Pharmacy to Construction Liaison Committee Meeting

Eglinton Crosstown LRT

January 26, 2021 Section Three and Four At-Grade: O’Connor Stop to Ionview Stop CONSTRUCTION ACTIVITIES

Location Activity Approx. Date & Duration

Section 3 & 4 • All shelters installed • Completed December 2020

O’Connor Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 (Victoria Park Ave) • Excavation for waiting area • Completed January 2021 Pharmacy Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021

• Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Hakimi Lebovic Stop • Excavation for waiting area • Completed January 2021

Golden Mile Stop • Formwork for guard rail • Completed January 2021 (Warden Ave) • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021

Birchmount Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021

• Fill old culvert complete • Complete Massey Creek Culvert • Build west wing wall • Ongoing through April 2021

• Formwork for guard rail • Ongoing until February 2021 Ionview Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021

3 ROSEMOUNT DRIVE AND EGLINTON AVE E Until as early as April 2021

• North side closure for Massey Creek Construction • Crews have completed filling old culvert • Crews will be completing Massey Creek culvert wingwall construction, which includes excavation, wet utilities, sidewalk reconstruction, and minor paving activities

4 CONSTRUCTION PROGRESS PHOTOS

TACTILE PLATES INSTALLED REBAR INSTALLATION FOR RAMP & FORMWORK PHARMACY STOP GOLDEN MILE STOP

5 CONSTRUCTION PROGRESS PHOTOS

REBAR INSTALLATION SHELTERS INSTALLED PHARMACY STOP IONVIEW STOP

6 Kennedy Station KENNEDY STATION UPDATE

Location Activity Approx. Date & Duration

• Conduit installation, plumbing and sheet • Ongoing through 2021 metal works, tiling, masonry works Kennedy Station Main Entrance • Elevator painting • Completed • Elevator installation and painting • Ongoing into 2021 • TPSS & TVS room electrical fit up • Ongoing through 2021 • Concrete works • Ongoing until early 2021 Kennedy Station – East of GO • Electrical and mechanical works • Ongoing until late 2021 • Wall pour • Completed • Concrete works, rebar and shoring • Ongoing until as early as May 2021 Kennedy Station Concourse Level • Floor tiling • Ongoing through 2021 Kennedy Portal (west of Kennedy • Railing installation • Ongoing until early 2021 Road) • Track works • Ongoing until early 2021 • Excavation for new east platform • Ongoing until early 2021 Kennedy Station Go Platform • Structural steel erection • Ongoing for approximately one month

8 KENNEDY CURRENT TRAFFIC CONFIGURATION December 2020 for approx. eight months

9 GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR August 17, 2020 for approx. one year

• As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year.

10 WALL POUR CONSTRUCTION PROGRESS PHOTOS GO EAST PLATFORM

GO ENTRANCE STRUCTURAL STEEL ERECTION

11 CONSTRUCTION PROGRESS PHOTOS

FLOOR TILING CONCOURSE LEVEL CEILING FRAMING MAIN ENTRANCE

12