Sample Procurement Plan

I. General

Public Disclosure Authorized 1. Bank’s approval Date of the procurement Plan: 2015 2. Date of General Procurement Notice: July, 10, 2015 3. Period covered by this procurement plan: The Project Period

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:

Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All Public Disclosure Authorized 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 1,500,000 All [Add other methods if necessary]

2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guideline

4. Any Other Special Procurement Arrangements: Given the prevailing impact of the

Public Disclosure Authorized ISIS conflict on , and need to address the urgent and developing requirements, procurement is being processed under paragraph 20 of OP 11.00 “Procurement under Situations of Urgent Need of Assistance or Capacity Constraints”, where “Simplified Procurement Procedures” may apply in accordance with paragraph 12 of the Bank OP 10.00 for investment project financing33. Procurement activities of this Project will include goods, works and both non- consultancy and consultant services under different Components. As they are identified, the activities will be packaged and finalized.

4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement)

Refer to the Procurement Plan

Public Disclosure Authorized III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

July 9, 2010 Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 200,000

2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Given the prevailing impact of the ISIS conflict on Iraq, and need to address the urgent and developing requirements, procurement is being processed under paragraph 20 of OP 11.00 “Procurement under Situations of Urgent Need of Assistance or Capacity Constraints”, where “Simplified Procurement Procedures” may apply in accordance with paragraph 12 of the Bank OP 10.00 for investment project financing33. Procurement activities of this Project will include goods, works and both non-consultancy and consultant services under different Components. As they are identified, the activities will be packaged and finalized.

4. Consultancy Assignments with Selection Methods and Time Schedule

Refer to the Procurement Plan

July 9, 2010 PROCUREMENT Iraq : Emergency Operation for Development PLAN General Information

Country: Iraq Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 Revised Plan Date(s): (comma delineated, leave blank if none)2020-09-16 Project ID: P155732 GPN Date: Project Name: Emergency Operation for Development Loan / Credit No: IBRD / 85200, IBRD / 87930 Executing Agency(ies):Ministry of Municipalities and Public Works - Roads & Bridges Directorate

WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned

EODP/MOCHPM/W2/3 / Restoring Electricity Maintenance of 20 KM of IBRD / 85200 Infrastructure and Prior Direct Selection Direct 949,093.00 9,011,223.05 Signed 2016-04-04 - Naft Khanna Connectivity Road in

EODP/MOCHPM/W8 / Restoring Electricity Rehabilitation of Al-Muthana IBRD / 85200 Infrastructure and Prior Direct Selection Direct 4,260,000.00 4,296,601.94 Signed 2016-08-10 Bridge (North Baghdad) Connectivity

EODP/MOCHPM/W10/1 / Restoring Electricity Rehabilitation of New and IBRD / 85200 Infrastructure and Prior Direct Selection Direct 8,980,677.00 952,321.28 Signed 2016-04-04 Old Al-Haronyah Bridges in Connectivity Diyala Governorate

EODP/MOCHPM/W10/2 / Restoring Electricity Rehabilitation (4) & (7) IBRD / 85200 Infrastructure and Prior Direct Selection Direct 1,902,525.00 1,908,996.29 Signed 2016-04-04 Imam Ways Bridges in Connectivity Diyala Governorate

EODP/MOCHPM/W10/7 / Rehabilitation of Steel & Restoring Electricity Concrete Bridge at Noreen IBRD / 85200 Infrastructure and Prior Direct Selection Direct 1,700,000.00 1,622,873.89 Signed 2016-04-04 river (on Qarataba - Connectivity Omarmandan road) in Diyala Governorate

EODP/MOCHPM/W10/3 / Restoring Electricity Rehabilitation of Al-Suodoor IBRD / 85200 Infrastructure and Prior Direct Selection Direct 951,101.00 954,336.58 Signed 2016-04-04 Bridge in Diyala Connectivity Governorate

EODP/MOCHPM/W2/2 / Restoring Electricity Maintenance of 42.5KM OF IBRD / 85200 Infrastructure and Prior Direct Selection Direct 9,950,000.00 9,227,740.87 Signed 2016-04-04 Naft Khanna -Mimili Road Connectivity in Diyala Governorate

EODP/MOCHPM/W5 / Rehabilitation of Al- Restoring Electricity Sheesheen Bridges (left & IBRD / 85200 Infrastructure and Prior Direct Selection Direct 2,117,270.00 2,124,471.85 Signed 2016-04-04 right sides) in Salah Ad-Din Connectivity Governorate

