<<

Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt. of Form IA Project Address Plot No 1,Sector 21, Dwarka, Delhi

APPENDIX II FORM-1 A (Only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed Environmental Management Plan & Monitoring Programme).

1. LAND ENVIRONMENT Attach panoramic view of the project site and the vicinity 1.1. Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

Cabinet Secretariat, Govt. of developing a Residential cum Training Complex for Special Protection Group located at Plot No 1, Sector 21, Dwarka, Delhi. DDA Issued a No Objection Certificate to Ministry of Defense measuring 24.62 Acre area and further transferred to Special Protection Group , Cabinet Secretariat, Govt. of India, for training needs and other operational requirements, Plot No. 21, Sector-21, Dwarka ( swapped with DMRC, Eastern side of Metro line.) and Annexure-I letter regarding allotment for “ Title for 24.62 acre” of SPG land at sector-21, Dwarka, . Copy of same is attached as .

The plot area of project is 99,637.14 sqm while the built-up area is 1,36,741.91sqm (less than 1,50,000sqm). Therefore, as per the Gazette Notification, MoEF&CC, Govt. of India S.O. 3999(E) Dated 09.12.2016; only Form IA has been submitted to the local authority and till date construction work of built up area of approx. 50,045.32 sqm is completed.

Now, as per the DPCC letter vide F. No. DPCC/SEIAA/2018/54/6633-6641 dated 7.2.2018; the projects with the built up area more than 20,000 sqm is required to seek prior Environmental Clearance from Delhi SEIAA as being done prior to MoEF&CC Notification dated 9.12.2016.

However, the tenure of Delhi SEIAA was completed on 1.4.2018; hence, in the absence of Delhi SEIAA; we are submitting the proposal for obtainingAnnexure the Environment-II and Clearance in the MoEF&CC. Annexure- III Location Map of 10 Km is attached as The Site Layout Plan of the Project site is attached as Table 1: Latitude and Longitude of the Project Site S. No. Description of Point Latitude Longitude

1. A 28°33'48..52"N 77°4'8.28"E 2. B 28°33'46.51"N 77°4'13.25"E Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 17 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt. of India Form IA Project Address Plot No 1,Sector 21, Dwarka, Delhi

3. C 28°33'40.67"N 77°4'9.67"E 4. D 28°33'29.23"N 77°3'57.08"E Source:5. Site visit by Team. E 28°33'31.38"N 77°3'52.28"E 6. F Annexure-IV. 28°33'42.65"N 77°4'4.59"E

PillarSurrounding Coordinate Features: Map is attached as Table 2. The surrounding features of the project site are presented in Table 2: Surrounding Features

S. No. Surrounding Features Description Aerial Distance & Direction from the Project Site

1 Nearest Metro station Dwarka Sector 21Metro Approx. 0.95 Km towards South direction station 2 Nearest Railway Station Shahabad Mohhamadpur Approx. 1Kms towards East direction Railway station 3 Nearest Airport IGI Airport Approx. 1 Km towards East direction 4 National highway National Highway – 8 Approx. 5 Kms towards East direction 5 Nearest Place of Worship Ambassdor of Zion Church Approx. 0.25 Kms towards West direction 6 Nearby School Mt. Carmel school Approx. 1 Kms towards West direction A R Hotel Management Approx. 2 Kms towards South direction 7 Critical Polluted Area Naraina Approx. 9.5 Kms towards North East Anand Parbat Approx. 14.5 Kms towards North East 8 Forest Centre Ridge Reserved Forest Approx. 11 Km towards North East Rajokri RF Approx. 8.5 km towards South East 9 Nearby water body Najafgarh drain Approx. 4Annexure Km towards-V WestAnnexure- VI The Google image of 500m radius and 10/15 km topo-map is attached as & respectively. 1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.

Area Requirements: The major project requirements are as follows.

The project2 will be developed on a plot area of 99,637.142 sq.m. The total built-up area proposed is 1,37,288.36 m and totalTable proposed– 3: Area Statement FAR is 88,431.89 m . The other details of area requirements are given is Table- 3. Sr. No. Particular Area in sqm Percentage

1 Total Plot Area 99,637.14 2 Permissible Ground Coverage 33,209.05 3 Achieved Ground Coverage 15,068.08 15.12 5 Green Area Provided 18,249.5 18.32 5 Area for surface Parking 12,818.09 12.86 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 18 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt. of India Form IA Project Address Plot No 1,Sector 21, Dwarka, Delhi

6 Area for roads/paved area 53,501.47 53.70 7 Permissible FAR (@2 of the total plot area) 1,99,274.28 8 Proposed FAR (@0.88 of the total plot area) 88,431.89 9 Non FAR 48,310.02 a Upper Basement Area 20,941.79 b Lower Basement Area 21,474.12 c Stilt 2,721.24 d Covered Parking 1,107.92 e UG Tank 546.45 f Guard room 18.93 g ESS Area 1443.79 h Dhalao 55.78 *Source: As per submitted plans. 10 Built Up Area 1,36,741.91

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 19 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt. of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Table 4: Details of Building Blocks Description No. of Blocks Non FAR in Ground FAR in Sqm Number of units Sqm Coverage in sqm

Centre of Excellence 1 1104.79 2902.38 Community Facility 1 912.39 3457.02 Type II and IIA No. Of Blocks 3 5682.54 Gd+8(II) 16806.10 428 Gd+8(II) 16806.10 Gd+8(IIA) 16806.10 212 Type III 96 No. of blocks 1 1167.78 Stilt+8 8957.86 Stilt 1274.24 Type-IV 28 No. of Blocks 1 484.40 Stilt+7 3200.09 Stilt 534.34 Type-V 28 No. of Blocks 864.29 Stilt+7 5862.71 Stilt 912.66 Upper Basement 1 20941.79 Lower Basement 1 21474.12 Nursery School 1 737.96 1475.92 Transit accommodation GO’s 1 190.74 915.58 8 Transit accommodation SA’s/ SO’s 1 603.98 3569.03 40 Hostel SA/SO 1 1403.26 6920.75 Rooms SO=50 Rooms SA=35 OAT 1 686.98 685.47 Reception 1 66.78 66.78 Guard room 3 18.93 Substation 6 ESS(2,3,4,5) 4 1,061.24 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 20 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt. of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

4 Nos. @ 265.31 Sq.m) (

ESS 1 1 157.49 ESS (6) 1 225.06 UG tank 1 546.45 TotalCovered Bus Parking 1 481,,107.92310.02 151107.02,068.08 88,431.89 Dhalao 1 55.78 55.78

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 21 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Water Requirement: Construction Phase: . 20 KLD The water requirement during the construction phase comprises mainly of two parts i.e. fresh water for laborers and treated water for building constructions. Approx of fresh water have been required for drinking purpose which have been imported in form of bottled 50 cans from the local fresh water supplier during the construction phase. Approx. KLD of treated water is required for the construction purpose which is met by the treated water from the CSTP, which is brought by the water tankers. Operation Phase: 769 KLD . It is estimated that the total water demand during the operation phase will be 473 KLD 296 KLD out of which fresh water will be provided by Delhi Jal Board The fresh water requirement for employees is calculated to , whereas the treated water requirement is approx. which includes water requirement for flushing, and horticulture. Detailed Power Requirements:

12,336 KVA. The power supply shall be supplied by BSES Rajdhani Power Limited. The demand load for the project is Transfer load @ 80% will be 15420 KV and for that size of the transformer will be 16 number of 990 KVA. There is provision of 8 DG set of total capacity 7500 kVA(10*600+2*750 KVA) for power back up in the project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and Table 5. adequate stack height for properTable-5smoke: Powerdispersion. RequirementThe for powerOperationrequirementsPhase during operation phase are givenParameters in Operation Phase 12,336 KVA

Power requirement Supply by BSES Rajdhani Power Limited (BRPL) Back-up power supply 7,500 kVA(10*600+2*750 KVA) Parking Requirements:

Adequate provision of 1,649 ECS for vehicular parking will be made within the residential complex. Table 6 And training centre. There will be sufficient parking provisions within the project premises. The required and proposed parkingTable is given6: Parking in Requirement S/n Items Norms FAR ECS

Source: (i) NDMC (ii) MoEF&CC 1 Required Parking 1.8 ECS/100 SQ.M. of FAR 88431.89 Sqm 1,591

Parking area in Number Distribution of ECS S. N. Description Norms sqm of ECS 4w 2w Bus

@ 32 1 Basement upper level sqm/ECS 16,864 527 311 864/4=216 @ 32 2 Basement lower level sqm/ECS 17,248 539 321 872/4=218 3 Surface parking @ 28 11,017 479 479 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 22 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

sqm/ ECS @ 28 4 Stilt parking (type- iii) sqm/ ECS 448 16 16 @ 28 5 Stilt parking (type- iv) sqm/ ECS 336 12 8 16/4=4 @ 28 6 Stilt parking (type- v) sqm/ ECS 672 24 22 10/4=2.5 @ 28 10x 7 Covered bus parking sqm/ ECS 1,120 40 4 Total @ 28 1, 649 03x 8 Open bus parking sqm/ ECS 276 12 4 9 Annexure- VII Annexure-VIII. Upper Basement and Lower Basement Plan is attached as and traffic circulation plan is attached as Connectivity and Community Facility Requirement:

Community facilities like hospitals, school, place of worship, etc. are available in near vicinity of the project site. 1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities details of the existing land-use, disturbance to the local ecology).

The project being a well planned activity will result in organized open spaces and green areas. No negative impact is anticipated of the activity on the existing facilities adjacent to the site such as open spaces & community facilities. The project activities are confined in the site only. The project will not have any adverse impact on the surrounding environment. The project has a proposal of green area development, which will increase2 the aesthetic value of the area. Total Green area development will be done on the 18,249.5 m . Plantation will be done on sides of roads and along the periphery of the plot area. 1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).

