Infrastructure and Urban Development Annual Report 2019

Annual Report 2019 1 2 Infrastructure and Urban Development Foreword

This year’s Annual reducing traffic congestion, and improving overall Report of the African mobility. The City Roads project will im- Development Bank’s prove the urban road network of and in- Infrastructure and troduce pilot dedicated public transport routes with Urban Development hybrid buses. The project will also provide institu- Department features tional support to build capacity in the development a record lending and management of green infrastructure and plan- amount of USD 2.2 ning of transportation investments. Billion for a diversified portfolio of 21 trans- A third category of transport projects supported port projects. by the Bank in 2019 targeted rural access and ur- ban-rural connectivity to break isolation, connect Cross-border road projects approved for funding farmers to markets and facilitate rural populations’ in 2019 include both regional corridors which have access to education and health facilities. The Eas- received longstanding support from the Bank, and tern Corridor Development Program in aims new corridors. The Nacala Road Corridor in Sou- to turn challenged rural areas along the road into thern is an example of the Bank’s long-term economically prosperous bread baskets. The pro- commitment to regional connectivity not only by fi- ject will impact the lives of over 5.4 million people, nancing the physical infrastructure but also in pro- stimulate socio-economic development, and pro- viding technical assistance in support of trade and mote inclusiveness. The Eboni State ring Road in transport facilitation and in designing optimum so- is another important rural-urban connectivity lutions for legal frameworks, technical, economic, project financed by the Bank in 2019. The project environmental and socio-economic options. Simi- will connect farming communities in 13 Local Go- larly, the Kenol-Sagana-Marua dual carriageway vernment Areas, and boost agricultural productivity. highway in will expand the capacity of the vital backbone corridor linking the to In line with its High Five strategies, the Bank has , . The new regional transport supported Africa’s infrastructure development in corridors supported include the Ethiopia- 2019 by providing comprehensive transport solu- corridor through an alternative shorter route, and tions for client countries and the private sector to the Kenya- coastal highway Malindi-Mom- address regional connectivity, urban mobility and basa-Bagamoyo-Dar es Salaam linking the region’s rural access. busiest ports and connecting industrial hubs and major tourist destinations along the coastal regions of the two countries.

Besides expanding regional road corridors, the 2019 portfolio included projects aimed at improving Amadou Oumarou urban mobility. The City outer ring road Director, will help guide the urbanization of Tanzania’s capital Infrastructure and Urban Development Department city by redistributing the location of activity centers, Annual Report 2019 1 Technical note

Choice of currency and conversions The Bank uses a Unit of Account (“UA”) equivalent to the IMF’s Special Drawing Right as its reporting currency. The value of the UA may vary from day to day.

Infrastructure and Urban Development projects approved by the Board of Directors of the African Development Bank are expressed in the currency of the Project. This may be in US Dollars (USD), (EUR) or Units of Account (UA).

In the case of active portfolio representations, the amounts have been converted into USD at the conversion rates of the month and year of the project approval by the Board.

All data on project funding and all socio-economic data is retrieved from the project appraisal report presented to the Board.

© 2020 African Development Bank Group All rights reserved – Published 2020

Disclaimer

Unless expressly stated otherwise, the findings, interpretations and conclusions expressed in this publication are those of the various authors of the publication and are not necessarily those of the Management of the African Development Bank (the “Bank”) and the African Development Fund (the “Fund”), Boards of Directors, Boards of Governors or the countries they represent. The content of this publication is provided without warranty of any kind, either expressed or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non- infringement of third-party rights. The Bank specifically does not make any warranties or representations as to the accuracy, completeness, reliability or current validity of any information contained in the publication. Under no circumstances including, but not limited to, negligence, shall the Bank be liable for any loss, damage, liability or expense incurred or suffered which is claimed to result directly or indirectly from use of this publication or reliance on its content. Contents

KEY PRODUCING AND 05 MESSAGES 71 SHARING KNOWLEDGE

Urban Development : Making P72 2019 LENDING Headway with Strategic Partners Preventing Road Accidents 07 ACHIEVEMENTS and Fatalities in Africa P74 2019 Knowledge Publications P76 Project Lending 2019 Transport and Urban Development P8 2019 Lending Breakdown P9 Road Corridors for Mobility and Opportunities P10 ABOUT 2019 Project Design Highlights P12 79 INFRASTRUCTURE AND URBAN DEVELOPMENT

DESCRIPTION OF Strategic Focus P80 17 PROJECTS FUNDED Department Organization P81 IN 2019 Staff P82

Infrastructure and Urban Development Projects P18 NEPAD-IPPF Regional Project Preparation projects P59

ACTIVE PROJECT 65 PORTFOLIO Implementation status of selected ongoing projects P66 Active Projects Portfolio 2019 P68 Portfolio Breakdown P69

Annual Report 2019 3 4 Infrastructure and Urban Development Key Messages

Commitments exceed $2 billion The Bank has increased its annual financial contribution to Infrastructure and Urban Develop- ment, committing USD 2.2 billion to 21 projects in 2019, compared to USD 1.9 billion to 19 projects in 2018 and USD 1.5 billion to 16 projects in 2017.

Strong emphasis on Africa’s roads In 2019 the Bank has supported and accompanied RMC in 17 road projects, in many cases from inception and through preparation to bankability point. The Bank has financed close to $2bn of road projects alone. Indeed, the road sub-sector accounts for a massive 86% of total financing in Transport and Urban Development this year. Efficient transport networks The 2019 portfolio of project financing alsoincludes 2 airport and 1 port projects, demonstrating the will of Africa’s regions to place emphasis on efficient transport networks for the movement of people and goods. In Tanzania for example, the financing of both the airport and the ring road in Dodoma are part of a holistic national strategy to stimulate development in the administrative capital. Trade facilitation and job creation 2019 projects support national and regional strategies to stimulate the economy and lift fragile communities out of their isolation. Each of the 17 road sector projects in 2019 will generate an average 2500 jobs during construction works, and thousands more indirect jobs created as economic activity grows thanks to the improved road network. 1200 direct jobs and 3000 indirect jobs will be created as a result of airport renovation, a further 665 direct jobs from port construction. 7.3 million urban inhabitants of Banjul, Dodoma, Kampala and will all directly benefit from enhanced trade and job opportunities from projects funded in 2019.

Annual Report 2019 5

Infrastructure and Urban Development 2019 Lending Achievements

In 2019, the Bank approved 21 Transport and Urban amount of financing by the Bank in the transport sector in Development construction projects for a total exceeding 2019 (USD 1.1billion). The road and airport constructions USD 2.2 billion. The number of projects and the financial pertaining to these projects will be in Kenya, Tanzania and commitments in 2019 compare favorably with 19 projects Uganda. The East Africa region took the lion's share of in 2018 (USD 1.9 billion), 16 projects in 2017 (USD 1.5 project funding. In total, the seven projects financed in billion), 10 projects in 2016 (USD 1.5 billion*) and 14 East Africa covered 64% of Bank infrastructure project projects in 2015 (USD 1.9 billion*). financing in 2019.

17 of the projects were in the roads sub-sector. These 24% of the USD 2.2 billion of approvals in 2019 was accounted for 86% of financing, the largest of them allocated to projects in Central Africa, the largest being being a new cross-border corridor between Kenya and the second phase of an on-going road project in North Tanzania. The Bank has committed $350 million to the Western . first phase ofth e Bagamoyo – Horohoro/Lunga- Lunga - Malindi road, a strategic coastal route which will serve the and Southern Africa accounted for 8% and main East African ports. 4% respectively of the remaining financing in 2019.

12% of financing was for 2 air transport projects, the To promote regional integration ambitions, six projects largest being the first phase of an important infrastructure aimed at facilitating trade and movement of people across upgrade to enable International air traffic to and from borders. Dodoma airport in Tanzania. - Kenya and Tanzania - and Tanzania A port capacity expansion project in supports - Mozambique and the Central Africa’s Great Lakes bid to increase - Ethiopia and Djibouti maritime traffic as part of a multimodal transport mix for - and the R. Congo passengers and fret. The project is part of a lake-wide - R. Congo and the DR.Congo development initiative supported by the Bank from the project preparation phase. Also in favour of regional integration, the NEPAD-IPPF financed four new project preparations, of which two in In addition to several transport projects which contained the transport sector and two new projects in the energy urban green growth components, one project was sector for a total of USD 5.37M. dedicated to planning for Urban Development of Greater Banjul in . Each project supported by the Bank contained components for ancillary works which promote green and Over 91% of financing was in the form of loans from the inclusive growth and provide training and job opportunities Bank. The rest of financing came in the form of grants. The for women and youth in the project area. As a result, over Ethiopia-Djibouti Road project alone attracted substantial nine million people living in the vicinity of the roads will grants totalling over USD 100 million. experience a direct improvement in their quality of life as the infrastructure financed in 2019 takes shape: more In terms of regional distribution, the four largest projects affordable and faster travel, lower fret and trading costs, approved in 2019 were all located in East Africa. Between and opportunities for sustainable and equitable social them, the four projects accounted for half of the total and economic development.

* Figures exclude ICT projects, formerly part of the Bank’s Infrastructure and Urban Development Department. Annual Report 2019 7 2019 Project Lending

24

ALGERIA

14

MALI 19 22 GAMBIA 25 BURKINA DJIBOUTI FASO 10

NIGERIA CÔTE GHANA D’IVOIRE 20 ETHIOPIA 8 23 9 CAMEROON 21 5 CAR 3 18

4 CONGO UGANDA 7 GABON DR CONGO KENYA 17 11 1 1 KENYA 11 DR CONGO National Road 12 Bagamoyo-Horohoro BURUNDI TANZANIA Lunga-Malindi Phase 1 Rehabilitation 2 USD 350.4m USD 69.7m 6 2 TANZANIA 12 CONGO - DR CONGO Congo River Road-Rail Msalato International Airport MALAWI 15 USD 271.1m Bridge access roads USD 54.9m 13 3 UGANDA Kampala City 13 MALAWI - MOZAMBIQUE Roads Rehabilitation Nacala Road Corridor MOZAMBIQUE Phase V USD 265.8m 16 USD 36.6m 4 ETHIOPIA - KENYA 14 NIGER Kenol-Sagana-Marua Tamaske-` Highway -Mararraba Roads USD 230.8m USD 32.8m

5 CAMEROON 15 COMOROS Transport sector support Road Network Phase 3 (2nd Installment) Rehabilitation RN2 USD 224.8m USD 31.6m

6 TANZANIA 16 MOZAMBIQUE -Negomano Road Dodoma City Outer 21 Ring Road Upgrade Phase 2 -Mpoko Airport Modernisation USD 180m USD 26.8m USD 1.5m 7 GABON 17 BURUNDI 22 EAST AFRICA Infrastructure sector Lake Tanganyika Standard Gauge Railway support Phase 1 Rehabilitation-Bujumbura Port Connecting Ethiopia And Sudan LEGEND USD 151.4m USD 26.1m USD 3.2m 18 SOMALIA WEST AFRICA 8 ETHIOPIA - DJIBOUTI 23 Road Port Transport Corridor Phase 1 Road Infrastructure Côte d’Ivoire -Liberia Interconnection USD 102.1m Programme USD 1.88m USD 16.9m 24 NORTH AFRICA 9 GHANA Air Urban Eastern Corridor Road 19 GAMBIA Corridors Study: -Tunisia borders Development USD 80.3m Greater Banjul Area SUDP USD 1m USD 3.0m 25 WEST AFRICA Project 10 NIGERIA 20 NIGERIA Ghana-Burkina- Power preparation Ebonyi State Ring Road Interconnection Phase II USD 70.0m Abia State IIDP Preparation Study 8 Infrastructure and UrbanUSD Development 1.7m USD 0.61m 2019 Lending Breakdown

bn 8 .6 .9 6 7 1 2 D 17 D S 2

S

U Ro

U Aition projects projects

2 18 of road construction and The new international airport in rehabilitation in 16 countries, including Dodoma: an important evolution for 21 650 km of transnational roads Tanzania’s administrative capital and PROJECTS of which a project initiating a new road continued efforts to meet International APPROVED corridor between Ethiopia and Djibouti. air safety standards.

