The World Bank Report No: ISR9019

Implementation Status & Results LIFELINE ROADS IMPROVEMENT PROJECT (P115486)

Operation Name: LIFELINE ROADS IMPROVEMENT PROJECT (P115486) Project Stage: Implementation Seq.No: 8 Status: ARCHIVED Archive Date: 25-Dec-2012 Country: Armenia Approval FY: 2009

Public Disclosure Authorized Product Line:IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): Key Dates Board Approval Date 24-Feb-2009 Original Closing Date 31-Dec-2010 Planned Mid Term Review Date Last Archived ISR Date 18-Apr-2012 Public Disclosure Copy Effectiveness Date 10-Apr-2009 Revised Closing Date 31-Dec-2013 Actual Mid Term Review Date

Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective of the Additional Financing would remain the same as in the original Project.

Has the Project Development Objective been changed since Board Approval of the Project?

● Yes No Public Disclosure Authorized Component(s)

Component Name Component Cost Component 1: Rehabilitation of the Lifeline Road Network 30.00 Component 2: Technical Assistance 0.40

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate

Public Disclosure Authorized Implementation Status Overview 1. The LRIP implementation continues to progress in a satisfactory manner. All civil works activities planned under the original and LRIP-AF1, and several planned for LRIP-AF2, are already completed. About 87% of Bank funds for the AF2 have been already disbursed and the AF1 closed in December 31, 2011. 2. The targets of the LRIP have now been met and even exceeded (incl. number of person-month of job created and number of km of roads rehabilitated). The second additional financing to the LRIP is expected to close on December 31, 2013

Public Disclosure Copy 3. The Transport PIU completed the recruiting exercise for additional staff. The capacity of the PIU to deliver on expected tasks and requests is very satisfactory. 4. The policy dialogue between the Bank and the Government on the issue of efficiency and sustainability in the road sector has been positive.

Page 1 of 9 Public Disclosure Authorized The World Bank Report No: ISR9019

Locations Country First Administrative Division Location Planned Actual Armenia Vayots' Dzori Marz Zarrit'ap'

Armenia 'i Marz

Armenia Syunik'i Marz

Armenia Syunik'i Marz

Armenia Syunik'i Marz

Armenia Syunik'i Marz Public Disclosure Copy

Armenia Vayots' Dzori Marz Sers

Armenia Syunik'i Marz

Armenia Vayots' Dzori Marz Martiros

Armenia Syunik'i Marz Maralzami

Armenia Syunik'i Marz

Armenia Syunik'i Marz Kuris

Armenia Syunik'i Marz

Armenia Syunik'i Marz Kavchut

Armenia Syunik'i Marz

Armenia Vayots' Dzori Marz Hermon

Armenia Syunik'i Marz

Armenia Syunik'i Marz

Armenia Syunik'i Marz Brrnakot'

Armenia Vayots' Dzori Marz Yeghegis

Armenia Vayots' Dzori Marz Aghavnadzor

Armenia Syunik'i Marz

Armenia Syunik'i Marz Agarak Public Disclosure Copy

Armenia Syunik'i Marz Geghavank'

Page 2 of 9 The World Bank Report No: ISR9019

Country First Administrative Division Location Planned Actual Armenia Vayots' Dzori Marz Vayots' Dzori Marz

Armenia 'i Marz

Armenia Shiraki Marz Horrom

Armenia Kotayk'i Marz Zovashen

Armenia Geghark'unik'i Marz Zovaber

Armenia Shiraki Marz Zorakert

Public Disclosure Copy Armenia Kotayk'i Marz Zarr

Armenia K'aghak' Yerevan

Armenia Shiraki Marz Voskehask

Armenia Shiraki Marz Voghji

Armenia Tavushi Marz Verin Karmiraghbyur

Armenia Geghark'unik'i Marz Verin Getashen

Armenia Aragatsotni Marz Vardenut

Armenia Geghark'unik'i Marz

Armenia Geghark'unik'i Marz Vahan

Armenia Tavushi Marz Lusahovit

Armenia Kotayk'i Marz

Armenia Shiraki Marz T'avshut

Armenia Aragatsotni Marz T'alin

Armenia Armaviri Marz Shenavan

Armenia Kotayk'i Marz Saranist

Armenia Kotayk'i Marz

Armenia Armaviri Marz Pshatavan

Public Disclosure Copy Armenia Lorru Marz Pokr

Armenia Kotayk'i Marz

Page 3 of 9 The World Bank Report No: ISR9019

Armenia Geghark'unik'i Marz Noratus

Armenia Geghark'unik'i Marz Nerk'in Getashen

Armenia Tavushi Marz Navur

Armenia Armaviri Marz Nalbandyan

Armenia Shiraki Marz Musayelyan

Armenia Tavushi Marz Mosesgegh

Armenia Lorru Marz Metsavan Public Disclosure Copy Armenia Kotayk'i Marz Mayakovski

Armenia Aragatsotni Marz Mastara

Armenia Geghark'unik'i Marz Madina

Armenia Armaviri Marz Lukashin

Armenia Shiraki Marz Lerrnakert

Armenia Geghark'unik'i Marz Lchashen

Armenia Kotayk'i Marz

Armenia Lorru Marz Kurt'an

Armenia Kotayk'i Marz Kotayk'

