219-231, 1975. BELL. J.S. On wave packet reduction in the Coleman-Hepp model. Helv. Phys. Acta 48,93-98, 1975. BELL. J.S., RUEGG, H. Dirac equations with an exact higher symmetry. Nucl. Phys. B9S, 151-153, 1975. BELL, J.S.. RUEGG, H. Hydrogen atom on null-plane and Melosh transformation. Nucl. Phys. 69j. 12-22.1975. BELL. M.. KUB1SCHTA, W. Simulation of simultaneous beam sharing between internal targets and slow ejection at the CPS. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings. Springfield, Nat. Tech. Inf. Serv., 1974. CONF740S22, p. 467-470. BELL, VV, CHESI. E., COOPER, R.. FISCHER, H.G., FLÜGGE, G., FREHSE, H., GOTTFRIED. C, HECK. B., INNOCENT!, P.G., McLAREN, !.. MINTEN, A., SCIRE, M., WEGENER. D. Operation system for a 50000-wirc proportional chamber detector. Nucl. lustrum. Meth. 124, 437-444, 1975. BENAYOUN, M., CORNILLE. H. On the reconstruction of coupled two-body channel amplitudes. Nuovo Cim. iOA, 1-33, 1975. BENVENUTI, C, BLECHSCHMIDT, D. The optimization of a tubular condensation cryopump for pressures below 10 ~u torr. Sixth international vacuum congress, Kyoto, 25-29 March 1974. Proceedings, ed. by Kumagi, H. and Toya, T., J. Appl. Phys. suppl. 2, pt. 1, 77-80. 1974. BERGER. E.L. Rapidity correlations at fixed multiplicity in cluster emission models. Nucl. Phys. B85, 61-101, 1975. BERNABEU, J. Restrictions for asymmetry and polarizations of recoil in muon capture. Phys. Lett. S5B, 313-317, 1975. BERNABEU, J.. ERICSON, T.E.O., FERRO-FONTAN, C. Intrinsic magnetic polarizability con­ tribution to the susceptibility of dense neutron matter. Astrophys. Lett. 16, 57-59, 1975. BERNABEU, J., TARRACH, R. Some comments on the n + p-»D + 2y anomaly. Phys. Lett. 58B. 1-4, 1975. BERNABEU. J., TARRACH, R. Unsubtracted dispersion relation for the longitudinal Compton amplitude. Phys. Lett. 55B, 183-186, 1975. BERNARDINI, M., BOLLINI. D., BRUNINI, PL., FIORENTINO, E., MASSAM, T., MONARI, L.. PALMONARI, F., RIMONDI, F.. ZICHICHI. A. Cross-section measurements for the ex­ clusive reaction e+e" -> 4jt± in the energy range 1.2-3.0 GeV. Phys. Lett. 53B. 384-386, 1974. BERNARDINI. M., BOLLINI, D., BRUNINI. P.L., FIORENTINO, E., MASSAM, T., MONARI. L.. PALMONARI, F., RIMONDI. F., ZICHICHI, A. A study of the hadronic angular distribution in (eTe~) processes from 1.2 to 3.0 GeV. Nuovo Gm. 26A, 163-168, 1975. BERNSTEIN, J. Adler's theorem in finite massless QED and possible extensions to non-Abelian gauge theories. Nucl. Phys. 695,461-476, 1975. BERNSTEIN, J. Adler's theorem in finite massless QED and possible extensions to non-Abelian gauge theories, 2. Nucl. Phys. B99, 541-544, 1975. BERTIN, A., CARBONI, G., DUCLOS, J., GASTALDI. U., GORINI, G., NERI, G., PICARD, J, PITZURRA, O., PLACCI, A., POLACCO, E., TORELLI, G., VITALE, A., ZAVATTINI, E. 4 + Measurement of the 2P>,!-S.! energy difference in the (n" He) muonic ion by means of a tunable infrared dye-laser. Phys. Lett. 55B, 411-414, 1975. BERTIN. A.. CARBON!, G.. DUCLOS, J., GASTALDI, U., GORINI, G., NERI, G., PICARD, J., PITZURRA, O.. PLACCI, A., POLACCO, E., TORELLI, G., VITALE. A., ZAVATTINI, E.,

    ZIOCK, IC. Preliminary experimental results on the energy difference between the 2S./s and 2PJA levels of the of the (u4He) + system. Atomic physics 4, ed. by zu Putlitz, G., Weber, E.W. and Winnacker, A., New York, Plenum Publ. Corp.. 1975, p. 141-162. BERTIN, A.. CARBON1, G., PLACCI, A., ZAVATTINI, E., GASTALDI, U., GORINI, G., NERI, G.. PITZURRA, O., POLACCO, E„ TORELLI, G., VITALE, A., DUCLOS, J„ PICARD, J. 4 Experimental study on the (u, He)2*s metastable system in helium gas. Nuovo Cim. 260, 433-480, 1975. BEUSCH. W„ BIRMAN, A.. WEBSDALE, D., WETZEL. W. A new upper limit for the decay rate (f -» nn). Phys. Lett. 607?, 101-104, 1975. DEUSCH. W., BORGHINI, M., LAUPER, S., WEBSDALE, D„ FLURI, L„ GENTIT, F.X., ASTBURY. P., GALLIVAN, J., JAFAR, J.. LETHEREN, M„ STEINER, V., WILSON, J.A., LE DU, P.. GU1SAN, O. Measurement of the polarization in the forward peak of n~p -» K°A at 5 GcV/c. Nucl. Phys. B99, 53-60, 1975 BEUSCH, W., POLGÂR, E., WEBSDALE, D., FREUDENREICH, K„ GENTIT, F.X., MÜHLEMANN, P., PERNEGR, J., WETZEL, W., ASTBURY, P., LEE, J.G., LETHEREN, M., BELLINI. G., DI CORATO, M., PALOMBO, F., RANCOITA, P.G., VEGNI, G. Evidence that absorption in the 7t + 7t"7t" system in nuclear matter is stronger in the Jp=0* than in the Jp=r state. Phys. Lett. 55B. 97-100, 1975. BIALAS, A., BIALAS, E. Impact parameter analysis of multiplicity distribution in high energy pp collisions. Acta Phys. Polon. B5. 373-383, 1974. BIL LING E. R. Progress on the 300-GeV programme. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522, p. 19-22. BINON. F.. DUTEIL, P., GOUANÈRE, M.. HUGON, L., JANSEN, J., LAGNAUX, J.P., PALEVSKY, H., PEIGNEUX. J.P., SPIGHEL, M., STROOT, J.P. Pion-"He scattering around 3 3 the /2, /2 resonance. Phys. Rev. Lett. 35. 145-148, 1975. BLECHSCHMIDT. D. Low pressure limitation of the orbitron ionization gauge. Sixth international vacuum congress, Kyoto, 25-29 March 1974. Proceedings, ed. by Kumagi, H. and Toya, T.. J. Appl. Phys. suppl. 2, pt. 1, 105-108, 1974. BLECHSCHMIDT. D. A miniature extractor gauge for the UHV. J. Vac. Sei. Tech. //. 1160-1165, 1974. BLECHSCHMIDT. D. New deflected-beam gauge for pressures below 10_liTorr. J. Vac. Sei. Tech. 12, 1072-1078, 1975. BLOKZIJL, R., DE GROOT, A.J., JONGEJANS, B., KLUYVER, J.C., MASSARO, G.G.G., WOLTERS, CF., NILSSON, S.. BERGE, J.P., GAY, J.B., HEMINGWAY, R.J.. MARECHAL, B, HEINEN, P.M., KITTEL, W., METZGER, W.J., T1ECKE, H.G., TIMMERMANS, J.J.M., VAN DE WALLE, R.T. (Amslerdam-CERN-Nijmegen Collaboration). Lambda production in the fragmentation processes p ^* A and K " A A at 4.25 GeV/c. Nucl. Phys. B98, 401-417, 1975. BLOMQVIST, J.. ERICSON, T. An anomaly in the reaction n + p -» D + 2y. Phys. Lett. 57B, 117-122, 1975. BOCK, R.K. Program portability in high-energy physics. Computer Phys. Commun. 9, 221-229, 1975. BÖHM, M. Bcthe-Salpeter equation and current conservation. Nucl. Phys. B91.494-508. 1975. BÖHM. M„ JOOS, H.. KRAMMER. M. Electromagnetic properties of hadrons in a relativistic quark model. Ninth Rencontre de Moriond, Méribel-les-Allues, 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J.. Paris, CNRS. 1974. v.2. p. 221-230. BÖHMER, V., ENGLER, J., FLAUGER, W., KEIM, H., MÖNNIG, F., PACK, K., SCHOPPER, H„ BABAEV, A.. BRACHMANN, E., ELISEEV, G., ERMILOV. A.. GALAKTIONOV, Yu., GORODKOV, Yu., KAMISHKOV, Yu., LEIK1N, E„ LUB1MOV, V., SHEVCHENKO, V., ZELDOVICH, O. Neutron-proton elastic scattering from 10 to 70 GeV/c. Nucl. Phys. B9I, 266-278, 1975. BÖHMER, V., ENGLER. J.. FLAUGER, W., KEIM, H., MÖNNIG, F., PACK, K., SCHOPPER, H., BABAEV. A., BRACHMAN, E., ELISEEV, G., ERMILOV, A., GALAKTIONOV, Yu., GORODKOV, Yu., KAMISHKOV, Yu., LE1K1N, E., LUBIMOV, V., SHEVCHENKO, V., ZELDOVICH, O. The performance of a total absorption spectrometer up to energies of 60 GeV. Nucl. Instrum. Meth. 122, 313-318, 1974. BOIS, D., MENANT, E„ OLSFORS, J. Automation du gyroscope. Journée d'étude sur la topométrie souterraine. CERN, Geneva, 5-6 March 1974. Proceedings. Lyon, Inst. Nat. Sei. Appl.. 1974, p. 167-190. BOLL1NI, D., GIUSTI, P., MASSAM, T., MONARI, L., PALMONÂRI, F., VALENT], G., ZICHICHI, A. An experimental study of acoplanar(u±u':) pairs produced in (e+e") annihilation. Nuovo Cim. 13. 380-382, 1975. BONAZZOLA. G.C., BRESSAN1, T., CESTER, R.. CH1AVASSA. E., DELLACASA. G, FA1NBERG, A., GALLIO, M., M1RFAKHRA1, N„ MUSSO, A., R1NAUDO. G. A double magnetic spectrometer for the study of hypernuclei production bv K " in flight. Nucl. Instrum. Meth. 123, 269-284, 1975. BONNIER, B. Derivation and implications of rigorous absolute bounds for un partial waves up to 1 GeV. Nucl. Phys. B95, 98-108, 1975. BONNIER, B.. JOHANNESSON. N. Analysis of PCAC constraints in a dispersive approach to off-mass-shell nn scattering. Nuovo Cim. 29A, 565-577, 1975. BONNIER, B.. JOHANNESSON. N. Upper bound of 1 =0 exchange in KK scattering. Nucl. Phys. B101, 72-76, 1975. BONNIER. B., LOPEZ, C. MENNESS1ER, G. Improved absolute bounds on the n°n° amplitude. Phys. Lett. 6I)B. 63-66. 1975. BORER, J., BRAMHAM, P.. HEREWARD, HG., HÜBNER, K., SCHNELL, W., THORNDAHL, L. Non-destructive diagnostics of coasting beams with Schottky noise. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield. Nat. Tech. Inf. Serv., 1974, CONF740522, p. 53-56. BOSETTI, P., DEUTSCHMANN, M., GRÄSSLER, H., OTTER, G., SEYFERT, H.H., BÖCKMANN K., HOFMANN, J., LOWSKY, J., ZOBERN1G, G., COCCONI, V.T., COGHEN, T, KAR1MÄK1, V., KELLNER, G., MORRISON, D.R.O., ZAORSKA, J. (Aachen-Bonn-CERN- Cracow Collaboration). Inclusive strange particle production in 7t+p interactions at 16 GeV/c. Nucl. Phys. B94, 21-38, 1975. BOSETTI, P.. HONECKER, R., SIXEL, P., KALTWASSER, J., KOSTKA, P., COUNIHAN, M.J., KELLNER, G., KOCHER, D.J., MORRISON, D.R.O.. DZIUN1KOWSKA, K., HIROSE, T., LEITNER. E., BACON, T.C., BARNHAM, K.W.J., DORNAN, P.J., MAGON, V., WILLIAMS, P., DALLMANN. D.P., GIRTLER, P., SOSNOWSK1, R., ZIEMINSK1. A. (Aachen-Berlin-Bonn- CERN-Cracow-Heidelberg-London-Vienna-Warsaw Collaboration). An impact parameter analysis of multiparticle production in medium-energy meson-proton interactions. Nucl. Phys. B97, 29-35, 1975. BOUCLIER, R., BROWN, R.C.A., CHESI, E., DUMPS, L., FISCHER, H.G., INNOCENTI, P.G., MAURIN, G., MINTEN, A., NAUMANN, L., PIUZ. F.. ULLALAND, O. A vertex detector with multigap proportional chambers. Nucl. Instrum. Meth. 125, 19-24, 1975. BOURQUIN, M., GAILLARD, J.M. Vector meson and i|/ contributions to single lepton spectra. Phys. Lett. 59B, 191-196, 1975. BOURRELY, C, SOFFER, J., WRAY, D. A diffractive model including spin for pp elastic scattering at very high energy. Nucl. Phys. B91, 33-44, 1975. BOURRELY. C, SOFFER, J., WRAY, D. Spin effects in hadron scattering at very high energies. Nucl. Phys. B89, 32-44, 1975.

    206 BOUSSARD. D„ BOUTHEON, M.. CARPENTER. B., LEFEVRE, P.. POTIER, J.P. Injection und trapping of the beam at 800 MeV in the CPS. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv.. 1974, CONF 740522, p. 475-479. •JBAMHAM. P., CARRON. G., HEREWARD, H.G, HÜBNER, K., SCHNELL, W., 1'HORNDAHL. L. Stochastic cooling of a stored proton beam. Nucl. Instrum. Meth. 125. 201-202. 1975. BRAMHAM. P.. HANSEN. S.. HOFMANN, A.. HÜBNER, K.. PESCHARDT. E. Investigation :ii)d cures oflongitudinal instabilities of bunched beams in the ISR. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv.. 1974. CONF740522. p. 359-364. BRANDER. O. On the number of solutions to a crossing symmetric neutral ir-ir model. Comm. Math. Phys. 40. 97-124. 1975. BRAUN, H.. CORNELSSEN. M„ MARTYN. H.U.. ERRIQUEZ. O., NATAL1, S.. ROMANO, F.. BERTRAND. D.. CSEJTHEY-BARTH, M., LEMONNE. J., RENTON, P.. VILAIN, P., CUNDY. D.C.. PEDERSEN. T.I.. WALDREN. D. A study of the semi-leptonic decays of K1 mesons. Nucl. Phys. B.W. 210-252. 1975. BRAUNERSREUTHER, E.. HEDIN. B., LEHM. D.. SKAREK, P., VOGT-NILSEN, N. Measurement and shimming of the improved CERN synchro-cyclotron magnet. Seventh international conference on cyclotrons and their applications. Zurich, 19-22 August 1975. Proceedings, ed. by Joho. W.. Basel. Birkhäuser Verlag. 1975. p. 187-190.

