MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

City Accepted Amount AIRDRIE

Replace a fire truck. $1,605,070

Design and construct a pedestrian tunnel. $1,807,830

Upgrade the traffic signal system. $570,800

Rehabilitate several roads and curbs. $1,224,300

Design and construct a transit storage and maintenance facility. $2,150,000 BEAUMONT

Upgrade portions of roads. $1,750,000 BROOKS

Upgrade a portion of roads and sidewalks. $1,006,344 CALGARY

Upgrade several fire stations. $4,567,000

Rehabilitate several light rail transit stations. $5,211,461

Construct affordable housing units. $10,145,897

Construct a bus maintenance and storage facility. $35,681,998

Construct the Varsity Multi-Service Centre. $9,987,840

Construct Foothills Athletic Park and Fieldhouse. $95,000,000

Develop preliminary engineering studies for the Northeast and $1,719,432 South light rail transit line extensions.

Prepare roadway engineering plans. $2,838,339

Design and construct a pedestrian bridge across 14 Street and 90 $5,746,383 Avenue Southwest.

Construct the Arts Commons theatre facility. $25,000,000 CAMROSE

Construct a fire training facility. $650,000

Rehabilitate several roads and sidewalks. $1,878,000 CHESTERMERE

Purchase fitness equipment for the fire department. $335,000

Replace municipal entrance signs. $586,000

Upgrade information technology hardware. $442,000

Purchase public works equipment. $515,000

Purchase peace officer vehicles. $201,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 1 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

CHESTERMERE

Purchase garbage carts. $502,000 COLD LAKE

Install water pressure reducing valves. $750,000

Rehabilitate a portion of roads. $984,640

Develop taxiways at the Cold Lake Regional Airport. $700,000

Install water meter communication towers. $325,000

Construct an animal shelter. $1,200,000

Purchase a water quality management and monitoring system. $250,000

Purchase and install community park information signs. $250,000

Construct a bike park. $400,000

Construct a boardwalk and amphitheatre at Kinosoo Beach. $999,900 EDMONTON

Upgrade the Shaw Conference Centre, including windows and $1,917,300 lighting.

Rehabilitate the D.L. MacDonald light rail transit garage. $3,087,500

Upgrade the Sir Wilfrid Laurier Park. $3,142,800

Remove and replace the light rail transit tracks at 66 Street. $6,775,534

Construct a maintenance building at Fort Edmonton Park. $5,720,400

Replace the Harbin Gate. $1,000,000 FORT SASKATCHEWAN

Rehabilitate several roads. $6,508,755

Replace a portion of roads and underground infrastructure. $2,452,000

Rehabilitate Veterans Way. $8,700,000

Rehabilitate Point Aux Pins Road, including street lighting. $1,326,243

Upgrade 112 Street, including road widening. $1,300,000 GRANDE PRAIRIE

Rehabilitate the storm waterlines and culverts. $1,000,000

Upgrade railway crossings. $1,000,000

Upgrade the curling rink ice plant. $722,000

Replace and construct new sidewalks. $603,230

Rehabilitate several roads. $4,870,351

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 2 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

LACOMBE

Rehabilitate a portion of Northstar Drive, including underground $299,775 utilities.

Upgrade Northstar Drive between the Valley Crescent entrances. $915,631

Upgrade the Highway 2A service road. $1,482,278

Rehabilitate 50 Avenue between 58 Street and 76 Street. $467,160 LEDUC

Rehabilitate several back lanes. $1,325,000

Upgrade a portion of Black Gold Drive. $4,332,100

Replace a fire engine. $825,000

Upgrade the Protective Services building, including roof. $676,769 LETHBRIDGE

Upgrade the Shooting Sports Facility in Peenaquim Park. $1,688,000

Upgrade several road intersections. $3,965,000

Rehabilitate portions of roads. $1,810,000

Update the transportation master plan. $1,000,000 LLOYDMINSTER

Upgrade the Lloydminster Golf and Curling Centre water irrigation $1,086,000 system.

Replace the municipal airport emergency generator. $300,000

Upgrade a portion of 47 Avenue, including underground utilities. $1,397,906

Install and replace municipal entrance signs. $250,000

Upgrade traffic signals, including hardware and software. $466,000

Install traffic signals. $250,000 MEDICINE HAT

Rehabilitate the Strathcona Centre facility. $1,000,000

Upgrade the library, including the roof, air conditioning and boilers. $1,000,000

Upgrade the storm water infrastructure. $2,900,000

Rehabilitate several roads and sidewalks, including traffic signals $4,004,455 and underground utilities. RED DEER

Upgrade waterlines along 54 Avenue. $1,328,000

Upgrade traffic signal infrastructure. $1,176,000

Repave roads. $6,199,596

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 3 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

RED DEER

Reconstruct roads. $5,399,681

Upgrade street lights. $1,106,000 SPRUCE GROVE

Jointly construct the Royal Canadian Mounted Police facility with $3,341,861 the Town of Stony Plain.

Relocate the Eco-Centre facility. $690,000

Construct several public transit bus stops. $570,725

Purchase a public transit storage facility and buses. $1,281,197

Rehabilitate local roads. $990,000 ST. ALBERT

Rehabilitate arterial roads. $2,494,029

Rehabilitate collector roads. $1,440,000

Rehabilitate several roads. $957,400

Upgrade back lanes. $1,350,000

Upgrade intersections. $2,150,000

Widen Ray Gibbon Drive, including sidewalks. $780,000

Upgrade the storm water system. $1,751,500 WETASKIWIN

Install a fibre optic network. $91,677

Reconstruct a road intersection, including underground utilities. $300,000

Rehabilitate sidewalks and a parking lot. $310,000

Specialized Municipality Accepted Amount CROWSNEST PASS, MUNICIPALITY OF

Purchase a wheel loader. $430,000

Replace public works vehicles. $160,000

Purchase graders. $930,000

Purchase a backhoe. $185,000

Purchase a tandem axle truck. $120,000

Rehabilitate several parking lots. $215,000

Upgrade a portion of storm water, wastewater and waterlines. $1,250,000 JASPER, MUNICIPALITY OF

Construct a parking lot. $350,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 4 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

JASPER, MUNICIPALITY OF

Replace a fire rescue truck. $750,000

Upgrade the arena ice plant. $408,823

Replace the Aquatic Centre mechanical system. $202,000

Purchase a dump truck. $325,000

Renovate the Jasper Recreation Complex. $3,053,515 MACKENZIE COUNTY

Rehabilitate several roads and replace a bridge culvert. $1,067,750

Upgrade several recreational facilities. $269,000

Rehabilitate several roads. $2,215,000 STRATHCONA COUNTY

Upgrade Township Road 522 between Highway 21 and Range $5,490,000 Road 224.

