Report No. PID5674

Project Name China - Power Development Project (@)

Region East Asia and Pacific

Sector Energy and Mining Development

Public Disclosure Authorized Project ID CN-PE-35698

Borrower People's Republic of China

Implementing Agency Hunan Electric Power Company (HEPC) Mr. Yu Xingqiang 64 Road, Hunan 410007, People's Republic of China Tel: 86-731-554-3115 Fax: 86-731-554-3182

Date PID Updated March 24, 1998

Indicative Schedule:

Public Disclosure Authorized Project Preparation October 1997 Pre-appraisal January 1998 Appraisal March 1998 Negotiation May 1998 Board Presentation June 1998

Sector and Institutional Background

1. Large-scale energy development and improvements in the efficiency of energy supply and use are critical to meet the fast growing demand, alleviate shortages and mitigate adverse impacts on the environment in China. China has experienced an annual growth rate of about 8.3 percent in installed capacity and energy generated in the period 1980-95. To meet the electricity demand in Public Disclosure Authorized the most cost-effective manner, the Government is implementing a comprehensive strategy of sectorwide institutional reforms, energy price reforms, and encouraging energy conservation. Consumer prices for the major forms of energy now largely reflect economic costs. A well-developed institutional network exists to promote energy conservation at the central, provincial and local levels. These measures have helped China achieve a remarkably low 0.86 elasticity demand growth to GDP growth during 1980-95. 2. Yet even with further improvements in conservation, generation capacity must increase by about 15 GW a year for the next five years if current shortages are not to become more acute. For continued efficiency improvements -- not simply in energy use but in the overall functioning of the sector -- and for the increased capital mobilization necessary for large-scale power industry development, China has launched an ambitious program of power sector reforms. Thus far, progress has been made in sector decentralization, cost recovery through major tariff reforms, and diversification of financing Public Disclosure Authorized sources, including development of a variety of independent power generation schemes. In the gradual process of legal reform and sector restructuring, three important steps have recently been taken, with passage of the country's first Electricity Law, a decision to abolish the Ministry of Electric Power and divide its functions among existing government agencies, and a further decision to create a State Power Corporation to, inter alia, represent the state as owner of government-owned power assets. Furthermore, several joint venture companies have been established to build power plants in Shandong Province and , while build, operate, transfer (BOT) schemes have been introduced in Guangdong and Fujian Provinces. The process of international competitive tendering for projects has also begun with the Laibin B project in Guangxi Zhuang Autonomous Region, which will be constructed by an international consortium, and bids are being evaluated for Changsha power project in Hunan Province. 3. Building on these accomplishments, the Government's future agenda for action includes: (a) further reforms to the sector's regulatory and legal framework; (b) further diversification in financing for power development, including private sector participation; (c) institutional restructuring via commercialization and corporatization of power companies, together with achievement of greater enterprise autonomy and sector restructuring; and (d) further measures to rationalize power tariffs. While actions have been initiated on all of the above fronts, measures to commercialize the power entities are now a focal point in the overall effort. These measures include separating the producing entities from the Government, granting them autonomy in business decision-making, and subjecting them to market forces in an arms- length regulatory framework. 4. The Chinese approach to reform encourages experimentation with different reform options and institutional forms. This gradual approach permits the Chinese to examine the relevance and applicability of specific reforms and also to fine-tune reform implementation for broader dissemination or replication in other parts of the country. 5. Accompanying the move to commercialization are efforts to curb air pollution related to the burning of coal and particularly to reduce the power sector's contribution to the problem. In terms of emission control in large and medium-scale plants, China has made substantial progress in particulate control, through deployment of high efficiency electrostatic precipitators. The Government announced in June 1994 that it would spend about $2 billion over the next seven years on an environmental program aimed at keeping S02 emissions at a level of 15 million metric tons a year, as part of a comprehensive program of acid rain abatement. The Government intends also to accelerate the development of hydropower and construction of large and efficient 300 and 600 MW coal-fired units to avoid the mushrooming of the small, highly polluting plants that still constitute about 60 percent of the additional installed capacity.

