CENTRAL COALFIELDS LIMTED RANCHI ANNEXURE-IV DETAILS CONTRACTS/TENDERS/PURCHASES CONCLUDED DURING THE MONTH OF JULY 2011 Tender No. Item/nature Mode of Date of Type of Last dt.of Nos.of tender Nos.&Name Nos.&Name Whether Contract Name of Value of Scheduled Actual date Actual date Reasons for of work tender Publ.of Bidding receipt received of parties of parties not contract No.& Date Contractor Contract date of of start of of completion delay if any enquiry tender (Single/Two tender qualified after qualified after awarded to (Rs.lakhs) completion of work/ of Bid system) tech.evaluatio tech.evaluati Lowest supplies/ supplies work/supplie n on tender/ work s evaluation L1

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 ARGADA AREA DEPTT.MINING 1 Coal loading Open Tender 10.01.2010 Two Bid 01.02.2010 Three 1. Shri Raju 1. Sri. Babulal YES Agreement Shri Raju 218.76 22.07.2013 23.07.2010 NA Not Applicable &Transportatio through News System Gupta, -'A' Gupta, Gidi-A No.GM(A)/SO( Gupta, Gidi-'A' n Papers & CCL 2. Sri.Dhiraj M)(A)/CT/GDA/ Website Singh 10-13/29 Dt.28.08.2010 2 Coal loading Open Tender 11.12.2009 Two Bid 04.01.2010 Three 1. Shri Raju NIL YES Agreement Shri Babulal 476.16 17.10.2013 18.10.2010 NA Not Applicable &Transportatio through News System Gupta, Gidi-'A' No.GM(A)/CT/ Gupta, Gidi-'A' n Papers & CCL 2. Shri. Babulal GDC/10-13/45 Website Gupta, Gidi-A. 3. dt. 02.12.2010. Sri. Harshit Logistic Pvt Ltd, Kolkata 3 Coal loading Open Tender 19.08.2008/20. Two Bid 08.09.2008 Two 1. Shri Raju NIL YES Agreement Shri Raju 185.52 29.03.2012 30.03.2009 NA NA &Transportatio through News 08.2008 System Gupta, Gidi-'A' No.CGM(A)/CT Gupta, Gidi-'A' n Papers & CCL 2. M/S Babulal /REL/09-12/33 Website Gupta, Gidi-A. Dt 04.06.2009

4 Reject Open Tender 25.08.2007 Two Bid 17.09.2007 Two 1.Shri Saryu NIL YES Agreement Shri Saryu 109.8 23.09.2010 24.09.2007 NA transportation through News System Gope 2. M/S No.CGM(A)/SO Gope Extended up to Papers & CCL Chenani (M)(A)/Reject 23.09.13 Website Transport Trans/GDW/08/ 217 Dt. 25.01.2008. NA CRS AREA DEPTT.MINING CRS/SO(C)/ Cleaning of Open 09.06.2011 Two Bid 17.06.2011 at . 03 . 03 _ L1 M/s No. 2243 M/s Hasan 2.94 Within 6 _ _ _ BRK/ TN/11- Sewerage 10:30 AM Naaz Hasan Traders dt.12.07.2011 Trader months from 12/2160 chamber and Construction Sri 10th days of dt.06-06-11 sewer line of Mangesh Singh issue of award NTS, and M/s Hasan lettar Barkakana Traders

