Annexure: A DETAILS OF CONTRACTS PLACED BY OPEN TENDER (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works) (Status for the Month of APRIL 2016 - FEBURARY 2017)

Works Awarded : APRIL 2016

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name and (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening and date address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ date etc Works) Mech. etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 e-Tender 16.12.2015 Supply, installation, testing & IRCON/J&K- M/s Hitech-JK Engineers ` 4,26,56,056.82 7.25% below ` 3,95,63,493/- 12 months IRCON/J&K- commissioning of 33/11KV, Cell/JAT/15//1014/ JV from the Cell/JAT/15//1 014/Package- 2X1000 KVA Conventional & Package-SS-1/967 Hall No. 112-B2, date of SS-1/967 11/.433 KV 2X1000 KVA Dated 14.04.2016 1st Floor, South Block, issue of Dated Package type Sub-station Bahu Plaza, LOA 04.11.2015 along with HT panel, LT panel, Jammu - 180 012 APFC panel, Metering panel, DG set etc. and other auxiliary works for Sumber Railway Station on Dharam- Qazigund Section of USBRL Project (J&K) (Package: SS-01) 2 e-Tender 13.04.2016 Supply of DG Set for 11 IRCON/9041/BD- M/s Elmech Engineers ` 39,60,000 Item Rate ` 35,09,000 01 month IRCON/9041/ Stations of Ishurdi - Darsana S&T/SIG.SUPPLY 1402, Chiranjiv Tower, Contract from the BD- S&T/SIG.SU section of Bangladesh Railway /13(R)/05/682 43, Nehru Place, date of PPLY/13(R)/ Dated 25.04.2016 New Delhi - 110 019 issue of 05 Dated LOA 07.04.2016

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

3 IRCON/J&K 08.02.2016 Detailed Design Construction IRCON/J&K- M/s Italferr S.P.A. - - ` 12,22,00,000/- 36 months Cell/JAT/14/ Supervision of Important Bridge Cell/JAT/14/ Via Vito Giuseppe Galati from the 1014/K-B/ DDC-Anji across river Anji Khad between Km 1014/K-B/ 71, 00155 Rome Italy date of Bridge/337/ 38.430 to Km 39.087 on Katra- DDC Anji issue of Dated Banihal Section of Udhampur – Bridge/337/ LOA 31.12.2015 Srinagar – Baramulla New BG 18388 Railway Line Project, J&K State, Dated (Package DDC - Anji Khad) 26.04.2016

4 e-Tender 22.04.2016 Supply of S&T materials & Tools/Test IRCON/9041 M/s General Auto Electric ` 36,99,611 9% ` 40,32,576 01 month IRCON/9041/ Equipment for 11 Stations of Ishurdi - /BD-S&T/ Corporation Above from the BD- S&T/TOOLS Darsana section of Bangladesh TOOLS & D-207, date of & TEST Railway TEST Ansa Industrial Estate, issue of EQPT/70 EQPT/70 Sakinaka, Andheri (E), LOA Dated Dated Mumbai - 400 072 13.04.2016 27.04.2016

5 e-Tender 22.03.2016 Works Contract for Maintenance of IRCON/J&K M/s Gh. Nabi Giri & Sons ` 1,74,83,400/- 3.40% ` 1,80,77,835.60 12 months IRCON/ J&K NR/IRCON’s establishments (office & Cell/JAT/14/ H.O.: Near Tehsil Office, Above from the Cell/JAT/14/ 1014/ D-Q/ camp up keeping and other misc) 1014/D-Q/ Banihal, date of Utility Works/ and assisting IRCON’s Engineers Utility Works/ Distt. Ramban, issue of M-39/168 during supervision of works & survey M-39/168 J&K - 182 146 LOA works as required at various Dated locations along the project alignment 30.04.2016 from Reasi to Banihal covering Ramban, Sangaldan, Sumber, Kohli, Dharam, Khari, Banihal, Reasi etc. in connection with Reasi - Banihal section of USBRL Project (Package: M-39)

Contd.../- Works Awarded : MAY 2016

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/2063/ 10.03.2016 Cast-in-situ bored piling work for IRCON/2063/ M/s Civcon ` 4,40,00,000/- ` 4,40,00,000/- ` 3,45,02,831.23 6-months DROB/HOWR New Howrah Divisional Railway DROB-HOWRAH/ Construction Pvt. Ltd. AH/TENDER/ PILE/15 Office Building at Howrah in PILE/CCPL/90 21A Shakespeare Dated Dated 03.05.2016 Sarani, 17.02.2016 Kolkata - 700 017

2 e-Tender 22.03.2016 Hiring of Survey Team on Team IRCON/JK M/s Skylark Designer & ` 94,37,574/- 3.50% Above ` 97,67,889.09/- 10 months IRCON/JK Month Basis for Survey Works Cell/JAT/14/1014/ Engineers Pvt. Ltd from the Cell/JAT/14/1 of R-D & D-B Sections in D-Q/Survey team B-48, IInd Floor, date of 014/D- Q/Survey connection with the Construction – K-B Section/ Sector-63, issue of team – R-B of Reasi-Dharam-Banihal S-2/274 Noida (UP) LOA Section/S-2/ Section of USBRL New Rail Link Dated Dated Project (Package: S-2) 10.05.2016 26.02.2016 3 IRCON/PO/ 28.03.2016 Construction of Staff Quarters, IRCON/2050/ M/s Om Construction ` 35,298,807.56 19.80% above ` 42,287,971.46 15 months TN/Jaynagar- Station Building, Services BGL.JBB/Tender/ At+Po-Bihat, form the 2050/16/40 Buildings, Platform, Roads & Pkg.-Bldg-06 Tola-Gurudaspur, date of other structures at Janakpur (Nepal)/175 Sunderban, issue of Halt (Nepal) in connection with Dated 10.05.2016 Dist. - Begusarai LOA “Gauge Conversion & (Bihar) PIN - 851 135 Construction of New Broad Mob.: 9934469716 Gauge Railway Line from Jaynagar (India) to Bardibas (Nepal). Pkg.-Bldg.-06 (Nepal)

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/2062/N03.03.2016 Earthwork in formation (Cutting IRCON/2062/NMD M/s NSPR RCPL JV, 8- `41.03Crores As Per BOQ `34,31,92,768 08 MDC/NISP/Rly & Filling), morum, Blanketing, C/NISP/LOA/EW & 2-12086/5-B, 2nd Floor Months Siding/EW & BR/PKG-II construction of new culverts BR/PKG-II Sneha House, Road No - (RT), Dated alng loading platforms drains, (RT)/438, 3, Banjara Hills, 10.02.2016 pathways etc. Pkg.-2 (RT) in Dated: 12.05.2016 Hyderabad - 500 034 connection with Construction of Private Railway Siding for NMDC’s Integrated Steel Plant at Nagarnar near Jagdalpur in Chhattisgarh 5 IRCON/2057/ 13.4.2016 Construction of Private Railway IRCON/2057/ M/s Hari Construction & `30,52,89,615.00 ` 30,52,89,615.00 ` 33,42,92,128.00 09 NSTPP/EW& Siding with all Contractor’s NSTPP/ Associates Pvt. Limited, Months P.Way/Pkg.- 2b./2016/01 Materials (Except Rails for EW & P.way/ At & P.O - Keshawe, Dated Plain Track issued Free of Pkg. -2b./e-Tender/ P.S- Barauni, 22.03.2016 Cost) For Coal transportation LOA/1280 Begusarai, system for Nabinagar Super Dated 13.05.2016 Bihar - 851 134 Thermal Power Project of NPGC Limited, near Ankohara Railway Station, Distt. Aurangabad, Bihar – Civil works From Ch. 0.972 to Ch. 5.320 & P. Way works In entire Siding System (Pkg. - 2b) 6 IRCON/PO/ 28.03.2016 Construction of Staff Quarters, IRCON/2050/ M/s Rajesh Kr. Singh ` 20,379,450.72 19.85 % above ` 24,42,4771.69 15 TN/Jaynagar- Station Building, Services BGL. JBB/Tender/ Vill+Po - Chhatauni, months 2050/16/41 Buildings, Platform, Roads & Pkg.-Bldg-09 P. S. - Basopatti, form other structures at Loharpatti (Nepal)/187 Dist.- Madhubani (Bihar) issue of Halt (Nepal) in connection with Dated 17.05.2016 Mob.: 9934949478 LOA “Gauge Conversion & Construction of New Broad Gauge Railway Line from Jaynagar (India) to Bardibas (Nepal). Pkg.-Bldg.-09 (Nepal) Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

7 IRCON/PO/ 28.03.2016 Construction of Staff IRCON/2050/ M/s Om Construction ` 32,269,722.94 19.90% above ` 15 months TN/Jaynagar Quarters, Station Building, BGL.JBB/Tender/ Ram Chowk, 38,691,397.81 form issue -2050/16/42 Services Buildings, Platform, Pkg.-Bldg-10 P. O. - Bhawara, of LOA Roads & other structures at (Nepal)/188 Dist. - Madhubani (Bihar) Singyahi Station (Nepal) in Dated 17.05.2016 Pin - 847 212 connection with “Gauge Mob.: 9431202889 Conversion & Construction of New Broad Gauge Railway Line from Jaynagar (India) to Bardibas (Nepal). Pkg.-Bldg.-10 (Nepal) 8 IRCON/2048/ 06.05.2016 Providing and fixing IRCON/2048/ M/s S.N. Marketing ` 95,00,000/- ` 94,90,000/- ` 99,81,500.00 4-months ISC- Aluminum Composite Panels ISC-BEHALA/ Sharada Complex, BEHALA/ TENDER/ for External Wall Cladding ACP/SNM/25406/ Sevoke Road, ACP/2016/20 including supply, fabrication 148 Silliguri - 734 001 Dated and erection of structural Dated 18.05.2016 14.04.2016 steel with necessary aluminum framework for New Sports Complex of Eastern Railway at Gholsapur (Behala), Kolkata, W.B. 9 IRCON/Civil/5 05.11.2015 Design & Construction of IRCON/Civil/ M/s Premco Rail Engineers Ltd. ` 11,94,91,794/- ` 11,87,11,952/- ` 15,02,10,791/- 11 Months 019/NELS.BN Flooring, Embedded Track, 5019/NELS. Axis Mall, CF-9, 3rd Floor, DM/ e-Tender/ Pit Track of various sheds BNDM/ 1C - Rajarhat, New Town, OT/11 and balance Service e-Tender/OT/ KOLKATA-700 156 (WB) Dated Buildings for Setting up of 11/54 Tel: 033-40230000-199 14.10.2015 Second Electric Loco Shed Dated 20.05.2016 Fax: 033-40230110 at Bondamunda, Rourkela E-mail: [email protected] (ODISHA) 10 IRCON/2048/ 18.05.2016 HVAC System for Indoor IRCON/2048/ M/s Unique Engineers Pvt. Ltd. ` 4,85,00,000/- ` 4,85,00,000/- ` 3,63,75,000/- 5-months ISC- Stadium & Cricket Pavilion ISC- 332, Tower-A, BEHALA/ TENDER/ for New Sports Complex of BEHALA/HVAC/ Spaze I-Tech Park, Sector-49, HVAC/2016/ Eastern Railway at Unique/25408/158 Sohna Road, 21 Dated Gholsapur (Behala), Kolkata, Dated 20.05.2016 Gurgaon - 122 002 20.04.2016 W.B. Contd.../- Works Awarded : JUNE 2016

