For discussion on 23 April 2012

Legislative Council Panel on Environmental Affairs

272DS – Port Shelter sewerage, stage 2 273DS – Port Shelter sewerage, stage 3 331DS – Outlying Islands sewerage, stage 2 – South Lantau sewerage works

PURPOSE

This paper seeks Members’ support for our proposals to – (a) upgrade part of 272DS – Port Shelter sewerage, stage 2 to Category A at an estimated cost of $107.1 million; (b) upgrade part of 273DS – Port Shelter sewerage, stage 3 to Category A at an estimated cost of $183.5 million; and (c) upgrade part of 331DS – Outlying Islands sewerage, stage 2 – South Lantau sewerage works to Category A at an estimated cost of $30.0 million in money-of-the-day (MOD) prices.

PROJECT SCOPE

272DS – Port Shelter sewerage, stage 2

2. The part of 272DS that we propose to upgrade to Category A comprises the construction of – (a) about 9.5 kilometres (km) of sewers for eight unsewered areas, namely Kap Pin Long, Nam Shan, Pak Kong, San Uk, Sha Kok Mei, Tai Ping Village, Tai Shui Tseng and Wo Tong Kong; and (b) ancillary works. A site plan showing the proposed works is at Enclosure 1. 273DS – Port Shelter sewerage, stage 3

3. The part of 273DS that we propose to upgrade to Category A comprises the construction of – (a) about 3.3 km of sewers for three unsewered areas, namely Lung Wo Tsuen, Pik Shui Sun Tsuen and the vicinity of Fei Ngo Shan Road; (b) about 3.6 km gravity trunk sewers from Shun Chi Street to Road and around Pik Shui Sun Tsuen; (c) one sewage pumping station (SPS) at Pik Shui Sun Tsuen; (d) about 900 metres (m) of twin rising mains at Pik Shui Sun Tsuen (in association with construction of the SPS in (c) above) and along sections of Road near Tseng Lan Shue and Pak Shek Wo; and (e) ancillary works.

A site plan showing the proposed works is at Enclosure 2.

331DS – Outlying Islands sewerage, stage 2 – South Lantau sewerage works

4. The part of 331DS that we propose to upgrade to Category A comprises – (a) a consultancy for implementation of sewerage works in South Lantau that includes – (i) detailed design of sewers, treatment works and associated facilities for the collection, conveyance, treatment and disposal of sewage from six unsewered areas, namely Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin; (ii) impact assessment on drainage, geotechnical, waterworks, traffic and other aspects necessary for completion of the detailed design; (iii) preparation of tender documents and assessment of tenders; (iv) supervision of the site investigation, surveys and laboratory testing in (b) below; and (b) site investigation, surveys and laboratory testing in support

– 2 – of the detailed design work and impact assessment. A site plan showing the project boundary and locations of the abovementioned unsewered areas is at Enclosure 3.

JUSTIFICATIONS

272DS – Port Shelter sewerage, stage 2 273DS – Port Shelter sewerage, stage 3

5. At present, sewage from a number of village areas in the Port Shelter catchment is often treated and disposed of by means of private on-site treatment facilities (such as septic tanks and soakaway (STS) systems). These facilities might however become ineffective in removing pollutants due to their proximity to watercourses 1 or inadequate maintenance. Sewage from these areas has therefore been identified as a source of water pollution to the receiving waters of Port Shelter.

6. The aforesaid situation will persist unless sewerage infrastructure is made available to collect and treat sewage from these areas properly. The Environmental Protection Department has formulated as a long-term measure a programme under the Port Shelter Sewerage Master Plan to expand the public sewerage in the Port Shelter catchment. The programme is divided into three stages for implementation. Stage 1 has been completed whereas Stages 2 and 3 are being implemented in phases.

7. We now propose to upgrade part of 272DS and 273DS to Category A for further implementation of the remaining works under Stages 2 and 3 of Port Shelter sewerage respectively. The proposed works under 272DS aim to provide public sewerage for eight unsewered areas around centre, namely Kap Pin Long, Nam Shan, Pak Kong, San Uk, Sha Kok Mei, Tai Ping Tsuen, Tai Shui Tseng and Wo Tong Kong. The sewers to be laid under this project will be connected to the adjacent gravity trunk sewers. On the other hand, the proposed sewerage works under 273DS cover three other unsewered areas, namely Lung Wo Tsuen, Pik Shui Sun Tsuen and the vicinity of Fei Ngo Shan

1 STS systems operate by allowing the effluent to percolate through gravels whereby pollutants are removed in a natural manner. However, if a STS system is located in an area where the ground water table is high, such as an area in proximity to watercourses, it will not function properly due to ineffective percolation.

– 3 – Road. The proposed works in Pik Shui Sun Tsuen also entails the construction of one SPS for overcoming the topographical constraints along the sewer alignment. Gravity trunk sewers and twin rising mains will also be laid to connect these areas to the existing gravity trunk sewers as well as to cater for the provision of public sewerage for areas including Pak Shek Wo, Pik Uk Au and Tseng Lan Shue in subsequent phases of Stage 3 works.

8. Upon completion of the proposed works under 272DS and 273DS, sewage collected from the areas to be sewered will be diverted away to the Sai Kung sewage treatment works (STW), the Tseung Kwan O preliminary treatment works (PTW) and the PTW for proper treatment and disposal. This will minimise the release of pollutants into the environment and bring about sustainable improvement to the water quality of Port Shelter.

9. Subject to funding approval of the Finance Committee (FC), Drainage Services Department (DSD) plans to commence construction of the proposed works under 272DS and 273DS in August 2012 for completion by August 2016. We will retain the remainders of 272DS and 273DS in Category B, which involve construction of about 30 km and 12 km of sewers for other unsewered areas in the Port Shelter catchment respectively. Funding for the remainders will be sought at a later stage after completion of the design and preparatory work.