Page 1 HQ-CIVIL DEPTT.CIVIL 02 of 2011 – 12 Construction of Through In CCL website Two bids Upto 3.00 PM Three Nill Yes, awarded GM(C)/2008/C. Manoj Kumar, 3 06 (Six) N.A. N.A. N.A. Community Hall to the Lowest Rs. 9.09 Lakhs vide no. publication in (Three) Vidyapati Months. 60’ x 18’ size on 02.05.2011 system on 16.05.2011. Tenderer. D./2011/ 936, News paper Nagar, Kanke GM(C)/Tender/ with verandah 1. M/s Raj dated Road, Ranchi. 2011 – 12/619, at Mukchund and CCL Kumar Toli, Chutia website. 2. Sunil Kumar 05.07.2011 Dated 23rd under CCL April 2011 CSR Scheme. 3. Manoj Kumar 21 of 2010 – 11 Repair of Coal Through In CCL website Two bids Upto 3.00 PM One Nill Yes, awarded GM(C)/2010/Ro M/S S. K. 1 Rs. 198.85 06 (Six) N.A. N.A. N.A. vide no. Trunk Road to the Lowest Mishra & Sons, publication in (One) Lakhs Months. GM(C)/Tender/ from Naya on 21.02.2011 system on 14.03.2011. Tenderer. ad/Kuju/2011/9 L. N. Mihra News paper 2010 – 11/189, More to 1. S. K. Mishra & Colony, Itki Chainpur 96, dated Road, Ranchi. Dated 10th and CCL Sons Railway Feb.' 2011 website. 18.07.2011 Crossing of (Length – 8.64 26 of 2010 – 11 ConstructionKms.) of Through In CCL website Two bids Upto 3.00 PM Two Nill Yes, awarded GM(C)/2012/B/ Rajesh Kumar 2 Rs. 10.84 03 (Three) N.A. N.A. N.A. boundary wall on 04.03.2011 to the Lowest vide no. publication in (Two) Sharma, New Lakhs Months. system on 18.03.2011. Tenderer. Wall/CRS/2011 enclosing old & Friends Colony, GM(C)/Tender/ News paper 1. Raj Kumar new S.T. Plant Gaushala Agarwal /1061, dated 2010 – 11/354, at CRS and CCL 2. Rajesh Kumar Road, Ramgarh dated 25th Barkakana. website. Sharma 30.07.2011 Cantt., February 2011 Ramgarh. 41 of 2010-11 Providing and Through In CCL Website Two bids upto 4.00 PM 5(Five) Five Nil Yes, awarded GM©/2011/N.K/ M/S Ranji & Rs- 57.17 06 (six) Months laying water publication in on 19.10.2010 systems on 27.10.2010. 1. M/S S.K to the Lowest 2011/10 48, Lakhs supply system News paper Mishra & Sons Tenderer. dated with and CCL 2. M/S Ranhit & 28.07.2011 vide construction of website. Co. 3. RCC reservoir M/S K.N .P and pump Singh house for 152 4. Sri Co. Hehal Ratu no.SO©/NK/Te units(D/S) Bishwanath N.A. N.A. N.A. MQ.Hostel and yadav 216 units (F/S) 5. M/S Shankar B-Type Qtrs.for & Co. nder/10- CISF Personnel at NK Area. Road ranchi-

11/1474,dated

23.09.2010 834005

Page 2 01 of 2011 – 12 Construction of Through In CCL website Two bids Upto 3.00 PM Three One Yes, awarded GM(C)/2009/Ba R & P

vide no. publication in Construction, Double storied rrack/ Rs. 181.12 to the Lowest 168/A, Lakhs GM(C)/Tender/ News paper CISF barrack 4 B&K/2011/991, 14 (Fourteen) N.A. N.A. N.A. Sonatand, 2011 – 12/600, (Four) Months. and CCL on 25.04.2011 system on 13.05.2011. Tenderer. for 128 persons 1. M/s S. K. dated Bokaro Steel dated 19th April website. Mishra & Sons 2. R & P City-827011 2011 (2 Blocks of 64 Construction 15.07.2011 3. Hindustan () Steelworks persons each) Construction Ltd.

near Football

ground, Kargali

at B & K Area. Gm(ws)/agm Transportation Open 16.04.11 Two 07.05.11 Three Three Nil No. ______Tender (kta)/(w)/t/KT of MIO jowder 1.BKB cancelled W-MIO/11/30 from UCIL, Transport pvt. vide notice Date- jadogoda to Ltd. no. 15.04.2011 kathara 2.Ajanta Coal GM9KTA)/A washery by co Traders GM(KTA)/T/ tractor's trucks 3.M/S KTW- damoder MIO/11/0983 including Marketing Pvt. & 09.07.2011 loading and Ltd. unloading after weighment of kathara washery weight bridge.

