Afghanistan Water Resources Development (AWARD) Technical Assistance Project - Technical and Implementation Support Consultancy (TISC)
Grant No. TF093637-AF/ Contract No. MEW/957/QBS
INVESTMENT PLAN FOR KABUL RIVER BASIN
January 2013
AWARD - TISC
Grant No. TF093637-AF/ Contract No. MEW/957/QBS
AFGHANISTAN
KABUL BASIN INVESTMENT PLAN
Report submitted by LANDELL MILLS LTD
This report was prepared at the request of the Ministry of Energy and Water. The views expressed are those of the Consultants and do not necessarily reflect those of the Government of Afghanistan or the World Bank.
KEY DATA
Name of Project: AWARD - TISC (Grant No. TF093637-AF/ Contract No. MEW/957/QBS) Contractor: Landell Mills Limited, Bryer-Ash Business Park, Bradford Road, Trowbridge, Wiltshire, BA14 8HE, UK Tel: +44 1225 763777 Fax: +44 1225 753678 www.landell-mills.com
in association with Mott MacDonald (www.mottmac.com) Contracting Authority: Ministry of Energy and Water, Islamic Government of Afghanistan Beneficiary: Ministry of Energy and Water Primary Location: Kabul Secondary Locations: Nationwide
DISTRIBUTION LIST
Recipient Copies Format Eng. Farhad, Director of Water Projects 10 English – electronic and hard copies
QUALITY ASSURANCE STATEMENT
Version Status Date Kabul Basin Investment Plan Version 3 6.02.13 Name Position Date Prepared by: Georg Petersen River Basin Planner 30.01.13 Devaraj de Condappa River Basin Modeller (WEAP) Laura Forni WEAP/LEA Specialist Checked by: Jelle Beekma Senior Consultant, Landell Mills Limited 31.01.13 Simon Foxwell Backstopping Director, Landell Mills Limited 31.01.13
ACKNOWLEDGEMENTS
We would like to thank the General Director of Planning, Mme. Zia Gul, Director of Water Projects, Eng. Farhad, and other staff of the MEW Department of Planning, as well as His Excellency the Deputy Minister Eng. Ziaie, for their cooperation and support to the team.
Page i AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
CONTENTS
ABBREVIATIONS AND ACRONYMS ...... III 1. EXECUTIVE SUMMARY ...... 1 1.1. Context ...... 1 1.2. Analysis ...... 1 1.3. Results ...... 3 1.4. Conclusions and Recommendations...... 8 2. BACKGROUND AND CONTEXT ...... 13 2.1. Motivation of this Analysis ...... 13 2.2. Main Characteristics of the River Basin ...... 17 2.3. Critical Issues ...... 26 2.4. Future Targets ...... 30 2.5. Development Options ...... 31 3. WATER RESOURCES AVAILABILITY AND DEMAND FOR YEAR 2030 ...... 33 3.1. Water Resources Availability for Year 2030 ...... 33 3.2. Demands for Year 2030 ...... 36 4. APPROACH AND METHODOLOGY ...... 43 4.1. Modelling Framework ...... 43 4.2. Hydrological Scenarios Modelling ...... 47 4.3. Reference Case...... 47 4.4. Future Scenarios ...... 49 4.5. Result Database ...... 63 4.6. Approach and Assessment Criteria for Investment ...... 63 4.7. Performance Assessment ...... 68 4.8. Robustness Aspects ...... 69 4.9. Assumptions ...... 70 4.10. Investment Tranches ...... 71 4.11. Development Sequence ...... 71 4.12. Limitations and Uncertainties ...... 72 4.13. Partnership and Stakeholder Involvement ...... 73 5. SCENARIO ANALYSIS AND RESULTS ...... 76 5.1. Reference Case...... 76 5.2. Overview of the Scenarios ...... 77 5.3. Priority for Coverage of Domestic Water Demand ...... 80 5.4. Analysis of Investment Tranches ...... 80 5.5. Asset Performance (Individual) ...... 144 5.6. Sensitivity Analysis ...... 149 5.7. Development Schedule...... 151 6. CONCLUSIONS AND RECOMMENDATIONS ...... 175 6.1. Conclusions ...... 175 6.2. Recommendations ...... 178 APPENDIX 1: REFERENCES ...... 181 APPENDIX 2: STAKEHOLDERS AND CONTACTS ...... 184 APPENDIX 3: EXISTING HYDRAULIC ASSET DETAILS ...... 187 APPENDIX 4: PROPOSED HYDRAULIC ASSET DETAILS ...... 188 APPENDIX 5: FINANCIAL PARAMETERS USED IN WEAP ...... 191
Page ii AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
ABBREVIATIONS AND ACRONYMS
ADB Asian Development Bank AEIC Afghan Energy Information Center AIMS Afghanistan Information Management Service ANDS Afghanistan National Development Strategy ARTF Afghanistan Reconstruction Trust Fund AUWSSC Afghanistan Urban Water Supply and Sewerage Corporation AWARD Afghanistan Water Resources Development (Project) BGR Federal Institute for Geosciences and Natural Resources, Germany CASA 1000 Central Asia South Asia Electricity Transmission and Trade Project CE Civil Engineer CIA Central Intelligence Agency CPHD Center for Policy and Human Development CSO Central Statistics Organization CTAP Civilian Technical Assistance Programme DSS Decision Support System EIRP Emergency Irrigation Rehabilitation Programme ESHA European Small Hydropower Association FAO Food and Agriculture Organization GAMS General Algebraic Modelling System GCMs Global Climate Models GD-P General Directorate of Planning GIS Geographic Information System GWSP Global Water System Project IBRD International Bank for Reconstruction and Development IPCC Intergovernmental Panel on Climate Change IUCN International Union for Conservation of Nature IWRM Integrated Water Resources Management JICA Japan International Cooperation Agency KDSS Kabul River Decision Support System KM Kabul Municipality LEA Large Ensemble Approach LML Landell Mills Limited MAIL Ministry of Agriculture, Irrigation and Livestock MECO Montreal Engineering Co. MEW Ministry of Energy and Water MoEC Ministry of Economy MoF Ministry of Finance MoFA Ministry of Foreign Affairs MoIC Ministry of Industries and Commerce MOM Management, Operation and Maintenance MoPH Ministry of Public Health MoRRD Ministry of Rural Rehabilitation and Development MoUD Ministry of Urban Development NB Net Benefit NEPA National Environment Protection Agency NGO Non-Governmental Organization
Page iii AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
NPP National Priority Program O&M Operation and Maintenance RB River Basin RBA River Basin Agency RBP River Basin Planning RCMs Regional Climate Models RCUWM Regional Centre on Urban Water Management RFP Request for Proposal SBA Sub Basin Agency SCoW Supreme Council of Water TA Technical Assistance TISC Technical Implementation Support Consultancy TOR Terms of Reference TL Team Leader TS Technical Secretariat USGS United States Geological Service WB World Bank WEAP Water Evaluation and Planning WFP World Food Program WRPU Water Resources Planning Unit
Page iv AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
1. EXECUTIVE SUMMARY
1.1. CONTEXT
The Afghanistan Water Resources Development (AWARD) Technical Assistance Project was prepared through a World Bank Water Resources Development Proposal which was approved by the Afghanistan Reconstruction Trust Fund (ARTF) in December 2008. The grant became effective upon the signing of the ARTF Grant No. TF0903637 on 23 March 2009, and follows Conditions for Grants made by the World Bank out of various funds. The Technical Implementation Support Consultancy (TISC) was contracted by the Ministry of Energy and Water (MEW) in January 2011 and the team was mobilized in late February 2011.
The investment plan for the Kabul River basin details the analysis of a set of development opportunities which may potentially be implemented in the basin. The investments were analysed and described based on information given in different feasibility studies that have previously been established through various consultancies. Potential investments for which sufficient data were not available have not been included in the analysis but may be considered at a later time once studies have been carried out and the information required for analysis becomes available.
The socioeconomic situation in the Kabul basin as well as in Afghanistan as a whole has been considered in the analysis. Potential transboundary aspects including water demands or power import/export could not be considered due to a lack of available information and unclear long term plans. However, the influence of various combinations of infrastructure on the flow at the border is shown. There also may be potential for benefit sharing in-between the different basins in Afghanistan which could not be considered either due to lack of detailed information.
1.2. ANALYSIS
The analysis was carried out using a combined approach of logical assumptions, water resources modelling and database analysis. The logical assumptions are based on report findings as well as stakeholder inputs (which for example led to prioritising domestic water demands) as well as economic considerations and data embedded in the analysis. For testing the different water resources allocation options under the various different scenarios of asset combinations, their operation, priorities and runoff conditions, WEAP modelling software (Yates et al., 2005) was used.
Due to a large number of possible investment combinations that all influence each other in combination with various management option and uncertainty of hydrologic regimes in the future, a large number of runs was carried out in which the various parameters were varied. An automated batch file was developed for the running of these combinations, referred to as the Large Ensemble Approach (LEA). The LEA was used to generate a database for analysing the various basin development scenarios. The scenarios cover domestic and industrial water use, irrigation, hydropower development options, and three hydrological regimes. The database allows for analysis of various development paths and can be adapted at any moment to the new reality if different sequences of projects are implemented.
Flood aspects were not considered due to insufficient data availability regarding discharge-flood relations as well as insufficient information of flood impacts on economics. The LEA results were
Page 1 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
analysed using Tableau (Tableau Software, 2012), software that allows for the multidimensional analysis of large databases in a semi-automated approach.
Additional to the LEA, sensitivity was tested for different irrigation efficiencies, since irrigation is by far the major water user and effects of improving efficiency will significantly reduce water withdrawals. Sensitivity was also analysed for the price of domestic water in view of the fact that in absence of water supply systems, high prices are actually paid for alternative water supply and the price used in the LEA (0.50 US$/m3) causes the water supply projects to have relatively low net revenue. Lastly the reliability of the reservoirs was tested for extreme conditions of three consecutive dry years, which according to available data occurred only three times during the last century.
The scenario analysis simulates conditions for the year 2030 and includes various possible combinations of new schemes1: • Shatoot dam, a multipurpose scheme on Maidan River • Gulbahar dam, a multipurpose scheme on Panjshir River • Baghdara dam, a hydropower scheme on Panjshir River for which two options were evaluated, Baghdara A2, with negligible storage and Baghdara D1 with considerable storage • Sarubi II run-of-river, a hydropower scheme on Kabul River • Shal dam, a hydropower scheme on Konar River • Konar A dam, a hydropower scheme on Konar River • Gambiri scheme, a hydropower and irrigation scheme on Kunar River • Kama scheme, a hydropower and irrigation scheme on Kunar River
The schemes in the year 2030 are represented by developed conditions with the reservoirs partly filled as it would occur under routine operation. The new schemes are assumed to be operational and generating revenues, resulting in a return of investment. Incurred Operation and Maintenance (O&M) costs and capital costs are being annualised. In addition to the 2030 scenario, the best possible development paths were assessed based on covering domestic water needs and best net benefit, leading to recommendations for sequencing of the investments.
Parameters considered in the scenario modelling and analysis include:
• Different flow scenarios (hydrological conditions reflecting future uncertainties). To characterise the monthly and inter-annual variability in streamflow the median flow as well as two mild variations are simulated. The median flow represents a flow with a probability of occurring every 2 years and to represent the most likely flow every year. The two mild deviations from the median labelled Dry 5 and Dry 10 represent typical variations of streamflows drought with a probability of occurring every 5 or 10 years respectively. • Irrigation condition alterations have been considered through sensitivity runs in order to assess the effects of different irrigation efficiencies. • Different priorities for water allocation of the different schemes (i.e. different operational rules) as well as their combinations were used to test different development options. This includes priority shifts between domestic water supply, hydropower generation, irrigation water supply and filling the reservoirs.
1 The investment plan does not analyse the technical feasibility of each scheme.It is assumed at this stage that all schemes are technically feasible.
Page 2 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
• Different water allocation rules were tested in line with the different prioritization, e.g. to what level a reservoir would need to be filled before release could take place, etc. • While crop related activities could change in the future, there is no detailed information available in this regard. Cropping patterns and crop management were respectively kept standard as they are currently in use (yields were increased by 20% where irrigation systems are improved). • A plant factor for depicting the actual productive time of the power generating assets considering maintenance needs and downtimes. • Population estimates have been included in the analysis to obtain domestic water demand needs for Old- and New Kabul City. Possible different projections in per capita water consumption have not been further tested. • Available funding limits have been utilized in the database analysis to filter different sets of ideal investments, i.e. to determine which structures provide the highest benefit under different funding conditions.
In addition to the technical parameters, reliable data for the economic assessment was collected by the team economist who has worked closely with stakeholders in Afghanistan to quantify the relevant costs and benefit data for this study. The data was used to identify the investment option with the highest total net benefit, the highest agricultural net benefit change, and the highest hydropower revenue under various streamflow regimes.
To ensure that the selected options satisfy high levels of performance of the different sectors investigated, an initial “optimal bundle” of options was identified that would perform well under the various varied parameters of the system and hence constitute the “optimal bundle of investment options”. Based on this pre-selection, robust options were selected by considering the performance of the optimal bundle under the different streamflow regimes, i.e., Median, Dry 5 and Dry 10. The selected option would be providing the highest performance under median streamflow conditions while satisfying the optimal bundle conditions under the other streamflows (robustness).
For each investment option, the impact on the flow at the outlet of the basin is provided which provides data for the government to use in trans-boundary negotiations with Pakistan. While some investment options have a seasonal impact on flow, all have an insignificant impact on the annual floow.
1.3. RESULTS
The results of scenarios with new combinations of infrastructure were compared to the Reference Case. The Reference Case is the situation in which no new projects are developed and the demands for domestic water and electricity are projected to the year 2030. Comparisons were made for change in Net-benefit, Change in Agricultural Benefit, Coverage of Domestic Water for Kabul and total hydropower production. The analysis of the investment options lead to sets of results that were further evaluated. Investment options were grouped in budget tranches to enable decision makers to select investment options that fit the financing situation. This will enable the government, for example, to lobby for funding at donor conferences, and then, based on the level of donor commitments, to choose the appropriate investment option, based on the development priorities.
Page 3 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
≤ 0.5 BUS$: Although net benefits for the Baghdara A2 and Kama schemes are higher than for the Shatoot dam, the construction of the Shatoot dam is the preferred option in this tranche because domestic water delivery to Old Kabul city has the highest priority (as confirmed by MEW and stakeholders and also recommended as the priority for water users by ourselves). The costs for Gulbahar, which is the other domestic water supply option are much higher and therefore cannot be considered in this tranche. Other potential sources for water supply, for which no finalised feasibility studies were available, have not been considered
For higher investment tranches, the Shahtoot Dam was maintained as an initial investment in the basin because of the priority of the supply of domestic water to Old Kabul city and the likely increased pressure on the nearby lower Logar Aquifer. While Gulbahar is also an option for supplying water to Old Kabul city in tranches above 1.5 BUS$, it is a scheme planned primarily for New Kabul city and the amount planned for Old Kabul City is negligible, while Shatoot covers 87% of the demand for Old Kabul city, thus Shatoot remains the initial investment. The optimum scheme combination of subsequent tranches thus depends on the preferences set for additional development priorities, i.e. for maximum net benefit, electricity production, water supply to New Kabul city or change in agricultural benefit. The government has not indicated which of these development priorities is preferred so we have listed the best performing infrastructure combinations for each priority below:
≤1.0 BUSD: • Highest net benefit and increase in agricultural benefit: Shatoot, Gambiri, Kama • Highest electricity production: Shatoot, Baghdara D1
≤1.5 BUSD: • Highest net benefit and highest electricity production: Shatoot, Gambiri, Konar A • Highest increase in agricultural benefit: Shatoot, Gambiri, Kama, Baghdara A2
≤2.0 BUSD: • Highest net benefit, electricity production and increase in agricultural benefit: Shatoot, Gambiri, Kama, Konar A • Supply of domestic water to New Kabul city: Shatoot, Gulbahar
≤2.5 BUSD: • Highest net benefit and electricity production: Shatoot, Gambiri, Kama, Baghdara D1, Konar A • Domestic supply to New Kabul city and increase in agriculture benefit: Shatoot, Gulbahar, Gambiri and Kama
≤3.0 BUSD: • Highest net benefit: Shatoot, Gambiri, Kama, Baghdara D1, Konar A • Electricity Production: Shatoot, Baghdara D1, Surubi II, Konar A • Domestic water supply to New Kabul city and agricultural benefit: Shatoot, Gulbahar, Gambiri, Kama, Konar A
Page 4 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
≤3.5 BUSD: • Highest net benefit and electricity production: Shatoot, Baghdara D1, Surubi II, Gambiri, Kama, Konar A • Domestic water supply to New Kabul city and increase in agricultural benefit: Shatoot, Gulbahar, Gambiri, Kama, Konar A
≤4.0 BUSD: • For all criteria: Shatoot, Gulbahar, Baghdara D1, Gambiri, Kama, Konar A
>4.0 BUSD • Highest net benefit and increase in agricultural benefit, with loan financing: Shatoot, Gulbahar, Baghdara D1, Gambiri, Kama, Konar A • Highest net benefit and increase in agricultural benefit, with grant financing: Shatoot, Gulbahar, Baghdara D1, Surubi II, Gambiri, Kama, Shal • Electricity Production: Shatoot, Gulbahar, Baghdara D1, Surubi II, Gambiri, Kama, Shal
The best investment combinations for the various budget tranches are summarised below.
