Western Regional Power Committee

Title: Minutes of the Meeting Number: 517 Name of meeting: Operation & Coordination sub-Committee Date & venue: 13thMarch 2019 at WRPC, Mumbai.

517thmeeting of Operation & Co-ordination sub-Committee (OCC) of Western Regional Power Committee (WRPC) was held on 13th March, 2019 at WRPC, Mumbai. The list of participants is enclosed at Annexure-I. Member Secretary (MS), WRPC extended warm welcome to all the participants of the 517thOCC meeting. He informed the forum about the following important operational highlights and events of WR grid during the month of February, 2019: a) After implementation of 4th amendment DSM regulation, frequency is remaining more in outside the band which is not desirable. b) “National Electricity Plan (Vol. II): Transmission” has been published by CEA. Grid scenario for the year 2026-27 has been addressed. Members were requested to go through the transmission plan for WR and accordingly do the needful. c) CERC (Terms and Conditions of Tariff) Regulations, 2019 (for 5 years: 1.4.2019 - 31.3.2024) has been notified by CERC. Tariff compensation provisions for installation of FGD system has been specified for both new and existing thermal power plants. d) MoP has issued an office memo on “Measures to promote Hydro Power Sector” specifying budgetary support and others. (Annexure-8.14) After the opening remarks, the agenda items were taken up for discussion by S.E(Opn),WRPC. █ Confirmation of the Minutes Minutes of 516th meeting of Operation & Coordination Sub-Committee (OCC) of WRPC held on 11th February, 2019 at WRPC Mumbai, were issued vide letter No. WRPC/OPN/OCC-Minutes/2018-19/2322 dated 25.02.2019. No Comments have been received. OCC subcommittee confirmed the 516th OCC minutes of meeting.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 1

█ Review of System Operation (February, 2019) 2.1 A. Frequency Particulars (February 2019) The frequency profile for last three months was as under:

Particulars Frequency Date Time Maximum instantaneous 50.27 Hz 27thFebruary, 2019 06:03:40 hrs Minimum instantaneous 49.68 Hz 01stFebruary, 2019 12:42:50 hrs Average 50.00 Hz

01st – 31st 01st – 31st 01st – 28th December,2018 January,2019 February,2019 Range (% time) (% time) (% time) IEGC band (49.9 < f < 77.03 70.26 70.73 50.05 Hz) < 49.9 Hz 12.68 10.69 7.01 > 50.05 Hz 10.29 19.06 22.26

Discussion: MS, WRPC expressed concern about shifting of frequency to higher levels. OCC subcommittee members are of the view that it is the impact of DSM 4th amendment. SE (Opn), WRPC, stated that the issue of impact of 4th DSM amendment on operation aspect was discussed in 516th OCC under agenda 8.9 and it was concluded that members would submit the comments at the earliest. He added that SLDC, Gujarat has brought the same agenda again in this OCC which is at item no. 8.9. He informed that the agenda related to DSM is more or less related to Commercial issue but operation aspects related to effect /impact on system parameters can be discussed in this forum. Commercial related issues can be brought to CCM for discussion. He requested all the participants to express their operation related concerns /issues on new DSM amendment regulation. CE, SLDC Gujarat informed that after implementation of amendment regulation, the States are increasing their generation for sign reversal even at the time of high frequency which cause the frequency to move outside the band. Therefore, important operation aspect of maintaining the real time frequency within the specified band is somehow being ignored by the system operator at the cost of maintaining deviation within the limit. This is being done by them to avoid exorbitant payment on account of sign change violation. This new trend of operation after DSM amendment is having detrimental effect on safety and stable operation of grid. All the constituents are losing crores of rupees even without their fault as it is purely due to difference in SCADA and SEM reading. He also informed that SCADA value measured by states and WRLDC is not the same. He further informed that there is a huge difference in number of sign violations as per

Minutes of 517thOCC meeting held on 13th March, 2019 Page 2

SCADA data monitored by the constituents and the final DSM bills issued by WRPC based on SEM readings. A constituent after continuously monitoring and managing the power flow during entire day may feel happy at the end of day, but if he knew that there was sign change violation recorded in SEM, he would certainly be heartbroken. In DSM accounts the sign reversals violations are approximately three to four times more than the monitored value at State LDC level causing more penalties for state. SE (Opn),WRPC, inquired whether the intended objectives of DSM amendment regulation have got achieved by imposing huge penalty to the constituents for violation of sign change. He requested all the participants to throw light on achievement of objectives of imposition of huge penalty. The CE, SLDC Gujarat informed that one of the objectives was to further narrowed down the frequency band but this is not being achieved. Certainly, there is a slight improvement in terms of Hertz but the frequency band has got widen due to changed methodology of operation which is purely based on least deviation instead of real time frequency. A representative of NTPC stated the following: 1. In a time-block sometimes RGMO command is generated for increasing load at dip in frequency while the same block maybe the 7th block for change of DSM sign to reduce load. This is being a contradictory affair and needs to be reviewed.

2. In night hours stations are getting low schedule with sustained high frequency. But to avoid penalty for sign change in every 7th block, we have to over-inject at high frequency time blocks. Similarly at low freq at high demand period, we have to under inject. This needs to be reviewed in keeping the point of grid security.

Apart of SLDC, Gujarat and NTPC, other participants stated that they would furnish the comments in details at the earliest. MS, WRPC informed that a meeting on CERC 4th DSM amendment was held at New Delhi which was arranged by CERC and views mentioned by the entities were discussed in the meeting. SE(Opn), SLDC Chhattisgarh informed that 20% error was observed between SCADA and metering data at Raigarh ICTs. He requested to correct the errors of SCADA at state interface values. SE(Opn) requested all concerned utilities to furnish their comments with relevant data by 28/03/2019 for further transmission to CERC/ CEA . OCC subcommittee noted as above.

2.1 B. State-wise Power Scenarios of the Region & PSP System operation during the month of February 2019 was satisfactory. The regional demand (Gross) was 54536MW. The corresponding peak shortfall was in the range of 244 MW (peak deficit of 0.45%). The energy requirement during the said period was 29656 MUs (Ex-bus).

Minutes of 517thOCC meeting held on 13th March, 2019 Page 3

The power supply position (provisional) for the month of February 2019 was as follows:

Peak Demand Availability/Unrestricted Requirement (Gross) In (MW)

GUJ MP CG MAH GOA DD DNH ESIL WR

REQUIREMENT 15409 13505 4094 21079 595 331 800 898 54536

AVAILABILITY 15409 13505 4090 21020 594 331 799 895 54292

SHORTFALL 0.00 0.00 4.29 58.86 0.21 0.46 1.12 2.19 244.00

% SHORTFALL 0.00 0.00 0.10 0.28 0.03 0.14 0.14 0.24 0.45

Energy Availability/ Requirement etc.(Ex-Bus) in (MUs)

GUJ MP CG MAH GOA DD DNH ESIL WR

Net Actual Energy 29648 Supplied 8595 6119 2187 11378 319 199 525 325

29656 Unrestricted 8595 6119 2195 11378 319 199 525 325 Requirement SHORTFALL in 0.00 0.00 7.67 0.00 0.00 0.00 0.00 0.00 7.67 MU 0.000 0.000 0.349 0.000 0.000 0.000 0.000 0.000 0.026 % SHORTFALL

Further it is requested all the utilities to furnish the monthly data e.g. unit wise generation of hydro and thermal generating unit, unit wise generation of hydro and thermal generating unit, unit wise /station wise auxiliary consumption of hydro and thermal generating unit, station-wise /state-wise generation of Solar/Wind/ Biomass, State-wise ISTS drawl etc. in new format attached at Annexure-2.1A. Discussion: SE (Opn), WRPC informed that recently, CEA pointed out that there was a negative growth in case of Chhattisgarh for the month of January 2019 vis-à-vis 2018 and sought comments. Subsequently, CE, SLDC, Chhattisgarh was contacted and it was informed by him that the PSPM data was not correct. He further added that PSPM (Power Supply Position Report) is one of the important documents which is used for planning of power sector by CEA / MoP and therefore, it is necessary for every States and UTs to tally the figures with their data base and point out the discrepancy if any in the same OCC so that correction can be made in revised PSPM (final). He also informed that Revised PSP will be attached with OCC minutes for perusal by the constituents.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 4

Revised PSP is attached as Annexure-2.1B. The Sub-Committee noted as above.

2.2 Inter-Regional Exchanges (February-2019) There was a net inter-regional export of 6260 MUs from WR to other regions against net export schedule of 6352MUs. The Sub-Committee noted as above.

2.3 Voltage Profile Voltage profile at some of 765/400 kV sub-stations furnished by WRLDC is enclosed at Annexure-2.3. Discussion:

SE(Opn) informed that high voltages in the range of 804 – 809 kV was recorded at some of the 765KV nodes such as Durg, Wardha, Tamnar and kotra recorded. He further informed that in case of 400KV nodes such as Karad, Dehgam, Boisar and Wardha, the max voltage recorded was in the range of 429 – 431 kV. He requested WRLDC to explain voltage regulation measures taken during the month and constraints on voltage regulation.

WRLDC representative informed that high voltages persisted only for a small time period. He also informed that due to the outage of Kolar-Talcher HVDC link, all power to SR was diverted through 765 KV and 400 KV network causing high voltages.

CE, SLDC Gujarat informed that 765KV Banaskantha-Chittorgarh line is under continuous outage for more than 5 days after charging and charging of long transmission line without line reactor poses operational challenges causing high voltages. He further requested PGCIL to bring the above line in service at the earliest.

WRLDC representative informed that Koradi unit 8 and 9, TAPS 3 in Maharashtra. JP BINA unit 1, Satpura unit 10 and 11, Singhaji unit 1 and 2 and Jhabua in Madhya Pradesh. Essasr Mahan, DB power, JPL unit 1, JPL Tamnar unit 2 and 4 in Chhattisgarh all are injecting reactive power during high voltage periods. This is not desirable and not in line with grid code.

SE(Opn), WRPC informed that the details regarding real time MVAR flow particularly during the high voltage condition have been sought from identified generators long back during the discussion in special meeting on high voltage. But the sought details have not been received and therefore second meeting on high voltage could not be arranged. He further added that now the meeting will be conducted shortly with all concerned generators to address high voltages issue.

The Sub-Committee noted the same.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 5

2.4 U/F Relay Operations As per WRLDC records the system frequency didn’t reach 49.4 Hz (which is revised Stage-I frequency after 8th NPC decision) and no UFR operation was reported to WRLDC. The Sub-Committee noted as above.

2.5 Power Cuts / Load Restrictions Details of Power Cuts and Regulatory measures as furnished by the State utilities are given in Annex. 2.5. The Sub-Committee noted as above.

2.6 Details of Generating Units under Forced outages Details of generating units under forced outages are given in Annex-2.6. Discussions:

SE(Opn), WRPC enquired about the status of revival of Uran 7, Paras unit 3 , Chandrapur unit 4, JPL-3 and 4, TRN, SGTPS unit 3, KAPS 1. MP representative informed that SGTPS unit 3 will be revived in two weeks. KAPS representative informed that unit 1 will be revived by June 19. The Sub-Committee noted as above. 2.7 Details of Generating Units under Planned outages

The details of generating units under Planned Outages are given in Annex- 2.7. The Sub-Committee noted the same.

2.8 Presentation on operational aspects by SLDCs & RLDC. All SLDC’s/RLDC presentations on operational aspects during last month and specific issues which need deliberations may be highlighted separately. Presentations are attached at Annexure 2.8.

Discussion: Representative from NTPC gave a brief presentation on AGC system installed at NTPC Mouda stage-II. He explained about hardware and communication infrastructure involved in communication to NLDC. OCC subcommittee appreciated NTPC for giving detailed presentation regarding control logic and hardware infrastructure of AGC control system.

OCC subcommittee noted the same.

2.9 List of New Grid Elements added / list of elements decommissioned. The list of New Elements added in WR Grid is attached at Annexure-2.9.

The Sub-Committee noted the same.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 6

2.10 Submission of failure analysis of grid elements Under regulation 27 of CEA (Grid Standards) Regulations, 2010, failure analysis of equipment failure and tower collapse is to be submitted to RPC and Authority. All the constituents are requested to report incidences of equipment failure and tower collapse to RPC and Authority as and when such incidences take place. The Sub-Committee noted the same.

2.11 Coal stock position In prevailing situation of scarcity of coal in the region, it is important to monitor the coal stocks on monthly basis in OCC forum so that deviation of load and generation can be kept minimum. To sensitize all the constituents of WR above the issue of coal scarcity and its impact on load generation, latest CEA coal stock position is attached at Annexure-2.11-a. Discussion: SE(Opn), WRPC informed that MoP has issued four O.Ms (Annexure-2.11-b) regarding coal supply improvement for thermal power plants keeping expected increase in demand till monsoon. 1. All pithead generation and consequently coal and rake supply (as needed) should be maximized immediately for meeting the needs of current year/next few months and all pit head plants be given full priority in coal and rake allotment for full PLF irrespective of their ACQ/FSA, in this period. 2. Central and state government plants should be given more responsibility and must be encouraged and facilitated to gear up their generation to provide uninterrupted power at appropriate price to consumers. 3. All power plants are advised to be watchful, and to maintain plant availability and adequate coal stocks as per norms. 4. Imported coal-based plants are advised to have adequate stocks to meet demand. The Sub-Committee noted the same.

█ Operational Planning 3.1 Proposed planned maintenance programme of generating units Maintenance programme of generating units for the month of February 2019 & March 2019 was discussed. The finalised list of maintenance programme of generating units for the months February 2019 & March 2019 given in Annexure 3.1. The Sub-Committee noted as above. 3.2 Outage programme of Transmission Lines/Elements.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 7

List of proposals for transmission elements outage to be availed during the month of April2019is given in Annexure 3.2.

Discussion:

SE(Opn), WRPC informed to all entities to follow the procedure laid down in IEGC and OCC meetings. He informed entities to not mount pressure on WRPC officials through any other means. He requested all entities to stick to the outage plan as per approved plan and not to extend the outages causing curtailment of other planned outage. WRLDC representative informed that, 59% of the approved outages were availed by utilities. All utilities are requested for further improvement and requested to avail maximum approved outages as lot of time is spent by committee members for discussing and approving outages. The percentage of planned outages vs availed outages is very less for utilities viz. PGCIL WR-I, WR-II, Maharashtra and Madhya Pradesh as a lot of outages are differed by utilities on D-3 basis or readiness not given. The statistics of outages availed by utilities in the month of Feb’19 is shown below.

Approved vs Planned Vs S.N. Utility OCC Month Planned Approved Availed Availed Availed 1 PGCIL WR-2 Feb-19 426 208 133 64% 31% 2 PGCIL WR-1 Feb-19 295 181 100 55% 34% 3 Maharashtra Feb-19 114 57 25 44% 22% 4 Gujarat Feb-19 137 72 54 75% 39% 5 PPTL Feb-19 12 9 5 56% 42% Madhya 6 Feb-19 59 40 9 23% 15% Pradesh 7 NTPC Feb-19 29 13 12 92% 41% 8 ATIL Feb-19 20 9 7 78% 35% 9 Chhattisgarh Feb-19 6 3 2 67% 33% 10 TPL - DGEN Feb-19 13 11 7 64% 54% 11 MEGPTCL Feb-19 16 10 9 90% 56%

The Sub-Committee noted the same.

3.3 Anticipated power supply position for the months –March 2019&April 2019. Details of anticipated restricted & un-restricted demands for the months of March 2019 & April 2019 are given in Annexure 3.3. Maharashtra, Gujarat, MP & Chhattisgarh updated the anticipated data.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 8

The Sub-Committee noted the information.

█ Operational Statistics for the month of February 2019 The details of actual generation, demand, drawl of power from grid; exchanges etc. are given in the following Annexures: Annexure 4.1 - Actual generation and requirement. Annexure 4.2 - Peak demand data. Annexure 4.3 - Integrated operation of the system and operation of Inter-state tie-lines. Annexure 4.7 – Details of level of major reservoirs in Western Region.

Discussion: WRPC requested all IPPs to submit monthly unit wise details of generation, peak demand and auxiliary consumption to WRPC for prepare of monthly reports to CEA. The Sub-Committee noted / agreed to furnish information.

█ System Disturbances in Western Region There was no major grid disturbance in the Western Region during the month of February, 2019. The details of minor incidences during the month received from WRLDC are enclosed at Annexure-5. Discussion:

WRLDC representative informed that during charging of Korba-Marwa ckt all 400KV lines connected to it were tripped on over voltage causing unit 3 and 4 outage.

S.E(Opn),WRPC requested for necessary remedial measures to avoid such kind of undesirable tripping of multiple lines in future.

The Sub-Committee noted as above. █ Healthiness status of SERs/DRs of equipment in the system. The updated status of Constituents who have furnished the status of healthiness of SER/DRs in their systems is given at Annexure-6. WRPC enquired about entities who have not submitted the status of SERs/DRs of equipment in the system. Constituents assured to submit the status on time. The Sub-Committee noted as above.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 9

█ Status of completion of ongoing schemes in WR 7.1 Status of Commissioning of Reactors 7.2 Status of Transmission schemes - 765/400 kV and above 7.3 Status of Commissioning of new Generating units in WR The updated status of above items is at Annexure-7. The Sub-Committee noted the above information. █ Miscellaneous Operational Items 8.1 Quarterly review of Crisis Management Plan (CMP) and Physical &Cyber Security (P&CS) in power sector All constituents are requested to submit current status of CMP and P&CS report (constituent wise) for the Third quarter (October to December 2018) as per format enclosed at Annexure-8.1. Discussion: MS, WRPC requested all entities to provide the CMP and P&CS plan on timely manner. The Sub-committee noted the same agreed to furnish the information. 8.2 Monitoring of Schemes funded from PSDF As per the decision taken in NPC meetings, RPC may follow up with the utilities regularly in OCC to expedite the completion of various approved schemes by giving due priority. Accordingly, WRPC has been taking up this issue in OCC forum for discussion. In this matter, the details related to State-wise sanctioned grant and disbursement amount for the approved schemes to be funded from PSDF is attached at Annexure-8.2A. Also, as per the procedure, the utilities are required to furnish the information in the prescribed format by first week of every month on regular basis to Member Convener, PSDF project monitoring group (AGM, NLDC, POSOCO) with a copy to NPC & WRPC division. A copy of prescribed format is attached at Annexure–8.2B.

Subcommittee noted as above.

8.3 State-wise details for Installation of capacitors to be furnished to WRPC In accordance with provision in clause 1.5 (ii) of IEGC, “RPC shall file monthly report on installation of capacitors by states vis-a-vis the requirement/targets, as decided in the RPC”

SLDC’s /DISCOMs are therefore requested to expedite the matter and ensure to furnish the status of capacitor report in format attached at Annexure 8.3 on monthly basis regularly. SLDC’s are also requested to compile the details

Minutes of 517thOCC meeting held on 13th March, 2019 Page 10

of various utilities and send the compiled report of entire state by 8th day of every month.

Discussion:

SE(Opn), requested all the participants to furnish the details by 8th day of month to in order to avoid delay and issue of capacitor report to CERC.

The Sub-Committee noted the same.

8.4 First time availability certification for transmission system. CEO, PJTL (Power Grid Jabalpur Transmission System) vide letter dated 19.02.2019 informed that transmission elements of PJTL i.e 765KV Vindhyachal to Jabalpur D/C was commissioned on 01.01.2019 (trial operation and CERC documents are attached at Annexure 8.4) and requested MS, WRPC to start issuing transmission availability certificate. Discussion: SE (Opn), WRPC informed that CEO, PJTL (Power Grid Jabalpur Transmission Limited) requested MS, WRPC for transmission availability for PJTL transmission licensee from 01.01.2019 after commissioning of 765 KV Vindhyachal to Jabalpur D/c. He also informed that availability certificate will be issued accordingly as per relevant regulations. The Sub-Committee noted the same.

8.5 Cyber security related works /activities being carried out in Western Region. CE(IT), CEA, New Delhi vide letter dated 31.08.2018 informed that Secretary (Power) is going to review the cyber security related works /activities being carried out in Power Sector shortly. In this regard, it is requested to provide the utilities/ State-wise status on following action points pertaining to cyber security:

1. Appointment of organization-wise Chief Information Security Officers and its status. 2. Identification of organization-wise Critical Infrastructure and its status. 3. Preparation of organization-wise Crisis Management Plan and its status. 4. Status of Cyber Security Mock Drill activity in coordination with CERT-In. 5. Status of Training / Workshops on Cyber Security organized / participated by power sector entities. 6. Status of action taken on CERT-In / NCIIPC advisories.

The agenda point had also discussed in the 512th OCC meeting wherein all the utilities had been requested to furnish the detail information related to above action points. However, all the utilities have not so far furnished the requisite

Minutes of 517thOCC meeting held on 13th March, 2019 Page 11

details. The mane of utilities who has furnished the information and who are yet to furnish the information is listed in the following table A and table B respectively:

A. Data/information received (): Sr Name of Utilities Sr Name of Utilities No No

1 Chhattishgarh 13 KSK Mahanadi 2 Madhya Pradesh 14 MB Power(Hindustan Power) 3 NTPC 15 RKM Power 4 TATA Power 16 WRTS-II, PGCIL Vadodara 5 WRLDC 17 Gujarat 6 NHDC 18 SKS Energy 7 WRTS-I PGCIL, Nagpur 19 DB power 8 CGPL 20 JPL 9 APML 21 APL 10 Essar Mahan 22 GMR Chhattishgarh 11 GMR Warora 23 JNSTPS 12 NPCIL

B. Data/information Awaited (): SN Utilities Reason for non- submission 1 DTPS Dahanu

2 NCA Confidential as per NCA representative 3 DD

4 DNH

5 GOA SLDC Goa Representative informed that action will be taken 6 Sasan Power Sasan power submitted details vide e mail dated 12/03/2019 7 Jhabua Power

8 Lanco Power

9 TRN Energy

10 ACBIL Energy

Minutes of 517thOCC meeting held on 13th March, 2019 Page 12

All utilities listed in Table- B are requested to submit the point-wise information during the meeting.

Discussion:

SE(Opn) requested all those entities who have not submitted details to submit the details at the earliest.

OCC Sub-Committee noted the same. 8.6 Operation of Hydro power projects in peaking mode

Background: a) A sub-committee has been constituted under Chairperson, CEA with heads of POSOCO, NHPC, SJVN & THDC as members and Director (H), MoP as Member convenor. In the meeting of the sub-committee, it was concluded that there is scope of 2000 MW additional power generation from hydro stations during peak hours. b) In order to sensitize about the benefits of peaking mode of operation of hydro stations, the matter had been discussed during 497th, 499th OCC meeting as well. Also, a committee of FOLD members had been constituted to study the pattern of generation from hydro stations in India and suggest measures to exploit the available capabilities of hydro units while honoring the existing hydrological constraints. c) During the 497th OCC, WRPC suggested all respective constituents to find the scope of complete utilisation of hydro power and discuss the practical issues in monthly OCC meetings. d) The matter was further discussed during 499th OCC meeting held on 20.09.2018, wherein shifting of hydro power projects from base load operation mode to peaking mode was discussed and SLDC’s were advised to utilize the available water judiciously and schedule hydro stations for peaking mode of operation. e) Further the following recommendations of Sub-Committee (under Chairperson CEA), shall be taken as a regular agenda item in monthly OCC: “The status of peaking support provided by the hydropower stations, constraints if any for inability to provide support for peaking may be included as a standing agenda item in all future monthly Operation Co-ordination Committee (OCC) Meetings. Objective of this agenda item would be to maximize peaking availability by optimizing period of shut down of hydro units, monitoring of shut downs / outage of the units and follow- up to expedite revival thereof.” In view of above SLDCs may apprise OCC:  The present status of hydro reserves in respective states.  Constraints if any for providing peaking support from hydro stations.  Actions being taken to maximize peaking availability from hydro Stations. Discussion: SE(Opn),WRPC requested all SLDCs to appraise OCC forum regarding the relevant details of operation of Hydro power projects. SE(Opn), Maharashtra informed that Koyna HEP and Ghatghar HEP are used for peaking mode and sign reversal after DSM 4th amendment.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 13

The Sub-Committee noted the same. 8.7 Compliance of new Environmental norms by WR Generators. Background: Chief Engineer, TPRM Div, CEA, New Delhi vide letter no. 2/16/VIP/TPRM/2016/CEA/ 82-108 dated 01.02.2018 and subsequently WRPC letter dated 12.02.2018 requested for the status of progress of works of FGD installation and ESP up-gradation to meet the emission level as per new environmental norms (SOx, NOx and SPM).

Subsequently, the issue was deliberated during 505th OCC meeting it was decided to monitor the installation of FGD covering the details as given in Annexure-8.6A.

Discussions in the 513th OCC and new updates:

NTPC representative informed that NIT has already been invited for 27690 MW across all regions and NIT for additional 3000 MW is expected to be invited by November 2018. Further he informed that NTPC shall adhere to the time lines as per MoEF for FGD.

Maharashtra representative informed that the process of technical bid and financial bid has been completed for koradi unit no 10 (660 MW).

All concerned generators are requested to provide the update in status for installation of FGD & ESP as per the timelines given by Central Pollution Control Board which is at Annexure 8.6B (http://cpcb.nic.in/uploads/direction/Direction_tpp_Combined_12.06.2018.pdf).

Discussion: SE(Opn), WRPC requested all the entities concerned to implement FGD installation as per plan mentioned by CPCB. The Sub-Committee noted the same.

8.8 Geospatial energy map of India Background:

Geographical Information System (GIS) based energy map for India (https://vedas.sac.gov.in/powergis_main/index.jsp) is being implemented by NITI Aayog. This would provide true locations of all energy resources including power plants and transmission lines, etc. on a map of India which would be hosted on NITI Aayog’s website. CEA is a designated nodal agency for collecting power sector data and accordingly power utilities and DISCOMs were requested to submit the requisite data to CEA for onward transmission to NITI Aayog. The details required are - name, voltage level, capacity, longitude and latitude of all

Minutes of 517thOCC meeting held on 13th March, 2019 Page 14

s/s of 33 kV and above; longitude and latitude of origin and terminating points of lines of 33 kV and above.

DISCOMs and other power utilities are requested to submit the requisite data to CEA through [email protected] email id at the earliest. The above agenda was discussed in the 513thOCCDISCOMS are requested to update the status on the same. Discussion: SE(Opn), WRPC requested all entities who have not submitted requisite details to submit to submit to DPD Division, CEA with a copy to WRPC, Mumbai. The Sub-Committee noted the same.

8.9 Consequences of Implementation of 4th amendment of DSM regulation w.e.f. 01.01.19.

Background of issue discussed in 516th OCC: CE, SLDC, Gujarat vide letter dated 02.02.2019 have informed that Hon’ble Central Electricity Regulatory Commission has made fourth amendment in Deviation Settlement Mechanism (DSM) and related matters Regulations, 2014. It has been implemented with effect from 01.01.2019. The frequency band has been tightened (Earlier, it was 49.70 Hz to 50.10 Hz. Now, it is 49.85 Hz to 50.05 Hz). For the first time, the additional charges for violation of sign change has been introduced as specified below: “In the event of sustained deviation from schedule in one direction (positive or negative) by any regional entity (buyer or seller), such regional entity shall have to change sign of their deviation from schedule, at least once, after every 6 time blocks. To illustrate, if a regional entity has positive deviation from schedule from 07.30 Hrs. to 09.00 Hrs, sign of its deviation from schedule shall be changed in the 7th time block i.e. 09.00 Hrs to 09.15 Hrs from positive to negative or vice versa as the case may be. Provided that violation of the above shall attract an additional charge of 20% on the daily base DSM payable / receivable as the case may be.” The additional charge for violation of sign change stipulation shall be levied for each such violation during a day. In this regard, SLDC – Gujarat has made very sincere efforts to comply above directives. SLDC – Gujarat would like to share operational experiences with all WR utilities: The No. of ramp up and ramp down regulations of thermal generators have been increased. The wear and tear in thermal units have been increased. There are almost 80 interface points for deriving drawl of State. It is very difficult to get accurate data from all interface points in real time despite of taking all

Minutes of 517thOCC meeting held on 13th March, 2019 Page 15

initiatives for getting accurate data. The two to five percent variation between actual SCADA data and metered data are always there. The attention and eyes of system operator remains only on deviation and sign reversal only. He cannot concentrate on other operational parameters in real time. As a result, the action of system operators are absolutely contrary to the requirement. Sometimes, they takes action for reducing drawl by rescheduling load, increases generation at high frequency vice a versa curtailing generation at low frequency for compliance of sign change clause of the regulation. The instances of wind energy curtailment, load rescheduling and load shedding have been increased. All above have been exercised vigorously to avoid huge burden of additional charges for violation of sign change. Even though, the SIC is not sure about the burden of additional charges on State Utilities. Moreover, there are 66 Nos. of intra State entities participating in State UI Pool account. The holding company do not allow SLDC to keep costly gas generators on bar just for avoiding additional charges for violation of sign change. There are limited Hydro resources. Their power schedule is based on irrigation and drinking water requirement. Therefore, the hydro and gas-based stations are not on disposal of system operator when it actual requires. Therefore, it is necessary that the views of other SLDCs and ISGS to be taken thoroughly and matter to be represented at appropriate authority for necessary change in regulations.

516th OCC Discussion:

SE (Opn), WRPC requested CE SLDC Gujarat to briefly explain the forum about operational experience and issues faced by Gujarat due to implementation of 4th DSM amendment.

CE SLDC Gujarat informed that due to the implementation of DSM 4th amendment Gujarat is shedding the load and backing down generation, Renewable generation to achieve sign reversal to avoid violation penalty. Further he also informed that all states are paying huge amounts more than the receivables due to the violation clause in DSM regulation. He also informed that DSM 4th amendment is contradicting provisions of IEGC. He requested MS,WRPC to submit the concerns of all utilities to Hon’ble CERC through WRPC Chairman as decided in the 37th WRPC meeting.

Maharashtra representative informed that to achieve sign reversals thermal generators are backed down and hydro generators were taken into service frequently which is not optimum utilisation of resources. Further he informed that as SCADA data value is not reliable, difficulties are being faced to recognise the sign reversal in real time due to which violation penalties have been imposed in DSM accounts on Maharashtra.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 16

NTPC representative informed that Solapur plant paid penalty of approx. 7 crores even though there is zero schedule for the plant.

CGPL representative informed that in a day 50 to 55 revisions are being made in generation schedule which is becoming difficult to implement. He also informed that as a generator its primary responsibility is to generate as it’s injection schedule but to maintain the violation criteria of DSM regulations the generator has to violate it’s schedule, hence the regulations are contradictory in nature from CGPL’s perspective.

GMR Warora representative informed that time drift of 7 to 8 minutes exists between PGCIL meter and meter at plant and in spite of maintaining violation stipulation of DSM regulations they have incurred violation penalty to a tune of 1 crore due to time drift errors in accounting meters.

NTPC representative informed that in some occasions thermal plants are getting technical minimum schedule and sign reversal to negative side is difficult to implement at technical minimum. He also informed that in during high frequency situations generator is not allowed to inject more power as per IEGC and DSM 4th amendment is contradictory in this regard.

NSPCL representative informed that NSPCL was penalised in 12 blocks in last three weeks. He informed that deviation in these blocks is 0.02 MW to 0.5 MW which is due to meter errors and drifts and these are also penalised for deviation

CS, representative informed that due to DSM 4th amendment wind and bio mass energy generators have to be backed down for sign reversal and becoming difficult to implement minimum environmental norms.

In view of the numerous concerns and huge financial implication on all stake holders MS,WRPC requested all entities to submit comments to WRPC on impact of 4th DSM amendment regulations within one week to WRPC secretariat for further necessary action.

516th OCC Decision:

Members of the Sub-Committee agreed to submit their comments within one week after receiving the concerns/ comments a letter highlighting the concerns would be sent to Hon’ble CERC through Chairman, WRPC.

As per above decision, all members were supposed to furnish the comments within a week time and incorporating all the comments / concerns, WRPC Secretariat would write to Hon’ble CERC. However no comments have been

Minutes of 517thOCC meeting held on 13th March, 2019 Page 17

received from any member except NTPC, Gujarat, RKM power, Torrent power and GMR power. All members are again requested to send the comments /concerns on 4th amendment of DSM regulation so that the same can be conveyed to CERC well before 01st April 2019

Discussion: SE(Opn),WRPC informed that a detailed discussion on this item has already been completed under item number 2.1 therefore, there is no need to discuss again. He reiterated to furnish the comments on 4th amendment of DSM regulation so that the same can be conveyed to CERC well before 01st April 2019.

The Sub-Committee noted the same.

8.10 Automatic Under Freq. Load Shedding Scheme (AUFLS) (A) Review of AUFLS settings The review of AUFLS scheme was being deliberated from the 2nd NPC meetings. National Power committee (NPC) in its 8th meeting dated 30th November 2018 has revised AUFLS settings by 0.2Hz each (MoM of 8th NPC at Annexure 8.10). The decision of the 8th NPC w.r.t to AUFLS scheme is as follows:

Quote After deliberation, the committee, agreed for the AUFLS scheme with 4stages and raising the frequency by 0.2 Hz viz. 49.4, 49.2, 49.0 & 48.8 Hz. The quantum for AUFLS would be reworked by NPC Secretariat based on the deliberation. It was also decided that, NRPC may appoint a Consultant from their own resources as proposed by MS (NRPC) for studying the AUFLS scheme for Indian grid and submit the study report to NPC Secretariat within a time of six months. The revised load relief for AUFLS computed by NPC Secretariat would be discussed along with the report of Consultant appointed by NRPC (if available), in the next meeting of NPC which would be held in the month of May, 2019.

Unquote

516th OCC Discussion: SE (opn), WRPC informed that 8th meeting of NPC agreed for AUFLS scheme with raising frequency by 0.2Hz viz 49.4,49.2,49.0 & 48.8 Hz. He requested all states and UTs to implement the changes in their AUFLS scheme on priority with intimation to WRPC. OCC subcommittee noted the same and agreed to change settings.

During 516th OCC, all beneficiaries were requested to change their AUFLS settings as per the decision of the 8th NPC at the earliest under intimation to

Minutes of 517thOCC meeting held on 13th March, 2019 Page 18

WRPC secretariat. However, no intimation have been received from any beneficiaries changing the AULFS setting.

All beneficiaries may give status update to OCC subcommittee.

Discussion:

SE(Opn),WRPC requested all states to appraise the forum about action taken in this regard.

CE,SLDC Gujarat informed that settings were changed as per NPC directions.

SLDC MP, SLDC Maharashtra and SLDC Chhattisgarh representative informed that action will be taken and WRPC will be informed about the action.

OCC subcommittee noted the same.

(B) Mapping of feeders Background (516th OCC): Mapping of Feeders: In the 7th Meeting of NPC, it was agreed that each RPC would submit the details / progress of feeder mapping to NPC secretariat. In 8th NPC, WRPC Secretariat made the following statement: “WRPC has informed that the issue of mapping of feeders was discussed in OCC several times in recent past. In the 493rd OCC, all the constituents were requested to initiate the process of mapping of AULFS feeders in SCADA system as most of these feeders are not covered by SCADA. During the discussion, the Western Region constituents normally raised the following concerns: Maharashtra: AULFS wired feeders are at 66kV, 33kV and even at 11 kV level and these feeders are not covered under SCADA at present. Gujarat: Most of the AULF wired feeders are at 66kV which is not yet covered under SCADA and therefore these cannot be mapped at present. The views of remaining constituents are same as above” Under this agenda item, the following has been recorded in 8th NPC MoM.: Quote After deliberation, it was agreed that each RPC would submit the details / progress of feeder mapping to NPC secretariat on a regular basis (quarterly).” The issue of mapping of feeders have been discussed in 516th OCC and the following was the recommendation of 516th OCC: Quote:

MS,WRPC requested SLDC to provide details of typical substation of 66/33/11 KV levels where problems are being faced, so that study can be carried out by IIT/IISc for suitable implementation of feeder mapping.

SLDCs agreed to provide the details within one week. Unquote In view of above, SLDCs may update the status.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 19

Discussion: SE(Opn), WRPC requested all SLDC’s to provide the details as per the recommendation of 516th OCCM, so that IIT/IISc may be requested to carry out studies .

OCC subcommittee noted the same. 8.11 Details of existing transmission system (220 KV and above AC& DC voltage level) in the country as on 31st December 2018.

Background (516th OCC):

PSPM Division, CEA vide letter dated 28/01/2018 (letter enclosed at annexure 8.11) has requested for Details of existing transmission system (220 KV and above AC& DC voltage level) in the country as on 31st December 2018. An e-mail regarding the same has been sent by Operation Division, WRPC on 01/02/2019. All SLDCs, Transmission licensees are requested to kindly furnish the data to [email protected] with a copy to [email protected]. 516th OCC Discussion: SE (Opn), WRPC informed that CE,PSPM Division requested for Details of existing transmission system (220 KV and above AC& DC voltage level) in the country as on 31st December 2018. He requested concerned entities to submit data at the earliest to CEA.

Discussion: SE(Opn),WRPC informed that only some of the entities have provided the information and entities who have not provided the information may please submit the information at the earliest with intimation to WRPC. SLDC MP representative and SLDC Chhattisgarh representative informed that requisite data will be submitted with in a week.

OCC subcommittee noted the same.

8.12 Ambient temperature adjusted TTC 514th OCC background:

TTC assessment considering temperature dependant rating of lines and equipment:

NPC vide its letter 3/NRC/NPC/CEA/2018/942-948 dated 20.09.2018 raised the issue of ambient temperature adjustment TTC. In above said letter NPC stated that, in line with the decisions of the meeting of sub-committee of NRCE for finalising the methodology for computation of TTC/ATC/TRM, PGCIL vide letter dated 18.04.2018 has submitted the current rating of terminal equipment for high capacity 400 KV lines owned by PGCIL.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 20

In this issue POSOCO has further requested that terminal equipment rating of STU and other transmission licensees would also be required for full implementing of temperature adjusted TTC. Lastly NPC requested that the terminal equipment rating of STU and other transmission licensees of WR may be compiled and furnished to POSOCO with a intimation to NPC on priority basis.

Discussions 516th OCC:

SE (Operation), WRPC requested all the STU/ transmission licensees to furnish the details of terminal equipment rating so that same can be compiled and further transmitted to POSOCO & NPC.

A meeting was held among NPC, PGCIL and POSOCO on “Ambient temperature adjusted TTC” on 05/02/2019 at NPC. The summary records of discussion is attached at annexure 8.12.

In above meeting, it was decided that the terminal equipment rating of STUs and other private ISTS transmission licences to POSOCO with a copy to NPC, CEA. The abstract of important points is as follow:

Quote

It was observed that though the end equipment ratings are required for both the planning and operational studies, it becomes crucial for carrying out ambient temperature adjusted TTC/ATC studies of all the regions by POSOCO. Therefore, all the constituents i.e CEA, CTU, POSOCO(NLDC/RLDC) and RPCs should make all efforts to compile this information.

Unquote

In view of the above STUs and private ISTS transmission licensees of western region may furnish the terminal equipment rating immediately to POSOCO with a copy to NPC division, CEA. This detail may be furnished on the following email id [email protected] and [email protected].

Discussion:

SE(Opn),WRPCrequested STUs and ISTS transmission licensees to submit data to POSOCO under intimation to NPC,CEA.

OCC subcommittee noted the same.

8.13 Schedule for Rattan India Power Limited, Amravati

Shri Anil Kumar Mishra, AVP Rattan India Power Limited, Amravati vide e- mail dated 07/03/2019 informed that RIPL is not receiving any schedule from 2 months. He also informed that RIPL, Amravati accumulated 8.08 lakh metric ton of coal based on the discussions with MSEDCL.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 21

He further stated that due to rising ambient temperature and spontaneous heating of the coal, the same is catching fire and it is getting difficult day by day to control the heating and the fire in the coal. This may cause a major catastrophe damaging the safety and environment in and around the plant.

Discussion:

SE(Opn),WRPC requested RIPL representative to brief OCC forum about the issue.

Shri Anil Kumar Mishra, AVP Rattan India Power Limited informed that after meeting of generators with MSEDCL, RIPL acquired 8.08 lakh metric ton coal. But MSEDCL is not provided any schedule of power to RIPL. He also informed that due to rising ambient temperature and spontaneous heating, coal is catching fire.

SE(Opn), WRPC informed that this issue is bilateral and should be resolved by MSEDCL and RIPL. OCC forum suggested RIPL to take consent from beneficiaries for scheduling of power under URS to any other beneficiary requiring power.

NTPC representative requested beneficiaries to give schedule above 55% for kawas and gandhar as LP blades of Steam turbine are getting eroded due to lesser loading.

OCC sub-committee noted as above.

Additional agenda of 517th OCC meeting

AD-I: Outage of 400KV Bus-II at CGPL Mundra (Annexure 3.2)

PGCIL WR-2 requested for outage of 400 KV Bus-II at CGPL Mundra for termination of Mundra-Bhuj PS circuit 1 at CGPL Mundra. However, Chairman, CGPL vide letter dated 14/02/2019 informed that due to the constraints of achieving 80% Plant availability target of CGPL station, the outage request may not be permitted. He informed that huge financial loss will occur for CGPL Mundra failing 80% Plant availability target. CGPL also informed that the proposed outage may be taken in the last week of march 2019 along with bus bar protection scheme work planned by CGPL.

A meeting on 01/03/2019 was conducted with officials from WRPC, WRLDC, CGPL, PGCIL WR-II, SLDC(GETCO) through VC wherein outage of 400KV bus-II at CGPL was discussed.

PGCIL WR-II vide letter dated 11/03/2019 informed that consent was not received from CGPL for construction works. He informed that present project of

Minutes of 517thOCC meeting held on 13th March, 2019 Page 22

Mundra-Bhuj double circuit line is monitored by PMO through PRAGATI portal and deadline of the project is February 2019.

Discussion:

SE(Opn),WRPC briefly informed OCC forum regarding outage of CGPL bus-II for commissioning of Mundra-Bhuj D/c line. He requested CGPL representative to inform OCC forum details of denying outage to PGCIL.

CGPL representative informed that due to the constraints of achieving 80% Plant availability target of CGPL station, outage was not consented. He informed that huge financial loss will occur for CGPL Mundra failing 80% Plant availability target. CGPL also informed that the proposed outage may be taken in the last week of march 2019 along with bus bar protection scheme work planned by CGPL. He also informed that Mundra-Bhuj circuit-II can be commissioned after completion of other works by CGPL and circuit-1 may be commissioned after 25th march 2019 as it is expected to achieve target availability by 25th March 2019.

PGCIL representative informed that the project is being monitored by PMO through PRAGATI , the required outage may be permitted to complete commissioning activities.

SE(Opn), WRPC stated that the status of PLF of CGPL shall be reviewed on 22.03.2019 and accordingly outage for 400 KV Bus-II at CGPL would be considered.

PGCIL representative suggested the outage of bays of under construction 400 Kv Mundra-Bhuj-Ckt II.

OCC subcommittee recommended agreed on review of PLF of CGPL on 22/03/2019 and subsequent discussion on decision of date of Outage of 400KV Bus-II at CGPL Mundra.

AD-II: General election 2019 duties for WRPC officials

As announced by Election commission, General elections 2019 are planned in the month of April & May 2019.Election commission, Maharashtra has directed MS, WRPC for temporary posting of some of the officials of WRPC from all divisions for election duties. In this regard, WRPC informs all the constituents that some of the officers may not be available at WRPC in this period.

IN view of the above, it may happen that some reports and regulatory accounts may get delayed. To avoid this delay WRPC has already taken contingency steps, but inspite of best efforts unavoidable delays may creep in. Hence entities are requested to bear with this delay.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 23

Discussion:

SE(Opn),WRPC informed that some of the officers of WRPC were already deputed for General Election duty and some more officers are expected to be deputed. In this situation, the regulatory accounts and reports to be issued by respective divisions of WRPC may get delayed. He further requested all entities to kindly bear with this delay in future for till the election is over.

OCC sub-committee noted as above.

AD-III: Meeting schedule for finalization of LGBR 2019-2020

WRPC is in the process of finalization of LGBR for the year 2019-2020, for the same emails were sent and data was sought from all states and generators. Data has been received from entities and to finalize the LGBR entity wise meeting is proposed at WRPC as per the following schedule

1. 18.03.2019: Maharashtra and Gujarat. 2. 19.03.2019: Madhya Pradesh and Chattisgarh. 3. 20.03.2019:DD, DNH and Goa. 4. 22.03.2019: ISGS Discussion:

SE(Opn),WRPC informed to the forum regarding dates of forthcoming meeting with the constituents for finalisation of LGBR for 2019-20. He further informed that some of the entities have requested to postpone the dates of meeting due to HOLI festival on 21/03/2019. In this situation, it is better to decide the dates later on. He stated that the date of meeting would be decided later on and accordingly intimation would be issued by email.

OCC subcommittee noted the same.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 24

█ WRLDC Agenda Items

9.1 Primary Frequency Response

The average primary response of generators for last three events are shown below.

Event-33 Event-34 Event-35

NR-1400 NR-960 NR-900 Average Response S.No Generator/Station 16-01-19 12:26:00 23-01-19 06:37:10 05-02-19 11:57:10 as % of 49.97 49.96 50.13 Ideal

49.92 49.92 50.16

-0.05 -0.04 0.03

1 VSTPS-III(2x500) 0% 178% 120% 99%

2 KSTPS-II(3x500) 19% 101% 114% 78%

3 KSTPS-I (3x200) 70% 41% 120% 77%

4 KSTPS-III(1x500) 40% 110% 70% 73%

5 SIPAT-I(3x660) 71% 19% 121% 70%

6 MB Power(2x600) 47% 100% 49% 65%

7 DB Power(2x600) 51% 120% 7% 59%

8 SASAN(6x660) 47% 0% 121% 56%

9 Essar Mahan(2x600) 82% 34% 51% 56%

10 Lanco (2x300) 16% 25% 120% 54%

11 APML Tiroda(5x660) 23% 41% 86% 50%

12 VSTPS-IV(2x500) 0% 120% 20% 46%

13 Mouda-I(2x500) 119% 0% 11% 43%

14 Mouda-II (2x660) 53% 0% 59% 37%

15 JPL I (4x250) 73% 0% 36% 37%

JPL Tamnar (Stage 16 II)(4x600) 0% 5% 95% 33%

Minutes of 517thOCC meeting held on 13th March, 2019 Page 25

17 Balco (4x300) 28% 0% 64% 30%

18 CGPL(5x830) 47% 40% 0% 29%

19 KSK(3x600) 5% 22% 20% 16%

20 VSTPS-II(2x500) 0% 0% 40% 13%

21 SIPAT-II(2x500) 0% 0% 30% 10%

22 JP NIGRIE(2x600) 0% 9% 0% 3%

23 VSTPS-I (6x210) 0% 0% 0% 0%

24 GMR Raipur(2x685) 0% 0% 0% 0%

25 TRN (2x300) 0% 0% 0% 0%

26 Jhabua (1x600) 0% 0% 0% 0%

Data non-current/Zero Generation Based on the “report of expert group to review and suggest measures for bringing power system operation closer to national reference frequency”, the minimum frequency response expected is at least 40% of ideal response.

Hon’ble CERC notified Terms and Conditions of Tariff Regulations, 2019 on 7 Mar 19 and these regulations shall come into force on 1.4.2019. Clause no 30.2.i & 30.2.ii related to RGMO or FGMO are quoted below

Quote  In case of a new project, the rate of return on equity shall be reduced by 1.00% for such period as may be decided by the Commission, if the generating station or transmission system is found to be declared under commercial operation without commissioning of any of the Restricted Governor Mode Operation (RGMO) or Free Governor Mode Operation (FGMO), data telemetry, communication system up to load dispatch center or protection system based on the report submitted by the respective RLDC.

 in case of existing generating station, as and when any of the requirements under (i) above of this Regulation are found lacking based on the report submitted by the concerned RLDC, rate of return on equity shall be reduced by 1.00% for the period for which the deficiency continues. Unquote

Minutes of 517thOCC meeting held on 13th March, 2019 Page 26

Discussion: WRLDC informed that for the last three grid events the primary frequency of VSTPS-I, GMR Raipur, TRN and Jhabua is zero. WRPC enquired whether response is considered when unit is not in service and how the response is calculated. The stations whose data is non-current or zero generation is highlighted in frequency response table. The frequency response computations are done as per CERC approved procedure. In general frequency response of generating unit can be calculated as follows.

Delta f = 0.13 Hz Droop = 5% , MCR = 500 MW Ideal Response = (0.13/50) x (100/5) x 500 = 26 MW Actual response = 501.3-478.4=22.9 MW = Delta P observed Actual response as % of Ideal Response = 88 %

WRLDC advised states to monitor frequency response of stations under SLDC control area and may share the response in monthly OCC meetings. MS WRPC advised generating stations to provide adequate response and informed that the generating stations not responding to frequency incidents would undergo governor response testing and ROE would be deducted as per CERC regulations. OCC Subcommittee noted the same.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 27

9.2 Web Based OCC Outages Software for replacing the existing Google Sheet

As discussed in 516 OCC meeting, hands-on training on web based outage software to utilities was conducted on 22 Feb 19 at WRLDC. More than 50 representatives from utilities viz. PGCIL, NTPC, Sterlite, Adani, GETCO, MSETCL, MPPTCL and CSPTCL etc. Feedback received from the participants is being incorporated in the software.

At present google sheet and web based software are operating in parallel and utilities are filling their readiness and comments in both. The process of updating of database for web based software is under progress. Discussion:

WRLDC informed that updation of database is under progress. Feedback by utilities is being considered and incorporated to the extent possible in software. Any additional feedback for improvement of software may be informed by 20 Mar’19 to WRLDC. Utilities may give their readiness/remarks in both google sheet and outage software for Apr’19 outages. OCC Subcommittee noted the same. 9.3 Voltage Regulation in Western Region

9.3.1 High Voltage Nodes In the month of Feb’19, voltages were above IEGC band at 400 kV Raigarh, Dhule, Raipur, Karad, Dehgam and Kalwa etc. The Voltage Deviation Index of above nodes are tabulated below. % time Fault Remarks Voltage Station Voltage > than level S.No Deviation Name IEGC Index threshold 1 Dhule 85.37 0.85 21451 - 2 Wardha 75.01 0.75 66917 - 3 Kalwa 72.21 0.72 22515 - 23424 Prolonged outage of 80MVAR LR of 400 kV KARAD- LONIKHAND- 4 Karad 60.65 0.61 1 @KARAD

Minutes of 517thOCC meeting held on 13th March, 2019 Page 28

from 14-09- 2017 28921 MVAR injection by RKM, DB Power, JPL, 5 Raigarh 59.16 0.59 TRN 6 Kasor 57.08 0.57 15050 - 25408 MVAR injection by 7 Dehgam 56.04 0.56 Wanakbori 8 Mapusa 51.11 0.51 6354 - 42154 MVAR injection by RKM, DB Power, JPL, 9 Raipur 44.14 0.44 TRN 10 Magarwada 37.93 0.38 15567 - 11 Boisar 34.39 0.34 28108 - 12 Parli 28.56 0.29 32649 - 13 Damoh 17.13 0.17 11727 - 14 Khandwa 16.22 0.16 20859 -

9.3.2 Generators injecting MVAR into Grid The MW, MVAR and Voltage of generating units was analyzed for the month of Feb 19 with the help of SCADA data available at WRLDC. The list of generators injecting MVAR into the grid even when the bus voltage is above nominal are given below. 1. IPPs: Essar Mahan, RKM, Dhariwal, DB Power, Jhabua, TRN, JPL-I (U#3), JPL Tamnar (U#2, U#4) 2. ISGS: KSTPS (U#3, U#2), TAPS(U#3) 3. Gujarat: Wanakbori (U#4, U#5, U#6 & U#7) 4. Maharashtra: Koradi (U#8 & U#9) 5. M.P. JP Bina(U#1), Satpura (U#10 & U#11), Singhaji (U#1 & U#2) Discussion:

WRPC informed that a separate meeting will be conducted with Maharashtra generators and IPPs for discussing MVAR absorption by Generating stations to control high voltage and contribute in voltage regulation. WRPC suggested WRLDC to compile last six months data of generators injecting MVAr at high voltage so that generators not complying with RLDC instructions could be

Minutes of 517thOCC meeting held on 13th March, 2019 Page 29

identified. In meeting WRLDC can show last six months data of generators injecting MVAr at high voltage. OCC Subcommittee noted the same. 9.4 Preparedness for ensuring adequacy of Power Supply during Summer (April-June)

During summer, temperatures would remain above normal values in many areas. In the past several generating stations have been affected due to inadequate coal stock and water shortage. The actual demand of constituents in April-June is tabulated below:

Constituent Daily Energy Peak Demand Consumption in MUs in MW (Apr-Jun 18) (Apr-Jun 18) Maharashtra 385-517 16753-23755 Gujarat 316-375 14165-16983 Madhya 141-184 6788-9057 Pradesh Chhattisgarh 67-91 3018-3949 Goa 8-12 363-561 DNH 15-18 714-792 DD 5-8 274-382

The following aspects may be reviewed:  Revised short term demand forecast of the State  Review of outages of transmission elements which need backing down of generation and exploration of availing outages in the off peak hours which have impact on generation  Measures being taken for ensuring adequacy of power supply and avoid load shedding in respective States  Available coal stock in thermal power stations and measures being taken to ensure adequate fuel availability: (RKM, JPL, EPGL and KSK to update the status specifically)  Availability of water for thermal stations (Parli, Tirora, Mouda, Chandrapur to specifically update the status)  Availability/ Water level in reservoir hydro (Koyna, SSP, Kadana, Ukai and Bargi etc.)  Import transfer capability of States

Discussion:

Minutes of 517thOCC meeting held on 13th March, 2019 Page 30

WRLDC advised all constituents to take necessary measures and ensure adequacy of Power Supply during Summer. Maharashtra SLDC informed that at present there is no shortage of water for thermal stations (Parli, Tirora, Chandrapur).