331DS – Outlying Islands sewerage, stage 2 – South Lantau sewerage works

10. There is at present no public sewerage in South Lantau and sewage is often treated and disposed of by means of private on-site treatment facilities. Similar to the situation at unsewered areas within the Port Shelter catchment, sewage generated in South Lantau has been identified as a source of water pollution to our southern waters. The discharge also affects the water quality at four public beaches on the southern coast of Lantau, namely , , and .

11. In view of the above, public sewerage should be made available in South Lantau as a long-term measure to better protect the water quality of our southern waters and at the four public beaches. In 2008, a review of the sewerage scheme for South Lantau was completed and it recommended the provision of public sewerage for six unsewered areas, namely Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and

– 4 – Ham Tin. For the collection, conveyance, treatment and disposal of sewage generated from these areas, a schematic design comprising one secondary STW, six SPSs, one submarine outfall, gravity trunk sewers and rising mains along South Lantau Road as well as sewers within the unsewered areas mentioned above was also included in the review.

12. Based on the schematic design, DSD is conducting an assessment on the environmental implications of the proposed sewerage in South Lantau. DSD expects to complete the assessment in mid-2012 and seeks to commence the detailed design of the works thereafter. The impact on drainage, geotechnical, waterworks, traffic and other relevant aspects will be assessed whereas site investigation will also be carried out in support of such preparatory work.

13. Owing to insufficient in-house resources, DSD has proposed to employ consultants to undertake the preparatory work outlined in paragraph 4(a) above. Subject to funding approval of the FC, DSD plans to commence the proposed consultancy and site investigation in September 2012 for completion by September 2015. We will retain the remainder of 331DS, i.e. the construction works under this project, in Category B. Funding of the remainder of 331DS will be sought at a later stage after completion of the preparatory work to be carried out under the proposed consultancy.

FINANCIAL IMPLICATIONS

14. We estimate the capital cost of the proposed works under 272DS and 273DS and the proposed consultancy and site investigation under 331DS to be $320.6 million in MOD prices made up as follow –

$ million (MOD) (a) 272DS - Port Shelter sewerage, stage 2 107.1 (part) (b) 273DS - Port Shelter sewerage, stage 3 183.5 (part) (c) 331DS - Outlying Islands sewerage, 30.0 stage 2 – South Lantau sewerage works (part) Total 320.6

– 5 – 15. We estimate that implementation of the proposed works under 272DS and 273DS and the proposed consultancy and site investigation under 331DS will create 39 jobs (32 for labourers and another 7 for professional / technical staff), 63 jobs (51 for labourers and another 12 for professional / technical staff) and 15 jobs (5 for labourers and another 10 for professional / technical staff) respectively, providing a total employment of 4-730 man-months. Detailed breakdown is as follows –

( A ) ( B ) ( A ) + ( B ) ( C )

PWP item Numbers of jobs to be Total Employment no. created for number of in professional / labourers jobs created man-months technical staff

272DS (part) 32 7 39 1 680 273DS (part) 51 12 63 2 690 331DS (part) 5 10 15 360

Total 88 29 117 4 730

PUBLIC CONSULTATION

272DS – Port Shelter sewerage, stage 2 273DS – Port Shelter sewerage, stage 3

16. We consulted Sai Kung Rural Committee on the proposed works under 272DS on 26 September 2001 and 25 October 2007. We also consulted the Housing and Environmental Hygiene Committee under Council on 15 April 2008. Both committees supported the proposed works under 272DS.

17. We consulted Rural Committee on the proposed works under 273DS on 15 October 2001 and provided the Committee with updated information on the project in September 2007. The Housing and Environmental Hygiene Committee under Sai Kung District Council was also consulted on 15 April 2008. Both of them supported the proposed works under 273DS. In addition, we consulted the Environment and Hygiene Committee (EHC) under Kwun Tong District

– 6 – Council on 8 July 2009. Members of EHC were in general supportive of the proposed works under 273DS.

18. We gazetted the proposed works under 272DS in accordance with the Water Pollution Control (Sewerage) Regulation (WPC(S)R) under three schemes between December 2008 and July 2010. No objection was received and all the three schemes were subsequently authorised between May 2009 and November 2010.

19. We gazetted the proposed works under 273DS in accordance with the WPC(S)R under four schemes between August 2009 and July 2011. For the scheme that covers the proposed gravity trunk sewers and twin rising mains along (Tseng Lan Shue Section), one objection concerning the impact of the proposed works on certain existing installations (including a well, two pump chambers, some chain-link fence and gate) and fruit trees near a piece of land was received. We have repeatedly explained to the objectors that since the piece of land concerned is located over 50 m from the proposed works area, the proposed works would not pose the purported adverse impact. The objection nevertheless remained unresolved and the Chief Executive-in-Council authorised the scheme without modification on 13 March 2012. The notice of authorisation was gazetted on 13 April 2012. No objection was received in respect of the other three schemes and the proposed works were authorised between November 2009 and November 2011.

331DS – Outlying Islands sewerage, stage 2 – South Lantau sewerage works

20. We consulted South Lantao Rural Committee and the Tourism, Agriculture, Fisheries and Environmental Hygiene Committee under Council on 3 August 2010 and 18 July 2011 respectively. Both committees supported the provision of sewerage in South Lantau in principle.

HERITAGE IMPLICATIONS

21. Both the proposed works under 272DS and 273DS and the proposed consultancy and site investigation under 331DS will not affect any heritage site, i.e. all declared monuments, proposed monuments, graded historic sites/buildings, sites of archaeological interest and

– 7 – Government historic sites identified by the Antiquities and Monuments Office.

