HARYANA POWER SECTOR February 2009

TABLE OF CONTENTS Sr. Description Page No. No.

Profile of Power Sector 10

1. Vision 11

2. DISTRIBUTION UTILITIES

2.1 Names of Districts covered under various operation circles 12

2.2 Category-wise total no. of connections/connected load 13

2.3 Total no. of 11 KV / 33KV feeders 14

2.4 Length of LT/HT line UHBVN 14

2.5 Improvement in Distribution system 15

2.6 Financial & Technical progress in the Power Distribution Sector since 15-16

reforms

2.7 Special campaign for recovery of arrears of electricity bills 17

2.8 Settlement of the pending electricity bills of rural domestic & agriculture 18

consumers

2.9 Surcharge Waiver Scheme for Domestic consumers in Urban Areas 19-20

2.10 Voluntary Disclosure Scheme 21-23

2.11 Out of court settlement scheme 24

2.12 Checking of Power Thefts 25

2.13 Release of tubewell connections under various Tatkal Schemes 26-27

1 2.14 100% metering in Power Utility 28

2.15 Rehabilitation of 11kv Overloaded Feeders during 2005-06, 2006-07, 2007-08 & 28

2008-09

2.16 Reduction in damage rate of distribution transformers of UHBVN 29

2.17 Details of distribution transformers added in the System 29

2.18 Detail of achievements in respect of new/augmentation works of 33kV S/Stns 29

2.19 Progress regarding new/augmentation of 33kV lines 30

2.20 Circle wise Distribution losses and AT & C Losses 2008-09 (upto Nov. 2008) 30

2.21 Status of AT & C Losses 31

2.22 Recovery against Land Revenue Act 31

2.23 Defaulting amount ending October 2008 32

2.24 Other major achievements 32

2.25 Rajiv Gandhi Grameen Vidyutikaran Yojna Scheme 33-34

2.26 Segregation of agriculture load from rural domestic load 35-37

2.27 APDRP scheme 38-40

2.28 WS & S Connections (Public Health) 41

3. FINANCIAL POSITION OF HARYANA POWER UTILITIES

3.1 Profitability results 42

3.2 RE Subsidy 42

3.3 T&D Losses 43

3.4 Revenue Vs Cost per unit of power sold 44

3.5 Capital expenditure 44

3.6 Equity capital 45

3.7 Receivables 45

2 3.8 Loans 46

th 3.9 Haryana Power Sector - Summary of proposed 11 Five Year Plan 47

Investments

3.10 Annual Revenue Requirement approved by HERC 48

3.11 Funding of Power Projects through NABARD 49-54

3.12 Distribution tariff applicable in Haryana w.e.f. 1.9.2001 55-57

4. POWER SECTOR REFORMS IN HARYANA

4.1 State Govt. commitment to Power Sector Reforms 58

4.2 Important Milestone achieved 58-59

5. HARYANA POWER PURCHASE CENTER

5.1 Overall Power Supply Position in the State of Haryana 60

5.2 Rain fall data during last 4 years 61

5.3 The availability of the power from July 08 to Dec. 08 61-62

5.4 List of projects where either consent given or PPA signed as on 31.12.08 63-64

5.5 Yearly capacity addition scenario – till the end of 2012-13 65

ANNEXURES I - VII

1. Abstract of Annexure - I - District wise 33kV works completed during March 66

05 to December 08

2. Abstract of Annexure – II - District wise approved 33kV works under 67

construction/to be constructed

3. Abstract of Annexure – III - District wise 66kV and above transmission works 68

completed during March 05 to December 08

4. Abstract of Annexure – IV - District wise approved 66kV and above 69

transmission works i.e. new substations, augmentation of existing

3 substations and transmission lines under construction/to be constructed

5. Cost Abstract of Annexure - IV District wise approved 66kV and above 70

transmission works i.e. new substations, augmentation of existing

substations and transmission lines under construction/to be constructed

6. Annexure – I (District wise 33kV new substations commissioned/ augmented 71-84

and transmission lines added from March 2005 to December 2008

7. Annexure – II (District wise approved 33kV new substations, augmentation & 85-92

lines under construction and to be constructed

8. Annexure – III (District wise 220kV/132kV/66kV new substations 93-104

commissioned/ augmented and transmission lines added from March 2005

to December 2008

9. Annexure – IV (District wise detail of approved 220kV/132kV/66kV new 105-129

substations, augmentation & lines under construction / to be constructed

10. Annexure – V (Year wise progress of construction of new grid substation and 130

augmentation of existing substations during the past 12 years

11. Annexure – VI (Increase in installed capacity in the State in the past fifteen 131

years)

12. Annexure – VII (Power supply position during April-March period of last 10 132

years)

4

ANNEXURES

I TO VII

5

U H B V N L

6

POWER SECTOR REFORM

7

FINANCIAL

8

HPPC

9 PROFILE

Haryana power sector comprises four wholly State-owned Corporations i.e. HPGC, HVPN, UHBVN and DHBVN, which after unbundling of the HSEB in 1998 are responsible for power generation, trading, transmission and distribution in the State.

The State’s power sector was restructured on August 14, 1998. The Haryana State Electricity Board (HSEB) was reorganized initially into two State-owned Corporations namely Haryana Vidyut Prasaran Nigam Ltd. (HVPN) and Haryana Power Generation Corporation Ltd. (HPGC). HPGC was made responsible for operation and maintenance of State’s own power generating stations. HVPN was entrusted the power transmission and distribution functions. Simultaneously, an independent regulatory body i.e. Haryana Electricity Regulatory Commission, was constituted to aid and advise the State Govt. on the development of the power sector, to regulate the power utilities and take appropriate measures to balance the interest of various stake-holders in the power sector, namely electricity consumers, power entities and generation companies, etc.

HVPN was further reorganized on July 1, 1999 by carving out two more Corporations, namely Uttar Haryana Bijli Vitran Nigam Ltd. (UHBVN) and Dakshin Haryana Bijli Vitran Nigam Ltd. (DHBVN) with the responsibility of distribution and retail supply of power within their jurisdiction. While UHBVN is responsible for , Ambala, , , , , , Sonepat, , Jhajjar and districts, DHBVN caters to , Fatehabad, , , , , Mewat, , and districts. These distribution companies are at the moment serving about 43.5 lac consumers of different categories.

The total installed & contracted generation capacity available to the State is 4753.29 MW. The highest daily power supply of 1002.43 lac units was on 20.8.2007 and the record maximum demand of 4826 MW was met on 21.8.2007. The State power utilities are making a befitting contribution to the overall development of the State.

10 1. VISION

1. To perceptibly improve, within three years, the reliability, quantum and quality of power supply to all categories of consumers - agricultural, domestic – rural and urban, industrial, commercial and institutional. 2. To reduce the technical and commercial losses in the system to a level of 15% by 2011-12, by using appropriate and advanced technology, improved management methods and by mobilizing effective public cooperation. 3. To increase the capability of the generation, transmission and distribution systems by optimum and extensive use of I.T. 4. To increase the installed power capacity in the State by a minimum of 5000 MW. Effort would be made to tie up power purchase from pithead power projects on long term basis. Possibility of Joint Venture with other States will also be explored. 5. To formulate and implement a comprehensive human resource development programme for increasing productivity expertise, skills, commitment to the Organization, and personnel growth. 6. To improve the financial status and potential of the Power Utilities through a variety of innovative, stringent and flexible policies and measures. With special focus on recovery of outstanding dues from consumers using an appropriate range of administrative and legal options. 7. To recognize and welcome the emerging competition in the Power Sector, viewing competition as an opportunity to excel and raise the performance of the Power Utilities to international level. 8. To devise and implement a State wide plan for introducing efficiency in energy use through demand side management (DSM) and energy conservation. 9. To constructively apply and utilize the provisions of the Electricity Act, 2003, the National Electricity Policy, the National Electricity Plan, the Energy Conservation Act and relevant Acts and Regulations to create a working frame work of Reform that would tangibly improve the quality of services to consumers and at the same time strengthen the Power Utilities’ core competence.

11

2. DISTRIBUTION UTILITIES: 2.1 Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), Distribution Utilities are looking after the distribution of power supply in the 21 Districts of State through its 15 Operation Circles. The Districts covered in each operation circles are given below:- Table 2.1 Name of circle Name of Districts covered under Circle UHBVN Ambala i) Panchkula ii) Ambala Yamunanagar Yamunanagar Kurukshetra Kurukshetra Kaithal Kaithal Karnal Karnal Panipat Panipat Sonipat Rohtak Rohtak Jhajjar Jhajjar Jind Jind DHBVN Hisar i) Hisar ii) Fatehabad Narnaul i) Mohindergarh ii) Rewari Bhiwani Bhiwani Gurgaon i) Gurgaon ii) Mewat Faridabad i) Faridabad ii) Palwal Sirsa Sirsa

12 2.2 The category-wise total number of connections, connected load and number of new connections released since March 2005 of Discoms is as under:- • Category wise total no. of connections Table 2.2 Ending November- 08 Category UHBVN DHBVN Total DS 1788186 1574010 3362196 NDS 236822 189813 426635 Agriculture 269810 190174 459984 Industrial 35259 43137 78396 Street Light 587 518 1105 Village Chaupal 0 0 0 MITC/Society 48 0 48 PWW 5955 7321 13276 Bulk Supply 246 399 645 Railway Traction 65 1 66 Lift 94 187 281 Other 0 7435 7435 Total 2337072 2012995 4350067

• Category Wise Connected load (in KW) Table 2.3 Ending November-08 Category UHBVN DHBVN Total DS 2061423 2042161 4103584 NDS 420833 434761 855594 Agriculture 2096065 1595430 3691495 Industrial 1651306 2523681 4174987 Street Light 6493 6448 12941 Village Chaupal 0 0 0 MITC/Society 770 0 770 PWW 101475 107681 209156 Bulk Supply 83907 177743 261650 Railway Traction 62061 50000 112061 Lift 20414 86471 106885 Other 0 10642 10642 Total 6504747 7035018 13539765

13 • No. of New connections released :- Table 2.4 Category UHBVN DHBVN Total Mar.- 2005- 2006- 2007- 2008- March- 2005- 2006- 2007- 2008- 2008- 05 06 07 08 09 05 06 07 08 09 09 Upto Upto Upto 11/08 11/08 11/08 DS 6018 61144 58470 61975 40169 5071 69134 88429 71408 44319 84488 NDS 817 9618 9837 10053 6418 666 9230 11863 10327 6340 12758 Agriculture 410 5399 7354 11839 2233 548 7415 8905 11968 7090 9323 Industrial 223 2103 2325 2336 1101 272 3222 3415 3169 1949 3050 Street Light 1 3 18 36 22 0 19 7 20 20 42 MITC/Society 0 2 4 0 0 0 0 3 0 0 0 PWW 32 413 699 666 514 29 538 680 658 551 1065 Bulk Supply 1 2 12 18 9 18 42 32 25 19 28 Railway 0 1 0 0 0 0 1 0 0 0 0 Traction Lift 0 65 15 42 51 0 0 0 0 0 51 Total 7502 78750 78734 86965 50517 6604 89601 113334 97575 60288 110805

2.3 Total no. of 11 KV / 33KV feeders Table 2.5 (Ending November-08) Name of Power Utilities 11KV 33KV

UHBVN 2480 192 DHBVN 2493 121 Total 4973 313

2.4 Length of LT/HT line UHBVN & DHBVN Table 2.6 Period Length of Length of Length of Length of Length of Length LT line (in HT line (in LT line (in HT line (in LT line of HT Kms.) Kms.) Kms.) Kms.) (in Kms.) line (in Kms.) UHBVN DHBVN Total Upto 2003-04 59825 31563 48730 29451 108555 61014 2004-05 543 1174 2052 3450 2595 4624 2005-06 652 785 1074 533 1726 1318 2006-07 528 1380 603 1688 1131 3068 2007-08 730 2585 1160 2932 1890 5517 2008-09 65 842 101 4153 166 4995 (upto 11/2008) Total 62343 38329 53720 42207 116063 80536

14 2.5 IMPROVEMENT IN DISTRIBUTION SYSTEM

89 No. new 33 KV Substations have been commissioned, 144 no. existing 33 kV Sub Stations augmented and 685.406 Km of new 33 KV Lines have been added in the system at a cost of Rs. 189.93 crore to strengthen the distribution system during the period March 2005 to December 2008. The location-wise detail of 33kV substations completed/augmented is as per Annexure-I.

The year-wise abstract of the 33kV works proposed to be carried out during 2008-09 & FY 2009-10. Table 2.7 Period New Substations Augmentation Transmission Lines Total cost No. Cost (Rs. In No. Cost (Rs. Km Cost (Rs. (Rs. In crore) In crore) In crore) crore) 1.1.09 to 34 62.20 18 9.70 277.08 18.30 90.21 31.3.09 2009-10 58 96.27 10 10.84 465.50 22.73 129.83 Total 92 158.47 28 20.54 742.58 41.03 220.04

The location-wise detail of works is as per Annexure-II.

2.6 FINANCIAL AND TECHNICAL PROGRESS IN THE POWER DISTRIBUTION SECTOR SINCE REFORMS

Power Distribution Utilities came into existence w.e.f. July, 1999 and since then modernization and expansion of power distribution system, improved metering and better consumer services are on their main agenda. To make the Utilities commercially viable and to strengthen its financial health, emphasis has been on speedy recovery of dues from the consumers against energy bills and also recovery against the long outstanding dues from the consumers. The following efforts made reflect the effectiveness of the activities/ programmes carried out by the Nigam:-

15

Revenue Assessment Table 2.8 (Rs. In Lacs) Period UHBVN % increase DHBVN % increase Total % Increase 99-2000 107673.71 104126.29 211800.00 2000-01 117481.73 9.11 121713.21 16.89 239194.94 12.93 2001-02 147038.82 25.16 147411.81 21.11 294450.63 23.10 2002-03 154970.75 5.39 162977.00 10.56 317947.75 7.98 2003-04 171603.44 10.73 185471.00 13.80 357074.44 12.31 2004-05 180976.91 5.46 203654.98 9.80 384631.89 7.72 2005-06 187916.00 3.83 233023.57 14.42 420939.57 9.44 2006-07 204228.44 8.68 266064.00 17.87 470292.44 11.72 2007-08 224938.15 10.14 306242.59 15.10 531180.74 12.95 2007-08 (up to Oct.) 138770.54 190089.00 328859.54 2008-09 (up to Oct.) 137908.16 -0.62 201831.01 6.18 339739.17 3.31

Revenue Realisation (Rs. In Lacs) Period UHBVN % increase DHBVN % increase Total % Increase 99-2000 92026.09 93978.00 186004.09 2000-01 110429.10 20.00 112891.26 20.13 223320.36 20.06 2001-02 130633.47 18.30 137013.07 21.37 267646.54 19.85 2002-03 142813.04 9.32 150488.00 9.83 293301.04 9.59 4.59 11.10 316560.42 7.93 2003-04 149366.42 167194.00 148272.32 -0.73 177179.11 5.97 325451.43 2.81 2004-05 2005-06 156391.00 5.48 203261.64 14.72 359652.64 10.51 2006-07 174709.00 11.71 239582.00 17.87 414291.00 15.19 2007-08 206325.00 18.10 297092.00 24.00 503417.00 21.51 2007-08 (up to Oct.) 125984.14 184054.00 310038.14 2008-09 (up to Oct.) 120304.16 -4.51 184031.00 -0.01 304335.16 -1.84

Collection efficiency(%) Period UHBVN DHBVN Total 99-2000 85.47 90.25 87.82

2000-01 94.00 92.75 93.36

2001-02 88.84 92.95 90.90

2002-03 92.15 92.34 92.25

87.04 90.15 88.65 2003-04 2004-05 81.93 87.00 84.61

83.22 87.23 85.44 2005-06 85.55 90.05 88.09 2006-07 2007-08 (up to Oct.) 90.79 96.83 94.77

2008-09 (up to Oct.) 87.23 91.18 89.58

RIB (Rs. In Lacs) Period UHBVN % increase DHBVN % increase Total % Increase 99-2000 95563.35 95215.12 190778.47 2000-2001 112872.80 18.11 115012.60 20.79 227885.40 19.45 2001-2002 136586.89 21.01 142571.48 23.96 279158.37 22.50 2002-2003 144834.00 6.04 159159.85 11.64 303993.85 8.90 2003-04 158394.00 9.36 170173.00 6.92 328567.00 8.08 2004-05 157455.00 -0.59 187055.00 9.92 344510.00 4.85 2005-06 168592.00 7.07 218379.00 16.75 386971.00 12.33 2006-07 191066.00 13.33 18.09 16.01 257874.76 448940.76 2007-08 223400.00 16.92 315568.00 22.37 538968.00 20.05 2007-08 (up to Nov.) 153523.00 219992.20 373515.20 2008-09 (up to Nov.) -1.46 2.47 0.86 151285.00 225430.32 376715.32 16 2.7 Special campaign for recovery of arrears of electricity bills. A special campaign was launched to disconnect the premises of defaulting consumers. Under the campaign, till during 2008-09 (upto November- 08), 3.25 lacs connections were disconnected temporarily/ permanently and an amount of Rs 195.24 Crores recovered. Table 2.9 Recoveries (In Rs. Crores) 1.4.2004 to 31.3.2005 Description Arrears Recovered Nos. of disconnection UHBVN UHBVN Private Consumers 87.76 184379 DHBVN DHBVN Private Consumers 77.21 163250 Total 164.97 347629

1.3.2005 to 31.3.2005 Description Arrears Recovered Nos. of disconnection UHBVN UHBVN Private Consumers 6.82 14843 DHBVN DHBVN Private Consumers 6.18 14694 Total 13.00 29537

1.4.2005 to 31.3.2006 Description Arrears Recovered Nos. of disconnection UHBVN UHBVN Private Consumers 51.55 171325 DHBVN DHBVN Private Consumers 87.70 175941 Total 139.25 347266

1.4.2006 to 31.3.2007 Description Arrears Recovered Nos. of disconnections UHBVN UHBVN Private Consumers 68.49 206181 DHBVN DHBVN Private Consumers 115.03 275208 Total 183.52 481389

17 1.4.2007 to 31.3.2008 Description Arrears Recovered Nos. of disconnections UHBVN UHBVN Private Consumers 105.93 280816 DHBVN DHBVN Private Consumers 171.72 232624 Total 277.65 513440

1.4.2008 to 30.11.2008 Description Arrears Recovered Nos. of disconnections (Rs. Lacs) UHBVN UHBVN Private Consumers 58.00 161173 DHBVN DHBVN Private Consumers 137.24 164046 Total 195.24 325219

2.8 Settlement of the Pending Electricity Bills of Rural Domestic and Agriculture categories of consumers. Settlement of the Pending Electricity Bills of Rural Domestic and Agriculture categories of consumers. The has approved the scheme for the settlement of arrears of rural domestic & agriculture categories of consumers w.e.f. 17.06.2005. The Scheme remained in operation during 17.6.2005 to 31.7.06, and 16.10.06 to 31.12.06. The scheme was extended up to 31.3.07 w.e.f 6.2.07 in UHBVN & w.e.f. 25.1.07 in DHBVN. The scheme was extended from time to time for “dropped out” consumers upto 31.1.2008. The progress of the same in respect of UHBVN & DHBVN ending 31.12.07 is as under:- Table 2.10 UHBVN Name of Total defaulting No. of No. of consumers Amount Amount Utilities / amount frozen as on consumers who opted / freezed upto received as Category 16.6.2005 who initially completed the 31.1.08 of current bill opted the scheme upto opted / from scheme upto 31.1.2008 completed 17.6.2005 to No. Amount 31.3.2007 No. % age consumers 31.1.2008 (Rs. In (Rs. In Crore) (Rs. In Crores) Crore) Domestic 615449 854.48 380275 244900 39.79% 416.51 125.94 (Rural) Agriculture 148762 202.50 138605 97161 65.31% 174.2 96.03

Total 764211 1056.98 518880 342061 44.76% 590.71 221.97

18 Table 2.11 DHBVN Name of Total defaulting No. of No. of consumers Amount Amount Utilities / amount frozen as on consumers who opted / freezed upto received as Category 16.6.2005 who completed the 31.1.08 of current bill initially scheme upto opted / from opted the 31.1.2008 completed 17.6.2005 to No. Amount scheme No. % age consumers 31.1.2008 (Rs. In upto (Rs. In Crore) (Rs. In Crore) Crores) 31.3.2007 Domestic 518080 524.51 317830 212282 40.97% 233.14 107.27 (Rural)

Agriculture 104631 200.20 85026 64794 61.93% 174.94 58.09

Total 622711 724.71 402856 277076 44.50% 408.08 165.36

STATE Table 2.12

Name of Total defaulting No. of No. of consumers Amount Amount Utilities / amount frozen as on consumers who opted / freezed upto received as Category 16.6.2005 who completed the 31.1.08 of current bill initially scheme upto opted / from 17.6.2005 opted the 31.1.2008 completed to 31.1.2008 No. Amount scheme No. % age consumers (Rs. In Crore) (Rs. In upto (Rs. In Crore) Crores) 31.3.2007 Domestic 1133529 1378.99 698105 457182 40.33% 649.65 233.21 (Rural)

Agriculture 253393 402.7 223631 161955 63.91% 349.14 154.12

Total 1386922 1781.69 921736 619137 44.64% 998.79 387.33

The number of consumers have decreased as compared to 31.3.2007 as there are drop-out cases.

2.9 Surcharge Waiver Scheme for Domestic consumers in Urban Areas.

A Scheme was launched for waiver of surcharge of domestic consumers in urban areas

from 1.9.2007 to 31.12.2007. The scheme was applicable to domestic consumers (Connected

+ Disconnected) and was applicable to only those consumers who were defaulters as on

31.3.2007. As per the scheme, 100% surcharge amount shall be waived off in case of

19 domestic urban category on the liquidation of outstanding principal amount in lumpsum / 6

equal monthly installments. Surcharge should be waived off after the entire overdue amount of

principal is paid and provided there is no default in payment of any further current dues. The

scheme was also available to all those consumers who withdraw their cases from court before

31.12.2007, but it was not applicable to such court cases which are on account of theft of

electricity. The progress of scheme is given as under:

Table 2.13 (Amount Rs. In Crores) Name Defaulting amount as on 31.3.07 No. of consumers who opted the of utility scheme from 1.9.07 to 31.12.07 No. Principal Surcharge Total No. Principal Surcharge Amount amount waived off to be settled UHBVN 131914 80.77 18.61 99.38 3496 2.29 1.43 3.72

DHBVN 210023 307.62 55.54 363.16 5905 11.08 9.43 20.51

Total 341937 388.39 74.15 462.54 9401 13.37 10.86 24.23

The circle-wise details are given below:- Table 2.14 UHBVN (Rs. In Crores) Name of No. of Defaulting amount as on 31.3.07 No. of consumers who opted the scheme Circle urban from 1.9.07 to 31.12.07 defaulting Principal Surcharge Total No. Principal Surcharge Amount consumers (SOP + ED amount waived off to be as on + M Tax) settled 31.3.07 Ambala 8166 2.35 0.57 2.92 275 0.17 0.10 0.27

Yamunanagar 6940 2.31 0.26 2.57 508 0.28 0.14 0.42

Kurukshetra 25381 7.66 1.79 9.45 381 0.18 0.08 0.26

Karnal 18213 9.06 2.53 11.59 648 0.42 0.17 0.59

Panipat 20407 13.94 1.42 15.36 362 0.41 0.46 0.87

Sonepat 18881 12.45 2.48 14.93 166 0.10 0.06 0.16

Jind 10549 11.99 4.66 16.65 611 0.34 0.19 0.53

Rohtak 23377 21.01 4.90 25.91 545 0.39 0.23 0.62

Total 131914 80.77 18.61 99.38 3496 2.29 1.43 3.72

Table 2.15 DHBVN (Rs. In Crores) 20 Name of No. of Defaulting amount as on 31.3.07 No. of consumers who opted the scheme Circle urban from 1.9.07 to 31.12.07 defaulting Principal Surcharge Total No. Principal Surcharge Amount consumers (SOP + ED amount waived off to be as on + M Tax) settled 31.3.07 Faridabad 68420 162.52 15.61 178.13 1562 2.39 2.97 5.36

Gurgaon 35022 41.05 11.63 52.68 1017 4.42 3.90 8.32

Narnaul 20669 34.86 4.74 39.6 732 1.29 0.88 2.17

Bhiwani 26034 36.42 17.87 54.29 946 1.54 0.98 2.52

Hisar 46495 26.76 4.26 31.02 1164 1.15 0.41 1.56

Sirsa 13383 6.01 1.43 7.44 484 0.29 0.29 0.58

Total 210023 307.62 55.54 363.16 5905 11.08 9.43 20.51 2.10 Voluntary Disclosure Scheme

The Voluntary Disclosure Scheme was reintroduced w.e.f. 1.5.2005 which remained in effect up to 15.9.05. The scheme was again in operation from 16.1.06 to 15.2.06. The progress in respect of the same is as under:- UHBVN Table 2.16 (1.5.05 to 15.9.05) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 14631 30812 19.50 2. NDS 1708 7318 38.60 3. AP 40073 130891 53.14 Total 56412 169021 111.24

DHBVN Table 2.17 (1.5.05 to 15.9.05) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 16125 33505 27.47 2. NDS 1215 6117 36.24 3. AP 24615 85890 53.54 Total 41955 125512 117.25

STATE Table 2.18 (1.5.05 to 15.9.05) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 30756 64317 46.97 2. NDS 2923 13435 74.84 3. AP 64688 216781 106.68 Total 98367 294533 228.49

UHBVN Table 2.19 (16.1.06 to 21 15.2.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 72 145 0.82 2. NDS 25 135 1.75 3. AP 230 912 1.12 Total 327 1192 3.69

DHBVN Table 2.20 (16.1.06 to 15.2.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 1234 2397.084 6.54 2. NDS 128 536.508 5.95 3. AP 3257 9927.473 14.80 Total 4619 12861.065 27.29

STATE Table 2.21 (16.1.06 to 15.2.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 1306 2542.084 7.36 2. NDS 153 671.508 7.70 3. AP 3487 10839.473 15.92 Total 4946 14053.065 30.98

VDS was re-launched for the period 1.8.06 to 31.8.06 and the progress of the same in respect of UHBVN & DHBVN is as under :- UHBVN Table 2.22 (1.8.06 to 31.8.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 306 853 5.12 2. NDS 102 589 9.05 3. AP 2548 9909 20.27 Total 2956 11351 34.44

DHBVN Table 2.23 (1.8.06 to 31.8.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 810 2521.84 16.28 2. NDS 100 594.00 8.20 3. AP 1307 5034.01 8.83 Total 2217 8149.85 33.31

STATE Table 2.24 (1.8.06 to 31.8.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 1116 3374.84 21.40 2. NDS 202 1183.00 17.25

22 3. AP 3855 14943.01 29.10 Total 5173 19500.85 67.75

Voluntary Disclosure Scheme for Domestic, Non-Domestic and Agricultural Pumping supply consumers in rural and urban areas to declare their un-authorized load voluntarily has been launched from time to time, progress of which is as below:- UHBVN Table 2.25 (20.12.06 to 20.1.07) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 295 848 4.88 2. NDS 92 868 11.33 3. AP 1452 8596 13.04 Total 1839 10312 29.25

UHBVN Table 2.26 (1.11.07 to 30.11.07) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. AP 2958 11418 19.43

UHBVN Table 2.27 (1.1.08 to 31.1.08) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. AP 2927 12958.71 21.49 2. DS 577 1544.81 8.55 3. NDS 154 1167.10 17.15 Total 3658 15670.62 47.19

UHBVN Table 2.28 (2007-08) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. AP 6582 29324.47 47.36 2. DS 1264 3520.64 20.91 3. NDS 367 2590.56 42.46 4. Industrial 120 2527 22.15 Total 8333 37962.67 132.88

DHBVN Table 2.29 (20.11.06 to 31.12.06) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 986 1749.515 10 2. NDS 76 389.018 6.05 3. AP 5808 16734.717 27.61 Total 6870 18873.25 43.66

23 DHBVN Table 2.30 (19.09.07 to 31.03.08) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 3165 8424.120 54.02 2. NDS 206 1612.450 24.60 3. AP 15848 59008.520 98.77 4. Industrial 161 10435.820 52.58 Total 19380 79480.910 229.97

STATE Table 2.31 (20.12.06 to 31.03.08) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. AP 22430 88332.99 146.13 2. DS 4429 11944.76 74.93 3. NDS 573 4203.01 67.06 4. Industrial 281 12962.82 74.73 Total 27713 117443.58 362.85

UHBVN Table 2.32 (01.04.08 to 30.11.08) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (kW) (Rs. in lacs) 1. DS 3063 150463.40 47.03 2. NDS 711 4989.90 60.41 3. AP 38015 170331.60 265.45 4. Industrial 274 10282.07 109.66 Total 42063 336066.97 482.55

