Environmental Impact Assessment System of the Tokyo Metropolitan Government

An Environmental Impact Assessment (Environmental Assessment) system is a framework to estimate and minimize the possible impact that a proposed project will have on the environment. Prior to a decision being made on a major development project, an environmental impact assessment (EIA) is conducted to estimate and evaluate the likely in uence the project may have on the environment and review how to minimize the impact. The result of the assessment is made open to the public and comments are invited from local residents and relevant municipalities. It is also reviewed from the expert’s point of view.

Pollution and loss of the natural environment may impair people’s health and comfort. Sometimes it is difcult to restore the original natural environment. To preserve a sound natural environment, it is important to put proactive and preventive measures into effect, including the EIA system.

Since October 1981, the Tokyo Metropolitan Government has implemented environmental impact assessment procedures before making decisions on projects larger than a certain scale, in accordance with the Tokyo Metropolitan Environmental Impact Assessment Ordinance. The procedures are designed to ensure that such projects incorporate reasonable considerations on the prevention of pollution, preservation of the natural and historical environment, and maintenance of the landscape.

In July 2002, TMG revised the ordinance to specify that an environmental impact assessment procedure must be followed in the planning phase for projects larger than a specied scale. Basic Procedures Required in the Tokyo Metropolitan Environmental Impact Assessment Ordinance

Environmental Assessment procedure for planning Environmental Assessment Follow-up survey procedure * Only for a TMG project procedure for projects Within 45 days of the date of Within 20 days of the date of Within 45 days of the date of the public announcement the public announcement the public announcement Written Written Written opinions opinions opinions of Tokyo Residents the publicthe of the plan Participation Participation Participation Participation Announce to Announce Public inspection Public Public inspection Public inspection Public Restriction on project implementation Public inspection Public Submission Submission Submission Announce to the public the to Announce public the to Announce public the to Announce Announce to the public the to Announce Public announcement Public Announce to the public the to Announce examination reportexamination Respect the Governor’s the Respect and project) (EAR) Report Planning meeting meeting draft EAR Opinions of Opinions Selection of Businesses Environment Survey Plan Explanatory Explanatory Environmental Environmental Consideration organizations businesses and businesses and Assessment items Send Send (during project works) Assessment Report Follow-up survey plan Draft Environmental Environmental Environmental Completion statement Completion organizations on the (after completion of the the of completion (after Project StartProject Statement Follow-up survey report Follow-up survey report Noti cation Participation Noti cation Assessment ReportAssessment Report Submission Submission Submission Submission Submission Submission Submission Submission Submission Submission (10 days) of likely of residents Governor’s Governor’s (30 days) Governor affected areas affected (15 days) Governor’s statement statement to be informed be to determination survey plan and Make public the the public Make affected areas affected the draft EAR draft EAR and public inspection public Make public the public Make Planning-phase Planning-phase Report on the survey plan Report Make public the the public Make examination report examination of completion completion of and organizations and Decision on areas Make public the public Make Tokyo residents Tokyo report and make it make it available for public inspection public available for public for available Meeting to hear the hear to Meeting consideration reportconsideration inspection (30 days) opinions from Tokyo from opinions determination of likely likely of determination business’s opinion business’s available for public public for available Implementation-phase hear opinions from opinions hear make it available for inspection (20 days) of the project start Town hallTown meeting to Governor’s examination examination Governor’s examination report on for public inspection public for report and make them Make public the EAR and make it available Town hallTown meeting to hear report on the environment opinions from businesses from opinions Public announcement Public announcement Public environment consideration consideration environment as necessary as Report Provide opinions Provide opinions Provide Ask for comments for Ask Consult Consult Ask for Consult necessary Noti cation comments as comments Send copies/RequestSend Participation (Participation) (Participation) environment considerations environment Council Council Council Council Council Council Council Council Council

★ The Governor may ask for the Council’s opinion and examine details of the reports if necessary. When it is deemed that the project in question is likely to have serious impacts on the environment, the Government shall request immediately that the business and organization or issuer of the license or approval take or approval or or approval or necessary measures. Issuers of license Issuers of license Opinions Opinions Opinions municipal

governments Standard time period needed Standard time period needed Heads of related Heads of Standard time period for the Governor to process: Standard time period for the Governor to process: for the Governor’s actions: for the Governor’s actions: Approx. 180 days Approx. 45 to 60 days Approx. 70 days Approx. 70 days

1 Environment Consideration Report 4 Holding a town hall meeting to hear opinions from 6 Draft environmental assessment report (EAR) 9 Request considerations of issuers of the license Upon planning a project, the relevant business and organization shall Tokyo residents Based on the survey plan, businesses and organizations shall prepare or approval prepare an environment consideration report, describing the The Governor shall host a town hall meeting to hear opinions from the a draft EAR. The report shall be made open to the public and be The Governor shall request that issuers of the license or approval applicable environmental plans. The environment consideration report residents of Tokyo on the environment consideration report and on available for public inspection for 30 days from the date of the public should pay due consideration to the contents of the EAR in issuing the shall be made open to the public and be available for public the draft EAR. Members of the Environmental Assessment Advisory announcement. When a project is implemented in a speci ed area license or granting approval for implementing the project. inspection for 30 days from the date of the public announcement. Council may participate in the meeting to listen to the residents’ opinions. designated by the Governor, the project assessment procedure begins with the draft EAR process. 10 Procedure for follow-up survey 2 Explanatory meeting 5 Survey plan When the work starts, the business and organization shall report the start The relevant business and organization shall hold explanatory Businesses and organizations engaged in the relevant project shall 7 Business’s opinion report and submit a plan for conducting a follow-up survey (a follow-up survey meetings during the public inspection period, to inform residents of prepare a survey plan, describing methods for surveying, predicting The relevant business and organization shall prepare “business’s opinion plan). After the start of the work, the business and organization submit a the contents of the environment consideration report and the draft and assessing likely impacts on the environment of implementing the report” to express its views on the opinions of the residents on the draft follow-up survey report (during construction) and upon completion of the environmental assessment report (EAR). project. The survey plan shall be made open to the public and be EAR. The comments shall be made public and be available for public construction, the business and organization shall report the completion available for public inspection for 10 days from the date of the public inspection for 20 days from the date of the public announcement. and submit a follow-up survey report (after completion). 3 Submission of residents’ opinions announcement. The procedure for the survey plan may be omitted if Residents of Tokyo may submit opinions from the viewpoint of the project has already been undergone the EIA in the planning phase 8 Environmental assessment report environmental preservation within a certain period of time, concerning and speci ed procedures. The environmental assessment report shall be made public and be the environment consideration report, the survey plan and the draft available for public inspection for 15 days from the date of the public EAR. Opinions can be brought in personally or submitted by mail or announcement. e-mail.

* Procedures for special environment consideration reports are different from the standard procedure.

1 2 Types and requirements for relevant projects The table below shows types and requirements of relevant projects (Environmental Assessment Procedure for project) and individual plans and individual plans (Environmental Assessment Procedure for planning) required by the Ordinance.