Table 1: Best investment combinations for various budget tranches Investment Tranche Total Net Electricity Domestic Water Increase in Benefit production Coverage agricultural benefit < 0.5 BUS$ Baghdara A2 Baghdara A2 Shatoot Kama
0.5- 1.0 BUS$ Shatoot Shatoot, Shatoot, plus either Shatoot Gambiri Baghdara D1 of the other three Gambiri Kama (i.e. No specific Kama solution) 1.0- 1.5 BUS$ Shatoot Shatoot, plus either Shatoot Gambiri of the other four (i.e. Gambiri Konar A No specific solution) Kama Baghdara A2 1.5- 2.0 BUS$ Shatoot Shatoot Shatoot Gambiri Gulbahar Gambiri Kama Kama Konar A Konar A 2.0-2.5 BUS$ Shatoot Shatoot Gambiri Gulbahar Kama Gambiri Baghdara D1 Kama Konar A 2.5-3.0 BUS$ Shatoot Shatoot Shatoot Gambiri Baghdara D1 Gulbahar Kama Surubi II Gambiri Baghdara D1 Konar A Kama Konar A Konar A 3.0-3.5 BUS$ Shatoot Shatoot Baghdara D1 Gulbahar Surubi II Gambiri Gambiri Kama Kama Konar A Konar A
Page 5 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Investment Tranche Total Net Electricity Domestic Water Increase in Benefit production Coverage agricultural benefit 3.5-4.0 BUS$ Shatoot Gulbahar Baghdara D1 Gambiri Kama Konar A > 4.0 BUS$ With loan: Shatoot Shatoot, Gulbahar, With loan: Shatoot Gulbahar plus any combination Shatoot Gulbahar Baghdara D1 of the others (i.e. No Gulbahar Baghdara D1 Surubi II specific solution) Baghdara D1 Gambiri Gambiri Gambiri Kama Kama Kama Konar A Shal Konar A
With grant: With grant: Shatoot Shatoot Gulbahar Gulbahar Baghdara D1 Baghdara D1 Surubi II Surubi II Gambiri Gambiri Kama Kama Shal Shal
In addition optimum development sequences were assessed for the the best investment combinations in the above given budget tranches. Optimum development sequences were based on the assumption that funds from a given investment tranche would not be spent instantly but over a period of time, i.e. that the investments identified in the assessment would be implemented in a sequence. The sequence of construction is recommended to be based on (i) priority to satisfying domestic water demand and (ii) cost benefit considerations. Shatoot is the most logical choice for the first step. The further steps should follow the investment tranches as these are established based on economic considerations and provided in the table below:
Table 2: Recommended sequence of construction per investment tranche Investment Investment option* Year Year 2020 Year 2025 Year 2030 tranche 2018 ≤ 0.5 BUS$ Shatoot Shatoot Shatoot, Gambiri 3, Kama 3 Shatoot Kama Gambiri ≤ 1.0 BUS$ Shatoot Shatoot Baghdara Baghdara D1 2 D1 Shatoot, Gambiri 3, Konar A 2 Shatoot Konar A Gambiri Shatoot Shatoot Baghdara Kama Gambiri ≤ 1.5 BUS$ Gambiri 3 A2 Kama 3 Baghdara A2 Shatoot, Gambiri 3, Kama Shatoot Konar A Kama Gambiri ≤ 2.0 BUS$ 1,Konar A 2 Shatoot, Gulbahar 6 Shatoot Gulbahar Shatoot, Gambiri 3 Shatoot Konar A Baghdara Gambiri ≤ 2.5 BUS$ Kama 1 D1 Konar A 2 Kama
Page 6 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Investment Investment option* Year Year 2020 Year 2025 Year 2030 tranche 2018 Baghdara D1 2 Shatoot, Gulbahar 6 Shatoot Gulbahar Kama Gambiri Gambiri 3 Kama 3 Shatoot Shatoot Gulbahar Konar A Gambiri Gulbahar 5 Gambiri 3 Konar A 2 Shatoot Shatoot Konar A Baghdara Gambiri Gambiri 3 D1 ≤ 3.0 BUS$ Kama 1 Kama Konar A 2 Baghdara D1 2 Shatoot Shatoot Konar A Baghdara Surubi II Surubi II D1 Baghdara D1 2 Konar A 2 Shatoot Shatoot Konar A Baghdara Gambiri Gambiri 3 D1 Surubi II Kama 1 Kama Konar A 2 Baghdara D1 2 ≤ 3.5 BUS$ Surubi II Shatoot Shatoot Gulbahar Konar A Kama Gulbahar 6 Gambiri Gambiri 3 Kama 1 Konar A 2 Shatoot Shatoot Gulbahar Konar A Baghdara Gulbahar 6 Kama D1 Gambiri 3 Gambiri ≤ 4.0 BUS$ Kama 1 Konar A 2 Baghdara D1 Shatoot Shatoot Gulbahar Konar A Baghdara Gulbahar 6 Kama D1 Gambiri 3 Gambiri Kama 1 Konar A 2 Baghdara D1 > 4.0 BUS$ Shatoot Shatoot Gulbahar Baghdara Gambiri Gulbahar 6 Shal D1 Surubi II Gambiri 3 Kama Kama 3 Baghdara D1 1 Surubi II Shal * Numbers after each scheme = the operational rules
Page 7 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
1.4. CONCLUSIONS AND RECOMMENDATIONS
1.4.1. Conclusions
The main findings are:
1. Securing the supply of domestic water to the existing Old Kabul city is a priority for any investment in the basin. Projection of the population, consumption rate and connection rate have shown that less than 30% of the demand from the connected population of the city can be satisfied in year 2030 with the supply from neighbouring aquifers. This supply would even reduce further to 12% only if analysed in combination with the likely future water withdrawals for the Aynak mine from one of the main aquifers supplying the city.
2. Options for further development could be to tap farther aquifers or to develop surface water resources. At the time of this work no finalised studies were available for further groundwater exploitation but two projects were available for surface water exploitation: construction of a dam on the Maidan river, Shatoot dam for about 360 MUS$, and another dam on the Panjshir river, Gulbahar dam for about 1,400 MUS$. This analysis concludes that given a priority of domestic water supply in the exisiting Kabul city Shatoot should be a priority scheme for any investment in the basin due to its relative low cost and its reliable supply of domestic water which will, combined with the groundwater supply, cover almost 90% of the domestic water demands of the connected population. Gulbahar scheme was judged to be a good complement to Shatoot, since it is a very reliable source of water that would supply New Kabul city. It is advised in this study that the water supply from Gulbahar should also be connected to the existing (Old) Kabul city since Gulbahar would supplement the supply to Old Kabul city in case Shatoot fails under severe and extended drought.
3. In addition to the social benefit, investing in Shatoot and Gulbahar also has an economic benefit. It was shown that the benefit per volume of water from domestic water (about 0.21 US$/m3 at Gulbahar) is about 8 to 9 times greater than hydropower (about 0.03 US$/m3). The Shatoot asset has a poor net benefit but this is not due to prioritised allocation to domestic water supply but to the scarcity and high variability of the Maidan river flow which has lead to a large reservoir in comparison to the annual volume projected to be withdrawn. Further reservoir calculations under different hydrological scenarios should be carried out to better determine the required storage volume (see the Bulk Kabul Water Supply scoping study) which might result in a reduced reservoir volume and lower costs. Economic performance of Shatoot improves if analysed in conjunction with the start of Aynak mine operations. Relative timing of the two projects is important in order to minimise the effects of the mining on the domestic water supply of the existing Kabul city. Further analysis is needed to identify the best combination and phasing of the two projects, preferably in combination with other options for water supply to Kabul city as well. It should be considered however that timing is becoming a pressing issue.
4. The net benefit of Gulbahar is relatively small as well, which is due to its high investment cost and the relative small amount of water allocated to domestic water supply. Should it be possible technically to convey more than 100 Mm3/year from Gulbahar to Old and New Kabul city, substantial greater benefits could be generated at Gulbahar for a little reduction in benefit from agriculture and hydropower. Moreover, additional domestic supply from
Page 8 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Gulbahar would improve the reliability of the domestic water coverage under extended drought.
5. The performance of the new assets and their combinations were assessed in a multi- criteria analysis for four metrics: (i) coverage of domestic demand from Old and New Kabul city, (ii) change in total net benefit (as compared to the case where no new infrastructures would be built, referred to as Reference Case), (iii) change in agricultural net benefit (as compared to the Reference Case) and (iv) total amount of electricity produced from hydropower. The advised combination of new infrastructures for each of the four metrics is: • for best coverage of domestic demand: Shatoot and Gulbahar for an investment cost of about 1,800 MUS$, • for greatest increase in total net benefit: i) in case of a financing with a loan: Shatoot, Gulbahar, Baghdara D1, Gambiri, Kama and Konar A 2 for an investment cost of about 3,800 MUS$, ii) in case of a financing with a grant: Shatoot, Gulbahar, Baghdara D1, Surubi II, Gambiri, Kama and Shal for an investment cost of about 5,800 MUS$, • for greatest increase in agriculture net benefit: Shatoot, Gulbahar, Gambiri and Kama for an investment cost of about 2,400 MUS$ (the solution advised above for the greatest increase in total net benefit b i) generates the same high agriculture benefit but for a greater investment cost), • for greatest electricity production: Shatoot, Gulbahar, Baghdara D1, Surubi II, Gambiri, Kama and Shal for an investment cost of about 5,800 MUS$ (this solution only produces the greatest increase in total net benefit if the financing is with a grant, option b ii)).
6. In terms of individual net benefit, the best performing asset is the hydropower scheme Konar A, followed by the other hydropower plants Shal, Baghdara D1 and Baghdara A2. But these infrastructures are single purpose. For multipurpose, the best performing in terms of net benefit are Kama and Gambiri, which bring benefit in electricity production but also in irrigation. Shatoot and Gulbahar, which are the only domestic supply schemes through surface water in the basin, perform poorly in comparison for reasons explained in point 3. However, their net benefit performance is largely dependent on domestic water price and would be significantly boosted if international level prices were used. The worst performing asset is Surubi II which has a negative net benefit in case of a financing with a loan. This report considered the two options, A2 (negligible storage) or D1, for Baghdara. Option D1 performs better due to the ability to modify the flow and produce electricity in a more efficient way. The two options Shal and Konar A were also investigated for hydropower along the Konar River and Konar A performs better.
7. Investment in the Konar River is of great interest since any new scheme built in this region would benefit from the high flow of the river. This is particularly the case in this analysis for Konar A, Gambiri and Kama. Moreover, the performance of these schemes is reliable / robust due to the relatively small variability of the Konar River.
8. This study provides insight into beneficial interactions between new schemes. Further optimisation of the asset operation for a particular combination would be required but the preliminary results from this study are:
Page 9 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
• Along the Panjshir and Kabul river: there is a cascading effect with the chain Gulbahar, Baghdara D1, Naghlu, Surubi I and Surubi II since the electricity production get successively increased. The beneficial effect of Baghdara D1 in combination with Gulbahar is specifically interesting since in the scoping study for strategic option in the Kabul Basin (WB/IBRD 2010), the Baghdara dam showed consistently poor performance; • Along the Konar river: there is also a cascading effect with Konar A and Kama since the water released during winter by Konar A for electricity production can be used for power generation once more at Kama during this period when the irrigation demand is limited; • The combination of Baghdara D1 and Konar A, which are both reservoirs dedicated to electricity production, has the highest potential for increase the electricity production during winter.
9. The target for electricity production of 7,500 GWh/year as assessed by Fichtner (2012) was considered in this analysis. This target is never reached by any of the combinations identified. The production of electricity maximally increases from about 580 GWh/year in the Reference Case to about 6,300 GWh/year for the solution producing the highest amount of electricity. Hydropower can be a major source of electricity production to reach the target, but not the only one and it should therefore be used in combination with other power sources such as thermal power stations and through import (as is already the case under the present conditions with imports form Uzbekistan).
10. The analysis underlines that proposed design for the following new schemes could be improved: • Gulbahar: as mentioned in point 3, if possible technically, the supply of domestic water to New and Old Kabul city should be greater than 100 Mm3/year. Possible values are 150 Mm3/year to secure further the supply under normal hydrologic conditions or 200 Mm3/year for a more reliable supply under drought. Further study should be carried out to examine the feasibility of conveyance of a larger volume and to define more exactly this volume. • Shatoot: the simulations under normal conditions showed that Shatoot reservoir never filled up to its storage capacity of 250 Mm3. Further opertational reservoir studies are recommended. • Gambiri: the technical specifications used for Gambiri were those mentioned in the available feasibility study at the time of this report, in particular a maximum diversion of 50 m3/s from Konar River. This amount appeares low compared to the river capacity. The proposed maximum diversion is now 100 m3/s in the current design stage but no written document was available to support this value at the time of this study. • Shal: the value proposed for its live storage (174 Mm3) is very small compared to the river flow, hence it is not possible to operate the reservoir so as to buffer the flow and produce more electricity in winter. An alternative design with a greater live storage should be more valuable.
1.4.2. Recommendations
The results depend strongly on the data in the feasibility studies. In a portfolio review undertaken under AWARD (2012) many of the feasibility studies were found to be below standard. Thus additional study is required before implementation.
Page 10 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Considering data availability, the analysis had to make a number of assumptions and simplifications as described in the respective report sections. In addition, only those investment options for which sufficient data (feasibility studies) were available have been considered. It is recommended that with more information becoming available the analysis be revised in order to consider the additional information. The main aspects that would benefit from an update include: • Inclusion of specific investments for which feasibility study results become available; • New findings regarding potential changes in catchment hydrology, i.e. runoff, based on anthropogenic activities and climate change; • Political aspects that have an influence on the water utilization in the basin, i.e. that would impact on priorities; • External factors that can have an influence on the basin, with power transfer into- or from other basins as well as power transfer to Pakistan being the most likely scenarios; • Global aspects that could lead to changes on the food or energy market • Price changes.
In addition to the above potential new information, periodic updating of the analysis, especially reflecting developments that have actually been put in place, is recommended.
