High Speed Two Limited

High Speed 2

Infrastructure Maintenance Depot (IMD)

High Speed Two Limited

H igh Speed 2

Infrastructure Maintenance Depot (IMD)

March 2011

This r eport t akes i nto a ccount t he particular instructions and requirements of our client. It i s not i ntended f or a nd s hould n ot be relied u pon b y any third p arty a nd no responsibility i s u ndertaken to any t hird Ove Arup & Partners Ltd party The Arup Campus, Blythe Gate, Blythe Valley Park, , . B90 8AE

Tel +44 (0)121 213 3000 Fax +44 (0)121 213 3001 www.arup.com Job number

High Speed Two (HS2) Infrastructure Maintenance Depot

Contents

Page 1 Introduction 1 1.1 The December 2009 Report 1 1.2 Layout of this Report 1 2 Scope of Work, Methodology and Deliverables 2 2.1 Scope of Work 2 2.2 Meeting 1 2 2.3 Intermediate instructions 3 2.4 Meeting 2 3 3 Current Rail Operations and Future Developments 4 3.1 Context 4 3.2 - 4 3.3 – Claydon Line 4 3.4 High Speed 2 5 3.5 Evergreen 3 5 3.6 East West Project 5 4 Functional Requirements 6 5 Site Location Options 7 5.1 Introduction 7 5.2 Quadrant 1 9 5.3 Quadrant 2 11 5.4 Quadrant 3 15 5.5 Quadrant 4 17 5.6 Sites on HS2 (north) 18 6 Cost Estimates 20 6.1 Matrix table for all Site options 20 7 Conclusion 21 8 Selected Option Development 23 8.1 General layout 23 8.2 Specific site details 27 8.3 Site operation 28 8.4 West end connections 29 9 Calvert Waste Plant 30 9.1 Rail Access 30 9.2 Heat and power generation 32 10 Use of site as a potential construction depot 33

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

10.1 Additional land take 33 10.2 Use of other supplementary depots 33 11 Bicester MOD Depot 34

Figures Figure 1 Current track layout Figure 2 Quadrant locations Figure 3 Initial Site Identification Figure 4 Location plan – Site 1.1 Figure 5 Location plan – Site 2.1 Figure 6 Location plan – Site 2.2 Figure 7 Location plan – Site 2.3 Figure 8 Location plan – Site 3.1 Figure 9 Location plan – Site 3.2 Figure 10 Site Location Figure 11 Location plan – Site 4.0 Figure 12 Cost Estimate Figure 13 Matrix table Figure 14 Depot Layout Figure 15 Concept Plan Figure 16 Concept Plan – Plan A and Plan B Figure 17 Concept Depot Schematic Figure 18 West end connection sub option Figure 19 Comparison of siding lengths: single and double ended Figure 20 WRG Depot

Appendices Appendix A Functional Requirements Specifications A1 Introduction A2 General Requirements Appendix B Drawings B1 General Site Layout Concept Plans Drawing Numbers: HS2-ARP-07-DR-RW-00007 HS2-ARP-07-DR-RW-00008 HS2-ARP-07-DR-RW-00009 HS2-ARP-07-DR-RW-00010 HS2-ARP-07-DR-RW-00011

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

1 Introduction

1.1 The December 2009 Report

In December 2009, Arup issued a report to High Speed Two Limited (HS2) presenting the findings of a route engineering and alignment study for a potential new high-speed rail line from to the West Midlands. It described the process for generating route options connecting the two locations and the sieving process by which a Preferred Route – Route Number 3 – was chosen by HS2.

1.2 Layout of this Report

The report is laid out as follows: Section 1, this chapter, is introductory; Section 2, describes the Scope of Work, Methodology and Deliverables; Section 3, describes the current and future Rail Operations in the Calvert area; Section 4 , des cribes the F unctional Requirements required for an H S2 Infrastructure Maintenance Depot; Section 5, describes the site locations assessed during this study; Section 6, describes the Cost Estimate and contains an initial high level assessment of the potential costs involved in creating the depot; Section 7, describes the Conclusions and proposes a site to be developed; Section 8, describes the selected site and option development; Section 9, describes the Calvert Waste Recycling Site; Section 10, describes the Potential use of the depot as a Construction depot; and, Section 11, describes the Bicester MOD depot and its potential use.

Page 1

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

2 Scope of Work, Methodology and Deliverables

2.1 Scope of Work

In April 2010, a number of additional tasks were undertaken by Arup (refer to Arup, st Technical Financial Proposal, Section 3, dated 31 March 2010), one of which focused on the development of proposals for the siting of the Infrastructure Maintenance Depot (IMD). This report deals with the siting and specification of the Infrastructure Maintenance Depot. The obj ective of t his r eport i s t o pr ovide op erational and e ngineering proposals t o as sist HS2 to identify the best possible location and the master layout of the depot for the London to West Midlands HS2 route. The report identifies a suitable site for the IMD and develops a m aster layout f or the site, including both rail infrastructure and ancillary facilities such as office accommodation, services buildings, s torage an d lay down areas, s taff par king, ap proach r oads and ot her related items. The report makes proposals for a solution which appears to provide the best combination of facilities and location. It does not make conclusive proposals, and is provided to inform and illustrate. I t i s ex pected t hat t he s ite des ign will d evelop o ver t he nex t per iod f ollowing further consideration by HS2 and discussions with Arup, and meetings with relevant stakeholders such as the (EWR) project and Waste Recycling Group (WRG).

2.2 Meeting 1

An initial scoping meeting took place in London on 28th April, attended by – HS2 and Arup. The m eeting identified a s et of t asks w hereby Arup was r equired t o r eview t he f ollowing factors relating to the IMD. These are as follows: • Location; • Functional Requirements; • Maintenance Strategy, Size; • Site Issues, Equipment; • Visual Impact including simple visualisations; • Relationship to Calvert Waste Plant; • Geology/Aquifers, settlement, Constructability; • Cost, Programme; • Electricity Supply; • Liaise with construction logistics; and, • Environmental issues and constraints. The deliverables were agreed to be: • Large scale plan of depot layout , interface with HS2 and the network, and surrounding area; • Horizontal al ignment dr awings of c onnectivity to HS2 and ex isting r ail line ( East- West main line); • Master plan of depot; and, • Report.

Page 2 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

2.3 Intermediate instructions

In an intermediate discussion between John Castle (HS2 Senior Route Engineer) and Chris Lees (Arup Project Manager) on 14 th May, a list of possible sites was agreed, which Arup would scope to provide initial comments on suitability and functionality. These plans were prepared and discussed at Meeting 2.

2.4 Meeting 2

A s econd m eeting took place at Arup’s offices on 19 th May. At this m eeting a number of potential s ites were r eviewed and t heir attributes di scussed. T he H S2 t eam pr ovided a n input on the preferences for each site, and after discussion a refined set of objectives were produced. In addition to the above deliverables these comprised of:

• Development of proposals for sites 2.2 and 3.2, and a new option for a single ended set of sidings inside the chord line (site 2.3);

• Extension of the scope to examine any other possible level sites on HS2 up to 10 km north from Calvert; and,

• Review of op tions f or pos sible use of Ministry of D efence ( MOD) Bicester as a n I MD site.

Page 3

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

3 Current Rail Operations and Future Developments

3.1 Context

This s ection di scusses the current rail r outes in the C laydon ar ea, an d summarises proposals f or their development in t he next 10 years. T he p ossible impact of locating an IMD at Claydon is also discussed. The current track layout is shown in the diagram below. Track layouts are accurate but in diagrammatic format.

HS2 Milton route Keynes Passenger Bicester line to Town Claydon “Mothballed” line Oxford Station LNE Jn

Bletchley Waste To MOD train run Bicester round

WRG Calvert WCML Terminal

To Aylesbury

Figure 1 Current track layout

3.2 Oxford - Bletchley

The East-West Line is the former Oxford to , via Bletchley and Bedford, line. The status of the route is as follows:

• Oxford to Bicester Town – single track with no passing loops, used by passenger trains from O xford – Bicester T own, f reight t rains f rom D idcot t o MO D B icester, and freight trains from London and to the WRG Calvert private siding.

• Bicester Town to Claydon Junction - single track with no passing places. Used by freight trains f rom London a nd B ristol t o the W RG C alvert pr ivate s iding. A t C laydon LN E Junction there is a run round loop where trains bound for Calvert can reverse.

• Claydon London North Eastern (LNE) Junction to Bletchley – the line has been out of use since 1997, though it is officially still operational and only ‘mothballed’. Some track sections are missing and the route is unusable at present.

• Bletchley to Bedford– the line is double tracked and used by a passenger service from Bedford to Bletchley, and occasional freight traffic.

• Bletchley t o Mi lton K eynes – a c hord line gives ac cess t o t he West C oast Ma in Li ne (WCML) heading north to . This and the run round loop at the current end of the branch were previously used by engineering trains running from the Stewartby Local Distribution Centre (LDC) to the WCML.

3.3 Aylesbury – Claydon Line

The Aylesbury to Claydon line is a remnant of the former . The line is single tracked and the only connection is a set of loops to serve the WRG Calvert waste

Page 4 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

transfer terminal. This terminal is served by trains of containerised domestic refuse from the London and Bristol areas to the site for landfill, and some bulk trains of low grade hazardous waste. Freight traffic runs to the terminal from both Aylesbury and Claydon directions.

3.4 High Speed 2

HS2 is pr oposed t o r un South – North t hrough the area i n t he d iagram on a f ormation parallel and t o t he west of t he c urrent A ylesbury t o C laydon l ine, c ontinuing north on t he former Great Central Main Line trackbed. The current single line would be moved Eastwards within the rail corridor to facilitate this.

3.5 Evergreen 3

Chiltern R ailways, t he holder of t he Department f or T ransport (DfT) Chiltern f ranchise, i s constructing a ne w c hord line f rom the Marylebone t o B anbury line at Bicester to join the Oxford to Bicester line near Bicester Town station. Some track doubling will be carried out, and a half hourly Oxford to Marylebone service will be run. TWO powers are currently being applied f or, and t he pr oject i s ex pected t o b e c ompleted by 2013. E vergreen 3 i s a DfT franchise commitment.