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name and (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening And date address Contract Engg./Elect. /S&T/ Engg./Elect./S&T/ Mech. Date Mech. etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/ 21.01.2016 Construction of station building IRCON/2052/ M/s Bridge and Roof Co. ` 138.75 ` 126.67 Crores ` 130.51 Crores 18 months 2052/ TN/ (only composite structural part) Santragachi/ (India) Ltd., KANKARIA Crores SRC/ STN. BLDG./ with steel framework and RCC Stn.Bldg.-FOB- CENTRE (5th Floor), 2015/7 slabs, fabrication and erection of Ramp/ 2/1 Russel Street, Dated two nos. of 12 meter wide FOBs B&R/25409/ 219 Kolkata - 700 071 06.11.2015 (Foot Over Bridges) across Dated Santagachi Yard and one 08.06.2016 elevated ramp in front of station building including pile foundation at Santragachi station in connection with station development work of Santragachi station for South Eastern Railway 2 e-Tender 07.04.2016 Furnishing of admin building ( RCON/MECH/ M/s Durian Industries Ltd, Various type of ` 88,48,7222.00 ` 88,48,7222.00 12 weeks IRCON/ Phase-III Balance Furniture ) for 1029/RCF. 1/20 W.H.S. Kirti Nagar, furniture from the MECH/1029/ RCF.RBL-II/ RCF Rae Bareli RBL-II/ New Delhi-110 015 date of Furniture/301 Furniture/301/ Tel : 011-4714 0200, issue of Dated 6832 Dated 25161550 Fx : (011) - LOA 16.03.2016 09.06.2016 4740243 Email : delhidurian @gmail.com

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

3 e-Tender 09.04.2016 Alumino -Thermit welding of UIC IRCON/1035/ M/s India Thermit ` 30,78,000/- ` 30,78,000/- `.34,75,000/- 09.05.2017 IRCON/1035/D 60Kg rails, 1080 grade Head DMRC CT-1- Corporation Limited (11 months MRC CT-1-A /TENDER/ Hardened, on viaduct/ A/TENDER/ 84/22 Fazalganj, from the ATW Dated Underground at various locations ATW Dated Kanpur-208 012 (UP) date of 16.02.2016 along the alignment for CT-1-A 10.06.2016 Ph:0512-2215161 issue of contract of DMRC, Lajpat Nagar LOA) to Mukundpur Delhi 4 IRCON/J&K 18.05.2016 Balance work of Detailed Design IRCON/J & K M/s GEODATA - - ` 10,98,14,220/- 36 months Cell/JAT/14/ Consultancy, 3D monitoring & Cell/JAT/14/1014/ Engineering SPA, form issue 1014/K-B/ DDC T-2/8402 Construction Supervision of K-B/DDC T- Corso Boizano, 48/E- of LOA Dated Tunnel T-2 (Between km 33.212 2/349/8476 10121, Torino, Italy. 06.05.2016 to km 38.375) and associated Dated works in connection with the 23.06.2016 construction of Katra to Dharam Section of Udhampur – Srinagar – Baramulla New BG Railway Project. Works Awarded : JULY 2016

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/MECH 06.05.16 Supply of Electrically Operated IRCON/ M/s Marwaha i) Electrically ₹ 39,69,203.00 ₹ 39,69,203.00 5 & ½ 3016/NTPC/S Synchronized Screw Jack CAP. 35 MECH/3016/ Manufacturing Co. operated syn. months i.e. TPP/JACK/RE TON & Traversing Jack CAP 20 NTPC/JACK/ B/3, Street No. 2, Jack – 01 set up to V01/05 REV01/ Dated TON & 35 TON for NTPC’s SSTPP Anand Parbat Indl. ii) Traversing 26.12.16 SUPPLY/05 12.04.2016 Project, Sholapur. Area, Guru Gobind Jack 20 T & 35 T Dated 12.07.2016 Singh Marg, New – 2 nos. each Delhi-110005 2 IRCON/2060 12.04.2016 Construction of Civil Works IRCON/2060 DEEVEE-GAWAR ` 20441.43 Lakhs Item rate ` 19755.60 Lakhs 23 months /CGRLP- including Earthwork in Formation for /CGRLP- (JV) from issue EWC/ eTender/ Embankment and Cutting, EWC/ 1st Floor, Vikas date of LOA PkgI /05 Blanketing, Culverts, Major & Minor eTender/ Complex, Bridges and other Ancillary Works PkgI /05 Korba -495677 (C.G.) from Km 98.860 To Km 134.660 and Date: Ph. 07759-245168, Flyover Line from Km 128.000 To 19.07.2016 9993139999, Km 135.200 (Package I) in email: Connection with the Construction of [email protected] New BG Electrified Double Line in the State of Chhattisgarh over South East Central Railway East-West Corridor – Gevra Road-Pendra Road via Dipka, Kathghora, Sendurgarh and Pasan

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

3 IRCON/2064 17.05.2016 Construction of Service Buildings IRCON/2064 M/s Panchdeep ` 1225.33 Lakhs Item rate ` 1248.61 Lakhs 9 months /NMDC-S&T- including Commercial Office, OHE /NMDC- Constructions Ltd., from issue Pkg- II/eTender- Store & Office Room, OHE Staff S&T-Pkg-II/ 545, G.T. Road (S), date of LOA Service Room, Rolling Hut Room, C&W eTender- Howrah – 711 101 Buildings/01 Staff Room at Sick Lines, Weigh Service Bridge Room, C&W Office at HSM Buildings/01 Ph. 033-26382405, area, Crew Guard Rest Room, Dated Mob. 93391 47623 Intermediate Block Cabin, Route 21.07.2016 email: Relay Interlocking Cabin, C&W Panchdeep.howrah@ Shed, Diesel Loco Shed and other gmail.com allied works in connection with the Construction of Private Railway Siding for proposed 3 MTPA Integrated Steel Plant for NMDC Ltd., at Nagarnar, Chhattisgarh State (Package: II Schedule-A)

4 IRCON/MEC 06.05.2016 Supply of Electric Overhead IRCON/MEC M/s Krane Mfg (India) 01 No. ₹ 49,66,878.00 ₹ 49,66,878.00 Supplied on H3016/NTPC Travelling Crane 25/5 Ton for H/3016/NTP Pvt. Ltd, B-10, Anand 04.10.16 /STPP/EOT/ 06/ Dated NTPC’S SSTPP Project, Solapur. C/EOT/SUP Nagar, M.I.D.C.,Addl 12.04.2016 PLY/06 Ambernath-421506, Dated Dist. Thane (INDIA) 22.07.2016 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

5 IRCON/e- 25.04.2016 Supply, installation, testing & IRCON/ M/s Ahluwalia Fire `1,48,04,166/- `1,48,04,166/- `1,58,08,174/- 12 Months TN/Fire commissioning of firefighting e-TN/Fire Protection Engineers, Fighting_ IBT_ system & other related ancillary Fighting_ 10450, East Park GGN/16/03 works for International Business IBT_ GGN/ Road, (Near Filmistan Dated Tower at Plot No. 16, Sector - 32, 16/03/48 Cinema), 21.03.2016 Gurgaon (Haryana) Dated Karol Bagh, 22.07.2016 New Delhi – 110 005 Ph.: 23618533,23628796, Fax: 011-23628796, E-mail: [email protected] 6 IRCON/J&K 16.05.2016 Construction of Tunnel T-77D (KM IRCON/J&K M/s Beigh ` 102.32 Crores 14.99% Above ` 117.66 Crores 22 Months CELL/JAT/14 146.60 TO 148.36 approx. CELL/JAT/1 Construction Co. Pvt. from the /1014/K- B/T77D/341 (Western Side of Bichelri River) on 4/1014/K- Ltd. date of Dated: Katra - Dharam-Qazigund Section B/T77D/341/ Plot No. 4, Opp. issue of 18.02.2016 of Udhampur-Srinagar-Baramulla 8524, Wave Mall, Bye Pass LOA New BG Railway Line Project Dated: Road, Narwal, Jammu (Package: T- 77D) 25.07.2016 (J&K) 7 IRCON/J&K 16.05.2016 Construction of Tunnel T- 13, Part IRCON/J&K M/s Hindustan `1633.76Crores 7.09% Above ` 1749.59 Crores 30 Months CELL/JAT/14 Tunnel T-14 including Station Yard CELL/JAT/1 Construction Co.Ltd. from the /1014/K-B/T- 13/343 at Basindadhar, Approach Road 4/1014/K- (HCC) date of Dated: from Adit of T-13 (Khanikote) to P2 B/T-13/343/ Hincon House , 11th issue of 22.03.2016. of T-13 & P1 of T-14 (Basindadhar) 8526 Floor, 247 Park, Lal LOA and Bridge No. 60 (between Km Dated: Bahadur Shastri 61.004 to Km 73.785 approx.) on 25.07.2016 Marg, Vikroli (West) Dharam-Qazigund Section of Mumbai-400083. Udhampur – Srinagar – Baramulla New BG Railway Line Project (Package T-13) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

