Consolidated Procurement Plan (updated 27 December , 2011) : Lifeline Roads Improvement Project (Credit 4549 AM) and Additional Financing - Lifeline Roads Improvement Project (Loan 7751-AM) and Second Additional Financing (Loan 7936-AM)

Review By Expected Bank Contract No. of Procurement Invitation Bid- Start Completion Actual Contract price in Actual Contract price in Package No. Description/ Location (PRIOR / Award Contractor Packages Method Date Opening Date Date* USD the contract currency Post) Date Date

Public Disclosure Authorized A C D E F G H I K L M 1. WORKS for rehabilitation of roads: Aghavnadzor-link to M2 Highway (section 16) lot1, CJSC RBE of 1 NCB Prior 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Contract CW-NCB-1/2009 lot 1 260,270,830 AMD 2 1.24 Aghavnadzor-link to M2 Highway (section 16) lot2, CJSC RBE of 2 NCB Prior 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Contract CW-NCB-1/2009 lot 2 Yeghegnadzor 204,875,616 AMD Chkalov-link to M6 Highway (section 7), Contract CW- 3 1 NCB Post 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Tumanyani RBE OJSC 0.41 NCB-2/2009 154,430,544 AMD Joint Venture of Motor ----link to M1 Transport Road of 4 1 NCB Post 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 0.74 Highway (section 12) Contract CW-NCB-3/2009 Ashotck CJSC and Akhuryani CHSHSH 276,830,259 AMD -link to M3 Highway (section 1), Contract CW- 5 1 NCB Post 2-Apr-09 23-Apr-09 19-May-09 26-May-09 30-Nov-10 Mostovik LLC 0.94 NCB-4/2009 354,837,553 AMD

