<<

Procurement Plan (updated as of November 29, 2016) : Lifeline Roads Network Improvement Project Review By BDs/ITQ Bid- Contract Procurement No. of Procurement Invitation Contract Contractual completion Actual Contract Actual Contract price in Contract price as of Changed contract Planned/Actual Description/ Location Length (km) Bank Submission to No objection Opening Evaluation No objection Award Start Completion date* Contractor/Supplier Physical Progress % Payment Progress % Contract ID Amendment Amendment sign date ref.# Packages Method Date signing date* price in USD the contract currency contract signing date amount /in AMD/ (PRIOR / Post) the Bank Date Date

A B C D F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC 1. WORKS

Planned LRNIP Y1-Y2 program.M10-Nerkin 12/28/2012 1/16/2013 1/22/2013 3/7/2013 4/2/2013 5/13/2013 5/14/2013 6/11/2013 6/3/2013 10/30/2015 1 Getashen-VerinGetashen-Madina km 0+000 - 10.7 “Kapavor” Ltd $2,577,604 AMD 1,084,481,024 100% 100% Actual km10+100 12/25/2012 1/16/2013 1/19/2013 3/7/2013 4/2/2013 5/13/2013 5/14/2013 5/29/2013 6/3/2013 11/15/2015 Planned 2 ICB Prior Joint Venture 4/30/2013 12/28/2012 1/16/2013 1/22/2013 3/7/2013 4/2/2013 5/2/2013 5/17/2013 6/3/2013 12/26/2014 “Zangezurtransbuld” 2 LRNIP Y1-Y2 program. M12-Kornidzor 5.3 $1,699,252 AMD 691,674,275 100% 100% OJSC and Actual 12/25/2012 1/16/2013 1/19/2013 3/7/2013 4/2/2013 4/30/2013 5/2/2013 5/17/2013 6/3/2013 12/26/2014 “Kamurjshin” CJSC Planned LRNIP Y1-Y2 program.Mayakovski-Nor 1/9/2013 1/20/2013 2/4/2013 3/19/2013 4/6/2013 4/29/2013 4/30/2013 5/28/2013 6/3/2013 12/26/2014 3 Actual Gyugh---Zovashen km 0+000 - 17.4 1 ICB Prior “Khachhar” LLC $4,053,026 AMD 1,644,136,756 100% 100% km4+500 and km 7+000 - km 19+800 1/9/2013 1/31/2013 2/4/2013 3/19/2013 4/6/2013 4/29/2013 4/30/2013 5/22/2013 6/3/2013 12/26/2014

Planned 4/29/2013 LRNIP Y1-Y2 program.M1-Agarak-Byurakan- 12/28/2012 1/16/2013 1/22/2013 3/6/2013 3/29/2013 4/30/2013 5/28/2013 6/3/2013 12/26/2014 “Ararat-Chanshin” 4 Actual 8.7 $2,613,750 AMD 1,063,443,013 100% 100% Antarut km 0+000 – km8+650 12/25/2012 1/16/2013 1/19/2013 3/6/2013 3/29/2013 4/29/2013 4/30/2013 5/17/2013 6/3/2013 12/26/2014 LLC

Planned 12/28/2012 1/16/2013 1/22/2013 3/6/2013 3/29/2013 4/29/2013 4/30/2013 5/28/2013 6/3/2013 6/20/2015 LRNIP Y1-Y2 program.M5-- 5 Actual 5.3 3 ICB Prior “Sisiani FPAT” LLC $1,543,140 AMD 627,792,289 100% 100% Shenavan-Getashen km1+900-km6+700 12/25/2012 1/16/2013 1/19/2013 3/6/2013 3/29/2013 4/29/2013 4/30/2013 5/20/2013 6/3/2013 6/20/2015

Planned 12/28/2012 1/16/2013 1/22/2013 3/6/2013 3/29/2013 4/29/2013 4/30/2013 5/28/2013 6/3/2013 12/4/2014 6 Actual LRNIP Y1-Y2 program.M7-Arevashogh 2.5 “Arghishti-1” LLC $907,986 AMD 368,924,535 100% 100% 12/25/2012 1/16/2013 1/19/2013 3/6/2013 3/29/2013 4/29/2013 4/30/2013 5/20/2013 6/3/2013 12/4/2014