Outline of requirements for a relevant project Outline of requirements for an Outline of requirements for a relevant project Outline of requirements for an Type of project Type of project (description and size) individual plan (description and size) (description and size) individual plan (description and size)

National expressway or motor highway: Factories or facilities associated with manufacturing*: Factories or facilities associated with manufacturing*: [Construction] (1) Lot area of 9,000 m2 or larger [Construction] (1) Lot area of 18,000 m2 or larger [Construction] All (2) Building area of 3,000 m2 or larger (2) Building area of 6,000 m2 or larger [Renovation] (1) Additional lanes [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] (2) New road construction (1) Lot area increase of 4,500 m2 or larger and lot area after expansion (1) Lot area increase of 9,000 m2 or larger and lot (3) Relocation to underground, elevated or other locations 1 km or of 9,000 m2 or larger area after expansion of 18,000 m2 or larger (4) Renewal of facilities for elevated roads or bridges 1 longer (2) Building area increase of 1,500 m2 or larger and building area after (2) Building area increase of 3,000 m2 or larger and (only when removal of bridge pier, abutment or Construction or expansion of 3,000 m2 or larger floor space after expansion of 6,000 m2 or larger beam is involved) 1. renovation of roads Construction or [Facility renewal] (1) Removal of the whole existing facility and lot area of new factory of [Facility renewal] (1) Removal of the whole existing facility and lot Other types of roads (with 4 or more lanes): 9,000 or larger area of new factory of 18,000 or larger 1 modification of [Construction] 1 km or longer Other types of roads (with 4 or more lanes): 8. (2) Partial removal of the existing facility, lot area increase of 4,500 m2 (2) Partial removal of the existing facility, lot area [Renovation (addition of lanes, etc.)] 1 km or longer1, 2 [Construction] 2 km or longer manufacturing 2 2 2 or larger and lot area after facility renewal of 9,000 m or larger increase of 9,000 m or larger and lot area after 1. Even when the length to be constructed or renovated is less than 1 km, if the work is conducted as a part of, [Renovation (addition of lanes, etc.)] 2 km or longer factories (3) Building area of new facility of 3,000 m2 or larger (excluding facility renewal of 18,000 m2 or larger or as an extension to, a relevant project, it shall be subject to the procedure. 2. Renovation of other roads extended to 4 or more lanes should be projects subject to (4)) (3) Building area of new facility of 6,000 m2 or 2. Renovation of other roads extended to 4 or more lanes should be included. included. (4) Building area increase of 1,500 m2 or larger and total building area larger (excluding projects subject to (4)) after facility renewal of 3,000 m2 (4) Building area increase of 3,000 m2 or larger and 2 * Those owning facilities generating smoke or facilities generating ordinary and specified particulates total building area after facility renewal of 6,000 m Dam: designated in the Air Pollution Control Act, or those owning specified facilities designated in the Water * Those owning facilities generating smoke or facilities generating ordinary and Pollution Prevention Act, Noise Regulation Act or Vibration Regulation Act. specified particulates designated in the Air Pollution Control Act, or those [Construction] Height of 15 m or more and surface area of 75 ha or more owning specified facilities designated in the Water Pollution Prevention Act, Weirs: Noise Regulation Act or Vibration Regulation Act. Construction or [Construction] Surface area of 75 ha or more renovation of [Renovation] Surface area increase of 37.5 ha or more and surface area of 75 ha or [Construction] (1) Lot area of 5 ha or larger [Construction] (1) Lot area of 10 ha or larger dams, lake water more after renovation (2) Sludge treatment capacity (in solid material) of 100 t/day or greater (2) Sludge treatment capacity (in solid material) of 2. level control Lake water level control facilities: [Expansion (excluding projects subject to facility renewal)] 200 t/day or greater [Construction] The total area of land for installing the facility and the maximum horizontal (1) Lot area increase of 2.5 ha or larger and lot area after expansion of [Expansion (excluding projects subject to facility renewal)] facilities, discharge project area of the bottom is 75 ha or larger. 5 ha or larger (1) Lot area increase of 5 ha or larger and lot area channels or weirs Discharge channel: Discharge channel: (2) Sludge treatment capacity increase of 50 t/day or greater and after expansion of 10 ha or larger sludge treatment capacity after expansion of 100 t/day or greater (2) Sludge treatment capacity increase of 100 t/day [Construction] A river area with a width of 30 m or wider and a length of 1 km or longer; [Construction] A river area with a width of 30 m or wider [Facility renewal] (1) Removal of the whole existing facility and lot area of new sewage or greater and sludge treatment capacity after or a project that entails a change in the figuration of land of 75 ha or more and a length of 2 km or longer Construction or treatment plant of 5 ha or larger expansion of 200 t/day or greater modification of (2) Partial removal of the existing facility, lot area increase of 2.5 ha or [Facility renewal] (1) Removal of the whole existing facility and lot area 9. sewerage larger and lot area after facility renewal of 5 ha or larger of new sewage treatment plant of 10 ha or larger Railways, transport vehicle guideways and monorail track: Railways, transport vehicle guideways and treatment plants (3) Construction area of new facility of 5 ha or larger (2) Partial removal of the existing facility, lot area [Construction] All monorail tracks: (4) Sludge treatment capacity of new facility of 100 t/day or greater increase of 5 ha or larger and lot area after (excluding projects subject to (5)) facility renewal of 10 ha or larger [Renovation] (1) Addition of rail tracks [Construction] All projects excluding Shinkansen railways Construction or (5) Sludge treatment capacity increase of 50 t/day or greater and (3) Construction area of new facility of 10 ha or larger (2) Relocation to underground and to elevated lines, [Renovation] 2 km or longer (Addition of rail tracks, etc.) renovation of sludge treatment capacity after facility renewal of 100 t/day (4) Sludge treatment capacity of new facility of 200 t/day other forms of relocation 1 km or (Excluding renovation relating to or greater or greater (excluding projects subject to (5)) 3. railways, transport (3) Renewal of rail tracks or bridges on an elevated line or longer* Shinkansen railways.) bridge piers (only when removal of bridge pier, (5) Sludge treatment capacity increase of 100 t/day vehicle guideways or greater and sludge treatment capacity after and monorail tracks abutment or beam is involved) * Even when the length of the extension to be renovated is less than 1 km, if the work will be conducted as a facility renewal of 200 t/day or greater part of, or as an extension to, a relevant project, it is subject to the procedure. Garbage-disposal facilities: [Construction] Treatment capacities of each type of disposal facilities is 200 t/day or more Land airports, etc. and heliports: [Expansion (excluding projects subject to facility renewal)] Land airports, etc. and heliports: Treatment capacity increases of each type of disposal facilities is 100 t/day [Construction] All Construction or [Construction] All or more, and disposal capacity after expansion of 200 t/day or more [Facility renewal] All (only when all existing facilities are [Facility renewal] All (only when all existing facilities are removed) [Facility renewal] (1) Treatment capacities of each type of new disposal facilities is 4. modification of removed) airports/airstrips Airstrips: 200 t/day or more (excluding projects subject to (2)) [Construction and change of location] All Airstrips: (2) Treatment capacity increases of each type of disposal facilities is [Extension] Projects involving change of class, etc. [Construction and change of location] All 100 t/day or more, and disposal capacity after facility renewal of 200 t/day or more Night soil disposal plants: Power plants: [Construction] Treatment capacity of 100 kl/day or more [Construction] Thermal: 112, 500 kw or more [Expansion (excluding projects subject to facility renewal)] Hydraulic: 22,500 kw or more Treatment capacity increase of 50 kl/day or more and treatment Geothermal: 7,500 kw or more capacity after expansion of 100 kl/day or more Nuclear: All [Facility renewal] (1) Treatment capacity of new facility of 100 kl/day or more (excluding [Expansion (excluding projects subject to facility renewal)] projects subject to (2)) Thermal: Output increase of 56,250 kw or more and total output (2) Treatment capacity increase of 50 kl/day or more and treatment after expansion of 112,500 kw or more capacity after facility renewal of 100 t/day or more Hydraulic: Output increase of 11,250 kw or more and total output Construction or Land final disposal sites: after expansion of 22,500 kw or more modification of [Construction] Landfill area of 1 ha or more or landfill capacity of 50,000 m3 or more Geothermal: Output increase of 3,750 kw or more and total output after waste disposal (for specified hazardous industrial waste, landfill area of 1,000 m2 expansion of 7,500 kw or more 10. or more) Construction or Nuclear: All and treatment [Expansion] Landfill area increase of 5,000 m2 or more and area after expansion of modification of [Facility renewal] Thermal: (1) Output of new facility: 112.500 kw or more (excluding facilities 1 ha or more; or landfill capacity increase of 25,000 m3 and capacity projects subject to (2)) after expansion of 50,000 m3 or more (for specified hazardous 5. power plants or (2) Output increase of 56,250 kw or more and total output industrial waste, landfill area increase of 500 m2 or more and area after power transmission after expansion of 112,500 kw or more expansion of 1,000 m2 or more) Hydraulic: (1) Output of new facility: 22,500 kw or more (excluding line projects subject to (2)) Industrial waste intermediate treatment facility: [Construction] (1) Lot area of 9,000 m2 or more (2) Output increase of 11,250 kw or more and total output 2 after expansion of 22,500 kw or more (2) Building area of 3,000 m or more [Expansion (excluding projects subject to facility renewal)] Geothermal: (1) Output of new facility: 7,500 kw or more (excluding 2 projects subject to (2)) (1) Lot area increase of 4,500 m or more and area after expansion of 9,000 m2 or more (2) Output increase of 3,750 kw or more and total output 2 after expansion of 7,500 kw (2) Building area increase of 1,500 m or more and building area after expansion of 3,000 m2 or more Power transmission line: [Facility renewal] (1) Removal of the whole existing facility and lot area for new 1 2 [Construction, extension, pressure increase, relocation , facility renewal ] intermediate treatment facility of 9,000 m2 or more 170,000 v or more and 1 km or longer (2) Partial removal of the existing facility, lot area increase of 4,500 m2 1. Only when relocation of a steel tower is involved. or more and lot area after facility renewal of 9,000 m2 or more 2. Only when removal of a steel tower is involved. (3) Building area of new facility of 3,000 m2 or more (excluding projects subject to (4)) (4) Building area increase of 1,500 m2 or more and building area after facility renewal of 3,000 m2 or more Construction or [Construction] Production capacity of 1.5 million Nm3/day or more [Expansion] Capacity increase of 750,000 Nm3/day or greater and production 6. modification of 3 capacity of 1.5 million Nm /day or more Landfill or Landfill or reclamation land area of 15 ha or more Landfill or reclamation land area of 30 ha or more gas works 11. reclamation