Public Disclosure Authorized Aygeshat- (section 2), Contract CW-NCB- 6 1 NCB Post 2-Apr-09 23-Apr-09 5-May-09 19-May-09 30-Nov-10 Tshanshinvarpet CJSC 0.6 5/2009 227,332,359 AMD Geghanist-Horom (section 9) lot1, Contract CW-NCB- 7 NCB Post 2-Apr-09 23-Apr-09 29-Apr-09 5-May-09 30-Nov-10 UnderMoscow OJSC 6/2009 lot1 467,408,989 AMD Geghanist-Horom (section 9) lot2, Contract CW-NCB- 8 3 NCB Post 2-Apr-09 23-Apr-09 8-May-09 18-May-09 30-Nov-10 Blesk LLC 3.86 6/2009 lot2 610,182,373 AMD Geghanist-Horom (section 9) lot3, Contract CW-NCB- 9 NCB Post 2-Apr-09 23-Apr-09 29-Apr-09 5-May-09 30-Nov-10 UnderMoscow OJSC 6/2009 lot3 386,200,577 AMD Lernakert-link to M1 Highway (section 3), Contract 10 1 NCB Post 2-Apr-09 23-Apr-09 4-May-09 7-May-09 30-Nov-10 Khachhar LLC 1.3 CW-NCB-7/2009 493,926,092 AMD Voghji-link to M1 Highway (section 10) lot1 , Contract CHSHSH 11 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 CW-NCB-8/2009 lot1 CJSC 546,205,046 AMD Voghji-link to M1 Highway (section 10) lot2, Contract Akhuryan CHSHSH 12 3 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 4.3 CW-NCB-8/2009 lot2 CJSC 471,044,022 AMD Public Disclosure Authorized Voghji-link to M1 Highway (section 10) lot3, Contract Akhuryan CHSHSH 13 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 CW-NCB-8/2009 lot3 CJSC 599,851,530 AMD Joint Venture of -link to M7 Highway (section 4), Contract Akhuryani Koopshin Ltd 14 1 NCB Post 2-Apr-09 23-Apr-09 5-May-09 7-May-09 30-Nov-10 0.68 CW-NCB-9/2009 and Akhuryan CHSHSH CJSC 256,816,373 AMD - (section 11) lot1, Contract CW-NCB- Akhuryan CHSHSH 15 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 10/2009 lot1 CJSC 520,977,631 AMD 2 2.87 Aygabats-Gyumri (section 11) lot2, Contract CW-NCB- 16 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 UnderMoscow OJSC 10/2009 lot 2 560,020,088 AMD -link to M11 Highway (section 5), 17 1 NCB Post 7-Apr-09 28-Apr-09 5-May-09 15-May-09 30-Nov-10 Kapavor Ltd 0.57 Contract CW-NCB-11/2009 214,123,507 AMD - (section 6), Contract CW-NCB- 18 1 NCB Post 7-Apr-09 28-Apr-09 5-May-09 15-May-09 30-Nov-10 Kapavor Ltd 0.83 12/2009 315,034,280 AMD Dzoragyugh-link toM10Highway (section 8), Contract 19 1 NCB Post 7-Apr-09 28-Apr-09 5-May-09 11-May-09 30-Nov-10 OJSC RBE OF 0.92 Public Disclosure Authorized CW-NCB-13/2009 348,803,161 AMD L.Karmiraghbyur- (section 13) lot1, Contract CW- 20 NCB Post 7-Apr-09 28-Apr-09 5-May-09 15-May-09 30-Nov-10 Tavushi CJSC CHSH NCB-14/2009 lot1 317,285,121 AMD 2 1.39 L.Karmiraghbyur-Berd (section 13) lot2, Contract CW- CHSHSH 21 NCB Post 7-Apr-09 28-Apr-09 5-May-09 14-May-09 30-Nov-10 NCB-14/2009 lot2 OJSC 205,963,495 AMD -Pokr (section 14) lot 1, Contract 22 NCB Post 7-Apr-09 28-Apr-09 29-Apr-09 8-May-09 30-Nov-10 Sahakyanshin CJSC CW-NCB-15/2009 lot1 332,036,746 AMD 2 1.97 Chochkan-Pokr Ayrum (section 14) lot 2, Contract CW- 23 NCB Post 7-Apr-09 28-Apr-09 29-Apr-09 14-May-09 30-Nov-10 Levon Erkrord LLC NCB-15/2009 lot2 414,151,942 AMD Kurtan-Gyulakarak (section 15) lot1, Contract CW- 24 NCB Post 7-Apr-09 28-Apr-09 4-May-09 6-May-09 30-Nov-10 Argishti1 LLC NCB-16/2009 lot1 643,467,433 AMD 2 3.13 2 3.13 Kurtan-Gyulakarak (section 15) lot2, Contract CW- 25 NCB Post 7-Apr-09 28-Apr-09 4-May-09 20-May-09 30-Nov-10 Lorii CHSHSH CJSC NCB-16/2009 lot2 535,667,075 AMD H17-- km18+850-km22+800 lot1, 26 NCB Post 13-Jun-09 6-Jul-09 10-Jul-09 1-Aug-09 30-Nov-10 Kotayki CH SH SH LLC Contract