The proposed activity will not affect any significant land disturbance resulting in soil erosion, aftersubsidence back filling and instability. and using The for areasite developmentis not susceptible. to erosion. The estimated quantity of excavated earth material are being utilized at the site for leveling, backfilling and green area development or

Land/soil environment may be affected due to activities like site preparation, excavation, material handling & storage etc. during construction phase. Proper drainage system is being provided to deal with the storm water in case of rain. Soil type

: A quantitative assessment of the particle in size distribution of the soil was made by wet sieve analysis and sedimentation analysis using hydrometer, as per procedures laid down IS: 2720 Part IV. The particle sizes were designated according to the scale given in IS: 1498 and the soil type in the area is found to be loam. The project site is located in high seismic risk (Zone IV) by national standards. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 23 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Source: Building Materials and Technology Promotion Council

Figure 1: Seismic Zone Classification

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 24 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Flood Plain:

The project site is flat and artificial drains are passing through the vicinity of project site and therefore no incidence of flooding and water logging is envisaged by the project. 1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site)

The ground surface is almost level. The project is not likely to alter or obstruct any natural drainage courses. There is no natural watercourse passing through the project site. Hence, the project does not involve alteration of natural drainage systems. As a result of excavation of topsoil during construction phase, the impact on drainage pattern, and run off characteristics are restricted to the project area. Proper rain water drainage facility shall be provided and the run-off generated will be storing in underground water tank & reusing while operation phase. 1.6. What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc?)

The total excavated earth quantity is approximately 1,69,663.64 cubic meter. Excavation had been carried out till basement/foundation levels. The total excavated earth material is being reused for the purpose of back-filling and developing landscape. There are no transportation of earth material outside the project site. 1.7. Give details regarding water supply, waste handling etc during the construction period. Construction Phase: . The water requirement during the construction phase comprises mainly 20 KLD of two parts i.e. fresh water for laborers and treated water for building constructions. Approx of fresh water have been required for drinking purpose which have been imported in 50 KLD form of bottled cans from the local fresh water supplier during the construction phase. About of water will be required for the remaining construction purpose of the building. The treated water requirement will be met by the treated water from the nearby CSTP, which is brought by the private water tank. . The solid waste generated during the construction phase mainly comprises of concrete washout cement residue, litters, packaging waste, masonry blocks, scraps etc The generated waste are being re-used to raise the level of the site. Conclusively, it can be stated that impacts may be confined to small area (mainly to project site) and for short duration. Proposed mitigation plan suggests maximum re-use of construction waste on site, removal of non-reusable waste from the site and its proper disposal as per Construction and Demolition waste management Rules 2016, which would reduce the impact significantly. 1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity).

There are no wetlands or low-lying areas present in the vicinity of the project site. 1.9 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal).

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 25 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

During the construction phase, there is no such waste generated, which can cause health hazard. The surplus earth and the fertile topsoil are being used for developing landscape. Construction debris is collected and stored at earmarked places for reuse immediately at the construction site 2. WATER ENVIRONMENT 2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. Water Management: Construction Phase: . The water requirement during the construction phase comprises mainly 20 KLD of two parts i.e. fresh water for laborers and treated water for building constructions. Approx of fresh water have been required for drinking purpose which have been imported in 50 KLD form of bottled cans from the local fresh water supplier during the construction phase. About of water will be required for the remaining construction purpose of the building. The treated water requirement will be met by the treated water from the nearby CSTP, which is brought by the private water tank. Operation Phase: 769 KLD . It is estimated that the total water demand during the operation phase will 473 KLD be out of which fresh water will be provided by Delhi Jal Board The fresh water 296 KLD requirement for employees is calculated to , whereas the treated water requirement is approx. which includes waterTable requirement 7: Water Calculation for flushing, and horticulture. Area in Water Sqm/ Demand power per r. load in capita Fresh Treated Total Wastewa No. Particular No. KVA per day Water Water Water ter S Residential Population

1 4432 … 135 452.22 146.10 598.32 507.876 Visitors of Residential 2 Population 89 … 15 0.33 1.01 1.34 1.270 CommunityStaff of residential 3 Populationpopulation 44 … 45 0.48 1.50 1.98 1.883

4 … … … … … … a Guest Room 14 … 200 2.12 0.68 2.80 2.377 b Dormeteries 8 … 45 0.09 0.27 0.36 0.342 c Visitor 698 … 15 2.56 7.91 10.47 9.959 Centre of Excellence d Staff 10 … 45 0.11 0.34 0.45 0.428 OAT 5 600 … 45 6.59 20.41 27.00 25.681 Reception 6 1000 … 15 3.66 11.34 15.00 14.267 Nursery school 7 50 … 45 0.55 1.70 2.25 2.140 Landscape 8 400 … 45 4.40 13.60 18.00 17.121 Total 473.1 296.11 769.21 583.34 9 … 18249.5 5l/sqm 0 91.25 91.25 … Say 473 296 769 583 12 …

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 26 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

The water balance diagram is shown below in Figure 2:

Total Water Requirement (769 KLD)

Treated Water Fresh Water (296 KLD) (473 KLD)

Flushing Horticulture (205 KLD) Wastewater378 KLD (91KLD) (80% of 473 KLD)

Wastewater (205KLD) @100% Nil

Total Waste water (583 KLD)

STP Capacity 700 KLD

(296 KLD)

STP Treated Water (466KLD)

Discharge to Sewer (170 KLD)

Figure 2: Water Balance Diagram for Non Rainy Season

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 27 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Total Water Requirement (678 KLD)

Treated Water Fresh Water (205 KLD) (473 KLD)

Flushing (205 KLD) Horticulture Wastewater378 KLD (Nil) (80% of 473 KLD)

Wastewater (205KLD) @100% Nil

Total Waste water (583 KLD)

STP Capacity 700 KLD

(205 KLD)

STP Treated Water (466KLD)

Discharge to Sewer (261KLD)

Figure 3: Water Balance Diagram for Rainy Season

2.2 What is the capacity (dependable flow or yield) of the proposed source of water? 769 KLD . It is estimated that the total water demand during the operation phase will be out of 473 KLD 296 which fresh water will be provided by Delhi Jal Board The fresh water requirement for employees is calculated to , whereas the treated water requirement is approx. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 28 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

KLD 700 KLD which includes water requirement for flushing, and horticulture. from the STP of Capacity . The required fresh water will be provided by Delhi Jal Board (DJB). 2.3 What is the quality of water required, in case; the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

The water supply is from Delhi Jal Board. The data from the secondary source shows that all the parameters are well within the permissible limits and water can be used for drinking and domestic purposes after treatment upto tertiary level i.e RO system. 2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage). Details of Dual Plumbing: -

There will be a dual plumbing system for use of water for different applications thus reducing water demand. Installation of dual plumbing for using recycled water will save the potable water. There will be two pipe lines, one supplying freshwater for drinking, cooking etc. And other for supply of recycled water for flushing, landscape etc. this will result in saving of fresh water demand. It is expected that the project will generate approx. 583 KLD of wastewater which will be Annexure IX X treated in the STP of capacity 700 KLD and 296 KLD treated water will be achieved. Sewerage supply and water supply plan is attached as and respectively. 2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption).

No, there is no diversion of water from other users. Rise in water demand is a local phenomenon but the project would have limited regional impact on water reserves. 2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity).

170 KLD treated water discharge in non rainy season and 261 KLD in rainy season from project during the operational phase from domestic use. The wastewater generated will be treated in well-designed sewage treatment plant. The anticipated compositions of waste water characteristic are as followsTable. 8: Composition of Waste Water Characteristic Value Parameters Expected wastewater Treated wastewater characteristics characteristics

pH 6.5 – 8.5 6.0-8.5 5 BOD Upto 300 mg/l Less than 5 mg/l Suspended solids Upto 250 mg/l Less than 50 mg/l COD Upto 750 mg/l Less than 20 mg/l Oil and grease Upto50 mg/l below the detectable limit Detergents 50-100 mg/l Less than 10 mg/l 2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 29 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

The rainwater harvesting will help in raising the ground water table. The ground water will not be used for this project during construction and operational phase however the required water will be supplied by Delhi Jal Board. Water Harvesting:

The roof top rainwater harvesting through recharge pit process will be used for the recharge of the water at the project site. Peak hourly rainfall is considered as 50 mm/hr for designing of rainwater harvesting pit. 10 recharge pits are proposed. Mesh will be provided at the roof so that leaves or any other solid waste/debris will be prevented from entering the pit. The water collected will be used for replenishing the ground aquifers and creating surface storages for utilization in non-rainy season. Rainwater harvesting plan is as per the design approved in the manual issued by the GOI. Project proposing 10 number of rain water harvesting pits. A detailed “Storm Water Management” will be developed. This will incorporate best management practices as follows:  Regular inspection and cleaning of storm drains.  Clarifiers or oil/water separators shall be installed in all the parking areas.  Cover waste storage areas.  Avoid application of pesticides and herbicides before wet season.  Secondary containment and dykes in fuel/oil storage facilities.  Conducting routine inspections to ensure cleanliness. Provision of slit traps in storm water drains. 2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long-term basis? Would it aggravate the problems of flooding or water logging in any way?

No adverse impacts are envisaged due to the project on the runoff characteristics of the area as adequate arrangements will be made to trap the rainwater and suitable storm water drainage system will be provided. During the post-construction phase, runoff from the project shall not be allowed to stand or enter into the roadside or nearby drain. Adequate measures shall be taken to collect such run off and either shall be reused. No problem of flooding and water logging is envisaged as excess run-off will be drained to ground water. 2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent).

