The Department of Engineering announces the following road closures:

- REMINDER-- Cedar Lane Northbound will be closed for two weeks from today between West Norfolk Road and Western Freeway (VA-164). The detour is signed via West Norfolk Road and Western Freeway. Southbound traffic will not be impacted during this two-week northbound closure for emergency sewer force main work.

- Cypress Road will be closed at Willow Street on Monday, April 27th, from 9 a.m. until 3 p.m. Flaggers will direct traffic during work for Columbia Gas.

- Both eastbound lanes of Turnpike Road between Phillips Avenue and Gothic Street will be closed from 7 a.m. on Monday, April 27th, until Thursday, April 30th, at 5 p.m. Two-way traffic will be maintained during this 24-hour closure for sewer and water installation work.

- Deep Creek Boulevard will be closed between Columbus Avenue and Chicago Avenue from 7 a.m. on Monday, May 4th, until Friday, May 8th, at 5 p.m. A signed detour will be in place for this 24-hour closure during sewer connection work at Lexington Development.

For more information, please call 393-8592.

DriveERT WEEKLY LANE CLOSURE SCHEDULE From Friday, April 24 to Friday, May 1

Below is a list of significant tunnel/lane closures for the Elizabeth River Crossings (ERC) facilities. All work is dependent upon weather conditions and closure dates are subject to change. For updates, follow us on Twitter @DriveERT.

US 58 East Midtown Tunnel: Full tunnel closure in the Midtown Tunnel eastbound on Sunday, April 26 from midnight until to 2 a.m. US 58 West Midtown Tunnel: Alternating lane closures in the Midtown Tunnel westbound on Monday, April 27; Tuesday, April 28; Wednesday, April 29 and Thursday, April 30 from 8 p.m. to 5 a.m. the following morning.

I-264 East: Right lane closure on I-264 East between Frederick Blvd. and Effingham St. on Monday, April 27; Tuesday, April 28; Wednesday, April 29; Thursday, April 30 and Friday, May 1 from 9 a.m. to 3 p.m. I-264 West: Right lane closure on I-264 West between Effingham St. and Frederick Blvd. on Monday, April 27; Tuesday, April 28; Wednesday, April 29; Thursday, April 30 and Friday, May 1 from 9 a.m. to 3 p.m.

US 58 East: Alternating lane closures on US 58 East from London Blvd. to a half- mile before the Midtown Tunnel eastbound on Monday, April 27; Tuesday, April 28; Wednesday, April 29; Thursday, April 30 and Friday, May 1 from 9 a.m. to 3 p.m. US 58 West: Alternating lane closures on US 58 West from a half-mile after the Midtown Tunnel westbound to London Blvd. on Monday, April 27; Tuesday, April 28; Wednesday, April 29; Thursday, April 30 and Friday, May 1 from 9 a.m. to 3 p.m. VA 164 East: Alternating lane closures on VA 164 East from W. Norfolk Rd to London Blvd. on Monday, April 27; Tuesday, April 28; Wednesday, April 29; Thursday, April 30 and Friday, May 1 from 9 a.m. to 3 p.m. VA 164 West: Alternating lane closures on VA 164 West from London Blvd. to W. Norfolk Rd. on Monday, April 27; Tuesday, April 28; Wednesday, April 29; Thursday, April 30 and Friday, May 1 from 9 a.m. to 3 p.m.

Follow us!

The Virginia Department of Transportation (VDOT) encourages motorists to “Know Before You Go” and plan your trip with free tools:

• Download the 511 smartphone app • Visit the 511 Virginia website or dial 511 for traffic information on your phone

HAMPTON ROADS CLOSURES ON WATER CROSSINGS, INTERSTATES AND OTHER NOTABLE DETOURS For the week of April 26 - May 2

NOTE: This list covers full closures of interstates, ramps, bridges and primary roads, and lane closures at the bridge-tunnels and the Berkley, Coleman, High Rise and James River bridges.

*Scheduled closures are subject to change based on weather conditions.*

For information on the many other lane closures necessary for maintenance and construction throughout , visit 511Virginia.org, download the 511VA smartphone app, or dial 511.