EODP/MOCHPM/W7 / Rehabilitation of Al-Dhuluiya Restoring Electricity big & small Bridges and IBRD / 85200 Infrastructure and Prior Direct Selection Direct 4,772,162.00 4,788,393.20 Signed 2016-04-04 Approaches in Salah Ad-Din Connectivity Governorate

Page 1 EODP/MOCHPM/W3/R1 / Restoring Transport Rehabilitation of Sammarra Infrastructure and Pending Open - Single Stage - One diversion bridge and IBRD / 85200 Developing a Housing Prior Request for Bids 15,100,000.00 0.00 Implementat 2017-04-16 2017-06-21 2017-07-26 2017-08-31 2017-10-02 2019-04-30 International Envelope Approaches (on Baghdad- Reconstruction Subsidy ion

Muosel road) Scheme

Restoring Transport EODP-AF/MOCHPM/W1-M / Infrastructure and Rehabilitation of Mosel 2nd IBRD / 87930 Developing a Housing Prior Direct Selection Direct 10,000,000.00 8,611,834.26 Signed 2018-12-10 2018-12-10 2018-12-12 2018-12-26 2019-12-12 bridge Reconstruction Subsidy Scheme

EODP-AF/MOCHPM/W4-A/1 Restoring Transport / Rehabilitation of Infrastructure and Single Stage - One interchange (Right & Left ) IBRD / 87930 Developing a Housing Post Request for Bids Open - National 3,500,000.00 2,676,050.00 Signed 2018-12-25 2019-05-22 2019-01-02 2019-01-23 2019-06-17 2019-02-07 2019-07-11 2019-02-21 2019-10-09 2020-02-21 Envelope at station 29 on Reconstruction Subsidy Expressway No.1/ R9 Scheme

EODP-AF/MOCHPM/W4-A/2 / Rehabilittaion of two Restoring Transport bridges (underpass bridges ) Infrastructure and Single Stage - One at station 31.2 & IBRD / 87930 Developing a Housing Post Request for Bids Open - National 3,750,000.00 2,761,400.00 Signed 2018-12-25 2019-05-27 2019-01-02 2019-01-23 2019-06-17 2019-02-07 2019-07-11 2019-02-21 2019-10-09 2019-12-18 Envelope 51+culverts between two Reconstruction Subsidy stations on Expressway Scheme No1/ R9

Restoring Transport EODP/MOCHPM/W2/10/A / Infrastructure and The Rehabilitation of Al- Open - Single Stage - One IBRD / 85200 Developing a Housing Prior Request for Bids 17,000,000.00 0.00 Canceled 2018-10-16 2018-10-18 2018-10-17 2018-10-18 2018-11-14 2018-12-02 2018-12-05 2018-12-17 2020-06-14 Khalis -Adheem road (on International Envelope Reconstruction Subsidy Baghdad- road)-Part A Scheme

Restoring Transport EODP/MOCHPM/W6 / Infrastructure and Rehabilitation of Tikreet IBRD / 85200 Developing a Housing Prior Direct Selection Direct 4,200,000.00 7,902,905.40 Signed 2017-05-29 2017-06-14 2017-08-24 2017-08-24 2018-07-20 bridge (on Tikreet-Alam Reconstruction Subsidy road) Scheme

EODP-AF/MOCHPM/W4-A/3- Restoring Transport PART 1 / Rehabilittaion of Infrastructure and culverts between(s0.0- Single Stage - One IBRD / 87930 Developing a Housing Prior Request for Bids Open - National 5,250,000.00 4,097,700.00 Signed 2019-07-07 2019-09-18 2019-07-12 2019-10-12 2019-08-02 2019-11-11 2019-08-16 2020-02-24 2019-09-06 2020-03-04 2020-09-05 s28.8km) and stations (s52- Envelope Reconstruction Subsidy s90km)on Expressway No1/ Scheme R9

EODP-AF/MOCHPM/W4-A/3- Restoring Transport PART 2 / Rehabilitation of Infrastructure and culverts between(St90 R9 - Single Stage - One IBRD / 87930 Developing a Housing Prior Request for Bids Open - National 6,250,000.00 4,556,700.00 Signed 2019-07-07 2019-09-18 2019-07-12 2019-10-12 2019-08-02 2019-11-11 2019-08-16 2020-01-22 2019-09-06 2020-01-30 2020-09-05 St11 R10) and rehabilitation Envelope Reconstruction Subsidy of bridge at station (St11 Scheme R10)