Planned Public Disclosure Authorized 2/20/2013 3/15/2013 3/26/2013 5/8/2013 6/7/2013 7/3/2013 7/3/2013 8/1/2013 7/22/2013 12/30/2016 Variation Order 1 10/25/2013 -12,888,843

Actual Variation Order 2 10/30/2013 5,983,359

LRNIP Y1-Y2 program. Joint venture of Variation Order 3 6/11/2014 5,121,606 Rehabilitation&Мaintenance of M9-Arteni- “KHACHHAR” Contract CW-ICB-LRNIP - 7 23.4 1 ICB Prior 1/31/2016 $5,595,681 AMD 2,288,257,723 100% 99% AMD 2,295,071,870 Aragats-Getap km 25+940 - km 49+250 road LLC and “Kapavor” 2013/4 6/7/2013 7/3/2013 Variation Order 4 12.08.2014 -1,649,864 (R&M Pilot project) 2/26/2013 3/21/2013 3/26/2013 5/8/2013 7/3/2013 7/18/2013 7/22/2013 Ltd Variation Order 5 10/17/2014 -7,547,369

Variation Order 6 12/20/2014 1,880,820

Variation Order 7 12/22/2015 2,286,144 Planned LRNIP Y3-Y4 program.Road Safety and 3/13/2015 4/14/2015 4/20/2015 4/27/2015 5/1/2015 5/10/2015 12/30/2016 Contract CW-NCB-LRNIP- Varation Order 1 7/10/2015 -107,660 8 Black Spot improvement (CW-NCB-LRNIP- 1 NCB Post N/A N/A N/A Khachhar LTD 1/1/2016 $216,517 AMD 103,425,450 100% 100% AMD 107,901,184 Actual 2015/12-RS 2015/12-RS) - 4/9/2015 5/5/2015 5/25/2015 5/25/2015 6/1/2015 6/8/2015 12/17/2015 Varation Order 2 12/9/2015 -4,368,074 Planned 2/17/2015 3/10/2015 3/12/2015 4/13/2015 4/22/2015 4/28/2015 4/28/2015 5/1/2015 5/10/2015 12/30/2017 Varation Order 1 9/14/2015 7,259,932

Actual LRNIP Y3-Y4 program.Agarak- Yahdan- Koghes-Mghart-Arevatsag-KarmirAgheg-Tsater- Varation Order 2 10/9/2015 -8,176,980 Aygehat-Ardvi- Odzun-M6, km0+000- Contract CW-NCB-LRNIP- 9 15.7 1 NCB Prior Khachhar LTD 11/1/2016 $3,005,286 AMD 1,414,360,538 100% 98% AMD 1,421,000,000 km15+706 (CW-NCB-LRNIP -2015/3) 2015/3 Variation Order 3 5/10/2016 -821,390 2/17/2015 3/11/2015 3/13/2015 4/14/2015 5/8/2015 5/19/2015 5/20/2015 6/1/2015 6/8/2015 8/9/2016 Variation Order 4 7/26/2016 -1,962,474

Variation Order 5 8/12/2016 -2,938,550 Planned 2/17/2015 3/12/2015 3/16/2015 4/16/2015 4/24/2015 4/30/2015 5/1/2015 5/4/2015 5/14/2015 12/30/2017 Variation Order 1 9/24/2015 -21,409,603

Actual Variation Order 2 12/17/2015 3,045,239 LRNIP Y3-Y4 program.Agarak- Yahdan- Contract CW-NCB-LRNIP- Koghes-Mghart-Arevatsag-KarmirAgheg-Tsater- 6.2 Chanaparh LLC 11/4/2016 $905,292 AMD 434,847,209 100% 90% AMD 453,888,971 2015/2. lot1 Varation Order 3 5/13/2016 3,409,248 Aygehat-Ardvi- Odzun-M6, km15+706- 2/17/2015 3/11/2015 3/13/2015 4/14/2015 5/8/2015 5/20/2015 5/20/2015 6/4/2015 6/11/2015 8/8/2016 10 km21+900 (lot1) and 2 NCB Prior Varation Order 4 8/8/2016 -3,650,926 km21+900-km28+240 (lot2) (CW-NCB-LRNIP-2015/2, lot1 and lot2) Varation Order 5 8/11/2016 -435,720