DHBVN Table 2.33 (01.04.08 to 30.11.08) Sr. No. Category of No. of applications Ext. of Load Amt. consumers received (KW) (Rs. in lacs) 1. DS 1741 5986.030 33.79 2. NDS 376 3365.527 24.92 3. AP 6183 32080.06 45.08 4. Industrial 169 4340.810 34.39 Total 8469 45772.427 138.18

2.11 Out of Court Settlement Scheme In order to avoid prolonged litigation and to settle long pending court cases, a scheme called Out of court Settlement Scheme has been introduced in respect of various categories of consumers where disputes are pending in Courts/Arbitration. The scheme remained in operation from 20.11.05 to 15.12.05, 16.01.06 to 15.02.06. The scheme was again in operation for 18.01.08 to 31.03.08. The progress in respect of the same is as under:-

24 Table 2.34 (Rs. In Lacs) Utility Period No. of cases Amount Amount deposited settled Involved with the Nigam

UHBVN 20.11.05 to 15.12.05 251 587.24 126.71 16.1.06 to 15.2.06 49 38.97 16.23 Total 300 626.21 142.94

DHBVN 20.11.05 to 15.12.05 332 591.26 117.45 16.1.06 to 15.2.06 246 502.75 130.04 Total 578 1094.01 247.49

Table 2.35 (Rs. In Lacs) Utility Period No. of cases Amount Amount deposited settled Involved with the Nigam

UHBVN 18.01.08 to 31.07.08 54 179.90 32.15

DHBVN 26.06.08 to 31.07.08 14 9.77 3.06 Total 68 189.67 35.21

2.12 Checking of Power Thefts In order to curb the incidence of theft of electricity, special campaign was launched and checking of consumer premises was intensified. Simultaneously, the connected load of consumers was checked so that proper bill could be issued to the consumer. Sealing of consumer meters had also been taken up in a big way so that the tempering of meters could be prevented. Meters are now being installed in steel meter cupboards so as to prevent unscrupulous consumers to tamper with the meters. The progress achieved in checking of theft cases and levy of penalty amount has been as follows:- Table 2.36 Period Utility Number of Theft Penalty Penalty %age premises cases imposed recovered Realized checked detected (Rs. in lac) (Rs. in Lac)

2004-05 UHBVN 99542 12524 1186.04 410.66 34.62 DHBVN 103104 8442 1566.09 553.41 35.34 Total 202646 20966 2752.13 964.07 35.03 March-05 UHBVN 8437 893 115.00 30.48 26.50 DHBVN 8557 534 153.54 38.17 24.86 Total 16994 1427 268.54 68.65 25.56 2005-06 UHBVN 133819 15478 1894.73 783.36 41.34 DHBVN 167951 34689 3630.16 1612.47 44.42 Total 301770 50167 5524.89 2395.83 43.64 2006-07 UHBVN 233384 20993 2169.78 1095.90 50.51

25 DHBVN 149799 24596 2565.26 1006.92 39.25 Total 383183 45589 4735.04 2102.82 44.41 2007-08 UHBVN 136970 13538 1669.09 873.38 52.33 DHBVN 125741 20700 3438.44 1470.86 42.78 Total 262711 34238 5107.53 2344.24 45.90 2008-09 UHBVN 65122 5922 1007.45 480.67 47.71 (upto DHBVN November- 83956 14880 3331.69 1221.16 36.65 08) Total 149078 20802 4339.14 1701.83 39.22

2.13 Release of Tubewell Connections under various Tatkal Schemes:-

The various ‘Tatkal’ Schemes for release of tubewell connections were announced from time to time which includes providing cable connection, single pole connection and own your transformer. Lot of consumers came forward and number of connection year-wise under these schemes and under general category is given as under. The tubewell connections are now being released under General category scheme only. Under the scheme applicants have to deposit Rs. 20,000/- along with the consent and the balance has to be deposited @ Rs. 7,000/- per span. The scheme has been extended in UHBVN to the applicants who have applied upto 31.3.07:- Table 2.37 Year UHBVN DHBVN Total

2004-2005 6698 6507 13205 March-05 514 527 1041 2005-2006 5397 6556 11953 2006-2007 7352 8915 16267 2007-08 11995 11968 23963 2008-09 (upto November-08) 2190 6985 9175

Another 61 no. connection released under Self Executive Scheme in UHBVN. The details of pendency of the release of tube well connections is placed below:-

26 Pendency of the release of tubewell connections (Upto November 08)

Table 2.38 Name of Age wise Pendency Date of Oldest Circle Upto 3 3 to 6 6 month to 1 1 to 2 year 2 to 3 More than 3 yrs Total Pendency Months old months old year old old year old old Pendency Ambala 47 141 432 83 3 0 706 20.06.06 Karnal 328 536 845 367 179 0 2255 08.06.06 Panipat 798 146 48 81 0 0 1073 01.08.05 KKTRA 37 130 293 256 4 0 720 01.08.06 Y/Nagar 285 379 667 984 3 1 2319 15.05.06 Sonipat 809 298 241 252 2 1 1603 25.07.06 Jind 578 1592 471 297 0 0 2938 21.02.07 Rohtak 151 185 25 7 0 0 368 05.12.06 Jhajjar 75 58 95 105 0 1 334 22.07.05 Kaithal 642 509 754 137 0 7 2049 01.08.06 Total 3750 3974 3871 2569 191 10 14365 UHBVN Faridabad 220 411 207 68 2 0 908 05.10.06 Gurgaon 255 250 175 67 0 1 748 18.09.03 Narnaul 450 198 282 148 119 1 1198 20.01.04 Bhiwani 347 440 442 20 0 1 1250 28.01.03 Hisar 711 405 297 143 0 0 1556 21.04.05 Sirsa 3060 758 636 0 0 0 4454 09.02.08 Total 5043 2462 2039 446 121 3 10114 DHBVN Total 8793 6436 5910 3015 312 13 28930 (UHBVN + DHBVN)

27 2.14 100% Metering in Power Utility Table 2.39 Name of Installation of Single- Installation of Period power Phase Electronic meters Three-Phase utilities Electronic meters March-05 UHBVN 4739 192 DHBVN 7994 2246 Total 12733 2438 2005-2006 UHBVN 26148 1719 DHBVN 69913 11883 Total 96061 13602 2006-2007 UHBVN 12275 5166 DHBVN 72655 8304 Total 84930 13470 2007-2008 UHBVN 30339 7662 DHBVN 132691 6554 Total 163030 14216 2008-09 (upto UHBVN 2101 165 Oct.-08) DHBVN 6978 14360 Total 9079 14525

2.15 Rehabilitation of 11KV overloaded feeders during 2005-06, 2006-07, 2007-08 and 2008-09 Table 2.40 (Ending November-08) Name Period No. of 11 KV feeders Total no. of 11 KV Work in Hand of to be Bifurcated/ feeders Bifurcated/ Power Trifurcated during Trifurcated during Utilities the year the year Before After Before After Before After UHBVN 2005-06 44 106 36 97 11 KV feeders pending for bifurcation / trifurcation included in the targets for 2008-09 2006-07 111 224 63 118 48 106 2007-08 65 139 32 66 33 73 2008-09 66 138 5 10 61 128 (upto Nov.-08 DHBVN 2005-06 16 42 16 42 0 0 2006-07 48 96 48 96 0 0 2007-08 100 200 61 132 39 68 2008-09 139 278 52 104 17 34 (upto Nov.- 08) STATE 2005-06 60 148 52 139 0 0 2006-07 159 320 111 214 48 106 2007-08 165 339 93 198 72 141 2008-09 205 416 57 114 78 162 (upto 11/2008)

28 2.16 Reduction in damage rate of distribution transformers of UHBVN & DHBVN. The damage rate of distribution transformers for the year 2007-08 is 9.9% whereas it was 30.45% in the year 1997-98. Thus, there is a reduction of 20.55 % during the last nine years. Preventive maintenance and inspections have helped to achieve this reduction rate besides considerable saving of expenses on repair of transformers. Table 2.41 (ending November. 08) Year Population of T/F damaged excluding % damaged % transformer those damaged within damage warranty period and of both damage due to wind Utilities storm/ natural calamities UHBVN DHBVN UHBVN DHBVN UHBVN DHBVN

2004-05 82532 63926 12690 9783 15.51 15.30 15.34 2005-06 86706 68698 11847 9563 13.66 13.92 13.78 2005-06 86706 68698 11847 9563 13.66 13.92 13.78 2006-07 95429 76333 11829 9033 12.39 11.83 12.15 2007-08 108837 89495 11466 8177 10.54 9.14 9.90 2008-09 113291 99762 15673 7397 9.73 7.41 10.83 (upto 11/2008)

2.17 Details of distribution transformers added in the System. Table 2.42 (Ending November- 08) Name Nos. of Nos. of Nos. of Nos. of Nos. of Nos. of of distribution distribution distribution distribution distribution distribution Power T/F added T/F added T/F added T/F added T/F added T/F added Utilities during during during during during during 2004-05 March-05 2005-06 2006-07 2007-08 2008-09 ( Upto 11/08 )

UHBVN 6898 716 4174 8723 13408 4454 DHBVN 5414 419 4772 7635 13162 10267 Total 12312 1135 8946 16358 26570 14721

2.18 Detail of achievements in respect of New / Augmentation works of 33KV Sub/Stns Table 2.43 (ending December 08) Year UHBVN DHBVN State New Augmentation New Augmentation New Augmentation Works Works Works 2004-05 15 19 7 15 22 34 2005-06 10 35 4 20 14 55

29 2006-07 7 13 5 9 12 22 2007-08 21 19 15 14 36 33

2008-09 9 7 18 25 27 32 (upto Dec-08)

2.19 Progress regarding New/ augmentation of 33KV lines (In Kms.) Table 2.44 (ending December-08) Name of Power 2004-05 2005-06 2006-07 2007-08 2008-09 Utilities (Upto Dec-08) UHBVN 159.35 79.15 52.94 128.473 88.60 DHBVN 100.20 50.50 36.87 146.41 129.75 Total 259.55 129.65 89.81 274.883 218.35

2.20 Circle wise Distribution losses & AT&C Losses 2008-09 (upto November-08) Table 2.45 Name of Circle Distribution Loss % AT&C Loss % UHBVNL Kurukshetra 18.23 20.15 Yamunanagar 19.84 22.68 Ambala 24.22 26.97 Karnal 20.08 25.74 Kaithal 20.20 34.32 Rohtak 47.54 60.84 Sonipat 27.39 31.81 Jind 40.40 71.16 Panipat 28.43 32.41 Jhajjar 35.12 46.63 UHBVN as a whole (2008-09 26.74 35.45 upto November-08) 2005-06 30.80 42.41 2006-07 28.72 39.02 2007-08 27.87 33.84 2008-09 (up to November-08) 26.74 34.45 DHBVN Faridabad 20.53 24.90 Gurgaon 18.53 19.25 Narnaul 20.75 40.09

30 Bhiwani 31.35 55.63 Hisar 24.79 33.08 Sirsa 21.75 24.12 DHBVN as a whole 21.94 28.86 (2008-09 upto November-08) 2005-06 30.90 40.32 2006-07 29.65 37.49

2007-08 26.50 30.17

These figures are as per commercial data. 2.21 STATUS OF AT&C LOSSES (as per Balance Sheet) Table 2.46

Year UHBVN DHBVN UHBVN+DHBVN AT&C AT&C AT&C Distribution Distribution Distribution Losses Losses Losses Losses (%) Losses (%) Losses (%) (%) (%) (%) 2001-02 35.70 42.65 33.90 39.06 34.79 45.14 2002-03 35.00 38.70 35.00 38.02 35.01 41.85 2003-04 32.40 40.48 33.30 36.99 32.83 41.42 2004-05 30.70 42.37 32.70 36.86 31.67 42.42 2005-06 31.00 42.22 30.90 34.58 30.97 40.65 2006-07 28.70 37.38 29.60 32.48 29.15 37.67 2007-08 28.50 33.23 26.50 25.52 27.50 32.37 2008-09* 26.74 35.45 21.94 28.86 24.42 35.23 (up to Nov.-08)

* Un-audited figures

2.22 Recovery against Land Revenue Act Recovery of Defaulting amount against Land Recovery Act-1970 in respect of UHBVN &. DHBVN is as under:- Table 2.47 (ending October-08) Name of No. of cases forwarded Amount due No. of cases Amount recovered Power Utility to revenue department (Rs. In Lacs) settled (Rs. In Lacs) UHBVN 1003 271.64 179 15.35

DHBVN 4665 1641.62 532 158.06

Total 5668 1913.26 711 173.41

31 2.23 DEFAULTING AMOUNT (Rs in Crores) Table 2.48 (ending October 2008) Category UHBVN DHBVN

Connected Disconnected Total Connected Disconnected Total

Domestic 70.92 61.79 132.71 105.01 97.64 202.65 Urban Domestic 775.37 246.97 1022.34 435.11 184.22 619.33 Rural Non- 75.58 37.39 112.97 72.38 48.62 121.0 Domestic Industrial 77.69 42.01 119.7 58.43 49.82 108.25 Agriculture 73.57 14.56 88.13 33.49 16.17 49.66 Govt. 68.05 2.78 70.83 322.91 8.73 331.64 Department Total 1141.18 405.50 1546.68 1027.33 405.2 1432.53

2.24 Other Major achievements of the Discoms. • During the current FY 2008-09, 23604 energy meters have been replaced up to 10/2008 (UH). Meter cup- boards on the existing meters are being installed to prevent chances of theft of energy. • For the convenience of consumers for deposit of their bills, cash collection facilities have been extended to 55 branches of different banks, i.e. Central Bank of , Vijaya Bank, Bank of Punjab, ICICI Bank, Syndicate Bank, State Bank of Patiala. Outsourcing of activities like bill distribution and meter reading is being tried on experimental basis. • For the convenience of public, Complaint Centres namely BSKs have been set up at all the district headquarters. With these systems the consumers would be able to lodge their power supply complaints round the clock and it would be possible to monitor the time taken by the complaint staff in attending to the consumer complaints. • With a view to redress public grievances relating to electricity supply, Bijli Sabhas are being held at the district level. Any consumer having any grievance relating to power supply can get it redressed on the spot. Simultaneously, Consumer Advisory Committees have been set up to have a constant liaison with the consumer groups/ industries associations. It has been decided that Bijli Sabha would be held on 4th & 6th day of the every month from Oct. 04 onwards. The details of the Bijli Sabhas, which have been held during 2007-08 & 2008-09 (upto November-08) are given as under:- 32 Table 2.49 Name of No. of Bijli No. of complaints/ No. of complaints/ Power Utility Sabhas grievances grievances attended organized received on the spot UHBVN 2007-08 138 2038 1357 2008-09 72 1213 584 (up to Nov-08) DHBVN 2007-08 364 7129 6152 2008-09 548 4024 3209 (Upto Nov./08) STATE 2008-09 620 5237 3793 (upto Nov.-08)

2.25 RAJIV GANDHI GRAMEEN VIDYUTIKARAN YOJNA (RGGVY) SCHEME FOR RURAL ELECTRICITY INFRASTRUCTURE AND RURAL HOUSEHOLDS ELECTRIFICATION.

‘Rajiv Gandhi Grameen Vidyutikaran Yojna’ (RGGVY) Schemes was launched by Govt. of India through Rural Electrification Corp. Ltd. in April, 2005. Under this scheme 90% capital subsidy would be provided for overall cost of the Project. The agreement for implementation of the Project in Haryana was signed on 9th July 2005 between Rural Electrification Corp. Ltd., Govt. of Haryana and two Distribution Nigams of Haryana namely Uttar Haryana Bijli Vitran Nigam and Dakshin Haryana Bijli Nigam in the presence of the then Hon’ble Sh. P.M. Sayeed Power Minister Govt. of India and Hon’ble Chief Minister Haryana Sh. . These schemes are aimed at providing electricity to the below poverty line households and creating electricity infrastructure in rural areas.

Presently the scheme is being implemented in Haryana as per the details given below:- UHBVN Table 2.50 Name of BPL connections Cost of the scheme BPL Connections District to be released (Rs. In Crore) released upto 31.12.2008 Sonipat 22647 16.88 2120 Panipat 6501 9.51 2648 Karnal 15861 16.54 5199 Rohtak 4189 5.55 3005 Ambala 8777 6.38 328 Kurukshetra 6898 8.81 648 Nagar 1869 7.83 755

33 Jind 31146 13.31 953 Jhajjar 4452 6.24 601 Kaithal 7194 9.89 1597 Panchkula 625 3.41 0 Total 110159 104.35 17854 With the implementation of above schemes, 110159 domestic connections to BPL household will be released in UHBVN.

DHBVN Table 2.51 SANCTIONED SCHEMES Name of district BPL connections Cost of the scheme Connections released to be released (Rs. In crores) upto 31.12.2008 Sirsa 22118 14.76 No connections Bhiwani 21632 16.72 released so far. Fatehabad 8304 8.70 Hisar 24845 13.26 Mohindergarh 5007 12.42 Rewari 14073 11.09 Mewat 17935 16.09 Sub Total 113914 93.04 UNSANCTIONED SCHEMES Name of district BPL connections Cost of the scheme Remarks to be released (Rs. In crores) Faridabad 9558 15.74 Schemes has been Gurgaon 3282 9.68 sent to REC for approval. Sub Total 12840 25.42

¾ The work for Sirsa and Bhiwani districts has been awarded on 17.4.08. ¾ The work for Hisar, Mohinderegarh & has been awarded on 30.10.08, 30.10.08 & 3.11.08 respectively. ¾ The work for Fatehbad and Mewat districts have been finalized and LOA is being issued. ¾ Work of 604 No. Dhanis has been allotted in . ¾ Scheme for Faridabad & has been sent to REC for approval. With the implementation of above schemes, 126754 domestic connections to BPL household will be released in DHBVN.

With the implementation of above schemes, 236913 domestic connections to BPL households will be released at a cost of Rs.222.81 crore in the State as a whole.

34

2.26 Segregation of agriculture load from rural domestic load. The work of segregation of 11 kV rural feeders to segregate agricultural load from rural domestic load has been undertaken for improvement of power supply to rural sector. The progress of segregation of feeders is given below:-

Table 2.52 Name of Total No. Total No. of No. of No. of No. of Utility of 11KV 11KV feeders feeders yet feeders feeders to feeders for commission to be where work be erected which work ed commission in progress completed ed UHBVNL 691 382 382 0 309

DHBVNL 539 268 79 189 271 Total 1230 650 461 189 580

The circle wise details is given below:-

35 Table 2.53 Progress of segregation of rural domestic & agriculture load under UHBVN upto 31.12.2008

Sr. Name of Total No. of Total No. of No. of No. of feeders No. of feeders Likely date of No. Circle 11KV 11KV feeders feeders yet to be where work in completion of feeders to for which commissio commissioned progress work be erected work ned completed 1 Rohtak 33 22 22 0 11 15.02.2009

2 Jhajjar 45 18 18 0 27 15.02.2009

3 Sonipat 73 12 12 0 61 15.02.2009

4 Jind 73 63 63 0 10 15.02.2009

5 Panipat 46 3 3 0 43 15.02.2009

6 Ambala 63 51 51 0 12 15.02.2009

7 Kurukshetra 87 67 67 0 20 15.02.2009

8 Kaithal 69 56 56 0 13 15.02.2009

9 Yamuna 84 48 48 0 36 15.02.2009 Nagar 10 Karnal 118 42 42 0 76 15.02.2009

TOTAL 691 382 382 0 309

36

Table 2.54 Progress of segregation of rural domestic & agriculture load under DHBVN upto 31.12.2008

Total No. of No. of No. of Total No. of No. of 11KV feeders yet feeders Likely date of Name of 11KV feeders Sr.N feeders for to be where completion of Circle feeders to commission o. which work commission work in work be erected ed completed ed progress 1 Hisar 132 74 38 58 30.06.09 36 2 Sirsa 83 60 22 23 30.06.09 38 3 Faridabad 55 38 2 17 30.06.09 36 4 Gurgaon 66 36 7 30 30.06.09 29 5 Narnaul 131 31 7 100 30.06.09 24 6 Bhiwani 72 29 3 43 30.06.09 26 Total 539 268 79 189 271

37 2.27 APDRP Scheme

The APDRP scheme was launched by the Ministry of Power for strengthening of the distribution network in selected towns so as to achieve the following objectives:-

• To reduce the distribution losses • To improve the voltage regulation • To promote/encourage energy accounting • To provide better services to the consumers of the DISCOMs

The gist of activities/provisions of the APDRP Schemes 2002-03 for achieving the above objectives include the following:-

• Installation of energy meters to account for energy sold • Bi-furcation/Tri-furcation of overloaded feeders and installations of capacitors for improved voltage regaulations and reduction of losses • DT-metering for energy accounting • New 33 KV & augmentation of existing 33 KV substations and lines for better infrastructure, etc.

The funding pattern of the scheme is as under:-

I) Grant from Government of India 25 % of the cost of the project II) Arrangements of funds through loan/internal 75 % of the cost of the project accruals

As on 31.12.08, amounts of Rs.148.71 Crores & Rs.195.90 Crores have been utilized by the two Nigams (UHBVN & DHBVN respectively) under the scheme.

The status of the APDRP scheme up to 31.12.2008 is as under:-

38

Status of APDRP Schemes As on 31.12.2008

Table 2.55

(Rs. in Crore) UHBVNL DHBVNL Total (UH+DH) Circle/Town APDRP Utilization Circle/ APDRP Utilization APDRP Utilization Releases Town Releases Releases 54.72 43.52 Karnal Circle Hisar 76.04 67.68 173.83 147.71 43.07 36.51 Sonepat Circle 27.57 24.19 Faridabad 118.03 90.78 145.60 114.97 Ambala Town 15.47 9.51 Sirsa 9.91 14.58 25.38 24.09 Yamuna Nagar & 12.02 7.44 Fatehabad 5.49 0.70 17.51 8.14 Jagadhari Town 7.7 6.34 Tohana 5.76 3.33 13.46 9.67 Town Kaithal Town 3.39 1.72 Hisar-II 7.38 1.31 10.77 3.03 Rohtak Town 16.8 9.65 Hansi 1.72 1.72 18.52 11.37 10.35 6.77 Bhiwani 7.45 7.60 17.80 14.37 Town Gohana Town 2.75 3.06 Rewari 6.34 8.20 9.09 11.26 Total 193.84 148.71 238.12 195.90 431.96 344.61 SUMMARY (Rs. in Crore) Total APDRP releases 431.96 Expenditure upto 30.6.2008 344.61 Unutilized amount 87.35

39 Table 2.56 STATEMENT SHOWING THE RELEASE OF APDRP LOAN/GRANT UPTO 31.12.2008 APDRP LOANS Rs. In Crores Name of 2001-02 2002-03 2003-04 2004-05 2005-06 TOTAL the Company

GRANT LOAN TOTAL GRANT LOAN TOTAL GRANT LOAN TOTAL GRANT LOAN TOTAL GRANT LOAN TOTAL GRANT LOAN

HPGCL 5.93 5.93 11.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.93 5.93

UHBVN 6.83 6.83 13.66 8.02 8.02 16.04 23.9512 29.3196 53.271 23.141 22.921 46.063 4.61601 0.00000 4.62 66.56 67.09

DHBVN 12.06 12.06 24.11 10.62 10.62 21.24 29.5489 36.5355 66.084 26.649 26.399 53.047 14.1190 0.0000 14.12 92.99 85.61

HVPN 0.00 0.00 0.00 0.00 0.00 0.00 0.000 0.000 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL 'A' 24.81 24.81 49.62 18.64 18.64 37.28 53.500 65.855 119.355 49.790 49.320 99.110 18.7350 0.0000 18.7350 165.47 158.62 Note : The above figures include incentive with detail as under

Incentives UHBVN DHBVN Tolta FY 2003- 04 2.148 2.862 5.01 FY 2004- 05 43.08 57.4 100.48 Note2 : No funds have been released during FY 2006-07 and FY 2007-08

40 2.28 WS&S Connections (Public Health)

As on 31.12.2008, 1815 no. applications have been received from WS&S

(Public Health) Department, out of which 1007 no. connections stand released , work on 327

no. applications is in progress and 481 no. applications are lying pending. Out of the 481

nos. pending applications, 343 no. applications are lying pending with the Nigams and 138

no. applications are such where the WS&S authorities have yet to complete formalities. The

yearwise release of Public Health connections of the Nigams is as below:-

Year Utility UHBVN DHBVN 2005-06 387 538 2006-07 675 685 2007-08 638 598 2008-09 (December-08) 554 453 Total 2254 2274

41 3. FINANCIAL POSITION OF HARYANA POWER UTILITIES

3.1 The profitability results of Haryana Power Utilities for the last seven years and for Financial Year 2007-08 are as under: - Table 3.1 Rs. in Crore Particulars 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 Total 2684.30 3654.66 4215.74 4952.53 5121.47 5547.69 5575.74 6369.50 7879.80 Incomes Total 3317.12 3859.88 4099.81 4926.41 4881.84 5957.49 6007.47 6790.39 8506.27 Expenses Net Profit (632.82) (205.22) 115.93 26.12 230.03 (409.80) (432.53) (420.89) (626.47) (losses) Note: The Accounts of Haryana Power Utilities are prepared on mercantile/accrual basis. Therefore, the incomes as above do not represent cash realized and similarly the expenses as above do not represent cash payments.

From the above, it may please be seen that losses suffered by Haryana Power Utilities were Rs 632.82 crore in Financial Year 1999-2000, which reduced to Rs 205.22 crore in Financial Year 2000-2001. This was primarily because of increase in RE Subsidy provided by Government of Haryana from Rs 412 crore in Financial Year 1999-2000 to Rs 769.30 crore in Financial Year 2000-2001. Haryana Power Utilities earned profits of Rs 115.93 crore in Financial Year 2001-2002 as the tariffs were increased by 11.30% with effect from 1.1.2001. Haryana Power Utilities had been able to achieve record profits of Rs 239.63 crore in Financial Year 2003-2004 partly because of refunds of Rs 355 crore relating to prior periods received from NTPC towards downward revision in tariffs of Faridabad Gas Power Plant with effect from 2000-2001 and onwards. Besides this, Haryana Power Utilities received an incentive of Rs 105.49 crore in Financial Year 2003-04 from Ministry of Power, Government of India towards reduction in cash losses. The main reason for loss in 2004-05 is non-increase of tariff of retail consumers by HERC. The main reason for loss in 2004-05, 2005-06, 2006-07 & 2007-08 is non-increase of tariff of retail consumers by HERC and disallowance of expenditure by HERC.