3.6 East West Project

East –West R ail ( EWR) proposes to refurbish the Oxford – Bedford (and ul timately Cambridge) r oute, and r estore dou ble t rack on t he O xford t o C laydon s ection. F rom Claydon to Bletchley a new double track formation will be provided on the existing trackbed, and the section on to Bedford will be upgraded. EWR proposes a linespeed of 90 mph. The single l ine from A ylesbury will b e retained b ut u pgraded to 90 m ph. Comprehensive new s ignalling f acilities will be r equired t o provide s ufficient capacity on b oth routes. T he project is intended to be completed by 2017, subject to funding from central government and other sources such as property developers. Once complete the following service pattern is contemplated:

• Hourly Oxford to Milton Keynes;

• Hourly Oxford to Bletchley;

• Hourly fast Oxford to Milton Keynes;

• Hourly freight Oxford to WCML;

• Hourly Milton Keynes to Bedford; and,

• Hourly Aylesbury to Milton Keynes. No n ew s tations are proposed in t he C laydon/Calvert ar ea, with t he ne arest pr oposed station being at Winslow. Provision has been made for one daytime freight train per hour in each direction, but it is not clear how m any ( if any) of t hese p aths would b e available f or us e by HS2 i nfrastructure services. Capacity for freight trains to access the intermediate run round siding at Claydon is bound to be restricted. EWR will have to provide a new run round facility at Claydon, at roughly the point identified for run round loops to serve site 2.3, and there may be synergy between the projects here. It is unclear how EWR proposes to manage construction logistics, a nd whether t here i s s ynergy between t he pr oject and H S2 for t he l ocation of construction and track laying depots. Discussions with EWR would help resolve this.

Page 5

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

4 Functional Requirements Both A rup an d H S2 dr ew up ou tline s pecifications of t he F unctional R equirements f or an Infrastructure Mai ntenance D epot. Arup c arried o ut a c omparison of t he t wo d ocuments. There was a large degree of agreement in the requirements specified by both teams, and the results were therefore combined into one master Functional Requirements Specification (FRS). This was debated and agreed at Meeting 2. At t his s tage the FRS is i ntended t o b e a d iscussion doc ument, r ather t han a c onclusive statement of needs , a nd the intention is t hat t his f orms t he bas is of d iscussions an d consultations with stakeholders within HS2 and the wider rail business. The requirements were slightly revised following the meeting, to reflect emerging thinking by the H S2 t eam and t o al so t o incorporate s ite d evelopment t hinking. I n particular t he following changes were made:

• Storage sidings were allowed to be single ended to allow adoption of a more compact site.

• The range of track materials to be stored at the IMD was increased to include drainage, troughing and other materials.

• The r ole of Li ght Maintenance D epots ( one of w hich w ill be located at t he I MD) was clarified to reflect the need for maintenance staff to be based at the IMD site.

The c urrent F unctional R equirements S pecification ( FRS) i s i ncluded i n t his d ocument as Appendix A. The FRS has been used in the consideration of the suitability of each site to ensure that the selection process reflects the need to eliminate sites which are functionally unsuitable before consideration of a short list on the grounds of environmental, engineering and financial merit.

Page 6 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

5 Site Location Options

5.1 Introduction

To determine suitable site locations, Arup drew up a depot footprint and i dentified suitable areas where the footprint could be accommodated. The basic criteria for the site footprint (taken from the Functional Requirements Specification) were as follows:

• Level site.

• Straight site.

• Site length of approximately 1 km.

• Capability to connect with both HS2 and the EWR.

• Minimisation of environmental impact by avoiding:

o Immediate proximity to built up areas; o Use of flood plain; and, o Areas of high visual impact. A range of s uitable s ites was identified, allocated b y each qu adrant of t he two r ail r outes (HS2/Aylesbury – Calvert line (MCJ1) and The East West Oxford – Bletchley line (OXD) as shown below:

• Quadrant 1 North West

• Quadrant 2 North East

• Quadrant 3 South East

• Quadrant 4 South West

Quadrant Quadrant 1 2

OXD

Quadrant Quadrant 4 3

MCJ1

Figure 2 Quadrant locations A t emplate terminal footprint was drawn up an d assessed against Ordnance Survey mapping of t he ar ea t o identify possible s ites. N o c onsideration was g iven in t his initial exercise of specific site suitability. The sites identified as suitable by this process are shown on the following page (Figure 3):

1 MCJ is the Engineer’s Line Reference (ELR) for the line from Aylesbury to Calvert. Page 7

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

HS2 Quadrant 2 Steeple Claydon

EWR Quadrant 1

Quadrant 3

Calvert

Quadrant 4

HS2

Figure 3 Initial Site Identification

The s ites were then r eviewed in detail for s uitability against t he r equirements of t he F RS and for the means of linkage with both HS2 and the national rail network. Conclusions were drawn for each site as a result of this exercise. Sites are defined by using the following nomenclature: the first number refers to the quadrant they are located in, and the second number is the individual site identifier. Site location p lans c ontain di rectional ar rows r elating t o t he d irection of s ite p hotographs. E.g.

Page 8 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

5.2 Quadrant 1

5.2.1 Site 1.1 Twyford Lodge

Portway Farm

Figure 4 Location plan – Site 1.1

Photograph 1 Photograph 2

Description The s ite l ies t o t he north of t he EWR line be tween t he villages of P oundon a nd T wyford. The EWR line at this point is straight which allows for a straight site. The EWR line rises at approximately 1 in 1430 in this area. This means that a level site can be created; however the s ite is i n d irect view of t he village of T wyford, and du e t o t he t opography, s lightly elevated in open fields.

Page 9

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

Connections to HS2 It is not possible to build a West to South chord line to access HS2. It is also not possible to build a West to North chord to access HS2 without going very near to the village of Twyford and going through Portway Farm. The only way to access HS2 is to use a run round loop to the E ast of H S2 ( shared with t he waste t rains t o C alvert) t o ac cess i t f rom t he opp osite direction.

Page 10 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

5.3 Quadrant 2

5.3.1 Site 2.1 Pond Road

Figure 5 Location plan – Site 2.1

Photograph 3 Photograph 4

Description The site lies to the North of the EWR line adjacent to the village of Steeple Claydon. The site i s bisected b y P ond Road, an unclassified r oad r unning f rom S teeple C laydon t o Calvert. The EWR line is straight at this point which allows for a straight site. The EWR line rises at approximately 1 in 209 in this area, which means that significant earthworks would be required to create a level site. In addition, this would mean that the viable site would be

Page 11

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

near t o the existing C laydon London N orth E astern (LNE) Junction. Although t he s ite is below the village of Steeple Claydon it would be within 500 metres of it. The Eastern end of the site lies on flood plain.

Connections to HS2 There is already a chord line running from East to South that accesses the HS2 route which is used by the waste train running from the Bristol area to Calvert. It is possible to build an East to North chord to access HS2.

5.3.2 Site 2.2 Claydon Junction

Figure 6 Location plan – Site 2.2

Photograph 5 Photograph 6

Page 12 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

Description The site lies on the track of an E ast to North chord line running from the EWR line to the HS2 North section heading towards . The site would have to be curved to follow the route of the chord. The level of HS2 in this area is not finalised, but it is intended that it will run at level and the EWR line will be raised to run over it. This assumption means that the s ite c ould b e l evel with r elatively m inor ear thworks. Land t ake w ould be c onsiderable though, using relatively open farmland. T he s ite would b e c lose t o t wo relatively isolated houses, but not near significant habitation and not within the view of nearby villages.

Connections to HS2 The site lies on the chord line to HS2. Access to the site from the Oxford direction would be via a run round also required for waste trains from Bristol to Calvert. Access to HS2 South would be via run round loops alongside HS2 opposite the village of Twyford.

5.3.3 Site 2.3 Thame Road

Figure 7 Location plan – Site 2.3

Page 13

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

Photograph 7 Photograph 8

Description In agreeing that this could be a possible location, the requirement for all storage sidings to be double ended was relaxed. The site lies to the i mmediate East of HS2 an d within the East to North chord line, bounded to the South by the EWR line, to the West by HS2, and to the N orth East b y the c hord l ine. The l evel of H S2 i n t his ar ea is no t f inalised, but it is intended t hat it will run at level an d t he EWR line will b e raised over it. T his a ssumption means that the site could be level with relatively minor earthworks, though the former Great Central Main Line embankment would need to be removed. Land take would be relatively modest, and would maximise use of land already sterilised by the construction of the chord line. The site could be accessed from the Northern section of the existing unclassified “Thame R oad”, w hich in a ny c ase will r equire t o b e di verted because it crosses the EWR line at almost exactly the point where HS2 will intersect it. The s ite is n ot adjacent t o a ny properties. I t a ppears t hat a lmost al l the s ite c ould be constructed i n one field running in a n L s hape f rom C laydon J unction t o t he HS2 r oute, though land o wnership has not been r esearched. I n t he South W est corner of t he s ite between the East West “Thame Road” overbridge and the GC embankment there is a gas Pressure R educing Station on t he nat ional gas n etwork, ow ned b y S cotia N etworks Lt d. There does not ap pear t o be a di fficulty in d esigning a s ite layout t hat pr eserves this. However t he location of t he as sociated gas p ipelines has no t yet been as certained in a services search a nd this may pr esent a pr oject r isk i f t he pipeline is f ound t o r estrict s ite layout options or operations. One public footpath runs across the site, which will require closure or diversion.

Connections to HS2 Access to HS2 would be via the run round loop also required for waste trains from Bristol to Calvert, which would also act as headshunt for the site. A chord line would be constructed to the HS2 north, and trains to HS2 south could either use this chord and run round at the loops near Twyford village, or could use the existing east to south chord and access HS2 opposite the waste terminal.

Page 14 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

5.4 Quadrant 3

5.4.1 Site 3.1 Greatmoor

SSSI

Figure 8 Location plan – Site 3.1

Description The site lies to the East of the former Great Central Aylesbury – Claydon Junction line, and just t o t he N orth of t he f ormer G rendon U nderwood Junction. The Li ne f alls a t approximately 1 i n 17 6 t o t he N orth to an underbridge o ver a s mall dr ain ne ar t o Sheephouse Wood. There is a 5 metre difference in line height from one end of the site to the other, which means that a level site could only be created with considerable earthworks. It is understood that the site is owned by Waste Recycling Group (WRG). There is no road access t o t his ar ea, t hough t here is a pr oposal by WRG t o c onstruct an ac cess on t he former Junction line trackbed. The site is bounded to the North by Sheephouse Wood, which is a Site of Special Scientific Interest (SSSI). The site is not overlooked by any significant residential areas.