6 3 2 D D 1 S S USD 1 U Urbn 2.2 U Port Dont BILLION project project

25 000 TEU container capacity and A Digital masterplan for Greater Banjul 15 000 ferry passengers on Lake which focuses on green growth and Tanganyika, improving the regional environmental protection. integration of Burundi.

. 5 D 4 S Proct

U rrtion by NEPADIPPF

1 ro project , 1 ri project 2 nr projects

Annual Report 2019 9 Road Corridors for Mobility and Opportunities 650 km of multinational roads approved in 2019

Road corridor constructions in Africa reduce transport and logistic costs and promote cross-border trade and regional integration.

Road corridor sections approved by the Bank in 2019 Nigeria: Construction of 178km of road which will serve as an international link between Ebonyi State and the Republic of Cameroon. The road links to the Enugu – Bamenda Road Corridor which was supported by the Bank and completed in 2013, thereby facilitating interstate mobility in Nigeria.

Ghana: 69km of road heading North from Ghana’s ports to the region’s landlocked countries on the Eastern Corridor route. Ghana has the ambition to become the Transportation and Logistic Hub of West Africa – 15,452 km of trunk roads run through the country connecting the region. The Bank’s interventions include funding for Inter-Agency Coordination and Corridor Coordination with and Mali.

Gabon: 49km of road on the Trans-Gabonese corridor towards the South, providing a gateway to the Republic of Congo. The project complements works underway in Congo between Dolisie and Ngongo on the Gabon/Congo border, part of the ECCAS Consensual Master Plan for Transport in Central Africa.

Ethiopia-Djibouti : 60km of a new 4-lane highway, part of the Ethiopia-Djibouti Transport Corridor Project. Imports and exports to Ethiopia represent around 80% of the activities of the ports of Djibouti. The Bank is an active partner in the Ethiopian transport sector and a co-financer in the development of the Ports of Djibouti.

10 Infrastructure and Urban Development 1300 Youths will receive training in road construction

Road corridors invariably create employment opportunities. A large number of direct and indirect temporary jobs are created during the construction phase of the project. On completion of the project, job opportunities are generated in the project vicinity, and within the new transportation ecosystem created as a result of the project.

Kenya: Construction of 84km of road on the Trans-Africa Highway No. 4 (TAH-4) towards the border with Ethiopia. The Bank has already financed a significant part of the TAH-4 in the region : 800 km in Kenya, 300 km in Tanzania and 700 km in Ethiopia.

Tanzania and Kenya: 175km of road which runs along the Indian Ocean coast and bridges the link between the Northern and Central corridors which serve the ports of Mombasa and Dar es Salaam, respectively. The road is a priority project under PIDA and prioritized in the Bank’s Eastern Africa Regional Integration Strategy.

Mozambique: 35km in the North of Mozambique complements the already constructed Unity Bridge on the border with Tanzania towards the ports of Pemba in Mozambique and on the Mtwara Development Corridor. 500 construction job opportunities will be created, with a target of 15% of these to be taken up by women. The road will create 50 permanent jobs, of which 10 reserved for youth.

Malawi: 55 km of road in Phase V of financing of the Nacala Corridor complements previous projects which have enabled over 1000km of road along the strategic corridor since 2009, in , Malawi, and Mozambique. The current project will create 400 jobs.

Annual Report 2019 11 2019 Project Design Highlights

Transportation and urban development projects should be properly structured technically, ecenomically, legally and commercially to ensure sustainability. As part of the Bank's drive for sustainable and inclusive development, the projects presented to the Board combine due dilligence with best practices and expertise in new environmental trends. In 2019, the Bank pursued its efforts in mobilizing resources on behalf of its regional member countries and applying innovative responses adapted to the context of each project. The highlights of this year's project design reflect the focus on partnerships as well as cutting-edge solutions for sustainable development with green growth.

Emphasis on Partnerships PAGoDA, the EU Africa Investment Platform

In November 2019, The Bank and the 2019 Project Amount shook hands on a renewed commitment to unlock MUSD hundreds of millions in financing for African infrastructure Nacala Phase V and development needs. Collaboration between the two 47.2 institutions also puts strong focus on de-risking projects Somalia Road Infrastructure 42.2 in Africa, providing equity, guarantees and other types of Programme non-grant support. Senegambia Bridge 17.5 On behalf of recipient countries, the Bank acts as an Lake Tanganyika 21.7 administrator of projects financed by the European Union Bagamoyo Lunga Malindi under PAGoDA, an agreement concluded within the 33.1 framework of the Africa Investment Platform (AIP) under the TOTAL EU contribution 161.9 11th European Development Fund.

The successful conclusion of 5 infrastructure projects in 2019 showcases the Bank’s role in leveraging partner institutions to achieve greater development impact.

The Nacala Road Corridor - Support for the Mozambican Government In consultation with the Mozambican government, the Bank applied for an EU grant to supplement resources for two distinct phases of financing of the Nacala Road Corridor Development. The Bank and the EC signed a delegation agreement to define the activities entrusted to the Bank and lay down the rules governing the transfer of the EU’s contribution. The Bank finalized 2 separate financing agreements from the EU-AIP in June and November 2019, totalling USD47.2M to be disbursed under a grant agreement with the Government of Mozambique. The Senegambia Bridge - Continued Support for Transnational Traffic Funding has been allocated to improve the sustainability of the Bank’s achievements in financing the Senegambia bridge, commissioned in 2018. The PAGODA grant to the Senegambia bridge improvement project is a financing of EUR 16million awarded in 2019 that is exclusively intended for the strengthening of the 24 km of connecting roads between Farafenni and Senoba.

The Bank administers the AIP grant for the works, applying its own accounting, internal control and audit procedures, which have been positively assessed by the EC. The Bank will also apply its procurement policy and procedures. The grant mobilized from the EC by the Bank will make it possible to upgrade the approach road to prevent deterioration due to the increase in road traffic induced by the bridge.

12 Infrastructure and Urban Development Focus on Integrated Urban Planning, Climate Change and Green Growth

Every financing proposal submitted to the Board contains mitigation measures to reduce environmental impacts. Examples of affirmative actions for the environment in 2019 include:

Greenhouse Gas Reduction

As part of the multinational Kenya-Tanzania road project, the planting of trees along the project roads and within the degraded areas inside Saadani National Park (Tanzania) and forest mangroves (Kenya) is planned to support ecological resilience and carbon sequestration. In total, 200 ha of trees will be planted and will result in more than 60,000T of CO2 sequestered over a 40-year period. Secondly, provision of non-motorized transport facilities and smart energy efficient street lightings in urban sections will contribute to long-term GHG emissions reduction goals. Urban Green Growth

The Bank and UNIDO will collaboratively support the City of Dodoma towards Climate Change resilience through studies for a rapid bus transit and other energy efficient urban infrastructure.

In Kampala, the project includes eco-buses and a green bus route aimed at de-carbonizing mobility solutions in the city. It also includes the provision of 1,600 energy efficient streetlights in the city and 123km of pedestrian sidewalks. Climate Change Resilience - Prevention of Flooding

In the Comoros Islands, climate change engenders potential risks including fiercer cyclones, rising sea-levels, sea-water encroachment and abundant rainfall. The road project will build climate resilience through the construction of coastal protection structures. Existing infrastructure will be modified to enhance climate resilience by protecting bridge structures from stripping and abrasion, raising the elevation of the road, increasing the solidity of retaining walls and strengthening bridge structures.

For the Dodoma Ringroad project in Tanzania’s administrative capital, the low-lying nature of the terrain makes climate risk such as flooding problematic on some sections of the project. The project will support the City of Dodoma to integrate biodiversity and ecosystem values in urban planning. It will also assist in the restoration of degraded urban land and sustainable land management with funding for reforestation of the Dodoma city hill ranges, drainage system improvements to control rainwater runoff and soil erosion, and tree planting on the ring road embankments. Other components include the management of Dodoma’s natural capital and development of green space recreation parks.

Annual Report 2019 13 Emphasis on Project Preparation

The New Partnership for Africa’s Development Infrastructure Project Preparation Facility (NEPAD-IPPF) Special Fund, hosted by the Bank's Infrastructure and Urban Development Department, plays a catalytic role in mobilizing resources for preparation of regional projects and programs.

Preparing Complex Regional Preparing the Bujumbura Port Projects Project for Funding in 2019.

In 2019, the IPPF completed 3 studies for During 2019, the first phase of port important road corridor projects that the rehabilitation of Lake Tanganyika was Bank has financed in several stages, due facilitated by IPPF project preparation. to the complexity and scale of multinational The Governments of Zambia and transport projects. These are: Burundi submitted a request to the 1. The project preparation study of the Bank in 2013 for grant financing of a North-South Corridor Roads Rehabilitation project preparatory study to rehabilitate aims to improve the regulatory environment and modernize Mpulungu Port and on the corridor for subsequent financing Bujumbura Port on Lake Tanganyika. rounds.

The project preparation study of the 2. The IPPF intervention aimed to produce Kampala - - Addis Ababa - Djibouti an optimum engineering design for a Corridor intends to demonstrate the rapid return on investment. economic viability and thereby attract Specifically, the study identified specific investment in the project to provide South rehabilitation and modernization plans, Sudan and Northern Uganda with an analyzed the technical and economic alternative access to the Djibouti seaport. viability, carried out an environmental and social impact assessment, and The project preparation study of the 3. prepared a detailed engineering design rehabilitation of selected road sections of and tender documents. the Central Corridor in Tanzania, The output of the study, completed in and Burundi Phase II intends to bring the January 2019, has contributed to the project to bankability stage for subsequent Lake Tanganyika Transport Corridor financing. The project road will facilitate receiving project funding from the Bank access to the port of Dar es Salaam for in 2019. landlocked countries.

14 Infrastructure and Urban Development Emphasis on Preventing Road Accidents and Fatalities in Africa

Road safety is one of the priority areas in the Bank’s Infrastructure and Urban Development Department. During 2019, the Bank's road safety interventions were both in the form of knowledge sharing to strengthen institutional capacity and at operational level, with road safety audits and sensitization for communities living near road projects.

Urban Road Safety 2019 : Tanzania Rural Road Safety 2019 : Gabon The Dodoma Ring-road project in Tanzania The Road Improvement project in Gabon includes a study features traffic calming and safety measures like to update the Strategic Road Safety Plan and road safety rumble strips designed for 50km/h and repeated audits on certain highly accident-prone asphalt sections, every 250m at the beginning of a village section; including Lambaréné-Mouila (190 km), Mouila-Ndendé (75 raised pedestrian crossings at local schools; km) and Ndendé-Tchibanga (85 km). Firms contracted standard bus bays and terminal points to provide for road works will be required to apply the required a safe place for passengers to alight and board standards relating to signage and road safety features. from public transport; 2m wide sealed shoulders The project also incorporates road safety awareness on either side of the road to be used as pedestrian campaigns targeting users and the local communities. walkways and for cyclists/Non-Motorized Transport (NMTs); and security lights.

Road safety sign on the Léyou-Lastoursville road in Gabon

Annual Report 2019 15

2

Infrastructure and Urban Development Description of Projects Funded in 2019

1 Multinational: Bagamoyo-Horohoro/Lunga-Lunga-Malindi Road Phase I P 18 2 Tanzania: Msalato International Airport Construction P 20 3 Kampala City Roads Rehabilitation P 22 4 Kenol-Sagana-Marua Highway Improvement P 24 5 Cameroon Transport Sector Support - Phase III P 26 6 Tanzania: Dodoma City Outer Ring Road P 28 7 Gabon Infrastructure Sector Support - Phase I P 30 8 Multinational: Ethiopia-Djibouti – Transport Corridor, Phase I P 32 9 Ghana: Eastern Corridor Road Development Programme P 34 10 Nigeria: Ebonyi State Ringroad P 36 11 DRC – National Road No.1 Rehabilitation /Ndjili-Batshamba Section P 38 12 Multinational DRC-Congo: Access Roads to the Road-Rail Bridge over the Congo River P 40 13 Multinational – Nacala Road Corridor Development Project Phase V P 42 14 Niger: Tamaske-Tahoua And Tamaske-Mararraba Roads Development P 44 15 Comoros: Road Network Rehabilitation - RN2 (Moroni – Foumboumi) P 46 16 Multinational: Mueda–Negomano Road Upgrading Phase II P 48 17 Multinational: Lake Tanganyika Transport Corridor Development P 50 18 Somalia: Road Infrastructure Programme P 52 19 Digital Masterplan and Capacity Building Programme for the Greater Banjul Area P 54 20 Bangui-Mpoko International Airport Modernisation Support Project-Phase I P 56 21 Abia State Integrated Infrastructure Development Preparation Studies P 58 22 Standard Gauge Railway connecting Ethiopia and Sudan P 60 23 Corridors Study: Algeria-Tunisia borders P 61 24 Ghana-Burkina-Mali Power Interconnection Phase II P 62 25 Côte d’Ivoire-Liberia Interconnection P 63 Multinational: Bagamoyo – Horohoro/Lunga- Lunga - Malindi Road Phase I Kenya A strategic coastal route linking ports and enhancing Tanzania regional integration. Project Team Leader : Zerfu TESSEMA, Chief Transport Engineer

Poor infrastructure has been identified by the Governments of Tanzania and Kenya as one of the major constraints to regional integration and broader socio-economic development for both countries.