It should be noted that due to the complexity and uncertainty involved in the future development of the basin the scenarios were tested under operational conditions. Depending on what assets will finally be implemented and in what sequence as well as with what management and priorities, it will be important to conduct detailed studies for the finally agreed assets where their interaction with already existing assets, mainly during the construction and commissioning phase, is assessed in detail. The main aspects here include flow requirements during early construction (river diversion and closure) as well as impounding of the reservoir.
Flood related information, especially with regards to socioeconomic impacts of flood events, is not available in the basin and has respectively not been included in the investment plan. It is recommended that a respective study that uses flood modelling to derive flood risk zones under different discharge events and also studies socioeconomic impacts of flood events is conducted and that the results will be used to update the river basin investment plan by considering flood retention as a potential priority for the reservoirs. Providing flood retention would require reservoirs being as empty as possible which is contrary to the other sectors’ needs of having full reservoirs, i.e. for hydropower production, irrigation water, and domestic water supply. Nevertheless, if occurring frequently, avoiding floods and related costs of flood damage may be more beneficial than other services that a dam can provide. It is therefore further recommended that after such a study has been conducted the investment analysis should be revised under consideration of the flood impact information. Structural integrity of the new assets under flood events is another point for consideration and for which detailed studies related to flooding would be recommended.
Information about groundwater and especially groundwater recharge in the basin is scarce. Groundwater has therefore been included in the model with strong simplifications. With groundwater being an important resource especially for Kabul City, it is recommended that a better understanding of the groundwater and especially its recharge is necessary. Upon availability of such data and depending on the results of such a study, the investment plan should be updated accordingly.
Page 11 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Considering the operation of the investment assets that will finally put in place, it is recommended that a detailed study is carried out to optimize the assets with regards to their agreed function within the overall river basin system. At the current stage the investment plan has ensured that the recommended assets are robust to work under a variety of flow conditions and optimized based on the currently available knowledge. Nevertheless fine tuning, regarding the dams and schemes operation through detailed studies would be necessary to optimize benefits from the individual assets. This should include flood considerations as described above.
Finally, while additional studies are recommended as stated above, this should not delay the government in implementation of this Investment Plan, as they can be undertaken in parallel. We therefore recommend that the government undertakes the following steps (some of which can be undertaken in parallel):
1. Prepare Investment Plans for other basins in order to determine the total infrastructure needs and priorities for the whole country. Under AWARD an investment plan for the Panj- Amu basin will be produced (by February 2013), while information for an investment plan may be available from the Master Plan currently being developed by ADB for the Helmand Basin. This would leave investment plans for the Northern and Hari Rod-Murghab basins still to do. A knowledge base has been set-up for these basins under AWARD therefore the information is available to complete these plans.
2. While it has been agreed that domestic water supply for Old Kabul City is the main priority, it has not been decided by the government or stakeholders what the next priority should be. Therefore the government should decide on which of the following is the priority for the Kabul basin (and other basins): net benefit, water supply for New Kabul city, hydropower production, or agricultural production.
3. Present the investment plan(s) to donors.
4. Based on the agreed development priorities, and the funding commitments from the donor (as well as central government), the appropriate set of infrastructure options can be decided upon.
5. Based on the chosen set of infrastructure options, undertake transboundary negotiations with Pakistan.
6. Prepare a financing plan for each of the schemes within the investment option chosen, in co-ordination with the relevant donors and central government.
7. Implement the schemes according to the timeline presented in the plan(s).
Page 12 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
2. BACKGROUND AND CONTEXT
2.1. MOTIVATION OF THIS ANALYSIS
The Afghanistan Water Resources Development (AWARD) Technical Assistance Project was prepared through a World Bank Water Resources Development Proposal which was approved by the Afghanistan Reconstruction Trust Fund (ARTF) in December 2008. The Grant became effective upon the signing of the ARTF Grant No. TF0903637 on 23 March 2009, and follows Conditions for Grants made by the World Bank out of various funds. The Technical Implementation Support Consultancy (TISC) was contracted by the Ministry of Energy and Water (MEW) in January 2011 and the team was mobilized in late February 2011. The project was conceived to enhance and develop principles of Integrated Water Resources Management (IWRM), a primary theme for practitioners, institutions and government agencies alike.
Water resources endowment in Afghanistan is significant on an annual per capita basis, with five major river basins: Kabul, Panj-Amu, Hari Rod-Murghab, Northern and Helmand (see figure below), with numerous key rivers contributing to the total yield. However, measurements show that there is considerable seasonal variability in rainfall-runoff causing frequent periods of local and widespread drought and flood. Hence, the need for infrastructure investment for development of storage and delivery systems is vital for securing long term water supplies and retaining floodwaters to support economic development and poverty reduction.
Figure 1: Afghanistan river basins (source: Procedure on the framework for water resources management in the river basins, MEW May 2011)
Page 13 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Key to Afghanistan’s economic development and poverty reduction efforts is an increase in significant scale investments in effective and sustainable water resources development and management. The river basin perspective and integrated water resources management approaches have been adopted by the Afghanistan government for water resources development since 2002. This is reflected in the new water law of 2009 and the institutional structure of the Ministry, which at sub national level is subdivided into basin agencies.
Transitioning from the Vision of “River Basin Planning (RBP) perspective and IWRM approaches” to a Mission or program with concrete Actions has not yet been fully realized. This is understandable amidst the uncertainties and variability of adjustable government and donor priorities, evolving policies, complications in coordination and tenuous security environment. Although being addressed by numerous government and external development initiatives over time, there has not been a cohesive, comprehensive follow-up to the prospectus offered by the likes of the Water Resources Projects Atlas planning initiative, as one example. Following the ANDS (Afghanistan National Development Strategy) initiative and the Kabul Conference in July 2010, the MEW is involved in the ARD Cluster in developing the National Priority Program (NPP) for National Water and Natural Resource Development and is committed to investments in multi- purpose water resources infrastructure.
Putting the RBP and IWRM vision principles into effect as actions under the National Priority Program (NPP) and parallel programs within the MEW will serve to satisfy the future demands of water resources in a sustainable manner. Considering the complexities of such ambitious undertakings (policy, technology and socio-economics), to achieve the desired results, there are key considerations and issues to be addressed as a matter of course, including;
• Balancing and phasing the priorities and benefits of rehabilitation and small water sector projects with quick yield focus, with those of longer term yielding medium and larger projects implementation; • Analysis and prioritization of projects and preparation of implementation plans to an internationally acceptable standard within a multi-sectoral basin framework; • Improve effectiveness of coordination across water-related sector institutions to ensure shared-vision planning, development, and management of water across related institutions; • Enhance the technical, managerial and human resourced development capacity in MEW (and related line ministries) for integrated water resources management and project preparation.
2.1.1. Available Information
This investment plan focuses on the Kabul basin and builds on earlier works done. In the 1970s a large basin analysis and master planning was carried out by MECO (1978). This plan also formed the basis of the scoping study of the WB (IBRD/WB 2010) in which the most promising options were investigated through an economic optimization of net benefit in GAMS. The costs for the economic data used in the WB scoping study were largely based on prices from the MECO study escalated to 2004 costs using a GDP deflator of 2.37. Because costs have such a strong influence on the final outcome of the optimised infrastructure, the report states that getting more reliable cost data should be a priority.
Toosab and RCUWM (2006) in the Integrated Water Resources Management, Kabul River Basin report, review further infrastructure development options using some of the newly carried out pre-
Page 14 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
feasibility studies. They also updated various costs and prices and scoped a number of alternative options. Feasibility studies for specific projects were used for project specific assessments.
Information on domestic water supply and demand of Kabul city has been collected from Beller et al 2004. This report investigates the use of aquifers in and around Kabul city and options to enhance the recharge of aquifers. The report also studies the demand of the Kabul city and master plan for water supply targeted 2015. The options to supply water to New Kabul city is investigated in the Master plan for Kabul Metropolitan Area by JICA (2009). Based on the master plan, JICA (2012) has conducted a series of studies on water storage facilities to supply water to the New Kabul city.
The present and future power development of the basin is reported in Norconsult and Norplan (2004). Fitchner, 2012, has updated the 2004 master plan for demand forecast and the generation and transmission plan.
2.1.2. Management Options and Issues under IWRM Approach
There are many definitions of Integrated Water Resources Management (IWRM), essentially all using the same principles. The GWP, in 2002, defined IWRM as: "a process which promotes the coordinated development and management of water, land and related resources, in order to maximize the resultant economic and social welfare in an equitable manner without compromising the sustainability of vital ecosystems”.
The water sector in Afghanistan is going through institutional reforms aiming at IWRM in river basin planning. It should be noted though that IWRM is a flexible and common sense approach to water management. Reform strategies should recognize that the water sector in Afghanistan is of crucial importance and has generally been managed using administrative territorial boundaries rather than natural catchment areas. This introduces a number of very specific challenges and local needs.
IWRM builds on the Dublin principles established during the International Conference on Water and Environment in Dublin in 1992 and takes into account that: • Water is a finite and vulnerable resource essential for life and the environment; • Water development and management should be based on a participatory approach, involving users, planners and policy-makers at all levels, and decisions should be taken at the lowest appropriate level; • Women play a central part in the provision, management and safeguarding of water; • Water has an economic value in all its competing uses and should be recognized as an economic good; • The most appropriate geographical entity for the planning and management of water resources is the river basin, including surface and groundwater; • IWRM in basins is an iterative “learning by doing” management cycle and regular evaluation of the process and readjustment of the strategy and goals will be required.
Other guiding principles are: • In order to effectively carry out all the tasks related to integrated water management a separation is needed between constitutional tasks (policies, legislations), organizational tasks (planning, management, regulation) and operational tasks (water delivery, maintenance of systems, rehabilitation);
Page 15 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
• The environment is recognized as a water user and its rights should not be compromised; • Setting priorities for water use in general requires that all sub sectors should be balanced in such a way that they do not compromise other uses; • In case of emergencies, drinking water is the first priority since it involves the difference between life and death. Providing water for environment is also very important since once destroyed or dead it cannot (easily) recover and its services could be lost forever. These are typical prerequisite demands, followed by irrigation, industry, hydropower, fisheries and others, which are negotiable.
2.1.3. IWRM and Management in Afghanistan and the Kabul River Basin
The water sector reforms started with the 2002 Kabul understandings and have since achieved considerable progress including establishment of a policy coordination body, the Supreme Council of Water (SCoW), and its supporting technical secretariat (2005). This was followed by the promulgation of a new water law (2009) and three required procedures for its implementation (2011). In this report we have used the procedure for Integrated Water Resources Management in Basins (MEW, 2011) as reference for the official sub basins. The MEW and the provincial water management departments were restructured to enable better implementation of Integrated Water Resources Management. The restructuring was started in 2011 and is still ongoing.
The figure below shows the new organogramme of the MEW. The importance of the river basin organisations, here referred to as authorities, can be deduced from the grading of its managers (grade 1) which is the same as for general directorates. The basins’ prominent position in the organogramme, directly reporting to the Deputy Minister of Water, also indicates the importance of basin planning.
Figure 2: The organogramme of the Ministry of Energy and Water (Source MEW, 2012)
Page 16 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
The sub-ordinate levels of the basin organisation (i.e. under the river basin authority) are referred to as sub basin offices. The MEW has delineated the sub basins as much as possible according to hydrological boundaries. However, in certain cases this was not possible and administrative boundaries had to be mixed with natural hydrologic boundaries. Nevertheless the basins and sub basins form a good planning basis for integrated water resources management. Recognition of the basin principle underlying the water resources planning and management process is a significant step and puts Afghanistan among the world leaders in implementing Integrated Water Resources Management in Basins with regards to domestic and irrigation water but also with regard to the upcoming industrial water requirements that are expected to contribute to the necessary economic growth. In line with the provision of water quantity, water quality, especially through avoiding pollution, will be a challenge. It needs to be understood that in this regard a “polluter” is a significant water user as polluted water can, depending on the extent and type of pollution, not be used by other water users anymore.
Collection and treatment of sewage, both liquid and solid waste, will be of major importance in order not to further reduce the available water resources through pollution. So far efforts in this regard have not resulted in respective plans, and thus have not been considered in this study.
The balance that needs to be found in the Kabul River basin, considering both the harnessing of available water resources as well as the avoidance of pollution, includes the water needs of a variety of stakeholder groups, including: • Population with domestic water needs • Riparian population with flood protection needs • Irrigated agriculture for food production • Industry with processing water needs • Mining activities with processing water needs • Hydropower producers for energy generation • The environment with the need to maintain minimum flow requirements
Polluters that reduce the availability of usable water resources include: • Population with pit latrines leading to groundwater contamination • Population producing solid waste that without collection and treatment pollutes surface water • Population producing solid waste that without proper disposal contaminates groundwater through leaching • Industry that discharges untreated processing water • Mining that discharges untreated processing water
2.2. MAIN CHARACTERISTICS OF THE RIVER BASIN
2.2.1. Physical characteristics
Afghanistan is a landlocked country with a total area of about 652,000 km². It is bordered by Turkmenistan, Uzbekistan, and Tajikistan to the north, China to the northeast, Pakistan to the east and Iran to the west. The country has a harsh climate of the continental type and the severity of winter is accentuated by the high altitude of much of the country. Winter and spring are the seasons of most variable weather and most of the annual precipitation occurs from November to
Page 17 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
May. Summers are warm to very hot with little or no precipitation or streamflow, except in rivers and streams fed by melting snow and glaciers.
Monsoon influence can occur in the easternmost part of Afghanistan. It is also the most easterly country to experience the influence of the Mediterranean Sea, which is the source of most of the depressions that bring the winter precipitation and cause erratic rainfall in spring. Snowfall is concentrated in the central mountains and the higher ranges in the northeast. Overall the weather pattern with regards to precipitation is highly variable throughout the basin. The average basin discharge is about 19,900 Mm3 annually. An overview of the hydro-meteorological conditions and of the snow coverage is given in the figures below, as well as an overview of the principlan sub- basins.
Figure 3: Climate profile for Kabul River basin (Kabul Atlas, AWARD, 2012)
Page 18 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 4: Snow coverage in the Kabul River basin (Kabul Atlas, AWARD, 2012)
Figure 5: The Kabul River basin, its sub-basin divisions (left) and sub-basin office locations as well as administrative basin units (right) (Kabul Atlas, AWARD, 2012)
The Kabul River Basin is located in the eastern part of Afghanistan. The Kabul River flows in a general west to east direction, joining the Indus River in Pakistan’s Northwest Frontier Province.
Page 19 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
The basin drains around 12% of Afghanistan. The basin generates almost 40% of Afghanistan’s total runoff. The basins surface water resources supply approximately 28% of the total irrigated area in Afghanistan (IBRD/World Bank, 2010). The basin accounts for 35% of Afghanistan’s population, and has the fastest population growth rate in the country. The basin includes the Kabul urban area, which is one of the biggest engines of economic growth in the country. The basin also includes a large fraction of the installed energy generation capacity (IBRD/World Bank, 2010).
The Kabul River basin was digitized with a size of total 85,971 km2 and the area can be boardly divided in three parts. • The central area of Kabul River and its tributaries including the Afghan part of the Kunar River (52,976km2) • Southern part of Shamal and Khoram area that drains directly to the Indus River Basin (18,053 km2) • Pakistan part of Kunar River (14,941 km2)
The modelling analysis focuses primarily on the central area of the Kabul Basin. All the proposed infrastructure that have feasibility studies and financial analysis belong to the central part of the Kabul Basin (see development options in section 2.5). The Southern part of Shamal and Khoram area has no major infrastructures planned at the time of producing this investment plan report. The Pakistan part of Kunar River is outside the scope of the study.
In describing the Kabul River basin in detail as well as for the purpose of this investment planning we distinguish between the following hydrological units and respective terminology: • Sub basins as delineated by MEW in their procedures for IWRM in river basins (2011); • Catchment sub divisions of the modelling areas according to the gauging stations in the basin.
The Kabul Basin is divided into the following eight sub-basins (see figure above) based on climate, hydrology, and physiography as per IWRM procedure 2011.