8 IRCON/ 03.11.2015 Supply, Testing and Commissioning IRCON/MEC M/s Techno 01 No `47,00,000.00 `47,00,000.00 Within 02 MECH./1029 of 01 No Cable Fault Locating KIt for H./1029/RC Instrumentation month from /RCF-RBL- II/Cable Fault Modern Coach Factory Rae Bareli F-RBL- (India) Pvt Ltd., Plot the issue of Locating/298 II/Cable No 67, STREET No. LOA Dated Fault B, G T Road Friends 14.10.2015 Locating/298 Colony, Industrial /6911 Area Shahdara New Dated Delhi-110095 26.07.2016

9 IRCON/1034 14.06.2016 Repair and Rehabilitation work for IRCON/1034 M/s SSA Techno % Rate tender ` 175.10 Lakh Tendered 06 months / BPHP/ existing structures, Slab Culverts, / PBTL/e- Construction Pvt. Ltd. for composite Rate : i.e. up to e-Tender/ Rehabilitation Box Culverts, Minor Bridges Tender/ 101-C, Pal House, items (-) 27.07% 28.01.2017 Structures/78 complete between Km 4+200 to Km Rehab. Top Floor, Below Dated 163+500 of NH-15 near Phalodi in Str/1161 Hari Nagar Ashram, 21.05.2016 connection with Widening and Dated New Delhi - 110 014 Cost = Strengthening of existing Bikaner – 29.07.2016 ` 127.70 Lakh Phalodi section to four lane from Km 4+200 to Km 55+250 and two lane with paved shoulder from Km 55+250 to Km 163+500 in the state of Rajasthan Works Awarded : AUGUST 2016

Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/1034/ 20.06.2016 Transportation of Bulk Bitumen IRCON/1034/ M/s Gopal Kanhaiya 1000 MT Rate ` 2737/- Rate ` 2914/- 03 months BPHP/ (Grade : VG.40) from ex depot of BPHP/TPT OF Roadlines, per MT per MT i.e. up to e-Tender/ Tpt of Bitumen C- IOCL Koyali near Vadodara to BITUMEN C- Parashar Villa, 02.11.2016 1/79 Dated IRCON HMP site at Km 45+600 1/79/1178 3-NA-34 Jawahar Tendered Cost : Cost : 21.05.2016 near Techri Phanta, Shri Kolayat ji Dated Nagar, ` 27.37 Lakh ` 29.14 Lakh on Bikaner - Phalodi Highway 03.08.2016 Jaipur - 302 005 section of NH-15 in the state of Rajasthan 2 IRCON/MECH3 20.05.16 Supply of Fuel Injection Pump Test IRCON/MECH/ M/s SLVMR Fuel 01 Set ₹ 10,06,844 ₹ 10,06,844 Supplied on 016/NTPC/STP Bench with Master Pump Kit & 3016/NTPC/S Injection Equipments 24.11.16 P/FIP TEST STAND/08 Injector/Nozzle Testing Equipment TPP/FIP/08/0 360 Export Promotion Dated with Ultrasonic Cleaning Unit for Dated Industrial Park, 12.04.2016 NTPC’s SSTPP Project, Solapur. 03.08.2016 Kundli, Ph-III, Haryana – 131 028 3 e-Tender No. 27.10.2016 Hiring of inspection vehicles for IRCON/J&K- M/s Friends Sumo Taxi ` 7,99,05,600/- 11.26% Above ` 8,89,87,968/- 24 Months IRCON/J&K- IRCON's officers and staff in Cell/BNL/14/10 Owners Union from the Cell/BNL/14/ connection with the construction of 14/K-B/Hiring date of 1014/K-B/ Vehicle Hiring Vehicle Dharam-Banihal section of USBRL issue of Banihal/VH- Banihal/VH-20/ New Rail Link Project , J&K LOA 20/800 Dated Dated (Package: VH-20) 06.04.2016 05.08.2016 Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/CC/ 05.01.2016 Construction of Tunnel T-5 IRCON/2046/ M/s ABCI % Rate tender for 5% below Rs. 132.94 22 months TN/ SR-2046/ (between Km 11+604 to Km Sivok-/ Infrastructures Pvt. composite items Crore from the CONS. /T-5/ 15/732 13+697 approx.) on Sivok- T5/48/506 Ltd., 1/3Mc Donald Cost put to date of st Dated Rangpo Rail Link Project Dated Tower, 1 Floor, G. S. tender: ` 139.94 issue of 13.11.2015 05.08.2016 Road, Bhangagarh, Crore. LOA -781007, Assam

5 IRCON/1034/ 27.07.2016 Transportation of Bulk Bitumen IRCON/1034/ M/s Gopal Kanhaiya 1000 MT Rate ` 2458/- Rate ` 2617/- 03 months NH-15/BPHP/ (Grade : VG.40) from ex depot of BPHP/Tpt of Roadlines, per MT per MT i.e. up to Transport of Bitumen/LT-84 IOCL Koyali near Vadodara to Bitumen Parashar Villa, 23.11.2016 Dated IRCON HMP site at Km 45+600 C-2/87/1224 3-NA-34 Jawahar Tendered Cost : Cost : 21.05.2016 near Techri Phanta, Shri Kolayat Dated Nagar, ` 24.58 Lakh ` 26.17 Lakh ji on Bikaner - Phalodi Highway 24.08.2016 Jaipur - 302 005 section of NH-15 in the state of Rajasthan

6 IRCON/2048/ 01.08.2016 Balance Civil Works related to IRCON/2048/ M/s Basab Dutta, ` 2.75 Crores ` 2.75 Crores ` 2,54,37,500/- 5-months ISC-BEHALA/ Indoor Stadium & Cricket ISC-BEHALA/ 1/ 2/1, Upendranath TENDER/Fin. Works/2016/ Pavilion for New Sports Complex TENDER/FIN. Chatterjee Lane, 22 Dated of Eastern Railway at Gholsapur WORKS/2016 Howrah 05.05.2016 (Behala), Kolkata, W.B. /22/428 PIN-711 103 Dated 25.08.2016

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

7 IRCON/1034/ 31.05.2016 'Construction of Road Over-Bridge IRCON/1034/ M/s. Balabharti Infra- % Rate tender for % Rate tender Tendered Rate : 18 months BPH P/ and it's approaches with REW work BPH/e- BVS(JV), 2/536,S-1, composite items for composite (-) 14.01% Below i.e. Up to e-Tender/ nd ROB-LC-06/76 as per specifications, drawings, tender/ROB- 2 Floor, Chitrakoot Cost put to items Cost: ` 22.15 25.12.2016 Dated: designs and maintaining all quality LC-06/1226 Scheme Vaishali tender: ` 25.76 Crore 04.05.2016 control standards etc. complete at Dated Nagar, Jaipur -302 021 Crore. KM 11+300 of NH-15 near Nal in 26.08.2016 (Rajasthan) connection with Widening and Strengthening of existing Bikaner- Phalodi section to four lane from Km. 4+200 to Km. 55+250 and two lane with paved shoulder from Km. 55+250 to Km. 163+500 in the state Rajasthan” 8 IRCON/1034/ ’31.05.2016 'Construction of Road Over-Bridge IRCON/1034/ M/s. Balabharti Infra- % Rate tender for % Rate tender Tendered Rate : 18 months BPHP/ e- and it's approach with REW work BPHP/TN//T- BVS(JV), 2/536, S-1, composite items composite for (-) 12.66% i.e. Up to Tender/ROB- nd LC-57/77 as per specifications, drawings, 91/Laying of 2 Floor, Cost put to Composite items Below Cost: 25.12.2016 Dated: design, maintaining all quality Median Chitrakoot Scheme tender: ` 23.86 ` 20.84 Crore 04.05.2016 control standards etc. complete at Kerb/1245 Vaishali Nagar, Crore KM 162+850 of NH-15 near Dated: Jaipur -302 021 Phalodi in connection with 31.08.2016 Widening and Strengthening of existing Bikaner-Phalodi section to four lane from Km. 4+200 to Km. 55+250 and two lane with paved shoulder from Km. 55+250 to Km. 163+500 in the state Rajasthan” 9 e-Tender No. 10.08.2016 Providing support services for IRCON/J&K M/s BSS Enterpises ` 99,05,600/- 8.00% Above ` 7,99,05,600/- 12 Months IRCON/J&K IRCON's office and guest houses CELL/JAT/1 314, Suraksha from the CELL/JAT/14 /1014/DQ/Su and other locations at USBRL 4/1014/DQ/ Vihar,Palora Top, date of pport project office and establishments at Support Jammu (J&K) issue of Services/M- Jammu . (Package: M-40) Services/M- LOA 40/350 40/350/1252 Dated: 19.07.2016 Dated: 31.08.2016