WRLDC suggested that drawl schedule of states are to be limited to transfer capability. OCC Subcommittee noted the same.

9.5 Extension of outages of critical elements

As per approved outage procedure, utilities should adhere to outage schedules. After availing outages utilities should restore the element as per time line approved in OCC meetings. However it has been observed that utilities are not adhering to time line specified in OCC meeting and extending outages beyond approved timelines. In recent times planned outages of critical elements like 400 kV Rajgarh-Nagda D/C, 400 kV APL Mundra- Kansari, 400 kV Varsana-Kansari, 400 kV Kalwa-Karghar and 400 kV - Kalwa are extended beyond approved timelines.

Extension of outages beyond approved timeline is affecting the outage schedules of other parallel and nearby elements. It may also result in critical loading of other elements during contingences.

Discussion:

WRLDC informed that planned outages of critical elements like 400 kV Rajgarh-Nagda D/C, 400 kV APL Mundra-Kansari, 400 kV Varsana-Kansari, 400 kV Kalwa-Kharghar and 400 kV Pune-Kalwa are extended beyond approved timelines.

Gujarat SLDC informed that outage of 400 kV APL Mundra-Kansari and 400 kV Varsana-Kansari are extended due to field issues. Maharashtra SLDC informed that 400 kV Kalwa-Karghar and 400 kV Pune-Kalwa are extended due to ROW issues.

WRLDC informed that if outages are being availed for any construction works or traction works, SLDC shall assess daily status of work and tentative

Minutes of 517thOCC meeting held on 13th March, 2019 Page 31

schedule of restoring transmission element. If the work is not being completed within the approved time schedule, SLDC/utilities shall inform WLRDC at least one or two days ahead so that other utilities can be informed at the earliest regarding the rescheduling of the outages.. However, all efforts shall be made to adhere to the time line to avoid deferring of important outages to the later date. Utilities agreed for the same. OCC Subcommittee noted the same.

9.6 Delayed submission of First Time Charging (FTC) documents and Non-compliance of FTC procedure by MPPTCL

In 516 OCC meeting, NLDC and WRLDC mentioned that the first time charging documents A1-A6 has to be submitted on D-10 (ten days in advance) and B1-B5 on D-5 to RLDC. RLDC can send the A1-A6 documents to NLDC on D-5 and B1-B5 documents at least two working days in advance. However it has been observed that MPPTCL is not submitting the FTC documents as per time line mentioned above. Many a times operation code for charging is sought even before confirming protection coordination with adjacent stations. The above issues were faced while coordination FTC of elements at 400/220 kV Badnawar (LILO of 400 kV Nagda-Rajgarh-D/C)

Following documents need to be forwarded to WRLDC control room while intimating / seeking charging code first time for transmission elements  Format-IV (Approval of FTC from RLDC)  Sequence of charging elements  To intimate whether it is test charging or anti-theft charging or trial operation for 24 Hrs  Study results from STU related to voltage rise/fall and major change in MW flows after charging element.  Endorsement from neighboring substations regarding protection coordination.  Undertaking that all men and material have been removed

OCC members may like to note the above.

Discussion:

WRLDC informed that MPPTCL has not been submitting the FTC documents as per the time line. The charging code is sought with incomplete information

Minutes of 517thOCC meeting held on 13th March, 2019 Page 32

and documents. WRLDC informed that charging code would be issued only if all charging documents are complete and information regarding sequence of charging elements, the purpose of charging i.e, whether for testing for a short period only or idle charging for anti-theft purpose or for trial operation for 24 Hrs and study results from STU and endorsement from neighboring substations regarding protection coordination are provided. OCC Subcommittee noted the same. 9.7 Ramp compliance of Thermal Generators as per T&C of tariff

Hon’ble CERC notified Terms and Conditions of Tariff Regulations, 2019 on 7 Mar 19 and these regulations shall come into force on 1.4.2019. Clause no 30.2.iiii related to thermal generators ramp rate are quoted below

Quote

“in case of a thermal generating station, with effect from 1.4.2020:

a) rate of return on equity shall be reduced by 0.25% in case of failure to achieve the ramp rate of 1% per minute;

b) an additional rate of return on equity of 0.25% shall be allowed for every incremental ramp rate of 1% per minute achieved over and above the ramp rate of 1% per minute, subject to ceiling of additional rate of return on equity of 1.00%: Provided that the detailed guidelines in this regard shall be issued by National Load Dispatch Centre by 30.6.2019.”

Unquote

OCC members may like to note the above. Discussion:

WRLDC informed that as per CERC Terms and Conditions of Tariff Regulations, 2019 notified on 7 Mar 19, in case of a thermal generating station, with effect from 1.4.2020, rate of return on equity shall be reduced by 0.25% in case of failure to achieve the ramp rate of 1% per minute.

WRLDC advised ISGS to make note of above. WRPC suggested that the matter may be taken up separately and may discuss with other RPCs and

Minutes of 517thOCC meeting held on 13th March, 2019 Page 33

RLDCs, the process being adopted to ensure compliance “to achieve the ramp rate of 1% per minute.” OCC Subcommittee noted the same. 9.8 Lines / ICTs opened to control overloading

Following elements are kept open to control line/ICTs loading in downstream network. WRLDC reported the same in operational feedback of WRLDC to CERC, States/utilities to expedite the commissioning related elements.

Transmission Sl. Overloaded Element (s) Remarks No corridor opened

220 kV outlets from Pune (PG) to be expedited by MSETCL.

43rd SCM: MSETCL intimated that Talegaon (PG)–Talegaon (M)–Urse– 220 kV D/C is planned & under To control implementation and this line loading in 220 has been completed up to 400/220 kV 1. kV Pune (PG) – Urse S/s. One ICT is kept Pune(PG) one ICT Talegaon D/C opened to control load on lines 220kV Urse –Chinchwad S/C. It was intimated that Urse– Chinchwad 220 kV D/C and Pune (PG)–Hingewadi 220 kV D/C would be expected to get completed by Dec, 2018.

Present Status: Lines has not yet commissioned.

With the commissioning of 4th ICT (500 MVA) in May’18 at To control Boisar PG, Boisar-Boisar-T/c 400/220kV one loading on line loading further increased. 2 ICT at Boisar PG 220kV Boisar- To control the loading, one Boisar T/c lines ICT at Boisar PG is kept out to control line loading.

Remedial Action:

Minutes of 517thOCC meeting held on 13th March, 2019 Page 34

Transmission Sl. Overloaded Element (s) Remarks No corridor opened

Commissioning of 220kV Boisar-Borivali line LILO at Boisar PG & 220kV Boisar PG-Wada D/c line would relieve loading on Boisar- Boisar lines and reliability of Boisar PG area.

Commissioning of other To control outlets from Navsari PG 220kV Nasik- loading on 220kV would help in relieving Navsari one ckt & 3 220kV Navsari loading on 220kV Navsari PG- 400/220kV one PG-Navsari D/c Navsari D/c lines and ICT at Navsari PG lines reliability of supply of Navsari area.

DSPM (2x250 MW) generation was planned with LILO of existing 220kV Korba West- Korba East one ckt and To control 220kV Korba East- 220kV Suhela-Banari line. No loading on 4 Buddipadar S/c additional lines were planned 220kV DSPM- line for DSPM evacuation. This Korba East lines has resulted in overloading of 220kV DSPM-Korba East line when the power flow is towards Budhipadar end.

Keeping Satna PG-Maihar S/c To control increases the loading on loading on 400/220kV ICTs at Satna PG 220kV Satna PG- 400/220kV and also results in power flow Maihar S/c ICTs at Satna from Satna PG-Maihar-Katni (400kV). To avoid this 220kV 5 132kV Satna- PG & Satna PG-Maihar kept Maihar 132kV 220/132kV opened. Further 132kV Satna-Kymore (2x160 MVA) ICTs at Satna Satna-Maihar and 132kV MPPTCL Satna-Kymore line also kept out to control loading on 220/132kV (2x160 MVA) ICTs

Minutes of 517thOCC meeting held on 13th March, 2019 Page 35

Transmission Sl. Overloaded Element (s) Remarks No corridor opened

at Satna MPPTCL.

Almost most of the time 400/220kV (3x315 MVA) ICTs at Bina MPPTCL are loaded above 200MW. When total loading on ICTs above 750 To control MW, becomes N-1 non- 220kV Bina MP- loading on compliant. To control the the 6 Datia & 220kV 400/220kV loading on above said ICTs Bina MP- Shivpuri ICTs at Bina 220kV Bina MP-Datia & MPPTCL 220kV Bina MP-Shivpuri line kept opened. ICTs were N-1 non-compliant after opening these lines for 20% of the time in month of Oct’18 & Nov’18.

ICTs at Ektuni are N-1 non- compliant for 5% of the time. 400kV Ektuni- To control To facilitate the outage on any Bableshwar one loading on of the ICT requires opening of 7 ckt & 400kV 765/400kV 400kV Ektuni-Bableshwar Ektuni-Taptitanda ICTs at Ektuni. one ckt or Ektuni-Taptitanda one line one ckt. Also generation backing down also required.

To control loading on 220kV Amreli-Sawarkundla 220kV Amreli- 400kV Hadala- D/c line was N-1 non 8 Sawarkundla Amreli line compliant for 55% of the time line/ 220kV during the quarter. Jetpur-Gondal line

Utilities may apprise OCC, actions being to control line/ICT loading and the present status of commissioning of new elements to relieve overloading of above mentioned elements. Discussion:

Minutes of 517thOCC meeting held on 13th March, 2019 Page 36

Transmission Status as per 517 Sl. Overloaded Element (s) Remarks OCC meeting No corridor opened

220 kV outlets from Pune Will be completed (PG) to be expedited by in one year. MSETCL.

43rd SCM: MSETCL intimated that Talegaon (PG)–Talegaon (M)–Urse– Chinchwad 220 kV D/C is planned & under implementation and this To control line has been completed loading in 220 up to Urse S/s. One ICT 400/220 kV 1. kV Pune (PG) – is kept opened to control Pune(PG) one ICT Talegaon D/C load on 220kV Urse – lines Chinchwad S/C. It was intimated that Urse– Chinchwad 220 kV D/C and Pune (PG)–Hingewadi 220 kV D/C would be expected to get completed by Dec, 2018.

Present Status: Lines has not yet commissioned.

With the commissioning PGCIL informed of 4th ICT (500 MVA) in that one bay is May’18 at Boisar PG, available at Boisar-Boisar-T/c line Boisar. MSETCL loading further increased. may coordinate To control the loading, with PGCIL for one ICT at Boisar PG is second bay works kept out to control line for timely To control loading. completion (15th 400/220kV one loading on 2 May 19). ICT at Boisar PG 220kV Boisar- Remedial Action: Boisar T/c lines Commissioning of 220kV Boisar-Borivali line LILO at Boisar PG & 220kV Boisar PG-Wada D/c line would relieve loading on Boisar-Boisar lines and reliability of Boisar PG area.

220kV Nasik- To control Commissioning of other Gujarat SLDC 3 Navsari one ckt & loading on outlets from Navsari PG informed that Vav- 400/220kV one 220kV Navsari 220kV would help in 2 substation

Minutes of 517thOCC meeting held on 13th March, 2019 Page 37

Transmission Status as per 517 Sl. Overloaded Element (s) Remarks OCC meeting No corridor opened

ICT at Navsari PG PG-Navsari D/c relieving loading on expected by Apr lines 220kV Navsari PG- 19 that would Navsari D/c lines and relieve the loading. reliability of supply of Navsari area.

DSPM (2x250 MW) Chhattisgarh generation was planned SLDC informed with LILO of existing that second circuit 220kV Korba West-Korba of Korba East East one ckt and 220kV DSPM expected by To control Suhela-Banari line. No Oct’19. 220kV Korba East- loading on additional lines were 4 Buddipadar S/c 220kV DSPM- planned for DSPM line Korba East lines evacuation. This has resulted in overloading of 220kV DSPM-Korba East line when the power flow is towards Budhipadar end.

Keeping Satna PG-Maihar No status. S/c increases the loading on 400/220kV ICTs at To control Satna PG and also results loading on in power flow from Satna 220kV Satna PG- 400/220kV PG-Maihar-Katni (400kV). Maihar S/c ICTs at Satna To avoid this 220kV 5 PG & Satna PG-Maihar kept 132kV Satna- 220/132kV opened. Further 132kV Maihar 132kV Satna-Kymore (2x160 MVA) Satna-Maihar and 132kV ICTs at Satna Satna-Kymore line also MPPTCL kept out to control loading on 220/132kV (2x160 MVA) ICTs at Satna MPPTCL.

Almost most of the time No Status 400/220kV (3x315 MVA) ICTs at Bina MPPTCL are To control loaded above 200MW. 220kV Bina MP- loading on When total loading on 6 Datia & 220kV 400/220kV ICTs above 750 MW, Bina MP- Shivpuri ICTs at Bina becomes N-1 non- MPPTCL compliant. To control the the loading on above said ICTs 220kV Bina MP- Datia & 220kV Bina MP- Shivpuri line kept opened.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 38

Transmission Status as per 517 Sl. Overloaded Element (s) Remarks OCC meeting No corridor opened

ICTs were N-1 non- compliant after opening these lines for 20% of the time in month of Oct’18 & Nov’18.

ICTs at Ektuni are N-1 Maharashtra non-compliant for 5% of SLDC informed the time. To facilitate the that they would 400kV Ektuni- To control outage on any of the ICT suggest the Bableshwar one loading on requires opening of 400kV recommendation 7 ckt & 400kV 765/400kV Ektuni-Bableshwar one to STU planning. Ektuni-Taptitanda ICTs at Ektuni. ckt or Ektuni-Taptitanda one line one ckt. Also generation backing down also required.

To control Gujarat SLDC loading on 220kV Amreli- informed that 220 220kV Amreli- Sawarkundla D/c line kV Amerli-Dasa 400kV Hadala- 8 Sawarkundla was N-1 non compliant line LILO at Botar Amreli line line/ 220kV for 55% of the time during is about to Jetpur-Gondal the quarter. complete by line Mar’19

WRLDC informed that at present +/- 500 kV HVDC Chandrapur-Padghe bipole is operating under reduced power flow mode (upto 850 MW only) due to non- availability of base filter at Padghe end. This is causing overloading of other parallel lines during peak hours and constrained to operate HVDC Bhadrawati BTB poles on maximum power order. Maharashtra SLDC informed that 1. The base filter bank issue would be resolved in three months. 2. They are in consultation with ABB (OEM) for increasing power order beyond 850 MW with existing filters. OCC Subcommittee noted the same.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 39

9.9 Providing of wind turbine data of wind farms in control area of SLDCs as per direction of Hon’ble CERC. Information is to be submitted to Hon’ble CERC as per Recording of Proceeding issued by CERC in Petition No.237/MP/2017 along with I.A. No. 11/2018.

Quote

The Commission further directed the POSOCO to submit the States WTG-wise data containing (i) population of wind turbines as per models, make and voltage levels, and (ii) details of LVRT enabled, LVRT design supported and fitted to be enabled, LVRT design supported but to be fitted and LVRT to be retrofitted.

Unquote

Vide clause 8 of the subject ROP, Hon’ble CERC have directed all the parties to submit the information within one month from the issue of ROP that is till 08.03.19.

In this regard, a request for submission of the required data in prescribed format was made to all SLDCs vide e-mail dated 04.03.19 and subsequently letter dated 07.03.19. The information is still awaited.

All SLDCs are requested to submit the required data of all WTGs installed in your control area in the prescribed format at the earliest for onward submission to Hon’ble Commission. Discussion:

All constituents informed that the required data of all WTGs installed in their control area in the prescribed format would be submitted by Mar’19 end for onward submission to Hon’ble Commission. OCC Subcommittee noted the same and agreed for furnishing the data.

Minutes of 517thOCC meeting held on 13th March, 2019 Page 40

9.10 Telemetry issues a. Monthly telemetry status as per CERC mandate In compliance to CERC order dated 29.01.2016 on Petition 07/SM/2014 in the matter on “Non-compliance of Commission`s direction dated 26.9.2012 in Petition No. 168/MP/2011.”, telemetry status of central sector and state sector stations in the region is to be uploaded on WRLDC website every month. The telemetry status for the month of Feb. 2019 is shown in the table below:

The list of stations is attached in Annexure 9.10(a) As agreed in the 515th OCC meeting, the telemetry status has been updated for the month of Feb. 2019 by 5th March. 2019. Discussion:

Representative from Chhattisgarh SLDC informed that the telemetry concerns of non-telemetered substations will be resolved within one month. OCC Subcommittee noted the same.

b. Prolonged outage of Telemetered data. Prolonged outage of telemetry has been observed in the following stations Sr Station Outage Date Restoration Date No

1 IEPL 26-Nov-2018 19:45 Still down

Minutes of 517thOCC meeting held on 13th March, 2019 Page 41

(Maharashtra) hrs 2 Kudus 02-Mar-2019 23:30 Still down (Maharashtra) hrs

SLDC, Kalwa may update the status, reason and possible restoration date Discussion: MSETCL SLDC, informed that continuous follow up with regard to IEPL is being done. The telemetry of Kudus was down due to communication failure. It has started updating since 11th March 2019. OCC Subcommittee noted the same.

c. Correct telemetered data from old NTPC stations The telemetry issues of old NTPC stations viz. Kawas, Gandhar, KSTPS and VSTPS was discussed in 515th OCC meeting. The list of points is attached in Annexure 9.10(c). As per the 515th OCC meeting, a meeting was to be conducted between NTPC and PGCIL for the resolution of issues. KSTPS was attended by Manas automation however some the issues are still pending.

Discussion:

NTPC and PGCIL representative were not available for comment. The same may be taken up for discussion in next OCC meeting. OCC subcommittee noted the same.

d. Regional Communication Meeting under CERC Communication Regulation 2017 As discussed in 515th OCC, a meeting is required to be conducted quarterly at RPC level for discussing issues in communication and telemetry in WR.

Members may finalize the date of the meeting Discussion:

WRPC informed that the meeting will be held in April and will be accordingly scheduled on consultation with Member Secretary.

WRLDC requested Maharashtra SLDC to update the status of data exchange between Maharashtra SLDC Backup and WRLDC Backup which

Minutes of 517thOCC meeting held on 13th March, 2019 Page 42

was supposed to be completed by Feb. 2019 according to MOM of 515th and 516th OCC. Representative from Maharashtra SLDC informed that ICCP server is installed and tested however communication link between Maharashtra Backup SLDC at Ambazari and WRLDC Backup at New Delhi is not available as communication link between Ambazari to Wardha is yet to be established. Maharashtra has approached Powertel for alternate solution regarding communication link. It was informed that functioning of data exchange between Maharashtra BCC and WRLDC BCC is expected to be completed by the end of March, 2019. OCC Subcommittee noted the same.

█ Date and venue of next OCC meeting Date and venue for 518th OCC meeting will be intimated separately.

The sub-committee noted the same.

**********************

Minutes of 517thOCC meeting held on 13th March, 2019 Page 43

Anaulagnak 2.1

frvarI 2019 maoM AavaRi%t ko AaMkD,aoM ka ivavarNa (piScama xao~ Baar p`oYaNa kond` kI AavaRi%t irpaoT- ko AaQaar pr) FREQUENCY PARTICULARS DURING FEBRUARY 2019 (AS PER FREQUENCY REPORT OF WRLDC) 1. INTEGRATED OVER AN-HOUR ek GaMTo maoM samaakilat

1.1 MAXIMUM FREQUENCY 50.12 Hz. BETWEEN 1300 Hrs & 1400 Hrs on 20.02.2019 AiQaktma AavaRi%t

1.2 MINIMUM FREQUENCY 49.83 Hz. BETWEEN 0000 Hrs & 0100 Hrs Hrs. ON 21.02.2019 nyaUnatma AavaRi%t

1.3 AVERAGE FREQUENCY 50.00 Hz. AaOsat AavaRi%t 2. INSTANTANEOUS ta%kailak

2.1 MAXIMUM FREQUENCY 50.27 27 th Feb at 06:03:40 AiQaktma AavaRi%t

2.2 MINIMUM FREQUENCY 49.68 on 01st Feb at 12:42:50 hrs nyaUnatma AavaRi%t

3. %AGE OF TIME WHEN FREQUENCY WAS frvarI 2019 janavarI 2018 idsaMbar 2018 AavaRi%t ka samaya p`itSat maoM

3.1 Below 49.9 Hz. 7.01 10.69 12.68 49.9 hT\ja sao kma 3.2 BETWEEN 49.9 Hz. AND 50.05 Hz. 70.73 70.26 77.03 49.9 hT\ja AaOr 50.05 hT\ja ko baIca mao 3.3 ABOVE 50.05 Hz. 22.26 19.06 10.29 50.05 hT\ja ko ऊपर 4.1 NO. OF TIMES FREQUENCY TOUCHED 49.20 Hz. 0 0 0

4.2 NO. OF TIMES FREQUENCY TOUCHED 49.00 Hz. 0 0 0

4.3 NO. OF TIMES FREQUENCY TOUCHED 48.8 Hz. 0 0 0

वयुतदाब परेखा फरवर 2019 Voltage Profile during the month of Feb'2019 Annexure 2.3

दनांक भोपाल खंडवा इटारसी दमोह नागदा इंदौर वालयर रायपुर रायगढ़ Date Bhopal Khandwa Itarsi Damoh Nagda Indore Gwalior Raipur Raigarh 400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV

अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min 1 419 399 425 408 416 398 423 401 423 403 421 402 415 392 425 416 425 418 2 418 399 423 407 415 398 423 401 420 402 419 401 415 394 424 414 425 416 3 419 401 423 409 417 400 424 402 421 405 419 403 414 394 425 416 426 418 4 420 400 424 409 418 399 425 403 421 405 420 403 415 396 426 415 426 417 5 419 399 423 407 414 398 422 402 420 403 417 401 414 394 425 415 425 417 6 419 401 423 408 415 400 423 403 421 403 418 402 415 398 424 416 425 416 7 421 406 423 409 417 403 426 412 419 407 418 405 411 397 423 414 425 417 8 418 400 423 408 415 400 424 407 419 404 418 402 410 396 424 414 425 417 9 419 400 422 409 416 400 424 404 420 403 418 402 413 395 425 415 426 418 10 419 402 423 409 416 400 423 404 421 404 419 403 415 400 424 412 425 415 11 420 400 424 409 417 398 425 402 422 403 419 402 413 396 425 414 425 416 12 418 398 423 407 415 397 423 402 421 401 419 401 412 395 424 413 425 415 13 417 400 421 407 414 399 422 403 420 403 417 402 415 398 423 413 425 415 14 422 402 423 409 416 400 426 407 421 404 418 402 415 395 422 414 424 415 15 421 403 423 407 416 400 428 411 420 401 418 400 415 396 425 413 425 414 16 418 403 421 408 414 401 425 409 419 404 416 403 412 398 425 417 426 416 17 416 403 421 409 414 401 422 408 419 404 417 404 411 394 423 415 424 417 18 417 403 423 410 414 402 423 408 421 404 418 404 414 399 425 415 425 417 19 417 403 422 410 414 402 424 406 419 404 417 404 415 396 424 416 424 416 20 417 403 422 410 415 402 422 407 419 406 417 404 413 397 422 415 423 415 21 417 402 422 409 415 401 422 415 419 406 418 404 415 394 422 414 422 415 22 418 402 421 407 415 400 416 416 419 404 417 404 410 396 422 415 422 413 23 419 403 421 409 416 402 416 416 418 405 417 404 412 395 422 415 422 415 24 418 405 422 410 415 403 416 416 420 407 418 407 413 395 424 417 424 418 25 417 400 421 408 414 400 416 416 420 405 419 404 414 391 423 416 425 416 26 419 401 423 410 416 400 424 414 422 407 421 406 412 404 423 415 423 416 27 417 403 421 410 414 402 423 407 418 406 418 405 414 395 422 416 423 417 28 419 401 423 410 416 400 424 414 422 407 421 406 412 404 423 415 423 416 422 398 425 407 418 397 428 401 423 401 421 400 415 391 426 412 426 413 दनांक भलाई वधा धुले परल बोईसर कलवा कराड़ असोज देहगाम Date Bhilai Wardha Dhule Parli* Boisar Kalwa Karad Asoj Dehgam 400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV

अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min 1 421 411 426 414 438 410 427 405 425 413 436 414 428 409 418 403 427 413 2 421 410 425 412 437 414 428 404 426 410 437 412 427 408 416 398 426 406 3 422 412 428 414 437 413 430 409 427 416 437 420 428 414 418 406 427 415 4 422 411 428 416 435 415 430 408 428 406 439 407 429 412 418 404 428 414 5 421 411 426 416 435 413 427 408 423 407 432 406 428 409 415 403 427 413 6 421 412 428 415 436 414 427 405 423 406 432 406 427 409 417 402 429 412 7 419 410 426 419 435 411 427 395 424 408 433 410 428 410 416 403 426 411 8 421 410 427 413 437 407 427 398 426 412 436 415 428 409 416 404 429 415 9 421 411 427 413 435 414 427 403 428 410 439 412 428 411 417 405 430 415 10 420 408 426 424 434 414 426 401 428 410 439 412 428 406 418 404 430 414 11 421 408 428 417 437 416 428 405 429 412 439 414 429 412 419 405 431 414 12 419 408 426 415 435 413 426 404 425 409 434 410 426 408 417 402 427 405 13 418 408 427 414 433 413 426 411 424 407 434 406 426 414 417 404 424 406 14 418 409 429 418 437 413 427 407 426 409 437 410 429 409 419 401 429 413 15 420 408 428 415 436 414 427 402 428 413 436 417 428 411 418 402 430 413 16 421 411 426 413 434 408 426 400 428 413 438 417 427 408 417 402 429 413 17 418 410 427 416 436 413 426 406 425 412 436 416 428 411 417 404 430 415 18 420 411 427 415 438 414 426 405 426 409 437 411 430 410 418 402 430 412 19 419 411 426 414 436 412 426 403 425 409 435 410 427 410 417 402 428 413 20 418 410 425 417 434 414 425 406 424 407 434 410 428 409 416 400 427 409 21 417 409 425 416 434 412 426 404 423 405 432 409 425 407 416 400 427 411 22 418 410 424 414 433 413 425 406 426 414 436 417 427 408 417 400 429 414 23 417 410 424 414 433 412 423 402 424 408 434 410 428 411 416 400 428 411 24 419 412 425 418 436 415 427 406 424 410 434 413 426 411 417 405 427 416 25 418 411 426 416 435 411 426 401 424 402 432 403 428 408 418 402 429 413 26 418 410 425 417 435 417 424 405 422 409 432 413 427 411 418 404 429 412 27 418 411 424 416 434 417 424 403 423 406 431 409 428 410 417 402 430 413 28 418 410 425 417 435 417 424 405 422 409 432 413 427 411 418 404 429 412 422 408 429 412 438 407 430 395 429 402 439 403 430 406 419 398 431 405 दनांक कासोर जेतपरु अमरेल वापी मापसु ा कला मगरवाड़ा हज़ीरा बीना इंदौर Date Kasor Jetpur Amreli Vapi Mapusa Kala Magarwada Hazira Bina Indore 400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV 765Kv 765Kv

अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min 1 426 415 412 399 416 406 420 406 431 403 422 408 425 412 419 397 793 766 791 756 2 425 412 412 398 416 400 420 403 430 400 421 405 425 410 418 394 795 767 788 754 3 425 417 414 397 419 408 421 408 431 410 423 411 427 417 419 400 799 768 789 759 4 425 415 413 394 417 398 423 403 433 409 424 403 429 409 420 400 799 770 791 759 5 424 415 413 400 416 400 419 402 431 404 420 405 422 408 416 381 794 766 787 755 6 425 413 416 405 419 410 419 400 429 402 421 402 423 405 416 386 796 767 788 759 7 426 416 418 399 422 402 419 400 429 403 419 402 423 407 418 394 798 776 789 761 8 425 415 415 401 420 400 419 403 431 403 420 402 424 411 418 392 797 772 787 759 9 425 414 417 402 421 407 422 403 433 405 422 403 429 408 420 399 795 763 787 757 10 425 415 418 401 421 405 422 404 433 406 423 406 428 411 421 395 796 767 788 759 11 425 415 418 400 421 405 424 405 436 408 425 406 428 413 420 398 799 768 791 758 12 424 413 413 395 419 400 419 401 431 403 420 401 424 409 417 394 797 766 788 754 13 424 413 415 400 420 406 420 404 430 400 420 406 424 409 418 392 797 770 787 757 14 424 411 415 401 419 403 421 402 431 402 422 403 426 408 418 395 799 774 789 759 15 424 412 416 401 420 408 422 404 431 401 424 406 429 413 422 400 799 770 789 755 16 424 413 416 401 421 406 422 405 430 400 423 407 428 413 420 398 798 774 785 759 17 424 413 415 399 418 404 420 402 431 407 421 404 426 412 419 394 795 765 791 759 18 424 412 414 398 418 401 422 397 435 406 424 401 427 409 419 392 794 770 787 760 19 424 415 412 397 417 402 420 402 430 407 422 404 425 407 416 395 794 771 786 760 20 424 412 415 399 419 402 419 400 432 407 420 400 425 407 416 387 793 770 785 761 21 425 413 416 401 420 405 418 399 430 403 419 400 422 406 415 389 794 768 790 758 22 426 416 415 404 419 407 421 405 432 405 422 407 427 413 421 395 792 769 785 757 23 425 412 418 403 421 406 419 399 431 406 420 400 423 405 419 393 796 774 787 760 24 425 416 416 401 419 407 419 404 430 410 421 406 425 412 418 402 795 777 787 765 25 426 413 419 399 421 404 420 399 432 405 421 400 425 404 417 392 794 764 787 758 26 426 415 416 402 420 407 419 402 433 409 420 404 422 409 416 396 794 766 791 761 27 425 411 417 404 421 407 418 400 431 407 419 401 424 408 417 389 794 767 786 763 28 426 415 416 402 420 407 419 402 433 409 420 404 422 409 416 396 794 766 791 761 426 411 419 394 422 398 424 397 436 400 425 400 429 404 422 381 799 763 791 754 दनांक सासन सतना तमनार कोटरा वडोदरा दगु वालयर सपत सयोन वधा Date Sasan Satna Tamnar Kotra Vadodara Durg Gwalior Sipat Seoni Wardha 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv

अधकतम युनतम अधकतम युनतम अधकतम अधकतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम अधकतम युनतम Max Min Max Min Max Max Max Min Max Min Max Min Max Min Max Min Max Min Max Min 1 779 764 788 766 793 783 794 783 799 770 795 779 797 763 777 765 793 768 799 771 2 781 765 790 768 798 780 800 781 797 763 797 774 799 767 777 762 791 764 796 768 3 783 765 793 766 802 789 804 790 798 774 806 784 800 762 779 766 794 770 802 774 4 783 766 792 770 797 781 799 782 799 770 804 776 801 768 780 764 796 767 800 772 5 779 764 789 766 797 783 799 783 794 768 803 778 798 767 778 765 793 768 800 774 6 781 763 789 765 799 786 800 786 796 768 805 786 798 769 778 766 793 770 803 775 7 782 770 792 775 800 784 801 785 795 769 803 777 798 774 779 764 794 764 799 761 8 784 768 792 773 797 785 798 786 795 765 797 780 799 771 779 766 792 769 798 768 9 784 765 794 765 796 782 798 783 794 770 798 778 799 767 778 764 793 765 799 768 10 782 764 790 768 790 777 792 778 796 770 792 773 798 777 774 760 791 766 798 770 11 784 765 794 768 802 780 803 781 799 772 807 777 801 768 778 762 795 766 805 772 12 783 764 791 765 804 781 806 782 794 767 809 777 797 765 777 763 793 766 802 772 13 781 766 791 772 804 787 806 741 793 770 809 783 800 770 777 764 793 766 802 770 14 783 769 792 774 804 785 805 786 798 766 808 787 799 773 777 765 794 771 802 779 15 784 767 794 771 804 785 805 786 797 766 808 785 800 770 777 762 795 767 803 761 16 783 768 794 771 801 788 802 788 792 766 800 784 798 771 777 764 791 767 796 769 17 780 763 790 767 801 790 802 791 794 780 800 785 797 767 776 765 792 767 805 770 18 781 766 790 771 804 791 806 793 797 768 809 788 798 771 778 766 794 769 804 771 19 781 766 789 771 804 790 806 791 794 767 802 785 797 766 779 767 791 769 797 770 20 779 766 786 770 802 790 805 792 792 766 805 786 796 765 777 767 790 772 799 776 21 778 764 789 767 799 789 800 790 793 764 798 785 799 766 775 765 790 768 796 773 22 777 766 785 768 801 788 802 788 792 768 800 783 795 771 779 768 790 769 794 770 23 779 767 788 772 800 789 801 789 791 761 799 786 797 771 778 768 790 771 793 772 24 779 766 787 771 804 791 805 792 796 772 807 792 799 767 780 772 793 777 800 782 25 778 763 787 763 796 786 797 786 795 765 802 784 799 763 780 770 791 771 797 775 26 777 764 787 765 794 784 794 784 796 765 800 785 796 780 780 770 793 771 797 777 27 779 764 787 765 798 785 798 784 793 769 801 786 798 762 780 771 790 772 796 775 28 777 764 787 765 794 784 794 784 796 765 800 785 796 780 780 770 793 771 797 777 784 763 794 763 804 777 806 741 799 761 809 773 801 762 780 760 796 764 805 761 Annexure 2.5 piScama xao~Iya ivaVut saimait, mauMba[- WESTERN REGIONAL POWER COMMITTEE, MUMBAI saM. pxaoivasa / p`caalana/ ivaVut kTaOityaaM /2018-19 idnaaMk : 06.03.2019 From: AQaIxaNa AiBayaMta (p`caalana), pxaoivasa, mauMba[- Superintending Engineer (Operation), WRPC, Mumbai

To: 1. Director (GM), 6th Floor, Sewa Bhawan, CEA, New Delhi (fax no. 011- 26109750) 2. Chief Engineer, OPM Division, CEA, New Delhi (Fax no. 011-26732337, 26107416) ivaYaya : -frvarI 2019 ko daOrana piScama xao~ maoM ivaVut kTaOityaaM/ pabMaidyaaM Subject: - Power Cut/Restrictions in Western Region for the month of February-2019 k : gaujarat Gujarat

1 ]VaoogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid 1 Power Cut/ Restriction on Industries, Load Shedding in the state etc ivavarNa Details ivaVut kTaOtI kI maa~a pabandI ka samaya p`it idna kula }jaa- Remark Quantum of Restriction Timing kTaOtI Total power cut From Total Energy Cut (MW) Energy Cut (MUs /day (MUs /day (a) Power SaUnya Nil SaUnya Nil SaUnya Nil SaUnya Nil All industries are allowed to run Restrictions(Evening peak their units on all days of week & Hour) on non continuous if they want to avail staggered holiday, then they will have to process HT/LT IndustriesM SaUnya Nil SaUnya Nil SaUnya Nil SaUnya Nil stagger on notified day only & (b) Baar inayamana Load Shedding cannot avail as per their choice. All industries are required to (c) Anya jaanakarI Other keep their recess timings information SaUnya Nil SaUnya Nil SaUnya Nil SaUnya Nil staggered. 1.Weekly Off SaUnya Nil SaUnya Nil SaUnya Nil SaUnya Nil 2.Staggering of power supply 2 kRiYa xao~ kao ivaVut AapUit- 2. Power supply to Agricultural Sector: - ivavarNa Details sao From tk To idnaaMk p`it idna AapUit- GaMTo Supply Hours per day idnaaMk Date Date Max. (Hrs) Min. (Hrs) Average (Hrs) 2.1 Three phase supply 01.02.2019 28.02.2019 8:00 8:00 8:00 2.2 Single Phase supply 01.02.2019 28.02.2019 16:00 16:00 16:00

3 Anya jaanakarI 3. Any other information 1. Jayotigram Yojana-24 hours. 2. There is no load shedding in Urban areas

Page 1 of 4

K : maQya p`doSa Madhya Pradesh 1 ]VaoogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid 1 Power Cut/ Restriction on Industries, Load Shedding in the state etc ivavarNa Details ivaVut kTaOtI kI maa~a pabandI ka samaya p`it idna kula }jaa- kTaOtI Quantum of Restriction Timing Total Energy Cut power cut (MW) sao From tk To (MUs /day (a) Power Restrictions(Evening NIL NIL NIL NIL peak Hour) on non continuous process HT/LT IndustriesM (b) Baar inayamana Load Shedding (c) Anya jaanakarI Other information NIL NIL NIL NIL 1.Weekly Off 2.Staggering of power supply 2 kRiYa xao~ kao ivaVut AapUit- 2. Power supply to Agricultural Sector: - ivavarNa Details sao From tk To idnaaMk p`it idna AapUit- GaMTo Supply Hours per idnaaMk Date Date day Max. (Hrs) Min. (Hrs) Average (Hrs) 2.1 Three-Phase Supply(Mixed) 01.02.2019 28.02.2019 23:39 22:35 23:36 2.2 Three-Phase Supply(DLF) 01.02.2019 28.02.2019 23:44 23:11 23:34 2.3 Three-Phase Supply(Irrigation) 01.02.2019 28.02.2019 09:56 09:46 09:53 3 Anya jaanakarI 3. Any other information SahrI xao~aoM maoM inayamana ivaVut kTaOityaaM Scheduled Power cuts in Urban Areas ivavarNa Details sao From tk To idnaaMk Aaosat p`itidna Average Supply idnaaMk Date Date AapUit- GaMTo Hours per day Max. (Hrs) Min. (Hrs) Average (Hrs) 3.1 Commissionary H. Qtrs. 01.02.2019 28.02.2019 23:54 23:36 23:49 3.2 District Head Qtrs. 01.02.2019 28.02.2019 23:56 23:41 23:51 3.3 Tehsil Head Qtrs. 01.02.2019 28.02.2019 23:51 23:30 23:43

Page 2 of 4

ga : maharaYT/ Maharashtra 1 ]QyaaogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid

1 Power Cut/ Restriction on Industries, Load Shedding in the state etc Details Quantum of Restriction Total Energy power cut (MW) Timing Cut (MUs From To /day (a) Power Restrictions(Evening NIL NIL NIL peak Hour) on non-continuous process HT/LT Industries NIL (b) Load Shedding

(c) Other information NIL NIL NIL NIL 1.Weekly Off

2.Staggering of power supply Industrial Staggering LS Withdrawn from 03/02/2012

2. Power supply to Agricultural Sector: - Details From To Supply Hours per day Date Date Max. Min. Average (Hrs) (Hrs) (Hrs) 2.1 Three-Phase 10 8 9 Supply 01.02.2019 28.02.2019 2.1 Single-Phase 18 18 18 Supply 01.02.2019 28.02.2019

3. Scheduled Power cuts in Urban Areas

Details From To Average Supply Date Date Hours per day Max. Min. (Hrs) Average (Hrs) (Hrs) 3.1 Commissionary H. Qtrs. 01.02.2019 28.02.2019 NIL NIL NIL 3.2 District Head Qtrs. 01.02.2019 28.02.2019 NIL NIL NIL 3.3 Tehsil Head Qtrs. 01.02.2019 28.02.2019 NIL NIL NIL

4. Any other information Date Avg Mus/Day

3. Load Shedding due to NIL Transmission Constraint in real time. NIL NIL

NIL

Page 3 of 4

Ga : C%tIsagaZ, Chhattisgarh: ]VaoogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid 1 Power Cut/ Restriction on Industries, Load Shedding in the state etc ivavarNa Details ivaVut kTaOtI kI maa~a pabandI ka samaya p`it idna kula }jaa- kTaOtI Quantum of Restriction Timing Total Energy Cut power cut (MW) sao From tk To (MUs /day) (a)Power Restrictions(Evening 34.20 MW on 19- peak Hour) on continuous 02-2019 17:30 19:04 0.002 process HT/LT Industries M (b) Baar inayamana Load Shedding 131 MW [Max] on 26-02-2019 09:01 09:24 0.26

(c) Anya jaanakarI Other information 1.Weekly Off SaUnya Nil SaUnya Nil SaUnya Nil SaUnya Nil 2.Staggering of power supply SaUnya Nil SaUnya Nil SaUnya Nil SaUnya Nil 2 kRiYa xao~ kao ivaVut AapUit- 2. Power supply to Agricultural Sector: - ivavarNa Details sao From tk To idnaaMk p`it idna AapUit- GaMTo Supply Hours per day idnaaMk Date Date Max. (Hrs) Min. (Hrs) Average (Hrs) 2.1 Three-Phase NIL NIL Supply(Mixed) 01.02.2019 28.02.2019 NIL 2.2 Three-Phase NIL NIL NIL Supply(DLF) 01.02.2019 28.02.2019 2.3 Three-Phase Supply(Irrigation) 01.02.2019 28.02.2019 18:00 18:00 18:00 3 Anya jaanakarI 3. Any other information SahrI xao~aoM maoM inayamana ivaVut kTaOityaaM Scheduled Power cuts in Urban Areas ivavarNa Details sao From tk To idnaaMk Aaosat p`itidna Average Supply idnaaMk Date Date AapUit- GaMTo Hours per day Max. (Hrs) Min. (Hrs) Average (Hrs) 3.1 Commissionary H. Qtrs. 01.02.2019 28.02.2019 NIL NIL NIL 3.2 District Head Qtrs. 01.02.2019 28.02.2019 NIL NIL NIL 3.3 Tehsil Head Qtrs. 01.02.2019 28.02.2019 NIL NIL NIL

**************

Page 4 of 4

सलं नक Annex-2.6 अिनवाय युिनट आऊटेज का फरवरी 2019 का िवतारत यौरा Details of forced unit outages during the month of feb’2019

अनु युिनट सघं टक मता से कारण मांक Unit Constituent मेगावॉ From तक Reason /IPP Sl.No समय िदनांक To ट Cap.M समय िदनांक W Time Date Time Date

1. जीआईपीसीएल टेज GSECL 165 00:00 01-03-2018 Still out Still out No schedule GIPCL STG 2 2. डीजीबीपी DGBP 1 GSECL 107 12:54 25-09-2018 06:23 02-03-2019 Baring gear problem 250 3. BECL 2 GSECL 22:49 20-10-2018 Still out Still out Boiler inspection बीईसीएल 4. गांधीनगर Gandhinagar 3 GSECL 120 00:13 01-02-2019 02:56 04-02-2019 RSD 5. डीजीबीपी DGBP 3 GSECL 375 14:22 05-11-2018 Still out Still out RSD

6. उतरण टेज GSECL 19:39 15-01-2019 Still out Still out RSD UTRAN STG II 1 05-03- 7. BECL 1 GSECL 250 07:54 07-02-2019 12:01 BTL बीईसीएल 2019 8. गांधीनगर Gandhinagar 3 GSECL 210 15:40 08-02-2019 09:12 13-02-2019 RSD 9. एसटीपीएस STPS 3 GSECL 250 08:54 09-02-2019 04:08 13-02-2019 RSD.

10. वानकबोरी Wanakbori 2 GSECL 210 15:48 13-02-2019 Still out Still out RSD

11. वानकबोरी Wanakbori 1 GSECL 210 16:48 13-02-2019 Still out Still out RSD 12. वानकबोरी Wanakbori 4 GSECL 210 18:00 13-02-2019 11:59 22-02-2019 RSD 13. वानकबोरी Wanakbori 5 GSECL 210 03:15 14-02-2019 01:56 20-02-2019 RSD. 14. एसटीपीएस STPS 3 GSECL 125 20:39 17-02-2019 03:55 20-02-2019 RSD 15. एसटीपीएस STPS 4 GSECL 250 08:57 23-02-2019 Still out Still out RSD 16. वानकबोरी Wanakbori 4 GSECL 210 11:55 23-02-2019 Still out Still out RSD 17. गांधीनगर Gandhinagar 2 GSECL 120 15:40 24-02-2019 01:47 04-03-2019 RSD 18. ओपीजीएस OPGS 1 GSECL 150 23:59 24-02-2019 Still out Still out Annual Maintenance 19. जीपीपीसी GPPC 2 GSPC 351 20:47 17-10-2018 Still out Still out RSD 20. जीपीपीसी GPPC 1 GSPC 351 20:40 02-11-2018 Still out Still out RSD 21. िजसगे टेज GSEG Stage II 1 GSPC 351 17:01 06-02-2019 Still out Still out RSD 22. जीपके GPEC 4 CLPIPL 241 16:36 06-12-2018 Still out Still out PPA expired 23. एसएलपीपी SLPP 3 GIPCL 125 10:57 17-02-2019 05:15 21-02-2019 BTL. 24. एसएलपीपी SLPP 1 GIPCL 125 15:00 19-02-2019 07:50 23-02-2019 BTL 25. परली Parli 4 MAHAGENCO 210 19:47 05-07-2015 Still out Still out Economic shutdown 26. परली Parli 5 MAHAGENCO 210 14:55 06-07-2015 Still out Still out Economic shutdown

27. पायोनीर MAHAGENCO 388 17:45 07-02-2017 Still out Still out RSD Pioneer(262+126) 1 Uran 7 Compressor & Turbine 28. उरण MAHAGENCO 108 12:53 20-07-2018 Still out Still out Blade Failure. 29. उरण URAN B0 1 MAHAGENCO 120 12:19 08-09-2018 Still out Still out Transformer shifting work Withdrawn due to unit B0 30. Uran 8 MAHAGENCO 108 22:08 08-09-2018 Still out Still out उरण & U-7 heat rate high

31. पारस Paras 3 MAHAGENCO 250 00:55 15-09-2018 Still out Still out Stator Earth Fault 32. डबयपू ीसीएल WPCL 1 MAHAGENCO 135 04:48 25-11-2018 Still out Still out NO PPA 33. डबयपू ीसीएल WPCL 2 MAHAGENCO 135 00:00 27-11-2018 Still out Still out No schedule 34. परली Parli 7 MAHAGENCO 250 00:00 12-12-2018 Still out Still out Zero schedule 35. परली PARLI 6 MAHAGENCO 250 00:00 12-12-2018 Still out Still out Zero schedule 36. भसु ावल Bhusawal 3 MAHAGENCO 210 03:00 14-12-2018 Still out Still out No Schedule 37. डबयपू ीसीएल WPCL 4 MAHAGENCO 135 00:00 15-12-2018 Still out Still out RSD 38. वीआईपीएल VIPL 1 MAHAGENCO 300 00:30 29-12-2018 Still out Still out Coal shortage 39. नािसक Nasik 3 MAHAGENCO 210 19:33 09-01-2019 Still out Still out RSD 40. परली PARLI 8 MAHAGENCO 250 12:00 12-01-2019 Still out Still out Zero Schedule 41. वीआईपीएल VIPL 2 MAHAGENCO 300 00:15 17-01-2019 Still out Still out Coal Shortage 42. कोराडी Koradi 7 MAHAGENCO 210 18:21 19-01-2019 Still out Still out Poor coal receipt 43. पायोनीर Pioneer- 1 MAHAGENCO 388 17:45 07-02-2017 Still out Still out RSD 44. कोराडी Koradi 6 MAHAGENCO 210 22:09 03-02-2019 07:46 14-02-2019 BTL 45. चंपरु Chandrapur 4 MAHAGENCO 210 23:23 05-02-2019 23:13 10-02-2019 Maintenance 46. नािसक Nasik 4 MAHAGENCO 210 05:18 08-02-2019 14:13 24-02-2019 RSD 47. चंपरु Chandrapur 5 MAHAGENCO 500 12:32 09-02-2019 02:30 15-02-2019 Air heater basket replacement. 48. पारस Paras 4 MAHAGENCO 250 04:55 10-02-2019 04:36 14-02-2019 APH problem 49. जयगड Jaigad 1 MAHAGENCO 300 14:34 15-02-2019 14:28 18-02-2019 Condenser tube leakage 50. चंपरु Chandrapur 6 MAHAGENCO 500 22:06 20-02-2019 Still out Still out Rotor earth fault 51. चंपरु Chandrapur 8 MAHAGENCO 500 19:40 21-02-2019 07:28 25-02-2019 BTL Zero Schedule ( RSD), 52. Nasik 3 MAHAGENCO 210 17:20 23-02-2019 Still out Still out नािसक changeover with unit-4

53. कोयना टेज MAHAGENCO 250 10:00 26-02-2019 11:35 02-03-2019 Pipe Leakages Koyna Stag-IV 3 BTL Super heater zone at 54. Koradi 2 MAHAGENCO 660 20:11 28-02-2019 00:31 04-03-2019 कोराडी penthouse Electrical fault/later Stator 55. SGTPS 3 MPPGCL 210 03:52 26-01-2019 Still out Still out एसजीटीपीएस earth fault 56. सातपरु ा Satpura II 6 MPPTGL 200 11:15 08-02-2019 10:47 12-02-2019 Reheater tube leakage. 57. सातपरु ा Satpura II 6 MPPGCL 200 13:50 14-02-2019 17:55 17-02-2019 BTL 58. एसजीटीपीएस SGTPS 5 MPPGCL 500 14:34 22-02-2019 20:45 25-02-2019 BTL 59. ोबे Trombay 6 TPC 500 00:00 06-03-2016 Still out Still out Economic shutdown Kept on dry preservation/ Gas 60. RGPPL-1B RGPPL 230 23:00 31-03-2014 Still out Still out आरजीपीपीएल Shortage 61. आरजीपीपीएल RGPPL-1A RGPPL 320 13:30 8-07-2014 Still out Still out Less requisition Unit change over; less gas 62. RGPPL 3A RGPPL 230 19:48 05-02-2019 Still out Still out आरजीपीपीएल fuel Unit change over; less gas 63. RGPPL 3B RGPPL 230 17:45 06-02-2019 Still out Still out आरजीपीपीएल fuel अमरावती टीपीपी Rattan Power India 64. 270 16:30 14-12-2018 Still out Still out No Schedule AMRAVATI Ltd TPP(INDIABULL)3 अमरावती टीपीपी Rattan Power India 65. 270 00:00 20-12-2018 Still out Still out RSD AMRAVATI Ltd TPP(INDIABULL)4 अमरावती टीपीपी Rattan Power India 66. 270 19:30 27-12-2018 Still out Still out RSD AMRAVATI Ltd TPP(INDIABULL)2 अमरावती टीपीपी Rattan Power India 67. 270 19:30 28-12-2018 Still out Still out RSD AMRAVATI Ltd TPP(INDIABULL)5

अमरावती टीपीपी Rattan Power India 68. 270 02:17 27-01-2019 Still out Still out RSD AMRAVATI Ltd TPP(INDIABULL)1

69. एपीएमएलितरोड़ा ATIL 660 14:52 13-02-2019 16:47 17-02-2019 APH-B gearbox problem APML Tiroda 5 Condenser tube 70. जपे ीएल टेज JPL Stg-I 2 JPL 250 21:15 30-08-2018 Still out Still out leakage/Coal shortage since 00:00hrs of 02-09-2018 71. जपे ीएल टेज JPL Stg-I 1 JPL 250 00:00 24-10-2018 Still out Still out Coal shortage 72. जपे ीएल टेज JPL Stg-II 4 JPL 600 12:38 29-12-2018 Still out Still out Coal feeding problem 73. जपे ीएल टेज JPL Stg-II 3 JPL 600 11:16 08-02-2019 Still out Still out Condenser Tube Leakage 74. जपे ीएल टेज JPL Stg-I 3 JPL 250 00:00 10-02-2019 Still out Still out Coal Shortage 75. जपे ीएल टेज JPL Stg-II 1 JPL 600 00:00 15-02-2019 23:08 21-02-2019 Coal shortage 76. ईपीजीएल EPGL -2 ESSAR 600 20:25 24-10-2017 Still out Still out Coal shortage 77. ईपीजीएल EPGL 1 ESSAR 600 18:51 23-01-2018 Still out Still out Coal shortage 78. एसार Essar(Mahan) 2 ESSAR 600 00:02 08-11-2018 14:25 14-02-2019 Low schedule 79. एसार ESSAR(Mahan) I ESSAR 600 15:03 14-02-2019 Still out Still out Maintenance work 80. एसार Essar(Mahan) 2 ESSAR 600 07:58 27-02-2019 23:51 04-03-2019 APH stuck up 81. उनोसुजन UNOSUGEN-1 TPGL 382 21:55 04-03-2016 Still out Still out RSD 82. डीजीईएन DGEN-52 TPGL 400 20:00 25-11-2016 Still out Still out No schedule(NO PPA) 83. डीजीईएन DGEN-53 TPGL 400 19:12 23-12-2016 Still out Still out No schedule(NO PPA) 84. डीजीईएन DGEN-51 TPGL 400 00:00 22-05-2018 Still out Still out No schedule(NO PPA) 85. जीपके जीटी GPEC GT 3 TPGL 138 11:36 10-12-2018 Still out Still out No schedule(PPA expired) 86. जीपके जीटी GPEC GT 1 TPGL 138 12:34 10-12-2018 Still out Still out No schedule(PPA expired) 87. जीपके जीटी GPEC GT 2 TPGL 138 18:55 10-12-2018 Still out Still out No schedule(PPA expired) 88. सजू न SUGEN 2 TPL 382 15:03 31-01-2019 12:48 15-02-2019 RSD 89. सजू न SUGEN 2 TPGL 382 19:30 16-02-2019 07:00 25-02-2019 RSD Stator earth fault protection 90. KWPCL 1 KWPCL 600 22:12 22-05-2017 Still out Still out केडलपू ीसीएल operated/maintenance APH problem./Coal shortage 91. केएसके महानदी KMPCL 600 02:29 03-10-2018 Still out Still out KSK Mahanadi 3 since 00:00hrs/15-10-2018

92. केएसके महानदी KMPCL 600 23:51 29-01-2019 16:47 19-02-2019 Coal shortage KSK Mahanadi 2 93. आईईपीएल IEPL I IEPL 270 21:26 28-08-2018 Still out Still out Coal Shortage

94. आरकेएम पावर RKMPPL 360 12:57 31-01-2019 Still out Still out coal shortage RKM Power 1

95. आरकेएम पावर RKMPPL 360 15:57 04-01-2019 Still out Still out coal shortage RKM Power 2 Regulation of Power Supply 96. टीआरएन एनिज TRN 300 00:00 04-01-2019 Still out Still out TRN Energy 2 by PGCIL 97. बालको BALCO- 1 BALCO 300 16:44 09-02-2019 02:21 19-02-2019 HP Bypass Problem Problem in ash handling 98. BALCO(300 MW) 2 BALCO 300 16:13 24-02-2019 Still out Still out बालको system. Units tripped due to boiler 99. SKS 2 SKS 300 13:20 01-01-2019 Still out Still out एसकेएस MCC cable fault. 100. एसकेएस SKS 1 SKS 300 00:16 10-02-2019 04:55 13-02-2019 Coal Shortage

101. धारीवाल एसटीयू DIL 300 10:50 12-01-2019 Still out Still out Coal Shortage Dhariwal STU 1 102. एसीबीआईएल ACBIL 135 09:59 02-02-2019 Still out Still out BTL ACBIL 1

103. सीजीपीएल CGPL 1 CGPL 830 13:13 20-02-2019 14:34 23-02-2019 BTL 104. कॅ स KAPS 1 NPCIL 220 08:52 11-03-2016 Still out Still out Reactor side problem

105. सोलापुर NTPC 660 00:23 14-11-2018 Still out Still out RSD Solapur STPS 1 IP wet steam protection 106. गडरवाड़ा NTPC 800 03:13 24-11-2018 07:42 16-02-2019 Gadarwada 1 operated 107. गांधार Gandhar GT 2 2 NTPC 144 13:30 12-01-2019 Still out Still out RSD 108. कावास Kawas GT 2B NTPC 106 11:23 24-01-2019 13:04 20-02-2019 RSD 109. कावास Kawas GT 2A NTPC 106 13:17 24-01-2019 08:48 20-02-2019 RSD 110. मौदा Mouda 2 NTPC 500 03:13 27-01-2019 19:27 20.02.2019 RSD 111. मौदा Mouda 3 NTPC 500 21:50 31-01-2019 10:01 22-02-2019 RSD During start-up preparedness 112. कावास Kawas ST 2C NTPC 106 18:15 01-02-2019 19:15 04-02-2019 checking, non-closure of CV- 2 was observed 113. कावास Kawas ST 2C NTPC 106 19:15 04-02-2019 12:28 20-02-2019 RSD 114. गांधार Gandhar GT 1 1 NTPC 144 12:13 05-02-2019 Still out Still out RSD, Change over with GT-3 RSD, all GTs are on RSD 115. गांधार Gandhar 4 NTPC 144 12:02 11-02-2019 18:36 28-02-2019 due to less requisition on RLNG 116. गांधार Gandhar GT 3 NTPC 144 12:09 11-02-2019 Still out Still out RSD 117. कावास Kawas GT 1A NTPC 106 12:40 20-02-2019 Still out Still out RSD; Changeover of units 118. कावास Kawas ST 1C NTPC 106 13:47 20-02-2019 Still out Still out RSD; Changeover of units 119. कावास Kawas GT 1B NTPC 106 13:54 20-02-2019 Still out Still out RSD; Changeover of units Note: Units out for more than 72 hrs are only included.

