SCOPE OF WORK

SKAGIT COUNTY STREET WASTE FACILITY PROJECT #WA402170

This contract provides for the construction of a street waste decant and disposal facility within an existing incinerator building in accordance with the attached Contract Plans, these Contract Provisions, and the Standard Specifications. The project includes the following: • Demolition and replacement of a portion of the existing tipping floor to create a decant settling area. • Installation of concrete partition walls to separate decant dump areas from decant settling area. • Vertical extension of the existing pit wall to form a concrete push wall at the rear of the decant dump and settling areas. • Installation of a concrete sump and sump pump within the existing refuse pit, and discharge piping connection to an existing wastewater manhole. • Extension of electrical power to sump pump and control panel location, and installation of flow meter on the sump discharge line. • Installation of accessory structures including chain link fence and an access ladder.

Schedule: This project will be ready to proceed upon contract execution.

Measurement and Payment: Each item will be per the bid proposal.

Project Location: 14104 Ovenell Road, Mount Vernon, WA

1 CONTENTS 2 PAGE 3 INTRODUCTION------1 4 AMENDMENTS TO THE STANDARD SPECIFICATIONS

5 Section 1-01, Definition and Terms ------1 6 Section 1-02, Bid Procedures and Conditions ------2 7 Section 1-03, Award and Execution of Contract ------2 8 Section 1-05, Control of Work ------2 9 Section 1-06, Control of Material ------2 10 Section 1-07, Legal Relations and Responsibilities to the Public ------3 11 Section 1-08, Prosecution and Progress ------5 12 Section 1-09, Measurement and Payment ------6 13 Section 3-01, Production From Quarry and Pit Sites ------6 14 Section 3-04, Acceptance of Aggregate ------6 15 Section 4-06, Asphalt Treated Base------7 16 Section 5-01, Cement Concrete Pavement Rehabilitation ------8 17 Section 5-02, Bituminous Surface Treatment ------8 18 Section 5-04, Hot Mix Asphalt ------11 19 Section 5-05, Cement Concrete Pavement ------12 20 Section 6-02, Concrete Structures ------13 21 Section 6-03, Steel Structures ------17 22 Section 6-05, Piling ------20 23 Section 6-06, Bridge Railings ------20 24 Section 6-07, Painting ------20 25 Section 6-10, Concrete Barrier ------21 26 Section 6-12, Noise Barrier Walls ------22 27 Section 6-13, Structural Earth Walls ------23 28 Section 6-14, Geosynthetic Retaining Walls ------23 29 Section 6-15, Soil Nail Walls ------23 30 Section 6-16, Soldier Pile and Soldier Pile Tieback Walls ------24 31 Section 6-17, Permanent Ground Anchors ------25 32 Section 6-19, Shafts ------25 33 Section 7-02, Culverts ------28 34 Section 7-03, Structural Plate Pipe, Pipe Arch, Arch, and Underpass ------28 35 Section 7-04, Storm Sewers ------28 36 Section 7-05, Manholes, Inlets, Catch Basins, and Drywells ------29

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 A PAGE 1 Section 7-08, General Pipe Installation Requirements ------29 2 Section 7-09, Water Mains ------29 3 Section 8-01, Erosion Control and Water Pollution Control ------29 4 Section 8-02, Roadside Restoration------36 5 Section 8-03, Irrigation Systems ------38 6 Section 8-04, Curbs, Gutters, and Spillways ------38 7 Section 8-07, Precast Traffic Curb and Block Traffic Curb ------39 8 Section 8-11, Guardrail ------39 9 Section 8-12, Chain Link Fence and Wire Fence ------40 10 Section 8-15, Riprap ------43 11 Section 8-20, Illumination, Traffic Signal Systems, And Electrical ------43 12 Section 8-21, Permanent Signing ------52 13 Section 8-22, Pavement Marking ------55 14 Section 8-25, Glare Screen------56 15 Section 8-29, Wire Mesh Slope Protection ------56 16 Section 9-02, Bituminous Materials------58 17 Section 9-03, Aggregates ------60 18 Section 9-04, Joint And Crack Sealing Materials ------62 19 Section 9-05, Drainage Structures, Culverts, and Conduits ------63 20 Section 9-06, Structural Steel and Related Materials ------65 21 Section 9-07, Reinforcing Steel ------65 22 Section 9-10, Piling ------65 23 Section 9-13, Riprap, Quarry Spalls, Slope Protection, & Rock for Erosion 24 and Scour Protection and Rock Walls ------66 25 Section 9-14, Erosion Control and Roadside Planting ------66 26 Section 9-15, Irrigation System ------72 27 Section 9-16, Fence and Guardrail ------72 28 Section 9-18, Precast Traffic Curb and Block Traffic Curb ------76 29 Section 9-20, Concrete Patching Material, Grout, and Mortar ------76 30 Section 9-23, Concrete Curing Materials and Admixtures ------76 31 Section 9-26, Epoxy Resins ------76 32 Section 9-28, Signing Materials and Fabrication ------77 33 Section 9-29, Illumination, Signal, Electrical ------77 34 Section 9-34, Pavement Marking Material ------106 35 Section 9-36, Shaft-Related Materials ------106 36

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 February 2014 B PAGE 1 SPECIAL PROVISIONS

2 DIVISION 1 3 GENERAL REQUIREMENTS

4 DESCRIPTION OF WORK ------108 5 Definitions ------108 6 BID PROCEDURES AND CONDITIONS ------110 7 Prequalification of Bidders ------110 8 Plans and Specifications ------110 9 Preparation Of Proposal ------110 10 Delivery of Proposal ------111 11 Public Opening Of Proposal ------111 12 Irregular Proposals ------111 13 Disqualification of Bidders ------112 14 AWARD AND EXECUTION OF CONTRACT ------115 15 Department of Ecology Funding Clauses ------115 16 Scope of the Work ------116 17 Coordination of Contract Documents, Plans, Special Provisions, Specifications, 18 and Addenda ------116 19 Control of Work ------116 20 Conformity With And Deviations From Plans And Stakes ------116 21 Contractor Surveying - Structure ------116 22 Superintendents, Labor and Equipment of Contractor ------119 23 Method of Serving Notices------119 24 Water and Power ------119 25 Oral Agreements ------119 26 CONTROL OF MATERIAL------120 27 Approval of Materials Prior to Use ------120 28 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC ------120 29 State Sales Tax ------120 30 Permits And Licenses ------121 31 Load Limits ------121 32 Contractor's Responsibility for Work ------121 33 Repair of Damage ------121 34 Utilities and Similar Facilities ------121 35 Public Liability and Property Damage Insurance ------121

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 February 2014 C PAGE 1 Public Convenience and Safety ------122 2 PROSECUTION AND PROGRESS ------122 3 Preliminary Matters ------122 4 Preconstruction Conference------122 5 Prosecution of Work ------123 6 Notice to Proceed and Prosecution of Work------123 7 Time for Completion ------123 8 MEASUREMENT AND PAYMENT ------124 9 Force Account ------124 10 Claims Resolution ------124 11 Claims $250,000 or Less ------124 12 DIVISION 2 13 EARTHWORK

14 REMOVAL OF STRUCTURES AND OBSTRUCTIONS ------125 15 Description ------125 16 Construction Requirements ------125 17 Removal of Pavement, Sidewalks, Curbs, and Gutters------125 18 Payment------125 19 DIVISION 3 20 AGGREGATE PRODUCTION AND ACCEPTANCE

21 ACCEPTANCE OF AGGREGATES ------126 22 Description ------126 23 Rejected Work ------126 24 General ------126 25 Rejection by Contractor ------126 26 Rejection Without Testing ------126 27 DIVISION 4 28 BASES

29 GRAVEL BASE ------127 30 Materials ------127 31 Construction Requirements ------127 32 BALLAST AND CRUSHED SURFACING ------127 33 Materials ------127 34 Construction Requirements ------127

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 February 2014 D PAGE 1 DIVISION 5 2 SURFACE TREATMENTS AND PAVEMENTS

3 CEMENT CONCRETE PAVEMENT REHABILITATION ------128 4 Construction Requirements ------128 5 Material Acceptance ------128 6 HOT MIX ASPHALT ------128 7 Construction Requirements ------128 8 Hot Mix Asphalt Pavers ------128 9 Conditioning of Existing Surface ------128 10 Preparation of Aggregates ------129 11 Mixing ------130 12 Reject Work ------130 13 Surface Smoothness ------130 14 Payment------131 15 Quality Assurance Price Adjustments ------131 16 DIVISION 7 17 DRAINAGE STRUCTURES, STORM SEWERS, SANITARY 18 SEWERS, WATER MAINS, AND CONDUITS

19 DEWATERING ------132 20 Description ------132 21 Measurement ------132 22 Payment------132 23 DIVISION 8 24 MISCELLANEOUS CONSTRUCTION

25 SUMP PUMP AND CONTROLS ------133 26 Description ------133 27 Materials ------133 28 Construction Requirements ------134 29 Measurement ------134 30 Payment------135 31 SUMP AREA ------135 32 Description ------135 33 Materials ------135 34 Construction Requirements ------135 35 Measurement ------136 36 Payment------136

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 February 2014 E PAGE 1 ELECTRICAL WORK ------136 2 Description ------136 3 Materials ------136 4 Construction Requirements ------136 5 Measurement ------136 6 Payment------136 7 DECANT AREA ------137 8 Description ------137 9 Materials ------137 10 Construction Requirements ------137 11 Measurement ------137 12 Payment------137 13 DIVISION 9 14 MATERIALS

15 AGGREGATES ------138 16 Aggregates for Ballast and Crushed Surfacing ------138 17 Crushed Surfacing ------138 18 Aggregate for Gravel Base ------138 19 DRAINAGE STRUCTURES, CULVERTS, AND CONDUITS ------138 20 Polyvinyl Chloride (PVC) Pipe ------138 21 Schedule 80 PVC Pipe and Fittings ------138 22 GUARDRAIL ------139 23 ACCESS LADDER ------139 24 ADDITIONAL SPECIAL PROVISIONS 25 26 CONCRETE FORMWORK ------142 27 CONCRETE REINFORCEMENT ------146 28 ANCHORS, INSERTS AND EMBEDDED PRODUCTS ------148 29 WATERSTOPS ------150 30 CAST-IN-PLACE CONCRETE ------151 31 GALVANIZING ------161 32 STRUCTURAL STEEL ------164 33 METAL FABRICATION ------167 34 GENERAL REQUIREMENTS FOR ELECTRICAL WORK------170 35 APPENDICES ------189 36 STANDARD PLANS ------190

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 February 2014 F 1 INTRODUCTION

2 The following Amendments and Special Provisions shall be used in conjunction with the 3 2012 Standard Specifications for Road, Bridge, and Municipal Construction. 4 5 AMENDMENTS TO THE STANDARD SPECIFICATIONS 6 7 The following Amendments to the Standard Specifications are made a part of this contract 8 and supersede any conflicting provisions of the Standard Specifications. For informational 9 purposes, the date following each Amendment title indicates the implementation date of the 10 Amendment or the latest date of revision. 11 12 Each Amendment contains all current revisions to the applicable section of the Standard 13 Specifications and may include references which do not apply to this particular project. 14 15 Section 1-01, Definition and Terms 16 August 5, 2013

17 1-01.2(2) Items of Work and Units of Measurement 18 The following abbreviation in this section is deleted: 19 20 ATB Asphalt Treated Base 21 22 1-01.3 Definitions 23 The definition for “Bid Documents” is revised to read: 24 25 The component parts of the proposed Contract which may include, but are not limited 26 to, the Proposal Form, the proposed Contract Provisions, the proposed Contract Plans, 27 Addenda, and, for projects with Contracting Agency subsurface investigations, the 28 Summary of Geotechnical Conditions and subsurface boring logs (if any). 29 30 The definition for “Superstructures” is revised to read: 31 32 The part of the Structure above: 33 34 1. The bottom of the grout pad for the simple and continuous span bearing, or 35 36 2. The bottom of the block supporting the girder, or 37 38 3. Arch skewback and construction joints at the top of vertical abutment members 39 or rigid frame piers. 40 41 Longitudinal limits of the Superstructure extend from end to end of the Structure in 42 accordance with the following criteria: 43 44 1. From the face of end diaphragm abutting the bridge approach embankment for 45 end piers without expansion joints, or 46 47 2. From the end pier expansion joint for bridges with end pier expansion joints. 48 49 Superstructures include, but are not limited to, the bottom slab and webs of box girders, 50 the bridge deck and diaphragms of all bridges, and the sidewalks when shown on the 51 bridge deck. The Superstructure also includes the girders, expansion joints, bearings,

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 1 1 barrier, and railing attached to the Superstructure when such Superstructure 2 components are not otherwise covered by separate unit measured or lump sum bid 3 items. 4 5 Superstructures do not include endwalls, wingwalls, barrier and railing attached to the 6 wingwalls, and cantilever barriers and railings unless supported by the Superstructure. 7 8 Section 1-02, Bid Procedures and Conditions 9 January 2, 2012

10 1-02.4(2) Subsurface Information 11 The first two sentences in the first paragraph are revised to read: 12 13 If the Contracting Agency has made subsurface investigation of the site of the proposed 14 work, the boring log data, soil sample test data, and geotechnical recommendations 15 reports obtained by the Contracting Agency will be made available for inspection by the 16 Bidders at the location specified in the Special Provisions. The Summary of 17 Geotechnical Conditions, as an appendix to the Special Provisions, and the boring logs 18 shall be considered as part of the Contract. 19 20 Section 1-03, Award and Execution of Contract 21 April 2, 2012

22 1-03.1(1) Tied Bids 23 This section’s title is revised to read: 24 25 1-03.1(1) Identical Bid Totals 26 27 Section 1-05, Control of Work 28 August 6, 2012

29 1-05.13(1) Emergency Contact List 30 The second sentence in the first paragraph is revised to read: 31 32 The list shall include, at a minimum, the Prime Contractor’s Project Manager, or 33 equivalent, the Prime Contractor’s Project Superintendent, the Erosion and Sediment 34 Control (ESC) Lead and the Traffic Control Supervisor. 35 36 Section 1-06, Control of Material 37 August 5, 2013

38 1-06.1(3) Aggregate Source Approval (ASA) Database 39 The last paragraph is revised to read the following two new paragraphs: 40 41 Aggregate materials that are not approved for use in the ASA database may be sampled 42 and tested by the Agency, for a specified use on a project, from the source or from a 43 processed stockpile of the material and all cost for the sampling and testing will be 44 deducted from the Contract. 45 46 The Contractor agrees to authorize the Project Engineer to deduct the sampling and 47 testing costs from any money due or coming due to the Contractor. 48

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 2 1 1-06.1(4) Fabrication Inspection Expense 2 The first paragraph is revised to read: 3 4 In the event the Contractor elects to have items fabricated beyond 300 miles from 5 Seattle, Washington, the Contracting Agency will deduct from payment due the 6 Contractor costs to perform fabrication inspection on the following items: 7 8 • Bridge Bearings (Cylindrical, Disc, Fabric Pad, Pin, Pendulum, Rocker, and 9 Spherical) 10 • Cantilever Sign Structures and Sign Bridges 11 • Epoxy-Coated Reinforcing Steel 12 • Metal Bridge Railing and Handrail 13 • Modular Expansion Joints 14 • Painted Piling and Casing 15 • Painted and Powder-Coated Luminaire and Signal Poles 16 • Precast Concrete Catch Basins, Manholes, Inlets, Drywells, and Risers 17 • Precast Concrete Drain, Perforated Underdrain, Culvert, Storm Sewer, and 18 Sanitary Sewer Pipe 19 • Precast Concrete Three Sided Structures 20 • Precast Concrete Junction Boxes, Pull Boxes, Cable Vaults, Utility Vaults, and 21 Box Culverts 22 • Precast Concrete Traffic Barrier 23 • Precast Concrete Marine Pier Deck Panels 24 • Precast Concrete Floor Panels 25 • Precast Concrete Structural Earth Walls, Noise Barrier Walls, and Wall Stem 26 Panels 27 • Precast Concrete Retaining Walls, including Lagging Panels 28 • Prestressed Concrete Girders and Precast Bridge Components 29 • Prestressed Concrete Piles 30 • Seismic Retrofit Earthquake Restrainers 31 • Soldier Piles 32 • Steel Bridges and Steel Bridge Components 33 • Steel Column Jackets 34 • Structural Steel for Ferry Terminals, including items such as Dolphins, 35 Wingwalls, and Transfer Spans 36 • Treated Timber and Lumber 6-inch by 6-inch or larger 37 • Timber 38 • Additional items as may be determined by the Engineer 39 40 The footnote below the table is revised to read: 41 42 * An inspection day includes any calendar day or portion of a calendar day spent by 43 one inspector inspecting, on standby, or traveling to and from a place of fabrication. 44 An additional cost per inspection day will be assessed for each additional inspector. 45 Reimbursement will be assessed at $280.00 per day for weekends and holidays for 46 each on site inspector in travel status, but not engaged in inspection or travel 47 activities when fabrication activities are not taking place. 48 49 Section 1-07, Legal Relations and Responsibilities to the Public 50 April 1, 2013

51 1-07.1 Laws to be Observed 52 The following two sentences are inserted after the first sentence in the third paragraph:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 3 1 2 In particular the Contractor’s attention is drawn to the requirements of WAC 296.800 3 which requires employers to provide a safe workplace. More specifically WAC 4 296.800.11025 prohibits alcohol and narcotics from the workplace. 5 6 1-07.9(2) Posting Notices 7 This section is revised to read: 8 9 Notices and posters shall be placed in areas readily accessible to read by employees. 10 The Contractor shall ensure the following are posted: 11 12 1. EEOC - P/E-1 (revised 11/09) - Equal Employment Opportunity is THE LAW 13 published by US Department of Labor. Post for projects with federal-aid 14 funding 15 16 2. FHWA-1022 (revised 11/11) - NOTICE Federal-Aid Project published by 17 Federal Highway Administration (FHWA). Post for projects with federal-aid 18 funding 19 20 3 WH 1321 (revised 04/09) - Employee Rights under the Davis-Bacon Act 21 published by US Department of Labor. Post for projects with federal-aid 22 funding 23 24 4. WHD 1088 (revised 07/09) - Employee Rights under the Fair Labor Standards 25 Act published by US Department of Labor. Post on all projects 26 27 5. WHD - 1420 (revised 01/09) - Employee Rights and Responsibilities under The 28 Family and Medical Leave Act published by US Department Of Labor. Post on 29 all projects 30 31 6. WHD-1462 (revised 01/12) – Employee Polygraph Protection Act published by 32 US Department of Labor. Post on all projects 33 34 7. F416-081-909 (revised 12/12) - Job Safety and Health Law published by 35 Washington State Department of Labor and Industries. Post on all projects 36 37 8. F242-191-909 (revised 12/12) - Notice to Employees published by Washington 38 State Department of Labor and Industries. Post on all projects 39 40 9. F700-074-909 (revised 12/12) - Your Rights as a Worker in Washington State 41 by Washington State Department of Labor and Industries (L&I). Post on all 42 projects 43 44 10. EMS 9874 (revised 04/12) - Unemployment Benefits published by Washington 45 State Employee Security Department. Post on all projects 46 47 11. Post one copy of the approved “Statement of Intent to Pay Prevailing Wages” 48 for the Contractor, each Subcontractor, each lower tier subcontractor, and any 49 other firm (Supplier, Manufacturer, or Fabricator) that falls under the provisions 50 of RCW 39.12 because of the definition of “Contractor” in WAC 296-127-010 51 52 12. Post one copy of the prevailing wage rates for the project 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 4 1 1-07.9(5) Required Documents 2 Item number 2. in the first paragraph is revised to read: 3 4 2. A copy of an approved “Affidavit of Prevailing Wages Paid”, State L&I’s form 5 number F700-007-000. The Contracting Agency will not grant Completion until all 6 approved Affidavit of Wages paid for Contractor and all Subcontractors have been 7 received by the Project Engineer. The Contracting Agency will not release to the 8 Contractor any funds retained under RCW 60.28.011 until all of the “Affidavit of 9 Prevailing Wages Paid” forms have been approved by State L&I and a copy of all 10 the approved forms have been submitted to the Engineer. 11 12 1-07.14 Responsibility for Damage 13 The fifth paragraph is revised to read: 14 15 Pursuant to RCW 4.24.115, if such claims, suits, or actions result from the concurrent 16 negligence of (a) the indemnitee or the indemnitee’s agents or employees and (b) the 17 Contractor or the Contractor’s agent or employees, the indemnity provisions provided in 18 the preceding paragraphs of this Section shall be valid and enforceable only to the 19 extent of the Contractor’s negligence or the negligence of its agents and employees. 20 21 1-07.15 Temporary Water Pollution/Erosion Control 22 The third paragraph is deleted. 23 24 Section 1-08, Prosecution and Progress 25 April 1, 2013

26 1-08.1 Subcontracting 27 In the eighth paragraph, “Contracting Agency” is revised to read “WSDOT”. 28 29 1-08.3(1) General Requirements 30 The following new paragraph is inserted after the first paragraph: 31 32 Total float belongs to the project and shall not be for the exclusive benefit of any party. 33 34 1-08.5 Time for Completion 35 The last paragraph in this section is supplemented with the following: 36 37 e. Copies of the approved “Affidavit of Prevailing Wages Paid” for the Contractor and 38 all Subcontractors 39 40 1-08.7 Maintenance During Suspension 41 The second paragraph is revised to read: 42 43 At no expense to the Contracting Agency, the Contractor shall provide through the 44 construction area safe, smooth, and unobstructed roadways and pedestrian access 45 routes for public use during the suspension (as required in Section 1-07.23 or the 46 Special Provisions.) This may include a temporary road, alternative pedestrian access 47 route or detour. 48

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 5

9-03.1 Concrete Aggregate (pavement) 4000 2000 $15.00 $30.00

1 2 2

pavement)

9-03.1 Concrete Aggregate (except 2000 1000 $15.00 $30.00

1 2 2

47

46 Table 1, the top two rows are revised to read the following three new rows: In

45

04.3( 44 8)“.

43 In the second paragraph, the reference “Section 3-04.3(6)C “ is revised to read “Section 3-

3-04.5 Payment 42

41

40 ichever is higher.) wh

39 ity of material) (unit bid price or Contingent Unit Price as shown in Table 1, (quant

38 regate Compliance Price Adjustment = (Composite Pay Factor – 1.00) Agg

37

36 The calculation in the first paragraph is revised to read:

3-04.3(8) Price Adjustments for Quality of Aggregate 35

34

33 The last sentence is deleted.

3-04.3(7)D4 An Entire Lot 32

August 5, 2013 31

Section 3-04, Acceptance of Aggregate 30

29

28 In the first paragraph, “asphalt treated base” is deleted.

3-01.1 Description 27

August 5, 2013 26

Section 3-01, Production From Quarry and Pit Sites

25 1 Section 1-09, Measurement and Payment

24

23 invoice. 2 April 1, 2013

3 1-09.1 Measurement of Quantities 4 The following new sentence is inserted after the sentence ““Ton”:2,000 pounds of 5 avoirdupois weight”: 6 7 Items of payment that have “Lump Sum” or “Force Account” in the Bid Item of Work 8 shall have no specific unit of measurement requirement. 9 10 1-09.2(5) Measurement 11 The second sentence in the first paragraph is revised to read: 12 13 The frequency of verification checks will be such that at least one test weekly is 14 performed for each scale used in weighing contract items of Work. 15 16 1-09.6 Force Account 17 In item No. 3. For Equipment, the last sentence in the third sub-paragraph is revised to 18 read: 19 20 In the event that prior quotations are not obtained and the vendor is a firm independent 21 from the Contractor or Subcontractor, then after-the-fact quotations may be obtained by 22 the Engineer from the open market in the vicinity and the lowest such quotation may be used in place of submitted

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 6 9-03.4(2) Crushed Screening3 1000 500 $20.00 $40.00 1 2 In Table 1, the row containing the item “Gravel Borrow for Geosynthetic Retaining Wall” is 3 revised to read: 4 9-03.14(4) Gravel Borrow for Structural Earth 4000 2000 $30 $60 Walls 5 6 The footnotes below the Table 1 are revised to read: 7 8 1. Based on 1000 CY of Concrete. 9 10 2 Price adjustment only applies to the actual quantity of aggregate used in the 11 concrete. 12 13 3 Contingent unit price per S.Y. is $0.30. 14 15 In Table 2, the first row is revised to read: 16 9-03.1 Concrete Aggregate (all concrete aggregate - 2 2 2 10 20 including pavement)

17 18 In Table 2, the row containing the item “Gravel Backfill for Foundations Class A” is revised to 19 read: 20 9-03.12(1)A Gravel Backfill for Foundations Class A3 21 22 In Table 2, the row containing the item “Gravel Borrow for Geosynthetic Retaining Wall” is 23 revised to read: 24 9-03.14(4) Gravel Borrow for 2 2 5 5 5 10 Other4 Structural Earth Walls 25 26 Item 1 in the footnotes below Table 2 is revised to read: 27 28 1 For Aggregate, the nominal maximum size sieve is the largest standard sieve 29 opening listed in the applicable specification upon which more than 1-percent of the 30 material by weight is permitted to be retained. For concrete aggregate, the nominal 31 maximum size sieve is the smallest standard sieve opening through which the 32 entire amount of aggregate is permitted to pass. 33 34 The footnotes below the Table 2 are supplemented with the following: 35 36 3 Use the price adjustment factors for the material that is actually used. 37 38 4 Resistivity 10, pH 10, Chlorides 5, and Sulfates 5. 39 40 Section 4-06, Asphalt Treated Base 41 August 5, 2013

42 This section including title is deleted in its entirety and replaced with the following: 43

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 7 1 Vacant 2 3 Section 5-01, Cement Concrete Pavement Rehabilitation 4 August 5, 2013

5 5-01.3(2)B Portland Cement Concrete 6 The fifth sentence in the third paragraph is revised to read: 7 8 The lower Specification limit for compressive strength shall be 4,000-psi. 9 10 The last two sentences in the third paragraph are deleted. 11 12 5-01.3(4) Replace Portland Cement Concrete Panel 13 This section is supplemented with the following: 14 15 Replacement panels that crack shall be repaired as specified in Section 5-05.3(22) at 16 no cost to the Contracting Agency. Epoxy-coated dowel bars meeting the requirements 17 of Section 9-07.5(1) may be substituted for the corrosion resistant dowel bars specified. 18 19 5-01.3(6) Dowel Bar Retrofit 20 The second sentence in the ninth paragraph is revised to read: 21 22 The foam insert shall fit tightly around the dowel and to the bottom and edges of the slot 23 and extend to the top of the existing pavement surface. 24 25 5-01.3(11) Concrete Slurry 26 This section including title is revised to read: 27 28 5-01.3(11) Concrete Slurry and Grinding Residue 29 All concrete slurry and grinding residue shall be removed from the pavement surface on 30 a continual basis immediately behind the grinding or cutting operations. Slurry shall not 31 be allowed to drain into an area open to traffic, off of the paved surface or into any 32 drainage structure. 33 34 The Contractor shall collect the concrete slurry and grinding residue from the pavement 35 surface and dispose of it in accordance with Section 2-03.3(7)C. 36 37 Opening to traffic shall meet the requirements of Section 5-05.3(17). 38 39 Section 5-02, Bituminous Surface Treatment 40 August 5, 2013

41 In this section, “Asphalt Emulsion” is revised to read “Emulsified Asphalt”. 42 43 5-02.1(1) New Construction 44 This section is revised to read: 45 46 This method of treatment requires two applications of emulsified asphalt and three 47 applications of aggregate. The first application of emulsified asphalt is applied to an 48 untreated Roadway that is followed with an application of aggregate. The second 49 application of emulsified asphalt is followed with two additional applications of 50 aggregate. 51

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 8 1 5-02.1(2) Seal Coats 2 This section is revised to read: 3 4 This method requires the placing of one application of emulsified asphalt and one or 5 more sizes of aggregate as specified to an existing pavement to seal and rejuvenate the 6 surface and to produce a uniform Roadway surface with acceptable nonskid 7 characteristics. 8 9 5-02.2 Materials 10 The following new paragraph is inserted after the second paragraph: 11 12 Each source of aggregate for bituminous surface treatment shall be evaluated 13 separately for acceptance in accordance with Section 3-04. 14 15 The second and fourth paragraphs (after implementing the preceding Amendment) are 16 deleted. 17 18 5-02.3(1) Equipment 19 The second sentence in the second paragraph is revised to read: 20 21 A temperature measuring device shall be capable of reporting the temperature of 22 emulsified asphalt in the tank. 23 24 5-02.3(2)A New Construction 25 The fourth and fifth paragraphs are revised to read: 26 27 Immediately before the first application of emulsified asphalt, the Roadway surface shall 28 be in the following condition: firm and unyielding, damp, free from irregularities and 29 material segregation, and true to line, grade, and cross-section. 30 31 No traffic will be allowed on the prepared surface until the first application of emulsified 32 asphalt and aggregate has been completed. 33 34 5-02.3(3) Application of Asphalt and Aggregate 35 The table “Application Rate” is revised to read: 36 Application Rate

Undiluted Emulsified Aggregate Asphalt (gal. Application per sq. yd.) Rate (lbs. per Applied Aggregate sq. yd.) Size New Construction

First 0.35-0.65 ½ inch- No. 4 25-45 Application or ¾ inch-½ inch

Second 0.35-0.60 ½ inch- No. 4 25-40

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 9 Application

Choke Stone N/A No. 4 - 0 4-6

Seal Coats

⅝ inch – No. 4 0.40-0.65 ⅝ inch- No. 4 25-45 Choke Stone No. 4 - 0 4-6

½ inch – No. 4 0.35-0.55 ½ inch- No. 4 20-35 Choke Stone No. 4 - 0 4-6

⅜ inch – No. 4 0.35-0.55 ⅜ inch- No. 4 20-30

Choke Stone N/A No. 4 - 0 4-6

1 2 The table “Pavement Sealing” is deleted. 3 4 The second paragraph is revised to read: 5 6 The Project Engineer will determine the application rates. The second application of 7 emulsified asphalt shall be applied the next day, or as approved by the Project Engineer. 8 9 The second to last paragraph is revised to read: 10 11 Before application of the fog seal, all surfaces shall be thoroughly cleaned of dust, soil, 12 pavement grindings, and other foreign matter. The fog seal emulsified asphalt shall be 13 CSS-1 or CSS-1h diluted with water at a rate of one part water to one part emulsified 14 asphalt unless otherwise approved by the Project Engineer. The fog seal shall be 15 uniformly applied to the pavement at a diluted rate of 0.10 – 0.18 gal/sy. The finished 16 application shall be free of streaks and bare spots. 17 18 5-02.3(5) Application of Aggregates 19 The sixth paragraph is revised to read: 20 21 The Contractor shall apply choke stone to the Roadway with additional spreading 22 equipment immediately following the initial rolling of the coarse aggregate unless 23 otherwise specified in the Contract documents or specified by the Project Engineer. 24 Excess aggregate shall be removed from the Roadway. A minimum of one pass with a 25 pneumatic roller shall be made across the entire width of the applied choke stone. 26 27 5-02.3(7) Patching and Correction of Defects 28 The last sentence in the last paragraph is revised to read: 29 30 The CSS-1 or CSS-1h emulsified asphalt may be diluted with water at a rate of one part 31 water to one part emulsified asphalt unless otherwise specified by the Project Engineer. 32

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 10 1 5-02.5 Payment 2 The first sentence in the second paragraph is revised to read: 3 4 The unit Contract price per mile for “Processing and Finishing” shall be full pay for all 5 cost to perform the specified work including, blading, scarifying, processing, leveling, 6 finishing, and the manipulation of aggregates as required 7 8 The third paragraph is revised to read 9 10 “Emulsified Asphalt (______)”, per ton. 11 12 The fourth paragraph is revised to read: 13 14 The unit Contract price per ton for “Emulsified Asphalt (______)” shall be full pay for all 15 costs to perform the specified Work including furnishing, heating, hauling, and spreading 16 the emulsified asphalt on the Roadway. 17 18 The sixth paragraph is revised to read: 19 20 The unit Contract price per ton for “Asphalt for Fog Seal” shall be full pay for all costs to 21 perform the specified Work for the fog seal. 22 23 The eighth paragraph is revised to read: 24 25 The unit Contract price per cubic yard for “Aggregate from Stockpile for BST” shall be 26 full pay for all costs to perform the specified Work including loading, transporting, and 27 placing the material in the finished Work. 28 29 The eleventh paragraph is revised to read: 30 31 The unit Contract price per cubic yard or per ton for “Furnishing and Placing Crushed 32 (______) shall be full pay for costs to perform the specified Work including furnishing, 33 transporting, and placing the material in the finished Work. 34 35 The thirteenth paragraph is revised to read: 36 37 The unit Contract price per hour for “Additional Brooming” shall be full pay for all costs 38 to perform the specified Work including rebrooming the Roadway. 39 40 Section 5-04, Hot Mix Asphalt 41 April 1, 2013

42 5-04.2 Materials 43 The following material reference is deleted from this section: 44 45 Blending Sand 9-03.8(4) 46 47 The fourth paragraph is revised to read: 48 49 The grade of asphalt binder shall be as required by the Contract. Blending of asphalt 50 binder from different sources is not permitted. 51

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 11

made for the weight of asphalt binder, mineral filler, or any other component of

38 measured by the ton in accordance with Section 1-09.2, with no deduction being 1 5-04.3(7)A1 General 2 This section is supplemented with the following: 3

4 The Contractor shall include the brand and type of anti-stripping additive in the mix

39 the 40 mixture. 41 42 The last paragraph is deleted. 43 44 5-04.5 Payment 45 46 following bid item are deleted. 47 48 Section 5-05, Cement Concrete Pavement 49 August 5, 2013

50 5-05.3(1) Concrete Mix Design for Paving 51 5 design submittal and provide certification from the asphalt binder manufacture that the 6 anti-stripping additive is compatible with the crude source and formulation of asphalt 7 binder proposed in mix design. 8 9 5-04.3(7)A3 Commercial Evaluation 10 The second sentence in the second paragraph is deleted. 11 12 5-04.3(10)B3 Longitudinal Joint Density 13 The section including title is revised to read: 14 15 5-04.3(10)B3 Vacant 16 17 5-04.3(11)D General 18 The last sentence in the first paragraph is deleted. 19 20 5-04.3(12)A Transverse Joints 21 In the second paragraph “planning” is revised to read “planing”. 22 23 5-04.3(20) Anti-Stripping Additive 24 This section is revised to read: 25 26 Anti-stripping additive shall be added to the liquid asphalt by the asphalt supplier prior to 27 shipment to the asphalt mixing plant. For HMA accepted by statistical and nonstatistical 28 evaluation the anti-stripping additive shall be added in the amount designated in the 29 WSDOT mix design/anti-strip evaluation report provided by the Contracting Agency. For 30 HMA accepted by commercial evaluation the Project Engineer will determine the 31 amount of anti-strip to be added; paving shall not begin before the anti-strip 32 requirements have been provided to the Contractor. 33 34 5-04.4 Measurement 35 The first sentence in the first paragraph is revised to read: 36 37 HMA Cl. ___ PG ___, HMA for ___ Cl. ___ PG ___, and Commercial HMA will be

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 12 1 Portland Cement Concrete Batch Weights, per cubic yard of Concrete 2 3 5-05.3(6) Subgrade 4 The last paragraph in this section is deleted. 5 6 Section 6-02, Concrete Structures 7 January 7, 2013

8 6-02.3(2) Proportioning Materials 9 The Lean Concrete value in the column “Minimum Cemetitious Content (pounds)” in the 10 table titled “Cementitious Requirement for Concrete” is revised to read: 11 12 ****145 13 14 The following new note is inserted after the note “*** No maximum specified” in the table 15 titled “Cementitious Requirement for Concrete”: 16 17 ****Maximum of 200 pounds 18 19 The paragraph following the table “Cementitious Requirements for Concrete” is revised to 20 read: 21 22 When both ground granulated blast furnace slag and fly ash are included in the 23 concrete mix, the total weight of both these materials is limited to 40 percent by weight 24 of the total cementitious material for concrete Class 4000D and 4000A, and 50 percent 25 by weight of the total cementitious material for all other classes of concrete. 26 27 6-02.3(2)B Commercial Concrete 28 The second paragraph is revised to read: 29 30 Where concrete Class 3000 is specified for items such as, culvert headwalls, plugging 31 culverts, concrete pipe collars, pipe anchors, monument cases, Type PPB, PS, I, FB 32 and RM signal standards, pedestals, cabinet bases, guardrail anchors, fence post 33 footings, sidewalks, curbs, and gutters, the Contractor may use commercial concrete. If 34 commercial concrete is used for sidewalks, curbs, and gutters, it shall have a minimum 35 cementitious material content of 564 pounds per cubic yard of concrete, shall be air 36 entrained, and the tolerances of Section 6-02.3(5)C shall apply. 37 38 6-02.3(2)D Lean Concrete 39 This section is revised to read: 40 41 Lean concrete shall meet the cementitious requirements of Section 6-02.3(2) and have 42 a maximum water/cement ratio of 2. 43 44 6-02.3(4)A Qualification of Concrete Suppliers 45 The first paragraph is revised to read : 46 47 Batch Plant Prequalification requires a certification by the National Ready Mix Concrete 48 Association (NRMCA). Information concerning NRMCA certification may be obtained 49 from the NRMCA at 900 Spring Street, Silver Springs, MD 20910 or online at 50 www.nrmca.org. The NRMCA certification shall be valid for a 2-year period from the 51 date of certificate. The following documentation shall be submitted to the Project

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 13 1 Engineer; a copy of the current NRMCA Certificate of Conformance, the concrete mix 2 design(s) (WSDOT Form 350-040), along with copies of the truck list, batch plant scale 3 certification, admixture dispensing certification, and volumetric water batching devices 4 (including water meters) verification. 5 6 6-02.3(5)G Sampling and Testing Frequency for Temperature, Consistency, 7 and Air Control 8 The last sentence in the second paragraph is revised to read: 9 10 Sampling shall be performed in accordance with WSDOT FOP for WAQTC TM 2 and 11 random samples shall be selected in accordance with WSDOT TM 716. 12 13 6-02.3(14)C Pigmented Sealer for Concrete Surfaces 14 This section is revised to read: 15 16 The Contractor shall submit the pigmented sealer manufacturer’s written instructions 17 covering, at a minimum, the following: 18 19 1. Surface preparation 20 21 2. Application methods 22 23 3. Requirements for concrete curing prior to sealer application 24 25 4. Temperature, humidity and precipitation limitations for application 26 27 5. Rate of application and number of coats to apply 28 29 The Contractor shall not begin applying pigmented sealer to the surfaces specified to 30 receive the sealer until receiving the Engineer’s approval of the submittal. 31 32 All surfaces specified in the Plans to receive pigmented sealer shall receive a Class 2 33 surface finish (except that concrete barrier surfaces shall be finished in accordance with 34 Section 6-02.3(11)A). The Contractor shall not apply pigmented sealer from a batch 35 greater than 12 months past the initial date of color sample approval of that batch by the 36 Engineer. 37 38 The pigmented sealer color or colors for specific concrete surfaces shall be as specified 39 in the Special Provisions. 40 41 The final appearance shall be even and uniform without blotchiness, streaking or 42 uneven color. Surface finishes deemed unacceptable by the Engineer shall be re- 43 coated in accordance with the manufacturer’s recommendations at no additional 44 expense to the Contracting Agency. 45 46 For concrete surfaces such as columns, retaining walls, pier walls, abutments, concrete 47 fascia panels, and noise barrier wall panels, the pigmented sealer shall extend to 1 foot 48 below the finish ground line, unless otherwise shown in the Plans. 49 50 6-02.3(16) Plans for Falsework and Formwork 51 Item No. 4 in the seventh paragraph is revised to read: 52 53 4. Conditions required by other Sections of 6-02.3(17), Falsework and Formwork.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 14 1 2 Item’s No. 5, 6, 7, and 8 in the seventh paragraph are deleted. 3 4 The following paragraph is inserted after the seventh paragraph: 5 6 Plan approval can be done by the Project Engineer for footings and walls 4 to 8 feet high 7 (excluding pedestal height) provided: 8 9 1. Concrete placement rate is 4 feet per hour or less. 10 11 2. Facing is ¾-inch plywood with grades as specified per Section 6-02.3(17)I. 12 13 3. Studs, with plywood face grain perpendicular, are 2 by 4’s spaced at 12 inches. 14 15 4. Walers with 3,000 pound safe working load ties spaced at 24 inches are two 2 by 16 4’s spaced at 24 inches. 17 18 6-02.3(17)F Bracing 19 In the first paragraph, the phrase “per Section 6-02.3(17)I” is revised to read “in accordance 20 with Section 6-02.3(17)I”. 21 22 This section is supplemented with the following new sub-section: 23 24 6-02.3(17)F5 Temporary Bracing for Bridge Girders During Diaphragm and 25 Bridge Deck Concrete Placement 26 Prestressed concrete girders shall be braced to resist forces that would cause rotation 27 or torsion in the girders caused by the placing of precast concrete deck panels and 28 concrete for the bridge deck. 29 30 Bracing shall be designed and detailed by the Contractor and shall be shown in the 31 falsework/formwork plans submitted to the Engineer for approval. These braces shall be 32 furnished, installed, and removed by the Contractor at no additional cost to the 33 Contracting Agency. The Contractor may consider the bracing effects of the 34 diaphragms in developing the falsework/formwork plans. The Contractor shall account 35 for the added load from concrete finishing machines and other construction loadings in 36 the design of the bracing. 37 38 Falsework support brackets and braces shall not be welded to structural steel bridge 39 members or to steel reinforcing bars. 40 41 6-02.3(17)F4 Temporary Bracing for Bridge Girders 42 This section including title is revised to read: 43 44 6-02.3(17)F4 Temporary Bracing for Bridge Girders During Erection 45 Steel girders shall be braced in accordance with Section 6-03.3(7)A. 46 47 Prestressed concrete girders shall be braced sequentially during girder erection. The 48 bracing shall be designed and detailed by the Contractor and shall be shown in the 49 falsework/formwork plans submitted to the Engineer for approval. The Contractor shall 50 furnish, install, and remove the bracing at no additional cost to the Contracting Agency. 51 52 At a minimum, the Contractor shall brace girders at each end and at midspan to prevent 53 lateral movement or rotation. This bracing shall be placed prior to the release of each

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 15 1 girder from the erection equipment. If the bridge is constructed with cast-in-place 2 concrete diaphragms, the bracing may be removed once the concrete in the 3 diaphragms has been placed and cured for a minimum of 24 hours. 4 5 6-02.3(17)H Formwork Accessories 6 The first paragraph is deleted and replaced with the following two new paragraphs: 7 8 Formwork accessories such as form ties, form anchors, form hangers, anchoring 9 inserts, and similar hardware shall be specifically identified in the formwork plans 10 including the name and size of the hardware, manufacturer, safe working load, and 11 factor of safety. The grade of steel shall also be indicated for threaded rods, coil rods, 12 and similar hardware. Wire form ties shall not be used. Welding or clamping formwork 13 accessories to Contract Plan reinforcing steel will not be allowed. Driven types of 14 anchorages for fastening forms or form supports to concrete, and Contractor fabricated 15 “J” hooks shall not be used. Field drilling of holes in prestressed girders is not allowed. 16 17 Taper ties may be used provided the following conditions are met: 18 19 1. The structure is not designed to resist water pressure (pontoons, floating 20 dolphins, detention vaults, etc.) 21 22 2. After the taper tie is removed, plugs designed and intended for plugging taper 23 tie holes shall be installed at each face of concrete. The plug shall be installed 24 a minimum of 1 ½” clear from the face of concrete. 25 26 3. After the plug is installed, the hole shall be cleaned of all grease, 27 contamination and foreign matter. 28 29 4. Holes on the exposed faces of concrete shall be patched and finished to match 30 the surrounding concrete. 31 32 6-02.3(25)N Prestressed Concrete Girder Erection 33 The third sentence in the fifth paragraph is revised to read: 34 35 The girders shall be braced in accordance with Sections 6-02.3(17)F4 and 6- 36 02.3(17)F5. 37 38 6-02.3(26)E5 Leak Tightness Testing 39 The first sentence in the first paragraph is revised to read: 40 41 The Contractor shall test each completed duct assembly for leak tightness after placing 42 concrete but prior to placing post tensioning reinforcement. 43 44 The second paragraph is revised to read: 45 46 Prior to testing, all grout caps shall be installed and all vents, grout injection ports, and 47 drains shall either be capped or have their shut-off valves closed. The Contractor shall 48 pressurize the completed duct assembly to an initial air pressure of 50 psi. This 49 pressure shall be held for five minutes to allow for internal adjustments within the 50 assembly. After five minutes, the air supply valve shall be closed. The Contractor shall 51 monitor and measure the pressure maintained within the closed assembly, and any 52 subsequent loss of pressure, over a period of one minute following the closure of the air 53 supply valve. The maximum pressure loss for duct assemblies equal to or less than 150

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 16 1 feet in length shall be 25 psig. The maximum pressure loss for duct assemblies greater 2 than 150 feet in length shall be 15 psig. If the pressure loss exceeds the allowable, 3 locations of leakage shall be identified, repaired or reconstructed using methods 4 approved by the Engineer. The repaired system shall then be retested. The cycle of 5 testing, repair and retesting of each completed duct assembly shall continue until the 6 completed duct assembly completes a test with pressure loss within the specified 7 amount. 8 9 Section 6-03, Steel Structures 10 August 5, 2013

11 6-03.3(7)A Erection Methods 12 The following new paragraph is inserted after the second paragraph: 13 14 The Contractor may submit for approval the use of an engineered and fabricated lifting 15 bracket bolted to the girder top flanges providing the following requirements are 16 satisfied: 17 18 1. The lifting bracket shall be engineered and supporting calculations shall be 19 submitted with the erection plan; 20 21 2. The calculations shall include critical stresses in the girder including local 22 stresses in the flanges at lifting bracket locations; 23 24 3. The calculations shall include computation of the lifting bracket and associated 25 bolt hole locations and the expected orientation of the girder during picking 26 operation; 27 28 4. The lifting bracket shall be load tested and certified for a load at least 2 times 29 the working load and at all angles it will be used (angle of load or rigging). 30 Certification documentation from a previous project may be submitted for 31 approval; 32 33 5. Bolt holes in girders added for the lifting bracket connections shall be shown in 34 the shop plans and shall be drilled in the shop. Field drilling of bolt holes for 35 lifting brackets will not be permitted; 36 37 6. Bolt holes in girder top flanges shall be filled with high strength bolts after 38 erection in accordance with Section 6-02.3(17)K. 39 40 The last sentence in the fourth paragraph (after implementing the preceding Amendment) is 41 revised to read: 42 43 The plan, including lifting bracket working drawings and calculations, shall be prepared 44 by (or under the direct supervision of) a Professional Engineer, licensed under Title 18 45 RCW, State of Washington, in the branch of Civil or Structural, and shall carry the 46 engineer’s seal and signature, in accordance with Section 6-02.3(16). 47 48 6-03.3(13) Fabricating Tension Members 49 Item number 2. is revised to read: 50 51 2. Fabricated from plate stock with the primary rolling direction of the stock parallel to 52 the length of the member, or as shown in the Plans.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 17 1 2 6-03.3(28)A Method of Shop Assembly 3 The first sentence in Item 2.C. is revised to read: 4 5 For Trusses and Girders – After the first stage has been completed, each subsequent 6 stage shall be assembled to include: at least one truss panel or girder shop section of 7 the previous stage and two or more truss panels or girder shop sections added at the 8 advancing end. 9 10 6-03.3(32) Assembling and Bolting 11 The first sentence in the fourth paragraph is revised to read: 12 13 To complete a joint following one of the methods listed above, the Contractor shall fill all 14 remaining holes of the field connection or splice place with bolts and tighten to snug- 15 tight. 16 17 The following two new paragraphs are inserted after the fourth paragraph: 18 19 The Contractor shall complete the joint or connection within ten calendar days of 20 installing the first bolt or within a duration approved by the Engineer. Any bolts inserted 21 in an incomplete connection, either loose or tightened snug-tight, which exceed the 22 specified duration for completing the connection, shall be subject to the following 23 requirements: 24 25 1. Three assemblies for each size and length shall be removed from 26 connection(s) that are to be tensioned. Rotational capacity tests shall be 27 performed on the removed assemblies to demonstrate the assembly has 28 sufficient lubricant to be tensioned satisfactorily. 29 30 2. Five assemblies shall be removed from the connection to establish the 31 inspection torque. 32 33 3. In the case of tension controlled bolts, three assemblies shall be removed and 34 tested in accordance with Section 6-03.3(33)A to verify the minimum specified 35 tension can be achieved prior to shearing of the spline. 36 37 Assemblies removed for the purpose of rotational capacity testing, determination of the 38 inspection torques, or verification of tension controlled bolt performance shall be 39 replaced with new bolts at no additional expense to the Contracting Agency. To 40 minimize the number of removed assemblies, the Contractor may combine rotational 41 capacity testing and inspection torque determination as approved by the Engineer. 42 6-03.3(33) Bolted Connections 43 The fourth paragraph is revised to read: 44 45 All bolted connections are slip critical. Painted structures require either Type 1 or Type 3 46 bolts. Unpainted structures require Type 3 bolts. Bolts shall not be galvanized unless 47 specified in the Contract documents. AASHTO M 253 bolts shall not be galvanized and 48 shall not be used in contact with galvanized metal. 49 50 In the tenth paragraph, the first paragraph of Item number 3. is revised to read: 51 52 3. Twist Off Type Tension Control Structural Bolt/Nut/Washer Assembly 53 Method (Tension Control Bolt Assembly) - Tension control bolt assemblies

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 18 1 shall include the bolt, nut, and washer(s) packaged and shipped as a single 2 assembly. Unless otherwise approved by the Engineer, tension control bolt 3 assembly components shall not be interchanged for testing or installation and 4 shall comply with all provisions of ASTM F 1852. If approved by the Engineer, 5 the tension control bolt assembly components may be interchanged within the 6 same component lot for girder web splices or other locations where access to 7 both sides of the connection is restricted. 8 9 6-03.3(33)A Pre-Erection Testing 10 The following new paragraph is inserted after the fourth paragraph: 11 12 Three twist off-type tension controlled bolt assemblies, per assembly lot, shall be tested 13 in a bolt tension calibrator. The bolts shall first be tensioned to a snug tight condition. 14 Tensioning shall then be completed by tightening the assembly nut in a continuous 15 operation using a spline drive installation tool until the spline shears from the bolt. The 16 bolt assembly tension shall meet the requirements of Table 1. If any specimen fails, the 17 assembly lot is rejected. 18 19 6-03.3(33)B Bolting Inspection 20 The first paragraph is revised to read: 21 22 The Contractor, in the presence of the Project Engineer, shall inspect the tightened bolt 23 using a calibrated inspection torque wrench, regardless of bolting method. The 24 Contractor shall supply the inspection torque wrench. Inspection shall be performed 25 within seven calendar days from the completion of each bolted connection or as 26 approved by the Project Engineer. 27 28 6-03.3(36) Setting and Grouting Masonry Plates 29 Item number 2. in the second paragraph is revised to read: 30 31 2. Place steel shims under the masonry plates to position pin centers or bearings to 32 line and grade and in relationship to each other. Steel shims shall be the size and 33 be placed at the locations shown in the Plans; 34 35 6-03.3(39) Swinging the Span 36 The second and third paragraphs are revised to read: 37 38 After the falsework is released (spans swung free), the masonry plates, shoes, and 39 keeper plates are grouted, and before any load is applied, the Contractor (or the 40 Engineer if the Contracting Agency is responsible for surveying) shall survey elevations 41 at the tenth points along the centerline on top of all girders and floorbeams. The 42 Contractor shall calculate the theoretical top of girder or floorbeam flange elevations 43 and compare the calculated elevations to the surveyed elevations. The theoretical pad 44 or haunch depth shown in the Plans shall be increased or decreased by the difference 45 between the theoretical and surveyed top of girder or floorbeam elevations. The soffit 46 (deck formwork) shall be set based on the Plan bridge deck thickness and the adjusted 47 pad or haunch depth. 48 49 The Contractor shall submit all survey data and calculations to the Engineer for review 50 ten working days prior to placing any load, beyond the maximum five pounds per square 51 foot of form weight allowed, on the Structure. 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 19 1 Section 6-05, Piling 2 August 6, 2012

3 6-05.5 Payment 4 The paragraph following the bid item, “Driving St. Pile”, per each is revised to read: 5 6 The unit Contract price per each for “Driving (type) Pile (____)” shall be full pay for 7 driving the pile to the ultimate bearing and/or penetration specified. 8 9 Section 6-06, Bridge Railings 10 August 6, 2012

11 6-06.3(2) Metal Railings 12 The third paragraph is revised to read: 13 14 Anchor bolts shall be positioned with a template to ensure that bolts match the hole 15 spacing of the bottom channels or anchorage plates. 16 17 Section 6-07, Painting 18 August 5, 2013

19 6-07.3(9)A Paint System 20 The first sentence in the second paragraph is revised to read: 21 22 All paint coating components of the selected paint system shall be produced by the 23 same manufacturer. 24 25 6-07.3(10)H Paint System 26 The first and second sentences in the second paragraph are revised to read: 27 28 All paint coating components of the selected paint system shall be produced by the 29 same manufacturer. 30 31 6-07.3(10)N Field Coating Application Methods 32 The first sentence is revised to read: 33 34 The Contractor shall apply paint materials in accordance with the manufacturer’s 35 recommendations by air or airless spray, brush, roller, or any combination of these 36 methods unless otherwise specified. 37 38 The third sentence is revised to read: 39 40 The Contractor shall use brushes to apply the stripe coat, to ensure complete coverage 41 around structural geometric irregularities, and to push the paint into gaps between 42 existing steel surfaces and around rivets and bolts. 43 44 6-07.3(10)O Applying Field Coatings 45 The first sentence in the sixth paragraph is revised to read: 46 47 All steel surfaces cleaned to bare metal by abrasive blast cleaning shall receive the 48 primer coat within the same working day as the cleaning to bare metal and before any 49 rust begins to form. 50

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 20 1 6-07.5 Payment 2 The third paragraph is revised to read: 3 4 The lump sum Contract price for “Cleaning and Painting - _____” shall be full pay for the 5 Work as specified, including developing all submittals, arranging for and 6 accommodating contact and on-site attendance by the paint manufacturer's technical 7 representative, furnishing and placing all necessary staging and rigging, furnishing, 8 operating and mooring barges, furnishing and operating fixed and movable work 9 platforms, accommodating Contracting Agency inspection access, conducting the 10 Contractor's quality control inspection program, providing material, labor, tools, and 11 equipment, furnishing containers for containment waste, collecting and storing 12 containment waste, collecting, storing, testing, and disposing of all containment waste 13 not conforming to the definition in Section 6-07.3(10)F, performing all cleaning and 14 preparation of surfaces to be painted, applying all coats of paint and sealant, correcting 15 coating deficiencies, completing coating repairs, and completing project site cleanup. 16 17 The first sentence in the fourth paragraph is revised to read: 18 19 Progress payments for "Cleaning and Painting - _____" will be made on a monthly basis 20 and will be based on the percentage of the total estimated area satisfactorily cleaned 21 and coated as determined by the Project Engineer. 22 23 Section 6-10, Concrete Barrier 24 August 5, 2013

25 6-10.3 Construction Requirements 26 This section is supplemented with the following: 27 28 Steel welded wire reinforcement deformed, conforming to Section 9-07.7, may be 29 substituted in concrete barrier in place of deformed steel bars conforming to Section 9- 30 07.2, subject to the following conditions: 31 32 1. Steel welded wire reinforcement spacing shall be the same as the deformed 33 steel bar spacing as shown in the Standard Plans. 34 35 2. The minimum cross sectional area for steel welded wire reinforcement shall be 36 no less than 86 percent of the cross sectional area for the deformed steel bars 37 being substituted. 38 39 3. Development lengths and splice lengths shall conform to requirements 40 specified in the AASHTO LRFD Bridge Design Specifications, current edition. 41 42 6-10.3(6) Placing Concrete Barriers 43 The first and second sentences in the first paragraph are revised to read: 44 45 Precast concrete barrier Types 2 and 4, precast single slope barrier, and transitions 46 shall rest on a paved foundation shaped to a uniform grade and section. The foundation 47 surface for precast concrete barrier Types 2 and 4, precast single slope barrier, and 48 transitions shall meet this test for uniformity: 49 50 6-10.5 Payment 51 In the second paragraph, the bid item “Conc. Class 4000” is revised to read: 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 21 1 “Conc. Class 4000___” 2 3 Section 6-12, Noise Barrier Walls 4 August 6, 2012

5 6-12.3(3) Shaft Construction 6 The third sentence in the fifth paragraph is revised to read: 7 8 When efforts to advance past the obstruction to the design shaft tip elevation result in 9 the rate of advance of the shaft drilling equipment being significantly reduced relative to 10 the rate of advance for the rest of the shaft excavation, then the Contractor shall remove 11 the obstruction under the provisions of Section 6-12.5. 12 13 6-12.3(6) Precast Concrete Panel Fabrication and Erection 14 The second sentence in item number 3 is deleted. 15 16 6-12.5 Payment 17 This section is supplemented with the following: 18 19 “Removing Noise Barrier Wall Shaft Obstructions”, estimated. 20 21 Payment for removing obstructions, as defined in Section 6-12.3(3), will be made for the 22 changes in shaft construction methods necessary to remove the obstruction. The 23 Contractor and the Engineer shall evaluate the effort made and reach agreement on the 24 equipment and employees utilized, and the number of hours involved for each. Once 25 these cost items and their duration have been agreed upon, the payment amount will be 26 determined using the rate and markup methods specified in Section 1-09.6. For the 27 purpose of providing a common proposal for all bidders, the Contracting Agency has 28 entered an amount for the item "Removing Noise Barrier Wall Shaft Obstructions" in the 29 bid proposal to become a part of the total bid by the Contractor. 30 31 If the shaft construction equipment is idled as a result of the obstruction removal work 32 and cannot be reasonably reassigned within the project, then standby payment for the 33 idled equipment will be added to the payment calculations. If labor is idled as a result of 34 the obstruction removal work and cannot be reasonably reassigned within the project, 35 then all labor costs resulting from Contractor labor agreements and established 36 Contractor policies will be added to the payment calculations. 37 38 The Contractor shall perform the amount of obstruction work estimated by the 39 Contracting Agency within the original time of the contract. The Engineer will consider a 40 time adjustment and additional compensation for costs related to the extended duration 41 of the shaft construction operations, provided: 42 43 1. the dollar amount estimated by the Contracting Agency has been exceeded, 44 and; 45 46 2. the Contractor shows that the obstruction removal work represents a delay to 47 the completion of the project based on the current progress schedule provided 48 in accordance with Section 1-08.3. 49

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 22 1 Section 6-13, Structural Earth Walls 2 April 1, 2013

3 6-13.2 Materials 4 In the first paragraph, the following item is inserted after the item “Aggregates for Portland 5 Cement Concrete”: 6 7 Gravel Borrow for Structural Earth Walls 9-03.14(4) 8 9 6-13.4 Measurement 10 In the second paragraph, “Backfill” is revised to read “Gravel borrow”. 11 12 6-13.5 Payment 13 In this section, the bid item “Backfill for Structural Earth Wall Incl. Haul” is revised to read: 14 15 “Gravel Borrow for Structural Earth Wall incl. Haul”. 16 17 Section 6-14, Geosynthetic Retaining Walls 18 April 1, 2013

19 6-14.2 Materials 20 The first paragraph is revised to read: 21 22 Materials shall meet the requirements of the following sections: 23 24 Portland Cement 9-01 25 Aggregates for Portland Cement Concrete 9-03.1 26 Sand 9-03.13(1) 27 Gravel Borrow for Structural Earth Wall 9-03.14(4) 28 Polyurethane Sealant 9-04.2(3) 29 Closed Cell Foam Backer Rod 9-04.2(3)A 30 Anchor Rods and Associated Nuts, Washers, and Couplers 9-06.5(1) 31 Reinforcing Steel 9-07 32 Wire Mesh for Concrete Reinforcement 9-07.7 33 Grout 9-20.3(4) 34 Construction Geosynthetic 9-33 35 36 6-14.4 Measurement 37 In the second paragraph, “geosynthetic retaining wall backfill” is revised to read ”structural 38 earth wall backfill”. 39 40 6-14.5 Payment 41 In this section, the bid item “Gravel Borrow for Geosynthetic Ret. Wall Incl. Haul”. Is revised 42 to read: 43 44 “Gravel Borrow for Structural Earth Wall incl. Haul” 45 46 Section 6-15, Soil Nail Walls 47 January 2, 2012

48 6-15.2 Materials 49 The referenced section for the following item is revised to read: 50

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 23 1 Grout 9-20.3(4) 2 3 6-15.3(3) Submittals 4 Item f beneath item number 3 is revised to read: 5 6 f. Mix design and procedures for placing the grout. 7 8 6-15.3(6) Soil Nailing 9 This section is supplemented with the following: 10 11 The Contractor shall make and cure grout cubes once per day in accordance with 12 WSDOT Test Method T 813. These samples shall be retained by the Contractor until all 13 associated verification and proof testing of the soil nails has been successfully 14 completed. If the Contractor elects to test the grout cubes for compressive strength, 15 testing shall be conducted by an independent laboratory and shall be in accordance 16 with the WSDOT FOP for AASHTO T106. 17 18 Section 6-16, Soldier Pile and Soldier Pile Tieback Walls 19 January 2, 2012

20 6-16.3(3) Shaft Excavation 21 The third sentence in the seventh paragraph is revised to read: 22 23 When efforts to advance past the obstruction to the design shaft tip elevation result in 24 the rate of advance of the shaft drilling equipment being significantly reduced relative to 25 the rate of advance for the rest of the shaft excavation, then the Contractor shall remove 26 the obstruction under the provisions of Section 6-16.5. 27 28 6-16.5 Payment 29 This section is supplemented with the following: 30 31 “Removing Soldier Pile Shaft Obstructions”, estimated. 32 33 Payment for removing obstructions, as defined in Section 6-16.3(3), will be made for the 34 changes in shaft construction methods necessary to remove the obstruction. The 35 Contractor and the Engineer shall evaluate the effort made and reach agreement on the 36 equipment and employees utilized, and the number of hours involved for each. Once 37 these cost items and their duration have been agreed upon, the payment amount will be 38 determined using the rate and markup methods specified in Section 1-09.6. For the 39 purpose of providing a common proposal for all bidders, the Contracting Agency has 40 entered an amount for the item "Removing Soldier Pile Shaft Obstructions" in the bid 41 proposal to become a part of the total bid by the Contractor. 42 43 If the shaft construction equipment is idled as a result of the obstruction removal work 44 and cannot be reasonably reassigned within the project, then standby payment for the 45 idled equipment will be added to the payment calculations. If labor is idled as a result of 46 the obstruction removal work and cannot be reasonably reassigned within the project, 47 then all labor costs resulting from Contractor labor agreements and established 48 Contractor policies will be added to the payment calculations. 49 50 The Contractor shall perform the amount of obstruction work estimated by the 51 Contracting Agency within the original time of the contract. The Engineer will consider a

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 24 1 time adjustment and additional compensation for costs related to the extended duration 2 of the shaft construction operations, provided: 3 4 1. the dollar amount estimated by the Contracting Agency has been exceeded, 5 and; 6 7 2. the Contractor shows that the obstruction removal work represents a delay to 8 the completion of the project based on the current progress schedule provided 9 in accordance with Section 1-08.3. 10 11 Section 6-17, Permanent Ground Anchors 12 August 6, 2012

13 6-17.3(3) Submittals 14 The first sentence in the sixth paragraph is revised to read: 15 16 The Contractor shall submit the mix design for the grout conforming to Section 9-20.3(4) 17 and the procedures for placing the grout to the Engineer for approval. 18 19 6-17.3(7) Installing Permanent Ground Anchors 20 The following new paragraph is inserted after the sixth paragraph: 21 22 The Contractor shall make and cure grout cubes once per day in accordance with 23 WSDOT Test Method T 813. These samples shall be retained by the Contractor until all 24 associated verification, performance and proof testing of the permanent ground anchors 25 has been successfully completed. If the Contractor elects to test the grout cubes for 26 compressive strength, testing shall be conducted by an independent laboratory and 27 shall be in accordance with the WSDOT FOP for AASHTO T106. 28 29 6-17.3(9) Permanent Ground Anchor Acceptance Criteria 30 The fourth paragraph is deleted. 31 32 Section 6-19, Shafts 33 August 5, 2013