Contd.../- Works Awarded : SEPTEMBER 2016

Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. opening and date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 1 eTender 21.07.2016 Construction of Toll Plaza and IRCON/3017/ M/s SEWAK RAM `1,66,63,289.00 Schedule A: `1,66,46,497.00 11 Month IRCON/301 other facilities at Km.258.90 on SGTL/eTend Engineers & Civil + 10.999% from date of 7/SGTL/eT NH-3 for Ircon SGTL (Agreement er/Toll Contractors Schedule B: issue of ender/Toll No.ISGTL/CO/SG/IRCON/CORR Plaza/321 A-108, + 10.999% LOA Plaza/321 ES/02 dtd.02.09.2015) in Dated Flex Apartments, CPWD connection with “4-Laning of 02.09.2016 C-58/22,Sector 62, Schedule-A Shivpuri -Guna section of NH-3 Noida. -0.10% from Km 236.000 TO KM 332.100 in the State of Madhya Pradesh” (STAGE-I). 2 IRCON/MECH/ 08.06.2016 Supply, Installation and IRCON/MECH M/s Innotech 02 `10,44,480.00 `10,44,480.00 03 Month 1029/RCF.RB Commissioning of 02 Nos /1029/RCF.R Engineering Devices from the L-II/UTM/304 Dated Universal Testing Machine BL-II/UTM Pvt. Ltd., RZ-D1/6, issue of 17.05.2016 /304/7052 Vashist Park, Opp Purchase Dated Janak Cinema, New Order 06.09.2016 Delhi-110046 3 e-Tender no. 07.07.2016 Construction of Type-II Railway IRCON/Civil/ M/s Vishnu Saran & Co., `2452.55 Lacs Schedule A: `22,48,22,120 18 Months IRCON/civil/e- houses (154 Nos) for providing E-Tender/ 113/163 - 8.4% /- from the Tender/1029/R CF-RBL- resenditial accommodation to 1029/RCF- Swaroop Nager , Schedule B: date of II/OT/02 Modern Coach Factory Personnel RBL/OT/02/ Kanpur – 208 002 (UP) - 5 % issue of Dated. including internal electrical and 9207 Schedule-C LOA 07.06.2016. telecom works, internal sanitary Dated -8.44% and plumbing works ,Garraige & 09.09.2016. Miscellaneous works in the township of MCF/RBL

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 4 IRCON/CC/ 23.06.2016 Supplying and stacking of 50mm IRCON/CC/ M/s Gopal Mishra, `4,89,00,000.00 Item rate `5,46,67,275.00 4 Month e-TN/JBRLP/ size Pakur variety machine e-TN/JBRLP/ Rajhata, Binodpur, from date of 2050/16/733 Dated: crushed track ballast for New 2050/16/733/ Katihar – 845 105 issue of 19.05.2016 B.G. Line from Jaynagar (India) 542, Dated (Bihar) LOA to Bardibas (Nepal) Railway 15.09.2016 project for Indian portion only from Km 0+000 to Km 2+975 5 IRCON/ 3017/ 30.08.2016 Supply of crushed WMM & IRCON/ 3017 M/s, Anil Construction `1,37,50,000.00 ` 310 per MT `1,55,00,000.00 75 days SGTL/ Asphalt aggregates as per / SGTL/ Company, from issue eTender/ Works/ WMM Required Gradation & Spec- eTend-er/ Krishan Puram, of LOA & Asphalt ifications Including Transport- Works/ WMM Shivpuri - 473 551 Aggregates-1/ ation and unloading of & Asphalt (MP) 324 aggregate at IRCON’s main Aggregates- Dated 03.08.2016 camp 1/324 Dtd:21.09.16 6 IRCON/CC/ 23.06.2016 Supplying and stacking of IRCON/CC/ M/s Raman `13,78,00,000/- Item Rate `16,10,20,035/- 6 Month e-TN/JBRLP/ 50mm size Pakur variety e-TN/JBRLP/ Construction Pvt. Ltd., from date of 2050/16/734 Dated machine crushed track ballast 2050/16/734/ Janakpur-9, issue of 19.05.2016 for New B.G. Line from 551, Dhanusha LOA Jaynagar (India) to Bardibas Dated Nepal (Nepal) Railway project for 21.09.2016 Nepal only from Km Km 2+975 to KM16+340

Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 7 IRCON/CC/ 23.06.2016 Supplying and stacking of 50mm IRCON/CC/ M/s Raman `20,88,00,000/- Item Rate `22,28,51,725/- 6Month e-TN/JBRLP/ size Pakur variety machine e-TN/JBRLP/ Construction Pvt. Ltd., from date of 2050/16/735 Dated crushed track ballast for New 2050/16/735/ Janakpur-9, Dhanusha issue of 19.05.2016 B.G. Line from Jaynagar (India) 550 Nepal LOA to Bardibas (Nepal) Railway Dated project for Nepal only from Km 21.09.2016 Km 16+340 to KM34+800 8 IRCON/2049/R 05.09.2016 Tender for Construction of balance IRCON/2049/ M/s. Tribeni `129,158,419/- 14.25% above `14,75,63,492.57 09 Month OB-II- work of Road over Bridge both ROB-Bihar/e- Construction Ltd., from the BIHAR/LC- 53A/2016/25, railway span and adjacent Tender/LC- New Town Square, date of issue Dated approach span including 53A/LOA/45 Office No.-4M, 4th Floor, of LOA 06.08.2016 Reinforced Earth wall/ Retaining /1740 Chinarpark, wall in lieu of LC- 53 A at Km Dated Kolkata – 700 136 613/19-21 between Kauriya Halt - 20/21.09.2016 Bihiya Section on Patna - Mughalsarai Route in Danapur Division of E C Railway , Bihar 9 IRCON/MECH/ 05.07.2016 Supply, Testing and IRCON/MEC M/s Godrej & Boyce 02 `47,63,994.00 `47,63,994.00 16 weeks 1029/RE/MCF commissioning of 10 Ton ( 02 H/1029/RE/M Mfg. Co. Ltd., from the RBL-II/FORK LIFT/307 Nos) Diesel Fork Lift Trucks for CF RBL- Godrej Bhawan, Sher issue of Dated Modern Coach Factory II/FORK Shah Suri Marg , Okhla Purchase 09.06.2016 LIFT/307 Dt: New Delhi – 110 065 Order 23.09.2016

Contd.../- Works Awarded : OCTOBER 2016 Schedule Quantity Rate d S. Tender Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completi N. No. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. on etc Works) etc Works) Date (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 1 IRCON/ 28.07.2016 Construction of Sports Hostel, IRCON/Civil/ M/s Prakash Infra ` 1668 Lakh Sch A: - 5% `15,53,83,253.89 15 Months civil/ Maintenance office (05 Nos) and E-Tender/ Venture Pvt Ltd, Sch B - 5% from the e-Tender/ Sch-C-5% 1029/RCF- external Services including 1029/RCF- 631/305, Patel Nagar, date of RBL-II/ Drainage ,sewerage ,water RBL/OT/ Ismail ganj, Sch D - 5% issue of OT/05 supply,roads fencing Toe wall 05/9299 Indra Nagar, Sch E - As per LOA Dated horticulture work ,external Dated Sec-8, quoted 24.06.2016. Sch F - As per electrical & telecom works for new 05.10.2016 Lucknow – 226 016 quoted type –II & III Rly Houses & Miscellaneous civil works in Prashanti Parishar township of MCF/RBL for Rly Personnel

2 IRCON/ELE 28.6.2016 Design ,Drawing, Supply, IRCON/ M/s Lanco Solar 01MW Solar `7,37,83,003.00 09 (Nine) CT/1029/M Installation, Testing and ELECT/1029/ Energy Pvt. Ltd., Power Plant months CF.RBL- Commissioning of 01MW Solar MCF-RBL/ 2nd Floor, Plot No. 397, II/SOLAR Power Plant with all the electrical SOLAR Udhyog Vihar, PLANT/01 and associated equipments PLANT/01/ Phase -III, Dated 07.06.2016 including civil works & integrating it 7157 Gurgaon -122 016 with existing 2MW solar Power Dated ( Haryana) Plant at Modern Coach Factory, 05.10.2016 Rae Bareli, Lucknow (UP

3 IRCON/MECH 06.06.2016 Supply of Hydraulic Re-Railing IRCON/ M/s Francis Klein & Co. 01 Set ₹ 43,66,220 ₹ 43,66,220 16 weeks 3016/NTPC/ST Equipment (HRE) for NTPC’s MECH/3016/ Private Limited i.e. up to PP/RE- th RAILING SSTPP Project, Sholapur. NTPC/STPP/ Om Tower, 7 Floor, 30.01.2017 EQUIP/07 RE-RAILING 32, Chowringhee Road Dated EQUIP./LOI/P Kolkata 700 071 12.04.2016 ART-I/07 Fax (+91) (33) 22171540 Dated Email: 10.10.2016 td.choudhary@francisklei n.in (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 4 eTender 21.07.2016 Repair and rehabilitation of IRCON/3017/ M/s. Tech Fast Rebuild `1,78,00,000.00 Schedule A: + `1,61,39,490.82 09 Month IRCON/3017/ existing structures on NH-3 for SGTL/Tender Pvt. Ltd. 5.62% from date SGTL/Tender /Structure Ircon SGTL in connection with “4 /Structure A-20,Kalpana Enclave Schedule B: + of issue of rehabilitetion/ Laning of Shivpuri-Guna Section of rehabilitetion/ Mumbai – 400 069 8.32% LOA 331 NH-3 from Km236+000 to Km. 331 Dated 332+100 in the state of Madhya 15.10.2016 Pradesh (Stage-I)”. 5 IRCON/1034/ 27.07.2016 Transportation of Bulk Bitumen IRCON/1034/ M/s Gopal Kanhaiya 1000 MT Rate ` 2737/- Rate ` 2914/- per 03 months BPHP/e- (Grade : VG.40) from ex depot of BPHP/Tpt of Roadlines, per MT MT i.e. up to Tender/Tpt of Bitumen C- IOCL Koyali near Vadodara to Bitumen C- Parashar Villa, 17.01.2017 1/84 IRCON HMP site at Km 45+600 1/84/1343 3-NA-34 Jawahar Tendered Cost : Cost : Dated near Techri Phanta, Shri Kolayat ji Dated Nagar, ` 27.37 Lakh ` 29.14 Lakh 05.07.2016 on Bikaner - Phalodi Highway 18.10.2016 Jaipur - 302 005 section of NH-15 in the state of Rajasthan 6 IRCON/2046/ 24.09.2016 Construction of access road from IRCON/2046/S M/s Samdup Lepcha, ` 2.44 Crore 9.00 Below ` 2.22 Crore 03 Months NFR- existing NH-10 to Portal-II of ivok-Rangpo/ Pagung, from the SRRP/e- tender/A. Tunnel -14(approx 1150 mtr long) e-Tender/ Chungthang, date of Road/ including nala crossing, protection T-14A. Road North issue of 122/2064 work & other ancillary work in /122/2023 LOA. connection with Sivok(WB) to Dated Rangpo(Sikkim) New BG Rail Line 21.10.2016 Project. Contd.../ (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 7 eTender 19.09.2016 Transportation of Bulk Bitumen ( IRCON/3017/ M/s Arbuda Logistics, `1,94,12,250.00 Item rate `1,83,39,750.00 16 Month IRCON/301 Grade VG 40) from Ex-depot of SGTL/Tender Plot No. 1204, from date of 7/SGTL/Ten IOCL, Koyali near Vadodara to /Bitumen Ranoli GIDC issue of der/Bitumen IRCON’s Hot Mix Plant Site at Km. Transport/ Vadodara – 391 350, LOA Transport/ 276, Bamaur Village on NH-3 for 326 Gujrat 326 Ircon SGTL in connection with “4 Dated Laning of Shivpuri-Guna Section of 22.10.2016 NH-3 from Km. 236+000 to Km. 332+100 in the state of Madhya Pradesh (Stage-I)”. 8 eTender 19.09.2016 Tranportation of Rapid Settin IRCON/3017/ M/s Arbuda Logistics, `6,89,610.00 Item rate `6,66,900.00 16 Month IRCON/301 Emulsion (RS-1) from Ex Depot of SGTL/Tender Plot No. 1204, from date of 7/SGTL/Ten HPCL savli to IRCON’s Hot Mix /Bitumen Ranoli GIDC issue of der/Bitumen Plant Site at Km. 276, Bamaur vill. Transport/ Vadodara – 391 350, LOA Transport/ On NH-3 for Ircon SGTL in 326 Gujrat 327 connection with “4 Laning of Dated Shivpuri-Guna Section of NH-3 22.10.2016 from Km. 236+000 to Km. 332+100 in the state of Madhya Pradesh (Stage-I)”. 9 IRCON/CC/e- 30.06.2016 Manufacturing, Supplying, IRCON/CC/e- M/s Daya Engineering 14,92,00000.00 Item rate `19,88,11,794/- 6 months TN/JBRLP/20 transportation & Stacking of TN/JBRLP/20 Works Pvt. Ltd., from the 50/16/736 Dated various sizes of 60 Kg UIC Rail 50/16/736/567 The Safe Legend, date of 07.06.2016 PSC Mono Block Sleepers for B.G. Dated 6-3-1239/B/111, issue of Main Line, Loop Line, Turnouts , 24.10.2016 Renuka Enclave, LOA Derailing Switch, Bridge Raj Bhawan Road, approaches & deck slab sleepers, Samajiguda, Switch Expansion Joints (SEJ) and Hyderabad – 500 082 Level Crossings from Km 2+975 to Km 34+800 for Nepal Portion of Jaynagar (India) to Bardibas (Nepal) New Rail Line Project.