3.2 RE Subsidy The above profits of the Haryana Power Utilities have been worked out after taking into account the RE subsidy provided/to be provided by the State Government, which is as under: -

42 Table 3.2 Rs. in Crore Year Amount of RE Subsidy

1999-2000 412.00 2000-2001 769.30 2001-2002 763.54 2002-2003 829.10 2003-2004 923.88 2004-2005 1102.00 2005-2006 1302.39 2006-2007 1544.37 2007-08 2371.42 2008-09 (Proposed in revised BE) 2898.11

3.3 T&D LOSSES The quantum of power available, power sold and T&D losses during the last seven years are as under: - Table 3.3 (Figures in MUs) Particulars 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 upto 11/08 Total power available 17847.42 19434.14 20498.88 21460.01 23243.77 25125.35 25688.83 18569 (Mus) Direct Sale (Mus) 66.22 130.31 387.36 296.63 140.06

Net Power Available 17847.42 19434.14 20498.88 21393.79 23113.46 24737.99 25392.2 18428.94 (Mus) Power sold to 16567.05 18331.71 19551.04 20269.62 22092.37 23536.31 24184.97 17563.62 Discoms (Mus) Transmission Losses 1280.37 1102.43 947.84 1124.17 1021.09 1201.68 1207.23 865.32 (MUs) Trans. Losses (in%) 7.17% 5.67% 4.62% 5.24% 4.39% 4.78% 4.70% 4.66%

Power sold to 10803.37 11913.78 13132.43 13850.23 15250.36 16675.48 17534.10 13275.11 consumers (Mus) Distribution Losses ( 5763.68 6417.93 6418.61 6419.39 6842.01 6860.83 6650.87 4288.51 MUs) Distribution losses 34.79% 35.01% 32.83% 31.67% 30.97% 29.15% 27.50% 24.42% (%) T&D Losses (%) 39.47% 38.70% 35.94% 35.26% 34.02% 32.59% 30.95% 27.96 %

Collection efficiency 93.89 96.66 94.25 92.44 93.06 94.66 98.51 89.91 (%) Units not collected 1012.25 612.28 1124.18 1532.38 1533.21 1256.84 360.36 1339.18 MUs) Units realized (in 9791.13 11301.50 12008.25 12317.85 13717.15 15418.64 17173.75 11935.93 MUs) Total Units lost (T, D 8056.29 8132.64 8490.63 9075.94 9396.31 9319.35 8218.45 6493.01 & UR) (in MUs) AT&C Losses (%) 45.14% 41.85% 41.42% 42.42% 40.65% 37.67% 32.37% 35.23%

43 3.4 Revenue Vs Cost per unit of power sold Revenue per unit and cost per unit of power sold of Haryana Power Utilities for the last ten years is as under: Table 3.4 (Figures in paise per unit) Particulars 1998-99 1999-00 2000- 01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 Unit Sold (MU) 9290 9930.94 10395.26 10891.70 12004.98 13387.68 14161.50 15188.06 16910.14 17294.64 Revenue per 203.10 200.13 246.88 258.93 344.53 252.75 249.52 266.26 260.58 294.92 unit Other income 20.63 34.13 31.96 54.60 56.11 72.06 39.14 4.11 20.68 17.67 per unit Subsidy & 39.18 41.49 74.00 70.10 69.06 69.01 77.83 84.90 91.32 131.62 grants per unit FSA 0.00 0.00 0.00 19.22 34.56 -8.33 25.23 54.81 43.11 0.00 Total 262.91 275.75 352.85 402.85 413.59 385.48 391.72 410.08 415.69 441.21 Revenue/unit Cost of power 285.70 339.47 372.59 392.20 411.42 367.58 420.68 442.67 441.13 479.81 sold per unit Profit/(Loss) (32.79) (63.72) (19.74) 10.64 2.18 17.90 (28.96) (32.59) (25.44) (38.60) per unit Revenue/cost 89% 81% 95% 103% 101% 105% 93% 93% 94 % 91.95% %

Revenue per unit includes average tariff of Rs 253 paise per unit and the remaining amount is on account of other incomes. The decline in the revenue per unit in Financial Year 2003- 04 is because of decline in the revenue on account of Fuel Surcharge Adjustment. The decline in the cost of power sold in Financial Year 2003-2004 was because of (a) decline in power purchase cost from Rs 1.86 per unit in 2002-03 to Rs 1.75 per unit in Financial Year 2003-04 (b) decline in the T&D losses from 38.70% in Financial Year 2002-03 to 35.94% in Financial Year 2003-04. 3.5 CAPITAL EXPENDITURE The capital expenditure incurred by the Haryana Power Utilities since 1999-2000 is as under: - Table 3.5

Year Transmission Distribution Generation Total 1999-2000 138.51 52.97 351.17 542.65 2000-2001 163.78 132.26 214.15 510.19 2001-2002 107.92 218.04 170.49 496.45 2002-2003 229.18 210.50 287.67 727.35 2003-2004 206.80 228.13 1005.05 1439.98 2004-2005 254.07 213.80 453.36 921.23 2005-2006 196.00 208.48 437.09 841.57 2006-2007 310.63 804.49 1484.39 2599.51 2007-08 (Provisional) 541.00 1390.59 1725.83 3657.42 2008-09 (Proposed) 997.00 1579.18 2951.13 5527.31 Total 3144.89 5038.44 9080.33 17263.66

44 3.6 EQUITY CAPITAL

The equity capital provided by the State Government to the Haryana Power Utilities for the last seven years is as under: - Table 3.6 Rs. in Crore Year Amount 1999-2000 350.00 2000-2001 265.00 2001-2002 10.00 2002-2003 133.67 2003-2004 162.64 2004-2005 233.35 2005-2006 275.44 2006-2007 785.80 2007-2008 * 848.90 2008-2009 (Budgeted) * 855.70 * Rs.65 crore in 2007-08 and Rs.80 in 2008-09 will be paid extra by GoH through Haryana Financial Corporation.

3.7 RECEIVABLES

The Haryana Power utilities are facing cash crunch because of the stupendous rise in the receivables from the consumers. The total receivables from the consumers since 1999- 2000 are as under: - Table 3.7 Rs. in Crore Year (as on 31st March) Amount 2000 1134.32 2001 1329.74 2002 1612.66 2003 1785.79 2004 2228.03 2005 3091.18 2006 3520.48 2007** 2974.16 2008** 2293.22 ** Reduction in receivables is due to writing off the surcharge as per settlement scheme of the pending electricity bills of Rural Domestic and Agriculture categories of consumers

45

3.8 LOANS Because of the non-realization of the dues from the consumers, the Haryana Power Utilities had to borrow funds for meeting its working capital requirement. The loans were also borrowed for meeting the capital expenditure requirement. The total loans held by the Haryana Power Utilities during the last five years and projected as on 31st March 2008 are as under: - Table 3.8 Rs. in Crore Year (As on 31st March) Amount 2000 3591.95 2001 4975.46 2002 5248.74 2003 5857.95 2004 6416.83 2005 7476.42 2006 7980.24 2007 9979.70 2008 12382.22

46 3.9 HARYANA POWER SECTOR - SUMMARY OF PROPOSED 11TH FIVE YEAR PLAN INVESTMENTS Table 3.9 PROJECTS/SCHEMES Amount (Rs. Crore) A) Generation State Plan Others Total a) New Generation Projects 2222.18 8391.58 10613.76 b) Renovation & Modernization i) Refurbishment of PTPS Unit-1, 3 to 5 123.40 518.00 641.40 ii) Raising of Ash Dyke Panipat 0.00 12.00 12.00 iii) R&M Schemes Faridabad 0.30 0.00 0.30 iv) R&M Hydel Power Houses 25.00 60.05 85.05 c) Other Works 0.00 14.50 14.50 Total Generation (A) 2370.88 8996.13 11367.01 B) Transmission a) New Sub Stations i) 400 KV (6 Nos) 138.90 1361.10 1500.00 ii) 220 KV (40 Nos) 424.12 2267.88 2692.00 iii) 132 KV (51 Nos) 281.09 1179.91 1461.00 iv) 66 KV (49 Nos) 277.80 1222.20 1500.00 b) Augmentations of Existing Sub Stations 46.30 243.70 290.00 c) SLDC 37.04 162.96 200.00 Total Transmission (B) 1205.25 6437.75 7643.00 C) Distribution 1 New 33 KV S/Stn(291Nos)., Aug. of 33 KV S/Stn(190Nos)., New 33 KV Lines(2650Kms) and HT capacitors(1360.80 Mvar) 162.41 664.35 826.76 2 Bi/Trifurcation of 11 KV Feeders(1900Nos), Aug. and addition of new DTs(89650Nos) alongwith 11 KV and LT Lines, Strengthening of Dist. System under RGGVY, AB cables. 507.28 1409.14 1916.42 3 Segregation of Rural domestic load from rural agriculture load(1913 feeders) 87.18 504.68 591.86 4 Providing HVDS/LVDS(4990villages) 163.50 700.65 864.15 5 Providing Area Load Despatch Centre 17.45 68.07 85.52 6 Consumers metering, DT metering, feeders metering, prepaid metering 61.60 304.42 366.02 7 Demand side management activities 291.39 1089.62 1381.01 8 NABARD Works 5.00 0.00 5.00 9 APDRP Works 20.73 0.00 20.73 10 Providing Distribution Automation system by providing RMUs, Aytoreclosers/ sectionlisers on 11 KV lines, providing connectors on 33 KV/11 KV/LT 23.62 136.57 160.19 11 Providing Network Energy Management system by providing High definition advanced technology metering in urban areas 22.15 174.82 196.97 12 Providing 33/0, 433 KV system 3.69 5.00 8.69 13 Customer care centre 0.00 4.00 4.00 14 Packaged sub station (11 KV) 0.00 3.00 3.00 15 Civil Works cost of land, construction of offices & residences in UHBVNL 0.00 34.00 34.00 16 Other-Cost of material for execution of works under various schemes mentioned above and other Misc. Capital Works to be done departmentally. 0.00 50.00 50.00 Total Distribution (C) 1366.00 5148.32 6514.32 Grand Total (A+B+C) 4942.13 20582.20 25524.33

47 3.10 ANNUAL REVENUE REQUIREMENT APPROVED BY HERC

For Transmission & Bulk Supply:

The volume of power purchase, the cost and the BST tariff approved by the HERC for the year 2002-03 to 2005-06 is as under:- Table 3.10 Year Power HERC Tariff for Bulk Aggregate purchase approved Supply to Revenue volume cost for Distribution & Requirement of approved by purchase of Retail Supply HVPNL (in HERC (MU) power (in Business (in Million Rs.) Million Rs.) Rs.) 2002-03 16821.26 27144.67 1.478 per unit 29054.84 96.964 per KW 2003-04 19050.00 34044.10 1.517 per unit 34783.58 113.99 per KW 2004-05 21208.48 39426.87 1.743 per unit 41509.49 93.303 per KW 2005-06 21249.00 40109.43 1.754 per unit 42315.24 96.961 per KW

Separate orders have been issued by HERC from FY 2006-07 onwards for transmission tariff, bulk tariff & SLDC charges. Table 3.11 Transmission tariff

2006-07 23863.20 52163.60 122.851 per kW 5116.97 per month 2007-08 26372 59977 120.85 per kW 5434.37 per month 2008-09 28431.08 114.13 per kW 5453.76 per month SLDC charges

2006-07 6.904 million per 82.85 month 2007-08 7.91 million per 94.909 month 2008-09 6.515 million per 78.18 month Bulk Supply Tariff

2006-07 23863.20 52163.60 2.194 per unit 52365.07

2007-08 26372 59977 2.40 per unit 60514.65

48 3.11 Funding of power projects through NABARD

National bank for agriculture and Rural development launched RURAL Infrastructure Development Fund (RIDF) for funding of various projects which strengthen the rural and agriculture sector. The fund is created under different RIDF trenches. Transmission and Distribution projects of power Sector were eligible for funding under this window under RIDF-VI to RIDF-IX. This window has been closed for power sector since RIDF-X. The funding from NABARD is at subsidized interest rate of 6.5 % p.a. An attempt was made by raising the issue through Hon’ble CM, Haryana with the Finance Minster, Govt. of India for continuing to include power projects under the umbrella of NABARD but it was denied by the Finance Ministry on policy issues. Under the NABARD finding 75% of the cost of the project was given as loan and balance 25 % was to be contributed by the borrower as equity. Following is the summary of projects sanctioned by NABARD:- Table 3.12 Rs. In Crores) Sr. No. Name of 2000-01 2001-02 2002-03 2003-04 Total the Utility 1. HVPNL 7.72 16.65 11.34 4.36 40.07 2. UHBVNL 0.00 13.46 13.89 16.85 44.20 3. DHBVNL 0.00 7.70 10.48 7.04 25.22 Total 7.72 37.81 35.71 28.25 109.49 Against above projects, a loan of Rs. 94.43 crores was sanctioned by NABARD. Present Status All the above projects has been executed and summary of drawl of loan is given as under:- Table 3.13 (Rs. In Lacs) Sr. No. Particulars HVPNL UHBVNL DHBVNL Total 1. Cost of NABARD funded 4006.84 4419.83 2522.20 10948.87 projects 2. Loan portion 3440.6 3853.74 2147.96 9442.30 3. Claims received upto 3435.87 3305.78 1489.49 8231.14 31.12.2007 4. Less cost savings due to 4.73 547.96 658.47 1211.16 reorientation of works 5. Claims under release by 0.00 0.00 0.00 0.00 GoH 6. Amount to be surrendered 4.73 547.96 658.47 1211.16 Unclaimed amount 0.00 0.00 0.00 0.00 Note: the above figures of DHBVNL include release of Rs. 13.97 lacs in RIDF VII and Rs. 4.26 lacs in RIDF VIII(Total Rs. 18.23 lacs). The surrender of loan is due to cost saving and/or re-orientation of works.

49 Table 3.14 Physical And Financial Progress of NABARD Projects As on 31.12.2008 Rs. in lacs Assistance Cumulative Assistance received Assistance received Balance Approved from received Sr. NABARD State from amount to be Remarks / Physical Name of the Project. Outlay by NABARD from No share share NABARD received/ Achievement NABARD. upto June NABARD upto surrendered 2008 during upto 31.3.2008 FY 2008-09 31.12.2008 1 2 3 4 5 6 7 8 9 10 A HVPN Projects: Scheme covered under RIDF-VI (2000-01) 1 66 kV substation Dangali / Yara 772.52 695.24 77.28 695.24 0.00 695.24 0.00 66 kV substation with associated lines Yara commissioned 66 kV substation Kalsana with on 19.06.2004 and associated lines 66 kV substation Kalsana commissioned on 9.12.2004. Scheme covered under RIDF-VII (2001-02) 2 132 kV substation Sikenderpur 329.65 296.68 32.97 295.60 - 295.60 0.00 Substation with associated lines. commissioned on 24.01.2004. Scheme stands closed

50 3 Power system improvement in Transformer three district of Haryana commissioned on (Faridabad, Jind and 19.07.2002 Panchkula). It includes i) Scheme stands Augmentation of 132 kV closed substation Garhi with additional 1x10/16 MVA, 132/11 kV transformer. ii) Augmentation of 220 kV 1334.71 1201.24 133.47 1197.59 0.00 1197.59 0.00 Transformer substation Panchkula with commissioned on additional 1x100 MVA, 220/66 16.1.2003 kV transformer. Scheme stands closed iii) Creation of 66 kV substation Substation at Allawapur with associated commissioned on transmission line. 20.01.2004 Scheme stands closed iv) Creation of 132 kV substation Substation at Dhamtan Sahib with commissioned on associated transmission line. 14.06.2004 Scheme stands closed

51

Scheme covered under RIDF-VIII (2002-03) 4 Power system improvement in 1133.91 833.20 300.71 833.2 0.00 833.20 0.00 66 kV substation Faridabad of Haryana. It Aurangabad and includes i) Augmentation of 220 Prithla (Bhagola) kV substation Palwal with commissioned on additional 1x100 MVA, 220/66 31.8.2004 and kV transformer. ii) Creation of 66 31.10.2006 resp.. kV substation Prithla / Bhagola Augmentation of 220 with associated line. iii) Creation kv susbtation Palwal of 66 kV sub with 1X 100 MVA transformer commissioned on 2.1.2006.

Scheme covered under RIDF-IX (2003-04) 5 Up-gradation of 33 kV substation 436.05 414.24 21.81 414.24 0.00 414.24 0.00 Substation Assa-Khera to 132 kV level. commissioned on 21.7.2004 Total (A) 4006.84 3440.60 566.24 3435.87 0.00 3435.87 0.00

B UHBVN Projects:- Scheme covered under RIDF-VII 1 System improvement in power 1346.09 1211.48 134.61 1070.23 0 1070.23 141.25 Balance work in sector in three Districts of being carried out Haryana (Jind, Yamuna-Nagar, against Bid No. 44. & Ambala)

Scheme covered under RIDF-VIII 2 System improvement in power 1389.08 1041.81 347.07 948.88 0 948.88 92.93 All the four Nos. 33 sector in 2 Districts of Haryana KV Sub stations (Kurukshetra & Kaithal) including already 4 No. 33 kV substation commissioned.

52 Scheme covered under RIDF-IX 3 System improvement in power 1684.66 1600.45 84.21 1286.67 0 1286.67 313.78 Balance work in sector in five District of Haryana being carried out Ambala, Yamuna Nagar, against Bid No. 34. Kurukshetra, Kaithal & Jind) including one No. 33 kV substation Sainsa. Total (B) 4419.83 3853.74 565.89 3305.78 0 3305.78 547.961 Note Balance of Rs. 547.961 lacs is proposed to be : surrendered. C DHBVN Projects Scheme covered under RIDF-VII 1 System Improvement in Power 770.48 693.43 77.05 473.46 0.00 473.46 219.97 Scheme includes Sector in three District of rehabilitation of 19 Haryana (Rehabilitation of 11 kV Nos. 11 kV rural Rural feeder under Gurgaon & feeders under Narnaul Operation Circles) Gurgaon & Narnaul circle. Work on three No. feeders in Gurgaon circle has been completed. Rest of the work is in progress.

53

Scheme covered under RIDF-VIII 2 System Improvement in Power 1047.97 785.97 261.99 428.40 0.00 428.40 357.57 Scheme includes Sector in two District of Haryana rehabilitation of 12 (Rehabilitation of 11 kV Rural Nos. 11 kV feeders feeder under Sirsa & Bhiwani under Bhiwani & operation Circles) Sirsa circles; creation of new 33 kV substations at Kharia & Rasulpur Theri and augmentation of 33 kV substation Nathusari under Sirsa circle. 33 kV substations Rasulpur Theri and Kh Scheme covered under RIDF-IX 3 System improvement in power 703.75 668.56 35.19 587.63 0.00 587.63 80.b 93 Scheme includes sector in two District of Haryana rehabilitation of 11 (Rehabilitation of 11 kV Rural kV Rural feeder feeder under Sirsa & Narnaul under Sirsa & operation Circles) Narnaul operation Circles. HT work on 12 Nos 11 kV feeders in Sirsa area stands completed. 33 kV substation Zerpur was commissioned in November 2003. 33 kV substations Bawania , Barda, Dah Total C 2522.20 2147.96 374.23 1489.49 0.00 1489.49 658.47 Total (A+B+C) 10948.87 9442.30 1506.36 8231.14 0.00 8231.14 1206.43 54 3.12 DISTRIBUTION TARIFF APPLICABLE IN HARYANA WITH EFFECT FROM 1.9.2001 Table 3.15 Sr. Category Rates i.e. 1.9.2001 Fuel surcharge Total Total with FSA No. (Paise/unit/month) adjustment (FSA) for a FSA period of 36 months (paise per unit per month) w.e.f Additional 1.12.06 w.e.f 01.08.2008 1. Domestic Upto 40 units 263 13 5 18 281 41 to 300 units 363 30 7 37 400 Above 300 units 428 40 8 48 476 2. NDS 419 39 8 47 466 3. LT Industry At LY 428 40 8 48 466 At 11kV 409 457 Or above 4. HT Industry At 11kV 409 38 8 46 455 At 33kV 397 442 At66/132kV 385 431 At 220 kV 377 424

5. Agriculture Metered 25 Nil NIl Nil Metered 25 (Metered) tubewells Ps/unit tubewells Ps/unit (Ps/unit) i.e. (Ps/unit) i.e. 15.8.2004 15.8.20 04 6. Agriculture Unmetered Rs.35/ Nil Nil Nil Unmeter Rs.35/ (Un- tubewells BHP/ ed BHP/ metered) (Rs/BHP/month) Month tubewells Month i.e. (Rs/BHP/ i.e. 15.8.2004 month) 15.8.20 04 7. Irrigation 37 8 45 i)Direct 400 445 Irrigation Tubewell 400 445 ii)Augmenta tion Canal 400 445 iii)Lift Irrigation 8. Railway At 11kV 409 37 8 45 454 Traction At 33kV 397 442 At 66/132kV 385 430 At 200kV 377 422 Plus Demand Charges @ Rs.60/KVA/Month

55 9. Bulk Supply For LT 419 Bulk Bulk 8 46 396 domestic domestic/ supply 350 non- paise per domestic unit supply 38 455 Bulk non- paise per domestic unit. supply 409 paise per unit w.e.f. 1.11.06 on 455 11kV For 11kV 409 10. Street Light 415 38 8 46 461 11. Public Water Works 400 37 8 45 445 i)Sewerage treatment and 400 445 disposal ii)Water Supply by 400 445 PWD/Public Health iii)Water Supply by Muncipal corporation/ Muncipal Committee/ Council, Panchayats and religious institutions 12. Horticulture/ 200 Paise per unit w.e.f. 40 240 Paise per Fisheries 1.11.06 unit w.e.f. 1.11.06 13. Regd. 200 Paise per unit w.e.f. 39 239 Paise per Gaushala 1.6.07 unit w.e.f. 1.6.07

Notes:-

1. A rebate of 10 paise per unit per month is given to women consumers in domestic category. 2. The Village Chaupals shall not have any separate category but shall be governed by ‘Domestic Supply’ category of power supply. 3. The tubewells installed at religious places for drinking water purposes shall be governed by ‘Public Water Works’ category of tariff. 56 4. The fuel surcharge shall be levied on the consumption recorded on or after mid-night of 30.11.2006. For this purpose, consumption shall be worked out on pro-rata basis as per existing practice. The billing agencies/ field offices are required to show separately the amount of FSA in the electricity bills, assessment summary reports, revenue realization reports and arrears reports. 5. The revised rates are exclusive of Electricity Duty and Municipal tax. 6. The revised rates shall be made applicable on the energy consumed after midnight of Ist September 2001. For the purpose, the energy consumed prior to 1.9.2001 the same shall be worked out on proposed basis. 7. The revised FSA shall be levied on the consumption recorded on or after midnight of 31.07.2008. 8. Other rates and terms and provisions as are not contained in these instructions shall remain unchanged.

57 4. POWER SECTOR REFORMS IN HARYANA 4.1 State Government commitment to Power Sector Reforms

The State Government indicated its commitment to undertake in-depth reforms in the State Power Sector initially through “General Power Sector Policy Statement” released in 01.01.1996. The State Commitment was reiterated in Nov. 1997 when a “Detailed Policy Statement” issued. The latest commitment has been conveyed vide 06.10.2000. The Government of India negotiated a Loan of US$ 60 Million with the World Bank in November 1997 for implementation of the 1st phase of Haryana Power Restructuring Project (APL-1). The Loan was sanctioned in Jan. 1998 and became effective in March, 1998 and was valid up to 31.12.2000. A MoU has been signed with Govt. of India to assist in the State’s programme for power sector reforms on 13.2.2001. The Govt. of India would also assist the State in implementing the new power projects, provide extra allocation of power from Centrally Sponsored Schemes and provide funds for strengthening the power transmission and distribution system.

4.2 IMPORTANT MILESTONES ACHIEVED

The Haryana State has achieved the following major milestones:

10.03.1998 Haryana Electricity Reforms Act notified in official Gazette

14.08.1998 Haryana Electricity Reforms Act made effective.

14.08.1998 Erstwhile HSEB reorganised to create Generation Company (HPGC) and Transmission Company (HVPN). The Assets, Liabilities and Personnel of HSEB transferred to new entities vide 1st Transfer Policy Scheme dated 14.08.1998.

16.08.1998: Haryana Electricity Regulatory Commission established

March, 1999 Two independent State Owned Distribution Companies were established to look after Power Distribution functions.

01.7.1999 2nd Transfer scheme was notified thereby assets liabilities and personnel of HVPN were transferred to the Two Distribution Companies

June, 2000 Fuel Surcharge Adjustment (FSA) Application was made to the Commission. HERC has approved the levy of Surcharge vide their letter dated 27.07.2000 order implemented.

June 2000 HVPN made 1st Tariff filing to the Regulatory Commission seeking re- fixation of Electricity Tariff in the State. HERC has issued orders for revision of tariff w.e.f. 1st January 2001 vide order dated 22-12-2000 order implemented. 58 Mar 2001 HVPN made second tariff filing to the Regulatory Commission seeking re-fixation of electricity tariff in the State. HERC has issued orders for revision of tariff vide Order dated 11.8.2001.

Dec. 2001 HVPN filed with HERC Annual Revenue Requirement for Transmission and Bulk supply and Distribution and Retail supply business alongwith transmission and Bulk Supply Tariff for FY 2003. HERC has issued order on Annual Revenue requirement on 16.8.2002

Dec.2002 HVPN filed with HERC Annual Revenue Requirement for Transmission & Bulk Supply businesses along with Transmission & Bulk Supply Tariff and Distribution & Retail Supply business for the FY 2004. HERC has issued orders dated 12.8.2003 and 20.8.2003 respectively.

Dec.2003 HVPN filed with HERC Annual Revenue Requirement for Transmission & Bulk Supply businesses along with Transmission & Bulk Supply Tariff and Distribution & Retail Supply business for the FY 2005.

Dec. 2004 HVPN filed with HERC Revised Annual Revenue Requirement for Transmission & Bulk Supply business for FY 2006. The HERC issued order on 10.05.2005.

May 2005 HERC issued notification dated 19.5.2005 on “terms & conditions for open access for intra-State transmission & distribution system, regulation -2005” HVPNL has also notified procedure for short term open access on 9.3.2006. HVPNL & Distribution Companies have notified various charges to be paid by Open Access customers. Distribution Companies have also declared that no surcharge/additional surcharge shall be levied to the open access customers for the period April to September 2007.

Dec. 2005 HVPN & Discoms filed with HERC Annual Revenue Requirement for Transmission, Bulk Supply & Retail Supply business for FY 2007. Public hearing was held on 27.3.2006.HERC issued Orders in June, 2006 on which review petition was filed by HVPNL. Orders on review petition have been issued by HERC in Dec, 2006. Dec. 2006 HVPNL filed the ARR for transmission business and SLDC business for the year 2007-08 on 10.12.2006. The hearing on ARR was held on 23.2.2007. HERC issued its orders on 8.5.2007. HVPNL filed review petition on the above ARR order on 6.6.2007. Additional grounds seeking review of the ARR order dated 8.5.2007 were filed with HERC on 20.8.2007. The hearing on the review petition was held on 30.8.2007. HERC issued the order on review petition on dated 26.09.2007. Nov. 2007 HVPNL filed the ARR for transmission business and SLDC for FY 2008-09 on 30.11.2007. The hearing on the ARR was held on 26.2.2008. HERC issued orders on ARR for transmission business and SLDC on 23.04.2008. HVPNL filed review petitions on the orders dated 23.04.2008 on 22.05.2008. Hearing on review petition is awaited. Dec. 2008 HVPNL filed the ARR for transmission business and SLDC for FY 2009-10 on 01.12.2008.

59 5. HARYANA POWER PURCHASE CENTER.

5.1 OVERALL POWER SUPPLY POSITION IN THE STATE OF HARYANA .

There has been sustained improvement in the over-all power availability in the State. The power supply position since 1998-99 has been as follows:- Table 5.1 LU per day Year 98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09 Power 367 415 447 475 519 556 578 622 665 723 756* supplied % Increase over 13 7 6 9 7 4 7.6 7 8.8 4.61 last year

* Upto Dec. 08

The comparison of power supplied to the State and agriculture sector during last 3 years is as follows:- Table 5.2 Average Lacs units per day State as whole Agriculture sector Month 2005-06 2006-07 2007-08 2008-09 % 2005-06 2006-07 2007-08 2008-09 % increase increase over over 2007-08 2007-08 April 547 564 608 594* - 235.68 239.24 240 - 232* May 645 692 733 686* - 306.15 307.42 317 275* - June 695 772 847 784* - 358.24 393.53 420 335* - July 700 780 924 902* 364.80 408.09 481 446* Aug 755 769 912 898* 424.98 434.32 486 430* Sept 642 753 813 785* 331.02 386.00 391 369* Oct. 644 672 686 767 11.81% 323.49 346 348 355 2.0% Nov. 569 597 628 684 8.92% 276.46 279 304 308 1.3% Dec. 547 611 623 707 13.48% 285.53 300 299 350 17.1% Jan. 592 615 612 301.32 313.00 318 Feb. 584 571 640 295.74 257.00 330 March 536 573 645 247.91 243 332

* Consumption is less due to wide spread rains in the State.

60

5.2 Rain fall data during last 4 years:-

Table 5.3 (Fig. In mms) Month Normal 2004 2005 2006 2007 2008 Actual Actual Actual Actual Actual January 22.4 35.5 18.4 2.8 0.3 2.5 February 17.5 2.8 38.0 0.3 83.8 0.2 March 14.7 0 38.4 40 51.1 0.0 April 7.3 12.4 3.7 0.9 0.7 11.9 May 14.7 43.7 8.5 30.1 7.7 65.9 June 48.0 72 59.3 48 78.2 117.8 July 185.0 25.6 217.3 152.8 63.6 102.7 August 184.7 276.7 64.5 43.5 77.5 155.0 September 95.3 28.5 169.9 51.5 44.0 104.0 October 17.0 57.7 0 3.3 0.80 0.80 November 5.0 0 0.7 0.6 0.00 2.70 December 7.7 0.3 0.0 2.0 1.20 0.00

5.3 The availability of the power from July 08 to Dec. 08:-

The total installed generation capacity available with the State of Haryana is 4753.29 MW. Out of this 2187.7 MW is located within the State at the Thermal Power Stations in Panipat, Faridabad, Yamunanagar and Hydro-electric Station at Yamunanagar.

The available capacity varies between 2800 to 3600 MW during different seasons depending upon inflows at Hydro Stations/planned/forced outages of the generators. The demand varies between 3100 to 5100 MW in various seasons and during off peak & peak hrs. The demand of Haryana is increasing exponentially @ more than 14% per year on account of industrialization and more consumption on agriculture sector and also because of being part of National Capital Region. The power availability from above mentioned projects is not sufficient to meet the demand of the State particularly during peak Paddy and Rabi crop season. As such HPPC has to resort to short term power purchase and planning of long term power arrangements. Total availability of power from long term source and short term arrangement to the State was as under during July 08 to Dec. 08 ( Operational data ) :-

61 Table 5.4

Source July Aug Sept. Oct. Nov. Dec.