1. The Medium Kabul sub basin, contains three small rivers, the Maidan, Paghman, and Qargha, which all originate upstream of Kabul city. These rivers join at different confluences throughout Kabul city and flow through the centre of Kabul city. The Maidan river is formed by numerous small streams west of Kabul city. The River changes its name to Kabul River before it enters the city and flows across the city where it is joined by the Paghman and Qargha tributaries and then flows further until Naghlu dam where it flows into the Panshir River.
The main water projects and users of the Kabul River are Qargha reservoir, Shatoot irrigation and water supply to Maidan Shar and Tangi Saidan. When the Maidan river reaches Kabul city it has little or no water due to high water withdrawal for irrigation. The annual average flow is approximately 140 Mm3 at Maidan, 490 Mm3 at Tangi Gharu, and 3,400 Mm3 at Naghlu (see figure below). Only 15% of flow at Naghlu is contributed by the Kabul River. After the confluence with the Panshir river the river continues as Kabul River.
Page 20 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 6: Historical hydrographs in the Medium Kabul sub-basin. Mind the difference in vertical scale.
2. The Logar sub basin drains a dry and hilly watershed south of the Kabul city. a. The Logar watershed comprises approximately 75 percent of the drainage area of the Logar-Kabul area. There is modest but significant irrigated agriculture along the Logar River valley and in the river valleys upstream of Kabul. b. The main water users are a) Chak e Wardak dam for hydro power production b) narrow strips of irrigated land along the river and c) Kole Hasmat Khan wetland South of Kabul. c. The average annual flow is 230 Mm3 at Kajab and 300 Mm3 at Sangi Naweshta (see figure below).
Figure 7: Historical hydrographs in the Logar sub-basin.
3. The Ghorband sub basin is formed by the Ghorband River flowing until its confluence with the Panjshir River. The average annual flow at Ghorband River is 730 Mm3 at Pule Ashawa
Page 21 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
(see figure below). After the confluence with the Panshir River the river is referred to as Panshir River.
Figure 8: Historical hydrographs in the Ghorband sub-basin.
4. The Panjshir Sub Basin is formed by the Panjshir River and its tributaries, Salang, and Shatul rivers. - The upper portion of this watershed consists of steep mountain valleys in the Hindu Kush mountain range, which reaches over 6,000 meters above sea level and remains snow covered throughout the year - The southern portion of the Panjshir watershed opens onto the broad and gently sloping fertile Shomali Plain which has some of the most important irrigated land in the basin. - Although the drainage area of the Panjshir River at Shukhi is smaller at approximately 84 percent compared with the Upper Kabul River, its average annual streamflow is over 6 times as large - Average annual runoff of Panjshir River is 1,710 Mm3 at Gulbahar (see figure below). - Below their confluence, the Panjshir and Ghorband Rivers together are named Panshir River and flow down to the Naghlu dam. The combined flow is 3,080 Mm3 observed at Sukhi.
Figure 9: Historical hydrographs in the Panjshir sub-basin.
5. The Laghman Sub Basin includes the Alishang and Alingar rivers, which after their confluence are referred to as Laghman River. The Laghman River, drains into the Kabul River at Darunta dam where the valley begins to widen. The average annual flow is 1,850 Mm3 (see figures below).
Page 22 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 10: Historical hydrographs in the Laghman sub-basin.
6. The Kunar Sub Basin is formed by the Valley of the Kunar River. The river originates from the Karakoram range south of Wakhan corridor in Pakistan. This a glacier fed river and it maintains a high flow in the summer. Due to the high flow, several projects are proposed in the Kunar sub basin. The average annual flow is 12,130 Mm3 at Asmar and 14,830 Mm3 at Pul e Kama (see figure below). The present water users are Konari irrigation, Gambiri irrigation, Sigi irrigation and Kama irrigation along the river.
Figure 11: Historical hydrographs in the Konar sub-basin.
7. The Lower Kabul Sub Basin extends downstream from the Naghlu basin and after confluence of the Ghorband, Panshir, Medium Kabul and Logar Sub Basins and flows to the Pakistan border. The Lower Kabul Sub Basin has the Laghman and Konar Rivers as tributaries. It comprises two large watersheds to the north or left bank of the main stem of the river. a. There are numerous small tributaries on the right bank, including the Surkhrud near Jalalabad, which, with a population of approximately 120,000, is the only large city in the Lower Kabul subbasin. b. As the main stem of the river continues eastward, the valley widens into a broad plain that comprises the second largest and second most agricultural area in the Kabul River basin c. Three dams and reservoirs have been constructed in the Lower Kabul area, mainly for hydropower purpose. Naghlu dam and Sarobi dam just below the confluence of Upper Kabul and Panjshir Rivers and further below Darunta dam, just upstream form Jalalabad City. The latter dam also has an important irrigation function.
Page 23 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
d. Streamflow in the lower basin comes predominately from the two large, mountainous sub-basins, namely the Laghman and the Konar, whose higher snow- and glacier-covered areas reach nearly 6,500 meters above sea level. e. Except for the high mountain areas to the north, the climate of this lower region is influenced by the southwest monsoon, complemented by a few days each year of hard frost or freezing temperatures. f. The average annual flow is 6,000 Mm3 at Darunta and is 19,900 Mm3 at Dakah before the Pakistan border.
Figure 12: Historical hydrographs in the Lower Kabul sub-basin. Mind the difference in vertical scale.
8. The Shamal and Khuram Sub Basin (which includes the Gomal area) is formed by several small tributaries, and they all flow directly to the Indus River in Pakistan.
The topography of the basin is shown in the figure below. The northern areas of the catchment consist of high mountains and steep slopes, while the southern portions drains mainly low mountain ranges, foothills, and plains. The main flow contribution originates from the Northern tributaries which are largely fed by snowmelt and glaciermelt water. The glaciers in the upper river reaches of the river basins represent a long term asset that stabilizes the water supply within and between years and are a source of steady streamflows. The future role of the glaciers will depend on their rate of retreat or expansion – a process associated to climate change and atmospheric pollution observed in some regions of the world.
Page 24 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 13: Topography and elevation in the Kabul River basin (Kabul Atlas, AWARD, 2012)
The lower eastern portion of the basin towards the Pakistani border includes extensive but rapidly diminishing forests (11,800 km2) that comprise nearly 93 percent of the country’s forest area. Rangeland (32,700 km2) is limited to approximately 13 percent of the national total, as is rainfed agriculture (1,140 km2), which accounts for only 3.5 percent of the country’s total rain-fed agricultural area. Irrigated land in the basin, with intensive cultivation of one or two crops per year, is currently estimated to be 4,100 km2, or nearly 25 percent of the estimated 15,600 km2 of the irrigated area in Afghanistan. The four existing hydroelectric power stations in the Kabul River basin (Mahipar, Naghlu, Sarubi, and Darunta) form the core of the country’s hydro power system (IBRD/World Bank, 2010).
2.2.2. Population and Economy
Aside from two major urban centres, the basin population in the Kabul River basin is rural. A population overview is given in the table below. The population is highly dependent upon irrigated agriculture.
Table 3: Kabul River Basin Population, from census data published by Central Statistic Organization of Afghanistan (CSO, 2012) Province* Population Kabul ** 3,818,700 Kapisa 413,000 Parwan 620,900 Wardak 558,400 Logar 367,000
Page 25 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Province* Population Nangarhar 1,409,600 Laghman 417,200 Panjsher 143,700 Konar 421,700 Nooristan 138,600 Chitral (Pakistan) 318,689 Source: http://www.infopak.gov.pk/districtPK.aspx Total 8,627,489 *Khost, Paktiya and Paktika Provinces which are part of the Indus basin but do not drain into the Kabul River are not shown here ** Numbers are inconsistent depending on source, e.g. numbers shown by JICA and CSO for Kabul differ.
For Kabul city, JICA (2009) and JICA (2012) provide detailed information on the population projections for Old and New Kabul City. The reports envision a population of 5.0 million for Old Kabul City and 1.5 million for New Kabul City for 2025. For the purpose of this study the growth has been linearly extrapolated to show population numbers of 5.2 million for Old Kabul City and 1.9 million for New Kabul City for 2030. Combined the cities will house 6.5 million and 7.1 million people in 2025 and 2030 respectively.
The Gross Domestic Product for Afghanistan is estimated at about US$ 1,000 per capita (CIA, 2012). This is very low compared to world averages and in addition disguises the acute income disparities in-between the population.
A reported 38% of the people still live below the poverty line (CIA, 2012). The lowest 10% of income earners generate 3.8% of national income while the top 10% generate 24% of national income. The current wage of a worker is about $5/day, which amounts to $1560/year. The salary of skilled (experienced) labourers may be about twice as much.
The unemployment rate is approximately 35% (estimated from CIA, 2012).
2.3. CRITICAL ISSUES
Sustainable water resource use is a key factor for long lasting development. Currently a strongly unsustainable situation exists in the Kabul River Basin with the upper catchments degrading, groundwater levels dropping and pollution of water sources increasing. Sustainable water management would be a prerequisite to the long-term viability of both urban and rural communities in the basin.
There are a number of issues that are becoming increasingly critical in the Kabul River basin: • Competition of stakeholders for water resources: - Drinking water supply for urban centres in need of a stable year-round water supply of high quality - Organized sewage treatment and waste disposal - Flood control with the need for low level in reservoirs before the flood season - Hydropower with the need for timely flow (peak needs in winter) - Irrigation water with a need for timely flows (peak needs in summer) - Industry with the need for process water and discharging of effluents and pollutants - Environmental requirements with a need for environmental flows to maintain wetlands, water quality, fish populations, ecosystem services and recreation potential.
Page 26 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
- Groundwater recharge is essential for sustainable supply • Population growth leading to increased water demand as well as increased pressure on land resources • Mismanagement leading to upper catchment degradation which results in increased runoff in the precipitation period accompanied by increased erosion and respective sediment intrusion in the watercourses • Pollution due to wastewater discharge from domestic and industrial sources rendering water quality unsuitable for drinking and/or irrigation use and fishing • Climate change or climate variations with potential impacts on glacier flow. Climate change is not well understood in the Kabul River basin which leads to the need for robust and resilient planning • Transboundary water need / potential water conflict (including Konar River upper catchment located in Pakistan)
From a purely economic perspective, most public institutions are still relatively weak while the underlying legal/regulatory environment is equally fragile. This, in turn, has greatly inhibited private investment, particularly with respect to the extensive but largely undeveloped mineral resources in the country. Government resources are further constrained by the absence of an effective tax regime. Revenue “leakages” from illegal opium exports are equally debilitating. Even the parallel influx of external public funding can sometimes undermine the integrity of the public financial sector and can, in effect, simply delay the indigenous development of a sustainable long-term socio- economic development trajectory.
2.3.1. Degraded infrastructures and uncoordinated development
Afghanistan’s economy is constricted by instability and conflict which exacerbates its levels of poverty, and has resulted in a very low level of development of water resources and very low levels of water-related services, including water supplies, hydropower, and storage.
The country faces tremendous stresses internally and is at a critical point in its strategy on water resources development since the newly rehabilitated and reconstructed infrastructure is insufficient to meet the growing demands of the communities for domestic/industrial water supply, hydropower and irrigation.
Further to the general situation the basin features some key hydraulic assets that include hydropower as well as irrigation schemes (partly multipurpose). A list of existing hydraulic assets in the Kabul River basin is shown in the table below. Similarly to the choice of new development options (see section 2.5), only medium and large existing hydropower infrastructures (greater than 10 MW following the EHSA (2004) classification) were considered (except for Chak-e-Wardak for which information has been readily available and due to the relative importance of this scheme for storage (22Mm³)).
Table 4: Existing large hydraulic assets (plus Chak-e-Wardak)
Scheme River Purpose Year Pi Pa Q S A (ha) Source (MW) (MW) (MCM/yr) (MCM) Norconsult, Mahipar Kabul Hydropower 1966 3X22 53 485 ROR NA 2004 Norconsult, Naghlu Kabul Hydropower 1967 4x25 75 3560 496 NA 2004
Page 27 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Scheme River Purpose Year Pi Pa Q S A (ha) Source (MW) (MW) (MCM/yr) (MCM) Norconsult, Sarubi Kabul Hydropower 1957 2x10 20 3560 6.5 NA 2004 Norconsult, Hydropower 2004 Darunta Kabul and 1967 3X3.85 7.5 5920 40 23075 Gambiri Irrigation Feasibility, 2008 Chak-e- Norconsult Logar Hydropower 1938 3x1.2 0.9 235 22 Wardak (2004)
Pi – Installed power, Pa – Actual power, Q - Average annual stream flow, S – Storage, Irrigated area – A, ROR – Run of river
2.3.2. Water Availability and Scarcity, Competing Stakeholder Needs
Surface water availability in the Kabul River basin is dependent on seasonal runoff resulting from glacier melt, snowmelt, rain and catchment baseflow. Suitability of the water, in addition, depends on the state of the water courses with regards to pollution levels and respective usability for different purposes. Availability is generally high in spring and summer when snowmelt in the upper catchments leads to runoff of meltwater. With catchment degradation the runoff characteristics of the rivers may become increasingly extreme which can lead to increased floods (numbers and intensities) in the summer months and increased droughts after the snowmelt season due to decreased retention potential of the upper catchments.
With the continued and expanding use of groundwater, levels are gradually dropping. With periodic droughts, a reported 60-70% of the Karezes are no longer in use while a reported 85 percent of the shallow wells have dried up. Between 1965 and 2005, i.e. over a period of 40 years, the groundwater table in Kabul has dropped by 6.5m (BGR, 2005). The need to compensate for this by digging deeper wells or fetch water from other sources is expected to have negative social and economic consequences.
Low water availability is not only a quantitative problem but also a timing problem. The timely availability of water in a basin can to some extent be controlled by dams and reservoirs which store the water and release it with a delay and a different flow regime depending on dam size and operation schedule. Conflicts may arise not only based on water quantity demanded by competing stakeholders but also by different timing needs. Hydropower production for example needs reservoirs as full as possible at any time and discharges the water based on electricity consumption needs (i.e. in winter). Irrigation water users on the other hand need timely water supply only during the growing season. Flood control would require the reservoirs to be as empty as possible to provide flood retention.
2.3.3. Upper Catchment Degradation
Degradation in the upper catchments caused by the increasing population has lead to unsustainable conditions with overuse of natural resources through deforestation and overgrazing. The decreased ground cover is expected to cause reduced water retention capacity resulting in increased and more imminent runoff which in return may lead to more extreme streamflow conditions with increase in flood and drought situations along the rivers. Floods and droughts can have serious impacts on the communities through destruction of crops, housing and infrastructure,
Page 28 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
loss of property, livestock and life and interruption of business life through primary and secondary impacts.
2.3.4. Pollution of Water Resources
Pollution is observed in both surface water and groundwater resources. Surface water is polluted by uncontrolled domestic waste and sewage disposal. Raw industrial effluents and the more widespread use of chemical fertilizers may play a large role in the future and should also be addressed now (IUCN, 1994). Groundwater quality suffers from wastewater leaching into the underground from unsanitary open pits and leakage from septic tanks (BGR, 2005). While being costly, interventions to deal with water resource degradation will be unavoidable to maintain long term sustainability.
2.3.5. Climate Change
The complex topography with different natural conditions like high-altitude and arid areas and the mesoscale weather systems of different influences (Mediterranean and monsoon) of the central Asia region need to be taken into account in Afghanistan. The Global Climate Models (GCMs) typically perform poorly over the region, a fact that needs to be taken into consideration when discussing and judging climate change projections. Importantly, the GCMs, and to a lesser extent Regional Climate Models (RCMs), tend to overestimate the precipitation for the arid and semi-arid areas in the north (IPCC, 2007).