Contd.../ (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

10 IRCON/CC/ 30.06.2016 Manufacturing, Supplying, IRCON/CC/ M/s Daya Engineering `3,19,00,000/- Item rate `4,54,66,223/- 4 months e-TN/JBRLP/ transportation & Stacking of e-TN/JBRLP/ Works Pvt. Ltd., from the 2050/16/737 Dated: various sizes of 60 Kg UIC Rail 2050/16/737/ The Safe Legend, 6-3- date of 07.06.2016 PSC Mono Block Sleepers for B.G. 568 1239/B/111, Renuka issue of Main Line, Loop Line, Turnouts , Dated Enclave, Raj Bhawan LOA Derailing Switch, Bridge 24.10.2016 Road, Samajiguda, approaches & deck slab sleepers, Hyderabad – 500 082 Switch Expansion Joints (SEJ) and Level Crossings from Km 0+000 to Km 2+975 for Indian Portion of Jaynagar (India) to Bardibas (Nepal) New Rail Line Project.

11 IRCON/ 01.07.2016 Supply & Commissioning of 260 IRCON/MECH/ M/s Delite Kom 260 Nos `15,630.00 `50,35,877.00 90 Days MECH/1029/ Nos Locker Cabinet for Modern 1029/MCF. Limited, from the MCF.RBL-II/ Coach Factory Rae Bareli. RBL-II/Locker Kukreja House issue of Locker Cabinet/306/ Cabinet/306 IInd Floor, Purchase 7202 Dated Dated 46 Rani Jhansi Raod Order 25.10.2016 19.06.2016 New Delhi – 110 055 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

12 e-tender 30.06.2016 Providing Consultancy Services to IRCON/CO/ M/s Delhi Integrated `1,28,28,897.00 18% Above `1,51,38,098.31 12 months IRCON/CO/ carry out Feasibility Study, PETS GM(W)/2071/ Multi Modal Transit from the GM(W)/207 (Preliminary Engineering and Shivpur System Ltd., date of 1/Shivpur Traffic Survey), Topographic Kathautia/ 1st Floor, issue of Kathautia/C onsultancy/ Survey, Final Location Survey, Consultancy/ Maharana Pratap LOA 1 preparation of Detailed Cost 1/166 ISBT Building, Estimate, Conceptual and Dated Kashmere Gate, Preliminary Design and General 28.10.2016 Delhi – 110 006 Arrangement Drawings of structures (excluding buildings), alignment design, assessment of land requirement and assistance in Land Acquisition and preparation of Detailed Project Report (DPR) including financial viability and bankability of the project, in connection with construction of new Railway Coal Corridor from Shivpur (Distt. Chatra) to Kathautia station (Distt Hazaribag) (approximate route length of 49 km) in the state of Jharkhand under the jurisdiction of ECR

13 IRCON/J&K 16.05.2016 Construction of Tunnel T74-R IRCON/J&K M/s. ABCI ` 228.42 Crores 12.25% Above ` 256.41 Crores 22 Months CELL/jat/14/1 balance work at North Portal from CELL/jat/14/1 INFRASTRUCTURE from the 014/K- B/Tunnel- Km 130/950 to Km 133/910 014/K- Pvt Ltd date of 74R- (Approx) on Katra -Banihal B/Tunnel- 1/3, Mc Donald Tower, issue of B(N)/342/ Section of Udhampur – Srinagar – 74R- 1st Floor, G.S. Road, LOA Sated Baramulla New BG Railway Line B(N)/342/ Bhangagarh, Guwhati- 18.02.2016 Project (Package-T-74R-B(N)) Dated 781007 (Assam) 28.10.2016 Works Awarded : NOVEMBER 2016

Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/Elect/5 01.08.2016 Design, Drawing, Supply, Erection, IRCON/Elect/ M/s Hitech Erectors As per Detailed Given in the `9,63,95,820/- 15 months 109/NELS.BN Testing & Commissioning of 5109/NELS.B Pvt Ltd, BOQ of activities. BOQ DM/S.Rtn.& Elect.works/O 33kV/433V,2x1000kVA sub NDM/S.Rtn.& 303, Pragati T/16 Dated station, Power distribution system, Elect.works/ Chambers, 08.06.2016 Lighting & power supply works jn OT/16 Ranjit Nagar, buildings & workshops including Dated Commercial Complex, Indoor/Outdoor lighting for setting 04.11.2016 New Delhi – 110 008. up of Second Electric Loco Shed at Bondamunda (Odisha)

2 IRCON/ 26.08.16 Construction of two (2) Nos. IRCON/ M/s. ITD Cementation `21.28 Cr. `20.50 Cr. `246479489.00 12 months 2053/TN/ SHM Subway through Railway Track by 2053/SHM/S Indian Ltd., (excluding /SW/ 2016/26 Box Pushing and its dispersals on W/25416/ Godrej Waterside, 3 months the platforms of Shalimar Railway 611 Tower No.1, Sector-V, monsoon Station in Howrah District for South Dated Salt Lake City, period) Eastern Railway in West Bengal. 08.11.2016 Kolkata – 700 091 3 IRCON/MECH/ 15.09.2016 Supply, Testing , Commissioning & IRCON/MEC M/s MIGATRONIC A/s MAG Co2 Euro 340215.00 Euro 340215.00 120 Days 1029/MCF.RB Prove Out of 30 Nos Synergic H/1029/MCF. Post Box 206 Welding Sets & from L-II/Co2 WELDING Pulse MIG/MAG Co2 Welding Sets RBL-II/Co2 DENMARK 70 Nos Synergic opening of Sets/RET & 70 Nos Synergic MIG/MAG Co2 WELDING MIG/MAG Co2 Letter of Dated Welding Sets for Modern Coach Sets/RET/ Welding Sets Credit (L/c) 03.08.2016 Factory at Lalganj Rae Bareli 7235 Dtd. 08.11.16 Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/MECH 19.08.2016 Supply, Testing, & IRCON/MEC M/s Cranes Limited, ( 20T- 02 Nos, `2,87,28,149.00 `2,87,28,149.00 180 Days /1029/RE/MC Commissioning of Electric H/1029/RE/M 9, D D A Market, 10T-03 Nos & 5T- from the F RBL-II/EOT Crane/308 Overhead Travelling Cranes ( CF RBL- Katwaria Sarai, 01 Nos) issue of Dated 20T- 02 Nos, 10T-03 Nos & 5T- II/EOT Opposite QUTAB Hotel, LOA. 16.07.20 16 01 Nos) for Modern Coach Crane/308/ New Delhi – 110 016 Fcatory Rae Bareli- UP. 7249 Dated 16.11.2016 5 IRCON/ELEC 13.10.2016 Supply, Erection, Testing & IRCON/ELEC M/s Umed Singh `7,76,47,898/- 38.00% above `3,10,74,690.00 6 months T/CTP- Commissioning & other T/CTP- Parnami Tower, (3 Packages) from the 12/DFC /S&E /01A Sated Associated Works including 12/DFC/S&E/ SCO-50-51, 2nd Floor, date of Dated Fabrication complete in all 01A/Pkg-I/ Old Judicial Complex, issue of 9.09.2016 respect for Dated Civil Lines, LOA Construction/Modification/Reloc 17.11.2016 Gurgaon – 122 001 ation of Electrical Utility of 33 Kv ` & below Power Lines for IRCON/ELEC M/s Creative 3,10,74,690.00 Dedicated Freight Corridor T/CTP- Entrepreneurs LLP (Vaitarana- Sachin Section of 12/DFC/S&E/ A-3/332, Sector-8, Western DFC-Phase-2) 01A/Pkg-II/ Rohini, Package-CTP-12 Project. Dated Delhi – 110 085 25.11.2016 IRCON/ELEC M/s Gupta Traders `3,10,74,690.00 T/CTP- Plot No.4, 12/DFC/S&E/ Unit No. 108, 01A/Pkg-III/ Vardhman Shopping Dated Complex, 23.11.2016 Derawal Nagar, Delhi – 110 009