Connections to HS2 The site is alongside the HS2 route, and accessed from the EWR line via the existing chord line. A West to South chord is not possible because of a nature reserve and lakes which lie on the route. The only way to access HS2 from the Oxford direction is to use a run round loop to the East of HS2 (shared with the WRG waste trains to Calvert). If the East West proposals ar e i mplemented, i t is un derstood t hat t here i s likely to b e a n h ourly s ervice i n each direction along the existing single line. There would be capacity to access HS2 form the site with appropriate signalling.

Page 15

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

Site 3.2 Great Pond

Figure 9 Location plan – Site 3.2

Photograph 9 Photograph 10

Description The site lies to the East of the former Great Central Aylesbury – Claydon Junction line, and opposite the current WRG waste transfer terminal. The Line falls at approximately 1 in 330 to the North to the former station site, which is level, and t hen rises at approximately 1 i n 176. This means that a level site could be created with modest earthworks. The site is on agricultural l and with no i mmediate h ousing o verlooking i t, t hough i t i s o pposite C alvert village. T he s ite would be al ongside t he pr oposed r elocated WRG t ransfer station which would a dd c onsiderably t o t he land t ake, as the WRG s ite will r equire r easonable r oad vehicle c irculating ar eas, and r oad access r equirements w ould po tentially c onflict with rail access routes. It can only be created with considerable earthworks. Page 16 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

The site is bounded to the South by Decoypond Wood. The site is overlooked from across the railway line by the edge of Calvert village, though there is some tree screening

Connections to HS2 The site is alongside the HS2 route, and accessed from the EWR line via the existing chord line. A West to South chord is not possible because of a nature reserve and lakes which lie on the route. The only way to access HS2 from the Oxford direction is to use a run round loop t o t he eas t of H S2 (shared with t he WRG waste tr ains to C alvert). If th e EWR proposals are i mplemented, i t is un derstood t hat t here i s likely to b e a n h ourly s ervice i n each direction along the existing single line. There would be capacity to access HS2 from the site with appropriate signalling.

5.5 Quadrant 4

No suitable sites were identified i n Q uadrant 4, as t his ar ea i s oc cupied b y C alvert a nd Charndon villages, and the former Calvert brick pits (which are now used for landfill).

Page 17

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

5.6 Sites on HS2 (north)

5.6.1 Site 4.0 Mixbury At the m eeting on 19th May HS2 asked Arup to widen its consideration of sites to include any l evel site on the HS2 alignment North of Calvert and within 10 km of the junction with the EWR line. A search on the proposed HS2 route revealed only one potential site which met the required attributes of length and level at Mixbury, just on the 10 km boundary. The site lies on the West of the HS2 route, to the South West of Mixbury village. While the HS2 formation is level at this point the adjacent land rises to the North West, which means that substantial e arthworks w ould be r equired. T he land i s in agr icultural us e a nd i s directly overlooked only by Mixbury Lodge. A public footpath runs across the site.

Figure 10 Mixbury Site Location

Page 18 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

Figure 11 Location plan – Site 4.0

Photograph 11 Photograph 12

5.6.2 Connections to HS2 The site is alongside the HS2 route, and would have to be reached by construction of a new 10 km single line from Claydon, which would need to cross the HS2 formation at some point by either an overbridge or underbridge, depending on the vertical alignment. Access from the EWR line would be via a new East to North chord line. Access from the Oxford direction would be via a run round loop to the East of HS2 (shared with the waste trains to Calvert).

Page 19

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

6 Cost Estimates We hav e c arried out a n i nitial hi gh level as sessment of t he potential c osts i nvolved in creating the depot. This is be based on compilation of an outline bill of quantities for each of the sites, using standard assumptions on track layout and required facilities, but customised for each site to reflect specific attributes. The bill of quantities has been priced using unit costs based on Arup rate and experiences on recent similar projects with similar attributes. The costs should be treated as indicative, and demonstrating in relative terms the respective costs of each of the options considered. The summary of the cost estimates is shown in the table below.

Figure 12 Cost Estimate

6.1 Matrix table for all Site options

The s ites w ere r eviewed t o i dentify whether t heir s pecific at tributes ag ainst a list of k ey requirements as set out in the Functional Requirements Specification, and other key requirements which have been identified during project development. Each site was scored in a range of 1 (poor) to 3 (good) for each of the requirements, and then the scores were totalled. Although a relatively crude measure, this provides an easily understood guide to the relative merits of the various sites. The matrix should therefore be read as providing a guide rather than as being a definitive sift process. The evaluation for each site is shown plotted on the matrix below:

Score 1 High risk/problematic 2 Medium 3 Low/ OK

Matrix table for IMD

Site 1.1 Site 2.1 Site 2.2 Site 2.3 Site 3.1 Site 3.2 Site 4.0 Sufficient area for depot layout 3 3 3 3 3 3 3 HS2 connection - direct connection 1 3 3 3 3 3 2 Railway issues Amount of shunt moves required 1 3 3 2 3 3 3 Level site 2 2 3 3 1 2 3 East-West line connection 3 3 3 3 2 2 1 Potential Visual Intrusion 1 1 2 3 3 2 1 Environmental impact to Potential Noise level 1 1 2 3 3 2 1 surrounding area Impact on Flood Plain 3 1 3 3 3 3 3 Undulated terrain 3 3 3 3 3 3 3 No conflicting land use 3 3 2 3 3 1 3 Geographical issues Services 3 3 2 2 3 3 3 flat/even terrain 3 2 3 3 1 2 3 Road access 3 3 3 3 1 2 3 Logistics potential construction site 1 1 1 3 2 1 2 Cost 2 1 2 3 1 2 1 Score 33 33 38 43 35 34 35 Worst possible score 15 Best possible score 45 Figure 13 Matrix table Page 20 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

7 Conclusion Following assessment of the sites, we have drawn up conclusions of the suitability of each location, i ncluding t he r esults of the m atrix assessment a bove, an d other m ore qualitative factors w hich ap ply s pecifically to c ertain s ites. T he c onclusions of t his exercise ar e summarised below.

7.1.1 Site 1.1 Twyford Lodge The site would be very visible from the village of Twyford and relatively inaccessible from HS2. A new west to north chord line would be relatively intrusive because of the angle of the lines in this area. It is recommended that this site option is not developed.

7.1.2 Site 2.1 Pond Road The topography of the land in this area would make connections difficult without substantial earthworks. The s ite i s c onsidered t o be t oo c lose t o t he v illage of S teeple C laydon an d interferes with the flood plain. It would also require Pond Lane to be diverted or closed. It is recommended that this site option is not developed.

7.1.3 Site 2.2 Claydon Junction The site would be viable, but requires relatively large agricultural land take and is closer to Steeple Claydon than option 2.3. Given that option 2.3 appears to offer reduced land take, a more compact site and is further from neighbouring residential properties it is recommended that this site option is not developed.

7.1.4 Site 2.3 Thame Road It i s r ecommended t hat t his site is de veloped i n d etail, as i t of fers t he bes t opt ion of minimised land take and minimised environmental impact. However in view of the potential risk to site use posed by the gas pipeline, other sites should be kept under review in case significant issues are identified.

7.1.5 Site 3.1 Greatmoor While it would be technically possible to construct an IMD on this site it would require major earthworks to create a level site. The site is environmentally sensitive, with an SSSI immediately t o t he N orth. There i s al so n o r oad access t o t his s ite. It is t herefore not recommended that this site should be developed.

7.1.6 Site 3.2 Great Pond It is technically possible to construct an IMD on this site, though it is close to Calvert village. The s ite w ould be c omplicated b y t he presence of t he r elocated WRG w aste t ransfer terminal whose r oad access r equirements pot entially c omplicate t he s ite layout. F or t his reason it i s r ecommended t hat the s ite be c onsidered f urther, but not as a d evelopment priority.

7.1.7 Site 4.0 Mixbury It is technically possible to construct an IMD on this site, but the length of new branch line required in p arallel t o t he H S2 f ormation would only be j ustified i f t he s ite c hosen was substantially m ore suitable than o thers. T his is not t he c ase, as s ite levels would require major alteration, while the site itself is in a prime rural setting. It is not recommended that this option is developed.

7.1.8 Overall Conclusion The overall conclusion of the exercise is that the site which best meets the criteria laid down in the Functional Requirements Specification is site 2.3 – Thame Road. Although of all the options, this alone requires engineering train storage to be in single ended sidings (therefore requires increased s hunting m oves,) the s ite h as the advantage of remoteness f rom local communities, and is contained within the overall rail footprint.

Page 21

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

Site 3.2 – Great Pond also appears to have some suitable attributes, but is compromised by the WRG discharge terminal and proximity to Calvert village, and therefore should be only examined further if Thame Road appears to have major problems.

Page 22 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot

8 Selected Option Development

8.1 General layout

The overall conclusion of the exercise is that the site which best fits the criteria laid down in the Functional requirements specification is site 2.3 – Thame Road To dem onstrate t he p otential l ayout of t he s ite a s eries of c oncept layout dr awings were created, il lustrating possible o ptions. T he ov erall l ocation of t he s ite r elative t o t he r ail connections and the concept layout are shown on the following three pages:

Page 23

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

Figure 14 Depot Layout

Page 24 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

Figure 15 Concept Plan

Page 25 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

Figure 16 Concept Plan – Plan A and Plan B

Page 26 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

8.2 Specific site details

The site has the following features:

• On the assumption that the Thame Road is diverted or closed, the former road formation is used as an access road to the IMD.

• A concept road diversion option is shown, though other work packages are dealing with this.

• A new East to North chord line is constructed to give access to HS2.

• To minimise the HS2 main line connection S&C it is intended that this chord is the only access t o H S2, and t hat t he East t o South c hord is r etained as n ow purely as a n access to the Aylesbury route and waste terminal, though HS2 connections c ould be included without major impact.

• Three run r ound s idings ( all s ignalled f or n ormal s peed ( 30 m ph) en try and e xit) ar e created at t he E ast e nd of t he s ite, f or bot h HS2 engineering t rains and f or t rains accessing the Calvert waste site and Aylesbury line.

