Updated Resettlement Plan

Updated Resettlement Plan Project Number 45303-001 February 2018

CAM: Rural Energy Project

Prepared by Electricite Du Cambodge (EDC) through the Ministry of Mines and Energy (MME) of the Kingdom of , the Asian Development Bank (ADB) and the Australian Department of Foreign Affairs and Trade (DFAT).

This updated resettlement plan report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

KINGDOM OF CAMBODIA Nation Religion King

ELECTRICITÉ DU CAMBODGE

Rural Energy Project ADB Grant No. 0336-CAM (EF)

Updated Resettlement Plan (URP)

February 2018

ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of province)

Table of Contents

Page ABBREVIATIONS ...... 3 DEFINITION OF TERMS ...... 4 EXECUTIVE SUMMARY ...... 5 I. PROJECT DESCRIPTION ...... 7 II. PROJECT IMPACTS ...... 9 2.1 Introduction ...... 9 2.2 Methodology Used in Updating the Resettlement Plan ...... 9 2.2.1 Data Gathering Instrument ...... 9 2.2.2 Basic Unit Cost of Affected Assets/Trees ...... 9 2.3 Inventory of Affected Trees ...... 11 III. Socio-economic Information and Profile ...... 12 3.1 Household Background ...... 12 IV. Information Disclosure, Consultation, and Participation ...... 15 4.1 Consultation ...... 15 4.2 Disclosure ...... 16 V. GRIEVANCE REDRESS ...... 17 VI. LEGAL AND POLICY FRAMEWORK ...... 18 6.1 Cambodia Legal and Policy Framework ...... 18 6.1.1 Relevant Laws ...... 18 6.1.2 Other Relevant Regulations ...... 20 6.2 Policy Gap Analysis ...... 21 VII. PROJECT RESETTLEMENT POLICY ...... 22 7.1 Objectives ...... 22 7.2 Key Principles ...... 23 7.3 Entitlements ...... 23 VIII. COSTS AND BUDGET ...... 25 IX. ORGANIZATIONAL FRAMEWORK ...... 25 9.1 EDC/ Social, Environment and Public Relations Office (SEPRO) ...... 26 9.2 Project Implementation Consultant (PIC) ...... 26 9.3 Construction Contractor ...... 26 X. IMPLEMENTAION PROCESS AND SCHEDULE ...... 27 XI. MONITORING ...... 27

1 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of )

LIST OF TABLE Table 1: Annual Inflation of Cambodia Key Economic Indicators ...... 9 Table 2: Cost Estimation by type of Productive Tree ...... 10 Table 3: Number of Affected Trees and Budgets in 2014 and 2017 ...... 11 Table 4: Education Level in Relation to Age ...... 12 Table 5: Development in % of households with solar energy ...... 14 Table 6: Hours of household usage of electricity ...... 15 Table 7: Public Consultations were held on 22-25 Nov, 2014 and 23 December, 2017 ...... 16 Table 8: Road and Railways ROW Dimensions ...... 21 Table 9: Verification of and Comparison between Cambodian System and ADB Safeguard Policy Statement (June 2009) ...... 21 Table 10: Entitlement Matrix ...... 24 Table 11: Number of AHs and affected trees for donation/compensation ...... 25 Table 12: Indicative Schedule of Resettlement Activities ...... 27

LIST OF FIGURE Figure 1: Overview of Medium Voltage and Low Voltage Lines ...... 7 Figure 2: Project location map & the MV line routes ...... 8

ANNEXES Annex 1: Template of Negotiated Settlement Agreement ...... 28 Annex 2: Receipt prepared by consultant ...... 30 Annex 3: List of donators by commune and feeders (MV) ...... 31 Annex 4: Project Information Booklet or Information Bulletin for the project in Khmer ...... 74 Annex 5: The Consultation with AHs for additional cost of 12% of inflation rate (CPI)...... 79 Annex 6: Field pictures for house to house consultation implemented and compensation by the Contractor cooperates with EDC/SEPRO, in July and August 2017 ...... 93

2 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

ABBREVIATIONS ADB : Asian Development Bank AH : Affected Household AP : Affected Person AT : Affected Trees COI : Corridor of Impact DMS : Detailed Measurement Survey EDC : Electricité du Cambodge GDR : General Department of Resettlement GRM : Grievance Redress Mechanism HH : Household IOL : Inventory of Losses LV : Low Voltage MAFF : Ministry of Agriculture Forestry and Fisheries MEF : Ministry of Economy and Finance MV : Medium Voltage NGO : Non-Governmental Organization PIB : Public Information Booklet PIC : Project Implementation Consultants RCS : Replacement Cost Study RGC : Royal Government of Cambodia ROW : Right-of-Way REE : Rural Electricity Enterprise SEPR : Social, Environment and Public Relations Unit (within EDC) SES : Socio-economic Survey SPS : ADB’s Safeguard Policy Statement (June 2009) URP : Updated Resettlement (Assistance) Plan

CURRENCY EQUIVALENTS Currency Unit : Riel (KHR) : United States Dollar (USD) KHR 4,000.00 = USD 1.00 UNITS OF MEASUREMENTS GW - Gigawatt GWh - Gigawatt-hour Ha/ha - Hectare kg - Kilogram Km - Kilometer kV - Kilovolt kWh - Kilowatt-hour MW - Megawatt MWh - Megawatt-hour lm - Linear Meter m - Meter m² - Square Meter m³ - Cubic Meter

3 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

DEFINITION OF TERMS Affected : Refers to any person or persons, household, firm, private or public institution person (AP)/ that, on account of changes resulting from the project, will have its: Affected (i) standard of living adversely affected; household (ii) right, title or interest in any house, land (including residential, commercial, (AH) agricultural, forest and/or grazing land), water resources or any other moveable or fixed assets acquired, possessed, restricted or otherwise adversely affected, in full or in part, permanently or temporarily; and/or (iii) business, occupation, place of work or residence or habitat adversely affected, with or without displacement. In the case of AH, it includes all members residing under one roof and operating as a single economic unit, who are adversely affected by a project or any of its components. Compensation : This is payment given in cash or in kind to AHs as replacement cost for assets, resources or income acquired or adversely affected by the project Corridor of : It is the area which is required by the project or by the need to retain sites for Impact (COI) future use for construction or for repair and maintenance. Cut-off Date : This refers to the date prior to which the occupation or use of the project area makes residents/users of the same eligible to be categorized as AP. Persons not covered in the census are not eligible for compensation and other entitlements, unless they can show proof that (i) they have been inadvertently missed out during the census and inventory of losses (IOL) or (ii) they have lawfully acquired the affected assets following completion of the census and the IOL and prior to the conduct of detailed measurement survey (DMS). Entitlement : Refers to a range of measures, such as compensation for loss of affected assets and assistance to be provided to the AHs depending on the type and severity of their losses. Inventory of : This is the process where all affected trees and sources of income and Losses (IOL) livelihood inside the COI are identified, and their replacement costs calculated. Replacement : The method of valuation of assets that helps determine the amount sufficient cost to replace lost assets and cover transaction costs. In applying this method of valuation, depreciation of assets should not be taken into account. Resettlement : This is a time-bound action plan with budget, setting out the resettlement plan objectives and strategies, entitlements, activities and responsibilities, and resettlement monitoring and evaluation. ROW : ROW is the area, owned or still to be acquired, reserved for public use or for a government project. Consumer : Methodology in summary: For the compilation of the Consumer Price Index Price Index (CPI) for whole country prices are collected for a sample of 259 items price (CPI) observations are collected from the markets. In general, prices are collected from a sample of four outlets within each market. For items not offered for sale at the markets price are collected from nearby outlets.

4 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

EXECUTIVE SUMMARY 1. Rural Energy Project (Component 1: Rural Electrification of Svay Rieng Province) (hereinafter referred to as "the Project") is an AusAID funded grant and will assist the efforts of Eléctricité du Cambodge (EDC) to electrify approximately 8,000 households by extending 220 km of 22 kV medium-voltage (MV) sub-transmission line and 400 km of low-voltage (LV) distribution network in Svay Rieng Province. The development of an electricity transmission network in rural areas will displace expensive and environmentally unsustainable off-grid diesel generation by rural electricity enterprises (REEs) providing them with more cost-effective electricity supplies. The project is classified as Category B for involuntary resettlement and Category C for indigenous peoples under ADB Safeguard Policy Statement (2009). 2. Generally, a Corridor of Impact (COI) of the Project is within Right-of-Way (ROW) of the road which is classified as the state land. No physical relocation will be required, and potential impact will be limited to the installation of concrete poles using about 0.2m2 of land and the stringing of conductors requiring tree branches to be trimmed. Some trees may need to be removed in some villages and market areas. The type of productive trees identified that may require removal includes mango trees, palm trees, coconut trees and of lesser importance, tamarind trees, and so forth. The assistance in cases of removal is calculated on the basis of 5 years of production. 3. The 22 kV sub-transmission lines will be connected from grid-substations in provincial towns to the existing and new Low Voltage (LV) distribution and service lines owned and operated by private REEs. 4. EDC will own, operate and maintain the 22 kV sub-transmission lines installed under the project. The ownership and the responsibility for operating and managing the LV distribution network will remain with the respective REEs and EDC will supply electricity to REEs under a Power Purchase Agreement (PPA). 5. This Updated Resettlement Plan (URP) is prepared based on the Resettlement (Assistance) Plan which was prepared by EDC and disclosed on ADB website in August 2012, and the URP updated and approved in December 2014. 6. Due to the change of drawings and alignment, it is required that the 2014 resettlement plan has to be updated again. Its main contents include compensation policy, entitlement matrix, role & responsibility and grievance redress mechanism. During the URP preparation, a number of consultation meetings (public and house to house consultation) were also conducted to allow APs to understand about the project. 7. The resettlement policy in this URP allows compensation for affected economic tree or affected assets at replacement cost to ensure improvement, or at least maintaining their living standards and income to the level they would have without the project. 8. The compensation rates implemented are based on 2014 market price, to comply with ADB’s SPS 2009, this rates have to update based on 2017 market price. Therefore, Resettlement Expert of PIC has been mobilized to prepare this URP. Since the project already compensate to all affected households, using 2014 market rates, it is recommended that additional compensation (with 2017 rates) should be made or consultation with affected people shall carry out whether or not the affected households are still voluntary donate their trees or additional compensation is required. 9. It is agreed with EDC and SEPRO that the methodology for updating the market price for compensation rates from 2014 to 2017 is based on Cambodia consumer price index (CPI). From 2014 to 2017, the inflation rate was calculated at 12% increase1 and is used for calculation of compensation rates of affected economic trees at 2017 market price.

1 Cambodia Key Economic Indicator, ACLEDA Bank, 2017.

5 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

10. With the new rates, the resettlement expert together with EDC/SEPRO and the Contractor, on 22 – 23 December 2017 and 14-15 February 2018, conducted public consultation meeting with Local Authorities at four main communes and APs who had compensated during implementation. In addition, house to house consultation, from 5-9 February 2018, with every affected household had done by the EDC/SEPRO. The objective for these public consultations were to get their view on the differences of compensation using rates in 2014 and 2017 and if additional payment for the differences is required. 11. These consultation were carried out at Ang Tasou commune, Pouthi Reach commune, Thlok commune, and Kouk Pring commune of , Svay Rieng province where affected fruit/economic trees are cut and compensated. All affected households, were invited to joint these public consultation meeting even though they had provided thumb print during house to house consultation from 5-9 February 2018. In this significant occasion, project information was disclosed to the participants, such as 1) general civil works of the Rural Energy Project; 2) Phases of Application for connection (information in PIB); 2) the comparability of compensation rates 2014 and the new rates based on 2017 market price; and 3) Revised PIB were distributed to all participants. The rates of economic trees were updated with 12% based on the inflation rate from 2014 to 2017 (see in Table 3). 12. As the result of consultation meeting, all APs are informed about the new calculated rates and the different from previous compensation. Though the compensated rates in 2014 were slightly lower than actual market rates in 2017, people in the meeting express their willingness to participate in the project and together agreed that additional compensation for the affected trees is not required. The minutes of meeting, photos and attendant sheets are compiled in annex 5 of this URP. 13. In general, Executing Agency, EDC, of the project established a mechanism to receive and facilitate resolution of affected peoples’ concerns, complaints, and grievance about the project social and environmental performance. The grievance redress mechanism was disclosed to the villagers or affected people during public consultation meeting, house to house consultation during compensation and the recent consultation on 22-23 December 2017 and 14-15 February 2018. The GRM process is detailed in section 5 of the main report. 14. According to March 2017, based on verification process using the collected data of the 620 likely affected households, the actual number of the trees subject to compensation has been reduced from 3,619 mixed of type of trees to 1,009 fruit trees only (reduced by 72%). And the number of likely affected household has been reduced from 620 AHs to only 246 AHs (reduced by 60%). This significant reduction of number of affected tree is based on the entitlement matrix of the approved RP. 15. The implemented/compensated resettlement costs are USD 48,687.5. This amount excludes the inflation of 12% from 2014 to 2017 since additional amount (in total about US$ 5,842.50) was not claimed by affected people due to recent consultations. However, the total estimation based on 12% inflation is of the resettlement plan is USD 54,530.