The building structure will have rainwater-harvesting infrastructure. The rainwater harvesting facility will be used to recharge the ground water, which will have positive impact on the prospects of ground water. Water requirement will be reduced by recycling of treated water. Further ground water will not be used during construction phase rather it will be supplied by the STP treated water suppliers.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 30 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts).

To prevent degradation and maintain the quality of the water source, adequate control measure has been proposed to check the surface run-off. Following management measures are being taken to protect the water quality for the further construction work: Care will be taken to avoid soil erosion. The storm water disposal system for the proposed Project shall be self-sufficient to avoid any collection/ stagnation and flooding of water. Maximum rain water harvesting will be done within the site. 2.11 How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels).

The storm water disposal system for the proposed Project shall be self-sufficient to avoid any collection/stagnation and flooding of water. Maximum harvesting will be done within the site. A detailed “Storm Water Management Plan” will be developed. The plan will incorporate best management practices which will include following: Rain water outlets/ spouts will be provided in terrace for taking out rainwater.  The rainwater collected through channels and catch basins will be collected in an underground de-silting tank. Regular inspection and cleaning of storm drains.  A grating at the main entrance will be provided to prevent entry of outside rainwater to the premises or inside level to lie higher than outside level. All road crossings for services shall be provided with RCC Hume pipe and manholes for the ease of maintenance and to avoid any digging of roads. 2.12 Will the deployment of construction laborers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation).

Labour hutments have been provided at a location away from construction site. All the basic needs (drinking water, electricity, etc) are there along with rest shelters, wash place, mobile toilets have been provided to labourers on the project site. Portable toilets with soak pit facility has been provided to treat the wastewater generated. 2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal).

During operation 583 KLD of wastewater will be generated, which will be treated in the sewage treatment plant & treated water from STP will be utilized for flushing, and landscape development. Details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal are given in Table 9.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 31 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Table 9: Waste water Quantity, Treatment, Reuse & Disposal Parameters Details

Quantity of waste water 583 KLD Waste water generated during the operation phase will be collected Collection of waste water through underground piping system (pipe drain) for treatment in STP upto tertiary level. Sustainable Microbial Anaerobic Reactor TechnologyWaste water. will be treated in a Sewage Treatment Plant (STP) of Treatment of waste water Capacity 700 KLD of

Reuse/recycle and During normal operations treated sewage will be recycled and reused for Disposal of treated sewage flushing, 2.14. Give details of dual plumbing system if treated waste is used for flushing of toilets or any other use.

There will be a dual plumbing system for use of water for different applications thus saving on the high quality water. Installation of dual plumbing for using recycled water will save the potable water from authorized private water agency. There will be two pipe lines, one supplying freshwater for drinking, cooking etc. and other for supply of recycled water for flushing, landscape irrigation, etc. This will result in saving fresh water demand and life of existing sewerage will be improved. 3. VEGETATION 3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with its unique features, if any).

No threatened, rare, endangered or endemic species were observed during the survey in core zone. More trees will be planted on site so as to have thick vegetation. 3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project).

The project site was vacant land at the start of construction and as the project related activities (during construction and operation) are confined within the project premises. 3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc. along with a layout plan to an appropriate scale?).

Extensive plantation and green area and landscape development in the area of 18,249.5sq. m is planned. This is hereby ensured that the indigenous / local plants will be planted all around the periphery of the project area and along the roadsides; as per the Guidelines for the development of Greenbelt by CPCB. Plantation would be of flowering, evergreen, broadleaf trees that provide adequate shade. Efforts will be made to plant species as given below. Greenbelt Development

The following species can be used, as in a greenbelt, to serve as noise breakers:

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 32 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Table 10(a) :-Trees for Greenbelt Development S. Binomial Name Common Height Flowering Season Crown surface Leaf Stomatal No Name (Meters) area (sqm) Area Index . sqc) Acacia auriculiformisA.c 1 Australian 16m June-Jan 8548.22 140.5 10.9 unn Wattle Acacia nilotica (Linn) Willd. 2 Indian Gum- 8m Aug-JAN. 8293.74 135.7 11.23 Anonasquamosa Arabic-tree Linn. 3 Custard apple 10m March -July 2178.21 53.86 26.19 extended upto Anonareticulata sept. Linn. 4 Bullock's 10m June. 2017.44 50.91 17.24 Cassia Heart pumilaLamk 5 Yellow Cassia 10-12m 13,273.70 118.47 19.84 Cassia siameaLamk 6 Iron wood tree 10-12m Aug - May 3927.36 138.32 21.2 Citrus aurantium Linn 7 5m Sept - Nov 494.9 20.23 35.81 DalbergiasisooRo xb 8 Sissoo 10m March-April-June 5848.5 190.84 18.72 Derris indica (Lam.) Bennett. 9 Pongam-Oil 10m April - June 6278.1 79.6 25.2 Eucalyptus Tree, Karanj hybrid 10 Mysore gum 20m Feb. -April, Oct.- 50047.33 50.37 12.91 Source: Guidelines for developing greenbelt- CPCB-2007 Dec.

Table 10(b):- Shrubs for Green Belt Development S.No. Binomial Common Height Flowering Crown Leaf Stoma Name Name (Meters) Season surface area Area tal (sqm) (sqc) Index Bougainvill ea spectabilis Willd Bougainvill Clerodendr 1 ea 8m Through the year 939.25 33.15 32.53 uminfortun atum Linn (auct), Wight Hamelia 2 Bhant 3-4m Oct-Jan 854 47.9 19.07 patens Jacq Scarlet Lawsoniain 3 bush 3m Oct.- Jan 824.06 47.2 19.07 ermis Linn Murrayapa 4 Henna 5m April -July 71.85 77.8 17 niculata

5 5m June - Oct. 1354.61 35.3 10.31 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 33 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

S.No. Binomial Common Height Flowering Crown Leaf Stoma Name Name (Meters) Season surface area Area tal (sqm) (sqc) Index Linn Neriumindi cum Mill Pink Throughout the Ricinuscom 6 oleander 5m year 5747.63 32.62 15.7 munis Linn Tabernaem 7 The castor 6m Sept - Oct 942.56 243.5 15.71 onatanadiv aricata Linn Tecomasta 8 3m Through the Year 128.67 47.81 30.2 ns Linn. Thevetiape 9 5m Feb -April 61.23 43.7 23.8 ruviana (Pers.)Merr ill. Yellow 10Source: Guidelines foroleander developing6m greenbelt- CPCB-2007 21775.22 11.08 27.8

4. Fauna 4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details.

No displacement of fauna is envisaged due to Residential Cum Training Complex for Special Protection Group. The project site is free of nesting, roasting foraging habitat of wild animals further there is no proposal of creation of any barrier for terrestrial or aquatic fauna, hence it can be inferred that the proposed project is not going to disturb the movement of fauna. 4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

No direct impact on avifauna is envisaged. However, after the commissioning of the project the better environmental conditions may provide a better habitat to the avifauna of the area. There may be some indirect impact to avian fauna; however that will be minimized by adopting proper waste management, controlling noise pollution and bird friendly lightening. 4.3 Prescribe measures such as corridors, fish ladders etc. to mitigate adverse impacts on fauna.

No direct or indirect impact on fauna is envisaged hence no mitigation measures are prescribed. 5. AIR ENVIRONMENT 5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions).

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 34 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

The nature of the residential will not increase the atmospheric concentration of gases to such an extent may lead to the formation of heat islands. During construction phase, there are movements of vehicles that can generate the air pollution. So, wheel washing provision is being provided to the vehicles movement at entry and exits to reduce air pollution. The marginal increase in traffic due to project is not going to cause any significant increase in atmospheric concentration of gases and will not result in heat island formation. 5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters. Prediction of Impacts

Vehicular emissions and DG sets emission are major sources of air pollution from the Residential Cum Training Complex for Special Protection Group located at Sector 21, Dwarka, Delhi. During post construction phase, Ground Level Concentration of pollutants (as added by the project) will depend upon the following:  Emission of pollutants from additional traffic on the roads due to the project.  Meteorological conditions. Emission sources from D.G. Sets. , 2 2 PM NO , SO and CO will be the main pollutants of primary concern released from traffic movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the dispersion of vehicular emissions would be confined within limited distance from the road and concentration will decrease with the increase in distance from road. It is anticipated that the contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well within the stipulated National Ambient Air Quality Standards due to traffic movement and vehicles used inside the premises. DG sets will be main source of Air Pollution in the project. CPCB/ MoEFCC approved USEPA dispersion model-ISCST3 have been used for prediction of impacts caused by DG sets. Stack & emission data was used as per the CPCB emission norms. Other primary data used as input for model were hourly meteorological data of Wind speed & direction, temperature stability class and mixing height. Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. In this project,12 no. of DG sets of capacity 7500 kVA(10*600+2*750 KVA)will be provided as the source of back up of electricity supply during power failure. The incremental load in the ambient air environment will be found to be very low as given in the report. The stack height of 6 mtrs will be provided for the D.G. sets as per the stipulated guidelines of Central Pollution Control Board (CPCB)/ National Building Code Manual to facilitate proper dispersion of pollutants and to minimize the impact on Ambient Air Quality under the influence of local meteorology. AIR ENVIRONMENT Prediction of Impacts

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 35 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Vehicular emissions and DG sets emission will be major sources of air pollution from the Residential cum Training Complex for Special Protection Group.During post construction phase, Ground Level Concentration of pollutants (as added by the project) will depend upon the  following: Emission of pollutants from additional traffic on the roadsdue to the  project.  Meteorological conditions. Emission sources from D.G. Sets. , 2 2 PM NO , SO and CO will be the main pollutants of primary concern released from traffic movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the dispersion of vehicular emissions would be confined within limited distance from the road and concentration will decrease with the increase in distance from road.It is anticipated that the contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low sulphur diesel will be used.Ground Level Concentration (GLC) of pollutants is found to be well within the stipulated National AmbientAir Quality Standardsdue to traffic movement and vehicles used inside the premises.DG sets will be main source of Air Pollution in the project. CPCB/ MoEF approved USEPA dispersion model -ISCST3 have beenused for prediction of impacts caused by DG sets.Stack&emission data was used as per the CPCB emission norms. Other primary data used as input for model werehourly meteorological data ofWind speed & direction, temperature stability class andmixing height. Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. In this project, DG set of capacity 2 x 750 + 10 x 600 kVA will be provided asthe source of back upof electricity supply during power failure. The incremental load in the ambient air environment will be found to be very low as given in the report.The stack height of 5.5 mtrs will be provided for the D.G. sets as per the stipulated guidelines of Central Pollution Control Board (CPCB)/ National Building Code Manual to facilitate proper dispersion of pollutantsand to minimize the impact on Ambient Air Quality under the influence of local meteorology. Meteorology:

Assessment ofMetrological Impact to Airdata Environment: has been taken Guidelines for the period for conducting of February, Air 2018procured Quality Modeling from IMD Delhi. Extrapolation of wind data, as hourly data was not available, has been done as per (Ref: PROBES/70/1997-98). " " published by CPCB, Delhi in 1998 As referred above mixing height data has been taken from the “Atlas of Hourly Mixing Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. Windrose:

Windrose have been plotted with the aid of software WR PLOT and following results have been Interpretation of Windrose: obtained.