• The s idings will be in c utting at l ower level t han t he s urrounding f ields, and w ill be screened by this level difference from Steeple Claydon village.

• An additional loop is c reated a longside H S2 at T wyford t o pr ovide r oute ac cess for engineering trains.

• The chord line and run round sidings are overhead wired, but not the depot itself.

• The chord line, run round sidings and depot are all constructed to UIC GC gauge.

• The chord line forms the railway boundary and all sidings are contained within it.

• Six single ended engineering train storage sidings are created inside the depot.

• A 200 m etre x 40 m etre equipment storage and laydown s ite is provided in the depot and handling will be by 2 gantry cranes spanning the storage area.

• Where feasible overhead lighting will be provided by portals over the tracks to minimise light spillage outside the site.

• The run round sidings will be lit at low level by walkway lights to minimise visual impact.

• Locomotive and yellow p lant s tabling s idings, a m aintenance de pot an d f uelling point, and wagon cripple sidings are all provided in line with the requirements of the FRS.

• Access to the depot is via a barrier controlled level crossing, but the office buildings and car par king ar e s ituated o utside t he r ail b oundary t o minimise movements ac ross t he crossing.

• The rail site will be a high security site with access controlled by gate (incorporating the level crossing). The general administration offices and car parking will be outside this high security area to ensure that only authorised personnel enter it.

• Almost all the site footprint appears to be within one common field boundary, minimising land take and site acquisition.

• The ex isting gas f eeder s tation is s afeguarded and r etained on i ts c urrent f ootprint.

Page 27

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

8.3 Site operation

The schematic track layout is shown below.

Figure 17 Concept Depot Schematic It i s i ntended t hat t rains o r r ailborne pl ant ar riving at t he I MD will r un into t he run r ound sidings. Where appropriate, trains could be taken from here direct to HS2. Other trains will be s hunted i nto t he storage s idings to b e he ld ready to g o on to possessions l ater. T rains with materials for the storage area (S&C components, sleepers etc.) will be shunted into the storage yard f or unl oading. I t i s e nvisaged t hat t he de pot will r equire one s hunting locomotive to perform these functions. Yellow plant, ‘thunderbird’ locomotives and other HS2 on track equipment will be maintained and fuelled at the maintenance depot in the North corner of the site, and storage sidings are also provided to stable locomotives while waiting for duty at the neck of the yard. Covered m aterials s tores w ill a lso be within t he r ail ar ea. T he c hord line and ot her r ail routes ( EWR and H S2) will pr ovide nat ural s ecurity, but t he r ail s ite will b e f enced with security fencing, and access will be strictly controlled. The only road access will be via a level crossing. Other site activities (offices, car parking, non essential stores and the Light Maintenance D epot) will b e l ocated out side t his s ecurity area on land t o t he N orth of t he site. Trains bei ng pr epared to g o ont o pos session s ites o n H S2 will be f ormed on t he s torage sidings, ei ther f rom i ncoming t rains or f rom wagons l oaded i n t he s torage area w ithin t he depot. Trains will be pulled out into the run round sidings and taken down to Twyford loop

Page 28 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

ready for despatch onto HS2. It is envisaged that propelling movements will be minimised, and that in normal service only trains being shunted into the depot will be propelled. It is envisaged that t he m ajority of possession t rains o n H S2 will be ‘ top an d t ailed’, which minimises the number of run round moves which are required at the IMD or at Twyford.

8.4 West end connections

A sub option of the depot design has been examined, to provide connections between the stabling sidings at the Western buffer stop end, to allow locomotives to run round incoming trains. Connection to the EWR line is not possible at this point, due to the line being carried over HS2 on an overbridge. The location of the headshunt is constrained by the need to avoid the Pressure Reducing Station. The connections for this sub option shown in the diagram, below.

Figure 18 West end connection sub option

The effect of the sub option is to reduce the length of the stabling sidings, as demonstrated in the table below: Usable standage on siding

Single Ended Option Double Ended Option Siding No. 01 775m 537m Siding No. 02 775m 572m Siding No. 03 775m 678m Siding No. 04 775m 678m Siding No. 05 775m 607m Siding No. 06 775m 537m

Figure 19 Comparison of siding lengths: single and double ended

There is limited opportunity to move the yard neck eastwards, because of the tie-in with the chord line and the EWR line. The trade off between maximising the length of storage and increasing o perational f lexibility i s t herefore c lear. Our c onclusion i s t hat the add itional operational functionality offered by this sub option is outweighed by the loss of siding length, and therefore the run round option should not be adopted.

Page 29

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

9 Calvert Waste Plant

9.1 Rail Access

This report has not reviewed, in detail, the facilities to be provided for WRG at a relocated Calvert terminal site. It is understood that this will be on the east of the Aylesbury – Claydon line parallel to the existing sidings and near the footprint of site 3.2. It is proposed that the existing sharply curved chord line from Claydon London North Eastern (LNE) Junction will be retained in its current location to minimise environmental impact, and that HS2 formation will be adjusted to provide space for this. The proposed depot location means that the new shallower curved east to north chord can be used for HS2 access, and it is proposed that no use is made of the existing chord, which will only carry Aylesbury - Milton Keynes passenger trains and freight services. Therefore no c onnections h b een pr oposed b etween t he Network R ail line and H S2 at C alvert, though this could be provided if desired. In concept, we believe that the waste depot will require two sidings at least 800 metres in length (to provide movement of the train under a static gantry s ite as at pr esent) or 2 x 400 m etre s idings w ith f ull Rail M ounted G antry (RMG) access to the length of the train. Road access to the site will be via a new overbridge to a new circulating area on the east side of the terminal, which is one of the reasons why site 3.2 is not considered suitable for the IMG. Drawing n umber HS2-ARP-07-DR-RW-00011 Issue 1.0 s hows a n i ndicative layout for the WRG, shown on the following page.

Page 30 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

Figure 20 WRG Depot

Page 31

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

9.2 Heat and power generation

The Calvert WRG plant already runs a local power station, fed by methane generated from the landfill area. The landfill will continue to generate methane through the life of the IMD project, and it would appear appropriate to consider using this as a source of fuel for heat and po wer generation purposes, possibly though a small combined heat and power plant, located alongside the IMD. This would potentially allow the IMD to become independent of grid power and gas supplies and would be an a ppropriate ex ploitation of an av ailable c arbon neutral e nergy s ource. Further development of this option in conjunction with WRG would be appropriate.

Page 32 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

10 Use of site as a potential construction depot As par t of t his pr oject, discussions h ave b een h eld with t he Arup team r eviewing construction logistics, and options for supplying track materials to HS2. In principle the IMD could provide all or part of this function, though the site is probably too small to handle all the trains required for the two year construction phase. There appear to be two options to supplement capacity.

10.1 Additional land take

It would be possible to provide additional sidings on a short term basis, with restoration of the a dditional site after construction ha d been c ompeted (as happened on the H S1 Beechbrook Farm depot). This would be possible, and such sidings could be to the north of the c hord line on a djacent agr icultural l and. S ome of t he ot her s ites c onsidered i n t his report (and specifically site 3.2) may also be suitable for temporary use.

10.2 Use of other supplementary depots

There are two other sites which are located on the East-West route, and which may have capacity to act as secondary materials supply depots. Neither of these sites could support GC gauge traffic, and their remoteness from the HS2 connections and route access limitations may restrict their usefulness. However they both have the capability of providing the required additional capacity for a short period at minimal capital cost and environmental impact. The MOD site at Bicester is described below, and may have the capability to handle trains for HS2 track lying, though access to the site may be difficult. Network Rail established a site to supply West Coast Route Modernisation (WCRM) requirements at the WRG Stewartby terminal, near Bedford on the EWR line (some 17 miles away). The depot performed the role of a classic Local Distribution Centre (LDC), and had ballast stockpiling and spoil disposal facilities, as well as engineering train storage. There were however problems with operating long (600 metres+) trains because of an automatic half barrier crossing to the east of the site. The terminal is now out of use following the completion of WCRM, and could therefore be adapted for use as a secondary stocking option for HS2 track laying. Because of the distance from the HS2 route this depot has not been evaluated for suitability as an IMD.

Page 33

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

11 Bicester MOD Depot As part of this review, Arup suggested and HS2 agreed that consideration should be given to the possibility of use of land at the MOD depot at Bicester to perform the functions of an IMD. No discussions have been held with MOD. The Bicester depot is a massive complex which controls most of the stores for the British Army. It is administered by the Defence Storage and Distribution Agency (DSDA), and the rail operation is managed by DSDA Rail and Container Services (DRCS). There are over 30 m iles of track on the 1,500 acre s ite which dispatches traffic b y rail o ver a connection with EWR line a t B icester T own s tation. D RCS owns its o wn l ocomotive f leet and r ail operational personnel. The rail connection and exchange sidings face towards Oxford. DB Schenker has a contract with DSDA to move equipment around the country and through the Channel , and operates at least one train per day between Didcot and Bicester. The maximum t rain l ength t hat c urrently c an be ac commodated i nto t he s ite i s approximately 500 metres, though this could be increased with track alterations MOD has been seeking to open the site to commercial use (initially in the distribution sector) which would b e c ompatible with t he c urrent s ite us es. A n o pen day was h eld in 2 009 to canvas p ossible private s ector s upport, though to date no f irm plans hav e em erged. T he site has the benefits of high security, available development land with good rail access and limited planning restrictions, and very good road access to the A41 and M40. However the site is 8 miles from Claydon Junction, and is only cleared to Network Rail W8 gauge ( though t here ar e i ndications t hat D fT may c onsider f unding an i ncrease t o W10 gauge for 9’6” containers as part of the EWR project). There are 6 overbridges on the route which m ay limit t he options f or gr eater ga uge c learance ( one of t hese o verbridges i s t he Chiltern L ine Princes R isborough – Aynho J unction route) t o per mit t he pas sage of G C gauge v ehicles. T he c onnections at Bicester f ace t he w rong d irection, while i n f uture t he EWR and C hiltern Bicester – Oxford s ervice pr oposals m ay limit ac cess opt ions bet ween Bicester and Claydon. For this reason it appears unlikely that a site at Bicester could fulfil the function of an IMD and provide strategic access to HS2 on a daily basis, because of its distance from the route. There c ould h owever b e considerable m erit i n c onsidering locating additional temporary facilities here for the track laying phase of the project, and it would be worth conducting at least a n i nitial c onversation w ith D SDA t o u nderstand what pot ential f acilities c ould b e offered.

