Environmental Management Plan

Updated Environmental Management Plan Project Number 45303-001 February 2017

CAM: Rural Energy Project

Prepared by Electricite Du Cambodge (EDC) through the Ministry of Mines and Energy (MME) of the Kingdome of , the Asian Development Bank (ADB) and the Australian Department of Foreign Affairs and Trade (DFAT).

This environmental management plan report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

KINGDOM OF CAMBODIA Nation Religion King

6

ELECTRICITE DU CAMBODGE (EDC)

RURAL ENERGY PROJECT – PROPOSED ADMINISTRATION OF GRANT BY THE GOVERNMENT OF AUSTRALIA

ADB Grant No. 0336-CAM (EF): Rural Energy Project

(Updated) ENVIRONMENTAL MANAGEMENT PLAN

For

Rural Energy Project

February 2017

Content Page

Abbreviations ...... 2

A. Background ...... 3

B. Project Scope ...... 3

B.1 Concrete Poles ...... 4

B.2 Foundation ...... 4

B.3 Overhead Ground Wires ...... 4

B.4 Transformers and Automatic Voltage Regulators ...... 4

C. Environmental ConditionS ...... 8

D. Environmental Impacts and Mitigation Measures ...... 8

D.1 Design Stage ...... 8 D.1.1 Loss of property, trees and agricultural land ...... 8 D.1.2 Damage to existing structures ...... 8 D.1.3 Risk of Land Mines and UXO ...... 9

D.2 Construction Stage ...... 9 D.2.1 Dust Impacts ...... 9 D.2.2 Noise Impacts ...... 9 D.2.3 Generation of wastes ...... 9 D.2.4 Water contamination ...... 10 D.2.5 Soil erosion ...... 10 D.2.6 Loss of trees ...... 10 D.2.7 Loss of property and agricultural land ...... 10 D.2.8 Traffic congestion, Safety and Health ...... 10

E. Appendices ...... 11

Appendix 1: Environmental Management Plan ...... 11

Appendix 2: Environmental Monitoring Plan (EMoP) ...... 18

Appendix 3: General Environmental Monitoring Checklist ...... 24

Appendix 4: Number of affected villages ...... 27

EMP-Rural Energy Project Page 1 ABBREVIATIONS

ADB Asian Development Bank

DFAT Australian Department of Foreign Affairs and Trade

EA Executing Agency

EARF Environmental Assessment and Review Framework

EDC Electricity Du Cambodge

EMP Environnent Management Plan

IA Implementing Agency

IEE Initial Environmental Examination

IEC International Electro Technical Commission

MEF Ministry of Economy and Finance

MME Ministry of Mines and Energy

MOE Ministry of Environment

MOU Memorandum of Understanding

LV Low Voltage

MV Medium Voltage

PIC Project Implementation Consultant

PMO1 EDC’s Project Management Office 1

REE Rural Electricity Enterprises

REP Rural Energy Project

ROW Right of Way

RAP Resettlement Action Plan

SPS ADB’s Safeguard Policy Statement (2009)

SEPRO EDC’s Social, Environmental and Public Relations Office

UXO Unexploded Ordnance

EMP-Rural Energy Project Page 2 ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN

A. BACKGROUND

1. Rural Energy Project (Component 1: Rural Electrification of Svay Rieng Province) (hereinafter referred to as "the project") is an DFAT funded grant and will assist the efforts of Eléctricité du Cambodge (EDC) to electrify approximately 8,000 households by extending 220 km of 22 kV medium-voltage (MV) sub-transmission line and 400 km of low-voltage (LV) distribution network in Svay Rieng Province. The development of an electricity transmission network in rural areas will displace expensive and environmentally unsustainable off-grid diesel generation by rural electricity enterprises (REEs) providing them with more cost- effective electricity supplies. The project is classified as Category B for environment and Category C for indigenous peoples under ADB Safeguard Policy Statement (2009).

2. EDC is the Executing Agency of the project. EDC is a state-owned power utility mandated to implement the Government’s long-term objective of achieving 100% electrification of villages by 2020 and 70% of households by 2030 in cooperation with Rural Electricity Enterprises (REEs). The Ministry of Mines and Energy (MME) is the Implementing Agency (IA) for the component 2 on improved cooking stoves at Kampong Cham Province. The EDC is the IA for the capacity development component.

3. Overall, the proposed project aims to: (i) Increase electrification rate in Svay Rieng province through the extension of 22kV MV sub-transmission and LV distribution lines; (ii) Improve reliability of the electricity grid; and (iii) Reduce dependence on firewood and biomass for fuel in cooking to prevent threats to health due to air pollution.

4. In compliance with the ADB’s Safeguard Policy Statement 2009, this updated Environmental Management Plan (EMP) was prepared for inclusion in the tender documents for Rural Energy Project under Component 1: Rural Electrification of Svay Rieng province. The EDC-SEPRO with the assistance of PIC will perform periodic monitoring to ensure that the mitigation measures provided in the EMP are appropriately implemented.

5. The EMP summarizes the project scope, the environmental conditions, the impacts, the mitigation measures and monitoring plan to be implemented particularly during the construction stage of the project. The national environmental standards related to discharges of wastes, emissions release and disturbances by noise and vibration are also presented in the Appendices as reference.

B. PROJECT SCOPE

6. The project consists of installation of concrete electricity poles along the existing rural roads thereby increasing electrification rate in Svay Rieng Province through the extension of 22kV MV sub-transmission and LV distribution lines covering more than 90 villages, 25 Communes/Sangkat, 6 districts/Krong in Svay Rieng province (Appendix 4).

7. The proposed project will consist of 220 circuit-kilometers (cct-km) of MV lines and 400 cct-km of LV lines. Figure 2 presents the overview of Svay Rieng MV Route Line project of the distribution line. In general, the 22 kV distribution line will pass along existing roads and through flat, rural, and agricultural terrain.

EMP-Rural Energy Project Page 3 B.1 Concrete Poles

8. The distribution poles will consist of round pre-stressed concrete poles. The average distance between poles is 60 – 80 m. The LV poles will be positioned 15 m from the center of existing road while the MV poles will be installed at 25 m from the center of the road. The height of the poles will be 12 – 14 m. As required for safety, a minimum vertical clearance of 2 - 3 m from existing structures and trees will be maintained by EDC. Tall trees within the ROW will be removed as necessary to maintain the minimum conductor clearance. During the final design of the transmission line, it will be sited to avoid houses to the maximum extent possible.