The Hunan Power Grid - Area of Project Impact

6. Hunan province, where the proposed project is located, is the seventh- most populous province in China with a population of 63.5 million at the end of 1995. It is bordered by Sichuan and Guizhou in the west, Guangxi and Guangdong in the south, Jiangxi in the east, and Hubei in the north. Although it has abundant nonferrous mineral resources and is China's lead rice producer, Hunan remains one of the country's poorest provinces. In 1995, its per capita gross domestic product (GDP) was 3,456 Yuan, about 28 percent lower than the national average. The province was nevertheless experiencing impressive growth in the past five years. From 1990 to 1995, the average annual growth rate of GDP of the province was 12 percent. For the same period, the average annual growth rate of energy consumption was 8.98 percent. The peak demand in 2005 is expected to be around 12,700 MW and demand for

-2 - energy generation 69.8 TWh based on an annual average growth rate of 8.4 W and 7.7 ', respectively. 7. The Hunan Power Grid (HPG) is an important part of the Central China Grid (CCG), located in the south of the Central China Grid. CCG covers Henan, Hubei, Jiangxi, and Hunan Provinces. HPG is connected with CCG through two transmission lines, one 500 kV line to Gezhouba hydro power station and one 220 kV line to Fengfanshan substation in , Hubei. 8. By the end of 1995, HPG had a total installed generating capacity of 7,755.5 MW, of which 3,544.2 MW coal-based (45.7%) and 4,211.3 MW of hydropower (54.3%). The peak load was 5,554 MW and the total electricity supply (including energy exchanges) was 33,934 GWh. The net power import from other provinces was 890 GWh. Electricity consumption per capita was 530 kWh, about 65.6 percent of the national average. The provincial power sector is plagued by acute power shortages: in 1995, load was shed (35kV and above switches) about 3,968 times. The minimum daily load was about 70 percent of the maximum daily load, much higher than the ratio of 50-60 percent in developed countries. This indicates important load shedding and suppressed demand in the system. Shortages were estimated at about 3,000 GWh in 1995. Moreover, the elasticity of electricity consumption growth relative to GDP growth in Hunan was only 0.84 from 1991 to 1995, an exceptionally low elasticity which is not sustainable to support the economic development in the province. 9. To remedy the situation, Hunan needs to (i) accelerate the installed capacity for both peak and base loads to ensure sufficient and reliable electricity supply for the anticipated economic growth; (ii) construct large size and high efficient coal-fired power plants to improve the system's capacity during the dry season; (iii) construct mine mouth power plants to take advantage of the rich and cheap anthracite resources in Hunan and reduce the pressure on the overburdened railway system; (iv) retrofit the small thermal units or replacing them by larger, more efficient, and less polluting plants; and (v) optimize harnessing of the hydropower resources to ensure an environmentally sustainable development of the power sector. 10. The transmission system in 1995 has a total length of 13,373 km, consisting of 669 km of 500 kV lines, 4,653 km of 220 kV lines, and 8,051 km of 110 kV lines. HEPC owns and operates almost the whole transmission system. The system also includes transformer substations, with a total capacity of 22,083 MVA. 11. The existing transmission network is experiencing problems of reduced reliability, overloading of major substations and lines, and higher fault levels at 220 kV systems exceeding the permitted safe operating ranges. These problems are mainly caused by an inadequate investment in the transmission systems required to transmit the new production to load centers. Most generation projects only have enough transmission capacity to connect the plant to the nearest point on the system. Reinforcement of the core transmission system is urgently required Project Development Objectives and Description 12. The Project's development objective is to remedy power shortages in Hunan by providing efficient, reliable, and environmentally sound power supply. This project also supports the Country Assistance Strategy for China to alleviate infrastructure bottlenecks in an interior province to foster integrated economic development in Hunan. The Project objective would be achieved by: (a) development of two 300 MW anthracite-fired generating units at the Leiyang Power Plant to alleviate power shortage, improve the generation mix in a system dominated by seasonal hydro power, and facilitate the retirement of