EODP-AF/MOCHPM/W4-A/4 Restoring Transport / Rehabilitation of WADI Infrastructure and Single Stage - One HORAN BRIDGE + Two IBRD / 87930 Developing a Housing Post Request for Bids Open - National 4,500,000.00 3,334,380.00 Signed 2019-07-10 2019-07-23 2019-07-16 2019-07-23 2019-08-06 2019-08-27 2019-08-27 2019-10-21 2019-09-13 2019-10-07 2020-09-12 Envelope bridges at station(St361 ,St Reconstruction Subsidy 262 KM) Scheme

EODP-AF/MOCHPM/W4-A/5 Restoring Transport / Rehabilitation of Two Infrastructure and Single Stage - One bridges at stations (St 335 IBRD / 87930 Developing a Housing Post Request for Bids Open - National 3,500,000.00 2,227,330.00 Signed 2019-07-10 2019-07-23 2019-07-16 2019-07-23 2019-08-06 2019-08-27 2019-08-27 2019-12-02 2019-09-13 2019-12-15 2020-09-12 Envelope ,St 355km) on Expressway Reconstruction Subsidy No.1/ R9 Scheme

EODP-AF/MOCHPM/W4-A/6 Restoring Transport / Rehabilitation of Two Infrastructure and Single Stage - One bridges at stations (St 313 IBRD / 87930 Developing a Housing Post Request for Bids Open - National 3,500,000.00 2,540,000.00 Signed 2019-07-10 2019-07-23 2019-07-16 2019-07-23 2019-08-06 2019-08-27 2019-08-27 2019-09-17 2019-09-13 2019-09-26 2020-09-12 Envelope ,St 280km) on Expressway Reconstruction Subsidy No.1/ R9 Scheme

Page 2 Restoring Transport EODP/MOCHPM/W2/10/A/R1 Infrastructure and / The Rehabilitation of Al- Open - Single Stage - One 12,093,100.0 IBRD / 85200 Developing a Housing Prior Request for Bids 16,000,000.00 Signed 2019-07-03 2019-09-17 2019-07-13 2019-09-17 2019-08-10 2019-08-07 2019-09-07 2019-09-18 2019-09-21 2019-11-14 2020-12-14 Khalis -Adheem road (on International Envelope 0 Reconstruction Subsidy Baghdad-Kirkuk road)-Part A Scheme

EODP- Restoring Transport AF/MOCHPM/W2/10/B / Infrastructure and Under REHABILITATION & Open - Single Stage - One IBRD / 87930 Developing a Housing Prior Request for Bids 15,250,000.00 0.00 Implementat 2020-01-24 2020-02-11 2020-01-31 2020-04-01 2020-02-28 2020-04-29 2020-03-20 2020-04-06 2021-06-30 MAINTENANCE OF International Envelope Reconstruction Subsidy ion KHALIS- ETHAIM Scheme HIGHWAY 50 KM (Part 2) Km 38 -Km 63

EODP-AF/MOCHPM/W5/R1 Restoring Transport / REHABILITATION OF 30 Infrastructure and Under KM OF AL SHERQAT Open - Single Stage - One IBRD / 87930 Developing a Housing Prior Request for Bids 13,250,000.00 0.00 Implementat 2020-01-24 2020-02-09 2020-01-31 2020-03-31 2020-02-28 2020-04-29 2020-03-20 2020-04-06 2021-06-30 intersection - International Envelope Reconstruction Subsidy ion RAMADHANYAT ROAD Scheme (TWO WAY)

Restoring Transport EODP-AF/MOCHPM/W2-M / Infrastructure and Open - Single Stage - One Rehabilitation of mosel 4th IBRD / 87930 Developing a Housing Prior Request for Bids 14,000,000.00 0.00 Canceled 2020-01-27 2020-02-09 2020-02-03 2020-04-20 2020-03-16 2020-04-29 2020-04-13 2020-08-30 2020-04-30 2022-04-30 International Envelope bridge crossing tigris river Reconstruction Subsidy

Scheme

Restoring Transport EODP-AF/MOCHPM/W3-M / Infrastructure and Open - Single Stage - One Under Rehabilitation of mosel 5th IBRD / 87930 Developing a Housing Prior Request for Bids 17,000,000.00 0.00 2020-01-27 2020-02-09 2020-02-06 2020-04-20 2020-03-19 2020-04-29 2020-04-16 2020-05-03 2022-05-03 International Envelope Review bridge crossing tigris river Reconstruction Subsidy