B.2 Foundation

9. The foundations of the poles will be reinforced concrete, cast in-situ. The size of pole foundations is about 1m x 1m while the excavation depth is about 1.2m. All excavated soil will be utilized for backfilling of the pole foundations.

B.3 Overhead Ground Wires

10. The distribution line will use the overhead ground wire for lighting protection, conductors, and insulators for corrosion control. All insulators and fittings to be utilized by the project shall conform to the international standard of the International Electro Technical Commission (IEC). B.4 Transformers and Automatic Voltage Regulators

11. There will be about 77 pole- mounted distribution transformers and AVRs that will be installed for the project. The outdoor transformers include 4-250KVA, 5-160KVA, 29- 100KVA, 21-50KVA, 9-50KVA, and 9-25KVA transformers.

EMP-Rural Energy Project Page 4

Figure 1: Project Location Map

EMP-Rural Energy Project Page 5

Figure 2: Line route of Rural Energy Project

EMP-Rural Energy Project Page 6

Figure 3: Line route of Rural Energy Project

EMP-Rural Energy Project Page 7 C. ENVIRONMENTAL CONDITIONS

12. The proposed project is expected to contribute positively to the economic development of the Svay Rieng province through the improvement of the power distribution grid. The project is also expected to improve reliability and security of power supply that would allow EDC to meet the increased power demand in overall province in the near future.

13. Sensitive areas including cultural heritage sites, protected areas, wetland, mangrove, estuarine and buffer zone of protected area are not adjacent or within the project area. Wildlife of rare and endangered species were also not found at project site.

14. The distribution line will traverse around 25 communes with the 6 districts (including 1 Krong) in Svay Rieng province, therefore houses, schools, health centers, small-scale business shops, rice fields and productive trees were found along the alignments and will be impacted by the proposed project. However, any impacts of the project during the construction phase are temporary and limited to the surrounding area and can be readily mitigated through proper implementation of measures during design and construction.

D. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

D.1 Design Stage

D.1.1 Loss of property, trees and agricultural land

15. Clearing/trimming of trees and vegetation at both sides along the ROW for wiring of conductors and stringing of cable will be required and will cause temporary disturbance. Permanent acquisition of land for the pole foundations will be made within the government- designated right of way where existing residential structures may present. Furthermore, the temporary acquisition of land for storage of poles and cable reels may cause nuisance to access roads. Site inspection found that most of the lands at both sides along the ROW are used for planting rice and other crops by people who live there. Distribution line will only follow the designated ROW for rural roads. Nonetheless, there will be some potential impacts on trees and natural forest depending on the location of electricity poles.

16. During the design stage, engineering design consultant ensures that there is acceptable alternative in each concrete pole location that would have an overall advantage in minimizing environmental impact during and after construction.

D.1.2 Damage to existing structures

17. The concrete poles will be installed along the ROW. Distribution line will not traverse any historically or culturally significant sites. Likewise, the lines will not encroach upon any ecologically significant areas. However, most ROWs are being used as rice field and these agricultural lands are also the main source of income of local people in the area.

18. A number of houses, small-scale business shops and trees are located within the vicinity of the project. To lessen the project impacts, the distribution line was designed in such a way that the need for removal of trees and structures along the alignment is minimized. Resettlement Plan in accordance with ADB’s Safeguard Policy Statement as well as Cambodian laws, policies, and regulations is prepared and will be implemented.

EMP-Rural Energy Project Page 8 D.1.3 Risk of Land Mines and UXO

19. Unexploded ordnances (UXO) contamination occurred in Cambodia following decade of civil war in the country. Highly dangerous and littered UXO is still reportedly present in some areas in the country especially along the Cambodia’s border in Svay Rieng province. However, according to the results of the survey, there are no areas along the ROW with severe UXO contamination. The agricultural lands in the vicinity have been cultivated for a long time and therefore the risk of encountering UXO is considered low. In addition, the excavated areas for each electric pole are small and shallow.

20. Before commencement works period, however; any public consultation meetings with local communities and stakeholders are necessary to identify areas where there are risks of mines or UXO. Suspected areas should be cleared before construction activities to ensure that all suspected areas has already got a certificate or issued official letter by Mine .

D.2 Construction Stage

D.2.1 Dust Impacts

21. Dust generation is expected during earthworks and sports from tran or hauling of construction materials to the site. Dust pollution coulduisance be ato ncommunities adjacent to roads where construction takes place, especially duringseason. dry

22. The Contractor will be required to formulate and implement a dust control program that includes spraying of water on roads and work areas ges within close villa to the road. Vehicles transporting concrete poles and other materials beshould covered with tarpaulin or similar materials.

D.2.2 Noise Impacts

23. Similar to dust, operation of construction equipment and transporting materials will cause temporary noise and vibration. Communities close to work areas will be affected.

24. The Contractor should consider proper scheduling of construction activities particularly in sensitive areas. Acoustic barriers or enclosures for working areas should be provided where required.

D.2.3 Generation of wastes

25. During construction, various wastes will be generated.ntial Potesources are wastes from construction workers, site clearing, and excavation,ntling disma of old structures and from other construction-related activities.

26. Contractor should formulate and implement a Waste Management Plan where required. This should include: (1) application of waste tion segrega (recyclables/biodegradable/residual wastes), (2) designate anppropriate a location as temporary staging area for excavated materials and other, (3) wastes provide sufficient garbage containers at work site, (4) proper disposal ofat wastesa designated area, (5) provide sanitary facilities to workers which should beand cleaned maintained regularly. Upon completion of construction works, storage and work siteshall usedbe restoreds to its original state.

EMP-Rural Energy Project Page 9

D.2.4 Water contamination

27. The potential sources of water contamination would be from leaked fuel or used lubricant. These substances are toxic to living organisms.

28. Contractor shall ensure that: (i) diesel and waste oils are handled and stored properly to prevent leakage or spill, (ii) waste oils are stored in suitable containers and transported away from the sites (iii) the Contractor shall prepare a Spill Management Plan including measures to be taken and equipment to be used to ensure adequate cleanup of any spills.