    BREHIN. S.. DIAMANT BERGER, A.. MAREL. G.. TARTE, G., TURLAY, R., CHARPAK. G., SAU LI. F. Some observations concerning the construction of proportional chambers with thick sense wires. Nucl. Instrum. Moth. I2S, 225-229, 1975. BRESK1N, A.. CHARPAK, G.. SAULI, F., ATKINSON, M.. SCHULTZ, G. Recent observa­ tions and measurements with high-accuracy drift chambers. Nucl. Instrum. Meth. 124. 189-2"!4. 1975. BRESKIN. A.. CHARPAK. G.. SAUL1. F. High-accuracy bi-dimensional drift chambers. Nucl. Instrum. Meth. /25, 321-322, 1975. BROADHURST. D.J. A strong constraint on chiral symmetry breaking at short distances. Nucl. Phys. BS5. 189-207. 1975. BROWER, R.C.. ELLIS, J., SAVIT. R., ZAKRZEWSKI, W.J. Reggeon field theory on a lattice; a formulation. Nucl. Phys. B94. 460-476. 1975. BRUCE, D„ CORRIGAN. E., OLIVE. D. Group theoretical calculation of traces and determinants occurring in dual theories. Nucl. Phys. B95. 427-433. 1975. BRÜCKNER, W.. FAESSLER. M.A.. KILIAN, K.. LYNEN, U.. PIE1RZYK, B., POVH, B., RITTER, H.G.. SCHÜRLEIN. B„ SCHRÖDER. H.. WALENTA, A.H. Hypercharge exchange reactions on nuclei. Phys. Lett. 55 B, 107-110, 1975. BRUINS, T., OLOFSSON, K.S., PALANDRI, E.M., SLETTENHAAR, HJ.. STRACK­ ZIMMERMANN. H. SUPERMUX -a mulli-host data communication concentrator multiplexor. International meeting on mini-computers and data communication, Liège, 20-22 January 1975. Proceedings, Liège, Ass. des Ingénieurs sortis de l'Institut Electrotechnique Montefiore (A.I.M.). 1975. contribution no. 5, p. 1-12. Extract of CERN 74-19. BRUTON, P., DAV1ES, J., EKELÖF, T., FISHER, S.. FÄLDT, G., GRAFSTRÖM, P., HAGBERG, E., JOHANSSON, T., JONSSON. S., KULLANDER, S., NASSALSKI. J., READ, A.L. Incoherent production of p7t+tt" systems in proton-nucleus collisions at 18.6 GeV. Phys. Lett. 59B, 490-494. 1975. BRYANT. P.J. Dynamic compensation during stacking of the de-tuning caused by space charge effects. Ninth international conference on high energy acceltrators. Stanford, 2-7 May 1974. Proceedings. Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522. p. 80-82. BRYANT, P.J., COURBER, J.P. Experimental investigation of single-beam and beam-beam space charge effects. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF740522, p. 87-91. BRYANT, P.J., PERIN, R. Influence of the split field magnet spectrometer on the CERN Inter­ secting Storage Rings. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Scrv., 1974, CON F 740522, p. 75-79. BURAN, T., EIDE, A., HELGAKER, P., LEHMANN, P., LUNDBY, A., NAVARRO-SAVOY, A.. STAURSET, L., S0RUM, O., BAGLIN, C, BRIANDET, P., FLEURY, P., DE ROSNY, G., THENARD, J.M., CARLSON, P.J., JOHANSSON, K.E., D'ALMAGNE, B., RICHARD, F., TREILLE, D., GRACCO, V. Antiproton-proton elastic scattering at 6.2 GeV/c. Nucl.Phys.B97, 11-28,1975. BURKHARDT, H., MARTIN, A. Unique inelastic phase shifts from general structure in two variables. Nuovo Cim. 29A, 141-152, 1975. BÜSSER, KW., CAM1LLER1, L., DI LELLA, L., POPE, B.G., SMITH, A.M., BLUMENFELD, B.J., WHITE, S.N., ROTHENBERG. A.F.. SEGLER, S.L., TANNENBAUM, M.J., BANNER, M., CHEZE, J.B., HAMEL, J.L., KASHA, H., PANSART, J.P., SMADJA, G„ TEIGER, J., ZACCONE, H., ZYLBERSTEJN, A. Observation of high mass electron-positron pairs produced in proton-proton collisions at the CERN ISR. Phys. Lett. 56B, 482-486, 1975. BÜSSER, F.W., CAMILLER1, L., DI LELLA, L., POPE, B.G., SMITH, A.M., BLUMENFELD. B.J., WHITE, S.N., ROTHENBERG, A.F., SEGLER, S.L., TANNENBAUM, M.J., BANNER, M, CHEZE, J.B., HAMEL, J.L., KASHA, H„ PANSART, J.P., SMADJA, G., TEIGER, J., ZACCONE, H., ZYLBERSTEJN, A. A study of high transverse momentum r\ and jf mesons at the CERN 1SR. Phys. Lett. 55B, 232-236, 1975. BUÎ.SER, FW., CAMILLERI, L, DI LELLA, L., POPE, B.G., SMITH, A.M., BLUMENFELD, B.J., VHITE, S.N., ROTHENBERG, A.F., SEGLER, S.L., TANNENBAUM, M.J., BANNER, M., CHEZH, J.B., KASHA, H., PANSART, J.P., SMADJA, G., TEIGER, J., ZACCONE, H.. ZYLBEkSTEJN, A. Observation of high mass electron-positron pairs produced in proton-proton collisions at the CERN ISR. Colloque international sur la physique du neutrino à haute énergie, Paris, 18-20 March 1975. Proceedings, Paris, CNRS, 1975, p. 79-90.

    CAILLIAU, M., FOUCHER, R., HUSSON, J.P., LETESS1ER, J. (ISOLDE Collaboration). Etude de la désintégration ' 8*Au -> ' 8*Pt (T.^ = 53,0+1,4 s). J. Physique 35, A 69-482, 1974. CALDER, R., FISCHER, E., GRÖBNER, O., JONES, E. Vacuum conditions for proton storage rings. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522, p. 70-74.

    CALMET, J., DE RAFAEL, E. Eighth-order contribution to the Callan-Symanzik function in quantum electrodynamics from fourth-order vacuum polarization insertions. Phys. Lett. 56B, 181-184, 1975. CALMET, J., PETERMAN, A. Contribution to the muon anomaly from a set of eighth order diagrams. Phys. Lett. 56B, 383-384, 1975. CALMET, J., PETERMAN. A. On the contribution of quantum electrodynamics to the anomaly of the muon. Phys. Lett. 5SB, 449, 1975. CANESCH1, L., GRASSBERGER, P.. MIETTINEN, H.I., HENYEY, F. Unitarity bounds for in­ elastic diffraction. Phys. Lett. 56B, 359-363, 1975. CANESCH1, L., JENGO, R. Asymptotic behaviour of multiplicities in models with interacting Pomerons. Nucl. Phys. B89, 19-31, 1975. CARBONI, G., PITZURRA, O. Radiative collisional quenching of the mctastable muonic-helium ionuHe*(2S). Nuovo Cim. 25B, 367-389, 1975. CARLITZ, R., WEYERS, 1. Constituent quark analysis of hadronic transitions. Phys. Lett. 56B. 154-158. 1975. CARNEY, J.N., COLLEY. D.C., JAMES, M.F., JOBES, M., JONES, G.T., KINSON, J.B., STORR, K.M., WATK1NS, D.C., JOHNSON, D.D., PEETERS, P., VERBEURE, F., CIAPETT1, C, DUNWOODIE, W., GOLDSCHMIDT-CLERMONT, Y., GRANT, A., MULLER, F.. QUINQUARD, J., SEKERA, Z.. GRARD, F., HENRI, V.P., HERQUET, P., SKURA, J„ WINDMOLDERS, R.. MANESSE, D., VIGNAUD, D. A spin-parity analysis of the K+K+K~ system produced in the reaction K + p-»K+K+K"p. Phys. Lett. 55B. 117-120,1975. CHABAUD, V, KURODA, K. A time-dependent analysis of asymmetry measurements in polarized- target experiments. Nucl. Instrum. Meth. 125, 119-124. 1975. CHAICHIAN, M„ HAGEDORN, R., HAYASHI, M. Ideal relativistic quantum gas and invariant phase space. Nucl. Phys. B92. 445-468, 1975. CHALOUPKA, V., BR1CMAN, C, BARBARO-GALTIERI, A., CHEW, D.M., KELLY, R.L., LASINSKI, T.A.. RITTENBERG. A., ROSENFELD, A.H., TR1PPE, T.G., UCHIYAMA, F., BARASH-SCHMIDT, N„ SÖDING, P., ROOS, M. (Particle Data Group) Review of particle properties. Phys. Lett. 50B. no. 1, April 1974. CHALOUPKA, V.. BRICMAN, C, BARBARO-GALTIERI, A., CHEW. D.M., KELLY, R.L., LASINSKI. T.A., RITTENBERG, A., ROSENFELD, A.H., TRIPPE, T.G., UCHIYAMA, F., YOST, G.P., BARASH-SCHMIDT, N„ ROOS. M. (Particle Data Group) Review of particle properties - supplement to 1974 edition. Rev. Mod. Phys. 47, 535-541, 1975. CHAMAYOU, J.M.F., EL TOM, M.E.A. On the approximate solution or the delay integral equa­ tion of the statistical theory or radiation damage. Computer Phys. Commun. 9, 131-140, 1975. CHARPAK, G. Drift chambers. ESRO workshop on research goals for cosmic-ray astrophysics in the 1980's, Frascati, 24-25 October 1974. Proceedings. Paris. ESRO, 1975, ESRO SP 109, p. 109-130. CHARPAK, G., MAJEWSKI, S., SAULI, F. The scintillating drift chamber; a new tool for high- accuracy, very-high-rate particle localization. Nucl. Instrum. Meth. 126. 381-389, 1975. CHLIAPNIKOV, P.V., GERDYUKOV, L.N., GORBUNOV, P.A., UVAROV, U.A., GRARD, F., HENRI, V.P., HERQUET, P., WINDMOLDERS, R., VERBEURE, F., CIAPETTI, G.. DRIJARD, D, DUNWOODIE, W, GOLDSCHMIDT-CLERMONT, Y, GRANT, A.. NIELSEN, S.. PAPE, L., SEKERA. Z., TUOMINIEMI, J., YAMDAGNI, N., YARBA, V.A. Inclusive K°, K**(892) and it1 production in K+p interactions at 8.2 and 16 GeV/c and quark models in the central and fragmentation regions. Nucl. Phys. B88, 189-201, 1975. CHLIAPNIKOV. P.V, GERDYUKOV, L.N., LUGOVSKY, S.B., TCHIKILEV, O.G., UVAROV, V.A., VOROBJEV, A.P., CIAPETTI. G., DUNWOODIE, W., GOLDSCHMIDT-CLERMONT, Y., GRANT, A., YARBA, V., TUOMINIEMI, J., SEKERA, Z„ STERGIOU, A., KINSON, J.B., JOBES, M., STORR, K.M., WATKINS, D„ VERBEURE, F., GRARD, F., HENRI, V.P., HERQUET, P., WINDMOLDERS, R. Study of the inclusive reaction K+p-< K° +anything at 5, 8.2 and 16 GeV/c in the central region. Nucl. Phys. B97. 1-10, 1975. CHLIAPNIKOV, P.V., GERDYUKOV, L.N., TCHIKILEV, O.G., VOROBJEV, A.P., CIAPETTI, G., DUNWOODIE, W., GOLDSCHMIDT-CLERMONT, Y„ GRANT, A., SEKERA, Z., STERGtOU, A., TUOMINIEMI, J.. YAMDAGNI, N., CARNEY, J.N., COLLEY, D.C., JAMES, M., JONES. G.T., SHERRATT, D., GRARD, F.. HERQUET, P., HENRI, V., WINDMOLDERS, R., VERBEURE, F.. GtNESTET, J., MANESSE, D., VIGNAUD, D. (CERN-Birmingham-Brussels- Mons-Paris-Saclay-Serpukhov Collaboration). Study of the K + rc" total cross section Tor cm. energy up to 3.4 GeV. Phys. Lett. 55B, 237-240, 1975. CHLIAPN1KOV. P.V., GERDYUKOV. L.N., TCHIK1LEV, O.G., VOROBJEV, A.P., GRARD, F., HENRI. V.P., HERQUET, P., WINDMOLDERS, R„ VERBEURE, F., C1APETTI, G., DRIJARD, D.. DUNWOOD1E, W., GOLDSCHMIDT-CLERMONT, Y., GRANT, A., NIELSEN, S., PAPE. L., SEKERA, Z.. TUOM1NIEMI, J., YAMDAGNI, N. Determination of the K +n" total cross section for cm. energy up to 1.8 GeV. Nucl. Phys. BW. 413-424, 1975. CHRISTODOULOU. D. The principle. Nuovo Cim. 26B. 67-93. 1975. CIAFALONI, M.. MARCHES1N1, G. Approach to asymptopia from s-ehannel dynamics. Phys. Lett. 55B. 471-476, 1975. CIAFALONI. M., MARCHESINI. G. Final-state absorption in multiperipheral models. Nucl. Phys. BUS. 109-135. 1975. CIAFALONI. M.. MARCHESINI. G. Rcscattcring corrections and the Pomeron structure. Ninth Rencontre de Moriond, Méribel-les-Allues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van. J.. Paris. CNRS. 1974, i:l. p. 339-351. CIAFALONI. M.. MARCHESINI, G.. VENEZIANO. G. A topological expansion for high-energy hadronic collisions. 1 ; general properties and connection with the Reggeon calculus. Nucl. Phys. 89«. 472-492. 1975. CIAFALONI. M„ MARCHESINI. G.. VENEZIANO. G. A topological expansion for high-energy hadronic collisions. 2; s-channel discontinuities and multiparticle content. Nucl. Phys. B9H, 493-520. 1975. CIAPETT1. G.. DUNWOOD1E. W.. GOLDSCHMIDT-CLERMONT, Y., GRANT, A.. SEKERA. Z., STERGIOU. A.. TUOM1N1EMI, J.. YAMDAGNI. N„ CARNEY, J.N.. COLLEY, D.C., JAMES. M.J., JONES. G.T.. SHERRATT. D., GRARD, F., HERQUET, P., HENRI, V., WINDMOLDERS. R., VERBEURE, F., GINESTET, J., MANESSE, D., VIGNAUD, D., SENE, M. (CERN-Birmingharn-Brussels-Mons-Paris-Saelay-Collaboration). Study of the inclusive reaction K +p -» K° i anything at 5. S.2 and 16 GeV/c in the proton fragmentation region. Nucl. Phys. B89 365-382. 1975. CLEYMANS. J.. CLOSE. F.E. On the u> dependence of exclusive hadronic final states in lepton- hadron scattering. Nucl. Phys. «#5.429-441. 1975. CLOSE. F.E. Why polarized electroproduction is interesting. Ninth Rencontre de Moriond. Méribel-les-Allues, 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J„ Paris, CNRS. 1974, i:2. p. 285-300. CLOSE. F.E.. COTTINGHAM, W.N. The kinematic and symmetry structure of e+e~-> hadron pairs. Nucl. Phys. BW, 61-84, 1975. CLOSE. F.E.. RUBINSTEIN. H.R., FERRO-FONTAN. C. The dynamical origin or the right- signature fixed pole in Compton scattering? Nucl. Phys. BS5. 461-470, 1975. CORN1LLE, H., MARTIN. A. Asymptotic constraints on a^';"'. in asymptotically free theories. Nucl. Phys. B9i, 61-73. 1975. CORRIGAN, £., FA1RLIE. D B. OIT-shell states in dual resonance theory. Nucl. Phys. B91, 527-545. 1975. COTTRELL. R.. DELLA NEGRA, M., DRIJARD, D., FISCHER, H.G., FONTAINE, G.. FREHSE, H., GHESQUIÈRE. C. HANKE, P.. INNOCENTI, P.G., ISENBECK, W., KLUGE. E.E.. KORBEL, V.. KRZYWDZINSKI, S., MINTEN, A., PUTZER, A., SCHMIDT. K.H.. SCHNEIDER, H., SCHWILLE, W.J.. STROYNOWSKI, R., SZEPTYCKA, M., WAHL, H., WEGENER. D. Measurement of large transverse momentum positive particles produced at medium angles at v/s = 52.5 GeV. Phys. Lett. 5iB, 341-344. 1975. COUN1HAN, M.J. 'Principal axis' variables for the analysis of multiparticle production. Phys. Lett. 59B, 367-368. 1975. CRAIGIE. N.S., SCHIERHOLZ, G. On extracting the deep inelastic structure of Reggeons from high-energy muon-proton experiments. Nucl. Phys. B100. 125-156, 1975.