LAND ACQUISITION

22. We have to resume two private agricultural lots and part of five private agricultural lots (about 279 square metres in total) for carrying out the proposed works under 272DS. The land resumption and clearance will not affect any households or structures. Both the proposed works under 273DS and the proposed consultancy and site investigation under 331DS do not require any land acquisition.

ENVIRONMENTAL IMPLICATIONS

272DS – Port Shelter sewerage, stage 2 273DS – Port Shelter sewerage, stage 3

23. The proposed sewerage works at Pik Shui Sun Tsuen under 273DS constitute a designated project under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) is required for its construction and operation. Having regard to the project profile prepared and submitted by DSD, the Director of Environmental Protection was satisfied that the environmental impacts of the works concerned could meet the requirements of the Technical Memorandum on Environmental Impact Assessment Process. With the consent of the Secretary for the Environment, the permission to apply directly for an EP was granted on 23 November 2011 and the EP was issued on 20 December 2011. DSD shall implement the mitigation measures as set out in the EP and comply with the conditions therein accordingly.

24. As regards the proposed works under 272DS and other proposed works under 273DS, they are not designated projects under the EIAO. DSD completed an Environmental Study that covers these sewerage works in December 2010 and it was concluded that, with the implementation of appropriate mitigation measures, these sewerage works would not have long-term adverse environmental impacts.

25. For short-term environmental impacts during construction, we will control noise, dust and site run-off to levels within established standards and guidelines through implementation of environmental

– 8 – mitigation measures, such as the use of silenced construction equipment and noise barriers to reduce noise generation, water-spraying to reduce emission of fugitive dust, and proper treatment of site run-off before discharge. We will also carry out regular site inspections to ensure that these recommended mitigation measures and good site practices will be properly implemented on site. We have included sums of $1.7 million and $3.1 million2 (in September 2011 prices) in the project estimates of the proposed works under 272DS and 273DS respectively for implementation of the necessary environmental mitigation measures.

26. At the planning and design stages, we have considered ways to reduce the generation of construction waste where possible. For example, in addition to the need for meeting the hydraulic and traffic requirements, we have also designed the alignment of the proposed sewers in such a manner that excavation and demolition of existing structures will be minimised. In addition, we will require the contractors to reuse inert construction waste (e.g. excavated soil) on site or in other suitable construction sites as far as possible in order to minimise the disposal of inert construction waste at public fill reception facilities (PFRF)3. We will encourage the contractors to maximise the use of recycled or recyclable inert construction waste, as well as the use of non-timber formwork to further minimise the generation of construction waste.

27. At the construction stage, we will require the contractors to submit for approval a plan setting out the waste management measures, which will include appropriate mitigation means to avoid, reduce, reuse and recycle inert construction waste. We will ensure that the day-to-day operations on site comply with the approved plan. We will require the contractors to separate the inert portion from non-inert construction waste on site for disposal at appropriate facilities. We will control the disposal of inert construction waste and non-inert construction waste at PFRF and landfills respectively through a trip-ticket system.

28. We estimate that the proposed works will generate about 85-800 tonnes of construction waste in total (55-770 tonnes and 30-030 tonnes for the proposed works under 272DS and 273DS respectively).

2 This amount also covers the cost of employing an independent checker to audit the implementation of mitigation measures in relation to the proposed works at Pik Shui Sun Tsuen for fulfilling the relevant condition under the EP. 3 PFRF are specified in Schedule 4 of the Waste Disposal (Charges for Disposal of Construction Waste) Regulation. Disposal of inert construction waste in PFRF requires a licence issued by the Director of Civil Engineering and Development.

– 9 – Of these, we will reuse 64-650 tonnes (75%) of inert construction waste on site and deliver another 20-400 tonnes (24%) to PFRF for subsequent reuse. We will dispose of the remaining 750 tonnes (1%) of non-inert construction waste at landfills. The total costs for accommodating construction waste at PFRF and landfill sites are estimated to be about $0.42 million and $0.22 million for the proposed works under 272DS and 273DS respectively (based on a unit cost of $27 per tonne for disposal at PFRF and $125 per tonne4 at landfills).

331DS – Outlying Islands sewerage, stage 2 – South Lantau sewerage works

29. The proposed consultancy and site investigation under 331DS is not a designated project under the EIAO. The proposed consultancy will not cause any adverse environmental impacts. We shall implement suitable mitigation measures to control any short-term environmental impacts arising from site investigation and surveys.

30. The site investigation works will only generate an insignificant quantity of construction waste. We will require the consultants to fully consider measures to minimise the generation of construction waste and to reuse or recycle such waste as much as possible when carrying out site investigation.

ADVICE SOUGHT

31. Members are invited to support our proposals for upgrading the proposed works under 272DS and 273DS and the proposed consultancy and site investigation under 331DS to Category A. Subject to Members’ advice, we plan to submit our proposals for endorsement by the Public Works Subcommittee in May 2012 with a view to seeking FC’s funding approval in June 2012.

Environmental Protection Department Drainage Services Department April 2012

4 This estimate has taken into account the cost for developing, operating and restoring the landfills after they are filled and the aftercare required. It does not include the land opportunity cost for existing landfill sites (which is estimated at $90 per cubic metre), nor the cost to provide new landfills (which is likely to be more expensive) when the existing ones are filled.