Planned 2/17/2015 3/12/2015 3/16/2015 4/16/2015 4/24/2015 4/30/2015 5/1/2015 5/4/2015 5/14/2015 12/30/2017 Contract CW-NCB-LRNIP- Varation Order 1 9/23/2015 -25,691,028 6.3 Argishti-1 LTD 11/5/2016 $1,747,341 AMD 835,936,865 100% 100% AMD 835,999,999 Actual 2015/2. lot 2 Public Disclosure Authorized 2/17/2015 3/11/2015 3/13/2015 4/14/2015 5/8/2015 5/20/2015 5/21/2015 6/5/2015 12.06..2015 12/2/2015 Varation Order 2 11/10/2015 25,627,894 Planned N/A N/A 3/17/2015 4/17/2015 4/27/2015 N/A 5/2/2015 5/4/2015 5/14/2015 12/30/2017 Variation Order 1 12/17/2015 -14,494,929 LRNIP Y3-Y4 program.Agarak- Yahdan- Actual Koghes-Mghart-Arevatsag-KarmirAgheg-Tsater- Aygehat-Ardvi- Odzun-M6, Access to Ardvi, Contract CW-NCB-LRNIP- 11 3.5 1 NCB Post Chanaparh LLC 11/2/2016 $536,134 AMD 256,194,462 100% 90% AMD 258,950,952 Variation Order 2 5/16/2016 13,870,260 km0+000-km2+571 and Access to Mghart, 2015/6 km0+000-km0+907 N/A N/A 3/13/2015 4/14/2015 5/25/2015 N/A 5/25/2015 6/2/2015 6/9/2015 8/8/2016 (CW-NCB-LRNIP -2015/6) Variation Order 3 8/5/2016 -2,131,821

