City Accepted Amount AIRDRIE
Replace a fire truck. $1,605,070
Design and construct a pedestrian tunnel. $1,807,830
Upgrade the traffic signal system. $570,800
Rehabilitate several roads and curbs. $1,224,300
Design and construct a transit storage and maintenance facility. $2,150,000 BEAUMONT
Upgrade portions of roads. $1,750,000 BROOKS
Upgrade a portion of roads and sidewalks. $1,006,344 CALGARY
Upgrade several fire stations. $4,567,000
Rehabilitate several light rail transit stations. $5,211,461
Construct affordable housing units. $10,145,897
Construct a bus maintenance and storage facility. $35,681,998
Construct the Varsity Multi-Service Centre. $9,987,840
Construct Foothills Athletic Park and Fieldhouse. $95,000,000
Develop preliminary engineering studies for the Northeast and $1,719,432 South light rail transit line extensions.
Prepare roadway engineering plans. $2,838,339
Design and construct a pedestrian bridge across 14 Street and 90 $5,746,383 Avenue Southwest.
Construct the Arts Commons theatre facility. $25,000,000 CAMROSE
Construct a fire training facility. $650,000
Rehabilitate several roads and sidewalks. $1,878,000 CHESTERMERE
Purchase fitness equipment for the fire department. $335,000
Replace municipal entrance signs. $586,000
Upgrade information technology hardware. $442,000
Purchase public works equipment. $515,000
Purchase peace officer vehicles. $201,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 1 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
CHESTERMERE
Purchase garbage carts. $502,000 COLD LAKE
Install water pressure reducing valves. $750,000
Rehabilitate a portion of roads. $984,640
Develop taxiways at the Cold Lake Regional Airport. $700,000
Install water meter communication towers. $325,000
Construct an animal shelter. $1,200,000
Purchase a water quality management and monitoring system. $250,000
Purchase and install community park information signs. $250,000
Construct a bike park. $400,000
Construct a boardwalk and amphitheatre at Kinosoo Beach. $999,900 EDMONTON
Upgrade the Shaw Conference Centre, including windows and $1,917,300 lighting.
Rehabilitate the D.L. MacDonald light rail transit garage. $3,087,500
Upgrade the Sir Wilfrid Laurier Park. $3,142,800
Remove and replace the light rail transit tracks at 66 Street. $6,775,534
Construct a maintenance building at Fort Edmonton Park. $5,720,400
Replace the Harbin Gate. $1,000,000 FORT SASKATCHEWAN
Rehabilitate several roads. $6,508,755
Replace a portion of roads and underground infrastructure. $2,452,000
Rehabilitate Veterans Way. $8,700,000
Rehabilitate Point Aux Pins Road, including street lighting. $1,326,243
Upgrade 112 Street, including road widening. $1,300,000 GRANDE PRAIRIE
Rehabilitate the storm waterlines and culverts. $1,000,000
Upgrade railway crossings. $1,000,000
Upgrade the curling rink ice plant. $722,000
Replace and construct new sidewalks. $603,230
Rehabilitate several roads. $4,870,351
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 2 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
LACOMBE
Rehabilitate a portion of Northstar Drive, including underground $299,775 utilities.
Upgrade Northstar Drive between the Valley Crescent entrances. $915,631
Upgrade the Highway 2A service road. $1,482,278
Rehabilitate 50 Avenue between 58 Street and 76 Street. $467,160 LEDUC
Rehabilitate several back lanes. $1,325,000
Upgrade a portion of Black Gold Drive. $4,332,100
Replace a fire engine. $825,000
Upgrade the Protective Services building, including roof. $676,769 LETHBRIDGE
Upgrade the Shooting Sports Facility in Peenaquim Park. $1,688,000
Upgrade several road intersections. $3,965,000
Rehabilitate portions of roads. $1,810,000
Update the transportation master plan. $1,000,000 LLOYDMINSTER
Upgrade the Lloydminster Golf and Curling Centre water irrigation $1,086,000 system.
Replace the municipal airport emergency generator. $300,000
Upgrade a portion of 47 Avenue, including underground utilities. $1,397,906
Install and replace municipal entrance signs. $250,000
Upgrade traffic signals, including hardware and software. $466,000
Install traffic signals. $250,000 MEDICINE HAT
Rehabilitate the Strathcona Centre facility. $1,000,000
Upgrade the library, including the roof, air conditioning and boilers. $1,000,000
Upgrade the storm water infrastructure. $2,900,000
Rehabilitate several roads and sidewalks, including traffic signals $4,004,455 and underground utilities. RED DEER
Upgrade waterlines along 54 Avenue. $1,328,000
Upgrade traffic signal infrastructure. $1,176,000
Repave roads. $6,199,596
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 3 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
RED DEER
Reconstruct roads. $5,399,681
Upgrade street lights. $1,106,000 SPRUCE GROVE
Jointly construct the Royal Canadian Mounted Police facility with $3,341,861 the Town of Stony Plain.
Relocate the Eco-Centre facility. $690,000
Construct several public transit bus stops. $570,725
Purchase a public transit storage facility and buses. $1,281,197
Rehabilitate local roads. $990,000 ST. ALBERT
Rehabilitate arterial roads. $2,494,029
Rehabilitate collector roads. $1,440,000
Rehabilitate several roads. $957,400
Upgrade back lanes. $1,350,000
Upgrade intersections. $2,150,000
Widen Ray Gibbon Drive, including sidewalks. $780,000
Upgrade the storm water system. $1,751,500 WETASKIWIN
Install a fibre optic network. $91,677
Reconstruct a road intersection, including underground utilities. $300,000
Rehabilitate sidewalks and a parking lot. $310,000
Specialized Municipality Accepted Amount CROWSNEST PASS, MUNICIPALITY OF
Purchase a wheel loader. $430,000
Replace public works vehicles. $160,000
Purchase graders. $930,000
Purchase a backhoe. $185,000
Purchase a tandem axle truck. $120,000
Rehabilitate several parking lots. $215,000
Upgrade a portion of storm water, wastewater and waterlines. $1,250,000 JASPER, MUNICIPALITY OF
Construct a parking lot. $350,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 4 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
JASPER, MUNICIPALITY OF
Replace a fire rescue truck. $750,000
Upgrade the arena ice plant. $408,823
Replace the Aquatic Centre mechanical system. $202,000
Purchase a dump truck. $325,000
Renovate the Jasper Recreation Complex. $3,053,515 MACKENZIE COUNTY
Rehabilitate several roads and replace a bridge culvert. $1,067,750
Upgrade several recreational facilities. $269,000
Rehabilitate several roads. $2,215,000 STRATHCONA COUNTY
Upgrade Township Road 522 between Highway 21 and Range $5,490,000 Road 224.