CW-NCB-17/2009 lot1 360,480,969 AMD 2 1.78 H17-Armavir-Isahakyan km22+800-km25+956 lot 2, Motor Transport Road of 27 NCB Post 13-Jun-09 6-Jul-09 10-Jul-09 20-Jul-09 30-Nov-10 Contract CW-NCB-17/2009 lot2 Talin OJSC 313,668,905 AMD Sers-Martiros-Zaritap km0+000-km3+681 lot 1, 28 NCB Post 13-Jun-09 6-Jul-09 16-Jul-09 21-Jul-09 30-Nov-10 Vayki CHSHSH CJSC 413,807,366 AMD Contract CW-NCB-18/2009 lot1 Sers-Martiros-Zaritap km3+681-km7+788 lot 2, 29 3 NCB Post 13-Jun-09 6-Jul-09 10-Jul-09 20-Jul-09 30-Nov-10 Vayki CHSHSH CJSC 3.15 Contract CW-NCB-18/2009 lot2 331,537,983 AMD Sers-Martiros-Zaritap km7+788-km11+385 lot 3, 30 NCB Post 13-Jun-09 6-Jul-09 16-Jul-09 1-Aug-09 30-Nov-10 Kapani CHSHSH LLC Contract CW-NCB-18/2009 lot3 440,096,945 AMD Joint Venture of Sisiani - km 0+000-km2+960 lot 1, Contract 31 NCB Prior 24-Jun-09 15-Jul-09 22-Jul-09 1-Aug-09 15-Dec-10 BUAT LLC and Vahagn 347,656,092 AMD CW-NCB-AF-1/2009 lot1 ev Samvel LLC 2 1.68 Joint Venture of Megru Sisian-Brnakot km 2+960-km4+749 lot 2, Contract 32 NCB Prior 24-Jun-09 15-Jul-09 22-Jul-09 1-Aug-09 15-Dec-10 T SH SH D OJSC and 295,439,064 AMD CW-NCB-AF-1/2009 lot2 Sisiani TCHANSHIN M17- km0+000-km3+000 Contract CW-NCB- LLC 33 1 NCB Prior 25-Jun-09 14-Aug-09 3-Sept-09 10-Sept-09 15-Dec-10 Megru T SH SH D OJSC 1.04 AF-2/2009 396,165,535 AMD M2-Kavchut-Geghavanq km0+000-km2+500 lot 1, 34 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 17-Sept-09 15-Dec-10 Kapani CHSHSH LLC Contract CW-NCB-AF-7/2009 lot1 410,690,678 AMD 2 2.49 M2-Kavchut-Geghavanq km2+500-km6+000 lot 2, 35 Post 1-Aug-09 24-Aug-09 3-Sept-09 17-Sept-09 15-Dec-10 Kapani CHSHSH LLC Contract CW-NCB-AF-7/2009 lot2 542,518,327 AMD M17-Alvanq km0+000-km2+597, Contract CW-NCB- 36 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 15-Dec-10 Megru T SH SH D OJSC 0.83 AF-6/2009 317,099,018 AMD M2-Levaz---Kuris-Karjevan 37 (Vahravar- Gudemnis-Kuris section) 1 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 10-Sept-09 15-Dec-10 Megru T SH SH D OJSC 1.69 km0+000–km4+330, Contract CW-NCB-AF-3/2009 652,226,328 AMD M12-Hartashen km0+000-km5+090, Contract CW- 38 1 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 7-Sept-09 15-Dec-10 Zangezurtransshin OJSC 1.12 NCB-AF-8/2009 427,567,919 AMD M2- km0+000-km0+602 and - 39 M17 km0+000-km1+684, Contract CW-NCB-AF- 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 15-Dec-10 Megru T SH SH D OJSC 0.62 5/2009 238,667,427 AMD M2-Agarak km0+000-km2+175, Agarak bypass 40 km0+000-km0+970 and M2-Tkhkut 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 15-Dec-10 Megru T SH SH D OJSC 0.71 km0+000–km0+420, Contract CW-NCB-AF-4/2009 272,292,871 AMD H3, --Geghard (km 10+770-km 13+850), 41 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 14-Sept-09 15-Dec-10 Kotayki CH SH SH LLC 0.92 Contract CW-NCB-AF-10/2009 353,907,135 AMD Tcambarak-Vahan km0+000-km3+000 lot 1, Contract 42 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 10-Sept-09 31-May-11 “Kapavor” Ltd CW-NCB-AF-9/2009 lot1 469,318,922 AMD 2 2.15 Tcambarak-Vahan 3+000-km 5+730 lot 2, Contract “Chambarak CHSHSH” 43 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 30-Aug-11 CW-NCB-AF-9/2009 lot2 OJSC 341,685,808 AMD H62, Sisian- km 0+000-km2+180, Contract CW- 44 NCB Prior 22-May-10 22-Jun-10 11-Aug-10 11-Aug-10 30-Nov-12 Sisiani Chanshin LLC 271,322,666 AMD NCB-AF-1/2010 lot 1 2 Joint Venture of Sisiani 1.6 H62, Sisian-Aghitu