– 10 – “ ENCLOSURE 1 21.2 116.1 51.6 9.5

402.7 63.5

68.7

60.3

76.5

¶¸ 118.6 91.2

136.8 Wong Chuk Wan 58.5 104.6 44.7 55.1 81.7 72.0 71.8 27.5 52.1 391.5 F¨¤ 828 000 N 38.1 50.1 Sha Kok Mei 34.5 22.6

42.9 51.6 6.8 38.6 29.9 371.8 è¦ 66.9 38.7 61.8 49.7 SAI KUNG 37.4

26.3 _¥ s· p 23.1 30.6 Pak Kong x San Uk 398.6 28.5 20.5 102.5

14.7 19.7 j¤F ¥ 40.9 · 14.7 61.1 Jetty 22.4 391.0 Tai Chung Hau 33.5 Wo Tong Kong 14.9 14.4 5

67.6 54.1 54.5 10.9 ¥© 14.5 Rocky Area 50.3 n« 11.3 13.3

ß⁄ Nam26.6 Shan 5.7 11.1 PORT SHELTER 40.8 17.9 58.6 12.9

85.8

4.2

31.1

50.3 40.8 5.6 F¨¤ 10.8 81.3

50 43.6 13.7 827 500 N j⁄ Sha15.8 Kok Mei ƒm LOCATION PLAN 7.4 11.3 SCALE 1 : 100 000 Tai Shui Tseng 21.3 ñ¤ 44.4 5.3 30.6 78.9 5.0

6.7 I¬u ˇ„ 121.4 15.0

7.5 LEGEND: 47.4 5.6

10.6

5.3

124.8 217.2 6.3 –Ø»ƒ{†‡ƒ”“ 5.6 85.7

¥ 3.7 CONNECT TO EXISTING 76.5 53.6 6.1

5.6 4.6 GRAVITY TRUNK SEWERS 43.2 Kap Pin Long3.6 34.7 I¬u Works in 5.4 progress «”“m¶ł§ˆƒ 32.2 195.7 90.3 4.3 110.0 ⁄D¥— 36.4 5.4 PROPOSED AREA FOR 50.7 IMPLEMENTATION OF 4.5 VILLAGE SEWERAGE WORKS 4.2 97.1 3.8 57.1 76.3 4.4

20.0 94.1 70.5 91.6 p 827 000 N 88.7 3.8

100.6 88.4 4.5 33.4 59.1 63.1 4.3

3.9 3.7 ⁄› p 19.5 X½ 14.2 6.1 X½ Pier Tai Ping Village Pier 146.1

107.0 73.3

168.3 4.1

51.5 _¥ 28.2 68.7 10.4 7.2 82.9

105.8 29.5 3.9 4.8 è¦ 91.0 63.2 Pak Kong 4.0

88.9 6.2

56.8 23.8 5.9 105.8 SAI KUNG

95.1 40.2

23.5 99.1 o´ 4.0 X½ Filter Bed 29.6 X½ 5.7 Pier Pier

36.8 5.8 26.8 90.2

21.4 36.8 29.6

17.7 p 31.8 23.5 27.4 † Slipway 26.8 X½ X½ p 18.8 12.9 Pier 106.3 Pier X½ X½ Pier 826 500 N 27.6 Pier 30.0 5.1 27.3 63.5 0 100 200 300 400 500 m

34.8 17.1 44.7

24.0 15.0

22.2 68.2 1 : 7500 SCALE BAR 17.4 34.6 48.5 27.0 33.3 48.1 111.1

13.9

78.4 44.7 53.0 38.2 35.4 5.0

18.6 24.8 47.5 43.6

C. C. CHAN 05 MAR 2012 DSP/272DS1/11011 AS SHOWN Ir S. P. CHOW 05 MAR 2012 u⁄¨p›”„¶¥˜† 272DS „‚ - Ir C. K. WONG 05 MAR 2012 PWP ITEM NO.272DS - PORT SHELTER SEWERAGE, STAGE 2

Col_pdf_cswp_v8.plt PLOTPEN.TBL c:\temp\dsd_pw\dms12003\DSP_272DS1_11011.dgn “ ENCLOSURE 2

ß⁄ ( TA SHE YAU AU ) || 5.6 WEST ´¥®Ä[ ~¨w NGAU AU SHAN ¥ 10.2 ƒ« _ÂY MONG Lo Shue SHEK NGA PUI HOI SING WAN 29 TUEN TAU CHAU 23.0 Tin ł¥ 103.3 CHAU TSAI 91.8 Kei Pik Shan ¼¿| 30.0 6 ´¥®Ä[ Tsiu Hang 385 36.0 Hau 103.7 “T 18.7 yƒ 53.3 Fu Yung Pei QÆÐ TSIM MEI FUNG C'¥› C¹¥¸± YIM TIN PAI Marina j¤£¸ KIU TSUI LONG MONG 44.7 Tai No COUNTRY PARK 30.0 Sheung Yeung KIU TSUI WAN 18.8 410.5 136 ⁄u Z› C fl Mau Tso Ngam 823 500 N ^±I Tso Tui Ha 132 Kong Pui Tsuen j¤ · m 5 Tai No ( KIU TSUI CHAU ) LO CHI PAI 12.8 [˘ 5 Kwun Yam Shan 80.2 KIU TAU 30 SHEK KWU 65.1 WAN ˇ„

¤bs⁄¥ ¶s 62.5 CÄY HAK SHAN TENG MAN TAU TUN EªÐ COUNTRY PARK 43.7 F¨ 22.1 [˘› Fªv SHA TSUI 45.1 Kwun Yam T­ j⁄ TUNG YEUNG SHAN ‹ Wang Che ƒŒ Mau Tat Shan Tsuen TATE'S CAIRN Kai Ham LO FU NGAM ( TAI LO SHAN ) Ð¥ LEGEND: 53.1 577 Tin Liu TATE'S RIDGE Qƒ ³x 41.4 TIU TSO NGAM ˜ j⁄ O·³ Ma Lam Wat HAP MUN BAY BEACH Police Post TATE'S PASS SHA TIN PASS ( TAI LO AU ) U¸Y 114 ( TSZ WAN SHAN ) SAM SING WAN HAP MUN BAY MAN TAU TSUI 82.5 22.7 ˦ Chuk Yuen 24.6 j¤¥ s·†

