41 Simmond Street PROVINCE Sage Life Building

Marshalltown, 2107

Roads and Transport Private Bag X83, Marshalltown, 2107

Tel.: +27 (11) 355 7000 REPUBLIC OF SOUTH AFRICA Fax: +27 (11) 355 7235

CHIEF DIRECTORATE: ROADS

CONTACT NO: DRT 46/08/2013

AGREEMENT NO: D14/02/PD & DD

PROJECT DESCRIPTION: CONSULTING ENGINEERING SERVICES FOR THE PRELIMINARY DESIGN REVIEW, FULL SURVEY, FULL ENVIRONMENTAL IMPACT ASSESSMENT, DETAIL DESIGN, CONTRACT DOCUMENTATION AND SITE SUPERVISION FOR ROAD K109 BETWEEN K27 AND DALE ROAD (APPROXIMATELY 4.9km)

TRAFFIC IMPACT STUDY

November 2015

Prepared by: Aphane Consulting cc Address: P.O BOX 19964, Sunward Park, 1470 Contact Person: Dennis Sinkonde Phone Number: 011 907 6700 Fax Number: 011 869 7434 Email Address: [email protected]

APHANE CONSULTING CC GAUTENG DEPARTMENT OF ROADS AND TRANSPORTCONTRACT NO: DRT 46/08/2013 November 2015

DOCUMENT VERIFICATION APHANE CONSULTING CC

JOB TITLE CONSULTING ENGINEERING SERVICES FOR THE PRELIMINARY DESIGN REVIEW, FULL SURVEY, FULL ENVIRONMENTAL IMPACT ASSESSMENT, DETAIL DESIGN, CONTRACT DOCUMENTATION AND SITE SUPERVISION FOR ROAD K109 BETWEEN K27 AND DALE ROAD (APPROXIMATELY 4.9KM)

DOCUMENT TITLE TRAFFIC IMPACT STUDY REPORT

FILE PATH Z:\AC292 - ROAD K109 - DALE ROAD - GAUTRANS\ADMIN\REPORTS\TRAFFIC\COVER.DOCX

DATE DESCRIPTION FINAL REPORT

FINAL PREPARED BY CHECKED BY APPROVED BY

NAME FHATUWANI MURAVHA VICTOR RAKOSA DENNIS SINKONDE

SIGNATURE

Z:\Lokisa\Lokisa Projects\Aphane - Road K109\Dennis\New folder\Cover.docx

K109 TRAFFIC IMPACT STUDY )

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Table of Contents Page

1 Introduction 1

2 Scope of Study 1

3 Background to K109 1

4 Surrounding Road Network 2

5 Existing Traffic Volumes 4

6 Trip Generation 5

7 Traffic diversion and re-distribution assessment 5

8 Forecast Traffic 7

9 Analysis Method and Scenarios 9 9.1 Access assessment 9 9.2 Crossing Roads 10 9.3 Scenarios 11 9.4 Analysis Software 11 9.5 At-grade Intersections 11

10 Public Transport and Non-Motorised Transport 15

11 Conclusions and recommendations 16

Tables Table 1: ADT variables from GDRT traffic count data (Station ID: 0325, 2011) Table 2: ADT Estimates (Using AM peak hour flows)Table 3: ADT Estimates (Using PM peak hour flows) Table 4: Performance Criteria Table 5: 2019 Intersections Performances

Figures Figure 1: Locality Plan Figure 2: Aerial View Figure 3: Strategic Provincial Road Network Figure 4: 2014 Baseline Traffic Volumes (AM Peak) Figure 5: 2014 Baseline Traffic Volumes (PM Peak) Figure 6: K109 Traffic Net Traffic Diversion Effect (AM Peak) Figure 7: K109 Traffic Net Traffic Diversion Effect (PM Peak) Figure 8: Baseline Traffic Volumes with K109 (AM Peak) Figure 9: Baseline Traffic Volumes with K109 (PM Peak) Figure 10: 2019 Background Traffic Volumes with K109 (AM Peak) Figure 11: 2019 Background Traffic Volumes with K109 (PM Peak) Figure 12: 2034 Background Traffic Volumes with K109 (AM Peak) K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Figure 13: 2034 Background Traffic Volumes with K109 (PM Peak)

Appendices

Preliminary Design Drawing

Traffic Impact Assessment| Final| July

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

1 Introduction

Aphane Consulting CC was appointed by Gauteng Department of Roads and Transport to undertake a traffic study for the detailed design of K109 between Halfway House and Olifantsfontein, North. The K109 forms part of Gauteng Department of Transport (GDRT) future road network planning aimed to enhance connectivity within the province and to other provinces. The K109 in its entirety is planned to run in a north-south direction commencing from (Old Pretoria Main Road) in Halfway House and terminating at in Brakfontein. Figures 1and 2 shows the extent of K109 between Halfway House and Olifantsfontein and Figure 3 shows the K109 in the context of the future road network planning. The purpose of this study is to inform the detailed design of the route with regards to design standards that are applicable in terms of lane requirements, pavement design and access management.

2 Scope of Study

It is important to note that the study is not intended to deal with any proposed township applications or to provide an opinion on any application that has been submitted. The scope of the study entails the following:  To determine the expected heavy vehicles along the corridor for the estimation of E80 axial loading to be used in the pavement design  Estimate expected future traffic volumes over 20 year design period to establish typical design requirements for the road as a single or dual carriageway;  Conduct capacity analysis to determine concept designs of the proposed intersection as well as the required intersection control;  Review the proposed access/intersection positions against the Road Classification and Access Management (RCAM) requirements and recommend changes if necessary; and  Assessment non-motorised transport (NMT) and public transport requirements along the proposed corridor.

3 Background to K109

The K109 forms part of GDRT future road network planning aimed to enhance connectivity within the province and to other provinces. The K109 is planned to run in a south-north direction commencing from R101 (Old Pretoria Main Road) in Halfway House and terminating at M39 in Brakfontein. This route will provide an alternative to the congested and Old Pretoria Road (R101) as well as Allan Road in connecting and Centurion. This study, however, only addresses the portion of K109 between Halfway House and (K27) in Olifantsfontein. The route alignment is planned off bituminous Dale Road through undeveloped land, round the Glen Austin nature reserve, to join the alignment of

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 1

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Van Rebeeck Road and thereafter stretches over undeveloped land until its intersection with R562 (K27). Van Rebeeck Road intersects with George road and Olifantsfontein Road (D795) along its length.

4 Surrounding Road Network

Allan Road

Allan Road/ Modderfontein Road runs in a north- south direction starting from Dale Road and intersecting with Douglas Road, George road and Olifantsfontein Road and terminating at its intersection with R562 (K27). Allan Road/ Modderfontein Road functions as a class 3 road, a minor arterial. It is a single carriageway with one lane in each direction.

