Moray DAS ( & ) – Progress Report

For the period ending 21st September 2007 Ref: 415/14248

Summary

This progress report gives an overview of the tasks currently being carried out by MWH and OnSite/IETG/Future (survey contractors) in Rothes & Forres. This should be read in conjunction with the attached Programme.

Monthly Overview

Stage 1 - Scoping

• MWH consider the need for a Scoping Report has been superseded and request its removal, as the work has already been carried out and will be reported in the Model Build and Verification report.

Stage 2 - Model Build & Verification

• Model Build 1 – has now been completed. • Flow survey has been completed for both areas and all interim data has been received and reviewed. • CCTV and Manhole survey have been completed for both areas and data input to the model build. • CSO survey for Rothes and Forres are complete. • Final model build is now almost complete.

Stage 3 – FPS Analysis

• At a meeting between MWH, SW & MFAS on Friday 25th May, MFAS intimated that digitised conceptual FAS for Forres & Rothes would not be available until autumn 2007. This data is critical to the delivery of the FAS assessment and impacts considerably on the overall programme delivery. Information has been received in word format from SW relating to the Rothes scheme. MWH have also received a CD containing details of the Flood Prevention Schemes for Rothes and Forres from Moray Council, this information was provided in pdf format. Further drawings have been requested in a GIS compatible format.

Programme • Please see attached programme for our latest delivery estimates. The delivery of the Model Build & Verification programme is dictated by the availability of data from MFAS regarding the FAS scheme.

MWH ```````````` Rothes & Forres DAS Sept 07