Planned N/A N/A 3/17/2015 4/17/2015 4/27/2015 N/A 5/2/2015 5/4/2015 5/14/2015 12/30/2017 Variation Order 1 12/17/2015 -24,886,332 LRNIP Y3-Y4 program.Agarak- Yahdan- Actual Koghes-Mghart-Arevatsag-KarmirAgheg-Tsater- Aygehat-Ardvi- Odzun-M6, Access to Contract CW-NCB-LRNIP- 12 Arevatsag-Tsater km0+000-km3+877 and 7.8 1 NCB Post Chanaparh LLC 11/2/2016 $1,114,113 AMD 532,030,232 100% 90% AMD 513,887,775 2015/7 Variation Order 2 12/17/2015 40,613,190 Section Arevatsag-Karmir Aghek km0+000- N/A N/A 3/13/2015 4/14/2015 5/25/2015 N/A 5/25/2015 6/2/2015 6/9/2015 8/8/2016 km3+973 (CW-NCB-LRNIP -2015/7) Variation Order 3 8/5/2016 2,415,599 LRNIP Y3-Y4 program.M2-Shaki-Sisian- Planned Tolors-Bnunis-Torunik-Dastakert, km0+000- N/A N/A 3/19/2015 4/20/2015 4/28/2015 5/4/2015 5/5/2015 5/6/2015 5/14/2015 12/30/2017 km6+000 and access to Shaki km 0+000 - km 6.6 Actual 0+600 (lot1) and km6+000-km9+340 (lot2) N/A N/A 3/18/2015 4/20/2015 5/25/2015 N/A 5/25/2015 5/27/2015 6/3/2015 12/15/2015 Contract CW-NCB-LRNIP- 13 2 NCB Post Sisiani FPAT LLC 10/27/2016 $3,021,938 AMD 1,447,939,105 100% 100% AMD 1,271,011,071 Variation Order 1 11/30/2015 176,928,034 2015/8. lot1 and lot2 Planned (CW-NCB-LRNIP-2015/8, lot1 and lot2) N/A N/A 3/19/2015 4/20/2015 4/28/2015 N/A 5/5/2015 5/6/2015 5/14/2015 12/30/2017 3.4 Actual N/A N/A 3/18/2015 4/20/2015 5/25/2015 N/A 5/25/2015 5/27/2015 6/3/2015 12/15/2015 Planned LRNIP Y3-Y4 program.M2-Shaki-Sisian- N/A N/A 3/20/2015 4/21/2015 4/29/2015 N/A 5/7/2015 5/8/2015 5/14/2015 12/30/2017 Variation Order 1 8/5/2015 -3,146,640 Tolors-Bnunis-Torunik-Dastakert, km9+340- 9.9 Actual km17+500 and access to Bnunis km0+000- N/A N/A 3/18/2015 4/20/2015 5/25/2015 N/A 5/25/2015 6/4/2015 6/11/2015 12/15/2015 J/V Variation Order 2 9/9/2015 -161,027,000 km1+726 (lot1) and km17+500-km26+248 and "Zangezurtransbuld" Contract CW-NCB-LRNIP- 14 Planned 2 NCB Post N/A N/A 3/20/2015 4/21/2015 4/29/2015 N/A 5/7/2015 5/8/2015 5/14/2015 12/30/2017 12/4/2016 $2,685,856 AMD 1,285,026,603 100% 100% AMD 1,208,777,768 access to Torunik km0+000-km0+460 (lot2) OJSC and 2015/9. lot1 and lot2 Variation Order 3 10/9/2015 185,346,356 Actual (CW-NCB-LRNIP-2015/9, lot1 and lot2) 9.2 "Kamurjshin" CJSC Variation Order 4 11/18/2015 64,789,963 N/A N/A 3/18/2015 4/20/2015 5/25/2015 N/A 5/25/2015 6/4/2015 6/11/2015 12/15/2015 Variation Order 5 12/4/2015 -9,713,844 Public Disclosure Authorized Planned N/A N/A 3/23/2015 4/24/2015 4/30/2015 N/A 5/11/2015 5/12/2015 5/14/2015 12/30/2016 Variation Order 1 8/6/2015 -2,445,552 Actual Variation Order 2 9/22/2015 21,601,500 LRNIP Y3-Y4 program.H5-Argel-Karenis- Contract CW-NCB-LRNIP- 15 5.3 1 NCB Post AAB Project LLC 1/2/2016 $1,258,336 AMD 603,495,112 100% 100% AMD 578,280,000 Charentcavan, km0+000-km5+346 N/A N/A 3/20/2015 4/22/2015 5/25/2015 N/A 5/25/2015 6/2/2015 6/8/2015 12/8/2015 2015/1 (CW-NCB-LRNIP -2015/1) Variation Order 3 10/15/2015 9,629,534

Variation Order 4 12/8/2015 -3,570,370 Planned N/A N/A 3/24/2015 4/24/2015 5/1/2015 N/A 5/12/2015 5/13/2015 5/14/2015 12/30/2017 Variation Order 1 9/30/2015 9,844,192

Actual LRNIP Y3-Y4 program.-Norapat- Variation Order 2 12/17/2015 -2,172,295 --Eeghegnut-Eraskhahun, J/V "Kuarlini" LLC, km0+000-km7+800 "Sisiani FPAT" LLC Contract CW-NCB-LRNIP- 16 7.8 1 NCB Post 6/2/2016 $2,326,904 AMD 1,079,816,176 100% 100% AMD 1,082,045,045 Variation Order 3 5/31/2016 -8,636,890 (CW-NCB-LRNIP -2015/10) and "Road- 2015/10 N/A N/A 3/18/2015 4/20/2015 5/25/2015 N/A 5/25/2015 6/5/2015 6/12/2015 8/1/2016 Transport cars"CJSC Variation Order 4 7/21/2016 -957,100