    210 CREWTHER. R.J.. NIELSEN. N.K. Short-distance analysis of the triangle anomaly in quantum electrodynamics. Nucl. Phys. BS7. 52-60. 1975.

    CROWLEY-MILLING, M.C. Computer control of accelerators. Ninth international conference on high energy accelerators. Stanford, 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv., 1974. CON F 740522, p. 485-489. discussion, p. 489.

    CROWLEY-MILLING. M.C. Selection case history - minicomputer network for control of a large nuclear particle accelerator. Minicomputer evaluation and selection. London. 4-6 June 1973. Proceedings, ed. by Cain. G.. Paker. Y.. and Morse, P.. London, Miniconsult. 1974. p. 109-135.

    DAUMEN. H.D.. KONETSCHNY. W„ STEINER. F. Analytic representation of the six-point function and inclusive processes. Nucl. Phys. Blifi. 104-124. 1975.

    DARRIULAT. P., GYGI. E.. HOLDER. M.. MeDONALD. K.T.. PUGH. H.G.. SCHNEIDER, F.. T1TTEL. K. Conversion efliciency of lead for 30-200 McV photons. Nuel. lustrum. Meth. I2

    DASS. G.V. Non-diagonal neutral currents and the scattering of neutrinos and untincutrinos by electrons. Nucl. Phys. BIOL 125-135. 1975.

    DAUM. C. KEATON. P.W. A null tochnique for calibrating polarisation \alues in /tp scattering. Nucl. lustrum. Melh. 129, 85-89. 1975.

    DE BOER. W. Dynamic orientation of a deuteron-spin system by rf irradiation of a polari?ed- proton-spin system. Phys. Rev. B12. 828-838. 1975.

    DEDEN. H.. HASERT. F.J.. KRENZ. W.. VON KROGH. J.. LANSKE. D.. MORFIN. J.. POHL. M.. SCHULTZE. K.. WEERTS. H.. BERTRAND-COREMANS. G.H.. GOOSSENS, M.. MULKENS. H.. SACTON. J.. VAN DONINCK. W.. VILAIN, P.. BURMEISTF.R. H.. CUNDY. D.C.. HAIDT. D.. LLORET. A., MUSSET. P.. PATTISON. J.B.M.. PERKINS. D.H.. ROMANO. F.. ROUSSET. A.. WACHSMUTH. II.. BEHR. L.. BRISSON. V.. COMTET. A., DEGRANGE. B.. HAGUENAUER. M.. KLUBERG. L.. NGUYEN-KHAC. U.. PÉTIAU, P.. BELLOTTI. E.. BONETTI. S.. CAVALLI. D.. FIORINI. E.. PULLIA. A.. ROLLIER. M.. AUBERT. B.. CHOUNET. L.M.. GANDSMAN. J.. HEIISSE. P.. JAFFRE. M.. JAUNEAU. L.. LONGUEMARE. C. LUTZ. A.M.. PASCAUD, C. VIALLE. J.P.. BULLOCK. F.W,. JONES. f.W.. MICHETTE. A.G.. MYATT. G.. PINFOLD. J. Strange particle production and charmed particle search in the Gargamelle neutrino experiment. Phys. Lett. 5XB. 361-366. 1975.

    DEDEN. H.. I1ASERT. I-.J.. KRENZ. W.. VON KROGH. J.. LANSKE. D.. MORFIN. J SCHULTZE. K.. WFERTS. H„ BERTRAND-COREMANS. G.H.. S'vCTON. J.. VAN DONINCK. W.. VILAIN. P.. CUNDY. B.C.. HAIDT. D.. JAFFRE. M.. NATALI. S.. PATTISON. J.B.M.. PERKINS. D.H.. ROUSSET.

    DEGRAND. T.A.. DETAR. CE. s-channel structure of the luo-Rcggeon cut. Nucl. Phys. BW. 189-202. 1975.

    DE GROOT. E.H. The multiplicity distributor in ;i unitary uncorrected cluster model. Phvs. Lett. 57/J. 159-160. 1975.

    DF GROOT. E.H.. RUI.IGROK. TAV. A unitary model for independent cluster production. Nucl. Phys. B/W.9S-III. 1975. HELLA NEGRA, M.. DRIJARD. D.. FISCHER. H.G.. FONTAINE. G., FREHSE. H.. FRENKIEL. P.. GHESQUIÈRE. C. GOKIELI, R„ HANKE. P., HOFMANN, W., INNOCENTI, P.C., ISENBECK. W.. KLUGE. E.E.. KORBEL, V.. KRZYWDZ1NSKI, S.. LINGLIN. D.. MiNTEN. A.. MORITZ. J.. MORRISON. D.R.O.. PUTZER A.. SCHNEIDER. H.. STROYNOWSKI, R.. STEIN. S.. SCHWILLE. W.J.. WEGENER, D. (CERN-Collège de Franrc-

    Heidelberg-Karlsruhe Collaboration). Composition of ^articles emitted at large pr and medium

    angles in pp collisions at v's = 52.5 GeV. Phys. Leu. 59B. 481-484. 1975. HELLA NEGRA. M., DRUARD, D.. FISCHER. H.G.. FONTAINE. G.. FREHSE. H.. FRENKIEL. P.. GHESQUIÈRE. G.. GOKIELI. R.. HANKE. P.. INNOCENTI. P.G.. ISENBECK. W.. KLUGE. E.E.. KORBEL. V.. KRZYWDZINSKI, S.. LINGLIN. D.. MINTEN. A.. MORRISON. D.R.O.. PUTZER. A.. SCHNEIDER. H.. STROYNOWSKI. R.. STEIN. S.. SCHWILLE. W.J.. WEGENER. D. Observation of leading particles in pp interactions with large transverse momentum secondaries at the CERN-ISR. Phys. Lett. .WB.4Ü 1-404. 1975. DE TAR. CE.. ELLIS. S.D.. LANDSHOFF. P.V. Final slate interactions in large transverse momentum lcpton and hadron production. Nucl. Phys. IW. 176-lhS. 1975.

    DEUTSCHMANN. M.. HONECKER. R.. RUMPF. K.. KUNDT. U.. WALTER, M.. 1DSCHOK. U.. HARTMANN. R.. COCCONI. V.T.. COGHEN. T.. HUMBLE. S.. KOTANSKI. A.. MOKR1SON. D.R.O.. F1G1EL. J.. GULA. A.. MALECK 1, P.. MURYN. B., SUSZYCKI, L., ZALEWSKA. A.. ZAORSKA, J.. KIROSE. T.. LEITNER. E. (Aachcn-Berlin-Bonn-CERN- Cracow-Meidelberg Collaboration). Differential cross sections for the charge exchange process jr'p-> rcVp)at 8. l6and23GeV/c. Nucl. Phys. BK5. 31-38. 1975. DEUTSCHMANN. M.. KIRK, H.. S1XEL. P.. BÖCKMANN. K.. HARTMANN, R.. PLOTHOW, H.. BÖTTCHER. H.. ROLOFF. H.. MORRISON. D.R.O.. K1SIELEWSKA. D., DC TH. W., HIROSE. T.. LEITNER. E.. STIEWE. J.. WOTSCHACK. J. (Aachen-Berlin-Bc ^ERN- Cracow-Heidclberg-Warsaw Collaboration). Prism plo: analysis of the reaction n*p -»pit'it n~ at 16GeV/c. Nucl. Phys. BW. 397-419. 1975.

    DEUTSCHMANN. M., SCHMITZ, P.. SCHULTE. R., KLEIN. M.. NAHNHAUER, R., BÖCKMANN. K.. PLOTHOW, H.. ZOBERNIG. G., COGHEN, T.. COUNIHAN, M.J.. HUMBLE. S„ KITTEL, W.. MORRISON. D.R.O.. RUDNICKA. H.. SUSZYCKI, L.. HIROSE. T., LEITNER. E.. STIEWE. J. (Aachen-Berlin-Bonn-CERN-Cra^ow-Heidelberg Collaboration). Prism plot analysis of the reaction ir'p -» pn*it" at 16 GeV/c. Nucl. Phys. BS6. 221-242. 1975. DIAMBRINI-PALAZZI. G. The high-energy inverse bremsstrahlung process and self-acceleration of high-density electron beams crossing a target. Phys! Lett. 576. 491-493. 1975.

    DICK. L.. GONIDEC. A.. GSPONER. A.. WERLEN. M.. CAVERZASIO. C, KURODA. K.. MICHALOWICZ. A.. POULET. M.. ASCHMAN. D.. GREEN. K.. PHIZACKLEA. P.. SALMON. G.L. Spin effects in the inclusive reactions n1 + p(f) -» it* + anything at 8 GeV/c. Phys. Lett. 5 70.93-96. 1975.

    DISS. J.P. Le bruit nuisance professionnelle. Ther. Umsch. 32. 157-160. 1975.

    DRUMMOND. IT. Dimensional regularization of massless theories in spherical space-time. Nucl. Phys. B94. 115-144. 1975.

    DUNWOODIE. W.. GRANT. A.. GOLDSCHMIDT-CLERMONT. Y., MULLER. F.. QUINQUARD. I. DE JONGH, G.. TAVERNIER. S.. CORNET. P., DUFOUR. P.. GRARD, F., HENRI. V.P.. SCHLESINGER. J., WINDMOLDERS. R.. DHEM, G.. GÖBEL. G.. WITTEK. W„ WOLF. G. The reaction K "d - K+ JT+ it d at 4.6 GeV/c. Nucl. Phys. B91. 189-218. 1975.

    DUTRANNOIS, J., BAARLI. J. Problèmes principaux de radioprotection autour des accélérateurs de haute énergie. J. Belge Radial. 57, 317-324. 1974. EGGERT. K.. '-'RENZEL. H.. G1BON1. K.L.. THOME, W.. BETEV. B.. DARRIULAT. P.. DI'lTMANN. P.. HOLDER. M.. McDONALD. K.T.. PUGH, H.G.. MODIS. T.. T1TTEL. K„ ECKARDT. V.. GEBAUER. HJ.. MEINKE. R.. SANDER. O.R.. SEYBOTH. P. A measurement of the proton-proton cross section at the ŒRN ISR. Nucl. Phvs. H'ÄS, 93-99. 1975. EGGERT. K.. FRENZEL. H., THOME. W.. BETEV, B.. DARRlULAT. P., DITTMANN, P.. IIOIDER. M.. MCDONALD, K.T.. MODIS. T„ PUGH. H.G.. TITTEL. K.. DERADO. I.. ECKARDT. V.. GEBAUER. HJ.. MEINKE. R.. SANDER. OR.. SEYBOTH. P. Angular correla­ tions between the charged particles produced in pp collisions al ISK energies. Nucl. Phvs. flNft. 201-215. 1975. EGGI'RT. K.. GIHONi. K.L.. THOME. \V„ BETEV. B.. ÜARRIULAT. P.. DITTMANN, P.. HOLDER. M.. McDONALD. K.T. PUGH. H.G.. VESZTERGOMBI. G.. MODIS. T.. ITi'TEL. K.. ECKARDT. V.. GEBAUER. HJ.. MEINKE. R.. SANDER. O.R.. SEYBOTH. P. A study of high transverse momentum n"S at ISR energies. Nucl. Plus. ihs. -19-72. 1975. EGGI RT. K.. THOME. W„ BI-TEV. B„ BÖHM. G.. DARRIULAT. P.. DITTMANN. P.. GYGI. I-.. HOLDER. M.. McDONALD. K.T.. PUGH. H.G.. SCHNEIDER. F.. ALBRCCHT, H.. MODES. T.. TITTEL. K.. DERADO. I.. ECKARDT. V., GEBAUER. HJ.. MEINKE. R.. SANDER. O.R.. .SEYBOTH. P. A streanier-chamher detector at the CERN Intersecting Storage Rings. Nucl. lustrum. Mclh. .'_V>. 477-491. 1975. EGGERT. K.. [HOME. W.. GIBONi. K.L.. BETEV. B.. DARRIULAT. P.. DITTMANN, P.. HOLDER. M.. KALTWASSER. ./.. McDONALD. K.T.. PUGH. H.G.. VESZTERGOMBI. G.. MODIS. !.. TITTEL. K.. ALLEN, P.. DERADO, I.. ECKARDT. V.. GEBAUER. HJ., MEINKE. R.. SANDER. O.R.. SEYBOTH. P., UHLIG. S. Angular coi.dations in proton-proton collisions producing a high Iransverse momentum ttp. Nucl. Phvs. BW. 7.3-92. 1975. EKSTROM. C. Nuclear deformation of futctium isotopes. International conference on nuclear structure and spectroscopy. Amsterdam. 9-13 Septcmher 1974. Proceedings, cd. hv Blok. H.P. and Dieperink. A.E.L.. Amsterdam, Scholar's Press, 1974. v.l. p. I OK. ELLIS. J.. GAILLARD. M.K.. NANOPOULOS. D.V. On the weak decays of high-mass hadron.s. Nucl. Phvs. BHW. 3I3-32S. 1975. ELLIS. J.. SAVIT. R. High-energy scattering and the nature of the hadronic phase transition. Nucl. Phys. ßW. 477-49X. 1975. ELLIS. J.. SAVIT. R. Phase transitions and the high temperature expansion for the Rcggeon calculus. Nucl. Phys. «94.477-500. 1975.

    ELLIS. S.. THUN. R. Large transverse momentum phenomena; an experimental and theoretical review. Ninth Rencontre de Moriond. Meribel-les-AUues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van. J.. Paris. CNRS. 1974. v.l. p. 37-74. EL TOM. M.E.A. Efficient algorithms for Volterra imegral equations of the second kind. Computing U. 153-166. 1975.

    ELVEKJAER. F. On the relation between inclusive and exclusive p± distributions. Nucl. Phys. B1IU. 112-124. 1975.

    EI.VEKJAER. F., PETERSEN. J.L. Geometrical description of binary reactions and large p± phenomena. Nucl. Phys. BW. I00-114. 1975. ENGFER. R.. SCIINEUWLY. H.. VUILLEUM1ER. J.L.. WALTER, U.K., ZEHNDER. A. Charge-distribution parameters, isotope shifts, isomer shifts, and magnetic hyperline constants from muonic atoms. At. Data Nucl. Data Tables 14. 509-597. 1974. ENGFER. R.. WALTER, H.K.. SCHNEUWLY. H. Study of nuclear properties with muonic atoms. (In Russian). Fiz. Elcm. Chas. Alomn. Yadra. 5. 382-418, 1974. KNCJLER. J.. FRIEND. B.. HOFMANN, W.. KEIM. H., NICKSON, R.. SCHMIDT- PARZhFALL. W.. SEGAR. A.. TYRRELL. M.. WEGENER. D., WILLARD. T.. WINTER. K. (CERN-Hambnrg-Karlsruhc-Oxford-Rutherford Laboratory-Westfield College Neutrino Collabora­ tion). A liquid-argon ionization calorimeter for detection of electromagnetic and hadronic showers. Nud. hvitrum. Meth. 120. 157-162. 1974. ENCiLER. J.. G1BBARD. B„ ISENBECK. W.. MÖNNJG. F.. MORITZ, J.. PACK. K.. SCHMIDT, K.H.. WEGENER. D.. BARTEL. W.. FLAUGER. W., SCHOPPER. H. Measure­ ment of inclusive neutron spectra at the ISR. Nucl. Phys. ßM. 70-82. 1975. ÏNGLERT. F.. FRÈRE. J.M.. NICOLETOPOULOS. P. Dynamical symmetry breakdown in pure Yang-Mills Held theory. Nud. Phys. B')5. 269-300. 1975. ERIC SON, T. Pion-nucleus interactions. International school of nuclear physics the investigation of nuclear structure by scattering processes at high energies. Erice. 22 September-1 October 1974. Proceedings, ed. by Schopper. H.. Amsterdam. North Holland. 1975. p. 165-203. F.RICSON. T.E.O. Dielectric constants and magnetic susceptibilities of nuclei and particles. International studies in nuclei, cd. by Jochim. H. and Ziegler, B.. Amsterdam. North Holland. 1975. p. 577-597; discussion, p. 598. ERICSON. T.E.O. Magnetic susceptibilities of nuclei and elementary particles. Ann. N.Y. Acad. Sei. .'.57. 56-71. 1975. ERICSON, T.E.O.. OSLAND. P. Polarization break-up of antideutcrons in the nuclear Coulomb field. Nucl. Phys. A24V. 445-456. 1975. ERK'SON. T.E.O.. WILKIN. C. Rare electromagnetic decays of pionic atoms. Phys. Lett. 57 B. 345-.U8. 1975.