1. Predominant wind direction is North while second and third predominant wind is NW &NE respectively. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 36 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

3. Calm conditions was recorded as 65.63 % 4. Average wind speed was found to be 1.76m/s

Figure 4:- Wind Rose(Feb-2018)

Model details and Frame work of Computation:

The predictions for air quality during operation phase were carried using CPCB/MoEF approved “USEPA, Industrial Source Complex (Version - ISCST3)”. Dispersion model developed by the US Environmental Protection Agency (USEPA) for prediction of pollutants dispersion from single or multiple point sources using emission and hourly meteorological data of the study period. Assumptions used in the model are as follows:

The plume rise is limited to that of the mixing layer as published by IMDin the  Catalogue of Atlas of Mixing Heights in India for the site  Stack down-wash is not considered.  Flat terrain is used for computations; It is assumed that the pollutants do not undergo any physico-chemical  transformation. Chemical and scavenging process occurred in the atmosphere in the pollutants released at the stack exit is not considered.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 37 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Prediction is based on single/multiplepoint sources, pollution released at stack exit and dispersed on the ground under influence of local meteorological  conditions during the season. As hourly data was not available for modeling, extrapolation has been done as (Ref: PROBES/70/1997- per "Assessment of Impact to Air Environment: Guidelines for conducting Air 98) Quality Modeling" published by CPCB, Delhi in 1998

ISCST3 dispersion model was used to predict GLC caused by a different point source at each receptor of 100m x 100m of grid network covering total area of 4000m x 4000m around the proposed source with stack & emission values and 1-hourly meteorological data. It was 2 2 observed that SO , NO , CO and PM were significant pollutants released from the fuel of the D.G. 2 2 sets. Emission of PM, CO and SO were found insignificant with low values compared to NO . In 2 this project, NO was the worstTable pollutant11:-Stack released and Emission into the Details atmosphere (Table 11) with high emission value DG set Stack & Flue details Pollutants Emission factor Stack Capacity No. Height velocity Temp Diameter NO2 SO2 PM CO (kVA) (m) (m/s) (K) (m) (g/s) (g/s) (g/s) (g/s)

1. 750 45.5 25.23 773 0.33 1.53 0.19 0.05 0.58

Note:3. - 600 45.5 25.11 773 0.27 1.02 0.13 0.03 0.39

2 2 24-h GLC were predicted for SO , NO , CO and PM Discussion of Results

PM ISCST3 - Dispersion model was used to predict GLC ofPMwith stack &emission and 0.29 µg/m3 (500,0);500 m Eastdirection hourlymeteorological data. 24-hours average maximum Incremental GLC of was found to be

occurred at room the DG sets fitted3 with chimneys3 of 2 2 stack heightand3 GLC of other pollutants SO , NO and CO were 1.62µg/m , 9.29 µg/m and 3.55µg/m respectively occurred at the same distance. The meteorological data of the predicted concentrationTable 12:- Meteorological under the worst data forcase the is 24shown-hour in average Table 1 maximum2. predicted Concentration under worst meteorological condition Year Month Day Hour Wind Direction Wind Speed Temperature (Degree) ( m/s) (K )

2018 2 10 1.00 292.5 0.514 284.15 2018 2 10 2.00 292.5 0.514 284.15 2018 2 10 3.00 292.5 0.514 283.15 2018 2 10 4.00 0 0.514 283.15 2018 2 10 5.00 0 0.514 283.15 2018 2 10 6.00 0 0.514 282.15 2018 2 10 7.00 0 0.514 282.15 2018 2 10 8.00 0 0.514 282.15 2018 2 10 9.00 0 0.514 281.15 2018 2 10 10.00 0 0.514 281.15 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 38 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

2018 2 10 11.00 0 0.514 281.15 2018 2 10 12.00 45 0.514 293.15 2018 2 10 13.00 45 0.514 293.15 2018 2 10 14.00 45 0.514 293.15 2018 2 10 15.00 45 0.514 293.15 2018 2 10 16.00 45 0.514 293.15 2018 2 10 17.00 45 0.514 293.15 2018 2 10 18.00 45 0.514 296.15 2018 2 10 19.00 45 0.514 296.15 2018 2 10 20.00 45 0.514 296.15 2018 2 10 21.00 45 0.514 287.15 2018 2 10 22.00 45 0.514 287.15 2018 2 10 23.00 67.5 0.514 287.15 2018 2 10 24.00 270 0.514 285.15 Figure5

Spatial distribution of PMis shown in iso-pleth . It was observed that GLC closed to the

proposed source will be not significant3 due to high stack attached with DG sets. 24-h maximum incremental GLC will be0.29µg/m occurred at the distance 500m (East) i.e. (500, 0) from the project site.

Figure 5: Particulate Matter maximum incremental GLC (0.29µg/m3)at (500,0) stack height of 45.5 m Spatial distribution of 24-hours average 500m(E) . Moderate to high wind speed and facilitates dispersion at long distance of under the influence of local meteorology.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 39 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Figure 6

2 Spatial distribution of SO is shown in iso-pleth . It was observed that GLC closed to the

proposed source will be not significant3 due to high stack attached with DG sets. 24-h maximum incremental GLC will be1.62 µg/m occurred at the distance 500 m (E) (500, 0)from the project site.

Figure 6: SO2 maximum incremental GLC (1.62 µg/m3) at (500,0) i.e. in East direction. stack height of Spatial distribution of 24-hours average 45.5 m 500 m(E) Moderate to high wind speed and facilitates dispersion at long distance of under the influence of local meteorology. Figure 7

2 Spatial distribution of NO is shown in iso-pleth . It was observed that GLC closed to

the proposed source will be not significant3 due to high stack attached with DG sets. 24-h maximum incremental GLC will be9.29 µg/m occurred at the distance approx. 500 m from the DG set location in the East directionof project site.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 40 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Figure 7 : NO2 maximum incremental GLC (9.29µg/m3) at (500,0). stack height of 45.5 m Spatial distribution of 24-hours average 500 mEast Moderate to high wind speed and facilitates dispersion at long distance of directionunder the influence of local meteorology. Figure 8

Spatial distribution of CO is shown in iso-pleth . It was observed that GLC closed to the

proposed source will be not significant3 due to high stack attached with DG sets. 24-h maximum incremental GLC will be3.55 µg/m occurred at the distance of 500 m in the East direction of project site.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 41 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Figure 8 : S CO maximum incremental GLC (3.55µg/m3) at (500,0). stack height of 45.5m patial distribution of 24-hours average 500m (E) Moderate to high wind speed and facilitates dispersion at long distance of under the influence of local meteorology. 5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

There will be sufficient parking space for the vehicles. The provision of parking space will be as Table 13. per the norms. The parking provision will be made at basement,. We are providing total 1,649 Table 13: Parking Requirement ECSS/ . The consolidated parking statement is shown in Items Norms FAR ECS n

1.8 ECS/100 SQ.M. of Source:1 (i) NDMCRequired (ii) MoEF&CC Parking 88431.89 Sqm 1,591 permissible FAR

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 42 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Parking area in Number Distribution of ECS S. N. Description Norms sqm of ECS 4w 2w Bus

@ 32 1 Basement upper level sqm/ECS 16864 527 311 864/4=216 @ 32 2 Basement lower level sqm/ECS 17248 539 321 872/4=218 @ 28 3 Surface parking sqm/ ECS 11017 479 479 @ 28 4 Stilt parking (type- iii) sqm/ ECS 448 16 16 @ 28 5 Stilt parking (type- iv) sqm/ ECS 336 12 8 16/4=4 @ 28 6 Stilt parking (type- v) sqm/ ECS 672 24 22 10/4=2.5 @ 28 10x 7 Covered bus parking sqm/ ECS 1120 40 4 Total @ 28 1, 649 03x 8 Open bus parking sqm/ ECS 276 12 4 Transport9 Infrastructure:

The project site is well connected to Dwarka 21 Metro station and Shahabad Mohammadpur Railway station. Adequate measures have been proposed to manage the traffic within and outside the site. There will be a proper entrances and exits for the proposed project to segregate the incoming and outgoing traffic. The vehicular traffic will move around the periphery of the project without disturbing the landscaped areas and organized open spaces. Internal roads of 6.0 m wide have been provided for traffic along with this; proper entry/exits have been planned. 5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

In the circulation plan of the project, there will be proper entry and exit points for systematic control of the vehicular movement within the project. Wide internal road (around 6.0m) will be provided for the smooth traffic movement. The project has roads running on the periphery at all sides that will facilitate the movement of traffic. Internal roads, footpaths, ramps with suitable width have also been provided. Adequate lighting arrangements will be provided covering all corners. 5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above.