Armenia Tavushi Marz Khasht'arrak

Armenia Kotayk'i Marz Kat'naghbyur

Armenia Shiraki Marz Karrnut

Armenia Geghark'unik'i Marz Karmirgyugh

Armenia Geghark'unik'i Marz Karchaghbyur

Armenia Kotayk'i Marz

Armenia Geghark'unik'i Marz Gavarr

Armenia Tavushi Marz Itsakar Public Disclosure Copy Armenia Tavushi Marz

Page 4 of 9 The World Bank Report No: ISR9019

Armenia Kotayk'i Marz

Armenia Armaviri Marz Armavir

Armenia Shiraki Marz

Armenia Lorru Marz Gyulagarak

Armenia Armaviri Marz Getashen

Armenia Kotayk'i Marz Geghard

Armenia Ararati Marz Geghanist Public Disclosure Copy Armenia Geghark'unik'i Marz Geghark'unik'

Armenia Geghark'unik'i Marz Geghamavan

Armenia Aragatsotni Marz Garnovit

Armenia Kotayk'i Marz Garrni

Armenia Geghark'unik'i Marz Gagarin

Armenia Aragatsotni Marz Dzoragyukh

Armenia Armaviri Marz Janfida

Armenia Geghark'unik'i Marz Ddmashen

Armenia Lorru Marz Chochkan

Armenia Lorru Marz Ch'kalov

Armenia Tavushi Marz Ch'inari

Armenia Geghark'unik'i Marz

Armenia Aragatsotni Marz Byurakan

Armenia Tavushi Marz

Armenia Kotayk'i Marz

Armenia Armaviri Marz Aygeshat

Armenia Tavushi Marz Aygedzor Public Disclosure Copy Armenia Shiraki Marz Aygabats

Page 5 of 9 The World Bank Report No: ISR9019

Armenia Shiraki Marz Hartashen

Armenia Shiraki Marz Ardenis

Armenia Kotayk'i Marz Aramus

Armenia Aragatsotni Marz Aragats

Armenia Aragatsotni Marz Antarut

Armenia Armaviri Marz Amasiya

Armenia Kotayk'i Marz Akunk' Public Disclosure Copy Armenia Shiraki Marz Akhuryan

Armenia Shiraki Marz Aghvorik

Armenia Aragatsotni Marz Agarak

Armenia Tavushi Marz Ach'ajur

Armenia Lorru Marz Vardablur

Armenia Tavushi Marz Gandzak'ar

Armenia Tavushi Marz Artsvaberd

Armenia Aragatsotni Marz Zovasar

Armenia Kotayk'i Marz

Armenia Armaviri Marz

Armenia Armaviri Marz Gay

Armenia Aragatsotni Marz Aragatsotni Marz

Armenia Armaviri Marz Armaviri Marz

Armenia Geghark'unik'i Marz Geghark'unik'i Marz

Armenia Lorru Marz Lorru Marz

Armenia Shiraki Marz Shiraki Marz

Armenia Tavushi Marz Tavushi Marz Public Disclosure Copy Armenia Armaviri Marz Haykashen

Page 6 of 9 The World Bank Report No: ISR9019

Armenia Ararati Marz Hovtashat

Armenia Syunik'i Marz

Armenia Shiraki Marz Jararat

Armenia Aragatsotni Marz Dashtadem

Armenia Armaviri Marz Noravan

Armenia Armaviri Marz Khanjyan

Armenia Armaviri Marz Nor Kesaria Public Disclosure Copy

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Travel time improvement to drive the length of Text Value 0 36.8 percent reduction 20 percent reduction the section over current situation. Date 31-Jan-2009 30-Nov-2012 31-Dec-2011 Comments Number of persons-months of local jobs Text Value 0 39,486 36,650 created. Date 31-Jan-2009 30-Nov-2012 31-Dec-2011 Comments Target exceeded One pilot of "safe villages" program Yes/No Value No Yes Yes implemented Date 31-Dec-2009 31-Dec-2010 31-Dec-2010 Comments

Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of km upgraded Text Value 0 433 430 Date 31-Jan-2009 30-Nov-2012 31-Dec-2013 Comments Road Safety Audit Manual Developed Yes/No Value No Yes Yes Date 31-Dec-2009 31-Dec-2010 31-Dec-2010 Comments Establishment of data collection unit in ARD Yes/No Value Yes Yes Yes Public Disclosure Copy

Page 7 of 9 The World Bank Report No: ISR9019

Date 31-Dec-2009 30-Dec-2011 30-Dec-2011 Comments

Data on Financial Performance (as of 13-Dec-2012)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P115486 IBRD-77510 Closed 27-Aug-2009 04-Sep-2009 20-Nov-2009 31-Dec-2011 31-Dec-2011 P115486 IBRD-79360 Effective 15-Jul-2010 23-Jul-2010 15-Nov-2010 31-Dec-2013 31-Dec-2013 P115486 IDA-45490 Closed 24-Feb-2009 26-Feb-2009 10-Apr-2009 31-Dec-2010 31-Dec-2010

Public Disclosure Copy P115486 TF-94897 Closed 17-Nov-2009 17-Dec-2009 02-Feb-2010 30-Apr-2010 31-May-2012

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P115486 IBRD-77510 Closed USD 36.60 36.60 0.00 36.60 0.00 100.00 P115486 IBRD-79360 Effective USD 40.00 40.00 0.00 35.45 4.55 89.00 P115486 IDA-45490 Closed USD 25.00 25.00 0.00 24.99 0.00 100.00 P115486 TF-94897 Closed USD 0.05 0.07 0.03 0.07 0.00 100.00

Disbursement Graph Public Disclosure Copy

Page 8 of 9 The World Bank Report No: ISR9019

Key Decisions Regarding Implementation None

Restructuring History There has been no restructuring to date.

Related Projects P116760-Lifeline Road Improvement Project - Additional Financing, P121287-LIFELINE ROADS IMPROVEMENT PROJECT - 2ND ADDL. FIN. Public Disclosure Copy Public Disclosure Copy

Page 9 of 9