Page 34 Ove Arup & Partners Ltd

Appendix A Functional Requirements Specifications

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

A1 Introduction This F unctional R equirements S pecification s ets o ut t he k ey r equirements f or an HS2 Infrastructure maintenance\depot (IMD). It is the result of discussion between the HS2 and Arup teams. Any design for an IMD must confirm to the requirements of this specification. This document is intended at this stage to be a discussion document, rather than a conclusive statement of needs, and the intention is that this forms the basis of discussions and consultations with stakeholders within HS2 and the wider rail business.

A1.1 Purpose

There will be three light maintenance depots on HS1, where track and infrastructure maintenance g angs will b e l ocated, and t ravel t o worksite b y r oad t ransport. S tocks o f consumable spares will be k ept on site. One of these three depots will be in the London area, one near Birmingham, and the third will be located at the IMD. In the case of major infrastructure work, involving heavy maintenance and renewals, and rail delivery of r eplacement t rack materials will b e s upplied f rom a c entral I nfrastructure Maintenance Depot (IMD). The prime functions of the IMD are:

• Provide a base from which all rail based infrastructure maintenance activities are resourced a nd m aterials s upplied f or t he whole of t he s outhern t runk s ection o f H S2 (Euston – Birmingham inclusive).

• A c entral s upply p oint f or all e ngineering ( track & O LE) m aterial t hat r equires t o be delivered to site by rail plus strategic materials stocks

• A fuelling, servicing and stabling facility for:

o HS2 rescue and recovery locomotives

o HS2 on track plant (including GC gauge vehicles not able to travel on the National Rail network)

A1.2 Assumptions

This document makes the following assumptions:

• Standard track materials common across the high speed and classic rail networks will be supplied by Network Rail from their own Local Distribution Centre (LDC) and transferred to HS2 via the IMD, which will act as the storage and interface point. Track components s pecific t o HS2 will be s tored at t he I MD, which will ac t as t he s trategic supply point for the line.

• Excluding yellow plant moves, the maximum number of possessions to be supplied from the IMD is 2 on any working night, and the maximum number of possession train to be supplied onto HS2 is 4 on any working night.

• Track materials s upplied by t he I MD will b e l imited principally to b allast, s poil, r ail, sleepers, S &C, an d O LE ( masts and wiring). I t i s a ssumed t hat m aterials f or pur ely road b ased m aintenance operations would be h eld at t he L ight Ma intenance depots, and not normally be handled by the IMD (except for those items held by the local depot).

• Except where specifically stated in this document all materials wagons used to supply HS2 will be b uilt t o a g auge c ompatible with t heir m ovement on t he National R ail network (maximum Network Rail W8 gauge).

• Ballasted t rack w ill be t he us ual s pecification f or ope n a ir s ections.

Page A1

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

A1.3 Ballast

The ballast for HS2 will conform to the normal UK Network Rail track ballast specification. Ballast will be supplied by Network Rail, either in standard NR/HS2 ballast wagons (hoppers or side tippers) or in High Output Ballast Cleaners. Rolling Stock would probably be owned by a 3 rd party. A ll t rack bal last will be loaded at N etwork R ail s ites, and t here w ill b e no ballast stockpiling at the IMD. The following requirements are identified for track ballast: • The minimum ballast stabling siding length is 400m. At least one siding must be 775 metres in length to allow for storage of an HOBC. • The HOBC will be serviced and restocked at another site and not at the IMD. • The nu mber of bal last s tabling s idings pr ovided m ust be equa l t o t he m aximum number of ballast trains planned to be supplied to all sites on HS2 on one working night, plus 50% for contingency. • Passive provision will be made for a temporary ballast stock pile of 10,000 tonnes of ballast.

A1.4 Rail

HS2 will be laid with UIC 60 specification rail. Rail will be supplied by Network Rail, normally in 216 m etre s trings on L ong Welded R ail ( LWR) s ets or i n s ingle 20 m etre length on conventional wagons. Rolling Stock would probably be owned by a 3rd party. All rail will be loaded at manufacturing p oints (Corus S cunthorpe or NR E astleigh pl ant) and w ill not be unloaded at the IMD. The wagons used to bring materials from the National Rail; network will be used to drop rail on the HS2 trackbed. Where appropriate scrap rail will be reloaded to these wagons and returned to Network Rail for disposal or reuse. The Track Renewal Train (TRT) does not form part of this section (see sleepers below). The following requirements are identified for handling rail: • The minimum rail stabling siding length is 400m. • One line will be provided for stabling rail wagons (LWR sets or individual wagons).

A1.5 Spoil

Spoil ( used bal last) will b e br ought f rom pos session s ite t o t he I MD, a nd h anded o n t o Network Rail for disposal at an LDC. Rolling Stock would be owned by a 3rd party. Spoil will not constitute hazardous waste. No spoil will be unloaded or handled at the IMD The following requirements are identified for handling rail: • The minimum ballast stabling siding length is 400m. At least one siding must be 775 metres in length to allow for storage of an HOBC.(see section A1.4 ‘ballast’ above). • the number of spoil wagon stabling sidings provided must be equal to the maximum number of s poil t rains p lanned t o be s upplied t o a ll s ites on HS2 on one w orking night, plus 50% for contingency.

A1.6 Sleepers

Sleepers specified on HS2 will be monoblock or twin block concrete bearers with a maximum w idth of 2, 500 m m. S leepers w ill be s upplied f rom t he N ational R ail ne twork, either on 20 metre wagons (Salmons) or as part of the Track Renewal Train (TRT), where scrap sleepers are recovered from the trackbed in a possession they will return to the IMD on the wagons and will be sent on to a Network Rail LDC for recycling. Sleepers will not be stored on site at the IMD. The following requirements are identified for handling sleepers:

Page A3

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

• The minimum sleeper stabling siding length is 400m. • At least one siding must be 775 metres in length to allow for storage of the Track Renewal Train (TRT). • The TRT will be serviced and restocked at another site and not at the IMD.

A1.7 Switches & Crossings (S&C)

It is assumed that S&C will be specific to HS2 and will not be comparable to Network Rail units. C omponents ( switches, c rossings, be arers, p oint m otors, s tock r ails et c.) w ill be stored at the IMD. The IMD will also act as an initial build up area for new S&C units, and transportation to site may be carried out by rail (using GC gauge sleeper carriers along the pattern of similar units being introduced by Network Rail. The following requirements are identified for handling S&C: • New build up area required for S& C units – 150m x 20m. • At least one dead ended siding required with a usable length of at least 200 metres, and access by crane or forklift from both sides of the track. • build up area to have rail access for loading possession wagons. • build up area to have road access for material deliveries. • Component stock area required. • stock area to have rail access for loading possession wagons. • Stock area to have road access for material deliveries. • S&C handling to be by overhead crane (2 heads).

A1.8 OLE

It i s as sumed t hat O LE m aterials will b e s pecific t o HS2 and will n ot b e c omparable t o Network Rail equipment. Components (masts, insulators, registration arms, droppers, catenary wire, c ontact wire etc.) will be s tored at the IMD. T ransportation to s ite may b e carried out by rail (using a specific wiring train) on rail or road/rail equipment, or by road. The following requirements are identified for handling OLE materials: • Component stock area required. • stock area to have rail access for loading possession wagons. • Stock area to have road access for material deliveries. • stock area to have road access for road or road/rail vehicles. • At least one dead ended siding required with a usable length of at least 200 metres, and access by crane or forklift from both sides of the track. • handling to be by forklift truck.

A1.9 Miscellaneous

In addition to the above items, the IMD will also stock standard components for the following systems:

• Track drainage.

• Cable troughing.

• Consumables for track treatment such as de icing fluid, sandite etc.

Page A4 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

A1.10 Fuelling and servicing

On track plant and rescue locomotives will require fuelling, servicing and light maintenance facilities. It is assumed that heavy maintenance (including tyre turning) will be undertaken elsewhere, but i t i s possible t hat G C gauge equipment will not be a ble t o ac cess ot her depots off the network, and road movement may have to be considered. The following requirements are identified for fuelling and servicing:

• Fuelling facilities for two locomotives or on track vehicles at a time.

• Fuel storage tanks of at least 100,000 litres capacity.

• Full fuel spill recovery facilities to be provided.

• Gas oil to be delivered by road.

• Fuelling siding to be double ended and at least 100 metres length.

• servicing shed to be provided with:

o Single road. o Covered shed with lighting, heating and closable end doors.

o Fitted with fume extraction equipment.

o Provided with under floor pit. A1.11 Crippled wagon facilities

The IMD will be provided with a separate siding where crippled or defective wagons can be repaired and returned to use or moved off site. The following requirements are identified for cripple facilities:

• One dead e nded s iding of at l east 10 0 m etres l ength with t he m eans t o isolate t he points to prevent unauthorised shunt moves into the siding.

• Lighting.

• Under floor inspection pit.

• Road access f or a heav y lift ( 45 t onnes) c rane or l ow l oader t o r emove wagons f rom site.

• Full concrete apron capable of 25 tonne point loads for wagon jacks.

A2 General Requirements The following requirements have been identified for the IMD:

A2.1 General

• The IMD will be located approximately m idway along the HS2 route with the objective that engineering pos session t rains c an r each a ny worksite al ong t he r oute within o ne hour (assuming 100 kph running).

• The I MD will be op erational and ac cessible by r ail at a ll t imes. C apable of 2 4hours operation 7 days per week.

• The site will be lit throughout, but mindful of avoiding energy waste and light pollution to the vicinity of the area.

Page A5

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

• The m ajority of m aterials will arrive b y r ail, with access road being used o nly for light equipment or as a last resort.

• The site shall be made available from an early stage, and it can be considered for use as a construction site/depot for HS2 during construction stage.

• The site will be practically level throughout.

A2.2 Rail

• A connection will be provided onto the classic network, so that trains can access/ egress the maintenance depot without having to go onto the HS network.

• Where possible the IMD should be capable of direct access from both directions of the neighbouring National Rail route.

• The IMD must be capable of providing direct access to HS2 in both directions.