There is marginal increase in the traffic noise; the sources are due to traffic movement within the project area. The horns are prohibited inside the project site. The traffic movements are restricted only in daytime during the construction phase. In operational phase only staff vehicles will come inside the project boundary. The pollution will be further minimized by plantation on the sides and around the periphery of whole project. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 43 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

5.6 What will be the impact of D.G. sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

In construction phase, DG Sets are being used for back-up. So, D.G. sets are the main source of 2 2 air and noise pollution. Gaseous pollutants like NO , SO and PM may be generated from activities like burning of fuel through D.G. sets. HSD diesel will be used with low sulphur. During operation, vehicular movement and operation of D.G. sets are the major sources of noise pollution. But both these activities – D.G. sets and vehicular movement will not have any significant impact on the area. Since D.G. sets will not be operational continuously and moreover Impacts on Air Quality it will be placed enclosed with suitable enclosures, hence no or minimal impact is anticipated.

Impacts on ambient air quality during operation due to emissions from the stacks attached to Mitigation Measures for Impacts of DG Sets on Ambient Air Quality: standby D.G. sets would be very less. However suitable mitigation measures will be adopted.   D.G. sets will be used only during power failure  D.G. sets will comply with the applicable as per emission norms.  Adequate stack height for D.G. sets will be provided as per C.P.C.B. norms. During operation stage, monitoring of emissions from D.G. sets and ambient air quality will be carried out as per norms. 6. AESTHETICS 6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

The project site does not have any scenic amenity or landscaping in its surroundings so there is no possibility of obstruction of above-mentioned conditions. Moreover the approvals of the architectural plan of the building have been taken from local development authority. The project will not in any way result in the obstruction of a view scenic amenity or landscapes. The present project itself is planned with provisions of landscaping and green area development and afforestation. This will surely enhance the aesthetic beauty of the area. 6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

No adverse impact on the existing structures is envisaged. There is adequate space to provide landscaping. The development of the project area is as per the approved Master Plan. 6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.

There are no local considerations of urban forms & urban design influencing the design criteria. The proposed site falls under the area of approved final development plan of the Delhi Development Authority (DDA). The project will be constructed within the designed site as per the defined NBC norms. 6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 44 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

There is not any anthropological or archaeological site or artifacts or any other significant features in the vicinity of the site, hence not considered. 7. SOCIO-ECONOMIC ASPECTS 7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the details. Construction phase:

About 200 labours will be engaged during construction phase. Alteration to the existing demographic profile of the area is not anticipated as labour habitation will be Operation phase: temporary. It is a Residential Cum Training Complex for Special Protection Group project and no demographic pattern will be affected due to this project. 7.2 Give details of the existing social infrastructure around the proposed project.

The project site is located in the developed area under the Master Plan. The ancillary infrastructure like roads, public health, amenities and conveyance facilities are already developed in the project area. However some of the existing social infrastructures available in the nearby area are as follows.

1 Ambassdor of Zion Church Approx. 0.25 Kms towards West direction 2 Mt. Carmel school Approx. 1 Kms towards West direction 3 A R Hotel Management Approx. 2 Kms towards South direction 4 Artemis Hospital Approx. 0.82 Kms towards North West direction 7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?

The Residential Cum Training Complex for Special Protection Group project is constructed within the designated site as per the defined bye-laws. There is a sacred site in nearby vicinity of project which is religious in nature. Respect to the local sacred site will be maintained without any disturbance to the users. 8. BUILDING MATERIALS 8.1 May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency).

Conventional construction material will be used. Energy efficient building materials will be used as specified in the Energy Conservation Building Code. The major materials used for the construction of the project are steel, cement, bricks, metal, flooring tiles/stones, sanitary and hardware items, electrical fittings, Autoclave aerated block,water etc. Cement is PPC which is a green product. Fly ash bricks are being used in construction of walls. 8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

During the construction phase the air quality has adverse impact. Construction activities especially related to handling of loose material likely to cause generation of fugitive dust that Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 45 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

adversely impacts the air quality of the surrounding area of the project site. To minimize the impact, loose material are either stacked or transported with proper covering. The site are enclosed with 3 m high barricade sheets to contain dust within the site itself to a maximum extent. During construction phase the expected noise levels lies between 70 – 85 dB (A), which decreases with increase in distance. Administrative as well as engineering control measures of noise has been implemented. High barricades around the site also cut down the spread of the noise. 8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?

Yes the recycled material will be used in the development of proposed Project to the extent possible. The possibilities will be searched and if feasible following recyclable material will be used in construction. 1. Fly ash Bricks 2. Clean wood 3. Recycled Gypsum 4. Mortar cement 5. Particle boards or other fiber-boards 8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project.

During the operation phase, waste will comprise domestic as well as horticulture waste. The solid waste generated from the project shall be mainly domestic waste and estimated quantity of the waste shall be approx. 2,647.25 kg per day, @0.25 kg per capita per day for the staff members, @0.15 kg per capita per day for the visitors, 0.12kg per capita per day for the institute and landscape wastes @ 0.2 kg/acre/day). Following arrangements will be made at the site in accordance to Solid Wastes ManagementTable 14: Solid Rules, Waste 2016. CalculationCalculation and Composition of solid waste generation is given in Table 14. Waste Sr. No./ Generation/kg/capita/da Solid Waste No. Particular Acres y Generation

1 Residential & Servant quarter 4,432 0.5 2,216 Community+COE+Reception+O 2 AT 1,672 0.15 250.8 Nursery school 400 0.12 48 3 Staff 54 0.25 13.5 Visitor 787 0.15 118.05 4 Landscape 4.5 0.2 kg/acre/day 0.9 (Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment EngineeringTotal Organization, Ministry of Urban Development, (, May 2000) 2,647.25

 Collection and Segregation of waste

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 46 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

1. A collection system will be provided for collection of waste in colored bins 2. The local vendors will be hired to provide separate colored bins for dry recyclables and Bio- Degradable waste. 3. Adequate number of colored bins (Green and white & blacks bins– separate for Bio- degradable, Non-Bio-degradable& inert waste) will be provided at the suitable locations of the project site.  Treatment of waste 

Bio-Degradable wastes 1. Bio-degradable waste will be processed in organic waste converter within project site.  2. Horticultural Waste is proposed to be composted and will be used for gardening purposes. Grass Recycling Recyclable wastes i. – The cropped grass will be spread on the green area. It will act as manure after decomposition. ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.  Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approved agency. Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of Solid Wastes Management Rules, 2016. 9. ENERGY CONSERVATION 9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?

The power supply shall be supplied by BSES Rajdhani Power Limited (BRPL). The demand load for the project is 12,336 KW. There is provision of 12 DG set of capacity (2 x 750 kVA and 10 x 600kVA) for power back up in the project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height Energy Conservation Measures & Management Plan: for proper dispersion of smoke.

In the operational phase, appropriate energy conservation measures and management plan will be adopted in order to minimize the consumptions of non-renewable fuel. The following measures are suggested to be adopted:  Passive Solar designs refer to the use of Sun’s energy for the heating and cooling of living spaces.  The orientation of the building will be done in such a way that maximum daylight is available.  The orientation of the building will be done in such a manner that most of glazed areas in north and east. Service areas have been planned on western sides. Lesser opening will be provided on the west facing walls.  Landscape and greens areas will be developed so as to cool the surrounding environment, which will reduce energy consumption. EnvironmentUsing electronic ballast for discharge lamps. Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 47 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

 Following measures have been proposed to reduce energy consumption for Electrical Use of Solar backed LED landscape lights instead of par lamps. installations: 

In the operational phase, appropriate energy conservation measures and management plan  will be adopted in order to minimize the consumptions of non-renewable fuel. The  following measures are suggested to be adopted: Solar panels will be installed to generate power which will be utilized within the complex. Use of LED instead of GLS lamps Common Areas. 9.2 What type of and capacity of, power back-up to you plan to provide?

In emergency situations, there is provision of 12 DG set of capacity 7500 kVA (10 x 600 kVA & 2 x 750) kVA for power back up in the project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion of smoke exhaust. 9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation?

Suitable thickness of glass will be chosen depending upon the panel size to keep the U value as per the requirement of ECBC. DGU glass will be used in windows to minimize heat transmission into the building. 9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project? 

 The orientation of the building will be done in such a way that maximum daylight is available.  The orientation of the building will be done in such a manner that most of glazed areas in north and east. Public areas will be cooled by natural ventilation.  Lesser opening will be provided on the west facing walls. Mainly service areas have been planned on west side. Landscape and green areas will be developed so as to cool the surrounding environment, which will reduce energy consumption. 9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details. 

Orientation is done in such a manner so that surface of the building cuts direct radiation of critical hours and thus building will be less affected with the heat. Building units will be made environment friendly with optimum use of solar radiations.  Solar photovoltaic cells will be installed at the roof and power generated thus will be used in complex. Solar water heater shall be used for residential block.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 48 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

9.6 Is shading effectively used to reduce cooling / heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

The shading will be effective to reduce the cooling loads. The following techniques are proposed to be adopted:  For walls of the building, a maximum of 10% window to wall ratio will be there to minimize solar radiation, which further helps minimizes cooling/ventilation costs.  Living areas will be aligned to get maximum north south light and services areas are to be located on the western side. DGU glass will be used to increase cooling effect in the buildings.  There will be less number of openings on the west and south side and more number of openings on the North and East sides.  Training of staff on methods of energy conservation and to be vigilant to such opportunities. Reflective materials will be used on roof surface for with solar reflectance ranging from 0.3 - 0.6. This will result in less absorption of sunlight causing 40% back reflection and less heating of building structures during summer seasons. Cavity wall construction on west and south sides to reduce heat transmission into the building. 9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications. 