    FABJA'N. C.W.. STRUCZiNSKI. W. Coherent emission of transition radiation in periodic radiators. Phys. Lett. 57'B 483-486. 1975. FAB.IAN. C.W.. STRUCZINSKI. W.. WILLIS. W.J.. KOURKOUMELIS. C. LANKFORD. A.J.. REHAK. P. Hadron cascades in iron and uranium. Phys. Lett. 60B. 105-108. 1975. FFRRANDO. A.. HOLMGREN S.O.. KORKEA-AHO. M.. MONTANET. L.. VAN HOVE, L. A method of multichannel analysis of hadron collisions exemplified on the reaction K +p -> K°K ' p at 5 GeV.'c. Nucl. Phys. B92. 61-77. 1975. FERRARA. S. Supersymmctric gauge theories in two dimensions. Nuovo Cim. Lett. 13. 629-635, 1975. FERRARA. S.. P1GUET, O. Perturbation theory and renormalbalion of supcrsymmetric Yang- Mills theories. Nucl. Phys. BV3. 261-302. 1975. FERRARA. S., REM1DD1. E. Absence of the anomalous magnetic moment in a supersymmelric Abdian gauge theory. Phys. Lett. 53 B. 347-350. 1974. [-HRRARA. S.. ZUMINO, B. Transformation properties of the supercurrent. Nucl. Phys. flcS'7. 207-220. 1975. FETT. E.. HAATUFT. A.. OLSEN, J.M.. HART. W.. KNIGHT. W.L.. MADROLLE. P.. WAL DR EN. D.. ALIBRAN, P.. DEGRANGE. B.. ARNOLD. R.. ENGEL. J.P., GUYONNET, J.L.. KURTZ. N.. DE UNAMUNO. S. An experimental study of the production of neutral pions in pp annihilations at 1.6 GeV c. Phys. Lett. 59 ft 182-186. 1975. FKTI. O.. GOLOVCHENKO. JA., NIELSEN. K.O.. UGGERHOJ. E. Channeling of 1.1 GeV/c protons and pions. Phys. Lett. .570. 90-92. 1975. FIDECARO. M. The SPS experimental program. Ninth Rencontre de Moriond. Méribel-les-Aliues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J.. Paris, CNRS, 1974. r. /. p. 191-218.

    214 FIEBIG. A.. HOHBACH. R. Principles and performance of the Cce beam stretching system at CERN SC2. Seventh international conference on cyclotrons and their applications, Zurich. 19-22 August 1975. Proceedings, ed. by Joho, W„ Basel, Birkhiiuser Verlag, 1975. p. 175-179. FINOCCHIARO. G.. GRANNIS. P.. GREEN, D., JÖSTLEIN, H., KEPHART, R.. THUN, R„ AMENDOLIA. S.R.. BELLETTIN1, G., BRACCINI. P.L.. BRADASCHIA. C, CASTALDI, R., CERR1, C. DEL PRETE. T.. FOÂ. L„ GIROMINI. P.. LAURELLI, P., MENZIONE, A., RISTORI, L.. SANGUINETTI. G.. VALDATA, M. Measurement of charged particle multiplicities associated with large transverse momentum photons in proton-proton collisions. Phys. Lett. 50B. 396-402. 1974. FISCHER. E. Vacuum and ultrahigh vacuum for particle accelerators and storage rings. Sixth international vacuum congress. Kyoto. 25-29 March 1974. Proceedings, ed. by Kumagi, H. and Toya. T.. J. Appl. Phys. suppl. -', pi. 1. 199-204. 1974. I-ORNBERG. B. On a Fouric method for the integration of hyperbolic equations. S1AM J. Num. Analysis / ?. 509-528. 1975. FORNBERG. B„ KÖLBIG. K.S, Complex zeros of the Jonquicrc or polylogarithm function. Math. Comput. 29. 582-599. 1975. I'RIDMAN. A. A/imuthal correlations in high-energy multipiirliclc production. Z. Phys. A274. 395-397. 1975. FUBINl. S. The de\elopment of dual theory: a general introduction. Dual theory, cd. by Jacob. M.. Physics Reports Reprint Series r. 1. Amsterdam, North-Holland, 1974. p. 1-6' FLiKUDA. R.. KYRIAKOPOULOS. E. Derivation of the effective potential. Nucl. Phys. B«5. 354-364. 1975. '"' LCHER. LP.. MUKHOPADHYAY. N.C. Electromagnetic corrections to the induced pseudo- scalar term in nuclear union capture. Nuovo Cim. 2.S.-1. 487-509. 1975. FURMAN. M.A.. KOMEN. G.J. Scaling behaviour of charged spin-one partons in a gauge model. Nucl. Phys. 1184. 323-332. 1975. GALIANA. R.. GIANNINI. R.. HEDIN. B.. VOGT-NILSEN. N.. BELL, R.A. Ion source and central region in (lie impro\cd CERN 600 MeV synchro-cyclotron. Seventh international conference on cyclotrons and their applications, Zurich. 19-22 August 1975. Proceedings, cd. b> Joho. W.. Basel. Birkhiiuser Verlag. 1975. p. 371-375. GAREYTE. J. Head-tail type instabilities in the CERN PS and Booster, pt. 1 : PS Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Scrv.. 1974. CONF 740522. p. 341-343. GAREYTE. J.. SACHERER. F. Head-tail type instabilities in the CERN PS and Booster, pt. 2: Boostci Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv.. 1974. COS F 740522. p. 344-346. GFRMOND. J.F.. WILKIN. C. Pion-carbon scattering in the 2-purticlc model. Nucl. Phys. ,1237.477-492. 1975. GERVAISE. J. La geodesic souterraine du synchrotron de 400 GcV (SPS). Géomètre H7.4. 14-28. 1974, GERVAISE. J. Geodesy and large particle accelerators. Europhys. news 5. 1-4. 1974. GERVAISE. J. Mesures géodésiques de haute precision appliquées à la construction des accéléra­ teurs de particules. Géomètre 117. 7. 14-30. 1974. GERVAISE. J. Présentation des journées. Journée d'étude sur la topométrie souterraine. CERN. Geneva. 5-6 March 1974. Proceedings, Lyon. Inst. Nat. Sei. Appl.. 1974. p. 5-12. GERVAISE. J. Résultats obtenus dans la géodésie souterraine du synchrotron de 400 GcV (SPS). Journée d'étude sur la topométrie souterraine. CERN. Geneva. 5-6 March 1974. Proceedings, Lyon. Inst. Nat. Sei. Appl.. 1974, p. 193-217. GHID1NI. B.. MÜLLER. K„ EADES. J.. FRENCH. 13.. VANDELLI. L, NAVACH. F.. PICCTARELLI, V.. UAiLEY. J.. EDWARDS. M.. SMITH. I.L.. EDWARDS. D.N.. FRY, J.. CAR. R.. D'ANGELO. P.. GRABAR. S.. M1NELLI. G. A long scintillation counter for precise measurement of time of night mid impact position. Nucl. lustrum. Melh. 125. 357-363. 1975.

    GIACOMELL1. G.. ROSSI, A.M.. VANNINI. G.. BUSSIÈRE. A.. BARONI. G.. Df LIBERTO. S.. PETRERA. S.. ROMANO. G. Search for magnetic monopoles at the CERN-ISR with plastic detectors. Nuo\oCim.:.S'.-l. 21-28. 1975.

    GIANNINI. R.. MANDRILLON. P. On the possibility of accelerating multiply changed ions in the CERN synchro-cyclotron. Scionlli international conference on cyclotrons and their applications. Zurich. 19-22 August 1975. Proceeding*, ed. h> .loho. W.. Basel. Birkhiin.ser Verlag. 1975. p. 609-6)3.

    (iOTTERIED. K. Space-time structure of hadronic collisions and nuclear multiple production. Phys. Re\. Lett. 32. 957-961. 1974.

    GOl'NARIS. G.J.. VERGANEl.AKIS. A. On dil'fracii\e photoproiluclion and eleclroproduction of the ill's. Nuo\oCim. /3. 241-246. 1975.

    GRANT. A. Estimation ol'missing energy in v interactions in hydrogen huhhle chambers. Nucl. Inslrum. Mclh. 127. 355-359. 1975.

    GRANT. A. A Monte Carlo calculation of high energy hadronic cascade in matter. Nucl. Instrum. Mein. IM. 167-172. 1975. GRASSBERGER. P.. MIETTINEN. H.I. On the charge structure ofhigh-eneigy multiple produc­ tion. Nucl. Phys. BS2. 26-44. 1974.

    GRASSBERGER. P.. MIETTINEN. H 1. Quanuim number transfer and overlap calculations. Nucl. Phys. Ö92. 309-326. 1975.

    GRASSBERGER. P.. MIETTINEN. H.I. Simple structure of charged neutral correlations. Nucl. Phys. BH9. 109-117. 1975.

    GRASSLER. H.. HONECKER. R.. KIRK. H.. BECKER. L.. KAUFMANN. H.H., LOHMANN. W.. MATTHAEUS. E., SCHREIBER. HJ.. WEIGT. G.. COUNIHAN. M.J.. MORRISON. D.R.O.. BARNH\M. K.W.J.. POLLOCK. B.. THORNTON. P.R.. DALLMAN. P.P.. PORTH. P. (Aachcn-Bcrlin-CERN-London-Vicnna Collaboration). K*(890) production in K"p-»NK3it final states at 10 GeV.e. Nucl. Phys. B97. 365-376. 1975.

    GRASSLER. H.. KIRK. H.. OTTER. G.. BÖTTCHER. H.. WALTER. M.. BÖCKMANN, K.. HARTMANN. R.. PI.OTHOW. H., ZOBERNIG, G.. COCCON1. V.T.. COUNIHAN. M.J.. HUMBLE, S.. MORRISON D.R.O.. H1ROSE. T.. LEITNER. E.. STIEWE. J. (Aachen-Berlin- Bonn-CERN-Heidclberg Collaboration). Study of s- and t-channel helicily conservation in the diffractive part of the reaction 7t*p -» 7t(Nn)at 16 GcV c. Nucl. Phys. B9.\ 1-11. 1975.

    GRASSLER. H.. KIRK. H.. RUMPF, K.. KLEIN, M.. NAHNHAUER. R., BÖCKMANN. K.. HARTMANN. R.. IDSCHOK, U„ BERGER. EX.. COGHEN. T.. COUNIHAN. M.J.. GENSCH. U.. KARIMÄKI. V., KUHN. D.. MORRISON. D.R.O.. SCHMID. P.. HIROSE, T.. LEITNER. E. (Aaehen-Berlin-Bonn-CERN-Hcidelberg Collaboration). Rapidity dispersion analysis of individual events in rc'p interactions al 8 to 23 GeV/c. Nucl. Phys. BUS. 1-13. 1975.

    GRASSLER. H.. KIRK. H.. SCHULTE. R.. GENSCH, U.. KLABUHN. J., HOFMANN. H.. LOWSKY. J., STÖCKER. B.. BERGER. E.L.. COUNIHAN. M.J.. HUMBLE. S., KELLNER, G, KARIMÄKI. V.. KUHN. D.. MORRISON. D.R.O.. SCHMID. P.. DZIUNIKOWSKA. K.. ZIELINSKI. W.. HIROSE, T.. STIEWE. J.. SZCZEKOWSKI. M. (Aachen-Berlin-Bonn-CERN- Cracow-Heidelberg-Warsaw Collaboration). Forward-backward multiplicities in n+p interactions between 8 and 23 GeV/c. Nucl. Phys. BW. 461-470. 1975. GRÀSSLER. H.. LAVEN. H.. SCHULTE, R.. BECKER. L.. KLABUHN. J.. LOHMANN. W.. MATTHAEUS. E.. SCHREIBER. HJ.. WEIGHT. G.. KUHN. D.. MORRISON. D.R.O.. SCHMID. P.. SOTIRIOU. IX DORNAN. P.. POLLOCK. B.. THORNTON. P.R.. BUSCHBECK. B.. STRAUSS. J.. WERNHARD. K.L. (Aachen-Berlin-CERN-London-Vienna Collaboration). K*(S90) production in NKTCTC final states at 10 GcV/c. Nucl. Ph) s. «M. 1-17. 1975.

    GRASSMANN. HC. JANKOVSKY. R.. PIRKL. W. Neues HF-System des 28-GeV-Protoncn- suichrotrons hei CERN. Siemens-Z.. 299-306. 1975. CiRI EN. M.B.. JACOB. M.. LANDSHOFF. P.V. Production or the new resonances in hadronic colhsions. NuouiCim. 2V.-1. 123-139. 1975. GRISEL1N. J.. GIVERNAUD. A.. BARLOUTAUD. R.. PREVOST. J.. GANDINI. F.. KIESLING. C. PLANE. D.E.. WITTEK. W.. BAILLON. P.. BR1CMAN, C. FERRO-LUZZI. M.. PETERSEN. J.O.. BURKHARDE E.. OBERLACK. H.. PUTZER. A.. SCHLEICH. H. K p cross sections between 1.1 and l.4GeVc. Nucl. I'bys. 1393. 189-216. 1975.

    GUEX. E.H.. JOSEPH. C. TRAN. M.T.. VAUCHER, B.. WINKELMANN. E.. BAYER. W.. HILSCHI R. H.. SCHMITT. H.. ZUPANCIC. C. TRUÖL. P. Differential cross-sections for f p — yn in the first resonance region. Pins. Lett. .v«. 101-106. 1975. GUMOWSK1. I. Stochastic elTccls in longitudinal phase space. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf Serv.. 1974". CONF 740522. p. 429-433.

    GUPTA. V.. KÖGERLER. R. The SU(3) properties of the photon and the new resonances. Pins. Lett. 5611. 473-476. 1975.

    HAGEBO. E.. LUND. T. Fission or lead induced by 600 MeV protons. J. lnorg. Nucl. Chem. 37. 1569-1582. 1975. HAGEDORN. R. Statistical thermodynamics of strong interactions. High energy astrophysics and its relation to elementary particle physics, ed. by Brecher. K. and Selli. G.. Cambridge. Mass.. MIT Press. 1974. p. 255-296.

    HAGCENAUER. M. (Aachen-Brussels-CERN-Ecofe Polytechnique. Paris-Orsay-Padua Garga- melle Neutrino-Propane Collaboration). Preliminary result on v-ncutron and v-proton charged current cross-sections ratio. Colloque international sur la physique du neutrino à haute énergie. Paris. 18-20 March 1975. Proceedings. Paris. CNRS. 1975, p. 327-330. HALLIDAY. I.G.. ORZALESI. CA.. NERI. F.. TAU. M. Multiple exchange and high-energy fixed-angle scattering. NiunoCim. Lett. 14. 280-282. 1975. HAMBRO. L. MUKHOPADHYAY. N.C. Effects of nonstalistical hyperfine populations in muon capture by pohtri/cd nuclei. NuouiCmi. Lett. 14. 53-59. 1975.

    HANSEN. .I.D.. JONES. G.T.. OTTER. G.. RUDOLPH. G. Formalism and assumptions involved in partial-wave analysis of threc-meson systems. Nucl. Phys. BUI. 403-430. 1974.

    HANSEN. P.C. Nuclei far from stability. International conference on nuclear structure and spectroscopy. Amsterdam. 9-13 September 1974. Proceedings, ed. by Blok. H.P. and Diepcrink. A.E.L.. Amsterdam. Scholar's Press. 1974. r. 2. p. 662-695. H.ARA. Y.. KURODA. T. Peripheral orbit model. 2: application to p + p -» K + K* reactions. Progr. Theor. Phys. 53. 1058-1071, 1975. HARDT. W. Gammii-transition-jump scheme ofthe CPS. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv.. 1974. CONF 740522. p. 434-438.

