Qualitative Sequencing Investment Strategies – listed by sequenced time period July 2020

Delivery S1 S2 S3 BAU Period

Post 2027 • Leeds – Newcastle Corridor (major • Leeds – Newcastle Corridor (major • Leeds – Newcastle Corridor (major Reference upgrade via to upgrade via East Coast Main Line to upgrade via East Coast Main Line to Case include provision for HS2 services running include provision for HS2 services running include provision for HS2 services running (Schemes in north to Scotland) north to Scotland) north to Scotland) an existing • Sheffield – Leeds Corridor (connection to • Sheffield – Leeds Corridor (connection to • Sheffield – Leeds Corridor (connection to programme HS2) HS2) HS2) e.g. NPR / • Airport – Manchester • Manchester Airport – Manchester • Manchester Airport – Manchester TPT) Corridor (via HS2) Corridor (via HS2) Corridor (via HS2) • – Manchester Airport Corridor • Liverpool – Manchester Airport Corridor • Liverpool – Manchester Airport Corridor (new line) (new line) (new line) • Manchester – Leeds Corridor (new line • Manchester – Leeds Corridor (new line • Manchester – Leeds Corridor (new line via Bradford) via Bradford) via Bradford) • Manchester – Sheffield Corridor (further • Manchester – Sheffield Corridor (further • Manchester – Sheffield Corridor (further interventions) interventions) interventions) • Interventions at the major hubs • Interventions at the major hubs • Interventions at the major hubs necessary to realise the benefits of necessary to realise the benefits of necessary to realise the benefits of improved connectivity along the corridors improved connectivity along the corridors improved connectivity along the corridors identified above, including Newcastle, identified above, including Newcastle, identified above, including Newcastle, York, Sheffield, Manchester Piccadilly, York, Sheffield, Manchester Piccadilly, York, Sheffield, Manchester Piccadilly, Liverpool Lime Street and Leeds Liverpool Lime Street and Leeds Liverpool Lime Street and Leeds • West Coast Main Line – Wigan and • West Coast Main Line – Wigan and • West Coast Main Line – Wigan and Preston to Scotland (journey time and Preston to Scotland (journey time and Preston to Scotland (journey time and capacity improvements) capacity improvements) capacity improvements) • Borders railway (supporting cross-border • Borders railway (supporting cross-border • Borders railway (supporting cross-border working with Transport Scotland and working with Transport Scotland and working with Transport Scotland and Borderlands Partnership) Borderlands Partnership) Borderlands Partnership) • station (later phases) • Stockport station (later phases) • Stockport station (later phases) • Bank Quay station (or • Warrington Bank Quay station (or • Warrington Bank Quay station (or integrated station at Warrington) integrated station at Warrington) integrated station at Warrington) • Lancaster station • Lancaster station • Lancaster station • Oxenholme station • Oxenholme station • Oxenholme station • Penrith station • Penrith station • Penrith station • Northallerton Station • Northallerton Station • Northallerton Station • Durham Station • Durham Station • Durham Station • York to Newcastle • York to