Bridges & Tunnels:

Hampton Roads Bridge-Tunnel, I-64:  Alternating single-lane closures westbound on April 27-30 from 9 p.m. to 5 a.m.  Full directional closures for tide gate testing on May 3:  eastbound from 1-2:30 a.m.  westbound from 2:30-4 a.m.

Monitor-Merrimac Memorial Bridge-Tunnel, I-664:  Single-lane closures southbound on April 27-30 from 9 p.m. to 5 a.m. , Route 17:  Single-lane closure northbound May 2, from 12:30-6 a.m., with full directional stoppages estimated to last up to 45 minutes, between 2 a.m. and 5 a.m.

High Rise Bridge, I-64:  Single-lane closure westbound on April 28 from 7 p.m. to 2 a.m.

Berkley Bridge, I-264:  Alternating, mobile, single-lane closures westbound on April 28 from 10 a.m. to noon.

I-64 Widening Project, York County:  Single-lane closures on I-64 east and west from Route 199/Lightfoot exit (exit 234) to Route 199/Humelsine Parkway (exit 242) April 26-30, from 7 p.m. to 5 a.m.  Traffic shift scheduled to begin overnight starting as early as April 28, on I-64 east starting from 1 mile west of Route 199/Newman Road to the Lightfoot exit at Route 199/Newman Road (exit 234).  A consecutive, long-term lane closure under traffic signal control on Colonial Parkway at the I-64 overpass continues.  A consecutive, long-term full ramp closure on Route 143 Merrimac Trail north to I-64 west continues. Traffic will follow detour signage in place directing motorists to the Route 143 south on-ramp to I-64 west during the closure.

I-64 Southside Widening, High Rise Bridge Expansion:  Alternating, single-lane closures on I-64 in both directions between South (exit 281) and Greenbrier Parkway (exit 289):  April 27-30  I-64 westbound from 6:30 p.m. to 5 a.m.  I-64 eastbound from 7 p.m. to 5 a.m.  May 1, from 8 p.m. to 8 a.m.  May 2, from 8 p.m. to 9 a.m.  May 3, from 8 p.m. to 5 a.m.

I-64 Express Lanes:  Full closure of I-64 Express Lanes in both directions on April 27-30 from 8 p.m. to 3 a.m.

I-64, Hampton:  Full ramp closures on I-64 west April 27-30, from 10 p.m. to 5 a.m.:  Off-ramp to eastbound Armistead Avenue/LaSalle Avenue (exit 265A)  Off-ramp to westbound Armistead Avenue/LaSalle Avenue (exit 265B)

I-64/I-264 Interchange Improvements Project, Norfolk/Virginia Beach:  Double-lane closures on I-264 east from Newtown Road (exit 15) to Witchduck Road (exit 16) on April 26-30 starting as early as 7 p.m. to 5 a.m.  Single-lane closure on I-264 east from Newtown Road (exit 15) to Witchduck Road (exit 16) on April 27 through May 1 from 9 a.m. to 3 p.m.  Single-lane closure on I-264 west from Witchduck Road (exit 16) to Newtown Road (exit 15):  From April 24 at 7 p.m. to April 27 at 5 a.m.  From May 1 at 7 p.m. to May 4 at 5 a.m.  Single-lane closures on I-264 west from Witchduck Road (exit 16) to Newtown Road (exit 15) on April 27 through May 1 from 9 a.m. to 3 p.m. and 7 p.m. to 5 a.m.

I-264, Norfolk:  Full closure on I-264 east (inside set) off-ramp to I-64 west (exit 14C) on April 27-30, from 11 p.m. to 4 a.m.

Other Notable Closures:

Route 199, James City County:  Right-lane closure on Route 199 west at the College Creek bridge April 27, from 7 a.m. to 7 p.m.  Alternating, consecutive single-lane closures on Route 199 west at the College Creek bridge, starting at 7 p.m. on April 28 through 7 p.m. on May 2. Elizabeth River Tunnels (Downtown/Midtown tunnels): Go to Elizabeth River Tunnels for maintenance schedules on the Downtown Tunnel (I-264), Midtown Tunnel (U.S. 58) and MLK Expressway (Route 164).

HRBT Expansion Project: For future lane closures and project updates related to the HRBT Expansion Project, visit HRBTExpansion.org.