Independent Quality Assurance for USAID’S Stabilization Program Activities in FATA and KP

Annual Implementation Report No. 02

IQC Contract No. AID-391-I-11-00002 Task Order No. AID-391-TO-15-00005 Halcrow (Pvt) Limited 3rd Floor, Nawa-e-Waqt House, Mauve Area Sector G-7/1, Zero Point, Islamabad, Pakistan Tel + 92 51 220 3451 Fax + 92 51 220 3462 www.halcrowpk.com

This report is made possible by the support of the American People though the United States April 2016 to March 2017 Agency for International Development. The contents are the sole responsibility of Halcrow Pakistan (Pvt) Ltd and do not necessarily reflect the views of USAID or the United States Government.

Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Document history

Independent Quality Assurance for USAID’s Stabilization Program Activities in FATA and KP

Annual Implementation Report No. 02 (April 2016 to March 2017):

This document has been issued and amended as follows:

Version Date Description Created by Verified by Approved by

MSZ+FMK+ 01 31/05/2017 Final AM MSZ SAK+RZG+FUR

MSZ – Muhammad Saeed Zia: Acting CoP / Quality Assurance Manager (Buildings)

SAK – Said Afsar Khan: Quality Assurance Manager (Roads)

RZG – Rustam Zad Gul: Quality Assurance Manager (Power)

FMK – Fazal Mahmood Khan: Quality Assurance Manager (Water)

FUR – Fasih ur Rahman: Environmental Compliance Specialist

AM – Asim Masud: Office Engineer

April 2016 to March 2017 (i) HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report Acronyms

AIR Annual Implementation Report BMG – Miran Shah – Ghulam Khan BOQ Bill of Quantities COR Contracting Officer Representative CoP Chief of Party DWSS Drinking water supply schemes EDF Environmental Documentation Form EMMP Environmental Monitoring & Mitigation Plan FATA Federally Administrated Tribal Areas FARA Fixed Amount Reimbursement Agreement FIP FATA Infrastructure Program FWO Frontier Works Organization HSSE Health, Safety, Security and Environment HPK Halcrow Pakistan (Pvt) Ltd IPC Interim Payment Certificate IQA Independent Quality Assurance NWA North Waziristan Agency PaRRSA Provincial Reconstruction Rehabilitation and Settlement Authority PIL Project Implementation Letter QA Quality Assurance QAE Quality Assurance Engineer QAM Quality Assurance Manager QAS Quality Assurance Supervisor QC Quality Control SWA South Waziristan Agency SOP Standard Operating Procedure TO Task Order USAID United States Agency for International Development VO Variation Order WSM Wana-Shakai-Makeen Road

April 2016 to March 2017 (ii) HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Contents

1 Executive Summary 1

2 Project Introduction 3 2.1 FATA Infrastructure Program 3 2.2 KP Reconstruction Program 3 2.3 Types of Projects 4 2.4 Geography 5 2.5 Scope of HPK Services 6

3 Results Achieved 7 3.1 Element 1: General Management and Administrative Support 7 3.1.1 General Advice 7 3.1.2 Overall Management & Administrative Support 7 3.1.3 Security 7 3.1.4 Reporting System 8 3.1.5 Project Communications 8 3.2 Element 2: Design Quality Assurance and Cost Review 8 3.2.1 QA for Design Review Services 9 3.2.2 Third Party Inspection 9 3.2.3 Design Codes & Technical Specifications 9 3.2.4 Review of Bill of Quantities (BOQs) and Engineer’s Cost Estimates 10 3.2.5 Element 3: Construction Quality Assurance 11 3.2.6 Establishment of Field Offices 11 3.2.7 Construction Quality Assurance, Inspections & Testing 11 3.2.8 Environmental Compliance 12 3.3 Milestone Certification for Construction Projects 13

4 Significant Implementation Problems 14 4.1 Building Sector 14 4.2 Road Sector 14 4.2.1 BMG Road 14 4.3 Power Sector 15 4.3.1 132kV Grid Station Khar, Bajaur Agency: 15 4.4 Water Sector 15 4.4.1 Munda Head-works: 15 4.4.2 Amandara Headworks: 15 4.4.3 Dhana Weir: 15

5 Actions taken by HPK 16

6 Observations/Recommendations 17

Annexure A – Task Order Deliverables

Annexure B – Project Organization Chart

Annexure C – HPK Deployed Staff List

Annexure D – Progress Review of Sub projects

Annexure E – Success Stories

Annexure F – Pictorial Progress

April 2016 to March 2017 (iii) HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

April 2016 to March 2017 (iv) HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

1 Executive Summary

Annual Implementation Report No. 2, covers the performance period for year 2 of the IQA program starting from April 01, 2016 to March 31, 2017. This report is submitted pursuant to Task Order Deliverables under Clause F.5.1.3, at the end of the second performance year. This AIR comprises an introduction to the project, results achieved during the second year of the project implementation, problems encountered and actions suggested to enhance qualitative and quantitative values of the works. The report also shows a preview of public events like collecting feedbacks of local community directly benefiting from the USAID stabilization program.

The main objective of the annual report is to give a preview of overall status of different ongoing and upcoming sub-projects in buildings, roads, power and water sectors during this period. USAID enhanced the projects list by adding new projects under FIP & KPRP. These sub-projects include rehabilitation and reconstruction of roads, grid stations, education buildings, rehabilitation of damaged electrical infrastructure and construction of solar based tube wells for irrigation and water supply.

The report also indicates issues arising throughout the year in each sector and suggestions by HPK to tackle these issues. Later in the report, recommendations from HPK to crop better results in the upcoming years are suggested.

HPK categorized all the subprojects assigned to it in three zones i.e. North, South and Centre. The North Zone comprises districts in Malakand Division and Bajaur Agency, while the South Zone comprises North/South Waziristan Agencies, and Bannu, Tank & DI Khan districts. Central zone comprises districts of Nowshera and Charsadda.

One of the core components of the annual report is to demonstrate the accomplishments made within the year. Focusing on key deliverables during second year of the project, HPK successfully;

 Reviewed and verified the structural, architectural, electrical and WATSAN designs for signature projects like Tehsil Level-Government Complex, Kabal and GHSS Akbar Pura, Nowshera.  Checked and verified detailed Engineer’s cost estimates for construction projects including schools, governmental buildings, basic health units, transmission lines, grid stations, roads, and bridges.  Provided construction quality assurance for all the ongoing construction projects. During this tenure 12 militancy damaged schools, 07 BHUs, 04 water supply schemes and 02 headworks in the North Zone attained final completion. In South Zone allied works on DI Khan-Tank Road and BMG Road, 01 bridge on WSM Road and 05 bridges on BMG Road attained final completion. In addition, numerous subprojects are near completion.

April 2016 to March 2017 Page 1 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

 Certified US$ 32.026 Million worth of payment milestones in accordance with the relevant Project Implementation Letters (PILs) in all four sectors of the project.

USAID added reconstruction of 57 flood damaged schools to HPK’s scope in November 2015 and physical construction on all the schools is underway and assessment surveys for further schools were conducted with PaRRSA. Work on 23 new schools is about to commence soon.

In January 2017 through a modification no. 04 in the Task Order, USAID assigned the task to HPK to inspect the ongoing building works funded by USAID on their behalf. Under this amendment, HPK visited various buildings in KP and Gilgit Baltistan.

During the course of construction numerous types of issues are generally encountered which are regularly communicated to USAID on weekly / monthly basis. A preview of some of the encountered issues is described in the relevant section.