Newcastle • York to Newcastle • Trans Pennine • Trans Pennine Tunnel • Trans Pennine Tunnel • Northallerton - Newcastle capacity • Northallerton - Newcastle capacity • Northallerton - Newcastle capacity enhancements and timetable resilience enhancements and timetable resilience enhancements and timetable resilience • Crewe – Stoke – Derby (journey time • Crewe – Stoke – Derby (journey time • Crewe – Stoke – Derby (journey time improvements) improvements) improvements) • M60 Manchester North West Quadrant • M60 Manchester North West Quadrant • M60 Manchester North West Quadrant including M62 to A57 Junction and Link including M62 to A57 Junction and Link including M62 to A57 Junction and Link • Bradford to Leeds (journey time • Bradford to Leeds (journey time • Bradford to Leeds (journey time improvements) improvements) improvements) SOP 2027- • Wigan North Western station (or • Wigan North Western station (or • Wigan North Western station (or 2033 ‘Fixed integrated station at Wigan) integrated station at Wigan) integrated station at Wigan) Window’ • York to Scarborough (journey time • York to Scarborough (journey time • York to Scarborough (journey time Schemes improvements) improvements) improvements) • Service frequency enhancements • Service frequency enhancements • Service frequency enhancements between Ormskirk and Preston between Ormskirk and Preston between Ormskirk and Preston • Access improvements to Crewe HS2 Hub • Access improvements to Crewe HS2 Hub • Access improvements to Crewe HS2 Hub • Doncaster-Leeds - journey time & • Doncaster-Leeds - journey time & • Doncaster-Leeds - journey time & capacity improvements capacity improvements capacity improvements • M1 Junction 35A to 39 Sheffield to • M1 Junction 35A to 39 Sheffield to • M1 Junction 35A to 39 Sheffield to Wakefield Extra Capacity Wakefield Extra Capacity Wakefield Extra Capacity • A1 Doncaster-Darrington • A1 Doncaster-Darrington • A1 Doncaster-Darrington • A19 North of Newcastle Junctions (Part) • A19 North of Newcastle Junctions (Part) • A19 North of Newcastle Junctions (Part) comprising: A19/A1 Seaton Burn Junction comprising: A19/A1 Seaton Burn Junction comprising: A19/A1 Seaton Burn Junction Improvements; A19 /A189 Moor Farm; Improvements; A19 /A189 Moor Farm; Improvements; A19 /A189 Moor Farm; A19/A1056 Killingworth; and A19/A193 A19/A1056 Killingworth; and A19/A193 A19/A1056 Killingworth; and A19/A193 Howdon Interchange Howdon Interchange Howdon Interchange • Skipton - Colne - Gannow Junction • Skipton - Colne - Gannow Junction • Skipton - Colne - Gannow Junction (journey time and service improvements) (journey time and service improvements) (journey time and service improvements) • Preston to York via Blackburn (journey • Preston to York via Blackburn (journey • Preston to York via Blackburn (journey time improvements) time improvements) time improvements) • M65 Junctions 2 to 6 • M65 Junctions 2 to 6 • M65 Junctions 2 to 6 • A64 Hopgrove • A64 Hopgrove • A64 Hopgrove • M1/M62 Lofthouse Interchange • M1/M62 Lofthouse Interchange • M1/M62 Lofthouse Interchange • Links to Terminal 2 at • Light Rail Links to Terminal 2 at • Light Rail Links to Terminal 2 at Manchester Airport Manchester Airport Manchester Airport