Dale Road

Dale Road functions as a connector road road running in an east –west direction. Dale road starts from Old Pretoria Road (R101), intersects with Allan Road/ Modderfontein Road () and several local access roads to the surrounding residential areas along its length and ends as a cul de sac in Kaalfontein. Dale Road is a single carriageway road with one lane in each direction.

Van Reibeeck Road

Van Rebeeck Road is a gravel Road which functions as an access road on the western boundary of Glen Austin AH residential area.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 2

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Douglas Road

Douglas Road functions as a local access road within the Glen Austin AH residential area. It runs in an east-west direction has one lane in each direction throughout its length. Douglas Road is 5m wide and has traffic calming in the form of speed bumps.

George Road

Similar to Douglas Road, George Road functions as a local access road within the Glen Austin AH residential area. It also runs in an east-west direction starting from Van Rebeeck Road, intersecting with Allan Road/ Modderfontein Road and Old Pretoria R oad ending as a cul de suc just before the . George Road has one lane in each direction throughout its length. It is 5m wide and has traffic calming in the form of speed bumps

Olifantsfontein Road

Olifantsfontein Road also runs in running in an east-west direction. It connects Olifantsfontein to the north-western suburbs of Johannesburg. Olifantsfontein starts as a class 3 road at its intersection with R562 (K27) until its intersection with the Old Pretoria Road. Thereafter, it proceeds as a class 2 road to Plantation Road in Midrand.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 3

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

R562 (K27)

R562 (K27) is a provincial road running in an east-west direction that extends between R101 and in Tembisa. Olifantsfontein is a dual carriageway road with two lanes in each direction.

5 Existing Traffic Volumes

Detailed traffic counts were undertaken on Thursday, 19 June 2014 as part of the K109 corridor study at the following intersections:  Allan Road/Dale Road;  Dale Road/Archefish Drive;  Dale Road / Licensing offices Access;  Douglas Road/ Van Riebeeck Road;  George Road/ Van Riebeeck Road;  Olifantsforntein Road / Van Riebeeck Road; and  Olifantsfontein Road / R562 (K27) These traffic counts are summarised in Figures 4 and 5 for the AM and PM peak hours respectively. The following observations can be made:  Allan Road: The AM two-way traffic flow between Dale Road and Douglas Road is 937veh/hr. There is approximately a 70:30 split in north: south traffic flow. During the PM this section of the road experiences similar traffic volumes (914veh/hr.) as the AM peak hour with an approximate balanced split in north: south flow;  Dale Road: The section of Dale Road between Allan Road /Modderfontein Road and Archerfish Drive has two-way traffic flow of 1075veh/hr during the AM peak hour with a 30: 70 directional split in east: west flow. The PM two-way traffic flows are slightly higher at 1274veh/hr with a directional split of 75:25 in east: west flow;  Van Riebeeck Road: This road has low traffic volumes, not exceeding 80 veh/hr during the AM and PM peak hours;  George Road: The two-way traffic flow of George Road just before its intersection with Van Riebeeck Road are less than 50 veh/hr for both the AM and PM peak hours;

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 4

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

 Douglas Road: Similar to George Road, traffic flows on Douglas road before its intersection with Van Riebeeck Road are very low, not exceeding 60veh/h during the AM and PM peak hours;  Olifantsfontein Road: The two-way traffic flow on Olifantsfontein Road from R562 (K27) to Van Riebeeck Road is approximately 640veh/hr and 1140veh/hr during the AM and PM peak hour respectively; and  R562 (K27): The two-way traffic flow east R562 (K27) / Olifantsfontein Road intersection ranges between 2850 and 3200veh/hr during the AM and PM peak hours. The road section west of R562 (K27) / Olifantsfontein Road intersection has flow ranging between 2000veh/hr and 2300 veh/hr. This is a result of significant turning movements from the R562 (K27) eastern approach onto Olifantsfontein Road and vice versa.

6 Trip Generation

Once developed, the K109 is expected to have similar characteristic to Allan Road/ Modderfontein Road (Modderfontein Road). Although the link is not expected to generate new traffic on the network, it is however expected to trigger traffic re-distribution and diversion on the surrounding road network. An assessment of the expected traffic diversion and re-distribution is given in Section 7.

7 Traffic diversion and re-distribution assessment

Key infrastructure interventions, such as the proposed K109 link, usually affect traffic patterns in the surrounding road network based on the notion ‘build it and they will come’. The most likely impact could be re-distribution of traffic from congested parallel routes to take advantage of the additional network capacity. A SATURN model, which was developed for traffic impact assessment in the Waterfall and Modderfontein area was used to assess the traffic diversion as a result of the introduction of the link. The model does have high level representation of the area and include the major roads in the wider area. However, the model lacks sufficient detail for intersection capacity analysis in the immediate vicinity to the location of the new link. Due to the complicated nature of the traffic diversion assessment, it was decided that the SATURN model be used for an assessment of traffic diversion and re-distribution whilst the detailed intersection capacity analyses were carried out using data from manual data count. Thus, the traffic that is expected to be diverted to the proposed link was superimposed on traffic flow data from manual turning counts. The graphics below illustrate the traffic diversion effect of the proposed K109 link. The graphics represent a ‘with and without’ K109 scenarios. The blue (negative) numbers represent traffic diversion from the link, and the green (positive) numbers represent an attraction to the road links. The analysis was carried out for both AM and PM scenarios.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 5

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Picture 1: K109 Traffic diversion (AM)

Picture 2: K109 Traffic diversion (PM) The analysis demonstrated that the link could attract about 600 vehicles in either the northbound or southbound direction during the AM peak hour, from the surrounding road network, most notable Allan Road, Republic Road and the R101. In the PM peak hour the link is expected to attract about 650 and 400 vehicles, in the northbound and southbound directions respectively.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 6

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

The traffic attracted to the link in the diversion assessment was superimposed on the traffic count data for capacity analysis. The model traffic distribution was used to distribute the attracted traffic along the proposed K109 link. Figures 6 to 9 show the traffic distribution for ‘with and without’ K109 scenarios for the base year (2014)

8 Forecast Traffic

According to the South African Engineering Service Contribution Manual for Municipal Road Infrastructure COTO TMH 15 (2012), Structural design life for road pavements is typically 20 years. Thus for the purposes of pavement design the traffic volumes have been forecasted to year 2034. A 5-year design horizon (i.e. 2019) was used in accordance with the guidelines of traffic impact studies for the assessment of intersection capacity. The future levels of traffic have been estimated based on the following:  Manual turning count data;  Traffic diversion assessment;  Traffic yearbook data by the Gauteng Department of Roads and Transport (GDRT, 2010 & 2011) The base year (2014) was derived from the traffic diversion using the Modderfontein SATURN model and the manual traffic counts as discussed in the previous section of this report. The growth rate per annum was established using Traffic yearbook data by the Gauteng Department of Roads and Transport (GDRT, 2010 & 2011). The latest counts (2012 and 2013) data that was available from the GDRT but was not used as it was from different seasons and did not offer a good basis for comparative assessment. However the 2010 and 2011 data is comparable as the counts were conducted during the same period of the year. Counts station ‘0325’, Zuurfontein Roa d between Chloorkop and Modderfontein was deemed to be the closest representative count site for purposes of traffic growth and Average Daily Traffic (ADT) estimates on the proposed K109 link. From the count data, it was established that there has been a 3.5% negative traffic growth during the peak hours as well as throughout the day between 2010 and 2011. A view was therefore taken that a 1% pa (positive) growth rate would be a more suitable growth rate for this area. Future peak hour traffic demand is depicted in Figures 10 to 13. Variables that could be used for peak hour / ADT traffic conversions were extracted from the GDRT count data and are tabulated below: These variables were applied to the peak hour traffic flows to estimate Average Daily Traffic (ADT) and Average Daily Truck Traffic. The final (ADTT) estimates are given in Passenger Car Units (PCUs) or Equivalent Vehicle Units (EVUs).