34 6-19.3(2) Submittal 35 This section including title is revised to read: 36 37 Shaft Construction Submittals 38 The shaft construction submittal shall be comprised of the following three components: 39 construction experience; shaft installation narrative; and shaft slurry technical 40 assistance. The submittal shall be submitted in a PDF format to the Project Engineer a 41 minimum of 30 calendar days prior to the start of the Work. 42 43 6-19.3(2)A Construction Experience Submittal 44 This section’s title is revised to read: 45 46 Construction Experience 47 48 The first sentence in the first paragraph is revised to read: 49 50 The Contractor shall submit a project reference list to the Project Engineer for verifying 51 the successful completion by the Contractor of at least three separate foundation

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 25 1 projects with shafts of diameters and depths similar to or larger than those shown in the 2 Plans, and ground conditions similar to those identified in the Contract. 3 4 The first sentence in the second paragraph is revised to read: 5 6 The Contractor shall submit a list identifying the on-site supervisors and drill rig 7 operators potentially assigned to the project to the Project Engineer. 8 9 The first and second sentences in the last paragraph are deleted. 10 11 6-19.3(2)B Shaft Installation Narrative Submittal 12 This section’s title is revised to read: 13 14 Shaft Installation Narrative 15 16 The first sentence in the first paragraph is revised to read: 17 18 The Contractor shall submit a shaft installation narrative to the Engineer. 19 20 Item number 4. (except the table) is revised to read: 21 22 4. A slurry mix design, including all additives and their specific purpose in the slurry 23 mix, with a discussion of its suitability to the anticipated subsurface conditions shall 24 be submitted and include the procedures for mixing, using, and maintaining the 25 slurry. A detailed plan for quality control of the selected slurry, including tests to be 26 performed, test methods to be used, and minimum and/or maximum property 27 requirements which must be met to ensure the slurry functions as intended, 28 considering the anticipated subsurface conditions and shaft construction methods, 29 in accordance with the slurry manufacturer’s recommendations and these Special 30 Provisions shall be included. As a minimum, the slurry quality control plan shall 31 include the following tests: 32 33 Item number 9. is revised to read (except the lettered items): 34 35 9. Reinforcing steel shop drawings with details of reinforcement placement, including 36 bracing, centering, and lifting methods, and the method to ensure the reinforcing 37 cage position is maintained during construction, including use of bar boots and/or 38 rebar cage base plates, and including placement of rock backfill below the bottom 39 of shaft elevation, provided the conditions of Section 6-19.3(5)D are satisfied. 40 41 The reinforcing steel shop drawings and shaft installation narrative shall include, at 42 a minimum: 43 44 The paragraph following item number 9 n is deleted. 45 46 The first sentence in the paragraph following item number 9 n.. (after implementing the 47 preceding Amendment) is revised to read: 48 49 The Engineer will evaluate the shaft installation narrative for conformance with the 50 Plans, Specifications, and Special Provisions, within the review time specified. 51 52 6-19.3(2)C Shaft Slurry Technical Assistance Submittal 53 This section’s title is revised to read:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 26 1 2 Shaft Slurry Technical Assistance 3 4 The second sentence in the first paragraph (except for the numbered items) is revised to 5 read: 6 7 The Contractor shall submit the following to the Engineer: 8 9 6-19.3(4)B Minimum Level of Slurry in the Excavation 10 This section is revised to read: 11 12 When slurry is used in a shaft excavation the following is required: 13 14 1. The height of the slurry shall be as required to provide and maintain a stable 15 hole to prevent bottom heave, caving, or sloughing of all unstable zones. 16 17 2. The Contractor shall provide casing, or other means, as necessary to meet 18 these requirements. 19 20 3. The slurry level in the shaft while excavating shall be maintained above the 21 groundwater level the greater of the following dimensions: 22 23 a. Not less than 5 feet for mineral slurries. 24 25 b. Not less than 10 feet for water slurries. 26 27 c. Not less than 10 feet for synthetic slurries. 28 29 4. The slurry level in the shaft throughout all stops as specified in Section 6- 30 19.3(3)A and during concrete placement as specified in Section 6-19.3(7) shall 31 be no lower than the water level elevation outside the shaft. 32 33 6-19.3(4)F Slurry Disposal 34 This section including title is revised to read: 35 36 6-19.3(4)F Disposal of Slurry and Slurry Contacted Spoils 37 The Contractor shall dispose of the slurry and slurry-contacted spoils as specified in the 38 shaft installation narrative in accordance with Section 6-19.3(2)B, item 8, and in 39 accordance with the following requirements: 40 41 1. Water slurry with no additives may be infiltrated to an upland area within the 42 confines of the Contracting Agency Right of Way for the project. Infiltration is 43 allowed provided the ground-line at the disposal site is at least 5 feet above 44 the current water table, and that disposal operations conform to the temporary 45 erosion and sedimentation control (TESC) requirements established for this 46 project. For the purposes of water slurry disposal, upland is defined as an area 47 that has no chance of discharging directly to waters of the State, including 48 wetlands or conveyances that indirectly lead to wetlands or waters of the 49 State. Spoils in contact with this slurry may be disposed of as clean fill. 50 51 2. Synthetic slurry and water slurry with polymer-based additives shall be 52 contained and disposed of by the Contractor at an approved facility. The 53 Contractor shall acquire all permits or approvals necessary for disposal of the

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 27 1 slurry and shall provide copies to the Engineer. Spoils in contact with synthetic 2 slurry or water slurry with polymer-based additives shall be disposed of in 3 accordance with Section 2-03.3(7)C. With approval of the Engineer, the 4 Contractor may re-use these spoils on-site. 5 6 3. Mineral slurry may be infiltrated to a temporary sediment trap located in an 7 upland area within the confines of the Contracting Agency Right of Way for the 8 project. Infiltration is allowed provided the ground-line at the disposal site is at 9 least 5 feet above the current water table, and that disposal operations 10 conform to the temporary erosion and sedimentation control (TESC) 11 requirements established for this project. For the purposes of mineral slurry 12 disposal, upland is defined as an area that has no chance of discharging 13 directly to waters of the State, including wetlands or conveyances that 14 indirectly lead to wetlands or waters of the State. Spoils in contact with mineral 15 slurry shall be disposed of in accordance with Section 2-03.3(7)C. With 16 approval of the Engineer, the Contractor may re-use these spoils on-site. 17 18 Section 7-02, Culverts 19 August 6, 2012

20 7-02.2 Materials 21 Note 3 in the table titled, “Culvert Pipe Schedules” is revised to read: 22 23 3Polypropylene pipe, 12 inch to 30 inch diameters approved for Schedule A and 24 Schedule B, 36 inch to 60 inch diameters approved for Schedule A only. 25 26 7-02.5 27 The bid item “Steel Rib Reinforced Polyethylene Culvert Pipe _____ In. Diam.”, per linear 28 foot is revised to read: 29 30 “St. Rib Reinf Polyethylene Culv. Pipe ______In. Diam.”, per linear foot 31 32 Section 7-03, Structural Plate Pipe, Pipe Arch, Arch, and Underpass 33 August 6, 2012

34 7-03.3(1) Foundations, General 35 This section is supplemented with the following: 36 37 When aluminum pipe or pipe arch is in contact with cement concrete, two coats of paint 38 shall be applied in accordance with Section 7-08.3(2)D. 39 40 7-03.3(5) Headwalls 41 This section is supplemented with the following: 42 43 When aluminum pipe or pipe arch is in contact with cement concrete, two coats of paint 44 shall be applied in accordance with Section 7-08.3(2)D. 45 46 Section 7-04, Storm Sewers 47 August 6, 2012

48 7-04.3(1)B Exfiltration Test – Storm Sewers 49 The fifth column title “PE4” is revised to read “PP4” from the table titled, “Storm Sewer Pipe 50 Schedules”.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 28 1 2 Note 4 in the table titled, “Storm Sewer Pipe Schedules” is revised to read: 3 4 4PP = Polypropylene Pipe, 12 inch to 30 inch approved for Schedule A and Schedule B, 5 36 inch to 60 inch diameters approved for Schedule A only. 6 7 7-04.5 8 The bid item “Steel Rib Reinforced Polyethylene Storm Sewer Pipe _____ In Diam”, per 9 linear foot is revised to read: 10 11 “St. Rib Reinf Polyethylene Storm Sewer Pipe ______In. Diam”, per linear foot 12 13 Section 7-05, Manholes, Inlets, Catch Basins, and Drywells 14 April 2, 2012

15 7-05.3 Construction Requirements 16 The third paragraph is supplemented with the following: 17 18 Leveling and adjustment devices that do not modify the structural integrity of the metal 19 frame, grate or cover, and do not void the originating foundry’s compliance to these 20 specifications and warranty is allowed. Approved leveling devices are listed in the 21 Qualified Products List. Leveling and adjusting devices that interfere with the 22 backfilling, backfill density, grouting and asphalt density will not be allowed. The 23 hardware for leveling and adjusting devices shall be completely removed when 24 specified by the Project Engineer. 25 26 Section 7-08, General Pipe Installation Requirements 27 August 6, 2012

28 7-08.3(2)D Pipe Laying – Steel or Aluminum 29 The following new sentence is inserted after the first sentence in the second paragraph: 30 31 The paint shall cover all the surface in contact with the concrete and extend one inch 32 beyond the point of contact. 33 34 Section 7-09, Water Mains 35 August 6, 2012

36 7-09.3(19)A Connections to Existing Mains 37 In the second paragraph, “Special Conditions” is revised to read “Special Provisions”. 38 39 Section 8-01, Erosion Control and Water Pollution Control 40 August 5, 2013

41 8-01.2 Materials 42 The first paragraph is revised to read: 43 44 Materials shall meet the requirements of the following sections: 45 46 Corrugated Polyethylene Drain Pipe 9-05.1(6) 47 Quarry Spalls 9-13 48 Seed 9-14.2 49 Fertilizer 9-14.3

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 29 1 Mulch and Amendments 9-14.4 2 Tackifiers 9-14.4(7) 3 Erosion Control Devices 9-14.5 4 High Visibility Fence 9-14.5 5 Construction Geotextile 9-33 6 7 8-01.3(1) General 8 The last two sentences in the first paragraph are deleted. 9 10 In the seventh paragraph, “perimeter silt fencing” is revised to read “silt fencing”. 11 12 8-01.3(2)D Mulching 13 The following two new paragraphs are inserted after the fourth paragraph: 14 15 Short-Term Mulch shall be hydraulically applied at the rate of 2500 pounds per acre and 16 may be applied in one lift. 17 18 Moderate-Term Mulch and Long-Term Mulch shall be hydraulically applied at the rate of 19 3500 pounds per acre with no more than 2000 pounds applied in any single lift. 20 21 8-01.3(2)E Soil Binders and Tacking Agents 22 This section including title is revised to read: 23 24 8-01.3(2)E Tackifiers 25 Tackifiers applied using a hydroseeder shall have a mulch tracer added to visibly aid 26 uniform application. This tracer shall not be harmful to plant, aquatic, or animal life. A 27 minimum of 125 pounds per acre and a maximum of 250 pounds per acre of Short-Term 28 Mulch shall be used as a tracer. Tackifier shall be mixed and applied in accordance with 29 the manufacturer’s recommendations. 30 31 Soil Binding Using Polyacrylamide (PAM) – The PAM shall be applied on bare soil 32 completely dissolved and mixed in water or applied as a dry powder. Dissolved PAM 33 shall be applied at a rate of not more than ⅔ pound per 1,000 gallons of water per acre. 34 A minimum of 200 pounds per acre of Short-Term Mulch shall be applied with the 35 dissolved PAM. Dry powder applications may be at a rate of 5 pounds per acre using a 36 hand-held fertilizer spreader or a tractor-mounted spreader. 37 38 PAM shall be applied only to areas that drain to completed sedimentation control BMPs 39 in accordance with the TESC Plan. PAM may be reapplied on actively worked areas 40 after a 48-hour period. 41 42 PAM shall not be applied during rainfall or to saturated soils 43 44 8-01.3(2)F Dates for Application of Final Seed, Fertilizer, and Mulch 45 In the first paragraph, “Engineer” is revised to read “Project Engineer”. 46 47 Note 1 of the table in the first paragraph is revised to read: 48 49 1 Where Contract timing is appropriate, seeding, fertilizing, and mulching shall be 50 accomplished during the fall period listed above 51 52 The third paragraph is deleted. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 30 1 8-01.3(3) Placing Erosion Control Blanket 2 This section including title is revised to read: 3 4 8-01.3(3) Placing Biodegradable Erosion Control Blanket 5 Biodegradable Erosion Control Blankets are used as an erosion prevention device and 6 to enhance the establishment of vegetation. Erosion control blankets shall be installed 7 according to the manufacturer’s recommendations. 8 9 Seeding and fertilizing shall be done prior to blanket installation. 10 11 Select erosion control blanket material for an area based on the intended function: slope 12 or ditch stabilization, and site specific factors including soil, slope gradient, rainfall, and 13 flow exposure. Erosion Control Blankets shall not be used on slopes or in ditches that 14 exceed the manufacturer’s recommendations. 15 16 8-01.3(4) Placing Compost Blanket 17 This section is revised to read: 18 19 Compost blanket shall be placed to a depth of 3 inches over bare soil. Compost blanket 20 shall be placed prior to seeding or other planting. An organic tackifier shall be placed 21 over the entire composted area when dry or windy conditions are present or expected 22 before the final application of mulch or erosion control blanket. The tackifier shall be 23 applied immediately after the application of compost to prevent compost from leaving 24 the composted area. 25 26 Compost shall be Medium Compost. 27 28 8-01.3(5) Placing Plastic Covering 29 This section including title is revised to read: 30 31 Plastic Covering 32 Erosion Control - Plastic coverings used to temporarily cover stock piled 33 materials, slopes or bare soils shall be installed and maintained in a way that 34 prevents water from intruding under the plastic and prevents the plastic cover from 35 blowing open in the wind. Plastic coverings shall be placed with at least a 12-inch 36 overlap of all seams and be a minimum of 6 mils thick. 37 38 Containment - Plastic coverings used to line concrete washout areas, contain 39 wastewaters, or used in secondary containment to prevent spills, shall be seamless 40 to prevent infiltration and be a minimum of 10 mils thick. 41 42 Vegetation Management - Plastic covering placed over areas that have been 43 seeded shall be clear and where vegetative growth is to inhibited it shall be black 44 and be a minimum of 4 mils thick. 45 46 8-01.3(6) Check Dams 47 This section is revised to read: 48 49 Check dams are used as an erosion and sediment control device in channels or 50 conveyance areas. Check dams shall be installed as soon as construction will allow, or 51 when designated by the Project Engineer. The Contractor may substitute a different 52 check dam material, in lieu of what is specified in the contract, with approval of the 53 Project Engineer. Check dam materials shall meet the requirements in Section 9-

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 31 1 14.5(4). Straw bales shall not be used as check dams. The check dam is a temporary 2 or permanent structure, built across a minor channel placed perpendicular to the flow of 3 water. Water shall not flow freely through the check dam structure. Check dams shall be 4 constructed in a manner that creates a ponding area upstream of the dam to allow 5 pollutants to settle, with water from increased flows channeled over a spillway in the 6 check dam. The check dam shall be constructed to prevent erosion in the area below 7 the spillway. The outer edges shall extend up the sides of the conveyance to prevent 8 water from going around the check dam. Check dams shall be of sufficient height to 9 maximize detention, without causing water to leave the ditch. 10 11 Wattles, coir logs and compost sock used as check dams shall not be trenched in and 12 shall be installed as shown in the Standard Plans. 13 14 When wattles, coir logs, and compost socks are used as check dams they shall be 15 measured and paid as check dam in accordance with Section 8-01.4 and 8-01.5. 16 17 8-01.3(6)A Geotextile-Encased Check Dam 18 This sections content including title is deleted. 19 20 8-01.3(6)B Quarry Spall Check Dam 21 This sections content including title is deleted. 22 23 8-01.3(6)C Sandbag Check Dam 24 This sections content including title is deleted. 25 26 8-01.3(6)D Wattle Check Dam 27 This sections content including title is deleted. 28 29 8-01.3(6)E Coir Log 30 This section including title and section number is revised to read: 31 32 8-01.3(6)A Coir Log 33 Coir logs are used as erosion and sediment control or bank stabilizing device. Coir logs 34 shall be laid out, spaced, staked and installed in accordance with the Standard Plans. 35 36 Live stakes in accordance with Section 9-14.6(1) can be used in addition to, but not as a 37 replacement for, wooden stakes. 38 39 8-01.3(7) Stabilized Construction Entrance 40 The first paragraph is revised to read: 41 42 Temporary stabilized construction entrance shall be constructed in accordance with the 43 Standard Plans, prior to beginning any clearing, grubbing, embankment or excavation. 44 All quarry spall material used for stabilized construction entrance shall be free of 45 extraneous materials that may cause or contribute to track out. 46 47 8-01.3(9)A Silt Fence 48 This section and all sub-sections including title is revised to read: 49 50 8-01.3(9)A Fencing 51 8-01.3(9)A1 High Visibility Fencing 52 High visibility fencing (HVF) shall be in color and installed along the site 53 preservation lines shown in the Plans or as specified by the Engineer. Post

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 32 the 1 spacing and attachment of the fencing material to the posts shall be as shown in 2 the Standard Plans and in accordance with Section 9-14.5(8). The HVF shall not 3 be fastened to trees.

the 4

33 geotextile it supports. The strength of the wire 34 or plastic mesh shall be equivalent to or greater than as required in Section 9- 35 33.2(1), Table 6, for unsupported geotextile (i.e., 180 lbs. grab tensile strength in 36 the machine direction). Post spacing and attachments shall be as shown in 37 Standard Plans. 38 39 8-01.3(9)A3 High Visibility Silt Fence 40 High visibility silt fence (HVSF) shall be orange in color and only be used for the 41 dual purpose of demarcating site preservation lines and a sediment control device 42 in a location where high visibility mesh fence and black silt fence would otherwise 43 be used together at same location. If use of HVSF is allowed the geotextile 44 material shall meet the material requirements of Section 9-33.2(1), Table 6. Post 45 spacing and attachments shall be as shown in Standard Plans. 46 47 High Visibility Silt Fence with Backup Support 48 Where backup support is needed for high visibility silt fence (HVSF) in areas where 49 extra strength may be required, such as the toe of steep cut or fill slopes or areas 50 where equipment may push excessive soils toward the sensitive or protected 51 areas. When backup support is used, wire shall have a maximum mesh spacing of 52 2 inches, and the plastic mesh shall be as resistant to ultraviolet radiation as 5 8-01.3(9)A2 Silt Fence 6 Silt fence shall be black in color and used as a sediment control device to prevent 7 sediment laden water from leaving project boundaries, to manage stormwater 8 within the site, or to create small detention areas. Silt fence shall be installed at 9 locations shown in the Plans. The geotextile shall be securely attached to the posts 10 and support system. Post spacing and attachments shall be as shown in Standard 11 Plans. 12 13 Geotextile material shall meet the requirements of Section 9-33.2(1), Table 6 and 14 be sewn together at the point of manufacture, or at a location approved by the 15 Engineer, to form geotextile lengths as required. All sewn seams and overlaps shall 16 be located at a support post. 17 18 Posts shall be either wood or steel. Wood posts shall have minimum dimensions of 19 1¼ by 1¼ inches by the minimum length shown in the Plans. 20 21 When sediment deposits reach approximately ⅓ the height of the silt fence, the 22 deposits shall be removed and stabilized in accordance with Section 8-01.3(15). 23 24 If trenching is not feasible due to rocky soils or not advisable due to proximity to a 25 downslope sensitive area, a different sediment control device that does not require 26 trenching shall be used in place of silt fence. 27 28 Silt Fence with Backup Support 29 Where backup support is needed for silt fence in areas where extra strength may 30 be required, such as the toe of steep cut or fill slopes or areas where equipment 31 may push excessive soils toward the fence. When backup support is used, wire 32 shall have a maximum mesh spacing of 2 inches, and the plastic mesh shall be as resistant to ultraviolet radiation as

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 33 1 unsupported geotextile (i.e., 180 lbs. grab tensile strength in the machine direction). 2 Post spacing shall be as shown in Standard Plans. 3 4 When sediment deposits reach approximately 1/3 the height of the silt fence, or 8 5 inches whichever is lower, the deposits shall be removed and stabilized in 6 accordance with Section 8-01.3(15). 7 8 8-01.3(9)B Gravel Filter, Wood Chip, or Compost Berm 9 The first paragraph is revised to read: 10 11 Filter berms shall retain sediment and direct flows. The gravel filter berm shall be a 12 minimum of 1 foot in height and shall be maintained at this height for the entire time 13 they are in use. Rock material used for filter berms shall meet the grading requirements 14 in Section 9-03.9(2), but shall not include any recycled materials as outlined in Section 15 9-03.21. 16 17 The last sentence in the third paragraph is revised to read: 18 19 Compost shall be Medium Compost. 20 21 8-01.3(9)C Straw Bale Barrier 22 This section including title is revised to read: 23 24 8-01.3(9)C Vacant 25 26 8-01.3(10) Wattles 27 This section is revised to read: 28 29 Wattles are used as a flow control and sediment control device. Wattles shall be 30 installed as soon as construction will allow or when designated by the Engineer. Wattle 31 installation and trenching shall begin from the base of the slope and work uphill prior to 32 any topsoil or compost placement. Excavated material from trenching shall be spread 33 evenly along the uphill slope and be compacted using hand tamping or other method 34 approved by the Engineer. On gradually sloped or clay-type soils trenches shall be 2 to 35 3 inches deep. On loose soils, in high rainfall areas, or on steep slopes, trenches shall 36 be 3 to 5 inches deep, or half the thickness of the wattle, whichever is greater. 37 38 Wattles shall be laid out, spaced and staked in accordance with the Standard Plans. 39 Live stakes in accordance with Section 9-14.6(1) can be used in addition to, but not as a 40 replacement for, wooden stakes. If trenching and staking is not possible due to rocky 41 soils, compost socks shall be used instead of wattles. 42 43 The Contractor shall exercise care when installing wattles to ensure the method of 44 installation minimizes disturbance and prevents sediment or pollutant discharge into 45 water bodies. 46 47 8-01.3(11) Vacant 48 This section including title is revised to read: 49 50 8-01.3(11) Outlet Protection 51 Outlet protection shall prevent scour at the outlets of ponds, pipes, ditches or other 52 conveyances. All quarry spall material used for outlet protection shall be free of 53 extraneous material and meet the gradation requirements in Section 9-13.6.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 34 1 2 8-01.3(12) Compost Socks 3 This section is revised to read: 4 5 Compost socks are used as a flow control and sediment control device. Compost socks 6 shall be installed as soon as construction will allow or when designated by the Project 7 Engineer. Compost socks shall be installed prior to any mulching or compost 8 placement. Compost socks shall be laced together end-to-end with coir rope or ends 9 shall be securely overlapped to create a continuous length. Terminal ends of the 10 continuous length shall be curved 2 to 4 feet upward into the slope to prevent 11 concentrated flows from going around the terminal ends. Finished grades shall be of a 12 natural appearance with smooth transitions. Compost for compost socks shall be 13 Medium Compost. 14 15 Compost sock shall be laid out, spaced and staked in accordance with the Standard 16 Plans. Live stakes in accordance with Section 9-14.6(1) can be used in addition to, but 17 not as a replacement for, wooden stakes. If staking is not possible or if the compost 18 sock is being used on concrete, heavy blocks or an equivalent item shall be used to 19 weigh down and secure the sock. Compost socks shall be laid out, spaced and staked 20 in accordance with the Standard Plans. 21 22 The Contractor shall exercise care when installing compost socks to ensure that the 23 method of installation minimizes disturbance of waterways and prevents sediment or 24 pollutant discharge into water bodies. Stakes shall be removed to minimize soil 25 disturbance. 26 27 8-01.3(13) Temporary Curb 28 This section is revised to read: 29 30 Temporary curbs shall divert or redirect water around erodible soils. 31 32 Temporary curbs shall be installed along pavement edges to prevent runoff from flowing 33 onto erodible slopes. Water shall be directed to areas where erosion can be controlled. 34 The temporary curbs shall be a minimum of 4 inches in height. Ponding shall not be in 35 roadways. 36 37 8-01.3(16) Removal 38 The first sentence in the first paragraph is revised to read: 39 40 When the Project Engineer determines that an erosion control BMP is no longer 41 required, the Contractor shall remove the BMP and all associated hardware from the 42 project limits. 43 44 The first and second sentences in the second paragraph are revised to read: 45 46 The Contractor shall remove BMPs and associated hardware in a way that minimizes 47 soil disturbance. The Contractor shall permanently stabilize all bare and disturbed soil 48 after removal of BMP’s. 49 50 8-01.4 Measurement 51 The third paragraph is revised to read: 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 35 1 Check dams will be measured per linear foot one time only along the completed check 2 dam. No additional measurement will be made for check dams that are required to be 3 rehabilitated or replaced due to wear. 4 5 The ninth paragraph is deleted. 6 7 The twelfth paragraph (after the preceding amendment is applied) is revised to read: 8 9 Seeding, fertilizing, liming, mulching, mowing, and tackifier will be measured by the acre 10 by ground slope measurement or through the use of design data 11 12 The fifteenth paragraph (after the preceding amendment is applied) is revised to read: 13 14 Fencing will be measured by the linear foot along the ground line of the completed 15 fence. 16 17 This section is supplemented with the following: 18 19 Outlet Protection will be measured per each initial installation at an outlet location. 20 21 8-01.5 Payment 22 The paragraph following the bid item, “Plastic Covering”, per square yard is revised to read: 23 24 The unit Contract price per square yard for “Plastic Covering” shall be full payment to 25 perform the Work as specified in Section 8-01.3(5) and as shown in the Plans, including 26 removal and disposal at an approved disposal site. 27 28 The bid item “Straw Bale”, per each is deleted. 29 30 The bid item “___Erosion Control Blanket”, per square yard is deleted. 31 32 The bid item “Soil Binder or Tacking Agent”, per acre is deleted. 33 34 This section is supplemented with the following: 35 36 “Outlet Protection”, per each. 37 The unit Contract price per each for “Outlet Protection” shall be full payment for all costs 38 incurred to complete the Work. 39 40 “Tackifier”, per acre. 41 The unit Contract price per acre for “Tackifier” shall be full payment for all costs incurred 42 to complete the Work. 43 44 “Biodegradable Erosion Control Blanket”, per square yard. 45 The unit Contract price per square yard for “Biodegradable Erosion Control Blanket” 46 shall be full pay for all costs to complete the specified Work. 47 48 “High Visibility Silt Fence”, per linear foot. 49 50 Section 8-02, Roadside Restoration 51 August 5, 2013

52 In this section, “psiPE” is revised to read “PSIPE”.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 36 1 2 8-02.3(2) Roadside Work Plan 3 The first sentence in the second paragraph is revised to read: 4 5 The Roadside Work Plan shall also include a copy of the approved progress schedule. 6 7 The sub paragraph titled “Progress Schedule” is deleted. 8 9 8-02.3(4)C Topsoil Type C 10 In this section, “9-14.1(2)” is revised to read “9-14.1(3)”. 11 12 8-02.3(8) Planting 13 Item number 1 in the second paragraph is revised to read: 14 15 1. Non-Irrigated Plant Material 16 West of the summit of the Cascade Range - October 1 to March 1. 17 East of the summit of the Cascade Range - October 1 to November 15. 18 19 8-02.4 Measurement 20 The first sentence is revised to read: 21 22 Topsoil, mulch and soil amendments will be measured by the acre along the grade and 23 slope of the area covered immediately after application. 24 25 The seventh sentence is revised to read: 26 27 Compost will be measured by the acre along the grade and slope of the area covered 28 immediately after application. 29 30 8-02.5 Payment 31 The bid item “Topsoil Type _____”, per cubic yard and following paragraph are revised to 32 read: 33 34 “Topsoil Type ____”, per acre. 35 36 The unit contract price per acre for “Topsoil Type ____” shall be full pay for providing the 37 source of material for topsoil Type A and C, for pre-excavation weed control, excavating, 38 loading, hauling, intermediate windrowing, stockpiling, weed control on stockpiles or 39 windrows, and removal, placing, spreading, processing, cultivating, and compacting 40 topsoil Type A, Type B, and Type C. 41 42 The bid item “Fine Compost”, per cubic yard is revised to read: 43 44 “Fine Compost”, per acre. 45 46 The bid item “Medium Compost”, per cubic yard is revised to read: 47 48 “Medium Compost”, per acre. 49 50 The bid item “Coarse Compost”, per cubic yard and following paragraph are revised to read: 51 52 “Coarse Compost”, per acre. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 37 1 The unit Contract price per cubic yard for “Fine Compost”, Medium Compost” or 2 “Coarse Compost” shall be full pay for furnishing and spreading the compost onto the 3 existing soil. 4 5 The bid item “Soil Amendment”, per cubic yard and following paragraph are revised to read: 6 7 “Soil Amendment”, per acre. 8 9 The unit Contract price per acre for “Soil Amendment” shall be full pay for furnishing and 10 incorporating the soil amendment into the existing soil. 11 12 The bid item “Bark or Wood Chip Mulch”, per cubic yard and following paragraph are revised 13 to read: 14 15 “Bark or Wood Chip Mulch”, per acre. 16 17 The unit Contract price per acre for “Bark or Wood Chip Mulch” shall be full pay for 18 furnishing and spreading the mulch onto the existing soil. 19 20 Section 8-03, Irrigation Systems 21 April 2, 2012

22 8-03.3(7) Flushing and Testing 23 The fifth paragraph is deleted. 24 25 Section 8-04, Curbs, Gutters, and Spillways 26 April 2, 2012

27 8-04.3(1) Cement Concrete Curbs, Gutters, and Spillways 28 This section is supplemented with the following new sub-section: 29 30 8-04.3(1)B Roundabout Cement Concrete Curb and Gutter 31 Roundabout cement concrete curb and gutter and roundabout splitter island nosing curb 32 shall be shaped and finished to match the shape of the adjoining curb as shown in the 33 Plans. All other requirements for cement concrete curb and cement concrete curb and 34 gutter shall apply to roundabout cement concrete curb and gutter. 35 36 8-04.4 Measurement 37 This section is supplemented with the following: 38 39 Roundabout splitter island nosing curb will be measured per each. 40 41 8-04.5 Payment 42 The bid item, “Roundabout Truck Apron Cement Concrete Curb”, per linear foot is deleted. 43 44 This section is supplemented with the following: 45 46 “Roundabout Cement Concrete Curb and Gutter”, per linear foot 47 48 The unit Contract price per linear foot for “Roundabout Cement Concrete Curb and 49 Gutter” shall be full payment for all costs for the Work including transitioning the 50 roundabout cement concrete curb and gutter to the adjoining curb shape. 51

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 38 1 “Roundabout Splitter Island Nosing Curb”, per each. 2 3 The unit Contract price per each for “Roundabout Splitter Island Nosing Curb” shall be 4 full payment for all costs for the Work including transitioning the roundabout splitter 5 island nosing curb to the adjoining curb shape. 6 7 Section 8-07, Precast Traffic Curb and Block Traffic Curb 8 January 7, 2013

9 This section’s title is revised to read: 10 11 8-07 Precast Traffic Curb 12 13 8-07.1 Description 14 This section is revised to read: 15 16 This Work consists of furnishing and installing precast traffic sloped mountable curb or 17 dual faced sloped mountable curb of the design and type specified in the Plans in 18 accordance with these Specifications and the Standard Plans in the locations indicated 19 in the Plans or as staked by the Engineer. 20 21 8-07.2 Materials 22 The material reference “Block Traffic Curb 9-18.3” is deleted from this section. 23 24 The referenced section for the following item is revised to read: 25 26 Paint 9-34.2 27 28 8-07.3(1) Installing Curbs 29 The fifth and seventh paragraphs are deleted from this section. 30 31 8-07.4 Measurement 32 The first paragraph is deleted from this section. 33 34 8-07.5 Payment 35 The following bid items are deleted from this section: 36 37 “Type A Precast Traffic Curb”, per linear foot. 38 “Type C Precast Traffic Curb”, per linear foot. 39 “Type A Block Traffic Curb”, per linear foot. 40 “Type C Block Traffic Curb”, per linear foot. 41 42 Section 8-11, Guardrail 43 August 5, 2013

44 8-11.2 Materials 45 The following material reference is deleted from this section: 46 47 Weathering Steel Beam Guardrail 9-16.8 48 49 8-11.3(1)B Erection of Rail 50 The last sentence in the first paragraph is revised to read:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 39 1 2 All holes shall be painted with two coats of paint conforming to Section 9-08.1(2)B. 3 4 The fourth paragraph is revised to read: 5 6 Galvanized steel rail plates shall be fastened to the posts with galvanized bolts, 7 washers, and nuts of the size and kind shown in the Plans. 8 9 The last paragraph is deleted. 10 11 8-11.3(1)D Removing Guardrail and Guardrail Anchor 12 The first two sentences in the first paragraph are revised to read: 13 14 Removal of the various types of guardrail shall include removal of the rail, cable 15 elements, hardware, and posts, including transition sections, expansion sections, 16 terminal sections and the rail element of anchor assemblies. Removal of the various 17 types of guardrail anchors shall include removal of the anchor assembly, including 18 concrete bases, rebar, steel tubes, and any other appurtenances in the anchor 19 assembly. 20 21 8-11.4 Measurement 22 The seventh paragraph is revised to read: 23 24 Measurement of removal of guardrail will be by the linear foot measured along the line 25 of guardrail removed including transition sections, expansion sections, guardrail anchor 26 rail elements and terminal sections. 27 28 8-11.5 Payment 29 The bid item “Weathering St. Beam Guardrail Type ____”, per linear foot is deleted. 30 31 The second paragraph is revised to read: 32 33 The unit Contract price per linear foot for “Beam Guardrail Type____”, “Beam Guardrail 34 Type 1-____ Ft. Long Post”, and “Beam Guardrail Type 31-____ Ft. Long Post”, shall be 35 full payment for all costs to obtain and provide materials and perform the Work as 36 described in Sections 8-11.3(1)A and 8-11.3(1)B, including costs for additional rail 37 elements when nested rail is required, and when connections to concrete masonry 38 Structures are required. 39 40 The paragraph following the bid item “Removing Guardrail Anchor”, per each is revised to 41 read: 42 43 The unit Contract price per each for “Removing Guardrail Anchor” shall be full payment 44 for all costs to perform the Work as described in Section 8-11.3(1)D, including rail 45 removal, if there isn’t a Bid Item for Removing Guardrail in the run of guardrail 46 connecting to the anchor. 47 48 Section 8-12, Chain Link Fence and Wire Fence 49 April 2, 2012

50 In this Section “Engineer” is revised to read “Project Engineer”. 51

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 40 1 8-12.2 Materials 2 This section is supplemented with the following: 3 4 Paint 9-08.1(2)B 5 6 8-12.3(1)A Posts 7 The words “for Type 3 and Type 4 fences” and “on Type 3 and Type 4 fences” are deleted 8 from this section. 9 10 The first sentence of the fifth paragraph is revised to read: 11 12 After the post is set and plumbed, the hole shall be filled with Grout Type 4. 13 14 The third sentence in the sixth paragraph is replaced with the following two sentences: 15 16 After the post is set and plumbed, the hole in the portion of the post in solid rock shall 17 be filled with Grout Type 4. The grout shall be thoroughly worked into the hole so as to 18 leave no voids. 19 20 The seventh paragraph is deleted. 21 22 The ninth paragraph is revised to read: 23 24 Steep slopes or abrupt topography may require changes in various elements of the 25 fence. It shall be the responsibility of the Contractor to provide all posts of sufficient 26 length to accommodate the chain link fabric. 27 28 The tenth paragraph is revised to read: 29 30 All round posts shall have approved top caps fastened securely to the posts. The base 31 of the top cap fitting for round posts shall feature an apron around the outside of the 32 posts. 33 34 8-12.3(1)B Top Rail 35 This section’s content including title is deleted and replaced with: 36 37 8-12.3(1)B Vacant 38 39 8-12.3(1)C Tension Wire and Tension Cable 40 This section’s content including title is revised to read: 41 42 8-12.3(1)C Tension Wire 43 Tension Wires shall be attached to the posts as detailed in the Plans or as approved by 44 the Engineer. 45 46 47 8-12.3(1)D Chain Link Fabric 48 The first three paragraphs are revised to read: 49 50 Chain link fabric shall be attached after the cables and wires have been properly 51 tensioned. 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 41 1 Chain link fabric shall be placed on the face of the post away from the Highway, except 2 on horizontal curves where it shall be placed on the face on the outside of the curve 3 unless otherwise directed by the Project Engineer. 4 5 Chain link fabric shall be placed approximately 1-inch above the ground and on a 6 straight grade between posts by excavating high points of ground. Filling of depressions 7 will be permitted only upon approval of the Project Engineer. 8 9 The fourth sentence in the fourth paragraph is revised to read: 10 11 The top and bottom edge of the fabric shall be fastened with hog rings to the top and 12 bottom tension wires as may be applicable, spaced at 24-inch intervals. 13 14 8-12.3(1)E Chain Link Gates 15 The third paragraph is deleted. 16 17 8-12.3(2)A Posts 18 In the second paragraph, “commercial” is deleted. 19 20 The first sentence of the fifth paragraph is revised to read: 21 22 After the post is set and plumbed, the hole shall be filled with Grout Type 4. 23 24 The fourth sentence in the sixth paragraph is replaced with the following two sentences: 25 26 After the post is set and plumbed, the hole in the portion of the post in solid rock shall 27 be filled with Grout Type 4. The grout shall be thoroughly worked into the hole so as to 28 leave no voids. 29 30 The tenth paragraph is revised to read: 31 32 Where the new fence joins an existing fence, the 2 shall be attached in a manner 33 satisfactory to the Project Engineer, and end or corner posts shall be set as necessary. 34 35 The eleventh paragraph is deleted. 36 37 8-12.5 Payment 38 The paragraph following the item “Chain Link Fence Type ____”, per linear foot is revised to 39 read: 40 41 The unit Contract price per linear foot for “Chain Link Fence Type ___” shall be full 42 payment for all costs for the specified Work including brace post installation and all 43 other requirements of Section 8-12 for Chain Link Fence, unless covered in a separate 44 Bid Item in this Section. 45 46 The following paragraph is inserted after the item “End, Gate, Corner, and Pull Post for 47 Chain Link Fence”, per each: 48 49 The unit Contract price per each for “End, Gate, Corner, and Pull Post for Chain Link 50 Fence” shall be full payment for all costs for the specified Work. 51 52 The following paragraph is inserted after the item “Single 6 Ft. Chain Link Gate”, per each: 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 42 1 The unit Contract price per each for “Double 14 Ft. Chain Link Gate”, “Double 20 Ft. 2 Chain Link Gate”, and “Single 6 Ft. Chain Link Gate”, shall be full payment for all costs 3 for the specified Work. 4 5 The paragraph following the item “Wire Fence Type ____”, per linear foot is revised to read 6 7 The unit Contract price per each for “Wire Fence Type ____” shall be full payment for all 8 costs for the specified Work including payment for clearing of the fence line. 9 10 The following paragraph is inserted after the item “Double Wire Gate 20 Ft. Wide”, per each: 11 12 The unit contract price per each for “Single Wire Gate 14 Ft. Wide” and “Double Wire 13 Gate 20 Ft. Wide” shall be full payment for all costs for the specified Work. 14 15 The paragraph following the item “Access Control Gate”, per each is revised to read: 16 17 The unit contract price per each for “Access Control Gate” shall be full payment for all 18 costs to perform the specified Work. 19 20 Section 8-15, Riprap 21 April 2, 2012

22 8-15.1 Description 23 The second paragraph is revised to read: 24 25 Riprap will be classified as heavy loose riprap, light loose riprap, and hand placed 26 riprap. 27 28 Section 8-20, Illumination, Traffic Signal Systems, And Electrical 29 August 5, 2013

30 8-20.3(4) Foundations 31 The first paragraph is revised to read: 32 33 Foundation concrete shall conform to the requirements for the specified class, be cast- 34 in-place concrete and be constructed in accordance with Sections 6-02.2 and 6-02.3. 35 Concrete for Type II, III, IV, V, and CCTV signal standards and light standard 36 foundations shall be Class 4000P. Concrete for pedestals and cabinets, Type PPB, PS, 37 I, FB, and RM signal standards and other foundations shall be Class 3000. Concrete 38 placed into an excavation where water is present shall be placed using an approved 39 tremie. If water is not present, the concrete shall be placed such that the free-fall is 40 vertical down the center of the shaft without hitting the sides, the steel reinforcing bars, 41 or the steel reinforcing bar cage bracing. The Section 6-02.3(6) restriction for 5-feet 42 maximum free-fall shall not apply to placement of Class 4000P concrete into a shaft. 43 Steel reinforcing bars for foundations shall conform to Section 9-07. 44 45 8-20.3(5) Conduit 46 This sections content is deleted and replaced with the following new sub-sections: 47 48 8-20.3(5)A General 49 The ends of all conduit, metallic and nonmetallic, shall be reamed to remove burrs and 50 rough edges. Field cuts shall be made square and true. The ends of unused conduits 51 shall be capped. When conduit caps are removed, the threaded ends of metal conduit

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 43 1 shall be provided with approved conduit bushings and non-metal conduit shall be 2 provided with end bells. 3 4 Reducing couplings will not be permitted. 5 6 Existing conduit in place scheduled for installation of new conductor(s) shall first have 7 any existing conductor(s) removed and a cleaning mandrel shall be pulled through. The 8 existing conduit shall then be prepared subject to the same requirements outlined in this 9 paragraph, for new conduit and innerduct, unless otherwise indicated in the plans. All 10 new conduit and all innerduct shall be blown clean with compressed air. Then in the 11 presence of the Engineer, an 80 percent sizing mandrel, correctly sized for the raceway, 12 shall be pulled through to ensure that the raceway has not been deformed. This shall 13 be done prior to pulling wire or fiber optic cable and after final assembly is in place. 14 Existing conductor(s) shall be reinstalled unless otherwise indicated in the Plans. 15 16 As soon as the sizing mandrel has been pulled through innerduct, a 200-lb minimum 17 tensile strength pull string shall be installed and attached to duct plugs at both ends. 18 When conduit is installed for future use, as soon as the bushing or end bell has been 19 installed and the sizing mandrel has been pulled through, the ground wire shall be 20 installed and both ends shall be capped. 21 22 8-20.3(5)A1 Fiber Optic Conduit 23 Where conduit to contain fiber optic cable or conduit identified to contain future fiber 24 optic cable is installed by open trenching, Detectable Underground Warning Tape 25 shall be placed 12-inches above the conduit unless otherwise detailed in the Plans. 26 Detectable Underground Warning Tape shall extend 2-feet into boxes or vaults. 27 Splicing of the tape shall be in accordance with tape manufacturer’s recommended 28 materials and procedures. 29 Location Wire shall be installed with all nonmetallic conduit that contains fiber optic 30 cable and all conduits identified to contain future fiber optic cable. When open 31 trenching is used, the location wire shall be placed in continuous lengths directly 32 above the conduit. Where conduit is installed by other methods, the Location Wire 33 shall be attached to the outside of the conduit with electrical tape placed at 34 minimum 18-inch intervals. Location Wire shall extend 12-feet into boxes or vaults. 35 Splices shall be crimped using a non-insulated butt splice, soldered and covered 36 with moisture-blocking heat shrink. 37 38 8-20.3(5)A2 ITS and Cabinet Outer and Inner Duct Conduit 39 ITS conduit and both ends of conduit runs entering cabinets, with the exception of 40 the ½ inch grounding conduit, shall be sealed with self expanding water proof foam 41 or mechanical plugs; unless otherwise required. At other locations conduit shall be 42 sealed with Duct Seal. 43 44 Outer-duct conduit with non factory assembled innerduct shall be sealed around 45 the innerduct with self-expanding waterproof foam. Outer-duct conduit with factory 46 assembled innerduct shall be sealed around the innerduct with a multiplex 47 expansion plug. Innerduct containing one cable shall be plugged using an 48 expandable split plug. Innerduct with multiple cables shall be sealed with self- 49 expanding waterproof foam. Duct plugs shall be installed in all unused inner-ducts 50 (those that are specified as empty) at the time of conduit installation. Duct plugs 51 shall be installed in all used inner-ducts (as specified in the Plans), at the time of 52 conduit installation, unless cable pulling for those inner-ducts will commence within 53 48-hours. Installation shall conform to the manufacturer’s recommendations. 54

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 44 1 Foam sealant shall be installed with the following additional requirements: 2 3 1. Penetration of the sealant into the conduit or duct shall be limited using a 4 high temperature backer rod material or rag. 5 2. Penetration of the sealant into the conduit shall be limited to 1-inch. 6 3. The foam sealant shall not project outside the end of the conduit or duct. 7 8 Where open trenching is allowed and conduit with innerduct is installed, a 9 maximum of 1000-feet of continuous open trench will be allowed unless otherwise 10 approved by the Engineer. 11 12 8-20.3(5)B Conduit Type 13 Conduit shall be PVC, high density polyethylene (HDPE), rigid metal conduit (RMC) or 14 liquid tight flexible metal depending on the application. 15 16 Rigid metal conduit (RMC) shall be installed at the following locations: 17 18 1. Within railroad right of way. 19 20 2. All pole risers, except when otherwise required by owning utilities. 21 22 3. All surface-mounted conduit, with the exception of electrical service utility 23 poles. 24 25 4. All runs within slip form placed concrete. 26 27 Service lateral runs shall be Schedule 80 PVC except when otherwise required by 28 owning utilities. Conduit installed using the plowing method, shall be schedule 80 high- 29 density polyethylene (HDPE). 30 31 Conduit runs, including outer-duct, that enter the traveled way or shoulders, shall be 32 Schedule 80 high-density polyethylene (HDPE), Schedule 80 PVC, or rigid metal 33 conduit (RMC). 34 35 Conduit runs, including outer-duct, which do not enter the traveled way or shoulders, 36 shall be Schedule 80 high-density polyethylene (HDPE), Schedule 40 PVC or rigid 37 metal conduit (RMC). 38 39 Liquid tight flexible metal conduit is allowed only at locations called for in the Plans. 40 41 Except as described under Non-Metallic Conduit, unless otherwise indicated in the 42 Plans or Standard Plans, the same type of conduit shall be used for the entire length of 43 the run, from outlet to outlet. 44 45 Innerduct shall have a smooth wall non ribbed interior surface, with factory pre- 46 lubricated coating. 47 48 Innerduct within the Traveled Way or Shoulders and innerduct which is not factory 49 installed shall be schedule 40 high-density polyethylene (HDPE). The innerduct shall be 50 continuous with no splices. Innerduct which is pulled into the outer duct in the field shall 51 be installed with an extra 2 feet of conduit beyond each end of the outer-duct and shall 52 be allowed to finish contracting for 21 calendar days before it is terminated. Innerduct 53 shall be terminated with end bells flush to ¼ inch out of the outer-duct and the space

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 45 1 between the outer-duct and innerduct shall be sealed with rodent and moisture resistant 2 foam designed for this application and installed in accordance with the manufacturer’s 3 recommendations. 4 5 8-20.3(5)B1 Rigid Metal Conduit 6 Slip joints or running threads will not be permitted for coupling metallic conduit; 7 however, running threads will be permitted in traffic signal head spiders and rigid 8 metal conduit (RMC) outer-duct. When installing rigid metal conduit (RMC), if a 9 standard coupling cannot be used, an approved three-piece coupling shall be used. 10 Conduit bodies, fittings and couplings for rigid metal conduit (RMC) shall be 11 cleaned first and then painted with one coat of paint conforming to Section 9- 12 08.1(2)B. The paint shall have a minimum wet film thickness of 3-mils. The painted 13 coating shall cover the entire coupling or fitting. The threads on all metal conduit 14 shall be rust-free, clean, and painted with colloidal copper suspended in a 15 petroleum vehicle before couplings are made. All metallic couplings shall be 16 tightened so that a good electrical connection will be made throughout the entire 17 length of the conduit run. If the conduit has been moved after assembly, it shall be 18 given a final tightening from the ends prior to backfilling. 19 20 Rigid metal conduit (RMC) ends shall be terminated with grounded end bushings. 21 Rigid metal conduit (RMC) entering cable vaults or pull boxes shall extend 2-inches 22 beyond the inside wall face. (for the installation of grounded end bushing and 23 bonding.) 24 Rigid metal conduit (RMC) entering concrete shall be wrapped in 2-inch-wide pipe 25 wrap tape with a minimum 1-inch overlap for 12-inches on each side of the 26 concrete face. Pipe wrap tape shall be installed in accordance with the 27 manufacturer’s recommendations. 28 29 Rigid metal conduit (RMC) bends shall have a radius consistent with the 30 requirements of Code Article 344.24 and other articles of the Code. Where factory 31 bends are not used, conduit shall be bent, using an approved conduit bending tool 32 employing correctly sized dies, without crimping or flattening, using the longest 33 radius practicable. 34 35 Where the coating on galvanized conduit has been damaged in handling or 36 installing, such damaged areas shall be thoroughly painted with paint conforming to 37 Section 9-08.1(2)B. 38 39 Metal conduit ends shall be threaded and protected with a snug fitting plastic cap 40 that covers the threads until wiring is started. 41 42 8-20.3(5)B2 Non-Metallic Conduit 43 Where non-metallic conduit is installed, care shall be used in excavating, installing, 44 and backfilling, so that no rocks, wood, or other foreign material will be left in a 45 position to cause possible damage. 46 47 PVC conduit ends shall be terminated with end bell bushings. PVC or HDPE 48 conduit entering cable vaults and pull boxes shall terminate with the end bell flush 49 with the inside walls of the Structure. 50 51 Non-metallic conduit bends, where allowed, shall conform to Article 352.24 of the 52 Code. Eighteen-inch radius elbows shall be used for PVC conduit of 2-inch nominal 53 diameter or less. Standard sweep elbows shall be used for PVC conduit with 54 greater than 2-inch nominal diameter unless otherwise specified in the Plans. In

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 46 1 nonmetallic conduit less than 2-inch nominal diameter, pull ropes or flat tapes for 2 wire installation shall be not less than ¼-inch diameter or width. In nonmetallic 3 conduit of 2-inch nominal diameter or larger, pull ropes or flat tapes for wire 4 installation shall be not less than ½-inch diameter or width. When HDPE conduit is 5 used for directional boring, it shall be continuous, with no joints, for the full length of 6 the bore. The conduit run shall be extended to the associated outlets with the same 7 schedule HDPE or PVC conduit. Entry into associated junction box outlets shall be 8 with the same schedule PVC conduit and elbows. The same requirements apply for 9 extension of an existing HDPE conduit crossing. 10 11 PVC conduit and elbows shall be connected to HDPE conduit with an approved 12 mechanical coupling. The connection shall have minimum pullout strength of 700- 13 pounds. Prior to installation of a mechanical coupling, the HDPE conduit shall first 14 be prepared with a clean, straight edge. A water-based pulling lubricant may be 15 applied to the threaded end of the mechanical coupling before installation. Solvent 16 cement or epoxy shall not be used on the threaded joint when connecting the 17 HDPE conduit to the mechanical coupling. The mechanical coupling shall be 18 rotated until the HDPE conduit seats approximately ¾ of the distance into the 19 threaded coupling depth. 20 21 For PVC installation through a directional bore, the PVC shall be in rigid sections 22 assembled to form a watertight bell and spigot-type mechanical joint with a solid 23 retaining ring around the entire circumference of the conduit installed in accordance 24 with the manufacturer’s recommendations. The conduit run shall be extended 25 beyond the length of the bore, to the associated outlets with the same mechanical 26 coupled PVC or with standard PVC conduit of the same schedule. The same 27 requirements apply for extension of an existing PVC conduit Roadway crossing. 28 29 PVC conduit shall be assembled using the solvent cement specified in Section 9- 30 29.1. 31 32 Conduit ends shall be protected with a snug fitting plastic cap until wiring is started. 33 34 Conduit caps, end bells and the section of PVC between the coupling and end bell 35 bushing in cabinet foundations shall be installed without glue. 36 37 8-20.3(5)C Conduit Size 38 The size of conduit used shall be as shown in the Plans. Conduits smaller than 1-inch 39 electrical trade size shall not be used unless otherwise specified, except that grounding 40 conductors at service points may be enclosed in ½-inch-diameter conduit. 41 Conduit between light standards, PPB, PS, or Type 1 poles and the nearest junction box 42 shall be the diameter specified in the Plans. Larger size conduit is not allowed at these 43 locations. At other locations it shall be the option of the Contractor, at no expense to the 44 Contracting Agency, to use larger size conduit if desired, provided that junction box or 45 vault capacity is not exceeded. Where larger size conduit is used, it shall be for the 46 entire length of the run from outlet to outlet. 47 Conduit runs with innerduct, shall have 4-inch outer-duct and shall be installed with four 48 1-inch innerduct unless otherwise indicated in the plans. 49 50 8-20.3(5)D Conduit Placement 51 Conduit shall be laid so that the top of the conduit is a minimum depth of: 52 53 1. 24-inches below the bottom of curb in the sidewalk area.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 47 1 2 2. 24-inches below the top of the roadway base. 3 4 3. 48-inches below the bottom of ties under railroad tracks unless otherwise 5 specified by the railroad company. 6 7 4. 36-inches below finish grade when installed using conduit plowing method. 8 9 5. 24-inches below the finish grade in all other areas. 10 11 Conduit entering through the bottom of a junction box shall be located near the end 12 walls to leave the major portion of the box clear. At all outlets, conduit shall enter from 13 the direction of the run, terminating 6 to 8-inches below the junction box lid and within 3- 14 inches of the box wall nearest its entry location. 15 16 Conduit runs shown in the Plans are for Bidding purposes only and may be relocated 17 with approval of the Engineer, to avoid obstructions. 18 19 8-20.3(5)D1 Surface Mounting 20 Where surface mounting of conduit is required, supports shall consist of channel with 21 clamps sized for the conduit. Support spacing shall comply with the Code, with the 22 exception that spacing of channel supports for conduit shall not exceed 5-feet. 23 The minimum distance between adjacent clamps and between the clamp and the end of 24 the channel supports shall be 1-inch. Channel supports shall be installed with stops, to 25 prevent clamps from sliding out of the ends. 26 27 8-20.3(5)D2 Structures 28 All conduits attached to or routed within bridges, retaining walls, and other structures 29 shall be equipped with approved expansion, deflection, and/or combination 30 expansion/deflection fittings at all expansion joints and at all other joints where structure 31 movement is anticipated, including locations where the Contractor, due to construction 32 method, installs expansion and/or construction joints with movement. All conduit fittings 33 shall have movement capacity appropriate for the anticipated movement of the 34 Structure at the joint. Approved deflection fittings shall also be installed at the joint 35 between the bridge end and the retaining wall end, and the transition from bridge, wall, 36 or other structure to the underground section of conduit pipe. 37 38 8-20.3(5)E Method of Conduit Installation 39 Conduit shall be placed under existing pavement by approved directional boring, 40 jacking, or drilling methods at locations approved by the Engineer. The pavement shall 41 not be disturbed unless allowed in the Plans or with the approval of the Engineer in the 42 event obstructions or impenetrable soils are encountered. High density polyethylene 43 (HDPE) conduit runs, which enter the traveled way or shoulders, shall be installed using 44 the directional boring method. 45 46 8-20.3(5)E1 Open Trenching 47 When open trenching is allowed, trench construction shall conform to the following: 48 49 1. The pavement shall be saw-cut a minimum of 3-inches deep. The cuts 50 shall be parallel to each other and extend 2-feet beyond the edge of the 51 trench. 52 53 2. Pavement shall be removed in an approved manner.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 48 1 2 3. Trench depth shall provide a minimum cover for conduit of 24-inches 3 below the top of the roadway base 4 5 4. Trench width shall be 8-inches or the conduit diameter plus 2-inches, 6 whichever is larger. 7 8 5. Trenches located within paved Roadway areas shall be backfilled with 9 Controlled density fill (CDF) meeting the requirements of Section 2- 10 09.3(1)E. The controlled density fill shall be placed level to, and at the 11 bottom of, the existing pavement. The pavement shall be replaced with 12 paving material that matches the existing pavement. 13 14 6. On new construction, conduit shall be placed prior to placement of base 15 course pavement. 16 17 8-20.3(5)E2 Conduit Plowing 18 All conduit plowing shall be supervised by a licensed electrical Contractor. 19 The starting point shall be anchored or held such that conduit movement at the 20 start of the plowing operation is kept to a minimum. The conduit reel shall be 21 mounted on the vehicle such that conduit movement is kept to a minimum once it is 22 in the ground. Use of a stationary reel is not allowed. The feed shoe shall have 23 rollers which conform to the conduit at a radius of not less than 15 times the 24 diameter of the conduit. The conduit will not be permitted to pass over stationary 25 guides nor over rollers or sheaves, which will permit a bend radius of less than 15 26 times conduit diameter. The width of the tooth and feed shoe shall not exceed the 27 conduit diameter by more than 2-inches 28 The conduit shall be installed using a continuous reel, with no joints, for the full 29 length of the conduit run, unless conduit splicing is allowed as indicated below. 30 31 If an obstruction is encountered that cannot be plowed through, the following 32 remedies shall be attempted in order: 33 34 1. Contractor shall stop the plowing operation and attempt to remove the 35 obstruction. If the obstruction is removed, plowing operations shall 36 continue along the approved path. 37 38 2. Deviations of up to one foot from the projected path may be authorized by 39 the Engineer, provided the new route does not result in total conduit run 40 bends exceeding NEC requirements. Deviations in excess of one foot 41 from the projected path are not allowed and the maximum taper rate is 1- 42 inch per linear foot of conduit. 43 44 3. The Contractor may request approval to intercept the installed conduit and 45 route another section of HDPE to avoid the obstruction, provided the new 46 route does not result in total conduit run bends exceeding NEC 47 requirements. Connection between the sections shall be accomplished 48 using an approved fusion splicing method, which is compatible with the 49 conduit manufacturer’s recommendations. 50 51 4. Where none of the above remedies are successful, all conduit installed so 52 far in that run shall be removed and a new plow path established to avoid 53 the obstruction. 54

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 49 1 In the event of a breakage, all conduit installed in that run shall be removed. 2 3 The conduit run shall be extended to the associated outlets, subject to the same 4 requirements indicated when HDPE is installed using the directional boring method. 5 6 The depth of installation shall be continually adjusted as necessary to compensate 7 for changes in terrain. 8 9 Plowed conduit shall be laid so that the top of the conduit is a minimum depth of 10 36-inches below the finish grade with the exception that the conduit shall be swept 11 up to enter the knock outs of associated pull boxes or cable vaults. 12 13 The plow placing the conduit shall be marked at a proper distance above the plow’s 14 conduit exit point to indicate when the minimum installation depth is not met. The 15 mark shall be visible from a safe distance from the plowing operation when it is 16 exposed above ground. While plowing this mark must remain below ground level 17 at all times, with the exception of the entry and exit points at the end of the run, in 18 order to ensure that minimum burial depth of the conduit is achieved. 19 20 If the depth mark on the plow comes above ground, the Contractor shall stop the 21 plowing operation and attempt to correct the placement depth. If the conduit depth 22 can be verified to meet the minimum burial requirements at the location where the 23 depth mark came above ground, the plowing operation shall resume subject to the 24 Engineers approval. 25 26 The compacted surface shall be firm, non-yielding, and result in a finished surface 27 that matches the lines and grades of the terrain prior to plowing. 28 29 8-20.3(5)E3 Boring 30 Bore pits shall be backfilled and compacted in accordance with Section 2-09.3(1)E. 31 Directional boring, jacking or drilling pits shall be a minimum of 2-feet from the edge 32 of any type of pavement, unless otherwise approved by the engineer. Excessive 33 use of water that might undermine the pavement or soften the Subgrade will not be 34 permitted. 35 36 When approved by the Engineer, small test holes may be cut in the pavement to 37 locate obstructions. When the Contractor encounters obstructions or is unable to 38 install conduit because of soil conditions, as determined by the Engineer, additional 39 Work to place the conduit will be paid in accordance with Section 1-04.4. 40 41 8-20.3(5)E4 Directional Boring 42 Directional boring for electrical installations shall be supervised by a licensed 43 electrical contractor in accordance with Section 8-20.1(1). Where directional boring 44 is called for, conduit shall be installed using a surface-launched, steerable drilling 45 tool. Drilling shall be accomplished using a high-pressure fluid jet tool-head. The 46 drilling fluid shall be used to maintain the stability of the tunnel, reduce drag on the 47 conduit, and provide backfill between the conduit and tunnel. A guidance system 48 that measures the depth, lateral position, and roll shall be used to guide the tool- 49 head when creating the pilot hole. Once the pilot hole is established, a reamer and 50 swivel shall be used to install the conduit. Reaming diameter shall not exceed 1.5 51 times the diameter of the conduits being installed. Conduit that is being pulled into 52 the boring shall be installed in such a manner that the conduit is not damaged 53 during installation. The pullback force on the conduit shall be controlled to prevent 54 damage to the conduit. A vacuum spoils extraction system shall be used to remove

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 50 1 any excess spoils generated during the installation. Excess drilling fluid and spoils 2 shall be disposed of. The method and location used for disposal of excess drilling 3 fluid and spoils shall be subject to the Engineer’s approval. Drilling fluid returns 4 (caused by fracturing of formations) at locations other than the entry and exit points 5 shall be minimized. Any drilling fluid that surfaces through fracturing shall be 6 cleaned up immediately. Mobile spoils-removal equipment capable of quickly 7 removing spoils from entry or exit pits and areas with returns caused by fracturing 8 shall be used as necessary during drilling operations. 9 10 8-20.3(5)E5 Boring with Casing 11 Where boring with casing is called for, the casing shall be placed using an auger 12 inside the casing to remove the soil as the casing is jacked forward. The auger 13 head shall proceed no more than 4-inches ahead of the pipe being jacked. Boring 14 operations shall be conducted to prevent caving ahead of the pipe. Installed casing 15 pipe shall be free from grease, dirt, rust, moisture, and any other deleterious 16 contaminants. 17 18 The space between the conduit and casing shall be plugged with sandbags and a 19 grout seal 12-inches thick at each end of the casing. Casing abandoned due to an 20 encountered obstruction shall be grout sealed in the same manner. Grout shall 21 conform to Section 9-20.3(4). 22 23 In lieu of sandbags and grout, unopened prepackaged concrete and grout may be 24 used to seal the casing. 25 26 Material shall not be removed from the boring pit by washing or sluicing. 27 All joints shall be welded by a Washington State certified welder. Welding shall 28 conform to AWS D 1.1-80 Structural Welding Code, Section 3, Workmanship. 29 30 8-20.3(8) Wiring 31 The fifteenth through seventeenth paragraphs are revised to read: 32 33 When conductors, either cable or single, are being installed, the Contractor shall not 34 exceed the tension limitations recommended by the manufacturer. Conductors may be 35 pulled directly by hand, or with mechanical assistance. If conductors are pulled by any 36 mechanical means, a dynamometer with drop-needle hand shall be used on every 37 mechanically assisted pull. 38 39 On mechanically assisted pulls, insulation shall be stripped off the individual conductor 40 and the conductor formed into a pulling eye and firmly attached to the pulling rope/tape, 41 or a cable grip shall be used. The Contractor shall determine the maximum allowable 42 pulling tension, taking into account the direction of the pull, type of raceway, cable 43 geometry, weight of the cable, the coefficient of friction, and side wall pressure, using 44 the information from the cable manufacturer. If there are bends in the raceway or 45 sheaves are used for the cable pull, the Contractor shall use the cable manufacture’s 46 side wall pressure limits to determine the maximum pulling tension. The maximum 47 pulling force applied directly to the conductor when pulling eyes are used or when the 48 conductor is formed into a loop, shall be limited to that shown in the following table for 49 copper conductor. When a cable grip is applied over nonmetallic sheathed cables, the 50 maximum pulling force shall be limited to 1,000-pounds provided this is not in excess of 51 the force as determined above. 52 Conductor Pounds