Rehabilitate several roads. $9,540,000
Upgrade several roads. $6,238,653
Rehabilitate several recreational and community centres. $1,800,000
Expand the Strathcona Public Services Yard. $5,097,600
Upgrade County Hall, including energy efficient heating and $3,960,000 lighting.
Upgrade parks in the Hamlet of Ardrossan. $2,056,500
Widen Wye Road between Estate Drive and Clover Bar Road. $3,167,820
Upgrade the lift station in the Hamlet of Collingwood Cove. $1,350,000
Replace public transit buses. $1,335,420
Purchase public works equipment. $1,417,540
Municipal District Accepted Amount ATHABASCA COUNTY
Rehabilitate gravel roads. $786,632
Rehabilitate several roads. $1,500,000 BEAVER COUNTY
Replace a grader and packer. $566,667
Rehabilitate a portion of roads. $1,133,333
Gravel a portion of roads. $598,558
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 5 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
BIG LAKES COUNTY
Upgrade the administration building in the Hamlet of Kinuso. $100,695
Purchase public works vehicles and equipment. $867,100
Purchase a fire truck and a rescue unit for the hamlets of Enilda $109,866 and Joussard.
Rehabilitate a bridge. $844,170
Pave a parking lot and prepare roadway engineering plans for the $206,864 hamlets of Enilda and Grouard.
Construct a Family and Community Support Services building. $293,913
Construct an animal impound facility. $300,000
Purchase a fire truck. $200,000
Rehabilitate the storm water drainage system at the High Prairie $500,000 Airport.
Rehabilitate several roads in the Hamlet of Grouard. $500,000 BIGHORN NO. 8, M.D. OF
Replace a fire truck. $165,000
Replace garbage bins. $120,000 BIRCH HILLS COUNTY
Purchase public works equipment. $618,400
Haul gravel for road rehabilitation. $413,293 BONNYVILLE NO. 87, M.D. OF
Reconstruct and pave a portion of Range Road 485. $3,522,200
Repave roads and sidewalks in the Hamlet of Ardmore. $2,635,560 BRAZEAU COUNTY
Construct a trail between Brazeau Sports Park and Range Road $166,650 73.
Rehabilitate roads in the Hamlet of Cynthia. $1,386,000
Replace a portion of waterline in the Hamlet of Cynthia. $1,688,000
Replace a portion of wastewater line in the Hamlet of Cynthia. $737,000
Contribute funding to the Town of Drayton Valley to construct an $3,900,000 aquatic facility. CAMROSE COUNTY
Rehabilitate gravel roads. $699,914
Rehabilitate a portion of the alley between McGill Street and $50,077 Beaver Street.
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 6 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
CAMROSE COUNTY
Upgrade a portion of MacQuarrie Avenue, including water and $9,506 wastewater lines.
Upgrade the water and wastewater facility. $125,958
Rehabilitate portions of Township Road 464 and 460, and Range $3,434,875 Road 171.
Rehabilitate gravel roads. $619,319 CARDSTON COUNTY
Purchase a grader. $272,700
Replace a grader. $295,200
Purchase a public works vehicle. $143,800
Crush gravel for road maintenance. $405,446
Crush gravel for roads. $405,446 CLEARWATER COUNTY
Replace bridge culvert 70149. $437,000
Replace a bridge. $795,000
Replace bridge culvert 81567. $410,000
Replace bridge 9970. $1,275,582
Rehabilitate bridge culvert 78043. $360,000
Replace bridge culvert 70707. $437,000 CYPRESS COUNTY
Rehabilitate portions of roads. $1,403,660
Rehabilitate several bridges. $337,974
Upgrade roads and underground infrastructure in the Hamlet of $3,763,295 Seven Persons. FLAGSTAFF COUNTY
Conduct an assessment of the wastewater lagoon in the Hamlet of $295,000 Strome.
Upgrade the water treatment plant in the Hamlet of Galahad. $158,812
Rehabilitate and replace several bridges. $278,271
Drill a water well in the Hamlet of Galahad. $250,000 FOOTHILLS COUNTY
Purchase public works maintenance equipment. $1,252,050
Purchase a grader. $530,000
Crush gravel for road maintenance. $1,300,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 7 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
FOOTHILLS COUNTY
Contribute funding to the Millarville Racing and Agricultural Society $150,000 to expand the water storage system.
Contribute funding to the Priddis Greens Services Co-op Limited to $250,000 upgrade the water and wastewater treatment plants. GRANDE PRAIRIE NO. 1, COUNTY OF
Rehabilitate several roads. $2,962,845
Rehabilitate several south division roads. $10,085,620 KNEEHILL COUNTY
Rehabilitate a portion of Range Road 24-4 and 24-5. $2,422,603 LAC STE. ANNE COUNTY
Purchase graders. $910,350 LACOMBE COUNTY
Crush gravel for road rehabilitation. $463,277
Pave a portion of Centreview Road. $3,519,000
Pave a portion of Range Road 231. $1,132,000 LAMONT COUNTY
Purchase a public works truck and equipment. $377,000 LEDUC COUNTY
Rehabilitate several roads and bridges. $1,738,560
Upgrade the bulk water filling station. $640,000
Purchase fire trucks. $1,067,500 LETHBRIDGE COUNTY
Rehabilitate roads in the Sunset Acres subdivision. $747,000
Rehabilitate roads in the Stewart Siding Industrial Park. $560,000
Rehabilitate roads in the Broxburn Business Park. $454,000
Rehabilitate a portion of Range Road 21-4. $250,000
Rehabilitate roads in Riverbank Estates. $153,000
Reconstruct a portion of Range Road 23-2. $250,000
Upgrade roads and underground infrastructure in the Hamlet of $623,900 Shaughnessy.