km 2+180-km4+680, Contract CW- 45 NCB Prior 22-May-10 22-Jun-10 15-Jul-10 15-Jul-10 30-Nov-12 BUAT LLC and Vahagn 309,534,491 AMD NCB-AF-1/2010 lot 2 ev Samvel LLC M4- km0+000-km3+676, Contract CW-NCB- 46 1 NCB Prior 12-Jun-10 09-Jul-10 22-Jul-10 22-Jul-10 30-Nov-12 Ijevani T SH SH CJSC 1.07 AF-8/2010 388,796,440 AMD --M4 km0+000-km5+520, 47 1 NCB Prior 29-Jun-10 27-Jul-10 24-Aug-10 26-Aug-10 15-Dec-12 Ijevani T SH SH CJSC 1.8 Contract CW-NCB-AF-2/2010 652,100,713 AMD Joint Venture of Tavushi Movsesgyugh-Norashen-Verin Karmir Aghbyur 48 1 NCB Prior 29-Jun-10 27-Jul-10 25-Aug-10 31-Aug-10 15-Dec-12 Ch SH SH CJSC and 1.77 641,519,757 AMD km0+000-km8+815, Contract CW-NCB-AF-3/2010 Ararat Chanshin LLC H17-Armavir-Isahakyan-Gyumri km 9+425- 49 1 NCB Post 26-Jun-10 23-Jul-10 17-Aug-10 20-Aug-10 15-Dec-12 Kotayqi CH SH SH LLC 1.0 363,922,359 AMD km14+000, Contract CW-NCB-AF-11/2010 H17-Armavir-Isahakyan-Gyumri km 14+000-km 50 1 NCB Post 26-Jun-10 23-Jul-10 17-Aug-10 20-Aug-10 15-Dec-12 Kotayqi CH SH SH LLC 0.98 354,990,720 AMD 18+842, Contract CW-NCB-AF-12/2010 M4-Gagarin- km0+000-km6+093, 51 1 NCB Prior 05-Jul-10 02-Aug-10 09-Sep-10 09-Sep-10 15-Dec-12 Sevani TSH SH CJSC 1.51 545,979,988 AMD Contract CW-NCB-AF-10/2010 H39--Gegharquniq km9+200-km14+129, 52 1 NCB Prior 12-Jun-10 09-Jul-10 22-Jul-10 22-Jul-10 30-Nov-12 OJSC RBE OF GAVAR 1.53 553,224,188 AMD Contract CW-NCB-AF-4/2010 Joint Venture of Vayqi M2-Zaritap km0+000-km5+775, Contract CW-NCB- CH SH SH CJSC and 53 1 NCB Prior 29-Jun-10 27-Jul-10 25-Aug-10 25-Aug-10 15-Dec-12 2.2 798,512,220 AMD AF-5/2010 Meghru Ch SH SH TS OJSC Eghegis-Hermon km 0+000-km3+500, Contract CW- 54 1 NCB Prior 05-Jul-10 02-Aug-10 25-Aug-10 26-Aug-10 15-Dec-12 Khachar LLC 1.13 408,691,145 AMD NCB-AF-7/2010 Eghegis-Hermon km 3+500-km7+540, Contract CW- CJSC RBE of 55 1 NCB Prior 29-Jun-10 27-Jul-10 24-Aug-10 26-Aug-10 15-Dec-12 1.3 471,114,634 AMD NCB-AF-18/2010 Yeghegnadzor Joint Venture of M12-Khdzoresk km0+000-km1+830, Contract CW- 56 1 NCB Post 26-Jun-10 23-Jul-10 06-Aug-10 08-Aug-10 15-Dec-12 Zangezurtransshin OJSC 0.48 174,136,029 AMD NCB-AF-13/2010 and Kamurjshin OJSC Akhuryan- km4+000-km8+000, Contract CW- 57 1 NCB Prior 05-Jul-10 02-Aug-10 23-Aug-10 23-Aug-10 15-Dec-12 UnderMoscow OJSC 1.74 629,859,566 AMD NCB-AF-16/2010 Join venture of Karnut-Musaelyan km8+000-km13+000, Contract CW- Akhuryani Koopshin 58 1 NCB Prior 05-Jul-10 02-Aug-10 25-Aug-10 25-Aug-10 15-Dec-12 2.11 765,460,832 AMD NCB-AF-17/2010 LLC and Axuryani CH SH SH OJSC Musaelyan-Jrarat km13+000-km16+770, Contract CW- Axuryani CH SH SH 59 1 NCB Prior 05-Jul-10 02-Aug-10 25-Aug-10 25-Aug-10 15-Dec-12 1.68 607,331,474 AMD NCB-AF-15/2010 OJSC Joint Venture of Kuarlini -Gay-Hovtashat km4+100 km 8+926, 60 1 NCB Prior 05-Jul-10 02-Aug-10 14-Oct-10 18-Oct-10 15-Dec-12 LLC and 1.59 574,916,660 AMD Contract CW-NCB-AF-14/2010 Tshanshinvarpet CJSC Metsamor-Haikashen-Gay km 0+000-km 2+718, 61 1 NCB Post 26-Jun-10 23-Jul-10 18-Aug-10 07-Sep-10 15-Dec-12 Kuarlini LLC 0.79 285,197,220 AMD Contract CW-NCB-AF-6/2010 Vardenut-Aragatc km3+470-km6+530, Contract CW- 62 1 NCB Prior 12-Jun-10 09-Jul-10 21-Jul-10 21-Jul-10 30-Nov-12 Kapavor Ltd 0.97 352,771,580 AMD NCB-AF-9/2010 Joint venture of Hrazdani M4-Tcakhakadzor km0+000-km2+600, Contract CW- 63 1 NCB Post 10-Sep-10 08-Oct-10 20-Oct-10 22-Oct-10 15-Dec-12 CHSHSH OJSC and 0.62 223,000,001 AMD NCB-AF-19/2010 Nairi CHSHSH OJSC