• Speed - minimum 25 mph c onnections f rom E ast-West R ailway m ainline t o at least 1 Reception Line. Other connections can be low speed (nominal 5 mph).

• Minimum curve radius for connecting tracks will be R=400m, for sidings will be R=200m. Sidings to be as straight as possible.

• All track to be specified for RA10 loads.

• All IMD lines, including Reception Sidings and link lines connecting the IMD with HS2, will be cleared to GC gauge.

• The maximum length trains that will be handled at the IMD and onto and off HS2 will be 750 metres.

• Shunting necks will be provided to allow repositioning of 750m trains without occupying the main running-line.

• The depot reception lines and all running loops shall be electrified at 25kV AC (and be capable of local isolation), all other lines within the depot shall not be electrified.

• There should be a minimum of 6m between the running edge of the main lines, and any depot facilities.

• Provision will be made for stabling one or more diesel “Thunderbird” rescue / recovery locomotives. T hese l ocos w ould a lso work engi neering t rains on HS2 ( as t hey w ill be fitted with all the necessary cab signalling, whereas locomotives arriving at the depot off the classic network will probably not be so equipped).

• Track spacing within depot layout will be based on 5m running edge to running edge to permit safe staff access to all tracks.

• The IMD will be signalled on Network Rail standard principles to allow access by non HS2 locomotives and trains.

• A num ber of s idings s hall be pr ovided i mmediately adj acent t o t he H S l ine as an emergency recess facility in the event of failures, in addition to provide a recess / run round facility for engineering trains.

• HS2 s hall not pr event the i ntroduction of a f ull r ange of s ervices o n t he A ylesbury – Claydon and Oxford – Bletchley routes, as proposed by the East West Rail Consortium.

A2.3 Depot

• The IMD will be securely fenced on all sides (with lockable gates at the rail entrances interlocked with depot signalling).

Page A6 Ove Arup & Partners Ltd

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

• Road access will be provided.

• Depot facilities shall include the following:

o Office accommodation. o Shower block and mess room for maintenance staff. o Stores. o First aid room and facilities. o Car parking. o Separate workshops for electrical plant & mechanical equipment. o Gantry crane accessing road rail. o Storage areas. o Access road direct from the depot to the HS2 trackside. o Helicopter landing pad. o Depot to be provided with a backup power supply.

Page A7

Appendix B Drawings

High Speed Two (HS2) High Speed 2 Infrastructure Maintenance Depot (IMD)

B1 General Site Layout Concept Plans

Drawing Numbers: HS2-ARP-07-DR-RW-00007 HS2-ARP-07-DR-RW-00008 HS2-ARP-07-DR-RW-00009 HS2-ARP-07-DR-RW-00010 HS2-ARP-07-DR-RW-00011

Page B1

A1 A B C D E F G H I J K L M N O P

m dgn

.4 . 4 8 00011 Key Proposed WRG Depot Schematic - W R -

R N D

Turnouts - 40kph (25mph) - 07 1 - P R

HS2 Rail (Route 3) A - nd o 2 P m S .1

4 H 8 EWR t\ po e D

d n ce o

P n a n e

D t ra in n i a M \ d e

on t P Standage 400m ou

D R ra T in _ o 100m 100m f C _o e n la i y L 2 don 07_ \

To Aylesbury s ng i w a r D 0_ Dra \ in s ng i w

To Birmingham a To London r D

03 - 4 \ a t a D

t ec j o r P

l

3 a n r e

t H n

I R

Dr

a 4 m

in \

2

2 .

00 1 -

D rain 209742

m \ .6 5 8 209000 :\

T J r ac nd k o P

k c a r T Drain 4 in Dra Access Road (Double lane)

s

d

n

on i d P a

r oo d

D o W o

W T r nd a o d c n d k p o on oy p P y ec o D ec D Total 1 no. of Rail Mounted Gantry Crane

Access Road (Single lane)

H

R

5 Proposed WRG Calvert Terminal m

22 . A 1

t New bridge over railway s a < To Claydon M To Aylesbury > Connects to East - West Rail 100.000

8

100.000 5 15 157 .7 m 5 P P P 7 . .2 M M M 1 P P .5 9 S M P M Ward Bdy P S Ward Bdy

h 400.000 Track ac b l

aze 6 H am 12 A B ingh C

irm T

B H

o R T To London >

17

m d

2 m W

< 2 n

r a a

. .5 r 1 d e B t o dy S P

2 90 H D HS lt e B

e f R b h W k u ac S Tr

m S

l

22 E . 1

1 BR

AC 1 K x LE Y o LAN B W E

F

r

e

ace r tt r e 7

ED e L

& W 6

ard Bdy T 11 03 1 m 7 r . e 8 8 t n Track k r r W

F e e 13 ac v

W r l 97 T a

C 1

2

E S

6

O 19 18

7 6 L

C 24

e 7

1

id S s N 22 d

e A 3 d k C 1 n

a

S 95 u on L

U n o P

T o k 1

ac r

Tr 2 ili G 4 v

1 BR 93 a m I C P s .0 KH ILL t W 85 AY r

12 6 o

2 n p

2 o 1 10

li S d 0 i

1 n 14 v a u P o 5 r s G t 6 d f 1 7 r n s e 58

D 7 o u t p

5 4 o r 11 k

2 S o

r c 12 p a

e 21 G

S r d T 4 v 19

n 8 r o P

10 e 22 8

OAD s 83 14 R

e r m 16 ANDY 2 0 S 5 e . R 5 r

t 7 SE 8 LO 1 S C e

a INDLE t R 28 B s a 8 e W t d W

12 r 81 r n u o u 1 p o t 14 S a r Calvert 7

40 G AY 7 N E

W OS CL

S

3 ER S H

8 AT

D E

16 H 20

L O a t 10

W S

S

2 T

1 O ub

S C 6

l E

24 d p 1 Proposed WRG Depot Cross-Section 5 n m r o u e SE 14 P P E LO t 14 S C O E 1 a L 2

C 1 W 79 ON S T S IC r T S e 12 U AND R S t a m W in 2 a . r D 85 75 1 7 Gantry Crane

d n

ou

r

n 38 i r

yg e a 7 a t

l r

a 9 P D W

44

4 3

4.5m 10m 10m 4.5m 4m 5m 25m 5m

20 0

3 Fence

4 3 Fence

7

6

n i

d a r

on D P n

ll ee

61 a r H G 48

y t r it e n v u l a

mm C n

o i

C a r

B D L

3 HS2 2 Access Roads East - West Rail WRG Depot Sidings

10 23 E

S (Single Lane)

O

L C 2

2

N

L I

2

K 0 Section A-A

m 19

Y 18

Reproduced by.5 permission of the Ordnance Survey on behalf of Her Majesty's Stationery Office © Crown A

8

W

8 15

E

5 S

47

copyright and database right 2009. All rights reserved. Ordnance Survey Licence number 0100049190. S

4

D

O L

8 L

O

C

W

S

N

T L

I

O K Key C Client Job Title Drawing Title High Speed 2 Route 3 HS2 Track (Route 3) 2.0 09/07/10 HW CL PH Feasibility Study Infrastructure Maintenance Depot EWR For Approval Waste Recycling Group Depot

Drawing Status Job No Access Roads 1.0 22/06/10 HW RD PH The Arup Campus, Blythe Gate, Blythe Valley Park Solihull, West Midlands B90 8AE

Scale at A1 T +44(0)121 213 3000 F +44(0)121 213 3001 For Approval 209742-00 For Co-ordination 1:2500 www.arup.com Drawing No Issue Discipline Issue Date By Chkd Appd Rail HS2-ARP-07-DR-RW-00011 2.0

Do not scale © Arup

A0 A B C D E F G H I J K L M N O P Q R S T U V W dgn .

00010 - W N R - R D - 07 1 - P R A - 2 S H t\ po e D

ce n a n e t n i a M \ e t ou R _ f _o e n i 2 L 07_ \ s ng i w a r D 0_ \ s ng i w a r D

03 - 4 \ a t a D

t ec j o r P

3 l a n r e t n I

4 \ 00 - 209742 \ 209000 :\ J

4 06

05

04

5 03

H

6

07

08

7 01

02

8

9

10

200

. 00

0

11 09

10

12 m a ngh i Concept Depot Schematic

m e r i g B a

o m nd T a t S 800

13

Infrastructure Maintenance Depot

14

To Oxford To Bletchley Standage 775m Standage 800m

Key

Depot Tracks (25kv OLE) Waste Depot Depot Tracks

Turnouts - 80kph (50mph)

15 Turnouts - 40kph (25mph)

Route 3 Tracks

Network Rail Tracks ondon L

Reproduced by permission of the Ordnance Survey on behalf of Her Majesty’s Stationery Office ' Crown o

copyright and database right 2009. All rights reserved. Ordnance Survey Licence number 0100049190. T

Client Job Title Drawing Title

High Speed 2 Route 3 Feasibility Study Infrastructure Maintenance Depot Interactive Map

Draft & Confidential The Arup Campus, Blythe Gate, Blythe Valley Park Drawing Status Job No 01 16/06/10 HW CL PH Solihull, West Midlands B90 8AE Scale at A0 T +44(0)121 213 3000 F +44(0)121 213 3001 For Information 209742-00 For Information 1:5000 www.arup.com Drawing No Issue Discipline Issue Date By Chkd Appd Rail HS2-ARP-07-DR-RW-00010

Do not scale ' Arup

A1 A B C D E F G H I J K L M N O P

dgn . N 00009 - W R - R D - 07 1 - P R A - 2 S H t\ po e D

ce n a n e t n i a M \ e t ou R _ f _o e n i 2 L 07_ \ s ng i w a r D 0_ \ s ng i w a r D

03 - 4 \ a t a D

t ec j o r P

l

3 a n r e t n I

4 \ 00 - 209742 \ 209000 :\ J

4 s x ing ed Sid Sh pot t De Depo 4 e Lin sity Var

2 s x ding t Si Depo t Shun 30m

5

t Shun 30m

e Lin sity Var

6

R ou

te 7 3

8

To Milton Keynes Depot Schematic

Key

Junction / depot Tracks 9 m Turnouts - 40kph 400

s Turnouts - 80pkh ng i

d Route 3 Tracks i S m Network Rail Tracks 775

ng i d i S

10 Siding 1200m

To London

Reproduced by permission of the Ordnance Survey on behalf of Her Majesty's Stationery Office © Crown To Birmingham copyright and database right 2009. All rights reserved. Ordnance Survey Licence number 0100049190. To Oxford