Page 3 GM(KTA)SO Supply of drinking Openwater tanker 4.6.11 Two 11.6.11 Three Chand Entp. GM(KTA) 1.12 60. Days 15.6.11 15.8.11

Yes Sarwan Singh

( C)/Tende/ in diff.villages/tolastender at water Karam Singh SO( C)/Ad/ Nil 11/266 distribution center of Hazari Sarwan Singh 2011/585 dt.4.6.11 Panchayat C.D.Scheme, dt. 18.07.11

Kathara Open 4.6.11 Two 11.6.11 Three Chand Entp. GM(KTA) 2.48 60. Days 15.6.11 15.8.11 do Supply of drinking water by Yes Karam Singh

water tanker in diff.tender village Karam Singh SO( C)/Ad/

/tolas at water distribution Sarwan Singh Nil 2011/551

center of Jhirkeyand Bandh dt. 14.07.11

Basti under CD scheme, Kathara do Open 16.5.11 Two 30.511 Three GM(KTA) 1 month 152 dt. R/M of south Eastern portion Ashique Ansari Yes Ashique Ansari 1.12 13.7.11 12.8.11

16.05.11 of boundary wall oftender Base work H.W.P.Enterprises SO( C)/Ad/ Nil sho at Kathara Colliery J.D.Enterprises 2011/544

dt.

11/12.07.11

Open 16.5.11 Two 30.5.11 Three GM(KTA) 1. month do Repairing of roof of Base work Ashique Ansari Yes Ashique Ansari 1.5 11.7.11 10.8.11

152 dt. shop , store , Compressortender shed H.W.P.Enterprises Nil SO( C)/Ad/

16.05.11 ,Repair shed of Drill section J.D.Enterprises 2011/511

under Kathara Coliery. dt. 8/9.07.11

Open Two 10.6.11 Three GM(KTA) 2. months do R/M of room (E & F . Incline) at 25.5.11 K.B.Pandey Yes K.B.Pandey 1.25 15.7.11 14.9.11

214 dt. Jarangdih seam of tenderSawang Vindeshwar Pd. Nil SO( C)/Ad/

25.5.11 Colliery (U/G) Bhagwati Constrction 2011/545

dt.14.07.11

Open 25.5.11 Two 10.6.11 Three GM(KTA) 2. months do R/M of sanitation work in Vishal Builders Yes Vishal Builders 1.81 3.7.11 2.9.11

214 dt. Officers colony A,B,tender type and R.K.Enterprises Nil SO( C)/Ad/

25.5.11 II, III type colony at Sawang Saroj Construction 2011/465

dt.2.07.11

Page 4 do Open 25.5.11 Two 10.6.11 Three GM(KTA) 2. months 214 dt. R/M of 15 nos. qtrs. On occasion Bhagwati Constrn. Yes Bhagwati Constrn. 1.57 11.7.11 10.9.11

25.5.11 of marriage, shiftingtender etc at Vindeshwar Pd. Nil SO( C)/Ad/

Sawang Colliery K.B. Pandey 2011/510

dt.9.07.11

Open 25.5.11 Two 10.6.11 Three GM(KTA) 2. months do Extension, repairing and heigh- Hi-Tech System Yes Hi-Tech System 1.61 18.7.11 17.9.11

214 dt. tening of fencing walltender all around Bigan Ram Nil SO( C)/Ad/

25.5.11 E.F. stowing bunker of Sawang Vindeshwar Pd. 2011/592

Colliery dt.16.07.11

Open 1.6.11 Two Three GM(KTA) 4. months do R/M of doors and windows in 17.611 Sushil Kr. Singh Yes Sushil Kr. Singh 4.91 28.7.11 27.11.11

247 dt. qtrs. In diff. coloniestender of GM, R.S. Const. Nil SO( C)/Ad/

1.6.11 Unit , Kathara Vishal Builders 2011/620

dt.24/27.07.11

Open 1.6.11 Two Three do Day to Day maint. Work for 17.611 Jai Mata Dee Yes GM(KTA) 6. months 247 dt. water tank, floor, plaster,tender Enterprises -II Jai Mata Dee 1.96 28.7.11 27.1.12 Nil 1.6.11 drain etc. in IB NMQ 1 C.A. type Dinesh Kumar SO( C)/Ad/ Enterprises -II