Rehabilitate several gravel roads. $869,000
Rehabilitate several roads. $547,420
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 8 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
MINBURN NO. 27, COUNTY OF
Replace a portion of waterline in the Hamlet of Lavoy. $203,878
Purchase gravel for road rehabilitation. $773,608
Gravel several roads. $543,778 MOUNTAIN VIEW COUNTY
Crush gravel for road rehabilitation. $420,000
Rehabilitate gravel roads. $2,050,000
Stabilize a portion of roads. $800,000
Extend the Olds-Didsbury Airport runway. $170,342
Rehabilitate roads. $452,000
Rehabilitate portions of roads. $180,000 NORTHERN SUNRISE COUNTY
Regravel several roads. $1,169,392 PAINTEARTH NO. 18, COUNTY OF
Purchase graders. $814,000
Replace the Lake Thelma Bridge. $300,000
Rehabilitate the Weber Bridge. $1,060,000
Purchase an excavator and graders. $880,000 PARKLAND COUNTY
Resurface several roads. $2,165,000
Reconstruct a bridge. $620,000 PEACE NO. 135, M.D. OF
Rehabilitate gravel roads. $270,000
Purchase a public works maintenance vehicle. $275,000 PINCHER CREEK NO. 9, M.D. OF
Upgrade Summerview Road. $550,000
Upgrade Kerr Road. $600,000
Upgrade roads and drainage system in the Hamlet of Lundbreck. $400,000
Replace culverts along Willow Valley Road. $500,000
Upgrade the Global Postioning System and Geographic $53,000 Information Systems.
Purchase a security system for the public works yard and $85,000 administration building.
Rehabilitate a portion of Range Road 29-3. $150,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 9 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
PINCHER CREEK NO. 9, M.D. OF
Reconstruct a portion of Southfork Road. $1,963,250
Replace a bridge. $978,000 PONOKA COUNTY
Rehabilitate several roads. $3,301,955 PROVOST NO. 52, M.D. OF
Rehabilitate a portion of Range Road 15. $2,738,334 RANCHLAND NO. 66, M.D. OF
Rehabilitate gravel roads. $100,000 RED DEER COUNTY
Reconstruct Township Road 370. $3,221,544
Pave a portion of Range Road 275 along the C & E Trail. $314,947 ROCKY VIEW COUNTY
Upgrade a portion of Township Road 250. $800,000
Upgrade a portion of Range Road 290. $1,000,000
Construct a fire station. $9,000,000
Upgrade a portion of Dickson Stevenson Trail. $1,100,000 SMOKY LAKE COUNTY
Rehabilitate portions of roads, including Township Road 594 and $240,000 Range Road 152.
Upgrade and stabilize roads. $512,000
Gravel roads. $457,251
Replace a grader. $400,000 SMOKY RIVER NO. 130, M.D. OF
Gravel portions of roads. $200,000
Rehabilitate roads. $757,318
Conduct a drainage study on Township Road 765. $75,000
Replace bridge culverts. $182,750 SPIRIT RIVER NO. 133, M.D. OF
Purchase an excavator. $140,000
Purchase mowers. $225,000
Rehabilitate gravel roads. $168,680
Expand and rehabilitate the administration building, including $410,000 accessibility features.
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 10 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
ST. PAUL NO. 19, COUNTY OF
Rehabilitate Township Road 590E between Highway 36 and $1,704,104 Highway 881.
Replace public works maintenance equipment. $831,000 STETTLER NO. 6, COUNTY OF
Upgrade the storm water system in the Hamlet of Botha. $485,658 STURGEON COUNTY
Rehabilitate a portion of Range Road 245 and Glenview Acres $813,000 subdivision.
Reconstruct roads, including the purchase of right-of-ways. $1,794,000
Purchase gravel and rehabilitate roads. $550,000
Pave a portion of Range Road 230. $1,000,000 TABER, M.D. OF
Rehabilitate gravel roads. $647,791
Replace a storm water culvert. $150,000
Construct a highway rest area. $900,000
Rehabilitate a portion of Range Road 18. $225,000 THORHILD COUNTY
Rehabilitate gravel roads. $494,189
Purchase a loader. $313,430 TWO HILLS NO. 21, COUNTY OF
Purchase public works maintenance equipment. $1,084,990
Rehabilitate wastewater lines in the Hamlet of Willingdon. $196,893
Rehabilitate several roads. $1,531,787
Upgrade a water filling station in the Hamlet of Willingdon. $80,000 VERMILION RIVER, COUNTY OF
Pave a portion of Range Road 14. $1,705,007
Rehabilitate gravel roads. $903,137 VULCAN COUNTY
Replace a tandem tractor. $184,481
Replace graders. $786,709
Rehabilitate bridges. $1,288,713 WARNER NO. 5, COUNTY OF
Rehabilitate gravel roads. $692,031
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 11 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
WARNER NO. 5, COUNTY OF
Rehabilitate asphalt roads. $1,152,732
Upgrade several roads. $1,433,123 WESTLOCK COUNTY
Resurface and rehabilitate several range and township roads. $1,358,235
Rehabilitate gravel roads. $1,600,000 WETASKIWIN NO. 10, COUNTY OF
Contribute funding to the Wetaskiwin Agricultural Society to $100,000 construct a multi-use building.