The regional climate change model suggests that in general in the arid region of Central and South East Asia, the average annual temperature would rise and average annual precipitation would decrease (IPCC, 2007) as shown in the figures below. This could result in an increase in crop water requirements and other demands while the basin will have less annual river flow. However no quantitative data is available for this kind of analsyis. Climate change could have a major impact in Afganistan since the rivers are fed by snow and glaciers. Therefore, we have carried out sensitivity analysis to address the issue of climate change with varying flow regimes and with a sequence of dry flow in the model.
Figure 14: Temperature anomalies with respect to 1901 to 1950 for the central Asian land region for 1906 to 2005 (black line) and as simulated (red envelope) using Multi Model Data (MMD models)
Page 29 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
incorporating known data for the same time period. Temperatures projected by MMD models for the A1B scenario (orange envelope) are shown for 2001 to 2100. The bars at the end of the orange envelope represent the range of projected changes for 2091 to 2100 for the B1 scenario (blue), the A1B scenario (orange) and the A2 scenario (red). (IPCC, 2007)
Figure 15: Temperature and precipitation changes over Asia from the MMD-A1B simulations. Top row: Annual mean, DJF and JJA temperature change between 1980 to 1999 and 2080 to 2099, averaged over 21 models. Middle row: same as top, but for fractional change in precipitation. Bottom row: number of models out of 21 that project increases in precipitation. (IPCC, 2007)
2.3.6. Transboundary Water Management
The Kabul River basin is located in both Afghanistan and Pakistan. The Konar catchment, which is part of the basin, features the particularity of receiving part of its runoff from Pakistan, while just downstream of the confluence between Konar- and Kabul River the waters flow back into Pakistan.
2.4. FUTURE TARGETS
Future targets in the Kabul Basin aim to conserve water resources and to provide water in sufficient quantity, quality, and timing for all of the actual and potential water users in the Basin. The aim will largely be met by construction of several dams in the different sub-basins which in combination can provide the required water storage and flood retention capacity. In addition, water resources conservation, especially through reduction of pollution of surface- and groundwater resources, will be an important issue. The primary goal over the coming years is the provision of sufficient water quantities, although the rapidly growing population with increasing domestic and
Page 30 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
irrigation water demands will make it very difficult to achieve this goal. An overview of the currently planned projects is shown below.
2.5. DEVELOPMENT OPTIONS
Several development projects have been identified in the Kabul River basin. The project options are listed in the table below, and an overview is shown in the figure below. The listed dams cater for different and mostly mixed purposes. The new schemes considered here are only those for which detailed information, i.e., recent feasibility studies with cost information, was available at the time of this study. This is to ensure an equal and confident level of analysis. This implies in particular that the schemes Kajab (Logar River), Gat (Logar River), Totumdara (Ghorband River) and Laghman (Laghman River) were not investigated in this report due to unavailability of a feasibility study.
We have generally concentrated on larger schemes with a significant influence on the basin hydrology and with potentially large benefits. For example water supply and sanitation schemes for small towns have not been dealt with individually, but were grouped under rural water supply. Equally small hydropower projects are not included in the investment analysis. According to the ESHA (2004) hydropower schemes that produce less than 10 MW are considered small. We have used this limit to exclude the smaller schemes, which have negligible influence on the total hydropower production in the basin.
Table 5: Project options in the Kabul River basin – reservoirs (with existing feasibility studies) S S Q A C Source and Scheme River Purpose P (MW) t l (Mm3) (Mm3) (Mm3/a) (ha) (MUS$) stage of study Domestic, Shatoot Irrigation, 255 Pooyab (2011) Maidan 4.5 250 236.5 170 362 Dam Hydropow 7 Feasibility study er Irrigation, Yekom (2010) Gulbahar hydropow 54,0 Norconsult(2004) Panjshir 116 490 405 1725 1,437 Dam er, 00 JICA (2012) domestic Feasibility study Hydropow Baghdara er Fichtner (2007) Panjshir 165 1.9 1.8 3022 NA 475 A2 Dam Pre-feasibility study
Hydropow Baghdara er Fichtner (2007) Panjshir 244 400 275 3022 NA 547 D1 Dam Pre-feasibility study
Technopromexport Surubi II – Hydropow Kabul 105 ROR ROR 4077 NA (1988) Stage 1 er Feasibility study 1,058 Technopromexport Surubi II – Hydropow Kabul 23 ROR ROR 4077 NA (1988) Stage 2 er Feasibility study Hydropow CES (2009) Shal Dam Konar 798 1,874 174 11577 NA 1,819 er Feasibility study MECO(1978/79); Konar A Hydropow Konar 366 1,680 1000 11577 NA 876 Norconsult (2004) Dam er Pre-feasibility study Irrigation Gambiri 600 Toossab (2008) Kunar Hydropow 23 ROR ROR 13070 253 Scheme 0 Feasibility study er Irrigation Mahab Godss Kama 620 Kunar Hydropow 45 ROR ROR 14829 341 (2008) Scheme 0 er Feasibility study
Page 31 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
P – Installed power, Qt - Average annual stream flow on site, St – Total Storage, Sl – Live storage, Irrigated area – A, ROR - Run off River, C – Total Investment cost (Capital Cost + Land Acquisition and Resettlement + Contingencies and Administration).
All proposed options have different benefits and impacts. With the final operation schedules not fixed, the impacts of the schemes are difficult to discuss but the following list of competing stakeholders and their requirements can form a guideline for a future full assessment.
Primary needs related to the dams include:
• Reservoir use - Water for human consumption as domestic water - Water for agricultural use through irrigation - Water for energy production through hydropower • Downstream use - Water for downstream domestic users - Water for irrigation - Water for industrial users - Water for the environment through maintaining an environmental flow component - Floodwater control through flood retention - Transboundary water needs
Figure 16: Overview of assessed potential water infrastructure projects
Page 32 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
3. WATER RESOURCES AVAILABILITY AND DEMAND FOR YEAR 2030
3.1. WATER RESOURCES AVAILABILITY FOR YEAR 2030
Two types of water resources are considered for future conditions: surface water (rivers) and groundwater.
3.1.1. Surface Water resource
The flow of the rivers in the Kabul basin is modelled through a semi-distributed river schematic, itself based on the flow gauge stations in the basin. The flow in the river increases from upstream to downstream, between segments formed by the gauge stations. The streamflow values are based on historical observations from 1965 to 1979 before the period of conflicts, turmoil and war started. Three streamflow regimes are considered here to represent the future flows: a Median streamflow regime, extended by regimes for Dry 5 and Dry 10 scenarios. The median (50% chance of occurrence, every 2 years) was used instead of the average to ensure that it covers the most frequent streamflow conditions.
Two annual deviations from the median, which are assumed to have negative impact (less water) and labelled Dry 5 and Dry 10, are defined as being respectively the probable drought occurring every 5 and 10 years (see table below) and supposed to be representative of future conditions. These deviations were estimated with the empirical stochastic distribution of annual flows and adjusted according to the average monthly flow. The estimations at the stations Gulbahar (Panshir River) and Maidan River are illustrated in the figure below. No wet regime was examined since flooding is not included in the analysis due to unavailability of flood damage data.
Table 6: Estimated variability of the hydrological regime in the Kabul River basin Hydrological regime Definition Why? 3 consecutive dry years The driest sequence of 3 years To represent a continuous measured in the historical time- drought over 3 years series Dry 10 Probable annual drought To represent a year of drought occurring every 10 years Dry 5 Probable annual drought To represent a year of mild occurring every 5 years drought. Median Annual Median calculated with Most likely yearly streamflow the historical time-series
Page 33 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 17: Empirical drought curve at two stations in the Kabul basin
A time series of climate data on annual precipitation anomalies in Afghanistan and the vicinity of Afghanistan (MRRD 2004 in CPHD, 2011) shows that severe droughts are generally characterised by three consecutive dry years. During the last century there were three of such sequences, around 1900, around 1970 and again by the end of the 20th century. The sequence of the 1970s occurred during the period for which hydrologic data are available. We have used the actual data of these years to analyse the water supply with new water supply projects under serious drought conditions. This also provides an indication of conditions that could potentially occur more frequently as a result of climate change.
Figure 18: Long term rainfall pattern in Afghanistan and vicinity. Source: CPHD (2011).
The dry conditions were chosen as three consecutive dry years in three strategic locations in the basin. These conditions were identified using the streamflow data at these three locations: • Flow of the Panjshir River at Gulbahar, which will be used to examine the new reservoir Gulbahar: the driest observed sequence is 1975-76 to 1977-78. • Flow of the Maidan River at Maidan, which will be used to examine the new reservoir Shatoot: the driest observed sequence is 1976-77 to 1978-79. • Flow of the Konar River at Asmar, which will be used to examine the new reservoirs Shal and Konar A: the driest observed sequence is 1961-62 to 1963-64.
The sequence identified for each station is represented in the figure below. The Maidan River is clearly having the largest variability and most critical dry sequence.
Page 34 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 19: Historical streamflow (left) and 3-years moving total (right) at three locations in the basin. The line in black is the Median streamflow. The driest sequence is circled in red.
3.1.2. Groundwater resource
Little information was available on the groundwater resource. In theory, a variable streamflow regime, as described above, should be associated with variability in the groundwater resource. In particular, reports (e.g. KfW / Beller at al. 2004; USGS 2009) describe qualitatively a strong link between river flows and groundwater recharge. However, there is no quantitative data on this link hence the groundwater recharge was assumed to remain constant with varying streamflows. Respectively, it was decided to avoid expressing the variation of groundwater recharge as an arbitrary function of the variation in streamflows.
Aquifer information was obtained from the available literature (e.g. KfW / Beller at al. 2004; USGS 2009), and the groundwater resource was represented in the modelling as a bucket with a safe extraction rate, replenishment rate (groundwater recharge) and a maximum withdrawal rate (safe exploitation). The major systems were those supplying Old Kabul city with groundwater, namely the Upper Kabul / Allauddin aquifer, the Lower Logar / Bagrami aquifer and the Paghman / Afshar aquifer.
Page 35 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
3.2. DEMANDS FOR YEAR 2030
Two particular types of demands for year 2030 are considered: the water demand (domestic, irrigation and mining) and the energy demand.
3.2.1. Domestic Water Demands
The Domestic water is essentially of two categories: rural and urban. The rural demands are scattered geographically by nature but are agglomerated per sub-basin for modelling purpose. The trend for rural water requirements are taken from Toossab (2006), with a per capita requirement of 60L/day, and the total demand for year 2030 at the basin level is about 50 Mm3/year.
The urban demand in the year 2030 is principally from the Old- (existing) and New Kabul city, and to a smaller extent from other towns in the basin. The trend for smaller towns, in particular Jalalabad, is taken from Toossab (2006) with a per capita requirement of 100 L/day.
For Old Kabul city, demographic growth is based on JICA (2009) with an average annual growth of 1.3%. JICA´s projections reach the year 2025 and have been extended in this report to the year 2030 using the same growth rate (see figure below), resulting in 5.2 million inhabitants. The growth rate reduces significantly from year 2008 (3.9 million) to 2025 (5.0 million) as JICA (2009) suggests measures to control demographic growth. This could also be due to more decentralised development in provincial and other towns leading to a reduction in the pace of demographic growth in Old Kabul city. This is a critical assumption and needs to be confirmed in the coming years as the growth rate has a severe effect on the urban water demand.
Concerning New Kabul city, JICA (2012) predicts a population of 1.5 million inhabitants by year 2025 and extrapolating these values leads to a population of 1.9 million in year 2030 (see figure below). A portion of the population of Old Kabul city could be shifting to the new city, which is another possible cause for a decreasing pace of demographic growth in the old Kabul city. The total for the metropolitan area composed by Old and New Kabul city for year 2030 is 7.1 million persons. In the old city only the portion of the population connected to municipal water is considered in the modelling.
The increase in domestic water demand due to population growth and, also based on growth in per capita requirement and better pipe connections (KfW / Beller at al., 2004; JICA, 2009 and 2012), is shown in the figures below. The New Kabul city was originally planned to have been started by 2012 with the number of inhabitants to be supplied with water increasing to 350,000 by the year 2015 (JICA, 2012). It is now obvious that the actual development will fall behind the timeline shown by in JICA (2012). However in the absence of more detailed information, the JICA (2012) predictions were used in the investment plan. The model can be updated in the future when a new timeline is available.
Page 36 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 20: Projection for population in Old and New Kabul city, and the total for both cities. The data from JICA, up to year 2025, have been extended in this work up to year 2030.
Figure 21: Population connected to municipal water in Old and New Kabul city (left) and municipal connection rate (right).
Figure 22: Domestic water demand for the connected population of Old and New Kabul city. The per capita water requirement for Old Kabul city is the agglomerate of the house connections and public taps.
The table below summarises the calculation of the domestic water demands. The total urban water demand is expected to reach about 200 Mm3/year in year 2030.
Page 37 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Table 7: Parameters used to model the Domestic Water demands in Kabul River basin in year 2030 Description Connected Demand Values Water loss in Water loss References population (L/cap/day) conveyance (%) in treatment (%) OLD KABUL CITY House 75% of 120 25 5 KfW / Beller at Connection connected al. (2004) population JICA (2009) Public Taps 25% of 50 25 5 KfW / Beller at connected al. (2004) population JICA (2009) NEW KABUL CITY House 100% of 120 20 5 JICA (2012) connection connected population RURAL AREAS Rural demands 60 Toossab (2006)
JALALABAD AND OTHER SMALL TOWNS House 100 Toossab (2006) Connection
Box 1: How the domestic demand is represented in the model: • 60% of total population in Kabul being connected by municipal water (piped), the rest being supplied informally by private tankers and groundwater hand pumps is unaccounted for. • The serviced population is further sub-divided into house connections and public taps (complementary to 100%). • The source of the water is the three neighbouring groundwater aquifers: Upper Kabul (a.k.a. Allaudin), Lower Logar (a.k.a. Bagrami) and Paghman (a.k.a. Afshar) aquifers. • There are losses in the city pipe distribution system due to leakages, ageing of equipment and illegal connections. • There are also losses during the water treatment process. • Scattered rural demands agglomerated per sub-catchment.
3.2.2. Irrigation Water Demand
Irrigation is the largest water consumer in Afghanistan accounting for approximately 90% of all water use. Therefore the correct assessment of irrigation water demand is of crucial importance. The irrigation water demand was calculated using the crop water requirements of the feasibility studies verified by our own CROPWAT calculations and found generally to be well represented. However, there were a few deviations found. In case of large deviations between the feasibility study and our verifications we used the verified data. The crop water requirements are shown in the figure below.
Page 38 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 23: Crop water requirement calculated with CROPWAT (mm per month)
The final water withdrawal is dependent on the irrigation requirement and the project irrigation efficiency. Irrigation efficiency is strongly related to the irrigation technique and the infrastructure conditions. It is also related to precipitation, with lower efficiencies found in areas with higher rainfall (Wolters, 1991). Wolters shows project irrigation efficiencies between 20% and 50% under the climatic conditions prevalent in the Kabul Basin. The FAO aquastat database (http://www.fao.org/nr/water/aquastat /wateruse/index5.stm) shows country wide irrigation efficiencies between 16% and 50% worldwide for the year 2000.
For Afghanistan aquastat assumes an efficiency of 38% countrywide in 2000. In the Kabul basin it can be expected that irrigation efficiency is lower since water is available in relatively large quantities and precipitation is relatively high for Afghanistan. Moreover the condition of the infrastructure is poor and efficiency is affected by leakage from unlined canals, the deteriorated status of water control structures and the use of flood irrigation as irrigation technology, in combination with poor on-farm water management. The feasibility studies use values of 20-30% for the current project irrigation efficiency. This is in line with the above. The feasibility studies mention a post-project irrigation efficiency in newly developed areas between 35 to 40%. In this investment plan we assume a gross project irrigation efficiency of 25% for the non-developed areas and of 30- 40% in the developed areas according to the respective feasibility studies.