NTPC 109.2 108.4 126.6 131.9 126.6 129.6 NHPC. 73.7 76.1 48.6 30.7 19.1 17.7 NPC 9.2 8.3 5.3 7.1 8.8 8.0 B.B.M.B 120.8 143.8 113.7 95.1 69.3 69.6 I.P. 6.6 6.8 5.0 5.4 5.5 6.4 NJPC 21.0 20.5 15.4 9.7 6.4 4.9 Tehri Hydro 9.3 13.1 5.8 2.9 3.2 3.8 FARAKHA , KHELGAON, TALA 16.9 17.7 19.2 16.2 14.4 17.6 Own Generation HPGCL 293.1 348.2 324.3 352.4 368.6 378.5 FARIDABAD Gas 68.7 68.9 64.1 50.9 46.9 61.3 Total availability from Long Term 728.4 804.6 720.4 695.9 663.6 685.1 Total short term 76.1 35.2 42.3 26.0 14.6 13.0 Banking 49.9 45.1 13.0 11.6 -18.1 -43.9 UI Energy 62.2 20.2 16.2 40.1 1.3 53.4 CS losses Ex-bus (E) 14.4 13.2 12.1 12.4 11.6 12.9 Power supplied to the state / Availability 902.3 897.7 787.3 767.4 25.6 707.0

The anticipated availability of the power from long term sources, demand projection and corresponding short falls during Jan. 09 to Feb. 09 are as under:- Table 5.5 Average Lacs units per day Source Jan. 09 Feb. 09 March 09 NTPC 126 114 115 NHPC 23 26 30 NPC 12 12 12 BBMB 52 53 52 IP Share 5 5 5 NJPC 4 6 8 Tehri 2 2 2 Tala, Farakka & Kehlgaon 20 20 20 HPGC 381 353 345 FGPS [Gas] 75 75 75 62 Total Availability from long term sources 700 666 664 (-)Return of Banked power * -49 -42 -31 Total Availability including banking 651 624 633 Demand Projected with 14% Growth over 698 730 706 demand met during 2007-08/2008-09 Surplus/Deficit with 14% Growth over -47 -106 -73 demand met during 2007-08/2008-09 Scenario - 4 Demand Projected with 14% Growth over 873 881 890 demand felt during 2007-08/2008-09 Surplus/Deficit with 14% Growth over -222 -257 -257 demand felt during 2007-08/2008-09

There may be additional availability by 30 LUs per day from over drawl from Grid and 20 LUs per day from liquid scheduling.

5.4 LIST OF PROJECTS WHERE EITHER CONSENT GIVEN OR PPA SIGNED AS ON 31.12.2008 Table 5.6 Year Capacity of Hydel/Thermal/ Haryana Name of the Project onwards Project (MW) Coal/Gas Share (MW) 2007-08 Magnum 25 Oil 25

2008-09 Kahalgaon, Stage II. ER 1500 Thermal 35 RAPP Unit 5 440 Nuclear 12.5 Baglihar (J&K) 450 Hydel 50 Sub Total 97.5 2009-10 RAPP Unit 6 440 Nuclear 12.5 Amarkantak, Chattisgarh 30 Thermal 300 Sewa II, J&K 120 Hydro 9 Koldam, H.P 800 Hydro 43 Budhil, H.P 70 Hydro 70 Barh, Stage 1 Er 1980 Thermal 23 Mejia B TPS (DVC) 1000 Thermal 100 Sub Total 557.5 2010-11 Chamera III HP 231 Hydro 16 Koteshwar. Uttranchal 400 Hydro 20 Prabati III, HP 520 Hydro 34 Uri II, J&K 240 Hydro 13 Barh, Stage 1 Er 1980 Thermal 45 Raghunathpur TPS DVC) 1000 Thermal 100 Koderma TPS (DVC) 1000 Thermal 100 Sub Total 328 2011-12 Malwa of MPGENCO 1000 Thermal 100 Subansari, ER 2000 Hydro 53 Kameng Arunachal 600 Hydro 16 Tehri PSP Uttranchal 1000 Hydro 100 Rampur H.P 434 Hydro 15

63 Karcham Wangtoo HP 1000 Hydro 200 Teesta III, Sikklim 1200 Hydro 200 Barh, Stage II Er 1320 Thermal 46 Rihand Stage III 1000 Thermal 57 Mundra Gujrat 4000 Ultra Mega 80 Parbati-ii 800 Hydro 26 PTC/GMR(Case-1) Dhankanal,Orissa 300 Adani (case—1) Mundra Gujrat 475 Sub Total 1668 2012-13 Kishanganga, J&K 330 Hydro 16 ONGC Gas Plant, Tripura 750 Gas 200 N. Karanpura, ER 1980 Thermal 68 Pakal Dhul, J&K 1000 Hydro 57 Kotli Bhel, (All 3 stages) Uttranchal 1045 Hydro 58 Siang Middle, ER 1000 Hydro 56 West Seti, Nepal 750 Hydro 150 Tipaimukh Manipur 1500 Hydro 40 Thermal Coal * Sasan, MP 4000 Ultra Mega 450 *Mundra, Gujrat 4000 320 Orissa 4000 400 Jharkhand UMPP 4000 200 Vishnugarh Piplakoti 444 Hydro 24 Lanco (Case-1) Dhenkanal, Orissa 389 Adani (Case-1) Mumdra, Gujrat 949 Sub Total 3377 Grand Total 6053

64 5.5 Yearly Capacity Addition Scenario – Till The End of 2012-13. Table 5.7

Sources of installed capacity 2008-09 2009-10 2010-11 2011-12 2012-13

State Owned Projects 1587.70 1587.70 1587.70 1587.70 1587.70

Central Sector Share 1518.11 1518.11 1518.11 1518.11 1518.11

Shared Projects - BBMB & IP 937.50 937.50 937.50 937.50 937.50

DCRTPP Yamuna Nagar 600.00 600.00 600.00 600.00 600.00 Hisar TPS (600X2) Mega Plant Status 0 1080.00 1080.00 1080.00 1080.00 (10% Power sale in other state) Jhajjar Case- II =1320 MW 0 0 0 1188.00 1188.00 (10% Power sale in other state) Aravali STPS,Jhajjar 0 0 750.00 750.00 750.00 (500*3){Haryana: - 50:50} Additional availability through PPA 122.5 706 1008 2676 6053 with IPPs/CPSU Yamuna Nagar Extention 0 0 300.00 300.00 300

Faridabad Gas 0 0 0 0 432

Total Capacity (MW) 4765.81 6429.31 7781.31 10637.31 14446.31

Load Growth, Capacity Addition & Available Capacity (MW):

16000 15000 14446 14000 12388 13000 Demand with 14% Growth 10867 12000 Available capacity 11000 9533 10637 10000 8362 9000 7335 8000

7000 7781

6000 6429 5000 4000 4765 3000 2008-09 2009-10 2010-11 2011-12 2012-13 Year

65

ABSTRACT OF ANNEXURE – I

DISTRICT-WISE 33kV WORKS COMPLETED DURING MARCH 2005 TO DECEMBER 2008

Sr. Name of District 33kV substation Cost (Rs. in lacs) No. New Aug. New Aug. line G total 1. Ambala 1 0 137 0 2 139 2. Panchkula 0 0 0 0 0 0 3. Yamunanagar 0 2 0 35 0 35 4. Kaithal 9 10 1180 377 299 1856 5. Kurukshetra 2 7 225 160 85 470 6. Karnal 10 14 986 483 280 1749 7. Panipat 4 7 486 251 235 972 8. Jind 9 6 1221 213 336 1770 9. Sonipat 2 12 281 409 76 766 10. Rohtak 7 6 912 150 285 1347 11. Jhajjar 3 11 366 302 92 760 12. Hisar 4 8 399 342 166 907 13. Fatehabad 2 20 202 807 114 1123 14. Bhiwani 14 13 1506 406 517 2429 15. Sirsa 11 8 1056 296 581 1933 16. Mohindergarh 6 6 788 321 210 1319 17. Rewari 5 10 710 425 152 1287 18. Gurgaon 0 0 0 0 0 0 19. Faridabad 0 0 0 0 0 0 20. Mewat 0 4 0 131 0 131 Total 89 144 10455 5108 3430 18993

66

ABSTRACT OF ANNEXURE – II

DISTRICT-WISE APPROVED 33KV NEW SUBSTATIONS, AUGMENTATION OF EXISTING SUBSTATIONS AND TRANSMISSION LINES UNDER CONSTRUCTION / TO BE CONSTRUCTED.

District 33KV works Cost (Rs. In lac)

New Aug. Line (Km) New Aug. Line Total (No.) (No.)

Ambala 1 0 10.00 150 0 50 200

Panchkula 0 0 0 0 0 0 0

Yamunanagar 0 1 18 0 80 126 206

Kurukshetra 7 2 22.95 1424 240 202 1866

Kaithal 15 4 114 3187 270 718 4175

Karnal 11 5 86.10 1950 490 517 2957

Panipat 3 1 29.50 720 160 185 1065

Jind 2 2 27.00 300 200 115 615

Sonipat 7 1 85.5 1348 30 527 1905

Rohtak 4 1 18.8 780 32 107.5 919.5

Jhajjar 4 0 38 638 0 210 848

Hisar 3 3 28 450 152 115 717 Fatehabad 6 1 28.29 820 20 132 972 Bhiwani 12 4 101.5 1700 220 511 2431 Sirsa 8 2 63.64 1150 140 293.5 1583.5 Mohindergarh 6 0 48.8 810 0 191 1001 Rewari 2 0 8.5 270 0 33 303 Gurgoan 0 0 0 0 0 0 0 Mewat 1 1 14 150 20 70 240 Faridabad 0 0 0 0 0 0 0 Total 92 28 742.58 15847 2054 4103 22004

67 ABSTRACT OF ANNEXURE-III

DISTRICT-WISE 66kV & ABOVE TRANSMISSION WORKS COMPLETED DURING MARCH 2005 TO DECEMBER 2008

Sr. Name of 220kV 132kV 66kV Total Capacity Expenses incurred (Rs. in lacs) No. District substation substation substation substation Added (in MVA) New Aug. New Aug. New Aug. New Aug. New Aug. New Aug. Line G total 1. Ambala - 1 - - 1 6 1 7 16 154 248 894 181 1323 2. Panchkula - 1 - - - 4 - 5 - 64 - 937 - 937 3. Yamunanagar - 1 - - 1 5 1 6 16 137.5 354 1252 1201 2807 4. Kaithal - 1 4 5 - - 4 6 73 148 1950 1290 1318 4558 5. Kurukshetra 2 2 - 3 4 4 6 9 165.5 329 6155 1874 3413 11442 6. Karnal 1 - - 3 - - 1 3 216 70 2500 743 692 3935 7. Panipat - - - 3 - - - 3 - 66 - 498 - 498 8. Jind - - 4 8 - - 4 8 80 148 2647 1859 2931 7437 9. Sonepat - 2 - 1 - - - 3 - 136 - 757 678 1435 10. Rohtak - 3 2 3 - - 2 6 57 175 1730 1625 512 3867 11. Jhajjar 1 1 1 7 - - 2 8 132 180.5 2360 1641 2357 6358 12. Hisar - - 2 2 - - 2 2 60 32 1120 490 1075 2685 13. Fatehabad 1 1 2 1 - - 3 2 176 116 3237 435 823 4495 14. Bhiwani - 1 - 7 - - - 8 - 115 - 1402 1097 2499 15. Sirsa - 1 - 8 - - - 9 - 216.5 - 2176 - 2176 16. Mohindergarh ------17. Rewari - 2 1 3 - - 1 5 16 82.5 450 840 849 2139 18. Gurgaon 1 1 - - 4 12 5 13 215 316.5 3772 3295 2930 9997 19. Mewat - - - - 1 1 1 1 16 0.5 360 45 135 540 20 Faridabad - 3 - - 3 7 3 10 40 178.5 830 1799 315 2944 21 Palwal - 2 - - 2 1 2 3 32 114 731 823 510 2064 Total 6 22 16 54 16 40 38 117 1310.5 2779.5 28444 24675 21017 74136

68 ABSTRACT OF ANNEXURE-IV

DISTRICT-WISE APPROVED 66KV AND ABOVE TRANSMISSION WORKS i.e. NEW SUBSTATIONS, AUGMENTATION OF EXISTING SUBSTATIONS AND TRANSMISSION LINES UNDER CONSTRUCTION / TO BE CONSTRUCTED

District New Substations (Nos.) Augmentation of existing Transmission Lines (Km) Substations (Nos.) 400 kV 220KV 132K 66K Total 220K 132KV 66KV Total 400 220K 132K 66KV Total V V V kV V V Ambala 7 7 1 1 2 112 112 Panchkula 1 2 3 1 1 2 5 55 60 Yamunanagar 1 2 3 3 3 48 65 113 Kurukshetra 5 5 1 1 2 53 98 10 161 Kaithal 2 3 5 2 3 5 72 128 200 Karnal 1 9 10 1 4 5 95 130 225 Panipat 2 5 7 4 4 68 92 160 Jind 3 3 2 2 4 41 41 Sonepat 1 1 3 5 1 5 6 47 32 41 119 Rohtak 1 1 2 4 1 1 80 24 26 130 Jhajjar 2 2 2 2 31 31 Hisar 1 1 1 3 1 1 97.5 73 124 295 Fatehabad 1 3 4 1 1 109 124 233 Bhiwani 4 6 10 1 6 7 183 159 342 Sirsa 1 1 3 5 4 4 100 140 56 296 Mohindergarh 1 3 4 5 5 74 20 76 170 Rewari 2 1 1 4 1 1 2 133 46 28 207 Gurgaon 1 4 12 17 2 5 7 164 98 194 456 Mewat 2 2 1 1 126 162 288 Faridabad 1 2 2 5 2 16 18 2 24 35 61 Palwal 1 4 5 Total 7 26 49 26 108 15 40 32 87 565 1302 1172 661 3699

69

COST ABSTRACT OF ANNEXURE – IV

COST OF DISTRICT-WISE APPROVED 66 kV AND ABOVE NEW SUBSTATIONS, AUGMENTATION OF EXISTING SUBSTATIONS AND TRANSMISSION LINES UNDER CONSTRUCTION / TO BE CONSTRUCTED Rs in lac District New Substation Augmentation of existing Transmission Lines Grand Substations Total 400 kV 220KV 132KV 66KV Total 220KV 132KV 66kV Total 400 220KV 132KV 66KV Total kV Ambala 5500 5500 750 250 1000 3088 3088 9588 Panchkula 2500 5500 8000 750 200 950 225 2772 2997 11947 Yamunanagar 3000 1438 4438 365 365 2260 1569 3829 8632 Kurukshetra 4140 4140 250 115 365 2585 2830 290 5705 10210 Kaithal 5000 2790 7790 750 600 1350 4000 3596 7596 16736 Karnal 3000 8303 11303 550 913 1463 3967 4706 8673 21439 Panipat 5000 4200 9200 840 840 3712 2858.5 6571 16611 Jind 2690 2690 750 500 1250 1153 1153 5093 Sonepat 10000 3000 2624 15624 238 1265 1503 6500 1740 1775 10015 27142 Rohtak 10000 2500 3000 15500 87 87 8000 1175 513 9688 25275 Jhajjar 1745 1745 500 500 783 783 3028 Hisar 10000 2500 633 13133 250 250 10008 2990 2789 15787 29170 Fatehabad 3000 2585 5585 250 250 5986 2760 8746 14581 Bhiwani 11600 6131 17731 1100 1450 2550 9205 4672 13877 34158 Sirsa 10000 2500 2800 15300 704 704 5000 8190 1960 15150 31154 Mohindergarh 10000 3000 13000 1230 1230 7500 1080 1990 10570 24800 Rewari 6500 1000 1000 8500 700 200 900 4705 1945 840 7490 16890 Gurgaon 8500 21000 17650 47150 1550 1447 2997 15400 5771 7580 28750 78897 Mewat 6000 6000 60 60 7024 6759 13783 19843 Faridabad 10000 11500 1500 23000 800 4120 4920 200 1450 4575 6225 34145 Palwal 0 0 0 0 0 250 800 1050 0 1050 Total 68500 88600 45641 32588 235329 8188 9039 7357 24584 52608 66065 34330 27473 180476 440389

70 ANNEXURE – I

District wise 33KV New Substations commissioned / Augmented and Transmission Lines added from March 2005 to December 2008.

Sr. Name of Sub-station Capacity Cost Date of added in MVA (Rs. In Lacs) Commissioning Line in Km. A District Ambala I. New Substation 1. 33kV Substation Jatwar 8MVA 137 31.3.2007 Total-I 8MVA 137 II. Augmentation - - III. Transmission Lines 1. 33kV link line from Dhulkote- 0.8 KM 2 31.3.2007 line for Jatwar Total-III 0.8 KM 2 Total Cost I – III 139

B. District Panchkula I. New Substation - - - II. Augmentation - - - III. Transmission Lines - - - Total Cost I – III -

C. District Yamunanagar I. New Substation -- II. Augmentation 1. 33KV Substation Bhud Kalan 1MVA 18 1.4.2005

2. 33kV Substation Bhud Kalan 3MVA 17 29.4.2007 Total-II 4 MVA 35 Total I – II 35 III. Transmission Lines - - Total Cost I – III 35

D District Kaithal I. New Substation 1. 33kV Substation Manas 8MVA 136 13.4.2007 2. 33kV Substation Mehmoodpur 8MVA 102 10.5.2007 3. 33kV Substation Urlana 8MVA 119 15.5.2007 4. 33kV Substation Budsoi 8MVA 70 10.6.2007 5. 33kV Substation Karora 8MVA 126 25.9.2007 6. 33kV Substation Guhna 8MVA 118 17.12.2007 7. 33kV Substation Mundri 8 MVA 130 26.2.2008 8. 33kV Substation Sanghan 16MVA 234 16.7.2008 9. 33 KV Substation Kurar 10 MVA 145 5.11.2008 Total-I 82 MVA 1180 II. Augmentation 1. 33KV Substation Daba 3MVA 30 25.8.2005

71 2. 33KV Substation Noutch 2.3MVA 28 21.11.2005 3. 33KV Substation Mini Sect. 8MVA 26 16.12.2005 Kaithal 4. 33 KV Substation Paprala 3 MVA 40 24.1.2006 5. 33KV Substation Habri 3MVA 30 23.12.2006 6. 33KV Substation Jakholi 5MVA 20 24.11.2007 7. 33KV Substation Teontha 4MVA 55 2.1.2008 8. 33kV Substation Paprala 1.7 MVA 48 27.3.2008 9. 33kV Substation Keorak 8 MVA 60 5.6.2008 10. 33kV Substation Teak 5MVA 40 25.7.2008 Total-II 43 MVA 377 Total I-II 125 MVA 1557 III. Transmission Lines 1. T-off from 33kV Kaithal-Padla 2.200 KM 17 13.4.2007 line at Manas 2. 33kV Gulha Cheeka (132kV)- 12.616 KM 68 10.5.2007 Mehmoodpur line 3. T-off from 33kV Cheeka- 5.451 KM 29 15.5.2007 Chaku Ladana line to Urlana 4. 33kV T-off from 33kV Guhla- 2.500 KM 11 10.6.2007 Cheeka-Bhagal line to Badsui 5. 33kV T-off from 33kV 3.200KM 25 25.9.2007 Rajound-Pai line for Karora 6. 33kV line for 33kV 4.700KM 24 17.12.2007 Substation Guhna 7. 33kV line from 132kV 5.200KM 23 26.2.2008 substation Pundri to Mundri 8. 33kV line from 132 KV S/stn. 5.600KM 32 16.7.2008 Padla to Sanghan. 9. 33 KV line from 132 KV 14.000 KM 70 5.11.2008 substation. Padla to Kurar Total-III 55.467 KM 299 Total Cost I – III 1856 E District Kurukshetra I. New Substation 1. 33kV Substation Jhansa Rd 8MVA 104 9.3.2007 Kurukshetra 2. 33 KV substation Guldera 8 MVA 121 1.9.2008 Total-I 16MVA 225 II. Augmentation 1. 33KV Substation Dhurala 1.3MVA 40 11.4.2005 1.3MVA 27.4.2005 2. 33KV Substation KU 4MVA 20 17.5.2005 Kurukshetra 3. 33KV Substation Kirmich 3MVA 20 20.6.2005 4. 33KV Substation Ismailbad 5MVA 20 29.6.2005 5. 33KV Substation Barna 2.3MVA 20 17.7.2005 6. 33KV Substation Sainsa 4MVA 20 1.12.2005 7. 33kV Substation Murthali 6.3MVA 20 31.7.2007 Total-II 27.2 MVA 160 Total I-II 43.2MVA 385 72 III. Transmission Lines - - 1. 33kV line for Jhansa Rd. 6.000 KM 22 9.3.2007 Kurukshetra 2. 33 KV line for Guldera 9.500 KM 63 8.8.2008 Total-III 15.500KM 85 Total Cost I – III 470

F District Karnal

I. New Substation 1. 33KV Substation Salwan 8MVA 90 15.8.2005 2. 33KV Substation Thal 8MVA 90 29.8.2005 3. 33KV Substation Shamgarh 8MVA 90 28.9.2005 4. 33KV Substation S-12 HUDA 5MVA 130 1.3.2006 Karnal 5. 33KV Substation S-6 HUDA 5MVA 71 26.4.2006 Karnal 6. 33kV Substation Budhanpur 8MVA 102 7.3.2007 7. 33kV Substation Chor Karsa 5MVA 70 4.6.2007 8. 33kV Substation Brass 8MVA 103 20.9.2007 9. 33kV Substation Bahari 8MVA 118 21.2.2008 10. 33kV Substation Popra 8MVA 122 2.3.2008 Total-I 71 MVA 986 II. Augmentation 1. 33KV Substation Kutail 4MVA 20 9.5.2005 2. 33KV Substation Kohand 4MVA 20 23.5.2005 3. 33KV Substation Kohand 3MVA 20 4.6.2005 4. 33KV Substation Kutail 3MVA 20 24.6.2005 5. 33KV Substation Nagla 1MVA 10 23.8.2005 6. 33KV Substation Nalipar 3MVA 45 13.9.2006

7. 33KV Substation Old Power 3MVA 43 6.11.2006 House Karnal 8. 33kV Substation Garhi Birbal 3MVA 38 17.5.2007 9. 33KV Substation Garhi Birbal 3MVA 60 25.10.2007 10. 33KV Substation S- 12 Karnal 8MVA 70 28.11.2007 11. 33kV Substation HSIDC S-3 4MVA 50 16.2.2008 Karnal 12. 33kV Substation Old Power 5MVA 15 3.3.2008 House Karnal 13. 33kV Substation S-6 Karnal 8MVA 60 10.6.2008 14. 33kV Substation Nigdhu 5 MVA 12 8.7.2008 Total-II 57 MVA 483 Total I –II 128 MVA 1469 III. Transmission Lines 1. LILO from 33KV idle 0.400 KM 2 15.8.2005 Safidon –Jalmana line to 33KV substation Salwan 2. 33KV –Thal line 12.000 KM 30 29.8.2005

73 3. 33KV Nilokheri- 10.000 KM 25 28.9.2005 Shamgarh/Dadupur line 4. 33KV Karnal-Sector 12, 4.500 KM 14 1.3.2006 HUDA Karnal line 5. 33KV Madhuban – Sector 6.300 KM 18 26.4.2006 6, HUDA Karnal line 6. 33kV line for Budhanpur 13.138 KM 77 7.3.2007 7. 33kV line from Nissing- 5.706 KM 43 4.6.2007 Dacher upto Chor Kersa 8. 33kV line from Nissing- 3.500KM 22 20.9.2007 Rasina upto Brass 9. 33 kV line from 132 kV 7.000 KM 34 21.2.2008 substation Alewa to Bahari 10. 33 kV line from 132 kV 3.000 KM 15 2.3.2008 substation Uchana to Popra Total-III 65.544 280 Total Cost I – III 1749 G. District Panipat I. New Substation 1. 33KV Substation Assand 16MVA 135 14.8.2005 Road Panipat (Jattal) 2. 33KV Substation Ahar 8MVA 90 19.9.2005 3. 33kV Substation Brahaman 8MVA 144 8.5.2008 Majra 4. 33 KV substation Dahar 8 MVA 117 22.12.08 Total-I 40 MVA 486 II. Augmentation 1. 33KV Substation Naultha 3MVA 20 21.6.2005 2. 33KV Substation Sewa 8MVA 28 8.12.2005 3. 33KV Substation Bapoli 5MVA 35 9.6.2006 4. 33KV Substation Naultha 3MVA 40 14.6.2006 5. 33KV Substation Naultha 1.7 MVA 40 23.7.2006 6. 33KV Substation Sanoli Road 1.3MVA 40 8.8.2006 Panipat 7. 33kV Substation Dharamgarh 4 MVA 48 3.3.2008 Total-II 26 MVA 251 Total I – II 66 MVA 737 III. Transmission Lines 1. T-off line from 33KV Gohana 10.500 KM 27 14.8.2005 road Panipat –Munak line to 33KV substation Assandh road Panipat (Jattal) 2. 33Kv Matlauda – Ahar line 12.000 KM 30 19.9.2005 3. 33kV line from 132kV 12.000KM 66 8.5.2008 substation Madlauda to Brahman Majra 4. 33KV line for Dahar 16.000 KM 112 22.12.08 Total-III 50.500 235 Total Cost I-III 972 H District Jind 74 I. New Substation 1. 33KV Substation Shri Rag 8MVA 127 16.11.2005 Khera 2. 33KV Substation Rasidon 8MVA 131 30.11.2006 3. 33kV Substation Gangoli 8MVA 106 5.4.2007 4. 33kV Substation Didwara 8MVA 155 10.9.2007 5. 33kV Substation Chhattar 8MVA 136 3.10.2007 6. 33kV Substation Lochhab 8MVA 144 15.10.2007 7. 33kV Substation Manoharpur 10 MVA 158 26.2.2008 8. 33kV Substation Pipaltha 8MVA 120 13.3.2008 9. 33kV Substation Kakrod 8MVA 144 2.5.2008 Total-I 74 MVA 1221 II. Augmentation 1. 33KV Substation Pindara 4MVA 30 14.7.2005 2. 33KV Substation Hatt 4MVA 30 31.8.2005 3. 33KV Substation 4.7MVA 19 6.10.2005 Ramrai/Bibipur 4. 33kV Substation Kinana 5MVA 12 12.7.2007 5. 33kV Substation Singhana 4 MVA 50 20.3.2008 6. 33kV Substation Rag Khera 8 MVA 72 24.7.2008 Total-II 29.7 MVA 213 Total I-II 103.7 MVA 1434 III. Transmission Lines 1. T-off of 33KV line from 132KV 1.250 KM 3 16.11.2005 substation Jind to Naguran for Siri Rag Khera 2. 33KV Garhi – Rasidon line 13.000 KM 37 6.11.2006 3. 33kV Kheri Taloda-Gangoli 9.500 KM 40 5.4.2007 line 4. 33KV line from 33KV Safidon- 3.000KM 15 10.9.2007 Jalmana to Didwara 5. 33KV line from 132KV 16.000KM 67 3.10.2007 substation Uchana to Chhattar 6. 33KV Narwana-Dhamtan 8.000KM 50 15.10.2007 upto Lochhab line 7. 33kV line for Manohar Pur 0.250KM 3 26.2.2008 8. 33kV line from 33kV 7.000KM 31 13.3.2008 substation Pipaltha 9. 33kV line from 132kV 14.000KM 90 2.5.2008 substation Uchana to Kakrod Total-III 72.000KM 336 Total Cost I – III 1770