6 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

I. PROJECT DESCRIPTION 1. Rural Energy Project (Component 1: Rural Electrification of Svay Rieng Province) (hereinafter referred to as "the project") is an AusAID funded grant and will assist the efforts of Eléctricité du Cambodge (EDC) to electrify approximately 8,000 households by extending 220 km of 22 kV medium-voltage (MV) sub-transmission line and 400 km of low-voltage (LV) distribution network in Svay Rieng Province. The development of an electricity transmission network in rural areas will displace expensive and environmentally unsustainable off-grid diesel generation by rural electricity enterprises (REEs) providing them with more cost-effective electricity supplies. The project is classified as Category B for involuntary resettlement and Category C for indigenous peoples under ADB Safeguard Policy Statement (2009). Generally, a Corridor of Impact (COI) of the project is within Right-of-Way (ROW) which is the state land. No physical relocation will be required, and potential impact will be limited to the installation of concrete poles using about 0.2 m2 of land and the stringing of conductors requiring tree branches to be trimmed. Dependent upon tree density and final design, some trees may need to be removed in some villages and market areas. The type of productive trees identified that may require removal includes mango trees, palm trees, coconut trees and of lesser importance, tamarind trees. The assistance in cases of removal is calculated on the basis of 5 years of production. 2. The MV lines will pass along existing roads within the existing ROW of the rural roads and will be strung from concrete poles located approximately 60m to 80m interval between each pole (see Figure 1). Any transformer required will be pole-mounted which will avoid any land requirement. During the final design of the MV lines, they will be sited to avoid houses and livelihood assets to the maximum extent possible.

Figure 1: Overview of Medium Voltage and Low Voltage Lines 3. Construction will involve mainly manual activities and will be confined to small-scale works including transporting poles to the road side, erection of poles, stringing of line conductors and erection of poles mounted transformers where required. No excavation is required other than auguring a hole for the pole footing. Removal or trimming of some roadside trees may be required to ensure appropriate safety clearances for the power lines. The blue colour lines indicated MV lines.

7 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

Figure 2: Project location map & the MV line routes

8 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

II. PROJECT IMPACTS 2.1 Introduction 4. Affected persons will, in most cases, be direct project beneficiaries as a result of receiving rural electrification. Potential resettlement impacts are not significant as they are located within existing road corridors. Further, the poles will be located to avoid disturbance to land owners and the conductors will be fixed at 10 m height resulting in a very low impact on vegetation and structures. Limited scope of construction activities involving small teams of workers, minimal use of powered mechanical equipment and insignificant excavation will further ensure minimal impacts. 2.2 Methodology Used in Updating the Resettlement Plan 5. The following sections describe the processes and methods employed in the survey on adverse social impacts for the project. The impact survey involved the conduct of IOL wherein all potential affected trees located inside the COI were identified, counted. The owners of those properties were identified, and their replacement values were also calculated. Likewise, the severity of impact on the affected assets and to the livelihood and productive capacity of AHs were determined. The impact survey of AHs was conducted in 2016 during the project implementation. 2.2.1 Data Gathering Instrument 6. The survey questionnaire was use during in the IOL with the help from Contractor (see annex 3 for voluntary donation). The questionnaire also included information of the affected assets and income, and their perception on the project. 7. The data in the URP was based on resettlement plan approved in 2014. However, the updating/identifying of affected economic trees was carried out by the Contractor as per detail engineering design and realignment of the rout line during construction. 2.2.2 Basic Unit Cost of Affected Assets/Trees 8. The RCS of affected assets in the project area was carried out in 2014 by the research team which was led by a local resettlement specialist. The main objective of the RCS is to determine the rate of productive trees for costing the resettlement plan. In compliance with ADB safeguard policy 2009, it is therefore, the unit rates of affected assets/trees need to be updated at current market price 2017. 9. The resettlement expert together with EDC/SEPRO decided that the project only compensate to those economic tree of up to five years or more. Smaller tree will not consider to be compensated as it will not affect or only branch trimming. Furthermore, it is agreed that to update the replacement cost from 2014 to 2017, Consumer Price Index (CPI) will be served to factor the change in pricing. And this new rates will be used for compensation. The below table is indicating the Consumer Price Index (CPI) from 2012 to 2017. Table 1: Annual Inflation of Cambodia Key Economic Indicators 2012 2013 2014 2015 2016e 2017f 1. GDP GDP % Change 7.3 7.4 7.1 7 7 7 Per Capita GDP (in U.S. Dollar) 973 1,043 1,138 1,215 1,300 1,422 2. Inflation Inflation (Annual Average) 2.9 3 3.9 1.2 2.8 3.7 (End Year) 2.5 4.6 1.1 2.6 - - 3. Government Budget (as a percent of GDP) Revenue 16.9 18.4 17.5 18.9 17.9 18.2 Expenditure 20.7 20.5 21.55 20.9 22.8 23.1

9 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 2012 2013 2014 2015 2016e 2017f 4. Money and Credit (12 months percentage change) M2 20.9 14.6 29.9 14.7 20.8 - Total Deposits in the Banking System 24.9 13.8 30.1 16.4 20 - Total Outstanding Loans in the Banking 35.1 25.2 16.2 25.7 18 - System Loan as % of Deposit 86.8 98 94 102.6 101.7 - Private Sector Credit 28 26.7 31.3 27.1 21.6 - Deposits to GDP 47.3 49 53 61.9 67.8 - Loans to GDP 41 49.8 50 63.5 69 - 5. Balance of Payments (US$ million) Exports 6,015.70 6,530 7,408e 8,208.80 9,017.70 9,936.70 - - - Imports -8,426 -9,744 -10,542 10,991e 11,449.60 12,559.30 - Trade Balance -2,967 -3,214 -3,583e -2,431.90 -2,219.10 2,333.20 - Current Account (excluding official transfers) -1,835 -2,171 -2,356e -2,029.10 -2,219.10 1,908.40 Nominal GDP (Billions of U.S Dollars) 14.1 15.35 16.91 18.08 20.09 22.21 Exchange Rate (Riel per Dollar end period) 4,033 4,027 4,038 4,060 4,050 4,050

Source: https://www.acledabank.com.kh/kh/eng/fi_keyecoindicator

10. From the CPI table, the inflation during 4 years’ time from 2014 to 2017 is calculated at 12% increase. Below is the comparison of compensation rate from 2014 and 2017. Table 2: Cost Estimation by type of Productive Tree

Total Yield per year Cost of CPI Year for Unit Price Seedling (Inflation No. Description Unit Qty Compen- Cost USD USD USD/ Rate, Total Sation USD in 2014 Unit Qty / Unit 2017) USD Unit 1 Coconut Tree 1 Fruit 30 0.25 7.50 0.5 5 7.50 38.0 42.56 2 Tamarind Tree 1 Lump Sum 5.50 0.5 6 5.50 33.5 37.52 3 Phyllanthus/Kantuot Tree 1 Lump Sum 3.00 0.5 3 3.00 9.5 10.64 4 Deum Chan Tree 1 Lump Sum 5.00 0.5 5 5 25.5 28.56 5 Kamping Reach Tree 1 Fruit 250 0.03 7.50 0.5 4 7.50 30.5 34.16 Elephane 6 Tree 1 Fruit 100 0.08 8.00 0.5 4 8.00 32.5 36.4 apple/Khveet 7 Jackfruit Tree 1 Fruit 5 2.00 10.00 0.5 4 10.00 40.5 45.36 8 Sour fruit/Krasaing Tree 1 Fruit 200 0.03 6.00 0.5 4 6.00 24.5 27.44 Jambolan 9 Tree 1 Kg 40 0.15 6.00 0.5 5 6.00 30.5 34.16 plum/Pring 10 Hog plum/Mkak Tree 1 Kg 24 0.25 6.00 0.5 5 6.00 30.5 34.16 Deum Mean 11 Tree 1 Kg 10 1.50 15.00 0.5 4 15.00 60.5 67.76 (longan) 12 Sorghum/Sdau Tree 1 bunch 20 0.50 10.00 0.5 3 10.00 30.5 34.16 13 Pomelo/Grapefruit Tree 1 Fruit 15 0.50 7.50 0.5 4 7.50 30.5 34.16 14 Milk fruit/Teuk Dos Tree 1 Fruit 100 0.10 10.00 0.5 5 10.00 50.5 56.56 15 Mango Tree 1 Lump Sum 10.00 1.0 5 10.00 51.0 57.12 16 Sugar Palm Tree 1 Kg 20 0.40 8.00 0.5 8 8.0 64.5 72.24

10 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

Total Yield per year Cost of CPI Year for Unit Price Seedling (Inflation No. Description Unit Qty Compen- Cost USD USD USD/ Rate, Total Sation USD in 2014 Unit Qty / Unit 2017) USD Unit 17 Rubber Tree 1 Lump Sum 5.00 1.0 4 5.00 21.0 23.52 18 Areca palm/Sla tree 1 dozen 40 0.20 8.00 1.0 3 8.00 25.0 28 19 Other tree Tree 1 Lump Sum 10.0 11.2

Data source: The calculation of the supplementary income changes commodity price, Dec. 2017

2.3 Inventory of Affected Trees 11. During IOL, a total of 620 households will be affected with 3,619 productive trees. However, the actual number of the trees subject to compensation can be smaller than 3,619 because (i) the contractors will finalize the detailed alignments minimizing the negative impact to the extent possible, (ii) some of the counted trees might not contribute to the affected persons (APs)’ livelihood, and (iii) some of the counted trees do not need to be cut but just trimmed slightly. There is no any physical displacement2 and affected private land. 12. However as of March 2017, based on verification process using the collected data of the 620 likely affected households, the actual number of the trees subject to compensation has been reduced from 3,619 mixed of type of trees to 1,009 fruit trees only (reduced by 72%). And the number of likely affected household has been reduced from 620 AHs to only 246 AHs (reduced by 60%). This significant reduction of number of affected tree is based on the entitlement matrix of the approved RP. 13. Below is the table of affected tree and the cost in 2014 and 2017 (increase inflation rate of 12%) for comparison.

Table 3: Number of Affected Trees and Budgets in 2014 and 2017 Total # of affected trees CPI Unit Cost in 2014 compensation Type of trees for (Inflation Rate) (USD) cost in 2014 implementation in 2017 (USD) Palm Tree 344 65 22,188.00 24,850.56 Tamarind 30 34 1,005.00 1,125.60 Coconut 102 38 3,876.00 4,341.12 Jambolan 19 31 579.5 649.04 Ampil Toek 8 10 80 89.60 Mango 316 51 16,116.00 18,049.92 Cashew 55 10 550 616.00 Kapok 5 10 50 56.00 Krasang 6 25 147 164.64 Rose apple - 33 - - Wood Apple 38 33 1,235.00 1,383.20 Jackfriut 45 41 1,822.50 2,041.20 Jujube - 35 - - Semaon 18 10 180 201.60 Guava 6 10 60 67.20

2 Physical displacement relocation, loss of residential land, or loss of shelter as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

11 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Total # of affected trees CPI Unit Cost in 2014 compensation Type of trees for (Inflation Rate) (USD) cost in 2014 implementation in 2017 (USD) Milkfruit 14 51 707 791.84 Kamping Reach 3 31 91.5 102.48 Total 1,009 48,687.50 54,530.00

III. Socio-economic Information and Profile 14. Since the project carried out Social Impact Assessment (SIA) in February 2017, this information is now used in this section of socio-economic profile for the project in this URP. 15. From SIA, the total of 150 affected households are interviewed. Of which 100 households as treatment group (within the project area) and 50 households as control group (out of project area). Below is the information adapted from SIA. 3.1 Household Background 3.1.1 Civil Status 16. In 75% of the households is the couple married. The remaining 25% is in most cases widow (34 of 37) and some were divorced. The widows and divorcees were all female except one. None of the households belong to a minority group. 3.1.2 Age and disability 17. The average age of the family head is 53 years. The typical household has five members of which 53% is female. In 22% are household members aged below 17, while 12% is above 61 years of age. At six households was a member with a disability. Three of them were blind while others had a mute boy, mental sick boy and lame daughter. 3.1.3 Education 18. Most of the heads (68%) and their wives (75%) have primary school as highest formal education. Illiteracy is found considerably more with both wives and widowed or divorced female heads. There is a clear relation with the education level versus the average age. Younger generations had more (access to) education. Table 4: Education Level in Relation to Age Education level in relation to age Male head Female head Female (wife or head) Education Age Age Age Number in % Number in % Number in % (average) (average) (average) Illiterate 3 3% 74 11 30% 56 25 17% not asked Primary school 76 67% 54 21 57% 56 111 75% not asked Secondary school 21 19% 44 2 5% 55 6 4% not asked High school 13 12% 43 3 8% 49 6 4% not asked Total 113 100% 52 37 100% 56 148 100%

3.1.4 Living Conditions 19. The majority of the households (74%) live on paved roads in good condition. The remaining 26% have unpaved road in front of their homes. The condition of unpaved roads varies. Also due to some parts of the visited districts were flooding during the last wet season. It is remarkable that 82% of the unpaved roads were in treatment villages. 20. All households own the house they live in. The data regarding housing materials was influenced by the selection criteria. The reason for this is that focusing on housing

12 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) materials helps the team to quickly identify candidates for the interviews and is often a good indicator of the relative social class of the household. In 53% do households live in houses with wooden or concrete walls in combination with a titled roof. The remainder has houses of cheaper materials like zinc and thatched walls and or roofs.