Construct the G3 Resource Road. $1,882,100
Contribute funding to the Mulhurst Lutheran Church Camp $50,000 Association to upgrade the campground shower and washroom facility. WHEATLAND COUNTY
Pave Glenmore Trail. $2,255,000
Upgrade a portion of Township Road 252. $2,520,000
Purchase graders and an excavator. $2,089,961 WILLOW CREEK NO. 26, M.D. OF
Rehabilitate several roads. $678,575
Purchase a fire pumper truck. $100,000 WOODLANDS COUNTY
Gravel roads. $930,100
Town Accepted Amount ATHABASCA
Replace a wastewater main. $498,968
Replace sidewalks. $50,000
Rehabilitate a portion of University Drive. $200,000 BASHAW
Replace a portion of water and wastewater lines along 54 Avenue, $446,849 including road rehabilitation.
Replace several fire hydrants. $40,000 BEAVERLODGE
Purchase an air compressor. $20,635
Install a wastewater bypass along 7 Avenue. $80,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 12 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
BEAVERLODGE
Purchase calcium containment storage tanks, pumps, and a $37,500 storage shed. BENTLEY
Rehabilitate portions of roads, including sidewalks and storm $455,503 waterlines. BLACK DIAMOND
Upgrade 6 Street, including underground utilities and water looping. $614,975
Install water and wastewater lines along 4 Street Southwest. $62,000
Rehabilitate a portion of wastewater line. $44,520
Construct a portion of water and wastewater lines. $1,477,506 BLACKFALDS
Purchase a building for the public works operations facility. $5,000,000 BON ACCORD
Rehabilitate 54 Street from Range Road 235 to 47 Street. $45,485
Rehabilitate a portion of 49 Avenue, including sidewalks and $322,046 underground utilities.
Rehabilitate the Bon Accord Arena. $29,312 BONNYVILLE
Upgrade a portion of 47 and 49 Street, including sidewalks and $646,420 underground utilities.
Pave several roads. $340,950 BOW ISLAND
Construct a portion of Highway 3. $150,000
Rehabilitate the airport runway and lighting. $240,328 BOWDEN
Upgrade wastewater lines and manholes. $138,150 BRUDERHEIM
Purchase a public works utility vehicle. $25,000
Purchase a skid steer and attachments. $50,000 CALMAR
Purchase a grader and loader. $397,822 CANMORE
Reconstruct several roads and sidewalks, including lighting and $3,375,000 underground utilities.
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 13 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
CARDSTON
Purchase public works equipment. $194,000
Replace a portion of road, including sidewalks and underground $225,000 infrastructure.
Replace a portion of road and sidewalk along 3 Street East. $115,000
Rehabilitate a portion of roads. $205,000
Replace a portion of road and underground infrastructure along 6 $100,000 Street West.
Expand the Lee Creek Campground. $275,500 CASTOR
Upgrade the fire hall. $100,000
Upgrade wastewater and water systems. $112,500
Replace the boiler in the town hall. $11,000 CLARESHOLM
Convert and renovate a building into a multi-use community $202,380 complex.
Replace public works vehicles. $140,000
Prepare a storm water management plan. $151,433 COALHURST
Purchase a bylaw officer vehicle. $90,000 COCHRANE
Upgrade a portion of Quigley and Riverview Drive. $668,500
Upgrade George Fox Trail. $1,579,200 DAYSLAND
Replace a public works vehicle. $33,713 DIDSBURY
Upgrade 20 Street, including sidewalks and storm water facilities. $540,000 DRAYTON VALLEY
Construct an aquatic facility. $2,420,165 DRUMHELLER
Replace the Aquaplex air handling unit. $300,000
Purchase public works maintenance equipment. $300,000 ECKVILLE
Purchase public works equipment. $16,900
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 14 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
ECKVILLE
Purchase recycling collection bins. $45,500
Purchase a wastewater flow meter. $18,500
Purchase a public works truck. $60,000
Install solar powered street lights. $190,000
Rehabilitate a wastewater lift station. $23,000
Install a fibre internet network. $30,000
Upgrade the public works yard fence. $14,500
Construct a walking trail. $155,000 ELK POINT
Upgrade a wastewater lift station. $127,052 FAIRVIEW
Rehabilitate a portion of road. $700,000
Purchase a loader. $224,000 FORT MACLEOD
Purchase a vacuum truck. $350,000
Prepare a storm water management and drainage plan. $29,700
Prepare design and engineering plans for 17 Street upgrades. $65,000
Replace a portion of sidewalks. $75,000
Repave a portion of roads. $100,000 GIBBONS
Rehabilitate several roads, including sidewalks. $175,735
Rehabilitate the arena and curling rink parking lots. $174,384 GRIMSHAW
Replace the road and waterline along 45 Street and 56 Street. $682,715 HANNA
Rehabilitate roads. $1,070,000
Purchase a tandem axle truck. $65,000 HIGH LEVEL
Replace a street sweeper. $375,000
Replace the arena boards. $200,000
Upgrade the arena change rooms and washrooms. $60,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 15 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
HIGH PRAIRIE
Jointly upgrade the reservoir pump station with Big Lakes County. $304,500
Jointly rehabilitate the intersection of 56 Avenue and 50 Street, $605,000 including underground utilities, with Big Lakes County.
Replace municipal welcome signs. $25,000
Jointly upgrade the arena parking lot with Big Lakes County. $186,000
Upgrade a portion of 52 Avenue, including underground utilities $410,000 and manholes.
Enhance the downtown core, including lighting and landscape. $50,000
Upgrade a portion of 55 Avenue, including sidewalks, manholes, $260,000 and a fire hydrant.