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 7

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Table 1: ADT and ADTT variables from GDRT traffic count data (Station ID: 0325, 2011) Variable AM Peak Hour PM Peak Hour k-Factor* 0.102 0.088 % Heavies** 3.5% 3.6% *k-Factor is defined as a proportion of peak hour traffic in comparison to ADT. ** As per the GDRT guidelines, 1 heavy vehicle is defined as equivalent to 3 Passenger Car Units (PCUs). The computation of the ADTs for the 2014 baseline and future horizon year is shown in the diagram below and summarised in Tables 2 and 3 for the AM and PM peak hour data respectively. K109 Average Daily Traffic (ADT) Estimates

Table 2: ADT and ADTT Estimates (Using AM peak hour flows) Peak Hour Daily

Year ADT ADT NB SB Total ADTT (Total Vehicles) (PCUs) 2014 737 746 1483 14,512 508 15,527 2019 775 784 1559 15,255 534 16,323 2034 899 910 1809 17,702 620 18,941

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 8

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Table 3: ADT and ADTT Estimates (Using PM peak hour flows) Peak Hour Daily Year ADT ADT NB SB Total ADTT (Total Vehicles) (PCUs) 2014 807 471 1278 14,491 522 15,535 2019 848 495 1343 15,228 548 16,325 2034 985 575 1560 17,689 637 18,963 The results show that the 20 year ADT and ADTT estimate for the proposed new K109 link is approximately 18,000 vehicles per day of which 640 are heavy vehicles respectively. It is recommended that E80 value be based on these volumes. The year 2034 estimated two-way peak hourly total traffic volume for the proposed K109 is 1510 veh/hr. According to the Gauteng Department of Public Transport, Road and Work Road Design Manual, a single carriageway with two lanes (one lane in each direction) would provide sufficient capacity for the proposed K109.

9 Analysis Method and Scenarios

The base year (2014) has not been analysed as the existing volumes along Van Riebeeck Road are low and by observation, the current traffic operations are deemed acceptable. The upgrade of this route to full K-route standard requires that all informal/temporary accesses on the proposed alignment are closed and that access is taken from approved intersection points that were determined during the preliminary design of this route (see Appendix A). In addition to this, existing metropolitan roads, provincial roads and future K-routes which cross the K109 were also considered when evaluating the future traffic flows.

9.1 Access assessment In general road networks are designed to serve two purposes and that is to provide mobility and access of people and goods between their origins and destinations. Access management is a systematic control of access to developments so as to maintain road safety for all users whilst ensuring efficient usage of the road network by balancing accessibility and mobility. This is achieved by the carefully planning of access location, access and intersection design and operation of driveways, median openings and street connections, among other road network characteristics. The South African Road Classification and Access Management Manual classifies and defines urban mobility and access as shown in diagram below which illustrates the interaction and transition between mobility and accessibility.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 9

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Functional road classification – balancing mobility and accessibility

The K109 is planned to function as a Class 3 road, a minor arterial, which means limited access will be allowed. The South African Road Classification and Access Management Manual recommends a spacing between intersections of 600m +/- 20% on Class 3 roads. These guidelines are in accordance with GDRT standards. A review of the preliminary design indicates that the proposed intersections along the proposed K109 meet the minimum spacing requirements for a class 3 road.

9.2 Crossing Roads For the purposes of this study, K109 is planned to intersect with the following roads:  Dale Road: The K109 is planned to be the third leg forming a T-junction with Dale Road ;  Douglas Road: Douglas road would be extended to intersect with K109 to form a T- Junction;  George Road: The planned future intersection would be at the current location of the George Road and Van Riebeeck Road T-junction;  Olifantsfontein Road: The planned future intersection would be at the current location of the Olifantsfontein Road and Van Riebeeck Road intersection; and  R562 (K27): The propose K109 is planned to be the third leg at its intersection with R562 (K27) forming new T-junction. Each of these intersections has been analysed in this study.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 10

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

9.3 Scenarios Only one scenario was assessed: 2019 AM and PM peak hour future traffic using 1% per annum growth in background traffic as previously articulated in section 8 of this report.

9.4 Analysis Software The proposed intersections along K109 were assessed using SIDRA Intersection Software. The purpose of the analyses was to determine concept designs of the proposed intersections as well as the required intersection control by considering level of service (LOS), volume / capacity (v/c) and delays. The performance criteria for the intersections are indicated in Table 4 below. The level of service (LOS), delay and volume / capacity (v/c) have been defined in accordance with the Highway Capacity Manual (HCM 2000) . In addition, if a signal controlled intersection operates at a v/c ratio of more than 0.95, it is regarded as operating at capacity. Table 4: Performance Criteria

CONTROL DELAY PER VEHICLE (Seconds (d))

LEVEL OF SERVICE Signal and Stop and Give-Way / Roundabouts Yield Signs

A d ≤ 10 d ≤ 10 B 10 < d ≤ 20 10 < d ≤15 C 20 < d ≤ 35 15 < d ≤25 D 35 < d ≤ 55 25 < d ≤ 35 E 55 < d ≤ 80 35 < d ≤ 50 F d > 80 d ≤ 50

9.5 At-grade Intersections As previously stated, the projected traffic flows have shown the need for the K109 to be a single carriageway facility, with one traffic lane per direction. At the intersections the approaches need to be widened to allow for separate turning movement lanes. A 5 year horizon was applied for the assessment of the intersection capacity analysis also using 1% per annum growth rate. The diagrams below outline the proposed intersection configurations.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 11

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

R562 (K27)/K109  Proposed to be a signalised T-junction.  R562 (K27) eastbound – dual carriageway with double straight ahead lanes and one 60m right turning slots into K109;  R562 (K27) westbound – dual carriageway with a single 60m separate left turning slot and double straight ahead lanes;  K109 northbound – single carriageway with a 60m right turning slot and single left turning lanes.