The design of the building will be such that maximum use of natural lighting can be achieved. The walls, roofs and opening will be designed that influx of heat is minimum. The Energy Efficient Features: designo also incorporates the optimal and judicious use of natural lighting. o o Use of LED`s lamps instead of GLS lamps. o Use of LED`s lamps instead of GLS lamps for Common area Lights. Use of Solar backed LED landscape lights instead of par lamps. o Energy efficient VRV system will be proposed for Air conditioning in the building. Load of air conditioning is 815 T. 16 x 990 kVA dry type transformer will be installed having 99 % of efficiency 9.8. What are the likely effects of the building activity in altering the micro-climates? Provide a self- assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects? 

The building will use energy efficient and environmental friendly designs that will control formulation of heat island effect. There will be also green cover at the site to reduce formation of heat island. Passive design concepts have been used to minimize energy consumption and maximize the energy efficiency. Heat emission from the project and associated operations can be from the following sources: Heat absorbed and radiated from the paved and concrete structures, heat generated from Environmentequipments/appliances and due to increased population for a particular stretch of land. Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 49 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

However, the heat generated will not be significant and will be dissipated with the lush green provided within the project. Hence, it can be concluded that the heat island effect shall not be a concern for the project and will have an overall positive effect on the microclimate of the area.  Due to the project there would be insignificant emission of air pollutants by vehicular movements and occasional use of D.G/ sets, hence no heat island effect is envisaged. To reduce the heat load reflective insulated glass shall be used in fenestrations to cut on heat loads and subsequently capital & operating cost of air conditioning. 9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R- values of the individual components.

The building envelope for external walls will be made of bricks, concrete and steel. Proper roof insulation will be provided to achieve desired thermal comfort. The entire building envelope, opening between conditioned and non- conditioned spaces will be gasketed, provided with air curtains or sealed with sealants. Bricks, concrete & Glass will be used as construction material. Cavity wall and balconies shall be constructed for residential block. 9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.

In case of emergency, immediate steps will be taken to raise alarm and stop fire. The Fire Protection System would be based on the regulations of National Building Code, 2016 and local fire norms.  Provision of separate fire hydrant pipe.  The building is entirely covered with sprinkler systems  Fire tower will be provided with staircase, lifts and FHC  Smoke exhaust system have been designed for individual floors There is provision of firefighting pumps. Optical type smoke detectors shall be used in most areas. 9.11 If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics.

Glass will not be used as a wall material. 9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration. 

 Reduced air infiltration combined with proper ventilation cannot only reduce energy consumption but it can also improve the quality of indoor air. Outdoor air for which leakage account for 25 - 40% of energy will be used for heating and cooling in a typical building. For this purpose the building will be designed in a compact manner, leaving ventilation shafts in between for facilitating the escape of hot exhaust air. 9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used.

Non- conventional energy technologies shall be used to save overall energy consumption. EnvironmentFollowing technologies would be used in order to conserve energy: Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 50 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

  Replacement of High energy consuming incandescent lights with LEDs. Solar panels will be installed to generate solar power. 10. ENVIRONMENT MANAGEMENT PLAN Introduction

The Environment Management Plan (EMP) is a site specific plan developed to ensure that the project is implemented in an environmental sustainable manner where all contractors and subcontractors, including consultants, understand the potential environmental risks arising from the project and take appropriate actions to properly manage that risk. EMP also ensures that the project implementation is carried out in accordance with the design by taking appropriate mitigation actions to reduce adverse environmental impacts during its life cycle. The plan outlines existing and potential problems that may adversely impact the environment and recommends corrective measures where required. The Environment Management Plan (EMP) would consist of all mitigation measures for each component of the environment due to the activities increased during the construction, operation and the entire life cycle to minimize adverse environmental impacts resulting from the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the sites Objectives including fire.

 Actions/ activities required to comply with rules and requirements of the environmental clearance, consent to establish, consent to operate and other NOC from Govt. Departments.  Ensure that the Project meets all contractual, legal and other environmental requirements including best practices of construction.  To ensure that the residential Project is operated in accordance with the approved design. Provide proposed project personnel with systems, procedures and documentation necessary to undertake the construction meeting with environmental requirements and to minimize the impact on the natural environment.  A system that addresses public complaints during construction and operation of the facilities. EMP includes four major elements  A plan that ensures remedial measures is implemented effectively in a planned way. : Commitment & Policy: The management will strive to provide and implement the Environmental Management Plan that incorporates all issues related to air, water, land and noise.  Planning: This includes identification of environmental impacts, legal requirements and setting environmental objectives. Implementation: This comprises of resources available to the developers, accountability of contractors, training of operational staff associated with environmental control facilities and documentation of measures to be taken. Measurement & Evaluation: This includes monitoring, counteractive actions and record Activities: keeping.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 51 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

The following table is a detailed list of activities that will be carried out during each phase of Table 15 construction of the project and which phases require environmental management monitoring and reporting, . Table 15.Activities and requirement of EMP Phases Activities Required environmental management monitoring and reporting

 Construction Phase  Site Establishment Fences & hoardings to site compound. Required throughout the  Temporary services and site amenities. duration of this phase.  Temporary access roads.  Labour hutments (away from project site) Foundations  & Detailed excavation. Required throughout the Ground works  Lift Pit; duration of this phase.  Formwork.  Sand blinding & water proofing.  Steel reinforcement.  Place concrete  In ground hydraulic services.  In ground electrical services. In ground Fire Sprinkler services. Termite barriers.  Structure 1. Footings; Required throughout the  Formwork edge boards. duration of this phase.  Sand blinding & water proofing. Steel reinforcement.  Place concrete. 2. Slab on ground;  Formwork edge boards.  Sand blinding & plastic membrane. Steel reinforcement.  Place concrete. 3. Suspended Slabs  Formwork decks & columns.  Electrical conduits & penetrations.  Hydraulic pipe work & penetrations. Steel reinforcement. Place concrete. 4. Structural Steel framing. 5. Roofing. 6. External wall cladding.  Fit Out & Finishes Masonry Walls Required throughout the  Steel Stud wall & ceiling framing duration of this phase.  Windows & glazed doors  Electrical services  Hydraulic services  Mechanical services  Plasterboard wall & ceiling linings Cement Rendering Carpentry & joinery fitout Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 52 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Phases Activities Required environmental management monitoring and reporting    Tiling  Painting  Carpet  Vinyl External Works  Roads Required throughout the  Concrete Footpaths duration of this phase.  Formwork edge boards.  Sand blinding & plastic membrane.  Steel reinforcement.  Place concrete. Transportable Fences & hoardings to site compound. Required throughout the Building Site Confirm location of services installed by others. duration of this phase. Establishment   Transportable  Excavated earth Required throughout the Building Material Bricks, Sand duration of this phase  Steel reinforcement.  concrete Transportable  Deliver to site on trucks Required throughout the Building Delivery Crane into position duration of this phase & Installation Connect Services to buildings.

An Environmental Management Plan (EMP) is required to mitigate the adverse environmental impacts during construction and operation phase of the project and these are discussed as follows. EMP for Air Construction Phase

10 2.5 To mitigate the impacts of PM & PM during the construction phase of the project, the following measures are recommended for implementation: The most cost-effective dust suppressant is water because water is easily available on construction site and it can be applied using water trucks, handled sprayers and automatic  sprinkler systems.  Incoming loads could be covered to avoid loss of material in transport, especially if material is transported off-site.  The whole site is covered with GI sheets in order to contain the dust within project site. Construction equipment is commonly left idle while the operators are on break or waiting for the completion of another task. Emission from idle equipment tends to be high, since catalytic converters cools down, thus reducing the efficiency of hydrocarbon and carbon monoxide oxidation. Existing idle control technologies comprises of power saving mode, which automatically off the engine at preset time and reduces emissions, without intervention from the operators. Significant emission reductions can be achieved through regular equipment maintenance. Contractors will be asked to provide maintenance records for their fleet as part of the contract

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 53 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

bid, and at regular intervals throughout the life of the contract. Incentive provisions will be established to encourage contractors to comply with regular maintenance requirements. Rapid on-site construction would reduce the duration of traffic interference and therefore, Operation Phase will reduce emissions from traffic delay.

To mitigate the impacts of pollutants from DG set and vehicular traffic during the operational phase of Proposed Project, following measures are recommended for implementation: Adequate stack height of 30 m will be maintained to disperse the air pollutants generated from the operation of DG set to dilute the pollutants concentration within the immediate vicinity. Hence no additional emission control measures have been suggested.  During construction, vehicles will be properly maintained to reduce emission. As it is a Redevelopment project, vehicles will be generally having “PUC” certificate. Adequate footpaths and pedestrian ways would be provided at the site to encourage non- polluting methods of transportation. EMP FOR NOISE Construction Phase

To mitigate the impacts of noise from construction equipment during the construction phase on the site, the following measures are recommended for implementation.  Noisy construction equipment would not be allowed to use at night time. Workers employed in high noise areas will be employed on shift basis. Hearing protection such as earplugs/muffs will be provided to those working very close to the noise generating machinery. Operation Phase

To mitigate the impacts of noise from diesel generator set during operational phase, the following measures are recommended: DG set will be housed in a suitable acoustic enclosure so that noise level at a distance of 1 m does not exceed 25 dB(A) as per CPCB standards or is meeting the local standard (whichever is higher). It would be ensured that the manufacturer provides acoustic enclosure as an integral part along with the diesel generators set. EMP FOR WATER: Construction Phase

To prevent degradation and to maintain the quality of the water source, adequate control measures needs to be adopted. The prime objective is to check the surface run-off as well as uncontrolled flow of water into any water body. The following management measures are suggested to protect the water source being polluted during the construction phase:  Avoid excavation during monsoon season  Care would be taken to avoid soil erosion Common toilets will be constructed on site during construction phase and the waste water would be channelized to the soak pits in order to prevent waste water to enter into any water body Any area with loose debris within the site shall be planted Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 54 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

To prevent surface and ground water contamination by oil and grease, leak-proof containers would be used for storage and transportation of oil and grease. The floors of oil and grease handling area would be kept effectively impervious. Any wash off from the oil and grease handling area or workshop shall be drained through imperious drains All stacking and loading area will be provided with proper garland drains, equipped with Operation Phase baffles, to prevent run off from the site, to enter into any water body.