Variation Order 5 7/29/2016 -306,776

Planned N/A N/A 3/24/2015 4/24/2015 5/1/2015 N/A 5/12/2015 5/13/2015 5/14/2015 12/30/2017 Variation Order 1 7/2/2015 112,377,756

LRNIP Y3-Y4 program.Armavir-Norapat- Mrgashat-Arevik-Eeghegnut-Eraskhahun, Contract CW-NCB-LRNIP- 17 11 1 NCB Post Kapavor LTD 12/26/2015 $2,091,112 AMD 1,002,942,242 100% 100% AMD 888,389,029 km7+800-km18+795 2015/11 (CW-NCB-LRNIP -2015/11) Public Disclosure Authorized Actual LRNIP Y3-Y4 program.Armavir-Norapat- Variation Order 2 9/7/2015 1,627,747 Mrgashat-Arevik-Eeghegnut-Eraskhahun, Contract CW-NCB-LRNIP- 17 11 1 NCB Post Kapavor LTD 12/26/2015 $2,091,112 AMD 1,002,942,242 100% 100% AMD 888,389,029 km7+800-km18+795 2015/11 Variation Order 3 10/14/2015 -14,520 N/A N/A 3/18/2015 4/20/2015 5/25/2015 N/A 5/25/2015 5/26/2015 6/2/2015 11/27/2015 (CW-NCB-LRNIP -2015/11) Variation Order 4 05.11.2015 835,190 Variation Order 5 11/27/2015 -272,960 Planned N/A N/A 3/23/2015 4/24/2015 4/30/2015 N/A 5/11/2015 5/12/2015 5/14/2015 12/30/2017 Variation Order 1 7/29/2015 -11,179,276 LRNIP Y3-Y4 program.Ashtarak-Oshakan- Actual Dasht-M3, km0+000-km8+796 Contract CW-NCB-LRNIP- Variation Order 2 10/22/2015 32,639,394 18 (CW-NCB-LRNIP-2015/4) 8.8 1 NCB Post Kotayk REC LLC 6/3/2016 $1,787,008 AMD 855,503,446 100% 100% AMD 833,988,725 2015/4 N/A N/A 3/20/2015 4/22/2015 5/25/2015 N/A 5/25/2015 6/3/2015 6/10/2015 12/15/2015 Variation Order 3 12/4/2015 209,885

Variation Order 4 12/16/2015 -155,282 Planned LRNIP Y3-Y4 program.-- N/A N/A 3/24/2015 4/24/2015 5/1/2015 N/A 5/12/2015 5/13/2015 5/14/2015 12/30/2017 Variation Order 1 6/30/2015 43,414,241 Yehvard-M1,km0+000-km12+000 Contract CW-NCB-LRNIP- 19 Actual (CW-NCB-LRNIP-2015/5) 12 1 NCB Post "Kapavor" LTD 5/26/2016 $2,412,822 AMD 1,152,395,736 100% 100% AMD 1,108,985,500 2015/5 Variation Order 2 9/7/2015 -2,312 N/A N/A 3/20/2015 4/22/2015 5/25/2015 N/A 5/25/2015 5/26/2015 6/1/2015 10/27/2015 Variation Order 3 10/14/2015 -1693 Planned N/A N/A 5/7/2015 6/10/2015 6/19/2015 N/A 6/22/2015 6/22/2015 6/29/2015 12/30/2017 Variation Order 1 7/24/2015 7,969,147 Actual Variation Order2 19.09.2015 1,839,685

Variation Order 3 9/22/2015 19,822,644 LRNIP Y3-Y4 program (additional road). J/V: “KHACHHAR” Dashtadem-H75 km7+706-km13+300, LLC, “Ararat- Contract CW-NCB-LRNIP- 20 Dashtadem-H75km13+300-km18+972 and H17- 14.9 1 NCB Post Chanshin” LLC and 7/3/2016 $3,200,174 AMD 1,531,406,857 100% 100% AMD 1,509,870,648 Variation Order 4 15.10.2015 -2,580,456 2015/13 km0+000-km3+700 N/A N/A 5/7/2015 6/10/2015 6/19/2015 N/A 6/22/2015 7/3/2015 7/10/2015 12/17/2015 “Motor Transport and (CW-NCB-LRNIP-2015/13) Road of Talin” CJSC Variatiom Order 5 11/20/2015 -2,335,214