संलनक Annex-2.7

िनयोिजत युिनट आऊटेज का फरवरी 2019 का िवतारत यौरा Details of planned unit outages during the month of Feb. 2019 अनु युिनट सघं टक मता से तक कारण मांक Unit Constituent/ मेगावॉट From To Reason IPP Sl.No Cap.MW समय िदनांक समय िदनांक Time Date Time Date 1. डबयूपीसीएल WPCL 3 MAHAGENCO 135 00:28 01-11-2018 Still out Still out AOH 2. उकई Ukai 4 GSECL 200 00:35 20-01-2019 23:00 13-02-2019 AOH 3. वानकबोरी Wanakbori 6 GSECL 210 00:00 28-01-2019 21:40 01-03-2019 AOH

4. मारवा टीपीएस CSPGCL 500 22:44 15-01-2019 Still out Still out AOH Marwa TPS 1 5. बालको BALCO- 3 BALCO 300 23:30 11-01-2019 04:43 03-02-19 AOH 6. वीएसटीपीएस VSTPS 13 NTPC 500 00:19 23-01-2019 14:53 16-02-2019 AOH 7. जपे ी िबना JP BINA MPPGCL 250 00:00 26-02-2019 Still out Still out AOH

Commissioning of New Elements-Feb'19 Annexure 2.9 a)Generating Units

Date of Sl. No. Owner/ Location(Const.) Station Name Capacity (MW) Unit No. Date of COD Synchronization 14-02-2019(Date of 1 RUMS/MP Rewa,Arinsun(Solar) 90+50 3 26/07/2018 added 50MW capacity commisioned) 2 NTPC, Maharashtra Solapur 660 2 15/02/2019 b)Transmission Lines

Date of Added Line Length (in Sl. No. Owner/ Location(Const.) Line Name Ckt No. KV Synchronization Km) 1 MPPTCL/MP Pitampur-Badnawar I 400 08/02/2019 71 (Line will be as Ukai-Kosamaba- 2 GETCO/Gujarat Ukai-Kosamaba Ckt-1 LILO at Vav 400 10/02/2019 61 1 bypassed at Vav) LILO of 220kV Bhanpura- 3 ISTS(MP & RAJ) Ranpur(Raj)-Bhanpura I 220 16/02/2019 Sakatpur line at Ranpur(RJ) 4 MPPTCL/MP Rajgarh-Badnawar-ILILO of 400kV Nagda-Rajgarh 400 17/02/2019 4 Ckt-I at Badnawar 5 MPPTCL/MP Badnawar-Nagda-I 400 19/02/2019 6 MPPTCL/MP Rajgarh-Badnawar-II LILO of 400kV Nagda-Rajgarh 400 17/02/2019 4 7 MPPTCL/MP Badnawar-Nagda-II Ckt-2 at Badnawar 400 19/02/2019 PGCIL/Gujarat 8 Bhuj PS-Banaskantha I 765 23/02/2019 289 (Line will be as Chorania- Chorania-Kosamba Ckt-2 with LILO 9 GETCO/Gujarat Kosamaba-2 bypassed at 400 23/02/2019 46 line of Panchham (Direct line) Panchham) 10 MPPTCL/MP Singhaji Stg II-Pitampur III 400 26/02/2019 140 11 MPPTCL/MP Singhaji Stg II-Pitampur IV 400 26/02/2019 140 12 GETCO/Gujarat(IR Line) Banaskantha-Chhittorgarh II 765 26/02/2019 302 13 GETCO/Gujarat(IR Line) Banaskantha-Chhittorgarh I 765 28/02/2019 302 Total 1359 c)ICTs

Capacity Sl. No. Owner/ Location(Const.) Station Name ICT No KV Ratio Date (MVA) 1 PGCIL/MP Rewa 3 400/220 500 05/02/2019 2 PGCIL/Gujarat Bhuj PS 2 765/400 1500 27/02/2019 3 MSETCL/Maharashtra Kalwa 4 400/220 500 28/02/2019 d)Line Reactor Capacity Sl. No. Owner/ Location(Const.) Station Name Line Name KV Date (MVAR) 1 PGCIL/Gujarat Banaskantha Bhuj-Banskantha-I 765 330 23/02/2019 2 PGCIL/Gujarat Bhuj PS Bhuj-Banskantha-I 765 330 23/02/2019 Banaskantha-Chhittorgarh-I(IR 3 PGCIL/Gujarat Banaskantha 765 330 26/02/2019 Line) Banaskantha-Chhittorgarh -II(IR 4 PGCIL/Gujarat Banaskantha 765 330 28/02/2019 Line) e)Bus Reactor Capacity Sl. No. Owner/ Location(Const.) Station Name B/R No KV Date (MVAR) 1 PGCIL/Gujarat Bhuj PS 1 765 330 26/02/2019 f) Spare Elements Charged Capacity Sl. No. Owner/ Location(Const.) Station Name Element KV Date (MVA/MVAR) NIL g) FACTS Devices

Capacity Sl. No. Owner/ Location(Const.) Station Name Element No KV (MVAR) NIL (As on 06.03.2019) CENTRAL ELECTRICITY AUTHORITY Annexure 2.11 FUEL MANAGEMENT DIVISION DAILY COAL STOCK REPORT COAL STOCK POSITION FOR COAL LINKAGE BASED THERMAL POWER STATIONS IN THE COUNTRY

Actual Stock Critical(*)/Sup Requirement PLF % PLF % Normative er Critical(**) Mode of Capacity for the day Region/State Name of Thermal Power Station Sector (Feb, (Apr,18- Stock Reqd. In '000 Tonnes' as per Trigger Reasons for critical coal stock/Remarks Transport (MW) (In '000 In Days 2019) Feb,19) (Days) level & other Tonnes') Indigenous Import Total conditions

1 2 3 4567 8 9 1011121314 15 Northern Haryana 1 RAIL INDIRA GANDHI STPP JV 1500 62.5 58.3 25 12.99 72.81 33.31 106.12 8 2 RAIL MAHATMA GANDHI TPS P 1320 65.2 59.5 25 10.47 335.66 0 335.66 32 3 RAIL PANIPAT TPS S 920 16.6 42.5 25 8.07 219.13 0 219.13 27 4 RAIL RAJIV GANDHI TPS S 1200 0.0 39.6 25 10.88 372.78 0 372.78 34 5 RAIL YAMUNA NAGAR TPS S 600 77.8 61.3 25 5.83 155.38 0 155.38 27 Punjab 6 RAIL GH TPS (LEH.MOH.) S 920 0.0 33.0 30 7.40 435.85 0 435.85 59 7 RAIL GOINDWAL SAHIB TPP P 540 64.5 49.3 30 6.50 13.66 0 13.66 2 CIL supply 89% of prorata ACQ 8 RAIL RAJPURA TPP P 1400 81.8 77.0 30 10.97 93.73 50.02 143.75 13 9 RAIL ROPAR TPS S 840 0.0 20.2 25 7.42 372.32 0 372.32 50 10 RAIL TALWANDI SABO TPP P 1980 41.6 61.3 25 17.81 309.41 109.9 419.31 24 Rajasthan Total coal stock (Linkage + Captive) available with the plant 11 RAIL CHHABRA TPP S 1660 91.1 82.4 30 6.21 0 0 0 0 as on 31.01.2019 is 2,59,800 Tonnes. 12 RAIL KAWAI TPS P 1320 80.7 65.3 30 19.84 28.93 5.65 34.58 2 CIL Supply 90% of prorata ACQ. 13 RAIL KOTA TPS S 1240 76.1 75.1 30 16.89 67.69 0 67.69 4 * CIL Supply to RRVUNL 67% of prorata ACQ. 14 RAIL SURATGARH TPS S 1500 41.8 58.0 30 12.20 241.3 0 241.3 20 Uttar Pradesh 15 PITHEAD ANPARA C TPS P 1200 64.7 79.4 15 9.53 84.01 0 84.01 9 16 PITHEAD ANPARA TPS S 2630 85.0 87.2 15 31.27 449.63 0 449.63 14 17 RAIL BARKHERA TPS P 90 0.0 20.6 25 0.77 7.24 0 7.24 9 18 RAIL DADRI (NCTPP) C 1820 56.6 68.2 30 15.88 196.5 44.01 240.51 15 19 RAIL HARDUAGANJ TPS S 605 22.1 59.1 25 4.88 84.43 0 84.43 17 20 RAIL KHAMBARKHERA TPS P 90 0.0 19.6 30 0.77 7.63 0 7.63 10 21 RAIL KUNDARKI TPS P 90 0.0 28.2 30 0.77 6.22 0 6.22 8 22 RAIL LALITPUR TPS P 1980 0.0 33.9 30 15.91 481.02 0 481.02 30 23 RAIL MAQSOODPUR TPS P 90 0.0 19.6 30 0.77 5.03 0 5.03 7 24 RAIL OBRA TPS S 1094 41.9 37.4 20 11.93 267.08 0 267.08 22

25 RAIL PARICHHA TPS S 1140 55.6 51.3 30 10.12 76.98 0 76.98 8

26 RAIL PRAYAGRAJ TPP P 1980 41.1 44.9 25 16.62 59.68 0 59.68 4 CIL Supply 77% of prorata ACQ. 27 PITHEAD RIHAND STPS C 3000 89.1 85.8 15 43.24 1072.11 0 1072.11 25 28 RAIL ROSA TPP Ph-I P 1200 8.8 42.2 25 9.95 630.66 0 630.66 63 29 PITHEAD SINGRAULI STPS C 2000 88.1 83.7 15 28.43 556.04 0 556.04 20 30 RAIL TANDA TPS C 440 37.3 67.1 25 3.74 483 0 483 129 31 RAIL UNCHAHAR TPS C 1550 65.3 72.3 25 14.42 585.91 0 585.91 41 32 RAIL UTRAULA TPS P 90 0.0 27.2 30 0.77 8.29 0 8.29 11 Total of Northern Region 38029 24 373.27 7780.11 242.89 8023 21 1 Actual Stock Critical(*)/Sup Requirement PLF % PLF % Normative er Critical(**) Mode of Capacity for the day Region/State Name of Thermal Power Station Sector (Feb, (Apr,18- Stock Reqd. In '000 Tonnes' as per Trigger Reasons for critical coal stock/Remarks Transport (MW) (In '000 In Days 2019) Feb,19) (Days) level & other Tonnes') Indigenous Import Total conditions

Western Chhatisgarh 33 RAIL AKALTARA TPS P 1800 30.7 49.4 15 15.44 98.94 0.2 99.14 6 Coal supply as per payment 34 RAIL BALCO TPS P 600 56.6 53.5 15 5.62 5.1 0 5.1 1 CIL Supply 94% of prorata ACQ 35 ROAD BANDAKHAR TPP P 300 93.7 80.4 15 5.19 100.22 0 100.22 19 36 RAIL BARADARHA TPS P 1200 66.5 64.6 15 13.22 290.89 0 290.89 22 37 RAIL BHILAI TPS JV 500 83.6 76.9 20 7.63 68.36 0 68.36 9 38 RAIL DSPM TPS S 500 84.8 87.7 15 7.01 142.77 0 142.77 20 39 PITHEAD KORBA-II S 440 39.2 39.9 15 5.62 41.21 0 41.21 7 40 PITHEAD KORBA STPS C 2600 94.8 87.3 15 37.11 215.98 0 215.98 6 41 PITHEAD KORBA-WEST TPS S 1340 80.7 81.2 15 15.03 318.3 0 318.3 21 42 RAIL MARWA TPS S 1000 46.0 74.1 15 8.60 230.98 0 230.98 27 43 RAIL NAWAPARA TPP P 600 48.3 59.8 15 6.37 76.27 0 76.27 12 44 RAIL PATHADI TPP P 600 78.7 81.8 15 8.06 30 0 30 4 CIL Supply 83% of prorata ACQ. 45 PITHEAD SIPAT STPS C 2980 90.4 91.1 15 44.58 317.25 0 317.25 7 46 RAIL TAMNAR TPP P 2400 46.9 39.6 20 18.15 14.18 0 14.18 1 CIL Supply 87% of prorata ACQ. 47 RAIL UCHPINDA TPP P 1080 0.0 28.2 15 9.27 21.55 0 21.55 2 CIL Supply 75% of prorata ACQ. Gujarat 48 RAIL GANDHI NAGAR TPS S 630 62.3 69.8 30 5.82 225.62 22.79 248.41 43 49 RAIL SABARMATI (C STATION) P 422 78.7 75.1 30 4.50 55.49 32.62 88.11 18 50 RAIL UKAI TPS S 1110 73.5 70.3 30 13.37 320.59 2.47 323.06 24 51 RAIL WANAKBORI TPS S 1470 42.9 67.5 30 12.79 362.35 17.56 379.91 30 Madhya Pradesh 52 PITHEAD AMARKANTAK EXT TPS S 210 99.1 89.1 15 2.85 31.95 0 31.95 11 53 RAIL ANUPPUR TPP P 1200 59.9 63.5 25 11.00 24 0 24 2 CIL Supply 75% of prorata ACQ. 54 RAIL BINA TPS P 500 61.7 57.5 25 4.28 47.55 0 47.55 11 55 RAIL SANJAY GANDHI TPS S 1340 68.6 74.3 20 13.54 75.2 0 75.2 6 CIL supply to MPPGCL 90% prorata ACQ 56 RAIL SATPURA TPS S 1330 67.9 62.9 20 16.51 180.64 0 180.64 11 57 RAIL SEIONI TPP P 600 49.2 46.1 20 5.74 21.83 0 21.83 4 CIL Supply 86% of prorata ACQ. 58 RAIL SHREE SINGAJI TPP S 1860 68.5 59.5 20 21.74 73.76 0 73.76 3 CIL supply to MPPGCL 90% prorata ACQ 59 PITHEAD VINDHYACHAL STPS C 4760 86.5 89.8 15 68.04 1850.28 0 1850.28 27 Maharashtra 60 RAIL AMARAVATI TPS P 1350 0.0 36.4 20 10.60 722.39 81.92 804.31 76 61 RAIL BHUSAWAL TPS S 1210 63.8 62.1 20 13.61 165.12 0 165.12 12 62 RAIL BUTIBORI TPP P 600 0.0 46.0 20 4.95 5.51 0 5.51 1 CIL Supply 94% of prorata ACQ. CHANDRAPUR(MAHARASHTRA 63 RAIL S 2920 71.4 61.9 20 35.23 501.21 0 501.21 14 ) STPS 64 RAIL DAHANU TPS P 500 80.4 82.7 25 5.49 190.44 25.26 215.7 43 65 RAIL DHARIWAL TPP P 600 35.9 62.5 20 4.36 95.09 12.97 108.06 25 66 RAIL GMR WARORA TPS P 600 88.3 72.5 20 7.64 24.83 2.35 27.18 4 * CIL Supply 68% of prorata ACQ.

67 RAIL KHAPARKHEDA TPS S 1340 75.3 62.2 25 21.36 88.41 0 88.41 4 CIL and SCCL Supply to MAHAGENCO 91% prorata ACQ

68 RAIL KORADI TPS S 2400 58.6 38.7 25 23.27 12.23 42.72 54.95 2 CIL and SCCL Supply to MAHAGENCO 91% prorata ACQ

69 RAIL MAUDA TPS C 2320 47.0 56.8 20 24.94 370.51 19.8 390.31 16 70 RAIL NASIK TPS S 630 27.3 43.0 25 6.59 101.05 0 101.05 15 71 RAIL PARAS TPS S 500 35.7 61.0 25 4.86 92.91 0 92.91 19 72 RAIL PARLI TPS S 1170 0.0 29.4 25 11.23 353.5 0 353.5 31 73 RAIL SOLAPUR C 660 0.0 33.7 25 5.66 192.41 7.49 199.9 35 74 RAIL TIRORA TPS P 3300 80.3 73.6 20 43.41 502.62 4.83 507.45 12 75 ROAD WARDHA WARORA TPP P 540 0.0 24.3 20 4.63 40.64 0 40.64 9

Total of Western Region 54012 20 614.90 8700.13 272.98 8973.11 15 1 Actual Stock Critical(*)/Sup Requirement PLF % PLF % Normative er Critical(**) Mode of Capacity for the day Region/State Name of Thermal Power Station Sector (Feb, (Apr,18- Stock Reqd. In '000 Tonnes' as per Trigger Reasons for critical coal stock/Remarks Transport (MW) (In '000 In Days 2019) Feb,19) (Days) level & other Tonnes') Indigenous Import Total conditions

Southern Andhra Pradesh DAMODARAM SANJEEVAIAH 76 RAIL S 1600 34.1 48.2 20 12.49 95.85 20.82 116.67 9 TPS 77 RAIL Dr. N.TATA RAO TPS S 1760 59.2 70.1 20 21.82 584.38 0 584.38 27 78 RAIL PAINAMPURAM TPP P 1320 40.1 70.9 20 9.94 64.5 25.31 89.81 9 79 RAIL RAYALASEEMA TPS S 1650 56.7 44.9 25 22.40 158.74 0 158.74 7 80 RAIL SIMHADRI C 2000 83.0 70.1 25 29.16 31.8 61.91 93.71 3 CIL supply to NTPC 98 % of prorata ACQ Supply kept in abeyance by MCL due to APERC order dated 81 RAIL VIZAG TPP P 1040 0.0 8.7 25 10.81 30.03 15.51 45.54 4 31.01.2018 Karnataka 82 RAIL BELLARY TPS S 1700 33.4 25.7 30 13.73 169.47 0 169.47 12 83 RAIL KUDGI STPP C 2400 52.7 37.2 30 21.45 96.29 11.88 108.17 5 CIL supply to NTPC 98 % of prorata ACQ 84 RAIL RAICHUR TPS S 1720 60.8 56.5 30 21.44 335.66 0 335.66 16 85 RAIL YERMARUS TPP S 1600 0.0 6.2 30 6.83 43.74 0 43.74 6 Bridge linkage Tamil Nadu 86 INTER MODAL METTUR TPS S 840 86.6 69.6 30 11.76 74.76 54.83 129.59 11 87 INTER MODAL METTUR TPS - II S 600 86.6 69.6 30 8.04 60.6 64.01 124.61 16

88 INTER MODAL NORTH CHENNAI TPS S 1830 69.8 65.6 30 22.05 59.38 18.83 78.21 4 CIL Supply to TANGEDCO 85% prorata ACQ

89 RAIL TUTICORIN (JV) TPP JV 1000 39.4 64.4 30 8.61 271.93 61.59 333.52 39 90 INTER MODAL TUTICORIN TPS S 1050 70.8 68.4 30 13.19 251.52 48.51 300.03 23 91 INTER MODAL VALLUR TPP JV 1500 67.6 56.7 30 21.14 218.99 0 218.99 10 Telangana 92 PITHEAD KAKATIYA TPS S 1100 73.8 79.8 15 10.63 197.75 0 197.75 19 93 RAIL KOTHAGUDEM TPS S 720 46.1 58.8 20 8.12 318.66 0 318.66 39 94 RAIL KOTHAGUDEM TPS (NEW) S 1000 89.2 86.4 20 15.75 440.4 0 440.4 28

95 RAIL KOTHAGUDEM TPS (STAGE-7) S 800 89.2 86.4 20 8.68 153.35 0 153.35 18 96 PITHEAD RAMAGUNDEM STPS C 2600 83.9 81.5 15 34.64 642.07 0 642.07 19 97 RAIL SINGARENI TPP S 1200 98.4 81.8 15 16.47 267.73 0 267.73 16 Total of Southern Region 31030 25 349.13 4567.60 383.20 4950.80 14 0

Eastern Bihar 98 RAIL BARH II C 1320 71.5 85.7 20 11.27 632.99 0.2 633.19 56 99 PITHEAD KAHALGAON TPS C 2340 78.0 80.3 15 36.45 529.26 0 529.26 15 100 RAIL MUZAFFARPUR TPS JV 610 69.2 55.9 20 6.44 82.35 0 82.35 13 101 RAIL NABI NAGAR TPP JV 500 94.6 59.1 20 7.79 47.54 0 47.54 6 CIL supply to NTPC 98 % of prorata ACQ Jharkhand 102 RAIL BOKARO `B` TPS C 710 57.7 56.7 20 7.14 176.5 0 176.5 25 103 RAIL CHANDRAPURA(DVC) TPS C 630 49.5 66.8 20 4.93 292.85 0 292.85 59 104 RAIL KODARMA TPP C 1000 81.2 70.4 20 10.07 99.96 0 99.96 10 105 RAIL MAITHON RB TPP JV 1050 83.4 78.4 20 12.32 375.81 6.25 382.06 31 106 ROAD TENUGHAT TPS S 420 46.1 46.6 20 4.05 184.62 0 184.62 46 Odisha 107 PITHEAD IB VALLEY TPS S 420 79.1 83.5 15 7.43 76.92 0 76.92 10

108 RAIL KAMALANGA TPS P 1050 51.1 72.7 20 11.90 388.65 27.09 415.74 35

109 PITHEAD TALCHER (OLD) TPS C 460 101.5 89.3 15 9.18 202.38 0 202.38 22 110 PITHEAD TALCHER STPS C 3000 85.5 79.4 15 55.57 107.72 10.09 117.81 2 CIL supply to NTPC 98 % of prorata ACQ Actual Stock Critical(*)/Sup Requirement PLF % PLF % Normative er Critical(**) Mode of Capacity for the day Region/State Name of Thermal Power Station Sector (Feb, (Apr,18- Stock Reqd. In '000 Tonnes' as per Trigger Reasons for critical coal stock/Remarks Transport (MW) (In '000 In Days 2019) Feb,19) (Days) level & other Tonnes') Indigenous Import Total conditions

West Bengal 111 RAIL BAKRESWAR TPS S 1050 88.4 76.7 20 9.41 148.35 0 148.35 16 112 RAIL BANDEL TPS S 330 52.2 45.3 20 4.38 29.9 0 29.9 7 113 RAIL BUDGE BUDGE TPS P 750 93.7 92.0 20 9.64 176.92 0 176.92 18 114 RAIL D.P.L. TPS S 660 39.6 43.3 25 5.47 21.83 0 21.83 4 CIL Supply to WBPDCL 98% prorata ACQ 115 RAIL DURGAPUR STEEL TPS C 1000 81.5 71.1 20 10.86 243.96 0 243.96 22 116 RAIL DURGAPUR TPS C 210 19.9 52.0 20 1.92 199.36 0 199.36 104 117 PITHEAD FARAKKA STPS C 2100 80.0 80.8 15 22.33 111.71 0 111.71 5 118 RAIL HALDIA TPP P 600 77.3 88.6 20 7.52 135.07 3.15 138.22 18 119 RAIL KOLAGHAT TPS S 1260 33.6 40.9 25 13.12 151.84 0 151.84 12 120 RAIL MEJIA TPS C 2340 76.2 61.1 20 26.00 119.71 0 119.71 5 CIL Supply to DVC 103% of prorata ACQ. 121 RAIL RAGHUNATHPUR TPP C 1200 43.6 28.4 15 11.18 86.34 0 86.34 8 122 RAIL SAGARDIGHI TPS S 1600 30.7 51.6 20 13.05 96.55 0 96.55 7 123 RAIL SANTALDIH TPS S 500 90.3 79.3 20 8.26 162.81 0 162.81 20 124 RAIL SOUTHERN REPL. TPS P 135 11.5 24.9 20 1.24 28.57 0 28.57 23 125 RAIL TITAGARH TPS P 240 0.0 0.0 20 2.06 14.02 0 14.02 7 Total of Eastern Region 27485 19 330.99 4924.49 46.78 4971.27 15 0

North Eastern Assam 126 RAIL BONGAIGAON TPP C 500 68.9 63.9 20 4.18 140.28 0 140.28 34 Total of North Eastern 500 20 4.18 140.28 0.00 140.28 34 0 Region

Region-wise/All India total 151056 22 1672.47 26112.61 945.85 27058.46 16 2

Total Stock Total Stock Capacity Daily Req ('000 T) (in Days) Pithead Plants Mode No. of Plants (MW) ('000 T)

(*) No. of plants with Critical Stock (<5 Days) 0 Pithead 17 33180 461.9 6814.7 15 (**) No. of plants with Super Critical Stock (<3 Days) 0 Non-Pithead 109 117876 1210.5 20243.8 17 Non-Pithead TOTAL 126 151056 1672.5 27058.5 16 (*) No. of plants with Critical Stock (<7 Days) 2 (**) No. of plants with Super Critical Stock (<4 Days) 0 Total 2

NOTE: (i) % Materialisation (including Deemed Delivery) as per CIL is for the period 01.04.2018 to 31.01.2019 (ii) Power Plants having less coal stock due to outstanding dues/ supply more than committed quantity/ not lifting offered coal/Bridge linkage/New Linkage are not shown as having critical /supercritical coal stock. (iii) Daily coal requirement is based on the maximum of the requirement for average actual consumption of the plant for last 7 days or requirement for installed capacity of plant at 55%PLF.

C:Central Sector; S: State Sector; P: Private Sector; JV: Joint Venture ANNEXURE 3.1