II and type III colony of Sawng K.B. Pandey 2011/653

colliery. dt.24/27.07.11

Open 1.6.11 Two Three GM(KTA) 7. months do Day to day sanitation work in 17.611 Md Yasin Yes Md Yasin 2.81 28.7.11 27.2.12

247 dt. colony no. 1,2, & 3tender at R.R. R.S. Const. Nil SO( C)/Ad/

1.6.11 Shop Jarangdih . J.D. Const. 2011/652

dt.24/27.07.11

Open 9.6.11 Two Three GM(KTA) 2. months do R/M of 13 nos. ROM qtrs. At 27.6.11 Inderdeo Paswan Yes Inderdeo Paswan 2.31 28.7.11 27.9.11

344 dt. Mahabir Asthan attender Sawang Vindeshwar Prasad Nil SO( C)/Ad/

9.6.11 Colliery U.K. Singh 2011/651

dt.27.07.11

Page 5 Open 1.6.11 Two Three GM(KTA) 2. months do R/M of fallen boundary wall 17.611 Bigan Ram Yes Bigan Ram 3.25 28.7.11 27.9.11

247 dt. and replacement oftender old Vindeshwar Prasad SO( C)/Ad/

1.6.11 damaged CGI sheet of Sub- Hi - Tech System Nil 2011/650 Station and store at Sawang dt.27.07.11

Colliery

Repair of 30 GM(KTA)/Excv/ 1. M/S Thakur Nos. Through Tender/Dumper/J Tyre Retrading Cuts of OTR M/S Thakur Tyre RD- Works, Dhanbad. 173 Dt Tyre Size Open Tender 28/29.05.11 Two bid system 16.06.11 Two NIL Yes Retraiding, 1.03 30 Sept. Not available Not available Not applicabe SWG/2011/114 2. M/S.Hindustan 22.06.2011 18.00X25 for Dhanbad DT. Tyre Waria, JRD & SWG of 28/29.05.2011 Durgapur-3 Kathara Area.

Repairing of 1. M/S Annapurna front wall 03 Enterprises, Nos. Front Roof, Kathara. GM(KTA)/Excv/ Side gate & 2. M/S. Manoj M/S Manoj 10 days from the Tender/Dumper/ Railing,Crowd Engg.Work Shop, 198 Dt Engg.Work date of handing SWG- Platform railing Open Tender 18.05.11 Two bid system 31.05.11 Three NIL Yes 0.4 Not available Not available Not applicabe Kathara 27.06.2011 Shop, over the machine GVP/2011/71 & crowd motor 3. M/S. Coalfield Kathara at site DT. 18.05.2011 cover of EKG- Janta 5A Shovel Sl. Engg.Works, No. Exc-2500 of Jarangdih. Sawang-Gvp.

Testing of Air tank/ vessels of folowing equipments 1. M/S deployed at Automation respective Controls, Nagpur. GM(KTA)/Excv/ 10 days from the project of 2. M/S. Anukul Tender/HEMM/ 206 Dt M/S Automation date of handing Kathara area.The Open Tender 08.02.11 Two bid system 22.02.11 Three Engineers, Nagpur NIL Yes 1.87 Not available Not available Not applicabe AREA/2011/760 02.07.2011 Controls, Nagpur over the machine testing should be 3. M/S. DT. 08.02.2011 at site done Technocrate, hydraulically and Jharsuguda wall thickness of (Orissa). air tank should be measured ultrasonically.

Page 6 Dismatling & 1. M/S Shiv Engg. fitting/repairing GM(KTA)/Excv/ Works, Phusro. or replacement of Spot 2. M/S. Sunil M/S Shiv 15 days after Boom Assly. Of 213 Dt Qtn./Shovel/JRD Spot Tender 23.06.11 Single bid system 23.06.11 Three Engg. Works, NIL Yes Engg.Works, 0.56 handing over the Not available Not available Not applicabe Exc-2435 L&T 08.07.2011 /2011/184 DT. Phusro Phusro machine at site 300 CK Shovel 23.06.2011 3. M/S. Trehanco of Jarangdih Pvt. Ltd., Phusro. Colliery.