    HARIGEL. G. Die Grosse Europäische Blasenkammer im CERN. T. 1. Pins. Blatt. 31. 13-64. 1975. HARTMANN. R.. LEUTZ. H. A magnetized focusing iron shield against muons in high-energy neutrino beams. Nucl. lnstrum. Meth. 126. 165-174. 1975. HASERT, F.J. (Gargamelle Neutrino-Freon Collaboration) Further results on muon-antineutrino- clectron scattering. Colloque international sur la physique du neutrino à haute énergie. Paris. 18-20 March 1975. Proceedings. Paris. CNRS, 1975. p. 257-264. HEARD. K.S.. HE1NTZE. J.. HEINZELMANN. G.. IGO-KEMENES. P.. KALBRE1ER. W.. MITTAG. E.. RIESEBERG, H., SCHÜRLEIN. B.. S1EBERT, H.W.. SOERGEL. V.. STREIT, K.P.. WAGNER. A.. WALENTA, A.H. A measurement of K^ decay. Phys. Lett. 55 B. 324-326, 1975. HEARD. K.S.. HEINTZE. J.. HEINZELMANN. G.. IGO-KEMENES. P., KALBRE1ER. W.. MITTAG. E.. RIFSEBERG. H.. SCHÜRLEIN. B.. SiEBERT. H.W.. SOERGEL. V., STREIT. K.P.. WAGNER, A.. WALENTA. A.H. A measurement of the (K+ -> e" v)/(K* - |Tv) branching ratio. Phys. Lett. 55B. 327-330, 1975. HEMINGWAY. R.J.. EADES, J.. HARMSEN. D.M., PETERSEN, m. PUTZER. A.. KIESLING. C. PLANE. D.E.. W1TTEK. W. New data on K p -> K p and K°n and a partial-wave analysis between 1840 and 2234 MeV center of mass energy. Nucl. Phys. B91. 12-32. 1975. HENR1CHSEN. K.N., DE JONGE. M..I. Acceleration by phase displacement in the ISR. Ninth international conference or high energy accelerators. Stanford. 2-7 May 1974. Proceedings, Springfield. Nat. Tech. Inf. Serv.. 1974. COXF 740522. p. 390-393. HEUSCH. C.A. A remark on the baryon-antibaryon bound-state model of the new narrow resonances. Nuovo Cim. Lett. 12. 552-556. 1975. HEY. A.J.G. What do we learn from deep inelastic scattering with polarized targets'? Ninth Rencontre dc Moriond. Mcribcl-lcs-Allucs. 3-15 March 1974. Proceedings, ed. b> Tran Thanh Van. J.. Paris. CNRS. 1974. v. 2. p. 267-283. HORNSHOJ. P.. ERDAL. B.R.. HANSEN. P.G.. JONSON. B.. ALEKLETT. K.. NYMAN. G. Beta-strength functions of neutron-deficient isotopes in the xenon and mercury regions. Nucl. Phys. A239. 15-28. 1975. HORNSHOJ. P.. TIDEMAND-PETERSSON. P.. BETHOUX. R.. CARETTO. A.A.. CRÜTER. J.W.. HANSEN. P.G.. JONSON, B.. HAGBERG. E.. MATTSSON. S. Beta-delaved alpha-particle emission from "8- ,20Cs. Phys. Lett. 57B. 147-149. 1975. HORNSHOJ. P.. W1LSKY. K.. HANSEN. P.G.. JONSON. B. Beta-delayed alpha-particle emission in the decay of 3.6 s ""Hg. Phvs. Lett. 55B. 53-55. 1975. HÜBNLR. K. A search for a beam-beam effect in the ISR. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv.. 1974. COXF 740522. p. 63-65. HUMBLE. S. The peripheral impact parameter description of inelastic diffraction dissociation at very high energies. Nucl. Phys. ßW:. 2X5-295. 1975. HYAV1S. B.. JONES, C. WEILHAMMER. P., BLUM. W.. DIETL. H.. GRAYER. G.. KOCH. W.. LORENZ. F.. I.ÜTJENS. G.. MÄNNER. W.. MEISSBURGER. J.. OCHS. W.. ST1ERLIN. U. A study of the nn phase-shift solutions in the mass region 1.0 to 1.8 GeV from n"p -» it ~ n * n al P.2GcV. Nucl. Phys. BUM. 205-224. 1975. HYMAN. J.T. The computer control system for the SPS. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Teeh. Inf. Serv.. 1974. COXF 740522. p. 503-507. ILIOPOULOS. J.. 1TZYKSON. C, MARTIN. A. Functional methods and perturbation theory. Rev. Mod. Phys. 47. 165-192. 1975. IMMF.LE. J.D.. MUKHOPADHYAY. N.C. An open-shell finite Fermi systems approach to the structure of A = 12 nuclei. Phys. Lett. 56B. 13-16, 1975.

    218 IRVING, A.C. Comparison of exchange mechanisms in JIN -> pN and pion photo- and electro- production. Nucl. Phys. B86, 125-141, 1975. IRVING, A.C., CHALOUPKA, V. Axial vector meson production. Nucl. Phys. B89, 345-356, 1975. JACOB, M. The elusive asymptopia. Comments Nucl. Particle Phys. 6 (2), 31-40, 1974. JACOB, M. Multi-body phenomena in strong interactions. Particle interactions at very high energies, Louvain, 12-25 August 1973. Proceedings, NATO advanced study institutes ser B - Physics, v. 4, ed. by Speiser, D., Halzen, F. and Weyers, J., New York, Plenum Press, 1974, pt. A, p. 247-370. JACOB, M. Physics at the ISR - a review of recent results. Fields Quanta J, 345-411, 1974. JACOB, M. The proton structure and its hidden charm. Phys. Bull. 26, 175-181. 1975. JAKOB, H.P., KROLL, P. Constraints on the asymptotic behaviour of total cross sections. Nucl. Phys. B92, 171-188, 1975. JEAVONS. A.P., CHARPAK, G., STUBBS, R.J. The high-density multiwire drift chamber. Nucl. Instrum. Meth. 124, 491-503. 1975. JENNI, P., BAILLON, P., BRICMAN. C. FERRO-LUZZI, M., PERREAU, J.M., TRIPP, R.D., YPSILANT1S, T., DECLAIS, Y.. SEGUINOT, J. Measurement of the real part of the forward amplitude in pp elastic scattering. Nucl. Phys. B94, 1-20. 1975. JESSE, G. Analyse des gaz dans les métaux par thermo-extraction sous vide et Chromatographie en phase gazeuse. Spectra, no. 15, 19-26, 1975. JOHNSEN, K. Present status and future plans for the ISR. Ninth international conference on high energy accelerators. Stanford, 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv., 1974, CONF 740522, p. 32-36. JONSON, B. (ISOLDE Collaboration) Alpha branching ratios and s-wave decay widths for neutron- deficient lead isotopes. International conference on reactions between complex nuclei, Nashville, 10-14 June 1974. Proceedings, ed. by Robinson, R.L.. McGowan, F.K.. Ball, J.B. and Hamilton, J.H., Amsterdam, North Holland, 1974. p. 195. JOVANOVICH, J.V., MILLAR, T.W., O'CONNOR, P., BOZZO, M., BÖHM, A., FOETH. H., HANSROUL, M., MADERNI, G., RUBBIA. C, STAUDE, A., STROLIN, P. (Aachen-CERN- Genova-Harvard-Torino Collaboration). A search for slow massive particles with Z s 2 at the CERN Intersecting Storage Rings. Phys. Lett. 56B. 105-108, 1975.

    KEIL. E. Perspectives on colliding beams. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522, p. 660-670. KEIL, E., MESSERSCHMID, E. Study of non-linear effects of a resonant cavity on the longitudinal dynamics of a coasting particle beam. Nucl. Instrum. Meth. 128, 203-219, 1975. KONETSCHNY, W.. STEINER, F. Resonances, form factors und the hadron spectrum in inelastic electron-proton scattering. Nuovo Cim. Lett. 12,463-469, 1975. KRIENEN. F.. WALKER, E. A new total-absorption shower-cascade detector. Nucl. Instrum. Meth. 125. 349-352, 1975. KWAK, N„ LOHRMANN, E.. NAGY, E., REGLER. M., SCHMIDT-PARZEFALL, W., SCHUBERT, KR., WINTER. K.. BRANDT, A.. DIBON, H., FLÜGGE. G., NIEBERGALL, F., SCHUMACHER, P.E.. AUBERT, J.J., BROLL, C. COIGNET. G.. FA VIER, J.. MASSONNET, L., V1VARGENT, M., BARTL, W., EICHINGER. H.. GOTTFRIED. C. NEUHOFER, G. Experi­ mental results on large angle elastic pp scattering at the CERN ISR. Phys. Lett. 58B. 233-236, 1975. LAUSCHER, P., OTTER. G., WIECZOREK, H., MATTHAEUS, E., SCHREIBER, HJ., COCCON1, V.T., COUN1HAN, M.J., HANSEN, J.D., KELLNER, G., KOTANSKI, A., MORRISON, D.R.O.. SCHMID, P., SOTIRIOU, D., ALLEN, J.E., DORNAN, P.J., THORNTON, P.R., KOCHER, D.J., MARKYTAN, M., STRAUSS, J. (Aachen-Berlin-CERN-London-Vienna Collaboration). Spin-parity structure of the (Kit) system produced in the reaction K"p -> K~J[+)n. Nucl. Phys. B86, 189-200, 1975. LAZEYRAS, P., LEHRAUS, 1., MATTHEWSON, R., TEJESSY, W. Computer-aided control of separated bubble chamber beams. Nucl. Instrum. Meth. 123, 11-44, 1975. Also publ. as CERN 74-1. LENGELER, H. Particle separation for counter beams in the 100 GeV/c momentum range. Nucl. Instrum. Meth. 123, 301-325, 1975. LESQUOY, E., MÜLLER, A., TR1ANT1S, F.A., BERTHON, A., MONTANET, L., PAUL, E.. SAETRE, P. Partial waves in the K + p interaction between 1.2 and 1.7 GeV/c. Nucl. Phys. B99, 346-364, 1975. LEUTZ H. Track sensitive target construction and operating conditions. Argonne Nat. Lab., 1974, ANL HEP 7414, p. 25-66. LEWIS, C.W. Doppler measurements of recoil momenta from nuclear absorption at rest. Nucl. Instrum. Meth. 123, 289-294, 1975. LITCHFIELD, P.J., HEMINGWAY. R.J., BAILLON, P., ALBRECHT, H.. BURKHARDT, E. Partial-wave analysis of the reactions K"p -> A(18I5)it between threshold and 2170 MeV. Nucl. Phys. B74, 12-18, 1974. LLEWELLYN SMITH, C.H. Remarks on e+e' annihilation. Ninth Rencontre de Moriond, Méribel-les-Allues, 3-15 March 1974. Proceedings, ed. by Tran Thanh Van. J., Paris, CNRS, 1974, v. 2, p. 161-179. LLEWELLYN SMITH, C.H. Unified models of weak and electromagnetic interactions. International symposium on electron and photon interactions at high energies, Bonn, 27-31 August 1973. Proceedings, ed. by Rollnik, H. and Pfeil, W., Amsterdam, North-Holland, 1974, p. 449-465. LONDON, G.W., YU, Y.P., BOYD, D., BEGGS, T., CANDLIN, D.J., GOSHAW, AT., VENUS, W., KAHN, S., LOWYS, J.P., WUTHRICK, J.P., COLAS, J., FARWELL, C, FERRER, A., HOFMOKL, T., SIX. J., GAMBA, D., MARZARI, A., ROMERO, A. Study of the reactions K" p -» A0 + neutrals in the cm. energy range from 1580 to 1750 MeV. Nucl. Phys. BS5. 289-310, 1975. LOSTY, M.J., CHALOUPKA, V., MONTANET, L, PAUL, E., YAFFE, D., ZIEMINSKI, A., GANDOIS, B., ALITTL J., LOUIE, J. AJ production in TTp interactions at 3.9 GeV/c. Phys. Lett. 56B, 96-100, 1975.

    MARCHESINI, G., VENEZIANO, G. Non-vanishing of the bare triple-Pomeron coupling from s-channel unitarity. Phys. Lett. 56B, 271-274, 1975. MARTIN, A. Addendum to the paper 'Construction of the scattering amplitude to the differential cross-section'. NuovoCim. 26A, 94, 1975. MARTIN, A. Optimization of telescope images. J. Opt. Soc. Amer. 65, 858, 1975.

    MARTIN, A.D., MICHAEL, C. Amplitudes and exchange mechanisms for JtN -> f0N. Nucl. Phys. B84, 83-92, 1975. MENANT, E. Problèmes de topométrie souterraine au CERN. Journée d'étude sur la topométrie souterraine, CERN, Geneva, 5-6 March 1974. Proceedings, Lyon, Inst. Nat. Sei. Appl., 1974, p. 123-166. MICHAEL, C. Production mechanisms for high mass resonances. Ninth Rencontre de Moriond, Méribel-les-Allues, 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J., Paris, CNRS, 1974, v. 1, p. 147-152. MICHAEL, C. The production of Regge recurrences. Particle interactions at very high energies, Louvain, 12-25 August 1973. Proceedings, NATO advanced study institutes ser B - Physics, v. 4, ed. by Speiser, D., Halzen, F. and Weyers, J., New York, Plenum Press, 1974, pt. A, p. 385-395.

    220 MIETTINEN, H. Impact structure of diffraction scattering. Ninth Rencontre de Moriond, Méribel-les-Allues, 3-15 Marr!. 1974 Proceedings, ed. by Tran Thanh Van, J.. Paris, CNRS, 1974, v. 1, p. 363-402. MINKOWSKI, P. Quark triplets in self-interaction and tht 'ighl-cone structure of current com­ mutators. Nucl.Phys.B6S, 139-156, 1974. MÖHL, D., SCHÖNAUER, H. Landau damping by non-linear space-charge forces and oclupoles. Ninth international conference on high energy accelerators, Stanford, 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522, p. 380-384.

    MOREL, A., PETERSSON, B. Multiplicity distributions in a bootstrap model including multiply dirtractive events. Nucl. Phys. B91, 109-124, 1975.

    MORRISON, D. Comments on diffraction processes and total cross sections. Ninth Rencontre de Moriond, Méribeî-les-ADues, 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J., Paris, CNRS, 1974, v. 1, p. 275-297.

    MORRISON, D.R.O. Recent results from Serpukhov. Summer institute on particle physics, Stanford, 29 July-10 August 1974. Proceedings, ed. by Zipf, M.C., Stanford, SLAC, 1974, SLAC 179. v. 2, p. 205-221.

    MORRISON, D.R.O. Total inelastic cross sections for Jt*p, K±pand p*p interactions. Summer institute on particle physics, Stanford, 29 July-10 August 1974. Proceedings, ed. by Zipf, M.C., Stanford, SLAC, 1974, SLAC 179, v. 2, p. 223-235.

    MUSSET, P. Neutrino interactions at ANL, BNL and CERN. Ecole d'été de physique des particules, Gif-sur-Yvette, 9-21 September 1974. Proceedings, Orsay, Univ. Paris. Inst. Phys. Nucl., Part. Elément., 1974, v. 1, p. 325-373.

    NAGY, E., REGLER, M., SCHMIDT-PARZEFALL, W., SCHUBERT, K.R., WINTER, K., BRANDT, A., DIBON, H., FLÜGGE, G., NIEBERGALL, F., SCHUMACHER, P.E., BROLL. C, COIGNET, G., FAVIER, J., VIVARGENT, M., EICHINGER. H., GOTTFRIED, G, NEUHOFER, G. Observation of high mass u+u~ pairs at the ISR. Phys. Leu. 60 B, 96-100, 1975.