In the operation phase of the project, water conservation and development measures will be taken. Following measures will be adopted:  Minimizing water consumption. Promoting reuse of water after treatment and development of closed loop systems for different water streams. Water Conservation

The water conservation is the need of the hour and consumption of fresh water will be minimized by combination of water saving devices and other domestic water conservation measures. Further, to ensure ongoing water conservation, an awareness program will be introduced for the staff. The following section discusses the specific measures, which shall be Domestic and Commercial Usage implemented:

 Use of water efficient plumbing fixtures (low flow sinks and WC cisterns). Water efficient plumbing fixtures uses less water with no marked reduction in quality and service  Leak detection and repair techniques.  Sweep with a broom and pan where possible, rather than hose down for external areas.  Meter water usage: Implies measurement and verification methods.  Monitoring of water uses is a precursor for management.  Horticulture Drip irrigation system shall be used for the lawns and other green area. Drip irrigation can  save 15-40% of the water, compared with other watering techniques.  Plants with similar water requirements shall be grouped on common zones to match precipitation heads and emitters.  Use of low-angle sprinklers for lawn areas.  Select controllers with adjustable watering schedules and moisture sensors to account for seasonal variations and calibrate them during commissioning. Storm Water Management Place 3 to 5 inches of mulch on planting beds to minimize evaporation.

Most of the storm water produced on site will be harvested to ground through bore well after passing through a holding tank/de-silting chamber. The proper management of water resource is a must to ensure that it is free from contamination. Contamination of Storm Water is possible from the following sources:  Diesel and oil spills in the diesel power generator and fuel storage area  Waste spills in the solid / hazardous waste storage area  Oil spills and leaks in vehicle parking lots Silts from soil erosion in gardens Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 55 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

  Spillage of sludge from sludge drying area of sewage treatment plant  Storm water management plan will incorporate best management practices which will include following:  Regular inspection and cleaning of storm drains  Covered waste storage areas  Avoid application of pesticides and herbicides before wet season  Secondary containment and dykes in fuel/oil storage facilities  Conducting routine inspection to ensure cleanliness Provision of slit traps in storm water drains EMP FOR WASTE: Construction Phase

The waste generated from construction activity includes construction debris, biomass from land clearing activities, waste from the temporary make shift labour hutments and hazardous waste. Following section discuss the management of each type of waste. Besides waste generation, Construction Debris management of the topsoil is an important area for which management measures are required.

Construction debris is bulky and heavy and re-utilization and recycling is an important strategy for management of such waste. As concrete and masonry constitute the majority of waste generated, recycling of this waste by conversion to aggregate can offer benefits of reduced landfill space and reduced extraction of raw material for new construction activity. Mixed debris with high gypsum, plaster, shall not be used as fill, as they are highly susceptible to contamination, and will be send to designated solid waste composting site. Metal scrap from structural steel, piping, concrete reinforcement and sheet metal work shall be removed from the site by construction contractors. A significant portion of wood scrap will be reused on site. Recyclable wastes such as plastics, glass fiber insulation, roofing etc shall be sold Hazardous waste to recyclers.

Construction sites are sources of many toxic substances such as paints, solvents wood preservatives, pesticides, adhesives and sealants. Hazardous waste generated during construction phase shall be stored in sealed containers and disposed off as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016. Some management practices to be developed are:  Herbicides and pesticide will not be over applied (small-scale applications) and not applied prior to rain. Paintbrushes and equipment for water and oil based paints shall be cleaned within a contained area and will not be allowed to contaminate site soils, water courses or drainage systems. Provision of adequate hazardous waste storage facilities. Hazardous waste collection containers will be located as per safety norms and designated hazardous waste storage areas will be away from storm drains or watercourses.  Segregation of potentially hazardous waste from non-hazardous construction site debris.  Well labeled all hazardous waste containers with the waste being stored and the date of generation. Instruct employees and subcontractors in identification of hazardous and solid waste. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 56 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Even with careful management, some of these substances are released into air, soil and water and many are hazardous to workers. With these reasons, the best choice is to avoid their use as much as possible by using low-toxicity substitutes and low VOC (Volatile Organic Compound) materials. Waste from Labour Hutments

Labour hutments have been made away from the site. However, Wastes generated from temporary make shift labor hutments will mainly comprise of household domestic waste, which will be managed by the contractor of the site. The wastewater generated will be channelized to Top Soil Management the septic tank.

To minimize disruption of soil and for conservation of top soil, the contractor has kept the top soil cover separately and stockpiles it. After the construction activity is over, top soil will be utilized for landscaping activity. Other measures, which would be followed to prevent soil erosion and contamination includes:  Maximize use of organic fertilizer for landscaping and green belt development. To prevent soil contamination by oil/grease, leak proof containers would be used for storage and transportation of oil/grease and wash off from the oil/grease handling area shall be drained through impervious drains and treated appropriately before disposal. Removal of as little vegetation as possible during the development and re-vegetation of  bare areas after the project.  Working in a small area at a point of time (phase wise construction). Operational Phase Construction of erosion prevention troughs/beams. R R R R The philosophy of solid waste management at the proposed Project will be to encouraging the four R’s of waste i.e. eduction, euse, ecycling and ecovery (materials & energy). Regular public awareness meetings will be conducted to involve the staff in the proper segregation and storage techniques. The Environmental Management Plan for the solid waste focuses on three major components during the life cycle of the waste management system i.e., collection and transportation, treatment or disposal and closure and post-closure care of treatment/disposal facility. Collection and Transportation 

During the collection stage, the solid waste of the project will be segregated into biodegradable waste and recyclable waste. Biodegradable waste and recyclable waste will be collected in separate bins. Biodegradable waste will be treated in the project premises by organic waste converter. The recyclable wastes will be sent off to recyclers. Proper guidelines for segregation, collection and storage will be prepared as per Solid waste Management Rules, 2016. To minimize littering and odour, waste will be stored in well-designed containers/ bins that will be located at strategic locations to minimize disturbance in traffic flow. Care would be taken such that the collection vehicles are well maintained and generate minimum noise and emissions. During transportation of the waste, it will be covered to avoid littering.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 57 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Figure 9: Waste Management Flow Diagram (Operation Phase)

Disposal

With regards to the disposal/treatment of waste, the management will take the services of the authorized agency for waste management and disposal of the same on the project site during its operational phase. EMP FOR ECOLOGY & BIODIVERSITY

Construction activity changes the natural environment. But the project also creates a built environment for its inhabitants. The project requires the implementation of following choices Construction Stage exclusively or in combination. 

 Restriction of construction activities to defined project areas, which are ecologically sensitive Restrictions on location of temporary labor hutments and offices for project staff near the project area to avoid human induced secondary additional impacts on the flora and fauna species Cutting, uprooting, coppicing of trees or small trees if present in and around the project site for cooking, burning or heating purposes by the labors will be prohibited and suitable  alternatives for this purpose will be made Along with the construction work, the peripheral green belt would be developed with suggested native plant species, as they will grow to a full-fledged covered at the time of Operation Stage completion.  Improvement of the current ecology of the project site will entail the following measures:  Plantation and Landscaping Avenue Plantation Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 58 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Plantation and landscaping The section below summarizes the techniques to be applied to achieve the above objectives:

Selection of the plant species would be done on the basis of their adaptability to the existing geographical conditions and the vegetation composition of the forest type of the region earlier Avenue Plantation found or currently observed. 

 Gardens maintained for recreational and ornamental purposes will not only improve the quality of existing ecology at the project site but also will improve the aesthetic value.  Avenue Plantation  Trees with colonial canopy with attractive flowering.  Trees with branching at 7 feet and above.  Trees with medium spreading branches to avoid obstruction to the traffic. Fruit trees to be avoided because children may obstruct traffic and general movement of EMPpublic. for Socio-Economic conditions

The social management plan will be designed to take proactive steps and adopt best practices, which are sensitive to the socio-cultural setting of the area. The Social Management Plan for Income Generation Opportunity during Construction and Operation Phase Redevelopment project focuses on the following components:

The Redevelopment project would provide employment opportunity during construction and operation phase. There would also be a wide economic impact in terms of generating opportunities for secondary occupation within and around the Project. The main principles considered for employment and income generation opportunities are out lined below:  Employment strategy will provide for preferential employment of local people Conditions of employment would address issues like minimum wages and medical care for the workers. Contractors would be required to abide to employment priority towards locals and abide by the labor laws regarding standards on employee terms and conditions Improved Working Environment for Employees

The Redevelopment project would provide safe and improved working conditions for the workers employed at the facility during construction and operation phase. With the proposed ambience and facilities provided, the proposed project will provide a new experience in living, work environment, seem less data transfer, edge cutting technologies etc. Following measures would be taken to improve the working environment of the area:  Less use of chemicals and biological agents with hazard potential  Developing a proper interface between the work and the human resource through a system of skill improvement  Provision of facilities for nature care and recreation e.g. indoor games facilities  Measures to reduce the incidence of work related injuries, fatalities and diseases Maintenance and beautifications of the complex and the surrounding roads.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 59 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

EMP FOR ENERGY CONSERVATION

Energy conservation program will be implemented through measures taken both on energy demand and supply.