Olifantsfontein Road (D795)/K109  Proposed to be a signalised four legged intersection.  Olifantsfontein Road (D795) eastbound – single carriageway with a 60m right turning lane, one through lane and one 60m slip lane one through left right into K109;  Olifantsfontein Road (D795) westbound – single carriageway with one through and left turning lane and a single 60m right turning slot;  K109 northbound – single carriageway with a 60m right turning slot, a 90m approach lane for the through and right turning movements and a single lane for the through and left turning movements; and.  K109 southbound – single carriageway with a 60m right turning slot and a single lane for the through and left turning movements.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 12

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

George Road/K109

 Proposed to be a priority controlled T-junction with K109 as the major road;  George Road westbound – single carriageway with a single lane for left and right turning movements into K109;  K109 northbound – single carriageway with a single through lane and 60m left turning movements; and.  K109 southbound – single carriageway with a 60m right turning slot and a single through lane.

Douglas Road/K109  Proposed to be a priority controlled T-junction with K109 as the major road;  Douglas Road westbound – single carriageway with a single lane for l eft and right turning movements into K109;  K109 northbound – single carriageway with a single through lane and 60m left turning movements; and.  K109 southbound – single carriageway with a 60m right turning slot and a single through lane.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 13

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Dale Road/K109  Proposed to be a priority controlled ‘Y’ shaped intersection with K109 as the major road;  Dale Road westbound – single carriageway with a single lane for left and right turning movements into K109;  K109 northbound – single carriageway with a single t hrough lane and 60m right turning movements; and.  K109 southbound – single carriageway with a 60m left turning slot and a single through lane.

Table 5 show the results for the AM and PM peak hours for the proposed intersection layouts.

Table 5: 2019 Intersections Performances

Intersection AM Peak Hour PM Peak Hour

V/C V/C LOS LOS Type Name Demand Demand Approach Delay (sec) Delay (sec)

K109 – Northbound 393 0.45 27.0 C 424 0.53 27.3 C R562 (K27) – 1861 0.80 16.8 B 1104 0.44 11.6 B Westbound R562(K27) – 881 0.43 10.8 B 1375 0.68 13.0 B Eastbound Traffic signals R562 (K27)/K109 Overall 3135 0.80 16.4 B 2903 0.68 14.6 B

K109 – Northbound 709 0.89 30.4 C 720 0.70 15.2 B Olifantsfontein Road 1149 0.95 31.7 C 444 0.33 7.1 A (D795) – Westbound K109 – Southbound 312 0.51 19.7 B 223 0.38 11.4 B Olifantsfontein Road Traffic signals Olifantsfontein 402 0.37 12.4 B 483 0.70 11.5 B

Road(D795)/K109 (D795) – Eastbound Overall 2573 0.95 26.9 C 1871 0.70 11.9 B

K109 – Northbound 687 0.35 0.1 A 720 0.37 0.1 A George Road – 677 0.34 0.1 A 457 0.23 0.2 A Westbound K109 – Southbound 23 0.06 15.2 C 2 0.01 24.4 C Traffic signals

George Road/K109 Overall 1387 0.35 0.3 A 1179 0.37 0.1 A

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 14

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

Intersection AM Peak Hour PM Peak Hour

V/C V/C LOS LOS Type Name Demand Demand Approach Delay (sec) Delay (sec)

K109 – Northbound 676 0.34 0.1 A 731 0.37 0.1 A Douglas Road (D795) – 669 0.32 0.1 A 448 0.22 0.2 A Westbound

Douglas K109 – Southbound 23 0.06 14.1 B 2 0.01 24.4 C Traffic signals

Road(D795)/K109 Overall 1368 0.34 0.4 A 1181 0.37 0.2 A

Dale Road – 173 0.33 14.6 B 91 0.15 12.0 B Westbound K109 – Southbound 665 0.42 5.5 A 443 0.29 5.4 A

K109 – Eastbound 861 0.35 5.0 A 893 0.38 5.0 A Dale/K109 Traffic signals Overall 1654 0.42 6.2 A 1426 0.38 5.6 A

The results for the AM and PM peak hours shown in Table xx demonstrate that the proposed intersection layouts are expected to operate at good level of service.

10 Public Transport and Non-Motorised Transport

A notable number of pedestrians and cyclists were observed using Dale Road and Van Riebeeck Road during a site visit. These are likely Thembisa residents who rely mostly on public transport and walking and cycling to access places of employment in Glen Austin and the surrounding areas. It is likely that over time these movements will increase thus proper pedestrian accommodation along the K109 corridor is considered important to the extent that it is suggested that a pedestrian walkway of approximately 1.8m width is constructed along western side of K109. This walkway would be wide enough to also accommodate cyclists. It is also recommended that the upgraded intersections should be designed in line with Universal access principals. The only public transport services provided in the area are taxis travelling along Allan Road, Olifantsfontein Road and the R562 (K27). Once the K109 is constructed, taxi services can be expected to run on this corridor as well. Thus it is recommended that proper taxi/bus pick-up and drop-off facilities should be provided in accordance with the latest GDRT guidelines for such facilities along K-routes at the following intersections:  K109/ R562 (K27);  K109/ Olifantsfontein Road;  K109/ George Road;  K109/ Douglas Road;  K109/ Dale Road.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 15

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

11 Conclusions and recommendations

Aphane Consulting CC was appointed by the Gauteng Department of Roads and Transport to undertake a traffic study inform the detailed design of a portion of K109 between Halfway House and Olifantsfontein, Johannesburg North with regards to design standards that are applicable in terms of lane requirements, pavement design and access management. The following conclusions can be drawn from this analysis:  The 20 year traffic volumes for the proposed K109 link have been estimated to be approximately 19 000 vehicles per day of which 640 are heavy vehicles. It is recommended that E80 value be based on these volumes.  The estimated year 2034 two-way peak hourly total traffic volume for the proposed K109 is 1800 veh/hr. According to the Gauteng Department of Public Transport, Road and Work Road Design Manual, a single carriageway with two lanes (one lane in each direction) would provide sufficient capacity for the proposed K109.  The K109 is planned to function as a Class 3 road, a minor arterial, which means limited access will be allowed. The South African Road Classification and Access Management Manual recommends a spacing between intersections of 600m +/- 20% on Class 3 roads. A review of the preliminary design indicates that the proposed intersections along the proposed K109 meet the minimum spacing requirements for a class 3 road.  The following intersection layouts and intersection control are recommended for five proposed intersection along the proposed K109: o R562 (K27)/K109 Proposed to be a signalised T-junction. R562 (K27) eastbound – dual carriageway with double straight ahead lanes and one 60m right turning slots into K109; R562 (K27) westbound – dual carriageway with a single 60m separate left turning slot and double straight ahead lanes; and K109 northbound – single carriageway with a 60m right turning slot and single left turning lanes. o Olifantsfontein Road (D795)/K109 Proposed to be a signalised four legged intersection. Olifantsfontein Road (D795) eastbound – single carriageway with a 60m right turning lane, one through lane and one 60m slip lane one through left right into K109; Olifantsfontein Road (D795) westbound – single carriageway with one through and left turning lane and a single 60m right turning slot; K109 northbound – single carriageway with a 60m right turning slot, a single lane for the through and right turning movements and a single lane for the through and left turning movements; and.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 16