Mooring wharfs with 15 m or deeper water depth and 480 m or Petroleum pipelines: Construction of Mooring wharfs with 12 m or deeper water depth and 240 m or longer in extension [Construction] Conduit pipe of 15 km or longer (excluding buried portions) 12. wharfs longer in extension [Expansion] Extension of 7.5 km or longer and the total length of the pipeline after extension work of 15 km or longer Construction or Construction of Complexes with 1,500 houses or more Complexes with 3,000 houses or more Oil storage facilities: 13. housing complexes modification of [Construction] Storage capacity of 30,000 kl or more [Expansion (excluding projects subject to facility renewal)] petroleum [Construction] Structures with a height of more than 100 m (including stair halls, 7. Storage capacity increase of 15,000 kl or more and a total storage elevator towers, etc.) and with a gross floor area of more than pipelines or oil capacity after expansion of 30,000 kl or more 100,000 m2 (including parking lot areas)* storage facilities [Facility renewal] (1) Storage capacity of new facility: 30,000 kl or more (excluding Construction of [Facility renewal] New structure with a height of more than 100 m (including stair halls, projects subject to (2)) high-rise 14. elevator towers, etc.) and with a gross floor area of more than (2) Storage capacity increase of 15,000 kl or more and a total storage structures 100,000 m2 (including parking lot areas)* capacity after facility renewal of 30,000 kl or more * For specified areas, structures with a height of more than 180 m and with a gross floor area of more than 150,000 m2

3 4 Types and requirements for relevant projects The table below shows types and requirements of relevant projects (Environmental Assessment Procedure for project) and individual plans and individual plans (Environmental Assessment Procedure for planning) required by the Ordinance.

Outline of requirements for a relevant project Outline of requirements for an Outline of requirements for a relevant project Outline of requirements for an Type of project Type of project (description and size) individual plan (description and size) (description and size) individual plan (description and size)

