<<

The Urban Flood Control Project in the Mountainous Area in Province Loaned by the Asian Development Bank

The External Resettlement Monitoring & Assessment Report

( City, City, , City, County, , , Xintian County, Jianghua County, County, , City, City, City, Zhuzhou County and Youxian County)

No.1, 2008 Total No. 1

Hunan Water & Electricity Consulting Corporation

(HWECC)

September, 2008

Approved by: Wang

Reviewed by: Long Xiachu

Prepared by: Long Xiachu, Wei Riwen

2 Contents 1. Introduction 2. Project Outline 2.1 Project Outline 2.2 Resettlement Outline 3. Establishment and Operation of Resettlement Organizations 3.1 Organization Arrangement 3.2 Organization Operation 4. Project Implementation Progress 4.1 Jiangyong County 4.2 Chenzhou City 5. Resettlement Implementation Progress 5.1 Resettlement Implementation Schedule 5.2 Resettlement Policy and Compensation Standards 5.3 Progress of Land Acquisition 5.4 Progress of Resettlement Arrangement 5.5 Removal Progress of Enterprises and Institutions 5.6 Progress of Resettlement Area Construction 5.7 Arrival and Payment of the Resettlement Fund 6. Psychology and Complaint of the Resettled People 6.1 Complaint Channel 6.2 Complaint Procedures 7. Public Participation, Consultation and Information Publicizing 7.1 Jiangyong County 7.2 Chenzhou City 8. Existed Problems and Suggestions

3 1. Introduction

The Urban Flood Control Project in the Mountainous Area in Hunan Province (referred to as the Project in short) loaned by the Asian Development Bank (referred to as the Asian Bank in short) has started officially. According to the requirements of the Asian Bank, the Project has introduced the resettlement monitoring and assessment mechanism to monitor and assess the process of land acquisition and resettlement, as well as the quality and effect of the resettlement for the purpose of overall understanding of the resettlement and scientific decision-making by the Owner and the Asian Bank based on the monitoring assessment reports provided by the resettlement monitoring and resettlement institute.

According to the Minutes of meeting held on Apr. 29, 2007 by the Project Office and the fax issued on Aug. 16, 2007 by the Asian Bank, Hunan Water & Electricity Consulting Corporation (referred to as HWECC) would be responsible for the external monitoring and assessment of 16 non-core sub-projects including Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Jiangyong County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Chenzhou City, Zhuzhou City, Liling City, Zhuzhou County and Youxian County.

After signing of the resettlement monitoring and assessment contract, HWECC has contacted all project units actively and has signed resettlement monitoring and assessment contracts with 3 sub-projects including Jiangyong City, Chenzhou City and Liling City. Established in January of 2008, the Resettlement and Assessment Department for the Urban Flood Control Project in the Mountainous Area in Hunan Province

4 loaned by the Asian Development Bank (referred to the Resettlement and Assessment Department) in HWECC started its preparatory work, worked out the Resettlement Monitoring and Assessment Work Outline for the Urban Flood Control Project in the Mountainous Area in Hunan Province loaned by the Asian Development Bank (the draft) as well as the sub-project resettlement monitoring and assessment work outline and has begun the first stage monitoring and assessment. Since the Project has just started soon, the finished resettlement was not big and the progress was behind the resettlement plan. Therefore, the monitoring and assessment at this stage is focused on followings: (1). Establishment and operation of resettlement organizations. (2). Used resettlement policy and compensation standards . (3). Progress of land acquisition and Demolition. (4). Raising and payment of resettlement funds.

2. Project Outline

2.1 Project Outline

The Urban Flood Control Project in the Mountainous Area in Hunan Province covers 35 county-level cities in the mountainous area in Hunan Province which suffer severe floods, including 8 prefecture-level cities (the Zhuzhou City, City, Hengyang City, City, City, Chenzhou City, Shaoyang City, City and the City which is the capital city of the , as well as 27 counties (cities) under 12 Cities (prefecture).

The contents of the 16 non-core sub-projects undertaken by the HWECC include flood control projects, waterlogging projects, river dredging and bridges, etc., and the total investment is 1862,1127 million RMB Yuan, while the resettlement costs account for 452,9304 million RMB Yuan.

5 After implementation, the flood control and waterlogging standards of prefecture-level cities will be increased to 1-in-50 years and 1-in-20 years respectively, while the standards of county-level cities will be increased to 1-in-20 years and 1-in-10 years respectively, which means significant social and economic benefits. The basic information of the 16 sub-projects is shown in Table 2.1.

Table 2.1 Basic information of 16 non-core sub-projects

Planned Investment Resettlement No Project name Project Contents Schedule X103RMB X103RMB

Total (1).8.27 km dike. (2).11 culvers & construction gates. (3).2 drainage stations. period: 36 Lengshuijiang 1 (4).Flood control commanding months (33 97750 23346.6 City system and necessary months for management facilities. main project).

(1).Including 4 protection zones (Lantian, Guangming Street, Shimashan, Chengbei), 4 dikes with total length of 15.895 km Total Lianyuan (2.233 km embankment and construction 2 98758.2 16544.4 City 13.662 km flood control wall). period :48 (2).10 culverts and gates. (3). months Flood control commanding system and necessary management facilities.

(1).9.8 km dike. (2).12 culverts Total and gates. (3).2 drainage stations. Shuangfeng construction 3 (4).A 1.605km flood discharge 105460 15197.8 County period:48 channel, 2 flood discharge months. culverts with length of 1.13 km.

6 (1).Including 6 protection zones (Baitian, Shentan, Xiwaiwan, Shaoshuidonglu, Shaoshuixi, Total Shaoyang Maoping, Hongqihe), 7 dikes with construction 4 206530 33041.8 City total length of 12.174 km. (2).9 period: 48 culverts and gates. (3).1 months communication gate. (4).7 drainage stations (4800KW).

(1).Including 3 protection zones (Liangshitang, Xinglong and Meiling), 7 dikes with total length of 11.686km (11.148km embankment, 0.538km earth & rock embankment), 3.704 km Total slope protection, 3.069km bank construction protection. (2).7 culverts and gates period: 34 Shaodong 5 and 2 communication gates. months (23 127900 45625.6 County (3).Demolition of Caojiaba Dam, months for 10 abandoned pumping houses, 1 main bridge pier, 4 waste heaps. (4). project) 1.53km Majiawan flood discharge channel. (5).4 drainage stations (1290KW). (6). Flood control commanding system and necessary management facilities.

(1).8.219km dike. (2).5 culverts and gates, 2 communication gates. (3).3 drainage stations with 6 Total pumps and capacity of 784KW. Longhui construction 6 (4).1.8km river dredging and 3 76430 15423.1 County period: 48 sand dunes in the riverbed months (452,000m3). (5). Flood control commanding system and necessary management facilities.

Total (1). 4 dikes with total length of construction 6.67km (4.48 km embankment, period: 24 Jiangyong 2.19km flood control wall). (2). 4 7 months (20 44940 6900.8 County culverts and gates. (3). months for Consolidation and improvement main of 4 flood discharge channels. project)

7 (1).Enlargement of existing stone dike (6.514km). (2). 9.789 Total embankment. (3). 2.033km flood Xintian construction 8 control wall. (4). 0.61km bank 39824.5 11869 County period: 36 protection. (5). 2 culverts and months gates. (6). 2 pumping stations (4 units and 644 KW).

(1).3.6 km dike (2.85 km embankment, 0.75km masonry Total wall). (2). 3.6 km grass slope construction protection and 2.85 km masonry period: 34 Jianghua slope protection. (3).3 electric 9 months (28 52130 10748.7 County drainage stations (660KW). (4).3 months for culverts and gates. (5).3.6 km main surface hardening of flood control project) dike. (6). clearing up obstacles in the river.

