Armenian Social Investment Fund Procurement Plan for the Third Additional Financing

11-Sep-12

Expected Status (1 Expected Contract No Estimated price in Post/prior Bid active, 5- Level of Completeness Contract ID Description Type Method Invitation signing Contract price Contractor Ranking . AMD review Opening complet damege status Date date

Public Disclosure Authorized Date ed)

Overhaul of Vanand second school Complete 1 AR-029 building with placement of kindergarten, W NCB 107,994,056 post 23.05.12 22.06.12 Aug-12 AMD 100,916,460 1 "Baghramyanshin" OJSC 40-60% 2 phase 2 Marz of Armavir Installation of the heating system, completion of renovation of the Cultural Complete 2 AR-030 W Shopping 27,640,796 prior 20.08.12 03.09.12 Sep-12 20-40% - House in the village of Voskehat., marz phase 2 of Armavir Completion of construction of the 3 AT-070 kindergarten's second building and W NCB 129,374,620 post 12.04.12 12.05.12 Jul-12 AMD 118,703,686 1 "Araratshin" LLC 0-20% - Complete

Public Disclosure Authorized warm passage in Ayntap, Marz of Ararat

Reinforcement, overhaul of the music Complete 4 GQ-050 W NCB 129,846,221 post 28.07.12 29.08.12 Sep-12 20-40% 3 school in , Marz of Gegharqunik Construction of the daily run-off pond 5 GQ-052 and external water-pipe in , W NCB 57,716,442 post 01.09.12 02.10.12 Oct-12 20-40% - Complete Marz of Gegharqunik Overhaul of two buildings and the warm passages of the kindergarten in the Complete 6 GQ-053 village of , installation of W NCB 104,423,483 post 24.09.12 24.10.12 Nov-12 20-40% 2 phase 1 the heating system, Marz of Public Disclosure Authorized Gegharqunik Completion of cultural center’s renovation and installation of its heating 7 GQ-055 W Shopping 23,135,112 post 25.09.12 09.10.12 Oct-12 0-20% - Complete system in the village of , Marz of Gegharqunik Installation of the heating system of 8 GQ-056 school in the village of , Marz W Shopping 30,658,068 post 25.09.12 09.10.12 Oct-12 20-40% 1 Complete of Gegharqunik Construction of a kindergarten in Artavaz 9 KQ-035 W NCB 128,618,280 post 05.09.12 05.10.12 Oct-12 40-60% - Complete community, Marz of Kotayq Completion of construction works for 10 LR-043 community center of Arevashogh, Marz W NCB 129,997,543 prior 28.07.12 27.08.12 Sep-12 20-40% ` Complete Public Disclosure Authorized of Lori Completion of construction works for 11 LR-044 community center of Hartagyugh, Marz W NCB 125,605,805 prior 28.07.12 27.08.12 Sep-12 40-60% Complete of Lori Installation of the heating system termo/water insulation works of the 12 LR-045 W Shopping 9,965,250 post 14.09.12 28.09.12 Oct-12 20-40% - Complete museum after H.Toumanyan in the village of , Marz of Lori Overhaul of the kindergarten building in 13 SH-044 Ashotsk community, installation of the W NCB 83,372,149 post 24.08.12 24.09.12 Oct-12 20-40% 2 Complete heating system, Marz of Shirak

