Report on Public Debt (Domestic and External Loans) Guarantees And

Total Page:16

File Type:pdf, Size:1020Kb

Report on Public Debt (Domestic and External Loans) Guarantees And THE REPUBLIC OF UGANDA REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 Presented to Parliament by Hon. Matia Kasaija Minister for Finance, Planning and Economic Development March 2016 REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 i THE REPUBLIC OF UGANDA REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 Presented to Parliament by Hon. Matia Kasaija Minister for Finance, Planning and Economic Development March 2016 REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES ii AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 1 Table of Contents List of Tables ................................................................................................................................ 3 List of Charts ................................................................................................................................ 4 List of Acronyms .......................................................................................................................... 5 EXECUTIVE SUMMARY ............................................................................................................... 6 2.0 BACKGROUND ..................................................................................................................... 7 2.1 External Assistance ................................................................................................................ 7 2.2 Domestic Debt ........................................................................................................................ 8 3.0. GOVERNMENT INDEBTEDNESS ............................................................................................ 9 3.1 External Debt .......................................................................................................................... 9 3.1.1 External Debt by Source ................................................................................................... 10 3.1.2 External Debt Trends. ........................................................................................................ 10 3.1.3 External Debt by Creditor .................................................................................................. 11 3.1.4 External Debt Service ........................................................................................................ 12 3.1.5 Commitment fees paid out ................................................................................................ 14 3.2 Domestic debt ...................................................................................................................... 14 3.2.1 Domestic Debt by type and tenure ................................................................................... 15 3.2.3 Domestic Debt Trends FY 2011/12- FY 2014/15 .............................................................. 16 3.2.3 Domestic Debt Service FY 2014/15 .................................................................................. 17 3.2.4 Market developments ........................................................................................................ 18 3.3 Public Debt Sustainability .................................................................................................... 19 3.3.1 Debt Sustainability Stance as end June 2015. .................................................................. 19 4.0 NEW EXTERNAL FINANCING ................................................................................................21 4.2 New Loans Approved by Parliament in FY 2015/16 ............................................................ 21 4.2.1 New Loan Commitments by Sector .................................................................................. 22 4.2.4 Status of pipeline projects ................................................................................................. 24 4.2.5 The Creditor Terms ........................................................................................................... 25 4.3 Grant Agreements Concluded in FY 2015/16 as at 31st December 2015 ........................... 25 4.3.1 New Grants concluded by Sector in FY 2015/16 as at end December 2015 ................... 26 4.3.3 Trends in the New Grants Concluded ............................................................................... 27 5.0 GOVERNMENT GUARANTEES ...............................................................................................28 6.0 TECHNICAL ASSISTANCE ....................................................................................................31 7.0 PERFORMANCE AND ACHIEVEMENT OF OBJECTIVES OF DEVELOPMENT ASSISTANCE ............3 2 7.1 Financial Performance of Development Assistance ............................................................. 32 REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES 2 AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 7.1.1 Budgeted External resources vs Actual Disbursements ................................................... 32 7.2 Grant Disbursements ........................................................................................................... 33 7.2.1 Grant Disbursements by Development Partner ................................................................ 