Construction Update Victoria Park Avenue to Kennedy Station

Total Page:16

File Type:pdf, Size:1020Kb

Construction Update Victoria Park Avenue to Kennedy Station Construction Update Victoria Park Avenue to Kennedy Station Eglinton Crosstown LRT March 30, 2021 Section Three and Four At-Grade: O’Connor Stop to Ionview Stop CONSTRUCTION ACTIVITIES Location Activity Approx. Date & Duration O’Connor Stop to • Light poles installation (stops) • Completed March Ionview Stop O’Connor Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April (Victoria Park Ave) Pharmacy Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April • Concrete for both east & west planter curbs • Completed March Hakimi Lebovic Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April Golden Mile Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April (Warden Ave) Birchmount Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April • West wing wall construction • Completed March Massey Creek Culvert • Backfill • Ongoing through April Ionview Stop • Shelter finishing activities; platform ramps, walls • Ongoing until April 3 ROSEMOUNT DRIVE AND EGLINTON AVE E Until as early as April 2021 • North side closure for Massey Creek Construction • Crews have completed filling old culvert • Crews have completed the wingwall construction • Crews continue with backfilling and minor paving activities 4 CONSTRUCTION PROGRESS PHOTOS CURB COMPLETE PLANTERS COMPLETED O’CONNOR STOP PHARMACY STOP 5 CONSTRUCTION PROGRESS PHOTOS PLANTERS COMPLETED CURBS COMPLETE PHARMACY STOP BIRCHMOUNT STOP 6 Kennedy Station KENNEDY STATION UPDATE Location Activity Approx. Date & Duration Kennedy Rd and Eglinton Ave E • Pedestrian Change • Ongoing for approx. six months Kennedy Portal • Track works • Ongoing through Spring (west of Kennedy Road) • Conduit installation, plumbing and sheet • Ongoing through 2021 metal works, tiling, masonry works Kennedy Station Main Entrance • Elevator & escalator installation • Ongoing through 2021 • TPSS & TVS electrical fit up • Ongoing until May • Concrete works, rebar, and shoring • Ongoing through Spring Kennedy Station Box • Floor tiling • Ongoing through 2021 • GO entrance precast installation • Completed March Kennedy Station GO Entrance and • Excavation & concrete works • Ongoing through June Platform • Retaining wall construction • Ongoing through Spring • Weekend utility work • April 2 - 4 • Final invert pour; waterproofing • Completed March • Concrete & masonry works • Ongoing through Spring Kennedy Station – East of GO Platform construction, track & drainage • • Ongoing through 2021 alignment • Ongoing through 2021 • Electrical and mechanical works 8 KENNEDY CURRENT TRAFFIC CONFIGURATION March 2021 for approx. six months 9 UTILITY CASING CROSSING April 2-4, 2021 • Installation of utility casing includes the use of excavators, front end loaders, rollers, and tampers • Crews will be excavating to install the casing, and then refilling and levelling the demolition site with fresh granular material and compaction of the material into the ground • Noise and vibration can be expected 10 GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR August 17, 2020 for approx. one year • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year. 11 CONSTRUCTION PROGRESS PHOTOS CONCRETE WORKS GO EAST PLATFORM CEILING GRID INSTALLATION PLATFORM LEVEL 12 CONSTRUCTION PROGRESS PHOTOS PRECAST INSTALLATION GO ENTRANCE REBAR AND CONCRETE WORK STATION BOX 13 .
Recommended publications
  • Connecting the Region
    EGLINTON CROSSTOWN CONSTRUCTION UPDATE EASTERN WORKS OPEN HOUSE | APRIL 9, 2020 WELCOME Our Eastern Works Open House will feature the following stations and stops: • Science Centre • Aga Khan Park & Museum, Wynford, Sloane, O’Connor • Pharmacy , Hakimi Lebovic, Golden Mile, Birchmount, Ionview • and Kennedy. 2 COVID-19 MANAGEMENT • Crosslinx Transit Solutions (CTS) has been exercising all safety protocols on-site including social distancing. • For more information on CTS’ COVID-19 Management, please visit their website: http://www.crosslinxtransit.ca/wp-content/uploads/CTS_COVID- 19_mobile_v2.png EGLINTON CROSSTOWN LRT PROJECT • A 19-kilometre route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface in east • 15 underground stations and 10 surface stops • A maintenance and storage facility • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station PROJECT PROGRESS Maintenance and Storage Facility complete 12 vehicles received 50% of track installed Mining complete at Laird and Oakwood stations Deep excavation underway or complete at all stations 2019 PROJECT HIGHLIGHTS FIRST LIGHT RAIL VEHICLE ON MAINLINE 8 9 10 SCIENCE CENTRE STATION RENDERINGS AERIAL VIEW MAIN ENTRANCE WEST PORTAL LOBBY BUS TERMINAL SCIENCE CENTRE STATION: WHAT TO EXPECT Year What to Expect • Completion of all structural concrete works 2019 Milestones • Completion of support of excavation • Completion of excavation • Interior works at Station Box • Interior and exterior finishes as Main Entrance • Track work and rail installation Remaining Work • Waterproofing and backfill for 2020 • Permanent road restoration • Substantial completion late 2020 SCIENCE CENTRE STATION PROGRESS PHOTOS WALL TILING AT THE MAIN ENTRANCE GLAZING AT THE BUS TERMINAL Aga Khan & Museum Stop to O’Connor Stop (Don Valley Parkway to Victoria Park Ave) Brentcliffe Portal AGA KHAN PARK & MUSEUM STOP RENDERINGS SIDEWALK PLATFORM AERIAL VIEW WYNFORD STOP RENDERINGS SIDEWALK PLATFORM .