RAJRAPPA AREA CIVIL NIL HQ-MM NO Supply Order has been given more than Rs. 2.00 Crores & above BARKA-SAYAL AREA (S&IC) DEPTT. 37 D.R. Ball L.T.E 28.05.11 Two bid 28.06.11 2 1, (1) M/s. J. 1 (1) M/s. yes SO(MM)/RS(B M/s. J. 0.62 Ex. Stock 21.07.11 22.07.11 Bearing 23936 Umashankar & Chitlangiya S)/Snd/02021 Umashankar & within 30 days Co. Kolkata trading 1-063 dt. Co. Kolkata from the date corporation, 14.07.11 of receipt of Kolkata purchase order

25 Fluorescent Open 06.05.11 Two bid 07.06.11 5 4, (1) M/s. 1, (1) M/s. yes SO(MM)/RS/(B M/s. R.R. 2.69 within 2-4 28.07.11 28.07.11 Jacket Delkon Textiles Kirtikumar & S)/Snd/11- Enterprises, week from the Pvt. Ltd. (2) Co. 12/020211- Ramgarh date of receipt M/s. R.R. 064 dt. Cantt. of order Enterprises (3) 16.07.11 M/s. Gaurav & Co. (4) Ana Digi Sales (P) Ltd.

Page 7 42 DGMS L.T.E. 31.05.11 Two bid 21.06.11 2 2, (1) M/s. Hi NIL yes RS/(BS)/11- M/s. Shree 4.07 Immediate but due due Approved tech 12/020211- Shyam within 1 cement Enterprises (2) 066 dt. Suraksha month from capsule M/s. Shree 16.07.11 Udyog the date of Shyam Dhanbad receipt of Suraksha order. Udyog 28 PVS L.T.E. 10.05.11 Two bid 10.06.11 1 1, (1) M/s. NIL yes RS/(BS)/11- M/s. Anand 1.97 within 4-6 due due Ventilation Anand Micons 12/020211- Micons , New week from the Ducting 068 dt. Delhi date of receipt 21.07.11 of order

131 Spare for SDL L.T.E. 13.03.11 Two bid 05.04.11 1 1, (1) M/s. NIL Properietary RS/(BS)/11- M/s. Eimco 4.55 Within 18 due due Eimco Elcon basis 12/020211- Elecon (India), weeks for (India) 071 dt. Dhanbad indigenous 27.07.11 parts and 24 weeks for imported parts from the date of receipt of order

Page 8 (CMC) DEPTT. CGM(CMC)/Ba Loading & Open 26.11.10 Two Bid 25.12.10 Two 1. M/S Ajay N.A Yes GM(BS)/GM( M/S Jai 1348.8 21.06.2014 22.06.2011 NA NA rka- Transportation Transport Co. M)(BS)/Ct?UR Mahalaxmi sayal/2010/86 of caol from At& PO : M-OCP- Transport Co. dated- surface stock Ramgarh Cantt. At & Po: 23.11.2010 of urimari OCP District: Sdg/11- Ramgarh to saunda Ramgarh 12/4822 Date- Cantt. siding (Jharkhand) 26.07.11 District: 2. M/S Jai Ramgarh Mahalaxmi (Jharkhand) Transport Co. At & Po: Ramgarh Cantt. District: Ramgarh (Jharkhand)

(E&M) DEPTT. 1 SO(E&M)/B- Hiring of one Open Computer’s Two bid 15-07-11 03(Three) Nos. 02(Two) 01 No. Sri LOI No.-4737, Sri Snehashish 06,04,732/= Time of --- S/ Tender/ Br.New Diesel tender CD sent to system Nos.1. Sri Narayan Dtd.-25-07- Chakraborty, completion of Hiring- Closed Jeep GM(System), Snehashish Prasad 2011 Riverside, Contract is for Br.New for CCL, for Chakraborty 24 months D.Closed deployment display on 2. Sri Indra Jeep/GM under the CCL’s web Deep Nayak Unit/11- control of site vide letter 12/2580, S.O.(E&M), No.-3807, Dated-31- Barka-Sayal. Dtd.-29-06-11 05/01-06-11