The project road is a strategic coastal trade route. It will constitute a link between the Northern and Central corridors, which serve the region’s busiest ports of Mombasa and Dar es Salaam respectively. Complementary soft components of the project, in the form of a trade and transport facilitation study, aim at optimising the benefits of regional integration afforded by the coastal road. The study will identify key constraints to trade, bottlenecks affecting transit time and overall corridor efficiency. In particular, the study will prioritise the preparation of a coordinated border management system at the Lunga Lunga/Horohoro border post.

In Kenya, 83% of the local population live and work within the traverse area and are therefore the primary stakeholders to the Road Project. In Tanzania, most of the community members in the area of influence are small-scale farmers. An estimated 3 million people in the two countries will benefit from this project, in addition to regional traders and the tourist industry.

Studies to build a One-Stop Border Post (OSBP) on the coastal road between Kenya and Tanzania are part of the 2019 multinational road project. Pictured here, the Namanga OSBP, located on the Tanzania-Kenya border along the road between Arusha and Athi River is the main inland border crossing point. Commissioned in 2017, it has significantly reduced transit time, with truck clearance now possible in 15-20 minutes in both directions.

18 Infrastructure and Urban Development II UU U Govt. of Tanzania Govt of Kenya UA 18.3M 2018 2023 UA 26.9M 5.6% 100 person 8.2% months of jobs Travel time for trucks Travel time for trucks on European ADB (loan) (30 women) 2 27% on road section road section Union 7.5 UA 88.M 5 3 UA 2.6M % 25000 trees planted volume of trade volume of trade UA 326M at border at border USD 11 iion USD 169 iion ADF (loan 500 youths 1% to Kenya) trained UA 6.M Poverty level in Tanzania Poverty level in Tanzania 21.0% 18% 37.5% ADF Lon to Tnni UA 122.3M

Approval Completion December December 2019 2020 2025 2026 Effective May 2020

KENYA Malindi

Kilifi

5

Mombasa

orohoro TANZANIA Weighbridge

Tanga

Pangani

Mkwaja

120 Mkange

Bagamoyo 19 Dar es Salam Tanzania: Msalato International Airport II UU U Govt of Tanz 2019 2024 Construction USD 57.8M 17.5% N trin building Support for the development of Dodoma as a modern Airline passengers Airline passengers Tanzania at Msalato at Msalato administrative capital. 3600 runway 6 500 Pr 200 000 P r AGTF USD 50.00M Project Team Leader : Romain EKOTO, Chief Aviation Officer 15% USD 329.7M Contro Tor 153 ton 800 Ton of freight / year of freight / year Dodoma city is currently served by a small airport with an annual capacity of 50,000 passengers, located within the city and which operates only domestic flights via small aircrafts. Since the transfer of all ministries and key government agencies to ADF 7% Ti USD 1.23M Dodoma, population growth is higher than the national average,due both to the relocation of public servants and to others who 60.3% 1200 direct jobs and relocate to take advantage of employment opportunities in supporting services.Consequently, travel out of Dodoma airport has 100 t 3000 indirect ADB (Loan) trained increased faster than the national average at 13 percent annually. USD 198.63M

The Government of Tanzania has prioritized the construction of the new Msalato International Airport (MSIA) to stimulate business and economic development. It is projected that travel demand will exceed 200,000 passengers annually by 2023. The works financed include a new Terminal building, a Runway, taxiways with NAVaids/AGL, a control tower, access road and fence. Approval Completion December June The airport is set to benefit an estimated regional population of more than 200 million people in East Africa and the international 2019 2020 202 2025 trade networks including business travellers and tourists. Effective March 2020

RWANDA KENYA

Arusha

Kilimandjaro International Airport

TANZANIA

Msalato Airport Dodoma A computer-generated image of the future Msalato International Airport in Dodoma, Tanzania. Dar es Salaam ulius Nyerere 20 Infrastructure and Urban Development International Airport II UU U

Govt of Tanz 2019 2024 USD 57.8M 17.5% N trin building Airline passengers Airline passengers at Msalato at Msalato 3600 runway 6 500 Pr 200 000 P r AGTF USD 50.00M 15% USD 329.7M Contro Tor 153 ton 800 Ton of freight / year of freight / year

ADF 7% Ti USD 1.23M 60.3% 1200 direct jobs and 100 t 3000 indirect ADB (Loan) trained USD 198.63M

Approval Completion December June 2019 2020 202 2025 Effective March 2020

RWANDA KENYA

Arusha

Kilimandjaro International Airport

TANZANIA

Msalato Airport Dodoma

Dar es Salaam ulius Nyerere International Airport 21 II UU U Kampala City Roads Rehabilitation Govt of Uganda USD 11.00M 10 of roads 2019 2025 1% % and 22 junctions The project will modernize the transport network in the Global Ugandan capital city, improving mobility, productivity and Environment 65in 35in Uganda Fund 123 of 2 quality of life for the population. USD 2.00M non-motorized traf c Average travel time Average travel time facilities constructed to work to work ADF (Loan) Project Team Leader : George Makajuma, Principal Transport Engineer USD 51.00M 18% 10000 tr 1703 1003 USD 288.00M planted Concentration of Concentration of air pollutants air pollutants Kampala has a road network of 2,110km out of which only 30% is paved. Congestion and competing minibuses and motorbike 1600 Smart taxis on the poor road network have increased accident risk and degraded air quality. In parallel, the concentration of industries street lights 10 FTE ob created in Kampala is driving demand for infrastructure improvements which will increase productivity and spur economic growth. 200 out trained and Authorities are unable to keep pace with the required capital investments and insufficient capacity for planning, operating, and 78% ADB (Loan) 50 bu in employed during construction maintaining urban infrastructure and services. USD 22M operation

The Kampala City Roads Rehabilitation Project (KCRRP) aims at improving improving the road network for cars and pedestrians, and at deploying pilot dedicated public transport routes coupled with the introduction of pproval ompleton environmentally friendly hybrid buses. Institutional support under the project aims to build capacity in development October December and management of green infrastructure, sound planning of schemes and sustainability of public investments. 2019 2020 2025 2026 The improved transport network in the capital city is poised to strengthen foundations for higher productivity for Kampala’s ffectve 1.6 million people, including commuters, businesses, and transporters, while ensuring better access to basic infrastructural January services. It is further expected to foster a conducive environment for foreign direct investments.

KAWEMPE

hway ss hig ypa b rn e h rt o NAKAWA N Green bus route la a p

m a

K RUBAGA Gadda National Mosque Kampala

MAKINDYE

This computer-generated image shows the future layout of bus lanes and facilities for public transport in Greater Kampala.

22 Infrastructure and Urban Development II UU U Govt of Uganda USD 11.00M 10 of roads 2019 2025 1% % and 22 junctions Global Environment 65in 35in Fund 123 of 2 USD 2.00M non-motorized traf c Average travel time Average travel time facilities constructed to work to work ADF (Loan) USD 51.00M 18% 10000 tr 1703 1003 USD 288.00M planted Concentration of Concentration of air pollutants air pollutants 1600 Smart street lights 10 FTE ob created 200 out trained and 78% ADB (Loan) 50 bu in employed during USD 22M operation construction

pproval ompleton October December 2019 2020 2025 2026 ffectve January

KAWEMPE

hway ss hig ypa b rn e h rt o NAKAWA N Green bus route la a p

m a

K RUBAGA Gadda National Mosque Kampala

MAKINDYE

Annual Report 2019 23 Kenol-Sagana-Marua Highway Improvement A sustained effort towards efficient and safe mobility in the Kenya Mount Kenya region. Project Team Leader : Zerfu TESSEMA, Chief Transport Engineer

Part of the Mombasa - Nairobi - Addis Ababa Highway, the existing section of the project road is a two-lane asphalt road, which is congested and unsafe. The road links the capital Nairobi to some of the commercially and agriculturally prosperous localities in the Mount Kenya region. It serves as a gateway to the landlocked countries of Uganda, Rwanda, Burundi, the Democratic and , and also serves Ethiopia via the border town of Moyale.

The Bank has already financed a significant portion of the Mombasa - Nairobi - Addis Ababa Highway. The construction work will result in a 4-lane highway, with two interchanges and numerous road safety facilities. Tree planting and complementary social activities are also an integral part of the project.

The main beneficiaries are the 2 million inhabitants of the five counties crossed, and in particular the traders and farmers of the area, who will gain better access to national, regional and international markets.

Marsabit, Kenya, on the Nairobi-Addis Ababa Highway.

24 Infrastructure and Urban Development II UU U

Govt of Kenya 2019 2024 851M 19% 8 of road Truck journey time: Truck journey time: Kenol to Marua 2 Kenol to Marua 1.9 our 1. our 250 unemployed AGTF 12% youths trained 31.15M 25768M Gross product in Gross product in project area : project area : 7500 person 1.98 biion USD 2.37 biion USD ADB (Loan) months of jobs 178.02M (30 women) 69%

Approval Completion September December 2019 2020 202 2025 Effective April 2020

Marua Interchange Karatina Nairobi KENYA

5 counties crossed : Muranga, Machakos, Embu, Kirinyaga and Nyeri Population >3.5 million Road surface TANZANIA doubled from 1 lane each way to 2 lanes

Sagana

KENYA

Makutano Interchange

Kenol Town Annual Report 2019 25 Cameroon Transport Sector Support - Phase III This second installment of Phase III to improve conditions in the North West and add a transport link to Nigeria. Cameroon Project Team Leader : Pierre MORE NDONG, Principal Transport Engineer

The population of the programme area in the North West of Cameroon is estimated at 1.7 million, with a growth rate of 1.9%. About 62% of the population is aged below 20 years. The region lacks transport links for the growing population to trade with neighbouring Nigeria.

The Bank is financing 280 kilometres of the 365 km road loop. Works in this phase include the MisajeDumbo border section, linking Cameroon to Nigeria. This second instalment and the AGTF loan approved in 2019 are allocated to the works of the sections of the main road and urban roads; and support for the employability of youths in the project area.

Upgrading the ring road will contribute to diversifying the economy and opening up opportunities with neighbouring Nigeria. The annual average daily traffic on the ring road sections is projected to increase by 5% per year, to reach 2000 by 2022.

26 Infrastructure and Urban Development E

Govt of ADB (loan) Cameroon 17.96M 2018 2024 32.8M 280 of road 13% 7% 36 of urban 300 1000 AGTF road netors and Average traf c Average traf c (loan 2019) 206 of access 2.6M roads 17% AF 500 AF 300 255M 2500 ob operating Vehicle operating on construction costs costs sites 52% of women ADB 30% of women (loan 2019) below the income below the income poverty line 63.% 161.6M poverty line

pproval econd ompletion of first instalment instalment December November December 2019 2018 2019 2020 202 2025 rogramme launch Q1 2019

NIGERIA

NIGERIA E E

BECAMEROON

Misaje Nkambe

CAMEROON Kumbo

Bamenda

Annual Report 2019 27 Tanzania: Dodoma City Outer Ring Road Inclusive and green growth in urban development plans for the city of Dodoma. Tanzania Project Team Leader : Jeremy Bassy AGUMA, Principal Transport Economist,

Dodoma is the new administrative capital of Tanzania. The city is experiencing rapid urbanization, increased motorization, and increased transit of goods, all of which are driving the need for coherent urban development

The project involves construction of a new bitumen standard dual-carriage ring road (110.2km) around Dodoma City, drainage capacity improvement, roadside stops and dedicated amenities for truck drivers and other motorists, and other social amenities that include water sources, schools and health centres. A pilot road safety improvement around Dodoma City is also one of the other project interventions. Heavy vehicles will be diverted onto the Outer Ring Road to bypass Dodoma City centre. The project is economically viable with an EIRR of 35.4%.