D.2.5 Soil erosion

29. Soil erosion may occur during site clearing and other earth moving works. When heavy rain comes, sediments are carried into ditches, culverts, nearby water bodies and adjacent lands.

30. The contractor will be required to implement soil erosion control to minimize soil erosion and sedimentation of waterways. The alternative approaches should be: (1) provide adequate cross drainage to avoid over flow or flooding and (2) re-vegetation of erosion-prone areas.

D.2.6 Loss of trees

31. The project will only follow the existing alignment along the rural roads. Impact on trees is insignificant.

32. Clearing/trimming of trees and vegetation should be avoided as much as possible. Removed/trimmed branch of trees will be cleared by the Contractor in order to avoid disturbance to residential area and access roads.

D.2.7 Loss of property and agricultural land

33. Most of the lands at both sides along the ROW of the rural roads are used for planting rice fields and other crops. There will be potential loss of fruit trees and impact on residential structures.

34. The Project alignments will be carefully routed to ensure that the impact is minimized as much as possible especially in areas with high concentration of trees and houses.

35. The Contractor shall prepare a compensation scheme for affected structures, trees, and privately owned land as required in Resettlement Plan. The grievance redress mechanism, monitoring, and institutional arrangements shall also be disclosed to the local people during the public consultation meeting before commencement of construction works.

36. The contractor shall be responsible for mitigating any adverse impacts to the existing environment as results of their construction works, for instance, damage to access roads due to moving construction vehicles

D.2.8 Traffic congestion, Safety and Health

37. Traffic congestion may occur during transportation of concrete poles and other construction materials.

EMP-Rural Energy Project Page 10 38. The contractor shall formulate Traffic Management Plan and Health and Safety Plan. This shall include the followings: (i) Install traffic/warning signs, i.e., ”Slow down - Construction in Progress”, “Safety First” at the construction area including reflective fences or enclosures (ii) direct drivers to drive at low speeds, especially near market, school, hospital in urban areas. (iii) keep the roadway or bypass accessible to commuters to avoid traffic jam (iv) park vehicles at designated area (v) detour road should be provided and accessible to commuters (vi) workers should be provided with Personal Protective Equipment (vii) a trained first aid personnel and health facility should be provided on site (viii) potable water and sanitary facilities should be provided to workers. These plans shall be submitted to EDC and PIC at the early stages of the project.

E. APPENDICES

Appendix 1: Environmental Management Plan The Environmental Management Plan shall form part of the Technical Specifications, and therefore will take precedence in any conflict with General Specifications.

This item will not be measured separately; instead this will be assessed by the PIC environmental specialist whether the Contractor has met all the requirements based on the Specifications.

No separate payment shall be made with respect to the implementation of the Environmental Management Plan. The Contractor should incorporate the cost of mitigation measures or items in the EMP to his Bill of Quantities.

It is the responsibility of the Contractor to comply with the government policy and ADB’s Safeguard Policy, 2009.

The EMP below shall be served as general guide for the contractor to follow. After contract award and mobilization of the contractor, construction EMP (CEMP) should be prepared. This must give specific details of locations of borrow areas; access roads, workers camps and other facilities. This must be submitted to EDC for approval before works commence.

Compliance monitoring reports will be submitted by the contractor to PMO1/SEPRO of EDC and PIC on a monthly basis.

EMP-Rural Energy Project Page 11

Institutional Responsibilities Project Potential Environmental Project Phase Proposed Mitigation Measures Activity Impacts Implement Supervise

1.Pre- Detailed 1) Loss of trees  At design stage, ensure that PIC, PMO1 in PIC Consultant, Construction Engineering there are acceptable alternatives cooperation with EDC-SEPRO Design for alignments/borrow pit areas if EM &C contractor any that would minimize the needs for removal of trees.

2) Damage to existing  The design should avoid PIC, PMO1 in PIC Consultant, structures impacts on existing structures. cooperation with EDC-SEPRO Resettlement Plan for the EM &C contractor Project in compliance with ADB’s Safeguard Policy and Cambodian laws, policies, and regulations shall be followed.

3) Risk of land mines or UXO  Consultative meetings with local PIC, EDC-SEPRO PIC Consultant, communities are necessary to in cooperation with EDC-SEPRO identify areas where there are EM &C contractor risks of mines or UXO. Suspected areas should be cleared before commencement of works.

2. Construction Earthworks, 4). Dust generation  The Contractor will be required EM &C contractor PIC Consultant, site clearing, to formulate and implement a EDC-SEPRO hauling of Dust Abatement Program that construction includes spraying of water on materials, piling roads and work areas within works,

EMP-Rural Energy Project Page 12

Institutional Responsibilities Project Potential Environmental Project Phase Proposed Mitigation Measures Activity Impacts Implement Supervise

Operation of villages close to the road. construction/ workers’  Vehicles transporting materials camps, borrow should be covered with tarpaulin pits, handling of or similar material construction wastes

5). Noise and vibration  The Contractor should consider EM&C Contractor PIC Consultant, proper scheduling of EDC-SEPRO construction activities particularly in sensitive areas, i.e schools, health centers, pagodas.

6). Water contamination  Waste/used oil should be EM&C Contractor PIC Consultant, collected, properly stored and EDC-SEPRO disposed of at an approved site (according to national standard/guideline). Storage should be in drums raised off the ground and properly covered to keep rain water out. Lining or pan should be provided to contain any spills;

 The Contractor shall prepare a Spill Management Plan (including measures to be taken

EMP-Rural Energy Project Page 13

Institutional Responsibilities Project Potential Environmental Project Phase Proposed Mitigation Measures Activity Impacts Implement Supervise

and equipment to be used) to ensure adequate cleanup of any spills.

 Avoid discharging of petrol, or lubricants into stream, reservoir or land.

 Construction shall be carried out during the dry season, if possible

7). Loss of agriculture land  The contractor will seek to EM&C Contractor PIC Consultant, due to concrete poles minimize impacts on agriculture EDC-SEPRO installation along the ROWs of land wherever possible. rural roads

8) Loss of trees  Tree clearing should be avoided EM&C Contractor PIC Consultant, as much as possible; EDC-SEPRO

 The pits/bored holes that are left unused will be backfilled before being handed back to the affected residents.