DETAILS OF PROPOSED MAINTENANCE PROGRAM OF GENERATING UNITS DURING March 2019 & April 2019

Capacity Outage Plan S. No. Unit No. Reason

(MW) From To

1 GUJARAT

2 MADHYAPRADESH

3 CHHATTISHGARH

3.1 Korba east 5 120 16-Apr-19 22-Apr-19 AOH

3.2 DSPM # 2 2 22-Mar-19 29-Mar-19 AOH 250

4 MAHARASHTRA

5 Central Sector and IPPs

5.1 CGPL 40 830 25-Mar-19 05-Apr-19 To carry out emergency nature works

5.2 22-Apr-19 16-May-19 Gandhar GT 3C 3C 144.3 Major overhauling works

5.3 02-Apr-19 01-May-19 AOH Korba 1 200

5.4 16-Mar-19 09-Apr-19 AOH Vindhyachal 3 210

5.5 01-Apr-19 15-Apr-19 AOH OSP 1 65

5.6 16-Apr-19 30-Apr-19 AOH OSP 2 65

5.7 01-Apr-19 15-Apr-19 ISP 2 125 annual maintanence

5.8 16-Apr-19 30-Apr-19 ISP 1 125 annual maintanence

5.9 SSP-RBPH 6 200 06-Apr-19 26-Apr-19 ROUTINE AOH WORK

5.1 SSP-CHPH 1 50 15-Apr-19 01-May-19 ROUTINE AOH WORK

5.11 27-Mar-19 12-Apr-19 SSP-CHPH 3 50 ROUTINE AOH WORK NPCIL has informed that proposed dates are tentative 5.12 TAPS 3 540 20-Apr-19 24-May-19 in nature and final dates will be confirmed after NPCIL 3 confirmation to WRPC Transmission Element Outage planning for the month of April 2019 Annexure 3.2 From To Type Sr. No Line / ElementBasis Reason System Agency Date Time Date Time 1 765 765KV JABALPUR 1 MAIN BAY(709) AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 01/Apr/19 02/Mar/19 2 400 400kV RAIPUR LINE-1 & 400kV Bus -1 AT NSPCL BHILAI END 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 01/Apr/19 01/Apr/19 3 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 01/Apr/19 01/Apr/19 managed on 4 400 400KV RANCHI-SIPAT I 8:00 18:00 Daily INSTALLATION OF GLASS/LONG ROD INSULATORS AT WRTS-I WRTS-I C 01/Apr/19 01/Apr/19 POWER LINE/RAILWAY/ROAD CROSSINGS IN BILASPUR 5 400 Bhachau-Mundra Ckt-3 9:00 11:00 daily For online rectification work of PLCC Channel-1 at both ends POWERGRID WR-II 01/Apr/19 01/Apr/19 6 765 765kV Jabalpur-Orai-1 9:00 17:00 Daily Variable frequency tan delta of Line Reactor bushings , at Orai POWERGRID NR-3 R 01/Apr/19 01/Apr/19 7 765 765KV orai-jabalpur ckt 1 9:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings , at Orai PGCIL PGCIL R 01/Apr/19 01/Apr/19 8 400 Bay No-401 Main Bay of 400kv Augrangabad-Boisar-I Line at 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Boisar. 01/Apr/19 01/Apr/19 9 765 BUS REACTOR_765kV_240MVAR_CHAMPA 9:00 13:00 Daily For Spare Bus Reactor Changeover WRTS-I WRTS-I R 01/Apr/19 01/Apr/19 10 400 400kV Dehgam -Sami # 1at Dehgam, dia to be kept open at both 9:00 18:00 Daily Amp work of Terminal Equipments ADANI WR-II R ends. 01/Apr/19 01/Apr/19 11 400 413 Kakrapar 1 Main Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 01/Apr/19 01/Apr/19 12 400 400KV VINDHYACHAL - JABALPUR # 1 Line, A/R to be kept in 9:00 18:00 Daily AMP of 400 kV Vindhyachal # 1 LR and line terminal POWERGRID WR-II R non-auto of circuit-2 and dia to be kept open. 01/Apr/19 01/Apr/19 equipments. A/R of 400 kV Vindhyachal - Jabalpur # 2 is to be 13 765 765kV ICT-1 & BR Tie bay (702) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 01/Apr/19 01/Apr/19 14 765 765 kV Bus-1 at Bilaspur PS 9:00 18:00 Daily For Bus bar stability test in Rajnandgaon#1 line WRTS-I WRTS-I C 01/Apr/19 01/Apr/19 15 220 400/220KV ICT-I 220KV SIDE _MAIN_BAY_201 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 01/Apr/19 01/Apr/19 16 765 765 KV Aurangabad-3 Main Bay 719 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 01/Apr/19 01/Apr/19 17 765 ICT1_765/400kv_AURANGABAD 9:00 18:00 Daily For Attending oil leakage works in Y ph MOG WRTS-I WRTS-I R 01/Apr/19 01/Apr/19 18 220 220KV Bus-I at Raipur ss 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 01/Apr/19 01/Apr/19 19 400 ICT1_400/220kv_MAPUSA 10:00 14:00 Daily For installation of rain canopies for Bucholz and PRD WRTS-I WRTS-I R 01/Apr/19 01/Apr/19 20 765 765KV Bina#1 switchable Line Reactor at pooling 10:00 18:00 Daily For replacement of multiple base by single insulated base from POWERGRID WR-II R station,Jabalpur 01/Apr/19 01/Apr/19 CGL make LA 21 400 400 KV BUS-I at Tamnar PS 10:00 18:00 Daily For AMP works WRTS-I WRTS-I R 01/Apr/19 01/Apr/19 22 400 Bhachau-Mundra Ckt-3 11:00 13:00 daily For online rectification work of PLCC Channel-2 at both ends POWERGRID WR-II 01/Apr/19 01/Apr/19 23 400 Bhachau-Mundra Ckt-3 14:00 16:00 daily For end to end testing of PLCC POWERGRID WR-II 01/Apr/19 01/Apr/19 24 400 400 kV Varsana-Hadala Line 8:00 19:00 Daily Line and bay equipment maintenance work GETCO GETCO 01/Apr/19 01/Apr/19 25 400 KHADKA- DEEPNAGAR CKT 1 & 2 (AR IN NON-AUTO MODE) 08:00 15:00 Daily For PID Testing by PID Unit,Khadka MSETCL MSETCL A/R required in 01/Apr/19 02/Apr/19 Non-Auto Mode 26 400 DHULE- - BABLESHWAR - I & II (AR IN NON-AUTO MODE) 09:00 17:00 Daily PID testing of insulators MSETCL MSETCL 400kV BBLR ckt- 01/Apr/19 02/Apr/19 1 & 2 A/R switch 27 400 Circuit -2 Lanco - PGCIL Bharari (Line length - 75.3 Km) 6:00 18:00 Daily 1. Annual Maintenance of Transmission Line. LANCO LANCO R 01/Apr/19 03/Apr/19 2. Maintenance of Bay-6 at Lanco end. 28 400 400KV ISP -II at 400KV S/S Indore 9:00 18:00 Continue For replacement of bus-I P.G isolator of ISP-II.400 KV ISP-II MPPTCL MPPTCL R 01/Apr/19 03/Apr/19 will be on TBC. 29 400 400KV Main Bus -I at 400KV S/S Indore 9:00 18:00 Continue For replacement of bus-I P.G isolator of following feeders.400 MPPTCL MPPTCL R 01/Apr/19 05/Apr/19 KV Main Bus-I will be OFF. 30 400 400/220/33 KV 315MVA ICT - 3 @ KARAD 10:00 17:00 Continuous OLTC overhauling work, Attending oil leakage by new MSETCL MSETCL Load manage on 01/Apr/19 05/Apr/19 technique,ICT Painting work & Annual Maint. Work, 400 KV other Two ICT'S 31 400 400/220 KV Jhanor ICT-1(167 MVA) Bay-401 8:00 18:00 CONTINOUS ANNUAL BAY MAINTENANCE :Transformer Testing(3 Nos) NTPC NTPC R 01/Apr/19 06/Apr/19 including bushings, Cooling system cheching/overhauling of 32 400 400 KV BUS BAR PROTECTION @ CHANDRAPUR 09:00 18:00 Continuous For Final online Termination at Interfacing points and MSETCL MSETCL During this 01/Apr/19 06/Apr/19 commissioning the new ZIV make numerical busbar protection outage period, 33 400 Bus Reactor #3 Main Bay (401) at Itarsi 9:00 18:00 Continuous For Over Hauling of Circuit Breaker POWERGRID WR-II R 01/Apr/19 06/Apr/19 34 400 PADGHE - KALWA 1 09:00 18:00 Daily PID Testing work of 400 KV Kalwa-Padgha Ckt-1 line Insulator MSETCL MSETCL Line will be in 01/Apr/19 09/Apr/19 strings at various locations. Auto-Reclose function to be out of service 35 400 400KV MAIN BUS-2 at 400KV S/s Bina 8:30 17:00 Continue S/D is required for 400 KV PG Isolators replacement works of MPPTCL MPPTCL R 01/Apr/19 10/Apr/19 X-mer - I, II & III and Bhopal - I & II. No any interruption 36 400 BABHALESHWAR - PADGHE 1 09:00 17:00 Daily PID testnig work MSETCL MSETCL AR required in 01/Apr/19 15/Apr/19 non -auto mode 37 400 500 MVA 400/220 kV ICT # 2 HAZIRA 9:00 18:00 Continuous ICT Internal inspection & over-hauling for rise of disloved EPTCL EPTCL R 01/Apr/19 15/Apr/19 gases. 38 765 BAY 714 ( TIE BAY OF 765KV INDORE VADODARA LINE ) AT 9:00 18:00 Continuous FOR CONSTRUCTION WORKS OF NEW 765KV INDORE- POWERGRID WR-II C INDORE PS 01/Apr/19 15/Apr/19 KHANDWA LINE 39 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1 09:00 18:00 Daily For PID Work,Shifting of auto reclose switch to non auto mode. MSETCL MSETCL NIL 01/Apr/19 16/Apr/19 40 400 400kV Mundra - Sami Ckt-1 8:00 18:00 Daily Earth wire replacement work on transmission tower and Auto ATIL ATIL Constrution 01/Apr/19 20/Apr/19 Recloser will be in disabled mode 41 400 400kV Mundra - Sami Ckt-2 8:00 18:00 Daily Earth wire replacement work on transmission tower and Auto ATIL ATIL Constrution 01/Apr/19 20/Apr/19 Recloser will be in disabled mode 42 220 PUSAD - WARDHA (PG) 07:00 17:00 Daily PID Work MSETCL MSETCL NIL 01/Apr/19 30/Apr/19 43 400 A/R in non-auto mode of Mundra-Jetpur-1 7:00 18:00 Daily For live line OPGW Works POWERGRID WR-II C 01/Apr/19 30/Apr/19 44 400 Bhinmal- Zerda 7:00 19:00 DAILY Relay setting may be changed from Auto reclose to Non-auto PGCIL PGCIL Constrution 01/Apr/19 30/Apr/19 reclose mode for OPGW LIVE LINE stringing works 45 400 A/R IN NON AUTO MODE OF 400kV KORBA-MAHAN 8:00 18:00 Daily A/R in Non Auto mode required for PID work. Line will remian WRTS-I WRTS-I 01/Apr/19 30/Apr/19 in service. 46 400 NEW KOYNA-KARAD -CKT 1 & 2 (AR IN NON-AUTO MODE) 09:00 17:00 Daily Permission for Auto Reclose to be kept OFF for PID testing MSETCL MSETCL Permission for 01/Apr/19 30/Apr/19 work AR required in 47 220 A/R IN NON AUTO MODE OF 220 KV BUDHIPADAR KORBA 9:00 17:00 Daily A/R in Non auto mode for PID works bt Raigarh-TLM WRTS-I WRTS-I R LINE III 01/Apr/19 30/Apr/19 48 400 PARLI-SOLAPUR (LAMBOTI) 10:00 18:00 Daily PID work MSETCL MSETCL Line will be in 01/Apr/19 30/Apr/19 service 49 Orai (765KV)-JABALPUR1 09:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings NRPC POWERGRID 01/Apr/19 01/Apr/19 50 712 765 Kv BR Main Bay 712 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 02/Apr/19 02/Apr/19 51 400 400KV Kansari-Kankroli 9:00 10:00 Daily For Pre summer maintenance Works POWERGRID WR-II R 02/Apr/19 04/Apr/19 52 400 VADAVI-CHORANIYA-2 LINE at Vadavi by Pirana S/s 9:00 18:00 Continuous INTERRUPTER REPLACEMENT WORK at Vadavi POWERGRID WR-II R 02/Apr/19 05/Apr/18 53 400 400KV ICT 1 & FUTURE TIE BAY(420) AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 02/Apr/19 02/Apr/19 54 400 400kV RAIPUR LINE-2 & 400kV Bus -2 AT NSPCL BHILAI END 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 02/Apr/19 02/Apr/19 55 400 400 kV SSNL - Dhule - 1 (Auto reclose of Dhule - 2 will remain 7:00 18:00 Daily Maintenance Work NCA GETCO out) 02/Apr/19 02/Apr/19 56 400 MAIN BAY (416) OF CHANDRAPUR ckt-2 @ WARORA 08:00 16:00 Daily Routine maintainance and DCRM/CRM/CB Timings Testing MSETCL MSETCL Line will be 02/Apr/19 02/Apr/19 works and isolater maintainance work . charged through 57 220 220 KV OLD GCR PARLI - PARLY (PG) 08:00 16:00 Daily LINE maintenance MSETCL MSETCL - 02/Apr/19 02/Apr/19 58 400 400 kV Varsana - Hadala Line (Auto reclose of APL - Hadala will 8:00 18:00 Daily Bay and line maintenance work GETCO GETCO remain out) 02/Apr/19 02/Apr/19 59 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 02/Apr/19 02/Apr/19 managed on 60 220 BHUGAON - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Purti - 02/Apr/19 02/Apr/19 Bhugaon Ckt 61 400 VSTPS BUS-1 8:00 18:00 Continuous Hot Spot rectification of Bus-1 NTPC NTPC R 02/Apr/19 02/Apr/19 62 400 400KV RANCHI-SIPAT II 8:00 18:00 Daily INSTALLATION OF GLASS/LONG ROD INSULATORS AT WRTS-I WRTS-I C 02/Apr/19 02/Apr/19 POWER LINE/RAILWAY/ROAD CROSSINGS IN BILASPUR 63 400 BUS REACTOR_400kV_63MVAR_SOLAPUR 8:00 19:00 Daily For Bus Reactor controlling through STATCOM. WRTS-I WRTS-I C 02/Apr/19 02/Apr/19 64 400 Bhachau-Mundra Ckt-4 9:00 11:00 daily For online rectification work of PLCC Channel-1 at both ends POWERGRID WR-II 02/Apr/19 02/Apr/19 65 765 701-Bay - Main Bay of 765/400 Kv ICT-1 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 02/Apr/19 02/Apr/19 66 765 765kV Jabalpur-Orai-2 9:00 17:00 Daily Variable frequency tan delta of Line Reactor bushings , at Orai POWERGRID NR-3 R 02/Apr/19 02/Apr/19 67 400 400KV Bus-1 at Pune (Talegaon) 9:00 17:00 Daily Replacment of Clamps & connectors WRTS-I WRTS-I R 02/Apr/19 02/Apr/19 68 765 765KV orai-jabalpur ckt 2 9:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings , at Orai PGCIL PGCIL R 02/Apr/19 02/Apr/19 69 400 Bay No-402 Tie Bay of 400kv Aurangabad-Boisar Line-I & 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Furture Bay at Boisar 02/Apr/19 02/Apr/19 70 400 400 kV BUS-A Veloda 9:00 18:00 Daily Bus/ BC Bay maintenance work GETCO GETCO 02/Apr/19 02/Apr/19 71 765 765KV Vadodara-Indore Line by Vadodara, dia to be kept open at 9:00 18:00 Daily For Insulator cleaning work POWERGRID WR-II R both ends 02/Apr/19 02/Apr/19 72 765 713 Sasan 2 Main Bay at Vindhyachal Pooling 9:00 18:00 Daily For AMP work POWERGRID WR-II R 02/Apr/19 02/Apr/19 73 765 765kV ICT-1 Main bay (701) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 02/Apr/19 02/Apr/19 74 400 ICT1_400/220kv_PARLI 9:00 18:00 Daily For CSD commissioning WRTS-I WRTS-I C 02/Apr/19 02/Apr/19 75 400 400 KV BUS-II at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 02/Apr/19 02/Apr/19 76 220 400/220KV ICT-II 220KV SIDE _MAIN_BAY_202 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 02/Apr/19 02/Apr/19 77 765 765 KV Durg-3 Main Bay 718 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 02/Apr/19 02/Apr/19 78 400 400KV Bhadrawati Main bay at Bhilai ss 9:30 17:30 Daily AMP at Bhillai SS WRTS-I WRTS-I R 02/Apr/19 02/Apr/19 79 400 ICT2_400/220kv_MAPUSA 10:00 14:00 Daily For installation of rain canopies for Bucholz and PRD WRTS-I WRTS-I R 02/Apr/19 02/Apr/19 80 765 765KV Bina#2 switchable Line Reactor at pooling 10:00 18:00 Daily For replacement of multiple base by single insulated base from POWERGRID WR-II R station,Jabalpur 02/Apr/19 02/Apr/19 CGL make LA 81 400 315 MVA ICT-1 at Khandwa SS, dia to be kept open. 10:00 18:00 Daily For AMP work POWERGRID WR-II R 02/Apr/19 02/Apr/19 82 400 Bhachau-Mundra Ckt-4 11:00 13:00 daily For online rectification work of PLCC Channel-2 at both ends POWERGRID WR-II 02/Apr/19 02/Apr/19 83 400 Bhachau-Mundra Ckt-4 14:00 16:00 daily For end to end testing of PLCC POWERGRID WR-II 02/Apr/19 02/Apr/19 84 400 63 MVAR Bus Reactor # 1 for main bay CT Replacement (dia- 408 9:00 18:00 Daily Replacement of Bay CT (Reactor outage is required for CT POWERGRID WR-II R & 409 to be kept open) at Jabalpur 02/Apr/19 02/Apr/19 Replacement work. Hence Bay No. 408 & 409 are to be 85 765 714,NHPTL & Gwalior-2 Tie bay at Bina 9:15 17:30 Daily For AMP work. POWERGRID WR-II R 02/Apr/19 02/Apr/19 86 400 VSTPS BUS SECTION-1 (Stage-I, Bay No. 13) 8:00 18:00 Continuous Annual Bay Maintenance NTPC NTPC R 02/Apr/19 03/Apr/19 87 400 400 KV Mouda Bay 416 & 417 (Tie)- spare dia 8:00 18:00 Continuous Annual Maintenance NTPC NTPC R 02/Apr/19 04/Apr/19 88 765 765/400kV ,1000MVA ICT-1 along with respective Bays(800-14 8:00 20:00 Continuous Equipment and Bay Yearly Maintenance SASAN RELIANCE R ,15 & 400-1 ,2 ) at sasan 02/Apr/19 04/Apr/19 89 220 220KV ICT-I at 220KV S/S Sukha 9:00 17:00 Continue For bay equipment maintenance and testing work MPPTCL MPPTCL R 02/Apr/19 04/Apr/19 90 400 400KV ICT#3 at Rewa, dia to be kept open 10:00 18:00 DAILY COMMISSIONING AND FINE TUING OF CSD AND POWERGRID WR-II R 02/Apr/19 05/Apr/19 INTEGRATION OF RTCC WITH OLTC 91 400 400 KV Bay No - 8, Bus Coupler alongwith one bus dead Bus-I) 8:30 17:30 Continuous Installation, Commissioning & Testing of control and relay CSPGCL CSPGCL Constrution at 400 KV S/s HTPS,Korba West. 02/Apr/19 08/Apr/19 panel. 92 220 BOISAR II - PGCIL ckt 1 & 2 (AR IN NON-AUTO MODE) 09:00 16:00 Daily PID TESTING OF LINE INSULATORS(ONLY A/R NON-AUTO MSETCL MSETCL Line will remain 02/Apr/19 20/Apr/19 REQUIRED) in service 93 220 220KV Mapusa-Ponda 9:00 16:00 Daily Washing/Cleaning of Line Insulators of 16 nos of Towers ( TLN GED GED 02/Apr/19 03/Apr/19 80 to 91G ) in the Amona Belt, prone to graphite pollution. 94 Orai (765KV)-JABALPUR2 09:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings NRPC POWERGRID 02/Apr/19 02/Apr/19 95 KANKROLI (400KV)-ZERDA-WR (400KV)I 08:30 18:30 DAILY For pre- summer line maintenance work. NRPC POWERGRID 02/Apr/19 04/Apr/19 96 400 Sipat-Raipur1 main Bay-9 at NTPC Sipat 8:00 18:00 Continuous PM (Sipat Raipur Line-1 will reamin charged through its Tie WRTS-1 NTPC R 03/Apr/19 04/Apr/19 bay) 97 400 400KV CGPL Mundra Bachau-1 line at CGPL end 8:00 20:00 Daily Line equpiments terminal tightness & PM PGCIL CGPL R 03/Apr/19 03/Apr/19 98 400 50MVAR Shujalpur-Bina Ckt-I Switchable Line Reactor bay 10:00 18:00 Daily Siemens make CSD fine tuning work. POWERGRID WR-II C (401LR) at Shujalpur. ( Line will be sercive though main and Tie 03/Apr/19 03/Apr/19 99 400 /220 ICT-1 WITH 220kV BAY-4 (401) & 400kV BAY-10 (1001) &9 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R (901) , 220kV TRANSFER BUS,400kV BUS-1 AT NSPCL SWITCH 03/Apr/19 03/Apr/19 100 400 TIE BAY (415) OF CHANDRAPUR-2 & ADANI - 2 @ WARORA 08:00 16:00 Daily Routine maintainance and DCRM/CRM/CB Timings Testing MSETCL MSETCL Line will be 03/Apr/19 03/Apr/19 works and isolater maintainance work . charged through 101 400 400 kV Chorania - Charal Line (Auto reclose of Chorania - 8:00 18:00 Daily Line maintenance work. GETCO GETCO Kosamba - 2 & Kosamba - Charal line will remain out) 03/Apr/19 03/Apr/19 102 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 03/Apr/19 03/Apr/19 managed on 103 220 BHUGAON - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Purti - 03/Apr/19 03/Apr/19 Bhugaon Ckt 104 220 KALMESHWAR-PANDHURNA 08:00 18:00 Daily Restringing of bottom ph conductor and Routine Maintenance MSETCL MSETCL Outage to be 03/Apr/19 03/Apr/19 & Dignostic testing work availed subject to 105 400 400/220/33kV 315MVA ICT # 2 at Dehgam, dia to be kept open. 8:00 18:00 Daily Retrofitting of T- Isolator, Repeat Cap & Tan Delta POWERGRID WR-II R 03/Apr/19 03/Apr/19 Measurement & Precommissionin testing work (Dia will be 106 400 Bhachau-Mundra Ckt#1 with Non Auto mode of Ckt-2 (Dia to be 8:00 18:00 daily Open spacer fixing and Hotspot attending work POWERGRID WR-II kept open at both end) 03/Apr/19 03/Apr/19 107 400 Bhachau-Mundra Ckt-1 9:00 11:00 daily For online rectification work of PLCC Channel-1 at both ends POWERGRID WR-II 03/Apr/19 03/Apr/19 108 765 702-Bay - Tie Bay of 765/400 kV ICT-1 & Future bay at Koradi- 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL III substation 03/Apr/19 03/Apr/19 109 220 220 KV Raigarh-PGCIL Ckt-I at 220 KV S/s Raigarh 9:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R 03/Apr/19 03/Apr/19 110 132 KANHAN-PENCH 09:00 17:00 Daily Replacement of Jumper MSETCL MSETCL Outage to be 03/Apr/19 03/Apr/19 availed subject to 111 400 400Kv PUNE(GIS)-PUNE(TALEGOAN)_3 9:00 17:00 Daily Rectification of condcutor unwind at Line dropper 'Y' phase WRTS-I WRTS-I R 03/Apr/19 03/Apr/19 112 400 Bay No-404 Main Bay of 500 MVA ICT-3 at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 03/Apr/19 03/Apr/19 113 400 416 Kakrapar 2 Main Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 03/Apr/19 03/Apr/19 114 400 400 kV Bus Reactor at Vindhyachal Pooling, dia to be kept open 9:00 18:00 Daily For AMP work POWERGRID WR-II R 03/Apr/19 03/Apr/19 115 220 220kV Bus#1 at Satna 9:00 18:00 Daily AMP work POWERGRID WR-II R 03/Apr/19 03/Apr/19 116 765 765kV ICT-4 Main bay (704) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 03/Apr/19 03/Apr/19 117 400 ICT2_400/220kv_PARLI 9:00 18:00 Daily For CSD commissioning WRTS-I WRTS-I C 03/Apr/19 03/Apr/19 118 220 220KV SEONI CKT-I_MAIN_BAY_204 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 03/Apr/19 03/Apr/19 119 220 220 KV BUS-1 at Wardha 9:00 18:00 Daily For AMP work of CVT and Oil top up in B phase CVT WRTS-I WRTS-I 03/Apr/19 03/Apr/19 120 38.5 38.5KV_STATCOM-1_BAY_601 at Solapur 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 03/Apr/19 03/Apr/19 121 715 765Kv Wardha-1 Main Bay 715 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 03/Apr/19 03/Apr/19 122 400 315 MVA ICT#1 at Damoh S/S, dia to be kept open 9:00 18:00 Daily AMP work POWERGRID WR-II R 03/Apr/19 03/Apr/19 123 400 400KV Korba-III Main bay (425) at Raipur 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 03/Apr/19 03/Apr/19 124 400 ICT3_400/220kv_MAPUSA 10:00 14:00 Daily For installation of rain canopies for Bucholz and PRD WRTS-I WRTS-I R 03/Apr/19 03/Apr/19 125 400 400kV Rajgarh-SSP#1 Line Reactor at Rajgarh 10:00 17:00 Daily DCRM testing of Circuit Breaker. POWERGRID WR-II R 03/Apr/19 03/Apr/19 126 400 DGEN Bus isolator change over/trial for following Bays: 400kv 10:00 18:00 Daily monthly routine testing of isolators operation TPL - DGEN TPL - DGEN R DGEN Navsari line-1,Navsari line-2,125 MVA Reactor Bay, 03/Apr/19 03/Apr/19 127 400 Bhachau-Mundra Ckt-1 11:00 13:00 daily For online rectification work of PLCC Channel-2 at both ends POWERGRID WR-II 03/Apr/19 03/Apr/19 128 220 SOUTH SOLAPUR (KUMBHARI)-PGCIL 1 11:00 16:00 Daily QM Work MSETCL MSETCL Load can be 03/Apr/19 03/Apr/19 managed on 129 400 Bhachau-Mundra Ckt-1 14:00 16:00 daily For end to end testing of PLCC POWERGRID WR-II 03/Apr/19 03/Apr/19 130 765 703 Bay of ICT-1 at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 03/Apr/19 04/Apr/19 131 220 220 kV Khanpur- Dehgam (PG) line no.1 8:00 18:00 Daily Maintenance Work GETCO GETCO 03/Apr/19 04/Apr/19 132 400 400kV 421 52 Main breaker of GT#40 at CGPL end 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R 03/Apr/19 04/Apr/19 133 220 Kawas Haldarwa 1 by Navsari TLM 9:00 17:00 Daily AMP of TLM/Attending Shutdown nature defects POWERGRID WR-II R 03/Apr/19 04/Apr/19 134 765 765kv Bus Reactor Main Bay-703 at Champa PS 9:00 17:30 Daily For AMP works. WRTS-I WRTS-I R 03/Apr/19 04/Apr/19 135 765 765KV KORBA& ICT-3_TIE_BAY_717 at Bilaspur PS 9:00 18:00 Conti? For AMP works WRTS-I WRTS-I R 03/Apr/19 04/Apr/19 136 265MVA, 20/420kV, 1-ph Transformer 8:00 18:00 daily SC testing NHPTL NHPTL 03/Apr/19 05/Apr/19 137 400 400 kV Choraniya - Hadala Line 8:00 18:00 Daily Bay equipment maintenance work GETCO GETCO 04/Apr/19 04/Apr/19 138 400 400KV CGPL Mundra Bachau-2 line at CGPL end 8:00 20:00 Daily Line equpiments terminal tightness & PM PGCIL CGPL R 04/Apr/19 04/Apr/19 139 38.5 38.5KV_STATCOM-2_BAY_602 at Solapur 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 04/Apr/19 04/Apr/19 140 400 50MVAR Shujalpur-Bina Ckt-II Switchable Line Reactor bay 10:00 18:00 Daily Siemens make CSD fine tuning work. POWERGRID WR-II C (406LR) at Shujalpur. ( Line will be sercive though main and Tie 04/Apr/19 04/Apr/19 141 400 400 Korba Mahan Bay at NTPC Korba end 8:00 18:00 Continuous For Shunt reactor erection work WRTS-2 NTPC C 04/Apr/19 07/Apr/19 142 400 /220 ICT-2 WITH 220kV BAY-1(1001) & 400kV BAY-8 (801) & 9(901) , 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 220kV TRANSFER BUS,400kV BUS-2 AT NSPCL SWITCH YARD 04/Apr/19 04/Apr/19 143 400 400 kV SSNL-Dhule-2 (Auto reclose of Dhule - 1 will remain out) 7:00 18:00 Daily Maintenance work NCA GETCO 04/Apr/19 04/Apr/19 144 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1 08:00 14:00 Daily DCRM Testing MSETCL MSETCL - 04/Apr/19 04/Apr/19 145 400 TIE BAY (412) OF CHANDRAPUR-1 & ADANI - 1 @ WARORA 08:00 16:00 Daily Routine maintainance and DCRM/CRM/CB Timings MSETCL MSETCL Line will be 04/Apr/19 04/Apr/19 charged through 146 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 04/Apr/19 04/Apr/19 managed on 147 220 BHUGAON - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Purti - 04/Apr/19 04/Apr/19 Bhugaon Ckt 148 220 KALMESHWAR-PANDHURNA 08:00 18:00 Daily Restringing of bottom ph conductor and Routine Maintenance MSETCL MSETCL Outage to be 04/Apr/19 04/Apr/19 & Dignostic testing work availed subject to 149 400 Bhachau-Mundra Ckt#2 with Non Auto mode of Ckt-1 (Dia to be 8:00 18:00 daily Open spacer fixing and Hotspot attending work POWERGRID WR-II kept open at both end) 04/Apr/19 04/Apr/19 150 400 Bhachau-Mundra Ckt-2 9:00 11:00 daily For online rectification work of PLCC Channel-1 at both ends POWERGRID WR-II 04/Apr/19 04/Apr/19 151 400 Bhachau-Mundra Ckt-2 9:00 11:00 daily For online rectification work of PLCC Channel-2 at both ends POWERGRID WR-II 04/Apr/19 04/Apr/19 152 765 704-Bay - Main Bay of 765/400 kV ICT-2 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 04/Apr/19 04/Apr/19 153 220 220 KV Raigarh-PGCIL Ckt-II at 220 KV S/s Raigarh 9:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R 04/Apr/19 04/Apr/19 154 400 PARLI - LONIKAND 2 CKT 2 09:00 17:00 Daily (1) Distance relay testing work. (2) Bay Maint. Work MSETCL MSETCL - 04/Apr/19 04/Apr/19 155 220 220KV Gwalior(PGCIL)-Malanpur-I 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 04/Apr/19 04/Apr/19 156 400 Bay No-405 Tie Bay of 400kv Aurangabad-Boisar Line-I & 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Furture Bay at Boisar 04/Apr/19 04/Apr/19 157 400 400KV Damoh-Katni 9:00 18:00 Daily For line maintenance work MPPTCL MPPTCL R 04/Apr/19 04/Apr/19 158 765 765 kV Vindhyachal-Satna 2 Line swichable Reactor at V'chal 9:00 18:00 Daily For AMP work POWERGRID WR-II R 04/Apr/19 04/Apr/19 159 220 220kV Bus#2 at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 04/Apr/19 04/Apr/19 160 765 765kVBR Main bay (703) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 04/Apr/19 04/Apr/19 161 400 765/400kV ICT-1 400KV side-Main Bay-401 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 04/Apr/19 04/Apr/19 162 765 765kV Bus-2 & Bus-4 Bus Section 711 Bay at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 04/Apr/19 04/Apr/19 163 220 220KV Bus-I at Mapusa 9:00 18:00 Daily Providing mechanical interlock and alignment works of 21389A WRTS-I WRTS-I R 04/Apr/19 04/Apr/19 isolator 164 220 220KV SEONI CKT-II_MAIN_BAY_205 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 04/Apr/19 04/Apr/19 165 765 765 KV Durg-3 Tie Bay 717 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 04/Apr/19 04/Apr/19 166 400 400kV ICT-3 Main bay_404 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 04/Apr/19 04/Apr/19 167 400 315 MVA ICT#2 at Damoh S/S, dia to be kept open 9:00 18:00 Daily AMP work POWERGRID WR-II R 04/Apr/19 04/Apr/19 168 400 400kV Bus coupler-II Bay(402) at Raipur 9:30 17:00 Daily For AMP works. WRTS-I WRTS-I R 04/Apr/19 04/Apr/19 169 400 400 Rewa -Jabalpur # 2 Line at Jabalpur 11:00 13:00 Daily Replacement of Bay CT, Line outage is required for CT POWERGRID WR-II R 04/Apr/19 04/Apr/19 dismentling and new CT Erection. After erection line will be 170 400 Bhachau-Mundra Ckt-2 11:00 13:00 daily For end to end testing of PLCC POWERGRID WR-II 04/Apr/19 04/Apr/19 171 132 DHARANI - NEPANAGAR 11:00 17:00 Daily For Jumper tightening work at loc no. 104 and 105 and line MSETCL MSETCL This is the 04/Apr/19 04/Apr/19 signature analysis interstate line 172 400 Rewa - Jabalpur # II 9:00 18:00 Daily Replacement of Bay CT POWERGRID WR-II R (407 Main Bay) at Jabalpur 04/Apr/19 04/Apr/19 173 315 MVA ICT -I at 400 KV S/s Raita. 8:00 17:00 Continuous Annual Maintenance Programme. CSPTCL CSPTCL R 04/Apr/19 05/Apr/19 174 220 220 KV Korba-Budhipadar Feeder No-3 at 220 KV S/s KTPS, 8:00 17:30 Continuous Annual Maintenance Programme. CSPGCL CSPGCL R Korba East. 04/Apr/19 05/Apr/19 175 400 400KV Transformer-IV at 400KV S/S Indore 9:00 18:00 Continue For replacement of bus-I P.G isolator of ICT-IV.ICT-IV will be MPPTCL MPPTCL R 04/Apr/19 05/Apr/19 on TBC. 176 220 220KV Mapusa-Amona 9:00 16:00 Daily Washing/Cleaning of Line Insulators of 11 nos of Towers ( TLN GED GED 04/Apr/19 04/Apr/19 80 to 90 ) in the Amona Belt, prone to graphite pollution. 177 Orai (765KV)-ALIGARH-PG (765KV)I 09:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings NRPC POWERGRID 04/Apr/19 04/Apr/19 178 400 400 kV Soja - Kansari 8:00 18:00 Daily Line maintenance work GETCO GETCO 05/Apr/19 05/Apr/19 179 400 400 kV Soja - Kansari 8:00 18:00 Daily Line maintenance work GETCO GETCO 05/Apr/19 05/Apr/19 180 765 Bus-2 and Bus-4 Bus Sectionalizer Bay-17 at NTPC Sipat 8:00 18:00 Continuous PM (Both Bus i.e. Bus-2 and Bus-4 will remain charged.) NTPC NTPC R 05/Apr/19 07/Apr/19 181 400 400 kV Mansar-Choraniya Line 8:00 18:00 Daily Bay equipment conditioning monitoring work PGCIL GETCO 05/Apr/19 05/Apr/19 182 765 765kV DURG PS- CHAMPA_1 8:00 18:00 Daily For AMP work & ckt-2 AR in non auto mode required. WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 183 220 220kV BUS -1 AT NSPCL SWITCH YARD 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 05/Apr/19 05/Apr/19 184 400 MAIN BUS - 2 @ WALUJ 08:00 16:00 Daily Quarterly Maintenance MSETCL MSETCL 400kV Bhusawal 05/Apr/19 05/Apr/19 Bay @ Waluj End 185 400 400 KV Khedamara-Raita-I Line at 400 KV S/s Khedamara as 8:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R well as at 400 KV S/s Raita end. 05/Apr/19 05/Apr/19 186 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 05/Apr/19 05/Apr/19 managed on 187 220 BHUGAON - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Purti - 05/Apr/19 05/Apr/19 Bhugaon Ckt 188 400 Mundra-Jetpur Ckt#1 with Non Auto mode of Ckt-2 (Dia to be 8:00 18:00 daily Testing & Commissioning of NIFPS Scheme and to attending POWERGRID WR-II kept open at both end) 05/Apr/19 05/Apr/19 hot spot & rectifying open line spacer dampers 189 400 Mundra-Jetpur Ckt#1 with Non Auto mode of Ckt-2 (Dia to be 8:00 18:00 daily For fixing of Bird Flight Diverter in the Earth Wire. POWERGRID WR-II kept open at both end) 05/Apr/19 05/Apr/19 190 400 Itarsi-Indore #2 Line by Itarsi TLM, dia to be kept open at both 8:00 18:00 Daily Repairing of earth-wire mid span joint POWERGRID WR-II R ends 05/Apr/19 05/Apr/19 191 400 400KV CGPL Mundra Jetpur-1 line at CGPL end 8:00 20:00 Daily Line equpiments terminal tightness & PM PGCIL CGPL R 05/Apr/19 05/Apr/19 192 765 706-Bay - Main Bay of 765 kV Bus Reactor at Koradi-III 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL substation 05/Apr/19 05/Apr/19 193 220 NALASOPARA - BOISAR PG 09:00 17:00 Daily PRE MANSOON MAINTENANCE WORK MSETCL MSETCL - 05/Apr/19 05/Apr/19 194 220 220KV Gwalior(PGCIL)-Malanpur-II 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 05/Apr/19 05/Apr/19 195 400 400KV Bus-2 at Pune (Talegaon) 9:00 17:00 Daily Replacment of Clamps & connectors WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 196 400 400kV LARA(NTPC)-CHAMPA II and ckt-1 AR off 9:00 17:00 Daily REPLACEMENT OF PILOT INSULATOR STRING AT WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 TRANSPOSITION TOWER (LOC.No:108) 197 400 Bay No-406 Main Bay of 400kv Augrangabad-Boisar-II Line at 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Boisar 05/Apr/19 05/Apr/19 198 400 125MVAr Bus-Reactor#2 at Damoh S/S, dia to be kept open 9:00 18:00 Daily AMP work POWERGRID WR-II R 05/Apr/19 05/Apr/19 199 400 407 Boisar Main bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 05/Apr/19 05/Apr/19 200 765 765kV ICT-2 & Solapur-1 Tie bay (705) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 05/Apr/19 05/Apr/19 201 400 400KV Parli-2 & ICT-1 Tie Bay-402 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 05/Apr/19 05/Apr/19 202 400 400kV Pune-II Main Bay (406) at Parli 9:00 18:00 Daily For Bay AMP works WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 203 765 765kV ICT-4 Main Bay (714) at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 204 220 220KV Bus-I at Mapusa 9:00 18:00 Daily Providing mechanical interlock and alignment works of 21389A WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 isolator 205 765 765 kV Sipat-3 Tie bay 702 at Bilaspur PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 206 220 220KV BUS COUPLER_MAIN_BAY_206 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 207 765 765KV BUS REACTOR 2 MAIN BAY(710) AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 05/Apr/19 05/Apr/19 208 765 765 KV Durg-4 Main Bay 715 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 05/Apr/19 05/Apr/19 209 400 400kV ICT-3 & Future Tie Bay_405 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 210 716 765 Kv Champa-1 Main Bay 716 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 211 400 80MVAR Bus Reactor & ICT-1Tie bay (411) at Raipur SS 9:30 17:00 Daily For AMP works. WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 212 400 400kV Rajgarh-Khargone Line Reactor at Rajgarh 10:00 17:00 Daily DCRM testing of Circuit Breaker. POWERGRID WR-II R 05/Apr/19 05/Apr/19 213 765 765/400kV 1500 MVA ICT-1 @ EKTUNI 10:00 18:00 Daily Diagnostic Testing & Routine Maintainence MSETCL MSETCL 765/400kV ICT- 05/Apr/19 05/Apr/19 II will be in 214 400 400KV Shujalpur-Bina Ckt-II Main Bay (406) at Shujalpur. ( Line 10:00 18:00 Daily Vizimax make CSD relay removal work. POWERGRID WR-II C will be sercive though Tie bay) 05/Apr/19 05/Apr/19 215 400 400kV Kolhapur MSETCL-II Main bay (410) at Kolhapur-GIS 10:00 18:00 Daily For AMP works WRTS-I WRTS-I R 05/Apr/19 05/Apr/19 216 220 Kawas Haldarwa 2 by Navsari TLM 9:00 17:00 Daily Attending Shutdown Nature defects POWERGRID WR-II R 05/Apr/19 06/Apr/19 217 400 400 KV LBB PROTECTION @ CHANDRAPUR 09:00 18:00 Continuous For interfacing trip output of old LBB protection relay in to new MSETCL MSETCL During outage, 05/Apr/19 06/Apr/19 ZIV busbar protection. the LBB 218 220 Vapi-Khadoli & Vapi-Sayali at Vapi 8:00 18:00 Continuous LILO line of Vaghchipa contruction work POWERGRID WR-II C 05/Apr/19 12/Apr/19 219 765 765kV S/C Dhule -Aurangabad Line 8:00 19:00 Continuous Location 498-499, Tower modification work for new flyover BDTCL BDTCL C 05/Apr/19 30/Apr/19 construction on NH 211 220 AGRA-PG (765KV)-GWALIOR-WR (765KV)I 07:00 18:30 DAILY Replacement of suspension and tension string (Porcelain) with NRPC POWERGRID 05/Apr/19 05/Apr/19 Polymer insulator (String) in main and Tie bay along with 221 765 765kV Bus#1at Satna 9:00 14:00 Daily AMP work POWERGRID WR-II R 06/Apr/19 06/Apr/19 222 400 400 kV Chorania - Charal Line (Auto reclose of Chorania - 8:00 18:00 Daily Line maintenance work GETCO GETCO Kosamba - 2 & Kosamba - Charal line will remain out) 06/Apr/19 06/Apr/19 223 400 Itarsi-Indore #1 Line by Itarsi TLM, dia to be kept open at both 8:00 18:00 Daily Repairing of earth-wire mid span joint POWERGRID WR-II R ends. 06/Apr/19 06/Apr/19 224 765 765KV Bina#3 Line alongwith switchable Line Reactor at pooling 10:00 18:00 Daily For replacement of multiple base by single insulated base from POWERGRID WR-II R station,Jabalpur, dia to be kept open. 06/Apr/19 06/Apr/19 CGL make LA 225 765 765 Bus -II at Dharamjaygarh 9:00 18:00 Continous For Equipment erection work under 765KV Bus for Bus- WRTS-I WRTS-I C 06/Apr/19 07/Apr/19 Sectionalizing work by M/s Techno at Dharamjaigarh PS. 226 400 411,Satna-4 & Shujalpur-2 Tie bay at Bina 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 06/Apr/19 08/Apr/19 227 400 400 kV Chorania - Charal Line (Auto reclose of Chorania - 8:00 18:00 Daily Line maintenance work GETCO GETCO Kosamba - 2 & Kosamba - Charal line will remain out) 06/Apr/19 06/Apr/19 228 400 Itarsi-Indore #1 Line by Itarsi TLM, dia to be kept open at both 8:00 18:00 Daily Repairing of earth-wire mid span joint POWERGRID WR-II R ends 06/Apr/19 06/Apr/19 229 400 400KV Shujalpur-Bina Ckt-I Main Bay (401) at Shujalpur. ( Line 10:00 18:00 Daily Vizimax make CSD relay removal work. POWERGRID WR-II C will be sercive though Tie bay) 06/Apr/19 06/Apr/19 230 220 BHUGAON - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Purti - 06/Apr/19 06/Apr/19 Bhugaon Ckt 231 765 765kV DURG PS- CHAMPA_2 8:00 18:00 Daily For AMP work & ckt-1 AR in non auto mode required. WRTS-I WRTS-I R 06/Apr/19 06/Apr/19 232 400 400KV CGPL Mundra Jetpur-2 line at CGPL end 8:00 20:00 Daily Line equpiments terminal tightness & PM PGCIL CGPL R 06/Apr/19 06/Apr/19 233 400 Itarsi-Jabalpur #2 Line at Itarsi 9:00 9:15 Daily To Take Line Reactor Out of Service for reactor Over hauling POWERGRID WR-II R 06/Apr/19 06/Apr/19 Works. 234 220 220 KV Raigarh-PGCIL Ckt-III at 220 KV S/s Raigarh 9:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R 06/Apr/19 06/Apr/19 235 400 Bay No-407 Main Bay of 400kv Paghe-boisar Line at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 06/Apr/19 06/Apr/19 236 400 400kV BALCO-Dharamjaygarh Ckt-2 9:00 18:00 Daily For AMP works. BALCO WRTS-I R R 06/Apr/19 06/Apr/19 237 765 765kV Solapur-1 Main bay (706) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 06/Apr/19 06/Apr/19 238 400 400KV Parli-2 Main Bay-403 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 06/Apr/19 06/Apr/19 239 765 765kV Bus-1 & Bus-3 Bus Section Bay (710) at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 06/Apr/19 06/Apr/19 240 220 220KV Bus-II at Mapusa 9:00 18:00 Daily Alignment works of 21289B and 21389B isolators WRTS-I WRTS-I R 06/Apr/19 06/Apr/19 241 220 220KV TBC_MAIN_BAY_207 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 06/Apr/19 06/Apr/19 242 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 06/Apr/19 11/Apr/19 managed on 243 400 Line Reactor of Mundra-Jetpur Ckt#2 at GETCO Jetpur 9:00 18:00 Continuous For installation of NIFPS System at Jetpur end POWERGRID WR-II 06/Apr/19 12/Apr/19 244 400 Itarsi-Jabalpur #2 Line Reactor at Itarsi 9:00 18:00 Continuous For Over Hauling of Reactor POWERGRID WR-II R 06/Apr/19 18/Apr/19 245 AGRA-PG (765KV)-GWALIOR-WR (765KV)II 07:00 18:30 DAILY Replacement of suspension and tension string (Porcelain) with NRPC POWERGRID 06/Apr/19 06/Apr/19 Polymer insulator (String) in main and Tie bay along with 246 765 765kV Bus#2 at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 07/Apr/19 07/Apr/19 247 400 Itarsi-Indore #2 Line by Itarsi TLM, dia to be kept open at both 8:00 18:00 Daily Repairing of earth-wire mid span joint POWERGRID WR-II R ends 07/Apr/19 07/Apr/19 248 765 765KV Bhopal switchable Line Reactor at pooling 10:00 18:00 Daily For replacement of multiple base by single insulated base from POWERGRID WR-II R station,Jabalpur 07/Apr/19 07/Apr/19 CGL make LA 249 765 765kV DURG PS -WARDHA_1 9:00 18:00 Daily For commissioning of newly Erected SPARE Reactor at Wardha WRTS-I WRTS-I C 07/Apr/19 07/Apr/19 end & during opportunity shutdown Line AMP work ckt-2 AR 250 400 KALWA - TALEGAON (PGCIL) 08:00 18:00 Daily Routine Maintenance MSETCL MSETCL - 07/Apr/19 07/Apr/19 251 400 400KV CGPL Mundra Bachau-3 line at CGPL end 8:00 20:00 Daily Line equpiments terminal tightness & PM PGCIL CGPL R 07/Apr/19 07/Apr/19 252 765 701,Seoni Main bay at Bina 9:15 17:30 Continuous Replacement of Main CB MB. POWERGRID WR-II R 07/Apr/19 12/Apr/19 253 220 220KV Bus-1 at Pune (Talegaon) 9:00 17:00 Daily Replacment of Clamps & connectors WRTS-I WRTS-I R 07/Apr/19 07/Apr/19 254 220 220KV Mapusa-Ponda 9:00 16:00 Daily Washing/Cleaning of Line Insulators of 10 nos of Towers ( TLN GED GED 07/Apr/19 07/Apr/19 90 to 91G ) in the Amona Belt, prone to graphite pollution. 255 765 765kV Satna-Orai 9:00 17:00 Daily Variable frequency tan delta of Line Reactor bushings , at Orai POWERGRID NR-3 R 08/Apr/19 08/Apr/19 256 765 765KV Orai-satna 9:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings , at Orai PGCIL PGCIL R 08/Apr/19 08/Apr/19 257 400 400 KV RAIGARH_II & FUTER TIE BAY (443)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 08/Apr/19 08/Apr/19 258 220 220kV BUS -2 AT NSPCL SWITCH YARD 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 08/Apr/19 08/Apr/19 259 400 400 kV APL - Hadala Line (Auto reclose of Varsana - Hadala will 8:00 18:00 Daily Spacer providing work GETCO GETCO remain out) 08/Apr/19 08/Apr/19 260 400 CHANDRAPUR 2-KUMBHARGAON(NANDED) CKT - 2 08:00 18:00 Daily Replacement of Broken Spacer cum Vibration Damper MSETCL MSETCL nil 08/Apr/19 08/Apr/19 261 400 400KV CGPL Mundra Bachau-4 line at CGPL end 8:00 20:00 Daily Line equpiments terminal tightness & PM PGCIL CGPL R 08/Apr/19 08/Apr/19 262 400 400kV SATNA- Bina#1 at Satna SS 9:00 10:00 Daily To take L/R out of service at Satna for Attending Oil Lekage & POWERGRID WR-II R 08/Apr/19 08/Apr/19 Gasket Replacement Work 263 765 708-Bay - Tie Bay of 765 kV Tiroda-Line 2 and Akola Line 1 at 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL Koradi-III substation 08/Apr/19 08/Apr/19 264 220 Haldarwa - KAPP line 1 9:00 17:00 Daily Bay maintenance wo at Haldarva end PGCIL GETCO 08/Apr/19 08/Apr/19 265 400 400Kv PUNE(GIS)-PUNE(TALEGOAN)_4 9:00 17:00 Daily Replacment of Clamps & connectors at Pune (Talegaon) WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 266 765 765kV TAMNAR PS-KOTRA PS I 9:00 17:00 Daily For Line AMP works. Ckt-2 A/R in Non auto mode required. WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 267 400 Bay No-408 Tie Bay of 400kv Boisar-Padghe Line & ICT-I at 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Boisar 08/Apr/19 08/Apr/19 268 400 63 Mvar Bus reactor at Navsari 9:00 17:30 Daily AMP works on 63Mvar Bus Reactor at Navsari GIS POWERGRID WR-II R 08/Apr/19 08/Apr/19 269 400 410 Sugen Main Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 08/Apr/19 08/Apr/19 270 765 765kV Solapur-2 Main bay (709) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 08/Apr/19 08/Apr/19 271 400 SWITCHABLE_LR_400kV_PARLI2_ WARORA_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 08/Apr/19 08/Apr/19 272 400 400kV Solapur-I Main Bay (409) at Parli 9:00 18:00 Daily For Bay AMP works WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 273 220 220KV CHHINDWDA CKT-I_MAIN_BAY_208 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 274 765 765KV BILASPUR MAIN BAY(712) AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 08/Apr/19 08/Apr/19 275 400 400 KV Mauda-2 Main Bay 430 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 08/Apr/19 08/Apr/19 276 765 765 KV Aurangabad-2 Main Bay 713 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 08/Apr/19 08/Apr/19 277 765 ICT2_765/400kV_AURANGABAD 9:00 18:00 Daily For Attending oil leakage in Y ph Conservator WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 278 720 765Kv Champa-2 Main Bay 719 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 279 400 400kV KUDGI-KOLHAPU(GIS)-I 9:00 18:00 Daily Partial discharge traces observed in GIS Bus duct portion at SRTS-I WRTS-I R 08/Apr/19 08/Apr/19 Kolhapur end, Ckt-2 A/R in Non auto mode required during 280 400 400kV Damoh-Birsinghpur line#1 terminal equipment With Line 9:00 18:00 Daily AMP work POWERGRID WR-II R Reactor at Damoh, dia to be kept open at both ends 08/Apr/19 08/Apr/19 281 400 400KV Bhadrwati-II Main bay(419) at Raipur ss 9:30 17:00 Daily For AMP works. WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 282 400 BUS REACTOR_400kV_50MVAR_MAPUSA 10:00 14:00 Daily For installation of rain canopies for Bucholz and PRD WRTS-I WRTS-I R 08/Apr/19 08/Apr/19 283 220 MUDSHINGI - CHIKODI 10:00 17:00 Daily Pre-monsoon Maintance i.e. Cold line insulator Cleaning MSETCL MSETCL - 08/Apr/19 08/Apr/19 284 400 400KV ICT#1 at Rewa, dia to be kept open 10:00 18:00 DAILY AMP WORKS POWERGRID WR-II R 08/Apr/19 08/Apr/19 285 400 50MVAR Nagda-Shujalpur Ckt-I Switchable Line Reactor bay 10:00 18:00 Daily Vizimax make CSD relay Installation and testing work. POWERGRID WR-II C (404LR) at Nagda. ( Line will be sercive though main and Tie bay) 08/Apr/19 08/Apr/19 286 400 400 Rewa -Jabalpur # 1 Line at Jabalpur. 11:00 13:00 Daily Replacement of Bay CT. Line outage is required for CT POWERGRID WR-II R 08/Apr/19 08/Apr/19 dismentling and new CT Erection. After erection line will be 287 400 Jabalpur - Rewa # I 9:00 18:00 Daily Replacement of Bay CT POWERGRID WR-II R (406 Main Bay) at Jabalpur 08/Apr/19 08/Apr/19 288 765 706 main bay of ICT-2 at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 08/Apr/19 09/Apr/19 289 400 DHULE- - BABLESHWAR - I & II (AR IN NON-AUTO MODE) 09:00 17:00 Daily PID testing of insulators MSETCL MSETCL 400kV BBLR ckt- 08/Apr/19 09/Apr/19 1 & 2 A/R switch 290 400 400KV Transformer-III at 400KV S/S Indore 9:00 18:00 Continue For replacement of bus-II P.G isolator of ICT-III. ICT-III will be MPPTCL MPPTCL R 08/Apr/19 09/Apr/19 on TBC. 291 400 400 KV ESSAR1_MAIN_BAY_409 at Bilaspur PS 9:00 18:00 Conti? For AMP works WRTS-I WRTS-I R 08/Apr/19 09/Apr/19 292 400 DGEN 315 MVA ICT 1 - Energization - Testing of both bus 10:00 14:00 Continuous ICT 1 routine energisation testing during RSD and shutdown TPL - DGEN TPL - DGEN R isolator operation before charging. Finally ICT-1 charge with bus 08/Apr/19 09/Apr/19 for energy conservation 293 400 Sipat-Ranchi Line-1 8:00 18:00 Continuous For PM WRTS-1 NTPC R 08/Apr/19 10/Apr/19 294 400 400KV Main Bus -II at 400KV S/S Indore 9:00 18:00 Continue For replacement of bus-II P.G isolator of following feeders, MPPTCL MPPTCL R 08/Apr/19 11/Apr/19 Main bus II will be OFF 295 400 400/220 KV 315MVA ICT - 2 @ KARAD 10:00 17:00 Continuous OLTC overhauling work, Attending oil leakage by new MSETCL MSETCL Load manage on 08/Apr/19 11/Apr/19 technique, ICT Painting work & Annual Maint. work, 400 KV other Two ICTs 296 400 400KV KORADI-BHUSAWAL (Bhusawal end) 08:00 18:00 Continuous Restringing of conductor of all three phases of 400 kV Koradi- MSETCL MSETCL 400 kV Akola- 08/Apr/19 12/Apr/19 Bhusawal line due to conversion of Metergauge to Broadgauge Bhusawal, 400 297 400 400/220/33kV 315MVA ICT # 1at Dehgam, dia to be kept open 9:00 18:00 Continuous Replacement of 220kV Y-ph Bushing due to oil Leakage,Repeat POWERGRID WR-II R 08/Apr/19 13/Apr/19 Cap & Tan Delta Measurement & Precommissionin testing 298 400 Bus Reactor #2 Main Bay (426) at Itarsi 9:00 18:00 Continuous For Over Hauling of Circuit Breaker POWERGRID WR-II R 08/Apr/19 13/Apr/19 299 220 EKLAHARA-(OCR)-NAVASARI I 08:00 18:00 Continuous Replacement of insulatorwith longrod MSETCL MSETCL (if made available 08/Apr/19 16/Apr/19 by CO mumbai) 300 220 DEOLI(PGCIL)-BADNERA (AR IN NON-AUTO MODE) 08:00 17:00 Daily PID Testing MSETCL MSETCL For PID work, 08/Apr/19 27/Apr/19 Shifting of auto 301 400 L/R of 400kV Satna-Bina-1 at Satna 9:00 10:00 Continuous for Attending Oil Lekage & Gasket Replacement Work POWERGRID WR-II R 08/Apr/19 30/Apr/19 302 Orai (765KV)-JABALPUR1 10:00 18:30 DAILY For Fine tunning of CSD relay available for associated Line NRPC POWERGRID 08/Apr/19 08/Apr/19 Reactor through on Line switching, requested by WR-2 303 Orai (765KV)-SATNAS/C 09:00 17:00 DAILY Variable frequency tan delta of Line Reactor bushings NRPC POWERGRID 08/Apr/19 08/Apr/19 304 PHAGI (765KV)-GWALIOR-WR (765KV)1 09:30 18:30 DAILY For Pre-summer maintenance work eg. CC Ring, Spacer,VD, NRPC POWERGRID 08/Apr/19 10/Apr/19 Bird Guard & Jumper tightening and line maintenance work. 305 400 419,Bina-3 Main bay at Bina 9:00 17:30 Daily For AMP work. POWERGRID WR-II R 09/Apr/19 09/Apr/19 306 765 765 KV Gwalior- Agra # 1 line, dia to be kept open 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 09/Apr/19 09/Apr/19 Polymer insulator (String) in main and Tie bay along with 307 765 765 kV Vindhyachal- Satna 1 Line swichable Reactor at V'chal 9:00 18:00 Daily For switchable reactor Bay AMP work POWERGRID WR-II R 09/Apr/19 09/Apr/19 308 765 765KV Jabalpur-DharamjayGarh#4 Line at Pooling 10:00 18:00 Daily For replacement of multiple base by single insulated base from POWERGRID WR-II R station,jabalpur, dia to be kept open at both ends. 09/Apr/19 09/Apr/19 CGL make LA 309 765 718 Bay, Bus Recator#2 main bay at Satna 9:00 18:00 Daily AMP work POWERGRID WR-II R 09/Apr/19 09/Apr/19 310 400 413,Satna-1 Main bay at Bi na 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 09/Apr/19 11/Apr/19 311 765 765kv Durg-1 Main Bay-704 at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 09/Apr/19 09/Apr/19 312 765 765kV ICT-4 Tie Bay (713) at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 09/Apr/19 09/Apr/19 313 400 400kV PARLI-2 & KOLHAPUR Tie bay _417_at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 09/Apr/19 09/Apr/19 314 400 CGPL MUNDRA 400kV Main Bus-2 at CGPL 8:00 20:00 Continuous Implementation of changes in Bus Protection scheme and CGPL CGPL R 09/Apr/19 10/Apr/19 testing of the same & rectfication of 407 89A isolator alignment 315 400 400 KV RAIGARH_II MAIN BAY_(442)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 09/Apr/19 09/Apr/19 316 220 220kV TRANSFER BUS AT NSPCL SWITCH YARD 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 09/Apr/19 09/Apr/19 317 400 400KV Bhopal- PGCIL Itarsi-I 7:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 09/Apr/19 09/Apr/19 318 400 400 kV SSP - Rajgarh - 1 (Auto reclose of Rajgadh - 2 will remain 7:00 18:00 Daily Maintenance work NCA GETCO out) 09/Apr/19 09/Apr/19 319 400 400 KV Bus -II at 400 KV S/s Khedamara. 8:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R 09/Apr/19 09/Apr/19 320 400 400 kV APL - Hadala Line (Auto reclose of Varsana - Hadala will 8:00 18:00 Daily Spacer providing work GETCO GETCO remain out) 09/Apr/19 09/Apr/19 321 400 CHANDRAPUR-PARLI CKT-3 08:00 18:00 Daily Replacement of Broken Spacer cum Vibration Damper & MSETCL MSETCL nil 09/Apr/19 09/Apr/19 Replacement of faulty Disc 322 220 PUSAD - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Pusad - 09/Apr/19 09/Apr/19 Yewatmal Ckt is 323 400 400kV Vindhyachal-Rihand-I 8:00 18:00 Daily Re-fixing of earthwire , AT SKT POWERGRID NR-3 R 09/Apr/19 09/Apr/19 324 765 765kV ,GT #2 Bay No 800-4 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 09/Apr/19 09/Apr/19 325 220 220KV Gwalior(PGCIL)-Mahalgaon-I 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 09/Apr/19 09/Apr/19 326 400 Gandhar Navsari 2 at Navsari 9:00 17:00 Daily CB Drive Testing at Navsari End & Attending Shutdown nature POWERGRID WR-II R 09/Apr/19 09/Apr/19 defects on 400KV Gandhar navsari 2, required simultaneous 327 400 Navsari Magarwada 2 at Navsari 9:00 17:00 Daily CB Drive Testing at Navsari End & Attending Shutdown nature POWERGRID WR-II R 09/Apr/19 09/Apr/19 defects on 400KV Gandhar navsari 2, required simultaneous 328 400 Bay No-409 Main Bay of 315 MVA ICT-1 at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 09/Apr/19 09/Apr/19 329 400 125MVA BUS REACTOR at Pirana, dia to be kept open 9:00 18:00 Daily CSD RECTIFICATION WORK POWERGRID WR-II C 09/Apr/19 09/Apr/19 330 765 765kV Warora-1 & Solapur-2 Tie bay (708) at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 09/Apr/19 09/Apr/19 331 400 400KV Parli-1 & ICT-2 Tie Bay-405 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 09/Apr/19 09/Apr/19 332 400 400 KV BUS-I at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 09/Apr/19 09/Apr/19 333 220 220KV CHHINDWDA CKT-II_MAIN_BAY_209 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 09/Apr/19 09/Apr/19 334 765 765 KV Seoni-2 Main Bay 710 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 09/Apr/19 09/Apr/19 335 400 SWITCHABLE LR_400kV_B'WATI 2_RAIPUR 9:30 17:00 Daily For AMP works. WRTS-I WRTS-I R 09/Apr/19 09/Apr/19 336 400 315 MVA ICT-2 at Khandwa SS, dia to be kept open 10:00 18:00 Daily For AMP work POWERGRID WR-II R 09/Apr/19 09/Apr/19 337 400 50MVAR Nagda-Shujalpur Ckt-II Switchable Line Reactor bay 10:00 18:00 Daily Vizimax make CSD relay Installation and testing work. POWERGRID WR-II C (403LR) at Nagda. ( Line will be sercive though main and Tie bay) 09/Apr/19 09/Apr/19 338 400 400KV Rihand-Vindhyachal PS ckt 1 0:00 0:00 DAILY Re-fixing of broken earthwire , at Shaktinager (UP) PGCIL PGCIL R 09/Apr/19 09/Apr/19 339 315 MVA ICT -II at 400 KV S/s Raita. 