Reduced transit times and less traffic congestion will consequently result in a reduction in greenhouse gas emissions and improve the quality of life for the 2.4 million people living in Greater Dodoma and surrounding regions. Tanzania’s efforts to address climate change challenges go a step further. An Urban Development component of the project will contribute to improving urban planning and management. Part of the funds are reserved for greening Dodoma through tree-planting on embankments of the Ring Road, and other areas within the City.

The Dodoma Ring Road will alleviate current bottlenecks from transiting vehicles crossing the city. The road will feature road safety features such as cycle lanes and vegetal road separators, as shown in this digital image. Pedestrian crossings will be placed at the approach to roundabouts.

28 Infrastructure and Urban Development II UU U 3% Govt. of Tanzania GEF Grant 2018 2023 USD 3.69M USD 5.7M 110 of road 15% 50in 20in 8 Counit 2 water source Transit Time for Trucks Transit Time for Trucks boreholes through Dodoma City through Dodoma City 19 CCTV surveillance 33.3% 31.0% % USD 220.39M cameras Poverty Level Poverty Level in Tanzania in Tanzania (Dodoma Region (Dodoma Region Africa 6 ambulances Growing Together Fund 63% ADB (loan) AGTF Loan USD 138M USD 2M

Approval Completion April December 2019 2020 202 2025 Effective November

Nairobi RWANDA KENYA

BURUNDI Mombasa

TANZANIA Dodoma

Dar es Salaam C en tra TANZANIA l co rri dor Veyula

Nala idor ntral corr Nala – Veyula - Ihumwa Ce Lake Sulunga 50.2km To Dar es Salaam Ihumwa-Matumbulu-Nala Ihlumwa 60.0km Dodoma

Matumbulu

Annual Report 2019 29 Gabon Infrastructure Sector Support - Phase I A strong contribution to economic development and regional integration Gabon Project Team Leader : Augustin KARANGA, Chief Transport Economist

The potential of Ngounié Province as a contributor to regional economic integration is undermined by the poor state of the Doussala-Ndendé section on the Libreville - Congo Border Road. The main road concerned by this project, as well as most of the feeder roads, are not motorable, especially during the rainy season.Timber, mining, metallurgy and the agro-industry all suffer from the difficulty to-market. The precarious rural situation has led to massive population exodus to the cities and hence a decline in agricultural production. Consequently, Gabon relies massively on imports, especially from neighbouring countries Congo and Cameroon.

Phase I consists of construction work which will contribute to the connection of the capital cities of Gabon and Congo. Studies will be conducted for the control of road investment costs and the future implementation of a corridor management system. Phase I also caters for urban development, with the construction of 21 km of roads and their related facilities in Libreville. The project will address the crucial need to open up production areas, improve mobility, diversify the economy, and reduce poverty for the population living along the Doussala-Dolisie corridor.

Main beneficiaries are the +100 000 inhabitants of Ngounié Province, with the 1 million population of Libreville also benefiting from the positive impact of the road.

This photo of road construction works financed by the AfDB on the Léyou-Lastoursville road in Gabon shows attention given to road safety. The new road project will provide a southern link to the national road network and a gateway to Congo.

30 Infrastructure and Urban Development II UU U

Africa Growing 2018 2023 Together Fund 32.58% AGTF (loan) 9 of road .8M 500 direct and indirect jobs created 19 of urban 10 our 8 our road netor Travel time on the 2 Travel time on the 137.6M Libreville-Mouila-Ndend- Libreville-Mouila-Ndend- Doussala highway section Doussala highway section 2 bus statons 25% 60% Rural Accessibility Rural Accessibility 1 en Inde Inde 67.2% staton The Rural Accessibility Inde is the proportion of the rural population ADB (loan) 92.8M within 2 km of a road passable

pproval ompleton December December 2019 2020 202 2025 ffectve May 2020

Libreville Libreville 21 km of urban roads

GABON

49 km Ndendé OSBP Doussala Ndendé GABON Nyanga Nyanga CONGO Kibangou

Brazzaville Dolisie

CONGO

Kibangou

Brazzaville

Dolisie 31 Multinational: Ethiopia-Djibouti Transport Corridor Phase I

Ethiopia The first stretch of a new Southern trade route to the Port of Djibouti. Project Team Leader : Mumina WA-KYENDO, Chief Transport Engineer

The 900 km Addis Ababa-Djibouti corridor handles more than 90% of Ethiopia’s imports and exports via Djibouti’s ports and the Galafi border. Ethiopian trade accounts for around 80% of Djibouti port activities. The current northern corridor is long and degraded.

The project involves the construction of the first 60 km of a new 4-lane toll highway stretching 126 km from Adama to Awash on the alternative southern corridor, passing through the Dewele / Gaulile border post. This route will be 120 km shorter and reduce transportation costs and carbon emissions.

The beneficiaries of the project will be the 0.5 million people living in the project area on the Ethiopian side. Additional beneficiaries will be people working in agriculture, trade and import-export sectors, and include 3,000 truck drivers who cover the 900 km of road that connect Djibouti and Addis Ababa, as well as young people, who will benefit from more 95% of the job opportunities expected during the construction phase. Djibouti will benefit from the development of trade, port revenues, jobs as well as bankable projects, and improved capacity in the management of the transport sector.

The Adama – Awash expressway project is an extension of the existing Addis Ababa - Adama Expressway pictured here, and will have similar features.

32 Infrastructure and Urban Development II UU U 2019 2028 ADF (Loan) UC 73.M 60 50% of Ethiopian 0% of highway import/export transit through the border at Dewele 1000 obont 2 936 3 718 UC 18160M created Average daily traf c Average daily traf c

1. our 1 our Journey time from 2 Journey time from Adama to Awash Adama to Awash 60% Govt Ethiopia UC 108.16M

pproval ompleton July December 2019 202 2025 2026

Djibouti

ETHIOPIA r o

d

i

r

r

o c Djibouti - Addis Ababa

rn 900km e h t SOMALIA r o

N or rid outhern cor S w e N

Addis Ababa Awash 60km

Adama

To Moyale, Annual Report 2019 33 Kenya border Ghana: Eastern Corridor Road Development II UU U Govt. of Ghana UA 4.72M 2019 2024 Programme OFID 6% 62.1 km of road, UA 14.29M including 2 15 days 9 days A strategic trade corridor from Ghana’s coastal region to the 24h Ghana interchanges transit time transit time for goods hinterlands 19% between Ghana and Burkina Faso Project Team Leaders: Mam Tut WADDA, Principal Transport Engineer and Sheila Akyea, 1,500 (30% women) receive TVET support 2 hours 1 hour Senior Transport Infrastructure Engineer 24h UA 77.31M and 500 youth (40% Tema to Asikuma Tema to Asikuma women) benefit from travel time travel time The Central Corridor which links Ghana’s coast to the northern hinterland suffers chronic congestion, particularly in the urban Labour Intensive zones it crosses. The Eastern Corridor provides a strategic alternative route. Road accident mortality Public Works; rate reduced by 40% Phase 1 of the Eastern Corridor Road Development Programme includes road construction and civil works whilst incorporating 75% 15 schools, 1,500 direct jobs (at least ADF (loan) 6 health facilities 30 women) during community support activities. The project envisages to turn challenged rural areas along the road corridor into economically UA 58.3M and 3 markets construction and 850 prosperous bread baskets. On completion, the roads will be tolled and axle weighing facilities will be provided to control constructed/ indirect jobs (250 youth overloading and contribute towards government’s efforts to assure the sustainability of the road infrastructure. rehabilitated – at least 40 women).

The main objective of the project is to contribute towards an efficient transportation system that promotes Ghana’s ports and corridors to enhance inclusiveness, stimulate socio-economic development and facilitate domestic and regional trade and Approval Completion integration. It will address the needs of an estimated 230,000 people and impact the lives of over 5.4 million inhabitants. From June June 2024 2025 the outset, the project will address the human capital deficit in the construction sector by training over 500 youth (at least 40% 2019 2020 Effective female) in skills such as masonry, steel fixing and auto mechanics. Longer term job creation will be achieved through the support February of District and Community Level Agro-Processing Facilities for women and youth.

CÔTE D’IVOIRE GHANA

Asikuma junction Interchange

39 km

GHANA Dufor Adidome Interchange 23 km Lome

Asutsuare Sogakope junction

The upgraded Fufulso-Sawla road has improved economic opportunities in the Northern Region of Ghana. The 2019 Eastern Corridor project aims to replicate the success. Tema 34 Infrastructure and Urban Development 34 Infrastructure and Urban Development II UU U Govt. of Ghana UA 4.72M 2019 2024 OFID 6% 62.1 km of road, UA 14.29M including 2 15 days 9 days interchanges transit time 24h transit time for goods 19% between Ghana and Burkina Faso 1,500 (30% women) receive TVET support 2 hours 1 hour 24h UA 77.31M and 500 youth (40% Tema to Asikuma Tema to Asikuma women) benefit from travel time travel time Labour Intensive Road accident mortality Public Works; rate reduced by 40% 75% 15 schools, 1,500 direct jobs (at least ADF (loan) 6 health facilities 30 women) during UA 58.3M and 3 markets construction and 850 constructed/ indirect jobs (250 youth rehabilitated – at least 40 women).

Approval Completion June June 2019 2020 2024 2025 Effective February

CÔTE D’IVOIRE GHANA

Asikuma junction Interchange TOGO

39 km

GHANA Dufor Adidome Interchange 23 km Lome

Asutsuare Sogakope junction

Tema Annual Report 2019 35 Accra Nigeria: Ebonyi State Ringroad II UU U 2019 2025 A strong contribution to the agriculture sector and to the ADB (Loan) 178 of roads USD 22M rehabilitated Nigeria national economy. 6 our 3 our 2% Vehicle journey time 2 Vehicle journey time Project Team Leader : Patrick MUSA, Senior Transport Engineer Islamic 1 500 construction on sections on sections Development 8% jobs created Bank (IsDB) USD 1.1 USD 0.8 USD 80M USD 150M Vehicle operating Vehicle operating Ebonyi State is well known for the production of and . Other cash crops produced in the region are yam, cashew 60 youths costs/ km costs/ km trained nuts, , cocoa and rubber. There is a very high potential for improvement in agricultural productivity (1.12 MT annual 0 1.2 iion Rural Accessibility yield of rice with a potential 1.375 million and 1.3 MT annual yield of cassava with a potential 2.1 million), yet the movement 17% Rural Accessibility coo Inde Inde of agricultural produce is heavily impacted by the poor condition of the road. Most sections of the road have lost their asphalt Africa Growing rehabilitated Together Fund The Rural Accessibility Inde is the proportion of the rural population surfacing, and some sections become impassable during the rainy season. The main form of transportation in most of the (AGTF) within 2 km of a road passable project areas is by bicycle and walking, resulting in spoilage at farm gate and en-route to markets. USD 30M

In addition to rehabilitation and upgrade of the ringroad, the project contains a capacity building components and a Social Infrastructure component to stimulate opportunities and provide the population with the means to develop their commercial pproval ompleton December activities. October 2019 2020 2025 2026 The road is expected to serve as an international link between Ebonyi State and the Republic of Cameroon, and to provide ffectve interstate access between Ebonyi, Benue and Enugu States. It will serve as a link connecting farming communities in the 13 January Local Government Areas, accounting for 70% of the State population.

