COUNTY CAPITAL WORKS COMPLETED, ONGOING AND STALLED PROJECTS NO PROJECT POPULATION SCOPE OF WORKS COST/ REMARKS/ NAME TO BE SERVED FINANCIER STATUS (000,000) – COMPLETED PROJECTS

1. Masinga Kitui 180,000  Intake works and water treatment plant of 9,000m3/day 2,200 ADB Completed and Water supply and (Clean water)  105 Km raising main and distribution system operational sanitation project  2 No reinforced tanks of 3000m3 and 2 No reinforced tanks of 30,000 1500m3 (Sewerage System)  Kitui town sewerage system of 27 km and stabilization ponds of 2500m3/day 2. Town & 22,800 Mutitu Town 77 KIDP Completed and Thua – Kinaakoni  Infiltration gallery operational Water supply  RC sub surface dam  50M3 sump project  Pump house  6.2Km raising main  500M3 RC tank  Grade 9 House  Distribution lines and 7No. water kiosk Thua Kinakoni  Infiltration Gallery  100M3 RC sump tank  5.5Km raising main  Rehabilitation of 4No. 50M3 tanks and 5No. Water kiosks.

Page 1 of 16

NO PROJECT POPULATION SCOPE OF WORKS COST/ REMARKS/ NAME TO BE SERVED FINANCIER STATUS (000,000) 3. Ikanga – 25000  Pump house 120- KIDP Completed and water supply  Installation of Genset operational project  30KM rising main 200mm Diameter  Water Service Providers Office

ONGOING & PLANNED CAPITAL PROJECTS

NO PROJECT POPULATION SCOPE OF WORKS COST/ REMARKS/ NAME TO BE SERVED FINANCIER STATUS (000,000) KITUI COUNTY – Ongoing & Planned Projects

1 Migwani Water 15,000  Drilling of 2 No. Boreholes 100 Project is 99% Supply Project (clean water)  Equipping of 1 No. Borehole complete  Laying of a 23 Km pipeline KIDDP  Construction of 2 No. masonry tank  Production Capacity 992m3/d 2 Last mile 40,000  Extension of sewerage system and individual connections for Kitui 550 ADB Procurement of connectivity (Water & Sewerage town residents with sewer lines. consultancy Extension of Kitui systems)  Water supply pipeline extensions services ongoing town Sewerage system project 3 Kiambere 56,000  Intake works & T. works of 5,600m3/day 1,450 Project ongoing and water supply and (clean water)  Construction of 18Km rising main at 3.6% complete sanitation project  Construction of 86 Km distribution line, GoK and 20,000  Construction of RC tanks- 13No. ranging from 800M3 to, 150M3 and Italian 3 (sewer system) steel elevated tank of 100M Cooperatio  Construction of Mwingi town sewerage system of 2.400m3/day n

Page 2 of 16

NO PROJECT POPULATION SCOPE OF WORKS COST/ REMARKS/ NAME TO BE SERVED FINANCIER STATUS (000,000) 4 Kitimui Dam 75,000  Consultancy services for Technical designs, ESEA, RAP and Preparation of 110 ADF Proposal forwarded Water Supply (clean water) Tender documents for Kitimui Dam Water Supply Project. 13 to development Project partners for funding

5 Mutomo Water 80,000  Dam construction of 34m, Intake works, ,treatment works of 5,000m3/day, 1,000 ADF Proposal forwarded supply Project (Clean water) pumping units, main pipeline works of over 50km, Main distribution 14 to development pipelines of over 100km, water storage tanks and ablution blocks for Mutomo and towns partners for funding

STALLED CAPITAL PROJECTS

NO PROJECT POPULATION SCOPE OF WORKS COST/ REMARKS/ NAME TO BE SERVED FINANCIER STATUS (000,000) KITUI COUNTY – Stalled Projects

1 Umaa Dam 75,000 People  28 M high dam with storage capacity of 870,000M3 of water GOK Project is implemented by National Water Conservation & Pipeline Corporation

Page 3 of 16

SUMMARY TABLE OF ALL BOREHOLES (NEW AND REHABILITATIONS) IN KITUI COUNTY

S/NO COUNTY NO. OF COST IN KSHS. POPULATION SERVED WATER ADDED BOREHOLES IN M3/HR

1 Ongoing 17 153,237,253.05 28,500 people, 6,000 LU 98

2 Completed 103 154,021,194.00 114,104 people & 1,000 191 m3/hr LU

3 Completed and 142,604 people & 7,000 Ongoing 120 307,258,447.05 LU 288.50

Page 4 of 16

SUMMARY OF ONGOING BOREHOLES IN F/Y 2018/19

Ongoing New Boreholes for Drilling and Equipping in F/Y 2018/19 under Drought Mitigation Programme