Client Job Title Drawing Title Rail Features Legend High Speed 2 Route 3 Junction/Depot Tracks 2.0 09/07/10 HW CL PH Feasibility Study Infrastructure Maintenance Depot For Approval HS2 Track (Route 3) Initial Depot Layout

Drawing Status Job No EWR 1.0 11/06/10 HW CL PH The Arup Campus, Blythe Gate, Blythe Valley Park Solihull, West Midlands B90 8AE

Scale at A1 T +44(0)121 213 3000 F +44(0)121 213 3001 For Approval 209742-00 For Comment 1:5000 www.arup.com Drawing No Issue Discipline Issue Date By Chkd Appd Rail HS2-ARP-07-DR-RW-00009 2.0

Do not scale © Arup

G

R E T E E E R S

A B C D E F G H I J N T t K K L M N O P S

A1 15 C

W C 2

7 Pond T TCB 21 e O 8 O S g

E Sub 16 D S a 40

O W r 4 AN

52 a a T El 9 14

AD 46 DH 12

20 D Sta ic 14 4 4 1 H P 1

a V 3 O

E Sub 48 L 12

P 6 M 15

E 3 E 5 West End L 7 P H

A Sta T E

Oakfield Honey Farm A D AY 1 W C M 20

84.7m 4 DO O dgn

E 6 L

AD 3 Pond

52 C 1 .

E 5 K M 22

b S m 5 3

L 3 1 49 2 DHO 8 . D 2 C

N 6 N

C

r E 2 87 8 A

G H 1 4

a a 4 H 5

Pond A A 108 S 3 a V 16 i 38 7 R 5 52 I

n 8 LL A Y 6

Tel 3 I 9 8

C O 15 81 R

C 5 L d LE Y I l 18 h

T N O t 39 E A

S V a M YS Ex 6 P A E K

H O E 1 y PLEL P 3 2 W 10 e NGA C I r O Pond R R E

N O h I L e 6 O 5 48 S S T T Firethorn 53 O F U Y k R

The O

S I a

1 EL L 4

N 3

E 5 B GH Cottage 2 I 3 1

R Bungalow C 2 3 D 3 00008 D O 42 N WHITES CLOSE AD

C -

W 3 6

2

2 11 Pond 2 L H 55 2

I 4 7

t 6 27

T 5 N 4

1 4 5

4 8 f I

5 E 4 0 0 GH 5 F S o 41 O

S 56 0 1 R H r C P Rookery Farm

1 T G

) L E a W 1 c Jasmine Cottage

2 I 38 I Posts C t

m C C O O N N 2 L h 2 y S GA 4 A O u L F S ( o r e E E (u (Kennels) O 9 I t i n LE S m h West End S C EL e T )

1 7 e 4 r W D

3 L 4 t 70

t 4 E s 1 l o 4 A R

a 4 O s Foxgloves

D o a 1 MY A

P l h y 1 2 S 5 C I g T a C O

4 -

10 E HA

s 3 e w 4 1 y d 5 n f LB R

3 s l Ivy E

d n 9 3 r a 59 a 2 L

B l o H S 7

84.1m 9 1 lk 9 c e igh Cottage M 65

J 4 d R

3 2

1 Clematis El E

a A d e A 12 9 i 1 d a F 2 M c L r 47 9 s H

y 2 l L

a E W b il Cottage 46 Sub

S 3 9 s

O s h 9 O M 8 1 L e 4 a H n W C d 2 i g NG H O D s 3 C i Library P 9 p I Sta U

ND m 44 a 0 a HA H 4 L 7 E t p H 6 N

& r l i e K E -

T C I R ND T 9

a e P l 2

S LL 3 A

E o e L e C A

F E 5 2 73 S W s 3 D 4 m d 5 E t ON R U S A E nd a o t o 0 77 N D t 19 S

H o 2 B T

d a 19 nu E

r n f O 1 0

3 g 2 t R E 83.0m 3 3

a F L

2

6 s S 5

e 2 07

3

e 3

t a e C

i s 0 34 3 n s h s 61

r 7 B

2 46a -

e 3 5 C

2 3

m 6 3 2

17 3 W 5 Y

2

4 6

8 d E

2 dhou

2

15 1

6 o o

1 6

o N

1 P 1 o w A l N

W 3 1

3 Pump

1 e I C 5 h

Three Bridge 36 2 1 Vicarage

6 P 3 2 C

n V 4 Garage h 11 i 4 V 44

S R a u 2 I I 38 C Mill 2 C C V r r 28 HU 3 T

52 5 A 2 I

2 2 E D 84.7m c 2 8 9

O R A Depot 0 106.1m W 4 RC

50 1 h T 9 R AG 0 2 1 E 1

E - Y 8 R 7 2 Surgery H TT T E

SS 0

54 E A 1 1 0 3

W 3 H 18 R 12 2 a 5 I

S O C 2 54 ES 2 7 4b 7 H A L Downe

5 L 1 32 22 16 8 2 15 G D O A Pond

R 2 4 S

14 4 3

ND S 4 6 a

Hog Bridge O 4 14 E 5 8

2 V 48 60 2 81.1m 81.7m 6 6 24

a E 4 18 1 8

5

1 6 1 13 H

1 37 2 2 14

FB 6 10 3 12

80.6m Q t\

T U 7 E 85.7m EN

Briarhill h 2 1 C

PH A P

i T 7 H

s 5 3 E

a

16 a 5 R

l E 3 IN

t 39 l l c E y 6 ROA t

l ib S D e h

po 3a S u 3 d b

o S 3 (

ADD Police t b w 2 101.4m u

a The Phoenix 109.5m e

5 5

n 5

1 m

13 Station 5 10 I 1 ) F 12 (PH) W S o D i O u l M l N 2

r o

u PO

4

Pond w 5 14 16 1 l m b d R G a e e O e a Church End Camp Barn rr n A r b e D FB t ce l y 109.1m

e S 1

l s h

il n

o 2 M 0 18 a

Nightingale

3 1 6 E N n

LA 7 View Pond Weir E Willow Farm G e 1 RA T 100.3m t

FB CA Manor Farm

r I 7 Earthwork

e V a Sluice 9 House 30

P n a e t d URUS i

TA CL o b 1 u p r y e Pond s a c Pond

B Ra

r 17 o ill 6 95.3m o M 40 M k Manor Farm Seven Steeple \

e Stars Cottage 87.8m 27

Pond 52 t 8 29 5

83.9m

1 107.6m 2

Claydon ou 4 6 8 6 1 St Michael's R n C

i Little Rising Church

a O

4 _

r 1 B 7

B D f CS C E O T R T Camp Close

O S

N _o El Sub Sta A M

T O 1 I U e O

89.6m N

4 N 3 T

n 4 5 P i

1 L 1 A

C L E 11 Pond 2 D e

f

R E

07_

D

6 \

L

A N

s

D

C Allotment Gardens

L O

ng

1 S

4 i

E 2 P a t h

w (u m ) a r 103.7m D

Pond

Cattle Grid 86.9m 0_

86.9m \ 106.1m s Pond 85.6m 84.2m

um) ng ath (

P i 83.1m 107.1m 83.5m w 83.8m Lake Farm 85.3m a

Pond Elm Tree Farm r Silo D Stone Court Farm

)

m 104.2m

u

(

FB E 03 D h - t

& a 4 85.2m P W \ a r

83.0m a d D

t r B

a d Pond

i a y n )

m

u D (

h 98.1m t t

a

P ec j Pond 95.5m o r Track Redland Bridge es ag

t P ot C

y ilwa

Ra l 1

3 a

Pear Tree House 6 n r e t Pond n I

83.6m 90.9m 4 \ LB Level Crossing 00 - 82.6m Pond FB Path (um) 85.6m

90.7m H 1 R

.2 s m 2 ing 2 ) d m i S .2 m nd 1 R u ( ou H R

un ) 209742 h R LE O 88.2m \ t Kv a 5 (2 H P R

m Pond 2 .2 1

87.3m 209000 :\ J Pond

n i a r MP .5 D Pond 91.9m

Pond

H R

m

.22 1 Pond

85.4m

4 Pond

D is m a n t le d MP .75

R P a a i lw t a y h

( u

m

)

Drain

H R

m

.22 86.0m 1 ng i ) ist SP 89.1m 85.4m Ex m n u tai ( e on R ti P a h t a S t t ub a S h P

( u

m rk ) D a P Pond r ar

a C

i

n

Poors' Piece

POR s TWAY ing R id OAD S ling 87.4m 1 b . ta Pond 2 S 2 en El Sub Sta Pond r m Op te e Poors' Piece op R tiv lic d H o He Pa com ing e Lo and tiv L istra 89.0m min ding Pond Ad uil H ce B Offi 88.9m Portway Farm

1

. 2

2 MP.25

m

5 R

H

S Pond ING n nce ID ai ntra S M t E LING po AB D De ST r ng) N a i E i c P n es Fen f O ran ty o H C ri m R ry u Pond t ec 775 m se Gan S . x igh no 22 ou ed H 6 . e H t ry ( tal 1 at Moun a To tation G ail ound S f R B SP Pond Sub . o Site d 2 no Roa tal ss To Ponds ce cce Pond an A 84.6m ten MP ain Pond t M ing Ligh uild ce B Offi ark ar P C Pond shop D rk r o a W i n 88.7m Pond ge tora S 85.5m

Rosehill Farm SP D

e SP

f te ou Pond 2 R HS e t otiv epo 86.6mom e D Ponds oc anc L ten ain rea M A Blackmoorhill n 1 t w . oin o 2 P y-d 2 ng La m elli Fu and R age H or The Old Brick Yard St (disused)

nt Shepherd's ) Pla m 6 l Furze Farm u

Fue (

Pond h

t a

s P ture uc SP Str Ponds ng Ponds ighti tal L or H f P R . o no m MP 13 2 15 2 al . ot 1 ion T ers g Div idin ad S Ro bling 92.8m Sta P gon a a Pond t W h d le (u ipp tion m Cr ng ta ) isti S Footbridge Ex cing tain edu Re re R ssu Pre

P

a

t

h

(

u

m

) Pond

MP.25 ay idge ailw Br R Pond ew isting Ponds N Ex ver O Pond

H 89.6m R E D m 2 .2 & 1

W

a

r

d D d) i se s su B (di m y d a wa y ail n R tl FF e d Pond

R a 7 il w a MP.5 y

SP

86.4m

Pond

Pond

Water

Pond m Pond a

P

a

t h f De (

u m Nature Reserve ) Pond ngh i Concept Depot Schematic

m e r i g B D a

e

90.6m f o m nd T a t

H R S 800

m .22 Pond 1

) D m e u f ( 8 Grebe Lake h

t

84.4m a

P

Water

85.6m Pond Calvert Cottages

Club

Grebe Lake House 5 f 84.1m e

D Infrastructure Maintenance Depot 90.1m 1

91.9m

SP 90.7m 92.3m

88.2m 88.2m

1

.