Rehabilitate several roads. $9,540,000

Upgrade several roads. $6,238,653

Rehabilitate several recreational and community centres. $1,800,000

Expand the Strathcona Public Services Yard. $5,097,600

Upgrade County Hall, including energy efficient heating and $3,960,000 lighting.

Upgrade parks in the Hamlet of Ardrossan. $2,056,500

Widen Wye Road between Estate Drive and Clover Bar Road. $3,167,820

Upgrade the lift station in the Hamlet of Collingwood Cove. $1,350,000

Replace public transit buses. $1,335,420

Purchase public works equipment. $1,417,540

Municipal District Accepted Amount ATHABASCA COUNTY

Rehabilitate gravel roads. $786,632

Rehabilitate several roads. $1,500,000 BEAVER COUNTY

Replace a grader and packer. $566,667

Rehabilitate a portion of roads. $1,133,333

Gravel a portion of roads. $598,558

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 5 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

BIG LAKES COUNTY

Upgrade the administration building in the Hamlet of Kinuso. $100,695

Purchase public works vehicles and equipment. $867,100

Purchase a fire truck and a rescue unit for the hamlets of Enilda $109,866 and Joussard.

Rehabilitate a bridge. $844,170

Pave a parking lot and prepare roadway engineering plans for the $206,864 hamlets of Enilda and Grouard.

Construct a Family and Community Support Services building. $293,913

Construct an animal impound facility. $300,000

Purchase a fire truck. $200,000

Rehabilitate the storm water drainage system at the High Prairie $500,000 Airport.

Rehabilitate several roads in the Hamlet of Grouard. $500,000 BIGHORN NO. 8, M.D. OF

Replace a fire truck. $165,000

Replace garbage bins. $120,000 BIRCH HILLS COUNTY

Purchase public works equipment. $618,400

Haul gravel for road rehabilitation. $413,293 BONNYVILLE NO. 87, M.D. OF

Reconstruct and pave a portion of Range Road 485. $3,522,200

Repave roads and sidewalks in the Hamlet of Ardmore. $2,635,560 BRAZEAU COUNTY

Construct a trail between Brazeau Sports Park and Range Road $166,650 73.

Rehabilitate roads in the Hamlet of Cynthia. $1,386,000

Replace a portion of waterline in the Hamlet of Cynthia. $1,688,000

Replace a portion of wastewater line in the Hamlet of Cynthia. $737,000

Contribute funding to the Town of Drayton Valley to construct an $3,900,000 aquatic facility. CAMROSE COUNTY

Rehabilitate gravel roads. $699,914

Rehabilitate a portion of the alley between McGill Street and $50,077 Beaver Street.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 6 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

CAMROSE COUNTY

Upgrade a portion of MacQuarrie Avenue, including water and $9,506 wastewater lines.

Upgrade the water and wastewater facility. $125,958

Rehabilitate portions of Township Road 464 and 460, and Range $3,434,875 Road 171.

Rehabilitate gravel roads. $619,319 CARDSTON COUNTY

Purchase a grader. $272,700

Replace a grader. $295,200

Purchase a public works vehicle. $143,800

Crush gravel for road maintenance. $405,446

Crush gravel for roads. $405,446 CLEARWATER COUNTY

Replace bridge culvert 70149. $437,000

Replace a bridge. $795,000

Replace bridge culvert 81567. $410,000

Replace bridge 9970. $1,275,582

Rehabilitate bridge culvert 78043. $360,000

Replace bridge culvert 70707. $437,000 CYPRESS COUNTY

Rehabilitate portions of roads. $1,403,660

Rehabilitate several bridges. $337,974

Upgrade roads and underground infrastructure in the Hamlet of $3,763,295 Seven Persons. FLAGSTAFF COUNTY

Conduct an assessment of the wastewater lagoon in the Hamlet of $295,000 Strome.

Upgrade the water treatment plant in the Hamlet of Galahad. $158,812

Rehabilitate and replace several bridges. $278,271

Drill a water well in the Hamlet of Galahad. $250,000 FOOTHILLS COUNTY

Purchase public works maintenance equipment. $1,252,050

Purchase a grader. $530,000

Crush gravel for road maintenance. $1,300,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 7 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

FOOTHILLS COUNTY

Contribute funding to the Millarville Racing and Agricultural Society $150,000 to expand the water storage system.

Contribute funding to the Priddis Greens Services Co-op Limited to $250,000 upgrade the water and wastewater treatment plants. GRANDE PRAIRIE NO. 1, COUNTY OF

Rehabilitate several roads. $2,962,845

Rehabilitate several south division roads. $10,085,620 KNEEHILL COUNTY

Rehabilitate a portion of Range Road 24-4 and 24-5. $2,422,603 LAC STE. ANNE COUNTY

Purchase graders. $910,350 LACOMBE COUNTY

Crush gravel for road rehabilitation. $463,277

Pave a portion of Centreview Road. $3,519,000

Pave a portion of Range Road 231. $1,132,000 LAMONT COUNTY

Purchase a public works truck and equipment. $377,000 LEDUC COUNTY

Rehabilitate several roads and bridges. $1,738,560

Upgrade the bulk water filling station. $640,000

Purchase fire trucks. $1,067,500 LETHBRIDGE COUNTY

Rehabilitate roads in the Sunset Acres subdivision. $747,000

Rehabilitate roads in the Stewart Siding Industrial Park. $560,000

Rehabilitate roads in the Broxburn Business Park. $454,000

Rehabilitate a portion of Range Road 21-4. $250,000

Rehabilitate roads in Riverbank Estates. $153,000

Reconstruct a portion of Range Road 23-2. $250,000

Upgrade roads and underground infrastructure in the Hamlet of $623,900 Shaughnessy.