3.1.5 Social Economical Information 21. Income: Based on the Social Impact Assessment indicates that the income in the yearly or monthly income is not easy to calculate as family members get income from several separate activities (see figure below) and often do not have a regular monthly income or any administration. Most of the households make their income from agriculture-related activities, of which the profit depends on inputs or activities bounded to self-sufficiency, labour costs, harvest seasons and weather conditions. Nearly all households are involved in rice cultivation (99%), however just 29% makes an income with rice farming followed by animal husbandry of pigs, cow or chicken as foremost agricultural activities. A significant number households receive from contributions from often migrated (within Cambodia or abroad) family members. The reported average annual income is nearly $ 1,600 or about $ 5 per day, but this is without those family contributions. The majority (89%) of the households have monthly income while others are dependent on seasonal or harvest related income alone. For 42% of the households is the income not sufficient to cover the expenses. Loans are taken at $ 2,000 on average and savings, $ 560 on average are reported at respectively 29% and 18% of the households.

22. Animal holdings: Compared to 2015 is a downwards trend noticeable for large animal categories as cows, buffaloes and pigs. In total were animal holdings decreased by 26%. In 2017 does a household own 3 large animals on average. The strongest decline (57%) is seen with buffaloes as small tractors (ko-yun) are quickly changing the local scenery. The small tractor is owned by 19% of the households. Many households have some chicken and ducks at their house, but none of them raise them in large numbers. 23. Energy for cooking: Traditional stoves with fuel wood are very common in the project area with 87% of the households using this as primary cooking fuel. Due to the wide availability of wood is this wood usually gathered for free. LPG is the secondary cooking fuel with some households (6%) using it as primary source, but mostly is LPG the secondary source for special occasions in 27% of the households. Biogas, dried dung (typical for the area) and charcoal are used at the remaining households. Besides family cooking at all households are water boiling (67%) and animal food preparation (25%) the other purposes for the cooking fuel. Only 29% of the households have costs related to cooking. These costs are almost exclusive to LPG and are on average $ 53 per year or about one dollar per week. 24. Energy for electricity: A major finding in the baseline survey was the mix of electricity sources found in the project area. Solar energy is by far the most used primary source of electricity in the project area with 89% of the interviewed households while the traditionally used (car) batteries were used at only 8% of the households. This energy mix in the project area near the Vietnamese border is quite unique compared to many off

13 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) grid areas where car batteries and to lesser extend local grids often outpace solar energy due to barriers as upfront investment costs and trust issues. SEAC5 and industry insiders, contacted by the consultant, mentioned that solar energy adoption rates of this considerable scale is unique in Cambodia. Contacted village chiefs however confirm the data and point to the money that migrated family members to Thailand and Korea bring in to support their families.

Table 5: Development in % of households with solar energy

25. The average reported solar home system has 110wp capacity. At least that is the system size the household assumes to have as in the past cases are known in rural areas with untrustworthy vendors who cheat with the system size specifications. It is however not checked whether this was the case at any of the households in the survey. In 88% are the systems between 51-150-watt peak and often did this include an energy efficient LCD/LED TV.

26. Electrical appliances: A remarkable number of 62% of the households have a modern energy efficient LCD/LED television in their homes while another 8% consider buying a LCD/LED television. This significant adoption rate can be explained due to the solar home systems kits that often comes with LCD/LED television that 97% of those households have. Households have the plan or desire to buy kitchen related appliances as a refrigerator, rice cooker and also electric stoves. Water cookers are not mentioned despite 67% of the households reported frequent water boiling. Water pumps for better irrigation of rice fields is another planned purchase that could potentially double or triple the rice harvest. The follow-up survey will give insight if the planned purchases also were materialized.

14 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

27. The households estimated the average time per day that they use their electronic appliances (see table below). This data will be compared with their replies in the future follow-up survey. Table 6: Hours of household usage of electricity

IV. Information Disclosure, Consultation, and Participation 4.1 Consultation 28. Public Consultations were arranged by EDC during the study of RP, in four different places among the seventeen (17) communes which were affected areas. The aim of the public consultation is to disclose the project to the community and discuss resettlement issues due to the project activities. During that time, awareness of Grievance Redress Mechanism (GRM) was disseminated to all APs as well. 29. The first meeting of public consultation was conducted on November 24th, 2014 (at 9:30 am) for the two communes: 1) Chan Trea, and 2) Thmey in Chantrea Commune, Chan Trea district. During implementation, the consultation has been carried out from house to house with the help from the Contractor during settlement negotiation of the affected economic trees. Annex 6 is the pictures of house to house consultation implemented by the Contractor. Below is the summary of consultation for the project. 30. However, the following meeting was prepared on December 23, 2017 at 8:30 AM in Ang Tasou Commune Centre at Ang Tasou commune, the two villages, namely: Cheng Meng and Roka villages were invited to join this meeting. The participants came from 2 villages, with a total of 40 persons, 21 are women. The minutes of meeting and attendance lists is shown in Annex 5.

15 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Table 7: Public Consultations Meeting with AHs Date & Time Commune Meeting Place Participant

- Chan Trea Male=17 24 Nov. 2014 (9:30am) Chan Trea - Thmey Female=8 - Thlok - Angk Ta Sou Male=40 24 Nov.2014 (14:00pm) - Svay Angk Roka pagoda Female=5 - Svay Yeay - Doun Sar - Thmea - Chantrei Male=21 24 Nov. 2014 (16:00pm) - Mream Mukh Da Female=3 - Mukh Da - Trapeang Sdau - Prey Chek - Sangkhoar Male=35 28 Feb.2014 (14:00PM) - Chek Chek Female=13 - Pouthi Reach - Svay Chek Angk Ta Sou Male=19 23 Dec. 2017 (08:30am) - Angk Ta Sou Commune Centre Female=21

Male=9 14 Feb. 2018 (08:30am) - Porthi Reach Ou Samdei village Female=10

Male=5 14 Feb. 2018 (14:00pm) - Thlok Thlok village Female=15

Male=2 15 Feb. 2018 (08:30am) - Kouk Pring Doun Leab village Female=12

31. Topic discussed in the last meeting are: 1) Brief information about the project and costs/benefits to economic development of the country; 2) Explanation of the GRM; 3) Explained the Replacement Cost Study that conducted; 4) Different of compensation rates in 2014 and the updated rates in 2017 5) Phases of Application Submission; 6) Connection fee, the deposit cost, and electricity usage fee (in PIB); and 7) Distribution of PIB; 8) Agreement of no additional compensation with the updated rates in 2017.

4.2 Disclosure 32. The public consultation meetings conducted in the project areas since the feasibility study in 2014 because of at that time the national individual consultant did not mobilize yet. However, during implementation in 2016 – 2017, house to house consultation was carried out by the Contractor. In addition, during this updated RP consultations had conducted on 23 December 2017 and 14-15 February 2018 to disclosed the project situation, presented information on the project design, expected timing, scope of impacts, eligibility, entitlements, and the grievance redress mechanism. An information booklet in (please see in Annex 4 for the final the project information booklet in Khmer).

16 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

V. GRIEVANCE REDRESS 33. The project (Grant:0336) has established a grievance redress mechanism (GRM) and this project will also provide a well-defined grievance redress and resolution mechanism to resolve grievances and complaints in a timely and satisfactory manner. All affected persons will be made fully aware of their rights, and if households change their minds (donation of affected trees), it will be a priority task for the implementation team (especially for contractor) to resolve complaints as quickly as possible and at the local level through a process of conciliation; and, if that is not possible, to provide clear and transparent procedures for appeal. The community will be provided the details of the implementation grievance redress procedure as an added safety valve. 34. A grievance redress committee (GRC) will be established at provincial level with a process starting from Commune Offices. As practiced, the GRC include the relevant local commune or village chiefs and where needed, a local NGO may assist the affected persons in filing complaints, particularly for those who are illiterate, do not know how to prepare written complaints, and ethnic minority who have language difficulties. The designated commune officials shall exercise all efforts to settle complaints and issues at the commune level through appropriate community consultation. All meetings shall be recorded in each grievance process and copies shall be provided to the affected persons. A copy of the minutes of meetings and actions undertaken shall be provided to EDC and ADB upon request. 35. The grievance redress procedures set out as below: 36. Stage 1: Affected person/household (AP) will submit a letter of complaint/request to the village or commune office (a copy may be submitted to the provincial resettlement sub- committee (PRSC). The Commune Office will be obliged to provide immediate written confirmation of receiving the complaint. If, after 15 days, the aggrieved AP does not hear from the village or commune, or if the AP is not satisfied with the decision taken by in the commune office, the complaint may be brought to the district office. 37. Stage 2: The district office has 15 days within which to resolve the complaint to the satisfaction of all concerned. If the complaints cannot be resolved in this stage, the district office will bring the case to the Provincial Grievance Redress Committee. 38. Stage 3: The Provincial Grievance Redress Committee meets with the aggrieved party and tries to resolve the complaint. The Committee may ask for a review of the detail measurement survey (DMS). Within 30 days of the submission of the grievance, the Committee must make a written decision and submit a copy of the same the AP. 39. Stage 4: Court Procedures. If the aggrieved AP does not hear from the Provincial Grievance Redress Committee or is not satisfied with the proposed solution, the AP can bring the case to the Provincial Court. The Court will make a written decision and send copies to the AP and to provincial GRC. If any party is still unsatisfied with the Provincial Court’s judgment, the party can refer the case to a higher level court. 40. In cases where APs do not have the writing skills or are unable to express their grievances verbally, it is a common practice that APs are allowed to seek assistance from any recognized local NGO or other family members, village heads or community chiefs to have their complaints or grievances written for them. Aps will be allowed to have access to the DMS or contract document to ensure that all the details have been recorded accurately enabling all parties to be treated fairly. Throughout the grievance redress process, the responsible committee will ensure that the concerned APs are provided with copies of complaints and decisions or resolutions reached. 41. If efforts to resolve disputes using the grievance procedures remain unresolved or unsatisfactory, APs have the right to directly discuss their concerns or problems with the ADB’s Environment, Natural Resources and Agriculture Division, Southeast Asia Department through the ADB Cambodia Resident Mission (CARM). If APs are still not

17 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) satisfied with the responses of CARM, they can directly contact the ADB Office of the Special Project Facilitator. The Office of the Special Project Facilitator procedure can proceed based on the accountability mechanism in parallel with the project implementation.