Qualitative Sequencing Investment Strategies – listed by sequenced time period July 2020

Delivery S1 S2 S3 BAU Period

• A174 Greyston21/04/20es Roundabout • A174 Greystones Roundabout • A174 Greystones Roundabout Improvements Improvements Improvements • Port of Tyne Connectivity • Port of Tyne Connectivity • Port of Tyne Connectivity • Tees Dock Road Roundabout • Tees Dock Road Roundabout • Tees Dock Road Roundabout Improvements Improvements Improvements • Eastern route access package to • Eastern route access package to • Eastern route access package to Liverpool John Lennon Airport and Liverpool John Lennon Airport and Liverpool John Lennon Airport and associated developments associated developments associated developments • A63/A1033 junction • A63/A1033 junction • A63/A1033 junction • Grimsby Western Relief Road • Grimsby Western Relief Road • Grimsby Western Relief Road • Selby to Port of Hull gauge • Selby to Port of Hull gauge • Selby to Port of Hull gauge enhancements and journey time enhancements and journey time enhancements and journey time improvements improvements improvements • Port Salford rail freight access • Port Salford rail freight access • Port Salford rail freight access • East-West Transpennine W12 gauge • East-West Transpennine W12 gauge • East-West Transpennine W12 gauge cleared rail freight route cleared rail freight route cleared rail freight route • Preston to Blackpool South (South Fylde • Preston to Blackpool South (South Fylde • Preston to Blackpool South (South Fylde Line) - journey time and capacity Line) - journey time and capacity Line) - journey time and capacity improvements improvements improvements • A66 Improvements (Scales/Troutbeck) • A66 Improvements (Scales/Troutbeck) • A66 Improvements (Scales/Troutbeck) • Newby Bridge Flooding Alleviation • Newby Bridge Flooding Alleviation • Newby Bridge Flooding Alleviation • A595 Whitehaven Relief Road, Bigrigg • A595 Whitehaven Relief Road, Bigrigg • A595 Whitehaven Relief Road, Bigrigg Bypass and Egremont Junctions Bypass and Egremont Junctions Bypass and Egremont Junctions • Station and Sunderland • and Sunderland • Sunderland Station and Sunderland Station track layout improvements Station track layout improvements Station track layout improvements • Newcastle to (Durham • Newcastle to Middlesbrough (Durham • Newcastle to Middlesbrough () – route & station Coast Line) - route & Hartlepool station Coast Line) - route & Hartlepool station upgrade and service improvements upgrade and service improvements upgrade and service improvements • Sunderland Strategic Transport Corridor • Sunderland Strategic Transport Corridor • Sunderland Strategic Transport Corridor (Phases 4 & 5) (Phases 4 & 5) (Phases 4 & 5) • A1068 Fisher Lane • A1068 Fisher Lane • A1068 Fisher Lane • Middlesbrough to York (journey time and • Middlesbrough to York (journey time and • Middlesbrough to York (journey time and service improvements) service improvements) service improvements) • A66 Darlington to Teesport capacity • A66 Darlington to Teesport capacity • A66 Darlington to Teesport capacity improvements improvements improvements • A15 junctions (A63 to M180) • A15 junctions (A63 to M180) • A15 junctions (A63 to M180) • A558 Daresbury Expressway • A558 Daresbury Expressway • A558 Daresbury Expressway improvements improvements improvements • to Sandbach rail re-opening • Northwich to Sandbach rail re-opening • Northwich to Sandbach rail re-opening and new stations and new stations and new stations • Manchester to via • Manchester to Chester via Knutsford • Manchester to Chester via Knutsford (Mid- Line) - journey time and (Mid-Cheshire Line) - journey time and (Mid-Cheshire Line) - journey time and capacity improvements capacity improvements capacity improvements • Liverpool to Manchester via Warrington • Liverpool to Manchester via Warrington • Liverpool to Manchester via Warrington (Cheshire Lines Committee) - capacity and (Cheshire Lines Committee) - capacity and (Cheshire Lines Committee) - capacity and service improvements service improvements service improvements • A550 Chester Box Route Enhancements • A550 Chester Box Route Enhancements • A550 Chester Box Route Enhancements • Chester – Broughton growth corridor • Chester – Broughton growth corridor • Chester – Broughton growth corridor • Middlewich southern and western link • Middlewich southern and western link • Middlewich southern and western link (including access to the M6 from ) (including access to the M6 from Winsford) (including access to the M6 from Winsford) • Bus Rapid Transit Schemes connecting • Bus Rapid Transit Schemes connecting • Bus Rapid Transit Schemes connecting Wigan Borough and Salford City Wigan Borough and Salford City Wigan Borough and Salford City • Northern Gateway access and capacity • Northern Gateway access and capacity • Northern Gateway access and capacity enhancements enhancements enhancements • Manchester South East Junction • Manchester South East Junction • Manchester South East Junction Improvements Improvements Improvements • M60/M67 Denton Island improvements • M60/M67 Denton Island improvements • M60/M67 Denton Island improvements • Burnley to Manchester (journey time and • Burnley to Manchester (journey time and • Burnley to Manchester (journey time and service improvements) service improvements) service improvements) • Leeds North West Quadrant • Leeds North West Quadrant • Leeds North West Quadrant improvements improvements improvements • M1 Leeds Eastern Gateway • M1 Leeds Eastern Gateway • M1 Leeds Eastern Gateway • South East Bradford Link Road • South East Bradford Link Road • South East Bradford Link Road • Shipley Eastern Relief Road • Shipley Eastern Relief Road • Shipley Eastern Relief Road • A638 improvements – Dewsbury to the • A638 improvements – Dewsbury to the • A638 improvements – Dewsbury to the A1(M) A1(M) A1(M) • Leeds to Sheffield via Barnsley (Hallam • Leeds to Sheffield via Barnsley (Hallam • Leeds to Sheffield via Barnsley (Hallam Line) - journey time improvements Line) - journey time improvements Line) - journey time improvements • Journey time and capacity improvements • Journey time and capacity improvements • Journey time and capacity improvements between Cleethorpes and Doncaster to between Cleethorpes and Doncaster to between Cleethorpes and Doncaster to increase links between Northern increase links between Northern increase links between Northern