Variatiom Order 6 11/30/2015 5,809,120

Variatiom Order 7 12/8/2015 -8,632,801

Variatiom Order 8 12/18/2015 -355,916 Planned N/A N/A 5/7/2015 6/10/2015 6/19/2015 N/A 6/22/2015 6/22/2015 6/29/2015 12/30/2017 Variation Order 1 8/4/2015 -2,216,088 Actual Variation Order 2 23.09.2015 2,164,932

Variation Order 3 9/28/2015 44,570,373 LRNIP Y3-Y4 program (additional road). road Sevan-Varser, km0+000-km-3+577 and Contract CW-NCB-LRNIP- 21 3.8 1 NCB Post “Shant-Sejran” LLC 12/7/2015 $1,220,099 AMD 585,663,457 100% 100% AMD 475,136,148 Variation Order 4 10/20/2015 66,215,220 road M4-Sevan- M4, km 0+000-km 1+044 N/A N/A 5/7/2015 6/10/2015 6/24/2015 N/A 6/26/2015 7/7/2015 7/8/2015 12/8/2015 2015/14 (CW-NCB-LRNIP-2015/14) Variation Order 5 11/17/2015 6,965,712

Variation Order 6 11/27/2015 -6,993,116

Variation Order 7 12/15/2015 -179,724

Planned LRNIP Y3-Y4 program (additional road). (L- N/A N/A 7/20/2015 8/21/2015 8/31/2015 N/A 9/2/2015 9/4/2015 9/11/2015 12/30/2017 Variation Order 1 11/6/2015 46,200,407 2-25) –Lanjazat - (L-2-27) km 0+000-km “Zangezurtransbuild Contract CW-NCB-LRNIP- 22 2.8 1 NCB Post 1/31/2016 $593,907 AMD 286,244,372 100% 100% AMD 213,488,945 Actual 2+831 ” OJSC 2015/15 N/A N/A 7/22/2015 8/21/2015 8/27/2015 N/A 8/27/2015 8/31/2015 9/7/2015 12/17/2015 Variation Order 2 12/10/2015 26,555,020 (CW-NCB-LRNIP-2015/15) Planned N/A N/A 5/20/2016 6/20/2016 6/29/2016 N/A 7/2/2016 7/30/2016 8/6/2016 8/6/2017 LRNIP Y3-Y4 program (additional road) Contract CW-NCB-LRNIP- 23 3.1 1 NCB Post “Kuarlini” LLC 7/27/2016 $737,632 AMD 350,264,994 0 20% AMD 350,264,994 Actual Djanfida 2016/4 N/A N/A 6/2/2016 7/4/2016 7/11/2016 N/A 7/12/2016 7/27/2016 8/3/2016 Under construction

Planned TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD 23 LRNIP Y4 program . TBD TBD NCB Post Actual