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

K109 southbound – single carriageway with a 60m right turning slot and a single lane for the through and left turning movements. o George Road/K109 Proposed to be a priority controlled T-junction with K109 as the major road; George Road westbound – single carriageway with a single lane for left and right turning movements into K109; K109 northbound – single carriageway with a single through lane and 60m left turning movements; and. K109 southbound – single carriageway with a 60m right turning slot and a single through lane. o Douglas Road/K109 Proposed to be a priority controlled T-junction with K109 as the major road; Douglas Road westbound – single carriageway with a single lane for left and right turning movements into K109; K109 northbound – single carriageway with a single through lane and 60m left turning movements; and. K109 southbound – single carriageway with a 60m right turning slot and a single through lane. o Dale Road/K109 Proposed to be a priority controlled ‘Y’ shaped intersection with K109 as the major road; Dale Road westbound – single carriageway with a single lane for left and right turning movements into K109; K109 northbound – single carriageway with a single through lane and 60m right turning movements; and. K109 southbound – single carriageway with a 60m left turning slot and a single through lane.  The upgrade of this route to full K-route standard requires that all informal/temporary accesses on the proposed alignment are closed and that access is taken from approved intersection points that were determined during the preliminary design of this route.  There are currently a notable number of pedestrians and cyclists were observed using Dale Road and Van Riebeeck Road during a site visit. It is likely that over time these movements will increase thus proper pedestrian accommodation along the K109 corridor is considered important to the extent that it is suggested that a pedestrian walkway of approximately 1.8m width is constructed along both sides of K109. These walkways would be wide enough to also a accommodate cyclists.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 17

K109 TRAFFIC IMPACT STUDY

APHA NE CONSULTING GAUTENG DEPARTMENT OF ROADS AND TRANSPORT

 It is recommended that taxi/bus pick-up and drop-off facilities should be provided in accordance with the latest GDRT guidelines for such facilities along K-routes at the following intersections: o K109/ R562 (K27); o K109/ Olifantfontein Road; o K109/ George Road; o K109/ Douglas Road; and o K109/ Dale Road.

TRAFFIC IMPACT ASSESSMENT| FINAL| JULY Page 18

Figures

Locality Plan - Figure 1

) 1 Louwlardia 0 1 R ( duff Ave a d alak lyjames M R Bal g ° r u b s l e y n O a n l i e w a ve h h n h v

g o h c A i J s Ye b o bo f h r H t f s o d u n A l u O v n

Rd e a O d s m e nd e

W o ra m m a a h S a t c j

e y

S l

d r l l

R n a t o i o e u B pr B Courtday Elevation Ave iets R R d Kosmosdal e l Av Corporate a rks a a St.Andrews Blvd. r ndm k La Park North

s Dr. Beauly Ave i i

u i

h

i

o y a o w Hawa R Randjesfontein h g i

Lev Headway H

L e n t r

i R

s d a e Hill l o m y l m e Fir P r b R lle Rd e o e d o L l. n i F h ly n c ibovi o S R S n e S t B re

l

i t z Ever

i fair Ave a k

G A c Ol a if ve u Ki an e ze ng t w b W sfo h d il n ll lo te c e w in e Cr Rd e Rh e . (R L 5 62) Graham Rd Jav Nyala La. Suni a Rd . King Willow Cr

e

b

e

Rd s d

T s I a s e R

ter m i d

rs b u e

O r R gi li lie t fan l tsf

lne o Ci nt Po 1 ein 4th Rd Mi Rd (R5 62) 8th Rd

Packa

rd S

Fred Noordwyk t d

o er tein Rd o i

ck Dr. Olifantsfon E w ss d e n R e r

e Rd d

e

v

l

e

eeck H

B b a e George m Rd p

t o

Bronberg St n

Van Ri

R d Erand ) 1

0 Gardens 1 R Glen ( h Rd d

R

Pitzer Rd Austin 15t

George R d d n i

a R A.H. Erand M n a i r Alla R o rt d A.H. t Robe e . r

P Pl

d s ' l

O sie

Ro 13th Rd

d Dougla R s Rd

n Midridge i t s u 6th Rd ) Park 1 D A 1 on 0 o van 1 S R t (

Gle Med d i R cal R d n St n i a R ainbo N Randjespark M w St 3rd Rd ew R a d i r

a Ne o i w t r Rd Dale e a r v P a d

B l

O N e 1 w N R D d o n o v an R d

N1

n

R ai

d M ( a i

2nd St R r 1 o

t 0 e

1 r Halfway ) P House Dale Rd K109 UNDER REVIEW Pretoriu 2nd Rd President Bro adwalk K Di S r Park A.H. t u 0175 350 700 1 050 1 400 1 750 m

a B g M s

e

e gonal S R

v ond St o A

a r r d d d A A R le derfont

xa t

itke n d

n S B P S

t l v

e e

d l k a t . a C k w tr t

n b T Ce i rot S o r ein R Pa d P r o n o. t n a R N r B r n o G S

rt r e e e v

h o t Ma gro St t a

South o n illa

t v . k a d n S d ga r

d r Fo u a t oP

t i m C t R

i w a B n

u a S u h S M t G I ic

a M che Rd g l

t o i S

k e a t l r l B b it a S u z o a l m u A i h os a i t n c Swar i B p v r l x c e Ivory e u h e C R h y l. a R C off b c ch S d v d and Rd Stey I t Dr r R o t B t A L Fin ( n R Park

eana

R e

. d Fuch T

n S i d h K

1 s n ia St u

re e t m 0 Upgrading of the K109 from Dale Road to R562 (K109) k P K Rd S h a 1 o l Drac e z o Richards Dr. upto ) n a L w a 237074 © Arup Source: The information is derived from the Corporate Geo-Informatics (CGIS) database of the City of Johannesburg. CGIS does not assume any liability for the damages arising from errors, ommissions or the use of this information. Users of the information are advised to use this data appropriately. Aerial View - Figure 2 ° Everfair Ave Randjesfontein lElevation Ave

Riboville Rd

562) Olifantsfontein Rd (R Graham R d

rs Rd

illie Rd

r

PotgieterRd C

e

n

l

Mi

ntein Rd Olifantsfo

d R e r e d e v l e B

ebeeck Rd

H Glen Ri a m n

p Austin Va t

o

n A.H.