(1). 13.63 km dike (9.28km for Total the Xiangjiang River and 4.355km construction for the Qishui River). (2).10 period: 48 Qiyang 10 culverts and gates and 3 drainage months (44 132830 32378.4 City stations (880KW). (3).13.635km months for surface hardening of flood control main dike. project)

(1).8.06 km flood control dike. Total Ningyuan (2).4 culverts and gates. (3). construction 11 56530 9858.1 County Improvement of 4 flood discharge period: 34 channels. months

(1).5.83 km dike (including 2.14 km natural slope cutting). Total (2).11.19km flood control wall. Chenzhou construction 12 (3).15 culverts and gates. (4). 15 177850 44889.2 City period: 24 flood discharge channels with months total length of 2960m. (5). River dredging.

8 (1).33.057 km dike consolidation (13.638km in Qingxiangtian Zone, 11.645km in Heming Zone and 7.774 km in Qujian Zone). (2).6.723 km anti-leakage treatment within the dike (3km in

Qingxiangtian Zone, 1 km in

Heming Zone and 2.723 km in

Qujian Zone). (3). Renovation of

7 culverts and gates (4 in

Qingxiangtian Zone, 1 in Heming

Zone and 2 in Qujian Zone). 13 Total (4).6.678km slope protection construction (4.878 km in Qingxiangtian Zone, period: 48 1.8 km in Heming Zone). (5).5.47 months (47 km dike grouting (3.5 km in Zhuzhou months for Qingxiangtian Zone, 0.97 km in 377900 116692.1 City main Heming Zone and 1 km in Qujian project) Zone). (6). There are 30 drainage stations with 53 pumps (6218KW), of which 10 drainage stations with 28 pumps (5150KW) are available, and 39 new pumps (12863KW) will be installed.

3.3906 km masonry wall, 3.6818 km dike consolidation, 5.1953 Total flood control dike, 5 culverts and construction gates, river clearing up, period: 58 Liling 14 construction of flood control road, months (56 104780 38524.3 City etc. waterlogging works including months for 4 drainage stations (535 KW), 2 main flood discharge channels (5.7588 project) km).

9 (1).3.43 km embankment. (2).5.963 km dike consolidation. (3). 3.96 km slope protection with concrete blocks. (4).8.318 km concrete road surface. (5).3.108 Total km anti-wave wall. (6).1.045 construction stone road. (7). 9.393 km turf period: 21 Zhuzhou 15 slope protection. (8). 2 new months (18 71960 18211.5 County culverts and 4 rebuilding culverts, months for 19 culvert extensions. (9).2 new main pumping stations (904KW) and project) enlargement of 3 pumping stations (210KW). (10).dredging of 2 flood discharging channels (3.1km). (1).1.2 km retaining wall. (2).3.28 km embankment protection. (3).A 1.3 km flood discharge channel & Total 6.817 km embankment. (4).5 new construction culverts and gates. (5).4 pumping period: 35 Youxian 16 stations (12 units and 1035 KW). months (24 90540 13689 County (6). Improvement of 2 flood months for discharge channels (4.5km). (7). main Diversion of Tanzhou River project) (0.9km). (8). 3 bridges and 2 canal culverts.

Total 1862112.7 452930.4

2.2 Resettlement Outline

According to the resettlement plan of the 16 non-core sub-projects including Lengshuijiang City, lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Jiangyong County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Chenzhou City, Zhuzhou City, Liling City, Zhuzhou County and Youxian County, 6285.84 Mu land will be occupied permanently, including 4637.86 Mu collective land (1609.52 paddy fields, 911.65 Mu dry land, 472.78 Mu vegetable land, 231.61 Mu fish ponds, 181.06 Mu rural house

10 land and 922.85 Mu unused land), 1546.78 Mu state-owned land (7.5 Mu for organization purpose, 412.45 Mu for housing, 755.62 Mu for other uses), and 4595.93 Mu land will be temporarily occupied (including 154.61 Mu paddy fields, 821.29 Mu dry land and 175.66 Mu forest land). 2675 households with 10217 persons will be resettled, and 349,509.31 m2 houses will be removed. The influence of the resettlement plan is shown in Table 2.2-1, 2.2-2, 2.2-3 and 2.24.

Table 2.2-1 List of permanently used land County/City Involved Permanent No Collective land State-owned land Sub-project Village/group land use 214.48 Mu, including 2.78 Mu paddy fields, 77.99 Mu dry 111.28 Mu, 2 street offices, land, 56.86 Mu commercial including 30.63 Mu Lengshuijiang 5 neighbor- 325.76 Mu vegetable land, 2.35 Mu pond, house land, 2.13 1 City hoods, 19 various land 15.35 Mu garden land, 3.73 Mu industrial land, groups Mu bush land, 5.21 Mu timber 78.52 Mu unused land, 10.84 Mu rural house land. land, 39.37 Mu unused land 224.1 Mu, including 111.3 Mu 2 towns 96.7 Mu, including paddy fields, 27.3 Mu dry Lianyuan (townships), 320.8 Mu 21.7 Mu house 2 land, 76.4 Mu commercial City 11 villages, various land land, 75 Mu unused vegetable land, 1.5 Mu pond, 30 groups land 7.6 Mu rural house land

136.6 Mu, including 72.3 Mu 226.7 Mu, 9 Villages paddy fields, 44.2 Mu dry including Shuangfeng (neighbor- 362.3 Mu 3 land, 15.7 Mu vegetable land, 24.8 Mu house County hoods), 24 various land 1.9 Mu pond, 1.5 Mu rural land, 201.9 Mu groups house land waste land

131.71 Mu, 642.2 Mu, including 100 Mu including 5.33 Mu paddy fields, 411.5 Mu dry 6 Towns commercial land, land, 3.9 Mu vegetable land, Shaoyang (street offices) 773.91 Mu 3.84 Mu house 4 31.3 Mu garden land, 21.6 Mu City 11 villages, various land land, 122.54 Mu pond, 3.7 Mu timber land, 21 groups land for other 14.3 Mu rural house land, 55.9 purposes Mu unused land

11 858.22 Mu, including 628.8 Mu paddy fields, 145.6 Mu 13 Mu, including 1 town, Shaodong 871.22 Mu dry land, 67.5 Mu commercial 8.32 Mu industrial 5 9 villages, County Various land vegetable land, 9 Mu garden land, 4.68 Mu 32 groups land, 2.42 Mu pond, 4.8 Mu house land forest land. 113.6 Mu, including 72.5 Mu 54.3 Mu, including 1 town, Longhui 169.1 Mu Paddy fields, 3.5 Mu dry land, 6 Mu industrial 6 7 villages, County Various land 37.6 Mu vegetable land, 1.2 land, 35 groups Mu economic forest land. 48.3 Mu house land 22.49 Mu, 30 Mu, including 5 villages Jiangyong 52.49 Mu Including 16.34 Mu paddy 7.5 Mu unit land, 7 (street offices) County Various land fields, 3 Mu dry land, 0.55 Mu 22.5 Mu unused 14 groups pond, 2.6 Mu rural house land land 98 Mu, 26 Mu, including 1 township, Xintian 124 Mu Including 51 Mu paddy fields, 19 Mu industrial 8 3 villages, County Various land 37 Mu vegetable land, 10 Mu land, 7 Mu urban 12 groups Rural house land house land

6 villages 79.86 Mu, 47.6 Mu, including (street offices) Including 34.3 Mu paddy 2.6 Mu enterprise Jianghua 127.46 Mu 9 In Tuojian fields, 17.06 Mu dry land, land, 6.4 Mu house County Various land Town, 17 17.3 Mu pond, 5.6 Mu waste land, 38.6 Mu land groups land, 5.6 Mu rural house land for other purposes