Roads safety improvement M3-Gylaqaraq-Vardablur - 64 Kurtan km 0+000 and section km0+300-km0+600 1 MW Post 25-Oct-10 8-Nov-10 9-Nov-10 10-Nov-10 25-Nov-12 Argishti1 LLC 0.020 7,876,650 AMD minor works, Contract MCW-SVP-2010/1 M2- km0+000-km6+145 Joint venture of 65 (Section M2-), Contract CW-NCB-1/AF2- 1 NCB Prior 12-Jun-10 02-Jul-10 15-Jul-10 15-Jul-10 30-Sept.-12 Chanaparh LLC and 1.96 711,925,335 AMD 2010 Gorisi CHSHSH OJSC M2-Halidzor km6+146-km8+400 66 1 NCB Prior 12-Jun-10 02-Jul-10 15-Jul-10 15-Jul-10 30-Nov-12 Vosmar LLC 2.91 1,056,461,540 AMD (Shinuhayr section), Contract CW-NCB-2/AF2-2010 M2-Halidzor km8+400+000-km11+975 67 (Section M2-Shinuhayr–Halidzor section), Contract 1 NCB Prior 12-Jun-10 02-Jul-10 15-Jul-10 15-Jul-10 30-Sept.-12 Zangezurtransshin OJSC 2.04 741,084,104 AMD CW-NCB-3/AF2-2010 M3- km0+000-km8+534, Contract CW-NCB- 68 1 NCB Post 06-Aug-10 03-Sep-10 09-Sep-10 10-Sept.-10 15-Dec.-12 Lori ChShSh CJSC 1.40 508,437,559 AMD 4/AF2-2010 Gavar- km2+560-km4+700, Contract CW- 69 1 NCB Post 08-Jul-10 05-Aug-10 09-Aug-10 13-Aug-10 15-Dec.-12 OJSC RBE OF GAVAR 0.19 70,508,776 AMD NCB-5/AF2-2010 M10- km0+000-km1+700, Contract CW- 70 1 NCB Post 08-Jul-10 05-Aug-10 09-Aug-10 13-Aug-10 15-Dec.-12 Sevani CHSHSH CJSC 0.25 91,991,065 AMD NCB-6/AF2-2010 M4--Mayakovski-Aramus-Katnaghbyur- 71 Akunk-Zar- km 6+800- km 15+300, Contract 1 NCB Post 08-Jul-10 05-Aug-10 20-Aug-10 20-Aug.-10 15-Dec.-12 Shinforum LLC 0.81 294,517,572 AMD CW-NCB-7/AF2-2010 M4-Balahovit-Mayakovski-Aramus-Katnaghbyur- 72 Akunk-Zar-Sevaberd km15+300-km23+100,Contract 1 NCB Post 08-Jul-10 05-Aug-10 24-Aug-10 26-Aug.-10 15-Dec.-12 Khachar LLC 1.57 569,830,800 AMD CW-NCB-8/AF2-2010 Joint venture of Motor M9-Talin km0+000-km4+500, Contract CW-NCB- 73 1 NCB Post 08-Jul-10 05-Aug-10 20-Aug-10 20-Aug.-10 15-Dec.-12 Transport Road of Talin 1.76 637,700,342 AMD 9/AF2-2010 CJSC and Berma CJSC Talin-Dashtadem km4+500-km7+706, Contract CW- Motor Transport Road of 74 1 NCB Post 08-Jul-10 05-Aug-10 20-Aug-10 20-Aug.-10 15-Dec.-12 1.16 422,309,559 AMD NCB-10/AF2-2010 Talin CJSC Agarak- km0+000-km4+035, Contract CW- 75 1 NCB Post 09-Jul-10 05-Aug-10 26-Aug-10 26-Aug.-10 30-Nov-12 Meghru CHSHSH OJSC 1.60 581,404,693 AMD NCB-11/AF2-2010 for 2011 year “Axuryani CHSHSH” 76 Gyumri -Akhuryan and Basen- 740,300,009 AMD CJSC 2 ICB Prior 06-May-11 17-Jun-11 14-Jul-11 19-Jul-11 30-Nov-12 Joint venture OJSC 3.66 77 Gavar-Tsaghkashen RB&E OF GAVAR 640,024,148 AMD and Chanaparh LLC “Ijevani CHSHSH” 78 Contract CW-ICB-AF2-2011/2 lot 1, - 440,827,320 AMD CJSC Joint venture of “Sisian 2 ICB Prior 17-May-11 28-Jun-11 21-Jul-11 27-Jul-11 30-Nov-12 3.89 Contract CW-ICB-AF2-2011/2 lot 2, Araks - Freight & Passenger 79 1,020,830,407 AMD Metsamor and Araks-Metsamor-Gay-Hovtashat Autitransport” LLC and “Kuarlini” LLC 80 - CW-ICB-AF2-2011/5 1 ICB Prior 08-Jul-11 24-Aug-11 31-Aug-11 05-Sep-11 31-Jul-13 UnderMoscow OJSC 0.92 349,309,218 AMD Joint venture of CW-ICB-AF2-2011/13 lot 1Chinari-- Mostovik LLC, A.A.B 81 -Verin Karmir Aghbyur-Berd km 0+000- 1,606,974,000 AMD Project LLC, and Sisian km22+900 2 ICB Prior 05-Oct-11 17-Nov-11 22-Dec-11 01-Apr-12 30-Nov-13 FPAT LLC 6.40 CW-ICB-AF2-2011/13 lot 2 Chinari-Aygedzor- Argishti-1 LLC and 82 Artsvaberd-Verin Karmir Aghbyur-Berd km 22+900- Axuryani CHSHSH 856,999,999 AMD km32+520. CJSC Joint venture of Zangezurtransbuld OJSC CW-ICB-AF2-2011/6 lot 1 Artsvakar district-Gavar- and 83 844,379,436 AMD Karmirgyugh OJSC RB&E OF 2 ICB Prior 20-Sep-11 02-Nov-11 08-Dec-11 01-Apr-12 31-Aug-13 GAVAR 4.76