Qualitative Sequencing Investment Strategies – listed by sequenced time period July 2020

Delivery S1 S2 S3 BAU Period

Lincolnshire and the Sheffield City Region Lincolnshire and the Sheffield City Region Lincolnshire and the Sheffield City Region and the North West and the North West and the North West • Skelmersdale Rail Link • Skelmersdale Rail Link • Skelmersdale Rail Link • New & Upgraded Stations in the Mersey • New & Upgraded Stations in the Mersey • New & Upgraded Stations in the Mersey Dee area (Shotton, Deeside Park, Dee area (Shotton, Deeside Park, Dee area (Shotton, Deeside Park, Broughton) Broughton) Broughton) SOP 2027- • Newcastle to Carlisle () - • M6 Junctions 16 to 19 corridor 2033 ‘Edge’ route upgrade and journey time improvements Schemes improvements • M6 Junction 26 to 32 Improvements • York to Hull (service improvements) • A194(M) Whitemare Pool Junction • New/upgraded route around the North of Improvements Barnsley and Doncaster Districts or along • A19 North of Newcastle Junctions (Part) the A6195/ A635 corridor comprising: A19 junction and on-line • Fixed infrastructure links to Liverpool improvements between Killingworth John Lennon Airport interchange and Coast Road/Silverlink • Knutsford to Manchester Airport interchange (Western Link) • A69 De-Trunking / A689 Trunking to • Rail connection and station for Doncaster improve the route function Sheffield Airport (DSA) • A69 route improvement, climbing lanes • East Coast Main Line spur to Newcastle and targeted junction improvements Airport (including the B6351 Hexham west • Parkside enhanced freight connectivity junction) • West Coast Main Line freight capacity • M62 Junctions 5 to 10 enhancements • New/upgraded route between the M65 • Enhanced public transport links to and Skipton/A629/A650 Fleetwood • M62 Junction 32 to 30 westbound • Journey time improvements Preston - • New/upgraded route around the North of Blackpool North Barnsley and Doncaster Districts or along • Barrow-in-Furness to Lancaster (Furness the A6195/ A635 corridor Line) - journey time and reliability • Fixed infrastructure links to Liverpool improvements John Lennon Airport • Rail/ Metro integration improvements • M57 Junctions 4 and 5 within to include routes, • Switch Island (M57/M58/A5036) stations and timetabling • West Coast Main Line freight capacity • South of Tyne rail-based Park-and-Ride enhancements at Follingsby • Rail/ Metro integration improvements • Bishop Auckland to Saltburn, via within Tyne and Wear to include routes, Darlington and Middlesbrough (Bishop and stations and timetabling Saltburn Lines) – service frequency and • A164 dualling (A63 to B1232) journey time improvements • M56 Chester Box Improvements • Hull to Scarborough (journey time and • M66 Improvements frequency improvements • M60/M56 interchange improvements • Extend services to • A663 Broadway / M60 Junctions 21 Liverpool Central via Wapping Tunnel re- Upgrade opening • Lancaster - Morecambe additional • Chester – Warrington Bank Quay services (journey time improvements) • M1 Online Improvements Junction 43 to • Lancaster - Morecambe additional Hook Moor services • M62 Junction 24a • Phase 2 – medium term: Leeds City • North Kirklees Orbital Route Region further programme of works • A638 improvements – Wakefield to the delivering capacity to enable forecast A1(M)) growth, as well as reliability • A61 Corridor Improvements improvements, and supporting the • A57 South Anston bypass introduction of HS2 & NPR • Sheffield to Lincoln (journey time, frequency and capacity improvements) • Huddersfield to Sheffield (Penistone Line) - journey time, frequency and capacity improvements SOP Post • to Wigan (journey time • Southport to Wigan (journey time • Southport to Wigan (journey time 2033 ‘Fixed’ improvements) improvements) improvements) Window • East Coast Main Line (journey time and • East Coast Main Line (journey time and • East Coast Main Line (journey time and Schemes reliability improvements) - Doncaster to reliability improvements) - Doncaster to reliability improvements) - Doncaster to York York York • Crewe to Preston additional calls • Crewe to Preston additional calls • Crewe to Preston additional calls (additional path between Winsford and (additional path between Winsford and (additional path between Winsford and Preston) Preston) Preston) • M6 Junctions 19 to 21A improvements • M6 Junctions 19 to 21A improvements • M6 Junctions 19 to 21A improvements