TAI NGAM j¤¥ LUNG NGAN YUEN TAU HAU TAI NGAM TSUI 544 ZÆ Man Wo ‚› Z û¸Å 65.3 Kau Tsin –Ø»ƒ{†‡ƒ”“ Fª û¤ Uk i±½ Ngau Liu CHEUNG KUNG ¥¤ 27.4 411 SHAN PAK MA TSUI j¤Å 105.4 58.5 EªÐPEAK Tai Lam û¤I CHAM TIN SHAN ¥P Wu Ngau Pui ]­ Tsz Ching Estate Shek Pok 121.0 Wo HEBE KNOLL 83.6 Wai Mau Tin 64.4 122 105.9 O·Á X¼ Tsz Man Estate Cemetery 30.5 t ¥¤ Ser Res n«s ( FEI NGO SHAN ) CAMPERS' BEACH CONNECT TO EXISTING GRAVITY 35.8 Nam Shan Mei ˦ PAK MA TSUI PAI 584 51.7 Chuk”⁄ Kok H¶ “‚ 123.1 MIDDLE HILL KWAI AU SHAN 121.5 61.0 õ¤® ʦá Crematorium ( ) 127.7 PAK FA LAM 312 Pik Uk Pik Shui TRUNK SEWERS HEBE KNOLL 42.6

I´s ¶p Wong Keng Estate Tsai 346 j¤ »§º´ £Ãs Sun Tsuen «⁄ TAI PAI Grand View King Shan Garden Court 603 PAK SHUI WUN §‹‰ 602 Chi Lin Nunnery Tseng Lan Shue ' R

t ß⁄ Ser Res ß⁄ NGAU CHI WAN »›·‹ «”“L£ 366.6 4 j¤H 75.3 ß⁄ƒ Ngau Chi Wan 6 m±i Village Choi Hung 67.2 Estate ˛ PORT SHELTER M m±³ D W' BAY ROAD Ping Shek Pik Uk Au Estate PROPOSED GRAVITY TRUNK SEWERS

t q¹v¼s 234.8 Ser «ˆƒ 153.5 ¶¶Q t Res Ser Res Estate ” RĹ´ 188 Richland ¥ …¿ Gardens Tsiu Lan W¥ R Shue Au Tau –~ 69.6 Kai Yip 71.0 j¤û TAI WONG ¶¶w 213.7 _Ä Estate Pak ShekN±x­ Wo WAN Shun On TAI Tseung Kwan O t Estate NGAU WU Village {‰ PROPOSED SEWAGE û¤Y Ser Res Yau Yue 101.3 NGAU TAU Wan _ÄL ß⁄ KOK ^­ú Po Lam Estate «”“ø´” ¶¶ Ying Ming ¥q Court 150.1 Shun Tin Quarry w…” t Estate 419 Telford Ser Res Yªú 105.9 Œ» aª 75.0 Gardens j¤W A»L Yan Ming Court 104.4 ¤¤ Sw P PUMPING STATION International a¦U¤KÅ …fi q¹v¼s Trademart q¨Z Tsui Lam Estate (U⁄ Lok Nga Court s·£ MTR Depot ß⁄Y⁄ SAU MAU PING ( under ) Lower … Est Lok Wah North t 82.9 Estate Ser Res t º´L PROPOSED TWIN RISING MAINS Metro City King Lam ¥©Y 124.9 q¨Z­ Ser Res LITTLE PALM R Estate NGAM TAU SHA êúA BEACH 100.7 82.9 ß⁄Y⁄ Hiu Lai … The Pinnacle Upper Court 823 000 N t d±±² Lok Wah South t I·„ Ngau Tau Kok Est Ser ¤ Estate Ser Res Hong Sing Garden Res t sƽ p«w |§ Ser Res |¹ú Hau Tak θú CROCODILE HILL A» 2 Chung MingEstate Yu Ming Court TSUI LAM Court áªé¶ Garden Estate ›⁄ M' F“ Wo Lok ú©w b¥£ wƒ„ East Point Estate Sau Mau Ping 4 Ming Tak Estate Boon Kin T› On Ning City D¿ù Estate Village Mau Wu ¥ 164.7 A»« Garden •œ Ð¥U¤ Tsui Ping (North) Tsai Yuk Ming Tin Ha Wan ‡ 4 Estate n«´ x¬ «”“m¶ł§ˆƒ Court Village Nan Fung Plaza s·_ bÂ} PAN LONG WAN t “‚ 350.3 R La Cite Noble Ser Res \«Î ³¿Ð ¯³Î 233 s¼ú s©½ 162.5 Hing Tin _Äú Kwong Ming Estate Po Ming T› Court A»« MAU WU SHAN Court |§§ Tsui Ping (South) D¿© 118.4 t |©w Hang Mei Deng Kwun Tung Estate Ser Res Sheung Tak Estate O Pui Village Village Typhoon Shelter aª ÅÂÐÅ I´d± 95.6 ÅÂÐ¥ ›⁄ Sw P Lam Tin Beverey Estate Lam Tin Park LAM TIN BLACK HILL Garden W¤v W¤ 6 ( NG KWAI SHAN ) PROPOSED AREA FOR IMPLEMENTATION t 304 –— t157.0 Ser Res ›œ Ser Res Kai Tin f‹ Tong Ming Estate ˚ƒ w¼Ð Court Tak Tin • PAK SHING KOK ­¥Ð Estate Gas Works 166.5 ¶”· 133.5 ·‰ R˜ Sceneway Garden 281 OF VILLAGE SEWERAGE WORKS Ferry Piers Ping Tin ‹ Estate Laguna City U¤ øªs s¼Ð CHEUNG U¤v j¤| Kwong Tin LUNG TIN HA YEUNG SHAN Estate 219.9 315.5 p¤| 10 q¼