VI. LEGAL AND POLICY FRAMEWORK 42. Cambodia has experienced severe social, economic, and political turmoil during the last quarter century. Before the Khmer Rouge came to power in 1975, private land ownership was widespread and governed by the Cambodia Civil Code of 1920. Under the Khmer Rouge from 1975 to 1979 however, private property was abolished and all records were destroyed. After the said regime, the new government introduced usufruct rights to facilitate orderly occupation by people returning to urban areas, of vacant land and structures. However, all lands in Cambodia remained under the property of the state until private ownership on residential land of maximum 2,000m2 was restored in 1989. The current legislations governing land ownership is the Land Laws of October 1992 and of August 2001, which recognize claims to land made after the downfall of the Khmer Rouge in 1979. There is no specific government policy relating to the details of resettlement and compensation in Cambodia, other than general requirements for compensation to be provided. Therefore, compromise between relevant Cambodian laws and development partner policies is necessary in terms of dealing with resettlement issues caused by development projects. 6.1 Cambodia Legal and Policy Framework 6.1.1 Relevant Laws (a) 1993 Constitution 43. The 1993 Constitution of Cambodia has established one governing principle in Article 44 pertaining to land acquisition.  Article 44 states that “All persons, individually or collectively, shall have the right to ownership. Only Khmer legal entities and citizens of Khmer nationality shall have the right to own land. Legal private ownership shall be protected by law. The right to confiscate properties from any persons shall be exercised only in the public interest as provided for under the law and shall require fair and just compensation in advance.” (b) Land Law 44. The rights to land and property in Cambodia are governed by the 2001 Land Law, which are primarily based on the provisions of the 1993 Constitution. The law defines the scope of ownership of immovable properties, such as land, trees and fixed structures. 45. The Land Law, Article 5, states that “No person may be deprived of his ownership, unless it is in the public interest. Any ownership deprivation shall be carried out in accordance with the governing procedures provided by law and regulations, and after the payment of fair and just compensation in advance.” 46. Other provisions of the Land Law that are relevant to land acquisition, compensation and resettlement include:  Only legal possession as provided by law can be transformed to land ownership. (Article 6)  Any regime of ownership of immovable property prior to 1979 shall not be recognized. (Article 7)  Article 15 states that “the following properties are included as public properties of state and public legal entities: a) any property that has a natural origin, such as forests, courses and banks of navigable and floatable rivers or natural lakes and seashores; b) that is made available for public use such as quays of harbors, port, railways, railways station and airports; or, c) any property which is made available, either in its natural state or after

18 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) development, for public use such as roads, tracks, oxcart ways, pathways, gardens or public parks and reserved lands.”  Article 18 states that "the following are null and void and cannot be made legal in any form whatever: a) any entering into possession of public properties of State and public legal entities and any transformation of possession of private properties of State into ownership rights that was not pursuant to the legal formalities and procedures that have been stipulated prior to that time, irrespective of the date of creation of possession or transformation; e) any entering into possession of private properties of State, through any means, that occurs after this law comes into effect".  Article 19 states that “any persons whose land title or factual circumstance fall within the scope of article 18 of this law shall not have the right to claim compensation or reimbursement of expenses paid for the maintenance or management of immovable property that was illegally occupied. Any illegal and intentional of fraudulent acquisition of public properties of state or of public legal entities shall be penalized pursuant to article 259 of this law. The penalties shall be doubled where any occupation of public properties because damages or delay to works undertaken in the general interest, especially the occupation of roadway reversed land".  Ownership of immovable properties described in Article 25 is granted by the state to indigenous minorities3 as collective ownership. This collective ownership includes all of the rights and protections as enjoyed by private owners. The exercise of collective ownership rights shall be subject to the responsibility of the traditional authorities and decision-making mechanisms of the indigenous community, according to their customs and subject to the laws of general enforcement related to immovable property such as the law on environmental protection. (Article 26)  Persons with legally valid possession of land for five years (at the time the law came into effect) are allowed to be registered as the owner of the land (Article 30). Persons who (at the time the law came into effect) held legal possession but had not yet completed the five years were allowed to remain in possession until they were eligible to be registered as the owner. (Article 31)  Any beginning of occupation for possession shall cease when this law comes into effect (article 29). After this law comes into force, any new occupant with title to an immovable property belonging to the public bodies or private persons shall be considered as illegal occupant and shall be subject to the penalties provided in Article 259 of this Law (Articles 34).  Article 38 states that "in order to transform into ownership of immovable property, the possession shall be unambiguous, non-violent, and notorious to the public, continuous and in good faith".  Landless people may apply for land for residential and subsistence farming purposes at no cost, as part of a social land concessions scheme. The concessionaire may obtain ownership of this land after fulfilling conditions set out in a separate Sub-Decree on Social Land Concessions. (Articles 50, 51). (c) Expropriation Law Dec. February 2010 - procedures for acquiring private properties for national or public interest  Article 2: the law has the following purposes: (i) ensure reasonable and just deprivation of a legal right to ownership of private property; (ii) ensure payment of reasonable and just prior compensation; (iii) serve the public and national interests; and (iv) development of public physical infrastructure.

3 As per Article 23 of the Land Law, “An indigenous community is a group of people that resides in Cambodia whose members manifest ethnic, social, cultural and economic unity and who practice a traditional lifestyle, and who cultivate the lands in their possession according to the customary rules of collective use.”

19 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)  Article 7: Only the state may carry out an expropriation for use in the public and national interests.  Article 8: The state shall accept the purchase of the remaining part of the real property left over from an expropriation at a reasonable and just price at the request of the owner of land/or the holder of rights in the expropriated real property, if he is no longer able to live near the expropriated scheme or build a residence or conduct any business.  Article 16 states that “Prior to make any expropriation project proposal, the Expropriation Committee shall conduct a public survey by recording of a detailed description of all entitlements of the owners and/or of the holder of real right to immovable property and other properties subject to compensation as well as recording of all relevant issues.” 47. In conducting the survey, the Expropriation Committee shall organize public consultations at the Capital, Municipal-Provincial, and District-Khan authority levels with Commune/Sangkat councils and Village or community representative to be affected by the expropriation to provide specific and concise information and collect inputs from all stakeholders regarding the proposed basic public infrastructure project. 48. In order to set a dateline for the expropriation or relocation or compensation, the Expropriation Committee shall conduct a dateline interview with all concerned parties about the issues of immovable property to be affected by the public physical infrastructure project. 49. Within 30 (thirty) working days after the completion of the survey, the Expropriation Committee shall produce a report with recommendations and submits it to the Royal Government for approval.” 50. Article 22: Stipulates the amount of compensation to be paid to the owner of and/or holder of rights in the real property, which is based on the market value of the real property or the replacement cost as of the date of the issuance of the Prakas on the expropriation scheme. The market value or the replacement cost shall be determined by an independent commission or agent appointed by the expropriation committee. 6.1.2 Other Relevant Regulations 51. The private ownership of land was re-established in 1989, and confirmed in the 2001 Land Law (Article 4). Cambodians are able to register the land they occupy with the local Cadastral Administration Office, whereupon a certificate of land title is granted. Issuing land titles is a lengthy process and most offices have a major backlog of applications. People are given a receipt and until the official title deed is issued, this receipt is accepted as a proof of real occupant of the land for land purpose or sale. 52. The present legal status of land use in Cambodia can be classified as follows: (i) Privately owned land with title: The owner has official title to land, and both owner and the Cadastral Administration Office have a copy of the deed. (ii) Privately owned land without title: The owner has made an application for title to land, and is waiting for the issuance of a title deed. The Cadastral Administration Office recognizes the owner. (iii) Land use rights certified by the Government: In this case, a receipt for long-term land use has been issued. This land use right is recognized by the Cadastral Administration Office. (iv) Lease land: The Government or private owners lease the land, usually for a short period. There is provision for the owner to reclaim land if it is needed for development. (v) Non-legal occupation: The user has no land use rights to State land that he occupies or uses. The Cadastral Administration Office does not recognize the use of this land. 53. Sub-Decree on Social Land Concession, March 2003 - provides for allocations of free private state land to landless people of residential or family farming, including the replacement of land lost in the context of involuntary resettlement. 54. Prakas No.6, entitled “Measures to Crack Down on Anarchic Land Grabbing and Encroachments”, sets ROW for road and railway. In support of this Prakas, Ministry of

20 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Economy and Finance (MEF) on 6 April 2000 issued Decree No.961 prohibiting compensation for structures and other assets located in the ROWs. Some Road dimensions are modified by the Sub-Decree No.197 adopted on 23 November 2009 on to Management of ROW along the national road and railway in Cambodia.

Table 8: Road and Railways ROW Dimensions ROW Dimensions under ROW Dimensions under Road Category Prakas No.06 Sub-decree No.197 NR-1, 4, and 5 30 m from the centreline 30 m from the centreline Other 1-digit NRs 25 m from the centreline 30 m from the centreline 2-digit NRs 25 m from the centreline 25 m from the centreline Provincial roads 20 m from the centreline not specified Commune roads 15 m from the centreline not specified Railway outside city, 30 m from the centreline 30 m from the centreline province and crowned place Railways in forest area 100 m from the centreline 100 m from the centreline Source: MPWT 30a. MEF Circular No.006 on the Resettlement Implementation Procedure for development projects dated on April 2nd, 2014. This new circular instructed clearly the administrative management and role and responsibility of all relevant Implementing Agency and Provinces in implementing the resettlement for development project. 6.2 Policy Gap Analysis 55. Law and regulation framework on resettlement and land issues are still in the stage of development in Cambodia, and some implementation documents and institutions are not yet prepared completely, however, RGC understands such situation and the SPS, and considers supplemental measures and assistance in URP on a case by case. 56. Thus, in terms of practical operation, there is not so much crucial gap between Cambodian country system and the SPS’s concept and requirements (see Table 2-2). Some other discussing points which are not mentioned clearly or concretely in Cambodian country system are also considered based on the SPS, this URP, and other relevant documents to fulfil gaps.

Table 9: Verification of and Comparison between Cambodian System and ADB Safeguard Policy Statement (June 2009) Law/Regulation in Actual Operation Policy No. Item ADB Safeguard Cambodia (officially (Gap Filling

Statement promulgated ) Measures) Support system It is necessary to give Sub-Decree on Social Income restoration for socially appropriate Land Concession program and vulnerable consideration to provides allocations of assistance groups vulnerable groups. free private state land to (allowance) to landless people of vulnerable groups 1 residential or family will be prepared, farming, including the depending on the replacement of land lost resettlement in the context of impact. involuntary resettlement. Assistance to Living standards and The government has no Income restoration restore and income opportunities, clear policy or program will be improve living and production levels of procedure to restore the prepared , 2 standards project affected people livelihood of APs. depending on the should be improved or resettlement at least restored to pre- impact. project levels.

21 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Law/Regulation in Actual Operation Policy No. Item ADB Safeguard Cambodia (officially (Gap Filling

Statement promulgated ) Measures) Enhancement Appropriate participation It is clearly declared in Public consultation of public of APs and their the Expropriation Law meetings and participation in communities should be (Article 16) that in interview of AHs planning and promoted in planning, conducting a survey of shall be conducted implementation implementation and entitlements, public at appropriate of resettlement monitoring of consultations shall be stages according plan involuntary AHs and organized to provide to the SPS and the measures taken against specific and concise Expropriation Law. 3 the loss of their means information and collect of livelihood. inputs from all stakeholders regarding the proposed basic public infrastructure project and that a dateline interview with all concerned parties shall be conducted. Compensation Prior compensation will The amount of Negotiated for land be done with compensation to be settlements, or acquisition with replacement cost, which paid to the owner of when negotiated replacement means that and/or holder of real settlement is cost compensation for lost right to the immovable unavoidable, assets must be made in property shall be based compensation at 4 full amount at on the market price or replacement cost, replacement cost and at replacement cost as of will be applied. current market price. the date of the issuance of the declaration on the expropriation project. (the Expropriation Law (Article 22)) AHs residing in People to be resettled Under the Land Law Assistance to AHs the project involuntarily and those 2001, those who have who are residing in affected area whose means of occupied ROW or the project affected before cut-off livelihood will be public property are not area (including date hindered or lost should entitled to any public state land) 5 be sufficiently compensation or social at the time of cut- compensated and support. off date will be supported by the project prepared . proponents in appropriate time. Grievance Grievance redress Grievance redress Grievance redress redress system must be system is stipulated in system will be mechanism formulated and must the Expropriation Law; formulated. 6 function appropriately. however, it has provisions to exclude public infrastructure projects.

VII. PROJECT RESETTLEMENT POLICY 7.1 Objectives 57. The project’s resettlement and assistance policies are to be in accordance with Cambodian law as well as the SPS. 58. The URP aims to ensure that the losses incurred by APs are redressed such that APs share project benefits and are not worse off than they would have been without the project.

22 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 7.2 Key Principles 59. A key area of difference in relation to the comparison between Cambodian Law and the requirements of the SPS is that MEF Decision no. 961 requires that RGC will not spend national budget to make payments for structures or other items located on the RGC claimed rights of way, i.e. ROW for roads and railroads. The requirements of Cambodian Law and ADB policy are in contrast on this point as ADB’s policy requires that anybody who experiences a loss of an asset or income source as a result of an ADB funded project will receive full and fair assistance for that loss, regardless of title. 60. In seeking ADB funding, RGC and EDC agree to comply with the core safeguard principles of ADB, as summarized below: (i) Negotiated settlements based on meaningful consultation with APs, including those without legal title to assets offering a fair price for land and/or other assets will be the key approach adopted by the project. EDC will ensure that any negotiations with displaced persons openly address the risks of asymmetry of information and bargaining power of the parties. (ii) When involuntary resettlement is unavoidable, the responsibility rests with the borrower country to follow the Bank’s policies. Where there is conflict with the Borrower’s policies and laws, the ADB policies shall be applied, as per the URP. The URP is viewed as a legal commitment in this regard. (iii) In principle, poll installation and conductor stringing will be done within the existing ROW and not require acquisition of private land, but it may request the donation of crops, trees and other structures. (iv) Non-titled APs, including displaced tenants, sharecroppers and squatters, are entitled to various options of resettlement assistance, provided they cultivated/occupied the land prior to the eligibility cut-off date. Resettlement assistance to non-titled APs may also include replacement land, although there is no entitlement to this. The resettlement package may include measures to ensure that such APs are able to find alternative sites or income sources, depending on their losses. (v) For non-land assets, all eligible APs, whether titled, legalizable or non- titled, must be provided assistance at replacement cost, through cash or replacement assets.