    [Show full text]
  • CROSSTOWN LRT TOWN HALL April 2019 Agenda
    CROSSTOWN LRT TOWN HALL April 2019 Agenda 7:00 to 7:30 – View Deck 7:30 to 8:00 – Presentation 8:00 to 8:30 – Question & Answer 2 Eglinton Crosstown Overview • 19 km route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface east of Laird • 15 underground stations and 10 surface stops • 20,000 m2 maintenance and storage facility to maintain and house 76 vehicles • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station 3 Eglinton Avenue East - Final Configuration O’Connor Stop at Victoria Park and Eglinton Avenue 4 Eglinton Avenue East - At-Grade Construction • Major work will be occurring at intersection between Leslie and Ionview throughout 2019 • LRT guideway will be constructed in the middle of Eglinton and track will be installed • The work takes place in two stages – paving, followed by guideway construction and track installation 5 2019 Construction Schedule – Leslie to Ionview Road 6 Sunnybrook Park Stop – Leslie/Eglinton 7 July-August Traffic Restriction - Leslie/Eglinton • Crosslinx is seeking city permits for a temporary eight week restriction on vehicles travelling between Leslie Street & Eglinton Avenue East • Allows for LRT guideway construction & track installation. • Eglinton Avenue will remain open in both directions at all times. • Leslie Street will otherwise function normally. • Traffic lanes will open up & turn restrictions will be lifted at Bayview/Eglinton & Don Mills/Eglinton before the Leslie work starts. • Proposed timeline is during the lowest traffic volume months. 8 8 July-August Traffic Restriction - Leslie/Eglinton • Emergency services access to and from Eglinton Avenue will be maintained at all times.
    [Show full text]
  • CROSSTOWN LRT November 14, 2017
    CROSSTOWN LRT Science Centre Station & West At-Grade Surface Stops November 14, 2017 WHO IS METROLINX? PLAN BUILD OPERATE 2 THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041) outlines how governments and transit agencies can work together to continue building an integrated transportation system to support a high quality of life, a prosperous and competitive economy, and a protected environment in our region. As the provincial agency mandated with improving the coordination and integration of all modes of transportation in the GTHA, Metrolinx has developed the Draft Plan for review in consultation with partners, stakeholders and the public. The Next RTP LEARN MORE, GET INVOLVED Metrolinx has just released its Draft 2041 Regional Plan which outlines how people and goods will move across our great region. Curious about what’s in the Draft 2041 Plan? You can review and comment on the plan at metrolinx.com/theplan and join us for one of our roundtable discussions, where you can share your views on the future of regional mobility. Other ways to stay engaged: • Visit metrolinxengage.com • Read our blog, The Link • Follow us on social media Continuing TTC rollout in 2017 What Are We Building – a New Modern LRT • 15 underground stations and 10 surface stops – 9 km below ground and 10 km above ground • A maintenance and storage facility • A 19-kilometre route separated from regular traffic • Transit communications system • Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station 6 Safety First – Our #1 Priority We train and direct staff to: • Always have a site specific safety plan and site specific emergency plan.