d±f t j¤| Hong Pak Court Ser Res ¤ R T­ TAI HANG ù¯G j⁄ p¤ª TUK ”⁄

«ˆƒ 172.1 103.6 135.5 146.9 178.6 147.6 144.3

ƒm LOCATION PLAN PROPOSED SEWAGE PUMPING STATION Pik Shui178.0 186.0

196.0 116.9 ñ¤ SCALE 1 : 100 000 151.2 Sun Tsuen 210.2 199.1 172.9

316.8

296.0 310.5 y¦· 144.3 126.2 HEBE HILL (TSIM FUNG SHAN) 132.3 128.3 8.2 345.8 129.1

822 500 N 130.0 115.7 340.8 297.5

343.5 137.6 227.9 108.5 240.9 ¯•⁄

248.6 223.4

340.4 x 342.5 Water 235.4 125.3 251.5 Tank ÂÅl 120.7

139.6 277.4 239.9 RAZOR HILL 240.8

125.0

˛ 130.2 94.4 242.9 (CHE KWU SHAN) 119.6 320.1 ¥¥ 267.0 234.2 ÂÅl B§½ Pik Uk Au 137.2 PAK KUNG ¸­ZAU RAZOR HILL Pak Shek Wo 432.2 (CHE KWU SHAN) 231.4 248.5 431.9 130.6 230.3 122.0 246.7 246.6 224.7 121.2 San Tsuen 240.4

( FEI NGO SHAN ) 231.0 130.4

207.4 268.5 p 214.6 198.3 121.3 210.1

200.2 207.6

217.0 822 000 N 254.1

209.4

233.8 238.5

249.1

279.5 I¬u 133.4 196.1 174.3 «⁄ 123.0 194.4 ¥ 163.8 264.8 298.3

124.5 Tseng Lan Shue 187.1 286.3 Pak Shek Wo ù¯d 186.0 CHA LIU AU 192.9 136.8 134.4 124.6

204.6 163.0 194.2

201.6

185.3 199.7 138.0

168.9 208.0

175.2 217.8

194.0

197.3 155.1 133.3 206.6 124.4 Works in progress 190.3

192.9 198.3 201.5 p 200.9 188.7 198.8 203.5

125.8 260.9 191.5 128.5

203.2

135.9 I¬u s 202.6

132.1 821 500 N 225.5 139.6 123.5

I¬u Lung Wo Tsuen 169.1 130.0 231.9 132.3

118.8 201.9

Works in progress x 199.1 216.6 ⁄ 179.6 206.9 111.2 202.7 p

202.1 156.7 65.5 SAM LONG 162.3 185.9 58.9 197.8

´¬ 133.8 203.7

46.7 p 55.8

153.3 TAN SHAN x 215.5 153.0 Water Works in progress 182.6 Tank

28.2 0 100 200 300 400 500 m

37.0 109.5 151.9

1 : 10 000 SCALE BAR

140.3

143.4 152.7

194.0 24.8 I¬u 23.9

C. C. CHAN 20 MAR 2012 DSP/273DS1/11021 AS SHOWN Ir S. P. CHOW 20 MAR 2012 u⁄¨p›”„¶¥˜† 273DS „‚ - Ir C. K. WONG 20 MAR 2012 PWP ITEM NO.273DS - PORT SHELTER SEWERAGE, STAGE 3

Col_pdf_cswp_v8.plt PLOTPEN.TBL c:\temp\dsd_pw\dms11694\DSP_273DS1_11021.dgn 10 20 “ ENCLOSURE 3

o´ Water Treatment Works ù©W |¥ Sze Pak

ˆƒ⁄B Sewage Treatment SZE PAK WAN Works T¤ Sam Pak Ngong Ping Tsuen SIU HO WAN |¥ ª¨P SAM PAK WAN Sze Pak Tsui NGAU TAU WAN G⁄ |© Chianti DISNEYLAND RESORT CHEK LAP KOK YI PAK AUfi Neo Horizon fiÆ… Siena

[ DISCOVERY BAY TEI TONG TSAI YI PAK WAN (TAI PAK WAN) ú©A Greenvale Village Parkridge hºá Village LAU FA TUNG ˆX Q¯Ç «½ Hai Kam Tsui Wu Ying Pai 400 _Ĭ½ r´º Headland Village ˇ„ t Discovery Bay j¤F