2. GOODS Planned Supply and installation of road portable profiler, including the 6/27/2014 7/4/2014 7/5/2014 8/19/2014 9/15/2014 9/5/2014 9/6/2014 10/3/2014 9/25/2014 3/15/2015 Contract NoICB- 1 ICB Prior DYNATEST $151,533 Euro 134 400 100% 100% Actual training 1 6/27/2014 7/1/2014 7/5/2014 8/19/2014 8/27/2014 8/27/2014 9/3/2014 9/25/2014 9/25/2014 3/15/2015 LRNIP-G/2014-1 Planned N/A N/A 11/30/2014 12/15/2014 12/15/2014 N/A 12/18/2014 12/18/2014 12/19/2014 12/22/2014 "Toyota-Yerevan" Contract No SH/V- 2 4WD Vehicle for ARD SH Post $58,073 AMD 24 180 000 100% 100% Actual 1 N/A N/A 11/30/2014 12/15/2014 12/15/2014 N/A 12/18/2014 12/18/2014 12/19/2014 12/22/2014 LLC 2014/1 Planned 3/10/2016 3/14/2016 3/14/2016 5/10/2016 5/16/2016 5/26/2016 6/4/2016 6/6/2016 6/14/2016 10/14/2016 3 Traffic counters ICB Prior Actual 1 4/8/2016 4/11/2016 4/29/2016 6/28/2016 10/31/2016 11/9/2016 The bid is rejected Planned 12/15/2016 12/20/2016 12/20/2016 2/2/2017 2/12/2017 2/19/2017 2/20/2017 3/15/2017 3/20/2017 6/20/2017 4 Traffic counters ICB Prior Actual 1 Planned N/A N/A 2/16/2017 3/1/2017 3/10/2017 3/16/2017 3/21/2017 3/30/2017 3/30/2017 6/30/2017 Supply of road signs* NCB Post 5 Actual 1 Planned N/A N/A 3/1/2017 3/17/2017 3/20/2017 N/A 3/25/2017 3/28/2017 3/29/2017 4/3/2017 SH 6 Actual IT/ Office Equipment** Post 1 Planned Office furniture for PIU (including furniture set for conference N/A N/A 3/1/2017 3/17/2017 3/20/2017 N/A 3/25/2017 3/28/2017 3/29/2017 4/3/2017 7 SH Post Actual hall)*** 1 Review Adverti- Shortlist/RFP No objection Comple- Procurement Selection by Bank sement Receiving of Proposal Technical Final Start Actual Contract price in Actual Contract price in Contract price as of Changed contract Description of Assignment/ Location submitted to No objection Issuing of RFP No objection to the draft Contract signing tion Consultant Contract ID Amendment Amendment sign date ref.# Method Prior / for EOI EOI submission evaluation evaluation Date USD the contract currency contract signing date amount the Bank contract Date Post Date 3. CONSULTANTS' SERVICES

Planned 2/12/2013 3/12/2013 1/25/2013 - - 5/16/2013 - - - - 5/17/2013 5/20/2013 30.12.2016* Joint venture of “Ameria” CJSC 1 Social Monitoring and Evaluation Study CQS Post $59,066 AMD 24,640,000 SME- LRNIP AMD 20,780,000 Amendment 1 1/22/2016 AMD 3,860,000 and “Media- Actual 2/12/2013 3/12/2013 - - - 5/16/2013 - - - - 5/17/2013 5/20/2013 12/10/2016 Model” LLC

9/21/2012 1/25/2013 2/5/2013 2/5/2013 4/20/2013 5/6/2013 Planned 8/24/2012 3/6/2013 3/15/2013 3/20/2013 5/6/2013 5/20/2013 12/30/2016 Kocks Consult 2 Technical Supervision of LRNIP Y1 roads QSBC Prior $1,296,966 $1,296,966 TS-LNIP Y1-2013 GMBH (Germany) Actual 8/24/2012 9/21/2012 1/25/2013 2/5/2013 2/5/2013 3/6/2013 3/15/2013 3/20/2013 4/20/2013 5/6/2013 5/6/2013 5/20/2013

- 10/24/2013 11/18/2013 11/25/2013 Planned 9/24/2013 12/25/2013 2/5/2014 - 2/12/2014 - 2/14/2014 3/10/2014 12/1/2017 Grant Thornton LRNIP-A#1 No AT- 3 Audit of Project accounts (2013-2017) LCS Post $40,752 AMD 16,800,000 CJSC A4-016-04 Actual 9/24/2013 - 10/24/2013 11/18/2013 11/25/2013 12/25/2013 2/5/2014 - 2/12/2014 - 2/14/2014 3/10/2014

Contract No. DAS- Planned 4/30/2013 5/23/2014 5/29/2014 6/4/2014 6/4/2014 7/4/2014 7/10/2014 8/20/2014 8/20/2014 8/27/2014 8/27/2014 9/2/2014 6/30/2017 $205,404 $14,580 LRNIP-Y3-Y4