33 7.2.2 Grant Disbursements by Sector ........................................................................................ 34 7.2.3 Grant Disbursements by Trends ....................................................................................... 34 7.3 Loan Disbursements ............................................................................................................ 35 7.3.1 Loan Disbursements by Sectors ....................................................................................... 35 7.3.2 Loan Disbursements by Creditors ..................................................................................... 35 7.3.3 Loan Disbursement Trends by Creditor FY 2009/10- FY 2015/16.................................... 36 7.4 Alignment of Development Assistance to the NDP II ........................................................... 36 8.0 DEVELOPMENT ASSISTANCE MANAGED OUTSIDE GOVERNMENT SYSTEMS ...............................................39 8.1 Off Budget Disbursements by Sector .................................................................................. 39 8.2 Off Budget Disbursement by Development Partner ............................................................. 40 9.0 CONCLUSION .................................................................................................................................................42 ANNEX 1: STOCK OF EXTERNAL DEBT AS OF 31ST DECEMBER 2015 (USD) .......................................... 43 ANNEX 2: LOAN INVENTORY AND UTILISATION .................................................................................... 50 ANNEX 3: MEDIUM TERM EXPENDITURE FISCAL FRAME WORK FY 2015/16 – FY 2020/21 ................... 68 ANNEX 4: PROJECTS MANAGED OUTSIDE GOVERNMENT SYSTEMS FY 2015/16 – FY 2020/21 ............. 73 ANNEX 5: FISCAL LTEF TABLE USED DURING THE OCTOBER 2015 DSA EXERCISE ................................ 80 ANNEX 6: LIST OF PIPELINE PROJECTS USED DURING THE OCTOBER 2015 DSA EXERCISE .................. 81 ANNEX 7: TECHNICAL ASSISTANCE BY BENEFICIARY AND DEVELOPMENT PARTNER ........................... 83 ANNEX 8: CONTINGENT LIABILITIES FROM MAJOR PPPS OVER THE MEDIUM TERM...........................86 REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 3 Tables Table 1: Total Public Debt by source category Table 2: External Debt stock by source Table 3: Stock of External Debt by Creditor Table 4: Projected vs Actual Debt service by Creditor Table 5: Stock of Domestic Debt as at 31st December 2015 Table 6: Domestic Debt Stock by tenor Table 7: Overview of Domestic Financing for 2015/16 Table 8: Domestic Debt Issuance by time to maturity Table 9: T-Bond yields at primary auction Table 10: Summary of Fiscal Debt Sustainability Status Table 11: New Loans approved by Parliament during FY 2015/16 Table 12: Status of Pipeline loan Projects Table 13: Creditor Terms. Table 14: New Grants Concluded in FY 2014/15 Table 15: Government Guarantees Table 16: Summary of Sector performance as at December 2015 Table 17: Trends in Grant Performance Table 18: Loan Disbursements by trends by Creditor Table 19: Implementation of the National Flagship Projects in the NDP REPORT ON PUBLIC DEBT (DOMESTIC AND EXTERNAL LOANS), GUARANTEES 4 AND OTHER FINANCIAL LIABILITIES AND GRANTS FOR FINANCIAL YEAR 2015/16 Charts Chart 1: Public Debt Trends FY 2006/07 to FY 2015/16 Chart 2: Annual External Public Debt Trends Chart 3: Proportion of DOD by top five Creditors Chart 4: External Debt Service 2011/12- 2015/16 Chart 5: Commitment fees paid out FY 2007/08 – FY 2015/16 Chart 6: Commitment Fees by Creditor Chart 7: Domestic Debt Stock by year of maturity Chart 8: Domestic Debt Stock by tenor Chart 9: Foreign holdings of domestic debt incl. monetary policy securities Chart 10: Domestic Debt trends Chart 11: Domestic
Recommended publications
  • Buikwe District Economic Profile
    BUIKWE DISTRICT LOCAL GOVERNMENT P.O.BOX 3, LUGAZI District LED Profile A. Map of Buikwe District Showing LLGs N 1 B. Background 1.1 Location and Size Buikwe District lies in the Central region of Uganda, sharing borders with the District of Jinja in the East, Kayunga along river Sezibwa in the North, Mukono in the West, and Buvuma in Lake Victoria. The District Headquarters is in BUIKWE Town, situated along Kampala - Jinja road (11kms off Lugazi). Buikwe Town serves as an Administrative and commercial centre. Other urban centers include Lugazi, Njeru and Nkokonjeru Town Councils. Buikwe District has a total area of about 1209 Square Kilometres of which land area is 1209 square km. 1.2 Historical Background Buikwe District is one of the 28 districts of Uganda that were created under the local Government Act 1 of 1997. By the act of parliament, the district was inniatially one of the Counties of Mukono district but later declared an independent district in July 2009. The current Buikwe district consists of One County which is divided into three constituencies namely Buikwe North, Buikwe South and Buikwe West. It conatins 8 sub counties and 4 Town councils. 1.3 Geographical Features Topography The northern part of the district is flat but the southern region consists of sloping land with great many undulations; 75% of the land is less than 60o in slope. Most of Buikwe District lies on a high plateau (1000-1300) above sea level with some areas along Sezibwa River below 760m above sea level, Southern Buikwe is a raised plateau (1220-2440m) drained by River Sezibwa and River Musamya.