7.3 Entitlements 61. Anticipated impacts are minimal and restricted primarily to the removal of trees which may be used for livelihood purposes and possibly impacts on informal crops. It is not expected that businesses will be affected nor that acquisition of private land will be required, however to ensure completeness of the URP, these eventualities are addressed and provision established for assistance. 62. Economic trees that yield fruits every year or season are eligible for assistance if APs can demonstrate that the trees contribute to their livelihood. If reliance cannot be demonstrated, or if the community leadership cannot confirm the use of the tree by a particular AP, then assistance will not be paid. Commercial trees that have only one-time value, basically trees for timber and naturally grown, will not be compensated because AH can sell it at present market value when tree is cut. 63. The entitlements adopted were guided by the applicable national laws and regulations and the SPS. Negotiated settlements based on meaningful consultation with APs, including those without legal title to assets offering a fair price for land and/or other assets will be the key approach adopted by the project. EDC will ensure that any negotiations with displaced persons openly address the risks of asymmetry of information and bargaining power of the parties. Full and fair information has to be provided to the APs (including disclosure of what would be a fair replacement cost), and all negotiations need to be overseen by the Project Implementation Consultant (PIC).

23 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Table 10 below outlines the entitlements for APs where negotiated settlements cannot be reached:

24 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Table 10: Entitlement Matrix Eligible Type Of Loss Entitlements Implementation Issues Persons A. Removable of Trees/crops Persons who The clearance fee . AHs to be notified at least 7 days in Trees located immediately in can will be full advance before the start of civil works front of the AP’s residence demonstrate replacement cost where the land will be utilized by the and where the AP can that based on market project. demonstrate that the tree trees/crops value including . Ahs can voluntarily donate the contributes to their income contributes recurring production affected trees contribute to the and livelihood. to their for a period of five project without income and years without assistance/compensation. Crops located immediately in livelihood deduction for . Those who opt for donation of the front of the AP’s residence salvageable affected tree, it is required to sign the such as informal paddy, materials. VCF as attached in this URP. vegetable gardens, fruit . Annual Crops AHs will be given 7 bearing shrubs and other – days crops which contribute to ’ notice that the land on which their crops are planted will be used income and livelihood. by the project and that they must If reliance cannot be harvest their crops before the civil demonstrated, or if the work. community leadership cannot . If crops cannot be harvested due to confirm the use of the construction schedule, AHs are tree/crops by a particular AP, entitled to cash compensation for the then assistance will not be affected crops at replacement cost. paid. . Remaining ROW is still public state land. B. Removable of structures such as shops

Only where permanent Owner/renter Relocation of . AHs to be notified at least 15 days in removal required (this is of the shop structure or advance before the start of civil works considered to be unlikely as assistance in where the land will be utilized by the the MV/LV conductors will relocating (and project. maintain a safe distance from reconstructing) the . AHs to get cash compensation at shops and other structures) shop in a location least 10 days ahead of civil works in agreed by the locality to allow the AHs sufficient community time to gradually reorganize the leadership. house and/or shop, thereby avoiding any disruption in their livelihood. . AHs must completely cut, move back or relocate their structures to new site within 7 days after receiving compensation. . If the structure is found no longer viable for living, compensation will be paid for the entire structure. C. Permanent land acquisition

In the unlikely event that Owner of the Acquisition of the . AHs to be notified at least 15 days in poles need to be located on affected affected land at full advance before the start of civil works private land. private land replacement cost. in the locality of the actual date that the land will be utilized by the project. . EDC will ensure payment of all compensation for which AHs are entitled to at least 10 days prior to the scheduled start of civil works. Note: The civil work can commence before the implementation of the URP in the areas where there is no resettlement impact.

25 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) VIII. COSTS AND BUDGET 64. As of March 2017, 246 households with 1009 productive trees are affected by the project and the actual compensation amount was USD 48,687.5. However, based on the updated rates at 2017 market price, the total budget of updated resettlement plan is USD 54,530.00 (based on inflation rate increasing of 12% in 2017). According to public consultation at field on 22-23 December 2017 and 14-15 February 2018 and house to house consultation from 5-9 February 2018, all affected households opted for no additional compensation. 65. Below is the cost estimation comparison of resettlement budget. Table 11: Number of AHs and affected trees for donation/compensation No of affected CPI No of AHs for trees for (Inflation District Commune donation/comp Amount (USD) donation/compe Rate, ensation nsation 2017) Kampong 12 47 2,698.5 3,022.32 Ampil Romduol Meun Chey 2 49 6 161 183.0 8,361.5 204.96 Svay Chek 7 25 1,221.0 1,367.52 Thmea 28 83 4,259.0 4,770.08 Angk Prasrae 5 11 484.0 542.08 Chantrei 4 29 1,525.5 1,708.56 Doung 40 159 7,020.0 7,862.40 Romeas Kampong 16 122 77 3,695.0 24,972.0 4,138.40 Haek Trach 505 Mream 21 79 3,966.0 4,441.92 Mukh Da 5 20 914.0 1,023.68 Trapeang 31 130 7,367.5 8,251.60 Sdau Angk Tasou 4 28 362.0 405.44 Basak 7 21 1,314.5 1,472.24 Chheu Teal 7 36 2,176.0 2,437.12 Doun Sa 2 6 163.0 182.56 Svay Kouk Pring 13 45 2,371.0 2,655.52 69 13,672.5 Chrum Kruos 3 15 291 725.5 812.56 Pouthi Reach 3 9 427.5 478.80 Svay Angk 1 2 129.0 144.48 Svay Yea 19 98 4,604.5 5,157.04 Thlok 10 31 1,399.5 1,567.44 Svay Rieng Chek 2 2 6 6 306.0 306.0 342.72 Svay Teab Sambuor 4 4 46 46 1,375.5 1,375.5 1,540.56 5 23 246 1,009 48,687.5 54,530.00

It is noted that the resettlement implementation budget was only USD 48,687.50 since additional budget for affected trees (5,842.50) were not claimed as per recent consultation with affected people.

IX. ORGANIZATIONAL FRAMEWORK 66. The owner of the project is the Executing Agency (EA) which is EDC; therefore, it has overall responsibility for the successful implementation of the URP. This chapter presents a brief summary to illustrate the role and responsibility of various institutions and organizations dedicated to resettlement implementation.

26 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 9.1 EDC/ Social, Environment and Public Relations Office (SEPRO) 67. EDC through its SEPRO is responsible for resettlement operations and management of the project. To achieve this, EDC will:  Implement this URP as approved; the Contractor cooperates with EDC/SEPRO for house to house consultation and compensation to affected households.  Act as internal monitor to supervise the activities regarding social impacts of the project including: (i) Documentation of impacts and benefits including recording and photographs of assets to avoid potential later grievances. (ii) Informing the communities APs of their rights under the URP (iii) Collect information from the APs to determine level of AP satisfaction (iv) Ensure all assistance is provided to AHs before any physical impact is created.

9.2 Project Implementation Consultant (PIC) 68. One national social safeguard specialist (PIC) engages to support EDC with the preparation and implementation of social safeguard measures. The PIC helps build capacity in EDC in relation to resettlement and compensation (assistance); ensure effective and timely implementation of resettlement activities. The PIC will work with EDC, the Contractor and local authorities to ensure the URP is implemented so that the requirements of the SPS are satisfied. 69. The PIC will identify, and propose solutions to, safeguards related project risks and assist with regular reporting to ADB. Where negotiated settlements are achieved with APs, the PIC will prepare a report of the negotiation and settlement processes which documents that: (i) full and fair information was provided to the APs (including disclosure of what would be a fair replacement cost); (ii) the Project is not severely affected to the living standards of APs; (iii) the project is linked directly to benefits for the AH; (iv) any negotiated settlement will be confirmed through written record; (v) there is an adequate grievance process; and (vi) no AH will be displaced from housing. A template, which collect and report on information to demonstrate that negotiations with displaced persons openly address the risks of asymmetry of information and bargaining power of the parties to ensure both parties are adequately protected, has been prepared (see Appendix 1: Template of Negotiated Settlement Agreement). 9.3 Construction Contractor 70. The key role of the construction contractor under this URP is to ensure the design and alignments of the MV/LV lines have the least possible impact on livelihoods and assets including resettlement assistance (in contract agreement). The contractor will be required to work with the PIC to ensure the optimal design and construction methodologies to minimize impacts are adopted. The contractor will also liaise with the PIC to ensure APs are well informed and compensated prior to any impacts.

27 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) X. IMPLEMENTAION PROCESS AND SCHEDULE 71. EDC will be responsible for the implementation of the URP and social issues with support from PIC. In addition, EDC will be responsible for ensuring that the funds for the assistance are available in a timely manner. The URP will be implemented before civil works in any given geographic area. 72. The following activities will be undertaken during project implementation to ensure compliance with this URP and the SPS: (i) During spotting of the pole footprints, contractor, village/commune/district leaders, EDC, and PIC will confirm potential losses and negotiate acquisition from APs based on meaningful consultations; (ii) EDC will implement the URP prior to any civil work; (iii) Assistance for those who may experience livelihood loss or loss of private land/assets will be delivered by EDC before the impact is created; (iv) EDC will retain evidence that such assistance was provided and the APs agreed; (v) The PIC will conduct spot checks on this process including verification of negotiated settlements.

Table 12: Indicative Schedule of Resettlement Activities ACTIVITIES SCHEDULE ADB Approval of URP Q1 2016 ~ Q2 2017 Mobilization of PIC Q1 2016 Mobilization of Contractor Q1 2016 Implementation of the Approved URP Q1 2016 ~ Q2 2017 - Negotiation and contract making process Q1 2016 ~ Q2 2017 - Compensation payment process Q1 2016 ~ Q2 2017 - Consultation on inflation amount 12% to affected 23 December 2017 productive trees - Consultation on inflation amount 12% to affected 22-23 December 2017 and 14-15 Feb. productive trees 2018 Start of Civil Works* Q1 2016 Internal Monitoring (Submission of Quarterly Progress Q1 2016 ~ Q2 2017 Reports) PIC Monitoring (Intermittent) Q1 2016 ~ Q2 2017 * For sections where there are no resettlement impacts.

XI. MONITORING 73. The central role of monitoring activities will be to ensure that all compensation payments/arrangements including any negotiated settlements are based on meaningful consultation with affected persons, including those without legal title to assets. A negotiated settlement will offer adequate and fair price for trees and/or other assets. 74. The PIC will document the negotiation and settlement processes. Once the resettlement activities start, quarterly (every three months) monitoring reports will be prepared by EDC assisted by PIC, and submitted to ADB. Based on ADB’s Public Communication Policy (PCP 2011), these will be uploaded to the ADB website as received.