528 Mu, Including 177 Mu paddy 73.2 Mu, 1 Township fields, 64 Mu dry land, 95 Mu Including 4 Mu Qiyang (town, office), 601.2 Mu 10 commercial vegetable land, 12 house land, 69.2 County 10 villages, Various land Mu garden land, 117 Mu Mu land for other 48 groups pond, 40 Mu economic forest purposes land, 23 Mu rural house land

160.41 Mu, 81.49 Mu, 1 town including 95.5 Mu paddy Including 2.6 Mu Ningyuan (office), 241.9 Mu 11 fields, 29.5 Mu dry land, 0.9 urban house land, County 6 villages, Various land Mu pond, 26.4 Mu waste land, 78.89 Mu free and 18 groups 8.11 Mu rural house land unused land

409.9 Mu, 6 towns / 83.26 Mu, Including 15.63 Mu street offices, Including 6.2 Mu dry land, 4.1 industrial land, Chenzhou 15 villages Mu commercial vegetable 12 493.16 Mu 178.6 Mu urban City (neighbor- land, 3.2 Mu fish pond, 26.2 house land, 215.67 hoods), 32 Mu rural house land, 43.56 Mu urban free and groups Mu unused land unused land

12 3 districts 300.78 Mu, 114.6 Mu, 9 Township Including 121.4 Mu paddy Including 34.8 Mu (town, office), fields, 45.2 Mu dry land, 27.3 Zhuzhou house land, 4.7 Mu 13 16 villages 415.38 Mu Mu commercial vegetable City enterprise land, (neighbor- land, 57.7 Mu pond, 39.18 75.1 Mu land for hoods), 37 rural house land, 10 Mu other purposes groups unused land 635.3 Mu, Including 39.6 Mu farmland 53 Mu, 4 towns Liling 788.3 Mu (25.2 Mu paddy fields, 14.4 Including 33 Mu 14 (street offices) City various land Mu commercial vegetable house land, 20 Mu 13 villages land), 8.3 Mu garden land, enterprise land 687.4 Mu unused land 362.4 Mu, 1 town, Including 91 Mu paddy fields, Zhuzhou 373 Mu 15 6 villages, 12 Mu dry land, 14 Mu garden 10.6 Mu County Various land 10 groups land, 16.4 Mu house land, 131 Mu pond, 98 Mu forest land 179.16 Mu, 66.7 Mu, Including 10 Mu paddy fields, 2 towns, Including 12.1 Mu Youxian 245.86 Mu 14.6 Mu dry land, 37.02 Mu 16 5 villages, Urban house land, County Various land vegetable land, 5.19 Mu pond, 14 groups 54.6 Mu land for 15.73 Mu rural house land, other purposes 86,62 Mu unused land

Table 2.2-2

List of temporarily used land

Mean Sub-project Temporarily No Involved village Type of land use City/county used land period 18.78 dry land, 135.37 Lengshuijiang 2 street offices, 5 361.81 Mu 1 Mu bush forest land, 2 years City neighborhoods, 11 groups Various land 207.66 Mu waste land Lianyuan 1township (street office), 55 Mu 18.6 Mu dry land, 36.4 2 2 years City 2 villages, 4 groups Various land Mu waste land 25.95 Mu dry land, Shuangfeng 1 township (street office), 93 Mu 3 67.05 Mu bush forest 2 years County 2 villages Various land land Shaoyang 6 townships (street offices), 637.2 Mu 94.4 Mu dry land, 542.8 4 2 years City 11 villages Various land Mu bush forest land

13 111 Mu dry land, 177.6 Shaodong 444 Mu 5 1 town, 5 villages, 5 groups Mu bush forest land, 2 years County Various land 155.4 Mu waste land 11.4 Mu dry land, 18.1 Longhui 1 township (town), 44.3 Mu 6 Mu bush forest land, 2 years County 5 villages Various land 14.8 Mu timber land 94.9 Mu paddy fields, 167 Mu dry land, 50.78 Jiangyong 422.78 Mu 7 1 town, 3 villages, 3 groups Mu economic forest 2 years County Various land land, 110.1 Mu bush forest land Xintian 1 township (town), 57.45 Mu 6.96 Mu dry land, 50.49 8 2 years County 2 villages Various land Mu bush forest land 81.7 Mu dry land, 9.9 Jianghua 178.2 Mu 9 1 town, 2 villages, 2 groups Mu bush forest land, 2 years County Various land 86.6 Mu waste land 130.9 Mu dry land, Qiyang 1 township (town), 312.41 Mu 10 181.51 Mu bush forest 2 years County 4 villages Various land land 46.52 Mu paddy fields, 52.5 Mu dry land, 41.64 Ningyuan 211.65 Mu 11 1 town, 2 villages Mu timber land, 25.5 Mu 2 years County Various land bush forest land, 45.5 Mu waste land 33.9 Mu dry land, 27.2 Chenzhou 3 townships (street offices), 427.05 Mu 12 Mu forest land, 365.95 2 years City 5 villages, 9 groups Various land other land 13.2 Mu paddy fields, Zhuzhou 2 districts, 4 street offices, 859.49 Mu 47.41 dry land, 116.24 13 2 years City 4 villages Various land Mu bush forest land, 682.64 Mu waste land 4 townships (towns, street 27.6 Mu dry land, 45.2 Liling 120 Mu 14 offices), Mu bush forest land, 2 years City Various land 5 villages 47.2 Mu waste land 1 township (town, street 11.26 Mu dry land, 21.36 Zhuzhou 103 Mu 15 office), Mu bush forest land, 2 years County Various land 4 villages 70.68 Mu waste land Youxian 268.59 Mu 92.93 Mu dry land, 16 1 town, 1 village 2 years County Various land 175.66 Mu forest land

14 Table 2.2-3 List of affected population

Individual Land Resettled Land industrial Needing Needing Affected Sub-Project Total occupied but land occupied Affected Removed Affected and job house Vulnerabl County/City Population but not not & units units minority commercial arranging building e groups resettled occupied resettled households House- 483 323 113 47 13 160 11 Lengshui- holds jiang Persons 1738 1142 459 137 871 231 596 24

House- 308 184 124 124 10 Lianyuan holds City Persons 983 592 391 396 391 37

House- Shuang- 189 50 139 139 5 holds feng Persons County 699 238 461 183 461 11

House- 571 420 151 35 116 Shaoyang holds City Persons 2594 2065 529 120 455 409 9

House- 411 385 26 4 26 11 Shaodong holds County Persons 1225 992 164 69 945 164 33

House- 234 119 105 10 4 105 Longhui hold County Persons 1134 482 318 348 318 59 16

Jiangyong House- 83 57 21 5 5 26

15 Individual Land Resettled Land industrial Needing Needing Affected Sub-Project Total occupied but land occupied Affected Removed Affected and job house Vulnerabl County/City Population but not not & units units minority commercial arranging building e groups resettled occupied resettled households holds County Persons 435 228 64 16 127 32 80 13 86

House- 694 624 58 12 70 Xintian holds County Persons 2932 2647 236 49 83 285 80

House- 119 18 95 6 3 100 Jianghua holds County Persons 722 77 451 28 166 34 475 26 390

House- 1377 1140 22 215 1 217 Qiyang holds County Persons 5689 4299 130 1249 518 1380 19

House- 123 28 23 72 95 Ningyuan holds County Persons 563 157 100 306 266 406 11

House- 502 68 431 3 21 415 11 Chenzhou holds City Persons 3418 216 3193 9 1892 59 1235 135

House- 395 149 155 91 5 1 15 246 Zhuzhou holds City Persons 1788 644 653 387 944 48 414 1040 67