S/ Name of Borehole County Constitue Contracted Major Activities to Expected Current Status/ Water production No Project ncy Amount in be done Beneficiaries Kshs. 1 Manyumbani B/H Kitui Kitui 4,000,000 Drilling and 2,000 people Hydro-geological survey not yet done for the Orphans Rural equipping borehole to be done. 2 Mwambiu B/H Kitui Mwingi 5,000,000 Drilling and capped 2,000 people Hydro-geological survey was done, (Nuu Special School Central borehole drilled with a discharge of for Mentally 2.5m3/hr. handicapped) 3 Kavyuvaa B/H Kitui Kitui 5,000,000 Drilling and 2,000 people Hydro-geological survey not yet done South equipping borehole to be done. 4 Kilevi B/H Kitui Kitui 1,215,360 Drilling and capping 2,000 people Hydro-geological survey not yet done Rural borehole 5 Tseikuru B/H Kitui Mwingi 3,784,640 Equipping borehole 450 people mostly B/H complete and operational with a North done. the students of water output of 3m3/hr. The borehole Tseikuru Sec. School had been drilled during Phase II funding. 6 Ngomano B/H Kitui Kitui East 4,000,000 Drilling and 2,000 people Hydro-geological survey not yet done equipping borehole to be done. 7 Mutitu B/H Kitui Kitui East 3,981,381 Drilling and capped 2,000 people Hydro-geological survey was done, borehole drilled with a borehole yield of 3m3/hr. Since the safe borehole abstraction is 1.8m3/hr, it will be a point source. Sub-Total Kitui 28,000,000 14,000 people

Page 5 of 16

Ongoing Repair/Rehabilitation of Boreholes/Water Supplies in F/Y 2018/19 under Drought Mitigation Programme

S/ Name of Borehole County Constituency Allocated Major Activities to be done Expected Current Status/ Water No Project/GPS Amount in Beneficiaries production Kshs. 1. Kaumu Community Kitui Kitui East 1,200,000 Replacement of submersible pump and 10,000 Pump testing to be done Water Project/ motor, minor electrical rewiring of the people first to establish the N 9837786 control panel, replacement of some including shallow well water E 411277 at elevation sections of the leaking pipeline sections, institutions, capacity in m3/hr and 610m. upgrading of distribution pipelines, markets and there after a replacement of leaking non working government comprehensive BOQ will pipe fittings. offices. be provided. 2. Kitui Kitui West 3,000 people The borehole is currently operational with either Mutini B/H/ solar or genset. The N 9860792 800,000.00 Power supply electricity grid power to E 375213 at elevation be supplied at a distance 1,215m. of 280m. The BOQ will be provided later. Sub-Total for Kitui County 2,000,000 13,000 County

Page 6 of 16

Ongoing new borehole Projects under Priority Projects (not complete)

S/ Name of County Ward/ Funded Cost (Kshs.) Population Total Date Current Status No Project Constituency Components Served Water Started/ Productio Date n Completed

1 Kiangu Kitui Kitui South Equipping with 1,200 1.8m3/hr 5th Feb-18 Drilling works and pump Borehole solar 5,004,846.15 People and to July testing complete. Water 2,000 2018 Implementation at 80% and is Project livestock in the process of lowering the pump.

2 Mbakoni Kitui Kitui South Equipping with 1,200 7.0m3/hr 6th Feb-18 Borehole drilled and cased. Borehole genset, 8,101,445.16 People and to July Equipping commenced in April Water construction of 2,000 2018 2018. Implementation at 80%. Project a pump house livestock and electricity connection.

3 Kithuki Kitui Kitui South Equipping with 1,100 1.5m3/hr 7th Feb-18 Borehole drilled and cased. Water solar 5,130,961.74 People and to July Equipping at 80%. Supply 2,000 2018 livestock

18,237,253.05 3,500 people & 6,000 livestock

Page 7 of 16

LOT 2 – KITUI COUNTY Total of 8 boreholes and associated works of Ksh. 105m were to be done. All the 8 boreholes were drilled under World Bank Programme by Athi Water Services Board.