This report likewise covers the prompt actions taken by HPK to address the issues. HPK suggested corrective measures to USAID and other stakeholders throughout the year and communicated the status of all the subprojects through its reporting system which, as per provisions of the TO contains field visit reports, weekly email updates, monthly progress reports etc.

The security situation in the North, South & Central Zones remained peaceful due to effective involvement of LEAs. During this tenure site visits by HPK staff were regularly conducted adhering to the security protocols set forth in the security assessment plan.

Task Order deliverables which serve as means of communication with USAID are also discussed in detail in this report. TO deliverables include but are not limited to QA Plan, Pre-Construction Visit Reports, Security Plan, Monthly Progress Reports, Weekly Email Updates, Minutes of Coordination Meetings and Success Stories etc. During the second year HPK successfully submitted all deliverables within the stipulated time frame.

The potential adverse environmental impacts of the construction activities on local environment, were monitored by HPK throughout the year as per guidelines and recommendations of the Environmental Documentation Form (EDF) and Environmental Management and Monitoring Plan (EMMP).

April 2016 to March 2017 Page 2 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

2 Project Introduction

The United States Agency for International Development (USAID) has appointed Halcrow Pakistan (Pvt.) Ltd. (HPK) in March 2015 to provide Architect-Engineer services for Independent Quality Assurance (IQA) of USAID’s Stabilization Program Activities in the Federally Administered Tribal Areas (FATA) and (KP) province.

Further, in January 2017 via Modification 4 to the Task Order, the USAID expanded the geographical and programmatic scope of HPK. The objective was to conduct third party visits to various projects funded by the USAID across Pakistan on their behalf.

HPK is required to provide services on activities being undertaken in the following two USAID stabilization programs: 2.1 FATA Infrastructure Program

In FATA Infrastructure Program, USAID is in partnership with FATA Secretariat. The main objective of the FATA Infrastructure Project is to improve conditions for the long-term development of the Federally Administered Tribal Areas by constructing or rehabilitating public service infrastructure in Buildings, water, energy, irrigation systems and roads.

FATA Infrastructure Program is being implemented in FATA as well as in KP Province. The project, financed by USAID under Fixed Amount Reimbursement (FAR) procedure, was started in 2010. The project aimed to restore and rehabilitate the infrastructure in the four major sectors including Buildings, roads, power and water. Halcrow Pakistan (HPK) had been entrusted by USAID to provide Architect- Engineer services for Independent Quality Assurance on this project in FATA & KP.

In March 2017 USAID enhanced the projects list by adding new projects under FIP. These sub-projects include rehabilitation and reconstruction of roads, grid stations, education buildings, rehabilitation of damaged electrical infrastructure and construction of solar based tube wells for irrigation and water supply. FATA Secretariat has hired the services of M/s Cameos Architects & Consultants to provide the engineering services such as identification, site assessment and detailed engineering designs for the upcoming “Rehabilitation and Reconstruction of Damaged Infrastructure in the Conflict Affected Areas of FATA”. 2.2 KP Reconstruction Program

In KP Reconstruction Program, USAID is in partnership with Provincial Reconstruction Rehabilitation and Settlement Authority (PaRRSA). The main objective of the KP Reconstruction Program is to enhance the stabilization and development of Khyber

April 2016 to March 2017 Page 3 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Pakhtunkhwa by rebuilding public infrastructure for education, health, water, roads, sanitation and increasing the capacity of the provincial government.

The people of KP, especially of Swat, Dir (L), Dir (U) and Buner districts of Malakand Division, suffered heavy losses in the war against terrorism and militancy. During more than one year of violence in the valley of Swat, Dir (L), Dir (U) and Buner districts, the suspected militants mainly used the destruction of schools as an effective tool to bring the government to its knees, while reversing the process of education in the restive mountainous districts. According to an official data, the insurgents destroyed 177 (primary, middle and high) schools, when the tension gripped the districts. The violence came to a halt following the Pakistan Army offensive against the in 2009.

For post conflict, Malakand Reconstruction and Recovery Program (MRRP) (Now KP-Reconstruction Program), an Assistance Agreement (No 391-011) was signed in September 2009 between the GoP and the USG. This was followed by an Implementation Letter (IL) No. MLK-01, signed in December 2009 for initial obligation of funds of US$ 36M for the rehabilitation and/or reconstruction of damaged facilities of Education, Health, Watsan and enhancing government capacity in the four districts of the Malakand Division: Dir. (L), Dir. (U), Swat and Buner. The project started in June 2010. Later, an additional sum of about US$ 16 M was sub-obligated for flood affected infrastructures in KP/ FATA and for capacity building of government in KP. The Independent Quality Assurance for this Project was awarded to HPK in April 2015; the IQA services are expected to continue for Four (4) years.

After addition of 57 flood damaged schools to the scope in August 2016, joint identification of new schools is also underway and approximately 50 more schools are likely to be added to the scope. Thus the expected figure will be 100 plus.

Construction activities on the signature projects like GGHS Akbar Pura located in District Nowshera and Tehsil Level Judicial Complex, Kabal, District Swat are likely to commence as the design review task is completed by HPK. 2.3 Types of Projects

The sectors and the types of engineering projects in this Task Order (TO) include:

 Roads  Bridges  Schools (Including Flood & Militancy Damaged)  Government Buildings & Hospitals

April 2016 to March 2017 Page 4 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

 Basic Health Units (BHUs)  Weirs  Irrigation Headworks  Grid Stations  Transmission Lines  Rehabilitation of Damaged Distribution System  Drinking Water Supply Schemes & Solarized Tube Wells 2.4 Geography

Geographically planned / upcoming projects under FATA Infrastructure Program are located in South Waziristan, Bajaur, Orakzai, Kurram, Mohmand and Khyber agencies and Frontier Regions of Peshawar, Kohat and Tank.

The Projects in KP are primarily in areas that are part of the Malakand Division and other districts of KP like Charsadda, Nowshera and DI Khan.

Map Source: https://en.wikipedia.org/wiki/Federally_Administered_Tribal_Areas

April 2016 to March 2017 Page 5 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

2.5 Scope of HPK Services

HPK is required to provide the following services under this task order:

 Review of designs, drawings, technical specifications, Bills of Quantities (BOQ), engineer’s estimates prepared by the Government of Pakistan (GoP) agencies/departments; and  Independent Quality Assurance (IQA) for construction activities in accordance with the technical specifications, construction drawings and EDF/EMMP.  Verifying the payment milestones as identified in Project Implementation Letters (PILs).

Under amendment 04 to the Task Order of HPK is expanded the geographical and programmatic scope for providing Architect- Engineer services. Modification is made to replace services provided in "KP and FATA" with "throughout Pakistan". HPK would now be providing the same services outlined in this award throughout Pakistan and not only in Khyber Pakhtunkhwa and Federally Administered Tribal Area.

This document aims to provide a plan for undertaking quality assurance of construction activities and milestone certification.

Although QA roles may be over-lapping between the supervision consultants and the IQA contractor i.e. HPK, this document has been prepared with the objective to elaborate how HPK undertakes its role as independent quality assurance contractor.

April 2016 to March 2017 Page 6 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

3 Results Achieved

During the second year of the project, following targets were set and successfully achieved by HPK as per TO requirements;

 Element-1: Provided general management and administrative support to USAID, including reports & deliverables;  Element-2: Provided design quality assurance and reviewed bill of quantities (BOQs) and cost estimates;  Element-3: Provided construction quality assurance support to USAID, including reports & deliverables.