Design and Author Supervision of LRNIP Y3,Y4 roads and “Dorproject” 4 QSBC Prior $1,174,410 $1,174,410 Amendment 1 3/11/2015 Black Spots Improvement Institute LTD

Contract No. D- Actual 4/30/2013 5/23/2014 5/29/2014 6/4/2014 6/4/2014 7/4/2014 7/10/2014 8/20/2014 8/20/2014 8/27/2014 8/27/2014 9/2/2014 $818,496 $135,930 LRNIP-Y3-Y4

Planned 6/6/2014 6/20/2014 5/9/2014 8/9/2014 9/9/2014 9/10/2014 10/17/2014 10/24/2014 10/28/2014 11/11/2014 11/20/2014 11/20/2014 7/20/2015 Routhton Contract FS-LRNIP- 5 Roads Financing Study FBS Prior $300,000 $300,000 Actual 6/6/2014 6/20/2014 5/9/2014 8/9/2014 9/9/2014 9/10/2014 10/17/2014 10/29/2014 11/10/2014 11/13/2014 11/14/2014 11/20/2014 7/20/2015 International 2014 Planned 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 2017/2018 6 Road Safety Education and Public Awareness CQS Post Actual Individual Planned Concept of Road Assets Output and Performance Based 11/30/2014 12/14/2014 12/15/2014 12/18/2014 12/18/2014 12/20/2014 1/9/2015 1/12/2015 1/12/2015 1/15/2015 1/15/2015 1/15/2015 5/1/2015 Contract No PBC-I- 7 IC Prior Consultant Raimo $68,974 $68,974 Contracting 2015 Actual 11/26/2014 12/10/2014 12/25/2014 1/5/2015 1/13/2015 1/23/2015 N/A N/A 7/21/2015 7/24/2015 7/30/2015 8/23/2015 Sallanmaa Planned 11/30/2014 12/15/2014 12/24/2014 1/19/2015 1/20/2015 2/20/2015 2/25/2015 3/1/2015 3/5/2015 3/10/2015 3/20/2015 4/15/2015 6/30/2017 Amendment 1 7/29/2015 $187,483 Technical Supervision of LRNIP Y3 and Y4 roads and Black Kocks Consult Contract TS-LRNIP- 8 QCBS Prior $2,325,427 $2,325,427 $2,085,600 Actual Spots Improvement 12/16/2014 1/14/2015 1/20/2015 1/26/2015 1/27/2015 2/27/2015 3/30/2015 4/1/2015 4/14/2015 6/26/2015 6/29/2015 6/1/2015 GMBH (Germany) Y3-Y4-2015 Amendment 2 9/1/2015 $52,344

Planned Postponed Postponed Postponed Postponed Postponed Postponed Postponed Postponed Postponed Postponed Postponed Postponed Postponed 9 Road Safety Capacity Building IC Prior Actual

Planned Preparation of Design and Environmental Management Plans “Dorproject” Amendment 1 3/29/2016 10 QCBS Prior 4/9/2015 5/5/2015 5/25/2015 6/5/2015 6/10/2015 7/20/2015 7/30/2015 8/10/2015 8/15/2015 8/20/2015 8/30/2015 9/5/2015 6/30/2017 $361,470 $419,502 D-LRNIP-AF-Y1 $361,470 LRNIP-AF Year 1 roads rehabilitation works Institute LTD Actual Amendment 2 $58,032 4/9/2015 5/5/2015 6/17/2015 7/17/2015 7/20/2015 8/20/2015 9/1/2015 9/9/2015 10/2/2015 10/22/2015 11/2/2015 11/2/2015 6/2/2016 5/25/2016 Planned Preparation of Design and Bidding Documents for Road Assets TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD 11 FBS Post Actual Output and Performance Based Contracting Planned 2/5/2017 2/20/2017 2/28/2017 N/A 3/1/2017 3/30/2017 07.04..2017 N/A 4/10/2016 N/A 4/15/2017 4/25/2016 10/1/2019 12 Independent Technical Audit* CQS Post Actual Planned TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD 13 Design of Future Road Project CQS Post Actual Planned TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD 14 Training TBD Actual