Rehabilitate several gravel roads. $869,000

Rehabilitate several roads. $547,420

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 8 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

MINBURN NO. 27, COUNTY OF

Replace a portion of waterline in the Hamlet of Lavoy. $203,878

Purchase gravel for road rehabilitation. $773,608

Gravel several roads. $543,778 MOUNTAIN VIEW COUNTY

Crush gravel for road rehabilitation. $420,000

Rehabilitate gravel roads. $2,050,000

Stabilize a portion of roads. $800,000

Extend the Olds-Didsbury Airport runway. $170,342

Rehabilitate roads. $452,000

Rehabilitate portions of roads. $180,000 NORTHERN SUNRISE COUNTY

Regravel several roads. $1,169,392 PAINTEARTH NO. 18, COUNTY OF

Purchase graders. $814,000

Replace the Lake Thelma Bridge. $300,000

Rehabilitate the Weber Bridge. $1,060,000

Purchase an excavator and graders. $880,000 PARKLAND COUNTY

Resurface several roads. $2,165,000

Reconstruct a bridge. $620,000 PEACE NO. 135, M.D. OF

Rehabilitate gravel roads. $270,000

Purchase a public works maintenance vehicle. $275,000 PINCHER CREEK NO. 9, M.D. OF

Upgrade Summerview Road. $550,000

Upgrade Kerr Road. $600,000

Upgrade roads and drainage system in the Hamlet of Lundbreck. $400,000

Replace culverts along Willow Valley Road. $500,000

Upgrade the Global Postioning System and Geographic $53,000 Information Systems.

Purchase a security system for the public works yard and $85,000 administration building.

Rehabilitate a portion of Range Road 29-3. $150,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 9 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

PINCHER CREEK NO. 9, M.D. OF

Reconstruct a portion of Southfork Road. $1,963,250

Replace a bridge. $978,000 PONOKA COUNTY

Rehabilitate several roads. $3,301,955 PROVOST NO. 52, M.D. OF

Rehabilitate a portion of Range Road 15. $2,738,334 RANCHLAND NO. 66, M.D. OF

Rehabilitate gravel roads. $100,000 RED DEER COUNTY

Reconstruct Township Road 370. $3,221,544

Pave a portion of Range Road 275 along the C & E Trail. $314,947 ROCKY VIEW COUNTY

Upgrade a portion of Township Road 250. $800,000

Upgrade a portion of Range Road 290. $1,000,000

Construct a fire station. $9,000,000

Upgrade a portion of Dickson Stevenson Trail. $1,100,000 SMOKY LAKE COUNTY

Rehabilitate portions of roads, including Township Road 594 and $240,000 Range Road 152.

Upgrade and stabilize roads. $512,000

Gravel roads. $457,251

Replace a grader. $400,000 SMOKY RIVER NO. 130, M.D. OF

Gravel portions of roads. $200,000

Rehabilitate roads. $757,318

Conduct a drainage study on Township Road 765. $75,000

Replace bridge culverts. $182,750 SPIRIT RIVER NO. 133, M.D. OF

Purchase an excavator. $140,000

Purchase mowers. $225,000

Rehabilitate gravel roads. $168,680

Expand and rehabilitate the administration building, including $410,000 accessibility features.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 10 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

ST. PAUL NO. 19, COUNTY OF

Rehabilitate Township Road 590E between Highway 36 and $1,704,104 Highway 881.

Replace public works maintenance equipment. $831,000 STETTLER NO. 6, COUNTY OF

Upgrade the storm water system in the Hamlet of Botha. $485,658 STURGEON COUNTY

Rehabilitate a portion of Range Road 245 and Glenview Acres $813,000 subdivision.

Reconstruct roads, including the purchase of right-of-ways. $1,794,000

Purchase gravel and rehabilitate roads. $550,000

Pave a portion of Range Road 230. $1,000,000 TABER, M.D. OF

Rehabilitate gravel roads. $647,791

Replace a storm water culvert. $150,000

Construct a highway rest area. $900,000

Rehabilitate a portion of Range Road 18. $225,000 THORHILD COUNTY

Rehabilitate gravel roads. $494,189

Purchase a loader. $313,430 TWO HILLS NO. 21, COUNTY OF

Purchase public works maintenance equipment. $1,084,990

Rehabilitate wastewater lines in the Hamlet of Willingdon. $196,893

Rehabilitate several roads. $1,531,787

Upgrade a water filling station in the Hamlet of Willingdon. $80,000 VERMILION RIVER, COUNTY OF

Pave a portion of Range Road 14. $1,705,007

Rehabilitate gravel roads. $903,137 VULCAN COUNTY

Replace a tandem tractor. $184,481

Replace graders. $786,709

Rehabilitate bridges. $1,288,713 WARNER NO. 5, COUNTY OF

Rehabilitate gravel roads. $692,031

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 11 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

WARNER NO. 5, COUNTY OF

Rehabilitate asphalt roads. $1,152,732

Upgrade several roads. $1,433,123 WESTLOCK COUNTY

Resurface and rehabilitate several range and township roads. $1,358,235

Rehabilitate gravel roads. $1,600,000 WETASKIWIN NO. 10, COUNTY OF

Contribute funding to the Wetaskiwin Agricultural Society to $100,000 construct a multi-use building.