8:00 17:00 Continuous Annual Maintenance Programme. CSPTCL CSPTCL R 09/Apr/19 10/Apr/19 340 400 VSTPS - KORBA Line# 2 (Stage-I, BAY No. 23) at VSTPS end. 8:00 18:00 Continuous Annual Bay Maintenance WRTS-1 NTPC R Being DMT scheme, line outage is required for complete bay 09/Apr/19 10/Apr/19 341 400 400kV WARDHA-MAUDA I 8:00 18:30 Daily Line AMP works & ckt-2 A/R in Non auto mode required for WRTS-I WRTS-I R 09/Apr/19 10/Apr/19 safety. 342 400 Main Bay (414) of 400 KV Tiroda - Warora Line-2 at Warora SS 9:00 18:00 Continouus Breaker Pole replacement ATIL ATIL 09/Apr/19 10/Apr/19 343 400 400kv BR & Future Tie bay (414) at Mapusa 9:00 18:00 Cont. Replacement of existing VARM AR Relay with numerical Relay WRTS-I WRTS-I R 09/Apr/19 10/Apr/19 344 765 765 Bus -I at Dharamjaygarh 9:00 18:00 Continous For Equipment erection work under 765KV Bus for Bus- WRTS-I WRTS-I C 09/Apr/19 10/Apr/19 Sectionalizing work by M/s Techno at Dharamjaigarh PS. 345 400 400 KV ITARSI # 1 L/R AT 400 KV MPPTCL INDORE SS 9:00 18:00 CONTINUOUS FOR VAIOUS TESTS OF CONDITION ASSESSMENT OF POWERGRID WR-II R 09/Apr/19 10/Apr/19 REACTORS ABOVE 20 YEARS( LINE SHALL REMAIN IN 346 400 126 MVAR,400KV Bus reactor-3 , Phase -4 switchyard,(4061 & 10:00 10:00 Continuous 400KV Bus reactor No-3 with 4061 Main bay & 4060 tie bay ATIL ATIL Routine 4060 bay) APMuL ,Mundra 09/Apr/19 10/Apr/19 ,Annual routine maintenance work 347 400 VSTPS - KORBA Line# 2 Line Reactor ( Stage-I, BAY No. 23) at 8:00 18:00 Continuous Annual Maintenance, Testing & Attending oil Leakage NTPC NTPC R VSTPS end 09/Apr/19 12/Apr/19 348 400 400kV BUS-1 at 400 KV Nikol-2 S/S 10:00 20:00 Continuous To replace faulty module (GC01.Y phase) TPL TPL R 09/Apr/19 13/Apr/19 349 400 400 KV PGCIL (PIRANA) - NICOL.2(TPL) –LINE 1 10:00 20:00 Continuous To replace faulty module (GC01.Y phase) and leakage from TPL TPL R 09/Apr/19 14/Apr/19 GC02.R phase compartment. 350 400 JAIGAD-KARAD - I & II (AR IN NON-AUTO MODE) 09:00 18:00 Daily Hotline insulator washing JPTL JPTL AR to be kept in 09/Apr/19 15/Apr/19 Non-auto mode 351 Orai (765KV)-JABALPUR2 10:00 18:30 DAILY For Fine tunning of CSD relay available for associated Line NRPC POWERGRID 09/Apr/19 09/Apr/19 Reactor through on Line switching , requested by WR-2 352 RIHAND NTPC (400KV)- VINDHYACHAL POOL-WR (400KV)1 08:00 18:00 DAILY Re-fixing of broken earthwire . NRPC POWERGRID 09/Apr/19 09/Apr/19 353 765 765 KV Gwalior-Agra # 2 line, dia to be kept open 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 10/Apr/19 10/Apr/19 Polymer insulator (String) in main and Tie bay along with 354 400 400 KV _RAIGARH_I MAIN BAY (441)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 10/Apr/19 10/Apr/19 355 220 220kV BSP Line-1 with 220kV BUS-2 AT NSPCL SWITCH YARD 6:30 17:00 Daily Annual Maintenance NSPCL NSPCL R 10/Apr/19 10/Apr/19 356 400 400KV Sarni-Seoni 7:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 10/Apr/19 10/Apr/19 357 220 MAHALAXMI - AMONA 08:00 17:00 Daily Routine Maintenance & Diagnostic testing work MSETCL MSETCL - 10/Apr/19 10/Apr/19 358 400 400 kV APL - Hadala Line (Auto reclose of Varsana - Hadala will 8:00 18:00 Daily Spacer providing work GETCO GETCO remain out) 10/Apr/19 10/Apr/19 359 220 220 kV Khanpur - Dehgam (PG) line No. 2 8:00 18:00 Daily Maintenance work GETCO GETCO 10/Apr/19 10/Apr/19 360 400 CHANDRAPUR 2-KUMBHARGAON(NANDED) CKT - 2 08:00 18:00 Daily Replacement of Broken Spacer cum Vibration Damper MSETCL MSETCL nil 10/Apr/19 10/Apr/19 361 132 MANSAR-PENCH 09:00 17:00 Daily Replacement of Jumper MSETCL MSETCL Outage to be 10/Apr/19 10/Apr/19 availed subject to 362 220 220KV Gwalior(PGCIL)-Mahalgaon-II 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 10/Apr/19 10/Apr/19 363 400 Gandhar Kosamba by Navsari TLM 9:00 17:00 Daily Line AMP/ Attending Shutdown nature defects POWERGRID WR-II R 10/Apr/19 10/Apr/19 364 400 Bay No-410 Main Bay of 400kv Tarapur-boisar ckt-II Line at 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Boisar 10/Apr/19 10/Apr/19 365 400 WARORA - Wardha(PG) 09:00 18:00 Daily Routine Maintenance & Dignostic testing work Nut Bolt MSETCL MSETCL 400KV WARORA- 10/Apr/19 10/Apr/19 Tightning work IEPL Line is in 366 400 BUS COUPLER @ KOLHAPUR-III (TALANDGE)-400 KV 09:00 18:00 Daily Quarterly. Maint. work MSETCL MSETCL - 10/Apr/19 10/Apr/19 367 400 415 KALA 1 Main Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 10/Apr/19 10/Apr/19 368 400 Jabalpur -Itarsi #1 CH-2 PLCC at both ends 9:00 18:00 Daily Online Retrofitting of CH-2 ABB make ETI-21 PLCC and NSD- POWERGRID WR-II C 10/Apr/19 10/Apr/19 60 Protection Coupler with ETL-41 PLCC and NSD-50 369 400 400KV Parli-1 Main Bay-406 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 10/Apr/19 10/Apr/19 370 400 400kV Dhariwal and Solapur-II Tie bay (411) at Parli 9:00 18:00 Daily For Bay AMP works WRTS-I WRTS-I R 10/Apr/19 10/Apr/19 371 400 400 KV BUS-II at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 10/Apr/19 10/Apr/19 372 220 220kV JEUR Main Bay_209 at Solapur 9:00 18:00 Daily For AMP works MSETCL WRTS-I R 10/Apr/19 10/Apr/19 373 706 765 Kv ICT-2 Main Bay 706 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 10/Apr/19 10/Apr/19 374 400 400kV Damoh-Birsinghpur line#2 terminal equipment With Line 9:00 18:00 Daily AMP work POWERGRID WR-II R Reactor at Damoh, dia to be kept open at both ends 10/Apr/19 10/Apr/19 375 400 400KV Bhadrawati-III Main bay (421) at Raipur ss 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 10/Apr/19 10/Apr/19 376 400 ICT2_400/220kv_BHATAPARA 10:00 12:00 Daily For Replacement of faulty WTI sensors WRTS-I WRTS-I R 10/Apr/19 10/Apr/19 377 220 JEUR - SOLAPUR PG 10:00 16:00 Daily QM Work MSETCL MSETCL Load affected : 10/Apr/19 10/Apr/19 132KVParewadi, 378 400 PARLI-SOLAPUR (LAMBOTI) 10:00 17:00 Daily (1) Line maint. Work. (2) Bay maint.work. (3) C&Tan delta MSETCL MSETCL - 10/Apr/19 10/Apr/19 Measurement of CVT 379 400 400KV ICT#2 at Rewa, dia to be kept open 10:00 18:00 DAILY AMP WORKS POWERGRID WR-II R 10/Apr/19 10/Apr/19 380 400 Jabalpur -Itarsi #1 Line 16:00 18:00 Daily Line Outage for checking end-to-end testing and code POWERGRID WR-II C 10/Apr/19 10/Apr/19 transmission after retrofitting of CH-2 PLCC and Protection 381 765 707 main bay of 765kV 240 MVAR Bus Reactor at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 10/Apr/19 11/Apr/19 382 400 765 kV S/C Solapur - Pune 8:00 20:00 Daily Power line crossing of 765 kV D/C Solapur-Pune line by 765 PGCIL CWRTL Constrution 10/Apr/19 11/Apr/19 KV D/C LILO Aurangabad - Padghe Line 383 400 400KV ISP -I at 400KV S/S Indore 9:00 18:00 Continue For replacement of bus-II P.G isolator of ISP-I.400 KV ISP-I MPPTCL MPPTCL R 10/Apr/19 11/Apr/19 will be on TBC. 384 400 400 KV ICT3_MAIN_BAY_407 at Bilaspur PS 9:00 18:00 Conti? For AMP works WRTS-I WRTS-I R 10/Apr/19 11/Apr/19 385 220 PUSAD - WARDHA (PG) 08:00 18:00 Daily Fixing of vibration Damper at various line location. MSETCL MSETCL 220 kV Pusad - 10/Apr/19 12/Apr/19 Yewatmal Ckt is 386 400 400 KV Jhanor Bus-1 8:00 18:00 CONTINOUS ANNUAL MAINTENANCE(checking and cleaning of BPI, clamp NTPC NTPC R 10/Apr/19 12/Apr/19 tightness checking/replacement if any) 387 400 PADGHE - KALWA 2 (AR IN NON-AUTO MODE) 09:00 18:00 Daily PID Testing work of 400 KV Kalwa-Padgha Ckt-2 line Insulator MSETCL MSETCL - 10/Apr/19 20/Apr/19 strings at various locations. Auto-Reclose function to be out of 388 765 765kV Gwalior-Jaipur#1 Line (dia to be kept open) along with 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 765kV Bus-1 at Gwalior 11/Apr/19 11/Apr/19 Polymer insulator (String) in main and Tie bay along with 389 765 765kV Gwalior-Phagi-1 8:00 18:30 Daily For Pre-summer maintenance work eg. CC Ring, Spacer,VD, POWERGRID NR-I R 11/Apr/19 13/Apr/19 Bird Guard & Jumper tightening 390 400 400KV VINDHYACHAL - JABALPUR # 2 Line 9:00 18:00 Daily AMP of 400 kV Vindhyachal # 2 LR and line terminal POWERGRID WR-II R (404 L), A/R to be kept in the non-auto of circuit-1, dia to be kept 11/Apr/19 11/Apr/19 equipments. A/R of 400 kV Vindhyachal - Jabalpur # 1 is to be 391 400 400 KV Raipur-1 Main Bay 415 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 11/Apr/19 11/Apr/19 392 400 CGPL MUNDRA 400kV Main Bus-1 at CGPL 8:00 20:00 Continuous Implementation of changes in Bus Protection scheme and CGPL CGPL R 11/Apr/19 12/Apr/19 testing of the same 393 400 400 Korba Mahan Bay at NTPC korba end 8:00 18:00 Continuous For Shunt reactor erection work WRTS-2 NTPC C 11/Apr/19 13/Apr/19 394 220 PUSAD - WARDHA (PG) 07:00 17:00 Daily String Replacement work MSETCL MSETCL nil 11/Apr/19 11/Apr/19 395 400 400KV Bhopal- PGCIL Itarsi-II 7:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 11/Apr/19 11/Apr/19 396 400 400 kV SSP - Rajgarh - 2(Auto reclose of Rajgadh - 1 will remain 7:00 18:00 Daily Maintenance work NCA GETCO out) 11/Apr/19 11/Apr/19 397 400 400 kV Hadala-Vadinar line 2 8:00 18:00 Daily Bay equipment maintenance work GETCO GETCO 11/Apr/19 11/Apr/19 398 400 CHANDRAPUR-PARLI CKT-3 08:00 18:00 Daily Replacement of Broken Spacer cum Vibration Damper MSETCL MSETCL nil 11/Apr/19 11/Apr/19 399 400 MAIN BUS - 1 @ AKOLA 08:00 18:00 Daily Routine Maintenance & testing work MSETCL MSETCL NIL 11/Apr/19 11/Apr/19 400 400 DHULE- - BABLESHWAR - I & AR OF CKT-2 IN NON-AUTO 08:00 18:00 Daily Replacement of faulty insulator found in PID MSETCL MSETCL 400kV BBLR ckt MODE 11/Apr/19 11/Apr/19 2 A/R switch to 401 765 765kV ,GT #2 Tie Bay No 800-5 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 11/Apr/19 11/Apr/19 402 220 220 kV Haldarva-Kawas line - 1 9:00 17:00 Daily Maintenance work GETCO GETCO 11/Apr/19 11/Apr/19 403 400 MAIN BUS 'B' @ CHAKAN 09:00 17:00 Daily Half yearly testing and maintenance activities MSETCL MSETCL - 11/Apr/19 11/Apr/19 404 400 Ukai- Navsari at Navsari 9:00 17:00 Daily Attending Shutdown nature defects of 400KV Ukai Navsari, POWERGRID WR-II R 11/Apr/19 11/Apr/19 required simultaneous shutdown to facilitate work on Multi 405 400 Navsari Magarwada 2 at Navsari 9:00 17:00 Daily Attending Shutdown nature defects of 400KV Ukai Navsari, POWERGRID WR-II R 11/Apr/19 11/Apr/19 required simultaneous shutdown to facilitate work on Multi 406 400 Bay No-411 Tie Bay of 400kv Boisar-Vapi & 400kv Boisar- 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Tarapur ckt-II Line at Boisar 11/Apr/19 11/Apr/19 407 400 400 kV Kosamba Aoj line 9:00 18:00 Daily Maintenance of bays at Kosamba end GETCO GETCO 11/Apr/19 11/Apr/19 408 400 80 MVAr Bus reactor @ Talandge 09:00 18:00 Daily Quarterly. Maint. work MSETCL MSETCL - 11/Apr/19 11/Apr/19 409 400 400kV ICT1 Main bay _401 at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 11/Apr/19 11/Apr/19 410 400 SWITCHABLE_LR_400kV_PARLI1_ WARORA_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 11/Apr/19 11/Apr/19 411 765 765kV Bus-2 & Bus-4 Bus Section Bay (711) at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 11/Apr/19 11/Apr/19 412 765 765KV RANCHI 1 MAIN BAY(731) AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 11/Apr/19 11/Apr/19 413 38.5 MSR-2 of STATCOM at Aurangabad 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 11/Apr/19 11/Apr/19 414 765 765 KV INDORE VADODARA LINE at Indore 9:00 0:00 DAILY FOR INSTALLATION OF ADDITIONAL BPI TO PROVIDE FOR POWERGRID WR-II C 11/Apr/19 11/Apr/19 DROP CONDUCTOR IN PHASE NOT HAVING WAVE TRAP 415 400 400KV Tamnar-I & Future Tie bay(432) at Raipur ss 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 11/Apr/19 11/Apr/19 416 400 ICT1_400/220kv_BHATAPARA 10:00 12:00 Daily For Replacement of faulty WTI sensors WRTS-I WRTS-I R 11/Apr/19 11/Apr/19 417 400 400 kV Kudgi-I and Mapusa Ckt-II Tie bay (402) at Kolhapur-GIS 10:00 18:00 Daily For AMP works WRTS-I WRTS-I R 11/Apr/19 11/Apr/19 418 400 DGEN Unit 53BAT 480MVA generator transformer energization 11:00 18:00 Continuous Unit 53 generator transformer routine energisation during RSD TPL - DGEN TPL - DGEN R 11/Apr/19 11/Apr/19 for healthiness checking 419 400 DGEN 51BAT 480MVA generator transformer De energization 11:00 18:00 continuous Unit 51 Generator transformer remains de-energized during TPL - DGEN TPL - DGEN R 11/Apr/19 11/Apr/19 RSD and shutdown for energy conservation 420 400 400 kV Kasor-SSP line (Auto reclose of 400 KV Asoj-Chorania 7:00 17:00 Daily Line maintenance work GETCO GETCO line 1 and 400 KV Asoj-SSP will remain out) 11/Apr/19 12/Apr/19 421 765 765kv ICT-1 Main Bay 706 at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 11/Apr/19 12/Apr/19 422 400 400kV WARDHA-MAUDA II 8:00 17:00 Daily Line AMP works & ckt-1 A/R in Non auto mode required for WRTS-I WRTS-I R 11/Apr/19 12/Apr/19 safety. 423 400 Sipat-Raipur Line-2 8:00 18:00 Continuous For PM WRTS-1 NTPC R 11/Apr/19 13/Apr/19 424 765 765kV Gwalior-Phagi-2 8:00 18:30 Daily 'For Pre-summer maintenance work eg. CC Ring, Spacer,VD, POWERGRID NR-1 R 11/Apr/19 13/Apr/19 Bird Guard & Jumper tightening. 425 400 400 kV APL - Hadala Line (Auto reclose of Varsana - Hadala will 8:00 18:00 Daily Open Spacer providing work in line GETCO GETCO remain out) 11/Apr/19 11/Apr/19 426 PHAGI (765KV)-GWALIOR-WR (765KV)2 08:00 18:00 DAILY For Pre-summer maintenance work eg. CC Ring, Spacer,VD, NRPC POWERGRID 11/Apr/19 13/Apr/19 Bird Guard & Jumper tightening and line maintenance work. 427 220 PUSAD - WARDHA (PG) 07:00 17:00 Daily String Replacement work MSETCL MSETCL nil 12/Apr/19 12/Apr/19 428 765 765 kV Bus -II at Vindhyachal Pooling 9:00 18:00 Daily For Bus side Isolator alaignment rectification work. POWERGRID WR-II R 12/Apr/19 13/Apr/19 429 400 400KV Asoj-Indore #1 at Asoj 9:00 18:00 Daily For Line Isolator 89L Replacement work POWERGRID WR-II R 12/Apr/19 12/Apr/19 430 400 414,Satna-1 & Bus reactor Tie bay at Bina 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 12/Apr/19 14/Apr/19 431 400 400KV Asoj-Indore #1 at Asoj 9:00 18:00 Daily PLCC Ch-2 Retrofitting & replacement of coupling devices at POWERGRID WR-II C 12/Apr/19 12/Apr/19 Both end 432 400 400KV Pithampur Indore (PGCIL)-I 10:00 18:00 Daily For Pre monsoon maintenance and testing work MPPTCL MPPTCL R 12/Apr/19 12/Apr/19 433 400 400 KV Raipur-1 Tie Bay 414 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 12/Apr/19 12/Apr/19 434 400 400 KV RAIGARH_I &RKM-II TIE BAY_ (440) KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 12/Apr/19 12/Apr/19 435 400 400 KV Khedamara-Korba West Ext-I Line at 400 KV S/s 8:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R Khedamara. 12/Apr/19 12/Apr/19 436 400 400 kV Hadala-Vadinar line 2 8:00 18:00 Daily Maintenance work GETCO GETCO 12/Apr/19 12/Apr/19 437 400 400 kV Chorania-Mansar Line 8:00 18:00 Daily Conditioning monitoring work at 400KV Chorania S/s. PGCIL GETCO 12/Apr/19 12/Apr/19 438 400 NAGOTHANE - DABHOL 1 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing MSETCL MSETCL Load can be 12/Apr/19 12/Apr/19 managed on 439 400 DHULE- - BABLESHWAR - II & AR OF CKT-1 REQUIRED IN NON- 08:00 18:00 Daily Replacement of fault insulator strings found in PID MSETCL MSETCL 400kV BBLR ckt- AUTO MODE 12/Apr/19 12/Apr/19 1 A/R switch to 440 765 765KV D'JAIGARH- CHAMPA I 8:30 19:00 Daily For Line AMP works. WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 441 765 709-Bay - Main Bay of 765 kV Akola Line 1 Koradi-III at 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL substation 12/Apr/19 12/Apr/19 442 220 Haldarwa - Kawas line 2 9:00 17:00 Daily Maintenance work PGCIL GETCO 12/Apr/19 12/Apr/19 443 400 Bay No-412 Main Bay of 400kv Vapi-boisar Line at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 12/Apr/19 12/Apr/19 444 400 417 Kala 2 Main Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 12/Apr/19 12/Apr/19 445 400 125 MVAR Bus Reactor #1 at Itarsi, dia to be kept open 9:00 18:00 Daily For Re-Commissinong of CSD and Retrofitting of REF Relay POWERGRID WR-II C 12/Apr/19 12/Apr/19 446 400 400KV Wardha-1 & Future Tie Bay-408 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 12/Apr/19 12/Apr/19 447 400 400kV Solapur-II Main Bay (412) at Parli 9:00 18:00 Daily For Bay AMP works WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 448 765 765kV ICT-4 Main Bay (714) at Tamnar PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 449 400 ICT1_400/220kv_SEONI 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 450 765 765KV JABALPUR 3 SWITCHABLE LR AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 12/Apr/19 12/Apr/19 451 765 SWITCHABLE LR_765kV_RAICHUR 2_SOLAPUR 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 452 38.5 MSR-1 of STATCOM at Aurangabad 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 453 402 765/400Kv ICT-1 & Future Tie bay 402 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 454 400 400kV Damoh-Bhopal line#1 terminal equipment at Damoh, dia 9:00 18:00 Daily AMP work POWERGRID WR-II R to be kept open both ends 12/Apr/19 12/Apr/19 455 400 400KV Tamnar-I Main bay (433) at Raipur ss 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 456 400 KANSARI-VELUDA LINE at Kansari by Pirana S/s 10:00 17:00 Daily DC MIXING ISSUE RESOLVE POWERGRID WR-II R 12/Apr/19 12/Apr/19 457 765 765kV ICT-2Aurangabad-1 Tie bay (705) at Padghe-GIS 10:00 17:00 Daily For AMP works WRTS-I WRTS-I R 12/Apr/19 12/Apr/19 458 765 765/400kV 1500MVA ICT-2 @ EKTUNI 10:00 18:00 Daily Diagnostic Testing & Routine Maintainence MSETCL MSETCL 765/400kV ICT-I 12/Apr/19 12/Apr/19 will be in service. 459 220 220 KV Bhestan 1 (bay 209) at Navsari 10:00 18:00 Daily RTV Coating on terminal equipments POWERGRID WR-II R 12/Apr/19 12/Apr/19 460 400 BAY 403 ( MAIN BAY OF 400KV ITARSI-1 LINE ) AT MPPTCL by 0:00 0:00 DAILY BAY AMP WORKS POWERGRID WR-II R Indore S/s 12/Apr/19 12/Apr/19 461 765 708 main bay of 765kV 240 MVAR Bus Reactor at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 12/Apr/19 13/Apr/19 462 400 400kV 418 52 Main breaker of Bus Reactor at CGPL end 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R 12/Apr/19 13/Apr/19 463 400 400kv ICT-I & Kolhapur-1 Tie Bay (411) at Mapusa 9:00 18:00 Cont. Replacement of existing VARM AR Relay with numerical Relay WRTS-I WRTS-I R 12/Apr/19 13/Apr/19 464 400 400 KV ACBL2_MAIN_BAY_416 at Bilaspur PS 9:00 18:00 Conti? For AMP works WRTS-I WRTS-I R 12/Apr/19 13/Apr/19 465 220 BOISAR II - PGCIL 2 ON TBC 09:00 17:00 Continuous TBC OPERATION FOR BREAKER OVERHAULING WORK AT MSETCL MSETCL Line will be in 12/Apr/19 14/Apr/19 220KV BOISAR-II S/S service. Only 466 400 315MVA ICT-II at Shujalpur.(Dia will be open after putting ICT-II 10:00 18:00 Continuous Oil leakage attending and backup Impedance relay installation POWERGRID WR-II C out ) 12/Apr/19 14/Apr/19 and testing work. 467 400 400/220 KV 315MVA ICT - 1 @ KARAD 10:00 17:00 Continuous OLTC overhauling work, Attending oil leakage by new MSETCL MSETCL Load manage on 12/Apr/19 16/Apr/19 technique, ICT Painting work & Annual Maint. Work, 400 KV other Two ICTs 468 400 400 kV APL - Hadala Line (Auto reclose of Varsana - Hadala will 8:00 18:00 Daily Open Spacer providing work in line GETCO GETCO remain out) 12/Apr/19 12/Apr/19 469 220 WARDHA- PGCIL(DEOLI) 10:00 17:00 Daily Maintenance work on line MSETCL MSETCL PGCIL(deoli)- 13/Apr/19 13/Apr/19 Badnera ckt, 470 400 400 kV Amreli - Hadala Line (Auto reclose of Amreli - Jetpur - 2 8:00 18:00 Daily Line maintenance work GETCO GETCO will remain out) 13/Apr/19 13/Apr/19 471 400 Mundra-Jetpur Ckt#2 Line 9:00 10:00 daily To take Line Reactor out for NIFPS system installation at POWERGRID WR-II 13/Apr/19 13/Apr/19 Jetpur End 472 400 400/220 kV, 315 MVA ICT-1 Mansar 8:00 18:00 Daily Bay maintenance, 89-A & 89-C Isolator maint work GETCO GETCO 13/Apr/19 13/Apr/19 473 400 400 kV Bus-A Mansar 8:00 18:00 Daily 89-A & 89-C Isolator maint work of ICT-1 bay GETCO GETCO 13/Apr/19 13/Apr/19 474 400 400 kV Bus Coupler Mansar 8:00 18:00 Daily 89-A & 89-C Isolator maint work of ICT-1 bay GETCO GETCO 13/Apr/19 13/Apr/19 475 400 400 kV TBC Bus Mansar 8:00 18:00 Daily 89-A & 89-C Isolator maint work of ICT-1 bay GETCO GETCO 13/Apr/19 13/Apr/19 476 400 400KV Asoj-Indore # 2 at Asoj 9:00 18:00 Daily For Line Isolator 89L Replacement work POWERGRID WR-II R 13/Apr/19 13/Apr/19 477 400 400KV Pithampur Indore (PGCIL)-II 10:00 18:00 Daily For Pre monsoon maintenance and testing work MPPTCL MPPTCL R 13/Apr/19 13/Apr/19 478 400 PADGHE - NAGOTHANE 1 08:00 17:00 Daily Faulty string and Jumper replacement work MSETCL MSETCL ... 13/Apr/19 13/Apr/19 479 400 KORADI 2-WARDHA PGCIL 09:00 18:00 Daily Routine Maintenance & Dignostic testing work Nut Bolt MSETCL MSETCL 400KV WARORA- 13/Apr/19 13/Apr/19 Tightning work IEPL Line is in 480 400 CHANDRAPUR-PARLI CKT-3 08:00 18:00 Daily Replacement of Broken Spacer cum Vibration Damper MSETCL MSETCL Nil 13/Apr/19 13/Apr/19 481 400 BABHALESHWAR - PADGHE 1 08:00 18:00 Daily DCRM & DIAGNOSTIC TESTING WORK MSETCL MSETCL DIAHNOSTIC 13/Apr/19 13/Apr/19 TESTING WORK 482 765 765kV , Bus Reactor Bay No 800-6 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 13/Apr/19 13/Apr/19 483 400 400KV Chakan & Kharghar Tienbay (402) at Pune (Talegaon) 9:00 17:00 Daily Replacment of Clamps & connectors WRTS-I WRTS-I R 13/Apr/19 13/Apr/19 484 400 Bay No-413 Main Bay of 400kv Tarapur-boisar ckt-I Line at 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Boisar 13/Apr/19 13/Apr/19 485 400 417 Bay, Vind#4- Bina#4 Tie bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 13/Apr/19 13/Apr/19 486 400 400KV Wardha-1 Main Bay-409 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 13/Apr/19 13/Apr/19 487 400 400 KV Warora-1 Tie bay 405 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 13/Apr/19 13/Apr/19 488 220 220 KV Bhestan 2 (bay 210) at Navsari 10:00 18:00 Daily RTV Coating on terminal equipments POWERGRID WR-II R 13/Apr/19 13/Apr/19 489 400 BAY 404 ( MAIN BAY OF 400KV ITARSI-2 LINE ) AT MPPTCL by 0:00 0:00 DAILY BAY AMP WORKS POWERGRID WR-II R Indore S/s 13/Apr/19 13/Apr/19 490 400 400/220/33 KV 315MVA ICT - 2 @ BABHALESHWAR 08:00 18:00 Continuous Oil Filtration work MSETCL MSETCL 400/220kV 13/Apr/19 15/Apr/19 315MVA ICT- I , 491 400 NEW KOYNA - DABHOL - II 08:00 18:00 Daily LE Scheme for insulator string replacement & Cold washing of MSETCL MSETCL Load can be 13/Apr/19 20/Apr/19 insulators managed on 492 500 CHANDRAPUR - PADGHE HVDC POLE 2 06:00 18:00 Daily Erection and Dismantling of 3 nos. of Towers & Stringing Of MSETCL MSETCL 500KV HVDC 14/Apr/19 14/Apr/19 Conductor ( 5 span) Of 33KV Chandrapur-Chincholi Earth Pole-I Line will 493 765 765kV Satna-Bina Line-2 at Bina, dia to be kept open at both 9:15 17:30 Daily For erection of additional BPI in Y phase of Line isolator. POWERGRID WR-II R ends 14/Apr/19 14/Apr/19 Line , Line Reactor and dia. will be out of service during outage 494 500 CHANDRAPUR - PADGHA POLE 1 & 2 06:00 22:00 Daily Replacement of Bent D leg of tower loc. 121 of 500KV MSETCL MSETCL During recent 14/Apr/19 14/Apr/19 Chandrapur-Padghe HVDC Line. patrolling it is 495 765 765kV Satna-Bina Ckt#2 by Damoh TLM, dia to be kept open at 9:00 18:00 Daily AMP work & rectification of S/D nature defects POWERGRID WR-II R both ends. 14/Apr/19 14/Apr/19 496 765 765 KV ICT-2 at Gwalior, dia kto be kept open 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 14/Apr/19 14/Apr/19 Polymer insulator (String) in main and Tie bay along with 497 400 400 kV Bus-A Mansar 8:00 18:00 Daily Isolator maintenance work of Reactor bay GETCO GETCO 14/Apr/19 14/Apr/19 498 400 400 kV Bus Coupler Mansar 8:00 18:00 Daily Isolator maintenance work of Reactor bay GETCO GETCO 14/Apr/19 14/Apr/19 499 400 400 kV TBC Bus Mansar 8:00 18:00 Daily Isolator maintenance work of Reactor bay GETCO GETCO 14/Apr/19 14/Apr/19 500 400 AC Filter Bank 2 Main bay (459) at Champa-HVDC 9:00 18:00 Daily For AMP Works WRTS-I WRTS-I R 14/Apr/19 14/Apr/19 501 220 220KV Bus-2 at Pune (Talegaon) 9:00 17:00 Daily Replacment of Clamps & connectors WRTS-I WRTS-I R 14/Apr/19 14/Apr/19 502 765 765 kV Satna- Bina#2 line at Satna for Installation of BPI, dia to 9:00 18:00 Daily Installation of BPI in Phase where Wave Trap is not available POWERGRID WR-II C be kept open. 14/Apr/19 14/Apr/19 503 400 400 KV Warora-1 Main Bay 406 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 14/Apr/19 14/Apr/19 504 400 125 MVAR Bus Reactor #2 at Itarsi, dia to be kept open. 9:00 18:00 Daily For Replacement of WTI and Retrofitting of REF Relay POWERGRID WR-II C 14/Apr/19 14/Apr/19 505 400 400kV BUS-2 at 400 KV Nikol-2 S/S 10:00 20:00 Daily To attend leakage from GC02.R phase compartment. TPL TPL R 14/Apr/19 14/Apr/19 506 400 400KV Jabalpur-MB#1 Line at Pooling Station,Jabalpur, dia to 10:00 18:00 Daily For replacement of oil leakage Line BPH CVT POWERGRID WR-II R be kept open. 14/Apr/19 14/Apr/19 507 765 765kV Satna-Bina Ckt#1 by Damoh TLM, dia to be kept open at 9:00 18:00 Daily AMP work & rectification of S/D nature defects POWERGRID WR-II R both ends 15/Apr/19 15/Apr/19 508 765 765kV ICT-1 at Gwalior, dia to be kept open 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 15/Apr/19 15/Apr/19 Polymer insulator (String) in main and Tie bay along with 509 400 400KV BUS-1 at Pirana 9:00 17:00 Daily AMP WORK POWERGRID WR-II R 15/Apr/19 15/Apr/19 510 400 400 kV Bus-A Mansar 8:00 18:00 Daily 89-A & 89-C Isolator maint work of ICT-2 bay GETCO GETCO 15/Apr/19 15/Apr/19 511 400 400 kV Bus Coupler Mansar 8:00 18:00 Daily 89-A & 89-C Isolator maint work of ICT-2 bay GETCO GETCO 15/Apr/19 15/Apr/19 512 400 400 kV TBC Bus Mansar 8:00 18:00 Daily 89-A & 89-C Isolator maint work of ICT-2 bay GETCO GETCO 15/Apr/19 15/Apr/19 513 400 400/220 kV, 315 MVA ICT-2 Mansar 8:00 18:00 Daily Bay maintenance, 89-A & 89-C Isolator maint work GETCO GETCO 15/Apr/19 15/Apr/19 514 400 400 KV Bus-1 at Wardha 9:00 18:00 Daily For alignment of newely erected isolator WRTS-I WRTS-I 15/Apr/19 15/Apr/19 515 400 412 ( Main bay of 400 KV Bus reactor # 3) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 15/Apr/19 16/Mar/19 516 400 400 KV DB POWER-I & ICT_1 TIE BAY (431)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 15/Apr/19 15/Apr/19 517 400 400KV Bhopal BDTCL-I 8:00 8:00 Daily For bay equipment maintenance and testing work MPPTCL MPPTCL R 15/Apr/19 15/Apr/19 518 400 400KV Korba Bhilai-1 at NTPC Korba end 8:00 18:00 Continuous For Bay PM WRTS-1 NTPC R 15/Apr/19 15/Apr/19 519 220 KAPS-UKAI - MOTA Line 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 15/Apr/19 15/Apr/19 520 765 711-Bay - Tie Bay of 765 kV Tiroda-Line 1 and Akola Line 2 at 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL Koradi-III substation 15/Apr/19 15/Apr/19 521 220 Haldarva - KAPP line 2 9:00 17:00 Daily Bay Maintenance work at Haldarva end PGCIL GETCO 15/Apr/19 15/Apr/19 522 220 BOISAR II - TARAPUR 09:00 17:00 Daily REPLACEMENT OF DAMAGED EARTH-WIRE MSETCL MSETCL - 15/Apr/19 15/Apr/19 523 400 400KV Pune GIS # 2 & Pune-GIS-3 Tie bay (408) at Pune 9:00 17:00 Daily Replacment of Clamps & connectors WRTS-I WRTS-I R (Talegaon) 15/Apr/19 15/Apr/19 524 400 Bay No-414 Tie Bay of 400kv Tarapur-Boisar-I Line & ICT-II at 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R Boisar 15/Apr/19 15/Apr/19 525 400 400KV Wardha-2 & Future Tie Bay-411 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 15/Apr/19 15/Apr/19 526 400 400 KV SEONI-KHANDWA-1 LR at Seoni 9:00 18:00 Daily FOR MINOR LEAKAGE ATTENDING WORK. WRTS-I WRTS-I R 15/Apr/19 15/Apr/19 Line outage required for take out/in of non switchable line 527 765 765KV JABALPUR 4 SWITCHABLE LR AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 15/Apr/19 15/Apr/19 528 400 400 KV Akola-1 Main Bay 413 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 15/Apr/19 15/Apr/19 529 765 SWITCHABLE LR_765kV_AURANGABAD 1_SOLAPUR 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 15/Apr/19 15/Apr/19 530 400 400kV Damoh-Bhopal line#2 terminal equipment With Line 9:00 18:00 Daily AMP work POWERGRID WR-II R Reactor at Damoh, dia to be kept open at both ends 15/Apr/19 15/Apr/19 531 220 220KV BUS 1 at Vapi 9:00 19:00 Daily Terminal Tightness Work POWERGRID WR-II R 15/Apr/19 15/Apr/19 532 400 765KV ICT#2 Main bay (406 bay) 400KV side at Pooling 10:00 14:00 Daily AMP Works POWERGRID WR-II R station,jabalpur 15/Apr/19 15/Apr/19 533 400 400 KV Kakrapar Navsari 1 at Navsari 10:00 18:00 Daily RTV Coating on terminal equipments POWERGRID WR-II R 15/Apr/19 15/Apr/19 534 400 500MVA ICT # 1 at Vadodara, dia to be kept open 10:00 18:00 Daily For AMP work POWERGRID WR-II R 15/Apr/19 15/Apr/19 535 403 765/400Kv ICT-1 Main bay 403 at Durg PS 10:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 15/Apr/19 15/Apr/19 536 400 765KV ICT#1 Main bay (403 bay) 400KV side at Pooling 14:30 18:00 Daily AMP Works POWERGRID WR-II R station,jabalpur 15/Apr/19 15/Apr/19 537 400 BAY 405 ( MAIN BAY OF 400KV INDORE-1 LINE ) AT MPPTCL by 0:00 0:00 DAILY BAY AMP WORKS POWERGRID WR-II R Indore S/s 15/Apr/19 15/Apr/19 538 765 765kV 240MVAR Dhule- Aurangabad Line reactor at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 15/Apr/19 16/Apr/19 539 400 400kV 413 52 Main breaker of Mundra Bhachau-4 line at CGPL 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R end 15/Apr/19 16/Apr/19 540 400 DHULE - SSNNL I & II (AR IN NON-AUTO MODE) 09:00 17:00 Daily PID testing of insulator strings MSETCL MSETCL 400kV SSNNL- 1 15/Apr/19 16/Apr/19 & 2 A/R switch 541 765 765 ICT-4 Main Bay 717 at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 15/Apr/19 16/Apr/19 542 400 400 KV LANCO1_MAIN_BAY_419 at Bilaspur PS 9:00 18:00 Conti? For AMP works WRTS-I WRTS-I R 15/Apr/19 16/Apr/19 543 400 315MVA ICT-I at Shujalpur.(Dia will be open after putting ICT-I 10:00 18:00 Continuous Oil leakage attending and backup Impedance relay installation POWERGRID WR-II C out ) 15/Apr/19 16/Apr/19 and testing work. 544 400 400KV Nagda at 400KV S/S Indore 14:00 18:00 Continue For replacement of Line Isolators of 400 KV Nagda, Line will be MPPTCL MPPTCL R 15/Apr/19 16/Apr/19 OFF. 545 400 Sipat-Ranchi Line-2 8:00 18:00 Continuous For PM WRTS-1 NTPC R 15/Apr/19 17/Apr/19 546 400 Bus Reactor #2 Tie Bay (427) at Itarsi 9:00 18:00 Continuous For Over Hauling of Circuit Breaker POWERGRID WR-II R 15/Apr/19 20/Apr/19 547 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1 & 2 (AR 09:00 18:00 Daily For PID Work,Shifting of auto reclose switch to non auto mode. MSETCL MSETCL NIL IN NON-AUTO MODE) 15/Apr/19 30/Apr/19 548 400 CHANDRAPUR-PARLI CKT-3 (AR IN NON-AUTO MODE) 09:00 18:00 Daily For PID Work,Shifting of auto reclose switch to non auto mode. MSETCL MSETCL nil 15/Apr/19 30/Apr/19 549 765 701 bay of Dhule -Vadodara line at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 16/Apr/19 16/Apr/19 550 400 400 kV Varsana - Bhachau - 1 8:00 19:00 Daily cold line Water Washing work. GETCO GETCO 16/Apr/19 16/Apr/19 551 765 765kV Jabalpur-Bina Ckt#1 by Damoh TLM, 9:00 18:00 Daily AMP work & rectification of S/D nature defects POWERGRID WR-II R 16/Apr/19 16/Apr/19 552 400 Bhachau-Varsana Ckt#1 with Non Auto mode of Ckt-1 and 8:00 18:00 daily For application of Silicon grease in bay equipment at Varsana. POWERGRID WR-II 400kV Bus-A at Varsana SS (Dia to be kept open at both end) 16/Apr/19 16/Apr/19 553 765 713 Bay, Vindhyachal#1 main bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 16/Apr/19 17/Apr/19 554 400 400KV BUS-2 at Pirana 9:00 17:00 Daily AMP WORK POWERGRID WR-II R 16/Apr/19 16/Apr/19 555 765 709 (765 KV ICT # 2 main bay) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 16/Apr/19 17/Apr/19 556 400 416,Satna-2 Main bay at Bina 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 16/Apr/19 18/Apr/19 557 400 400 KV Bus-2 at Wardha 9:00 18:00 Daily For alignment of newely erected isolator WRTS-I WRTS-I 16/Apr/19 17/Apr/19 558 400 400 kV Bus-02 (400 kV Hadala SS) 8:00 18:00 Daily Maintenance work GETCO GETCO 16/Apr/19 16/Apr/19 559 400 400 KV ICT_1_MAIN BAY (430)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 16/Apr/19 16/Apr/19 560 400 400 kV Asoj - SSP (Auto reclose of Kasor - SSP will remain out) 7:00 18:00 Daily Maintenance work GETCO GETCO 16/Apr/19 16/Apr/19 561 220 OSMANABAD - PARLY (PG) 08:00 16:00 Daily LINE maintenance MSETCL MSETCL - 16/Apr/19 16/Apr/19 562 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1 08:00 18:00 Daily Replacement of Polymer String MSETCL MSETCL NIL 16/Apr/19 16/Apr/19 563 400 VSTPS BUS #3 8:00 18:00 Continuous Hot Spot rectification of Bus-3 NTPC NTPC R 16/Apr/19 16/Apr/19 564 220 KAPS-VAPI Line # 1 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 16/Apr/19 16/Apr/19 565 765 765kV ,GT #3 Bay No 800-7 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 16/Apr/19 16/Apr/19 566 765/400 765/400 kV ICT #1 at Vindhyachal Pooling, dia to be kep to 9:00 14:00 Daily For taking Spare ICT with ICT#1 B Ph POWERGRID WR-II R open. 16/Apr/19 16/Apr/19 567 400 400KV Bus Reactor Main Bay (415) at Pune (Talegaon) 9:00 17:00 Daily For AMP works WRTS-I WRTS-I R 16/Apr/19 16/Apr/19 568 400 Bay No-415 Main Bay of 315 MVA ICT-2 at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 16/Apr/19 16/Apr/19 569 400 400 kV Jhanor - Kosamba line Main & Tie bay at Kosamba (line 9:00 18:00 Daily Bay maintenance and condition monitoring work PGCIL / GETCO GETCO will remain out) 16/Apr/19 16/Apr/19 570 220 220KV Pandhurna-Kamleshwar 9:00 18:00 Daily For line maintenance work MPPTCL MPPTCL R 16/Apr/19 16/Apr/19 571 400 400KV Wardha-2 Main Bay-412 at Warora_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 16/Apr/19 16/Apr/19 572 400 400kV Parli(MSETCL)-II Main Bay (418) at Parli 9:00 18:00 Daily For Bay AMP works WRTS-I WRTS-I R 16/Apr/19 16/Apr/19 573 400 400kv Bus -I at Dharamjaygarh 9:00 18:00 Daily Bus Bar integration and jumper connection for up coming WRTS-I WRTS-I C 16/Apr/19 16/Apr/19 400KV Bus Reactor 574 400 400KV Raigarh-IV Main bay(439) at Raipur ss 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 16/Apr/19 16/Apr/19 575 400 500 MVA ICT-3 at Khandwa SS, dia to be kept open 10:00 18:00 Daily For AMP work POWERGRID WR-II R 16/Apr/19 16/Apr/19 576 400 400 KV Kakrapar Navsari 2 at Navsari 10:00 18:00 Daily RTV Coating on terminal equipments POWERGRID WR-II R 16/Apr/19 16/Apr/19 577 400 400 kV PGCIL(Dehgam) - Soja line (Auto relcose of WTPS - 8:00 18:00 Daily Maintenance work GETCO GETCO Dehgam will remain out) 16/Apr/19 16/Apr/19 578 400 BAY 406 ( MAIN BAY OF 400KV INDORE-2 LINE ) AT MPPTCL by 0:00 0:00 DAILY BAY AMP WORKS POWERGRID WR-II R Indore S/s 16/Apr/19 16/Apr/19 579 400 VSTPS BUS SECTION-3 (Stage-III, Bay No. 28) 8:00 18:00 Continuous Annual Bay Maintenance NTPC NTPC R 16/Apr/19 17/Apr/19 580 764 715 Bay, GWALIOR main bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 16/Apr/19 16/Apr/19 581 400 400kv Kolhapur-I Main Bay (412) at mapusa 10:00 16:00 Cont. Replacement of existing VARM AR Relay with numerical Relay WRTS-I WRTS-I R 16/Apr/19 17/Apr/19 582 400 400 kV Transfer Bus & Bay -Amreli 8:00 18:00 Daily Bay maintenance + Condition monitoring work GETCO GETCO 16/Apr/19 17/Apr/19 583 400 BABHALESHWAR - PADGHE 2 09:00 17:00 Daily PID testing work MSETCL MSETCL AR required in 16/Apr/19 18/Apr/19 non-auto mode 584 220 TAPS 34 - Boisar Line 2 9:00 18:00 Continuous CB, ES, DS, LA, CT, LA, WT, POWERGRID NPCIL R 16/Apr/19 17/Apr/19 CVT Annual PM 585 765 702 tie bay of Dhule Vadodara Line at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 17/Apr/19 17/Apr/19 586 400 400 kV Varsana-Bhachau-2 8:00 19:00 Daily Line maintenance work GETCO GETCO 17/Apr/19 17/Apr/19 587 765 765kV Jabalpur-Bina Ckt#2 by Damoh TLM, dia to be kept open 9:00 18:00 Daily AMP work & rectification of S/D nature defects POWERGRID WR-II R at both ends. 17/Apr/19 17/Apr/19 588 400 Bhachau-Varsana Ckt#2 with Non Auto mode of Ckt-1 and 8:00 18:00 daily For application of Silicon grease in bay equipment at Varsana POWERGRID WR-II 400kV Bus-B at Varsana SS (Dia to be kept open at both end) 17/Apr/19 17/Apr/19 589 765 MAIN BUS - 1 @ EKTUNI 10:00 18:00 Daily Diagnostic Testing & Routine Maintainence MSETCL MSETCL 765kV Main Bus- 17/Apr/19 17/Apr/19 II will be in 590 765 765 kV Satna-SASAN#1 line at Satna, dia to be kep to open at 9:00 18:00 Daily Installation of BPI POWERGRID WR-II C both ends. 17/Apr/19 17/Apr/19 591 400 PARLI - KUMBHARGAON(NANDED) CKT - 2 09:00 17:00 Daily Distance relay testing work. MSETCL MSETCL - 17/Apr/19 17/Apr/19 592 400 400 KV _ICT_2_MAIN BAY (429)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 17/Apr/19 17/Apr/19 593 220 TILARI - AMONA LINE 08:00 17:00 Daily Routine Maintenance & Diagnostic testing work MSETCL MSETCL - 17/Apr/19 17/Apr/19 594 400 400KV Korba Bhilai-2 at NTPC Korba end 8:00 18:00 Continuous For Bay PM WRTS-1 NTPC R 17/Apr/19 17/Apr/19 595 220 KAPS-VAPI Line # 2 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 17/Apr/19 17/Apr/19 596 220 Bay No. 201 Main Bay of ICT-I at Boisar, ICT-I will be in service 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R through TBC 17/Apr/19 17/Apr/19 597 220 Itarsi-Hoshangabad #2 Line at Itarsi 9:00 18:00 Daily For AMP works and Relay Testing Works. POWERGRID WR-II R 17/Apr/19 17/Apr/19 598 765 765kV Warora-1 Main_707 at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 17/Apr/19 17/Apr/19 599 400 400kV Bus Reactor-II and Parli-II Tie Bay (417) at Parli 9:00 18:00 Daily For Bay AMP works WRTS-I WRTS-I R 17/Apr/19 17/Apr/19 600 400 400/220KV ICT 1_MAIN_BAY_412 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 17/Apr/19 17/Apr/19 601 400 400kv Bus -II at Dharamjaygarh 9:00 18:00 Daily Bus Bar integration and jumper connection for up coming WRTS-I WRTS-I C 17/Apr/19 17/Apr/19 400KV Bus Reactor 602 400 400kV Future & NTPC-1_Tie Bay_420 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 17/Apr/19 17/Apr/19 603 406 765/400Kv ICT-2 Main bay 406 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 17/Apr/19 17/Apr/19 604 400 AC Filter Bank 1 Main bay (457) at Champa-HVDC 9:00 18:00 Daily For AMP Works, Power regulation not required. WRTS-I WRTS-I R 17/Apr/19 17/Apr/19 605 220 220KV BUS 2 at Vapi 9:00 19:00 Daily Terminal Tightness Work POWERGRID WR-II R 17/Apr/19 17/Apr/19 606 765 765KV Bus Reactor#2 at Pooling station,jabalpur 7:00 9:00 Daily Swapping of Oil leakage Reactor with spare reactor POWERGRID WR-II R 17/Apr/19 17/Apr/19 607 400 MAIN BAY - 404 OF SOLAPUR PG @ ALKUD 10:00 13:30 Daily Quarterly Maint. Work MSETCL MSETCL NA 17/Apr/19 17/Apr/19 608 220 Jhanor Haldarwa 2 at Haldarwa 10:00 17:00 Daily Bay AMP works at GETCO Haldarwa POWERGRID WR-II R 17/Apr/19 17/Apr/19 609 400 MAIN BUS - 1 @ ALKUD 10:00 17:30 Daily Quarterly maintenance work MSETCL MSETCL Load will be 17/Apr/19 17/Apr/19 managed on Bus 610 400 125MVAr BUS Reactor at Vadodara, dia to be kept open 10:00 18:00 Daily For AMP work POWERGRID WR-II R 17/Apr/19 17/Apr/19 611 400 400 kV SOLAPUR-II MAIN bay at Kolhapur(MSETCL) 10:00 18:00 Daily For AMP works, Line will be changed to TBC at WRTS-I WRTS-I R 17/Apr/19 17/Apr/19 Kolhapur(MSETCL) end. 612 400 TIE BAY - 405 OF SOLAPUR PG @ ALKUD 14:00 17:30 Daily Quarterly Maint. Work MSETCL MSETCL NA 17/Apr/19 17/Apr/19 613 400 400 kV PGCIL(Dehgam) - Soja line (Auto relcose of WTPS - 8:00 18:00 Daily Maintenance work GETCO GETCO Dehgam will remain out) 17/Apr/19 17/Apr/19 614 765 765kV 240MVAR Dhule- Vadodara Line reactor at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 17/Apr/19 18/Apr/19 615 220 KALMESHWAR-PANDHURNA 08:00 18:00 Daily Restringing of bottom ph conductor. MSETCL MSETCL Outage to be 17/Apr/19 18/Apr/19 availed subject to 616 400 400kV 426 52 Tie breaker of Mundra Bhachau-2 line at CGPL 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R end 17/Apr/19 18/Apr/19 617 400 BABHALESHWAR - PADGHE 2 (AR IN NON-AUTO MODE) 09:00 17:00 Daily PID testing work MSETCL MSETCL AR required in 17/Apr/19 20/Apr/19 non-auto mode 618 400 JAIGAD-NEW KOYNA-I & II (AR IN NON-AUTO MODE) 09:00 18:00 Daily Hotline insulator washing work JPTL JPTL A/R to be kept 17/Apr/19 20/Apr/19 into non auto 619 220 EKALAHARA(OCR)-NAVASARI II 09:00 18:00 Continuous Repalcement of insulator with long rod MSETCL MSETCL if made available 17/Apr/19 25/Apr/19 by CO mumbai 620 765 765 KV BUS 1 AT INDORE PS 9:00 18:00 Continuous For equipment connection for new line bays of 765 KV POWERGRID WR-II C 18/Apr/19 20/Apr/19 Khandwa-Indore D/C line 621 400 400 kV Mansar - Bhachau Line 8:00 18:00 Daily Bay equipment conditioning monitoring work PGCIL GETCO 18/Apr/19 18/Apr/19 622 765 765 kV Vindhyachal- Sasan 2 Line with 765 kV Bus -I at V'chal 9:00 18:00 Daily For Isolator alaignment rectification work. POWERGRID WR-II R 18/Apr/19 19/Apr/19 623 400 MAIN BUS - 2 @ AKOLA 08:00 18:00 Daily Routine Maintenance & testing work MSETCL MSETCL NIL 18/Apr/19 18/Apr/19 624 400 400KV RAIPUR-WARDHA I 9:00 18:00 Daily For line AMP work & ckt-2 A/R in Non auto mode required for WRTS-I WRTS-I R 18/Apr/19 18/Apr/19 safety. 625 400 Busbar - I, 400/220 KV ICT#02, Bay 401, 402, 403 at Betul 10:00 10:00 Continuous 400 KV Online PDM system upgradation POWERGRID WR-II R 18/Apr/19 19/Apr/19 626 765 716 Bay (Main Bay of 765kV Satna Line) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 18/Apr/19 18/Apr/19 627 765 765kV Jabalpur-Bina ckt-1 at Bina, dia to be kept open at both 9:15 17:30 Daily Line AMP( for Attending the shut down nature defects in line.) POWERGRID WR-II R ends 18/Apr/19 19/Apr/19 628 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1 08:00 18:00 Daily Replacement of Polymer String MSETCL MSETCL NIL 18/Apr/19 18/Apr/19 629 400 400 kV Bus- 01 with Bus Coupler (400 kV Hadala SS) 8:00 18:00 Daily Bay maintenance work GETCO GETCO 18/Apr/19 18/Apr/19 630 400 400 KV PIRANA(TPL) –PGCIL(KAMOD) LINE 1 8:00 18:00 Daily CONNECTION TIGHTNESS WORK(WAVETRAP+CT) TPL TPL R 18/Apr/19 18/Apr/19 631 400 400 KV BUS.1 (PIRANA TPL) PIRANA (TPL S/S) 8:00 18:00 Daily BUS ISOLATOR ALIGNEMENT CHECKING WORK TPL TPL R 18/Apr/19 18/Apr/19 632 765 765kV GADARWARA-WARORA(PWTL)-I 8:00 18:00 Daily Line AMP works & Other ckt A/R in non auto mode required PWTL PWTL R 18/Apr/19 18/Apr/19 for safety. 633 220 KAPS-VAV Line # 1 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 18/Apr/19 18/Apr/19 634 765 765kV ,GT #3 Tie Bay No 800-8 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 18/Apr/19 18/Apr/19 635 765 707-Bay-Main Bay of 765 kV Tiroda Line 2 at Koradi-III 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL substation 18/Apr/19 18/Apr/19 636 220 220KV Malanpur-Auraiya 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 18/Apr/19 18/Apr/19 637 400 400kV ICT-2 Main bay (412) at Pune (Talegaon) 9:00 17:00 Daily For AMP works WRTS-I WRTS-I R 18/Apr/19 18/Apr/19 638 220 Bay No. 202 Main Bay of 220kv Boisar-Boisar-III Line at Boisar, 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R line will be in service through TBC 18/Apr/19 18/Apr/19 639 400 MAIN BUS - 2 @ 09:00 18:00 Daily Half yearly testing & maint. MSETCL MSETCL Total load will be 18/Apr/19 18/Apr/19 fed from 400kV 640 220 PUSAD - WARDHA (PG) 09:00 18:00 Daily For Routine Maintenance Work MSETCL MSETCL nil 18/Apr/19 18/Apr/19 641 400 421 Vindhyachal#3 Main Bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 18/Apr/19 18/Apr/19 642 765 765kV Warora-2 Main_710 at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 18/Apr/19 18/Apr/19 643 400 400kV SATPURA_MAIN_BAY_413 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 18/Apr/19 18/Apr/19 644 220 220kV Damoh#2 bay (206 Bay) at Damoh S/S, line will be in 9:00 18:00 Daily AMP work POWERGRID WR-II R service thorugh TBC 18/Apr/19 18/Apr/19 645 400 400kV TARAPUR-PADGHE 1 10:00 18:00 Daily For AMP Work at PADGHE (MSETCL) WRTS-I WRTS-I R 18/Apr/19 18/Apr/19 646 400 Itarsi-Jabalpur #2 Line at Itarsi 18:00 18:15 Daily For Taking Line Reactor Into Service after Completion of Over POWERGRID WR-II R 18/Apr/19 18/Apr/19 Hauling Works. 647 400 400 kV PGCIL(Dehgam) - Soja line (Auto relcose of WTPS - 8:00 18:00 Daily Maintenance work GETCO GETCO Dehgam will remain out) 18/Apr/19 18/Apr/19 648 400 NAGOTHANE - DABHOL 2 08:00 17:00 Daily Tree cutting work MSETCL MSETCL ... 18/Apr/19 19/Apr/19 649 400 DGEN 315 MVA ICT 2 - energization - Testing of both bus isolator 10:00 15:00 Continuous ICT 2 routine energisation testing during RSD and shutdown TPL - DGEN TPL - DGEN R operation before charging. Finally ICT-1 charge with bus 1 18/Apr/19 19/Apr/19 for energy conservation 650 765 Sipat-Bilaspur Line-2 Main Bay-13 at NTPC Sipat 8:00 18:00 Continuous PM (Sipat Bilaspur line - 2 will remain charged through its tie NTPC NTPC R 18/Apr/19 20/Apr/19 bay.) 651 400 80 MVAr BUS REACTOR - 1 @ BABHALESHWAR 08:00 18:00 Continuous Oil Filtration work MSETCL MSETCL 80MVAR Reactor - 18/Apr/19 20/Apr/19 2 are in service 652 400 315MVA Transformer-I at 400KV S/S Indore 9:00 18:00 Continue For OLTC , Conservator pending work by M/s BHEL MPPTCL MPPTCL R 18/Apr/19 20/Apr/19 653 400 409,Shujalpur-1 Main bay at Bina 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 18/Apr/19 20/Apr/19 654 400 400KV Korba-II Main bay at Bhilai ss 9:30 17:30 Continuous For R & Y phase CT replacement at Bhilai end WRTS-I WRTS-I R 18/Apr/19 23/Apr/19 655 400 400KV MAIN BUS-1 at 400KV S/s Bina 8:30 17:00 Continue S/D is required for 400 KV PG Isolators replacement works of MPPTCL MPPTCL R 18/Apr/19 27/Apr/19 X-mer - I, II & III and Bhopal - I & II. No any interruption 656 400 Anuppur – Jabalpur line# I ( Dia open at both end & A/R 8:00 18:00 Daily attending shut down nature defects preferably line spacers, POWERGRID WR2 R disablement of ckt # 2 also required.) 18/Apr/19 18/Apr/19 rigid spacers, missing jumper BN, missing tower parts/BN AWL 657 400 Mundra-Jetpur Ckt#2 with Non Auto mode of Ckt-1 (Dia to be 8:00 18:00 daily Testing & Commissioning of NIFPS Scheme at Jetpur and to POWERGRID WR-II kept open at both end) 19/Apr/19 19/Apr/19 attending hot spot & rectifying open line spacer dampers 658 400 417,Satna-2 & BPSCL Tie bay at Bina 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 19/Apr/19 21/Apr/19 659 400 765 KV ICT-2 Main Bay 407(400 KV Side) at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 19/Apr/19 19/Apr/19 660 400 Busbar - II, 400/220 KV ICT#01, 125 MVAR Bus Reactor, Bay 10:00 10:00 Continuous 400 KV Online PDM system upgradation POWERGRID WR-II R 404, 405, 406 at Betul 19/Apr/19 20/Apr/19 661 765 713 ( 765 KV Orai main bay) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 19/Apr/19 19/Apr/19 662 400 CHANDRAPUR 2-KUMBHARGAON(NANDED) CKT - 2 09:00 17:00 Daily Line maintenance work. MSETCL MSETCL - 19/Apr/19 19/Apr/19 663 400 400 kV Transfet Bus-Coupler (400 kV Hadala SS) 8:00 18:00 Daily Bay maintenance work GETCO GETCO 19/Apr/19 19/Apr/19 664 220 KAPS-VAV Line # 2 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 19/Apr/19 19/Apr/19 665 400 401 Main bay of ICT-1 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 19/Apr/19 19/Apr/19 666 220 BORIVALI - TARAPUR 09:00 17:00 Daily Routine Maintenance and REPLACEMENT OF DAMAGED MSETCL MSETCL - 19/Apr/19 19/Apr/19 EARTH-WIRE 667 220 220KV Mahegaon-Auraiya 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 19/Apr/19 19/Apr/19 668 400 315 MVA ICT #1 at Itarsi, dia to be kept open 9:00 18:00 Daily For testing and commissioning of Back up Impedence relay at POWERGRID WR-II C 19/Apr/19 19/Apr/19 Itarsi SS. 669 765 765kV Warora-2 & Future Tie bay_711 at New Parli 9:00 18:00 Daily Post Commissioning Wroks PPTL PPTL R 19/Apr/19 19/Apr/19 670 400 400kV Jetpur-2 line reactor at CGPL end 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R 19/Apr/19 20/Apr/19 671 400 Anuppur – Jabalpur line# II ( Dia open at both end & A/R 8:00 18:00 Daily attending shut down nature defects preferably line spacers, POWERGRID WR2 R disablement of ckt # 1 also required.) 