S/ Name of GPS Current Status No Borehole POSITION

01021’20”S 1 Nduumoni The borehole was drilled, equipped with solar power and pump. 37052'23''E

01048’45”S 2 Mutha The borehole was drilled, equipped with solar power and pump. 38025'37''E

01035’34”S 3 The borehole was drilled, equipped with solar power and pump. 38007'24''E

01016’50”S 4 Kauma The borehole was dry and an alternative site identified and another borehole yet to be drilled since 3rd quarter of F/Y 2017/18. 37059'54''E

01004’06”S Works done are drilling, test pumping, pump installation and tank installation. Water kiosk construction is at 50%. Works not yet done are 5 Kwa Masai 38003'58''E pump house construction, construction of solar panels support and pipeline works. Works done are drilling, test pumping and pump installation. Pump house construction is at 50%, construction of solar panels support is 01035’46”S 6 Kithanake complete but the control panels are not yet installed. The 24m3 steel elevated tank construction is complete and trenching of the pipeline 38011'27''E is done but the pipes have not been laid. Works done are drilling, test pumping borehole is capped. Works not yet done are pump house construction, pump installation, tank 01011’10”S 7 Kangondi installation, water kiosk construction, construction of solar panels support and pipeline works. 38000'30''E

00030’33”S Works done are drilling, test pumping borehole is capped. Works not yet done are pump house construction, pump installation, tank 8 Katse 38004'36''E installation, water kiosk construction, construction of solar panels support and pipeline works. 3 boreholes out of 8 are complete.

Page 8 of 16

SUMMARY TABLE OF COMPLETED BOREHOLES PER COUNTY

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed 1 Complete and Manyuuni Kitui Mutomo New Borehole drilling 998,580 functional

2 Tungutu Borehole drilling Kitui Tungutu New Village 2,272,400

3 Borehole drilling 998,000 Kamwiu Kitui Kyamatu New

4 Kyangwithy Borehole drilling Kyaani Kitui New a West 5,550,240

5 Kitui Borehole drilling Nzinia New 3,418,780

6 Nguni Kiuni Kitui Maluma New Borehole drilling 1,810,000

7 Kitui Borehole drilling Equipped by Kitui Ambi Mutomo New County, 3,160,000 operational

8 Kitui Borehole drilling 991,900.00 Mwambani voo New

9 Drilling borehole and Mithasyani Kitui Ngomeni New 933,001.65 1,500 Drilled dry and casing payment for drilling

Page 9 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed component paid. To be re-sited

10 Borehole drilling & Ikuyuni Kitui Maluma New equipping 6,554,000

11 Drilling and Karung'a Kitui Mwingi New equipping with 2,391,318.75 4,500 Complete (Mumbuni) genset

12 Drilling and Musuani Kitui Kyome New equipping with solar 2,255,550.40 4,500 Complete pump

13 Drilling and Mwambiu- Kitui Nuu New equipping with solar 2,569,319.00 4,500 Complete Kavuti pump. 14 Drilling, equipping Drilling Complete, 1 Masyungw Katumbi Kitui New with solar and 1no. 1,283,925.00 1,500 kiosk constructed a (Tseikuru) Kiosk and a pump house 15 Musavani - Drilling borehole and Kyenini Kitui New 933,341.65 1,500 Completed Tseikuru) capping 16 Rehabilitation of existing borehole but Complete equipped Matooni Kitui Ngomeni New scope changed to 781,830.00 1,500 by county drilling of new shallow borehole 17 Rehabilitation of Mulangoni Kitui Masungwa New 1,240,750.00 1,500 Complete existing borehole

Page 10 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed 18 Drilling, borehole Drilling and casing of development, Kitumbi Kitui Kyome New a shallow borehole, 2,063,550.00 4,500 pump construction 1 kiosk done. 19 Drilling of a deep Complete equipped Mathuma Kitui Kisovo New 388,440.00 1,500 borehole by county 20 Drilling and Drilling Complete. Iiani Kwa Kitui Kiomo New development of a 1,957,662.95 4,500 B/H equipped by Ndung'u deep borehole. County 21 Drilling and Kisovo Kitui Kisovo New development of a 1,957,662.95 4,500 complete deep borehole. 22 Ikaaie Kitui New Drilling and 4,572,178.00 450 1.75 13/7/2017 100% complete equipping with to and operational Genset pump house, 27/9/2017 water kiosk, piping, 10m3 water tank and fencing. 23 Kasunguni Kitui New Drilling and 1,555,380.00 100 1.4 10/7/2017 100% complete installation with to and operational Afridev hand pump, 31/07/201 fencing and gate. 7 24 Kyandeve Kitui New Drilling and 2,271,312.00 No 1.61 12/07/201 The project is done equipping with populatio 7 50% as the Genset pump house, n served. borehole collapsed water kiosk, piping, before pump 10m3 water tank and