28 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Annex 1: Template of Negotiated Settlement Agreement

29 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

30 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Annex 2: Receipt prepared by consultant

31 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Annex 3: List of donators by commune and feeders (MV) Additional # of Comp. Amount Feeder Name of donator Village Commune District Tree Cost (Inflation Rate 12%) S01-S02 Kem Nary/ Sokhoeun Chhuk Sa Chheu Teal Svay Chrum 8 516 61.92 S01-S02 Soam Seap/Kemly Chhuk Sa Chheu Teal Svay Chrum 4 258 30.96 S01-S02 Ngoun Yean/Saream Chhuk Sa Chheu Teal Svay Chrum 2 129 15.48 S01-S02 In Kimleng Chhuk Sa Chheu Teal Svay Chrum 13 838.5 100.62 S01-S02 Ouk Sameth Chhuk Sa Chheu Teal Svay Chrum 3 133 15.96 S01-S02 Yin Sam OL/Sokhary Chhuk Sa Chheu Teal Svay Chrum 1 64.5 7.74 S01-S02 Sim Thae/ Thavy Chhuk Sa Chheu Teal Svay Chrum 5 237 28.44 S69-S70 Pich Ry Doun Leaeb Kouk Pring Svay Chrum 5 295.5 35.46 S69-S70 Roth Dan/ Phapath Doun Leaeb Kouk Pring Svay Chrum 5 255 30.6 S69-S70 Mey Sarom/ Yoem Doun Leaeb Kouk Pring Svay Chrum 3 153 18.36 S69-S70 Chou Vanna/ Kunthea Doun Leaeb Kouk Pring Svay Chrum 3 71 8.52 S69-S70 Sin Sam Arth Doun Leaeb Kouk Pring Svay Chrum 1 51 6.12 Chheoun Sovann/Sam S69-S70 Orn Doun Leaeb Kouk Pring Svay Chrum 1 10 1.2 S69-S70 Hem Sanith/Nary Doun Leaeb Kouk Pring Svay Chrum 2 102 12.24 Prak Ponareay/Sam S69-S70 Arth Doun Leaeb Kouk Pring Svay Chrum 4 231 27.72 S69-S70 Prom Sanha/Sokha Doun Leaeb Kouk Pring Svay Chrum 1 38 4.56 S69-S70 Nhoem Sarith/Vanna Doun Leaeb Kouk Pring Svay Chrum 6 319.5 38.34 S69-S70 Kim Samedy/Srey Neth Doun Leaeb Kouk Pring Svay Chrum 3 162.5 19.5 S69-S70 Touch Soy/Phen Doun Leaeb Kouk Pring Svay Chrum 2 102 12.24 S69-S70 Sot Sarin/Sam Oeurn Doun Leaeb Kouk Pring Svay Chrum 9 580.5 69.66 S17-S18 Prach Im/Sam Phors Roka Angk Tasou Svay Chrum 2 102 12.24 S17-S18 Ourn Samouern Roka Angk Tasou Svay Chrum 4 40 4.8 S17-S18 Khorng Horn Roka Angk Tasou Svay Chrum 12 120 14.4 S17-S18 Som Sok Roka Angk Tasou Svay Chrum 10 100 12 S01-S02 Roth Nov/Soun Lvea Kruos Svay Chrum 7 330.5 39.66 S01-S02 Neang Sean Lvea Kruos Svay Chrum 3 99 11.88 S01-S02 Puth Khorn/Map Lvea Kruos Svay Chrum 5 296 35.52 S41-41 Thim Sineth Svay Ph'aem Svay Angk Svay Chrum 2 129 15.48 S52-S53 Som Sok Damnak Kantuot Svay Yea Svay Chrum 3 153 18.36 S52-S53 Soam Oung Damnak Kantuot Svay Yea Svay Chrum 20 1020 122.4 S17-S18 Sum Pon Svay Yea Svay Yea Svay Chrum 2 102 12.24 S17-S18 Phoeun Pheakdei Robaoh Pring Svay Yea Svay Chrum 1 51 6.12 S17-S18 Thoang Nhem Kien Ta Siv Svay Yea Svay Chrum 2 102 12.24 S17-S18 Yann Channy Kien Ta Siv Svay Yea Svay Chrum 3 180 21.6 S17-S18 Kong Vann Kien Ta Siv Svay Yea Svay Chrum 9 336 40.32 S17-S18 Mao Run Kbal Damrei Svay Yea Svay Chrum 2 89 10.68 S17-S18 Chhim Hol Kbal Damrei Svay Yea Svay Chrum 9 509.5 61.14 S17-S18 Siv Sarun Kbal Damrei Svay Yea Svay Chrum 1 51 6.12 S17-S18 Sor Savun Kbal Damrei Svay Yea Svay Chrum 2 89 10.68 S17-S18 Soun Sina Kbal Damrei Svay Yea Svay Chrum 1 51 6.12

32 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

S17-S18 Long Yoeun Kbal Damrei Svay Yea Svay Chrum 3 114 13.68 S17-S18 Keo Morn Kbal Damrei Svay Yea Svay Chrum 9 459 55.08 S17-S18 Mei Sarourn Kbal Damrei Svay Yea Svay Chrum 10 365 43.8 S17-S18 Pen Cheoun Kbal Damrei Svay Yea Svay Chrum 2 89 10.68 S17-S18 Sor Teal Kbal Damrei Svay Yea Svay Chrum 4 163 19.56 S52-S53 Kong Vuth Prey Ph'ong Svay Yea Svay Chrum 4 193.5 23.22 S52-S53 Hong Samith Prey Ph'ong Svay Yea Svay Chrum 11 487.5 58.5 S33-S34 Soam Sopha Ou Samdei Pouthi Reach Svay Chrum 2 61 7.32 S33-S34 Chou Tha Ou Samdei Pouthi Reach Svay Chrum 5 296 35.52 S33-S34 Chan Son Ou Samdei Pouthi Reach Svay Chrum 2 70.5 8.46 S33-S34 Som Kim San Tey Yea Thlok Svay Chrum 2 98 11.76 S33-S34 Hun Sarath Tey Yea Thlok Svay Chrum 4 132 15.84 S33-S34 Prak Sarun Tey Yea Thlok Svay Chrum 3 161.5 19.38 S33-S34 Im Som Oun Thlok Thlok Svay Chrum 1 32.5 3.9 S33-S34 Khiev Tha Thlok Thlok Svay Chrum 5 162.5 19.5 S33-S34 Yeay Khun Thlok Thlok Svay Chrum 2 97 11.64 S33-S34 Srey Sam Arth Thlok Thlok Svay Chrum 8 453 54.36 S33-S34 Mom Maphavy Thlok Thlok Svay Chrum 2 129 15.48 S33-S34 Sok Ya Thlok Thlok Svay Chrum 2 67 8.04 S33-S34 Leang Samaen Thlok Thlok Svay Chrum 2 67 8.04 S37-S38 En Sam An Doung Preah Doun Sa Svay Chrum 2 65 7.8 S37-S38 Prak Phalla Doung Preah Doun Sa Svay Chrum 4 98 11.76 S58-S59 Som Sarot Basak Basak Svay Chrum 1 64.5 7.74 S58-S59 So Ny Basak Basak Svay Chrum 5 322.5 38.7 S58-S59 Soa Somkhan Basak Basak Svay Chrum 4 258 30.96 S58-S59 Sin Samy Basak Basak Svay Chrum 2 115.5 13.86 S58-S59 Mey Set Basak Basak Svay Chrum 5 322.5 38.7 S58-S59 Som Samal Basak Basak Svay Chrum 2 102.5 12.3 S58-S59 Soum Srey Basak Basak Svay Chrum 2 129 15.48 S73-S74 Sdoerng Kunthea Sambuor Sambuor Svay Teab 2 129 15.48 S73-S74 Pich Sarith Sambuor Sambuor Svay Teab 7 357 42.84 S73-S74 Chea Sovannara Sambuor Sambuor Svay Teab 32 607 72.84 S73-S74 Prom Thea Sambuor Sambuor Svay Teab 5 282.5 33.9 S31-S32 Ros Thy Chek Chek Svay Rieng 2 102 12.24 S31-S32 Kang Sotheany Chek Chek Svay Rieng 4 204 24.48 S13-S14 Phann Thorn Thmei Svay Chek Romduol 5 290.5 34.86 S13-S14 Hay Pao Thmei Svay Chek Romduol 2 67 8.04 S13-S14 Mom Marina Thmei Svay Chek Romduol 1 32.5 3.9 S13-S14 Pen Noun Svay Chek Svay Chek Romduol 5 322.5 38.7 S13-S14 Pen Sokly Svay Chek Svay Chek Romduol 4 204.5 24.54 S13-S14 En Roeun Svay Chek Svay Chek Romduol 3 114 13.68 S13-S14 Pen Samorn Svay Chek Svay Chek Romduol 5 190 22.8 S05-S06 In Mao Prey Pou Thmea Romduol 1 38 4.56 S05-S06 Horm Ratana Prey Pou Thmea Romduol 2 89 10.68

33 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

S05-S06 Sin Bath Prey Pou Thmea Romduol 2 129 15.48 S05-S06 Ung Chhorn Prey Pou Thmea Romduol 2 129 15.48 S05-S06 Mom Han Prey Pou Thmea Romduol 2 115.5 13.86 S05-S06 Choun Choeun Prey Pou Thmea Romduol 3 140.5 16.86 S05-S06 Sek Chhum Prey Pou Thmea Romduol 1 64.5 7.74 S05-S06 En Sarun Prey Pou Thmea Romduol 1 51 6.12 S05-S06 Mao Yon Thmea Thmea Romduol 2 65 7.8 S05-S06 Kong Moeun Thmea Thmea Romduol 5 194.5 23.34 S05-S06 Khoun Chhan Thmea Thmea Romduol 4 258 30.96 S05-S06 Ngoek Chhoam Thmea Thmea Romduol 3 131.5 15.78 S05-S06 Voang Thlang Thmea Thmea Romduol 5 322.5 38.7 S05-S06 Mei Kim Hean Boeng Kaek Thmea Romduol 4 258 30.96 S05-S06 Preap Un Boeng Kaek Thmea Romduol 1 33.5 4.02 S05-S06 Thoa Saboun Boeng Kaek Thmea Romduol 5 322.5 38.7 S05-S06 Chan Rorn Boeng Kaek Thmea Romduol 6 355 42.6 S05-S06 Prom Son Un Pongro Thmea Romduol 2 50.5 6.06 S05-S06 Lay Sok Pongro Thmea Romduol 3 153 18.36 S05-S06 En Phean Pongro Thmea Romduol 2 76 9.12 S05-S06 Sim Chhang Pongro Thmea Romduol 8 468 56.16 S05-S06 Preab Oun Pongro Thmea Romduol 5 241.5 28.98 S05-S06 Touch Bunthoeun Trapeang Poun Thmea Romduol 2 115.5 13.86 S05-S06 Som Saphon Trapeang Poun Thmea Romduol 3 153 18.36 S05-S06 Phouk Sambath Trapeang Poun Thmea Romduol 2 129 15.48 S05-S06 Nhoem Sao Trapeang Poun Thmea Romduol 2 102 12.24 S05-S06 Kuy Try Preaek Tnaot Thmea Romduol 2 43.5 5.22 S05-S06 Nhem Sam An Preaek Tnaot Thmea Romduol 3 30 3.6 S13-S14 Ouk Chhour Trach Totueng Meun Chey Romduol 3 153 18.36 S13-S14 Pin Sa Oeurn Ta Kheng Meun Chey Romduol 3 30 3.6 S05-S06 Chea Sophap Kampong Ampil Kampong Ampil Romduol 2 129 15.48 S05-S06 Khat Vibol Kampong Ampil Kampong Ampil Romduol 5 322.5 38.7 S05-S06 Ros Than Kampong Ampil Kampong Ampil Romduol 1 64.5 7.74 S05-S06 Nhoek Phon Ta Tae Kampong Ampil Romduol 1 38 4.56 S05-S06 Keo Phal Ta Tae Kampong Ampil Romduol 4 258 30.96 S05-S06 Chhim Sopheap Ta Tae Kampong Ampil Romduol 8 396 47.52 S05-S06 Tout Chan Ra Ta Tae Kampong Ampil Romduol 2 102 12.24 S05-S06 Mao Kea Ta Tae Kampong Ampil Romduol 8 516 61.92 S05-S06 Kang San Ta Tae Kampong Ampil Romduol 7 424.5 50.94 S05-S06 Sok Saban Ta Tae Kampong Ampil Romduol 3 193.5 23.22 S05-S06 Tourt Saphat Ta Tae Kampong Ampil Romduol 2 76 9.12 S05-S06 Kang Saveth Ta Tae Kampong Ampil Romduol 4 178.5 21.42 S45-S46 Mao Hornn Svay Pok Doung Romeas Haek 3 30 3.6 S45-S46 Mom Choun Svay Pok Doung Romeas Haek 6 60 7.2 S45-S46 Touch Sornn Svay Pok Doung Romeas Haek 1 64.5 7.74 S45-S46 So San Svay Pok Doung Romeas Haek 1 51 6.12