NIGERIA DII NIGERIA EBONYI EBONYI STATE STATE Population 2.2 million II Izzi

Ohaukwu

Ebonyi Ishielu

Abakaliki

Ezza North

Ezza South Ikwo

36 Infrastructure and Urban Development II UU U 2019 2025 ADB (Loan) 178 of roads USD 22M rehabilitated 6 our 3 our 2% Vehicle journey time 2 Vehicle journey time Islamic 1 500 construction on sections on sections Development 8% jobs created Bank (IsDB) USD 1.1 USD 0.8 USD 80M USD 150M Vehicle operating Vehicle operating 60 youths costs/ km costs/ km trained 0 1.2 iion Rural Accessibility 17% Rural Accessibility coo Inde Inde Africa Growing rehabilitated Together Fund The Rural Accessibility Inde is the proportion of the rural population (AGTF) within 2 km of a road passable USD 30M

pproval ompleton October December 2019 2020 2025 2026 ffectve January

NIGERIA DII NIGERIA EBONYI EBONYI STATE STATE Population 2.2 million II Izzi

Ohaukwu

Ebonyi Ishielu

Abakaliki

Ezza North

Ezza South Ikwo

37 DRC: National Road No.1 Rehabilitation Kinshasa/Ndjili – Batshamba Section A key road to the interior and an important facilitator of regional DR Congo integration. Project Team Leader : Anatole BIZONGO, Senior Transport Engineer

The RN1 is a major corridor for internal and inter-regional transit and trade between Central Africa, East Africa, and Southern Africa. The Kinshasa-Batshamba link, including the 72.80-km Kwango-Kenge section financed by the Bank, is currently badly degraded due to erosion which could potentially cause the road to collapse.

The project follows the existing road along the section from Moanda to Kasumbalesa. and covers land with very variable relief. The Government has devoted most funding from donors involved in the transport sector to its gradual rehabilitation. The project will serve to safeguard and ensure the sustainability of investments, for year-round connectivity. The construction of parking areas around urban centres (Bankana, Kenge, Masimanimba and Kikwit) and speed limit measures and signs will help reduce the risk of accidents. The project intends to treat embankments and cuttings along the RN1 with systematic revegetation to reduce erosion on ditches, drains and collectors.

Beneficiaries are the inhabitants of Kinshasa and of the provinces Mai Ndombe, Kwango, and Kwilu, particularly traders and farmers, for whom the road will improve food security, increase the availability of agricultural products, reduce travel time and build the capacity of support services.

38 Infrastructure and Urban Development II UU U 2018 2024 622 of road + 131 of feeder 11 2 8 road in 2021 Travel time 2018 Travel time 2024

1500 out 232 357 trin Average traf c Average traf c UA 50.57M 5 rt 55680 tonn 9099 tonn constructed Goods transported Goods transported ADF Loan UA 50.57M Rttion USD 380 USD 660 of embanments Farmers monthy Farmers monthy income income

pproval ompleton June November

2019 2020 2021 2022 ffectve December

GABON

DEMOCRATIC REPUBLIC OF REPUBLIC OF CONGO CONGO

Kenge Kinshasa Kikwit

Batshamba

ANGOLA Annual Report 2019 39 Multinational DRC-Congo: Access Roads to the Road-Rail Bridge over the Congo River Part of a holistic project to link capital cities and improve DR Congo regional integration. R.Congo Project Team Leader : Augustin KARANGA, Chief Transport Economist

The construction of a road-rail bridge between Kinshasa and Brazzaville will link two fast-growing cities across the Congo River border and take into account traffic growth prospects, the continued urbanisation of both Kinshasa and Brazzaville and the establishment of special economic zones in Maluku in the Democratic Republic of Congo (DRC) and Maloukou in the Republic of Congo (RC).

The access road links leading to the bridgeheads are 10 kilometres long, of which 6.8 kilometres on the left bank (DRC) and 3.2 kilometres on the right bank (RC) of the Congo River. The first phase of the project will cover the construction of the 6.8km access roads on the DRC side and studies on other infrastructure, including the Kinshasa bypass and on access roads on the RC side.

The project is in line with the drive to develop border trade on RDC’s four main trade corridors, in the North with Brazzaville- Douala, in the East, with Brazzaville-Kinshasa, and in the South with Cabinda-Nzassi and along the Dolisie-Doussala highway. The main project beneficiaries are finance, trade, transport, mining, electricity and agricultural sector operators. Local and foreign enterprises in both countries and private carriers will benefit from the facilities developed by the project, as will the 700 000 inhabitants of Maluku and the 30 000 persons expected to move to the Maloukou Special Economic Zone.

A digital representation of the future bridge over the Congo River. As part of a holistic regional integration project, the Bank is financing access roads to the bridge, improving the future road link between the capitals Kinshasa and Brazzaville.

40 Infrastructure and Urban Development II UU U 2019 2025

6.8 RRB-Maluku 39 r tonn 26 r tonn road section in DRC Average Freight cost Average Freight cost developed as a dual carriageway 750 000 1 900 000 ADF (loan) Number of passengers Number of passengers UA 0M UA 0M Studies for Pointe Noire - Kinshasa Pointe Noire - Kinshasa upgrading access roads and special 2 200 000 T 500 000 T economic zones Freight traf c Freight traf c Pointe Noire - Kinshasa Pointe Noire - Kinshasa

ase I ompleton roect pproval December December 2019 2020 2023 202 ffectve February 2020

Studies for the construction of: 23 km long Yié-Maloukou road section Maloukou and the 3.2 km access road to the bridge; Special Economic Zone Reinforcement of the 26 km long Igné-Maloukou Tréchot road section

REPUBLIC OF Brazzaville CONGO

Maluku DR CONGO Special Economic Zone Studies for the construction of: Construction 27 km long Maluku-RN1 Junction road of 6.8 km section and Kinshasa bypass road access road

Kinshasa Annual Report 2019 41 Multinational: Nacala Road Corridor Development Project Phase V Continued development of a strategic corridor with road Malawi construction in Malawi and border facilities with Mozambique. Mozambique Project Team Leader : Davies MAKASA, Principal Transport Engineer

Malawi depends on international transport corridors leading to the seaports for its imports and exports. The Nacala Road Corridor is the shortest route to the seaport from Malawi yet due to the poor road infrastructure and lengthy clearing processes at the border crossing, only 15% of the country’s international trade transits the corridor.

Phase V of the Nacala Road Corridor Project will contribute to maximizing the economic benefits of the on-going project phases III and IV. The project involves the rehabilitation of a 55 km road between Nsipe and Liwonde and the construction of a one-stop border post between Malawi and Mozambique at the Chiponde-Mandimba border post, financed on the Mozambique side under Phase III of the project. Works in Phases I and II, financed by the Bank in 2012, have since been completed. The projects have enabled the rehabilitation to bituminous standards of over 1,165 km of road in Malawi, Mozambique and Zambia, and an ongoing construction of a OSBP between Malawi and Zambia at the Mchinji-Mwami border post.

The beneficiaries include an estimated population of over 2 million people who use the Nacala Road Corridor for personal travel and economic activities. Other beneficiaries include import and export firms in Malawi, Zambia, and northern Mozambique and tourists.

Photo of the Mangoche section the Nacala Corridor Development project. Financed by the Bank, the section was completed in 2019.

42 Infrastructure and Urban Development II UU U Govt of Malawi UA 3.57M 2018 2025 7.9%

55 1% 2 25% of road Trade volume Trade volume

1 OSBP 1.5 our 50 in. UA 5.28M Travel time from 2 Travel time from EU Africa Nsipe to Liwonde Nsipe to Liwonde Investment 00 Job Platform created 2 our 6 our Grant Wait-time for cargo traf c Wait-time for cargo traf c UA 50.57M 33.% 58.7% ADF Loan UA 26.60M

pproval ompleton June November 2019 2020 202 2025 ffectve December

Mchinji OSBP ZAMBIA – Construction works On-going under Nacala Road corridor Project Phase IV

Lilongwe Chiponde OSBP

Mangochi-Liwonde Mangochi Chiponde Construction works completed in 2019 Nsipe Feasibility Liwonde study

iver zi R be am Z MALAWI

MOZAMBIQUE

Annual Report 2019 43 Niger: Tamaske-Tahoua and Tamaske- Mararraba Roads Development Niger Support for improved resilience and and trade opportunities.

Project Team Leader : Jean Noel ILBOUDO, Division Manager

As the main migrant route to the Sahara and Europe, Niger is a key transit country for migratory flows and is also prey to illegal trafficking in contraband. The economy of Niger is largely dominated by agriculture and , but movement of goods to market is thwarted by the poor state of the road. Aware of the critical role that transport plays in the Niger economy, the Government has allocated significant resources in recent years to improve transport sector performance, despite the context of a drop in prices and heavy pressure from security and humanitarian challenges.

The project road will connect the Keita and Tahoua Divisions of Niger, a region with high agro-pastoral potential. It includes financing of a building for youth training in light industry such as masonry, stone cutting, mechanics, welding and carpentry, and market sheds for agricultural produce.

Beneficiaries are the 4m people living in the district, particularly the 400 000 in the project area, who will gain job opportunities and enhanced access to basic social services. The road will open up several localities in Tahoua region thereby contributing to revitalising the local economy, improving food security and building resilience among the youth and poor segments of the population.

Preparing the road apron at PK185, part of the works on the -Assamaka road in Niger, financed by the Bank in 2013

44 A TSF Grant UA 2.51M 2019 2023 9% 65 K of road 00 000T 0 000T production Cereal production 3 rooo processing units A constructed 5 our 2 1.5 our UA 29.6M Average travel time Average travel time TSF Loan 1300 tr for a HGV for a HGV UA 11.1M 38% planted Transition 53% Support Facility ADF Loan UA 15.81M

Approal opleton October December 2019 2020 2023Tchin-Tabaradene 202 ete March 2020

Taza

NIGER MALI

Abala Mararraba Kaloma Tahoua Tamaské Kalfou Keita Bagaroua

Dakoro Bouza

Madaoua

Mararaba

Tahoua Kaloma

Kalfou Annual Report 2019 45 Tamaské Comoros: Road Network Rehabilitation - RN2 (Moroni – Foumboumi) Comoros The Moroni - Ouroveni Section will continue the investments made in sustainable road development on the islands. Project Team Leader : John NDIKUMWAMI, Transport Engineer

Road infrastructure constructed in Comoros in the 1980s and 1990s has deteriorated due to lack of regular maintenance. The dilapidated sections targeted by this project account for 57.6% of the total road network which carries 90% of the goods and passenger traffic in Comoros. Phase I of the Road Network Rehabilitation was approved in 2017, but a funding gap reduced the extent of planned construction.

Supplementary financing will allow the continuation of works started in 2018 in addition to ancillary works to protect the coast from marine intrusion and climate change-induced floods. The new road coating will withstand higher temperatures and the capacity of road drainage systems will be increased. Climate resilience of existing infrastructure will be reviewed to strengthen and protect bridge structures, to raise the elevation of the road and increase the solidity of retaining walls.

The rehabilitation and extension of the national road network will contribute to the development of the tourism and fishing sectors, identified as potential growth poles for the national economy. The new financing package also provides support for the financial empowerment of women in the project area, who will for example be enabled to smoke and package fish.

46 Infrastructure and Urban Development A Govt of Comoros 1% UA 0.16M 2016 2022 68.5 of road 30% 3639 85 1 rir bri on RN2 on RN2 ADF Grant A 1. r 0.8 r UA 6.97M 12 oun ninr travel time 2 travel time UA 23.20M trained on RN2 section on RN2 section

Entrepreneurship 30% 10% training for Losses in sh trade Losses in sh trade 69% 500 on ADF Loan UA 16.07M

Approal opleton November December 2019 2020 2022 2023 ete December

GRANDE COMORE

Moroni COMOROS

Mitsoudje

Panda Ifoundihe Ourovéni Chambouani

Sima ANJOUAN

Moya Multinational: Mueda–Negomano Road Upgrading Phase II Enabling regional trade and a better quality of life for inhabitants of the project area. Mozambique Project Team Leader : João Mabombo, Senior Transport Engineer

The Mueda – Negomano road section is an important link along the Mtwara Corridor to the border with Tanzania at Unity Bridge. The road link to the bridge on the Mozambican side has remained unpaved and in poor condition. Heavy Goods Vehicles spend up to a week to travel the full length of the road of only 163km during the rainy season. The main cash crop is , yet the value chain is small and localized due to spatial exclusion imposed by the Zambezi River and and poor road links to markets.

The current Phase II (Lot A) financing serves to extend the strecth financed by the Bank in Phase I beyond Roma to Mueda. The section will be upgraded to a 7 metre wide bituminous standard road, properly signed and with all the bridges and culverts rehabilitated. It will include the construction of access roads, weigh bridges, roadside stations, and a cycle lane, in addition to support for women’s entrepreneurship environmental and social mitigation measures along the corridor, especially water-related facilities to ease the burden of water collection.