Construct the G3 Resource Road. $1,882,100

Contribute funding to the Mulhurst Lutheran Church Camp $50,000 Association to upgrade the campground shower and washroom facility. WHEATLAND COUNTY

Pave Glenmore Trail. $2,255,000

Upgrade a portion of Township Road 252. $2,520,000

Purchase graders and an excavator. $2,089,961 WILLOW CREEK NO. 26, M.D. OF

Rehabilitate several roads. $678,575

Purchase a fire pumper truck. $100,000 WOODLANDS COUNTY

Gravel roads. $930,100

Town Accepted Amount ATHABASCA

Replace a wastewater main. $498,968

Replace sidewalks. $50,000

Rehabilitate a portion of University Drive. $200,000 BASHAW

Replace a portion of water and wastewater lines along 54 Avenue, $446,849 including road rehabilitation.

Replace several fire hydrants. $40,000 BEAVERLODGE

Purchase an air compressor. $20,635

Install a wastewater bypass along 7 Avenue. $80,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 12 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

BEAVERLODGE

Purchase calcium containment storage tanks, pumps, and a $37,500 storage shed. BENTLEY

Rehabilitate portions of roads, including sidewalks and storm $455,503 waterlines. BLACK DIAMOND

Upgrade 6 Street, including underground utilities and water looping. $614,975

Install water and wastewater lines along 4 Street Southwest. $62,000

Rehabilitate a portion of wastewater line. $44,520

Construct a portion of water and wastewater lines. $1,477,506 BLACKFALDS

Purchase a building for the public works operations facility. $5,000,000 BON ACCORD

Rehabilitate 54 Street from Range Road 235 to 47 Street. $45,485

Rehabilitate a portion of 49 Avenue, including sidewalks and $322,046 underground utilities.

Rehabilitate the Bon Accord Arena. $29,312 BONNYVILLE

Upgrade a portion of 47 and 49 Street, including sidewalks and $646,420 underground utilities.

Pave several roads. $340,950 BOW ISLAND

Construct a portion of Highway 3. $150,000

Rehabilitate the airport runway and lighting. $240,328 BOWDEN

Upgrade wastewater lines and manholes. $138,150 BRUDERHEIM

Purchase a public works utility vehicle. $25,000

Purchase a skid steer and attachments. $50,000 CALMAR

Purchase a grader and loader. $397,822 CANMORE

Reconstruct several roads and sidewalks, including lighting and $3,375,000 underground utilities.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 13 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

CARDSTON

Purchase public works equipment. $194,000

Replace a portion of road, including sidewalks and underground $225,000 infrastructure.

Replace a portion of road and sidewalk along 3 Street East. $115,000

Rehabilitate a portion of roads. $205,000

Replace a portion of road and underground infrastructure along 6 $100,000 Street West.

Expand the Lee Creek Campground. $275,500 CASTOR

Upgrade the fire hall. $100,000

Upgrade wastewater and water systems. $112,500

Replace the boiler in the town hall. $11,000 CLARESHOLM

Convert and renovate a building into a multi-use community $202,380 complex.

Replace public works vehicles. $140,000

Prepare a storm water management plan. $151,433 COALHURST

Purchase a bylaw officer vehicle. $90,000 COCHRANE

Upgrade a portion of Quigley and Riverview Drive. $668,500

Upgrade George Fox Trail. $1,579,200 DAYSLAND

Replace a public works vehicle. $33,713 DIDSBURY

Upgrade 20 Street, including sidewalks and storm water facilities. $540,000 DRAYTON VALLEY

Construct an aquatic facility. $2,420,165 DRUMHELLER

Replace the Aquaplex air handling unit. $300,000

Purchase public works maintenance equipment. $300,000 ECKVILLE

Purchase public works equipment. $16,900

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 14 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

ECKVILLE

Purchase recycling collection bins. $45,500

Purchase a wastewater flow meter. $18,500

Purchase a public works truck. $60,000

Install solar powered street lights. $190,000

Rehabilitate a wastewater lift station. $23,000

Install a fibre internet network. $30,000

Upgrade the public works yard fence. $14,500

Construct a walking trail. $155,000 ELK POINT

Upgrade a wastewater lift station. $127,052 FAIRVIEW

Rehabilitate a portion of road. $700,000

Purchase a loader. $224,000 FORT MACLEOD

Purchase a vacuum truck. $350,000

Prepare a storm water management and drainage plan. $29,700

Prepare design and engineering plans for 17 Street upgrades. $65,000

Replace a portion of sidewalks. $75,000

Repave a portion of roads. $100,000 GIBBONS

Rehabilitate several roads, including sidewalks. $175,735

Rehabilitate the arena and curling rink parking lots. $174,384 GRIMSHAW

Replace the road and waterline along 45 Street and 56 Street. $682,715 HANNA

Rehabilitate roads. $1,070,000

Purchase a tandem axle truck. $65,000 HIGH LEVEL

Replace a street sweeper. $375,000

Replace the arena boards. $200,000

Upgrade the arena change rooms and washrooms. $60,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 15 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

HIGH PRAIRIE

Jointly upgrade the reservoir pump station with Big Lakes County. $304,500

Jointly rehabilitate the intersection of 56 Avenue and 50 Street, $605,000 including underground utilities, with Big Lakes County.

Replace municipal welcome signs. $25,000

Jointly upgrade the arena parking lot with Big Lakes County. $186,000

Upgrade a portion of 52 Avenue, including underground utilities $410,000 and manholes.

Enhance the downtown core, including lighting and landscape. $50,000

Upgrade a portion of 55 Avenue, including sidewalks, manholes, $260,000 and a fire hydrant.