    NAHNHAUER, R. (Aachen-Berlin-Bonn-CERN-Cracow-Heidelberg-Warsaw Collaboration). A correlated jet model description of the reaction rc+p -+p3K+2n~ at 8 and 16GeV/c. Fourth international symposium on high energy and elementary particle physics, Varna, 22-27 September 1974. Proceedings, Dubna, 1974, D 8405, p. 155-160.

    NAKKASYAN, A. New data on K"p-> wA and a partial-wave analysis between the cm. energies 1915 and 2168 MeV. Nucl. Phys. B93, 85-108, 1975. NANOPOULOS. D.V., ROSS, G.G. Asymptotic freedom and the Callan-Cross relation. Phys. Lett. 58B, 105-110, 1975.

    NANOPOULOS, D.V., ROSS, G.G. Rare decay modes of the K mesons and KL-KS mass difference in an asymptotically free gauge theory. Phys. Lett. 56B, 279-285, 1975.

    NANOPOULOS, D.V., ROSS, G.G. SU(3) properties of the new particles - a problem for unified gauge theories. Phys. Lett. 59B, 475-476, 1975. NGUYCN-KHAC, U. (Aachen-Brussels-CERN-Ecole Polytechnique, Paris-Milan-Orsay-University College, London Collaboration). Strange particle production and charmed particle search in Gargamelle neutrino experiment. Colloque international sur la physique du neutrino à haute énergie, Paris. 18-20 March 1975. Proceedings, Paris, CNRS, 197.', p. 173-181.

    OLIVE, D. Further developments in the operator approach to dual theory. Dual theory, ed. by Jacob, M., Physics Reports Reprint Series v. 1, Amsterdam. North-Holland, 1974, p. 129-152. Suppl. to Phys. Reports 6, 269-346,1971. OTTER, G., RUDOLPH, G., RUMPF, K„ SEYFERT, H.H., SIXEL, P., WIECZOREK, H., BECKER, U KAUFMANN, H.H., HARTMANN, R., PLOTHOW, H., ZOBERNIG, G., HANSEN, J.D., JONES, G.T., KOTANSKI, A., MORRISON, D.R.O., SOT1RIOU, D„ LEITNER, E., STIEWE, J., DORNAN, P.J., THORNTON, P.R., KALMNGER, W., MARKYTAN, M., STRAUSS, J. (Aachen-Berlin-Bonn-CERN-Heidelberg-London-Vienna Collabo­ ration). A comparative investigation of low mass JI+M and K "w systems at various energies. Nucl. Phys. B87.189-206, 1975. OTTER, G., RUDOLPH, G., RUMPF, K., WIECZOREK, H., BÖTTCHER, H., NOWAK, W.D., COCCONI, V.T., COUNIHAN, M.J., HANSEN, J.D., JONES, G.T., KOTANSKI, A., MORRISON, D.R.O., SCHM1D, P., BARNHAM, K.W.J., DORNAN, P.J., THORNTON, P.R., BUSCHBECK, B., MARKYTAN, M., STRAUSS, J. (Aachen-Berlin-CERN-London-Vienna Col­ laboration). Evidence for different polarization properties of the pK and K*(890)rc states of the 1+ wave in the Q region. Nucl. Phys. B93, 365-386, 1975. OTTER, G., RUDOLPH, G., RUMPF, K., WIECZOREK, H., ROLOFF, H„ WALTER, M., COCCONI, V.T., HANSEN, J.D., HUMBLE, S., MORRISON, D.R.O., SCHMID, P., BARNHAM, K.W.J., DORNAN, P.J., POLLOCK, B., MACNAUGHTON, J.N., MARKYTAN, M., STRAUSS, J. (Aachen-Berlin-CERN-London-Vienna Collaboration). Partial-wave analysis of the (KKK) system in the reaction K~p -» K"K"K + p at 10 and 16GeV/c. Nucl. Phys. B89, 201-209, 1975. OTTER, G., RUDOLPH, G., SCHMITZ, P., WIECZOREK, H., LOHMANN, W., VOGT, H., BERGER, E.L., COCCONI, V.T., HANSEN, J.D., KOTANSKI, A., MORRISON, D.R.O., SCHMID, P., SOTIRIOU, D., STERGIOU, A., DORNAN, PJ., POLLOCK, B., THORNTON, P.R., KISIELEWSKA, D., MARKYTAN, M., STRAUSS, J., MICHAELIDIS, P., VASILIADIS, G.. FILIPPAS, T.A., GRAMMATIKAKIS, G.A., FRY, J.R., MUIRHEAD, H. (Aachen-Berlin- CERN-London-Vienna Collaboration) (Athens-Democritus-Liverpool-Vienna Collaboration). Evidence for unnatural spin-parity states of (KitTt)0 in the charge-exchange reaction K-p^(K°Jü+Tt-)n. Nucl. Phys. B84. 333-341, 1975. OTTER, G., RUDOLPH, G., SEYFERT, H.H., WIECZOREK, H., BECKER, L., LOH- MANN, W., BÖCKMANN, K., HARTMANN, R., LOWSKY, J., COCCONr, V.T., COGHEN, T., HANSEN, J.D., LJUNG, S.B., MORRISON, D.R.O., LEITNER, E., STIEWE, J. (Aachen- Berlin-Bonn-CERN-Heidelberg Collaboration). Investigation of the low-mass JIKK system in the reactions ju±p -» (it±K*K")p at 16 GeV/c. Nucl. Phys. B96, 365-378, 1975. OTTER, G., RUDOLPH, G., SEYFERT, H.H., WIECZOREK, H., KLUGOW. J., NOWAK, H., COCCONI, V.T., COUNIHAN, M.J., HANSEN, J.D., MORRISON, D.R.O., SCHMID, P., BARNHAM, K.W.J., POLLOCK, B., THORNTON, P.R., KALLINGER, W., MARKYTAN, M. (Aachen-Berlin-CERN-London-Vienna Collaboration). Partial-wave analysis of the (K°7t" it0) system produced in the Q-mass region in K"p -> (K°7t"7t°)p at 10 and 16 GeV/c. Nucl. Phys. B96, 29-44, 1975. PICCIOTTO, C. Ambiguities in hard-photon theorems for radiative nN scattering. Nucl. Phys. B89, 357-364, 1975. PALEV, T. Parastatistics and the Lie algebraical methods used there. Internat. J. Theor. Phys. 10. 229-237,1974. PICCIOTTO, C. Nucléon structure effects in pion-nucleon bremsstrahlung. Nuovo Cim. 29A, 41-48, 1975. PIGUET, O., SCHWEDA, M. A complete BPHZ version of the supersymmetry and broken chiral symmetry model. Nucl. Phys. B92, 334-364,1975. P1ZER, H.I. A fast multichannel time recorder. Nucl. Instrum. Meth. 123.461-464, 1975. POMENTALE, T. A boundary-value problem for the equation y = Xf(x, y) + h(x, y) - g(x, y)y. Z. Angew. Math. Phys. 54, 723-728, 1974. POMENTALE, T. Generalized Picard theorem for ordinary differential equations. Atti Accad. Naz. Lincei, Rend., Cl. Sci. Fis. Mat. Nat. 56,482-486, 1974. POTTER, K.. TURNER, S. High precision for ISR luminosity measurements. IEEE Trans. Nucl. Sei. 22, 1589-1592, 1975. PREPARATA, G. Massive quarks and large transverse momenta, 2; one-particle inclusive scattering. Nucl. Phys. B89,445-462, 1975. RANFT. G. Cluster model und structure in the two-particle rapidity plane in inclusive and semi- inclusive correlations. Ninth Rencontre de Moriond. Méribel-les-Allues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van. J.. Paris. CNRS. 1974. f. /. p. 445-450. RAVN. H. (ISOLDE Collaboration). Production and study of very neutron-deficient nuclei. International conference on reactions between complex nuclei, Nashville. 10-14 June 1974. Proceedings, ed. by Robinson. R.L.. McGowan. F.K.. Ball. J.B. and Hamilton. J.H.. Amsterdam. North-Holland. 1974. p. 194. RAVN. H.L.. SUNDELL. S.. WESTGAARD. L. (ISOLDE Collaboration). Target techniques for the ISOLDE on-line isotope separator. Nucl. lustrum. Meth. 123. 131-144. 1975. RAVN. H.L.. SUNDELL. S.. WESTGAARD. L.. ROECKL. E. Short-lived isotopes of alkali and alkaline-earth elements studied by on-line isotope separator techniques. J. Inorg. Nucl. Chem. 37. 383-393. 1975. REBBI. C. Dual models and relativistic quantum strings. Dual theory, ed. by Jacob. M.. Physics Reports Reprint Series r. /. Amsterdam. North-Holland. 1974. p. 221-293. Also Publ. in Phys. Reports /:. 1-73. 1974. REDEI. L.B. Incoherence and cluster emission. Nucl. Phys. B88. 136-144. 1975. REICH, K.H. Maximizing productivity and employee morale in an era of tight budgets. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv., 1974, CONF 740522. p. 326. REICH. K.H. (PSB Staff). The CERN PS Booster - design expectation confronted with reality, two years after start-up. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv.. 1974. CONF 740522. p. 480-484. RIZOV, V.A.. TODOROV. I.T.. ANEVA. B.L. Quasipotential approach to the Coulomb bound state problem for spin-0 and spin-'/: particles. Nucl. Phys. 398.447-471, 1975. ROI-CKL. E., LODE. D.. BACH MANN. K.. NEIDHART. B„ WOLF. G.K., LAUPPE. W„ KAFFRELL. N.. PATZELT. P. (ISOLDE Collaboration). Decay properties of neutron deficient Kr isotopes. Z. Phys. 266. 65-67. 1974. ROECKL. E.. LODE. D.. PESSARA. W. (ISOLDE Collaboration). The decay of 75Kr. Z. Phys. 266. 123-128. 1974. ROLLIER. M. (Gargamelle Neutrino Collaboration) (Aachen-Brussels-CERN-Ecole Polytechnique. Paris-Orsay-University College. London Collaboration). Elastic neutrino and antineutrino inter­ actions. Colloque international sur la physique du neutrino à haute énergie. Paris. 18-20 March 1975. Proceedings. Paris. CNRS. 1975, p. 349-355. RÖMER. H.. YANK.IELOWICZ. S., RUBINSTEIN. H.R. Zeros and infinities of the Callan- Symanzik function ß in a perturbative approach to the Dashen-Frishman model. Nucl. Phys. B79. 285-300, 1974. ROSSI. A.M.. VANNIN1. G.. BUSSIÊRE, A., ALBINI. E.. D'ALESSANDRO, D, GIACOMELLI. G. Experimental study of the energy dependence in proton-proton inclusive reactions. Nucl. Phys. BH4. 269-305. 1975. ROTHE. K.D. Exact and perturbative solutions for the vacuum polarization in a soluble model in scalar field theory. Nucl. Phys. B88, 501-524. 1975. ROUTTI. J.T., VAN DE VOORDE. M.H. Estimates of neutron leakage through penetrations of the CERN Intersecting Storage Rings by Monte Carlo albedo calculations. Nucl. Eng. Design 34. 293-305. 1975. RUBBIA. C. Les expériences neutrino au Fermi National Laboratory. Ecole d'été de physique des particules, Gif-sur-Yvette, 9-21 September 1974. Proceedings, Orsay, Univ. Paris, lnst. Phys. Nucl.. Part. Elément.. 1974, v. 1, p. 375-377.

    223 RUBINSTEIN. H.R. e+e - six or more pions in search of a theory. Ninlh Rencontre de Moriond. Méribel-les-Allues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J., Paris, CNRS, 1974. r. 2, p. 181-192. SACHERER, FJ. Transverse bunched beam instabilities - theory. Ninth international conference on high energy accelerators, Stanford. 2-7 May 1974. Proceedings, Springfield, Nat. Tech. Inf. Serv., 1974, CONF 740522, p. 347-351. SAMUEL, R.L., THIZV, F., NEIL, K.S. Materials and surface problems in ultra-high vacuum systems. Vuoto Sei. Technol. 7. 47-59, 1974. SARKAR, S., STRUBBE. H. Anomalous dimensions in background field gauges. Nucl.Phys.B90. 45-51. 1975. SAUDINOS, J.. CHARPAK, G., SAULI. F., TOWNSEND. D., VINCIARELLI. J. Nuclear scattering applied to radiography. Phys. Med. Biol. 20.890-905, 1975. SCHAAP. M.M.. VENEZIANO. G. Self-consistent p-P'trajectory from the planar dual bootstrap. Nuovo Cim. Lett. 12. 204-206. 1975. SCHILLER, H. (Aachen-Bonn-CERN-Cracow-Heidelberg-Warsaw Collaboration). A multi­ dimensional study of clustering in the reaction jt~p -» pnTitTjr~ at 16 GeV/c. Fourth international symposium on high energy and elementary particle physics. Varna, 22-27 September 1974. Proceedings. Dubna, 1974, D8405, p. 161-170. SCHÖNBACHER. H„ VAN DE VOORDE. M.. BURTSCHER. A., CASTA. J. Studium der Strahlenschäden an Hochenergiebeschleuniger-Bauteilen durch Bestrahlung in einem Kern­ reaktor Study on radiation damage to high energy accelerator components by irradiation in a nuclear reactor. Kerntechnik 6,268-280. 1975. SCHORR. B. Numerical inversion of a class of characteristic functions. BIT 15. 94-102, 1975. SCHREMPP. B„ SCHREMPP. F. Derivative relations for helicity amplitudes. Nucl. Phys. B96. 307-330. 1975. SCHREMPP. B„ SCHREMPP. F. Dual peripheral model. Ninth Rencontre de Moriond. Méribel-les-Allues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J.. Paris, CNRS, 1974, v. 1. p. 113-134. SCHREMPP, B., SCHREMPP, F. Is large angle exclusive scattering controlled by the hadronic radius? Phys. Lett. 55B. 303-306. 1975. SENS. J.C. Topics in particle physics with colliding proton beams. Particle interactions at very high energies. Louvain. 12-25 August 1973. Proceedings, NATO advanced study institutes ser. B - Physics, r. 4. ed. by Speiser, D„ Halzen, F. and Weyers, J„ New York. Plenum Press. 1974. pi. A. p. 61-182. SETTLES. R.. MANZ. A.. MARRAFF1NO. J.. HANSL, T., REUCROFT, S., PEYROU. C. A method for on-line optical tagging of bubble chamber tracks. München, Max-Plank Inst.. 1975. (MPI PAE Exp. El. 43). SEXL. R.U. Black-hole physics. Acta Phys. Austriaca 42. 303-347. 1975. SIMONS. L.M. Parity mixtures in muonic atoms. International studies in nuclei, ed. by Jochim H. and Ziegler, B., Amsterdam, North-Holland, 1975. p. 73-81 : discussion, p. 82. SOTIRIOU. D.S. (Aachen-Berlin-CERN-London-Vienna Collaboration) (Athens-Democritus-Liver- pool-Vienna Collaboration). The spin-parity structure of the (K~JI*) and (K07t'fre"") systems produced in charge exchange reactions. Ninth Rencontre de Moriond, Méribel-les-Allues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van. J.. Paris. CNRS. 1974. r. 1. p. 171-190. STROL1N. P.. ALBROW. M.G. The inclusive reaction pp = pX at theCERN ISR. Ninth Rencontre de Moriond, Méribel-les-Allues. 3-15 March 1974. Proceedings, ed. by Tran Thanh Van, J.. Paris. CNRS, 1974. v. 1. p. 237-248. TARRACH, R. Invariant amplitudes for virtual Compton scattering off polarized nucléons free from kinematical singularities, zeros and constraints. Nuovo Cim. 28A. 409-422. 1975. TAUSCHER. L.. BACKENSTOSS. G.. FRANSSON. K.. KOCH. H.. NILSSON. A.. DE RAEDT. J. Test of quantum electrodynamics by niuonic atoms; an experimental contribution. Phys. Rev. Lett. 35. 410-412. 1975. TAYLOR. B.G. Signal encoding for party-line digital data transmission. Electron. Lett. //. 454-456. 1975. T HOOFT. G., VELTMAN. M. Diagrammar. Particle interactions at very high energies. Louvain. 12-25 August 1973. Proceedings. NATO advanced study institutes ser B - Physics, i\ 4. ed. by Speiser. D.. Halzen. F. and Weyers, J.. New York. Plenum Press. 1974. pt. B. p. 177-322. Also publ. as CERN 73-9. T HOOFT. G.. VELTMAN, M. One-loop divergencies in the theory of gravitation. Ann. Inst. H. Poincaré .420. 69-94, 1974.