2 SO(E&M)/B- Repairng of 34 Open Tender Computer’s Two bid 19-07-11 03(Two) Nos. 02(Two) Nos. M/s R.M. TCR has been M/s Micro 1,08,193=27 Time of Work not yet -- S/ Tender/ Nos. Flight CD sent to system Industries prepared and Spares completion of awarded Repair- Flight Bars of Elecon GM(System), under process Parts,Ranchi Contract is for Bars./FB//11- make Feeder CCL, for of observing have quoted 20 days 1. M/s 12/3980, Breaker of display on formalties the L-1 offer. Dolphin Dated-01/04- Urinary CCL’s web Engg., 07-11 Project site vide letter 2. M/s Micro No.-4020, Spares Parts Dtd.-05-07-11

Page 9 3SO(E&M)/BS/ Repairing of Open Tender Computer’s Two bid 20-07-11 02(Two) Nos. 02(Two) Nos. Nil TCR has been M/s Sunrise 94,810=98 Time of Work not yet -- Tender/Repair- 1000GPM , CD sent to system prepared and Enterprises, completion of awarded Pump/BHK 350 Mtrs GM(System), under process PTPS,Patratu Contract is for UG/11- head, MLA-7 CCL, for of observing have quoted 20 days 12/4024, Kirloskar display on formalties the L-I offer. make Pump of CCL’s web Dated-04/05- UG Mine of site vide letter 1.M/s Sunrise 07-2011. Bhurkunda No.4082, Dtd. Enterprises. Project. 06/07-07-2011

2. M/s Aditya Enterprises

4 SO(E&M)/B- Hiring of one Open Tender Computer’s Two bid 22-07-11 03(Three) Nos. 02(two) Nos. 01(one) No. LOI No.5092, Sri Krishna 13,23,986=70 Time of 2/8/2011 - - S/ Tender/ 52 Seater Bus CD sent to system Dated-01-08- Kumar Dubey, completion of Hiring- Buses/ for GM(System), 1. Sri Shakti M/s 11 Patel Nagar, Contract is for 11-12/ 3758 deployment at CCL, for Kumar Singh B.S.Travels, Bhurkunda 12 months Dtd. 28-06-11 Urimari display on Ranchi. Project CCL’s web 2. Sri Krishna site vide letter Kumar Dubey No.- 3807,Dt.29-06- 11

5 SO(E&M)/B- Hiring of one Open Tender Computer’s Two bid 22-07-11 03(Three) Nos. 02(two) Nos. 01(one) No.LOI No.5093, Sri Shakti 13,93,676=76 Time of 2/8/2011 - - S/ Tender/ 52 Seater Bus CD sent to system Dated-01-08- Kumar Singh, completion of Hiring- Buses/ for GM(System), 11 PTPS, Contract is for 11-12/ 3758 deployment at CCL, for 12 months Dtd. 28-06-11 Birsa Project display on 1. Sri Shakti M/s Patratu CCL’s web Kumar Singh B.S.Travels, site vide letter Ranchi. No.- 3807,Dt.29-06- 11 2. Sri Krishna Kumar Dubey

Page 10 6 SO(E&M)/B- Repairing & Open Tender Computer’s Two bid 22-07-11 02(two) 02(two) Nos. Nil TCR has been M/s Chanda 44,489=50 Time of Work not yet -- S/ Tender/ rewinding of CD sent to system prepared and Electrical completion of awarded Repair- 160HP, 550V, GM(System), under process Works, Contract is for Stator/Rotor/St 1470RPM, CCL, for of observing Ramgarh have 15 days arter 11-12/ M&P make display on quoted the L-I Nos. 1. M/s Chanda formalties 4161 Dtd. Elect.Motor CCL’s web offer. Electrical 07/08-07-11 Stator(Local site vide letter Works. Sly. No.-4229, No.811/SND- Dtd.-09/11-07- 2. M/s Rajeev D) of Saunda- 2011 Engg. D