16 Individual Land Resettled Land industrial Needing Needing Affected Sub-Project Total occupied but land occupied Affected Removed Affected and job house Vulnerabl County/City Population but not not & units units minority commercial arranging building e groups resettled occupied resettled households House- 595 51 544 2 1 544 22 Liling holds City Persons 2481 202 1994 285 76 1994 84

House- 104 58 41 5 46 Zhuzhou holds County Persons 505 248 233 24 126 257 10

House- 329 159 138 32 170 Youxian holds County Persons 1223 576 525 122 122 647 95

House- 6517 3833 2186 625 64 6 50 2599 70 holds Total Persons 28129 14805 9901 2327 4354 168 4288 10138 713 492

17 Table 2.2-4 List of removed house area

Including Tota Including Sub- Total resettled l removed Urban Rural Non- project Urban Rural population house house house house County population population area area area area /city House house House person person person m2 m2 m2 m2 -hold -hold -hold Lengshuij iang 160 596 113 411 47 185 29283.64 19966.83 6920.89 2395.92 City Lianyuan 124 391 80 251 44 140 11202 7314.52 3887.48 City Shuangfeng 139 461 134 445 5 16 16014.1 15344.1 670 County Shaoyang 116 409 26 98 90 311 22810.1 3869.5 12876.5 6064.4 City Shaodong 26 164 26 164 13666.0 9151 4515 County Longhui 105 318 105 318 15785.76 10306.46 5479.3 County Jiangyong 26 80 26 80 7278 2276 5002 County Xintian 70 285 37 148 33 137 11400 4094 7306 County Jianghua 101 479 83 379 18 100 15193.01 9747.35 3694.16 1751.5 County Qiyang 273 1380 20 117 217 1263 17997 2375 15422 200 County Ningyuan 95 406 23 100 72 306 7150 1737 5413 County Chenzhou 434 1310 381 1142 53 168 55990 37514 5194 13282 City Zhuzhou 246 1040 113 468 133 572 53978.8 19393.8 25805 8780 City Liling 544 1994 544 1994 46776 43647 3129 City Zhuzhou 46 257 18 110 28 147 12188 4845 7343 County Youxian 170 647 90 327 80 320 12796.6 5506.6 7290 County 1021 2675 1793 6472 846 3745 349509.31 194812.16 104098.03 50599.12 Total 7

18 3. Establishment and operation of resettlement organizations

3.1 Organization Arrangement

3.1.1 Project management organization

According to 3 sub-projects which have signed the external resettlement monitoring and assessment contracts, both local governments and owners have attached great importance to the arrangement of resettlement and have established project management organizations and arranged corresponding staffs in order to carry out the resettlement smoothly.

(1). Jiangyong County

According to the notice of Yongban (2006) 9 issued by the Office of Jiangyong County Party Committee, the Leading Group of Jiangyong County Urban Construction and the Leading Group of Urban Flood Control Dike Project Headquarters have been established to be in charge of the lead and coordination of the Project, and the Headquarters is responsible for specific management and implementation of the Project.

(2). Chenzhou City

On Nov. 7, 2006, according to the notice of Chenzhengbanhan (2006) 159 issued by Chenzhou City Government, the Tongxin River Harness Headquarters was established by the City Government to be responsible for the management and coordination of the Project.

(3). Other Counties (cities)

19 Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

3.1.2 Project Resettlement Organization

Resettlement organizations have been established under the project management organizations in the Jiangyong County and Chenzhou City, and staffs of the resettlement organizations are arranged from the government and the departments of land, water resources, agriculture, etc., who are experienced in grass-roots work and will be in charge of the resettlement coordination and implementation. Major chiefs have taken part in professional training held be the Provincial Project Office.

Resettlement group with 5 staffs has been established under the Urban Flood Control Dike Project Headquarters of Jiangyong County.

Resettlement department with 5 staffs has been established under the Tongxin River Harness Headquarters of Chenzhou City.

1-2 leaders in every affected townships (towns) and villages have been assigned to be responsible for their resettlement work.

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

20 As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

3.2 Organization Operation

3.2.1 Jiangyong County

(1). Check and determination of physical resettlement indexes

Check of the houses before pulling down in Jiangyong County

Five parties including the resettlement group of the Project Headquarters, the County Land Bureau, the County Planning Bureau, village representative and the resettled household jointly check and determine the physical resettlement indexes.

(2). Signing of the land acquisition and resettlement agreement

21 After determining the physical indexes, the Owner directly negotiated with the village committee and resettled households about land acquisition and resettlement compensation, the Owner and local village committees signed the trust agreements of collective land acquisition and the agreements of land compensation arrangement, the Owner and the resettled households signed the resettlement compensation agreements, and all above agreements were required to be reported to the County Land Bureau.

(3). Resettlement implementation

After signing of the trust agreement and arrival of the resettlement compensation fund, the village committees are responsible for the management and implementation of the land acquisition.

(4). Allocation and checking-out of the compensation costs

The land acquisition fund is checked out between the Owner and the village committees directly. The village committees hold villagers meeting to decide allocation scheme. According to the resettlement arrangement plan and the requirements of the Document (2005) 53 issued by the provincial government, 75% of the land acquisition compensation and 100% resettlement arrangement fund must by paid to the resettled farmers. And the part of the resettlement fund obtained by the village collective should be used for social security and production development and is not allowed for other purposes. Compensations including house removal, private compensation, sporadic fruit trees, etc., were checked out between the Owner and the resettled households directly and the compensation agreements were signed.

22 3.2.2 Chenzhou City

(1). Check and determination of physical resettlement indexes

Organized by the Project Headquarters, the Owner, the water resources bureau, the land bureau, the townships (town ) and the villages jointly checked the physical indexes including land acquisition and resettlement and the results were publicized in the villages and groups.

(2). Signing of the land acquisition and resettlement agreement

After determining the physical indexes, the Owner’s representative directly negotiated with the village committee and resettled households about land acquisition and resettlement compensation, the Owner’s representative and local village committees signed the trust agreements of collective land acquisition and the agreements of land compensation arrangement, the Owner’s representative and the resettled households signed the resettlement compensation agreements.

(3). Resettlement implementation

After signing of the trust agreement and arrival of the resettlement compensation fund, the village committees are responsible for the management and implementation of the land acquisition. With regard to enterprise and institutions, the Owner signs removal agreements with the units and they are responsible for the removals.

(4). Fund settlement

The Owner and the village committees make open fund settlement for land acquisition and removal belonging to the collective and the village committees hold farmers’ meeting to decide the allocation scheme of the

23 compensation fund. The Owner and the resettled households make direct settlement for compensations such as houses which belong to the private property and the resettled households need to sign the resettlement compensation agreements.

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

4. Project Implementation Progress

Constrained by various factors, the implementation progresses of the Jiangyong and Chenzhou Sub-projects are behind the planned schedule at the moment.

4.1 Jiangyong County

The Urban Flood Control Sub-project of Jiangyong County is divided into Chengnan and Chengbei zones, including 4 new dikes (6.67 km, 4.48 km embankment and 2.19km flood control wall), 4 culverts and gates, and consolidation of 4 flood discharge channels. The total construction period is 24 months, while the construction of the main works will be 20 months. The Sub-project has been started in October of 2007. The progress of the Sub-project is shown in Table 4.1.