Upgrade the first responders radio communication system. $60,000 HIGH RIVER

Upgrade and expand the fire hall. $7,340,000

Replace a grader. $375,000

Upgrade a lift station and decommission two lift stations. $1,600,000

Upgrade the main lift station generator. $250,000

Relocate utilities along Centre Street. $550,000

Upgrade the Bob Snodgrass Recreation Complex, including $735,900 lighting and parts of the roof.

Rehabilitate sidewalks and ramps. $250,000

Construct a pathway along 12 Avenue. $200,000

Replace the fire and emergency services radio systems. $325,000

Demolish the water tower and restore the site as a public park. $550,000

Replace the Bob Snodgrass Recreation Centre arena seats. $132,000

Rehabilitate the Bob Snodgrass Recreation Complex field $300,000 house parking lots.

Replace the Bob Snodgrass Recreation Complex roof. $170,000

Remediate and restore municipal facilities. $190,000

Rehabilitate the downtown core, including roads, and underground $3,700,000 utilities.

Rehabilitate the Bob Snodgrass Recreation Complex, including the $275,000 aquatic electrical system.

Rehabilitate a wastewater lift station. $450,000 HINTON

Rehabilitate a portion of water and wastewater lines on Athabasca $2,100,000 Avenue.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 16 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

INNISFAIL

Upgrade water and wastewater lines. $1,100,087

Repair and replace asphalt. $724,000 IRRICANA

Upgrade several recreational facilities. $36,457 KILLAM

Upgrade 51 Street, including underground utilities and sidewalks. $242,000 LAMONT

Rehabilitate roads, including water and wastewater lines. $607,712 LEGAL

Purchase a street sweeper. $125,000 MAGRATH

Replace sidewalks. $47,721

Install wastewater lines along 3 Avenue North and 2 Street West. $479,468

Install water and wastewater lines. $92,790

Construct a pedestrian tunnel under Highway 62. $171,337

Upgrade 2A Street East, including sidewalks, curbs and gutters. $284,000

Purchase a bucket truck. $45,000 MAYERTHORPE

Rehabilitate several sidewalks. $68,461

Purchase a mower. $20,000

Construct a skateboard and bike park. $75,000

Rehabilitate a wastewater lagoon. $66,920

Upgrade computers. $15,000

Rehabilitate a waterline. $61,748 MILLET

Rehabilitate a portion of 48 Avenue. $404,447

Upgrade the arena ice plant. $200,000 MUNDARE

Purchase public works vehicles. $50,000

Conduct an engineering study for lift station upgrades. $50,000

Replace sidewalks. $50,000

Reline wastewater lines. $229,550

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 17 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

NANTON

Replace water treatment equipment. $60,000 NOBLEFORD

Upgrade the lagoon. $265,000 OKOTOKS

Jointly construct the Okotoks Arts and Learning Campus with $18,300,000 the Christ The Redeemer Catholic School, including the purchase of land.

Purchase firefighting equipment. $345,000

Construct a pedestrian plaza. $250,000

Purchase land for park development. $1,282,500

Upgrade the information technology systems and equipment. $384,600

Purchase public works equipment and a patrol vehicle. $460,000

Upgrade the emergency operations centre. $300,000 OLDS

Replace the information technology network servers at municipally $255,360 owned facilities.

Purchase public works equipment. $558,000

Rehabilitate trails and upgrade a playground. $220,000

Construct and rehabilitate a portion of roads, including $1,075,360 underground utilities.

Upgrade the Sportsplex, including the arena ice plant chiller. $300,000 ONOWAY

Rehabilitate Township Road 544 and Range Road 21. $155,960

Replace sidewalks. $100,000

Upgrade the lift station and water plant roofs. $31,540

Purchase a water meter reader. $15,000

Pave a portion of 47 Avenue. $291,082 OYEN

Purchase a loader. $152,000

Upgrade the airport runway. $146,250 PENHOLD

Purchase public works equipment. $98,000

Rehabilitate Minto Street. $561,229

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 18 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

PINCHER CREEK

Rehabilitate roads and sidewalks. $218,000

Upgrade Thistle Crescent. $350,000

Upgrade a pump at the water retention pond. $150,000

Upgrade the wastewater treatment lagoon. $746,754 PONOKA

Upgrade a portion of 64 Street. $375,000

Rehabilitate several roads, including sidewalks and storm water $120,000 infrastructure.

Pave several roads. $850,000

Replace and purchase public work equipment. $245,000

Construct a parking lot at the Civic Centre. $350,000 RAINBOW LAKE

Upgrade cable and internet systems. $148,400

Purchase a bucket truck. $47,000 REDCLIFF

Upgrade roads, including water and wastewater lines along 4 $1,540,000 Street.

Purchase and install emergency generators. $50,000

Purchase and install a storm water and wastewater camera. $60,000

Upgrade the aquatic centre pools. $240,000

Purchase water meter radios. $77,000

Upgrade the splash park. $100,000 REDWATER

Prepare engineering plans for the heating, ventilation, and air $65,000 conditioning system at Pembina Place. RIMBEY

Upgrade roads and sidewalks. $541,228

Prepare design and engineering plans for 51 Street upgrades. $136,500 ROCKY MOUNTAIN HOUSE

Rehabilitate 59 Avenue from 54 Street to Highway 11. $201,000

Rehabilitate a wastewater lagoon. $1,629,320 SEDGEWICK

Upgrade the heating, ventilation, and air conditioning system at the $110,000 water treatment plant.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 19 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

SEDGEWICK

Rehabilitate a portion of Main Street, including sidewalks and $300,000 underground facilities. SEXSMITH

Replace a portion of sidewalk. $103,825

Construct an asphalt pad next to the arena. $49,203

Rehabilitate the civic centre roof. $91,950

Purchase a snowblower. $132,290

Install storm water infrastructure along 99 Avenue. $204,365

Pave a portion of 95 Avenue. $764,569 SPIRIT RIVER

Replace the water and wastewater lines along McAlpine Crescent. $250,000 ST. PAUL

Purchase a tractor. $51,185

Replace a tractor. $45,000

Purchase public works equipment and upgrade the public works $789,900 shop.

