Support to UKTram Activity Group 1 Protection and Diversion of Apparatus Phase 1b Analysis of Responses to Questionnaires Sent to UK Tramway Promoters and Operators, Continental Operators and Utility Companies June 2010 Title Support to UKTram Activity 1 “Protection and Diversion of Apparatus” Phase 1b – Analysis of Responses to Questionnaires Sent to UK Tramway Promoters and Operators, Continental Operators and Utility Companies Customer UKTram Customer reference Confidentiality, Copyright David Rumney, except logos and front copyright and sheet photograph, which are used by permission of reproduction the respective owners. Distribution and reproduction permitted at the discretion of UKTram. File reference C:\C154-UKTram Activity 1\Phase 1B Report\Master.doc Report number Issue number Final David Rumney 33 Woodside Lane Poynton Stockport Cheshire SK12 1BB Telephone: 01625 858448 E-mail:
[email protected] Author D J Rumney 11th June 2010 Reviewed by Approved by iii Contents 1 INTRODUCTION 1 2 QUESTIONNAIRES 1 3 DISTRIBUTION OF QUESTIONNAIRES 6 4 PRELIMINARY PRESENTATION OF QUESTIONNAIRES 6 5 ANALYSIS OF THE RESPONSES TO THE QUESTIONNAIRES 6 Promoters’ and Operators’ Questionnaire 6 Continental tramways 12 Utility Companies 14 SCHEDULE 1 – UKTRAM ACTIVITY GROUPS SCHEDULE 2 – QUESTIONNAIRE DISTRIBUTION LIST SCHEDULE 3 – ITINERARY FOR SEMINAR 28TH JUNE 2007 SCHEDULE 4 – TABLE OF RESPONSES TO UK PROMOTERS’ AND OPERATORS’ QUESTIONNAIRE SCHEDULE 5 – TABLE OF RESPONSES TO CONTINENTAL OPERATORS’ QUESTIONNAIRE SCHEDULE 6 – TABLE OF RESPONSES TO UTILITIES’ QUESTIONNAIRE SCHEDULE 7 - LIGHT RAIL PROMOTERS’ AND OPERATORS’ QUESTIONNAIRE SCHEDULE 8 – CONTINENTAL OPERATORS’ QUESTIONNAIRE SCHEDULE 9 – UTILITY COMPANIES’ QUESTIONNAIRE SCHEDULE 10 – SUMMARY OF PRINCIPAL FEATURES OF RISK-BASED UTILITIES MANAGEMENT STRATEGIES iv 1 Introduction UKTram is an organisation that represents the promoters and operators of tramways and light railways in the United Kingdom.