National expressway or motor highway: Factories or facilities associated with manufacturing*: Factories or facilities associated with manufacturing*: [Construction] (1) Lot area of 9,000 m2 or larger [Construction] (1) Lot area of 18,000 m2 or larger [Construction] All (2) Building area of 3,000 m2 or larger (2) Building area of 6,000 m2 or larger [Renovation] (1) Additional lanes [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] (2) New road construction (1) Lot area increase of 4,500 m2 or larger and lot area after expansion (1) Lot area increase of 9,000 m2 or larger and lot (3) Relocation to underground, elevated or other locations 1 km or of 9,000 m2 or larger area after expansion of 18,000 m2 or larger (4) Renewal of facilities for elevated roads or bridges 1 longer (2) Building area increase of 1,500 m2 or larger and building area after (2) Building area increase of 3,000 m2 or larger and (only when removal of bridge pier, abutment or Construction or expansion of 3,000 m2 or larger floor space after expansion of 6,000 m2 or larger beam is involved) 1. renovation of roads Construction or [Facility renewal] (1) Removal of the whole existing facility and lot area of new factory of [Facility renewal] (1) Removal of the whole existing facility and lot Other types of roads (with 4 or more lanes): 9,000 or larger area of new factory of 18,000 or larger 1 modification of [Construction] 1 km or longer Other types of roads (with 4 or more lanes): 8. (2) Partial removal of the existing facility, lot area increase of 4,500 m2 (2) Partial removal of the existing facility, lot area [Renovation (addition of lanes, etc.)] 1 km or longer1, 2 [Construction] 2 km or longer manufacturing 2 2 2 or larger and lot area after facility renewal of 9,000 m or larger increase of 9,000 m or larger and lot area after 1. Even when the length to be constructed or renovated is less than 1 km, if the work is conducted as a part of, [Renovation (addition of lanes, etc.)] 2 km or longer factories (3) Building area of new facility of 3,000 m2 or larger (excluding facility renewal of 18,000 m2 or larger or as an extension to, a relevant project, it shall be subject to the procedure. 2. Renovation of other roads extended to 4 or more lanes should be projects subject to (4)) (3) Building area of new facility of 6,000 m2 or 2. Renovation of other roads extended to 4 or more lanes should be included. included. (4) Building area increase of 1,500 m2 or larger and total building area larger (excluding projects subject to (4)) after facility renewal of 3,000 m2 (4) Building area increase of 3,000 m2 or larger and 2 * Those owning facilities generating smoke or facilities generating ordinary and specified particulates total building area after facility renewal of 6,000 m Dam: designated in the Air Pollution Control Act, or those owning specified facilities designated in the Water * Those owning facilities generating smoke or facilities generating ordinary and Pollution Prevention Act, Noise Regulation Act or Vibration Regulation Act. specified particulates designated in the Air Pollution Control Act, or those [Construction] Height of 15 m or more and surface area of 75 ha or more owning specified facilities designated in the Water Pollution Prevention Act, Weirs: Noise Regulation Act or Vibration Regulation Act. Construction or [Construction] Surface area of 75 ha or more renovation of [Renovation] Surface area increase of 37.5 ha or more and surface area of 75 ha or [Construction] (1) Lot area of 5 ha or larger [Construction] (1) Lot area of 10 ha or larger dams, lake water more after renovation (2) Sludge treatment capacity (in solid material) of 100 t/day or greater (2) Sludge treatment capacity (in solid material) of 2. level control Lake water level control facilities: [Expansion (excluding projects subject to facility renewal)] 200 t/day or greater [Construction] The total area of land for installing the facility and the maximum horizontal (1) Lot area increase of 2.5 ha or larger and lot area after expansion of [Expansion (excluding projects subject to facility renewal)] facilities, discharge project area of the bottom is 75 ha or larger. 5 ha or larger (1) Lot area increase of 5 ha or larger and lot area channels or weirs Discharge channel: Discharge channel: (2) Sludge treatment capacity increase of 50 t/day or greater and after expansion of 10 ha or larger sludge treatment capacity after expansion of 100 t/day or greater (2) Sludge treatment capacity increase of 100 t/day [Construction] A river area with a width of 30 m or wider and a length of 1 km or longer; [Construction] A river area with a width of 30 m or wider [Facility renewal] (1) Removal of the whole existing facility and lot area of new sewage or greater and sludge treatment capacity after or a project that entails a change in the figuration of land of 75 ha or more and a length of 2 km or longer Construction or treatment plant of 5 ha or larger expansion of 200 t/day or greater modification of (2) Partial removal of the existing facility, lot area increase of 2.5 ha or [Facility renewal] (1) Removal of the whole existing facility and lot area 9. sewerage larger and lot area after facility renewal of 5 ha or larger of new sewage treatment plant of 10 ha or larger Railways, transport vehicle guideways and monorail track: Railways, transport vehicle guideways and treatment plants (3) Construction area of new facility of 5 ha or larger (2) Partial removal of the existing facility, lot area [Construction] All monorail tracks: (4) Sludge treatment capacity of new facility of 100 t/day or greater increase of 5 ha or larger and lot area after (excluding projects subject to (5)) facility renewal of 10 ha or larger [Renovation] (1) Addition of rail tracks [Construction] All projects excluding Shinkansen railways Construction or (5) Sludge treatment capacity increase of 50 t/day or greater and (3) Construction area of new facility of 10 ha or larger (2) Relocation to underground and to elevated lines, [Renovation] 2 km or longer (Addition of rail tracks, etc.) renovation of sludge treatment capacity after facility renewal of 100 t/day (4) Sludge treatment capacity of new facility of 200 t/day other forms of relocation 1 km or (Excluding renovation relating to or greater or greater (excluding projects subject to (5)) 3. railways, transport (3) Renewal of rail tracks or bridges on an elevated line or longer* Shinkansen railways.) bridge piers (only when removal of bridge pier, (5) Sludge treatment capacity increase of 100 t/day vehicle guideways or greater and sludge treatment capacity after and monorail tracks abutment or beam is involved) * Even when the length of the extension to be renovated is less than 1 km, if the work will be conducted as a facility renewal of 200 t/day or greater part of, or as an extension to, a relevant project, it is subject to the procedure. Garbage-disposal facilities: [Construction] Treatment capacities of each type of disposal facilities is 200 t/day or more Land airports, etc. and heliports: [Expansion (excluding projects subject to facility renewal)] Land airports, etc. and heliports: Treatment capacity increases of each type of disposal facilities is 100 t/day [Construction] All Construction or [Construction] All or more, and disposal capacity after expansion of 200 t/day or more [Facility renewal] All (only when all existing facilities are [Facility renewal] All (only when all existing facilities are removed) [Facility renewal] (1) Treatment capacities of each type of new disposal facilities is 4. modification of removed) airports/airstrips Airstrips: 200 t/day or more (excluding projects subject to (2)) [Construction and change of location] All Airstrips: (2) Treatment capacity increases of each type of disposal facilities is [Extension] Projects involving change of class, etc. [Construction and change of location] All 100 t/day or more, and disposal capacity after facility renewal of 200 t/day or more Night soil disposal plants: Power plants: [Construction] Treatment capacity of 100 kl/day or more [Construction] Thermal: 112, 500 kw or more [Expansion (excluding projects subject to facility renewal)] Hydraulic: 22,500 kw or more Treatment capacity increase of 50 kl/day or more and treatment Geothermal: 7,500 kw or more capacity after expansion of 100 kl/day or more Nuclear: All [Facility renewal] (1) Treatment capacity of new facility of 100 kl/day or more (excluding [Expansion (excluding projects subject to facility renewal)] projects subject to (2)) Thermal: Output increase of 56,250 kw or more and total output (2) Treatment capacity increase of 50 kl/day or more and treatment after expansion of 112,500 kw or more capacity after facility renewal of 100 t/day or more Hydraulic: Output increase of 11,250 kw or more and total output Construction or Land final disposal sites: after expansion of 22,500 kw or more modification of [Construction] Landfill area of 1 ha or more or landfill capacity of 50,000 m3 or more Geothermal: Output increase of 3,750 kw or more and total output after waste disposal (for specified hazardous industrial waste, landfill area of 1,000 m2 expansion of 7,500 kw or more 10. or more) Construction or Nuclear: All and treatment [Expansion] Landfill area increase of 5,000 m2 or more and area after expansion of modification of [Facility renewal] Thermal: (1) Output of new facility: 112.500 kw or more (excluding facilities 1 ha or more; or landfill capacity increase of 25,000 m3 and capacity projects subject to (2)) after expansion of 50,000 m3 or more (for specified hazardous 5. power plants or (2) Output increase of 56,250 kw or more and total output industrial waste, landfill area increase of 500 m2 or more and area after power transmission after expansion of 112,500 kw or more expansion of 1,000 m2 or more) Hydraulic: (1) Output of new facility: 22,500 kw or more (excluding line projects subject to (2)) Industrial waste intermediate treatment facility: [Construction] (1) Lot area of 9,000 m2 or more (2) Output increase of 11,250 kw or more and total output 2 after expansion of 22,500 kw or more (2) Building area of 3,000 m or more [Expansion (excluding projects subject to facility renewal)] Geothermal: (1) Output of new facility: 7,500 kw or more (excluding 2 projects subject to (2)) (1) Lot area increase of 4,500 m or more and area after expansion of 9,000 m2 or more (2) Output increase of 3,750 kw or more and total output 2 after expansion of 7,500 kw (2) Building area increase of 1,500 m or more and building area after expansion of 3,000 m2 or more Power transmission line: [Facility renewal] (1) Removal of the whole existing facility and lot area for new 1 2 [Construction, extension, pressure increase, relocation , facility renewal ] intermediate treatment facility of 9,000 m2 or more 170,000 v or more and 1 km or longer (2) Partial removal of the existing facility, lot area increase of 4,500 m2 1. Only when relocation of a steel tower is involved. or more and lot area after facility renewal of 9,000 m2 or more 2. Only when removal of a steel tower is involved. (3) Building area of new facility of 3,000 m2 or more (excluding projects subject to (4)) (4) Building area increase of 1,500 m2 or more and building area after facility renewal of 3,000 m2 or more Construction or [Construction] Production capacity of 1.5 million Nm3/day or more [Expansion] Capacity increase of 750,000 Nm3/day or greater and production 6. modification of 3 capacity of 1.5 million Nm /day or more Landfill or Landfill or reclamation land area of 15 ha or more Landfill or reclamation land area of 30 ha or more gas works 11. reclamation