R d

George Rd

Robert Rd

Douglas Rd

e al

G D

l e Ra n inbo w St S t K109 UNDER REVIEW

075 150 300 450 600 750 m

e Rd Dal Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, UpgradingPresident of the K109 from Dale Road to R562 (K109)Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Park A.H. Community 237074 Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community © Arup Source: The information is derived from the Corporate Geo-Informatics (CGIS) database of the City of Johannesburg. CGIS does not assume any liability for the damages arising from errors, ommissions or the use of this information. Users of the information are advised to use this data appropriately. Strategic Provincial Road Network - Figure 3

l a a r k s i ) u 1 K22 h 0 0 i 1 o R o ( ° R d R

g l r u b s e n n a h o J d Samrand l O

1

N1/2

y a

w 1 h g i

H ) 1 ) n Rd (R562 K27 a 0 Olifantsfontein 1 m R K11 e ( o d h c R

S n i

n a e M Olifants B a i fon r K109 o tein t Rd e (R562) r P

d l

O Oli fantsfon tein Rd (R562)

d

R er PWV ev 5 L

1

0

1

K

Rd

n

lla

A

)

1

0

1

R (

d

R

n i

a

M

a New Rd i r

o t

e r

P

d N1/21 l

O

K

N1 56

) 1 0 1 R ( d R n i a M a i r o t e r P K109 UNDER REVIEW

Mod 0225 450 900 1 350 1 800 2 250 m derf

ontein Rd

K111 Upgrading of the K109 from Dale Road to R562 (K109) 237074 © Arup Source: Gautrans Schematic (NTS) +27 +27 218 11 7600

936 b b 647 12 11 10 3 2 1

346 a b 232 232 183

865 407 663

c c b a

b 112 b 09 09 Allan Rd Modderfontein Rd 8 9 e e

a b c d e 67 523 365 14 73 119 274 f

4 5 6 88 7

610 b b 432 Olifantsfontein Rd Olifantsfontein Upgrading of the K109 from Dale Road to R562 (K27) R562 to Road Dale from K109 the of Upgrading Dale Rd Dale

756 b b 319 2014 Baseline (AM) Baseline 2014 12 11 10 3 2 1

639 a b 242

699 77

c c b

b 60 08 08

7 8 9 Douglas Rd Douglas George Rd George e a b 117 271 29

4 5 6

b b b b 1412 779 334 795 20 20 6 6 b b b b

146 b b 137 10 12 11 10 12 11 10 12 11 10 12 11 10 12 11 10 12 11 3 2 1 4 3 2 1 4 3 2 1 1 1 3 2 1 a a b b a a b 36 321 795 20 20 2 9 4

137 2 31 33 33 20 20 20 40 41 7

c

c c

a c c b a b a a 3 3 b b b b b b 106 b b 33 5 02 04 03 06 05 07 04 03 02 07 06 05

Van Riebeeck Rd (K109)

7 8 9 8 9 8 9 7 8 9 7 8 9 8 9 e e e e e e e e d d a c a 6 d e 6 a b c d e 9 b e 1412 734 139 3 3 146 8 2 138 139 139 6 6 6 12 12 12

f f

4 7 7 5 6 4 5 6 4 5 6 7

4 5 6 1 5 6 5 6 3

b b b b 1412 740 329 795 107 139 10 b b 33 b b Traffic DepartmentTraffic Dale Road Dale

1412 b 795 b 12 11 10 1

6 a 794 1

223 3 2

c c Fig: b

b 217 Job Ref No: 01 01

8 9 e a b 1406 664 4 235669 665 4 5 6 7

2070 b b 1011 H H

10 9 8 7 b 1242 11 1242 b 1242 10 9 8 7

b 12 b 1242 11 1239 1702 c 02 02 b 12 3 b

b 6 b 01

b b 818 b 818 5 818 a c 6

1 2 3 4 818 2 816 5 1155 463 a b b a 1 2 3 339 4

b e 465 342 9 b e 22

10 9 a b 9 8 7 1

418 11 401 21 402 c b 12 8 d e f b 03 Olifantsfontein Rd 03

b 6 b a b c c

217 196 5 201 a b b a 1 2 3 5 4

b e 13

b e 13 Van Van Riebeeck Rd (K109)

10 a 9 8 7

11 7 6 c b 12 d e

George Rd 0404 b a b 6 Rd 7 5

Allan 1 2 3 4

b e 6

b e 6 a 10 9 8 7

11 6

b 12 d

Douglas Rd 0505

b 6

6 5

1 2 3 4

10 9 8 7

11 185

12 e f b

0606 Dale Road

c 6 b

a a 5 2 185

1 2 3 2 4

b e 2 185 2 185 b e

10 9 8 7

11 1 1 9

12 e f b

0707 Traffic Department

b c 36 6 b

8 5 106 149 a c a 1 2 3 70 4

b e 71 157

407 b e 507

10 72 a b 9 8 7 10 9 8 7 b c

882 11 555 38 811 960 11 147 157 298 171 c b 12 255 d e f b b 12 813 b

0909 Dale Rd 0808

b 84 6 b b 6 b a b c c a b c

554 85 305 5 418 314 10 41 5 71 211 251 273 a b b a a b b a 1 2 3 29 4 1 2 3 30 4

b e b e 547 582 283 843 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2014 Baseline (PM) 5 H

10 b 9 8 7

11 246 10 b 9 8 7 c

b 12 b 246 11 246 492 c 02 02 b 12 b

b a c 6 b 01

108 5 270 b 6 b

108 246 a c a b b a 1 2 3 270 4 270 270 5 570 246 a b b a 1 2 3 300 4 b e 354 270 b e 300 246

354 b e 270

10 a b 9 8 7

30 11 246 270 c b 12 30 d e f b 03 Olifantsfontein Rd 03

b 6 b a b c c

5 300 354 246 a b b a 1 2 3 300 4

b e 600 600

600 b e 600 Van Van Riebeeck Rd (K109)

10 a 9 8 7

11 600 c b 12 d e

George Rd 0404 b a b 6 Rd 5 600

Allan 1 2 3 4

b e 600 600

600 b e 600

10 a 9 8 7

11 600 c b 12 d e

Douglas Rd 0505

b a b 6

5 600

1 2 3 4

b e 600 600

600 b e 600

10 9 8 7

11 600

12 e f b

0606 Dale Road 10 b

b c c 6

5 600

1 2 3 a 4

b e 600 600

600 b e 600

10 9 8 7

11 600 TrafficDepartment 12 e

0707

b 6

5 600

1 2 3 4

b e 600 600

b e a a b 10 9 8 7 10 b 9 8 7

408 11 408 600 600 11 600 600 c c b 12 d e f b b 12 b

0909 Dale Rd 0808

b 6 b b 6 b a b c c a b c

576 576 5 600 600 600 5 600 192 a b b a a b b a 1 2 3 24 4 1 2 3 4

b e b e 24 192 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 K109 Net Diversion effect (AM) 6 H

10 b 9 8 7

11 267 10 b 9 8 7 c

b 12 b 267 11 267 533 c 02 02 b 12 b

b a c 6 b 01

117 5 180 b 6 b

117 267 a c a b b a 1 2 3 180 4 180 180 5 380 267 a b b a 1 2 3 200 4 b e 384 180 b e 200 267