I District Sonepat I. New Substation 1. 33KV Substation Sardana 8MVA 130 6.3.2006 2. 33KV Substation Firogpur 8MVA 151 31.1.2007 Banger Total-I 16MVA 281 II. Augmentation 75 1. 33KV Substation Aterna 2.3MVA 20 19.5.2005 2. 33KV Substatiion Khewra 5MVA 30 17..6.2005 3. 33KV Substation Larsoli 1.7MVA 30 10.8.2005 4. 33KV Substation Aterna 2.3MVA 20 25.10.2005 5. 33KV Substatiion Kundli 4MVA 23 5.12.2005 6. 33KV Substation Khanpur 4MVA 16 30.3.2006 7. 33KV Substation Barota 4MVA 15 1.2.2007 8. 33KV Substation Kathura 2.3MVA 20 15.10.2007 9. 33KV Substation Bahalgarh 1.7MVA 55 17.10.2007 10. 33KV Substation Butana 1.7MVA 55 3.1.2008 11. 33kV Substation Khanpur 4 MVA 52 5.3.2008 Kalan 12. 33kV Substation Sugar Mill 8 MVA 73 24.7.2008 Sonipat Total-II 41 MVA 409 Total I-II 57 MVA 690 III. Transmission Lines 1. 33KV Ganaur-Sardana line 12.000KM 36 6.3.2006 2. 33KV line for 33KV substation 10.000KM 40 31.1.2007 Ferozpur Banger Total-III 22 76 Total Cost I – III 766 J. District Rohtak I. New Substation 1. 33KV Substation Bhagwatipur 8MVA 90 10.9.2005 2. 33KV Substation Sector 6 8MVA 125 30.5.2007 Rohtak 3. 33kV Substation Sr. I. School, 6.3MVA 130 10.7.2007 Rohtak 4. 33kV Substation Baniyani 8MVA 150 25.9.2007 5. 33kV Substation Hassangarh 8 MVA 150 27.2.2008 6. 33 KV substation Bal Bhawan 8 MVA 150 8.8.2008 Rohtak 7. 33 KV substation Jindran 8 MVA 117 7.11.2008 Total-I 54.3 MVA 912 II. Augmentation 1. 33KV Substation Jassia 2.3 MVA 20 27.3.2005 2. 33KV Substation Madina 2.3MVA 20 14.7.2005 3. 332KV Substation HCC 6.3MVA 30 8.8.2005 Rohtak 4. 33KV Substation Jassia 4MVA 30 27.8.2005 5. 33KV Substation Kahanaur 3MVA 30 27.9.2006 6. 33KV Substation Bhalaut 5MVA 20 17.10.2007 Total-II 22.9 MVA 150 Total I-II 77.2 MVA 1062 III. Transmission Lines 1. T-off of 33KV Rohtak- 11.000 KM 28 10.9.2005 Madina- Meham line for Bhagwatipur

76 2. T-off from 33kV Rohtak 0.300 KM 2 30.5.2007 (132kV)-Bhalaut line to Sector 6 Rohtak 3. T-off from 33kV Kot 2.850 KM 44 10.7.2007 – Meham line for Sr.Sec. School, Rohtak 4. 33kV Kalanaur (132kV)- 11.500KM 57 25.9.2007 Baniyani line 5. 33kV line from 132 kV 15.000KM 73 27.2.2008 substation Sampla to Hasangarh 6. 33 KV line for Bal Bhawan 1.500 KM 36 8.8.2008 Rohtak 7. 33 KV line for Jindran line. 6.000 KM 45 7.11.2008 Total-III 48.150 285 Total Cost I – III 1347 K. District Jhajjar I. New Substation 1. 33KV Substation Kunjiya 8MVA 90 9.9.2005 2. 33KV Substation Bamnauli 8MVA 125 29.12.2006 3. 33KV Substation Rohad 8MVA 151 9.4.2008 Total-I 24 MVA 366 II. Augmentation 1. 33KV Substation HNG 4MVA 30 28.4.2005 Bahadurgarh 2. 33KV Substation Suriya 1.7MVA 20 19.5.2005 Roshni 3. 33KV Substation Jassour 6.3MVA 30 27.5.2005 Kheri 4. 33KV Substation Bupania 5MVA 20 22.11.2005 5. 33KV Substation.Badli 5MVA 18 10.2.2006 6. 33KV Substation Jhajjar 2.3MVA 20 26.2.2006 7. 33Kv Substation Jahajgarh 4MVA 16 10.5.2006 8. 33KV Substation Machhrauli 4MVA 40 16.8.2006 9. 33KV Substation Ladain 5MVA 20 22.1.2007 10. 33kV Substation Sasrauli 2.3MVA 15 21.4.2007 11. 33 KV Substation Bupania 6 MVA 73 20.10.08 Total-II 45.6 MVA 302 Total I-II 69.6 MVA 668 III. Transmission Lines 1. 33KV Bahadurgarh- Surya 3.500 KM 10 13.7.2005 Roshni line 33KV Bahadurgarh-Surya Roshni line 2. LILO of 33KV -Jhajjar 2.000 KM 5 9.9.2005 line for Kunjiya 3. T-off line from 33KV 4.000 KM 25 29.12.2006 Bahadurgarh–Jasour Kheri line to 33KV S/Stn. Bamnauli 4. 33kV line from 132 kV 10.000KM 52 9.4.2008 substation Sampla to Rohad 77 Total-III 19.5 92 Total Cost I – III 760 L. District Hisar

I. New Substation 1. 33KV Substation Umra 8MVA 100 6.4.2005 2. 33KV Substation Bass 10MVA 132 30.3.2008 3. 33KV Substation Nangthala 4MVA 67 27.9.2008 4. 33KV Substation Modda 10MVA 100 16.10.2008 Khera Total-I 32 MVA 399 II. Augmentation 1. 33KV Substation 4MVA 21 11.5.2005 2. 33KV Substation Arya Nagar 4MVA 19 28.5.2005 3. 33KV Substation HTM Hisar 4MVA 25 1.8.2006 4. 33KV Substation Sharwa 4MVA 40 1.12.2006 5. 33kV Substation Koth Kalan 4MVA 23 5.4.2007 6. 33KV Substation HTM Hisar 6MVA 70 16.5.2008 7. 33KV Substation Behlalpur 3.7MVA 70 28.5.2008 8. 33 KV Sub-station Sarsod 10 MVA 74 21. 8.2008 Total-II 39.7MVA 342 Total I-II 71.7 MVA 741 III. Transmission Lines 1. 33KV line from 132KV 10.000KM 20 6.4.2005 substation Hansi to 33KV substation Umra 2. 33kV Mundhal-Bass line 12.000KM 66 30.3.2008 3. T-off from existing 33 KV 10.000KM 40 27.9.2008 Adampur-Agroha line for 33 KV substation Nangthala 4. T-off from existing 33KV 10.000 KM 40 16.10.2008 Adampur-Siswal line for 33 KV substation Modda Khera Total-III 42.000KM 166 Total Cost I – III 907

M. District Fatehabad

I. New Substation 1. 33KV Substation Mohamdki 5MVA 80 9.8.2006 2. 33KV substation Hazrawan 10 MVA 122 25.8.2008 Kalan Total-I 15MVA 202 II. Augmentation 1. 33KV Substation Leharian 5MVA 17 26.5.2005 2. 33KV Substation Jakhal 1MVA 20 9.6.2005 3. 33KV Substation Bhutan 6.2MVA 32 16.6.2005 4. 33KV Substation Telewara 1MVA 13 21.6.2005 5. 33KV Substation Pirthla 4MVA 15 12.7.2005 6. 33KV Substation Bhuma 2.3MVA 11 15.7.2005

78 7. 33KV Substation Degoh 3MVA 20 17.8.2005 8. 33KV Substation Dhani Raipur 4MVA 25 12.6.2006 9. 33KV Substation Mohammadki 3MVA 19 17.9.2007 10. 33kV Substation Nehla 4MVA 10 8.4.2008 11. 33kV Substation Daryapur 3 MVA 50 12.4.2008 12. 33kV Substation Rainwali 3.7 MVA 70 7.5.2008 13. 33kV Substation Bhuna 5 MVA 70 26.5.2008 14. 33kV Substation Ayalki 3.7 MVA 70 30.5.2008 15. 33kV Substation Teliwara 1.3 MVA 15 3.7.2008 16. 33kV Substation Pirthla 5 MVA 70 26.7.2008 17. 33kV Substation Badopal 6 MVA 70 30.7.2008 18. 33kV Substation Gularwala 3.7 MVA 70 21.10.2008 19. 33kV Substation Haroli 6 MVA 70 5.11.2008 20. 33kV Substation Mehmra 5 MVA 70 15.11.2008 Total-II 75.9 MVA 807 Total I-II 90.9 MVA 1009 III. Transmission Lines 1. 33KV line from Baliala to 12.000 KM 40 9.8.2006 Mohamdki 2. T-off from 33 KV Fatehabad 9.200 KM 74 25.8.2008 –Bhattu line for 33 KV substation Hazrawan Kalan Total-III 21.200 KM 114 Total Cost I – III 1123

N. District Bhiwani I. New Substation 1. 33KV Substation Chang 8MVA 75 22.7.2005 2. 33KV Substation Serla 5MVA 70 13.4.2006 3. 33KV Substation Khanak 8MVA 80 19.5.2006 4. 33kV Substation Nandha 4MVA 57 6.2.2007 5. 33kV Substation Pataudi 10MVA 103 16.3.2008 6. 33kV Substation Kari Dhani 10MVA 132 27.3.2008 7. 33kV Substation Chhapar 10MVA 132 28.3.2008 8. 33kV Substation Singhani 10MVA 104 28.3.2008 9. 33kV Substation Siswala 10MVA 103 28.3.2008 10. 33kV Substation Kheri Batter 10MVA 98 30.5.2008 11. 33kV Substation Pichoppa 5 MVA 114 26.8.2008 kalan 12. 33kV Substation Chehar 10MVA 174 30.9.2008 Kalan 13 33kV Substation Kakroli 10MVA 132 3.11.2008 Sardara 14. 33kV Substation Mandola 10MVA 132 27.11.2008 Total-I 120 MVA 1506 II. Augmentation 1. 33KV Substation Dawarka 4MVA 19 9.3.2005 2. 33KV Substation Siwani 2.3MVA 12 11.6.2005 3. 33KV Substation Berla 5MVA 25 31.10.2005 4. 33KV Substation Kadma 5MVA 25 25.11.2005

79 5. 33KV Substation Rudrol 5MVA 25 14.1.2006 6. 33KV Substation Mithi 2MVA 15 18.1.2006 7. 33KV Substation Mandi 4MVA 25 5.6.2006 8. 33kV Substation RD-0 Bhiwani 1MVA 5 10.4.2007 9. 33kV Substation Sanjarwas 2.3MVA 41 5.7.2007 10. 33kV Substation Rudral 6MVA 57 4.1.2008 11. 33kV Substation Siwani 4 MVA 42 27.5.2008 12. 33kV Substation Nandha 10 MVA 70 24.10.2008 13. 33kV Substation Morwala 4 MVA 45 18.12.2008 Total-II 54.6MVA 406 Total I-II 174.6 MVA 1912 III. Transmission Lines 1. T-off line from 33KV line from 13.000 KM 40 22.7.2005 132KV substation Bhiwani to 33KV substation I.A. Bhiwani for Chang 2. T-off from 33KV Jui –Behal 0.070 KM 2 13.4.2006 line to Serla 3. 33KV T-off from existing 10.000 KM 35 19.5.2006 33KV line from 132KV substation Miran to at Khanak 4. 33kV Badhra-Nandha line 9.400 KM 40 6.2.2007 5. 33KV line from 132KV 2.400KM 4 20.10.2007 substation Tosham to 33kV Miran-Tosham line 6. 33kV line from 33kV 11.200KM 29 16.3.2008 substation Pataudi 7. 33kV line from 33kV 10.000KM 55 27.3.2008 substation Kari Dharni 8. 33kV line from 33kV 7.350KM 40 28.3.2008 substation Chhapar 9. 33kV line from 33kV 5.060KM 22 28.3.2008 substation Singhani 10. 33kV line from 33kV 5.500KM 32 28.3.2008 substation from Siswala 11. 33 kV line from 132kV 8.900KM 40 30.5.2008 substation Ch.Dadri-II to Kheri Batter for 33kV substation Kheri Batter 12. 33 KV line from 132 KV 6.500KM 28 26.8.2008 S/Stn. Atella Kalan to 33 KV S/Stn. Pichopa kalan 13. T-off from 33 KV Dighwan 7.000 KM 28 30.9.2008 Jattan –Nakkipur line for 33 KV substation Chehar Kalan 14. T-off from 33 KV Badhra – 7.500 KM 50 3.11.2008 Nandha-Lad line for 33 KV substation Kakroli Sardara

80 15. T-off from 33 KV Dadri-(II) – 12.600 KM 72 27.11.2008 Makrana line for 33 KV substation Mandola Total-III 116.480 KM 517 Total Cost I – III 2429 O. District Sirsa I. New Substation 1. 33KV Substation Dhani Khan 8MVA 75 21.7.2005 Singh/Titu Khera 2. 33KV Substation 8MVA 53 26.9.2005 Shahidawalik 3. 33KV Substation Risalia Khera 10MVA 102 3.1.2008 4. 33KV Substation Khuian 10MVA 102 5.1.2008 Malkana 5. 33KV Substation 8MVA 67 14.1.2008 Mohammadpuria 6. 33KV Substation Desu Jodha 10 MVA 102 21.2.2008 7. 33KV Substation Jamal 10MVA 139 27.3.2008 8. 33KV Substation Baragudha 8MVA 79 29.3.2008 9. 33KV Substation Mirzapur 8MVA 113 20.4.2008 10. 33KV Substation Kagdana 10MVA 140 21.4.2008 11. 33KV Substation Ahmadpur 8MVA 84 30.12.2008 Road, Sirsa Total-I 98 MVA 1056 II. Augmentation 1. 33KV Substation Farwian 4MVA 20 11.7.2005 2. 33KV Substation Ganga 2.3MVA 20 27.10.2005 3. 33kV Substation Panjwana 8MVA 68 15.7.2007 4. 33KV Substation Rori 4MVA 30 16.7.2007 5. 33KV Substation Kalanwali 4MVA 19 11.9.2007 6. 33KV Substation Kharia 4MVA 24 10.10.2007 7. 33KV Substation Keharwala 6.3 MVA 35 7.4.2008 8. 33kV Substation Bhuratwala 6 MVA 80 29.12.2008 Total-II 38.6MVA 296 Total I-II 136.3 MVA 1352 III. Transmission Lines 1. T-off line from existing 33KV 1.500 KM 3 21.7.2005 line to 33KV substation Madhosinghana for Titukhera 2. T-off of 33KV line from 4.500 KM 11 26.9.2005 220KV substation Sirsa- Madhosinghana line for Shahidiwali 3. T-off from existing 33KV 11.400KM 100 3.1.2008 Dabwali-Kalanwali line for 33KV substation Risalia Khera 4. T-off from existing 33KV 2.000KM 22 5.1.2008 Dabwali-Kalanwali line for 33KV substation Khuian Malkana 81 5. 33kV Jeevan Nagar- 9.500KM 41 14.1.2008 Mohammadpuria line 6. T-off from 33 kV Dabwali- 9.800KM 84 21.2.2008 Kalanwali line at Desu Jodha 7. T-off from existing 33 kV 19.400KM 172 27.3.2008 Begu-Nathusari line for 33kV substation Jamal 8. 33kV line from 132kV 7.500KM 34 29.3.2008 substation Odhan to Baragudha 9. T-off from 33kV Jiwan Nagar- 7.350KM 10 20.4.2008 Ellenabad lilne to Mirzapur 10. T-off from 33kV Beghu- 9.200KM 100 21.4.2008 Nathusari line to Kagadana 11. T-off from old 33 kV 1.3 KM 4 30.12.2008 Madhosinghana line to Ahmadpur Road, Sirsa. Total-III 83.45 KM 581 Total Cost I – III 1933 P. District Mohindergarh I. New Substation 1. 33KV Substation IA Narnaul 8MVA 80 9.5.2006 2. 33KV Substation Sehlang 8MVA 80 5.11.2007 3. 33KV Substation Budeen 10MVA 177 31.7.2008 4. 33KV Substation Majra Kalan 10MVA 177 29.8.2008 5. 33KV Substation Dholera 10MVA 130 30.8.2008 6. 33KV Substation Shobhapur 10MVA 144 23.12.2008 Total-II 56MVA 788 II. Augmentation 1. 33KV Substation Dablana 5MVA 30 13.9.2006 2. 33KV Substation Bhojawas 7.5MVA 29 18.9.2007 3. 33KV Substation Dhani Batota 2MVA 30 2.1.2008 4. 33kV Substation Kanti 5 MVA 79 12.6.2008 5. 33kV Substation Jant 5 MVA 80 2.7.2008 6. 33kV Substation Garhi 10 MVA 73 10.10.2008 Mahasar Total-II 34.5MVA 321 Total I-II 90.5MVA 1109 III. Transmission Lines 1. 33KV T-off from existing 0.040 KM 1 9.5.2006 33KV line from 220KV substation Narnaul to Dhani Bhatota at IA Narnaul 2. T-off from existing 33KV 10.000 KM 37 5.11.2007 Mohindergarh-Jant line to Sehlang 3. T-off of idle/ existing 33kV 8.500 KM 48 31.7.2008 Mohindergarh- line to 33kV substation Budeen

82 4. T-off of 33kV Mohindergarh- 2.000 KM 11 29.8.2008 Kanina line to 33kV substation Majra Kalan 5. T-off from existing 33kV 9.800 KM 34 1.2.2008 Narnaul-Dhani Batota line to Dholera 6. T-off from existing 33kV 9.800 KM 34 30.8.2008 Narnaul-Dhani Batota line to Dholera 7. T-off of 33kV Narnaul-Dhani 9.400 KM 45 23.12.2008 Batota line to 33 MVA substation Shobhapur. Total-III 49.540 KM 210 Total Cost I – III 1319

Q. District Rewari I. New Substation 1. 33kV Substation Bisowa 5MVA 69 8.7.2007 2. 33kV Substation Ahrod 10 MVA 199 28.2.2008 3. 33kV Substation S-10 Rewari 10MVA 135 9.6.2008 4. 33KV substation Kaluwas 10MVA 131 12.8.2008 5. 33KV substation Beharampur 10MVA 176 25.8.2008 Total-I 45MVA 710 II. Augmentation 1. 33KV Substation JC-II Jathusana 3MVA 28 28.4.2005 2. 33KV Substation JC-I Gudiani 5MVA 25 26.9.2005 3. 33KV Substation Khol 5MVA 30 3.10.2006 4. 33KV Substation Bharwas 4MVA 25 19.10.2006 5. 33KV Substation Gudiani 4MVA 25 20.10.2006 6. 33kV Substation Model Town 2.3MVA 57 28.1.2008 Rewari 7. 33kV Substation Bishowa 5 MVA 31 13.3.2008 8. 33kV Substation Model Town 5 MVA 63 25.7.2008 Rewari 9. 33kV Substation Khol 5 MVA 71 27.8.2008 10. 33kV Substation Khushpura 5 MVA 70 8.9.2008 Total-II 43.3MVA 425 Total I-II 88.3MVA 1135 III. Transmission Lines 1. 33kV line for Bishowa 9.500 KM 45 8.7.2007 2. T-off from existing substation 33 6.000KM 26 28.2.2008 kV from Buroli-Khol line to Ahrod 3. 33kV line from 220kV 1.000KM 4 9.6.2008 substation Rewari making T- off from 33kV Rewari- Jonawas line to S-10 Rewari 4. T-off from 33 kV Rewari – 2.500KM 11 12.8.2008 Bharawasl line to Kaluwas. 5 33kV line from 132 kV Kosli to 12.000 KM 66 25.8.2008 33 KV substation Behrampur Total-III 31.000KM 152 Total Cost I – III 1287 83 R. District Mewat I. New Substation - - II. Augmentation 1. 33KV Substation Ferozpur 1MVA 21 20.6.2005 Zhirka 2. 33KV Substation 4MVA 22 5.10.2005 Rozkameo 3. 33KV Substation Pinagwa 4MVA 20 10.5.2006 4. 33KV Substation Pingawa 6MVA 68 7.2.2008 Total-II 15MVA 131 Total I-II 15MVA 131 III. Transmission Lines - - Total Cost I – III 131 S. District Gurgaon I. New Substation - - II. Augmentation - - III. Transmission Lines Total Cost I – III - T. District Faridabad I. New Substation - - II. Augmentation - - III. Transmission Lines - - Total Cost I – III -

84

ANNEXURE – II

DISTRICT-WISE DETAIL OF APPROVED 33kV NEW SUBSTATIONS, AUGMENTATION OF EXISTING SUBSTATIONS AND TRANSMISSION LINES UNDER CONSTRUCTION / TO BE CONSTRUCTED Sr. Name of Sub-station Capacity in Cost Completion MVA / (Rs. In schedule Line in Km Lacs) A. I. New Substations 1. 33 KV Substation Jaitpura 10 150 2008-09 Total-I 10 150 II. Augmentation -- Total-II -- III. Transmission Lines 1. 33 KV line for Jaitpura 10 50 2008-09 Total-III 10 50 Total (I+II+III) 200 B. I. New Substations - - Total I -- II. Augmentation -- Total II -- III. Transmission Lines - - Total III -- Total (I+II+III) - - C. I. New Substations - - Total I -- II. Augmentation 1. 33 KV Substation Budhkalan 3 80 2008-09 Total II 3 80 III. Transmission Lines 1. 33 KV line from 66 KV 18 126 2008-09 Substation Yamuna nagar to Budhkalan Total III 18 126 Total (I+II+III) 206 D. Kurukshetra District I. New Substations 1. 33 KV Substation Bagthala 8 170 2008-09 2. 33 KV Substation Sandhola 8 177 2008-09 3. 33 KV Substation KDB Brahm 10 185 2009-10 Sarovar 4. 33 KV substation Sector 4, KKR 8 122 2009-10 5. 33 KV substation Bodla 10 220 2009-10 6. 33 KV Substation Sirsala 16 250 2009-10 7. 33 KV substation Bhusthala 20 300 2009-10

85 Total I 80 1424

II. Augmentation 1. 33kV substation Jhansa Road 6.0 80 2008-09 Kurukshetra. 2 33kV substation K.U. 7.4 160 2008-09 Kurukshetra Total II 13.4 240 III. Transmission Lines 1. 33 KV line for Bagthala 5 25 2008-09 2. 33 kV line for Sandhola 4 20 2008-09 3. 33 KV line KDB Brahm Sarovar 1.25 8 2009-10 4. 33 KV line Sector 4, Kurukshetra 1.5 8 2009-10 5. 33 KV line Bodla 6 35 2009-10 6. 33 KV line Sirsala 5 105 2009-10 7. 33 KV line Bhusthala 0.2 1 2009-10 Total III 22.95 202 Total (I+II+III) 1866 E. New Substations 1 33KV substation Deeg 10 187 2009-10 2 33 KV substation Barsana 10 155 2008-09 3 33 KV Substation Neemwala 10 165 2009-10 4 33 KV Substation Sirta 10 160 2009-10 5 33 KV Substation Deora 14.3 210 2009-10 6 33 KV Substation Lander 20 300 2009-10 Keema 7 33 KV Substation Harnola 10 220 2009-10 8 33 KV Substation Budha Khera 10 220 2009-10 9 33 KV Substation Sisla Sismore 10 220 2009-10 10 33 KV Substation Kheri Rai wali 10 220 2009-10 11 33 KV Substation Kathwar 10 220 2009-10 12 33 KV Substation Jagdishpura 10 220 2009-10 13 33 KV Substation Mandi 16 250 2009-10 Sadhran 14 33 KV Substation Chandana 10 220 2009-10 15 33 KV Substation Kutubpur 10 220 2009-10 Total I 170.3 3187 II. Augmentation 1. 33 KV Substation Pharal 3 40 2009-10 2. 33 KV Substation Kwartan 6 80 2009-10 3. 33 KV Substation Siwan gate 4 70 2009-10 Kaithal 4. 33 KV Substation P.C. Kaithal 10 80 2009-10 Total II 23 270 III. Transmission Lines 1 33KV line for Deeg 5.5 28 2009-10 2 33 KV line Barsana 9 45 2008-09 3 33 KV line Neemwala 7.5 40 2009-10 4 33 KV line Sirta 11 50 2009-10 86 5 33 KV line Deora 6 30 2009-10 6 33 KV line Lander Keema 7 49 2009-10 7 33 KV line Harnola 8 56 2009-10 8 33 KV line Budha Khera 5 35 2009-10 9 33 KV line Sisla Sismore 7 49 2009-10 10 33 KV line Kheri Rai wali 9 63 2009-10 11 33 KV line Khatwar 8 56 2009-10 12 33 KV line Jagdishpur 13 91 2009-10 13 33 KV line Mandi Sadhran 3 21 2009-10 14 33 KV line Chandana 6 42 2009-10 15 33 KV line Kutubpur 9 63 2009-10 Total III 114 718 Total (I+II+III) 4175 F. I. New Substations 1 33 KV Substation Dabarthala 8 170 2009-10 2 33 KV Substation Raipur Jattan 10 180 2009-10 3 33 KV Substation Barota 10 155 2009-10 4 33 KV Substation Kaimla 10 170 2009-10 5 33 KV Substation Kalram 10 170 2009-10 6 33 KV Substation Shahpur 10 118 2009-10 7 33KV Substation Gularpur 8 107 2009-10 8 33KV Substation Rindle 10 220 2009-10 9 33KV Substation Chochra 10 220 2009-10 10 33KV Substation Dadlana 10 220 2009-10 11 33KV Substation Shekhupura 10 220 2009-10 Total I 106 1950 II. Augmentation 1 33 KV Sub station Rahra 8 70 2008-09 2 33 KV Sub station Dachar 6 80 2008-09 3 33 KV Sub station Ramba 4 180 2008-09 4 33 KV Sub station Shamgarh 8 70 2008-09 5 33 KV Sub station Jamba 10 90 2008-09 Total II 36 490 III. Transmission Lines 1 33 KV line Dabarthala 7 30 2009-10 2 33 KV line Raipur Jattan 4.6 25 2009-10 3 33 Kv line Barota 9 45 2009-10 4 33 KV line Kaimla 6 30 2009-10 5 33 KV line Kalram 6 30 2009-10 6 33 KV line Shahpur 12 68 2009-10 7 33 KV line Gularpur 7.5 44 2009-10 8 33 KV line Rindle 8.5 59.5 2009-10 9 33 KV line Chochra 12.5 87.5 2009-10 10 33 KV line Dadlana 7.5 59.5 2009-10 11 33 KV line Shekhupra 5.5 38.5 2009-10 Total III 86.1 517 Total (I+II+III) 2957 G. I. New Substations 87 1 33 KV Substation Jalalpur 10 220 2009-10 2 33KV Substation Babarpur 8 200 2009-10 3 33KV Substation Mandi 20 300 2009-10 Total I 38 720 II. Augmentation 1. 33KV Substation Naraina 10 160 2009-10 Total II 10 160 III. Transmission Lines 1. 33 KV line Jalalpur 8 56 2009-10 2. 33 KV line Babarpur 2.5 18 2009-10 3. 33 KV line Mandi 8 56 2009-10 4. 33 KV line Naraina 11 55 2009-10 Total III 29.5 185 Total (I+II+III) 1065 H. I. New Substations 1. 33 KV substation Shamdo 8 150 2008-09 2. 33 KV substation Songri Guliana 10 150 2008-09 Total I 18 300 II. Augmentation 1. 33KV substation 6 40 2008-09 2. 33KV substation Pindara 7 160 2008-09 Total II 13 200 III. Transmission Lines 1. 33 KV line Shamdo 12 55 2008-09 2. 33 KV line Songri Guliana 15 60 2008-09 Total III 27 115 Total (I+II+III) 615 I. I. New Substations 1. 33KV substation Bhogipur 8 150 2008-09 2. 33KV substation Bichpari 10 178 2008-09 3. 33 KV substation Sisana 8 160 2008-09 4. 33 KV substation Sikanderpur 8 200 2009-10 Majra 5. 33 KV substation Umedgarh 10 220 2009-10 6. 33 KV substation Rajpur 10 220 2009-10 7. 33 KV substation BPSMU 10 220 2009-10 Khanpur Kalan Total I 64 1348 II. Augmentation 1. 33KV substation 3 30 2008-09 Total II 3 30 III. Transmission Lines 1. 33KV line for Bhogipur 12 60 2008-09 2. 33KV line for Bichpari 15.5 77 2008-09 3. 33 KV line Sisana 8 40 2008-09 4. 33 KV line Sikanderpur Majra 18 126 2009-10 5. 33 Kv line Umedgarh 12 84 2009-10 6. 33 KV line Rajpur 10 70 2009-10 88 7. 33 KV line BPSMU Khanpur 10 70 2009-10 Kalan Total III 85.5 527 Total (I+II+III) 1905 J. I. New Substations 1. 33KV substation Ritauli 10 180 2008-09 2. 33KV substation Kherawer 8 160 2008-09 3. 33 KV substation Grain Market 10 220 2009-10 Rohtak 4. 33 KV substation OPH Rohtak 10 220 2009-10 Total I 38 780 II. Augmentation 1. 33 KV Substation Madina 4 32 2008-09 Total II 4 32 III. Transmission Lines 1. 33KV line for Ritauli 4 20 2008-09 2. 33KV line for Kherawer 10 50 2008-09 3. 33 KV line Grain Market Rohtak 2.5 17.5 2009-10 4. 33 KV line OPH Rohtak 2.3 20 2009-10 Total III 18.8 107.5 Total (I+II+III) 919.5 K. I. New Substations 1. 33KV substation Dighal 8 150 2008-09 2. 33KV substation Dubal Dhan 8 160 2008-09 3. 33 KV substation Sampla Rd Jhajjar 8 128 2008-09 4 33 KV substation Kaloi 8 200 2009-10 Total I 32 638 II. Augmentation Total II - - III. Transmission Lines 1. 33KV line for Dighal 12 60 2008-09 2. 33KV line for Dubal Dhan 10 50 2008-09 3. 33 KV line for Sampla Road, 6 30 2008-09 Jhajjar 4. 33 KV line for Kaloi 10 70 2009-10 Total III 38 210 Total (I+II+III) 848 L. I. New 33KV Substations 1 33KV substation Thurana 10 150 2009-10 2. 33KV substation Budana 10 150 2009-10 3. 33KV substation Bithmara 10 150 2009-10 Total-I 30 450 II. Augmentation 1. 33KV substation Vidyut Nagar 4 40 31.3.2009 Hisar 2. 33KV substation Agroha 5 50 31.3.2009 3. 33KV substation Rajgarh Road 8 62 2009-10 89 Total-II 17 152 III. Transmission Lines 1 33KV line for Thurana 13 47 2009-10 2 33KV line for Budana 5 18 2009-10 3 33KV line for Bithmara 10 50 2009-10 Total-III 28 115 Total (I+II+III) 717 M. Fatehabad District I. New Substations 1. 33KV substation Jamalpur 10 130 31.3.2009 Shakho 2. 33kV substation Bhirdana 8 120 15.6.2009 3. 33KV substation Kamana 8 140 15.6.2009 4. 33KV substation Alalwas 8 140 15.6.2009 5. 33KV substation Nanheri 8 140 15.6.2009 6. 33KV substation Chando Khurd 10 150 2009-10 Total-I 52 820 II. Augmentation 1. 33KV substation Gandha 1.3 20 31.3.2009 Total-II III. Transmission Lines 1. 33KV line for Jamalpur Shekho 0.08 1 31.3.2009 2. 33KV line for Bihrdana 0.5 3 15.6.2009 3. 33KV line for Kamana 0.21 1 15.6.2009 4. 33KV line for Alalwas 12 60 15.6.2009 5. 33KV line for Nanheri 7.5 38 15.6.2009 6. 33KV line for Chando khurd 8.0 29 Total-III 28.29 132 Total (I+II+III) 972 N. I. New Substations 1 33KV substation Barlau 10 130 28.2.2009 2 33KV substation Hassan 10 130 28.2.2009 3 33KV substation Alampur 10 130 31.3.2009 4 33KV substation Bapora 10 130 15.2.2009 5 33kV substation Budhera 10 130 31.3.2009 6 33 KV Substation Baganwala 10 150 2009-10 7 33 KV Substation Pinjokhera 10 150 2009-10 8 33 KV Substation Mandoli Khurd 10 150 15.6.2009 9 33 KV Substation Gopalwas 10 150 15.6.2009 10 33 KV Substation Bhera 10 150 15.6.2009 11. 33 KV Substation Nangla 10 150 2.9.2009 12 33 KV Substation Pokharwas 10 150 2.9.2009 Total-I 120 1700 II. Augmentation 1 33 KV Substation Mithi 4 40 31.3.2009 2. 33 KV Substation Khanak 10 70 31.3.2009 3. 33 KV Substation Nakkipur 5 50 31.3.2009 4. 33 KV Substation Bawani Khera 6 60 31.3.2009 Total-II 25 220