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 51

8 132

6 210

4 334

3 421

2 531

1 669

1/0 845

2/0 1,065

3/0 1,342

4/0 1,693

250Kcmil 2,000 500Kcmil 4,000 1 2 Adequate lubrication of the proper type to reduce friction in conduit and duct pulls shall 3 be utilized. The grease and oil-type lubricants used on lead sheathed cables shall not 4 be used on nonmetallic sheathed cables. 5 6 8-20.3(9) Bonding, Grounding 7 The first sentence in the second paragraph is replaced with the following two sentences: 8 9 All conduit installed shall have an equipment ground conductor installed in addition to 10 the conductors noted in the Contract. Conduit with innerducts shall have an equipment 11 ground conductor installed in each innerduct that has an electrical conductor. 12 13 Section 8-21, Permanent Signing 14 January 7, 2013

15 8-21.2 Materials 16 The third sentence is revised to read: 17 18 Materials for sign mounting shall conform to Section 9-28.11. 19 20 8-21.3(9)A Fabrication of Steel Structures 21 The first sentence in the first paragraph is revised to read: 22

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 52 1 Fabrication shall conform to the applicable requirements of Section 6-03 and 9-06. 2 3 This section is supplemented with the following: 4 5 All fabrication, including repairs, adjustments or modifications of previously fabricated 6 sign structure members and connection elements, shall be performed in the shop, under 7 an Engineer approved shop drawing prepared and submitted by the Contractor for the 8 original fabrication or the specific repair, adjustment or modification. Sign structure 9 fabrication repair, adjustment or modification of any kind in the field is not permitted. If 10 fabrication repair, adjustment or modification occurs after a sign structure member or 11 connection element has been galvanized, the entire member or element shall be re- 12 galvanized in accordance with AASHTO M 111. 13 14 8-21.3(9)B Vacant 15 This section including title is revised to read: 16 17 8-21.3(9)B Erection of Steel Structures 18 Erection shall conform to the applicable requirements of Sections 6-03 and 8-21.3(9)F. 19 Section 8-21.3(9)F notwithstanding, the Contractor may erect a sign bridge prior to 20 completion of the shaft cap portion of one foundation for one post provided the following 21 conditions are satisfied: 22 23 1. The Contractor shall submit design calculations and working drawings of the 24 temporary supports and falsework supporting the sign bridge near the location 25 of the incomplete foundation to the Engineer for approval in accordance with 26 Section 6-01.9. The submittal shall include the method of releasing and 27 removing the temporary supports and falsework without inducing loads and 28 stress into the sign bridge. 29 30 2. The Contractor shall submit the method used to secure the anchor bolt array in 31 proper position with the sign bridge while casting the shaft cap concrete to 32 complete the foundation. 33 34 3. The Contractor shall erect the sign bridge and temporary supports and 35 falsework, complete the remaining portion of the incomplete foundation, and 36 remove the temporary supports and falsework, in accordance with the working 37 drawing submittals as approved by the Engineer. 38 39 8-21.3(9)F Foundations 40 The following new paragraph is inserted after the second paragraph: 41 42 Concrete placed into an excavation where water is present shall be placed using an 43 approved tremie. If water is not present, the concrete shall be placed such that the free- 44 fall is vertical down the center of the shaft without hitting the sides, the steel reinforcing 45 bars, or the steel reinforcing bar cage bracing. The Section 6-02.3(6) restriction for 5- 46 feet maximum free-fall shall not apply to placement of Class 4000P concrete into a 47 shaft. 48 49 The ninth paragraph (after implementing the preceding Amendment) is replaced with the 50 following three new paragraphs: 51 52 After construction of concrete foundations for sign bridge and cantilever sign structures, 53 the Contractor shall survey the foundation locations and elevations, the anchor bolt

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 53 1 array locations and lengths of exposed threads. The Contractor shall confirm that the 2 survey conforms to the sign structure post, beam, span and foundation design geometry 3 shown in the Plans, and shall identify any deviations from the design geometry shown in 4 the Plans. When deviations are identified, the Contractor shall notify the Engineer, and 5 such notice shall be accompanied by the Contractor’s proposed method(s) of 6 addressing the deviations, including removal and reconstruction of the shaft cap portion 7 of the affected concrete foundation as outlined in this Section, or fabrication repair, 8 adjustment or modification, with associated shop drawings, in accordance with Section 9 8-21.3(9)A. 10 11 If the Contractor’s survey indicates that a concrete foundation has been constructed 12 incorrectly for a sign structure that has already been fabricated, the Contractor may 13 remove and reconstruct the shaft cap portion of the foundation, in accordance with 14 Section 1-07.13, provided the following conditions are satisfied: 15 16 1. The Contractor shall submit the method and equipment to be used to remove 17 the portion of the concrete foundation to be removed and reconstructed to the 18 Engineer for approval in accordance with Section 1-05.3. The submittal shall 19 include confirmation that the equipment and the method of operation is 20 appropriate to ensure that the existing anchor bolt array and primary shaft 21 vertical steel reinforcing bars will not be damaged. 22 23 2. All steel reinforcing bars, except for steel reinforcing bars extending from the 24 bottom portion of the foundation to remain, shall be removed and disposed of 25 in accordance with Sections 2-02.3 and 2-03.3(7)C, and shall be replaced with 26 new steel reinforcing bars conforming to the size, dimensions and geometry 27 shown in the Plans. All concrete of the removed portion of the foundation shall 28 be removed and disposed of in accordance with Sections 2-02.3 and 2- 29 03.3(7)C. 30 31 3. The Contractor shall adjust the primary shaft vertical steel reinforcing bars as 32 necessary in accordance with Section 6-02.3(24)C to provide clearance for the 33 anchor bolt array. 34 35 Sign structures shall not be erected on concrete foundations until the Contractor 36 confirms that the foundations and the fabricated sign structures are either compatible 37 with each other and the design geometry shown in the Plans, or have been modified in 38 accordance with this Section and as approved by the Engineer to be compatible with 39 each other, and the foundations have attained a compressive strength of 2,400-psi. 40 41 Item number 4 in the twelfth paragraph (after implemented the preceding Amendments) is 42 revised to read: 43 44 4. Concrete shall be Class 4000P, except as otherwise specified. The concrete for the 45 shaft cap (the portion containing the anchor bolt array assemblies above the 46 construction joint at the top of the shaft) shall be Class 4000. 47 48 Item number 3 in the thirteenth paragraph (after implemented the preceding Amendments) is 49 revised to read: 50 51 3. Unless otherwise shown in the Plans, concrete shall be Class 4000P. 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 54 1 8-21.5 Payment 2 This section is supplemented with the following: 3 4 All costs in connection with surveying completed concrete foundations for sign bridges 5 and cantilever sign structures shall be included in the lump sum contract price for 6 “Structure Surveying”, except that when no Bid item is included in the Proposal for 7 “Structure Surveying” then such costs shall be included in the lump sum contract 8 price(s) for “Sign Bridge No. ___” and “Cantilever Sign Structure No. ___”. 9 10 11 Section 8-22, Pavement Marking 12 January 7, 2013

13 8-22.3(3)D Line Applications 14 The last paragraph is supplemented with the following: 15 16 Grooved line pavement marking shall not be constructed on bridge decks or on bridge 17 approach slabs. 18 19 8-22.3(6) Removal of Pavement Markings 20 The following two new sentences are inserted after the first sentence: 21 22 Grinding to remove painted markings is not allowed. Grinding to remove plastic marking 23 is allowed to a depth just above the pavement surface, then water blasting or shot 24 blasting shall be required to remove the remaining markings. 25 26 8-22.4 Measurement 27 The items “Painted Wide Line” and “Plastic Wide Line” are deleted from the fourth 28 paragraph. 29 30 The sixth paragraph is revised to read: 31 32 Diagonal lines used to delineate parking stalls that are constructed of painted or plastic 33 4-inch lines will be measured as “Paint Line” or “Plastic Line” by the linear foot of line 34 installed. Crosswalk line will be measured by the square foot of marking installed. 35 36 The following two new paragraphs are inserted after the sixth paragraph: 37 38 Crosshatch markings used to delineate median and gore areas will be measured by the 39 completed linear foot as “Painted Crosshatch Marking” or “Plastic Crosshatch Marking”. 40 41 The measurement for “Painted Crosshatch Marking” and for “Plastic Crosshatch 42 Marking” will be based on the total length of each 8-inch or 12-inch wide line installed. 43 44 8-22.5 Payment 45 The bid items “Painted Wide Line”, per linear foot and “Plastic Wide Line”, per linear foot are 46 deleted from this section. 47 48 This section is supplemented with the following two new bid items: 49 50 “Painted Crosshatch Marking”, per linear foot. 51 “Plastic Crosshatch Marking”, per linear foot. 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 55 1 The following new paragraph is inserted after the last bid item in this section: 2 3 The unit Contract price for the aforementioned Bid items shall be full payment for all 4 costs to perform the Work as described in Section 8-22. 5 6 Section 8-25, Glare Screen 7 April 9, 2012

8 In this section, “tension cable” and “cable” are deleted. 9 10 8-25.3(3) Posts 11 The first sentence in the first paragraph is revised to read: 12 13 Posts shall be constructed in accordance with the Standard Plans and applicable 14 provisions of Section 8-12.3(1)A. 15 16 The last paragraph is revised to read: 17 18 All round posts for Type 1 Design B and Type 2 glare screen shall be fitted with a 19 watertight top securely fastened to the post. Line posts shall have tops designed to 20 carry the top tension wire. 21 22 8-25.3(5) Tension Cables 23 This sections content including title is deleted: 24 25 8-25.3(6) Fittings, Attachments, and Hardware 26 This sections content including title is deleted. 27 28 Section 8-29, Wire Mesh Slope Protection 29 January 7, 2013

30 This section is deleted in its entirety and replaced with the following: 31 32 8-29 Wire Mesh Slope Protection

33 8-29.1 Description 34 This Work consists of furnishing and installing the anchors and the wire mesh slope 35 protection in accordance with these Specifications and the details shown in the Plans and in 36 conformity with the lines and dimensions shown in the Plans or established by the Engineer. 37 38 8-29.2 Materials 39 Materials shall meet the requirements of Section 9-16.4. 40 41 8-29.3 Construction Requirements 42 8-29.3(1) Submittals 43 The Contractor shall submit a wire mesh slope protection plan to the Project Engineer a 44 minimum of seven calendar days prior to beginning the work. The wire mesh slope 45 protection plan shall include the following: 46 47 1. Plan sheets for anchor layout and installation, and the equipment and process 48 used to confirm the capacity of the constructed anchors including the 49 calibration data for the stressing devices used to proof test the anchors, as

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 56 1 completed by an independent testing laboratory within 60 calendar days of the 2 wire mesh slope work. 3 4 2. Working drawings for the temporary yoke or load frame to be used for anchor 5 proof testing in accordance with Section 6-01.9. 6 7 3. Plans and details for assembling wire mesh and erecting the assembled mesh 8 on the slope. 9 10 All costs for the Work required for Submittals shall be included in the unit Bid price 11 detailed in Section 8-29.5. 12 13 8-29.3(2) Anchors 14 The Contractor shall install anchors of the type shown in the Plans and in conformance 15 with the layout shown in the Wire Mesh Protection Plan as described in Section 8- 16 29.3(1). The spacing and number of the anchors and wire ropes as shown in the Plans 17 are approximate only, and upon review of the wire mesh slope protection plan, the 18 Engineer may arrange the spacing to better hold the wire mesh against the slope. 19 Backfill material shall be thoroughly compacted with a mechanical compactor. 20 21 The Contractor shall proof test up to 25 percent of the anchors in vertical pullout to the 22 minimum allowable anchor capacity specified in the Plans. Proof testing of anchors shall 23 be performed against a temporary yoke or load frame. No part of the temporary yoke or 24 load frame shall bear within three feet of the anchor being tested. For vertical pullout 25 proof testing, an anchor is acceptable if it sustains the specified capacity for 10 minutes 26 with no loss of load. Anchors that fail this criterion shall be replaced and retested. If 27 more than three anchors fail, the Contractor shall proof test all anchors. 28 29 8-29.3(3) Wire Rope 30 All wire rope loops shall include a thimble. No wire rope splicing will be allowed. 31 32 8-29.3(4) Wire Mesh 33 The wire mesh shall be fastened to the completed wire rope assembly as shown in the 34 Plans. High tensile steel fasteners on the vertical seams shall be staggered across 35 width of the seam. Horizontal splices joining 2 rolls of mesh shall be made by 36 overlapping the mesh approximately 3 feet and either weaving 3 rows of lacing wires 37 through every mesh opening or using 4 rows of high tensile steel fasteners placed on 38 approximately 3-inch spacing. All top and bottom laps shall be made by folding the 39 mesh to the outside, away from the slope, to avoid the possibility of falling material 40 hanging up in the folds. The bottom of the mesh shall be located as shown in the Plans. 41 The ends of all lacing wires shall be secured to the mesh with a minimum of 1½-turns. 42 43 The wire mesh shall not be tensioned in any direction, but is to remain loose so as to 44 increase its dampening effect on rolling rocks. The Contractor shall use care in the 45 handling and installing of the wire mesh and wire rope. Any mesh or wire rope damaged 46 due to the Contractor’s operations shall be replaced by the Contractor at no expense to 47 the Contracting Agency. 48 49 8-29.4 Measurement 50 Measurement of anchors will be per each for the completed anchor. Anchor types will not be 51 differentiated. 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 57 1 Wire mesh slope protection will be measured by the square foot of wire mesh erected on the 2 slope. There will be no deduction made for overlapping the wire mesh material as required 3 for splices or for coverage due to variations in the slope or ground conditions. 4 5 8-29.5 Payment 6 Payment will be made in accordance with Section 1-04.1, for each of the following Bid items 7 that are included in the Proposal: 8 9 “Wire Mesh Slope Protection Anchor”, per each. 10 The unit Contract price per each for “Wire Mesh Slope Protection Anchor” shall be full 11 payment for all costs for the Work described in Sections 8-29.3(1) and 8-29.3(2). 12 13 “Wire Mesh Slope Protection”, per square foot 14 The unit Contract price per square foot for “Wire Mesh Slope Protection” shall be full 15 payment for all costs for the Work described in Section 8-29.3(3) and 8-29.3(4). 16 17 Section 9-02, Bituminous Materials 18 August 5, 2013

19 In this section, “Asphalt Emulsion” is revised to read “Emulsified Asphalt”. 20 21 9-02.1 Asphalt Material, General 22 In this section, “Cationic Emulsified Asphalt” is revised to read “Emulsified Asphalt”. 23 24 The first paragraph is revised to read: 25 26 Asphalt furnished under these Specifications shall not have been distilled at a 27 temperature high enough to produce flecks of carbonaceous matter, and upon arrival at 28 the Work, shall show no signs of separation into lighter and heavier components. 29 30 9-02.1(6) Cationic Emulsified Asphalt 31 The “Cationic Emulsified Asphalt Table” is revised to read: 32 Cationic Emulsified Asphalt Table

Rapid Setting Medium Setting Slow Setting

Type CRS-1 CRS-2 CMS-2S CMS-2 CMS-2h CSS-1 CSS-1h AASHTO Test Grade Method Min. Max Min. Max. Min. Max. Min. Max. Min. Max. Min. Max. Min. Max.

Tests on Emulsified Asphalts:

Viscosity T 59 20 100 20 100 SFS @ 77ºF (25°C)

Viscosity T 59 20 100 150 400 50 450 50 450 50 450 SFS @ 122ºF (50°C)

Storage T 59 1 1 1 1 1 1 1 stability

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 58 test 1 day %

Demulsibili ty 35 ml

0.8% sodium dioctyl

sulfosucci T 59 40 40 nate, %a

Particle T 59 Pos Pos Pos Pos Pos Posb Posb charge test

Sieve T 59 0.10 0.10 0.10 0.10 0.10 0.10 0.10 Test, %

Cement mixing T 59 2.0 2.0 test, %

Distillation:

Oil distillate by vol. T 59 3 1.5 3 20 12 12 of emulsions %

Residue, T 59 60 65 60 65 65 57 57 %

Tests on residue from distillation tests:

Penetratio n, 77ºF T 49 100 250 100 250 100 250 100 250 40 90 100 250 40 90 (25°C)

Ductility, 77ºF (25°C) T 51 40 40 40 40 40 40 40 5 cm/min., cm

Solubility in T 44 97.5 97.5 97.5 97.5 97.5 97.5 97.5 trichloroet hylene, %

a The demulsibility test shall be made within 30 days from date of shipment.

b If the particle charge test for CSS-1 and CSS-1h is inconclusive, material having a maximum pH value of 6.7 will be acceptable. 1 2 9-02.1(6)A Polymerized Cationic Emulsified Asphalt CRS-2P 3 The first paragraph (except for the table) is revised to read: 4

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 59 1 CRS-2P shall be a polymerized cationic emulsified asphalt. The polymer shall be milled 2 into the asphalt or emulsion during the manufacturing of the emulsified asphalt. CRS-2P 3 shall meet the following requirements: 4 5 Footnote 1 below the table is revised to read: 6 7 1. Distillation modified to use 300 grams of emulsified asphalt heated to 350°F ± 9°F 8 and maintained for 20 minutes. 9 10 9-02.1(8) Flexible Bituminous Pavement Marker Adhesive 11 The fifth row in the table is revised to read: 12 Ductility, 39.2ºF, 1 cm/minute, cm AASHTO T 51 5 Min. 13 14 9-02.4 Anti-Stripping Additive 15 This section is revised to read: 16 17 Anti-stripping additive shall be a product listed in the current WSDOT Qualified Products 18 List (QPL). 19 20 Section 9-03, Aggregates 21 August 5, 2013

22 9-03.1(1) General Requirements 23 The eighth paragraph is deleted. 24 25 9-03.6 Aggregate for Asphalt Treated Base (ATB) 26 This section including title is deleted in its entirety and replaced with the following: 27 28 Vacant 29 30 9-03.8(4) Blending Sand 31 This sections including title is revised to read: 32 33 Vacant 34 35 9-03.13 Backfill for Sand Drains 36 This section is supplemented with the following: 37 38 That portion of backfill retained on a No. 4 sieve shall not contain more than 0.05 39 percent by weight of wood waste. 40 41 9-03.13(1) Sand Drainage Blanket 42 The last paragraph is revised to read: 43 44 That portion of backfill retained on a No. 4 sieve shall not contain more than 0.05 45 percent by weight of wood waste. 46 47 9-03.14(1) Gravel Borrow 48 Note 1 is deleted, including the reference in the table. 49

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 60 1 9-03.14(2) Select Borrow 2 Note 1 is deleted. 3 4 Note 2 is re-numbered Note 1, including the reference in the table. 5 6 9-03.14(4) Gravel Borrow for Geosynthetic Retaining Wall 7 This section including title is revised to read: 8 9 Gravel Borrow for Structural Earth Wall 10 All backfill material within the reinforced zone for structural earth walls shall consist of 11 granular material, either naturally occurring or processed, and shall be free draining, 12 free from organic or otherwise deleterious material. The material shall be substantially 13 free of shale or other soft, poor durability particles, and shall not contain recycled 14 materials, such as glass, shredded tires, portland cement concrete rubble, or asphaltic 15 concrete rubble. The backfill material shall meet the following requirements for grading 16 and quality: 17 Geosynthetic Metallic

Reinforcement Reinforcement Sieve Size Percent Passing Percent Passing 4 99-100 2 75-100 1 ¼ “ 1 99-100 1” 90-100 No. 4 50-80 50-80 No. 40 30 max. 30 max. No. 200 7.0 max. 7.0 max. Sand Equivalent 50 min. 50 min. 18 19 All percentages are by weight 20 Property Test Method Geosynthetic Metallic Reinforcement Reinforcement Requirements Requirements Los Angeles Wear AASHTO T 96 35 percent max. 35 percent max 500 rev. Degradation Factor WSDOT Test Method T 15 min. 15 min. 113 Resistivity WSDOT Test Method T 3,000 ohm-cm, 417 min. pH WSDOT Test Method 4.5-9 5-10 113 Chlorides AASHTO T 291 100 ppm max. Sulfates AASHTO T 290 200 ppm max. 21 22 If the resistivity of the gravel borrow equals or exceeds 5,000 ohm-cm, the specified 23 chloride and sulfate limits may be waived. 24 25 Wall backfill material satisfying these grading and property requirements shall be 26 classified as nonaggressive. 27 28 9-03.21(1) General Requirements 29 The first sentence in the first paragraph is revised to read: 30

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 61 1 Hot Mix Asphalt, Concrete Rubble, Recycled Glass (glass cullet), and Steel Furnace 2 Slag may be used as, or blended uniformly with naturally occurring materials for 3 aggregates. 4 5 9-03.21(1)C Vacant 6 This section including title is revised to read: 7 8 9-03.21(1)C Recycled Glass (Glass Cullet) 9 Glass Cullet shall meet the requirements of AASHTO M 318 with the additional 10 requirement that the glass cullet is limited to the maximum amounts set in Section 9- 11 03.21(1)E for recycled glass. Prior to use the Contractor shall provide certification to 12 the Project Engineer that the recycled glass meets the physical properties and 13 deleterious substances requirements in AASHTO M-318. 14 15 9-03.21(1) E Table on Maximum Allowable Percent (By Weight) of Recycled 16 Material 17 In the table, the row containing the item “Aggregate for Asphalt Treated Base (ATB)” is 18 deleted. 19 20 The column heading “Recycled Glass” is revised to read “Recycled Glass (Glass Cullet) in 21 the table. 22 23 In the column “Recycled Glass (Glass Cullet)” all amounts are revised to read “20” beginning 24 with the item “Ballast” and continuing down until the last item in the table. 25 26 Section 9-04, Joint And Crack Sealing Materials 27 January 7, 2013

28 9-04.2 Joint Sealants 29 This section is supplemented with the following new sub-sections: 30 31 9-04.2(3) Polyurethane Sealant 32 Polyurethane sealant shall conform to ASTM C 920 Type S Grade NS Class 25 Use M. 33 34 Polyurethane sealant shall be compatible with the closed cell foam backer rod. When 35 required, compatibility characteristics of sealants in contact with backer rods shall be 36 determined by Test Method ASTM C 1087. 37 38 9-04.2(3)A Closed Cell Foam Backer Rod 39 Closed cell foam backer rod for use with polyurethane sealant shall conform to ASTM C 40 1330 Type C. 41 42 9-04.10 Crack Sealing – Rubberized Asphalt 43 This section is deleted. 44 45 9-04.11 Butyl Rubber and Nitrile Rubber 46 This sections number is revised to read: 47 48 9-04.10 49

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 62 1 Section 9-05, Drainage Structures, Culverts, and Conduits 2 January 7, 2013

3 9-05.0 Acceptance by Manufacturer’s Certification 4 This section including title is revised to read: 5 6 9-05.0 Acceptance and Approval of Drainage Structures, and Culverts 7 The Drainage Structure or Culvert may be selected from the Qualified Products List, or 8 submitted using a Request for Approval of Materials (RAM) in accordance with Section 9 1-06. 10 11 Certain drainage materials may be accepted by the Engineer based on a modified 12 acceptance criteria when materials are selected from the Qualified Products List (QPL). 13 The modified acceptance criteria are defined in the QPL for each material. 14 15 9-05.1(6) Corrugated Polyethylene Drain Pipe, Couplings, and Fittings (Up to 16 10 Inch) 17 This section is supplemented with the following: 18 19 Corrugated polyethylene drain pipe manufacturers shall participate in the National 20 Transportation Product Evaluation Program (NTPEP) work plan for HDPE (High Density 21 Polyethylene) Thermoplastic Pipe and be listed on the NTPEP audit website displaying 22 they are NTPEP compliant. 23 24 9-05.1(7) Corrugated Polyethylene Drain Pipe, Couplings, and Fittings (12 Inch 25 Through 60 Inch) 26 This section is supplemented with the following: 27 28 Corrugated polyethylene drain pipe manufacturers shall participate in the National 29 Transportation Product Evaluation Program (NTPEP) work plan for HDPE (High Density 30 Polyethylene) Thermoplastic Pipe and be listed on the NTPEP audit website displaying 31 they are NTPEP compliant. 32 33 9-05.2(7) Perforated Corrugated Polyethylene Underdrain Pipe (Up to 10 Inch) 34 This section is supplemented with the following: 35 36 Perforated corrugated polyethylene underdrain pipe manufacturers shall participate in 37 the National Transportation Product Evaluation Program (NTPEP) work plan for HDPE 38 (High Density Polyethylene) Thermoplastic Pipe and be listed on the NTPEP audit 39 website displaying they are NTPEP compliant. 40 41 9-05.2(8) Perforated Corrugated Polyethylene Underdrain Pipe (12-Inch 42 Through 60 Inch Diameter Maximum), Couplings, and Fittings 43 This section is supplemented with the following: 44 45 Perforated corrugated polyethylene underdrain pipe manufacturers shall participate in 46 the National Transportation Product Evaluation Program (NTPEP) work plan for HDPE 47 (High Density Polyethylene) Thermoplastic Pipe and be listed on the NTPEP audit 48 website displaying they are NTPEP compliant. 49 50 9-05.19 Corrugated Polyethylene Culvert Pipe, Couplings, and Fittings 51 The word “producer” is revised to read “manufacturer”. 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 63 1 The second paragraph is revised to read: 2 3 Joints for corrugated polyethylene culvert pipe shall be made with either a bell/bell or 4 bell and spigot coupling and shall incorporate the use of a gasket conforming to the 5 requirements of ASTM D 1056 Type 2 Class B Grade 3 or ASTM F 477. All gaskets shall 6 be factory installed on the coupling or on the pipe by the qualified manufacturer. 7 8 This section is supplemented with the following: 9 10 Corrugated polyethylene culvert pipe manufacturers shall participate in the National 11 Transportation Product Evaluation Program (NTPEP) work plan for HDPE (High Density 12 Polyethylene) Thermoplastic Pipe and be listed on the NTPEP audit website displaying 13 they are NTPEP compliant. 14 15 9-05.20 Corrugated Polyethylene Storm Sewer Pipe, Couplings, and Fittings 16 The word “producer” is revised to read “manufacturer”. 17 18 The first paragraph is revised to read: 19 20 Corrugated polyethylene storm sewer pipe, couplings, and fittings shall meet the 21 requirements of AASHTO M 294 Type S or D. The maximum pipe diameter for 22 corrugated polyethylene storm sewer pipe shall be the diameter for which a 23 manufacturer has submitted. Fittings shall be blow molded, rotational molded, or factory 24 welded. 25 26 This section is supplemented with the following: 27 28 Corrugated polyethylene culvert pipe manufacturers shall participate in the National 29 Transportation Product Evaluation Program (NTPEP) work plan for HDPE (High Density 30 Polyethylene) Thermoplastic Pipe and be listed on the NTPEP audit website displaying 31 they are NTPEP compliant. 32 33 9-05.24 Polypropylene Culvert Pipe, Polypropylene Storm Sewer Pipe, and 34 Polypropylene Sanitary Sewer Pipe 35 This sections content is deleted and replaced with the following: 36 37 All joints for polypropylene pipe shall be made with a bell/bell or bell and spigot coupling 38 and shall conform to ASTM D 3212 using elastomeric gaskets conforming to ASTM F 39 477. All gaskets shall be factory installed on the pipe in accordance with the producer’s 40 recommendations. 41 42 Qualification for each producer of polypropylene storm sewer pipe requires joint system 43 conformance to ASTM D 3212 using elastomeric gaskets conforming to ASTM F 477 44 and a formal quality control plan for each plant proposed for consideration. 45 46 A Manufacturer’s Certificate of Compliance shall be required and shall accompany the 47 materials delivered to the project. The certificate shall clearly identify production lots for 48 all materials represented. The Contracting Agency may conduct verification tests of pipe 49 stiffness or other properties it deems appropriate. 50 51 This section is supplemented with the following new sub-sections: 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 64 1 9-05.24(1) Polypropylene Culvert Pipe and Storm Sewer Pipe 2 Polypropylene culvert and storm sewer pipe shall conform to the following requirements: 3 4 1. For dual wall pipe sizes up to 30 inches: ASTM F2736. . 5 6 2. For triple wall pipe sizes from 30 to 60 inches: ASTM F2764. 7 8 3. For dual wall profile pipe sizes 36 to 60 inches: AASHTO MP 21, Type S or 9 Type D. 10 11 4. Fittings shall be factory welded, injection molded or PVC. 12 13 9-05.24(2) Polypropylene Sanitary Sewer Pipe 14 Polypropylene sanitary sewer pipe shall conform to the following requirements: 15 16 1. For pipe sizes up to 30 inches: ASTM F2736. 17 18 2. For pipe sizes from 30 to 60 inches: ASTM F2764. 19 20 3. Fittings shall be factory welded, injection molded or PVC. 21 22 Section 9-06, Structural Steel and Related Materials 23 April 1, 2013

24 9-06.5(3) High Strength Bolts 25 In this section, “AASHTO M 291” is revised to read “ASTM A 563”, “AASHTO M 164” is 26 revised to read “ASTM A 325”, “AASHTO M 293” is revised to read “ASTM F 436”, “AASHTO 27 M 253” is revised to read “ASTM A 490”, and “AASHTO M 298” is revised to read “ASTM B 28 695”. 29 30 9-06.5(4) Anchor Bolts 31 In this section, “AASHTO M 291” is revised to read “ASTM A 563”. 32 33 34 Section 9-07, Reinforcing Steel 35 August 6, 2012

36 9-07.7 Wire Mesh 37 The first sentence in the first paragraph is revised to read: 38 39 Wire mesh for concrete reinforcement shall conform to the requirements of AASHTO M 40 55, Welded Steel Wire Fabric for Concrete Reinforcement or AASHTO M 221, Steel 41 Welded Wire Reinforcement, Deformed for Concrete. 42 43 Section 9-10, Piling 44 April 2, 2012

45 9-10.4 Steel Pile Tips and Shoes 46 In the first paragraph “ASTM A 148 Grade 60-90” is revised to read “ASTM A 148 Grade 90- 47 60”. 48

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 65 1 Section 9-13, Riprap, Quarry Spalls, Slope Protection, & Rock for Erosion and 2 Scour Protection and Rock Walls 3 April 1, 2013

4 9-13.5(1) Semi-Open Concrete Masonry Units Slope Protection 5 In this section, “ASTM C 90” is revised to read “ASTM C 1319”. 6 7 Section 9-14, Erosion Control and Roadside Planting 8 August 5, 2013

9 9-14.3 Fertilizer 10 The second sentence in the first paragraph is revised to read: 11 12 It may be separate or in a mixture containing the percentage of total nitrogen, available 13 phosphoric acid, and water-soluble potash or sulfur in the amounts specified. 14 15 9-14.4(2) Hydraulically Applied Erosion Control Products (HECPs ) 16 The first sentence in the third paragraph is revised to read: 17 18 All HECPs shall be furnished premixed by the manufacturer with Organic or Synthetic 19 Tackifier as specified in Section 9-14.4(7). 20 21 The third and fourth rows in Table 1 is revised to read: 22 Heavy Metals EPA 6020A Total Metals Antimony – < 4 mg/kg Arsenic – < 6 mg/kg Barium – < 80 mg/kg Boron – < 160 mg/kg Cadmium – < 2 mg/kg Total Chromium – < 4 mg/kg Copper – < 10 mg/kg Lead – < 5 mg/kg Mercury – < 2 mg/kg Nickel – < 2 mg/kg Selenium – < 10 mg/kg Strontium – < 40 mg/kg Zinc – < 30 mg/kg Water Holding ASTM D 7367 800 percent minimum Capacity 23 24 9-14.4(2)A Long Term Mulch 25 In the first paragraph, the phrase “within 2 hours of application” is deleted. 26 27 9-14.4(4) Wood Strand Mulch 28 The last sentence in the second paragraph is deleted. 29 30 This section is supplemented with the following new paragraph: 31 32 The Contractor shall provide Material Safety Data Sheet (MSDS) that demonstrates that 33 the product is not harmful to plant life and a test report performed in accordance with 34 WSDOT Test Method 125 demonstrating compliance to this specification prior to 35 acceptance. 36

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 66 1 9-14.4(8) Compost 2 The second paragraph is revised to read: 3 4 Compost production and quality shall comply with WAC 173-350 and for biosolids 5 composts, WAC 173-308. 6 7 The third paragraph is to read: 8 9 Compost products shall meet the following physical criteria: 10 11 1. Compost material shall be tested in accordance with U.S. Composting Council 12 Testing Methods for the Examination of Compost and Composting (TMECC) 13 02.02-B, “Sample Sieving for Aggregate Size Classification”. 14 15 Fine compost shall meet the following gradation: 16 Sieve Size Percent Passing Minimum Maximum 1” 100 5 /8” 90 100 ¼” 75 100 17 18 Note Maximum particle length of 4 inches. 19 20 Medium compost shall meet the following gradation: 21 Sieve Size Percent Passing Minimum Maximum 1” 100 5 /8” 85 100 ¼” 70 85 22 23 Note Maximum particle length of 4 inches. Medium compost shall have a 24 carbon to nitrogen ration (C:N) between 18:1 and 35:1. The carbon to 25 nitrogen ration shall be calculated using dry weight of “Organic Carbon” 26 using TMECC 04.01A divided by the dry weight of “Total N” using TMECC 27 04.02D. 28 29 Coarse compost shall meet the following gradation: 30 Sieve Size Percent Passing Minimum Maximum 2” 100 1” 90 100 ¾” 70 100 ¼” 40 60 31 32 Note Maximum particle length of 6 inches. Coarse compost shall have a carbon 33 to nitrogen ratio (C:N) between 25:1 and 35:1. The carbon to nitrogen ratio 34 shall be calculated using the dry weight of “Organic Carbon” using 35 TMECC 04.01A divided by the dry weight of “Total N” using TMECC 36 04.02D. 37

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 67 1 2. The pH shall be between 6.0 and 8.5 when tested in accordance with U.S. 2 Composting Council TMECC 04.11-A, “1:5 Slurry pH”. 3 4 3. Physical contaminants, defined in WAC 173-350 (plastic, concrete, ceramics, 5 metal, etc.) shall be less than 0.5 percent by weight as determined by U.S. 6 Composting Council TMECC 03.08-A “Classification of Inerts by Sieve Size”. 7 8 4. Minimum organic matter shall be 40 percent by dry weight basis as determined 9 by U.S. Composting Council TMECC 05.07A “Loss-On-Ignition Organic Matter 10 Method (LOI)”. 11 12 5. Soluble salt contents shall be less than 4.0 mmhos/cm when tested in 13 accordance with U.S. Composting Council TMECC 04.10 “Electrical 14 Conductivity.” 15 16 6. Maturity shall be greater than 80 percent in accordance with U.S. Composting 17 Council TMECC 05.05-A, “Germination and Root Elongation”. 18 19 7. Stability shall be 7-mg CO2–C/g OM/day or below in accordance with U.S. 20 Composting Council TMECC 05.08-B “Carbon Dioxide Evolution Rate”. 21 22 8. The compost product shall originate from organic feedstocks as defined in 23 WAC 173 350 as “Wood waste”, “Yard debris”, “Post-consumer food waste”, 24 “Pre-consumer animal-based wastes”, and/or “Pre-consumer vegetative 25 waste”. The Contractor shall provide a list of feedstock sources by percentage 26 in the final compost product. 27 28 9. The Engineer may also evaluate compost for maturity using U.S. Composting 29 Council TMECC 05.08-E “Solvita® Maturity Index”. Fine compost shall score a 30 number 6 or above on the Solvita® Compost Maturity Test. Medium and 31 Coarse compost shall score a 5 or above on the Solvita® Compost Maturity 32 Test. 33 34 9-14.4(8)A Compost Approval 35 This section’s title is revised to read: 36 37 9-14.4(8)A Compost Submittal Requirements 38 39 The first sentence in this section up until the colon is revised to read: 40 41 The Contractor shall submit the following information to the Engineer for approval: 42 43 Item No. 2 in the first paragraph is revised to read: 44 45 2. A copy of the Solid Waste Handling Permit issued to the manufacturer by the 46 Jurisdictional Health Department in accordance with WAC 173-350 (Minimum 47 Functional Standards for Solid Waste Handling) or for biosolid composts a copy of 48 the Coverage Under the General Permit for Biosolids Management issued to the 49 manufacturer by the Department of Ecology in accordance with WAC 173-308 50 (Biosolids Management). 51 52 9-14.5 Erosion Control Devices 53 This section is supplemented with the following new sub-section:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 68 1 2 9-14.5(9) High Visibility Silt Fence 3 High visibility silt fence shall be a minimum of 5 feet in height, high visibility orange, UV 4 stabilized and shall meet the geotextile requirements in Section 9-33 Table 6. Support 5 posts shall be in accordance with the Standard Plans. The posts shall have sufficient 6 strength and durability to support the fence through the life of the project. 7 8 9-14.5(1) Polyacrylamide (PAM) 9 The fourth sentence is replaced with the following two new sentences: 10 11 The minimum average molecular weight shall be greater than 5-mg/mole. The charge 12 density shall be no less than 15 percent and no greater than 30 percent. 13 14 9-14.5(2) Erosion Control Blanket 15 This section including title is deleted in its entirety and replaced with the following: 16 17 9-14.5(2) Biodegradable Erosion Control Blanket 18 Biodegradable erosion control blankets shall be made of natural plant fibers, and all 19 netting material, if present, shall biodegrade within a life span not to exceed 2 years. 20 21 The Contractor shall provide independent test results from the National Transportation 22 Product Evaluation Program (NTPEP) meeting the requirements of Section 9-14.5(2)B, 23 9-14.5(2)C and 9-14.5(2)D. 24 25 9-14.5(2)A Approval and Acceptance of Biodegradable Erosion Control 26 Blankets 27 The erosion control blanket may be selected from the Qualified Products List, or 28 submitted using a Request for Approval of Materials (RAM) in accordance with 29 Section 1-06. Erosion control blankets may be accepted by the Engineer based on 30 the modified acceptance criteria when materials are selected from the QPL. The 31 modified acceptance criteria are defined in the QPL for each material. 32 33 9-14.5(2)B Biodegradable Erosion Control Blanket for Slopes Steeper than 34 3:1 (H:V) 35 36 Table 6 37 Properties ASTM Test Method Requirements for Slopes Steeper than 3:1 Protecting ASTM D 6459 C factor = 0.04 maximum for Slopes from cumulative R-Factor<231 Rainfall-Induced Soil tested shall be sandy Erosion loam as defined by the NRCS** Soil Texture Triangle Mass Per Unit ASTM D 6475 7.6 oz./sq. yd. minimum Area Light ASTM D 6567 44 % maximum Penetration

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 69 Tensile Strength ASTM D 6818 10.0 x 6.0 pounds/inch minimum MD x XD* Tensile ASTM D 6818 38% x 33% maximum Elongation MD x XD* *MD is Machine Design and XD is Cross Direction **Natural Resource Conservation Services

1 2 3 9-14.5(2)C Biodegradable Erosion Control Blanket for Slopes Flatter than 4 3:1(H:V) 5 6 Table 7 7 Properties ASTM Test Method Slope Flatter than 3:1 Requirements Protecting ASTM D 6459 C factor = 0.15 maximum for Slopes from cumulative R-Factor<231 Rainfall-Induced Soil tested shall be sandy Erosion loam as defined by the NRCS** Soil Texture Triangle Mass Per Unit ASTM D 6475 7.6 oz./sq. yd. minimum Area Light ASTM D 6567 40% maximum Penetration Tensile Strength ASTM D 6818 6.5 x 2.3 pounds/inch minimum MD x XD* Tensile ASTM D 6818 38% x 33% maximum Elongation MD x XD* *MD is Machine Design and XD is Cross Direction **Natural Resource Conservation Services

8 9 10 9-14.5(2)D Biodegradable Erosion Control Blanket for Ditches 11 12 Table 8 13 Properties Test Method Requirements

Performance in ASTM D 6460 Limiting Shear (TLimit) = 2.0 psf Protecting Soil tested shall be sandy minimum. Earthen loam as defined by the

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 70 Channels from NRCS** Limiting Velocity (VLimit) = 7.5 Stormwater- Soil Texture Triangle ft/sec flow minimum. Induced Erosion Mass per Unit ASTM D 6475 7.4 oz./ sq. yd. minimum Area Light ASTM D 6567 65 % maximum Penetration Tensile Strength ASTM D 6818 9.6 x 3.2 lbs/inch minimum MD x XD* Tensile ASTM D 6818 38% x 33% maximum Elongation MD x XD* *MD is Machine Design and XD is Cross Direction **Natural Resource Conservation Services

1 2 3 9-14.5(3) Clear Plastic Covering 4 This section including title is revised to read: 5 6 Plastic Covering 7 Plastic covering shall meet the requirements of ASTM D 4397 for polyethylene sheeting. 8 9 9-14.5(4) Geotextile Encased Check Dam 10 This section including title is revised to read: 11 12 9-14.5(4) Check Dams 13 All materials used for check dams shall be non-toxic and not pose a threat to wildlife 14 when installed. 15 16 This section is supplemented with the following new sub-sections: 17 18 9-14.5(4)A Biodegradable Check Dams 19 Biodegradable check dams shall meet the following requirements: 20 21 Biodegradable Check Dams Materials 22 Wattle Check Dam 9-14.5(5) 23 Compost Sock Check Dam 9-14.5(6) 24 Coir Log Check Dam 9-14.5(7) 25 26 The Contractor may substitute a different biodegradable check dam as long as it 27 complies with the following and is approved by the Engineer: 28 29 1. Made of natural plant fiber. 30 31 2. Netting if present shall be biodegradable. 32 33 3. Straw bales shall not be used as check dams. 34

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 71 1 9-14.5(4)B Non-biodegradable Check Dams 2 Non-biodegradable check dams shall meet the following requirements: 3 4 1. Geotextile materials shall conform to section 9-33 for silt fence. 5 6 2. Other such devices that fulfill the requirements of section 9-14.5(4) and shall 7 be approved by the Engineer prior to installation. 8 9 9-14.5(5) Wattles 10 The second sentence in the first paragraph is revised to read: 11 12 Wattle shall be a minimum of 8-inches in diameter. 13 14 The first sentence in the second paragraph is revised to read: 15 16 Compost filler shall be Medium Compost and shall meet the material requirements as 17 specified in Section 9-14.4(8). 18 19 The last paragraph is revised to read: 20 21 Wood stakes for wattles shall be made from untreated Douglas fir, hemlock, or pine 22 species. Wood stakes shall be 2 by 2-inch nominal dimension and a minimum 24 inches 23 in length. 24 25 9-14.5(6) Compost Socks 26 In this section, “Coarse Compost” is revised to read “Medium Compost”. 27 28 The last paragraph is revised to read: 29 30 Wood stakes for compost socks shall be made from untreated Douglas fir, hemlock, or 31 pine species. Wood stakes shall be 2 by 2-inch nominal dimension and a minimum 24 32 inches in length. 33 34 9-14.5(8) High Visibility Fencing 35 The first paragraph is revised to read: 36 37 High visibility fence shall be UV stabilized, orange, high-density polyethylene or 38 polypropylene mesh. 39 40 9-14.6(1) Description 41 In item No. C in the fourth paragraph, “22-inch” is revised to read “2-inch”. 42 43 Section 9-15, Irrigation System 44 April 1, 2013

45 9-15.1(2) Polyvinyl Chloride Pipe and Fittings 46 In the first paragraph, “ASTM D 1784” is revised to read “ASTM D 1785”. 47 48 Section 9-16, Fence and Guardrail 49 August 5, 2013

50 9-16.1(1)A Post Material for Chain Link Fence 51 The first paragraph is revised to read:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 72 1 2 Except as noted otherwise, post material shall conform to the requirements of AASHTO 3 M 181, Type 1 (zinc-coated steel), Grade 1 or 2, and shall include all round and roll- 4 formed material (line posts, brace posts, end posts, corner posts, and pull posts). 5 6 The last sentence in the fourth paragraph is deleted. 7 8 9-16.1(1)C Tension Wire and Tension Cable 9 This section including title is revised to read: 10 11 9-16.1(1)C Tension Wire 12 Tension wire shall meet the requirements of AASHTO M 181. Tension wire galvanizing 13 shall be Class 1. 14 15 9-16.1(1)D Fittings and Hardware 16 The second sentence in the first paragraph is deleted. 17 18 The last paragraph is deleted. 19 20 9-16.1(2) Approval 21 This section is deleted. 22 23 9-16.2(2) Approval 24 This section is deleted. 25 26 9-16.3(2) Posts and Blocks 27 The first sentence in the first paragraph is revised to read: 28 29 Posts and blocks may be of creosote, pentachlorophenol, waterborne chromate copper 30 arsenate (CCA), or ammoniacal copper zinc arsenate (ACZA), treated timber, or 31 galvanized steel (galvanized steel posts only – no blocks). 32 33 The following reference is deleted from the third paragraph: 34 35 ACA 0.50 lbs. pcf 36 37 The sixth paragraph is deleted. 38 39 9-16.4(2) Wire Mesh 40 This section is revised to read: 41 42 The galvanized wire mesh shall be a Style 1 double-twisted hexagonal mesh 43 conforming to ASTM A 975 with 8 by 10 opening, except when a colorized, polyvinyl 44 chloride coating is required then the Style shall be a Style 3. 45 46 The longitudinal edges of the wire mesh fabric shall have knuckled selvedges with 47 continuous selvedge wire as specified in ASTM A 975. 48 49 9-16.4(3) Wire Rope 50 This section is revised to read: 51 52 Wire rope shall be ¾- inch-diameter, independent wire rope class (IWRC) 6x19, extra 53 improved plow steel (EIP) wire rope galvanized in accordance with ASTM A1023. Each

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 73 1 lot of wire rope shall be accompanied by a Manufacturer’s Certificate of Compliance, a 2 mill certificate, and a test report showing the wire rope meets the minimum breaking 3 force requirements of ASTM A 1023. 4 5 9-16.4(4) Hardware 6 This section is revised to read: 7 8 Weldless steel rings shall be drop-forged steel and heat treated after forging; have a 9 single pull, working load limit of at least 10,000 lbs; and meet performance requirements 10 of Federal Specification RR-C-271D Type VI. 11 12 Thimbles required for all wire rope loops shall be standard weight, galvanized, and meet 13 performance requirements of Federal Specification FF-T-276b Type II. 14 15 Wire rope clips shall have drop-forged steel bases, be galvanized, and meet 16 performance requirements of Federal Specification FF-C-450 Type I Class 1. 17 18 9-16.4(5) Hog Rings and Tie Wire 19 This section including title is revised to read: 20 21 9-16.4(5) Fasteners and Lacing Wire 22 Fasteners shall consist of 11 gauge high tensile steel. Lacing wire shall consist of 9 23 gauge, zinc-coated steel wire conforming to ASTM A 641. 24 25 9-16.4(6) Grout 26 This section including title is deleted. 27 28 9-16.4(7) Anchor 29 This section including title and section number is revised to read: 30 31 9-16.4(6) Ground Anchors 32 Threaded bar ground anchors shall be deformed, continuously threaded, steel 33 reinforcement bars conforming to either Section 9-07.2 or Section 9-07.11. Threaded 34 bar ground anchors shall be either epoxy-coated in accordance with Sections 6- 35 02.3(24)H and 9-07.3 or galvanized after fabrication in accordance with ASTM A 767 36 Class I. 37 38 Hollow-core anchor bars shall have continuous threads/deformations and be fabricated 39 from steel tubing conforming to ASTM A 519. Couplers and nuts shall provide 100% of 40 the guaranteed minimum tensile strength of the hollow core anchor bars. 41 42 Bearing plates shall conform to ASTM A 572 Grade 50 and shall be galvanized after 43 fabrication in accordance with AASHTO M 111. Nuts shall conform to either AASHTO M 44 291 Grade B, hexagonal, or Section 9-07.11. Nuts shall be galvanized after fabrication 45 in accordance with AASHTO M 111 for plate washers and AASHTO M 232 for all other 46 hardware. 47 48 Grout for ground anchors shall be Grout Type 2 for Nonshrink Applications, conforming 49 to Section 9-20.3(2). 50 51 Concrete for soil anchor deadmen shall be either commercial concrete conforming to 52 Section 6-02.3(2)B or Class 3000 conforming to Section 6-02. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 74 1 Steel reinforcing bars for soil anchor deadmen shall conform to Section 9-07.2, and 2 shall be epoxy-coated in accordance with Sections 6-02.3(24)H and 9-07.3. 3 4 9-16.6(3) Posts 5 This section is revised to read: 6 7 Line posts for Types 1 and 2 glare screens shall be 2 inch inside diameter galvanized 8 steel pipe with a nominal weight of 3.65 pounds per linear foot. End, corner, brace, and 9 pull posts for Type 1 Design A and B and Type 2 shall be 2 ½ inch inside diameter 10 galvanized steel pipe with a nominal weight of 5.79 pounds per linear foot. Intermediate 11 pull posts (braced line posts) shall be as specified for line posts. 12 13 The base material for the manufacture of steel pipes used for posts shall conform to the 14 requirements of ASTM A 53, except the weight tolerance on tubular posts shall be 15 applied as provided below. 16 17 Posts provided for glare screen will have an acceptance tolerance on the weight per 18 linear foot, as specified, equal to plus or minus 5 percent. This tolerance will apply to 19 each individual post. 20 21 All posts shall be galvanized in accordance with AASHTO M 181 Section 32. The 22 minimum average zinc coating is per square foot of surface area. This area is defined 23 as the total area inside and outside. A sample for computing the average of mass of 24 coating is defined as a 12-inch piece cut from each end of the galvanized member. 25 26 9-16.6(5) Cable 27 This section including title is revised to read: 28 29 9-16.6(5) Vacant 30 31 9-16.6(6) Cable and Tension Wire Attachments 32 This section including title is revised to read: 33 34 9-16.6(6) Tension Wire Attachments 35 All tension wire attachments shall be galvanized steel conforming to the requirements of 36 AASHTO M 232 unless otherwise specified. Eye bolts shall have either a shoulder or a 37 back-up nut on the eye end and be provided with an eye nut where needed or standard 38 hex nut and lock washer ⅜-inch diameter for tension wire and of sufficient length to 39 fasten to the type of posts used. Turnbuckles shall be of the shackle end type, ½ inch 40 diameter, with standard take-up of 6 inches and provided with ⅜ inch diameter pins. 41 42 9-16.6(9) Fabric Bands and Stretcher Bars 43 The first paragraph is revised to read: 44 3 45 Fabric bands shall be ⅛ inch by 1inch nominal. Stretcher bars shall be ⁄16 inch by ¾ 5 5 46 inch nominal or /16 inch diameter round bar nominal. A /16 inch diameter round 47 stretcher bar shall be used with Type 1. Nominal shall be construed to be the area of the 48 cross section of the shape obtained by multiplying the specified width by thickness. A 49 variation of minus 5-percent from this theoretical area shall be construed as “nominal” 50 size. All shall be galvanized to meet the requirements of ASTM F 626. 51 52 9-16.7 Vacant 53 This section including title is deleted in its entirety.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 75 1 2 9-16.8 Weathering Steel Beam Guardrail 3 This section including title is deleted in its entirety. 4 5 Section 9-18, Precast Traffic Curb and Block Traffic Curb 6 August 6, 2012

7 This section’s title is revised to read: 8 9 9-18 Precast Traffic Curb 10 11 9-18.3 Block Traffic Curb 12 This section including title is revised to read: 13 14 9-18.3 Vacant 15 16 Section 9-20, Concrete Patching Material, Grout, and Mortar 17 January 2, 2012

18 9-20.3(3) Grout Type 3 for Unconfined Bearing Pad Applications 19 This section is revised to read: 20 21 Grout Type 3 shall be a prepackaged material meeting the requirements of ASTM C 928 22 – Table 1, R2 Concrete or Mortar. 23 24 9-20.3(4) Grout Type 4 for Multipurpose Applications 25 In the third sentence of the first paragraph, the reference “0.40” is revised to read “0.45”. 26 27 Section 9-23, Concrete Curing Materials and Admixtures 28 August 5, 2013

29 9-23.2 Liquid Membrane-Forming Concrete Curing Compounds 30 In the first paragraph, “moisture loss” is revised to read “water retention”. 31 32 9-23.6(9) Type S Specific Performance Admixtures 33 The first sentence is revised to read the following two new sentences: 34 35 Type S Specific Performance admixtures are limited to ASR-mitigating, viscosity 36 modifying, shrinkage reducing, rheology-controlling, and workability-retaining 37 admixtures. They shall conform to the requirements of ASTM C 494 Type S. 38 39 Section 9-26, Epoxy Resins 40 August 5, 2013

41 9-26.3(1)A Traffic Bearing Applications 42 The first sentence in the first paragraph is revised to read: 43 44 Epoxy grout/mortar/concrete for traffic bearing applications shall have a 7-day 45 compressive strength of not less than 4,000 psi when tested in accordance with ASTM 46 C 579. 47

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 76 1 Section 9-28, Signing Materials and Fabrication 2 April 1, 2013

3 9-28.14(2) Steel Structures and Posts 4 “AASHTO M 291” is revised to read “ASTM A 563” and “AASHTO M 293” is revised to read 5 “ASTM F 436”. 6 7 Section 9-29, Illumination, Signal, Electrical 8 August 5, 2013

9 9-29.1(4) Non-Metallic Conduit 10 This section is supplemented with the following new sub-section: 11 12 9-29.1(4)D Deflection Fittings 13 Deflection Fittings for use with rigid PVC conduit shall be as described in 9-29.1(2)A 14 15 9-29.2 Junction Boxes, Cable Vaults, and Pull Boxes 16 The section is supplemented with the following: 17 18 The Contractor shall perform quality control inspection. The Contracting Agency intends 19 to perform Quality Assurance Inspection. By its inspection, the Contracting Agency 20 intends only to verify the quality of that Work. This inspection shall not relieve the 21 Contractor of any responsibility for identifying and replacing defective material and 22 workmanship. Prior to the start of production of the precast concrete units, the 23 Contractor shall advise the Engineer of the production schedule. The Contractor shall 24 give the Inspector safe and free access to the Work. If the Inspector observes any 25 nonspecification Work or unacceptable quality control practices, the Inspector will 26 advise the plant manager. If the corrective action is not acceptable to the Engineer, the 27 unit(s) will be rejected. 28 29 9-29.2(1) Standard Duty and Heavy-Duty Junction Boxes 30 The third paragraph is deleted and replaced with the following new paragraphs: 31 32 The Contractor shall provide shop drawings for all components, hardware, lid, 33 frame, reinforcement, and box dimensions. The shop drawings shall be 34 prepared by (or under the supervision of) a Professional Engineer, licensed 35 under Title 18 RCW, State of Washington, in the branch of Civil or Structural, 36 and each sheet shall include the following: 37 1. Professional Engineer’s original signature, date of signature, original seal, 38 registration number, and date of expiration. 39 40 2. The initials and dates of all participating design professionals 41 42 3. Clear notation of all revisions including identification of who authorized the 43 revision, who made the revision, and the date of the revision. 44 45 4. Design calculations shall carry on the cover page, the Professional Engineer’s 46 original signature, date of signature, original seal, registration number, and 47 date of expiration. 48 49 For each type of junction box, or whenever there is a change to the junction box design, 50 a proof test, as defined in this Specification, shall be performed and new shop drawings 51 submitted.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 77 1 2 9-29.2(1)A Standard Duty Junction Boxes 3 The first paragraph is supplemented with the following: 4 5 All Standard Duty Junction Boxes placed in sidewalks, walkways, and shared use paths 6 shall have slip resistant surfaces. Non-slip lids and frames shall be hot dip galvanized 7 in accordance with AASHTO M 111. 8 9 The sub-paragraph’s titled “Concrete Junction Boxes” are revised to read: 10 11 Concrete Junction Boxes 12 The Standard Duty Concrete Junction Box steel frame, lid support, and lid shall be 13 painted with a black paint containing rust inhibiters or painted with a shop applied, 14 inorganic zinc primer in accordance with Section 6-07.3, or hot-dip galvanized in 15 accordance with AASHTO M 111. 16 17 Concrete used in Standard Duty Junction Boxes shall have a minimum compressive 18 strength of 6,000 psi when reinforced with a welded wire hoop, or 4,000 psi when 19 reinforced with welded wire fabric or fiber reinforcement. The frame shall be anchored to 20 the box by welding headed studs ⅜ by 3 inches long, as specified in Section 9-06.15, to 21 the frame. The wire fabric shall be attached to the studs and frame with standard tie 22 practices. The box shall contain ten studs located near the centerline of the frame and 23 box wall. The studs shall be placed one anchor in each corner, one at the middle of 24 each width and two equally spaced on each length of the box. 25 26 Materials for Type 1, 2, and 8 Concrete Junction Boxes shall conform to the following: 27 Materials Requirement Concrete Section 6-02 Reinforcing Steel Section 9-07 Fiber Reinforcing ASTM C 1116, Type III Lid ASTM A 786 diamond plate steel Slip Resistant Lid ASTM A 36 steel ASTM A 786 diamond plate steel or ASTM Frame A36 steel Slip Resistant Frame ASTM A 36 steel Lid Support ASTM A 36, or ASTM A1011 Grade SS ASTM A 36 steel or ASTM A1011 Grade Handle & Handle support CS or SS Anchors (studs) Section 9-06.15 ASTM F 593 or A 193, Type 304 or 316, or Bolts, Studs, Nuts, Stainless Steel grade 302, 304, or 316 Washers steel in accordance with approved shop drawing Locking and Latching In accordance with approved shop Mechanism Hardware drawings and Bolts 28 29 30 9-29.2(1)B Heavy Duty Junction Boxes 31 The section is revised to read:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 78

31

30 The second paragraph is revised to read:

29

28 testing facility, and a test report issued documenting the results of the tests performed.

27 Junction boxes, cable vaults and pull boxes shall be tested by an independent materials

26 The Contractor shall provide for testing of junction boxes, cable vaults and pull boxes.

25

24 The first paragraph is revised to read:

9-29.2(1)C Testing Requirements 23

22

21 it bears on the frame.

20 a feeler gage. The bearing area percentage will be measured for each side of the lid as

19 of the bearing areas to be seated with a tolerance of 0.0 to 0.005 inches measured with

18 bearing seat and lid perimeter bar shall be machined to allow a minimum of 75 percent

17 be liberally coated with anti-seize compound. Bolts shall be installed snug tight. The

16 burrs, dirt, and other foreign debris that would prevent solid seating. Bolts and nuts shall

15 fabrication of the frame and lid. The bearing seat and lid perimeter bar shall be free from

14 contact, around the perimeter, between the bearing seat and lid stiffener plates, after

13 The lid stiffener plates shall bear on the frame, and be milled so that there is full even

12

11

Hardware and Bolts

drawings

Latching Mechanism

In accordance with approved shop

Hinges and Locking and

accordance with approved shop drawing

Washers

Stainless steel grade 302, 304, or 316 in 1

Bolts, Studs, Nuts,

ASTM F 593 or A 193, Type 304 or 316, or

Anchors (studs) Section 9-06.15

CS or SS

Handle

ASTM A 36 steel or ASTM A 1011 Grade

degrees F

plates

with min. CVN toughness of 20 ft-lb at 40

Frame and stiffener

ASTM A 572 grade 50 or ASTM A 588, both

degrees F. 2 Heavy-Duty Junction Boxes shall be concrete and have a minimum vertical load rating

min. CVN toughness of 20 ft-lb at 40

Lid grade 50 or ASTM A 588, and having a

from plate complying with ASTM A 572,

ASTM A 786 diamond plate steel, rolled

Reinforcing Steel Section 9-07

Concrete Section 6-02

Requirement

Materials 3 of 46,000 pounds without permanent deformation and 60,000 pounds without failure 10

Mat 9 erials for Type 4, 5, and 6 Concrete Junction Boxes shall conform to the following:

8

7 -07.3. shop applied, inorganic zinc primer in accordance with Section 6 4 when tested in accordance with Section 9-29.2(1)C.