Replace a portion of wastewater line along 51 Avenue. $145,000

Replace a portion of wastewater line along 52 Avenue. $130,000 STAVELY

Purchase a mower. $8,500

Prepare a water treatment plant assessment study. $30,000

Upgrade several roads, including an industrial subdivision. $30,000

Rehabilitate portions of roads. $8,750

Rehabilitate the wastewater lagoon. $8,750 STETTLER

Rehabilitate a portion of 51 Avenue and 49 Avenue. $369,210

Replace a portion of waterline along 52 Street. $280,000

Replace a portion of waterline and wastewater line along 57A $440,000 Street.

Upgrade a pumphouse. $150,000

Rehabilitate a wastewater lagoon. $300,000

Replace a portion of storm waterline along 57 Street. $100,000

Purchase a tandem truck. $170,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 20 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

STETTLER

Purchase a snow blower. $180,000 STONY PLAIN

Construct a cemetery. $2,000,000 STRATHMORE

Construct a municipal administration building, including park $9,626,129 facilities and trail system. SWAN HILLS

Purchase public works maintenance equipment and attachments. $160,000

Purchase a public works vehicle. $40,000

Pave several roads. $73,576 SYLVAN LAKE

Upgrade the NexSource Centre. $485,000

Construct an asphalt trail. $200,000

Rehabilitate a portion of Hunter Road. $450,000

Rehabilitate the roads in the village area, including underground $3,000,000 infrastructure.

Rehabilitate roads and sidewalks. $500,000

Upgrade Memorial Trail at 60 Street West. $400,000

Upgrade the intersection at Highway 20 and Memorial Trail. $650,000

Upgrade 50 Avenue between 33 and 50 Streets. $3,746,000

Construct a water reservoir. $3,000,000 TABER

Install a carbon dioxide system at the water treatment plant. $264,000

Replace the water and wastewater line along 52 Street. $569,425

Construct a fire hall and emergency services building. $404,000 THORSBY

Replace a portion of wastewater line along 47 Street between 49 $78,216 Avenue and 50 Avenue.

Pave a portion of roads. $21,955

Rehabilitate a portion of 48 Avenue. $339,298

Pave portions of 54 Avenue and 52 Street. $538,413 TOFIELD

Install solar powered lighting at the Tofield Airport. $18,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 21 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

TOFIELD

Replace a wastewater lift station. $560,000 TROCHU

Upgrade the water pump house. $23,000 TURNER VALLEY

Purchase a backhoe. $108,807

Pave a portion of alleyways. $58,890

Purchase a mobile fire service trailer. $38,396

Purchase a global positioning system. $18,620 VAUXHALL

Purchase a waste transfer vehicle. $130,000

Purchase a street sweeper. $75,000

Upgrade playground equipment. $75,000

Upgrade several sidewalks. $200,000 VEGREVILLE

Repave a section of 47A Street and 49 Avenue. $865,045 VERMILION

Upgrade the recreation centre change rooms. $60,000

Prepare plans and install the preliminary infrastructure for a $345,000 broadband internet network.

Purchase a fire truck. $700,000 VIKING

Replace a storm water culvert and rehabilitate drainage. $167,624 VULCAN

Construct a pool. $1,335,200

Upgrade storm water drainage along Highway 23. $280,000 WEMBLEY

Rehabilitate a portion of Township Road 712. $480,000

Purchase a paver. $265,000 WESTLOCK

Purchase a backhoe. $150,000

Reline the pool. $340,000

Rehabilitate the aquatic centre, including electrical and air handling $329,740 system.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 22 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

WESTLOCK

Upgrade storm water infrastructure. $860,553

Village Accepted Amount ACME

Conduct an overland drainage study. $50,000

Replace several curb stops. $20,000

Replace several fire hydrants and water valves. $20,000

Upgrade a portion of wastewater lines. $50,000

Purchase and install water meters. $15,000

Purchase land to expand the campground. $45,000

Purchase a sanding truck. $15,000 AMISK

Construct and loop several waterlines along 50, 51 and 53 Street. $87,500

Install a portion of waterline. $155,000

Purchase office equipment. $10,000

Purchase and repair welcome signs. $12,000 ANDREW

Rehabilitate a portion of 53 Street and 53 Avenue. $213,140

Replace an administration building boiler. $18,000 ARROWWOOD

Purchase a skid steer and attachments. $100,000

Purchase computers and hardware for utility readings. $30,000

Rehabilitate the municipal office building. $30,000

Install fibre-optic infrastructure. $50,000

Contribute funding to the Northwest District Recreation Board to $50,000 construct a multi-use trail system.

Extend 2A Street East between 1 Avenue East and Railway $50,000 Avenue East, including underground utilities.

Prepare an asset management plan. $50,000 BEISEKER

Upgrade a wastewater lift station. $28,745

Upgrade a portion of water and wastewater lines. $20,000

Upgrade the water meter readers. $24,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 23 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

BEISEKER

Upgrade a portion of 3 Avenue. $255,385 BERWYN

Replace water main valves and infrastructure. $202,000 BIG VALLEY

Pave roadways. $155,000

Purchase public works vehicle. $26,000 BITTERN LAKE

Upgrade the waterline air release valves. $35,000

Purchase computers. $10,000

Upgrade the recreation area, including skating rink and $360,570 playground. BOYLE

Replace the water treatment plant roof. $25,690

Construct a dressing room in the arena. $25,554

Pave several roads. $270,974

Purchase land for the construction of a municipal centre. $320,585 BRETON

Rehabilitate a portion of roads. $34,860

Rehabilitate a wastewater lagoon. $60,700 CARMANGAY

Upgrade a portion of waterline and wastewater line. $250,347 CAROLINE

Replace a portion of 49 Avenue, including underground $1,150,000 infrastructure. CHAMPION