 Any tree planting to compensate lost trees should be carried out in appropriate locations in coordination with MoE/MAFF-

EMP-Rural Energy Project Page 14

Institutional Responsibilities Project Potential Environmental Project Phase Proposed Mitigation Measures Activity Impacts Implement Supervise

Foresty Administration regarding the species of trees to be re- planted.

9) Soil erosion  The contractor will be required EM&C Contractor PIC Consultant, to implement soil erosion control EDC-SEPRO to minimize erosion and sedimentation of waterways. The alternative approaches should be: (1) provide adequate measures to avoid over flow to the water courses and (2) re- vegetation of erosion-prone areas

10) Generation of wastes Contractor shall formulate and EM&C Contractor PIC Consultant, implement a Waste Management EDC-SEPRO

Plan that will:

 designate an appropriate location as temporary staging area for excavated materials and other wastes

 provide sufficient garbage containers in storage areas and at work sites

 regular disposal of wastes to an

EMP-Rural Energy Project Page 15

Institutional Responsibilities Project Potential Environmental Project Phase Proposed Mitigation Measures Activity Impacts Implement Supervise

approved landfill or site

 provide sanitary facilities for workers; this should be cleaned and maintained regularly

 Upon completion of construction works, storage and work sites used should be restored to its original state/condition.

11) Traffic congestion, Health The contractor shall formulate EM&C Contractor PIC Consultant, and Safety Traffic Management Plan as well as in coordination with EDC-SEPRO Health & Safety Plan. the sub-district officials  Keep the roadway or bypass accessible to commuters to avoid disruption of traffics  Park at designated area  Detour road should be provided and accessible to commuters  Temporary storage of equipment and vehicle parking locations must be established and approved by the sub-district officials  Workers should be provided with Personal Protective Equipment (PPE)  A trained first aid personnel and

EMP-Rural Energy Project Page 16

Institutional Responsibilities Project Potential Environmental Project Phase Proposed Mitigation Measures Activity Impacts Implement Supervise

health facility should be provided on site  Potable water and sanitary facilities should be provided to workers  EM&C Contractor PIC Consultant, 12) Generation of The contractor should comply EDC-SEPRO, employment with the Labor Law and Gender Action Plan; employ local people local authorities from villages including women wherever possible

 3.Operation Management Inform locals in advance through IA/EA (EDC- PIC Consultant, 13) alignment of distribution Phase and Control of the village chiefs on the SEPRO) EDC-SEPRO, line Vegetation at schedule of maintenance and local authorities Distribution line trimming works.  Avoid encroachment into rice or cropland of villagers.  Provide any warning signs on accident-prone points especially near schools, hospitals and market areas.

EMP-Rural Energy Project Page 17

Appendix 2: Environmental Monitoring Plan (EMoP)

Monitoring Start/ Mitigation Measures Schedule / Issue Required/Methods/ Completion Reporting Responsibility (Items to Monitor) Frequency Parameters Date

Pre-Construction Phase

Loss of trees Ensure that there are acceptable Confirmed by EDC- Once during Before start of Note to file PIC Consultant, alternatives of alignment that IA via note to file Contract Construction regarding EDC-SEPRO would minimize the needs for preparation stage / Before action(s) by removal of trees end of design EDC-IA stage

Damage to The design should avoid impacts Confirmed by EDC- Once during Before start of Note to File PSC Consultant, existing on existing structures. IA via note to file Contract Construction regarding EDC-SEPRO structures Resettlement Plan for the Project preparation stage / Before action(s) by in compliance with ADB’s end of design EDC-SEPRO Safeguard Policy and Cambodian stage laws, policies, and regulations shall be followed.

Possible Consultative meetings with local Verify Information Before the Before the Information PIC Consultant, accidents due to communities are necessary to from local mobilization mobilization of from local EDC-SEPRO risk of land mines identify areas where there are communities of contractor communities or UXO risks of mines or UXO. contractor Suspected areas should be cleared before commencement of works.

Construction Phase

Dust generation  .The Contractor will be -Check copy of the Monthly Start of Proof that PIC Consultant, required to formulate and Dust Abatement Construction copies of the EDC-SEPRO

EMP-Rural Energy Project Page 18

Monitoring Start/ Mitigation Measures Schedule / Issue Required/Methods/ Completion Reporting Responsibility (Items to Monitor) Frequency Parameters Date implement a Dust Abatement Plan stage/Constructi IEE/EMP are Contractor’s Program that includes on stage received by the Safeguard -Check level of dust spraying of water on roads contractor; Specialist (self- pollution by: and work areas within villages monitoring) Compliance close to the road. 1) Aesthetics monitoring through visual  reports Vehicles transporting observation materials should be covered with tarpaulin or similar 2) Feedback from material village people

Generation of Contractor should formulate and Check aesthetics Monthly Construction Compliance PIC Consultant, wastes implement a Waste Management through visual stage monitoring EDC-SEPRO Plan: observation reports Contractor’s

Safeguard  designate an appropriate Specialist (self- location as temporary staging monitoring) area for excavated materials

and other wastes

 provide sufficient garbage containers in the storage and at work sites

 regular disposal of wastes to an approved landfill or site

 provide sanitary facilities for workers; this should be cleaned and maintained regularly

EMP-Rural Energy Project Page 19

Monitoring Start/ Mitigation Measures Schedule / Issue Required/Methods/ Completion Reporting Responsibility (Items to Monitor) Frequency Parameters Date  Upon completion of construction works, camps and work sites used should be restored to its original condition.