Mooring wharfs with 15 m or deeper water depth and 480 m or Petroleum pipelines: Construction of Mooring wharfs with 12 m or deeper water depth and 240 m or longer in extension [Construction] Conduit pipe of 15 km or longer (excluding buried portions) 12. wharfs longer in extension [Expansion] Extension of 7.5 km or longer and the total length of the pipeline after extension work of 15 km or longer Construction or Construction of Complexes with 1,500 houses or more Complexes with 3,000 houses or more Oil storage facilities: 13. housing complexes modification of [Construction] Storage capacity of 30,000 kl or more [Expansion (excluding projects subject to facility renewal)] petroleum [Construction] Structures with a height of more than 100 m (including stair halls, 7. Storage capacity increase of 15,000 kl or more and a total storage elevator towers, etc.) and with a gross floor area of more than pipelines or oil capacity after expansion of 30,000 kl or more 100,000 m2 (including parking lot areas)* storage facilities [Facility renewal] (1) Storage capacity of new facility: 30,000 kl or more (excluding Construction of [Facility renewal] New structure with a height of more than 100 m (including stair halls, projects subject to (2)) high-rise 14. elevator towers, etc.) and with a gross floor area of more than (2) Storage capacity increase of 15,000 kl or more and a total storage structures 100,000 m2 (including parking lot areas)* capacity after facility renewal of 30,000 kl or more * For specified areas, structures with a height of more than 180 m and with a gross floor area of more than 150,000 m2

3 4 Areas whose urban functions will be enhanced, with a comfortable environment ensured (specified areas)

Outline of requirements for a relevant project Outline of requirements for an Type of project Ikebukuro (description and size) individual plan (description and size) Station Off-street parking lots (excluding temporary parking lots): Off-street parking lots: (excluding temporary parking lots): Ueno Station [Construction] Simultaneous parking capacity of 1,000 spaces or more (excluding [Construction] Simultaneous parking capacity of 2,000 spaces or more spaces for residents of houses) (excluding spaces for residents of houses) Kinshicho [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] Station Parking capacity increase of 500 spaces or more and parking Parking capacity increase of 1,000 spaces or more and Construction or capacity after expansion of 1,000 spaces or more (excluding spaces parking capacity after expansion of 2,000 spaces or more 15. modification of for residents of houses) (excluding spaces for residents of houses) Station parking lots [Facility renewal] (1) Parking capacity of new parking lots of 1,000 spaces or more [Facility renewal] (1) Parking capacity of new parking lots of 2,000 spaces Tokyo (excluding spaces for residents of houses) (excluding projects or more (excluding spaces for residents of houses) Station subject to (2)) (excluding projects subject to (2)) (2) Parking capacity increase of 500 spaces or more and parking (2) Parking capacity increase of 1,000 spaces or more and capacity after facility renewal of 1,000 spaces or more (excluding parking capacity after facility renewal of 2,000 spaces spaces for residents of houses) or more (excluding spaces for residents of houses) [Construction] Lot area of 10 ha or more [Construction] Lot area of 20 ha or more Station [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] Lot area increase of 5 ha or more and lot area after expansion of 10 ha Lot area increase of 10 ha or more and lot area after Construction or or more expansion of 20 ha or more [Facility renewal] (1) Removal of the whole existing facility and lot area of new wholesale [Facility renewal] (1) Removal of the whole existing facility and lot area of 16. modification of market of 10 ha or more new wholesale market of 20 ha or more wholesale markets (2) Partial removal of the existing facility, lot area increase of 5 ha or (2) Partial removal of the existing facility, lot area increase more and lot area after facility renewal of 10 ha or more of 10 ha or more and lot area after facility renewal of (3) Construction area of new facility of 10 ha or more 20 ha or more Osaki Station (3) Construction area of new facility of 20 ha or more Development of 17. distribution facility All All complex