Contd.../- Works Awarded : DECEMBER 2016

Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/2070/N 07.10.2016 Construction of Civil Works IRCON/2070/ M/s RKTC-MBPL JV, `24.07 Cr. Item Rate `23,28,09,565.42 09 months MDC-Pkg.- including Earthwork in Formation NMDC-Pkg.- Plot no. 65-A, from the dt. IV/eTender- Civil Misc. & P- for Embankment and Cutting, IV/eTender- Transport Nagar, Of LOA Way Works/11 Blanketing, Drains, Platforms, Civil Misc. & Korba - 495 677 (C.G.) Approach Roads, Sand Hump, P-Way Foot Over Bridge, Permanent Works/11 works, Extension of existing Dated Bridges and Level Crossings, 08.12.2016 Miscellaneous works and other allied works 2 e-Tender No: 27.09.2016 Supply & laying of Epoxy flooring IRCON/Mech M/s Quantum `167.24 Lacs Item Rate `1,35,46,428.30 08 Months IRCON/Mech/ in Shell shop and Finishing shop / 1029/RCF- Technologies, Contract from the 1029/RCF- RBL/Epoxyfloo RBL/Epoxyflo HO – 876, date of ring (Shell oring (Shell Sector - 8 issue of Sheet & Sheet & Faridabad LOA Finishing), Finishing)/95 Dated 22.08.2016 46, Dated 19.12.2016 3 IRCON/J7K 14.09.2016 Consutancy Services for Proof IRCON/J7K M/s Flient & Neill Ltd., ` 2,86,15,000.00 5.63% Above ` 3,89,76,812.00 36 Months CELL/JAT/14/ Checking of Drawings and CELL/JAT/14 Bevis Marks House, from the 1014/K-B/ Proof Technical Guidance for important /1014/K-B/ 24 Bevis Marks, date of Checking-Anji bridge aross the river Anji Khad Proof London EC3A 7JB issue of Bridge/347 between km 38.430 to km 39.087 Checking- United Kingdom LOA Dated on Katra-Banihal Section of Anji 19.08.2016 Udhampur-Srinagar-Baramulla Bridge/347/ Rial Link Project, J&K 8604 Dated 20.12.2016 Contd.../- Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/Civil/5 29.09.2016 Detailed Engineering & Design IRCON/Civil/ M/s. Kachroo Design As per BOQ on AS per BOQ `11.11 Lakhs 24 months 019/NELS.BN consultancy work for Drainage, 5019/NELS. Consulting (P) Ltd, item rates basis DM/e- Tender/OT/ 17 Water supply arrangement, BNDM/ B-71, Sector -64, Dated: Sewerage, Roads, Track, STP, e-Tender/OT/ NOIDA-201301 (UP) 02.09.2016 Fire fighting with related 17 Tel: 0120-2406460, structures and External services Dated: 4121525 related to construction of Second 30.12.2016 Electric Loco Shed at Bondamunda, Rourkela (Orissa) 5 IRCON/S&T/2 17.11.2016 Supply of Relays as per RDSO IRCON/S&T/ M/s. AEW `1,30,07,499.78 13.59% lower `1,12,40,273.60 03 months 064/02(R) RDSO Specification in 2064/02(R)/A Technologies LLP than the from the Dated 26.10.2016 connection with construction of Dated 14, Watkins Lane, estimated cost date of Private Rly. Siding for 3MTPA 30.12.2016 Gokul Apartment (near issue of Integrated Steel Plant of NMDC Howrah AC Market) LOA Limited at Nagarnar near Howrah - 711101 Jagdalpur city in Bastar District of Chhattisgarh state. 6 IRCON/S&T/2 17.11.2016 Supply of Relays as per RDSO IRCON/S&T/ M/s. Quartz `18,53,201.28 6.85% lower `17,26,280.64 03 months 064/02(R) RDSO Specification in 2064/02(R)/Q Technologies, than the from the Dated 26.10.2016 connection with construction of Dated K-36, Udyog Nagar, estimated cost date of Private Rly. Siding for 3MTPA 30.12.2016 Rohtak Road, issue of Integrated Steel Plant of NMDC Near Peera Garhi LOA Limited at Nagarnar near Chowk, Jagdalpur city in Bastar District of Delhi- 110041. Chhattisgarh state Contd.../- Works Awarded : JANUARY 2017

Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ completio Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For Value of Contract N. opening And date and address Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ n etc Works) Mech. etc Works) Date (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 1 IRCON/J&K 30.11.2016 Construction of Cable Stayed IRCON/J&K M/s. Hindustan `349,78,18,634/- 5.10% below `368,57,94,145/- 36 months Cell/JAT/14/10 Bridge including its approaches Cell/JAT/14/ Construction Co. than the from the 14/K-Q/(Pkg BR-Anji Khad) across river Anji Khad between 1014/K-Q/ Ltd.(HCC), tendered value date of /357 Tunnel T-2 and T-3 on Katra- (Pkg BR-Anji Hincon House, issue of Dated Banihal Section of USBRL Khad) /357/ 11th Floor, 247, LOA 10.10.2016 Project Jammu and Kashmir 8618 Dated Park, Lal Bahadur (Pkg BR-Anji Khad-Bridge) 06.01.2017 Shastri Marg, 2 IRCON/CO/ 08.09.2016 Earthwork in filling in emba- IRCON/CO/2 M/s. Ram Kripali Singh Both -Item Rate Both -Item `179,86,28,947/- 18 months 2067/KG/CIVIL nkment, provision of blanketing 067/KG- Construction Pvt. Ltd., & percentage Rate & from the /TENDER/11/ EW & material, construction /extension I/11/EW- 702, 7th Floor, percentage date of BRIDGES-I of minor bridges, major bridges PKG- Panchwati Plaza, LOA Dated no. 32, 40, 63, 64, 97, 123, 140, I/RKSCPL Kuchery Road, 10.08.2016 165, 168 (excluding steel Dated Ranchi – 834 001 superstructure) from Ch-2.000 10.01.2017 (Jharkhand) (Luckeesarai) to Ch-70.50 (Naw- adah) and misc works in connection with doubling of Railway line in b/w Kiul- Gaya 3 IRCON/CO/ 17.08.2016 Earthwork in filling in emba- IRCON/CO/2 M/s. Ram Kripal Singh Both -Item Rate Both -Item `181,16,71,249.58 18 months 2068/hb/Civil/ nkment, provision of blanketing 068/HB/11/E Construction Pvt. Ltd., & percentage Rate & from the GMW/Tender/ 11/EW 7 material, construction of major W & 702, 7th Floor, percentage date of Bridges bridge (excluding steel Bridges/RKS Panchwati Plaza, LOA Dated superstructure), extension of CPL/ Kuchery road, Ranchi- 26.06.2016 minor bridges, construction of Dated 834001 (Jharkhand) Gate lodge, Level crossing and 11.01.2017 miscellaneous work from Ch- 195.72 (BachwaraStn.) to Ch- 266.98 (Hajipur) in connection with doubling of Railway line in between Hajipur - Bachwara Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/J&K 31.12.2016 Providing Support Services for IRCON/J&K M/s. Dreamland ` 4,49,580/- 10.00% above ` 4,94,538/- 12 months Cell/JAT/14/1 Northern Railway’s office at Cell/JAT/14/ Travels. from 014/K-QSup- Services/NR/J USBRL Project, Jammu 1014/K-Q Shop No. 9, 01.02.17 ammu/M- (Package-M-41/NR) Sup-Services General Bus Stand, 41/357 /NR/Jammu/ Jammu Dated M-41/357/1570 16.12.2016 Dated 16.01.2017 5 IRCON/CO/20 09.09.2016 Earthwork in filling in IRCON/CO/ M/s. Hari GPT (JV), Item Rate Item Rate `905111057.42 18 months 67/KG/CIVIL/T embankment, provision of 2067/KG- C/O: Hari Construction from the ender//EW & Brides-II blanketing material, construction/ II/EW-PKG- and Associates Pvt. date of extension of minor bridges, major II/HARI-GPT Ltd. issue of bridge no. 209, 230, 248, 297, Dated At & PO: Keshawe, LOA 305 (excld. steel superstructure) 18.01.2017 PS: Barauni, from Ch-70.500 (Nawadah) to Distt.: Begusarai Ch-123.00 (Manpur) and misc. PIN - 851 134 (Bihar) works in connection with doubling of Railway line in between Kiul – Gaya 6 IRCON/1034/ 26.10.2016 Transportation of BULK IRCON/1034/ M/s Narendra Road 6000MT/ ` 2575 per MT/ `1,54,50,000/- 3 Months BPHP/e- BITUMEN (GRADE VG-40) from BPHP/e- Lines, ` 1,74,84,000/- ` 1,54,50,000/- Tender/Tpt of Bitumen Ex depot of IOCL Koyali near Tender/Tpt of Plot No. 313, GIDC, C-1/95 Vadodara to IRCON HMP Site at Bitumen Ranoli, Vadodara, Dated Km. 45+600 near Techri Phanta, C-1/95/53 , Gujarat 26.09.2016 Shri Kolayat ji on Bikaner- Dated Phalodi Highway Section of NH- 18.01.2017 15 in the State of Rajasthan