90 III. Transmission Lines 1 33KV line for Barlau 15 75 28.2.2009 2 33KV line for Hassan 12 60 28.2.2009 3 33KV line for Alampur 8 40 31.3.2009 4 33KV line for Bapora 2.5 13 15.2.2009 5 33KV line for Budhera 8 40 31.3.2009 6 33 KV line for Baganwala 4 20 2009-10 7 33 KV line for Pinjokhera 7 35 2009-10 8 33 KV line for Mandoli Khurd 15 75 15.6.2009 9 33 KV line for Gopalwas 7.5 38 15.6.2009 10 33 KV line for Bhera 7.5 38 15.6.2009 11 33 KV line for Nangla 8 39 2.9.2009 12 33 KV line for Pokharwas 7 38 2.9.2009 Total-III 101.5 511 Total (I+II+III) 2443 O. I. New Substations 1 33KV substation Kuttabadh 10 130 15.6.2009 2 33kV substation Panihari 8 120 15.6.2009 3 33 KV Substation Pipli 10 150 2009-10 4 33 KV Substation Khokhar 10 150 2009-10 5 33 KV Substation Bansudhar 10 150 15.6.2009 6 33 KV Substation Haripura 10 150 2.9.2009 7 33 KV Substation Mastangarh 10 150 2.9.2009 8 33 KV Substation Dholpalia 10 150 2.9.2009 Total-I 78 1150 II. Augmentation 1. 33 KV Substation Panjuana 3.7 70 31.3.2009 2. 33 KV Substation Rori 5 70 31.3.2009 Total-II 8.7 140 III. Transmission Lines 1 33KV line for Kuttabadh 5.2 26 31.3.2009 2 33KV line for Panihari 6.54 33 31.3.2009 3 33KV line for Pipli 9 45 2009-10 4 33KV line for Khokhar 16 80 2009-10 5 33KV line for Bansudhar 7.5 38 31.3.2009 6 33 KV line for Haripura 0.3 1.1 2.9.2009 7 33 KV line for Mastangarh 0.1 0. 4 2.9.2009 8 33 KV line for Dholpalia 19 70 2.9.2009 Total-III 63.64 293.5 Total (I+II+III) 1583.5 P. Mohindergarh District I New Substations 1 33KV substation Khudana 8 120 15.6.2009 2 33KV substation Lehroda 10 130 31.3.2009 3 33kV substation Bhungharka 10 130 15.6.2009 4 33kV substation Bhilwara 10 130 15.6.2009 5 33 KV Substation Satnali Bass 10 150 15.6.2009 6 33 KV Subsatation Bazar 10 150 15.6.2009 Total-I 58 810 91

II. Augmentation - - Total-II - - III. Transmission Lines 1 33KV line for Khudana 17.3 61 15.6.2009 2 33KV line for Lehroda 0.5 2 31.3.2009 3 33KV line for Bhungaraka 8.5 30 15.6.2009 4 33KV line for Bhilwara 10 35 15.6.2009 5 33KV line for Satnali Bass 2.5 13 15.6.2009 6 33KV line for Bazar 10 50 15.6.2009 Total-III 48.8 191 Total (I+II+III) 1001 Q. Rewari District I. New Substations 1. 33KV substation Gurawara 8 120 31.3.2009 2. 33kV substation Nangal Pathani 10 150 2009-10 Total-I 18 270

II. Augmentation - - Total-II - - III. Transmission Lines 1. 33KV line for Gurawara 7 25 31.3.2009 2. 33KV line for Nangal Pathani 1.5 8 2009-10 Total-III 8.5 33 Total (I+II+III) 303 R. Gurgaon District I. New Substations - - II. Augmentation - - III. Transmission Lines - - Total (I+II+III) - - S. Mewat District I. New Substations 1 33 KV Substation Bahin 10 150 15.6.2009 Total-I 10 150 II. Augmentation - - 1 33 KV Substation Bhadas 2 20 31.3.2009 Total-II 2 20 III. Transmission Lines 1 33 KV line for Bahin 14 70 15.6.2009 Total-III 14 70 Total (I+II+III) 240 I. I. New Substations -- II. Augmentation - - III. Transmission Lines - - Total (I+II+III) -

92 ANNEXURE – III

District wise 220KV/132KV/66KV New Substations commissioned/ augmented and Transmission Lines added from March 2005 to December 2008.

Sr. Name of Sub-station Capacity Cost Date of added in MVA (Rs.In Lacs) Commissioning Line in Km. A. District Ambala I. New Substation 1. 66KV Substation Sonda 16MVA 248 24.3.2006 Total-I 16MVA 248 II. Augmentation 1. 220kV Substation Tepla 100MVA 250 19.5.2006 2. 66KV Substation Adhoya 6MVA 45 2.6.2006 3, 66KV Substation Barnala 8MVA 65 29.7.2006 4. 66KV Substation Barnala 8MVA 51 4.4.2007 5. 66kV Substation Barwala 8MVA 97 6.7.2007 6. 66kV Substation Mullana 8MVA 133 12.1.2008 7. 66kV Substation Sonda 16MVA 253 6.11.2008 Total- II 154MVA 894 Total I- II 170MVA 1142 III. Transmission Lines 1. 66KV D/C Dukheri- Layalpur 20.597KM 125 25.7.2005 Basti line 2. LILO of one Ckt of 66KV D/C 3.227 KM 56 23.3.2006 Dukheri-Layalpur Basti line at 66KV substation Sonda Total-III 23.824 KM 181 - Total Cost I – III 1323 B. District Panchkula

I. New Substation - - - II. Augmentation 1. 220KV Substation Madanpur 8.5 MVA 96 3.3.2005 2. 66KV Substation 7.5MVA 45 7.6.2006 3. 66kV Substation Sector 1 16MVA 265 23.5.2007 Panchkula 4. 66kV Substation Sector 3 16MVA 256 20.6.2007 Panchkula 5. 66kV Substation I.A. 16MVA 275 19.5.2008 Panchkula Total-II 64MVA 937 Total I – II 64MVA 937 - III. Transmission Lines - - Total-III -- - Total Cost I – III 937

93

C. District Yamunanagar I. New Substation 1. 66KV Substation Gulab 16MVA 354 10.8.2006 Nagar Total-I 16MVA 354 II. Augmentation 1. 220KV Substation Jorian 100MVA 767 14.8.2008 Yamunanagar 2. 66KV Substation Radaur 10MVA 84 19.3.2005 3. 66KV Substation 6MVA 45 17.1.2006 Yamunanagar 4. 66KV Substatiion 3.5MVA 35 15.5.2006 Chhachharoli 5. 66kV Substation Basantpur 10MVA 51 12.5.2007 6. 66KV Substation Jathalana 8MVA 270 29.12.2008 Yamunanagar Total-II 137.5MVA 1252 Total I – II 153.5MVA 1606 III. Transmission Lines 1. 220kV D/C YTPP-Jorian 10.900KM 677 11.10.2007 (Yamunanagar) line 2. 66KV S/C Yamunanagar- 16.571KM 113 26.72005 Radaur line at 220KV substation Yamunanagar 3. 66KV S/C line from 220KV 4.500KM 45 10.8.2006 substation Khera to 66KV substation Gulab Nagar 4. 66KV S/C Yamunanagar 18.320KM 266 30.12.2006 (Jorian) – Radaur line 5. 66kV S/C line from PH-C to 4.000 KM 100 8.3.2007 PH-B Total-III 54.291 KM 1201 Total Cost I – III 2807 D. District Kaithal I. New Substation 1. 132KV Substation Rasina 16MVA 300 30.5.2006 2. 132KV Substation Nautch 25MVA 600 24.4.2008 3. 132KV Substation Rajaund 16MVA 450 30.4.2008 4. 132KV Substation Dhand 16MVA 600 23.12.2008 Total-I 73MVA 1950 II. Augmentation 1. 220KV Substation Kaithal 50MVA 380 17.7.2006 2. 132KV Substation Kaithal 16MVA 103 6.7.2007 3. 132KV Substation Pai 16 MVA 171 2.2.2008 4. 132KV Substation Rajaund 16MVA 150 5.5.2008 5. 132KV Substation Padla 25MVA 200 21.8.2008 6. 132KV Substation Bhagal 25MVA 286 31.12.2008 Total-II 148MVA 1290

94 Total I-II 155MVA 3240 III. Transmission Lines 1. 2ND Ckt. Of 220KV Kaithal- 14.180 KM 243 22.3.2006 Cheeka line for 400KV substation Kaithal to terminal tower at 220KV substation Kaithal 2. 2nd Ckt. Of 220KV Kaithal- 37.060 KM 283 4.1.2007 Cheeka line from 400KV PGCIL substation Kaithal to 220KV substation Cheeka 3. 132KV Nissing-Rasina line 14.795 KM 181 29.5.2006 4. LILO from 132KV S/C 4.284KM 165 6.12.2007 Kaithal-Thana line to 132KV substation Nautch 5. 132Kv S/C Kaithal – Rajaund 19.805 KM 250 27.4.2008 line 6. 132Kv S/C – Dhand 11.405 196 15.12.2008 line Total III 101.529KM 1318 Total Cost I – III 4558 E. District Kurukshetra I. New Substation 1. 220kV substation Salempur 100MVA 2000 7.1.2008 2. 220kV substation Durala 100MVA 2800 30.10.2008 3. 66KV Substation Jalkheri 16MVA 170 13.12.2005 4. 66KV Substation Gangori 7.5MVA 335 16.6.2006 5. 66KV Substation Mathana 16MVA 350 4.3.2008 6. 66KV Substation Lohara 16MVA 500 2.5.2008 Total-I 165.5MVA 6155 II. Augmentation 1. 220KV Substation Salempur 100MVA 500 27.5.2008 16MVA 15.5.2008 2. 220KV Substation Durala 100MVA 249 15.12.2008 16MVA 3. 132KV Substation Thana 9MVA 84 20.5.2005 4. 132Kv Substation Bhore 16NVA 108 16.9.2005 5. 132kV Substation Malikpur 16MVA 179 5.3.2007 6. 66KV Substation Nalvi 8MVA 59 8.4.2005 7. 66kV Substation Gangori 16MVA 277 3.5.2007 8. 66kV Substation Mathana 16MVA 237 18.7.2008 9. 66kV Substation Lohara 16MVA 181 18.9.2008 Total-II 329MVA 1874 Total I-II 494.5MVA 8029 III. Transmission Lines 1. 220KV D/C Nissing-Salempur 41.000 KM 1498 6.10.2006 line 2. 220KV D/C YTPP-Salempur 39.408KM 1250 7.1.2008 line (Ckt.-I)

95 3. LILO of 1st Ckt.220KV 2.812KM 135 27.10.2008 Pehowa-Shahbad line at 220KV substation Durala 4. 66KV S/C line from existing 4.400 KM 40 13.12.2005 TL-16 of Shahbad –Yara S/C line on D/C towers for 66KV substation Jalkheri 5. Stringing of 2nd circuit of 66KV 2.200 KM 8 13.12.2005 Shahbad –Yara line on D/C towers up to TL No.16 & 17 6. 66KV S/C Jorian 18.400 KM 114 15.6.2006 (Yamunanagar)-Gangori line 7. 66KV S/C Salempur – 7.000 KM 100 22.12.2006 Mathana line on D/C tower 8. 66KV D/C Salempur-Lohara line 11.000 KM 100 22.12.2006 9. 66kV D/C Salempur- line 12.000 KM 100 22.12.2006 10. Stringing of 2nd Ckt 66kV line 8.000 KM 68 30.7.2007 between 220kV Substation Shahbad to T-off point on D/C tower and construction of S/C line from T-off point to Nalvi Total III 146.22 KM 3413 Total Cost I – III 11442 F. District Karnal I. New Substation - - 1. 220KV Substation Unispur 100MVA 2500 5.7.2008 (Nilokheri) 100MVA 31.7.2008 16MVA 8.7.2008 Total-I 216MVA 2500 II. Augmentation 1. 132KV Substation Assandh 25MVA 157 14.8.2005 2. 132KV Substation Newal 20MVA 300 14.5.2007 3. 132KV Substation Sagga 25MVA 286 11.12.2008 Total-II 70MVA 743 Total I –II 286MVA 3243 III. Transmission Lines 1. 220kV S/C Nilokheri-Karnal 19.465 KM 400 23.4.2008 line 2. 132KV S/C Sagga–Amin line 17.192 KM 248 31.5.2005 3. LILO of 132KV S/C Nilokheri- 0.984KM 44 26.11.2008 Amin line at 220KV substation Nilokheri Total-III 37.641 KM 692 Total Cost I – III 3935 G. District Panipat I. New Substation -- II. Augmentation 1. 132KV Substation Matloda 25MVA 185 15.9.2005 2. 132KV Substation Chhajpur 16MVA 113 30.9.2005 3. 132KV Substation Matloda 25MVA 200 23.11.2007 Total-II 66MVA 498 96 Total I – II 66MVA 498 - III. Transmission Lines --

Total Cost I-III 498 H District Jind I. New Substation 1. 132KV Substation Julana 16MVA 347 11.4.2005 2. 132Kv Substation Naguran 32MVA 700 30.5.2007 3. 132Kv Substation Dhanori 16MVA 700 12.7.2007 4. 132Kv Substation Alewa 16MVA 900 2.6.2008 Total-I 80MVA 2647 II. Augmentation 1. 132KV Substation Uchana 12.5MVA 65 20.4.2005 2. 132Kv Substation Damtan 16MVA 200 30.3.2007 Sahib 3. 132KV Substation Uchana 12.5MVA 400 29.10.2007 4. 132KV Substation Kheri Taloda 25 MVA 258 4.4.2008 5. 132KV Substation Dhanauri 16MVA 150 8.4.2008 6 132KV Substation Alewa 25MVA 150 22.7.2008 7. 132KV Substation Narwana (Old) 16MVA 363 22.7.2008 8. 132KV Substation Dhanauri 25MVA 273 18.10.2008 Total-II 148MVA 1859 Total I-II 228MVA 4506 III. Transmission Lines 1. 220KV D/C Jind-Hisar line 61.000 KM 1425 6.4.2005 2. 220KV D/C Jind-Safidon line 45.000 KM 783 12.8.2006 3. 132KV S/C Jind-Julana line 25.000 KM 193 11.4.2005 4. 132Kv S/C Jind (220Kv)- 14.037 KM 203 29.5.2007 Naguran line` 5. 132Kv S/C Garhi-Dhanori line 8.000 KM 155 3.7.2007 6. 132kV S/C Naguran-Alewa 8.775 KM 172 5.2.2008 line Total-III 161.812 KM 2931 Total Cost I – III 7437 I District Sonepat I. New Substation - - II. Augmentation 1. 220KV Substation Sonepat 100MVA 295 11.11.2005 2. 220KV Substation Sonepat 16MVA 294 18.9.2008 3. 132KV Substation Rai 20MVA 168 28.3.2005 Total-II 136MVA 757 Total I-II 136MVA III. Transmission Lines 1. 2nd Ckt. Of 220KV PTPP – 50.440KM 544 17.8.2005 Sonipat line 2. LILO of 132KV Sewah- 0.240KM 34 7.9.2006 Ganaur-Sonipat line at 220KV substation Sonipat

97 3. LILO line from132KV Sonipat- 1.774KM 100 23.11.2007 Rai line at 132KV substation HSIDC Rai Total-III 52.454 KM 678 Total Cost I – III 1435

J. District Rohtak I. New Substation - - 1. 132Kv Substation Sector 3, 16MVA 950 24.8.2007 Rohtak 2. 132Kv Substation Jassia, 41MVA 780 6.9.2008 Rohtak Total-I 57MVA 1730 II. Augmentation 1. 220kV Substation Rohtak 50MVA 150 8.2.2006 2. 220kV Substation Rohtak 50MVA 485 30.6.2006 3. 220kVSubstation Rohtak 16MVA 175 20.7.2006 4. 132kV Substation Kalanaur 9MVA 300 9.7.2007 5. 132kV substation Sampla 25MVA 315 5.12.2007 6. 132kV substation Sector- 3 Rohtak 25MVA 200 26.5.2008 Total-II 175MVA 1625 Total I-II 232MVA 3355 III. Transmission Lines 1. 2nd Ckt. Of 220KV TDLTPS – 62.500 KM 388 1.8.2005 Rohtak D/C line 2. LILO arrangement of 132kV 0.500 KM 100 6.8.2007 S/C Rohtak-Sonepat line at 132kV substation Sector 3 Rohtak 3. LILO of 132kV Rohtak- 0.500 KM 24 5.9.2008 Mundlana line at 132kV substation Jassia Total-III 63.500 KM 512 Total Cost I – III 3867 K. District Jhajjar I. New Substation 1. 220KV Substation 100MVA 1900 27.7.2006 Bahadurgarh 16MVA 2. 132KV Substation MIE 16MVA 460 25.8.2006 Bahadurgarh Total-I 132MVA 2360 II. Augmentation 1. 220kV Substation Nunamajra 100MVA 243 8.6.2007 Bahadurgarh 2. 132KV Substation 5MVA 112 31.8.2005 Bahadurgarh 3. 132KV Substation 5MVA 20 15.9.2005 Bahadurgarh 4. 132KV Substation Jhajjar 20MVA 282 5.4.2006 5. 132KV Substation MIE 20 MVA 197 15.2.2008 Bahadurgarh 98 6. 132KV Substation Jhajjar 5MVA 350 1.4.2008 5MVA 25.4.2008 7. 132KV Substation 4.5MVA 187 16.4.2008 8. 132KV Substation Bahu 16MVA 250 30.9.2008 Total-II 180.5MVA 1641 Total I-II 312.5MVA 4001 III. Transmission Lines 1. 220KV D/C line from 220KV 46.500 KM 1474 27.7.2006 substation Bahadurgarh to 220KV substation Rohtak 2. 220KV D/C line from 400KV 3.000 KM 154 7.10.2006 substation PGCIL Bahadurgarh to 220KV substation Nuna Majra Bahadurgarh 3. 132KV LILO line from 132KV 2.500 KM 69 1.6.2006 Jhajjar-Bahadurgrh line at 220KV substation Bahadurgarh 4. 132KV S/C line from 220KV 11.178 KM 161 23.8.2006 substation Bahadurgarh to 132KV MIE Part-A substation Bahadurgarh 5. LILO of 132KV 132KV S/C 2.500 KM 69 30.8.2006 Bahadurgarh-Jhajjar line at 220KV substation Bahadurgarh 6. 132kV S/C Jhajjar-Beri line 21.00 KM 430 4.2.2008 Total-III 86.678 KM 2357 Total Cost I – III 6358 L. District Hisar I. New Substation 1. 132kV Substation Barwala 20MVA 670 30.6.2007 2. 132kV Substation Khedar 20MVA 450 12.12.2008 20MVA 14.12.2008 Total-I 60MVA 1120 II. Augmentation 1. 132kV Substation Beer 16MVA 240 27.2.2007 2. 132kV Substation Barwala 16MVA 250 4.7.2007 Total-I 32MVA 490 Total I-II 92MVA 1610 III. Transmission Lines 1. 2ND Circuit for TL No.127 of 1.500 KM 19 26.7.2007 220kV Hisar-Narwana line to shift to Hisar-Sangrur line (Ckt-II) 2. 2nd Circuit of 220kV BBMB-IA 1.543 KM 415 3.8.2007 Hisar line 3. 132kV S/C Uklana-Barwala 12.500 KM 256 28.6.2007 line 4. 132kV Barwala – Khedar S/C 9.200 KM 385 3.12.2008 line on D/C towers Total-III 24.743 KM 1075 Total Cost I – III 2685

99 M. District Fatehabad I. New Substation 1. 220kV substation Bhuna 100MVA 2200 14.10.2008 8 MVA 17.10.2008 2. 132KV Substation Teliwara 36MVA 667 31.1.2007 3. 132KV Substation Bhattu Kalan 32MVA 370 12.3.2008 Total-I 176MVA 3237 II. Augmentation 1. 220KV Substation Fatehabad 100MVA 295 31.3.2006 2. 132KV Substation Dharsul 16MVA 140 12.5.2006 Total-II 116MVA 435 Total I-II 292MVA 3672 III. Transmission Lines 1. LILO of 220KV Narwana- 7.992KM 329 12.10.2008 Fatehabad S/C line at 220KV substation Bhuna 2. LILO of 220KV Narwana- 1.200KM 46 25.11.2008 Fatehabad & Fatehabad- Sirsa line at 400KV PGCIL substation Matana (Fatehabad) 3. LILO of 132KV Dharsul-Ratia 2.000 KM 160 31.1.2007 line at 132KV substation Teliwara 4. 132kV Fatehabad – Bhattu 15.300 KM 288 10.3.2008 Kalan line Total-III 26.492 KM 823 Total Cost I – III 4495 N. District Bhiwani I. New Substation - - II. Augmentation 1. 220KV Substation Bhiwani 16MVA 240 31.5.2008 2. 132KV Substation Jhojju 16MVA 113 15.7.2005 Kalan 3. 132KV Substation 8MVA 95 15.12.2005 4. 132KV Substation IA Bhiwani 16MVA 103 9..3.2006 5. 132KV Substation Loharu 8MVA 124 15.9.2006 6. 132kV Substation Dadri-I 8MVA 240 27.2.2007 7. 132kV Substation Tosham 25MVA 300 19.6.2007 8. 132kV Substation Dadri-II 18MVA 187 5.5.2008 31.5.2008 Total-II 115MVA 1402 Total I-II 115MVA 1402 III. Transmission Lines - - 1. 132kV Isherwal-Miran line 10.712 222 26.5.2008 2. 132kV Isherwal-Behal line 19.260 375 27.5.2008 3. 132kV Isherwal- 21.59 500 30.5.2008 Tosham line 5 Total-III 51.567KM 1097 Total Cost I – III 2499 100 O. District Sirsa I. New Substation - - II. Augmentation 1. 220kV Substation Rania 100MVA 370 16.4.2007 2. 132KV Substation Jeevan Nagar 8MVA 116 18.3.2005 3. 132kV Substation Shahpur Begu 16MVA 150 30.4.2005 4. 132kV Substation 16MVA 240 25.12.2006 Madhosinghana 5. 132kV Substation Ramnagaria 16MVA 240 29.12.2006 6. 132kV Substation Shahpur Begu 16MVA 240 11.1.2007 7. 132kV Substation Ding 12.5MVA 220 28.12.2007 8. 132kV Substation Ellenabad 16MVA 300 30.1.2008 9. 132kV Substation Sikenderpur 16 MVA 300 27.2.2008 Total-II 216.5MVA 2176 Total I-II 216.5MVA 2176 III. Transmission Lines - - Total Cost I – III 2176

P. District Mohindergarh

I. New Substation - - II. Augmentation - - Total I-II - - III. Transmission Lines - - Total Cost I – III - Q. District Rewari I. New Substation 1. 132KV Substation Dahina 16MVA 450 26.6.2008 Total-I 16MVA 450 II. Augmentation 1. 220KV Substation Rewari 50MVA 250 29.12.2006 2. 220kV Substation Rewari 12.5MVA 300 22.7.2007 3. 132KV Substation Kosli 1MVA 12 6.9.2005 4. 132KV Substation Kosli 3MVA 38 14.4.2007 5. 132KV Substation Pali/Gothra 16MVA 240 10.9.2007 Total-II 82.5MVA 840 Total I-II 98.5MVA 1290 III. Transmission Lines 1. LILO of 220kV D/C 21.000 KM 735 26.2.2007 -Rewari line at 400kV Substation Bhiwadi 2. LILO of 132kV Rewari-Baroli line 1.000 KM 114 2.6.2008 at Dahina Total-III 22.000 KM 849 Total Cost I – III 2139

R. District Gurgaon I. New Substation 1. 220kV substation Daultabad 100MVA 1902 23.10.2007 16MVA 1.10.2007 2. 66KV Substation Harsaru 16MVA 300 7.4.2005 101 3. 66kV Substation Sector 38 31.5MVA 400 31.8.2007 Gurgaon 4. 66kV Substation Sec-9 31.5MVA 670 6.3.2008 Gurgaon 5. 66kV Substation Sector-28 20MVA 500 26.4.2008 Gurgaon Total-I 215MVA 3772 II. Augmentation 1. 220KV Substation Sector Daultabad 100MVA 600 13.6.2008 16MVA 2. 66KV Gurgaon Substation 6MVA 75 22.5.2005 3. 66KV Substation Sector 44 15.5MVA 200 29.7.2005 4. 66KV Substation Maruti 15.5MVA 284 31.7.2006 5. 66KV Substation Sector 44 31.5MVA 250 30.12.2007 6. 66KV Substation Bhora Kalan 16MVA 180 1.1.2008 7. 66KV Substation Pataudi 16 MVA 225 2.2.2008 8. 66KV Substation Sector-56 Gurgaon 16 MVA 225 15.2.2008 9. 66KV Substation Sector-34 Gurgaon 16MVA 200 9.4.2008 10. 66KV Substation Sector-10 Gurgaon 16MVA 180 11.5.2008 11. 66KV Substation Sector-28 20MVA 180 30.5.2008 Gurgaon 12. 66KV Substation DLF Gurgaon 16MVA 225 22.10.2008 13. 66KV Substation Harsaru 16MVA 471 31.12.2008 Total-II 316.5MVA 3295 Total I-II 531.5MVA 7067 III. Transmission Lines 1. 220KV Badshahpur –IMT 11.600 KM 339 31.5.2005 Manesar S/C line on D/C towers 2. 220KV IMT Manesar- 18.000 KM 630 10.9.2006 Daultabad line 3. LILO of 66KV S/C 0.600 KM 120 6.4.2005 Badshahpur – Farukh Nagar line to 66KV substation Harsaru 4. 66KV line from 220KV 6.360 KM 200 3.6.2006 substation Sector 52A to 66KV substation Dundahera 5. 66KV D/C Daultabad-Harsaru 11.000 KM 264 1.9.2006 line 6. 66KV D/C line from 10.760 KM 330 14.10.2006 Daultabad to Sector 23A Gurgaon 7. 66KV D/C Daultabad- 6.300 KM 630 14.10.2006 Sector-9 Gurgaon line