Scheme

EODP/MOCHPM/W11 / Restoring Transport Rehabilitation of Al-Baqaq Infrastructure and Under Concrete Bridge and IBRD / 85200 Developing a Housing Post Direct Selection Direct 2,900,000.00 0.00 Implementat 2020-08-10 2020-07-02 2020-08-10 2020-08-24 2021-04-21 Approaches in Nineveh Reconstruction Subsidy ion Governorate Scheme

Restoring Transport EODP-AF/MOCHPM/W2- Infrastructure and Pending M/R1 / Rehabilitation of Open - Single Stage - One IBRD / 87930 Developing a Housing Prior Request for Bids 11,700,000.00 0.00 Implementat 2020-09-14 2020-09-20 2020-10-18 2020-11-17 2020-12-22 2022-03-17 mosel 4th bridge crossing International Envelope Reconstruction Subsidy ion tigris river (rebidding) Scheme

EODP-AF/MOCHPM/K-W1 / Restoring Transport Maintenance of (32.11) Km Infrastructure and Pending Single Stage - One of KIRKUK-MANZALAH- IBRD / 87930 Developing a Housing Prior Request for Bids Open - National 5,200,000.00 0.00 Implementat 2020-09-18 2020-09-22 2020-10-13 2020-11-03 2020-12-07 2021-12-07 Envelope HAWIJAH ROAD in Kirkuk Reconstruction Subsidy ion Governorate Scheme

Restoring Transport EODP-AF/MOCHPM/K-W2 / Infrastructure and Pending Rehabilitation of Maktab Single Stage - One IBRD / 87930 Developing a Housing Post Request for Bids Open - National 1,110,000.00 0.00 Implementat 2020-09-18 2020-09-22 2020-10-13 2020-11-10 2020-12-09 2021-08-06 Khalid Bridge in Kirkuk Envelope Reconstruction Subsidy ion Governorate Scheme

Restoring Transport EODP-AF/MOCHPM/K-W3 / Infrastructure and Pending Rehabilitation Sadar Al-Nahr Single Stage - One IBRD / 87930 Developing a Housing Post Request for Bids Open - National 1,750,000.00 0.00 Implementat 2020-09-28 2020-10-11 2020-11-01 2020-12-01 2020-12-29 2021-10-25 Bridge in Kirkuk Envelope Reconstruction Subsidy ion Governorate Scheme

Restoring Transport EODP-AF/MOCHPM/B-SW1 Infrastructure and Pending Request for Single Stage - One / Renovation of Elevators of IBRD / 87930 Developing a Housing Post Limited 135,000.00 0.00 Implementat 2020-09-21 2020-11-15 2021-03-15 Quotations Envelope RBD Building Reconstruction Subsidy ion Scheme

GOODS

Page 3 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Restoring Electricity MOCH/G1 / Procurement of IBRD / 85200 Infrastructure and Prior Direct Selection Direct 11,018,664.00 11,018,664.00 Signed 2015-12-10 Prefabricated Steel Panels Connectivity

NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Restoring Transport MOCHPM/C7 / Construction Infrastructure and Quality And Cost- Open - Supervision (AL KHALIS IBRD / 85200 Developing a Housing Prior 1,500,000.00 1,222,410.00 Signed 2018-10-16 2019-08-01 2018-10-17 2018-10-17 2018-11-05 2019-01-10 2018-11-28 2019-03-05 2018-12-12 2019-08-02 2018-12-24 2020-06-20 2019-01-14 2019-12-12 2020-07-12 Based Selection International ADHEEM ROAD ) Reconstruction Subsidy

Scheme

EODP-AF/MOCHPM/M-C1 / Restoring Transport CONSTRUCTION Infrastructure and Quality And Cost- Open - SUPERVISION SEVRICES IBRD / 87930 Developing a Housing Prior 600,000.00 388,800.00 Signed 2018-12-10 2018-12-11 2018-12-12 2019-01-03 2019-01-07 2019-02-27 2019-01-21 2019-04-18 2019-02-03 2019-06-04 2019-02-11 2019-06-23 2020-02-11 Based Selection International FOR 2ND BRIDGE Reconstruction Subsidy