Joint venture of A.A.B 84 CW-ICB-AF2-2011/6 lot 2 Berd--Itsakar Project LLC and 988,800,000 AMD UnderMoskow OJSC Blesk LLC Armenian 85 CW-ICB-AF2-2011/7 -Zovaber- 1 ICB Prior 24-Aug-11 06-Oct-11 24-Oct-11 01-Apr-12 31-Aug-13 1.51 Branch 581,519,004 AMD CW-ICB-AF2-2011/10 lot 1 Aramus-- 86 -Saranist and M4-Balahovit-Mayakovski- Kapavor LLC Aramus 2 ICB Prior 05-Oct-11 16-Nov-11 22-Dec-11 01-Apr-12 30-Sep-13 3.79 896,428,115 AMD CW-ICB-AF2-2011/10 lot 2 -Dzoragyugh- Motor Transport and 87 -, Road of Talin CJSC 562,649,891 AMD M5-Amasia-Nalbandyan-Janfida- and 88 Armavir-Noravan--Khanjan CW-ICB-AF2- 1 ICB Prior 01-Feb-12 15-Mar-12 01-Apr-12 15-Apr-12 30-Sep-15 3.33 2011/11 89 M-4 CW-ICB-AF2-2011/12 1 ICB Prior 01-Feb-12 15-Mar-12 01-Apr-12 15-Apr-12 30-Sep-14 3.20 2. GOODS 4WD Vehicle for Supervision (PIU), Contract SH/VH 1 1 SH Post 15-May-09 20-May-09 20-May-09 20-May-09 21-May-09 Muran Ltd 0.032 2009/1 11,711,000.00 AMD 4WD Vehicle for Supervision (ARD) Contract SH/VH 2 1 SH Post 16-Oct-09 30-Oct-09 13-Nov-09 17-Nov-09 29-Dec-09 Muran Ltd 0.05 2009/2 19,225,000.00 AMD