5 6 The Heavy-Duty Junction Box steel frame, lid support and lid shall be painted with a

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 79 1 For concrete junction boxes, vaults and pull boxes, the independent testing laboratory 2 shall meet the requirements of AASHTO R 18 for Qualified Tester and Verified Test 3 Equipment. The test shall be conducted in the presence of a Professional Engineer, 4 licensed under Title 18 RCW, State of Washington, in the branch of Civil or Structural, 5 and each test sheet shall have the Professional Engineer’s original signature, date of 6 signature, original seal, registration number, and date of expiration. One copy of the test 7 report shall be furnished to the Contracting Agency certifying that the box and cover 8 meet or exceed the loading requirements for a concrete junction box, and shall include 9 the following information: 10 11 1. Product identification. 12 13 2. Date of testing. 14 15 3. Description of testing apparatus and procedure. 16 17 4. All load deflection and failure data. 18 19 5. Weight of box and cover tested. 20 21 6. Upon completion of the required test(s) the box shall be loaded to failure. 22 23 7. A brief description of type and location of failure. 24 25 The third paragraph is revised to read: 26 27 For non-concrete junction boxes the independent testing laboratory shall meet the 28 requirements of AASHTO R 18 for Qualified Tester and Verified Test Equipment. The 29 test shall be conducted in the presence of a Professional Engineer, licensed under Title 30 18 RCW, State of Washington, in the branch of Civil or Structural, and each test sheet 31 shall have the Professional Engineer’s original signature, date of signature, original 32 seal, registration number, and date of expiration. One copy of the test report shall be 33 furnished to the Contracting Agency certifying that the box and cover meet or exceed 34 the loading requirements for a non-concrete junction box, and shall include the following 35 information: 36 37 1. Product identification. 38 39 2. Date of testing. 40 41 3. Description of testing apparatus and procedure. 42 43 4. All load deflection data. 44 45 5. Weight of box and cover tested. 46 47 The first paragraph following the title “Testing for the Standard Duty Non-Concrete 48 Junction Boxes” is revised to read: 49 50 Non-concrete Junction Boxes shall be tested as defined in the ANSI/SCTE 77-2007 Tier 51 15 test method with test load minimum of 22,500 lbs. In addition, the Contractor shall 52 provide a Manufacture Certificate of Compliance for each non-concrete junction box 53 installed. 54

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 80 1 9-29.2(2) Standard Duty and Heavy-Duty Cable Vaults and Pull Boxes 2 This section is revised to read: 3 4 Standard Duty and Heavy-Duty Cable Vaults and Pull Boxes shall be constructed as a 5 concrete box and as a concrete lid. The lid for the Heavy-Duty and Standard Duty Cable 6 Vaults and Pull Boxes shall be interchangeable and both shall fit the same box as 7 shown in the Standard Plans. 8 9 The Contractor shall provide shop drawings for all components, including concrete box, 10 Cast Iron Ring, Ductile Iron Lid, Steel Rings, and Lid. In addition, the shop drawings 11 shall show placement of reinforcing steel, knock outs, and any other appurtenances. 12 The shop drawing shall be prepared by or under the direct supervision of a Professional 13 Engineer, licensed under Title 18 RCW, State of Washington, in the branch of Civil or 14 Structural, and each sheet shall carry the following: 15 16 1. Professional Engineer’s original signature, date of signature, original seal, 17 registration number, and date of expiration. 18 19 2. The initials and dates of all participating design professionals 20 21 3. Clear notation of all revisions including identification of who authorized the 22 revision, who made the revision, and the date of the revision. 23 24 4. Design calculations shall carry on the cover page, the Professional Engineer’s 25 original signature, date of signature, original seal, registration number, and 26 date of expiration. 27 28 For each type of box or whenever there is a change to the Cable Vault or Pull box 29 design, a proof test, as defined in this Specification, shall be performed and new shop 30 drawings submitted. 31 32 9-29.2(2)A Standard Duty Cable Vaults and Pull Boxes 33 This section is revised to read: 34 35 Standard Duty Cable Vaults and Pull boxes shall be concrete and have a minimum load 36 rating of 22,500 pounds and be tested in accordance with Section 9-29.2(1)C for 37 concrete Standard Duty Junction Boxes. 38 39 Concrete for standard duty cable vaults and pull boxes shall have a minimum 40 compressive strength of 4,000 psi. The lid frame shall be anchored to the vault/box 41 concrete lid by welding headed studs ⅜ by 3 inches long, as specified in Section 9- 42 06.15, to the frame. The wire fabric shall be attached to the studs and frame with 43 standard tie practices. The vault/box concrete lid shall contain ten studs located near 44 the centerline of the frame and wall. Studs shall be placed one anchor in each corner, 45 one at the middle of each width and two equally spaced on each length of the vault/box. 46 The steel frame, lid support, and lid shall be painted with a black paint containing rust 47 inhibiters or painted with a shop applied, inorganic zinc primer in accordance with 48 Section 6-07.3 or hot-dip galvanized in accordance with ASTM M 111. 49 50 All Standard Duty Cable Vaults and Pull Boxes placed in sidewalks, walkways, and 51 shared-use paths shall have slip-resistant surfaces. The steel frame, lid support, and lid 52 for the Standard Duty Cable Vaults and Pull Boxes shall be hot-dip galvanized. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 81 1 Materials for Standard Duty Cable Vaults and Pull Boxes shall conform to the following: 2 Materials Requirements Concrete Section 6-02 Reinforcing Steel Section 9-07 Lid ASTM A 786 diamond plate steel Slip Resistant Lid ASTM A 36 Steel ASTM A 786 diamond plate steel or ASTM Frame A 36 Slip Resistant Frame ASTM A 36 Steel ASTM A 36 Steel, or ASTM A 1011 Grade Lid Support SS Handle & Handle ASTM A 36 steel or ASTM A 1011 Grade Support CS or SS Anchors (studs) Section 9-06.15 ASTM F593 or A 193, type 304 or 316, or Bolts, Studs, Nuts, Stainless steel grade 302, 304, 316 per Washers approved shop drawing Hinges and Locking In accordance with approved shop Mechanism Hardware drawings and Bolts 3 4 5 9-29.2(2)B Heavy-Duty Cable Vaults and Pull Boxes 6 This section is revised to read: 7 8 Heavy-Duty Cable Vaults and Pull Boxes shall be constructed of concrete having a 9 minimum compressive strength of 4,000 psi, and have a minimum vertical load rating of 10 46,000 pounds without permanent deformation and 60,000 pounds without failure when 11 tested in accordance with Section 9-29.2(1)C for Heavy-Duty Junction Boxes. 12 13 Materials for Heavy Duty Cable Vaults and Pull boxes shall conform to the following: 14 Materials Requirements Concrete Section 6-02 Reinforcing Steel Section 9-07 Cover Section 9-05.15(1) Ring Section 9-05.15(1) Anchors (studs) Section 9-06.15 ASTM F 593 or A 193, Type 304 or 316, or Bolts, Nuts, Washers Stainless steel grade 302, 304, 316 in accordance with approved shop drawing 15 16 9-29.6(2) Slip Base Hardware 17 “AASHTO M 291” is revised to read “ASTM A 563”, “AASHTO M 164” is revised to read 18 “ASTM A 325”, and “AASHTO M 293” is revised to read “ASTM F 436. 19 20 9-29.6(5) Foundation Hardware 21 “AASHTO M 291” is revised to read “ASTM A 563”. 22

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 82 1 9-29.10 Luminaires 2 The third paragraph is revised to read: 3 4 All luminaires shall be provided with markers for positive identification of light source 5 type and wattage in accordance with ANSI C136.15-2011. Legends shall be sealed with 6 transparent film resistant to dust, weather, and ultraviolet exposure. 7 8 9-29.10(2) Decorative Luminaries 9 The second sentence in the third paragraph is deleted. 10 11 9-29.13 Traffic Signal Controllers 12 This section and all sub-sections including title is revised to read: 13 14 9-29.13 Control Cabinet Assemblies 15 Control cabinet assemblies shall include all necessary equipment and auxiliary 16 equipment for controlling the operation of traffic signals, programmable message signs, 17 illumination systems, ramp meters, data stations, CCTV, and similar systems as 18 required for the specific application. Traffic Signal Controller Cabinet Assemblies shall 19 meet the requirements of the NEMA TS1 and TS2 specification or the California 20 Department of Transportation “Transportation Electrical Equipment Specifications” 21 (TEES) dated March 12, 2009 as defined in this specification. 22 23 9-29.13(1) Environmental, Performance, and Test Standards for Solid-State 24 Traffic Controller Assemblies 25 The scope of this Specification includes the controller of solid-state design installed 26 in a weatherproof controller cabinet. The controller assembly includes the cabinet, 27 controller unit, load switches, signal conflict monitoring circuitry, accessory logic 28 circuitry, AC line filters, vehicle detectors, coordination equipment and interface, 29 and preemption equipment. NEMA control assemblies shall meet or exceed current 30 NEMA TS 1 Environmental Standards. Normal operation will be required while the 31 control assembly is subjected to any combination of high and low environmental 32 limits (such as low voltage at high temperature with high repetition noise 33 transients). All other control equipment shall meet the environmental requirements 34 of California Department of Transportation “Transportation Electrical Equipment 35 Specifications” (TEES) dated March 12, 2009. 36 37 The Contractor shall furnish to the Contracting Agency all guarantees and 38 warranties furnished as a normal trade practice for all control equipment provided. 39 40 9-29.13(2) Manufacturing Quality 41 The fabricator of the Control, cabinet Assemblies shall perform quality control (QC) 42 inspections based on their QC program. Their QC program shall be submitted and 43 approved by WSDOT at least annually. The fabricator of the controller shall certify 44 that the controller meets all requirements of the Standard Specifications and 45 Special Provisions for the specific application. 46 47 The QC program shall include, but not be limited to, the following: 48 49 1. Quality Statement 50 51 2. Individual responsible for quality (organizational chart) 52 53 3. Fabrication procedures

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 83 1 2 4. Test procedures 3 4 5. Documented inspection reports 5 6 6. Documented test reports 7 8 7. Certification package 9 10 9-29.13(2)A Traffic Signal Controller Assembly Testing 11 Each traffic signal controller assembly shall be tested as follows. The supplier 12 shall: 13 1. Seven days prior to shipping, arrange appointment for controller 14 cabinet assembly, and testing at the WSDOT Materials Laboratory or 15 the facility designated in the Special Provisions. 16 17 2. Assembly shall be defined as but not limited to tightening all screws, 18 nuts and bolts, verifying that all wiring is clear of moving parts and 19 properly secured, installing all pluggables, connecting all cables, 20 Verify that all Contract required documents are present, proper 21 documentation is provided, and all equipment required by the 22 Contract is installed. 23 24 3. The assembly shall be done at the designated WSDOT facility in the 25 presence of WSDOT personnel. 26 27 4. The supplier shall demonstrate that all of the functions required by 28 this Specification and the Contract Plans and Special Provisions 29 perform as intended. Demonstration shall include but not be limited to 30 energizing the cabinet and verifying that all 8 phases, 4 pedestrian 31 movements, 4 overlaps (as required by the Contract Provisions) 32 operate in accordance with Section 9-29.13. The supplier shall place 33 the controller in minimum recall with interval timing set at convenient 34 value for testing purposes. Upon a satisfactory demonstration the 35 controller assembly will then be accepted by WSDOT for testing. 36 37 5. If the assembly and acceptance for testing is not complete within 5 38 working days of delivery, the Project Engineer may authorize the 39 return of the assembly to the supplier, with collect freight charges to 40 the supplier. 41 42 6. The Contractor will be notified when the testing is complete, and 43 where the assembly is to be picked-up for delivery to the project. 44 45 7. The supplier has 5 working days to repair or replace any components 46 that fail during the testing process at no cost to the Contracting 47 Agency. A failure shall be defined as a component that no longer 48 functions as intended under the conditions required or does not meet 49 the requirements of the Contract Specifications and is at the sole 50 discretion of WSDOT. 51 52 8. Any part or component of the controller assembly, including the 53 cabinet that is rejected shall not be submitted for use by WSDOT or 54 any City or County in the State of Washington.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 84 1 2 9-29.13(3) Traffic Signal Controller 3 The traffic signal controller shall conform to the Contract requirements and the 4 applicable Specifications as listed below: All solid-state electronic traffic-actuated 5 controllers and their supplemental devices shall employ digital timing methods. 6 7 A. NEMA control and all auxiliary equipment shall conform to current NEMA 8 TS1 or TS2 Specification. Every pin of every connecting plug shall be 9 utilized as described within the NEMA requirement, except that those pins 10 identified as “spare” or “future” shall remain unused. 11 12 B. Type 170E controllers shall conform to the TEES. The 170E controller 13 shall be provided with a program card, one blank ROM chip, and two 64K 14 non-volatile memory chips. 15 16 C. Type 170E/HC-11 controllers shall conform to the current Oregon 17 Department of Transportation Specification for model 170E/HC-11 18 controller. The 170E controller with the HC11 chip shall be compatible with 19 the software specified in the Contract. The controller shall be provided 20 with one ROM chip and one 64K non-volatile memory chip. 21 22 D. Vacant 23 24 E. Type 2070 controllers shall conform to the TEES. The standard 2070 25 controller shall consist of the following: 26 2070 2070E 2070N1 2070-5 VME cage 2070-1E CPU 2070-1E CPU 2070-1E CPU Card Card Card 2070-3B Front 2070-3B 2070-3B Front Panel Panel Front Panel 2070-4 Power 2070-4 Power 2070-4 Power Supply Supply Supply 2070-2A Field 2070-2A Field 2070-2B Field I/O I/O I/O X X 2070-8 Interface 27 28 9-29.13(4) Traffic-Signal Controller Software 29 All traffic signal controllers shall operate with software specified in the contract. 30 31 Traffic-actuated controllers shall be electronic devices which, when connected to 32 traffic detectors or other means of actuation, or both, shall operate the electrical 33 traffic signal system at one or more intersections. 34 35 If the complete traffic controller defined in the Special Provision requires NTCIP 36 compliance the following are the minimum requirements for NTCIP operation. 37 38 Communication 39 The traffic controller hardware and software shall communicate with the central 40 computer in a polled multi-drop operation. In the polled multi-drop operation, 41 several traffic controllers shall share the same communication channel, with each

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 85 1 controller assigned a unique ID number. Controller ID numbers shall conform to 2 the NTCIP requirements for address numbers. A traffic controller shall only reply to 3 messages labeled with its ID. In polled multi-drop mode, traffic controllers never 4 initiate communication, but merely transmit their responses to messages from the 5 central computer. 6 7 A laptop computer connected to the traffic controller’s local communication port 8 shall have the same control and diagnostic capabilities as the central computer. 9 However, local laptop control capability shall be limited to that traffic controller. 10 11 NTCIP Requirements 12 The traffic controller software shall comply with the National Transportation 13 Communications for ITS Protocol (NTCIP) documents and all related errata sheets 14 published before July 1, 1999 and as referenced herein. 15 16 The traffic controller software shall support the following standards: 17 18 1. NTCIP 1101, Simple Transportation Management Framework (STMF), 19 Conformance Level 1 (Simple Network Management Protocol (SNMP)) 20 21 2. NTCIP 2001, Class B Profile. All serial ports on the device shall support 22 communications according to these standards. 23 24 3. NTCIP 2101, SP-PMPP/RS232 Point-to-Multi-Point Protocol (PMPP) 25 26 4. NTCIP 2201, NTCIP TP-Null Transport Profile Null (TP-NULL) 27 28 The traffic controller software shall implement all mandatory objects of all 29 mandatory conformance groups as defined in NTCIP 1201, Global Object 30 Definitions, and NTCIP 1202, Object Definitions for Actuated Traffic Signal 31 Controller Units. Software shall implement the following conformance groups: 32 33 NTCIP 1202, Object Definitions for ASC 34 Conformance Group Reference Configuration 1201 2.2 Time Management Time Base Event Schedule Report 2.5 Phase 1202 2.2 Rings 2.8 Detector 2.3 Unit 2.4 Preempt 2.7 Time Base 2.6 Coordination 2.5 Channel 2.9 Overlaps 2.10 35 36 The software shall implement the following optional objects: 37 38 Objects required by these specifications shall support all values within its 39 standardized range. The standardized range is defined by a size, range, or

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 86 1 enumerated listing indicated in the object’s SYNTAX field and/or through 2 descriptive text in the object’s description field. The following list indicates the 3 modified object requirements for these objects. 4 Object Object Minimum Name ID Requirements Global Configuration moduleType Value 3 Database Management dBCreateTransaction All Values dBErrorType All values Time Management globslDaylightSavings Values 2 and 3 Timebase Events Schedule maxTimeBaseScheduleEntries 16 MaxDayPlans 15 MaxDayEvents 10 Report maxEventLogCongifs 50 MventConfigMode Values 2 thru 5 mventConfigAction Values 2 and 3 MaxEventLogSize 255 MaxEventClasses 7 PMPP maxGroupAddress 2 ASC Phase maxPhases 8 pPhaseStartp Values 2 thru 6 phaseOptions All Values maxPhaseGroups 1 Rings maxRings 2 maxSequences 16 Detector maxVehicleDetectors 64 vehicleDetectorOptions All Values maxPedestrianDetector 8 Unit unitAutoPedestrianClear All Values unitControlStatus All Values unitFlashStatus All Values unitControl All Values maxAlarmGroups 1 Special Function maxSpecialFunctionsOutputs 8 Coordination coordCorrectionMode Values 2 thru 4 coordMaximumMode Values 2 thru4 coordForceMode Values 2 and 3 maxPatterns 48 patternTableType Either 2,3 or 4 maxSplits 16 splitMode Values 2 thru 7 localFreeStatus Values 2 thru 11 Time Base maxTimebaseAscAction 48 Preempt maxPreempts 4 preemptControl All Values preemptState Values 2 thru 9 Overlaps maxOverlaps 4 overlapType Value 2 and 3 maxOverlapstatusGroup 1 Channels maxChannels 16 channelControlGroup Values 2 thru 4

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 87 channelFlash Value 0,2,4,6,8,10,12 and 14 channelDim Values 0 thru 15 maxChannelStatusGroup 2 TS 2 Port 1 maxPortAddresses 18 port1Table Values 2 and 3 1 2 * values in excess of the minimum requirement are considered to meet the 3 specification. 4 5 Documentation 6 Software shall be supplied with all documentation on a CD. ASCII versions of the 7 following Management Information Base (MIB) files in Abstract Syntax Notation 1 8 (ASN.1) format shall be provided on CD-ROM: 9 10 1. The official MIB Module referenced by the device functionality. 11 12 2. A manufacturer-specific version of the official MIB Module with the non- 13 standardized range indicated in the SYNTAX field. The filename shall 14 match the official MIB Module, with the extension “spc”. 15 16 3. A MIB Module of all manufacturer-specific objects supported by the device 17 with accurate and meaningful DESCRIPTION fields and the supported 18 ranges indicated in the SYNTAX field. 19 20 9-29.13(5) Flashing Operations 21 All traffic signals shall be equipped for flashing operation of signal displays. 22 Controllers and cabinets shall be programmed for flashing displays for all 23 approaches. During flashing operation, all pedestrian circuits shall be de-energized. 24 25 Actuated traffic signal control mechanisms shall be capable of entry into flash 26 operation and return to stop-and -go operation as follows: 27 28 1. Terminal Strip Input (Remote Flash). When called as a function of a 29 terminal strip input, the controller shall provide both sequenced entry into 30 flash and sequenced return to normal operation consistent with the 31 requirements of the latest edition of the Manual on Uniform Traffic Control 32 Devices. 33 34 2. Police Panel Switch. When the flash-automatic switch located behind the 35 police panel door is turned to the flash position, the signals shall 36 immediately revert to flash; and, the controller shall have a stop time input 37 applied. When the switch is placed on automatic, the controller shall 38 immediately time an 6 second all red period then resume stop-and-go 39 operations at the beginning of major street . 40 41 3. Controller Cabinet Switches. When the flash-automatic switch located 42 inside the controller cabinet is placed in the flash position, the signals shall 43 immediately revert to flash; however, the controller shall not have a stop 44 time input applied. When the flash-automatic switch is placed in the 45 automatic position, the controller shall immediately time a 6 second all red

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 88 1 period, then resume stop-and-go operation at the beginning of the major 2 green. 3 4 4. Power Interruption. On “NEMA” controllers any power interruption longer 5 than 475 plus or minus 25 milliseconds, signals shall re-energize 6 consistent with No. 2 above to ensure an 6-second flash period prior to 7 the start of major street green. A power interruption of less than 475 plus 8 or minus 25 milliseconds shall not cause resequencing of the controller 9 and the signal displays shall re-energize without change. Type 170 10 controllers shall re-energize consistent with No. 2 above after a power 11 interruption of 1.75 plus or minus 0.25 seconds. The 6-second flash period 12 will not be required. Any power interruption to a 2070 type controller shall 13 result in a 6 second flash period once power is restored. 14 15 5. Conflict Monitor. Upon detecting a fault condition the conflict monitor shall 16 immediately cause the signal to revert to flash and the controller to stop 17 time. After the conflict monitor has been reset, the controller shall 18 immediately take command of the signal displays at the beginning of 19 major street green. 20 21 9-29.13(6) Emergency Preemption 22 Immediately after a valid call has been received, the preemption equipment shall 23 cause the controller to terminate the appropriate phases as necessary with the 24 required clearance intervals and enter any programed subsequent preemption 25 sequence. Preemption sequences shall be as noted in the Contract. 26 27 9-29.13(7) Wiring Diagrams 28 Schematic wiring diagrams of the controllers, cabinets and auxiliary equipment 29 shall be submitted when the assemblies are delivered. The diagram shall show in 30 detail all circuits and parts. The parts shall be identified by name or number in a 31 manner readily interpreted. Two hard copies of the cabinet wiring diagram and 32 component wiring diagrams shall be furnished with each cabinet and a pdf file of 33 the cabinet wiring and component drawings. The schematic drawing shall consist of 34 a single sheet, detailing all circuits and parts, not to exceed 52-inches by 72-inches. 35 The cabinet wiring diagram shall indicate and identify all wire terminations, all plug 36 connectors, and the locations of all equipment in the cabinet. Included in the 37 diagram shall be an intersection sketch identifying all heads, detectors, and push 38 buttons and a phase diagram. 39 40 9-29.13(8) Generator Transfer Switch 41 When specified in the contract, A generator transfer switch shall be included. . The 42 Generator Transfer Switch shall be capable of switching power from a utility power 43 source to an external generator power source. 44 45 The Transfer Switch enclosure shall be of identical materials and dimensions and 46 installation methods as the Police Panel type enclosure specified in the first 47 paragraph of Special Provision 9-29.13(10)D except that the enclosure door shall 48 include a spring loaded construction core lock capable of accepting a Best 6-pin CX 49 series core. The core lock shall be installed with a green construction core. Upon 50 contract completion, two master keys for the construction core shall be delivered to 51 the Engineer. 52 53 The enclosure shall include the following Transfer Switch equipment: 54

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 89 1 1. One Nema L5-30P Flanged Inlet generator connector 2 3 2. One Utility power indicator light 4 5 3. One generator indicator light 6 7 4. Two 30 amp, 120 volt, single pole, single phase, circuit breakers. One 8 circuit breaker shall be labeled “Generator” and the other circuit breaker 9 shall be labeled “Utility”. Both labels shall be engraved phenolic name 10 plates. 11 12 5. A mechanical lock out feature that prevents the Utility circuit breaker and 13 the Generator circuit breaker from being in the ON position at the same 14 time. The circuit breakers shall be capable of being independently 15 switched. 16 17 6. The conductors from the Generator Transfer Switch enclosure to the 18 cabinet circuit breaker shall be enclosed in nylon mesh sleeve. 19 20 7. The enclosure door shall be labeled with the letters “GTS”. 21 22 9-29.13(9) Vacant 23 24 9-29.13(10) NEMA, Type 170E, 2070 Controllers and Cabinets 25 26 9-29.13(10)A Auxiliary Equipment for NEMA Controllers 27 The following auxiliary equipment shall be furnished and installed in each 28 cabinet for NEMA traffic-actuated controllers: 29 30 1. A solid-state Type 3 NEMA flasher with flash-transfer relay which will 31 cut in the flasher and isolate the controller from light circuits. See 32 Section 9-29.13(5) for operational requirements. 33 34 2. Modular solid state relay load switches of sufficient number to provide 35 for each vehicle phase (including future phases if shown in the plans), 36 each pedestrian phase and preemption sequence indicated in the 37 Contract. Type P & R cabinets shall include a fully wired 16-position 38 back panel. Solid-state load switches shall conform to NEMA 39 standards except only optically isolated load switches will be allowed. 40 Load switches shall include indicator lights on the input and output 41 circuits. The controller cabinet shall have all cabinet wiring installed 42 for eight vehicle phases, four pedestrian phases, four emergency pre- 43 empts, four overlaps (OL A, B, C, D). 44 45 3. A power panel with: 46 47 a. A control-display breaker sized to provide 125 percent overload 48 protection for all control equipment and signal displays, 20 49 ampere minimum. 50 51 b. A 15 ampere accessory breaker wired parallel to the control 52 display breaker. The breaker will carry accessory loads, including 53 vent fan, cabinet light, plug receptacle, etc. 54

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 90 1 c. A busbar isolated from ground and unfused for the neutral side of 2 power supply. 3 4 d. A radio interference suppresser installed at the input power point. 5 Interference suppressers shall be of a design which will minimize 6 interference in both broadcast and aircraft frequencies, and shall 7 provide a minimum attenuation of 50 decibels over a frequency 8 range of 200 kilohertz to 75 megahertz when used in connection 9 with normal installations. The interference filters furnished shall 10 be hermetically sealed in a substantial case filled with a suitable 11 insulating compound. Terminals shall be nickel plated, 10-24 12 brass studs of sufficient external length to provide space to 13 connect two 8 AWG wires, and shall be so mounted that they 14 cannot be turned in the case. 15 16 Ungrounded terminals shall be insulated from each other and 17 shall maintain a surface leakage distance of not less than ½-inch 18 between any exposed current conductor and any other metallic 19 parts with an insulation factor of 100-200 megohms dependent 20 on external circuit conditions. 21 22 Suppressers shall be designed for operations on 50 amperes, 23 125 volts, 60 cycles, single wire circuits, and shall meet 24 standards of the Underwriters’ Laboratories and the Radio 25 Manufacturers Association. 26 27 e. A Surge Protection Device connected to the controller power 28 circuit for protection against voltage abnormalities of 1 cycle or 29 less duration. The Surge Protection Device shall be a solid state 30 high energy circuit containing no spark gap, gas tube, or crow 31 bar component. The device shall provide transient protection 32 between neutral and ground, line and ground, as well as line and 33 neutral. If the protection circuits fail, they shall fail to an open 34 circuit condition. The minimum interrupting capacity shall be 35 10,000 Amps. The Voltage Protection Rating shall be 600 volts or 36 less when subjected to an impulse of 6,000 volts, 3,000 amp 37 source impedance, 8.0/20 microsecond waveform as described 38 in UL 1449. In addition, the device shall dissipate a 13,000 Amp 39 or greater repeated single peak 8/20 microsecond current 40 impulse, and withstand, without failure or permanent damage, 41 one full cycle at 264 volts RMS. The device shall contain circuitry 42 to prevent self-induced regenerative ringing. There shall be a 43 failure warning indictor which shall illuminate a red light or 44 extinguish a green light when the device has failed and is no 45 longer operable. 46 47 f. Cabinet ground busbar independent (150K ohms minimum) of 48 neutral. 49 50 4. A police panel located behind the police panel door with a flash 51 automatic switch and a control-display power line on-off switch. See 52 Section 9-29.13(5) for operational requirements. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 91 1 5. An auxiliary control panel located inside the controller cabinet with a 2 flash-automatic switch and a controller on-off switch. See Section 9- 3 29.13(5) for operational requirements. A three wire 15 ampere plug 4 receptacle with grounding contact and 15 ampere ground fault 5 interrupter shall also be provided on the panel. 6 7 6. A conflict monitor conforming to NEMA standards. See Section 9- 8 29.13(5) for operational requirements. The unit shall monitor 9 conflicting signal indications at the field connection terminals. The unit 10 shall be wired in a manner such that the signal will revert to flash if 11 the conflict monitor is removed from service. 12 13 Supplemental loads not to exceed 10 watts per monitored circuit or 14 other means, shall be provided to prevent conflict monitor actuation 15 caused by dimming or lamp burn-out. Supplemental loads shall be 16 installed on the control side of the field terminals. Conflict monitors 17 shall include a minimum of one indicator light for each phase used. 18 The monitoring capacity of the unit shall be compatible with the 19 controller frame size. Conflict monitors shall include a program card. 20 21 7. A “Detector Panel”, as specified in Standard Specification Section 22 9-29.13(10)B, shall be installed. The panel shall be mounted on the 23 inside of the front cabinet door. The detector panel shall be 24 constructed as a single unit. Detector switches with separate operate, 25 test, and off positions shall be provided for each field detector input 26 circuit. A high intensity light emitting diode (LED) shall be provided for 27 each switch. The lamp shall energize upon vehicle, pedestrian or test 28 switch actuation. The test switch shall provide a spring loaded 29 momentary contact that will place a call into the controller. When in 30 the OFF position, respective detector circuits will be disconnected. In 31 the operate position, each respective detector circuit shall operate 32 normally. Switches shall be provided on the panel with labels and 33 functions as follows: 34 35 a. Display On — Detector indicator lights shall operate 36 consistent with their respective switches. 37 38 b. Display Off — detector indicator lights shall be de- 39 energized. 40 41 A means of disconnecting all wiring entering the panel shall be 42 provided. The disconnect shall include a means to jumper detection 43 calls when the display panel is disconnected. All switches on the 44 panel shall be marked with its associated Plan detector number. All 45 markers shall be permanent. 46 47 8. Insulated terminal blocks of sufficient number to provide a termination 48 for all field wiring. A minimum of 12 spare terminals shall be provided. 49 Field wire connection terminal blocks shall be 600 volt, heavy duty, 50 barrier type, except loop detector lead-ins, which may be 300 volt. 51 The 600 volt type terminal strips shall be provided with a field-side 52 and a control-side connector separated by a marker strip. The 300 53 volt type shall have a marker strip, installed on the right side of

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 92 1 vertical terminal strips or below horizontal terminal strips. The marker 2 strip shall bear the circuit number indicated in the plans and shall be 3 engraved. Each connector shall be a screw type with No. 8 post 4 capable of accepting no less than three 12 AWG wires fitted with 5 spade tips. 6 7 9. A vent fan with adjustable thermostat. The minimum CFM rating of the 8 fan shall exceed three times the cabinet volume. 9 10 10. VACANT 11 12 11. All wiring within the cabinet, exclusive of wiring installed by the signal 13 controller manufacturer, shall have insulation conforming to the 14 requirements of Section 9-29.3. Cabinet wiring shall be trimmed to 15 eliminate all slack and shall be laced or bound together with nylon 16 wraps or equivalent. All terminals, shall be numbered and 17 permanently identified with PVC or polyolefin wire marking sleeve 18 consistent with the cabinet wiring diagram provided by the signal 19 controller manufacturer and the Contract. The cabinet will be 20 completely wired so that the only requirement to make a field location 21 completely operational is to attach field power and ground wiring. 22 Internal cabinet wiring shall not utilize the field side connections of the 23 terminal strip intended for termination of field wires. 24 25 12. Cabinet wiring diagram and component wiring diagrams meeting the 26 requirements of 9-29.13(7) shall be furnished with each cabinet. Each 27 cabinet shall be equipped with a, shelf mounted roll out drawer 28 mounted directly below the controller to house one or more cabinet 29 wiring diagrams. The cabinet wiring diagram shall indicate and 30 identify all wire terminations, all plug connectors, and the locations of 31 all equipment in the cabinet. Included in the diagram shall be an 32 intersection sketch identifying all heads, detectors, and push buttons; 33 and a phase diagram. 34 35 13. Each vehicle detector amplifier, video detection output channel 36 pedestrian call isolation unit, phase selector, discriminator, and load 37 switch shall be identified with semi-permanent stick-on type label. The 38 following information shall be included: 39 40 a. Vehicle Detector Amplifier Channel 41 42 1. Loop number 43 44 2. Assigned phase(s) 45 46 b. Ped Call Isolation Unit 47 48 1. Push button number 49 50 2. Assigned phase(s) 51 52 c. Load Switches 53 54 1. Signal head number

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 93 1 2 2. Assigned phase(s) 3 4 d. Phase Selectors 5 6 1. Circuit Letter 7 8 2. Phase(s) called 9 10 The label shall be placed on the face of the unit. It shall not block any switch, 11 light, or operational words on the unit. The lettering on this label shall be neat, 12 legible, and easily read from a distance of approximately 6-feet. 13 14 9-29.13(10)B Auxiliary Equipment for Type 170E, 2070 Assemblies 15 The following requirements apply to required auxiliary equipment furnished 16 with Type 170E, 170E-HC-11 and 2070 controllers: 17 18 A. Flashers, flash transfer relays, conflict monitor, AC isolators, DC 19 isolators, discriminator modules, program modules, modem modules, 20 breakers, buses, police panel switches, receptacle requirement, vent 21 fan and auxiliary control panel switches shall conform to the 22 requirements noted in the TEES. 23 24 B. Flashing operation shall conform to Section 9-29.13(5), except the 6- 25 second flash period described in Item 2 of that section will not be 26 required. Emergency preemption shall conform to Section 9-29.13(6). 27 28 C. Input and output terminals shall be installed with a marking strip with 29 field wire numbers noted in the Contract embossed on the strip. All 30 cabinet and field conductor shall have a PVC or polyolefin wire 31 marking sleeve installed, matching the input and output terminals 32 above. Marking on sleeves shall be embossed or type written. 33 34 D. The input panel terminal blocks TB 2 through TB 9 and associated 35 cable to the input files as described in the TEES shall be provided in 36 all control assemblies. 37 38 E. Supplemental load resistor, not less than 2000 ohms and not greater 39 than 5000 ohms not to exceed 10 watts per monitored circuit, shall be 40 provided to prevent conflict monitor actuation caused by dimming or 41 lamp burn-out. 42 43 An individual supplemental load resistor shall be installed within the 44 output file, and shall be installed on each of the following terminal 45 circuits: 46 FT1-105 (SP 4P-Y) FT1-111 (SP 8P-Y) FT2-114 (SP 2P-Y) FT2-120 (SP 6P-Y) FT2-117 (SP 3-Y) FT2-118 (SP 3-G) FT2-123 (SP 7-Y) FT2-124 (SP 7-G) FT3-126 (SP 1-Y) FT3-127 (SP 1-G) FT3-132 (SP 5-Y) FT3-133 (SP 5-G) 47 48 F. Load switches of sufficient quantity to fully populate the output files 49 shall conform to TEES and shall have indicator lights on input and 50 output circuits.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 94 1 2 G. A detection panel, which shall be constructed as a single unit. 3 Detector switches with separate operate, test, and off positions shall 4 be provided for each field detector input circuit. A high intensity light 5 emitting diode (LED) shall be provided for each switch. The lamp shall 6 energize upon vehicle, pedestrian or test switch actuation. The test 7 switch shall provide a spring loaded momentary contact that will place 8 a call into the controller. When in the OFF position, respective 9 detector circuits will be disconnected. In the operate position, each 10 respective detector circuit shall operate normally. Switches shall be 11 provided on the panel with labels and functions as follows: 12 13 a. Display On — Detector indicator lights shall operate 14 consistent with their respective switches. 15 16 b. Display Off — detector indicator lights shall be de- 17 energized. 18 19 A means of disconnecting all wiring entering the panel shall be 20 provided. The disconnect shall include a means to jumper detection 21 calls when the display panel is disconnected. All switches on the 22 panel shall be marked with its associated Plan detector number. All 23 markers shall be permanent. 24 25 H. A “Detector Termination and Interface Panel” shall be provided. When 26 viewing the cabinet from the back, the panel shall be located on the 27 upper left hand side of the cabinet. The panel shall be electrically 28 located between the “detection Panel” and the C-1 connector. The 29 panel shall utilize insulated terminal blocks and each connector shall 30 be a screw type with post. 31 32 I. Each switchpack socket shall have pin 11 common to Nutral. 33 34 J. The AC input Service Panel Assembly (SPA), line voltage filter, 35 transient surge protection and all neutral bus bars and equipment 36 ground bus bars shall be on the right side of the cabinet, mounted no 37 more that 18 inches from the bottom of the cabinet when viewed from 38 the rear, and meet the requirements described in TEES. 39 40 K. The PED yellow terminals on the CMU edge connector shall be 41 extended with a 2 foot wire, coiled, heat shrink tipped and labeled for 42 the correct corresponding terminal as CH-13Y/CMU-8, CH-14Y/CMU- 43 11, CH-15Y/CMU-K, CH-16Y/CMU-N. 44 45 L. An “Absence Of Red Programming Assembly” shall be provided. 46 There shall be provided on the back panel of the output file, 17 47 accessible jumper plug attachment areas, made up of three male pins 48 per position (one, for each conflict monitor channel and one for red 49 enable function). Each jumper plug shall be a two position connector, 50 It shall be possible, by inserting and positioning one of the 16 51 connectors on the right two pins on the monitor board, to apply 120 52 VAC into a corresponding channel of the conflict monitor red 53 channels. The connection between the red monitor board and the

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 95 1 conflict monitor shall be accomplished via a 20 pin ribbon cable and 2 the industry standard P-20 connector that attaches on the front panel 3 of the monitor. It shall be possible, by inserting and positioning one of 4 the 16 jumper plugs on the two left pins on the monitor board, to 5 enable the corresponding channel to monitor for red fault by the 6 conflict monitor. There shall be installed on the red monitor board a 7 red fail monitor disable function that controls the 120 VAC red enable 8 signal into the conflict monitor. During stop-and –go operation, 9 120VAC is sent via pin #20 on the P20 connector to enable red failure 10 monitoring on the conflict monitor by having the connector moved to 11 the side labeled “Red Enable”. If this is disengaged by moving the 12 connector to the side labeled “Red Relay”, then 120VAC is removed 13 from pin #20, and the conflict monitor will no longer monitor for red fail 14 faults. The red enable function will also be wired such that if the 15 traffic signal is in cabinet flash, then there will be no voltage on pin 16 #20, and the conflict monitor will not monitor for red fail faults. 17 18 M. Each cabinet shall be provided with at least 20 empty neutral 19 connections to accommodate field wiring. The neutral bus bars shall 20 be of the style in which a lug is not needed to be applied to the 21 neutral field wire(s). All of the neutral bars shall be secured in 22 accordance with the TEES. All neutral bars shall be at the same 23 electrical potential. 24 25 N. The main breaker on the SPA shall be provided with a cover to 26 prevent accidental tripping. The cover shall be removable and 27 replaceable without the use of tools. VACANT 28 29 O. Equipment Branch Breaker –The duplex receptacle on the rear of 30 either PDA #2L or 3L shall be wired in parallel with the ground fault 31 current interrupt receptacle on the front of the power supply. The 32 ground fault current interrupt receptacle being in the “Test” mode shall 33 not remove power to the rear receptacle. 34 35 9-29.13(10)C NEMA Controller Cabinets 36 Each NEMA traffic controller shall be housed in a weatherproof cabinet 37 conforming to the following requirements: 38 39 1. Construction shall be of 0.073-inch minimum thickness series 300 40 stainless steel or 0.125 minimum thickness 5052 H32 ASTM B209 41 alloy aluminum. The stainless steel shall be annealed or one-quarter- 42 hardness complying with ASTM A666 stainless steel sheet. Cabinets 43 may be finished inside with an approved finish coat of exterior white 44 enamel. If no other coating is specified in the Contract Provisions the 45 exterior of all cabinets shall be bare metal. All controller cabinets shall 46 be furnished with front and rear doors. 47 48 2. The cabinet shall contain shelving, brackets, racks, etc., to support 49 the controller and auxiliary equipment. All equipment shall set 50 squarely on shelves or be mounted in racks and shall be removable 51 without turning, tilting, or rotating or relocating one device to remove 52 another. A 24 slot rack or racks shall be installed. The rack(s) shall be 53 wired for 2 channel loop detectors and as follows. Slots 1 & 2 phase 1 54 loop detectors. Slots 3, 4, & 5 phase 2 loop detectors. Slots 6 & 7

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 96 1 phase 3 loop detectors. Slots 8, 9, & 10 phase 4 loop detectors. Slots 2 11 & 12 phase 5 loop detectors. Slots 13, 14, & 15 phase 6 loop 3 detectors. Slots 16 & 17 phase 7 loop detectors. Slots 18, 19 & 20 4 phase 8 loop detectors. Slot 21 upper phase 1 loop detector. Slot 21 5 lower phase 5 detector. Slot 22 wired for a 2 channel discriminator 6 channels A, C. Slot 23 wired for a 2 channel discriminator, channels 7 B, D. Slot 24 wired for a 4 channel discriminator, wired for channel A, 8 B, C, and D. All loop detector slots shall be wired for presence/pulse 9 detection/extension. If an external power supply is required in order 10 for the entire racks(s) to be powered it shall be installed. All rack(s) 11 slots shall be labeled with engraved identification strips. 12 13 3. Additional detection utilizing the “D” connector shall be installed in 14 accordance with the Contract. The cabinet shall be of adequate size 15 to properly house the controller and all required appurtenances and 16 auxiliary equipment in an upright position with a clearance of at least 17 3-inches from the vent fan and filter to allow for proper air flow. In no 18 case shall more than 70 percent of the cabinet volume be used. 19 There shall be at least a 2-inch clearance between shelf mounted 20 equipment and the cabinet wall or equipment mounted on the cabinet 21 wall. 22 23 4. The cabinet shall have an air intake vent on the lower half of the front 24 door, with a 12-inch by 16-inch by 1-inch removable throw away filter, 25 secured in place with a spring-loaded framework. 26 27 5. The cabinet door(s) shall be provided with: 28 29 a. Cabinet doors shall each have a three point latch system. Locks 30 shall be spring loaded construction locks capable of accepting a 31 Best 6 pin core. A 6 pin construction core of type (, green, or 32 Red) specified in the contract shall be installed in each core lock. 33 One core removal key and two standard keys shall be included 34 with each cabinet and delivered to the Engineer. 35 36 b. A police panel assembly shall be installed in the front door and 37 shall have a stainless steel hinge pin and a police panel lock. 38 Two police keys with shafts a minimum of 1¾-inches long shall 39 be provided with each cabinet. 40 41 c. All doors and police panel door shall have one piece, closed cell, 42 neoprene gaskets. 43 44 d. A two position doorstop assembly. 45 46 6. Fluorescent fixtures or LED light strips (only one type per cabinet) for 47 cabinet lighting. Color temperature shall be 4100K (cool white) or 48 higher. Fluorescent fixtures shall use 12 inch (nominal), 8W, type T5 49 shatterproof tubular bulbs. LED light strips shall be approximately 12 50 inches long, and have a minimum output of 320 lumens. Lighting 51 shall be ceiling mounted and oriented parallel to the door face. 52 Lighting shall not interfere with the proper operation of any other 53 ceiling mounted equipment. All lighting fixtures shall energize

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 97 1 whenever any door is opened. Each door switch shall be labeled 2 “Light”. 3 4 9-29.13(10)D Cabinets for Type 170E and 2070 controllers 5 Type 170E and 2070 controllers shall be housed in a model 332L cabinet 6 unless specified otherwise in the contract. Type 332L cabinets shall be 7 constructed in accordance with TEES with the following modifications: 8 9 1. Each door shall be furnished with the equipment listed in Standard 10 Specifications 9-29.13(10)C item 5 above. 11 12 2. The cabinet shall be furnished with auxiliary equipment described in 13 Standard Specification 9-29.13(10)B. 14 15 3. The cabinet shall be fabricated of stainless steel or sheet aluminum in 16 accordance with Section 9-29.13(10)C, Item 1 above. Painted steel, 17 painted or anodized aluminum is not allowed. 18 19 4. A disposable paper filter element with dimensions of 12” x 6” x 1” shall 20 be provided in lieu of a metal filter. The filter shall be secured in the 21 filter holder with a louvered aluminum cover. The maximum depth of 22 the cover shall not be more than 0.5” inch to provide the filter to be 23 flush against the door. No incoming air shall bypass the filter 24 element. 25 26 5. Field wire terminals shall be labeled in accordance with the Field 27 Wiring Chart. 28 29 6. Fluorescent fixtures or LED light strips (only one type per cabinet) for 30 cabinet lighting. Fluorescent fixtures shall use 12 inch (nominal), 8W, 31 type T5 tubular bulbs. Tubular bulbs shall be contained within a 32 shatterproof lamp cover. Led strips shall be approximately 12 inches 33 long, and have a minimum output of 320 lumens. There shall be one 34 fixture for each rack within the cabinet. Lighting shall be ceiling 35 mounted and oriented perpendicular to the door face. Rack mounted 36 lights are not allowed. Lighting shall be positioned such that the 37 fixture is centered between the front and rear of the cabinet. Lighting 38 shall not interfere with the proper operation of any other ceiling 39 mounted equipment. Each lighting fixture shall energize automatically 40 when either door to that respective rack is opened. Each door switch 41 shall be labeled “Light”. 42 43 7. One drawer shelf, as shown in the TEES 44 45 8. 332D Controller Cabinet 46 47 a. The 332D Controller cabinet shall have the appearance of two 48 Type 332 controller cabinets joined at opposing sides. The 49 outside Dimensions of the cabinet shall be 67” High X 48 1/2” 50 Wide X 30 1/4” Deep. 51 52 b. The right side of the cabinet, as viewed from the front, shall be 53 considered the Signal Control side. The left side of the cabinet,

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 98 1 when viewed from the front, shall be considered the ITS/COMM 2 side. 3 4 c. One police access panel shall be installed on the right side of the 5 cabinet, as viewed from the front. 6 7 d. Two cabinet lights shall be provided one on each side and as 8 described in section 9-29.13(10)D.6 9 10 e. Vacant 11 12 f. The Traffic Signal Control side of the cabinet shall contain the 13 Traffic Signal Controller assembly and shall be furnished with 14 equipment as described in the contract specifications. The 15 Traffic Signal Control side of the cabinet shall also meet all the 16 additional equipment requirements of the Type 332 Signal 17 Controller cabinet as indicated in the contract specifications. 18 19 g. The ITS/COMM side of the cabinet shall contain ITS and 20 Communication equipment and shall be furnished with the 21 following: 22 23 1. One controller shelf unit, mounted 36 inches from the bottom 24 of the cabinet opening to the front of the cabinet and 25 attaching to the front rails of the EIA rack, shall be provided. 26 The shelf shall be fabricated from aluminum and shall 27 contain a rollout flip-top drawer for storage of wiring 28 diagrams and manuals. 29 30 2. One aluminum sheet metal panel, 1/8”x 15”x 54”, shall be 31 installed to the rear of the cabinet on the right hand (when 32 facing the front) side railing. 33 34 3. Additional ITS and Communication equipment as described 35 in the Contract Plans and the ITS section of the Contract 36 Special Provisions. 37 38 9-29.13(11) Traffic Data Accumulator and Ramp Meters 39 All cabinets designated for use as a traffic data or ramp meter shall be Type 334L 40 cabinets furnished to meet the TEES with the modifications listed in Section 9- 41 29.13(10)D and include the following accessories: 42 43 1. Each cabinet shall be equipped with a fully operable controller equipped as 44 specified in the Contract Provisions. 45 46 2. Two input files, shall be provided. 47 48 3. The PDA #3L shall contain three Model 200 Load Switches. 49 A second transfer relay, Model 430, shall be mounted on the rear of the PDA 50 #3L and wired as shown in the Plans. 51 52 4. Police Panel shall contain only one DPDT toggle switch. The switch shall be 53 labeled POLICE CONTROL, ON-OFF.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 99 1 2 5. Display Panel 3 4 A. General 5 Each cabinet shall be furnished with a display panel. The panel shall be 6 mounted, showing and providing detection for inputs and specified 7 controller outputs, at the top of the front rack above the controller unit. The 8 display panel shall be fabricated from brushed aluminum and constructed 9 according to the detail in the Plans. 10 11 B. Text 12 All text on the detector panel shall be black in color and silk screened 13 directly to the panel except the Phenolic detector and cabinet nameplates. 14 15 A nameplate for each loop shall be engraved with a ¼-inch nominal text 16 according to the ITS Field Wiring Charts. The nameplates shall be 17 permanently affixed to the detector panel. 18 19 C. LEDs 20 The LEDs for the display panel shall meet the following Specifications: 21 22 Case size T 1-¾ 23 Viewing angle 50° minimum 24 Brightness 8 Milli candelas 25 26 LEDs with RED, YELLOW or GREEN as part of their labels shall be red, 27 yellow or green in color. All other LEDs shall be red. All LEDs shall have 28 tinted diffused lenses. 29 30 D. Detector panel Control Switch 31 Each display panel shall be equipped with one detector display control 32 switch on the panel with labels and functions as follows: 33 34 ON 35 Detector panel LEDs shall operate consistent with their separate 36 switches. 37 38 OFF 39 All detector indicator LEDs shall be de-energized. Detector calls shall 40 continue to reach the controller. 41 42 TEST 43 All detector indicator LEDs shall illuminate and no calls shall be 44 placed to the controller. 45 46 E. Advance Warning Sign Control Switch 47 Each display panel shall be equipped with one advance warning sign 48 control switch on the panel with labels and functions as follows: 49 50 AUTOMATIC 51 Sign Relay shall energize upon ground true call from controller. 52 53 SIGN OFF

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 100 1 Sign Relay shall de-energize. 2 3 SIGN ON 4 Sign Relay shall energize. 5 6 F. Sign Relay 7 The sign relay shall be plugged into a socket installed on the rear of the 8 display panel. The relay shall be wired as shown in the Plans. The relay 9 coil shall draw (or sink) 50 milliamperes ± 10% from the 170E/HC11 10 controller and have a DPDT contact rating not less than 10 amperes. A 11 1N4004 diode shall be placed across the relay coil to suppress voltage 12 spikes. The anode terminal shall be connected to terminal #7 of the relay 13 as labeled in the Plans. The relay shall energize when the METERING 14 indicator LED is lit. 15 16 G. Detector Input Indicators 17 One LED and one spring-loaded two-position SPST toggle switch shall be 18 provided for each of the 40 detection inputs. These LEDs and switches 19 shall function as follows: 20 21 TEST 22 When the switch is in the test position, a call shall be placed to the 23 controller and energize the associated LED. The switch shall 24 automatically return to the run position when it is released. 25 26 RUN 27 In the run position the LEDs shall illuminate for the duration of each 28 call to the controller. 29 30 H. Controller Output Indicators 31 The display panel shall contain a series of output indicator LEDs mounted 32 below the detection indicators. The layout shall be according to the detail 33 in the Plans. These LEDs shall illuminate upon a ground true output from 34 the controller via the C5 connector. 35 36 The output indicator LEDs shall have resistors in series to drop the voltage 37 from 24 volts DC to their rated voltage and limit current below their rated 38 current. The anode connection of each LED to +24 VDC shall be wired 39 through the resistor. 40 41 I. Connectors 42 Connection to the display panel shall be made by three connectors, one 43 pin (labeled P2) and one socket (labeled P1) and one labeled C5. The P1 44 and P2 connectors shall be 50-pin cannon D series, or equivalent 50 pin 45 connectors and shall be compatible such that the two connectors can be 46 connected directly to one another to bypass the input detection. Wiring for 47 the P1, P2 and C5 connectors shall be as shown in the Plans. 48 49 The Contractor shall install wire connectors P1, P2, C1P, C2, C4, C5 and 50 C6 according to the pin assignments shown in the Plans. 51 52 6. Model 204 Flasher Unit

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 101 1 Each Model 334 ramp meter cabinet shall be supplied with one Model 204 sign 2 flasher unit mounted on the right rear side panel. The flasher shall be powered 3 from T1-2. The outputs from the flasher shall be wired to T1-5 and T1-6. 4 5 7. Fiber Optic Patch Panel 6 The Contractor shall provide and install a rack-mounted fiber optic patch panel 7 as identified in the Plans. 8 9 Cabinet Wiring 10 Terminal blocks TB1 through TB9 shall be installed on the Input Panel. Layout and 11 position assignment of the terminal blocks shall be as noted in the Plans. 12 13 Terminals for field wiring in traffic data and/or ramp metering controller cabinet shall 14 be labeled, numbered and connected in accordance with the following: 15 Terminal Block Pos. Terminal and Wire Numbers Connection Identification TBS 501-502 AC Power, Neutral T1-2 641 Sign on T1-4 643 Sign off T1-5 644 Flasher Output NC T1-6 645 Flasher Output NO T4-1 631 Lane 3 - Red T4-2 632 Lane 3 – Yellow T4-3 633 Lane 3 – Green T4-4 621 Lane 2 - Red T4-5 622 Lane 2 - Yellow T4-6 623 Lane 2 – Green T4-7 611 Lane 1 – Red T4-8 612 Lane 1 – Yellow T4-9 613 Lane 1 – Green 16 17 18 Loop lead-in cables shall be labeled and connected to cabinet terminals according 19 to the ITS Field Wiring Chart. This chart will be provided by the Engineer within 20 20 days of the Contractor’s request. 21 22 9-29.13(12) ITS cabinet: 23 Basic ITS cabinets shall be Model 334L Cabinets, unless otherwise specified in the 24 Contract. Type 334L Cabinets shall be constructed in accordance with the TEES, with 25 the following modifications: 26 27 1. The basic cabinet shall be furnished with only Housing 1 B, Mounting Cage 1, 28 Service Panel #1, a Drawer Shelf, and Controller Unit Supports. Additional 29 equipment may be specified as part of the cabinet function-specific standards. 30

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 102 1 2. Housing aluminum shall be 5052 alloy with mill finish. Painted or anodized 2 aluminum is not allowed. 3 4 3. The door air filter shall be a disposable paper filter element of at least 180 5 square inches. 6 7 4. Locks shall be spring loaded construction core locks capable of accepting a 8 Best 6-pin core. A 6-pin construction core of the type (Blue, Green, or Red) 9 specified in the Contract shall be installed in each core lock. One core 10 removal key and two standard keys (properly marked) shall be included with 11 each cabinet and delivered to the Engineer upon Contract completion. 12 13 5. Each cabinet shall include a 120VAC electric strip heater with a rating of 100 14 watts, which shall be thermostat controlled. The heater strip shall be fed by 15 wire with a temperature rating of 400°F or higher, and shall be shielded to 16 prevent contact with wiring, equipment, or personnel. If the heater thermostat 17 is separate from the fan thermostat, the heater thermostat must meet the same 18 requirements a++++s the fan thermostat as defined in TEES. 19 20 6. Fluorescent fixtures or LED light strips (only one type per cabinet) for cabinet 21 lighting. Color temperature shall be 4100K (cool white) or higher. Fluorescent 22 fixtures shall use 12 inch (nominal), 8W, type T5 tubular bulbs contained within 23 a shatterproof lamp cover. LED light strips shall be approximately 12 inches 24 long, and have a minimum output of 320 lumens. There shall be two fixtures 25 for each rack within the cabinet Lighting shall be ceiling mounted and oriented 26 parallel to the door face – rack mounted lighting is not permitted. Lighting shall 27 not interfere with the proper operation of any other ceiling mounted equipment. 28 All lighting fixtures above a rack shall energize whenever either door to that 29 respective rack is opened. Each door switch shall be labeled “Light”. 30 31 7. Each cabinet shall be equipped with a power distribution assembly (PDA) 32 mounted in a standard EIA 19-inch (ANSI/EIA RS-310-C) rack utilizing no more 33 than five Rack Mounting Units (RMU) (8.75 inches). The PDA shall include the 34 following equipment: 35 36 a. One duplex NEMA 5-15R GFCI receptacle on the front of the PDA. 37 38 b. Four duplex NEMA 5-15R receptacles on the rear of the PDA. These 39 receptacles shall remain energized on a trip or failure of the GFCI 40 receptacle. 41 42 c. Four 1P-15A, 120VAC Equipment/Field Circuit Breakers. 43 44 d. Line filter meeting the requirements of 9-29.13(10)A.d. 45 46 PDA components shall be mounted in or on the PDA such that they are 47 readily accessible, provide dead front safety, and all hazardous voltage 48 points are protected to prevent inadvertent contact. 49 50 8. Service Panel #1 shall include a service terminal block labeled “TBS”, a Tesco 51 TES-10B or equivalent surge suppressor connected to provide power in line 52 surge suppression, and a 1P-30A Main Breaker. The Service Panel Assembly 53 (SPA) shown in the TEES shall not be included. 54

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 103 1 9. Each cabinet shall include a rack mounted fiber optic patch panel of the type 2 specified in the Contract. 3 4 Cabinet drawings and wiring diagrams shall be provided in the drawer shelf. 5 Additionally, an electronic (PDF format) copy of all drawings and wiring diagrams shall 6 be provided. 7 8 9-29.16(1)A1 Conventional Optical System 9 This section’s title is revised to read: 10 11 9-29.16(1)A1 Non-LED Optical System 12 13 9-29.16(1)D1 Electrical - Conventional 14 This section’s title is revised to read: 15 16 9-29.16(1)D1 Electrical – Non-LED 17 18 9-29.20 Pedestrian Signals 19 This section is revised to read: 20 21 Pedestrian signals shall be Light Emitting Diods (LED) type. 22 23 The LED pedestrian signal module shall be operationally compatible with controllers 24 and conflict monitors. The LED lamp unit shall contain a disconnect that will show an 25 open switch to the conflict monitor when less than 60 percent of the LEDs in the unit are 26 operational. 27 28 The Pedestrian signal heads shall be on the QPL or the Contractor shall submit a 29 Manufacturer’s Certificate of Compliance, in accordance with Standard Specification 1- 30 06.3, with each type of signal head. The certificate shall state that the lot of pedestrian 31 signal heads meet the following requirements: 32 33 1. All pedestrian signal heads shall be a Walk/Don’t Walk module with a 34 countdown display. 35 36 2. All pedestrian displays shall comply with the MUTCD and ITE publication ST 37 011B, VTCSH2 or current ITE Specification and shall have an incandescent 38 appearance. The Contractor shall provide test results from a Nationally 39 Recognized Testing Laboratory documenting that the LED display conforms to 40 the current ITE and the following requirements: 41 42 a. All pedestrian signals supplied to any one project shall be from the same 43 manufacturer and type but need not be from the same manufacturer as 44 the vehicle heads. 45 46 b. Each pedestrian signal face shall be a single unit housing with the signal 47 indication size, a nominal 16 inch x 18 inch with side by side symbol 48 messages with countdown display. 49 50 c Housings shall be green polycarbonate or die-cast aluminum and the 51 aluminum housings shall be painted with two coats of factory applied 52 traffic signal green enamel (Federal Standard 595-14056). All hinges and 53 latches and interior hardware shall be stainless steel.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 104 1 2 3. Optical units for traffic signal displays shall conform to the following: 3 4 a. Pedestrian “RAISED HAND” and “WALKING PERSON” modules shall be 5 the countdown display type showing the time remaining in the pedestrian 6 change interval. When the pedestrian change interval is reduced due to a 7 programming change, the display may continue to show the previous 8 pedestrian change interval for one signal cycle. During the following 9 pedestrian change interval the countdown shall show the revised time, or 10 shall be blank. In the event of an emergency vehicle preemption, during 11 the following two cycles, the display shall show the programmed 12 pedestrian change interval or be blank. In the event the controller is put in 13 stop time during the pedestrian change interval, during the following two 14 cycles the display shall show the programmed clearance or be blank. In 15 the event there is railroad preempt during the pedestrian change interval, 16 during the following two cycles the display shall show the programmed 17 clearance or be blank. Light emitting diode (LED) light sources having the 18 incandescent appearance are required for Portland Orange Raised Hand 19 and the Lunar White Walking Person. 20 21 4. LED displays shall conform to the following: 22 23 a. Wattage (Maximum): Portland Orange Raised Hand, 15 watts: Lunar 24 White Walking Person, 15 watts. 25 26 b. Voltage: The operating voltages shall be between 85 VAC and 135 VAC. 27 28 c. Temperature: Temperature range shall be -35° F to +165° F. 29 30 d. LED pedestrian heads shall be supplied with Z crate visors. Z crate visors 31 shall have 21 members at 45 degrees and 20 horizontal members. 32 33 9-29.20(1) LED Pedestrian Displays 34 This section is deleted. 35 36 9-29.20(2) Neon Grid Type 37 This section is deleted. 38 39 9-29.24 Service Cabinets 40 In the first paragraph, the lettered items A-J are re-lettered to read B-K respectfully. 41 42 The first paragraph is supplemented with the following new lettered item: 43 44 A. Display an arc flash warning label that meets the requirements of ANSI Z535. 45 46 9-29.25 Amplifier, Transformer, and Terminal Cabinets 47 In item No. 2.C., “Transformer 23.1 to 12.5 KVA” is revised to read “Transformer 3.1 to 12.5 48 KVA” and the height column value of 40” is revised to read “48”. 49 50 The first and second sentences in the first paragraph are revised to read: 51 52 Amplifier and terminal and transformer cabinets shall be NEMA 3R and the following: 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 105 1 Item number 5 is revised to read: 2 3 5. All cabinets shall provide a gasketed door flange 4 5 Item number 7 is revised to read: 6 7 7. Insulated terminal blocks shall be 600 volt, heavy-duty, barrier type. The terminal 8 blocks shall be provided with a field-side and a control-side connector separated by 9 a marker strip. One spare 12-position insulated terminal block shall be installed in 10 each terminal cabinet and amplifier cabinet. 11 12 Item number 8 is revised to read: 13 14 8. Each non-pad mounted Terminal, Amplifier and Transformer cabinet shall have 1/4 15 inch drain holes in back corners. Each pad mounted Terminal, Amplifier and 16 Transformer cabinet shall drain to a sump and through a 3/8 inch diameter drain 17 pipe to grade as detailed in the Standard Plans. 18 19 Item number 10 is revised to read: 20 21 10. Transformer cabinets shall have two separate compartments, one for the 22 transformer and one for the power distribution circuit breakers. Each compartment 23 shall be enclosed with a dead front. Each breaker shall be labeled with the device 24 name by means of a screwed or riveted engraved name plate. 25 26 Section 9-34, Pavement Marking Material 27 August 5, 2013

28 9-34.2 Paint 29 The second paragraph is revised to read: 30 31 Blue and black paint shall comply with the requirements for yellow paint in Section 9- 32 34.2(4) and Section 9-34.2(5), with the exception that blue and black paints do not need 33 to meet the requirements for titanium dioxide, directional reflectance, and contrast 34 ration. 35 36 9-34.3(4) Type D – Liquid Cold Applied Methyl Metharcrylate 37 The column headings in the table titled “98:2 Formulations Type D – Liquid Cold Applied 38 Methyl Methacrylate” are revised to read: 39 98:2 Formulations Type D – Liquid Cold Applied Methyl Methacrylate Property D-1 D-2 D-3 D-4 D-5 D-6 Test Method Min. Max. Min. Max. Min. Max. Min. Max. Min. Max. Min. Max. 40 41 42 Section 9-36, Shaft-Related Materials 43 August 5, 2013

44 9-36.1(1) Permanent Casing 45 This section is revised to read: 46 47 Permanent casing shall be of steel base metal conforming to ASTM A 36, ASTM A 252 48 Grades 2 or 3, ASTM A 572, or ASTM A 588.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 106 1 2 SPECIAL PROVISIONS 3 4 The following Special Provisions are made a part of this contract and supersede any 5 conflicting provi sions of the 2012 Standard Specifications for Road, Bridge and Municipal 6 Construction and the foregoing Amendments to the Standard Specifications. 7 8 Several types of Special Provisions are included in this contract; General, Region, Bridges 9 and Structures, and Project Specific. Special Provisions types are differentiated as follows: 10 11 (date) General Special Provision 12 (******) Notes a revision to a General Special Provision 13 and also notes a Project Specific Special Provision. 14 (Regions1 date) Region Special Provision 15 (BSP date) Bridges and Structures Special Provision 16 (APWA GSP) Local Agency General Special Provision, which has been 17 approved by the APWA Div. 1 Subcommittee. 18 (date) Sk. Co. Skagit County General Special Provision 19 20 General Special Provisions are similar to Standard Specifications in that they typically 21 apply to many projects, usually in more than one Region. Usually, the only difference from 22 one project to another is the inclusion of variable project data, inserted as a “fill-in”. 23 24 Region Special Provisions are commonly applicable within the designated Region. Region 25 designations are as follows: 26 27 Regions1 28 NWR Northwest Region 29 WSF Washington State Ferries Division 30 31 Bridges and Structures Special Provisions are similar to Standard Specifications in that 32 they typically apply to many projects, usually in more than one Region. Usually, the only 33 difference from one project to another is the inclusion of variable project data, inserted as a 34 “fill-in”. 35 36 Project Specific Special Provisions normally appear only in the contract for which they 37 were developed. 38 39 Skagit County General Special Provisions are only applicable in Skagit County Public 40 Works contracts. 41 42 43

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 107 1 Division 1 2 General Requirements 3 4 DESCRIPTION OF WORK 5 6 (******) 7 This Contract provides for the construction of a street waste decant and disposal facility 8 within an existing incinerator building. The project includes demolition and replacement of a 9 portion of the existing tipping floor to create a decant settling area, installation of concrete 10 partition walls to separate decant dump areas from decant settling area, vertical extension of 11 the existing pit wall to form a concrete push wall at the rear of the decant dump and settling 12 areas, installation of a concrete sump and sump pump within the existing refuse pit, and 13 discharge piping connection to an existing wastewater manhole, extension of electrical 14 power to sump pump and control panel location, and installation of flow meter on the sump 15 discharge line, installation of accessory structures including chain link fence and an access 16 ladder, and other work, all in accordance with the attached Contract Plans, these Contract 17 Provisions, and the Standard Specifications. 18 19 1-01.3 Definitions 20 (March 8, 2013 APWA GSP) 21 22 Delete the heading Completion Dates and the three paragraphs that follow it, and replace 23 them with the following: 24 25 Dates 26 Bid Opening Date 27 The date on which the Contracting Agency publicly opens and reads the Bids. 28 Award Date 29 The date of the formal decision of the Contracting Agency to accept the lowest 30 responsible and responsive Bidder for the Work. 31 Contract Execution Date 32 The date the Contracting Agency officially binds the Agency to the Contract. 33 Notice to Proceed Date 34 The date stated in the Notice to Proceed on which the Contract time begins. 35 Substantial Completion Date 36 The day the Engineer determines the Contracting Agency has full and unrestricted 37 use and benefit of the facilities, both from the operational and safety standpoint, any 38 remaining traffic disruptions will be rare and brief, and only minor incidental work, 39 replacement of temporary substitute facilities, plant establishment periods, or 40 correction or repair remains for the Physical Completion of the total Contract. 41 Physical Completion Date 42 The day all of the Work is physically completed on the project. All documentation 43 required by the Contract and required by law does not necessarily need to be 44 furnished by the Contractor by this date. 45 Completion Date 46 The day all the Work specified in the Contract is completed and all the obligations of 47 the Contractor under the contract are fulfilled by the Contractor. All documentation 48 required by the Contract and required by law must be furnished by the Contractor 49 before establishment of this date. 50 Final Acceptance Date 51 The date on which the Contracting Agency accepts the Work as complete.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 108 1 2 Supplement this Section with the following: 3 4 All references in the Standard Specifications, Amendments, or WSDOT General Special 5 Provisions, to the terms “State”, “Department of Transportation”, “Washington State 6 Transportation Commission”, “Commission”, “Secretary of Transportation”, “Secretary”, 7 “Headquarters”, and “State Treasurer” shall be revised to read “Contracting Agency”. 8 9 All references to “State Materials Laboratory” shall be revised to read “Contracting 10 Agency designated location”. 11 12 All references to “final contract voucher certification” shall be interpreted to mean the 13 final payment form established by the Contracting Agency. 14 15 The venue of all causes of action arising from the advertisement, award, execution, and 16 performance of the contract shall be in the Superior Court of the County where the 17 Contracting Agency’s headquarters are located. 18 19 Additive 20 A supplemental unit of work or group of bid items, identified separately in the Bid 21 Proposal, which may, at the discretion of the Contracting Agency, be awarded in addition 22 to the base bid. 23 24 Alternate 25 One of two or more units of work or groups of bid items, identified separately in the Bid 26 Proposal, from which the Contracting Agency may make a choice between different 27 methods or material of construction for performing the same work. 28 29 Business Day 30 A business day is any day from Monday through Friday except holidays as listed in 31 Section 1-08.5. 32 33 Contract Bond 34 The definition in the Standard Specifications for “Contract Bond” applies to whatever 35 bond form(s) are required by the Contract Documents, which may be a combination of a 36 Payment Bond and a Performance Bond. 37 38 Contract Documents 39 See definition for “Contract”. 40 41 Contract Time 42 The period of time established by the terms and conditions of the Contract within which 43 the Work must be physically completed. 44 45 Notice of Award 46 The written notice from the Contracting Agency to the successful Bidder signifying the 47 Contracting Agency’s acceptance of the Bid Proposal. 48 49 Notice to Proceed 50 The written notice from the Contracting Agency or Engineer to the Contractor authorizing 51 and directing the Contractor to proceed with the Work and establishing the date on which 52 the Contract time begins. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 109 1 Traffic 2 Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and 3 equestrian traffic. 4 5 1-02 BID PROCEDURES AND CONDITIONS

6 1-02.1 Prequalification of Bidders 7 8 Delete this Section and replace it with the following: 9 10 1-02.1 Qualifications of Bidder 11 (January 24, 2011 APWA GSP) 12 13 Before award of a public works contract, a bidder must meet at least the minimum 14 qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified 15 to be awarded a public works project. 16 17 1-02.2 Plans and Specifications 18 (June 27, 2011 APWA GSP) 19 20 Delete Section 1-02.2 and replace it with the following: 21 22 Information as to where Bid Documents can be obtained or reviewed can be found in the 23 Call for Bids (Advertisement for Bids) for the work. 24 25 After award of the contract, plans and specifications will be issued to the Contractor at no 26 cost as detailed below: 27 To Prime Contractor No. of Sets Basis of Distribution Reduced plans (11" x 17") 6 Furnished automatically upon award. Contract Provisions 6 Furnished automatically upon award.