14 SH-045 Reconstruction of the kindergarten W NCB 70,311,326 post 06.09.12 05.10.12 Oct-12 20-40% 2 Complete building in Pemzashen, Marz of Shirak Reconstruction of the Art school in 15 SQ-038 Agarak, installation of the heating W NCB 129,702,233 post 26.09.12 26.10.12 Nov-12 40-60% 3 Complete system, Marz of Syuniq Overhaul of the school in Gorayq, Marz 16 SQ-039 W NCB 129,783,125 post 30.08.12 01.10.12 Oct-12 20-40% 2 Complete of Syuniq Construction completion of the school in 17 SQ-040 the village of Shamb, community, W NCB 129,427,200 post 30.08.12 01.10.12 Oct-12 20-40% - Complete Marz of Syuniq Overhaul of the school in the village of 18 SQ-041 Tsghuk, installation of the heating W NCB 129,880,195 post 30.08.12 01.10.12 Oct-12 40-60% 2 Complete system, Marz of Syuniq Reconstruction of the museum after H. 19 SQ-042 Sahyan in the village of Lor, Marz of W Shopping 28,559,730 post 18.09.12 02.10.12 Oct-12 40-60% 2 Complete Syuniq School furniture for Shirak marz of 20 TAFG-01 G NCB 45,000,000 prior 24.09.12 24.10.12 Nov-12 21 TAFG-02 Computer equipment for ASIF G Shopping 10,262,500 prior 18.09.12 02.10.12 Oct-12 Completion of renovation in Complete 22 TV-030 W NCB 97,858,288 post 18.05.12 18.06.12 Jul-12 AMD 79,145,076 1 "Jean Shean" LLC 40-60% 1 school, Marz of Tavoush phase 3 Construction of the community center in 23 TV-031 W NCB 62,691,300 post 10.07.12 10.08.12 Aug-12 AMD 63,428,192 1 "Bazalt M" LLC 40-60% - Complete , Marz of Tavoush Construction of a kindergarten in 24 TV-032 W NCB 125,382,600 post 28.07.12 28.08.12 Sep-12 40-60% - Complete Voskevan, Marz of Tavoush Overhaul of N2 kindergarten in , Complete 25 TV-033 installation of the heating system, Marz W NCB 129,726,500 post 26.09.12 26.10.12 Nov-12 20-40% 2 phase 1 of Tavoush Construction of the community center in 26 TV-034 the village of Nerqin Karmiraghbyur, W NCB 112,844,340 post 05.09.12 04.10.12 Oct-12 40-60% - Complete Marz of Tavoush Overhaul of the secondary school building in the village of , 27 TV-035 W NCB 115,272,718 post 15.09.12 15.10.12 Nov-12 40-60% 2 Complete installation of the heating system, Marz of Tavoush Placement of kindergarten in community 28 TV-036 center’s building in the village of Teghut, W NCB 75,951,926 post 10.10.12 09.11.12 Nov-12 20-40% 2 Comlpete Marz of Tavoush Technical Supervision of Construction, 29 TAFTS-001 Shirak,Lori,Aragatsotn,, CS CQ 25,000,000 prior 01.03.12 15.03.12 Jun-12 AMD 5,611,950 1 "Alternative" LLC Gegharqunik. Technical Supervision of 30 TAFTS-002 Construction,Syuniq,Vayoc CS CQ 25,000,000 prior 01.03.12 15.03.12 Jul-12 AMD 3,258,000 1 "Durgabshin" Ltd. Dzor,Ararat,Armavir, Kotayq Design & Author Supervision of Potable Hayjrnakhagits institute" 31 TPD-001 Water, Sewerage & Irrigation Systems CS CQ 12,000,000 prior 01.03.12 15.03.12 Jul-12 AMD 4,820,000 1 CJSC throughout RoA Design & Author Supervision for 32 TPD-002 Construction & Reconstruction of CS CQ 25,000,000 prior 01.03.12 15.03.12 May-12 AMD 23,186,000 1 "Glomma" CooP Buildings Tavush,Lori,Gegharqunik Design & Author Supervision of Capital Renovation & Reconstruction of 33 TPD-003 CS CQ 40,000,000 prior 01.03.12 15.03.12 Apr-12 AMD 28,743,824 1 "Engineering Evros" LLC Buildings & Constructions Aragatsotn,Shirak,Kotayq Design and Author supervision for 34 TPD-004 Construction & Rehabilitation of CS CQ 20,000,000 prior 01.03.12 15.03.12 Jun-12 AMD 11,061,600 1 "Mara ev Dustrer" LLC buildings, Armavir,Ararat. Design and Author supervision for 35 TPD-005 Construction & Renovation of CS CQ 20,000,000 prior 01.03.12 15.03.12 May-12 AMD 20,625,750 1 "Jean Shean" LLC buildings,Vayoc Dzor,Syuniq. Design and Author supervision for 36 TPD-006 CS CQ 20,000,000 post 19.07.12 06.08.12 Aug-12 AMD 6,325,800 1 "Ratman" LLC Construction & Renovation of buildings

"HH Nakhagtseri Petakan 37 TEX-01 Expertise of Architectural Design CS CQ 12,000,000 prior 01.03.12 15.03.12 May-12 AMD 9,232,000 1 Artagerateschakan Pordzaqnnutyun" CJSC Expertise of buildings stability, "ARSEA" Gitaartadrakan 38 TEX-02 ventilation, power and water supplies CS CQ 8,000,000 prior 01.03.12 15.03.12 Jun-12 AMD 1,976,400 1 LLC and drainage systems Reconstruction of the kindergarten in 39 VZ-019 the village of Gladzor, installation of the W NCB 126,466,553 post 30.08.12 02.10.12 Oct-12 0-20% 2(3) Complete heating system, Marz of Vayots Dzor

Reconstruction of the kindergarten in 40 VZ-020 the village of Getap, installation of the W NCB 129,713,558 post 30.08.12 02.10.12 Oct-12 0-20% 2(3) Complete heating system, Marz of Vayots Dzor Reconstruction of the potable water 41 VZ-021 system in the village of Rind, Marz of W NCB 128,666,815 post 06.09.12 04.10.12 Oct-12 20-40% - Complete Vayots Dzor