Works 7 SO(E&M)/B- Repairing of Open Tender Computer’s Two bid 22-07-11 02(two) 02(two) Nos. Nil TCR has been M/s Shiv 97,094=25 Time of Work not yet -- S/ Tender/ 115KW(160H CD sent to system prepared and Shakti completion of awarded Repair- P), 550V, GM(System), under process Electrical, Contract is for Stator/Rotor/St 1460RPM, CCL, for of observing CCL, Saunda 20 days Nos. 1. M/s Shiv arter 11-12/ M&P make display on formalties Shakti 4161 Dtd. Rotor/ Stator CCL’s web Electrical 07/08-07-11 at Water site vide letter Works. Supply, Sayal- No.-4229, 2. M/s D Dtd.-09/11-07- Coalfields 2011 Engg. Works 8 SO(E&M)/B- Repairing & Open Tender Computer’s Two bid 22-07-11 02(two) 02(two) Nos. Nil TCR has been M/s Chanda 67,276=00 Time of Work not yet - - S/ Tender/ reconditioning CD sent to system prepared and Electrical completion of awarded Repair- of Kilburn GM(System), under process Works, Contract is for Stator/Rotor/St make 170KW, CCL, for of observing Ramgarh have 15 days arter 11-12/ 3.3KV, display on formalties quoted the L-I 4161 Dtd. DOL/VCB CCL’s web Nos. 1. M/s Chanda offer. 07/08-07-11 Starter( Sl. site vide letter Electrical No.C- No.-4229, Works. SND/3.3KV/0 Dtd.-09/11-07- 2) of C- 2011 2. M/s Rajeev Saunda. Engg.

Works

Page 11 9 SO(E&M)/B- Hiring of one Open Tender Computer’s Two bid 25-07-11 02(two) Nos. Part-I has not ------S/ Diesel Closed CD sent to system been Tender/Hiring- Jeep for GM(System), examined. Diesel Closed deployment CCL, for Jeep/Urimari/1 under the display on 1-12/3978, control of CCL’s web Dtd.-01/04-07- Project site vide letter 11 Officer, No.-4020td.- Urimri 05-07-2011

10SO(E&M)/B- Repairing & Open Tender Computer’s Two bid 29-07-11 02(two) 02(two) Nos. Nil Part-II Opened Sri Ashok Kr. 1,66,554=25 Time of Work not yet -- S/ Strengthening CD sent to system TCR has not Singh, Central completion of awarded Tender/Repair- of 10 Nos. GM(System), been prepared Saundra have Contract is for Tubular Poles Tubular Poles CCL, for quoted the L-I 15 days & HPSV of Elect. OHL, display on Offer. Lamps/Sayal- 440V with CCL’s web D/11-12/4370, Service wire of site vide letter Dtd-13/14 CCL Colony, No.-4436,Dtd.- Street Lighting 14/18-07-2011 Works of Patratu Water Works.

-2018 Nos. 1. Sri Satyendra Kr.Singh 2. Sri Ashok Kr. Singh 11SO(E&M)/B- Repairing of Open Tender Computer’s Two bid 29-07-11 02(two) 02(two) Nos. Nil Part-II Opened Sri Satyendra - Time of Work not yet -- S/ 31 Nos. HPSV CD sent to system TCR has not Kr. Singh, completion of awarded Tender/Repair- Lamps of GM(System), been prepared Sayal have Contract is for Tubular Poles Officers CCL, for quoted the L-I 15 days & HPSV Colony, IB & display on Offer. Lamps/Sayal- IC type CCL’s web D/11-12/4370, Quarters and site vide letter Dtd-13/14 of Shakti No.-4436,Dtd.- Colony of 14/18-07-2011 Sayal-D Project. -2018 Nos. 1. Sri Satyendra Kr.Singh 2. Sri Ashok Kr. Singh

Page 12