Upgrade the first responders radio communication system. $60,000 HIGH RIVER
Upgrade and expand the fire hall. $7,340,000
Replace a grader. $375,000
Upgrade a lift station and decommission two lift stations. $1,600,000
Upgrade the main lift station generator. $250,000
Relocate utilities along Centre Street. $550,000
Upgrade the Bob Snodgrass Recreation Complex, including $735,900 lighting and parts of the roof.
Rehabilitate sidewalks and ramps. $250,000
Construct a pathway along 12 Avenue. $200,000
Replace the fire and emergency services radio systems. $325,000
Demolish the water tower and restore the site as a public park. $550,000
Replace the Bob Snodgrass Recreation Centre arena seats. $132,000
Rehabilitate the Bob Snodgrass Recreation Complex field $300,000 house parking lots.
Replace the Bob Snodgrass Recreation Complex roof. $170,000
Remediate and restore municipal facilities. $190,000
Rehabilitate the downtown core, including roads, and underground $3,700,000 utilities.
Rehabilitate the Bob Snodgrass Recreation Complex, including the $275,000 aquatic electrical system.
Rehabilitate a wastewater lift station. $450,000 HINTON
Rehabilitate a portion of water and wastewater lines on Athabasca $2,100,000 Avenue.
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 16 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
INNISFAIL
Upgrade water and wastewater lines. $1,100,087
Repair and replace asphalt. $724,000 IRRICANA
Upgrade several recreational facilities. $36,457 KILLAM
Upgrade 51 Street, including underground utilities and sidewalks. $242,000 LAMONT
Rehabilitate roads, including water and wastewater lines. $607,712 LEGAL
Purchase a street sweeper. $125,000 MAGRATH
Replace sidewalks. $47,721
Install wastewater lines along 3 Avenue North and 2 Street West. $479,468
Install water and wastewater lines. $92,790
Construct a pedestrian tunnel under Highway 62. $171,337
Upgrade 2A Street East, including sidewalks, curbs and gutters. $284,000
Purchase a bucket truck. $45,000 MAYERTHORPE
Rehabilitate several sidewalks. $68,461
Purchase a mower. $20,000
Construct a skateboard and bike park. $75,000
Rehabilitate a wastewater lagoon. $66,920
Upgrade computers. $15,000
Rehabilitate a waterline. $61,748 MILLET
Rehabilitate a portion of 48 Avenue. $404,447
Upgrade the arena ice plant. $200,000 MUNDARE
Purchase public works vehicles. $50,000
Conduct an engineering study for lift station upgrades. $50,000
Replace sidewalks. $50,000
Reline wastewater lines. $229,550
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 17 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
NANTON
Replace water treatment equipment. $60,000 NOBLEFORD
Upgrade the lagoon. $265,000 OKOTOKS
Jointly construct the Okotoks Arts and Learning Campus with $18,300,000 the Christ The Redeemer Catholic School, including the purchase of land.
Purchase firefighting equipment. $345,000
Construct a pedestrian plaza. $250,000
Purchase land for park development. $1,282,500
Upgrade the information technology systems and equipment. $384,600
Purchase public works equipment and a patrol vehicle. $460,000
Upgrade the emergency operations centre. $300,000 OLDS
Replace the information technology network servers at municipally $255,360 owned facilities.
Purchase public works equipment. $558,000
Rehabilitate trails and upgrade a playground. $220,000
Construct and rehabilitate a portion of roads, including $1,075,360 underground utilities.
Upgrade the Sportsplex, including the arena ice plant chiller. $300,000 ONOWAY
Rehabilitate Township Road 544 and Range Road 21. $155,960
Replace sidewalks. $100,000
Upgrade the lift station and water plant roofs. $31,540
Purchase a water meter reader. $15,000
Pave a portion of 47 Avenue. $291,082 OYEN
Purchase a loader. $152,000
Upgrade the airport runway. $146,250 PENHOLD
Purchase public works equipment. $98,000
Rehabilitate Minto Street. $561,229
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 18 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
PINCHER CREEK
Rehabilitate roads and sidewalks. $218,000
Upgrade Thistle Crescent. $350,000
Upgrade a pump at the water retention pond. $150,000
Upgrade the wastewater treatment lagoon. $746,754 PONOKA
Upgrade a portion of 64 Street. $375,000
Rehabilitate several roads, including sidewalks and storm water $120,000 infrastructure.
Pave several roads. $850,000
Replace and purchase public work equipment. $245,000
Construct a parking lot at the Civic Centre. $350,000 RAINBOW LAKE
Upgrade cable and internet systems. $148,400
Purchase a bucket truck. $47,000 REDCLIFF
Upgrade roads, including water and wastewater lines along 4 $1,540,000 Street.
Purchase and install emergency generators. $50,000
Purchase and install a storm water and wastewater camera. $60,000
Upgrade the aquatic centre pools. $240,000
Purchase water meter radios. $77,000
Upgrade the splash park. $100,000 REDWATER
Prepare engineering plans for the heating, ventilation, and air $65,000 conditioning system at Pembina Place. RIMBEY
Upgrade roads and sidewalks. $541,228
Prepare design and engineering plans for 51 Street upgrades. $136,500 ROCKY MOUNTAIN HOUSE
Rehabilitate 59 Avenue from 54 Street to Highway 11. $201,000
Rehabilitate a wastewater lagoon. $1,629,320 SEDGEWICK
Upgrade the heating, ventilation, and air conditioning system at the $110,000 water treatment plant.
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 19 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
SEDGEWICK
Rehabilitate a portion of Main Street, including sidewalks and $300,000 underground facilities. SEXSMITH
Replace a portion of sidewalk. $103,825
Construct an asphalt pad next to the arena. $49,203
Rehabilitate the civic centre roof. $91,950
Purchase a snowblower. $132,290
Install storm water infrastructure along 99 Avenue. $204,365
Pave a portion of 95 Avenue. $764,569 SPIRIT RIVER
Replace the water and wastewater lines along McAlpine Crescent. $250,000 ST. PAUL
Purchase a tractor. $51,185
Replace a tractor. $45,000
Purchase public works equipment and upgrade the public works $789,900 shop.