Large plans (e.g., 22" x 34") 3 Furnished only upon request.

28 29 Additional plans and Contract Provisions may be obtained by the Contractor from the 30 source stated in the Call for Bids, at the Contractor’s own expense. 31

32 1-02.6 Preparation Of Proposal 33 34 Section 1-02.6 is supplemented with the following: 35 36 (August 2, 2004) 37 The fifth and sixth paragraphs of Section 1-02.6 are deleted. 38 39

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 110 1 1-02.9 Delivery of Proposal 2 (5/15/13) Sk. Co. 3 4 Delete Section 1-02.9 and replace it with the following: 5 6 Each proposal shall be submitted in a sealed envelope, with the Project Name and 7 Project Number as stated in the Call for Bids clearly marked on the outside of the 8 envelope, or as otherwise required in the Bid Documents, to ensure proper handling 9 and delivery. 10 11 The Contracting Agency will not open or consider any Bid Proposal that is received after 12 the time specified in the Call for Bids for receipt of Bid Proposals, or received in a 13 location other than that specified in the Call for Bids. 14 15 1-02.12 Public Opening Of Proposal 16 (10/27/10) Sk. Co. 17 18 Section 1-02.12 is supplemented with the following: 19 20 Sealed bids shall be received at the time and location specified in the call for bids, 21 unless modified by addenda. 22 23 1-02.13 Irregular Proposals 24 (March 13, 2012 APWA GSP) 25 26 Revise item 1 to read: 27 28 1. A proposal will be considered irregular and will be rejected if: 29 a. The Bidder is not prequalified when so required; 30 b. The authorized proposal form furnished by the Contracting Agency is not 31 used or is altered; 32 c. The completed proposal form contains any unauthorized additions, deletions, 33 alternate Bids, or conditions; 34 d. The Bidder adds provisions reserving the right to reject or accept the award, 35 or enter into the Contract; 36 e. A price per unit cannot be determined from the Bid Proposal; 37 f. The Proposal form is not properly executed; 38 g. The Bidder fails to submit or properly complete a Subcontractor list, if 39 applicable, as required in Section 1-02.6; 40 h. The Bidder fails to submit or properly complete a Disadvantaged Business 41 Enterprise Certification, if applicable, as required in Section 1-02.6; 42 i. The Bidder fails to submit written confirmation from each DBE firm listed on 43 the Bidder’s completed DBE Utilization Certification that they are in 44 agreement with the bidders DBE participation commitment, if applicable, as 45 required in Section 1-02.6, or if the written confirmation that is submitted fails 46 to meet the requirements of the Special Provisions; 47 j The Bidder fails to submit DBE Good Faith Effort documentation, if applicable, 48 as required in Section 1-02.6, or if the documentation that is submitted fails to 49 demonstrate that a Good Faith Effort to meet the Condition of Award was 50 made; 51 k. The Bid Proposal does not constitute a definite and unqualified offer to meet 52 the material terms of the Bid invitation; or

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 111 1 l. More than one proposal is submitted for the same project from a Bidder under 2 the same or different names. 3 4 1-02.14 Disqualification of Bidders 5 (March 8, 2013 APWA GSP, Option B) 6 7 Delete this Section and replace it with the following: 8 9 A Bidder will be deemed not responsible if the Bidder does not meet the mandatory 10 bidder responsibility criteria in RCW 39.04.350(1), as amended; or does not meet the 11 following Supplemental Criteria: 12 13 1. Delinquent State Taxes 14 15 A Criterion: The Bidder shall not owe delinquent taxes to the Washington 16 State Department of Revenue without a payment plan approved by the 17 Department of Revenue. 18 19 B. Documentation: The Bidder shall not be listed on the Washington State 20 Department of Revenue’s “Delinquent Taxpayer List” website: 21 http://dor.wa.gov/content/fileandpaytaxes/latefiling/dtlwest.aspx , or if they 22 are so listed, they must submit a written payment plan approved by the 23 Department of Revenue, to the Contracting Agency by the deadline listed 24 below. 25 26 2. Federal Debarment 27 28 A Criterion: The Bidder shall not currently be debarred or suspended by the 29 Federal government. 30 31 B. Documentation: The Bidder shall not be listed as having an “active 32 exclusion” on the U.S. government’s “System for Award Management” 33 database (www.sam.gov). 34 35 3. Subcontractor Responsibility 36 37 A Criterion: The Bidder’s standard subcontract form shall include the 38 subcontractor responsibility language required by RCW 39.06.020, and the 39 Bidder shall have an established procedure which it utilizes to validate the 40 responsibility of each of its subcontractors. The Bidder’s subcontract form 41 shall also include a requirement that each of its subcontractors shall have 42 and document a similar procedure to determine whether the sub-tier 43 subcontractors with whom it contracts are also “responsible” subcontractors 44 as defined by RCW 39.06.020. 45 46 B. Documentation: The Bidder, if and when required as detailed below, shall 47 submit a copy of its standard subcontract form for review by the Contracting 48 Agency, and a written description of its procedure for validating the 49 responsibility of subcontractors with which it contracts. 50

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 112 1 4. Prevailing Wages 2 3 A Criterion: The Bidder shall not have a record of prevailing wage violations 4 as determined by WA Labor & Industries in the five years prior to the bid 5 submittal date, that demonstrates a pattern of failing to pay workers 6 prevailing wages, unless there are extenuating circumstances and such 7 circumstances are deemed acceptable to the Contracting Agency. 8 9 B. Documentation: The Bidder, if and when required as detailed below, shall 10 submit a list of all prevailing wage violations in the five years prior to the bid 11 submittal date, along with an explanation of each violation and how it was 12 resolved. The Contracting Agency will evaluate these explanations and the 13 resolution of each complaint to determine whether the violation demonstrate 14 a pattern of failing to pay its workers prevailing wages as required. 15 16 5. Claims Against Retainage and Bonds 17 18 A Criterion: The Bidder shall not have a record of excessive claims filed 19 against the retainage or payment bonds for public works projects in the 20 three years prior to the bid submittal date, that demonstrate a lack of 21 effective management by the Bidder of making timely and appropriate 22 payments to its subcontractors, suppliers, and workers, unless there are 23 extenuating circumstances and such circumstances are deemed acceptable 24 to the Contracting Agency. 25 26 B. Documentation: The Bidder, if and when required as detailed below, shall 27 submit a list of the public works projects completed in the three years prior 28 to the bid submittal date that have had claims against retainage and bonds 29 and include for each project the following information: 30 31 • Name of project 32 • The owner and contact information for the owner; 33 • A list of claims filed against the retainage and/or payment bond for 34 any of the projects listed; 35 • A written explanation of the circumstances surrounding each claim 36 and the ultimate resolution of the claim. 37 38 6. Public Bidding Crime 39 40 A Criterion: The Bidder and/or its owners shall not have been convicted of a 41 crime involving bidding on a public works contract in the five years prior to 42 the bid submittal date. 43 44 B. Documentation: The Bidder, if and when required as detailed below, shall 45 sign a statement (on a form to be provided by the Contracting Agency) that 46 the Bidder and/or its owners have not been convicted of a crime involving 47 bidding on a public works contract. 48 49 7. Termination for Cause / Termination for Default 50 51 A Criterion: The Bidder shall not have had any public works contract 52 terminated for cause or terminated for default by a government agency in 53 the five years prior to the bid submittal date, unless there are extenuating

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 113 1 circumstances and such circumstances are deemed acceptable to the 2 Contracting Agency. 3 4 B. Documentation: The Bidder, if and when required as detailed below, shall 5 sign a statement (on a form to be provided by the Contracting Agency) that 6 the Bidder has not had any public works contract terminated for cause or 7 terminated for default by a government agency in the five years prior to the 8 bid submittal date; or if Bidder was terminated, describe the circumstances. 9 10 8. Lawsuits 11 12 A Criterion: The Bidder shall not have lawsuits with judgments entered against 13 the Bidder in the five years prior to the bid submittal date that demonstrate a 14 pattern of failing to meet the terms of contracts, unless there are 15 extenuating circumstances and such circumstances are deemed acceptable 16 to the Contracting Agency 17 18 B. Documentation: The Bidder, if and when required as detailed below, shall 19 sign a statement (on a form to be provided by the Contracting Agency) that 20 the Bidder has not had any lawsuits with judgments entered against the 21 Bidder in the five years prior to the bid submittal date that demonstrate a 22 pattern of failing to meet the terms of contracts, or shall submit a list of all 23 lawsuits with judgments entered against the Bidder in the five years prior to 24 the bid submittal date, along with a written explanation of the circumstances 25 surrounding each such lawsuit. The Contracting Agency shall evaluate 26 these explanations to determine whether the lawsuits demonstrate a pattern 27 of failing to meet of terms of construction related contracts 28 29 As evidence that the Bidder meets the mandatory and supplemental responsibility 30 criteria stated above, the apparent two lowest Bidders must submit to the Contracting 31 Agency by 12:00 P.M. (noon) of the second business day following the bid submittal 32 deadline, a written statement verifying that the Bidder meets all of the mandatory and 33 supplemental criteria together with supporting documentation including but not limited 34 to that detailed above (sufficient in the sole judgment of the Contracting Agency) 35 demonstrating compliance with all mandatory and supplemental responsibility criteria. 36 The Contracting Agency reserves the right to request such documentation from other 37 Bidders as well, and to request further documentation as needed to assess Bidder 38 responsibility. The Contracting Agency also reserves the right to obtain information 39 from third-parties and independent sources of information concerning a Bidder’s 40 compliance with the mandatory and supplemental criteria, and to use that information 41 in their evaluation. The Contracting Agency may (but is not required to) consider 42 mitigating factors in determining whether the Bidder complies with the requirements of 43 the supplemental criteria. 44 45 The basis for evaluation of Bidder compliance with these mandatory and supplemental 46 criteria shall include any documents or facts obtained by Contracting Agency (whether 47 from the Bidder or third parties) including but not limited to: (i) financial, historical, or 48 operational data from the Bidder; (ii) information obtained directly by the Contracting 49 Agency from others for whom the Bidder has worked, or other public agencies or 50 private enterprises; and (iii) any additional information obtained by the Contracting 51 Agency which is believed to be relevant to the matter. 52 53 If the Contracting Agency determines the Bidder does not meet the bidder 54 responsibility criteria above and is therefore not a responsible Bidder, the Contracting

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 114 1 Agency shall notify the Bidder in writing, with the reasons for its determination. If the 2 Bidder disagrees with this determination, it may appeal the determination within two (2) 3 business days of the Contracting Agency’s determination by presenting its appeal and 4 any additional information to the Contracting Agency. The Contracting Agency will 5 consider the appeal and any additional information before issuing its final 6 determination. If the final determination affirms that the Bidder is not responsible, the 7 Contracting Agency will not execute a contract with any other Bidder until at least two 8 business days after the Bidder determined to be not responsible has received the 9 Contracting Agency’s final determination. 10 11 Request to Change Supplemental Bidder Responsibility Criteria Prior To Bid: Bidders 12 with concerns about the relevancy or restrictiveness of the Supplemental Bidder 13 Responsibility Criteria may make or submit requests to the Contracting Agency to 14 modify the criteria. Such requests shall be in writing, describe the nature of the 15 concerns, and propose specific modifications to the criteria. Bidders shall submit such 16 requests to the Contracting Agency no later than five (5) business days prior to the bid 17 submittal deadline and address the request to the Project Engineer or such other 18 person designated by the Contracting Agency in the Bid Documents. 19 20 1-03 AWARD AND EXECUTION OF CONTRACT 21 22 Add the following new section: 23 24 1-03.5 Department of Ecology Funding Clauses 25 (******) 26 27 It is anticipated that this project will be funded in part by the Washington State Department of 28 Ecology. Neither the State of Washington nor any of its departments or employees are, or 29 shall be, a party to any contract or any subcontract resulting from this solicitation for bids.

30 Third-Party Beneficiary: All parties agree that the State of Washington shall be, and is 31 hereby, named as an express third-party beneficiary of this contract, with full rights as such.

32 Protection of the Environment: No construction related activity shall contribute to the 33 degradation of the environment, allow material to enter surface or ground waters, or allow 34 particulate emissions to the atmosphere, which exceed state or federal standards. Any 35 actions that potentially allow a discharge to state waters must have prior approval of the 36 Washington State Department of Ecology.

37 A Construction Quality Assurance Plan (CQAP) will be provided to the Contractor prior to the 38 start of construction. The Contractor will be responsible for providing the key personnel 39 contact information and Type A progress schedule to finalize the draft CQAP, and for 40 following the CQAP throughout construction. The CQAP is included in Appendix G of these 41 Special Provisions. All costs associated with the CQAP shall be incidental to the various bid 42 items.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 115 1 1-04 Scope of the Work

2 1-04.2 Coordination of Contract Documents, Plans, Special Provisions, 3 Specifications, and Addenda 4 (March 13, 2012 APWA GSP) 5 6 Revise the second paragraph to read: 7 8 Any inconsistency in the parts of the contract shall be resolved by following this order of 9 precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth): 10 1. Addenda, 11 2. Proposal Form, 12 3. Special Provisions, 13 4. Contract Plans, 14 5. Amendments to the Standard Specifications, 15 6. Standard Specifications, 16 7. Contracting Agency’s Standard Plans or Details (if any), and 17 8. WSDOT Standard Plans for Road, Bridge, and Municipal Construction. 18 19 1-05 Control of Work

20 Conformity With And Deviations From Plans And Stakes 21 22 Section 1-05.4 is supplemented with the following: 23 24 (******) 25 Contractor Surveying - Structure 26 27 The Contractor shall be responsible for setting, maintaining, and resetting all alignment 28 stakes, slope stakes, and grades necessary for the construction of the street waste 29 facility. Calculations, surveying, and measuring required for setting and maintaining the 30 necessary lines and grades shall be the Contractor's responsibility. 31 32 The Contractor shall inform the Engineer when monuments are discovered that were 33 not identified in the Plans and construction activity may disturb or damage the 34 monuments. All monuments noted on the plans “DO NOT DISTURB” shall be protected 35 throughout the length of the project or be replaced at the Contractors expense. 36 37 Detailed survey records shall be maintained, including a description of the work 38 performed on each shift, the methods utilized, and the control points used. The record 39 shall be adequate to allow the survey to be reproduced. A copy of each day's record 40 shall be provided to the Engineer within three working days after the end of the shift. 41 42 The meaning of words and terms used in this provision shall be as listed in "Definitions 43 of Surveying and Associated Terms" current edition, published by the American 44 Congress on Surveying and Mapping and the American Society of Civil Engineers. 45 46 The survey work by the Contractor shall include but not be limited to the following: 47 48 49

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 116 1 1. Establish, by placing hubs and/or marked stakes, the location with offsets of 2 foundations. 3 4 2. Establish offsets to footing corners for structure excavation. 5 6 3. Establish offsets to footing corners for footing forms. 7 8 4. Establish top of wall profile grade. 9 10 5. Check elevations at top of footing concrete line inside footing formwork 11 immediately prior to concrete placement. 12 13 6. Establish slab alignment, grades and provide dimensions. Set elevations for 14 concrete slabs. 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 117 1 The Contractor shall provide the Contracting Agency copies of any calculations and 2 staking data when requested by the Engineer. 3 4 The Contracting Agency may spot-check the Contractor's surveying. These spot- 5 checks will not change the requirements for normal checking by the Contractor. 6 7 The Contractor shall calculate coordinates for the points associated with slabs, walls, 8 footings and sump elevations, and drainage structures. The Contracting Agency may 9 verify these coordinates prior to issuing approval to the Contractor for commencing with 10 the survey work. The Contracting Agency will require up to seven calendar days from 11 the date the data is received to issuing approval. 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 118 1 Contract work to be performed using contractor-provided stakes shall not begin until the 2 stakes are approved by the Contracting Agency. Such approval shall not relieve the 3 Contractor of responsibility for the accuracy of the stakes. 4 5 Payment 6 All costs for all labor, equipment, materials, and supervision utilized to perform the Work 7 Specified, including any resurveying, checking, correction of errors, replacement of 8 missing or damaged stakes, and coordination efforts will be incidental to the various bid 9 items. 10 11 1-05.13 Superintendents, Labor and Equipment of Contractor 12 (August 14, 2013 APWA GSP) 13 14 Delete the sixth and seventh paragraphs of this section. 15 16 1-05.15 Method of Serving Notices 17 (March 25, 2009 APWA GSP)

18 Revise the second paragraph to read: 19 20 All correspondence from the Contractor shall be directed to the Project Engineer. All 21 correspondence from the Contractor constituting any notification, notice of protest, notice 22 of dispute, or other correspondence constituting notification required to be furnished 23 under the Contract, must be in paper format, hand delivered or sent via mail delivery 24 service to the Project Engineer's office. Electronic copies such as e-mails or 25 electronically delivered copies of correspondence will not constitute such notice and will 26 not comply with the requirements of the Contract. 27 28 Add the following new section: 29 30 1-05.16 Water and Power 31 (******) 32 33 The contractor may obtain 110-V power from the following sources on site, in coordination 34 with the Engineer: 35 • Receptacles on the south and east walls of the compactor bay within the existing 36 incinerator building. 37 • Receptacles on the south wall of the boiler room, which is located directly behind the 38 compactor hydraulic power source. 39 40 The Contractor shall make necessary arrangements, and shall bear the costs for all other 41 power and water necessary for the performance of the work. 42 43 Add the following new section: 44 45 1-05.17 Oral Agreements 46 (October 1, 2005 AWPA GSP) 47 48 No oral agreement or conversation with any officer, agent, or employee of the Contracting 49 Agency, either before or after execution of the contract, shall affect or modify any of the 50 terms or obligations contained in any of the documents comprising the contract. Such oral 51 agreement or conversation shall be considered as unofficial information and in no way

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 119 1 binding upon the Contracting Agency, unless subsequently put in writing and signed by the 2 Contracting Agency. 3 4 1-06 CONTROL OF MATERIAL

5 1-06.1 Approval of Materials Prior to Use 6 (******) 7 8 Section 1-06.1 is supplemented with the following: 9 10 The Contractor shall prepare submittals for the following materials, to be approved by 11 the Engineer prior to construction: 12 • Asphalt mix design 13 • Tack coat 14 • Concrete mix design 15 • Crushed surfacing top course 16 • Pipe bedding and backfill 17 • Sump pump product data 18 • Float switches and control 19 • Flow meter product data 20 • Electrical conduit 21 • Electrical cable 22 • Galvanized pipe for sump 23 • Schedule 80 PVC pipe and fittings 24 • Weir boards and angle guides 25 • Oil absorbent boom 26 • PVC ball valve and operating nut 27 • FRP grating 28 • Guardrail 29 • Access ladder 30 • Chain link fence and gate 31 32 This list is provided as a convenience to the Contractor and does not relieve the 33 Contractor of the responsibility to make other submittals required by the Contract 34 Documents which are not included in this list. 35 36 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC

37 1-07.2 State Taxes 38 39 Section 1-07.2 is supplemented with the following: 40 41 (March 13, 1995) 42 The work on this contract is to be performed upon lands whose ownership obligates the 43 Contractor to collect State sales tax from the Contracting Agency. The provisions of 44 Section 1-07.2(2) apply. 45 46

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 120 1 1-07.6 Permits And Licenses 2 3 Section 1-07.6 is supplemented with the following: 4 5 (******) 6 It is not anticipated that any permits held by the Contracting Agency for this project will 7 impact the Contractor’s operations. All contacts with the permitting agency concerning 8 the permit(s) held by the County shall be through the Engineer. 9 10 No building permit is required for this project. The Contractor shall obtain additional 11 permits as necessary, and keep copies on site as required. All costs to obtain and 12 comply with additional permits shall be included in the applicable bid items for the work 13 involved. 14 15 1-07.7 Load Limits 16 17 Section 1-07.7 is supplemented with the following: 18 19 (March 13, 1995) 20 If the sources of materials provided by the Contractor necessitates hauling over roads 21 other than State Highways, the Contractor shall, at the Contractor's expense, make all 22 arrangements for the use of the haul routes. 23 24 1-07.13 Contractor's Responsibility for Work 25 26 Repair of Damage 27 28 Section 1-07.13(4) is revised to read: 29 30 (August 6, 2001) 31 The Contractor shall promptly repair all damage to either temporary or permanent 32 work as directed by the Engineer. For damage qualifying for relief under Sections 1- 33 07.13(1), 1-07.13(2) or 1-07.13(3), payment will be made in accordance with 34 Section 1-04.4. Payment will be limited to repair of damaged work only. No 35 payment will be made for delay or disruption of work. 36 37 1-07.17 Utilities and Similar Facilities 38 39 Section 1-07.17 is supplemented with the following: 40 41 (******) 42 Locations and dimensions shown in the Plans for existing facilities are in accordance 43 with available information obtained without uncovering, measuring, or other verification. 44 45 No utility companies are known or suspected of having facilities within the project limits. 46 47 The Contractor shall provide the Contracting Agency with surveyed as-built information 48 (location and burial depth) for all utilities that are installed as part of this project. 49 50 1-07.18 Public Liability and Property Damage Insurance 51 52 (January 5, 2004) 53 Item number 1 in the first paragraph of Section 1-07.18 is deleted.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 121 1 2 Item number 2 of the first paragraph of Section 1-07.18 is revised to read: 3 4 (January 3, 2011) 5 2. Commercial General Liability (GCL) Insurance written under ISO Form CG0001 or 6 its equivalent with minimum limits of $1,000,000 per occurrence and in the 7 aggregate for each one year policy period. Products and completed operations 8 coverage shall be provided for a period of three years following Substantial 9 Completion of the work. 10 11 Public Convenience and Safety 12 13 Section 1-07.23 is supplemented with the following: 14 15 (******) 16 During the Contractor’s operations the Contractor shall take any and all measures 17 required to ensure the safety of the public and the employees of the site, including any 18 traffic control, pedestrian control, security fencing, or any other measures required. Any 19 costs associated with this work shall be incidental to the various bid items in the 20 contract. 21 22 1-08 PROSECUTION AND PROGRESS 23 24 Add the following new section: 25 26 1-08.0 Preliminary Matters 27 (May 25, 2006 APWA GSP) 28 29 1-08.0(1) Preconstruction Conference 30 (******) 31 32 Prior to the Contractor beginning the work, a preconstruction conference will be held 33 between the Contractor, the Engineer and such other interested parties as may be 34 invited. The purpose of the preconstruction conference will be: 35 36 1. To review the initial progress schedule; 37 2. To establish a working understanding among the various parties associated or 38 affected by the work; 39 3. To establish and review procedures for progress payment, notifications, approvals, 40 submittals, etc.; 41 4. To establish working hours for the work; 42 5. To establish site access routes for the Contractor; 43 6. To review safety standards and traffic control; and 44 7. To discuss such other related items as may be pertinent to the work. 45 46 The Contractor shall prepare and submit at the preconstruction meeting the following: 47 48 1. A breakdown of all lump sum items 49 2. A preliminary schedule of working drawing submittals 50 3. A list of material sources for approval if applicable 51 4. A list of emergency contacts 52 5. Traffic Control Plan 53 6. Water Diversion/Dewatering Plan

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 122 1 7. Utility coordination communication 2 8. Construction Waste Management Plan 3 9. Spill Prevention Control and Countermeasures Plan, per WSDOT 1-07.15(1) 4 10. Key contacts list and Type A progress schedule for the CQAP, per SP 1-03.5 5 6 1-08.4 Prosecution of Work 7 8 Delete this section in its entirety, and replace it with the following: 9 10 1-08.4 Notice to Proceed and Prosecution of Work 11 (June 27, 2011 APWA GSP) 12 13 Notice to Proceed will be given after the Contract has been executed and the contract 14 bond and evidence of insurance have been approved and filed by the Contracting 15 Agency. The Contractor shall not commence with the work until the Notice to Proceed 16 has been given by the Engineer. The Contractor shall commence construction activities 17 on the project site within ten days of the Notice to Proceed Date, unless otherwise 18 approved in writing. The Contractor shall diligently pursue the work to the physical 19 completion date within the time specified in the Contract. Voluntary shutdown or slowing 20 of operations by the Contractor shall not relieve the Contractor of the responsibility to 21 complete the work within the time(s) specified in the Contract. 22 23 When shown in the Plans, the first order of work shall be the installation of high visibility 24 fencing to delineate all areas for protection or restoration, as described in the Contract. 25 Installation of high visibility fencing adjacent to the roadway shall occur after the 26 placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). 27 Upon construction of the fencing, the Contractor shall request the Engineer to inspect the 28 fence. No other work shall be performed on the site until the Contracting Agency has 29 accepted the installation of high visibility fencing, as described in the Contract. 30 31 1-08.5 Time for Completion 32 (11/4/10) Sk. Co. 33 34 Revise the third paragraph of Section 1-08.5 to read: 35 36 Contract time shall begin on the tenth working day following the Notice to Proceed Date. 37 If the Contractor starts Work on the project at an earlier date, then Contract time shall 38 begin on the first working day when onsite Work begins. 39 40 Section 1-08.5 is supplemented with the following: 41 42 (March 13, 1995) 43 This project shall be physically completed within ***40 *** working days. 44

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 123 1 1-09 MEASUREMENT AND PAYMENT

2 1-09.6 Force Account 3 (10/17/12) Sk. Co. 4 5 Section 1-09.6 is supplemented with the following: 6 7 Payment for unanticipated work performed during construction shall be made using the 8 estimated Bid item “Unanticipated Site Work”. Measurement and payment will be made 9 in accordance with Section 1-09.6. 10 11 (October 10, 2008 APWA GSP) 12 13 Supplement this section with the following: 14 15 The Contracting Agency has estimated and included in the Proposal, dollar amounts for 16 all items to be paid per force account, only to provide a common proposal for Bidders. All 17 such dollar amounts are to become a part of Contractor's total bid. However, the 18 Contracting Agency does not warrant expressly or by implication, that the actual amount 19 of work will correspond with those estimates. Payment will be made on the basis of the 20 amount of work actually authorized by Engineer. 21 22 1-09.13 Claims Resolution 23 24 1-09.13(3) Claims $250,000 or Less 25 (October 1, 2005 APWA GSP) 26 27 Delete this Section and replace it with the following: 28 29 The Contractor and the Contracting Agency mutually agree that those claims that 30 total $250,000 or less, submitted in accordance with Section 1-09.11 and not 31 resolved by nonbinding ADR processes, shall be resolved through litigation unless 32 the parties mutually agree in writing to resolve the claim through binding arbitration. 33 34 1-09.13(3)A Administration of Arbitration 35 (October 1, 2005 APWA GSP) 36 37 Revise the third paragraph to read: 38 39 The Contracting Agency and the Contractor mutually agree to be bound by the 40 decision of the arbitrator, and judgment upon the award rendered by the 41 arbitrator may be entered in the Superior Court of the county in which the 42 Contracting Agency’s headquarters are located. The decision of the arbitrator 43 and the specific basis for the decision shall be in writing. The arbitrator shall 44 use the contract as a basis for decisions. 45

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 124 1 Division 2 2 Earthwork 3 4 2-02 Removal of Structures and Obstructions

5 2-02.1 Description 6 7 (******) 8 Supplement 2-02.1 with the following: 9 10 The following items shall be removed and disposed of off the project site in accordance 11 with the requirements of Section 2-02: 12 13 1. Concrete bollards – 4 each 14 2. Concrete floor slab – 980 SF 15 3. Asphalt pavement – 342 SF 16 17 The removal and disposal item quantities included above are to be included in the 18 lump sum bid price for “Removal of Structures and Obstructions”. They are estimates 19 only, and are provided for Contractor convenience as a basis of bid. 20 21 2-02.3 Construction Requirements 22 23 2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters 24 25 Section 2-02.3(3) is supplemented with the following: 26 27 (******) 28 Pavement shall be saw cut in such a fashion as to form a neat break line. Saw 29 cutting is incidental to the bid item involved. 30 31 (September 8, 1997) 32 The approximate thickness of the *** existing asphalt *** pavement is *** 8 to 12 33 inches *** and the approximate thickness of the *** existing concrete floor slab *** is 34 *** 10 inches ***. 35 36 2-02.5 Payment 37 38 (******) 39 All costs for sawcutting shall be incidental to the lump sum Contract price for “Removal 40 of Structures and Obstructions”. 41 42

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 125 1 Division 3 2 Aggregate Production and Acceptance 3 4 3-04 Acceptance of Aggregates

5 (11/28/12) Sk. Co. 6 7 Section 3-04 is deleted in its entirety and replaced with the following: 8 9 3-04.1 Description 10 11 There will be no price adjustments for aggregates. Aggregates having all constituents falling 12 within the specification limits and meeting all other requirements of the standard 13 specifications, these specifications, and the plans shall be accepted at the unit contract 14 price. 15 16 3-04.2 Rejected Work 17 18 3-04.2(1) General 19 20 Work that is defective or does not conform to Contract requirements shall be rejected. 21 Any material rejected by the Contractor or the Agency shall not be paid for and shall be 22 removed and disposed of by the Contractor at no expense to the Contracting Agency. 23 24 3-04.2(2) Rejection by Contractor 25 26 The Contractor may, prior to sampling, elect to remove any defective material and 27 replace it with new material. Any such new material will be sampled, tested, and 28 evaluated for acceptance. 29 30 3-04.2(3) Rejection Without Testing 31 32 The Project Engineer may, without sampling, reject any load or stockpile that appears 33 defective. Material rejected before placement shall not be incorporated into the work. 34 Any rejected work shall be removed. 35 36 No payment will be made for the rejected material unless the Contractor requests that 37 the rejected material be tested. If the Contractor elects to have the rejected material 38 tested, a representative sample shall be obtained and tested by the Engineer. If the 39 rejected material fails the test, no payment will be made for the rejected material; in 40 addition, the cost of sampling and testing shall be borne by the Contractor. If the 41 rejected material passes the test, the material will be considered accepted and shall be 42 paid for at the unit bid price; in addition, all costs for sampling and testing shall be borne 43 by the Contracting Agency. 44 45

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 126 1 Division 4 2 Bases 3 4 4-02 Gravel Base 5 (******) 6 7 4-02.2 Materials 8 Section 4-02.2 is revised to read: 9 10 Materials shall meet the requirements of these Special Provisions and the following 11 section. 12 13 Gravel Base 9-03.10 14 15 4-02.3 Construction Requirements 16 Section 4-02.3 is supplemented with the following: 17 18 The Contractor shall use the “Road Mix Method” for mixing, placing and spreading 19 gravel base, as outlined in Sections 4-04.3(3)2 and 4-04.3(4)2. 20 21 4-04 Ballast and Crushed Surfacing 22 (******) 23 . 24 4-04.2 Materials 25 26 Section 4-04.2, delete the first sentence and replace with the following: 27 28 Materials shall meet the requirements of these Special Provisions and the following 29 sections: 30 31 Ballast 9-03.9(1) 32 Permeable Ballast 9-03.9(2) 33 Crushed Surfacing 9-03.9(3) 34 Maintenance Rock 9-03.9(4) 35 36 4-04.3 Construction Requirements 37 38 Section 4-04.3 is supplemented with the following: 39 40 The Contractor shall use the “Road Mix Method” for mixing, placing and spreading 41 crushed surfacing, as outlined in Sections 4-04.3(3)2 and 4-04.3(4)2 of the Standard 42 Specifications.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 127 1 Division 5 2 Surface Treatments and Pavements 3 4 5-01 CEMENT CONCRETE PAVEMENT REHABILITATION 5 6 Construction Requirements 7 8 Material Acceptance 9 10 5-01.3(2)B Portland Cement Concrete 11 12 (******) 13 The fifth sentence in the third paragraph is revised to read: 14 15 The compressive strength shall be as stated in Structural Specification Section 16 033000. 17 18 5-04 Hot Mix Asphalt 19 20 Construction Requirements 21 22 Hot Mix Asphalt Pavers 23 24 Material Transfer Device/Vehicle 25 26 (August 3, 2009) 27 Section 5-04.3(3)A is deleted in its entirety. 28 29 Conditioning of Existing Surface 30 31 (4/24/13) Sk. Co. 32 Preparation of Existing Surfaces 33 34 Section 5-04.3(5)A is revised as follows: 35 36 The third sentence of the first paragraph of Section 5-04.3(5)A is revised to 37 read: 38 39 All pavements, bituminous surfaces, concrete surfaces, and shoulders 40 shall be thoroughly cleaned of dust, soil, plant or organic material, 41 pavement grindings, and other foreign matter. 42 43 44

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 128 1 Preparation of Aggregates 2 3 Mix Design 4 (November 20, 2013 APWA GSP) 5 6 Statistical or Nonstatistical Evaluation 7 8 Delete Section 5-04.3(7)A2 and replace it with the following; 9 10 Mix designs for HMA accepted by Nonstatistical or Commercial evaluation 11 shall; 12 • Be submitted to the Project Engineer on WSDOT Form 350-042 13 • Have the aggregate structure and asphalt binder content 14 determined in accordance with WSDOT Standard Operating 15 Procedure 732 and meet the requirements of Sections 9-03.8(2) 16 and 9-03.8(6). 17 • Have anti-strip requirements, if any, for the proposed mix design 18 determined in accordance with WSDOT Test Method T 718 or 19 based on historic anti-strip and aggregate source compatibility 20 from WSDOT lab testing. Anti-strip evaluation of HMA mix designs 21 utilized that include RAP will be completed without the inclusion of 22 the RAP. 23 24 At or prior to the preconstruction meeting, the contractor shall provide one 25 of the following mix design verification certifications for Contracting 26 Agency review; 27 • The proposed mix design indicated on a WSDOT mix design/anti- 28 strip report that is within one year of the approval date 29 • The proposed HMA mix design submittal (Form 350-042) with the 30 seal and certification (stamp & signature) of a valid licensed 31 Washington State Professional Engineer. 32 • The proposed mix design by a qualified City or County laboratory 33 mix design report that is within one year of the approval date. 34 35 The mix design will be performed by a lab accredited by a national 36 authority such as Laboratory Accreditation Bureau, L-A-B for Construction 37 Materials Testing, The Construction Materials Engineering Council 38 (CMEC’s) ISO 17025 or AASHTO Accreditation Program (AAP) and shall 39 supply evidence of participation in the AASHTO Material Reference 40 Laboratory (AMRL) program. 41 42 At the discretion of the Engineer, agencies may accept mix designs 43 verified beyond the one year verification period with a certification from the 44 Contractor that the materials and sources are the same as those shown 45 on the original mix design. 46 47 Evaluation of anti-strip additives are to be provided as part of the mix 48 design acceptance criteria. Acceptable anti-strip evaluations include 1.) a 49 WSDOT validated mix design showing the validated anti-strip additive and 50 dosage 2.) an historic anti-strip determination from WSDOT not greater 51 than two (2) calendar years old or 3.) a passing TSR test at the anti-strip 52 dosage proposed by the Contractor. 53

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 129 1 No paving shall begin prior to Contracting Agency approval of the 2 Contractor provided mix design. 3 4 Mixing 5 6 Acceptance Sampling and Testing - HMA Mixture 7 8 General 9 (November 20, 2013 APWA GSP) 10 11 Delete Section 5-04.3(8)A1 and replace it with the following: 12 13 Acceptance of HMA shall be as defined under nonstatistical or commercial 14 evaluation. 15 16 Nonstatistical evaluation will be used for all HMA not designated as 17 Commercial HMA in the contract documents. 18 19 The mix design will be the initial JMF for the class of HMA. The Contractor 20 may request a change in the JMF. Any adjustments to the JMF will require 21 the approval of the Project Engineer and may be made in accordance with 22 Section 9-03.8(7). 23 24 Commercial evaluation will be used for Commercial HMA and for other 25 classes of HMA in the following applications: sidewalks, road approaches, 26 ditches, slopes, paths, trails, gores, prelevel, and pavement repair. Other 27 nonstructural applications of HMA accepted by commercial evaluation 28 shall be as approved by the Project Engineer. Sampling and testing of 29 HMA accepted by commercial evaluation will be at the option of the 30 Project Engineer. Commercial HMA can be accepted by a contractor 31 certification letter stating the material meets the HMA requirements 32 defined in the contract. 33 34 Reject Work 35 36 Rejection Without Testing 37 (******) 38 Section 5-04.3(11)C is revised to read: 39 40 The Project Engineer may, without sampling, reject any batch, load, or section 41 of Roadway that appears defective. Material rejected before placement shall 42 not be incorporated into the pavement. Any rejected section of Roadway shall 43 be removed. 44 45 Surface Smoothness 46 47 The second sentence of Section 5-04.3(13) is revised to read: 48 49 (January 5, 2004) 50 The completed surface of the wearing course shall not vary more than 1/4 inch 51 from the lower edge of a 10-foot straightedge placed on the surface parallel to 52 centerline.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 130 1 Payment 2 3 Quality Assurance Price Adjustments 4 (******) 5 6 Section 5-04.5(1) is deleted in its entirety. 7

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 131 1 Division 7 2 Drainage Structures, Storm Sewers, Sanitary 3 Sewers, Water Mains, and Conduits 4 5 Add the following new section: 6 7 7-20 Dewatering

8 (******) 9 7-20.1 Description 10 11 The Contractor shall obtain permits, construct, install, maintain, and operate diversion 12 piping, force mains, sumps, pumps, or other structures and equipment necessary to 13 protect the work areas from flooding. The contractor shall obtain approval of the 14 Engineer before each day’s operation of the dewatering system, and any day on which 15 the dewatering system is operated without the prior approval of the Engineer shall not be 16 measured for payment. 17 18 The Contractor shall drain or otherwise dewater all structural excavations to a minimum 19 1 foot below subgrade elevation to allow construction to be performed under suitable 20 subgrade soil conditions. Dewatering equipment shall be furnished to keep the 21 excavation free of water continuously from the time excavation is begun until backfill is 22 completed. Disposal of water shall be in a manner that will not harm or damage adjacent 23 property or the downstream drainage system. Possible disposal options for dewatering 24 water include direct discharge to an on-site sewer manhole. The Contractor shall comply 25 with local, State, and Federal laws and permit conditions regarding sedimentation and 26 water quality control from dewatering water discharge. The contractor shall obtain any 27 permits necessary for dewatering. The dewatering shall be accomplished in a manner 28 that prevents loss of fines and maintains the stability of the excavated area. 29 30 The Contractor shall be solely responsible for the proper design, installation, proper 31 operation, permitting, maintenance, and failure repair of any component of the 32 dewatering system. This requirement shall apply continuously and not be limited to 33 normal working hours. Submission and approval of the dewatering plan in no way 34 relieves that contractor from any obligations under the Contract. For bidding purposes, 35 Contractor shall assume a water table elevation of 25 feet AMSL at the sump area. 36 37 7-20.4 Measurement 38 39 Dewatering will be measured per day for each day on which the dewatering system is 40 operated. 41 42 7-20.5 Payment 43 44 Payment will be made in accordance with Section 1-04.1 for the following Bid item: 45 46 “Dewatering”, per day. 47

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 132 1 Division 8 2 Miscellaneous Construction 3 4 Add the following new section: 5 6 8-30 Sump Pump and Controls 7 (******) 8 8-30.1 Description 9 10 This section specifies submersible sump pump complete with motor, discharge flange, 11 cable, level controls and control panel. 12 13 8-30.2 Materials 14 15 Pump shall be of the submersible, centrifugal nonclog type for use in pumping decant 16 wastewater, with the ability to pass up to ¾-inch solids. Pump shall be modified to 17 provide specified features and to meet specified operating conditions. 18 19 Equipment provided under this section shall conform to the following: 20 Rated capacity, Design Max. Max. sphere Voltage Max. Discharge pipe gpm at head, speed, passage, size, and phase horsepower size, inches design feet rpm inches head 28 26 3450 115V, 1- 1/2 1-1/2 3/4 phase 21 22 MOTOR 23 24 The motor shall be designed to be nonoverloading over the entire pump curve. The 25 motor housing shall be of submersible construction with the windings operating in a 26 sealed environment. Motors shall be either air or dielectric oil filled with built-in 27 automatic reset overload protection. Motors shall be explosionproof and shall be UL 28 listed in accordance with UL 674 for Class I, Group D hazardous atmosphere. 29 30 CABLE 31 32 Pump motor and detector cables shall be suitable for submersible pump applications. 33 Power for the motor shall be carried by a heavy-duty, flexible, watertight portable cable, 34 sealed at the motor bell and of sufficient length to connect to the control panel. The 35 cable entry shall prevent water from leaking into the motor due to capillary action even if 36 cable is cut or damaged. A field installed stainless steel strain relief device shall be 37 supplied with the motor cable. 38 39

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 133 1 CONTROLS 2 3 The control panel for this application shall be a simplex NEMA 4X 316L SS. The control 4 panel shall come complete with inputs for three float switches, aux contacts and an 5 audio and visual alarm beacon/strobe mounted to the top of the control panel. Terminal 6 blocks shall be provided for all external inputs, including source power, float switches 7 and output to the sump pump motor. The control panel shall have an HOA selector 8 switch to choose the mode of operation, and come complete with an integral disconnect 9 switch and 120V rated motor starter. 10 11 Sump pump shall operate on a float type level control system when in the AUTO mode. 12 The floats shall be non-mercury type and a minimum of three floats shall be provided 13 with the system, When the sump level rises above the high level setpoint, as shown on 14 the Contract Drawings, the pump shall run. When the sump level falls below the low 15 level setpoint, as shown on the Contract Drawings, the pump shall stop running. If sump 16 level rises above the high-high level setpoint, as shown on the Contract Drawings, the 17 high level alarm shall be triggered. When the selector switch is in the MANUAL mode 18 the sump pump shall run until the position of the selector switch is changed. 19 20 SPARE PARTS 21 22 Each pump shall be provided with the following spare parts: 23 24 1 set – each size of fuses 25 1 each- spare pump (complete) 26 27 PRODUCT DATA 28 29 The Contractor shall provide the following submittals in accordance with Section 1-06.1: 30 31 1. Manufacturer's data including materials of construction and equipment weight. 32 33 2. Predicted performance curves developed for the specific application. 34 35 3. Applicable operation and maintenance information. 36 37 8-30.3 Construction Requirements 38 39 INSTALLATION 40 41 Sump pump shall be installed in accordance with the manufacturer's recommendations. 42 43 TESTING 44 45 Pump system shall be tested for control and capacity over a 2-hour period. 46 47 8-30.4 Measurement 48 49 No unit of measurement shall apply to the Sump Pump and Controls, which shall be 50 incidental to the Sump Area construction. 51

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 134 1 8-30.5 Payment 2 3 All costs for the Sump Pump and Controls shall be incidental to the lump sum Contract 4 price for “Sump Area”. 5 6 Add the following new section: 7 8 8-31 Sump Area 9 (******) 10 11 8-31.1 Description 12 13 This section specifies construction of structural and mechanical components of the 14 sump area. Sump area includes: Concrete partition wall; FRP grating and supports; inlet 15 tee, absorbent boom, and connections; concrete removal and construction of new 16 sump; sump pump and controls; access ladder; guardrail; and sump discharge piping 17 and fittings, including coring through existing concrete pit wall, and all work incidental to 18 and necessary to complete the construction of the sump area as shown on the Contract 19 Drawings and Specifications. 20 21 8-31.2 Materials 22 23 Schedule 80 PVC Pipe and Fittings: 9-05.12(3) 24 Guardrail: 9-41 25 Access Ladder: 9-42 26 Structural components: CSI Divisions 03 and 05 27 Sump Pump and Controls: 8-30 28 Drop Structure 29 Ball valve 30 Oil absorbent sock/net boom and eye hooks 31 Polypropylene steps 32 33 Ball Valve shall be a socket end PVC ball valve with square operating nut, as 34 manufactured by Asahi/America, Chemtrol, GSR, or approved equal, with PTFE seats 35 and Viton 0-rings. 36 37 Oil absorbent sock/net boom shall be an oil-only absorbent boom, 8” diameter by 10’ 38 long, with a minimum absorption capacity of 9 gallons per boom, with metal connector 39 clips at each end of the boom. 40 41 Polypropylene steps shall be polypropylene plastic conforming to ASTM D4101, injected 42 molded around a one-half (½) inch diameter, Grade 60, steel reinforcing bar, conforming 43 to ASTM A-615. The steps shall also meet the applicable requirements of ASTM C-478 44 and AASHTO M-199. 45 46 8-31.3 Construction Requirements 47 48 Sump Area shall be constructed as shown on the Contract Drawings and as described 49 in these Contract Specifications. 50 51 Contractor shall install the eye hooks for the oil absorbent sock/net boom as shown in 52 the Contract Drawings, and provide one boom separately to be installed by the Agency.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 135 1 Contractor shall also provide and install all necessary hardware for connecting the 2 connector clips at each end of the boom to the eye hooks installed in the partition wall. 3 4 8-31.4 Measurement 5 6 No unit of measurement shall apply to the lump sum price for Sump Area. 7 8 8-31.5 Payment 9 10 Payment will be made in accordance with Section 1-04.1 for the following Bid item: 11 12 “Sump Area”, per lump sum. 13 14 Add the following new section: 15 16 8-36 Electrical Work 17 (******) 18 19 8-36.1 Description 20 21 This section specifies Electrical Work for the Facility as described in Special Provision 22 Section 16000. 23 24 8-36.2 Materials 25 26 Materials shall conform to those shown on the Contract Drawings and described in 27 Special Provision Section 16000. 28 29 8-36.3 Construction Requirements 30 31 Electrical work shall be constructed in accordance with the Contract Drawings and as 32 described in Special Provision Section 16000. 33 34 8-36.4 Measurement 35 36 No unit of measurement shall apply to the lump sum price for Electrical Work. 37 38 8-36.5 Payment 39 40 Payment will be made in accordance with Section 1-04.1 for the following Bid item: 41 42 “Electrical Work”, per lump sum. 43 44

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 136 1 Add the following new section: 2 3 8-37 Decant Area 4 (******) 5 6 8-37.1 Description 7 8 This section specifies construction of structural and mechanical components of the 9 decant area. Decant area includes: Concrete partition walls and push walls; re-grading 10 and replacement of concrete floor slab; weirs; speed bumps; temporary chain link, 11 permanent chain link fence and gate; and all work incidental to and necessary to 12 complete the construction of the decant area as shown on the Contract Drawings and 13 Specifications. 14 15 8-37.2 Materials 16 17 Materials shall conform to those shown on the Contract Drawings. 18 19 8-37.3 Construction Requirements 20 21 The Decant Area shall be constructed in accordance with the Contract Drawings. 22 23 8-37.4 Measurement 24 25 No unit of measurement shall apply to the lump sum price for the Decant Area. 26 27 8-37.5 Payment 28 29 Payment will be made in accordance with Section 1-04.1 for the following Bid item: 30 31 “Decant Area”, per lump sum. 32

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 137 1 Division 9 2 Materials 3 4 Aggregates 5 6 Aggregates for Ballast and Crushed Surfacing 7 8 Crushed Surfacing 9 (8/11/03) Sk. Co. 10 11 Section 9-03.9(3) is revised as follows: 12 13 The minimum value for Sand Equivalent for Top Course and Keystone of Section 9- 14 03.9(3) is revised to read: 50 15 16 Aggregate for Gravel Base 17 18 (3/19/08) Sk. Co. 19 20 The grading and quality requirements of Section 9-03.10 are revised as follows: 21 22 Sieve Size Percent Passing 23 24 ¼” square opening 25-70 25 No. 200 sieve 10.0 max. 26 Dust Ratio: % Passing U.S. No. 200 2/3 max 27 % Passing U.S. No. 40 28 Sand Equivalent 35 min. 29 30 All percentages (%) are by weight 31 32 Gravel base material retained on a ¼ inch square sieve shall contain not more than 33 0.20 percent by weight wood waste. 34 35 Drainage Structures, Culverts, and Conduits

36 Polyvinyl Chloride (PVC) Pipe 37 38 Add the following new section: 39 40 9-05.12(3) Schedule 80 PVC Pipe and Fittings 41 (******) 42 43 Schedule 80 PVC material for pipe and fittings shall conform to ASTM D1784, 44 Class 12454 B. Pipe and fittings shall be in accordance with ASTM D1785. 45 Neoprene gaskets with push on joints shall conform to ASTM F477. 46 47 Schedule 80 PVC socket type fittings shall conform to ASTM D2467. PVC solvent 48 weld cement for socket connections shall meet the requirements of ASTM D2564. 49 50 PVC pipe shall be joined by means of socket fittings and solvent welding in 51 conformance with ASTM F402. Solvent-cemented joints shall be made in strict

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 138 1 compliance with the manufacturer's/supplier's instructions and recommended 2 procedures. 3 4 Contractor shall submit proposed Schedule 80 PVC pipe and fittings product data 5 sheets for approval by Engineer prior to construction. 6 7 Add the following new section: 8 9 (******) 10 9-41 Guardrail

11 Guardrail shall be constructed of 1 ½” schedule 40 anodized aluminum pipe and shall 12 be plate mounted to the outer surface of the sump partition wall as shown on the 13 Contract Drawings. Support post spacing shall be a maximum of 48” on center, or as 14 specified by the manufacturer. Guardrail shall be constructed to meet applicable OSHA 15 and WSHA fall protection and minimum impact resistance requirements. 16 17 Contractor shall submit guardrail product data sheet for approval by Engineer prior to 18 construction. 19 20 Add the following new section: 21 22 (******) 23 9-42 Access Ladder 24 25 Access ladder shall be installed and secured in the location shown on the Contract 26 Drawings, in accordance with the manufacturer's recommendations and with OSHA and 27 ANSI A14.3-2002, American National Standard for Ladders-Fixed-Safety Requirements. 28 29 Contractor shall submit access ladder product data sheet for approval by Engineer prior 30 to construction. 31

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 139

[This page left blank intentionally.]

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 140 1 ADDITIONAL SPECIAL PROVISIONS 2 3 The Special Provisions listed below supersede the corresponding Sections of the Standard 4 Specifications.

5 CSI DIVISION 03 – CONCRETE 6 03 10 00 – CONCRETE FORMWORK 7 03 20 00 – CONCRETE REINFORCEMENT 8 03 25 20 – ANCHORS, INSERTS, AND EMBEDDED PRODUCTS 9 03 25 30 – WATERSTOPS 10 03 30 00 – CAST-IN-PLACE CONCRETE

11 CSI DIVISION 05 – METALS 12 05 03 00 – GALVANIZING 13 05 12 00 – STRUCTURAL STEEL 14 05 50 00 – METAL FABRICATION

15 DIVISION 16 – ELECTRICAL 16 16 000 – GENERAL REQUIREMENTS FOR ELECTRICAL WORK

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 141 SKAGIT COUNTY PUBLIC WORKS SECTION 031000 STREET WASTE FACILITY CONCRETE FORMWORK

1 Part 1 – GENERAL

2 1.01 SUMMARY

3 A. Section Includes: 4 1. Forms 5 2. Form Coatings

6 1.02 REFERENCES

7 A. Comply with the following list of standards referenced in this section:

8 1. “Recommended Practice for Concrete Formwork,” ACI 347.

9 2. “Section 1906,” International Building Code.

10 3. U.S. Product Standard PS 1 for Plywood.

11 4. Standard Grading and Dressing Rules No. 17 of the West Coast Lumber 12 Inspection Bureau.

13 1.03 PRODUCT DELIVERY, STORAGE, AND HANDLING

14 A. On delivery to job site, place materials in area protected from weather.

15 B. Store materials above ground on framework or blocking and cover with 16 protective water-proof covering providing for adequate air circulation or 17 ventilation.

18 C. Handle materials to prevent damage.

19 Part 2 – PRODUCTS

20 2.01 MATERIALS

21 A. Plywood: New or in new condition “B-B Plyform Class 1 Exterior” grade 22 plywood, 5/8 inch minimum thickness.

23 B. Steel Panels: Flat steel sheet or plate of sufficient thickness, or braced 24 sufficiently, to prevent noticeable deflection from pressure of concrete. Steel 25 forms galvanized and/or coated to prevent rust and staining.

26 C. Framing, Studding, and Bracing: “Standard” or “Construction” grade West 27 Coast Species lumber.

28 D. Form Ties: Prefabricated rod of the cone-type snap-tie configuration; or 29 approved threaded internal disconnecting type to resist all imposed loads of 30 freshly placed concrete, and permit tightening and spreading of forms. Plastic 31 cone snap-ties shall break back 1 to 1-1/2 inches.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 142 SKAGIT COUNTY PUBLIC WORKS SECTION 031000 STREET WASTE FACILITY CONCRETE FORMWORK

1 E. Form Coating:

2 1. Lacquer, plastic or epoxy coating or non-staining form oil that will not 3 impair the bonding quality for final finish of the painting or protective 4 coating. Coatings containing mineral oils or other non-drying ingredients 5 will not be permitted.

6 2. Chamfer Strips: Chamfer strips (for all exposed edges) 3/4 inch, 45° 7 bevel wood strips or reusable plastic triangular strips.

8 Part 3 – EXECUTION

9 3.01 DESIGN OF FORMWORK

10 A. Design formwork to safely support vertical and lateral loads which might be 11 applied until such loads can be supported by the concrete structure. Carry 12 vertical and lateral loads by formwork system to ground or to in-place 13 construction which has attained adequate strength for that purpose.

14 B. Design formwork to be readily removable without impact, shock, or damage to 15 cast-in-place concrete surfaces and adjacent material.

16 C. Prevent oil or other agents from getting on reinforcing steel, embedded items, or 17 other surfaces requiring bond with concrete.

18 3.02 LAYOUT OF FORMWORK

19 A. Locate and stake out all forms and establish all lines and levels and elevations.

20 3.03 CONSTRUCTION OF FORMS

21 A. Formwork - General:

22 1. Before concrete is placed in any form, verify horizontal and vertical form 23 position and correct all inaccuracies. Complete all wedging and bracing 24 in advance of placing of concrete.

25 2. When setting form ties, allow no metal to remain in wall closer than one 26 inch from surface. Ties shall fit tight to prevent mortar leakage at holes 27 in forms. Ties shall be protected from rusting at all times. No wire ties 28 or wood spreaders will be permitted. Cutting ties back from concrete 29 face will not be permitted.

30 3. At construction joints, anchor forms by using an adequate number of 31 form ties in the new pour a few inches from the construction joints. Do 32 not rely on ties adjacent to the joint used in previous placements. All 33 joints to be horizontal and vertical.

34 4. For exposed concrete, forms shall be of new plywood, metal panel, or 35 approved panel materials, smooth, and continuous.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 143 SKAGIT COUNTY PUBLIC WORKS SECTION 031000 STREET WASTE FACILITY CONCRETE FORMWORK

1 B. Chamfered Corners: All corners chamfered 3/4 inch, unless shown otherwise 2 on drawings. Provide 45-degree triangular moldings in forms for all chamfering 3 required.

4 D. Coordination: Coordinate the installation of all items to be inserted or 5 embedded in concrete. Support all items to maintain accurate alignment and 6 prevent distortion during concrete placement.

7 E. Cleaning: All dirt, chips, sawdust, mud, water and other foreign matter shall be 8 removed from within the forms or within the excavated areas before any 9 concrete is deposited therein.

10 3.04 NOTIFICATION AND INSPECTION

11 A. Prior to placing of any concrete, and after placement of reinforcing steel in the 12 forms, notify the Engineer at least 24 hours in advance of placing concrete to 13 permit inspection.

14 3.05 DEFECTIVE WORK

15 A. Any form movement or deflection during construction or finished surface 16 variations in excess of the tolerances specified will be basis for rejection of cast- 17 in-place product and requirement for replacement of same.

18 3.06 REMOVAL OF FORMS

19 A. Do not remove forms and supports until concrete has attained sufficient strength 20 to support anticipated loads.

21 B. The listing below serves only as a guide in determining the minimum length of 22 time required before removal of forms and is based on the use of Type I 23 Portland Cement. When high early strength Portland Cement is used, the 24 length of time listed below may be reduced to not less than one-third time listed, 25 but not less than 1 day.

26 1. Thin walls (12 inches or less) ...... 48 hours 27 C. Use methods of form removal which will not cause overstressing of the 28 concrete.

29 D. Break back ties after concrete has cured sufficiently to maintain unbroken bond 30 with steel rod.

31

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 144 SKAGIT COUNTY PUBLIC WORKS SECTION 031000 STREET WASTE FACILITY CONCRETE FORMWORK

1 3.07 REUSE OF FORMS

2 A. Any reused form for exposed concrete work shall be reconditioned to “like new” 3 condition. Any reused form shall be cleaned, repaired, and recoated before 4 each reuse.

5

6 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 145 SKAGIT COUNTY PUBLIC WORKS SECTION 032000 STREET WASTE FACILITY CONCRETE REINFORCEMENT

1 Part 1 – GENERAL

2 1.01 SUMMARY

3 A. Section Includes: 4 1. Reinforcing bars. 5 2. Welded wire fabric.

6 1.02 REFERENCES

7 A. Comply with the following list of standards referenced in this Section.

8 B. American Concrete Institute (ACI) – www.concrete.org. 9 1. ACI 315 – Details and Detailing of Concrete Reinforcement 10 2. ACI 318 – Building Code Requirements for Structural Concrete and 11 Commentary.

12 C. ASTM International – www.astm.org: 13 1. ASTM A615 – Standard Specification for Deformed and Plain Carbon-Steel 14 Bars for Concrete Reinforcement. 15 2. ASTM A185 – Standard Specification for Steel Welded Wire 16 Reinforcement, Plain, for Concrete.

17 D. Concrete Reinforcing Steel Institute (CRSI) – www.crsi.org.

18 1.03 SUBMITTALS

19 A. Shop drawings: 20 1. Placing drawings, bending and cut sheet schedules. 21 2. Mill test reports for each shipment of reinforcement shall be submitted to 22 the Engineer for review. 23 3. All wall reinforcement to be shown in elevation on the placing drawings.

24 1.04 QUALITY ASSURANCE

25 A. Manual of Standard Practice for Detailing Reinforced Concrete Structures, ACI 26 315.

27 B. Manual of Standard Practice, Concrete Reinforcing Steel Institute.

28 1.05 DELIVERY, STORAGE, AND HANDLING

29 A. Deliver reinforcement to project site in bundles marked to coordinate with 30 placement drawings.

31 B. Handle and store to prevent contamination from dirt, oil and other materials 32 which will affect bond.

33 C. Store a minimum of six (6) inches above ground and in locations where the 34 material will not be subject to abuse. 35

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 146 SKAGIT COUNTY PUBLIC WORKS SECTION 032000 STREET WASTE FACILITY CONCRETE REINFORCEMENT

1 Part 2 – PRODUCTS 2 2.01 MATERIALS

3 A. Reinforcing Bars: Unless specified otherwise, all bars for concrete 4 reinforcement deformed, and meet requirements ASTM Designation A 615, 5 Grade 60, “Billet Steel Bars for Concrete Reinforcement.”

6 B. Welded Wire Fabric: Steel, conforming to ASTM A 185, 65 ksi yield strength. 7 Supply in sheets, rolls are not acceptable.

8 C. Tie Wire: Steel, black annealed, sixteen (16) gage minimum.

9 D. Reinforcing Bar Supports: Per CRSI “Manual of Standard Practice,” Chapter 3, 10 pre-galvanized or plastic-coated. 11 Part 3 – EXECUTION

12 3.01 INSTALLATION

13 A. Placement and Tolerances: Conform to CRSI “Manual of Standard Practice”.

14 B. Splices: 15 1. Do not splice bars except at locations shown or noted on the drawings or as 16 otherwise approved. 17 2. Tie lap splices securely with wire to prevent displacement of splice during 18 placement of concrete.

19 C. Cleaning: Remove dirt, grease, oil, loose mill scale, excessive rust, and foreign 20 matter that may reduce bond with concrete.

21 D. Protection during concreting: Keep reinforcing in proper position during 22 concrete placement.

23 E. Concrete cover: Maintain minimum concrete cover over reinforcement as 24 specified in ACI 318 or as noted. 25

26 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 147 SKAGIT COUNTY PUBLIC WORKS SECTION 032520 STREET WASTE FACILITY ANCHORS, INSERTS AND EMBEDDED PRODUCTS

1 Part 1 – GENERAL

2 1.01 SUMMARY

3 A. Section Includes: 4 1. Anchors. 5 2. Insets. 6 3. Embedded products.

7 1.02 REFERENCES

8 A. Comply with the following list of standards referenced in this Section.

9 B. American Iron and Steel Institute (AISI) – www.steel.org:

10 C. ASTM International – www.astm.org: 11 1. ASTM A108 – Standard Specification for Steel Bar, Carbon and Alloy, Cold- 12 Finished. 13 2. ASTM A 240 – Standard Specification for Chromium and Chromium-Nickel 14 Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for 15 General Applications. 16 3. ASTM A 307 – Standard Specification for Carbon Steel Bolts and Studs. 17 4. ASTM A 563 – Standard Specification for Carbon and Alloy Steel Nuts. 18 5. ASTM F1554 – Standard Specification for Anchor Bolts.

19 D. American National Standards Institute (ANSI) – www.ansi.org: 20 1. ANSI B18.2.2. 21 2. ANSI 18.22.1.

22 1.03 SUBMITTALS

23 A. Shop drawings for all anchors, inserts and embedded products.

24 1.04 QUALITY ASSURANCE

25 A. Use only materials compatible with embedded concrete environment.

26 Part 2 – PRODUCTS

27 2.01 MATERIALS

28 A. Anchor Bolts: ASTM F1554, Grade 36 Steel unless otherwise noted.

29 B. Drilled-in Expansion Bolts 30 1. Acceptable Products: 31 a) Hilti – ‘Kwik Bolt Type TZ’. 32 b) Simpson – ‘Strong Bolt – 2’. 33 c) Red Head – ‘Trubolt +’. 34 d) Or Approved Equal. 35

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 148 SKAGIT COUNTY PUBLIC WORKS SECTION 032520 STREET WASTE FACILITY ANCHORS, INSERTS AND EMBEDDED PRODUCTS

1 C. Drilled-in Adhesive Anchoring System 2 1. Acceptable Products: 3 a) Hilti – ‘Hit – RE 500 SD’. 4 b) Simpson – ‘Set – XP’. 5 c) Red Head – ‘Epcon S7’. 6 d) Or Approved Equal. 7

8 Part 3 – EXECUTION

9 3.01 INSTALLATION

10 A. Coordinate the location and placement of all items to be embedded in concrete.

11 B. Coat any embedded aluminum with asphalt paint.

12 C. Embedding: Set accurately and hold in position all embedded products during 13 placement until the concrete is set. 14 15 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 149 SKAGIT COUNTY PUBLIC WORKS SECTION 032530 STREET WASTE FACILITY WATERSTOPS

1 Part 1 – GENERAL

2 1.01 PRODUCT DELIVERY, STORAGE AND HANDLING

3 A. Deliver in original container.

4 B. Store and handle in manner to prevent damage or contamination which would 5 cause leaks or affect bond with concrete.

6 Part 2 – PRODUCTS

7 2.01 MATERIALS

8 A. Strip Applied Hydrophilic Waterstop: “Hydrotite” by Greenstreak, “Ultraseal 9 MC2012” by Adeka, “Earth Shield Stype 20” by JP Specialties, Inc., or 10 approved equal, where shown on Drawings.

11 B. Strip Applied Bentonite or Plastic Waterstop: Volclay “Waterstop RX” by 12 American Colloid Co., “Swellstop” by Greenstreak, “Superstop by Tremco, 13 or approved equal, where shown on Drawings.