Water  Waste/used oil should be  Check copy of Monthly Construction Compliance PIC Consultant, contamination collected, properly stored and Spill stage monitoring EDC-SEPRO reports Contractor’s disposed to an approved site Management (according to national Plan; records of Safeguard standard). Storage should be waste/used oil Specialist (self- in drums raised off the ground spillage monitoring) and properly covered to keep  Visual inspection rain water out. Lining or pan of waste/used oil should be provided to contain in the storage any spills area  The Contractor shall prepare a  Check the color Spill Management Plan of surface water (including measures to be at project sites taken and equipment to be through visual used) to ensure adequate inspection cleanup of any spills

Loss of trees  Tree clearing should be Visual observation, Monthly Construction Compliance PIC Consultant, records of trees stage monitoring EDC-SEPRO avoided wherever possible; affected; reports Contractor’s  Tree planting should be Safeguard

carried out in the appropriate Specialist (self- locations of the road in monitoring) coordination with MoE regarding the species of trees

EMP-Rural Energy Project Page 20

Monitoring Start/ Mitigation Measures Schedule / Issue Required/Methods/ Completion Reporting Responsibility (Items to Monitor) Frequency Parameters Date to be used.

Soil erosion  The contractor will be required  Visual Monthly Construction Compliance PIC Consultant, stage monitoring EDC-SEPRO to implement soil erosion observation of control to minimize erosion possible eroded reports Contractor’s and sedimentation of ground. Safeguard waterways. Alternative Specialist (self-

approaches should be: (1) monitoring)  provide adequate cross Visual drainage to avoid over flow or observation for flooding and (2) re-vegetation the possible of erosion-prone areas change of color of surface water at project sites.

Safety and  The Contractor should Check copy of Monthly Construction Compliance PIC Consultant, Health formulate and implement a Health and Safety stage monitoring EDC-SEPRO Plan; health/accident reports Contractor’s Health and Safety Plan to prevent accident to workers records Safeguard Specialist (self- and villagers. A trained first aid personnel and health monitoring) Visual observation – facility should be provided on site. The Contractor should Safety signs incorporate in the Health and installed, spot Safety Plan in their activities. checks  Provide potable water and sanitary facilities to workers  Install warning signs like “safety first” at the construction area including

EMP-Rural Energy Project Page 21

Monitoring Start/ Mitigation Measures Schedule / Issue Required/Methods/ Completion Reporting Responsibility (Items to Monitor) Frequency Parameters Date fences or enclosures  Provide Protective Personal Equipment (PPE) to workers e.g. safety shoes, hardhats, earplugs, etc.

Traffic  Contractor should perform the  Feedback from Monthly Construction Compliance PIC Consultant, congestion following: i) instruct the drivers village people stage monitoring EDC-SEPRO reports Contractor’s or equipment operators to about traffic; comply with the required visual Safeguard speed limit. (ii) drive at low observation Specialist (self- speeds, especially in market, monitoring)  Check copy of school, hospital, urban areas. Traffic (iii) keep the roadway or Management bypass accessible to Plan commuters to avoid traffic jams. (iv) park at designated area.  Prepare and implement a Traffic Management Plan  Provide appropriate storage area for the construction materials.  Detour road should be provided and accessible to commuters  Temporary access of equipment and trucks must be established and approved by

EMP-Rural Energy Project Page 22

Monitoring Start/ Mitigation Measures Schedule / Issue Required/Methods/ Completion Reporting Responsibility (Items to Monitor) Frequency Parameters Date the sub-district officials

Generation of  The contractor should comply Check Monthly Construction Compliance PIC Consultant, employment with the Labor and Gender reports/records on stage monitoring EDC-SEPRO particularly Action Plan ; employ people women/list of reports Contractor’s among women from villages including women workers employed Safeguard and local people wherever possible Specialist (self- monitoring)

Operation Phase

Health and  Provide warning signs at  Inspect integrity Monthly Operation stage Compliance EDC-SEPRO safety; injury to accident-prone areas, of the poles and monitoring workers and especially near schools, distribution line reports villagers hospitals and market. in order to maintain and  Regular maintenance of ensure good concrete poles condition  Inspect warning signs/boards if placed well on poles, and note accident record

EMP-Rural Energy Project Page 23

Appendix 3: General Environmental Monitoring Checklist

EMP-Rural Energy Project Page 24

EMP-Rural Energy Project Page 25

EMP-Rural Energy Project Page 26

Appendix 4: Number of affected villages Province District/Krong Commune/Sangkat # of Village Svay Rieng Kampong Rou Sam Yaong 1. Ruessei Lieb Svay Rieng Kampong Rou Sam Yaong 2. Svay Kantrae Svay Rieng Kampong Rou Sam Yaong 3. Sam Yaong Svay Rieng Svay Chrum Angk Ta Sou 1. Chaeng Maeng Svay Rieng Svay Chrum Angk Ta Sou 2. Trapeang Chhuk Svay Rieng Svay Chrum Angk Ta Sou 3. Boeng Svay Rieng Svay Chrum Angk Ta Sou 4. M'am Svay Rieng Svay Chrum Angk Ta Sou 5. Trapeang Thmai Svay Rieng Svay Chrum Angk Ta Sou 6. Svay Ming Svay Rieng Svay Chrum Angk Ta Sou 7. Sanlaot Svay Rieng Svay Chrum Angk Ta Sou 8. Thma Pean Svay Rieng Svay Chrum Angk Ta Sou 9. Prey Chheuteal Svay Rieng Svay Chrum Angk Ta Sou 10. Roka Svay Rieng Svay Chrum Angk Ta Sou 11. Boeng Kriel Svay Rieng Svay Chrum Angk Ta Sou 12. Meun Svay Svay Rieng Svay Chrum Basak 1. Sala Rien Svay Rieng Svay Chrum Basak 2. Svay Ta Phlo Svay Rieng Svay Chrum Basak 3. Bayab Svay Rieng Svay Chrum Basak 4. Pou Ta Ros Svay Rieng Svay Chrum Basak 5. Basac Svay Rieng Svay Chrum Thlok 1. Doun Tong Svay Rieng Svay Chrum Thlok 2. Snay Kreang Svay Rieng Svay Chrum Thlok 3. Ampov Rieng Svay Chrum Thlok 4. Thlok Svay Rieng Svay Chrum Thlok 5. Kadal Svay Rieng Svay Chrum Thlok 6. Thum Svay Rieng Svay Chrum Thlok 7. Tey Yea Svay Rieng Svay Chrum Thlok 8. Samdei Svay Rieng Svay Chrum 1. Rum Denh Svay Rieng Svay Chrum Chheu Teal 2. Traok Svay Rieng Svay Chrum Chheu Teal 3. Samraong Svay Rieng Svay Chrum Chheu Teal 4. Poun Kaki Svay Rieng Svay Chrum Chheu Teal 5. Chek Svay Rieng Svay Chrum Chheu Teal 6. Sang Kae Svay Rieng Svay Chrum Chheu Teal 7. Ta Reak Svay Rieng Svay Chrum Chheu Teal 8. Prey Roka Svay Rieng Svay Chrum Chheu Teal 9. Chhuk Sa Svay Rieng Svay Chrum Chheu Teal 10. Chheu Teal Svay Rieng Svay Chrum Chheu Teal 11. Prey Chambak Svay Rieng Svay Chrum Chheu Teal 12. Nearea Ten Svay Rieng Svay Chrum Doun Sa 1. Boeng Kaek Svay Rieng Svay Chrum Doun Sa 2. Prey Roka