Replace a portion of wastewater line along 51 Avenue. $145,000
Replace a portion of wastewater line along 52 Avenue. $130,000 STAVELY
Purchase a mower. $8,500
Prepare a water treatment plant assessment study. $30,000
Upgrade several roads, including an industrial subdivision. $30,000
Rehabilitate portions of roads. $8,750
Rehabilitate the wastewater lagoon. $8,750 STETTLER
Rehabilitate a portion of 51 Avenue and 49 Avenue. $369,210
Replace a portion of waterline along 52 Street. $280,000
Replace a portion of waterline and wastewater line along 57A $440,000 Street.
Upgrade a pumphouse. $150,000
Rehabilitate a wastewater lagoon. $300,000
Replace a portion of storm waterline along 57 Street. $100,000
Purchase a tandem truck. $170,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 20 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
STETTLER
Purchase a snow blower. $180,000 STONY PLAIN
Construct a cemetery. $2,000,000 STRATHMORE
Construct a municipal administration building, including park $9,626,129 facilities and trail system. SWAN HILLS
Purchase public works maintenance equipment and attachments. $160,000
Purchase a public works vehicle. $40,000
Pave several roads. $73,576 SYLVAN LAKE
Upgrade the NexSource Centre. $485,000
Construct an asphalt trail. $200,000
Rehabilitate a portion of Hunter Road. $450,000
Rehabilitate the roads in the village area, including underground $3,000,000 infrastructure.
Rehabilitate roads and sidewalks. $500,000
Upgrade Memorial Trail at 60 Street West. $400,000
Upgrade the intersection at Highway 20 and Memorial Trail. $650,000
Upgrade 50 Avenue between 33 and 50 Streets. $3,746,000
Construct a water reservoir. $3,000,000 TABER
Install a carbon dioxide system at the water treatment plant. $264,000
Replace the water and wastewater line along 52 Street. $569,425
Construct a fire hall and emergency services building. $404,000 THORSBY
Replace a portion of wastewater line along 47 Street between 49 $78,216 Avenue and 50 Avenue.
Pave a portion of roads. $21,955
Rehabilitate a portion of 48 Avenue. $339,298
Pave portions of 54 Avenue and 52 Street. $538,413 TOFIELD
Install solar powered lighting at the Tofield Airport. $18,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 21 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
TOFIELD
Replace a wastewater lift station. $560,000 TROCHU
Upgrade the water pump house. $23,000 TURNER VALLEY
Purchase a backhoe. $108,807
Pave a portion of alleyways. $58,890
Purchase a mobile fire service trailer. $38,396
Purchase a global positioning system. $18,620 VAUXHALL
Purchase a waste transfer vehicle. $130,000
Purchase a street sweeper. $75,000
Upgrade playground equipment. $75,000
Upgrade several sidewalks. $200,000 VEGREVILLE
Repave a section of 47A Street and 49 Avenue. $865,045 VERMILION
Upgrade the recreation centre change rooms. $60,000
Prepare plans and install the preliminary infrastructure for a $345,000 broadband internet network.
Purchase a fire truck. $700,000 VIKING
Replace a storm water culvert and rehabilitate drainage. $167,624 VULCAN
Construct a pool. $1,335,200
Upgrade storm water drainage along Highway 23. $280,000 WEMBLEY
Rehabilitate a portion of Township Road 712. $480,000
Purchase a paver. $265,000 WESTLOCK
Purchase a backhoe. $150,000
Reline the pool. $340,000
Rehabilitate the aquatic centre, including electrical and air handling $329,740 system.
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 22 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
WESTLOCK
Upgrade storm water infrastructure. $860,553
Village Accepted Amount ACME
Conduct an overland drainage study. $50,000
Replace several curb stops. $20,000
Replace several fire hydrants and water valves. $20,000
Upgrade a portion of wastewater lines. $50,000
Purchase and install water meters. $15,000
Purchase land to expand the campground. $45,000
Purchase a sanding truck. $15,000 AMISK
Construct and loop several waterlines along 50, 51 and 53 Street. $87,500
Install a portion of waterline. $155,000
Purchase office equipment. $10,000
Purchase and repair welcome signs. $12,000 ANDREW
Rehabilitate a portion of 53 Street and 53 Avenue. $213,140
Replace an administration building boiler. $18,000 ARROWWOOD
Purchase a skid steer and attachments. $100,000
Purchase computers and hardware for utility readings. $30,000
Rehabilitate the municipal office building. $30,000
Install fibre-optic infrastructure. $50,000
Contribute funding to the Northwest District Recreation Board to $50,000 construct a multi-use trail system.
Extend 2A Street East between 1 Avenue East and Railway $50,000 Avenue East, including underground utilities.