34 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

S45-S46 Mom Voeurn Svay Pok Doung Romeas Haek 1 33.5 4.02 S45-S46 Voir Saveth Svay Pok Doung Romeas Haek 1 64.5 7.74 S45-S46 Sok Khoeurn Svay Pok Doung Romeas Haek 7 323.5 38.82 S45-S46 Sok Samsot Kranhung Doung Romeas Haek 3 30 3.6 S45-S46 Pao Oun Kranhung Doung Romeas Haek 2 20 2.4 S45-S46 Phorngk Kosal Kranhung Doung Romeas Haek 3 30 3.6 S45-S46 Keo Neang Kranhung Doung Romeas Haek 3 153 18.36 S45-S46 Meas Ry Kranhung Doung Romeas Haek 2 20 2.4 S45-S46 Mom Seath Kranhung Doung Romeas Haek 6 224 26.88 S45-S46 Pen Soeurn Thlok Pring Doung Romeas Haek 10 471.5 56.58 S45-S46 Ouk Sarom Chea Theach Doung Romeas Haek 8 369 44.28 S45-S46 Toa Hoeurn Chea Theach Doung Romeas Haek 4 172.5 20.7 S50-S51 Pin Nay Poun Doung Romeas Haek 6 334 40.08 S50-S51 Put Phalla Poun Doung Romeas Haek 5 296 35.52 S50-S51 Preap Chhae Poun Doung Romeas Haek 5 223.5 26.82 S50-S51 Ouk Soen Poun Doung Romeas Haek 6 346.5 41.58 S50-S51 Siv Chhorn Poun Doung Romeas Haek 2 76 9.12 S50-S51 Sok Soeur Poun Doung Romeas Haek 3 153 18.36 S50-S51 En Neang Poun Doung Romeas Haek 10 456 54.72 S50-S51 Moeng Rith Poun Doung Romeas Haek 10 559.5 67.14 S50-S51 Prom Som Oeurn Poun Doung Romeas Haek 3 112 13.44 S50-S51 Mak Sakhom Poun Doung Romeas Haek 3 127 15.24 S50-S51 Kuch Savorn Poun Doung Romeas Haek 4 204 24.48 S50-S51 So Chaem Doung Doung Romeas Haek 12 559.5 67.14 S50-S51 Toek Phoeurn Doung Doung Romeas Haek 4 205 24.6 S50-S51 Oum Saban Doung Doung Romeas Haek 1 38 4.56 S50-S51 Moeng Mey Doung Doung Romeas Haek 2 81 9.72 S50-S51 Ty Sarorn Doung Doung Romeas Haek 2 50.5 6.06 S50-S51 Ty Sarun Doung Doung Romeas Haek 2 88.5 10.62 S50-S51 Sek San Doung Doung Romeas Haek 2 81 9.72 S50-S51 Long Yoeurn Ta Suos Doung Romeas Haek 6 387 46.44 S50-S51 Sok Sarorn Ta Suos Doung Romeas Haek 2 115.5 13.86 S50-S51 Keo Thorn Ta Suos Doung Romeas Haek 1 38 4.56 S50-S51 Pen Chen Ta Suos Doung Romeas Haek 3 193.5 23.22 S50-S51 Pao Sean Ta Suos Doung Romeas Haek 2 76 9.12 S50-S51 Vong Sarath Ta Suos Doung Romeas Haek 2 102 12.24 S29-S30 Keo Sinath Trapeang Pring Angk Prasrae Romeas Haek 4 152 18.24 S29-S30 Keo Syna Trapeang Pring Angk Prasrae Romeas Haek 1 38 4.56 S29-S30 Srey So Trapeang Pring Angk Prasrae Romeas Haek 3 127 15.24 S29-S30 Puth Sakhut Trapeang Pring Angk Prasrae Romeas Haek 1 38 4.56 S29-S30 Som Phan Trapeang Pring Angk Prasrae Romeas Haek 2 129 15.48 S33-S34 Hourt Samnang Mukh Da Mukh Da Romeas Haek 8 363.5 43.62 S33-S34 Loek Sarorn Mukh Da Mukh Da Romeas Haek 2 76 9.12 S33-S34 Chhoem Sam Un Mukh Da Mukh Da Romeas Haek 3 114 13.68

35 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

S33-S34 Chhon Som Oeurn Mukh Da Mukh Da Romeas Haek 3 193.5 23.22 S33-S34 Ros Sarorn Mukh Da Mukh Da Romeas Haek 4 167 20.04 S45-S46 Kong Noy Ta Khob Kampong Trach Romeas Haek 2 102 12.24 S45-S46 Som Sarouen Ta Trav Kampong Trach Romeas Haek 6 306.5 36.78 S45-S46 Has Sakhorn Ta Trav Kampong Trach Romeas Haek 5 294.5 35.34 S45-S46 Keo Chanra Ta Trav Kampong Trach Romeas Haek 5 267.5 32.1 S45-S46 Ken Saven Ta Trav Kampong Trach Romeas Haek 4 175 21 S45-S46 Ouk Lourk Ta Trav Kampong Trach Romeas Haek 5 255 30.6 S45-S46 Ouk Vichet Ta Trav Kampong Trach Romeas Haek 5 208 24.96 S45-S46 Prom Phann Ta Trav Kampong Trach Romeas Haek 7 315 37.8 S45-S46 Voir Long Ta Trav Kampong Trach Romeas Haek 4 177 21.24 S45-S46 Oum Son Ta Trav Kampong Trach Romeas Haek 3 151.5 18.18 S45-S46 Mey Sophal Ta Trav Kampong Trach Romeas Haek 2 81 9.72 S45-S46 Pen Chamroern Ta Trav Kampong Trach Romeas Haek 9 413.5 49.62 S45-S46 Mom Pong Ry Ta Trav Kampong Trach Romeas Haek 9 457.5 54.9 S45-S46 Mom Phan Ta Trav Kampong Trach Romeas Haek 7 301.5 36.18 S45-S46 oum Samouern Ta Trav Kampong Trach Romeas Haek 1 50.5 6.06 S45-S46 Voir Vanny Ta Trav Kampong Trach Romeas Haek 3 139 16.68 S60-61, 62-63-64 Bhal Sokkhorn Knorng Chouk Keart Trapeang Sdau Romeas Haek 1 32.5 3.9 S60-61, 62-63-64 Khoung Sarouern Knorng Chouk Keart Trapeang Sdau Romeas Haek 2 20 2.4 S60-61, 62-63-64 Khol Vanna Knorng Chouk Keart Trapeang Sdau Romeas Haek 3 91.5 10.98 S60-61, 62-63-64 Meas Moa Ta Kot Trapeang Sdau Romeas Haek 3 193.5 23.22 S60-61, 62-63-64 Prom Khea Ta Kot Trapeang Sdau Romeas Haek 1 10 1.2 S60-61, 62-63-64 La Borin Ta Kot Trapeang Sdau Romeas Haek 1 51 6.12 S60-61, 62-63-64 Sor Lak Knorng Chouk Lech Trapeang Sdau Romeas Haek 2 61 7.32 S60-61, 62-63-64 Prom Samorn Knorng Chouk Lech Trapeang Sdau Romeas Haek 1 51 6.12 S60-61, 62-63-64 Torch houern Knorng Chouk Lech Trapeang Sdau Romeas Haek 4 258 30.96 S60-61, 62-63-64 Porch Samay Knorng Chouk Lech Trapeang Sdau Romeas Haek 1 64.5 7.74 S60-61, 62-63-64 Yoem Somhouern Knorng Chouk Lech Trapeang Sdau Romeas Haek 1 64.5 7.74 S60-61, 62-63-64 Chen Heatt Knorng Chouk Lech Trapeang Sdau Romeas Haek 2 102.5 12.3 S60-61, 62-63-64 Rous Ren Knorng Chouk Lech Trapeang Sdau Romeas Haek 5 243 29.16 S60-61, 62-63-64 Brak Nak Svay Tor Teum Trapeang Sdau Romeas Haek 5 243 29.16 S60-61, 62-63-64 Yorng Sourn Svay Tor Teum Trapeang Sdau Romeas Haek 4 258 30.96 S60-61, 62-63-64 Moa Sokha Svay Tor Teum Trapeang Sdau Romeas Haek 3 193.5 23.22 S60-61, 62-63-64 Chan Torn Svay Tor Teum Trapeang Sdau Romeas Haek 10 645 77.4 S60-61, 62-63-64 Serng Savi Svay Tor Teum Trapeang Sdau Romeas Haek 4 258 30.96 S60-61, 62-63-64 Mey Seny Svay Tor Teum Trapeang Sdau Romeas Haek 5 322.5 38.7 S60-61, 62-63-64 Keov Phorl Svay Tor Teum Trapeang Sdau Romeas Haek 1 33.5 4.02 S60-61, 62-63-64 Pouv Toch Bonla shet Trapeang Sdau Romeas Haek 9 580.5 69.66 S60-61, 62-63-64 Keov Pouv Bonla shet Trapeang Sdau Romeas Haek 1 32.5 3.9 S60-61, 62-63-64 Keov Vanna Bonla shet Trapeang Sdau Romeas Haek 7 327.5 39.3 S60-61, 62-63-64 Keov Sitha Bonla shet Trapeang Sdau Romeas Haek 5 322.5 38.7 S60-61, 62-63-64 Ouk Samorn Bonla shet Trapeang Sdau Romeas Haek 5 255 30.6 S60-61, 62-63-64 Ouk Bonly Bonla shet Trapeang Sdau Romeas Haek 9 580.5 69.66

36 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

S60-61, 62-63-64 Chan Dara Bonla shet Trapeang Sdau Romeas Haek 12 774 92.88 S60-61, 62-63-64 O Moern Bonla shet Trapeang Sdau Romeas Haek 4 132 15.84 S60-61, 62-63-64 Soum Dam Bonla shet Trapeang Sdau Romeas Haek 2 102 12.24 S60-61, 62-63-64 Mao Choj Bonla shet Trapeang Sdau Romeas Haek 1 32.5 3.9 S60-61, 62-63-64 Soum Norn Bonla shet Trapeang Sdau Romeas Haek 16 1032 123.84 S03-04, S54-55 Chak Sokhanra Lbaeuk Mream Romeas Haek 2 115.5 13.86 S03-04, S54-55 Un Samean Lbaeuk Mream Romeas Haek 1 38 4.56 S03-04, S54-55 Un E Lbaeuk Mream Romeas Haek 4 178 21.36 S03-04, S54-55 Hong Seat Lbaeuk Mream Romeas Haek 1 51 6.12 S03-04, S54-55 Ouk Sum Lbaeuk Mream Romeas Haek 1 38 4.56 S03-04, S54-55 Mey Sophea Lbaeuk Mream Romeas Haek 4 204 24.48 S03-04, S54-55 Chan Sok Lbaeuk Mream Romeas Haek 6 306 36.72 S03-04, S54-55 Ouk Sarourn Lbaeuk Mream Romeas Haek 4 204 24.48 S03-04, S54-55 Nav Kheng Lbaeuk Mream Romeas Haek 4 204 24.48 S03-04, S54-55 Loek Soy Lbaeuk Mream Romeas Haek 6 293 35.16 S03-04, S54-55 Preap Horn Lbaeuk Mream Romeas Haek 6 306 36.72 S03-04, S54-55 Prom Song Lbaeuk Mream Romeas Haek 9 446 53.52 S03-04, S54-55 Sim Oun Lbaeuk Mream Romeas Haek 1 64.5 7.74 S03-04, S54-55 Heng Nol Lbaeuk Mream Romeas Haek 3 153 18.36 S03-04, S54-55 Sin Chea Lbaeuk Mream Romeas Haek 10 510 61.2 S03-04, S54-55 Sok Than Tbaeng Mream Romeas Haek 2 129 15.48 S03-04, S54-55 Khan Sarin Tbaeng Mream Romeas Haek 7 357 42.84 S03-04, S54-55 Tith Sokha Tbaeng Mream Romeas Haek 2 102 12.24 S03-04, S54-55 Keo Phoeurn Tbaeng Mream Romeas Haek 1 51 6.12 S03-04, S54-55 Preap Chey Tbaeng Mream Romeas Haek 3 114 13.68 S03-04, S54-55 Im Saroeun Tbaeng Mream Romeas Haek 2 102 12.24 S03-04, 15-16 En Koek Samla Chhau Chantrei Romeas Haek 4 183 21.96 S03-04, 15-16 Tep Pheang Samla Chhau Chantrei Romeas Haek 1 51 6.12 S03-04, 15-16 Meas Saroeur Trapeang Run Ti Pir Chantrei Romeas Haek 21 1138.5 136.62 S03-04, 15-16 Ung Lay Trapeang Run Ti Pir Chantrei Romeas Haek 3 153 18.36 Total 246 50 23 5 1,009 48,687.50 5,842.50

37 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

75.

38 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

39 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

40 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

41 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

42 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

43 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

44 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

45 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

46 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

47 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

48 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

49 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

50 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

51 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

52 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

53 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

54 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

55 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

56 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

57 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

58 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

59 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

60 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

61 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

62 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

63 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

64 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

65 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

66 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

67 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

68 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

69 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

70 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

71 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

72 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

73 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

74 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Annex 4: Project Information Booklet or Information Bulletin for the project in Khmer

្រាាា្ររ្ាព ាត ិ ាសា ្រះមា្ស្ត

អ្គ រ ្ាព

្្្ោអ្គជ

្្ោ្ជ រ ្ញា្េខ ០៣៣៦ រ ាារអភវ ្ឍា (ADB Grant No. 0336 - CAM)

រ ្ៀវ្ៅរត័ ោ ្្្ោ

ʒʐʑʗ

75

ELECTRICITÉ DU CAMBODGE Medium-Voltage Sub-Transmission

Expansion Sector Project, Package 1

Appendix 2: Project Information Booklet (English Draft Version)

ELECTRICITÉ DU CAMBODGE Medium-Voltage Sub-Transmission

Expansion Sector Project, Package 1

ELECTRICITÉ DU CAMBODGE

ADB Grant No.0336

PUBLIC INFORMATION BOOKLET

1. QUESTION: What is the rural electrification project?

ANSWER: The project is a rural energy project sub-transmission expansion sector project of Medium Voltage and Low Voltage, Which will expand the electricity sub-transmission infrastructure by constructing about 8,000 household in 5 districts and 1 city at Svay Rieng province.