Journeys to the ports of Pemba in Mozambique and Mtwara in Tanzania will be more direct, effectively enhancing regional integration and trade opportunities for the 1.8 million people living in the .

48 A

Govt of 2019 2024 Mozambiue UA 0.39M 35 of road USD 10 iion USD 30 iion Annual trade volumes Annual trade volumes between Mozambiue between Mozambiue A 1 Trinin cntr and Tanzania and Tanzania constructed UA 2.8M 1 our 26 in Travel Time 2 Travel Time Roma- Nambungale Roma- Nambungale TSF Grant Primary schools UA 12.00M and 2 health centres 10 rnnt ob rehabilitated created for youth 300 ob opportunities ADF Grant during construction UA 12.09M

Approal opleton October December 2019 2020 2022 2023 ete December

Mtwara Mtwara

TANZANIA

MOZAMBIQUE Pemba

Roma 3 bridges along the section MOZAMBIQUE Mtambaswala

Negomano Nambungale

Mueda

Annual Report 2019 49 Multinational: Lake Tanganyika Transport Corridor Development Burundi Phase I concerns the rehabilitation of Bujumbura Port, opening up new possibilities for maritime transport. Project Team Leader : John NDIKUMWAMI, Senior Transport Engineer

Transport on the Tanganyika Lake Corridor is hampered by inadequate port and navigation infrastructue and lack of harmonised measures to facilitate cross-border trade and movement of people. Infrastructure at Bujumbura Port has not been upgraded since the port was built in the 1950s and therefore cannot meet future demand.

The project involves upgrading and expanding port infrastructure, including the number of quays and the basins for navy bessels. Port facilities will also be acquired, including cranes, patrol and rescue ships, and lighthouses.

The rehabilitation of Bujumbura Port will reduce port of call times for vessels and increase the capacity of terminal, thereby creating economic opportunities and stimulating cross-border trade with countries bordering the lake. Additionally, the rehabilitation of the port will unlock multimodal transport potential via the railway and the lake, thereby offering a more cost-effective, safe and environmentally friendly transport mix for the 1.25 million inhabitants, 53% of which are women. The project will also boost trade in a wide range of agricultural, manufactured and fishery products.

50 Infrastructure and Urban Development A Govt of Burundi USD 1.76M 2019 2023 5% ADB (Grant) 38.5% USD 1.07M 590of uay 28 TEU 25 000 TEU constructed Container capacity Container capacity 0 15 000 EU (Grant) 3% A Number of Number of USD 15.78M 11 of access USD 36.55M roads to the port passengers passengers 1.1 Vessel waiting time Vessel waiting time 3 itou 13.5% TSF (Grant) 665 Job USD .9M created UGANDA Approal opleton December December 2019 2020 Kampala 2023 202

RWANDA

Lodja BURUNDI Bujumbura

DR CONGO

Kigoma

Lake Tanganyika

Kalemie TANZANIA

Mbeya Annual Report 2019 51 ZAMBIA Mpulungu Somalia: Road Infrastructure Programme

Somalia An important contribution to value chains in the livestock and agriculture sectors, and an adequate response to fragility. Project Team Leader : Jumbe Katala, Senior Transport Engineer

Transport infrastructure in Somalia has suffered from years of neglect. Their condition has deteriorated in particular due to the difficulties encountered in carrying out maintenance and improvement works in the difficult prevailing institutional and security context.

The total length of the country’s main roads is 4,124 km, of which 2,860 km are surfaced and 1,264 km are unpaved or gravel. 90% of paved roads are severely degraded and unsuitable for vehicles. Restoring and improving connectivity is essential for economic revitalization and political integration.

The project area is home to a population of over 2 million people who will benefit from improved connectivity, reduced travel time and transportation costs, and a better quality of life. This project will offer employment opportunities to women and young people; Project communities will also benefit indirectly from the improved environment and economic activities. Along the Galkayo-Hobyo section for example, the population suffers from severe water scarcity, with families collecting water runoff from the road. A budget of $0.68M for ancillary works will serve to drill boreholes and build solar water systems for these communities.

52 Infrastructure and Urban Development A

ADF Grant 2019 2025 UA 7.5M 16% 16 % GDP 25% GDP 175 of Volume of eports Volume of eports TSF grant 10% asphalt road UA 6.63M A 180 of gravel road 3 20 in 1 0 in UA 5.9M Average journey 2 Average journey Govt of time (100 km) time (100 km) Somalia 6% UA 2.83M 2 500 tr planted 27 327 Vehicles/day Vehicles/day 68% EU Grant UA 30.9M 300 ob created

Approal opleton July December 2019 2020 202 2025 ete September

Garowe

ETHIOPIA Galkayo

82 km of road rehabilitated with gravel

327 km 241 km Hobyo 164km of road asphalted

Beledweyne

Dolow SOMALIA 80 km of road rehabilitated with gravel Luuq

KENYA

Mogadishu Annual Report 2019 53 Digital Masterplan and Capacity Building Programme for the Greater Banjul Area Technical assistance to assist the Gambia in achieving The Gambia sustainable urban development. Project Team Leader : Victoria Flattau, Senior Urban Development Officer

The Gambia has one of the fastest urbanisation rates in Sub-Saharan Africa, with the Greater Banjul Area already accounting for 68% of the population. Environmental and socio-economic problems have arisen from uncontrolled urban sprawl: deforestation, soil pollution, pollution and waste, in addition to stress on social services.

The project comprises three components. Firstly, project financing will assist in producing a Greater Urban Digital Masterplan for Banjul. Secondly, as part of a capacity building initiative, authorities will be assisted in setting up innovative mechanisms to manage revenue collection, enable development action and leverage private investments in infrastructure, all with the aim of ensuring the sustainability of metropolitan investments. Thirdly, technical support will enable the municipality to set up coordinated and unified platform for project management, with the ability to interpret new data, manage land and recover revenue, among others.

The Bank’s Urban and Municipal Development Fund will offer assistance in urban planning to the Government of the Gambia, Banjul City Council (BCC), Municipal Council, and Brikama Area Council, the Gambia Port Authority and the Ministry of Lands and Regional Government in the Gambia.

54 Infrastructure and Urban Development A 2019 2022 Digital Masterplan Uncontrolled Sustainable 3 Urban encroachment of environmental protection wetlands of the peninsula A development investment plans UA 2.15M Lack of bankable Increased private 5 Ministries receive projects investments in urban TSF training in Project infrastructure (Transition Management States Facility) UA 2.15M

Approal opleton Q1 2019 Q4 2021 2019 2020 2021 2022

Ebo Town -low-lying unplanned Banjul Port GREATER BANJUL AREAdistrict prone to ooding

Wetlands, including River Gambia mangrove swamps being encroached upon

Population 1.2 M in 2000 2.3M in 2019

Annual Report 2019 Banjul 55 International Airport Bangui-Mpoko International Airport Modernisation Support Project – Phase I Raising safety and security standards in the Central African CAR Republic’s only international airport. Project Team Leader : Augustin KARANGA, Chief Transport Economist

Bangui-Mpoko is the Central African Republic’s only international airport. Commissioned in 1967, it no longer meets the operational requirements of a modern international airport in terms of security, safety, available surface area, arrival capacity, passenger processing, baggage delivery times, facilitation and amenities offered to operators. Failure to meet ICAO Recommended Standards and Practices could ultimately lead to its closure to leading regional and international airlines.

Despite the poor level of service, international traffic rose by 10% between 2017 and 2018 to reach 339,000 passengers. The project is designed to enable the airport to cater for more passengers, with modern equipment for luggage handling and screening. It will be implemented in two phases, with phase I consisting of works on the air terminal and phase II financing complementary works and capacity building of the Civil Aviation Administration.

The project will be a source of construction-related short-term jobs using unskilled labour, including women and young people. In the operational phase, the project will create jobs by contributing to the development of passenger and freight transportation particularly in the agricultural, trade and tourism sectors, in addition to job creation in airport services. Air travellers will benefit from new airline destinations, greater comfort, more regularity and enhanced flight security.

56 Infrastructure and Urban Development A TSF grant 2019 UA 0.12M 2022 11% 2 complete baggage conveyor systems installed 372000 50000 Number of Number of 11 baggage drop-off passengers / year passengers / year and weighing belts A 2 000 ton 5 000 ton UA 1.12M 6 curit cc Freight traf c level Freight traf c level oint equipped / year / year

Sor n 8% Compliance rate 50% Compliance rate irconitionin for (with government (with government terminal building standards) standards) 89% ADF Grant UA 1M

Approal opleton October December 2019 2020 2022 2023

ete October

Casablanca

Agadir

To Paris

BENIN CAR CAMEROON Bangui Mpoko Airport Cotonou Lome Yaoundé TOGO UGANDA Douala Entebbe KENYA Nairobi CONGO Brazzaville

Luanda Annual Report 2019 57 Abia State Integrated Infrastructure Development Preparation Studies Nigeria A holistic project to improve roads and waste management.

Umuahia, the Capital of Abia State, and Aba, the commercial hub, are both characterized by serious infrastructure deficiencies. Over 95% of the roads are in poor and the situation is compounded by gully erosion and illegal dump sites on roadsides.

A feasibility study and detailed engineering design are planned to bring the project to bankability stage.

The development objectives of the studies are the reduction of transport costs for the combined populations of around 1 million people, through the rehabilitation of the road network to all-weather standard, gully erosion control, improved sanitation in the two cities and support for institutional reform.

Approval Completion Janv. December 2019 2020 2021 Effective March

FINANCING ASG 8% UA 0.1M

TOTAL COST USD 1.3M

92% Middle Income Country TA Grant UA 1.3M

58 Infrastructure and Urban Development NEPAD-IPPF

The New Partnership for Africa’s Development Infrastructure Project Preparation Facility (NEPAD-IPPF) Special Fund, hosted by the African Development Bank, is a leading project preparation facility in Africa which plays a catalytic role in mobilizing resources for preparation of regional projects and programmes.

The NEPAD-IPPF is currently supported by the African Development Bank and receives regular or targeted funds from , , United Kingdom, , , and . Participation in the special fund is open to donors, institutional funds and other special infrastructure funds.

Description of NEPAD-IPPF Project Preparation Funding in 2019

22 Standard Gauge Railway connecting Ethiopia and Sudan P 60 23 Corridors Study: Algeria-Tunisia borders P 61 24 Ghana-Burkina-Mali Power Interconnection Phase II P 62 25 Côte d’Ivoire-Liberia Interconnection P 63

59 Standard Gauge Railway connecting Ethiopia and Sudan

East The Ethiopia-Sudan Standard Gauge Railway project will improve transport connectivity Africa between two neighbouring and trading countries and provide an alternative seaport access for land-locked Ethiopia. The IPPF intervention aims to attract PPP investors.

A A Counterpart Contribution 7% USD 0.2M Conduct a feasibility study Increased traf c & trade volumes Analyse a potential Public between the two Private Partnership (PPP) countries A model USD 3.M

3% NEPAD-IPPF ADF (Grant) 59% USD 1.2M USD 2M

Planned Approval completion July July 2019 2020 2021 2022

Port-Sudan

Haiya

SUDAN

Kassala

Al-Qadrarif

Al-Galabat Métemma Gondar

Wereta Weldiya DJIBOUTI

60 SOUTH ETHIOPIA SOMALIA Addis-Ababa SUDAN Corridors Study: Algeria-Tunisia borders

North Africa Development of a transport corridor and a logistics zone to facilitate regional trade between Algeria, Tunisia, and . The IPPF intervention aims to implement a PPP business model.