Prepare an asset management plan. $50,000 BEISEKER
Upgrade a wastewater lift station. $28,745
Upgrade a portion of water and wastewater lines. $20,000
Upgrade the water meter readers. $24,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 23 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
BEISEKER
Upgrade a portion of 3 Avenue. $255,385 BERWYN
Replace water main valves and infrastructure. $202,000 BIG VALLEY
Pave roadways. $155,000
Purchase public works vehicle. $26,000 BITTERN LAKE
Upgrade the waterline air release valves. $35,000
Purchase computers. $10,000
Upgrade the recreation area, including skating rink and $360,570 playground. BOYLE
Replace the water treatment plant roof. $25,690
Construct a dressing room in the arena. $25,554
Pave several roads. $270,974
Purchase land for the construction of a municipal centre. $320,585 BRETON
Rehabilitate a portion of roads. $34,860
Rehabilitate a wastewater lagoon. $60,700 CARMANGAY
Upgrade a portion of waterline and wastewater line. $250,347 CAROLINE
Replace a portion of 49 Avenue, including underground $1,150,000 infrastructure. CHAMPION
Construct a pathway. $125,000
Upgrade the public works building. $15,758 CHAUVIN
Pave a portion of roads. $120,000 CHIPMAN
Rehabilitate the Chipman National Hall. $105,200
Purchase a sanding truck. $39,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 24 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
CLYDE
Upgrade the water distribution plant and associated equipment. $98,750 COUTTS
Replace the main waterline and valves. $38,204
Replace a waterline and valve. $15,000
Pave portions of roads. $58,000 CREMONA
Pave several streets, including sidewalks. $187,000
Upgrade the water treatment plant. $28,400
Rehabilitate a portion of the storm water system along 1 Street $70,000 West. DELBURNE
Rehabilitate a portion of road. $80,000
Resurface several roads. $45,783
Construct roads and underground infrastructure in the Fawn $275,226 Meadows subdivision. DELIA
Upgrade a portion of water and wastewater line along 1 Avenue. $575,691
Replace several sidewalks. $152,000
Expand and upgrade the water reservoir. $764,405
Contribute funding to the Prairie Land School Division to $100,000 construct a library and gymnasium. DONNELLY
Upgrade a portion of waterline and replace a water main valve. $34,005
Inspect and rehabilitate a portion of wastewater line. $52,213
Rehabilitate roads and sidewalks. $334,553 EDBERG
Prepare a road, water and stormwater infrastructure study. $44,596
Purchase information technology equipment, including computers, $10,000 printers, monitors and office furniture.
Upgrade a portion of 1 Street South, including water and $175,504 wastewater utilities.
Upgrade the water tower. $13,000 EMPRESS
Purchase firefighting equipment. $10,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 25 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
FOREMOST
Expand the campground. $70,000
Prepare an asset management plan. $12,500
Purchase garbage bins. $38,000 FORESTBURG
Rehabilitate portions of 57 Street West and install a storm $300,000 water swale. GIROUXVILLE
Rehabilitate several roads. $15,000 GLENWOOD
Upgrade storm water drainage. $79,000 HALKIRK
Resurface gravel alleys. $10,000
Purchase mowers. $20,000
Expand and upgrade the fire hall. $180,000 HAY LAKES
Replace a portion of sidewalk. $45,044 HEISLER
Purchase a lift station heater and generator. $45,000
Replace water curb stops. $65,000
Rehabilitate a portion of Main Street. $25,000 HILL SPRING
Upgrade the SCADA system to integrate the lift station. $12,000
Replace a portion of sidewalk. $33,000
Replace a water pump. $22,254
Replace culverts. $18,000 HUGHENDEN
Replace a garbage truck and collection bins. $20,000 HUSSAR
Replace a portion of 2 Avenue, including sidewalks and $468,782 underground utilities. HYTHE
Upgrade a water well. $220,075
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 26 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
HYTHE
Upgrade a wastewater lift station, including security and alarm $33,184 system.
Reline the wastewater main. $235,996
Upgrade the administration building. $30,854
Develop and install a fibre-optic network. $115,000
Rehabilitate portions of 100 Street. $109,720 INNISFREE
Replace the public works truck. $30,000
Upgrade the administration building. $68,200
Rehabilitate the public works facility. $10,704
Replace the water treatment plant chlorine monitor. $6,650
Purchase a public works truck. $11,000
Purchase public works maintenance equipment. $10,000 LONGVIEW
Replace a portion of waterline and wastewater line. $964,165 LOUGHEED
Replace the administration building roof. $59,000
Replace water main valves. $248,684 MANNVILLE
Rehabilitate a portion of 52 Avenue. $228,000
Purchase computer hardware and security cameras. $21,500
Purchase an air compressor for the fire hall. $20,000
Purchase public works equipment. $38,000
Replace the roof on the water distribution building. $35,000
Upgrade the golf course kitchen. $15,000
Upgrade the roof on the golf course clubhouse. $15,000
Replace several water main valves. $20,000
Upgrade the public works and fire hall buildings. $17,000
Rehabilitate the arena road. $60,000
Replace the sidewalk along 50 Street. $20,000
Upgrade the downtown gazebo. $30,000
Upgrade the baseball diamonds and concession. $40,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 27 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
MARWAYNE
Upgrade a portion of roads and storm water infrastructure. $144,979 MILO
Replace the trees along Centre Street. $35,007
Upgrade waterlines and hydrants. $110,000 MYRNAM
Upgrade the Construction and Technology Education Centre. $133,000 NAMPA
Prepare an infrastructure management plan. $40,000
Upgrade a public works building. $30,000
Upgrade roads. $212,786 PARADISE VALLEY
Construct a water distribution plant. $693,700 ROCKYFORD
Replace fire hydrants. $42,500 ROSALIND
Rehabilitate a portion of roads. $93,609 ROSEMARY
Rehabilitate a portion of Rose Street and Iris Street. $321,210 RYCROFT
Install street lights along Highway 2 and Highway 49. $44,711 RYLEY
Reconstruct a portion of 52 Avenue between 52 Street and 57 $147,688 Avenue. SPRING LAKE
Construct a public works storage building. $55,000 STANDARD
Replace a portion of roads and underground infrastructure. $133,990 VETERAN
Contribute funding to the Special Areas Board for the construction $421,019 of a fire hall. WABAMUN