    [Show full text]
  • Eglinton Crosstown Update: Eastern Works (Victoria
    EGLINTON CROSSTOWN UPDATE: OPEN HOUSE MEETING EASTERN WORKS (VICTORIA PARK AVE. TO KENNEDY RD.) Metrolinx is building the Eglinton Crosstown, Toronto’s new 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue with a central 10 km underground section. The Crosstown will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today. With 25 stations and stops and connections to 3 TTC subway stations, 54 local bus routes, 3 GO Transit lines and the UP Express, the Crosstown will improve travel times and change the way we move through the heart of the city. Join Metrolinx and its constructor, Crosslinx Transit Solutions (CTS), at the upcoming open house and learn about the progress at: Pharmacy Stop Hakimi Lebovic Stop Golden Mile Stop Birchmount Stop Ionview Stop Kennedy Station Join us to learn about: • current and upcoming construction in your neighbourhood; • construction impacts and who to contact if you have questions/concerns, and; • station progress, design and other informative pieces. When: Wednesday, November 21, 2018 6:30 p.m. to 8:00 p.m. Where: Eglinton Square Shopping Centre (Bay Corridor) 1 Eglinton Square Sign up at www.thecrosstown.ca/sign-up for construction updates and download the aCrosstown mobile app to get real-time traffic information for the Eglinton corridor. East Community Office Email: EGLINTON CROSSTOWN 660 Eglinton Avenue East [email protected] 416-482-7411 www.thecrosstown.ca facebook.com/thecrosstown twitter.com/crosstownTO.
    [Show full text]
  • Train Testing Video: Click Here
    IT’S HAPPENING, TODAY Forum Eglinton Crosstown LRT Metrolinx’s Core Business – Providing Better, Faster, Easier Service We have a strong connection with our Adding More Service Today Making It Easier for Our customers, and a Customers to Access Our great understanding Service of who they are and Building More to Improve Service where they are going. Planning for New Connections Investing in Our Future MISSION: VISION: WE CONNECT GETTING YOU THERE COMMUNITIES BETTER, FASTER, EASIER 3 Train Testing Video: Click Here 6 Eglinton Crosstown Supports for Community • The Eglinton Crosstown LRT Project contractually requires the constructor, Crosslinx Transit Solutions Constructors (CTSC), to embed community benefits in their work, including ensuring that local communities and historically disadvantaged groups benefit directly from the province’s $5.3 billion investment. • We are committed to making the pathway to professional, administrative and technical (PAT) roles in the construction industry more accessible to people facing barriers to employment. • CTS has hired 209 people in PAT roles to date, as well as 185 apprentices and journey persons from historically disadvantaged and equity seeking groups. • We are committed to supporting small and medium sized businesses along the Eglinton corridor, businesses impacted by our construction, and social enterprises that create employment and training opportunities for people who face systemic barriers to employment. • CTS has spent more than $800,000 on social enterprises and more than $7 million at local businesses. EGLINTON CROSSTOWN Eglinton Crosstown COVID-19 Construction Safety • With construction remaining classified as an essential industry, work on the Eglinton Crosstown LRT continues through the COVID-19 pandemic.
    [Show full text]
  • ECLRT Environmental Report Cover.Ai
    Transit City Eglinton Crosstown Light Rail Transit EGLINTON CROSSTOWN LRT Transit Project Assessment Study Eglinton Crosstown An agency of the Government of Ontario TCG Transit City Group ENVIRONMENTAL PROJECT REPORT March 2010 N T A R I O E O L A K Toronto Transit Commission/City of Toronto EGLINTON CROSSTOWN LIGHT RAIL TRANSIT TRANSIT PROJECT ASSESSMENT ENVIRONMENTAL PROJECT REPORT ENVIRONMENTAL PROJECT REPORT MARCH 2010 Toronto Transit Commission/City of Toronto EGLINTON CROSSTOWN LIGHT RAIL TRANSIT TRANSIT PROJECT ASSESSMENT Environmental Project Report 2.2 Feasibility Studies ............................................................................................................... 17 TABLE OF CONTENT 2.2.1 Renforth to Kennedy Station ............................................................................................... 17 1. INTRODUCTION .................................................................................................................................. 1 2.2.2 Airport Link Pearson International Airport to Martin Grove ................................................... 17 1.1 Study Purpose ...................................................................................................................... 1 2.2.3 Key Challenges and Constraints ......................................................................................... 18 1.2 Study Scope ......................................................................................................................... 1 2.2.4 Options ..............................................................................................................................