2 88.5m 2

m

R

H

1

.

22

m

R

H

MP 157

E D

&

D W 1.22m RH Grebe Lake r a a r i Hall Grebe Lake n d 1

. 22 B E 85.6m D d B m dy y

R 9 H Playing Field

Def Pond

T To Oxford To Bletchley 89.6m D

r

r

ac

a ED B dy i n Nature Reserve k Standage 775m Def Standage 800m 88.5m Water

90.6m Granary Cottage

Pond Key 87.7m

D Pond Farm

r

a

i n The Old Dairy Hazelbach 91.7m Ponds 88.2m Waste Depot Depot Tracks (25kv OLE) 6

4 H 3 C R hes 2 h 1 Co ire tt C a h m

ge es T SC s hir

HO Co e r OL tt 1 22

H ag ac ILL es . 1 Depot Tracks

Shelter k

Werner Terrace 1 100 PO 2 90.5m 8 91.3m ox TCB B er Allotment LB tt SC Le W . HOO F 000 D Gardens L Lakeside 88.7m r HIL L a

H i 85.0m 1 R n

88.5m FW Turnouts - 80kph (50mph)

m 7 2 2 W 1.

a 85.0m 13

Allotment Gardens r 19 d

D 1

e

B f 10 85.2m dy Turnouts - 40kph (25mph)

ack Tr B 1 7 R MP.25 A

C H

K Mast R LE

Calvert

m Pond Y

2 HS2 Track (Route 3)

L 2

Pond .

AN 1 6 Earthworks T r E ac n k i a

r

D EWR

1 1 Pond ondon L

103

Reproduced by permission of the Ordnance Survey on behalf of Her Majesty's Stationery Office © Crown Pond Pond Shrubs Wood o

El Sub Sta

copyright and database right 2009. All rights reserved. Ordnance Survey Licence number 0100049190. T 18 21

Rail Features Legend Client Job Title Drawing Title High Speed 2 Route 3 Depot Tracks (25kv OLE) 2.0 09/07/10 HW CL PH Feasibility Study Infrastructure Maintenance Depot

Depot Tracks For Approval Overall Depot Concept Plan Layout

Drawing Status Job No HS2 Track (Route 3) 1.0 11/06/10 HW CL PH The Arup Campus, Blythe Gate, Blythe Valley Park Solihull, West Midlands B90 8AE

Scale at A1 T +44(0)121 213 3000 F +44(0)121 213 3001 For Approval 209742-00 For Comment 1:5000 EWR www.arup.com Drawing No Issue Discipline Access Roads Issue Date By Chkd Appd Rail HS2-ARP-07-DR-RW-00008 2.0

Do not scale © Arup

A0 A B C D E F G H I J K L M N O P Q R S T U V W dgn .

00007 - N W R - R D - 07 1 - P R A - 2 S H t\ po e D

ce n a n e t n i a M \ e t ou R _ f _o e n i

2 L 07_ \ s ng i w a r D 0_ \ B s ng ir i m w a r

i D ngh 03 - 4 \

a a t

m a D

t ec j o r P

3 l a n r e t n I

4 \ 00 - 209742 \ 209000 :\ J P la n C 4

A Plan

B Plan

5

H

89 .1m N

Helicopter Car Park Landing Pad

1 . 22 H

m 6 D R ra H in

89 .0m

Administrative Office Building

1

. Sub Station 22 Po nd

m

R

H

Light Maintenance Office Building Main Depot Entrance

D r Car Park a

i 7 n Gate House

MP

Workshop Access Road

HS2 Route Storage 88 .7m Total 2 no. of Rail Mounted Gantry Cranes

Site Boundary (High Security Fencing) 8 Fuelling Point

D 8 e 6 f Locomotive.6m Maintenance Depot

400 Total 6 no. x 775m of OPEN STABLING SIDINGS

. 000 Fuel Plant

Road Diversion D

r Locomotive Open Stabling Sidings

a

i n P P Storage and Lay-down Area ond la n Crippled Wagon Stabling Siding D 9

Oxford 9 2 .8m

SP

SP SP M MP P.25 MP .2 13 5

Total 15 no. of Portal Lighting Structures Plan A New Bridge Retain Existing

Pressure Reducing Station Scale 1: 2500 Over Existing Railway SP N

85 .4m 95 .5m 10 Retain Existing Sub Station

Pea Run Round Sidings r T ree

Hou (25Kv OLE) se

El Sub

St a 90 P .9 ond m

BletchleyLB L ev el Cr oss ing

SP M P . 75 MP .5 MP .25 88 .9m Pond 90 .7m 11 Poo r s' Piece

S C 8 ) Plan B 8 m .

u 2 d ( m n o

P h t a ) P N m u ( Scale 1: 2500

h Poo t d r a on s P ' P PiecePond

ond m P m .6 85

f a e D

H

R

m k c a 22 . r 1 T ngh

i Concept Depot Schematic

e m g

a e w s r e k S r i H o

R W g

n i m

a B r 22 . Chord to Depot a D 1 ond

P o

n ) m 12 i m

a nd u r (

D T h t m a 9 a P . 91 t

Dismantled Railway Dismantled Railway Track

Track S 800

d n o P ond P

w ie V

h c r u h m C r Birmingham a ld London F e 's i y F r a M

t e ing S s y ou H la P

k

c

a

r

T m k s 2 H ' . o R y m 85 e r o at .0 chg a m ur M Infrastructure Maintenance Depot r Ch h 86 c B t 22 r The . S s 1 u wthorn in h Ha a C r y D

e n o r i

g nd Berry E il

a v u a t P

b n

t i

d o w a d

e

C o

w

r a R

d e

D i ld l P ion

O e

V d L ea

r lands n Wood M o u P

a

L

GRAN n GE CLOSE lo a e v g A d e i Twyford - HS2 Runningim Loops Plan C r L

B y 's 1a a n t C o t il e oo e h e l F h a nd T e C ac d b l r o e e P e P l s m 13 G o ou H e S m e e s h Scale 1: 5000 .2 ng e ou T a om t H en 84 H r sc G re nd C o ok s 1 o y P r e B b L

T l E r F EET

a il e n lm nd M R c h a o

k AN T do T C

y s P OAD S en L R

la ind

C L ydene AY H e ck Th Be W

C RT

R PO

U

H

C Drain N

in Access Road (Double lane) Dra

s

nd

n

o i d P a o

r o d

D o W o

d W T r ac on d n k p o y ond o p P y ec o D ec D

Access Road (Single lane)

Proposed WRG Calvert Terminal To Oxford To Bletchley

t New bridge over railway s a M Standage 775m 100.000 100.000 Standage 800m

58 5 1 14 157 7 . m P P P 7 . .25 M M M 1 P P .5 9 S M P M Ward Bdy P S Ward Bdy

h 400.000 Track ac b l e Key z a H 12

B C

T

H

R

17

m d

2 m W

2 r a a n . 5 Aylesbury

. r 1 d e B t o t dy S P

l 90 H D e B Depot Tracks (25kv OLE) e f R h W k c Waste Depot ub a S Tr

m S

l

22 E . 1

1 BR

AC 1 K x LE Y o L AN B W E

F

e r e ac t Depot Tracks r t

Claydon e 7 r

ED e L

& W 6

ard Bdy T 11 03 1 m 7 r . e 88 t n Track k r r W c

F e e 13 a v

W r l 97 T a

C 1

2 Turnouts - 80kph (50mph)

E S

8 66

O 19 1 L

C 24

e 7 1

id S Refer to DRG HS2-ARP-07-DR-RW-00011, s 22 d

e AN 3 d C Plan D k 1 n Calvert- WRG Relocated Terminal n

a

S 95 o L

U n ou P

T o k 1 i r

ac l 2 Issue 2.0 Turnouts - 40kph (25mph) Tr i G v

14 BR 93 a m I C P s .0 KH I t 5 L Scale 1: 5000 L LW 8 AY r

12 6 o

2 n p o

12 10 S 0 ili

1 ond 15 14 v a P ound r HS2 Track (Route 3) G

s t r

po S o n EWR ondon L Reproduced by permission of the Ordnance Survey on behalf of Her Majesty's Stationery Office © Crown o

copyright and database right 2009. All rights reserved. Ordnance Survey Licence number 0100049190. T Rail Features Legend Environmental Features Legend Special Areas of Conservation National Parks 3.0 09/07/10 HW CL PH Client Job Title Drawing Title Depot Tracks (25kv OLE) For Approval High Speed 2 Route 3 Listed buildings Special Protection Areas Flood Risk Zones

Depot Tracks Feasibility Study Infrastructure Maintenance Depot 2.0 01/07/10 HW CL PH Area of Outstanding Natural Beauty National Nature Reserves Depot Concept Plan HS2 Track (Route 3) For Co-ordination Draft & Confidential Drawing Status Job No The Arup Campus, Blythe Gate, Blythe Valley Park RAMSAR Parks and Gardens EWR 1.0 11/06/10 HW RD PH Solihull, West Midlands B90 8AE Scale at A0 T +44(0)121 213 3000 F +44(0)121 213 3001 For Approval 209742-00 1:10000 Scheduled Ancient Monuments For Co-ordination www.arup.com World Heritage Site Access Roads Drawing No Issue Discipline Issue Date By Chkd Appd Rail HS2-ARP-07-DR-RW-00007 3.0 SSSI Historical Battlefields

Do not scale © Arup