Land adjustment Project land area of 40 ha or more (20 ha or more if it includes a forest area with a size of Project land area of 80 ha or more (40 ha or more if it includes 18. projects 15 ha or more) a forest area with a size of 30 ha or more) High-rise apartment building areas Development of new 19. Project land area of 40 ha or more Areas speci ed in Article 51.2 of residential areas the regulations Construction or 20. modification of All All industrial parks Urban redevelopment Areas specified in Article 51.2 of the regulations 21. Project land area of 20 ha or more Project land area of 40 ha or more project Municipality Area Urban infrastructure 22. development projects All All Uchikanda 1–3 chome, Uchisaiwaicho 1–2 chome, Otemachi 1–2 chome, Kajicho 1–2 chome, Kasumigaseki 1–3 chome, Kanda-aioicho, Kanda-awajicho 1–2 chome, Kanda-iwamotocho, Kanda-ogawamachi 1–3 chome, Development of 23. Project land area of 20 ha or more Project land area of 40 ha or more Kanda-kajicho 3 chome, Kanda-kitanorimonocho, Kanda-konyacho, Kanda-sakumacho 1 chome, Kanda-sudacho 1–2 residential area Chiyoda Ward chome, Kanda-surugadai 1–4 chome, Kanda-tacho 2 chome, Kanda-tsukasamachi 2 chome, Kanda-tomiyamacho, [Construction] Project land area of 40 ha or more (20 ha or more if it includes forest [Construction] Project land area of 80 ha or more (40 ha or more if it Kanda-nishikicho 1–3 chome, Kanda-nishifukudacho, Kanda-neribeicho, Kanda-hanaokacho, Kanda-higashikonyacho, land of 15 ha or more) includes forest land of 30 ha or more) Kanda-higashimatsushitacho, Kanda-matsunagacho, Kanda-mikuracho, Kanda-mitoshirocho, Sotokanda 1 and 3–6 [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] Construction or Project land area increase of 20 ha or more and land area after Project land area increase of 40 ha or more and land area chome, Nagatacho 1–2 chome, Hibiyakoen, Marunouchi 1–3 chome, Yurakucho 1–2 chome modification of expansion of 40 ha or more (project land area increase of 10 ha or after expansion of 80 ha or more (project land area increase of structures, such as more if it includes forest land of 7.5 more or more) 20 ha or more if it includes forest land of 15 more or more) Akashicho, Irifune 1–3 chome, Kachidoki 1-6 chome, Kyobashi 1–3 chome, Ginza 1–8 chome, Shintomi 1–2 [Facility renewal] (1) New project land area for structures, such as baseball fields, track [Facility renewal] (1) New project land area for structures, such as baseball chome, Tsukiji 1–7 chome, Tsukishima 1–4 chome, Tsukuda 1–3 chome, Toyomicho, Nihonbashi 1–3 chome, 24. baseball fields, and field stadiums, amusement parks, cemeteries, etc. of 40 ha or fields, track and field stadiums, amusement parks, track and field more (20 ha or more if it includes forest land of 15 ha or more) cemeteries, etc. of 80 ha or more (40 ha or more if it Chuo Ward Nihonbashi-kabutocho, Nihonbashi-kayabacho 1-3 chome, Nihonbashi-koamicho, Nihonbashi-hongokucho 1–4 stadiums, (excluding projects subject to (2)) includes forest land of 30 ha or more) (excluding (2) Project land area increase of 20 ha or more and land area after projects subject to (2)) chome, Nihonbashi-honcho 1–4 chome, Nihonbashi-muromachi 1–4 chome, Hacchobori 1-4 chome, Harumi 1–5 amusement parks, facility renewal of 40 ha or more (project land area increase of 10 (2) Project land area increase of 40 ha or more and land chome, Minato 1–3 chome, Yaesu 1–2 chome cemeteries, etc. ha or more if it includes forest land of 7.5 ha or more) area after facility renewal of 80 ha or more (project land area increase of 20 ha or more if it includes forest land of 15 ha or more) Akasaka 1–9 chome, Azabujuban 1 chome, Azabudai 1–3 chome, Azabu-nagasakacho, Azabu-mamianacho, Atago 1–2 chome, Kaigan 1 chome, Konan 1–2 chome, Shiba 4–5 chome, Shibaura 1 and 3–4 chome, Shibakoen Other development Minato Ward 1–4 chome, Shibadaimon 1–2 chome, Shinbashi 1–6 chome, Daiba 1–2 chome, Takanawa 2–4 chome, of land for Project land area of 40 ha or more (20 ha or more, if it includes forest land of 15 ha or more) Project land area of 80 ha or more (40 ha or more if it includes Toranomon 1–5 chome, Nishishinbashi 1–3 chome, Hamamatsucho 1–2 chome, Higashiazabu 1–3 chome, 25. forest land of 30 ha or more) architectural Higashishinbashi 1–2 chome, Mita 3–4 chome, Minamiaoyama 1 chome, Roppongi 1–7 chome structures Shinjuku Ward Kabukicho 1–2 chome, Kitashinjuku 1–2 chome, Shinjuku 3–6 chome, Naitomachi, Nishishinjuku 1–3 and 5–8 chome 26. Quarrying or mining Project land area of 10 ha or more Bunkyo Ward Yushima 3 chome In the revision of the ordinance in 2018, “facility renewal” was newly defined and the requirements with the project size and other requirements Akihabara, Asakusa 1–2 chome, Ueno 1–7 chome, Kaminarimon 1–2 chome, Kitaueno 1–2 chome, Kuramae 2–4 are clarified. The definition of “facility renewal” is stipulated in the Tokyo Metropolitan Environmental Impact Assessment Ordinance and the chome, Kojima 2 chome, Kotobuki 1–4 chome, Komagata 1–2 chome, Taito 4 chome, Nishiasakusa 1–3 chome, Regulations for Enforcement of the Tokyo Metropolitan Environmental Impact Assessment Ordinance as follow: Taito Ward Hanakawado 1–2 chome, Higashiueno 1–6 chome, Matsugaya 1–3 chome, Misuji 2 chome, Motoasakusa 1–4 chome ■ Notes on the Appendix of the Ordinance (excerpt) An act to remove the whole or part of an existing facility (building, structure, or another type of facility) and simultaneously construct a new facility that serves the Sumida Ward Kinshi 1–4 chome, Kotobashi 1–4 chome, Taihei 1–4 chome same purposes as the existing facility in the same lot. ■ Notes for Table 1 in the Appendix of the Regulation (excerpt) Koto Ward Aomi 1–2 chome, Ariake 1–3 chome, Kameido 1–2 and 4–8 chome, Shinonome 1–2 chome, Toyosu 1–6 chome, 1. “Facility renewal” does not include construction conducted for the purpose of conservation, such as repair work, nor any acts that are otherwise specified by publicly-owned water body ahead of Ariake 1 chome area the governor. 2. “Facility renewal” includes an act where only a part of the lot for the new facility exists in the area of the lot of the existing facility. Ward Osaki 1–5 chome, Kitashinagawa 1 and 4–6 chome, Nishigotanda 1–2 and 6–8 chome, 1–5 3. “A new facility that serves the same purpose as the existing facility” is referred to a new facility that is to be constructed to serve for the facility involved in the chome, Higashiyashio relevant project as before the facility renewal. Ota Ward Hanedakuko 1-2 chome Requirements for wide-area complex development projects Uguisudanicho, Udagawacho, Kamiyamacho, Sakuragaokacho, Sarugakucho, Shibuya1–4 chome, Shoto 1 Shibuya Ward Requirements for a multiple development plan for large area (Environmental Assessment Procedure for planning) covered by chome, Shinsencho, Jingumae 5–6 chome, Jinnan 1 chome, Sendagaya 5–6 chome, Daikanyamacho, Dogenzaka 1–2 chome, Nanpeidaicho, Higashi 1 chome, Honmachi 1 chome, Maruyamacho, Yoyogi 1–3 chome the Ordinance are as follows: 1. Area: 30 ha or over Ikebukuro 1–2 chome, Kamiikebukuro 2 chome, Nishiikebukuro 1–3 and 5 chome, Higashiikebukuro 1–5 chome, Toshima Ward Minamiikebukuro 1–3 chome 2. Projects (regardless of their scale) subject to more than one ordinance are planned 3. Projects that specify area, scale, population plan and land-use plans by use The specified areas do not constitute all areas of the above-listed blocks. The specified areas have been notified by maps. Please refer to the website of the Bureau of the Environment for details.

5 6 Areas whose urban functions will be enhanced, with a comfortable environment ensured (specified areas)