3 Vehicle for Supervision (PIU), Contract SH/VH 2009/3 1 SH Post 2-Nov-09 17-Nov-09 13-Nov-09 17-Nov-09 18-Nov-09 Muran Ltd 0.018 5,990,000.00 AMD 202253 Euro plus taxes Fallind Weight Deflectometer (ARD), Contract ICB- KUAB Konsult & 4 1 ICB Prior 21-Aug-11 05-Oct-10 03-Dec-10 17-Dec-10 17-Mar-11 0.277 in amount of 16635099 FWD-1/2010 Utveckling AB AMD Two 4WD Vehicles for Supervision (PIU), Contract 5 1 SH Post 11-Nov-10 29-Nov-10 29-Nov-10 30-Nov-10 30-Dec-10 Vekar LLC 0.037 SH/AF 2010/V 13,500,000.00 AMD 6 IT equipment for PIU, Contract OE 2010-1 1 SH Post 16-Nov-10 30-Nov-10 13-Dec-10 17-Dec-10 29-Jan-11 Compass LLC 0.007 2,652,000.00 AMD

7 Roads and Pavement Condition Data Collection System 1 ICB Prior 02-Jul-12 16-Aug-12 14-Sep-12 30-Sep-12 30-Nov-12 0.15 Actual Contract price Review Adverti- Expected Actual Contract price Selection Contract Comple- in the contract Package by Bank sement Proposal Start in USD Description of Assignment/ Location Method Award tion Consultant currency No. Prior / for EOI Submission Date Date Date Post Date Date