-3 - about 10 small, aging, inefficient, and polluting generating units in the provincial power grid;

(b) reinforcement of the existing 220 kV transmission systems - supply and installation of about 794 km of 220 kV lines and 1,920 MVA of transformer substations capacity. These lines will connect Leiyang Power Plant Phase II and competitively bid BOT Changsha Power Plant (2x350 MW) to HPG and reinforce the transmission system in order to supply the increasing demand in a reliable, economic, and efficient manner;

(c) provision of technical assistance for construction management of Leiyang Power Plant phase II;

(d) provision of technical assistance for preparation of commercial power purchase agreements and other relevant documentation;

(e) provision of technical assistance for implementation of HEPC's restructuring plan, including incorporation of generation and transmission/distribution companies, and incorporation of future Leiyang Power Plant; and

(g) provision of technical assistance for improvement of the financial management system. Financing Plan

Million US $

IBRD 300.0 HEPC 149.7 China Construction Bank 148.8 State Development Bank 148.7 Total 747.2

Institutional and implementation arrangements

13. The beneficiary, Hunan Electric Power Company (HEPC), will be the executing agency for the project. The overall management of the project will be carried out by HEPC. HEPC has been operating the Hunan Power Grid for more than twenty years and has qualified personnel to undertake project preparation, implementation and operation. In addition, it has had operating experience with anthracite fired units (200 MW and below) for more than ten years. To facilitate effective project implementation, HEPC has set up a Project Implementation Unit with full-time staff, headed by the deputy chief engineer. Moreover, the Hunan Provincial Electric Power Design Institute (HPEPDI) with assistance by international engineering consultants will undertake preparation of technical bidding documents, bids evaluation, detailed construction design with the assistance of international consultants and a Chinese expert group. Project preparation and future implementation is being coordinated by a steering committee chaired by HEPC's vice president in charge of overall project management and coordination, reform and financial issues. The institutional reform elements of the proposed project will be supervised by the Ministry of Electric Power (MOEP) and/or its successor entities (i.e. State Economic and Trade Commission and State Power

- 4 - Corporation). The State Power Corporation will be responsible for obtaining State Council approvals on major reform issues. The provincial government representatives will oversee the planning and implementation of resettlement. Benefits and Target Population 14. The Project would have a marked impact on the economic development of Hunan province. The direct benefits attributable to the project are: (a) reduction in the value of lost production due to power rationing and load shedding; (b) improvements in quality of supply in terms of reduced interruptions and recognized but more difficult to quantify service parameters, such as, frequency, voltage, reactive energy; and (c) improvements in local air quality with retirement of older polluting generating units. 15. The other major benefit of the project is the implementation of the sector reform plan and increased commercial orientation of HEPC. The development of a competitive commercial framework for purchase of power from all generating units on the system will be conducive to economic dispatch and overall generation efficiency. The clear separation of the generation from transmission and distribution will provide a framework to promote competition at generation level and private investments in power generation. The proposed project would therefore benefit all power consumers in Hunan province. Environmental Aspects