Using the above crop water requirements and irrigation efficiencies gross water withdrawal for the existing irrigation areas under current conditions is approximately 17,700 m3/ha for the 167,000 ha taken into consideration. This is in line with the data discussed in the GWSP Digital Water Atlas (2008). GWSP (2008) mentions a water abstraction of 15,000- 20,000 m3/ha in Egypt where infrastructure is more developed and better maintained than in Afghanistan. For the newly developed areas the water withdrawals are lower, leading to an average combined gross water withdrawal of 17,300m3/ha for 192,500 ha of command areas. Consequently a change in irrigation
Page 39 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
in the basin in year 2030 (as compared to the time of this study, year 2012) is considered to be the result of: • a change in command area due to schemes under consideration (described in Table 5); • an improvement of irrigation efficiency due to rehabilitation (Shatoot) or construction of new irrigation water distribution systems in the context of the new schemes (Gulbahar, Kama, Gambiri). The consequence would be a reduction of the withdrawals (or gross irrigation water demand) and thus better water availability and a potentially larger irrigated area in months with limited water availability
Due to the high withdrawals by irrigation the effect of different irrigation efficiencies will be assessed by a sensitivity analysis. This will give an indication of the potential economic gains that could be made by specific investment in improving irrigation efficiency.
It was assumed that the cropping patterns in the existing and new developed areas would be the same as the ones prevailing at the time of this study, in year 2012. This assumption was introduced to avoid any bias across the various projects in the cost / benefit analysis from agriculture production. It was also assumed that the present cropping pattern is in balance with a sophisticated system of social preferences, limitations of transport and market systems and other factors that are not well understood and likely to continue into the future. Therefore it was supposed that the patterns of new irrigation schemes will stay the same as in nearby existing irrigated areas; in particular the new crops proposed in the feasibility studies were not included because these vary widely across the feasibility studies and do not always seem to reflect the most appropriate choice from climatic and soil conditions.
The table below summarises the calculation of the irrigation water demands.
Table 8: Parameters used to model the irrigation water demands in the Kabul River basin in year 2030 Item How is it represented? References Total irrigation • Demand based on command area, cropping patterns, • Toossab (2006) requirement monthly crop water requirement and irrigation efficiency • Yekom (2010) • Small irrigated areas agglomerated per sub-catchments. • Pooyab (2011) • Large irrigated areas considered as punctual • Toossab (2008) Command areas The command areas of specific schemes are taken from • Mahab Godss feasibility report. (2010) MAJOR ITEM • Landsat images for area Shamoli and Irrigated areas Areas along Logar Kapisa plains downstream the river (Tangi along the Kabul basin in Wardak, Karwar, Panjsher river Nangrahar Surkab) province, along Kabul and Konar rivers
Cropping pattern • The cropping patterns are based on existing ones, taken from feasibility reports. • Each crop has a monthly irrigation requirement.
MAJOR ITEM
Page 40 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Item How is it represented? References Winter crops: Summer Crops: Perennial Crops: • Wheat • Maize • Orchard Grapes • Winter • Rice Vegetables • Summer Vegetables
Irrigation Efficiency Agglomerates Conveyance and Application efficiency. Irrigation Return • Return of irrigation water to the rivers due to losses in Flow irrigation canals (as expressed with the irrigation efficiency)
3.2.3. Mining Water Demand
The only predominant new mine scheme considered in this study is the Aynak Mine, along the Logar River. At the time of this study the only information available on this new scheme are from Toossab (2006) and Hagler Bailly (2010). The source of water supply for the mine (32 Mm3/year plus a non-described amount of secondary processing water) is not clear at this stage and may be taken from either the Logar River or from groundwater. For the purpose of this study two scenarios were uses, 1) the water was assumed to be withdrawn from the Logar River and 2) the water is withdrawn form the Lower Logar aquifer and reduces water availability for Kabul city. Details of the mine scheme are not assessed in the study due to unavailability of economic data. In addition to the water demand, discharge of polluted processing water into Logar River may be an issue, which could not be assessed due to unavailability of data.
3.2.4. Overview of the Total Water Demand
The figure below summarises all the water demands considered for year 2030, taking the irrigation corresponding to the situation in year 2012 (167,000 ha). This underestimates the irrigation demand since some of the new infrastructures examined in this work (Table 5) should augment irrigated areas. Nevertheless, irrigation demand is by far the greatest demand in the basin, even using the values of year 2012.
Figure 24: Total water demands for year 2030. The Irrigation water demand is the one for year 2012, i.e. without any new irrigated areas.
Page 41 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
3.2.5. Electricity Demand
The projection for electricity was based on the Draft Final Report for the Afghan Power Sector Master Plan (Fichtner 2012) which estimated the electricity demand for the whole of Afghanistan up to the year 2032. This report presents a net energy demand, which is the requirement by the users, and a gross energy demand, which is the amount of electricity which should be produced by the power generation plants, before distribution and losses; the gross demand was considered afterwards in the analysis. The value representative of the Kabul basin is equal to about 7,500 GWh/year and was derived by summing the gross demand for the provinces included in the basin, namely Kabul, Kapisa, Konar, Laghman, Logar, Nangarhar, Nooristan, Panjshir, Parwan and Wardak (see figure below).
For year 2030
Province GWh/yr Kabul 5,822 Kapisa 121 Konar 159 Laghman 156 Logar 138 Nangahar 465 Nooristan 41 Panjshir 42 Parwan 316 Wardak 220 Total 7,481
Figure 25: Projection of Gross Electricity demand (production from Electricity Plants) in the Kabul basin.
The former report Norconsult and Norplan (2004) estimated the electricity demand in the basin as about 3,200 GWh/year in the year 2030. This is more than two times smaller than the projection from Fichtner (2012) mentioned above. It could be possible therefore that the final draft report from Fichtner overestimates the demand or the study from Norconsult and Norplan underestimates it, or both.
The final draft calculation from Fichtner yields a total gross energy demand for Afghanistan equal to 4,017 GWh/year for the year 2012. The report Norconsult and Norplan estimates 2,424 GWh/year for the same, while the total electricity produced by hydropower, termal and importation was equal to 3,086 GWh in year 2011 (AEIC, 2012). Referring to the current electricity shortage in Afghanistan, hence the deficiency in the current electricity production, it appears that the recent final draft from Fichtner (2012), with its projection of 7,500 GWh/year for year 2030, is more accurate than the former report from Norconsult and Norplan (2004), which seems to underestimate the future energy demand.
Page 42 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
4. APPROACH AND METHODOLOGY
This section details the method of the assessment approach for the investment options that could be included in the Investment Plan for the Kabul River Basin.
The Investment Plan aims to provide insight into best combinations of the various infrastructure options described in section 2.5. The options are evaluated against four metrics, 1) net benefit as compared to a reference case (the without projects scenario in 2030), 2) against maximum hydropower production, 3) against satisfaction of domestic water supply and 4) against agricultural benefits. In order to account for the limited data availability and the questionable quality of data for some of the feasibility studies as clearly demonstrated in the portfolio review conducted under AWARD (Landell Mills, 2012), hydrological regimes, management practices and combinations of various infrastructure optiones were systematically varied. Influence of irrigation efficiency, water pricing for domestic water and extreme droughts was investigated by sensitivity analysis.
In order to evaluate the various investment options on an equal footing, the benefits are calculated for comparable conditions and in the most unbiased manner. These comparable conditions mean that all projects are assumed to be in equilibrium conditions and that we run all combinations only for one year. Therefore the Investment Plan does provide the relative benefits of the various projects, but not the exact influence of financing and sequencing of financing. It needs to be underscored here that the Investment Plan is not a Financing Plan. The Investment Plan is a source for the Government to select the best combinations possible; a Financing Plan has to be developed by the Ministry of Finance in coordination with the appropriate line ministry on the basis of this choice. A financing plan needs to further distinguish between sources of financing such as revenues for the investments, central budget and donor funding.
We have provided snap shots in time for the best combinations. These snap shots provide a slightly more detailed impression of financing consequences. The use of two financing scenarios, namely one without interest (represented as a Grant) and one with a 5% annual interest, also provides additional information on financial consequences of choices.
The various investment options were evaulauted for different hydrological scenarios and operational rules. The calculations of hydrological performance and economics were done using the water allocation modelling software WEAP and its economic application. The following sections provide details on the calculations done in support of the Investment Plan.
4.1. MODELLING FRAMEWORK
The modelling setup was based on GIS information and data pertaining to streamflows, water demands, existing and planned infrastructures in the Kabul basin. This information was extracted from the knowledge base on the Kabul basin which has been established within the Water Resources Planning Unit (WRPU) in the context of the AWARD project. The framework includes the WEAP (Water Evaluation and Planning) modelling software which was used to generate input data for the financial and technical analysis to draft the investment plan.
Page 43 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
4.1.1. GIS
For practical purposes the central part of the Kabul Basin was delineated in GIS as determined by gauging stations. This gives us the best basis for calibration of the current situation in a model that will be used to simulate the interaction between the various proposed projects and the economic benefits related to it.
4.1.2. WEAP model
The modelling software WEAP is a modelling tool which integrates: • Water resources availability, such as hydrological modelling; • Water management practices driven by water demands, environmental requirements, physical networks of infrastructure such as reservoirs, canals, and diversions; • Financial routines for water infrastructure developments.
WEAP software was chosen for the analysis because of the following reasons: • Large international user base and active user forum; • Free to users in developing countries (e.g. MEW); • Relatively easy to set up and use; • Models irrigation systems well, models conjunctive use, and if needed, can be linked to a distributed groundwater model and has rainfall-runoff routines, now including snowmelt, built in.
It is an object oriented model. Each object can be a river, a catchment (in case of hydrological modelling), a groundwater system, a water demand (e.g. domestic, irrigation, industry, hydropower), a reservoir, a canal, run of river etc. The objects are organised spatially in a chain of supplies and uses, forming a schematic of the natural system being modelled. The schematic of the Kabul basin is illustrated in Figure 16.
Each development infrastructure option is modelled in WEAP where physical and financial implications of each combination of investment options are represented by turning them on and off. In addition, a set of water management decision simulations are represented via the use of priority combinations (see box below).
Box 2: Water allocation priority in WEAP An important parameter in WEAP is the water allocation priority for each water use object. This priority characterises, for instance, how important it is to satisfy particular water demands or storage in reservoirs. WEAP uses a linear program to maximise satisfaction of requirements for water demand, minimum streamflow requirement and hydropower, subject to allocation priorities, supply preferences, mass balance and other constraints. WEAP attempts to satisfy first the water uses having the highest priorities – in case of equal priority it satisfies the demands equally. The allocation priority typically depends on the position in the basin, e.g., without any particular agreements upstream user demands may consume / divert water without consideration for downstream user demands hence in such a context upstream demands would have a higher priority in WEAP. Depending on policies or agreements between users, e.g. domestic water demands and environmental flows could have higher priorities than others.
WEAP software was used to define key assumptions for this study that feed into the different scenarios. The model contains several key assumptions described as follows: • Irrigation Efficiencies: efficiency of canal irrigation systems.
Page 44 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
• Irrigation Return Flow: part of the irrigation water which returns to the river, due to proximity to the river, irrigation in cascade sequences. • Cost and benefit information for the modelled infrastructure development as well as agricultural production input and output prices and quantities per unit of land. • Hydropower Plant Factor: percentage of each month that hydropower plant is running, as will be explained just below.
The definition of the Plant Factor used in WEAP is the percentage of each month that the hydropower plant is running. The plant factor more precisely presents: • Ageing infrastructure: the maximum operational capacity was taken smaller than the initial capacity due to ageing infrastructure as well as unexpected breakdowns. • Monthly release management for seasonal production of electricity in a reservoir. • Regular maintenance.
4.1.3. Large Ensemble Approach (LEA)
In order to analyse the various scenarios, including considering cause-consequence chains and interrelations, a Large Ensemble Approach (LEA), has been carried out that includes a large number of WEAP simulations covering a variety of potential developments, their combinations and operational rules under different hydrological scenarios.The objective of the LEA analysis was to identify the best investment options (best possible combinations of new infrastructure and operations under a set of criteria measures) and then single out each sector’s option that is robust under various conditions.
The large number of potential new options explored in the LEA is compared to a Reference Case where no new infrastructures development occurs (see section 4.3). The outputs of the LEA were analysed using Tableau software. The variables were varied within specific intervals: • New water infrastructure, as introduced in Table 5 and described in section 4.4.3, switched on or off to form potential combinations of new infrastructures. • Priority for water allocation: the priority at each demand / reservoir is a function of the location in the basin and 'competing' demands in the vicinity, hence the priority coefficient varied per spatial cluster; a particular set of water allocation rules was selected every time a new scheme was switched on, as described in Section 4.4.3. • Hydrological regimes: 3 possible values used, Median, Dry 5 and Dry 10, as described in section 3.1.1.
Changing the priority of water allocation explores the various management options of storing water in the reservoir and allocating water in priority to irrigation or hydropower. Supplying domestic water is imposed as the highest priority for each new scheme in the basin. Irrigation and hydropower are typically competing demands due to peak electricity demand in winter and peak irrigation demand in summer.
The combinations of all possible values introduced above form the entire ensemble of input possibilities for the LEA modelling approach. The LEA process is based on running WEAP for each chosen matrix of input combinations of water infrastructures as well as water allocation combinations under different climate. In total 24,576 runs were carried out in the LEA. This automatic process exports the results for each run creating a large database of about 100 monthly and annual output tables for each run. The algorithm that modifies, runs and export WEAP results
Page 45 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
also stores all the output data in a large file which is then analysed in Tableau software described in section 4.6.3.
The year 2030 is represented by developed conditions with the reservoirs partly filled; the new structures operational and generating revenues. The initial investment costs are composed of the capital costs (structures, equipments), the costs for engineering works (supervision, mobilisation and de-mobilisation), the price-quantity contingencies and the land acquisition, and resettlement costs. These, together with the incurred O&M costs, are being annualised for the cost-benefit analysis. Though the analysis is projected in the year 2030, the above rates of the year 2012 were used as the best available information.
The costs and benefits calculated in the Reference Case serve as a reference to estimate the change, or incremental economic metrics.
Water quality issues and pollution have not been included in this assessment, assuming that pollution will be successfully prevented. If water will be polluted it may not be suitable for domestic or irrigation use resulting in less water available than estimated in the study.
4.1.4. Sensitivity analysis
The net benefit of the various investment options depends strongly on assumptions that determine the total water withdrawal of the projects, as well as by the price setting of outputs. The reliability of the investment options depends on performance under extreme conditions.
Following the LEA, the following sensitivity analyses were investigated through various runs of the WEAP model: • higher tariff for domestic water (results in section 5.6.1), • higher irrigation efficiencies (results in section 5.6.2), • extended drought of 3-years, as defined in section 3.1.1 (results in sections 5.4.1 to 5.4.10).
Various scenarios for prices of outputs are worked out in a separate optimisation report. The prices for agricultural products are dependent on various factors which are difficult to predict, such as the development of transport networks and post harvest technology. Moreover, instead of producing certain crops, a country can always import various food products. The prices for electricity are largely set by the international market, especially since it is likely that Afghanistan will be connected to an international grid under the CASA 1000 project. Therefore if the local price would largely exceed the international market price, the country would opt to import electricity instead of producing it locally. However for domestic water there is no alternative and in case the water is scarce the cutomer is willing to pay a much higher price. On the basis of this analysis we also conducted a sensitivity analysis for the price of domestic water.
The change in net benefit of the Shatoot and Gulbahar projects was analysed for varying water tariffs (0.50 US$/m3, 0.75 US$/m3, 1.00 US$/m3)
Supply of domestic water is essential and the investment prioritised would largely suffice for the water supply of Kabul city under the various hydrological scenarios. Due to the modelling framework chosen, the results do not give insight in the effects of various consecutive dry years. The effect of consecutive dry years on domestic water supply and reliability of reservoirs was
Page 46 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
simulated through manual runs using observed river flows during sequences of three consecutive dry years.