Outline of requirements for a relevant project Outline of requirements for an Type of project Ikebukuro (description and size) individual plan (description and size) Station Off-street parking lots (excluding temporary parking lots): Off-street parking lots: (excluding temporary parking lots): Ueno Station [Construction] Simultaneous parking capacity of 1,000 spaces or more (excluding [Construction] Simultaneous parking capacity of 2,000 spaces or more spaces for residents of houses) (excluding spaces for residents of houses) Kinshicho [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] Station Parking capacity increase of 500 spaces or more and parking Parking capacity increase of 1,000 spaces or more and Construction or capacity after expansion of 1,000 spaces or more (excluding spaces parking capacity after expansion of 2,000 spaces or more Shinjuku 15. modification of for residents of houses) (excluding spaces for residents of houses) Station parking lots [Facility renewal] (1) Parking capacity of new parking lots of 1,000 spaces or more [Facility renewal] (1) Parking capacity of new parking lots of 2,000 spaces Tokyo (excluding spaces for residents of houses) (excluding projects or more (excluding spaces for residents of houses) Station subject to (2)) (excluding projects subject to (2)) (2) Parking capacity increase of 500 spaces or more and parking (2) Parking capacity increase of 1,000 spaces or more and capacity after facility renewal of 1,000 spaces or more (excluding parking capacity after facility renewal of 2,000 spaces spaces for residents of houses) or more (excluding spaces for residents of houses) Shibuya [Construction] Lot area of 10 ha or more [Construction] Lot area of 20 ha or more Station [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] Lot area increase of 5 ha or more and lot area after expansion of 10 ha Lot area increase of 10 ha or more and lot area after Construction or or more expansion of 20 ha or more [Facility renewal] (1) Removal of the whole existing facility and lot area of new wholesale [Facility renewal] (1) Removal of the whole existing facility and lot area of 16. modification of market of 10 ha or more new wholesale market of 20 ha or more wholesale markets (2) Partial removal of the existing facility, lot area increase of 5 ha or (2) Partial removal of the existing facility, lot area increase more and lot area after facility renewal of 10 ha or more of 10 ha or more and lot area after facility renewal of (3) Construction area of new facility of 10 ha or more 20 ha or more Osaki Station (3) Construction area of new facility of 20 ha or more Development of 17. distribution facility All All complex

Land adjustment Project land area of 40 ha or more (20 ha or more if it includes a forest area with a size of Project land area of 80 ha or more (40 ha or more if it includes 18. projects 15 ha or more) a forest area with a size of 30 ha or more) High-rise apartment building areas Development of new 19. Project land area of 40 ha or more Areas speci ed in Article 51.2 of residential areas the regulations Construction or 20. modification of All All industrial parks Urban redevelopment Areas specified in Article 51.2 of the regulations 21. Project land area of 20 ha or more Project land area of 40 ha or more project Municipality Area Urban infrastructure 22. development projects All All Uchikanda 1–3 chome, Uchisaiwaicho 1–2 chome, Otemachi 1–2 chome, Kajicho 1–2 chome, Kasumigaseki 1–3 chome, Kanda-aioicho, Kanda-awajicho 1–2 chome, Kanda-iwamotocho, Kanda-ogawamachi 1–3 chome, Development of 23. Project land area of 20 ha or more Project land area of 40 ha or more Kanda-kajicho 3 chome, Kanda-kitanorimonocho, Kanda-konyacho, Kanda-sakumacho 1 chome, Kanda-sudacho 1–2 residential area Chiyoda Ward chome, Kanda-surugadai 1–4 chome, Kanda-tacho 2 chome, Kanda-tsukasamachi 2 chome, Kanda-tomiyamacho, [Construction] Project land area of 40 ha or more (20 ha or more if it includes forest [Construction] Project land area of 80 ha or more (40 ha or more if it Kanda-nishikicho 1–3 chome, Kanda-nishifukudacho, Kanda-neribeicho, Kanda-hanaokacho, Kanda-higashikonyacho, land of 15 ha or more) includes forest land of 30 ha or more) Kanda-higashimatsushitacho, Kanda-matsunagacho, Kanda-mikuracho, Kanda-mitoshirocho, Sotokanda 1 and 3–6 [Expansion (excluding projects subject to facility renewal)] [Expansion (excluding projects subject to facility renewal)] Construction or Project land area increase of 20 ha or more and land area after Project land area increase of 40 ha or more and land area chome, Nagatacho 1–2 chome, Hibiyakoen, Marunouchi 1–3 chome, Yurakucho 1–2 chome modification of expansion of 40 ha or more (project land area increase of 10 ha or after expansion of 80 ha or more (project land area increase of structures, such as more if it includes forest land of 7.5 more or more) 20 ha or more if it includes forest land of 15 more or more) Akashicho, Irifune 1–3 chome, Kachidoki 1-6 chome, Kyobashi 1–3 chome, Ginza 1–8 chome, Shintomi 1–2 [Facility renewal] (1) New project land area for structures, such as baseball fields, track [Facility renewal] (1) New project land area for structures, such as baseball chome, Tsukiji 1–7 chome, Tsukishima 1–4 chome, Tsukuda 1–3 chome, Toyomicho, Nihonbashi 1–3 chome, 24. baseball fields, and field stadiums, amusement parks, cemeteries, etc. of 40 ha or fields, track and field stadiums, amusement parks, track and field more (20 ha or more if it includes forest land of 15 ha or more) cemeteries, etc. of 80 ha or more (40 ha or more if it Chuo Ward Nihonbashi-kabutocho, Nihonbashi-kayabacho 1-3 chome, Nihonbashi-koamicho, Nihonbashi-hongokucho 1–4 stadiums, (excluding projects subject to (2)) includes forest land of 30 ha or more) (excluding (2) Project land area increase of 20 ha or more and land area after projects subject to (2)) chome, Nihonbashi-honcho 1–4 chome, Nihonbashi-muromachi 1–4 chome, Hacchobori 1-4 chome, Harumi 1–5 amusement parks, facility renewal of 40 ha or more (project land area increase of 10 (2) Project land area increase of 40 ha or more and land chome, Minato 1–3 chome, Yaesu 1–2 chome cemeteries, etc. ha or more if it includes forest land of 7.5 ha or more) area after facility renewal of 80 ha or more (project land area increase of 20 ha or more if it includes forest land of 15 ha or more) Akasaka 1–9 chome, Azabujuban 1 chome, Azabudai 1–3 chome, Azabu-nagasakacho, Azabu-mamianacho, Atago 1–2 chome, Kaigan 1 chome, Konan 1–2 chome, Shiba 4–5 chome, Shibaura 1 and 3–4 chome, Shibakoen Other development Minato Ward 1–4 chome, Shibadaimon 1–2 chome, Shinbashi 1–6 chome, Daiba 1–2 chome, Takanawa 2–4 chome, of land for Project land area of 40 ha or more (20 ha or more, if it includes forest land of 15 ha or more) Project land area of 80 ha or more (40 ha or more if it includes Toranomon 1–5 chome, Nishishinbashi 1–3 chome, Hamamatsucho 1–2 chome, Higashiazabu 1–3 chome, 25. forest land of 30 ha or more) architectural Higashishinbashi 1–2 chome, Mita 3–4 chome, Minamiaoyama 1 chome, Roppongi 1–7 chome structures Shinjuku Ward Kabukicho 1–2 chome, Kitashinjuku 1–2 chome, Shinjuku 3–6 chome, Naitomachi, Nishishinjuku 1–3 and 5–8 chome 26. Quarrying or mining Project land area of 10 ha or more Bunkyo Ward Yushima 3 chome In the revision of the ordinance in 2018, “facility renewal” was newly defined and the requirements with the project size and other requirements Akihabara, Asakusa 1–2 chome, Ueno 1–7 chome, Kaminarimon 1–2 chome, Kitaueno 1–2 chome, Kuramae 2–4 are clarified. The definition of “facility renewal” is stipulated in the Tokyo Metropolitan Environmental Impact Assessment Ordinance and the chome, Kojima 2 chome, Kotobuki 1–4 chome, Komagata 1–2 chome, Taito 4 chome, Nishiasakusa 1–3 chome, Regulations for Enforcement of the Tokyo Metropolitan Environmental Impact Assessment Ordinance as follow: Taito Ward Hanakawado 1–2 chome, Higashiueno 1–6 chome, Matsugaya 1–3 chome, Misuji 2 chome, Motoasakusa 1–4 chome ■ Notes on the Appendix of the Ordinance (excerpt) An act to remove the whole or part of an existing facility (building, structure, or another type of facility) and simultaneously construct a new facility that serves the Sumida Ward Kinshi 1–4 chome, Kotobashi 1–4 chome, Taihei 1–4 chome same purposes as the existing facility in the same lot. ■ Notes for Table 1 in the Appendix of the Regulation (excerpt) Koto Ward Aomi 1–2 chome, Ariake 1–3 chome, Kameido 1–2 and 4–8 chome, Shinonome 1–2 chome, Toyosu 1–6 chome, 1. “Facility renewal” does not include construction conducted for the purpose of conservation, such as repair work, nor any acts that are otherwise specified by publicly-owned water body ahead of Ariake 1 chome area the governor. 2. “Facility renewal” includes an act where only a part of the lot for the new facility exists in the area of the lot of the existing facility. Shinagawa Ward Osaki 1–5 chome, Kitashinagawa 1 and 4–6 chome, Nishigotanda 1–2 and 6–8 chome, Higashigotanda 1–5 3. “A new facility that serves the same purpose as the existing facility” is referred to a new facility that is to be constructed to serve for the facility involved in the chome, Higashiyashio relevant project as before the facility renewal. Ota Ward Hanedakuko 1-2 chome Requirements for wide-area complex development projects Uguisudanicho, Udagawacho, Kamiyamacho, Sakuragaokacho, Sarugakucho, Shibuya1–4 chome, Shoto 1 Shibuya Ward Requirements for a multiple development plan for large area (Environmental Assessment Procedure for planning) covered by chome, Shinsencho, Jingumae 5–6 chome, Jinnan 1 chome, Sendagaya 5–6 chome, Daikanyamacho, Dogenzaka 1–2 chome, Nanpeidaicho, Higashi 1 chome, Honmachi 1 chome, Maruyamacho, Yoyogi 1–3 chome the Ordinance are as follows: 1. Area: 30 ha or over Ikebukuro 1–2 chome, Kamiikebukuro 2 chome, Nishiikebukuro 1–3 and 5 chome, Higashiikebukuro 1–5 chome, Toshima Ward Minamiikebukuro 1–3 chome 2. Projects (regardless of their scale) subject to more than one ordinance are planned 3. Projects that specify area, scale, population plan and land-use plans by use The specified areas do not constitute all areas of the above-listed blocks. The specified areas have been notified by maps. Please refer to the website of the Bureau of the Environment for details.