24 Table 4.1

Implementation Progress of the Jiangyong County Sub-project

Cost Finished Consulting Starting Finished No Name Contractor ⅹ103 company date ⅹ103 proportion

Yongzhou Hunan Hydro & Chengbei 1 9189,3 Kehong Power Oct.,2007 5302 57.7% Zone Company Consulting Company Yongzhou Chengnan Hunan Hydro & and 1 9383.8 Kehong Power Oct.,2007 8211 87.5% Chengdong Company Consulting Zone Company 4.2 Chenzhou City

The Urban Flood Control Sub-project of Chenzhou City is divided into two protection zones, including the Central City Zone and the Xiameiqiao Zone, with total dike length of 23.597 km and 6.57 km already finished. The Sub-project includes following items:

(1). 5.53 km new embankment (including 2.14 km natural slope-cutting and masonry protection).

(2). 11.19 km new masonry flood control wall.

(3). 15 new culverts and gates.

(4). 15 new flood discharge channels with total length of 2.96 km.

(5). River dredging and clearing.

The total construction period of the Sub-project is 24 months. Beginning from Aug. of the first year, the Sub-project will be completed in Jul. of

25 the third year. According to arrangement, the Tongxinhe 1st Stage Project of the Central City Zone (from the Tongxinqiao to Chengjiang River mouth) will be implemented firstly and it was started on Dec. 4, 2007 and the progress is shown in Table 4.2.

Table 4.2

Implementation Progress of the Chenzhou City Sub-project

Cost Finished Consulting Starting Finished No Name Contractor ⅹ103 company date ⅹ103 proportion

Tongxinhe Hunan 1 Xiameiqiao 32488.9 Kehong HWECC Dec.4,2007 9300 29% Project Company 5. Resettlement Implementation Progress

5.1 Resettlement Implementation Schedule

5.1.1 Jiangyong County

According to the Resettlement Plan of the Urban Flood Control Project of the Jiangyong County approved by the Chinese Government and agreed by the Asian Bank, the targets of the resettlement schedule are as followings: the resettlement preparation started in Mar. of 2006 and ended in Jun. of 2007, the resettlement agreements signed beginning from Sept. of 2007, the resettlement restoration begun from Sept. of 2007 and ended by the end of Dec. of 2008, the resettlement acceptance carried out in Mar. of 2009 and post-assessment started in Apr. of 2009. At the moment, except removal of some miscellaneous houses and auxiliary facilities, the houses of 26 households have not been removed and the actual progress is shown in 5.3.1, 5.4.1 and 5.5.1.

26 5.1.2 Chenzhou City

According to the Resettlement Plan of the Urban Flood Control Project of the Chenzhou City approved by the Chinese Government and agreed by the Asian Bank, the targets of the resettlement schedule are as followings: the resettlement preparation started in Mar. of 2006 and ended in Jun. of 2007, the resettlement agreements signed beginning from Sept. of 2007, the resettlement restoration begun from Sept. of 2007 and ended by the end of Oct. of 2008, the infrastructure restoration started from Sept. of 2007 and ended by the end of Feb. of 2008, the resettlement acceptance carried out in Mar. of 2009 and post-assessment started in Apr. of 2009. At the moment, except removal of some miscellaneous houses and auxiliary facilities, the houses of the resettled households have not been started, the Chenzhou Tiancheng Chemical Company has finished removal work. The actual progress is given in Table 5.3.2, Table 5.4.2 and Table 5.5.2.

Various factors, such as resettlement funding difficulty in local cities (districts), higher demanding of the resettled people than the standards listed in the resettlement plan, complex approval procedures, etc., have increased the difficulty and time to sign the compensation agreements, causing later starting of the project implementation and making the real progress be behind the planned schedule. It is recommended to adjust the implementation schedule based on the real progress of the Project.

5.1.3. Other Counties (Cities)

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

27 As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

5.2 Resettlement Policy and Compensation Standards

5.2.1 Jiangyong County

The land acquisition and resettlement policy and standards of the Urban Flood Control Project of the Jiangyong County are in accordance with the Resettlement Arrangement Plan of the Jiangyong County. However, during implementation, the local people require to raise compensation standards, otherwise no agreements can be achieved. The actual compensation standards are much higher than those in the Resettlement Plan (see below Table 5.2.1-1 and Table 5.2.1-2).

Table 5.2.1-1

Comparison of permanent land compensation

Unit: ⅹ104RMB/Mu Planning Real Land owner Land type Notes compensation compensation Paddy fields 21254 43600 30000 for preserved land Dry land 14645 33600 20000 for preserved land collective Pond 20736 43600 30000 for preserved land Vegetable land 0 0 Rural house land 18318 Unit’s land 41354 State-owned Free of Other land charge

28

Table 5.2.1-2

Comparison of house removal compensation

Planned Change Real House type structure unit compensation scope Compensation Brick & RMB/m2 318 280-340 concrete Rural Brick & wood RMB/m2 244 210-270 house Soil & wood RMB/m2 miscellaneous RMB/m2 60 100 Brick & Office RMB/m2 376 345-405 concrete

Warehouse,plant Brick & wood RMB/m2 288 260-310

miscellaneous RMB/m2 60

5.2.2 Chenzhou City

The land acquisition and resettlement policy and standards of the Urban Flood Control Project of the Chenzhou City are in accordance with the Resettlement Arrangement Plan of the Chenzhou City. However, during implementation, the local people require to raise compensation standards, otherwise no agreements can be achieved. The actual compensation standards are much higher than those in the Resettlement Plan (see below Table 5.2.2-1 and Table 5.2.2-2).

29

Table 5.2.1-1

Comparison of permanent land compensation

Unit: ⅹ104RMB/Mu Compensation Real compensation Land owner Land type standards standards

Paddy fields 26400

Dry land 18150

Commercial vegetable land 58725 88000 collective Fish pond 36000

Rural house land 22600

Unused land 3200

Industrial land 117450

State-owned Residential land 60030 Other land Free of charge

Table 5.2.2-2 Comparison of house removal compensation

Planned Change Real House type Structure Unit Notes standards scope standards

Frame 2 RMB/m 650 Structure

Brick & 2 Urban RMB/m 540 495-585 concrete house 2 Brick & wood RMB/m 435 400-470

Miscellaneous 2 RMB/m 120 100-150 house

Rural Brick & 2 RMB/m 380 342-418 house concrete

30 Brick & 2 RMB/m 290 261-319 wood

Miscellaneous 2 RMB/m 90 100-150 house

5.2.3 Other Counties (Cities)

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

5.3 Progress of Land Acquisition

5.3.1 Jiangyong County

(1). Progress of land acquisition

For details please see Table 5.3.1-1 and Table 5.3.1-2.

Table 5.3.1-1 Comparison of Land acquisition in Jiangyong County Unit: Mu

Proportion of real Planned land acquisition Real land acquisition finished land acquisition Item State- State- State- Total collective Total collective Total collective owned owned owned Amount 52.49 22.49 30 45.51 15.51 30 86% 68.9% 100%

31 Notes

Table 5.3.1-2 Land Acquisition implementation in Jiangyong County

Fund Fund Signed date needed to already Village Group Used land Land type of land pay paid acquisition ⅹ103 ⅹ103

Chengjiajie 1-5 7.11 Collective 10/08/2007 287.2 287.2 Village Hejia Village 1,3,6 6.7 Collective 10/08/2007 270.5 270.5 Sanyuangong 2,3,4,5 1.8 Collective 10/08/2007 72.6 72.6 Village

Unit land 30 State-owned 10/08/2007 1240.6 1240.6

Total 10/08/2007 1870.9 1870.9

(2). Progress of land acquisition approval procedures

The land acquisition scheme of Jiangyong County flood control sub-project has been approved by the Provincial Land Resources Department and both farm land occupation tax and farm land reclamation fee have been paid in Jan. of 2008.