19/Apr/19 19/Apr/19 rigid spacers, missing jumper BN, missing tower parts/BN AWL 672 765 765 KV Gwalior-Bina # 2 line(dia to be kept open) along with 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 765kV Bus-2 at Gwalior 20/Apr/19 20/Apr/19 Polymer insulator (String) in main and Tie bay along with 673 765 765KV Jabalpur-V'chal#1 Line alongwith associated Line Reactor 10:00 18:00 Daily For Fine tunning of CSD relay available for associated Line POWERGRID WR-II C at Pooling station,jabalpur, dia to be kept open. 20/Apr/19 20/Apr/19 Reactor through on Line switching 674 400 Bhachau-Ranchodpura ckt-2 with Bhachau-Ranchodpura ckt-1 8:00 18:00 daily For fixing of Bird Flight Diverter in the Earth Wire. POWER GRID WR-II in non auto reclose mode (Dia to be kept open at both ends) by 20/Apr/19 23/Apr/19 675 400 400 KV Warora-2 Tie Bay 408 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 20/Apr/19 20/Apr/19 676 400 Jabalpur-MB#2 Main Bay(419 bay) at Pooling station,jabalpur 10:00 18:00 Continuous For replacement of damaged YPH pole by new one POWERGRID WR-II R 20/Apr/19 21/Apr/19 677 765 765 kV Vindhyachal-Jabalpur 1 Line at V'chal, dia to be kept 9:00 18:00 Daily CSD commissioning (Make:-CGL) in 720 Tie bay of Jabalpur #1 POWERGRID WR-II C open 20/Apr/19 20/Apr/19 Line 678 400 400 KV NICOL.2(TPL) –PGCIL (DEHGAM) LINE 2 400 KV NICOL 2 8:00 18:00 Daily CONNECTION TIGHTNESS WORK(WAVETRAP+CT) TPL TPL R (TPL S/S) 20/Apr/19 20/Apr/19 679 765 765kV GADARWARA-WARORA(PWTL)-II 8:00 18:00 Daily Line AMP works & Other ckt A/R in non auto mode required PWTL PWTL R 20/Apr/19 20/Apr/19 for safety. 680 400 400KV Bhopal-Bina-II 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 20/Apr/19 20/Apr/19 681 220 Bay No. 203 Main Bay of 220kv Nalasopara-Boisar Line at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 20/Apr/19 20/Apr/19 682 400 405 Tie Bay of ICT and Future Bay at Akola-II substation 9:00 18:00 Daily Maintenance of Circuit Breaker MEGPTCL MEGPTCL 20/Apr/19 20/Apr/19 683 400 500 MVA ICT #2 at Itarsi 9:00 18:00 Daily For testing and commissioning of Back up Impedence relay at POWERGRID WR-II C 20/Apr/19 20/Apr/19 Itarsi SS. 684 400 404 Nigrie #2 Main Bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 20/Apr/19 20/Apr/19 685 400 765/400KV ICT-II 400KV SIDE _MAIN_BAY_419 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 20/Apr/19 20/Apr/19 686 765 BUS REACTOR_765kV_330MVAR_WARDHA 9:00 18:00 Daily For connection of newly 765 KV Auxilliary bus and 145v kv WRTS-I WRTS-I C 20/Apr/19 20/Apr/19 neutral bus of spare bus reactor to existing 765 kv auxilliary 687 220 220kV Damo-Sagar#1 bay (208 Bay) with terminal equipments at 9:00 18:00 Daily AMP work of Terminal Equipments POWERGRID WR-II R Damoh S/S. 20/Apr/19 20/Apr/19 688 400 400kV RAIPUR-BHADRAVATI III NON SWITCHABLE LINE 9:30 17:30 Daily Non switchable line Reactor AMP works. Line outage also WRTS-I WRTS-I R REACTOR AT RAIPUR 20/Apr/19 20/Apr/19 required for taking Reactor IN/OUT of service. 689 220 220KV BUS-I SHUTDOWN at KAPS-1&2 9:00 12:00 Continuous Yearly PM checks NPCIL KAPS-1 & 2 R 20/Apr/19 23/Apr/19 690 765 765 KV BUS 2 AT INDORE PS 9:00 18:00 Continuous For equipment connection for new line bays of 765 KV POWERGRID WR-II C 21/Apr/19 23/Apr/19 Khandwa-Indore D/C line 691 765 765 KV Gwalior-Bina # 1 line(dia to be kept open), along with 7:00 18:00 Daily Replacement of suspension and tension string (Porcelain) with POWERGRID WR-II C 765kV Bus-2 at Gwalior 21/Apr/19 21/Apr/19 Polymer insulator (String) in main and Tie bay along with 692 400 BUS - 1 @ NEW KOYNA 08:00 18:00 Daily Cold washing & Routine maint. Work MSETCL MSETCL Main Bus-II will 21/Apr/19 21/Apr/19 be in service 693 765/400 765/400 kV ICT #3 at Vindhyachal Pooling, dia to be kept open 9:00 18:00 Daily For AMP work POWERGRID WR-II R 21/Apr/19 21/Apr/19 694 400 PADGHE - KALWA 1 09:00 18:00 Daily Bay Maintenance & Testing work. MSETCL MSETCL - 21/Apr/19 21/Apr/19 695 400 Busbar-II, 400 KV Mauda - Betul Line ckt# 02 with Reactor, 400 10:00 10:00 Continuous 400 KV Online PDM system upgradation POWERGRID WR-II R KV Betul - Khnadwa Line ckt #01 with Reactor, Bay 407, 407R, 21/Apr/19 22/Apr/19 696 765 765 kV Sipat-3 Main bay 701 at Bilaspur PS 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 21/Apr/19 21/Apr/19 697 400 400 KV Warora-2 Main Bay 409 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 21/Apr/19 21/Apr/19 698 220 BOISAR II - PGCIL 1 09:00 17:00 Daily PRE MANSOON MAINTENANCE WORK MSETCL MSETCL - 21/Apr/19 21/Apr/19 699 220 KAPS-Haldarwa Line # 1 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 21/Apr/19 21/Apr/19 700 220 220kV Tikamgarh line bay (202 Bay) with terminal equipments at 9:00 18:00 Daily AMP work of Terminal Equipments POWERGRID WR-II R Damoh S/S. 21/Apr/19 21/Apr/19 701 400 413 Bay (Main Bay of 400 KV ICT # 3) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 21/Apr/19 21/Apr/19 702 765 765KV jabalpur-DJ#4 Line alongwith associated Line Reactor at 10:00 18:00 Daily AMP WORK POWERGRID WR-II R Pooling station,jabalpur 21/Apr/19 21/Apr/19 703 400 315MVA Transformer-IV at 400KV S/S Indore 9:00 18:00 Continue Replacement of 400 KV Line Isolator Under PSDF ICT- IV Will MPPTCL MPPTCL R 21/Apr/19 22/Apr/19 be Off 704 400 BABHALESHWAR - PADGHE 2 09:00 17:00 Daily PID testing work MSETCL MSETCL AR required in 21/Apr/19 30/Apr/19 non-auto mode 705 765 765KV Jabalpur-Orai#1 Line alongwith associated Line Reactor 10:00 18:00 Daily For Fine tunning of CSD relay available for associated Line POWERGRID WR-II C at Pooling station,jabalpur, dia to be kept open. 22/Apr/19 22/Apr/19 Reactor through on Line switching 706 400 BUS - 2 @ NEW KOYNA 08:00 18:00 Daily Cold washing & Routine maint. Work MSETCL MSETCL Main Bus-I will 22/Apr/19 22/Apr/19 be in service 707 765 765 kV Vindhyachal-Satna 2 Line swichable Reactor at 9:00 14:00 Daily For taking Spare Reactor with Satna #2 Reactor Y Ph POWERGRID WR-II R Vindhyachal Pooling 22/Apr/19 22/Apr/19 708 400 CHAKAN - TALEGAON(PG) 09:00 17:00 Daily Half yearly testing and maintenance activities MSETCL MSETCL - 22/Apr/19 22/Apr/19 709 400 Busbar-I, 400 KV Mauda - Betul Line ckt# 01 with Reactor, 400 10:00 10:00 Continuous 400 KV Online PDM system upgradation POWERGRID WR-II R KV Betul - Khnadwa Line ckt #02 with Reactor, Bay 410, 410R, 22/Apr/19 23/Apr/19 710 400 400 KV Raipur-2 Main Bay 412 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 22/Apr/19 22/Apr/19 711 765 765KV/400KV ICT-1 at Bina, dia on both sides to be kept open. 9:15 18:00 Daily For installation of back up impedance protection. POWERGRID WR-II R 22/Apr/19 22/Apr/19 Transformer and dia on both side i.e. 765 kV & 400 kV will be 712 400 400 KV ICT-II & BUS REACTOR TIE BAY_(428)KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 22/Apr/19 22/Apr/19 713 400 400 kV Amreli - Hadala Line (Auto reclose of Amreli - Jetpur - 2 7:00 13:00 Daily Silicon application work on tension location of line GETCO GETCO will remain out) 22/Apr/19 22/Apr/19 714 765 765kV 240MVAR Bus Reactor at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 22/Apr/19 22/Apr/19 715 220 220 kV Vapi- TAPS 8:00 18:00 Daily Maintenance Work GETCO GETCO 22/Apr/19 22/Apr/19 716 220 220 kV Navsari-Dastan line no.1 8:00 18:00 Daily Bay equipment maintenance work PGCIL GETCO 22/Apr/19 22/Apr/19 717 400 400 kV Chorania - Kosamba - 2 Line (Auto reclose of 400 KV 8:00 18:00 Daily Line maintenance work GETCO GETCO Chorania - Charal and 400 KV Charal - Kosamba will remain out) 22/Apr/19 22/Apr/19 718 220 KAPS-Haldarwa Line # 2 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 22/Apr/19 22/Apr/19 719 400 402 Tie bay of ICT-1 & Line-4 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 22/Apr/19 22/Apr/19 720 400 400KV Pune GIS # 1 & Pune-GIS-2 Tie bay (405) at Pune 9:00 17:00 Daily For AMP works WRTS-I WRTS-I R (Talegaon) 22/Apr/19 22/Apr/19 721 220 Bay No.204 Main Bus coupler at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 22/Apr/19 22/Apr/19 722 400 414 KAPP1 Kala1 Tie Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 22/Apr/19 22/Apr/19 723 765 ICT2_765/400kv_WARORA_PWTL 9:00 18:00 Daily For tertiary bus sleeve installation PWTL PWTL C 22/Apr/19 22/Apr/19 724 400 400KV BUS REACTOR-2_MAIN_BAY_433 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 22/Apr/19 22/Apr/19 725 765 765KV JHARSUGUDA 1 SWITCHABLE LR AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 22/Apr/19 22/Apr/19 726 220 220 KV Bus coupler Bay 201 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 22/Apr/19 22/Apr/19 727 400 400kV NTPC-1_Main Bay_421 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 22/Apr/19 22/Apr/19 728 419 400Kv GMR-1 Main bay 419 at Durg PS 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 22/Apr/19 22/Apr/19 729 220 220kV Damoh-Damoh line#1 bay (204 Bay) at Damoh S/S, line 9:00 18:00 Daily Bay AMP work POWERGRID WR-II R will be in service through TBC 22/Apr/19 22/Apr/19 730 220 TALANDAGE - CHIKODI 10:00 17:00 Daily Pre-monsoon Maintance i.e. Cold line insulator Cleaning MSETCL MSETCL - 22/Apr/19 22/Apr/19 731 765 715 LR Bay (765kV Bina#2 L/R Bay) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 22/Apr/19 22/Apr/19 732 400 Navsari Magarwada 1 at Navsari 10:00 18:00 Daily CVT Replacement at Navsari End POWERGRID WR-II R 22/Apr/19 22/Apr/19 733 400 400KV Shujalpur-Nagda ckt-I at Shujalpur (Line outage not 10:00 18:00 Daily On line Diode replacement in PLCC Chanel-I&II (during diode POWERGRID WR-II C required ,work will be done online) 22/Apr/19 22/Apr/19 repalcement one channel will be in service) 734 765 765KV Jabalpur-V'chal#1 Tie bay ( 826 Bay) at Pooling 10:45 11:30 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 22/Apr/19 22/Apr/19 735 400 DGEN Unit 52BAT 480MVA generator transformer energization 11:00 18:00 Continuous Unit 52 generator transformer routine energisation during RSD TPL - DGEN TPL - DGEN R 22/Apr/19 22/Apr/19 for healthiness checking 736 400 DGEN 53BAT 480MVA generator transformer De energization 11:00 18:00 continuous Unit 53 Generator transformer remains de-energized during TPL - DGEN TPL - DGEN R 22/Apr/19 22/Apr/19 RSD and shutdown for energy conservation 737 765 BAY 705 ( TIE BAY OF 765KV INDORE BINA LINE ) AT INDORE 0:00 0:00 DAILY FOR TESTING OF BAY CB (DCRM & TIMING ) AFTER RECENT POWERGRID WR-II R PS 22/Apr/19 22/Apr/19 TRIPPING/AUTO-RECLOSURE OF LINE 738 400 400kV 423 52 Tie breaker of Mundra Jetpur-1 line at CGPL end 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R 22/Apr/19 23/Apr/19 739 400 DHULE - SSNNL I & II (AR IN NON-AUTO MODE) 09:00 17:00 Daily PID testing of insulator strings MSETCL MSETCL 400kV SSNNL- 1 22/Apr/19 23/Apr/19 & 2 A/R switch 740 765 765kv Kotra-1 Tie Bay 719 at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 22/Apr/19 23/Apr/19 741 400 400kv kV Kolhapur ckt 2 & ICT 2 Tie Bay (408) at Mapusa 9:00 18:00 Cont. Replacement of existing VARM AR Relay with numerical Relay WRTS-I WRTS-I R 22/Apr/19 23/Apr/19 742 400 400 KV ICT3 & ESSAR1_TIE_BAY_408 at Bilaspur PS 9:00 18:00 Conti? For APM works. WRTS-I WRTS-I R 22/Apr/19 23/Apr/19 743 765 Sipat-Bilaspur Line-1 Main Bay-18 at NTPC Sipat 8:00 18:00 Continuous PM (Sipat Bilaspur line - 1 will remain charged through its tie NTPC NTPC R 22/Apr/19 24/Apr/19 bay.) 744 400 412,Shujalpur-2 Main bay at Bina 9:15 17:30 Continuous For CB drive over hauling. POWERGRID WR-II R 22/Apr/19 24/Apr/19 745 400 KALWA - TALEGAON (PGCIL) ALONGWITH KALWA - KHARGHAR 09:00 18:00 Daily PID Testing work of 400 KV Kalwa-Talegaon & 400KV Kalwa- MSETCL MSETCL Line will remain (AR IN NON-AUTO MODE) 22/Apr/19 25/Apr/19 Kharghar (D/C) line Insulator strings at various locations. Auto- in service 746 400 400KV AKOLA-BHUSAWAL (Bhusawal end) 08:00 18:00 Continuous Restringing of conductor of all three phases of 400 kV Akola- MSETCL MSETCL 400 kV Koradi- 22/Apr/19 26/Apr/19 Bhusawal line due to conversion of Metergauge to Broadgauge Bhusawal, 400 747 400 Jabalpur #4 Tie Bay (408) at Itarsi 9:00 18:00 Continuous For Over Hauling of Circuit Breaker POWERGRID WR-II R 22/Apr/19 29/Apr/19 748 400 80MVAR Reactor 2 at 400KV S/s Bhopal 8:00 18:00 Continue For attending oil leakage MPPTCL MPPTCL R 22/Apr/19 30/Apr/19 749 400 KV RANCHI-SIPAT-1 LINE AND ITS 80 MVAR LINE REACTOR 10:00 17:00 ODB AMP & Replacement of defective CAPTHOR in FSC AND To ERPC POWERGRID AT RANCHI 22/Apr/19 22/Apr/19 attend oil leakage in Line Reactor 750 765 765KV Jabalpur-Orai#2 Line alongwith associated Line Reactor 10:00 18:00 Daily For Fine tunning of CSD relay available for associated Line POWERGRID WR-II C at Pooling station,jabalpur, dia to be kept open. 23/Apr/19 23/Apr/19 Reactor through on Line switching 751 765/400 765/400 kV ICT #3 at Vindhyachal Pooling, dia to be kept open 9:00 18:00 Daily CSD commissioning (Make:-GE) in main bay of ICT-3 POWERGRID WR-II C 23/Apr/19 23/Apr/19 752 765 707 ( 765 KV Agra # 1 main bay) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 23/Apr/19 23/Apr/19 753 765 765kV , sasan-Satna line-2 Main Bay No 800-9 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 23/Apr/19 23/Apr/19 754 400 400 KV Raipur-2 Tie Bay 411 at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 23/Apr/19 23/Apr/19 755 400 KHARGHAR - TALEGAON (PG) 08:00 18:00 Daily Routine Maintenance MSETCL MSETCL - 23/Apr/19 23/Apr/19 756 400 400 KV BUS REACTOR MAIN BAY_(427)_KOTRA PS 6:00 18:00 Daily For AMP works. WRTS-1 WRTS-1 R 23/Apr/19 23/Apr/19 757 400 400 kV Amreli - Hadala Line (Auto reclose of Amreli - Jetpur - 2 7:00 13:00 Daily Silicon application work on tension location of line GETCO GETCO will remain out) 23/Apr/19 23/Apr/19 758 220 OSMANABAD - PARLY (PG) 08:00 16:00 Daily LINE maintenance MSETCL MSETCL - 23/Apr/19 23/Apr/19 759 400 400 KV Khedamara-Raita-III Line at 400 KV S/s Khedamara as 8:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R well as at 400 KV S/s Raita end. 23/Apr/19 23/Apr/19 760 400 CHANDRAPUR 2 - WARORA CKT-2 08:00 17:00 Daily Tightening of conductor ,Earthwire Hardware. MSETCL MSETCL Tightening of 23/Apr/19 23/Apr/19 conductor 761 220 220 kV Bhilad- TAPS 8:00 18:00 Daily Maintenance Work GETCO GETCO 23/Apr/19 23/Apr/19 762 220 220 kV Navsari - Dastan line no. 2 8:00 18:00 Daily General bay maintenance work PGCIL GETCO 23/Apr/19 23/Apr/19 763 400 400 kV Charal - Kosamba Line (Auto reclose of Chorania - 8:00 18:00 Daily Line maintenance work GETCO GETCO Kosamba - 2 & Chorania - Charal line will remain out) 23/Apr/19 23/Apr/19 764 400 403 Main bay of 400 kV Future Line 4 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 23/Apr/19 23/Apr/19 765 400 400kV ICT-3 Main bay (418) at Pune (Talegaon) 9:00 17:00 Daily For AMP works WRTS-I WRTS-I R 23/Apr/19 23/Apr/19 766 220 Bay No.205 Transfer Bus at Boisar 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R 23/Apr/19 23/Apr/19 767 400 400 kV Kosamba Ukai-1 MAIN+TIE BAY at Kosamba 9:00 18:00 Daily Second six monthly maintenance GETCO GETCO 23/Apr/19 23/Apr/19 768 400 400KV Seoni-Sarni 9:00 18:00 Daily For line maintenance work MPPTCL NHDC R 23/Apr/19 23/Apr/19 769 220 203 Bay, Satna#1 Line Main Bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 23/Apr/19 23/Apr/19 770 400 765/400KV ICT 3 & FUTURE_TIE_BAY_429 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 23/Apr/19 23/Apr/19 771 765 765KV JHARSUGUDA 2 SWITCHABLE LR AT 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R DHARAMJAYGARH(KORBA) SS 23/Apr/19 23/Apr/19 772 220 ICT1_400/220kv_WARDHA 9:00 18:00 Daily For AMP work WRTS-I WRTS-I R 23/Apr/19 23/Apr/19 773 400 400KV Raigarh-I Tie bay (406) at Raipur 9:30 17:30 Daily For AMP works. WRTS-I WRTS-I R 23/Apr/19 23/Apr/19 774 765 1500MVA ICT # 1 Main bay(703) at Vadodara 10:00 17:00 Daily For CB AMP work, ICT will remain charge through Tie Bay POWERGRID WR-II R 23/Apr/19 23/Apr/19 775 400 400KV Shujalpur-Nagda ckt-II at Shujalpur (Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I&II (during diode POWERGRID WR-II C required ,work will be done online) 23/Apr/19 23/Apr/19 repalcement one channel will be in service) 776 765 765KV Jabalpur-Orai#2 Main bay ( 834 Bay) at Pooling 11:00 11:45 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 23/Apr/19 23/Apr/19 777 765 765KV Jabalpur-Orai#2 Tie bay ( 835 Bay) at Pooling 12:00 12:45 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 23/Apr/19 23/Apr/19 778 765 765KV/400KV ICT-2 at Bina, dia on both sides to be kept open 9:15 17:30 Daily For installation of back up impedance protection. POWERGRID WR-II R 23/Apr/19 23/Apr/19 Transformer and dia. on both side i.e. 765 kV & 400 kV will be 779 400 400 kV Kasor - Chorania line (Auto reclose of Asoj - Chorania line 7:00 17:00 Daily Line maintenance work GETCO GETCO No. 1 will remain out) 23/Apr/19 24/Apr/19 780 400 VSTPS - HVDC Line# 1 (Stage-I, BAY No. 2) at VSTPS end. 8:00 18:00 Continuous Annual Bay Maintenance WRTS-2 NTPC R Being DMT scheme, line outage is required for complete bay 23/Apr/19 24/Apr/19 781 400 315MVA Transformer -III at 400KV S/S Indore 9:00 18:00 Continue Replacement of 400 KV Line Isolator & 220 KV Auxiliary MPPTCL MPPTCL R 23/Apr/19 24/Apr/19 Isolator under PSDF ICT -III will be Off 782 400 DGEN 315 MVA ICT 3 - energization - Testing of both bus isolator 10:00 15:00 Continuous ICT 3 routine energisation testing during RSD and shutdown TPL - DGEN TPL - DGEN R operation before charging. Finally ICT-1 charge with bus 1 23/Apr/19 24/Apr/19 for energy conservation 783 220 220KV BUS-II SHUTDOWN at KAPS 14:00 20:00 Continuous Yearly PM checks NPCIL KAPS-1 & 2 R 23/Apr/19 26/Apr/19 784 765 kV New Ranchi - Dharamjaygarh CKT-II 9:00 18:00 ODB for replacement of broken Glass insulators damaged by ERPC POWERGRID 23/Apr/19 27/Apr/19 miscreants about 140 nos. locations 785 765 765kV Bina-Indore Line at Bina, dia to be kept open at both ends 9:15 17:30 Daily Line AMP (for Attending the shut down nature defects in line.) POWERGRID WR-II R 24/Apr/19 24/Apr/19 786 765 765KV Jabalpur-V'chal#2 Line alongwith associated Line Reactor 10:00 18:00 Daily For Fine tunning of CSD relay available for associated Line POWERGRID WR-II C at Pooling station,jabalpur, dia to be kept open. 24/Apr/19 24/Apr/19 Reactor through on Line switching 787 765 765 kV Vindhyachal-Jabalpur 2 Line at Vindhyachal Pooling, dia 9:00 14:00 Daily For taking Spare Reactor with Jabalpur #2 Line Reactor Y Ph POWERGRID WR-II R to be kept open. 24/Apr/19 24/Apr/19 788 765 765 KV INDORE BINA LINE, dia to be kept open 9:00 18:00 DAILY FOR COMMISSIONING OF TRAVELLING WAVE FAULT POWERGRID WR-II C 24/Apr/19 24/Apr/19 LOCATOR AND FOR INSTALLATION OF ADDITIONAL BPI TO 789 400 Bhachau-Ranchodpura ckt-1 with Bhachau-Ranchodpura ckt-2 8:00 18:00 daily For fixing of Bird Flight Diverter in the Earth Wire. POWER GRID WR-II in non auto reclose mode (Dia to be kept open at both ends) by 24/Apr/19 27/Apr/19 790 765 765KV jabalpur-DJ#3 Line alongwith associated Line Reactor at 10:00 18:00 Daily AMP WORK POWERGRID WR-II R Pooling station,jabalpur 24/Apr/19 24/Apr/19 791 400 400kV KORBA-MAHAN 8:00 18:30 Daily Replacement of broken insulators. Other ckt A/R to be in Non WRTS-I WRTS-I R 24/Apr/19 25/Apr/19 auto mode required. 792 765 765kV ,GT #4 Bay No 800-10 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 24/Apr/19 24/Apr/19 793 765 702 Bay (Tie bay of Jaipur # 2 and Bus reactor ) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 24/Apr/19 24/Apr/19 794 400 Bhachau-Essar ckt-1 with Bhachau-Essar ckt-2 in non auto 8:00 18:00 daily For fixing of Bird Flight Diverter in the Earth Wire. POWER GRID WR-II reclose mode (Dia to be kept open at both ends) 24/Apr/19 30/Apr/19 795 400 400 kV Amreli - Hadala Line (Auto reclose of Amreli - Jetpur - 2 7:00 13:00 Daily Silicon application work on tension location of line GETCO GETCO will remain out) 24/Apr/19 24/Apr/19 796 400 400/220 kV, 315MVA ICT-2 Mansar 8:00 18:00 Daily 89-B Isolator maintenance of LV bay GETCO GETCO 24/Apr/19 24/Apr/19 797 400 CHANDRAPUR 2 - WARORA CKT-1 08:00 17:00 Daily Tightening of conductor ,Earthwire Hardware. MSETCL MSETCL Tightening of 24/Apr/19 24/Apr/19 conductor 798 220 220 kV Vapi- Vapi (PG) 8:00 18:00 Daily Maintenance Work GETCO GETCO 24/Apr/19 24/Apr/19 799 220 220 kV Navsari-Nashik line no.1 8:00 18:00 Daily General bay maintenance work GETCO GETCO 24/Apr/19 24/Apr/19 800 400 400 KV PIRANA (TPL) –PGCIL(KAMOD) LINE 2 8:00 18:00 Daily CONNECTION TIGHTNESS WORK(WAVETRAP+CT)+ISOLATOR TPL TPL R 24/Apr/19 24/Apr/19 PROBLEM ATTEDING WORK 801 220 KAPS-Haldarwa Line # 1 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 24/Apr/19 24/Apr/19 802 400 400 KV BUS.2 & ICT.3 (PIRANA TPL) 8:30 18:00 Daily CONNECTION TIGHTNESS WORK+ISOLATOR PROBLEM TPL TPL R 24/Apr/19 24/Apr/19 ATTEDING WORK 803 400 404 Main bay of ICT-2 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 24/Apr/19 24/Apr/19 804 220 220KV Malanpur-Adani 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 24/Apr/19 24/Apr/19 805 220 220kV Talegaon (MSETCL)-1 Main bay (202) at Pune (Talegaon) 9:00 17:00 Daily For AMP works WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 806 220 Bay No. 206 Main Bay of 220kv Boisar-Boisar-I Line at Boisar, 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R line will be in service thorugh TBC 24/Apr/19 24/Apr/19 807 400 400KV Khandwa-Seoni Ckt-1, A/R OFF of Circuit-2 & dia to be 9:00 18:00 Daily For Spacer/VD problem rectification work, Ckt-2 A/R to be POWERGRID WR-II R kept open 24/Apr/19 24/Apr/19 kept in Non Auto Mode. 808 400 416 KAPP2 KALA2 TIE bAY at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 24/Apr/19 24/Apr/19 809 765 BUS REACTOR_765kV_330MVAR_WARORA _PWTL 9:00 18:00 Daily Warantee period testing & to take spare in service. PWTL PWTL R 24/Apr/19 24/Apr/19 810 400 400kV ICT2-KHANDWA1_TIE_BAY_420 at Seoni 9:00 18:00 Daily For AMP works. WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 811 765 SWITCHABLE LR_765kV_A'BAD 4_WARDHA 9:00 18:00 Daily For AMP work WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 812 400 400kV NTPC-2_Main Bay_424 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 813 400 400Kv GMR-1 Line bay 419-89L at Durg PS 9:00 18:00 Daily For Line outage required for line side equipment AMP works. WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 814 400 AC Filter Bank 1 & 2 Tie bay (458) at Champa-HVDC 9:00 18:00 Daily For AMP Works, Power regulation not required. WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 815 400 400kv Raigarh-I Main bay (405) at Raipur ss 9:30 17:30 Daily For AMP works at Raipur SS WRTS-I WRTS-I R 24/Apr/19 24/Apr/19 816 400 MAIN BUS - 2 @ ALKUD 10:00 17:30 Daily Quarterly Maint. Work MSETCL MSETCL Load will be 24/Apr/19 24/Apr/19 managed on Bus 817 400 400KV Shujalpur-RAPP ckt-I at Shujalpur (Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I&II (during diode POWERGRID WR-II C required ,work will be done online) 24/Apr/19 24/Apr/19 repalcement one channel will be in service) 818 220 SOUTH SOLAPUR (KUMBHARI)-PGCIL 2 11:00 16:00 Daily QM Work MSETCL MSETCL Load can be 24/Apr/19 24/Apr/19 managed on 819 400 400 kV Wanakbori - Soja line 8:00 18:00 Daily Maintenance work GETCO GETCO 24/Apr/19 24/Apr/19 820 765 765/400kV ICT-1 at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 24/Apr/19 25/Apr/19 821 765 765kv ICT-5 Main Bay 720 at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 24/Apr/19 25/Apr/19 822 400 400 kV MCCPL Tie bay 417 at Bilaspur PS 9:00 18:00 Conti? For APM works. WRTS-I WRTS-I R 24/Apr/19 25/Apr/19 823 400 80 MVAr BUS REACTOR - 2 @ BABHALESHWAR 08:00 18:00 Continuous Oil Filtration work MSETCL MSETCL 80MVAR Reactor - 24/Apr/19 26/Apr/19 1 are in service 824 765 765KV Vadodara-Indore Line by Vadodara, dia to be kept open at 9:00 18:00 Daily For replacement work of damaged earthwire. POWERGRID WR-II R both ends 25/Apr/19 25/Apr/19 825 400 400kV Indore-Asoj-1 at Indore MP 9:00 9:30 Daily To take L/R out of service for AMP Works POWERGRID WR-II R 25/Apr/19 25/Apr/19 826 400 400kV Indore-Asoj-1 at Indore MP 17:30 18:00 Daily To take L/R into service after AMP Works POWERGRID WR-II R 25/Apr/19 25/Apr/19 827 400 400 KV INDORE-ASOJ # 1 LINE REACTOR AT INDORE MPPTCL 8:00 18:00 DAILY FOR AMP OF LINE REACTOR POWERGRID WR-II R by Indore S/s 25/Apr/19 25/Apr/19 828 765 765 kV Satna-Gwalior line at Satna, dia to be kept open at both 9:00 18:00 Daily Installation of BPI in Phase where Wave Trap is not available POWERGRID WR-II C ends. 25/Apr/19 25/Apr/19 829 765 765KV Jabalpur-V'chal#1 Main bay ( 827 Bay) at Pooling 8:00 8:30 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 25/Apr/19 25/Apr/19 830 765 765KV Jabalpur-V'chal#2 Main bay ( 830 Bay) at Pooling 11:45 12:30 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 25/Apr/19 25/Apr/19 831 765 765KV Jabalpur-V'chal#2 Tie bay ( 829 Bay) at Pooling 13:30 14:15 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 25/Apr/19 25/Apr/19 832 765 765KV Jabalpur-Orai#1 Main bay ( 831 Bay) at Pooling 15:00 15:45 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 25/Apr/19 25/Apr/19 833 765 765KV Jabalpur-Orai#1 Tie bay ( 832 Bay) at Pooling 16:00 16:45 Daily For taking the oil sample from Bay CT POWERGRID WR-II R station,jabalpur 25/Apr/19 25/Apr/19 834 400 400 kV Chorania-Asoj - 1 Line (Auto reclose of Kasor -Chorania 8:00 18:00 Daily Line maintenance work GETCO GETCO will remain out) 25/Apr/19 25/Apr/19 835 400 400 kv Bus Reactor Tie Bay(417) at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 25/Apr/19 25/Apr/19 836 765 Vadodara-Indore Line Main bay(704) at Vadodara 10:00 17:00 Daily For CB AMP work, Line will remain charge through Tie Bay POWERGRID WR-II R 25/Apr/19 25/Apr/19 837 400 400kv 405 Tie bay of KWPCL -2 at PGCIL new kotra pooling 6:00 18:00 Daily For AMP work of 405 KWPCL-2 tie bay at PGCIL new kotra PGCIL KWPCL R station 25/Apr/19 25/Apr/19 pooling station 838 400 400 kV Amreli - Hadala Line (Auto reclose of Amreli - Jetpur - 2 7:00 13:00 Daily Silicon application work on tension location of line GETCO GETCO will remain out) 25/Apr/19 25/Apr/19 839 220 220 kV Charadav Bhimasar -1 8:00 18:00 Daily Routine Maintenance work GETCO GETCO 25/Apr/19 25/Apr/19 840 765 765kV ,GT #4 Tie Bay No 800-11 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 25/Apr/19 25/Apr/19 841 400 400 KV Khedamara-Raita-II Line at 400 KV S/s Khedamara as 8:00 17:00 Daily Annual Maintenance Programme. CSPTCL CSPTCL R well as at 400 KV S/s Raita end. 25/Apr/19 25/Apr/19 842 220 220 kV Bhilad- Vapi (PG) - 1 8:00 18:00 Daily Maintenance Work GETCO GETCO 25/Apr/19 25/Apr/19 843 220 220 kV Navsari-Nashik line no.2 8:00 18:00 Daily Maintenance work GETCO GETCO 25/Apr/19 25/Apr/19 844 400 400 kV Chorania-Asoj - 1 Line (Auto reclose of Kasor -Chorania 8:00 18:00 Daily For Line maintenance work. GETCO GETCO will remain out) 25/Apr/19 25/Apr/19 845 400 LONIKAND2-LONIKAND1 (INTERCONNECTOR 1) 08:00 18:00 Daily Half yearly maintenance and diagnostic testing work MSETCL MSETCL The work will be 25/Apr/19 25/Apr/19 carried by tech 846 220 Bhachau-lalpar Line at Bhachau 8:00 18:00 daily Line outage required for Installation of ABT meter at both ends POWERGRID WR-II 25/Apr/19 25/Apr/19 847 220 KAPS-Haldarwa Line # 2 8:00 20:00 Daily Yearly PM checks of Bay Equipments NPCIL KAPS-1 & 2 R 25/Apr/19 25/Apr/19 848 400 405 Tie bay of ICT-2 & Line-3 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 25/Apr/19 25/Apr/19 849 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1 09:00 17:00 Daily LINE maintenance MSETCL MSETCL - 25/Apr/19 25/Apr/19 850 220 Bay No. 207 Main Bay of 220kv Tarapur-Boisar Line at Boisar, 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R line will be in service through TBC 25/Apr/19 25/Apr/19 851 400 400KV Khandwa-Seoni Ckt-2, A/R OFF of Circuit-1 & dia to be 9:00 18:00 Daily For Spacer/VD problem rectification work, Ckt-1 A/R to be POWERGRID WR-II R kept open 25/Apr/19 25/Apr/19 kept in Non Auto Mode. 852 220 204 Bay, 400/220kV ICT#1 Main Bay at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 25/Apr/19 25/Apr/19 853 400 400 kv Bus Reactor Main Bay(418) at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I 25/Apr/19 25/Apr/19 854 765 Vadodara-Indore Line Tie bay(705) at Vadodara 10:00 17:00 Daily For CB AMP work, Line will remain charge through Main Bay POWERGRID WR-II R 25/Apr/19 25/Apr/19 855 220 PUSAD - WARDHA (PG) 10:00 17:00 Daily For Routine Maintenance Work MSETCL MSETCL nil 25/Apr/19 25/Apr/19 856 400 MAIN BUS - 1 @ EKTUNI 10:00 18:00 Daily Diagnostic Testing & Routine Maintainence MSETCL MSETCL 400kV Main Bus- 25/Apr/19 25/Apr/19 II will be in 857 400 404 ( Main Bay of Bus reactor # 1 ) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 25/Apr/19 25/Apr/19 858 220 220 KV BUS Coupler at Navsari 10:00 18:00 Daily 220KV Bus coupler AMP at Navsari POWERGRID WR-II R 25/Apr/19 25/Apr/19 859 400 400KV Shujalpur-RAPP ckt-II at Shujalpur.(Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I&II (during diode POWERGRID WR-II C required ,work will be done online) 25/Apr/19 25/Apr/19 repalcement one channel will be in service) 860 400 400 kV Wanakbori - Soja line 8:00 18:00 Daily Maintenance work GETCO GETCO 25/Apr/19 25/Apr/19 861 765 765kV Bus Reactor-2 (Switchable reactor) at Bina 9:15 17:30 Daily For AMP work. POWERGRID WR-II R 25/Apr/19 25/Apr/19 862 400 NEW KOYNA - DABHOL - I 08:00 18:00 Daily Cold washing & string replacement of insulator strings MSETCL MSETCL Load can be 25/Apr/19 26/Apr/19 managed on 863 400 ICT-1 Tie To IBT-1 Bay-14 at NTPC Sipat 8:00 18:00 Continuous PM (Both ICT-1 and IBT-1 Transformer will remain charged NTPC NTPC R 25/Apr/19 26/Apr/19 through there Main Bays) 864 400 400kV 416 52 Main breaker of Mundra Bhachau-3 line at CGPL 8:00 20:00 Daily Breaker testing and PM CGPL CGPL R end 25/Apr/19 26/Apr/19 865 400 400 kV Kosamba Charal line 9:00 18:00 Daily Bay equipment maintenance work at Kosamba end GETCO GETCO 25/Apr/19 26/Apr/19 866 400 315MVA Transformer -I at 400KV S/S Indore 9:00 18:00 Continue X-MER Maintenance work and replacement of 400 KV Line MPPTCL MPPTCL R 25/Apr/19 26/Apr/19 Isolator & 220 KV Auxiliary Isolator under PSDF ICT -I will be 867 400 400 kV Kolhapur Ckt 2 Main Bay (407) at Mapusa 9:00 18:00 Cont. Replacement of existing VARM AR Relay with numerical Relay WRTS-I WRTS-I R 25/Apr/19 26/Apr/19 868 400 765kV BUS_REACTOR & ICT2_TIE_BAY_714 at Seoni 9:00 18:00 Conti? For AMP works. WRTS-I WRTS-I R 25/Apr/19 26/Apr/19 869 400 400 KV Jhanor Bus-2 8:00 18:00 CONTINOUS ANNUAL MAINTENANCE(checking and cleaning of BPI, clamp NTPC NTPC R 25/Apr/19 27/Apr/19 tightness checking/replacement if any) 870 220 TAPS1&2 -Borivali 8:00 19:00 Daily Basis Annual maintenance Works MSETCL NPCIL R 25/Apr/19 27/Apr/19 871 765 765kV Main Bus -1 at Bhopal BDTCL 8:00 19:00 Daily AMP works BDTCL BDTCL R 26/Apr/19 26/Apr/19 872 765 765 kV Vindhyachal-Sasan 1 Line at V'chal, dia to be kept open 9:00 18:00 Daily T point Isolators connection of ankaring bolt POWERGRID WR-II R at both ends 26/Apr/19 26/Apr/19 873 765 Vadodara-Dhule Line Tie bay(702) at Vadodara 10:00 17:00 Daily For CB AMP work, Line will remain charge through Main Bay POWERGRID WR-II R 26/Apr/19 26/Apr/19 874 400 400kV BHATAPARA-KORBA 9:00 18:00 Continous Retrofitting of Autoreclose relay at Korba end & Line AMP WRTS-I NTPC R 26/Apr/19 27/Apr/19 works. 875 400 408 Boisar Tie Bay at Vapi 9:00 18:00 Daily Terminal Tightness Work POWERGRID WR-II R 26/Apr/19 26/Apr/19 876 400 400 kV Amreli - Hadala Line (Auto reclose of Amreli - Jetpur - 2 7:00 13:00 Daily Silicon application work on tension location of line GETCO GETCO will remain out) 26/Apr/19 26/Apr/19 877 220 220 kV Charadav Bhimasar -2 8:00 18:00 Daily Routine Maintenance work GETCO GETCO 26/Apr/19 26/Apr/19 878 220 220 kV Bhilad- Vapi (PG) - 2 8:00 18:00 Daily Maintenance Work GETCO GETCO 26/Apr/19 26/Apr/19 879 400 400 kV Chorania-Asoj-2 Line (Auto reclose of Chorania -Amreli 8:00 18:00 Daily Line maintenance work GETCO GETCO will remain out) 26/Apr/19 26/Apr/19 880 400 KHARGHAR - TALEGAON (PG) 08:00 18:00 Daily Routine Maintenance & Diagnostic testing work MSETCL MSETCL Nil 26/Apr/19 26/Apr/19 881 400 PADGHA - BOISAR (PG) 08:00 18:00 Daily DIAGNOSTIC TESTING WORK POWERGRID MSETCL ISOLATOR 26/Apr/19 26/Apr/19 MAINT WORK 882 400 DHULE - SSNNL I Alogwith A/R switch to be kept on non-auto 08:00 18:00 Daily Replacement of faulty insulator strings found in PID MSETCL MSETCL 400kV SSNNL- 2 mode of Dhule - SSNNL- ckt 2 26/Apr/19 26/Apr/19 A/R switch to be 883 220 Bhachau-Charvada#2 Line at Bhachau 8:00 18:00 daily Line outage required for Installation of ABT meter at both ends POWERGRID WR-II 26/Apr/19 26/Apr/19 884 400 400kv 408 Tie bay of KWPCL - 1 at PGCIL new kotra pooling 9:00 12:00 Daily For AMP work of 408 KWPCL-1 tie bay at PGCIL new kotra PGCIL KWPCL R station 26/Apr/19 26/Apr/19 pooling station 885 400 408 Tie bay of 400 kV Koradi-II Line-2 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 26/Apr/19 26/Apr/19 886 220 220KV Mahgaon-Adani 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 26/Apr/19 26/Apr/19 887 220 Bay No. 208 Main Bay of ICT-II at Boisar, ICT-II will be in service 9:00 17:30 Daily For Bay AMP POWER GRID WR-II R through TBC 26/Apr/19 26/Apr/19 888 400 400KV Khandwa - Betul Ckt-1, A/R OFF of Circuit-2 & dia to be 9:00 18:00 Daily For Spacer/VD problem rectification work, Ckt-2 A/R to be POWERGRID WR-II R kept open 26/Apr/19 26/Apr/19 kept in Non Auto Mode. 889 765 SWITCHABLE_LR_765kV_PARLI1_ WARORA_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 26/Apr/19 26/Apr/19 890 765 ICT1_765/400kv_D'JAIGARH 9:00 18:00 Daily For Installation & Commissioning of Back-up Impedance Relay. WRTS-1 WRTS-1 C 26/Apr/19 26/Apr/19 891 765 BUS REACTOR_765kV_240MVAR_WARDHA 9:00 18:00 Daily For AMP work WRTS-I WRTS-I R 26/Apr/19 26/Apr/19 892 400 400kV KOLHAPUR Main bay_418 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 26/Apr/19 26/Apr/19 893 400 400KV Raigarh-II Main bay(404) at Raipur ss 9:30 17:30 Daily For AMP works WRTS-I WRTS-I R 26/Apr/19 26/Apr/19 894 765 1500MVA ICT # 2 Main bay (706) at Vadodara 10:00 17:00 Daily For CB AMP work, ICT will remain charge through Tie Bay POWERGRID WR-II R 26/Apr/19 26/Apr/19 895 220 220KV Annupur-Kotmikala-I 10:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 26/Apr/19 26/Apr/19 896 220 220V Shujalpur-Shujalpur ckt-I at Shujalpur. (Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I. POWERGRID WR-II C required ,work will be done online) 26/Apr/19 26/Apr/19 897 220 210 Bay (220kV Sithouli#2 Bay) at Gwalior, line will be in service 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R through TBC 26/Apr/19 26/Apr/19 898 400 400kv 406 Main bay of KWPCL - 2 at PGCIL new kotra pooling 11:30 14:00:00 PM Daily For AMP work of 406 KWPCL-2 main bay at PGCIL new kotra PGCIL KWPCL R station 26/Apr/19 26/Apr/19 pooling station 899 400 400 kV Wanakbori - Soja line 8:00 18:00 Daily Maintenance work GETCO GETCO 26/Apr/19 26/Apr/19 900 400 BAY 407 ( TBC ) AT MPPTCL at Indore 0:00 0:00 DAILY BAY AMP WORKS POWERGRID WR-II R 26/Apr/19 26/Apr/19 901 765 765kkV Gwalior-Bina ckt-1 at Bina, dia to be kept open at both 9:15 17:30 Daily Line AMP (for Attending the shut down nature defects in line.) POWERGRID WR-II R ends 26/Apr/19 26/Apr/19 902 765 765/400kV ICT-2 at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 26/Apr/19 27/Apr/19 903 400 KALWA - TALEGAON (PGCIL) ALONGWITH KALWA - KHARGHAR 09:00 18:00 Daily PID Testing work of 400 KV Kalwa-Talegaon & 400KV MSETCL MSETCL - (AR IN NON-AUTO MODE) 26/Apr/19 30/Apr/19 Kharghar-Talegaon (D/C) line Insulator strings at various 904 400 MAIN BUS - 2 @ CHANDRAPUR 09:00 18:00 Continuous 1) For replacement of old damaged quadraple bus conductor of MSETCL MSETCL During outage, 27/Apr/19 28/Apr/19 Main Bus-II in HVDC- I & II bay section span. 2) For all connected 905 765 765 kV Vindhyachal-Satna #1 Line at V'chal, dia to be kept open 9:00 18:00 Daily T point Isolators connection of ankaring bolt POWERGRID WR-II R at both ends 27/Apr/19 27/Apr/19 906 765 765 kV Satna- Vindhyachal#1 at Satna, dia to be kept open 9:00 18:00 Daily Installation of BPI in Phase where Wave Trap is not available POWERGRID WR-II C 27/Apr/19 27/Apr/19 907 400 400 kV Asoj - Wanakbori 7:00 18:00 Daily Line maintenance work GETCO GETCO 27/Apr/19 27/Apr/19 908 400 400 kV Transfer Bus Kansari 8:00 18:00 Daily Busbar maintenance work GETCO GETCO 27/Apr/19 27/Apr/19 909 400 400 kV Chorania-Asoj-2 Line (Auto reclose of Chorania -Amreli 8:00 18:00 Daily Line maintenance work GETCO GETCO will remain out) 27/Apr/19 27/Apr/19 910 220 220 kV Bhilad- Vapi (PG) - 3 8:00 18:00 Daily Maintenance Work GETCO GETCO 27/Apr/19 27/Apr/19 911 400 DHULE - SSNNL II Alogwith A/R switch to be kept on non-auto 08:00 18:00 Daily Replacement of faulty insulator strings found in PID MSETCL MSETCL 400kV SSNNL- 1 mode of Dhule - SSNNL- ckt 1 27/Apr/19 27/Apr/19 A/R switch to be 912 400 400 KV SUGEN VAPI Line 8:00 18:00 Daily For Porcelain Insulator string replacement of Tension Towers TPGL TPGL R 27/Apr/19 27/Apr/19 913 220 Bhachau-Charvada#1 Line at Bhachau 8:00 18:00 daily Line outage required for Installation of ABT meter at both ends POWERGRID WR-II 27/Apr/19 27/Apr/19 914 400 400kV Satna- Vindhyachal#1 at Satna 9:00 9:30 Daily To isolate L/R at Satna for AMP Works POWERGRID WR-II R 27/Apr/19 27/Apr/19 915 400 400Kv Boisar-Padghe line at Boisar 9:00 14:00 Daily code for Online Main-I relay replacement & For tripping and POWER GRID WR-II R 27/Apr/19 27/Apr/19 A/R Trials of Main-I relay (Line will be out of service) 916 400 409 Main bay of 400 kV Koradi-II Line 2 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 27/Apr/19 27/Apr/19 917 220 BOISAR II - PGCIL 3 09:00 17:00 Daily FIXING OF REPAIR SLEEVE AND OTHER MAINTENANCE MSETCL MSETCL - 27/Apr/19 27/Apr/19 WORK 918 220 201 Bay( 400kV ICT-1 Main bay (201) at 220KV side at Pune 9:00 17:00 Daily For AMP works WRTS-I WRTS-I R (Talegaon) 27/Apr/19 27/Apr/19 919 400 765kv ICT-1 Main Bay 400kv side -419 at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 27/Apr/19 27/Apr/19 920 400 400KV Khandwa - Betul Ckt-2, A/R OFF of Circuit-1 & dia to be 9:00 18:00 Daily For Spacer/VD problem rectification work, Ckt-1 A/R to be POWERGRID WR-II R kept open 27/Apr/19 27/Apr/19 kept in Non Auto Mode. 921 400 400kV Satna- Vindhyachal#1 Line Reactor at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 27/Apr/19 27/Apr/19 922 765 ICT2_765/400kv_D'JAIGARH 9:00 18:00 Daily For Installation & Commissioning of Back-up Impedance Relay. WRTS-1 WRTS-1 C 27/Apr/19 27/Apr/19 923 765 SWITCHABLE LR_765kV_A'BAD 2_WARDHA 9:00 18:00 Daily For AMP work WRTS-I WRTS-I R 27/Apr/19 27/Apr/19 924 765 765kV Gwalior-Bina ckt-2 at Bina, dia to be kept open at both 9:15 17:30 Daily Line AMP (for Attending the shut down nature defects in line.) POWERGRID WR-II R ends 27/Apr/19 27/Apr/19 925 400 400KV Raigarh-II tie bay (403) at Raipur ss 9:30 17:30 Daily For AMP work WRTS-I WRTS-I R 27/Apr/19 27/Apr/19 926 765 240MVAr BUS Reactor Main bay(707) at Vadodara 10:00 17:00 Daily For CB AMP work, Bus Reactor will remain charge through Tie POWERGRID WR-II R 27/Apr/19 27/Apr/19 Bay 927 400 BUS COUPLER @ KARAD 10:00 17:00 Daily 400 KV PG & HCB Isolator overhauling work, MSETCL MSETCL NA 27/Apr/19 27/Apr/19 Quarterly. Maint. Work 928 220 220V Shujalpur-Shujalpur ckt-II at Shujalpur. (Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I. POWERGRID WR-II C required ,work will be done online) 27/Apr/19 27/Apr/19 929 765 708 Bay (Tie Bay of Agra#1 Line) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 27/Apr/19 27/Apr/19 930 400 400kV Satna- Vindhyachal#1 at Satna 18:00 18:30 Daily To take L/R into service at Satna after AMP Works POWERGRID WR-II R 27/Apr/19 27/Apr/19 931 220 A BUS @ BOISAR II 07:00 19:00 Continuous OUTAGE ON 220KV A-BUS AT 220KV BOISAR-II S/S FOR MSETCL MSETCL All Lines & 27/Apr/19 28/Apr/19 MAINTENANCE WORK equipments will 932 400 315MVA Transformer -II at 400KV S/S Indore 9:00 18:00 Continue X-MER Maintenance work and replacement of 400 KV line MPPTCL MPPTCL R 27/Apr/19 28/Apr/19 Isolator & 220 KV Auxiliary Isolator under PSDF ICT-II will be 933 765 765 KV BUS 2 AT INDORE PS 9:00 0:00 CONTINUOUS FOR CONSTRUCTION WORK OF NEW 765 KV KHANDWA POWERGRID WR-II C 27/Apr/19 29/Apr/19 LINE BAYS 934 400 400kV Sami - Dehgam Ckt-1 7:00 18:00 Daily Line modification work in mentioned transmission Line for ATIL ATIL Constrution 27/Apr/19 30/Apr/19 crossing of under construction railway line of DFCCIL.(Other 935 400 400kV Sami - Dehgam Ckt-2 7:00 18:00 Daily Line modification work in mentioned transmission Line for ATIL ATIL Constrution 27/Apr/19 30/Apr/19 crossing of under construction railway line of DFCCIL.(Other 936 400 NAGOTHANE - DABHOL 2 08:00 18:00 Daily Cold washing & Hill Cutting Work MSETCL MSETCL Load can be 27/Apr/19 30/Apr/19 managed on 937 400 400 kV Chorania - Bhachau Line 8:00 18:00 Daily Conditioning monitoring work at 400KV Chorania S/s. PGCIL GETCO 28/Apr/19 28/Apr/19 938 400 400KV Bhopal-Bina-I 9:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 28/Apr/19 28/Apr/19 939 400 400 kV Vadavi - Dehgam line No. 2 (Auto reclose of Vadavi - 8:00 18:00 Daily Line maintenance work GETCO GETCO Dehgam line No. 1 will remain out) 28/Apr/19 28/Apr/19 940 765 765kV Bus#2 at V'chal 9:00 18:00 Daily T point Isolators connection of ankaring bolt POWERGRID WR-II R 28/Apr/19 28/Apr/19 941 400 400kV KORBA-SIPAT 8:00 18:30 Daily Line AMP works. WRTS-I WRTS-I R 28/Apr/19 29/Apr/19 942 400 KALWA - KHARGHAR 08:00 18:00 Daily Bay Maintenance & testing work MSETCL MSETCL - 28/Apr/19 28/Apr/19 943 400 400 KV SUGEN VAPI Line 8:00 18:00 Daily For Porcelain Insulator string replacement of Tension Towers TPGL TPGL R 28/Apr/19 28/Apr/19 944 765 712 Bay (Main bay of Bina#1 Line) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 28/Apr/19 28/Apr/19 945 400 400 kV Bus Transfer Asoj 7:00 18:00 Daily Replacement of Pantograph of Bus Transfer - 400KV Bus1 GETCO GETCO 29/Apr/19 29/Apr/19 946 400 400 kV Bus- 1 Asoj 7:00 18:00 Daily Replacement of Pantograph of Bus Transfer - 400KV Bus1 GETCO GETCO 29/Apr/19 29/Apr/19 947 765 765kV Bus-1 with Bus Reactor at Dhule 7:00 19:00 Daily Anuual Maintenance and testing BDTCL BDTCL R 29/Apr/19 29/Apr/19 948 400 220kV Bus-1 (All feeders/ICTs will remain charged through Bus- 8:00 18:00 daily For application of Silicon grease in Isolators POWERGRID WR-II 2) at Bhachau 29/Apr/19 29/Apr/19 949 765 765kV Vindhyachal-Satna#2 Line at V'chal, dia to be kept open 9:00 18:00 Daily T point Isolators connection of ankaring bolt POWERGRID WR-II R at both ends 29/Apr/19 29/Apr/19 950 400 400 kV Chorania-Asoj-2 Line (Auto reclose of Chorania -Amreli 8:00 18:00 Daily Line maintenance work GETCO GETCO will remain out) 29/Apr/19 29/Apr/19 951 400 400 kV Vadavi - Bhachau line No. 1 8:00 18:00 Daily Bay equipment CM work PGCIL GETCO 29/Apr/19 29/Apr/19 952 400 400kV Pune - Pune (GIS) - 1 8:00 16:00 Daily Annual Maintenance work WTPL WTPL Routine 29/Apr/19 29/Apr/19 953 400 400 KV PIRANA(TPL) - UNOSUGEN(TPL) LINE 8:00 18:00 Daily CONNECTION TIGHTNESS WORK(WAVETRAP+CT)+ TPL TPL R 29/Apr/19 29/Apr/19 CONNECTED HARDWARE REPLACEMENT WORK 954 220 Bhachau-Morbi Line at Bhachau 8:00 18:00 daily Line outage required for Installation of ABT meter at both ends POWERGRID WR-II 29/Apr/19 29/Apr/19 955 400 400kV Satna- Vindhyachal#2 at Satna 9:00 9:30 Daily To isolate L/R at Satna for AMP Works POWERGRID WR-II R 29/Apr/19 29/Apr/19 956 400 40kv Tarapur-Boisar-ll line at Boisar 9:00 14:00 Daily code for Online Main-I relay replacement & For tripping and POWER GRID WR-II R 29/Apr/19 29/Apr/19 A/R Trials of Main-I relay (Line will be out of service) 957 400 411 Tie bay of 400 kV Koradi-II Line-1 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 29/Apr/19 29/Apr/19 958 220 220KV Urse-2 Main bay (208) at Pune (Talegaon) 9:00 17:00 Daily AMP of Line Equipments WRTS-I WRTS-I R 29/Apr/19 29/Apr/19 959 400 765/400kv ICT-2 Main Bay 421 400kv side at Champa PS 9:00 17:30 Daily For APM works. WRTS-I WRTS-I R 29/Apr/19 29/Apr/19 960 400 400kV Satna- Vindhyachal#2 Line Reactor at Satna 9:00 18:00 Daily AMP Work POWERGRID WR-II R 29/Apr/19 29/Apr/19 961 400 400KV Khandwa - Khargone, A/R to be kept in non-auto of 9:00 18:00 Daily For replacement of Porcelain disc Insulator to Polymer /Glass POWERGRID WR-II C 400KV Khandwa-Rajgarh & dia to be kept open. 29/Apr/19 29/Apr/19 Insulator in Railway crossing ( Loca 11-12)….. 962 765/400 765/400 kV ICT #2at V'chal, dia to be kept open 9:00 18:00 Daily B/U Impedance relays commissioning POWERGRID WR-II C 29/Apr/19 29/Apr/19 963 765 SWITCHABLE_LR_765kV_PARLI2_ WARORA_PWTL 9:00 18:00 Daily For Warantee period testing PWTL PWTL R 29/Apr/19 29/Apr/19 964 765 765kV SEONI-WARDHA I 9:00 18:00 Daily For Line AMP Line reactor AMP at both ends. WRTS-I WRTS-I R 29/Apr/19 29/Apr/19 965 400 400kV Parli-2 Main bay_416 at Solapur 9:00 18:00 Daily For AMP works WRTS-I WRTS-I R 29/Apr/19 29/Apr/19 966 400 400kV RAIPUR-RAIGARH III 9:30 17:30 Daily Line AMP works, ckt-4 A/R in Non auto mode required. WRTS-I WRTS-I R 29/Apr/19 29/Apr/19 967 220 220V Shujalpur-Rajgarh ckt-I at Shujalpur. (Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I. POWERGRID WR-II C required ,work will be done online) 29/Apr/19 29/Apr/19 968 220 207 Bay (220kV Mahalgaon#2 Bay) at Gwalior, line will be in 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R service through TBC 29/Apr/19 29/Apr/19 969 400 400kV Satna- Vindhyachal#2 at Satna 18:00 18:30 Daily To take L/R into service at Satna after AMP Works POWERGRID WR-II R 29/Apr/19 29/Apr/19 970 765 765kV Gwalior-Bina ckt-3 at Bina, dia to be kept open at both 9:15 17:30 Daily Line AMP (for Attending the shut down nature defects in line.) POWERGRID WR-II R ends 29/Apr/19 29/Apr/19 971 400 KHADKA- DEEPNAGAR CKT 1 & 2 (AR IN NON-AUTO MODE) 08:00 15:00 Daily For PID Testing by PID Unit,Khadka MSETCL MSETCL A/R Required in 29/Apr/19 30/Apr/19 Non-Auto Mode 972 400 ICT-2 Main Bay-24 at NTPC Sipat 8:00 18:00 Continuous PM (ICT-2 Transformer will remain charged through it's Tie NTPC NTPC R 29/Apr/19 30/Apr/19 bay) 973 400 400 KV LANCO1__TIE_BAY_420 at Bilaspur 9:00 18:00 Conti? For AMP works WRTS-I WRTS-I R 29/Apr/19 30/Apr/19 974 220 TAPS 1&2- TAPP 3&4 tie line 8:00 19:00 Daily Basis Annual maintenance Works MSETCL NPCIL R 29/Apr/19 02/May/19 975 220 220kV Bus-2 (All feeders/ICTs will remain charged through Bus- 8:00 18:00 daily For application of Silicon grease in Isolators POWERGRID WR-II 1) at Bhachau 30/Apr/19 30/Apr/19 976 765/400 765/400 kV ICT #1 at V'chal, dia to be kept open 9:00 18:00 Daily B/U Impedance relays commissioning POWERGRID WR-II C 30/Apr/19 30/Apr/19 977 765 765kV , sasan-Satna line-1 Main Bay No 800-12 at sasan 8:00 20:00 Dialy Bay Yearly Maintenance SASAN RELIANCE R 30/Apr/19 30/Apr/19 978 765 765kV Dhule-Vadodara Line with 701 main and 702 tie bays at 7:00 19:00 Daily Relay and line equipment testing at BDTCL Dhule BDTCL BDTCL R Dhule 30/Apr/19 30/Apr/19 979 765 765kV Satna-Bina ckt-1 at Bina, dia to be kept open at both ends 9:15 0:00 Daily Line AMP (for Attending the shut down nature defects in line.) POWERGRID WR-II R 30/Apr/19 30/Apr/19 980 400 400 kV Kasor - GPEC line 7:00 17:00 Daily SRI replacement work GETCO GETCO 30/Apr/19 30/Apr/19 981 400 400kV Pune - Pune (GIS) - 2 8:00 16:00 Daily Annual Maintenance work WTPL WTPL Routine 30/Apr/19 30/Apr/19 982 400 KALWA - KHARGHAR 08:00 18:00 Daily Routine Maintenance & Diagnostic testing work MSETCL MSETCL Nil 30/Apr/19 30/Apr/19 983 400 400 KV PIRANA(TPL) - UNOSUGEN(TPL) LINE 400 KV PIRANA 8:00 18:00 Daily CONNECTION TIGHTNESS WORK(WAVETRAP+CT) + TPL TPL R (TPL S/S) 30/Apr/19 30/Apr/19 CONNECTED HARDWARE REPLACEMENT WORK 984 400 400/220/33KV 315MVA ICT -1 at Bhachau (Dia to be kept open) 8:00 18:00 daily Leakage arresting work in IV Bushing Turret. POWERGRID WR-II 30/Apr/19 30/Apr/19 985 400 400kV SATNA- Bina#1 at Satna SS 9:00 10:00 Daily To take L/R into service at Satna POWERGRID WR-II R 30/Apr/19 30/Apr/19 986 400 412 Main bay of 400 kV Koradi-II Line 1 at Koradi-III substation 9:00 16:00 Daily SF6 gas analysis of breakers MEGPTCL MEGPTCL 30/Apr/19 30/Apr/19 987 400 400 kV Kosamba Chorania-2 (Auto reclose of 400 KV Chorania - 9:00 18:00 Daily Line and bay maintenance work by Kosamba GETCO GETCO Charal and 400 KV Charal - Kosamba will remain out) 30/Apr/19 30/Apr/19 988 400 400KV Khandwa - Rajgarh, A/R to be kept in non-auto of 400KV 9:00 18:00 Daily For replacement of Porcelain disc Insulator to Polymer /Glass POWERGRID WR-II C Khandwa-Khargone & dia to be kept open. 30/Apr/19 30/Apr/19 Insulator in Railway crossing ( Loca 11-12) 989 765 ICT2_765/400kv_PARLI _PPTL 9:00 18:00 Daily Faulty Aircell replacement works by OEM agency PPTL PPTL R 30/Apr/19 30/Apr/19 990 220 220 KV Bus-2 at Wardha 9:00 18:00 Daily For AMP work. WRTS-I WRTS-I R 30/Apr/19 30/Apr/19 991 765 765 Kv ICT-3 Main bay(709) at Wardha 9:00 18:00 Daily For AMP work WRTS-I WRTS-I R 30/Apr/19 30/Apr/19 992 400 400kV RAIPUR-RAIGARH IV 9:30 17:30 Daily Line AMP works, ckt-3 A/R in Non auto mode required. WRTS-I WRTS-I R 30/Apr/19 30/Apr/19 993 220 220KV Annupur-Kotmikala-II 10:00 17:00 Daily For line maintenance work MPPTCL MPPTCL R 30/Apr/19 30/Apr/19 994 220 220V Shujalpur-Rajgarh ckt-II at Shujalpur. (Line outage not 10:00 18:00 Daily Online Diode replacement in PLCC Chanel-I. POWERGRID WR-II C required ,work will be done online) 30/Apr/19 30/Apr/19 995 400 415 Bay (Main Bay of 400kV side of 765kV ICT#2) at Gwalior 10:00 18:00 Daily AMP WORKS POWERGRID WR-II R 30/Apr/19 30/Apr/19 996 400 315 MVA ICT -I at 400 KV S/s Khedamara. 8:00 17:00 Continuous Annual Maintenance Programme. CSPTCL CSPTCL R 30/Apr/19 01/May/19 997 220 220KV Transfer Bay 201 at Mapusa 9:00 18:00 Cont. Replacement of existing VARM AR Relay with numerical Relay WRTS-I WRTS-I R 30/Apr/19 01/May/19 Anaulagnak 3.3