Construct a pathway. $125,000

Upgrade the public works building. $15,758 CHAUVIN

Pave a portion of roads. $120,000 CHIPMAN

Rehabilitate the Chipman National Hall. $105,200

Purchase a sanding truck. $39,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 24 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

CLYDE

Upgrade the water distribution plant and associated equipment. $98,750 COUTTS

Replace the main waterline and valves. $38,204

Replace a waterline and valve. $15,000

Pave portions of roads. $58,000 CREMONA

Pave several streets, including sidewalks. $187,000

Upgrade the water treatment plant. $28,400

Rehabilitate a portion of the storm water system along 1 Street $70,000 West. DELBURNE

Rehabilitate a portion of road. $80,000

Resurface several roads. $45,783

Construct roads and underground infrastructure in the Fawn $275,226 Meadows subdivision. DELIA

Upgrade a portion of water and wastewater line along 1 Avenue. $575,691

Replace several sidewalks. $152,000

Expand and upgrade the water reservoir. $764,405

Contribute funding to the Prairie Land School Division to $100,000 construct a library and gymnasium. DONNELLY

Upgrade a portion of waterline and replace a water main valve. $34,005

Inspect and rehabilitate a portion of wastewater line. $52,213

Rehabilitate roads and sidewalks. $334,553 EDBERG

Prepare a road, water and stormwater infrastructure study. $44,596

Purchase information technology equipment, including computers, $10,000 printers, monitors and office furniture.

Upgrade a portion of 1 Street South, including water and $175,504 wastewater utilities.

Upgrade the water tower. $13,000 EMPRESS

Purchase firefighting equipment. $10,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 25 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

FOREMOST

Expand the campground. $70,000

Prepare an asset management plan. $12,500

Purchase garbage bins. $38,000 FORESTBURG

Rehabilitate portions of 57 Street West and install a storm $300,000 water swale. GIROUXVILLE

Rehabilitate several roads. $15,000 GLENWOOD

Upgrade storm water drainage. $79,000 HALKIRK

Resurface gravel alleys. $10,000

Purchase mowers. $20,000

Expand and upgrade the fire hall. $180,000 HAY LAKES

Replace a portion of sidewalk. $45,044 HEISLER

Purchase a lift station heater and generator. $45,000

Replace water curb stops. $65,000

Rehabilitate a portion of Main Street. $25,000 HILL SPRING

Upgrade the SCADA system to integrate the lift station. $12,000

Replace a portion of sidewalk. $33,000

Replace a water pump. $22,254

Replace culverts. $18,000 HUGHENDEN

Replace a garbage truck and collection bins. $20,000 HUSSAR

Replace a portion of 2 Avenue, including sidewalks and $468,782 underground utilities. HYTHE

Upgrade a water well. $220,075

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 26 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

HYTHE

Upgrade a wastewater lift station, including security and alarm $33,184 system.

Reline the wastewater main. $235,996

Upgrade the administration building. $30,854

Develop and install a fibre-optic network. $115,000

Rehabilitate portions of 100 Street. $109,720 INNISFREE

Replace the public works truck. $30,000

Upgrade the administration building. $68,200

Rehabilitate the public works facility. $10,704

Replace the water treatment plant chlorine monitor. $6,650

Purchase a public works truck. $11,000

Purchase public works maintenance equipment. $10,000 LONGVIEW

Replace a portion of waterline and wastewater line. $964,165 LOUGHEED

Replace the administration building roof. $59,000

Replace water main valves. $248,684 MANNVILLE

Rehabilitate a portion of 52 Avenue. $228,000

Purchase computer hardware and security cameras. $21,500

Purchase an air compressor for the fire hall. $20,000

Purchase public works equipment. $38,000

Replace the roof on the water distribution building. $35,000

Upgrade the golf course kitchen. $15,000

Upgrade the roof on the golf course clubhouse. $15,000

Replace several water main valves. $20,000

Upgrade the public works and fire hall buildings. $17,000

Rehabilitate the arena road. $60,000

Replace the sidewalk along 50 Street. $20,000

Upgrade the downtown gazebo. $30,000

Upgrade the baseball diamonds and concession. $40,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 27 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

MARWAYNE

Upgrade a portion of roads and storm water infrastructure. $144,979 MILO

Replace the trees along Centre Street. $35,007

Upgrade waterlines and hydrants. $110,000 MYRNAM

Upgrade the Construction and Technology Education Centre. $133,000 NAMPA

Prepare an infrastructure management plan. $40,000

Upgrade a public works building. $30,000

Upgrade roads. $212,786 PARADISE VALLEY

Construct a water distribution plant. $693,700 ROCKYFORD

Replace fire hydrants. $42,500 ROSALIND

Rehabilitate a portion of roads. $93,609 ROSEMARY

Rehabilitate a portion of Rose Street and Iris Street. $321,210 RYCROFT

Install street lights along Highway 2 and Highway 49. $44,711 RYLEY

Reconstruct a portion of 52 Avenue between 52 Street and 57 $147,688 Avenue. SPRING LAKE

Construct a public works storage building. $55,000 STANDARD

Replace a portion of roads and underground infrastructure. $133,990 VETERAN

Contribute funding to the Special Areas Board for the construction $421,019 of a fire hall. WABAMUN

Upgrade the water treatment and distribution facility. $18,320

Replace the community hall air conditioning system. $30,490

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 28 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

WABAMUN

Rehabilitate roads and sidewalks. $120,000

Replace water main valves. $15,000

Upgrade the wastewater lagoon and lift station. $190,232

Upgrade storm water drainage. $14,000

Construct an ambulance parking lot. $10,000 WARBURG

Rehabilitate portions of 53 Street and 51 Avenue. $558,342 WARNER

Rehabilitate gravel roads. $51,000

Extend a portion of waterline and wastewater line. $125,000 WASKATENAU

Rehabilitate a portion of 50 Avenue. $372,624 YOUNGSTOWN

Upgrade the village public works shop. $30,500

Upgrade the library and village office. $15,000

Upgrade the curling rink chiller. $14,286

Upgrade the community hall. $21,716

Summer Village Accepted Amount BETULA BEACH

Upgrade a portion of Willow Road. $92,000

Construct a walking trail. $15,300

Upgrade the intersection of Kos Street, Birch Lane and Terrace $143,000 Avenue. BIRCHCLIFF