Qualitative Sequencing Investment Strategies – listed by sequenced time period July 2020

Delivery S1 S2 S3 BAU Period

• A1 North of Ellingham to Edinburgh • A1 North of Ellingham to Edinburgh • A1 North of Ellingham to Edinburgh Dualling (cross-border) Dualling (cross-border) Dualling (cross-border) • A1 dualling and capacity improvements • A1 dualling and capacity improvements • A1 dualling and capacity improvements in the North East (A1(M) in the North East (A1(M) in the North East (A1(M) • Barton to Chester-le-Street widening) • Barton to Chester-le-Street widening) • Barton to Chester-le-Street widening) • North East new strategic river crossing • North East new strategic river crossing • North East new strategic river crossing • A19/B1404 Seaton Lane to A19/A183 • A19/B1404 Seaton Lane to A19/A183 • A19/B1404 Seaton Lane to A19/A183 Chester Road Chester Road Chester Road • Preston to Sheffield (journey time • Preston to Sheffield (journey time • Preston to Sheffield (journey time improvements) improvements) improvements) • Liverpool to Preston via Wigan (journey • Liverpool to Preston via Wigan (journey • Liverpool to Preston via Wigan (journey time and service improvements) time and service improvements) time and service improvements) • New Manchester Airport - Nottingham via • New Manchester Airport - Nottingham via • New Manchester Airport - Nottingham via Crewe and Derby limited stop service, Crewe and Derby limited stop service, Crewe and Derby limited stop service, increasing Crewe-Derby frequency from 1 increasing Crewe-Derby frequency from 1 increasing Crewe-Derby frequency from 1 to 2tph to 2tph to 2tph • A689 M6 to Carlisle Lake District Airport • A689 M6 to Carlisle Lake District Airport • A689 M6 to Carlisle Lake District Airport capacity improvements and improved M6 capacity improvements and improved M6 capacity improvements and improved M6 connectivity connectivity connectivity • A69-A696-A1 link to form a NW ring road • A69-A696-A1 link to form a NW ring road • A69-A696-A1 link to form a NW ring road of Newcastle via the airport of Newcastle via the airport of Newcastle via the airport • A66 to A1 New Link and Junction north • A66 to A1 New Link and Junction north • A66 to A1 New Link and Junction north of Scotch Corner of Scotch Corner of Scotch Corner • M65 improvements • M65 improvements • M65 improvements • New/upgraded route between • New/upgraded route between • New/upgraded route between A629/A650 and the A1(M)/M1 A629/A650 and the A1(M)/M1 A629/A650 and the A1(M)/M1 • A64 Technology Improvements - A1(M) • A64 Technology Improvements - A1(M) • A64 Technology Improvements - A1(M) Bramham to A1237 Hopgrove Bramham to A1237 Hopgrove Bramham to A1237 Hopgrove • A64 Crambeck to Scarborough • A64 Crambeck to Scarborough • A64 Crambeck to Scarborough improvements improvements improvements • A1079 York to Hull improvements • A1079 York to Hull improvements • A1079 York to Hull improvements • A1 to A19 link • A1 to A19 link • A1 to A19 link • A19 to M18 link • A19 to M18 link • A19 to M18 link • A1 to M1 link, comprising A1 to HS2 link • A1 to M1 link, comprising A1 to HS2 link • A1 to M1 link, comprising A1 to HS2 link from Redhouse and M1 to HS2 link from Redhouse and