14 C. Mastic Waterstop: “Lockstop” by Greenstreak or “Synkoflex” by Synko-flex 15 Products, “Earth Shield Type 10” by JP Specialties, Inc., or approved equal, 16 where shown on Drawings. 17

18 Part 3 – EXECUTION

19 3.01 AREAS REQUIRED

20 A. Waterstops shall also be provided in locations as shown on drawings.

21 3.02 INSTALLATION

22 A. Install in accordance with the manufacturer's installation instructions for 23 continuous watertightness. Thoroughly vibrate or compact concrete under 24 and around the waterstop to achieve concrete contact with all waterstop 25 surfaces. 26

27

28 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 150 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 Part 1 – GENERAL

2 1.01 SUMMARY

3 A. Section Includes: 4 1. Cast-in-place concrete.

5 1.02 REFERENCES

6 A. American Concrete Institute (ACI) – www.concrete.org. 7 1. ACI 301 – Specifications for Structural Concrete for Buildings.

8 B. ASTM International – www.astm.org: 9 1. ASTM C 33 – Standard Specification for Concrete Aggregates. 10 2. ASTM C 94 – Standard Specification for Ready-Mixed Concrete. 11 3. ASTM C 150 – Standard Specification for Portland Cement. 12 4. ASTM C 260 – Standard Specification for Air-Entraining Admixtures for 13 Concrete. 14 5. ASTM C 618 – Standard Specification for Coal Fly Ash and Raw or 15 Calcined Natural Pozzolan for Use in Concrete.

16 1.03 SUBMITTALS

17 A. Submit two (2) copies of trial mix designs proposed and the mix design used 18 from a record of past performance in accordance with ACI 301.

19 B. Submit manufacturer's certification of meeting these specifications for 20 materials proposed including names, sources, descriptions and warranties, 21 for cement, fly-ash, grouts, water-reducing admixtures, epoxy bonding 22 materials, and curing compounds.

23 C. Submit a sample ready-mixed concrete delivery ticket.

24 1.04 QUALITY ASSURANCE

25 A. Materials and work shall conform to the requirements of standards and 26 recommended practices required in this section. In conflicts between industry 27 standards, required standards and this specification, or this specification and 28 the local building code, the more stringent requirement shall govern.

29 B. Standards: Concrete is designed and controlled by the latest edition of the 30 following: 31 1. ACI 301. “Specifications for Structural Concrete for Buildings.” 32 2. Field Reference Manual (ACI Publication SP-15).

33 C. Contractor shall have available in the field office a copy of the ACI Field 34 Reference Manual SP-15. This field reference manual is a compilation of 35 ACI 301 and selected ACI and ASTM references listed in that specification.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 151 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 D. Concrete Test Cylinders: The Contracting Agency will retain the services of an 2 independent testing laboratory to perform the following: 3 1. Prepare a minimum of three test cylinders for each day’s placement. 4 2. Test set of three (3) cylinders as follows: 5 a) One (1) at seven (7) days. 6 b) Two (2) at twenty-eight (28) days.

7 E. Prior to placement have available at placement location all tools, cylinder 8 molds, slump cone, rod, curing containers and all other apparatus required for 9 sampling and testing.

10 F. Air Entrained: One (1) test for each mix design.

11 Part 2 – PRODUCTS

12 2.01 MATERIALS

13 A. Concrete: 14 1. ASTM C 94 and mix design approved by Engineer. 15 2. Strength: 16 a) For Slab and Push Wall - 6000 psi minimum at twenty- 17 eight (28) days. Cement content not less than 704 lbs. 18 per cubic yard of concrete. 19 b) For concrete not otherwise specified – 4000 psi 20 minimum at twenty-eight (28) days. Cement content 21 not less than 510 lbs per cubic yard of concrete. 22 c) Water/Cement content not more than 0.45. 23 d) Entrained air six (6) ± one (1) percent. 24 e) Maximum slump 3 inches. 25 3. Cement ASTM C 150, Type I or II. 26 4. Aggregates: For concrete twelve (12) inches thick or less, maximum 27 aggregate size three-quarter (3/4) of an inch conforming to ASTM C33, 28 grading No. 67. 29 5. Water: 30 a) Clear and not detrimental to concrete. 31 6. Admixtures: 32 a) Use only those specified in approved mix design. 33 b) Air entrain all concrete unless elsewhere excepted, with 34 agent conforming to ASTM C 260. 35 c) Apply in strict accordance with manufacturer's printed 36 instructions. 37 d) No chloride contents permitted. 38 e) Compatible with other admixtures. 39 f) No job added superplasticizers except to adjust slump 40 from a particular load when approved by the Engineer. 41 g) Pozzolan Admixture: Class F flyash conforming to 42 ASTM C 618, except as modified herein. 43 1) Loss of ignition: Maximum 3 percent. 44 2) Water Requirement: Maximum 100 percent of 45 control.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 152 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

5 - CaO(%) - 5 1 3) Maximum: 1.5 Fe O32 (%) 2 4) Flyash content shall be eighteen (18) to twenty 3 (20) percent of total weight of flyash plus cement.

4 B. Grout: 5 1. For Anchoring Dowels and Reinforcing Bars: Epoxy grout shall be medium 6 viscosity epoxy conforming to ASTM C 881 Types I, II, III, Class B and C. 7 2. Acceptable products for epoxy grout: 8 a) Hilti – HIT – RE 500SD 9 b) Burke – ‘881 LPL epoxies’. 10 c) Sika Corporation – ‘Sikadur 31 Hi-Mod Gel’ 11 d) Master Builders – ‘Concresive Liquid LPL’. 12 e) Or Approved Equal.

13 C. Curing Materials: 14 1. Polyethylene Sheeting 0.004 inch thick. 15 2. Waterproof Paper: Polyethylene-coated, Fed. Spec. UU-B-790 Type I, 16 Grades A, B, C, Style 4. Define lap control lines clearly by printed 17 markings. 18 3. Masonry Sand: ASTM C 144 (Maintained continually moist). 19 4. Membrane Forming Compound: ASTM C 309 Type I. 20 5. Acceptable products: 21 a) Master Builders – ‘Masterkure’. 22 b) Euclid Chemical – ‘Kurez DR – 100’. 23 c) Sonneborn – ‘Kure 1315’. 24 d) Or Approved Equal.

25 D. Dry Shake Metallic Floor Hardener 26 1. For tipping floor slab. 27 2. Apply at the rate of 3lbs per square foot of floor according to 28 manufacturer’s instructions. 29 3. Acceptable products 30 a) Master Builders, Inc – ‘Master Plate 200’. 31 b) Euclid Chemical – ‘Euco Plate HD’. 32 c) Metalcrete Industries – ‘Metal Plate’. 33 d) Or Approved Equal.

34 E. Bonding Agent: 35 1. Epoxy Adhesive Bonding Agent: A two (2) component compound, 100 36 percent solids, 100 percent reactive compound suitable for use on dry or 37 damp surfaces. 38 2. Acceptable products: 39 a) Master Builders, Inc. – ‘Concresive Liquid (LPL)’. 40 b) Sika Corporation – ‘Sikadur 32 Hi-Mod LPL’. 41 c) Euclid Chemical – ‘Dural452 Gel’. 42 d) Or Approved Equal.

43 F. Hot Weather Finishing Aid

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 153 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 1. Evaporation retardant used to retard rapid evaporation of water from 2 exposed concrete. 3 2. Acceptable products: 4 a) Master Builders Inc. – ‘Confilm’. 5 b) Conspec – ‘Aquafilm’. 6 c) W.R. Meadows – ‘Top-Stop’. 7 d) Or Approved Equal.

8 2.02 MIXES

9 A. Ready-Mixed Concrete: Conform to ASTM C94 Alternate No. 3.

10 2.03 FINISHES

11 A. Concrete Slab Finishes: 12 1. Do not excessively use “jitterbugs” or other special tools designed for the 13 purpose of forcing coarse aggregate away from the surface and allowing a 14 layer of mortar to accumulate. 15 2. Do not dust surfaces with dry materials. 16 3. Thoroughly compact slabs and floors by vibration. 17 4. Round off all edges of slabs and tops of walls with a steel edging tool, 18 except where a cove finish is shown. Steel edging tool radius shall be one- 19 quarter (1/4) of an inch for all slabs subject to wheeled traffic. 20 5. After applying the final floor finish and after curing cover slabs with 21 Visqueen or other material to keep floor clean and protect it from material 22 and damage due to other construction work.

23 B. Type S-1 – Concrete Slab Finish Steel Troweled Finish: 24 1. Finish by screeding and floating with straightedges to bring surfaces to 25 required finish elevation shown. 26 2. While concrete is still green, but sufficiently hardened to bear a person's 27 weight without deep imprint, wood float to true, even plane with no coarse 28 aggregate visible. 29 3. Use sufficient pressure on wood floats to bring moisture to surface. 30 4. After surface moisture has disappeared, hand trowel concrete to produce 31 smooth, impervious surface, free from trowel marks. 32 5. Burnish surface with an additional troweling. Final troweling shall produce a 33 ringing sound from trowel. 34 6. Do not use dry cement or additional water during troweling, nor will 35 excessive troweling be permitted. 36 7. Power Finishing: 37 a) An approved power machine may be used in lieu of 38 hand finishing for finishing concrete floors and slabs in 39 accordance with directions of machine manufacturer. 40 b) Do not use power machine when concrete has not 41 attained the necessary set to allow finishing without 42 introducing high and low spots in slab. 43 c) Do first steel troweling for slab S-1 finish by hand. 44

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 154 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 8. Type S-2 – Slab Finish Wood Float: 2 a) Finish slabs to receive fill and mortar setting beds by 3 screeding with straightedges to bring surface to 4 required finish plane. 5 b) Wood float slab to compact and seal surface. 6 c) Remove all laitance and leave surface clean. 7 d) Coordinate with other finish procedures. 8 9. Type S-3 – Broomed Finish: 9 a) Finish as specified for Type S-1 floor finish, except omit 10 final troweling and finish surface by drawing a fine-hair 11 broom lightly across the surface. 12 b) Brooming: Sloped slabs, perpendicular to slope.

13 C. Tolerances: 14 1. Unless otherwise required, allowable tolerances for concrete surfaces 15 shall be in accordance with those shown in the table below. Surface 16 irregularities are classified as either “abrupt” or “gradual.” Offsets caused 17 by displaced or misplaced form sheathing, lining, or form section or by 18 defective form lumber shall be considered as abrupt irregularities. All 19 others are classed as gradual irregularities. Gradual irregularities shall 20 be measured with a template consisting of a straight edge for plane 21 surfaces and its equivalent for curved surfaces. 22 2. The length of the template for testing formed surfaces five (5) feet. The 23 length of the template for unformed surfaces ten (10) feet. Maintain a 24 five (5) foot length and ten (10) foot length steel template on the job site. 25 3. Maximum allowable irregularities in concrete: Irregularity in Inches

Location Gradual Abrupt

Slabs 1/4 1/4

Walls 1/4 3/16

26 Part 3 – EXECUTION

27 3.01 PREPARATION

28 A. Deliver only in sufficient quantities required for specified time interval use and 29 placement. Do not place concrete having initial set. No remixing with water or 30 supplementing with other materials will be permitted once initial set has 31 occurred. Initial set as evidenced by typical hydration characteristics to be 32 determined by Engineer.

33 B. Place as nearly as possible to final position to avoid segregation of the 34 materials and displacement of reinforcement. Placement shall be completed 35 within thirty (30) minutes after water is first added to the mix. However, at the 36 Engineer's discretion if climatic and temperature conditions are suitable and

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 155 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 when the concrete is continually agitated, the time may be extended to one 2 and one-half (1½) hours.

3 C. Do not change consistency (slump) for a given placement without the 4 Engineer's written permission.

5 D. Keep open trough and chutes of steel or steel lined, clean and free from 6 coatings of hardened concrete.

7 E. Layout and sequence of placing of concrete in monolithic structures as shown 8 on the drawings or approved by the Engineer.

9 F. Unless specified otherwise, place all slabs and finished floors to finish 10 elevation in one continuous operation. Floor slab sectional thicknesses shown 11 are minimum thicknesses. Slopes on floors increase, rather than decrease, 12 slab thicknesses.

13 G. Construction Joints: 14 1. Limit size of each slab or wall pour as shown on the drawings, or as 15 approved by the Engineer, or as follows: 16 a) Where expansion or control joints are shown to be at 17 sixty (60) feet approximately, intermediate construction 18 joints will not be required. 19 b) Where expansion or control joints are not shown, 20 construction joint spacing shall not exceed forty (40) 21 feet. 22 2. Locate construction joints so as not to impair the strength of the structure, 23 and only at locations shown on the shop drawings or approved by the 24 Engineer. 25 3. Construct bulkheads to neatly fit reinforcement and prevent concrete 26 leakage. 27 4. Provide sealants in construction joints where required. 28 5. Continue reinforcement through construction joint unless otherwise shown 29 or noted. 30 6. Alternate pour at each side of construction joints with seven days minimum 31 curing time between pours. 32 7. Before placing concrete against previously placed concrete, thoroughly 33 roughen and clean by wet sandblasting or green cutting with an air-water 34 jet.. 35 a) Use air-water cutting at the proper time after the initial 36 set. Use a high pressure air-water jet to expose clean, 37 sound aggregate without undercutting the edges of the 38 larger aggregate. Protect adjacent subgrade when 39 cutting is used on slab edges. 40 b) After cutting or sandblasting, rinse the surface until 41 wash water contains no cloudiness. Dispose of wastes 42 from cutting, washing and rinsing so they do not stain or 43 abrade exposed surfaces. 44 8. Place concrete continuously to a predetermined construction joint.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 156 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 H. Care shall be taken in placing concrete through reinforcements so that no 2 segregation of the coarse aggregate occurs. In any placement where they 3 may occur, the concrete shall be designed flowable and placed at six (6) inch 4 plus slump. Vibrators shall be inserted no farther than three (3) feet from the 5 point of placement of concrete into forms, as concrete is being placed.

6 I. Special care shall be taken to prevent splashing forms or reinforcement with 7 concrete. Any hardened concrete or partially hardened concrete on the forms 8 or reinforcements above the level of the concrete already in place shall be 9 removed before proceeding with the work.

10 J. Cold Weather Placement: 11 1. Concrete shall be placed only when the temperature is at least forty (40) 12 degrees Fahrenheit, and rising, unless permission to pour is obtained from 13 the Engineer. 14 2. Material shall be heated and otherwise prepared so that batching and 15 mixing can proceed in full accord with the provisions of this Specification. 16 3. Suitable means shall be provided for maintaining the concrete at a 17 temperature of at least fifty (50) degrees Fahrenheit for a period of at least 18 the first five (5) days and at a temperature above freezing for the remainder 19 of the specified curing period, except that where high-early-strength cement 20 is used, this period may be reduced to seventy-two (72) hours. The 21 methods proposed for heating the materials and protecting the concrete 22 shall be approved by the Engineer. 23 4. Salts, chemicals, or other materials shall not be mixed with concrete for the 24 purpose of preventing freezing. 25 a) Acceptable Products: 26 1) Master Builders, Inc – ‘Pozzutec 20’. 27 2) Or Approved Equal.

28 K. Hot Weather Placement: 29 1. The temperature of fresh concrete at the time of placement during hot 30 weather shall be a maximum of ninety (90) degrees Fahrenheit, to prevent 31 an accelerated setting of the concrete. 32 2. A retarding densifier admixture shall be used when the high expected 33 atmospheric temperature for the day is eighty-five (85) degrees Fahrenheit 34 or above. 35 3. Admixture shall be used in accordance with the manufacturer's 36 recommendations.

37 L. Placing Concrete Slabs: 38 1. Smooth subgrade surface irregularity with thin film of masonry sand.

39 3.02 INSTALLATION

40 A. Compact all concrete with high frequency internal vibrators immediately after 41 placing.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 157 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 B. Use external vibrators for compacting concrete where the concrete is 2 inaccessible for adequate compaction by internal vibrators; construct forms 3 sufficiently rigid to resist displacement or damage from external vibration.

4 C. Use mechanical vibrating equipment, always keeping the vibrator within three 5 (3) feet of the discharge point into the form.

6 D. For exposed concrete surfaces, keep the vibrator on the unexposed side of 7 the reinforcing steel or at least two and one-half (2½) inches from the form 8 surface.

9 E. Vibrate the concrete as the concrete is being placed to prevent honeycomb, 10 rock pockets and voids.

11 F. Do not insert vibrators into lower layers of concrete that have begun to set.

12 3.03 REPAIR/RESTORATION

13 A. Immediately after removal of forms, break back all form ties and inspect 14 concrete surfaces for defects.

15 B. Complete repair of defects within forty-eight (48) hours after removal of forms. 16 No repairs shall be made until the defects have been reviewed and method of 17 repair approved by the Engineer.

18 C. Remove all defective or damaged concrete, including honeycombed, sand 19 streaked, or fractured material from the area to be repaired. Chip out areas to 20 one inch minimum depth. Edge shall be squared with the surface to eliminate 21 feather edges.

22 D. Before placing the repair material obtain Engineer inspection. Clean area free 23 of chipping dust, dried mortar, and all other foreign material.

24 E. Keep surfaces to be repaired continuously wet for at least three hours prior to 25 placing new concrete or mortar. No free water on the surface when the repair 26 material is placed.

27 F. Apply a bonding agent to the area to be repaired before placing repair 28 material. Apply the bonding agent per manufacturer's published instructions 29 attached to container.

30 G. For all repair surfaces permanently exposed to atmosphere use white cement 31 in proportions found by trial to be effective in producing a color which, in the 32 hardened patch, will match the surrounding concrete surface.

33 H. Make repairs by: (1) dry-packing, (2) filling with concrete, or (3) plastering with 34 mortar or a combination of all 3 in conformance with the following:

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 158 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 1. Use the dry-pack method for holes at least one inch deep where the depth 2 is equal to, or greater than the smallest surface dimension of the defect, 3 such as cone-bolt or form tie holes, and for narrow slots cut for the repair of 4 cracks. Do not use the dry-pack method where lateral restraint cannot be 5 obtained. Place and pack dry-pack mortar in layers having a compacted 6 thickness of approximately 3/8 inch. Solidly compact each layer over its 7 entire surface by use of a hardwood stick and hammer. Do not use metal 8 tools for compacting. Compact surface just flush with adjacent area. Do 9 not use steel finishing tools or water to facilitate finishing. Color match. 10 2. Use concrete replacement for (1) holes extending entirely through concrete 11 sections; (2) for holes larger than one square foot and deeper than four 12 inches in which no reinforcement is encountered; (3) for holes larger than ½ 13 of one square foot where reinforcement is exposed. Concrete used for 14 replacement shall be of the same strength and mixture as used in the 15 structure. Color match. 16 3. Use mortar replacement for holes too wide to dry-pack and too shallow for 17 concrete replacement and when approved by the Engineer for other 18 conditions not covered by items (1) and (2) above.

19 I. Cure all repairs with the same methods as new concrete. 20

21 3.04 FIELD QUALITY CONTROL

22 A. Any concrete placed which fails to meet or exceed the specified strength 23 requirements as determined from molded cylinders, or cores, or to meet the 24 density or surface requirements, or which has been frozen during placing or 25 curing, shall be removed and replaced with satisfactory materials at the 26 Contractor's expense.

27 B. Method of determining unsatisfactory concrete: Visual appearance 28 characteristic of rain or freeze damage to concrete which is apparent to the 29 Engineer.

30 3.05 CLEANING

31 A. Clean existing concrete surfaces by using wet sandblast or ultra-high pressure 32 water jet to remove the surface film and contaminants. Coat the contact 33 surfaces with bonding agent specified hereinbefore. Apply the bonding agent 34 in conformance with the manufacturer's instruction. As concrete is placed, 35 thoroughly vibrate against the contact overface. Concrete at the contact 36 surface should be revibrated deeply as late as the running vibrator will 37 penetrate the concrete of its own weight.

38 3.06 PROTECTION

39 A. Maintain at site ready to install, before actual concrete placing begins, all 40 equipment and materials needed for optimum concrete curing and protection; 41 maintain extra vibrators on standby in case of malfunction of any unit.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 159 SKAGIT COUNTY PUBLIC WORKS SECTION 033000 STREET WASTE FACILITY CAST-IN-PLACE CONCRETE

1 B. Protect finished surfaces or edges from stains, abrasions and breakage during 2 the entire construction period.

3 C. Protect all concrete from accelerated drying and excessive heat at all times.

4 D. Install slab curing covers immediately after initial set or as soon as free water 5 has disappeared from the surface of the concrete after finishing or surfacing.

6 E. Curing compounds: 7 1. Use only when specifically approved and for optimum climatic conditions. 8 2. Do not use curing compounds unless their use is authorized in writing by 9 the Engineer. Curing compounds unacceptable where concrete is exposed 10 to the direct rays of the sun or accelerated drying conditions. 11 3. All interior slabs shall have membrane-forming compounds that meet the 12 moisture retention required by ASTM C 309-81 when applied at a normal 13 single coat. 14 4. Prior to applying curing compounds to formed surfaces, the surfaces shall 15 be moistened with a spray of water immediately after forms are removed. 16 Moistening shall be continued until the surfaces will not readily absorb more 17 water. The compound shall be applied as soon as the moisture film has 18 disappeared and while the surface is still damp. 19 5. On slabs, the compounds shall be applied immediately after finishing and 20 after bleeding water and “shine” has disappeared. 21 6. Curing compounds shall not be used on surfaces where future bonding, 22 painting or protective coating is required. In cold weather, curing 23 compounds shall not be used on concrete surfaces which are kept at curing 24 temperature by the use of steam.

25 F. Saturated Sand Curing: 26 1. Horizontal construction joints and finished surfaces, cured with sand, shall 27 be kept covered with a minimum thickness of one inch of sand. It shall be 28 kept uniformly distributed and continuously wetted with clean water for a 29 period of 7 days.

30 SCHEDULES

31 G. Schedule of Concrete Finishes: 32 33 Area Type 34 Slabs – Interior S-1 35 Top of Walls S-3 36 37 38 39 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 160 SKAGIT COUNTY PUBLIC WORKS SECTION 050300 STREET WASTE FACILITY GALVANIZING

1 Part 1 – GENERAL 2

3 1.08 SUMMARY

4 B. Section Includes:

5 1. Metal Fabrication 6 2. Steel 7 1.09 DEFINITIONS

8 A. Hot-Dip Galvanizing: The dipping of steel members and assemblies into molten 9 zinc for lasting (or long-term) corrosion protection. The resultant zinc coating 10 fuses permanently with the base steel material.

11 B. Passivating: The mechanical treatment of freshly galvanized steel materials to 12 prevent humid storage stain (white rust or white corrosion). This treatment 13 (passivation) consists of quenching freshly galvanized steel in water to which a 14 chromate or a chromic-acid solution, or other proprietary solution, has been 15 added.

16 1.010 QUALITY ASSURANCE

17 A. Reference Standards

18 1. American Hot-Dip Galvanizers Association, Inc. (AHDGA): Publication, 19 “Inspection Manual for Hot-Dip Galvanized Products.”

20 B. Certification. Furnish Certificates of Compliance with ASTM Specifications, and 21 Standards specified herein. Each certificate to be signed by Contractor and 22 Galvanizer certifying that steel materials, bolts, nuts, washers, and items of iron 23 and steel hardware conform with specified requirements.

24 1.011 PRODUCT DELIVERY, STORAGE AND HANDLING

25 A. Packaging. Of type to prevent damage to galvanized surfaces and distortion of 26 steel materials and components.

27 B. Handling and Storage. Handle and protect galvanized materials from damage 28 to zinc coating. To avoid humid storage stain, space surfaces of galvanized 29 materials to permit free circulation of air.

30 C. Damaged Material. Repair material showing evidence of damage to zinc 31 coating. If not repairable, material with damaged coating will be subject to 32 rejection.

33

34

35

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 161 SKAGIT COUNTY PUBLIC WORKS SECTION 050300 STREET WASTE FACILITY GALVANIZING

1 Part 2 – PRODUCTS 2 3 2.01 STEEL MATERIALS

4 A. Material for galvanizing to be geometrically suitable for galvanizing as specified 5 in ASTM A 384 and A 385. Steel Materials suitable for galvanizing include 6 structural shapes, pipe, sheet, fabrications, and assemblies.

7 B. Material to be chemically suitable for galvanizing.

8 2.02 IRON AND STEEL HARDWARE

9 A. Bolts, nuts, washers, and items of iron and steel hardware furnished for 10 galvanizing to be suitable for hot-dip galvanizing.

11 B. Inspect iron and steel hardware before galvanizing and ascertain whether 12 suitable for galvanizing. Replace items which are not suitable for galvanizing.

13 2.03 ZINC FOR GALVANIZING

14 A. Conform with ASTM B 6, and specified in ASTM A 123.

15 2.04 GALVANIZING

16 A. Steel members, fabrications, and assemblies to be galvanized after fabrication, 17 by hot-dip process in accordance with ASTM A 123. Weight of zinc coating to 18 conform to requirements specified under “Weight of Coating” in ASTM A 123.

19 B. Safeguard against steel embrittlement in conformance with ASTM A 123.

20 C. Safeguard against warpage or distortion of steel members to conform with 21 ASTM A 384. Notify the Engineer of potential warpage problems which may 22 require modification in design, before proceeding with steel fabrications.

23 D. Finish and uniformity of zinc coating and adherence of coating to conform with 24 ASTM A 123, A 153, or A 386, as applicable.

25 E. Bolts, nuts, and washers, and iron and steel hardware components to be 26 galvanized in accordance with ASTM A 153. Weight of zinc coating to conform 27 to requirements specified under “Weight of Coating” in ASTM A 153. Nuts to be 28 tapped after galvanizing to minimum diametral amounts specified in ASTM A 29 563. Coat nuts with waterproof lubricant, clean and dry to touch. High strength 30 bolts for structural steel joints to be galvanized in accordance with ASTM A 325.

31 2.05 PASSIVATING

32 A. Galvanized materials subject to extended periods of storage in open, exterior 33 locations to be given passivating treatment or light oiling to prevent humid 34 storage stain. Treatment, solution and process subject to review and 35 acceptance by the Engineer. Chromate passivation should not be used on 36 items galvanized after fabrication which are to be painted after erection.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 162 SKAGIT COUNTY PUBLIC WORKS SECTION 050300 STREET WASTE FACILITY GALVANIZING

1 2.06 PRESERVATIVE OILS

2 A. Do not treat freshly galvanized or passivated surfaces with oils, grease, or 3 chemicals which might interfere with adhesion of subsequent paint primers and 4 coatings.

5 Part 3 – EXECUTION 6 7 3.01 INSTALLATION OF STEEL MATERIALS

8 B. Steel materials, fabrications, and assemblies are to be installed as shown on the 9 Drawings or specified.

10 3.02 FIELD INSPECTION

11 A. Inspect installed galvanized materials, fabrications, and assemblies in 12 accordance with the applicable requirements of AHDGA “Inspection Manual for 13 Hot-Dip Galvanized Products,” for visual inspection.

14 3.03 TOUCH UP AND REPAIR

15 A. Repair damaged galvanized surfaces in accordance with ASTM A 780.

16 B. Dry film thickness of applied repair materials to be not less than galvanized 17 coating thickness required by ASTM A 120, A 123, A 153, as applicable.

18 C. Touch up primed-painted surfaces with same galvanized primer applied in shop. 19 Clean damaged surfaces first to assure proper paint adhesion.

20

21 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 163 SKAGIT COUNTY PUBLIC WORKS SECTION 051200 STREET WASTE FACILITY STRUCTURAL STEEL

1 Part 1 – GENERAL

2 1.01 SUMMARY

3 A. Section Includes: 4 1. Structural steel. 5 2. Bolts. 6 3. Anchor Bolts.

7 1.02 REFERENCES

8 A. Comply with the following list of standards referenced in this Section.

9 B. ASTM International – www.astm.org: 10 1. ASTM A 36 – Standard Specification for Carbon Structural Steel. 11 2. ASTM A 53 – Standard Specification for Pipe, Steel, Black and Hot-Dipped, 12 Zinc-Coated Welded and Seamless. 13 3. ASTM A123 – Standard Specification for Zinc (Hot-Dip Galvanized) 14 Coatings on Iron and Steel Products. 15 4. ASTM A 307 – Standard Specification for Carbon Steel Bolts and Studs, 60 16 000 PSI Tensile Strength. 17 5. ASTM A 325 – Standard Specification for Structural Bolts, Steel, Heat, 18 Treated 120/105 ksi Minimum Tensile Strength. 19 6. ASTM A 500 – Standard Specification for Cold-Formed Welded and 20 Seamless Carbon Steel Structural Tubing in Rounds and Shapes. 21 7. ASTM A780 – Standard Practice for Repair of Damaged and Uncoated 22 Areas of Hot-Dip Galvanized Coatings. 23 8. ASTM A992 – Standard Specification for Steel Shapes. 24 9. ASTM B6 – Standard Specification for Zinc.

25 1.03 SUBMITTALS

26 A. Shop Drawings: All fabricated metals illustrating dimensions, erection details, 27 cuts, copes, connections, holes, threaded fasteners, and welds. Base 28 dimensional data on actual field measurements where connections interface 29 with other materials required.

30 B. Mill Test Reports: Submit mill test reports for each shipment of materials or 31 products.

32 1.04 QUALITY ASSURANCE

33 A. Materials, Fabrication, and Erection: Conform with the latest edition of AISC 34 Specification for the Design, Fabrication, and Erection of Structural Steel for 35 Buildings.

36 B. Welding: By operators qualified by tests as prescribed by the AWS in Standard 37 Qualification Procedure for performance of the type of work required. Structural 38 welding shall be performed by welders certified by WABO or local building 39 department jurisdiction.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 164 SKAGIT COUNTY PUBLIC WORKS SECTION 051200 STREET WASTE FACILITY STRUCTURAL STEEL

1 1.05 DELIVERY, STORAGE, AND HANDLING

2 A. Delivery of Materials Installed Under Other Sections: 3 1. Deliver anchor bolts, anchorage devices, sleeves and other steel to be 4 embedded in cast-in-place concrete prior to start of concrete work. 5 2. Provide setting drawings, templates, and direction for installation of anchor 6 bolts and other devices.

7 B. Store above grade. Protect from corrosive elements.

8 C. Handle and store during construction to prevent overstressing any elements.

9 Part 2 – PRODUCTS

10 2.01 MATERIALS

11 A. Structural Steel: 12 1. All new material, clean and free from damage: 13 a) Other rolled shapes, bars, and plates - ASTM A36, unless otherwise 14 noted on drawings. 15 b) Steel pipe – ASTM A53.

16 B. Bolts: 17 1. Standard bolts and nuts - ASTM A307. 18 2. Anchor bolts – ASTM A307.

19 C. Welding Electrodes: AWS E70XX.

20 D. Galvanizing: Hot-Dip Galvanize all embedded and exposed assembled steel 21 work or products including bolts, fasteners and hardware unless otherwise 22 noted in conformance with ASTM B6 and ASTM A123.

23 E. Shop Paint Primer: Prime assembled steel compatible with finish specified.

24 2.02 FABRICATION

25 A. Fabricate structural and architectural steel in accordance with the appropriate 26 AISC Specifications with the modifications and additional requirements specified 27 in this section.

28 B. Weld all shop connections unless otherwise noted. 29 1. Conform to AWS Code for Arc Welding in Building Construction. 30 2. Remove all weld splatter from exposed surfaces.

31 C. Straightness of Structural Members: Straightness of structural members and 32 fabricated assemblies shall conform to AISC specification. Straighten 33 galvanized items after galvanizing. 34

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 165 SKAGIT COUNTY PUBLIC WORKS SECTION 051200 STREET WASTE FACILITY STRUCTURAL STEEL

1 D. Shop Assembly: 2 1. Fabricate units in as large parts and sections as practicable. 3 2. Holes in members: Punch or drill as necessary to receive bolts and similar 4 items. Do not cut holes with a torch.

5 Part 3 – EXECUTION

6 3.01 ERECTION

7 A. Set and secure structural steel members and appurtenant connections 8 accurately to the required lines and levels shown on drawings.

9 B. All procedures and tolerances per AISC Standards and Specifications.

10 C. Bolts, Anchors and Other Accessories: Install as necessary and as required for 11 erection of structural steel.

12 D. Anchor Bolts and Anchors: Locate and build into connecting work. Preset 13 anchor bolts and anchors attached to templates of configuration required for 14 fastening to structural members.

15 E. Repairing Galvanizing: Repair damaged galvanized surfaces in accordance 16 with ASTM A780. 17 18 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 166 SKAGIT COUNTY PUBLIC WORKS SECTION 055000, Page 167 STREET WASTE FACILITY METAL FABRICATION

1 Part 1 – GENERAL 2 3 1.012 SUMMARY

4 D. Section Includes:

5 1. Structural Steel

6 1.013 QUALITY ASSURANCE

7 A. Materials, Fabrication, and Erection: Conform with the latest edition of AISC 8 Specification for the Design, Fabrication, and Erection of Structural Steel for 9 Buildings.

10 B. Materials, Fabrication, and Erection: Conform with the latest editions of 11 “Aluminum Construction Manual” and all applicable standards and data as set 12 forth by the Aluminum Association.

13 C. Welding: By operators qualified by tests as prescribed by the AWS in Standard 14 Qualification Procedure for performance of the type of work required. Structural 15 welding will require all welders to be certified by WABO or local building 16 department jurisdiction.

17 D. Comply with OSHA and Building Code requirements.

18 1.014 SUBMITTALS

19 A. Shop Drawings: All fabricated metals illustrating dimensions, erection details, 20 cuts, copes, connections, holes, threaded fasteners, and welds. Base 21 dimensional data on actual field measurements where connections interface 22 with other materials required.

23 B. Mill Test Reports: Submit mill test reports for each shipment of materials or 24 products.

25 1.015 PRODUCT DELIVERY, STORAGE AND HANDLING

26 A. Deliver, store and handle materials in such a manner as to prevent damage to 27 finished surfaces.

28 B. Store above grade in clean dry locations. Protect from corrosive elements.

29 C. Handle and store during construction to prevent overstressing any elements.

30

31 Part 2 – PRODUCTS 32 33 2.01 STRUCTURAL STEEL: Conform to Section 051200.

34 A. All steel shall be galvanized unless otherwise specified.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 167 SKAGIT COUNTY PUBLIC WORKS SECTION 055000, Page 168 STREET WASTE FACILITY METAL FABRICATION

1 2.02 STEEL PIPE RAILING

2 A. Fabricated of 1½-inch steel pipe conforming to ASTM A 53, Grade A, Type E or 3 S.

4 B. All posts and rails shall be fabricated of schedule 40 pipe.

5 C. All connections shall be welded, ground smooth and galvanized after fabrication. 6 Field welds shall be galvanized with Galvweld.

7 D. Maximum spacing of posts shall be 6 feet.

8 E. Toe boards consisting of ¼-inch-thick by 4 inches high steel plate with a 1-inch 9 lip on top and bottom shall be provided on all exposed sides of all floor openings 10 above space occupied by people and where indicated on the plans. Not more 11 than ¼-inch clearance shall be permitted between toe board and floor level.

12 F. At openings in handrail, provide chain across opening unless otherwise noted. 13 Chain for use in conjunction with hand railing shall be common chain 14 galvanized, trade size ¼-inch inside, length 1 inch, 12 links per foot, weighing 60 15 lbs per 100 feet. Provide stainless steel eyehooks and half eyes as required.

16 G. Handrailing shall be OSHA and WISHA approved.

17 2.03 FABRICATION

18 A. Fabricate in accordance with the Drawings and additional requirements 19 specified in this section.

20 B. Shop Assembly:

21 2. Fabricate units in as large parts and sections as practicable.

22 3. Holes in Members: Punch or drill as necessary to receive bolts and 23 similar items. Do not cut holes with a torch. Provide adequate 24 fastenings for wood nailers and similar items.

25 4. Close all ends of pipe railing or hand rail with post terminal or cap with 26 hemispherical caps of approved design.

27 C. Galvanize all steel including bolts, fastenings, and hardware unless otherwise 28 noted.

29 Part 3 – EXECUTION 30 31 3.01 ERECTION

32 A. Set and secure accurately to the required lines and levels shown on Drawings.

33 B. Protect the finish from scratches, nicks, and dents during erection.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 168 SKAGIT COUNTY PUBLIC WORKS SECTION 055000, Page 169 STREET WASTE FACILITY METAL FABRICATION

1 C. Handrail:

2 1. Install true to line and grade. Fabricated elements and in place 3 elements centerline not to exceed a variation greater than 1/16 inch from 4 design line and grade at any point.

5 2. Pipe may be fastened to concrete by floor or wall flanges or by dry 6 packing into concrete.

7 D. Repairing Galvanizing: As specified in Section 050300.

8 E. Anchor Bolts and Anchors: Locate and build into connecting work. Preset 9 anchor bolts and anchors attached to templates of configuration required for 10 fastening to structural members.

11 F. Grouting: After all structural members have been properly positioned and all 12 bolts and anchor bolts tightened, place grout between concrete and metal. 13 Finish exposed surfaces flush and smooth.

14

15 END OF SECTION

16

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 169 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 PART 1 - GENERAL 2 3 1.01 DESCRIPTION

4 A. This section specifies general requirements for electrical work; furnishing and 5 installation of all raceways, fittings, wireways, and boxes; process 6 instrumentation requirements; conductors and cables rated 600V, and less, 7 used for scheduled power, signal, data and control circuits; and miscellaneous 8 electrical control, power devices and disconnect switches.

9 1.02 SUBMITTALS

10 A. CONTRACTOR RESPONSIBILITIES:

11 1. Be responsible for the accuracy and completeness of the information 12 contained in each submittal.

13 2. Verify that the material and equipment described in each submittal 14 conforms to the requirements of the Contract prior to submittal.

15 3. Ensure that the material, equipment and methods of work used shall 16 be as described in the submittal.

17 4. Ensure there is no conflict with other submittals. Notify the Engineer 18 where such submittal may affect the work of another submittal.

19 5. Ensure coordination of submittals among the suppliers, related crafts, 20 subcontractors, and with the planned work.

21 6. Call out all deviations, substitutions or approved equals as defined in 22 this section in the body of the submittal.

23 B. ITEMS TO BE SUBMITTED FOR THIS SPECIFICATION:

24 1. Catalog cuts of all equipment, devices, and materials provided under this 25 specification section. Catalog information shall include technical 26 specifications and application information, including ratings, range, 27 weight, accuracy, etc. Catalog cuts shall be edited to show only the 28 items, model numbers, and information which apply. Catalog cuts shall 29 be assembled in a folder with a cover sheet, indexed by item, and cross 30 referenced to the appropriate specification paragraph.

31 2. The design specified in the Contract Drawings and this specification 32 section is based on manufacturers and product numbers as indicated in 33 these specifications, and on the Contract Drawings. If the Contractor 34 submits a design differing from what is specified the Contractor shall 35 submit a marked up copy of this specification and submit revised 36 drawings depicting all changes required to the Contract Documents.

37 3. Test results for electrical system tests specified in this section.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 170 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 4. A copy of this specification section, with addendum updates included, 2 and all referenced and applicable sections, with addendum updates 3 included, with each paragraph check-marked to indicate specification 4 compliance or marked to indicate requested deviations from 5 specification requirements. Check marks shall denote full compliance 6 with a paragraph as a whole. If deviations from the specifications are 7 indicated, and therefore requested by the Contractor, each deviation 8 shall be underlined and denoted by a number in the margin to the right 9 of the identified paragraph, referenced to a detailed written 10 explanation of the reasons for requesting the deviation.

11 The Engineer shall be the final authority for determining acceptability 12 of requested deviations. The remaining portions of the paragraph not 13 underlined will signify compliance on the part of the Contractor with 14 the specifications.

15 Failure to include a copy of the marked-up specification sections, 16 along with justification(s) for any requested deviations to the 17 specification requirements, with the submittal shall be sufficient cause 18 for rejection of the entire submittal with no further consideration.

19 5. A copy of the Contract Drawings with addendum updates included, 20 edited to depict any required changes resulting from the Contractor’s 21 locating of existing underground utilities as specified herein.

22 6. Wiring diagrams for systems installed or modified.

23 C. PRODUCT DATA: The following information and product data specified under 24 this specification section shall be provided:

25 1. Applicable operation and maintenance information on an item-by-item 26 basis. Operation and maintenance information shall be provided at 27 the time of equipment, device, or material site delivery, Full-size 28 drawings shall be reduced to 11 x 17 inches.

29 2. Test results for electrical systems specified in this section. A file of the 30 original test results shall be maintained by the Contractor. Prior to 31 acceptance of work, the resulting file shall be provided to the 32 Engineer.

33 1.03 QUALITY ASSURANCE

34 A. REFERENCES: This Section incorporates by reference the latest revisions of 35 the following documents. They are part of this Section. In case of conflict 36 between the requirements of this Section and the listed documents, the 37 Contractor shall point out the conflict to the Engineer; lacking a definitive answer 38 otherwise, the requirements of the Contract Specifications shall prevail. If 39 referenced documents have been discontinued by the issuing organization, 40 references to those documents shall mean the replacement documents issued 41 or otherwise identified by that organization or, if there are no replacement 42 documents, the last version of the document before it was discontinued.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 171 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 1. ANSI C80.1, Rigid Steel Conduit-Zinc Coated

2 2. ASTM B3 Soft or Annealed Copper Wire

3 3. ASTM B33 Tinned Soft or Annealed Copper Wire for Electrical Purposes

4 4. ASTM B8 Concentric-Lay-Stranded Copper Conductors, Hard, Medium- 5 Hard, or Soft

6 5. ASTM F512, Smooth-Wall Polyvinylchloride Conduit and Fittings for 7 Underground Installation

8 6. IBC International Building Code

9 7. NECA-1, National Electrical Contractors Association – Standard 10 Practices for Good Workmanship in Electrical Contracting

11 8. NFPA, National Fire Protection Association

12 9. NFPA-70, National Electrical Code

13 10. NFPA-70E, National Electrical Safety Code

14 11. FEDSPEC WW-C-581E, Conduit, Metal, Rigid and Intermediate; and 15 Coupling, Elbow, and Nipple, Electrical Conduit; Zinc Coated

16 12. FEDSPEC W-C-1094A, Conduit and Conduit Fitting Plastic, Rigid

17 13. NEMA RN 1, Polyvinyl-Chloride (PVC) Externally Coated Galvanized 18 Rigid Steel Conduit And Intermediate Metal Conduit

19 14. NEMA TC6, PVC and ABS Plastic Utilities Duct for Underground 20 Installation

21 15. NEMA WC7 Cross-Linked-Thermosetting Insulated Wire and Cable for 22 the Transmission and Distribution of Electric Energy

23 16. UL 1, Flexible Metal Electrical Conduit

24 17. UL 6, Rigid Metal Electrical Conduit

25 18. UL 44 Rubber-Insulated Wires and Cables

26 19. UL 83 Thermoplastic-Insulated Wires and Cables

27 20. UL 360 Liquid Tight Flexible Electrical Conduit

28 21. UL 514 Nonmetallic Outlet Boxes, Flush-Device Boxes and Covers

29 22. UL 651, Rigid Nonmetal Electrical Conduit

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 172 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 B. IDENTIFICATION OF LISTED PRODUCTS: All materials and equipment 2 specified herein shall, within the scope of UL Examination Services, be 3 approved by the Underwriter's Laboratories for the purpose for which they are 4 used and shall bear the UL label. Equipment that is not available with the UL 5 label shall be listed by a Nationally Recognized Testing Laboratory agency 6 acceptable to the local Authority Having Jurisdiction. When a product is not 7 available with a testing laboratory listing for the purpose for which it is to serve, 8 the product may be required by the inspection authority, to undergo inspection at 9 the manufacturer's place of assembly. All costs and expenses incurred for such 10 inspections shall be included in the original contract price.

11 1.04 SITE CONDITIONS AND NEW AND EXISITNG UTILITIES

12 A. Search of known records and limited field investigations have been performed to 13 identify utilities which exist within the limit of work. However, the accuracy and 14 completeness of the utilities indicated on the drawings is not guaranteed and 15 may be incomplete. It shall be the responsibility of the Contractor to determine 16 the exact location of all utilities and their service connections. The Contractor 17 shall make his own investigation as to the location, type, kind of material age, 18 and condition of existing utilities which may be affected by the contract work and 19 in addition shall notify the Engineer of any utility located by him which have been 20 incorrectly shown or omitted from the drawings. The Contractor shall complete 21 the investigation and determine location of utilities prior to performing any 22 construction activities.

23 B. Coordinate the installation of underground raceways with existing piping and 24 raceways. All trench work shall be coordinated with other Division’s work. 25 Underground electrical conduit shall be kept 3' - 0" horizontally and 1' - 0" 26 vertically at crossings from other underground utilities except telephone. 27 Minimum cover shall be 2' - 0".

28 C. Corrosive Areas: Areas shall be considered as corrosive environments where 29 there is reasonable potential for exposure of equipment to water and moisture 30 ingress, and where corrosive vapors may be present. Corrosive environments 31 shall be defined as the following:

32 a. Decant Facility sump area

33 b. Outdoor, exposed installations

34

35 PART 2 - PRODUCTS

36 2.01 EQUIPMENT AND MATERIALS

37 A. Equipment and materials shall be new and free from defects. All material and 38 equipment of the same or a similar type shall be of the same manufacturer 39 throughout the work. Standard production materials shall be used wherever 40 possible. All electrical and instrumentation materials shall conform to all 41 applicable local, state, and federal codes, standards, and requirements. Where

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 173 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 specifications listed herein conflict with any local, state or federal codes, 2 standard or requirement, the applicable code, standard, or requirement shall 3 take precedent

4 2.02 WIRE MARKERS

5 A. GENERAL

6 1. Each power, control and signal conductor shall be identified at each 7 terminal to which it is connected.

8 2. Conductors shall have identification sleeves, adhesive strips are not 9 acceptable. The Contractor shall determine appropriate identification 10 labels that are consistent with existing conductor labeling scheme.

11 3. The letters and numbers that identify each wire shall be machine printed 12 on sleeves in permanent black ink with figures 1/8 inch high.

13 4. Sleeves shall be yellow or white tubing and sized to fit the conductor 14 insulation. Shrink the sleeves with hot air after installation to fit the 15 conductor.

16 B. ACCEPTABLE MANUFACTURERS: Candidate manufacturers include TMS 17 Thermofit Marker System by Raychem Co, Sleeve style wire marking system by 18 W. H. Brady Co, Sleeve style wire marking by Panduit, or approved equal.

19 2.03. RACEWAY MARKERS

20 A. Identify installed conduit with raceway marker tags.

21 B. Tags shall be laser engraved with two lines identifying termination locations of 22 the raceway, one per line.

23 C. 3/16-inch minimum character height.

24 D. Material: 22 gauge, 316 Stainless Steel.

25 E. Attached to the raceway with 316 stainless steel wire.

26 2.04 NAMEPLATES

27 A. Nameplates shall be provided for all electrical equipment and boxes.

28 B. Where no wording is specified, the Contractor shall provide the functional 29 description of the device on the nameplate.

30 C. Nameplates shall be made from laminated phenolic plastic. Outdoor nameplates 31 shall be UV resistant.

32 D. Nominal size: 3/4 inch high by 2 inches long.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 174 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 E. Black backgrounds with 3/16-inch white letters. Fastened using self-tapping 2 stainless steel screws.

3 2.05 CONDUIT AND SUPPORTS

4 A. GENERAL

5 1. Raceway Types and Size shall be as identified on drawings and as 6 specified in this specification section.

7 2. Provide plastic bushings at all raceway terminations to prevent 8 conductor damage as conductors exit raceway.

9 3. Terminate all conduits that enter enclosures by fittings that ensure that 10 the NEMA rating of the enclosure is not affected or changed.

11 4. Individual conduit supports shall be stainless steel one-hole pipe straps 12 used with clamp backs and nesting backs where required. Where 13 routed along walls, conduit shall be supported a minimum of every 10 14 feet. Stainless steel rods, hangers and hardware shall be provide for all 15 installation locations.

16 5. Table A identifies the type of raceway required for each location and 17 application. Raceway types are specified in Paragraph 2.05-B, below. 18 Unscheduled conduit shall be rigid steel conduit, type GRS.

19 Table A

Location Application/Condition RACESPEC Indoor, noncorrosive Exposed GRS Indoor, corrosive Exposed PGRS Outdoor Exposed PGRS Underground Power circuits encased in concrete duct PVC4 bank or direct-buried 20

21 B. RACEWAY TYPES

22 1. GRS-Galvanized Rigid Steel Conduit

23 a. Compliance: ANSI C80.1 and UL 6

24 b. Finish: GRS shall be hot- dip galvanized after fabrication, inside 25 and outside. Smooth finished surfaces.

26 c. Minimum size: ¾ inch

27 d. Fittings and Hubs: Provide galvanized fittings. Threadless 28 fittings are not acceptable. Hubs for connection of conduit to

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 175 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 junction, device, or terminal boxes shall be threaded and made 2 of cast ferrous alloy. Hubs shall be galvanized steel and have 3 insulating bushings. The hubs shall utilize a neoprene O-ring 4 and shall provide a watertight connection.

5 f. Boxes: Type and enclosure rating as specified on the Contract 6 Drawings and in this Section.

7 g. Manufacturers: Conduit shall be Allied Tube and Conduit Corp., 8 Wheatland Tube Co., or equal. Fittings shall be Appleton, 9 Crouse-Hinds, Hubbell, or equal.

10 h. Installation: Rigid steel conduit shall be made up tight and with 11 conductive thread compound. Joints shall be made with 12 standard couplings or threaded unions. Steel conduit shall be 13 supported away from the structures using hot-dip galvanized 14 malleable iron straps with nesting backs or framing channel. 15 Conduit entering boxes shall be terminated with a threaded hub 16 with a grounding bushing. Exposed male threads on rigid steel 17 conduit shall be coated with zinc-rich paint.

18 2. PGRS-Rigid Steel Conduit, Corrosion-Resistant, Polyvinyl Chloride-PVC 19 Coated:

20 a. Compliance: ANSI C80.1, UL 6, NEMA RN1

21 b. Finish: PGRS shall be hot dipped galvanized rigid steel conduit. 22 The inside and outside, as well as the threads shall be 23 galvanized. A minimum 40-mil-thick PVC coating shall be 24 bonded to the outside of the conduit and the inside shall be 25 coated with 2-mil urethane. Coating shall be free of pinholes. 26 Bending of conduit shall not damage either the interior or exterior 27 coating. Bond strength shall exceed the tensile strength of the 28 PVC coat. Elbows shall be factory made and coated

29 c. Minimum size: ¾ inch.

30 d. Fittings: Similarly coated to the same thickness as the conduit 31 and provided with Type 316 stainless steel hardware. A 2-mil 32 urethane coating shall be applied to the interior, and the threads 33 of all fittings and couplings.

34 e. Hubs: Hubs for connection of conduit to junction, device, or 35 terminal boxes shall be threaded and made of cast ferrous alloy. 36 Hubs shall be galvanized steel and have insulating bushings. 37 The hubs shall utilize a neoprene O-ring and shall provide a 38 watertight connection.

39 f. Boxes: Type and enclosure rating as specified on the Contract 40 Drawings and in this Section.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 176 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 g. Manufacturers: Conduit shall be Robroy Industries, Plasti-Bond, 2 Perma-Cote, KorKap or equal. Fittings shall be by same 3 manufacturer as conduit.

4 h. Installation: PVC coated conduit shall be supported away from 5 the structure using PVC coated conduit wall hangers. All conduit 6 threads shall be covered by a plastic overlap which shall be 7 coated and sealed per manufacturer’s recommendations. 8 Plastic-coated conduit shall be made tight with special wrenches 9 and fittings designed for tightening PVC coated conduit. Pipe 10 wrenches and channel locks shall not be used for tightening 11 plastic-coated conduits. Damaged areas shall be patched, using 12 manufacturer’s recommended material. The area to be patched 13 shall be built up to the full thickness of the coating. Painted 14 fittings are not acceptable.

15 3. PVC4-Rigid Nonmetallic Conduit, Schedule 40 PVC, High-Impact 16 Polyvinylchloride

17 a. Compliance: NEMA TC2, UL 651

18 b. Minimum Size: 1 inch

19 c. Fittings: PVC solvent weld type.

20 d. Boxes: Nonmetallic NEMA Class 4X.

21 e. Installation: PVC conduit entering fiberglass boxes or cabinets 22 shall be secured by threaded bushings on the interior of the box 23 and shall be terminated with a threaded male terminal adapter 24 having a neoprene O ring. Joints shall be made with standard 25 PVC couplings. PVC conduit shall have bell ends where 26 terminated at walls and boxes.

27

28 2.06 CONDUCTORS, WIRE AND CABLE

29 A. GENERAL

30 1. Conductor, wire and cable types and size shall be as identified on 31 drawings and as specified in this specification section.

32 2. All conductors shall be copper unless otherwise specified.

33 3. Conductors shall be continuous from termination to termination.

34 4. All conductors shall be installed in conduit.

35 5. Where not specified on the Drawings, conductors and cables shall be 36 sized in accordance with the National Electrical Code for the particular 37 equipment served. Provide stranded conductors for all cable or wires.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 177 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 Provide minimum conductor size of 12 AWG for power and lighting 2 circuits and minimum conductor size of 14 AWG for control circuits.

3 6. Factory cable between manufactured instrument system components 4 shall be provided in compliance with the instrument manufacturer's 5 recommendations.

6 B. SPLICING AND TERMINATING MATERIALS

7 1. Connectors shall be tool applied compression type of correct size and 8 UL listed for the specific application. Connectors shall be tin-plated high 9 conductivity copper. Wire nuts for a splice are prohibited.

10 2. Signal and control conductors shall be connected to terminal blocks and 11 field devices and instruments shall be terminated with conductor 12 terminals.

13 C. CONDUCTOR, WIRE AND CABLE TYPES

14 1. XHHW-2-Single Conductor Cross-Linked Polyetheylene Power and 15 Control Cable:

16 a. Voltage: 600V.

17 b. Conductor Material: Bare annealed copper; stranded in 18 accordance with ASTM B8.

19 c. Insulation: XHHW-2, 90 degree C dry, 75 degree C wet, cross- 20 linked polyethylene in accordance with ICEA S-66-524.

21 d. Manufacturers: Okonite X-Olene, Southwire, Cablec Durasheath 22 X L P, o r approved equal.

23 2.07 MAGNETIC FLOW METERING SYSTEM

24 A. GENERAL

25 1. Description: Magnetic flow meter provided as a system consisting of a 26 flow tube meter with integral mounted junction box with separate remote 27 mounted amplifier and data acquisition/recording unit.

28 2. System shall be suitable for measuring industrial decant water.

29 3. Signal Input: Process

30 4. Signal Output: 4-20mA automatically scaled to provide 4 mA at lower 31 range value and 20 mA at upper range value. Full scale continuously 32 adjustable between 0.10 and 39 ft. /s, 1 ft. /s (0.3 m/s) minimum span.

33 5. Remote mounted flow meter amplifier for full-scale flow rates from 1.0 to 34 30 feet per second. System error shall not exceed the greater of 0.5 35 percent of flowrate or 0.1 foot per second from 2 to 30 feet per second.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 178 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 B. FLOW TUBE

2 1. Process Connection: Flange, ANSI B16.5, ANSI Class 150, Stainless 3 Steel. Provide gaskets between flow tube, grounding rings, and pipeline 4 flanges.

5 2. Electrode Material: 316L Stainless Steel

6 3. Flow Range: 0.1-39 feet per second.

7 4. Grounding: Ground per manufacturer’s recommendations. Provide 8 grounding rings connected to the flow tube flanges by grounding straps, 9 #12 AWG copper wire, locate gaskets on both sides of grounding rings, 10 ground to solid earth ground.

11 5. Liner: Appropriate for Application, polytetrafluoroethylene or chemical 12 resistant hard rubber.

13 6. Coil Power: Pulsed DC from amplifier.

14 7. Manufacturer: Badger Meter M2000, Endress & Hauser Promag 53W, 15 ABB Magmaster MFE, or approved equal.

16 C. AMPLIFIER/TRANSMITTER:

17 1. Description: Remote Mount Signal converter/transmitter shall be suitable 18 for an adjustable full-scale flow within the limits of from 1 to 39 feet per 19 second.

20 2. Enclosure: Rating NEMA-4X

21 3. LCD Display: 4x20 character display with backlight.

22 4. Power Supply: 120V AC Power Supply

23 5. Mounting: Remotely mounted from flow tube. Provide suffcient cable for 24 the connection between Amplifier and Flow Tube.

25 6. Analog Output: 4-20mA

26 7. Low Flow Cutoff, programmable

27 8. High/Low Flow alarm.

28 9. Fuses: 2 amps, per manufacturer’s recommendation. Provide one spare 29 set of fuses.

30 10. Manufacturer: Badger Meter M2000, Endress & Hauser Promag 53W, 31 ABB Magmaster MFE, or approved equal.

32

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 179 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 2.08 BOXES, GUTTERS, TERMINAL CABINETS, MANHOLES, AND HANDHOLES

2 A. Unless otherwise specified boxes shall be NEMA 4X stainless steel. Provide 3 Type 316L (low carbon), 317, or Type 316 stainless products where specified. 4 Enclosure constructed of mild sheet steel shall be hot-dipped galvanized after 5 fabrication. Hinges shall be continuous type and for NEMA-4X cabinet’s hinges 6 shall be stainless steel.

7 B. Boxes and enclosures shall be provided with neoprene gaskets on the hinged 8 doors or removable covers. Box and gutter sizes, metal thickness, and 9 grounding shall comply with the National Electrical Code.

10 C. Nameplates shall be provided for boxes. Nameplate shall provide the functional 11 description of the device and or circuits located within box.

12 D. HANDHOLES: Handholes shall be pre-cast polymer concrete type with solid 13 bottoms and gasketed covers. Stacked boxes shall have gasketed joints. 14 Manufactured by Hubbell Power Systems, Oldcastle, Armorcast, or equal. 15 16 2.09 MOLDED CASE CIRCUIT BREAKER

17 A. GENERAL

18 1. Molded-case type provided for the current ratings and pole 19 configurations specified on the panelboard schedule. Interrupting 20 ratings shall be inherent breaker ratings. Interrupting ratings based on 21 series rated circuit breakers are not acceptable. Interrupting ratings shall 22 match ratings of existing breakers in Panelboard A.

23 2. Contractor shall provide circuit breakers which match type, voltage and 24 interrupting rating of circuit breakers in existing Panelboard A. Ampacity 25 shall be as indicated on the Contract Drawings.

26 B. MANUFACTURER

27 1. Square D EGB. No equal.

28 2.10 SELECTOR SWITHCES

29 Selector switches shall have maintained position contacts. Switches shall be provided 30 with contact blocks and number of positions as required performing the specified or 31 indicated operations. Field instruments shall have a lock-out style selector switch for 32 locking on or locking off the 120VAC power source. The selector switch shall be two- 33 position, maintained contact, mounted in a NEMA 4X control station with locking cover. 34 35 1. UL Listed. 36 37 2. Dielectric Strength: 1300 Volts for one minute for Logic Reed contacts, 2200 38 Volts for one minute for other contacts. 39 40 3. 30.5mm mounting hole.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 180 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 2 4. Temperature operating range –10 degree C. to +55 degree C. 3 4 5. Standard knob operator (not lever type nor wing lever type) 5 6 6. Number of positions and contact configuration as shown on Drawings. 7 8 7. Furnish contacts with NEMA Utilization Category rating A600 rated not less than 9 10 amperes continuous and 6 amperes break at 120 Vac. 10 11 8. Manufacturer: Allen-Bradley, Eaton, Square D, or equal. 12 13 14 PART 3 - EXECUTION

15 3.01 GENERAL

16 A. CONSTRUCTION:

17 1. Perform the work specified by Contract Documents in accordance with 18 these specifications.

19 2. Coordinate the location of electrical material or equipment with the work 20 and adjust conduit location to accommodate equipment in accordance 21 with the accepted submittal drawings from the manufacturer.

22 3. Miscellaneous electrical materials, hardware and commodity items not 23 identified in these specifications but which are required for a code 24 compliant and/or neat and workmanlike installation shall be provided. 25 Provided materials and items shall comply with industry standards. 26 Unless otherwise specified supports, structural attachments, fittings, 27 strut and accessories shall be Steel, Hot Dipped Galvanized after 28 fabrication. Unless otherwise specified hardware including but not limited 29 to nuts, bolts, washers, and fasteners shall be Steel, Hot Dipped 30 Galvanized after fabrication or Type 316 stainless steel.

31 4. Electrical layout drawings are diagrammatic, unless otherwise detailed 32 or dimensioned. The Contractor shall coordinate the location of 33 electrical material or equipment with the work.

34 5. Minor changes in location of electrical material or equipment made prior 35 to installation shall be made at no cost to the Agency.

36 6. The Contractor shall inform the Engineer of any required power outages 37 necessary to perform the work. Notification shall be made a minimum of 38 48 hours in advance. Loads fed from Panel DE shall be required to be 39 kept in service throughout construction. The Contractor shall request 40 direction from the Engineer if Panel DE is required to be without power 41 for more than 10 minutes for whatever reason.

42

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 181 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 B. HOUSEKEEPING

2 1. Refer to the National Electrical Contractors Association’s (NECA) 3 National Electrical Installation Standards (NEIS) for Standard 4 Practices for Good Workmanship in Electrical Contracting (NECA-1) 5 as a minimum baseline of quality and workmanship for installing 6 electrical products and systems that defines what is meant by “neat 7 and workmanlike” as required by the National Electrical Code Section 8 110-12. Specified requirements supersede NECA practices.

9 2. Protect electrical equipment from dust, water and damage. Cover the 10 exterior to keep dry.

11 3. Protect electrical equipment temporarily exposed to weather, debris, 12 liquids, or damage during construction.

13 4. Clean equipment prior to acceptance testing and energization and 14 again prior to detailed inspection and acceptance of the work.

15 C. INSTALLATION:

16 1. Splices are not allowed except by permission. Splices and 17 terminations are subject to inspection prior to and after insulating and 18 may require re-termination after inspection.

19 2. Adhere to the NEC raceway fill limitations. Provide separate conduits 20 for for power and signal/instrument conductors and cables.

21 3. The Contractor shall note that the electrical installation shown on the 22 Drawings is based on the equipment as specified in this Section. If 23 alternative equipment that is provided under this Contract varies in 24 requirements, size or layout from the specified equipment, the 25 Contractor shall be responsible for any costs associated with the 26 variances in electrical equipment requirements including wiring, circuit 27 breakers, disconnects and conduits. Any costs for engineering 28 required for the variances in layout shall also be the Contractor’s 29 responsibility.

30 4. Where not in direct conflict with these specifications install vendor 31 supplied cable per vendor specifications.

32 D. CONDUCTOR, WIRE, AND CABLE INSTALLATION:

33 1. Identify conductors at each connection terminal and at splice points 34 with the identification as specified in this section.

35 2. Install wire and cable into raceways, conduit, cable trays, or wireways 36 without damaging or putting undue stress on the insulation or jacket. 37 Provide manufacture’s recommended and UL Listed pulling 38 compounds lubricants for pulling wire and cable. Grease is prohibited.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 182 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 3. Raceway construction shall be complete, cleaned, and protected from 2 the weather before cable is installed.

3 E. RACEWAY INSTALLATION:

4 1. Provide additional pullboxes not identified on the drawings for conduit 5 runs with greater than 360-degrees in any run between pull boxes. Limit 6 maximum conduit runs without additional pullboxes to 400 feet, less 50 7 feet for every 90 degrees for the conduit run change in direction.

8 2. Determine conduit routing that conforms to the installation 9 requirements set forth herein and in accordance with the NEC 10 requirements for size and number of pullboxes.

11 3. Install exposed conduit either parallel or perpendicular to structural 12 members and surfaces.

13 4. Exposed conduit shall be run on supports spaced not more than 10 feet 14 apart.

15 5. Raceway ends shall be capped during construction. Conduits in which 16 water or foreign matter have accumulated shall be thoroughly cleaned to 17 the satisfaction of the Engineer or be replaced.

18 6. Exposed threads on PGRS conduits located below grade shall be 19 coated in the field following installation.

20 7. Grout conduit into any openings cut into concrete and masonry 21 structures.

22 8. Exposed raceway mounted on painted structures shall be painted to 23 match structure color as close as possible.

24 9. Provide conduits with flashed and watertight seals routed through 25 roofs or metal walls.

26 10. Terminate conduits that enter enclosures with fittings that match the 27 NEMA rating of the enclosure.