Figure 10: Energy Conservation measures

Energy conservation will be one of the main focuses during the proposed project planning and  Architectural design operation stages. The conservation efforts would consist of the following:  Maximum utilization of solar light will be done.  Maximize the use of natural lighting through design. The orientation of the buildings will be done in such a way that maximum daylight is  available. The green areas will be developed, so that a significant reduction in the temperature can  Energy Saving Practices take place.  Energy efficient lamps will be provided within the Redevelopment project.  Constant monitoring of energy consumption and defining targets for energy conservation. Adjusting the settings and illumination levels to ensure minimum energy used for desired  Behavioral Change on Consumption comfort levels.  Promoting staff awareness on energy conservation Training staff on methods of energy conservation and to be vigilant to such opportunities. ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN

For the effective and consistent functioning of the complex, an Environmental Management system (EMS) would be established at the site. The EMS would include the following:  Environmental management cell.  Environmental Monitoring.  Personnel Training.  Regular Environmental audits and Correction measures. Documentation – standards operation procedures Environmental Management Plan and other records.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 60 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

ENVIRONMENTAL MANAGEMENT CELL

Apart from having an Environmental Management Plan, it is also proposed to have a permanent organizational set up charged with the task of ensuring its effective implementation of mitigation measures and to conduct environmental monitoring. The major duties and responsibilities of Environmental Management Cell shall be as given below:  To implement the environmental management plan.  To assure regulatory compliance with all relevant rules and regulations.  To ensure regular operation and maintenance of pollution control devices.  To minimize environmental impact of operations as by strict adherence to the EMP.  To initiate environmental monitoring as per approved schedule.  Review and interpretation of monitored results and corrective measures in case monitored results are above the specified limit. Maintain documentation of good environmental practices and applicable environmental  laws for a ready reference.  Maintain environmental related records.  Coordination with regulatory agencies, external consultants, monitoring laboratories. Maintenance of log of public complaints and the action taken. Structure of Environmental Management Cell

Normal activities of the EMP cell would be supervised by a dedicated person who will report to the site manager/coordinator of the Redevelopment Project. The hierarchical structure of suggested Environmental Management Cell is given in following Figure 11.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 61 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot No. 1, Sector 21, Dwarka, Delhi

Rep from Corporate Site Corporate Environmental Manager Planning group Division

Site Environmental Coordinator

Sewage & effluent Landscape Dev. Treatment Plant Incharge Operator

Figure 11: Environnent Management Cell Structure

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 62 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot 1, Sector 21, Dwarka, Delhi

Table 16: Summary Of Management Measures And Responsibility S. No. Environmental Potential Impacts Potential Source of Management Measures Responsibility Issues (Direct/ Indirect) Impact

Execution/ Supervision Civil Work   1. Ground Water Ground Water Construction Phase No surface accumulation will be allowed. Contractor Project Quality Contamination Waste water generated Proponent (SHE from temporary labor  division)  hutments. Operation Phase The sewage will be discharged to the Project Project Discharge from the municipal sewer after prior permission Proponent Proponent (SHE  project division) 2. Ground Water Ground Water Construction Phase Not Applicable None Not applicable Quantity Depletion Ground water will not use during construction   phase. Operation Phase  Black and Grey water treatment and Project Project The source of water reuse. Proponent Proponent (SHE during operation Rainwater will be harvested to ground. division) phase is Municipal  Awareness Campaign to reduce the water  Supply. consumption. 3. Surface Water Surface water Construction Phase Silt traps and other measures such as Contractor Project Quality contamination Surface runoff from site additional onsite diversion ditches will be Proponent (SHE during construction constructed to control surface run-off during division)  activity. site development Operation Phase Domestic water will be treated into STP of Project Project Discharge of domestic capacity 700 KLD Proponent Proponent (SHE wastewater STP of  division)  capacity 700 KLD  4. Air Quality Dust Emissions Construction Phase Regular sprinkling Contractor Project All heavy construction  Covered transportation of construction Proponent (SHE activities material division) Covered storage of loose material Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 63 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot 1, Sector 21, Dwarka, Delhi

S. No. Environmental Potential Impacts Potential Source of Management Measures Responsibility Issues (Direct/ Indirect) Impact

Execution/ Supervision Civil Work    Arrangement of wheel wash  Covering of project site with GI sheets Emissions of PM, Construction Phase Rapid on-site construction and improved Contractor Project 2 2 SO , NO and CO Operation of maintenance of equipment. Proponent (SHE construction equipment division)  and vehicles during site development. Running D.G. set (back  up)  Operation Phase Use of low sulphur diesel if available Project Project  Power generation by DG Providing Footpath and pedestrian ways Proponent Proponent (SHE Set during power failure within the site for the staff. division) Emission from vehicular Green belt will be developed with specific traffic in use  species to help to reduce pollution level Use of equipment fitted with silencers Proper maintenance of equipment.

5. Noise  Environment   Operation Phase Green area Development Project Project Noise from vehicular  Development of silence zones to check the Proponent Proponent movement traffic movement (SHE division) Provision of noise shields near the heavy  construction operations and acoustic enclosures for DG set. Noise from DG set  Construction activity is limited to day time operation hours only DG set will be equipped with acoustic Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 64 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot 1, Sector 21, Dwarka, Delhi

S. No. Environmental Potential Impacts Potential Source of Management Measures Responsibility Issues (Direct/ Indirect) Impact

Execution/ Supervision Civil Work

  enclosures 6. Land Environment Soil contamination Construction Phase Construction debris will be collected and Contractor Project Disposal of suitably used on site as per the solid waste Proponent  construction debris management plan for construction phase. (SHE division) Operation Phase It is proposed that the solid waste generated Project Project  Generation of will be managed as per Solid Waste Proponent Proponent municipal solid waste Management Rules, 2016 (SHE division) Used oil generated Collection, segregation, transportation and from D.G. set disposal will be done as per Solid Waste  Management rule, 2016 by the authorized agency.  Used oil generated will be sold to authorized  recyclers 7. Biological Displacement of Construction Phase Important species of trees, if any, will be Contractor Project Environment Flora and Fauna on Site Development identified and marked and will be merged Proponent (Flora and Fauna) site  during construction with landscape plan. (SHE division) Operation Phase Suitable green areas will be developed as per Project Project Increase in green landscaping plan in and around the site using Proponent Proponent  covered area local flora (SHE division) 8. Socio-Economic Population Construction Phase It is as per Master Plan. Contractor Project Environment displacement and Construction activities Proponent loss of income  leading to relocation (SHE division) Operation Phase Project Proponent will provide employment Project Project Site operation opportunities to the local people in terms of Proponent Proponent labor during construction and service (SHE division)  personnel (guards, securities, gardeners etc)  during operations Providing quality-Integrated infrastructure. 9. Traffic Pattern Increase of Construction Phase Heavy Vehicular movement will be restricted Contractor Project Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 65 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot 1, Sector 21, Dwarka, Delhi

S. No. Environmental Potential Impacts Potential Source of Management Measures Responsibility Issues (Direct/ Indirect) Impact

Execution/ Supervision Civil Work 

vehicular traffic Heavy Vehicular to daytime only. Proponent movement during (SHE division) construction   Operation Phase Vehicular movement will be regulated inside Project Project Traffic due to staff the project with adequate roads and parking Proponent Proponent once the project is lots in the project. (SHE division) operational

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 66 Project Name Residential Cum Training Complex for Special Protection Group Project Proponent Special Protection Group, Cabinet Secretariat, Govt of India Form IA Project Address Plot 1, Sector 21, Dwarka, Delhi

ENVIRONMENTAL MONITORING

The purpose of environmental monitoring is to evaluate the effectiveness of implementation of Environmental Management Plan (EMP) by periodic monitoring. The important environmental parameters within the impact area are selected so that any adverse effects are detected and time action can be taken. The project proponent will monitor ambient air Quality, Ground Water Quality and Quantity, and SoiTablel Quality17: Environmental in accordance withMonitoring an approved Plan – Constructionmonitoring schedule. Phase Source Monitoring Location Parameters to be Frequency Monitored

Ambient Air At 1 location at boundary of 2.5 10 2 2, As per recommendation of PM , PM , SO ,NO CO Quality the project site. Environment cell At 1 location at boundary of Day and night equivalent As per recommendation of Ambient Noise the project site. noise level Environment cell At 1 location nearest to the As per recommendation of Ground water As per standards project site. Environment cell At 1 location outside the As per recommendation of Soil As per standards project site. Environment cell Table 18: Environmental Monitoring Plan – Operation Phase Source Monitoring Location Parameters to be Frequency Monitored

DG set 2 2 As per recommendation of DG stacks PM, SO , NO emissions Environment cell At 0.5 m distance from As per recommendation of DG set noise Noise level enclosure Environment cell pH, BOD, Suspended Solid, As per recommendation of STP Inlet and Outlet Oil & Grease Environment cell Ambient Air 2.5 10 2 2, As per recommendation of Project Site PM , PM , SO ,NO CO Quality Environment cell Day and night equivalent As per recommendation of Ambient Noise Project Site noise level Environment cell Awareness and Training

Training and human resource development is an important link to achieve sustainable operation of the facility and environment management. For successful functioning of the project, relevant EMP Staff and Contractors would be communicated to:

Staff must be made aware of the importance of waste segregation and disposal, water and energy conservation. The awareness can be provided by periodic integrated meetings. They would be Environmental Audits and Corrective Action Plans informed of their duties.

The project is envisaged for IGBC Gold star rating also. To assess whether the implemented EMP is adequate, periodic environmental audits will be conducted by the project proponent. These audits will be followed by Correction Action Plan (CAP) to correct various issues identified during the audits. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant 67