ƒŒ ” j⁄ Tai Pak Tsui `¯ Ser Res TAI HO WAN Midvale Village Beach Village

TSOI YUEN ˚› WAN ` Crestmont Villa fi Peninsula Village NAM SHAN Fª _Ä La Costa Parkvale Village Po Lin [ƺ TUNG CHUNG ¥ ” Pak Mong fi Coastline Villa M¬W d±z La Vista Hillgrove Village fi‡ fi¯ Monastery Seaview Crescent La Serene Caribbean TAI HO NIM SHUE Coast Z‚ ¯´⁄ WAN HAU HOK Coastal Skyline Nim Shue WAN Wan Village o´ LEGEND: û¤º SHA LO WAN Ð¥ Water Treatment Ngau Kwu Long Works Tin Sam ¥F Ð¥ øªF Pak Sha Tsui Tin Liu j¤ ( TAI TUNG SHAN ) û¸ Cheung Sha Lan F¨³ÁW Kau Liu TAI LEI F“‡ Sha Lo Wan ˆƒ⁄B j¤s Tai Lung Chung Hau Tung Chung Sewage W© j¤®Ä Tsuen Treatment Crescent I´F Tai Ho PENG CHAU Fu Tung Works “W ˘ θF San Tsuen zÂp Kam Peng Estate s¤» San Tau Yu Tung Bijou Hamlet Estate F¨³ÁW C±g Shan Ting Court Tsuen TUNG WAN Sha Lo Wan F¨³Á POR San Tsuen Sha Lo Wan Tsuen ¤W TUNG CHUNG BAY Ma Wan Chung ‡J¥« ¶d – Wai Tsai Tseng ⁄ SHA LO WAN Wong Nai Uk San Tsuen È» MONG TO AU gM ‡J NGAN CHAU IJ@¤ Wai Tsai Tai Yat j¤ Tsuen Tai Wo HUNG FA NGAN San Tsuen ¸¤­ n«WÆs¤ F¨C Yuen Ling Nam Wan Shan Sha Tsui Tau h¶F Tsai ˘ Ting San Tsuen Yat Tung Estate n«WÆ San Shek Wan ¤W˘ ¥W Nam Wan A PO LONG San Tsuen NAM WAN Ma Wan WO SHEUNG AU TAI SHUI HANG New Village j¤¬Ç¦P ¶‰ Fui Yiu Ha s¤ W¤­ Wong Kung Tin Sheung Ling Pei Shan Ha U¤­ Ha Ling Pei C§H® ¶a Tei Po û¤ Wong Ka Wai “¤P⁄ New Village Ngau Au Chek Lap Kok s« s·Fª New Village «”“m¶ł§ˆƒ New Tung Chung Hang Fª Lung Tseng Tau Tung Hing

SHAM SHEK TSUEN Å ¶s Wong Lung ¯ªë n« Lam Che FªW Nam Tin Hang ” Kau Shat Wan ¥h Wo Tin Tung Wan Tau ¯ªë Shek Lau Po Z¸ Wang Tong F‹†'zˆ õ¬» s Hung Fan Nim Yuen Kau Shat Wan Lung Mei Tsuen «⁄Y Government Shek – Explosives Depot † ¥¨ SHAM WAT WAN ¥d Tseng Tau Mok Ka San Tsuen Pak Ngan Heung NGONG PING } “ WO LIU TUN MUI WO h¹ù Fong Yuen KÅw Sai Tso Wan s T­ Chap Mun ¹½º Tit Tak Shue Tau Lung Mei Hang BUTTERFLY HILL s· `² ¥ø –” Ø Sham Wat Shek Mun San Chau Mui Wo Tsoi Yuen F¯ PROPOSED AREA FOR IMPLEMENTATION Kap Kau Tsuen Tsuen Chung Hau s· j¤a San Keng Tai Tei Tong U¸ SILVER MINE BAY Man Kok ¬½á U¸¤ Mau Yuen ¥ 479 Shek Pik Au ¥ Man Kok Tsui SHEK SZE SHAN È»W j¤¬ Ngan Wan MUI Estate WO

–˙ LANTAU ISLAND ‡a Luk Tei Tong Œ¶ `˘ ùÂF Round Table ˆƒ⁄B Imhoff Tank OF VILLAGE SEWERAGE WORKS SHEUNG TUNG AU ¯ªù Village Sewage Treatment Works P©½ Kau San Tei 227 o´ ñ»Ä Water Treatment SUNSHINE ISLAND _Ä] H¶ Works WÆ (CHAU KUNG TO) Po Chue CHEUNG SHAN Wan Tsai êª Tam j¤FU SHAN G¤F flK“ ⁄‰ 900 Lai Chi Yuen Tsuen NGONG PING TAI O TEI TONG TSAI j¤F ˆƒ⁄B SUNSET PEAK 918 NAM SHAN Sewage Treatment ( TAI TUNG SHAN ) ¥J Works MUK YUE Shek TsaiSHAN Po YIM TIN s— sa Lung Tin Lung Hin Court Estate | • Wang Hang Village ‡F SZE SHAN T­ HEI LING CHAU TAI O Mau Yuen ( FUNG WONG SHAN⁄« ) ¥I ‡ ⁄‰ ñ»Ä Shui Tseng Wan •l⁄ Pak Fu Tin Luk Wu SZE TSZ TAU SHANMUK YUE SHAN LANTAU PEAK û¤º Ngau Kwu Wan s· ( FUNG WONG SHAN ) San Tsuen |§ B§½(F“F 934 W¤Â –˛ o´ Hang Mei PAK KUNG AU Leung Uk Water Upper ( TUNG CHUNG AU ) Treatment Tsuen Works u⁄{¶ n«F U¤Â j¤· TAI FUNG AU Nam Chung Tsuen Lower Keung Shan B§½(F“F '¤D¿ Wang Tong Pui O Hei Ling Chau Typhoon Shelter KEUNG SHAN Lo Wai Tsuen f› ©¨D¿s Fan Kwai Tong øª ¹ÃÎ Pui O Cheung Ting Lo Uk San Wai Tsuen Tsuen PAK KUNG AU ú¤N |§ Q⁄æ Hang Pui Shap Long Nga Ying Kok ÐÄÐ¥ San Tsuen Ham Tin San Tsuen CHI MA WAN

y¦p ÐÄÐ¥ TSIM FUNG SHAN Ham Tin Kau Tsuen PROJECT BOUNDARY Q⁄æ [˘ ( TUNG CHUNG AU ) û¤L Shap Long Ngau Kwo Tin KWUN YAM SHAN Kau Tsuen ¯ªú ˘ PUI O BEACH o´ San Shek Wan Q⁄æ Water Shap Long ú¤N Treatment PUI O WAN Chung Hau NGA YING SHAN Works øªF¨ Cheung Sha C«L Sheung Tsuen '¤D¿ Tsing Lam Kok sJ¥ Lung Tsai Ng Yuen øª CHEUNG SHA