Accomplishments against TO deliverables are described in detail in the following sections and summarized in Annexure-A. 3.1 Element 1: General Management and Administrative Support

Under this element the activities executed for the second year are covered but not limited to general advice and support, overall management and administrative support, security, performance monitoring, branding and marking and communications with USAID through reports as per TO by deploying the proposed staff in the project / design offices

Annexure-B presents an organization chart of all HPK personnel who rendered services during the second year of the project.

3.1.1 General Advice

HPK provided general advice to USAID FATA/KP office and its G2G partners that related mostly to engineer’s estimates, preparation of milestones, revision of PILs and other issues relating to power, building and road sector projects.

3.1.2 Overall Management & Administrative Support

HPK provided management and administrative services by using proper and efficient management and administration practices, information technology, reporting system, human resource management, asset control, security and cost control systems.

HPK further ensured an effective and optimized use of staff, office space and other facilities.

The deployed human resources and their utilization in the first year have been outlined in Annexure-C.

3.1.3 Security

A Security Assessment Plan has been prepared and duly approved by USAID was framed to mitigate prevailing threats and risks to enable the staff to discharge their duties in a safe and secured

April 2016 to March 2017 Page 7 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

environment. Standard Operating Procedures (SOPs) for each activity have been formulated to be followed in different eventualities during all project related activities by the project staff.

The security situation in KP is calm however, incidents of target killing and bomb blasts occur occasionally. But the security situation in FATA areas has been volatile despite military operation “Zarb-e- Azb”.

While planning field visits of any HPK IQA staff member a Journey Management Plan (JMP) is prepared by the project security manager with the approval of Chief of Party. The Visiting team follows the travel protocols as per duly approved Security Assessment Plan.

While planning field visits in FATA areas permission for entering is sought through FATA Secretariat and concerned political agents. After the consent from the political agent is received the HPK IQA staff will visit the construction sites with the security cover managed by the security department of HPK.

Considering the upcoming projects in Orakzai, Kurram, Mohmand, Bajaur, Khyber and South Waziristan Agencies, HPK security team is planning to carry out threat and risk assessment of all the project areas as per HPK’s Security Assessment Plan and the dynamics of the FATA regions, the security measures will be taken accordingly.

In perspective of overall security situation in the country the staff is warned time and again about the various risks and threats through training sessions and security drills etc.

3.1.4 Reporting System

HPK timely submitted all reports, deliverables or outputs required under the Task Order i.e. Quality Assurance Plan, Pre-Construction & Field Visit Reports, Security Plan, Cost Control Report, Branding and Marking Plan, Monthly Progress Reports, Weekly Email Updates, Minutes of Coordination Meetings, Success Stories, Annual Implementation Report and PAKINFO Reporting.

3.1.5 Project Communications

Chief of Party (CoP) as well as HPK’s key staff coordinated with USAID TOCOR for all the communications set forth in the TO. The CoP frequently provided weekly email updates and held numerous coordination meetings with USAID and other stakeholders. 3.2 Element 2: Design Quality Assurance and Cost Review

HPK provided design quality assurance under the task order from time to time. The activities executed during the second year of the project under this element also covered review of bill of quantities

April 2016 to March 2017 Page 8 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

(BOQs) and engineer’s cost estimates. The activities executed for the second year under this element are detailed in this section.

3.2.1 QA for Design Review Services

HPK reviewed structural designs and drawings to ensure its conformity to the desired codes and standards. HPK reviewed the structural, architectural, electrical and WATSAN designs and drawings of the following sub-projects during the reporting year;

 Tehsil Level-Government Complex in Kabal, District Swat.  Government Higher Secondary School Akbar Pura, District Nowshera.

After conducting the pre-construction visit to Jamrud Bypass located in Khyber Agency during the reporting year, design review was started on directions of USAID.

3.2.2 Third Party Inspection

In January 2017 through a modification no. 04 in the Task order, USAID assigned the task to HPK to inspect the construction process of substantially completed building structures all over Pakistan on their behalf. Under this amendment, HPK visited the below listed ongoing projects and submitted comprehensive reports comprising site observations and conclusions.

i. Centre for Advanced Studies in Energy, UET Peshawar ii. Faculty of Education - Karakoram International University, Gilgit iii. Pre-fabricated Smart Container School - GGPS Daulat Tajazai, Lakki Marwat iv. Burns & Trauma Centre, HMC Peshawar

In addition to the above stated projects, further such visits are anticipated in near future.

3.2.3 Design Codes & Technical Specifications

Testing was carried out as per ASTM, AASHTO, BS EN, however mix-designs of asphalt/cement concrete was made according to relevant sections of American Asphalt/Cement Concrete Institute Manuals. Similarly hot and cold weather concreting was done according to ACI Manual sections 305-1 and 306-1. Concrete test results were evaluated as per ACI-214.

Standard specifications of National Transmission & Dispatch Company (NTDC) WAPDA were followed for inspection and testing of electrical material/equipment.

April 2016 to March 2017 Page 9 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

3.2.4 Review of Bill of Quantities (BOQs) and Engineer’s Cost Estimates

HPK periodically reviewed numerous BOQs and engineer’s cost estimates of sub-projects under buildings, roads, power and water sectors. These cost estimates served as the basis for establishing costs in the PILs in concurrence with existing site conditions as mentioned below:

i. Review of revised engineer’s estimates of all partially and fully damaged BHUs in Malakand Division. ii. Review of pending milestones of Munda and Amandara Head Works for PIL revision. iii. Preparation of revised milestones of Khwaza Khela Bridge in District Swat. iv. Revision of milestones and review of engineer’s estimate of militancy damaged schools (PIL-09). v. Revision of milestones and review of engineer’s estimate of partially damaged BHUs (PIL-21). vi. Preparation of milestones and review of engineer’s estimates of flood damaged schools (PIL-28).

In addition to above stated reviews of engineer estimates and revision of milestones, below reviews are underway:

i. Review of engineer’s estimate of GHSS Akbar Pura. ii. Revision of milestones and review of revised engineer’s estimate of flood damaged schools (PIL-30). iii. Review of engineer’s estimate of new 23 flood damaged schools. iv. Review of engineer’s estimate of Jamrud Bypass. v. Review of engineer’s estimate of additional works on BMG Road. vi. Review of engineer’s estimate of 132kV Transmission Line from Timergara to Khar.

April 2016 to March 2017 Page 10 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

3.2.5 Element 3: Construction Quality Assurance

HPK delivered Independent Quality Assurance services for the second year of the project as per the Task Order. Activities described under this element are, establishment of field offices, construction quality assurance, inspections, environmental compliance and record keeping. The activities executed under this element are detailed below:

3.2.6 Establishment of Field Offices

As per original task order HPK has already established project office in Peshawar and field offices in DI Khan and Swat and to conduct IQA activities for the ongoing 57 flood damaged schools, 132kV Grid Station and Transmission Line Khar, HPK established an additional field office in Timergara and additional laboratories in Timergara and Peshawar. It is pertinent to mention here that almost 40 flood damaged schools are likely to be added to the scope.

However, to cater the upcoming projects in Orakzai, Kurram, Khyber, Mohmand, Bajaur and South Waziristan Agencies and in Frontier Regions of Peshawar, Kohat and Tank, HPK plans to shift its DI Khan office to Hangu or Kohat to meet the upcoming sub-projects requirement.

HPK plans to hire additional staff for upcoming works in FATA regions after USAID’s approval as the pace / quantum of work expedites.