A A A A Counterpart Govt of Tunisia Contribution 7% Conduct a feasibility and USD 0.186M 16% Increase in trade USD 0.2M design study Conduct a feasibility study Increased traf c between the countries of the & trade volumes Prepare tender documents Analyse a potential Public between the two Arab Maghreb Private Partnership (PPP) Union countries Analyse eligibility for PPP A model A USD 3.M USD 1.186M NEPAD-IPPF 3% NEPAD-IPPF ADF (Grant) 59% USD 1M USD 1.2M USD 2M 8%

Planned Approval completion Approval Completion July July June December 2019 2020 2021 2022 2019 2020 2021 2022

Port-Sudan

Sbeitla Haiya Bouchebka border post Gitaza

Thélepte SUDAN TUNISIA Sfax ALGERIA Kassala ERITREA Gafsa

Al-Qadrarif Tozeur Al-Galabat Métemma Gabès Gondar

Wereta Weldiya Hazoua Zarzis DJIBOUTI border post

Medenine

Ras Jedir SOUTH ETHIOPIA SOMALIA 61 Addis-Ababa SUDAN Ghana-Burkina-Mali Power Interconnection Phase II

West The project wll increase interconnectivity and enhance the reliability of power exchanges of Africa the West African Power Pool (WAPP) through the diversification of electricity provisioning. The IPPF intervention aims to bring the project to bankability stage.

A A A A

Conduct a feasibility study, Eports represent represent Eports study, feasibility a Conduct 8% AFD AFD % 8 USD 2.18M Prepare engineering design design engineering Prepare 2.18M USD Prepare tender documents 15% 15% documents tender Prepare A of the capacity of of capacity the of A the line by 2024 2024 by line the orld Bank 38% USD .5M Conduct an ESIA with a a with ESIA an Conduct .5M USD % 8 3 Bank orld USD 1.7M Resettlement Action Plan Plan Action Resettlement 1.7M USD

1% NEPAD-IPPF NEPAD-IPPF 1% USD 0.61M 0.61M USD

Approval Completion ompletion C Approval June June June June 2019 2020 2021 2022 2022 2021 2020 2019

MALI MALI

Sikasso BURKINA FASO FASO BURKINA Sikasso Bobo Dioulasso Dioulasso Bobo

330 kv kv 330 700 km of of km 700 transmission line line transmission Bolgatanga Bolgatanga

CÔTE D’IVOIRE D’IVOIRE CÔTE

High voltage GHANA GHANA voltage High transmission line line transmission High voltage substation substation voltage High

62 Infrastructure and Urban Development Côte d’Ivoire-Liberia Interconnection

The interconnection is a priority project in the ECOWAS Master Plan for the Development West of Regional Power Generation and Transmission Infrastructure 2019 - 2033. The IPPF Africa intervention aims to bring the project to bankability stage.

A A A A

Eports represent represent Eports study, feasibility a Conduct AFD % 8 6% design engineering Prepare Feasibility Study and Exchange Preparation of Bidding2.18M USD 15% 15% documents tender Prepare Documents of the capacity of of capacity the of 10% A USTDA 2024 by line the Line Route and Environ- of the energy A a with ESIA an Conduct .5M USD % 8 3 Bank orld USD 1.57M Plan Action Resettlement mental and Social Impact capacity of the USD 3.5M Assessment Study line by 2024 1.7M USD NEPAD-IPPF USD 1.88M

NEPAD-IPPF 5% 1% USD 0.61M USD

ompletion C Approval Palnned ApprovalJune completion June 2022 July 2021 2020 July 2019 2019 2020 2021 2022

Intersection with the 225 kV MALI Côte d’Ivoire – Liberia – Interconnection and with the OMVG interconnection FASO BURKINA Sikasso Bobo Dioulasso Dioulasso CÔTE Bobo D’IVOIRE Tiboto Buchanan 330 kv kv 330 LIBERIA of km 700 Intersection with the WAPP transmission line transmission Coastal Transmission Backbone1 Bolgatanga that spans from Nigeria to Côte d’Ivoire 599 km transmission lines

Greenville San Pedro Installation of SCADA and D’IVOIRE CÔTE bre optic systems (OPGW) GHANA voltage High High voltage line transmission transmission line substation voltage High High voltage substation

Annual Report 2019 63 64 Infrastructure and Urban Development Infrastructure and Urban Development Active Project Portfolio

Annual Report 2019 65 Implementation Status of Selected Ongoing Projects

The Accra Urban 65% Transport Project complete in 2019 In 2016 the ADF approved a UA 60 million loan for the Accra Urban Transport Project in Ghana's capital. Scheduled for completion end 2021, the project has reached 60% disbursement and is approximately 65% complete.

The objective is to improve urban mobility and livelihoods in the project area of influence. A major component of the works, the Pokuase Interchange will facilitate traffic between two key roads, the Tema-- corridor and the Awoshie-Pokuase road, both financed by the Bank.

Community support began in the last quarter of 2019 The four-tier Pokuase interchange with 10km of feeder roads including support to the local women’s group and procurement of school equipment.

The Arusha - Holili/ Taveta-Voi Road

The Arusha-Holili/Taveta-Voi Road between Tanzania and Kenya links the Northern Corridor at Voi to the Central Corridor across the common border at Holili/ Taveta through Arusha, Babati to Dodoma and Singida. Approved in 2013, ADF loans of UA 80 million and UA 75 million to the respective governments were disbursed at around 75% in 2016. The new road was commissioned in 2019.

The Project Completion Report of November 2019 found that all the expected outcomes of the project related to increased cross border trade and tourism had been achieved and often exceeded. Socio- economic benefits have also exceeded the initial targets. For example, over 2 300 new jobs have Completed been created in Tanzania, compared to the original in 2019 estimation of 1500. Also, the improved road has attracted new investors in the Education sector, including two new higher education campuses.

66 Infrastructure and Urban Development The Liwonde-Mangochi Road

Approved in 2013, the 51 million UA financing by the Bank for the 75km road between Malawi and Zambia was completed in Sept 2019. The road construction, under the Nacala Road Corridor Development Phase 4, included 2 large bridges which have considerably reduced travel time along the stretch. The districts covered by the road have a combined population of approximately 1,3 million, comprising 70% youth. The road construction has created around 100 permanent jobs.

Completed in 2019

Annual Report 2019 67 Active Projects Portfolio 2019 An overview of ongoing infrastructure and urban development projects per country, and the amounts committed by the Bank, end 2019.

7 TUNISIA 970.2bn MOROCCO 671.9M 4 ALGERIA LIBA EGPT

1 2 2 CABO VERDE 33.8M MALI NIGER 59.4M 151M ERITREA 162.1M SUDAN 704.8M 2 GAMBIA 8 BURKINA 110M 100M 2 FASO DIBOUTI 1 342.2M 3 4 5.2M GUINEA- 2 GUINEA 21.6M 237.6M 6 NIGERIA 6 CTE 3 5 7 SIERRA LEONE 3 D’IVOIRE 305.6M 1 76.8M GHANA 6.6M ETHIOPIA 1.079Bn 6 SOUTH SUDAN 4 280.9M 8 CENTRAL AFRICAN 737.2M LIBERIA 10 REPUBLIC 10.7M CAMEROON 2 1 215M TOGO 1.016Bn 237.4M UGANDA SOMALIA EUATORIAL 965.1M 7 16.6M GUINEA GABON CONGO 6 KENA 352.6M 181.6M 6 1.071Bn 197M DEMOCRATIC 3 3 REPUBLIC RANDA OF CONGO SAO TOME 323.1M 4 425.37M TANANIA BURUNDI 1.942Bn 302.2M 10 9 COMOROS 2 53.1M 1 ANGOLA MALAI 233.7M 4.5M AMBIA LEGEND 329.8M 4 non portolo e 4 7 1 1 MOAMBIUE n IMBABE 1.6M 628.1M 0 - 100M 1 1.4M 2 BOTSANA 157.3M 101 - 499M 140M

500 - 999M ESATINI 2 1Bn 75.6M 3 1 Number of projects 801.4M

68 Infrastructure and Urban Development Portfolio Breakdown

Total portfolio Sovereign Non sovereign USD 16.03 billion 13,92 billion 2.11 billion

Ar ranport ort ea USD 1.15 md ranport USD 309.78 M ran USD 1.36 md 9% ort Ara 1.66 md 32% 13% at Ara entral Ara 5.58 bn 1.95 md Ral USD 1.57 md Active Active Portfolio Portfolio 16% by Sector by Region outern Ara 2.41 md

30% et Ara 4.31 md Roa USD 11.58 md

3,62 bn 2,86 bn

USD 11,08 billion 1.96bn 1.64 bn 1,61 bn for national 1,35 bn 1.55bn projects 795 M USD 4.95 billion 601 M for multinational 2.7 M 6.9 M projects at Ara entral Ara ort outern Ara et Ara anaran Ara atonal ultnatonal

Annual Report 2019 69 70 Infrastructure and Urban Development Infrastructure and Urban Development Producing and Sharing Knowledge

Annual Report 2019 71 Urban Development : Making Headway with Strategic Partners

Donor support : The Urban and Municipal Development Fund (UMDF) is Officially Launched

The Bank hosted the launch event of the Urban and Municipal Development Fund (UMDF) at the Bank’s Headquarters in on April 3rd 2019. The initial donors of the UMDF are the Nordic Development Fund (NDF), the Wallonne Exports and Foreign Investments Agency (AWEX), , and the State Secretariat for Economic Affairs (SECO), . The overall objective of the Fund is to support African cities and municipalities to better manage urban growth and climate-resilient development by improving governance and quality of basic services.

From L to R : Valerie Dabady, Division Manager of Resource Mobilization and Partnerships Department, Amadou Oumarou, Director of Infrastructure and Urban Development, Pierre Guislain VP for Private Sector, Infrastructure and Industrialization, Karin Isaksson, ED for Nordic countries and India and incoming Managing Director for the Nordic Development Fund (NDF), Hugues Chantry, Ambassador of Belgium in Cote d’Ivoire. Working with Development Partners

As part of the Greater Banjul City Urban Development program, partners AfDB and UNOPS are working together with stakeholders from the government in areas related to land-use planning, economic development, urban survey and data management, urban vision and project management training.

72 Infrastructure and Urban Development Sharing Expertise with Urban Development Stakeholders

In close collaboration with the Infrastructure and Urban Development Department of the African Development Bank, Côte d’Ivoire is preparing its urban strategy by developing a supporting National City Policy document. In this context, a seminar on Urban Policy in Côte d’Ivoire entitled «Building Together the Ivorian City of the Future» was held from June 12th to 14th in Abidjan.

Urban Development Division Manager Stefan Atchia joined experts from the worlds of finance, politics and urban planning to converge for a panel discussion, in the presence of Dominique Strauss Kahn, guest of honor and presenter on the theme of «International Issues and African Cities». Capacity Building : the Cities Leadership Workshop

The Cities Leadership workshop, held on the 25th and 26th September 2019 in Abidjan in partnership with the Bank and the Korean Urban Landscape Fund- KOAFEC, marked the launch of the Urban Municipal Development Fund (UMDF) City Diagnostics for five pilot cities in Africa. The City Diagnostics program is fully funded by the UMDF and will benefit (Madagascar), Bizerte (Tunisia), (Republic of Guinea), Dodoma (Tanzania) and Libreville (Gabon) during the pilot phase 2019-2020. The workshop was attended by authorities of the pilot cities, in addition to city managers and international urban development experts. As a preamble to the event, a Cities Program Workshop took place in Abidjan, from 16th to 18th July 2019. The UMDF presented its Diagnostic, Prioritizing and Pre-Investment methodologies with the Bank’s Management and conducted skills-building exercises for urban development stakeholders attending the workshop.

Annual Report 2019 73 Preventing Road Accidents and Fatalities in Africa Joining Forces with the Africa Transport Policy Program

The Bank hosted a Road Safety Leadership Program in Abidjan, which kicked off at the Bank’s Headquarters in Abidjan on 4th February 2019. The programme, designed to develop leadership capabilities in road safety planning, implementation, management, and operations; and ultimately help reduce the number of road crashes on the roads of Africa, was organized by the Africa Transport Policy Program (SSATP, an international partnership hosted by the ). Representants from the World Bank, the United Nations Economic Commission for Africa, and academia shared their experiences on improving road safety through practical examples and best practices, with examples coming from successful operations in Australia, Europe and African countries.

Developing a Road Safety Framework and Guidelines

The African Development Bank hosted a 2-day technical workshop on 7th and 8th May 2019 to develop a Road Safety Framework and Guidelines. High-level specialists from 25 African countries, including representatives of regional economic communities and regional road corridor organizations, were invited to attend the workshop.