EMP-Rural Energy Project Page 27

Svay Rieng Svay Chrum Doun Sa 3. Rumpoat Chruk Svay Rieng Svay Chrum Doun Sa 4. Prey Pou Svay Rieng Svay Chrum Doun Sa 5. Ou Srangam Svay Rieng Svay Chrum Doun Sa 6. Chensa Svay Rieng Svay Chrum Doun Sa 7. Doun Sar Svay Rieng Svay Chrum Doun Sa 8. Trach Svay Rieng Svay Chrum Doun Sa 9. Doung Preah Svay Rieng Svay Chrum Doun Sa 10. Sour Svay Rieng Svay Chrum Doun Sa 11. Kuoy Svay Rieng Svay Chrum Kouk Pring 1. Kdom Pi Svay Rieng Svay Chrum Kouk Pring 2. Kantuot Praong Svay Rieng Svay Chrum Kouk Pring 3. Thna Svay Rieng Svay Chrum Kouk Pring 4. Kandal Svay Rieng Svay Chrum Kouk Pring 5. Angk Kabbas Svay Rieng Svay Chrum Kouk Pring 6. Svat Prahut Svay Rieng Svay Chrum Kouk Pring 7. Leach Chhuk Svay Rieng Svay Chrum Kouk Pring 8. Chambak Thloeng Svay Rieng Svay Chrum Kouk Pring 9. Tbaeng Svay Rieng Svay Chrum Kouk Pring 10. Doun Leaeb Svay Rieng Svay Chrum Kruos 1. Chambak Svay Rieng Svay Chrum Kruos 2. Thna Svay Rieng Svay Chrum Kruos 3. Kruos Svay Rieng Svay Chrum Kruos 4. Krau Svay Rieng Svay Chrum Kruos 5. Rovieng Svay Rieng Svay Chrum Kruos 6. Samraong Svay Rieng Svay Chrum Kruos 7. Krasang Chrum Svay Rieng Svay Chrum Kruos 8. Phluoh Svay Rieng Svay Chrum Kruos 9. Kandal Svay Rieng Svay Chrum Kruos 10. Svay Rieng Svay Chrum Kruos 11. Traok Svay Rieng Svay Chrum Pouthi Reach 1. hen Sa Svay Rieng Svay Chrum Pouthi Reach 2. aeng Svay Rieng Svay Chrum Pouthi Reach 3. Anh Chanh Svay Rieng Svay Chrum Pouthi Reach 4. Khleang Svay Rieng Svay Chrum Pouthi Reach 5. Ta Mom Svay Rieng Svay Chrum Pouthi Reach 6. Prey Khla Svay Rieng Svay Chrum Pouthi Reach 7. Pouthi Reach Svay Rieng Svay Chrum Pouthi Reach 8. Prey Damloung Svay Rieng Svay Chrum Pouthi Reach 9. Prasat Svay Rieng Svay Chrum Pouthi Reach 10. Ou Samdei Svay Rieng Svay Chrum Pouthi Reach 11. Trapeang Thok Svay Rieng Svay Chrum Svay Angk 1. Andoung Svay Rieng Svay Chrum Svay Angk 2. Kandal Svay Rieng Svay Chrum Svay Angk 3. Sampoar Svay Rieng Svay Chrum Svay Angk 4. Svay Angk

EMP-Rural Energy Project Page 28

Svay Rieng Svay Chrum Svay Angk 5. Koul Svay Rieng Svay Chrum Svay Angk 6. Thnong Svay Rieng Svay Chrum Svay Angk 7. Khnor Khang Cheung Svay Rieng Svay Chrum Svay Angk 8. Khnor Khang Tboung Svay Rieng Svay Chrum Svay Angk 9. Svay Ph'aem Svay Rieng Svay Chrum Svay Yea 1. Moha Suon Svay Rieng Svay Chrum Svay Yea 2. Svay Chum Rov Svay Rieng Svay Chrum Svay Yea 3. Prey Banteay Svay Rieng Svay Chrum Svay Yea 4. Robaoh Pring Svay Rieng Svay Chrum Svay Yea 5. Damnak Kantuot Svay Rieng Svay Chrum Svay Yea 6. Kbal Dam Rei Svay Rieng Svay Chrum Svay Yea 7. Tuol Vihear Svay Rieng Svay Chrum Svay Yea 8. Kdei Sla Svay Rieng Svay Chrum Svay Yea 9. Prama Svay Rieng Svay Chrum Svay Yea 10. Sikar Svay Rieng Svay Chrum Svay Yea 11. Kien Ta Siv Svay Rieng Svay Chrum Svay Yea 12. Chamkar Chek Svay Rieng Svay Chrum Svay Yea 13. Svay Yea Svay Rieng Svay Chrum Svay Yea 14. Prey Ph'ong Svay Rieng Svay Chrum Svay Yea 15. Ta Kaor Svay Rieng Svay Teab Sambour 1. Tuol Angkob Svay Rieng Svay Teab Sambour 2. Thmei Svay Rieng Svay Teab Sambour 3. Trapeang Ampil Svay Rieng Svay Teab Sambour 4. Prey Totueng Svay Rieng Svay Teab Sambour 5. Ou K'am Svay Rieng Svay Teab Sambour 6. Svay Kruoh Svay Rieng Svay Teab Sambour 7. Sambuor Svay Rieng Svay Teab Sambour 8. Prey Samphor Svay Rieng Krong Svay Rieng Sangkat Chek 1. Svay Svay Rieng Krong Svay Rieng Sangkat Chek 2. Thmol Svay Rieng Krong Svay Rieng Sangkat Chek 3. Svat Svay Rieng Krong Svay Rieng Sangkat Chek 4. Totea Svay Rieng Krong Svay Rieng Sangkat Chek 5. Chek Svay Rieng Krong Svay Rieng Sangkat Chek 6. Chambak Svay Rieng Krong Svay Rieng Sangkat Chek 7. Kandal Svay Rieng Krong Svay Rieng Sangkat Chek 8. Meloung Svay Rieng Krong Svay Rieng Sangkat Chek 9. Khleang Svay Rieng Krong Svay Rieng Sangkat Chek 10. Kok Pae Svay Rieng Rum Duol Svay Chek 1. Anlong Spean Svay Rieng Rum Duol Svay Chek 2. Ba Krong Svay Rieng Rum Duol Svay Chek 3. Chrak Skor Svay Rieng Rum Duol Svay Chek 4. Kandal Svay Rieng Rum Duol Svay Chek 5. Popul Svay Rieng Rum Duol Svay Chek 6. Roung Damrei Svay Rieng Rum Duol Svay Chek 7. Svay Check