maaca- 2019 AaOr Ap`Ola 2019 maah ko ilayao Apoixat maMaga evMa }jaa- kI AavaSyakta

Anticipated demand and energy for the month of March 2019 AND April 2019

maaMga }jaa- kI AavaSyakta rajya State DEMAND ENERGY REQUIREMENT maogaavaaT (MW) imailayana yauinaTsa maaca- 2019 Ap`Ola 2019 maaca- 2019 Ap`Ola 2019 March 2019 April 2019 March 2019 April 2019

1 gaujarat GUJARAT saIimat RESTRICTED 16125 16500 10540 10740 AsaIimat UNRESTRICTED 16150 16525 10550 10750

2 maQya p`doSa MADHYA PRADESH saIimat RESTRICTED 11500 8967 6100 6217 AsaIimat UNRESTRICTED 11500 9250 6100 6659

3 C

4 maharaYT/ MAHARASHTRA saIimat RESTRICTED 23500 24000 14450 14750 AsaIimat UNRESTRICTED 23500 24000 14500 14800

5 gaaovaa GOA saIimat RESTRICTED 571 622 360 361 AsaIimat UNRESTRICTED 586 659 390 371

6 dmana dIva DD saIimat RESTRICTED 354 344 222 225 AsaIimat UNRESTRICTED 372 348 240 236

7 DI ena eca DNH saIimat RESTRICTED 863 800 499 557 AsaIimat UNRESTRICTED 900 800 619 557

8 piScama xao~ WESTERN REGION saIimat RESTRICTED 55849 53025 37969 35994 AsaIimat UNRESTRICTED 53701 55254 39450 36229

Anaulagnak 4.1 Unit -wise Actual generation for the month of FEBRUARY 2019 frvarI 2019

Actual vaastivak k`maaMk sToSana ka naama }jaa- carma Auxillary Sr. Station Name Energy Peak Consumption No. (MUs) (Mw) (MUs) UKAI(H) - 1 5.86 75 UKAI(H) - 2 1.11 75 UKAI(H) - 3 0.00 0 UKAI(H) - 4 0.00 0 0.00 UKAI(TOTAL) 6.97 150 0.3140 UKAI LBCH - 1 0.81 1 UKAI LBCH - 2 0.09 1 0.00 UKAI LBCH (TOTAL) 0.90 2 0.02 KADANA - 1 0.80 52 KADANA - 2 10.04 55 KADANA - 3 2.36 51 KADANA - 4 8.65 56 0.00 KADANA (TOTAL) 21.85 214 0.04 PANAM 0.59 1 0.01 Madhuban Dam (Hy.)-1 0.97 4 Madhuban Dam (Hy.)-2 0.95 4 Madhuban Dam (Hy.)-3 0.50 4 0.01 AREVA HY(KARJAN) 2.06 3 0.00 Ajanta hy (DOLATPURA)-1 0.00 0 Ajanta hy (DOLATPURA)-2 2.27 4 Ajanta hy (DOLATPURA)-3 1.62 4 0.00 SMALL HYDRO 8.97 26 0.02 SSP RBPH-1 0.00 0 0.00 SSP RBPH-2 0.00 0 0.00 SSP RBPH-3 0.00 0 0.00 SSP RBPH-4 0.00 0 0.00 SSP RBPH-5 0.00 0 0.00 SSP RBPH-6 0.00 0 0.00 SSP-CHPH-1 13.28 33 0.20 SSP-CHPH-2 1.55 32 0.02 SSP-CHPH-3 18.50 36 0.28 SSP-CHPH-4 9.95 36 0.15 SSP-CHPH-5 18.70 34 0.28 SSP (TOTAL) * 61.98 171 0.93 SSP GUVNL Share 9.92 27 0.15 GUJARAT TOTAL ( HYDRO ) 38.68 420 396.39 THERMAL(GUJARAT) Torrent Power Ltd.- D 75.15 123 6.31 Torrent Power Ltd.- E 76.29 123 6.17 Torrent Power Ltd.- F 71.73 124 6.23 TOTAL TP AHMEDABAD 223.17 370 18.70 DGB - GT1 0.00 0 DGB - STG1 0.00 0 0.13 DGB - GT2 20.15 94 DGB - STG2 8.59 0 1.84 DGB - GT3 0.00 0 DGB - STG3 0.00 0 0.28 TOTAL DHUVARAN 28.73 94 2.25 UKAI-3 111.21 198 10.67 UKAI-4 59.76 203 5.71 UKAI-5 112.90 212 10.68 UKAI-6 264.36 506 15.25 TOTAL UKAI 548.24 1119 42.30 GANDHINAGAR -3 75.62 213 8.30 GANDHINAGAR -4 64.64 213 7.35 GANDHINAGAR -5 123.49 217 12.18 TOTAL GANDHINAGAR 263.75 643 27.84 WANAKBORI -1 23.52 213 WANAKBORI -2 31.04 214 WANAKBORI -3 122.78 217 WANAKBORI -4 48.72 210 WANAKBORI -5 76.79 215 WANAKBORI -6 0.00 0 WANAKBORI -7 120.32 216 TOTAL WANAKBORI 423.18 1285 43.57 UGPP GT-4 0.00 0 UGPP STG-2 0.00 0 0.56 TOTAL UTRAN 0.00 0 0.56 SIKKA - 3 90.22 253 9.28 SIKKA - 4 98.81 255 9.33 TOTAL SIKKA 189.02 508 18.61 Akrimota Linite-1 46.12 106 8.72 Akrimota Linite-2 40.45 91 7.76 TOTAL Akrimota Lignite 86.57 197 16.47 Kutch Lig.-1 32.18 60 4.70 Kutch Lig.-2 32.03 62 4.83 Kutch Lig.-3 25.63 77 3.25 Kutch Lig.-4 26.81 55 6.10 TOTAL Kutch Lig 116.64 254 18.89 GIPCL - GT 1 0.00 0 GIPCL - GT 2 20.17 32 GIPCL - GT 3 20.51 32 GIPCL - ST 1 21.28 33 GIPCL - GT 4 0.00 0 GIPCL - ST 2 0.00 0 TOTAL GIPCL 61.96 98 1.33 SURAT - LIG1 64.73 127 6.52 SURAT - LIG 2 75.69 127 7.93 SURAT - LIG 3 63.91 122 7.09 SURAT - LIG 4 74.84 129 7.94 Total SURAT -LIG 279.17 505 29.49 EPGL1 0.00 0 0.34 EPGL 2 0.00 0 0.47 TOTAL ESSAR 0.00 0 0.80 CLPIPL GT1 0.00 0 0.00 CLPIPL GT2 0.00 0 0.00 CLPIPL GT3 0.00 0 0.00 CLPIPL STG 0.00 0 0.00 TOTAL CLPIPL 0.00 0 0.00 GSEG 1 0.00 0 GSEG 2 0.00 0 GSEG STG 0.00 0 0.35 GSEG -II GT 1 0.00 0 0.00 GSEG -II STG 0.00 0 0.19 TOTAL GSEG 0.00 0 0.54 Sugen (GT 1) 178.98 393 Sugen (GT 2) 21.45 353 Sugen ( GT 3) 176.28 387 8.32 Uno Sugen 0.00 0 0.46 TOTAL SUGEN 376.71 1133 8.78 APL 1 182.16 338 0.00 APL 2 186.64 339 0.00 APL 3 186.42 341 0.00 APL 4 194.39 343 0.00 APL 5 393.32 676 0.00 APL 6 370.50 670 0.00 APL 7 353.22 650 0.00 APL 8 371.59 670 0.00 APL 9 377.21 675 0.00 TOTAL APMuL 2615.45 4702 172.99 OPGS GT1 79.79 149 6.84 OPGS GT2 97.28 154 7.91 TOTAL OPGS 177.08 303 14.75 BECL 1 23.79 189 6.08 BECL 2 0.00 0 0.46 TOTAL BECL 23.79 189 6.54 GPPC GT1 0.00 0 GPPC STG1 0.00 0 0.28 GPPC GT2 0.00 0 GPPC STG2 0.00 0 0.27 TOTAL GPPC 0.00 0 0.56 OTHER CPP 6.86 10 0.00 TOTAL CPP 6.86 10 0.00 GUJARAT TOTAL (Th.) 5420.31 11408 424.96 0.00 GUVNL TOTAL (H+T ) 5458.99 11827 425.36 WIND ENERGY 756.18 1050 15.12 SOLAR ENERGY 241.65 336 4.83 BIO -MASS ENERGY 7.97 11 0.16 GUJARAT TOTAL RES 1005.80 1397 20.12 GUVNL TOTAL (H+T+RES ) 6464.79 13224 425.38

MADHYA PRADESH H Y D R O

G.' SAGAR 50.99 0 0.07 R.P.SAGAR 56.63 0 0.04 J.' SAGAR 39.50 66 0.02 TOTAL CHAMBAL(100%) 147.11 66 0.13 MP CHAMBAL SHARE (50%) 73.55 33 0.06 PENCH 2.30 157 0.04 MP PENCH SHARE(2/3) 1.53 105 0.03 BARGI 15.43 92 0.04 BARGI (LEFT BANK (NVDA) 0.00 0 0.00 Bansagar TONS 30.39 315 0.19 Bansagar Devlondh 0.00 63 0.03 Bansagar Silpara 4.43 20 0.04 Bansagar Jinaha 9.18 22 0.04 Madikheda 8.31 69 0.12 BIR'PUR 0.00 21 0.00 TAWA 0.00 0 0.00 TOTAL 67.73 602 0.46 RAJGHAT 8.76 42 0.02 MP SHARE RAJGHAT(50%) 4.38 21 0.01 Omkareshwar Unit-1 1.36 65 Unit-2 6.26 65 Unit-3 5.18 65 Unit-4 9.03 65 Unit-5 10.61 65 Unit-6 1.63 65 Unit-7 2.32 65 Unit-8 5.35 64 TOTAL Omkareshwar 41.74 460 0.31 Indira Sagar - 1 9.73 134 Indira Sagar - 2 8.71 134 Indira Sagar - 3 11.43 135 Indira Sagar - 4 15.72 135 Indira Sagar - 5 18.95 134 Indira Sagar - 6 11.77 132 Indira Sagar - 7 7.00 133 Indira Sagar - 8 9.66 129 TOTAL INDIRA SAGAR (100%) 92.98 555 0.46 MP SSP SHARE 35.33 97 0.53 MP TOTAL (H) 281.91 1776 1.32

MADHYA PRADESH (THERMAL)

AMARKANTAK (III UNIT-5) 139.79 220 0.00 TOTAL AMARKANKTAK-II 139.79 220 12.66 SATPURA-II UNIT - 6 75.65 0 SATPURA-II UNIT - 7 92.99 175 SATPURA-II (UNITS 6 - 7) 168.64 175 16.16 SATPURA-III UNIT - 8 88.00 188 SATPURA-III UNIT - 9 89.64 195 SATPURA-III (UNITS 8-9) 177.64 383 16.81 SATPURA-IVUNIT - 10 130.33 265 SATPURA-IV UNIT - 11 129.67 259 SATPURA-III (UNITS 10-11) 260.01 524 25.53 TOTAL SATPURA 606.29 1082 58.50 S.GANDHI TPS-1 115.60 204 S.GANDHI TPS-2 109.98 202 SGTPS PHASE-I 225.58 406 20.78 S.GANDHI TPS-3 0.00 209 S.GANDHI TPS-4 118.78 213 SGTPS PHASE-II 118.78 422 12.91 S.GANDHI TPS-5 274.10 509 SGTPS PHASE-III 274.10 509 15.27 TOTAL S.GANDHI TPS 618.46 1337 48.96 SRI SINGHAJI(SSTPS)-I 291.18 605 SRI SINGHAJI(SSTPS)-II 228.84 599 SSTPS PHASE-I 520.02 1204 28.70 SRI SINGHAJI(SSTPS)-III 338.43 527 SRI SINGHAJI(SSTPS)-IV 76.49 0 SSTPS PHASE-II 414.92 527 TOTAL SSTPS 934.94 1731 53.46 BLA POWER 0.00 0 0.00 JP BINA+CPP 202.42 281 11.46 MP IPP INJECTION 202.42 281 11.46 MP TOTAL (Th.) 2501.90 4651 185.04

MP TOTAL (H+T ) 2783.81 6427 186.36 WIND ENERGY 233.16 324 11.66 SOLAR ENERGY 194.21 270 9.71 BIO -MASS ENERGY 29.41 41 1.47 TOTAL MP RES 456.78 634 22.84 MP TOTAL (H+T+RES ) 3240.58 7061 209.20

CHHATTISGARH

HYDRO H. BANGO 7.67 120 0.05 Gangrel 2.09 10 0.03 Mini Micro KWB 0.00 7 0.00 CHHATTISHGARH TOTAL (H) 9.76 137 0.08 CHHATTISHGARH (THERMAL) KORBA (E-II) -1 0.00 0 KORBA (E-II) -2 0.00 0 KORBA (E-II) -3 0.00 0 KORBA (E-II) -4 0.00 0 TOTAL KORBA (E) 1-4 0.00 0 0.00 KORBA (E) -5 56.65 97 KORBA (E) -6 59.12 78 TOTAL KORBA (E) 5-6 115.77 182 12.00 TOTAL KORBA (E) 115.77 182 12.00 KORBA(W) - 1 106.07 167 KORBA(W) - 2 114.53 206 TOTAL KORBA (W) 1-2 220.60 373 20.93 KORBA(W) - 3 92.33 190 KORBA(W) - 4 111.88 193 TOTAL KORBA (W) 3-4 204.20 383 19.26 KWB EXTN -5 304.54 498 15.64 TOTAL KORBA (W) 729.35 2010 55.83 KORBA(EB) Extn - 1 (DSPM 1) 132.09 255 KORBA(EB) Extn - 2 (DSPM 2 152.92 255 TOTAL KORBA (E) DSPM 285.01 510 22.60 MARWA-1 0.00 0 MARWA-2 308.76 515 TOTAL MARWA 308.76 515 17.76 TOTAL CHHATTISHGARH (THERMAL) 1438.89 3217 108.20 CHHATTISGARH (TH+HY) 1448.65 3354 108.27

MAHARASHTRA H Y D R O Koyana I & II 64.55 0 1.04 Koyana IV 20.64 0 0.74 Koyana III 29.43 0 0.22 K.D.P.H. 11.38 0 0.02 Total KGSC 126.00 0 2.02 Panshet 4.21 0 0.01 V'sgaon 1.26 0 0.00 Pawna 2.22 0 0.01 M'kdoh 0.04 0 0.01 Dimbhe 1.15 0 0.00 Bhatghar 2.71 0 0.01 Kanher 0.92 0 0.01 Dhom 0.83 0 0.00 Ujjani 0.93 0 0.01 Warna 2.69 0 0.01 Tillari 5.98 0 0.03 D'ganga 0.00 0 0.02 T'medhe 0.05 0 0.00 R'nagari 0.00 0 0.00 Bhira 9.28 0 0.01 Total HPC Pune 32.27 0 0.14 Vaitarna 5.30 0 0.07 Vaitarna D.T. 0.36 0 0.00 Bhatsa 8.61 0 0.02 Surya 0.00 0 0.01 Yeldari 0.00 0 0.01 Paithan 2.39 0 0.02 Ghatghar U-I 4.15 0 0.14 Ghatghar U-II 0.00 0 0.00 Total HPC Nasik 20.81 0 0.27 TATA HYDRO KHOPOLI 28.22 75 BHIVPURI 13.73 72 BHIRA 35.11 150 BHIRA PS 51.16 165 TOTAL TATA HYDRO 128.21 0 1.64 TOTAL MAHARASHTRA (Hydro) 323.38 0 3.32 THERMAL NASIK - 3 0.00 0 NASIK - 4 51.90 208 NASIK - 5 63.45 200 TOTAL NASIK 115.35 408 TROMBAY - 5 235.76 486 TROMBAY - 6 0.00 0 TROMBAY -8 145.40 239 TROMBAY - 7 A 72.17 117 TROMBAY - 7 B 42.91 68 TOTAL TROMBAY 496.24 910 KORADI - 6 62.97 200 KORADI - 7 0.00 0 KORADI - 8 285.13 567 KORADI - 9 307.83 665 KORADI - 10 288.37 629 TOTAL KORADI 944.30 2061 BHUSAWAL - 3 0.00 0 BHUSAWAL - 4 275.26 505 BHUSAWAL - 5 243.19 510 TOTAL BHUSAWAL 518.45 1015 #REF! #REF! #REF! PARLI - 4 0.00 0 PARLI - 5 0.00 0 PARLI - 6 0.00 0 PARLI - 7 0.00 0 PARLI - 8 0.00 0 TOTAL PARLI 0.00 0 K'KHEDA - II - 1 100.68 180 K'KHEDA - II - 2 103.68 165 K'KHEDA - II - 3 97.89 183 K'KHEDA - II - 4 106.04 180 K'KHEDA - II - 5 269.68 495 TOTAL K'KHEDA 677.97 1203 PGPL-1 0.00 0 PGPL-2 0.00 0 TOTAL PGPL 0.00 0 URAN (G) - 5 0.00 0 URAN (G) - 6 0.00 0 URAN (G) - 7 0.00 0 URAN (G) - 8 178.80 424 ALL URAN (G) 194.55 334 URAN - WHR -I 0.00 0 URAN - WHR -II 0.00 0 TOTAL URAN - WHR 0.00 0 CHANDRAPUR -3 121.79 198 CHANDRAPUR -4 95.74 192 CHANDRAPUR -5 209.45 435 CHANDRAPUR -6 167.41 465 CHANDRAPUR -7 264.73 462 CHANDRAPUR -8 258.39 500 CHANDRAPUR -9 293.17 500 TOTAL CHANDRAPUR 1410.68 2752 PARAS -3 0.00 0 PARAS - 4 120.06 259 TOTAL PARAS 120.06 259 REL DAHANU - I 144.76 250 REL DAHANU - I I 144.76 250 TOTAL DAHANU 270.15 500 APML(All Units) 1785.06 0 JSWEL(All Units) 590.37 0 VIPL(All Units) 0.00 0 RPL AMT(All Units) 0.00 0 WPCL(All Units) 0.00 0 Other CPPS/IPPS 355.64 0 TOTAL MAHARASHTRA CPPS/IPPS 2731.07 3793 MAHARASHTRA TOTAL (Th.)(INCL TATA,ADANI) 7478.82 13235 345.91 MAHARASHTRA TOTAL (H+T ) 7802.20 13235 349.24 Wind injection (W) 290.33 403 5.81 Solar injection (S) 184.57 256 3.69 TOTAL MAHARASHTRA RES 474.90 660 9.50 TOTAL MAHARASHTRA (TH+H+RES) 8277.10 13895 358.74

GOA IPP GOA 15.71 22 0.31

CENTRAL SECTOR N P C I L TAPS - I 107.95 160 0.00 TAPS - II 110.45 160 0.00 TOTAL TAPS 1-2 218.40 320 14.12 TAPS - III 367.30 549 0.00 TAPS - IV 366.36 546 0.00 TOTAL TAPS 3-4 733.66 1095 64.92 KAKRAPAR - I 0.00 0 0.00 KAKARAPAR - II 152.01 222 0.00 TOTAL KAPS 1-2 152.01 222 15.41 TOTAL NPCIL GENERATION 952.06 1415 94.45

N T P C K S T P S - 1 123.81 215 0.00 K S T P S - 2 132.78 214 0.00 K S T P S - 3 133.70 213 0.00 K S T P S - 4 328.38 513 0.00 K S T P S - 5 326.85 514 0.00 K S T P S - 6 280.79 515 0.00 K S T P S - 7 330.55 513 0.00 TOTAL K S T P S 1656.86 2697 102.14 V S T P S - 1 129.53 215 0.00 V S T P S - 2 128.04 212 0.00 V S T P S - 3 106.18 211 0.00 V S T P S - 4 128.17 213 0.00 V S T P S - 5 124.83 214 0.00 V S T P S - 6 130.53 215 0.00 V S T P S -7 308.80 513 0.00 V S T P S -8 323.74 515 0.00 V S T P S -9 309.00 514 0.00 V S T P S -10 311.58 513 0.00 V S T P S -11 308.01 513 0.00 V S T P S -12 321.15 514 0.00 V S T P S -13 136.86 515 0.00 TOTAL V S T P S 2766.42 4877 175.24 SIPAT STPS-1 364.23 660 0.00 SIPAT STPS-2 436.34 660 0.00 SIPAT STPS-3 438.24 670 0.00 SIPAT STPS-4 239.14 520 0.00 SIPAT STPS-5 332.66 520 0.00 TOTAL SIPAT 1810.61 3030 96.22 KAWAS-GT-1A 36.60 105 0.00 KAWAS-GT-1B 36.59 106 0.00 KAWAS- ST-1 43.49 116 0.00 KAWAS-GT-2A 17.28 106 0.00 KAWAS-GT- 2 B 16.64 106 0.00 KAWAS-ST-2 19.07 116 0.00 TOTAL KAWAS 169.67 655 4.77 GANDHAR - GT1 9.05 144 0.00 GANDHAR - GT2 0.00 144 0.00 GANDHAR - GT3 13.97 144 0.00 GANDHAR - ST3 11.28 0 0.00 TOTAL GANDHAR 34.30 432 1.82 MAUDA-1 261.38 510 0.00 MAUDA-2 75.28 510 0.00 MAUDA-3 57.74 660 0.00 MAUDA-4 338.04 500 0.00 TOTAL MAUDA 732.44 2180 41.97 SOLAPUR-1 0.00 680 0.00 SOLAPUR-2 0.00 0 0.00 TOTAL SOLAPUR 0.00 660 9.31 LARA-1 0.00 0 0.00 LARA-2 0.00 0 0.00 TOTAL LARA 0.00 660 0.00 GADARWADA-1 0.00 0 0.00 GADARWADA-2 0.00 0 0.00 TOTAL GADARWADA 0.00 660 0.00 KHARGAONE-1 0.00 0 0.00 KHARGAONE-2 0.00 0 0.00 TOTAL KHARGAONE 0.00 660 0.00 TOTAL NTPC GENERATION 7170.30 16511 431.48

RGPPL RGPPL (Dabhol) Phase I 0.00 0 0.00 RGPPL (Dabhol) Phase II 262.65 560 0.00 RGPPL (Dabhol) Phase III 59.43 265 0.00 RGPPL TOTAL 322.08 560 8.05 OTHER REGIONAL IPPS SASAN TOTAL 2780.14 0 139.01 CGPL TOTAL 2606.69 0 130.33 JPL TOTAL 126.70 0 6.34 JPL EXT TOTAL 672.38 0 33.62 BALCO -1 0.00 0 0.00 BALCO -2 0.00 0 0.00 BALCO -3 0.00 0 0.00 BALCO -4 0.00 0 0.00 BALCO TOTAL 251.33 0 12.57 ACBIL -1 0.00 0 0.00 ACBIL -2 0.00 0 0.00 ACBIL TOTAL 183.44 0 9.17 TRN -1 0.00 0 0.00 TRN-2 0.00 0 0.00 TRN TOTAL 211.13 0 10.56 NSPCL -1 0.00 0 0.00 NSPCL-2 0.00 0 0.00 NSPCL TOTAL 174.71 0 8.74 JAYPEE NIGRIE -1 0.00 0 0.00 JAYPEE NIGRIE-2 0.00 0 0.00 JAYPEE NIGRIE TOTAL 478.35 0 23.92 KSK MAHANADI -1 0.00 0 0.00 KSK MAHANADI -2 0.00 0 0.00 KSK MAHANADI -3 0.00 0 0.00 KSK MAHANADI TOTAL 489.61 0 24.48 MB POWER -1 0.00 0 0.00 MB POWER-2 0.00 0 0.00 MB POWER TOTAL 584.33 0 29.22 DB POWER -1 0.00 0 0.00 DB POWER-2 0.00 0 0.00 DB POWER TOTAL 598.98 0 29.95 RKM POWER GENERATION -1 0.00 0 0.00 RKM POWER GENERATION -2 0.00 0 0.00 RKM POWER GENERATION -3 0.00 0 0.00 RKM POWER GENERATION TOTAL 56.64 0 2.83 KWPCL -1 0.00 0 0.00 KWPCL-2 0.00 0 0.00 KWPCL TOTAL -0.63 0 -0.03 JHABUA POWER-1 0.00 0 0.00 JHABUA POWER-2 0.00 0 0.00 JHABUA POWER TOTAL 261.43 0 13.07 LANCO(AMERKANTAK PATHADI)-1 0.00 0 0.00 LANCO(AMERKANTAK PATHADI)-2 0.00 0 0.00 LANCO(AMERKANTAK ) TOTAL 332.22 0 16.61 SKS-1 0.00 0 0.00 SKS-2 0.00 0 0.00 SKS POWER GEN TOTAL 109.58 0 13.47

GMR RAIPUR -1 0.00 0 0.00 GMR RAIPUR-2 0.00 0 0.00 GMR RAIPUR GEN TOTAL 88.04 0 4.40

DHARIWAL-1 0.00 0 0.00 DHARIWAL-2 0.00 0 0.00 DHARIWAL GEN TOTAL 143.35 0 7.17

EPML-1 0.00 0 0.00 EPML-2 0.00 0 0.00 EMPL GEN TOTAL 251.15 0 12.56 TOTAL WR IPP 10399.57 0 516.40

(I) piScamaI xao~ WESTERN REGION ga`aosa ]%padna Gross generation 38290.84 (J) ]plabQata Availability 36138.56 naoT ivainamaya Net Exchanges -6187.46 ]plabQa }jaa- Energy Availability 29951.10 Anaulagnak 4.2 ANNEX-4.2

rajya State vaastivak Actual (MW) idnaaMk samaya AavaRi

2 एचवीडीसी बॅक टु बॅक लकं वंयाचल पोल 2 HVDC back-to back link Vindhyachal-Pole 2 0:00:00 3 एचवीडीसी मँदु रा टु महेनदरगढ़ पोले 1 HVDC Mundra-Mahendergarh Pole 1 672:00:00 4 एचवीडीसी मँदु रा टु महेनदरगढ़ पोले 2 HVDC Mundra-Mahendergarh Pole 2 672:00:00 5 एचवीडीसी चांपा टु कु े पोल 1 HVDC Champa-Kurukshetra Pole-1 656:47:00 6 एचवीडीसी चांपा टु कु े पोल 2 HVDC Champa-Kurukshetra Pole-2 670:32:00 7 एचवीडीसी बॅक टु बॅक लकं भावती पोल 1 HVDC back-to back link Bhadrawti Pole-1 653:07:00

8 एचवीडीसी बॅक टु बॅक लकं भावती पोल 2 HVDC back-to back link Bhadrawti Pole-2 652:47:00 अतं र-ेीय लाइन Inter-Regional Lines 1 765 के वी सोलापुर से रायचूर -I 765kV solapur to Raichur I 467:00:00 2 765 के वी सोलापुर से रायचूर -II 765kV solapur to Raichur II 672:00:00 3 765 केवी वधा से नजामाबाद-I 765kV Wardha to Nizamabad I 672:00:00 4 765 केवी वधा से नजामाबाद-II 765kV Wardha to Nizamabad II 672:00:00 5 765 केवी वालयर से फागी-I 765kV Gwalior to Phagi I 672:00:00 6 765 केवी वालयर से फागी-II 765kV Gwalior to Phagi II 672:00:00 7 765 केवी वालयर से आगरा-I 765kV Gwalior to Agra I 650:12:00 8 765 केवी वालयर से आगरा-II 765kV Gwalior to Agra II 658:37:00

9 765 केवी धरमजयगड से यू रांची-I 765kV D'garh to New Ranchi I 643:26:00 10 765 केवी धरमजयगड से यू रांची-II 765kV D'garh to New Ranchi II 672:00:00 11 765 के वी धरमजयगड से झारसुगुड़ा-I 765kV D'garh to Jharsuguda I 644:11:00 12 765 के वी धरमजयगड से झारसुगुड़ा-II 765kV D'garh to Jharsuguda II 644:31:00 13 400 केवी कोहापुर से नर I 400kV Kolhapur-Narendra I 672:00:00 14 400 केवी कोहापुर से नर II 400kV Kolhapur-Narendra II 672:00:00 15 400 केवी कंसार से भनमल 400kV Kansari- Bhinmal 625:05:00 16 400 केवी कंसार से कं ोल 400kV Kansari- Kankroli 672:00:00

17 400 के वी रैप से सूजलपुर-I 400 kV RAPP-Sujalur I 666:51:00 18 400 के वी रैप से सूजलपुर-II 400kV RAPP-Sujalur II 672:00:00 19 400 केवी सपत से रांची I 400kV Sipat-Ranchi I 672:00:00 20 400 केवी सपत से रांची II 400kV Sipat-Ranchi II 672:00:00

21 400 के वी रायगढ़ से झरसुगुड़ा I 400kV Raigarh to Jharsuguda I 672:00:00 22 400 के वी रायगढ़ से झरसुगुड़ा II 400kV Raigarh to Jharsuguda II 672:00:00 23 400 के वी रायगढ़ से झरसुगुड़ा III 400kV Raigarh to Jharsuguda III 672:00:00 24 400 के वी रायगढ़ से झरसुगुड़ा IV 400kV Raigarh to Jharsuguda IV 399:28:00 25 400 के वी रायगढ़ से बुधपदर 220kV Raigarh-Budhipadar 672:00:00 26 220 के वी कोरबा पूव से बुधपादर-II 220kV K(E) to Budhipadar-II 587:10:00 27 220 के वी कोरबा पूव से बुधपादर-III 220kV K(E) to Budhipadar-III 672:00:00 28 220 के वी बदोड़ स े साकतपुर 220kV Badod to Sakatpur 672:00:00 29 220 के वी भनपुर से मोडक 220kV Bhanpur to Modak 655:21:00 30 220 के वी महगाओ ं से औरैया 220kV Mehgaon to Auraiya 672:00:00

31 220 के वी मालनपुर से औरैया 220kV Malanpur to Auraiya 672:00:00 अतं र-रायीय लाइन Inter-State Lines 1 765 केवी सवनी से वधा-I 765kV Seoni to Wardha-I 661:04:00 2 765 केवी सवनी से वधा-II 765kV Seoni to Wardha-II 672:00:00 3 765 के वी दगु से वधा -I 765kV Durg to Wardha I 294:29:00 4 765 के वी दगु से वधा -II 765kV Durg to Wardha II 526:16:00 पिचम ेय भार ेषण क , मुबई WRLDC, Mumbai 5 765 के वी दगु से वधा -III 765kV Durg to Wardha III 545:51:00 6 765 के वी दगु से वधा -IV 765kV Durg to Wardha IV 397:31:00 7 765 के वी धुले से वडोदरा-I 765kV Dhule to Vadodara I 610:39:00 8 765 केवी इंदौर से वडोदरा-I 765kV Indore(PG) to Vadodara I 672:00:00 9 765 के वी धरमजयगड से जबलपुर-I 765kV D'garh to Jabalpur I 494:35:00 10 765 के वी धरमजयगड से जबलपुर-II 765kV D'garh to Jabalpur II 650:35:00 11 765 के वी धरमजयगड से जबलपुर-III 765kV D'garh to Jabalpur III 621:27:00 12 765 के वी धरमजयगड से जबलपुर-IV 765kV D'garh to Jabalpur IV 487:27:00 13 765 केवी सवनी से बलासपुर-I 765kV Seoni to Bilaspur-I 672:00:00 14 765 केवी सवनी से बलासपुर-II 765kV Seoni to Bilaspur-II 672:00:00 15 400 केवी भलाई से कोराडी 400kV Bhilai to Koradi 672:00:00 16 400 केवी भलाई से भावती 400kV Bhilai to Bhadravati 672:00:00 17 400 केवी भलाई से सयोन 400kV Bhilai to Seoni 672:00:00

18 400 के वी रायपुर से भावती -I 400kV Raipur to Bhadravati-I 672:00:00 19 400 के वी रायपुर से भावती –II 400kV Raipur to Bhadravati-II 672:00:00 20 400 के वी रायपुर से भावती –III 400kV Raipur to Bhadravati-III 672:00:00 21 400 के वी रायपुर से वधा–I 400kV Raipur to Wardha-I 672:00:00 22 400 के वी रायपुर से वधा–II 400kV Raipur to Wardha-II 664:36:00 23 400 के वी सातपुरा स े कोराडी 400kV Satpura to Koradi 672:00:00 24 400 केवी कोहापुर(GIS) से मापुसा-I 400kV Kolhapur(GIS)-Mapusa-I 672:00:00 25 400 केवी कोहापुर(GIS) से मापुसा-II 400kV Kolhapur(GIS)-Mapusa-II 672:00:00 26 400 के वी खंडवा से धुले-I 400kV Khandwa-Dhule-I 672:00:00 27 400 के वी खंडवा से धुले-II 400kV Khandwa-Dhule-II 672:00:00 28 400 के वी एसएसपी से धुले-I 400kV SSP-Dhule-I 331:55:00 29 400 के वी एसएसपी से धुले-II 400kV SSP-Dhule-II 396:20:00 30 400 केवी वापी से बोईसर 400kV Vapi-Boisar 649:44:00 31 400 केवी एसएसपी से राजगढ़-I 400kV SSP- Rajgarh -I 364:35:00 32 400 केवी एसएसपी से राजगढ़-II 400kV SSP- Rajgarh -II 386:25:00 33 400 केवी कासोर से राजगढ़-I 400kV Kasor- Rajgarh -I 544:06:00 34 400 केवी कासोर से राजगढ़-II 400kV Kasore- Rajgarh -II 547:25:00 35 400 केवी इंदौर से असोज-I 400kV Indore to Asoj-I 672:00:00 36 400 केवी इंदौर से असोज-II 400kV Indore to Asoj-II 669:46:00 37 400 केवी कोरबा से बीरसगं पुर I 400kV Korba-Birsigpur I 660:26:00 38 400 केवी कोरबा से बीरसगं पुर II 400kV Korba-Birsigpur II 672:00:00 39 400 केवी कोरबा से एसार महान 400kV Korba-Essar Mahan 646:56:00 40 400 केवी कोरबा से वंयाचल 400kV Korba-Vindhyachal 672:00:00 41 400 केवी नागदा से देहगाम-I 400kV Nagda to Dehgam I 663:07:00 42 400 केवी नागदा से देहगाम-II 400kV Nagda to Dehgam II 672:00:00

पिचम ेय भार ेषण क , मुबई WRLDC, Mumbai Anaulagnak 4.7 Annex-4.7 frvarI 2019 ko AMt maoM piScama xao`~ ko mau#ya jalaaSayaaoM ko str LEVEL OF MAJOR RESERVOIRS IN WESTERN REGION AT THE END OF MONTH OF FEBRUARY 2019

ivavarNa Particulars gau ] iva ina ila GUVNL map`iva]kM ila MPPGCL ena eca DI saI NHDC maraiva]kM ila MSEGCL

]ka[- Ukai gaaMQaIsaagar Gandhisagar [Midra saagar Indira Sagar kaoyanaa Koyna

Levels in Mtrs. str maITr maoM maah ko AMt maoM 93.06 384.26 256.27 650.14 At the end of the month ipClao vaYa- [sa maah ko Anau$p AaMkD,oM 96.16 389.87 251.53 651.39 Corresponding Figure of the month Last Year Western Region-Event Report for February 2019 Annexure 5 Outage Revival Outage Duration Category as per CEA Energy Unserved S.No Region Name of Elements Owner/Agency Event Generation Loss (MW) Load Loss (MW) standards (MU) Date Time Date Time Time

Tripping of 1. 400 KV Korba (W)-Marwa Ckt. At 400/220 kV Korba(W) substation,While charging 400 kV Korba(W)-Marwa all the other 400 kV 2. 400 KV Korba (W)-Raita Ckt. 1 WR CSPTCL 06/02/2019 22:00 06/02/2019 22:51 0:51 lines at Korba(W) tripped on Over Voltage. 210 MW Korba(W) Units 3&4 also tripped during the 337 Nil GD-1 Nil 3. 400 KV Korba (W)-Bhilai Ckt. event. 4. 210 MW Korba(W) Unit 3&4

Tripping of 2 WR 1.800 kV HVDC Champa-Kurukshetra Pole 1 PGCIL 07/02/2019 21:40 07/02/2019 22:06 0:26 800 kV HVDC Champa-Kurukshetra BI-Pole tripped due to TOVC operation at Kurukshetra end. Nil Nil GI-2 Nil 2.800 kV HVDC Champa-Kurukshetra Pole 2

At 765/400 kV Bhopal substation,765 kV Bhopal-Indore tripped at Indore end on B phase to earth Tripping of fault but from the Bhopal end line was not tripped on distance protection due to the problem in B 1.765 kV Bhopal-Indore 3 WR BDTCL 14/02/2019 1:58 14/02/2019 5:39 3:41 phase CVT. Since the DEF setting was 1.5 second, 765 kV Bhopal-Jabalpur tripped from Jabalpur end Nil Nil GI-2 Nil 2.765 kV Bhopal-Jabalpur on Zone 3 distance protection operation and the line tripped at Bhopal end due to the DT receipt 3.765 kV Bhopal Bus reactor from Jabalpur on OverVoltage. 765 kV Bus reactor tripped on differential protection operation.

Tripping of 1. 400 kV ACBIL-BILASPUR 1 2. 400 kV MCCPL-Bilaspur1 3. 300 MW MCCPL Unit 1 ACBIL/MCCPL/ Due to the tripping of 400 kV Bilaspur-ACBIL and 400 kV Bilaspur-MCCPL on B-E fault, ACBIL and 4 WR 4. 30 MW Chakabura Unit 1 24/02/2019 22:14 24/02/2019 22:53 0:39 483 Nil GD-1 Nil SCPL MCCPL generators tripped due to the loss of evacuation path and got blacked out. 5. 30 MW Chakabura Unit 2 6. 135 MW ACBIL Unit 2 7. 50 MW SCPL Unit 2

Disclaimer : The Above details are based on the preliminary/flash report of the event and may change after finalisation of the detailed report.The qunatum of load/generation loss is based on details given by SLDC and utility and may vary later with updated details. Annexure-6 Status of healthiness of SERs/DRs S.l. Name of Constituent Date of No. Receipt 1 PGCIL,WRTS-I 05.03.2019 2 PGCIL,WRTS-II 05.03.2019 3 MPPTCL 02.01.2019 4 NTPC 02.10.2018 5 CSPTCL 05.03.2019 6 GETCO 05.10.2018 7 MSETCL 05.03.2019 8 DD/DNH 17.08.2018 9 GOA 02.10.2018 10 NPCIL 01.03.2019 11 NCA/SSP 05.03.2019 12 NHDC 04.10.2018 13 Jindal PL 17.08.2018 14 CGPL 05.10.2018 15 DB POWER 07.08.2018 16 KWPCL 01.03.2019 17 ACBIL/TRN ENERGY 04.10.2018 18 KSK 02.01.2019 19 GMR CHHATTISHGARH 21.08.2018 20 JNSTPS 05.10.2018 21 MB POWER 09.08.2018 22 SASAN UMPP 21.08.2018 23 NSPCL 21.08.2018 24 RGPPL 06.10.2018 25 SUGEN/DGEN 01.02.2019 26 RKM POWER 05.10.2018 27 ESSAR POWER 09.08.2018 28 BDTCL/JTCL/RTCL 08.10.2018 29 RELIANCE TRANSMISSION 02.10.2018 30 ADANI POWER 05.02.2019 31 JHABUA POWER 04.10.2018 32 EPTCL 05.10.2018 33 TPGL 01.03.2019

***** Annexure-7.1 Status of Reactors Sl. 400 kV Size Implementing Expected date of No. Sub/Stn. (MVAr agency commissioning ) 1 Nanded 125 MSETCL Commissioned on 02/2018 2 Kolhapur 125 MSETCL Commissioned on 02/2018 3 Akola 125 MSETCL Commissioned on 02/2018 4 ISP 125 NHDC December – 2019 expected

5 Satpura-ISP 50 MPPGCL Apr-2019 Line Rx(at Satpura end) 6 Bus Reactor at 330 PGCIL Commissioned on 24.04.2018 New Parli(PG)

7 Bus Reactor at 80 DIL Commissioned on 23.05.2018 Dhariwal

8 Warora(PS) 80 PWTL/Maharashtra Commissioned on 09-05-2018

9 Warora(PS) 80 PWTL/Maharashtra Commissioned on 09-05-2018

10 Warora(PS) 330 PWTL/Maharashtra Commissioned on 18-05-2018

11 Warora(PS) 330 PWTL/Maharashtra Commissioned on 18-05-2018

12 New Parli 330 PPTL/Maharashtra Commissioned on 21-05-2018

13 New Parli 330 PPTL/Maharashtra Commissioned on 21-05-2018

14 Warora(PS) 330 PWTL/Maharashtra Commissioned on 10-05-2018

15 KAPS 3&4 125 NPCIL/Gujarat Commissioned on 14-05-2018

16 EPTCL/ Commissioned on 21.07.2018 50 EPTCL Chhattisgarh

17 EPTCL / Commissioned on 27.07.2018 50 EPTCL Chhattisgarh

************** Annexure 7.2 Status of Transmission schemes: 765/400 kV and above The updated status on various ongoing transmission schemes for the year 2018-19 as per the current information available is as follows: - Sl. Name of the Line Ckt km Target Remarks No. Completion Date Powergrid 1 LILO of Lonikhand-Kalwa at Navi 16 Mar 19 Mumbai GIS-JSL/LS Cable 2 18 Commissioned Parli(PG)-New Parli(PG) ckt I & II on 21.04.2018

3 765kV Vindhyachal - Jabalpur 749 Charged on D/C 29.12.2018

4 765kV D/C Gadarwara STPP - 453.6 Commissioned in Warora Oct 18 5 800 kV Raigarh-Pugalur HVDC 3676 March-19 Work under Bipole progress

6 400kV D/C Banaskantha - 43.4 Charged on Sankheri (GETCO) 18.12.2018 7 765kV D/C Banaskantha - 293.3 March 2018 Chittorgarh 8 400kV D/C Banaskantha 132 June 2019 (Radhanesda) - Banaskantha (PG) 9 765kV Bhuj-Banaskamta DC 583 Mar 19 10 400 kV Mundra UMPP – Bhuj DC 190 Mar 19

11 400 kV D/c Wardha- 347 February 19 Work is in Aurangabad(Upgradable to 1200 progress kV) 12 765 kV D/C Jharsuguda- 149 Charged on Dharamjaigarh line 2 01.11.18 14 LILo of 400Kv D/C Wardha – Parli 196 Commissioned at Warora on 16.05.2018

15 765Kv D/C Warora - Parli 698 Commissioned on 04.06.2018

16 765Kv D/C Parli - Solapur 236 Commissioned on 27.04.2018

17 400Kv D/C Parli - Parli 37 Commissioned on 27.04.2018

Chhattishgarh 1 LILO of 400kV Raita-Jagdalpur at 2 August 19 Order placed on Dhamtari 21.02.18

2 LILO of 220 kV Raigarh-Budipadar - Commissioned at 400 kV PGCIL S/s Raigarh. Idle on 09.11.18 charged on 11.8.2015 for anti theft reason 3 220 kV Barsoor-Jagdalpur 175 Mar 19 4 2nd circuiting of 220 KV Korba- 155 Commissioned Bishrampur line(DCSS) on 04.09.18 Gujarat 1 400 kV D/C Vadinar-Amreli line 116.85 Aug 19 2 400kV APL-Hadala LILO to Halvad 89.40 June 19 3 400 kV D/C Amreli-Kasor line 164.30 June 19 4 400kV D/C Vadavi - Halvad Line 146.4 March 19 5 400 kV Varsana-Halvad 143.38 June 19 6 400 kV Wanakbori-Soja DC 121.75 Mar 19 8 7 400 kV Soja-Zerda DC 268.92 Mar 19 8 400 kV Hadala-Shapar D/c 124.34 Mar 19 9 400 kV Bhogat- Kalawad D/C 260.57 Mar 20 10 400 kV Bhachuunda-Varsana D/c 276.16 June 20 11 LILO of both ckt. of 400kV D/C 25.76 March 2019 Mundra - Zerda line at 400kV Charanka S/s

Madhya Pradesh

1 400 KV DCDS (Quad moose) 282 Jan 19 line from Shri Singa Ji TPS (Stage-II) to Pithampur 2 400 KV DCDS (Quad moose) 140 Nov 19 line from Pithampur to Badnawar

3 LILO of both circuit of 400KV 16.3 Feb 19 Nagda-Rajgarh line at 400KV Substation Badnawar

Maharashtra (STU) 1 400 kV Bableshwar-Kudus D/C 150 March 19 Forest clearance (Quad) awaited, severe ROW problem

2 New Parli(PG)-Solapur ckt-I & II 118 Commissioned on 24.04.2018 3 400 KV D/C Jejuri-Hinjewadi March 19 101 Line(Jejuri-Wainjhar) Package-I.

4 400 KV D/C Jejuri-Hinjewadi Line Mar 19 92.67 (Wainjhar- Hinjewadi) Package-II.