16. In accordance with OD 4.01 (Environmental Assessment), the project has been assigned Category A. The Environmental Assessment (EA), was prepared as two separate reports: Part A the Leiyang Power Plant, and Part B the Transmission System. Both Parts were prepared by a team consisting of international consultants specializing in environmental issues related to thermal power plants and transmission lines and the Electric Power Research Institute (NEPRI). For the power plant, the international consultant took the lead role in EA preparation and for the transmission line, NEPRI assumed the lead role. The EA document has been approved by the National Environmental Protection Agency (NEPA) and has been reviewed and approved by the World Bank; it is considered that all environmental aspects of the project are satisfactorily addressed and in compliance with all Chinese and World Bank environmental policies and procedures. Because of the unusual characteristics of the fuel to be used, some deviation to existing World Bank nitrogen oxides (NOx) emission guidelines and Chinese ambient NOx standards were established, thermal discharges from once through cooling water also exceed Chinese standards. However, the EA analysis determined that the environmental consequences of these variances were insignificant. A monitoring program will be incorporated into the project to ascertain and verify these conclusions on a sustained basis. Should additional mitigation be required, the Borrower has agreed to take the appropriate measures. 17. Key issues addressed in the EAs included: air pollution (dust, sulfur dioxide, nitrogen oxides), water pollution (primarily thermal pollution impacts to aquatic ecology in the Leishui River), ash management, worker health and safety (including the mine supplying the coal), electric field, noise, losses in land productivity, interferences with communications and bird flight patterns, and influences of construction and operational labor forces on the local infrastructure. Furthermore, the proposed project (2 units of 300 MW each) is the second phase of what might be a three phase program at the Leiyang site. To avoid future adverse environmental consequences, the EA examined both the immediate impacts of the subject project (600 MW) as well as cumulative impacts including a possible third phase (2x600 MW). 18. All mitigating measures for air, water, and solids management (coal, ash) are designed to meet appropriate Chinese requirements and/or World Bank

- 5 - guidelines whichever is stricter. In the absence of either, international codes of practice will be used (as is the case for nitrogen oxides emissions). Resettlement Aspects

19. The resettlement for the proposed project will be carried out in two phases. The first phase includes: (a) policies and regulations, institutional arrangements, implementation procedures that would be applied to all components of the proposed project; and (b) detailed resettlement plans for (i) Leiyang Power Plant; (ii) four 220 kV substations (Furong, Dongfenghu, Hengbei, and Wangcheng); and (iii) two sections of 220 kV transmission lines (Huaneng Power Plant to Dongfenghu, and Macha to Hengbei). The second phase includes resettlement activities related to five 220 kV substations and 18 sections of 220 kV transmission lines. A Resettlement Action Plan (RAP) has been prepared for the first phase. The RAP for the second phase will be prepared by March 1999 following the completion of the design of routing and siting of these subcomponents. 20. The Bank carried out full review of the RAP and the assessment found that the resettlement needs and PAPs are well analyzed and mitigating measures of adverse social impacts are thoroughly formulated and adequate. The second phase RAP and any unforeseen resettlement associated with the project will be carried out according to the policy and procedures established in the first phase RAP. 21. Minimization of the scope of resettlement was, and will continue to be a high priority throughout the planning, design and implementation of the proposed project. Where land acquisition and demolition are unavoidable, the resettlement plans provide for replacement of housing, alternative employment opportunities, infrastructure, services and other resources to improve, or at least restore, the living conditions and income of the project affected persons (PAPs). Special attention was given to the most vulnerable groups (household headed by women, senior people, and poorest households). 22. The project (including two phases) would (a) require acquisition of 1,097.5 mu (about 73 ha) of land; (b) affect 396 persons due to land loss; (c) demolition of 100,145 square meters of floor spaces in rural and urban areas; and (c) relocation of 266 households or 1418 persons. The first phase components require acquisition of a total of 438.5 mu land area, affecting 108 people; demolishing 15,941 square meters of floor spaces, and relocating 175 households or 993 individuals. Based on a preliminary estimate, the remaining project components will require acquisition of 659.0 mu land area, affecting 289 farmers; removing 84,204 square meters structures, and relocating 91 households or 425 individuals. 23. In order to effectively implement the resettlement program, resettlement offices were established at the provincial, city, county, and power supply bureaus levels. To strengthen the resettlement offices' implementation capabilities, a resettlement policy and implementation workshop will be conducted for staff involved in the resettlement activities. Contact Point: The InfoShop The World Bank 1818 H Street, N.W. Washington, D.C. 20433 Telephone No. (202)458 5454 Fax No. (202) 522 1500

Note: This is information on an evolving project. Certain activities and/or components may not be included in the final project.

- 6 - Processed by the InfoShop week ending March 27, 1998.

-7 -