    [Show full text]
  • The Least Cost Generation Plan 2016
    THE LEAST COST GENERATION PLAN 2016 – 2025 EXECUTIVE SUMMARY In 2013, the Authority developed a 5 year Least Cost Generation Plan (LCGP) that covered the period 2013 to 2018. An update of the LCGP has been undertaken covering a 10 year period of 2016 to 2025. The update involved review of the load forecast in light of changed parameters, commissioning dates for committed projects, costs of generation plants, transmission and distribution system investment requirements. In the update of the plan, similar to the Power Sector Investment Plan, prepared by the Ministry of Energy and Mineral Development, the ”Econometric Demand” forecasting method was used at distribution level to forecast Commercial, Medium Industry and Large Industry customer category demand. A bottom up approach was used for Domestic customer category using the end-user method. A Base Case, Low Case and High Case scenario were developed for sensitivity analysis. The resultant demand forecast was 6.5%, 3.6% and 12% growth rate in energy demand for the Base Case, Low Case and High Case scenarios respectively. This growth rate is lower than the projection in the 2013 LCGP of 10%, 5% and 14% for Base Case, Low Case and High Case respectively. A number of energy supply options were considered including Hydro, Peat, Solar PV, Bagasse Cogeneration, Wind and Natural Gas. The planned supply considered already existing, committed and candidate generation plants/projects with their estimated commissioning dates aligned. We note that more than 80% of the generation will come from hydro. 1 In the demand supply balance, Figure E1 shows the demand and supply balance over the planning period.
    [Show full text]
  • Private Power Generation (Bujagali) Project (P089659)
    MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE UGANDA: PRIVATE POWER GENERATION (BUJAGALI) PROJECT (P089659); WATER MANAGEMENT AND DEVELOPMENT PROJECT (P123204); AND ENERGY FOR RURAL TRANSFORMATION PHASE III PROJECT (P133312) Management has reviewed the Request for Inspection of the Uganda: Private Power Generation (Bujagali) Project (P089659); Water Management and Development Project (P123204); and Energy for Rural Transformation Phase III Project (P133312), received by the Inspection Panel on June 20, 2016 and registered on September 6, 2016 (RQ16/05). A second Request for Inspection for the same projects was received by the Inspection Panel on September 19, 2016 and registered on September 22, 2016 (RQ16/08). Management has prepared the following response. October 27, 2016 Bujagali, WMDP and ERT-3 Projects CONTENTS Abbreviations and Acronyms ......................................................................................... iv EXECUTIVE SUMMARY ....................................................................................................... v I. INTRODUCTION .......................................................................................................... 1 II. THE PROJECTS .......................................................................................................... 2 III. RELATED PLANS AND AGREEMENTS ........................................................................ 5 IV. ELIGIBILITY CONSIDERATIONS ...............................................................................
    [Show full text]
  • Bujagali Final Report
    INDEPENDENT REVIEW PANEL COMPLIANCE REVIEW REPORT ON THE BUJAGALI HYDROPOWER AND INTERCONNECTION PROJECTS June 20, 2008 1 ACKNOWLEDGEMENTS The IRM Compliance Review Panel could not have undertaken and completed this report without the generous assistance of many people in Uganda and at the African Development Bank. It wishes to express its appreciation to all of them for their cooperation and support during the compliance review of the Bujagali Hydropower and Interconnection projects. The Panel thanks the Requesters and the many individuals from civil society and the communities that it met in the Project areas and in Kampala for their assistance. It also appreciates the willingness of the representatives of the Government of Uganda and the projects’ sponsors to meet with the Panel and provide it with information during its visit to Uganda. The Panel acknowledges all the help provided by the Resident Representative of the African Development Bank in Uganda and his staff and the willing cooperation it has received from the Bank’s Management and staff in Tunis. The Panel appreciates the generous cooperation of the World Bank Inspection Panel which conducted its own review of the “UGANDA: Private Power Generation Project”. The Compliance Review Panel and the World Bank Inspection Panel coordinated their field investigations of the Bujagali projects and shared consultants and technical information during this investigation in order to enhance the efficiency and cost effectiveness of each of their investigations. While this collaboration between the Panel and the World Bank Inspection Panel worked to the mutual benefit of both parties, each Panel focused its compliance review on its own Bank’s policies and procedures and each Panel has made its own independent judgments about the compliance of its Management and staff with its Bank’s policies and procedures.
