Construction Update Victoria Park Avenue to

Eglinton Crosstown LRT

March 30, 2021 Section Three and Four At-Grade: O’Connor Stop to Ionview Stop CONSTRUCTION ACTIVITIES

Location Activity Approx. Date & Duration

O’Connor Stop to • Light poles installation (stops) • Completed March Ionview Stop O’Connor Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April (Victoria Park Ave)

Pharmacy Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April

• Concrete for both east & west planter curbs • Completed March Hakimi Lebovic Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April

Golden Mile Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April (Warden Ave)

Birchmount Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April • West wing wall construction • Completed March Massey Creek Culvert • Backfill • Ongoing through April

Ionview Stop • Shelter finishing activities; platform ramps, walls • Ongoing until April

3 ROSEMOUNT DRIVE AND EGLINTON AVE E Until as early as April 2021

• North side closure for Massey Creek Construction • Crews have completed filling old culvert • Crews have completed the wingwall construction • Crews continue with backfilling and minor paving activities

4 CONSTRUCTION PROGRESS PHOTOS

CURB COMPLETE PLANTERS COMPLETED O’CONNOR STOP PHARMACY STOP

5 CONSTRUCTION PROGRESS PHOTOS

PLANTERS COMPLETED CURBS COMPLETE PHARMACY STOP BIRCHMOUNT STOP

6 Kennedy Station KENNEDY STATION UPDATE

Location Activity Approx. Date & Duration Kennedy Rd and Eglinton Ave E • Pedestrian Change • Ongoing for approx. six months Kennedy Portal • Track works • Ongoing through Spring (west of Kennedy Road) • Conduit installation, plumbing and sheet • Ongoing through 2021 metal works, tiling, masonry works Kennedy Station Main Entrance • Elevator & escalator installation • Ongoing through 2021 • TPSS & TVS electrical fit up • Ongoing until May • Concrete works, rebar, and shoring • Ongoing through Spring Kennedy Station Box • Floor tiling • Ongoing through 2021 • GO entrance precast installation • Completed March Kennedy Station GO Entrance and • Excavation & concrete works • Ongoing through June Platform • Retaining wall construction • Ongoing through Spring • Weekend utility work • April 2 - 4 • Final invert pour; waterproofing • Completed March • Concrete & masonry works • Ongoing through Spring Kennedy Station – East of GO Platform construction, track & drainage • • Ongoing through 2021 alignment • Ongoing through 2021 • Electrical and mechanical works

8 KENNEDY CURRENT TRAFFIC CONFIGURATION March 2021 for approx. six months

9 UTILITY CASING CROSSING April 2-4, 2021

• Installation of utility casing includes the use of excavators, front end loaders, rollers, and tampers • Crews will be excavating to install the casing, and then refilling and levelling the demolition site with fresh granular material and compaction of the material into the ground • Noise and vibration can be expected

10 GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR August 17, 2020 for approx. one year

• As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year.

11 CONSTRUCTION PROGRESS PHOTOS

CONCRETE WORKS GO EAST PLATFORM

CEILING GRID INSTALLATION PLATFORM LEVEL

12 CONSTRUCTION PROGRESS PHOTOS

PRECAST INSTALLATION GO ENTRANCE

REBAR AND CONCRETE WORK STATION BOX