102 8. LILO of 66kV Badshapur- 0.500 KM 119 1.4.2008 Sector 56-Q Block- Dundahera line to 66kV substation Sector-28 Gurgaon 9. 66KV D/C Sector-44- 3.050 298 1.12.2008 Sector-28 Gurgaon line Total-III 68.17KM 2930 Total Cost I – III 9997

S. District Mewat I. New Substation 1. 66KV Substation Punhana 16MVA 360 16.12.2006 Total-I 16MVA 360 II. Augmentation 1 66KV Substation Nagina 0.5MVA 45 23.8.2005 Total-II 0.5MVA 45 Total I-II 16.5 MVA 405 III. Transmission Lines 1. 66KV S/C Hodal-Punhana line 16.200 KM 135 24.11.2006 Total-III 16.200 KM 135 24.11.2006 Total Cost I – III 540 T. District Faridabad I. New Substation 1. 66KV Substation Bhopani 16MVA 190 17.10.2005 2. 66kV Substation Fatehpur 8MVA 360 31.7.2007 Biloch 3. 66kV Substation Escort-I 16MVA 280 5.7.2008 Faridabad Total-I 40MVA 830 II. Augmentation 1. 220kV Substation Palla 3.5MVA 160 7.4.2007 2. 220kV Substation Palla 8MVA 239 16.1.2008 3. 220kV Substation Pali 100MVA 350 22.11.2008 4. 66kV Substation Sec.31 16MVA 100 19.4.2005 Faridabad 5. 66KV Substation Escort II 3.5MVA 75 16.9.2005 6. 66KV Substation Oswal steel 10MVA 120 23.3.2006 Faridabad 7. 66kV Substation Dhauj 8MVA 175 31.3.2007 8. 66kV Substation Jharsethli 16MVA 225 3.1.2008 9. 66kV Substation NH 3 10 MVA 225 5.2.2008 Faridabad 10. 66kV Substation Jharsatly 3.5MVA 130 26.8.2008 Total-II 178.5MVA 1799 Total I-II 218.5MVA 2629 III. Transmission Lines 1. 66kV Sector 31 to Bhopani 8.800 KM 195 15.10.2005 line

103 2. 66kV D/C line from Pali-NH3 4.300 KM 60 28.1.2006 Faridabad 3. 2nd Ckt. 66KV Palla-Sector 31 3.000 KM 20 14.3.2006 Faridabad line 4. 66kV S/C Ford-Escort line 2.136 KM 40 2.7.2008 Total-III 18.236KM 315 Total Cost I – III 2944 S. District Palwal I. New Substation 1. 66KV Substation Hasanpur 16MVA 331 20.5.2005 2. 66KV Substation Bhagola 16MVA 400 31.10.2006 Total-I 32MVA 731 II. Augmentation 1. 220KV Substation Palwal 100MVA 463 2.1.2006 2. 220KV Substation Palwal 6MVA 225 16.9.2008 3. 66kV Substation Hodal 8MVA 135 20.3.2007 Total-II 114MVA 823 Total I-II 146MVA 1554 III. Transmission Lines 1. 66KV S/C Aurangabad- 18.415 KM 156 20.5.2005 Hasanpur line 2. LILO of 66KV Palwal- 1.200 KM 42 16.9.2006 Ballabgarh line to 66KV substation Bhagola 3. 66kV D/C Palwal-Aurangabad 13.460 KM 312 27.2.2007 line Total-III 33.075KM 510 Total Cost I – III 2064

104 ANNEXURE – IV

DISTRICT-WISE DETAIL OF APPROVED 220kV/132kV/66kV NEW SUBSTATIONS, AUGMENTATION OF EXISTING SUBSTATIONS AND TRANSMISSION LINES UNDER CONSTRUCTION / TO BE CONSTRUCTED

Sr. Name of substation or line Capacity in Tentative Tentative No. section MVA and Line Cost in Rs Completion Length in km lac Schedule

I Ambala New Substations 1 66 kV substation Mohra 16 600 2009-10 2 66 kV substation Ugala 32 1000 2009-10 3 66 kV substation Air Force Ambala 16 800 2008-09 Cantt (By Air Force) 4 66 kV substation MES (Army) 16 800 2008-09 Ambala Cantt (By MES) 5 66 kV substation Company Bagh 16 600 2009-10 Ambala City 6 66 kV substation Berkheri 16 700 2010-11 7 66 kV substation Santokhi 32 1000 2010-11 Total-I 144 5500 Augmentations 1 220 kV substation Tepla 100 750 2008-09 2 66 kV substation 16 250 2008-09 Total-II 116 1000 Transmission Lines 1 LILO of one circuit of 66kV D/C 3 85 2008-09 Dukheri - Layalpur Basti (Circuit other than feeding 66 kV Sonda) at proposed 66 kV substation Mohra. 2 66 kV D/C line from 220 kV 26 600 2009-10 substation Tepla to 66 kV substation Ugala. 3 66 kV S/C line from 220 kV 16 304 2008-09 substation Tepla to 66 kV proposed Air Force substation, Ambala Cantt. 4 66 kV S/C line from 220 kV 8 152 2008-09 substation Tepla to 66 kV proposed substation MES Ambala Cantt. 5 66 kV S/C line from 66 kV substation 8 152 2008-09 MES (army) Ambala Cantt to 66 kV substation Air Force, Ambala Cantt. 6 LILO of one circuit of 66 kV D/C 1 25 2009-10 Dukheri - Layalpur Basti line at 66 kV substation Company Bagh Ambala City on D/C towers. 105 7 Lying of cable in the portion between 0.8 40 2009-10 point where LILO line crosses railway line and 66 kV substation Company Bagh Ambala City 8 66 kV D/C line from proposed 220 kV 14 502 2010-11 substation Raiwali to proposed 66 kV substation Santokhi 9 66 kV D/C line from proposed 66 kV 15 538 2010-11 substation Santokhi to proposed 66 kV substation Berkheri 10 66 kV D/C line from proposed 66 kV 10 360 2010-11 substation Berkheri to existing 66 kV substation Naraingarh

11 66 kV S/C line from existing 66 kV 10 330 2010-11 substation Shahzadpur to existing 66 kV substation Naraingarh Total-III 112 3088 Total-I+II+III 9588 II Bhiwani New Substations 1 220 kV substation Isharwal 100 2600 2008-09 2 220 kV substation Gignow near 200 3000 2010-11 Loharu

3 220 kV substation Sagwan near 200 3000 2010-11 Tosham 4 220 kV substation Jhajjukalan 200 3000 2010-11 (Upgradation of 132 kV Jhojjukalan) 5 132 kV substation Halluwas (Dadri 16 531 2009-10 Road Bhiwani) 6 132 kV substation 25 800 2010-11 7 132 kV substation Khanak 50 1200 2010-11

8 132 kV substation Berla 50 1200 2010-11 9 132 kV substation Makrani 50 1200 2010-11 10 132 kV substation Barsi 50 1200 2010-11 Total-I 941 17731 Augmentations 1 220 kV substation Isherwal 200 1100 2009-10 2 132 kV substation Digwan Jattan 25 250 2009-10 3 132kV substation Badhra 25 250 2009-10 4 132 kV substation Miran 25 250 2009-10 5 132 kV substation Jhojjukalan 25 250 2009-10 6 132 kV substation Atela Kalan 25 200 2009-10 7 132 kV substation Jui 25 250 2009-10 Total-II 350 2550

106 Transmission Lines 1 220 kV D/C line from 400 kV 53 2385 2008-09 substation Mayyar (Hisar) to 220 kV substation Isharwal 2 220 kV D/C line from proposed 220 50 2700 2010-11 kV substation Dhanonda (Mohindergarh) to proposed 220 kV substation Gignow 3 220 kV D/C line from proposed 220 30 1620 2010-11 kV substation Isharwal (under construction) to proposed 220 kV substation Gignow 4 LILO of proposed 220 kV D/C 10 500 2010-11 Dhanaunda - Gignow line at proposed 220 kV substation Jhojju Kalan 5 LILO of both circuits of existing 220 40 2000 2010-11 kV D/C Hisar (400 kV substation Mayyar of PGCIL) - Isharwal line at the proposed 220 kV substation Sagwan by erecting about 40 km 220 kV D/C line 6 LILO of existing 132 kV S/C Jui - 12 420 2010-11 Digwan Jattan line at 220 kV substation Gignow 7 132 kV S/C line on D/C towers from 8 320 2010-11 proposed 220 kV substation Gignow to existing 132 kV substation Loharu

8 132kV S/C Dadri- Jhojjukalan line 16 426 2009-10 9 Link line for feeding 132 kV Halluwas 1 38 2009-10 from 220 kV substation Dadri by utilizing idle portion of 132 kV S/C Dadri - Bhiwani line. 10 132 kV S/C line from the end of 1 16 2009-10 existing portion of Dadri-Bhiwani line upto proposed 132 kV substation Halluwas. 11 Stringing of 3rd 132 kV circuit 29 291 2008-09 between 220 kV substation Bhiwani and 132 kV substation Jui. 12 132 kV S/C line from 220 kV 36 725 2008-09 substation Isharwal to 132 kV substation Jui. 13 LILO of 132kV Isherwal - Jui line at 2 80 2010-11 132 kV substation Kairu 14 132 kV D/C line from proposed 220 5 220 2010-11 kV substation Sagwan to proposed 132 kV substation Khanak

107 15 132 kV D/C line from the proposed 15 660 2010-11 220 kV substation Jhojju Kalan to the proposed 132 kV substation Berla. 16 LILO of proposed 132 kV S/C Dadri - 4 140 2010-11 Bahu line at the proposed 132 kV substation Makrani. 17 132 kV D/C line from proposed 220 30 1336 2010-11 kV substation to proposed 132 kV substation Barsi Total-III 342 13877 Total-I+II+III 34158 III Faridabad New Substations 1 400 kV substation Nawada 630 10000 2010-11 2 220 kV substation A-5 Faridabad 200 3000 2010-11 (Upgradation of 66 kV level) 3 220 kV substation A-4 Faridabad 200 8500 2010-11 (Upgradation of 66 kV level) {GIS} 4 66 kV substation Sector-64 32 800 2010-11 Ballabgarh 5 66 kV substation by M/s Star Wire 20 700 2009-10 (India) Ltd. at village Chainsa Total-I 1082 23000 Augmentations 1 220 kV substation Palli 8.5 200 2008-09 2 220 kV substation Palla 27.5 600 2009-10 3 66 kV substation Ford Faridabad 16 170 2008-09 4 66 kV substation Dabriwala 16 250 2009-10 5 66 kV substation USA Faridabad 3.5 250 2008-09 6 66 kV substation Oswal Steel 15.5 250 2010-11 Faridabad 7 66 kV substation Hyderabad 31 500 2010-11 Asbestos 8 66 kV substation NH-3 Faridabad 21.5 250 2010-11

9 66 kV substation Sector 46 15.5 250 2010-11 Faridabad 10 66 kV substation Sector 31 15.5 250 2010-11 Faridabad 11 66 kV substation Northern India 15.5 250 2010-11 Faridabad 12 66 kV substation A-2 Faridabad 15.5 250 2010-11 13 66 kV substation A-4 Faridabad 15.5 250 2010-11 14 66 kV substation Fatehpur Biloch 16 200 2010-11 Faridabad 15 66 kV substation A-5 Faridabad 15.5 250 2010-11

16 66 kV substation Escort-II Faridabad 16 250 2010-11

108 17 66 kV substation Badraula 16 250 2010-11 Faridabad 18 66 kV substation Chhainsa 16 250 2010-11 Faridabad Total-II 296.5 4920 Transmission Lines 1 LILO of 400 kV Samaypur - G. Noida 2 200 2010-11 line at proposed 400 kV substation Nawada (Faridabad) 2 220 kV D/C line from proposed 400 5 300 2010-11 kV substation Nawada to 220 kV substation A-5 Faridabad. 3 220 kV D/C line from A-3 Palla to A-5 15 900 2010-11

4 LILO of one circuit of 220 kV D/C A-3 4 250 2010-11 Palla to A-5 line at proposed 220 kV substation A-4 Faridabad. 5 66 kV D/C link from 220 kV 4 344 2009-10 substation Palli to 66 kV substation Dhauj. 6 To augment the 66 kV conductor in 2500 2009-10 Faridabad ring main to improve the power supply position in Faridabad by enhancing current carrying capacity of the ring main after augmentation (51 km.). 7 To provide four single core cable 5 350 2009-10 connection (one core spare) for both 66 kV circuits i.e. 220 kV Ballabgarh to 66 kV Hyderabad Asbestos and 220 kV Ballabgarh to 66 kV Globe Steel. 8 66 kV D/C line from proposed 400 kV 8.8 616 2010-11 substation Nawada to 66 kV substation Fatehpur Biloch. 9 66 kV D/C line ACSR conductor from 10 430 2010-11 400/220 kV S/S Nawada to 66 kV substation Sector-64 Ballabgarh. 10 LILO arrangement of one circuit of 66 5 215 2010-11 kV D/C BBMB – A-5 line on D/C Towers for providing supply to proposed 66 kV substation Sector-64 Ballabgarh. 11 Underground cable from 66 kV 2 120 2009-10 Chainsa to 66 kV substation M/s Star Wire Chainsa Total-III 60.8 6225

Total-I+II+III 34145

109 IV Fatehabad New Substations 1 220 kV substation Samain (Tohana) 300 3000 2010-11 2 132 kV substation Jakhal 32 431 2009-10 3 132 kV substation Bhutan Kalan 50 954 2008-09

4 132 kV substation Chanderkhurd 50 1200 2010-11 Total-I 432 5585 Augmentations 1 132 kV substation Teliwara 25 250.00 2009-10 Total-II 25 250.00 Transmission Lines 1 220 kV D/C from 400 kV substation 25 1450 2009-10 Kirori (Hisar) to under construction 220 kV substation Bhuna. 2 220 kV D/C line from the proposed 36 1944 2010-11 400 kV substation Kirori to proposed 220 kV substation Samain (Tohana) 3 220 kV D/C line from the proposed 48 2592 2010-11 220 kV substation Samain (Tohana) to proposed 220 kV substation Masudpur (Hansi) 4 132 kV S/C line from proposed 220 25 369 2009-10 kV substation Bhuna to 132 kV substation Jakhal 5 LILO of 132kV S/C Tohana - Dharsal 19 577 2008-09 line at 220 kV substation Bhuna 6 LILO of 132 kV S/C Dharsal - 28 425 2008-09 Telewara line at 220 kV substation Bhuna 7 132 kV S/C line from 220 kV 25 483 2008-09 proposed substation Bhuna to 132 kV substation Uklana 8 132 kV S/C line on D/C towers from 15 372 2008-09 220 kV substation Bhuna to proposed 132 kV substation Bhutan Kalan 9 132 kV D/C line from proposed 220 12 534 2010-11 kV substation Samain to proposed 132 kV substation Chander Khurd

Total-III 233 8746 Total-I+II+III 14581 V Gurgaon New Substations 1 400 kV substation Daultabad 945 8500 2010-11 (Gurgaon) 2 220 kV substation Sector-56 200 3000 2009-10 Gurgaon

110 3 220 kV substation Sector-72 300 3000 2010-11 Gurgaon

4 220 kV substation Sector-20 263 7500 2010-11 Gurgaon (GIS) 5 220 kV substation Sector-57 200 7500 2010-11 Gurgaon (GIS) 6 66 kV substation Nimoth 16 800 2010-11 7 66 kV substation Sector-15 II 40 750 2009-10 Gurgaon 8 66 kV substation Sector-2 Gurgaon 63 1000 2009-10 9 66 kV substation Sector-3 Gurgaon 31.5 600 2010-11 10 66 kV substation Sector-51 Gurgaon 63 2500 2009-10 (GIS) 11 66 kV substation Sector-43 Gurgaon 63 2500 2009-10 (GIS) 12 66 kV substation DLF Phase-V 80 1700 2009-10 Sector-43, Gurgaon (M/s DLF) 13 66 kV substation South City-II 60 1400 2009-10 (Sector-47 Gurgaon) (M/s Unitech).

14 66 kV substation HLF Ambience 72 1600 2010-11 Project Sector-24, Gurgaon (M/s HLF) 15 66 kV substation Sector-17 Gurgaon 63 2500 2010-11 (GIS) 16 66 kV substation M/s Vipul Ltd. 32 800 2010-11 Gurgaon (M/s Vipul) 17 66 kV substation by M/s Canton 51.5 1500 2010-11 Buildwell Pvt. Ltd. on Gurgaon - Faridabad road Total-I 2543 47150 Augmentations 1 220 kV substation IMT Manaser 100 750 2009-10 (by HSIIDC) 2 220 kV substation Sector-52A 100 750 2008-09 Gurgaon 3 66 kV substation Dharuhera 3.5 147 2008-09 (Gurgaon)

4 66 kV substation Sector-38 Gurgaon 31.5 300 2008-09 5 66 kV substation Manesar 15.5 300 2009-10 6 66 kV substation Sector-56 Gurgaon 15.5 250 2010-11 7 66 kV substation Bhore Kalan 31 500 2010-11 Total-II 297 2997 Transmission Lines 1 400 kV D/C line from Jhajjar TPS to 70 7000 2010-11 Daultabad (Gurgaon) .

111 2 400 kV D/C line from Daultabad 24 2400 2011-12 (Gurgaon) - 400 kV substation Sector-72, Gurgaon (PGCIL) 3 400 kV Mohindergarh (Dhanonda) - 70 6000 2011-12 Daultabad quad moose conductor D/C line. 4 220kV D/C IMT Maneser (220 kV) - 18 912 2008-09 Daultabad (220 kV) line 5 2nd Ckt. of 220kV Badshahpur (220 11.6 486 2009-10 kV) - IMT Manaser (220 kV) line on D/C towers. 6 LILO of 220 kV D/C Palli-sector-52A 1 45 2009-10 Gurgaon line at proposed 220 kV substation Sector-56 Gurgaon. 7 220kV D/C Sector 72 (220 kV) - 24 1440 2010-11 Sector 20 (220 kV) line 8 4 circuit 220 kV from 400 kV Sector 0.1 5 2010-11 72 (PGCIL) to 220 kV Sector 72 Gurgaon 9 220 kV D/C line from 220 kV Sector 10.5 630.00 2010-11 72 Gurgaon to Sector 56 Gurgaon 10 220 kV D/C line from 220 kV Sector 12.5 750.00 2010-11 72 Gurgaon to Sector 52 Gurgaon 11 220 kV LILO of Sector 72 (220 kV) - 0.5 27 2010-11 Sector 52 Gurgaon D/C line at proposed 220 kV substation Sector 57 Gurgaon. 12 220 kV D/C Sector-72 - Badshahpur 5 275 2011-12 line 13 220 kV Daultabad - Sector 20 15 1200 2011-12 Gurgaon D/C (O/H line in outer areas and 220 kV multi cables in city area where O/H line may not be feasible). 14 LILO of 66kV D/C Badshahpur - 8 49 2008-09 Sector 56 - Dundahera line at 220 kV substation Sector-52A Gurgaon 15 66kV D/C IMT Manaser (220 kV) - 15 255 2009-10 Harsaru line 16 66kV D/C Sector 44 Gurgaon - 6 99 2008-09 Sector 38 Gurgaon line 17 66kV D/C Daultabad (220 kV) - 13 217 2008-09 Sector 10 Gurgaon line 18 Upgradation of Badshahpur - 720 2008-09 Dundahera 66 kV D/C line (18 km.) 19 Upgradation of Badshahpur - 360 2009-10 Mehrauli Road 66 kV D/C line(12 km) 20 LILO of 66 kV line from Ballabgarh to 1.75 44 2010-11 Sohna at proposed 66 kV substations Nimoth.

112 21 LILO of 2nd circuit of 66kV 2 44 2008-09 Badshahpur–Dundahera line at 66 kV substation "Q" block, Gurgaon. 22 Stringing 2nd ckt of 66kV Sector 23A 22 161 2009-10 - Dundahera line. 23 LILO of 66 kV D/C line from 1 35 2008-09 Badshahpur to Mehrauli Road at the site proposed 66 kV substation Sector-15 II Gurgaon 24 LILO of 66 kV D/C line from 220 kV 2 50 2009-10 substation Rohtak Road Delhi to 66 kV substation Mehrauli Road at the proposed 66 kV substation Sector-3 Gurgaon. 25 Up gradation of old 66 kV Mehrauli 40 800 2009-10 Road Gurgaon - Pataudi circuit on H- rail pole on tower line in the section between 66 kV substation Harsaru and 66 kV substation Pataudi and connecting with 66 kV substation Harsaru and 66 kV substation Pataudi 26 LILO of 66 kV D/C line from 1 40 2009-10 Daultabad to Sector 23 at proposed 66 kV substation Sector-2 Gurgaon 27 66 kV D/C line from 220 kV 2 206 2009-10 substation Sector-52A Gurgaon to proposed 66 kV substation Sector-51 Gurgaon 28 LILO of 66 kV D/C Badshahpur – 1.75 75 2009-10 sector 56 – DLF line at proposed 66 kV substation Sector-43 Gurgaon 29 LILO of Sector-56 - Q block section 1 40 2008-09 of 66 kV D/C Badshahpur - Sector 56 - Q Block - Dundahera line on 2xD/C line with higher conductor size at 220 kV substation sector-52A passing through 66 kV DLF substation proposed above. One circuit to be LILOed at 66 kV DLF substation in the first instance and the second circuit in future as the system conditions demand (M/s DLF). 30 66 kV D/C from 220 kV substation 1.5 60 2009-10 Badshahpur to proposed 66 kV substation in South City-II Gurgaon (M/s Unitech). 31 66 kV D/C line from 220 kV 8 320 2010-11 substation sector 52-A to the proposed 66 kV substation Sector 24 (M/s HLF)

113 32 Underground cable connection at 66 4 280 2010-11 kV level (double circuit nature with one core spare) from proposed 220 kV substation Sector 20 Gurgaon to 66 kV substation Phase-IV Dundahera. 33 Underground cable connection at 66 10 700 2010-11 kV level (double circuit nature with one core spare) from proposed 220 kV substation Sector 20 Gurgaon to 66 kV proposed substation Sector-17 Gurgaon 34 Underground cable connection at 66 4 280 2010-11 kV level (double circuit nature with one core spare) from proposed 220 kV substation Sector 20 Gurgaon to 66 kV proposed substation HLF (Ambience) Gurgaon 35 66 kV D/C line from 220 kV Sector 8.5 382 2010-11 72 Gurgaon to Sector 51 Gurgaon 36 66 kV LILO of existing 66 kV D/C line 8 122 2010-11 Badshahpur - Sector 34 - Sector 10 line at Sector 72 Gurgaon. 37 Augmentation of Badshahpur - 600 2010-11 Sector 72 - Sector 34 - Sector 10 line with higher capacity INVAR conductor. (12 Km) 38 66 kV D/C line from 220 kV Mau to 10 400 2010-11 Bhore Kalan. 39 66 kV D/C line from 220 kV 2 140 2009-10 substation Sector-57 Gurgaon to proposed 66 kV substation Ardee City Gurgaon. 40 66 kV D/C line from 220 kV 4 280 2010-11 substation Sector-57 Gurgaon to proposed 66 kV substation Sector-45 Gurgaon. 41 66 kV D/C line from 220 kV 6 420 2009-10 substation Sector-57 Gurgaon to proposed 66 kV (DMRC) Metro. 42 66 kV S/C line conductor from 220 2 80 2010-11 kV substation Sector-72 Gurgaon to 66 kV substation of M/S Vipul Limited Sector 71 Gurgaon erected on multi circuit towers 43 LILO of one circuit of 66 kV 2 80 2010-11 Badshahpur-Sector 72-Sector-34 line with 0.15 Sq” INVAR conductor at 66 kV substation of M/S Vipul Limited Sector 71 Gurgaon

114 44 66 kV D/C line from 220 kV 7 240 2010-11 substation Sector 56 Gurgaon to 66 kV substation by M/s Canton Buildwell Pvt. Ltd. on Gurgaon - Faridabad road Total-III 455.7 28750 Total I +II+III 78897 VI Hisar New Substations 1 400 kV substation Kirori (Hisar) 945 10000 2009-10 2 220 kV substation Masudpur (Hansi ) 200 2500 2010-11 3 132 kV substation Arya Nagar 16 633 2008-09 (Hissar) Total-I 1161 13133 Augmentations 1 132 kV substation Adampur 25 250 2008-09 Total-II 25 250 Transmission Lines 1 400 kV D/C line from Hisar TPS 12.5 1260 2009-10 (Khedar) to proposed 400 kV substation Kirori (Hisar) 2 400 kV D/C line from Hisar TPS to 45 4748 2009-10 400 kV substation Fatehabad PGCIL. 3 400 kV D/C Kirori (Hisar) - Jind line 40 4000 2011-12

4 Loop in of Jind - Hisar IA 220 kV D/C 25 750 2009-10 at 400 kV substation Kirori (Hisar) making it Jind – Kirori D/C line. 5 Link between proposed 220 kV 8 240 2009-10 substation Hansi to the LILO point of Jind - Hisar IA line in order to complete Hansi - Hisar IA line. 6 220 kV D/C from 400 kV substation 40 2000 2009-10 Kirori (Hisar) to proposed 220 kV substation Hansi. 7 LILO of existing 132 kV S/C Hansi - 18 630 2010-11 Narnaund line at proposed 220 kV substation Masudpur (Hansi). 8 2nd. ckt. of Beer (132 kV)-to T-off 3 17 2008-09 point (Tower No.45) on already erected D/C Towers

9 132 kV S/C line on D/C towers from 20 496 2008-09 Location No. 45 (T-off point) to 132 KV substation Arya Nagar 10 Stringing of 2nd. ckt. from 132kV 38 211 2008-09 Hisar I.A to Arya Nagar line 11 132 kV S/C line on D/C towers from 20 500 2009-10 400 kV substation Kirori (Hisar) to under construction 132 kV substation Barwala. 115 12 132 kV S/C line from 400 kV 25 935 2009-10 substation Kirori (Hisar) to 132 kV substation Adampur. First few spans from Kirori (2-3 km) shall be on D/C tower. Total-III 294.5 15787 Total-I+II+III 29170 VII Jhajjar New Substations 1 132 kV substation Beri 41 945 2008-09 2 132 kV substation Bahadurgarh 20 800 2009-10 (HSIDC) Total-I 61 1745 Augmentations 1 132 kV substation Mattanhail 8 250 2008-09 2 132 kV substation Bahu ( for M/s 25 250 2008-09 Aravali Power Company Private Limited). Total-II 33 500 Transmission Lines 1 132 kV S/C line from 132 kV 4 133 2008-09 substation Jhajjar to proposed 132 kV substation Beri 2 132 kV S/C line from 220 kV 22 500 2010-11 substation Sampla to 132 kV substation Beri. 3 132 kV S/C line on D/C towers from 5 150.00 2008-09 220 kV substation Bahudargarh to proposed 132 kV substation 132 kV Bahadurgarh (HSIDC) Total-III 31 783 Total-I+II+III 3028 VIII Jind New Substations 1 132 kV substation Bibipur 16 750 2009-10 2 132 kV substation Dablain 20 800 2009-10 3 132 kV substation Ghoghrian 41 1140 2010-11 Total-I 77 2690 Augmentations 1 220 kV substation Jind 100 550 2009-10 2 220 kV substation Safidon 5 200 2009-10 3 132 kV substation Naguran 25 250 2008-09 4 132 kV substation Narnaund 25 250 2009-10 Total-II 155 1250 Transmission Lines 1 132 kV S/C line from 132 kV 13 240 2008-09 substation Kheri Taloda to proposed 132 kV substation Alewa

116 2 132 kV S/C line from 132 kV 14 440 2008-09 substation Jalmana to 132 kV substation Assandh 3 LILO of Jind - Narnaud line at Bibipur 7 245 2009-10 4 LILO of 132 kV Narwana – Uklana 1 35 2009-10 line at proposed 132 kV substation Dablain. 5 LILO of 132 kV Jind (O) - Uchana 5.5 193 2010-11 S/C line at proposed 132 kV substation Ghoghrian. Total-III 41 1153 Total-I+II+III 5093 IX Kaithal New Substations 1 220 kV substation Kaul 200 2500 2009-10 2 220 kV substation Batta near Kalayat 200 2500 2010-11 3 132 kV substation Kheri Gulam Ali 50 930 2009-10 4 132 kV substation Habri 50 930 2009-10 5 132 kV substation Khurana 50 930 2009-10 Total-I 550 7790 Augmentations 1 220 kV substation Cheeka 100 550 2009-10 2 220 kV substation Kaithal 25 200 2010-11 3 132 kV substation Padla 25 200 2008-09 4 132 kV substation Pundri 25 200 2008-09 5 132 kV substation Nautch 25 200 2008-09 Total-II 200 1350 Transmission Lines 1 220 kV D/C line from 220 kV 20 1200 2010-11 substation Pehowa to proposed 220 kV substation Kaul. 2 220 kV D/C line from 220 kV 50 2700 2010-11 substation Bastra to proposed 220 kV substation Kaul. 3 LILO of 220 kV Narwana - Kaithal 2 100 2010-11 D/C line at proposed 220 kV substation Batta 4 132kV S/C Kaithal-Pai line 16 426 2008-09 5 132 kV S/C line on D/C towers from 25 860 2009-10 220 kV substation Cheeka to the proposed 132 kV substation Kheri Gulam Ali 6 132 kV D/C line from 220 kV 8 400 2009-10 substation Kaul to 132 kV substation Dhand.