M1 to HS2 link from Redhouse and M1 to HS2 link • M1 to M18 link • M1 to M18 link • M1 to M18 link • M18 Junctions 2 to 5 (and online • M18 Junctions 2 to 5 (and online • M18 Junctions 2 to 5 (and online improvements to M18 Jn 2) improvements to M18 Jn 2) improvements to M18 Jn 2) • Windermere and Barrow to Manchester • Windermere and Barrow to Manchester • Windermere and Barrow to Manchester Airport (frequency and journey time Airport (frequency and journey time Airport (frequency and journey time improvements) improvements) improvements) • A556 Corridor Improvements • A556 Corridor Improvements • A556 Corridor Improvements • A63 Relief Route • A63 Relief Route • A63 Relief Route • A63 technology improvements • A63 technology improvements • A63 technology improvements • A180 • A180 • A180 • M18 Junction 4 connection to Doncaster • M18 Junction 4 connection to Doncaster • M18 Junction 4 connection to Doncaster Sheffield Airport Sheffield Airport Sheffield Airport • North East rail freight enhancements • North East rail freight enhancements • North East rail freight enhancements (passing loops and port connections) (passing loops and port connections) (passing loops and port connections) • A585 corridor improvements (M55 to • A585 corridor improvements (M55 to • A585 corridor improvements (M55 to Fleetwood) Fleetwood) Fleetwood) • New Ribble Crossing • New Ribble Crossing • New Ribble Crossing • Windermere to West Yorkshire (service • Windermere to West Yorkshire (service • Windermere to West Yorkshire (service improvements) improvements) improvements) • A590 South Cumbria (dualling and wider • A590 South Cumbria (dualling and wider • A590 South Cumbria (dualling and wider capacity, journey time and resilience capacity, journey time and resilience capacity, journey time and resilience improvements) improvements) improvements) • A590 Ulverston bypass • A590 Ulverston bypass • A590 Ulverston bypass • Reinstatement of passenger services on • Reinstatement of passenger services on • Reinstatement of passenger services on Stillington Line (Stockton – Ferryhill) Stillington Line (Stockton – Ferryhill) Stillington Line (Stockton – Ferryhill) • A580 Dual Carriageway and Some Grade • A580 Dual Carriageway and Some Grade • A580 Dual Carriageway and Some Grade Separation Separation Separation • M57 improvements • M57 improvements • M57 improvements • Birchwood park and ride • Birchwood park and ride • Birchwood park and ride • A500 dual carriageway with grade • A500 dual carriageway with grade • A500 dual carriageway with grade separated junctions separated junctions separated junctions • A34 (potential expressway) • A34 (potential expressway) • A34 (potential expressway) • Nantwich Southern Relief Road • Nantwich Southern Relief Road • Nantwich Southern Relief Road • Heavy rail capacity and journey time • Heavy rail capacity and journey time • Heavy rail capacity and journey time improvements in the South Manchester improvements in the South Manchester improvements in the South Manchester area and on the Wilmslow and Buxton lines area and on the Wilmslow and Buxton lines area and on the Wilmslow and Buxton lines

Qualitative Sequencing Investment Strategies – listed by sequenced time period July 2020