3.2.7 Construction Quality Assurance, Inspections & Testing

The project teams deployed in North, South and Central Zones continued and followed procedures as laid down in the approved QA plan to ensure that all construction activities were performed in accordance with the approved designs, drawings and technical specifications.

During site inspections HPK field staff performed the following main activities;

 Conducted independent inspections of the ongoing works as per frequency outlined in the QA Plan.  Verified the quantities and quality of construction/installation work and ensured conformity to design drawings, technical specifications and requirements by conducting requisite tests as per codes and standards during the course of construction of each sub-project.  Certified invoices of the implementing agencies for payments based on the acceptance of works after independent quality testing.

April 2016 to March 2017 Page 11 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

 Monitored environmental compliance. Reported safety conditions at construction sites and identified violations of safety regulations.  Recorded security incidents, extreme weather conditions, and any other events that could potentially affect the progress of work.  Regularly communicated the above works to USAID along with pictorial records.

The comparison of progress of all the subprojects between April- 2015, April-2016 and March 2017 has been outlined in Annexure-D.

3.2.8 Environmental Compliance

Environmental monitoring compliance of the project against approved Environmental Documentation Form (EDF) and Environmental Mitigation and Monitoring Plan (EMMP) is also the main component of the Task Order.

A two tiered environmental compliance monitoring protocol was followed which was inspection of environmental compliance against the approved EMMP by the HPK field staff visiting sites on regular basis and by an HPK Environmental Compliance Specialist (ECS).

HPK conducted a detailed assessment of local environmental and social conditions of the project area. It is pertinent to note that the assessment was done only under the scope of EMMP and comprehends the issues and concerns identified in the document only.

During the course of time, environmental screening was carried out for upcoming sub-projects in Frontier Regions of KPK. Details of environmental aspects of sub-projects were reported to USAID in form of pre-construction reports.

All environmental non-compliances noted were reported to USAID with recommendations for corrective actions in the form of field visit reports and monthly progress reports. Field supervision teams followed up with the construction contractors for implementation of corrective actions. Major issue observed at site was the unawareness of supervisory consultant and contractor about the environmental component of the project. All non-compliances were discussed in detail at site with contractors and supervisory consultants for rectification and advised for implementation of EDF/EMMP.

During the reporting year as per Task Order clause no. F.5.1.10, a success story of DI Khan – Tank Road was prepared and submitted to USAID. The submitted success story is attached as Annexure – E.

April 2016 to March 2017 Page 12 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

3.3 Milestone Certification for Construction Projects

HPK certified the achievement of payment milestone of all the ongoing construction projects during this period. Payment milestone certification was done in accordance with relevant PIL based on established testing protocols as per QA Plan.

Sector wise detail of the certified amount from April 2016 to March 2017 is summarised in the following table:

Sr. No. Sector Certified Amount (US$)

01 Building Sector 4,233,798 02 Road Sector 22,601,232 03 Power Sector 2,014,385 04 Water Sector 3,176,998

April 2016 to March 2017 Page 13 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

4 Significant Implementation Problems

Sector wise significant implementation problems encountered during the first year of IQA Project are described below: 4.1 Building Sector

i. Work on Water Supply Schemes is very slow especially in Buner and Swat. Some contractors have abandoned the work due to nonpayment of the executed tasks. In Buner, only 05 schemes and in Swat only 01 scheme are completed but work on the remaining schemes is either stopped or going on a slow pace. PaRRSA needs to ease the cash flow of the executing agencies (TMA Mingora in Swat and PHED in Buner) to clear the liabilities of the construction contractors. ii. Approval of the revision in PILs of flood damaged schools is pending which is required to regularize payment of the completed milestones. USAID to expedite the process of approval. iii. Commencement of work on Tehsil Level-Government Complex Kabal is significantly delayed due to delay in redesigning of the buildings by the consultant PePAC. It is already awarded to the construction contractors. iv. Work on the signature project GHSS Akbar Pura could not be started due to delay in design by the design consultant SHAZ. v. For flood damaged schools, information like construction drawings are not being shared timely by the executing agency and design consultant. 4.2 Road Sector

4.2.1 BMG Road

i. Work on joint/groove has been completed in the constructed rigid pavement except the last 165 m length where joint sealant is yet to be provided. ii. FWO/NESPAK are yet to provide the breakup of cost estimate for proposed works against savings on BMG Road.

April 2016 to March 2017 Page 14 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

4.3 Power Sector

4.3.1 132kV Grid Station Khar, Bajaur Agency:

i. The limited capacity of the supervision consultant M/s Allied Engineering Consultant (AEC) necessitated the enhanced frequency of visits of HPK’s IQA team. The IQA team had conducted 46 visits to the grid station till the reporting year. ii. Balance set of Factory Lab tests results as well as inspection certificates of already inspected local / imported material and equipment duly vetted by AEC are yet to be submitted by TESCO to HPK for review. iii. TESCO is yet to provide a complete set of corrected approved foundation drawings (AutoCAD) duly vetted by AEC for 132kV Transmission line, Khar. iv. Vetted documents of 132kV Grid Station /Transmission Line Khar i.e. design specifications and electrical drawings are yet to be submitted by AEC. 4.4 Water Sector

4.4.1 Munda Head-works:

Submission of an updated “Maintenance Plan” as a milestone is awaited from PaRRSA.

4.4.2 Amandara Headworks:

Submission of an updated “Maintenance Plan” as a milestone is awaited from PaRRSA.

4.4.3 Dhana Weir:

Removal of identified snags is pending since long.

April 2016 to March 2017 Page 15 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

5 Actions taken by HPK

HPK always suggested immediate and corrective actions to USAID and other stakeholders throughout the second year of IQA services in face of the problems encountered from time to time. A glimpse of actions taken is as below:

i. HPK timely communicated all issues raised on sites to USAID through weekly email updates, field visit reports and monthly progress reports. ii. HPK field staff enhanced their inputs where supervision consultant was not deployed. iii. HPK furnished investigation reports and suggested corrective measures as and when advised by USAID. iv. HPK timely communicated non-compliances at site to USAID which the executing agencies could not get rectified by the construction contractors. v. HPK assisted the implementing agencies in procurement of electrical equipment.

April 2016 to March 2017 Page 16 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

6 Observations/Recommendations

Following are some of the observations/recommendations for smooth execution of the project activities:

i. It has been noted that capacity of the design and supervision consultants M/s SHAZ and PePAC deployed on 57 flood damaged schools and Tehsil Level-Government Complex Kabal respectively, is not enough to timely respond to the construction related issues. This necessitated enhanced involvement of HPK staff in design review and discharge of IQA activities. ii. Cash flow problems of the construction contractors need to be addressed by the executing / implementing agencies for expedition of the ongoing works especially water supply schemes. iii. It is noted that the stipulated completion dates of majority of the sub-projects is not properly pursued by the executing agencies which causes unlimited delay in completion. It is recommended that the works schedules of each sub-project be strictly monitored and appropriate actions / measures be adopted. iv. For the upcoming sub-projects under KPRP and FIP the capacity of design and supervision consultant be properly scrutinized by the executing agencies before award of work. v. HPK recommends timely revision of PILs by the USAID.