7 IRCON/1034/ 26.10.2016 Transportation of Bulk Bitumen IRCON/1034/ M/s Narendra Road 6000MT/ ` 2315 per MT `1,38,90,000/- 3 Months BPHP/e- (Grade VG-40) from Ex depot of BPHP/e- Lines, ` 1,57,02,000/- ` 1,38,90,000/- Tender/Tpt of Bitumen IOCL Koyali near Vadodara to Tender/Tpt of Plot No. 313, GIDC, C-2/96 , Dated IRCON's Hot Mix Plant at Km. Bitumen Ranoli, Vadodara, 26.09.2016 127+00 near Bap Village, C-2/96/54 , Gujarat Phalodi on Bikaner Phalodi Dated Highway Project Section on NH- 18.01.2017 15 in the State of Rajasthan (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 8 IRCON/2065/ 04.11.2016 Earthwork in filling in IRCON/2065/ M/s Tracks & Towers As per BOQ on AS per BOQ `139,79,67,150/- 18 months Katni-Singrauli/ embankment, provision of Katni – Infratech (P) Ltd., item rates basis from the GMW/Tender/ 11/EW&Bridges blanketing material, construction Singrauli/GM Plot No. 206, date of -1 Dated /Extension of minor bridges, W/Tender/11/ Phase-III, Road No. 76, issue of 20.09.2016 Limited Height Subways (LHS) EW & Jubilee Hills, LOA and RUBs (only sub-structure), Bridges – 1 Hyderabad – 500 033 drains and Retaining walls, Level Dated Crossings in the stretch from New 25.01.2017 Katni Jn. to Beohari station, both inclusive, in connection with construction of doubling of Railway line in between Katni-Singrauli of West Central Railway. 9 IRCON/2065/ 04.11.2016 Earthwork in filling in IRCON/2065/ M/s Tracks & Towers As per BOQ on AS per BOQ `139,79,67,150/- 18 months Katni-Singrauli embankment, provision of Katni – Infratech (P) Ltd., item rates basis from the /GMW/Tender/ 11/EW&Bridges blanketing material, construction Singrauli/GM Plot No. 206, date of -1 Dated /Extension of minor bridges, W/Tender/11/ Phase - III, issue of 20.09.2016 Limited Height Subways (LHS) EW & Road No.-76, LOA and RUBs (only sub-structure), Bridges – 1 Jubilee Hills, drains and Retaining walls, Level Dated Hyderabad – 500 033 Crossings in the stretch from New 25.01.2017 Katni Jn. to Beohari station, both inclusive, in connection with construction of doubling of Railway line in between Katni-Singrauli of West Central Railway. 10 IRCON/2065/ 04.11.2016 Earthwork in filling in IRCON/2065/ M/s Tracks & Towers As per BOQ on AS per BOQ `120,38.89,804/- 18 months Katni- embankment, provision of Katni – Infratech (P) Ltd., item rates basis from the Singrauli/GM blanketing material, construction/ Singrauli/GM Plot No. 206, date of W/Tender/12/ Extension of minor bridges, W/Tender/12/ Phase- III, issue of EW&Bridges- Limited Height Subways (LHS), EW & Road No. 76, LOA II Dated drains and Retaining walls, Level Bridges – II Jubilee Hills, 20.09.2016 Crossings & Gate Lodge in the Dated Hyderabad – 500 033 stretch from Marwasgram station 27.01.2017 to Singrauli station, both inclusive, in connection with construction of doubling of Railway line in between Katni-Singrauli of WCR (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 11 IRCON/2065 04.11.2016 Earthwork in filling in IRCON/2065/ M/s Tracks & Towers As per BOQ on AS per BOQ `120,38.89,804/- 18 months /Katni- embankment, provision of Katni- Infratech (P) Ltd., item rates basis from the Singrauli/GM blanketing material, construction/ Singrauli/ Plot No. 206, date of W/Tender/12 Extension of minor bridges, GMW/Tender Phase –III, issue of /EW&Bridges Limited Height Subways (LHS), /12/EW & Road No. 76, LOA -II Dated 20.09.2016 drains and Retaining walls, Level Bridges – II Jubilee Hills, Crossings & Gate Lodge in the Dated Hyderabad – 500 033 stretch from Marwasgram station 27.01.2017 to Singrauli station, both inclusive, in connection with construction of doubling of Railway line in between Katni- Singrauli of WCR 12 IRCON/J&K- 05.10.2016 Engagement of vehicles on hiring IRCON/J&K- M/s. Dreamland ` 64,37,934.34 3.25% above ` 66,47,167.20 12 months Cell/JAT/14/ basis for Officers and Staff Cell/JAT/14/ Travels. than the from 1014/K- working in the office of the CAO, 1014/K- Shop No. 9, tendered value 01.02.2017 B/Vehicle- Northern Railway USBRL Project, B/Vehicle- General Bus Stand, NR//VH- Jammu (J&K) (Package no. VH- NR//VH-21/ Jammu 21/352 Dated 21) 352/1630 12.09.2016 Dated 30.01.17 13 e- 17.01.2017 Execution of MILING WORK of IRCON/1034/ M/s Singla 450000 sqm/ Item Rate `1,47,00,000/- 10 Months Tender/IRCON existing Asphalt Pavement BPHP/TN/NI Construction Ltd., ` 1,82,00,000/- /1034/BPHP/T N/NIT ET-111 , where ever required between Km T/ET- SCO, 22/23, 4+200 to 163+500 in connection 111/Milling First Floor, Sector-28C, with Widening and Strengthening work/84 , Chandigarh of Bikaner-Phalodi Section of NH- Dated 15 in the state of Rajasthan. 30.01.2017 Cont…../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

14 IRCON/2048/ 05.12.2016 Supply, Fixing, Installation, IRCON/2048/ M/s. ESCON Elevators `16,10,000/- `16,10,000/- `15,36,745/- 5 Months ISC-BEHALA Testing, Commissioning of 1 No. ISC-BEHALA Pvt. Ltd. /TENDER/LIFT /2016/33, Machine Room Less Lift/Elevator /TENDER/ EL-116/2, Dated for atleast 8 passengers/544 Kg LIFT/2016/ T.T.C. Electronic Zone, 11.11.2016 capacity with a speed of 1.0m/sec 33/907, M.I.D.C. Mahape, for 4 stops B PLUS G PLUS 2 Dated Navi Mumbai - 400 710 with hairline finish stainless steel 31.01.2017 car as per BOQ for New sports Complex of Eastern Railway at Ghoslapur Behala, Kolkata, W.B

15 IRCON/ 2053 06.12.2016 Construction of one no 12 m wide IRCON/ M/s. Urmila R.C.P. `23.17 Cr. `21.39 Cr. `208049368.33 18 Months /TN/ SHM/ Foot Over Bridge FOB 2053/SHM/ Projects Pvt. Ltd., FOB, Subway & PF/2016/ 30, connecting all the platforms, two SW/Urmila/ Flat No.2/A, Block - 2, Dated nos. RCC Subway and Platform 25420/940 Haldiram Enclave, 02.11.2016 No. 1 Partial stretch at Shalimar Dated VIP Road, Rly. Station in Howrah district for 31.01.2017 Kolkata – 700 059 South Eastern Railway in West Bengal

16 IRCON/MECH/ 16.01.2017 Shipmant of Equipment from IRCON/MEC MSA SHIPPING PVT LTD, ` 50 Lacs Item Rate `48,44,764/- 50 Days PE/SHIPMEN Malaysia to Kasganj(U.P) H/P&E/SHIP 118 H&I,VBMS Towers, T/MAL/EE/544 Dated MENT/MAL/E First Floor, 23.12.2016 E/544 South Raja Street, Dated 3rd Floor, Hawk Tower 31.01.2017 New No 123 Old No 16 TUTICORIN, TAMILNADU – 628 001 Phone: 04614049327, Mob: 9789454320, [email protected] Cont…../- -Works Awarded : FEBURARY 2017

Quantity Rate Scheduled S. Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Tender No. Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. opening And date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ Mech. Date etc Works) etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/3018/ 15.11.2016 Supply of Electronic Total Station IRCON/3018/ M/s Aimil Limited `12,38,940.00 `12,38,940.00 `10,76,288/- 30 Days DFCCIL-CTP- (2) nos. and Auto level (6 nos.) DFCCIL- Naimax House (Surat Section) 12/ST-TS/ SUR-INS/2016 CTP-12/ST- A-8 Mohan /Dated TDR/206 Cooperative Industrial 20.09.2016 Dated Estate 02.02.2017 Mathura Road, New Delhi 2 NIT-04/ST- 07.11.2016 Building & miscellaneous civil IRCON/3018/ M/s MH Khanusia, ` 2,36,26,632.00 `2,36,26,632.00 `2,62,27,284/- 180 Days 2016 work of Ancheli Depot DFCCIL-CTP First Floor Divine India (Surat Section) -12/ST-TDR Bulding, /Civil/204/209 Near RTO Office, Dated Himmatnagar 03.02.17 3 IRCON/3018/ 12.01.2017 Construction of RUB at LC IRCON/3018/ M/s Jalaram Projects `11,87,76,000 `11,87,76,000 `13,01,65,110 14 Months DFCC-CTP- number 65,67,70,72,73,78,89, 96 DFCCIL- Pvt. Ltd. (Surat Section) 12/ST- TDR/RUB/213/ ,99,100,103,104,105,112,116,12 CTP-12/ST- 203 0,121,122,127,131,132,134,136, TDR/RUB/21 &138 of sec-II of Dedicated 3/208 Freight Corridor Project-CTP-12 Dated of Vaitarna - Sachin section of 4.02.2017 Western Dedicated Freight Corridor Cont…../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/2059/ 05.07.2016 Supply, Fabrication, Erection and IRCON/2059/ M/s SPDD Infra Private `1973 Lakh Schd. A – 0.01% `197329515.56 14 Months CGRP/e- Launching of Steel Girders for CGRP/EC16/ Limited, Below including Tender EC16/16/ Major Bridges Km.16.00 to 16/Girders Flat No. 3195, & monsoon Girders Pkg.-II, Km.74.00 (5 nos) in connection Pkg.-II/748, Paradise Enclave Schd. B- At Par period from Dated with new B.G. Electrified double Dated Secr 50D, the date of 25.05.2016 line Railway track in the State of 06.02.2017 Chandigarh – 160 047, issue of LOA Chhattisgarh over South East Ph: 0172-2673195, Central Railway between Chhal M - 9646031286, and Dharmjaygarh 9988763300, spdd [email protected] 5 IRCON/2056/ 06.10.2016 Earthwork in filling in IRCON/2056/ M/s ECI-Nayak (JV), `19378.06 Lakh Schd.-I `2085912526.27 18 Months Agartala- embankment, provision of Agartala- Plot no. A-12-13, `1285845499.60 from the date Akhaura/GMW /Tender/02/EW blanketing material, construction Akhaura/PPP Panchavati Township, of issue of & bridges of viaduct, minor bridges and /Tender/02/ Manikonda, Schd. II- LOA Dated RUB, in the stretch from Km 0.00 EW & Hyderabad – 500 089 `783567026.67 26.07.2016 (Agartala) to Km 5.1 (India- Bridges/ Telangana Bangladesh Border) and 39/32, Ph: 04024786099, & construction of service road from Dated Fax: 04024786100, Schd.-III – transhipment yard to NH-44 in 07.02.2017 Email: [email protected] ` 1,65,00,000/- connection with construction of new B.G. Railway line from Agartala (India)- Akhaura (Bangladesh) 6 IRCON/3018/ 20.01.2017 Construction of RUB at LC IRCON/3018/ M/s Rajasthan Const. `4,60,97,874 `4,60,97,874/- `5,19,91,948/- 14 Months DFCC-CTP- number 44,45,46,47,49,50, DFCCIL- Pvt Ltd. 12/02 53,54,59 and 63 of section II of CTP-12/672 Dedicated Freight Corridor Dated Project-CTP-12 of Vaitarna- 16.02.2017 Sachin section of Western Dedicated Freight Corridor