Delivery S1 S2 S3 BAU Period

• M62-Carrington-M60 link • M62-Carrington-M60 link • M62-Carrington-M60 link • A6 Disley and High Lane bypass • A6 Disley and High Lane bypass • A6 Disley and High Lane bypass • M6 Junction 25 slip roads • M6 Junction 25 slip roads • M6 Junction 25 slip roads • Rossendale to Manchester public • Rossendale to Manchester public • Rossendale to Manchester public transport connectivity transport connectivity transport connectivity • Clitheroe to Manchester Victoria via • Clitheroe to Manchester Victoria via • Clitheroe to Manchester Victoria via Blackburn and Bolton (journey time and Blackburn and Bolton (journey time and Blackburn and Bolton (journey time and service improvements) service improvements) service improvements) • A59 corridor improvements (Liverpool to • A59 corridor improvements (Liverpool to • A59 corridor improvements (Liverpool to Preston) Preston) Preston) • M58 & M6 Interchange • M58 & M6 Interchange • M58 & M6 Interchange • A56 corridor improvements (M65 to • A56 corridor improvements (M65 to • A56 corridor improvements (M65 to M66) M66) M66) • Phase 3 – long term: Leeds City Region • Phase 3 – long term: Leeds City Region • Phase 3 – long term: Leeds City Region additional works improving the capacity of additional works improving the capacity of additional works improving the capacity of the network to enable forecast growth, the network to enable forecast growth, the network to enable forecast growth, and realising the introduction of HS2 and and realising the introduction of HS2 and and realising the introduction of HS2 and NPR, enabling their benefits to be spread NPR, enabling their benefits to be spread NPR, enabling their benefits to be spread and maximised and maximised and maximised • Rotherham to Leeds (frequency • Rotherham to Leeds (frequency • Rotherham to Leeds (frequency improvements) improvements) improvements) • M1 Junction 37a • M1 Junction 37a • M1 Junction 37a • Sheffield – Nottingham (journey time • Sheffield – Nottingham (journey time • Sheffield – Nottingham (journey time improvements) improvements) improvements) • A534 route upgrade • A534 route upgrade • A534 route upgrade • A51 Improvements (Nantwich to Chester • A51 Improvements (Nantwich to Chester • A51 Improvements (Nantwich to Chester – potential expressway) – potential expressway) – potential expressway) • A54 Corridor Improvements (M6 to • A54 Corridor Improvements (M6 to • A54 Corridor Improvements (M6 to Chester) Chester) Chester) • A15 improvements (M180 to A46 Lincoln • A15 improvements (M180 to A46 Lincoln • A15 improvements (M180 to A46 Lincoln Bypass) Bypass) Bypass) • A1 improvements (south of Blyth) • A1 improvements (south of Blyth) • A1 improvements (south of Blyth) SOP Post • M6 Junctions 16 to 19 corridor • Newcastle to Carlisle (Tyne Valley Line) - • M6 Junctions 16 to 19 corridor 2033 ‘Edge’ improvements route upgrade and journey time improvements Schemes • M6 Junction 26 to 32 Improvements improvements • M6 Junction 26 to 32 Improvements • A194(M) Whitemare Pool Junction • York to Hull (service improvements) • A194(M) Whitemare Pool Junction Improvements • Knutsford to Manchester Airport Improvements • A19 North of Newcastle Junctions (Part) (Western Link) • A19 North of Newcastle Junctions (Part) comprising: A19 junction and on-line • Rail connection and station for Doncaster comprising: A19 junction and on-line improvements between Killingworth Sheffield Airport (DSA) improvements between Killingworth interchange and Coast Road/Silverlink • East Coast Main Line spur to Newcastle interchange and Coast Road/Silverlink interchange Airport interchange • A69 De-Trunking / A689 Trunking to • Parkside enhanced freight connectivity • Newcastle to Carlisle (Tyne Valley Line) - improve the route function • Enhanced public transport links to route upgrade and journey time • A69 route improvement, climbing lanes Fleetwood improvements and targeted junction improvements • Journey time improvements Preston - • York to Hull (service improvements) (including the B6351 Hexham west Blackpool North • New/upgraded route around the North of junction) • Barrow-in-Furness to Lancaster (Furness Barnsley and Doncaster Districts or along • M62 Junctions 5 to 10 Line) - journey time and reliability the A6195/ A635 corridor • New/upgraded route between the M65 improvements • A69 De-Trunking / A689 Trunking to and Skipton/A629/A650 • South of Tyne rail-based Park-and-Ride improve the route function • M62 Junction 32 to 30 westbound at Follingsby • A69 route improvement, climbing lanes • M57 Junctions 4 and 5 • Bishop Auckland to Saltburn, via and targeted junction improvements • Switch Island (M57/M58/A5036) Darlington and Middlesbrough (Bishop and (including the B6351 Hexham west • A164 dualling (A63 to B1232) Saltburn Lines) – service frequency and junction) • M56 Chester Box Improvements journey time improvements • M62 Junctions 5 to 10 • M66 Improvements • Hull to Scarborough (journey time and • New/upgraded route between the M65 • M60/M56 interchange improvements frequency improvements and Skipton/A629/A650 • A663 Broadway / M60 Junctions 21 • Extend Merseyrail City Line services to • M62 Junction 32 to 30 westbound Upgrade Liverpool Central via Wapping Tunnel re- • Fixed infrastructure links to Liverpool • M1 Online Improvements Junction 43 to opening John Lennon Airport Hook Moor • Chester – Warrington Bank Quay • Knutsford to Manchester Airport • M62 Junction 24a (journey time improvements) (Western Link) • North Kirklees Orbital Route • Phase 2 – medium term: Leeds City • Rail connection and station for Doncaster • A638 improvements – Wakefield to the Region further programme of works Sheffield Airport (DSA) A1(M)) delivering capacity to enable forecast • East Coast Main Line spur to Newcastle • A61 Corridor Improvements growth, as well as reliability Airport • A57 South Anston bypass improvements, and supporting the • M57 Junctions 4 and 5 introduction of HS2 & NPR • Switch Island (M57/M58/A5036) • Sheffield to Lincoln (journey time, • Parkside enhanced freight connectivity frequency and capacity improvements)

