DEPARTMENT OF TRANSPORTATION and SMC MASS RAIL TRANSIT 7, INC. MRT 7 PROJECT THE PROJECT CONCESSION

CA CONCESSION AGREEMENT Signed: June 18, 2008 Confirmed and Approved by NEDA Board: July 9, 2009 Effectivity of CA: February 19, 2016

Milestones Conceptualized: 2001 NEDA Board re-approval of Cost: 21 November 2013 Signing of Implementation Guidelines (IG): 21July 2014 Effectivity of CA: 19 February 2016 Start of Construction: August 2016 Concession Period: 25 Years

Project Cost

USD 1,540,004,020.86 COMPONENTS OF THE PROJECT

• 22.6 kms rail system from North Avenue EDSA to San Jose del Monte Bulacan • Joint Station with LRT Line 1, MRT Line 3 and Subway along North EDSA • 108 cars or 36 trainsets (3-car configuration) • Can operate at 6-car configuration RAIL • 3rd rail power system METRO RAIL TRANSIT SYSTEM (MRTS)

• 6-lane Highway that will connect the Intermodal Transportation Terminal (ITT) in San Jose Del Monte, Bulacan to Bocaue/Balagtas Interchange North Luzon Expressway (NLEX). HIGHWAY MRT 7 – ROAD ACCESS

• Located adjacent to Depot which can accommodate 60 buses at any INTERMODAL given time, complete with facilities, i.e., passenger waiting areas, TRANSPORTATION lounges, ticket booths, etc. TERMINAL • With facilities standard to an intermodal terminal INTERMODAL TRANSPORTATION TERMINAL (ITT) MRT7 ALIGNMENT

STATION TO STATION DISTANCE (m)

North Avenue - QMC 2,195 QMC - University Avenue 836 University Avenue - Tandang Sora 1,664 Tandang Sora - Don Antonio 2,356 Don Antonio – Batasan 973 Batasan - Manggahan 1391 Manggahan - Doña Carmen 1,470 Doña Carmen - Regalado 1,145 Regalado - Mindanao 3,430 Mindanao - Quirino 787 Quirino - Sacred Heart 1,855 Sacred Heart - Tala 2,025 Tala - San Jose Del Monte 2,543 TOTAL 22,623 PROJECT STATUS Particulars Physical Remarks/Status Accomplishment I. Civil Works 40.16%

i. Guideway On-going guideway construction (14,000m out of 23,200m) along Sta. 2,4,5,6,7,8 & 9 1. Underground/Depressed Excavation/concreting works in progress

2. At-grade Excavation/concreting works in progress

3. Elevated Installation of coping beam, girder & trans-slabs are in progress ii. Stations On-going construction on 9 stations 1. Elevated On-progress

2. Underground/Depressed On-progress

II. Rolling Stock and E&M Works 53.22% The shipment of the 1st set of trains which is available January 2018 was deferred due to unavailability of the holding/depot area. At present, 108 cars are already completed.

Total Accomplishment 46.44% As of July 2019 01-North Avenue Station (Elevated) On-going Column Rebar Installation and Bored Piling Works

02-Quezon Memorial Circle Station (Depressed) Preparation for Track Works 03-University Avenue Station (Depressed) On going Construction of Mat foundation

04-Tandang Sora Station (Elevated) Bored Piling Works 05-Don Antonio Station (Elevated) Girders and Trans-Slab Erection

06- (Elevated) Steel Beams and Girder Erection 07-Manggahan Station (At-Grade) Installation of Columns and Bored Piling Works

08-Doña Carmen Station (Elevated) Column Installation 09-Regalado Station (Elevated) Installation of Columns

10-Mindanao Avenue Station (Elevated) Column Rebar Installation and Bored Piling Works 11-Quirino Station (Elevated) Girder and Trans-Slab Erection

12- (At-Grade) Installation of Girders along Sacred Heart Guideway 13- (Elevated) Guideway to Tala with Several Coping Beams and Girders

14-San Jose Del Monte Station (Depressed) Under Expropriation 22.6 km

19.65 km

16.9 km COMPLETED TRAINS THANK YOU!