(2). Signing of the land acquisition agreements

The Project Headquarters has signed land acquisition agreements with affected villages including Chenjiajie Village, Hejia Village, Sanyuangong Village in Xiaopu Town, and all land acquisition funds have been paid to all villages and groups and have been allocated to

32 persons based on the allocation method decided by discussion among the villages, groups and villagers.

5.3.2 Chenzhou City

(1). Progress of land acquisition

For details please see Table 5.3.2-1 and Table 5.3.2-2.

Table 5.3.1-1 Comparison of Land acquisition in Chenzhou City Unit: Mu

Proportion of real Planned land acquisition Real land acquisition finished land acquisition Item State- State- State- Total collective Total collective Total collective owned owned owned Amount 493.16 83.26 409.9 25.03 25.03 0 5.0% 30% 0 Notes

Table 5.3.1-2 Land Acquisition implementation in Jiangyong County

Fund Fund Signed needed already Used l Land date of Town Village Group to pay paid Notes and type land acquisition ⅹ103 ⅹ103

Including land compensation, Chen- Yuchang arrangement Jiang 4 25.03 Collective 11/032008 2202,6 2202,6 Village compensation, Town young crops compensation Yuchang Auxiliary 4 Collective 450.6 270.5 Village facilities

Total 2653.2 2653.2

33

Notes: According to the Report (No.2007-11-26) made by the Land Surveying Team on Nov. 20, 2007, the total area is 16688.7 m2, including 7471.8 m2 (11.20 Mu) vegetable land, other urban residential land 59 m2, 1212.4 m2grass land, 1825.6 m2 industrial land, 6038.1 m2 (9.05 Mu) fish pond and 81.8 m2 road, but the villagers strongly ask to compensate all land according to the standards of vegetable land, otherwise they refuse to sign the compensation agreement.

(2). Land acquisition

① Progress of land acquisition approval procedures

The land acquisition of the sub-project has been pre-reviewed by the Chenzhou City Land Resources Bureau (pre-review No. (2005) 53 and (2008) 8) in Aug. of 2005 and Apr. of 2008 respectively.

②Signing of the land acquisition agreements

The Project Headquarters has signed 25.03 Mu land acquisition compensation agreement with Group 4, Yuchang Village, Chenjiang Town, all land acquisition funds have been paid to the Village but the internal allocation method within the Village has not been worked out.

5.3.3 Other Counties (Cities)

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

34 5.4 Progress of Resettlement Arrangement

5.4.1 Jiangyong County

(1). Progress of Resettlement

Please see Table 5.1-1 and Table 5.4.1-2.

Table 5.4.1-1

Comparison of Resettlement in Jiangyong County

Item Unit Amount Notes Residential house Planned removed house m2 7278 2276m2,non-residential Planned house 5082 m2 Planned resettled household household 26 Planned resettled population person 80 All belonging to Finished house removal m2 437.89 auxiliary houses Finished All belonging to Finished resettled household household 0 auxiliary houses Finished resettled population person 0 Finished house removal % 6 Proportion Finished resettled household % 0 Finished resettled population % 0

35 Table 5.4.1-2 List of Resettlement in Jiangyong County

Compen Compen Removed New -sation -sation Date Arrange- Village Group Name old house house need to already Of signing notes ment area area pay paid Agreem. (RMB) (RMB) Jiang Children Jianfeng Jiang No need Play Oct.31, Pu Shu- Jian- 6000 6000 for ground 2006 Ping feng arrang. Pu Hai- hang Quan Auxiliary No need Nov.17, Qi- house 2000 2000 for 2006 sheng 20m2 arrang. Auxiliary No need Zhu house 8864 8864 Jan.8, 2008 for Tanhao 88.64m2 arrang. Masonry Zhu foundatio 13500 13500 Tanhao n Auxiliary Xiao- 30150 30150 house Jiang No.7 1 iron Village shed, He Mar.10, 2 Septic Qiu- 4320 4320 2008 tanks, sheng 11 fruit tress Giving Jiang- Auxiliary 15 yong Oct.24, house 105 auxiliary Foods 2006 281.25m2 houses Company 105m2 Market Shop Apr. 16, Manag. Front 18100 18100 2008 Center 27m2 Auxiliary People’s Apr. 16, house 4800 4800 Hospital 2008 48m2 Total 87734 87734

36 (2). Progress of resettled people

Please see Table 5.4.1-3.

Table 5.4.1-3

Comparison of resettled people in Jiangyong County

Town Item Unit amount Notes Total resettled household 26 Resettlement Xiaopu Town people person 80 arrangement Hejia Village, household 26 plan Move-back Sanyuangong arrangement person 80 Village No need for arrangement, only Finished None removing auxiliary houses

5.4.2 Chenzhou City

(1). Progress of resettlement

Please see Table 5.4.2-1 and Table 5.4.2-2.

37 Table 5.4.2-1

Comparison of Resettlement in Chenzhou City

Item Unit Amount Notes Residential house 2 2 Planned removed house m 55990 42708m ,non-residential house 13282 m2 Planned Planned resettled household household 434

Planned resettled population person 1310

2 Finished house removal m 1589.60

Finished Finished resettled household household 0

Finished resettled population person 0 Finished house removal % 2.84% Proportion Finished resettled household % 0 Finished resettled population % 0

38 Table 5.4.2-2

List of Resettle ment in Chenzhou City

Compen- Compen- Removed sation sation Date Town Name house need to already Of signing Notes area pay paid Agreement (RMB) (RMB) Li Dingqiu 81.70 16340 16340 02/07/2008 Deng 04/07/2008 36.60 5800 5800 Wenli Zhang 02/07/2008 14.0 2100 2100 Baosheng Yong 02/07/2008 Simple shed 68 12840 12840 Guolin 44m2 Li Xiaobo 08/07/2008 Compensation Including 153.41m2 pig 18.26 32964 32964 house, 201m2 Pond, 1 well, resettling cost 200RMB Tiancheng Non 16/01/2008 Including Chemical Residential workshop, 1371 298000 29800 Company house gate, oil tank, W.C.,etc Tiancheng 16/07/2008 Market sheds 2 Chemical (78m ) 24000 24000 and auxiliary Company facilities Zhou 03/07/2008 walls 5713 5713 Xiaobing Not including Vegetable 1589.6 397757 397757 market sheds 78m2

(2). Progress of resettled people

Please see Table 5.4.2-3.

39 Table 5.4.2.3

Comparison of resettled people in Jiangyong County

Town Item Unit Amount Notes household 415 Including 300 households, Beihu Total 898 persons in Beihu , resettled District, 115 households, Suxian person 1235 people 337 persons in District Resettlement household 89 Including 44 households arrangement Monetary in Beihu District, 193 plan compensate person 268 persons in Suxian District Property household 277 Including 187 households Right in Beihu District, 552 person 814 exchange persons in Suxian District Move-back household 49 All belonging to Chenjiang arrangement person 153 Town, Beihu District 3 households have Real finish None removed only auxiliary houses

5.4.3 Other Counties (cities)

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

5.5 Removal Progress of Enterprises and Institutions

40 5.5.1 Jiangyong County

(1). Removal Plan of Enterprises and institutions

According to the resettlement plan, 5 enterprises and institutions, including the County People’s Hospital, the County Planning & Construction Bureau, the County Timber Company, the County Aquatic & Meat company and the County Town Market need to remove part of their offices or auxiliary houses. As the above 5 enterprises and institutions occupy a large area, they have enough space to build new houses, monetary compensation will be used to for them.

(2). Finished removal work of Enterprises and institutions

According to the information provided by the Owner and surveyed by the monitoring personnel, the Owner has signed monetary compensation agreement with affected enterprises and institutions.

