MRT 7 Project Site Visit

MRT 7 Project Site Visit

DEPARTMENT OF TRANSPORTATION and SMC MASS RAIL TRANSIT 7, INC. MRT 7 PROJECT THE PROJECT CONCESSION CA CONCESSION AGREEMENT Signed: June 18, 2008 Confirmed and Approved by NEDA Board: July 9, 2009 Effectivity of CA: February 19, 2016 Milestones Conceptualized: 2001 NEDA Board re-approval of Cost: 21 November 2013 Signing of Implementation Guidelines (IG): 21July 2014 Effectivity of CA: 19 February 2016 Start of Construction: August 2016 Concession Period: 25 Years Project Cost USD 1,540,004,020.86 COMPONENTS OF THE PROJECT • 22.6 kms rail system from North Avenue EDSA to San Jose del Monte Bulacan • Joint Station with LRT Line 1, MRT Line 3 and Subway along North EDSA • 108 cars or 36 trainsets (3-car configuration) • Can operate at 6-car configuration RAIL • 3rd rail power system METRO RAIL TRANSIT SYSTEM (MRTS) • 6-lane Highway that will connect the Intermodal Transportation Terminal (ITT) in San Jose Del Monte, Bulacan to Bocaue/Balagtas Interchange North Luzon Expressway (NLEX). HIGHWAY MRT 7 – ROAD ACCESS • Located adjacent to Depot which can accommodate 60 buses at any INTERMODAL given time, complete with facilities, i.e., passenger waiting areas, TRANSPORTATION lounges, ticket booths, etc. TERMINAL • With facilities standard to an intermodal terminal INTERMODAL TRANSPORTATION TERMINAL (ITT) MRT7 ALIGNMENT STATION TO STATION DISTANCE (m) North Avenue - QMC 2,195 QMC - University Avenue 836 University Avenue - Tandang Sora 1,664 Tandang Sora - Don Antonio 2,356 Don Antonio – Batasan 973 Batasan - Manggahan 1391 Manggahan - Doña Carmen 1,470 Doña Carmen - Regalado 1,145 Regalado - Mindanao 3,430 Mindanao - Quirino 787 Quirino - Sacred Heart 1,855 Sacred Heart - Tala 2,025 Tala - San Jose Del Monte 2,543 TOTAL 22,623 PROJECT STATUS Particulars Physical Remarks/Status Accomplishment I. Civil Works 40.16% i. Guideway On-going guideway construction (14,000m out of 23,200m) along Sta. 2,4,5,6,7,8 & 9 1. Underground/Depressed Excavation/concreting works in progress 2. At-grade Excavation/concreting works in progress 3. Elevated Installation of coping beam, girder & trans-slabs are in progress ii. Stations On-going construction on 9 stations 1. Elevated On-progress 2. Underground/Depressed On-progress II. Rolling Stock and E&M Works 53.22% The shipment of the 1st set of trains which is available January 2018 was deferred due to unavailability of the holding/depot area. At present, 108 cars are already completed. Total Accomplishment 46.44% As of July 2019 01-North Avenue Station (Elevated) On-going Column Rebar Installation and Bored Piling Works 02-Quezon Memorial Circle Station (Depressed) Preparation for Track Works 03-University Avenue Station (Depressed) On going Construction of Mat foundation 04-Tandang Sora Station (Elevated) Bored Piling Works 05-Don Antonio Station (Elevated) Girders and Trans-Slab Erection 06-Batasan Station (Elevated) Steel Beams and Girder Erection 07-Manggahan Station (At-Grade) Installation of Columns and Bored Piling Works 08-Doña Carmen Station (Elevated) Column Installation 09-Regalado Station (Elevated) Installation of Columns 10-Mindanao Avenue Station (Elevated) Column Rebar Installation and Bored Piling Works 11-Quirino Station (Elevated) Girder and Trans-Slab Erection 12-Sacred Heart Station (At-Grade) Installation of Girders along Sacred Heart Guideway 13-Tala Station (Elevated) Guideway to Tala with Several Coping Beams and Girders 14-San Jose Del Monte Station (Depressed) Under Expropriation 22.6 km 19.65 km 16.9 km COMPLETED TRAINS THANK YOU!.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    15 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us