28 11. Underground metallic or nonmetallic conduit that turn out of concrete, 29 masonry or earth: Install a 90-degree elbow of PVC-coated rigid steel 30 conduit before emergence above ground.

31 3.02 TESTING

32 A. Perform all testing for equipment and systems specified in this specification 33 consistent with the requirements of all applicable Codes, and the manufacturers’ 34 current Quality Assurance program.

35 B. Pre-test conductors prior to installation, as appropriate. Replace damaged 36 conductors. Megger test all power and control conductors after installation.

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 183 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 Provide completed test forms indicating test procedure, conductors under 2 test, and recorded test data. See sample test form at the end of this section.

3 C. Provide certified factory calibration testing and reports which duplicate, as 4 nearly as possible, conditions of operation. Include the name and address of 5 the laboratory that conducts the calibration testing for the Magnetic Flow 6 Metering System.

7 D. The installed Magnetic Flow Metering System shall be tested as an integrated 8 system. Check operation from field instrument to amplifier. If the output 9 control or monitoring device fails to indicate properly, corrections to the 10 circuitry or devices shall be made. The test shall be repeated until devices 11 and instruments operate as required. Correct circuitry and repeat the test until 12 the instruments operate properly.

13 3.03 RECORD DOCUMENTS

14 A. Contract documents shall be maintained and annotated by the Contractor during 15 construction. Include addendum items, requests for information, change 16 orders, and field changes posted or drawn on the Record Drawings. Include 17 the following drawings with the Record Drawings.

18 1. Interconnection Diagrams

19 2. Original Submittal Drawings

20 B. Schedule a meeting with the Engineer to review the Record Drawings at the end 21 of the project. Make corrections to the Record Drawings prior to re-submitting 22 the Record Drawings to the Engineer.

23 C. Submit Record Drawings and Operations and Maintenance (O&M) Manuals 24 to be included in the completed project Record Document Set for the Agency.

25 3.04 TRAINING

26 A. Contractor shall provide (1) 2-hour training on operation, use and 27 maintenance of installed flow meter system. Training shall be scheduled with 28 the Engineer. 29 30 3.05 TEST FORMS 31 32 The following sample test data forms are provided in this section for reference. The 33 Contractor shall provide completed test data forms documenting all required testing 34 in accordance with Section 3.02. 35 Form No. Title

16000-A Wire and Cable Resistance Test Data Form

16000-B Transmitter Calibration Test Data Form 36

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 184 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 A. WIRE AND CABLE RESISTANCE TEST DATA FORM 2 3 4 Wire or Cable No.: Temperature, oF: 5 6 7 Insulation resistance, Location of Test megohms 1.

2.

3.

4.

5.

6.

7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 CERTIFIED Date 25 Contractor's Representative 26 27 28 29 WITNESSED Date 30 Inspector 31 32 33

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 185 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 B. TRANSMITTER CALIBRATION TEST DATA FORM 2 3 4 Tag No. and Description: 5 6 Make & Model No.: Serial No.: 7 8 Input: 9 10 Output: 11 12 Range: Scale: 13 14 15 Simulate process variable (flow, pressure, temperature, etc.) and measure output with 16 appropriate meter. 17 % of Range Input Expected Actual Reading % Deviation Reading 0 50 100 % Deviation Allowed: 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 CERTIFIED Date 34 Contractor's Representative 35 36 37 38 WITNESSED Date 39 Inspector 40 41 42

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 186 SKAGIT COUNTY SECTION 16000 STREET WASTE FACILITY GENERAL REQUIREMENTS FOR ELECTRICAL WORK

1 END OF SECTION

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 187

[This page left blank intentionally.]

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 188

1 Appendices 2 (January 2, 2012)

3 The following appendices are attached and made a part of this contract: 4 5 APPENDIX A: 6 Standard Plans 7 8 APPENDIX B: 9 Prevailing Wage Rates (retrieved from Washington State Department of Labor 10 and Industries web page January 3, 2014) 11 12 APPENDIX C: 13 Washington State Department of Ecology Stormwater Grant Programs 14 Specifications Insert 15 16 APPENDIX D: 17 Construction Contract and Contract Bond 18 19 APPENDIX E: 20 Proposal 21 22 APPENDIX F: 23 Construction Quality Assurance Plan 24 25 APPENDIX G: 26 Vicinity Map and Plans 27 28 29

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 189

1 (January 6, 2014) 2 Standard Plans

3 The State of Washington Standard Plans for Road, Bridge and Municipal Construction M21- 4 01 transmitted under Publications Transmittal No. PT 13-037, effective August 5, 2013 is 5 made a part of this contract. 6 7 The Standard Plans are revised as follows: 8 9 A-50.10 10 Sheet 2 of 2, Plan, with Single Slope Barrier, reference C-14a is revised to C-70.10 11 12 A-50.20 13 Sheet 2 of 2, Plan, with Anchored Barrier, reference C-14a is revised to C-70.10 14 15 A-50.30 16 Sheet 2 of 2, Plan (top), reference C-14a is revised to C-70.10 17 18 B-10.20 and B-10.40 19 Substitute “step” in lieu of “handhold” on plan 20 21 B-25.20 22 Add Note 7. See Standard Specification Section 8-04 for Curb and Gutter requirements 23 24 B-90.40 25 Offset & Bend details, add the subtitle, “Plan View” above titles 26 27 C-16a 28 Note 1, reference C-28.40 is revised to C-20.10 29 30 C-16b 31 Note 3, reference C-28.40 is revised to C-20.10 32 33 C-20.10 34 All callouts for “W6 x 9 STEEL POST” are revised to read “W6 x 9 STEEL POST OR 6 x 35 8 TIMBER POST.” 36 37 Isometric View, callout, “W6 x 9 x 6’ LONG STEEL POST” is revised to read ““W6 x 9 x 38 6’ LONG STEEL POST OR 6 x 8 x 6’ LONG TIMBER POST.” 39 40 Add General Note 5. “All posts for any standard barrier run shall be of the same type: 41 timber or steel.” 42 43 C-20.40 44 All callouts for “W6 x 9 STEEL POST” are revised to read “W6 x 9 STEEL POST OR 6 x 45 8 TIMBER POST.” 46 47 C-20.42 48 The callout for “W6 x 9 STEEL POST” is revised to read “W6 x 9 STEEL POST OR 6 x 49 8 TIMBER POST.” 50 51

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 190

1 C-22.14 2 Section B, callout, “ 5/8” x 2” LONG BUTTON HEAD BOLT WITH 7/32” OVAL GRIP, 3 CUT WASHER, AND HEX NUT” is revised to read “ 5/8” x 2” LONG BUTTON HEAD 4 BOLT WITH 7/32” OVAL GRIP, CUT WASHER, AND HEX NUT FOR STEEL POST OR 5 5/8” x 10” LONG BUTTON HEAD BOLT WITH 7/32” OVAL GRIP, CUT WASHER, AND 6 HEX NUT FOR TIMBER POST” 7 8 C-22.16 9 Section B, callout, “ 5/8” x 2” LONG BUTTON HEAD BOLT WITH 7/32” OVAL GRIP, 10 CUT WASHER, AND HEX NUT” is revised to read “ 5/8” x 2” LONG BUTTON HEAD 11 BOLT WITH 7/32” OVAL GRIP, CUT WASHER, AND HEX NUT FOR STEEL POST OR 12 5/8” x 10” LONG BUTTON HEAD BOLT WITH 7/32” OVAL GRIP, CUT WASHER, AND 13 HEX NUT FOR TIMBER POST” 14 15 C-23.60 16 Add General Note 7. “Posts shall match those of connecting run: timber or steel.” 17 18 C-25.18 19 General Notes, Note 6 is revised to read “ Posts 1 and 2 are 10 x 10 timber or W6 x 15 20 steel posts ~ 7’ – 6” long. Posts 3 through 9 are 6 x 8 timber or W6 x 9 steel posts ~ 6’ – 21 0’ long..” 22 23 C-25.80 24 Add General Note 5. “All posts for any standard barrier run shall be of the same type: 25 timber or steel.” 26 27 C-70.10 28 Elevation, and Barrier Connection Detail, callout for premolded joint filler, revise ¼” to 29 3/8” Note 1, revise ¼” to 3/8”. 30 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 31 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 32 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 33 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 34 Standard Specification 6-10.3.” 35 36 C-75.10 37 Elevation, callout for premolded joint filler, revise ¼” to 3/8”, Note 1, revise ¼” to 3/8”. 38 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 39 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 40 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 41 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 42 Standard Specification 6-10.3.” 43 44 C-75.20 45 Elevation, callout for premolded joint filler, revise ¼” to 3/8”, Note 1, revise ¼” to 3/8”. 46 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 47 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 48 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 49 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 50 Standard Specification 6-10.3.” 51 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 191

1 C-75.30 2 Elevation, and Plan views, callout for premolded joint filler, revise ¼” to 3/8” ”, Note 1, 3 revise ¼” to 3/8”. 4 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 5 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 6 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 7 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 8 Standard Specification 6-10.3.” 9 10 C-80.10 11 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 12 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 13 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 14 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 15 Standard Specification 6-10.3.” 16 17 C-80.20 18 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 19 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 20 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 21 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 22 Standard Specification 6-10.3.” 23 24 C-80.30 25 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 26 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 27 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 28 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 29 Standard Specification 6-10.3.” 30 31 C-80.40 32 The Welded Wire Reinforcing Substitution Option Table is deleted. The note, “*Optional 33 Substitutions to Welded Wire Reinforcements shall conform to Standard Specification 34 Sections 6-10 and 9-07” is revised to read: “Steel Welded Wire Reinforcement 35 Deformed, for Concrete may be substituted for reinforcing steel in accordance with 36 Standard Specification 6-10.3.” 37 38 C-85.14 39 General Notes, Note 1, reference to Standard Plan C-13 is revised to C-70.10 40 41 C-85.15 42 General Notes, Note 2, reference to Standard Plan C-13 is revised to C-70.10 43 44 C-85.16 45 General Notes, Note 1, reference to Standard Plan C-13 is revised to C-70.10 46 47 C-85.18 48 General Notes, Note 1, reference to Standard Plan C-13 is revised to C-70.10 49 50 C-85.20 51 General Notes, Note 3, reference to Standard Plan C-13 is revised to C-70.10 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 192

1 F-10.12 2 Note 1. See Standard Plan F-30.10 for Curb Expansion and Contraction Joint spacing. 3 Is revised to read; “See Standard Plan F-30.10 for Curb Expansion and Contraction 4 Joint spacing and see Standard Specification section 8-04 and 9-04 for additional 5 requirements.” 6 7 F-10.62 8 Plan Title, Precast Concrete Sloped Mountable Curb is revised to read; “Precast Sloped 9 Mountable Curb” 10 11 F-10.64 12 Plan Title, Plan Title, Precast Concrete Dual Faced Sloped Mountable Curb is revised to 13 read; “Precast Dual Faced Sloped Mountable Curb” 14 15 F-30.10 16 Sections, left side of sheet, (4 places), dimension, Sidewalk - 6’ – 0” MIN.(See Contract) 17 is revised to read; “Sidewalk (See Contract)” 18 Section, top middle of sheet, dimension, Sidewalk – 6’ – 0” MIN. (See Contract) is 19 revised to read; “Sidewalk (See Contract)” 20 21 F-80.10 22 callout, top middle of sheet, Match Sidewalk Width See Contract Plans ~ 4’ – 0” MIN. is 23 revised to read; “Match Sidewalk Width See Contract Plans” 24 dimension, PLAN VIEW TYPE 2, (2 places), 4’ – 0” MIN, is revised to read; “(See 25 Contract)” 26 dimension, SECTION C, See Contract Plans ~ 4’ – 0” MIN. is revised to read; “See 27 Contract Plans” 28 29 G-60.20 30 Side View, callout, “Anchor Rod ~ 1-3/4” Diam. x 4’-4” Threaded 8” Min. Each End; W/ 31 2 Washers & 4 Heavy Hex Nuts ~ Galvanize Exposed Anchor Rod End for 1’-0” Min.” is 32 revised to read; “Anchor Rod ~ 1-3/4” Diam. x 4’-4” Threaded 8” Min. Each End; W/ 2 33 Washers & 6 Heavy Hex Nuts ~ Galvanize Exposed Anchor Rod End for 1’-0” Min.” 34 35 G-60.30 36 End View, callout, “Anchor Rod ~ 1-3/4” Diam. x 4’-4” Threaded 8” Min. Each End; W/ 2 37 Washers & 4 Heavy Hex Nuts ~ Galvanize Exposed Anchor Rod End for 1’-0” Min.” is 38 revised to read; “Anchor Rod ~ 1-3/4” Diam. x 4’-4” Threaded 8” Min. Each End; W/ 2 39 Washers & 6 Heavy Hex Nuts ~ Galvanize Exposed Anchor Rod End for 1’-0” Min.” 40 41 H-70.20 42 Sheet 2, Spacing Detail, Mailbox Support Type 1, reference to Standard Plan I-70.10 is 43 revised to H-70.10 44 45 J-3b 46 Sheet 2 of 2, Plan View of Service Cabinet, Boxed Note, “SEE STANDARD PLAN J- 47 6C…” is revised to read: “SEE STANDARD PLAN J-10.10…” 48 Sheet 2 of 2, Plan View of Service Cabinet Notes, references to Std. Plan J-9a are 49 revised to J-60.05 (3 instances). 50

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 193

1 Sheet 2 of 2, “Right Side of Service Cabinet” detail, callout, “1 5/8” x 2 7/16” 12 GA. 2 SLOTTED STEEL CHANNEL BRACKETS (3 REQ’D), EMBED 12”MIN. IN 3 FOUNDATION.” 4 Is revised to read: “1-5/8” x 3-1/4”, 12 GA. BACK TO BACK SLOTTED STEEL 5 CHANNEL BRACKETS (3 REQ’D), EMBED 12” MIN. IN FOUNDATION” 6 7 J-10.10 8 Note 2.”The contractor shall install the conduits in the locations shown. Conduits shall 9 extend 2” min. above the coupling. The conduit containing unfused utility conductors 10 shall extend into the utility chase.” is revised to read: 11 12 ”The contractor shall install the conduits in the locations shown. Conduits shall extend 13 2” min. above the coupling. The grounded end bushing on GRS conduit and the end bell 14 bushing on PVC conduit shall extend 3” max. above the coupling. The conduit 15 containing unfused utility conductors shall extend into the utility chase.” 16 17 Note 4. “The cabinets shall be attached to the foundation with 4 each: 1/2" × 12" × 2" × 18 4" 19 hot dip galv. anchor bolts, washers, and nuts. Stainless steel epoxy anchors may be 20 used as an alternative, and shall be 1/2" diam. × 9", or 5/8" diam. × 8". Bolts shall 21 extend 1 1/2" min. to 2" max. above the concrete pad.” is revised to read: 22 23 “The cabinets shall be attached to the foundation with 4 each: ½” x 12” x 2” x 4” anchor 24 bolts, washers, and nuts conforming to Section 9-06.5(1) and galvanized after 25 fabrication in accordance with AASHTO M 232. Stainless steel epoxy anchors may be 26 used as an alternative, and shall be ½” diameter x 9”, or 5/8” diameter x 8”. Threaded 27 Rod (conforming to ASTM F 593), washers (conforming to ASTM A 240), and nuts 28 (conforming to ASTM F 594), all shall be Type 304 stainless steel. Bolts shall extend 1 29 ½” min. to 2” max. above the concrete pad.” 30 31 J-10.15 32 ANCHOR BOLT detail, callout – ASTM A307 with washer and nut – Galvanized per 33 AASHTO M 232 is revised to read; “Anchor bolts, washers, and nuts conforming to 34 Section 9-06.5(1) and galvanized after fabrication in accordance with AASHTO M 232 “ 35 36 J-15.10 37 Elevation View (3x), Depth dimension, reads; ”Depth ~ See Std. Spec. 9-20.3(14)E and 38 Contract”, revised to read; ”Depth ~ See Std. Spec. 8-20.3(13)A and Contract” 39 40 J-15.15 41 General Notes, Note 3, reference to Standard Plan J-7c is revised to J-27.15 42 43 J-20.10 44 Foundation Detail, callout, “½” diameter steel hex nut, with 1 ½” flat washer (2) each 45 req’d per anchor bolt” is revised to read; ½” diameter steel heavy hex nut, with ½” flat 46 washer (2) each req’d per anchor bolt 47 48 J-20.11 49 Sheet 1, View A, callout, “½” x 26” full thread ~ (4) required ½” hex nuts ~ (4) required 50 per anchor bolt” is revised to read; “½” x 24” full thread ~ (4) required ½” heavy hex nuts 51 ~ (4) required per anchor bolt” 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 194

1 Section B, callout, “1/2” diameter steel hex nut, with ½” flat washer, (2) required per 2 anchor bolt” is revised to read; 1/2” diameter steel heavy hex nut, with ½” flat washer, 3 (2) required per anchor bolt 4 5 Sheet 2, Elevation, callout, “Anchor bolt ½” x 28” full thread ~ (4) required ½” hex nuts ~ 6 (4) required per anchor bolt” is revised to read: Anchor bolt 3/4” x 36” full thread ~ (4) 7 required 3/4” heavy hex nuts ~ (4) required per anchor bolt” 8 9 J-20.16 10 Elevation, callout, “1/4” Premolded Joint Filler” is revised to read; “3/8” Premolded Joint 11 Filler” 12 Add General Note 9. “Junction Box serving the Standard shall preferably be located 5’ – 13 0” (10’ – 0” Max.) from the Standard.” 14 15 J-21.10 16 Sheet 1, Round Concrete Foundation Detail, Elevation, callout, “¾” hex nuts, steel, (4) 17 Req’d. per Anchor Bolt” is revised to read; Anchor bolt ¾” x 30” full thread ~ (4) required 18 ¾” heavy hex nuts, steel, (4) Req’d. per Anchor Bolt 19 20 Sheet 1, Square Concrete Foundation Detail, Elevation, callout, “¾” hex nuts, steel, (4) 21 Req’d. per Anchor Bolt” is revised to read; Anchor bolt ¾” x 30” full thread ~ (4) required 22 ¾” heavy hex nuts, steel, (4) Req’d. per Anchor Bolt 23 24 Sheet 1, Detail C, callout, “Base Plate Assembly ~ ½” Diam. steel hex nut, with 1 ½” flat 25 washer, 2 each req’d per anchor bolt ~ minimum of 2 threads above top of nut or 5/8” 26 maximum (Typ.)” is revised to read; Base Plate Assembly ~ 3/4” heavy hex nut, with ¾” 27 flat washer, 2 each req’d per anchor bolt ~ minimum of 2 threads above top of nut or 28 5/8” maximum (Typ.)” 29 30 Sheet 2, Round Concrete Foundation Detail, Elevation, callout, “Anchor Bolts ~ (4) req’d 31 per assembly (Typ.)” is revised to read; Anchor Bolt ¾” x 30” full thread ~ (4) req’d per 32 assembly (Typ.)” 33 Callout, “3/4” hex nuts, steel ~ (4) req’d. per anchor bolt” is revised to read; 3/4” heavy 34 hex nuts, steel ~ (4) req’d. per anchor bolt 35 36 Sheet 2, Round Concrete Foundation Detail, Elevation, callout, “Anchor Bolts ~ (4) req’d 37 per assembly (Typ.)” is revised to read; Anchor Bolt ¾” x 30” full thread ~ (4) req’d per 38 assembly (Typ.)” 39 Callout, “3/4” hex nuts, steel ~ (4) req’d. per anchor bolt” is revised to read; 3/4” heavy 40 hex nuts, steel ~ (4) req’d. per anchor bolt 41 42 J-22.15 43 Ramp Meter Signal Standard, elevation, dimension 4’ - 6” is revised to read; 6’-0” 44 45 J-29.10 46 Galvanized Welded Wire Mesh detail, callout – “Drill and Tap for ¼” Diam. Cap Screw, 3 47 Places, @ 9” center, all 4 edges S.S. Screw, ASTM F593 and washer” 48 Is revised to read; 49 “Drill and Tap for ¼” Diam. Cap Screw, 3 Places, @ 9” center, all 4 edges S.S. Screw, 50 ASTM F593 and washer. Liberally coat the threads with Anti-seize Compound.” 51 52

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 195

1 J-29.15 2 Title, “Camera Pole Standard” is revised to read; “Camera Pole Standard Details” 3 4 J-29-16 5 Title, “Camera Pole Standard Details” is revised to read; “Camera Pole Details” 6 7 J-60.14 8 All references to J-16b (6x) are revised to read; J-60.11 9 10 J-75.40 11 Detail C, callout– EQUIPMENT GROUNDING CONDUCTOR ~ CLAMP TO STEEL 12 REINFORCING BAR, SIZE PER NEC MIN. SIZE # 8 13 Is revised to read; EQUIPMENT GROUNDING CONDUCTOR ~ CLAMP TO STEEL 14 REINFORCING BAR, SIZE PER NEC minimum size # 4 AWG 15 16 Detail C, callout – Stainless Steel, selftapping ¼” Diam. Screw w/ S.S. Washer, space 17 approx. 9” O.C. is revised to read; “Stainless Steel, selftapping ¼” Diam. Screw w/ S.S. 18 Washer, space approx. 9” O.C., liberally coat the threads with Anti-seize compound” 19 20 J-75.45 21 Detail D, callout– EQUIPMENT GROUNDING CONDUCTOR ~ CLAMP TO STEEL 22 REINFORCING BAR, SIZE PER NEC. MIN. SIZE # 8 23 24 Is revised to read: 25 26 EQUIPMENT GROUNDING CONDUCTOR ~ CLAMP TO STEEL REINFORCING BAR, 27 SIZE PER NEC minimum size # 4 AWG 28 Detail C, callout – Stainless Steel, selftapping ¼” Diam. Screw w/ S.S. Washer, space 29 approx. 9” O.C. is revised to read; “Stainless Steel, selftapping ¼” Diam. Screw w/ S.S. 30 Washer, space approx. 9” O.C., liberally coat the threads with Anti-seize compound” 31 32 J-90.10 33 Section B, callout, “Hardware Mounting Rack ~ S. S. 1-5/8” Slotted Channel” is revised 34 to read: “Hardware Mounting Rack (Typ.) ~ Type 304 S. S. 1-5/8” Slotted Channel” 35 36 J-90.20 37 Section B, callout, “Hardware Mounting Rack (Typ.) ~ S. S. 1-5/8” Slotted Channel” is 38 revised to read: “Hardware Mounting Rack (Typ.) ~ Type 304 S. S. 1-5/8” Slotted 39 Channel” 40 41 K-80.30 42 In the NARROW BASE, END view, the reference to Std. Plan C-8e is revised to Std. 43 Plan K-80.35 44 45 The following are the Standard Plan numbers applicable at the time this project was 46 advertised. The date shown with each plan number is the publication approval date 47 shown in the lower right-hand corner of that plan. Standard Plans showing different 48 dates shall not be used in this contract. 49 A-10.10-00...... 8/7/07 A-30.35-00...... 10/12/07 A-50.20-01…...... 9/22/09 A-10.20-00...... 10/5/07 A-40.00-00...... 8/11/09 A-50.30-00…....11/17/08 A-10.30-00...... 10/5/07 A-40.10-02...... 6/2/11 A-50.40-00…....11/17/08

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 196

A-20.10-00...... 8/31/07 A-40.15-00...... 8/11/09 A-60.10-01...... 10/14/09 A-30.10-00...... 11/8/07 A-40.20-02...... 5/29/13 A-60.20-02...... 6/2/11 A-30.15-00...... 11/8/07 A-40.50-01...... 6/2/11 A-60.30-00...... 11/8/07 A-30.30-01...... 6/16/11 A-50.10-00…....11/17/08 A-60.40-00...... 8/31/07 1 B-5.20-01...... 6/16/11 B-30.50-01...... 4/26/12 B-75.20-01...... 6/10/08 B-5.40-01...... 6/16/11 B-30.70-03...... 4/26/12 B-75.50-01...... 6/10/08 B-5.60-01...... 6/16/11 B-30.80-00...... 6/8/06 B-75.60-00...... 6/8/06 B-10.20-01...... 2/7/12 B-30.90-01...... 9/20/07 B-80.20-00...... 6/8/06 B-10.40-00...... 6/1/06 B-35.20-00...... 6/8/06 B-80.40-00...... 6/1/06 B-10.60-00...... 6/8/06 B-35.40-00...... 6/8/06 B-82.20-00...... 6/1/06 B-15.20-01...... 2/7/12 B-40.20-00...... 6/1/06 B-85.10-01...... 6/10/08 B-15.40-01...... 2/7/12 B-40.40-01...... 6/16/10 B-85.20-00...... 6/1/06 B-15.60-01...... 2/7/12 B-45.20-00...... 6/1/06 B-85.30-00...... 6/1/06 B-20.20-02...... 3/16/12 B-45.40-00...... 6/1/06 B-85.40-00...... 6/8/06 B-20.40-03...... 3/16/12 B-50.20-00...... 6/1/06 B-85.50-01...... 6/10/08 B-20.60-03...... 3/15/12 B-55.20-00...... 6/1/06 B-90.10-00...... 6/8/06 B-25.20-01...... 3/15/12 B-60.20-00...... 6/8/06 B-90.20-00...... 6/8/06 B-25.60-00...... 6/1/06 B-60.40-00...... 6/1/06 B-90.30-00...... 6/8/06 B-30.10-01...... 4/26/12 B-65.20-01...... 4/26/12 B-90.40-00...... 6/8/06 B-30.20-02...... 4/26/12 B-65.40-00...... 6/1/06 B-90.50-00...... 6/8/06 B-30.30-01...... 4/26/12 B-70.20-00...... 6/1/06 B-95.20-01...... 2/3/09 B-30.40-01...... 4/26/12 B-70.60-00...... 6/1/06 B-95.40-00...... 6/8/06 2 C-1...... 6/16/11 C-6...... 5/30/97 C-23.60-02...... 6/21/12 C-1a...... 10/14/09 C-6a...... 10/14/09 C.24.10-00...... 7/12/12 C-1b...... 6/16/11 C-6c...... 1/6/00 C-25.18-03...... 7/2/12 C-1c...... 5/30/97 C-6d...... 5/30/97 C-25.20-05...... 7/2/12 C-1d...... 10/31/03 C-6f...... 7/25/97 C-25.22-04...... 7/2/12 C-2...... 1/6/00 C-7...... 6/16/11 C-25.26-02...... 7/2/12 C-2a...... 6/21/06 C-7a...... 6/16/11 C-25.80-02...... 7/2/12 C-2b...... 6/21/06 C-8...... 2/10/09 C-40.14-02...... 7/2/12 C-2c...... 6/21/06 C-8a...... 7/25/97 C-40.16-02...... 7/2/12 C-2d...... 6/21/06 C-8b...... 6/27/11 C-40.18-02...... 7/2/12 C-2e...... 6/21/06 C-8e...... 2/21/07 C-70.10-00...... 4/8/12 C-2f...... 3/14/97 C-8f...... 6/30/04 C-75.10-00...... 4/8/12 C-2g...... 7/27/01 C-10...... 6/3/10 C-75.20-00...... 4/8/12 C-2h...... 3/28/97 C-16a...... 6/3/10 C-75.30-00...... 4/8/12 C-2i...... 3/28/97 C-16b...... 6/3/10 C-80.10-00...... 4/8/12 C-2j...... 6/12/98 C-20.10-01...... 6/20/13 C-80.20-00...... 4/8/12 C-2k...... 7/27/01 C-20.14-02...... 7/2/12 C-80.30-00...... 4/8/12 C-2n...... 7/27/01 C-20.15-01...... 7/2/12 C-80.40-00...... 4/8/12 C-2o...... 7/13/01 C-20.18-01...... 7/2/12 C-80.50-00...... 4/8/12 C-2p...... 10/31/03 C-20.19-01...... 7/2/12 C-85.10-00...... 4/8/12 C-3...... 7/2/12 C-20.40-03...... 7/2/12 C-85.11-00...... 4/8/12 C-3a...... 10/4/05 C-20.42-03...... 7/2/12 C-85.14-00...... 6/16/11 C-3b...... 6/27/11 C-20.45.01...... 7/2/12 C-85.15-00...... 6/16/11 C-3c...... 6/27/11 C-22.14-02...... 6/16/11 C-85.16-00...... 6/16/11 C-4b...... 6/8/06 C-22.16-03...... 4/18/12 C-85-18-00...... 6/16/11 C-4e...... 2/20/03 C-22.40-02...... 6/16/10 C-85.20-00...... 6/16/11 C-4f...... 7/2/12 C-22.45.00...... 6/16/11 C-90.10-00...... 7/3/08 3

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 197

D-2.04-00...... 11/10/05 D-2.48-00...... 11/10/05 D-3.17-01……5/17/12 D-2.06-01...... 1/6/09 D-2.64-01...... 1/6/09 D-4...... 12/11/98 D-2.08-00...... 11/10/05 D-2.66-00...... 11/10/05 D-6...... 6/19/98 D-2.14-00...... 11/10/05 D-2.68-00...... 11/10/05 D-10.10-01...... 12/2/08 D-2.16-00...... 11/10/05 D-2.80-00...... 11/10/05 D-10.15-01...... 12/2/08 D-2.18-00...... 11/10/05 D-2.82-00...... 11/10/05 D-10.20-00...... 7/8/08 D-2.20-00...... 11/10/05 D-2.84-00...... 11/10/05 D-10.25-00...... 7/8/08 D-2.32-00...... 11/10/05 D-2.86-00...... 11/10/05 D-10.30-00...... 7/8/08 D-2.34-01...... 1/6/09 D-2.88-00...... 11/10/05 D-10.35-00...... 7/8/08 D-2.36-02...... 1/6/09 D-2.92-00...... 11/10/05 D-10.40-01...... 12/2/08 D-2.42-00...... 11/10/05 D-3.09-00...... 5/17/12 D-10.45-01...... 12/2/08 D-2.44-00...... 11/10/05 D-3.10-01……5/29/13 D-15.10-01...... 12/2/08 D-2.60-00...... 11/10/05 D-3.11-02……5/29/13 D-15.20-02...... 6/2/11 D-2.62-00...... 11/10/05 D-3.15-02……6/10/13 D-15.30-01...... 12/02/08 D-2.46-00...... 11/10/05 D-3.16-02……5/29/13 1 E-1...... 2/21/07 E-4...... 8/27/03 E-2...... 5/29/98 E-4a...... 8/27/03 2 F-10.12-02...... 6/16/11 F-10.62-01...... 9/05/07 F-40.15-02...... 6/20/13 F-10.16-00...... 12/20/06 F-10.64-02...... 7/3/08 F-40.16-02...... 6/20/13 F-10.18-00...... 6/27/11 F-30.10-02...... 6/20/13 F-45.10-01...... 6/21/12 F-10.40-02...... 6/21/12 F-40.12-02...... 6/20/13 F-80.10-02...... 3/15/12 F-10.42-00...... 1/23/07 F-40.14-02...... 6/20/13 3 G-10.10-00...... 9/20/07 G-24.60-02.....5/20/13 G-70.20-02....6/10/13 G-20.10-00...... 9/20/07 G-25.10-04...... 6/10/13 G-70.30-02...... 6/10/13 G-22.10-01...... 7/3/08 G-30.10-02.....6/20/13 G-90.10-01…..5/11/11 G-24.10-00...... 11/8/07 G-50.10-01.....6/20/13 G-90.20-02…..3/22/13 G-24.20-01...... 2/7/12 G-60.10-02...... 6/10/13 G-90.30-02…..3/22/13 G-24.30-01...... 2/7/12 G-60.20-01...... 6/27/11 G-90.40-01…..10/14/09 G-24.40-03.....6/20/13 G-60.30-01...... 6/27/11 G-95.10-01.....6/2/11 G-24.50-02.....6/20/13 G-70.10-02...... 6/10/13 G-95.20-02...... 6/2/11 G-95.30-02...... 6/2/11 4 H-10.10-00...... 7/3/08 H-32.10-00...... 9/20/07 H-70.10-01...... 2/7/12 H-10.15-00...... 7/3/08 H-60.10-01...... 7/3/08 H-70.20-01...... 2/16/12 H-30.10-00...... 10/12/07 H-60.20-01...... 7/3/08 H-70.30-02...... 2/7/12 5 I-10.10-01...... 8/11/09 I-30.20-00...... 9/20/07 I-40.20-00...... 9/20/07 I-30.10-02...... 3/22/13 I-30.30-01...... 6/10/13 I-50.20-01...... 6/10/13 I-30.15-02...... 3/22/13 I-30.40-01...... 6/10/13 I-60.10-01...... 6/10/13 I-30.16-00...... 3/22/13 I-30.60-00...... 5/29/13 I-60.20-01...... 6/10/13 I-30.17-00...... 3/22/13 I-40.10-00...... 9/20/07 I-80.10-01...... 8/11/09 6 J-3...... 8/1/97 J-26.15-01…..5/17/12 J-40.40-00……5/20/13 J-3b...... 3/4/05 J-27.10-00…..3/15/12 J-50.10-00…….6/3/11 J-3c...... 6/24/02 J-27.15-00…..3/15/12 J-50.11-00…….6/3/11 J-10...... 7/18/97 J-28.10-01...... 5/11/11 J-50.12-00…….6/3/11 J-10.10-01……5/11/11 J-28.22-00...... 8/07/07 J-50.15-00…….6/3/11 J-10.15-00...... 7/2/12 J-28.24-00...... 8/07/07 J-50.16-01…….3/22/13 J-10.22-00...... 5/29/13 J-28.26-01...... 12/02/08 J-50.20-00…….6/3/11

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 198

J-15.10-00...... 5/18/12 J-28.30-02...... 6/27/11 J-50.25-00…….6/3/11 J-15.15-00……6/16/10 J-28.40-01...... 10/14/09 J-50.30-00…….6/3/11 J-28.42-00...... 8/07/07 J-60.05-00…….6/16/11 J-28.45-01...... 6/27/11 J-60.11-00…....5/20/13 J-20.10-02...... 6/10/13 J-28.50-02...... 6/2/11 J-60.12-00…....5/20/13 J-20.11-01...... 6/10/13 J-28.60-01...... 6/2/11 J-60.13-00…....6/16/10 J-20.15-02...... 6/10/13 J-28.70-01...... 5/11/11 J-60.14-00……6/16/10 J-20.16-01...... 7/12/12 J-29.10-00...... 6/27/11 J-75.10-01……5/11/11 J-20.20-02...... 5/20/13 J-29.15-00...... 6/27/11 J-75.20-00……2/10/09 J-20.26-01...... 7/12/12 J-29.16-01...... 6/20/13 J-75.30-01…….5/11/11 J-21.10-03...... 6/10/13 J-40.10-03…...5/20/13 J-75.40-00……10/14/09 J-21.15-01...... 6/10/13 J-40.20-01…...5/17/12 J-75.45-00……10/14/09 J-21.16-01...... 6/10/13 J-40.30-03……5/20/13 J-90.10-01…….6/27/11 J-21.17-01...... 6/10/13 J-40.35-01……5/29/13 J-90.20-01…….6/27/11 J-21.20-01...... 6/10/13 J-40.36-01……5/20/13 J-22.15-01...... 6/10/13 J-40.37-01……5/20/13 J-22.16-02...... 6/10/13 J-40.38-01...... 5/20/13 J-26.10-02…..3/15/12 J-40.39-00……5/20/13

1 K-70.20-00...... 2/15/07 K-80.10-00...... 2/21/07 K-80.20-00.....12/20/06 K-80.30-00...... 2/21/07 K-80.35-00...... 2/21/07 K-80.37-00...... 2/21/07

2 L-10.10-02...... 6/21/12 L-40.10-02...... 6/21/12 L-70.10-01...... 5/21/08 L-20.10-02...... 6/21/12 L-40.15-01...... 6/16/11 L-70.20-01...... 5/21/08 L-30.10-01...... 6/16/11 L-40.20-02...... 6/21/12 3 M-1.20-02...... 6/3/11 M-9.60-00…….2/10/09 M-40.10-02...... 5/11/11 M-1.40-02...... 6/3/11 M-11.10-01...... 1/30/07 M-40.20-00...10/12/07 M-1.60-02...... 6/3/11 M-15.10-01...... 2/6/07 M-40.30-00...... 9/20/07 M-1.80-03...... 6/3/11 M-17.10-02...... 7/3/08 M-40.40-00...... 9/20/07 M-2.20-02...... 6/3/11 M-20.10-02...... 6/3/11 M-40.50-00...... 9/20/07 M-3.10-03...... 6/3/11 M-20.20-01...... 1/30/07 M-40.60-00...... 9/20/07 M-3.20-02...... 6/3/11 M-20.30-02.....10/14/09 M-60.10-01...... 6/3/11 M-3.30-03...... 6/3/11 M-20.40-02...... 6/3/11 M-60.20-02...... 6/27/11 M-3.40-03...... 6/3/11 M-20.50-02...... 6/3/11 M-65.10-02...... 5/11/11 M-3.50-02...... 6/3/11 M-24.20-01...... 5/31/06 M-80.10-01...... 6/3/11 M-5.10-02...... 6/3/11 M-24.40-01...... 5/31/06 M-80.20-00...... 6/10/08 M-7.50-01...... 1/30/07 M-24.50-00...... 6/16/11 M-80.30-00...... 6/10/08 M-9.50-01...... 1/30/07 M-24.60-03...... 5/11/11 4 5

SKAGIT COUNTY STREET WASTE FACILITY Project No.: WA402170 March 2014 199

APPENDIX A Standard Plans

NOTES PULT POST - SPÁCEI¡ HOG RÌIGS rYP.) @r0øMAL SPACED @ 24' ilÐ( 1 . All cor¡crEle pos¡ bâêês shall òe I 0' Í{r¡lrìm d¡årFtû. TE¡*¡ION IQUCK¡.¡DSELVAGE rEixltoN wRE RJLL PO61 IENSþI{ IYIRE wrRE r cfYPl BRACE POST 2. Aþng tho top erÉ bohom, uÊlng l-bg RhgB, frst€n th€ Chdn Unk Rir¡ce Fabric b fho Tene¡on Wiß witrh th€ o l¡m¡b of tho firEt full Þbrlc ryeåw. od TIEWIRE 3. Deta¡s ar€ alLdrat¡ve and shall not o FYP-) l¡mlt hüûvarÞ (þslgn ù posl Bslæ- l6 lim of eny parücuhr lbnco type. ot FABRIC EAND OYP.) TrE WRES (fYP.'- 4 S'IREICI{ER BARfiYP.) SÏRETCHER BAR,(TYP.) SPACED O r4-üAr á ê

TENSIOI{ WRE KNUC|TED SEIVAGE CT{A¡N LINK HOG Rrt{cs (fYP.) (fYP.) FE¡EE FABRIC IEM|K'NWRE EPACED O2,F l¡lAX

CONCREÎÊ POST BASE FYP.) FAER¡C 8A¡¡D- SPACED l5- r¡A:X. ÏYPE 3

PULL FOAT - SPACED ¡€cR|NGSfiYP-) END ORCORNER (BRACEI POST e cx)'itÆ( sPÁcEo g ã'irAr

BRACE lEr{sþr¡ tvrE PtÀt PosT TENSIOII IVIRE IûL,CKLED TEiStOf{ VvrRE P6T SELVAGE BRACEPOST IETHOO OF FASTE]{ING SÏRETCHER SARTO POST

TIE IYIRE ßvp.)

KI{JCICED AELVAGE O.U¡NLINK tfYP.) FEI{CÊ FAIRIC COilCAEIEFOST BASE (fYP.)

F(x¡T AII D RAIL 8PECIFICATIOI¡8 5. U. Z.ott- cl{Atx Ltl{K FEt{cE PIPE ROLLFOilED ÎYPEA 3 AND 4 POAT TOT,SEE (scll. {o} wEtor{1 ETAHDARD PLAII Þ2O.'ÈO2 SEgftoil (ù,n) l-o- SHEÊII OF2STIEE¡S ENO, COR¡ËR, OR RJIT POST 21t7 otÀl,- o 510 & Lll,{E OR BR¡C€ FOST ? OIA¡tl, @ tE5 w- blrbhùfúsdrh9* o É o o á f jj

E á

TEi¡EO}I wlRE

TENSþilwtRES 'fENStOr'lWRES

FABRIC EAND CTYP.)

sfRErcHER 8AR (IYP.) 5'Zt'?otL GIIAIN LIIIK FEI{GE TYPEA 3 AND 4 STAIIDARD PLAI' L.2O.I GO2 STEEÍ 2 ()F 2SHEETS

w- Íd{[ù ú D.prrddlq¡Ú DOUSLE 14 FT. CHAIN LII{K GATE - PAY UI,IT ._ I C}TA,N LINK FEilcE TYPE 3 oR 4 DOUÊLE ã' FT. CHAIN LINK GAÎE - PAY UMIT , PAY UMÍT | *u o*" - 14-ü OR 2{Ï-0" z | @zcvnx.ovp.)""o"* g TIE WRES CI'YP.) - _ M.ÀTCII FENCE PUI.I É SELVAGE POST E SPACED e 14" MAX. / CrYP.) roP HTNGE - 180' ó IENSION WRE I s/úNG GYP.) TENSION I/VRE o o

FAERIC BAND [YP.) =oÍ

STRETCHER BAR (TYP )

BOTTOü HNGE - 160. srúNG (fYP ) C¡IA¡N UNK FÊNCÉ FABRIC HOG RINGS - SPACEO @ 24'MAx. CrYP) 3 - O' - CHAIN LINK FENCE TYPE 3 ? - OÊ - C}IAIN LINK FENCE TYPE 4

DOUBLE GATE

SINGLEGFT CI-IAINLINKGATE TYPE3OR4 PAY UMIT

10 - 0'ITYP

TEI{SION I¡/IRE FOR GATE POST TOP HINGE - REOI.TRED ONLY ON HINGE SIOE 90'SwlNG -

FABRIC BAND (fYP-)

STRETCHER BAR (rYP )

BOTTol' II¡NGE - gt. swNc CHAIN LINK GATE CTIAIIT LINK FENCE FABRIC nÊ TMRES GYP ) - 3 - C - CHAIN UNK FÊ}æE TYPE 3 SPACED @ 14'MAX 2 - (r - CHÀN UflX FEI{CE TYPE 4 STAilDARD PI-Ail ç39.10{1 SHEETIOF2SHEEIS SINGLE GATE "t'4

Ø-, WolÉEb S* D.FtddlEryËb uz É U @ ¿ø TENSION li¡lRE É 3 FAAR¡C 8^ND oÉ TENSOTI WRE

TOP HINGE

STRETHCER BAR

ÍENSION WRE

IENSION YVIRE

TURNBUCKLE

BOTTOû' TilNGE rENStoN wlRE (fYP.) (NOT REQUIRED FOR CIIAIN UNK FENCE TYPE 4)

EYE BOLI

CI{AIN LINK GATE

STAIÚDARD PI.AN L.3O. I O.OI SfIEET2OF2SHÊETS

APPENDIX B State Prevailing Wages

Page 1 of 17

State of Washington Department of Labor & Industries Prevailing Wage Section - Telephone 360-902-5335 PO Box 44540, Olympia, WA 98504-4540

Washington State Prevailing Wage The PREVAILING WAGES listed here include both the hourly wage rate and the hourly rate of fringe benefits. On public works projects, worker's wage and benefit rates must add to not less than this total. A brief description of overtime calculation requirements are provided on the Benefit Code Key.

Journey Level Prevailing Wage Rates for the Effective Date: 3/6/2014

County Trade Job Classification Wage Holiday Overtime Note Skagit Asbestos Abatement Workers Journey Level $41.69 5D 1H Skagit Boilermakers Journey Level $64.44 5N 1C Skagit Brick Mason Brick And Block Finisher $43.26 5A 1M Skagit Brick Mason Journey Level $50.12 5A 1M Skagit Brick Mason Pointer-Caulker-Cleaner $50.12 5A 1M Skagit Building Service Employees Janitor $10.00 1 Skagit Building Service Employees Shampooer $9.32 1 Skagit Building Service Employees Waxer $9.32 1 Skagit Building Service Employees Window Cleaner $9.32 1 Skagit Cabinet Makers (In Shop) Journey Level $18.85 1 Skagit Carpenters Acoustical Worker $50.82 5D 1M Skagit Carpenters Bridge, Dock And Wharf $50.82 5D 1M Carpenters Skagit Carpenters Carpenter $50.82 5D 1M Skagit Carpenters Carpenters on Stationary Tools $50.95 5D 1M Skagit Carpenters Creosoted Material $50.92 5D 1M Skagit Carpenters Floor Finisher $50.82 5D 1M Skagit Carpenters Floor Layer $50.82 5D 1M Skagit Carpenters Scaffold Erector $50.82 5D 1M Skagit Cement Masons Journey Level $51.18 7A 1M Skagit Divers & Tenders Diver $105.37 5D 1M 8A Skagit Divers & Tenders Diver On Standby $59.50 5D 1M Skagit Divers & Tenders Diver Tender $54.82 5D 1M Skagit Divers & Tenders Surface Rcv & Rov Operator $54.82 5D 1M Skagit Divers & Tenders Surface Rcv & Rov Operator $51.07 5A 1B Tender Skagit Dredge Workers Assistant Engineer $53.00 5D 3F Skagit Dredge Workers Assistant Mate (Deckhand) $52.58 5D 3F

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 2 of 17

Skagit Dredge Workers Boatmen $52.30 5D 3F Skagit Dredge Workers Engineer Welder $54.04 5D 3F Skagit Dredge Workers Leverman, Hydraulic $55.17 5D 3F Skagit Dredge Workers Mates $52.30 5D 3F Skagit Dredge Workers Oiler $52.58 5D 3F Skagit Drywall Applicator Journey Level $50.82 5D 1H Skagit Drywall Tapers Journey Level $50.87 5P 1E Skagit Electrical Fixture Maintenance Journey Level $21.48 1 Workers Skagit Electricians - Inside Cable Splicer $60.71 7H 1E Skagit Electricians - Inside Construction Stock Person $29.41 7H 1D Skagit Electricians - Inside Journey Level $56.69 7H 1E Skagit Electricians - Motor Shop Craftsman $15.37 1 Skagit Electricians - Motor Shop Journey Level $14.69 1 Skagit Electricians - Powerline Cable Splicer $68.33 5A 4A Construction Skagit Electricians - Powerline Certified Line Welder $62.50 5A 4A Construction Skagit Electricians - Powerline Groundperson $42.56 5A 4A Construction Skagit Electricians - Powerline Heavy Line Equipment $62.50 5A 4A Construction Operator Skagit Electricians - Powerline Journey Level Lineperson $62.50 5A 4A Construction Skagit Electricians - Powerline Line Equipment Operator $52.47 5A 4A Construction Skagit Electricians - Powerline Pole Sprayer $62.50 5A 4A Construction Skagit Electricians - Powerline Powderperson $46.55 5A 4A Construction Skagit Electronic Technicians Electronic Technicians Journey $36.59 5B 1B Level Skagit Elevator Constructors Mechanic $80.14 7D 4A Skagit Elevator Constructors Mechanic In Charge $86.77 7D 4A Skagit Fabricated Precast Concrete Journey Level - In-Factory $13.50 1 Products Work Only Skagit Fence Erectors Fence Erector $12.00 1 Skagit Flaggers Journey Level $35.34 7A 3I Skagit Glaziers Journey Level $53.76 7L 1Y Skagit Heat & Frost Insulators And Journeyman $58.93 5J 1S Asbestos Workers Skagit Heating Equipment Mechanics Mechanic $56.69 7F 1E Skagit Hod Carriers & Mason Tenders Journey Level $42.99 7A 3I Skagit Industrial Power Vacuum Journey Level $9.32 1 Cleaner Skagit Inland Boatmen Boat Operator $54.57 5B 1K Skagit Inland Boatmen Cook $50.95 5B 1K

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 3 of 17

Skagit Inland Boatmen Deckhand $51.19 5B 1K Skagit Inland Boatmen Deckhand Engineer $52.18 5B 1K Skagit Inland Boatmen Launch Operator $53.40 5B 1K Skagit Inland Boatmen Mate $53.40 5B 1K Skagit Inspection/Cleaning/Sealing Of Cleaner Operator, Foamer $9.73 1 Sewer & Water Systems By Operator Remote Control Skagit Inspection/Cleaning/Sealing Of Grout Truck Operator $11.48 1 Sewer & Water Systems By Remote Control Skagit Inspection/Cleaning/Sealing Of Head Operator $12.78 1 Sewer & Water Systems By Remote Control Skagit Inspection/Cleaning/Sealing Of Technician $9.32 1 Sewer & Water Systems By Remote Control Skagit Inspection/Cleaning/Sealing Of Tv Truck Operator $10.53 1 Sewer & Water Systems By Remote Control Skagit Insulation Applicators Journey Level $50.82 5D 1M Skagit Ironworkers Journeyman $59.77 7N 1O Skagit Laborers Air, Gas Or Electric Vibrating $41.69 7A 3I Screed Skagit Laborers Airtrac Drill Operator $42.99 7A 3I Skagit Laborers Ballast Regular Machine $41.69 7A 3I Skagit Laborers Batch Weighman $35.34 7A 3I Skagit Laborers Brick Pavers $41.69 7A 3I Skagit Laborers Brush Cutter $41.69 7A 3I Skagit Laborers Brush Hog Feeder $41.69 7A 3I Skagit Laborers Burner $41.69 7A 3I Skagit Laborers Caisson Worker $42.99 7A 3I Skagit Laborers Carpenter Tender $41.69 7A 3I Skagit Laborers Caulker $41.69 7A 3I Skagit Laborers Cement Dumper-paving $42.46 7A 3I Skagit Laborers Cement Finisher Tender $41.69 7A 3I Skagit Laborers Change House Or Dry Shack $41.69 7A 3I Skagit Laborers Chipping Gun (under 30 Lbs.) $41.69 7A 3I Skagit Laborers Chipping Gun(30 Lbs. And $42.46 7A 3I Over) Skagit Laborers Choker Setter $41.69 7A 3I Skagit Laborers Chuck Tender $41.69 7A 3I Skagit Laborers Clary Power Spreader $42.46 7A 3I Skagit Laborers Clean-up Laborer $41.69 7A 3I Skagit Laborers Concrete Dumper/chute $42.46 7A 3I Operator Skagit Laborers Concrete Form Stripper $41.69 7A 3I Skagit Laborers Concrete Placement Crew $42.46 7A 3I

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 4 of 17

Skagit Laborers Concrete Saw Operator/core $42.46 7A 3I Driller Skagit Laborers Crusher Feeder $35.34 7A 3I Skagit Laborers Curing Laborer $41.69 7A 3I Skagit Laborers Demolition: Wrecking & Moving $41.69 7A 3I (incl. Charred Material) Skagit Laborers Ditch Digger $41.69 7A 3I Skagit Laborers Diver $42.99 7A 3I Skagit Laborers Drill Operator $42.46 7A 3I (hydraulic,diamond) Skagit Laborers Dry Stack Walls $41.69 7A 3I Skagit Laborers Dump Person $41.69 7A 3I Skagit Laborers Epoxy Technician $41.69 7A 3I Skagit Laborers Erosion Control Worker $41.69 7A 3I Skagit Laborers Faller & Bucker Chain Saw $42.46 7A 3I Skagit Laborers Fine Graders $41.69 7A 3I Skagit Laborers Firewatch $35.34 7A 3I Skagit Laborers Form Setter $41.69 7A 3I Skagit Laborers Gabian Basket Builders $41.69 7A 3I Skagit Laborers General Laborer $41.69 7A 3I Skagit Laborers Grade Checker & Transit $42.99 7A 3I Person Skagit Laborers Grinders $41.69 7A 3I Skagit Laborers Grout Machine Tender $41.69 7A 3I Skagit Laborers Groutmen (pressure)including $42.46 7A 3I Post Tension Beams Skagit Laborers Guardrail Erector $41.69 7A 3I Skagit Laborers Hazardous Waste Worker (level $42.99 7A 3I A) Skagit Laborers Hazardous Waste Worker (level $42.46 7A 3I B) Skagit Laborers Hazardous Waste Worker (level $41.69 7A 3I C) Skagit Laborers High Scaler $42.99 7A 3I Skagit Laborers Jackhammer $42.46 7A 3I Skagit Laborers Laserbeam Operator $42.46 7A 3I Skagit Laborers Maintenance Person $41.69 7A 3I Skagit Laborers Manhole Builder-mudman $42.46 7A 3I Skagit Laborers Material Yard Person $41.69 7A 3I Skagit Laborers Motorman-dinky Locomotive $42.46 7A 3I Skagit Laborers Nozzleman (concrete Pump, $42.46 7A 3I Green Cutter When Using Combination Of High Pressure Air & Water On Concrete & Rock, Sandblast, Gunite, Shotcrete, Water Bla Skagit Laborers Pavement Breaker $42.46 7A 3I

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 5 of 17

Skagit Laborers Pilot Car $35.34 7A 3I Skagit Laborers Pipe Layer Lead $42.99 7A 3I Skagit Laborers Pipe Layer/tailor $42.46 7A 3I Skagit Laborers Pipe Pot Tender $42.46 7A 3I Skagit Laborers Pipe Reliner $42.46 7A 3I Skagit Laborers Pipe Wrapper $42.46 7A 3I Skagit Laborers Pot Tender $41.69 7A 3I Skagit Laborers Powderman $42.99 7A 3I Skagit Laborers Powderman's Helper $41.69 7A 3I Skagit Laborers Power Jacks $42.46 7A 3I Skagit Laborers Railroad Spike Puller - Power $42.46 7A 3I Skagit Laborers Raker - Asphalt $42.99 7A 3I Skagit Laborers Re-timberman $42.99 7A 3I Skagit Laborers Remote Equipment Operator $42.46 7A 3I Skagit Laborers Rigger/signal Person $42.46 7A 3I Skagit Laborers Rip Rap Person $41.69 7A 3I Skagit Laborers Rivet Buster $42.46 7A 3I Skagit Laborers Rodder $42.46 7A 3I Skagit Laborers Scaffold Erector $41.69 7A 3I Skagit Laborers Scale Person $41.69 7A 3I Skagit Laborers Sloper (over 20") $42.46 7A 3I Skagit Laborers Sloper Sprayer $41.69 7A 3I Skagit Laborers Spreader (concrete) $42.46 7A 3I Skagit Laborers Stake Hopper $41.69 7A 3I Skagit Laborers Stock Piler $41.69 7A 3I Skagit Laborers Tamper & Similar Electric, Air $42.46 7A 3I & Gas Operated Tools Skagit Laborers Tamper (multiple & Self- $42.46 7A 3I propelled) Skagit Laborers Timber Person - Sewer (lagger, $42.46 7A 3I Shorer & Cribber) Skagit Laborers Toolroom Person (at Jobsite) $41.69 7A 3I Skagit Laborers Topper $41.69 7A 3I Skagit Laborers Track Laborer $41.69 7A 3I Skagit Laborers Track Liner (power) $42.46 7A 3I Skagit Laborers Traffic Control Laborer $37.79 7A 3I 8R Skagit Laborers Traffic Control Supervisor $37.79 7A 3I 8R Skagit Laborers Truck Spotter $41.69 7A 3I Skagit Laborers Tugger Operator $42.46 7A 3I Skagit Laborers Tunnel Work-Compressed Air $60.06 7A 3I 8Q Worker 0-30 psi Skagit Laborers Tunnel Work-Compressed Air $65.09 7A 3I 8Q Worker 30.01-44.00 psi Skagit Laborers Tunnel Work-Compressed Air $68.77 7A 3I 8Q Worker 44.01-54.00 psi

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 6 of 17

Skagit Laborers Tunnel Work-Compressed Air $74.47 7A 3I 8Q Worker 54.01-60.00 psi Skagit Laborers Tunnel Work-Compressed Air $76.59 7A 3I 8Q Worker 60.01-64.00 psi Skagit Laborers Tunnel Work-Compressed Air $81.69 7A 3I 8Q Worker 64.01-68.00 psi Skagit Laborers Tunnel Work-Compressed Air $83.59 7A 3I 8Q Worker 68.01-70.00 psi Skagit Laborers Tunnel Work-Compressed Air $85.59 7A 3I 8Q Worker 70.01-72.00 psi Skagit Laborers Tunnel Work-Compressed Air $87.59 7A 3I 8Q Worker 72.01-74.00 psi Skagit Laborers Tunnel Work-Guage and Lock $43.09 7A 3I 8Q Tender Skagit Laborers Tunnel Work-Miner $43.09 7A 3I 8Q Skagit Laborers Vibrator $42.46 7A 3I Skagit Laborers Vinyl Seamer $41.69 7A 3I Skagit Laborers Watchman $32.12 7A 3I Skagit Laborers Welder $42.46 7A 3I Skagit Laborers Well Point Laborer $42.46 7A 3I Skagit Laborers Window Washer/cleaner $32.12 7A 3I Skagit Laborers - Underground Sewer General Laborer & Topman $41.69 7A 3I & Water Skagit Laborers - Underground Sewer Pipe Layer $42.46 7A 3I & Water Skagit Landscape Construction Irrigation Or Lawn Sprinkler $14.15 1 Installers Skagit Landscape Construction Landscape Equipment $14.15 1 Operators Or Truck Drivers Skagit Landscape Construction Landscaping or Planting $14.18 1 Laborers Skagit Lathers Journey Level $50.82 5D 1H Skagit Marble Setters Journey Level $50.12 5A 1M Skagit Metal Fabrication (In Shop) Fitter $15.16 1 Skagit Metal Fabrication (In Shop) Laborer $11.13 1 Skagit Metal Fabrication (In Shop) Machine Operator $10.66 1 Skagit Metal Fabrication (In Shop) Painter $11.41 1 Skagit Metal Fabrication (In Shop) Welder $15.16 1 Skagit Millwright Journey Level $38.36 1 Skagit Modular Buildings Journey Level $9.32 1 Skagit Painters Journey Level $37.80 6Z 2B Skagit Pile Driver Journey Level $51.07 5D 1M Skagit Plasterers Journey Level $49.29 7Q 1R Skagit Playground & Park Equipment Journey Level $9.32 1 Installers Skagit Plumbers & Pipefitters Journey Level $62.57 5A 1G Skagit Power Equipment Operators Asphalt Plant Operators $53.49 7A 3C 8P

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 7 of 17

Skagit Power Equipment Operators Assistant Engineer $50.22 7A 3C 8P Skagit Power Equipment Operators Barrier Machine (zipper) $53.00 7A 3C 8P Skagit Power Equipment Operators Batch Plant Operator, $53.00 7A 3C 8P Concrete Skagit Power Equipment Operators Bobcat $50.22 7A 3C 8P Skagit Power Equipment Operators Brokk - Remote Demolition $50.22 7A 3C 8P Equipment Skagit Power Equipment Operators Brooms $50.22 7A 3C 8P Skagit Power Equipment Operators Bump Cutter $53.00 7A 3C 8P Skagit Power Equipment Operators Cableways $53.49 7A 3C 8P Skagit Power Equipment Operators Chipper $53.00 7A 3C 8P Skagit Power Equipment Operators Compressor $50.22 7A 3C 8P Skagit Power Equipment Operators Concrete Pump: Truck Mount $53.49 7A 3C 8P With Boom Attachment Over 42 M Skagit Power Equipment Operators Concrete Finish Machine -laser $50.22 7A 3C 8P Screed Skagit Power Equipment Operators Concrete Pump - Mounted Or $52.58 7A 3C 8P Trailer High Pressure Line Pump, Pump High Pressure. Skagit Power Equipment Operators Concrete Pump: Truck Mount $53.00 7A 3C 8P With Boom Attachment Up To 42m Skagit Power Equipment Operators Conveyors $52.58 7A 3C 8P Skagit Power Equipment Operators Cranes: 20 Tons Through 44 $53.00 7A 3C 8P Tons With Attachments Skagit Power Equipment Operators Cranes: 100 Tons Through 199 $54.04 7A 3C 8P Tons, Or 150' Of Boom (Including Jib With Attachments) Skagit Power Equipment Operators Cranes: 200 Tons To 300 Tons, $54.61 7A 3C 8P Or 250' Of Boom (including Jib With Attachments) Skagit Power Equipment Operators Cranes: 45 Tons Through 99 $53.49 7A 3C 8P Tons, Under 150' Of Boom (including Jib With Attachments) Skagit Power Equipment Operators Cranes: A-frame - 10 Tons And $50.22 7A 3C 8P Under Skagit Power Equipment Operators Cranes: Friction 100 Tons $54.61 7A 3C 8P Through 199 Tons Skagit Power Equipment Operators Cranes: Friction Over 200 Tons $55.17 7A 3C 8P Skagit Power Equipment Operators Cranes: Over 300 Tons Or 300' $55.17 7A 3C 8P Of Boom (including Jib With Attachments) Skagit Power Equipment Operators Cranes: Through 19 Tons With $52.58 7A 3C 8P Attachments A-frame Over 10 Tons Skagit Power Equipment Operators Crusher $53.00 7A 3C 8P Skagit Power Equipment Operators Deck Engineer/deck Winches $53.00 7A 3C 8P

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 8 of 17

(power) Skagit Power Equipment Operators Derricks, On Building Work $53.49 7A 3C 8P Skagit Power Equipment Operators Dozers D-9 & Under $52.58 7A 3C 8P Skagit Power Equipment Operators Drill Oilers: Auger Type, Truck $52.58 7A 3C 8P Or Crane Mount Skagit Power Equipment Operators Drilling Machine $53.00 7A 3C 8P Skagit Power Equipment Operators Elevator And Man-lift: $50.22 7A 3C 8P Permanent And Shaft Type Skagit Power Equipment Operators Finishing Machine, Bidwell And $53.00 7A 3C 8P Gamaco & Similar Equipment Skagit Power Equipment Operators Forklift: 3000 Lbs And Over $52.58 7A 3C 8P With Attachments Skagit Power Equipment Operators Forklifts: Under 3000 Lbs. With $50.22 7A 3C 8P Attachments Skagit Power Equipment Operators Grade Engineer: Using Blue $53.00 7A 3C 8P Prints, Cut Sheets, Etc Skagit Power Equipment Operators Gradechecker/stakeman $50.22 7A 3C 8P Skagit Power Equipment Operators Guardrail Punch $53.00 7A 3C 8P Skagit Power Equipment Operators Hard Tail End Dump $53.49 7A 3C 8P Articulating Off- Road Equipment 45 Yards. & Over Skagit Power Equipment Operators Hard Tail End Dump $53.00 7A 3C 8P Articulating Off-road Equipment Under 45 Yards Skagit Power Equipment Operators Horizontal/directional Drill $52.58 7A 3C 8P Locator Skagit Power Equipment Operators Horizontal/directional Drill $53.00 7A 3C 8P Operator Skagit Power Equipment Operators Hydralifts/boom Trucks Over $52.58 7A 3C 8P 10 Tons Skagit Power Equipment Operators Hydralifts/boom Trucks, 10 $50.22 7A 3C 8P Tons And Under Skagit Power Equipment Operators Loader, Overhead 8 Yards. & $54.04 7A 3C 8P Over Skagit Power Equipment Operators Loader, Overhead, 6 Yards. But $53.49 7A 3C 8P Not Including 8 Yards Skagit Power Equipment Operators Loaders, Overhead Under 6 $53.00 7A 3C 8P Yards Skagit Power Equipment Operators Loaders, Plant Feed $53.00 7A 3C 8P Skagit Power Equipment Operators Loaders: Elevating Type Belt $52.58 7A 3C 8P Skagit Power Equipment Operators Locomotives, All $53.00 7A 3C 8P Skagit Power Equipment Operators Material Transfer Device $53.00 7A 3C 8P Skagit Power Equipment Operators Mechanics, All (leadmen - $54.04 7A 3C 8P $0.50 Per Hour Over Mechanic) Skagit Power Equipment Operators Motor Patrol Grader - Non- $52.58 7A 3C 8P finishing Skagit Power Equipment Operators Motor Patrol Graders, Finishing $53.49 7A 3C 8P Skagit Power Equipment Operators Mucking Machine, Mole, Tunnel $53.49 7A 3C 8P Drill, Boring, Road Header