Page 11 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed fencing. installation. Project not complete. 24 Maluma Kitui New Drilling and 3,967,132.00 600 2.1 1/08/2017 100% complete equipping with to and operational Genset pump house, 4/10/2017 water kiosk, piping, 10m3 water tank and fencing. 26 Mathini Kitui New Drilling and 4,250,710.00 500 2.1 24/7/2017 100% complete equipping with to and operational Genset pump house, 28/9/2017 water kiosk, piping, 10m3 water tank and fencing. 27 Museve Kitui New Drilling and quipping 7,388,225.00 1,000 17.5 12/7/2017 100% complete with Genset pump to and operational house, water kiosk, 29/9/2017 piping, 10m3 water tank and fencing. 28 Nguumo Kitui New Drilling and 4,092,901.00 500 1.4 12/7/2017 100% complete equipping with to and operational Genset pump house, 22/12/201 water kiosk, piping, 7 10m3 water tank and fencing. 29 Kikule W/P Kitui Muthesya New Borehole water 9,315,316 6,500 1.9 Operational. Loc. Yatta source system. District

Page 12 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed 30 Kwandolo w/p Kitui Mavoloni New Borehole water 11,093,388 8,303 12 complete and Loc.-Yatta source system operational District 31 Ianguni w/p Kitui Ndalani New Borehole water 10,400,717 5,330 14.4 complete and Loc- Yatta source system operational District 32 Kenyatta w/p Kitui Kinyatta New Borehole water 9,842,846 8,500 19.2 complete and Loc.- Yatta source system operational District 33 Kyatune w/p Kitui Kyatune New Borehole water 9,112,670 5,601 12 complete and Loc.- source sytem operational Mutomo District 34 Kalivu W/P Kitui Kalivu Loc.- New Borehole water 8,402.040 6,100 - The source has Mutomo source system high salinity levels District alternative source identified and funded f/y 2012/2013 35 Kiwu Kitu Kitui Mivukoni New Borehole water 6,296,434 16,209 18.4 Alternative source Watsan Loc- Kyuso project funded project 50% Project District complete and ongoing- awaiting phase 11 of the funds 36 Itoleka W/P Kitui Itoleka Loc- New Borehole water 10,169,945 9,611 12 Alternative source Kitui project funded project 75%

Page 13 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed District complete and ongoing- awaiting phase 11 of the funds 37 Thitani B/H Migwani Kitui Rehabilita Installation of pump, 3,426,760 2,000 18m3/hr 1/02/2017 Complete and Project tion draw pipes and people & - operational control panel 1,000 28/03/201 livestock 7 Units (LU) 38 Katumbi/Kinani Kitui Rehabilita Katumbi B/H project 3,528,337 - Katumbi 5.8m3/hr 1/02/2017 Complete and e B/H projects tion - Installation of B/H - 600 - operational pump. people 10m3/hr 22/03/201 with 7 Kinanie B/H project - - Kinanie Installation of genset B/H - and draw pipes. 1,000 people 39 Kaaki Mutha & Kitui Rehabilita Kaaki Mutha was 1,198,446 Vutu B/H 10m3/hr 2/03/2017 Complete and Vutu B/Hs tion rehabilitated by the will - operational Project County. benefit 3/04/2017 Vutu B/H – 700 Installation & testing people a submersible pump 40 Ilusya B/H, Kitui Rehabilita - Ilusya B/H – 2,456,700 2,500 15m3/hr 14/03/201 Complete and Vote B/H, and tion replacement of people 7 - operational Kyatune B/H genset, control panel (Ilusya 3/04/2017 Project & general wiring; B/H - Vote B/H - 1,000,

Page 14 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed replacement of Vote B/H armored 500 & underground power Kyatune cable, general B/H service of the genset, 1,000) & providing gabion protection at the borehole. - Kyatune B/H - replacement of armored underground power cable, construction of communal water point & general service of the genset, 41 Kweromo B/H Kitui in Rehabilita Installation/testing 2,795,600 2,000 10m3/hr 26/01/201 Complete but not project Mwingi tion of genset and people 7 - The operational since North submersible pump. project was on 10/04/2017 the

completed genset was stolen

on and was reported 21/02/201 at Ngomeni Police 7 and was Post on handed 13/04/2017 – OB over to the 41 13/4/2017 community on

Page 15 of 16

S/ Name of County Ward/ New or Funded Components Cost (Kshs.) Populatio Total Date Current Status No Project Constituen Rehabilit n Served Water Started/ cy ation Productio Date n Completed 06/03/201 7. 42 Tseikuru B/H Kitui New Drilling of the 1,767,543.00 Not yet B/H Pump 4/07/2017 Drilling was project borehole equipped. testing - completed Waiting . yield was 19/07/201 for Phase III funds 4m3/hr) 7 so as to equip. Kitui County 154,021,194. 114,104 191m3/hr Sub-Total 00 people & 1,000 livestock Units (LU)

Under the JICA Programme in 2017 before the Tanathi Water Services Board was formed, 57 boreholes were drilled and equipped with powered pumps, solar pumps or hand pumps then one (1) spring was developed at Nuu. This was a total of 58 water sources developed. We shall avail the report shortly together with their total cost.