Distribution route maps of AP’s province revised after site survey by PIC/EDC are

Attached hereinafter.

2. QUESTION: Will the sub-transmission line affect us?

ANSWER: The design and construction of the sub-transmission line will attempt to avoid or at least minimize the negative impacts on the communities. Generally, the sub-transmission line will be constructed within the right-of-way of existing roads which is the state land. The potential impact will be limited to the installation of concrete poles using about 0.2 m² of land and the stringing of conductors requiring tree branches to be trimmed. Some trees may need to be removed in some villages and market areas.

The actual alignment will be determined during detailed design through consultation with you and the rest of the local communities. After the detailed design, the area that will be affected by the Project will be marked on the ground and trees will be marked so you, as project affected persons (APs), will know that your asset will be affected.

3. QUESTION: Does compensation apply to my affected trees?

ANSWER: Yes. The affected trees will be compensated. The contractors of the project will discuss the compensation rate with you. In addition to the compensation, you can take the cutting tree to use for other purposes.

4. QUESTION: Does that mean any affected trees can claim for compensation? Page 2 (Appendix 2)

ELECTRICITÉ DU CAMBODGE Medium-Voltage Sub-Transmission

Expansion Sector Project, Package 1 ANSWER: No. Only if APs can demonstrate that the trees contribute to their livelihood, the economic trees that yield fruits every year or season are eligible for assistance. If reliance cannot be demonstrated, or if the community leadership cannot confirm the use of the tree by a particular person, then assistance will not be paid. Commercial trees that have only one-time value, basically trees for timber and naturally grown, will not be compensated because people can sell it at present market value when tree is cut.

5. QUESTION: Do we need to clear the affected trees immediately once it was identified as affected?

ANSWER: No. The affected trees will be removed by the contractors of the project.

Clearing the affected trees will only take place after APs have received compensation for the lost trees. After the APs have acknowledged receipt of payment, the Project shall provide a reasonable time for them to clear the affected trees in order for construction activities to commence.

6. QUESTION: Do we need to pay any administrative or service fees to the project once we receive our compensation?

ANSWER: No. APs are do not need to pay any service fees. APs who are asked for service fees or donations by any government or Project staff in the area must report directly to the Provincial authority or EDC.

7. QUESTION: If there will be disagreements or problems that arise during project

Implementation such as compensation, technical and general project-related disputes, do I have the right to voice out my complaint?

ANSWER: If APs disagree with assistance options, they may present their questions or complaints to the local administrative officials and grievance committees either in person or in writing. A grievance redress mechanism has been established for the project as follows. Nothing in the Grievance Redress Mechanism (GRM) stops complainants from resolving the issue through the Cambodian legal system if Page 3 (Appendix 2)

ELECTRICITÉ DU CAMBODGE Medium-Voltage Sub-Transmission

Expansion Sector Project, Package 1 dissatisfied with the outcome of the GRM.

8. QUESTION: When is the project expected to commence and to finish?

ANSWER: The construction is expected to commence in 2015 and planned to finish in 2018.

If you have further queries and suggestions, please call or see us at:

EDC – Electricité du Cambodge

Ang Yukanthor (St.19), Wat Phnom, 12202,

Tel: 023 723 871 or 023 427 626

Fax: 023 426 593

Page 4 (Appendix 2)

ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Annex 5: The Consultation with AHs for additional cost of 12% of inflation rate (CPI)

5.1 Consultation meeting with AHs on 23 December 2017 Minute of Meeting Discussion Meeting with Affected People at Svay Chrum Distric, Svay Rieng Province

Date of the meeting 23rd December 2017 Consultation meeting to AHs about compensation and the inflation rate at the last Purpose of the meeting two years, and to discuss the safty when energize the electricification Issuer EDC/SEPRO and PIC Consultant Location Ang Tosou Commune, Svay Chrum District, Svay Rieng Province, Cambodia

Distribution

Participants Participants Local Authority/Commune EDC/SEPRO Contractor PIC Consultant *See participants list for details 40 persons/ Female=21

Agenda

 Introduction of the participants  Overview of the project  Presentation of the consumer price index and priorities  Discussion led by consultant experts  Others (PIB were distributed to all participants) Minutes of the Discussion

Introductions of the The participants all introduced themselves participants

Presentation of the The following points were made by the representatives from EDC-Svay Rieng: EDC/SEPRO (EDC-  Focus on remaining works on the site for the Rural Energy Project, grant No. 0336 SVR) and priorities  Procedure for connection and fees  Explain the example for calculation for monthly electricity usage fee of 1 household  How to prevent, electricity safety measures and energy saving  Show the warning signs and more information  And the last time showing the table of connection cost and the deposit fee for the first connection from public grid lines (the detail in BIP).

Bun San (Resettlement Expert):  There are 6 districts in Svay Rieng province that covering by the Rural Energy project

80 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)  Total number of AHs has been reduced from 620AHs to only 246 AHs with also reducing the affected trees from 3,619 mixed of type of trees to 1,009 fruit trees  The cost for resettlement based on the replacement cost study (RCS), the cash compensation equal to USD 48,687.5 (the estimated cost in 2016)  Based on the calculation of the supplementary income changes commodity price in 2017 – 12% (of which increasing the inflation rate); so equal to USD 54,530.0, it has to compensate to AHs who are already received the first compensation cost.  Most of affected Persons are willing to participate in the project and want the project operation soon, and other household would be happy to provide the affected trees without compensation but each participant requested to the EDC to reduce the connection fee.  There are only two households requested to connection the electrification as well due to their houses is far away from the alignment route around 500m to 1000m, but the EDC-Svay Rieng said that this route line will be installed the post by next year in 2018 by EDC-Svay Rieng fund.  There are no ethnic minority groups Representative of AHs (in Ang Tasou Commune):  Now people in the project area are using solar power; battery to lighting at the night and other purposed, however; for this project they would be happy and hope that this project will increase the income by saving energy  APs expressed that they are strongly supporting the Rural Energy Project as they expect significant benefits from the project  For the reference, all the APs raised their hands to support the project 100% without get more compensation 12% of the total compensated.  At the end of the meeting, PIB were distributed to all participants (40 persons) and give it to Commune Chief (20PIBs) for distributing to other villagers who did not join this meeting.

Next steps The following documents were requested:  All people who are living in the project area and willingness to connect the electricity, please apply or contact to EDC-Svay Rieng with attachment of requirement document from this day on 22 Dec. 2017  Plans for expansion the route lines of EDC-Svay Rieng  Operation and maintenance by EDC-Svay Rieng The consultant team will:  Check on the status of the Rural Energy project under the project targeted area  Environmental and Safeguards monitoring will be conducted every three months until June 2018.

Field work The team visited the route lines along the road in Rokar and Cheng Meng villages to the North-west of the town. The team also visited the transformer were already equipped at the sites.

End of the minutes.

81 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

82 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

83 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) PHOTOGRAPHS

Consultation meeting with APs and Commune Chief at Consultation meeting with APs and Commune Chief Ang Tasou commune on 23 Dec. 2017 at Ang Tasou commune on 23 Dec. 2017

All APs raised their hands to supported the project Some Affected persons are willingness to contribute during the discussion meeting on 23 Dec. 2017 donation their affected trees to the project without compensation

Clsoed ceremony meeting by Commune Chief Ang Tasou Commune

84 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 5.2 The consultation meeting with affected people at Svay Rieng province for The Rural Energy Project (ADB Grant No. 0336) on 14 – 15 Feb. 2018 1) Minute of Meeting Venue Meeting Place: 1) Ou Samdei village, Pouthi Reach commune; 2) Thlok village, Thlok commune; and 3) Doun Leab village, Kouk Pring commune.

- Date : 14 – 15 February 2018 - Agenda : Review and confirm the AHs agreed to donate the additional cost of compensation based on the CPI with inflation rate of 12%. - Attachment: - Minute of meeting; - Attendance list; - Field photos - Brief the result meetings (the 3 venues meetings) The Consultation meeting were arranged at the three venue meeting at 3 communes of Svay Chrum district, Svay Rieng province by Resettlement Specialist in three different places among the five districts which affected by the Rural Energy Project. The aim of the consultation meeting is to confirm the AHs agreed to donate the additional cost of compensation based on the CPI in 2017 to the community and discuss resettlement issues due to the project activities. During that time, awareness of Grievance Redress Mechanism (GRM) was disseminated to all AP as well. Village Chief expressed his warm welcome and thanked to all Study Team’s members (EDC/SEPRO, PIC and Contractor) and villagers especially with AHs for participating in the meeting for reviewing the progressive works of the project, and fact finding the Replacement Cost Study (RCS) prepared by Consultant and EDC/SEPRO. The Study Team (Resettlement Specialist) briefed progress of Project Implementation and the issues on the compensation cost and inflation rate were found during the RCS for the Rural Energy Project in Svay Rieng province. The point out that issue is mainly raised the following events. (i) Purpose of the meeting; (ii) The number of AHs; number of affected trees for donation/compensation; (iii) Cost estimate by type of trees in 2014 and CPI with inflation rate 12% in 2017; (iv) Resettlement assistant and donate the additional cost of compensation based on CPI of the AHs; (v) Closed the meeting. After the briefing, the study team invited the villagers or AHs and requested or raised additional explanation on the issues of the compensation cost were already compensated referring to the unit price in 2014 and additional cost of 12% based on replacement cost study in 2017. However, all AHs and villagers in the meeting wanted the project run the operation as soon as possible than the additional cost of 12% of the total amount were compensated. During that time the study team explained the schedule, purpose of the project, and the route line extension in the near future. As the results of deep discussion, all affected households agreed for donation of their total compensation cost to the project by voluntary donation without complaining for the smooth implementation of the project, the meeting concluded that:

85 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) (i) The participants in the meeting especially AHs is acceptable and agreed to donate the additional compensation cost of 12% to the project by the EDC for processing prior to submission to ADB for concurrence. (ii) Due to request and requirement of the villager’s willingness to connect the electricity, connection fee, utility cost, the study team will bring these proposals to EDC hard quarter at Phnom Penh for decision-making. The meeting has been closed with fruitful results, mutual understanding and friendly atmosphere on the same date.

The schedule of Consultation Meeting from 14 – 15 February, 2018 # of Location Participants Date Province District Commune Meeting place

14 Feb. 2018 Svay Rieng Svay Chrum Pouthi Reach Ou Samdei village 19 persons, (8:30AM) F=10

14 Feb. 2018 Svay Rieng Svay Chrum Thlok Thlok village 20 persons, (14:00PM) F=15

15 Feb. 2018 Svay Rieng Svay Chrum Kouk Pring Doun Leab village Persons 14, (8:30AM) F=12

Note: see detail attendant list.

86 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 2) Attendance lists 2.1 Attendance list at Ou Samdei village, Pouthi Reach commune

87 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

88 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 2.2 Attendance list at Thlok village, Thlok commune

89 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

90 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 2.3 Attendance list at Doun Leab village, Kouk Pring commune

91 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) 3) Photos Most of the questions have answered by study team after each question. The participants understand well on the project status and its activities. They expected that their community will get more benefits and improvement and cheaper cost for electricity consumer and saving time after the project construction completion. All the participants in this meeting support the project 100% and wanted to have this project done soon.

Photo 1&2: Consultation meeting at Purthi Reach commune, date 14 Feb. 2018 at 8:00 am

Photo: 3 &4: Consultation meeting at Thlok commune; date 14 Feb. 2018 at 14:00 pm

Photo: 5 &6: Consultation meeting at Kouk Pring commune, date 15 Feb. 2018 at 8:00 am

92 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province)

Photo: 7 & 8: House to house consultant by Contractor in Feb. 2018

93 ELECTRICITÉ DU CAMBODGE Rural Energy Project No.0336 (Component 1: Rural electrification of Svay Rieng province) Annex 6: Field pictures for house to house consultation implemented and compensation by the Contractor cooperates with EDC/SEPRO, in July and August 2017

Meeting with APs for house to house consultation Contractor cooperates with EDC/SEPRO for house to implemented by the Contractor cooperates with house consultation and compensation to affected EDC/SEPRO at Thlork commune, Svay Chrum district households at Thlork commune, Svay Chrum district date

Contractor cooperates with EDC/SEPRO for house to Contractor cooperates with EDC/SEPRO for house to house consultation and compensation to affected house consultation and compensation to affected households at Trapeang Sdau commune, Romeas Haek households at Pouthi Reach commune, Svay Chrum district, on August 2017 district, on August 2017

Discussion meeting with Commune Chief about the Field visited at Pouthi Reach commune, Svay Chrum ROW and realignment of MV and LV route lines district, Svay Rieng province

94