Conduct a drainage assessment of Birchcliff Road. $14,500

Conduct a traffic safety study. $6,000

Construct a pathway. $479,440 BURNSTICK LAKE

Purchase fire suppression equipment and construct a storage $95,000 facility. CRYSTAL SPRINGS

Rehabilitate a portion of Lakeview Drive. $300,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 29 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

GOLDEN DAYS

Install municipal addressing signage. $24,500

Reconstruct roads in the Vasa subdivison. $40,000

Purchase and install a speed sign. $5,000 GRANDVIEW

Construct Lakeshore Drive. $325,000 HALF MOON BAY

Design a wastewater collection system. $40,000

Prepare a design plan for the West Beach recreation area. $12,000

Purchase and install buoys and swim lines. $14,000

Upgrade entrance signs and a bulletin board. $50,000

Construct a recreational beach area, including a shelter and $80,000 pathways. HORSESHOE BAY

Rehabilitate several roads. $20,000 ISLAND LAKE

Pave several roads. $230,000 ITASKA BEACH

Rehabilitate a portion of roads, including dust abatement. $9,930

Rehabilitate the community entrance sign. $5,000

Rehabilitate a portion of road. $4,500

Purchase picnic tables and a park bench. $4,815 MA-ME-O BEACH

Design and reconstruct roads and sidewalks along 6 and 7 Street. $165,000 MEWATHA BEACH

Install community entrance signs. $8,412

Construct a park. $106,572

Rehabilitate portions of Mewatha Drive. $170,000 PARKLAND BEACH

Rehabilitate Parkland Place. $27,000

Rehabilitate Parkland Close. $24,000

Rehabilitate a portion of Parkland Drive. $92,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 30 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

PELICAN NARROWS

Construct Oriole Lane and rehabilitate Pelican Drive. $490,600 POINT ALISON

Install a roadway security camera. $6,205 POPLAR BAY

Rehabilitate Poplar Bay Drive. $405,000 SANDY BEACH

Rehabilitate a portion of roads. $65,592

Conduct a wastewater lagoon study. $20,000 SEBA BEACH

Rehabilitate a portion of 1 Avenue. $125,920 SILVER BEACH

Replace the entrance and informational signage. $30,000

Rehabilitate portions of Silver Beach Road. $225,000

Purchase and install radar speed signs. $10,000

Replace the playground equipment at Ouimette Park. $163,000 SUNDANCE BEACH

Replace an entrance sign and community bulletin board. $40,000

Purchase electronic speed road signs. $14,500

Rehabilitate gravel roads, including dust abatement. $38,500 SUNRISE BEACH

Purchase a sand and salt spreader. $8,000 SUNSET BEACH

Contribute funding to Athabasca County for the construction of a $30,000 pool and fitness centre. SUNSET POINT

Rehabilitate several park and municipal building entrances. $90,900

Rehabilitate the administration building. $110,000

Rehabilitate roads, including the storm water collection system. $236,000 WAIPAROUS

Install solar pedestrian crossing lights along Highway 40. $18,264

Engineer and upgrade the storm water drainage. $149,640

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 31 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

WHISPERING HILLS

Upgrade a portion of Whispering Hills Road. $203,870 YELLOWSTONE

Rehabilitate several roads. $224,517

Improvement District Accepted Amount I.D. NO. 04 (WATERTON)

Contribute funding to the Waterton Parks Community Association $353,000 to rehabilitate the Lions Hall.

Contribute funding to the Waterton Parks Community Association $125,000 to upgrade the spray park facility. I.D. NO. 13 (ELK ISLAND)

Purchase a loader. $278,460 I.D. NO. 25 (WILLMORE WILDERNESS)

Contribute funding to the Willmore Wilderness Foundation to $84,000 rehabilitate the trail system. KANANASKIS IMPROVEMENT DISTRICT

Purchase automatic external defibrillators. $8,263

Purchase firefighting equipment. $377,907

Replace public safety equipment, including an automatic $12,850 external defibrillator.

Purchase fire protection software. $65,000

Purchase an aerial fire truck. $1,100,000

Purchase a fire protection command trailer. $25,000

Purchase a search and rescue vehicle and trailer. $35,000

Special Area Accepted Amount SPECIAL AREAS BOARD

Upgrade Kirriemuir Road. $2,310,000

Metis Settlement Accepted Amount EAST PRAIRIE METIS SETTLEMENT

Purchase a grader. $469,600 ELIZABETH METIS SETTLEMENT

Upgrade the wastewater lagoon. $60,000

Purchase a grader. $107,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 32 Project descriptions and amounts include accepted amendments as of August 27, 2020. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2019 Accepted Projects Report

ELIZABETH METIS SETTLEMENT

Replace bridge culverts. $144,000

Regravel several roads. $206,024 FISHING LAKE METIS SETTLEMENT

Construct a recreation centre. $750,000 PEAVINE METIS SETTLEMENT

Purchase a backhoe. $230,895

Other Accepted Amount TOWNSITE OF REDWOOD MEADOWS ADMIN SOC

Purchase a fire truck. $132,000

Replace the fire department cardiac monitor. $30,000

Replace emergency radios. $30,000

Upgrade the fire hall, including retrofitting another building for use $75,000 by the fire department.

Upgrade a tennis court. $30,000

Upgrade the council chamber meeting room. $5,000

Rehabilitate several roads. $30,000

Construct an addition to the emergency services building. $20,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 33 Project descriptions and amounts include accepted amendments as of August 27, 2020.