Upgrade the water treatment and distribution facility. $18,320
Replace the community hall air conditioning system. $30,490
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 28 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
WABAMUN
Rehabilitate roads and sidewalks. $120,000
Replace water main valves. $15,000
Upgrade the wastewater lagoon and lift station. $190,232
Upgrade storm water drainage. $14,000
Construct an ambulance parking lot. $10,000 WARBURG
Rehabilitate portions of 53 Street and 51 Avenue. $558,342 WARNER
Rehabilitate gravel roads. $51,000
Extend a portion of waterline and wastewater line. $125,000 WASKATENAU
Rehabilitate a portion of 50 Avenue. $372,624 YOUNGSTOWN
Upgrade the village public works shop. $30,500
Upgrade the library and village office. $15,000
Upgrade the curling rink chiller. $14,286
Upgrade the community hall. $21,716
Summer Village Accepted Amount BETULA BEACH
Upgrade a portion of Willow Road. $92,000
Construct a walking trail. $15,300
Upgrade the intersection of Kos Street, Birch Lane and Terrace $143,000 Avenue. BIRCHCLIFF
Conduct a drainage assessment of Birchcliff Road. $14,500
Conduct a traffic safety study. $6,000
Construct a pathway. $479,440 BURNSTICK LAKE
Purchase fire suppression equipment and construct a storage $95,000 facility. CRYSTAL SPRINGS
Rehabilitate a portion of Lakeview Drive. $300,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 29 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
GOLDEN DAYS
Install municipal addressing signage. $24,500
Reconstruct roads in the Vasa subdivison. $40,000
Purchase and install a speed sign. $5,000 GRANDVIEW
Construct Lakeshore Drive. $325,000 HALF MOON BAY
Design a wastewater collection system. $40,000
Prepare a design plan for the West Beach recreation area. $12,000
Purchase and install buoys and swim lines. $14,000
Upgrade entrance signs and a bulletin board. $50,000
Construct a recreational beach area, including a shelter and $80,000 pathways. HORSESHOE BAY
Rehabilitate several roads. $20,000 ISLAND LAKE
Pave several roads. $230,000 ITASKA BEACH
Rehabilitate a portion of roads, including dust abatement. $9,930
Rehabilitate the community entrance sign. $5,000
Rehabilitate a portion of road. $4,500
Purchase picnic tables and a park bench. $4,815 MA-ME-O BEACH
Design and reconstruct roads and sidewalks along 6 and 7 Street. $165,000 MEWATHA BEACH
Install community entrance signs. $8,412
Construct a park. $106,572
Rehabilitate portions of Mewatha Drive. $170,000 PARKLAND BEACH
Rehabilitate Parkland Place. $27,000
Rehabilitate Parkland Close. $24,000
Rehabilitate a portion of Parkland Drive. $92,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 30 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
PELICAN NARROWS
Construct Oriole Lane and rehabilitate Pelican Drive. $490,600 POINT ALISON
Install a roadway security camera. $6,205 POPLAR BAY
Rehabilitate Poplar Bay Drive. $405,000 SANDY BEACH
Rehabilitate a portion of roads. $65,592
Conduct a wastewater lagoon study. $20,000 SEBA BEACH
Rehabilitate a portion of 1 Avenue. $125,920 SILVER BEACH
Replace the entrance and informational signage. $30,000
Rehabilitate portions of Silver Beach Road. $225,000
Purchase and install radar speed signs. $10,000
Replace the playground equipment at Ouimette Park. $163,000 SUNDANCE BEACH
Replace an entrance sign and community bulletin board. $40,000
Purchase electronic speed road signs. $14,500
Rehabilitate gravel roads, including dust abatement. $38,500 SUNRISE BEACH
Purchase a sand and salt spreader. $8,000 SUNSET BEACH
Contribute funding to Athabasca County for the construction of a $30,000 pool and fitness centre. SUNSET POINT
Rehabilitate several park and municipal building entrances. $90,900
Rehabilitate the administration building. $110,000
Rehabilitate roads, including the storm water collection system. $236,000 WAIPAROUS
Install solar pedestrian crossing lights along Highway 40. $18,264
Engineer and upgrade the storm water drainage. $149,640
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 31 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
WHISPERING HILLS
Upgrade a portion of Whispering Hills Road. $203,870 YELLOWSTONE
Rehabilitate several roads. $224,517
Improvement District Accepted Amount I.D. NO. 04 (WATERTON)
Contribute funding to the Waterton Parks Community Association $353,000 to rehabilitate the Lions Hall.
Contribute funding to the Waterton Parks Community Association $125,000 to upgrade the spray park facility. I.D. NO. 13 (ELK ISLAND)
Purchase a loader. $278,460 I.D. NO. 25 (WILLMORE WILDERNESS)
Contribute funding to the Willmore Wilderness Foundation to $84,000 rehabilitate the trail system. KANANASKIS IMPROVEMENT DISTRICT
Purchase automatic external defibrillators. $8,263
Purchase firefighting equipment. $377,907
Replace public safety equipment, including an automatic $12,850 external defibrillator.
Purchase fire protection software. $65,000
Purchase an aerial fire truck. $1,100,000
Purchase a fire protection command trailer. $25,000
Purchase a search and rescue vehicle and trailer. $35,000
Special Area Accepted Amount SPECIAL AREAS BOARD
Upgrade Kirriemuir Road. $2,310,000
Metis Settlement Accepted Amount EAST PRAIRIE METIS SETTLEMENT
Purchase a grader. $469,600 ELIZABETH METIS SETTLEMENT
Upgrade the wastewater lagoon. $60,000
Purchase a grader. $107,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 32 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report
ELIZABETH METIS SETTLEMENT
Replace bridge culverts. $144,000
Regravel several roads. $206,024 FISHING LAKE METIS SETTLEMENT
Construct a recreation centre. $750,000 PEAVINE METIS SETTLEMENT
Purchase a backhoe. $230,895
Other Accepted Amount TOWNSITE OF REDWOOD MEADOWS ADMIN SOC
Purchase a fire truck. $132,000
Replace the fire department cardiac monitor. $30,000
Replace emergency radios. $30,000
Upgrade the fire hall, including retrofitting another building for use $75,000 by the fire department.
Upgrade a tennis court. $30,000
Upgrade the council chamber meeting room. $5,000
Rehabilitate several roads. $30,000
Construct an addition to the emergency services building. $20,000
This report reflects the name and status in effect for each municipality at the time the report was produced. Page 33 Project descriptions and amounts include accepted amendments as of August 27, 2020.