5 400 KV DCQ BBLR-Kudus line March 19 306.46 (upto )

Other ISTS lines 1 Raigarh (Kotra) - Champa (Pool) 765 Commissioned 96 KV S/C on 31.08.18 2 Champa (Pool) - Dharamjaygarh Commissioned 51 765 KV S/C on 21.07.18 3 LILO of one ckt of Aurangabad - 130 Feb 19 Padghe 765 KV D/C line at Pune 4 Rajnandgaon - Warora 765 KV D/C 532 Feb 19 5 Commissioned Sipat STPS - Bilaspur 765 KV S/C 23 on 06.08.18 6 400kV D/C Mahan Sipat 674 Oct 2018 transmission line

7 Jharsuguda – Raipur 765 kV D/C March 19 Ready to charge 610 (hexa) line (Sterlite) 8 765KV D/C Khandwa Pool (KTL)- 180 March 19 Indore (PGCIL) Line(Sterlite)

9 765KV D/C Khandwa Pool (KTL)- 379 March 19 Dhule (BDTCL) Line(Sterlite)

10 LILO of one CKT of 400KV D/C Commissioned Khandwa-Rajgarh at NTPC, 14 on 06.07.18 Khargone (Sterlite) 11 400KV D/C Khargone TPP Switchyard (NTPC)-Khandwa Pool 49 July 2019 (KTL) Line(Sterlite) 12 CWRTL, 400 kV Gwalior(PG)-Morena -I 48 03-05-2018 Adani/MP 13 CWRTL, 400 kV Gwalior(PG)-Morena -II 48 03-05-2018 Adani/MP 14 PWTL/Maha 400 kV Wardha-Warora-I 98 09-05-2018 rashtra 15 PWTL/Maha 400 kV Warora(PS)-Parli(PG)-I 98 13-05-2018 rashtra 16 PWTL/Maha 400 kV Wardha-Warora-II 98 09-05-2018 rashtra 17 PWTL/Maha 400 kV Warora(PS)-Parli(PG)-II 98 14-05-2018 rashtra

The WR utilities may intimate the current status on above.

****************** Annexure 7.3 Status of Generating Units in WR The status regarding Generating units, commissioned /expected to be commissioned during the current year 2018-19 is as below: Name of the Power Projects Unit Capacity Date of Commissioning No. (MW) /Schedule Date Gujarat WTPS 8 800 March 19 Chhattisgarh NIL Maharashtra NIL

Madhya Pradesh

Essar Power MP Ltd(Mahan) 2 600 Synchronized on 03.08.2017 SHINGAJI 3 660 CoD on 18/11/2019

SHINGAJI 4 660 Synchronized on 27.12.2018

Central sector/IPP

RKM UNIT 4 300 Dec-18

NTPC LARA UNIT 1 800 Mar 19

NTPC GADARWADA UNIT 1 800 March 19

NTPC SHOLAPUR UNIT 2 660 Mar-19

KSK UNIT 5 600 Dec-18

Essar Mahar Unit 2 600 CoD on 07.10.2018

******** ANNEXURE-8.1 REPORT ON MOCK DRILL FOR CRISIS MANAGEMENT PLAN IN POWER SECTOR for the quarter ending ……………….

1. Name of Power Utility / Generating Station :

2. Date / Time of Mock-drill :

3. Location site of Mock-drill :

4. Observers : (Indicate names of Team designated Leader / Members to handle crisis situation)

5. Scenario of mock emergent situation :

6. Objective :

7. Chronological order of events logged :

Time Events Response Time

8. Observations on effectiveness of Mock Drill :

9. Recommendations / Suggestions on the observations (S. No. 8) :

Signature of Designated Signature of (Safety / Security Officer) (Head O & M of Plant)

Dated…………………… Dated…………………… Annexure -8.2 B Reporting Format to the PSDF Project Monitoring Group 1. Name of the Scheme 1.1 Name of the substation and its Location 1.2 Executing Agency 1.3 State/Region

2. Date of Sanction order 2.1 Date of Agreement of Entity with State Govt./NLDC 2.2 Total Approved Cost of the Scheme

2.3 Approved Grant by Monitoring Committee ( Rs. In Lakhs) 2.4 Date of Requisition by the Entity 2.4.a) date and Reference of LOA 2.4.b) Amount of LOA 2.5 Date of Disbursement and amount 2.5.1 : Ist Installment 2.5.2: IInd installment 2.5.3: IIIrd installment 2.6 Date of Scheduled completion of Work 2.7 Date of handing over of Site to entity (in case of turnkey projects)

Report for the Month of ____MM / YY______Quantity Qty. AS CUMMULATIVE No. Supply Description Received PER LOA PROGRESS Till date BALANCE Remarks during Month Sch. Act. 1 item Details 1.1 1.2 ….

works as per Progress CUMMULATIVE Erection Description Balance LOA During Month PROGRESS Till date

2 work details 2.1 2.2 ….

3 Others

Signature with seal of the Nodal Officer

Timelines for implementation of new emission norms for Thermal Power Plants (notified on 07.12.2015) as per direction issued on 11.12.2017 and 06.04.2018 u/s 5 of EP Act, 1986

Sl. Name of Thermal State FGD/ Unit-1 Unit-2 Unit-3 Unit-4 Unit-5 Unit-6 Unit-7 Unit-8 Unit-9 Unit- Unit- Unit- Unit-13 No. Power Plant ESP 10 11 12

1 Vizag TPP, Andhra FGD Jun-20 Sep-19 HNPCL Pradesh

ESP 2 Damodaram Andhra FGD Dec-20 Dec-19 Sanjeeviah TPS, Pradesh APPDCL ESP Dec-20 Dec-19 3 Rayalseema TPS, Andhra FGD Dec-21 Sep-21 Sep-20 Jun-21 Jun-20 APGENCO Pradesh

ESP Dec-21 Sep-21 Sep-20 Jun-21 Jun-20 4 Dr. N. Tata Rao Andhra FGD Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 TPS Pradesh

ESP Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 5 Sembcorp Gayatri Andhra FGD Dec-21 Sep-21 Pvt Ltd Pradesh

ESP 6 Painampuram Andhra FGD Dec-21 Sep-21 TPS, APGENCO Pradesh ESP 7 Simhadri NTPC Andhra FGD Mar-22 Jun-22 Sep-22 Dec-22 Pradesh

ESP Sep-22 Dec-22 8 Thamminapatnam Andhra FGD Complying Complying TPS, Meenakshi Pradesh Energy Ltd. ESP 9 Simhapuri TPS, Andhra FGD Complying Complying Complying Complying SEPL Pradesh

ESP 10 Bongaigaon Assam FGD Complying Complying NTPC

ESP 11 Barh NTPC Bihar FGD Sep-21 Mar-22 ESP 12 Nabi Nagar TPS, Bihar FGD Dec-21 Dec-22 NTPC ESP Dec-22 13 Kahalgaon TPS, Bihar FGD Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 NTPC ESP Dec-22 Dec-22 Dec-22 Dec-22 14 Muzaffarpur TPS, Bihar FGD Dec-20 Dec-20 Dec-22 Dec-22 NTPC-BSEB ESP Dec-20 Dec-20 Dec-22 Dec-22 15 Barauni TPS, Bihar FGD Dec-20 Dec-20 BSEB ESP Dec-20 Dec-20 16 Bandakhar TPP, Chhattisgarh FGD Mar-20 Maruti CCPL ESP 17 Raikheda TPP, Chhattisgarh FGD Jun-20 Sep-20 GMR

ESP 18 Baradarha TPS, Chhattisgarh FGD Jun-21 Sep-20 DB Power

ESP 19 Binjkote TPP, SKS Chhattisgarh FGD Sep-20 Power

ESP Sep-20 20 Nawapara TPP, Chhattisgarh FGD Complying Sep-20 TRN Energy

ESP Sep-20 21 Marwa TPS, CSEB Chhattisgarh FGD Jun-21 Mar-21

ESP 22 Lanco Chhattisgarh FGD Mar-21 Mar-21 Amarkantak TPP

ESP 23 Tamnar TPP, Chhattisgarh FGD Mar-21 Dec-21 Mar-22 Jun-22 Jindal

ESP 24 BALCO TPS Chhattisgarh FGD Sep-21 Jun-21

ESP Sep-21 Jun-21 25 Dr. Shyama Chhattisgarh FGD Jun-21 Sep-21 PMTPS, CSPGCL ESP 26 Korba West Extn Chhattisgarh FGD Dec-20 Dec-20 Dec-20 Dec-20 Sep-21 TPS

ESP Dec-20 Dec-20 Dec-20 Dec-20 27 Sipat NTPC Chhattisgarh FGD Dec-22 Dec-22 Dec-21 Dec-21 Dec-21

ESP 28 Uchpinda TPP, Chhattisgarh FGD Mar-22 Dec-21 RKM Power

ESP 29 Avantha Bhandar, Chhattisgarh FGD Mar-22 KWPCL

ESP 30 Akaltara TPS, Chhattisgarh FGD Jun-22 Mar-22 KSK Mahanadi ESP 31 OP Jindal TPS Chhattisgarh FGD Mar-22 Mar-22 Jun-22 Jun-22

ESP 32 Korba STPS, Chhattisgarh FGD Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 NTPC

ESP Dec-22 Dec-22 Dec-22 Dec-22 33 Bhilai TPS, NTPC Chhattisgarh FGD Dec-22 Dec-22 & SAIL

ESP 34 Chakabura TPP, Chhattisgarh FGD Complying ACBIL

ESP 35 Kasaipalli TPP, Chhattisgarh FGD Complying Complying ACBIL

ESP 36 Swastik Korba Chhattisgarh FGD Complying TPP, ACBIL

ESP 37 SVPL TPP, S V Chhattisgarh FGD Complying Power Ltd

ESP 38 Ratiza TPS, SCPL Chhattisgarh FGD Complying Complying

ESP 39 Katghora TPP, Chhattisgarh FGD Complying Vandana Vidyut

ESP 40 Korba II TPS, Chhattisgarh FGD Dec-20 Dec-20 Dec-20 Dec-20 CSPGCL

ESP Dec-20 Dec-20 Dec-20 Dec-20 41 Korba III TPS, Chhattisgarh FGD Dec-20 Dec-20 CSPGCL

ESP Dec-20 Dec-20 42 Rajghat TPS Delhi FGD Retired Retired ESP Retired Retired 43 Badarpur TPS, Delhi FGD Jul-18 Jul-18 Jul-18 Jul-18 Jul-18 NTPC Ltd

ESP Jul-18 Jul-18 Jul-18 Jul-18 Jul-18 44 Mundra UMTPP, Gujarat FGD Jun-20 Mar-21 Jun-21 Mar-22 Mar-22 Tata Power (CGPL) ESP 45 Salaya TPP, Essar Gujarat FGD Jun-21 Mar-21 ESP 46 Gandhi Nagar Gujarat FGD Retired Retired Dec-21 Dec-21 Dec-21 TPS ESP Retired Retired 47 Kutchh Lignite Gujarat FGD Dec-21 Dec-21 Dec-21 Complying TPS

ESP Dec-21 Dec-21 Dec-21 Dec-20 48 Ukai TPS Gujarat FGD Retired Retired Dec-21 Dec-21 Dec-21 Mar-22 ESP Retired Retired Dec-21 Dec-21 Dec-21 Mar-22 49 Wanakbori TPS Gujarat FGD Dec-21 Dec-21 Dec-21 Dec-21 Dec-21 Dec-21 Dec-21 ESP Dec-21 Dec-21 Dec-21 Dec-21 Dec-21 Dec-21 Dec-21 50 Sikka TPS, GSEL Gujarat FGD Retired Retired Jan-22 Jan-22 ESP Retired Retired 51 Mundra TPS, Gujarat FGD Dec-22 Dec-22 Sep-22 Sep-22 Jun-22 Mar-22 Complying Complying Complying Adani Power

ESP 52 Sabarmati, Gujarat FGD Dec-22 Dec-22 Dec-22 Torrent Power

ESP 53 Surat Lignite TPS, Gujarat FGD Complying Complying Complying Complying GIPCL

ESP Sep-20 Dec-20 54 Akrimota Lignite Gujarat FGD Complying Complying TPS

ESP Sep-20 Dec-20 55 Bhavnagar Lignite Gujarat FGD Complying Complying TPP

ESP 56 Sabarmati C - Gujarat FGD Apr-18 Apr-18 TPS, Torrent Power ESP Apr-18 Apr-18 57 Mahatma Gandhi Haryana FGD Dec-19 Dec-19 TPS, CLP

ESP 58 Indira Gandhi Haryana FGD Dec-19 Dec-19 Dec-19 STPP, NTPC

ESP Dec-19 Dec-19 Dec-19 59 Panipat TPS Haryana FGD Dec-19 Dec-19 Dec-19 Dec-19 ESP Dec-19 Dec-19 Dec-19 60 Yamuna Nagar Haryana FGD Dec-19 Dec-19 TPS ESP Dec-19 Dec-19 61 Rajiv Gandhi TPS Haryana FGD Dec-19 Dec-19 ESP Dec-19 Dec-19 62 Tenughat TPS Jharkhand FGD Dec-20 Dec-20 ESP Dec-20 63 Maithon TPP, Jharkhand FGD Sep-21 Jun-22 Tata Power

ESP 64 Kodarma TPP, Jharkhand FGD Dec-21 Dec-21 DVC ESP 65 Mahadev Prasad, Jharkhand FGD Jun-22 Jun-22 Adhunik

ESP 66 Bokaro A TPS, Jharkhand FGD Jun-22 DVC ESP Jun-22 67 Chandrapura Jharkhand FGD Retired Retired Dec-18 Dec-22 Dec-22 DVC ESP Retired Retired Dec-18 68 Bokaro B TPS, Jharkhand FGD Retired Retired Dec-20 DVC ESP Retired Retired Dec-20 69 Patratu TPS Jharkhand FGD Retired Retired Retired Retired Retired Retired Retired Retired Retired Retired ESP Retired Retired Retired Retired Retired Retired Retired Retired Retired Retired 70 Jojobera TPS, Tata Jharkhand FGD Dec-20 Dec-20 Power Co.

ESP Dec-20 Dec-20 71 Bellary TPS Karnataka FGD Dec-20 Jun-21 Dec-21 ESP 72 Raichur TPS Karnataka FGD Mar-21 Jun-21 Sep-21 Dec-21 Mar-22 Jun-22 Sep-22 Dec-22 ESP Mar-21 Jun-21 Sep-21 Dec-21 Mar-22 Jun-22 Sep-22 Dec-22 73 Yermarus TPP, Karnataka FGD Dec-21 Dec-22 KPCL ESP Dec-22 74 Udupi TPP, Adani Karnataka FGD Mar-22 Jun-22 Power

ESP 75 Torangallu TPS Karnataka FGD Jun-22 Sep-22 Extn, Jindal

ESP Jun-22 Sep-22 76 Torangallu TPS, Karnataka FGD Complying Complying Jindal

ESP 77 Kudgi NTPC Karnataka FGD Jun-22 Sep-22 Dec-22 ESP Sep-22 Dec-22 78 Seoni TPP, Jhabua Madhya FGD Mar-20 Pradesh

ESP 79 Nigri TPP, J.P.V.L Madhya FGD Jun-20 Sep-20 Pradesh

ESP 80 Mahan TPP, Essar Madhya FGD Dec-20 Power Pradesh

ESP 81 Amarkantak TPS, Madhya FGD Mar-21 MPPGCL Pradesh

ESP Mar-21 82 Sanjay Gandhi Madhya FGD Mar-21 Mar-21 Jun-21 Jun-21 Mar-21 TPS Pradesh

ESP Mar-21 Mar-21 Jun-21 Jun-21 Mar-21 83 Satpura TPS Madhya FGD Dec-20 Dec-20 Dec-20 Dec-20 Mar-21 Mar- Pradesh 21

ESP Dec-20 Dec-20 Dec-20 Dec-20 Mar-21 Mar- 21 84 Shri Singhaji TPP Madhya FGD Mar-21 Mar-21 Pradesh

ESP 85 Vindhyachal Madhya FGD Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Jun-21 Jun-21 Sep-21 Sep-21 Dec- Dec- Complying NTPC Pradesh 21 21

ESP Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Sep-21 Sep-21 86 Sasan UMTPP, Madhya FGD Sep-21 Jun-21 Mar-22 Mar-22 Dec-21 Sep-21 RPL Pradesh ESP 87 Annupur TPS, MB Madhya FGD Mar-22 Jun-22 Power Pradesh

ESP 88 Niwari TPP, BLA Madhya FGD Complying Pvt. Ltd. Pradesh

ESP 89 Bina TPS, BPSCL Madhya FGD Complying Complying Pradesh

ESP 90 Tata Power Maharashtra FGD Mar-18 Complying Tombay TPS

ESP Mar-18 91 Chandrapur Maharashtra FGD Retired Retired Mar-21 Mar-21 Mar-21 Mar-21 Mar-21 Mar-21 Mar-20 STPS, Mahagenco

ESP Retired Retired Mar-21 92 Koradi TPS Maharashtra FGD Retired Mar-21 Mar-21 Mar-21 Mar-21 Dec-20

ESP Retired Mar-21 Dec-20 93 Mouda NTPC Maharashtra FGD Dec-22 Dec-22 Dec-22 Dec-20

ESP Dec-22 Dec-22 Dec-20 94 Solapur NTPC Maharashtra FGD Dec-20

ESP Dec-20 95 Tirora TPS, Adani Maharashtra FGD Mar-22 Dec-21 Sep-21 Jun-21 Mar-21 Power ESP 96 Bhusawal TPS Maharashtra FGD Retired Mar-21 Mar-21 Mar-21

ESP Retired Mar-21 Mar-21 97 Khaperkheda TPS Maharashtra FGD Mar-21 Mar-21 Mar-21 Mar-21 Mar-21

ESP Mar-21 Mar-21 Mar-21 98 Nasik TPS, Maharashtra FGD Mar-21 Mar-21 Mar-21 Mahagenco

ESP Mar-21 Mar-21 99 Parli TPS, Maharashtra FGD Retired Mar-21 Mar-21 Mar-21 Mar-21 Mar-21 Mahagenco

ESP Retired Mar-21 Mar-21 Mar-21 Mar-21 100 Nashik Rattan Maharashtra FGD Mar-21 Mar-21 Dec-22 Dec-22 Dec-22 India TPS

ESP Mar-21 Mar-21 Dec-22 Dec-22 Dec-22 101 Butibori TPS, Maharashtra FGD Jun-21 Mar-21 Vidarbha IL

ESP 102 Wardha Warora Maharashtra FGD Sep-21 Sep-21 Dec-21 Dec-21 TPP, WPCPL

ESP 103 Dhariwal TPP Maharashtra FGD Mar-22 Mar-22

ESP 104 EMCO Warora Maharashtra FGD Mar-22 Mar-22 TPS, GMR EEL

ESP 105 Dahanu TPS, Maharashtra FGD Complying Complying BSES Ltd.

ESP 106 JSW Ratnagiri Maharashtra FGD Complying Complying Complying Complying TPP, JSW Energy

ESP 107 Paras TPS Maharashtra FGD Complying Complying

ESP Mar-21 Mar-21 108 Mihan TPS, Maharashtra FGD Complying Abhijeet MADC Nagpur Energy Pvt. Ltd. ESP 109 Bela TPS, Ideal Maharashtra FGD Complying Energy PL

ESP 110 Amravati TPS, Maharashtra FGD Complying Complying Complying Complying Complying Ratan Power

ESP 111 Gupta Energy P Maharashtra FGD Dec-20 Dec-20 Ltd. Phase-I

ESP Dec-20 Dec-20 112 Derang TPP, Odisha FGD Mar-21 Mar-21 Jindal IPL ESP 113 Kamalanga TPS, Odisha FGD Dec-21 Dec-21 Sep-21 GMR ESP 114 IB Valley TPS, Odisha FGD Sep-21 Sep-21 OPGCL ESP Sep-21 Sep-21 115 IND Barath TPP Odisha FGD Mar-22 ESP Mar-22 116 Sterlite TPP, Odisha FGD Mar-22 Sterlite Energy

ESP 117 Talcher STPS, Odisha FGD Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 NTPC ESP Dec-22 Dec-22 118 Talcher (Old) TPS, Odisha FGD Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 NTPC

ESP Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 119 Goindwal Sahib, Punjab FGD Apr-20 Feb-20 GVK Power ESP 120 Talwandi Sabo Punjab FGD Dec-19 Dec-19 Dec-19 TPP ESP 121 Nabha Power, Punjab FGD Dec-19 Dec-19 Rajpura TPP

ESP 122 Guru Hargobind Punjab FGD Dec-19 Dec-19 Dec-19 Dec-19 TPS, Lehra Mohabbat ESP Dec-19 Dec-19 Dec-19 Dec-19 123 Guru Nanak Dev Punjab FGD Retired Retired Retired Retired TPS, Bhatinda

ESP Retired Retired Retired Retired 124 Guru Gobind Punjab FGD Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Singh TPS, Ropar

ESP Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 125 Chhabra TPP, Rajasthan FGD Dec-21 Oct-21 Aug-21 Aug-21 Apr-20 RRVUNL ESP Dec-21 Oct-21 Aug-21 Aug-21 Apr-20 126 Kawai TPS, Adani Rajasthan FGD Aug-20 Jun-20 Power

ESP 127 Kalisindh TPS Rajasthan FGD Jun-21 Apr-21 ESP 128 Suratgarh TPS Rajasthan FGD Dec-22 Oct-22 Aug-22 Jun-22 Apr-22 Feb-22 ESP Feb-22 129 Kota TPS Rajasthan FGD Dec-20 Dec-20 Dec-20 Dec-20 Dec-22 Dec-22 Oct-22 ESP Dec-20 Dec-20 Dec-20 Dec-20 Dec-22 Dec-22 130 Jalipa Kapurdi, Rajasthan FGD Complying Complying Complying Complying Complying Complying Complying Complying JSW Rajwest Power Ltd ESP Dec-22 Dec-22 Aug-22 Aug-22 Apr-22 Apr-22 Dec-21 Dec-21 131 Barsingsar Rajasthan FGD Complying Complying Lignite, NLC

ESP Aug-20 Apr-20 132 Giral Lignite TPS, Rajasthan FGD Complying Complying RRVUNL

ESP 133 North Chennai Tamilnadu FGD Dec-19 Sep-20 Expn. TPS

ESP 134 Tuticorin (JV) TPP Tamilnadu FGD Dec-21 Jun-20 ESP Dec-21 Jun-20 135 TAQA Neyveli Tamilnadu FGD Jun-20 TPS ESP 136 Mettur TPS Extn Tamilnadu FGD Dec-20 ESP 137 Neyveli TPS - I, Tamilnadu FGD Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 NLC ESP Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 Sep-19 138 Neyveli Extn TPS, Tamilnadu FGD Jun-21 Dec-21 NLC ESP 139 Neyveli TPS-2, Tamilnadu FGD Dec-21 Sep-21 Jun-21 Mar-22 Jun-22 Sep-22 Dec-22 NLC ESP 140 Neyveli TPS-2 Tamilnadu FGD Complying Complying Expn, NLC

ESP 141 North Chennai Tamilnadu FGD Dec-22 Jun-22 Mar-22 TPS ESP Dec-22 Jun-22 Mar-22 142 Vallur TPP, NTEC Tamilnadu FGD Jun-22 Sep-22 Dec-22 ESP 143 Muthiara TPP, Tamilnadu FGD Sep-22 Dec-22 Coastal Energen

ESP 144 M/s IL & FS Tamilnadu FGD Complying Complying Tamil Nadu Power Company Ltd. ESP 145 Mettur TPS Tamilnadu FGD Complying Complying Complying Complying

ESP Mar-21 Jun-21 Sep-21 Dec-21 146 Ennore TPS, Tamilnadu FGD Retired Retired Retired Retired Retired Tangedco ESP Retired Retired Retired Retired Retired 147 Tuticorin TPS, Tamilnadu FGD Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 Tangedco

ESP Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 148 Tuticorin (P) TPS, Tamilnadu FGD Dec-20 Dec-20 IND Barath

ESP Dec-20 Dec-20 149 Singareni TPP, Telangana FGD Dec-19 Sep-19 SCCL ESP 150 Kothagudem TPS Telangana FGD Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-20 Dec-20 Sep- 19 ESP Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-20 Dec-20 Sep- 19 151 Kakatiya TPS, Telangana FGD Mar-20 Jun-20 TSGENCO

ESP Mar-20 152 Ramagundam Telangana FGD Mar-22 Mar-22 Jun-22 Jun-22 Sep-22 Sep-22 Dec-22 STPS, NTPC

ESP Mar-22 Jun-22 Sep-22 Sep-22 Dec-22 153 Ramagundem-B Telangana FGD Dec-19 TPS, TSGENCO

ESP Dec-19 154 Dadri NCTPP, Uttar FGD Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 Dec-19 NTPC Pradesh ESP 155 Prayagraj TPP, Uttar FGD Apr-20 Jun-20 Feb-20 PPGCL Pradesh

ESP Feb-20 156 Unchahar TPS, Uttar FGD Dec-22 Dec-22 Oct-22 Oct-22 Apr-22 Aug-20 NTPC Pradesh

ESP Dec-22 Dec-22 Oct-22 Oct-22 Apr-22 Aug-20 157 Lalitpur TPS, Uttar FGD Dec-20 Feb-21 Oct-21 LPGC Pradesh

ESP 158 Rihand NTPC Uttar FGD Feb-22 Dec-21 Oct-21 Apr-21 Feb-21 Dec-20 Pradesh

ESP Feb-22 Dec-21 Oct-21 Apr-21 159 Singarauli NTPC Uttar FGD Dec-21 Dec-21 Aug-21 Aug-21 Apr-21 Feb-21 Dec-20 Pradesh

ESP Dec-21 Dec-21 Aug-21 Aug-21 Apr-21 Feb-21 Dec-20 160 Anpara TPS, Uttar FGD Oct-22 Aug-22 Jun-22 Apr-22 Feb-22 Jun-21 Apr-21 UPRVUNL Pradesh

ESP Oct-22 Aug-22 Jun-22 Apr-22 Feb-22 Apr-21 161 Rosa TPP Ph-1 Uttar FGD Dec-21 Dec-21 Oct-21 Oct-21 Pradesh

ESP Dec-21 Dec-21 162 Harduaganj TPS Uttar FGD Retired Dec-19 Dec-19 Dec-19 Pradesh

ESP Retired Dec-19 163 Parichha TPS Uttar FGD Dec-20 Dec-20 Apr-22 Apr-22 Feb-22 Dec-21 Pradesh ESP Dec-20 Dec-20 Apr-22 Apr-22 Feb-22 Dec-21 164 Obra TPS Uttar FGD Retired Retired Dec-20 Dec-20 Aug-22 Oct-22 Dec- Jun- Apr-22 Pradesh 22 22

ESP Retired Retired Dec-20 Dec-20 Oct-22 Dec- Jun- Apr-22 22 22 165 Anpara C TPS, Uttar FGD Aug-22 Jun-22 Lanco Power Pradesh

ESP 166 Panki TPS, Uttar FGD Dec-18 Dec-18 UPRVUNL Pradesh

ESP Dec-18 Dec-18 167 Barkhera TPS, Uttar FGD Complying Complying Bajaj Power Co. Pradesh ESP Sep-21 Mar-21 168 Khambarkheda Uttar FGD Complying Complying TPS, Bajaj Power Pradesh Co. ESP Sep-21 Sep-21 169 Kundarki TPS, Uttar FGD Complying Complying Bajaj Power Co. Pradesh

ESP Sep-21 Mar-21

170 Maqsoodpur TPS, Uttar FGD Complying Complying Bajaj Power Co. Pradesh

ESP Sep-21 Mar-21 171 Utraula TPS, Bajaj Uttar FGD Complying Complying Power Co. Pradesh

ESP Sep-21 Mar-21 172 Tanda TPS, NTPC Uttar FGD Dec-20 Dec-20 Dec-20 Dec-20 Pradesh

ESP Dec-20 Dec-20 Dec-20 Dec-20 173 Sagardighi TPS, West Bengal FGD Dec-20 Mar-21 Mar-22 Mar-20 WBPDC

ESP Dec-20 Mar-21 174 Kolaghat TPS West Bengal FGD Jun-22 Mar-21 Sep-21 Mar-22 Jun-21 Dec-21

ESP Jun-22 Mar-21 Sep-21 Mar-22 Jun-21 Dec-21 175 Durgapur Steel West Bengal FGD Jun-21 Jun-21 TPS, DVC

ESP 176 Mejia TPS, DVC West Bengal FGD Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Sep-21 Sep-21

ESP Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Sep-21 Sep-21 177 Southern REPL West Bengal FGD Mar-22 Dec-21 TPS, CESC

ESP 178 Santaldihi TPS West Bengal FGD Retired Retired Retired Retired Mar-21 Dec-21

ESP Retired Retired Retired Retired Mar-21 Dec-21 179 D.P.L TPS West Bengal FGD Retired Retired Retired Mar-22 Jun-22

ESP Retired Retired Retired Mar-22 Jun-22 180 D.P.L Exn. TPS West Bengal FGD Mar-22

ESP Mar-22 181 Raghunathpur West Bengal FGD Mar-22 Mar-22 TPP, DVC

ESP 182 Budge-Budge West Bengal FGD Dec-22 Dec-22 Dec-22 TPS, CSEC

ESP 183 Titagarh TPS, West Bengal FGD Dec-20 Dec-20 Dec-20 Dec-20 CSEC

ESP Dec-20 Dec-20 Dec-20 Dec-20 184 Haldia TPP, West Bengal FGD Dec-22 Dec-22 Haldia Energy Ltd ESP 185 Farakka STPS, West Bengal FGD Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 Dec-22 NTPC

ESP Dec-22 Dec-22 Dec-22 Dec-22 186 Bakreshwar TPS, West Bengal FGD Complying Complying Complying Complying Complying WBPDCL

ESP 187 Durgapur TPS, West Bengal FGD Retired Dec-20 DVC

ESP Retired Dec-20 188 Bandel TPS, West Bengal FGD Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 WBPDCL

ESP Dec-20 Dec-20 Dec-20 Dec-20 Dec-20 189 India Power TPP, West Bengal FGD Dec-20 Bishagarh Power Co. ESP Dec-20

Note:

1. TPPs with Timeline mentioned in normal character were issued directions on 11.12.2017.

2. TPPs with Timeline/ Retirement status mentioned with BOLD & ITTALIC character were issued directions on 06.04.2018.

3. Directions u/s 5 of EPA have been issued to all the units notified as Retired to remain closed.

4. Compliance status of TPPs/Units mentioned as Complying is claimed by TPPs/Units, which is subject to verification.

vii) Chairperson, CEA&NPC: It is better to deliberate any technical issues/ policy issue among the members first before referring to MoP. If CTU approaches directly to MoP with a proposal to include CTU as a member of NPC, MoP may refer the proposal to CEA/NPC.

viii) NLDC: It is NLDC and not POSOCO was included as a member, to avoid any commercial interest. CTU is involved in interface metering, PSS tuning, Protection co-ordination activities etc. as per IEGC, it is advantageous to include CTU as a member of NPC. In addition to that, CTU is a statutory body like NLDC.

The committee accepted the proposal of CTU to include it as a member of NPC. It was decided that Member Secretary (NPC) shall take up with MoP for necessary amendment in the constitution of NPC. Action: NPC Secretariat.

4. Automatic Under Frequency Load Shedding (AUFLS) Scheme and Mapping of Feeders (A) Review of AUFLS Settings 4.1 As per the decision in the 2nd meeting of NPC held on 16th July 2013, the following AUFLS scheme with 4 stages of frequency viz. 49.2 Hz, 49.0 Hz, 48.8 Hz & 48.6 Hz had been implemented in all the regions:

AUFLS Frequency Load relief in MW (Hz) NR WR SR * ER NER Total Stage-I 49.2 2160 2060 2350 820 100 7490 Stage-II 49.0 2170 2070 2360 830 100 7530 Stage-III 48.8 2190 2080 2390 830 100 7590 Stage-IV 48.6 2200 2100 2400 840 100 7640 Total (MW) 8720 8310 9500 3320 400 30250 *SR grid not integrated with NEW grid.

Region wise/State wise Details of AUFLS and df/dt settings are given at Annexure- III 4.2 In the 7th meeting of NPC held on 08th September 2017, it was agreed that there is need for review of the quantum of load shedding without introduction of additional slabs/stages of frequency. And therefore, RPCs may deliberate on additional slabs of frequency as well as raising the set frequency for UFR operation and inform us about the outcome. The views of RPCs would be put up in next meeting of NPC.

4.3 During the presentation of Reports of the Consultants on Package A&B on power system analysis under contingencies held at CERC on 05th March 2018, CERC has

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 4 of 30 advised to assess if there is a need to revisit the setting of UF relays at 49.2 Hz in consultations with stakeholders.

4.4 Subsequently, WRPC has intimated that a meeting to review the stages and quantum in the existing Automatic Under Frequency Load Shedding Scheme was held on 13.03.2018 at WRPC Mumbai. In general it was agreed that the frequency setting of 1st stage of AUFLS be raised from existing 49.2 Hz to 49.4Hz.and to keep state-wise load shedding quantum same as existing.

4.5 Subsequently, SRPC vide letter dated 18.05.2018 had requested NPC to suggest the UFR quantum to be adopted by Southern Region in the current grid environment.

In view of the above and considering the change in grid size etc., NPC Secretariat vide letter dated 30.05.2018 (Annexure-IV) the two options (Frequency Slab: 49.2 to 48.6 Hz and 49.4 to 48.8Hz) and UFR quantum was communicated to RPCs for consideration/comments.

4.6 SRPC vide letter dated 07.06.2018 (Annexure-V) has communicated their views. The salient points are given below:

i. SR constituents have implemented UFR quantum of 10,653 MW against recommended quantum of 9,500 MW based on average loading of the feeders, around 11% more than the recommended quantum as per existing scheme. ii. It may need to be ascertained and ensured that all Regions are proportionately contributing towards arresting any frequency decay during contingency, based on average loading of the feeders. iii. Since the load relief being worked out on average basis, and daily load fluctuation factor is already been considered, the power number considered for SR that is 1,849 MW/Hz may kindly be reviewed. iv. Further, SR constituents have also provided around 5,610 MW under df/dt scheme. There may be a need to optimize df/dt locations, quantum and set points for all Regions. 4.7 POSOCO vide letter dated 02nd July 2018 (Annexure-VI) has stated that the quantum of load shedding through UFLS to the tune of 48GW suggested by NPC Division, CEA appears sufficient. POSOCO has proposed following aspects for consideration for modification of AUFLS scheme for Indian power system:

(a) Raise the reference frequency of operation of each stage of AUFLS by 0.4Hz, and set the revised AUFLS scheme in 4 stages at 49.6 Hz, 49.4 Hz, 49.2 Hz and 49.0 Hz. (b) Limit the total trip time of modified AUFLS to 200 milliseconds (including measurement time, relay operation time and breaker operation time).

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 5 of 30 (c) Design AUFLS scheme for at least 25% load generation mismatch in Indian power system. (d) Define the terms ‘Synthetic Inertia’ or ‘Fast Frequency Response’ and include appropriately in the gird standards. (e) Co-ordinate under frequency trip relays of Pump storage plants in pumping mode with modified AUFLS scheme, and set the trip frequency to around 49.8 Hz. (f) Geographically distribute the AUFLS trip relays to prevent over voltages.

4.8 NERPC, in its 146th meeting of OCC held on 17th July 2018 has noted that the revised scheme should be at 49.4 Hz, 49.2 Hz, 49.0 Hz & 48.8 Hz. It was decided that the state wise quantum would be prepared and presented in the next meeting for ratification.

4.9 ERPC vide e-mail dated 07.08.2018 has informed that the issue was discussed in 146th & 147th meetings of OCC. Comments on the proposal are given below for kind consideration of the NPC:

i. OCC in principle agreed for raising frequency stages of AUFLS scheme viz. 49.4, 49.2, 49.0 and 48.8 Hz except DVC and WBSETCL. ii. DVC and WBSETCL would like to continue with the existing frequency stages. However, DVC and WBSETCL stated that they had no objection if the upward revision of frequency stages is agreed in NPC. iii. Regarding quantum of load shedding, OCC opined that sufficient quantum of radial feeders might not be available for AUFLS scheme as some of the radial feeders are already covered under ADMS scheme and islanding scheme. OCC felt that 63% raise in total quantum of load shedding w.r.t 2013 may not be appropriate. Raise in quantum of load shedding might be considered as 30% for first two years and rest 33% for next two years.

4.10 NRPC vide letter dated 10.09.2018 (Annexure-VII) has informed the following recommendations of the Committee constituted for review of targets fixed for load relief from operation of df/dt & UFR relays in NR and AUFLS, for discussion in the 8th meeting of NPC:

i. It was agreed that frequency setting of the Stage-I shall be increased to 49.4Hz with subsequent margin of 0.2Hz for each stage with Stage-IV at 48.8 Hz. ii. Required load relief calculations should be revised considering increased power number around 15000 and calculated in MW rather MW/Hz i.e. load relief calculated in each stage shall be multiplied by corresponding frequency deviation from 50Hz.

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 6 of 30 iii. It was also recommended to calculate the load relief on pan India basis but for region and its states, seasonal variations in the demand of the states may be considered. iv. Committee was of the view that methodology for calculating load relief according the Zalte Committee report may be reviewed mainly with respect to Voltage Correction factor and daily load fluctuation factor, if deemed necessary by the states. 4.11 SRPC vide letter dated 20.09.2018 in response to NPC letter dated 05.09.2018 has informed that the issue regarding review of UFR quantum/additional slabs was discussed in the 138th meeting of OCC held on 11.12.2017 wherein, states had opined that there is no need for additional slabs of frequency as well as raising the said frequency for UFR operation. TCC had endorsed these decisions of OCC. In the 33rd meeting of SRPC held on 17.02.2018, constituents had expressed concern regarding paucity of additional radial feeders (without overlap) and also since islanding loads could not be identified for any of the relief schemes. Being large integrated grid, chances of fall of frequency were less and system should be provided space for self- healing before df/dt or UFR sets in. Regarding quantum (based on Power Number), the SR share was being complied as and when the same was being communicated. In the 34th meeting of SRPC held on 11.08.2018, it had been concluded that existing settings may be retained and the same be recommended to NPC.

4.12 Summary of the views/ input are as follows:

NRPC: Frequency setting of the Stage-I shall be increased to 49.4Hz with subsequent margin of 0.2Hz for each stage with Stage-IV at 48.8 Hz. Methodology for calculating load relief according the Zalte Committee report may be reviewed mainly with respect to Voltage Correction factor and daily load fluctuation factor, if deemed necessary by the states. WRPC: The frequency setting of 1st stage of AUFLS be raised from existing 49.2 Hz to 49.4Hz.and to keep state-wise load shedding quantum same as existing. SRPC: There is no need for additional slabs of frequency as well as raising the said frequency for UFR operation. Existing settings may be retained. ERPC: OCC in principle agreed for raising frequency stages of AUFLS scheme viz. 49.4, 49.2, 49.0 and 48.8 Hz except DVC and WBSETCL. Raise in quantum of load shedding might be considered as 30% for first two years and rest 33% for next two years. NERPC: OCC has noted that the revised scheme should be at 49.4 Hz, 49.2 Hz, 49.0 Hz & 48.8 Hz POSOCO: The quantum of load shedding through UFLS to the tune of 48GW suggested appears sufficient.

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 7 of 30 4.13 Deliberation / Decision in the meeting:

i) MS (NPC): AUFLS is the last resort measure to save the grid from complete grid collapse. The quantum of load shedding from AUFLS was computed/decided in the year 2013 (when SR grid was not connected). Being an interconnected All India Grid, with increasing generation capacity/load, there is a need to review the stages as well as the quantum of load shedding under AUFLS. He further added that the size of the grid may increase further at the time of implementation of the proposed settings (computed based on the present size of the grid). He requested RPCs to share their views on it.

ii) SRPC: Andhra Pradesh, Karnataka and Tamil Nadu had agreed for the AUFLS scheme with 4 stages of frequency viz. 49.4, 49.2, 49.0 & 48.8 Hz. SRPC Secretariat had requested KSEBL & TSTRANSCO to concur for revised settings in view of grid security requirements. Kerala & Telangana may agree in due course of time.

He stated that regarding POSOCO’s suggestion on ‘Synthetic Inertia’ and ‘Fast Frequency Response’, could be defined and adequately incorporated in the Grid standards and the implementation of the same should be at the disposal of the system operator through CERC/SERCs.

iii) NLDC: Pumped storage hydro power plant should get disconnected even before UFRs. In response that representative from SRPC observed that availability of pumped storage power plant on bar is for limited time only. Hence it is not very reliable to use pumped storage as a defense mechanism.

iv) NERPC: The AUFLS scheme with 4 stages of frequency viz. 49.4, 49.2, 49.0 & 48.8 Hz have been agreed by the constituents of NER.

v) WRPC: The quantum of relief computed and circulated by NPC Secretariat needs a little correction. The required load relief needed to be computed to achieve frequency at 50 Hz only and not one Hz on each stage as proposed. For Stage-I, load relief to be computed for raising frequency by 0.6 Hz and for Stage-II by 0.8 Hz.etc. for the AUFLS scheme with 4 stages of frequency viz. 49.4, 49.2, 49.0 & 48.8 Hz. In this regard, MS (NPC) mentioned that the power system doesn’t behave in a linear manner. The required jerk to increase the frequency by 1Hz may, in reality, leads to a jerk of less than that. Hence, if we envisage uplifting frequency by 0.6 Hz (for stage-I), we may not be able to arrest the falling frequency in real time situation.

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 8 of 30 vi) NRPC: The feeders, which were identified for AUFLS earlier, are not radial now, and further other defense mechanisms like SPS have come into picture and the entities have to manage all such defense mechanism with the available number of feeders. The Zalte Committee based on which NPC Secretariat recommended the quantum, is old and needs to be reviewed. At that time, frequency used to be low, hence frequency deviation of 1.5 which is taken, may be reconsidered. Nowadays, frequency deviation are very less. Also, the voltage correction factor of 1.085 may also be re-worked out. The load which is distributed on pro-rata basis should be reviewed considering season variation. In states like Punjab, Haryana; load to be shed is more than maximum load of the states, hence if scheme operates, entire states will go dark.

A detailed study needs to be done by academic experts/consultants to find out the required quantum relief for AUFLS. He requested to keep the quantum and stages of AUFLS unchanged until the study is completed. NRPC proposed that they can appoint a consultant from their own resources and the report would be submitted to NPC within six months. vii)Chairperson, CEA& NPC: Advised NRPC to appoint a consultant/ involve academicians for studying the quantum and stages under AUFLS for the Indian Grid and to submit the report within six months. NRPC agreed to conduct the study by funding form own source and to submit the study report to Chairperson CEA&NPC within six months. viii)NLDC: As per international practice, 25% of the total load is kept for operation under AUFLS. For Indian Grid, presently 43GW of load shedding is enough to restrain the fall in frequency. ix) MS (NPC): As per the computation of NPC secretariat, the quantum comes out to be about 48GW which is close to the quantum as recommended by NLDC. The existing settings could not arrest the fall in frequency because of the increased grid size as compared to the year 2013. By the time of implementation, the grid size may increase further. It is, therefore, recommended to implement the 2nd option as of now. In case, the consultant (to be appointed by NRPC) recommends a different quantum, the same could be implemented.

After deliberation, the committee, agreed for the AUFLS scheme with 4 stages and raising the frequency by 0.2 Hz viz. 49.4, 49.2, 49.0 & 48.8 Hz. The

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 9 of 30 quantum for AUFLS would be reworked by NPC Secretariat based on the deliberation.

It was also decided that, NRPC may appoint a Consultant from their own resources as proposed by MS (NRPC) for studying the AUFLS scheme for Indian grid and submit the study report to NPC Secretariat within a time of six months. Action: NRPC

The revised load relief for AUFLS computed by NPC Secretariat would be discussed along with the report of Consultant appointed by NRPC (if available), in the next meeting of NPC which would be held in the month of May, 2019. Action: NPC Secretariat

(B) Mapping of Feeders: In the 7th Meeting of NPC, it was agreed that each RPC would submit the details / progress of feeder mapping to NPC secretariat. The status furnished by the RPCs are as follows:

SRPC has informed that 84 % mapping of feeders on SCADA had been completed in SR (AP=59%, TS=78%, KAR =100%, KER=98%, TN=86% & PUDU=92%).

ERPC has informed that the mapping of feeders was yet to start in view of deficiencies in the communication/ telemetry infrastructure. However the operation of UFRs is being monitored in every OCC meetings.

WRPC has informed that the issue of mapping of feeders was discussed in OCC several times in recent past. In the 493rd OCC all the constituents were requested to initiate the process of mapping of AULFS feeders in SCADA system as most of these feeders are not covered by SCADA. During the discussion, the Western Region constituents normally raised the following concerns: Maharashtra: AULFS wired feeders are at 66kV, 33kV and even at 11 kV level and these feeders are not covered under SCADA at present. Gujarat: Most of the AULF wired feeders are at 66kV which is not yet covered under SCADA and therefore these cannot be mapped at present. The views of remaining constituents are same as above.

______Minutes of the 8th Meeting of NPC held on 30th November 2018 Page 10 of 30

File No.CEA-PS-13-17(23)/1/2018-PSPM Division-Part(3)

भ딾रत सरक딾र Government of India व픿दद्युत म뤂त딾लय Ministry of Power कक न दद य व픿दद्युत प딾 वधक र ण Central Electricity Authority व픿 दद्युत प ण딾 लद प रर यय ज न딾 प बय धन प भ딾 ग Power System Project Monitoring Division

सेवा मे, Member Secretary, Western Regional Power committee, F-3, MIDC Area, Andheri (East), Mumbai-400093

ववषय: देश मे 31 ददसंबर 2018 तक मौजुदा सबस्ेशन और टांसंमशन लाइनो की जानकारी उपलब् कराने के संबं् मे। Subject: Details of existing transmission system (220 kV and above AC & DC Voltage level) in the country as on 31st December 2018 - Regarding.

Sir, You are aware that transmission system is planned for evacuation of power from generating stations to load centers and for strengthening of existing transmission network to meet the projected load growth. Over the years, there have been phenomenal growth in expansion of transmission network and the transmission system, which was originally planned/ envisaged, has undergone modification by creation of LILO arrangements, change in terminal station etc.as per system requirement.

Ministry of power has desired information regarding statewise growth of transmission system over the years. The details of existing transmission system (interstate and intrastate system) is not available in Power System Project Monitoring (PSPM) Division of CEA. In absence of above details, it is not possible to provide such information.

Therefore, it is requested that information in respect of transmission system (Interstate and intrastate) including state power map and Single Line Diagram of transmission network (as on 31.12.2018) may please be collected from States, PGCIL and other Transmission Service providers (TSPs) in the region in the format attached at Annexure I & II and furnished to this Division for creation of database of existing transmission system.

Encl: As above.

भवदीय,

(एस. के .आर. मोहापात) मुखय अंभयंता

. ______. सक픿딾 भ픿न, आर. कक . पद्युरम-1, नई ददललद-110066 टकलदीयन : 011-26103242 ईमकल: [email protected] 픿कबस딾इट: www.cea.nic.in Sewa Bhawan, R.K Puram-1, New Delhi-110066 Telephone: 011-26103242 Email: [email protected] Website: www.cea.nic.in

Annexure-9.10 (a)

Annexure 9.10C Incorrect telemetered data from NTPC

List of non/wrongly updating points at Kawas Analogs Sr. IEC No. Point name address Remarks 1 220kV Kawas Bus 1 freq 3017 The raw count is 0 2 220kV Kawas Bus 2 freq 3019 The raw count is 0 3 220kV Kawas Icchapur 1 MW 3048 Wrong value 4 220kV Kawas Icchapur 1 MVAR 3049 The raw count is 0 5 220kV Kawas Icchapur 2 MVAR 3051 The raw count is 0

CB Sr. IEC No. Point name address Remarks 1 20652 ST1 CB 2004 Updating as Faulty 2 21352 ST2 CB 2011 Updating as Faulty Updating as Open whereas actual status 3 21552 Icchapore 1 CB 2017 is closed Updating as Open whereas actual status 4 21952 Icchapore 2 CB 2018 is closed Updating as Open whereas actual status 5 22052 Vav 2 CB 2019 is closed

1 21552 SOE Icchapore 1 1041 Suspect 2 21952 SOE Icchapore 2 1042 Suspect 3 22052 SOE Vav 2 1043 Suspect

Isolators Sr. IEC No. Point name address Remarks 1 Isolators L & T of lines, generators & ST All isolators are updating as open All isolators of bays 215 & 219 2 (Icchapore 1 & 2) Suspect 3 Transfer bus isolators of Haldarwa 2 102 Suspect

List of non/wrongly updating points at Jhanor Analogs Sr. No. Point name IEC address Remarks 1 220kV Jhanor Bus 1 freq 3034 Wrong value 2 220kV Jhanor Bus 2 freq 3036 Wrong value 3 400kV Jhanor Bus 1 freq 3017 Wrong value 4 400kV Jhanor Bus 2 freq 3019 Wrong value 5 400kV Jhanor Sugen MW 3031 Wrong value 6 400kV Jhanor Sugen MVAR 3028 Wrong value 7 400kV Jhanor GPEC MW 3029 Wrong value 8 400kV Jhanor GPEC MVAR 3030 Wrong value 9 ICT 1 MW 400kV side 3020 Wrong value 10 ICT 1 MVAR 400kV side 3021 Wrong value 11 ICT 2 MW 400kV side 3024 Wrong value 12 ICT 2 MVAR 400kV side 3025 Wrong value 13 ICT 1 MW 220kV side address required Not configured at site 14 ICT 1 MVAR 220kV side address required Not configured at site 15 ICT 2 MW 220kV side address required Not configured at site 16 ICT 2 MVAR 220kV side address required Not configured at site

CB Sr. No. Point name IEC address Remarks 1 400kV ICT 1 Tie bay 402 CB 2002 Faulty 400kV Dehgam 1 Tie bay 2 405 CB 2003 Faulty 400kV Dehgam 1 Main bay 3 406 CB 2008 Faulty 400kV ICT 2 Main bay 402 4 CB 2005 Faulty 400kV Sugen Main Bay 410 5 CB 2004 Faulty 400kV Sugen Tie Bay 411 6 CB 2009 Faulty 400kV GPEC Main Bay 412 7 CB 2010 Faulty 400kV Dehgam 2 Main Bay 8 413 CB 2011 Faulty

Isolators Sr. No. Point name IEC address Remarks 1 40189A address required Not configured at site Updating as Open whereas actual status 2 40589A 55 is closed Updating as Open whereas actual status 3 40589B 56 is closed Updating as Open whereas actual status 4 40689A 66 is closed Updating as Open whereas actual status 5 40689B 67 is closed 6 40689L address required Not configured at site 7 40789A address required Not configured at site 8 40989B address required Not configured at site Updating as Open whereas actual status 9 41089L 74 is closed Updating as Open whereas actual status 10 41189A 68 is closed Updating as Open whereas actual status 11 41189B 69 is closed Updating as Open whereas actual status 12 41289A 70 is closed 13 41289B address required Not configured at site Updating as Open whereas actual status 14 41289L 71 is closed Updating as Open whereas actual status 15 41389A 58 is closed 16 41389B address required Not configured at site 17 41389L address required Not configured at site 18 41489A address required Not configured at site 19 41489B address required Not configured at site Proper addreses 20 All 220kV Isolators requried Wrongly updating at WRLDC

List of non/wrongly updating points at KSTPS Analogs Sr. No. Point name IEC address Remarks 1 KSTPS Bus 2 KV 3018 Wrong value 2 KSTPS Bus 2 HZ 3019 Wrong value 3 KSTPS Bus 3 KV 3020 Wrong value 4 KSTPS Bus 3 HZ 3021 Wrong value 5 KSTPS Bus 4 KV 3022 Wrong value 6 KSTPS Bus 4 HZ 3023 Wrong value 7 Generator 1 MW 3038 Wrong value 8 Generator 1 MVAR 3039 Wrong value 9 GT 1 MW 3040 Wrong value 10 GT 1 MVAR 3041 Wrong value 11 Generator 6 MW 3058 Wrong value 12 GT 6 MVAR 3061 Wrong value 13 GT 6 MVAR 3063 Wrong value 14 Korba Bhillai 1 MVAR 3025 Wrong value 15 Korba Bhillai 2 MVAR 3031 Wrong value 16 Korba Sipat MVAR 3057 Wrong value 17 Korba Bhatapara MW 3064 Wrong value 18 Korba Bhatapara MW 3065 Wrong value 19 Korba Korba West MW 3042 Wrong value 20 Korba Korba West MW 3043 Wrong value

CB Sr. No. Point name IEC address Remarks 1 GT 7 CB address required Not configured 2 Korba West CB 2008 Updating as open but at site it is closed 3 Bus coupler 2 CB 2019 Updating as open but at site it is closed 4 Raipur 3 CB address required Not configured 5 Raipur 4 CB address required Not configured 6 TBC 2004 Updating as closed but at site it is open 7 Birsingput 1 CB address required Not configured 8 Bus sectionaliser 1 2012 Updating as open but at site it is closed

Isolators Sr. No. Point name IEC address Remarks 1 All isolators need to be checked