    [Show full text]
  • Regarding the Bujagali Hydro Power Project (IFC #24408 & MIGA #6732)
    CAO ASSESSMENT REPORT Complaint (Bujagali Energy-07) regarding the Bujagali Hydro Power Project (IFC #24408 & MIGA #6732) Malindi, Uganda April 2016 Office of the Compliance Advisor Ombudsman for the International Finance Corporation and Multilateral Investment Guarantee Agency www.cao-ombudsman.org About CAO The Office of the Compliance Advisor Ombudsman (CAO) is the independent accountability mechanism for the International Finance Corporation (IFC) and the Multilateral Investment Guarantee Agency (MIGA), the private sector arms of the World Bank Group. CAO reports directly to the President of the World Bank Group, and its mandate is to assist in addressing complaints from people affected by IFC/MIGA supported projects in a manner that is fair, objective and constructive and to enhance the social and environmental outcomes of those projects. For more information, see www.cao-ombudsman.org. – 2 – Table of Contents Table of Contents ....................................................................................................................... 3 LIST OF ACRONYMS ................................................................................................................ 4 1. OVERVIEW .......................................................................................................................... 5 2. BACKGROUND ................................................................................................................... 5 2.1. The Project .................................................................................................................
    [Show full text]
  • 2017 Statistical Abstract – Ministry of Energy and Mineral Development
    THE REPUBLIC OF UGANDA MINISTRY OF ENERGY AND MINERAL DEVELOPMENT 2017 STATISTICAL ABSTRACT 2017 Statistical Abstract – Ministry of Energy and Mineral Development i FOREWORD The Energy and Mineral Development Statistics Abstract 2017 is the eighth of its kind to be produced by the Ministry. It consolidates all the Ministry’s statistical data produced during the calendar year 2017 and also contains data dating five years back for comparison purposes. The data produced in this Abstract provides progress of the Ministry’s contribution towards the attainment of the commitments in the National Development Plan II and the Ministry’s Sector Development Plan FY2015/16 – 2019/20. The Ministry’s Statistical Abstract is a vital document for dissemination of statistics on Energy, Minerals and Petroleum from all key sector players. It provides a vital source of evidence to inform policy formulation and further strengthens and ensures the impartiality, credibility of data/information collected. The Ministry is grateful to all its stakeholders most especially the data producers for their continued support and active participation in the compilation of this Abstract. I wish also to thank the Energy and Mineral Development Statistics Committee for the dedicated effort in compilation of this document. The Ministry welcomes any contributions and suggestions aimed at improving the quality of the subsequent versions of this publication. I therefore encourage you to access copies of this Abstract from the Ministry’s Head Office at Amber House or visit the Ministry’s website: www. energyandminerals.go.ug. Robert Kasande PERMANENT SECRETARY 2017 Statistical Abstract – Ministry of Energy and Mineral Development ii TABLE OF CONTENTS FOREWORD .....................................................................................................................................................
    [Show full text]
  • Bujagali Energy Limited Project Number
    BUJAGALI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT SUMMARY Project Title: Bujagali Energy Limited Project Number: P-UG-FAB-008 Country: Uganda Department: Energy Financial Solutions, Policy & Regulation Division: Energy Financial Solutions Project Category: 1 1.0 Introduction Bujagali Energy Limited (BEL) is owned by SG Bujagali Holdings Ltd (an affiliate of Sithe Global Power LLC), Jubilee Insurance Company Ltd., as well as the Africa Power Platform PCC, which is owned by CDC (the UK’s Development Finance Institution), the Aga Khan Fund for Economic Development (AKFED) and IPS Kenya (“the Sponsors”). Operations and Maintenance Energy (Uganda) Limited (O&ME) operates the Hydropower project. The Bujagali Project is a 250MW hydropower facility — developed through a build-own-operate-transfer (BOOT) model — on the Victoria Nile River near the town of Jinja. It reached financial close in 2007, eight years after Government of Uganda (GoU) liberalized its electricity sector in 1999. When commissioned in 2012, it did not only displace expensive emergency power generation, but also contributed towards paving the way for a handful of other smaller scale IPPs that will provide more than 200 MW of small hydro, solar, and bagasse power to the network by around 2020. However, to drive the country’s industrialization program, the GoU is actively looking for ways to reduce the country’s electricity tariffs. In this context, and based on the projected tariff profile, the Bujagali tariff is set to increase from 11.3 US cents/kWh in 2016 to 13.3 US cents/kWh in 2018 and to 14.7 US cents by 2023 due to end of a tax ‘holiday’ (accelerated depreciation) and the debt amortization — before decreasing to 7 US cents/kWh from 2024.