April 2016 to March 2017 Page 17 of 17 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Annexure A – Task Order Deliverables

April 2016 to March 2017 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

To Date Report Title Due Date Frequency Clause submitted

F.5.1.1 Quality Assurance Plan - 19 May 15 Quarterly

F.5.1.1 Quality Assurance Plan – Rev 02 31 Mar 16 24 Mar 16 Quarterly

F.5.1.1 Quality Assurance Plan – Rev 03 30 Apr 17 24 May 17 Quarterly

F.5.1.2 Pre-Construction Visit Report - - As & when required

F.5.1.3 Annual Implementation Report 01 May 16 31 May 16 Annual

F.5.1.4 Security Assessment Plan - 15 Jul 15 As & when required

Once in project’s life F.5.1.5 Cost Control Report - 15 May 15 span On 10th of F.5.1.7 Monthly Progress Report - Monthly every month Every F.5.1.8 Weekly Progress Report - Weekly Monday F.5.1.10 Success Stories - 01 Feb 17 Semi-Annual

F.5.1.12 PAKINFO Reporting 14 May 17 12 May 17 Quarterly Once in project’s life - Branding & Marking Plan - 02 Nov 15 span - Field Visit Report - - Soon after field visit

April 2016 to March 2017 A-1 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Annexure B – Project Organization Chart

April 2016 to March 2017 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

April 2016 to March 2017 B-1 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Annexure C – HPK Deployed Staff List

April 2016 to March 2017 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

S. Location Company Name Designation Status #

1 PEW HPK TBN Chief of Party - QA Manager 2 PEW HPK M. Saeed Zia (Buildings) / Mobilized Acting CoP QA Manager 3 PEW HPK Said Afsar Khan Mobilized (Roads) QA Manager 4 PEW HPK Rustam Zad Gul Mobilized (Power) Mobilized QA Manager 5 PEW HPK Fazal Mahmood / Partial (Water) Position Design 6 ISB HPK Altaf Yunus Khan Mobilized Coordinator Muhammad Asim Office 7 PEW HPK Mobilized Masud Engineer Project Mian Ashfaq 8 PEW HPK Security Mobilized Hussain Shah Manager Junior 9 PEW HPK Shehryar Afridi Mobilized Engineer Environment 10 PEW HPK Fasih ur Rehman Compliance Mobilized Specialist IT & Admin 11 PEW HPK Manzar Habib Mobilized Manager 12 PEW HPK TBN Draftsman - Intermittent to Partial 13 PEW HPK provide partial IT & Database position input Computer 14 PEW HPK Tanveer Ahmad Mobilized Operator Admin 15 PEW HPK Shabbir Ahmed Mobilized Assistant 16 PEW AID Lai Khan QA Monitor Mobilized QA 17 PEW AID Zia ur Rehman Mobilized Supervisor-3 Lab 18 PEW AID Hamid Rehman Mobilized Technician Peon / Lab 19 PEW AID Afaq Dad Mobilized Helper Muhammad Driver - South 20 PEW AID Mobilized Arsalan Khan Region - 1 Muhammad Driver - South 21 PEW AID Mobilized Shahid Region - 2 22 PEW HPK Abidullah Driver - 1 Mobilized

23 PEW HPK Shahzad Munsif Driver - 2 Mobilized Muhammad 24 PEW HPK Driver - 3 Mobilized Sufiyan

April 2016 to March 2017 C-1 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

S. Location Company Name Designation Status #

25 PEW HPK Muhammad Riaz Driver - 4 Mobilized

26 PEW HPK Omar Rahman Cook Mobilized

27 PEW HPK Junaid Josef Janitor Mobilized

28 PEW HPK Wasif Ullah Peon – 1 Mobilized

29 PEW HPK Akber Hussain Peon – 2 Mobilized

30 South AID Zafar Alam QA Engineer Mobilized

31 South AID Adnan Khan QA Monitor Mobilized QA Monitor 32 South AID Adil Khursheed Mobilized (Water) Muhammad Abrar QA 33 South AID Mobilized Khan Supervisor-1 QA 34 South AID Muhammad Arif Mobilized Supervisor-2 Project 35 South HPK Capt. Haroon Latif Security Mobilized Officer Admin 36 South HPK Zeeshan Ahmed Assistant - Mobilized DIK M. Suleman Peon / Lab 37 South AID Mobilized Khattak Helper 38 South AID Adil Jalil Driver – 1 Mobilized Muhammad 39 South AID Driver – 2 Mobilized Ibrahim 40 South AID Ajab Gul Driver – 3 Mobilized

41 South AID Bilal Hussain Janitor Mobilized Ghulam 42 South AID Peon Mobilized Muhammad 43 South AID Naeem Iqbal Cook Mobilized Quantity 44 North HPK Imran Rashid Mobilized Surveyor 45 North HPK Shahid ur Rahman QA Engineer Mobilized QA Monitor - 46 North HPK Sharafat Ali Mobilized 1 QA Monitors – 47 North HPK Pazir Muhammad Mobilized 2 QA 48 North HPK Pervaiz Iqbal Mobilized Supervisors - 1 QA 49 North HPK Inam Khan Mobilized Supervisors - 2 QA 50 North HPK Abrarullah Mobilized Supervisors - 3 Muhammad QA Supervisor 51 North HPK Mobilized Haroon (Watsan)

April 2016 to March 2017 C-2 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

S. Location Company Name Designation Status # Lab 52 North HPK Amin Khan Mobilized Technician -1 Lab 53 North HPK Afaq Dad Mobilized Technician -2 54 North HPK Rashid Mahmood Lab Helper Mobilized Project 55 North HPK Capt. Asif Raza Security Mobilized Officer Muhammad Admin 56 North HPK Mobilized Qaisar Assistant 57 North HPK Yaad Nazar Driver - 1 Mobilized

58 North HPK Yaqoob Khan Driver - 2 Mobilized

59 North HPK Muhammad Zada Driver - 3 Mobilized

60 North HPK Sharif Ullah Driver - 4 Mobilized

61 North HPK Abdul Ahad Janitor Mobilized

62 North HPK Nisar Muhammad Cook Mobilized

63 North HPK Said Muhammad Peon Mobilized

April 2016 to March 2017 C-3 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Annexure D – Progress Review of Sub projects

April 2016 to March 2017 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

Building Sector - Militancy Damaged Schools (KPRP)

01 GGPS Bar Kalay Bishbanr Swat 100% 100% 100% Completed

02 GGMS Shakardara Swat 99.50% 100% 100% Completed

03 GGPS Ditpanai Swat 95.54% 100% 100% Completed

04 GGPS Paindai Sakhra Swat 87.12% 87.90% 100% Completed

05 GGPS Toor Toot Kishwara Swat 97.18% 100% 100% Completed

06 GHSS Zaimdara Dir Lower 93.20% 100% 100% Completed

07 GHS Sangolai Dir Lower 100% 100% 100% Completed

08 GGHS Tirat Qandil Swat 95.10% 100% 100% Completed

09 GGPS Bishbanr Swat 79.81% 100% 100% Completed

10 GGPS Seer Telegram Swat 100% 100% 100% Completed

11 GGHS Ganori Dir Upper 91.50% 100% 100% Completed

12 GGMS Bar Shawar Swat 71.80% 86.65% 100% Completed

13 GGPS Ghari Chuprial Swat 87.10% 100% 100% Completed

14 GHS Shekolai Tormang Dir Lower 65.50% 100% 100% Completed

15 GGPS Balasur Chuprail Swat 53.10% 93.19% 100% Completed

16 GGPS Chuprial Swat 45.33% 47.21% 67.00% In Progress

17 GPS Mirgam Bala Dir Lower 56.80% 96.31% 100% Completed

18 GGPS Saeed Abad No: 1 Swat 45.87% 83.39% 100% Completed

19 GHS Bar Shawar Swat 51.75% 100% 100% Completed

GGPS 20 Swat 81.10% 100% 100% Completed MalamJaba

21 GGPS Mangra Sakhra Swat 46.72% 89.67% 100% Completed

22 GPS Dapoor Dir Lower 41.75% 94.95% 100% Completed

23 GPS Chiragali Dir Upper 73.50% 100% 100% Completed

24 GHS Buner 43.90% 81.00% 100% Completed

GGPS Qayumabad 25 Swat 65.70% 100% 100% Completed Lalkoo

26 GMS Gul Bandai Buner 28.00% 28.00% 33.00% In Progress

April 2016 to March 2017 D-1 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