384 b e 180

10 a b 9 8 7

20 11 267 180 c b 12 20 d e f b 03 Olifantsfontein Rd 03

b 6 b a b c c

5 200 384 267 a b b a 1 2 3 200 4

b e 650 400

650 b e 400 Van Van Riebeeck Rd (K109)

10 a 9 8 7

11 400 c b 12 d e

George Rd 0404 b a b 6 Rd 5 650

Allan 1 2 3 4

b e 650 400

650 b e 400

10 a 9 8 7

11 400 c b 12 d e

Douglas Rd 0505

b a b 6

10 10 5 650

1 2 3 4

b e 660 400

650 b e 400

10 9 8 7

11 400

12 e f b

0606 Dale Road 10 b

b c c 6

5 650

1 2 3 a 4

b e 650 400

650 b e 400

10 9 8 7

11 400 TrafficDepartment 12 e

0707

b 6

5 650

1 2 3 4

b e 650 400

b e a a b 10 9 8 7 10 b 9 8 7

442 11 442 650 650 11 650 650 c c b 12 d e f b b 12 b

0909 Dale Rd 0808

b 6 b b 6 b a b c c a b c

384 384 5 400 400 400 5 400 208 a b b a a b b a 1 2 3 16 4 1 2 3 4

b e b e 16 208 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 K109 Net Diversion effect (PM) 7 H

10 b 9 8 7

795 11 795 1041 10 b 9 8 7 c

b 12 b 1041 11 1040 1503 c 02 02 b 12 1 b

b a c 6 b 01

1520 1412 5 1682 b 6 b

108 246 a c a b b a

1 2 3 270 4 1682 6 1676 5 2640 463 a b b a 1 2 3 964 4 b e 354 270 b e 965 469

361 b e 282

10 4 a b 9 8 7

364 11 321 9 3 575 270 c b 12 39 d e f b 03 Olifantsfontein Rd 03

b 3 6 b a b c c

779 36 734 5 1040 354 251 a b b a 1 2 3 303 4

b e 641 612

640 b e 612 Van Van Riebeeck Rd (K109)

10 20 a 9 8 7

20 11 6 606 c b 12 d e

George Rd 0404 b a b 6 Rd 6 5 620

Allan 1 2 3 4

b e 620 606

620 b e 606

10 20 a 9 8 7

20 11 6 600 c b 12 d e

Douglas Rd 0505

b a b 6

16 10 5 600

1 2 3 4

b e 610 600

610 b e 600

10 9 8 7 10 b 9 8 7

11 137 137 11 31 33 600 c 12 e f b b 12 106 b

0606 Dale Road 1010 b b b

b c c 10 6 a b c 6

5 156 156 8 2 148 5 149 600 137

1 2 3 a 146 4 1 2 3 1 4 a b b a

b e b e 10 737 746 107

737 b e 746

10 9 8 7

11 746 TrafficDepartment 12 e f

0707

b 6

5 737

1 2 3 4

b e 737 746 663 b e 274 a a b 10 183 9 8 7 10 b 9 8 7

1055 11 640 67 88 1032 919 11 677 737 119 c c b 12 232 d e f b b 12 242 b

0909 Dale Rd 0808

b 73 6 b b 6 b a b c c a b c

1512 1099 5 1210 1356 60 717 5 746 346 407 304 639 a b b a a b b a 1 2 3 38 4 1 2 3 29 4

b e b e 389 699 271 1057 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2014 Baseline, with K109 (AM) 8 H

10 b 9 8 7

1242 11 1242 1509 10 b 9 8 7 c

b 12 b 1509 11 1506 2235 c 02 02 b 12 3 b

b a c 6 b 01

935 818 5 998 b 6 b

117 267 a c a b b a

1 2 3 180 4 998 2 996 5 1535 730 a b b a 1 2 3 539 4 b e 384 180 b e 542 732

393 b e 202

10 9 a b 9 8 7 1

438 11 401 21 669 180 c b 12 28 d e f b 03 Olifantsfontein Rd 03

b 6 b a b c c

217 196 5 401 384 267 a b b a 1 2 3 205 4

b e 650 413

650 b e 413 Van Van Riebeeck Rd (K109)

10 a 9 8 7

11 7 406 c b 12 d e

George Rd 0404 b a b 6 Rd 7 5 650

Allan 1 2 3 4

b e 650 406

650 b e 406

10 a 9 8 7

11 6 400 c b 12 d e

Douglas Rd 0505

b a b 6

16 10 5 650

1 2 3 4

b e 660 400

660 b e 400

10 9 8 7 10 a b 9 8 7

11 157 157 11 149 185 400 c 12 e f b b 12 8 b

0606 Dale Road 1010 b b b

b c c 10 6 a b c 6

5 81 81 70 36 11 5 12 650 157

1 2 3 a 71 4 1 2 3 1 4 a b b a

b e b e 9 807 471 106

807 b e 471

10 9 8 7

11 471 TrafficDepartment 12 e

0707

b 6

5 807

1 2 3 4

b e 807 471

407 b e 507 a a b 10 72 9 8 7 10 b 9 8 7

1324 11 997 38 1461 1610 11 797 807 298 171 c c b 12 255 d e f b b 12 813 b

0909 Dale Rd 0808

b 84 6 b b 6 b a b c c a b c

938 689 5 818 714 10 441 5 471 211 251 293 273 a b b a a b b a 1 2 3 45 4 1 2 3 30 4

b e b e 755 598 283 843 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2014 Baseline, with K109 (PM) 9 H

10 b 9 8 7

836 11 836 1094 10 b 9 8 7 c

b 12 b 1094 11 1093 1580 c 02 02 b 12 1 b

b a c 6 b 01

1598 1484 5 1768 b 6 b

114 259 a c a b b a

1 2 3 284 4 1768 6 1761 5 2775 487 a b b a 1 2 3 1013 4 b e 372 284 b e 493 1014

379 b e 296

10 4 a b 9 8 7

383 11 337 9 3 604 284 c b 12 41 d e f b 03 Olifantsfontein Rd 03

b 3 6 b a b c c

819 38 771 5 1093 372 264 a b b a 1 2 3 318 4

b e 674 643

673 b e 643 Van Van Riebeeck Rd (K109)

10 21 a 9 8 7

21 11 6 637 c b 12 d e

George Rd 0404 b a b 6 Rd 6 5 652

Allan 1 2 3 4

b e 652 637

652 b e 637

10 21 a 9 8 7

21 11 6 631 c b 12 d e

Douglas Rd 0505

b a b 6

17 11 5 631

1 2 3 4

b e 641 631

641 b e 631

10 9 8 7 10 b 9 8 7

11 144 144 11 33 35 631 c 12 e f b b 12 111 b

0606 Dale Road 1010 b b b

b c c 11 6 a c 6

5 164 164 8 2 156 5 157 631 144

1 2 3 a 153 4 1 2 3 1 4 a b b a

b e b e 11 775 784 112

775 b e 784

10 9 8 7

11 784 TrafficDepartment 12 e

0707

b c 6

5 775

1 2 3 4

b e 775 784 697 b e 288 a a b 10 192 9 8 7 10 b 9 8 7

1109 11 673 70 92 1085 966 11 712 775 125 c c b 12 244 d e f b b 12 254 b

0909 Dale Rd 0808

b 77 6 b b 6 b a b c c a c

1589 1155 5 1272 1425 63 754 5 784 364 428 320 672 a b b a a b b a 1 2 3 40 4 1 2 3 30 4

b e b e 409 735 285 1111 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2019 Background, with K109 (AM) 10 H