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 9 of 17

And/or Shield Skagit Power Equipment Operators Oil Distributors, Blower $50.22 7A 3C 8P Distribution & Mulch Seeding Operator Skagit Power Equipment Operators Outside Hoists (elevators And $52.58 7A 3C 8P Manlifts), Air Tuggers,strato Skagit Power Equipment Operators Overhead, Bridge Type Crane: $53.00 7A 3C 8P 20 Tons Through 44 Tons Skagit Power Equipment Operators Overhead, Bridge Type: 100 $54.04 7A 3C 8P Tons And Over Skagit Power Equipment Operators Overhead, Bridge Type: 45 $53.49 7A 3C 8P Tons Through 99 Tons Skagit Power Equipment Operators Pavement Breaker $50.22 7A 3C 8P Skagit Power Equipment Operators Pile Driver (other Than Crane $53.00 7A 3C 8P Mount) Skagit Power Equipment Operators Plant Oiler - Asphalt, Crusher $52.58 7A 3C 8P Skagit Power Equipment Operators Posthole Digger, Mechanical $50.22 7A 3C 8P Skagit Power Equipment Operators Power Plant $50.22 7A 3C 8P Skagit Power Equipment Operators Pumps - Water $50.22 7A 3C 8P Skagit Power Equipment Operators Quad 9, Hd 41, D10 And Over $53.49 7A 3C 8P Skagit Power Equipment Operators Quick Tower - No Cab, Under $50.22 7A 3C 8P 100 Feet In Height Based To Boom Skagit Power Equipment Operators Remote Control Operator On $53.49 7A 3C 8P Rubber Tired Earth Moving Equipment Skagit Power Equipment Operators Rigger And Bellman $50.22 7A 3C 8P Skagit Power Equipment Operators Rollagon $53.49 7A 3C 8P Skagit Power Equipment Operators Roller, Other Than Plant Mix $50.22 7A 3C 8P Skagit Power Equipment Operators Roller, Plant Mix Or Multi-lift $52.58 7A 3C 8P Materials Skagit Power Equipment Operators Roto-mill, Roto-grinder $53.00 7A 3C 8P Skagit Power Equipment Operators Saws - Concrete $52.58 7A 3C 8P Skagit Power Equipment Operators Scraper, Self Propelled Under $53.00 7A 3C 8P 45 Yards Skagit Power Equipment Operators Scrapers - Concrete & Carry All $52.58 7A 3C 8P Skagit Power Equipment Operators Scrapers, Self-propelled: 45 $53.49 7A 3C 8P Yards And Over Skagit Power Equipment Operators Service Engineers - Equipment $52.58 7A 3C 8P Skagit Power Equipment Operators Shotcrete/gunite Equipment $50.22 7A 3C 8P Skagit Power Equipment Operators Shovel , Excavator, Backhoe, $52.58 7A 3C 8P Tractors Under 15 Metric Tons. Skagit Power Equipment Operators Shovel, Excavator, Backhoe: $53.49 7A 3C 8P Over 30 Metric Tons To 50 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoes, $53.00 7A 3C 8P Tractors: 15 To 30 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoes: $54.04 7A 3C 8P

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 10 of 17

Over 50 Metric Tons To 90 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoes: $54.61 7A 3C 8P Over 90 Metric Tons Skagit Power Equipment Operators Slipform Pavers $53.49 7A 3C 8P Skagit Power Equipment Operators Spreader, Topsider & $53.49 7A 3C 8P Screedman Skagit Power Equipment Operators Subgrader Trimmer $53.00 7A 3C 8P Skagit Power Equipment Operators Tower Bucket Elevators $52.58 7A 3C 8P Skagit Power Equipment Operators Tower Crane Over 175'in $54.61 7A 3C 8P Height, Base To Boom Skagit Power Equipment Operators Tower Crane Up To 175' In $54.04 7A 3C 8P Height Base To Boom Skagit Power Equipment Operators Transporters, All Track Or $53.49 7A 3C 8P Truck Type Skagit Power Equipment Operators Trenching Machines $52.58 7A 3C 8P Skagit Power Equipment Operators Truck Crane Oiler/driver - 100 $53.00 7A 3C 8P Tons And Over Skagit Power Equipment Operators Truck Crane Oiler/driver Under $52.58 7A 3C 8P 100 Tons Skagit Power Equipment Operators Truck Mount Portable Conveyor $53.00 7A 3C 8P Skagit Power Equipment Operators Welder $53.49 7A 3C 8P Skagit Power Equipment Operators Wheel Tractors, Farmall Type $50.22 7A 3C 8P Skagit Power Equipment Operators Yo Yo Pay Dozer $53.00 7A 3C 8P Skagit Power Equipment Operators- Asphalt Plant Operators $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Assistant Engineer $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Barrier Machine (zipper) $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Batch Plant Operator, $53.00 7A 3C 8P Underground Sewer & Water Concrete Skagit Power Equipment Operators- Bobcat $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Brokk - Remote Demolition $50.22 7A 3C 8P Underground Sewer & Water Equipment Skagit Power Equipment Operators- Brooms $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Bump Cutter $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Cableways $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Chipper $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Compressor $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Concrete Pump: Truck Mount $53.49 7A 3C 8P Underground Sewer & Water With Boom Attachment Over 42 M

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 11 of 17

Skagit Power Equipment Operators- Concrete Finish Machine -laser $50.22 7A 3C 8P Underground Sewer & Water Screed Skagit Power Equipment Operators- Concrete Pump - Mounted Or $52.58 7A 3C 8P Underground Sewer & Water Trailer High Pressure Line Pump, Pump High Pressure. Skagit Power Equipment Operators- Concrete Pump: Truck Mount $53.00 7A 3C 8P Underground Sewer & Water With Boom Attachment Up To 42m Skagit Power Equipment Operators- Conveyors $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Cranes: 20 Tons Through 44 $53.00 7A 3C 8P Underground Sewer & Water Tons With Attachments Skagit Power Equipment Operators- Cranes: 100 Tons Through 199 $54.04 7A 3C 8P Underground Sewer & Water Tons, Or 150' Of Boom (Including Jib With Attachments) Skagit Power Equipment Operators- Cranes: 200 Tons To 300 Tons, $54.61 7A 3C 8P Underground Sewer & Water Or 250' Of Boom (including Jib With Attachments) Skagit Power Equipment Operators- Cranes: 45 Tons Through 99 $53.49 7A 3C 8P Underground Sewer & Water Tons, Under 150' Of Boom (including Jib With Attachments) Skagit Power Equipment Operators- Cranes: A-frame - 10 Tons And $50.22 7A 3C 8P Underground Sewer & Water Under Skagit Power Equipment Operators- Cranes: Friction 100 Tons $54.61 7A 3C 8P Underground Sewer & Water Through 199 Tons Skagit Power Equipment Operators- Cranes: Friction Over 200 Tons $55.17 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Cranes: Over 300 Tons Or 300' $55.17 7A 3C 8P Underground Sewer & Water Of Boom (including Jib With Attachments) Skagit Power Equipment Operators- Cranes: Through 19 Tons With $52.58 7A 3C 8P Underground Sewer & Water Attachments A-frame Over 10 Tons Skagit Power Equipment Operators- Crusher $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Deck Engineer/deck Winches $53.00 7A 3C 8P Underground Sewer & Water (power) Skagit Power Equipment Operators- Derricks, On Building Work $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Dozers D-9 & Under $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Drill Oilers: Auger Type, Truck $52.58 7A 3C 8P Underground Sewer & Water Or Crane Mount Skagit Power Equipment Operators- Drilling Machine $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Elevator And Man-lift: $50.22 7A 3C 8P Underground Sewer & Water Permanent And Shaft Type Skagit Power Equipment Operators- Finishing Machine, Bidwell And $53.00 7A 3C 8P Underground Sewer & Water Gamaco & Similar Equipment

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 12 of 17

Skagit Power Equipment Operators- Forklift: 3000 Lbs And Over $52.58 7A 3C 8P Underground Sewer & Water With Attachments Skagit Power Equipment Operators- Forklifts: Under 3000 Lbs. With $50.22 7A 3C 8P Underground Sewer & Water Attachments Skagit Power Equipment Operators- Grade Engineer: Using Blue $53.00 7A 3C 8P Underground Sewer & Water Prints, Cut Sheets, Etc Skagit Power Equipment Operators- Gradechecker/stakeman $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Guardrail Punch $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Hard Tail End Dump $53.49 7A 3C 8P Underground Sewer & Water Articulating Off- Road Equipment 45 Yards. & Over Skagit Power Equipment Operators- Hard Tail End Dump $53.00 7A 3C 8P Underground Sewer & Water Articulating Off-road Equipment Under 45 Yards Skagit Power Equipment Operators- Horizontal/directional Drill $52.58 7A 3C 8P Underground Sewer & Water Locator Skagit Power Equipment Operators- Horizontal/directional Drill $53.00 7A 3C 8P Underground Sewer & Water Operator Skagit Power Equipment Operators- Hydralifts/boom Trucks Over $52.58 7A 3C 8P Underground Sewer & Water 10 Tons Skagit Power Equipment Operators- Hydralifts/boom Trucks, 10 $50.22 7A 3C 8P Underground Sewer & Water Tons And Under Skagit Power Equipment Operators- Loader, Overhead 8 Yards. & $54.04 7A 3C 8P Underground Sewer & Water Over Skagit Power Equipment Operators- Loader, Overhead, 6 Yards. But $53.49 7A 3C 8P Underground Sewer & Water Not Including 8 Yards Skagit Power Equipment Operators- Loaders, Overhead Under 6 $53.00 7A 3C 8P Underground Sewer & Water Yards Skagit Power Equipment Operators- Loaders, Plant Feed $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Loaders: Elevating Type Belt $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Locomotives, All $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Material Transfer Device $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Mechanics, All (leadmen - $54.04 7A 3C 8P Underground Sewer & Water $0.50 Per Hour Over Mechanic) Skagit Power Equipment Operators- Motor Patrol Grader - Non- $52.58 7A 3C 8P Underground Sewer & Water finishing Skagit Power Equipment Operators- Motor Patrol Graders, Finishing $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Mucking Machine, Mole, Tunnel $53.49 7A 3C 8P Underground Sewer & Water Drill, Boring, Road Header And/or Shield Skagit Power Equipment Operators- Oil Distributors, Blower $50.22 7A 3C 8P Underground Sewer & Water Distribution & Mulch Seeding Operator

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 13 of 17

Skagit Power Equipment Operators- Outside Hoists (elevators And $52.58 7A 3C 8P Underground Sewer & Water Manlifts), Air Tuggers,strato Skagit Power Equipment Operators- Overhead, Bridge Type Crane: $53.00 7A 3C 8P Underground Sewer & Water 20 Tons Through 44 Tons Skagit Power Equipment Operators- Overhead, Bridge Type: 100 $54.04 7A 3C 8P Underground Sewer & Water Tons And Over Skagit Power Equipment Operators- Overhead, Bridge Type: 45 $53.49 7A 3C 8P Underground Sewer & Water Tons Through 99 Tons Skagit Power Equipment Operators- Pavement Breaker $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Pile Driver (other Than Crane $53.00 7A 3C 8P Underground Sewer & Water Mount) Skagit Power Equipment Operators- Plant Oiler - Asphalt, Crusher $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Posthole Digger, Mechanical $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Power Plant $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Pumps - Water $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Quad 9, Hd 41, D10 And Over $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Quick Tower - No Cab, Under $50.22 7A 3C 8P Underground Sewer & Water 100 Feet In Height Based To Boom Skagit Power Equipment Operators- Remote Control Operator On $53.49 7A 3C 8P Underground Sewer & Water Rubber Tired Earth Moving Equipment Skagit Power Equipment Operators- Rigger And Bellman $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Rollagon $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Roller, Other Than Plant Mix $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Roller, Plant Mix Or Multi-lift $52.58 7A 3C 8P Underground Sewer & Water Materials Skagit Power Equipment Operators- Roto-mill, Roto-grinder $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Saws - Concrete $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Scraper, Self Propelled Under $53.00 7A 3C 8P Underground Sewer & Water 45 Yards Skagit Power Equipment Operators- Scrapers - Concrete & Carry All $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Scrapers, Self-propelled: 45 $53.49 7A 3C 8P Underground Sewer & Water Yards And Over Skagit Power Equipment Operators- Service Engineers - Equipment $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Shotcrete/gunite Equipment $50.22 7A 3C 8P Underground Sewer & Water

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 14 of 17

Skagit Power Equipment Operators- Shovel , Excavator, Backhoe, $52.58 7A 3C 8P Underground Sewer & Water Tractors Under 15 Metric Tons. Skagit Power Equipment Operators- Shovel, Excavator, Backhoe: $53.49 7A 3C 8P Underground Sewer & Water Over 30 Metric Tons To 50 Metric Tons Skagit Power Equipment Operators- Shovel, Excavator, Backhoes, $53.00 7A 3C 8P Underground Sewer & Water Tractors: 15 To 30 Metric Tons Skagit Power Equipment Operators- Shovel, Excavator, Backhoes: $54.04 7A 3C 8P Underground Sewer & Water Over 50 Metric Tons To 90 Metric Tons Skagit Power Equipment Operators- Shovel, Excavator, Backhoes: $54.61 7A 3C 8P Underground Sewer & Water Over 90 Metric Tons Skagit Power Equipment Operators- Slipform Pavers $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Spreader, Topsider & $53.49 7A 3C 8P Underground Sewer & Water Screedman Skagit Power Equipment Operators- Subgrader Trimmer $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Tower Bucket Elevators $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Tower Crane Over 175'in $54.61 7A 3C 8P Underground Sewer & Water Height, Base To Boom Skagit Power Equipment Operators- Tower Crane Up To 175' In $54.04 7A 3C 8P Underground Sewer & Water Height Base To Boom Skagit Power Equipment Operators- Transporters, All Track Or $53.49 7A 3C 8P Underground Sewer & Water Truck Type Skagit Power Equipment Operators- Trenching Machines $52.58 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Truck Crane Oiler/driver - 100 $53.00 7A 3C 8P Underground Sewer & Water Tons And Over Skagit Power Equipment Operators- Truck Crane Oiler/driver Under $52.58 7A 3C 8P Underground Sewer & Water 100 Tons Skagit Power Equipment Operators- Truck Mount Portable Conveyor $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Welder $53.49 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Wheel Tractors, Farmall Type $50.22 7A 3C 8P Underground Sewer & Water Skagit Power Equipment Operators- Yo Yo Pay Dozer $53.00 7A 3C 8P Underground Sewer & Water Skagit Power Line Clearance Tree Journey Level In Charge $44.86 5A 4A Trimmers Skagit Power Line Clearance Tree Spray Person $42.58 5A 4A Trimmers Skagit Power Line Clearance Tree Tree Equipment Operator $44.86 5A 4A Trimmers Skagit Power Line Clearance Tree Tree Trimmer $40.08 5A 4A Trimmers Skagit Power Line Clearance Tree Tree Trimmer Groundperson $30.20 5A 4A Trimmers

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 15 of 17

Skagit Refrigeration & Air Journey Level $23.95 1 Conditioning Mechanics Skagit Residential Brick Mason Journey Level $25.00 1 Skagit Residential Carpenters Journey Level $20.53 1 Skagit Residential Cement Masons Journey Level $16.00 1 Skagit Residential Drywall Applicators Journey Level $39.62 5D 1M Skagit Residential Drywall Tapers Journey Level $30.00 1 Skagit Residential Electricians JOURNEY LEVEL $28.93 1 Skagit Residential Glaziers Journey Level $36.20 7L 1H Skagit Residential Insulation Journey Level $13.96 1 Applicators Skagit Residential Laborers Journey Level $18.46 1 Skagit Residential Marble Setters Journey Level $25.00 1 Skagit Residential Painters Journey Level $15.00 1 Skagit Residential Plumbers & Journey Level $39.44 5A 1G Pipefitters Skagit Residential Refrigeration & Air Journey Level $36.92 5A 1G Conditioning Mechanics Skagit Residential Sheet Metal Journey Level (Field or Shop) $20.91 1 Workers Skagit Residential Soft Floor Layers Journey Level $23.46 1 Skagit Residential Sprinkler Fitters Journey Level $30.74 1 (Fire Protection) Skagit Residential Stone Masons Journey Level $25.00 1 Skagit Residential Terrazzo Workers Journey Level $25.00 1 Skagit Residential Terrazzo/Tile Journey Level $27.75 1 Finishers Skagit Residential Tile Setters Journey Level $25.00 1 Skagit Roofers Journey Level $31.84 1 Skagit Sheet Metal Workers Journey Level (Field or Shop) $56.69 7F 1E Skagit Shipbuilding & Ship Repair Carpenter $21.69 1 Skagit Shipbuilding & Ship Repair Electrician $18.72 1 Skagit Shipbuilding & Ship Repair Heat & Frost Insulator $58.93 5J 1S Skagit Shipbuilding & Ship Repair Laborer $11.71 1 Skagit Shipbuilding & Ship Repair Machinist $18.72 1 Skagit Shipbuilding & Ship Repair Operator $18.72 1 Skagit Shipbuilding & Ship Repair Painter $18.72 1 Skagit Shipbuilding & Ship Repair Pipefitter $18.72 1 Skagit Shipbuilding & Ship Repair Welder/burner $18.72 1 Skagit Sign Makers & Installers Journey Level $16.03 1 (Electrical) Skagit Sign Makers & Installers (Non- Journey Level $13.28 1 Electrical) Skagit Soft Floor Layers Journey Level $42.15 5A 3D Skagit Solar Controls For Windows Journey Level $9.32 1 Skagit Sprinkler Fitters (Fire Journey Level $36.91 1

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 16 of 17

Protection) Skagit Stage Rigging Mechanics (Non Journey Level $13.23 1 Structural) Skagit Stone Masons Journey Level $50.12 5A 1M Skagit Street And Parking Lot Journey Level $15.00 1 Sweeper Workers Skagit Surveyors Assistant Construction Site $52.58 7A 3C 8P Surveyor Skagit Surveyors Chainman $52.06 7A 3C 8P Skagit Surveyors Construction Site Surveyor $53.49 7A 3C 8P Skagit Telecommunication Journey Level $27.65 1 Technicians Skagit Telephone Line Construction - Cable Splicer $36.01 5A 2B Outside Skagit Telephone Line Construction - Hole Digger/Ground Person $20.05 5A 2B Outside Skagit Telephone Line Construction - Installer (Repairer) $34.50 5A 2B Outside Skagit Telephone Line Construction - Special Aparatus Installer I $36.01 5A 2B Outside Skagit Telephone Line Construction - Special Apparatus Installer II $35.27 5A 2B Outside Skagit Telephone Line Construction - Telephone Equipment Operator $36.01 5A 2B Outside (Heavy) Skagit Telephone Line Construction - Telephone Equipment Operator $33.47 5A 2B Outside (Light) Skagit Telephone Line Construction - Telephone Lineperson $33.47 5A 2B Outside Skagit Telephone Line Construction - Television Groundperson $19.04 5A 2B Outside Skagit Telephone Line Construction - Television Lineperson/Installer $25.27 5A 2B Outside Skagit Telephone Line Construction - Television System Technician $30.20 5A 2B Outside Skagit Telephone Line Construction - Television Technician $27.09 5A 2B Outside Skagit Telephone Line Construction - Tree Trimmer $33.47 5A 2B Outside Skagit Terrazzo Workers Journey Level $46.96 5A 1M Skagit Tile Setters Journey Level $46.96 5A 1M Skagit Tile, Marble & Terrazzo Journey Level $25.00 1 Finishers Skagit Traffic Control Stripers Journey Level $42.33 7A 1K Skagit Truck Drivers Asphalt Mix Over 16 Yards (W. $48.87 5D 3A 8L WA-Joint Council 28) Skagit Truck Drivers Asphalt Mix To 16 Yards (W. $48.03 5D 3A 8L WA-Joint Council 28) Skagit Truck Drivers Dump Truck $16.98 1 Skagit Truck Drivers Dump Truck And Trailer $16.98 1

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Page 17 of 17

Skagit Truck Drivers Other Trucks (W. WA-Joint $48.87 5D 3A 8L Council 28) Skagit Truck Drivers Transit Mixer $32.12 1 Skagit Well Drillers & Irrigation Pump Irrigation Pump Installer $11.60 1 Installers Skagit Well Drillers & Irrigation Pump Oiler $9.45 1 Installers Skagit Well Drillers & Irrigation Pump Well Driller $11.60 1 Installers

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 03/06/2014 Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

************************************************************************************************************ Overtime Codes

Overtime calculations are based on the hourly rate actually paid to the worker. On public works projects, the hourly rate must be not less than the prevailing rate of wage minus the hourly rate of the cost of fringe benefits actually provided for the worker.

1. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

B. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

C. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

D. The first two (2) hours before or after a five-eight (8) hour workweek day or a four-ten (10) hour workweek day and the first eight (8) hours worked the next day after either workweek shall be paid at one and one-half times the hourly rate of wage. All additional hours worked and all worked on Sundays and holidays shall be paid at double the hourly rate of wage.

E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

F. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

G. The first ten (10) hours worked on Saturdays and the first ten (10) hours worked on a fifth calendar weekday in a four-ten hour schedule, shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

H. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions or equipment breakdown) shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

I. All hours worked on Sundays and holidays shall also be paid at double the hourly rate of wage.

J. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over ten (10) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage.

K. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

M. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

1

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

1. N. All hours worked on Saturdays (except makeup days) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

O. The first ten (10) hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays, holidays and after twelve (12) hours, Monday through Friday and after ten (10) hours on Saturday shall be paid at double the hourly rate of wage.

P. All hours worked on Saturdays (except makeup days if circumstances warrant) and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

Q. The first two (2) hours after eight (8) regular hours Monday through Friday and up to ten (10) hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays (except Christmas day) shall be paid at double the hourly rate of wage. All hours worked on Christmas day shall be paid at two and one-half times the hourly rate of wage.

R. All hours worked on Sundays and holidays shall be paid at two times the hourly rate of wage.

S. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays and all other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays (except Labor Day) shall be paid at two times the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

V. All hours worked on Sundays and holidays (except Thanksgiving Day and Christmas day) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Thanksgiving Day and Christmas day shall be paid at double the hourly rate of wage.

W. All hours worked on Saturdays and Sundays (except make-up days due to conditions beyond the control of the employer)) shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

X. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. When holiday falls on Saturday or Sunday, the day before Saturday, Friday, and the day after Sunday, Monday, shall be considered the holiday and all work performed shall be paid at double the hourly rate of wage.

Y. All hours worked outside the hours of 5:00 am and 5:00 pm (or such other hours as may be agreed upon by any employer and the employee) and all hours worked in excess of eight (8) hours per day (10 hours per day for a 4 x 10 workweek) and on Saturdays and holidays (except labor day) shall be paid at one and one-half times the hourly rate of wage. (except for employees who are absent from work without prior approval on a scheduled workday during the workweek shall be paid at the straight-time rate until they have worked 8 hours in a day (10 in a 4 x 10 workweek) or 40 hours during that workweek.) All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and Labor Day shall be paid at double the hourly rate of wage.

Z. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid the straight time rate of pay in addition to holiday pay.

2

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

2 ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

B. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage.

C. All hours worked on Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at two times the hourly rate of wage.

F. The first eight (8) hours worked on holidays shall be paid at the straight hourly rate of wage in addition to the holiday pay. All hours worked in excess of eight (8) hours on holidays shall be paid at double the hourly rate of wage.

G. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay.

H. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage.

O. All hours worked on Sundays and holidays shall be paid at one and one-half times the hourly rate of wage.

R. All hours worked on Sundays and holidays and all hours worked over sixty (60) in one week shall be paid at double the hourly rate of wage.

U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked over 12 hours in a day or on Sundays and holidays shall be paid at double the hourly rate of wage.

W. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. On a four-day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The first eight (8) hours worked on the fifth day shall be paid at one and one-half times the hourly rate of wage. All other hours worked on the fifth, sixth, and seventh days and on holidays shall be paid at double the hourly rate of wage.

3. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

A. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at time and one-half the straight time rate. Hours worked over twelve hours (12) in a single shift and all work performed after 6:00 pm Saturday to 6:00 am Monday and holidays shall be paid at double the straight time rate of pay. Any shift starting between the hours of 6:00 pm and midnight shall receive an additional one dollar ($1.00) per hour for all hours worked that shift. The employer shall have the sole discretion to assign overtime work to employees. Primary consideration for overtime work shall be given to employees regularly assigned to the work to be performed on overtime situations. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more.

B. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

3

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

3. C. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more.

D. All hours worked between the hours of 6:00 pm and 6:00 am, Monday through Saturday, shall be paid at a premium rate of 15% over the hourly rate of wage. All other hours worked after 6:00 am on Saturdays, shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

E. All hours worked Sundays and holidays shall be paid at double the hourly rate of wage. Each week, once 40 hours of straight time work is achieved, then any hours worked over 10 hours per day Monday through Saturday shall be paid at double the hourly wage rate.

F. All hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay.

H. All work performed on Sundays between March 16th and October 14th and all Holidays shall be compensated for at two (2) times the regular rate of pay. Work performed on Sundays between October 15th and March 15th shall be compensated at one and one half (1-1/2) times the regular rate of pay.

I. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. In the event the job is down due to weather conditions during a five day work week (Monday through Friday,) or a four day-ten hour work week (Tuesday through Friday,) then Saturday may be worked as a voluntary make-up day at the straight time rate. However, Saturday shall not be utilized as a make-up day when a holiday falls on Friday. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

4. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

A. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturdays, Sundays and holidays shall be paid at double the hourly rate of wage.

Holiday Codes

5. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, and Christmas Day (7).

B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, the day before Christmas, and Christmas Day (8).

C. Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8).

D. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8).

4

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

5. H. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Day after Thanksgiving Day, And Christmas (6).

I. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6).

J. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Eve Day, And Christmas Day (7).

K. Holidays: New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9).

L. Holidays: New Year’s Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, And Christmas Day (8).

N. Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (9).

P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday And Saturday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). If A Holiday Falls On Sunday, The Following Monday Shall Be Considered As A Holiday.

Q. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6).

R. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Day After Thanksgiving Day, One-Half Day Before Christmas Day, And Christmas Day. (7 1/2).

S. Paid Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day (7).

T. Paid Holidays: New Year's Day, Washington’s Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, Christmas Day, And The Day Before Or After Christmas (9).

Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8).

Holiday Codes Continued

6. A. Paid Holidays: New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (8).

E. Paid Holidays: New Year's Day, Day Before Or After New Year's Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Day After Thanksgiving Day, Christmas Day, And A Half-Day On Christmas Eve Day. (9 1/2).

G. Paid Holidays: New Year's Day, Martin Luther King Jr. Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, The Friday After Thanksgiving Day, Christmas Day, And Christmas Eve Day (11).

H. Paid Holidays: New Year's Day, New Year’s Eve Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Christmas Day, The Day After Christmas, And A Floating Holiday (10). 5

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

6. I. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, And Christmas Day (7).

T. Paid Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Last Working Day Before Christmas Day, And Christmas Day (9).

Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). If a holiday falls on Saturday, the preceding Friday shall be considered as the holiday. If a holiday falls on Sunday, the following Monday shall be considered as the holiday.

Holiday Codes Continued

7. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday And Saturday After Thanksgiving Day, And Christmas Day (8). Any Holiday Which Falls On A Sunday Shall Be Observed As A Holiday On The Following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day.

B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

C. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

D. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran’s Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Unpaid Holidays: President’s Day. Any paid holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any paid holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

E. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

F. Holidays: New Year’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the last working day before Christmas day and Christmas day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

G. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday.

H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

6

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

7. I. Holidays: New Year's Day, President’s Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

J. Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

M. Paid Holidays: New Year's Day, The Day after or before New Year’s Day, President’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, And the Day after or before Christmas Day 10). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday.

O. Paid Holidays: New Year's Day, The Day After Or Before New Year’s Day, President’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, Christmas Day, The Day After Or Before Christmas Day, And The Employees Birthday. 11). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday.

Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day.

R. Paid Holidays: New Year's Day, the day after or before New Year’s Day, President’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day after or before Christmas Day (10). If any of the listed holidays fall on Saturday, the preceding Friday shall be observed as the holiday. If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.

S. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Christmas Day, The Day After Christmas, And A Floating Holiday (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.

7

Benefit Code Key – Effective 3-5-2014 thru 8-30-2014

Note Codes

8. A. In addition to the hourly wage and fringe benefits, the following depth premiums apply to depths of fifty feet or more: Over 50’ To 100' -$2.00 per Foot for Each Foot Over 50 Feet Over 100' To 150' -$3.00 per Foot for Each Foot Over 100 Feet Over 150' To 220' -$4.00 per Foot for Each Foot Over 150 Feet Over 220' -$5.00 per Foot for Each Foot Over 220 Feet

C. In addition to the hourly wage and fringe benefits, the following depth premiums apply to depths of fifty feet or more: Over 50’ To 100' -$1.00 per Foot for Each Foot Over 50 Feet Over 100' To 150' -$1.50 per Foot for Each Foot Over 100 Feet Over 150' To 200' -$2.00 per Foot for Each Foot Over 150 Feet Over 200' -Divers May Name Their Own Price

D. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour.

L. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $0.75, Level B: $0.50, And Level C: $0.25.

M. Workers on hazmat projects receive additional hourly premiums as follows: Levels A & B: $1.00, Levels C & D: $0.50.

N. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00, Level B: $0.75, Level C: $0.50, And Level D: $0.25.

P. Workers on hazmat projects receive additional hourly premiums as follows -Class A Suit: $2.00, Class B Suit: $1.50, Class C Suit: $1.00, And Class D Suit $0.50.

Q. The highest pressure registered on the gauge for an accumulated time of more than fifteen (15) minutes during the shift shall be used in determining the scale paid.

R. Effective August 31, 2012 – A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. These classifications are only effective on or after August 31, 2012.

S. Effective August 31, 2012 – A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012.

T. Effective August 31, 2012 – A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012.

8

APPENDIX C Ecology Specifications

WASHINGTON STATE DEPARTMENT OF ECOLOGY STORMWATER GRANT PROGRAMS SPECIFICATIONS INSERT

General Partial funding of this project is being provided by the Washington State Department of Ecology’s (Ecology) Stormwater Grant Program.

Compliance with State and Local Laws The construction of the project, including the letting of subcontracts in connection therewith, shall conform to the applicable requirements of state and local laws and ordinances.

State Interest Exclusion It is anticipated that this project will be funded in part by the Washington State Department of Ecology . Neither the State Of Washington nor any of its departments or employees are, or shall be, a party to this contract or any subcontract.

Third Party Beneficiary Partial funding of this project is being provided through the Washington State Department of Ecology Stormwater Grant Program. All parties agree that the State of Washington shall be, and is hereby, named as an express third-party beneficiary of this contract, with full rights as such.

Access to the construction site and to records The contractor shall provide for the safe access to the construction site and to the contractor's records by Washington State Department of Ecology personnel.

The Contractor shall maintain accurate records and accounts to facilitate the Owner’s audit requirements and shall ensure that all subcontractors maintain auditable records.

These Project records shall be separate and distinct from the Contractor’s other records and accounts.

All such records shall be available to the Owner and to Washington State Department of Ecology personnel for examination. All records pertinent to this project shall be retained by the Contractor for a period of three (3) years after the final audit.

Protection of the Environment No construction related activity shall contribute to the degradation of the environment, allow material to enter surface or ground waters, or allow particulate emissions to the atmosphere, which exceed state or federal standards. Any actions that potentially allow a discharge to state waters must have prior approval of the Washington State Department of Ecology.

Project Signs The Contractor shall display Ecology’s logo in a manner that informs the public that the project received financial assistance from the Washington State Stormwater Grant Program.

Utilization of Minority and Women Business Enterprises All bidders are encouraged to utilize certified minority-owned and women-owned businesses to the extent possible in the performance of this contract. All prospective bidders or persons submitting qualifications should take the following steps, when possible.

1. Include qualified minority and women's businesses on solicitation lists. 2. Assure that qualified minority and women's businesses are solicited whenever they are potential sources of services or supplies. 3. Divide the total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by qualified minority and women's businesses. 4. Establish delivery schedules, where work requirements permit, which will encourage participation of qualified minority and women's businesses. 5. Use the services and assistance of the State Office of Minority and Women's Business Enterprises (OMWBE) and the Office of Minority Business Enterprises of the U.S. Department of Commerce, as appropriate.

All prospective bidders must provide a list of the MBE/WBE subcontractors they intend to use during the project. This list must be provided with the bid package.

Revised 3/29/12

APPENDIX D Construction Contract and Contract Bond – Informational Only

CONSTRUCTION CONTRACT AGREEMENT

THIS AGREEMENT, effective upon the date of mutual execution, is made and entered into between Skagit County, Washington, and ______, hereinafter called the Contractor.

WITNESSETH: That in consideration of the terms and conditions contained herein and attached and made a part of this agreement, the parties hereto covenant and agree as follows:

I. The Contractor shall do all work and furnish all tools, materials, equipment, and transportation required for the construction of Skagit County Street Waste Facility #WA402170 in accordance with and as described in the attached plans and specifications and the Washington State Department of Transportation Standard Specifications for Road, Bridge, and Municipal Construction M 41-10 2012 edition, which are by this reference incorporated herein and made a part hereof, and shall perform any changes to the work in accord with the Contract Documents.

The Contractor shall provide and bear the expense of all equipment, work, and labor of any sort whatsoever that may be required for the transfer of materials and for constructing and completing the work provided for in this contract and every part thereof and shall guarantee said materials and work for a period of one year after substantial completion of this contract, except as may be modified by the plans, specifications and/or contract documents.

II. Skagit County, Washington, hereby promises and agrees with the Contractor to retain and does retain the Contractor to provide the materials and to do and cause to be done the above-described work and to complete and finish the same according to the attached plans and specifications and the terms and conditions herein contained, and hereby contracts to pay for the same according to the attached specifications and the schedule of prices bid and hereto attached, at the time and in the manner and upon the conditions provided for in this contract.

III. The Contractor for himself/herself, and for his/her heirs, executors, administrators, successors, and assigns, does hereby agree to full performance of all covenants required of the Contractor in the contract.

IV. It is further provided that no liability shall attach to Skagit County by reason of entering into this contract, except as provided herein.

IN WITNESS WHEREOF the Contractor has executed this instrument on the day and year first below written, and the Authorized Official has caused this instrument to be executed by and in the name of Skagit County the day and year first above written.

CONTRACTOR

Signature ______Mailing Address:

Printed ______

Title ______

Date ______Telephone No. (___) ____-____

DATED this _____ day of ______, 2014.

BOARD OF COUNTY COMMISSIONERS SKAGIT COUNTY, WASHINGTON

Ron Wesen, Chair

Kenneth A. Dahlstedt, Commissioner

Attest: Sharon D. Dillon, Commissioner

Clerk of the Board For contracts under $5,000: Authorization per Resolution R20030146

Recommended: County Administrator

Department Head

Approved as to form:

Civil Deputy Prosecuting Attorney

Approved as to indemnification:

Risk Manager

Approved as to budget:

Budget & Finance Director

CONTRACT BOND

KNOW ALL MEN BY THESE PRESENTS, that Skagit County, a Municipal Corporation of Washington, has awarded ______of ______, as Principal, and ______as Surety, are jointly and severally held and bound unto the County of Skagit in the penal sum of ______($______), dollars, for the payment of which we jointly and severely bind ourselves, our heirs, executors, administrators, and assigns, and successors and assigns, firmly by these presents.

THE CONDITION of this bond is such that whereas, on the ______day of ______A.D., 2014, the said Principal, herein, executed a certain contract with the County of Skagit by the items, conditions and provisions of which contract the said ______, Principal, herein agree to furnish all material and do certain work, to wit: That ______will undertake and complete the construction of

according to the maps, plans and specifications made a part of said contract, which contract as so executed, is hereunto attached, is now referred to and by reference is incorporated herein and made a part hereof as fully for all purposes as if here set forth at length. The bond shall cover all approved change orders as if they were in the original contract.

NOW, THEREFORE, if the Principal herein shall faithfully and truly observe and comply with the terms, conditions and provisions of said contract in all respects and shall well and truly and fully do and perform all matters and things by ______(principal) undertaken to be performed under said contract, upon the terms proposed therein, and within the time prescribed therein, and until the same is accepted, and shall pay all laborers, mechanics, subcontractors and material men, and all persons who shall supply such contractor or subcontractor with provisions and supplies for the carrying on of such work, and shall in all respects

faithfully perform said contract according to law, then this obligation to be void, otherwise to remain in full force and effect.

WITNESS our hands this ______day of ______, 2014.

______

______

______(Principal)

______

______

______Attorney-in-Fact, Surety

______Name and Address Local Office of Agent

APPROVED AS TO FORM APPROVED AS TO FORM RICH WEYRICH JESSICA NEILL HOYSON Skagit County Prosecuting Attorney Skagit County Risk Manager

BY: ______Approving Authority

DATE: ______, 2014

______SURETY BOND NUMBER CONTRACT NUMBER

______

APPENDIX E Proposal – Informational Only

Proposal For Bidding Purposes

For the Construction of:

SKAGIT COUNTY STREET WASTE FACILITY #WA402170

SKAGIT COUNTY PUBLIC WORKS

SKAGIT COUNTY Public Works Department 1800 Continental Place Mount Vernon, WA 98273

PROPOSAL

Skagit County Street Waste Facility #WA402170

Skagit County, Washington

2014

** ENTIRE PROPOSAL TO BE RETURNED AS YOUR BID PACKAGE **

All bid envelopes must be plainly marked on the outside, “Sealed Bid: Skagit County Street Waste Facility Project #WA402170.

Sealed Bids will be received at the following location before the specified time:

Hand Delivered: Skagit County Commissioners Reception Desk 1800 Continental Place, Suite 100 Mount Vernon, Washington, 98273-5625

Via Mail: Skagit County Commissioners 1800 Continental Place, Suite 100 Mount Vernon, Washington, 98273-5625

The bid opening date for this project will be Monday, April 7, 2014. The bids will be publicly opened and read after 2:00 p.m. on this date.

Skagit County Street Waste Facility WA402170

PROPOSAL

BOARD OF SKAGIT COUNTY COMMISSIONERS MOUNT VERNON, WASHINGTON 98273-5625

Attention:

This certifies that the undersigned has examined the location of

SKAGIT COUNTY STREET WASTE FACILITY #WA402170

and that the plans, specifications and contract governing the work embraced in this improvement, and the method by which payment will be made for said work is understood. The undersigned hereby proposes to undertake and complete the work embraced in this improvement, or as much thereof as can be completed with the money available in accordance with the said plans, specifications, and contract, and the following schedule of rates and prices:

(Note: Unit prices for all items, all extensions, and total amount of bid shall be shown. All entries must be typed or entered in ink.)

The Contractor shall include State Sales Tax with the bid, per Section APWA GSP 1-07.2(1) of the 2012 Standard Specification for Road Bridge and Municipal Construction, Rule 171 applies.

Skagit County Street Waste Facility #WA402170

Item Unit of Description Spec QTY No. Measure Unit Price Total Price

1 Mobilization 1-09.7 1.00 LS $______.___ $______.___

Removal of Structures 2 SP 2-02 1.00 LS and Obstructions $______.___ $______.___

3 Dewatering SP 7-20 5.00 DAYS $______.___ $______.___

4 Sump Area SP 8-31 1.00 LS $______.___ $______.___

5 Decant Area SP 8-37 1.00 LS $______.___ $______.___

6 Electrical Work SP 8-36 1.00 LS $______.___ $______.___

Skagit County Street Waste Facility WA402170

7 Unanticipated Site Work SP 1-09.6 EST DOL $ __1.00_ $______5,000.00_

Spill Prevention Control 8 and Countermeasures 1-07.15(1) 1.00 LS $______.___ $______.___ Plan

TOTAL BID $______.___

UNIT BID PRICES SHALL INCLUDE SALES TAX IN BID ITEMS. REFER TO SECTION 1-07.2(1) OF THE STANDARD SPECIFICATIONS FOR ROAD, BRIDGE, AND MUNICIPAL CONSTRUCTION 2012 AND DEPARTMENT OF REVENUE RULE #171

MUST ACCOMPANY EACH BID

FAILURE TO SIGN OR COMPLETE ALL INFORMATION CAN RESULT IN REJECTION OF THE PROPOSAL AS NON-RESPONSIVE.

Skagit County Street Waste Facility WA402170

PROPOSAL – Signature Page

The bidder is hereby advised that by signature of this proposal he/she is deemed to have acknowledged all requirements and signed all certificates contained herein.

The undersigned hereby agrees to pay labor not less than the prevailing rates of wages in accordance with the requirements of the special provisions for this project.

A proposal guaranty in an amount of five percent (5%) of the total bid, based upon the approximate estimate of quantities at the above prices and in the form as indicated below is attached hereto:

CASH In the amount of $______Dollars

CASHIER’S CHECK In the amount of $______Dollars

CERTIFIED CHECK In the amount of $______Dollars (Payable to Skagit County)

PROPOSAL BOND In the amount five percent (5%) of the total bid.

Receipt is hereby acknowledged of Addendum(s) No.(s) , ___ & __

Signature of Authorized Officials(s):

Proposal Must Be Signed

Firm Name:

Address:

Phone Number:

State of Washington Contractor’s License No.

UBI No. Employment Security Department No.

Note: (1) This proposal form is not transferable and any alteration of the firm’s name entered hereon without prior permission from the Skagit County will be cause for considering the proposal irregular and subsequent rejection of the bid. (2) Please refer to Section 1-02.6 of the Standard Specifications, “Preparation of Proposal”, or “Article 4” of the Instruction to Bidders for building construction jobs. (3) Should it be necessary to modify this proposal either in writing or by electronic means, please make reference to the following proposal number in your communication: WA402170.

MUST ACCOMPANY EACH BID

FAILURE TO SIGN OR COMPLETE ALL INFORMATION CAN RESULT IN REJECTION OF THE PROPOSAL AS NON-RESPONSIVE. Skagit County Street Waste Facility WA402170

NON-COLLUSION DECLARATION

I, by signing the proposal, hereby declare, under penalty of perjury under the laws of the United States that the following statements are true and correct:

1. That the undersigned person(s), firm, association or corporation has (have) not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the project for which this proposal is submitted.

2. That by signing the signature page of this proposal, I am deemed to have signed and have agreed to the provisions of this declaration.

NOTICE TO ALL BIDDERS

To report bid rigging activities call:

1-800-424-9071

The U.S. Department of Transportation (USDOT) operates the above toll free ’hotline’ Monday through Friday, 8:00 a.m. to 5:00 p.m., Eastern Standard Time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the ‘hotline’ to report such activities.

The ‘hotline’ is part of USDOT’s continuing effort to identify and investigate highway construction fraud and abuse and is operated under the direction of the USDOT Inspector General. All information will be treated confidentially and caller anonymity will be respected.

INITIAL:

MUST ACCOMPANY EACH BID

FAILURE TO SIGN OR COMPLETE ALL INFORMATION ON THE FORMS PROVIDED CAN RESULT IN REJECTION OF THE PROPOSAL AS NON-RESPONSIVE Skagit County Street Waste Facility WA402170

NON-DISBARMENT CERTIFICATION

Are you on Comptroller General’s list of Ineligible Contractors or list of parties excluded from Federal procurement or non-procurement programs? NO YES

Company Name:

Type of Business Corporation Partnership (general) Partnership (limited) Sole Proprietorship Limited Liability Company

FID #:

Company Address:

The County/State/Zip:

Phone: ______Fax:

E-Mail:

Print Name of Signatory:

Print Title of Signatory:

INITIAL:

MUST ACCOMPANY EACH BID

FAILURE TO SIGN OR COMPLETE ALL INFORMATION ON THE FORMS PROVIDED CAN RESULT IN REJECTION OF THE PROPOSAL AS NON-RESPONSIVE

Skagit County Street Waste Facility WA402170

SUBMIT THE ENCLOSED PROPOSAL BOND FORM WITH YOUR PROPOSAL

USE OF OTHER FORMS MAY SUBJECT YOUR BID TO REJECTION

NOTE: USE OF OTHER FORMS MAY LIMIT THE BOND BELOW AN AMOUNT EQUAL TO FIVE PERCENT (5%) OF THE BID TOTAL

Skagit County Street Waste Facility WA402170

PROPOSAL BOND

KNOW ALL MEN BY THESE PRESENTS, That we, ______of ______as principal, and the ______a corporation duly organized under the laws of the State of ______, and authorized to do business in the State of Washington, as surety, are held and firmly bound unto Skagit County in the full and penal sum of five (5) percent of the total amount of the bid proposal of said principal for the work hereinafter described for the payment of which, well and truly to be made, we bind our heirs, executors, administrators and assigns, and successors and assigns, firmly by these presents.

The condition of this bond is such, that whereas the principal herein is herewith submitting his or its sealed proposal for the following construction, to wit:

______

______

said bid and proposal, by reference thereto, being made a part hereof.

NOW THEREFORE, If the said proposal bid by said principal be accepted, and the contract be awarded to said principal, and if said principal shall duly make and enter into and execute said contract and shall furnish bond as required by Skagit County within a period of twenty (20) days from and after said award, exclusive of the day of such award, then this obligation shall be null and void, otherwise it shall remain and be in full force and effect.

IN TESTIMONY WHEREOF, The principal and surety have caused these presents to be signed and sealed this ______day of ______, 2014.

(Principal)

(Surety)

(Attorney-in-fact)

Skagit County Street Waste Facility WA402170

APPENDIX F Construction Quality Assurance Plan

Construction Quality Assurance Plan Skagit County Street Waste Facility Prepared for Skagit County, Washington July 23, 2013

Construction Quality Assurance Plan, Skagit County Street Waste Facility

Table of Contents

List of Tables ...... iii 1. Introduction ...... 1-1 1.1 Purpose ...... 1-1 1.2 Scope ...... 1-1 2. Construction Organization ...... 2-1 3. Construction Observation ...... 3-1 4. Construction Schedule ...... 4-1 4.1 Project Meetings...... 4-1 4.2 Construction Progress Schedule ...... 4-1 5. Quality Control ...... 5-1 6. Contract Modification Procedure/Change Order Procedure ...... 6-1 6.1 Initiation ...... 6-1 6.2 Pricing ...... 6-1 6.3 Work Change Directive and Force Account ...... 6-1 6.4 Washington State Department of Ecology Requirements ...... 6-1 7. Technical Records Handling ...... 7-1 7.1 Location of Files ...... 7-1 7.2 Correspondence ...... 7-1 7.3 Outgoing Submittals ...... 7-1 7.4 As-Built Documentation ...... 7-1 8. Construction Safety and Health ...... 8-1 8.1 Spill Prevention, Control, and Countermeasures Plan ...... 8-1 Appendix A: Construction Schedule ...... 1

List of Tables

Table 2-1. Key Personnel for the Skagit County Street Waste Decant and Disposal Facility ...... 2-1

iii

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 1

Section 1 Introduction

This section provides the purpose and scope of this Construction Quality Assurance Plan (CQAP) for the Skagit County (County) regional street waste decant and disposal facility (Facility). 1.1 Purpose The purpose of a Construction Quality Assurance Plan, as defined in Washington Administrative Code (WAC) 173-240-020, is to provide a means by which the professional engineer in responsible charge of inspection (observation) of the project will determine that the facilities are constructed without significant change from the Washington State Department of Ecology (Ecology) approved Plans and Specifications. The CQAP does not take precedence over the Contract Documents. Individual sections of the Contract Documents identified herein should be referenced for further detail as applicable. 1.2 Scope The Street Waste Facility project involves retrofitting an existing solid waste handling structure owned by the County into a regional street waste decant and disposal facility. The main purpose of this Facility will be to provide pretreatment for street sweeping and storm drain cleaning material prior to discharging effluent to the sanitary sewer. The project is being funded by the Washington State Department of Ecology FY 2012 Statewide Stormwater Grant Program, and by the County. Work for the Facility is described in Division 1 of the Special Provisions, “Description of Work.” The Facility involves the retrofitting of an existing structure, located at 14104 Ovenell Road, Mount Vernon, Washington. Retrofitting of the existing structure for use as the Facility includes the following activities: • Demolition, re-grading, and replacing of sections of existing slab-on-grade • Installation of reinforcing steel in epoxy adhesive • Construction of concrete footings and walls including the placing of reinforcing steel • Installation of timber weirs in angle guides • Fabrication and installation of an access ladder complete with fall protection • Installation of wedge/expansion anchors • Erection of chain link fencing and swing gate • Construction of a sump with oil/water separator • Installation of a sump pump, flow meter, discharge piping to an existing manhole, and associated electrical routing Additionally, the Contractor shall be responsible for protecting all items within the existing building that are to remain in place.

1-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 2

Section 2 Construction Organization

A summary of the parties involved in the construction, their contact information, and their role in Facility construction is provided in Table 2-1, which shall be updated by the selected Contractor following award of the construction contract.

Table 2-1. Key Personnel for the Skagit County Street Waste Decant and Disposal Facility Owner Engineer Contractor Funding Agency (FA) Washington State Department of Skagit County and Caldwell To Be Determined Ecology Kevin Renz Katie Saltanovitz, P.E. Name Robert Nolan, FA Project Manager Operations Manager, Solid Waste Engineering Project Manager Construction Manager 425.649.7197 360.336.9400 206.749.2260 xxx.xxx.xxx Michael See & Mike Farthing Design Team Name Douglas Howie, P.E. County Project Managers (Civil, Mechanical, and Electrical) Superintendent FA Project Engineer 360.336.9400 Brown and Caldwell xxx.xxx.xxx 360.407.6444 Meghan MacMullen Design Team Sean Mellon County Project Administrative (Structural) FA Financial Manager Assistant Bright Engineering 360.407.7151 360.339.9333 x3171 Jack Moore County Building Official 360.336.9410

The Skagit County Public Works Engineering Division personnel, supported by the County Building Official, will work as part of the Project Representative “team.” The Project Representative(s) will perform construction observations as described in Section 3 of this CQAP and will act as a liaison among the Engineering Project Manager, Contractor, and County. At a minimum, the Project Representative(s) will be at the work site for the activities and milestones listed in Section 3 of this CQAP. The Project Representative(s) will coordinate with the County Project Managers on a weekly basis through teleconferences and/or onsite meetings. The County Project Managers will oversee the work by the Engineer and Project Representative(s). They will also represent the County on all contractual matters with the Engineer, Contractor, and Funding Agency. The County Project Managers, or designated representative(s), will provide general coordination with the Engineer, Project Representative(s), Funding Agency, and Contractor. Principal duties of the County Project Managers, or designated representative(s), include the following: • Coordinate and monitor timely review and return of Contractor’s submittals • Coordinate and monitor timely response and resolution to design clarifications and construction issues as they arise • Coordinate and monitor sub-consultant work effort (if any) • Review Contractor’s schedule of values, certified payrolls for prevailing wages, and other submittals

2-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 2

• Coordinate change orders with the County and Funding Agency, including evaluation, negotiation, and recommendation • Conduct periodic construction progress meetings • Supervise activities of the Project Representative(s) • Conduct final inspection of the Facility • Cooperate and work closely with Funding Agency Representatives The County Project Managers, or designated representative(s), will review submittals from the Contractor and when required, solicit technical assistance and clarifications from the Design Team. The County Project Managers, or designated representative(s), will coordinate inspection/observation assistance for specialized construction activities as required. Efforts of the Design Team and sub-consultants will be coordinated through the County Project Managers. The County Project Managers, or designated representative(s), will be responsible for all project filing. The Funding Agency Project Engineer will review and accept change orders on Ecology’s behalf. The State Funding Agency Project Engineer will also review and accept project substantial completion determination and will review and accept pay requests on Ecology’s behalf.

2-2

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 3

Section 3 Construction Observation

The Project Representative(s) employed by the County will monitor progress of the Facility construction Contract. The Project Representative(s) may reject or accept materials and equipment to be incorporated in the work as authorized by the County. The County Building Official or designated representative can approve work within their County-delegated authority. The Project Representative(s) are not authorized to approve or accept any portion of the work or to issue instructions contrary to the Contract Documents. Approvals, acceptances, or instructions related to the Contract Documents must be given in writing and signed by the County. The principal activities of the Project Representative(s) are as follows: • Monitor construction work and progress • Review Contractor’s Critical Path Method schedules regularly • Assist in resolution of construction issues • Assist in administering a quality control program, including the following: − Monitor quality of testing service − Maintain quality control records of all tests and test results − Monitor frequency of testing • Physically observe all construction completed work for the activities and milestones discussed in this section • Observe required Contractor tests • Maintain daily log and construction records • Assist in the review of Contractor progress payment requests: − Obtain accurate measurements on unit price items − Verify Contractor’s monthly work quantities • Participate in field management meetings and biweekly construction meetings • Report and document field conditions that prevent construction per original design • Review Contractor’s as-built data • Take photographs and/or video for documentation The Contractor shall notify (a minimum of 48 hours in advance) the County Project Managers, Operations Manager, and Project Representative(s) to schedule completed work reviews for the following activities and milestones: • After demolition and re-grading of the slab-on-grade areas: The subgrade shall be observed and tested to verify that it has been prepared as required by project plans and specifications prior to gravel base installation. Gravels shall be observed after installation to verify that it has the proper thickness, confinement, and consolidation prior to placing reinforcing steel and concrete.

3-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 3

• After excavation and preparation of footings: Footings shall be checked for proper depth and width, and gravels supporting footings shall be verified as having the required thickness, confinement, and consolidation. • Prior to and during the installation of epoxy anchors: Locations to receive epoxied reinforcing steel shall be checked for embedment depth, hole diameter, and proper installation of reinforcing steel into epoxy adhesives per manufacturer recommendations. • After installation of reinforcing steel prior to closing of forms: Reinforcing steel shall be checked for proper size, location, clearances, and spacing as required by the project plans, specifications, and governing building codes. • Concrete placement: Concrete placements shall be observed to ensure that workmanship and materials supplied meet the requirements set forth by the project plans, specifications, and governing building codes. • Anchors, embeds, and insert installation: Prior to covering with formwork and prior to concrete placement, items shall be observed for quantity, location, embedment depth, and type to verify that they meet the requirements of the project plans, specifications, and governing building code. • After installation of aboveground piping: Piping shall be observed to verify that the size and type of piping installed meets the requirements of the project plans and specifications. Pressure testing of aboveground piping shall also be observed. • After installation of below-grade piping: Prior to backfilling of pipe trench the piping shall be pressure- tested and checked to verify that sizes and materials meet the requirements set forth in the project plans and specifications. • Sump pump along with associated equipment and electrical wiring: The pump shall be observed upon procurement to ensure the materials supplied are consistent with project submittals and specifications. Once installed with associated equipment and connected to a power source, the pump shall be observed to verify that the equipment operates as required by project plans and specifications. • Prefabricated access ladder and associated hardware: Upon the procurement of the access ladder and associated hardware, it shall be verified that the fabricated materials and associated hardware meet the requirements of the project plans and specifications. The fabricator of the access ladder shall provide a certificate of compliance for review and filing, and it must indicate that the welding and fabrication of the access ladder meets the applicable construction and workmanship provisions of the governing building codes and project plans and specifications. • Special cases: Work that, in the opinion of the County Building Official or other agency having jurisdiction, involves unusual hazards or conditions. Removal and/or correction of deficient work shall be the responsibility of the Contractor, regardless of when notified by the Project Representative(s), Operations Manager, Engineering Project Manager, County Building Official, or other agency having jurisdiction over the project. Deficient work shall be any work that has been established as not meeting the requirements of the project plans, specifications, and/or governing building codes as established by the Project Representative(s), Operations Manager, Engineering Project Manager, County Building Official, designated representatives, or other agency having jurisdiction over the project.

3-2

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 4

Section 4 Construction Schedule

This section describes project meetings and a construction schedule for the Street Waste Facility project. 4.1 Project Meetings Project meetings will include a pre-construction conference, periodic progress meetings, and weekly Contractor safety meetings. 4.2 Construction Progress Schedule The Contractor is required to prepare and submit a Type A progress schedule in accordance with paragraph 1-08.3 of the Standard Specifications (WSDOT 2012). The progress schedule shall be in the form of a Gantt Chart that provides a logical sequence and identifies the interdependence of construction activities. The critical path for completion of all construction activities within the specified construction period shall be identified in a summary network diagram. The Contractor shall attach the Construction Schedule as Appendix A of this CQAP. At monthly intervals, the Contractor shall produce a report of projected scheduled activities to be started, in process, or completed during the upcoming reporting period (Look-Ahead Report). At the end of the reporting period, the Contractor and Engineer shall jointly make entries on the preceding Look-Ahead Report as follows: • To show actual progress • To identify those activities started and those completed during the previous period • To show the estimated time required to complete each activity started but not yet completed • To reflect any changes in the network diagram Procedures for schedule changes by the Contractor or the County are described in Section 1-08 of the Contract Documents. Extensions of time will be based on provisions in Section 1-08.8. Considerations for extensions include the following: • Extensions of time will be granted only to the extent that equitable time adjustments for the activity or activities affected exceed the total float along the channels involved at the time Notice to Proceed was issued for the change and that the delays affected the Contract completion date. • Extensions of time will be granted only if circumstances prevail that are beyond the control of the Contractor and that could not be reasonably anticipated.

4-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 5

Section 5 Quality Control

The Contractor shall be responsible for quality control testing in accordance with Section 1-06 of the Contract Documents, which is summarized as follows: • Soils: in-place density tests required by the Contract Documents, Section 2-03.3.(14)B. • Concrete: Mix design, consistency, air content, temperature, compressive strength verification test cylinder casting, concrete compressive strength testing, and all other testing required by the Contract Documents, Section 033000, “Cast-in-Place Concrete” Other testing shall be performed as stated in the Contract Documents. Other quality control testing required by the Contract and performed by the Contractor in the presence of the Project Representative(s) includes the following: • Hydrostatic testing of all above- and below-ground pipes • Testing of all valves for operation • Startup testing of sump pump • Manufacturer’s installation certification is required for all equipment • Motor data • Wire resistance test • Flow meter calibration testing The Contractor shall notify the Project Representative(s), Operations Manager, and County Project Managers sufficiently in advance of operations to allow for assignment of personnel and scheduling of tests. In no case shall notification be less than 48 hours before the required test. The Contractor shall provide the County Project Managers with four copies of all test results within 7 days of receipt from the testing laboratory.

5-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 6

Section 6 Contract Modification Procedure/Change Order Procedure

Contract modification and change order procedures are provided in Section 1-04.4, “Changes,” of the Contract Documents. The Contract price and schedule may be changed only by an executed change order. Funding Agency concurrence is required for all change orders. 6.1 Initiation Change orders may be initiated by the County or Contractor. The terminology used for a potential change order as initially issued by the County to the Contractor is a “Request for Proposal” (RFP). RFPs are numbered sequentially as each change is identified for issuance to the Contractor. Contractor-initiated change orders are proposed by a letter to the County Project Managers explaining why the Contract Documents are deficient or how changes may be advantageous to both the County and the Contractor. After concurrence on price has been reached, the RFP will be incorporated into a change order for signature by the Contractor, County, and Funding Agency. Only after execution of the change order will adjustment of the Contract price or schedule occur. 6.2 Pricing The preferred method of pricing a Contract change is through an agreed lump sum. Change order price will be negotiated with the Contractor by the County Project Managers. Depending on the magnitude of the proposed change, the Design Team may prepare an independent cost estimate based on the best information available from cost estimating guides, manufacturers and suppliers, and the Design Team’s professional experience. The cost estimate will be compared to the Contractor’s proposal to determine if the proposal is reasonable and equitable. 6.3 Work Change Directive and Force Account If a change order cannot be negotiated or if there is insufficient time to follow the normal procedures, the County may issue a Work Change Directive. The Contractor shall proceed promptly with the changed work directed by the Work Change Directive and shall maintain records as needed to track the work. If the Contract calls for work or materials to be paid for by force account, payment amounts will be determined as provided in paragraph 1-09.6 of the Standard Specifications (WSDOT 2012). 6.4 Washington State Department of Ecology Requirements Change orders that deviate significantly from the approved Plans/Specifications must be submitted for Ecology review and approval, prior to execution. These types of change orders include: • Changes that alter the project performance • Changes that substantially vary from the approved Facility plan or design drawings and specifications, or that change the location, size, or capacity of any major component All change orders submitted to Ecology for review must include the following items:

6-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 6

• Project name and address • Names and telephone numbers of the County Project Managers, Contractor, and Project Representative(s) • Contract change order number • Description or information identifying the change and its location on the drawing • Appropriate drawings, sketches, and specifications • Calculations of altered sizes where appropriate • Justification explaining why this change is necessary for completion of the work originally contemplated by the Contract • Name and title of originator of change order request • Copy of the proposed change order document with approval signatures of the Project Representative • Time extension required for the change order work

6-2

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 7

Section 7 Technical Records Handling

This section sets forth technical records handling protocols for the Street Waste Facility project, including file location, correspondence, outgoing submittal requirements, and as-built documentation maintenance. 7.1 Location of Files The Contractor and other correspondents shall transmit all correspondence to the County Project Managers at 1800 Continental Place; Mount Vernon, WA 98273. This is the official project file copy. 7.2 Correspondence Correspondence includes both letters and memoranda to and from all parties associated with the project. Correspondence will receive a project file number and Contract identification number. The date received (incoming) or date written (outgoing) will serve as a chronological file reference. 7.3 Outgoing Submittals Outgoing submittals will be processed according to the following steps: 1. When comments are received from the submittal reviewer(s), the County Project Managers will review and consolidate all comments. 2. The County Project Managers will use a transmittal form to forward copies of the submittal, with consolidated comments, to the Contractor. Copies of the submittals will be kept at the County office. 3. The County Project Managers will monitor to ensure that the Contractor resubmits any submittal, or part of a submittal, as required by comments to the original submittal. Steps 1 and 2 above will be followed for any resubmittals. 7.4 As-Built Documentation As-built drawings, or record drawings, are those documents maintained and annotated in red ink by the Contractor during construction and are defined as follows: • A neatly and legibly marked set of Contract Drawings showing the final as-built location and size of structures, footings, piping, equipment, electrical conduits, and any other major elements of the work • Additional as-built documentation, such as schedules, lists, drawings, standard details, and electrical diagrams included in the Contract Documents or Shop Drawings • Contractor as-built layout and installation drawings Unless otherwise specified, record drawings shall be full-size and maintained in a clean, dry, and legible condition. Record documents shall not be used for construction purposes and shall be available for review by the Operations Manager or Project Representative(s) during normal working hours at the Contractor’s field office. At the completion of the work, prior to final payment, completed record drawings shall be submitted to the Operations Manager. The Contractor is responsible for submission of the completed record drawing set for all portions of the work including those portions performed by subcontractors. The record drawings submitted will be rejected unless all Contract drawings and all disciplines are included.

7-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility Section 8

Section 8 Construction Safety and Health

The Contractor shall require its personnel to observe proper safety and hygienic precautions when at the work site. The Contractor shall comply with the following health and safety standards: • The Federal Occupational Safety and Health Act (OSHA), as amended. • Safety and Health Standards for Construction as promulgated by the Director of the Department of Labor and Industries under Section 49.17.050 of the Washington Industrial Safety and Health Act of 1973, as set forth in Chapter 49.17, Revised Code of Washington (RCW). • Safety and Health Regulations for Construction as promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act, as set forth in Title 29, Code of Federal Regulations (CFR). Copies of these regulations may be obtained from Labor Building, 14th and Constitution Avenue NW, Washington, D.C. 20013. The phone numbers of emergency contacts for reference in case of an emergency are provided below. Fire, Medical, or Other Emergency 911 National Response Center 800.424.8802 Reporting Hazardous Material/Sewage Spills: Department of Ecology Southwest Region 360.407.6300 Poison Information Center 800.424.9300 Hazardous material identification 800.631.1884 Environmental Information Center 206.670.1638 Skagit County Emergency Management 360.428.3250 (open 7:30 a.m. through 4:30 p.m.; use 911 during non-business hours) Skagit County Sheriff 360.336.9450 Skagit County administration offices 360.336.9400 The Contractor shall submit an Emergency Contact List no later than 5 calendar days after the date the Contract is executed. This list shall include, at a minimum, the Prime Contractor’s Project Manager and the Prime Contractor’s Project Superintendent. The list shall identify a representative with delegated authority to act as the emergency contact on behalf of the Prime Contractor and include one or more alternates. The Emergency Contact List shall include 24-hour telephone numbers for all individuals identified as emergency contacts or alternates. 8.1 Spill Prevention, Control, and Countermeasures Plan The Contractor shall prepare and implement a project-specific spill prevention, control, and countermeasures plan (SPCC Plan) for the duration of the project, as described in Section 1-07.15(1) of the Contract Documents.

8-1

Construction Quality Assurance Plan, Skagit County Street Waste Facility

Construction Schedule

1

APPENDIX G Vicinity Map and Plans