27 GGPS Kass Khass Swat 30.30% 76.52% 100% Completed

28 GGPS Lalkoo Sakhra Swat 27.78% 73.47% 100% Completed

29 GGPS Swat 60.50% 87.38% 100% Completed

30 GGPS SpinaKhpa Swat 39.59% 98.49% 100% Completed

Building Sector - Flood Damaged Schools (KPRP)

1 GPS No. 2 Maloch Swat - - 49.52% In Progress

2 GPS Chinda Khora Swat - - 24.24% In Progress

3 GGPS Kas Swat - - 15.69% In Progress

4 GPS Pacha Kalay Swat - - 29.84% In Progress

5 GPS Godha Swat - - 24.07% In Progress

6 GGPS Godha Swat - - 4.30% In Progress

7 GPS Biha Swat - - 17.50% In Progress

8 GGMS Qayum Abad Swat - - 26.00% In Progress

9 GGPS Serai Gut Swat - - 12.00% In Progress

10 GPS Muraday Swat - - 11.00% In Progress

11 GGPS Swat - - 2.90% In Progress

12 GPS Hisar Baba Malakand - - 21.37% In Progress

13 GHS Inzargai Malakand - - 10.81% In Progress

14 GPS Jalal Kot Malakand - - 45.65% In Progress

15 GGPS Qambari Shangla - - 0.91% In Progress

16 GGPS Shalmano Kotkai Shangla - - 3.55% In Progress

17 GHS Shang Shangla - - 4.22% In Progress

GGPS Shalmano 18 Shangla - - 6.08% In Progress Chakesar

19 GMS Bilkanai Shangla - - 7.77% In Progress

20 GGPS Begumar Lahore Shangla - - 10.71% In Progress

21 GHS Amnavi Shangla - - 1.43% In Progress

22 GMS Asigi Kalay Dir Lower - - 3.82% In Progress

23 GHS Mian Brangola Dir Lower - - 1.83% In Progress

24 GPS Zimdara Dir Lower - - 6.85% In Progress

April 2016 to March 2017 D-2 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

25 GHS Mirgam Bala Dir Lower - - 0.90% In Progress

26 GGMS Kotkay Dir Lower - - 10.61% In Progress

27 GGHSS Kumbar Dir Lower - - - Dropped by PaRRSA

28 GHS Sadbar Kalay Dir Lower - - 52.11% In Progress

29 GPS Chinar Kot Dir Lower - - - Dropped by PaRRSA

30 GPS Raidgai Dir Lower - - 8.60% In Progress

31 GPS No.1 Sherkhanai Dir Lower - - 8.86% In Progress

32 GPS Sra Dherai Dir Lower - - - Dropped by PaRRSA

33 GPS Kass Dir Upper - - 2.10% In Progress

34 GPS Tangi Sar Dir Upper - - 8.00% In Progress

35 GPS Remin Kass Dir Upper - - 2.10% In Progress

36 GPS Shomai Dir Upper - - - In tendering stage

37 GPS Nihag Dir Upper - - 6.59% In Progress

38 GPS Zakria Dir Upper - - 1.42% In Progress

39 GPS Sundrai Dir Upper - - - In Progress

40 GPS Sundal Dir Upper - - 15.35% In Progress

41 GHS Jan Batti Dir Upper - - 2.20% In Progress

42 GPS Mansooka Charsadda - - 8.08% In Progress

43 GGPS Kaptan Kaley Charsadda - - 0.00% In Progress

44 GGPS Samunat Charsadda - - 34.80% In Progress

45 GPS Mian Kaley Charsadda - - - Dropped by PaRRSA

46 GPS Shahidan Charsadda - - 43.50% In Progress

Replaced with GGPS 47 GPS Mardand Charsadda - - - Mian Sahib Garhi

GPS Shahab Khail Kaka 48 Nowshera - - 30.12% In Progress Sahib

49 GPS Sherin Kotai Nowshera - - 54.49% In Progress

50 GPS Tor Dheri Nowshera - - 24.98% In Progress

51 GPS Kotar Pan No. 1 Nowshera - - 19.62% In Progress

52 GGPS Pushtoon Garhi Nowshera - - 68.09% In Progress

April 2016 to March 2017 D-3 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

53 GPS Baab e Jadeed Nowshera - - 25.38% In Progress

54 GPS Kandi Taaza Din Nowshera - - 45.98% In Progress

55 GPS No.1 Mishak Nowshera - - 22.47% In Progress

56 GGPS Maroba Nowshera - - 17.85% In Progress

57 GGPS Jhoke Gomla DI Khan - - 7.27% In Progress

58 GPS Roraa Nawa DI Khan - - 53.89% In Progress

59 GPS Makar DI Khan - - 40.35% In Progress

60 GPS No. 1 Yarak DI Khan - - 13.46% In Progress

61 GPS Jhoke Umaray Wali DI Khan - - 4.17% In Progress

62 GPS Bairoon Sharqi DI Khan - - 18.50% In Progress

Building Sector - Militancy Damaged Schools (FIP)

1 GPS Bora No.2 FR Peshawar - - -

2 GGPS Janat Khan FR Peshawar - - -

3 GHS Bora FR Peshawar - - -

4 GHS Musa Dara FR Peshawar - - -

5 GGHS Samand Khan FR Peshawar - - -

6 GGPS Feroz Khan FR Peshawar - - -

7 GPS Shahi Khel FR Kohat - - -

8 GPS Feroz Kili FR Kohat - - -

9 GPS Sarwar Khel FR Kohat - - - Pre-Construction 10 GGPS Zoor Kili FR Kohat - - - Report submitted to USAID 11 GMS Kohi Wal FR Kohat - - -

12 GGMS Noor Ali Khel FR Kohat - - -

GGMS Sara Meal Bosti 13 FR Kohat - - - Khel

14 GGMS Jammu Shahi Khel FR Kohat - - -

15 GGMS Bila Kili FR Kohat - - -

GGMS Surak Toor 16 FR Kohat - - - Chapper

17 GGMS Jani Khel FR Kohat - - -

18 GGMS Suni Khel FR Kohat - - -

April 2016 to March 2017 D-4 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

Building Sector - BHUs

01 BHU Chongai Shamozai Swat 72.18% 96.55% 100% In Progress

02 BHU MianKalay Swat 50.75% 82.71% 100% In Progress

03 BHU Nazarabad Swat 84.50% 99.34% 100% In Progress

04 BHU Kishwara Swat 77.75% 100% 100% Completed

05 BHU Topai Buner 69.55% 80.82% 96.00% In Progress

06 MCH Kithiari Dir Lower 42.20% 100% 100% Completed

07 CD Telegram Swat 100% 99.93% 99.93% In Progress

08 CD Pararai Swat 71.10% 100% 100% Completed

09 BHU Bishbanr Swat 11.70% 51.33% 100% In Progress

10 BHU Mashkomai Swat 25.19% 47.00% 54.25% In Progress

11 BHU Swat 29.40% 59.50% 100% In Progress

12 BHU Swat 8.20% 51.33% 100% In Progress

13 BHU Bandai Swat 17.75% 74.83% 100% In Progress Drinking Water Supply Schemes (DWSS)

DWSS Chonge (Hand 01 Buner 95.44% 100% 100% Completed Pumps)