117 7 132 kV S/C line on D/C towers from 12 390 2009-10 132 kV substation Rasina to proposed 132 kV substation Habri.

8 132 kV S/C line from 220 kV Pehowa 17 270 2010-11 to 132 kV Malikpur and connecting it to present 132 kV Malikpur - Ismailabad line 9 132 kV S/C line on D/C towers from 20 620 2009-10 220 kV substation Kaul to 132 kV substation Habri. 11 LILO of 132 kV Kaithal – Sewan line 20 350 2009-10 at 132 kV substation Khurana. 12 132 kV S/C line on D/C tower from 10 280 2009-10 upcoming 132 kV substation Kheri Gulam Ali to proposed 132 kV substation Khurana. Total-III 200 7596 Total-I+II+III 16736 X Karnal New Substations 1 220 kV substation Bastra 204 3000 2009-10 (Gharaunda) 2 132 kV substaion Bhadson 32 711 2008-09 3 132 kV substation Nagla Megha 32 712 2008-09 4 132 kV substation Sataundi 50 1000 2010-11 5 132 kV substation Nidana 29 950 2009-10 6 132 kV substation Biana 50 1000 2010-11 7 132 kV substation Rambha 50 1000 2010-11 8 132 kV substation Ballah 50 1000 2010-11 9 132 kV substation Dabri 50 1000 2010-11 10 132 kV substation Sitamai 50 930 2010-11 Total-I 597 11303 Augmentations 1 220 kV substation Nissing 100 550 2009-10 2 132 kV substation Indri 16 175 2009-10 3 132 kV substation Rasina 16 238 2009-10 4 132 kV substation Gharaunda 25 250 2008-09 5 132 kV substation Jalmana 25 250 2009-10 Total-II 182 1463 Transmission Lines 1 220kV D/C YTPP - Nilokheri line 70 2503 2008-09 2 220 kV D/C line from PTPP to 25 1464 2010-11 proposed 220 kV substation Bastra 3 132 kV S/C line from 220 kV 7 111 2008-09 Nilokheri to 132 kV Bhadson. 4 LILO of 132 kV S/C Karnal - Indri 10 280 2008-09 line at 220 kV Nilokheri.

118 5 132 kV S/C Madhuban to Nagla 7 167 2008-09 Megha line. 6 LILO of one circuit of Bastra-Jundla 6 210 2010-11 line at proposed 132 kV substation Sataundi. 7 LILO of 132 kV S/C line between 5 175 2010-11 Gharaunda and Madhuban at 220 kV substation Bastra. 8 132 kV D/C line from propopsed 220 15 780 2010-11 kV substation Bastra to under construction 132 kV substation Naglamegha. 9 132 kV D/C line from proposed 220 22 1088 2010-11 kV substation Bastra to 132 kV substation Jundla via Sataundi. 10 LILO of existing 132 kV idle line from 6 235 2009-10 132 kV Karnal to 220 kV Nissing at proposed 132 kV substation Nidana 11 LILO of Karnal - Nilokheri (220 kV) 4 80 2010-11 section of 132 kV Karnal - Indri S/C line at proposed 132 kV substation Biana 12 LILO of existing 132 kV Karnal - 5 175 2010-11 Nilokheri S/C line at proposed 132 kV substation Rambha. 13 132 kV S/C line on D/C towers from 26 887 2010-11 proposed 132 kV substation Ballah to 132 kV substation Sataundi.

14 LILO of 132 kV Karnal - Nissing line 6 210 2010-11 at proposed 132 kV substation Dabri. 15 132 kV S/C line on D/C towers from 11 308 2010-11 220 kV substation Kaul to the proposed 132 kV substation Sitamai. Total-III 225 8673 Total-I+II+III 21439 XI Kurukshetra New Substations 1 132 kV substation Bhusthala 50 800 2008-09 2 132 kV substation Kirmich 25 940 2009-10 3 132 kV substation Adhon 50 800 2008-09 4 132 kV substation Lukhi 50 800 2008-09 5 132 kV substation Bodhni 50 800 2008-09 Total-I 225 4140 Augmentations 1 66 kV substation Jalkheri 16 115 2009-10 2 132 kV substation Kirmich 25 250 2009-10 Total-II 41 365 Transmission Lines 1 220 kV D/C line from 220 kV Cheeka 53 2585 2008-09 to 220 kV substation Durala 119 2 132 kV D/C line from 220 kV 12.5 375 2009-10 substation Durala to proposed 132 kV substation Bhusthala 3 132 kV S/C line on D/C towers from 12 360 2009-10 132 kV substation Bhusthala to 132 kV substation Ismailabad 4 132 kV S/C line on D/C towers from 3 75 2009-10 220 kV substation Durala to proposed 132 kV substation Adhon 5 132 kV S/C line on D/C towers from 9 225 2009-10 220 kV substation Durala to 132 kV substation Lukhi 6 LILO of 132 kV Pehowa – Bhore line 11.5 345 2009-10 at 132 kV substation Lukhi. 7 LILO of S/C line 220 kV Pehowa – 7.5 225 2009-10 132 kV Ismailabad line at 132 kV substation Bodhni. 8 LILO of 132 kV Sagga – Amin line at 24 760 2009-10 132 kV substation Kirmich. 9 132 kV S/C line on D/C tower from 18 465 2009-10 upcoming 220 kV substation Nilokheri to proposed 132 kV substation Kirmich 10 66 kV S/C Lohara - Babain line. 10 290 2009-10 Total-III 161 5705 Total-I+II+III 10210 XII Mewat I New Substations 1 220 kV substation Rangala Rajpur 200 3000 2010-11 (Firozpurzirka)

2 220 kV substation Kherikanker (Nuh) 200 3000 2010-11 Total-I 400 6000 II Augmentations 1 66 kV substation Nagina 8 60 2009-10 Total-II 8 60 III Transmission Lines 1 220 kV D/C Kherikanker - Rangala 46 2600 2010-11 Rajpur (Firozpurzirka) line 2 220 kV D/C Palwal - Rangala Rajpur 49 2750 2010-11 (Firozpurzirka), line 3 220 kV D/C line from proposed 400 31 1674 2010-11 kV Sector 72 Gurgaon to proposed 220 kV Kherikanker (Nuh) 4 66kV S/C Hathin - Punhana line 22 535 2009-10 5 66 kV D/C line from 66 kV Rangala 18 810 2010-11 Rajpur - Nagina line 6 66 kV S/C Rangala Rajpur - 40 1800 2010-11 Punhana line on D/C towers

120 7 66 kV D/C line from proposed 220 kV 11 473 2010-11 Kherikanker (Nuh) to 66 kV Taoru (on 220 kV towers) 8 66 kV D/C line from proposed 220 kV 11 473 2010-11 Kherikanker (Nuh) to 66 kV Sohna (on 220 kV towers) 9 66 kV D/C line from proposed 220 kV 40 1720 2010-11 Kherikanker (Nuh) to 66 kV Nagina with LILO of one circuit at Nuh. 10 66 kV S/C Mandkola - Nuh line (New 20 420 2010-11 line) on D/C towers 11 66 kV S/C Sohna - Nuh - Nagina line 528 2010-11 from 0.1 Sq" ACSR to 0.15 Sq" AAAC. (44 kM) Total-III 288 13783 Total-I+II+III 19843 XIII Mohindergarh New Substations 1 400 kV substation Dhanonda 945 10000 2011-12 2 132 kV substation Seka 50 1000 2009-10 3 132 kV substation Nangal Mohanpur 50 1000 2010-11 4 132 kV substation Pali 50 1000 2010-11 Total-I 1095 13000 Augmentations 1 132 kV substation Satnali 25 200 2008-09 2 132 kV substation Ateli 25 380 2008-09 3 132 kV substation Mohindergarh 7.5 200 2008-09 4 132 kV substation Kanina Khas 20.0 200 2008-09 5 132 kV substation Mundia Khera 25 250 2009-10 Total-II 102.5 1230 Transmission Lines 1 400 kV D/C Jhajjar TPS (Case-2) - 40 4000 2011-12 Dhanonda line 2 LILO of one circuit of 400 kV Moga - 30 3000 2011-12 Bhiwadi line at Dhanonda 3 400 kV D/C Mohindergarh (Adani 4 500 2011-12 HVDC) - Mohindergarh (Dhanonda) HVPNL line. 4 220 kV D/C line from the proposed 20 1080 2010-11 220 kV substation Lula Ahir (Rewari) to the proposed 220 kV substation Dhanonda (Mohindergarh) 5 132 kV S/C line on D/C tower from 10 300 2009-10 220 kV substation Narnaul to proposed 132 kV substation Seka. 6 132 kV S/C line with from 132 kV 11 210 2009-10 substation Ateli to 132 kV substation Mundia Khera. 121 7 132 kV S/C line from proposed 132 20 380 2009-10 kV substation Seka to 132 kV substation Ateli. 8 132 kV S/C line on D/C towers from 10 400 2010-11 the proposed 220 kV substation Dhanonda to the proposed 132 kV substation Nangal-Mohanpur. 9 132 kV S/C line on D/C towers from 10 400 2010-11 the proposed 220 kV substation Dhanonda to the proposed 132 kV substation Pali 10 Extension of existing 132 kV S/C line 15 300 2010-11 Dadri - Bahu line upto proposed 220 kV substation Dhanonda to enable feeding of existing 132 kV substation Bahu from the proposed 220 kV substation Dhanonda. Total-III 170 10570 Total-I+II+III 24800.00 XIV Palwal I New Substations NIL II Augmentations 1 220 kV substation Palwal 16 250 2009-10 2 66 kV substation Aurangabad 16 250 2010-11 3 66 kV substation Bhagola 16 250 2010-11 4 66 kV substation Chandhut 16 250 2010-11 5 66 kV substation Hathin 8 50 2010-11 Total-II 1050.00 Transmission Lines NIL Total-I+II+III 1050.00 XV Panchkula New Substations 1 220 kV substation Raiwali 200 2500 2010-11 2 66 kV substation Sector 22 32 2500 2009-10 Panchkula (HSIDC) {GIS} 3 66 kV substation Sector 5 Panchkula 63 3000 2010-11 {GIS} Total-I 295 8000 Augmentations 1 220 kV substation Madanpur 100 750 2009-10 Panchkula 2 66 kV substation Barwala 8 200 2009-10 Total-II 108 950

122 Transmission Lines 1 LILO of one circuit of 220 kV double 5 225 2010-11 circuit Tepla - Madanpur line with 0.4 Sq” ACSR at proposed 220 kV substation Raiwali. 2 66kV S/C Panchkula (220 kV) - 3 135 2008-09 Sector 3 Panchkula line on D/C towers 3 Replacement of the existing 500 2009-10 conductorof 66kV Madanpur (220 kV) – Barwala - Shahzadpur- Naraingarh line (42 km) 4 66 kV D/C underground cable from 2 120 2009-10 220 kV substation Madanpur to proposed 66 kV substation at IT park, Sector-22 Panchkula ( at the cost of HSIIDC) 5 66 kV D/C line from proposed 220 kV 11 394 2010-11 substation Raiwali to existing 66 kV substation Barwala 6 66 kV D/C line from existing 66 kV 20 717 2010-11 substation Naraingarh to existing 66 kV substation Raipur Rani 7 66 kV D/C line from existing 66 kV 18 645 2010-11 substation Raipur Rani to proposed 220 kV substation Raiwali 8 Augmentation of existing 66 kV 75 2009-10 Sector 1 - Sector 3 Panchkula S/C line from 0.15 Sq" ACSR to 0.4 Sq" ACSR by putting mid span towers wherever necessary (2.5kM) 9 LILO of 66 kV Sec 1- Sec 3 1 21 2010-11 Panchkula S/C line at the proposed 66 kV GIS Sec 5. 10 Augmentation of both circuits of 165 2009-10 under construction 66 kV Madanpur- sec 3, Panchkula S/C line on D/C towers from 0.2 sq” to 0.4 sq” ACSR by putting mid span towers wherever necessary (5.5 kM) Total (III) 60 2997 Total-I+II+III 11947 XVI Panipat New Substations 1 220 kV substation Samalkha 200 2500 2010-11 2 220 kV substation Chhajpur 200 2500 2010-11

3 132 kV substation Beholi 50 1000 2010-11

4 132 kV substation Bega 25 800 2009-10

123 5 132 kV substation Naultha 25 800 2009-10 6 132 kV substation Kabri 25 800 2010-11 7 132 kV substation Sector-29, Part-II, 95 800 2009-10 Panipat Total-I 620 9200 Augmentations 1 132 kV substation Gohana Road, 16 140 2008-09 Panipat 2 132 kV substation Munak 9 250 2008-09 3 132 kV substation Chajjpur 12.5 200 2008-09 4 132 kV substation Israna 25 250 2010-11 Total-II 62.5 840 Transmission Lines 1 220 kV D/C line from proposed 220 24 1200 2010-11 kV substation Samalkha to 220 kV substation Chhajpur. 2 220 kV D/C line from proposed 400 16 1000 2010-11 kV substation BBMB Sewah to 220 kV substation Chhajpur. 3 220 kV D/C line from proposed 220 28 1512 2010-11 kV substation Mohana to proposed 220 kV substation Samalkha. 4 132 kV S/C line on D/C towers from 8 224 2010-11 Samalkha-Beholi line. 5 132 kV S/C line on D/C towers from 16 448 2009-10 Samalkha-Naultha line. 6 132 kV S/C line on D/C towers with 12 336 2009-10 from Samalkha to Bega. 7 LILO of 132 kV S/C line from 400 kV 2 80 2009-10 substation Sewah to 132 kV substation Israna at 132 kV substation Naultha. 8 132 kV S/C line on D/C towers from 13 364 2009-10 Beholi to Chhajpur. 9 LILO of one circuit of 132 kV D/C 2.5 88 2010-11 PTPS-Chandoli line at 132 kV substation Kabri. 10 LILO of 132 kV S/C Chandoli- 2 70 2009-10 Chhajpur line at 220 kV substation Chhajpur. 11 132 kV S/C line on D/C tower from 9 312 2009-10 220 kV substation Chhajpur to 132 kV substation Sector-29, Panipat. 12 LILO of 132 kV line from 400 kV 2 32 2009-10 substation Sewah to 132 kV substation Samalkha at proposed 132 kV substation Sector-29, Part-II, Panipat

13 132 kV S/C line on D/C towers 132 10 380 2009-10 kV Sataudi - Munak 124 14 Creation of new 132 kV D/C 15 525 2010-11 Mundlana - Israna line

Total-III 160 6571 Total-I+II+III 16611 XVII Rewari I New Substations 1 220 kV substation Lula Ahir 200 3000 2010-11 2 220 kV substation Dharuhera (Mau) 200 3500 2010-11 3 132 kV substation Gangaicha Jat 50 1000 2010-11 (Rewari) 4 66 kV substation Baliyar Kalan 40 1000 2010-11 Total-I 490 8500 Augmentations 1 220 kV substation Rewari 50 700 2009-10 25 2 132 kV substation Kosli 16 200 2009-10 Total-II 91 900 Transmission Lines 1 LILO of Dadri - Rewari 220 kV line at 5 250 2010-11 Lula Ahir 2 220 kV D/C line from Daultabad (220 20 1000 2010-11 kV) - Mau line 3 220 kV D/C line from Kherikanker 30 1500 2010-11 (220 kV) - Mau line 4 LILO of 220 kV S/C Badshahpur - 12 600 2010-11 Rewari line at Mau

5 LILO of 2nd circuit of 220 D/C 15 514 2008-09 Badshahpur - Rewari line at 400 kV PGCIL substation Bhiwadi. 6 Stringing of 2nd Ckt. of 220 kV 51 841 2008-09 Badshahpur - Rewari D/C line. 7 LILO of 132 kV S/C line on D/C 13 520 2009-10 towers from proposed 220 kV substation Lula Ahir to existing 132 kV substation Kosli. 8 LILO of one circuit of 132 kV Rewari 3 105 2010-11 - Kosli line at 132 kV substation Gangaicha Jat. 9 132 kV D/C Lula Ahir - Gangaicha 30 1320 2010-11 Jat line 10 LILO of existing 66 kV S/C Taoru - 11 187 2010-11 Dharuhera line at Mau. 11 LILO of existing 66 kV S/C Pataudi - 3 51 2010-11 Dharuhera line at Mau. 12 66 kV D/C line from 220 kV 14 602 2010-11 substation Mau to Baliyar Total-III 207 7490 Total-I+II+III 16890

125 XVIII Rohtak New Substations 1 400 kV substation Rohtak area 630 10000 2011-12 2 220 kV substation Sampla 200 2500 2010-11 3 132 kV substation Hisar Road 70 1500 2009-10 Rohtak 4 132 kV substation IMT Rohtak 75 1500 2009-10 Total-I 975 15500 Augmentations 1 132 kV substation MDU Rohtak 5 87 2009-10 Total-II 5 87 Transmission Lines 1 400 kV D/C Jhajjar - Rohtak line with 40 4000 2011-12 twin moose conductor matching with commissioning of 765 kV PGCIL substation at Bhiwani. 2 400 kV D/C Bhiwani - Rohtak line 40 4000 2011-12 with twin moose conductor matching with commissioning of 765 kV PGCIL substation at Bhiwani. 3 LILO of 220 kV D/C Rohtak- 23.5 1175 2009-10 Bahadurgarh line at 220 kV proposed substation Sampla. 4 LILO of one circuit of Rohtak - 1 32 2008-09 Mundlana line at proposed 132 kV Jassia 5 LILO of 132 kV S/C line from 220 kV 1.2 55 2008-09 substation Rohtak to 132 kV Gohana at proposed 132 kV substation Jassia 6 LILO of 132 kV Rohtak—Dadri line at 1 32 2008-09 132 kV substation Kalanaur. 7 Stringing of 2nd ckt of Rohtak— 21 124 2008-09 MDU—Sampla 132 kV line 8 Replacement of conductor between 110 2009-10 132 kV substation Rohtak and 132 kV Sec-3, Sonepat Road Rohtak from existing 0.15 sq” ACSR to maximum current carrying capacity conductor physically in the same range and which can be accommodated on the existing tower structures without requiring mid span installation (5.5 km.). 9 Replacement of conductor in weak 60 2009-10 portion of circuit II of 132 kV line from 220 kV Rohtak to 132 kV Rohtak from 0.15 sq” ACSR to 0.2 sq” ACSR to make it uniform line throughout the length (3 km)

126 10 LILO of 132 kV Rohtak – Kalanaur 0.5 40 2009-10 132 kV single circuit line at 132 kV substation Hisar Road Rohtak. 11 LILO of one circuit of 132 kV MDU 2 60 2009-10 Rohtak - Sampla D/C line at 132 kV substation HSIIDC, IMT, Rohtak. Total-III 90.5 9688 Total-I+II+III 25275 XIX Sirsa New Substations 1 400 kV substation Nuhiyawali 630 10000 2010-11 2 220 kV substation Chormar 200 2500 2009-10 3 132 kV substation Dhudhianwali 25 800 2009-10 4 132 kV substation Kurangawali 50 1000 2009-10 5 132 kV substation Khaikan 50 1000 2009-10 Total-I 955 15300 Augmentations 1 132 kV substation Ellenabad 25 182 2009-10 2 132 kV substation Odhan 20 182 2008-09 3 132 kV substation Madhosinghana 25 250 2009-10 4 132 kV substation Ding 3.5 90 2009-10 Total-II 74 704 Transmission Lines 1 LILO of one circuit of 400 kV D/C 100 5000 2010-11 Hisar TPS- Fatehabad line at proposed 400 kV substation Nuhiyawali. 2 220 kV D/C Chormar-Rania line via 45 2430 2010-11 the proposed 400 kV substation Nuhiyawali (Sirsa) 3 220 kV D/C Fatehabad (400 kV) - 95 5760 2009-10 Chormar line 4 LILO of 132 kV Sirsa - Dabwali S/C 3 105 2009-10 line at proposed 220 kV substation Chormar. 5 132 kV S/C line on D/C towers from 20 700 2009-10 400 kV substation Nuhiyawali (Sirsa) to Dhudhianwali

6 132 kV S/C line on D/C towers from 25 875 2009-10 proposed 220 kV substation Chormar to Kurangawali 7 LILO of Nuhiyawali- Sirsa 132 kV 3 105 2009-10 S/C line at 132 kV substation Khairekan

127 8 LILO of 132 kV Sirsa - Odhan S/C 5 175 2010-11 line at proposed 400 kV substation Nuhiyawali

Total-III 296 15150 Total-I+II+III 31154 XX Sonepat New Substations 1 400 kV substation Deepalpur 630 10000 2011-12 2 220 kV substation Mohana 200 3000 2010-11 3 132 kV substation Mundlana 41 1024 2008-09 4 132 kV substation substation Rai 20 800 2010-11 (HSIIDC) 5 132 kV substation Kundli (HSIIDC) 20 800 2008-09 Total-I 911 15624 Augmentations 1 220 kV substation Sonipat 16 238 2009-10 2 132 kV substation Murthal 25 315 2009-10 3 132 kV substation Rai (HSIDC) 16 250 2009-10 4 132 kV substation Kundli (HSIIDC) 16 250 2009-10 5 132 kV substation Kharkhoda 25 250 2009-10 6 132 kV substation Gohana 5 200 2009-10 Total-I 103 1503 Transmission Lines 1 400 kV double circuit line from 45 6300 2011-12 Rohtak - Deepalpur 2 LILO of one circuit of 400 kV 2 200 2011-12 Abdullapur - Bawana line at Deepalpur 3 220 kV D/C line from 400 kV 1.5 90 2010-11 substation Jajjy (PGCIL) to 220 kV substation Mohana. 4 220 kV D/C line from proposed 220 30 1650 2010-11 kV substation Sampla to proposed 220 kV substation Mohana. 5 LILO of Sonepat (220 kV) – Rai (132 1 20 2009-10 kV), 132 kV S/C line at 132 kV substation Rai of HSIDC. 6 LILO of 132 kV S/C line from 132 kV 1 20 2009-10 substation Kundli to 132 kV substation Rai at proposed 132 kV substation HSIDC Kundli 7 132 kV D/C Mohana - Mundalana 21 735 2010-11 line 8 LILO of existing 132 kV S/C Harsana 17.5 1000 2010-11 Kalan - Kharkhoda line at 220 kV substation Mohana with augmentation of 132 kV S/C Sonepat - Harsana Kalan - Kharkhoda line

128 Total-III 119 10015 Total-I+II+III 27142 XXI Yamunanagar New Substations 1 220 kV substation Rampur Kamboan 200 3000 2010-11 2 66 kV substation Sector-15 HUDA 32 738 2009-10 Jagadhari 3 66 kV substation Rattangarh 16 700 2009-10 Total-I 248 4438 Augmentations 1 66 kV substation Yamunanagar 4.5 40 2009-10 2 66 kV substation Jathlana 16 250 2009-10 3 66 kV substation Chhachharauli 8 75 2008-09 Total-II 28.5 365 Transmission Lines 1 220kV D/C YTPP - Abdullapur line 25 894 2008-09 2 LILO of one circuit of 220 kV D/C 23 1366 2010-11 YTPP - Abdullapur at proposed 220 kV substation Rampur Kamboan - 23 km 3 66kV S/C line from Y.Nagar 220 KV 15 113 2008-09 to Jathlana disbanding LILO of Yamunanagar - Radaur line at Jathlana 4 LILO of one circuit of 66 kV WYC - 0.8 2 2009-10 Yamunanagar D/C line at proposed 66 kV substation Sector-15 Jagadhari. 5 LILO of old Jorian – Radaur 66 kV 0.25 6 2009-10 S/C H-pole line at proposed 66 kV substation Rattangarh 6 66 kV D/C line from proposed 220 kV 25 896 2010-11 substation Rampur Kamboan to 66 kV substation . 7 66 kV D/C line from proposed 220 kV 12 276 2010-11 substation Rampur Kamboan to 66 kV substation Bilaspur 8 66 kV D/C line from proposed 220 kV 12 276 2010-11 substation Rampur Kamboan to 66 kV substation Sadhora Total-III 113.05 3829 Total-I+II+III 8632 Grand Total 440389

129

Annexure-V

Yearwise Progress of construction of new grid substation and augmentation of the existing substations during the past 12 years Year 220kV 132kV 66kV 33kV Total New Aug New Aug New Aug New Aug New Aug

1997-98 1 4 3 17 1 13 3 17 8 51 1998-99 - 4 2 11 1 4 8 17 11 36 1999-00 2 6 1 16 3 12 7 70 13 104 2000-01 - 3 2 11 - 9 3 21 5 44 2001-02 - 2 1 9 6 3 5 15 12 29 2002-03 3 4 5 18 3 14 4 32 15 68 2003-04 4 6 15 12 4 8 15 48 38 74 2004-05 3 8 13 9 7 17 22 34 45 68 2005-06 - 4 1 13 5 8 14 56 20 81 2006-07 1 5 3 11 4 7 12 21 20 44 2007-08 2 5 5 14 4 13 36 33 47 65 2008-09 (upto 3 8 7 14 3 11 27 32 40 65 Dec. 2008) March 2005 to Dec, 6 23 16 54 16 40 89 144 127 261 2008

Period New Augmentation Capacity New Investment Substations of Substation added transmission (in Rs. (in MVA) lines crore) (in KMs) 1997-98 8 51 758 302.623 97.59 1998-99 11 36 552 201.620 56.93 1999-00 13 104 1090 270.265 128.90 2000-01 5 44 409 146.772 57.45 2001-02 12 29 492 253.470 68.35 2002-03 15 68 1037 181.639 134.96 2003-04 38 74 1800 478.488 229.73 2004-05 45 68 1923 756.936 266.37 2005-06 20 81 1002 432.172 120.09 2006-07 20 44 887 469.296 204.63 2007-08 47 65 1498.9 422.404 276.63 2008-09 (upto 40 65 2089.4 349.966 324.91 Dec. 2008) March 2005 to 127 261 5530.3 1673.838 931.29 Dec. 2008 During March - 6 53 - 5.03 2005

130

ANNEXURE - VI

Increase in installed capacity in the State in the past fifteen years.

Year Installed Capacity (in MW) Increase per year (in MW) 1993-94 2296.70 - 1994-95 2347.20 50.5 1995-96 2347.20 - 1996-97 2354.90 7.7 1997-98 2392.00 37.1 1998-99 2447.00 55.0 1999.00 2750.20 303.2 2000-01 2780.10 29.9 2001-02 3198.60 418.5 2002-03 3356.90 158.3 2003-04 3408.90 52.0 2004-05 4033.30 624.4 2005-06 4033.30 - 2006-07 4051.30 18.0 2007-08 4368.01 316.71 2008-09 (Dec. 2008) 4753.29 385.28

131 Annexure-VII

Power supply position during April-March period of last 10 years

LU per day 98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09

April 334 332 375 384 440 478 532 547 564 608 594 May 364 381 422 423 498 529 556 645 692 733 684 Jun 394 424 463 490 556 650 644 695 769 847 782 July 424 469 483 538 624 596 735 700 780 925 902 Aug. 422 488 524 565 633 625 644 755 769 911 898 Sept. 378 484 503 557 557 615 632 642 753 813 785 Oct. 316 398 476 485 527 570 516 644 672 686 767 Nov. 335 379 419 438 487 478 528 569 597 628 684 Dec. 371 397 437 447 475 503 560 547 611 623 707 Jan. 359 391 404 457 447 525 549 592 615 613 Feb. 366 413 416 438 451 532 500 584 570 640 Mar. 344 428 435 468 530 565 528 537 574 646 Aver 367 415 447 475 519 556 578 622 665 723 756 age Upto 12/08 % Increase over 13 7 6 9 7 4 7.6 7 8.8 last year

The total availability of power to the State and power supplied to rural sector from 1998-99 to 2008-09 (Upto December 2008) has been as under: - (in Lac Units) Year Total availability Power supplied to rural sector 1998-99 140356 67178 1999-2000 156064 80474 2000-01 168554 85515 2001-02 175881 89000 2002-03 192087 98945 2003-04 207637 104803 2004-05 217136 106329 2005-06 226952 114202 2006-07 242581 119306 2007-08 264656 131269 2008-09 (upto December 2008) 208170 94856

132