4.2. HYDROLOGICAL SCENARIOS MODELLING
Two approaches were followed for modelling the hydrology: a single year in the LEA and a sequence of 3 consecutive years in sensitivity runs.
In the LEA, the range of variation in dry flow (Dry 5 and Dry 10) is not extreme since the focus of this study is the Median flow, i.e., the most likely streamflow regime in the basin based on historical data (see table below). Moreover, the Dry 5 or Dry 10 flow is assumed to succeed a sequence of normal (i.e., Median) flows, i.e., the initial storage of the reservoirs explored in this work (existing and proposed) is supposed to be in equilibrium under the Median flow. These two dry flows are used to model a drier year in a normal period and not a succession of dry years.
In the sensitivity analysis, a sequence of three dry years was identified in section 3.1.1 at three strategic locations in the basin, namely Panjshir river at Gulbahar (for Gulbahar), Maidan river at Maidan (for Shatoot) and Konar river at Asmar (for Konar A, Shal, Gambiri and Kama) (see table below).
Table 9: Values of the Median, Dry 5, Dry 10 and the sequence of 3 consecutive dry years at 3 locations in the basin used in the modelling. Median Dry 5 Dry 10 Year of the modelling dry sequence 1 2 3 Panjshir river Annual flow 1,700 1,350 1,250 1,552 1,068 1,315 @ Gulbahar (Mm3/year) Frequency of Every 2 Every 5 Every 10 Every 3 Every 22 Every 6 occurence years years years years years years Maidan river Annual flow 136 85 64 85 64 98 @ Maidan (Mm3/year) Frequency of Every 2 Every 5 Every 10 Every 5 Every 10 Every 3 occurence years years years years years years Konar river @ Annual flow 11,820 10,020 9,390 8,680 10,020 9,630 Asmar (Mm3/year) Frequency of Every 2 Every 5 Every 10 Every 16 Every 5 Every 8 occurence years years years years years years
4.3. REFERENCE CASE
The Reference Case as defined here will serve as a reference in the analysis of comparing different future scenarios. It represents the basin with the currently existing infrastructure projected to the year 2030, i.e. with the domestic growth in demands for year 2030 defined above, but without any of the potential assets development examined in this study (Table 5).
4.3.1. Modelling of exising infrastructures
The set of existing infrastructures included in the modelling is summarised in the table below. The modelling parameters of these schemes were tuned so as to reproduce the average electricity production and water storage which were measured. The measurements were obtained from the
Page 47 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Afghan Energy Information Center and are compiled in the figure below. The parameters in the model WEAP for the plant factor and the rule for filling Naghlu reservoir were tuned to approximate the average of the measurements.
Table 10: Representation of existing (in year 2012) hydropower infrastructures How it is represented Major items Through dams with a reservoir or run of river schemes. • Naghlu Dam: 100 MW operational (equal to full capacity) Plant Factor of the hydropower facilities, expressed as a • Mahipar run of river: 53 MW operational (initial percentage, represent the combination of: capacity = 66 MW) • ageing infrastructures: running capacity smaller than • Surubi I Dam: 22 MW operational (equal to full initial, capacity) • regular O & M / contingencies, • Darunta Dam: 4.5 MW operational (full • monthly releases management for seasonal production capacity = 11.5 MW) of electricity (i.e. high production during winter).
The Plant Factor of existing infrastructures is calibrated to reproduce the average measured production of electricity.
Calibrated water allocation rule for Naghlu: 1. Hydropower 2. Filling the reservoir.
Month 10 11 12 1 2 3 Month 10 11 12 1 2 3 Plant Factor 30% 35% 35% 35% 35% 40% Plant Factor 0% 9% 26% 40% 43% 43% Month 456789 Month 456789 Plant Factor 90% 90% 90% 80% 50% 30% Plant Factor 17% 10% 0% 0% 0% 0%
Page 48 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Month 10 11 12 1 2 3 Month 10 11 12 1 2 3 Plant Factor 70% 80% 80% 80% 80% 80% Plant Factor 50% 50% 50% 50% 60% 60% Month 456789 Month 456789 Plant Factor 80% 70% 70% 70% 70% 70% Plant Factor 60% 60% 60% 50% 50% 50% Figure 26: Observed versus modelled storage in Naghlu and electricity production at Naghlu, Mahipar, Surubi I and Darunta. In dotted lines the measurements obtained from the Afghan Energy Information Center, in black the average of the measurements and in red the modelled signal under the Median streamflow. The suitable operation rule for Naghlu reservoir and the tuned values for the Plant Factors are shown next to the graphs.
Regarding the operation of the Naghlu reservoir, the allocation rule giving higher priority to produce electricity than filling the reservoir reproduced better the observed water elevation. This setting was kept throught the analysis. Except for Surubi I, the value of the Plant Factor is relatively low. The values of these parameters were kept constant throughout the modelling, i.e., in the Reference Case as well as in the LEA.
4.3.2. Modelling of the Reference Case
The irrigation demand will be based on the values in the year 2012 except for the irrigated areas near Shatoot which are supposed to have reduced due to reduction in agricultural land in favour of further urbanisation of Old Kabul city; the value of this reduction in area is taken from the feasibility study of the Shatoot scheme (Pooyab, 2011).
The Reference Case will be assessed under the three single-year varying streamflows Median, Dry 5 and Dry 10. Some infrastructure developments, from year 2012, not examined in this work, are considered under the Reference Case. These are: • An augmentation of the domestic supply to the connected population of Old Kabul city from neighbouring groundwater resources, from 16.4 Mm3/year (45,000 m3/day) to 43.8 Mm3/year (120,000 m3/day) (Afghanistan Urban Water Supply and Sewerage Corporation, Personal Communication, 2011). • A reduction in leakage in the domestic water pipe system of the Old Kabul city, from 30% to 25% (Beller et al, 2004 and Afghanistan Urban Water Supply and Sewerage Corporation, Personal Communication, 2011). • An augmentation of the connected population in the Old Kabul city (i.e. the population supplied by municipal water) from 30% to 60%, as well as an increase in individual house connections from 60% to 75% (JICA 2009, 2012). • The construction and operation of the Aynak Mine.
Additionally in the Reference Case, it is assumed for the water allocation among the various demands in the basin that there is no upstream / downstream institutional coordination. It means that the respective upstream users as they are projected for year 2030 withdraw water without consideration for downstream demands.
4.4. FUTURE SCENARIOS
For the purpose of the Investment Plan, a variety of development scenarios were tested and analysed based on combinations of the different potential development schemes listed in Table 5 for which feasibility studies exist. The scenarios cover domestic water use, irrigation and hydropower while flood aspects were not considered due to insufficient data availability on discharge-flood relations as well as economic flood impacts.
Page 49 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
4.4.1. Overview
The schemes for proposed infrastructures with different sets of water allocation combination and hydrological scenarios are systematically tested by running each combination of schemes with the hydrological scenarios and water allocation rules in the large number of runs of the LEA. Additional sensitivity analyses, for which no batch processing was necessary due to the nature of the assessment, were tested individually with manual runs.
Initial conditions were used for objects having a "memory" (reservoirs and groundwater). Reservoirs were in “hot-start” conditions, i.e., partly full as expected under normal operating conditions, with an initial storage defined as being the storage in equilibrium in the long normal run (few years in the Panjsher and Konar River, 15 years in the Maidan River) in the month of October (first step of the calculation) under the Median flow regime. The withdrawal from groundwater objects is limited by an amount smaller than the groundwater recharge based on recommendations from Bellet et al. (2004). As a consequence the groundwater is managed sustainably and only the surface reservoirs may reach constraining conditions.
As a model time horizon, the scenarios were run at a monthly time step for a time period of one year with the a “hotstart” situation. All parameters were fixed during the runs and the analysis examined the results for one single year, the projection year 2030. This approach does not consider transient regimes or specific development paths (e.g., infrastructure A is built, then B etc.) to avoid externally-related biases (e.g., political and / or donors preference, security, etc.). Instead, it focuses on examining if the construction of new infrastructures in combination with other infrastructure assets, with a particular set of water management and allocation rules to domestic, irrigation and hydropower sectors, is advantageous under operational conditions or not (e.g. in term of net benefits, satisfaction of water demands, electricity production etc.). The advantage of this approach is its robustness. It does not depend on any assumption for the path / timeline of development or whether certain schemes are built in a certain order in time.
The different potential infrastructure assets were considered by turning “on” or “off” the respective demand or infrastructure. Two values are possible (“on” or “off”). Priority for domestic water allocation, irrigation water allocation, hydropower production or reservoir filling is controlled by a priority coefficient. The priority coefficient takes integer values from 1 to 99. The lower its value, the higher the priority.
An overview of the parameters used in the scenario analysis for the year 2030 and LEA run is shown in the table below. Details are provided in the following paragraph. The WEAP model is set up with some switches as described in the Table. These switches activate or deactivate the respective parameter during the LEA and lead to a total of 24,576 runs. When a particular situation or new scheme is switched on, the associated parameters become active. The domestic demand associated to New Kabul city is only considered if Gulbahar is switched on: it is proposed to supply the new city with several sources, namely the Panjsher Fan Aquifer, Salang and Gulbahar (JICA, 2012), but only Gulbahar could be included in this work as no detailed report with costs estimation was available for the options Panjsher Aquifer and Salang at the time of this work.
Page 50 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Table 11: Parameters for year 2030 used in scenario modelling Total Number of number of possible combinati Demand Switch Variable combinations ons, for each including parameter “on/off” Streamflow Streamflow Monthly streamflow 3 3 regime Rural Domestic Values for Population and per capita water 1 1 Supply year 2030 demand Urban Domestic Values for Population and per capita water 1 1 Supply year 2030 consumption Old (existing) Kabul Values for Connected population and per 1 1 Domestic Supply year 2030 capita water consumption New Kabul Domestic Included in Gulbahar scheme
Supply Aynak mine Values after Annual water withdrawal 1 1 full developmen t Gulbahar scheme Off 1 8 On Different priorities for water 7 allocation to Shamoli & Kapisa Irrigation, Hydropower and storing water in the reservoir Baghdara scheme Off 1 4 (Option A2 or option On Different priorities for water 3 D1)* allocation to Hydropower and storing water in the reservoir Shatoot scheme** On 1 1 Surubi II scheme Off 1 2 On 1 Hydropower reservoir Off Technical characteristics of the 1 4 upstream of the Konar dam, reservoir and hydropower river (Shal or Konar A) On Different priorities for water 3 allocation to Hydropower and storing water in the reservoir Gambiri scheme Off 1 8 On Different priorities for water 7 allocation to Irrigation demands, Gambiri hydropower and Diversion to Darunta Kama scheme On 1 4 Off Different priorities for water 3 allocation to Irrigation demands and Kama hydropower * There are two options for the scheme Baghdara ** As a result of the priority to meet domestic water demand Shatoot was always kept on in the LEA, other options were explored in manual runs. Further description is provided in Section 5.4.1
Page 51 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
4.4.2. Background configuration of the LEA
The specific combinations of parameters and settings are the base for the LEA simulations that form the database for investigating investment options for the investment plan. The section 4.4.3 below details the configuration for each case and shows the schematic in WEAP. Once a new scheme is switched on, different annual priority rules for water allocation are considered among the following competitive uses: • irrigation (if applicable), for which the demand is highest during summer • hydropower, for which the demand is highest during winter • storing water in the reservoir (if applicable) for later use
Supplying domestic water is always the first priority (i.e., for Shatoot and Gulbahar) and therefore is never varied. For each demand / reservoir, the priority is a function of the location in the basin and 'competing' demands in the vicinity. Hence the priority coefficient is varied per spatial cluster (e.g., Gulbahar and its attached demands, Shatoot and its attached demands, at Baghdara filling vs hydropower etc.). Having the reservoir as higher priority than irrigation or hydropower all the year, i.e., filling the reservoir is of higher priority, would mean that the reservoir would only release water when it is full which does not provide a benefit in the assessed situation. Respectively, cases where the reservoir has higher priority were not considered in the LEA analysis.
As was explained before (section 4.1.2), the plant factor for hydropower infrastructures as used in WEAP represents the combined effects of (i) ageing infrastructures, (ii) management of monthly release from reservoirs (if applicable) and (iii) regular maintenance. The values for new schemes are inspired by the values calibrated for modelling existing hydropower plants in the basin (cf. section 4.3.1) but the monthly values for reservoirs were chosen so as to produce more electricity in winter. Precisely, the plant factor is defined as follows: • Ageing infrastructure: the maximum possible value of the plant factor in any month is taken as 90%. • Monthly release management for seasonal production of electricity in a reservoir (if applicable): two patterns were accounted to define the monthly variation of the plant factor. First the outflow of reservoirs is high in the middle of the high flow season once the reservoirs are full; hence the plant factor should be maximum (90%) so as to produce electricity with this outflow. Second, the electricity demand is high during winter (December to February) hence the value of the plant factor was decreased after the high flows season, to store water, and increased again during winter, to facilitate production of electricity. • Regular maintenance: in case of a reservoir, the low value of plant factor in-between the high flow season and the winter allows for regular maintenance; based on calibrated values for existing plants (in particular Naghlu) this low value is taken equal to 30%. In case of a run-of-river, maintenance would occur during low flow seasons. • For run of rivers, the plant factor is constant throughout the year as there is no water storage to manage. Based on calibrated values for the existing plant Surubi I, it is taken equal to 80%.
A minimum flow requirement has been added downstream of each new reservoir to ensure that the natural flow is not too disturbed by the new scheme. Defining a minimum flow is a complex task which requires a holistic study for every new infrastructure. This is beyond the scope of this work therefore the simple method of Tennant (1976) based solely on the hydrological pattern is adopted here. Tennant defined several impact stages on the streamflows, from optimum to severely
Page 52 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
degraded (see table below). The category ‘Fair or degraded’ was chosen in this work referring to the high development need in the basin. A minimum flow equal to 10% during the low flow season and 30% during the high flow season was imposed downstream of every new scheme.
Table 12: Minimum streamflow based on the Tennant (1976) method, of a percentage of the mean annual flow Impact on the Recommended minimum flow streamflow Low flow season High flow season Optimum 60% to 100% Outstanding 40% 60% Excellent 30% 50% Good 20% 40% Fair or degraded 10% 30% Poor or minimum 10% Severe degradation < 10%
Costs from investment on planned infrastructure were included under the financial routines embedded in WEAP.
4.4.3. Details of options examined in the LEA
The new schemes introduced in Table 5 are examined in the LEA. The details of each scheme as modelled in WEAP are presented in the Boxes below.
Page 53 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 3: Gulbahar scheme The Gulbahar multipurpose project is proposed on the Panjsher river, upstream of the confluence with the Ghorband river and near the village Gulbahar. Its purpose is to supply domestic water principally to New Kabul City and to some northern parts of Old Kabul city, Shamoli plain and Kapisa irrigation and to produce electricity. JICA (2012) studied the supply of domestic water to New Kabul City solely and suggests conveying the water to Paymonar where the treatment plant would be built. Paymonar being close to the northern part of Old Kabul City, the supply to Old Kabul City (the connected population) was considered in this analysis as well. This water is conveyed by pipe (JICA, 2012) with an assumed total volume of 100 Mm3/year (Yekom, 2010). The existing irrigation in Shamoli plain and Kapisa would benefit from the scheme with the development of about 11,000 additional hectares with improved irrigation efficiency (40% instead of 25% in existing areas) (Yekom, 2010), leading to a total of 54,000 hectares. The third purpose of the Gulbahar scheme would be to produce electricity. Since the project will continue to use Gulbahar the existing irrigation canals located along the scheme Panjsher river downstream of the dam site, the water released for irrigation can also be used to produce electricity; hence the water is used
twice in this dual purpose.