    [Show full text]
  • Uganda Private Power Generation (Bujagali) Project and Submitted Its Investigation Report to the Board on August 29, 2008
    INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION THIRD PROGRESS REPORT ON THE IMPLEMENTATION OF MANAGEMENT’S ACTION PLAN IN RESPONSE TO THE INSPECTION PANEL INVESTIGATION REPORT (REPORT # 44977-UG) ON THE UGANDA PRIVATE POWER GENERATION (BUJAGALI) PROJECT (IDA GUARANTEE NO. B0130-UG) APRIL 25, 2012 ACRONYMS AND ABBREVIATIONS AfDB African Development Bank APRAP Assessment of Past Resettlement Activities and Action Plan BEL Bujagali Energy Limited BEMC Bujagali Environmental Monitoring Commission CDAP Community Development Action Plan CPMP Cultural Property Management Plan EAC East African Community EIB European Investment Bank EPC Engineering, Procurement and Construction ESU Environment and Social Unit GoU Government of Uganda GWh Gigawatt IACC Inter-Agency Coordination Committee IBRD/IDA International Bank for Reconstruction and Development/ International Development Association IFC International Finance Corporation JICA Japan International Cooperation Agency kV Kilo-volts kWh Kilo-watt M&E Monitoring and Evaluation MAP Management Action Plan MEMD Ministry of Energy and Mineral Development MIGA Multilateral Investment Guarantee Agency MW Megawatt NEMA National Environmental Monitoring Agency NFA National Forest Authority OP Operational Policy PAPs Project Affected Persons PoE Panel of Experts RAP Resettlement Action Plan SEAP Social and Environmental Action Plan SMP Sustainable Management Plan UMEME Private Sector Distribution Concessionaire i CONTENTS EXECUTIVE SUMMARY .............................................................................................
    [Show full text]
  • Designation of Tax Withholding Agents) Notice, 2018
    LEGAL NOTICES SUPPLEMENT No. 7 29th June, 2018. LEGAL NOTICES SUPPLEMENT to The Uganda Gazette No. 33, Volume CXI, dated 29th June, 2018. Printed by UPPC, Entebbe, by Order of the Government. Legal Notice No.12 of 2018. THE VALUE ADDED TAX ACT, CAP. 349. The Value Added Tax (Designation of Tax Withholding Agents) Notice, 2018. (Under section 5(2) of the Value Added Tax Act, Cap. 349) IN EXERCISE of the powers conferred upon the Minister responsible for finance by section 5(2) of the Value Added Tax Act, this Notice is issued this 29th day of June, 2018. 1. Title. This Notice may be cited as the Value Added Tax (Designation of Tax Withholding Agents) Notice, 2018. 2. Commencement. This Notice shall come into force on the 1st day of July, 2018. 3. Designation of persons as tax withholding agents. The persons specified in the Schedule to this Notice are designated as value added tax withholding agents for purposes of section 5(2) of the Value Added Tax Act. 1 SCHEDULE LIST OF DESIGNATED TAX WITHOLDING AGENTS Paragraph 3 DS/N TIN TAXPAYER NAME 1 1002736889 A CHANCE FOR CHILDREN 2 1001837868 A GLOBAL HEALTH CARE PUBLIC FOUNDATION 3 1000025632 A.K. OILS AND FATS (U) LIMITED 4 1000024648 A.K. PLASTICS (U) LTD. 5 1000029802 AAR HEALTH SERVICES (U) LIMITED 6 1000025839 ABACUS PARENTERAL DRUGS LIMITED 7 1000024265 ABC CAPITAL BANK LIMITED 8 1008665988 ABIA MEMORIAL TECHNICAL INSTITUTE 9 1002804430 ABIM HOSPITAL 10 1000059344 ABUBAKER TECHNICAL SERVICES AND GENERAL SUPP 11 1000527788 ACTION AFRICA HELP UGANDA 12 1000042267 ACTION AID INTERNATIONAL
    [Show full text]
  • Electricity Supply Industry Performance Report for the Year 2018
    Performance of Uganda’s Electricity Supply Industry in 2018 ELECTRICITY SUPPLY INDUSTRY PERFORMANCE REPORT FOR THE YEAR 2018 Off Grid Grid Supply Supply Total =976.5 MW =7.5 MW =984.0 MW i | P a g e Performance of Uganda’s Electricity Supply Industry in 2018 TABLE OF CONTENTS ACRONYMS ....................................................................................................................... iv LIST OF FIGURES .................................................................................................................. v EXECUTIVE SUMMARY.................................................................................................. vii I.Peak Demand ................................................................................................................vii II.Installed Generation Capacity ...................................................................................vii III.Electricity Supply to the National Grid ......................................................................vii IV.Transmission ................................................................................................................. viii V.Electricity Distribution .................................................................................................. viii VI.Off-Grid Generation and Supply ................................................................................ix 1.0.BACKGROUND ............................................................................................................. 1 1.1.Introduction ................................................................................................................