Monitoring personnel talking with Jiangyong County People’s Hospital

5.5.2 Chenzhou City

41 (1). Removal Plan of Enterprises and institutions

According to the resettlement plan, there area 21 affected enterprises and institutions within the project zone, including11enterprises, i.e., 6 in the Beihu District (Chenzhou Fertilizer Plant, Chenzhou Paper Factory, Chenzhou Petroleum company, Chenzhou Tongyong Machinery Works, Chenzhou Textile mill, Pesticide Factory), 5 in Suxian District (Anti-explosive Motor factory, Suxian Vehicle Repair Factory, Shimei Printing Factory, 2nd Paper Factory, Soft Drink Factory), 10 institutions, i.e., 9 in the Beihu District (the City House Management Bureau, the City Aquatic & Meat company, the City Hydro & Power Construction Company, the Commercial Bureau of Beihu District, the City Industrial and Commercial Bureau, Township Enterprise Bureau, 2nd National Tax Bureau, Beihu Water Resources Burea, the Chenzhou Industrial School, the City Museum of Art, the Chenzhou Normal College, the City No.3 Middle School, the Children’s Teacher School), and 1 in the Suxian District (the Suxian House Bureau). As all affected houses belong to management houses or auxiliary houses, the construction of the Project has limited influence on above enterprises and institutions , monetary compensation are used to arrange all 21 enterprises and institutions.

(2). Finished removal of the enterprises and institutions

According to the information provided by the Owner, the house removal agreement has been signed between the Owner and the Chenzhou Tiancheng Chemical Company (Chenzhou Fertilizer Factory) on Jan. 16, 2008 and the removal of houses and auxiliary facilities has been completed.

42

Part of non-residential houses of the Chenzhou Tiancheng Chemical Company removed

5.5.3 Other Counties (Cities)

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

5.6 Progress of Resettlement Area Construction

5.6.1 Jiangyong County

(1). Resettlement Area Plan

43 According to the resettlement plan, 26 households and 80 persons (all belonging to rural residents) in the Hejia Village and Sanyuangong Village, Xiaopu Town (17 households and 48 persons in the Hejia Village, 9 households and 32 persons in the Sanyuangong Village) need to be resettled within their own groups and villages. 4 move-back resettlement places in the 2 villages are arranged and the house land with 120 m2 per household (in total 4.68 Mu) belongs to dry land.

(2). Resettlement Progress

The Headquarters is now widely seeking the views of the resettlement households to determine the specific arrangement places.

5.6.2 Chenzhou City

(1). Resettlement Area Plan

According to the resettlement arrangement plan, 8 villages in 4 townships (towns, offices) will be affected and 1235 persons in 415 households are required to be resettled (including 1082 urban residents in 366 households and 153 rural residents in 49 households).

According to the requirements of the general planning of the Chenzhou City, the removal of the urban residential houses does not arrange re-construction land and monetary compensation plus house property exchange will be used for the affected urban residents, including 268 persons in 89 households by monetary compensation and 814 persons in 277 households by house property exchange.

44 Regarding rural residents, 153 persons in 49 households in the Tongxinqiao Village and Yuchang Village are needed to resettle and it is temporarily determined to use move-back arrangement within their own groups and villages, and the house land will be allocated by the village/group with standard of 120 m2/household and the houses will be built by themselves.

(2). Resettlement Progress

The Owner is discussing with the resettlement villages, groups and households regarding the move-back arrangement area. Monetary compensation and house property exchange are used for the urban residents. At the moment 130 households have signed the resettlement land agreements.

Planned resettlement place in Chenzhou City

5.6.3 Other Counties (Cities)

45 Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

5.7 Arrival and Payment of the Resettlement Fund

5.7.1 Jiangyong County

For details please see Table 5.7.1.

5.7.2 Chenzhou City

For details please see Table 5.7.2.

5.7.3 Other Counties (cities)

Liling City has signed the external monitoring and assessment contract, but the Project has not started yet.

As the external monitoring and assessment contracts in Lengshuijiang City, Lianyuan City, Shuangfeng County, Shaoyang City, Shaodong County, Longhui County, Xintian County, Jianghua County, Qiyang County, Ningyuan County, Zhuzhou City, Zhuzhou County and Youxian County have not been signed, monitoring and assessment work have not been carried out.

46 Table 5.7.1

Arrival and Payment of the resettlement fund in Jiangyong County Unit:10,000RMB Item Planned Arrival and payment Notes Item Sub-item investment arrival paid ratio 1.Resettlment 503.85 208.3734 208.7734 41.4 compensation 1).Land 251.93 187.09 187.09 74 compensation Including 2).House and 45.06 for auxiliary facilities 219.87 8.7734 8.7734 4 auxiliary compensation facilities of the fishing 3).Infrastructure 12.00 compensation 4).Relocation Transportation 2.80 costs 5).Sporadic fruit tree 0.02 compensation 6).Compensation for enterprises 12.51 12.51 12.51 100 & institutions 7).Compensation for self- 0 employed 8).Compensation 4.72 For weak mass 2.Compensation for special 19.90 facilities 1).Compensation For traffic 6.00 facilities 2).Compensation 7.43 For substation

3).Compensation for posts 3.11 facilities

47 4).Compensation for broadcast 3.36 and TV 3.Othe costs 5.11 1).Survey & 15.71 15.71 15.71 100 design fee 2).Implementation 15.71 15.71 15.71 100 Management fee 3).Opening fee For 9.33 9.33 9.33 100 implementation organization 4).Technical 2.52 2.52 2.52 100 training costs 5).Monitoring & assessment 7.86 fee 4. Basic reserve 57.49 5.total investment (not 632.37 including tax) 6 taxes & fees 57.71 1).Land 5.16 occupation tax 2).Land 10.20 reclamation fee 3).Forest recovery 42.35 fee 7. Total investment 690.08 (including taxes & fees)

48 Table5.7.2

Arrival and Payment of the resettlement fund in Chenzhou

Unit:10000RMB

Item Planned Arrival and payment Notes Item Sub-item investment arrival paid ratio 1.Resettlment 3357.73 500 348.63 10.38 compensation 1).Land 291.20 230 220.264 75.64 compensation 2).House and Including auxiliary facilities 45.06 for compensation 2700.36 200 85.54 3.12 auxiliary facilities of the fishing 3).Infrastructure 222.36 30 11.38 5.12 compensation 4).Relocation Transportation 74.10 costs 5).Sporadic fruit tree 0 compensation 6).Compensation for enterprises 39.85 40 32.3 81.05 & institutions 7).Compensation for self- 0 employed 8).Compensation 29.92 For weak mass 2.Compensation for special 318.70 facilities 1).Compensation For traffic 193.35 facilities 2).Compensation 10.60 For substation 3).Compensation for posts 6.00 facilities

49 4).Compensation for broadcast 4.55 and TV 5).Water 104.20 resources 3.Othe costs 387.52 29.45 7.6 1).Survey & 109.37 12.45 11.38 design fee 2).Implementation 109.37 15 13.72 Management fee 3).Opening fee For 95.00 implementation organization 4).Technical 16.79 training costs 5).Monitoring & assessment 55.15 2 3.6 fee 4. Basic reserve 406.40 5.total investment (not 4470.35 including tax) 6 taxes & fees 18.57 1).Land 6.93 occupation tax 2).Land 6.20 reclamation fee 3).Forest recovery 5.44 fee 7. Total investment 4488.92 (including taxes & fees)

50 6. Psychology and Complaint of the Resettled People

The resettled people enjoy the rights and obligations specified in ’s Constitution and it is specified that the legitimate rights of the resettled people shall not be violated. The Clause 15 in the Regulation of Land Compensation and Resettlement Arrangement for Large and Medium-sized Water Resources Projects specifies that “the State safeguards the legitimate rights of the resettled people”. If the resettled people consider that their legitimate rights are violated, they have the rights to complain until getting their rights.