The minimum flow requirement imposed downstream, after the dam and the irrigation diversion, is as follows:
250 Median Flow @ 200 Gulbahar Minimum Flow 150 (Tennant, 1976)
100 (m3/s) (m3/s)
50 5.4 m3/s 16.1 m3/s 0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
The annual minimum requirement is 340 Mm3/year.
Seven priority rules with different priority settings for water allocation as applied in WEAP (see Section 5) were examined for Gulbahar as follows:
Page 54 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Priority rule number 1 2 3 4 5 6 7 Priority setting for: Domestic 3 3 3 3 3 3 3 Irrigation 4 5 5 5 4 4 4 Hydropower 4 4 4 4 5 5 5 Reservoir 4 4 5 6 4 5 6 Minimum Flow 3 3 3 3 3 3 3 The priority starts at 3 to account for existing water uses (irrigation and rural domestic supply) upstream of Gulbahar which would withdraw water without accounting for Gulbahar downstream. These withdrawals are small compared to the river flow.
As the water can be used for dual purposes during its course, i.e. first being turbined and later on diverted for irrigation, the plant factor was chosen as a function of the priority setting: Month 10 11 12 1 2 3 Priority rule 30% 30% 40% 70% 90% 50% 1 Priority rule 30% 30% 40% 70% 90% 50% 2 to 4 Priority rule 90% 90% 90% 90% 90% 90% 5 to 7*
Month 4 5 6 7 8 9 Priority rule 90% 90% 90% 90% 90% 70% 1 Priority rule 90% 90% 90% 90% 30% 30% 2 to 4 Priority rule 90% 90% 90% 90% 90% 90% 5 to 7* * in this case the plant factor is constant as the release through the turbines follow the pattern for irrigation and the maintenance occurs in the months when there is little to no irrigation demand.
Page 55 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 4: Baghdara scheme
There are two options for this scheme, i.e. a small reservoir (1.9 Mm3) located some kilometres downstream of the station Sukhi which functions as a run-of-river (option A2) or a larger reservoir (400 Mm3) located further downstream (option D1). The sole purpose is hydropower.
The minimum flow requirement imposed downstream, after the dam and the irrigation diversion, is as follows:
400 350 Median Flow @ 300 Sukhi 250 Minimum Flow (Tennant, 1976) 200
(m3/s) (m3/s) 150 100 9.4 m3/s 28.3 m3/s 50 0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
The different priority settings for water allocation are:
Option A2 D1 Priority rule 1 1 2 Hydropower 9 8 8 Reservoir 8 8 9 Minimum Flow 8 8 8
In the case of option A2, there is not much room to operate the reservoir, hence the highest priority is given to fill this small reservoir, which will be filled-up almost instantaneously, to keep the high head for hydropower.
The Plant Factor was as follows:
Month 10 11 12 1 2 3 4 5 6 7 8 9 Option A2 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% D1 30% 40% 50% 70% 90% 50% 50% 90% 90% 90% 30% 30%
Page 56 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 5: Shatoot scheme
The scheme is suggested on the Maidan river, just upstream of the Old Kabul city. Its purpose is to supply Domestic Water to Old Kabul City and irrigation schemes downstream of the dam as well as to maintain a minimum streamflow after the irrigation withdrawal. The water allocated to Old Kabul City (the connected population) is the first priority and has a required volume of 97 Mm3/year (Pooyab 2011). The existing irrigation downstream is expected to reduce due to urbanisation in the vicinity of Old Kabul city (Pooyab 2011). As a third purpose, not mentioned in the feasibility study, hydropower was included as well in this study as an additional benefit.
The minimum flow water requirement imposed downstream of the dam and the irrigation diversion is based on the hypothetic natural flow of the Maidan river at the station Tangi Saidan, i.e. without the current water diversion for irrigation. The value chosen for this diversion is the estimation calculated by Pooyab (2011) and the minimum flow requirement is as follows:
20 Median Natural 15 Flow @ Tangi Saidan 10 Minimum Flow (Tennant, 1976) (m3/s)
5 0.5 m3/s 1.5 m3/s
0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
The minimum flow requirement amounts to a volume of 26 Mm3/year. It is noteworthy that imposing this minimum flow would improve the flow of the Maidan after Tangi Saidan, hence in Kabul city, since the median monthly flow at this station can currently drop below 0.3 m3/s during the low flow season.
The priority settings for water allocation are:
Priority rule Mini. Flow downstream Domestic Irrigation Hydropower Reservoir 1 3 3 4 4 4
The priority starts at 3 to account for existing water uses (irrigation and Maidan Shar urban domestic supply) upstream of Shatoot which would withdraw water without accounting for Shatoot downstream. Supplying domestic water and maintaining a minimum flow downstream of the dam and of the irrigation were given the same priority. The remaining uses, i.e. irrigation, storing water and hydropower, were given the same lower priority since the primary allocation (domestic and minimum flow) diverts almost all the water available in the reservoir.
Page 57 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
The Plant Factor was as follows:
Month 10 11 12 1 2 3 4 5 6 7 8 9 Plant 30% 30% 40% 60% 70% 90% 90% 90% 90% 30% 30% 30% Factor
Page 58 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 6: Surubi II scheme
Two staggered run-of-river schemes are suggested to be built on the Kabul river, downstream of the existing Surubi 1. The sole purpose is hydropower and consequently only one priority rule was investigated:
Priority rule number 1 Priority setting for: Hydropower 13
The Plant Factor was taken constant and equal to 80% for both stages.
Page 59 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 7: Hydropower reservoir upstream of the Konar river
There are two options for large reservoirs close to each other for hydropower production upstream of the Konar river. The sole purpose is hydropower. The first is referred to as ‘Konar A’ and the second is called Shal (Table 5). Shal has a small live storage as compared to its capacity (174 Mm3 vs. 1,874 Mm3), hence it operates almost like a run-of river scheme.
The minimum flow requirement imposed downstream of the two possible dams is as follows:
1 200 Median Flow @ 1 000 Asmar
800 Minimum Flow (Tennant, 1976) 600 (m3/s) (m3/s) 400 37.3 m3/s 200 111.8 m3/s
0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
The annual minimum requirement is 2,354 Mm3/year.
The different priority settings for water allocation are:
Option Konar A Shal Priority rule 1 2 1 Hydropower 1 1 1 Reservoir 1 2 1 Minimum Flow 1 1 1
In the case of Shal, there is little volume to operate due to the small live storage, hence only one operation rule is explored, with a same priority for filling the reservoir and producting electricity.
The Plant Factor was as follows:
Month 10 11 12 1 2 3 4 5 6 7 8 9 Option Shal 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% Konar A 30% 30% 40% 70% 90% 50% 50% 90% 90% 90% 90% 90%
Page 60 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 8: Gambiri scheme
The objective is to divert water from the Konar river through the Gambiri canal for three uses. According to discussions with different stakeholders, in particular MEW and Toossab, the proposed maximum diversion is 100 m3/s in the current design stage. However no written document was available to support this value at the time of this study. The maximum diversion amount eventually chosen in this study was the one mentioned in the feasibility study Toossab (2008), i.e. 50 m3/s. The project is designed to generate electricity with a new run of river plant (23 MW) and to convey the water from the canal back to the river. The second purpose is to irrigate existing lands in Shigi and the two new areas, Greater Gambiri and Lesser Gambiri. The third use is to divert part of the canal water into Darunta reservoir for irrigation along the Jalalabad canal and further production of electricity at Darunta.
The minimum flow requirement imposed downstream of the diversion on the Konar river is as follows:
1 200 Median Flow Konar @ Asmar 1 000 + Pech @ 800 Chaghasaray Minimum Flow 600 (Tennant, 1976) (m3/s) (m3/s) 400 129.0 m3/s 200 43.0 m3/s
0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
The annual minimum requirement is 2,715 Mm3/year.
The different priority settings for water allocation are:
Priority rule number 1 2 3 4 5 Gambiri Hydropower 4 4 4 5 5 Irrigation 4 5 5 4 4 Diversion to Darunta 4 5 6 5 6 Minimum Flow 3 3 3 3 3
Irrigation refers to the three irrigation areas Shigi, Greater Gambiri and Lesser Gambiri. The case where the Diversion to Darunta would be the highest priority is not examined since this would entail that all the canal water would be diverted to Darunta, hence with no electricity production at Gambiri hydropower and no coverage of the irrigation demands.
The Plant Factor was taken constant and equal to 80%.
Page 61 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Box 9: Kama scheme
Similar to the Gambiri scheme, this projects aims at diverting water from the Konar river. The intake is proposed to be near Pol-e-Kama, before the confluence with Kabul river. The diversion amount is 121.5 m3/s at maximum with a minimum streamflow of the Konar imposed right after the diversion. The project has two purposes. The first is to generate electricity with a new run of river plant (45 MW) built along a canal conveying the water from the Kama canal to the Kabul river. The second purpose is to irrigate existing lands near Pol-e-Kama and extended lands in Gerdab and Goshta.
The minimum flow requirement imposed downstream of the diversion on the Konar river is as follows:
1 200 Median Flow 1 000 Konar @ Pol-e- Kama 800
600 Minimum Flow
(m3/s) (m3/s) (Tennant, 1976) 400 132.6 m3/s 200 44.2 m3/s
0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
The annual minimum requirement is 2,793 Mm3/year.
The different priority settings for water allocation are:
Priority rule number 1 2 3 Priority setting for: Kama Hydropower 19 19 20 Irrigation 19 20 19 Minimum Flow 18 18 18
Irrigation refers to the three irrigation areas Pol-e-Kama, Gerdab and Goshta.
The Plant Factor was taken constant and equal to 80%.
Page 62 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
4.4.4. Stepped Development
The analysis of the LEA identifies the best combination of new infrastructures for the year 2030. The path of development to reach this target was also investigated. The path is a function of the variation of the demands in the basin, in such a way that infrastructures construction schedule will attempt to satisfy these demands increasing with time. The development was examined with four time steps for the years 2018, 2020, 2025 and 2030. The results are presented in Section 5.7.
4.5. RESULT DATABASE
The results from each of the assessments and considered scenarios are compiled in an output database. The LEA consists of external Visual Basic Scripts which operated all WEAP scenario inputs and outputs. The WEAP model contains a database of the results for each run, which were then exported in the large output database.
4.6. APPROACH AND ASSESSMENT CRITERIA FOR INVESTMENT
4.6.1. Approach
As previously highlighted, many water management challenges exist in the Kabul River Basin and management strategies seeking to respond to these challenges are being identified and developed. In this context, the ability to assess which strategies are the most likely to produce positive outcomes is critical to decision making related to future water sector investments. There are many metrics that could be used to assess the performance of a particular strategy or combination of strategies. These include standard engineering metrics such as supply reliability, environmental metrics related to water quality or ecosystem condition, and metrics related to the broad economic or social welfare gains that may accompany a water resource investment. In this analysis we have adopted a more limited cost benefit approach that focuses on the direct cost of realizing any particular investment strategy and direct benefits associated with any enhanced ability to deliver water under that strategy. While this approach, which is consistent with data and time constraints imposed on this project, will not produce any assessment of changes in the general welfare of the water users in various sectors, the analysis will shape an understanding of the long-term effects of the investments relative to the current state of affairs. The assessments of the costs and benefits from each potential investment are based on identifying the investment costs for each development and capturing their benefits in different sectors.
More specifically, the assessment criteria for modelling the different investment plans are based on the annual benefits and costs from each of the sectors: agricultural, hydropower and urban water demand in order to compare the net benefits from each scenario and their combinations. For each of the development scenarios the financial analysis was undertaken by evaluating the increase in benefits from the infrastructure development for one specific year which is defined by a particular set of assumptions about future hydrologic and water demand conditions.
In the analysis, we are assuming a fixed level of development for 2030. Here, one of the key assumptions in representing the investment plans in WEAP is that new infrastructure is considered as fully constructed and in operation. No construction period is considered and benefits are materialised during the assessed operation. The costs are uniformly annualised over the expected project lifetime (50 years)
Page 63 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Two financing options for the investment costs (civil engineer works, equipments, land acquisitions, resettlements, administrative and financial costs, contingencies) are considered: • a loan based on a 50 year term and an interest rate of 5% p.a: the annualised loan cost respectively includes the annual repayment of the loan as well as the interest; • or a grant: the annualised cost includes the investment cost divided by 50 in order to show the economic use of the funding.
These two annualisation approaches may not be the current situation of cash flows but they allow an annual comparison of the amortised costs of investments versus the benefits from the different affected sectors. In both cases, WEAP calculates annual investment costs from each one of the planned infrastructures as well as the annual O&M costs. While this approach ignores the actual temporal sequence of which individual investment strategies may be implemented, it has the advantage of relative analytical simplicity and of providing a metric that can be easily compared across strategies: namely, assuming that a given strategy has been realised, likely as the result of some capital investment annualised over some planning horizon, what will be the annual balance between the amortized cost and benefit flows. To compensate this, specific manual runs of WEAP were conducted with the identified investment option in the LEA to provide stepped development “snapshots”.
The economic assessment of development scenarios requires reliable data sets. The team economist has worked closely with stakeholders in Afghanistan in order to quantify the relevant costs and benefit data for this study. These data were one of the main sources for performing the economic assessment. In addition, data collection from previous modelling efforts, such as the construction of Kabul River Decision Support System (KDSS) (IRBD/World Bank, 2010), is used for input data collection.
The financial assessment of agricultural production was performed by calculating the production costs and benefits before and after the investment plans. Due to the lack of information regarding off-farm water delivery costs for irrigation it is assumed that these costs and benefits do not vary with water supply fluctuations. In order to better represent the estimated yield from the investment plans, it is estimated that with an adequate and timely water supply for irrigation the model increases yields by 20% (see figure below). Because of the lack of information regarding the sensitivity of the agricultural system to changes in water the loss in production from water shortages is approximated by reducing the total regional agricultural revenue by the minimum percentage amount of water demand that it is met in a critical vegetative period. This is fairly consistent with the extensive international data available regarding yield responses to water (Doorenbos et al., 1979).
Page 64 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
Figure 27: Illustrative yield response to water (Doorenbos et al., 1979)
Under this scope of work, social improvements such as changes in health, livelihoods and poverty reduction are not captured to any significant extent. The true socio-economic value of providing more and better potable water to the population also defies adequate quantification. In addition, other social aspects such as job generation or migration are not considered as a socio-economic benefit. Future model improvements can be considered in order to account for such changes as well as quantifying the economic value of such services.
4.6.2. Criteria for selection of investment options from the LEA
The approach implemented for the selection of a single optimal and robust investment option from the LEA output database is based on two steps: 1. The economic viability of a development option, i.e. the best possible combination of assets considering economically, environmentally and politically feasible aspects (Optimal Bundle Selection). 2. A sufficient robustness of the recommendation to acknowledge the uncertainties related not only to modelling aspects, but also, to exogenous factors such as climate to avoid regret-options and maintain decision-making flexibility.
The robustness of the finally recommended development options was achieved by using a structured approach that tests prioritised development options for a range of streamflow variations, and selects options where optimal results under median streamflows have little variation with respect to changes in regimes (see Section 4.2). By doing so, it was checked that the options performing the best under the most likely streamflows regime, i.e., the median, were stable under variable streamflows and “no regret” solutions were achieved.
The selection of performant options (step 1) was realised under the LEA methodology which tested the performance of options under a set of criteria. The metrics of performance were evaluated by segmenting each criterion in three discrete levels (high, medium, low). The options that are within high levels for all metrics constitute the optimum set of investment options of performance. Each one of the criteria designed for the distribution of the levels of performance measures were as follows:
Page 65 AWARD - TISC / LML / Kabul Basin Investment Plan / January 2013
1) Total Net Benefit for each Investment Combination:
(1.1) NB = ∑ + ∑ −∑ −