Against a backdrop of growing vehicle ownership and rapid urbanization which have increased the incidence of road accidents in Africa, “There is a strong need for regular and reliable data the Bank is pursuing its efforts to assist on road accidents, and this needs to be published RMC in developing and debated in public fora, including civil society their national strategy organizations and the media...Raising public awareness to improve road safety in Africa. of accident blackspots and the weak links in accident prevention will bring the issue to the forefront of public debate and help put road safety on political agendas.» Pierre Guislain, VP Private Sector, Infrastructure and Industrialization, speaking at the Road Safety Workshop in May 2019

74 Infrastructure and Urban Development 2019 Knowledge Publications

Creating Livable Cities : Regional Perspectives

This publication examines the urbanization trends and factors across Africa, Asia, Europe and Latin America that are informing operational strategies and approaches of urban development CREATING LIVABLE CITIES in developing and emerging economies across the four regional development banks–Asian REGIONAL PERSPECTIVES Development Bank (ADB), African Development Bank (AfDB), European Bank for Reconstruction and Development (EBRD), and Inter-American Development Bank (IDB).

African Ports Databook

The Port Data Book provides statistical data on port operations with the aim of improving the analytical capability of Governments, Port Authorities and Port operators to review, evaluate and benchmark their operations. The Port Data Book presents port performance through sets of ten comparable Key Performance Indicators (KPIs). The presentation contains data gathered and information collected from all the members operating seaports and covers 70 ports.

Ghana Transport Sector Review

This Ghana Transport Sector Review provides a comprehensive diagnosis of the country’s transport sector, with a view to reviewing key successes and identifying gaps that inhibit the country from realizing its objectives for the sector. This review covers all the relevant transport sub-sectors (roads, rail, ports and shipping, air, river and lake transport, urban transport) and provides analysis of key policies, institutions, and investment dynamics within the sector.

Ancillary Works in the Bank's Road Projects

Available in French only Ancillary Works were initiated to optimize the socio-economic impact of road projects and to meet the pressing needs expressed by the communities living along the main road. Community requests vary widely. This study takes stock of what has been done in the domain, with a focus on the problems encountered and the lessons to be learned.

Burundi : Suspended Foot-bridges

Available in French only This report presents the results of the ex-post evaluation, by the beneficiaries, of the socio- economic impact of the suspended foot-bridges built in Burundi in 2014. These foot-bridges were constructed as ancillary development works as part of the Burundi National Road Development Project (RN 15) between and Ngozi.

Annual Report 2019 75 76 Infrastructure and Urban Development About Infrastructure and Urban Development

Annual Report 2019 77 Overview

The Infrastructure and Urban Development Department provides assistance to the Bank's Regional Member Countries (RMCs) in the form of loans and grants to finance transport infrastructure and urban development projects and programs. The Department also provides analytical and advisory services which support lending programs, policy dialogue and sector reforms in RMC. Strategic Focus

Finnci uort Poic ic TRANSPORT AND LOGISTICS Proct ransport ector ction lan iin ir ransport evelopment ction lan olicy or ool it oad sset ngt Couniction n outrc oad afety ogistics olicy ialogue roect rigination mplementation uit NON o roct SOVEREIGN URBAN in OPERATIONS DEVELOPMENT olicy or on ogistics perationaliation of latform rd party Econoic logistics ith division Sctor Wor edium rban evelopment Kno olicy or on airports ction lan ith ivision term reparation pipeline evelop type of development of for roadsighays targets rban evelopment rban obility roect uit o nitiate end to end inttion ransaction dvisory olicy or on unicipal ransport edium inance and registry erm ction lan ousing ublic ransportation cale up financing Etrn INFRASTRUCTURE rtnri PARTNERSHIPS and 2.0 Ban rameor and ction lan Continuou ransaction dvisory iront rossban oordination rnin on esource obiliation artnerships Dont Ecot t oint olicy or ialogue utreach ith t Bn continental and global partners Etbiin ror Sit ccit buiin

78 Infrastructure and Urban Development Department Organization

STAFF STAFF IN REGIONS Finnci AT HQ uort 38 42 Poic ic TRANSPORT AND LOGISTICS Proct Director ransport ector ction lan iin Amadou Oumarou ir ransport evelopment ction lan olicy or ool it oad sset ngt Couniction n outrc oad afety ogistics olicy ialogue FRONT OFFICE roect rigination 7 t mplementation uit NON o roct SOVEREIGN URBAN in OPERATIONS DEVELOPMENT olicy or on ogistics perationaliation of latform rd party Econoic logistics ith division Sctor Wor edium rban evelopment Kno olicy or on airports ction lan ith ivision TRANSPORT URBAN INFRASTRUCTURE TRANSPORT term reparation pipeline & LOGISTICS DEVELOPMENT PARTNERSHIPS NSO evelop type of development of DIVISION DIVISION DIVISION DIVISION for roadsighays targets rban evelopment rban obility roect uit o nitiate end to end inttion Division Manager Division Manager Division Manager Division Manager ransaction dvisory olicy or on unicipal Jean Kizito Kabanguka Stefan Atchia Mike Salawou Marco Yamaguchi inance and registry ransport edium 8 t erm ction lan ousing ublic 5 t 7 t 10 t ransportation Transport & Highways Urban Development, Infrastructure, PPP, Investment Of cers cale up financing Road Safety, Aviation, Planning & Mobility, Coordination, Fund & Assistant Etrn INFRASTRUCTURE Ports & Maritime, Municipal Finance, Assistant Infrastructure PPP Land Management rtnri PARTNERSHIPS & Rail and 2.0 Ban rameor and ction lan Continuou ransaction dvisory iront rossban oordination rnin on esource obiliation artnerships Dont Ecot t oint olicy or ialogue utreach ith t Bn continental and global partners Etbiin ror NORTH AFRICA SOUTHERN AFRICA EAST AFRICA WEST AFRICA CENTRAL AFRICA Sit ccit buiin Regional Sector Mgr Regional Sector Mgr RegionalRegionalRegional SectorSector Sector ManagerManager Mgr Regional Sector Mgr Regional Sector Mgr Achraf Tarsim Farai Kanonda HusseinHusseinHussein YusufYusufYusuf ImamImam Jean-Noël Ilboudo Kouassi Joseph Nguessan 2 t 6 t 10 t 9 t 1 Niri 5 t

Annual Report 2019 79 Staff at Headquarters

OUMAROU Amadou Director [email protected] NONVIDE-GNANSOUNOU Espérance Team assistant [email protected] PICU 0 MALANDA Barthélemy Senior Business Analyst [email protected] FRONT OFFICE OUATTARA-COULIBALY Yéné Administrative Assistant y.ouattara-coulibaly@ afdb.org N'GUESSAN Aya Blonde Christelle Team assistant a.n'guessan afdb.org

KABANGUKA Jean Kizito Division Manager [email protected] EKOTO Romain Chief Aviation & Air Transport Officer [email protected]

AWOYOMI Seye Rotimi Principal Railway Infrastructure & PPP Officer [email protected] PICU 1 NGANGA James Principal Ports and Maritime Transport Officer [email protected] TRANSPORT AND LOGISTICS BEZABEH Girma Road Safety Specialist [email protected] DIVISION EHOUMAN Lydie Chief Transport Economist [email protected] RUGUMIRE Patrick Principal Transport Engineer [email protected] DOLLIE Charles Young Professional [email protected]

NABALAMBA Alice Chief Urban Planning Officer [email protected] PICU 2 URBAN LARBI Neji Principal Urban Mobility Officer [email protected] DEVELOPMENT FLATTAU Victoria Senior Urban Mobility Officer [email protected] DIVISION

SALAWOU Mike Division Manager [email protected] CODO Pamphile Principal Transport Expert [email protected]

CARVALHO DE MELO Epifanio Principal Infr. Energy Specialist [email protected] PICU 3 KOUADJO Viviane Essui Senior Administrative Assistant [email protected] INFRASTRUCTURE PARTNERSHIPS NJOCK OUKOUOMI Judith Laure Operations Assistant [email protected] DIVISION KOUAME KOUAKOU André Division Assistant [email protected] OKERO Janet Senior Program Officer [email protected]

YAMAGUCHI Marco Division Manager [email protected] TOURE Ismael Beidari Chief Investment Officer [email protected] WILSON Geraldine Investment Assistant [email protected] BEN AYED Hassen Senior Investment Officer [email protected] PICU 4 SONG Hyoin Expert PPP [email protected] TRANSPORT BOADZO Adele Young Professional [email protected] NON-SOVEREIGN DIVISION SOKONA Mohamed Young Professional [email protected] HARAMBE Celestin Senior Investment Officer [email protected] BALAYAH Mohamed Yusuf Principal Portfolio Mgt Officer [email protected] BONI Franck Obed Team Assistant [email protected]

80 Infrastructure and Urban Development Staff in Regions

BASED IN NORTH AFRICA REGION TARSIM Achraf Regional Sector Manager RDGN Tunisia [email protected] MOHAMED Ali Ismael Principal Transport Economist COMA Morocco [email protected] NDIAYE DIOP Maimounatou Principal Transport Engineer RDGN Tunisia [email protected] SHUNDO Kenji Principal Investment Officer RDGN Tunisia [email protected]

BASED IN SOUTHERN AFRICA REGION KANONDA Farai Regional Sector Manager RDGS/South Africa [email protected] ATCHIA Stefan Officer in Charge PICU2 RDGS/South Africa [email protected] MWILA Aaron Principal Transport Engineer RDGS/South Africa [email protected] ISOOBA Daniel Mukunya Senior Transport Engineer RDGS/Uganda [email protected] MABOMBO Joao David Senior Transport Engineer COMZ/Mozambique [email protected] MALINGA Richard Principal Transport Engineer RDGS/South Africa [email protected] NYIRUBUTAMA Jean Jacques Chief Transport Economist RDGS/South Africa j. [email protected] CHIRWA Mtchera Johannes Chief PPP Infr. Specialist RDGS/South Africa [email protected] EL GAZZAR Ahmed Principal Investment Officer RDGS/South Africa [email protected] MAKASA Davies Bwalya Principal Transport Engineer COMW/Malawi [email protected]

BASED IN EAST AFRICA REGION IMAM Hussein Regional Sector Manager RDGE/KENYA [email protected] AGUMA Jeremy Bassy Principal Transport Economist RDGE/KENYA [email protected] GARBADO Eriso Infrastructure Specialist RDGE/KENYA [email protected] MAKAJUMA Adongo George Principal Transport Engineer RDGE/Uganda [email protected] MINJA Mariehellen Principal Transport Engineer COTZ/Tanzania [email protected] NDIKUMWAMI John Senior Transport Engineer BIFO/Burundi [email protected] WADDA -SENGHORE Mam Tut Chief Investment Officer RDGE/KENYA [email protected] KATALA Jumbe Naligia Transport Engineer RDGE/KENYA [email protected] TESSEMA Zerfu Chief Transport Engineer RDGE/KENYA [email protected] WA-KYENDO Mumina Chief Transport Engineer RDGE/KENYA [email protected] MUNYARUYENZI Philippe Infrastructure Specialist CORW/Rwanda [email protected] BASED IN WEST AFRICA REGION ILBOUDO Jean-Noêl Regional Sector Manager RDGW/Côte d'Ivoire [email protected] BOCKARIE Abu Sandy Senior Transport Infr Engineer COSL/Sierra Leone [email protected] AKYEA Sheila Enyonam Senior Transport Infr Engineer COGH/Ghana [email protected] TAMBAH Prince Desea Senior Transport Infr Engineer COLR/Liberia [email protected] WADE Mohamed El Abass Transport Infrastructure Specialist COSN/Senegal [email protected] MUSA Patrick Tamba Senior Transport Engineer RDNG/Nigeria [email protected]

BASED IN CENTRAL AFRICA REGION NGUESSAN Kouassi Regional Sector Manager RDGC/Gabon [email protected] EDJODJOM'ONDO Jean Felix Transport Specialist RDGC/Gabon j.edjodjom'[email protected] BIZONGO Désiré Anatole Senior Transport Officer COCD/D.R.Congo [email protected] MORE N'DONG Pierre-Simon Principal Transport Engineer RDGC/Cameroon [email protected]

Annual Report 2019 81 Infrastructure and Urban Development Department frcan Development an our t admnstratve lateau bdan te dIvore afdbor

82 Infrastructure and Urban Development