6.1 Complaint Channel

There are various complaint channels for the resettled people, including delivering complaint to resettlement institutions at various levels, petition, discipline inspection, audit departments of various governments, as well as monitoring, justice and court, media, and the external monitoring institutions.

6.2 Complaint Procedures

The resettled people can deliver their complaint following the procedure of from low level to high level. Firstly they can contact their village committee, and the village committee or the resettled people then contact their township (town) government to coordinate and solve. They can also report to the upper resettlement institution and the upper institution should jointly study the complaint with the lower resettlement institution. if the complaint can not be suitably solved, they can report to another higher level or to the courts.

6.3 Psychology and Complaint of the Resettled People

51 According to the information provided by the resettlement institutions and site visit of the monitoring personnel, most resettled people support the construction of the flood control project and they believe the project will raise the flood standards, change the look of the city and safeguard people’s lives and properties. Residents living in the low area along the river feel most urgent to implement the project, and they express that they agree with the compensation standards. However, some resettled people are concerned that the compensation is not enough to buy new houses and they worry their future livelihood as their farmland occupied, minor resettled people’s demands are too high.

7. Public Participation, Consultation and Information Publicizing

Since the flood control projects are key projects in local cities (counties), local medias including TV, news papers have made widespread broadcasting and the make the public know the outline and progress of the Project.

Before implementation of the removal and resettlement, the resettlement institutions of all sub-projects have held various meetings to listen to the opinions of the resettled people, to implement the resettlement arrangement.

During the implementation, the resettlement personnel take the way of on-the-site meeting, to publicize items including land acquisition, house removal, compensation standards, etc., to the resettled people.

After checking of the physical indexes, they are publicized before signing the agreements to get the supervision of the mass and to make decision open, fair and just.

52 7.1 Jiangyong County

(1). The land acquisition investigation results and compensation standards have been publicized in affected villages.

(2). The resettlement personnel of the Headquarters have held various meetings in the affected villages to propagate the resettlement policy and ask for the views of the resettled people.

(3). Although the relevant contents in the resettlement manual have been propagated to the resettled people, the resettlement manual has not been released to the resettled people.

7.2 Chenzhou City

(1). The land acquisition investigation results and compensation standards have been publicized in affected villages.

(2). The resettlement personnel of the Headquarters have held various meetings in the affected villages to propagate the resettlement policy and ask for the views of the resettled people.

(3).The Headquarters has worked out the Compilation of the Propaganda Documents for House Removal of the Tongxinhe Project, which includes followings: 1).Briefing of the Project. 2).Management Regulation of the Urban House Removal issued by the State Council. 3).No.159 Order issued by the Hunan Provincial Government (Implementation of the Management Regulation of the Urban House Removal in Hunan Province). 4).Answers of legal questions in house removal. This material has released to the village heads and resettled people.

53 (4). Although the relevant contents in the resettlement manual have been propagated to the resettled people, the resettlement manual has not been released to the resettled people.

8. Existed Problems and Suggestions

(1). Harder work should be done as the real progress of the resettlement behind the planned schedule.

The resettlement progresses both in Jiangyong County and Chenzhou City are behind the planned schedule. The Jiangyong County planned to end all resettlement work by the end of Dec., 2008 and to make resettlement acceptance in Mar., 2009. The real situation is that except several households’ auxiliary house been moved, resettled households are checking the physical indexes, the removal agreements have not been signed and the new site for building houses still needs to discuss with the resettled households

The Chenzhou City planned to sign removal and resettlement agreements from Sept., 2007, to start restoration of the resettlement production and lives in Sept., 2007 and to end all works by the end of Oct., 2008, to restore the infrastructure from Sept., 2007 and finish by the end of Jan., 2008, to make resettlement acceptance in Mar. of 2009, and to make pose-assessment in Apr. of 2009. The real situation is as followings: The affected houses in the Chenzhou Tiancheng Chemical Company have been removed, the land acquisition agreements of 25 Mu collective land have been signed, the preparatory work of 11 Mu land used for resettlement and the negotiation of use of 70 Mu state-owned land have been completed, the removal of residents’ house have not been started except removal of several simple house and auxiliary facilities.

54 According to the monitoring information, the resettlements of both sub-projects are obviously behind the planned schedule. It is suggested that relevant units should attach great importance to the resettlement work and to take effective measures to speed up the implementation. The resettlement belongs to the work of the government, local governments should strengthen leadership of the resettlement and guarantee that the resettlement meets the progress of the Project construction.

(2). Implementing the physical indexes of the land acquisition and resettlement

Both sub-projects in Jiangyong County and Chenzhou City have been started construction formally, land acquisition and check of physical removal indexes are carrying out now, it is suggested to accelerate the work and to provide various physical data based on households, groups and villages to HWECC, so as to make foundation investigations and tracking surveys in accordance with the resettlement plan approved by the Asian Bank.

(3). Strengthening propaganda of the resettlement

Although a lot of propagandas have been carried out during physical resettlement index investigation and initial implementation, some resettled people still knew little about the resettlement policy and compensation standards, a few people have too high expectation to the compensation. To guarantee smooth implementation of the resettlement and the Project, first work should be make the resettled people know and to achieve public resettlement policy, public compensation standards, public physical indexes and public resettled population. At the moment the Resettlement Arrangement Information Manual approved by the

55 Asian Bank should be released to the resettled people as soon as possible, to get understanding and support of the resettled people.

(4). Improving file and information management

The resettlement covers a wide scope with complex contents and large information, and the statistic data change quickly. As the resettlement has just begun, because of lacking experience, the statistics, information and files of both sub-projects are behind the progress and it’s difficult for them to supply timely and systematic implementation information. Therefore, it is suggested that every sub-project improves file and information management, establishes file information management system, collects data and makes statistics timely, establishes databank, make good management of various physical figures, compensation agreements and compensation documents of the land acquisition and resettlement, and renews the data including implementation progress, payment of the compensation fund, etc., so as to achieve a more standardized and scientific implementation, management and decision-making of the Project.

(4). Adjusting the resettlement plan properly

Affected by tightening credit and fund difficulty, as well as long negotiation in resettlement compensation, the resettlement implementation progresses of both sub-project are behind the schedule of resettlement arrangement plan, the planned schedule has little meaning in controlling the progress. Another problem is a higher increase in land compensation in implementation. For instance, in Jiangyong County, the planned compensations for paddy fields and dry land are 21254 RMB/Mu and 14645 RMB/Mu, while the signed

56 compensations are 43600 RMB/Mu and 33600 RMB/Mu respectively. In Chenzhou City, the planned compensation for commercial vegetable land is 58725 RMB/Mu, while the real compensation is 88000 RMB/Mu. Because of the compensation increase, the resettlement costs will change significantly. Considering above factors and some other factors (such as change of some physical indexes), it is suggested to adjust the arrangement plan properly.

(5). It is suggested to report the land acquisition scheme of the Project in Chenzhou City to the Provincial Land Resources Department as early as possible.

(6).The collective land of Group 4, Yuchang Village, Chenjiang Town of Chenzhou City Sub-project (total area of 25.03 Mu) was measured by the Chenzhou National Land Surveying Team, it included 11.20 Mu vegetable land, but the villagers requested all land to be compensated in accordance with the vegetable land standard (880000 RMB per Mu), otherwise they refused to sign the agreement. Because of the urgency of starting the Project, the agreement was signed according to vegetable land compensation standard. Such incident should be taken as a lesson and should be avoided in future.

(7). According to the practice of HWECC for the Project, the signing of the external resettlement monitoring and assessment contracts is rather difficult and it is suggested that the Project Office should support and coordinate in order to make smooth implementation of the work.

57