Qualitative Sequencing Investment Strategies – listed by sequenced time period July 2020

Delivery S1 S2 S3 BAU Period

• Huddersfield to Sheffield (Penistone Line) • West Coast Main Line freight capacity - journey time, frequency and capacity enhancements improvements • Enhanced public transport links to Fleetwood • Journey time improvements Preston - Blackpool North • Barrow-in-Furness to Lancaster (Furness Line) - journey time and reliability improvements • Rail/ Metro integration improvements within Tyne and Wear to include routes, stations and timetabling • South of Tyne rail-based Park-and-Ride at Follingsby • Bishop Auckland to Saltburn, via Darlington and Middlesbrough (Bishop and Saltburn Lines) – service frequency and journey time improvements • Hull to Scarborough (journey time and frequency improvements • A164 dualling (A63 to B1232) • Extend Merseyrail City Line services to Liverpool Central via Wapping Tunnel re- opening • Chester – Warrington Bank Quay (journey time improvements) • M56 Chester Box Improvements • M66 Improvements • M60/M56 interchange improvements • A663 Broadway / M60 Junctions 21 Upgrade • Lancaster - Morecambe additional services • Phase 2 – medium term: Leeds City Region further programme of works delivering capacity to enable forecast growth, as well as reliability improvements, and supporting the introduction of HS2 & NPR • M1 Online Improvements Junction 43 to Hook Moor • M62 Junction 24a • North Kirklees Orbital Route • A638 improvements – Wakefield to the A1(M)) • Sheffield to Lincoln (journey time, frequency and capacity improvements) • Huddersfield to Sheffield (Penistone Line) - journey time, frequency and capacity improvements • A61 Corridor Improvements • A57 South Anston bypass