    TÖRNQVIST. N.A. The relative hadronic widths of the »{/-mesons and <{/ -> DD -> hadrons. Nuovo Cim. Lett. 13. 341-345. 1975. TREILLE. D. Status report on Omega apparatus and Omega experiments. Summer institute on particle physics. Stanford. 29 July-10 August 1974. Proceedings, ed. by Zipf. M.C.. Stanford. SLAC. I974.SDC / 79, r. 2. p. 139-157.

    VAN HOVE. L. High energy hadron collisions on complex nuclei and the propagation of hadionic systems through nuclear matter. Particle interactions at very high energies. Louvain. 12-25 August 1973. Proceedings. NATO advanced study institutes ser. B Physics, r. 4. ed. by Speiser. D.. Halzen. F. and Weyers. J.. New York. Plenum Press. 1974. pt. A. p. 371-383.

    VAN HOVE. L.. POKORSK1. S. High-energy hadron-hadron collisions and internal hadron structure. Nucl. Phys. BH6. 243-252. 1975.

    VENE:ZIANO. G. An introduction to dual models of strong interactions and their phj sical motiva­ tions. Dual theory, ed. by Jacob. M.. Physics Reports Reprint Series r. /. Amsterdam. North-Holland. 1974. p. 7-50. Also ptibl. in Phys. Reports 9. 199-242. 1974.

    VENEZ1ANO. G. Regge intercepts and unitarity in planar dual models. Nucl. Phys. 1374. 363"-377. 1974.

    VIALLE. J.P. (Aachen-Brussels-CERN-Ecole Polytechnique. Paris-Milan-Orsay-University College. London Collaboration). Neutral pion production b\ weak neutral currents in neutrino and anti- neutrino reaction. Colloque international sur la physique du neutrino à haute énergie. Paris. 18-20 March 1975. Proceedings. Paris. CNRS. 1975. p. 225-238. VINCIARELLI. P. Genesis of field theoretical bags and e'e annihilation. Phys. Lett. \1B. 457-461. 1975.

    VINCIARELLI. P. Sum over configurations (non-perlurbali\e quantum expansion for solitons and other stales in field theory). Phys. Lett. 5VÖ. 380-396. 1975.

    VINCIARELLI. P. Temporary quark confinement in field theoretical bags. Nucl. Phys. AW. 463-492. 1975. VINCIARELLI. P. Unified field theories of bags and strings. Nucl. Phys. BSV. 493-507. 1975.

    WEBB. R.. TRILLING. G.. TELEGDI. V.. STROLIN. P.. SHEN. U.. SCHLEIN. P.. RANDER. J.. NAROSKA. B.. MEYER. T.. MARSH. \V.. LOCKMAN. W.. LAYTI.R. J.. KERNAN. A.. HANSROUL. M.. FUNG. S.Y.. FOETH. H.. ELLIS. R.. DEREVSHIKOV. A.. BOZZO. M. BÖHM. A.. BAKSAY. L. Production of nucléon resonances by single diffraction dissociation at the CERN ISR. Phvs. Lett. 55ft 331-335. 1975. WEBB. R.. TRILLING, G.. TELEGDi. V., STROLIN. P.. STAUDE. A.. SHEN. B.. SCHLEIN, P.. RÄNDER. J.. NAROSKA. B.. MULLER. F., MEYER. T.. MARSH. W., LOCKMAN. W.. LAYTER. J.. KERNAN. A.. FOETH, H.. ELLIS. R.. BÖHM. A., BAKSAY. L. Double diffrac- lion dissociation and tesl of Pomer m factorization at the CERN ISR. Phys. Lett. 55B. 336-340. 1975. W'hYERS. J. Constituent quarks and current quarks. Particle interactions at very high energies. Louvain, 12-25 August 1973. Proceedings. NATO advanced study institutes ser. B Physics, r. 4. ed. by Speiser, D.. Halzen. F. and Weyers. J.. New York. Plenum Press. 1974. pi. B. p. 43-95. WINTER. K. A search for prompt production of electrons in proton-Pt collisions at 19 GeV'c. Phys. Lett. 5 7a. 479-482. 1975. WOLSTENHOLME. P. The impact of computer control on the performance of the CERN Inter­ secting Storage Rings. Ninth international conference on high energy accelerators. Stanford. 2-7 May 1974. Proceedings. Springfield. Nat. Tech. Inf. Serv.. 1974. CONF 740522. p. 508-510. WORDEN. R.P. New amplitudes for data analysis. Nucl. Phys. BV6. 509-514. 1975.

    ZEHNDER. A.. BÖHM. F. DEY. W.. ENGFER. P... WALTER. H.K.. VUILLEUMIER. J.L. Charge parameters, isotope shifts, quadrupole moments, and nuclear excitation in muonic 1-0-1-4. i7"Yr> Nucl. Phys. A254. 315-340. 1975. ZICHICHI. A. Why(e'e ) physics is fascinating. Nuovo Cim. Riv. 5. 339. 1975. Corrections to Nuovo Cim. Riv. 4. 498-532. 1974. ZIEMINSKI. A.. CHALOUPKA. V.. DOBRZYNSKI. L.. FERRANDO. A.. LOSTY. M.J.. MONTANET. L.. PAUL. E.. YAF'FE. D. A study of six-prong events produced in n" p interactions at 3.93 GeV c. Nucl. Phys. flftV. 502-530. 1974. ZOTTER. B. The Q-shift of off-center particle beams in elliptic vacuum chambers. Nucl. Instrum. Meth. 129. 377-395.1975. ZU MI NO. B. Application of gauge theories to weak and electromagnetic interactions. Rcnormali/ation and invariance in quantum Held theory, ed. by Caianiello, E.R.. New York, Plenum Publishing Corp.. 1974. p. 383-398. ZUM I NO. B. Supersymmctry and the vacuum. Nucl. Phys. BX9. 535-546. 1975. APPENDIX B * LECTURES AND SEMINARS

    PARTICLE PHYSICS SEMINARS AND COLLOQUIA

    FRAUENFELDER. H. (University of Illinois at Urbana-Champaign) (7.1): Search for parily violation in nuclear interactions. VANNUCCI. F. (Stanford University) (14.1): \|i production at SPEAR and their hadronic decays. KRISCH. A.D. (The University of Michigan. Ann Arbor) (21.1): Experiments with a polarized proton beam and a polari/ed target. RUFFINI. R. (The Institute for Advanced Study. Princeton) (23.1): From the binary pulsar to the y-rays bursts a new frontier for quantum and classical relalivistic field theories. WIIK. B. (DESY)(2S.l): Recent results on electron-positron collisions at DORIS. PACINI. F. (Laboratorio Astrofysica Spatiale. Frascati) (4.2) ; Physical processes in radio-galaxies. DYSON. F. (MPI Munich) (11.2) : Design of a telescope to see clearly through a turbulent atmosphere. SMITH. O.A. (Michigan State University) (18.2): n p and pp interactions at Fermilab energies: a) energy dependence of diflhictive excitation: b) two-particle correlations in the central region. OMNES. R. (Laboratoire de Physique Théorique et Hautes Energies. Orsay) (25.2): Antimatter in the universe. SEIDEN. A. (University of California. Santa Cruz CERN) (4.3): Hadron production in muon-nucleon collisions. LEPR1NCE-RINGUET. L. (College de France) ( 11.3) : Quelle éducation pour l'homme de demain? BARISH. B.C. (Caltech)( 13.3): Recent results on neutral currents and dimuons in the FNAL-Caltech neutrino experiment. LEE. W.Y. (Columbia University) (14.3): Production of v|i J by photons and neutrons at Fermilab. FIELD. .1. .(CERN)(18.3):Thenew muon (g-2) measurement al CERN. BREIDENBACH. M.(SLAC)(20.3): New results on the i|< particles from SPEAR. HUSON. I-.R. (FNAL Batavia) (25.3): Recent bubble chamber results at Fermilab and the future neutrino area program. LAPOSTOLLE. P. (Centre National d'Etudes des Telecommunications') (8.4): Transmission systems using light-optical fibers. PETIAU. P. (Ecole Polytechnique) ( 10.4): Review of the Paris Neutrino Conference. SC1AMA. D.W. (University of Oxford) ( 15.4): Particle ciealion by black holes. MUEHLEMANN. P. (University of Rochester) (22.4): Determination of the radiative decay width

    T(KB9O-* K"v) from coherent production on nuclei and consequences for SU3. DAMERELL. C. (Rutherford Laboratory) (29.4): A study of the line reversed hypercharge exchange reactions it ' p -» K ' I " and K p -» it I ' at 10 GeV c. D1MCOVSK1. Z. (Rockefeller University CERN) (6.5): Hadronic cluster production in the forward direction at the ISR. PACZYNSKI. B. (Institute of Astronomy. Warsaw) (13.5): Final stages of stellar evolution. TING. S.C.C. (MIT) (14.5): More on J particles. CHARPAK. G. (CERN) (15.5): New games with old detectors, old games with new detectors. SCHUBELIN. P.(BNL. Upton) (27.5): Final state characteristics of central pp collisions at 28.5 GeV c. OSBORNE. L. ( M IT) (29.5) : Charge symmetries in deep inelastic electron scattering. REGS. M. (University of Cambridge) (3.6): Galactic nuclei and cosmology. WEST. R.M. (ESO) ( 10.6): Astronomy now. TEMMER. G.M. (Rutgers and Aarhus) ( 12.6): Ultrashort lifetimes in nuclear and particle physics by the crystal blocking technique. NEZRICK. F.A. IFNAL. Batavia) ( 13.6): Neutrino interactions on protons at Fermilab energies. MOSSBAUER. R. (Laue-Langevin Institute. Grenoble) ( 17.6): Neutron beam research. LUTH. V. (SLAC) (3.7): Quantum numbers and decay modes of the i|< (3095) and I|I (3684) resonances \ •aimmarv of results from SPEAR.

    " Sol puhli,lied 227 GOTTFRIED. K. (Cornell University) (8.7): The space time structure of hadronic collision and nuclear multiple production. ZICHICHI. A. (CERN) (10.7): News in physics from Palermo. BRANDT. A. () (15.7): New measurements of large |t| elastic proton-proton scattering at the ISR. YAMAGUCHI, Y. (University of Tokyo) (22.7): High-energy physics in Japan - anecdotal accounts. JONES. R.V. (Aberdeen University) (29.7): Some experiments in optics involving the measurement of small displacements. WIIK. B.H. (DESY) (31.7) : Experimental results from DORISonthe.il GeV and 3.?GeV states and on the new intermediate state. DARRIULAT, P. (CERN) ('.8): Rapporteur talk at Palermo on collisions with large transverse momentum. SEXL. R. () (12.+ 14.8): Geometry and experience. Two lectures on the physics and epistomology of space and time. MUELLER, H. (Karlsruhe) (26.8): Evidence for the H-resonance and other results from the n p -» neutrals + neutron experiment at Serpukhov. SHIRK, E. (University of California) (28.8): Evidence for detection of a magnetic monopole. HARARE H. (Wcizmann Institute) (2.9): penology: Theory and phenomenology of the new particles. (Rapporteur talk on the new particles at the SLAC Conference). NARASIMHAM. V.S.(Tula Institute Bombay) (4.9): New particle observations in deep underground experiments. TREILLE. D. (CERN) (9.9): Report on the SLAC Conference. RICHTER. B. (SLAC) (ld.9): Recent results from SPEAR. SIEMENS. P.J. ( Institute) (23.9) : Shock waves in colliding nuclei. COCCONI, V.T. (CERN) (7.10): Determination of fireball dimensions from two-pion correlations observed in pion-proton interactions. GOLDIIABER. G. (Lawrence Berkeley Laboratory) (20.10): Further results on the \(/'s and related particles. STEFFEN. P. (DESY) (23.10): Radiative decays of the new particles. VAN GERVEN. L.(Universiteit Leuven) (28.10): Nuclear spin conversion. GOLDHABER. G.S. (Brook haven) (30.10): The variable moment of inertia (VMI) law. SCHATZMAN. E. (Observatoire de Paris) (4.11): On the formation of binary X-ray sources. GKEINER. W. (University of Frankfurt) (11.11): High-density shock waves in relativistic nucleus- nucleus collisions. LACH. .1. (ENAL) (13.11): Small-angle elastic scattering in the Coulomb region: preliminary results. WOLFENDAI E. A.W. (University of Durham) (18.11): Gamma-rays from the cosmos. CUNDY. D. (CERN) (19.11): Search for AS=-AQ and charm production by neutrinos in the 15 foot Fermilab hydrogen bubble chamber. HOFMANN. A.. WILLIS. W. (CERN) (20.II): Studies of a high-energy electron-proton colliding beam machine. HUBBARD. J. (CERN'Saclay) (25.11): Charm search at Omega. DENISOV. S.P.(IHEP.Scrpukho\)(26.ll):J.\li particle production by 70 GeV.c protons. GF1SS. J.(Unhersi(;il Bern) (27.11): Composition measurements in the solar wind with consequences in astrophysics and geophysics. REEVES. H. (CEN-Saclay) (2.12): Demographic inventory of our universe. .IENTSCHKE. W.. VAN'HOVE. L. CHARPAK. G. (CERN) (3.12): Visit to China. WOLTJER. L. (ESO) (9.12) : Quasars and red shifts. HORWITZ. G.(Racah Institute of Physics. Jerusalem) ( 11.12): Quasars, compact massive objects and gravitational red shifts. THIRRING. W. (Institut fiir Theoretische Physik. Vienna) (16.12): Stability of matter. MUSSET. P.(CERN) (18.12): Obser\ation ofu e* pairs associated with strange particles in neutrino interactions.

    NUCLEAR PHYSICS SEMINARS

    TAUSCH ER. L. (CERN Basel)) 17.1): QED and muonic Moms: A discussion of discrepancies betveen theory and experiment. PFDERSEN, J. (Niels Bohr Institute. Copenhagen) (31.1): Recent studies of shape isomers. SIMONS. L (CERN) (7.2) : Parity violation in muonic atoms. CARBONE G. (CERN) (14.2): The 2s-2p energy difference in light muonic atoms. BUGG. D. V. (University of London) ( 14.3) : Collision broadening. WYCECH. J. (CERN) (21.3): Strong interaction effects in hadronic atoms. GUSAKOW. M. ( Lyon CERN) (7.4) : y-spectroscopy of light hypernuclei. DONNELLY, T.W. (CERN/Stanford) (14.4): Electron scattering and neutrino reactions in nuclei. BERTIN, A. (Bologna/CERN) (21.4): Muon capture in hydrogen and deuterium: status of experiments. GRENACS, L. (Louvain)(28.4): Recoil nuclear polarizations in u." + '-C—vu + 12B(0f— 1") reaction. WESTGAARD, L. (CERN) (5.5): ISOLDE-2 - early results. P1LKUHN, H. (Karlsruhe) (12.5): The absorption in flight of negative hadrons. HUBER. G. (Orsay) (20.5): High-resolution laser spectroscopy on short-lived isotopes of sodium. HUFNER, J. (Heidelberg) (26.5): Three theses in pion absorption. LEWIS, C.W. (Karlsruhe/CERN) (2.6): Pion absorption, gamma-rays and momentum distributions. DEUTSCH, J. (Louvain) (7.7) : Threshold pion photoproduction from nuclei. ERICSON, T.E.O. (CERN) (21.7) : News from the Santa Fé Conference on High-End gy Physics and Nuclear Structure. LEON, M. (Rutherford Laboratory) ( 1.9) : Nuclear resonance effects in hadronic atoms. ALBER1, G. (CERN and Trieste University) (29.9): High-momentum components of spectator distributions. MYHRER, F.(CERN)(6.10): Pion-deuteron scattering in llieA resonance region. ENGFER, R. (Zurich University) (13.10): High spin states in it" absorption in heavy nuclei. THOMAS. A.W. (CERN) (27.10): Some results in low energy pion-dcuteron scattering. MUKHOPADHYAY, N. (SIN) (10.11): Manifestations of the muon-nuclear hyperfinc interactions. DAI.KAROV, O.D., KERB1KOV, B.O. (ITEP, Moscow) (28.11): Narrow NN resonances near threshold. ERICSON, M. (University of Lyon) (8.12): Weak interactions in nuclei. KOCH, H. (CERN) ( 15,12): Kaonic and antiprotonic atoms.