(AL HURRIYA) Scheme

EODP-AF/MOCHPM/A-C4 / (Design Review and Restoring Transport construction supervision ) Infrastructure and Quality And Cost- Open - Under For Damaged Wadi bridges IBRD / 87930 Developing a Housing Prior 1,500,000.00 0.00 2019-07-15 2019-09-25 2019-07-18 2019-09-25 2019-08-09 2019-12-27 2019-08-30 2020-01-30 2019-09-09 2020-05-07 2019-09-23 2019-10-07 2020-10-06 Based Selection International Implementation (under passes ) and over Reconstruction Subsidy pass along the western Scheme stretch of expressway No.1

EODP-AF/MOCHPM/M-C2 / Restoring Transport Consultancy services (Design Infrastructure and Quality And Cost- Open - Under Review and construction IBRD / 87930 Developing a Housing Prior 1,250,000.00 0.00 2019-10-03 2020-01-22 2019-10-10 2019-11-07 2020-03-10 2019-12-05 2020-04-22 2019-12-19 2020-01-09 2020-01-23 2022-01-22 Based Selection International Implementation supervision ) for mosel 4th Reconstruction Subsidy bridge Scheme

EODP-AF/MOCHPM/M-C3 / Restoring Transport Consultancy services (Design Infrastructure and Quality And Cost- Open - Under Review and construction IBRD / 87930 Developing a Housing Prior 850,000.00 0.00 2019-10-03 2020-01-22 2019-10-10 2020-01-23 2019-11-07 2020-04-23 2019-12-05 2019-12-19 2020-01-09 2020-01-23 2020-04-05 Based Selection International Implementation supervision ) for mosel5th Reconstruction Subsidy bridge Scheme

EODP-AF/MOCHPM/D-C6 / Restoring Transport Construction Supervision of Infrastructure and REHABILITATION & Quality And Cost- Open - Pending IBRD / 87930 Developing a Housing Prior 900,000.00 0.00 2020-09-17 2020-09-22 2020-10-22 2020-11-19 2020-11-20 2020-12-25 2021-01-29 2022-01-29 MAINTENANCE OF Based Selection International Implementation Reconstruction Subsidy KHALIS- ETHAIM Scheme HIGHWAY Part (2)

Page 4 EODP-AF/MOCHPM/S-C7 / Construction Supervision of Restoring Transport REHABILITATION OF 30 Infrastructure and Quality And Cost- Open - Pending KM OF AL SHERQAT IBRD / 87930 Developing a Housing Prior 800,000.00 0.00 2020-09-18 2020-10-09 2020-11-08 2020-11-29 2020-12-20 2021-01-24 2021-02-28 2022-02-28 Based Selection International Implementation intersection - Reconstruction Subsidy

RAMADHANYAT ROAD Scheme (TWO WAY)

Restoring Transport EODP-AF/MOCHPM/K-C9 / Infrastructure and Construction Supervision of Quality And Cost- Open - Pending IBRD / 87930 Developing a Housing Post 450,000.00 0.00 2020-09-28 2020-10-19 2020-12-02 2020-12-30 2021-01-29 2021-03-05 2021-04-08 2021-04-10 Kirkuk projects (Two Bridges Based Selection International Implementation Reconstruction Subsidy and one Road) Scheme

INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Restoring Transport EODP-AF/MOCHPM/M4-D1 Infrastructure and / Consultancy services IBRD / 87930 Developing a Housing Post Direct Selection Direct 160,000.00 160,000.00 Signed 2019-07-21 2019-07-24 2019-07-24 2019-08-27 2019-07-31 2019-09-30 2019-10-29 Design for mosel 4th bridge Reconstruction Subsidy Scheme

Restoring Transport EODP-AF/MOCHPM/M5-D2 Infrastructure and / Consultancy services IBRD / 87930 Developing a Housing Post Direct Selection Direct 100,000.00 100,000.00 Signed 2019-07-21 2019-07-24 2019-07-24 2019-08-27 2019-07-31 2019-09-26 2019-10-29 Design for mosel 5th bridge Reconstruction Subsidy Scheme

Restoring Transport MOCHPM/C11 / Infrastructure and Construction supervision IBRD / 85200 Developing a Housing Post Direct Selection Direct 300,000.00 0.00 Under Review 2019-08-20 2019-09-12 2019-08-22 2019-08-29 2020-11-21 ( ala alm bridge Reconstruction Subsidy Scheme

Page 5