    [Show full text]
  • UNSETTLING BUSINESS Social Consequences of the Bujagali Hydropower Project
    UNSETTLING BUSINESS Social consequences of the Bujagali hydropower project 1 Summary The Bujagali hydropower dam on The River Nile in Uganda was fi nally commis- sioned in August 2012 after eighteen years of controversy that delayed the dam con- struction. The dam faced numerous economic, environmental, social and spiritual challenges that stalled the dam construction while the project underwent investigations over bribery claims and project reviews on the dam design and capacity. The dam cost kept on growing from $580 million at inception to $860 million and fi nally $902 million ($3.6million per MW) at completion. Independent investigations by the Ugan- dan Parliamentary adhoc committee on energy put the dam’s actual cost at $1.3 billion ($5.2million per MW or more). The dam project was marketed by The Government of Uganda and the World Bank as the least-cost project. Two different hydropower companies - AES Nile Power and Bujagali Energy Limited – feature in the development of the Bujagali hydropower dam in Uganda. The project was undertaken as a Public Private Partnership between the Government of Uganda and International Financial Corporation (IFCs), the World Bank Group, European Investment Bank, African Development Bank in collaboration with dam construction companies- Industrial Promotions Services (IPS), a holding company of the Aga Khan and Sithe Global Power. The project partners, IPS, Sithe Global Power and the government set up a new company- Bujagali Energy Ltd (BEL) to operate and run the project. The Bujagali hydropower dam development was marred with controversies that saw the dam take over 18 years to complete. The dam project was investigated four times, twice by the Inspection Panel of The World Bank, by The African Development Bank’s Independent Review Mechanism (IRM), and by The European Investment Bank’s Compliance Review.
    [Show full text]
  • Uganda: Brave Reforms and New Growth
    UGANDA: BRAVE REFORMS AND NEW GROWTH Chapter 3 Uganda: brave reforms and new growth For decades Uganda has suffered from inadequate power supply. A disruptive civil war (from 1971 to 1986) and decreasing water levels in Lake Victoria, the main reservoir for the country’s hydro dominated electric power system, exacerbated this problem and led to a 60 per cent decrease in the country’s available generating capacity. It is therefore not surprising that as at 2009, overall access to electricity in Uganda was a low 11 per cent (41% urban, 4% rural),1 resulting in one of the lowest per capita electricity consumption rates in Africa. Another feature of the supply crisis is the high level of distribution losses which were measured at 40 per cent in 1988, and has remained above 30 per cent ever since. To deal with the crisis, the government in 1999 embarked upon the most extensive power-sector reform programme ever witnessed on the African continent. The state-owned and vertically integrated Uganda Electricity Board (UEB) was unbundled, and generation and distribution were subsequently privatised through 20-year concession agreements. An independent regulator, the Electricity Regulatory Authority, was established, together with the Electricity Disputes Tribunal and the Rural Electrification Fund. In the meantime, the country’s main hydropower station was rehabilitated, and an additional one was built nearby, bringing installed capacity to 380MW. Overall productivity increased with a leaner and more professional workforce. With generation liberalised, negotiations for the development of the first independent power producer (IPP), the 250MW Bujagali hydroproject, began. Financial closure on the Bujagali Project proved elusive however, and the negotiations became lengthy and controversial.
    [Show full text]