02 DWSS Buner 84.70% 99.00% 100% In Progress

03 DWSS Maskipur Buner 57.60% 58.07% 58.07% In Progress

04 DWSS Banda (Krapa) Buner 78.55% 93.00% 96.00% In Progress

05 DWSS Dagai Buner 23.05% 30.00% 36.00% In Progress

06 DWSS Jang Dara Buner 13.63% 65.00% 65.00% In Progress

07 DWSS Buner 17.79% 21.00% 41.00% In Progress

08 DWSS Sunigram Buner 20.21% 20.21% 46.00% In Progress

09 DWSS Qibla Maira Buner 65.40% 98.00% 100% In Progress

10 DWSS Soor Kamar Maira Buner 65.10% 75.69% 80.00% In Progress

11 DWSS Bagra Maira Buner 68.20% 99.00% 100% In Progress

12 DWSS Jowar Buner 1.90% 27.15% 25.15% In Progress

13 DWSS Aso Dara Buner 63.80% 98.68% 100% In Progress

14 DWSS Shagai zone 1 Swat 17.00% 45.00% 75.00% In Progress

April 2016 to March 2017 D-5 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

15 DWSS 120 Hand Pumps Swat 41.50% 45.00% 63.00% In Progress

16 DWSS Naway kaley Swat 0.50% 35.00% 85.00% In Progress

17 DWSS Akram Muhallahs Swat 18.60% 40.50% 67.00% In Progress

18 DWSS Barama Swat - 10.00% 48.00% In Progress

19 DWSS Akhon Baba Swat 27% 43.00% 62.00% In Progress

20 DWSS Makan Bagh Swat 2% 48.40% 68.00% In Progress

21 DWSS Maira Swat - 28.00% 67.00% In Progress

22 DWSS Shahidabad Fizagat Swat 13% 57.00% 62.00% In Progress

Transformers & Voltage 23 Swat 18.50% 73.00% 100% In Progress Regulators

Road Sector

01 DI Khan–Tank Road DI Khan & Tank 78% 99.00% 100% In Progress

In Progress 02 Tank Bypass Tank 5% 98.00% 100%

In Progress 03 Link to Tank City Tank - 98.00% 100%

North Bannu-MiranShah- 04 Waziristan 84% 91.00% 99.00% In Progress Ghulam Khan Road Agency

South Wana–Shakai– Makin 05 Waziristan 99% 100% 100% Completed Road Agency

Pre-Construction Construction of Jamrud 06 Khyber Agency - - - Report submitted to Bypass USAID

Road Sector – Bridges on WSM Road

South Makeen Bridge(29.29 m) at 01 Waziristan - 100 % 100 % Completed Km 71 Agency

South Badar Bridge (46.79 m) at 02 Waziristan - 95 % 100 % In Progress Km 58 Agency

South 03 Torwam Bridge at Km 28 Waziristan - 100 % 100 % Completed Agency

April 2016 to March 2017 D-6 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

Road Sector – Bridges on BMG Road

North Baran Bridge (176 m) at 01 Waziristan - 100 % 100 % Completed Km 7 Agency

North Chorai Bridge (30 m) at 02 Waziristan - 100 % 100 % Completed Km 26 Agency

North Khajuri Bridge (61 m) at 03 Waziristan - 92 % 100 % In Progress Km 30 Agency

North Charkha Bridge(96.943 m) 04 Waziristan - 75 % 100 % In Progress at Km 72 Agency

North Eidak Bridge (156.84 m)at 05 Waziristan - 92 % 100 % In Progress Km 45 Agency

North Dinga Bridge(88.034 m) at 06 Waziristan - 97 % 100 % In Progress Km 62 Agency

North 07 Churkhai Bridge at Km 81 Waziristan - 70 % 100% In Progress Agency

Power Sector

Transmission line from South 01 Gomal Zam Dam to Wana Waziristan 81% 100% 100% Completed Grid station, Agency

South 02 Wana Grid station Waziristan 96% 100% 100% Completed Agency

Rehabilitation of South 03 11kV/33kV distribution Waziristan 85% 87.5% 96% In Progress system Agency

04 Khar Grid Station Bajaur Agency - 17% 56.5% In Progress

Transmission Line from 05 Bajaur Agency - - - Work to be started yet Timergara to Khar

Water Sector

Restoration of Munda Munda, Substantially 01 98% 99.5% 100% Head Works Charsadda completed

Restoration of Amandara Batkhela, Substantially 02 98% 99.0% 100% Head Works Malakand completed

April 2016 to March 2017 D-7 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Progress Progress Progress S. as of as of as of Name of Project Location Status No. April April March 2015 2016 2017

South Dhana Irrigation and 03 Waziristan 30% 97.0% 99.4% In Progress Water Supply Scheme Agency

April 2016 to March 2017 D-8 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Annexure E – Success Stories

April 2016 to March 2017 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Pakistan

SUCCESS STORY

Aim to Bring People on the Highway of Success

USAID’s interventions to connect Roads make a crucial contribution to economic people, drive commerce, easy access development and growth to bring significant socio- to health facilities and maintain global economic benefits which were missing in Tank due competitiveness. to deprived road conditions.

Excellent infrastructure is the mainstay and paramount driver of socio-economic development, which every country strives to achieve. Road and highways help to connect people, drive commerce, easy access to health facilities and maintain global competitiveness. USAID always wishes to uplift the socio-economic conditions of dwellers by improving connectivity and providing approach to local markets and basic

facilities with expansion and improvement of roads. The road improvement not only makes the access easy but also One of such cases is widening and improvement of enhances the living standards of area DI Khan-Tank Road, which has been improved by creating opportunities for its under the USAID Programme in 2012-16. Now residents. there is a free flow of traffic and social as well as economic values of Tank’s population is on a track USAID’s programs help the people of improvement. of the community in provision of easy access to basic facilities and Mr. Gul Zaman, a truck driver, one of the main local/ international markets. beneficiaries of the subject project told that previously the poor condition of the road was a source of high expense and low income. Improvement of the road not only reduced the maintenance cost but also benefitted him financially in terms of maximum number of trips in a day.

This is not the only example as there are many success stories like these such as increase in number of filling stations, road side hotels and development of housing schemes connected with road improvement. Moreover, it plays a vital role in the enhancement of security of the area. One can say that DI Khan-Tank Road is a beacon of success for the people of Tank.