    [Show full text]
  • EXECUTIVE SUMMARY Amendment
    Toronto Transit Commission/City of Toronto EGLINTON CROSSTOWN LIGHT RAIL TRANSIT TRANSIT PROJECT ASSESSMENT Environmental Project Report and buses. The connection of the Eglinton Crosstown LRT to Kennedy Station will be the subject of an EA EXECUTIVE SUMMARY amendment. E.1. INTRODUCTION The connection of the Eglinton Crosstown LRT with the Airport Terminal lands will be determined following completion of Metrolinx‟s Airport Precinct Study and the Greater Toronto Airports Authority Transportation The Toronto Transit Commission (TTC) and City of Toronto have undertaken a Transit Project Assessment Master Plan. Subsequently, TTC and the City will comply with applicable environmental assessment for the 33 kilometre long Eglinton Crosstown Light Rail Transit (Eglinton Crosstown LRT) corridor that regulations for the finalization of the alignment on the federally-owned airport lands. would link the Pearson International Airport with the Kennedy Station. The Eglinton Crosstown LRT will connect with the Spadina Subway Line, the Yonge Subway Line, the Scarborough RT and the planned The preferred connection of the Eglinton Crosstown LRT with the TTC Maintenance and Storage Facility at Jane Street LRT, Don Mills Road LRT, Scarborough-Malvern LRT, and Mississauga BRT. This study Black Creek Drive is reflected in this Transit Project Assessment, although the TTC Maintenance and recommends that bus services along Eglinton Avenue be replaced by Light Rail Transit (LRT) with Storage Facility itself is undergoing a separate environmental assessment. electrically
    [Show full text]
  • Eglinton Crosstown Open House Panels Pt. 3
    Don Mills Station (Bus Terminal) At Open House 2 in June/July 2009, two alternatives were shown for the interchange with the Don Mills LRT. The preferred alternative is for the Don Mills LRT to operate at surface with an underground Eglinton LRT station. This alternative will improve the speed and reliability of the Eglinton Crosstown LRT through this busy intersection and will provide a safer and more convenient transfer between the two LRT lines and the bus terminal. 41 Wynford Stop At Open House 2 in June/July 2009, two alternatives were shown for this area. The preferred alternative shown here eliminates the need to climb stairs between Wynford Drive and the LRT. 42 Victoria Park Stop (Re-routed Left Turn) Northbound and southbound left turns are currently prohibited LRT Platform 43 Pharmacy Stop (U-turn) Northbound and southbound left turns from Pharmacy will be re-routed to the U-turn traffic signals shown on this panel. Motorists will proceed through the intersection, make a U-turn and then turn right similar to the U-turn routing shown on Eglinton Avenue. LRT Platform 44 Birchmount Stop (U-turn) 45 Kennedy Station 46 Traction Power Substations Traction power substations (TPS) provide system power to light rail vehicles and are planned with an average spacing of 1.5 kilometres along the surface sections and 2.0 kilometres along the underground sections. The specific locations of the traction power substations are shown in the roll-out drawing. 47 Emergency Exit Buildings An emergency exit building (EEB) is part of an emergency egress system that also includes a common stairwell vestibule between the twin tunnels, leading up to the surface level.
    [Show full text]
  • Keele Station
    Keele Station 3435 Caledonia Station 3536 Dufferin Station 36 Oakwood Station 37 Eglinton West - Allen Station 38 Bathurst Station 39 Chaplin Station 40 Avenue Station 41 Eglinton - Yonge Station 42 Mount Pleasant Station 43 Bayview Station 44 Brentcliffe Station 45 Don Mills Stop – Option 1 (Surface) Option 1 - In this option, both the Eglinton Crosstown LRT Stop and the Don Mills LRT Stop are at the surface level. Bus terminal (5 Bus Bays) Tracks connecting Don Mills Northbound / southbound LRT and Eglinton Crosstown Don Mills LRT platform LRT may be required for trains to access Maintenance Eastbound / westbound and Storage Facilities. Eglinton LRT platform Eglinton LRT LEGEND These requirements will be LRT Platform determined once the Eglinton Maintenance and Storage Crosstown LRT (Surface) Facilities sites are selected. Don Mills LRT Don Mills LRT (Surface) Ontario Science Centre Drawing not to scale. 46 Don Mills Stop – Option 1 (Surface) – Re-routed Left Turns Left turns are proposed to be re-routed in Option1 in order to achieve efficient LRT operation at the intersection of Don Mills Road and Eglinton Avenue. Refer to Panels 17a and LEGEND 17b for more information New Route for Left Turns on why re-routed left turns North to West are being considered. South to East East to North West to South Existing Traffic Signal Proposed Traffic Signal 47 Don Mills Station – Option 2 (Surface and Underground) Option 2 - In this option, the Eglinton Crosstown LRT Station is underground and the Don Mills LRT Stop is at the surface level. Bus terminal (5 Bus Bays) Tunnel portal Tracks connecting Don Mills LRT and Eglinton Crosstown Northbound / southbound LRT may be required for Don Mills LRT platform trains to access Maintenance and Storage Facilities.