øªF¨ Cheung Sha SHAP LONG IRRIGATION Ha Tsuen RESERVOIR G¤D YI O Yi O Hau øªF ('¤D SHUI LO CHO ´ F¨ Cheung Sha Wan KEUNG SHAN Sha Tsui û½ KAI KUNG SHAN G¤D¿ MAN CHEUNG PO Yi O San Tsuen ¶ Pui O Lo Wai Tsuen Tong Fuk ƒH CHEUNG SHA C H I M A W A N P E N I N S U L A

SHEK PIK (Pui O Au) s G¤D¿ Lung Mei Yi O Kau Tsuen ¼½½ Ha So Pai _¥øª TONG FUK MIU WAN Adamasta Rock MONG TUNG WAN ⁄ FÆ| Shui Hau j¤© LING WUI SHAN j⁄fi –F U¤ Mong Tung Wan TAI HOM SHAM Tai Long Wan CHUNG HAU j¤ Ha Keng Tai Long fiY Tsuen '¤D¿ KAN TAU AU TUNG WAN SHUI HAU WAN

⁄ Fª FAN SHUI AU ¥¥ Tung Wan TAI LONG WAN Lap Ngam Tsui FªW TUNG WAN TSAI Tung Wan _¥¤ Pui O Mei TAI KWAI WAN Pak Kok Tsui C© TAI LONG WAN Tsui Pai Æ… j¤Q¶W `²| Sea Ranch Tai Kwai Wan SHAM HANG LEK ¥ø San Tsuen ù¯G P¥½ SHEK MUN SHAN Sin Kung Tung CHA KWO CHAU _¥“ Lo Wai Tsuen YI LONG YI LONG WAN Pak She ˆƒ⁄B øªQ San Tsuen ¥V ‡V Sewage Cheung Kwai Treatment Estate Shek Lam LUK KENG SHAN G⁄ Works η½ ⁄ Yi Long Pai TUNG WAN Chau Shui Pai Tsin Yue Wan ¥ øª Pak Kok CHEUNG CHAU TUNG WAN BEACH

TÅÁ LO KEI WAN HEUNG CHUNG AU KWUN YAM WAN ©¨D¿s ⁄y CHEUNG CHAU WAN KWUN YAM FAN LAU TENG BEACH CHI MA NAM SHE 384 ¹ÃÎ HANG TONG Cheung Chau Typhoon Shelter j¤¬ Pui O FA PENG ‘† Sham Shui Pai ” TAI TSOI YUEN Greenery Crest Lo Uk FAN LAU KUI

FAN LAU SAI WAN TAI SHEK ⁄y SHUI HANG HAU NAM TAM Fan Lau Tsuen H«q San Wai Tsuen Lutheran SIN YAN TSENG ¯ª­ SAI WAN Village NAM TAM WAN Kau Ling Chung ł“w‹ i±O« Cheung Chau Tsuen O Cheung Po Tsai Meteorological Stn Cave FAN LAU TUNG WAN ‹g‚ E¤c CARE Village Kau Kung FAN LAU MIU WAN Tong § PO YUE WAN Mei Pai

PAK TSO WAN ¥“ LANTAU ISLAND ⁄y Fan Lau Kok SHEK KWU CHAU L ¥“„w‹ Shek Kwu Chau Treatment & Rehabilitation

_¥ ÐÄÐ¥ Pak Kok

W¤ Sheung Kok ÐÄ p⁄~ p¤~ SIU A CHAU SIU A CHAU 443 SHAN ©¨ Ham Tin San Tsuen U¤ PAK SHA Ha Kok WAN p⁄~ n«j⁄‹¥Siu A Chau Tsuen

… j⁄¥ CHEUNG MUK TAU TAI SHEK HA SHAN SIU A CHAU WAN s Lung Shuen Pai SUM WAN ˘ HAM TIN PUI O ÐÄÐ¥ SAN SHEK Ham Tin Kau Tsuen Q⁄æ LANTAU ƒm SOUTHLOCATION COUNTRY PLAN PARK Shap Long Kau Tsuen ¯ªú WAN˘ ©¨D¿ ñ¤ KAUSCALE NGA LING 1 : 250 000 o´ San Shek Wan Water øª PUI O 539 Treatment Works R˜ Leyburn Villas CHEUNG BEACH øªF¨ SHA Cheung Sha Sheung Tsuen

CHEUNG SHA

øªF¨ Cheung Sha 428 Ha Tsuen U¤øªF 5 LOWER CHEUNG W¤øªF SHA BEACH ¶ UPPER CHEUNG TONG¶ FUK Tong Fuk SHA BEACH

¶”g Tong Fuk ¶” Correctional Institution TONG FUK BEACH

⁄ SHUI HAU⁄ Shui Hau –F Mong Tung Wan

0 500 1000 m

179 æ⁄ ¥ø 1 : 30 000 SCALE BAR 30 SHEK MUN SHAN 138

W. Y. HUI 08 Mar 2012 DCM/2012/003

u⁄¨p›”„¶¥˜† 331DS „‚ K. H. LAI 08 Mar 2012 - n«j⁄‹s⁄ˆƒ W. Y. CHAN 08 Mar 2012 PWP ITEM NO. 331DS - OUTLYING ISLANDS SEWERAGE, STAGE 2 - SOUTH LANTAU SEWERAGE WORKS