3. CONSULTANTS' SERVICES

Update of existing design and development of EF and SSS Prior N/A 9-Jan-09 27-Jan-09 28-Jan-09 20-May-09 Dorproject Institute Ltd 0.196 73,059,948.00 AMD EMP for LRIP(2009), Contract RDU-1/09 1

Technical Supervision of Civil Works for roads Joint Venture of SAFEGE QCBS Prior 29-Dec-09 10-Apr-09 11-May-09 18-May-09 31-Dec-10 1.56 1,550,926.83 USD 2 Rehabilitation , Contract RRS-09 and IRD

Design Author Supervision LRIP, Contract DAS-09 SSS Prior N/A 27- Apr-09 26-May-09 26-May-09 30-Nov-09 Dorproject Institute Ltd 0.125 48,024,732.00 AMD 3 Independent Technical Audit for 2009, Contract TARR- IC Prior 15-Apr-09 5-May-09 22-May-09 25-May-09 31-Dec-09 Mr. Janusz Sobieniak 0.083 83,253.40 USD 4 09 Joint Venture of Dorproject Design and EMP for LRIP Additional Financing 2009 CQS Prior 21-Apr-09 3-June-09 10-June-09 11-June-09 1-Sep-09 Institute Ltd and Transproject 0.29 107,159,724 AMD roads, Contract DEFDU-09 5 Institute CJSC Joint Venture of Dorproject Design Author Supervision LRIP Additional Financing SSS Prior N/A 20-July-09 27-July-09 3-Aug-09 30-Sep-10 Institute Ltd and Transproject 0.105 39,982,584 AMD for 2009 roads*, Contract DAS-AF-09 6 Institute CJSC Joint Venture of Dorproject Design of LRIP Additional Financing 2010 roads, QCBS Prior 12-Jun-09 26-Oct-09 8-Feb-10 9-Feb-10 30-Dec-11 Institute Ltd and Transproject 0.64 635,040 USD Contract DTS-AF-LRIP 7 Institute CJSC Joint Venture of Dorproject Supervision of LRIP Additional Financing 2010 roads, QCBS Prior 12-Jun-09 26-Oct-09 8-Feb-10 9-Feb-10 30-Dec-11 Institute Ltd and Transproject 1.508 1,508,036 USD Contract DTS-AF-LRIP 8 Institute CJSC Review of Pavement Design and Construction, Contract IC Prior 15-Oct-09 3-Feb-10 17-Feb-10 1-Mar-10 31-Aug-10 Serji Amirkhanian 0.1 100,000 USD RPDCA-1 9 Road Safety Audit Manual & Road Safety Audit, IC Prior 15-Aug-09 22-Feb-10 26-Mar-10 1-Apr-10 30-Oct-10 Phil Jordan 0.157 156,726.7 USD 10 Contract RSAM-2010

Audit of Project accounts (2009-2011), Contract LRIP- QCBS Prior 27-Jan-10 23-Apr-10 11-June-10 11-June-11 30-June-12 Global Audit Services ltd 0.085 85,333.33 USD 11 A-1 Independent Technical Audit for 2010, Contract TARR- IC Prior 10-April-10 24-May-10 25-Jul-10 26-Jul-10 25-Dec-10 Walter Frankenberger 0.064 67,520 Euro 12 10 Design and EMP for H-46 road section, Contract PDH- JV of Dorproject Institute ltd CQ Prior 26-Feb-10 12-Mar-10 7-Apr-10 7-Apr-10 17-May-10 0.04 15,929,004 AMD 13 46 and Artsakhtshan CJCS

Design of AF2 LRIP 2011 roads QCBS Prior 9-Apr-10 15-Dec-11 28-Apr-11 30-Apr-11 08-Jun-11 Roughton International 0.79 786,385.33 USD 14 15 Supervision of AF2 LRIP 2012 roads QCBS Prior 16-Apr-11 01-Mar-12 20-Mar-12 01-Apr-12 30-Dec-13 1 16 Independent Technical Audit for 2011 CQ Prior 15-Feb-12 01-Mar-12 01-Apr-12 15-Apr-12 30-Dec-12 0.15

Audit of Project accounts (2011-2013) LCS Prior 28-Dec-11 01-Apr-12 15-Apr-12 01-May-12 14-May-14 0.1 17

Design of LNIP Roads QCBS Prior 01-Jan-12 01-May-12 01-Jun-12 15-Jun-12 30-Oct-12 0.75 18

19 Training SOE Prior N/A N/A N/A 15-Aug-12 15-Nov-12 0.01