EMP-Rural Energy Project Page 29

Svay Rieng Rum Duol Svay Chek 8. Trapeang Svay Rieng Rum Duol Svay Chek 9. Chambak Svay Rieng Rum Duol Svay Chek 10. Thmei Svay Rieng Rum Duol Meun Chey 1. Ampil Svay Rieng Rum Duol Meun Chey 2. Angk Pok Svay Rieng Rum Duol Meun Chey 3. Chong Preaek Svay Rieng Rum Duol Meun Chey 4. Haek Samnanh Svay Rieng Rum Duol Meun Chey 5. Meun Chey Svay Rieng Rum Duol Meun Chey 6. Prey Boeng Svay Rieng Rum Duol Meun Chey 7. Ta Kheng Svay Rieng Rum Duol Meun Chey 8. Trach Totueng Svay Rieng Rum Duol Meun Chey 9. Trapeang Kandal Svay Rieng Rum Duol Meun Chey 10. Veal Svay Rieng Rum Duol Thmea 1. Thmea Svay Rieng Rum Duol Thmea 2. Krasang Svay Rieng Rum Duol Thmea 3. Preaek Tnaol Svay Rieng Rum Duol Thmea 4. Boeng Kaek Svay Rieng Rum Duol Thmea 5. Trapeang Poun Svay Rieng Rum Duol Thmea 6. Prey Pou Svay Rieng Rum Duol Thmea 7. Pongro Svay Rieng Rum Duol Thmea 8. Prey Chamkar Svay Rieng Rum Duol Chrung Popel 1. Tuol Sala Svay Rieng Rum Duol Chrung Popel 2. Tuol Trea Svay Rieng Rum Duol Chrung Popel 3. Neang Chan Svay Rieng Rum Duol Chrung Popel 4. Krouch Svay Rieng Rum Duol Chrung Popel 5. Preah Angk Kaev Svay Rieng Rum Duol Chrung Popel 6. Trapeang Kruos Svay Rieng Rum Duol Chrung Popel 7. Trapeang Kraet Svay Rieng Rum Duol Kampong Ampil 1. Trapeang Damrei Svay Rieng Rum Duol Kampong Ampil 2. Tasak Svay Rieng Rum Duol Kampong Ampil 3. Kampong Ampil Svay Rieng Rum Duol Kampong Ampil 4. Boeng Svay Rieng Rum Duol Kampong Ampil 5. Tuol Chres Svay Rieng Rum Duol Kampong Ampil 6. Svay Rolum Svay Rieng Rum Duol Kampong Ampil 7. Ta Tae Svay Rieng Romeas Haek Angk Prasrae 1. Trapeang Reang Svay Rieng Romeas Haek Angk Prasrae 2. Kbal Krapeu Svay Rieng Romeas Haek Angk Prasrae 3. Trapeang Rumdenh Svay Rieng Romeas Haek Angk Prasrae 4. Samraong Svay Rieng Romeas Haek Ahgk Prasrae 5, Trapeang Pring Svay Rieng Romeas Haek Angk Prasrae 6. K'am Svay Rieng Romeas Haek Angk Prasrae 7. Angk Prasrae Svay Rieng Romeas Haek Angk Prasrae 8. Angk Knong Svay Rieng Romeas Haek Angk Prasrae 9. Chrak Mreak Svay Rieng Romeas Haek Angk Prasrae 10. Baek Chan