Cont…../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

7 IRCON/2062/ 25.01.2017 Supplying and stacking of IRCON/2062/ M/s Gulzar Singh & Co. `79,015 Cum. `1,785/- / cum `14,10,41,775/- 06 Months NMDC/NISP/ machine crushed stone ballast of NMDC/NISP/ Geedam Road, RLY.SIDING/ e-Tender/ 50mm size 65mm to 20mm well RLY.SIDING/ Jagdalpur, Bastar, Ballast/9, graded for Railway track as per Ballast/9/45, Chhattisgarh – 494 001, Dated relevant RDSO specification in Dated Ph:07782-222252, 11.01.2017 connection with Construction of 16.02.2017 [email protected] Private Railway Siding for NMDC’s Integrated Steel Plant at Nagarnar near Jagdalpur in Chhattisgarh 8 IRCON/2065/ 16.01.2017 Geotechnical investigation IRCON/CO/ M/s Jindal Consortium As per BOQ on Item rate `69,15,229.70 06 months KTE-SGLR/ including drilling of bore holes, 2065/Katni- SCF-9, Vikash Vihar item rates basis inclusive of 15% from the JGM/JBP/ TENDER/GEO collecting samples, testing of Singrauli/PP Ambala City, service Tax date of TECH-1/ sample in laboratory/field in the P/Geo-tech- PIN – 134 003 issue of Dated: stretch from New Katni Jn. to I/40/60 Haryyana LOA 21.12.2016 Beohari station(112Km), both Dated Email: (Corrigendum- 1 Dated inclusive, in connection with 17.02.2017 [email protected] 10.01.2017). construction of doubling of Railway line in between Katni- Singrauli of West Central Railway 9 e-Tender/ 17.01.2017 Execution of Miling Work of IRCON/1034/ M/s Singla 450000 sqm/ Item rate for `14700000/- 10 months IRCON/1034/ existing Asphalt Pavement where BPHP/TN/ Constructions Ltd., `18200000/- individual item/ from the BPHP/TN/NIT st ET-111 everrequired between Km 4+200 NIT ET- SCO, 22/23, 1 Floor, `14700000/- date of to 163+500 in connection with 111/Milling Sec-28C, Chandigarh. issue of widening & strengthning of work/136, LOA Bikaner-Phalodi Section of NH- Dated 15 in the State of Rajasthan. 18.02.2017 10 IRCON/1034/B 13.01.2017 Construction of Administrative IRCON/1034/B M/s Kartikye Individual 4.17 % above `2,33,60,326.36 6 months PHP/TN/NIT Building and other Facilities at PHP/Toll Constructions, quantity for from Cost put to from Date ET-106 Toll Plaza -3 near Km 84+500 of Plaza-1/NIT 280, Sector-15, Pat-1, individual item/ tender/ of issue of Bikaner-Phalodi Section of NH- ET-106/146, Delhi-Jaipur Road, `.2,24,25,197.25 `2,33,60,326.36 LOA 15 in the state of Rajasthan Dated (NH-8) 23.02.2017 Gurgaon – 122 001, kartikyeconstructionsg mail.com Cont…../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

11 IRCON/1034/ 14.01.2017 Providing & Relocation of IRCON/1034/ M/s Sarjan Individual (-) 5.05% Below `2,83,75,239.70 3 months BPHP/ TN/NIT Existing Air Force Water Pipe BPHP/ Infratech,1,Rajnagar quantity for from estimated from Date ET-109 Line between Km 4.200 to Km TN/WATER Society, Jail Road, individual item/ cost of issue of 12.800 along Project Highway PIPE LINE Mehsana-384002, ` 2,98,84,402. /`2,83,75,239.70 LOA on NH-15, in connection with /NIT ET- Ph:9879204243, Widening of Bikaner Phalodi 109/147, sarjan.infratech@ Highway in the State of Dated gmail.com Rajasthan (PACKAGE:BPHP/ 23/02/2017 WUS-AF-NAL) 12 IRCON/e-TN/ 27.12.2016 Providing and fixing plumbing IRCON/e-TN M/s. Sacred `106.87 Lacs Item rate `116.16 Lacs 26.10.2017 Plumbing_Ret and sanitary works for Retail Mall /Plumbing Constructions Pvt. Mall_NOIDA_ 43/16/Pkg. at Plot No. A-267/1-4, Sector-43, _Ret Mall_ Ltd., AN-29B, VIII/ NOIDA (U.P.) - Pkg. VIII NOI DA_43/ Shalimar Bagh,Delhi- Dated 16/Pkg.VIII/ 110088, 06.12.2016 330/Dated 27.02.2017 13 IRCON/e-TN/ 27.12.2016 Providing and fixing external IRCON/e-TN/ M/s. Sacred `347.35 Lacs Item rate `333.48 Lacs 27.09.2017 Ext finishing works including Ext Finishings Constructions Pvt. Finishings_ Ret structural glazing & stone _Ret Mall_NOI Ltd., Mall_NOIDA_ cladding works for Retail Mall at DA_43/16/Pkg AN-29B, Shalimar 43/16/Pkg. Plot No. A-267/1-4, Sector-43, . IX/332 Dated Bagh, IX/Dated NOIDA (U.P.)-Pkg. IX 28.02.2017 Delhi – 110 088 06.12.2016 14 IRCON/e-TN/ 27.01.2017 Interior finishing works for Retail IRCON/e- M/s. Quazar `744.50 Lacs Item rate ` 610.19 Lacs 26.10.2017 Int Finishing_ Mall at Plot No. A-267/1-4, TN/Int Infrastructure Private Ret Mall_NOIDA_ Sector-43, NOIDA (U.P.)-Pkg. X Finishing_Ret Limited , B-64, 43/16/Pkg. Mall_NOIDA_4 Chattarpur Enclave , X/Dated 3/16/Pkg. Phase-II, 03.01.2017 X/331/ Dated New Delhi – 110 074 28.02.2017 Cont…../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

15 IRCON/ 2048 / 24.11.2016 Fire Fighting, Fire detection, Fire IRCON/ M/s. S.K. Construction, `1.6 Cr. `1.60 Cr. `1,19,79,200.00 5 Months ISC-BEHALA/ alarm system and related works 2048/ISC- 1167, Purba Diganta, TENDER/ FIRE/ 2016/21 as per BOQ for New Sports Behala/Fire 2nd Floor, Dated Complex of Eastern Railway at Fighting/ Kolkata – 700 075. 26.10.2016 Gholsapur (Behala), Kolkata, SKC/25416/1 W.B. 004A Dated 28.02.2017 16 IRCON/J&K- 22.12.2016 Engagement of vehicles for IRCON/J&K- M/s. Dreamland ` 26,55,264/- 3.99% above `27,61,209/- 12 months Cell/JAT/14/10 Officers and Staff working in the Cell/JAT/14/1 Travels. than the from 14/K-B/Hiring Veh-Jammu/ office of the Executive 014/K- Shop No. 9, tendered value 01.03.17 354, Director/IRCON, USBRL Project, B/HiringVeh- General Bus Stand, Dated Jammu (J&K) (Package no. VH- Jammu/354/1 Jammu 21.11.2016 22) 719 Dated 28.02.2017 17 IRCON/J&K- 27.01.2017 Fabrication, Supply, Erection and IRCON/J&K- M/s. The Braithwaite `662127429.67 58.70% Above `1050796231/- 36 months CELL/JAT/14/ completing of Superstructure for CELL/JAT/14 Burn & Jessop than the from the 1014/K-B/ Br. 2, 3 & 61/ 362/ Bridge no.2 & 3 (In Sumber /1014/K-B/ Construction Co. Ltd., tendered value date of 8644 Station Yard) and Bridge no. 61 Br. 2, 3 & 61/ 27, Rajendra Nath issue of Dated (over Tatsun Nallah) on Katra- 362/ 8644 Mukharjee Road, LOA 05.01.2017 Qazigund Section of Udhampur- Dated P.O.Box No. 264, Srinagar-Baramulla New BG 28.02.2017 Kolkata – 700 001 Railway Line Project. (Package: (WB) Bridge- 2, 3 & 61) 18 IRCON/CC/TN 11.01.2017 Geotechnical investigation IRCON/2046/ M/s Arihant Drillings `460.81 Lacs 20.50% Below `36634395.00 4 Months /SR-2046/ including drilling of Boreholes, Sivok- Pvt. Ltd. 142/1, Adarsh Addl. GT/16/03 Dated testing of samples, seismic Rangpo/Addl. Nagar, Gurgoan- 20.12.2016 refraction etc. from Km 00+000 to GT Invest./ 122001, Haryana 45+000 for construction of Sivok 58/675 (West Bengal) – Rangpo (Sikkim) Dated New Single Line BG Rail Link 28.02.2017 Project.