    [Show full text]
  • CROSSTOWN LRT Pharmacy-Kennedy CLC Meeting May 28, 2019 East At-Grade: Pharmacy Stop to Ionview Stop East-At Grade: 2019/20 Look Ahead
    CROSSTOWN LRT Pharmacy-Kennedy CLC Meeting May 28, 2019 East At-Grade: Pharmacy Stop to Ionview Stop East-At Grade: 2019/20 Look Ahead Victoria Park to Pharmacy Avenue • Guideway work continues • Eglinton Square intersection re-opened April 8, 2019 • O’Connor Stop construction to begin mid-year Pharmacy Avenue to Warden Avenue • Boulevard work to be completed by mid year • Guideway work now underway between Pharmacy and Hakimi/Lebovic • Pharmacy guideway to be completed early June (June 8) • Hakimi/Lebovic weekend intersection traffic restrictions – June 1/2 and June 8/9 • Hakimi/Lebovic guideway intersection traffic restrictions – June 9th for 6 weeks • Traction Power Sub-Station (TPSS )11 work commenced April 17, 2019 Warden Avenue to Birchmount Road • Guideway work continues • Boulevard work to be completed by mid year • Warden Ave & Birchmount Road - intersection traffic restrictions in June Birchmount Road to Ionview Road • Work continues at Massey Creek culvert reconstruction • Rosemount - weekend intersection traffic restrictions fall 2019 • Traction Power Sub-Station (TPSS) 12 work commenced Traction Power Substations (TPSS) • Eglinton Crosstown LRT requires 12 traction power substations (TPSS) to power vehicles across the 19 km alignment. • TPSS takes power from THESL, converts it to the voltage required to run the LRT and distributes it to LRT system. • Prefab unit approximately 20 metres X 10 metres X 4 metres – Surrounded by architectural screen TPSS 11: Warden south of Eglinton near Golden Mile Stop TPSS 12: Eglinton at Birchmount near Birchmount Stop Upcoming Staging: Pharmacy to Hakimi Pharmacy Avenue intersection is expected to reopen June 8th. Guideway work zone will remain in place in the centre of Eglinton Avenue.
    [Show full text]
  • Systems & Track: What to Expect
    IT’S HAPPENING, TODAY Forum Eglinton Crosstown LRT Metrolinx’s Core Business – Providing Better, Faster, Easier Service We have a strong connection with our Adding More Service Today Making It Easier for Our customers, and a Customers to Access Our great understanding Service of who they are and Building More to Improve Service where they are going. Planning for New Connections Investing in Our Future MISSION: VISION: WE CONNECT GETTING YOU THERE COMMUNITIES BETTER, FASTER, EASIER 3 WELCOME Our Eastern Works Open House will feature the following stops and stations: • Science Centre Station • Aga Khan Park & Museum and Wynford Stop • Pharmacy and Hakimi Lebovic Stop • Golden Mile, Ionview and Birchmount Stop • Kennedy Station Read more about how Eglinton Crosstown will change Toronto’s cityscape here. Train Testing Video: Click Here Eglinton Crosstown PROJECT UPDATE • The Eglinton Crosstown project is now 70% complete • By the end of 2020, three stations – Mount Dennis, Keelesdale and Science Centre – will be largely complete • 69% of track has been installed • Vehicle testing is now underway Eglinton Crosstown What to Expect: Systems & Track 2020 Progress to-date Remaining Work in 2020 Remaining Work for 2021 • Track installed between Mount Dennis Station • Track installation between Wynford Stop to • Track installation between Fairbank Station to and Fairbank Station Sloane Stop track split and from Birchmount Laird Station, and Kennedy Station tail tracks • Track installed between East Portal Stop to Kennedy Station (excluding tail tracks)
    [Show full text]
  • Eglinton LRT Station Names
    Metrolinx Engage Report Eglinton LRT Station Names November 11, 2015 97 Front Street West 97, rue Front Ouest Toronto, Ontario M5J 1E6 Toronto (Ontario) M5J 1E6 - 2 - Contents Highlights .............................................................................................................................. 3 Methodology ......................................................................................................................... 4 Participation .......................................................................................................................... 8 Attendance ....................................................................................................................................8 Active Engagement ........................................................................................................................9 Moderation and Civility ....................................................................................................... 12 Traffic Sources ..................................................................................................................... 13 Facebook .....................................................................................................................................13 The Science Centre Member email Newsletter .............................................................................. 13 BlogTO.com ................................................................................................................................. 13 Twitter
    [Show full text]