5 6 (Basic) Project Process and Environmental Impact Reference: Assessment System Procedures Concerning Projects Governed by the Law

(In case of TMG project) Environmental Assessment Environmental Impact Procedures stipulated in the procedure for planning Assessment Law ordinance for projects subject Multiple plans to the law (relevant project) Environmental Impact Statement for Planning Governor

Selection of assessment items (for each plan) Publication Council Survey Prediction Assessment (for each plan) Opinions of residents, etc.

Preparation of an environment Opinion of the Governor consideration report Opinions of residents of Tokyo Governor’s examination report Class-1 project Class-2 project (In case of a private sector project) Project Plan Opinion of the Governor Opinions of heads of municipal governments Project Plan Environmental Assessment Relevant project Determination procedure for project Selection of assessment items Environmental assessment scoping document Speci ed areas Preparation of survey plans Public announcement and inspection (1 month) Governor Advice to the Council

Survey of existing conditions Prediction Opinions of residents, etc. Assessment Summary of opinions Opinions of residents Opinions of heads of Preparation of a draft environmental of Tokyo assessment report municipal governments Governor’s examination report Opinion of the Governor Report by the Council Submission of an environmental Determine what methods to be used for assessment report environmental impact assessment Report on selected assessment items and survey methods Project plan decided (Survey, prediction and assessment)

Reect in licensing and approval Draft Environmental Assessment Report Governor Advice to the Council

Implementation of the project Public announcement and inspection (1 month) Follow-up survey procedure Follow-up survey report Explanatory meeting

Opinions of residents, etc. Actions requested to regulatory authorities Outline of opinions and business’s opinion report Opinions of heads of municipal governments

Town hall meeting to hear Assessment items opinions from Tokyo residents

Record of opinions at Opinion of the Governor the town hall meeting

Report by the Council Air pollution Odors Noise and Water Soil vibration pollution pollution Environmental Assessment Report

Opinions of Opinions of authorities issuing Environment permits or approvals Minister Ground Topography Biology and Radio transformation and geology Water cycle ecology Shade disturbance Modi ed Environmental Assessment Report (When necessary)

Public announcement and inspection (1 month)

Historic sites Sites for Wind Greenhouse Landscape and cultural activities in Waste Review for licensing or approvals condition gases assets nature Procedure for follow-up survey Follow-up monitoring (When necessary)

7 8 (Basic) Project Process and Environmental Impact Reference: Assessment System Procedures Concerning Projects Governed by the Law

(In case of TMG project) Environmental Assessment Environmental Impact Procedures stipulated in the procedure for planning Assessment Law ordinance for projects subject Multiple plans to the law (relevant project) Environmental Impact Statement for Planning Governor

Selection of assessment items (for each plan) Publication Council Survey Prediction Assessment (for each plan) Opinions of residents, etc.

Preparation of an environment Opinion of the Governor consideration report Opinions of residents of Tokyo Governor’s examination report Class-1 project Class-2 project (In case of a private sector project) Project Plan Opinion of the Governor Opinions of heads of municipal governments Project Plan Environmental Assessment Relevant project Determination procedure for project Selection of assessment items Environmental assessment scoping document Speci ed areas Preparation of survey plans Public announcement and inspection (1 month) Governor Advice to the Council

Survey of existing conditions Prediction Opinions of residents, etc. Assessment Summary of opinions Opinions of residents Opinions of heads of Preparation of a draft environmental of Tokyo assessment report municipal governments Governor’s examination report Opinion of the Governor Report by the Council Submission of an environmental Determine what methods to be used for assessment report environmental impact assessment Report on selected assessment items and survey methods Project plan decided (Survey, prediction and assessment)

Reect in licensing and approval Draft Environmental Assessment Report Governor Advice to the Council

Implementation of the project Public announcement and inspection (1 month) Follow-up survey procedure Follow-up survey report Explanatory meeting

Opinions of residents, etc. Actions requested to regulatory authorities Outline of opinions and business’s opinion report Opinions of heads of municipal governments

Town hall meeting to hear Assessment items opinions from Tokyo residents

Record of opinions at Opinion of the Governor the town hall meeting

Report by the Council Air pollution Odors Noise and Water Soil vibration pollution pollution Environmental Assessment Report

Opinions of Opinions of authorities issuing Environment permits or approvals Minister Ground Topography Biology and Radio transformation and geology Water cycle ecology Shade disturbance Modi ed Environmental Assessment Report (When necessary)

Public announcement and inspection (1 month)

Historic sites Sites for Wind Greenhouse Landscape and cultural activities in Waste Review for licensing or approvals condition gases assets nature Procedure for follow-up survey Follow-up monitoring (When necessary)