EMP-Rural Energy Project Page 30

Svay Rieng Romeas Haek Angk Prasrae 11. Thnal Peam Svay Rieng Romeas Haek Angk Prasrae 12. Trapeang Thum Svay Rieng Romeas Haek Trapeang 1. Tuol Choar Svay Rieng Romeas Haek Trapeang Sdau 2. Voat Chas Svay Rieng Romeas Haek Trapeang Sdau 3. Trapeang Skon Thmei Svay Rieng Romeas Haek Trapeang Sdau 4. Svay Rieng Romeas Haek Trapeang Sdau 5. Ta Kot Svay Rieng Romeas Haek Trapeang Sdau 6. Svay Tontuem Svay Rieng Romeas Haek Trapeang Sdau 7. Krouch Svay Rieng Romeas Haek Trapeang Sdau 8. Mreah Prov Svay Rieng Romeas Haek Trapeang Sdau 9. Thmei Svay Rieng Romeas Haek Trapeang Sdau 10. Trapeang Skon Chas Svay Rieng Romeas Haek Trapeang Sdau 11. Trapeang Sdau Svay Rieng Romeas Haek Trapeang Sdau 12. Banla S'et Svay Rieng Romeas Haek Trapeang Sdau 13. Khnang Chruk Khang Kaeut Svay Rieng Romeas Haek Trapeang Sdau 14. Tuol Sokram Svay Rieng Romeas Haek Trapeang Sdau 15. Khnang Chruk Khang Lech Svay Rieng Romeas Haek Trapeang Sdau 16. Trapeang Chhneang Svay Rieng Romeas Haek Trapeang Sdau 17. Trapeang Rumdenh Svay Rieng Romeas Haek Trapeang Sdau 18. Trakeab Kdam Svay Rieng Romeas Haek Trapeang Sdau 19. Angk Svay Rieng Romeas Haek Trapeang Sdau 20. Tuol Romiet Svay Rieng Romeas Haek Chantrei 1. Balangk Chea Svay Rieng Romeas Haek Chantrei 2. Samla Chhau Svay Rieng Romeas Haek Chantrei 3. Trapeang Thlok Khang Cheung Svay Rieng Romeas Haek Chantrei 4. Trapeang Thlok Khang Tboung Svay Rieng Romeas Haek Chantrei 5. Prey Kabbas Svay Rieng Romeas Haek Chantrei 6. Trapeang Poun Svay Rieng Romeas Haek Chantrei 7. Ta Phor Svay Rieng Romeas Haek Chantrei 8. Chantrei Svay Rieng Romeas Haek Chantrei 9. Ta Khen Svay Rieng Romeas Haek Chantrei 10. Kraham Ka Svay Rieng Romeas Haek Chantrei 11. Trapeang Tom Svay Rieng Romeas Haek Chantrei 12. Prey Toteung Svay Rieng Romeas Haek Chantrei 13. Trapeang Run Ti Muoy Svay Rieng Romeas Haek Chantrei 14. Trapeang Run Ti Pir Svay Rieng Romeas Haek Chantrei 15. Trapeang Run Ti Bei Svay Rieng Romeas Haek Chantrei 16. Chong Preaek Svay Rieng Romeas Haek Chantrei 17. Prey Roluos Svay Rieng Romeas Haek Chantrei 18. Kor Svay Rieng Romeas Haek Mream 1. Ak Muol Svay Rieng Romeas Haek Mream 2. Boeng Phe Svay Rieng Romeas Haek Mream 3. Mream Khang Tboung Svay Rieng Romeas Haek Mream 4. Boeng Mung Svay Rieng Romeas Haek Mream 5. Tuol Srangam

EMP-Rural Energy Project Page 31

Svay Rieng Romeas Haek Mream 6. Veal Svay Rieng Romeas Haek Mream 7. Ampil Svay Rieng Romeas Haek Mream 8. Prey Preaek Svay Rieng Romeas Haek Mream 9. Prey Choar Svay Rieng Romeas Haek Mream 10. Thmea Svay Rieng Romeas Haek Mream 11. Tra Lach Svay Rieng Romeas Haek Mream 12. Tbaeng Svay Rieng Romeas Haek Mream 13. Trapeang Trasak Svay Rieng Romeas Haek Mream 14. Po Peay Svay Rieng Romeas Haek Mream 15. Chrung Popel Svay Rieng Romeas Haek Mream 16. Trapeang Choar Svay Rieng Romeas Haek Mream 17. Mream Kheng Cheung Svay Rieng Romeas Haek Mream 18. Ta Tru Svay Rieng Romeas Haek Mream 19. Lbaeuk Svay Rieng Romeas Haek Mream 20. Ta Pang Svay Rieng Romeas Haek Mukh Da 1. Mukh Da Svay Rieng Romeas Haek Mukh Da 2. Samraong Svay Rieng Romeas Haek Mukh Da 3. Kranhung Svay Rieng Romeas Haek Mukh Da 4. Prey Phdau Ti Muoy Svay Rieng Romeas Haek Mukh Da 5. Prey Phdau Ti Pir Svay Rieng Romeas Haek Mukh Da 6. Trapeang Tbal Svay Rieng Romeas Haek Mukh Da 7. Romiet Svay Rieng Romeas Haek Mukh Da 8. Thnal Totueng Svay Rieng Romeas Haek Mukh Da 9. Thnal Kruos Svay Rieng Romeas Haek Mukh Da 10. Bos Kabbas Svay Rieng Romeas Haek Kampong Trach 1. Khla Lout Svay Rieng Romeas Haek Kampong Trach 2. Prey Khcheay Svay Rieng Romeas Haek Kampong Trach 3. Kampong Trach Svay Rieng Romeas Haek Kampong Trach 4. Chong Ou Svay Rieng Romeas Haek Kampong Trach 5. Chheu Phleung Svay Rieng Romeas Haek Kampong Trach 6. Ta Hang Svay Rieng Romeas Haek Kampong Trach 7. Pramat Pram Svay Rieng Romeas Haek Kampong Trach 8. Prey Kralanh Svay Rieng Romeas Haek Kampong Trach 9. Ta Trav Svay Rieng Romeas Haek Kampong Trach 10. Ta Khob Svay Rieng Romeas Haek Doung 1. Ta Suos Svay Rieng Romeas Haek Doung 2. Poun Svay Rieng Romeas Haek Doung 3. Trapeang Sla Svay Rieng Romeas Haek Doung 4. Bos Sangkhor Svay Rieng Romeas Haek Doung 5. Kampong Thna Svay Rieng Romeas Haek Doung 6. Prich Svay Rieng Romeas Haek Doung 7. Trapeang Thlok Svay Rieng Romeas Haek Doung 8. Chheu Teal Svay Rieng Romeas Haek Doung 9. Trapeang Thum Svay Rieng Romeas Haek Doung 10. Prey Tuol

EMP-Rural Energy Project Page 32

Svay Rieng Romeas Haek Doung 11. Thmei Svay Rieng Romeas Haek Doung 12. Trapeang Svay Svay Rieng Romeas Haek Doung 13. Trapeang Kralanh Svay Rieng Romeas Haek Doung 14. Prey Angkunh Svay Rieng Romeas Haek Doung 15. Kor Svay Rieng Romeas Haek Doung 16. Doung Svay Rieng Romeas Haek Doung 17. Trapeang Phlong Svay Rieng Romeas Haek Doung 18. Kranhung Svay Rieng Romeas Haek Doung 19. Chea Theach Svay Rieng Romeas Haek Doung 20. Trapeang Rumpeak Svay Rieng Romeas Haek Doung 21. Svay Pok Svay Rieng Romeas Haek Doung 22. Thlok Pring 1 Province 6 Districts 25 Communes 279 Villages # of Affected villages 99 villages

Note: The yellow highlight is affected villages

EMP-Rural Energy Project Page 33