April 2016 to March 2017 E-1 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

Annexure F – Pictorial Progress

April 2016 to March 2017 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – MILITANCY DAMAGED SCHOOLS

Fig. 01. Completed GGPS Manlgawar, Swat (April Fig. 02. Completed GGPS Paindai Sakhra, Swat 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. Completed GGPS Balasur Chuprial, Swat Fig. 04. Completed GGPS Mangra Sakhra, Swat (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 05. Completed GPS Mergam Bala, Dir Lower Fig. 06. Completed GGPS Lalkoo Sakhra, Swat (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-1 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – MILITANCY DAMAGED SCHOOLS

Fig. 07. Completed GPS Dapoor, Dir Lower Fig. 08. Completed GGPS Kass Khass, Swat (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 09. Completed GGPS Saeed Abad, Swat Fig. 10. Completed GGMS Bar Shawar, Swat (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 11. Completed GHS Gul Bandai, Buner Fig. 12. Completed GGPS Spina Khpa, Swat (April (April 2016 – March 2017) 2016 – March 2017)

April 2016 to March 2017 F-2 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – FLOOD DAMAGED SCHOOLS

Fig. 01. Mumty work in progress at GHS Sadbar Fig. 02. Brick masonry work at first floor in Kalay, Dir Lower (April 2016 – March 2017) progress at GGMS Qayum Abad, District Swat (April 2016 – March 2017)

Fig. 03. GPS No.2 Maloch, Swat (An external view Fig. 04. Preparation for foundation excavation, of the school) (April 2016 – March 2017) GGPS Pashtoon Garhi, Nowshera (April 2016 – March 2017)

Fig. 05. Additional Plinth beam cast in GPS Hisar Fig. 06. Mumty Slab concreting in progress at GPS Baba, Malakand (April 2016 – March 2017) Jalal Kot, Malakand (April 2016 – March 2017)

April 2016 to March 2017 F-3 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – BHUs

Fig. 01. Completed BHU Chongai Shamozai, Swat Fig. 02. Completed BHU Kotanai, Swat (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. Completed BHU Mian Kalay, Swat Fig. 04. Completed residential quarters BHU Mian (April 2016 – March 2017) Kalay, Swat (April 2016 – March 2017)

Fig. 05. Completed BHU Bandai, Swat Fig. 06. Completed residential quarter, BHU Bandai, (April 2016 – March 2017) Swat (April 2016 – March 2017)

April 2016 to March 2017 F-4 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – BHUs

Fig. 07. Completed BHU Nazar Abad, Swat Fig. 08. Completed BHU Nazar Abad, Swat (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 09. Completed BHU Shalpin, Swat Fig. 10. Completed residential quarter BHU Shalpin, (April 2016 – March 2017) Swat (April 2016 – March 2017)

Fig. 11. Completed BHU Bishbanr, Swat Fig. 12. Completed CAT V-VI Residence building (April 2016 – March 2017) BHU Bishbanr, Swat (April 2016 – March 2017)

April 2016 to March 2017 F-5 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – WATSAN

Fig. 01. DWSS Bagra Maira, Buner Fig. 02. DWSS Shalbandi, Buner (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. DWSS Aso Dara, Buner Fig. 04. DWSS Banda Karapa Buner (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 05. DWSS Qibla Maira Fig. 06. Completed DWSS Deewana Baba, Buner (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-6 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

BUILDING SECTOR – 132 KV GRID STATION KHAR – BAJAUR AGENCY

Fig. 01. Pointing on walls of Control House Building Fig. 02. Dressing of front lawn of Control House (CHB) (April 2016 – March 2017) Building (CHB) (April 2016 – March 2017)

Fig. 03. OHWT in Khar Grid, Bajaur Fig. 04. View of draw pit at switch yard where brick (April 2016 – March 2017) masonry & plastering completed (April 2016 – March 2017)

Fig. 05. Front view of Control House Building Fig. 06. View of D-type quarters (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-7 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

ROAD SECTOR – DI KHAN – TANK ROAD

Fig. 01. View of Y-junctions on Tank Bypass Fig. 02. HPK staff measuring the dimensions of sign (April 2016 – March 2017) board at Tank by Pass Road (April 2016 – March 2017)

Fig. 03. HPK staff measuring the dimensions of sign Fig. 04. Sign board at section 05 of DIK – Tank Road board at Tank by Pass Road (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 05. HPK staff measuring the dimensions of sign Fig. 06. Sign board at Link to Tank board at Link to Tank (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-8 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

ROAD SECTOR – BMG ROAD

Fig. 01. Parapet walls on stone masonry retaining Fig. 02. HPK staff checking the road marking at km wall at km 40 of section# 04 of BMG Road 65 of section# 7B (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. RCC parapet wall on retaining wall at Fig. 04. Checking the load of truck at weigh station Churkhai Bridge (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 05. Ten KM post at km 41 of section#05 Fig. 06. Roll pointing on parapet wall of retaining (April 2016 – March 2017) wall at Dinga Bridge (April 2016 – March 2017)

April 2016 to March 2017 F-9 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

ROAD SECTOR – WSM ROAD

Fig. 01. Parapets on retaining wall at km-17 of Fig. 02. PCC parapet walls on stone masonry Section#02 of BMG Road retaining walls in Section I at WSM Road (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. A view of Badar Bridge on WSM Road Fig. 04. HPK staff measuring length of metal guard (April 2016 – March 2017) rail in Section IV of WSM Road (April 2016 – March 2017)

Fig. 05. PCC shoulder in Section III at WSM Road Fig. 06. HPK staff checking compressive strength of (April 2016 – March 2017) PCC parapet wall using Schmidt hammer in Section I at WSM Road (April 2016 – March 2017)

April 2016 to March 2017 F-10 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

REHABILITATION WORKS – POWER SECTOR

Fig. 01. Newly installed 100 KVA transformer on Fig 02. HPK field staff verifying the height of single double adda in village Sarkai Kalla adda for design conformity in village Akka Khel (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. Test arrangement for short Circuit Test of Fig. 04. HPK representative verifying the serial 200kV Aux Transformer numbers of CP-30, 50, Auxiliary and Capacitor (April 2016 – March 2017) Bank panel (April 2016 – March 2017)

Fig. 05. Newly installed Disc insulators, Cross rams, Fig. 06. HPK & TESCO representative performing Rabbit conductor in village Manzara/Paya No load losses and current test (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-11 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

WATER SECTOR

Fig. 01. Mechanical works at R/S Under sluices Fig. 02. VHF Repeater along with Batteries installed Gates D/S (April 2016 – March 2017) in Thandyani Abbottabad (April 2016 – March 2017)

Fig. 03. View of main Dhana weir structure from hill Fig. 04. Joint inspection of Mechanical works by side (April 2016 – March 2017) Irrigation Dptt. FATA, HPK, NESPAK & FWO teams at Dhana Weir (April 2016 – March 2017)

Fig. 05. R/S operator room constructed near by the Fig. 06. Measuring toe wall provided for Grouted R/S head regulator (April 2016 – March 2017) Rip Rap road (April 2016 – March 2017)

April 2016 to March 2017 F-12 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

SECURITY TRAINING OF STAFF

Fig. 01. Security briefing to drivers at IQA-DI Khan Fig. 02. Security briefing to IQA-Swat office staff Office (April 2016 – March 2017) (April 2016 – March 2017)

Fig. 03. Security briefing to IQA-Swat office staff Fig. 04. Security briefing to IQA-Swat office

(April 2016 – March 2017) supporting staff (April 2016 – March 2017)

Fig. 05. Security briefing to IQA-Swat office staff Fig. 06. Security briefing to IQA-Swat office staff (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-13 HPK Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report

ENVIRONMENT

Fig. 01. Properly managed construction site Fig. 02. Worker with safety helmet at overhead water (April 2016 – March 2017) tank site (April 2016 – March 2017)

Fig. 03. Improved housekeeping at construction of Fig. 04. Training session on environment accommodation building-engineers in partial (April 2016 – March 2017) compliance of PPEs (April 2016 – March 2017)

Fig. 05. Awareness session with team regarding Fig. 06. Training session conducted for site staff at environmental aspects of project at GGPS Samunath GGPS Maroba, Nowshera (April 2016 – March 2017) (April 2016 – March 2017)

April 2016 to March 2017 F-14 HPK