10 b 9 8 7

1305 11 1305 1585 10 b 9 8 7 c

b 12 b 1585 11 1582 2349 c 02 02 b 12 3 b

b a c 6 b 01

983 860 5 1049 b 6 b

123 280 a c a b b a

1 2 3 189 4 1049 2 1047 5 1613 767 a b b a 1 2 3 566 4 b e 403 189 b e 570 769

413 b e 212

10 9 a b 9 8 7 1

460 11 421 22 703 189 c b 12 29 d e f b 03 Olifantsfontein Rd 03

b 6 b a b c c

228 206 5 421 403 280 a b b a 1 2 3 215 4

b e 683 434

683 b e 434 Van Van Riebeeck Rd (K109)

10 a 9 8 7

11 7 427 c b 12 d e

George Rd 0404 b a b 6 Rd 7 5 683

Allan 1 2 3 4

b e 683 427

683 b e 427

10 a 9 8 7

11 6 420 c b 12 d e

Douglas Rd 0505

b a b 6

17 11 5 683

1 2 3 4

b e 694 420

694 b e 420

10 9 8 7 10 b 9 8 7

11 165 165 11 157 194 420 c 12 e f b b 12 8 b

0606 Dale Road 1010 b b b

b c c 11 6 a c 6

5 85 85 74 38 12 5 13 683 165

1 2 3 a 75 4 1 2 3 1 4 a b b a

b e b e 9 848 495 111

848 b e 495

10 9 8 7

11 495 TrafficDepartment 12 e

0707

b 6

5 848

1 2 3 4

b e 848 495

428 b e 533 a a b

10 76 9 8 7 10 b 9 8 7

1392 11 1048 40 1536 1692 11 838 848 313 180 c c b 12 268 d e f b b 12 854 b

0909 Dale Rd 0808

b 88 6 b b 6 b a b c c a c

986 724 5 860 750 11 463 5 495 222 264 308 287 a b b a a b b a 1 2 3 47 4 1 2 3 32 4

b e b e 794 629 297 886 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2019 Background, with K109 (PM) 11 H

10 b 9 8 7

970 11 970 1270 10 b 9 8 7 c

b 12 b 1270 11 1269 1834 c 02 02 b 12 1 b

b a c 6 b 01

1855 1723 5 2052 b 6 b

132 300 a c a b b a

1 2 3 329 4 2052 7 2045 5 3221 565 a b b a 1 2 3 1176 4 b e 432 329 b e 572 1177

440 b e 344

10 5 a b 9 8 7 4

444 11 392 11 702 329 c b 12 48 d e f b 03 Olifantsfontein Rd 03

b 4 6 b a b c c

951 44 896 5 1269 432 306 a b b a 1 2 3 370 4

b e 782 747

781 b e 747 Van Van Riebeeck Rd (K109)

10 24 a 9 8 7

24 11 7 739 c b 12 d e

George Rd 0404 b a b 6 Rd 7 5 757

Allan 1 2 3 4

b e 757 739

757 b e 739

10 24 a 9 8 7

24 11 7 732 c b 12 d e

Douglas Rd 0505

b a b 6

20 12 5 732

1 2 3 4

b e 744 732

744 b e 732

10 9 8 7 10 b 9 8 7

11 167 167 11 38 40 732 c 12 e f b b 12 129 b

0606 Dale Road 1010

b b b

b c c 12 6 a c 6 2

5 190 190 10 181 5 182 732 167 a b b a

1 2 3 a 178 4 1 2 3 1 4

b e b e 12 899 910 131

899 b e 910

10 9 8 7

11 910 TrafficDepartment 12 e

0707

b 6

5 899

1 2 3 4

b e 899 910 809 b e 334 a a b 10 223 9 8 7 10 b 9 8 7

1287 11 781 82 1259 1121 11 826 899 145 107 c c b 12 283 d e f b b 12 295 b

0909 Dale Rd 0808

b 89 6 b b 6 b a b c c a b c

1845 1341 5 1476 1655 73 875 5 910 422 497 371 780 a b b a a b b a 1 2 3 46 4 1 2 3 35 4

b e b e 475 853 331 1290 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2034 Background, with K109 (AM) 12 H

10 b 9 8 7

1515 11 1515 1841 10 b 9 8 7 c

b 12 b 1841 11 1837 2727 c 02 02 b 12 4 b

b a c 6 b 01

1141 998 5 1218 b 6 b

143 325 a c a b b a

1 2 3 220 4 1218 2 1215 5 1873 890 a b b a 1 2 3 658 4 b e 468 220 b e 661 893

479 b e 246

10 11 a b 9 8 7 1

534 11 489 26 816 220 c b 12 34 d e f b 03 Olifantsfontein Rd 03

b 6 b a b c c

265 239 5 489 468 325 a b b a 1 2 3 250 4

b e 793 504

793 b e 504 Van Van Riebeeck Rd (K109)

10 a 9 8 7

11 9 495 c b 12 d e

George Rd 0404 b a b 6 Rd 9 5 793

Allan 1 2 3 4

b e 793 495

793 b e 495

10 a 9 8 7

11 7 488 c b 12 d e

Douglas Rd 0505

b a b 6

20 12 5 793

1 2 3 4

b e 805 488

805 b e 488

10 9 8 7 10 b 9 8 7

11 192 192 11 182 226 488 c 12 e f b b 12 10 b

0606 Dale Road 1010

b b b

b c c 12 6 a c 6

5 99 99 85 44 13 5 15 793 192 a b b a

1 2 3 a 87 4 1 2 3 1 4

b e b e 11 985 575 129

575 985 b e

10 9 8 7

11 575 TrafficDepartment 12 e

0707

b 6

5 985

1 2 3 4

b e 985 575

497 b e 619 a a b

10 88 9 8 7 10 b 9 8 7

1616 11 1217 46 1783 1965 11 972 985 364 209 c c b 12 311 d e f b b 12 992 b

0909 Dale Rd 0808

b 102 6 b b 6 b a b c c a b c

1145 841 5 998 871 12 538 5 575 257 306 358 333 a b b a a b b a 1 2 3 55 4 1 2 3 37 4

b e b e 921 730 345 1029 Modderfontein Modderfontein Rd

Schematic (NTS)

Job Ref No: Upgrading of the K109 from Dale Road to R562 (K27) 235669 Fig: +27 11 218 7600 2034 Background, with K109 (PM) 13

Appendix A

Preliminary Design Drawing