    SYNCHRO-CYCLOTRON COMMITTEE SEMINAR

    MICHAELIS. E.G. (CERN) (1.12) .Report on visits to laboratories in the USSR.

    APPLIED PHYSICS SEMINARS

    BARNERT. H. (Kernforschungsanlagc Jülich) (5.2): Nuclear energy and new energy supply concepts. VON STURM. F. (Siemens. Erlangen) (5.3): Electrical energy generation and storage by electro­ chemical methods. WIENECKE. R. (Max-Planck Inslitut für Plasmaphysik, München) (15.4): The fusion reactor - a chance for solving thr energy problem? ASHBY. D.E.T.F.(AERE Harwell) (28.5): Laser fusion. KETTA^JI. M.A. (College of Petroleum and Minerals, Dhahran, Saudi Arabia) (2.7) : Future usage of solar energy on an industrial scale. BEGHI. G. (Euratom. lspra)(8.10): Hydrogen economy: prospect ofa future energy system. DE BENI. G. (Euratom, (spra) (29.10): Thermodynamic«! processes for h>drogen production. KLAUDY. P.A. (Anstalt für Ticftempcraturforschung. Graz) (17.11): Low-tcmpcrature energy trans­ mission.

    DISCUSSION MEETINGS

    CLOSE. F.. DOLGOV. A.. GAILLARD, M.K.. STE1NBERGER, J. (CERN) (31.1): The new part­ icles: what are they? AMALDI. U.. CHALOUPKA. V.. SONDEREGGER. P.. STROOT. J.P. (CERN) (21.2): The new particles: what are CERN experimentalists doing? CASHMORE. R.. LAURENS. G.. CANESCHI. L.. ELLIS. J. (4.4): New particles at the SPS. HOLDER. M„ NANAPOULOS. D.. ROLLIER. M. (9.5): Neutral currents at the SPS. BARONCELLI. A.. WACHSMUTH. H. ELLIS. J. (20.6): Neutral currents at the SPS (continued). DARR1ULAT. P.. LEADER. E.. MICHEL. L.. MOHL. D.. MUNDAY. G.L., SIMONIUS. M. (3.10): On the desirability of polarized protons from the PS and in the ISR. COCCONI. G.. POVH. B.. ANDERSSON. B.A., RHO. M. (21.11): Should we accelerate nuclei? MATTHEWS. P.T. (Imperial College). ELLIS. J. and GAILLARD, M.K. (CERN) (19.I2): Why has charm not been found?

    229 CERN COMPUTER SEMINARS

    LEHMAN, M.M. (Imperial College. London) (13.3): Evolution dynamics or large programs. POWELL. M.J.D. (AERE, Harwell) (24.4): A view or algorithms for unconstrained minimization calculations. BROOKS. F. (University of North Carolina) (15.5) : Trends in interactive computing. rfARBER, D.L.A. (National Physical Laboratory, Teddington) (22.5): The European informatics network project. NEWSON, D.(IBM. Brussels) (12.6): VM/370. LILLESTRAND. R.L. (Control Data Corporation. Minneapolis) (24.6): Techniques and applications of image correlations. CRAY. S. (Cray Research Inc.. Chippewa Falls) ( 10.9) : Designing large computer systems. SUMNER. L. (9.10): Computer creations. HEARN, A.C. (University of Utah) (13.11): Scientific problem solving by symbolic computation. N1EVERGELT. J. (ETH. Zurich) (5.12): Interactive systems for the casual user: experiences with PLATO. APPENDIX C * TRAINING PROGRAMMES

    ACADEMIC TRAINING

    Lecture series ( 17 lecture series: 58 lectures) Liquid crystals, by P. G de Gennes (Collège de France) (3 lectures). Diffraction phenomena, by F. Müller (3 lectures). Scaling in particle physics, by S. Fubini (3 lectures). Streamer chambers, by F. Schneider (3 lectures). Modern matrix methods in scientific computing, by Mrs E. Edbcr? (5 lectures). Intersecting storage rings, by K. Hübner (4 lectures). Problems of classical dynamical systems, by W. Thirring (Theoretical Physics Institute. Vienna) (4 lectures). Case histories on the nucleus/fundamentals interface, by D.H. Wilkinson (Oxford University) (6 lectures). Euler's decomposition of an integer into four squares and its impact on modern computing methods of satellite orbits, by E. Stiefel (ETH. Zurich) (2 lectures). Spin-parity analyses of multiparticlc systems, by V. Chaloupka (4 lectures). Information retrieval, by R.F. Churchhouse (University College. Cardiff) (4 lectures). Polarized particles for accelerator physicists, by J.S. Bell (3 lectures). Spin temperature and dynamic nuclear polarization. Nuclear anliferromagnetism and ferromagnetism. Nuclear pseudomagnetism. by A. Abragam (Collège de France) (3 lectures). Generalized comexity applications, by S. Mandelbrojt (College de France) (2 lectures). Special purpose hardware processors, by C. Verkerk (3 lectures). High densities of matter from particle collisions and from gravitation, by G. Cocconi (3 lectures). Les nouvelles particules (for non-physicists), by P. Sonderegger (3 lectures). (Audience at each lecture: maximum 130 minimum 7.)

    TECHNICAL TRAINING

    Courses

    Mathématiques générales Mathématiques (2nd year), by F. Louis/PE (26 lectures 45'i hours). Mathématiques (3rd year), by F. Louis/PE (30 lectures - 52 !-i hours). Mathématiques (4th year), by F. Louis/PE (26 lectures - 45 '/; hours). Mathématiques (5th year), by F. Louis/PE (29 lectures - 50% hours).

    Informatique Initiation à l'informatique, by T. Lingjaerde/DD (10 lectures - 40 hours). Introduction to computers, by H. Slettenhaar/DD and T. Lingjaerde/DD (10 lectures 40 hours). Informatique appliquée, by H. Slettenhaar/DD and G. Ferran/DD (12 lectures 48 hours). Informatique de gestion, by L. Grosset/FIN (11 lectures - 44 hours). FORTRAN IV. by F. Louis/PE (35 lectures 70 hours). Systèmes d'exploitation de mini-ordinateurs, by H. Davies/DD and S. Lauper/DD (24 lectures 96 hours).

    * flic titles of the courses and lectures are given in the language used. Electronique Constructions électroniques, by M. Mary/MPS, H. Schröter/DD and A. Gandi/SB (22 lectures - 88 hours). Initiation à l'électronique (2nd year), by Ph. Rochat/ISR (22 lectures - 80 hours). Circuits et systèmes logiques, by B. Frammery/MPS (22 lectures - 88 hours).

    Mécanique Initiation aux techniques d'atelier (1st year), by A. Menétrey/PE (20 lectures - 80 hours). Initiation aux techniques d'atelier (2nd year), by A. Menétrey/PE (20 lectures - 80 hours). Techniques des liaisons mécaniques, by Messrs. Rudaz and Liebish/Sécheron S.A., Gland: Richardel/Ecole Technique Supérieure, Geneva; Simm/Castolin S.A., St. Sulpice and Ravussin/Alcyon S.A., Renens (8 lectures- 32 hours). Techniques cryogéniques, by P. Laeng/Institut de Physique expérimentale, Lausanne (22 lectures - 88 hours).

    Physique Initiation aux techniques du vide (2nd year), by M. Brouet/MPS (19 lectures - 76 hours). Physique fondamentale, by J.P. Lagnaux/NP(25 lectures - 100 hours). Eléments de mathématiques appliquées à la physique, by C. Gaille/Cycle d'orientation de l'ensei­ gnement secondaire. Geneva (27 lectures - 108 hours). (2X2 students were admitted to the courses above.)

    Seminars

    Conception et réalisation des circuits imprimés, by H. Vcrelst/ISR. M. d'Auria/MPS. P. Guerineau/'SB. A. Gandi SB and D. Rouillier/Comelim, France. (About 400 people attended this one-day seminar.) Microprocessors microcomputers, by E. Garen/lnlegrated Computer Systems. Culver City, Ca. USA. (X0 people attended this two-day seminar.)

    CERN SUMMER STUDENT LECTURE PROGRAMME

    Introduction to quantum mechanics, by A. D. Martin (3 lectures). Panicles and symmetries, by V.F. Weisskopf (4 lectures + I tutorial). Particles and symmetries, by V.L. Telegdi (8 lectures + 6 tutorials). FORTRAN programming, by D. Burkhardt (7 television lectures). C. Curran (6 lectures) and E. Edberg (6 lectures). High-energy physics for non-scientists, by R. Carreras (2 lectures). Bubble chamber physics, by R. Hemingway (2 lectures). The CERN accelerators, by H.O. Wüster (1 lecture). Fast selective detectors for high-energy physics experiments, by F. Sauli (2 lectures). Electronics for high-energy physics, by R. W. Dobinson (3 lectures). The architecture of large computers, by T. Bloch (3 lectures). The SPS experimental programme, by J. Allaby (1 lecture). Radiation protection, by J. Baarli (1 lecture) and M. Höfert (I lecture). Ultrahigh vacuum for the ISR, by E. Fischer (2 lectures). Experimental strong interaction physics at CERN, by U. Amaldi (3 lectures). Symmetry principles in physics, by T. D. Lee (1 lecture). Computing techniques: the Monte Carlo method, by F. James (2 lectures). What is a random number?, by F. James (1 lecture). Experimental neutrino physics, by J. Steinberger (1 lecture). Cross-talk of nuclear and particle physics, by V.L. Telegdi (1 lecture). Applications of proportional chambers outside particle physics, by G. Charpak (1 lecture). A human computer at work, by W. Klein (1 lecture).

    (Average attendance: 96 summer students (plus 18 others); maximum: 500 - minimum: 51). LANGUAGE COURSES

    Levels Number Number of hours per year of courses {for euch course) I. Audio-visual/audio-oral type courses English 1-2-3-4 8 Levels 1-2 136 Levels 3-4 102 French 1-2-3 10 Levels 1-2 i36 Level 3 102 II. Conversation courses/grammar practice English 5 3 Level 5 51 French 3-4-5 4 Levels 3-4-5 51 German 4 1 Level 4 51 III. Special courses English: intensive audio-visual course (SB Division) - 1 110 French : audio-visual 1 2 84 ordinary 5 1 48

    (These 30 courses represent about 3000 hours of teaching. About 380 students took part in them.)

    GENERAL EDUCATION

    Under the title "Science pour tous". 31 talks and 27 seminars were organized for non-scientific members of the personnel. Each talk was prefaced by a review of new developments in scierce (about 200 people attended each talk).

    Talks by R. Carreras 1. L'explosion du Krakatoa. 2. Immunité, auto-immunité et viru». 3. Le noyau de l'atome. 4. Laser et énergie nucléaire. 5. L'influx nerveux. 6. Les restes de la naissance de l'Univers. 7. Les manipulations génétiques. 8. Les lysosomes. 9. Il y a" 50 ans. 10. Le rapport du New Scientist sur Uri Geller. 11. Un coin du ciel. 12. L'énigme des pigeons voyageurs. 13. La colonisation de l'espace. 14. L'eau polymérisée. 15. Les aléas des témoignages visuels. 16. Quelques aspects de l'énergie de fusion. 17. Les oscilloscopes de la "Belle Epoque". 18. Rayons X hier et aujourd'hui. 19. Les mycoplasmes. 20. Quelques grands radio-télescopes. 21. La fixation de l'azote, 22. Etoiles, rayons X et trous noirs. 23. La structure universelle (9 + 2) des cils vibratiles. 24. Le manteau de la Terre. 25. L'humanité avant l'humanité. 26. La rotation du Soleil.

    233 27. Enfants, chimpanzés et reconstruction de figures. 28. Horloges biologiques "astronomiques"". 29. L'effet Kirlian et ses interprétations. 30. Le microscope acoustique. 31. Des objets vieux de 4.6 milliards d'années.

    "Connaissance du CERN", course by R. Carreras This course was designed for non-scientific members of the personnel with the aim of familiarizing them with the various aspects of the Organization. During the academic year 1974-1975. it was given twice in French and once in English. This course consisted of six lectures: Connaissance du CERN Understanding CERN 1. Vue d'ensemble. 1. The meaning of N in CERN. 2. Les accélérateurs. 2. How would you accelerate protons? 3. Les faisceaux de particules. 3. Colliding and non-colliding beams. 4. Les détecteurs. 4. Detecting with detectors. 5. Les particules. 5. Quasi-objecls called particles. 6. Le CERN et le monde d'aujourdTiui. 6. The place of CERN in the world of science and technology.

    The "Connaissance du CERN" course was followed by some additional sessions: "L'information". '"Une expérience au CERN: de l'idée aux résultats" and "Métiers et professions au CERN". by A. Jesse. "Peti'c histoire des chambres à bulles". "Matière et anti-matière" and "Découvertes récentes", by R. Carreras.

    APPRENTICESHIPS

    Number of apprentices from September 1974 to August 1975

    ;.sr 3rd 4,1, Catei]nr\ i TovA year year year I year

    r 1 2 Laboratory workers (physics) 3 3 ; 8 2 Mechanic, electronic equipment assemblers 1 | 3 ! 1 7

    Total 15

    The three apprentices (two laboratory workers and one mechanic,electronic equipment assembler) who completed their apprenticeship in 1975 obtained the "Certificat Fédéral de Capacité".

    234 APPENDIX D SCIENTIFIC CONFERENCES AND SCHOOLS

    The Scientific Conference Secretariat assisted in the organization of the 1975 J1NR-CERN School of Physics which took place at Alushta. Crimea, USSR. 14-28 May 1975. and which was attended by 19 st idents from J1NR. 40 from 21 institutes in 7 of its Member States and 35 students from 25 institutes in 8 CERN Member Stales. The lecture programme was as follows: Weak interactions at high energies, by B. A. Arbusov (IHEP, Serpukhov). Research programme with relativistic nuclei, by A.M. Baldin (JINR). Electromagnetic interactions of leptons and hadrons, by R. N. Faustov (JINR). CERN research programme, by W. Jentschke (CERN). JINR research programme, by K. Lanius (JINR). Regge phenomena, by C. Michael (University of Liverpool). Resonance phenomena, by L. Montanet (CERN). Many-particle production, by A.N. Sissakian (JINR). IHEP research programme, by L.D. Soloviev (IHEP. Serpukhov). Information about the new particles, by B.H. Wiik (DESY. Hamburg). The Scientific Conference Secretarial also assisted in the organization of the following events: Ma-ting of Medical Officers. CERN, 20 June 1975 (16 participants). Inauguration of the Reconstructed Synchro-cyclotron. CERN. 1 July 1975 (95 participants from outside CERN). Visit to CERN for participants attending the Seventh International Conference on Cyclotrons and their Applications. 25 August 1975 (54 participants). Autumn meeting of NOCUS (Nord Computer Users Society). CERN, 22-24 October 1975 (120 participants). Uli l'RIMINO Ol IUI lUIMV-I/RSl \.SSL.\I KII*>RI oh im. I.I:ROPI:AV OIUJAM/AIION IOR M"("II;AR KISI.AKCH. dl MVA. WASCOMl'l 1.11 DON IUI. II I.V1.MH IMY Ol /INI: MM: 11.1.S Hl.'NDRhD AM) si vi su -six IIY mi: IMPKIMLKILS RIIM1S S.A.. I \i:SANM.